Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
PRINCE CONTRACTING, LLC vs DEPARTMENT OF TRANSPORTATION, 16-004982BID (2016)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Aug. 29, 2016 Number: 16-004982BID Latest Update: Jan. 20, 2017

The Issue Whether Respondent acted contrary to the agency's governing statutes, rules, or policies or the bid specifications in its proposed decision to award Contract No. T7380 to Astaldi Construction Corporation ("Astaldi").

Findings Of Fact Based on the oral and documentary evidence presented at the final hearing, and on the entire record of the proceeding, the following Findings of Fact are made: The Department is a state agency authorized by section 337.11 to contract for the construction and maintenance of roads within the State Highway System, the State Park Road System, and roads placed under its supervision by law. The Department is specifically authorized to award contracts under section 337.11(4) to “the lowest responsible bidder.” On April 15, 2016, the Department advertised a bid solicitation for Contract T7380, seeking contractors for the widening of a 3.8 mile portion of U.S. Highway 301 in Hillsborough County from two lanes to six lanes between State Road 674 and County Road 672 and over Big Bull Frog Creek. The advertisement provided a specification package for the project and the “Standard Specifications for Road and Bridge Construction” (“Standard Specifications”) used on Department roadway projects. The work included seven components: bridge structures (Section 0001), roadway (Section 0002), signage (Section 0003), lighting (Section 0004), signalization (Section 0005), utilities (Section 0006), and intelligent transportation systems (Section 0007). The advertisement identified 666 individual items of work to be performed and quantity units for each item. The project was advertised as a low-bid contract with a budget estimate of $51,702,729. The Department’s bid proposal form contains five columns with the following headings: Line Number; Item Number and Item Description; Approximate Quantities and Units; Unit Price; and Bid Amount. The bid proposal form contains line items for the seven components of the project. The utilities component contains 42 line items, each with an Item Number and Item Description. For example, Line Number 1410 corresponds with the following Item Number and Item Description: “1050 11225 Utility Pipe, F&I, PVC, Water/Sewer, 20–40.9 [inches].” Each bidder inserts a Unit Price for the line item in the corresponding “Unit Price” column. The “Bid Amount” column for each line item is an amount generated by multiplying a bidder’s Unit Price by the Quantities (determined by the Department) for each Line Number. The Bid Amount for each Line Number is then added together to generate the “Total Bid Amount” representing the bid for the entire project. Astaldi, Prince, Hubbard, and other potential bidders attended the mandatory pre-bid meeting. Prequalified contractors were given proposal documents that allowed them to enter bids through Bid Express, the electronic bidding system used by the Department. Plan revisions were issued by addenda dated May 10, 2016, and June 7, 2016. A Question and Answer Report was published and updated as inquiries were addressed. Bids were opened on the letting date of June 15, 2016. Bids for Contract T7380 were received from Astaldi, Prince, Hubbard, the DeMoya Group (“DeMoya”), Ajax Paving Industries of Florida, LLC (“Ajax”), and Cone & Graham, Inc. (“Cone & Graham”). The bids were reviewed by the Department’s contracts administration office to ensure they were timely, included a Unit Price for each line item, and contained the completed certifications required by the specifications. Bidders were checked against the Department’s list of prequalified bidders to confirm they possessed a certification of qualification in the particular work classes identified by the bid solicitation. Each bidder’s total current work under contract with the Department was examined to ensure that award of Contract T7380 would not place the bidder over its Department-designated financial capacity limit. Astaldi submitted the lowest bid, a total amount of $48,960,013. Prince submitted the next lowest bid, a total amount of $57,792,043. Hubbard’s total bid was the third lowest at $58,572,352.66. The remaining bidders came in as follows: DeMoya, $63,511,686.16; Ajax, $68,617,978.10; and Cone & Graham, $70,383,697.74. All bidders were prequalified in the appropriate work classes and had sufficient financial capacity, in accordance with section 337.14 and Florida Administrative Code Chapter 14-22. The Department’s construction procurement procedure, from authorization to advertisement through contract execution, is outlined in the Department’s “Road and Bridge Contract Procurement” document (“Contract Procurement Procedure”). The scope statement of the Contract Procurement Procedure provides: “This procedure applies to all Contracts Administration Offices responsible for advertising, letting, awarding, and executing low bid, design-bid-build, construction, and maintenance contracts.” Limited exceptions to the procedure may be made if approved by the assistant secretary for Engineering and Operations. If federal funds are included, the Federal Highway Administration division administrator, or designee, must also approve any exceptions from the procedure. The stated objectives of the Contract Procurement Procedure are: “to standardize and clarify procedures for administering low-bid, design-bid-build, construction, and maintenance contracts” and “to provide program flexibility and more rapid response time in meeting public needs.” The Department’s process for review of bids is set forth in the “Preparation of the Authorization/Official Construction Cost Estimate and Contract Bid Review Package” (“Bid Review Procedure”). The scope statement of the Bid Review Procedure states: This procedure describes the responsibilities and activities of the District and Central Estimates Offices in preparing the authorization and official construction cost estimates and bid review packages from proposal development through the bid review process. Individuals affected by this procedure include Central and District personnel involved with estimates, specifications, design, construction, contracts administration, work program, production management, federal aid, and the District Directors of Transportation Development. The Bid Review Procedure contains a definitions section that defines several terms employed by the Department to determine whether a bid or a unit item within a bid is “unbalanced.” Those terms and their definitions are as follows: Materially Unbalanced: A bid that generates reasonable doubt that award to that bidder would result in the lowest ultimate cost or, a switch in low bidder due to a quantity error. Mathematically Unbalanced: A unit price or lump sum bid that does not reflect a reasonable cost for the respective pay item, as determined by the department’s mathematically unbalanced bid algorithm. Official Estimate: Department’s official construction cost estimate used for evaluating bids received on a proposal. Significantly Unbalanced: A mathematically unbalanced bid that is 75% lower than the statistical average. Statistical Average: For a given pay item, the sum of all bids for that item plus the Department’s Official Estimate which are then divided by the total number of bids plus one. This average does not include statistical outliers as determined by the department’s unit price algorithm. For every road and construction project procurement, the Department prepares an “official estimate,” which is not necessarily the same number as the “budget estimate” found in the public bid solicitation. The Department keeps the official estimate confidential pursuant to section 337.168(1), which provides: A document or electronic file revealing the official cost estimate of the department of a project is confidential and exempt from the provisions of s. 119.07(1) until the contract for the project has been executed or until the project is no longer under active consideration. In accordance with the Bid Review Procedure, the six bids for Contract T7380 were uploaded into a Department computer system along with the Department’s official estimate. A confidential algorithm identified outlier bids that were significantly outside the average (such as penny bids) and removed them to create a “statistical average” for each pay item. Astaldi’s unit pricing was then compared to the statistical average for each item. The computer program then created an “Unbalanced Item Report,” flagging Astaldi’s “mathematically unbalanced” items, i.e., those that were above or below a confidential tolerance value from the statistical average. The unbalanced item report was then reviewed by the district design engineer for possible quantity errors. No quantity errors were found.1/ The Department then used the Unbalanced Item Report and its computer software to cull the work items down to those for which Astaldi’s unit price was 75 percent more than or below the statistical average. The Department sent Astaldi a form titled “Notice to Contractor,” which provided as follows: The Florida Department of Transportation (FDOT) has reviewed your proposal and discovered that there are bid unit prices that are mathematically unbalanced. The purpose of this notice is to inform you of the unbalanced nature of your proposal. You may not modify or amend your proposal. The explanation of the bid unit prices in your proposal set forth below was provided by ASTALDI CONSTRUCTION CORPORATION on ( ) INSERT DATE. FDOT does not guarantee advanced approval of: Alternate Traffic Control Plans (TCP), if permitted by the contract documents; Alternative means and methods of construction; Cost savings initiatives (CSI), if permitted by the contract documents. You must comply with all contractual requirements for submittals of alternative TCP, means and methods of construction, and CSI, and FDOT reserves the right to review such submittals on their merits. As provided in section 5-4 of the Standard Specifications for Road and Bridge Construction you cannot take advantage of any apparent error or omission in the plans or specifications, but will immediately notify the Engineer of such discovery. Please acknowledge receipt of this notice and confirmation of the unit bid price for the item(s) listed below by signing and returning this document. Section 5.4 of the Bid Review Procedure describes the Notice to Contractor and states: “Contracts are not considered for award until this form has been signed and successfully returned to the Department per the instruction on the form.” State estimating engineer Greg Davis testified that the stated procedure was no longer accurate and “need[s] to be corrected” for the following reason: Since the procedure was approved back in 2011, we’ve had some subsequent conversations about whether to just automatically not consider the award for those that are not signed. And since then we have decided to go ahead and just consider the contract, but we are presenting a notice, of course, unsigned and then let the technical review and contract awards committee determine. Astaldi signed and returned the Notice to Contractor and noted below each of the ten listed items: “Astaldi Construction confirms the unit price.” Mr. Davis explained that the purpose of the Notice to Contractor form is to notify the contractor that items have been identified as extremely low and to ask the contractor to confirm its understanding that in accepting the bid, the Department will not necessarily approve design changes, methods of construction, or maintenance of traffic changes. Section 6.6 of the Contract Procurement Procedure sets forth the circumstances under which an apparent low bid must be considered by the Department’s Technical Review Committee (“TRC”) and then by the Contract Awards Committee (“CAC”). Those circumstances include: single bid contracts; re-let contracts; “significantly mathematical unbalanced” bids; bids that are more than 25 percent below the Department’s estimate; 10 percent above the Department’s estimate (or 15 percent above if the estimate is under $500,000); materially unbalanced bids, irregular bids (not prepared in accordance with the Standard Specifications); other bid irregularities2/; or “[a]ny other reason deemed necessary by the chairperson.”3/ Bids that are not required to go before the TRC and CAC are referred to as “automatic qualifiers.” Because it was mathematically unbalanced, the Astaldi bid was submitted to the TRC for review at its June 28, 2016, meeting. The TRC is chaired by the Department’s contracts administration manager, Alan Autry, and is guided by a document entitled “Technical Review Committees” (“TRC Procedure”). The TRC Procedure sets forth the responsibilities of the TRC in reviewing bid analyses and making recommendations to the CAC to award or reject bids. The TRC voted to recommend awarding Contract T7380 to Astaldi. The TRC’s recommendation and supporting paperwork was referred to the CAC for its meeting on June 29, 2016. The duties of the CAC are described in a document entitled “Contracts Award Committees” (“CAC Procedure”). Pursuant to the CAC Procedure, the CAC meets approximately 14 days after a letting to assess the recommendations made by the TRC and determines by majority vote an official decision to award or reject bids. Minutes for the June 29, 2016, CAC meeting reflect 21 items before the committee including: two single bid contracts; four bids that were 10 percent or more above the official estimate; one bid that was 15 percent or more above the official estimate on a project under $500,000; three bids that were more than 25 percent below the official estimate; and 11 bids with significantly unbalanced items, including Contract T7380 with an intended awardee of Astaldi. The CAC voted to award Contract T7380 based on the low bid submitted by Astaldi. A Notice of Intent to award the contract to Astaldi was posted on June 29, 2016. As noted at Finding of Fact 2, supra, Contract T7380 consisted of seven components: structures, roadway, signage, lighting, signalization, utilities, and intelligent transportation system. The Department does not compare bids by component, but looks at the total bid amount to find the lowest bidder. The Department also reviews the bids for discrepancies in individual unit items using the process described above. Astaldi’s bid of $48,960,013 was approximately $8.8 million below Prince’s bid of $57,792,043, $9.6 million less than Hubbard’s bid of $58,572,352, and $2.7 million below the Department’s public proposal budget estimate of $51,702,729. As part of its challenge to the intended award, Prince performed a breakdown of bids by individual components and discovered that nearly all of the differences between its bid and Astaldi’s could be attributed to the utilities component. Astaldi’s bid for the utilities component was $7,811,720, which was roughly $8.5 million below Prince’s utilities bid of $16,305,903 and $5.8 million below Hubbard’s utilities bid of $13,603,846.4/ The utilities component was included pursuant to an agreement between the Department and Hillsborough County, the owner of the water and sewer lines, relating to the improvement of water and sewer lines along the roadway limits of the project. The utility work consists of installing a new water- line and force main sewer. The existing water main and the existing force main conflict with the proposed location of the new storm drainage system. The new water main and force main must be installed, tested, and approved before being put into active service. To prevent water utility outages to customers, the new system must be installed and approved before the existing waterline and existing force main can be cut off and removed. Utility work is therefore the first task to be performed on Contract T7380. Once the utility component is completed, the contractor will furnish and install the stormwater