The Issue The issue in this case is whether the land use designation placed on the property of intervenors is consistent with the goals, policies and objectives of the City of Jacksonville comprehensive plan.
Findings Of Fact Background This controversy involves a challenge to the City of Jacksonville 2010 Comprehensive Plan (Plan) by intervenors, Sybil L. Davis, Katherine T. Dekle, and Dr. James A. Acree, all residents and property owners in Duval County, Florida. The parties agree that intervenors are affected persons and thus have standing to pursue their claims. Intervenors contend generally that the land use designation given to their respective properties is inconsistent with other parts of the Plan and should be changed. If the requested relief is granted, intervenors would be able to develop their properties in a different manner than is now permitted under the Plan. The proposed Plan was first submitted by respondent, City of Jacksonville (City), to petitioner, Department of Community Affairs (DCA), on March 19, 1990. The DCA is the state land planning agency charged with the responsibility of reviewing comprehensive plans under Chapter 163, Florida Statutes. The City is a local government required to adopt a comprehensive plan pursuant to chapter 163. The proposed plan was the City's first attempt at meeting the compliance requirements established in that chapter. Under the law, the DCA is required to review all proposed plans for compliance with applicable statutes and rules. In that vein, besides its own in-house review, the DCA received comments from the Department of Environmental Protection and the Department of Transportation (DOT), considered such comments, and where appropriate, incorporated those views into its Objection, Recommendation and Comment Report (ORC) issued on July 10, 1990. The ORC contains the DCA's objections and comments concerning the Plan as well as recommendations which address those concerns. After considering the ORC, the City adopted a revised Plan on September 11, 1990, by Ordinance No. 90-794-380, which was then transmitted to the DCA. On November 9, 1990, the DCA issued its Statement of Intent to Find Comprehensive Plan Not in Compliance. After negotiations between the two parties, the City agreed to adopt remedial amendments to its Plan. This was accomplished by Ordinance No. 92-925-1405, effective January 22, 1993. Thereafter, on February 26, 1993, the DCA issued a Cumulative Notice of Intent to Find the Plan, as amended, in compliance with the law. As a consequence of this action, the interests of the City and DCA are aligned in this proceeding. Intervenors, however, consider the Plan to be internally inconsistent as to their respective properties and thus not in compliance with the law. It should be noted that during the local hearing process before the City, intervenors' requests to have their land use designation changed were denied. The Davis-Dekle Property Both Davis and Dekle own property which fronts on Southside Boulevard, a major arterial highway that runs in a north-south direction for ten to fifteen miles between Atlantic and Beach Boulevards. It consists of two northbound lanes, a divider (grass) median, and two southbound lanes. In addition, a twenty-foot service road runs along the outside of each roadway and is separated from the main roadway by a grass median. The highway right-of-way is 200 feet wide. This right-of-way has existed since at least the 1940's while the service roads were built in the 1950's. Davis owns two parcels of property on Southside Boulevard, also known as State Road 115. The first parcel, which is located at 2351 Southside Boulevard, is a vacant lot measuring 100 feet wide by 200 feet deep. The lot was purchased in 1987 with the intention of eventually converting the property to commerical use. A year later, Davis purchased a 1,000 square foot home located at 2615 Southside Boulevard. The house sits on a lot measuring approximately 85 feet wide by 200 feet deep. Although she currently resides in the home, Davis also intends to convert this property to commercial use if her appeal is successful. Both lots sit on the east side of Southside Boulevard between Atlantic and Beach Boulevards. Dekle's property is located at 2710 Southside Boulevard and lies on the west side of the street between Atlantic and Beach Boulevards. Dekle purchased the property in 1947 and has lived there for almost thirty years. The lot measures approximately 100 feet wide by 208 feet deep. Intervenors' properties are located in what is known as Southside Estates, a subdivision developed soon after World War II. The neighborhood surrounding their property is residential. Indeed, some 115 single-family homes are located on Southside Boulevard. Thus, the area historically has been a residential area since the 1940's and the predominant land uses along both sides of Southside Boulevard are single-family residences. Under the Plan, intervenors' properties are included in an area designated as "Low Density Residential," and thus this designation would bar intervenors from converting their properties to commercial use. "Low Residential Density" is defined in the future land use element of the Plan as follows: This category permits housing developments in a gross density range of up to seven (7) dwelling units per acre when full urban services are available to the site. Generally, single family detached housing will be the predominant land use in this category, although mobile homes, patio homes and multi-family dwellings shall also be permitted in appropriate locations. Minimum lot size shall be half acre per dwelling unit when both centralized potable water as well as wastewater are not available. The lot size shall be reduced to 1/4 acre per dwelling unit if either one of these services are not available. As noted above, intervenors' properties lie on Southside Boulevard between Atlantic and Beach Boulevards. The distance between these two latter roadways is approximately two miles. There is a major node of commercial development at the intersection of Southside and Atlantic Boulevards and a smaller commercial node at the intersection of Southside and Beach Boulevards. These uses, which extend approximately one-third of the distance between Atlantic and Beach Boulevards, are predominately offices, with the exception of more intense commercial uses near the intersection with Atlantic Boulevard. The southernmost extent of the commercial uses is approximately six or seven blocks north of the Dekle property. Intervenors complain that because of heavy traffic found on Southside Boulevard during the weekdays, their property should not carry a low residential density classification. More specifically, between 2:00 p. m. and 6:00 p. m. weekday afternoons, traffic backs up for more than a mile on the southbound lanes of Southside Boulevard between Atlantic and Beach Boulevards while there is a similar traffic backup in the northbound lanes during morning rush hours. This is confirmed by the fact that the roadway is functioning at a level of service "F," which means arterial flow is at "extremely slow speeds" and "intersection congestion" is likely at critical signalized locations. The DOT considers the minimum acceptable level of service to be level of service "D." Traffic counts, measured in average daily trips, are projected to reach 40,871 by 1995 at a point on Southside Boulevard 100 feet south of Atlantic Boulevard and 51,089 by the year 2010. Intervenors agree, however, that the service roads, on which their properties front, flow smoothly and are lightly traveled. Because intervenors' homes are located at the front of their lots closest to the service roads, they experience vehicle noise which affects their ability to watch television, sleep or carry on other normal activities unless windows and doors are closed at all times. Odors and fumes generated by the nearby traffic also require that windows and doors be shut at all times. Unless they retreat to the rear of their lots while outside their homes, they cannot escape the traffic fumes. In view of the foregoing condition, intervenors contend that a change in land use designation from low density residential to commercial is appropriate. "Commercial" is described in the future land use element of the Plan as follows: This category is intended to provide for all types of sales and services activities, such as retail trade, personal and professional services and storage, offices, hotels, motels, entertainment, and amusement facilities. Commercial recreation and entertainment activities, such as amusement parks and marinas, are also allowed in this category. Multi-family uses, when developed as part of an integrated mixes use project, are also permitted consistent with the Medium Density Residential (MDR) and High Density Residential (HDR) plan category description. The Plan includes five types of commercially dominated land use categories: residential-professional-institutional, neighborhood commerical, community/general commercial, regional commercial, and central business district. The primary uses range from a small convenience store, laundry/dry cleaning shop to a large shopping center or a multi-story office building. In considering intervenors' request to change the proposed land use to commercial, the City looked at the Greater Arlington Plan (an earlier land use plan completed in 1985), the existing use of the land, and the existing zoning. It also considered the general character of the area and the fact that most homes were graded in an "A" condition and were structurally sound. It should be noted here that the DCA did not raise any concerns over the proposed land use classification in its ORC report, nor has it subsequently posed any objection. In determining the appropriate land use classification for intervenors' properties, the Plan is the primary document to be used to guide the City's future growth and development. The future land use and housing elements of the Plan contain goals, objectives and policies which bear directly on this issue. More specifically, the following goals, objectives and policies found in the future land use and housing elements of the Plan support the classification given to intervenors' properties: Future Land Use Element GOAL 1 To ensure that the character and location of land uses optimize the combined potentials for economic benefit and enjoyment and protection of natural resources, while minimizing the threat to health, safety and welfare posed by hazards, nuisances, incompatible land uses and environmental degradation. Objective 1.1 Ensure that the type, rate, and distribution of growth in the City results in compact and compatible land use pattern, an increasingly efficient urban service delivery system and discourages proliferation of urban sprawl through implementation of regulatory programs, intergovernmental coordination mechanisms, and public/private coordination. Policy 1.1.1 The City shall ensure that all new development and redevelopment after the effective date of the 2010 Comprehensive Plan is consistent with the Future Land Use Map series, and textual provisions of this and other elements of the 2010 Comprehensive Plan, as provided in Chapter 163 (Part II), F.S. 1.1.8 By April 1, 1991, require that all new non-residential projects be developed either in nodal areas, in appropriate commercial infill locations, or as part of mixed or multi-use developments, as described in this element. GOAL 2 To enhance and preserve for future generations geographic areas with unique economic, social, historic or natural resource significance to the City. GOAL 3 To achieve a well balanced and organized combination of residential, non-residential, recreational and public uses served by a convenient and efficient transportation network, while protecting and preserving the fabric and character of the City's neighborhoods and enhancing the viability of non-residential areas. Issue: Residential Development Patterns The neighborhood is the functional unit of residential development. There is a need to protect existing, viable neighborhood units and the neighborhoods that will emerge in the future. However, much newer residential development occurs as enclaves, with little or no functional linkage to surrounding areas. Unplanned low density development has become a familiar land use pattern in Jacksonville as new subdivisions have been developed further and further out, away from the existing urban area. * * * Objective 3.1 Continue to maintain adequate land designated for residential uses which can accommodate the projected population and provide safe, decent, sanitary and affordable housing opportunities for the citizens. Protect single-family residential neighborhoods by requiring that any other land uses within single-family areas meet all applicable locational criteria of the 2010 Comprehensive Plan and subsequent Land Development Regulations. Policies 3.1.2 The City shall eliminate incompatible land uses or blighting influences from potentially stable, viable residential neighborhoods through active code enforcement and other regulatory measures. * * * 3.1.7 The City shall give high priority consideration to the provision of affordable housing in land development and funding decisions, especially those made relating to public/private cooperative efforts in which the City is participating. * * * Issue: Commerical and Industrial Development Patterns * * * Despite a significant increase in the number of planned centers approved in recent years, little change has occurred in the pattern of strip commerical uses lining the City's arterial and collector roadways. This development pattern is typically inefficient, unsafe, and aesthetically unattractive. It results in multiple curb cuts, sometimes up to 50 per mile, thereby reducing the traffic carrying capacity of highways while at the same time increasing the potential for accidents. With a clutter of signs of all sizes, shapes, color, and design, the appearance of these areas is not only unsightly, it is also distractive for traffic on the highway and can, therefore, be dangerous. Another problem relating to strip commercial uses has developed as the commercial market has begun to overbuild during the recent national economic expansion cycle. Commercial retail and office space has remained in an over-supply condition (indicated by vacancy rates over 15 percent) for the past several years,, and as a result, new space has come on line at square footage costs that create strong competition with existing space. This competitive market results in relocations of existing businesses to newer projects, leaving many older commercial buildings semi-vacant and with little investment benefit to the owners. Without the hope of a reasonable economic return, owners may not invest funds to maintain their structures, and inevitably, commercial blight begins to develop. For these reasons, new commercial development will be strongly encouraged to occur in nodes or clusters in the form of office parks, shopping centers and mixed use developments. Strip commercial expansion along arterial streets will be discouraged, except for commercial infill of uses such as hotels, motels, restaurants, auto sales and service, mobile home sales, convenience stores and gas stations, which shall continue to locate along highways. * * * Policies The City shall promote, through the use of development incentives and other regulatory measures, development of commercial and light/service industrial uses in the form of nodes, centers or parks, while discouraging strip commercial development patterns, in order to limit the number of curb cuts and reduce conflicts in land uses, particularly along collectors and arterials. The City shall promote, through the Land Development Regulations, infill and redevelopment of existing commercial areas in lieu of permitting new areas to commercialize. * * * The City shall permit expansion of commercial uses adjacent to residential areas only if such expansion maintains the residential character of and precludes non- residential traffic into adjacent neighborhoods. The City shall require neighborhood commercial uses to be located in nodes at the intersections of collector and arterial roads. Prohibit the location of neighborhood commercial uses interior to residential neighborhoods in a manner that will encourage the use of local streets for non-residential traffic. The City shall implement the locational criteria of this element for commercial and industrial uses consistent with the character of the areas served, availability of public facilities, and market demands. * * * Housing Element GOAL 1 The City shall develop stable and definable neighborhoods which offer sale, sound, sanitary housing that is affordable to all its present and future residents. Issue: Neighborhood Stabilization Urban housing is a function of neighborhood. Stable neighborhoods encourage residents to maintain, upgrade, build and buy housing resulting in a sound, diverse housing stock. * * * There is an inadequate number of organizations committed to the revitalization and cohesiveness of Jacksonville's neighborhoods. Preservation is relatively easy and inexpensive compared to redevelopment and will prevent widespread blight and deterioration in convenient residential locations close to transportation, schools, shopping and medical facilities. * * * Objective 1.4 Preserve, protect, and stabilize residential neighborhoods keeping the maximum number of dwelling units in the housing supply, as measured by the implementation of the following policies. * * * Policy * * * 1.4.5 Commercial and other non-residential uses lying adjacent to residential neighborhoods should not be expanded into residential neighborhoods unless: Such uses enhance or do not diminish or degrade the residential character of the neighborhood, and The expansion shall not result in a reduction of the level of service on the residential streets; * * * One of the overriding policies contained in the Plan was a desire to maintain the City's vibrant neighborhoods. The future land use element addressed those concerns by discouraging strip commercial development and promoting instead the development of commercial land uses at major intersectional nodes. Strip commercial development often has a "cancerous" effect on nearby residential land uses. Problems associated with strip commercial development include encroachment on adjacent residential neighborhoods, increased noise and traffic in residential areas, undesirable aesthetic appearances, and inefficient traffic flow along the roadways on which strip commercial development occurs. The Southside Estates subdivision is vulnerable to encroachment because of the grid pattern of streets, which increases the likelihood of non- residential traffic passing through the subdivision. If lots facing Southside Boulevard were converted to commercial land uses, traffic would likely increase on the neighborhood streets. The neighborhood is a stable neighborhood with a large inventory of homes in good condition. The current noise and traffic along Southside Boulevard has not impaired the neighborhood stability, as the character and condition of homes along Southside Boulevard is comparable with that in the interior of the neighborhood. The residential area in question constitutes an "established neighborhood" as that term is defined in the Plan. There, the term is defined as follows: A neighborhood where platted, or otherwise divided, land has been at least eighty percent developed and occupied without substantial deterioration since such development. The residential area surrounding intervenors properties provides a significant supply of affordable housing to both home buyers and renters. Preservation of that housing stock is preferable to development of additional housing elsewhere. Therefore, maintenance of this neighborhood for residential use supports the housing element of the Plan. As noted earlier, Southside Boulevard is classified as a principal arterial roadway in the Plan. It currently serves as a major north-south roadway. The State has planned and partially constructed State Road 9A, a limited access facility located to the east of Southside Boulevard. When completed, State Road 9A will be the eastern circumferential link to Interstate 95 north and south of the City. State Road 9A will accommodate some of the through traffic currently using Southside Boulevard and will reduce the volume of truck traffic on Southside Boulevard. Contrary to intevenors assertion, conversion of residential properties along this portion of Southside Boulevard would result in increased traffic along the main roadway as well as the service roads. It would also result in an increased number of vehicles entering onto Southside Boulevard. This would further exacerbate an already unacceptable level of service along that road. Southside Boulevard is not a limited access facility as defined in the future land use element of the Plan. Therefore, policy 3.1.12 within that element, which permits residential land use designations adjacent to limited access highways when the negative impact of the roadway can be mitigated, is not applicable. Policy 3.2.2 of the future land use element provides as follows: The City shall promote, through the Land Development Regulations, infill and redevelopment of existing commercial areas in lieu of permitting new areas to commercialize. "Infill development" is defined in the future land use element definitions as "development on scattered vacant sites within the urbanized/suburbanized area of the community." "Commercial infill" is defined as "commercial development of the same type and grade as adjacent commercial uses that is sited between those uses in existing strip commerical areas." Reclassification of this part of Southside Boulevard to a commercial land use would not consitute commercial infill development, as such development would not be occurring on scattered sites or vacant sites, nor are the adjacent uses commercial ones. The area in question cannot be considered a "blighted area" as that term is defined in the future land use element of the Plan. Policy 1.3.1 of the future land use element directs that the City require all non-residential development located along a designated major arterial to construct a service drive which connects to the service drive of adjacent properties, unless otherwise approved by the city traffic engineer. Such a service drive does not exist along this portion of Southside Boulevard. However, the same policy does not require that all property fronting a service drive be classified for commerical use. Further, in the event such service roads are provided in new locations, the policy does not require such roads to be constructed at City expense. Reclassification of intervenors' properties to commercial uses would constitute an expansion of commercial uses adjacent to residential areas. Policy 3.2.4 of the future land use element permits such expansion only if it maintains the residential character of and precludes non-residential traffic into adjacent neighborhoods. Establishment of commercial uses on the property would be a negative influence which would begin the erosion and decay of the surrounding neighborhood. Because of the street grid pattern, it would be difficult, if not impossible, to preclude non-residential traffic from utilizing streets in the adjacent neighborhood. Table L19 of the future land use element is a land use acreage allocation analysis. That table depicts the existing acreage for certain land use categories, the projected acreage needs for those categories to the year 2010, and the acreage allocated to those needs on the future land use map series. The amount of acreage allocated to commerical land use categories is 185.90 percent of the projected need while the acreage allocated to residential land use categories is 127.99 percent of the projected need. Therefore, the land use classifications found on the map series result in a greater overutilization of commercial land use acreage than that found with respect to residential land use acreage. The City's classification of intervenors' properties is similar to that along comparable areas elsewhere in the City. For example, State Road 13 (San Jose Boulevard/Hendricks Avenue) north from Baymeadows Road is characterized by predominately single family residential land uses interrupted by several nodes of commercial development. Like Southside Boulevard, San Jose Boulevard is a four-lane roadway carrying comparable volumes of traffic. This portion of San Jose Boulevard contains a parking lane, but it does not have parallel service roads and the overall width of the right-of-way is narrower than that found on Southside Boulevard. Therefore, homes along this portion of San Jose Boulevard are generally located as close to the right-of-way as those along Southside Boulevard and are closer to the traffic lanes themselves. Traffic counts are comparable, but projections for State Road 13 are as high as 78,426 by the year 2010. Despite this traffic, this area remains a viable, stable residential area. In summary, then, intervenors' properties should be classified as low residential density. This classification is consistent with and supported by the Plan's goals, objectives and policies. Therefore, intervenors' properties should not be reclassified as commercial. The Acree Property Intervenor Acree and his brother, who are both licensed veterinarians, own approximately 460 acres in the northwest portion of the county located on Acree Road (formerly Thomas Road). Of that amount, 360 acres were purchased in 1956 when the brothers started a wholesale dairy as an investment. Three adjoining parcels totaling 116 acres were later purchased as the dairy operation expanded. In 1989, the dairy animals were sold and Acree planned to sell the farm and retire. At that time, he hired civil engineers to develop a conceptual site plan for the purpose of ascertaining the value of his land for development under existing zoning regulatioins. Since the Plan changes his classification and impacts his ability to develop the property, Acree has brought this appeal for the purpose of challenging the land use classification given to his property. The Acree property is designated "agricultural" under the Plan. The allowable densities in an agricultural land use category are contained in the plan category descriptions of the future land use element and provide as follows: One dwelling unit (D.U.) per 100 acres of land for lots of record of 640 acres (section) or more in size at the time of adoption of the 2010 Comprehensive Plan; One dwelling unit (D.U.) per 40 acres of land area for lots of record of 160 acres (1/4 section) up to but not including 640 acres (section) in size at the time of adoption of the 2010 Comprehensive Plan; One dwelling unit (D.U.) per 10 acres of land area for lots of record of 40 acres and up to but not including 160 acres at the time of adoption of the 2010 Comprehensive Plan. One dwelling unit (D.U.) per 2.5 acres of land for single lots of record or the combination of contiguous lots of record under common ownership up to but not including 40 acres which were existing on September 21, 1990. In the event such land area equals 40 acres or more, the allowable number of dwelling units shall be determined according to paragraph (iii) above. Notwithstanding this requirement, one dwelling unit shall be permitted on any nonconforming lot of record which was existing on September 12, 1990. Development on such nonconforming lots of record shall be subject to all other plan provisions. By his petition, Acree seeks to have his property classified as rural residential. This classification is defined in the plan category descriptions of the future land use element as follows: This category is intended to provide rural estate residential opportunities in the suburban area of the City. Housing development at a net density range of up to two (2) dwelling units per acre will be allowed when community scale potable water and sewer facilities are available to the site, and one (1) unit per net acre when the site will be served with on-site water and wastewater facilities. Generally, single- family detached housing and mobile homes will be the predominant land uses in this category. In addition, agriculture, silviculture, and similar other uses may be permitted as secondary uses subject to the standards and criteria in the Land Development Regulations. If the petition is approved, Acree would be allowed to develop his property with a much higher density, and the value of the land would increase correspondingly. Prior to the adoption of the plan, Acree's property was zoned OR (agriculture). Under then-existing regulations, a residential density of one dwelling unit per acre of land was authorized. All other rural land in the county could be utilized for residences in one and one-half acre minimum size lots. This compares with current restrictions described in finding of fact 31. Acree's property is 3 miles by roadway (but only 2.4 linear miles) from the nearest available water and sewer utilities. The property is 1.5 miles from the nearest property classified as rural residential on the future land use maps. Presently, the farm is surrounded by timberland. In originally finding the City's Plan not in compliance, the DCA's concerns included the plan's projections of agriculture land use, its vested development rights, and urban sprawl considerations. As a consequence, in developing the Plan, one of the factors considered by the City was the discouragement of urban sprawl. That term is defined in the future land use element of the Plan as follows: A terminology commonly used to describe certain kinds of growth and development patterns. It refers to scattered, untimely, poorly planned urban development that occurs in urban fringe and rural areas without provisions for utilities and services. Urban sprawl typically manifests itself in one or more of the following patterns: (1) leapfrog development; (2) strip or ribbon development; and (3) large expanses of low-density, single- dimensional developments. This corresponds to the description given the term by the DCA in a technical memorandum issued by the DCA in 1989. The future land use element of the Plan contains the following objective and policies to discourage urban sprawl: Objective 1.1 Ensure that the type, rate and distribution of growth in the City result in compact and compatible land use patterns, an increasingly efficient urban service delivery system and discourages proliferation of urban sprawl through implementation of regulatory programs, intergovernmental coordination mechanisms, and public/private coordination. Policies * * * 1.1.16 Prohibit scattered, unplanned urban sprawl development without provisions for facilities and services at levels adopted in the 2010 Comprehensive Plan in locations inconsistent with the overall concepts of the Future Land Use Element. * * * 1.1.18 Limit urban scale development to the Urban and Suburban areas of the City, as identified in the 2010 Comprehensive Plan, in order to prevent urban sprawl, protect agriculture lands, conserve natural open space, and to minimize the cost of public facilities and services, except for urban villages and other large scale mixed use developments which are designed to provide for the internal capture of daily trips for work, shopping and recreational activities. * * * 1.1.20 Future development orders, development permits and plan amendments shall maintain compact and compatible land use patterns, maintain an increasingly efficient urban service delivery system, and discourage urban sprawl. * * * In addition, leapfrog development is defined in the future land use element as follows: An urbanizing growth pattern which occurs when new land development is sited away from existing urban area, bypassing vacant parcels located in or closer to the urban area that are suitable for development. It typically results in scattered, discontinuous growth patterns in rural areas. To discourage urban sprawl, the City has incorporated into its Plan a provision dealing with public facilities. This provision, which is found in the capital improvements element, establishes areas in which the City would provide public services during the time frame of the Plan. They include the "urban area," where urban services already exist or are programmed to be provided within a short time; the "suburban fiscal commitment area" where services such as water and sewer are in place or planned to be installed within five years; the "suburban non-fiscal commitment area," which is that portion of suburban area in which the City does not commit to providing water and sewer services witin the next five years; and the "rural area," which is predominately undeveloped and unplatted and comprises those areas not intended to be developed by the year 2010. Acree's property is located in the rural area as depicted in the capitol improvement element of the Plan. The sanitary sewer sub-element of the public utilities element of the Plan is also relevant to this issue. It provides in part as follows: Goal 1 The City shall provide for economically and environmentally sound wastewater collection and treatment systems which . . . promote beneficial land use and growth patterns and . . . discourage urban sprawl. Objective 1.1 In order to discourage urban sprawl and correct existing deficiencies, the City shall provide regional wastewater facilities in concert and conformance with the Public Facilities Map as adopted in the Capital Improvement Element. Policies * * * 1.1.5 The City shall not invest in sanitary sewer facilities in the Rural area as defined in the Future Land Use and Capital Improvements Elements, except where necessary to protect the public health and safety. The potable water sub-element of the public utilities element of the Plan contains comparable objectives and policies with regard to providing regional water facilities. The above provisions do not prevent a developer from paying the cost to extend such services to his property. Any facilities installed by the developer, however, must be maintained by the City after such facilities are turned over to the City by the developer. The plan category descriptions found in the Plan for agriculture land uses established a hierarchy based upon the size of the lot of record. The intent of the varying densities is to provide flexibility to owners of smaller lots of record while encouraging large land owners to maintain agricultural land uses, rather than converting to residential development. By law, certain development approved prior to the adoption of the Plan has vested rights. Local governments have included vesting language in their comprehensive plans. Some governments have elaborated upon vesting language to allow exceptions based upon density. The language regarding densities in agriculture land uses found in the Plan is similar to language found in other local government plans. Most plans with density exception language also contain provisions combining contiguous lots of record under common ownership. The density provisions found in the Plan do not make it inconsistent with Chapter 163, Florida Statutes, the DCA's rules, or the state comprehensive plan. At its closest point, Acree's property lies just 400 feet from the Nassau County line. He established that most of the land in Nassau County just north of the Duval County line, and just a short distance from his own, can now be developed at a residential density of one dwelling unit per acre while some can be developed at a residential density of one dwelling unit per one-half acre. He also established that all agriculture land in Nassau County can be developed with a residential density of one dwelling unit per twenty acres for tracts of 320 acres and greater regardless of the amount of land in single or contiguous ownership. However, there is nothing in chapter 163 or the agency's rules which require adjacent land uses in adjoining counties to be identical. Put another way, decisions made in Nassau County with respect to its comprehensive plan are not binding on Duval County. Therefore, the City was not required to classify Acree's property as rural residential merely because an adjoining county had classified nearby land in that manner. Redesignation of Acree's property from agriculture to rural residential would not constitute "infill" development. This is because of the property's distance from other urban development in the county and distance from existing water and sewer servcies. Given the location of Acree's property, reclassification to rural residential land would constitute leap frog development and promote urban sprawl as those terms are defined in the Plan. This is true even though nearby land in Nassau County is considered urban sprawl by City planning officials. Finally, preservation of agriculture land uses is a state concern, especially in areas not projected to be served by water and sewer services. Testimony established that there are several areas in Duval County classified as rural residential which constitute urban sprawl. With the exception of one such area, however, all areas reflect existing residential developments already in place. Table L19 of the future land use element of the Plan is a land use acreage allocation analysis which depicts the existing acreage for certain land use categories, the projected acreage needs for those categories to the year 2010, and the acreage allocated to those needs on the future land use map series. Table L19 indicates that the amount of the acreage allocated to the rural residential land use category is already 194.94 percent of the projected need. In summary, then, in order for the Plan to be internally consistent, Acree's property should be classified as agriculture. This will ensure that development occurs in a compact pattern, which is more cost efficient and compatible with the requirements of the Plan. Therefore, the property should not be reclassified as rural residential since this would be contrary to the goals, objectives and policies within the Plan.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Administration Commission enter a final order finding the City's Plan to be in compliance with the law. DONE AND ENTERED this 24th day of January, 1994, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of January, 1994. APPENDIX TO RECOMMENDED ORDER, CASE NO. 90-7496GM Petitioners Davis and Dekle: Partially accepted in finding of fact 1. Partially accepted in finding of fact 4. Partially accepted in finding of fact 2. Partially accepted in finding of fact 6. Partially accepted in finding of fact 7. Partially accepted in finding of fact 8. 7-8. Partially accepted in finding of fact 5. 9. Partially accepted in finding of fact 8. 10-11. Partially accepted in finding of fact 10. 12-13. Partially accepted in finding of fact 11. Petitioner Acree: Partially accepted in finding of fact 30. Rejected as being irrelevant. 3-4. Rejected as being a conclusion of law. 5. Partially accepted in finding of fact 35. 6-7. Rejected as being irrelevant. See finding of fact 42. 8. Partially accepted in findings of fact 35 and 44. 9. Partially accepted in finding of fact 42. 10. Partially accepted in finding of fact 33. 11. Partially accepted in finding of fact 30. 12. Partially accepted in finding of fact 42. 13. Partially accepted in findings of fact 31 and 41. 14. Partially accepted in findings of fact 32 and 42. 15. Partially accepted in findings of fact 35 and 43. DCA and the City: 1-2. Partially accepted in finding of fact 1. 3-5. Partially accepted in finding of fact 2. 6-7. Partially accepted in finding of fact 3. 8-10. Partially accepted in finding of fact 4. 11. Partially accepted in finding of fact 7. 12. Partially accepted in finding of fact 6. 13. Partially accepted in finding of fact 5. 14. Partially accepted in finding of fact 8. 15. Partially accepted in finding of fact 9. 16. Partially accepted in finding of fact 10. 17. Partially accepted in finding of fact 11. 18-19. Partially accepted in finding of fact 8. 20-21. Partially accepted in finding of fact 4. 22-24. Partially accepted in finding of fact 13. 25. Partially accepted in finding of fact 14. 26. Partially accepted in finding of fact 8. 27-28. Partially accepted in finding of fact 12. 29. Partially accepted in finding of fact 14. 30. Partially accepted in finding of fact 15. 31. Partially accepted in finding of fact 16. 32. Partially accepted in finding of fact 17. 33. Partially accepted in finding of fact 18. 34. Partially accepted in finding of fact 19. 35. Partially accepted in finding of fact 10. 36. Partially accepted in finding of fact 20. 37. Partially accepted in finding of fact 10. 38. Partially accepted in finding of fact 21. 39. Partially accepted in finding of fact 22. 40. Partially accepted in finding of fact 23. 41. Partially accepted in finding of fact 24. 42. Partially accepted in finding of fact 25. 43. Partially accepted in finding of fact 26. 44. Partially accepted in finding of fact 27. 45. Partially accepted in finding of fact 28. 46. Partially accepted in findings of fact 30 and 42. 47. Partially accepted in finding of fact 31. 48. Partially accepted in finding of fact 34. 49. Partially accepted in finding of fact 32. 50. Partially accepted in finding of fact 42. 51-53. Partially accepted in finding of fact 35. 54. Partially accepted in finding of fact 37. 55-56. Partially accepted in finding of fact 38. 57. Partially accepted in finding of fact 39. 58. Partially accepted in finding of fact 46. 59-60. Partially accepted in finding of fact 36. 61. Partially accepted in finding of fact 42. 62. Partially accepted in finding of fact 43. 63. Partially accepted in finding of fact 42. 64. Partially accepted in finding of fact 43. 65. Partially accepted in finding of fact 41. 66. Partially accepted in finding of fact 45. 67. Partially accepted in finding of fact 44. Note - Where a proposed finding has been partially accepted, the remainder has been rejected as being unnecessary, subordinate, cumulative, not supported by the evidence, or a conclusion of law. COPIES FURNISHED: Linda Loomis Shelley, Secretary Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 Dan R. Stengle, Esquire General Counsel Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 Katherine A. Castor, Esquire 2740 Centerview Drive Tallahassee, Florida 32399-2100 Michael A. Altes, Esquire 200 West Forsyth Street, Suite 1100 Jacksonville, Florida 32202-4308 James A. Acree 5031 Dianwood Drive East Jacksonville, Florida 32210 Tracey I. Arpen, Jr., Esquire 1300 City Hall 220 East Bay Street Jacksonville, Florida 32202
The Issue The issue to be resolved in this portion of this power plant site certification proceeding is whether the site for the proposed Seminole Generating Station Unit 3 Project is consistent and in compliance with the applicable land use plans and zoning ordinances of Putnam County, Florida, pursuant to Section 403.508(2), Florida Statutes.1
Findings Of Fact SECI is a member-owned generation and transmission electric cooperative. SECI supplies power to ten electric cooperative members throughout Florida. These cooperatives primarily serve rural areas of the State. SECI's members currently serve approximately 1.6 million customers throughout the State. SECI's headquarters are in Tampa, Florida. SECI first came into existence in 1948 under the Federal Rural Electrification Act to provide electric power to rural areas. Initially, SECI purchased power from other utilities for its individual members. In the 1970s, in response to the oil embargo, SECI's member cooperatives determined it was in their best interest to build their own power supply. SECI then licensed, constructed, and commenced operation of the coal- fired power plant near Palatka, in Putnam County. SECI also has a power plant in Hardee County, Florida. These two power plants allow SECI to provide approximately 70 percent of the power for the member cooperatives, while purchasing 30 percent of the power needs of the member cooperatives from other utilities. The Site is located in the unincorporated area of the county. It is approximately five miles north of the city of Palatka. The St. Johns River is located to the south and to the east of the power plant site. The Site is a 1,300 megawatt facility located on a site comprised of two parcels of land totalling approximately 2,000 acres in size. The larger parcel of the site, which contains the existing coal-fired Units 1 and 2 and almost all related facilities, began operation in 1984. Other existing facilities on the larger parcel include: two boiler buildings and the turbine generator buildings; precipitators, scrubber modules, and a combined flue stack; two natural draft cooling towers; a coal yard for unloading and storage of coal; an A-frame storage building for limestone used in the scrubber process; a rail spur and rail loop used to bring coal into the Plant site; and a coal conveyor to bring the coal from the coal yard to the boilers. The new Unit 3 will be constructed on this larger parcel. The balance of the larger parcel of the Site is in pine flat woods. North and northwest of the power plant is the Lafarge wallboard facility, where combustion by-products from the existing units are converted into synthetic gypsum for the manufacture of wallboard. The Site also includes a smaller parcel of approximately 4.5 acres located approximately 1,000 feet to the south along the St. Johns River. An intake pump house is located on this parcel to pump water from the river for use by the existing units. Currently, there are four underground pipes (one of which is not in use) and an underground duct bank with electrical conduit. The underground pipes and duct bank continue from the smaller parcel to the larger parcel through an existing privately-granted easement. The Site and the existing two steam electric generating units, Units 1 and 2, were certified in proceedings under the PPSA that took place in 1978 and 1979. In 1978, when the Site initially was being developed and certified under the PPSA, Putnam County was in the process of developing its Comprehensive Plan and its Future Land Use Map (FLUM). However, the County had zoning regulations in place, and it and rezoned the larger and smaller parcels as a PUD for the purpose of an electrical generating facility. During the 1978 land use hearing, which also addressed the pipeline easement which provides access to the St. Johns River, the Hearing Officer concluded that the Site was consistent and in compliance with the land use plans and zoning regulations in effect at that time. The Siting Board subsequently adopted the Hearing Officer’s conclusions regarding land use and zoning issues. In its Order Relating to Land Use and Zoning, entered on March 21, 1979, the Siting Board determined that the Site, including the intake pump house and pipeline easement, was consistent and in compliance with the land use plans and zoning ordinances of Putnam County. In the Order Relating to Land Use and Zoning, the Siting Board also ordered the “responsible zoning and planning authorities . . . to refrain from hereafter changing such land use plans or zoning ordinances so as to affect the proposed site.” IN RE: Seminole Electric Cooperative, Inc., Application for Power Plant Site Certification, Putnam County, DOAH Case No. 78-1388, 1979 Fla. ENV LEXIS 10 (Siting Board Mar. 21, 1979. Sierra Club was a party to the original site certification proceeding and is bound by its determinations on consistency with land use and zoning. SECI is proposing to construct a new Unit 3 at the Site designed for a capacity of 750 megawatts. The new unit and related facilities are much like the existing facilities and will utilize many of the existing onsite facilities. Like the two existing units, the new Unit 3 will burn coal as its primary fuel with up to 30 percent petroleum coke. The new unit will consist of a turbine generator building, a new boiler building, precipitators, scrubber modules, and a wet electrostatic precipitator. A single flue gas stack will serve the new unit. A new mechanical draft cooling tower will also be constructed on the site to serve the new Unit 3. The new cooling tower will have a lower profile than the existing natural draft cooling towers. The existing coal yard will be expanded for the new unit and additional facilities will be added in the limestone scrubber area to handle the additional gypsum that will be created. Construction for the new Unit 3 is planned to begin in late 2008. As planned, the new unit is expected to start up in May 2012. SECI's Unit 3 project will integrate the new unit into the existing plant facilities. The existing administration building and parking lot will support the new unit. SECI will continue to use the existing rail spur, including for the delivery of coal and construction materials. The existing switchyard and transmission area will be utilized for the new unit. There will be no new off-site electrical transmission lines for the Unit 3 Project. The existing plant access off Highway 17 will be improved to enhance access for turning vehicles into the site. As indicated, the existing units are supplied with cooling and other service water from the St. Johns River. SECI proposes to utilize the existing pump house and to install an additional water pipeline and duct bank within the easement to supply primarily cooling water and also other service water (primarily for bottom ash handling and for the scrubber system) to the proposed Unit 3. There will be some enhancements to the pumps and motors inside the pump house to increase the capacity of water withdrawals. Otherwise, there will be no changes to the existing pump house for the new Unit 3 project. The cooling and other service water for Unit 3 will be conveyed to the main power plant site by an additional 36-inch pipeline to be placed underground and within the existing private easement. As indicated, the existing easement was created in 1978 and the existing pipelines were installed as part of the development of Units 1 and 2. A second duct bank will also be placed in the existing easement. There will be no facilities constructed above the ground surface within that easement. The easement will be restored to its existing condition after the new water pipeline is installed. The existing land uses adjacent to the Site are primarily undeveloped land. Residential areas along the St. Johns River are the closest development to the Site, with the exception of the Lafarge gypsum plant located adjacent to the larger parcel of the Site. The closest communities are Bridgeport, which is located approximately 3.5 miles to the east, and Bostwick, which is located 2.5 miles to the north. The pattern of development in the area since the existing Units 1 and 2 began operation in 1984 has been single family residential development located along the river and the construction of the Lafarge wallboard plant. With the exception of the wallboard plant, the areas between that residential corridor and the Site, as well as in all four directions around the site, continue to be undeveloped land. There are two existing homes located near the Site. One home is located approximately one mile south of the proposed Unit 3 stack, and another home is approximately one mile west of the Plant site. There is existing power plant infrastructure between the Unit 3 site and those two nearest residences, including the large natural draft cooling towers, wastewater treatment equipment, and other associated facilities. The addition of the proposed Unit 3 would be compatible with the existing land uses at and near the Site. The new Unit 3 will have very similar operating characteristics to the existing units, but will use additional air emissions controls. The residential development along the St. Johns River has continued while Units 1 and 2 have operated. The new Unit 3 will be able to co-exist with existing land uses in that the new Unit 3 is not expected to have a significant adverse impact to nearby residential development. When its Comprehensive Plan with FLUM was adopted (after the Siting Board’s March 1979 Order Relating to Land Use and Zoning), the County designated the larger parcel in the Industrial Future Land Use category to recognize the existing Units 1 and 2 at the site. Electrical power plants are an allowed use in the Industrial future land use category. Approximately two-thirds of the smaller parcel of the site fronting on the St. Johns River was designated Agricultural II and approximately one-third (the part contiguous to the river) was designated Rural Residential under the County’s Comprehensive Plan and FLUM. The existing pump house is located on the Rural Residential part of the parcel. The underground water pipes and electrical duct bank lead from the pump house towards the larger parcel of the Site, which is designated Industrial. The existing pump house and underground water pipes and electrical duct bank are allowed uses in both the Agricultural II and in the Rural Residential future land use districts, as a Type 2 Community Facility. The underground water pipes and electrical duct bank proceed from the smaller parcel to the larger parcel of the Site through a privately-granted easement across property designated Agricultural II on the County’s FLUM. The County’s Comprehensive Plan does not prohibit such facilities in that land use designation. The lands in the pipeline easement are zoned Agricultural. Such facilities also are not precluded in that zoning district. The installation of the existing underground water pipes and electrical duct bank within the easement was approved by Putnam County at the time of the original site certification proceeding for the Site. In October 1978, the Putnam County Code Administrator stated that the County’s zoning for the lands covered by the easement to the St. Johns River did not preclude the use of the easement for the pipeline installation. On January 10, 2006, the Putnam County Commission adopted Ordinance 2006-02, which amended the original PUD zoning approval for the Site. The amended PUD zoning ordinance covers both parcels of the Site. This amended PUD zoning ordinance allows the placement of Unit 3 and its related facilities within both parcels of the Site. The PUD zoning ordinance incorporates a Development Agreement between Putnam County and SECI, which addresses the Unit 3 facilities proposed to be constructed by SECI. As part of the PUD zoning amendments, the Putnam County Board of County Commissioners reviewed SECI's Unit 3 Project for consistency with the County’s Comprehensive Plan. The Commission found the Project to be consistent with the County’s Comprehensive Plan. More specifically, Ordinance No. 2006-02 found that SECI’s proposed amendment to the PUD zoning was “consistent with the Comprehensive Plan,” would “not adversely affect . . . orderly development,” met “the requirements of the Land Development Code,” and “will not be placed in agricultural lands.” (SECI Exs. 12B, 13A, and 13B) The Development Agreement incorporated into Ordinance No. 2006-02 acknowledges that the existing pipeline easement “is not a part of the PUD.” The Development Agreement clearly differentiated between underground pipelines and other aspects of the Unit 3 Project: The existing pipeline easement, which is not a part of the PUD, runs across property zoned for agricultural uses and falling [sic] within the Agricultural II future land use category. Neither the County Comprehensive Plan nor the Land Development Code precludes the repair, replacement or addition of underground water pipes necessary to plant operations. The underground pipes, and the pipeline easement, were part of the original certification and any modifications required to accommodate Unit 3 will be reviewed as part of the site certification process. Subject to site certification under the PPSA, Unit 3 will be constructed primarily east of, but integrated with, existing Units 1 and 2 such that any new development activity will fall within that portion of Parcel 1 designated under the Industrial future land use category. But for the existing pump house, Parcel 2, which is part of the PUD, will remain undeveloped. Pumps within the existing pump house will be replaced or upgraded and existing underground water pipes may be replaced or upgraded, and new underground pipes may be added, but no new uses or structures are intended for Parcel 2. The pipeline easement – which is not part of the PUD – will remain undeveloped although pipes may be repaired, replaced (or additional pipes installed) underground between Parcels 1 and 2. Although no new uses or above-ground structures are anticipated on Parcel 2 or the pipeline easement, both are considered to be part of the electrical power plant to be certified under the PPSA and will be reviewed along with Parcel 1 throughout the State site certification process to which the COUNTY shall be a party. (SECI Ex. 13B, pp. 5-6) Sierra Club participated in the Putnam County January 2006 zoning hearing on the amended PUD zoning for the Site. The Sierra Club did not object to the adoption of the amended PUD zoning ordinance at that hearing. No party has appealed the Putnam County Commission’s amended PUD zoning ordinance for SECI's Unit 3 Project. Sierra Club is now bound by the determinations of land use and zoning consistency in these prior proceedings, as well as in the original site certification proceeding. Putnam County entered into a Stipulation with SECI which addresses land use and zoning issues. In the Stipulation, Putnam County acknowledged that the adoption of Putnam County Ordinance 2006-02, which amended the PUD zoning for the Site, and the approval of the Development Agreement referenced in that Ordinance by the Putnam County Board of County Commissioners, both confirm that the Site, including the proposed Unit 3 and the associated facilities, are consistent and in compliance with applicable land use plans and zoning ordinances as required under Section 403.508(2), Florida Statutes. Despite its participation in both the 1979 site certification proceeding and the 2006 re-zoning process, Sierra Club nonetheless takes the position in this case that the pump house and cooling water pipeline are “industrial” facilities which are not consistent with the future land use designations for the lands occupied by those facilities. Putnam County has adopted a definition of “development” that provides in pertinent part: The following operations or uses shall not be taken for the purposes of this act [the County’s land development code] to involve ‘development’: (b) Work by any utility and other persons engaged in the distribution or transmission of gas or water, for the purpose of inspecting, repairing, redoing, or constructing on established rights-of-way any sewers, mains, pipes, tables, utility tunnels, power lines, towers, poles, tracks or the like. Putnam County’s Land Development Code, Article 12, Section 12.01.01.a.2. This definition of “development” also applies to actions “seeking legislative action to amend this Code and the Comprehensive Plan” of Putnam County. Id. The County’s definition of “development” therefore excludes the additional cooling water pipeline and duct bank within the established easement containing similar pipelines and duct bank between the principal power plant site and the riverside pump house. No Comprehensive Plan amendments or other zoning approvals would be required for those pipelines and duct banks as they are not “development” subject to the plan or the local land development code. Underground pipelines and electrical duct banks such as those proposed for SECI's Unit 3 project are not typically regulated as a land use. All developed areas have water and sewer pipelines that radiate through different zoning districts and that serve the users that subscribe to such water and sewer service. The practical effect of regulating such facilities as “development” could result in a spider web of land use and zoning classifications running wherever those facilities are placed. Even if it were to be concluded that the underground water pipes and electrical duct banks were "development" subject to Putnam County’s Comprehensive Plan, SECI's expert land planner testified without contradiction that they would be considered a Type 2 community facility as defined in the Comprehensive Plan: "Type 2 [Community Facilities and Services] are light infrastructure facilities, including but not limited to, water wells, water tanks, sewage pump stations, electrical substations, and water and wastewater treatment plants with a capacity of less than 500,000 gallons per day." Type 2 community facilities are allowed in all eleven of Putnam County’s Future Land Use categories. As indicated, the smaller parcel of the Site is zoned as a PUD that allows the activities proposed. The easement for the underground water pipes and electrical duct banks is zoned for Agriculture zoning. As indicated, use of the easement for the underground facilities has been approved by the County since 1978. Unrebutted testimony demonstrated that there will be no physical changes to the pump house itself, but only replacement of the pump inside with a larger one with more capacity, and that the additional underground water pipe and duct bank will not be visible, as the land will be restored to current conditions. Sierra Club offered no evidence contradicting Putnam County’s interpretation of its own Comprehensive Plan land development regulations; offered no evidence as to how the community could be adversely affected by the continued use of the pump house, with larger pump, and the addition of underground water pipes and duct bank in the existing pipeline easement; and offered no evidence that these facilities for the pumping and conveyance of river water to the plant site constitute “industrial” uses under the land use plans and zoning regulations of Putnam County.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Siting Board find, pursuant to Section 403.508(2), Florida Statutes, that the site for SECI’s Unit 3 and its related facilities, to be located in Putnam County Florida, as described by the evidence presented at the hearing, are consistent and in compliance with existing land use plans and zoning ordinances and site-specific zoning approvals of Putnam County. DONE AND ENTERED this 31st day of August, 2006, in Tallahassee, Leon County, Florida. S J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 31st day of August, 2006.
The Issue The general issue for determination in this case is whether Amendment 00-D1 to Sumter County’s comprehensive plan (the “Plan Amendment”) is "in compliance" with the Local Government Comprehensive Planning and Land Development Act, Sections 163.3161 through 163.3217, Florida Statutes. (All statutory references are to the 2000 codification of the Florida Statutes.) The initial Petition to Request Administrative Hearing (Petition) alleged numerous reasons why the Plan Amendment should be found not "in compliance." But from the time of the initial Petition--through the Joint Prehearing Stipulation, opening statement at final hearing, and Proposed Recommended Order (PRO)--Petitioners reduced the number of reasons why they contend that the Plan Amendment is not "in compliance" to the following: simultaneous conversion of Future Land Use (FLU) from Agricultural to PUD allegedly inconsistent with parts of the County's Plan's; alleged lack of demonstrated need for land use allocations contrary to Section 163.3177 and Florida Administrative Code Rules Chapter 9J-5 (all rule citations are to the Florida Administrative Code); conversion of FLU from Agricultural to PUD allegedly inconsistent with the Plan's Policy 4.6.1.1 (the so-called "90% rule"); and alleged failure to discourage urban sprawl contrary to Rule 9J-5.0006(6). These are the only compliance issues that still have to be addressed in this proceeding. In addition, Intervenor contends that Sumter Citizens Against Irresponsible Development (SCAID) does not have standing.
Findings Of Fact Intervenor, the Villages of Lake-Sumter, Inc., owns land in the northeast part of Sumter County on which Intervenor plans to construct a mixed-use development of regional impact (DRI) known as the Villages of Sumter. The proposed DRI will encompass approximately 4,679 acres and is anticipated to contain: 11,097 residential dwelling units; 1,250,000 square feet of commercial area; 250,000 square feet of office area; 157,000 square feet of institutional area; 120,000 square feet of hotel (300 rooms); 100,000 square feet convention center; 23,500 square feet of movie theater (8 screens); 512 acres of golf courses (126 holes); 8 marina slips; 602 acres of wildlife management and Kestrel foraging areas; 162 acres of lakes, 162 acres of roads, 31 acres of parks and buffers; and 227 acres of stormwater and open space. The proposed DRI will feature neighborhood and town centers and will extensively utilize clustering, open spaces, and buffering as part of its design. It is anticipated that the Villages of Sumter DRI will have an internal vehicle capture rate of over 60%--i.e., over 60% of vehicle trips starting in the DRI will not go outside the DRI. The DRI will provide water, sanitary sewer, stormwater management, aquifer recharge areas, and other governmental services as part of its development. Eighty percent of the residents in the Villages of Sumter DRI will have to be occupied by persons 55 of age or older, and no one under 19 will be permitted to reside within this DRI. When Intervenor filed its Application for Development Approval (ADA) for the Villages of Sumter DRI, Intervenor also requested the subject Plan Amendment to accommodate the DRI, including a change in the Future Land Use Element (FLUE) and FLUM from Agricultural use to UEA and PUD. The ADA itself served as a major part of the data and analysis supporting the Plan Amendment. (Another major part of the data and analysis was the Evaluation and Appraisal Report (EAR) prepared by the County in 1995.) The western part of the northern boundary of the Plan Amendment parcel (i.e., the Villages of Sumter DRI) will be the western part of the southern boundary of a related DRI developed by Intervenor known as the Tri-County Villages. From there, the Tri-County Villages DRI extends north to the southern border of Marion County and east to the western border of Lake County. (Towards the east, the northern boundary of the DRI drops just a little south of the southern border of Marion County.) Tri- County Villages is a large mixed-use DRI. It includes residential, commercial, recreational, and open space land uses. Prior to the Tri-County Villages DRI, Intervenor or its predecessor also developed other related mixed-use DRIs to the east in Lake County. SCAID was formed in 1993 or 1994 to oppose the Tri- County Villages DRI and 1994 comprehensive plan amendments adopted to accommodate the Tri-County Villages DRI. SCAID, T. Daniel Farnsworth, and James E. Boyd filed a petition initiating Sumter Citizens Against Irresponsible Development, T. D. Farnsworth, and James E. Boyd vs. Department of Community Affairs and Sumter County, DOAH Case No. 94-6974GM, to oppose DCA's determination that the County's 1994 amendments were "in compliance." SCAID, Farnsworth, and Weir are collaterally estopped to deny facts established in DOAH Case No. 94-6974GM (SCAID I). (Latham and Roop are not estopped.) See Conclusions of Law 63-64, infra. In any event, all Petitioners agreed to official recognition of the Final Order entered in DOAH Case No. 94-6974GM. Among the facts established by adoption of the Recommended Order by the Final Order in SCAID I was the history of the earlier DRIs, the Tri-County Villages DRI, and the comprehensive plan amendments required by the Tri-County Villages DRI: [¶4] [I]ntervenor [Villages] is the owner and developer of the Tri- County Villages development located in unincorporated Sumter County. Development which predated the existing Tri-County Villages development commenced in approximately 1968 with Orange Blossom Garden North (OBGN). OBGN was an approximately 1,000-acre project owned and operated by Orange Blossom Hills, Inc. as a mobile home retirement community located mostly in the Town of Lady Lake, Florida. That community lies in the northwestern corner of Lake County, which adjoins the northeastern corner of Sumter County. Because the development of OBGN commenced prior to July of 1973, it is vested for purposes of development of regional impact (DRI) review pursuant to Section 380.06(20), Florida Statutes. [¶5] In 1987, Orange Blossom Hills, Inc. submitted an Application for Development Approval (ADA) with the Town of Lady Lake which requested authorization to develop Orange Blossom Gardens South (OBGS). The OBGS development was an approximately 595-acre extension of the vested OBGN retirement community and was determined by the DCA and Town of Lady Lake to be a DRI. On January 18, 1988, the Town of Lady Lake approved the proposed OBGS development. [¶6] In 1989, Orange Blossom Hills, Inc. submitted to the Town of Lady Lake and the County an ADA requesting a substantial deviation from the OBGS DRI. The substantial deviation request sought authorization to develop Orange Blossom Gardens West (OBGW). OBGW was planned as an approximately 1,700-acre extension to the OBGS DRI. The Town of Lady Lake approved the substantial deviation request through the issuance of an Amended Development Order on May 7, 1990. The County approved the development within its jurisdiction on May 29, 1990. [¶7] In September 1993, intervenor, as successor to Orange Blossom Hills, Inc., submitted an ADA to the County which requested a substantial deviation from the OBGS and OBGW DRI's. By submitting this latest development, intervenor sought to add approximately 1,960 acres to the existing OBGS and OBGW DRI's and modify the development already approved by adding a total of 6,250 residential units and 910,000 square feet of commercial square footage. The overall development was renamed Tri-County Villages. The development order approving the substantial deviation for Tri-County Villages was adopted by the County on September 20, 1994. [¶8] On September 20, 1994, or prior to approval of the Tri-County Villages development substantial deviation, but in conjunction with it, the County adopted plan amendment 94D1 by Ordinance No. 94-6. On November 10, 1994, the DCA determined the amendment to be in compliance. That amendment amended the plan's Future Land Use Map (FLUM) to revise the land use designations on approximately 1,960 acres of land. Specifically, the plan amendment designated as Planned Unit Development (PUD) all areas of the approved OBGW DRI and the additional 1,960 acres referred to in Exhibit 1 of 94D1 as parcels 5 and 8. Prior to the amendment, parcels 5 and 8 had been designated predominantly as agricultural, with small pockets of rural residential. [¶9] The plan amendment also revised the FLUM by extending the urban expansion area to include all of parcels 5 and 8. Prior to the amendment, only a small section of parcel 8 was included in the urban expansion area. [¶10] The plan amendment further included several textual revisions to the Future Land Use Element (FLUE), including a revision to FLUE Policy 1.5.7 concerning the ratio of commercial square footage to residential units and the addition of FLUE Objective 1.14 and Policies 1.14.1 - 1.14.6, which essentially incorporated the concept of sector planning into the plan. [¶11] Finally, the plan amendment revised Policy 2.1.5 of the Sanitary Sewer Element which, subject to submission of appropriate data and analysis, and Department of Environmental Protection approval, reduced the established level of service for sanitary sewer throughout the Tri-County Villages development. SCAID I, 17 F.A.L.R. 4527, 4531-32 (Dept. Community Affairs Aug. 1995). (The Recommended Order may also be found on WESTLAW at 1995 WL 1052949.) At its inception, the Tri-County Villages DRI was projected to build-out in approximately 2015. When the Tri- County Villages DRI first began construction in late 1992, the developer pulled 24 building permits. In 1993, the County issued 406 residential building permits, 365 of which were pulled for the Tri-County Villages DRI. In 1997, the developer pulled 1,052 building permits for the Tri-County Villages DRI. To date, approximately 13,000 homes have been built in the Tri- County Villages DRI. Based upon present projections, the Tri- County Villages DRI is anticipated to be substantially built-out in 2003-04, 12 years ahead of its initially projected build-out date of 2015. Presently, there are numerous cultural and recreational activities, shopping options, medical and governmental services available to residents within the Tri-County Villages DRI. While still designated as a UEA and PUD on the County's FLUM, the Tri-County Villages DRI in fact is a self-contained urban area, especially in the context of Sumter County. Sumter County is mostly rural. According to the 1995 EAR, the County's permanent (non-seasonal) population was projected to be: 38,961 for 1998; 56,000 for 2005; and 64,200 for 2010. The unincorporated portion of the County contains 334,903 acres, approximately 99,436 acres of which are state- owned conservation lands, and approximately 202,000 acres of which are agricultural lands. There are five municipalities in the County--Wildwood, Bushnell (also the County seat), Center Hill, Coleman and Webster. None are as urbanized as the Tri- County Villages DRI. Simultaneous Conversion Objective 7.1.2 of the County's comprehensive plan provides in pertinent part: Upon adoption of this plan, Sumter County shall . . . provide for a compatible and coordinated land use pattern which establishes agriculture as the primary use outside of the urban expansion area boundary and insures retention of agricultural activities, preserves natural resources and discourages urban sprawl. In pertinent part, the County Plan's Policy 7.1.1.2(e) provides that the County's land development regulations governing PUDs should be based on and consistent with the following standards for densities and intensities: Within the Urban Expansion Area, a base density of up to 8 residential units per gross acre in residential areas and 6 units per gross acre in commercial areas are allowed. . . . . Outside of an Urban Expansion Area, a base density of up to 4 residential units per gross acre in residential, commercial and agricultural areas are allowed. Policy 7.1.5.1 allows PUDs "in the following land use districts and at the following densities/intensities of use": 8 dwellings per gross acre in "Residential Areas Inside UEA"; 6 dwellings per gross acre in "Commercial Areas Inside UEA"; and 4 dwellings per gross acre in "Res./Comm. Uses Outside UEA." Petitioners contend that the foregoing objective and policies somehow combine to preclude the simultaneous conversion of Agricultural FLU to UEA and PUD; they appear to contend that these policies necessitated an intermediate conversion to UEA. (Protection of agricultural lands was raised in a more general sense, but this precise issue was not raised prior to final hearing.) But Petitioners argument not only is not persuasive, it is not even easily understood. It is at least fairly debatable that the objective and policies do not combine to preclude simultaneous conversion of Agricultural FLU to UEA and PUD. Even without prior notice of this precise issue, one of the County's expert witnesses in land planning persuasively testified that the cited objective and policies do not combine to preclude simultaneous conversion of Agricultural FLU to UEA and PUD. Even Petitioners' expert land planner ultimately agreed that there is nothing in the Florida Statutes or Florida Administrative Code Rules Chapter 9J-5 to prevent conversion of agricultural uses to more urban uses. Demonstrated Need As reflected in previous Findings of Fact, the subject Plan Amendment is for a highly mixed-use PUD. Of the many mixed uses involved, Petitioners focus on the allocation of land for residential use in their challenge to the demonstration of need for the Plan Amendment. In this context, demonstrated need refers to the existence of adequate data and analysis to demonstrate the need for additional allocation of residential dwelling units on the FLUM. Petitioners assert that the methodology utilized by the County to project need is flawed. Determination of the need for a certain allocation of residential densities starts with a projection of population on the planning horizon (2020). In doing so, all available data and analysis must be considered. (Petitioners also assert that Policy 7.1.2.5(b)1. of the County's comprehensive plan requires such an analysis "utilizing professionally accepted methods," but that policy speaks to additional densities and allocations of land use for developments proposed in agricultural areas, while the Plan Amendment in this case converts the agricultural land to UEA and PUD.) For the purpose of analyzing whether there is a demonstrated need for this Plan Amendment, the County's planner, Roberta Rogers, relied upon need projections made in conjunction with the preparation of the County's EAR. The EAR, prepared in 1999, included a projection of the County's population for the 2020 planning horizon. The EAR projected that the permanent population of unincorporated Sumter County, by the year 2020, will be 79,475. (The total County permanent population is projected to be 94,205.) One of the purposes of an EAR is to provide data and analysis for comprehensive plan amendments. In preparing the population projections reflected in the EAR, Rogers began her analysis by referring to the projections for Sumter County formulated by the Bureau of Economic and Business Research ("BEBR"), as reported in 1996. The 1996 BEBR Report actually reflected projections made in 1995. BEBR publishes yearly reports that state both the estimated current and the projected future populations for each Florida county. The population projections reflected in BEBR Reports are based upon historical trends of 10-15 years' duration. Because the development in the Tri-County Villages DRI is a relatively recent phenomenon, Rogers believed that reliance upon the BEBR projections alone would have resulted in a significant under-projection of the County's future population. As a consequence, Rogers added an annual rate of growth of 1000 building permits per year through 2005 and 500 permits per year through the remaining portion of the planning period for the Tri-County Villages and the Villages of Sumter. Her approach was a conservative approach, since the actual number of building permits issued for the Tri-County Villages DRI in the past two years has significantly exceeded 1000 per year. Rogers conferred with BEBR, prior to completing her analysis, and was assured that her approach was appropriate. Such an adjustment for the Villages is particularly appropriate since the Villages cater to a very specific segment of the population, i.e., persons 55 and above. Over the twenty- year planning horizon relevant to the Plan Amendment, the population of persons in Florida aged 55 and above will increase dramatically as the "baby boomer" population ages. The demand for residential housing for these senior citizens will show a similar dramatic increase. Henry Iler, the Petitioners' land planning expert, took the contrary position, opining that no additional growth factor should be added to the 1996 BEBR projections. However, Dr. Henry Fishkind, an expert in demography who was involved in the original development of the BEBR population projection methodologies, directly contradicted Iler's opinion, concluding instead that Ms. Rogers' methodology was appropriate. As Dr. Fishkind stated that [Sumter] county has experienced a dramatic structural change to its population growth and development because of the Villages, and that has altered the characteristics of its population growth. In light of that, the use of past trends, which is what the bureau [BEBR] does, is simply extrapolate past trends, would not be appropriate, for it would not have taken into account that major structural change. Ms. Rogers identified the structural change, she measured its amount, and then she added on to the bureau's projections, which were extrapolations of the past trends. That's a very appropriate adjustment, and it's the kind of adjustment that econometricians and economists make on a regular basis. DCA's analysis concurred that the high absorption rates in the Tri-County Villages DRI had to be taken into account. To have ignored the explosion of growth in the Tri- County Villages DRI, particularly in view of the generally accepted expectation that the population to be served by the Tri-County Villages and by the Villages of Sumter will experience tremendous growth, would have resulted in an inaccurate population forecast. Even Iler had to concede that he was aware of building permit data being used to project population figures. It is simply not his preferred methodology to use such information. Thus, Rogers' projection of the County's total population for the year 2020 appropriately incorporated all available and relevant data and was formulated using an accepted methodology. While not part of their PRO, Petitioners previously attacked the County's population projections by questioning the continued success of the Villages to attract out-of-state retirees. Primarily through Weir's testimony, they attempted to raise the specter of a reduction of sales and Intervenor's subsequent financial ruin. But there was no credible evidence to support Petitioners' prophecy of doom. On the evidence presented in this case, it would be more rational from a planning standpoint to expect the Villages to continue to be a marketing and financial success. Having reasonably projected future population, it was then incumbent upon the County to determine how many dwelling units would be needed to accommodate anticipated housing needs. This determination was made by Gail Easley, an independent planner retained by the County to assist Rogers in preparation of the EAR. Easley performed this calculation for the County. Easley used 2.46 as the average number of persons per dwelling unit in the County, a figure taken from the BEBR reports (not from 1990 census information, as Iler incorrectly surmised.) There was no evidence that a number other than 2.46 was appropriate. It would not be appropriate for the number of dwelling units needed in the future to be calculated simply by the division of the anticipated population by the average household size. Rather, it is appropriate to apply a "market factor" (or multiplier) in order to ensure that there is a choice of types of housing and to accommodate lands that are not actually useable for residential construction. Even Petitioner's expert, Henry Iler, agreed that the use of a market factor was appropriate in order to ensure sufficient housing supply and to avoid an increase in housing prices. Easley furnished Rogers with the market factor for the EAR. The market factor chosen by Easley was 1.5, a factor she viewed as conservative and as appropriate for a jurisdiction that is beginning to urbanize. In more rural counties, a higher market factor, such as 2.0, should be used. While Iler implied that a lower marker factor would be more suitable, the record clearly established that the market factor used by Easley fell within the range of reasonable choices. (In SCAID I, the ALJ expressly found, in paragraph 31 of the Recommended Order, that the 1.87 market factor used by the County on that occasion was reasonable and actually low compared to factors used for other comprehensive plans that had been found to be "in compliance." As reflected by this Finding of Fact, facts and circumstances bearing on the choice of a market factor for Sumter County have not changed significantly to date. Cf. Conclusion of Law 64, infra.) Applying the 1.5 market factor to the projected population and average household size, the County determined that 62,274 dwelling units will have to be accommodated during the twenty-year planning horizon. (This includes 48,461 units in permanent housing, 9,113 in seasonal housing, and 4,700 in transient housing.) The County then allocated those dwelling units in various land use categories. Much of Petitioners' PRO on this point was devoted to criticizing parts of the evidence in support of the demonstration of need. They state the obvious that Easley did not perform a demonstration of needs analysis for the Plan Amendment in the EAR, but that was not the purpose of the EAR; nonetheless, the EAR contained valuable data and analysis for use in the demonstration of need analysis for the Plan Amendment. Petitioners also questioned DCA's reliance on the DRI ADA in conducting its demonstration of need analysis, based on the timing of the ADA and Plan Amendment submissions and decisions; but it is not clear what it was about the timing that supposedly detracted from DCA's demonstration of need analysis, and nothing about the timing made it inappropriate for DCA to rely on the data and analysis in the ADA. Petitioners criticized Rogers' reference to up-to-date building permit information that was not offered in evidence; but this information only further supported Rogers' demonstration of need analysis. Petitioners asserted that one of Intervenor's witnesses may have overstated residential sales in the Tri- County Villages DRI (1,750 sales a year versus evidence of 1,431 building permits for 1999); but the witness's statement was not used in any of the demonstration of need analyses. Finally, Petitioners attacked one of Intervenor's witnesses for an alleged "conflict of interest, a lack of professional integrity and an indication of bias"; but the basis for this allegation supposedly was evidence that the witness worked for the County while also working for Intervenor or its predecessor for a few years in the late 1980's, not enough to seriously undermine the credibility of the witness's testimony in this case (which in any event had little or nothing to do with the demonstration of need analyses.) It is at least fairly debatable that the County's demonstration of need was based on relevant and appropriate data, and professionally acceptable methodologies and analyses. Likewise, it at least fairly debatable that the County's projections regarding housing needs, the growth in the retirement population, and the absorption rates achieved in the existing Tri-County Villages DRI adequately support the allocation of 11,000 dwelling units permitted by the Plan Amendment. So-called "90% Rule" The County's Plan Policy 4.6.1.1 provides: The County shall maintain approximately 90% of its land area in land uses such as agricultural (including timberland, mining and vacant), conservation, and open (recreation, open space etc.) land uses for this planning period. (Emphasis added.) This policy is found in the Utilities Element of the County's comprehensive plan under a goal to protect and maintain the functions of the natural groundwater aquifer recharge areas in the County and under an objective to protect the quantity of aquifer recharge. Although couched as an approximation, the policy has been referred to as the "90% rule." Based on the evidence presented in this case, it is at least fairly debatable that the subject Plan Amendment is not inconsistent with Policy 4.6.1.1. The primary debate had to do with the proper treatment of certain "open space" provided in the Tri-County Villages DRI and the Villages of Sumter DRI-- 1,032 acres in the former and 2,135 acres in the latter. This "open space" consists of golf courses, preserves, wetlands, parks/buffers, and some stormwater/open spaces. Petitioners' expert refused to count any of this acreage for purposes of the so-called "90% rule" because, while the FLUE and FLUM have Agricultural, Conservation, and Recreation land use categories, there is no category designated "Open Space." (Meanwhile, there is an entire element of the plan entitled "Recreation and Open Space.") The witnesses for the County and DCA counted those 3,167 acres. They reasoned persuasively that the policy's express mention of "open space" (as opposed to a specific land use category designated "Open Space") supports their position. They also argued persuasively for the logic of including "open space," which serves the objective of the policy to "protect quantity aquifer recharge quantity," even if there is no specific land use category designated "Open Space." Counting the 3,167 acres of "open space" in the two DRIs, the percentage calculated under Policy 4.6.1.1 exceeds 90% for existing land uses. Omitting that land, as well as another 500 acres that should have been counted, Petitioners' expert calculated 88.96%. Petitioners' expert also calculated a lower percentage (85.34%) by using land uses he projected for the end of the planning period. However, Petitioners' expert conceded that it was not clear that Policy 4.6.1.1 should be interpreted in that manner. If so interpreted, it would be possible for all plan amendments reducing agricultural, conservation, and open FLUs to be prohibited even if existing land uses in those categories did not fall below "approximately 90%" for another 20 years. It is at least fairly debatable whether such a result is logical, or whether it is more logical to wait until existing land uses in those categories did not fall below "approximately 90%" before prohibiting further FLUE and FLUM amendments. Urban Sprawl Petitioners contend that the Plan Amendment fails to discourage urban sprawl. They attempted to prove seven urban sprawl indicators. But their evidence was far from sufficient to establish any beyond fair debate. Petitioners did not prove that the Plan Amendment promotes, allows or designates for development substantial areas of the jurisdiction to develop as low intensity, low density, or single-use development or uses in excess of demonstrated need. To the contrary, while gross residential density may be relatively low (2.4-2.6 units per gross acre), the Plan Amendment PUD provides for highly mixed-use development, not single-use development, and densities in residential areas within the PUD are significantly higher (up to 5.6 units per acre), especially for Sumter County. Petitioners also did not prove that the Plan Amendment promotes, allows or designates significant amounts of urban development to occur in rural areas at substantial distances from existing urban areas while leaping over undeveloped lands which are available and suitable for development, or that the Plan Amendment promotes, allows or designates urban development in radial, strip, isolated or ribbon patterns generally emanating from existing urban developments. To the contrary, the evidence was that part of the northern boundary of the Plan Amendment parcel coincides with the western part of the southern boundary of the Tri-County Villages DRI, and the Villages of Sumter PUD will be an extension of the Tri-County Villages DRI, which already has all the characteristics of an existing urban area. The reason why the eastern part of the northern boundary of the Plan Amendment parcel does not coincide with the southern boundary of the Tri-County Villages DRI is the existence of land in between which is already in use and not available to become part of the Plan Amendment PUD. Development will not be in a radial or ribbon pattern like (usually) commercial development along main roadways; nor will development be isolated. Petitioners did not prove that the Plan Amendment fails to protect adjacent agricultural areas and activities, including silviculture, and including active agricultural and silvicultural activities as well as passive agricultural activities, and dormant, unique and prime farmlands and soils. Obviously, conversion of agricultural land eliminates such land from agricultural use. But the Plan Amendment protects adjacent agricultural land by phasing development starting from existing urban areas in the Tri-County Villages DRI by mixing in open and recreational uses throughout the Villages of Sumter PUD and by providing some additional buffer between the periphery of the PUD and adjacent agricultural lands. Petitioners did not prove that the Plan Amendment fails to maximize the use of existing public facilities and services. Indeed, Petitioners' land use planning expert admitted at the hearing that he "didn’t have the time or expertise, really, to try to evaluate this particular question." To the contrary, the evidence was that the Plan Amendment PUD will include water, sanitary sewer, stormwater management, aquifer recharge areas, and other governmental services as part of its development. In addition, impact to schools will be minimal or non-existent due to the character of the PUD as a retirement community. Petitioners did not prove that the Plan Amendment fails to provide a clear separation between rural and urban uses. To the contrary, the evidence was that clustering, open spaces and buffering in the Villages of Sumter PUD will provide a clear enough separation between rural and urban uses. Petitioners did not prove that the Plan Amendment discourages or inhibits in-fill development or the redevelopment of existing neighborhoods and communities. Specifically, Petitioners argued that in-fill in the City of Wildwood will be discouraged. But the evidence was to the contrary. Not only would development of the kind envisioned in the Plan Amendment PUD be unlikely to occur in Wildwood, sufficient land is not available for such a development there. Actually, the Plan Amendment might encourage in-fill in Wildwood, where service providers for the Villages of Sumter might be expected to reside. SCAID SCAID was formed in 1993 or 1994 by a small group of Sumter County citizens for the purposes of preserving the "rural lifestyle" of Sumter County, preventing urban sprawl, and ensuring "that development will not be a burden to the taxpayers" of the County. SCAID has about 80 members, who are not required to pay dues. The majority of SCAID's members live in Sumter County, including all of the individual Petitioners in this case. SCAID is not incorporated but has by-laws drafted in 1995 or 1996. The by-laws provide for election of officers for one-year terms, but SCAID has not had an election of officers since 1994. Petitioner, T. Daniel Farnsworth, is and always has been SCAID's president. The evidence was that, when former SCAID member James Boyd resigned, Petitioner Linda Latham was appointed to replace him as secretary. SCAID has held just two meetings since its inception. Approximately 15-20 persons attended each meeting. Most communication with members is by regular and internet mail. Financial contributions are solicited from time to time for litigation efforts initiated by SCAID. Farnsworth, on behalf of SCAID, submitted comments on the Plan Amendment to the County between the transmittal hearing and the adoption hearing. Farnsworth and Weir also testified on behalf of Petitioners at final hearing. The other individual Petitioners did not.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that, under Section 163.3184(9)(b), the Department of Community Affairs enter a final order that Sumter County's Amendment 00-D1 is "in compliance." DONE AND ENTERED this 20th day of February, 2001, in Tallahassee, Leon County, Florida. J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 20th day of February, 2001. COPIES FURNISHED: Martha Harrell Chumbler, Esquire Nancy G. Linnan, Esquire Carlton, Fields, Ward, Emmanuel, Smith & Cutler, P.A. Post Office Box 190 Tallahassee, Florida 32302-0190 Jane M. Gordon, Esquire Jonas & LaSorte Mellon United National Bank Tower Palm Beach Lakes Boulevard, Suite 1000 West Palm Beach, Florida 33401-2204 Terry T. Neal, Esquire Post Office Box 490327 Leesburg, Florida 34749-0327 Colin M. Roopnarine, Esquire Department of Community Affairs 2555 Shumard Oak Boulevard Tallahassee, Florida 32399-2100 Steven M. Seibert, Secretary Department of Community Affairs 2555 Shumard Oak Boulevard, Suite 100 Tallahassee, Florida 32399-2100 Cari L. Roth, General Council Department of Community Affairs 2555 Shumard Oak Boulevard Suite 325 Tallahassee, Florida 32399-2100
The Issue The issue in this case is whether comprehensive plan future land use map amendment (FLUMA) 07-L25, adopted by Marion County Ordinance 07-31 on November 20, 2007, which changed the FLUM designation on 378 acres of Urban Reserve and on 17.83 acres of Rural Land to Medium Density Residential, is "in compliance," as defined in Section 163.3184(1)(b), Florida Statutes.1
Findings Of Fact The parcel that is the subject of the FLUMA at issue (the Property) is approximately 395.83 acres in size. The existing FLUM designation for 378 acres of the Property is Urban Reserve, and the remaining 17.3 acres are designated as Rural Land. Both designations allow a maximum of 1 dwelling unit per 10 acres. The FLUMA would change the designation of the entire parcel to Medium Density Residential (MDR). MDR generally allows up to four dwelling units per acre. However, Future Land Use Element (FLUE) Policy 12.5.k, which also was adopted as part of County Ordinance 07-31, limits the maximum density on the Property to two dwelling units per acre. FLUE Policy 12.5.k also requires: that development on the Property "be served by central potable water and central sanitary sewer services available concurrent with development" and be a Planned Unit Development "to address site design, buffering, and access issues"; and that NW 90th Avenue be reconstructed from U.S. Highway 27 north to the north-eastern corner of the Property and that all traffic facility improvements needed at the NW 90th Avenue/U.S. 27 intersection, including signalization if approved by the Florida Department of Transportation, be constructed prior to the issuance of any certificates of occupancy for the Property. Finally, with respect to the 17.3 acres formerly designated as Rural Land, FLUE Policy 12.5.k defers compliance with the County's Transfer of Development Rights (TDR) Program until application for assignment of a zoning classification for the land. Petitioners' Challenge Intervenors own the Property. Petitioners own property nearby in Marion County. Intervenors and Petitioners commented on the proposed FLUMA between transmittal to DCA and adoption by the County. Petitioners contend: The FLUMA is not consistent with the stormwater drainage, retention, and management policies contained in Policies 1.1.a. and 1.1.d. of the Natural Groundwater Aquifer Recharge Sub-Element of the Infrastructure Element of the Comprehensive Plan. MDR is not suitable or compatible with existing and planned development in the immediate vicinity, as required by FLUE Policy 12.3 of the Comprehensive Plan. The Board of County Commissioners failed to evaluate the FLUMA's impact on “the need for the change” as provided in FLUE Policy 12.3 of the Comprehensive Plan. The FLUMA fails to take into account its impact on “water quality and quantity, the availability of land, water and other natural resources to meet demands, and the potential for flooding,” as required by Section 187.201(15)(b)6., Florida Statutes. The FLUMA is not consistent with Transportation Policy 1.0 of the Comprehensive Plan, which states: "Marion County shall create and maintain transportation facilities that operate in a safe and efficient manner within an established level of service." The FLUMA is not consistent with the State's Comprehensive Plan in that it does not "ensure that new development is compatible with existing local and regional water supplies," as required by Section 187.201(7)(b)5., Florida Statutes. The FLUMA does not direct development away from areas without sediment cover that is adequate to protect the Floridan Aquifer and does not prohibit non-residential uses within 200 feet of a sinkhole, solution channel, or other karst feature, in violation of FLUE Policy 4.2 of the Comprehensive Plan. The FLUMA does not comply with Section 187.201(7), Florida Statutes, concerning the protection of surface and ground water quality in the State. Recharge Sub-Element Policy 1.1.a. and d. Policy 1.1 of the Natural Groundwater Aquifer Recharge Sub-Element of the Infrastructure Element of the Marion County Comprehensive Plan provides in part: The County’s land development regulations shall implement the following guidelines for stormwater management consistent with accepted engineering practices by October 1, 2007: Stormwater retention/detention basin depth will be consistent with the water management district's storm water requirements for Karst Sensitive Areas so that sufficient filtration of bacteria and other pollutants will occur. Avoidance of basin collapse due to excessive hydrostatic pressure in Karst Sensitive Areas shall be given special consideration. * * * d. Require the use of swales and drainage easements, particularly for single family residential development in Karst Sensitive Areas. These are requirements for land development regulations (LDRs); they do not apply to comprehensive plan amendments. In any event, the evidence did not prove that the site is unsuitable for the density allowed under the adopted FLUMA due to karst features. The admissible evidence presented by Petitioners regarding stormwater management in karst topography generally related to flooding problems on the property contiguous to the Property, and to a karst feature referred to as the “63rd Street Sinkhole,” which is located in the general vicinity of the Property. Fay Baird, an expert hydrologist called by Petitioners, testified that the 63rd Street Sinkhole allows stormwater run- off to enter the upper aquifer. Ms. Baird testified generally of the problems and concerns regarding development and stormwater management systems in karst topography. She testified that the Property should be properly inventoried, that specific karst features should be identified, and that any stormwater system designed or developed should take into account karst features to protect against groundwater contamination and flooding. She testified that she had not been on the Property, had not seen or reviewed core borings or other data to determine the depth and nature of the sub-surface, and was not in a position to provide opinions as to whether or not a particular stormwater management system would or could adequately protect against her concerns. Intervenors’ expert, Richard Busche, testified that a stormwater management plan like the one recommended by Ms. Baird was being developed. Compatibility under FLUE Policy 12.3 FLUE Policy 12.3 provides in pertinent part: Before approval of a future land use amendment, the applicant shall demonstrate that the proposed future land use is suitable, and the County will review, and make a determination that the proposed land use is compatible with existing and planned development in the immediate vicinity . . . . Petitioners argued that the proposed MDR development of the Property is incompatible with surrounding agricultural uses. Actually, the Property is surrounded by a mixture of agricultural and residential uses, including residential subdivisions, a golf course, and scattered large-lot residential and equestrian uses. The properties immediately to the south and east of the Property are developed residential properties and are designated MDR. Before the FLUMA, most of the Property was designated Urban Reserve under the County's Comprehensive Plan. Such land "provides for expansion of an Urban Area in a timely manner." FLUE Policies 1.24.B and 2.18. "For an Urban Reserve Area to be designated an Urban Area, it must be compact and contiguous to an existing Urban Area, and central water and sewer must be provided concurrent with development within the expanded area." FLUE Policy 2.18. The Property is compact and is contiguous to existing Urban Area designated MDR. This indicates that the County already has planned for timely conversion of the Urban Reserve land on the Property to urban uses, including MDR. It also means that the County already has determined that at least certain urban uses, including MDR, are compatible with adjacent agricultural uses. The Property is in the receiving area under the County's Farmland Preservation Policy and TDR Program in FLUE Objectives 13.0 and 13.01 and the policies under those objectives. This means that the County already has determined that residential density can be transferred to the Property from the Farmland Preservation sending areas to increase residential density up to one dwelling unit per acre. See FLUE Policy 13.6. This would constitute Low Density Residential, which is an urban use under the County's Comprehensive Plan. See FLUE Policy 1.24.A. By establishing the Farmland Preservation Policy and TDR Programs, the County already has determined that Low Density Residential is compatible with adjacent Rural Land. In addition, Low Density Residential clearly is compatible with MDR. Although not raised in the Petition, Petitioners argued that the Urban Reserve and Farmland Preservation eastern boundary was improperly moved west to NW 90th Avenue. However, that change was made prior to the adoption of Ordinance 07-31 and the FLUMA at issue in this case and is not a proper subject of this proceeding. Demonstration of Need under FLUE Policies 13.2 and 12.3 FLUE Policy 13.2 provides: The Transfer of Development Rights program shall be the required method for increasing density within receiving areas, unless, through the normal Comprehensive Plan Amendment cycle, an applicant can both justify and demonstrate a need for a Future Land Use Map (FLUM) amendment. FLUE Policy 12.3 provides: Before approval of a future land use amendment, . . . the County . . . shall evaluate its impact on: The need for the change; The availability of facilities and services; The future land use balance; and The prevention of urban sprawl as defined by Rule 9J-5.006(5)(g), Florida Administrative Code. The evidence proved that the County interprets FLUE Policy 12.3 to require need and future land use balance to be assessed within the planning districts it has established. There is no need for additional MDR in the County's Planning District 5, where the Property is located. To accommodate the projected population increase in Planning District 5 by 2010, which is the planning horizon for the County’s Comprehensive Plan, an additional 644 dwelling units are needed. There are 1,893 vacant acres of MDR available in Planning District 5. At four units per acre allowed in MDR, the County has an available supply of 7,572 MDR dwelling units in Planning District 5. In the absence of a need in Planning District 5, the County relied on a need demonstration prepared for the Intervenors by Fishkind and Associates.6 Besides being a County-wide analysis instead of a planning district analysis, the Fishkind analysis assumed a planning horizon of 2015, rather than the 2010 horizon established in the Comprehensive Plan. Finally, the Fishkind analysis applied an allocation factor to the total projected need for residential use, most of which already is supplied, resulting in a projection of residential far in excess of the incremental need for additional residential land by 2015, much less by 2010. The result of the Fishkind approach was to allocate enough land for residential use to meet the County-wide projected incremental need for additional residential land use for approximately 45 years, which is five times the calculated incremental need for 2015. Even assuming that a County-wide demonstration of need complied with Marion County's Comprehensive Plan, this is much too high an allocation ratio to use to meet the incremental need projected for a 2015 plan, much less for a 2010 plan. The expert for Intervenors, Stanley Geberer, defended the Fishkind analysis in part by stating that it was comparable to demonstrations of need accepted by DCA in other cases. However, there was no evidence that the facts of those other cases were comparable to the facts of this case. Mr. Geberer also asserted that holding the County to its 2010 planning horizon would make it impossible for the County to plan for the future. However, nothing prevents the County from revising its Comprehensive Plan to plan comprehensively for a longer timeframe. There was no evidence of any other circumstances that would demonstrate a need for the FLUMA at issue in this case. State Comprehensive Plan Policy 187.201(15)(b)6. Petitioners did not prove that the FLUMA fails to take into account its impact on "water quality and quantity, the availability of land, water and other natural resources to meet demands, and the potential for flooding." To the contrary, the evidence was that those items were taken into account as part of the FLUMA. (However, as to the FLUMA's impact on the availability of land to meet demands, see "Demonstration of Need under FLUE Policies 13.2 and 12.3," supra.) Transportation Element Objective 1.0 Transportation Element Objective 1.0 provides: Marion County shall create and maintain transportation facilities that operate in an efficient and safe manner within established levels of service. Petitioners presented no expert testimony or admissible evidence that the FLUMA will change established levels of service or result in transportation facilities operating in an unsafe or inefficient manner. Intervenors presented the testimony of Jonathan Thigpen, an expert traffic engineer, who prepared and submitted to the County a Traffic Impact Study and testified that the FLUMA would not change established levels of service or result in transportation facilities operating in an unsafe or inefficient manner. The ultimate need for transportation improvement, such as turn lanes and traffic lights to mitigate the impacts of development under the FLUMA, will be determined at later stages of development. Petitioners suggested that the FLUMA will result in delays caused by additional traffic, frustrate drivers waiting to turn east on U.S. 27, and induce large numbers of them to seek an alternative route to the north through agricultural areas, some of which have inadequate slag roads. However, Petitioners failed to prove that this result is likely. State Comprehensive Plan Policy 187.201(7)(b)5 Petitioners presented no evidence that the designation of MDR on the Property is incompatible with existing local and regional water supplies. The evidence was that adequate local and regional water supplies exist. Even if they did not exist, the consequence would be less development than the maximum allowed by the FLUMA. FLUE Policy 4.2 FLUE Policy 4.2 provides in pertinent part: In order to minimize the adverse impacts of development on recharge quality and quantity in high recharge Karst sensitive and springs protection areas, design standards for all development shall be required and defined in the LDRs to address, at a minimum, the following: * * * f. Directing development away from areas with sediment cover that is inadequate to protect the Floridian [sic] Aquifer. * * * h. Prohibiting nonresidential uses within 200 feet of a sinkhole, solution channel, or other Karst feature. This policy sets forth requirements for the content of LDRs, not FLUMAs. Petitioners presented no evidence that sediment cover on the Property is inadequate to protect the Floridan Aquifer or that any non-residential uses would be constructed within 200 feet of a sinkhole, solution channel, or other karst feature under the FLUMA. Marion County has adopted amendments to its Comprehensive Plan to protect springs and karst features.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department determine the FLUMA at issue in this case to be not "in compliance" and take further action as required by Section 163.3184(9)(b), Florida Statutes. DONE AND ENTERED this 4th day of February, 2009, in Tallahassee, Leon County, Florida. S J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 4th day of February, 2009.
Findings Of Fact Based upon all of the evidence, including the stipulation of counsel, the following findings of fact are determined: Background The parties Respondent, Franklin County (County), is a local governmental unit subject to the land use planning requirements of Chapter 163, Florida Statutes. That chapter authorizes the County, under certain conditions, to adopt what is known as a small scale development amendment to its comprehensive plan. At issue in this case is a small scale development amendment adopted by the County on October 3, 1996. Petitioner, St. George Plantation Owners Association, Inc. (petitioner), is a not-for-profit corporation organized for the protection and management of the Plantation Area of St. George Island. The island lies just south of Apalachicola, Florida in the Gulf of Mexico. The parties have stipulated that petitioner is an affected person within the meaning of the law and thus it has standing to bring this action. Intervenors, Ben Johnson and Coastal Development Consultants, Inc., are the owners of approximately 58 acres on St. George Island known as the Resort Village Property. The property is adjacent to the St. George Island Airport. A portion of intervenors' property, 9.6 acres, is the subject of the plan amendment being challenged. The nature of the dispute Intervenors' property is subject to a 1977 Development of Regional Impact (DRI) order adopted by the County in 1977. The order has been amended from time to time. Among other things, the order provides conceptual approval for the development of "one or more high quality resort hotels or motels, together with such affiliated uses as may be appropriate or desirable, such as gift and tourist shops, restaurants, recreational activities and similar activities." Intervenors desire to develop the Resort Property Village consistent with the 1977 DRI order. The first part of the project consists of approximately 9.6 acres which they have designated as Phase I. The land is located within the Plantation Area of St. George Island and has a land use designation of residential. In June 1995, intervenors submitted detailed site plans for Phase I to the County. On August 1, 1995, the County conducted a public hearing to review the proposed site plans and specifications for Phase I. It adopted a motion which directed its staff "to review and perfect the plans presented, so that the Board can consider the final approval of the plan." It also directed its staff to provide advice concerning the procedure to be followed. After consulting with the Department of Community Affairs (DCA), which recommended that the comprehensive plan be amended to change the land use to accommodate the commercial uses, the staff recommended that the County adopt a small scale development amendment by changing the designation on its Future Land Use Map (FLUM) for 9.6 acres from residential to commercial. By a 3-2 vote, on October 3, 1996, the County adopted Ordinance No. 96- 22 which changed the designation for the 9.6 acres on the FLUM from residential to commercial. Because the amendment affected ten or fewer acres, the County opted to make the change with a small scale development amendment under Section 163.3187(1)(c), Florida Statutes. According to the site plan which accompanied a Notification of Proposed Change filed with the County on May 26, 1996, the Phase I development includes four hotels, 10,250 square feet of commercial space, 300 square feet of retail space, a beach club, a 325 seat conference center, various support and recreational facilities, and a wastewater treatment plant. The Phase I site plan, however, does not include the three subsurface absorption beds which are required to service the effluent from the wastewater treatment plant. If the absorption beds were included, they would increase the size of Phase I from 9.6 to approximately 14.6 acres. In a petition challenging the adoption of the small scale amendment, petitioner contends that, if the absorption beds are properly included in the land use amendment, the land use area would exceed ten acres and thus would require a full-scale land use amendment subject to DCA review. In response, the County and intervenors have contended that, under the current plan, there is no need to change the land use where the wastewater treatment facility will be located since such facilities are allowed in any land use category. As such, they contend there is no requirement to include such property in Ordinance 96- 22. The Wastewater Treatment Facility The proposed development will be served by a wastewater treatment facility. The Department of Environmental Protection (DEP) has issued a permit to Resort Village Utility, Inc., a utility certified by the Florida Public Service Commission to serve the entire 58-acre Resort Village property. The permit provides that the plant can accommodate up to, but not exceeding, 90,000 gallons of treated effluent per day. The facility consists of the wastewater treatment plant, lines to the plant from the development which carry the untreated wastewater to the plant, and lines from the plant to three sub-surface absorption beds where the treated effluent is disbursed. The absorption beds required for the Phase I project wastewater treatment facility will not serve any residential customers. Rather, they will only serve Phase I and any other subsequent phases of Resort Village development, which is a commercial development. Construction must begin on the wastewater treatment plant once the flow of waste effluent reaches 7,500 gallons per day, or if the wastewater from restaurants reaches 5,000 gallons per day. The Phase I project is required to use this facility once the rate of flow of waste effluent exceeds 10,000 gallons per day. Until these thresholds are met, the project will rely temporarily on aerobic systems to handle and treat waste effluent. Under the permit issued by the DEP, the wastewater treatment facility required for Phase I consists of both a wastewater treatment plant and three absorption beds. Through expert testimony of a DEP professional engineer, it was established that the absorption beds were integral to the design and successful operation of the facility. The County and intervenors acknowledge this fact. Therefore, the "use" that is the subject of the amendment is the entire wastewater treatment facility, including the absorption beds, and "involves" some 14.6 acres. Since the plan amendment does not involve "10 or fewer acres," as required by statute, the amendment cannot qualify as a small scale development amendment and is thus not in compliance. In making these findings, the undersigned has considered a contention by the County that Policy 2.3 of the comprehensive plan sanctions its action. That policy reads as follows: Public utilities needed to provide essential service to existing and future land uses in Franklin County shall be permitted in all the land use classifications established by this plan. Public utilities includes all utilities (gas, water, sewer, electrical, telephone, etc.) whether publicly or privately owned. At hearing, the County planner construed the term "public utilities" as being "minor (utility) infrastructure," including wastewater treatment plants not exceeding 100,000 gallons per day. Relying on this provision, the County reasons that the proposed facility is "minor" infrastructure, since it will only have 90,000 gallons per day capacity, and thus it can be placed in a residential land use category. They go on to argue that, since no change in land use classification is needed to permit the facility, it is unnecessary to include the facility in the plan amendment. According to the County, however, the plant (but not the beds) was included only because it was easier to draw a map for the entire 9.6 acres rather than excise that portion of the land where the plant will be located. Under the same theory, the County has placed at least two existing wastewater treatment facilities in the residential land use category. Those facilities, however, predate the adoption of the comprehensive plan in April 1991, and both serve residential, as opposed to commercial, developments. Moreover, the County admitted that it lacks any "clear" policy about the meaning of "public utilities," and it has never adopted a land development regulation to implement the interpretation given at hearing. The County's position is contrary to conventional land use planning practices which define "utilities" as infrastructure such as water or electrical lines that transport a service and would, by their very nature, be required to cross different land uses. Conversely, conventional land use planning practices define "facilities" as infrastructure that performs a service, such as power plants or pumping stations. This infrastructure does not cross different land use categories. In this case, the absorption beds perform a service by further processing and treating waste effluent from Phase I. Therefore, conventional land use planning practices would logically call for the plant and related absorption beds to be classified as "public facilities" under Policy 2.2(i) of the County's comprehensive plan. That policy defines the term as including "water and sewer facilities." The classification would also be compatible with the definition of "public facilities" found in DCA Rule 9J-5.003(105), Florida Administrative Code. Finally, the County and intervenors point out that the facility may not be constructed for many years, depending on the rate and amount of development that occurs in Phase I. Thus, they contend that there is no immediate requirement for the County to change the future land use designation of the property where the absorption beds will be located. But given the fact that the beds and plant are a single, interrelated system, the County cannot choose to change the land use designation for a portion of the facility while ignoring the remainder.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Administration Commission enter a Final Order determining Ordinance No. 96-22 adopted by Franklin County on October 3, 1996, as not in compliance for failing to meet the criteria of Section 163.3187(1)(c), Florida Statutes. DONE AND ENTERED this 13th day of February, 1997, in Tallahassee, Florida. DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 13th day of February, 1997. COPIES FURNISHED: Barbara Leighty, Clerk Growth Management and Strategic Planning The Capitol, Room 2105 Tallahassee, Florida 32399-0001 Richard W. Moore, Esquire Post Office Drawer 1759 Tallahassee, Florida 32302-1759 Alfred O. Shuler, Esquire Post Office Drawer 850 Apalachicola, Florida 32320-850 L. Lee Williams, Esquire Post Office Box 1169 Tallahassee, Florida 32302-1169 Stephanie Gehres Kruer, Esquire Department of Community Affairs 2555 Shumard Oak Boulevard, Suite 325-A Tallahassee, Florida 32399-2100 Gregory C. Smith, Esquire Office of the Governor The Capitol, Room 209 Tallahassee, Florida 32399-0001
The Issue The issue in these cases is whether the Collier County (County) Comprehensive Plan amendments adopted through Collier County Ordinance Number 02-32 ("the Rural Fringe Amendments" or "the Amendments") on June 19, 2002, are "in compliance," as defined in Section 163.3184(1)(b), Florida Statutes.
Findings Of Fact Background The Amendments at issue in these cases arose from a specific historical background which is relevant to help put them in context. In 1997, the County adopted Evaluation and Appraisal Report-based plan amendments ("EAR-based amendments"). DCA found the EAR-based amendments not to be "in compliance." Following an administrative hearing in which FWF and Audubon intervened, the Administration Commission entered a final order agreeing with DCA's determination. Joint Exhibit J.3. The Administration Commission’s final order, entered on June 22, 1999, directed the County to take the following steps in order to bring its comprehensive plan amendments into compliance: (1) rescind those EAR-based amendments found not in compliance; (2) adopt certain specific "remedial" amendments; (3) initiate an assessment of the area of the County designated on the Future Land Use Map ("FLUM") as Agricultural/Rural; (4) adopt interim amendments to remain in force during the course of the assessment; and (5) no later than June 22, 2002, adopt those plan amendments needed to implement the findings and results of the assessment. Summary of Rural Fringe Amendments In response to the Administration Commission's final order on the EAR-based amendments, the County elected to divide its Agricultural/Rural-designated area into two subdistricts-- Rural Fringe and Eastern Lands--for purposes of the assessment and implementing plan amendments. The Rural Fringe subdistrict was designated as "the Rural Fringe Mixed Used District" (or "the Rural Fringe"). The Rural Fringe is described in the amendments as follows: The Rural Fringe Mixed Use District is identified on the Future Land Use Map. This District consists of approximately 93,600 acres, or 7% of Collier County's total land area. Significant portions of this District are adjacent to the Urban area or to the semi-rural, rapidly developing, large-lot North Golden Gate Estates platted lands. * * * The Rural Fringe Mixed Used District provides a transition between the Urban and Estates Designated lands and between the Urban and Agricultural/Rural and Conservation designated lands farther to the east. The Rural Fringe Mixed Use District employs a balanced approach, including both regulations and incentives, to protect natural resources and private property rights, providing for large areas of open space, and allowing, in designated areas, appropriate types, density and intensity of development. The Rural Fringe Mixed Use District allows for a mixture of urban and rural levels of service, including limited extension of central water and sewer, schools, recreational facilities, commercial uses and essential services deemed necessary to serve the residents of the District. In order to preserve existing natural resources, including habitat for listed species, to retain a rural, pastoral, or park-like appearance from the major public rights-of-way within this area, and to protect private property rights, the following innovative planning and development techniques are required and/or encouraged within the District. J.4 at 50. Under the Amendments, the Rural Fringe was divided into areas designated as Sending, Receiving, or Neutral on the FLUM.18 J.5. Some Sending Areas are also designated Natural Resource Protection Areas (NRPAs). Receiving Lands "are those lands within the Rural Fringe Mixed Use District that have been identified as most appropriate for development . . . ." J.4. at 51. These lands have been chosen because they "have a lesser degree of environmental or listed species habitat value than areas designated as Sending and generally have been disturbed through development, or previous or existing agricultural operations." Id. Approximately 25,000 acres are designated Receiving Lands. Receiving Lands "are also located to allow for the provision of central water and sewer and have excellent access to the County's arterial road network." J.11. at 2. The base density within Receiving Lands is one dwelling unit per five acres. However, through the purchase of development rights from Sending Lands through the Transfer of Development Rights (TDR) program established by the Amendments (discussed in Findings 72-91, infra), Receiving Lands may increase density up to one dwelling unit per acre. Additional density may be obtained if a development preserves more than the minimum required amount of native vegetation. Limited commercial, industrial, and earth-mining uses are also allowed in Receiving Lands. Receiving Lands may also be developed as "Rural Villages." The Amendments provide for the possibility of one rural village within each of the four distinct Receiving Areas in the Rural Fringe. The purpose of rural villages is described as follows: Rural Villages may be approved within the boundaries of the Rural Fringe Mixed Use District in order to: maximize the preservation of natural areas and wildlife habitat within the Rural Fringe Mixed Use District; to reduce the need for residents of the District and surrounding lands to travel to the County's Urban area for work, recreation, shopping, and education; and, to enhance the provision of limited urban and rural levels of service through economies of scale. J.4 at 62. The rural villages permitted in the Rural Fringe must consist of compact neighborhoods with nearby neighborhood or village centers. The neighborhood or village centers are to include retail and office uses; public parks, squares, or greens; civic and government uses; and service facilities. J.4 at 63. Specific provision also is made for open space in and surrounding the rural village. J.4 at 63-64. In addition to the one-village-per-district limitation, the amendments impose the following additional locational criteria on a rural village: (1) it must be at least three miles from any other rural village; (2) it must have direct access to an arterial or collector road, or the developer must bear the cost of a new collector road directly accessing the village; and (3) it must be near already- existing or planned public infrastructure, such as water and sewer facilities. J.4 at 63. In addition, a rural village may only be approved if shown to be fiscally neutral to taxpayers outside the village. J.4 at 65. Neutral Lands "have been identified for limited semi-rural residential development" at a maximum density of one dwelling unit per five acres. J.4. at 55. Limited commercial, industrial, and earth-mining uses are also allowed in Neutral Lands. Approximately 7,000 acres have been designated as Neutral Lands. Sending Lands are those lands "that have the highest degree of environmental value" and "are the principal target for preservation and conservation." J.4. at 58. The residential use of this land is restricted to one dwelling unit per parcel which existed before June 22, 1999, or one unit per 40 acres, whichever yields the greatest density. Nonresidential uses of Sending Land, other than agriculture, are quite limited. There also are specific criteria for the protection of site-specific native vegetation, wildlife habitat, and wetlands. J.4 at 58-62; J.6 at 24, 27, and 29-30. Some of the land designated Sending is also subject to regulation as NRPA. The purpose of a NRPA designation "is to protect endangered or potentially endangered species and to identify large connected intact and relatively unfragmented habitat, which may be important for these listed species." J.4 at 79. Designation as a NRPA also limits the intensity and density of development in an area (J.4 at 58-61) and imposes specific restrictions for the preservation of native vegetation, wildlife habitat, and wetlands (J.6 at 24, 27, and 29). The principal additional effect of NRPA designation is to increase the requirement for the retention of native vegetation. In addition to the changes to the Future Land Use Element (FLUE), the Amendments also affected the Coastal and Conservation Element (CCE), Potable Water Sub-Element, and Sanitary Sewer Sub-Element. Standing of Petitioners and Intervenors The evidence was that the Husseys and Brown own property in Collier County and submitted comments regarding the Rural Fringe Amendments between the transmittal hearing and the adoption hearing. The parties stipulated to the standing of FWF, Audubon, Vision & Faith, and Section 20 Investments. There also was evidence that FWF and Audubon submitted comments regarding the Rural Fringe Amendments at both the transmittal hearing and the adoption hearing and that, at least as of June 14, 2000, they owned property or operated a business in Collier County and had members who reside in Collier County. Century is a for-profit corporation that has its principal place of business in Collier County. Century owns 12.5 acres of land in Collier County. According to the testimony of Donald Lester, President of both Century and Waterford Management, Inc., Century is a wholly-owned subsidiary of Century Holdings, a limited partnership. Waterford is Century Holdings' general partner. Waterford, Century, and approximately 300 other entities are limited partners of Century Holdings. All of these entities and the land they own are managed by Waterford. According to Lester, the various Waterford-managed entities are involved in real estate development and have spent $42 million (over $30 million in "land basis" and $7-8 million on professional fees and expenses) acquiring land for development in Collier County, including approximately $36 million for approximately 3,500 acres in North Belle Meade (NBM) in the Rural Fringe and approximately $6 million for another approximately 2,000 acres farther east in Collier County. There was no evidence that these lands have obtained any master development approval or are otherwise vested for development. Coalition is a not-for-profit corporation having its principal place of business in Collier County. Lester is its Executive Director. There was no evidence that Coalition itself owns property or conducts any type of business activity in Collier County, other than commenting on the Rural Fringe Amendments and participating in these administrative proceedings. Coalition is comprised of approximately 2,000 members. Of these members, approximately 300 are the various entities making up the Century Holdings partnership and managed by Waterford. A total of approximately 320-350 Coalition members own property approximately 3,500 acres in NBM; there was no evidence that the other approximately 1,650 members own property or conduct business in Collier County. An unspecified number of members own approximately 2,000 acres to the east of NBM in Collier County. According to Lester, some members voluntarily donate money to the Coalition; others have "been supporting the proceedings" in some unspecified manner. Lester testified at final hearing that he commented on the Rural Fringe Amendments on behalf of both Century and Coalition during the adoption hearing. He indicated that he filled out and submitted a "speaker card" in order to give his comments and that the card indicated that he was speaking on behalf of both Coalition and Century; but the card was not placed in evidence. The only other evidence on the subject consisted of the transcript of that hearing, which records Lester's introductory statement as follows: "I represent a director of 15,000 coalition. I represent landowners that own property within the TDR area." The transcript also reflects that Robert Diffenderfer commented and stated: "I represent the 15,000 coalition and literally thousands of individuals. . . . On behalf of coalition and the individuals, I have the list here. There are 4,000 plus of them." While the list was not placed in evidence, it can be inferred from Lester's testimony that it would have included Century and the other Coalition members owning land in Collier County. Petitioners' Challenges Petitioners' challenges to the Rural Fringe Amendments were narrowed during the course of this proceeding and now are essentially: (1) whether the County's delineation of Sending and Receiving Lands, especially within the NBM portion of the Rural Fringe, is based upon and reacts appropriately to the best available data19; and (2) whether the TDR Program is based upon and reacts appropriately to the best available data, in particular as to the feasibility of its operation.20 Delineation of Sending and Receiving Lands A. Data and Analysis The process of delineating Sending and Receiving Lands in the Rural Fringe was involved and complex. The County accumulated and considered a wide range of data in the process. Among the data sources used were: (1) the South Florida Water Management District's (SFWMD's) 1994/1995 Land Use/Land Cover map; (2) Natural Resources Conservation Service ("NRCS") soils survey data; (3) soils tables prepared by Florida soils scientist, Howard Yamataki; (4) the National Wetlands Inventory; (5) true-color aerial photographs provided by the County property appraiser's office; (6) the updated FWCC's "Closing the Gaps" Report; (7) FWCC's updated wildlife and wildlife habitat data, including its Florida panther and Florida black bear telemetry data and red-cockaded woodpecker colony data, as well as its updated strategic habitat data and Strategic Habitat Conservation Area (SHCA) maps; and (8) the 1999 U.S. Fish and Wildlife Service (USFWS) Multi- Species/Ecosystem Recovery Implementation Team (MERIT) data for South Florida, in particular pertaining to the Florida panther. The County also actively solicited updated data from property owners and other members of the public. These opportunities for public input included numerous publicly- noticed meetings and hearings before the Rural Fringe Advisory Committee (52 to 53 meetings), the Environmental Advisory Committee, the Planning Commission, and the Board of County Commissioners. At all of these meetings, the public was invited to submit information to the County. On two occasions, notification was mailed to each property owner in the Rural Fringe, alerting them of the County's consideration of the amendments and inviting their input. The County posted signs on the two main roads entering the Rural Fringe, notifying the public of the on-going evaluation of the Rural Fringe and providing a contact name and telephone number for those wanting further information. The County also solicited information from the public via the County web page. Members of the public did submit information, some of which resulted in adjustments to the designations ultimately adopted. For example, the County received data from both Audubon and the Collier County School Board regarding red-cockaded woodpecker (RCW) habitat in the northeast corner of NBM. Similarly, Brown submitted information regarding some of his land holdings in NBM that was used in the ultimate delineation of boundaries between Receiving and Sending. The Husseys also submitted data that was considered. While all information submitted by the public was considered, not all resulted in a change in designation. For example, the County received information regarding jurisdictional wetland determinations on four separate properties and reviewed that information in order to determine whether there was a consistent correlation between jurisdictional determinations and the wetlands land cover information obtained from SFWMD. No consistent correlation was found. In two instances, the jurisdictional wetlands were larger than the area shown as wetlands land cover; in the other two, they were smaller. Despite ample opportunity, the only information submitted to the County by the Husseys was a limerock mining exploration contract on some of their property; Coalition and Century did not make any information available to the County between the transmittal and adoption hearings.21 In its analysis of the data, the County recognized that they were collected during different time periods, ranging from the 1980s through 2001. The soils data from NRCS, for example, was developed in the early 1990's from Landsat satellite imagery from 1985-1989, while the panther telemetry data reflected field data through the end of 2001. SFWMD's data was generated based upon false color infrared aerial photography and reflected changes in land cover through 1995.22 At the time of adoption of the Amendments on June 19, 2002, SFWMD's land use/land cover data was the most recent publicly-available depiction of land uses and land cover in the Rural Fringe.23 Petitioners take the position that the NRCS Soils Survey data was the most accurate data available because it was "ground-truthed." But the NRCS data did not depict land use cover; and it was not proven that the NRCS data accurately and reliably depicted vegetative cover.24 Petitioners also criticized the County for not "ground-truthing" the SFWMD data despite having knowledge of inaccuracies in its depiction of jurisdictional wetlands. But even if it were the County's intention to delineate Sending Lands based on the presence of jurisdictional wetlands, "ground-truthing" would have required the collection of additional data, as Petitioners' own expert conceded. See Conclusion 105, infra. The Husseys also argued in their PRO that the NRCS soils survey data should have been used instead of the SFWMD land use and cover data to delineate wetlands because it was "ground-truthed." But even if it were the County's intention to delineate Sending Lands based on the presence of jurisdictional wetlands, the NRCS data does not purport to identify jurisdictional wetlands and should not be used as a proxy for the presence of jurisdictional wetlands due to drainage activities, particularly in NBM. The Husseys had a Lower Tamiami (Aquifer) Recharge/ Discharge map and a map of the County's Wellfield Protection Zones admitted in evidence and argued in their PRO that the County failed to consider these data in delineating Sending Lands and Receiving Lands. To the contrary, the only evidence was that these maps were considered by the County's environmental specialists. Moreover, there was no evidence that these data were in any way inconsistent with the delineation of Sending and Receiving Lands in the Rural Fringe. Having accepted the SFWMD land cover data as the most accurate indicator of land cover and land uses, the County "updated" Gaps Report maps of biodiversity hotspot areas (which were based upon 1980 satellite imaging) by removing areas shown on the more current SFWMD maps to have been cleared for agriculture by 1995 or 1996. Petitioners contended that "updating" the data in this manner made resulting data and analysis inaccurate and misleading by "masking" natural resource information. But those maps were intended to depict features on parts of the Rural Fringe not mapped as agricultural land use cover on SFWMD's land use cover maps. As such, these "updates" reflected the County’s reasonable determination that, while lands cleared for agricultural use can retain natural resource value, they generally have lower environmental and habitat value than uncleared wetland and forest. No evidence suggested that this judgment was unreasonable. The County's analysis resulted in sensible planning decisions that generally afforded undeveloped wetland or forested areas a higher level of protection than land that has been disturbed through agricultural clearing. Petitioners initially seemed to contend that the County failed to take into account changes in hydrology and wetland vegetative cover in NBM as a result of drainage canals and similar alterations. As the hearing progressed, however, it became clear that from the evidence that the County was aware of the changes in hydrology and vegetative cover in NBM and took those changes into account in its planning decisions. The best data and analysis available as of June 19, 2002, showed that NBM is utilized by both the Florida black bear and the Florida panther. The data and analysis indicate that both of these species make more use of areas to the east (the Florida Panther National Wildlife Refuge and largely undeveloped portions of Northern Golden Gates Estates) and south (the (South) Belle Meade NRPA and largely undeveloped portions of Southern Golden Gates Estates). However, both panther and black bear access NBM from those areas by crossing Everglades Boulevard to the east and Interstate 75 to the south. A significant population of black bear uses NBM. FWCC lists the Florida black bear as a threatened species. Areas mapped by FWCC as strategic habitat statewide would support approximately five populations of approximately 200 individual black bears. (By comparison, FWCC ideally would like to maintain enough strategic habitat to support ten populations of 200 individuals, in part to reduce adverse impacts from natural disasters and genetic problems from inbreeding.) FWCC lists the Florida panther as an endangered species. It is one of the most endangered large mammals in the United States. Only approximately 80 to perhaps 100 panthers are thought to exist in the wild, all in south Florida. The Florida panther faces extinction unless "aggressive action" is taken for its protection. Panthers require large areas of habitat to survive in the wild. Depending on habitat quality, individual males require a home range of 100-150, 200-250, or even as much as 400 square miles; females have a smaller home range of approximately 50-70 square miles. Notwithstanding its general goal of maintaining ten populations of 200 individuals, FWCC's realistic goal for the Florida panther is to maintain current panther habitat and population. The (South) Belle Meade NRPA is considered Priority 1 Panther Habitat by FWCC. Other Priority 1 and Priority 2 Panther Habitat exists farther to the southeast and east. While NBM is not as good for panther habitat, radio telemetry data show that panthers also use NBM. Telemetry data show that panther use of NBM has increased in the last ten years. This could be due in part to the introduction of a female Texas cougar as part of FWCC's breeding program. NBM is currently within the home range of at least one male Florida panther and the introduced female Texas cougar. (Other use is possible, as only about a third of the animals in the population are collared for telemetry.) The female denned and gave birth to three kittens in NBM in 1998. It is possible that panthers frequented NBM in the late 1990's in part because a ranch lessee on Brown property in Section 21 was operating a deer-feeding station there. Panther telemetry data seem to have decreased after Brown required his lessee to cease those operations. However, while panther may have returned to those feeding stations because of the deer being attracted, they first had to have been in the area to become aware of the deer being attracted. This indicates some panther use of NBM prior to establishment of the feeding station. FWCC and United States Fish and Wildlife Service data also indicated to the County that red-cockaded woodpecker (RCW) colonies existed in the old-growth forest areas that remain in the western part of NBM, nesting in cavities in these trees. There also were data that FWCC considered these lands to be RCW strategic habitat. To nest, RCWs need old-growth cavity trees in an area not overgrown with new growth. While there were data that drainage of land in NBM in the RCW strategic habitat area has resulted in invasion of melaleuca (a nuisance exotic species), RCW can continue to use the habitat and forage in and around the melaleuca unless the melaleuca blocks off the cavity tree. There were no data that RCW no longer use NBM due to melaleuca infestation. Much of the now-urbanized areas of Collier County once provided RCW habitat, but development has impaired the value of that land for RCW nesting and foraging. As with panther habitat, traditional RCW habitat has diminished under the current regulatory scheme, and additional protection is needed. The non-NRPA Sending Land in the western part of NBM is the last remaining viable RCW habitat that is not already in conservation status. In gathering and using data in the development of the Rural Fringe Amendments, the County was supported by various state agencies that informally reviewed and commented on the amendments. These agencies supported Collier's approach to the designation of Sending and Receiving Lands. It is found that the County used the best available data and reacted to it appropriately for planning purposes by applying professionally acceptable analysis in review and application of that data. Sending and Receiving Delineations in General Petitioners were most critical of the County's alleged exclusive use of the SFWMD vegetative and land use cover maps to delineate Sending Lands based on the presence of jurisdictional wetlands. But the evidence was clear that the County had no intention of designating Sending Lands solely on the basis of the presence of wetlands. See J.15 at 4 (identifying percentages of wetlands in each category, and showing that the County recognized there were wetlands in Receiving Lands and non-wetlands in Sending Lands). Petitioners' characterization of the County's effort was a gross oversimplification. It also was clear from the evidence that the County did not restrict its data and analysis to the SFWMD maps. Petitioners contended that the County ignored the actual boundary of natural features, such as wetlands, in delineating the boundaries of Sending and Receiving Lands. Instead, for planning purposes, the County attempted to delineate reasonably large, contiguous areas as Sending and Receiving Lands, rather than creating a "Swiss cheese pattern" of intermixed Sending and Receiving Lands, designating isolated pockets of Sending within a large Receiving Area, and vice versa. This made sense from a planning perspective, for a number of reasons, including: (1) it permitted concentration of infrastructure, reducing infrastructure costs; (2) it allowed greater opportunity for the protection of environmentally sensitive lands; (3) large, contiguous areas of habitat are necessary to support a viable population for some of the endangered species present in Collier County-- Florida panther, in particular; and (4) it prevented urban sprawl (in part because sufficient acreage must be available in order for higher density development feasible.) In some instances, the County chose to delineate the boundary between Sending and Receiving Lands with a straight, easily-defined line, rather than using the edge of some feature such as vegetative cover. This also made sense from a planning perspective. A straight boundary, such as a section line, is easier to administer and more easily communicated to the public than a natural feature like vegetation, which would require a survey and is often characterized by a gradual change, rather than the sharp demarcation necessary for a boundary. The County recognized that, as a result of the combined effect of its planning approach, Sending Lands would include some areas neither particularly environmentally sensitive nor--apart from the land surrounding it--valuable habitat. Conversely, some relatively environmentally- sensitive lands would fall within a Receiving Land designation; however, it also recognized that these lands would remain subject to site-specific criteria imposed both by the County's Comprehensive Plan (e.g., amended CCE Policy 6.1.2 criteria for preservation of native vegetation and amended CCE Policy 6.2.3 criteria for protection of wetlands25) and by state and federal regulatory programs. It was not shown that these planning decisions lacked merit; at the very least, their merit is fairly debatable. NBM Delineations Distilled to its essence, the testimony of the natural resource experts called by Petitioners argued that the natural resource data and analysis available at the time of adoption did not justify distinguishing Sending, Receiving, and Neutral Lands in NBM. In other words, their position was that measures for protection of practically the entire NBM would be an appropriate response to the data and analysis on wetland and forest cover and habitat value for Florida panther, Florida black bear habitat, and RCW. But it also is at least fairly debatable that the County's inclusion of Receiving and Neutral Lands in NBM was an appropriate response to the totality of the data and analysis. The Rural Fringe Amendments themselves include the County's rationale for the North Belle Meade (NBM) Receiving designations. The Receiving Areas are generally located in the northern portion of NBM [North Belle Meade] Overlay and are generally contiguous to Golden Gate Estates. Two sections are directly to the south of the APAC Earth Mining Operation. The Receiving Area exhibits areas of less environmental sensitivity than other portions of the NBM Overlay, because of their proximity to Golden Gate Estates and prior clearing and disturbance to the land. Within the Receiving Area of the NBM Overlay, are located Sections 21, 28 and the west 1/4 of Sections 22 and 27, which have been largely assembled under one property ownership. These lands are located south of the existing APAC earth mining operation and have been largely impacted by agricultural operations. The location of Sections 21 and 28 is just to the south and west of Wilson Boulevard located in the southern portion of north Golden Gate Estates. Because an earth mining operation and asphalt plant uses have existed for many years in the area, and the surrounding lands in Sections 21, 28 and the western halves of Sections 22 and 27 are reported to contain Florida Department of Transportation grade rock for road construction, these uses are encouraged to remain and expand. J.4 at 76-77. Section 20 (just west of Section 21) also was designated as Receiving. The southwestern corner of NBM, consisting of Sections 26 (Range 2626), 29, 30, 31, and 32, and the eastern half of Section 36 (Range 26) was designated as non-NRPA Sending, along with the southern halves of Sections 13 and 14 in the northeast corner. The southeastern corner (consisting of the eastern 3/4 of Sections 22 and 27, along with Sections 23, 24, 25, 26, 34, 35, and 36) was designated as NRPA Sending. The northwest corner (Section 24, Range 26) was designated Neutral, as was the northern halves of Sections 13 and 14 in the northeast corner. The 15,552 acres in NBM are surrounded on the south by the South Belle Meade (SBM) NRPA across Interstate 75; on the east by largely undeveloped portions of Northern Golden Gate Estates (NGGE); on the north by a more developed portion of NGGE; and on the west by Urban Fringe future land use, which is sandwiched between NBM and more densely developed urban land use to the west. NGGE is the fastest-growing area of the County. It is part of a proposed sprawling, essentially single-use residential development. To date most actual development in NGGE has occurred in the western part of it, closer to more urban uses, and along Golden Gate Boulevard, which is the main east-west road in NGGE. Because the western part of NBM does not extend as far north as the eastern part, it is farther away from Golden Gate Boulevard and its development than the eastern part of NBM. In NBM, the SFWMD data showed practically all wetland cover with some upland forest interspersed in the six sections making up the southeast corner of NBM, as well as the next section to the southwest (Section 34). The section of land immediately to the north of Section 34 (Section 27) showed up as wetland cover over approximately the eastern half and agricultural use over approximately the western half of the section. The section north of 27 (Section 22) showed up as mostly wetland cover with some agricultural use in the northwest corner and some forested upland in the northeast corner. To the north of Section 22 was a section (number 15) with a mix of urban use, agriculture, wetland, and forested upland cover. Proceeding to the east, Section 14 showed up as mostly forested upland, and Section 13 in the northeast corner with mostly wetland cover with some agriculture. The opposite (far western) side of NBM was shown to have approximately eight sections of land with predominately forest land use cover, interspersed with some wetland and agricultural use. Down the center of NBM are four sections shown by the SFWMD data to have, from north to south: (1) predominately, earth mines and mine pit lakes (Section 16); (2) predominately agriculture (Section 21); (3) a mix of agricultural, forested upland, and wetland cover (Section 28); and (4) approximately half forested (the southwest half) and half wetland cover (the northeast half) (Section 33). Of importance for planning purpose, Wilson Boulevard intersects Golden Gate Boulevard and extends south to the edge of NBM at a point approximately 500 feet west of the northeast corner of Section 16. There are plans to extend Wilson Boulevard south into NBM 500 feet west of the eastern boundaries of Sections 16, 21, 28, and 33. Co-location of infrastructure within the right-of-way of the Wilson Boulevard extension would make sense from a planning standpoint. Allowing development to proceed elsewhere in NBM would exacerbate urban sprawl. It also would be possible to locate rural village North Belle Meade near the proposed Wilson Boulevard extension so that public infrastructure could be provided to both the rural village and the existing residents of NGGE. While Section 20 includes both cleared and uncleared areas, it abuts NGGE on the north and west and other Receiving Land on the east. For that reason, the County considered it to be appropriate for future development. Section 28 also includes a "mixed bag" of habitat features and agriculture. However, the remaining forested areas are less valuable as habitat because they are surrounded by agriculture. In addition, prior to the date of adoption, an application had been filed to allow mining in Sections 20 and 28, as well as in Sections 21 and 27. The permit authorizing this mining was issued in December 2002. Once land is disturbed by mining, it loses its value as panther habitat. Taking all of these factors into consideration, the County judged Section 28 to be more appropriately designated as Receiving. The designation of the western quarters of Sections 22 and 27 as Receiving resulted both from the mixture of disturbed and undisturbed property in those areas and from their location in relation to the planned extension of Wilson Boulevard. This proximity to a planned, future transportation corridor was an important factor in identifying areas appropriate for development. Initially, all of the western part of NBM was to be designated as non-NRPA Sending Lands because of the RCW data. But the County School Board and Audubon furnished additional data pertaining to the extreme northwest section (Section 24, Range 26), which resulted in the ultimate designation of the land as Neutral. Even apart from any environmental or habitat distinctions, there are other valid land use planning reasons for the County's Receiving designations. The proximity of the NBM Receiving Lands to the most populous portion of NGGE makes them appropriate for future, mixed-use development. (In contrast, the part of NGGE near the NBM NRPA is not as densely developed and is not growing as fast as the part immediately north of the NBM Receiving Area.) Since NGGE is a large, single-use residential development, residents are currently required to travel great distances for commercial and other services. By encouraging more compact, mixed-use development in the part of NBM immediately adjacent to the most populous part of NGGE, the County hopes to address this dearth of ancillary, commercial, and institutional uses for the present residents of NGGE, as well as the future residents of NBM. In addition, the NBM Receiving Area is located so as to facilitate an extension of sewer and water service along Golden Gate Boulevard and, from there, into NBM. Recognizing that, with updated data, some of these delineations may need adjustment, the County made specific provision in the amendments for owners of Sending and Neutral Lands to submit additional data in support of a change in designation. J.4 at 61. In summary, it is found that the County's delineations of Sending and Receiving Lands in the Rural Fringe, and in NBM in particular, were based on data and analysis--i.e., they reacted appropriately to the extensive data available to the County on the date of adoption--and accomplish the County's objectives, including protection of environmentally sensitive land and habitat, control of urban sprawl, and successful implementation of the TDR program, which required maintenance of an adequate ratio between Sending and Receiving Lands. See Findings 72-91, infra. At the very least, the delineations are fairly debatable; and the contentions of Coalition, Century, and the Husseys to the contrary are rejected. TDR Program The County recognized that the additional restrictions on much of the property within areas designated as Sending may have an effect on property values. As a consequence, the County included a transfer of development rights ("TDR") program in the Rural Fringe Amendments. The Amendments describe the purpose of the TDR program as follows: The primary purpose of the TDR process within the Rural Fringe Mixed Use District is to establish an equitable method of protecting and conserving the most valuable environmental lands, including large connected wetlands systems and significant areas of habitat for listed species, while allowing property owners of such lands to recoup lost value and development potential through an economically viable process of transferring such rights to other more suitable lands. Within the Rural Fringe Mixed Use District and within designated areas of the Agricultural/Rural Mixed Use District, residential density may be transferred from lands designated as Sending Lands to lands designated as Receiving on the Future Land Use Map, subject to [certain expressly delineated criteria] . . . . J.4 at 50-51. The County's TDR program is an innovative land planning technique that is intended to enhance the protection of environmentally sensitive areas, provide for cost-efficient delivery of public facilities and services, and prevent urban sprawl. J.4 at 50. It is designed to give property owners an incentive to protect their property from development while receiving a return in value through the sale of development rights. In so doing, it also serves as a land management technique to direct development from areas where it is not desired, while preserving the value of that area. TDR programs balance the protection of areas incompatible with development with the preservation of private property rights. They are also recognized as a development tool for overcoming urban sprawl. Through the TDR Program, the owners of Receiving- designated property may increase the allowable residential density on their property by purchasing or otherwise obtaining development credits transferred from property designated as Sending. Forty acres of property in Sending--while assigned an allowable density of only one residential unit--is worth eight development credits (one credit for each five acres). J.4 at 58. The specifics of the TDR program, including the process for the "sale" of development rights and the tracking of these transactions, are to be established by the County in its Land Development Regulations (LDRs) within one year. The specific dollar value of a TDR credit will ultimately be decided by the marketplace. Based on a study of land sales in Collier County, the County's expert, Dr. James Nicholas, concluded that a single credit would probably be worth approximately $18,500. Dr. Henry Fishkind, the expert called by Coalition and Century, agreed that this figure is supported by sales data in the area. For example, a property owner with 40 acres in a Sending area could build one residence on that property, or he could sell eight TDR credits to someone who plans to develop a more compact development in a Receiving Area. J.4 at 58-59. If the Sending Land owner elects the latter, he retains ownership of his property and may still utilize it for certain specifically identified purposes, including agriculture, passive parks, passive recreational uses, certain essential services, and oil extraction. J.4 at 60-61. A property owner with 40 acres in a Receiving area could build eight residences on that property without purchasing any development credits, or he could purchase 32 TDR credits and build 40 residences. Once he has obtained enough TDR credits to achieve this one-to-one density, he could further increase his residential density slightly by preserving more than the minimum required native vegetation on site. J.4 at 51. Dr. Nicholas warned that an excess supply of TDR credits, relative to the amount of Receiving Land available to receive those credits, would undermine the success of the TDR program. The ratio of Receiving Land to Sending Land is critical. Dr. Nicholas prefers a ratio of at least two acres of Receiving Land to each acre of Sending. This ratio is not achieved within the Rural Fringe. Rather, the ratio is approximately 1:1 (25,729 acres of Receiving to 23,720 acres of Sending). See J.15 at 4 (which lists the acreages within each category). Taking into consideration Sending Lands that are already developed, Dr. Nicholas testified that approximately 4,100 TDR credits would be generated from the Sending Lands. Approximately 6,100 credits could be absorbed in the Receiving areas, where densities of up to one unit per acre--an increase of four additional units--can be achieved through a purchase of TDR credits. J.4 at 51. In order to bolster the demand for TDR credits, the Rural Fringe Amendments include a number of other additional markets for credits. First, the amendments provide for a limited transfer of TDR credits outside of the Rural Fringe for two purposes: (1) in-fill in the Urban Area on parcels of 20 acres or less; and (2) transfer from areas within one mile of the Urban boundary into lands designated Urban Residential Fringe. J.4 at 34-35. These two options will create a market for approximately 1,000 additional TDR credits (250 as urban in-fill and 750 in the urban fringe.) In addition, the Amendments provide a market for TDR credits for the development of rural villages. See Findings 11-13, supra, for description of rural villages. Rural villages must be at least 300 acres in size, up to a maximum of 1,500 acres, with the exception that a rural village located south of the (South) Belle Meade NRPA, which is south of Interstate 75, may be as large as 2,500 acres. The minimum and maximum gross densities for a rural village outside NBM are two units per acre and three units per acre, respectively. J.4 at 63. Thus, a rural village outside NBM must include at least 600 residential units, but could have as many as 4,500 or 7,500, depending upon its location. For each TDR credit purchased for the development of a rural village, the purchaser receives one bonus, up to the minimum required density, and the minimum density can only be achieved through the combination of base density, TDR credits, and TDR bonuses. J.4 at 64. Additional density--up to the maximum of three units per acre--can be achieved through the purchase of more TDR credits, through the preservation of more native vegetation on site than the minimum required, and/or through the inclusion of affordable housing. J.4 at 64. Consequently, for a rural village of 1,500 acres outside NBM, the developer would need to build at least 3,000 dwellings (2 units per acre). Assuming that the rural village is surrounded by a 800-acre greenbelt,27 it would start with a base density of 460 units28 and would need to purchase 1,270 TDR credits in order to achieve his minimum density of two units per acre. The provisions applicable to the one rural village permitted in NBM differ slightly. There, the minimum gross density is 1.5 units per acre, of which at least 0.5 units per acre must be obtained through the purchase of TDRs. J.4 at Assuming the same 1,500-acre development with an 800-acre greenbelt as described above, the developer would need to acquire 1,790 units more than would be available through the combined base densities of the village itself and the greenbelt in order to achieve minimum density.29 Of these additional units, 750 would have to be obtained through the purchase of TDR credits. Recognizing that there will probably be no more than two or three rural villages developed, Dr. Nicholas estimated that rural villages will absorb between 4,000 and 7,500 TDR credits, with the greater probability that the absorption rate will be closer to the lower number. Thus, in combination with the other markets for TDR credits created by the amendments, Dr. Nicholas estimated that there will be a demand for approximately 11,100 credits, resulting in a more acceptable ratio of just under three units of demand to one unit of supply. In their PRO, the Husseys attempted to raise the specter that the Amendments create too large a market for TDR credits so as to trigger Dr. Nicholas' concerns that, in that situation, potential transfers would be frustrated because TDR prices would rise to levels making their use infeasible for potential users, including developers of rural villages. But the Husseys based their concerns on maximum potential absorption of TDR credits, raising the supposed ratio of TDR buyers to sellers to 7-to-1 (or even 8-to-1 by disregarding the Urban Fringe one-mile limitation described in Finding 82, supra). The greater weight of the evidence was that the realistic market for TDR credits will be much smaller than the maximum potential absorption rates. Taking the realistic market into account, the probable actual absorption ratio is not much more than 2-to-1, which is ideal according to Dr. Nicholas. It also should be noted that the Husseys' arguments run counter to the testimony of their own expert on the subject. Dr. Fishkind agreed with Dr. Nicholas that there will be a functioning market for TDR credits generated from the Sending Areas, that the County’s TDR program is economically feasible, and that the County has the capacity to administer it. In addition, the Amendments include specific provisions requiring the County to establish a process for evaluating the TDR program. J.4 at 62. The purpose of such monitoring will be to assess whether revisions, such as the addition of either more Sending or Receiving Land or a change in the value of TDR credits, are necessary to ensure the success of the program. In concept, the success of the TDR program in achieving the objectives of directing development away from some areas and toward others, while preserving value in the former, is at least fairly debatable. The program's actual success in achieving these objectives initially hinges upon whether the County has appropriately designated Receiving and Sending Lands. If necessary, changes can be made to improve the program and increase its chances of success.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Community Affairs enter a final order finding the Collier County's Rural Fringe Amendments to be "in compliance." DONE AND ENTERED this 29th day of April, 2003, in Tallahassee, Leon County, Florida. ___________________________________ J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 29th day of April, 2003.
The Issue The issue in this case is whether the Bradford County Board of County Commissioners should approve or deny an application to rezone a 12.76-acre parcel located at the southwest corner of Highway 301 and County Road 18 in unincorporated Bradford County (“the Property”) from Residential, (Mixed) Single Family/Mobile Home (RSF/MH-1) to Commercial Intensive (CI).
Findings Of Fact The Parties Petitioners Craig W. Patterson and Timothy Buffkin own the Property and are the applicants for the proposed re-zoning. Bradford County is the local government responsible for determining the land use designation and zoning classification for the Property and has adopted a comprehensive plan and LDRs which it amends from time to time. The Property The Property is a 12.76-acre parcel located at the intersection of U.S. Highway 301 (US 301) and County Road 18 (CR 18) in unincorporated Bradford County. US 301 is a four-lane divided principal arterial roadway, and CR 18 is a two-lane major collector roadway. The intersection has a traffic light and left turn lanes on US 301. This is the only intersection of a principal arterial road and a major collector road in unincorporated Bradford County. The Property is roughly rectangular, with approximately 1,240 linear feet fronting on US 301 (eastern boundary of the Property) and approximately 450 feet fronting on County Road 18 (northern boundary). The Property is not located within a flood-prone area and has little or no wetlands. Approximately a half mile to the east of the Property is Hampton Lake. The Property is relatively flat. The soils on the property are poorly drained soils, but not indicative of wetlands. The soils and topography of the property do not preclude its development with a system to control stormwater and drainage. Currently, the Property contains one single-family dwelling unit. The Property is bounded on the north by a commercial land use and single-family residences, on the east by vacant and commercial land use, on the south by vacant land, and on the west by vacant land and single-family residences. Current Zoning and Land Use Designations Before October 2004, the Property was designated on the County’s Future Land Use Map (FLUM) as “Residential Low Density,” which authorizes residential development at a density of less than or equal to two dwelling units per acre. On October 21, 2004, the County amended the FLUM to re-designate the Property as “Commercial.” However, the zoning for the Property remained “Residential, (Mixed) Single Family / Mobile Home (RSF/MH-1). The current zoning does not allow the types of uses appropriate under its Commercial land use designation. The Property is also located within an Urban Development Area which is defined in the Future Land Use Element of the comprehensive plan as an “area to which higher density agricultural, residential (single family, multi-family and mobile homes) and commercial and industrial uses are to be directed.” Within Urban Development Areas, lands classified as “Commercial” are to be used for the “sale, rental and distribution of products or performance of services, as well as public, charter and private elementary, middle and high schools.” Certain other uses may also be approved as special exceptions or special permits. Surrounding Land Uses A portion of the land to the north of the Property and all of the land immediately east are within the municipal boundaries of the City of Hampton. The City of Hampton has zoned property at the US 301/CR 18 intersection as “CG”, a commercial designation which includes all of the uses authorized under Bradford County’s CI zoning district. Within the past several years, a truck repair and auto parts facility was located and is still operating east of the Property, across US 301. Farther east, but bordering those commercial lands, a residential subdivision (Fox Hollow) is under development. The Requested Re-zoning The Applicants seek to re-zone the Property to Commercial Intensive (CI). Permitted principal uses and structures allowed within the CI zoning district are consistent with the types of commercial uses listed in the comprehensive plan for the Commercial land use designation, namely retail outlets for the sale of food, home furnishings, vehicles, etc.; service establishments such as barber shops, shoe repair shops, repair and service garages; medical or dental offices; and wholesaling. The CI zoning district is described as “intended for intensive, highly automotive-oriented uses that require a conspicuous and accessible location convenient to streets carrying large volumes of traffic and shall be located within commercial land use classifications on the [FLUM].” The Property meets the description of a conspicuous and accessible location that is convenient to streets carrying large volumes of traffic. Concurrency Management Assessment The requested re-zoning is a “straight” re-zoning request, meaning that the re-zoning is not associated with any particular proposed use. Future development of the site will be subject to development plan review and approval, pursuant to Article Fourteen of the County LDRs. A concurrency reservation is not available until final site plan approval. However, at the County’s request, the North Central Florida Regional Planning Council (NCFRPC) performed concurrency management assessments of the re-zoning in 2006 and again in 2008. In 2006, the NCFRPC provided the County with nonbinding concurrency determination that the applicable service levels would be met or exceeded for potable water (to be supplied by potable water wells); sanitary sewer (to be served by on-site septic tanks); solid waste; drainage; recreation; affordable housing; and historic resources. As to transportation facilities, the 2006 concurrency management assessment determined that the maximum potential development of the Property would generate 389 trips on US 301 at “PM peak hour.” When added to the then-existing PM peak hour trips, based on Florida Department of Transportation (FDOT) traffic count data, US 301 would continue to operate within the adopted level of service (LOS). Between 2006 and 2008, the adopted LOS standard for US 301 was raised from “C” to “B,” meaning that the governmental objective was changed to maintain a freer flow of traffic during evening peak traffic. Therefore, despite the reduction of “background” trips on US 301, the 2008 concurrency management assessment determined that maximum development of the Property would cause the new LOS “B” standard to be exceeded. Petitioners presented a traffic analysis based upon more recent FDOT traffic count data than was used by the NCFRPC for its 2008 concurrency management assessment. The newer data showed a further decline in background trips on US 301, so that adding the maximum potential trips from the Property would no longer result in total PM peak hour trips that would exceed the adopted LOS standard. Petitioners’ more recent data and analysis is professionally acceptable and should be used. At the time of site plan review for any future development of the Property, an updated concurrency assessment will be required and will be based on the number of trips generated by the actual proposed use, rather than the trips that would be generated by the maximum development potential of the Property. The assessment will also use the most current FDOT traffic count data. Compatibility with Surrounding Land Uses The County’s Planning and Zoning Board reviewed the application for re-zoning at its July 10, 2006, meeting. It recommended denial of the re-zoning based upon the impact of the proposed change upon living conditions in the neighborhood. As factual support for the recommended denial, the Planning and Zoning Board’s report cites “all comments received during the said public hearing and the Concurrency Management Assessment concerning said application.” At the August 19, 2008, public hearing held before the Administrative Law Judge, members of the public expressed concern that the CI zoning would be incompatible with the existing residential development to the west, in the Hampton Lake area. Some members of the public also expressed concern about possible future uses of the Property, such as a truck stop or bar. Package stores for the sale of alcoholic beverages, bars, taverns, cocktail lounges, truck stops and automotive service stations can only be approved as special exception uses in the CI zoning district. Special exception uses require approval of the County’s Board of Adjustment after a public hearing, upon a finding that granting the special exception use would promote the “public health, safety, morals, order, comfort, convenience, appearance, propriety or the general welfare.” The Board of Adjustment must also determine that the special exception use would be compatible with adjacent properties. A favorable decision here on the requested re-zoning to CI is not a determination that a bar or truck stop on the Property would be compatible with the adjacent residential area. The LDRs impose site use and design criteria for commercial uses that adjoin residential districts. Site plan approval for commercial developments in CI zoning districts requires the consideration of landscape buffers, height restrictions, off-street parking requirements, lot coverage and yard standards. These development conditions are designed to minimize impacts to adjacent residential areas. Stormwater Some of the speakers at the public hearing expressed concern about stormwater runoff from the Property. One speaker, Michael Davis, testified that stormwater from the Property currently flows across his property. Another expressed concern that runoff from the Property would flow directly to Hampton Lake. On-site stormwater retention facilities would be required for the Property in conjunction with its development. The LDRs require that post-development runoff rates not exceed pre-development conditions. The objective of the required stormwater runoff controls is to approximate the rate, volume, quality, and timing of stormwater runoff that occurred under the site’s unimproved or existing state. There is no basis, at this stage of analysis, to determine that the County’s stormwater regulations are not adequate to prevent adverse stormwater impacts to adjacent residences or to Hampton Lake. Traffic on CR 18 Several speakers expressed concerns regarding increased traffic on CR 18. Petitioners conducted a site-specific traffic count for CR 18 east of US 301 and determined that the peak hour trips are now 131. The capacity for CR 18 is approximately 600. Based upon the total of 389 additional trips generated by the maximum potential development of the Property (on either US 301 or CR 18), the adopted LOS standard for CR 18 would not be exceeded. Petitioners demonstrated that the proposed re-zoning is consistent with the comprehensive plan and the LDRs.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Bradford County Board of County Commissioners approve the requested re-zoning. DONE AND ENTERED this 18th day of September, 2008, in Tallahassee, Leon County, Florida. BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 18th day of September, 2008. COPIES FURNISHED: Ray Norman, Clerk of the Board Bradford County Board of County Commissioners 945 North Temple Avenue Starke, Florida 32091 Marcia Parker Tjoflat, Esquire Charles L. Gibbs, Esquire Pappas Metcalf Jenks & Miller, P.A. 245 Riverside Avenue, Suite 400 Jacksonville, Florida 32202 William E. Sexton, Esquire Brown & Broling 486 N. Temple Avenue Starke, Florida 32091
The Issue Whether the amendment to the Future Land Use Map (FLUM) of the Putnam County Comprehensive Plan (Plan) adopted by Ordinance No. 2001-33 on December 11, 2001, which changes the future land use designation on the FLUM of an approximately 29-acre site from "Rural Residential" to "Commercial," is "in compliance" as that term is defined in Section 163.3184(1)(b), Florida Statutes, for the reasons set forth in the Petition for Administrative Hearing.
Findings Of Fact Petitioner, Frances Z. Parsons, lives at 215 Woodbury Trail, Satsuma, Putnam County, Florida, which is approximately one mile from the racetrack (on the site subject to the Amendment, see Findings of Fact 14 and 15) and has resided there for over seven years. Dr. Parsons understood at the time she purchased the house that a racetrack had been in existence, but was not operational and that no evidence of a racetrack could be seen from the road. A couple of years ago, Dr. Parsons noticed construction-type activity (e.g., earth-moving machines and erection of stadium-type bleachers and lights) occurring on the Property (racetrack site). Trees along the road were "bulldozed down," the site cleared, and a fence erected, after which, Dr. Parsons could see the racetrack from the road and racing commenced. Dr. Parsons also stated that the racetrack is operational and the noise level bothers her at her home. Dr. Parsons described Satsuma as "about a half a mile wide" and "fairly settled for a rural areas, but not for -- it's certainly not downtown." Dr. Parsons stated that the community character has not changed in the last five years. Dr. Parsons submitted oral or written comments and objections regarding the disputed Amendment during the period of time beginning with the transmittal hearing for the amendment and ending with the adoption of the amendment. Respondent, Putnam County, is a political subdivision of the State of Florida. Section 7.54, Florida Statutes. The County is the local government that adopted the Amendment. Respondent, Department of Community Affairs, is the state land planning agency and has the authority to administer and enforce the Local Government Comprehensive Planning and Land Development Regulation Act, Chapter 163, Part II, Florida Statutes, which includes a determination of whether comprehensive plan amendments are "in compliance." Intervenor, Florida Racing, is a private corporation and is the owner of the approximately 29 acres that are the subject of the challenged Amendment. Oral or written comments and regarding the disputed Amendment were submitted on behalf of Florida Racing during the period of time beginning with the transmittal hearing for the Amendment and ending with the adoption of the Amendment. Robert Joseph Potter is the Vice- President and Comptroller for Florida Racing. The Amendment In April 2001, Florida Racing submitted to the County an "Application for Amendment to the Putnam County Future Land Use Map" (Application). This Application requested that the land use designation for an approximately 29-acre site, consisting of five contiguous parcels under the same ownership, be changed from "Rural Residential" to "Commercial" on the FLUM. The Amendment was approved and transmitted to the Department for review under Section 163.3184(6)(a), Florida Statutes. The Department conducted this review, and raised no objections to the proposed FLUM change. On December 11, 2001, the Putnam County Board of County Commissioners (Board) adopted the proposed Amendment by Ordinance No. 2001-33. The Department timely caused to be published a Notice of Intent to find the Amendment "in compliance." On or about February 28, 2002, Petitioner filed a Petition for Administrative Hearing regarding the Department's Notice of Intent. This Petition alleges that the Amendment should be found not "in compliance" on several grounds. This challenge involves an existing development, a racetrack, on the Property. However, the Amendment would allow commercial development on the approximately 29 acres, subject to compliance with applicable Plan and Putnam County Zoning Ordinance (Zoning Ordnance) provisions. (In the Application, Florida Racing advised that proposed uses included a raceway, mobile home park, restaurant, and related amenities.) The Putnam County Speedway, the Surrounding Area, and the Review Process The approximately 29-acre site (five parcels total (Property)) subject to the Amendment is the site of an existing dirt automobile racetrack with bleachers, a press box, associated structures, and a masonry building/house. A commercial mini-warehouse building (personal storage) is located on the westernmost parcel. The racetrack is currently known as the "Putnam County Speedway" (Speedway). The Property is located on the west side of U.S. Highway 17 South between the Dunn's Creek Bridge and Buffalo Bluff Road (County Road 309B). The land surrounding the Property on the west, south, and east are designated as "Rural Residential" on the FLUM, the same as the Property prior to the proposed FLUM change. The land to the north is designated as "Conservation" on the FLUM and designated as vacant and wetlands as existing land uses. The zoning is "A." See Endnote 8. The land to the east is zoned "A" and is vacant as the existing land use. The land to the north and east of the Property is part of the 1,707-acre Murphy Creek Conservation area owned and managed by the St. Johns River Water Management District. The land to the west is zoned "C-2; A" and has an existing land use of commercial, but a future land use designation on the FLUM of Rural Residential. There is also additional land to the west of the Property within the Murphy Creek Conservation Area, a couple of residences and a vacant subdivision that has been determined not to be vested for development. There is a parcel of land to the west that is also owned by Florida Racing. The land to the south is zoned "C-4, C-1, C-2, [and] A" and is designated as vacant and commercial residential as existing land uses, and has a Rural Residential future land use designation on the FLUM. See Endnote 8. The land south of the Property across U.S. 17 includes an existing commercial establishment that includes a mini-warehouse building with outside storage of equipment and semi-trailers. (The mini- warehouse was rezoned in 1986.) Also, further south and west along U.S. 17, there are two or three additional commercial businesses. Mr. Spofford referred to this area as "a commercial cluster." However, most of the uses are nonconforming uses as to the existing Rural Residential future land use, and they would not be able to change to anything more intensive or that would have more adverse impacts on the surrounding residential uses. 1 Behind the mini-warehouse building are two residential neighborhoods with two subdivisions, one with 22 lots of approximately one acre in size and the other with 19 lots, with most of the lots being significantly larger than those in the former subdivision. Another residential area further west than the two subdivisions consists of approximately 40 parcels of land which have been subdivided over time and never platted. About four of these parcels on U.S. 17 are zoned for commercial use. There is also an existing aluminum business west with a C-4 zoning. It appears that almost all of these residential lots and parcels were created after the racetrack was established. The racetrack was in operation prior to the adoption of the Plan and zoning regulations. There is evidence that a racetrack existed before 1975, but has not remained in continuous use throughout that time. The record does not detail the history of the racetrack from its initial approval some time prior to 1975 to the date of the adoption of the Amendment. There is inference that the racetrack was not actively or frequently used in the mid-1990s. (It is noted in the County Staff Report that "[a]n aerial from the Florida Department of Transportation dated February 1972 shows the subject property cleared with what appears to be an oval dirt track. A 1964 aerial photograph did not show a racetrack on the subject property. A review of property appraisal data indicate the racetrack was established around the 1970 to 1972 period.") At some point after approximately 1995, and prior to the adoption of the Amendment, racing returned to the Speedway. An automobile racetrack is not an allowable or conforming use on land designated "Rural Residential." According to the Plan's Future Land Use Element (FLUE), "[t]he Rural Residential land use category depicted on the [FLUM] consists of water front development and developed areas interspersed within the active agricultural areas. These areas are somewhat isolated from the urban areas and rural centers. The development is situated primarily on large lots in the one to five-acre range and is either a homestead or a second home for people who seek the quiet enjoyment of living in a rural environment." As a nonconforming use, the Speedway (racetrack) is subject to County land use and zoning provisions that limit or restrict the ability to undertake improvements. For example, according to the Putnam County Zoning Ordinance 88-1, as amended by Ordinance 91-31 (collectively referred to as County Zoning Ordinance or Zoning Ordinance), the racetrack, as a nonconforming use, is restricted from being extended or enlarged, and repair of its structures is limited. For example, work may be done in any 12-consecutive month period on ordinary repairs, or on repair or replacement of 15 percent of the current assessed value of the particular structure if a nonconforming structure is involved, provided the cubic content of the structure as it existed on the date it became nonconforming shall not be increased in size.2 The intent of these nonconforming use restrictions is to "permit these nonconformities to continue until they are removed, but not to encourage their survival," and it is intended that such uses would become extinguished over time as a result of being prevented from expanding or extensively renovating their structures. See, e.g., County Zoning Ordinance, Sections 2-701-2-708. On March 20, 1998, John Salmons, the Putnam County Planner, advised Tim Keyser, Attorney, that the nonconforming status of the Speedway was still in effect. Mr. Keyser was also informed, in part, that the "Putnam County Speedway may continue to operate under the provisions of the nonconforming use section of the Zoning Ordinance." At the time Florida Racing purchased the racetrack in the 1990's (the specific date is uncertain), some of the existing structures had deteriorated and were in need of repair and/or replacement. To accommodate the renewed activity in racing and the need to upgrade the racetrack, seating at the racetrack was rearranged, new seating was added for children, and a second access driveway was installed north of the existing driveway. In 2000, in a series of letters to Mr. Potter, County staff raised concerns regarding plans to significantly upgrade the racetrack. On September 26, 2000, Mr. Salmons advised Mr. Potter "that the current zoning status for the [S]atsuma racetrack is Nonconforming. As a nonconforming use, the zoning ordinance acknowledges their existence, but does not encourage their survival. As such, there are very strict rules for repairing or maintaining a nonconforming use." Mr. Salmons also informed Mr. Potter that the Property had been designated "Rural Residential" on the County's FLUM at some point subsequent to the racetrack's initial operation. (The racetrack on the Property pre-dates the Plan, including the FLUM land use categories, including "Rural Residential.") Mr. Salmons understood at the time that Mr. Potter had plans to "significantly upgrade the racetrack" and advised Mr. Potter that he "would not be able to proceed with [his] plans." In order to upgrade, Mr. Salmons advised Mr. Potter that he would need to have the Property rezoned and given the current land use designation for the Property, Mr. Potter would need to obtain an amendment to the FLUM to change the Property's land use designation from "Rural Residential" to "Commercial." However, Mr. Salmons further advised that without doing an analysis of the proposed change, he suspected that "it would be difficult for staff to support such a change" "based upon what Future Land Use patterns surround the property." Finally, Mr. Potter was told that he could continue operations "as they were in the past." But, he could not "add seating, restaurants, structures, pave the track or do much more than do some minor maintenance at this time." On December 27, 2000, Mr. Salmons sent Mr. Potter another letter similar in content to the September 26, 2000, letter. Apparently, Mr. Salmons was advised by Mr. Potter that he had already spent in excess of the 15 percent allowed in the Zoning Ordinance. Mr. Potter was advised to stop making improvements until the land use designation was changed and rezoning approved. (There have not been any legal proceedings initiated to determine whether the 15 percent threshold was crossed.) On April 16, 2001, Florida Racing submitted the Amendment Application and requested the FLUM change suggested by County staff for the Property.3 (Florida Racing also requested rezoning of the Property which is not the subject of this proceeding.) Deficiencies in the applications were noted and additional information requested. The County's FLUE of the Plan was adopted on December 12, 1991, and amended on August 24, 1993. Policy A.1.9.3.A.5. of the FLUE describes the "Commercial" land use category and provides in part: The Commercial land use areas depicted on the [FLUM] are current locations of commercial development in the County with expansion areas provided and are intended to serve as the primary commercial locations for the next 10 years. Secondary commercial locations are provided for in the policies for development in the urban service, urban reserve and rural center land use categories. Commercial land uses include activities that are predominantly associated with the sale, rental, and distribution of products or performance of service. Future development shall be allowed as follows: The maximum permitted floor area for a site shall be 1:1. The maximum permitted impervious surface shall be 70 percent of the site.4 The Staff Report dated July 11, 2001, was prepared by Mr. Spofford, A.I.C.P., a senior planner with Putnam County. As noted in the Staff Report, the purpose of the land use "change is to bring a non-conforming automobile racetrack into compliance with the" Plan. Mr. Spofford testified that the scope of the Staff Report was broader than examining the racetrack. However, the primary focus of the Staff Report is the Property being used as a racetrack and not another commercial use. It was determined that the automobile racetrack is a commercial attraction because it attracts spectators for a fee and further noted: As such, the use is not appropriate for the Agriculture I and II and Rural Residential future land use categories. The site and surrounding area do not meet the intent and description of an Urban Service or Urban Reserve future land use category because urban type infrastructure does not currently exist and is not likely within the next 10 years. This means that the use is most appropriate for a Commercial future land use category. The subject site meets the intent of the Commercial category because it is a current location of a commercial- recreational-entertainment type use. Mr. Spofford explained that the data to support the FLUM change is set forth in the Staff Report. (Mr. Salmons, Mr. Spofford's superior, believed the data in the Staff Report was adequate to support the FLUM change.) The Application was reviewed for consistency with the Plan and various provisions of Rule 9J-5. Staff made the following recommendation: The existing automobile racetrack must go through a two step process to become compliant with the Comprehensive Plan and Zoning Ordinance. First, this proposed map amendment must be approved and adopted by the County, and found to be in compliance by the Florida Department of Community Affairs (DCA). The purpose of this public hearing is to determine whether or not the proposed map amendment should be transmitted for state agency review. Therefore, the Planning Commission must recommend to either transmit the map amendment as proposed, transmit the amendment with recommended changes or not to transmit the map amendment. If the proposed map amendment is transmitted, then state agencies will review the proposed map amendment and return comments to the County in October. The County would then likely hold public hearing[s] to consider actual adoption of the map amendment in November and December. When these public hearings are held to consider the map amendment, a rezoning application would simultaneously be reviewed. A rezoning to Planned Unit Development is a negotiable process where the County can gain greater control of the use. If the proposed map amendment is not transmitted, the a rezoning will not be necessary and the automobile racetrack will continue to be a non-conforming use. As a non-conforming use, code enforcement action will be taken to have the improvements removed that consist of an expenditure greater than 15 percent of the assessed value of the structure(s), with the exception of the permitted work that includes the press box and new lighting. All other improvements could be subject to removal. However, as a non-conforming use, the racetrack would be allowed to continue operation so long as it does not expand. This means that the County would not have much control over the days and hours of operation and other critical site design issues. Although this is not the ideal location for a racetrack, the fact is it has existed on the subject property and has been determined to be a bona fide non- conforming use. Research of County records and other known available sources of information indicates that the racetrack was established prior to the residential development in close proximity south of the subject site. The request for a large-scale comprehensive plan map amendment from Rural Residential to Commercial appears to be consistent with the Comprehensive Plan. Therefore, staff recommends that the proposed map amendment be transmitted to the Florida Department of Community Affairs with a request for their review. On July 11, 2001, the Putnam County Planning Commission unanimously approved the FLUM change after receiving comments. On July 24, 2001, the Board held a public hearing to consider the Amendment and approved same. The FLUM Amendment was transmitted to the Department. Pursuant to the Department's review of the Amendment, a Memorandum dated October 4, 2001, was prepared by Russell Paul Darst, a planner with the Department, and routed to James Stansbury and Mike Sherman, the section administrator, and ultimately to Charles Gauthier, A.I.C.P., and Bureau Chief, who issued the Department's Notice of Intent. Mr. Darst, as well as others at the Department, had no objections to the Amendment. In the Memorandum, Mr. Darst concluded: "The proposed FLUM change for this 29-acre property is from Rural Residential to Commercial. The property has been used for a race track since about 1970. The amendment would change the FLUM designation for the property to reflect the actual and long-standing use of the property. This use is not allowed in the Rural Residential FLUM category." This was the crux of the data and analysis relied on by Mr. Stansbury of the Department. The Memorandum also reflected the Northeast Florida Regional Planning Council comment: "Since the raceway already exists, the land use change will not create any additional impacts to regional resources. The proposed land use change may even protect regional resources in the future by granting the County the ability to regulate the property under the most appropriate zoning classification." Dr. Darst stated that in reviewing a FLUM amendment for the Department, it would be typical to examine the existing use of the land before making his recommendation. In reviewing the County's proposed FLUM change, Mr. Darst believed, based on his discussions with County staff, that the racetrack was not expected to expand (and not that it could not) and that the change in the FLUM would give the County "part of a means of gaining effective control over [the operation of the racetrack]." He reiterated that the FLUM change would reflect the actual and long-standing use of the Property as a racetrack. On December 11, 2001, during the public hearing, the Board approved the FLUM Amendment and transmitted the approval package to the Department. On February 13, 2002, the Department had published its Notice of Intent to find the Amendment "in compliance." The Challenges Petitioner alleges that the Amendment is not "in compliance" on several grounds: first, there is no "need" for additional land to be designated for a commercial use in Putnam County; second, the Amendment and proposed land use is not compatible with the community character and surrounding land uses; and, third, the Amendment is inconsistent with provisions of the Plan, Chapter 163, Part II, Florida Statutes, and Rule 9J-5, Florida Administrative Code. Need The term "need" as used in growth management refers to the amount of land required to accommodate anticipated growth. Section 163.3177(6)(a), Florida Statutes. Local governments are to analyze by acreage how much land within each land use category5 they need to accommodate projected growth through the planning timeframe, and then base their comprehensive plan on this estimate. Rule 9J-5.006(2)(c), Florida Administrative Code. The calculus of need is rather simple and, for that reason, inexact. The calculation of how much land is needed to accommodate the projected population involves comparing what is available for development under the comprehensive plan with the projected population over the same planning timeframe applicable to the plan. An "allocation ratio" to express this need can be derived by dividing the development potential by the projected population. For example, if a comprehensive plan allocated 100 residential dwelling units over the planning timeframe and the jurisdiction's population was projected to increase by 100 over the same time, there would be an allocation ratio of 1:1. This ratio would express an exact match between supply and demand. A ratio of 2:1, on the other hand, would demonstrate that the jurisdiction had twice as much land as designated for use as the projected population is expected to need. There is no allocation ratio adopted by statute or rule by which all comprehensive plans and plan amendments are judged. There is evidence that the County has more vacant land designated "Commercial" than is needed to accommodate its projected population.6 There is data and analysis which indicates an excess of vacant commercially-designation land on a County-wide basis. For example, Florida Racing Exhibit 1 is a copy of data and analysis in support of the FLUE. This data and analysis indicates that at least as of 1991, and projected to 2001, the County has an over-allocation of need for commercial land of about two times or, stated otherwise, the County has a 2:1 allocation ratio for commercial. This data is reflected in Petitioner's Exhibit P. Mr. Spofford explained that the population data was compiled prior to 1991, has not been updated, is not meant to provide a "detailed analysis," and it is only useful for providing the acreage for each planning district. The population for each planning district is then compared to the acreage to determine the allocation of commercial to service that population. From a very general standpoint, Mr. Spofford analyzed the FLUM Amendment application in light of whether more commercial acreage was needed. Mr. Spofford explained that because the Property was so close to the edge of the planning district, it was difficult to compare the commercial and population need. However, Mr. Spofford opined that the Planning District 1 (which includes the Property) and the one to the northeast are not over-allocated for commercial use. He also opined that, generally, "more is needed, if -- especially if you're looking out 20, ten or twenty years." Petitioner did not come forward with any independent or up-to-date analysis to demonstrate the County is in fact over-allocated for commercial land use. On the other hand, Fred Goodrow, A.I.C.P., opined that the County was over-allocated regarding the need for more commercial in light of the data previously mentioned. The existence and extent of any commercial over- allocation in Putnam County is, at best, fairly debatable. Nonconforming Use, Inconsistency, and Incompatibility Petitioner asserts that the Amendment is not "in compliance" because it fails to eliminate or reduce a nonconforming use in violation of Section 163.3177(6)(a), Florida Statutes, and Rule 9J-5.006(3)(b)3. and (3)(c)2., Florida Administrative Code. Petitioner also argues that the Commercial land use designation which would attach to the Property is incompatible with the character of the community and adjacent land uses. Petitioner also contends that the Amendment is inconsistent with several Plan provisions. Section 163.3177(2), Florida Statutes; Rule 9J-5.005(5), Florida Administrative Code. Objective A.1.3 of the FLUE requires that "[u]pon plan adoption, Putnam County shall act to eliminate or reduce uses inconsistent with the uses identified on the [FLUM] and associated adopted Goals, Objectives and Policies through implementing the following policies." Policy A.1.3.1 of the FLUE requires revision of the County's Land Development Regulations, specifically the County Zoning Code, "to reinforce its current provisions regarding the elimination of nonconforming land uses by expanding the definition of nonconforming land uses to include all uses which are inconsistent with the Future Land Use Map 2001 or cannot be made compatible with adjacent land uses. The requirements of this provision shall be enforced upon application for building permits to repair or improve such structures."7 The nonconforming use provisions of the Zoning Ordinance apply to and implement the FLUM. An automobile racetrack is not an appropriate use to put in a Rural Residential future land use category. In theory, one purpose of this land use designation is to protect residents from the intrusion of noisy racetracks which can impact an adjacent residential user. The dispute in this case is clearly framed. Petitioner contends that because the Property was designated "Rural Residential" when the County's Plan was adopted, the Speedway (racetrack) is a nonconforming use which must be restricted and eventually eliminated. Petitioner argues that the County lacks the authority to amend its FLUM to make the Speedway a conforming use under the Plan. Respondents and Florida Racing contend that the County has the authority to amend the FLUM, and acted properly in this instance in adopting the Amendment. The County has the authority to amend its FLUM, including the designations of properties as long as the designations are consistent with other provisions of the Plan and applicable provisions of Chapter 163, Part II, Florida Statutes, and Rule 9J-5, Florida Administrative Code. The persuasive evidence indicates that an automobile racetrack is an allowable use in the Commercial future land use category as opposed to the Rural Residential category. If the Amendment is approved, the raceway would no longer be considered a nonconforming use for Plan purposes, and could undertake improvements without the restrictions that accompany such a use, subject to compliance with applicable zoning requirements. Stated otherwise, the racetrack could expand without complying with the nonconforming use restrictions, subject to compliance with the nonconforming standards in the Zoning Ordinance because the Property would remain a nonconforming use under the Zoning Ordinance. (Of course, a zoning change for the Property, as contemplated in the County's Staff Report, would create different considerations as noted below.) The Property is currently zoned C-2 and A, with the bulk of the property zoned agriculture.8 If the Amendment is approved, the next step would be for the Property owner to apply for a zoning change, e.g., special exception, or pursue a planned unit development. Under either scenario, the County could impose conditions on the use of the Property such as the amelioration of off-site impacts. On the other hand, if the racetrack continued as a nonconforming use, the persuasive evidence indicates that the County would be limited in establishing any further limitation on the use of the Property, such as duration and frequency of use, e.g., hours of operation and other site design issues. There is no persuasive support for the proposition that all subsequent Boards of County Commissioners are bound in every instance by the decision of one Board regarding the land use of a particular parcel. There is some evidence that leads to at least a fair inference that the designation of the racetrack site as "Rural Residential" may have been in error. The data and analysis that was used to support the original designation indicates the area including the racetrack as being "woodlands." The County planner involved in the preparation of the Plan, including the FLUM, testified that he did not know there was a racetrack on the land designated "woodlands." The FLUM was based "to a great extent" on this data, and very well may have designated the Property as "Rural Residential" by "oversight" based on the incorrect representation of the area as woodlands. Several other commercial uses exist within the immediate vicinity of the site of the Property, are similarly depicted as "woodlands" by the referenced data, and are designated "Rural Residential" on the FLUM. These parcels, too, may be nonconforming by error, and not by some deliberate choice. Whether the original designation of the Property as nonconforming was erroneous or not, the true question is what is the proper standard by which to weigh a FLUM amendment when it affects a site on which there exists a nonconforming use. Neither Chapter 163, Part II, Florida Statutes, nor Rule 9J-5, Florida Administrative Code, directs the Department to review a FLUM amendment involving a nonconforming use under some specific provisions. Such an amendment must be subjected to the same standards applicable to any FLUM amendment. The Property has been used intermittently as a racetrack for approximately 30 years. A racetrack has operated on the Property as a nonconforming use, and has the right to continue do so under applicable County land use and zoning regulations. The racetrack is, in fact, eligible to expand by 15 percent under these regulations. The County would not have some absolute right to cease racetrack operations if it remained nonconforming, and would not have unlimited authority to address noise and traffic concerns. The uncontradicted testimony is that it is likely that the racetrack would continue to operate even if it remained a nonconforming use. The County does not lose any authority to address noise and traffic by virtue of the Amendment. Credible evidence in the record indicates that the County may actually have a better ability to address these concerns should the racetrack be made a conforming use. Nevertheless, the fact that the racetrack, operated as the Speedway, currently exists in the area as a nonconforming use does not mean that the use is automatically compatible with the adjacent land uses and surrounding area or is otherwise consistent with the character of the community. The nonconforming use designation only means that the racetrack can continue to operate, not that the racetrack can achieve a potentially more useful and elevated land use status by virtue of being an existing raceway and commercial use. Otherwise, an existing nonconforming use would have greater rights to a new and more permissive land use designation than a new entrant into the marketplace. Stated otherwise, the FLUM Amendment, if approved, will further and encourage the nonconforming use rather than its eventual elimination as contemplated by the Plan and Zoning Ordinance. In this case, it is beyond fair debate that if a new automobile racetrack were proposed on the Property today, it would be inconsistent with the existing residential and conservation areas surrounding the property, notwithstanding the existence of several commercial properties in the vicinity. The only reasonable conclusion to be reached is that that the Amendment is not "in compliance."
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be issued concluding that the Amendment adopted by Putnam County in Ordinance No. 2001- 33 is not "in compliance" as defined in Chapter 163, Part II, Florida Statutes, and the rules promulgated thereunder. DONE AND ENTERED this 2nd day of May, 2003, in Tallahassee, Leon County, Florida. ___________________________________ CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 2nd day of May, 2003.
The Issue Whether the amendments to the Hendry County Comprehensive Plan adopted on February 25, 2014, by County Ordinance No. 2014- 03, are “in compliance,” as that term is defined in section 163.3184(1)(b), Florida Statutes (2013).1/
Findings Of Fact The Parties and Standing Respondent, Hendry County (Respondent or County), is a political subdivision of the State of Florida with the duty and responsibility to adopt and amend a comprehensive growth management plan pursuant to section 163.3167. Petitioner, the Seminole Tribe of Florida (Petitioner or Seminole Tribe), owns real property consisting of the Big Cypress Seminole Indian Reservation and adjacent non-reservation lands located in the County. The address of the main tribal office is 31000 Josie Billie Highway, Clewiston, Florida 33440. On February 25, 2014, the Board of County Commissioners held a public hearing and adopted the Plan Amendment. The Seminole Tribe submitted written and oral comments to the County concerning the Plan Amendment through their counsel and several Tribal members at the adoption public hearing. Existing Land Uses and Future Designations Hendry County is approximately 1,190 square miles in size. The County is predominantly an agriculturally-based community with roughly 55 percent of the total land area in agricultural production and another 12 percent designated as preserve. Approximately 71 percent of the land area in the County is designated Agriculture on the Future Land Use Map (FLUM).2/ Lands within the Agriculture Future Land Use Category (Ag FLU), some 529,936 acres, predominantly comprise the central, southern and eastern portion of the County. The Ag FLU designates those lands which “will continue in a rural and/or agricultural state through the planning horizon of 2040.” The County has limited property designated for future industrial and commercial use. Less than one-half percent of the land area on the FLUM is designated as Industrial. Less than two-tenths percent is designated as Commercial. Other future land use categories which allow Industrial development include Agriculture, Public, Multi-Use Development, and land within the Rodina sector plan, which authorizes a maximum of 1,900,000 square feet of Office, Civic, and Industrial uses. Industrial uses allowed within the Agriculture land use category include processing of agricultural products as Level One uses allowed as permitted uses, special exceptions, or accessory uses under the Land Development Code. A number of other uses, such as utilities, bio-fuel plants, mining, and solid waste recovery, are allowed as Level Two uses which require rezoning of the property to a Planned Unit Development, with significant review by County staff and approval by the Board of County Commissioners. Less than one percent of the land area is designated for Public Use. The Public land use category designates areas which are publicly-owned, semi-public, or private lands authorized for public purposes, such as utilities and solid waste facilities. The largest industrial site in the County is the AirGlades industrial complex, which is designated as a Public land use on the FLUM. The site is approximately 2,400 acres in size, but only roughly 200 acres is in industrial use. The complex cannot be fully developed due to inadequate County wastewater facilities serving the site, Federal Aviation Authority restrictions (e.g., height limitations) on development in proximity to the Airglades airport, and lack of opportunity for fee ownership of property owned by the County.3/ Roughly one-half percent of the land area is designated Multi-Use. Designated lands are generally located adjacent to the primary transportation system and existing or programmed utilities. The purpose of this land use category is to promote new development and redevelopment of the properties located within the category. The Floor Area Ratio (FAR) for Industrial development in the Multi-Use category is limited to 0.75. As with industrial uses, commercial uses are allowed in land use categories other than Commercial. The Agriculture category allows commercial uses such as ornamental horticulture and nurseries. Non-residential intensity is generally limited to an FAR of .40. Commercial development is allowed within both the Medium–Density and High-Density Residential FLU Categories; however, development is limited to residential-serving commercial, must be approved through the PUD rezoning process, and is limited to 15 percent of the uses within the PUD. Less than one percent of the County is designated as Rural Special Density, and, under the existing Plan, this designation cannot be expanded. The Residential Special Density category allows commercial and retail on no more than 10 percent of the designated area and with a total cap of 200 square feet at buildout. Commercial development is also allowed within the Multi-Use category, but is limited to an FAR of .25 for retail commercial, .50 for mixed-use buildings (maximum of 25 percent retail), and .30 FAR for mixed-use buildings with commercial on the first floor. The County is sparsely populated with concentrations surrounding the cities of Clewiston and LaBelle, including Port LaBelle, as well as the unincorporated areas known as Felda and Harlem. The cities of LaBelle and Clewiston and the unincorporated populated areas are located at the northernmost end of the County along State Road 80 (SR 80). The Felda Community is located in the northwestern portion of the County, south of the City of LaBelle. Most of the development in the County since 1999 has occurred in and surrounding the incorporated areas of LaBelle and Clewiston, primarily adjacent to the City of LaBelle and along SR 80 from LaBelle to the Lee County line. The vast majority of land in the County is not served by centralized public utilities, such as sewer and water. Existing public utilities, including centralized water and sewer, are limited to the northernmost areas of the County surrounding the cities of LaBelle and Clewiston, and along SR 80. South of LaBelle and Clewiston, there are only three north/south and two east/west principle arterial or collector roads in the County. All of these are two-lane roads, and only SR 29 south of LaBelle is planned to be widened to four lanes under either alternative in the County’s 2040 long-range transportation plan. Economic Conditions It is undisputed that the economic condition of the County is dire. The County ranks high in many negative economic indicators, including a 30 percent poverty rate (compared to 17 percent statewide), the highest unemployment rate in the state for 34 of the most recent 36 months, and an annual wage $10,000 lower than the state average. Roughly 80 percent of County school children qualify for a free or reduced-price lunch, and a high percentage of the County population are Medicaid recipients. The County’s ability to raise revenue through taxation is limited by the extent of property exempt from ad valorem taxation (e.g., government-owned property), and the extent classified as Agricultural and assessed at less than just value. Slightly more than half of the just value of property in the County is subject to an Agricultural classification. Another 21 percent of the just value of property in the County is government-owned, thus exempt from ad valorem taxation. More than half of the parcels in the County are taxed as vacant residential, and less than two percent are taxable commercial properties. On May 24, 2011, the Board of County Commissioners conducted a workshop on proposed new Mission, Vision, and Core Values statements for the County. On September 13, 2011, the Board adopted the following Vision statement: “To be an outstanding rural community in which to live, work, raise a family and enjoy life by creating an economic environment where people can prosper.” The Plan Amendment The Plan Amendment was adopted in an effort to attract large-scale commercial and industrial businesses to locate in, and bring jobs to, the County. Under the Plan Amendment, a new development project that is designated as an Economic Engine Project (EEP), and “large-scale commercial and/or industrial” developments, are expressly permitted in any and all FLU categories throughout the County with the exception of Agricultural Conservation, Residential - Pre-Existing Rural Estates, and Felda Estates. The Plan Amendment is designed to spur economic development by “streamlining” the permitting process to give the County a competitive advantage in attracting new business. By permitting EEPs and large-scale commercial and industrial uses in nearly every future land use category, the Plan Amendment is intended to eliminate the costs (in both time and money) of processing comprehensive plan amendments for future development projects. The amount of land eligible for siting either an EEP or a large-scale commercial and/or industrial development under the Plan Amendment is approximately 580,000 acres.4/ The majority of that land area, 529,936.49 acres, is located within the Agriculture FLU category. The Plan Amendment significantly rewrites the Economic Development Element of the County’s Plan, and adds new policies to Chapter 1, Goal 2 of the Future Land Use Element (FLUE), related to “Innovative Planning and Development Strategies.” The Plan Amendment rewrites Goal 2 as follows:5/ In order to protect water resources, protect the environment and wildlife habitat, build a more sustainable tax base, encourage economic development, promote energy efficiency, and to permit job creation for the citizens and residents of Hendry County, the following innovative land use planning techniques should be encouraged: In order to build a sustainable tax base, encourage economic development, promote job creation, and support vibrant rural and urban communities, the following flexible development strategies are encouraged: Innovative and flexible planning and development strategies list in Section 163.3168, Florida Statutes. Innovative and creative planning tools. Innovative Flexible and strategic land use techniques listed and defined in this comprehensive plan. The Plan Amendment adds the following new Objective and Policies to FLUE Goal 2: Objective 2.1: Recognize the substantial advantages of innovative approaches to economic development to meet the needs of the existing and future urban, suburban and rural areas. Policy 2.1.1: A qualifying County economic development and job creation project (Economic Engine Project) is a project that complies with Policy 10.1.7. of the Economic Development Element, Hendry County's compatibility requirements, Policy 2.1.2, and which will have adequate infrastructure. These projects shall be allowed in any category listed in the Future Land Use Element except those lands designated as Agriculture Conservation, Residential/Pre- Existing Rural Estates, and Felda Estates residential areas, consistent with the goals, objectives, and policies of the Economic Development Element. Additionally, Economic Engine Projects shall be allowed in adopted sector plans only if they advance or further the goals, objectives and policies of respective lands pursuant to 163.3245, and the sector plan. Densities and Intensities shall not exceed the values that are established for commercial and industrial uses in the respective land use categories. In the residential land use categories, an Economic Engine Project shall not exceed an Intensity of 0.25 FAR. Policy 2.1.2: Large-scale commercial and/or industrial developments will be allowed in any Future Land Use category, except those lands designated as Agriculture Conservation, Residential/Pre-Existing Rural Estates, and Felda Estates residential areas if they meet the requirements below. In addition, large-scale commercial and/or industrial developments will be allowed in adopted sector plans only if they advance or further the goals, objectives and policies of respective lands pursuant to 163.3245, F.S., the sector plan, and meet the requirements below. Policy 2.1.2 does not apply to industrial development located in the industrial land use category nor commercial development located in the commercial land use category. The development is approved as a PUD as provided in the Land Development Code; The development is consistent with siting proposals developed by County staff and approved by the Board of County Commissioners; The project has direct access to principal arterials and collectors or access to the principal arterials and collectors via local roads with adequate capacity which can be readily provided by the development; The project has access to, will upgrade/extend existing utilities, or construct on-site utilities; or a public or private provider will extend and/or expand the utilities (including an upgrade if necessary) or has the extension of utilities in the utility's financially feasible plan. The project must have access to all existing or planned necessary utilities, such as water, sewer, electricity, natural gas, cable, broadband, or telephone; The project has access to and can provide on-site rail facilities, when appropriate; The project will provide sufficient open space, buffers, and screening from exterior boundaries where warranted to address all compatibility issues. Large-scale Commercial and/or Industrial development must be a minimum of eighty (80) acres. The County reserves the right to require the project area to be larger if the County finds that a project with more land is necessary to address the impacts of the development on the surrounding area, or if the County concludes that a larger site is necessary to provide a viable project. The project must demonstrate that it will produce at least fifty (50) new jobs within three years after the project is initiated. The development must contribute positively to the County's economy. If the project requires that the County expend funds not already provided for in the County Capital Improvement Program, the developer shall cooperate with the County in obtaining the funds. This provision includes requiring the County to accelerate a programmed project. If necessary, the owner/developer of the project will work with the appropriate educational facilities to create the necessary education and training programs that will enable Hendry County residents to be employed with the Large- scale Commercial and/or Industrial development. Intensities shall not exceed the Floor Area Ratio for Commercial and/or Industrial uses that are established in their respective land use categories. In the residential land use categories, an Economic Engine Project shall not exceed an Intensity of 0.25 FAR. Densities shall not exceed the Floor Area Ratio for Commercial uses that are established in their respective land use categories. Additionally, the Plan Amendment adds the following definitions to the Plan: "Economic Engine Project" means a qualifying County economic development and job creation project which complies with Policy 10.1.7. of the Economic Development Element and means the proposed development, redevelopment or expansion of a target industry. "Target Industry" means an industry that contributes to County or regional economic diversification and competitiveness. Targeted industries that are eligible to qualify as a County-approved Economic Engine Project include, but are not limited to: The targeted industries and strategic areas of emphasis listed with Enterprise Florida The targeted industries of Florida's Heartland Regional Economic Development Initiative Projects aligned with efforts of Visit Florida Projects that promote tourism Marine Industries; and Agricultural Industries New Economic Development Element Policy 10.1.7, reads as follows: The County Administrator has the authority to designate a project as a County-approved Economic Engine Project provided it meets the definition of an Economic Engine Project, the criterion in future land use element Objective 2.1, and policies 2.1.1- 2.1.2. Petitioner’s Challenge Petitioner challenges the Plan Amendment as not “in compliance” with chapter 163. Specifically, Petitioner alleges that the Plan Amendment fails to appropriately plan for orderly future growth by providing measurable and predictable standards to guide and control the future growth and distribution of large-scale commercial and industrial developments and Economic Engine Projects throughout the County; is not based on relevant and appropriate data and analysis; is internally inconsistent with other goals, objectives, and policies in the Plan; and fails to discourage urban sprawl. Meaningful and Predictable Standards Section 163.3177(1) provides, “The [local government comprehensive plan] shall establish meaningful and predictable standards for the use and development of land and provide meaningful guidelines for the content of more detailed land development and use regulations.” Section 163.3177(6)(a) requires the local government to designate, through the FLUE, the “proposed future general distribution, location, and extent of the uses of land for” commercial and industrial categories of use. Further, this section requires the local government to include the “approximate acreage and the general range of density or intensity of use . . . for the gross land area in each existing land use category.” Subparagraph 163.3177(6)(a)1. requires local governments to define each future land use category “in terms of uses included” and to include “standards to be followed in the control and distribution of population densities and building and structure intensities.” Designated Economic Engine Projects The Plan Amendment does not define an EEP in a manner sufficient to put property owners on notice as to what use might be approved within the approximately 580,000 acres affected by the Plan Amendment. The Plan Amendment defines an EEP as a “proposed development, redevelopment or expansion of a target industry.” “Target industry” is further defined by the Plan Amendment as “an industry that contributes to County or regional economic diversification and competitiveness.” The definition continues, as follows: Targeted industries that are eligible to qualify as a County-approved Economic Engine Project include, but are not limited to: The targeted industries and strategic areas of emphasis listed with Enterprise Florida The targeted industries of Florida’s Heartland Regional Economic Development Initiative Projects aligned with efforts of Visit Florida Projects that promote tourism Marine Industries Agricultural Industries Under Policy 2.1.1, a project that meets the definitions above may be designated as an EEP by the County Administrator, pursuant to Policy 10.1.7, if it meets the criterion in Policy 2.1.2, and if it “complies with the County’s compatibility requirements and [has] adequate infrastructure.” As adopted, the Plan Amendment provides no meaningful standard for the use or development of land for an EEP. The definition of an industry that “contributes to County or regional economic diversification and competitiveness” is essentially open-ended, defining an EEP only in the sense that it must be different from the existing predominate County industry -- Agriculture. Yet, even that distinction is eliminated by the inclusion of “Agricultural Industries” on the list of target industries “that are eligible to qualify as a County-approved” EEP. The list of industries defined as “eligible to qualify as a County-approved” EEP provides no meaningful standard because it incorporates by reference industries listed by, targeted by, or “aligned with,” private and quasi-government entities such as Enterprise Florida, Visit Florida, and Florida’s Heartland Regional Economic Development Initiative. The definition does not even fix to a specific date the list of targeted industries designated by those business development entities, thus rendering the Amendment “self-amending,” without any meaningful list of qualifying uses. Moreover, the definition of “target industry” incorporates these third-party lists with the qualification “including but not limited to.” Thus, determination of an EEP is at the sole discretion of the County Administrator. Sarah Catala, Hendry County associate planner, is the author of the Plan Amendment. Ms. Catala testified that an EEP could encompass a wide variety of uses, including ecotourism (e.g., bird-watching tours), manufacturing, and large-scale commercial development such as a Super Walmart. The Plan Amendment is essentially circular. The definition of an EEP refers to compliance with Policy 10.1.7, but Policy 10.1.7 refers back to the definition and the criteria in Policies 2.1.1 and 2.1.2. Policy 2.1.1 requires an EEP to comply with Policy 10.1.7, as well as Policy 2.1.2. Objective 2.1 and Policies 2.1.1 and 2.1.2 lack meaningful and predictable standards for the use and development of EEPs. Policy 2.1.1, as previously referenced, refers the reader to Policy 2.1.2 and further states that EEPs must “comply with Hendry County’s compatibility requirements” and must have “adequate infrastructure.” The Plan Amendment does not define either “compatibility requirements” or “adequate infrastructure.” Nor does the Plan Amendment cross-reference any specific compatibility or infrastructure requirement in either the Plan or the County’s Land Development Regulations. The County highlights Policy 2.1.2 as the measurable criterion that directs the location, timing and extent of development of both EEPs and large-scale commercial and industrial developments throughout the County. However, as discussed below, Policy 2.1.2 does not resolve the Plan Amendment’s failure to provide meaningful and predictable standards directing the location, amount and timing of the development of EEPs or large-scale commercial and industrial in the County. Large-scale Commercial and Industrial Developments Policy 2.1.2 adds “large-scale commercial and industrial developments” as an allowable use in every FLU category in the County with the exception of the same three categories from which EEPs are excluded: Agriculture Conservation, Residential/Pre-Existing Rural Estates, and Felda Estates. Large-scale commercial and industrial developments must meet the requirements listed in paragraphs (a) through (n) of Policy 2.1.2.6/ Policy 2.1.2(a) requires EEPs and large-scale commercial and industrial developments allowed by the Plan Amendment to undergo a rezoning to Planned Unit Development (PUD) during which time various site-specific criteria found in the land development regulations will be applied to development of a particular project. The PUD rezoning criterion in the County’s LDRs govern the location of a particular use on a specific property. The PUD requirements do not relate in any way to the appropriate location of either an economic project or large-scale commercial or industrial development within the approximately 580,000 acres open for those developments under the Plan Amendment. Thus, this criterion is not a meaningful standard that provides for the general distribution, location, and extent of land for EEPs or large-scale commercial or industrial use. Policy 2.1.2(b) requires EEPs and large-scale commercial and industrial developments allowed by the Plan Amendment to be “consistent with siting proposals developed by County staff and approved by the Board of County Commissioners.” It is undisputed that the said siting proposals have yet to be developed by staff. Ms. Catala anticipates developing a locational matrix that will “match up locations in the County with the needs of a business.” As such, the siting proposals will provide locational standards for future EEPs and large- scale commercial and industrial developments. As written and adopted, though, the Plan Amendment contains no such standards. Policy 2.1.2(c) requires EEPs and large-scale commercial and industrial developments to have “direct access to principal arterials and collectors or access to the principal arterials and collectors via local roads with adequate capacity which can be readily provided by the development.” This criterion simply requires EEPs and large-scale commercial and industrial developments to have access to a roadway of some sort. It does not guide developments to locate within proximity to a roadway, or require direct access to a particular class of roadway. The criterion does not preclude the developer from building a road from the project to an existing local roadway. Furthermore, the Plan Amendment neither defines the term “adequate capacity” nor cross-references an existing definition of that term elsewhere in the Plan. Without a definition, the reader is left to speculate whether a particular project site is appropriate in proximity to any particular roadway. As written, Policy 2.1.2(c) does not provide meaningful standards for the location, distribution, or extent of either EEPs or large-scale commercial or industrial projects within the approximately 580,000 acres designated eligible for these uses under the Plan Amendment. Policy 2.1.2(d) relates to the provision of utilities to serve an EEP or large-scale commercial or industrial project. The Policy reads as follows: The project has access to, will upgrade/extend, or construct on-site utilities; or a public or private provider will extend and/or expand the utilities (including an upgrade if necessary) or has the extension of utilities in the utility’s financially feasible plan. The project must have access to all existing or planned necessary utilities, such as water, sewer, electricity, natural gas, cable, broadband, or telephone. This criterion provides so many alternatives, it is essentially meaningless. Boiled down, the provision requires only that the project have utilities, which is essential to any development. The criterion does not direct the location of one of these projects to areas where utilities exist or are planned, but rather allows them anywhere within the approximately 580,000 acres as long as the developer provides needed utilities, somehow, some way. Policy 2.1.2(e) requires “[t]he project [to have] access to and . . . provide on-site rail facilities, when appropriate[.]” This criterion provides locational criterion to the extent that a development for which rail facilities are integral must locate in proximity thereto. However, that criterion is self-evident. The policy does not add any guidance for the location, distribution, and extent of EEPs and large- scale commercial or industrial projects which do not require rail facilities. Policy 2.1.2(f) requires the project to “provide sufficient open space, buffers, and screening from exterior boundaries where warranted to address all compatibility issues.” Buffers, screening, and open space requirements are addressed at the PUD rezoning stage of development and do not provide guidance as to the location of development within any particular land area. Furthermore, the language does not direct an EEP or large-scale commercial or industrial development away from existing uses which may be incompatible therewith. The Plan Amendment actually anticipates incompatibility and requires development techniques to address incompatibilities at the rezoning stage. Policy 2.1.2(g) requires a minimum of 80 acres for a large-scale commercial or industrial development. The policy allows the County to increase that minimum size “if the County finds that a project with more land is necessary to address the impacts of the development on the surrounding area, or if the County concludes that a larger site is necessary to provide a viable project.” The policy has a veneer of locational criterion: it excludes development or redevelopment of parcels, or aggregated parcels, which are smaller than the 80 acre threshold. However, the policy provides an exception for the County to require larger parcels solely at its discretion. Again, the policy anticipates incompatibility between large- scale commercial or industrial development and the existing land uses. Policies 2.1.2(h), (i), (j), (k), (l), and (m) bear no relationship to location, distribution, or extent of the land uses allowed under the Plan Amendment. Petitioner has proven beyond fair debate that the Plan Amendment neither provides for the general distribution, location, and extent of the uses of land for commercial and industrial purposes nor meaningful standards for the future development of EEPs and large-scale commercial and industrial development. Section 163.3177(1) requires local government plan amendments to establish meaningful guidelines for the content of more-detailed land development regulations. Policy 2.1.2(b) requires large-scale commercial and industrial developments to be consistent with “siting proposals,” which Ms. Catala testified are anticipated to be adopted in the County’s land development code. Ms. Catala generally described a matrix that would help industry “get the best fit for their needs in the County.” The Plan Amendment does not provide any guidelines for adoption of a matrix or any other siting proposals to be adopted by County staff and approved by the Board of County Commissioners pursuant to Policy 2.1.2.(b). Lastly, section 163.3177(6)(a) requires that the FLUE establish the general range of density and intensity of the uses allowed. Ms. Catala testified that the intent of the Plan Amendment is not to change the density or intensity of uses from those already allowed in the plan. The plain language of the Plan Amendment does not support a finding that densities and intensities of use remain the same under the Plan Amendment. The intensity of non- residential development allowed under the Plan Amendment is, at best, unclear, and in some cases left entirely to the discretion of the Board of County Commissioners. Policy 2.1.1 provides that the densities and intensities of EEPs “shall not exceed the values that are established for commercial and industrial uses in the respective land use categories.” The County argues that a fair reading of the Policy restricts non-residential development to the intensities established in the underlying category for non-residential development. Under Policy 2.1.2, intensities of large-scale commercial and industrial developments “shall not exceed the Floor Area Ratio for Commercial and/or Industrial Uses established in their respective land use categories.” While a fair reading of Policy 2.1.1 restricts the intensity of commercial or industrial development to the density established in the underlying land use district, Policy 2.1.2 does not. The pronoun “their” refers back to the Commercial and Industrial land use categories. Thus, under Policy 2.1.2, commercial and industrial uses can develop in other land use categories at the intensities established in the Commercial or Industrial category. Further, both Policy 2.1.1 and Policy 2.1.2 cap EEP intensity at 0.25 FAR in residential FLU categories. This language overrides the existing cap on non-residential development in those categories established in the FLUE. It also overrides those FLU categories, such as Residential Low- Density, which establish an FAR of 0.00. Finally, Policy 2.1.2 contains no intensity cap on development of commercial and industrial development within residential FLU categories. The County explains that large- scale commercial and industrial developments are simply not allowed in FLU categories, such as Residential Low-Density, which establish an FAR of 0.00. The County’s interpretation is not consistent with the plain language of the policy. Policy 2.1.2 specifically allows large-scale commercial and industrial development in all land use categories except Agricultural-Conservation, Residential/ Pre-Existing Rural Estates, and Felda Estates. If the County intended to exclude other FLU categories, they would have been included in the list of exceptions. Petitioner has proven beyond fair debate that the Plan Amendment does not establish the general range of intensity of large-scale commercial and industrial development. Data and Analysis Section 163.3177(6)(a)2. requires local government FLUE amendments “to be based upon surveys, studies, and data regarding the area, as applicable” including the following: The amount of land required to accommodate anticipated growth. The projected permanent and seasonal population of the area. The character of the undeveloped land. The availability of water supplies, public facilities, and services. The need for redevelopment, including the renewal of blighted areas and the elimination of nonconforming uses which are inconsistent with the character of the community. The compatibility of uses on land adjacent to an airport as defined in s. 330.35 and consistent with s. 333.02. The discouragement of urban sprawl. The need for job creation, capital investment, and economic development that will strengthen and diversify the community’s economy. The need to modify land uses and development patterns with antiquated subdivisions. County staff did not collect data or perform an analysis of the character of the undeveloped land affected by the Plan Amendment. County staff did not perform any analysis of the suitability of the land area affected by the Plan Amendment for either a large-scale commercial or industrial development nor for an EEP. County staff did not perform an analysis of the availability of the County water supplies, wastewater treatment, or other public facilities, to serve large-scale commercial or industrial development or an EEP located within the area affected by the Plan Amendment. In fact, County staff acknowledged that wastewater treatment facilities are inadequate to support full buildout of the industrial sites available at the Airglades airport facility. County staff did not perform an analysis of the compatibility of large-scale commercial or industrial development adjacent to the Airglades airport facility. In preparing the Plan Amendment, County staff clearly relied upon data reflecting the County’s needs for job creation, economic development, and a diversified economy, including the Department of Revenue Property Tax Overview for Hendry County, and the fact that the County is designated a Rural Area of Critical State Concern. County staff also considered, in support of the Plan Amendment, the County Commission’s recently-adopted Vision statement: “To be an outstanding rural community in which to live, work, raise a family and enjoy life by creating an economic environment where people can prosper.” No evidence was introduced to support a finding that County staff analyzed whether the Plan Amendment would achieve the goals of strengthening and diversifying the County’s economy. The County introduced the testimony of Greg Gillman, the County’s Economic Development Director, regarding his efforts to attract new business to the County, as well as the obstacles the County faces in these efforts. Mr. Gillman testified regarding five particular scenarios in which he worked with companies to find a suitable location in the County. In one scenario, the price was too high for the potential buyer. In another, the potential buyer was put off by the wooded acreage. In another, the seller would not subdivide. In another, the property is undergoing a PUD rezoning process. In the final scenario, Mr. Gillman testified the potential buyer rejected all proposed sites without explanation. Mr. Gillman did not give a single example of a scenario in which a potential business opportunity was lost due to the need to change the FLUM designation of a property. In fact, Mr. Gillman testified that he does not even show sites without appropriate land use classifications to potential buyers. While there is a plethora of data on the limited amount of land in the County classified for commercial and industrial uses, County staff gathered no data regarding, and conducted no analysis of, the vacancy rate of sites on which commercial and industrial uses are currently allowed. Mr. Gillman provided anecdotal evidence regarding recent efforts to redevelop vacant sites, some of which have been successful. Ms. Catala testified that, in addition to relying on the County’s Vision statement and economic data, she reviewed the comprehensive plans of other jurisdictions. From that review, she gleaned the idea of an EEP. The County introduced no evidence to support a finding that the threshold of 80 acres for an EEP was based upon data at all. Mr. Gillman’s testimony revealed that Ms. Catala originally proposed a higher threshold (perhaps 120 acres), but that he recommended a smaller acreage. Mr. Gillman gave no explanation of the basis for his recommendation. Section 163.3177(f) provides, “To be based on data means to react to it an appropriate way and to the extent necessary indicated by the data available on that particular subject at the time of adoption of the plan or plan amendment at issue.” Given the lack of evidence linking the Plan Amendment to spurring economic development, the County failed to demonstrate that it reacted appropriately to the economic data on which it relied. Even if Mr. Gillman’s anecdotes were accepted as data, they do not support eliminating plan amendments to allow commercial and industrial development in a variety of other land use categories. Internal Inconsistency Section 163.3177(2) provides as follows: Coordination of the several elements of the local comprehensive plan shall be a major objective of the planning process. The several elements of the comprehensive plan shall be consistent. The Petitioner alleges the Plan Amendment changes to the FLUE and Economic Development Element are inconsistent with a number of goals, objectives, and policies found within the FLUE and in other plan elements. Each one is taken in turn. Future Land Use Element First, Petitioner alleges internal inconsistency within the FLUE, specifically between the Plan Amendment and FLUE Goal 1, Objective 1.1, and Policies 1.1.1, 1.1.3, 1.1.4, 1.1.5, 1.1.9, 1.1.10, 1.1.11, and 1.1.13. Policy 1.1.1 governs land uses allowed within the Agriculture FLU category. The policy states, in pertinent part, as follows: Purpose The purpose of the Agriculture Future Land Use Category is to define those areas within Hendry County which will continue in a rural and/or agricultural state through the planning horizon of 2040. * * * Location Standards Areas classified as Agriculture are located within the rural areas of Hendry County. Lands in this category are not within the urban area, but may be adjacent to the urban area. Some of these lands may be converted to urban uses within the 2040 planning horizon. However, the majority of the lands classified Agriculture will remain in a rural, agricultural land use through the year 2040. The Plan Amendment affects more land designated as Agriculture than that designated in any other category. Slightly more than 70 percent of the County, almost 530,000 acres, is designated as Agriculture, and all of it is subject to development for an EEP or an 80-acre minimum commercial or industrial project under the Plan Amendment. Development of ill-defined EEPs and 80-acre minimum large-scale commercial and industrial projects is not consistent with designating lands “which will continue in a rural and/or agricultural state” through 2040. Respondent counters that the Plan Amendment is not inconsistent with Policy 1.1.1 because that Policy already allows a number of non-traditional agricultural uses which are commercial and/or industrial in nature, and may be sited through the PUD rezoning process, just as the uses allowed under the Plan Amendment. Policy 1.1.1 authorizes the use of Agriculture lands for utilities, bio-fuel plants, mining and earth extraction and processing operations, solid waste facilities, resource recovery facilities, and other similar uses. The County’s argument is not persuasive.7/ The non- agricultural uses allowed under the existing plan are agriculturally-related or agriculture-dependent uses, such as bio-fuel, mining, and resource recovery, or uses which, by their nature, are best suited to less-populated rural areas, such as utilities and solid waste facilities. In contrast, large-scale commercial and industrial uses are not limited to agriculturally-related or utility uses. Under the Plan Amendment, anything from an auto parts manufacturing plant to a Super Walmart could be developed in areas designated Agriculture. Any number of urban uses could be developed under the auspices of an EEP or large-scale commercial. Under the Plan Amendment, no amendment to the County’s comprehensive plan will be needed to allow such urban uses in the Agriculture category. Policies 1.1.3, 1.1.4, and 1.1.5 govern land uses in the following FLU categories: Residential – Rural Estates, Residential – Medium Density, and Residential – High Density, respectively. According to Policy 1.1.3, the purpose of the Residential – Rural Estates category is “to define those areas within Hendry County which have been or should be developed at lower density in order to promote and protect the rural lifestyle through the planning horizon of 2040.” The Policy permits only residential and customary accessory uses within the category. The Policy specifically sets a FAR of 0.00 for non- residential development. According to Policy 1.1.4, the purpose of the Residential – Medium Density category is “to identify those areas within Hendry County which currently, or should be, encouraged to become the primary location of residential development offering a mixture of residential products at suburban/urban style density through the planning horizon 2040.” The policy permits single- and multi-family development, as well as mobile homes, and customary accessory uses. Commercial development is allowed only as an element of mixed-use developments, of which commercial is limited to 15 percent. Additional limitations on commercial apply, including limits on size and character, location within the mixed-use development, and buffering from adjacent residential uses. Policy 1.1.4 establishes an FAR of 0.10 for non-residential development. According to Policy 1.1.5, the purpose of the Residential – High Density category is “to define those areas within Hendry County which are or should become higher density residential development through the planning horizon 2040.” The policy permits all types of residential development and customary accessory uses. As with medium-density category, Policy 1.1.5 allows some commercial development within mixed-use developments subject to limitations on size and character, location within the mixed-use development, and buffering. The policy establishes an FAR of 0.10 for non-residential development. Under the Plan Amendment, each of these three Residential categories is available for siting an EEP. New Policy 2.1.2 allows for development of EEPs in these categories at an FAR of 0.25. The Plan Amendment allows EEPs within the Residential Rural Estates category directly in contravention of Policy 1.1.3, which limits uses to residential, recreational, and limited agricultural, and provides zero intensity for non- residential uses. As previously noted, the Plan Amendment broadly defines EEPs, and the record supports a finding that such a project could encompass anything from a manufacturing facility to a Super Walmart. The broad array of uses to diversify the County’s economy is in conflict with the County’s previous decision, reflected in Policy 1.1.3 to designate these areas for future development at low-density residential “to promote and protect the rural lifestyle.” Likewise, the Plan Amendment opens up the Residential Medium Density and Residential – High Density categories for location of ill-defined EEPs in contravention of Policies 1.1.4 and 1.1.5, which limit development in those categories to primarily residential, only allowing commercial within a mixed- use development and limited to a maximum of 15 percent. Furthermore, the Plan Amendment allows these developments at a greater intensity than the FAR of 0.10 established for non- residential density in those categories. The parties disagreed as to whether the Plan Amendment authorizes large-scale commercial and industrial development in the Residential – Rural Estates category governed by Policy 1.1.3. The argument primarily turns on interpretation of new Policy 2.1.2, as discussed in the previous section herein titled “Meaningful and Predictable Standards.” The County contends that the correct interpretation of Policy 2.1.2 allows a large-scale commercial or industrial development at the maximum intensity established in the underlying land use category. In other words, if the underlying land use category establishes an FAR of 0.00 for industrial development, no industrial development is allowed. However, if the same category establishes an FAR for commercial development, the Plan Amendment allows commercial development in that category limited to the intensity established by the FAR. The undersigned has rejected that interpretation as discussed in the prior section herein. Petitioner contends that the language allows commercial and industrial development in every non-exempt land use category at the intensities established in the Commercial and/or Industrial land use category, as applicable. Petitioner’s interpretation is the correct interpretation, and indeed the only possible reading of the plain language of Policy 2.1.2(l).8/ Policy 1.1.9 governs uses in the Commercial land use category. The Policy allows non-residential development at the following intensities: Retail Commercial – 0.25 FAR Office – 0.50 FAR 0.50 FAR for mixed-use building with a maximum of 25% retail and a minimum of 75% office 0.30 FAR for mixed-use development with commercial on the first floor and residential on stories above the first floor. Allowing large-scale commercial development at the stated intensities directly conflicts with Policy 1.1.3, which provides an FAR of 0.00 for non-residential development in Residential – Rural Estates; Policy 1.1.4, which caps intensity at 0.10 for commercial in Residential – Medium; and Policy 1.1.5, which provides an FAR of 0.10 in Residential – High. Thus, Plan Amendment Policy 2.2.1 is in conflict with Policies 1.1.3, 1.1.4, and 1.1.5. Policy 1.1.10 governs uses in the Industrial land use category. The Policy allows industrial development at an intensity of 0.75. Allowing large-scale industrial development at an intensity of 0.75 directly conflicts with Policy 1.1.3, which provides an FAR of 0.00 for non-residential development in Residential – Rural Estates; and Policies 1.1.4 and 1.1.5, which limit non-residential uses to commercial and recreation in the Residential – Medium and Residential – High land use categories. Thus, Plan Amendment Policy 2.1.2 is in conflict with Policies 1.1.3, 1.1.4, and 1.1.5. Petitioner alleges the Plan Amendment is inconsistent with Policies 1.1.9 and 1.1.10 governing development within the Commercial and Industrial categories, respectively. The allegations were not supported by a preponderance of the evidence. The Plan Amendment does not alter either the uses allowed in those categories or the intensity of development allowed therein. Those policies are essentially unscathed. However, because the Plan Amendment allows the types and intensities of development described in the Commercial and Industrial categories to occur in residential and other categories in which those uses and intensities conflict, the Plan Amendment is inconsistent with the policies governing those residential and other categories. Policies 1.1.9 and 1.1.10 are merely the conduits through which Policy 2.1.2 is found to be inconsistent with Policies 1.1.3, 1.1.4, and 1.1.5. Policy 1.1.11 governs land uses in the Public category. The Policy establishes the following purpose and uses: Purpose The purpose of the Public Future Land Use Category is to establish regulations relative to use and location of publicly- owned lands, semi-public lands, and private lands authorized for public purposes which currently exist or which may become public through the planning horizon 2040. Description/Uses Lands in this category are areas designated for public and semi-public uses, including governmental buildings, schools, churches, and worship centers, utilities, solid waste handling and disposal facilities, airports, logistic centers when operated on public property, recycling facilities, and similar public and semi-public uses. This category may also include publicly-owned parks and other public/semi-public recreational facilities. There is no dispute that the Plan Amendment would allow both EEPs and large-scale commercial and industrial uses within the Public land use category. Large-scale commercial and industrial development is inconsistent with the purpose of the Public land use category adopted in Policy 1.1.11 and the uses established therein. Because the Plan Amendment provides no clear definition of an EEP, and leaves the determination solely to the County Administrator, it is impossible to determine whether allowing said development in the Public land use category would necessarily be inconsistent with Policy 1.1.11. Policy 1.1.13 governs uses in the Leisure/Recreation category. The Policy establishes the following purpose and uses: Purpose The purpose of the Leisure/Recreation Future Land Use Category is to define those areas within Hendry County which are used or may become used for free standing/independent leisure/recreation activities through the planning horizon 2040. * * * Description/Uses Leisure/Recreation areas are sites which are currently developed for leisure/recreation facilities or undeveloped sites which are designated for development as leisure/ recreation facilities. . . . Uses allowed within this category shall be limited to sports facilities whether individually developed or in sports complexes, active and/or passive parks, recreation vehicle parks, campgrounds (whether primitive or improved), marinas, golf courses, equestrian centers and riding areas, sporting clay facilities, eco tourism activities, and similar leisure and recreation facilities and ancillary facilities. Large-scale industrial and commercial development would directly conflict with the purpose and types of use allowed within this category pursuant to Policy 1.1.13. As the Plan Amendment provides a very broad definition of EEP, it is impossible to determine that every such use would be inconsistent with Policy 1.1.13. In fact, since an EEP may include eco-tourism uses, location within Leisure/Recreation may be entirely suitable. Petitioner next contends that the Plan Amendment is internally inconsistent with Policy 1.5.17, which provides, as follows: The County’s development regulations shall specifically encourage redevelopment, infill development, compatibility with adjacent uses, and curtailment of uses inconsistent with the character and land uses of surrounding area, and shall discourage urban sprawl. No evidence was introduced regarding whether the County’s land development regulations fall short of this Policy mandate. The County’s expert testified that he had not reviewed the County’s land development regulations to determine whether they met this requirement. Petitioner’s expert provided no testimony on this issue. Petitioner did not prove the Plan Amendment is inconsistent with Policy 1.5.17. Other Plan Elements Next, Petitioner contends the Plan Amendment is inconsistent with Infrastructure Element Objective 7.A.3 and Policy 7.A.3.1, which read as follows: Objective 7.A.3: The County shall maximize use of existing sewer facilities and discourage urban sprawl within infill development. In addition, limit the extension of sewer service to areas designated for urban development on the Future Land Use Map. This Objective shall be implemented through the following policies: Policy 7.A.3.1: The Future Land Use Element and Map allows density and the most flexibility for development in the areas near the Cities where sewer facilities are available, or are more feasible for sewer connections than the more remote areas. The Plan Amendment allows development of both EEPs and large-scale commercial and industrial projects regardless of the availability of existing sewer facilities to the project site. The Plan Amendment expresses no preference between, and alternately allows said development with either, access to existing sewer facilities, or provision of on-site wastewater treatment. The Plan Amendment does not change the land use designations on the existing Future Land Use Map. Nearly 580,000 acres opened up for EEPs and large-scale commercial and industrial development under the Plan Amendment is designated on the FLUM as Agriculture. Policy 1.1.1 specifically defines the Agriculture category for those areas of the County “which will continue in a rural and/or agricultural state through the planning horizon of 2040.” The Policy clearly characterizes the Agriculture designations on the FLUM as “rural areas of Hendry County,” and, while it recognizes that “some of these lands may be converted to urban uses” within the planning horizon, “the majority of the lands classified Agriculture will remain in a rural, agricultural land use through the year 2040.” Policy 2.1.2 specifically allows a public or private provider to “extend and/or expand” utilities in order to serve an EEP or large-scale commercial or industrial development. Thus, the Plan Amendment does not “limit the extension of sewer service to areas designated for urban development on the Future Land Use Map” as required by Objective 7.A.3. Likewise, the Plan Amendment does not “allow the greatest density and the most flexibility for development in the areas near the Cities where sewer facilities are available, or are more feasible for sewer extensions than the more remote areas.” Indeed, Ms. Catala testified consistently that one of the main objectives of the Plan Amendment was to provide more flexibility for development than allowed under the existing plan. Next, Petitioner maintains the Plan Amendment is inconsistent with Traffic Circulation Element Policy 8.5.3, which reads as follows: Revisions of the roads on the Future Traffic Circulation Map shall be coordinated with and connect or directly serve existing development areas or projected growth areas shown on the Future Land Use Map. The Plan Amendment does not revise any roads on the Future Traffic Circulation Map. No evidence was presented that the said revisions would not be coordinated with existing or projected growth areas shown on the Future Land Use Map. Thus, Petitioner did not prove the Plan Amendment is inconsistent with Policy 8.5.3. Next, Petitioner contends the Plan Amendment is inconsistent with Concurrency Management Element Policy 9.2.1, which reads, as follows: The Future Land Use Map is developed to coincide with the availability of public facilities and/or natural resources such that new facilities are not necessarily required for new development. The Plan Amendment allows both EEPs and large-scale commercial and industrial development to occur without regard to availability of public facilities. Although Policy 2.1.2 recognizes the importance of serving these new projects by adequate utilities of all types, it specifically allows public providers to build new, or extend existing, infrastructure to serve those developments. Further, the Plan Amendment anticipates the construction of new facilities to serve these developments, even requiring the County to accelerate projects in its Capital Improvements Program. The Plan Amendment conflicts with Policy 9.2.1 by authorizing development in areas on the FLUM for which public facilities are neither available nor planned. Future Land Use Map Series Finally, Petitioner alleges the Plan Amendment is inconsistent with the maps adopted in the current plan, specifically the FLUM and Conservation Map series. Because the Plan Amendment allows large-scale commercial and industrial developments in land use categories with which those uses are inconsistent, the location and distribution of uses shown on the FLUM are no longer accurate. The Conservation Map series indicates the generalized location in the County of eight different environmental categories, including soils, panther habitat, and historical resources. Very little evidence was adduced relative to whether the Plan Amendment directly conflicted with any one of the maps in the series. The evidence presented related more to the issue of whether the Plan Amendment was supported by data and analysis. Petitioner did not prove beyond fair debate that the Plan Amendment directly conflicts with the Conservation Map series. Urban Sprawl Petitioner’s final challenge to the Plan Amendment is that it does not discourage urban sprawl as required by section 163.3177(6)(a)9. Section 163.3177(6)(a)9.b. provides as follows: The future land use element or plan amendment shall be determined to discourage the proliferation of urban sprawl if it incorporates a development pattern or urban form that achieves four or more of the following: Directs or locates economic growth and associated land development to geographic areas of the community in a manner that does not have an adverse impact on and protects natural resources and ecosystems. Promotes the efficient and cost- effective provision or extension of public infrastructure and services. Promotes walkable and connected communities and provides for compact development and a mix of uses at densities and intensities that will support a range of housing choices and a multimodal transportation system, including pedestrian, bicycle, and transit, if available. Promotes conservation of water and energy. Preserves agricultural areas and activities, including siliviculture, and dormant, unique, and prime farmlands and soils. Preserves open space and natural lands and provides for public open space and recreation needs. Creates a balance of land uses based upon demands of the residential population for the nonresidential needs of an area. Provides uses, densities, and intensities of use and urban form that would remediate an existing or planned development pattern in the vicinity that constitutes urban sprawl or if it provides for an innovative development pattern such as transit-oriented development or new towns as defined in s. 163.3164. Petitioner maintains the Plan Amendment does not meet any of the listed criterion, thus the Plan Amendment does not discourage the proliferation of urban sprawl. The County maintains the Plan Amendment meets at least four of the foregoing indicators, and, thus, must be determined to discourage the proliferation of urban sprawl. The County’s expert witness testified that, in his opinion, the Plan Amendment meets indicators I, II, IV, V, VII, and perhaps VI. In making the following findings, the undersigned considered the testimony of both Petitioner’s and Respondent’s expert witnesses and found Petitioner’s expert opinions to be the more credible and persuasive. The Plan Amendment meets indicator I if it directs or locates EEPs and large-scale commercial and industrial development “in a manner that does not have an adverse impact on and protects natural resources and ecosystems.” The Plan Amendment contains no locational criteria for EEPs and large-scale commercial and industrial developments within the 580,000 acres of land opened up for these uses under the Plan Amendment. County staff had data, in the form of the existing conservation land use map series and the soils map, to draw from in determining areas inappropriate for these types of development. Ms. Catala did not rely upon that data, however, explaining instead that her knowledge of the location of wetlands, floodplains, and other natural resources within the subject area was derived from her day-to-day work. Ms. Catala performed no analysis of the impact of potential large-scale commercial or industrial uses on the natural resources and ecosystems which are present in the affected area. The County argues that the Plan Amendment meets criterion I because it does not allow the subject developments in the Agriculture Conservation Land Use Category, thus the Plan Amendment directs development away from natural resources located in that category. Policy 1.1.1(b). states the purpose of the Agriculture Conservation category is to define those areas within the County which are predominantly jurisdictional wetlands or contain a large portion of wetlands. Land in this category also includes state projects designed to meet the water quality and quantity goals related to the Comprehensive Everglades Restoration Plan. The policy strictly limits both the type and intensity of development which may be located within this category. For example, non-agricultural development is limited to large-lot single-family homes, clustered developments, and rural PUDs, at an intensity no greater than 0.10. The County’s argument misses the mark. The issue is not whether the uses allowed under the Plan Amendment are excluded from land in protected categories, but whether the Plan Amendment directs development away from natural resources present in the 580,000 acres affected by the Plan Amendment. The Conservation Element Map Series documents the location of wetland, floodplains, primary and secondary panther habitat, and hydric soils within the County, including the area affected by the Plan Amendment. Because the Plan Amendment allows the subject development to occur anywhere within the 580,000 acres without regard to location of natural resources, it cannot be found to direct or locate development “in a manner that does not have an adverse impact on and protects natural resources and ecosystems.” The Plan Amendment does not meet criterion I. Criterion II applies if the Plan Amendment promotes the efficient and cost-effective provision or extension of public infrastructure and services. The Plan Amendment allows the subject development to locate without regard to the availability of public infrastructure or services. The Plan Amendment acknowledges that the development must be served, but anticipates that a public or private provider may have to extend services to the property, and does not discourage location of said projects in remote areas where said services are neither available nor planned. Further, the Plan Amendment acknowledges that the County may have to “expend funds not already provided for in the County Capital Improvement Program” to serve the development. Extending services to remote areas of the County is neither efficient nor cost-effective, especially in light of the fact that development could occur in multiple far-flung areas under the Plan Amendment. The Plan Amendment does not meet criterion II. Likewise, the Plan Amendment does not meet sprawl criterion IV because it does nothing to promote conservation of water and energy. The Amendment allows on-site utilities, including wells, to service new development. By allowing development in remote areas of the County, the Plan Amendment does not promote energy conservation. Likewise, the Plan Amendment does not meet criterion V, “[p]reserves agricultural areas and activities, including silviculture, and dormant, unique and prime farmland and soils.” The Plan Amendment does not relate to the soils map and direct development away from prime farmland and soils. Further, the Plan Amendment allows conversion of some 580,000 acres of land designated “Agriculture” to non-agricultural uses. Lands in the Agriculture land use category have been designated by the County to “continue in a rural and/or agricultural state through the planning horizon of 2040.” The Plan Amendment meets criterion VI if it “preserves open space and natural lands and provides for public open space and recreation needs.” The County’s expert testified that the Plan Amendment will increase the County’s tax base so that more public open space and recreation can be provided. Petitioner’s expert testified that the subject developments will intrude into rural open spaces and natural lands and “could change the scenic landscape” of the County. The Plan Amendment does not meet criterion VI. Criterion VII applies if the Plan Amendment creates a balance of land uses based upon demands of the residential population for the non-residential needs of the area. Neither party introduced any evidence regarding the amount of commercial or industrial development needed to serve the residential population of the County. Certainly the unemployment statistics indicate a need for employment opportunities. Petitioner did not prove that the Plan Amendment does not meet criterion VII. Criterion III and VIII do not apply to the Plan Amendment. Having determined that the Plan Amendment does not meet four or more of the criterion to be determined not to promote the proliferation of urban sprawl, the analysis then turns to the primary indicators of urban sprawl. Section 163.3177(6)(a)9.a. lays out 13 primary indicators that a plan amendment does not discourage the proliferation of urban sprawl. Again, the evidence conflicted as to whether the Plan Amendment meets any of the indicators. In making the following findings, the undersigned has considered the testimony of both Petitioner’s and Respondent’s expert witnesses, and found the testimony of Petitioner’s expert to be the more credible and persuasive. The Plan Amendment meets several of the primary indicators of the proliferation of urban sprawl. The Plan Amendment allows loosely-identified EEPs and large-scale commercial development to occur in roughly 580,000 largely rural acres currently designated for Agriculture. The Plan Amendment does not limit location of these developments within the Agriculture designation. Thus, the Plan Amendment “[p]romotes, allows, or designates significant amounts of urban development to occur in rural areas at substantial distances from existing urban areas while using undeveloped lands that are available and suitable for development” which is indicator II. Promoting these areas for development is, in fact, the main purpose of the Plan Amendment. Indicator IV is triggered if the Plan Amendment “[f]ails to adequately protect and conserve” a litany of natural resources and natural systems. The Plan Amendment meets this indicator because it does not direct development away from natural resources which may be located within the 580,000 acres in which it promotes development. Under the Plan Amendment, vast areas currently in, or designated for, agricultural uses, are allowed to convert to urban uses without a plan amendment. The Plan Amendment does not direct development away from existing agricultural uses. Thus, the Plan Amendment meets indicator V: “Fails to adequately protect adjacent agricultural areas and activities, including silviculture, active agricultural and silvicultural activities, passive agricultural activities, and dormant, unique, and prime farmlands and soils.” Similarly, the Plan Amendment “[f]ails to provide a clear separation between rural and urban uses[,]” thus triggering indicator IX. On the issue of public facilities, the Plan Amendment meets both criterion VI and VII. The Plan Amendment fails to maximize the use of existing public facilities because it does not direct development to areas where public facilities, including roads, sewer, and water, are available. Likewise, the Plan Amendment fails to maximize the use of future public facilities, because it allows development to occur in areas where public facilities are not planned. In addition, the Plan Amendment anticipates the extension of facilities to serve potentially far-flung development, but would not require subsequent future development to locate where the new service was available (i.e., infill development). For this same reason, the Plan Amendment discourages infill development, triggering indicator X. Similary, because it allows scattered large-scale development, the Plan Amendment triggers indicator VIII: “Allows for land use patterns or timing which disproportionately increase the cost in time, money, and energy of providing and maintaining” a litany of public facilities and services. Petitioner did not prove by a preponderance of the evidence that the Plan Amendment triggers indicators I, III, XI, XII, and XIII. Petitioner proved that the Plan Amendment meets indicators II, IV, V, VI, VII, VIII, IX, and X. On balance, the Plan Amendment does not discourage the proliferation of urban sprawl.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Administration Commission enter a Final Order determining that the Plan Amendment is not “in compliance.” DONE AND ENTERED this 12th day of February, 2015, in Tallahassee, Leon County, Florida. S SUZANNE VAN WYK Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 12th day of February, 2015.
Findings Of Fact Based upon all of the evidence, including the stipulation of counsel, the following findings of fact are determined: Respondent, Jefferson County (County), is a local governmental unit subject to the land use planning requirements of Chapter 163, Florida Statutes. That chapter is administered by respondent, Department of Community Affairs (DCA). The DCA is charged with the responsibility of reviewing comprehensive growth management plans and amendments thereto. At issue in this case is a land development regulation adopted by the County. Petitioner, Jack Hamilton, is a resident of Jefferson County. He owns and operates a nursery, orchard and cattle operation on his property on the east side of Highway 19, approximately two miles north of Monticello, Florida. The land, which is approximately 135 acres in size, is presently designated in a land use category known as Agriculture 2. For almost thirty years, the Jefferson Nursing Center (JNC), a nursing home, has been situated on a seven acre parcel of land surrounded on three sides by petitioner's property. Here, petitioner challenges a land development regulation which allows nursing homes, including JNC, in the Agriculture 2 category. The parties have stipulated that petitioner is a substantially affected person within the meaning of the law and thus he has standing to bring this action. The County adopted its comprehensive plan (plan) on July 19, 1990. The plan was later determined by the DCA to be in compliance. The County has also adopted a Land Development Code (Code) containing various land development regulations which implement the plan. Prior to the adoption of the challenged ordinance, Section 2.02.03(B)3. of the Code included a provision allowing, among other things, the following uses in the Agriculture 2 land use district: Institutional, excluding residential care facilities and nursing homes. On September 1, 1994, the County adopted Ordinance No. 94-15, which amended Section 2.02.03(B)3. by removing the exclusion, thereby allowing nursing homes and residential care facilities in the Agriculture 2 land use district. Thus, the ordinance made nursing homes a permitted use in the Agriculture 2 district, like all other institutional uses which were allowed in agriculture districts. This was also consistent with other Code provisions which allowed nursing homes in almost every other district. On August 15, 1995, petitioner filed a petition with the DCA contending that the land development regulation was not consistent with the plan. An amended petition was later filed on September 12, 1995, alleging generally that nursing homes did not conform to, and were incompatible with, agriculture uses. On November 13, 1995, the DCA entered its Determination of Consistency of Jefferson County Ordinance 94-15. Among other things, the DCA based its finding of consistency on the following provisions in the Housing Element of the plan: GOAL: Assure the availability of housing to meet the existing and future needs of all residents of Jefferson County for all income levels. Objective 5: The useful life of the existing housing stock will be conserved and extended, and neighborhood quality will be improved. Policy 5-3: The County shall establish non-discriminatory standards and criteria addressing the location of group homes and foster care facilities as well as other types of special need housing. The specific uses to be allowed in the agricultural land use categories were largely deferred to the land development regulations contained in the Code. Those regulations define residential care facilities and nursing homes (group homes) as institutional uses. Policy 5-3 requires that the County establish "non-discriminatory standards and criteria" in addressing the location of group homes. Before the adoption of Ordinance 94-15, all institutional uses, except nursing homes and residential care facilities, were allowed in agricultural districts. The new land development regulation removes this discriminatory feature. The plan recogizes that the character of development in the rural areas of the County is of mixed uses which are of a scale to intermix without creating incompatibilities. The area in which petitioner's property and JNC are located contains a mix of uses. Ordinance No. 94-15 is consistent with the character of rural development in the County. The Future Land Use Element of the plan provides in relevant part as follows: GOAL: Efficiently manage and regulate land use types, locations, and densities in compatibility with natural and man-made resources so as to provide the residents of Jefferson County with an aesthetically pleasing, economically beneficial, and socially adequate environment. * * * Policy 1-3: The categories on the Future Land Use Map are defined as follows: * * * Agriculture 2: This includes areas appropriate for a variety of agricultural uses, including but not limited to crop land, pasture land, orchards and groves, or forestry. Dwellings and associated accessory farm buildings are allowable. Density for residential use shall not exceed 1 unit per 5 acres, except that transfer of property to members of the principal owner's immediate family is allowable, provided that all other applicable requirements are met. However, as provided in other policies of the Future Land Use Element, density is calculated on a gross basis (area-based allocation); actual units should be clustered, subject to the requirements set forth in the objectives and policies of the comprehensive plan so long as the gross density is not exceeded. Under the plan, dwellings are allowed uses in the agriculture 2 land use district. A disputed issue is whether the uses allowed by Ordinance No. 94- 15 are residential uses. Petitioner's expert conceded that it is within the discretion of a local government to define nursing homes as a residential use, and that the County's plan tends to do so. The evidence establishes that residential care facilities, such as adult congregate living facilities, are a residential land use. Since dwellings (residences) are an allowed use in the agriculture 2 land use district, it is at least fairly debatable that residential care facilities are also allowed in that district. In addition, in the Housing Element of the plan, nursing homes are included in the discussion and inventory of group homes in the County. They are considered to be special needs housing for the elderly. The plan recognizes that housing needs for the elderly often form a distinct sub-market of the total housing market, and projects that the elderly population (65 and older) will be the second fastest growing age group in the County by the year 2000. When reading the Housing Element provision in pari materia with the Future Land Use Element, it is at least fairly debatable that nursing homes are residential or dwelling uses in the plan and are therefore allowed in the agriculture 2 district. Given the foregoing, it is found that the challenged land development regulation is consistent with the plan.