The Issue The issue for consideration in this case concerns whether the Petitioners are entitled to an on-site sewage disposal system ("OSDS") permit authorizing the installation of an OSDS on property which they own near the Suwannee River in Dixie County, Florida, in accordance with the permitting requirements of Section 381.272, Florida Statutes, and Chapter 10D-6, Florida Administrative Code.
Findings Of Fact The Petitioners are the owners of certain real property located in Dixie County, Florida, in the proximity of the Suwannee River. The property is described as Lot 38, Highpoint Suwannee Riverfront Estates. The lot in question is 82 feet by 141 feet in size and was purchased in April, 1988 for approximately $5000.00. The lot, and the subdivision it is in, was platted in 1983. On February 21, 1990, the Petitioners made application for an on-site sewage disposal system ("OSDS") permit, seeking to install such a system on this lot in order to be able to construct a vacation cottage on the lot The proposed cottage would contain one bedroom and would have a heated and cooled area of approximately 500 square feet. Upon reviewing the application, the, Respondent informed the Petitioners that they would need to have a surveyor establish the elevation of their lot, and particularly the site of the proposed OSDS installation, as well as to establish, through contact with the Suwannee River Water Management District, the ten-year flood elevation for the property. Accordingly, the Petitioners obtained a survey by `Mr. Herbert Raker, a registered land surveyor of Cross City, Florida. That survey shows a benchmark elevation of 13.09 feet above mean sea level ("MSL") That benchmark elevation is six inches above the actual grade surface of the lot so that the elevation at the proposed OSDS installation site is 12.59 feet above MSL. The ten-year flood elevation for the property is 15 feet above MSL, as established by data from the Suwannee River Water Management District contained in a report which is in evidence as Respondent's Exhibit 1. That flood elevation data was submitted to the Respondent by the Petitioners with the application for the OSDS permit. The property in question is located within the ten- year flood plain of the Suwannee River, and it is also located within the regulatory floodway of the River. On April 24, 1990, after advising the Petitioners of the denial of the OSDS permit application, the Respondent, by letter, advised the Petitioners that they should pursue a formal administrative proceeding rather than file an informal variance application before the Respondent's own Variance Board. The Respondent took the position that a variance could not be granted from the requirements of Rule 10D- 6.47(6), Florida Administrative Code, because the subject property was located within the ten-year flood plain of the Suwannee River and because of the Respondent's interpretation of the affect of the Governor's Executive Order 90- 14, which adopted by reference the Suwannee River Task Force recommendation that all such systems be prohibited within the ten-year flood plain. The Respondent thus declined to exercise its discretion, accorded it in the statute and rule cited hereinbelow, to entertain and consider a variance application. Finally, it is established that the lot in question is not subject to frequent flooding; but because the surface grade is beneath the ten-year flood elevation, the bottom of the drain field trenches absorption bed to be installed would also be beneath the ten-year flood elevation. In other respects, the property is a amenable to the installation of an effective OSDS because the wet season water table is 48 inches beneath the surface grade and would be more than 24 inches beneath the proposed drain field. The normal water table is approximately 60 inches beneath the surface grade. Appropriate limited soils are present beneath the first six inches of soil below the surface and consist of fine sand, light brown and brown fine sand, down to 60 inches, which is appropriate for effective subterranean treatment and disposal of sewage effluent. The Petitioners established a definite hardship on their part by the fact that they have paid a substantial sum for the lot and are now unable to develop it unless they receive entitlement to an OSDS or some reasonable alternative. In that regard, no sufficient proof of truly effective, reasonable alternatives was established by the Petitioners. However, they did establish that an anaerobic septic tank and drain field disposal system might be an effective alternative treatment and disposal method for the property in question. An aerobic system involves the injection of air into the attendant septic tank to support aerobic bacteria which break down and treat sewage at a faster, more effective rate than does the normal anaerobic bacteria-based system. The resulting effluent is substantially lower in BOD and suspended solids than is the effluent from the normal subterranean and anaerobic septic tank and drain field disposal system. The problem with such an aerobic system is that it involves mechanical equipment, especially, an external electric motor and pump to force air into the system. This is disadvantageous in that, if the equipment suffers a breakdown, then treatment and appropriate disposal of the effluent stops. The untreated sewage can then rise to the surface of the property or otherwise pollute ground or surface waters and potentially cause a public health hazard. Thus, such systems would require inspection periodically to insure that they are in adequate working order because if the mechanical system malfunctions, the system will continue to put effluent through its drain field without adequate treatment. In this circumstance, the occupants of the dwelling served by the system might not notice for long periods of time that it is inoperative because the system will continue to dispose of effluent, but just of an untreated nature. Accordingly, when the motor and air pump system becomes inoperative, there is less incentive for the owner to repair it. Thus, it is likely that if such a system were installed, some means would have to be found to insure that the owner keeps the system in good repair and working order. The means by which such an arrangement for insuring that such an aerobic system works properly at all times was not established in this record, however. Consequently, the Petitioners failed to establish that reasonable alternatives to the proposed conventional system exist and what they might consist of.
Recommendation Having considered the foregoing findings of Fact, Conclusions of Law, the evidence of record, the carndor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is therefore, RECOMMENDED that a Final Order be entered denying the Petitioners' application for an OSDS permit. DONE AND ENTERED this 21st day of December, 1990, in Tallahassee, Leon County, Florida P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of December, 1990. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 90-3112 The Petitioners filed no proposed findings of fact. Respondent's Proposed Findings of Fact: 1-9. Accepted. COPIES FURNISHED: Sam Power, Agency Clerk Department of HRS 1323 Winewood Boulevard Tallahassee, FL 32399-0700 Linda K. Harris, Esquire General Counsel Department of HRS 1323 Winewood Boulevard Tallahassee, FL 32399-0700 Betsy K. Lanier, pro se P.O. Box 238 Old Town, FL 32680 Frances S. Childers, Esq. Assistant District III Legal Counsel Department of HRS 1000 N.E. 16th Avenue Gainesville, FL 32609
The Issue The issues in this case are: Whether Mr. Decker had an improperly maintained septic system on his property. Whether Mr. Decker illegally repaired his on-site sewage treatment and disposal system. Whether the Department of Health properly issued a citation to Mr. Decker for violation of Sections 381.0065(4) and 386.041(1)(b), Florida Statutes.