system, the roadway, the bridgework, and all other components. Article 3-1 of the Standard Specifications5/ reserves to the Department the right to delete the utility relocation work from the contract and allow the utility owner to relocate the utilities. Utilities are the only portion of a Department contract subject to deletion because the funding is provided by the utility owner, which usually has allocated a certain dollar figure to contribute towards the contract prior to the bidding. If the bid for utilities comes in over the utility owner’s budget, the owner can opt out of the contract and self-perform. In this case, Hillsborough County had contracted with the Department to contribute $8.9 million for utility relocation work. The Department did not exercise the option to delete the utilities portion of the contract. Jack Calandros, Prince’s chief executive, testified that Prince uses a computer program called HeavyBid, created and supported by a company called HCSS, to build the cost components of its bids. Every witness with industry knowledge agreed that HeavyBid is the standard program for compiling bids in the construction field. Mr. Calandros testified that cost components include material quotes provided by third-party vendors and quotes from potential subcontractors. Labor and equipment costs are ascertained by using historical rates and actual cost estimates that are tracked by the HeavyBid software. Prince maintains its own database of costs derived from 20 years’ experience. Mr. Calandros stated that Prince’s internal labor and equipment rates are checked and adjusted at least once a year to ensure they are current and accurate based on existing equipment and personnel. Prince received three vendor quotes for the materials to perform the utility work on Contract T7380. In compiling its bid, Prince ultimately relied on a final quote from Ferguson Waterworks (“Ferguson”) of $8,849,850. Based on this materials quote and Prince’s overall utilities bid of $16,305,903, Mr. Calandros opined that it would not be possible for Astaldi to perform the utilities component for its bid amount of $7.8 million. Prince’s estimating expert, John Armeni, reviewed Astaldi’s bid file, read the deposition testimony of Astaldi’s chief estimator, Ed Thornton, and spoke to Mr. Thornton by telephone. Mr. Armeni also reviewed Prince’s bid and the bid tabulation of all bidders’ utilities component line items. Based on his review and his extensive experience in the industry, Mr. Armeni concluded that Astaldi’s bid does not include all costs for labor, material, and equipment necessary to construct the utilities portion of this project. Mr. Armeni reviewed the materials quote from Ferguson that Prince used in its bid. He noted that Astaldi’s bid file contained an identical quote from Ferguson of $8.8 million for materials, including some non-utilities materials. Mr. Armeni noted that the Ferguson quote for utilities materials alone was approximately $8 million, an amount exceeding Astaldi’s entire bid for the utilities portion of the project. Mr. Armeni also noted that Astaldi’s overall bid was 18 percent below that of the second lowest bidder, Prince. He testified that 18 percent is an extraordinary spread on a bid where the Department is providing the quantities and all bidders are working off the same drawings and specifications. Mr. Armeni believed that the contracting authority “should start looking at it” when the difference between the lowest and second lowest bidder is more than 10 percent. In his deposition, Mr. Thornton testified he was not aware of how Astaldi arrived at its bid prices for the utility section of the project. Mr. Thornton indicated multiple times that he was not Astaldi’s most knowledgeable person regarding the bid submitted by Astaldi on Contract T7380 project. He testified that Astaldi intended to subcontract the utilities work and acknowledged that the company received a subcontractor quote of $14.9 million after the bids were submitted. Mr. Thornton did not know if Astaldi had solicited the quote. He said it is not unusual for a company to receive subcontractor bids after it has been named the low bidder on a project. Mr. Thornton conceded that Astaldi’s bid did not include all the costs necessary to construct the utilities portion of Contract T7380. At his deposition, he did not have before him the materials needed to determine which items of cost Astaldi had omitted. Mr. Thornton testified that Astaldi was not missing any information it needed at the time of bid submission and understood that its price was to include all labor, materials, and subcontracting costs to perform the contract. After the proposed bid award, Astaldi used HeavyBid to produce a report indicating that the company now estimates its cost of performing the contract at $53,708,129.03, or roughly $4.75 million more than its winning bid. Mr. Thornton testified that Astaldi nonetheless stood ready to execute the contract and perform the work at its bid price. Central to the dispute in this case is Standard Specifications Section 9, “Measurement and Payment,” article 9-2 of which is titled “Scope of Payments.” In particular, subarticle 9-2.1 provides: 9-2.1 Items Included in Payment: Accept the compensation as provided in the Contract as full payment for furnishing all materials and for performing all work contemplated and embraced under the Contract; also for all loss or damage arising out of the nature of the work or from the action of the elements, or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the work until its final acceptance; also for all other costs incurred under the provisions of Division I. For any item of work contained in the proposal, except as might be specifically provided otherwise in the payment clause for the item, include in the Contract unit price (or lump sum price) for the pay item or items the cost of all labor, equipment, materials, tools and incidentals required for the complete item of work, including all requirements of the Section specifying such item of work, except as specially excluded from such payments. Prince contends that the second paragraph of subarticle 9-2.1 renders Astaldi’s bid nonresponsive because Astaldi admittedly failed to include “the cost of all labor, equipment, materials, tools and incidentals” in its bid. Prince points out that the “Technical Special Provisions” governing the utilities portion of the project reinforce the requirement that each bidder include all costs for the work. Technical Special Provisions Section 1-7.1 provides that “[p]ipe installation cost shall include all necessary work, equipment, and labor needed for installing the pipe, such as, coordination with existing utilities and support during construction and support of existing power poles during construction.” Technical Special Provisions Section 1-8.1 goes on to say that “[n]o separate payment will be made for the following items for work under this Technical Special Provision and the cost of such work shall be included in the applicable contract pay items of work,” followed by a comprehensive list of 30 items. Prince concludes that the requirement that each bidder include all costs, including costs of all necessary labor, equipment, and materials, in the Unit Price for each work item is “manifest” in the bid specifications and requires rejection of any bid that does not include all costs. Mr. Armeni opined that if one bidder excludes a portion of its costs, the other bidders are placed at a competitive disadvantage. Alan Autry, the Department’s central contracts administration manager, testified that five other projects were let as part of the bid package that included Contract T7380. He stated that it is typical for the Department to list multiple projects on one day. Mr. Autry’s office usually performs one bid letting per month, with the holiday months of November and December rolled together in a single letting. Mr. Autry stated that his office lets between 200 and 300 projects per year, not counting contracts that are let at the district level. Twenty other contracts were before the CAC at the June 29, 2016, meeting at which the Astaldi award in this case was approved. As noted at Finding of Fact 2, supra, Contract T7380 included 666 line items. Six companies submitted bids, meaning there were a total of 3,996 line items in this single contract. Assuming that the 200 to 300 other projects let by the Department’s Tallahassee office contain similar numbers, there are more than one million line items bid in any given year. If Prince’s reading of the bid specifications is correct, the Department is required to examine each of these line items and somehow make a determination whether the item includes all of the bidder’s costs. This problem of determining bidder cost is complicated by the presence of “companion” or “sister” items in bids, i.e., two items that must be considered in tandem to arrive at something like the actual cost of the work. Prince provided an example of such companion items in its analysis of the bids in this project. Two bid items included in the structures section of the bid proposal form were concrete culverts and reinforcing steel. The contractor may cast the culverts in place at the worksite or purchase them precast. If the concrete culvert is cast in place at the worksite, then reinforcing steel must be used to strengthen the culvert. If the concrete culvert is precast by a materials supplier, then the reinforcing steel has already been incorporated into the culvert at the time of installation. Mr. Calandros explained that when a contractor uses precast culverts, there is no need to list a separate additional cost for reinforcing steel; all costs are captured in the line item for concrete culverts. In this bid, Prince used precast culverts and therefore bid a penny per unit for reinforcing steel.6/ Bidders who cast the culverts in place showed a much higher cost for reinforcing steel but a lower cost for the concrete culverts. When the “companion items” were considered in tandem, the total cost for each vendor was fairly consistent. Prince’s explanation for companion items was coherent but did not explain how the Department is supposed to know which items are companion items as it undertakes the line-by-line cost examination of each bid in accordance with Prince’s reading of the bid specifications. Prince also failed to provide an explanation as to how the Department is to determine a bidder’s costs for any one line item or, for that matter, for its overall bid on a project. Bidders consider their cost information and the processes by which they build bids to be confidential proprietary information. In the instant case, Prince disclosed its own information (aside from materials costs) only under seal during litigation. In its ordinary course of business, the Department does not have access to this information. In fact, as noted at Finding of Fact 23, supra, the Department does not compare bids by component. It looks only at the total bid amount in determining the lowest bidder. Standard Specifications Article 3-8 reserves to the Department the right to perform an audit of the contractor’s records pertaining to the project upon execution of the contract. No authorization is provided to audit records of bidders prior to contracting. Standard Specifications Subarticle 2-5.1 allows bidders to indicate “free” or “$.00” for items that will be supplied at no cost to the Department. Though the Department’s practice, according to Mr. Autry, is to include zero bid items on the Notice to Contractor for confirmation of the price, subarticle 2-5.1 requires no Department investigation as to whether the bidder’s cost for a zero bid is actually zero. Bidders often bid a penny on items, as Prince did on reinforcing steel in this case. Standard Specifications Article 3-5 requires all contracts to be secured by a surety bond such that, in the event of a default by the contractor, the surety company will indemnify the Department on all claims and performance issues. Standard Specifications Section 4 provides that the scope of work is to be determined within the contract, including the furnishing of all labor, materials, equipment, tools, transportation, and supplies required to complete the work. The Department is authorized to make changes to the scope of work and make equitable adjustments of payments. If necessary, the Department may enter into supplemental agreements for additional or unforeseen work. Prince cautions that these change provisions could become relevant because Astaldi’s bid contains no information explaining how Astaldi will cover the $4.75 million difference between its bid price and its actual cost to perform the contract. Prince accurately states that nothing in Astaldi’s bid demonstrates that it has cash reserves to cover the loss and still complete the entire scope of the work.7/ Prince contends that this lack of demonstrable reserves renders Astaldi nonresponsible as to this project. Prince argues that it is error for the Department to rely on Astaldi’s certificate of qualification as proof of the company’s responsibility. The certificate of qualification process considers a contractor’s financial status at the time it submits its financial statements and other information regarding company resources. Prince contends that the Department’s assessment of the contractor’s financial statements and issuance of a certificate of qualification is insufficient to determine the contractor’s responsibility on a given bid. Prince argues that the Department is required by its governing statutes and the Standard Specifications to award a particular contract to the particular bidder that is the lowest, responsive, and responsible bidder, and that “responsible” for a given project is not synonymous with “prequalified.” Prince hypothesizes that under the Department’s practice, a bidder could possess a certificate of qualification issued in January, be indicted in another state for fraud and bribery in February, submit the lowest bid for a Department project in March, and be awarded the contract. By relying solely on the bidder’s certificate of qualification to determine responsibility, the Department could award a contract to a nonresponsible bidder. Section 337.14 provides that any person desiring to bid on any construction contract in excess of $250,000 must first be certified by the Department. Mr. Autry explained that the Department prequalifies contractors to submit bids on certain types of contract, such as major bridges and structures. Contractors applying for certification are required to submit their latest annual financial statements. The Department is charged with reviewing applications to determine “whether the applicant is competent, is responsible, and possesses the necessary financial resources to perform the desired work.” § 337.14(3), Fla. Stat. The Department assigns the contractor work classes and a total capacity after evaluating its experience and financials. The Department’s certificate is good for 18 months, though the contractor’s capacity is reviewed annually. At the time of a particular bid, the Department verifies the contractor’s available capacity, which is simply its total assigned capacity minus current work the contractor is performing for the Department. Mr. Autry testified that the Department does not go back and look at a bidder’s financials to determine whether it can sustain a loss on a given project. The Department does not repeat its capacity analysis during the year, regardless of how many projects the company bids on. The Department’s analysis is limited to whether the company’s current capacity is sufficient for the project on which it is bidding.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that the Department of Transportation enter a final order dismissing Prince Contracting, LLC’s, second amended formal written protest and awarding Contract T7380 to Astaldi Construction Corporation. DONE AND ENTERED this 22nd day of December, 2016, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of December, 2016.

