Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
WINKO-MATIC SIGNAL COMPANY vs. DEPARTMENT OF TRANSPORTATION, 84-002250 (1984)
Division of Administrative Hearings, Florida Number: 84-002250 Latest Update: Jan. 18, 1985

Findings Of Fact On March 1, 1984, Respondent gave notice to qualified contractors that it would receive sealed bids for State Project No. 72000-3541, referred to as Federal-Aid Project No. M 9041(10). This project involves the installation of a computerized traffic control system for the City of Jacksonville. In response to the opportunity to bid, the Department of Transportation received four bids. Petitioner, Winko-Matic Signal Company, was among the bidders. The other bidders were Georgia Electric Company, Traffic Control Devices, Inc., and Sperry Systems Management. The bids of Traffic Control Devices and Sperry Systems were rejected based upon an error in bid tabulations on the part of Traffic Control, a mistake on the quantities page, with the Sperry rejection being based upon a bid bond problem. Traffic Control had been the apparent low bidder with a bid of $1,964,115. Winko-Matic was the second apparent low bidder with a bid of $2,279,604.70. The Department of Transportation had estimated that the total cost of the Jacksonville project would be $ 2,024,680.61. Having discarded the bid of Traffic Control Devices, the Department of Transportation telegrammed Winko-Matic on April 4, 1984, advising Winko-Matic that it was the apparent low bidder for the Jacksonville project. Subsequently, the awards committee of the Department of Transportation met on April 18, 1984, and determined to reject all bids and re-advertise the job. In the course of this meeting the awards committee was told that there were erratic bids received on contract items, pointing to some perceived confusion among the contractors as to requirements of the contract. Discussion was also held on the possibility of establishing a pre-bid conference if the project was re advertised. The awards committee then voted to reject the bids on the basis that the apparent low bidder, Winko-Matic, had submitted a bid which-was 12.6 percent over the Department's estimate, instead of being within 7 percent of the Department of Transportation's pre-bid estimate, a point above which the Department of Transportation in its non-rule policy would call to question to the acceptability of the apparent low bid. In addition to deciding to reject all bids and re-advertise, it was determined that a pre-bid conference should be scheduled at least 30 days prior to the bid-letting date. Winko-Matic was advised that the Department of Transportation's decision to reject all bids by correspondence of May 4, 1984, in which it was indicated that all bids had been rejected based upon the fact that they were too high. In response to this notice of rejection, Winko-Matic, effective May 17, 1984, filed a written notice of protest. The case was subsequently referred to the Division of Administrative Hearings on June 20, 1984, and a final hearing date was established by Notice of Hearing of July 5, 1984. The hearing date in this cause was September 12, 1984. The Jacksonville project in question requires the utilization of what has been referred to "UTCS Enhanced" software. This software package is unique and has only been used in a limited number of locations within the country. Those locations are Los Angeles, California; San Diego, California; Broward County, Florida; and Birmingham, Alabama. Another unique feature within the project design is the use of an associated coaxial computer sys gem. Given the unique nature of this project and the fact that the Department of Transportation had never advertised for bids related to UTCS software, Department of Transportation obtained assistance from a consulting firm, Harland, Bartholomew & Associates. In fulfilling its function Harland gave estimates to include an estimate related to the projected cost of the software, Item 681-102. The Harland estimate for the overall project was $2,143,130 including a $100,000 estimate for the software system. That estimate relating to the software was subsequently adjusted by the Department of Transportation to depict a cost of $13,780. The Department of Transportation estimate was based upon information within its computer related to a system unlike the enhanced software contemplated by the plans and specifications. In other words, the stored information in the Department of Transportation computer was not the same as contemplated by the plans and specifications in the Jacksonville project. Moreover, the initial estimate of Harland was based upon the idea of an extended software system, as opposed to an enhanced software system. Winko-Matic had bid $389,500 for the software in Item 681-102. That estimate was premised upon figures obtained from JHK and Associates, the group which Winko-Matic intended to use as its subcontractor for the enhanced software portion of the project. JHK developed the software and was responsible for systems integration of the Los Angeles, California, project, one of the locations in which UTCS enhanced software has been utilized. JHK premised its estimate for the software hare upon experience in Los Angeles and an evaluation of the tasks to be performed related to the enhanced software. This included general software development activities, hardware innovation, installation costs during the period of acceptance and testing, and the preparation of data base. The JHK bid price was $339,500. Another $50,000 was added to that price related to what the Petitioner describes as its management costs for that item. By June 20, 1984, when a further meeting was held by the awards committee on the subject of the Jacksonville project, it was concluded that the estimate made by the Department of Transportation of $13,780 was not correct, on the topic of the enhanced software. A more reasonable estimate, according to the information imparted in this session, would be $200,000 for enhanced software as called for in this project, with a $100,000 amount being a reasonable estimate had they chosen to use extended software. Adjusting the initial price related to the UTCS enhanced software to reflect a corrected estimate of the Department of Transportation in its original advertised bid, that estimate becomes $2,210,900.61 and its consultant Harland's estimate becomes $2,243,130. With this adjustment, the differential in the estimate made by the Department of Transportation and the Petitioner approaches 3 percent and not the 12.6 percent originally found. The 3 percent is below the threshold of 7 percent used as the policy for determining whether a bid might be rejected as being far beyond the acceptable limits set forth in the Department of Transportation's estimate. In the aforementioned June 20, 1984, awards committee meeting, the Department of Transportation continued to hold the opinion that all bids in the Jacksonville project should be rejected and the matter re-advertised. Although the problem pertaining to the estimate of the cost of the enhanced software package had been addressed, the committee continued to feel that the prices received in the bid letting were erratic Reference was also made to revisions or modifications to the project plan which would be offered if the matter were re- advertised. It was also pointed out that the Federal Highway Administration would concur in the Department's decision to reject all bids and would accept modifications. The awards committee again voted to reject the bids. The matter was again considered by the awards committee on August 31, 1984. On that occasion, it was pointed out that the revisions contemplated by the Department of Transportation, should the matter be re-advertised, would not affect in a substantial way the cost estimate for the project with the exception of Item 680-101, the system control equipment (CPU), which would promote a lower price for the project. The committee determined in the August, 1984, meeting to reject all bids and re-advertise. While the initial notice of rejection of May 4, 1984, had suggested the basis for rejection as being the fact that Petitioner's bid far exceeded the 7 percent allowance for price above the Department of Transportation's estimate of costs, the meetings of the awards committee and the suggestion of the Respondent in the course of the final hearing in this case indicated that there were other reasons for the decision to reject. Those Were: (a) an apparent lack of clarity among bidders regarding specifications for the Jacksonville job, (b) the desire of the Respondent to revise specifications on the Jacksonville project; and (c) a lack of sufficient competition in the bids. In connection with the first of the additional reasons Respondent suggests that variations within the bid responses related to particular line items within the specifications point out a lack of clarity in the project's specifications or confusion by bidders related to those specifications. Respondent did not bring forth any of the bidders who might speak to the matter of possible confusion or misunderstanding concerning some of the bid items. By contrast, the Petitioner's president; the president of JHK & Associates and James Robinson, Harland's project manager for the Jacksonville job, did not find the specifications in the original documents to be confusing. In addition, the testimony of those individuals established the fact that bid variations related to particular line items are not extraordinary and do not establish any apparent confusion by the bidders as to the requirements of those line items. In effect, what the differentials demonstrate are variations related to the manufacture or in-house capabilities of the bidders and an effort to allocate discretionary costs in various places as to line items. Moreover, they might indicate last- minute adjustments in the bid quote prior to the opening and a possible effort by a contractor to enter into a new job market. Finally, they demonstrate offsetting which is the allocation of item prices by a contractor to maximize profits. To do this, a contractor submits high bids on items representing quantities which the contractor feels will increase after the contract is awarded and submits low bids on items representing quantities which are not likely to change. In summary, while the Department of Transportation in its presentation expressed some concern about the variations in the pricing in the bid quotations offered by the respective bidders in this project, its suspicions on the question of the possible clarity of its specifications were not confirmed and are not convincing. On the topic of revisions which the Department of Transportation would offer if the matter were re-advertised, with one exception those matters appear to be items that could be attended through change orders or supplemental agreements. They are not matters which necessarily must be addressed through a rejection of all bids and a re-advertising of the project. The lone exception to this is the possibility that the Department of Transportation may not be able to protect its proprietary rights in the enhanced software which is being developed for the project, under the terms of the present bid documents. Given that uncertainty, the Respondent would wish to re-advertise the project and make certain that its proprietary interests are protected. Finally, Respondent has alluded to the fact that the Jacksonville project should be re-advertised in view of the lack of competition in the initial letting. Only four bidders expressed an interest in this project at the time of the first letting. Of those, two bidders were found to be responsive. While this is a low number of bidders, there does not appear to be any agency practice on the part of' the Department of Transportation to the effect that this number of bidders would not be accepted. Moreover, no indication has been given that should the matter be re-advertised a greater number of bidders would express an interest than was the case in the first letting. Consequently, this reason for bid rejection is not acceptable. If Respondent did not reject the bids and re-advertise the project, Winko-Matic would be the successful bidder in the Jacksonville project.