Findings Of Fact On April 25, 1997, an employee of the Department of Health, Volusia County Health Department, David Stark, inspected Mr. Decker's property known as Bulow Creek Farm. Mr. Decker provides low-cost rental housing on this property which utilizes an onsite well to provide drinking water. Mr. Stark observed a wet area in the ground with the smell of sewage near the building identified as Apartment Building C, which houses seven (7) apartments. Mr. Stark identified this area as a sewage leak. On May 28, 1997, Mr. Stark returned to Mr. Decker's property with another Volusia County Health Department employee, Ed Williams. They both observed a wet area in the ground with the smell of sewage in the vicinity of the septic tank serving Apartment Building C. Mr. Stark identified this area as a sewage leak. Mr. Stark issued a Notice of Violation (NOV) to Mr. Decker which stated the raw sewage leak was a sanitary nuisance and provided that Mr. Decker should have his drainfield repaired in accordance with the repair permit Mr. Decker had previously obtained from the Department. The NOV stated the repair should be completed no later than June 11, 1997. A repair permit is valid for a period of eighteen (18) months. Mr. Decker's permit expired on April 20, 1997. Repairs must be inspected by the Department as they are made. On June 13, 1997, Mr. Stark mailed Mr. Decker a letter reiterating the need for repair of his septic system and enclosed a Notice of Intended Action giving Mr. Decker a deadline of June 20, 1997 to make the needed repairs. Mr. Stark received a letter dated June 29, 1997, from Mr. Decker, informing him that Mr. Decker, himself, had repaired the drainfield for Apartment Building C. The letter described the new tank and drainfield which Mr. Decker had installed, and Mr. Decker stated his repair was a "cheaper version of what you wanted me to do in the first place." Mr. Decker had not sought the required inspections for the repairs which he had made to the septic system, and the repairs were not inspected and approved by the Department. The Department cited Mr. Decker for having an improperly built or maintained septic system, and for failing to repair the system in accordance with the terms of the permit. The citation levied a $500 civil fine for Mr. Decker's violation.
Recommendation Based upon the findings of fact and conclusions of law, it is RECOMMENDED: That the Department issue a final order affirming the civil penalty against Mr. Decker and requiring Mr. Decker to repair his septic system according to permit. If Mr. Decker fails to effect the repairs, the Department should initiate action to abate this public health hazard. DONE AND ENTERED this 6th day of March, 1998, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 6th day of March, 1998.
Findings Of Fact The Respondents, Frank L. Reppa and Denise J. Reppa, own and reside in their dwelling located at 3863 Plumosa Drive, St. James, Florida. The property is a narrow canal front lot. All lots in the area are small and narrow and the dwellings thereon, mostly mobile homes, are placed closely together. On January 11, 1988, as the result of a nuisance complaint by the Reppa's next door neighbor, Stephen E. Havig, an Environmental Specialist with the Lee County Health Department, a part of the State of Florida DHRS, inspected the property in question and observed that effluent from the Respondents' drain field, a malodorous liquid, had run from Respondent's property down onto the driveway of their neighbors. On January 13, 1988, he returned to the property and spoke with Mrs. Reppa who admitted to living on the property. He again observed that the drain field in the Reppas' septic system was heavily saturated and had failed. Effluent was coming to the surface due to the high water table resulting from heavy recent rains and the failure of the system, and there was still a sewage odor to the effluent. The effluent showed in stains on the neighbor's drive. Mr. Havig told Mrs. Reppa that the problem had to be corrected as it was a violation of the law to allow it to remain. In response, Mrs. Reppa indicated they had no money to effect the repairs and because of that, Mr. Havig, who could have cited them immediately, indicated he would return to his office to see if they could be given some additional time to have the work done. After checking with his supervisor, Mr. Havig, on the same day issued an "Official Notification of Insanitary Nuisance" and a "Notice of Intended Action", both of which were sent by Certified Mail and receipted for by Mrs. Reppa on January 19, 1988. The Notice gave the Reppas until January 28, 1988 to correct the problem. On January 14, 1988, Mr. Havig again talked with Mrs. Reppa, telling her what he was sending and advising her how she could get the problem fixed. When he again went out to the property on January 28, 1988, he noted that the property had dried out due to a lack of rain. However, he could see no evidence that any repairs had been effected. He returned to the property on February 1, 1988 after a rain and observed that the problems had reoccurred. Mr. Havig again spoke with Mrs. Reppa on February 8, 1988, at which time she advised him the problem was to be repaired, but they were without funds to pay for it. At that time, Mr. Havig gave the Reppas three weeks to have the work completed with a contractor to be retained within one week. When he spoke with Mrs. Reppa on February 16, 1988, she stated she was still having trouble getting a contractor. She had contacted one contractor who looked at the system on February 15, 1988 and who proposed to remove the washing machine from the drain system. When Mr. Havig talked with Mrs. Reppa on February 19, 1988, she indicated she would have to discuss the matter with her husband. Mr. Havig stated at that time that the Department would have to proceed with enforcement action if work was not started on the correction by February 22, 1988. No corrective action was taken by the Reppas and the Administrative Complaint was filed as a result. DHRS considers it important to properly dispose of effluent because, since it contains human waste, it carries bacteria, viruses and a danger of parasites. Agency policy requires that the septic system be continually monitored and that the tank be pumped and the drain field be repaired when necessary. The Department has no funds available to assist those who cannot afford to make repairs. In order to be properly processed, effluent drainage from septic tanks needs a minimum of two feet of soil between the discharge outlet of the tank and the water table. The soil acts as a filter to remove harmful organisms and contaminants from the effluent before it reaches the water table. A high water table, due to heavy rains or other causes, prevents this filtration and causes the effluent to come to the surface. The situation is correctable. Two methods of correction are: 1) elevate the system above the water table, or 2) remove the saturated soil and replace it with a good grade of sand. In October, 1985, another complaint against the Reppas, relating to the same situation, was filed with DHRS. At that time, the Reppas paid $650.00 to have the system repaired by an individual who replaced the drain field, drawing it away from adjoining property and toward the road. Though the contractor assured them this would fix the problem, wash water would continue to come to the surface. As a result, Mrs. Reppa has refrained from washing clothes at her home and takes them to the laundry in town. Because of the actions they have taken, such as having the drain field expanded and moved, the pumping out of the septic tank in January, 1988, and the cessation of washing clothes at home, Mr. and Mrs. Reppa are convinced the system is not overflowing and that the water on the neighbor's property is the accumulation of surface water drainage when it rains. The Reppa property is higher than the neighbor's property and Mrs. Reppa believes that rain water drains down there. The new part of the drain field works and the water in question, she feels, cannot be effluent. The evidence of record, however, indicates to the contrary and that it is waste effluent. Inquiry by the Reppas indicates that it would take $750.00 more to fix the system and the Reppas do not have that money. They are still paying back the money they borrowed from Mrs. Reppa's parents to make the first repairs. Mr. Reppa is a commercial fisherman whose income has been substantially reduced due to the restrictions placed on the taking of redfish. Many neighbors in the area, according to the Reppas, discharge sewage directly into the abutting canal and allow wash water to run out onto the ground. The Reppas cannot comprehend why these individuals, mostly three month winter visitors, are not cited while they, full time residents, are.