JAMES P. GILLS AND MARGARET R. GILLS vs. DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 86-003504BID (1986)
Division of Administrative Hearings, Florida Number: 86-003504BID Latest Update: Dec. 15, 1986

The Issue Whether the Department of Health and Rehabilitative Services (HRS) acted in an arbitrary and capricious manner in determining to award the bid for its district office to Koger Properties, Inc. (Koger) and whether the petitioner submitted the lowest and best bid under the terms of the bid specifications.

Findings Of Fact GENERAL BACKGROUND - STIPULATED FACTS Petitioners received a formal Invitation to Bid on Lease No. 590:1784 from HRS, District V. The purpose of the ITB was to obtain competitive proposals for the leasing of office space by HRS within a specifically defined area. Petitioners timely submitted their bid in response to the ITB. All timely received bids were first evaluated to determine technical responsiveness. Petitioners' bid was determined to be responsive to the technical requirements of the ITB. Responsive bids were then presented to a bid evaluation committee for comparison and formulation of a recommendation for award. In comparing the various responsive bids and formulating a recommendation for award, the members of the bid evaluation committee were required to visit each proposed facility and to apply the evaluation criteria as contained in the ITB package. By memorandum dated July 30, 1986, the bid evaluation committee recommended that the bid be awarded to Koger although petitioners submitted the lowest rental price. On or about August 5, 1986, petitioners received notice from HRS of its intent to award Lease No. 590:1784 to Koger. By letter dated August 6, 1986, petitioners notified HRS of their intent to protest the intended award of Lease No. 590:1784 to Koger. The Notice of Intent to Protest was timely filed pursuant to the provisions of Section 120.53(5), Florida Statutes, and Rule 10- 13.11, Florida Administrative Code. Thereafter, the petitioners timely filed their formal written protest. Petitioners are substantially affected by the decision of HRS to award the lease to Koger. THE BIDDING PROCESS The Department of Health and Rehabilitative Services issued an Invitation to Bid and Bid Submittal Form (ITB) seeking approximately 39,968 net rental square feet of office space in Pinellas County, Florida, to be used as the district administrative offices. The ITB set forth the method in which the bids would be evaluated as follows: EVALUATION OF BIDS Bids received are first evaluated to determine technical responsive- ness. This includes submittal on bid submittal form, inclusion of required information and data, bid signed and notarized, etc. Non responsive bids will be withdrawn from further consideration. Responsive bids are presented to a bid evaluation committee for com- parison and formulation of a recom- mendation for award. This is accomplished by a visit to each proposed facility and application of the evaluation criteria. The committees recommendation will be presented to the department's official having award authority for final evaluation and determin- ation of successful bidder. EVALUATION CRITERIA The successful bid will be that one determined to be the lowest and best. All bids will be evaluated based on the award factors enumerated in the bid submittal form. The ITB also provided that "the department agrees to enter into a lease agreement based on submission and acceptance of the bid in the best interests of the department and the state." In accordance with the ITB a pre-bid conference was held on April 29, 1986; however, neither petitioners nor any representative of petitioners attended the pre-bid conference. Further, petitioners made no oral or written inquiries concerning the ITB or the evaluation criteria to be utilized. Bids received from the following providers were determined to be responsive and presented to the bid evaluation committee for comparison and formulation of the recommendation for award: James P. & Margaret R. Gills (1100 Building) Koger Properties, Inc. (Koger) LTBCLH Partnership (Justice Building) Procacci Real Estate Management Co., Inc. (ICOT Building) Elizabethan Development, Inc. (Handy City Building). BID EVALUATION COMMITTEE The bid evaluation committee was composed of the following people who, along with their staffs, would occupy the leased property: Robert Withrow, Chairman of the Committee and District Administrative Services Director; Samuel Kinsey, Financial and Accounting Director for District V; Patricia Bell, Program Manager for Aging and Adult Services; Fredrick M. O'Brien, General Services, Manager for District V; and Pegi Hollingsworth, Personnel Officer. Each member of the evaluation committee received a bid package consisting of the bid specifications and the bids submitted. Each member also received a bid evaluation sheet which was used to rate each bidder. They received no other instructions with regard to the evaluation criteria. Although each specific evaluation criterion was weighted, i.e., given a comparative value, the committee members were not specifically instructed as to how points should be assigned for each category. The evaluation committee went to each of the proposed buildings for the purpose of making a comparative evaluation based on the evaluation criteria provided. However, the primary focus was on the Koger Building and the petitioners' 1100 Building because they had submitted the lowest rental rates of the five bidders considered. After the viewing process, the members of the committee, except Mr. Withrow, discussed the factors that should be considered in applying each of the evaluation criterion. Although the committee members had not formulated the evaluation criteria to be used, they were uniquely qualified to apply the evaluation criteria provided to the specific needs and requirements of the HRS offices that would occupy the building. Though the committee members were in agreement as to the various factors to be included in each of the criterion listed, they did not discuss the points that would be awarded to each facility. Each member independently assigned points to each facility based on his or her own evaluation of the facility's comparative value in each of the listed categories. Koger received the best evaluation from all five committee members with point totals of 98, 98, 98, 98 and 99 out of a possible 100 points. Petitioners' building was ranked last of the five buildings evaluated by four of the members, with point totals of 75, 77, 71 and 75, and fourth by Mr. Withrow with a total of 81 points. Based on the comparative evaluation of the buildings, the committee recommended that the bid be awarded to Koger. By letter dated July 30, 1986, the District V office received authorization from the HRS Director of General Services to award the bid to Koger as being in the best interest of the department and state. THE EVALUATION CRITERIA The ITB included the evaluation criteria list used by the committee to ascertain the relative value of each building. At the top of the page it is stated: The successful bid will be that one determined to be the lowest and best. All bids will be evaluated based on the award factors enumerated... The evaluation criteria are divided into three general areas: (1) Associated Fiscal Costs, (2) Location, and (3) Facility. Each general area includes subcategories, with each subcategory being given a total maximum value. Each of the criteria disputed by petitioners is discussed below. 1(a) Rental rates for basic term of lease. (Weighting: 45) All of the bids received by HRS were within the rental limits established by the Department of General Services and also much lower than expected. Even the highest bid was lower than anticipated, and Koger's and petitioners' bids were considered especially desirable. The bids received, listed at present value for the ton year basic lease period, are as follows: BIDDER TOTAL COST AMOUNT MORE THAN LOW BID 1100 BUILDING $1,881,690.1 KOGER 1,993,131.4 $111,441.3 JUSTICE 2,473,559.8 591,869.7 ICOT 2,655,306.1 773,616.0 HANDY CITY 3,223,202.0 1,341,511.9 Rental rates for the basic term of the lease were given a weighted value of 45. All of the committee members gave petitioners 45 points, as the low bidder, and all gave Koger 44 points as the next low bidder. However, four of the members simply agreed that the low bid would receive the maximum amount of points with each subsequent low bidder receiving one less point than the one before it, which resulted in the high bidder receiving 41 points even though its bid was 1.7 times greater than the low bid. Only Mr. Withrow made an attempt to prorate the points based on the differences in the amount bid, thus resulting in the high bidder receiving only 20 points. However, even Mr. Withrow awarded Koger 44 points based on the minimal difference between the Koger bid and the petitioners' bid. Both Mr. Withrow and Mr. Kinsey explained the award of 44 points to Koger by comparing the difference in the amounts bid to the HRS District V budget or the budgets of the entities using the facilities. However, the purpose of the evaluation was to compare each facility to the other facilities. Thus, the award of points for rental rates should have been based on a comparison of the rates offered. Although it was reasonable to assign the maximum number of points to petitioners, as the low bidders, the amount of points assigned to the remaining bidders should have been based on a comparison of the amount of each bid to the low bid. This would have made a significant difference in the points awarded to Justice, ICOT, and Handy City; however, even using a strict mathematical computation would not significantly affect the points awarded Koger due to the minimal difference in Koger's bid and petitioners' bid. Koger would receive no less than 42 points, only 2 points less than awarded, regardless of the method of mathematical computation used. 1/ 2(a) Proximity of offered space in central or preferred area of mad boundaries (Weighting: 5) All the members of the committee agreed that Koger is in the most preferred area because its location is more accessible to the employees and the persons who visit the office than any of the other buildings. Koger is in northeast St. Petersburg, minutes from the interstate. The 1100 Building is located in a more congested area in downtown Clearwater on the extreme northern boundary of the designated area. In making a comparison Of the building locations, all of which were located within the map boundary, the committee jusifiably determined that the building that was the most strategically located, in terms of accessibility, would be considered to be in the most preferred area. Thus, Koger was awarded five points by all committee members. The 1100 Building received 2, 0, 1, 3 and 1 points. Although all committee members awarded Koger the highest points, only one committee member resided closer to the Koger Building than the other buildings. Mr. Withrow, who lives closer to the 1100 Building than Koger, gave the 1100 Building only 1 point because it was more inaccessible to the district clients and employees. Further, the District Administrator, who approved the lease to Koger, resides closer to the 1100 Building. 2(b) Frequency and availability of satisfactory public transportation within proximity of the offered space (Weighting: 5) Both Koger and the 1100 Building received the maximum of five points in this category except from Mr. Withrow who gave the 1100 Building four points. The committee members felt that the bus transportation as about the same for each building. Although the 1100 Building had more buses passing the facility due to its location in downtown Clearwater, the committee considered the destination of the buses and concluded that a person would wait the same length of time for a bus to take him to his destination from either the Koger Building or the 1100 Building. Mr. Withrow differed on the points awarded because he considered the Koger location to be better due to its proximity to the airport. The district office has a large number of people that visit from Tallahassee and other districts in the state. 2(c) The effect of environmental factors, including the physical characteristics of the building and the area surrounding it, on the efficient and economical conduct of departmental operations planned for the requested space. (Weighting: 3) Koger received the maximum of 3 points from every committee member in this category; the 1100 Building received 0 points from every member. Although this category is listed within the general area of "Location", the committee members followed the category requirement and considered all environmental factors, including the physical characteristics of the building. In the 1100 Building, committee members noted problems with the air conditioning system and the elevators. The building was not maintained well, and the bathrooms were small and poorly ventilated. The HRS parking at the 1100 Building was not conveniently located. To get to the parking lot from the building an employee would have to cross a parking lot adjacent to the building, cross an intersection and then walk up to a block to get to his or her car. Many of the office employees work late and would be walking to their cars after dark, and there was concern expressed for employee safety considering the parking arrangement offered by petitioners. Koger had none of the problems observed at the 1100 Building. Further, Koger was better suited for the handicapped because there was no need to use a ramp as there was at the 1100 Building. 3(a) Conformance of space offered to the specific requirements contained in the Invitation to Bid. (Weighing: 10) 3(b) Susceptibility of the design of the space offered to efficient layout and good utilization. (Weighting: 10) 3(c) Provisions of the aggregate square footage in a single building. Proposals will be considered, but fewer points given, which offer the aggregate square footage in not more than two locations...within 100 yards of each other. (Weighting: 10) Koger's bid is for a two-story building containing approximately 39,000 square feet. The 1100 Building is a 15-story building. It would provide approximately 39,000 square feet on the second, fourth, fifth, part of the eighth, part of the ninth, and twelfth floors. The space allocation in the 1100 Building, spread over 6 floors, would provide a major problem in efficiently locating the staff. Certain offices could not be placed on certain floors because of space restrictions, and related offices could not be placed in close proximity to each other. Offices that needed to be on the same floor could not be located on the same floor. Because the space offered by petitioners is spread over 12 floors, accessibility to related offices would be much more difficult. Further, the limited space per floor makes it more difficult for HRS to properly utilize the space provided. None of the testimony provided by the committee witnesses related the "conformance of the space offered to the specific requirements contained in the Invitation to Bid" (e.s.) The ITB lists the offices and rooms required, giving sizes for each. Other than the total square footage, which petitioners met, there were no other specific requirements contained in the ITB. None of the committee members compared the conformance of the space offered to the specific room and office requirements. Indeed, the testimony of the committee members indicate that accessibility of the space was considered under criteria 3(a) rather than the conformance of the space to the ITB. Since the space offered by petitioners apparently complied with the requirements of the ITB, petitioners should have received 10 points for that category. The points awarded under 3(b) and 3(c), however, were proper. The space offered by the 1100 Building is not susceptible to an efficient layout or good utilization of the space offered. Further, the committee legitimately differentiated between the single buildings offered by each bidder, under 3(c), by considering where the space was located within the building. Obviously, factor 3(c) reflects a concern that the space offered not be too separated. It clearly provides that proposals for space in two separate buildings will get fewer points than single building proposals, and there is no indication that all single building proposals should receive the same maximum points. This factor clearly relates to the proximity of the spaces offered to one another, with contiguous space getting the most points. 3(d) Offers providing street-level space (Weighting: 2) Approximately half of the space offered by Koger is street-level space. Koger received two points. The 1100 Building provides no street-level space; it received no points in this category. Petitioners do not contend that they should have gotten any points, but assert Koger should only have gotten one point because not all its space was street-level space. THE COMPARATIVE EVALUATION The evaluation committee members were very conscientious in comparing the relative values of the buildings offered based on the criteria provided and their observations. Their evaluations were not made arbitrarily, but based upon the factors set forth in the evaluation criteria. Although errors were made in calculating the values awarded for categories 1(a) and 3(a), these errors were not due to arbitrary action by the committee members. Further, should the appropriate points under 3(a) be added to petitioners evaluations and three points be subtracted from Koger's evaluations (two points for 1(a) and one point for 3(d)), petitioners evaluations would be 79, 80, 76, 80 and 84, and Koger's would be 95, 95, 95, 95 and 96. The strategic plan for HRS, 1986-1991, Goal 12, is to enhance employee morale and job satisfaction in several ways, one of which is to replace or upgrade 90 percent of substandard physical work environments by December 31, 1990. The testimony and evaluations show, and the committee members found, that the Koger Center would provide a better work environment than the petitioners' 1100 Building. Based on the criteria set forth in the ITB, the Koger bid is the "lowest and best" bid.

Florida Laws (4) 120.53120.57255.249255.25
# 1
NATIONAL CLEANING OF FLORIDA, INC. vs DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 92-004311BID (1992)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Jul. 15, 1992 Number: 92-004311BID Latest Update: Sep. 14, 1992

The Issue Whether Respondent properly rejected Petitioner's bid on the grounds that the bid did not meet a fatal item requirement.

Findings Of Fact On April 24, 1992, Respondent published a Request for Proposals (RFP) for the provision of housekeeping services to South Florida State Hospital. Attached to the RFP as Appendix I was a blank copy of Respondent's "Standard Contract" which is also referred to as its "core model contract". Paragraph 1.a. of Section D of the RFP contains the following instructions to bidders: BIDDER RESPONSE a. State of Florida Request for Proposal Contractual Services Acknowledgment Form, Pur 7033 The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, Appendix II must be signed and returned ... with the proposal or submitted by itself if you choose not to submit a proposal and wish to remain on the department's active vendor list. Paragraph 1.g. of Section D of the RFP, contains the following instructions to bidders: Required Bidders Certification Contract Terms and Conditions The proposal must include a signed statement in response to the RFP indicating acceptance of the terms and conditions of provisions of service as specified in the RFP and contained in the core model contract. Bidders were provided a copy of the RFP rating sheet which contained the following under the heading of Fatal Items: The following criteria must be met in order for the proposal to be considered for evaluation, failure to receive a "Yes" response for any time [item] will result in automatic rejection of the proposal. * * * Does the proposal include a statement agreeing to terms and conditions set forth in the core model contract and the RFP? Petitioner was represented at a "Bidders' Conference" held May 15, 1992, at which the fatal items were discussed. Bidders were advised that it would be necessary for the responses to contain a statement agreeing to the terms and conditions set forth in the core model contract. The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, contains the following certification: I certify that this proposal is made without prior understanding, agreement, or connection with any corporation, firm, or person submitting a proposal for the same contractual services, and is in all respects fair and without collusion or fraud. I agree to abide by all conditions of this proposal and certify that I am authorized to sign this proposal for the proposer and that the proposer is in compliance with all requirements of the Request for Proposal, including but not limited to, certification requirements. In submitting a proposal to an agency for the State of Florida, the proposer offers and agrees that if the proposal is accepted, the proposer will convey, sell, assign or transfer to the State of Florida all rights, title and interest in and to all causes of action it may now or hereafter acquire under the Anti-trust laws of the United States and the State of Florida for price fixing relating to the particular commodities or services purchased or acquired by the State of Florida. At the State's discretion, such assignment shall be made and become effective at the time the purchasing agency tenders final payment to the proposer. The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, was signed by Richard A. Cosby on behalf of Petitioner and submitted as part of Petitioner's response to the RFP. Upon receipt of all responses, Respondent convened an evaluation committee to evaluate the responses. The evaluation committee determined that the response submitted by Petitioner did not contain the required statement agreeing to the terms and conditions set forth in the core model contract and the RFP. Consequently, the evaluation committee rejected Petitioner's proposal from further consideration. Petitioner does not challenge the specifications of the RFP, but, instead, asserts that Mr. Cosby's execution of the State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, was sufficient to meet the requirement the evaluation committee found lacking. The language of the Contractual Services Acknowledgment Form, PUR 7033, that most closely approximates the certification that the bidder accepts the terms and conditions set forth in the core model contract and of the RFP is as follows: I agree to abide by all conditions of this proposal and certify that I am authorized to sign this proposal for the proposer and that the proposer is in compliance with all requirements of the Request for Proposal, including but not limited to, certification requirements. The proposal submitted by Petitioner did not contain any other statement which could be construed as accepting the terms and conditions set forth in the core model contract and the RFP. The broad language of the Contractual Services Acknowledgment Form, PUR 7033, upon which Petitioner relies does not state that the bidder accepts the terms and conditions set forth in the core model contract and the RFP. The evaluation committee properly determined that Petitioner's response failed to meet this fatal item. In this proceeding, there was evidence that the Respondent routinely inserts in its Request for Proposals the fatal item requirement that the bidders agree in writing to accept the terms and conditions set forth in the core model contract and the RFP, and that Respondent has never waived that fatal item requirement. There was no evidence that Respondent was using this fatal item requirement to discriminate against or in favor of any bidder.

Recommendation Based upon the foregoing findings of fact and conclusion of law, it is hereby RECOMMENDED that the Respondent dismiss Petitioner's bid protest. DONE AND ENTERED this 18th day of August, 1992, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of August, 1992. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 92-4311BID The following rulings are made on the proposed findings of fact submitted on behalf of the Petitioner. 1. The proposed findings of fact submitted by Petitioner are accepted in material part by the Recommended Order. Petitioner's conclusions based on those facts are rejected for the reasons discussed in the Recommended Order. The following rulings are made on the proposed findings of fact submitted on behalf of the Respondent. 1. The proposed findings of fact submitted by Respondent are adopted in material part by the Recommended Order. COPIES FURNISHED: Richard A. Cosby, Vice President National Cleaning of Florida, Inc. 1101 Holland Drive, #32 Boca Raton, Florida 33487 Colleen A. Donahue, Esquire District 10 Legal Office Room 513 201 West Broward Boulevard Fort Lauderdale, Florida 33301-1885 Sam Power, Agency Clerk Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 John Slye, General Counsel Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700

Florida Laws (3) 120.57287.012287.057
# 2
PRINCE CONTRACTING, LLC vs DEPARTMENT OF TRANSPORTATION, 16-004982BID (2016)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Aug. 29, 2016 Number: 16-004982BID Latest Update: Jan. 20, 2017

The Issue Whether Respondent acted contrary to the agency's governing statutes, rules, or policies or the bid specifications in its proposed decision to award Contract No. T7380 to Astaldi Construction Corporation ("Astaldi").

Findings Of Fact Based on the oral and documentary evidence presented at the final hearing, and on the entire record of the proceeding, the following Findings of Fact are made: The Department is a state agency authorized by section 337.11 to contract for the construction and maintenance of roads within the State Highway System, the State Park Road System, and roads placed under its supervision by law. The Department is specifically authorized to award contracts under section 337.11(4) to “the lowest responsible bidder.” On April 15, 2016, the Department advertised a bid solicitation for Contract T7380, seeking contractors for the widening of a 3.8 mile portion of U.S. Highway 301 in Hillsborough County from two lanes to six lanes between State Road 674 and County Road 672 and over Big Bull Frog Creek. The advertisement provided a specification package for the project and the “Standard Specifications for Road and Bridge Construction” (“Standard Specifications”) used on Department roadway projects. The work included seven components: bridge structures (Section 0001), roadway (Section 0002), signage (Section 0003), lighting (Section 0004), signalization (Section 0005), utilities (Section 0006), and intelligent transportation systems (Section 0007). The advertisement identified 666 individual items of work to be performed and quantity units for each item. The project was advertised as a low-bid contract with a budget estimate of $51,702,729. The Department’s bid proposal form contains five columns with the following headings: Line Number; Item Number and Item Description; Approximate Quantities and Units; Unit Price; and Bid Amount. The bid proposal form contains line items for the seven components of the project. The utilities component contains 42 line items, each with an Item Number and Item Description. For example, Line Number 1410 corresponds with the following Item Number and Item Description: “1050 11225 Utility Pipe, F&I, PVC, Water/Sewer, 20–40.9 [inches].” Each bidder inserts a Unit Price for the line item in the corresponding “Unit Price” column. The “Bid Amount” column for each line item is an amount generated by multiplying a bidder’s Unit Price by the Quantities (determined by the Department) for each Line Number. The Bid Amount for each Line Number is then added together to generate the “Total Bid Amount” representing the bid for the entire project. Astaldi, Prince, Hubbard, and other potential bidders attended the mandatory pre-bid meeting. Prequalified contractors were given proposal documents that allowed them to enter bids through Bid Express, the electronic bidding system used by the Department. Plan revisions were issued by addenda dated May 10, 2016, and June 7, 2016. A Question and Answer Report was published and updated as inquiries were addressed. Bids were opened on the letting date of June 15, 2016. Bids for Contract T7380 were received from Astaldi, Prince, Hubbard, the DeMoya Group (“DeMoya”), Ajax Paving Industries of Florida, LLC (“Ajax”), and Cone & Graham, Inc. (“Cone & Graham”). The bids were reviewed by the Department’s contracts administration office to ensure they were timely, included a Unit Price for each line item, and contained the completed certifications required by the specifications. Bidders were checked against the Department’s list of prequalified bidders to confirm they possessed a certification of qualification in the particular work classes identified by the bid solicitation. Each bidder’s total current work under contract with the Department was examined to ensure that award of Contract T7380 would not place the bidder over its Department-designated financial capacity limit. Astaldi submitted the lowest bid, a total amount of $48,960,013. Prince submitted the next lowest bid, a total amount of $57,792,043. Hubbard’s total bid was the third lowest at $58,572,352.66. The remaining bidders came in as follows: DeMoya, $63,511,686.16; Ajax, $68,617,978.10; and Cone & Graham, $70,383,697.74. All bidders were prequalified in the appropriate work classes and had sufficient financial capacity, in accordance with section 337.14 and Florida Administrative Code Chapter 14-22. The Department’s construction procurement procedure, from authorization to advertisement through contract execution, is outlined in the Department’s “Road and Bridge Contract Procurement” document (“Contract Procurement Procedure”). The scope statement of the Contract Procurement Procedure provides: “This procedure applies to all Contracts Administration Offices responsible for advertising, letting, awarding, and executing low bid, design-bid-build, construction, and maintenance contracts.” Limited exceptions to the procedure may be made if approved by the assistant secretary for Engineering and Operations. If federal funds are included, the Federal Highway Administration division administrator, or designee, must also approve any exceptions from the procedure. The stated objectives of the Contract Procurement Procedure are: “to standardize and clarify procedures for administering low-bid, design-bid-build, construction, and maintenance contracts” and “to provide program flexibility and more rapid response time in meeting public needs.” The Department’s process for review of bids is set forth in the “Preparation of the Authorization/Official Construction Cost Estimate and Contract Bid Review Package” (“Bid Review Procedure”). The scope statement of the Bid Review Procedure states: This procedure describes the responsibilities and activities of the District and Central Estimates Offices in preparing the authorization and official construction cost estimates and bid review packages from proposal development through the bid review process. Individuals affected by this procedure include Central and District personnel involved with estimates, specifications, design, construction, contracts administration, work program, production management, federal aid, and the District Directors of Transportation Development. The Bid Review Procedure contains a definitions section that defines several terms employed by the Department to determine whether a bid or a unit item within a bid is “unbalanced.” Those terms and their definitions are as follows: Materially Unbalanced: A bid that generates reasonable doubt that award to that bidder would result in the lowest ultimate cost or, a switch in low bidder due to a quantity error. Mathematically Unbalanced: A unit price or lump sum bid that does not reflect a reasonable cost for the respective pay item, as determined by the department’s mathematically unbalanced bid algorithm. Official Estimate: Department’s official construction cost estimate used for evaluating bids received on a proposal. Significantly Unbalanced: A mathematically unbalanced bid that is 75% lower than the statistical average. Statistical Average: For a given pay item, the sum of all bids for that item plus the Department’s Official Estimate which are then divided by the total number of bids plus one. This average does not include statistical outliers as determined by the department’s unit price algorithm. For every road and construction project procurement, the Department prepares an “official estimate,” which is not necessarily the same number as the “budget estimate” found in the public bid solicitation. The Department keeps the official estimate confidential pursuant to section 337.168(1), which provides: A document or electronic file revealing the official cost estimate of the department of a project is confidential and exempt from the provisions of s. 119.07(1) until the contract for the project has been executed or until the project is no longer under active consideration. In accordance with the Bid Review Procedure, the six bids for Contract T7380 were uploaded into a Department computer system along with the Department’s official estimate. A confidential algorithm identified outlier bids that were significantly outside the average (such as penny bids) and removed them to create a “statistical average” for each pay item. Astaldi’s unit pricing was then compared to the statistical average for each item. The computer program then created an “Unbalanced Item Report,” flagging Astaldi’s “mathematically unbalanced” items, i.e., those that were above or below a confidential tolerance value from the statistical average. The unbalanced item report was then reviewed by the district design engineer for possible quantity errors. No quantity errors were found.1/ The Department then used the Unbalanced Item Report and its computer software to cull the work items down to those for which Astaldi’s unit price was 75 percent more than or below the statistical average. The Department sent Astaldi a form titled “Notice to Contractor,” which provided as follows: The Florida Department of Transportation (FDOT) has reviewed your proposal and discovered that there are bid unit prices that are mathematically unbalanced. The purpose of this notice is to inform you of the unbalanced nature of your proposal. You may not modify or amend your proposal. The explanation of the bid unit prices in your proposal set forth below was provided by ASTALDI CONSTRUCTION CORPORATION on ( ) INSERT DATE. FDOT does not guarantee advanced approval of: Alternate Traffic Control Plans (TCP), if permitted by the contract documents; Alternative means and methods of construction; Cost savings initiatives (CSI), if permitted by the contract documents. You must comply with all contractual requirements for submittals of alternative TCP, means and methods of construction, and CSI, and FDOT reserves the right to review such submittals on their merits. As provided in section 5-4 of the Standard Specifications for Road and Bridge Construction you cannot take advantage of any apparent error or omission in the plans or specifications, but will immediately notify the Engineer of such discovery. Please acknowledge receipt of this notice and confirmation of the unit bid price for the item(s) listed below by signing and returning this document. Section 5.4 of the Bid Review Procedure describes the Notice to Contractor and states: “Contracts are not considered for award until this form has been signed and successfully returned to the Department per the instruction on the form.” State estimating engineer Greg Davis testified that the stated procedure was no longer accurate and “need[s] to be corrected” for the following reason: Since the procedure was approved back in 2011, we’ve had some subsequent conversations about whether to just automatically not consider the award for those that are not signed. And since then we have decided to go ahead and just consider the contract, but we are presenting a notice, of course, unsigned and then let the technical review and contract awards committee determine. Astaldi signed and returned the Notice to Contractor and noted below each of the ten listed items: “Astaldi Construction confirms the unit price.” Mr. Davis explained that the purpose of the Notice to Contractor form is to notify the contractor that items have been identified as extremely low and to ask the contractor to confirm its understanding that in accepting the bid, the Department will not necessarily approve design changes, methods of construction, or maintenance of traffic changes. Section 6.6 of the Contract Procurement Procedure sets forth the circumstances under which an apparent low bid must be considered by the Department’s Technical Review Committee (“TRC”) and then by the Contract Awards Committee (“CAC”). Those circumstances include: single bid contracts; re-let contracts; “significantly mathematical unbalanced” bids; bids that are more than 25 percent below the Department’s estimate; 10 percent above the Department’s estimate (or 15 percent above if the estimate is under $500,000); materially unbalanced bids, irregular bids (not prepared in accordance with the Standard Specifications); other bid irregularities2/; or “[a]ny other reason deemed necessary by the chairperson.”3/ Bids that are not required to go before the TRC and CAC are referred to as “automatic qualifiers.” Because it was mathematically unbalanced, the Astaldi bid was submitted to the TRC for review at its June 28, 2016, meeting. The TRC is chaired by the Department’s contracts administration manager, Alan Autry, and is guided by a document entitled “Technical Review Committees” (“TRC Procedure”). The TRC Procedure sets forth the responsibilities of the TRC in reviewing bid analyses and making recommendations to the CAC to award or reject bids. The TRC voted to recommend awarding Contract T7380 to Astaldi. The TRC’s recommendation and supporting paperwork was referred to the CAC for its meeting on June 29, 2016. The duties of the CAC are described in a document entitled “Contracts Award Committees” (“CAC Procedure”). Pursuant to the CAC Procedure, the CAC meets approximately 14 days after a letting to assess the recommendations made by the TRC and determines by majority vote an official decision to award or reject bids. Minutes for the June 29, 2016, CAC meeting reflect 21 items before the committee including: two single bid contracts; four bids that were 10 percent or more above the official estimate; one bid that was 15 percent or more above the official estimate on a project under $500,000; three bids that were more than 25 percent below the official estimate; and 11 bids with significantly unbalanced items, including Contract T7380 with an intended awardee of Astaldi. The CAC voted to award Contract T7380 based on the low bid submitted by Astaldi. A Notice of Intent to award the contract to Astaldi was posted on June 29, 2016. As noted at Finding of Fact 2, supra, Contract T7380 consisted of seven components: structures, roadway, signage, lighting, signalization, utilities, and intelligent transportation system. The Department does not compare bids by component, but looks at the total bid amount to find the lowest bidder. The Department also reviews the bids for discrepancies in individual unit items using the process described above. Astaldi’s bid of $48,960,013 was approximately $8.8 million below Prince’s bid of $57,792,043, $9.6 million less than Hubbard’s bid of $58,572,352, and $2.7 million below the Department’s public proposal budget estimate of $51,702,729. As part of its challenge to the intended award, Prince performed a breakdown of bids by individual components and discovered that nearly all of the differences between its bid and Astaldi’s could be attributed to the utilities component. Astaldi’s bid for the utilities component was $7,811,720, which was roughly $8.5 million below Prince’s utilities bid of $16,305,903 and $5.8 million below Hubbard’s utilities bid of $13,603,846.4/ The utilities component was included pursuant to an agreement between the Department and Hillsborough County, the owner of the water and sewer lines, relating to the improvement of water and sewer lines along the roadway limits of the project. The utility work consists of installing a new water- line and force main sewer. The existing water main and the existing force main conflict with the proposed location of the new storm drainage system. The new water main and force main must be installed, tested, and approved before being put into active service. To prevent water utility outages to customers, the new system must be installed and approved before the existing waterline and existing force main can be cut off and removed. Utility work is therefore the first task to be performed on Contract T7380. Once the utility component is completed, the contractor will furnish and install the stormwater system, the roadway, the bridgework, and all other components. Article 3-1 of the Standard Specifications5/ reserves to the Department the right to delete the utility relocation work from the contract and allow the utility owner to relocate the utilities. Utilities are the only portion of a Department contract subject to deletion because the funding is provided by the utility owner, which usually has allocated a certain dollar figure to contribute towards the contract prior to the bidding. If the bid for utilities comes in over the utility owner’s budget, the owner can opt out of the contract and self-perform. In this case, Hillsborough County had contracted with the Department to contribute $8.9 million for utility relocation work. The Department did not exercise the option to delete the utilities portion of the contract. Jack Calandros, Prince’s chief executive, testified that Prince uses a computer program called HeavyBid, created and supported by a company called HCSS, to build the cost components of its bids. Every witness with industry knowledge agreed that HeavyBid is the standard program for compiling bids in the construction field. Mr. Calandros testified that cost components include material quotes provided by third-party vendors and quotes from potential subcontractors. Labor and equipment costs are ascertained by using historical rates and actual cost estimates that are tracked by the HeavyBid software. Prince maintains its own database of costs derived from 20 years’ experience. Mr. Calandros stated that Prince’s internal labor and equipment rates are checked and adjusted at least once a year to ensure they are current and accurate based on existing equipment and personnel. Prince received three vendor quotes for the materials to perform the utility work on Contract T7380. In compiling its bid, Prince ultimately relied on a final quote from Ferguson Waterworks (“Ferguson”) of $8,849,850. Based on this materials quote and Prince’s overall utilities bid of $16,305,903, Mr. Calandros opined that it would not be possible for Astaldi to perform the utilities component for its bid amount of $7.8 million. Prince’s estimating expert, John Armeni, reviewed Astaldi’s bid file, read the deposition testimony of Astaldi’s chief estimator, Ed Thornton, and spoke to Mr. Thornton by telephone. Mr. Armeni also reviewed Prince’s bid and the bid tabulation of all bidders’ utilities component line items. Based on his review and his extensive experience in the industry, Mr. Armeni concluded that Astaldi’s bid does not include all costs for labor, material, and equipment necessary to construct the utilities portion of this project. Mr. Armeni reviewed the materials quote from Ferguson that Prince used in its bid. He noted that Astaldi’s bid file contained an identical quote from Ferguson of $8.8 million for materials, including some non-utilities materials. Mr. Armeni noted that the Ferguson quote for utilities materials alone was approximately $8 million, an amount exceeding Astaldi’s entire bid for the utilities portion of the project. Mr. Armeni also noted that Astaldi’s overall bid was 18 percent below that of the second lowest bidder, Prince. He testified that 18 percent is an extraordinary spread on a bid where the Department is providing the quantities and all bidders are working off the same drawings and specifications. Mr. Armeni believed that the contracting authority “should start looking at it” when the difference between the lowest and second lowest bidder is more than 10 percent. In his deposition, Mr. Thornton testified he was not aware of how Astaldi arrived at its bid prices for the utility section of the project. Mr. Thornton indicated multiple times that he was not Astaldi’s most knowledgeable person regarding the bid submitted by Astaldi on Contract T7380 project. He testified that Astaldi intended to subcontract the utilities work and acknowledged that the company received a subcontractor quote of $14.9 million after the bids were submitted. Mr. Thornton did not know if Astaldi had solicited the quote. He said it is not unusual for a company to receive subcontractor bids after it has been named the low bidder on a project. Mr. Thornton conceded that Astaldi’s bid did not include all the costs necessary to construct the utilities portion of Contract T7380. At his deposition, he did not have before him the materials needed to determine which items of cost Astaldi had omitted. Mr. Thornton testified that Astaldi was not missing any information it needed at the time of bid submission and understood that its price was to include all labor, materials, and subcontracting costs to perform the contract. After the proposed bid award, Astaldi used HeavyBid to produce a report indicating that the company now estimates its cost of performing the contract at $53,708,129.03, or roughly $4.75 million more than its winning bid. Mr. Thornton testified that Astaldi nonetheless stood ready to execute the contract and perform the work at its bid price. Central to the dispute in this case is Standard Specifications Section 9, “Measurement and Payment,” article 9-2 of which is titled “Scope of Payments.” In particular, subarticle 9-2.1 provides: 9-2.1 Items Included in Payment: Accept the compensation as provided in the Contract as full payment for furnishing all materials and for performing all work contemplated and embraced under the Contract; also for all loss or damage arising out of the nature of the work or from the action of the elements, or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the work until its final acceptance; also for all other costs incurred under the provisions of Division I. For any item of work contained in the proposal, except as might be specifically provided otherwise in the payment clause for the item, include in the Contract unit price (or lump sum price) for the pay item or items the cost of all labor, equipment, materials, tools and incidentals required for the complete item of work, including all requirements of the Section specifying such item of work, except as specially excluded from such payments. Prince contends that the second paragraph of subarticle 9-2.1 renders Astaldi’s bid nonresponsive because Astaldi admittedly failed to include “the cost of all labor, equipment, materials, tools and incidentals” in its bid. Prince points out that the “Technical Special Provisions” governing the utilities portion of the project reinforce the requirement that each bidder include all costs for the work. Technical Special Provisions Section 1-7.1 provides that “[p]ipe installation cost shall include all necessary work, equipment, and labor needed for installing the pipe, such as, coordination with existing utilities and support during construction and support of existing power poles during construction.” Technical Special Provisions Section 1-8.1 goes on to say that “[n]o separate payment will be made for the following items for work under this Technical Special Provision and the cost of such work shall be included in the applicable contract pay items of work,” followed by a comprehensive list of 30 items. Prince concludes that the requirement that each bidder include all costs, including costs of all necessary labor, equipment, and materials, in the Unit Price for each work item is “manifest” in the bid specifications and requires rejection of any bid that does not include all costs. Mr. Armeni opined that if one bidder excludes a portion of its costs, the other bidders are placed at a competitive disadvantage. Alan Autry, the Department’s central contracts administration manager, testified that five other projects were let as part of the bid package that included Contract T7380. He stated that it is typical for the Department to list multiple projects on one day. Mr. Autry’s office usually performs one bid letting per month, with the holiday months of November and December rolled together in a single letting. Mr. Autry stated that his office lets between 200 and 300 projects per year, not counting contracts that are let at the district level. Twenty other contracts were before the CAC at the June 29, 2016, meeting at which the Astaldi award in this case was approved. As noted at Finding of Fact 2, supra, Contract T7380 included 666 line items. Six companies submitted bids, meaning there were a total of 3,996 line items in this single contract. Assuming that the 200 to 300 other projects let by the Department’s Tallahassee office contain similar numbers, there are more than one million line items bid in any given year. If Prince’s reading of the bid specifications is correct, the Department is required to examine each of these line items and somehow make a determination whether the item includes all of the bidder’s costs. This problem of determining bidder cost is complicated by the presence of “companion” or “sister” items in bids, i.e., two items that must be considered in tandem to arrive at something like the actual cost of the work. Prince provided an example of such companion items in its analysis of the bids in this project. Two bid items included in the structures section of the bid proposal form were concrete culverts and reinforcing steel. The contractor may cast the culverts in place at the worksite or purchase them precast. If the concrete culvert is cast in place at the worksite, then reinforcing steel must be used to strengthen the culvert. If the concrete culvert is precast by a materials supplier, then the reinforcing steel has already been incorporated into the culvert at the time of installation. Mr. Calandros explained that when a contractor uses precast culverts, there is no need to list a separate additional cost for reinforcing steel; all costs are captured in the line item for concrete culverts. In this bid, Prince used precast culverts and therefore bid a penny per unit for reinforcing steel.6/ Bidders who cast the culverts in place showed a much higher cost for reinforcing steel but a lower cost for the concrete culverts. When the “companion items” were considered in tandem, the total cost for each vendor was fairly consistent. Prince’s explanation for companion items was coherent but did not explain how the Department is supposed to know which items are companion items as it undertakes the line-by-line cost examination of each bid in accordance with Prince’s reading of the bid specifications. Prince also failed to provide an explanation as to how the Department is to determine a bidder’s costs for any one line item or, for that matter, for its overall bid on a project. Bidders consider their cost information and the processes by which they build bids to be confidential proprietary information. In the instant case, Prince disclosed its own information (aside from materials costs) only under seal during litigation. In its ordinary course of business, the Department does not have access to this information. In fact, as noted at Finding of Fact 23, supra, the Department does not compare bids by component. It looks only at the total bid amount in determining the lowest bidder. Standard Specifications Article 3-8 reserves to the Department the right to perform an audit of the contractor’s records pertaining to the project upon execution of the contract. No authorization is provided to audit records of bidders prior to contracting. Standard Specifications Subarticle 2-5.1 allows bidders to indicate “free” or “$.00” for items that will be supplied at no cost to the Department. Though the Department’s practice, according to Mr. Autry, is to include zero bid items on the Notice to Contractor for confirmation of the price, subarticle 2-5.1 requires no Department investigation as to whether the bidder’s cost for a zero bid is actually zero. Bidders often bid a penny on items, as Prince did on reinforcing steel in this case. Standard Specifications Article 3-5 requires all contracts to be secured by a surety bond such that, in the event of a default by the contractor, the surety company will indemnify the Department on all claims and performance issues. Standard Specifications Section 4 provides that the scope of work is to be determined within the contract, including the furnishing of all labor, materials, equipment, tools, transportation, and supplies required to complete the work. The Department is authorized to make changes to the scope of work and make equitable adjustments of payments. If necessary, the Department may enter into supplemental agreements for additional or unforeseen work. Prince cautions that these change provisions could become relevant because Astaldi’s bid contains no information explaining how Astaldi will cover the $4.75 million difference between its bid price and its actual cost to perform the contract. Prince accurately states that nothing in Astaldi’s bid demonstrates that it has cash reserves to cover the loss and still complete the entire scope of the work.7/ Prince contends that this lack of demonstrable reserves renders Astaldi nonresponsible as to this project. Prince argues that it is error for the Department to rely on Astaldi’s certificate of qualification as proof of the company’s responsibility. The certificate of qualification process considers a contractor’s financial status at the time it submits its financial statements and other information regarding company resources. Prince contends that the Department’s assessment of the contractor’s financial statements and issuance of a certificate of qualification is insufficient to determine the contractor’s responsibility on a given bid. Prince argues that the Department is required by its governing statutes and the Standard Specifications to award a particular contract to the particular bidder that is the lowest, responsive, and responsible bidder, and that “responsible” for a given project is not synonymous with “prequalified.” Prince hypothesizes that under the Department’s practice, a bidder could possess a certificate of qualification issued in January, be indicted in another state for fraud and bribery in February, submit the lowest bid for a Department project in March, and be awarded the contract. By relying solely on the bidder’s certificate of qualification to determine responsibility, the Department could award a contract to a nonresponsible bidder. Section 337.14 provides that any person desiring to bid on any construction contract in excess of $250,000 must first be certified by the Department. Mr. Autry explained that the Department prequalifies contractors to submit bids on certain types of contract, such as major bridges and structures. Contractors applying for certification are required to submit their latest annual financial statements. The Department is charged with reviewing applications to determine “whether the applicant is competent, is responsible, and possesses the necessary financial resources to perform the desired work.” § 337.14(3), Fla. Stat. The Department assigns the contractor work classes and a total capacity after evaluating its experience and financials. The Department’s certificate is good for 18 months, though the contractor’s capacity is reviewed annually. At the time of a particular bid, the Department verifies the contractor’s available capacity, which is simply its total assigned capacity minus current work the contractor is performing for the Department. Mr. Autry testified that the Department does not go back and look at a bidder’s financials to determine whether it can sustain a loss on a given project. The Department does not repeat its capacity analysis during the year, regardless of how many projects the company bids on. The Department’s analysis is limited to whether the company’s current capacity is sufficient for the project on which it is bidding.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that the Department of Transportation enter a final order dismissing Prince Contracting, LLC’s, second amended formal written protest and awarding Contract T7380 to Astaldi Construction Corporation. DONE AND ENTERED this 22nd day of December, 2016, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of December, 2016.

Florida Laws (18) 1.01119.07120.52120.53120.54120.56120.569120.57120.68129.0320.23334.048337.015337.11337.14337.16337.164337.168 Florida Administrative Code (1) 28-106.217
# 3
DERICK PROCTOR vs DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 93-000263F (1993)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jan. 25, 1993 Number: 93-000263F Latest Update: Oct. 04, 1994

The Issue The issue in this cause is whether costs and attorney's fees are due Petitioner, hereinafter PROCTOR, from Respondent, hereinafter HRS, pursuant to Section 57.111, Florida Statutes, as a result of Division of Administrative Hearings Case Number 91-5963-BID, and, if so, the amount of costs and fees.

Findings Of Fact The petition for fees and costs herein is brought exclusively under Section 57.111, Florida Statutes, and relates back to a bid protest wherein PROCTOR and TCC #3 LTD., INC., hereafter TCC, were the only bidders on HRS lease 590.236. PROCTOR was the protestant/Petitioner and TCC was the apparent successful bidder/Intervenor in Derick Proctor v. Department of Health and Rehabilitative Services, DOAH Case No. 91-5963BID. HRS' Invitation to Bid (ITB) for lease 590:236 required bidders to submit evidence of control of the property being offered, including the parking areas. Evidence of control could take the form of a deed for the property, an option to purchase the property, or a lease or option to lease showing a right to sublease. TCC did not submit a document labelled "deed," "option to purchase," "lease," or "option to lease" with its bid. TCC submitted as its evidence of control a contract for sale and purchase of the property with Hernando Plaza, Ltd., executed by Edward M. Strawgate and Harold Brown representing themselves to be general partners of the limited partnership. At all times material, the actual record title of the property submitted by TCC for the bid was in the Victor and Lillian Brown Foundation. At the times of the bid opening, evaluation, and August 27, 1991 notice of intended award, HRS had no reliable information as to what entity actually owned the property offered by TCC, and TCC had not disclosed to HRS that its contract to purchase the property was with an entity other than the record owner. Up to then, at least, Hernando Plaza, Ltd. had represented itself to TCC as being the owner of the property. The ITB did not require an abstract of title to be submitted with the bid. HRS normally does not require an abstract from successful bidders, although the ITB contained provisions for future disclosures from successful bidders. Absent some reason to "go behind" facial evidence of control, HRS' ITB attempted at the time to protect HRS by requiring successful bidders to post an irrevocable letter of credit to be forfeited in the event a successful bidder could not perform and for future disclosures concerning the chain of title. (See the recommended order in the underlying case). HRS accepted the contract to purchase the property from Hernando Plaza, Ltd. as TCC's required evidence of control, believing it to constitute an option to purchase. (See Findings of Fact 15-17 infra, this final order). On August 27, 1991, PROCTOR received from HRS a notice of intent to award the bid to TCC. This notice constituted the "window" for protests, if any, to be filed. PROCTOR then timely filed a notice of intent to protest and a formal written protest of the award to TCC. The filing of this protest resulted in an automatic suspension of the bid solicitation and contract award process and referral of the matter to the Division of Administrative Hearings, pursuant to Section 120.53(5)(c), Florida Statutes. This protest formed the basis of the underlying bid case, DOAH Case No. 91-5963BID. No later than the time of the Prehearing Order of September 23, 1991 in Case No. 91-5963BID, the law firm of Gibbs and Rudzik had made known to the hearing officer and counsel for both PROCTOR and HRS its retention as counsel for TCC. TCC moved for leave to intervene in a motion filed September 30, 1991, which was granted in an order of October 4, 1991. In a letter of October 10, 1991, counsel for PROCTOR made counsel for HRS aware of a question of whether TCC could obtain good title to the property. Counsel for PROCTOR proposed in a letter of October 14, 1991 to counsel for HRS that HRS reject both PROCTOR's and TCC's bids and rebid the lease, but this letter was primarily devoted to determining if HRS wished to interpose a new defense that PROCTOR's bid was unresponsive. In the instant fees and costs case, PROCTOR relies on its October 14, 1991 letter as the point from which HRS should have acted to avoid incurring attorney's fees and costs. After the receipt of the two letters, HRS did not reject both bids and rebid the contract but proceeded to formal hearing on October 30, 1991. PROCTOR and HRS share the mutual impression that had HRS accepted PROCTOR's proposal to reject both bids, HRS would have to have allowed TCC an opportunity to protest that decision. At the final hearing in Case No. 91-5963BID, evidence was offered that Hernando Plaza, Ltd. had a conditional option to purchase the property from the record title owner, the Brown Foundation. However, it was not established at the hearing that the conditions of the option had been fulfilled or that TCC or Hernando Plaza, Ltd. could otherwise gain good title to the property through a valid option. It was concluded as a matter of law in Case No. 91-5963BID, that on its face, the ITB stated that control could be evidenced merely by attachment of an "option to purchase," that the ITB stated no further requirements concerning the internal provisions of the option to purchase, and that TCC's conditional contract for purchase constituted a conditional option to purchase. The conditions of the option to purchase and the chain of title, among myriad other matters were subjects of proof at the formal hearing. The conditions of the option to purchase and various complicated real property concepts arising from recorded and unrecorded parts of the chain of title constituted the thrust of the recommended order's assessment that TCC's "control" was speculative only. It is here noted that the totality of the "chain" of title might have been unavailable even by "abstract" due to the lack of recordation of some documents. The lengthy formal hearing adduced evidence concerning the factual issue of whether or not the conditional option to purchase was between TCC and an entity which had such a sufficiently unequivocal interest in the proposed property that it could convey title to TCC in time for TCC to fulfill its obligations under its proposed lease to HRS. There is no evidence that HRS knew of these problems on August 27, 1991, when it gave notice of its intent to award the bid to TCC. Hernando Plaza, Ltd. was the entity with which TCC had contracted. At formal hearing, TCC relied on the legal concept that all interests in the property had merged in the non-title holder, Hernando Plaza, Ltd. This concept, together with recorded and unrecorded elements in the chain of title which were presented at formal hearing, were determined in the recommended order to be too "speculative" on the issue of TCC's control. However, it was also found, upon evidence submitted at formal hearing, that TCC's bid contained no other material deviations from the requirements of the ITB, that the signator of TCC's bid had sufficient status to submit the bid for the TCC corporation, and that TCC's signator could not submit the bid as an agent of the owners of the real property. TCC and its bid signator had never purported to have submitted the bid on behalf of the owners of the real property. (See the recommended order of the underlying bid case.) These issues were raised by PROCTOR and they addressed more than just the facial compliance of TCC's original bid documents which was all HRS had to consider when it made its initial decision in favor of TCC and against PROCTOR. However, the recommended order found HRS to have materially deviated in a number of ways from the bid process in its initial evaluation of PROCTOR's bid, not the least of which was determining that PROCTOR had complied with the ITB requirements for demonstrating control. All such evaluation flaws had been committed by HRS in favor of PROCTOR. Both TCC's and PROCTOR's bids were ultimately found to be unresponsive in the recommended order entered on December 20, 1991. The recommended order also found both had standing to be involved in the bid protest and formal hearing. The recommended order recommended rejecting both bids and readvertising the ITB. The Final Order of HRS entered on January 20, 1992 dismissed PROCTOR's protest on the basis that he lacked standing to protest, as his bid was unresponsive, and awarded the bid to TCC. HRS did not give PROCTOR notice that his bid was not responsive until it issued its Final Order. The Final Order of HRS was appealed to the First District Court of Appeals by PROCTOR. The First District Court of Appeals entered an order on June 22, 1992 finding PROCTOR had standing and remanding the case back to HRS for the purpose of a decision of the issue of whether TCC's bid was also unresponsive. On July 27, 1992, HRS entered its Amended Final Order determining both bids to be unresponsive and that the lease should be relet for bids. The First District Court of Appeals affirmed the Amended Final Order of HRS in a per curiam opinion without discussion on October 13, 1992. HRS did not reject both bids and rebid the contract until after this per curiam opinion. No motion for rehearing was filed with respect to either of the First District Court of Appeals' orders entered June 22 or October 13, 1992, nor was any notice to invoke the discretionary jurisdiction of the Supreme Court filed. PROCTOR did file a motion for rehearing solely on the court's denial of PROCTOR's motion for appellate fees. Mandate was issued by the Clerk of the First District Court of Appeals on December 3, 1992. HRS entered an Order Directing Release of Bid Protest Cost Bond on December 18, 1992, in which HRS stated: Petitioner, Derick Proctor, has prevailed in the above styled bid protest. Petitioner's domicile and principal place of business is Vero Beach, Florida. Petitioner has one employee. Petitioner is a sole proprietorship. Petitioner's net worth does not exceed $2,000,000.00. HRS was not a nominal party in the underlying bid case. HRS did not initially challenge PROCTOR's "small business party" status in this instant fees and costs proceeding. Therefore, that allegation of the fees and costs petition is not at issue. Also, Petitioner's "small business party" status is now stipulated to exist. The parties have stipulated that the maximum statutory fee is $15,000.00 and that $15,000.00 is a reasonable fee if an award of attorney's fees is due. HRS has not protested or objected to the amount of costs claimed, $411.25, if costs are due.

Florida Laws (4) 120.53120.57120.6857.111
# 4
CON-AIR INDUSTRIES, INC. vs SEMINOLE COUNTY SCHOOL BOARD, 98-004714BID (1998)
Division of Administrative Hearings, Florida Filed:Sanford, Florida Oct. 27, 1998 Number: 98-004714BID Latest Update: Jan. 20, 1999

The Issue Whether the School Board of Seminole County's, notice of intent to award Bid No. 102589, for air filter maintenance, service, and replacement to Filter Service and Installation Corporation was clearly erroneous, contrary to competition, arbitrary, or capricious.

Findings Of Fact The Seminole County School District is a political subdivision of the State of Florida, created by Article IX, Section 4, Florida Constitution. The powers and duties of the school board are enumerated in Chapter 230, Florida Statutes. The Superintendent of the Seminole County School District is a constitutional officer, whose office is created by Article IX, Section 5, Florida Constitution. The powers and duties of the Superintendent are enumerated in Chapter 230, Florida Statutes. The Seminole County School Board issued a call for bids for air filter maintenance service and replacement under Bid No. 102589 on September 14, 1998. Bids were submitted by Con-Air Industries, Inc., the protester, and Filter Service & Installation Corp., the apparent low bidder. The bids were opened on September 28, 1998, and were evaluated. Each bidder was determined to be a responsible bidder to the CFB. Intervenor submitted the lowest numerical bid. On October 1, 1998, Respondent's staff recommended that the CFB be awarded to Intervenor. The decision to recommend the award of the filter service Bid No. 102589 complies with the bid specifications. The instructions to bidders, as stated on the Proposal Form, direct a bidder to total lines A-C and to enter the total at line D. The instructions state that a bidder is not to include the cost as stated at lines E & F in the total. The proposal form then states that the total cost, as stated at line D shall be used to determine the apparent low bidder. The bid proposal document stated that the total of the prices stated at items A, B, and C would be used to determine the lowest numerical bid. The bid proposal document stated that the Respondent reserves the right to negotiate unit cost proposed for item E. The line D total submitted by the Petitioner is stated at $3.45. The line D total submitted by the apparent low bidder, is stated at $2.60. Intervenor submitted the lowest numerical bid. Intervenor does business under the fictitious name Filter Sales & Service. That fictitious name has been registered with the Secretary of State for the State of Florida. Filter Service & Installation Corp., and Filter Sales & Service are one and the same. The reference by Intervenor at line F to "Per Price Sheet" and the failure of Filter Service & Installation Corp. to attach a price sheet to its proposal form is not a material deviation from the requirements of the bid specifications. The total at line D is the total used to determine the lowest bidder. Filter Service & Installation Corp. is the lowest and best bid from a responsive and responsible bidder. The Petitioner followed the procedure set forth in the bid proposal document in making a determination that the Intervenor was the lowest numerical bidder. Petitioner reserved the right to reject all bids and to waive any informalities. Petitioner failed to prove that the notice of intent to award the bid to Intervenor was clearly erroneous, contrary to competition, arbitrary, or capricious.

Recommendation Upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Respondent award the contract for filter maintenance, service, and replacement under Bid No. 102589 to the Intervenor, Filter Service and Installation Corp., as recommended by its staff. DONE AND ENTERED this 11th day of December, 1998, in Tallahassee, Leon County, Florida. DANIEL M. KILBRIDE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 11th day of December, 1998. COPIES FURNISHED: Robert N. Hering, President Con-Air Industries, Inc. 3055 Pennington Drive Orlando, Florida 32804 Ned N. Julian, Jr., Esquire Seminole County Public Schools Legal Services Department 400 East Lake Mary Boulevard Sanford, Florida 32773-7127 Robert W. Smith, Esquire 430 North Mills Avenue, Suite 1000 Orlando, Florida 32803 Dr. Paul J. Hagerty, Superintendent Seminole County Public Schools 400 East Lake Mary Boulevard Sanford, Florida 32773-7127

Florida Laws (1) 120.57
# 5
SYNERGY GAS CORPORATION vs BROWARD COUNTY SCHOOL BOARD, 91-007494BID (1991)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Nov. 20, 1991 Number: 91-007494BID Latest Update: Mar. 18, 1992

The Issue The issue for consideration in this matter is whether the School Board of Broward County properly awarded Bid 92-143T for the procurement of propane gas for the school system for three years.

Findings Of Fact In August, 1991, the School Board of Broward County issued ITB's to various potential suppliers to supply it with liquid propane gas, (LP gas), for the next three years, under ITB number 92-143T. The current supplier under the contract let in 1989 is the Petitioner herein, Synergy. Synergy was one of the potential suppliers to receive a copy of the Board's new ITB. Paragraph 12 of the Special Bid Conditions required any protest of the specifications or conditions of the ITB to be filed within 72 hours of its receipt. Paragraph 15 of the Special Conditions allowed prospective bidders to address questions concerning the ITB to the Board's purchasing department. That agency's activity was limited to referring the inquirer to bid provisions which they could read and interpret for themselves. No Board employee was authorized to interpret any portion of the ITB or to release any information regarding requirements other than was contained in the written bid document. That Special Condition also notified prospective bidders that any official interpretations of the bid documents or its requirements, if necessary, would be communicated to the bidders in writing. The ITB was mailed on August 19, 1991 and bid opening was noticed therein to be at 2:00 pm on October 2, 1991 at the Board's purchasing department. The ITB was mailed to Synergy's Hollywood, Florida office and was, from there sent to the head office in New York. Mr. Garey, the responsible individual in Synergy's marketing department believes he received it on or about August 25, 1991. The general and special conditions and specifications of this ITB were, for the most part and as pertinent here, identical to those set forth in the 1989 ITB except that the current bid calls for delivery of the gas to the Board at specified locations which was not required in the prior contract. Shortly after receiving the ITB, Joel Garey, a long time employee of Synergy, who has prepared thousands of bids for government procurements, because gas prices were widely fluctuating, began to collect data on the price of LP gas preparatory to formulating Synergy's bid. Shortly before the bid was due, based on the latest available price information, Mr. Garey prepared Synergy's bid for the signature of Jeffrey Vogel, Synergy's vice president. The first bid prepared by Mr. Garey contained an error on the bid summary sheets. When, on October 1, 1991, one day before the bid was due, he noted what to him was an inconsistency in the bid specifications which, at paragraph 13, called for the bidder to deliver "full 100# tanks [of LP gas]," and to price invoice tickets, "with the conversion rate of 22 gallons per cylinder shown." The Board also wanted the filling of several 40# tanks for which delivery tickets and invoices, "will be in gallons based on the standard of 4.24 pounds per gallon." The parties agree that the accepted weight of a gallon of liquid propane gas weighs 4.24 pounds. Extrapolating from that point, Mr. Garey reasoned that if the Board wanted its tanks "filled to capacity", the 100# tanks would take 23.5 gallons of LP gas, (100 divided by 4.24), and the 40# tanks would take 9.43 gallons, (40 divided by 4.24). As a result, and being somewhat confused, Mr. Garey telephonically contacted the Board's contact point, Mr. Toman, who referred him to Mr. Combs, another Board official. Mr. Combs, notwithstanding the weight of 4.24 lbs/gal for LP gas listed in the Board's specifications, would not accept that figure from Mr. Garey without independent proof. Mr. Combs gave Mr. Garey his fax number so the proof could be sent when available and, in the meantime, said to fill the tanks to capacity. When he hung up from talking with Mr. Combs, Mr. Garey called his local manager and determined that under the 1989 contract which Synergy had with the Board, it had been filling the Board's tanks to capacity. When he called Mr. Tomans back at 4:00 PM that same day, Garey was told that Tomans had not heard from Combs about the problem, but that Garey should submit his bid timely or be out. Tomans also wanted to know why the issue had not been raised during the existing contract. Mr. Garey had no answer to that question. Based on the information he then had, Mr. Garey changed Synergy's bid and submitted one based on full tanks rather than the 22 and 6 gallons, respectively, mentioned in the bid specifications. Coincidentally, the bid as submitted was still in error in that Item C of the bid specs misstated the price per gallon delivered and this error was reflected in Items D, E, and G, and, ultimately, the total. This error was corrected, however, and did not play in the Board's decision to reject the Petitioner's bid. In arriving at Petitioner's bid based upon the "totally full" basis, Mr. Garey computed using the 23.5 and 9.43 gallon capacity cost divided by the 22 and 6 gallon conversion figures dictated by the Board. Mr. Garey was subsequently advised that Synergy was not the successful bidder. He also determined, from a telephone conversation with Mr. Tomans on October 3, 1991, that had the Petitioner's bid price not been raised to accommodate the larger volume, it's bid price would have been lower than that submitted by the successful bidder, Peoples Gas. During that conversation, Mr. Tomans advised Mr. Garey that ordinarily a bidder had 72 hours from receipt of the ITB to protest the specifications, but since there was some merit to Petitioner's contentions of an inconsistency regarding volume, he, Tomans, felt there should be an exception. However, Special Condition 15 specifically cautions prospective bidders it could not rely on any information given orally by Respondent and must submit any questions as to the bid consistent with the terms of General Condition 7. Mr. Garey admits he was remiss in not reading the fine print of paragraph 7 of the ITB and the protest provisions but on the afternoon of October 1, 1991, when he discovered the discrepancy, he immediately called the school board. If at that time they had told him he was too late to protest the specifications, this would have satisfied him and he would not have filed an appeal or protest. Instead, he was told that due to the merit of his argument he could protest, and he did so. His letter of protest was accepted even though not timely and the matter was brought to a hearing before the school board which ruled against Synergy on grounds other than time. He contends that the executive summary prepared for the school bard misled it into rejecting his protest. Mr. Garey also asserts that the bids were so close, if the margin had been greater than the discrepancy in the number of gallons to go into the cylinders he would have accepted the loss. Here, however, the total discrepancy is accounted for by the 3,770 gallons difference out of over 300,000 gallons. Mr. Arthur Hanby is the Director of Purchasing for the Broward County School Board and is familiar with this procurement and Synergy's bid. The provision in the ITB which provides for questioning of specifications was designed to comply with the requirements of Florida Statutes and the school board's policy. It is put in to equalize the opportunity for all prospective bidders to protest on an equal basis. It has been used by others in the past and when invoked, the bid solicitation process has been suspended until resolution of the matter in question. Mr. Hanby was also employed by the school board when the prior contract for propane was let with essentially the same specifications as are in issue here. The conversion rate was changed this year to more accurately reflect the market place. Even then no challenge was filed to the bid specifications. No written inquiry was received as to how to interpret them either, and at no time since Synergy, the winner then, has had the contract has it shown any confusion at to what it was to provide. Penny Good, General Manager for Peoples Gas, and the individual who prepared that company's bid read the bid solicitation thoroughly before preparing her company's bid. She was also employed with Peoples Gas when the prior contract was bid but had nothing to do with the bid at that time. She claims to have had no confusion as to what the school board wanted on this solicitation. She asked no questions of the school board because it was clear to her and she was satisfied the board wanted 22 gallons in a 100 # tank and 6 gallons in a 40 # tank, less than a tank filled to capacity. As she understands the business, there is no such thing as a "legal limit" on a tank. Admitting that an empty 100# tank would hold 23.5 gallons, which, practically, would be the maximum amount it could hold, it is easy to put less than 22 gallons in a 100# tank and less than 6 gallons in a 40 # tank. Under the terms of the agreement, tanks would not be filled on site. Empty tanks would be picked up and replaced with other tanks filled with either 22 gallons or 6 gallons as pertinent. From a review of all the evidence, it is clear that Synergy and Peoples Gas were not bidding the same thing. The quantity's to be provided were different and this accounts for the difference in bid price.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that a Final Order be entered denying Petitioner's protest of the Board's award of Bid No. 92-143T to Peoples Gas Company, and denying Peoples Gas Company's request for an award of costs and attorney's fees. RECOMMENDED in Tallahassee, Florida this 24th day of January, 1992. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of January, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 91-7494-BID The following constitutes my specific rulings on all Proposed Findings of Fact submitted by the parties to this proceeding under Section 120.59(2), Florida Statutes. FOR THE PETITIONER: & 2. Accepted and incorporated herein. Accepted and incorporated herein. Accepted and incorporated herein. & 6. Accepted and incorporated herein. & 8. Accepted and incorporated herein. Accepted but more a comment on the state of the evidence. Accepted. Not a proper Finding of Fact. & 13. Accepted. & 15. Rejected as not Findings of Fact but more Conclusions of Law. Accepted but Synergy's bid is not responsive to the Bid specifications. Rejected. Not a Finding of Fact. FOR THE RESPONDENT AND INTERVENOR: 1. & 2. Accepted and incorporated herein. 3. & 4. Accepted and incorporated herein. 5. - 8. Accepted and incorporated herein. & 10. Accepted and incorporated herein. Accepted and incorporated herein. Accepted and incorporated herein. - 15. Accepted and incorporated herein. Not a Finding of Fact but a restatement of the evidence. Accepted. Accepted and incorporated herein. & 20. Not Findings of Fact pertinent to the issues herein. COPIES FURNISHED: Joel Garey Marketing Department Synergy Gas Corporation 23102 Sandalfoot Plaza Drive Boca Raton, Florida 33428 Joel Garey Synergy Gas Corporation 175 Price Parkway Farmingdale, N.Y. 11735 Edward J. Marko, Esquire Suite 201 Victoria Park Centre 1401 East Broward Blvd. Post Office Box 4369 Fort Lauderdale, Florida 33338 Arthur S. Hamby, Jr. Director Purchasing and Warehousing Broward County School Board 1320 Southwest Fourth Street Fort Lauderdale, Florida 33312-7535 James L. Brady Director Business Affairs Broward County School Board 1320 Southwest Fourth Street Fort Lauderdale, Florida 33312-7535 Peoples Gas Company 2700 Southwest Second Avenue Fort Lauderdale, Florida 33315 Jeffrey R. Sonn, Esquire Mishan, Sloto, Hoffman & Greenberg Suite 2350 Southeast Financial Center 200 South Biscayne Boulevard Miami, Florida 33131 Virgil L. Morgan, Superintendnet School Board of Broward County 1320 Southwest Fourth Street Fort Lauderdale, Florida 33312-7535 Sydney H. McKenzie, General Counsel Department of Education The Capitol, PL-08 Tallahassee, Florida 32399-0400

Florida Laws (1) 120.57
# 6
INDUSTRIAL ENTERPRISES SANDBLAST AND PAINTING, INC. vs. DEPARTMENT OF TRANSPORTATION, 85-003592BID (1985)
Division of Administrative Hearings, Florida Number: 85-003592BID Latest Update: Dec. 11, 1985

Findings Of Fact Based upon the documentary evidence received and the entire record compiled herein, I hereby note the following findings of fact: Notice and Invitation to Bid on State Project Number 72001-3448 (the project) was extended to various contractors by the Respondent, Department of Transportation, on August 1, 1985. Sealed bids on the project were opened August 28, 1985. The scope of the project involved cleaning and painting the structural steel of the Buckman Bridge over the St. Johns River in Jacksonville, Florida. (State Bridge Numbers 720249 and 720343). The bids were opened and Petitioner was the apparent low bidder on the project with a bid amount of $193,000. The Department of Transportation, on October 2, 1985, rejected all bids "due to error in quantities in plans." According to the contract plans and specifications utilized by the Department of Transportation for the project, the beams, girders, bracing and trusses were composed of 2,540 tons of structural steel. The plans were in error and the tonnage of structural steel was less than 2,540 tons. Petitioner, upon visiting the job site as required, immediately recognized that there was less steel in the bridge than shown in the plans. In submitting and formulating his bid, the Petitioner considered the amount of work and materials which would actually be required to complete the project. 6 Prior to the bids being posted on the project, the Department of Transportation discovered that the amount of structural steel noted in the plans was grossly overestimated. On October 2, 1985, the Department of Transportation notified bidders in writing that all bids submitted on the project were rejected and that the plans would be revised and the project relet.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is, RECOMMENDED that the petition of Industrial Enterprise Sandblast and Painting, Inc., protesting the rejection of all bids on State Project No. 72001- 3448, be dismissed. DONE AND ORDERED this 11th day of December 1985 in Tallahassee, Florida. W. MATTHEW STEVENSON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of December 1985. APPENDIX Respondent's Findings of Fact FINDING RULING Accepted; see Recommended Order paragraph 1. Accepted; see Recommended Order paragraph 2. Accepted, but not included because subordinate. Accepted; see Recommended Order paragraph 4. Accepted; see Recommended Order paragraphs 3 and 6. Accepted; see Recommended Order paragraphs 3 and 6. Accepted; see Recommended Order paragraph 6. COPIES FURNISHED: HONORABLE THOMAS E. DRAWDY, SECRETARY DEPARTMENT OF TRANSPORTATION HAYDON BURNS BUILDING TALLAHASSEE, FLORIDA 32301 A. J. SPALLA, ESQUIRE GENERAL COUNSEL DEPARTMENT OF TRANSPORTATION 562 HAYDON BURNS BUILDING TALLAHASSEE, FLORIDA 32301 LARRY D. SCOTT, ESQUIRE DEPARTMENT OF TRANSPORTATION HAYDON BURNS BUILDING, M.S. 58 TALLAHASSEE, FLORIDA 32301-8064 INDUSTRIAL ENTERPRISE SANDBLAST & PAINTING, INC. P. O. BOX 1547 1502 FOX RUN DRIVE TARPON SPRINGS, FLORIDA 32486-1547

Florida Laws (2) 120.57337.11
# 7
SWEEPING CORPORATION OF AMERICA, INC. vs DEPARTMENT OF TRANSPORTATION, 91-008230BID (1991)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Dec. 26, 1991 Number: 91-008230BID Latest Update: May 01, 1992

Findings Of Fact Based upon the oral and documentary evidence adduced at the final hearing and the entire record in this proceeding, the following findings of fact are made. On October 11, 1991, DOT's District Four office let out for bid district contracts E4551 and E4554. Contract E4551 calls for the mechanical sweeping of Interstate 95 in Broward County. Contract E4554 calls for the mechanical sweeping of Interstate 95 in Palm Beach County. At a mandatory pre-bid conference, the bidders for the Contracts were provided with a packet which included a Notice to Contractors and Standard Specifications. The Notice to Contractors is a four page document which is specific to each contract. The Standard Specifications are the same for all district contracts. Both the Notice to Contractors and the Standard Specifications to the bidders required bidders to submit proof of the ability to acquire a performance and payment bond in an amount equal to the contract bid price. Bidders could satisfy this requirement by submitting a bid guarantee of 5% of the bid, submitting a notarized letter of intent from a bonding company or by providing a Certificate of Qualification issued by Respondent. The Notice to Contractors for both Contracts provided as follows: Failure to provide the following with each bid proposal will result in rejection of the contractor's bid.... District contracts of $150,000 or less require the following as proof of ability to acquire a performance and payment bond: A notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a performance and payment bond in the amount of your bid, should your firm be awarded the project; in lieu of a notarized letter the following may be substituted: (1) a bid guarantee of five percent (5%); or (2) a copy of the Contractor's Certificate of Qualification issued by the Department. (No emphasis added) Similarly, the first Standard Specification provides: 1.1 Bidders (contractors) A contractor shall be eligible to bid on this contract if:... (2) Proof of ability to acquire a performance and payment bond in an amount equal to the contract bid price is provided to the District Contract Administrator with the bid proposal. As such proof all bids must be accompanied by a notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a bond in the amount of your bid, should your firm be awarded the project.... The requirement to submit proof of the ability to acquire a performance and payment bond has been imposed on the Districts by DOT Directive 375-00-001-a (hereinafter the "Directive".) This Directive was in place at all times material to this proceeding. Section 3.2.2 of the Directive provides: A contractor shall be eligible to bid if: ...Proof of ability to acquire a performance and payment bond in an amount equal to the contract bid price is provided to the minicontract administrator with the bid proposal. As such proof all bids must be accompanied by a notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a bond in the amount of the bid, should the firm be awarded the project. A bid guaranty as specified above may substitute as proof of ability to obtain a performance and payment bond. This applies to bids amount over or under $150,000. A copy of the Contractor's Certificate of Qualification issued by the Department may be substituted in lieu of a notarized letter for those contracts not requiring a bid bond. The bids for the Contracts were opened on October 11, 1991 in Fort Lauderdale, Florida. Bids were received from four bidders: CPM, SCA, Florida Sweeping, Inc. and P. F. Gomez Construction Co., Inc. In its bid proposals, SCA included executed bid bonds in an amount sufficient to cover the amount of each bid proposal. Each bid bond cost $55.00. CPM did not submit executed bid bonds with its proposals. Instead, CPM submitted letters from Mark A. Latini dated September 25, 1991. Those letters were provided on the stationery of Bonina-McCutchen-Bradshaw, Insurance and indicate that Mr. Latini is the "bond manager." The letters provide as follows: Amwest Surety Insurance Company is the surety for the above-referenced contractor and stands ready to provide the necessary performance and payment bond for the referenced bid should Certified Property Maintenance, Inc., be low and awarded the referenced contract. All bonds are subject to normal underwriting requirements at the time of the bond request.... The letters submitted by CPM with its bid proposals were not notarized and were not binding obligations to issue bonds since they were conditioned upon meeting certain unspecified underwriting requirements at the time of the bond requests. The submitted bids were reviewed by the District Four Contractual Services Office. The bids submitted by CPM were the lowest for each contract. Its bid for Contract No. E4551 was $109,343.97. Its bid for Contract No. E4554 was $30,312.63. SCA's bids for the Contracts were $139,442.14 and $44,100.00, respectively. During the initial review of the bid proposals, the Contractual Services Office rejected CPM's bids for failure to have its bonding company "letters of intent" notarized. In addition, the bid proposals submitted by Florida Sweeping, Inc. were rejected for failure to note a required addendum and the bids submitted by P. F. Gomez Construction Co., Inc. were rejected because the "proposal bond was not of proper character". On October 18, 1991, DOT posted its Notice of Intent to Award the Contracts to SCA, the only bidder for the Contracts whose proposals had not been rejected. CPM timely filed protests of the proposed awards to SCA on October 22, 1991. The protests filed by CPM argued that its bids should not have been invalidated simply because the bonding company's letters did not include notary seals. At this point, the sole basis for the disqualification of CPM's bids was the failure to have the bonding company letters notarized. Respondent contends that, except for the absence of the notary seal, the letters submitted by CPM met the requirements of the Notice to Contractor and the Standard Specifications cited above. However, those letters are equivocal and do not evidence a binding commitment to issue a bond upon award of the contract. The DOT officials admit that they do not know what "normal underwriting requirements" would or could be required by CPM's bonding company. This conditional language makes it uncertain whether CPM could obtain the necessary bond. Therefore, it is concluded that those letters do not meet the requirements of the Notice to Contractors, the Standard Specifications or the Directive. A hearing on CPM's protest was not held. CPM's president, Raymond Hanousek, who prepared CPM's bid and attended the pre-bid meeting, called DOT's District office the day the bids were opened and was informed that his company's bid was low, but was rejected because its bond commitment letter was not notarized. Mr. Hanousek spoke with Joseph Yesbeck, the District's Director of Planning and Programs. After their conversation, Mr. Yesbeck reviewed the file and met with Teresa Martin, the District's contract administrator for construction and maintenance contracts, and other members of the contracting staff. Ms. Martin explained why CPM's bid had been disqualified, and the matter was thereafter discussed with the District and Department attorneys. After reviewing the situation, Mr. Yesbeck determined that the failure to submit notarized letters should be considered a non-material deviation and the bids submitted by CPM should be accepted and considered the low responsive bids. Mr. Yesbeck concluded that the absence of the notary seal did not give any competitive advantage to CPM and that defects of this nature are routinely allowed to be cured. Therefore, he reversed the contract administrator's decision to disqualify CPM on both Contracts. The District secretary concurred in the decision reached by Mr. Yesbeck to repost the award of the Contracts. Mr. Yesbeck prepared a joint letter of reposting which removed CPM's disqualification and declared CPM to be the low bidder for both Contracts. At the time Mr. Yesbeck made his decision, he had not reviewed the Directive from the Assistant Secretary's office stating that there must be a notarized letter showing proof of ability to obtain a performance and payment bond. Mr. Yesbeck did not review the Directive until his deposition was taken one week prior to the hearing in this case. According to Ms. Martin, the option to provide a notarized letter from a bonding company as an alternative to the posting of a 5% bid guarantee or obtaining prequalification was designed to promote participation in state contracting by small business and minority business enterprise applicants. While DOT was apparently trying to make it easier and cheaper for companies to bid by not requiring a bond to be posted, the DOT Directive and the bid documents still clearly required unconditional proof that a bid bond would be issued if the contract was awarded to the bidder. CPM was not prequalified nor did it post a bond. Thus, in order to meet the requirements of the Notice to Contractors and the Standard Specifications, CPM's only option was to submit a notarized letter showing proof of ability to obtain a performance and payment bond. DOT was never provided with any proof that CPM had been prequalified by the bonding company for a bond and/or that a bond would unconditionally be issued if CPM was awarded the Contracts. Because the letters stated they were "subject to normal underwriting requirements at the time of the bond request", there was some possibility CPM would not be able to obtain a bond. Such a condition was not permissible under the bid doucments. The decision to accept CPM's bid was contrary to the DOT Directive, the Notice to Contractors and the bid specifications which require that a bidder demonstrate proof of ability to obtain a performance and payment bond. Consequently, it is concluded that DOT's decision to accept the conditional, unnotarized letters submitted by CPM was arbitrary and capricious. There is some indication that other DOT Districts have, on occasion, waived the notarization requirement for the bond letter. However, it is not clear whether the language in the bid documents was the same or similar in those cases and/or whether the bond letters were conditional. In the past, whenever District Four has gotten a bid without a notarized bond letter, the bid was rejected. Apparently, there has never been a protest based on such a denial in District Four. Under Section 337.18, DOT does not need to require notarized, unconditional bond letters on contracts under $150,000. Indeed, there was a suggestion that some DOT Districts have dropped the requirement for certain contracts under $150,000. However, the bid documents in this case clearly required some proof that the bidder could acquire a performance and payment bond upon award of the Contracts. It was incumbent for all bidders to meet this requirement. It was arbitrary to delete this requirement after the bids were submitted.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner enter a Final Order finding the bids submitted by CPM to be non-responsive and rejecting those bids. Petitioner should enter into negotiations with SCA regarding the award of the contract. In the absence of a favorable negotiation, Petitioner should enter a Final Order rejecting all bids and opening the Contracts up for new bids. DONE and ENTERED this 24th day of March, 1992, at Tallahassee, Florida. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of March, 1992.

Florida Laws (8) 120.53120.57120.68287.012287.057337.11337.18343.97
# 8
MARPAN SUPPLY COMPANY, INC. vs DEPARTMENT OF MANAGEMENT SERVICES, 96-002777BID (1996)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jun. 11, 1996 Number: 96-002777BID Latest Update: Nov. 26, 1996

The Issue The issue for determination is whether Respondent acted fraudulently, arbitrarily, illegally, or dishonestly in selecting Intervenor as the lowest bidder for a contract to supply the state with lamps valued at $3,692,499.

Findings Of Fact The Parties Respondent is the state agency responsible for soliciting bids to establish a contract for the purchase of large lamps by state agencies and other eligible users. Petitioner is a Florida corporation and the incumbent vendor under similar contracts for the preceding 10 years. Petitioner does not manufacture lamps. Petitioner sells lamps manufactured by Osram-Sylvania ("Sylvania"). Intervenor is an Ohio corporation doing business in Florida. Intervenor manufactures the lamps it sells. The ITB On March 15, 1996, Respondent issued Invitation To Bid Number 39-285- 400-H, Lamps, Large, Photo and STTV (the "ITB"). The purpose of the ITB is to establish a 24 month contract for the purchase of Large Lamps (fluorescent, incandescent, etc.), Photo Lamps (audio visual, projection, flash), and Studio, Theatre, Television, and Video Lamps ("STTV") by state agencies and other eligible users. The contract runs from July 10, 1996, through July 9, 1998. The ITB estimates the contract price at $3,692,499. The ITB contains General and Special Conditions. General Conditions are set forth in 30 numbered paragraphs and elsewhere in DMS Form PUR 7027. Special Conditions are set forth in various unnumbered paragraphs in the ITB. General Conditions Paragraphs 5, 11, and 24 of the General Conditions are at issue in this proceeding. The terms of each paragraph are: 5. ADDITIONAL TERMS AND CONDITIONS: No additional terms and conditions included with the bid response shall be evaluated or considered and any and all such additional terms and conditions shall have no force and effect and are inapplicable to this bid. If submitted either purposely through intent or design or inadvertently appearing separately in transmittal letters, specifications, literature, price lists, or warranties, it is understood and agreed the general and special conditions in this bid solicitation are the only conditions applicable to this bid and the bidder's authorized signature affixed to the bidder's acknowledgment form attests to this. 11. QUALITY ASSURANCE: The contractor, during the contract term, upon mutual agree- ment with the Division of Purchasing, will provide reasonable travel and lodging accommodations for one (1) to three (3) government employees to perform an on-site inspection of the manufacturing process(es) and review of the manufacturer's product quality control(s) and total quality manage- ment program(s). The contractor will reim- burse the State for actual transportation cost, per diem and incidental expenses as provided in Section 112.061, F.S. It is the State's desire that the contractor provide demonstration of quality control for improvement rather than post production detection. 24. FACILITIES: The State reserves the right to inspect the bidder's facilities at any reasonable time with prior notice. Included Items Special Conditions in the ITB require bidders to submit prices for "Item 1" and "Item 2" lamps ("included items"). 1/ Item 1 lamps consist of Group 1 and 2 lamps. Group 1 lamps are Large Lamps such as fluorescent, incandescent, quartz, mercury vapor, metal halide, and high-pressure sodium lamps. Group 2 lamps are Photo Lamps such as audio visual, projection, flash, and STTV lamps. The total price for each group is multiplied by a weighted usage factor. The product calculated for Group 1 is added to the product calculated for Group 2 to determine the total price for Item 1 lamps. Item 2 consists of a category of lamps described as "T- 10 Lamps." The total price for Item 2 lamps is determined without application of the weighted usage factor used for Item 1 lamps. The total price for Item 2 lamps is a de minimis portion of the contract price. Special Conditions in the ITB require Respondent to award a single contract for included items to a single bidder. Special Conditions state that, "During the term of the contract established by this bid, all purchases of items will be made from the successful bidder." 2/ Excluded Items Special Conditions require that, "The bidder shall offer a fixed discount from retail prices on all excluded items." Excluded items include high technology lamps. The requirement for a fixed discount on excluded items is not considered in evaluating bid prices for included items. Rather, the requirement is intended to reduce the state's cost for both included and excluded items by assuring a meaningful discount on excluded items. Formatting Requirements Special Conditions prescribe the format in which bids must be submitted. Price lists and authorized dealers' lists are required to be submitted in hard copy and on computer diskette. The format prescribed for computer diskette includes requirements for font and graphics. The Special Conditions state that, "Failure to comply with this requirement will result in disqualification of your bid." The Bids The ITB prohibits the alteration of bids after they are opened. Respondent opened bids on April 10, 1996. Seven vendors submitted bids in response to the ITB. Included Items Four vendors, including Petitioner, submitted a bid for both Item 1 and Item 2 lamps. Intervenor and two other bidders did not submit a bid for Item 2 lamps. General Conditions Intervenor deleted paragraphs 11 and 24 of the General Conditions from its bid. At the direction of Intervenor's legal department in Cleveland, Ohio, Intervenor's regional sales manager struck through paragraphs 11 and 24 and initialed the deletions. The deletions are consistent with Intervenor's corporate policy. Intervenor routinely objects to contract provisions requiring inspection of Intervenor's facilities. Excluded Items Petitioner's bid includes a fixed discount of 44 percent on excluded items. Intervenor's bid includes a fixed discount of 0 percent. Formatting Requirements Intervenor included the information required by the ITB on the diskette it submitted with its bid. However, Intervenor supplied the information in Courier 12 characters per inch ("cpi") font, not the Courier 10 cpi font prescribed in the ITB. Proposed Agency Action Respondent determined that Intervenor's bid was responsive. The purchasing specialist for Respondent who reviewed each bid to determine if it was responsive failed to observe the deleted paragraphs in Intervenor's bid. The purchasing specialist forwarded those bids determined to be responsive to the purchasing analyst assigned by Respondent to: determine if the lamps offered in each bid met the specifications prescribed in the ITB; and evaluate bid prices. The purchasing analyst noted that paragraphs 11 and 24 were deleted from Intervenor's bid. The purchasing analyst and purchasing specialist conferred. They determined that paragraph 5 of the General Conditions cured Intervenor's deletions without further action. The purchasing analyst correctly determined: that lamps offered by Petitioner and Intervenor met ITB specifications; that Intervenor's bid is the lowest bid for Item 1 lamps; that Petitioner's bid is the second lowest such bid; and that Petitioner's bid is the lowest bid for Item 2 lamps. Petitioner's bid for Item 1 lamps is approximately five percent greater than Intervenor's bid. Respondent proposes to award one contract for Item 1 lamps to Intervenor. Respondent proposes to award a second contract for Item 2 lamps to Petitioner. At 4:00 p.m. on May 20, 1996, Respondent posted its intent to award the contract for Item 1 lamps to Intervenor. Petitioner timely filed its formal protest on June 3, 1996. Respondent did not award a contract for excluded items. Respondent's failure to award a contract for excluded items is not at issue in this proceeding. Arbitrary Respondent's proposed award of a contract to Intervenor for substantially all of the items included in the ITB is a decisive decision that Respondent made for reasons, and pursuant to procedures, not governed by any fixed rule or standard prescribed either in the ITB or outside the ITB. Respondent's proposed agency action is arbitrary. Excluded Items The requirement for bidders to offer a fixed discount on excluded items operates synergistically with the requirement for Respondent to award a single contract on included items to a single bidder. The combined action of the two requirements operating together has greater total effect than the effect that would be achieved by each requirement operating independently. The requirement for a fixed discount on excluded items, operating alone, may not induce a bidder who could receive a contract solely for Item 2 lamps to offer a discount that is as meaningful as the discount the bidder might offer if the bidder were assured of receiving a contract for Item 1 and 2 lamps upon selection as the lowest bidder. 3/ By assuring bidders that a single contract for Item 1 and 2 lamps will be awarded to a single bidder, the ITB creates an economic incentive for bidders to provide a meaningful discount on excluded items. Respondent frustrated the synergy intended by the ITB by applying the requirements for a fixed discount and for a single contract independently. Respondent penalized the bidder conforming to the requirement for a fixed discount on excluded items by awarding only a de minimis portion of the contract to the bidder. Respondent rewarded the bidder not conforming to the requirement for a fixed discount on excluded items by awarding substantially all of the contract to that bidder. If Respondent elects to purchase all excluded items from Petitioner, Respondent will have used the contract for Item 1 lamps to induce a meaningful discount from Petitioner without awarding Petitioner with the concomitant economic incentive intended by the ITB. Such a result frustrates the ITB's intent. Paragraph 5 Respondent's interpretation of paragraph 5 fails to explicate its proposed agency action. Respondent's interpretation of paragraph 5: leads to an absurd result; is inconsistent with the plain and ordinary meaning of the terms of the ITB; and is inconsistent with Respondent's actions. Respondent's interpretation imbues paragraph 5 with limitless curative powers. Respondent's interpretation empowers paragraph 5 to cure the deletion of all General Conditions in the ITB whether stricken by pen or excised with scissors. Respondent's interpretation of paragraph 5 would transform a bid containing no General Conditions into a responsive bid. Respondent's interpretation of paragraph 5 is inconsistent with the plain and ordinary meaning of its terms. Paragraph 5 operates to cure "additional" terms. It does not operate to restore deleted terms. Respondent's interpretation of paragraph 5 is inconsistent with Respondent's actions. Respondent did not rely on paragraph 5 to cure Intervenor's deletions without further action. Respondent took further action to cure the deletions. Further Action On the morning of May 20, 1996, the purchasing analyst for Respondent telephoned Intervenor's regional sales manager. The purchasing analyst demanded that Intervenor accept the conditions Intervenor had deleted from its bid by submitting a letter of acceptance before the bid tabulations were posted at 4:00 p.m. on the same day. The regional sales manager contacted Intervenor's corporate headquarters in Cleveland, Ohio. Intervenor authorized the regional sales manager to accept the deleted paragraphs. By letter faxed to Respondent at approximately 3:20 p.m. on May 20, 1996, Intervenor accepted the paragraphs it had previously deleted. The letter stated that, "GE Lighting [will accept] the Contract Conditions noted in Paragraphs 11 and 24 of the Lamp Quotation." [emphasis not supplied] At 4:00 p.m. on May 20, 1996, Respondent posted the bid tabulation form. The bid tabulation form stated that the "award is contingent upon General Electric's acceptance of all the terms in conditions (sic)" in the ITB. Respondent argues that the purchasing analyst who contacted Intervenor on the morning of May 20, 1996, exceeded her authority. Respondent characterizes the word "contingent" in the bid tabulation form as "poorly written" and a "bad word." Agency Construction Of ITB Terms Respondent construes terms in the ITB in a manner that is inconsistent with their plain and ordinary meaning. The ITB requires that, "The bidder [shall] offer a fixed discount from retail price list on all excluded items." [emphasis supplied] Respondent interprets the quoted provision as meaning the bidder may offer such a fixed discount if the bidder elects to do so. The purpose of the ITB is to establish "[a] 24 month contract" to supply large lamps to the state. [emphasis supplied] Respondent interprets the quoted provision as meaning that the purpose of the ITB is to establish two contracts. The ITB states that, "During the term of the contract established by this bid, all purchases of items [will] be made from [the] successful bidder." [emphasis supplied] Respondent interprets the quoted provision as meaning that purchases of some items will be made from one successful bidder and that purchases of other items will be made from a second successful bidder. The ITB states that the contract "[shall] be made statewide on an all or none basis" to the responsive bidder who satisfies the conjunctive requirements for: "[the] lowest "Award Figure Item (1; [and] lowest Award figure for Item (2." [emphasis supplied] Respondent interprets the quoted provision as meaning that separate contracts may be made statewide on less than an all or none basis to separate responsive bidders who satisfy the disjunctive requirements for either the lowest bid for Item 1 lamps or the lowest bid for Item 2 lamps, or both. The ITB requires offers to be submitted for all items listed within a group for a bid to qualify for evaluation. Respondent interprets the requirement as meaning that a bidder who does not qualify for evaluation for all of the groups in the contract nevertheless qualifies for evaluation for the contract. Finally, the ITB states that failure to comply with the formatting requirements for the diskette "[will] result in disqualification of your bid." [emphasis supplied] Respondent interprets the quoted language to mean that failure to comply with prescribed formatting requirements may result in disqualification of a bid. The interpretations of the quoted terms proposed by Respondent, individually and collectively, frustrate the purpose of the ITB. They also ignore material requirements of the ITB. Material Deviation Respondent deviated from the rule or standard fixed in the ITB in several respects. First, Respondent altered the bid evaluation procedure prescribed in the ITB. Second, Respondent ignored the requirement to award a single contract to a single bidder. Third, Respondent ignored the requirement that bidders provide a fixed discount on excluded items. Fourth, Respondent ignored the requirement to comply with the formatting requirements prescribed in the ITB. Each deviation from the rule or standard fixed in the ITB is a material deviation. Each deviation gives Intervenor a benefit not enjoyed by other bidders. Each deviation affects the contract price and adversely impacts the interests of Respondent. 4/ 5.5(a) Benefit Not Enjoyed By Others Intervenor enjoyed a benefit not enjoyed by other bidders. Intervenor obtained a competitive advantage and a palpable economic benefit. Respondent altered the bid evaluation procedure prescribed in the ITB. On the morning of May 20, 1996, Respondent disclosed the bid tabulations to Intervenor alone, 5/ gave Intervenor an opportunity that lasted most of the business day to determine whether it would elect to escape responsibility for its original bid, allowed Intervenor to cure the defects in its bid, accepted Intervenor's altered bid, and conditioned the bid tabulations on Intervenor's altered bid. Respondent used a bid evaluation procedure that is not prescribed in the ITB and did not allow other bidders to participate in such a procedure. 6/ In effect, Respondent rejected Intervenor's initial bid, with paragraphs 11 and 24 deleted, and made a counter offer to Intervenor to accept a bid with paragraphs 11 and 24 restored. Intervenor accepted Respondent's counter offer. Respondent excluded other bidders from that process. Respondent gave Intervenor an opportunity to determine whether it would elect: to escape responsibility for its original bid by declining Respondent's counter offer; or to perform in accordance with an altered bid by restoring paragraphs 11 and 24. A bidder able to elect not to perform in accordance with its bid has a substantial competitive advantage over other bidders unable to escape responsibility for their bids. 7/ Respondent awarded substantially all of the contract to Intervenor even though Intervenor failed to provide a meaningful discount on excluded items. Respondent provided Intervenor with a palpable economic benefit. 5.5(b) Bid Price And Adverse Impact On The State Respondent did not award a contract for excluded items. Respondent's proposed agency action allows Respondent to purchase excluded items from either Intervenor or Petitioner. If Respondent were to purchase all of the excluded items it needs from Intervenor, Respondent could pay substantially more for excluded items than Respondent would save from the five percent price advantage in Intervenor's bid for Item 1 lamps. In such a case, Respondent's proposed agency action would effectively increase costs to the state that are inherent, but not stated, in the ITB. 8/ Conversion of incorrectly formatted data to the required font shifts prices to incorrect columns and causes other problems in accessing information in the diskette. Such problems can not be rectified easily but require substantial time and effort. Responsive Bidder Respondent did not award the contract intended by the ITB to the lowest responsive bid. Although Intervenor's bid is the lowest bid for Item 1 lamps, it is not the lowest responsive bid for Item 1 and 2 lamps. Petitioner's bid is the lowest responsive bid for Item 1 and 2 lamps. 9/ Respondent is statutorily required to award the contract to the lowest responsive bidder. 10/ Illegal Intervenor's bid is not responsive within the meaning of Sections 287.012(17), Florida Statutes (1995). 11/ It does not conform in all material respects to the ITB. Intervenor's unaltered bid deletes paragraphs 11 and 24. It does not include a fixed discount on excluded items, does not include a bid for Item 2 lamps, and does not conform to the formatting requirements in the ITB. Section 287.057 requires Respondent to award the contract to the bidder who submits the lowest responsive bid. Respondent has no authority either: to consider bids that are not responsive; or to award the contract to a bidder other than the lowest responsive bidder. Respondent's attempt to engage in either activity is ultra vires and illegal. Minor Irregularities The ITB encourages, but does require, bidders to include quantity discounts for Item 1 and 2 lamps. Petitioner's bid does not include quantity discounts. Petitioner's bid does not fail to conform to material requirements in the ITB. Petitioner does not manufacture Item 1 and 2 lamps. Sylvania manufactures the lamps Petitioner sells. Petitioner has no legal right to require Sylvania to allow inspection of its facilities pursuant to paragraph 11 of the General Conditions. Petitioner's ability to provide the requisite inspections requires the cooperation of Sylvania. Petitioner's bid requires payment by the state within 30 days of an invoice. Section 215.422 and the ITB provide that Respondent has 40 days to issue warrants in payment of contract debts and that interest does not accrue until after 40 days. The defects in Petitioner's bid are minor irregularities within the meaning of Florida Administrative Code Rule 60A-1.001(16). 12/ They neither affect the bid price, give Petitioner a competitive advantage, nor adversely impact Respondent's interests. Petitioner has the practical ability to arrange inspection's of Sylvania's facilities. Petitioner is legally responsible for failing to do so. Respondent's employees have never visited Sylvania's facilities during the 10 years in which Petitioner has been the contract vendor to the state. The requirement for payment within 30 days does not obviate the provisions of Section 215.422. Private contracts can not alter mutually exclusive statutory provisions.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent enter a Final Order granting Petitioner's protest of Respondent's proposed agency action. RECOMMENDED this 26th day of September, 1996, in Tallahassee, Florida. DANIEL S. MANRY, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of September, 1996.

Florida Laws (6) 112.061120.57215.422287.001287.012287.057 Florida Administrative Code (1) 60A-1.001
# 9
NATKIN SERVICE COMPANY vs DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 95-005073BID (1995)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Oct. 17, 1995 Number: 95-005073BID Latest Update: Feb. 21, 1996

Findings Of Fact Respondent solicited contractors to replace a chiller in Building #45 at its Sunland facility located in Marianna, Florida. The project number for the replacement was HRS-95203000. The vendors were allowed until 10:00 a.m., Central Daylight Time, August 24, 1995, to submit responses to the request for bids. On August 24, 1995, Respondent received four responses. The responses were from Petitioner, Neel, JLS International and Smiths, Inc. On August 24, 1995, when the bids were opened JLS International and Smiths, Inc. were disqualified as nonresponsive bidders. On August 24, 1995, Respondent determined that Petitioner had submitted a base bid in the amount of $141,185.00 and as described on the tabulation form, an alternate bid in the amount of $14,750.00 for confined space compliance. The Neel bid as reflected on the tabulation was a base bid for $142,000.00. The forms upon which Petitioner and Neel had submitted their bid prices were forms identical in their format. The format was required by the Respondent. The Petitioner's bid stated: Base Bid: $141,185.00 With foregoing as a Base Bid the following costs of alternate proposals are submitted in accordance with the drawings and specifi- cations. Alternate No. 1 Add or Deduct $ N/A Alternate No. 2 Add of Deduct $ Alternate No. 3 Add or Deduct $ If more or less work is required than that qualified by the specifications and drawings the following unit prices shall be applicable. *If Required (not included in base bid) ITEM UNIT PRICE Compliance for confined space for refrigerants & equipment *Note: Base bid price is compiled costs for construction duration & equipment delivery of 18 weeks. When Petitioner submitted its response to the request for bids, it offered no further explanation concerning the $14,750.00 price for "compliance for confined space for refrigerants and equipment" than has already been described. The Neel bid stated: Base Bid: $142,000.00 With foregoing as a Base Bid the following costs of alternate proposals are submitted in accordance with the drawings and specifications. Alternate No. 1 Add or Deduct $ Alternate No. 2 Add of Deduct $ Alternate No. 3 Add or Deduct $ If more or less work is required than that qualified by the specifications and drawings the following unit prices shall be applicable. ITEM UNIT PRICE Respondent had provided written instructions to the bidders concerning execution of the bid proposal form to the effect: Omit mention of alternates entirely, if there are none. Unit prices are to be used only if unit prices are applicable and approved by the Project Director. This project did not call for alternate bids or unit prices. The request for bids did not contemplate a quotation other than the base bid for all items, to include any costs associated with implementation of a design that complies with all applicable codes associated with the installation and with any laws pertaining to refrigerant handling. Posting of the bid evaluation/tabulation and notice of contract award recommendation was given on September 8, 1995, indicating Respondent's intent to award to Petitioner in the amount of $141,185.00 as the base bid for the project. Prior to the posting of the bids on September 8, 1995, as was customary, Thomas McAuley, an account representative for Petitioner, who had submitted Petitioner's bid response had met with Respondent's project manager Glen Jenkins, a Professional Engineer III. The meeting was held to discuss Petitioner's bid response as the apparent responsive lowest and best bidder. In the conversation held between Messrs. McAuley and Jenkins, they did not discuss the $14,750.00 separate price quotation in the Petitioner's bid. They did discuss compliance with the codes that were going to be applicable to the project and whether the base price quotation took into account the code requirements. McAuley indicated his opinion that the base price quotation did account for compliance with code requirements contemplated by the terms in the request for bids. McAuley was specifically asked whether Petitioner was complete and thorough in its compliance with the bid specifications and in its prices, inclusive of all the items that were going to be mandated by the State of Florida, Department of Management Services. McAuley answered that question in the affirmative. In the specifications, under Article 7, Miscellaneous Provisions, within the request for bids is set forth Sections 7.2, 7.3 and 7.4 related to permit and code compliance issues, which state as follows: State Building Permit. Current DMS requirements for state building permit applications and for permit inspections are attached. It shall be the Contractor's responsibility to apply for and pay all costs associated with the state building permit (including the cost of preparing any permit documents on which the state building official may require the seal of a registered engineer). It shall further be the Contractor's responsi- bility to comply fully with all permit inspection requirements. Code Compliance. It is the Contractor's responsibility to implement a design complying with all codes applicable to this installation, and with all laws pertaining to refrigerant handling. Neither the Owner nor the Project Manager shall be held responsible for stating or setting forth (in this or any other document, or verbally) any code requirement which may be applicable to this project. By disseminating this "Statement of Work Scope and Contractual Conditions", the Owner merely sets forth minimum acceptance criteria for materials and workmanship, and neither the Owner nor the Project Manager shall thereby be held liable, in full or in part, for the Contractor's adherence or non-adherence to any governing code and/or legal requirement. Special Terms and Conditions for Cont- racts Under the National Energy Conservation Policy Act. Due to partial project funding under a federal NECPA grant, Contractor compliance with federal laws and regulations are a special requirement of this project. Special terms and conditions pertaining to wages and payrolls, records retention and access, apprenticeship and training, equal opportunity access, are set forth in the attached "Special Terms and Conditions for Contracts Under the National Energy Conserva- tion Policy Act". The contractor shall responsible for full compliance with the attached special terms and conditions. In the meeting between McAuley and Jenkins discussion was made concerning compliance with pertinent electrical codes. One question was asked about pipes in the system being installed in a manner to allow variable speed drives to be placed above the pipes. Jenkins considered that speed drive placement underneath the pipes would be contrary to code requirements. Related to the mechanical features in the project there was discussion about the provision of refrigerants in compliance with the mechanical code that pertained. In the meeting there was little discussion about code compliance within confined spaces, because the two individuals did not perceive that there would likely be a code requirement concerning confined spaces. Mention was made that some code inspector or code official who came to the job site might require attention to the confined spaces, even though that requirement was not found in the code. According to Jenkins, in his recount of the meeting with McAuley, if a code official required compliance for an item in the confined spaces that was not set forth in the code, that would constitute an item about which the Respondent had not requested information to be included in the base price quotation offered by the Petitioner. Further, Jenkins stated there would not be a problem for failing to offer a quotation for the features required by the inspector, because it was not sought by the Respondent in designing the bid requirements. As Jenkins describes, Petitioner's unit price for that work had been made known. This is taken to refer to the $14,750.00 quote for compliance for confined space for refrigerants and equipment. In that circumstance, Mr. Jenkins told Mr. McAuley that if a code official required something that was not contemplated by the code and the Respondent did not consider it worth fighting over, then Respondent would have to process a change order to install that equipment. This is taken to mean that Petitioner would be paid additional money under a change order for installing the equipment in the event that the Respondent did not choose to contest the decision of the code official. At the time that McAuley and Jenkins had the meeting, counsel for Neel had contacted Jenkins about protesting the decision to award the contract to Petitioner. That individual had stated the opinion to Respondent that Petitioner's discussion of confined space for refrigerants and the equipment at the additional cost of $14,750.00 might be perceived as potentially a code exclusion in violation of the requirements of Section 7.3 to the request for bids. Neel's counsel stated his belief that the vendors were expected to be in compliance with all codes and laws, even if it was not known to be a code requirement at the time the bid was submitted. He was concerned that someone might try and make it a requirement in the future. The Neel attorney explained that the reference to compliance for confined space for refrigerants and equipment set forth in Petitioner's bid response might be construed as a comment on code requirements through the contingency of someone's interpretation of the code. He believed that the responses to the request for bids needed to address that contingency as part of the basic quotation, not as a separate quotation. At the time McAuley and Jenkins had their meeting, Jenkins did not know of any requirement for compliance for confined space for refrigerants and equipment based upon his experience, but he had not researched the issue. Through information which Neel imparted to Mr. Jenkins before the meeting was held between Jenkins and McAuley, the Neel attorney expressed the opinion that there was not a present code requirement for compliance for confined space for refrigerants and equipment, a view held by McAuley and Jenkins. At the time the meeting was held between McAuley and Jenkins, Jenkins was of the opinion that the requirement for compliance for confined space for refrigerants and equipment was not foreseen to be a likely code requirement. As contrasted with Neel's view, as explained to Jenkins, that its base bid was intended to cover the eventuality that there might become a requirement for compliance for confined space for refrigerants and equipment, Neel's representative stated that Petitioner's bid had segregated that contingency for consideration by quoting the price of $14,750.00 separately. Neel did not appear at the hearing and there was no direct proof that the $142,000.00 base bid by Neel addressed the contingency that a future requirement might be imposed for compliance for confined space for refrigerants and equipment. However, it may properly be assumed the Neel bid met the requirement for a base bid quotation to cover all costs to Respondent absent proof to the contrary. Later, when Respondent decided to award the contract to Neel, Respondent implied that the $142,000.00 base bid would meet code requirements contemplated by Section 7.3. Concerning the responsibility to determine which code requirements pertained and when, Respondent expected the vendors to derive that answer. This case was unlike most projects by the Respondent in which design professionals, engineers or architects create design documents that are completed in view of code requirements and the vendors assume that the bid documents prepared would be in conformance with code requirements. At hearing Mr. Jenkins, as project manager, opined that Section 7.3 obligated the contractor to meet existing requirements of the permitting authorities, and if during the pendency of the contract there was some change to the codes or code requirements set forth by code inspectors, then the contractor must assume the risk. Moreover, when the bids were opened and tabulated initially and the preliminary decision was made to award the contract to Petitioner, Mr. Jenkins perceived the quotation of $14,750.00 set forth in the Petitioner's bid to be a unit price for a scope of work that was not expected to be required at any point and was not been asked for by Respondent. Jenkins considered this quote as an alternate that was being proffered, something that Respondent might opt for in the future. Although not set forth in exact terms, Mr. Jenkins perceived this information in the Petitioner's bid response to be related to an alarm system and breathing apparatuses. He held this belief based upon his experience in association with compliance for confined spaces. Mr. Jenkins surmised that what was being described by the Petitioner was the type of installation that you would put into a closed mechanical room where a refrigeration machine was located that contained toxic refrigerant, which if released might kill a serviceman. In that connection when discussing refrigerant compliance with Mr. McAuley in their meeting, Mr. Jenkins indicated that the discussion had been limited because the type of machine proposed by the Petitioner was a 134A machine which is "ozone friendly" and not restricted by clean air amendment regulations. Following the posting on September 8, 1995, which recommended that the contract be awarded to Petitioner, Neel had 72 hours to file a protest. That protest was filed. Having considered the remarks by Neel's attorney in support of that protest, Mr. Jenkins became persuaded that Petitioner might not have intended to describe an alternate (unsolicited) purchase when discussing the compliance for confined space for refrigerants and equipment for a price of $14,750.00; instead, Petitioner may have been describing how to comply with future code requirements. Consequently, Mr. Jenkins attempted to settle the issue by presenting the opportunity for the Petitioner to obtain a letter from the Department of Management Services permitting office establishing that the equipment described in the bid by Petitioner for compliance for confined space refrigerants and equipment was not then a code requirement. Mr. Jenkins wanted that information to be in writing. This opportunity to submit information was imparted to Stuart Zaritsky, Branch Manager for Petitioner in its Tallahassee office. Petitioner did not take the opportunity to send written information concerning the compliance for confined space for refrigerants and equipment as not being required by applicable codes. Instead, Mr. Zaritsky called Mr. Jenkins and told him that Petitioner had placed calls to the Department of Management Services permitting office and was unable to get a definitive response at that time. On September 26, 1995, Mr. Zaritsky wrote to Mr. Jenkins and stated: The confined space for refrigerants and equipment compliance is based on ASHRAE recommendations only. If any of these items are required by code, then we will install it at no cost. Our base bid of $141,185 is based on the specifications, including paragraph 7.3 on page 13 and all other portions of the contract documents without any qualifications. If it is determined by the owner, that they wish to upgrade the machine room to ASHRAE 15 standards, and it is not required by code, the $14,750 would be the price to add refrigerant monitors, refrigerant purge fans and self-contained breathing apparatus. Should the jurisdictional authority of code compliance determine that these items are required by code, they will be installed as part of our base bid of $141,185. On September 29, 1995, Respondent gave notice of an amended bid tabulation finding Neel to be the responsive lowest and best bidder for the project in its quotation of $142,000.00. The September 29, 1995 correspondence notified the Petitioner that: After further review of issues raised by responsive bidders on the above project, the Department has determined that the bid sub- mitted by Natkin Service Co. on the above referenced project either: is nonresponsive, because the bid was not in compliance with Section 7.3 of the Statement of Work Scope and Contractual Conditions, since it exempted its bid from certain refrigerant handling requirements; or if responsive, is in the amount of $155,935.00. In either case, the bid submitted by Neel Mechanical Contractors, Inc. in the amount of $142,000.00 is the lowest responsive bid. The September 29, 1995 determination that Petitioner was not responsive led to Petitioner's present protest. Sometime shortly before the amended posting of the bid tabulation on September 29, 1995, Mr. Jenkins spoke to Mr. McAuley concerning the opportunity to present information to address the question concerning whether compliance for confined spaces for refrigerants and equipment was a code requirement. To assist the Petitioner Mr. Jenkins provided information which had been received from the Department of Community Affairs related to code provisions under enforcement by the Department of Management Services. This information was not provided by Mr. Jenkins as a determination of code requirements; it was provided to inform Petitioner concerning what Mr. Jenkins understood to be the latest code requirements. The expectation was still held that Petitioner would submit separate information from the Department of Management Services that would settle the issue concerning the possible need to comply with code requirements for confined spaces for refrigerants and equipment. As Mr. Jenkins described at hearing, the basis for finding the Petitioner's bid unresponsive was alternatively stated. First, the Respondent believes that Petitioner tried to avoid the responsibility for complying with code requirements, whatever they may be during the contract pendency; or second, Petitioner split its bid into two parts. One in the amount of $141,185.00 for matters unrelated to code compliance for confined space for refrigerants and equipment and the second in an amount of $14,750.00 for such compliance. If the former view is taken, Petitioner's bid is unresponsive. If the latter view is taken Petitioner's bid is responsive but exceeds the quotation by the responsive bidder Neel. At hearing it was not proven by competent evidence whether there was any necessity to meet code requirements for compliance for confined space for refrigerants and equipment as described in Petitioner's bid response at any point in time. Other provisions within the request for bids that pertain to the manner in which the vender would address its price quotation are as follows: 1.5 The Contract Sum shall initially be that lump-sum amount which the Contractor shall have enclosed in his sealed bid proposal. Subject to additions and deduc- tions by Change Order, the Contract Sum shall be the amount which the Owner shall pay the Contractor for the performance of the work, subject to the terms and conditions as provided in the Contract Documents. 2.6 The Contractor shall apply for, and pay all costs associated with, any permit which may be required by the Department of Management Services. Such permitting costs for which the Contractor shall be responsible shall include the preparation of any permit documents on which the building official may require the seal of a registered engineer. B-9 Instruction for bidders; They (the bidders) are also required to examine carefully any drawings, specifications and other bidding documents to inform themselves thoroughly regarding any and all conditions and requirements that may in any manner effect the work.

Recommendation Upon consideration of the facts found and the conclusions of law reached, it is, RECOMMENDED: That the final order be entered which dismisses Petitioner's protest based upon the unresponsive of its bid and awards the contract for Project No. HRS- 95203000 to Neel. DONE and ENTERED this 20th day of December, 1995, in Tallahassee, Florida. CHARLES C. ADAMS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of December, 1995. APPENDIX The following discussion is given concerning the proposed fact finding by the parties: Petitioner's Facts: Paragraph B1 is contrary to facts found. Paragraph B2 is rejected in the suggestion that Respondent should be bound by resort to extrinsic evidence to determine Petitioner responsive to the bid invitation. Paragraph B3 is contrary to facts found. Paragraph B4 is rejected in the suggestion that it was inappropriate to defer to the Neel protest as a means for Respondent to reconsider its position. Paragraph B5 is rejected in the suggestion that Neel has controlled the outcome in this case. Paragraph B6 is rejected in the suggestion that Petitioner has complied with the bid invitation requirements. Paragraph B7 is rejected in the suggestion that the contrary position stated by the Respondent in the informal review wherein Petitioner had been preliminarily determined to be the responsive bidder and the point of view at hearing would preclude a decision favoring the Respondent. Respondent's Facts: Paragraphs 1 through 9 are subordinate to facts found. COPIES FURNISHED: Tommy McAuley, Account Manager Natkin Service Company 3428 A. Garber Drive Tallahassee, FL 32303 Sam Chavers, Esquire Department of Health and Rehabilitative Services 1323 Winewood Boulevard Building 1, Suite 200 Tallahassee, FL 32399-0700 Robert L. Powell, Agency Clerk Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, FL 32399-0700 Kim Tucker, General Counsel Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, FL 32399-0700 Informational Copies: JLS International, Inc. P. O. Box 490 Foley, AL 36536 Neel Mechanical Contractors, Inc. P. O. Box 1916 Thomasville, GA 31799 Smith's, Inc. of Dothan P. O. Box 1207 Dothan, AL 36302

Florida Laws (3) 120.53120.57287.057