Florida Laws (18) 1.01119.07120.52120.53120.54120.56120.569120.57120.68129.0320.23334.048337.015337.11337.14337.16337.164337.168 Florida Administrative Code (1) 28-106.217
# 1
HURST AWNING COMPANY, INC. vs DEPARTMENT OF TRANSPORTATION, 94-002297BID (1994)
Division of Administrative Hearings, Florida Filed:Miami, Florida Apr. 27, 1994 Number: 94-002297BID Latest Update: Jun. 24, 1994

Findings Of Fact Based upon the oral and documentary evidence adduced at the final hearing and the entire record in this proceeding, the following findings of fact are made: In January of 1994, FDOT issued an Invitation to Bid ("ITB") for contracts FE2494Z1 and FE2494Z2 to provide storm shutters for the FDOT facilities in Zones 1 and 2 of the Florida Turnpike. The ITB was entitled "Storm Shutters, Removable, Manufacture, Furnish and Install." Prospective bidders for the contracts were provided with a packet which included General Conditions, Special Conditions, Specifications and General Special Provisions. The General Conditions set forth the procedures for submitting and opening the bids. The Specifications called for custom-sized removable storm shutters and detailed the materials and installation procedures that were required. The bid package contained the following pertinent language in the Special Conditions, Section 1.0, entitled "Description", and in the Specifications, Section 1.0, entitled "Scope of Work": Work under this contract consists of providing all labor, materials, equipment, tools and incidentals necessary to manufacture, furnish and install galvanized steel storm panels and accessories for all of Zone 1 & Zone 2 buildings and locations as identified in the building listing listings document, see Exhibit "A" Zone 1 & Exhibit "A" Zone 2. The bid package contained the following pertinent language in Special Conditions Section 8.1, entitled "Required Documents": Bidders are required to complete and return the State of Florida "Invitation to Bid" form as well as the bid sheet(s). These forms must be signed by a representative who is authorized to contractually bind the bidder. All bid sheets and the "Invitation to Bid" form must be executed and submitted in a sealed envelope. At a mandatory pre-bid conference on February 17, 1994, the Department's representatives were available to answer questions regarding the bid package. During the pre-bid conference, John Vecchio of the Department orally advised the prospective bidders that they should return the whole bid package, including the specifications, when they submitted their bid. No written amendment to this effect was issued. The bids were opened on March 3, 1994 in Fort Lauderdale. Bids were received for each contract from at least three bidders, including Accurate and Hurst. The apparent low bidder for both contracts was Broward Hurricane Panel Co. ("Broward"). Prior to the bids being posted on March 28, 1994, Broward's bid was determined to be nonresponsive and Broward was therefore disqualified. After Broward was disqualified, Accurate was the apparent low qualified bidder for Zone 2 and Hurst was the apparent low qualified bidder for Zone 1. Hurst's bid for the contract for Zone 2 was $85,000. Its bid for the Contract for Zone 1 was $36,000. Accurate's bids for the contracts were $84,854.82 and $36,287.16, respectively. Hurst was awarded the contract for Zone 1 and that decision has not been challenged. At the same time the Department announced the award of the Contract for Zone 1 to Hurst, the Department announced its intent to award the contract for Zone 2 to Accurate. Hurst timely filed a notice of protest and a formal written protest of the proposed award of the contract for Zone 2 to Accurate. Initially, FDOT raised as a defense that Hurst had not posted a protest bond as required by Section 287.042(2)(c), Florida Statutes. At the hearing in this matter, FDOT conceded that Hurst had subsequently posted a protest bond which had been accepted by FDOT. Hurst contends that Accurate's bid should have been deemed nonresponsive because Accurate does not have the ability to "manufacture" the specified product in its own facility. The 2 inch corrugated shutter required by the ITB has to be shaped on a special type of machine that rolls, presses and forms the metal. Hurst owns and maintains at its Opa-Locka facility a rolling mill capable of forming the panels to the bid specifications. Accurate is in the business of supplying the types of products sought by the ITB in this case. However, Accurate does not own the kind of machine necessary to shape the metal. The evidence established that for many years, Accurate has had a continuing business relationship with a local subcontractor, Shutter Express, that rolls, presses and forms raw material supplied by Accurate in accordance with Accurate's specifications. Shutter Express has the capability of fabricating shutters with a 2 inch corrugation in accordance with the ITB. Accurate is equipped to attach the headers and sills, drill the necessary holes, complete the assembly and install the final product. The ITB in this case did not preclude subcontracting any or all of the work specified. While the description of the work in the ITB includes the term "manufacture", this reference should not be read to mean that only those companies that were able to fabricate the entire product at their own facility could properly respond to the ITB. There is no logical justification for such a narrow interpretation. Only a few companies have the ability to completely fabricate the shutters on their own property. At the prebid conference, there was discussion amongst the prospective bidders about subcontracting the fabrication work and the FDOT representatives did not raise any objections to such an arrangement. It was widely understood by the parties present at the pre-bid conference that the Department was not interpreting the ITB in the restrictive manner now urged by Hurst. Such a reading of the ITB would have precluded from the bidding process a number of companies such as Accurate that routinely supply and install shutters. Hurst also contends that the bid proposal submitted by Accurate should be deemed nonresponsive because Accurate failed to include the entire ITB with its proposal in accordance with the oral instructions at the pre-bid conference. Hurst's proposals included the entire ITB. As discussed below, Accurate's proposal did not include the entire ITB. FDOT determined that all essential pages were included in Accurate's response and the evidence did not establish that this conclusion was arbitrary, capricious or fraudulent. Paragraph 6 of the General Conditions of the ITB provided: ADDITIONAL TERMS AND CONDITIONS: No additional terms and conditions included with the bid response shall be evaluated or considered and any and all such additional terms and conditions shall have no force and affect and are inapplicable to the bid. As noted above, at the prebid conference held on February 17, 1994, an FDOT employee told all prospective bidders to return the entire bid package when making their submittals. This request that the entire bid package be returned was simply meant as a protection for the bidder to ensure that all the necessary documents referenced in Section 8.1 of the Specifications were submitted. Other than those documents referenced in Section 8.1 of the Specifications, FDOT had no interest in having the remaining portion of the ITB submitted with a proposal. Accurate's submittal contained every document required by Section 8.1 of the Specifications. Accurate's proposal did not contain pages 3 through 12, 14, 15 and 17 through 20 of the ITB, but did include pages 1 and 2, 13, 16, 21 and 22 along with a signed Form PUR 7068 and a signed acknowledgment of Addendum In other words, the submittal contained a signed and completed Bidder Acknowledgment, completed Bid Price Forms for Zones 1 and 2, a signed copy of Addendum #1, a completed copy of the Ordering Instructions, and a signed, but not notarized, statement regarding public entity crimes. 1/ In addition to the "REQUIRED DOCUMENTS," set forth in Section 8.1 of the Specifications and quoted in Findings of Fact 6 above, the ITB included Section 8.2, "PUBLIC ENTITY CRIMES STATEMENT" which provides: Any person submitting a bid or proposal in response to this invitation should execute the enclosed form PUR 7068, SWORN STATEMENT UNDER SECTION 287.133(A), FLORIDA STATUTES, ON PUBLIC ENTITY CRIMES, including proper check(s) provided, and submit it with the bid/proposal or within 72 hours of the bid opening. Page 7 of the ITB provided in pertinent part: 10.0 BID PREFERENCE IDENTICAL TIE BIDS - Preference shall be given to businesses with drug-free workplace programs. Whenever two or more bids which are equal with respect to price, quality and service are received by the State or by any political subdivision for the procurement of commodities or contractual services, a bid received from a business that certifies that it had implemented a drug-free workplace program shall be given preference in the award process. . . . Accurate's proposal did not include a certification that it was a drug-free workplace in accordance with this provision. However, such a certification is only used by the Department as a tie-breaker. In other words, in the event of identical bids, any firm with a drug-free workplace would get preference. Since there were no tied bids in this case, certification was totally irrelevant. When the bids were opened, Mary Bailey, the contracts administrator for the Department, noticed that Accurate's submittal was thinner than the others and asked Accurate's representative, Richard Johnson, about the remaining pages. Mr. Johnson replied that the other pages were in his truck and offered to retrieve them. Ms. Bailey told him there was no need to do so. Section 10 of the General Conditions in the bid package provides as follows: As the best interest of the State may require, the right is reserved...to reject any and all bids or waive any minor irregularity or technicality in bids received... It does not appear that Accurate has obtained any competitive advantage as a result of its failure to include the entire ITB with its bid proposals. Even if the oral instructions at the pre-bid conference are deemed to have modified the ITB so that the entire bid package should have been submitted, Accurate's failure to include the entire ITB with its response should be considered a minor technicality, pursuant to Section 10 of the General Conditions cited above, that can and should be waived in evaluating the responsiveness of the bid. Similarly, the failure to have the Form PUR 7068 notarized may have rendered Accurate's bid proposals incomplete, but not necessarily nonresponsive. This oversight can be easily corrected without giving Accurate a competitive advantage.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered finding the bid submitted by Accurate to be responsive and dismissing the challenge filed by Hurst. DONE and ENTERED this 24th day of June 1994, at Tallahassee, Florida. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of June 1994.

Florida Laws (8) 120.53120.57287.042287.087287.133287.16337.02337.11 Florida Administrative Code (2) 60A-1.00160A-1.002
# 2
ECCELSTON PROPERTIES, LTD. vs. DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 88-004901BID (1988)
Division of Administrative Hearings, Florida Number: 88-004901BID Latest Update: Jan. 12, 1989