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: Recommended that an administrative fine of $50.00 per day be assessed against the Reppas for the violation established, said fine to be effective upon entry of a Final Order herein, with provision that the fine be remitted upon satisfactory proof that the violation has been corrected. Recommended in Tallahassee, Florida this 24th day of August, 1988. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of August, 1988. COPIES FURNISHED: Eugenie G. Rehak, Esquire Staff Attorney Department of Health and Rehabilitative Services Post Office Box 06085 Ft. Myers, Florida 33906 Frank Lee Reppa, pro se Denise J. Reppa, pro se 3863 Plumosa Drive St. James, Florida 33986 R. S. Power, Agency Clerk Department of Health and Rehabilitative Services 1323 Winewood Blvd. Tallahassee, Florida 32399-0700 Gregory L. Coler, Secretary Department of Health and Rehabilitative Services 1323 Winewood Blvd. Tallahassee, Florida 32399-0700
The Issue The issue in this case is whether the Variance Review and Advisory Committee and the Department of Health had just cause to disapprove Petitioner's application for a variance.
Findings Of Fact The Department of Health (DOH) is the agency responsible for oversight of the on-site sewage treatment and disposal systems program and the Variance Review and Advisory Committee which meets monthly to recommend agency action on variance requests pursuant to Chapter 381, Florida Statutes. In August 1999, Petitioner applied to the DOH for a second variance to extend a variance previously granted in June 1999, to use an existing septic system for six months. Petitioner's application for the second variance stated that county sewer would be available in 2001, and she would be required to hook into the sewer. Therefore, Petitioner wanted an extension to continue using the existing undersized septic system until the sewer was available. She also attached water usage records for June 1998 through July 1999, for her property. Petitioner owns the commercial property served by the septic system and located on Howland Boulevard in Deltona, Florida. The property consists of a strip mall with five offices and one restaurant. The property originally contained six office spaces in 1990, when Petitioner applied for a permit to install a septic system to handle the building's sewage flow. See Petitioner's Exhibit No. 1. Petitioner was granted a construction permit for the septic system on August 14, 1990, which contained the statement: "no food service operations permitted in this building." Prior to May 1999, Petitioner leased an office in her commercial property to Milagros Martinez to operate a sandwich shop. Ms. Martinez applied to DOH for approval to use Petitioner's existing septic system to handle her sandwich shop sewage, and was denied because of increased water use and septic system demands of a restaurant. Petitioner's septic system contains a 750-gallon tank with 162 square feet of drainfield. In order to handle the additional sewage generated by the sandwich shop, the Florida Administrative Code requires a 1350-gallon tank and a drainfield of 787 square feet. There is enough room on Petitioner's property to install a separate septic system to handle the sewage generated from the sandwich shop. Petitioner applied to DOH for her first variance in May 1999, requesting to utilize the septic system to handle the waste from the sandwich shop. Petitioner appeared before the DOH Variance Review and Advisory Committee in June 1999. The committee recommended, and DOH concurred, to approve the first variance with four provisos. See DOH Exhibit No. 2. The four provisos were: The applicant shall obtain and maintain an annual onsite sewage treatment and disposal system operating permit in accordance with subsection 64E-6.003(5), F.A.C. The owner shall maintain an annual contract with a licensed septic tank contractor to inspect and service the onsite sewage treatment and disposal system at least once per month or more frequently as necessary. This variance allows operation of the sandwich shop for no more than six months. During that six months, the applicant shall take all necessary steps to increase the capacity of the system to accommodate the additional 230-gallon sewage flow from the sandwich shop. At the end of the six months, the system shall be in compliance or the sandwich shop shall be closed and remain closed until compliance is achieved. The four provisos were additionally explained to Petitioner in a letter dated July 14, 1999, from Sharon Heber, Director of the DOH Environmental Health Division. See DOH Exhibit No. 1. Petitioner accepted the provisions of the first variance on July 20, 1999. See DOH Exhibit No. 4. Petitioner does not have a current annual on-site sewage treatment and disposal system operating permit as required by the first proviso. Petitioner did not contract with a licensed septic tank contractor to inspect and service her system at least once per month as required in the second proviso. Petitioner called a contractor to inspect her system four times in the six-month period since the first variance was granted. Within six months, Petitioner did not take the necessary steps to increase the capacity of her septic system to handle the additional flow as required by the third proviso of the first variance. The system is not in compliance and the sandwich shop is not closed as stated in the fourth proviso. In August 1999, Petitioner filed for a second variance requesting that the first variance be extended until year 2001. That is the date the county plans to install a sewer line on Howland Boulevard in Deltona, which will serve her commercial property. She submitted a letter from the Volusia County Public Works Service Center stating that the "sewer service is planned to be available sometime in the year 2001." See Petitioner's Exhibit No. 4. The Variance Review and Advisory Committee considered Petitioner's request at their September meeting. The variance committee unanimously denied Petitioner's request for a second variance. The Petitioner's system was not designed to handle an increased amount of sewage flow, and that it would eventually collapse or fail. The committee's approval of the first variance was to allow Petitioner adequate time to install the necessary septic system for the restaurant, and not put Petitioner in the position of telling her tenant she could not open her restaurant. See DOH Exhibit No. 5. When Petitioner's existing system fails, sewage will pond on the ground. The ponding fluid will consist of raw sewage. The leaking/ponding sewage may seep into the groundwater and then into drinking water aquifers. In the right conditions, this pollution can cause the spread of waterborne diseases such as typhoid and cholera, or viral infections, such as hepatitis A or polio.