Florida Laws (3) 120.53120.57337.11
# 1
NAPLES BUSINESS EQUIPMENT AND SYSTEMS, INC. vs. LEE COUNTY SCHOOL BOARD, 88-000690BID (1988)
Division of Administrative Hearings, Florida Number: 88-000690BID Latest Update: Mar. 30, 1988

The Issue The first issue to be determined is whether the BOARD can reject all bids, with or without cause. The second issue is to determine if the BOARD is required to have cause, was there a sufficient basis for the rejection of all bids in Bid NO. 3996?

Findings Of Fact On December 14, 1987, the BOARD sent invitations to bid to a list of approved vendors in Bid NO. 3996. The purpose of the invitation was to obtain the lowest responsible bid on a purchase of one hundred and fifty typewriters. The bids were to be submitted prior to January 11, 1988 at 2:00 P.M.. They were opened by the BOARD on the same day. OFFICE did not receive an invitation to bid despite its request to be placed on the approved vendor's list in November of 1987. When OFFICE learned of the outstanding invitation to bid, its representative, Mr. Richard Foss, went to the BOARD's Purchasing Department and requested a bid package. The bid documents given to OFFICE mistakenly gave January 14, 1988 at 2:00 P.M. as the deadline for the bid submission. Because of the later date given by the BOARD to OFFICE, the company's bid was received after the opening of the bids. When the results of the bidding were made known at the public bid opening, NAPLES bid was the lowest received. On January 14, 1988, after 10:42 A.M., it was discovered by the BOARD that OFFICE's bid price was lower than the price submitted by NAPLES. At this time, NAPLES bid had not yet been accepted by the BOARD, and no formal announcement had been made awarding the contract to NAPLES. During the BOARD's Purchasing Department's bid analysis, a request was made to reject all bids in Bid NO. 3996. The reason given by Purchasing for the request for rejection was that the specifications were being revised. The bids were rejected on the same date. The written reason sent to the vendors on January 14, 1988 for the bid rejection was that one vendor had been given an incorrect opening date. Attached to the written notice to the vendors was a new bid invitation for Bid NO. 4013. The BOARD explained its mistake was unfair to the one vendor. A new bid opening date was given of February 1, 1988. On January 14, 1988, in addition to the required bid documents, OFFICE submitted a letter which listed additional offerings or incentives that OFFICE would give the BOARD if OFFICE was awarded the contract. These additional purchasing incentives were: wall charts and teacher/student manuals for each typing classroom in the county. OFFICE also informed the BOARD that one of the BOARD's own service personnel was already trained in the servicing of Swintec typewriters. The bid submitted by OFFICE did not meet either the weight or the print wheel specifications as set forth in Bid NO. 3996. The specifications as written in Bid NO. 3996 were not written to eliminate all other typewriters but the Brothers 511-11. Weight specifications required were below the Brother's minimum weight, and at least two other manufacturers provide protected drop-in cassette print wheels in electronic typewriters. The Invitation to Bid contained specific provisions which encouraged the bidding of typewriters other than the Brother 511-11, and set up procedures under which other typewriters, which substantially meet the specifications, could be reviewed on their merits. NAPLES was the lowest responsible bidder for the electronic typewriter contract in the prior school year. The BOARD had rejected all bids at that time because of the decision to consider a different brand of typewriter once bids were opened. A notice of protest was filed by NAPLES, and the BOARD agreed to honor NAPLES bid and award the company the contract. The BOARD revised its bid specifications from last year prior to its solicitations for bids in Bid NO. 3996. The protected drop-in cassette print wheel and the weight requirements were two new technical specifications. During the hearing, the BOARD was unable to determine whether the weight factor or the protected drop-in cassette print wheel requirement will continue to be included in future revisions of the specifications.

Recommendation Based on the foregoing, it is RECOMMENDED: That the BOARD reject the bid submitted by OFFICE as it was nonconforming and sought an advantage not enjoyed by the other bidders. Reinstate the bids which were rejected in Bid NO. 3996, consider the bids, and make an award of the contract to NAPLES. DONE and ENTERED this 30th day of March, 1988, in Tallahassee, Florida. VERONICA D. DONNELLY Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of March, 1988. COPIES FURNISHED: Stephen Emens, President Naples Business Equipment and Systems, Inc. 859 4th Avenue South Naples, Florida 33940 Harry A. Blair, Esquire 2138-40 Hoople Street Ft. Myers, Florida 33901 Richard Foss, Typewriter Sales Manager 8A-Del Prado Boulevard Cape Coral, Florida 33904 Karl Engel, Superintendent Lee County Public Schools The School Board of Lee County 2055 Central Avenue Fort Myers, Florida 33901

Florida Laws (2) 120.53120.57
# 2
GUIDING LIGHT ENTERPRISE, INC. vs DEPARTMENT OF TRANSPORTATION, 04-002163BID (2004)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Jun. 21, 2004 Number: 04-002163BID Latest Update: Sep. 17, 2004

The Issue The issue in this case is whether the Department of Transportation's proposed award of a contract to Daniels Janitorial Service is contrary to the agency's governing statutes, the agency's rules or policies, or the specifications of the Invitation to Bid (ITB).

Findings Of Fact In April 2004, DOT issued ITB-DOT-04/05-5002-PDW (the ITB) seeking to contract for janitorial services at two state office buildings in DeLand, Florida. The ITB included a "bid blank," upon which vendors were directed to submit their cost proposals. The bid blank was titled "MONTHLY JANITORIAL SERVICES PER SCOPE OF SERVICES." The bid blank included three spaces where each bidder was to provide cost information. The three spaces were titled as follows: "MONTHLY CLEANING - BUILDING 5000 - X 12 MONTHS," "MONTHLY CLEANING - BUILDING 5001 - X 12 MONTHS," and "TOTAL YEARLY AMOUNT BOTH BUILDINGS." In response to the ITB, DOT received 18 bids. The bids were opened at 3:00 p.m. on April 29, 2004. The lowest bid was $5,185.76, submitted by Daniels Janitorial Service, including: $4,895.76 for "MONTHLY CLEANING - BUILDING 5000 - X 12 MONTHS," $200.00 for "MONTHLY CLEANING - BUILDING 5001 - X 12 MONTHS," and $5,186.76 identified as "TOTAL YEARLY AMOUNT BOTH BUILDINGS." The second lowest bid was $10,686.00, submitted by Jan-Pro Cleaning Systems, including: $9,971.00 for "MONTHLY CLEANING - BUILDING 5000 - X 12 MONTHS," $715.00 for "MONTHLY CLEANING - BUILDING 5001 - X 12 MONTHS," and $10, 686.00 identified as "TOTAL YEARLY AMOUNT BOTH BUILDINGS." The third lowest bid was $67,777.77, submitted by the Petitioner. The remainder of the bids ranged between $69,600.00 to as much as $201,464.64. At the time of the opening, Diane Warnock, a DOT District Contract Specialist and Purchasing Agent in charge of the bid opening, observed that two of the bids (the Daniels Janitorial Service and the Jan-Pro Cleaning Systems bids) appeared to be very low in relation to the other bids. Ms. Warnock believed that the two lowest bids submitted were likely set forth on a monthly basis rather than annual amount, and that the bidders had failed to extend the monthly charges to an annual cost. Ms. Warnock contacted David Callaway, a DOT Procurement Analyst with statewide contract responsibilities, to discuss her observations. Mr. Callaway advised Ms. Warnock that she could contact the two low bidders and ascertain whether the bids submitted reflected a monthly or an annual cost. Ms. Warnock separately contacted each of the individuals responsible for submitting the low bids and inquired as to whether the bids reflected a monthly cost or an annual cost. Ms. Warnock learned that each vendor had submitted a monthly bid amount. Ms. Warnock multiplied the monthly amounts submitted by the two vendors by 12 to arrive at an annual cost. On the bid tabulation form, Ms. Warnock included the bid amount submitted by each bidder. For the two bidders who submitted monthly cost information, Ms. Warnock included the monthly costs submitted and the annual cost figures she had calculated. Based on annual costs, the lowest vendor was Daniels Janitorial Service with an annual bid amount of $62,229.12. Section 13.2 of the ITB provides as follows: 13.2 RESPONSIVENESS OF BIDS Bids will not be considered if not received by the Department on or before the date and time specified as the due date for submission. All bids must be typed or printed in ink. A responsive bid is an offer to perform the scope of services called for in this Invitation to Bid in accordance with all requirements of this Invitation to Bid. Bids found to be non- responsive will not be considered. Bids may be rejected if found to be irregular or not in conformance with the requirements and instructions herein contained. A bid may be found to be irregular or non-responsive by reasons that include, but are not limited to, failure to utilize or complete prescribed forms, modifying the bid requirements, submitting conditional bids or incomplete bids, submitting indefinite or ambiguous bids, or executing forms or the bid sheet with improper and/or undated signatures. Section 13.4 of the ITB provides as follows: 13.4 WAIVERS The Department may waive minor informalities or irregularities in bids received where such is merely a matter of form and not substance, and the correction or waiver of which is not prejudicial to other bidders. Minor irregularities are defined as those that do not have an adverse effect on the Department's interest and does not effect the price of the bid by giving a bidder an advantage or benefit not enjoyed by other bidders.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Transportation enter a final order awarding the contract for ITB-DOT-04/05- 5002-PDW to Daniels Janitorial Service. DONE AND ENTERED this 25th day of August, 2004, in Tallahassee, Leon County, Florida. WILLIAM F. QUATTLEBAUM Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 25th day of August, 2004. COPIES FURNISHED: C. Denise Johnson, Esquire Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0450 Anthony Payne 1031 Eagles Forrest Drive Apopka, Florida 32712 James C. Myers, Clerk of Agency Proceedings Department of Transportation 605 Suwannee Street Haydon Burns Building, Mail Stop 58 Tallahassee, Florida 32399-0450 Pamela Leslie, General Counsel Department of Transportation 605 Suwannee Street Haydon Burns Building, Mail Stop 58 Tallahassee, Florida 32399-0450