Findings Of Fact Prior to June, 1988, HRS determined that it needed 23,871 square feet of office space to house some of its social services for indigents in Northern Escambia County. Since HRS desired more than 2,000 square feet of office space, it was required to bid lease number 590:1987 competitively. To that end, Respondent prepared an Invitation to Bid and a bid submittal package. The package contained various bid specifications, bid evaluation criteria and the numerical weight assigned to each of those criteria. Specific areas of importance to Respondent in the selection of its office space were: client safety public access, ingress and egress availability of public transportation. The above areas were important to HRS since the agency would render indigent services to approximately 1000 people a month, many of whom are handicapped or lack good mobility due to age or infirmity. The majority of Respondent's clients are served within a 10 day period during each month. A great deal of pressure is placed on the surrounding area due to the in flux of people. Additionally, many of Respondent's clients utilize public transportation since they do not own or have access to personal vehicles. Because of servicing so many people the above factors received a great deal of weight under HRS's consideration of the property it desired to lease and occupy. All of the above areas were covered by Respondent's weighted bid evaluation criteria. Additionally, in order to submit a responsive bid, a prospective lessor was required to meet one of the following qualifications at the time the bid was submitted: (a) be the owner of record of the facility and parking areas; (b) be the lessee of the space being proposed and present with the bid a copy of the lease with documentation of authorization to sublease the facility and parking areas; (c) submit documentation of an option to purchase the facility and/or parking areas; or (d) submit documentation of an option to lease the facility with authorization to, in turn, sublease. The District Administrator of HRS, Chelene Schembera, is ultimately responsible for bidding, selection and leasing of all HRS facilities within District I, including Escambia County, Florida. In order to accomplish this task Ms. Schembera appointed a bid evaluation committee to review and grade the responsive bids under the criteria established in the bid package, and to recommend to her the committee's choice of the lowest and best bid. Ms. Schembera's purpose in establishing the bid evaluation committee was to secure input from a cross section of people who had a variety of backgrounds and knowledge that would be material in evaluating the office space, in light of the uses for which it was intended and the relative public worth of the work space. Ms. Schembera appointed individuals who were familiar with the type of work to be done in the proposed space, as well as persons familiar with the bid process. On July 21, 1988, HRS received five bids on the lease. Intervenors submitted the apparent low bid which Northside consisted of one building located at the Brentwood Shopping Center in Pensacola, Florida. At the time that the Intervenors submitted their bid, they included documentation which showed that they had a contract to purchase the subject facility; they have since closed on that transaction. This bid package did not include the four acres adjacent to the Brentwood Shopping Center property and no contract to purchase or other documentation was submitted as to the four acre parcel of property. Petitioner submitted the apparent second lowest bid which consisted of one building located at Fairfield Plaza in Pensacola, Florida. Petitioner's interest in Fairfield Plaza is that of a lessee under a Master Lease with rights to sublet the property. All appropriate documentation was submitted with the bid. This property was the subject of a semi-friendly foreclosure action at the time that the Petitioner's bid was submitted. Petitioner was still in possession and control of the property. Both Petitioner's and Intervenors' property were within the mandatory geographical area designated in the bid package. Both bids were responsive under the minimum bid specifications and bidder qualifications. The other three bids which were submitted by HRS are not in contention The committee members personally inspected the sites offered by the Petitioner and the Intervenors. While at the Intervenors' site, the committee's concern over the property's minimal parking (as compared to Fairfield) and limited safe public access, ingress and egress were raised. The only access to Intervenor's property was from a very busy multi-lane highway. Certain turns onto and off the property were extremely dangerous. In order to make its bid package more acceptable, Intervenors' representative orally amended the bid package to include the southerly four acres contiguous to the Brentwood property. The Inclusion of the southerly four acres would adequately increase Intervenors' parking. The amendment would also create additional and safer public ingress and egress since the four acres abutted on Murray Lane which intersects Highway 29. This amendment substantially worked to Intervenors' advantage and was a material change to the previously submitted bid. The improper amendment cannot be considered here. Following the on-site inspections, the committee members met and rated the properties submitted by Petitioner and Intervenors according to a Bid Synopsis evaluation sheet which they had been previously provided. The committee members' review of the Intervenors' property included the improper bid amendment. Even with the improper amendment, the unanimous recommendation of the evaluation committee was to award the lease to the Petitioner and Fairfield Plaza. The evaluation committee based its decision on the scores attributed to each property on the Bid Synopsis sheet by the individual committee members. The committee utilized all the weighted bid criteria. However, two factors were of primary importance. One was its determination that the property offered by the Intervenors presented greater problems for ingress and egress due to the congested nature the area. The other consideration was that service to Fairfield Plaza from public transportation was both more frequent and direct. The property offered by the Intervenors had less public transportation service. The stops were less frequent and a significant number of clients would be required to transfer buses to reach Brentwood when utilizing such public transportation. All bus passengers would be required to walk from the bus stop close to Brentwood and attempt at their peril to cross a very busy, dangerous and congested highway. The reasons given by the individual committee members for distinguishing and preferring one bid over another were rational and reasonable considerations and were covered by the bid evaluation criteria. Each individual member gave a rational and reasonable basis for the scoring he or she used on the Bid synopsis score sheets. The scoring was done by each member after discussion of the two buildings and without influence from the other committee members. In essence, the committee felt that Petitioner's property was the better property for the money. Importantly, every committee member came to the conclusion that Petitioner's property was the lowest and best bid. There is no statutory or rule requirement that one scoring method be preferred over another. The only requirement is that the method be rational and reasonable especially where highly subjective, but legitimate criteria are involved in the selection of a piece of property. On these facts, the individual scoring methods used by the individual committee members were not arbitrary and capricious, but were very rational and reasonably related to the relative importance the committee members gave the above factors. The District Administrator initially adopted the committee's recommendation and reported that recommendation to King Davis, the Director of General Services for HRS. The Director of General Services later informed the District Administrator that he and his staff were concerned with the fact that the recommendation was to award the lease to the second lowest bidder. The staff's review considered the improper amendment as part of the Intervenors' bid. Over a ten year period the Petitioner's rental cost was $62,381.00 more than the Intervenors'. In addition, the estimated energy consumption for the first year for the Petitioner's property was approximately $4800 more than for Intervenors. King Davis and his staff did not believe that the justifications cited in the recommendation letter would be considered crucial enough to override awarding the lease to the lowest bidder, should the agency get involved in a bid protest over the award. He and his staff did not disagree that the reasons assigned by the committee and Ms. Schembera were legitimate considerations. Their ultimate concern was that the reasons given by the committee and Ms. Schembera would not be given as great a weight by a Division of Administrative Hearings' hearing officer; and therefore, fail to withstand a potential bid challenge. But the conclusion that the lack of ingress and egress and public transportation could not outweigh the cost differences assumed that Intervenors' bid included the four acres. Without the four acres, the problems with ingress and egress, congestion and public transportation become even more important and can outweigh minor price differences in rent and energy. This is especially true when one considers the impact that the influx of at least 1000 people would have on an already congested and unsafe area. Put simply, the conclusion that the above factors can and do outweigh price and cost considerations in these facts is not an arbitrary and capricious decision, even though others may disagree with that decision. Instead of reconvening the committee after receiving the recommendation from King Davis and discussing the same with him, the District Administrator made the determination that the lease should be awarded to the Intervenors. The District Administrator, acquiesced in Mr. Davis' assessment that HRS could not succeed in a bid challenge. She did not like his advice. In fact, even at the hearing Ms. Schembera still believed Petitioner's property was the lowest and best for HRS purposes. However, through circular reasoning she also concluded that Intervenors' property was the lowest and best bid because she chose it. The agency's ability to succeed in a bid challenge which may or may not happen is not covered by any of the weighted bid evaluation criteria contained in the bid package and is not an appropriate reason to prefer one bid over another. The foregoing is particularly true when the reason given (surviving a bid protest) is based on the occurrence of a future event which may not occur. To reject a bid for a reason outside the bid criteria and one based on an unknowable future event is an arbitrary and capricious act on the part of Respondent. A court-appointed receiver was ordered to take control of the property belonging to the Petitioner on September 28, 1988, after the bid award was announced. Petitioner still retains its right of redemption of the property, and such an interest is sufficient to confer standing on Petitioner to maintain this action. Moreover, the evidence was clear that Petitioner had both the ability and wherewithal to perform the lease should it receive the bid award. Perfected ownership or control is not required. With Petitioner's apparent ability to perform, the fact of the foreclosure action and the receiver should not work against the Petitioner in this bid protest.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED: That the Department of Health and Rehabilitative Services enter a final order awarding lease number 590:1987 to Eccelston Properties, Ltd., as the lowest and best bidder. DONE and ORDERED this 10th day of January, 1989, in Tallahassee, Florida. DIANE CLEAVINGER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 10th day of January, 1989.

Florida Laws (7) 120.53120.5720.19255.249255.25255.254255.255
# 3
PROCACCI FINANCIAL GROUP, LTD., AND PROCACCI COMMERCIAL REALTY, INC. vs DEPARTMENT OF LABOR AND EMPLOYMENT SECURITY, 92-002650BID (1992)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Apr. 28, 1992 Number: 92-002650BID Latest Update: Oct. 27, 1992

The Issue Whether Respondent's rejection of all bids for Lease No. 540:0920 was improper.

Findings Of Fact The Respondent published an invitation to bid seeking to lease approximately 9,907 net square feet of office space in Broward County (the Lease). There was no evidence of any irregularities in the preparation or the issuance of the invitation. The Petitioner, whose responsive bid was rejected by Respondent, timely and properly brought its protest and has standing to protest the Respondent's rejection of all bids for the Lease. Lynn Mobley was the statewide lease manager of the Respondent and had the responsibility to generally oversee the preparation of the bid package and the bid opening procedures. Barbara Lollie was a staff member under the supervision of Ms. Mobley and was in charge of the preparation of the request for bid proposals. Ms. Mobley's supervisor was a Ms. Barron. Five bids in response to the invitation to bid were duly received by Respondent. An evaluation committee chaired by Don Walker, Respondent's area administrator, was appointed to inspect the proposed properties and to evaluate the bids. The evaluation committee ranked the bids in the following order of preference: 1/ 1. In-Rel ($499,141.80) 2. Taft ($519,090.30) 3. Donlon ($541,119.90) 4. Procacci ($618,373.30) 5. Stirlingwood ($761,906.30) Thereafter the responses to the invitation were forwarded to Ms. Mobley's office for evaluation. Ms. Mobley's staff determined that the top two bids, those of In-Rel and Taft, were non-responsive. 2/ Ms. Mobley, who did not actively participate in the evaluation of the proposals, then advised Mr. Walker of that determination and advised him of two alternatives: to award the bid to the lowest responsive bidder or to reject all bids and re-advertise. The evaluation committee chaired by Mr. Walker had wanted to lease the property to either In-Rel or Taft. Mr. Walker told Ms. Mobley that he wanted to reject all bids and to re-advertise. Pursuant to the request for bids promulgated by the Respondent and Rule 13M-1.015, Florida Administrative Code, the Respondent reserved the right to reject any and all bid proposals for the Lease. The request for proposal of bids specifically stated: The Department reserves the right to reject any and all bid proposals for reasons which shall include but not be limited to the agency's budgetary constraints; waive any minor informality or technicality in bids, to accept that bid deemed to be the lowest and in the best interest of the State, and if necessary, to reinstate procedures for soliciting competitive proposals. Following the telephone conversation between Mr. Walker and Ms. Mobley, Ms. Mobley sent a letter dated March 23, 1992, to all bidders which notified each bidder that all bids had been rejected. That letter did not state the reasons for the rejection of all bids. Mr. Walker sent a memo on March 20, 1992, to Ms. Lollie recommending the rejection of all bids. Although this memo predated the rejection letter and was subsequently made available to Ms. Mobley, the memo was received by Ms. Mobley's office after the rejection letter had been sent. The memo gave no explication of Mr. Walker's reasons for wanting to reject all bids. The Department of General Services (DGS) published lease rate guidelines for Broward County to inform the Respondent of maximum acceptable lease rates. The purpose of these DGS guidelines was to advise the Respondent that proposed lease rates above the guidelines would be summarily rejected. At the time of obtaining bid proposals, the DGS lease rate guidelines were the only established guidelines which could be consulted by the Respondent. At no time did the Respondent calculate a pre-bid estimate of what the Respondent felt was an acceptable range of lease rates in order to be used in determining whether lease rates were too high. The Petitioner's bid, along with the other responsive bidders, were within the DGS lease rate guidelines. Mr. Walker made the request for re-bid after he learned that the bids of Taft and In-Rel were non-responsive. Mr. Walker's decision to recommend the rejection of all bids was based only on the information that the two top choices of the evaluation committee had been found to be non-responsive and on his desire to reopen the bid process in the hope of attracting more bidders. 3/ Mr. Walker wanted to modify the specifications of the invitation to bid in two regards. First, he wanted to amend the specifications to permit the leased premises to be in more than one building. Second, he wanted the geographical boundaries in which the leased premises could be located to be expanded to hopefully attract additional bidders. Mr. Walker believed that a re-bid would provide a wider range of buildings at comparable prices from which to choose and would give him an opportunity to make changes to the bid specifications. His decision to recommend the rejection of all bids was not based on a lease bid analysis or on lease rate guidelines. The recommendation was not dictated by budgetary considerations, but by his desire to shop the bid. It was Mr. Walker's understanding that at the end of his telephone conversation with Ms. Mobley that the decision to reject all bids had been made and that all bids would be rejected. Ms. Mobley made the decision to reject all bids pursuant to the recommendation of Mr. Walker after obtaining input from Ms. Lollie and Ms. Barron. Although Ms. Mobley had Ms. Lollie's analysis of the five bids, that analysis made no comparison of the rates contained in the bids with existing lease rates or the DGS guidelines. Ms. Mobley did not consult the DGS lease rate guidelines, although she was generally familiar with those guidelines, and she was unaware of any budgetary constraints that would dictate the rejection of all bids. When Ms. Mobley decided to reject all bids, she did not compare the bid proposals to the existing lease rates paid by the Respondent for leased office space in Broward County. The decision to reject all bids was not made on the advice of an attorney. Although Ms. Mobley testified that all bids on the Lease were rejected solely for price considerations, the evidence presented established that the decision to reject all bids was not based on price, price guidelines, or the Respondent's budgeting constraints. The greater weight of the evidence establishes that Ms. Mobley rejected all bids because that was the action recommended by Mr. Walker. Respondent's invitation to bid did not contain any lease rate guidelines that would notify prospective bidders of a lease rate ceiling. There was no significant difference in the lease rates between the Taft and In-Rel bids that were favored but non-responsive and the third lowest bidder, the Donlon bid, which was responsive but rejected. Mr. Walker conceded that the Donlon bid was not rejected because of price considerations. Mr. Walker was of the opinion that the Donlon bid was at an acceptable price. He did not testify that the Petitioner's bid was at an unacceptable price and he did not testify as to what, other than the DGS guidelines, would be the maximum acceptable price. The DGS Lease Guidelines applicable to the bid for the Lease were as follows: A full service Lease (including electricity) -- $17.84 a square foot. 4/ Lease without electricity -- $15.18 a square foot. The present rate for the existing lease which was to be replaced by the Lease was $16.60 a square foot; this rate did not include electricity. If electricity was factored in at $2.50 a square foot, which was a factor regularly used by DGS, the present lease rate would be approximately $18.00 a square foot. The three responsive bids to the invitation were lower than the present lease after factoring in electricity. Ms. Goodman was of the opinion that Respondent's budget with respect to the Lease would be based on lease rates already in existence and consequently, that the responsive bids received and rejected were within the budget guidelines. Respondent offered no evidence to controvert that opinion. There was no evidence that the decision to reject all bids was based on economic considerations. All lease rates submitted by the rejected bidders were under the ceiling set by the DGS lease guidelines of $17.84. The Respondent acted arbitrarily when it rejected all bids.