Recommendation Based upon the findings of fact and conclusions of law, it is RECOMMENDED: That the Department of Health enter a final order affirming the decision of the Variance Review and Advisory Committee and the Department of Health to disapprove Petitioner's second variance application. DONE AND ENTERED this 17th day of April, 2000, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 17th day of April, 2000. COPIES FURNISHED: Connie Biancardi 2820 Howland Boulevard Deltona, Florida 32725-1606 Charlene J. Petersen, Esquire Department of Health Volusia County Health Department 420 Fentress Boulevard Daytona Beach, Florida 32114 Angela T. Hall, Agency Clerk Department of Health Bin A02 2020 Capital Circle, Southeast Tallahassee, Florida 32399-1703 William Large, General Counsel Department of Health Bin A02 2020 Capital Circle, Southeast Tallahassee, Florida 32399-1701 Dr. Robert G. Brooks, Secretary Department of Health Bin A02 2020 Capital Circle, Southeast Tallahassee, Florida 32399-1701
The Issue The issues to be resolved in this proceeding concern whether the Petitioner is entitled to a permit permitting installation of an on-site sewage disposal system (OSDS) on his property located in Dixie County, Florida, in the vicinity of the Suwannee River and whether he is entitled to seek a variance from the statutes and rules concerning permitting of such systems.
Findings Of Fact The department hereby adopts and incorporates by reference the findings of fact set forth in the Recommended Order.
Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the evidence of record, the candor and demeanor of the witnesses and the pleadings and arguments of the parties, it is therefore RECOMMENDED: That a Final Order be entered denying the Petitioner's application for an OSDS permit, without prejudice to the applicant applying for and seeking a variance from the statutory and rule requirements related to permitting for the reasons found and concluded above, and without prejudice to applying for and pursuing an OSDS permit application should the applicant, at a later time, be able to demonstrate that alternative methods of treatment and disposal of the sewage effluent at issue can feasibly be performed, within the bounds of the standards enunciated in the above-cited statutes and rules concerning on- site sewage disposal permitting. DONE and ENTERED this 21st of December, 1990 in Tallahassee, Leon County, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of December, 1990. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 90-2487 PETITIONER'S PROPOSED FINDINGS-OF FACT Accepted. Accepted. 5-14. Accepted. RESPONDENT'S PROPOSED FINDINGS OF FACT 1-7. Accepted. COPIES FURNISHED: Sam Power, Agency Clerk Department of HRS 1323 Winewood Boulevard Tallahassee, FL 32399-0700 Linda K. Harris, Esquire General Counsel Department of HRS 1323 Winewood Boulevard Tallahassee, FL 32399-0700 John K. McPherson, Esquire 22 South Main Street Gainesville, FL 32601 Frances S. Childers, Esquire Assistant District III Legal Counsel Department of HRS 1000 Northeast 16th Avenue Gainesville, FL 32609 =================================================================
Findings Of Fact Fallschase is a special taxing district which was created by the Board of County Commissioners of Leon County, Florida, in Leon County Ordinance No. 75-6. The district contains approximately 620 acres and is located in the area of the intersection of U.S. Highway 90 and Buck Lake Road in Leon County, Florida. The Intervenors are corporations which are seeking to develop the Fallschase area into a residential community. Through its permit application, Fallschase is seeking authority to construct a 167,000 gallon per day sewage treatment plant which would serve the proposed development. The plant would be of the extended aeration type with tertiary filters. Effluent from the plant would be discharged into a Percolation pond system. The City of Tallahassee operates a sanitary sewer system which serves areas within the city limits, as well as many unincorporated areas of Leon County. Service is provided to the unincorporated areas of the county in accordance with a contract between the City and Leon County which was executed in 1973. No election has been conducted within Leon County to authorize the contract. The County has terminated the contract, but the termination will not be effective until November 12, 1980. The City's sanitary sewer system is a regional system in that it serves a broad area not limited by the political boundaries of the City. The City's system has operated under temporary permits issued by the Department for a number of years because it does not meet the Department's requirements for tertiary sewage treatment. The City's regional sewage treatment system is capable of providing service to Fallschase. A 10-inch sewage pipe known as the "Belle Meade" Line runs adjacent to Fallschase. If a pumping station were constructed, sewage from Fallschase could be pumped into the Belle Meade Line and eventually into the City's primary sewage lines for treatment at one of the City's treatment facilities. In accordance with its statutory responsibilities, the Department has adopted Rule 17-4.26, Florida Administrative Code, which relates to permit requirements for sewage works. As filed with the office of the Secretary of State, the rule provided as follows: No person shall operate, maintain, construct, alter, modify, or expand any sewage collection system, sewage disposal system or sewage treatment facilities without a current and valid permit from the Department, pursuant to the Provision of Chapter 17-6, Florida Administrative Code. The Department shall deny an appli- cation for a permit and refuse to issue a permit unless the sewage collection, treatment and disposal system will pro- vide adequate and effective treatment in accordance with the rules and regu- lations of the Department and unless the system will operate as part of a regional system if one exists or be capable of tying into a regional system should one be established. Applications for a permit under this section shall be in accordance with Part I, Chapter 17-4, Florida Administrative Code. (e.s.) As filed with the Secretary of State, the rule included a clear policy choice in favor of regionalization of