Florida Laws (1) 120.57
# 3
HURST AWNING COMPANY, INC. vs DEPARTMENT OF TRANSPORTATION, 94-002297BID (1994)
Division of Administrative Hearings, Florida Filed:Miami, Florida Apr. 27, 1994 Number: 94-002297BID Latest Update: Jun. 24, 1994

Findings Of Fact Based upon the oral and documentary evidence adduced at the final hearing and the entire record in this proceeding, the following findings of fact are made: In January of 1994, FDOT issued an Invitation to Bid ("ITB") for contracts FE2494Z1 and FE2494Z2 to provide storm shutters for the FDOT facilities in Zones 1 and 2 of the Florida Turnpike. The ITB was entitled "Storm Shutters, Removable, Manufacture, Furnish and Install." Prospective bidders for the contracts were provided with a packet which included General Conditions, Special Conditions, Specifications and General Special Provisions. The General Conditions set forth the procedures for submitting and opening the bids. The Specifications called for custom-sized removable storm shutters and detailed the materials and installation procedures that were required. The bid package contained the following pertinent language in the Special Conditions, Section 1.0, entitled "Description", and in the Specifications, Section 1.0, entitled "Scope of Work": Work under this contract consists of providing all labor, materials, equipment, tools and incidentals necessary to manufacture, furnish and install galvanized steel storm panels and accessories for all of Zone 1 & Zone 2 buildings and locations as identified in the building listing listings document, see Exhibit "A" Zone 1 & Exhibit "A" Zone 2. The bid package contained the following pertinent language in Special Conditions Section 8.1, entitled "Required Documents": Bidders are required to complete and return the State of Florida "Invitation to Bid" form as well as the bid sheet(s). These forms must be signed by a representative who is authorized to contractually bind the bidder. All bid sheets and the "Invitation to Bid" form must be executed and submitted in a sealed envelope. At a mandatory pre-bid conference on February 17, 1994, the Department's representatives were available to answer questions regarding the bid package. During the pre-bid conference, John Vecchio of the Department orally advised the prospective bidders that they should return the whole bid package, including the specifications, when they submitted their bid. No written amendment to this effect was issued. The bids were opened on March 3, 1994 in Fort Lauderdale. Bids were received for each contract from at least three bidders, including Accurate and Hurst. The apparent low bidder for both contracts was Broward Hurricane Panel Co. ("Broward"). Prior to the bids being posted on March 28, 1994, Broward's bid was determined to be nonresponsive and Broward was therefore disqualified. After Broward was disqualified, Accurate was the apparent low qualified bidder for Zone 2 and Hurst was the apparent low qualified bidder for Zone 1. Hurst's bid for the contract for Zone 2 was $85,000. Its bid for the Contract for Zone 1 was $36,000. Accurate's bids for the contracts were $84,854.82 and $36,287.16, respectively. Hurst was awarded the contract for Zone 1 and that decision has not been challenged. At the same time the Department announced the award of the Contract for Zone 1 to Hurst, the Department announced its intent to award the contract for Zone 2 to Accurate. Hurst timely filed a notice of protest and a formal written protest of the proposed award of the contract for Zone 2 to Accurate. Initially, FDOT raised as a defense that Hurst had not posted a protest bond as required by Section 287.042(2)(c), Florida Statutes. At the hearing in this matter, FDOT conceded that Hurst had subsequently posted a protest bond which had been accepted by FDOT. Hurst contends that Accurate's bid should have been deemed nonresponsive because Accurate does not have the ability to "manufacture" the specified product in its own facility. The 2 inch corrugated shutter required by the ITB has to be shaped on a special type of machine that rolls, presses and forms the metal. Hurst owns and maintains at its Opa-Locka facility a rolling mill capable of forming the panels to the bid specifications. Accurate is in the business of supplying the types of products sought by the ITB in this case. However, Accurate does not own the kind of machine necessary to shape the metal. The evidence established that for many years, Accurate has had a continuing business relationship with a local subcontractor, Shutter Express, that rolls, presses and forms raw material supplied by Accurate in accordance with Accurate's specifications. Shutter Express has the capability of fabricating shutters with a 2 inch corrugation in accordance with the ITB. Accurate is equipped to attach the headers and sills, drill the necessary holes, complete the assembly and install the final product. The ITB in this case did not preclude subcontracting any or all of the work specified. While the description of the work in the ITB includes the term "manufacture", this reference should not be read to mean that only those companies that were able to fabricate the entire product at their own facility could properly respond to the ITB. There is no logical justification for such a narrow interpretation. Only a few companies have the ability to completely fabricate the shutters on their own property. At the prebid conference, there was discussion amongst the prospective bidders about subcontracting the fabrication work and the FDOT representatives did not raise any objections to such an arrangement. It was widely understood by the parties present at the pre-bid conference that the Department was not interpreting the ITB in the restrictive manner now urged by Hurst. Such a reading of the ITB would have precluded from the bidding process a number of companies such as Accurate that routinely supply and install shutters. Hurst also contends that the bid proposal submitted by Accurate should be deemed nonresponsive because Accurate failed to include the entire ITB with its proposal in accordance with the oral instructions at the pre-bid conference. Hurst's proposals included the entire ITB. As discussed below, Accurate's proposal did not include the entire ITB. FDOT determined that all essential pages were included in Accurate's response and the evidence did not establish that this conclusion was arbitrary, capricious or fraudulent. Paragraph 6 of the General Conditions of the ITB provided: ADDITIONAL TERMS AND CONDITIONS: No additional terms and conditions included with the bid response shall be evaluated or considered and any and all such additional terms and conditions shall have no force and affect and are inapplicable to the bid. As noted above, at the prebid conference held on February 17, 1994, an FDOT employee told all prospective bidders to return the entire bid package when making their submittals. This request that the entire bid package be returned was simply meant as a protection for the bidder to ensure that all the necessary documents referenced in Section 8.1 of the Specifications were submitted. Other than those documents referenced in Section 8.1 of the Specifications, FDOT had no interest in having the remaining portion of the ITB submitted with a proposal. Accurate's submittal contained every document required by Section 8.1 of the Specifications. Accurate's proposal did not contain pages 3 through 12, 14, 15 and 17 through 20 of the ITB, but did include pages 1 and 2, 13, 16, 21 and 22 along with a signed Form PUR 7068 and a signed acknowledgment of Addendum In other words, the submittal contained a signed and completed Bidder Acknowledgment, completed Bid Price Forms for Zones 1 and 2, a signed copy of Addendum #1, a completed copy of the Ordering Instructions, and a signed, but not notarized, statement regarding public entity crimes. 1/ In addition to the "REQUIRED DOCUMENTS," set forth in Section 8.1 of the Specifications and quoted in Findings of Fact 6 above, the ITB included Section 8.2, "PUBLIC ENTITY CRIMES STATEMENT" which provides: Any person submitting a bid or proposal in response to this invitation should execute the enclosed form PUR 7068, SWORN STATEMENT UNDER SECTION 287.133(A), FLORIDA STATUTES, ON PUBLIC ENTITY CRIMES, including proper check(s) provided, and submit it with the bid/proposal or within 72 hours of the bid opening. Page 7 of the ITB provided in pertinent part: 10.0 BID PREFERENCE IDENTICAL TIE BIDS - Preference shall be given to businesses with drug-free workplace programs. Whenever two or more bids which are equal with respect to price, quality and service are received by the State or by any political subdivision for the procurement of commodities or contractual services, a bid received from a business that certifies that it had implemented a drug-free workplace program shall be given preference in the award process. . . . Accurate's proposal did not include a certification that it was a drug-free workplace in accordance with this provision. However, such a certification is only used by the Department as a tie-breaker. In other words, in the event of identical bids, any firm with a drug-free workplace would get preference. Since there were no tied bids in this case, certification was totally irrelevant. When the bids were opened, Mary Bailey, the contracts administrator for the Department, noticed that Accurate's submittal was thinner than the others and asked Accurate's representative, Richard Johnson, about the remaining pages. Mr. Johnson replied that the other pages were in his truck and offered to retrieve them. Ms. Bailey told him there was no need to do so. Section 10 of the General Conditions in the bid package provides as follows: As the best interest of the State may require, the right is reserved...to reject any and all bids or waive any minor irregularity or technicality in bids received... It does not appear that Accurate has obtained any competitive advantage as a result of its failure to include the entire ITB with its bid proposals. Even if the oral instructions at the pre-bid conference are deemed to have modified the ITB so that the entire bid package should have been submitted, Accurate's failure to include the entire ITB with its response should be considered a minor technicality, pursuant to Section 10 of the General Conditions cited above, that can and should be waived in evaluating the responsiveness of the bid. Similarly, the failure to have the Form PUR 7068 notarized may have rendered Accurate's bid proposals incomplete, but not necessarily nonresponsive. This oversight can be easily corrected without giving Accurate a competitive advantage.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered finding the bid submitted by Accurate to be responsive and dismissing the challenge filed by Hurst. DONE and ENTERED this 24th day of June 1994, at Tallahassee, Florida. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of June 1994.

Florida Laws (8) 120.53120.57287.042287.087287.133287.16337.02337.11 Florida Administrative Code (2) 60A-1.00160A-1.002
# 4
THE URBAN GROUP vs DEPARTMENT OF TRANSPORTATION, 94-005967BID (1994)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Oct. 25, 1994 Number: 94-005967BID Latest Update: Feb. 14, 1995

Findings Of Fact The Department issued an invitation to bid (ITB) and solicited bids for district-wide miscellaneous property management maintenance services pursuant to ITB-DOT-94-95-4004. Kemp Services, Inc. (Kemp), submitted the lowest bid for the subject ITB. Petitioner, Urban Group, Inc., submitted the second lowest bid for the subject ITB. Section 1.1 of the ITB provided: Invitation The State of Florida Department of Transport- ation requests written bids from qualified firms to MAINTAIN RIGHT-OF-WAY STRUCTURES AND VACANT LOTS BY PROVIDING CLEAN-UP SERVICES, LAWN SERVICES, LANDSCAPE SERVICES, SECURING OF BUILDINGS, AND OTHER MISCELLANEOUS HANDYMAN AND SKILLED LABOR SERVICES. ALSO PROVIDE SERVICES FOR SIGN REMOVAL FOR STRUCTURES ILLEGALLY ON THE DEPARTMENT'S RIGHT-OF-WAY OR ILLEGALLY ON PRIVATE PROPERTY IN THE FOLLOWING FIVE COUNTY AREA: BROWARD, MARTIN, PALM BEACH, ST. LUCIE AND INDIAN RIVER COUNTIES. For the purpose of this document, the term "bidder" means the prime Consultant acting for itself and those individuals, partnerships, firms, or corporations comprising the bidder's team by joint venture or subcontract. The term "bid package" means the complete response of the bidder to the Invitation To Bid, including properly completed forms and supporting documentation. [Emphasis in text.] The services were to be provided on an as-needed basis for the term of the agreement, two years. Section 1.7.1 of the ITB provided: Qualifications 1.7.1 Bidders must meet the following minimum qualifications: BIDDERS MUST HAVE AT LEAST TWO YEARS EXPERIENCE PROVIDING AT LEAST TWO (2) OF THE SIX SERVICES OUTLINED IN THE SCOPE OF SERVICES IN EXHIBIT "A". BIDDERS MUST HAVE BEEN IN CONTINUOUS BUSINESS FOR THE PAST TWO (2) YEARS AND COMPLETE FORM "F" WITH THE INFORMATION REQUESTED REGARDING WORK EXPERIENCE AND REFERENCES. ALL REFERENCES WILL BE CHECKED. FAILURE TO PROVIDE FORM "F" AND THE WORK EXPERIENCE REQUESTED WILL CONSTITUTE A NON- RESPONSIVE BID. [Emphasis in text.] Section 1.7.4 of the ITB provided: Qualifications of Key Personnel Those individuals who will be directly involved in the project must have demonstrated experience in the areas delineated in the scope of work. Individuals whose qualifications are presented will be committed to the project for its duration unless otherwise accepted by the Department's Contract Manager. Where State of Florida registration or certification is deemed appropriate, a copy of the registration or certificate should be included in the bid package. Section 1.7.5 of the ITB provided: Authorizations and Licenses The Consultant must be authorized to do business in the State of Florida. Such authorization and/or licenses should be obtained by the bid due date and time, but in any case, will be required prior to award of the contract. For corporate authorization, contact: Florida Department of State Division of Corporations The Capitol Building Tallahassee, Florida 32399 (904)487-6052 Other than the provisions above, no other licensure or authorization to do business was required by the ITB. Section 1.8.2 of the ITB provided: Responsiveness of Bids All bids must be in writing. A responsive bid is an offer to perform the scope of services called for in this Invitation to Bid. Bids found to be non-responsive shall not be considered. Bids may be rejected if found to be irregular or not in conformance with the requirements and instructions herein contained. A bid may be found to be irregular or non-responsive by reasons, including, but not limited to, failure to utilize or complete prescribed forms, conditional bids, incomplete bids, indefinite or ambiguous bids, improper undated or unsealed signatures (where applicable). Section 1.8.4 of the ITB provided: Other Conditions Other conditions which may cause rejection of bids include evidence of collusion among bidders, obvious lack of experience or expertise to perform the required work, or failure to perform or meet financial obligations on previous contracts, or in the event an individual, firm, partnership, or corporation is on the United States Comptroller General's List of Ineligible Contractors for Federally Financed or Assisted Projects. Bids will be rejected if not delivered or received on or before the date and time specified as the due date for submission. Section 1.8.5 of the ITB provided: Waivers The Department may waive minor informalities or irregularities in bids received where such is merely a matter of form and not substance, and the correction or waiver of which is not prejudicial to other bidders. Minor irregular- ities are defined as those that will not have an adverse effect on the Department's interest and will not affect the price of the Bids by giving a bidder an advantage or benefit not enjoyed by other bidders. Section 1.18.1 of the ITB provided: Award of the Contract The Department intends to award a contract to the responsible and responsive bidder who bids the lowest cost as identified in Form "C", Bid Blank, attached hereto and made a part hereof. The ITB did not specify a minimum number of employees, vehicles or hours of service for a bidder to be deemed responsible or responsive. At all times material to this case, Kemp has been in continuous business for the past two (2) years, and completed form "F" with the information requested regarding work experience and references. The Department's agent, Mr. Gentile, checked with two of the references listed by Kemp to verify information relative to this bid requirement. At all times material to this case, Kemp had at least two years experience providing at least two (2) of the six services outlined in the scope of services. The Department's agent, Mr. Gentile, checked with two of the references listed by Kemp to verify information relative to this bid requirement. While Mr. Gentile was authorized to check with all references listed by Kemp, the failure to do so does not discount the information obtained from the sources that were checked. Kemp had an appropriate occupational license to perform work in the tricounty area, but did not have occupational licenses with the City of Hollywood or Broward County. At all times material to this case, Kemp maintained a warehouse to secure the equipment to be used such as lawnmowers, trimmers, and cleaning supplies/equipment. After the bid protest was filed, the Department verified that Kemp had used the warehouse as it claimed. No evidence to the contrary was presented. The mailing address Kemp listed on the first page of its bid response was 8637 S. Sutton Drive, Miramar, Florida. Mr. Faluade resides at that address. He listed that address for mail purposes. The business address for Kemp listed on the bid response was 6200 Johnson Street, Miramar, Florida. This address is a store-front facility with limited office equipment and furniture. Kemp maintains an office at this location but stores its equipment elsewhere as noted above. Kemp was the lowest responsive, responsible bid for ITB-DOT-94-95- 4004.