Recommendation Based upon the foregoing findings of fact and conclusion of law, it is hereby recommended that the Respondent accept and evaluate the responsive bids submitted for the Lease and determine the proper recipient for an award of the Lease. RECOMMENDED this 29th day of June, 1992, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1992.

Florida Laws (4) 120.57120.68255.25287.012
# 5
CHUCK BUNDSCHU, INC. vs. DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 82-000312 (1982)
Division of Administrative Hearings, Florida Number: 82-000312 Latest Update: Jul. 07, 1982

The Issue The questions presented here concern the entitlement of the Petitioner or Intervenor to be awarded lease rights under the Respondent's proposed Lease No. 590:8026, in that Petitioner and Intervenor have claimed that entitlement to the exclusion of the other party.

Findings Of Fact Respondent invited bid proposals for the provision of approximately 32,000 square feet of office space for its District VIII operation in Fort Myers, Florida. Petitioner, Chuck Bundschu, Inc., and Intervenor, Walter Lee Johnson d/b/a Walco Leasing Company, responded to the bid proposal by offering to provide the office space. Those responses may be found as part of the Composite Hearing Officer's Exhibit. Following the October, 1981, submittal of bid proposals, a bid evaluation committee was appointed by the Subdistrict Administrator for District VIII to consider the bids. In turn, he afforded guidance to that committee on the subject of the evaluation of the proposed bids offered by Bundschu and Walco, the only bidders for the project. The evaluation committee performed the task of weighing the bid proposals, in keeping with evaluation criteria which are outlined in Respondent's "Facilities, Acquisition and Management Manual" dealing with the procurement of lease space, which criteria are set forth in a form referred to as "HRSM 70-1, page A1-4-8," which is attached to chapter four of the manual. All criteria used for the evaluation process were drawn from that form with the exception of criterion No. 7, related to staff and client marking which was a product of this bid evaluation effort. (A copy of the HRS manual and forms may be found as Respondent's Exhibit No. 1, admitted into evidence. The evaluation committee's summarization utilizing the form criteria and the additional parking criterion may be found as a part of the Hearing Officer's Composite Exhibit, which is a replication of the original.) The HRS manual for procuring leased space is a publication of February, 1980, and establishes uniform guidelines by which bid proposals are considered by local officials who are part of Respondent's organization. Nonetheless, the exact weight to be afforded each criterion outlined in the manual is determined by the local evaluation committee. Weighing concerns the subject of awarding numerical values for beach bidder related to the various criteria with a maximum possible score being 100 points. On the basis of the evaluation performed by the committee, the Bundschu total was 88.25 points and the The Walco point total was 82 out of the possible 100 points. Consequently, the evaluation committee recommended that Bundschu be awarded the lease. Mark Geisler, in his capacity as Subdistrict Administrator, for District VIII, concurred in this evaluation as may be seen in his November 6, 1981, transmittal of the bid materials and associated evaluation, which transmittal may be found as pert of the Hearing Officer's Composite Exhibit. The District Administrator, District VII, in the person of Frances Clendenin, who was acting for the District Administrator, Ivor D. Groves, Ph.D., also recommended acceptance of the Bundschu bid. This position was made known by a memorandum of November 16, 1981. A copy of that recommendation is found as a part of the Hearing Officer's Composite Exhibit. The recommendations spoken to thus far were made known to Lester C. Missman, an official within the Division of General Services of the Department of Health and Rehabilitative Services. This division was, at the time of the bid proposals, and is now, headed by Dr. Homer Ooten, whose function within Respondent's organization includes the responsibility to evaluate lease proposals involving the Respondent agency and to make a final decision on the question of the lease award, based upon a review of the local subordinate unit's recommendation. By this, it is meant that the lease by Health and Rehabilitative Services as "user agency" is signed by Ooten based upon a delegation of authority to him through the vehicle of correspondence signed by the agency head. Ooten, upon considering the recommendation of the District Administrator's office, the Subdistrict Administrator and the evaluation committee, did not find fault with the criteria nor the point weighing scheme used in the evaluation process. He did question the cost analysis performed by the evaluation committee on the subject of client mileage for those clients receiving services from Respondent in a move from the HRS office in the Bundschu building where they were located at the time, to the building where Walco intended to let property. This was a distance of seven/tenths (7/10) of a mile and based upon the number of clients receiving services, there would be an estimated $100,000.00 in client mileage cost increase. This item was not deemed to be an appropriate consideration by Ooten and was disregarded in his review of the cost analysis performed by the evaluation committee. That cost analysis may be found as part of Respondent's Composite Exhibit No. 2, and includes interlineations by Ooten in his opinion on the subject of the cost analysis. That analysis had indicated an overall advantage of approximately $11,000.00 in favor of Bundschu and was premised upon costs related to Item 12 in the criteria, which criterion is cost of moving. It assumed a difference of over $131,000.00 in moving costs, the majority of which costs pertained to client inconvenience ($100,000.00), discounting $120,000.00 plus dollars related to the difference in the bid amount between the Walco and Bundschu bids which bid estimate was in favor of Walco. Ooten's opinion on the subject of the priority of including $100,000.00 plus dollars in clients' travel costs, when considered in the context of point awards under Item 12 in the criteria, lead Ooten to believe that the differential in point awards would not result in a 9.25 value of Bundschu versus a zero value for Walco. In his mind, the differential would be much less. Ooten made his own evaluation of moving costs per se, and through that process determined that approximately $15,600.00 would be necessary for a move into the Walco facility whereas $5,600.00 would be involved in the Bundschu move, which required the expansion of existing space in the Bundschu facility. Based upon an evaluation of the point differential in the rental rate criterion which was a differential of 2, that is 30 points out of a possible 30 for Walco and 28 points out of a possible 30 for Bundschu, Ooten also opined the this was an unreasonable assessment in view of the fact that the Walco bid amount was more than $120,000.00 less than the Bundschu bid. This taken together with the fact that there only existed approximately a $9,000.00 difference on moving costs between Bundschu and Walco, which was in favor of Bundschu, and there having been indicated a 9.25 out of a possible 10 point difference in Item 12 on the question of costs related to moving, led Ooten to believe that the true factual status of criteria Nos. 1 and 12 was not as depicted by the evaluation committee. Per Ooten, with proper assessment Walco would have received a higher point count than Bundschu through the process of applying the bid criteria, as well as being the lower bidder from the point of view of rental rates alone. After several exchanges with the District level personnel of Respondent who had been involved in the lease evaluation process, in which, on two (2) occasions, the local officials continued to support their initial opinion of the propriety of the award to Bundschu, a decision was made at the District VIII level to support the award of the lease to Walco as may be seen in the January 6, 1982, correspondence from the District Administrator to Missman, a copy of which may be found as Respondent's Exhibit No. 4, admitted into evidence. On January 6, 1982, Ooten issued a letter to the District VIII Administrative Services Director indicating the authority to award Lease No. 590:8026, formerly referred to as No. 590:1472, for the benefit of Walter Lee Johnson d/b/a Walco Leasing Company. Having learned of this decision and in keeping with the provision Subsection 120.53(5), Florida Statutes, Bundschu, through counsel, indicated opposition to that award on January 12, 1982, followed by a formal petition letter setting forth grounds for the opposition, which petition was filed on January 19, 1982. This series of documents is part of the Hearing Officer's Composite Exhibit, through copies. Subsequently, Items 4 and 6 in the petition letter were resolved between the parties without the necessity of a hearing and this is borne out by a copy of the February 1, 1982, correspondence from counsel for the Respondent to counsel to the Petitioner, part of the Hearing Officer's Composite Exhibit. The matter was then referred to the Division of Administrative Hearings for a formal Subsection 120.57(1), Florida Statutes, hearing by correspondence from the Assistant General Counsel for Respondent, dated February 4, 1982, a copy of which may be found as a part of the Hearing Officer's Composite Exhibit. There followed the intervention of Walter Lee Johnson as a party of record and the hearing was held on April 27, 1982. Petitioner's first contention deals with the idea of discounting the lease value based on the value of the "stream of future lease payments." This theory is contended for through Robert Sizemore, C.P.A., expert witness of the Petitioner. He would call for the discount of lease payments on the theory that present dollars will have a discounted value in the future, as the lease period unfolds. Taking into account the method of payment by the Respondent and the vicissitudes involved in attempting to establish the value of today's dollar at a future time, this theory of discounted dollars at a 10 percent or 12 percent rate per annum in succeeding years is not indicated. Assessment through the legislative appropriations process of sufficient funds to meet lease payment demands is not contingent upon the value of the dollar at any given point in the history of the lease. Therefore, the "stream of future lease payments" concept is inapplicable here. Likewise, trying to project the value of today's dollar at some future date is so tenuous as to be an unacceptable method to evaluate the competing lease proposals. Finally, even if this method was used, a 10 percent discount rate for inflation would leave approximately a $67,000.00 difference in the bid proposals and a 12 percent per annum discount rate related to inflation would leave approximately $52,000.00 difference in the bid proposals, in favor of the Walco bid. Petitioner has contended that Respondent failed to properly account for direct moving expenses. In that regard, the calculations made by Ooten on the question of moving expenses as reported above are accepted as fact. As a third claim, Petitioner has alleged the agency s disregard for recommendation of its evaluation committee in making the lease award. While the initial recommendations of the evaluation committee and staff were disregarded, the District Administrator eventually accepted the point of view of the Division of General Services within the Respondent's Department. Moreover, even if the local officials within the Respondent's Department had not accepted Ooten's viewpoint, the initial evaluation committee's development of criteria was flawed and the Ooten perception was correct, leading to a decision in favor of Walco. Finally, the contention by Petitioner that the agency did not seek adequate input from third parties affected by the relocation of the facility was not demonstrated through testimony. The method for review of the proposed lease was acceptable and to the extent that it required an appreciation and response to the needs of others not directly involved in the lease process, it has been amply afforded. Evaluation was in keeping with Respondent's "Facilities, Acquisition and Management Manual, HRSM 70-1, fourth chapter" and the award is based upon concurrence of the Division Director of the General Services Division of HRS pursuant to that chapter. Through argument, counsel for the Petitioner has also referred to the fact that in the initial evaluation process set forth in the sixth criterion, superior points of 2.5 for Walco as opposed to 2.25 for Bundschu had been awarded, when in fact the narrative summary of the reasons for such awards indicate an advantage to Bundschu. Even if the .25 points were allowed in the favor of Bundschu, this would not change the result.

Florida Laws (3) 120.53120.57255.25
# 6
CARMON S. BOONE vs. DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 88-004900BID (1988)
Division of Administrative Hearings, Florida Number: 88-004900BID Latest Update: Jan. 05, 1989

Findings Of Fact Prior to June, 1988, HRS determined that it needed 32,000 square feet of office space to house some of its indigent social services for southern Escambia County. Since the desired office space is greater than 2,000 square feet HRS was required to competitively bid lease number 590:1984. Towards that end, Respondent prepared an Invitation to Bid and a bid submittal package. The package contained various bid specifications, bid evaluation criteria and the numerical weight assigned to each of those criteria. Specific areas of importance to Respondent in the selection of its office space were: client safety one building to house all its units employee morale moving costs traffic flow within the building public access Many of the above areas were important to HRS since the agency would render indigent services to approximately 17,000 people a month, many of whom are handicapped or lack good mobility due to age or infirmity. Employee morale was important because of high employee burn out due to rendering aid to so many people who have so little and supplying a pleasant environment conducive to the work of the employees. Moving costs were important should HRS be required to find other space to operate in while necessary remodeling took place in the selected building, or be required to incur the expense of moving to a new building. 1/ All of the above areas were covered by one of Respondent's weighted bid evaluation criteria. The District Administrator of HRS, Chelene Schembera, is ultimately responsible for bidding, selection and leasing of all HRS facilities within District I, including Escambia County, Florida. In order to accomplish this task, Ms. Schembera appointed a bid evaluation committee to review and grade the responsive bids under the criteria established in the bid package, and to recommend to her the committee's choice of the lowest and best bid. Ms. Schembera's purpose in establishing the bid evaluation committee was to secure a cross section of input from people who had a variety of backgrounds and knowledge that would be material in evaluating the office space under the uses for which it was intended and the relative public worth of the work space. Ms. Schembera appointed individual who were familiar with the type of work to be done in the proposed space, as well as a persons familiar with the bid process. Ms. Schembera assigned to serve on the committee Charles Bates, Deputy District Administrator; Jim Peters, to provide a fiscal and overall administrative perspective as well as bid expertise; two citizens from the District Advisory Council to assure objectivity and to look at the properties from the perspective of a private citizen; Mamun Rashied, a program manager; Darlene McFarland, a program manager; Cherie Neal, a unit supervisor and program worker; and Stacey Cassidy, a clerical employee. Ms. Schembera did not personally know Cherie Neal or Stacey Cassidy. These staff members were designated by the supervisors upon Ms. Schembera's direction that she wanted persons who were both intelligent and respected by their peers. One private citizen member of the committee did not participate. The committee as constituted showed a great deal of thought on Ms. Schembera's part to ensure the objectivity of the bid process she was engaging in and to ensure the maximum amount of input from persons who had experience relevant to the overall review of the proposed real estate and to the decision they were being asked to make. The selection of the bid evaluation committee members was neither an arbitrary nor capricious act on Ms. Schembera's part. In fact, the evidence demonstrated the merit in constituting the committee as she did for the input she sought. The bid evaluation committee members, minus Mr. Bates, were briefed on their duties by Joe Pastucha, Facilities Services Manager. Mr. Pastucha is part of the staff responsible for the bid process at HRS. He provided these committee members with the weighted bid evaluation criteria found at page 15 in the bid package. He also gave the committee members a copy of Chapter 5 of the HRS manual containing guidelines for the bid process. His verbal instructions on specific procedures to follow in the evaluation process were limited since he did not wish to improperly influence the committee members. On July 20, 1988, HRS received three bids responding to its invitation to bid on Lease Number 590:1984. Bid A was submitted by Phillips and Company, the apparent second lowest bidder and Intervenor in this case. Its property consisted of one multi-story building located at 1740 North Palafox Street, Pensacola, Florida. Bid B was not responsive and therefore was not considered by HRS and is not a part of this litigation. Bid C was submitted by Petitioner Carmon S. Boone, and was the apparent low bid. Mr. Boone's property consisted of two buildings located at 401 and 411 North Baylen Street, Pensacola, Florida. The Boone property is the present location of Respondent's offices. Both Bid A and Bid C were within the mandatory geographical area designated in the bid package. Once the bids were received the bid evaluation committee began its work. The committee members, minus Mr. Bates, visited the Phillips property. However, the members did not visit the Boone property. There was no need. Four of the members currently worked at the Boone property and the other members had previously visited the Boone property on various other occasions. Mr. Bates was likewise already familiar with both properties. All members were sufficiently familiar with the cogent aspects of each property to allow them to make a rational decision. The bid evaluation committee, minus Mr. Bates, met as a group to evaluate each property in accordance with the weighted bid evaluation criteria. Each individual scored their sheets separately and the general consensus was supportive of recommending the Phillips property. Five committee members scored Mr. Phillips' property higher than the Boone property. The one exception was Mr. Peters who felt that HRS could not support a bid awarded for other than monetary reasons, i.e., he felt the lowest bid had to be accepted. Mr. Bates later reviewed all the bid synopsis sheets of the committee members and discussed the bid award with Mr. Peters and Mr. Pastucha. Mr. Bates felt that the Phillips property was the lowest and best bid. At about the same time, the staff responsible for providing technical assistance to the committee and the District Administrator were made aware that the general consensus of the committee was leaning towards the second lowest bidder, Phillips and Company, as the lowest and best bid. The staff members, one of whom was a bid committee member, disagreed with the award of the bid to Phillips and Company because the Boone property was the lower bid. The staff members sought to head off the committee's intended recommendation. The staff personnel held a meeting with some of the committee members in order to get them to join in a recommendation to Ms. Schembera of the Boone property. Mr. Boone was invited and attended the meeting. He was allowed to improperly bolster his bid by agreeing to convert the two buildings to one and other lesser additions. /2 The potential decision was discussed, but no committee member changed his or her mind. However, through a total lack of communication, a run away staff somehow rationalized themselves into a position of being authorized to submit a letter for Ms. Schembera's signature which awarded the Boone property the lease. Ms. Schembera became aware of her staff's attempt to subvert the bid process she had established. She refused to sign the letter submitted by the staff. She removed the staff member of the committee as a voting member. The staff member had supported the Boone property. She also removed a committee member who supported the Phillips property as a voting member. Ms. Schembera feared that her staff had improperly influenced this member to such an extent that his objectivity had been affected. Both members could still participate in committee discussions. Ms. Schembera thereby reasonably ensured the ongoing objectivity of the bid evaluation committee. The committee was reconvened, minus one member. It recommended the Phillips and Company property. Every reason given by the individual committee members for distinguishing and preferring one bid over another were rational and reasonable considerations and were covered by the bid evaluation criteria. Each individual member gave a rational and reasonable basis for the scoring he or she used on the bid synopsis score sheets. The scoring was done by each member after discussion of the two buildings and without influence from the other committee members. In essence, the committee felt that the Phillips property was the better property for the money. The Phillips property allowed working units to be located in one area with each such unit having its own access. It provided flat safe parking areas and sidewalks, bigger and more elevators, wide halls and windows which presented a bright, happy and pleasant working environment. The Boone property was in two buildings which could not accommodate co-located working units with their own access no matter how much remodeling took place. Parking and sidewalks are on a hill which is slippery when wet. It had one small elevator and narrow halls which did not adequately accommodate more than one wheel chair, and one ground floor where no windows could ever be remodeled into the building leaving a dark, dingy and unpleasant environment. Importantly, every committee member except for the staff member came to the conclusion that the Phillips and Company property was the lowest and best bid. There is no statutory or rule requirement that one scoring method be preferred over another. The only requirement is that the method be rational and reasonable especially where highly subjective, but legitimate criteria are involved in the selection of a particular piece of property. On these facts, the individual scoring methods used by the individual committee members were not arbitrary and capricious, but were very rational and reasonably related to the relative importance the committee members gave the above factors. After reviewing and considering information from the bid evaluation committee, the information on the bid synopsis sheet, and the oral recommendations of Mr. Bates, Mr. Peters and Mr. Pastucha, Ms. Schembera concluded that the Phillips property was vastly better, even considering costs. She found it to be materially superior in terms of construction, organization, client accessibility, handicap accessibility, repairability (in terms of walls), and maneuverability for clients and staff. She felt the Phillips' building's qualities would offer more "humanity" to the process of serving the Department's clients. Additional facts she considered when making her decision included the morale of the staff and their productivity; the ability of staff and clients to conduct their business in a reasonably pleasant, comfortable, safe, and easy to understand and comprehend environment; and the desire to provide a minimally adequate work space. In addition to other monetary costs, she considered energy costs and life cycle costs as reflected on the bid synopsis sheet. The bid synopsis sheet defined minimal energy and life cycle costs to be anything less than 55 BTU's per square feet per year. In this case, the Boone property reflected 39.5 BTU's per square feet and the Phillips property reflected 53.5 BTU's per square feet. Both properties were under the 55 BTU cutoff established by HRS. Translated into monetary figures (life cycle costs) the Boone property reflected a cost of $26,735.00 and the Phillips property reflected a cost of $41,160.00. It was the difference between the energy figures which caught Ms. Schembera's eye. In her layman's opinion, it was incomprehensible that the two buildings would have such a wide divergence of energy costs. /3 She learned from her staff that the information used to compute these costs was supplied by the bidders who had vested interests in the outcome. Ms. Schembera concluded the cost difference was minimal and not of overriding concern in relation to the physical characteristics of the two buildings and how they compared to each other. She quite correctly felt the two buildings were not comparable. In essence, the two buildings' differences in design location and construction rendered neither building comparable to the other building as a like facility under Section 255.254, Florida Statutes. 4/ Based on that information she gave the energy figures relatively little weight. More importantly, however, before the final bid award was made by HRS, the Division of General Services within HRS in its failsafe role in reviewing bids considered the life cycle cost figures of the two bids. The minimal language of Section 255.254, Florida Statutes, has been interpreted by HRS to mean that anything under 55 BTU's is minimal and except in one instance not applicable here, numerical differences under 55 BTU's are immaterial. The Division, without getting into the issue of the likeness of the facilities, concluded that both bids met the Department's interpretation of the "minimal" language of Section 255.254, Florida Statutes, and the relative numerical difference in the energy costs was immaterial. Ms. Schembera is entitled to rely on other more expert HRS Division staff to ensure a proper analysis of highly technical bid specifications such as the energy cost analysis required under Section 255.254, Florida Statutes. It does not matter that the review took place after Ms. Schembera had made her preliminary decision. What is important is that the review be made either personal or vicariously through staff before the final award is made. A proper review of energy costs was, therefore, made by Respondent before the final award was made. Likewise, Ms. Schembera's ultimate decision that the buildings were not comparable like facilities was a proper review of energy costs even though that conclusion was arrived at through a layman's unsophisticated, but more accurate intuition and common sense. To that extent, the energy cost data had no impact on the ultimate choice made by the District Administrator and were properly considered by the District Administrator. 5/ A letter for Ms. Schembera's signature adopting the committee's recommendation was drafted by Mr. Pastucha. The letter was signed and sent to the Department's Division of General Services for review. The District was requested to provide additional justification for its choice by the Department's Division of General Services. Mr. Rashied was directed to draft the response. He simply reorganized the original memorandum into a format more compatible with the Division's direction, clarified a few points and without significantly changing the content, submitted the response as directed. The Division acquiesced in Ms. Schembera's decision.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Department of Health and Rehabilitative Services enter a final order dismissing Case NO. 88-4900BID, and awarding lease number 590:1984 to Phillips and Company as the lowest and best bidder. DONE and ORDERED this 5th day of January, 1989, in Tallahassee, Florida. DIANE CLEAVINGER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of January, 1988.