sewage treatment systems. In accordance with its responsibilities, the office of the Secretary of State published the rule in the Florida Administrative Code. When the rule was published in the Code, the portion of the rule which is underlined in the above quote was omitted. The rule as published in the Code thus did not include a clear statement requiring regionalization, and does not make sense. This erroneous version of the rule has been published in the Florida Administrative Code for more than five years, and the error has been compounded in that the Department has utilized the Florida Administrative Code version of the rule in its official handouts. A citizen requesting a current copy of Rule 17-4.26 from the Department, or from the Secretary of State's office, would receive the erroneous rule. The error has been further compounded because the Department subsequently adopted a policy of evaluating applications for sewage treatment proposals without regard to whether hookups to a regional system were possible. This policy has been applied by the Department for at least three years in accordance with verbal and written instructions of the Department's then Secretary, Jay Landers. Additional language was later added to Rule 17-4.26 as follows: Except for regional treatment plants, as designated by approved metropolitan or basin plans, all permits for treat- ment plants shall be valid only until connection, according to an approved plan, can be made to regional facilities. Such connection shall be made within ninety (90) days of the scheduled date for connection as provided in the approved plan. This provision has no applicability to the City's treatment system because the City's system has never been approved as the metropolitan or basin clan by the Department. The City has contended that the sewage treatment plant proposed by Fallschase would result in violations of the Department's standards for nitrates in the groundwater in the area of the plant. Nitrates would be a constituent of the effluent which would be discharged from the proposed sewage treatment plant into percolation ponds. The engineer who has designed the proposed plant estimated that total nitrogen discharged into the percolation ponds would be approximately 20 milligrams per liter, or parts per million (p.p.m.). In extended aeration plants such as that proposed by Fallschase, a substantial portion of the nitrogen would be in the form of nitrates. The 20 p.p.m. estimate is high. The experience generally in north Florida has been that nitrogen concentrations would not exceed 10 p.p.m. in the effluent discharged into percolation ponds. Once the effluent is discharged into the ponds, a certain amount of nitrogen is removed during the settling process. As the effluent percolates through the subsoils into the groundwater, further nitrogen is removed. Estimates of nitrogen removal through these processes range from a low of 25 percent to a high of 75 percent. The groundwater below the proposed plant is classified as Class 1-B groundwater under the Department's rules. It is very unlikely that effluent reaching the groundwater would contain as much as 10 p.p.m. nitrates. Even if it did, mixing with the groundwater would cause an almost immediate dilution of nitrogen concentrations so that concentrations in the groundwater as high as 10 p.p.m. would be unlikely in the extreme. Many sewage treatment plants operate within the Department's northwestern region, which extends from Pensacola to Tallahassee. The Department monitors these plants. A violation of the Department's nitrate standards has never been observed in the region. Indeed, in the entire State of Florida, nitrate violations have been detected only in certain areas of Dade County. Testimony was presented by the City to the effect that chemical processes in percolation ponds can cause very drastic nitrate concentrations when the funds are intermittently flooded and drained. Such concentrations have been observed at one of the City's treatment plants. The City`s plant, however, is of a different sort than that proposed by Fallschase. The City's plant produces concentrations of nitrogen in ammonia compounds and utilizes intermittent drying and flooding of the percolation ponds as a part of its operation. Ammonia compounds will not be a major constituent of effluent placed in the Fallschase percolation ponds; and, furthermore, the ponds will not be intermittently flooded and drained in the manner that would cause such concentrations to develop. In its Notice of Intent to Issue the proposed permit, the Department indicated that sludge produced through the proposed treatment facility should be disposed of by hauling to a plant operated by the City. The City has indicated that it will not make its plant available for such disposal, and cotends that accordingly Fallschase has given no reasonable assurances that the sludge will be disposed of properly. The contention is without merit. Many alternatives exist for disposal of sludge. Fallschase has adequate area available to it for construction of sludge drying pits. Sludge can be hauled to many potential locations. Specific issues respecting sludge disposal can be addressed in the operating permit which would not be issued by the Department until it is established that the proposed plant can operate within the Department's rules and regulations. The soils which lie below the proposed percolation ponds are not of a highly permeable sort. To aid in the percolation of effluent through the ground into the groundwater, Fallschase proposes to construct two-foot diameter holes in the bottom of the percolation ponds. The holes would extend from 18 to 25 feet below the bottom of the percolation ponds. The holes would be filled with sand, and alternatingly coarse layers of gravel. The City has contended that these holes would constitute wells, and that they therefore would need to be permitted by the Department. This contention is without merit. These structures could fit loosely within the definition of a well, but their function is merely to aid in the percolation of effluent through the subsoils. They are not designed to inject effluent directly into the groundwater. These structures would constitute wells to the same extent that any drain field would constitute a well.
Findings Of Fact Respondent HDR has applied to DER for a permit to construct a 60,000 gallon per day extended aeration sewage treatment plant with percolation ponds. The facility would be used to provide secondary treatment of domestic waste from the HDR Mobile Home Park. The project is in Volusia County south of the City of Oak Hill and north of the Town of Edgewater. It is bounded on the east side by the Indian River and the west side by U.S. Highway One. The mobile home project site consists of approximately 156 acres, with the proposed wastewater treatment plant located in the southwest corner of the tract. HDR submitted Application No. 85433 to DER on July 2, 1984, requesting a permit to construct a 0.6 MGD extended aeration sewage treatment plant and associated percolation ponds for the mobile home project. Supplemental information was filed with DER on August 29, 1984. DER issued a notice of intent to permit the project on November 8, 1984. The plant would provide secondary treatment of effluent with a minimum of 90 percent removal of BOD's and suspended solids through aeration, settling and chlorination processes. The system is designed to collect sewage through a gravity system and lift station. The lift station dumps the sewage into the aeration chambers where forced air is mixed with the sewage, resulting in removal of organic materials and solids. The dissolved solids are then separated in the settling tank. From the settling tank, clear effluent enters the chlorine contact chamber where chlorine disinfectant is added prior to discharge into the percolation pond. The method of treatment described above and the design of the plant are standard. If the plant is operated properly, the wastewater will meet all DER criteria for secondary sewage treatment. Plant odor will be minimized by the continual feed of forced air into the system. Silencers will be installed on blowers to minimize any adverse noise effects from the blowers' operation. Aerosol drift is not a factor with the design of this plant. Security lighting will be provided, and the plant site will be surrounded by a six foot security fence. The design provides for effluent sampling access points and there will be a flow meter for measuring effluent discharge on site. A Class C operator will be required to operate the plant. Disposal of the 90 percent treated effluent will be made into two percolation ponds. The ponds will be alternately loaded, with one pond being loaded for seven days and then resting seven days. The total surface area for the two ponds is approximately 130,000 square feet. The ponds are designed with berms of three feet with an emergency overflow one foot from the top of each berm. The two ponds together are designed to handle 200,000 gallons per day which would be the ultimate build out of this project. However, the maximum capacity of the initial phase of the wastewater treatment plant would be 60,000 gallons a day. Any expansion to the sewage treatment plant would require a separate permit. The overall elevation of the area where the ponds are to be located is approximately 14 feet above sea level. Each pond is designed so that the pond bottom is two feet above the underground water table level measured at the highest point for the rainy season. In a 100 year flood, it is expected that the effluent and water can be absorbed without an overflow. The mobile home park has a storm retention system in which any theoretical overflow would be caught. The soil type at the location of the percolation ponds consists of several layers of sands. This type of soil has good permeability in that it provides a good transfer of water through the soil and is therefore suitable for siting of the percolation ponds. Pond design is conservative in that the hydraulic loading rate has a safety factor of at least 300 percent. Once the effluent has percolated into the ponds, the discharge will meet or exceed the level of quality of the G-2 ground water within the 100 foot zone of discharge. The design of the wastewater treatment plant also includes sufficient monitoring wells and provides for adequate buffer zones from residences and drainage ditches. No surface waters of the state are located within 500 feet of the sewage treatment plant or its percolation ponds. The Indian River, which is adjacent to the Hacienda Del Rio project, is approximately 2,500 feet from the sewage treatment plant. There will be no direct discharge by the sewage treatment plant into this body of water or any surface waters, nor would any indirect effect on surface waters be measurable. Shellfish harvesting is a local industry. The waters of the Indian River immediately east of the Hacienda Del Rio property are designated Class II waters suitable for shellfish harvesting. The Indian River is also part of the Canaveral National Seashore Waters, which are designated as Outstanding Florida Waters. Concern was expressed that additional growth in the area might contribute to degradation of these Class II waters. There was, however, no evidence to indicate that the construction or implementation of the wastewater treatment plant by HCD would degrade ore pollute the Indian River (which is both Class II and Outstanding Florida Water) or any other State of Florida surface waters. It should be noted that waters north and south of the property in the Indian River are closed to shellfish harvesting, apparently due to pollution. The Town of Edgewater north of the Hacienda Del Rio project has a secondary wastewater treatment plant which discharges its effluent directly into the Indian River. The City of Oak Hill to the south of the project has no wastewater treatment plant whatsoever. Individual businesses and homes utilize septic tanks, which can cause pollution to the Indian River through seepage. The HDR sewage treatment plant would thus meet higher standards than neighboring community facilities.
Recommendation From the foregoing, it is RECOMMENDED that the Department of Environmental Regulation issue a Final Order granting the application of Hacienda Del Rio. DONE and ENTERED this 31st day of May, 1985, in Tallahassee, Florida. R. T. CARPENTER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of May, 1985. COPIES FURNISHED: Betty J. Steffens, Esquire NABORS, GIBLIN & STEFFENS, P.A. 102 South Monroe Street Tallahassee, Florida 32302 William C. Henderson, Esquire HENDERSON & HENDERSON, P.A. Post Office Box 1840 New Smyrna Beach, Florida 32070 B. J. Owens, Esquire Department of Environmental Regulation 2600 Blairstone Road Tallahassee, Florida 32301 Alva Stewart, Vice President South Waterfront Park Homeowners Association 150 Charles Street Edgewater, Florida 32032 Victoria Tschinkel, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blairstone Road Tallahassee, Florida 32301
Findings Of Fact On October 13, 1988, Petitioner applied for a permit from Respondent for the operation of an onsite sewage disposal system in connection with a commercial project to be constructed on Petitioner's property in Polk County, Florida. Petitioner's application was disapproved that same day. Respondent denied the application because a publicly owned sewer system was available to Petitioner. A sewage line of the City of Lakeland, Florida, exists within a public easement abutting Petitioner's property. That sewage line is about 10 feet from Petitioner's property line. Gravity flow from Petitioner's proposed facility to the sewer line can be maintained. The city's system is under no moratoriums from any governmental body which would prevent the addition of Petitioner to the system. On October 17, 1988, Petitioner applied to Respondent's variance board, in accordance with provisions of Section 381.272(8), Florida Statutes, and Rule 10D-6.045, Florida Administrative Code. The variance application was considered by the board on November 3, 1988, and a recommendation that the variance be denied resulted. On December 12, 1988, Respondent notified Petitioner of the recommended denial of the variance application. The denial letter to Petitioner informed him that variances were granted for the relief or prevention of excessive hardship in those situations where there is a clear showing that the public health would not be impaired and pollution of groundwater or surface water would not result. The letter further stated that recommendation to deny variance was premised on the availability of public sewer to the property. Existence of adequate drainage for the proposed on site disposal system on Petitioner's property is questionable. The water table during the wettest season of the year on the property is only 20 inches from the surface. During other parts of the year, the water table is 38 inches from the ground surface. Two residences are presently situated on Petitioner's property and produce a flow to the present septic tank sewage disposal system of approximately 900 gallons per day. A commercial building also previously existed on the property and supplied a septic tank flow of approximately 700 gallons. The proof at hearing failed to establish whether the commercial building flow coexisted with the present residential flow. Petitioner proposes to construct a "mini mall" consisting of four stores, each with one toilet, on the property. Since public usage of the toilets in the building is not anticipated to be frequent, Petitioner estimates that approximately 600 gallons of sewage flow will be generated on a daily basis. Petitioner's property is presently served by the public water utility of the City of Lakeland. While the property lies outside the corporate city limits, it is bounded on two sides by property within the city limits on which restaurants, served by the city's sewage system, are situated. The city easement containing the sewer line runs along another side of the property which is contiguous to U.S. Highway 98. Under current policy of the City of Lakeland, connection to the city sewage system is permitted only to property located in the city limits. Petitioner must agree to annexation by the city of his property in order to obtain connection to the sewage system. However, the city assesses impact fees in addition to costs of sewage connection and in Petitioner's situation the amount of impact fees anticipated to be levied by the city is approximately $53,000. Petitioner estimates the value of his property when the "mini mall" is completed at $700,000. Estimated cost of construction, without consideration of the city's impact fees, will be $350,000. While Petitioner does not contemplate selling the property after the development is completed, he will be leasing the individual store facilities. The sole objection of Petitioner to denial of his request for a variance recommendation is that he will be forced to resort to joining the city's public sewage system and, by concomitantly accepting the city's annexation of his property, incurring the city's impact fees. It is Petitioner's contention that the impact fees effectively make the city's system unavailable to him. Alternatively, Petitioner also contends that assessment of impact fees by the city will pose a financial hardship on him and increase the per unit rental or lease costs he must charge tenants. Petitioner also contends that his commercial project will cause no adverse public health considerations because sewage flow from his facility to an on site sewage disposal system will be no more and possibly less than that presently flowing from the residences on the property to the existing septic tank system. This testimony is not credited due to the fact that anticipated drainage flow is an estimate by Petitioner with no demonstrated expertise in making such estimates; drainage at the proposed site location is questionable; and Petitioner's application states that the proposed site is located five feet from a public water well. Petitioner asserts that facts of a previous decision of the variance board established policy which requires that the variance he has requested be granted. On May 19, 1988, the variance board recommended a variance be granted to an automobile dealership in Polk County to operate an on site sewage disposal system. Had the variance not been granted, the dealership would have been force to accept annexation to a city adjoining the dealership property in order to have sewage disposal. Such a decision would have resulted in two dealerships from the same company within that city. The applicant in that case would have lost his automobile dealer franchise or have been forced to relocate elsewhere. The automobile dealership property site possessed adequate drainage with a water table 44 inches below the surface during the wettest season of the year and 84 inches at other times of the year. Anticipated sewage flow estimated at 525 gallons per day for the automobile dealership is similar to the estimate of 600 gallons per day for Petitioner's facility. Impact fees were not a consideration in the case.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered denying approval of the variance requested by Petitioner. DONE AND ENTERED this 21st day of April, 1989, in Tallahassee, Leon County, Florida. DON W. DAVIS Hearing Officer Division of Administrative Hearings The Desoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of April, 1989. COPIES FURNISHED: Deno P. Dikeou Liberty National Bank Building Suite 200 502 N. Highway 17-92 Longwood, Florida 32750 Raymond R. Deckert, Esquire Department of Health and Rehabilitative Services 4000 West Buffalo Avenue 5th Floor, Room 500 Tampa, Florida 33614 Gregory L. Coler Secretary Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 John Miller, Esq. General Counsel Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 Sam Power Clerk Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700
The Issue Whether the Petitioner's Application for Variance from Chapter 10D-6, FAC Standards for Onsite Sewage Disposal Systems should be approved?
Findings Of Fact By letter dated September 9, 1986, the County Engineer for Volusia County, Florida, denied the Petitioner's request for expedited subdivision. On or about October 15, 1986, the Petitioner filed an Application for Variance from Chapter 10D-6, FAC Standards for Onsite Sewage Disposal Systems (hereinafter referred to as the "Application"). On or about November 12, 1986, the Volusia County Health Department recommended denial of the Application. By letter dated November 24, 1986, the Respondent advised the Petitioner that his Application had been placed on the agenda of the Variance Review Group's December 4, 1986 meeting. By letter dated December 16, 1986, the Respondent informed the Petitioner that the Application was denied. By letter dated January 7, 1987, from the Petitioner's counsel, the Petitioner requested a formal administrative hearing to contest the proposed denial. The property involved in this case is located at 1083 Sheri Boulevard, Daytona Beach, Volusia County, Florida (hereinafter referred to as the "Property"). The Petitioner's parents originally owned 10 acres of property. By warranty deed dated September 12, 1958, the Petitioner's parents gave the Petitioner the Property which consisted of two lots from the ten acres, described as follows: The Easterly 149 feet of the Westerly 295 feet of the Southerly 1/2 (one half) of Lot 140, Blake, as per map in Map Book 1, page 38, of the public records of Volusia County, Florida. The Petitioner's parents also gave five acres of the ten acres to another individual in 1958. This property was developed as a mobile home park. The Property measures 150 feet x 150 feet. The property immediately to the west of the Property is currently owned by the Petitioner's Father. It measures 155 feet x 150 feet. Between 1958 and 1960 the Petitioner began construction of a single- story house on the Property. Also between 1953 and 1960 the Petitioner placed a mobile home on the Property. The Petitioner and his family lived in the mobile home while his house was being constructed. Two septic tanks were placed on the Property sometime between 1958 and 1960. The mobile home located on the Property was hooked up to one of the septic tanks. In 1960 construction of the house was completed and the Petitioner and his family moved into the house. The mobile home remained on the Property until 1961 when it was permanently removed. When construction of the house was completed, both septic tanks were connected to the house. Since 1961, trailers have been temporarily on the Property and have been hooked up to one of the septic tanks. Use of the septic tank by trailers has been infrequent, however, since 1961. Recently the Petitioner placed a mobile home on the Property and hooked it up to one of the septic tanks. The Petitioner was cited by the Volusia County Code Compliance Board for having the mobile home located on the Property. Subsequent to the action by the Volusia County Code Compliance Board the Petitioner attempted to subdivide the Property. The Petitioner proposes using a portion of the Property and a portion of his Father's adjoining property to create a lot 60 feet by 150 feet. The evidence failed to prove how much of the Property and how much of the Petitioner's Father's property would be used to create the new lot. The Petitioner wants to put a mobile home on the new lot and hook it up to one of the existing septic tanks on the Property. The Petitioner plans to provide the mobile home as a home for his daughter who is unemployed. Both of the existing septic tanks on the Property would remain on the Property if the subdivision is approved. The Property is .39 acres and the Petitioner's Father's adjoining lot is .48 acres. The Property and the Petitioner's Father's adjoining property have existing single story residences and use wells located on the property. The private well on the Property is less than 75 feet from the septic tanks. If a new lot is created, it will be located between the Property and the Petitioner's Father's property and all three lots will be less than 1/2 acre in size. The two septic tanks on the Property are larger than normal and the Petitioner is not aware of any problem with the two tanks. The Petitioner does not believe that there has been any contamination of his well caused by the septic tanks. Mobile homes are located in the mobile home park and on other lots in the area of the Property. The mobile homes are located on lots of less than 1/2 acre and they use septic tanks. There is therefore, a high concentration of septic tanks in the area. Mobile homes are frequently moved on and off property in the area but other lots do not remain vacant for any appreciable time. The Respondent reviewed the Petitioner's Application in accordance with its Rules.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Petitioner's Application be denied. DONE and ENTERED this 24th day of April, 1987, in Tallahassee, Florida. LARRY J. SARTIN Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of April, 1987. COPIES FURNISHED: Mr. Sam Power, Clerk Department Of Health and Rehabilitative Services 1323 Wine wood Boulevard Tallahassee, Florida 32399-0700 Mr. Gregory Coler, Secretary Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 James L. Rose, Esquire Rice and Rose Post Office Box 2599 Daytona Beach, Florida 32015 Frederick J. Simpson, Esquire District IV Legal Counsel Department of Health and Rehabilitative Services Post Office Box 2417 Jacksonville, Florida 32231-0083
Findings Of Fact Kearney is engaged in the development of real property in and around Hillsborough County, Florida, and is located in Tampa, Florida. Corrugated is a Louisiana Corporation which maintains a local headquarters in Tampa, Florida, and is presently seeking a business outlet in Hillsborough County for the assembly and distribution of metal buildings. At all times material hereto, Kearney and Corrugated have been parties to a real estate transaction concerning certain real property located at 1920 U.S. Highway 301 in Tampa, Hillsborough County, Florida. The subject property consists of .82 acres of undeveloped land which is located in an area of rapid commercial and industrial growth. Under the Hillsborough County Zoning Code, the subject property is designated M-1, which authorizes commercial and industrial uses. Corrugated is the purchaser of the subject property, and proposes to establish an assembly and distribution center for pre-painted sheet metal buildings. Corrugated does not propose to engage in any activity which will generate industrial wastewaters of any kind, and in particular, will not generate wastes or wastewaters of a "hazardous" or "toxic" nature. No centralized public wastewater service has been available to this property, and septic tanks with drainfields are utilized by both adjacent properties for their domestic and other wastewater needs. Kearney and Corrugated have determined that the property in question is suitable for the intended uses in all other respects, including water, electricity, and transportation. In September, 1988, Kearney and corrugated sought approval from Respondent of a permit to install an onsite sewage disposal system (septic tank and drainfield) for the sole purpcse of providing toilet services to employees of the company. The site plan and preliminary construction drawings for the on- site system were reviewed by the Department of Environmental Regulation (DER) to determine whether the project posed unusual wastewater problems or relied upon inadequately designed facilities. The DER had no objection to the installation of the septic tank and drainfield to serve the proposed system because of the non-hazardous character of the business, and the absence of floor drains in the proposed work areas. The Hillsborough County Health Department, however, gave immediate verbal denial of a septic tank permit based solely upon the industrial zoning of the property, and set forth its denial, in writing, on October 14, 1988. Following the County Health Departnent's denial, Kearney and Corrugated, based upon consultation with Respondent's officials in Tallahassee, assembled additional information to provide further assurance that the site would not generate industrial or hazardous wastes which could be disposed of via the septic tank. They provided detailed descriptions of each process to be performed by Corrugated, in substantiation of its claim that no wastewaters would be generated at the site. They also obtained the agreement of the Hillsborough County Building Department to subject any future building permit applications at the site to particular wastewater scrutiny, in addition to formal deed restrictions which they proposed for the subject property. Notwithstanding these additional representations, the Environmental Health Director of the Hillsborough County Health Department continued to reject the application on the sole ground that the property was zoned for industrial uses. On October 14, 1988, Petitioners submitted an application for a variance to the Hillsborough County Health Department and the Respondent, accompanied by supporting material setting forth the regulatory history referred to above, as well as the written representations and assurances, including proposed deed restrictions, which they had previously tendered to the County Environmental Health Director. They appeared before the Variance Advisory Review Board on November 3, 1988, to substantiate the specific measures which they proposed in order to ensure that no toxic or hazardous substances would be introduced into the septic tank system. These proposals were received by the Advisory Board without objection, and members observed that Petitioners had done everything they could do to provide the comfort margin which the agency sought. However, denial of the variance was recommended based upon the failure of Hi1sborough County to adopt a local ordinance providing for future inspections or controls by local officials to prevent future toxic or hazardous wastes from being disposed into the on- site sewage disposal system. Without such a local ordinance, the Advisory Board members expressed the view that it did not matter what the applicant presented to the Board. On December 2, 1988, the Respondent formally informed the Petitioners, in writing, that their application for a variance had been disapproved. This denial had the effect of formally denying Petitioners' permit application. Thereupon, Petitioners timely sought review of this decision by filing a petition for formal administrative hearing.
Recommendation Based upon the foregoing, it is recommended that the Respondent issue a permit for an onsite sewage disposal system to the Petitioners. DONE AND ENTERED this 18th day of May, 1989 in Tallahassee, Florida. DONALD D. CONN Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 Filed with the Clerk of the Division of Administrative Hearings this 18th day of May, 1989. COPIES FURNISHED: Charles G. Stephens, Esquire Bayport Plaza - Suite 460 6200 Courtney Campbell Causeway Tampa, Florida 33607 Raymond Deckert, Esguire W. T. Edwards Facility 4000 W. Buffalo 5th Floor, Room 500 Tampa, Florida 33614 John Miller, General Counsel 1323 Winewood Blvd. Tallahassee, Florida 32399-0700 Gregory Coler, Secretary 1323 Winewood Blvd. Tallahassee, Florida 32399-0700 Sam Power, Clerk 1323 Winewood Blvd. Tallahassee, Florida 32399-0700 =================================================================