Recommendation Based on the foregoing, it is, hereby, RECOMMENDED: That the Department of Transportation enter a final order dismissing Petitioner's challenge to the award of ITB-DOT-94-95-4004 to Kemp Services, Inc. DONE AND RECOMMENDED this 14th day of February, 1995, in Tallahassee, Leon County, Florida. JOYOUS D. PARRISH Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of February, 1995. APPENDIX TO RECOMMENDED ORDER, CASE NO. 94-5967 Rulings on the proposed findings of fact submitted by the Petitioner: Paragraphs 1 through 4, 6, and 8 are accepted. With regard to paragraphs 5, 7, and 16 noting that the additional emphasis is not in the text and that the citations are incomplete (and perhaps misleading), they are accepted. Paragraph 9 is rejected as contrary to the weight of credible evidence. Paragraph 10 is rejected as contrary to the weight of credible evidence. Paragraph 11 is rejected as incomplete, and therefore, misleading. Corporate documents may have been filed on that date, however, the weight of the credible evidence established that Kemp had been in business the requisite amount of time. Paragraph 12 is rejected as incomplete, and therefore, misleading. The business conducted by the Kemp personnel continued regardless of the business entity structure that was used. Paragraph 13 is rejected as contrary to the weight of credible evidence. Paragraph 14 is rejected as contrary to the weight of credible evidence or irrelevant. Paragraph 15 is rejected as contrary to the weight of credible evidence. Paragraph 16 is rejected as contrary to the weight of credible evidence. Moreover, no credible evidence was presented to establish that Kemp did not provide services as described in the ITB or that it was not in business the requisite time. Paragraph 17 is rejected as incomplete, and therefore, misleading. The mailing address listed by Kemp was a residential address. Paragraph 18 is rejected as irrelevant. Paragraph 19 is rejected as contrary to the weight of credible evidence. Paragraph 20 is rejected as irrelevant. Kemp probably does not have a Leon County occupational license either. It did have an appropriate occupational license at all times material to this case. Rulings on the proposed findings of fact submitted by the Respondent: 1. Paragraphs 1 through 29 are accepted. COPIES FURNISHED: Thomas H. Duffy Assistant General Counsel Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0450 Mitchell B. Polay Mark H. Klein 750 S.E. Third Avenue Suite 205 Fort Lauderdale, Florida 33316 Thornton J. Williams General Counsel Department of Transportation 562 Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0450 Ben G. Watts, Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0450

# 6
PROCACCI FINANCIAL GROUP, LTD., AND PROCACCI COMMERCIAL REALTY, INC. vs DEPARTMENT OF LABOR AND EMPLOYMENT SECURITY, 92-002650BID (1992)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Apr. 28, 1992 Number: 92-002650BID Latest Update: Oct. 27, 1992

The Issue Whether Respondent's rejection of all bids for Lease No. 540:0920 was improper.

Findings Of Fact The Respondent published an invitation to bid seeking to lease approximately 9,907 net square feet of office space in Broward County (the Lease). There was no evidence of any irregularities in the preparation or the issuance of the invitation. The Petitioner, whose responsive bid was rejected by Respondent, timely and properly brought its protest and has standing to protest the Respondent's rejection of all bids for the Lease. Lynn Mobley was the statewide lease manager of the Respondent and had the responsibility to generally oversee the preparation of the bid package and the bid opening procedures. Barbara Lollie was a staff member under the supervision of Ms. Mobley and was in charge of the preparation of the request for bid proposals. Ms. Mobley's supervisor was a Ms. Barron. Five bids in response to the invitation to bid were duly received by Respondent. An evaluation committee chaired by Don Walker, Respondent's area administrator, was appointed to inspect the proposed properties and to evaluate the bids. The evaluation committee ranked the bids in the following order of preference: 1/ 1. In-Rel ($499,141.80) 2. Taft ($519,090.30) 3. Donlon ($541,119.90) 4. Procacci ($618,373.30) 5. Stirlingwood ($761,906.30) Thereafter the responses to the invitation were forwarded to Ms. Mobley's office for evaluation. Ms. Mobley's staff determined that the top two bids, those of In-Rel and Taft, were non-responsive. 2/ Ms. Mobley, who did not actively participate in the evaluation of the proposals, then advised Mr. Walker of that determination and advised him of two alternatives: to award the bid to the lowest responsive bidder or to reject all bids and re-advertise. The evaluation committee chaired by Mr. Walker had wanted to lease the property to either In-Rel or Taft. Mr. Walker told Ms. Mobley that he wanted to reject all bids and to re-advertise. Pursuant to the request for bids promulgated by the Respondent and Rule 13M-1.015, Florida Administrative Code, the Respondent reserved the right to reject any and all bid proposals for the Lease. The request for proposal of bids specifically stated: The Department reserves the right to reject any and all bid proposals for reasons which shall include but not be limited to the agency's budgetary constraints; waive any minor informality or technicality in bids, to accept that bid deemed to be the lowest and in the best interest of the State, and if necessary, to reinstate procedures for soliciting competitive proposals. Following the telephone conversation between Mr. Walker and Ms. Mobley, Ms. Mobley sent a letter dated March 23, 1992, to all bidders which notified each bidder that all bids had been rejected. That letter did not state the reasons for the rejection of all bids. Mr. Walker sent a memo on March 20, 1992, to Ms. Lollie recommending the rejection of all bids. Although this memo predated the rejection letter and was subsequently made available to Ms. Mobley, the memo was received by Ms. Mobley's office after the rejection letter had been sent. The memo gave no explication of Mr. Walker's reasons for wanting to reject all bids. The Department of General Services (DGS) published lease rate guidelines for Broward County to inform the Respondent of maximum acceptable lease rates. The purpose of these DGS guidelines was to advise the Respondent that proposed lease rates above the guidelines would be summarily rejected. At the time of obtaining bid proposals, the DGS lease rate guidelines were the only established guidelines which could be consulted by the Respondent. At no time did the Respondent calculate a pre-bid estimate of what the Respondent felt was an acceptable range of lease rates in order to be used in determining whether lease rates were too high. The Petitioner's bid, along with the other responsive bidders, were within the DGS lease rate guidelines. Mr. Walker made the request for re-bid after he learned that the bids of Taft and In-Rel were non-responsive. Mr. Walker's decision to recommend the rejection of all bids was based only on the information that the two top choices of the evaluation committee had been found to be non-responsive and on his desire to reopen the bid process in the hope of attracting more bidders. 3/ Mr. Walker wanted to modify the specifications of the invitation to bid in two regards. First, he wanted to amend the specifications to permit the leased premises to be in more than one building. Second, he wanted the geographical boundaries in which the leased premises could be located to be expanded to hopefully attract additional bidders. Mr. Walker believed that a re-bid would provide a wider range of buildings at comparable prices from which to choose and would give him an opportunity to make changes to the bid specifications. His decision to recommend the rejection of all bids was not based on a lease bid analysis or on lease rate guidelines. The recommendation was not dictated by budgetary considerations, but by his desire to shop the bid. It was Mr. Walker's understanding that at the end of his telephone conversation with Ms. Mobley that the decision to reject all bids had been made and that all bids would be rejected. Ms. Mobley made the decision to reject all bids pursuant to the recommendation of Mr. Walker after obtaining input from Ms. Lollie and Ms. Barron. Although Ms. Mobley had Ms. Lollie's analysis of the five bids, that analysis made no comparison of the rates contained in the bids with existing lease rates or the DGS guidelines. Ms. Mobley did not consult the DGS lease rate guidelines, although she was generally familiar with those guidelines, and she was unaware of any budgetary constraints that would dictate the rejection of all bids. When Ms. Mobley decided to reject all bids, she did not compare the bid proposals to the existing lease rates paid by the Respondent for leased office space in Broward County. The decision to reject all bids was not made on the advice of an attorney. Although Ms. Mobley testified that all bids on the Lease were rejected solely for price considerations, the evidence presented established that the decision to reject all bids was not based on price, price guidelines, or the Respondent's budgeting constraints. The greater weight of the evidence establishes that Ms. Mobley rejected all bids because that was the action recommended by Mr. Walker. Respondent's invitation to bid did not contain any lease rate guidelines that would notify prospective bidders of a lease rate ceiling. There was no significant difference in the lease rates between the Taft and In-Rel bids that were favored but non-responsive and the third lowest bidder, the Donlon bid, which was responsive but rejected. Mr. Walker conceded that the Donlon bid was not rejected because of price considerations. Mr. Walker was of the opinion that the Donlon bid was at an acceptable price. He did not testify that the Petitioner's bid was at an unacceptable price and he did not testify as to what, other than the DGS guidelines, would be the maximum acceptable price. The DGS Lease Guidelines applicable to the bid for the Lease were as follows: A full service Lease (including electricity) -- $17.84 a square foot. 4/ Lease without electricity -- $15.18 a square foot. The present rate for the existing lease which was to be replaced by the Lease was $16.60 a square foot; this rate did not include electricity. If electricity was factored in at $2.50 a square foot, which was a factor regularly used by DGS, the present lease rate would be approximately $18.00 a square foot. The three responsive bids to the invitation were lower than the present lease after factoring in electricity. Ms. Goodman was of the opinion that Respondent's budget with respect to the Lease would be based on lease rates already in existence and consequently, that the responsive bids received and rejected were within the budget guidelines. Respondent offered no evidence to controvert that opinion. There was no evidence that the decision to reject all bids was based on economic considerations. All lease rates submitted by the rejected bidders were under the ceiling set by the DGS lease guidelines of $17.84. The Respondent acted arbitrarily when it rejected all bids.

Recommendation Based upon the foregoing findings of fact and conclusion of law, it is hereby recommended that the Respondent accept and evaluate the responsive bids submitted for the Lease and determine the proper recipient for an award of the Lease. RECOMMENDED this 29th day of June, 1992, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1992.

Florida Laws (4) 120.57120.68255.25287.012
# 7
MODERN MAILERS vs DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, 94-003593BID (1994)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jul. 07, 1994 Number: 94-003593BID Latest Update: Oct. 03, 1994

The Issue This case considers whether Petitioner's response to Invitation to Bid, No. 94-014, as revised, issued by the Respondent, is responsive to the terms of the Invitation to Bid. If Petitioner is found responsive, then the question is raised whether Petitioner has offered the lowest and best response to the invitation to bid.

Findings Of Fact On May 26, 1994, Respondent provided a memorandum to prospective vendors concerning Bid No. 94-014, as revised. This memorandum informed the prospective vendors that the new bid due date was June 6, 1994. The memorandum attached the bid instructions. Under general conditions to the invitation to bid the prospective vendors were reminded in Paragraph 7 that the Respondent could ". . . reject any or all bids or waive any minor irregularity or technicality in bids received." Under the heading "Special Provisions" prospective vendors were informed that "The charge per 1,000 for individual items under Exhibit A shall be the rates for the contract with the successful bidder." The prospective bidders were instructed as follows: REQUIRED ITEMS TO BE SUBMITTED WITH BID: The bidder must complete all required items below and submit as part of the bid package. Any bid in which these items are not used or in which these items are improperly executed, may be considered non-responsive and the bid may be subject to rejection. Among the items to be submitted with the bid was Exhibit A. The bidders were informed about the process of EVALUATION/AWARD. There it was stated: Bids will be evaluated and awarded on an all or none basis to one bidder. Award will be based on the total costs of four (4) theoretical jobs (See Exhibit B-Bid Total) requiring varying services and on the bidder's qualifications to best serve the Department's needs. The prospective bidders were then reminded a second time that: "THE DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION RESERVES THE RIGHT TO REJECT ANY AND ALL BIDS AND TO WAIVE ANY MINOR IRREGULARITIES IN BIDS RECEIVED." Within Exhibit A to the bid document was a category referred to as "Tabbing", calling for the charge per 1,000 for that service. Within Exhibit B under the fourth theoretical job was a requirement to quote the subtotal cost for 200,000 newsletter preparations to include "Tabbing." Three vendors submitted responses to the invitation to bid. Those responses were opened on June 6, 1994. The vendors who responded were Petitioner, Educational Clearinghouse, Inc. and Mail Masters of Tallahassee, Inc. In the subtotal for costs for 200,000 newsletter preparations, in activity four, concerning theoretical jobs, found within Petitioner's Exhibit B to the response to the invitation to bid, Petitioner made a mistake. It misplaced the decimal point and described the subtotal cost for 200,000 newsletter preparations as $73.80 instead of $7,380.00. Respondent characterized this as a typographical error or nominal mistake. In fact, this error constituted a minor irregularity which did not preclude the ability to understand Petitioner's response so that it might be compared to the responses by the competition. Petitioner made a second error. This error occurred when Petitioner failed to indicate the amount that it would charge per 1,000 for "Tabbing" within Exhibit A. Respondent did not consider this to be a minor irregularity and rejected Petitioner's bid as non-responsive for the failure to include a quotation for the charge per 1,000 for "Tabbing." This resulted in the intent to award the contract to Educational Clearinghouse, Inc. whose bid total for the four theoretical jobs under Exhibit B was $9,137.25 compared to Petitioner's bid total of $8,374.62. In preparing Exhibit B, activity four, Petitioner included a theoretical charge for "Tabbing" in the amount of $8.00 per 1,000. Petitioner contends that the $8.00 per 1,000 found within that entry may be correlated with the missing information concerning "Tabbing" in Exhibit A to its response to the invitation to bid. In the instructions to the vendors, Respondent has informed the vendors that the charge per thousand for individual items identified in Exhibit A constitutes the rate that the Respondent would expect to pay under a contract with the successful bidder. By contrast, the function of the information provided in Exhibit B is for purposes of awarding the contract based upon total costs of the four theoretical jobs and on the basis of the vendor's qualifications to best serve the Respondent's needs. Although not stated in the invitation to bid it can be inferred that similar references within Exhibits A and B, such as the reference to "Tabbing", calls for a comparable price to be set forth for the item in both Exhibit A and Exhibit B. Otherwise vendors would have the opportunity to quote low prices in completing Exhibit B as a means to win the cost comparison with their competitors for purposes of the award and then have the opportunity to charge higher costs per 1,000 as reflected in Exhibit A when establishing the charges for the contract with the Respondent following the competition contemplated in the comparison of the theoretical bid total under Exhibit B. Therefore, it would be reasonable for the Respondent to expect that the Petitioner would charge $8.00 per 1,000 for "Tabbing" under a contract between the Petitioner and Respondent based upon information that was set forth in the response to Exhibit B, activity four, "Tabbing." In summary, Petitioner's oversight in leaving out reference to the tabbing charge in Exhibit A does not affect the comparison of bid responses as contemplated by the instructions to the vendors, a function performed by comparing the respective Exhibits B. Otherwise, Respondent may gain the necessary understanding of Petitioner's charge per 1,000 for "Tabbing" as contemplated in instructions concerning Exhibit A as a means for entering into the contract. This understanding is achieved by transposing the $8.00 per 1,000 "Tabbing" quotation in Exhibit B to the "Tabbing" charge within Exhibit A as $8.00 per 1,000. With this adjustment, Modern Mailers, Inc. is the lowest responsive bidder and best able to serve Respondent's needs pertaining to Invitation to Bid No. 94-014, as revised.