Florida Laws (5) 120.53120.57255.25255.254255.255
# 7
ANTHONY P. CAMINITE vs. DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 82-003385 (1982)
Division of Administrative Hearings, Florida Number: 82-003385 Latest Update: May 12, 1983

Findings Of Fact Respondent invited bid proposals for a "collocated service center" in Manatee County, providing approximately 25,500 square feet of office space. The invitation sought a "turnkey lease" for an initial period of 15 years and permitted the bidder a choice of providing "full services" (option 1) or "full services without electrical" (option 2). Petitioner submitted his bid under option 2, while the successful bidder, Dr. Kenneth R. McGurn, selected option 1. Their bid proposals, along with others not relevant here, were forwarded to a bid review committee. Committee members were generally knowledgeable as to Respondent's operations and bid evaluation procedures, but were given no specific instructions on how to conduct their evaluations. Each of the four committee members evaluated the bids and assigned points in 12 separate categories. The evaluation criteria to be utilized were set forth in the bid proposal (page 12, Joint Exhibits 3 and 4). The greatest weight was to be given in category number 1, "Rental rate including projected operating expenses to be paid by lessee." The testimony of the bid evaluation committee members established that McGurn, rather than Petitioner, was the successful bidder primarily because his proposal included electrical service. The committee members did not individually or collectively seek assistance in projecting future electrical costs when making their determination as to the award of points in bid category number 1. Rather, they used their own judgment and experience to estimate possible costs and award rental and service expense points accordingly. Three of the four evaluators generally felt that known electrical costs were preferable to unknown costs for budget purposes even though Petitioners's proposal may ultimately have been less expensive. Site characteristics were factors in several of the categories for which points were to be assigned. Committee members visited the proposed sites and rated Petitioner's site somewhat higher than McGurn's. Proper zoning of the site was not included in the bid criteria. 1/ Petitioner's site is properly zoned while McGurn's is not. McGurn's potential difficulties in obtaining a zoning change and with utility service to his site led him to inquire of Respondent whether he would be permitted to change sites if he received the contract award. Respondent advised him that he could do so if there was a persuasive reason for the change. Petitioner obtained an option on the site he proposed to utilize and renewed it for 30 days when Respondent did not act on its bid within the announced period. 2/ This extension cost Petitioner the forfeiture of his $2,000 deposit but did not carry him through to the actual bid award date, November 4, 1982. Respondent's memorandum (Petitioner's Exhibit 2) dated September 14, 1982, indicates that Respondent had already decided to award the contract to McGurn by that date. Had Petitioner been advised of this decision, he could have saved the $2,000 expended to extend his option. During the period prior to the official announcement of bid award, McGurn became aware that he was the probable successful bidder and acquired Petitioner's site after the latter's renewal option expired. McGurn obtained this property for the purpose of substituting it for his proposed site after he received the contract. He has not yet requested site substitution.

Recommendation Based on the foregoing, it is RECOMMENDED: That the Respondent enter a Final Order setting aside the award of the subject contract and reissuing its bid proposal. DONE and ENTERED this 12th day of May, 1983, in Tallahassee, Florida. R. T. CARPENTER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of May, 1983.

Florida Laws (1) 255.25
# 8
MARPAN SUPPLY COMPANY, INC. vs DEPARTMENT OF MANAGEMENT SERVICES, 96-002777BID (1996)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jun. 11, 1996 Number: 96-002777BID Latest Update: Nov. 26, 1996

The Issue The issue for determination is whether Respondent acted fraudulently, arbitrarily, illegally, or dishonestly in selecting Intervenor as the lowest bidder for a contract to supply the state with lamps valued at $3,692,499.

Findings Of Fact The Parties Respondent is the state agency responsible for soliciting bids to establish a contract for the purchase of large lamps by state agencies and other eligible users. Petitioner is a Florida corporation and the incumbent vendor under similar contracts for the preceding 10 years. Petitioner does not manufacture lamps. Petitioner sells lamps manufactured by Osram-Sylvania ("Sylvania"). Intervenor is an Ohio corporation doing business in Florida. Intervenor manufactures the lamps it sells. The ITB On March 15, 1996, Respondent issued Invitation To Bid Number 39-285- 400-H, Lamps, Large, Photo and STTV (the "ITB"). The purpose of the ITB is to establish a 24 month contract for the purchase of Large Lamps (fluorescent, incandescent, etc.), Photo Lamps (audio visual, projection, flash), and Studio, Theatre, Television, and Video Lamps ("STTV") by state agencies and other eligible users. The contract runs from July 10, 1996, through July 9, 1998. The ITB estimates the contract price at $3,692,499. The ITB contains General and Special Conditions. General Conditions are set forth in 30 numbered paragraphs and elsewhere in DMS Form PUR 7027. Special Conditions are set forth in various unnumbered paragraphs in the ITB. General Conditions Paragraphs 5, 11, and 24 of the General Conditions are at issue in this proceeding. The terms of each paragraph are: 5. ADDITIONAL TERMS AND CONDITIONS: No additional terms and conditions included with the bid response shall be evaluated or considered and any and all such additional terms and conditions shall have no force and effect and are inapplicable to this bid. If submitted either purposely through intent or design or inadvertently appearing separately in transmittal letters, specifications, literature, price lists, or warranties, it is understood and agreed the general and special conditions in this bid solicitation are the only conditions applicable to this bid and the bidder's authorized signature affixed to the bidder's acknowledgment form attests to this. 11. QUALITY ASSURANCE: The contractor, during the contract term, upon mutual agree- ment with the Division of Purchasing, will provide reasonable travel and lodging accommodations for one (1) to three (3) government employees to perform an on-site inspection of the manufacturing process(es) and review of the manufacturer's product quality control(s) and total quality manage- ment program(s). The contractor will reim- burse the State for actual transportation cost, per diem and incidental expenses as provided in Section 112.061, F.S. It is the State's desire that the contractor provide demonstration of quality control for improvement rather than post production detection. 24. FACILITIES: The State reserves the right to inspect the bidder's facilities at any reasonable time with prior notice. Included Items Special Conditions in the ITB require bidders to submit prices for "Item 1" and "Item 2" lamps ("included items"). 1/ Item 1 lamps consist of Group 1 and 2 lamps. Group 1 lamps are Large Lamps such as fluorescent, incandescent, quartz, mercury vapor, metal halide, and high-pressure sodium lamps. Group 2 lamps are Photo Lamps such as audio visual, projection, flash, and STTV lamps. The total price for each group is multiplied by a weighted usage factor. The product calculated for Group 1 is added to the product calculated for Group 2 to determine the total price for Item 1 lamps. Item 2 consists of a category of lamps described as "T- 10 Lamps." The total price for Item 2 lamps is determined without application of the weighted usage factor used for Item 1 lamps. The total price for Item 2 lamps is a de minimis portion of the contract price. Special Conditions in the ITB require Respondent to award a single contract for included items to a single bidder. Special Conditions state that, "During the term of the contract established by this bid, all purchases of items will be made from the successful bidder." 2/ Excluded Items Special Conditions require that, "The bidder shall offer a fixed discount from retail prices on all excluded items." Excluded items include high technology lamps. The requirement for a fixed discount on excluded items is not considered in evaluating bid prices for included items. Rather, the requirement is intended to reduce the state's cost for both included and excluded items by assuring a meaningful discount on excluded items. Formatting Requirements Special Conditions prescribe the format in which bids must be submitted. Price lists and authorized dealers' lists are required to be submitted in hard copy and on computer diskette. The format prescribed for computer diskette includes requirements for font and graphics. The Special Conditions state that, "Failure to comply with this requirement will result in disqualification of your bid." The Bids The ITB prohibits the alteration of bids after they are opened. Respondent opened bids on April 10, 1996. Seven vendors submitted bids in response to the ITB. Included Items Four vendors, including Petitioner, submitted a bid for both Item 1 and Item 2 lamps. Intervenor and two other bidders did not submit a bid for Item 2 lamps. General Conditions Intervenor deleted paragraphs 11 and 24 of the General Conditions from its bid. At the direction of Intervenor's legal department in Cleveland, Ohio, Intervenor's regional sales manager struck through paragraphs 11 and 24 and initialed the deletions. The deletions are consistent with Intervenor's corporate policy. Intervenor routinely objects to contract provisions requiring inspection of Intervenor's facilities. Excluded Items Petitioner's bid includes a fixed discount of 44 percent on excluded items. Intervenor's bid includes a fixed discount of 0 percent. Formatting Requirements Intervenor included the information required by the ITB on the diskette it submitted with its bid. However, Intervenor supplied the information in Courier 12 characters per inch ("cpi") font, not the Courier 10 cpi font prescribed in the ITB. Proposed Agency Action Respondent determined that Intervenor's bid was responsive. The purchasing specialist for Respondent who reviewed each bid to determine if it was responsive failed to observe the deleted paragraphs in Intervenor's bid. The purchasing specialist forwarded those bids determined to be responsive to the purchasing analyst assigned by Respondent to: determine if the lamps offered in each bid met the specifications prescribed in the ITB; and evaluate bid prices. The purchasing analyst noted that paragraphs 11 and 24 were deleted from Intervenor's bid. The purchasing analyst and purchasing specialist conferred. They determined that paragraph 5 of the General Conditions cured Intervenor's deletions without further action. The purchasing analyst correctly determined: that lamps offered by Petitioner and Intervenor met ITB specifications; that Intervenor's bid is the lowest bid for Item 1 lamps; that Petitioner's bid is the second lowest such bid; and that Petitioner's bid is the lowest bid for Item 2 lamps. Petitioner's bid for Item 1 lamps is approximately five percent greater than Intervenor's bid. Respondent proposes to award one contract for Item 1 lamps to Intervenor. Respondent proposes to award a second contract for Item 2 lamps to Petitioner. At 4:00 p.m. on May 20, 1996, Respondent posted its intent to award the contract for Item 1 lamps to Intervenor. Petitioner timely filed its formal protest on June 3, 1996. Respondent did not award a contract for excluded items. Respondent's failure to award a contract for excluded items is not at issue in this proceeding. Arbitrary Respondent's proposed award of a contract to Intervenor for substantially all of the items included in the ITB is a decisive decision that Respondent made for reasons, and pursuant to procedures, not governed by any fixed rule or standard prescribed either in the ITB or outside the ITB. Respondent's proposed agency action is arbitrary. Excluded Items The requirement for bidders to offer a fixed discount on excluded items operates synergistically with the requirement for Respondent to award a single contract on included items to a single bidder. The combined action of the two requirements operating together has greater total effect than the effect that would be achieved by each requirement operating independently. The requirement for a fixed discount on excluded items, operating alone, may not induce a bidder who could receive a contract solely for Item 2 lamps to offer a discount that is as meaningful as the discount the bidder might offer if the bidder were assured of receiving a contract for Item 1 and 2 lamps upon selection as the lowest bidder. 3/ By assuring bidders that a single contract for Item 1 and 2 lamps will be awarded to a single bidder, the ITB creates an economic incentive for bidders to provide a meaningful discount on excluded items. Respondent frustrated the synergy intended by the ITB by applying the requirements for a fixed discount and for a single contract independently. Respondent penalized the bidder conforming to the requirement for a fixed discount on excluded items by awarding only a de minimis portion of the contract to the bidder. Respondent rewarded the bidder not conforming to the requirement for a fixed discount on excluded items by awarding substantially all of the contract to that bidder. If Respondent elects to purchase all excluded items from Petitioner, Respondent will have used the contract for Item 1 lamps to induce a meaningful discount from Petitioner without awarding Petitioner with the concomitant economic incentive intended by the ITB. Such a result frustrates the ITB's intent. Paragraph 5 Respondent's interpretation of paragraph 5 fails to explicate its proposed agency action. Respondent's interpretation of paragraph 5: leads to an absurd result; is inconsistent with the plain and ordinary meaning of the terms of the ITB; and is inconsistent with Respondent's actions. Respondent's interpretation imbues paragraph 5 with limitless curative powers. Respondent's interpretation empowers paragraph 5 to cure the deletion of all General Conditions in the ITB whether stricken by pen or excised with scissors. Respondent's interpretation of paragraph 5 would transform a bid containing no General Conditions into a responsive bid. Respondent's interpretation of paragraph 5 is inconsistent with the plain and ordinary meaning of its terms. Paragraph 5 operates to cure "additional" terms. It does not operate to restore deleted terms. Respondent's interpretation of paragraph 5 is inconsistent with Respondent's actions. Respondent did not rely on paragraph 5 to cure Intervenor's deletions without further action. Respondent took further action to cure the deletions. Further Action On the morning of May 20, 1996, the purchasing analyst for Respondent telephoned Intervenor's regional sales manager. The purchasing analyst demanded that Intervenor accept the conditions Intervenor had deleted from its bid by submitting a letter of acceptance before the bid tabulations were posted at 4:00 p.m. on the same day. The regional sales manager contacted Intervenor's corporate headquarters in Cleveland, Ohio. Intervenor authorized the regional sales manager to accept the deleted paragraphs. By letter faxed to Respondent at approximately 3:20 p.m. on May 20, 1996, Intervenor accepted the paragraphs it had previously deleted. The letter stated that, "GE Lighting [will accept] the Contract Conditions noted in Paragraphs 11 and 24 of the Lamp Quotation." [emphasis not supplied] At 4:00 p.m. on May 20, 1996, Respondent posted the bid tabulation form. The bid tabulation form stated that the "award is contingent upon General Electric's acceptance of all the terms in conditions (sic)" in the ITB. Respondent argues that the purchasing analyst who contacted Intervenor on the morning of May 20, 1996, exceeded her authority. Respondent characterizes the word "contingent" in the bid tabulation form as "poorly written" and a "bad word." Agency Construction Of ITB Terms Respondent construes terms in the ITB in a manner that is inconsistent with their plain and ordinary meaning. The ITB requires that, "The bidder [shall] offer a fixed discount from retail price list on all excluded items." [emphasis supplied] Respondent interprets the quoted provision as meaning the bidder may offer such a fixed discount if the bidder elects to do so. The purpose of the ITB is to establish "[a] 24 month contract" to supply large lamps to the state. [emphasis supplied] Respondent interprets the quoted provision as meaning that the purpose of the ITB is to establish two contracts. The ITB states that, "During the term of the contract established by this bid, all purchases of items [will] be made from [the] successful bidder." [emphasis supplied] Respondent interprets the quoted provision as meaning that purchases of some items will be made from one successful bidder and that purchases of other items will be made from a second successful bidder. The ITB states that the contract "[shall] be made statewide on an all or none basis" to the responsive bidder who satisfies the conjunctive requirements for: "[the] lowest "Award Figure Item (1; [and] lowest Award figure for Item (2." [emphasis supplied] Respondent interprets the quoted provision as meaning that separate contracts may be made statewide on less than an all or none basis to separate responsive bidders who satisfy the disjunctive requirements for either the lowest bid for Item 1 lamps or the lowest bid for Item 2 lamps, or both. The ITB requires offers to be submitted for all items listed within a group for a bid to qualify for evaluation. Respondent interprets the requirement as meaning that a bidder who does not qualify for evaluation for all of the groups in the contract nevertheless qualifies for evaluation for the contract. Finally, the ITB states that failure to comply with the formatting requirements for the diskette "[will] result in disqualification of your bid." [emphasis supplied] Respondent interprets the quoted language to mean that failure to comply with prescribed formatting requirements may result in disqualification of a bid. The interpretations of the quoted terms proposed by Respondent, individually and collectively, frustrate the purpose of the ITB. They also ignore material requirements of the ITB. Material Deviation Respondent deviated from the rule or standard fixed in the ITB in several respects. First, Respondent altered the bid evaluation procedure prescribed in the ITB. Second, Respondent ignored the requirement to award a single contract to a single bidder. Third, Respondent ignored the requirement that bidders provide a fixed discount on excluded items. Fourth, Respondent ignored the requirement to comply with the formatting requirements prescribed in the ITB. Each deviation from the rule or standard fixed in the ITB is a material deviation. Each deviation gives Intervenor a benefit not enjoyed by other bidders. Each deviation affects the contract price and adversely impacts the interests of Respondent. 4/ 5.5(a) Benefit Not Enjoyed By Others Intervenor enjoyed a benefit not enjoyed by other bidders. Intervenor obtained a competitive advantage and a palpable economic benefit. Respondent altered the bid evaluation procedure prescribed in the ITB. On the morning of May 20, 1996, Respondent disclosed the bid tabulations to Intervenor alone, 5/ gave Intervenor an opportunity that lasted most of the business day to determine whether it would elect to escape responsibility for its original bid, allowed Intervenor to cure the defects in its bid, accepted Intervenor's altered bid, and conditioned the bid tabulations on Intervenor's altered bid. Respondent used a bid evaluation procedure that is not prescribed in the ITB and did not allow other bidders to participate in such a procedure. 6/ In effect, Respondent rejected Intervenor's initial bid, with paragraphs 11 and 24 deleted, and made a counter offer to Intervenor to accept a bid with paragraphs 11 and 24 restored. Intervenor accepted Respondent's counter offer. Respondent excluded other bidders from that process. Respondent gave Intervenor an opportunity to determine whether it would elect: to escape responsibility for its original bid by declining Respondent's counter offer; or to perform in accordance with an altered bid by restoring paragraphs 11 and 24. A bidder able to elect not to perform in accordance with its bid has a substantial competitive advantage over other bidders unable to escape responsibility for their bids. 7/ Respondent awarded substantially all of the contract to Intervenor even though Intervenor failed to provide a meaningful discount on excluded items. Respondent provided Intervenor with a palpable economic benefit. 5.5(b) Bid Price And Adverse Impact On The State Respondent did not award a contract for excluded items. Respondent's proposed agency action allows Respondent to purchase excluded items from either Intervenor or Petitioner. If Respondent were to purchase all of the excluded items it needs from Intervenor, Respondent could pay substantially more for excluded items than Respondent would save from the five percent price advantage in Intervenor's bid for Item 1 lamps. In such a case, Respondent's proposed agency action would effectively increase costs to the state that are inherent, but not stated, in the ITB. 8/ Conversion of incorrectly formatted data to the required font shifts prices to incorrect columns and causes other problems in accessing information in the diskette. Such problems can not be rectified easily but require substantial time and effort. Responsive Bidder Respondent did not award the contract intended by the ITB to the lowest responsive bid. Although Intervenor's bid is the lowest bid for Item 1 lamps, it is not the lowest responsive bid for Item 1 and 2 lamps. Petitioner's bid is the lowest responsive bid for Item 1 and 2 lamps. 9/ Respondent is statutorily required to award the contract to the lowest responsive bidder. 10/ Illegal Intervenor's bid is not responsive within the meaning of Sections 287.012(17), Florida Statutes (1995). 11/ It does not conform in all material respects to the ITB. Intervenor's unaltered bid deletes paragraphs 11 and 24. It does not include a fixed discount on excluded items, does not include a bid for Item 2 lamps, and does not conform to the formatting requirements in the ITB. Section 287.057 requires Respondent to award the contract to the bidder who submits the lowest responsive bid. Respondent has no authority either: to consider bids that are not responsive; or to award the contract to a bidder other than the lowest responsive bidder. Respondent's attempt to engage in either activity is ultra vires and illegal. Minor Irregularities The ITB encourages, but does require, bidders to include quantity discounts for Item 1 and 2 lamps. Petitioner's bid does not include quantity discounts. Petitioner's bid does not fail to conform to material requirements in the ITB. Petitioner does not manufacture Item 1 and 2 lamps. Sylvania manufactures the lamps Petitioner sells. Petitioner has no legal right to require Sylvania to allow inspection of its facilities pursuant to paragraph 11 of the General Conditions. Petitioner's ability to provide the requisite inspections requires the cooperation of Sylvania. Petitioner's bid requires payment by the state within 30 days of an invoice. Section 215.422 and the ITB provide that Respondent has 40 days to issue warrants in payment of contract debts and that interest does not accrue until after 40 days. The defects in Petitioner's bid are minor irregularities within the meaning of Florida Administrative Code Rule 60A-1.001(16). 12/ They neither affect the bid price, give Petitioner a competitive advantage, nor adversely impact Respondent's interests. Petitioner has the practical ability to arrange inspection's of Sylvania's facilities. Petitioner is legally responsible for failing to do so. Respondent's employees have never visited Sylvania's facilities during the 10 years in which Petitioner has been the contract vendor to the state. The requirement for payment within 30 days does not obviate the provisions of Section 215.422. Private contracts can not alter mutually exclusive statutory provisions.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent enter a Final Order granting Petitioner's protest of Respondent's proposed agency action. RECOMMENDED this 26th day of September, 1996, in Tallahassee, Florida. DANIEL S. MANRY, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of September, 1996.

Florida Laws (6) 112.061120.57215.422287.001287.012287.057 Florida Administrative Code (1) 60A-1.001
# 9
R. A. M. PLANT GROWERS, INC. vs DEPARTMENT OF TRANSPORTATION, 92-000169BID (1992)
Division of Administrative Hearings, Florida Filed:Miami, Florida Jan. 13, 1992 Number: 92-000169BID Latest Update: Apr. 16, 1992

Findings Of Fact Nine bids were received for Contract E4571, Project/Job No. 99004-3516 ("E4571"). Petitioner's bid was timely received. Respondent opened bids on December 13, 1991. Respondent posted its intent to award E4571 to J & D Tropical Landscape Design on December 20, 1991. Section 1.2 of the Bid Specifications for E4571, as modified by the Special Provisions, states: A contractor's bid shall be in the form of a unit price for each unit expected to be accomplished. The Special Provisions to E4571 require each bidder to submit a single unit price for each pay item called for in the Bid Price Proposal. Item 4 in the Special "Provisions provides: It shall be the responsibility of the Contractor to submit to the Department A SINGLE unit price for each pay item called for in the Bid Price Proposal. The Contractor shall be responsible for his/her method of averaging. Failure to comply shall result in the Contractor's Bid Proposal being declared "Irregular" and such Bid Proposals will be rejected. (emphasis added) Petitioner's Bid Proposal was properly declared irregular and rejected by Respondent. Petitioner failed to comply with the requirements of Item 4 in the Special Provisions by failing to submit a single unit price for each pay item, by failing to correctly average a unit price, and by failing to state the unit price in words. The Unit Price Sheet on page 23 of the Bid Proposals contains the following table listing item numbers A582- 2 through A584-4. Petitioner listed item number A583 as follows: ITEM PLAN ITEM DESCRIPTION AND UNIT PRICE $ AMOUNTS NUMBER QUANTITIES UNIT PRICE (IN FIGURES) (Exten- (IN WORDS) sion Price) 3/ A583 4 200.000 TREES (8' TO 20, 85 20400 PLANT ' HEIGHT OR CLEAR TRUNK) @ DOLLARS CENTS The actual extension price 4/ for 200 trees at $85 per unit is $17,000 rather than the $20,400 stated by Petitioner in the table on page 23. The "Contract Total" stated by Petitioner in the bottom right corner of the table is $37,013.20. The "Contract Total" that should have been stated if Petitioner intended the extension price of item number A583-4 to be $17,000 would have been $33,613. The "Contract Total" listed by a bidder on the Unit Price Sheet is the unverified contract price. The actual contract price is determined by Respondent pursuant to the formula given in Section 1.3 of the Bid Specifications. Section 1.3 of the Bid Specifications foil E4571 states: The contract price is defined as the sum of the unit bid price times the planned work for each item as shown on the Unit Price Sheet. Petitioner would have been the lowest successful bidder irrespective of whether Respondent had replaced the extension price for item number A583-4 and the "Contract Total" stated by Petitioner with the actual extension price for item number A583-4 and the actual "Contract Total" . However, Respondent is precluded from doing so by Section 3-1 of the Standard Specifications For Road ,and Bridge Construction ("Standard Specifications"), published by the Florida Department of Transportation (1991) and by the Special Provisions for E4571. Respondent follows "Section 3-1 of the Standard Specifications for the purpose of evaluating bid proposals. Section 3-1 is used, in part, to determine the extension price for item numbers listed on the Unit Price Sheet. Section 3- 1 provides in relevant part: In the event of any discrepancy in the three entries for the price of any item, the unit price as shown in words shall govern unless the extension and the unit price shown in figures are in agreement with each other, In which case they shall govern over the unit price shown in words. Petitioner did not show the unit price in words for any item number on the Unit Price Sheet, including item number A583-4. There is a discrepancy in the three entries for item number A583-4 on the Unit Price Sheet. Petitioner failed to show the unit price for item number A583-4 in words, and the unit price and extension price are not in agreement. Under such circumstances, Respondent interprets Section 3-1 of the Standard Specifications as requiring that Petitioner's bid be declared irregular and rejected. Respondent's interpretation of Section 3-1 of the Standard Specifications is reasonable and is consistent with the mandate in Item 4 of the Special Provisions for E4571. See Finding 4, supra. Furthermore, in practice, the correct unit price of a pay item is necessary to process payment under the contract and the contractor must submit invoices based upon the pay items and unit prices listed in its bid. The bid specifications for E4571 provide that a bidder is responsible for his or her own averaging of a stated unit price, and that if a bidder fails to provide a single unit price for each pay item on the Unit Price Sheet the bid shall be declared "Irregular" and will be rejected. The requirement to provide a single unit price for each pay item was emphasized by Respondent at the mandatory pre-bid meeting. Petitioner's representative attended the mandatory pre-bid meeting. No challenges were made to the bid specifications by any bidder.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent enter a Final Order dismissing the protest filed by Petitioner. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 20th day of February, 1992. DANIEL MANRY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (964) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of February, 1992.

Florida Laws (2) 120.57337.11
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer