SWEEPING CORPORATION OF AMERICA, INC. vs DEPARTMENT OF TRANSPORTATION, 91-008230BID (1991)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Dec. 26, 1991 Number: 91-008230BID Latest Update: May 01, 1992

Findings Of Fact Based upon the oral and documentary evidence adduced at the final hearing and the entire record in this proceeding, the following findings of fact are made. On October 11, 1991, DOT's District Four office let out for bid district contracts E4551 and E4554. Contract E4551 calls for the mechanical sweeping of Interstate 95 in Broward County. Contract E4554 calls for the mechanical sweeping of Interstate 95 in Palm Beach County. At a mandatory pre-bid conference, the bidders for the Contracts were provided with a packet which included a Notice to Contractors and Standard Specifications. The Notice to Contractors is a four page document which is specific to each contract. The Standard Specifications are the same for all district contracts. Both the Notice to Contractors and the Standard Specifications to the bidders required bidders to submit proof of the ability to acquire a performance and payment bond in an amount equal to the contract bid price. Bidders could satisfy this requirement by submitting a bid guarantee of 5% of the bid, submitting a notarized letter of intent from a bonding company or by providing a Certificate of Qualification issued by Respondent. The Notice to Contractors for both Contracts provided as follows: Failure to provide the following with each bid proposal will result in rejection of the contractor's bid.... District contracts of $150,000 or less require the following as proof of ability to acquire a performance and payment bond: A notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a performance and payment bond in the amount of your bid, should your firm be awarded the project; in lieu of a notarized letter the following may be substituted: (1) a bid guarantee of five percent (5%); or (2) a copy of the Contractor's Certificate of Qualification issued by the Department. (No emphasis added) Similarly, the first Standard Specification provides: 1.1 Bidders (contractors) A contractor shall be eligible to bid on this contract if:... (2) Proof of ability to acquire a performance and payment bond in an amount equal to the contract bid price is provided to the District Contract Administrator with the bid proposal. As such proof all bids must be accompanied by a notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a bond in the amount of your bid, should your firm be awarded the project.... The requirement to submit proof of the ability to acquire a performance and payment bond has been imposed on the Districts by DOT Directive 375-00-001-a (hereinafter the "Directive".) This Directive was in place at all times material to this proceeding. Section 3.2.2 of the Directive provides: A contractor shall be eligible to bid if: ...Proof of ability to acquire a performance and payment bond in an amount equal to the contract bid price is provided to the minicontract administrator with the bid proposal. As such proof all bids must be accompanied by a notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a bond in the amount of the bid, should the firm be awarded the project. A bid guaranty as specified above may substitute as proof of ability to obtain a performance and payment bond. This applies to bids amount over or under $150,000. A copy of the Contractor's Certificate of Qualification issued by the Department may be substituted in lieu of a notarized letter for those contracts not requiring a bid bond. The bids for the Contracts were opened on October 11, 1991 in Fort Lauderdale, Florida. Bids were received from four bidders: CPM, SCA, Florida Sweeping, Inc. and P. F. Gomez Construction Co., Inc. In its bid proposals, SCA included executed bid bonds in an amount sufficient to cover the amount of each bid proposal. Each bid bond cost $55.00. CPM did not submit executed bid bonds with its proposals. Instead, CPM submitted letters from Mark A. Latini dated September 25, 1991. Those letters were provided on the stationery of Bonina-McCutchen-Bradshaw, Insurance and indicate that Mr. Latini is the "bond manager." The letters provide as follows: Amwest Surety Insurance Company is the surety for the above-referenced contractor and stands ready to provide the necessary performance and payment bond for the referenced bid should Certified Property Maintenance, Inc., be low and awarded the referenced contract. All bonds are subject to normal underwriting requirements at the time of the bond request.... The letters submitted by CPM with its bid proposals were not notarized and were not binding obligations to issue bonds since they were conditioned upon meeting certain unspecified underwriting requirements at the time of the bond requests. The submitted bids were reviewed by the District Four Contractual Services Office. The bids submitted by CPM were the lowest for each contract. Its bid for Contract No. E4551 was $109,343.97. Its bid for Contract No. E4554 was $30,312.63. SCA's bids for the Contracts were $139,442.14 and $44,100.00, respectively. During the initial review of the bid proposals, the Contractual Services Office rejected CPM's bids for failure to have its bonding company "letters of intent" notarized. In addition, the bid proposals submitted by Florida Sweeping, Inc. were rejected for failure to note a required addendum and the bids submitted by P. F. Gomez Construction Co., Inc. were rejected because the "proposal bond was not of proper character". On October 18, 1991, DOT posted its Notice of Intent to Award the Contracts to SCA, the only bidder for the Contracts whose proposals had not been rejected. CPM timely filed protests of the proposed awards to SCA on October 22, 1991. The protests filed by CPM argued that its bids should not have been invalidated simply because the bonding company's letters did not include notary seals. At this point, the sole basis for the disqualification of CPM's bids was the failure to have the bonding company letters notarized. Respondent contends that, except for the absence of the notary seal, the letters submitted by CPM met the requirements of the Notice to Contractor and the Standard Specifications cited above. However, those letters are equivocal and do not evidence a binding commitment to issue a bond upon award of the contract. The DOT officials admit that they do not know what "normal underwriting requirements" would or could be required by CPM's bonding company. This conditional language makes it uncertain whether CPM could obtain the necessary bond. Therefore, it is concluded that those letters do not meet the requirements of the Notice to Contractors, the Standard Specifications or the Directive. A hearing on CPM's protest was not held. CPM's president, Raymond Hanousek, who prepared CPM's bid and attended the pre-bid meeting, called DOT's District office the day the bids were opened and was informed that his company's bid was low, but was rejected because its bond commitment letter was not notarized. Mr. Hanousek spoke with Joseph Yesbeck, the District's Director of Planning and Programs. After their conversation, Mr. Yesbeck reviewed the file and met with Teresa Martin, the District's contract administrator for construction and maintenance contracts, and other members of the contracting staff. Ms. Martin explained why CPM's bid had been disqualified, and the matter was thereafter discussed with the District and Department attorneys. After reviewing the situation, Mr. Yesbeck determined that the failure to submit notarized letters should be considered a non-material deviation and the bids submitted by CPM should be accepted and considered the low responsive bids. Mr. Yesbeck concluded that the absence of the notary seal did not give any competitive advantage to CPM and that defects of this nature are routinely allowed to be cured. Therefore, he reversed the contract administrator's decision to disqualify CPM on both Contracts. The District secretary concurred in the decision reached by Mr. Yesbeck to repost the award of the Contracts. Mr. Yesbeck prepared a joint letter of reposting which removed CPM's disqualification and declared CPM to be the low bidder for both Contracts. At the time Mr. Yesbeck made his decision, he had not reviewed the Directive from the Assistant Secretary's office stating that there must be a notarized letter showing proof of ability to obtain a performance and payment bond. Mr. Yesbeck did not review the Directive until his deposition was taken one week prior to the hearing in this case. According to Ms. Martin, the option to provide a notarized letter from a bonding company as an alternative to the posting of a 5% bid guarantee or obtaining prequalification was designed to promote participation in state contracting by small business and minority business enterprise applicants. While DOT was apparently trying to make it easier and cheaper for companies to bid by not requiring a bond to be posted, the DOT Directive and the bid documents still clearly required unconditional proof that a bid bond would be issued if the contract was awarded to the bidder. CPM was not prequalified nor did it post a bond. Thus, in order to meet the requirements of the Notice to Contractors and the Standard Specifications, CPM's only option was to submit a notarized letter showing proof of ability to obtain a performance and payment bond. DOT was never provided with any proof that CPM had been prequalified by the bonding company for a bond and/or that a bond would unconditionally be issued if CPM was awarded the Contracts. Because the letters stated they were "subject to normal underwriting requirements at the time of the bond request", there was some possibility CPM would not be able to obtain a bond. Such a condition was not permissible under the bid doucments. The decision to accept CPM's bid was contrary to the DOT Directive, the Notice to Contractors and the bid specifications which require that a bidder demonstrate proof of ability to obtain a performance and payment bond. Consequently, it is concluded that DOT's decision to accept the conditional, unnotarized letters submitted by CPM was arbitrary and capricious. There is some indication that other DOT Districts have, on occasion, waived the notarization requirement for the bond letter. However, it is not clear whether the language in the bid documents was the same or similar in those cases and/or whether the bond letters were conditional. In the past, whenever District Four has gotten a bid without a notarized bond letter, the bid was rejected. Apparently, there has never been a protest based on such a denial in District Four. Under Section 337.18, DOT does not need to require notarized, unconditional bond letters on contracts under $150,000. Indeed, there was a suggestion that some DOT Districts have dropped the requirement for certain contracts under $150,000. However, the bid documents in this case clearly required some proof that the bidder could acquire a performance and payment bond upon award of the Contracts. It was incumbent for all bidders to meet this requirement. It was arbitrary to delete this requirement after the bids were submitted.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner enter a Final Order finding the bids submitted by CPM to be non-responsive and rejecting those bids. Petitioner should enter into negotiations with SCA regarding the award of the contract. In the absence of a favorable negotiation, Petitioner should enter a Final Order rejecting all bids and opening the Contracts up for new bids. DONE and ENTERED this 24th day of March, 1992, at Tallahassee, Florida. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of March, 1992.

Florida Laws (8) 120.53120.57120.68287.012287.057337.11337.18343.97
# 1
SOUTHERN STAR EVENT SERVICES, INC. vs PALM BEACH COUNTY SCHOOL BOARD, 94-002922BID (1994)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida May 26, 1994 Number: 94-002922BID Latest Update: Aug. 16, 1996

The Issue Whether Respondent acted fraudulently, arbitrarily, illegally, or dishonestly in determining that Intervenor's bid was responsive.

Findings Of Fact On March 16, 1994, the Respondent issued an invitation to bid (ITB) for security guard services. The desired services were described in detail by the bid documents. Bids from eleven bidders, including a bid from Petitioner and a bid from Intervenor, were opened on April 13, 1994. After the bids were evaluated, the Respondent determined that Intervenor's and Petitioner's bids were responsive. Intervenor was determined to be the lowest bidder and Petitioner was determined to be the second lowest bidder. Respondent thereafter notified all bidders that it intended to award the bid to Intervenor. Pertinent to this proceeding, the bid document contained the following general condition: AWARDS; In the best interest of the School Board, the Board reserves the right to reject any and all bids and to waive any irregularity in bids received . . . [Emphasis has been added.] Pertinent to this proceeding, the bid document contained the following special conditions: G. OCCUPATIONAL LICENSE: Each bidder, by submitting a bid, certifies that they possess a Class B license issued by the State of Florida as well as town and county occupational license. ALL BIDDERS MUST SUBMIT PROOF OF THE ABOVE REFERENCED LICENSE WITH THEIR BID (PHOTOCOPY) IF IT IS TO BE CONSIDERED FOR AWARD. * * * J. QUALIFICATIONS: The bidder will have maintained continual work experience in security guard services for a period of three years prior to the bid date. Bidder must submit written documentation with bid or within three days upon request, substantiating experience requirement. The bidder will have a place for contact by the owner during normal working days. [Emphasis in the original.] Petitioner timely protested the intended award of the bid to Intervenor on the ground that the Intervenor did not have an occupational license issued by Palm Beach County at the time of its response as required by Special Condition G. Intervenor submitted with its bid a copy of its Class B license issued by the State of Florida, Division of Licensing, and a copy of its occupational licenses issued by Broward County. Because Intervenor did not have any business in Palm Beach County at the time it submitted its bid, it did not have an occupational license issued by Palm Beach County. Respondent determined that Special Condition G. was met when Intervenor submitted a copy of its Class B license. Respondent has the discretion to waive as a minor irregularity the fact that Intervenor did not have a Palm Beach County occupational license at the time it submitted its bid. There was evidence that Respondent waived similar irregularities in the occupational licenses of other bidders, including an irregularity pertaining to the Petitioner. There was no evidence that the Respondent acted fraudulently, arbitrarily, illegally, or dishonestly in determining that Special Condition G. had been met. Intervenor was not afforded an unfair advantage in the bid process by this determination. Petitioner also timely protested the intended award of the bid to Intervenor on the ground that the Intervenor had not been incorporated for three years at the time of the bid and that it did not meet the experience condition contained in Special Condition J. The Intervenor was incorporated August 27, 1992. At the time of the bid, the Intervenor had been a viable business for more than two years but less than three years. Mr. Inyang, the president of the corporation, submitted documentation that established that his qualifications and experience exceeded the requirements of Special Condition J. Respondent acted within its discretion in determining that the experience of the president of the corporation satisfied the requirement that the bidder "... have maintained continual work experience in security guard services for a period of three years prior to the bid date" as required by Special Condition J. There was no evidence that the Respondent acted fraudulently, arbitrarily, illegally, or dishonestly in making this determination as to Intervenor's experience. Intervenor was not afforded an unfair advantage in the bid process by this determination.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Respondent dismiss Petitioner's bid protest. DONE AND ENTERED this 18th day of July, 1994, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of July, 1994. COPIES FURNISHED: Donald H. Neff, President Southern Star Event Services, Inc. 316 Flamingo Road West Palm Beach, Florida 33401 Robert A. Rosillo, Esquire Palm Beach County School Board 3318 Forest Hill Boulevard West Palm Beach, Florida 33406-5813 Robert E. Inyang, President Michael Graziano, Investigator Supreme Intelligence Agency, Inc. 4700 North State Road 7, Suite 120 Lauderdale Lakes, Florida 33319 Dr. C. Monica Ulhorn, Superintendent Palm Beach County School Board 3340 Forest Hill Boulevard West Palm Beach, Florida 33406-5869

Florida Laws (3) 120.57287.012287.057
# 3
VICK GRIFFIN CONSTRUCTION COMPANY vs. LONG CONTRACTORS, INC., AND NORTH FLORIDA JR. COLLEGE, 82-000654 (1982)
Division of Administrative Hearings, Florida Number: 82-000654 Latest Update: Apr. 29, 1982

Findings Of Fact On or about December 29, 1981, the College solicited sealed bids for construction of alterations and additions to the Technical and Gymnasium Buildings located on its campus in Madison, Florida. In response, seven general contractors submitted bids. (P-1, P-2, P-3.) Bids were publicly opened on February 9, 1982. Griffin Construction, with a bid of $536,575, was the apparent low bidder; the second lowest bidder was Long Contractors, with a bid of $539,512. (Testimony of Griffin, Sims, Rutherford; P-3, P-4, P-5.) After the low bid was identified, Tom McClanahan, representing Long Contractors, asked that the subcontractor list accompanying the low bid be opened. Griffin Construction's subcontractor list was then opened. McClanahan asked if the license and charter numbers of the subcontractors were listed. 2/ Upon learning that these numbers were not included on Griffin Construction's subcontractor list, McClanahan protested. (Testimony of Sims, Rutherford, Griffin.) At its February 15, 1982, meeting, the College District Board of Trustees ("Board") rejected the low bid of Griffin Construction on the sole ground that the omission of subcontractor license and charter numbers constituted a failure to comply with the conditions of the bid documents. 3/ The Board then voted to award the contract to Long Contractors, the second lowest bidder, on the ground that it was the lowest bid conforming to the bid documents. In so doing, the Board followed the College president's recommendation--a recommendation based on his belief that the non-complying bid must be rejected, that it did not involve a matter of Board discretion. (Testimony of Sims, Rutherford, Griffin; Stipulation of Parties; P-41.) The bid specifications contain instructions to bidders requiring "each Bidder . . . [to] submit with his proposal a list of the subcontractors who will perform the work . . . as indicated by the `List of Subcontractors' form." (P-1, P-2.) The instructions further provide: The applicable subcontractor license registration or certification number must be noted on the bid opposite his name, and in the event that the subcontractor is a corporation, his State Corporate Charter number shall also be noted. If the subcontractor is an out of state firm, their Charter number with the Secretary of State to do business in the State of Florida should also be noted. The "Listing of Subcontractors" form provided with the specifications contains column headings for the names and addresses of the subcontractors but does not contain a separate heading for the requested license or corporate charter numbers. 4/ The form states that the subcontractor list "is an integral part of the bid." (P-1, P-2.) The bid instructions further require bidders to evaluate and determine the qualifications of their listed subcontractors. The bidder shall have determined to his own complete satisfaction that a listed subcontractor has been successfully engaged in this particular type of business for a reasonable length of time, has successfully completed installations comparable to that which is required by this agreement and is qualified both technically and financially to perform that pertinent phase of the work for which he is listed. (P-1, P-2.) The bid documents expressly reserve to the College the right "to reject any or all bids, and to waive informalities." (P-1 P-2.) No bidder correctly listed the required license and corporate charter numbers on its "Listing of Subcontractors" form. Griffin Construction. Griffin failed to include any license or corporate charter numbers. However, by subsequent letters dated February 9 and February 18, 1982, and at hearing, it supplied the required subcontractor license and charter numbers. Long Contractors. Long listed for its roofing subcontractor a sheet metal registration number, not the required roofing license number. [A sheet metal registration does not qualify a contractor for roofing work. See, 489.105, 489.113, Fla. Stat. (1981).] For its electrical subcontractor, Long omitted the prefix, "ER" from the listed number. For its plumbing subcontractor, Long listed a mechanical registration number instead of the required plumbing certification or registration number. [A mechanical registration does not qualify a contractor to perform plumbing work. See, 489.105, 489.113, supra.] Of the four areas requiring state licenses--roofing, heating and air conditioning, electrical, and plumbing--Long listed correctly only the registration number for its heating and air conditioning subcontractor. Long incorrectly listed No. FO6962 as the corporate number of Gandy Enterprises, its painting subcontractor. This is the number of a related corporation, Industrial Coatings, Inc. Remaining Bidders. Of the five other general contractors submitting bids, two-- Richard Walker Construction Company and GRC Contracting, Inc.--omitted all subcontractor license and charter numbers. The other three bidders failed to completely list all the required numbers. (Testimony of Rutherford; P-11, P-12, P-13, P-14, P-15, P-16, P-17, P-34, P-37, R-1, R-5.) The project architect testified that the submittal of incorrect or incomplete subcontractor license and charter numbers was a deficiency which a bidder should be allowed to cure after bid opening. But the failure to submit any required "number" was a deficiency which, in his opinion, could not be similarly corrected. He failed, however, to supply a reasonable basis for drawing such a distinction. Therefore, his opinion on this question is given little weight. 5/ (Testimony of Rutherford.) Subcontractor license and charter numbers are readily obtainable and can be verified by contacting the pertinent state agency--the Florida Department of Professional Regulation, Construction Industry Licensing Board, or the Florida Department of State. (Testimony of Griffin, Rutherford; P-32, P-33, P- 34, P-35, P-36, P-37.) The project architect, William Rutherford, routinely requires the listing of subcontractor license and charter numbers on bids for public construction projects. The main purpose it serves is that it would enable him to identify the listed contractor, since sometimes subcontractors have similar business names. Although if he was uncertain about the qualifications of a subcontractor, he would ordinarily question the general contractor. (Testimony of Rutherford.) Although Mr. Rutherford has customarily required the listing of subcontractor "numbers" on public projects, he has never made any use of those numbers in the past. (Testimony of Rutherford.) The general contractor who is awarded the contract is responsible to Mr. Rutherford and the College for construction of the project in accordance with the bid specifications. If, after bid opening, a listed subcontractor is unable to perform, Mr. Rutherford would ordinarily arrange for substitution of a new subcontractor acceptable to the general contractor and owner. (Testimony of Rutherford.) Griffin Construction's failure to list the license and charter numbers of its listed subcontractors, and its subsequent curing of that failure, did not affect the amount of its bid 6/ by giving it an advantage or benefit not enjoyed by other bidders. The bid omission did not allow Griffin Construction the opportunity to change any material element of its bid after bid opening. The inclusion or exclusion of subcontractor "numbers" at bid opening does not affect the ability of a contractors to obtain the required bond, the quality of bidding general contractors, the quality of listed subcontractors, the quality of work performed, or any material feature of the competitive bidding process. (Testimony of Griffin, Rutherford.)

Recommendation Based on the foregoing, it is RECOMMENDED: That the construction contract in question be awarded to Vick Griffin Construction Company, the lowest responsible bidder. DONE AND RECOMMENDED this 29th day of April, 1982, in Tallahassee, Florida. R. L. CALEEN, JR. Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of April, 1982.

Florida Laws (3) 120.5720.15489.105
# 4
TAMCO ELECTRIC, INC. vs PINELLAS COUNTY SCHOOL BOARD, 13-002152BID (2013)
Division of Administrative Hearings, Florida Filed:St. Petersburg, Florida Jun. 13, 2013 Number: 13-002152BID Latest Update: Nov. 13, 2013

The Issue Whether Respondent's action to reject all bids submitted in response to ITB 13-803-205, relating to the removal and replacement of the public address system at Countryside High School, is illegal, arbitrary, dishonest, or fraudulent, as alleged in the Amended Petition.

Findings Of Fact On March 4, 2013, the ITB was issued by Respondent for work related to the removal and replacement of the public address system at Countryside High School in Clearwater, Florida. According to the Special Conditions portions of the ITB, the "scope" of the project is to "[p]rovide labor and materials to remove and replace the auditorium sound system as per plans and specifications by Keane Acoustics, Inc." The ITB was assigned bid number 13-803-205 by Respondent. Bids for the contract were to be submitted to Respondent by 3:00 p.m., April 11, 2013. Bids for the project were timely received from two companies. The first company, Becker Communications, Inc., d/b/a BCI Integrated Solutions (BCI), submitted a bid in the amount of $118,143.27. Petitioner submitted a bid in the amount of $108,000.00. There is a section of the ITB titled "special conditions." The special conditions provide in part that "[t]his is an ALL or NONE bid [and] [t]he entire contract shall be awarded to the lowest responsive and responsible bidder meeting the specifications." On April 22, 2013, Respondent posted a notice advising of its intent to award the contract to BCI. Although Petitioner submitted the lowest bid, Respondent determined that Petitioner's bid was non-responsive because the bid failed to include "proof of 5 years [of] experience with this type of work" as required by the special conditions of the ITB. Petitioner interpreted this provision as requiring five years of experience as a certain type of general contractor, which Petitioner had, whereas Respondent intended for the ITB to convey that five years of experience related to the removal and installation of audio equipment was the desired type of experience. Petitioner's failure to respond to the ITB in the manner contemplated by Respondent was a technical, nonmaterial irregularity.1/ Numbered paragraph six of the General Terms & Conditions of the ITB provides in part that Respondent "expressly reserves the right to reject any bid proposal if it determines that the . . . experience of the bidder, compared to work proposed, justifies such rejection." On April 24, 2013, Petitioner provided to Respondent a notice advising of its intent to protest the award of the contract to BCI. On May 3, 2013, Petitioner filed its formal protest challenging Respondent's intended action of awarding the contract to BCI. Petitioner's formal protest enumerated several grounds. Of particular concern to Respondent were Petitioner's assertions that the ITB was "inconsistent with Florida law since bidders [were] not required to submit a List of Subcontractors by the time of opening bid"2/ and that provisions of the ITB were ambiguous with respect to the type of experience required to qualify for bidding.3/ Prior to receiving Petitioner's protest, Respondent was unaware of the fact that its bid specifications governing the disclosure of subcontractors did not comply with Florida law. Upon consideration of Petitioner's grounds for protest, Respondent determined that the ITB, as alleged by Petitioner, failed to comply with section 255.0515, Florida Statutes (2012),4/ and that there was ambiguity in the language regarding the experience requirements for bidders.5/ Respondent refers to the problems with the ITB as "procedural errors." These procedural errors will be referred to herein as "irregularities" as this term is more in keeping with the nomenclature of this area of jurisprudence. Given the ITB's irregularities, Respondent decided to reject all bids. In explaining Respondent's rationale for rejecting all bids, Michael Hewett, Respondent's Director of Maintenance,6/ testified that "the [irregularities] were such that [they] potentially could give an unfair advantage to one bidder over another." As for the issue related to the requirements of section 255.0515, Mr. Hewett explained that neither of the two bidders submitted a listing of subcontractors. It would have been competitively disadvantageous to BCI if Petitioner were able to successfully argue that BCI should be disqualified for failing to provide a listing of subcontractors when Petitioner also failed to provide such listing. During the same approximate time that the ITB in the present case was issued, Respondent issued an ITB for nearly identical work to be performed at one of its other facilities (Palm Harbor). In all material respects, the Palm Harbor ITB was identical to the one at issue herein. Unlike the present case, BCI was the sole bidder for the Palm Harbor project and this distinguishing fact reasonably explains why Respondent did not reject BCI's bid for the Palm Harbor Project even though the ITB therein was plagued with the same irregularities found in the present case.7/

Recommendation Upon consideration of the above findings of fact and conclusions of law, it is RECOMMENDED: That the Pinellas County School Board enter a final order finding that the rejection of all bids submitted in response to ITB 13-803-205 was not illegal, arbitrary, dishonest, or fraudulent, and dismissing Tamco Electric, Inc.'s instant protest. DONE AND ENTERED this 16th day of October, 2013, in Tallahassee, Leon County, Florida. S LINZIE F. BOGAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 16th day of October, 2013.

Florida Laws (3) 120.569120.57255.0515
# 5
C AND S CHEMICAL COMPANY vs. DEPARTMENT OF TRANSPORTATION, 87-000012BID (1987)
Division of Administrative Hearings, Florida Number: 87-000012BID Latest Update: Mar. 03, 1987

The Issue Whether the Department of Transportation can reject all bids on State Project No. 37906-9007?

Findings Of Fact In response to an invitation to bid, petitioner C & S Chemical Company (C&S) submitted a bid, No. 9059-86, offering to undertake complete maintenance operations to ensure Rest Area facilities located on State Road 93 (1-75) in Suwannee and Hamilton Counties are maintained in a safe, attractive, clean and sanitary manner." Respondent's Exhibit No. 1. Invitations to bid were mailed in October of last year, (T.9), and bids were to have been opened on December 2, 1987. C&S's bid price was $14,860.76 monthly or $178,329.12 for the year. By letter dated December 9, 1986, however, the Department of Transportation (DOT) advised C&S that all bids had been rejected, stating that the "Department reserved the right to reject any/or all bids when it is determined to be in the best interest of the Department. Petitioner's Exhibit No. 1. C&S mailed notice of protest the same day it received the Department's advice that all bids had been rejected. C&S's formal written protest took the form of a letter, dated December 18, 1986, in which C&S inquired: [H]ow can the Department of Transportation offend and deprive legitimate contractors of this work by negotiating a Contract with a non-profit organization after the bid prices have been made public knowledge? Petitioner's Exhibit No. 2. In this letter, C&S took the position that DOT should not reject all bids: We feel that if the non-profit organizations are going to get Department of Transportation contracts, they should either bid compet[i]tively with private enterprises, or that certain contracts should be set aside for them well advance of the bidding process. At hearing, Mr. Sperring narrowed or clarified the grounds of the protest when he stated, "I have no objection to the concept of the nonprofit organizations as long as they are set aside," (T.12) before bids are invited. The parties agree that, after bids were solicited, DOT decided to award the contract for Project No. 37906-9007 to intervenor Florida Association of Rehabilitative Facilities, Inc. (FARF), even though FARF never bid on the project. By agreement dated August 21, 1985, the Commission for Purchase for the Blind and other Severely Handicapped designated FARF "the central nonprofit agency of the Commission . . . [and its] sole agent." Intervenor's Exhibit No. 2. The day before, DOT Secretary Thomas E. Drawdy had signed a policy statement proclaiming DOT's intention "to procure commodities or services from qualified nonprofit agencies for the blind or other severely handicapped when feasible unless otherwise restricted by budgetary constraints." Intervenor's Exhibit No. 1.

Florida Laws (7) 120.53120.57287.057337.02337.11413.032413.036
# 6
GUIDING LIGHT ENTERPRISE, INC. vs DEPARTMENT OF TRANSPORTATION, 04-002163BID (2004)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Jun. 21, 2004 Number: 04-002163BID Latest Update: Sep. 17, 2004

The Issue The issue in this case is whether the Department of Transportation's proposed award of a contract to Daniels Janitorial Service is contrary to the agency's governing statutes, the agency's rules or policies, or the specifications of the Invitation to Bid (ITB).

Findings Of Fact In April 2004, DOT issued ITB-DOT-04/05-5002-PDW (the ITB) seeking to contract for janitorial services at two state office buildings in DeLand, Florida. The ITB included a "bid blank," upon which vendors were directed to submit their cost proposals. The bid blank was titled "MONTHLY JANITORIAL SERVICES PER SCOPE OF SERVICES." The bid blank included three spaces where each bidder was to provide cost information. The three spaces were titled as follows: "MONTHLY CLEANING - BUILDING 5000 - X 12 MONTHS," "MONTHLY CLEANING - BUILDING 5001 - X 12 MONTHS," and "TOTAL YEARLY AMOUNT BOTH BUILDINGS." In response to the ITB, DOT received 18 bids. The bids were opened at 3:00 p.m. on April 29, 2004. The lowest bid was $5,185.76, submitted by Daniels Janitorial Service, including: $4,895.76 for "MONTHLY CLEANING - BUILDING 5000 - X 12 MONTHS," $200.00 for "MONTHLY CLEANING - BUILDING 5001 - X 12 MONTHS," and $5,186.76 identified as "TOTAL YEARLY AMOUNT BOTH BUILDINGS." The second lowest bid was $10,686.00, submitted by Jan-Pro Cleaning Systems, including: $9,971.00 for "MONTHLY CLEANING - BUILDING 5000 - X 12 MONTHS," $715.00 for "MONTHLY CLEANING - BUILDING 5001 - X 12 MONTHS," and $10, 686.00 identified as "TOTAL YEARLY AMOUNT BOTH BUILDINGS." The third lowest bid was $67,777.77, submitted by the Petitioner. The remainder of the bids ranged between $69,600.00 to as much as $201,464.64. At the time of the opening, Diane Warnock, a DOT District Contract Specialist and Purchasing Agent in charge of the bid opening, observed that two of the bids (the Daniels Janitorial Service and the Jan-Pro Cleaning Systems bids) appeared to be very low in relation to the other bids. Ms. Warnock believed that the two lowest bids submitted were likely set forth on a monthly basis rather than annual amount, and that the bidders had failed to extend the monthly charges to an annual cost. Ms. Warnock contacted David Callaway, a DOT Procurement Analyst with statewide contract responsibilities, to discuss her observations. Mr. Callaway advised Ms. Warnock that she could contact the two low bidders and ascertain whether the bids submitted reflected a monthly or an annual cost. Ms. Warnock separately contacted each of the individuals responsible for submitting the low bids and inquired as to whether the bids reflected a monthly cost or an annual cost. Ms. Warnock learned that each vendor had submitted a monthly bid amount. Ms. Warnock multiplied the monthly amounts submitted by the two vendors by 12 to arrive at an annual cost. On the bid tabulation form, Ms. Warnock included the bid amount submitted by each bidder. For the two bidders who submitted monthly cost information, Ms. Warnock included the monthly costs submitted and the annual cost figures she had calculated. Based on annual costs, the lowest vendor was Daniels Janitorial Service with an annual bid amount of $62,229.12. Section 13.2 of the ITB provides as follows: 13.2 RESPONSIVENESS OF BIDS Bids will not be considered if not received by the Department on or before the date and time specified as the due date for submission. All bids must be typed or printed in ink. A responsive bid is an offer to perform the scope of services called for in this Invitation to Bid in accordance with all requirements of this Invitation to Bid. Bids found to be non- responsive will not be considered. Bids may be rejected if found to be irregular or not in conformance with the requirements and instructions herein contained. A bid may be found to be irregular or non-responsive by reasons that include, but are not limited to, failure to utilize or complete prescribed forms, modifying the bid requirements, submitting conditional bids or incomplete bids, submitting indefinite or ambiguous bids, or executing forms or the bid sheet with improper and/or undated signatures. Section 13.4 of the ITB provides as follows: 13.4 WAIVERS The Department may waive minor informalities or irregularities in bids received where such is merely a matter of form and not substance, and the correction or waiver of which is not prejudicial to other bidders. Minor irregularities are defined as those that do not have an adverse effect on the Department's interest and does not effect the price of the bid by giving a bidder an advantage or benefit not enjoyed by other bidders.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Transportation enter a final order awarding the contract for ITB-DOT-04/05- 5002-PDW to Daniels Janitorial Service. DONE AND ENTERED this 25th day of August, 2004, in Tallahassee, Leon County, Florida. WILLIAM F. QUATTLEBAUM Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 25th day of August, 2004. COPIES FURNISHED: C. Denise Johnson, Esquire Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0450 Anthony Payne 1031 Eagles Forrest Drive Apopka, Florida 32712 James C. Myers, Clerk of Agency Proceedings Department of Transportation 605 Suwannee Street Haydon Burns Building, Mail Stop 58 Tallahassee, Florida 32399-0450 Pamela Leslie, General Counsel Department of Transportation 605 Suwannee Street Haydon Burns Building, Mail Stop 58 Tallahassee, Florida 32399-0450

Florida Laws (1) 120.57
# 7
THE URBAN GROUP vs DEPARTMENT OF TRANSPORTATION, 94-005967BID (1994)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Oct. 25, 1994 Number: 94-005967BID Latest Update: Feb. 14, 1995

Findings Of Fact The Department issued an invitation to bid (ITB) and solicited bids for district-wide miscellaneous property management maintenance services pursuant to ITB-DOT-94-95-4004. Kemp Services, Inc. (Kemp), submitted the lowest bid for the subject ITB. Petitioner, Urban Group, Inc., submitted the second lowest bid for the subject ITB. Section 1.1 of the ITB provided: Invitation The State of Florida Department of Transport- ation requests written bids from qualified firms to MAINTAIN RIGHT-OF-WAY STRUCTURES AND VACANT LOTS BY PROVIDING CLEAN-UP SERVICES, LAWN SERVICES, LANDSCAPE SERVICES, SECURING OF BUILDINGS, AND OTHER MISCELLANEOUS HANDYMAN AND SKILLED LABOR SERVICES. ALSO PROVIDE SERVICES FOR SIGN REMOVAL FOR STRUCTURES ILLEGALLY ON THE DEPARTMENT'S RIGHT-OF-WAY OR ILLEGALLY ON PRIVATE PROPERTY IN THE FOLLOWING FIVE COUNTY AREA: BROWARD, MARTIN, PALM BEACH, ST. LUCIE AND INDIAN RIVER COUNTIES. For the purpose of this document, the term "bidder" means the prime Consultant acting for itself and those individuals, partnerships, firms, or corporations comprising the bidder's team by joint venture or subcontract. The term "bid package" means the complete response of the bidder to the Invitation To Bid, including properly completed forms and supporting documentation. [Emphasis in text.] The services were to be provided on an as-needed basis for the term of the agreement, two years. Section 1.7.1 of the ITB provided: Qualifications 1.7.1 Bidders must meet the following minimum qualifications: BIDDERS MUST HAVE AT LEAST TWO YEARS EXPERIENCE PROVIDING AT LEAST TWO (2) OF THE SIX SERVICES OUTLINED IN THE SCOPE OF SERVICES IN EXHIBIT "A". BIDDERS MUST HAVE BEEN IN CONTINUOUS BUSINESS FOR THE PAST TWO (2) YEARS AND COMPLETE FORM "F" WITH THE INFORMATION REQUESTED REGARDING WORK EXPERIENCE AND REFERENCES. ALL REFERENCES WILL BE CHECKED. FAILURE TO PROVIDE FORM "F" AND THE WORK EXPERIENCE REQUESTED WILL CONSTITUTE A NON- RESPONSIVE BID. [Emphasis in text.] Section 1.7.4 of the ITB provided: Qualifications of Key Personnel Those individuals who will be directly involved in the project must have demonstrated experience in the areas delineated in the scope of work. Individuals whose qualifications are presented will be committed to the project for its duration unless otherwise accepted by the Department's Contract Manager. Where State of Florida registration or certification is deemed appropriate, a copy of the registration or certificate should be included in the bid package. Section 1.7.5 of the ITB provided: Authorizations and Licenses The Consultant must be authorized to do business in the State of Florida. Such authorization and/or licenses should be obtained by the bid due date and time, but in any case, will be required prior to award of the contract. For corporate authorization, contact: Florida Department of State Division of Corporations The Capitol Building Tallahassee, Florida 32399 (904)487-6052 Other than the provisions above, no other licensure or authorization to do business was required by the ITB. Section 1.8.2 of the ITB provided: Responsiveness of Bids All bids must be in writing. A responsive bid is an offer to perform the scope of services called for in this Invitation to Bid. Bids found to be non-responsive shall not be considered. Bids may be rejected if found to be irregular or not in conformance with the requirements and instructions herein contained. A bid may be found to be irregular or non-responsive by reasons, including, but not limited to, failure to utilize or complete prescribed forms, conditional bids, incomplete bids, indefinite or ambiguous bids, improper undated or unsealed signatures (where applicable). Section 1.8.4 of the ITB provided: Other Conditions Other conditions which may cause rejection of bids include evidence of collusion among bidders, obvious lack of experience or expertise to perform the required work, or failure to perform or meet financial obligations on previous contracts, or in the event an individual, firm, partnership, or corporation is on the United States Comptroller General's List of Ineligible Contractors for Federally Financed or Assisted Projects. Bids will be rejected if not delivered or received on or before the date and time specified as the due date for submission. Section 1.8.5 of the ITB provided: Waivers The Department may waive minor informalities or irregularities in bids received where such is merely a matter of form and not substance, and the correction or waiver of which is not prejudicial to other bidders. Minor irregular- ities are defined as those that will not have an adverse effect on the Department's interest and will not affect the price of the Bids by giving a bidder an advantage or benefit not enjoyed by other bidders. Section 1.18.1 of the ITB provided: Award of the Contract The Department intends to award a contract to the responsible and responsive bidder who bids the lowest cost as identified in Form "C", Bid Blank, attached hereto and made a part hereof. The ITB did not specify a minimum number of employees, vehicles or hours of service for a bidder to be deemed responsible or responsive. At all times material to this case, Kemp has been in continuous business for the past two (2) years, and completed form "F" with the information requested regarding work experience and references. The Department's agent, Mr. Gentile, checked with two of the references listed by Kemp to verify information relative to this bid requirement. At all times material to this case, Kemp had at least two years experience providing at least two (2) of the six services outlined in the scope of services. The Department's agent, Mr. Gentile, checked with two of the references listed by Kemp to verify information relative to this bid requirement. While Mr. Gentile was authorized to check with all references listed by Kemp, the failure to do so does not discount the information obtained from the sources that were checked. Kemp had an appropriate occupational license to perform work in the tricounty area, but did not have occupational licenses with the City of Hollywood or Broward County. At all times material to this case, Kemp maintained a warehouse to secure the equipment to be used such as lawnmowers, trimmers, and cleaning supplies/equipment. After the bid protest was filed, the Department verified that Kemp had used the warehouse as it claimed. No evidence to the contrary was presented. The mailing address Kemp listed on the first page of its bid response was 8637 S. Sutton Drive, Miramar, Florida. Mr. Faluade resides at that address. He listed that address for mail purposes. The business address for Kemp listed on the bid response was 6200 Johnson Street, Miramar, Florida. This address is a store-front facility with limited office equipment and furniture. Kemp maintains an office at this location but stores its equipment elsewhere as noted above. Kemp was the lowest responsive, responsible bid for ITB-DOT-94-95- 4004.

Recommendation Based on the foregoing, it is, hereby, RECOMMENDED: That the Department of Transportation enter a final order dismissing Petitioner's challenge to the award of ITB-DOT-94-95-4004 to Kemp Services, Inc. DONE AND RECOMMENDED this 14th day of February, 1995, in Tallahassee, Leon County, Florida. JOYOUS D. PARRISH Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of February, 1995. APPENDIX TO RECOMMENDED ORDER, CASE NO. 94-5967 Rulings on the proposed findings of fact submitted by the Petitioner: Paragraphs 1 through 4, 6, and 8 are accepted. With regard to paragraphs 5, 7, and 16 noting that the additional emphasis is not in the text and that the citations are incomplete (and perhaps misleading), they are accepted. Paragraph 9 is rejected as contrary to the weight of credible evidence. Paragraph 10 is rejected as contrary to the weight of credible evidence. Paragraph 11 is rejected as incomplete, and therefore, misleading. Corporate documents may have been filed on that date, however, the weight of the credible evidence established that Kemp had been in business the requisite amount of time. Paragraph 12 is rejected as incomplete, and therefore, misleading. The business conducted by the Kemp personnel continued regardless of the business entity structure that was used. Paragraph 13 is rejected as contrary to the weight of credible evidence. Paragraph 14 is rejected as contrary to the weight of credible evidence or irrelevant. Paragraph 15 is rejected as contrary to the weight of credible evidence. Paragraph 16 is rejected as contrary to the weight of credible evidence. Moreover, no credible evidence was presented to establish that Kemp did not provide services as described in the ITB or that it was not in business the requisite time. Paragraph 17 is rejected as incomplete, and therefore, misleading. The mailing address listed by Kemp was a residential address. Paragraph 18 is rejected as irrelevant. Paragraph 19 is rejected as contrary to the weight of credible evidence. Paragraph 20 is rejected as irrelevant. Kemp probably does not have a Leon County occupational license either. It did have an appropriate occupational license at all times material to this case. Rulings on the proposed findings of fact submitted by the Respondent: 1. Paragraphs 1 through 29 are accepted. COPIES FURNISHED: Thomas H. Duffy Assistant General Counsel Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0450 Mitchell B. Polay Mark H. Klein 750 S.E. Third Avenue Suite 205 Fort Lauderdale, Florida 33316 Thornton J. Williams General Counsel Department of Transportation 562 Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0450 Ben G. Watts, Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0450

# 8
LEE A. EVERHART AND COMPANY, INC. vs. DEPARTMENT OF CORRECTIONS, 83-001761 (1983)
Division of Administrative Hearings, Florida Number: 83-001761 Latest Update: May 02, 1990

Findings Of Fact On or about February 9, 1983, the State of Florida, Department of General Services, Division of Construction and Property Management, Bureau of Property Management ("DGS"), received a certification of need from the Department of Corrections ("DOC") requesting authority for DOC to advertise for competitive bids from private persons interested in providing leased office space needed to house DOC's Bureau of Industries. The Bureau of Industries was then located in leased space with leases which were scheduled to expire June 30, 1983. The Bureau of Industries has been located in DOC's central office area since its creation in 1957. The DOC central office includes the Secretary and Deputy Secretary; the Assistant Secretaries for Operations, Programs, Management, and Budget. All these officials, together with subsidiary bureaus, staff, and other subordinates are located in two adjacent buildings of the Winewood Office Complex on Blair Stone Road in Tallahassee. The prison industry program is under the supervision of the industries administrator who reports directly to the Assistant Secretary for Operations. DOC sought approval from DGS to enter into a lease for privately owned office space because of its perceived need to locate within walking distance of its central office. Programs administered by the Bureau of Industries work closely with other DOC personnel and functions located in the central office in the Winewood Office Complex. Moving any distance from the central office would create problems for the DOC mailing system and would require extra time spent traveling to and from the central office. Personnel in the Bureau of Industries utilize central office files, and confer often with staff located in the central office. Locating outside the general area of the central office would require additional expenses with regard to availability of vehicles, pick up of mail and supplies, and duplication of support services. Accordingly, DGS and DOC determined, and the record in this cause establishes, that it would not be in the state's best interest to require DOC to locate its Bureau of Industries program either in state-owned buildings in the Capitol Center, or in any area beyond walking distance of the central office location. On March 21 and 31, 1983, respectively, DOC published an advertisement in the Tallahassee Democrat inviting all interested persons to submit sealed bids at or before 2:00 p.m. on April 19, 1983, in accordance with the Invitation to Bid and Specifications prepared by DOC for the office space needed to house the Bureau of Industries. A portion of the bid specifications required that office space to be leased be located within a circle drawn on a city map of the City of Tallahassee, Florida, which could roughly be described as the southeastern portion of the city, in the vicinity of the Winewood Office Complex. There were four possible bidders in the area within the circle on the map attached to the bid specifications. Of these four possible bidders, two within the area actually submitted bids--Blairstone Center Partners and Washington Square, Ltd. One of the general provisions of the bid specifications provided as follows: The Department of Corrections reserves the right to reject any and all bids, waive any minor informality or technicality in bids received and to accept that bid deemed to be the lowest and best. . . At or before 11:00 a.m. on April 19, 1983, DOC received sealed bids from Petitioner and Intervenors in response to the aforesaid advertisement, and at 11:00 a.m. on April 19, 1983, DOC opened, tabulated, and published each of the bids. The bid submitted by Petitioner was not responsive to the requirements of the Invitation to Bid and Specifications because the property offered by Petitioner in its response was outside the area indicated on the map annexed to the Invitation to Bid. The bid submitted by Intervenor, Blairstone Center Partners, failed to offer the full services specified in paragraph six of DOC's Bid Submittal Form; failed to offer the exclusive parking specified in the paragraph seven of the Bid Submittal Form; failed to supply the photographs specified in paragraph ten of Respondent's Bid Submittal Form; and failed to supply the information specified in paragraphs one through eight of the Bid Submittal Form. Accordingly, the record in this cause fully establishes that the bids submitted by Petitioner and by Intervenors Blairstone Center Partners, failed to comply with the requirements of the Invitation to Bid and Bid Submittal Form, and that the deficiencies in the bids of Petitioner and Intervenor, Blairstone Center Partners, were so material as to require their rejection. The Invitation to Bid and Bid Submittal Form required that bidders offer for lease 2,683 square feet, plus or minus three percent. The bid submitted by Intervenor, Washington Square, Ltd., offered 2,797 square feet, which is approximately 34 square feet more than allowed in the Invitation to Bid. After this fact was discovered upon opening the bid, DOC personnel contacted a representative of Washington Square, Ltd., and advised the net square footage offered in the bid submitted by Washington Square, Ltd., exceeded the net square footage of space that DOC was authorized to lease and pay for under the Invitation to Bid. Washington Square, Ltd., subsequently agreed to modify its proposal by relieving DOC from any obligation to pay for the extra 34 square feet, and reducing the annual rental for the first year from $26,012.10 to $25,695.90, and for the second year from $27,576.60 to $27,243.18. The record in this cause does not establish any misconduct or collusion between Washington Square, Ltd., and DOC personnel obtaining this modification, nor does the record in this cause establish that any actual or prospective bidders suffered any competitive disadvantage as a result of this modification. The effect of Washington Square, Ltd.'s modification of its proposal rendered that proposal the only bid which was responsive to the Invitation to Bid. On August 18, 1983, Washington Square, Ltd., executed a deed to the property which was the subject matter of its bid to Ben Grace. Washington Square also executed an assignment of the proposed bid award to Grace.

Florida Laws (3) 120.57243.18255.25
# 9
PROCACCI FINANCIAL GROUP, LTD., AND PROCACCI COMMERCIAL REALTY, INC. vs DEPARTMENT OF LABOR AND EMPLOYMENT SECURITY, 92-002650BID (1992)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Apr. 28, 1992 Number: 92-002650BID Latest Update: Oct. 27, 1992

The Issue Whether Respondent's rejection of all bids for Lease No. 540:0920 was improper.

Findings Of Fact The Respondent published an invitation to bid seeking to lease approximately 9,907 net square feet of office space in Broward County (the Lease). There was no evidence of any irregularities in the preparation or the issuance of the invitation. The Petitioner, whose responsive bid was rejected by Respondent, timely and properly brought its protest and has standing to protest the Respondent's rejection of all bids for the Lease. Lynn Mobley was the statewide lease manager of the Respondent and had the responsibility to generally oversee the preparation of the bid package and the bid opening procedures. Barbara Lollie was a staff member under the supervision of Ms. Mobley and was in charge of the preparation of the request for bid proposals. Ms. Mobley's supervisor was a Ms. Barron. Five bids in response to the invitation to bid were duly received by Respondent. An evaluation committee chaired by Don Walker, Respondent's area administrator, was appointed to inspect the proposed properties and to evaluate the bids. The evaluation committee ranked the bids in the following order of preference: 1/ 1. In-Rel ($499,141.80) 2. Taft ($519,090.30) 3. Donlon ($541,119.90) 4. Procacci ($618,373.30) 5. Stirlingwood ($761,906.30) Thereafter the responses to the invitation were forwarded to Ms. Mobley's office for evaluation. Ms. Mobley's staff determined that the top two bids, those of In-Rel and Taft, were non-responsive. 2/ Ms. Mobley, who did not actively participate in the evaluation of the proposals, then advised Mr. Walker of that determination and advised him of two alternatives: to award the bid to the lowest responsive bidder or to reject all bids and re-advertise. The evaluation committee chaired by Mr. Walker had wanted to lease the property to either In-Rel or Taft. Mr. Walker told Ms. Mobley that he wanted to reject all bids and to re-advertise. Pursuant to the request for bids promulgated by the Respondent and Rule 13M-1.015, Florida Administrative Code, the Respondent reserved the right to reject any and all bid proposals for the Lease. The request for proposal of bids specifically stated: The Department reserves the right to reject any and all bid proposals for reasons which shall include but not be limited to the agency's budgetary constraints; waive any minor informality or technicality in bids, to accept that bid deemed to be the lowest and in the best interest of the State, and if necessary, to reinstate procedures for soliciting competitive proposals. Following the telephone conversation between Mr. Walker and Ms. Mobley, Ms. Mobley sent a letter dated March 23, 1992, to all bidders which notified each bidder that all bids had been rejected. That letter did not state the reasons for the rejection of all bids. Mr. Walker sent a memo on March 20, 1992, to Ms. Lollie recommending the rejection of all bids. Although this memo predated the rejection letter and was subsequently made available to Ms. Mobley, the memo was received by Ms. Mobley's office after the rejection letter had been sent. The memo gave no explication of Mr. Walker's reasons for wanting to reject all bids. The Department of General Services (DGS) published lease rate guidelines for Broward County to inform the Respondent of maximum acceptable lease rates. The purpose of these DGS guidelines was to advise the Respondent that proposed lease rates above the guidelines would be summarily rejected. At the time of obtaining bid proposals, the DGS lease rate guidelines were the only established guidelines which could be consulted by the Respondent. At no time did the Respondent calculate a pre-bid estimate of what the Respondent felt was an acceptable range of lease rates in order to be used in determining whether lease rates were too high. The Petitioner's bid, along with the other responsive bidders, were within the DGS lease rate guidelines. Mr. Walker made the request for re-bid after he learned that the bids of Taft and In-Rel were non-responsive. Mr. Walker's decision to recommend the rejection of all bids was based only on the information that the two top choices of the evaluation committee had been found to be non-responsive and on his desire to reopen the bid process in the hope of attracting more bidders. 3/ Mr. Walker wanted to modify the specifications of the invitation to bid in two regards. First, he wanted to amend the specifications to permit the leased premises to be in more than one building. Second, he wanted the geographical boundaries in which the leased premises could be located to be expanded to hopefully attract additional bidders. Mr. Walker believed that a re-bid would provide a wider range of buildings at comparable prices from which to choose and would give him an opportunity to make changes to the bid specifications. His decision to recommend the rejection of all bids was not based on a lease bid analysis or on lease rate guidelines. The recommendation was not dictated by budgetary considerations, but by his desire to shop the bid. It was Mr. Walker's understanding that at the end of his telephone conversation with Ms. Mobley that the decision to reject all bids had been made and that all bids would be rejected. Ms. Mobley made the decision to reject all bids pursuant to the recommendation of Mr. Walker after obtaining input from Ms. Lollie and Ms. Barron. Although Ms. Mobley had Ms. Lollie's analysis of the five bids, that analysis made no comparison of the rates contained in the bids with existing lease rates or the DGS guidelines. Ms. Mobley did not consult the DGS lease rate guidelines, although she was generally familiar with those guidelines, and she was unaware of any budgetary constraints that would dictate the rejection of all bids. When Ms. Mobley decided to reject all bids, she did not compare the bid proposals to the existing lease rates paid by the Respondent for leased office space in Broward County. The decision to reject all bids was not made on the advice of an attorney. Although Ms. Mobley testified that all bids on the Lease were rejected solely for price considerations, the evidence presented established that the decision to reject all bids was not based on price, price guidelines, or the Respondent's budgeting constraints. The greater weight of the evidence establishes that Ms. Mobley rejected all bids because that was the action recommended by Mr. Walker. Respondent's invitation to bid did not contain any lease rate guidelines that would notify prospective bidders of a lease rate ceiling. There was no significant difference in the lease rates between the Taft and In-Rel bids that were favored but non-responsive and the third lowest bidder, the Donlon bid, which was responsive but rejected. Mr. Walker conceded that the Donlon bid was not rejected because of price considerations. Mr. Walker was of the opinion that the Donlon bid was at an acceptable price. He did not testify that the Petitioner's bid was at an unacceptable price and he did not testify as to what, other than the DGS guidelines, would be the maximum acceptable price. The DGS Lease Guidelines applicable to the bid for the Lease were as follows: A full service Lease (including electricity) -- $17.84 a square foot. 4/ Lease without electricity -- $15.18 a square foot. The present rate for the existing lease which was to be replaced by the Lease was $16.60 a square foot; this rate did not include electricity. If electricity was factored in at $2.50 a square foot, which was a factor regularly used by DGS, the present lease rate would be approximately $18.00 a square foot. The three responsive bids to the invitation were lower than the present lease after factoring in electricity. Ms. Goodman was of the opinion that Respondent's budget with respect to the Lease would be based on lease rates already in existence and consequently, that the responsive bids received and rejected were within the budget guidelines. Respondent offered no evidence to controvert that opinion. There was no evidence that the decision to reject all bids was based on economic considerations. All lease rates submitted by the rejected bidders were under the ceiling set by the DGS lease guidelines of $17.84. The Respondent acted arbitrarily when it rejected all bids.

Recommendation Based upon the foregoing findings of fact and conclusion of law, it is hereby recommended that the Respondent accept and evaluate the responsive bids submitted for the Lease and determine the proper recipient for an award of the Lease. RECOMMENDED this 29th day of June, 1992, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1992.

Florida Laws (4) 120.57120.68255.25287.012