Recommendation Based upon the findings of fact and the conclusions of law reached, it is, RECOMMENDED: That a final order be entered which finds that Petitioner is a "qualified" and "responsible" bidder who is the lowest and best responsive bidder to Invitation to Bid, No. 94-014, as revised and is entitled to the award of the contract contemplated by that invitation to bid. DONE and ENTERED this 8th day of September, 1994, in Tallahassee, Florida. CHARLES C. ADAMS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of September, 1994. APPENDIX The following discussion is given concerning the proposed findings of fact of the Parties: Petitioner's Facts: Paragraph 1 is subordinate to facts found. Paragraph 2 is not necessary to the resolution of the dispute. Paragraphs 3 through 5 are subordinate to facts found. Paragraphs 6 and 7 are rejected to the extent that they are intended to establish an excuse for the Petitioner not providing information related to the cost for tabbing called for in Exhibit A in the invitation to bid. Paragraph 8 is subordinate to facts found. Paragraphs 9 through 12 are not necessary to the resolution of the dispute. Paragraph 13 is subordinate to facts found. Paragraph 14 is rejected to the extent that it suggests that Petitioner may amend its response to the invitation to bid to specifically set forth the amount attributable to the tabbing charges per 1,000 in Exhibit A. Nonetheless one may infer that the cost per 1,000 for tabbing is the same as is set forth in Exhibit B. Paragraphs 15 through 17 are subordinate to facts found. Paragraph 18 constitutes legal argument. Respondent's Facts: Paragraph 1 is subordinate to facts found. Paragraph 2 is contrary to facts found Paragraph 3 is rejected in fact and law. Paragraph 4 is rejected in the suggestion that the Petitioner does not have the ability to perform the contract. COPIES FURNISHED: Daniel W. Dobbins, Esquire Callahan & Dobbins 433 North Magnolia Drive Tallahassee, FL 32308 Vytas J. Urba, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Jack McRay, General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 George Stuart, Secretary Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Informational Copies: Ronald W. Brooks, Esquire Brooks and LeBoeuf, P.A. 863 East Park Avenue Tallahassee, FL 32301 Joan Reeves, Vice President Educational Clearinghouse Post Office Box 3951 Tallahassee, FL 32315

Florida Laws (3) 120.53120.57287.012
# 8
KELLOGG AND KIMSEY, INC. vs LEE COUNTY SCHOOL BOARD, 91-007597BID (1991)
Division of Administrative Hearings, Florida Filed:Fort Myers, Florida Nov. 26, 1991 Number: 91-007597BID Latest Update: Mar. 02, 1992

Findings Of Fact Upon consideration of the oral and documentary evidence addressed at the hearing, the following relevant findings of fact are made: The request for sealed bids for the construction of the Project was advertised on October 9, 16 and 23, 1991. There were six addenda to the original bid documents which added, deleted or modified provisions of the original bidding requirements, contract requirements, administrative requirements and technical specifications. The original bid documents plus the six addenda will be referred to herein as the "bid documents". The bid documents required that all bids be in full accord with the contract documents. Sealed bids for the Project were opened on October 30, 1991. Wright submitted the lowest lump sum bid for the Project, with Sovran submitting the second lowest lump sum bid and Kellogg submitting the third lowest lump sum bid. At the time of the bid opening, the bid documents listed only four casework manufacturers that were approved to furnish casework for the Project. Empire Custom Cabinets, Inc. (Empire) was not listed as one of the four approved casework manufacturers in the bid documents. The bid documents did not require the bidder to list the casework manufacturer it intended to obtain the casework from, but only that the bidder name the casework subcontractor. The only work item in the bid documents which requires identifying the name of the manufacturer on the subcontractor's list is the metal roof system. Because Empire's bid on the casework was extremely low compared to other bids received by Wright on the casework, Wright called Empire prior to submitting its bid to confirm that Empire's bid was submitted per plans and specifications. Although Wright did not specifically inquire of Empire at this time as to which manufacturer Empire was obtaining the casework from for the Project, Empire did advise Wright that Empire's bid on the casework was according to plans and specifications. Additionally, Empire did not divulge or advise Wright at this time that the bid was based on Empire manufacturing the casework for the Project. Based on this representation from Empire, Wright listed Empire as its casework subcontractor, and calculated its lump sum bid for the Project using Empire's bid. Although Wright listed Empire as its casework subcontractor in its bid, this did not create an irregularity in Wright's bid since Wright's bid was per plans and specification without exception or exclusion. This would require Wright to furnish casework for the Project manufactured by one of the four approved casework manufacturers listed in the bid documents regardless of which subcontractor Wright listed as the subcontractor for casework. By letter dated November 1, 1991, the Board's architect for the Project requested Wright to have Empire submit written certification by one of the four approved casework manufacturers that its casework was being furnished to Empire for the project. By letter dated November 4, 1991, Empire advised Wright that Empire's bid on the casework for the Project was based on casework to be manufactured by Empire. On the same day, Wright furnished the architect for the Project a copy of Empire's letter of November 4, 1991. In response to a request by the Board, Wright, by letter dated November 7, 1991, advised the Board that Wright would furnish casework manufactured by one of the four approved manufacturers listed in the bid documents for the Project. By letter dated December 3, 1991, Empire advised Wright that Empire would need to withdraw its bid if Empire was required to use casework manufactured by one of the four approved casework manufacturers listed in the bid documents. On that same day, Wright furnished the Board a copy of Empire's letter and requested that the Board allow Wright to remove and replace Empire with Steven Ward and Associates, Inc. (Ward), as the casework subcontractor since Ward would be able to furnish and install casework manufactured by LSI Corporation of America, Inc., one of the four approved casework manufacturers. No Action has been taken on that request. The bid documents provide for a subcontractor to be removed and replaced from the list of subcontractors after the bid is opened if there is a showing of good cause and written approval by the Board and the Project architect is obtained. Although Empire's bid on the casework for the Project submitted to Wright was based on Empire manufacturing the casework, there is competent substantial evidence in the record to establish facts to show that at the time Wright submitted its bid on the Project it had reasonable grounds to believe that Empire's bid on the casework was based on Empire furnishing and installing casework manufactured by one of the four approved casework manufacturers. After determining that Empire could not perform under its bid, Wright obtained a bid from Ward for furnishing and installing the casework for the Project which was less than Ward's original bid submitted to Wright before the bid opening. However, this bid was substantially more than Empire's bid, and if Wright is allowed to substitute Ward for Empire, Wright will have to absorb the additional costs since the bids were lump sum bids. Wright is neither attempting to furnish casework from a manufacturer that is not approved, nor is Wright requesting an increase in the lump sum bid price. The advertisement for Sealed Bids for the Project required that all bidders be prequalified by the Board prior to the bid date. Sovran and one other bidder were not prequalified by the Board prior to the bid date in accordance with Advertisement for Sealed Bids for the Project. Sovran received the bid documents for the Project approximately one month before the bid date but did not file a Notice of Protest of the prequalification requirement contained in the Advertisement for Sealed Bids for the Project. Sovran holds a certificate as a general contractor licensed in the State of Florida in accordance with Chapter 489, Florida Statutes. As a certified general contractor Sovran, pursuant to Section 489.125, Florida Statutes, was authorized to bid on the Project notwithstanding the Board's prequalification requirement. This was explained by the Board's representative at the bid opening. The bid documents required that a subcontractor list be submitted by all bidders, and when submitted with the bid becomes an integral part of the bid. The purpose of the subcontractor list was to prevent bid shopping, and to allow the Board an opportunity to review the subcontractors to determine if any subcontractor on the list had performed unsatisfactorily on previous Board projects. Neither the statutes relating to competitive bidding nor the bid documents prohibit the listing of the general contractor together with a subcontractor on a subcontractor list. The subcontractor list submitted by Sovran indicated "Sovran Constr/Naples" as the name of the subcontractor for the masonry work and "Sovran/Naples" as the name of the subcontractor for the poured-in-place concrete work. "Naples" is Naples Concrete and Masonry Work, Inc. The bid received by Sovran from Naples was for both labor and materials for the poured-in-place concrete and masonry work. Sovran neither requested nor did Naples furnish Sovran a bid to provide labor only for the poured-in-place concrete and masonry work. There was no agreement between Sovran and Naples whereby Sovran would supply the materials and Naples would furnish the labor for the poured-in-place concrete and masonry work. Sovran did request and receive bids from other companies for furnishing materials only for the poured-in-place concrete and masonry work. Sovran listed itself, the general contractor, along with Naples on the subcontractor list for the purpose of supplying the materials for the poured-in- place concrete and masonry work. Sovran's main reason for supplying the materials was that Naples was not bondable. Without a payment bond from Naples, Sovran would be without protection and could be forced into paying double for the materials in the event Naples failed to pay the material suppliers. Although the Superintendent of the Lee County Schools has recommended to the Board that the Board accept Wright's bid for the Project, the Board has not voted on that recommendation. The fact that Wright used Empire's bid to calculate its lump sum bid in no way excuses Wright for the requirement set out in the bid documents that casework used for the Project (when the time comes) be manufactured by one of the four approved casework manufacturers. Wright gains no economic advantage in this regard since the lump sum bid price remains the same. The advertisement for Sealed Bids on the Project provides that the Board reserves the right to waive any and all irregularities of any bid received.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, accordingly RECOMMENDED: That the Board enter a Final Order dismissing the instant bid protest and awarding to Wright the contract for the construction of Elementary School "C", Job No. 91063. DONE and ORDERED this 13th day of February, 1992, in Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13 day of February, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NUMBER 91-7597B1D The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the parties in this case. Rulings on Proposed Findings of Fact Submitted by the Petitioner Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 1 - 3(1,2 and 3 , respectively); 4 - 5(6); 6(4); 7 - 9(5); 12(10); 13(11); 15 - 16(12); 17(13); 18 - 19(16); 20(29); 21(18); 23(19); 24 - 25(20); 26(22); 27(23); 28(22); 29 - 30(29); 32 - 33(25); and 34(26). Proposed finding of fact 10 is rejected as not being supported by competent substantial evidence in the record in that Wright's bid was as per plans and specifications without exceptions or exclusions which included the use of casework manufactured by one of the approved casework manufacturers. Proposed finding of fact 11 is rejected as not being supported by competent, substantial evidence in the record in that the Board knew of Empire's bid being based on nonconforming materials prior to issuing its Notice of Intent. However, the only information the Board had in reference to Wright's bid before issuing its Notice of Intent was that Wright had bid as per plans and specifications and would be installing casework manufactured by one of the approved manufacturers. The only question was whether Empire could furnish casework manufactured by one of the approved manufacturers. Proposed finding of fact 14 is neither material nor relevant. How the Board's architect interpreted Wright's bid is neither material nor relevant to this proceeding. Proposed finding of fact 22 is unnecessary to the conclusion reached in the Recommended Order. Proposed finding of fact 31 is more in the way of an argument than a finding of fact. Proposed findings of fact 35 and 36 are covered in the Preliminary Statement. The timeliness of Kellogg's protest is not an issue and therefore, a finding that it was timely is unnecessary. Rulings on Proposed Findings of Fact Submitted by the Respondent While not specifically adopting proposed finding of fact 1, where material or relevant or necessary to this proceeding, and supported by competent, substantial evidence in the record the stipulated facts have been adopted. Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 2(4,5); 3(9); 4 - 5(7); 7 - 8(8); 10(16); 11(14); 12(31); 13(21); and 15(23). Proposed finding of fact 6 is more in the way of an argument than a finding of fact. Proposed finding of fact 9 and 14 are neither material nor relevant. Rulings on Proposed Findings of Fact Submitted by the Intervenor See ruling on Respondent's proposed finding of fact Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 2 - 3(21); 4(24); 5 - 6(21); 13(23); 14(24,28); 15(22); 16 - 17(23,24); and 18(28). Proposed findings of fact 7 through 12 are neither material nor relevant to this proceeding. COPIES FURNISHED: David E. Gurley, Esquire Norton, Gurley & Darnell, P.A. 1819 Main Street, Suite 610 Sarasota, FL 34236 Marianne Kantor, Esquire The School Board of Lee County 2055 Central Avenue Fort Myers, FL 33901 James M. Talley, Esquire Fisher, Rushmer, Werrenrath, Keiner, Wack & Dickson, P.A. Post Office Box 712 Orlando, FL 32802 Karl Engel Superintendent Lee County School Board 2055 Central Avenue Ft. Myers, FL 33901 Honorable Betty Castor Commissioner of Education The Capitol Tallahassee, FL 32399-0400

Florida Laws (3) 120.53120.57489.125
# 9
LEE A. EVERHART AND COMPANY, INC. vs. DEPARTMENT OF CORRECTIONS, 83-001761 (1983)
Division of Administrative Hearings, Florida Number: 83-001761 Latest Update: May 02, 1990

Findings Of Fact On or about February 9, 1983, the State of Florida, Department of General Services, Division of Construction and Property Management, Bureau of Property Management ("DGS"), received a certification of need from the Department of Corrections ("DOC") requesting authority for DOC to advertise for competitive bids from private persons interested in providing leased office space needed to house DOC's Bureau of Industries. The Bureau of Industries was then located in leased space with leases which were scheduled to expire June 30, 1983. The Bureau of Industries has been located in DOC's central office area since its creation in 1957. The DOC central office includes the Secretary and Deputy Secretary; the Assistant Secretaries for Operations, Programs, Management, and Budget. All these officials, together with subsidiary bureaus, staff, and other subordinates are located in two adjacent buildings of the Winewood Office Complex on Blair Stone Road in Tallahassee. The prison industry program is under the supervision of the industries administrator who reports directly to the Assistant Secretary for Operations. DOC sought approval from DGS to enter into a lease for privately owned office space because of its perceived need to locate within walking distance of its central office. Programs administered by the Bureau of Industries work closely with other DOC personnel and functions located in the central office in the Winewood Office Complex. Moving any distance from the central office would create problems for the DOC mailing system and would require extra time spent traveling to and from the central office. Personnel in the Bureau of Industries utilize central office files, and confer often with staff located in the central office. Locating outside the general area of the central office would require additional expenses with regard to availability of vehicles, pick up of mail and supplies, and duplication of support services. Accordingly, DGS and DOC determined, and the record in this cause establishes, that it would not be in the state's best interest to require DOC to locate its Bureau of Industries program either in state-owned buildings in the Capitol Center, or in any area beyond walking distance of the central office location. On March 21 and 31, 1983, respectively, DOC published an advertisement in the Tallahassee Democrat inviting all interested persons to submit sealed bids at or before 2:00 p.m. on April 19, 1983, in accordance with the Invitation to Bid and Specifications prepared by DOC for the office space needed to house the Bureau of Industries. A portion of the bid specifications required that office space to be leased be located within a circle drawn on a city map of the City of Tallahassee, Florida, which could roughly be described as the southeastern portion of the city, in the vicinity of the Winewood Office Complex. There were four possible bidders in the area within the circle on the map attached to the bid specifications. Of these four possible bidders, two within the area actually submitted bids--Blairstone Center Partners and Washington Square, Ltd. One of the general provisions of the bid specifications provided as follows: The Department of Corrections reserves the right to reject any and all bids, waive any minor informality or technicality in bids received and to accept that bid deemed to be the lowest and best. . . At or before 11:00 a.m. on April 19, 1983, DOC received sealed bids from Petitioner and Intervenors in response to the aforesaid advertisement, and at 11:00 a.m. on April 19, 1983, DOC opened, tabulated, and published each of the bids. The bid submitted by Petitioner was not responsive to the requirements of the Invitation to Bid and Specifications because the property offered by Petitioner in its response was outside the area indicated on the map annexed to the Invitation to Bid. The bid submitted by Intervenor, Blairstone Center Partners, failed to offer the full services specified in paragraph six of DOC's Bid Submittal Form; failed to offer the exclusive parking specified in the paragraph seven of the Bid Submittal Form; failed to supply the photographs specified in paragraph ten of Respondent's Bid Submittal Form; and failed to supply the information specified in paragraphs one through eight of the Bid Submittal Form. Accordingly, the record in this cause fully establishes that the bids submitted by Petitioner and by Intervenors Blairstone Center Partners, failed to comply with the requirements of the Invitation to Bid and Bid Submittal Form, and that the deficiencies in the bids of Petitioner and Intervenor, Blairstone Center Partners, were so material as to require their rejection. The Invitation to Bid and Bid Submittal Form required that bidders offer for lease 2,683 square feet, plus or minus three percent. The bid submitted by Intervenor, Washington Square, Ltd., offered 2,797 square feet, which is approximately 34 square feet more than allowed in the Invitation to Bid. After this fact was discovered upon opening the bid, DOC personnel contacted a representative of Washington Square, Ltd., and advised the net square footage offered in the bid submitted by Washington Square, Ltd., exceeded the net square footage of space that DOC was authorized to lease and pay for under the Invitation to Bid. Washington Square, Ltd., subsequently agreed to modify its proposal by relieving DOC from any obligation to pay for the extra 34 square feet, and reducing the annual rental for the first year from $26,012.10 to $25,695.90, and for the second year from $27,576.60 to $27,243.18. The record in this cause does not establish any misconduct or collusion between Washington Square, Ltd., and DOC personnel obtaining this modification, nor does the record in this cause establish that any actual or prospective bidders suffered any competitive disadvantage as a result of this modification. The effect of Washington Square, Ltd.'s modification of its proposal rendered that proposal the only bid which was responsive to the Invitation to Bid. On August 18, 1983, Washington Square, Ltd., executed a deed to the property which was the subject matter of its bid to Ben Grace. Washington Square also executed an assignment of the proposed bid award to Grace.

Florida Laws (3) 120.57243.18255.25
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer