The Issue The issue in this proceeding is whether the Respondent, the Department of Insurance, acted illegally, arbitrarily, fraudulently, or dishonestly in rejecting all bids for lease #460:0119 and not awarding subject lease to Petitioner.
Findings Of Fact The Department of Insurance established a requirement to lease 5371 square feet of office space in Daytona Beach, Florida, and a "Request for Space Need" was approved by the Department of Management Services on February 11, 1998. The Department of Insurance subsequently issued a Request for Proposal (RFP) for lease #460:0119 (Respondent's Exhibit 1). A non-mandatory pre-bid conference was held on June 1, 1998, in Daytona Beach and two prospective bidders, Petitioner and Nova Village Market partnership attended. The RFP provided that proposals which did not meet all mandatory requirements of the RFP would be rejected as non- responsive. The RFP provided for evaluation criteria are awards factors. The awards factors totaled 100 points with no minimum point total required. Ten of the points were allotted for moving costs defined as the costs of relocating communications, networks, furniture and other equipment. This factor gave the current landlord an automatic 10-point advantage since there would be no relocation costs. Moving costs provisions tend to discourage the presentation of bids because the bidders have to overcome an automatic 10-point advantage provided the current landlord. The RFP also provided that all proposals could be rejected, however, such "rejection shall not be arbitrary, but be based on strong justification." None of the conditions of the RFP were questioned or challenged by interested parties. Two responses were received by the Department of Insurance in response to the RFP and these were opened in Respondent's Tallahassee office on July 8, 1998, by Mr. Kip Wells of the Department. One was received from the current landlord, Nova Village Partnership, hereafter Nova, and the other from the Petitioner. The Nova proposal was deemed non-responsive. Neither Nova nor Petitioner contested the determination that Nova's proposal was non-responsive. Only one responsive proposal, the Petitioner's proposal, remained. On July 9, 1998, the Department representative, Mr. Kip Wells, called Petitioner to schedule an appointment for 9:00 a.m., on July 10, 1998, to visit and evaluate the proposed facility. No persons from the Department appeared at the scheduled appointment. At 10:45 a.m., on July 10, 1998, Kip Wells called Petitioner to say that since Petitioner's proposal was the only responsive proposal received, and that "all bids" were being rejected. Mr. Wells testified at hearing. His reason for rejecting the remaining bid was: When I saw that it was obvious the current landlord was not going to be very cooperative, I decided that one choice was not enough. If we were going to have to make a move, we needed more than one thing to choose from. So, I immediately - - since I had already set up with local people in Daytona to tell them that I was coming down to evaluate the bids, I sent them an E-mail and told them that I would not be meeting the following day to evaluate the bids. Mr. Wells decided to reissue the RFP without any moving costs criteria, and redistribute those 10 points among the other award factors. Petitioner filed a Notice of Intent to Protest and then a Formal Protest, both in a timely fashion. There is no state policy prohibiting the award of a lease to a sole bidder on a RFP. The "Leasing Policy" of the Department of Insurance states that "The Lease Administrator, with assistance from the Division employees, will establish bid or quote specifications. These specifications will include special needs for the Division(s) as well as the evaluation criteria upon which to evaluate the proposals." Neither the Department's Lease Policy (Petitioner Exhibit 3) nor the State's Real Property Leasing Manual (Petitioner's Exhibit 4) give the Lease Administrator the authority to reject or evaluate bid responses. Neither does he have a vote in the bid evaluation process. His responsibility is to coordinate the process. Randall Baker, Manager of Private Sector Leasing of the Bureau of Property Management of the Department of Management Services (hereinafter DMS), testified. The DMS prepares a manual as a guideline for user agencies to assist in the leasing of property. The DMS manual is not binding on agencies and DMS has no review oversight; however, their comments on agencies' leases are reviewed by the state auditing authorities and failure to follow the guidelines can result in audit criticism. Baker confirmed that the agency's written procedures as outlined in the RFP were consistent with the DMS guidelines. The DMS manual states as follows regarding the receipt of only one responsive proposal: When only one responsive proposal is received it may be considered and accepted providing the following conditions are documented: Adequate competition was solicited. The rate is within established rental rate guidelines. The proposal meets stated requirements. The proposal was processed as though other proposals were received. The Petitioner's bid was responsive to the RFP and the lease rate bid by the Petitioner was less than the average rate for state leases in the Daytona area and less than the amount budgeted by the Department for this lease. The lease rate by the Petitioner was reasonably priced and competitive. Although the agency failed to complete the process as envisioned, see paragraph 20 below, this was in no way the fault of Petitioner. The Department's leasing policy requires that the lowest and best response to an RFP be determined through cost analysis and evaluation by an evaluation committee. Mr. Wells did not forward Petitioner's bid to or discuss with the evaluation committee Petitioner's bid, but unilaterally rejected it. It was clear from Mr. Wells' testimony that this was his individual decision and was based upon his personal belief that it was the best thing to do.1 At hearing, the stated justification for rejecting "all bids" was that it gave the Department the opportunity to delete the requirement of moving costs from the awards factors; however, the evidence does not indicate that the moving cost provision result in non-competitive bids. The sole responsive bidder was within the local lease price range and within budget. Neither the Respondent nor DMS has established a policy prohibiting the acceptance of a sole responsive bid if there is competition solicited. The Department of Insurance has accepted a sole bid on at least one project in the past. There was no evidence that the RFP was not an open and fair competition. The evidence shows that it was properly advertised, that all conditions were known, and that all interested parties had an equal opportunity to participate. In sum, there was adequate competition in submitting the bids. Mr. Baker testified regarding the policy of DMS. The DMS policy is that if there is one responsive bidder, there has been competitive bidding. The RFP provides that the Respondent may reject all bids if it has strong justification. See paragraph 5 above. Mr. Baker also provided examples of "strong justification for rejecting proposals." His examples include facilities which are proposed outside the required geographic area, prices considerably in excess of state guidelines and agency budgets, specification changes due to modification of the agency's program requirements, and "intervening external forces." No evidence establishing a strong justification for rejecting the Petitioner's bid was presented. Without completing the process and evaluating the Petitioner's bid, the agency never considered whether the bid was in the state's best interest. However, this was not the fault of the Respondent, and the agency's failure to follow its procedures should not inure to its benefits. Further, Because there was no minimum score required on the evaluation criteria of the RFP, there is no need to evaluate Petitioner's proposal because it is the only responsive proposal. For all the reasons stated above, the rejection of Petitioner's bid was contrary to the terms of the RFP, contrary to state policy, and arbitrary.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is, RECOMMENDED: That a Final Order be entered which finds that: Respondent's actions in rejecting Petitioner's responsive bid were arbitrary; The Respondent did not follow the requirements set forth in the Department of Insurance Leasing Policy, nor the Department of Management Services Real Property Leasing Manual, or the Request for Proposal itself; That no adverse interest to the State or the Department would have occurred had Petitioner's responsive bid been accepted; and therefore, Petitioner's claim shall be upheld as the lowest cost and best proposal for RFP #460:0119, and that the Department of Insurance shall award Petitioner Lease #460:0119. DONE AND ENTERED this 30th day of October, 1998, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 30th day of October, 1998.
Findings Of Fact In August, 1975, the Department of General Services invited competitive bids for the purchase of supervisory and control equipment and revenue metering equipment for expansion of primary electric utilities in the Capitol Center, a project known as State Project No. DGS-6026/6424, AEP File No. 74288-003. Plans and specifications for the project were developed by the department's consulting architect/engineers Reynolds, Smith and Hills. The Department of General Services (hereinafter Department) and Reynolds, Smith and Hills (hereinafter Reynolds) conducted formal bid opening on September 25, 1975. Bid proposals were received from petitioner, Weston Instruments, Inc. (hereinafter Weston), and from Respondents, Harris Corporation (hereinafter Harris) and Hathaway Instruments, Inc. (hereinafter Hathaway). The amount of the bids were as follows: CONTRACTOR BASE BID ALTERNATE NO. 1-ADD TOTAL Harris 332,000.00 28,649.00 360,649.00 Weston 338,991.00 20,965.00 359,996.00 Hathaway 343,429.00 33,224.00 376,653.00 Hathaway's bid as submitted was responsive to the specifications and other requirements of the bid invitation. Weston's bid was responsive to the specifications and requirements of the bid invitation with the following exception. Specification B-2, in its second paragraph, states: "In order to facilitate the execution of the Agreement, the Bidder shall submit with his proposal a list of and brief description of similar work satisfactorily completed, with location, date of contracts, together with names and addresses of Owners." Weston did not submit that information with its bid but did submit that information on October 9, 1975. The Harris bid as submitted was not responsive to the specifications and requirements of the bid invitation. The material deviations from the specifications found in the Harris bid are as follows: Paragraph 16755-13(c) of the specifications states that data logger equipment by Teletype, Lear Siegler or General Electric will be considered. The Harris bid proposed a data logger manufactured by Practical Automation, Inc. and noted that if Harris was required to conform to the specifications by furnishing a data logger manufactured by one of the three specified manufacturers, its base bid would have to be increased by $635.00. Paragraph 16755-18 of the specifications requires a specific number of supervisory functions at each of the nineteen locations. The Harris bid met the requirements of the specifications at only one of the nineteen locations. At each of the other eighteen locations the Harris bid was from one to three supervisory points deficient. According to the evidence presented it would cost between $250 to $300 per location to furnish the supervisory points left out of Harris' bid. Paragraph 16755-13(d) of the specifications requires that the data logger shall log an uninitiated (alarm) change of status in red lettering. Harris' bid states that the equipment they have chosen is not available with red ribbon printout and that they therefore propose that all changes normally logged in red would instead have an asterisk in the first column. This specification requiring logging in red of an alarm change of status was included by the specifications writer of the architect/engineers as a safety feature. Paragraph 16755-13(e) of the specifications requires that the log shall contain time in a 24 hour format to a tenth of a minute. The Harris bid proposes that the log shall be in seconds rather than tenths of a minute. The specifications require equipment delivery to the job site and substantial completion within 180 calendar days after receipt of Notice To Proceed. The specifications further provide for liquidated damages of $100 per day for each day the contractor fails to meet the above completion date. The Harris bid requested that the liquidated damages clause and the required time for completion be modified to provice that the 180 day period would not commence until all drawings had been approved by the architect/engineers. The architect/engineers, Reynolds, Smith and Hills, calculated that the required drawing time was approximately 60 days. Therefore, the Harris bid proposes that Harris would have 240 days instead of 180 days in which to deliver the equipment to the site and substantially complete the contract. The Harris bid proposed a deviation from the warranty provision of the specifications. The specifications in paragraph E-17 placed the final determination of the need for repairs or changes under the guarantee clause of the specifications with the architect/engineers and the owner. Harris proposes to alter those specifications and place the right of final determination as to the existence and cause of any claim defect with Harris. Harris' bid contained information setting forth their experience with the Micro II System, which is the system they proposed in their bid. That information shows that the Micro II System had been in use no more than two and one-half years at the time of the bid letting. In its evaluation of the bidders' proposals, based upon the data contained in the original bid packages, Reynolds calculated that the deviation from the specifications by Harris gave Harris at least a $10,135 advantage in its bidding (See Petitioner's Exhibit 8). That evaluation did not include a dollar value for the deviation from the specification concerning the warranty. In that evaluation Reynolds noted the failure of Harris to meet the supervisory point requirements. They calculated that this would add $3,900 to Harris' bid based on twelve locations at $300 per location. In fact, Harris failed to meet the requirements at eighteen locations, which at $300 per location, would add $5,400 to Harris' bid. Thus, using the evaluation figures of Reynolds, it appears that Harris' deviations from the specifications gave them at least an $11,635 advantage in the bidding. On October 9, 1975, Reynolds held a conference with each of the three bidders. At that conference Weston provided a list of three names, with addresses of customers for whom Weston had completed work similar to that proposed in its bid. Reynolds did not receive any material information from these references until after October 31, 1975. At least two of the references commented favorably on Weston's performance in letters to Reynolds dated January 13, 1976 and January 20, 1976, respectively. By letter dated October 31, 1975, Reynolds' project manager for this project conveyed the architect/engineers' recommendation for award to the Department. That recommendation was that the contract be awarded to Hathaway Instruments, Inc., for the base bid item only. The recommendation noted that the alternate should be rejected because the bids for the alternate were excessively high. As stated in the letter of recommendation, Reynolds rejected Harris' bid because "there were several major exceptions taken to the specification (sic), the most serious of which was their not being able to meet the delivery schedule." Also, as stated in the letter of recommendation, Weston's bid was apparently rejected because they "could not meet the experience qualifications as specified." Harris, at the time of the bid letting, had five years experience with its Micro I equipment but had only two and one-half years experience with its Micro II equipment. The two lines of equipment constitute two generations of equipment. Neither Harris nor Weston had five years experience with the specific equipment proposed in their bids. Both, however, have had five years experience with the general type system and equipment proposed with Harris being the more experienced of the two. Based upon the evidence presented Weston and Harris are both responsible bidders. In November, 1975, the Department directed Reynolds to contact Harris and determine whether Harris would conform their bid to the specifications. The project manager for Reynolds so contacted Harris and by letter dated November 17, 1975 (Petitioner's Exhibit 4), notified the Department that Harris stated they would deliver the equipment within the time required by the specifications. That letter reiterated Reynolds' recommendation of Hathaway as contained in their letter of October 31, 1975. Reynolds did not retreat from their recommendation of Hathaway and at the final hearing again stated that recommendation. Thereafter, the Department proposed to award the contract to Harris and set the matter for final decision on December 2, 1975. Harris' bid was a responsible offer but was not in full compliance with the bid specifications and conditions. The bids of Weston and Hathaway were responsible offers and were in full compliance with the bid specifications and conditions except as noted in paragraphs 4, 7 and 19 herein. Paragraph B-18 of the Specifications and Contract Documents (Petitioner's Exhibit 1) states that "No bid modification will be accepted after the close of bidding has been announced." Section A of the same document states that bids would be received until 2:00 p.m. EDST, on September 25, 1975. No evidence was presented which would show that the time for receiving bids was extended beyond that set forth above. Therefore, the close of bidding appears to have been at 2:00 p.m., EDST, September 25, 1975. The agreement by Harris to conform their bid to the specifications and conditions constituted a material modification of their bid. This modification occurred in November, 1975, after the close of bidding, and was therefore not allowable under the terms of the Specifications and Contract Documents set forth above. The lowest base bid and alternate bid of those responsible offers received in full compliance with the bid specifications and conditions was that of Weston. No evidence was presented which would show that the Department submitted its complete File on this matter to the Division of Purchasing along with its reasons for recommending a bid other than the low bid meeting specifications, as required by Section 13A-1.02(a), F.A.C.
The Issue Whether Respondent acted contrary to the agency's governing statutes, rules or policies, or the bid specifications in its proposed decision to award Contract No. T1285 to Intervenor Kamminga & Roodvoets, Inc. ("K & R").
Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of the proceeding, the following findings of fact are made: On May 14, 2008, the Department released its bid solicitation for Contract T1285. The proposed contract was for the construction of a one-way pair through Lake Alfred, including new construction, reconstruction, milling and resurfacing, widening, drainage improvements, lighting, signalization, signing and pavement marking and landscaping on State Road 600 (U.S. 17/92). Polk County, the location of the project, lies in the Department's District 1. Qualified contractors, including Mid-State and K & R, received an electronic disk containing the solicitation, bid blank, plans and specifications for Contract T1285. The letting date for this project was June 18, 2008. Bids were to be submitted on or before that date via Bid Express, the electronic bidding system used by the Department. No party submitted a protest of the terms, conditions, and specifications contained in the solicitation pursuant to Subsection 120.57(3)(b), Florida Statutes. The work to be performed on Contract T1285 included the installation of limerock road base to be paid for in accordance with line item 0175, Optional Base Group 09 ("Base Group 09"). The bid documents included a set of "Supplemental Specifications." Section 6 of the Supplemental Specification was titled "Control of Materials." Subsection 6-3.3, titled "Construction Aggregates," provided as follows: "Aggregates used on Department projects must be in accordance with Florida Administrative Code Rule 14-103."2 Under the heading "Developmental Specifications" is a February 15, 2008, revision to the Construction Aggregates subsection that provides: Subarticle 6-3.3 (Page 54) is expanded by the following: 6-3.3.1 Department Directed Source for Aggregates: For this Contract, obtain aggregates for use in limerock base from the following vendor: Vulcan Construction Materials LP. Upon award of the Contract, provide the vendor and the Department a schedule of project aggregate needs. Once a schedule has been provided to both the Department and vendor, the Engineer will issue written authorization, with a copy to the vendor, for the purchase of aggregates from the vendor. This authorization is required before aggregates will be released by the vendor. Pick up the required aggregate such that the project schedule will be maintained. Payment to the vendor by the Contractor will be due upon receipt of the materials pursuant to the Department's Vendor Contract No. BDH50. This rate is the unit price agreed upon by the Department and the vendor and will be made available to bid proposal holders at the time of bid at http://www.dot.state.fl.us/construction/aggregate /aggregate.htm. The Department will make payment to the Contractor for the aggregates on progress estimates as a part of the bid unit price for the appropriate pay items. The rate is subject to change and adjustments for such changes will be made to the bid unit price of the appropriate pay items. Disputes with the vendor concerning aggregate supply will not be cause for Contract time adjustments, time suspensions or monetary adjustments to the Contract amount. The Contractor will be solely responsible for providing the necessary advance notice to the vendor and other coordination to obtain timely aggregate supply for the project. The import of Developmental Specification 6-3.3.1 was that all bidders would be required to obtain the limerock needed for Base Group 09 from a single vendor, Vulcan Construction Materials LP ("Vulcan"). The winning bidder would agree to pay Vulcan in accordance with a separate contract negotiated between Vulcan and the Department. The hyperlink provided in Developmental Specification 6-3.3.13 led to a document called "Aggregate Guidance" produced by the Department's State Construction Office. The front page of the Aggregate Guidance document contained "Bidder Information" consisting of a spreadsheet setting forth the Vulcan price per ton for limerock base and limestone coarse aggregate, with the price varying depending on the date and port of delivery. Between January and June 2008, the Vulcan price per ton for limerock base from both the Port of Tampa and Port Canaveral was $16.93. The Aggregate Guidance page contained additional hyperlinks with the following titles: "Aggregate Vendor Contract Usage," "Aggregate Vendor Contract," "Aggregate Vendor Projects List," "Aggregate Vendor Authorization Letter," "Aggregate Vendor Contract Frequently Asked Questions," and "Aggregate Price Adjustment Sheet." Alvin Mulford is the vice-president of Mid-State who, along with his estimator, put together his company's bid for Contract T1285. Mr. Mulford testified that his company has been bidding on Department work, and that he has never before seen a provision similar to Developmental Specification 6-3.3.1. Mr. Mulford directed his estimator to obtain clarification from the Department, to be sure that the bidders were required to purchase the limerock base from Vulcan. One reason for Mr. Mulford's concern was the "exorbitant" rate charged by Vulcan in comparison to other vendors. The restriction to a single supplier was so abnormal, and that supplier's rate was so out of line with the market, that Mr. Mulford decided to seek guidance from the Department through the question and response internet bulletin board provided by the Department for its projects. The question posed by Mid-State was as follows: Does the contractor have to use Vulcan materials for the limerock base at a rate of $16.93 per ton as stated in the Developmental Specifications 6-3.3.1? If so from which location is the material to be picked up? Is it also true that payment to the vendor (Vulcan Materials) will be due immediately upon receipt of the materials? I wanted to clarify this issue as it is unusual for the contractor to be limited to the use of only one vendor. The Department's response was as follows: The unit rate for the Material can be found at the following website: http://www.dot.state.fl.us/construction/ Aggregate/Aggregate.htm Pickup locations for the Material can be found at the following website: http://www.dot.state.fl.us/construction/ Aggregate/Aggregate.htm Payment should be issued by the Contractor to the Vendor (Vulcan Construction Materials LP) upon receipt of the materials as defined in Developmental Specification 6-3.3.1. Because the Department's response did no more than redirect him to the Department's website, Mr. Mulford decided to look at the website in more detail. He investigated the hyperlinks, including the Vulcan contract with the Department. When he clicked on the hyperlink titled "Aggregate Vendor Contract Usage," he found a document that provided as follows, in relevant part: Aggregate Vendor Contract Usage by Districts With the execution of the contract with Vulcan Construction Materials LP, contract number BDH50, Vulcan has committed to provide aggregate in the types and quantities defined in the contract (attached). The process for this contract in Districts 1, 5, and 7, is as follows: Include in the projects identified in the attached spreadsheet the appropriate special provision beginning with the July 2007 lettings. The District Specifications Engineer and District Construction Office will need to coordinate this effort. There are two special provisions for the purpose of notifying construction contract bidders of the Department's intention toward the aggregate. The first special provision is the mandatory version that will direct the bidder to obtain aggregates for the specified work from Vulcan. The second special provision provides the bidder an option to obtain its aggregates from Vulcan. * * * After these projects have been awarded, the contractor is required to notify FDOT and Vulcan a schedule of its aggregate needs for the project. After receiving this schedule, FDOT's Resident Engineer will issue written authorization to the contractor, with copy to Vulcan. This authorization is required before Vulcan will release aggregate to the contractor. Payment to Vulcan will be from the contractor. FDOT will pay cost of aggregate on progress estimates as part of the contractor's bid price for the work. The contractor is required to include in its bid price for the work the cost of the aggregate at the Vulcan rate. The Vulcan rate will be posted on the FDOT State Construction Website showing the rate. When adjustments are made to the Vulcan rate, FDOT will make adjustments in the construction contract unit price. . . . (Emphasis added.) Mr. Mulford testified that he understood the underscored language in the hyperlinked document to be a directive to the bidders and therefore a mandatory requirement of the bid specifications. He did not ask the Department for further clarification because he believed the requirement was clearly stated in the hyperlinked document. David Sadler, the director of the Department's office of construction, testified that the hyperlinked document was developed by his office to offer guidance to the districts as to the concept behind and use of the aggregate vendor contract. The document was not a part of the bid solicitation document. Mid-State's bid price was $7,429,398.44. Mid-State's price for Base Group 09 was $619,645.80, or $19.30 per square yard. This price reflected the Vulcan rate for limerock base of $16.92 plus tax and Mid-State's costs for the work associated with Base Group 09. 19. K & R's bid price was $7,370,505.24, or $58,893.20 lower than the bid price of Mid-State. K & R's price for Base Group 09 was $256,848.00, based on a stated unit price of $8.00 per square yard for limerock base. K & R's price for Base Group 09 was $362,797.80 lower than that of Mid-State, accounting for more than the differential between the overall bids of Mid-State and K & R. Marcus Tidey, Jr., K & R's vice president in charge of its Florida division, testified that K & R was well aware that the Vulcan price for limerock base was $16.93, and that K & R understands its obligation to pay that price to Vulcan should K & R be awarded Contract T1285. Mr. Tidey testified that at the time of bid submission, he cut K & R's bid price to $8.00 per square yard as a competitive strategy to win the contract. Mr. Tidey made a conscious decision that K & R would absorb the difference between $8.00 bid price and the Vulcan price of $16.93. Mr. Tidey testified that K & R needed to win this job in order not to have its crews and equipment sit idle during the economic downturn, and therefore decided to take all of its markup, roughly $250,000, out of the bid. He could have made the $250,000 cut on any item or items in the bid, but decided on Base Group 09 because the limerock base was a big item and therefore easy to cut by a large amount. Mr. Tidey also testified that the contract provides a $400,000 incentive payment for early completion of the job, meaning that K & R will be able to work "faster and smarter" and make up for the price reduction at the end of the job. Mr. Tidey testified that he obtained the Vulcan prices from the Department's website as instructed by Developmental Specification 6-3.3.1. He did not click on the hyperlinks, which appeared to reference the contract between the Department and Vulcan and therefore was of no concern to him. The Department and K & R dispute Mid-State's assertion that the underscored language of the hyperlink set forth in Finding of Fact 15 was a requirement of the bid specifications, based on Mr. Sadler's direct testimony and the underlying illogic and unfairness of requiring bidders to seek out hidden specifications. The Department and K & R concede that if the bid specifications did in fact require the bidders to include in Base Group 09 the full costs associated with obtaining the limerock base from Vulcan, then K & R's bid is nonresponsive. Developmental Specification 6-3.3.1 directed bidders to the Department's webpage for the purpose of obtaining the current Vulcan rate quote. It did not instruct the bidders to investigate the hyperlinks or to assume that the information contained therein was mandatory. Absent an instruction to bidders to review the information contained in the hyperlinks, the Department could not make such information mandatory without placing less curious bidders at a competitive disadvantage. The Department had no intent to play hide-and-seek with the bid specifications in the manner suggested by Mid-State. In addition, K & R points to three line items of the bid specifications in which the Department eliminates competition, instructing the bidders not to bid and inserting a fixed unit price and bid amount for all bidders as to those items. K & R reasonably asserts that the Department was fully capable of treating Base Group 09 in the same fashion, had it intended to require the bidders to pass through to the Department all the costs associated with obtaining the limerock base from Vulcan. However, the Department supplied the bid quantity (31,106 square yards) and left it to the bidders to determine the price per unit they would bid. K & R's bid was responsive. Nothing in the bid specifications prevented K & R from absorbing part of the cost of the Vulcan limerock base and passing the savings on to the Department, or required bidders to pass on to the Department the full costs of complying with the bid specifications regarding Base Group 09. The sole remaining issue is whether K & R's bid, though facially responsive, was materially unbalanced. The Department routinely conducts reviews of bid line items that appear "unbalanced," i.e., for which there appear to be significant differences between the price bid and the Department's cost estimate, in order to determine whether the price difference is due to a quantity error by the bidder. The Department's review confirms that the bid quantity specified on the bid blank is accurate. If a quantity error is found, the bids are recalculated using the bidders' unit prices and the correct quantities to determine whether the bid rankings would change. A bid for which there is a discrepancy between the bid and the Department's estimate is termed "mathematically unbalanced." A mathematically unbalanced bid that affects the ranking of the low bid is "materially unbalanced." A mathematically unbalanced bid is acceptable, but a materially unbalanced bid affords the bidder an unfair competitive advantage and must be rejected. The Department followed its usual procedure in analyzing the K & R bid to determine whether it was unbalanced. Philip Gregory Davis, the Department's state estimates engineer, testified that there were some unbalanced items in the K & R bid, but no quantity errors that would have changed the ranking of the bids. Richard Ryals, the project designer who conducted the unbalanced bid review, testified that the quantities were correct for Base Group 09. As noted above, K & R's low bid for Base Group 09 was an intentional strategy, not the result of a quantity error. K & R's current bonded capacity qualification with the Department is $258 million in contracts at any one time. K & R posted a bid bond, and has more than enough capacity to comfortably perform this contract. There is no economic danger to the Department in accepting K & R's low bid.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that the Department of Transportation enter a final order dismissing Mid-State's formal written protest and awarding Contract T1265 to K & R. DONE AND ENTERED this 9th day of January, 2009, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th day of January, 2009.
The Issue The issue for determination in this proceeding is whether a contract for a perimeter security system at Calhoun Correctional Institution and Holmes Correctional Institution should be awarded to Intervenor.
Findings Of Fact On January 19, 1994, Respondent issued an Invitation To Bid, Bid No. 94-INST-6197, the ("ITB"). The ITB requested bidders to submit bids to supply materials for perimeter security systems and to provide training for the installation and maintenance of the systems at Calhoun Correctional Institution and Holmes Correctional Institution. Responsive bids had to include materials and training necessary for Respondent to install and maintain the security systems. Bids had to be filed no later than February 10, 1994. Petitioner and Intervenor submitted bids along with three other bidders in a timely manner. The ITB required bidders to hold a Florida alarm contractor's license. Intervenor does not hold such a license. However, the ITB defines the term "bidder" to include an individual, firm, partner, or corporation. Intervenor's bid contemplated that it will supply the materials required in the ITB. Another company that holds a Florida alarm contractor's license will provide the training required for Respondent to install and maintain the security systems. Intervenor and the other company responded to the ITB as partners in a single bid that provides a single price for all materials and training required by the ITB. Intervenor's bid complies with the terms of the ITB and is responsive. Respondent notified Intervenor of its intent to award the contract to Intervenor as the lowest responsive bidder. Intervenor's bid is approximately $14,000 less than Petitioner's bid. Petitioner is the second lowest bidder. Respondent's interpretation that the ITB allows materials and training to be supplied separately by Intervenor and its partner is a reasonable interpretation that is neither arbitrary nor capricious. The intent and purpose of such an interpretation is to encourage flexibility that may result in savings to the state. The provision of materials and services by separate companies in Intervenor's bid will, in fact, result in substantial savings to the state. The terms of the bid does not create an unfair advantage for Intervenor. The term bidder is defined in the bid documents to include a partner and a corporation. Florida law expressly exempts Intervenor from the requirement for an alarm contractor's license if Intervenor merely supplies materials and does not fabricate or consume the materials in performing the work of a contractor. Section 489.503(10), Florida Statutes. Therefore, only Intervenor's partner is required to hold an alarm contractor's license, and, in fact, Intervenor's partner holds the requisite license. Respondent's interpretation of the ITB is consistent with applicable law. Any other interpretation of the ITB by Respondent would have purported to impose a stricter licensing requirement than that imposed by the legislature.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner's written formal protest be DENIED. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 26th day of April, 1994. DANIEL MANRY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of April, 1994. APPENDIX Petitioner's Proposed Findings of Fact 1.-5., 7-8. Accepted in substance 6. Irrelevant and immaterial Rejected as recited testimony Accepted in substance 11.-13. Rejected for the factual and legal reasons stated in the Recommended Order Respondent's Proposed Findings of Fact All of Respondent's proposed findings of fact are accepted in substance. COPIES FURNISHED: Beth Atchison, Esquire Assistant General Counsel Florida Department of Corrections 2601 Blair Stone Road Tallahassee, FL 32399-2500 Teresa Hurtado Schaefer, CEO FSM, Inc. 3559 S. W. 69th Way Miramar, FL 33023 Harry K. Singletary, Jr. Secretary Department of Corrections 2601 Blairstone Road Tallahassee, FL 32399-2500 Louis A. Vargas, Esquire General Counsel Department of Corrections 2601 Blairstone Road Tallahassee, FL 32399-2500 Michael G. Kanche, Jr. Southwest Microwave 2922 South Rosevelt Street Tempe, Arizona 85282-2042
Findings Of Fact Prior to June, 1988, HRS determined that it needed 32,000 square feet of office space to house some of its indigent social services for southern Escambia County. Since the desired office space is greater than 2,000 square feet HRS was required to competitively bid lease number 590:1984. Towards that end, Respondent prepared an Invitation to Bid and a bid submittal package. The package contained various bid specifications, bid evaluation criteria and the numerical weight assigned to each of those criteria. Specific areas of importance to Respondent in the selection of its office space were: client safety one building to house all its units employee morale moving costs traffic flow within the building public access Many of the above areas were important to HRS since the agency would render indigent services to approximately 17,000 people a month, many of whom are handicapped or lack good mobility due to age or infirmity. Employee morale was important because of high employee burn out due to rendering aid to so many people who have so little and supplying a pleasant environment conducive to the work of the employees. Moving costs were important should HRS be required to find other space to operate in while necessary remodeling took place in the selected building, or be required to incur the expense of moving to a new building. 1/ All of the above areas were covered by one of Respondent's weighted bid evaluation criteria. The District Administrator of HRS, Chelene Schembera, is ultimately responsible for bidding, selection and leasing of all HRS facilities within District I, including Escambia County, Florida. In order to accomplish this task, Ms. Schembera appointed a bid evaluation committee to review and grade the responsive bids under the criteria established in the bid package, and to recommend to her the committee's choice of the lowest and best bid. Ms. Schembera's purpose in establishing the bid evaluation committee was to secure a cross section of input from people who had a variety of backgrounds and knowledge that would be material in evaluating the office space under the uses for which it was intended and the relative public worth of the work space. Ms. Schembera appointed individual who were familiar with the type of work to be done in the proposed space, as well as a persons familiar with the bid process. Ms. Schembera assigned to serve on the committee Charles Bates, Deputy District Administrator; Jim Peters, to provide a fiscal and overall administrative perspective as well as bid expertise; two citizens from the District Advisory Council to assure objectivity and to look at the properties from the perspective of a private citizen; Mamun Rashied, a program manager; Darlene McFarland, a program manager; Cherie Neal, a unit supervisor and program worker; and Stacey Cassidy, a clerical employee. Ms. Schembera did not personally know Cherie Neal or Stacey Cassidy. These staff members were designated by the supervisors upon Ms. Schembera's direction that she wanted persons who were both intelligent and respected by their peers. One private citizen member of the committee did not participate. The committee as constituted showed a great deal of thought on Ms. Schembera's part to ensure the objectivity of the bid process she was engaging in and to ensure the maximum amount of input from persons who had experience relevant to the overall review of the proposed real estate and to the decision they were being asked to make. The selection of the bid evaluation committee members was neither an arbitrary nor capricious act on Ms. Schembera's part. In fact, the evidence demonstrated the merit in constituting the committee as she did for the input she sought. The bid evaluation committee members, minus Mr. Bates, were briefed on their duties by Joe Pastucha, Facilities Services Manager. Mr. Pastucha is part of the staff responsible for the bid process at HRS. He provided these committee members with the weighted bid evaluation criteria found at page 15 in the bid package. He also gave the committee members a copy of Chapter 5 of the HRS manual containing guidelines for the bid process. His verbal instructions on specific procedures to follow in the evaluation process were limited since he did not wish to improperly influence the committee members. On July 20, 1988, HRS received three bids responding to its invitation to bid on Lease Number 590:1984. Bid A was submitted by Phillips and Company, the apparent second lowest bidder and Intervenor in this case. Its property consisted of one multi-story building located at 1740 North Palafox Street, Pensacola, Florida. Bid B was not responsive and therefore was not considered by HRS and is not a part of this litigation. Bid C was submitted by Petitioner Carmon S. Boone, and was the apparent low bid. Mr. Boone's property consisted of two buildings located at 401 and 411 North Baylen Street, Pensacola, Florida. The Boone property is the present location of Respondent's offices. Both Bid A and Bid C were within the mandatory geographical area designated in the bid package. Once the bids were received the bid evaluation committee began its work. The committee members, minus Mr. Bates, visited the Phillips property. However, the members did not visit the Boone property. There was no need. Four of the members currently worked at the Boone property and the other members had previously visited the Boone property on various other occasions. Mr. Bates was likewise already familiar with both properties. All members were sufficiently familiar with the cogent aspects of each property to allow them to make a rational decision. The bid evaluation committee, minus Mr. Bates, met as a group to evaluate each property in accordance with the weighted bid evaluation criteria. Each individual scored their sheets separately and the general consensus was supportive of recommending the Phillips property. Five committee members scored Mr. Phillips' property higher than the Boone property. The one exception was Mr. Peters who felt that HRS could not support a bid awarded for other than monetary reasons, i.e., he felt the lowest bid had to be accepted. Mr. Bates later reviewed all the bid synopsis sheets of the committee members and discussed the bid award with Mr. Peters and Mr. Pastucha. Mr. Bates felt that the Phillips property was the lowest and best bid. At about the same time, the staff responsible for providing technical assistance to the committee and the District Administrator were made aware that the general consensus of the committee was leaning towards the second lowest bidder, Phillips and Company, as the lowest and best bid. The staff members, one of whom was a bid committee member, disagreed with the award of the bid to Phillips and Company because the Boone property was the lower bid. The staff members sought to head off the committee's intended recommendation. The staff personnel held a meeting with some of the committee members in order to get them to join in a recommendation to Ms. Schembera of the Boone property. Mr. Boone was invited and attended the meeting. He was allowed to improperly bolster his bid by agreeing to convert the two buildings to one and other lesser additions. /2 The potential decision was discussed, but no committee member changed his or her mind. However, through a total lack of communication, a run away staff somehow rationalized themselves into a position of being authorized to submit a letter for Ms. Schembera's signature which awarded the Boone property the lease. Ms. Schembera became aware of her staff's attempt to subvert the bid process she had established. She refused to sign the letter submitted by the staff. She removed the staff member of the committee as a voting member. The staff member had supported the Boone property. She also removed a committee member who supported the Phillips property as a voting member. Ms. Schembera feared that her staff had improperly influenced this member to such an extent that his objectivity had been affected. Both members could still participate in committee discussions. Ms. Schembera thereby reasonably ensured the ongoing objectivity of the bid evaluation committee. The committee was reconvened, minus one member. It recommended the Phillips and Company property. Every reason given by the individual committee members for distinguishing and preferring one bid over another were rational and reasonable considerations and were covered by the bid evaluation criteria. Each individual member gave a rational and reasonable basis for the scoring he or she used on the bid synopsis score sheets. The scoring was done by each member after discussion of the two buildings and without influence from the other committee members. In essence, the committee felt that the Phillips property was the better property for the money. The Phillips property allowed working units to be located in one area with each such unit having its own access. It provided flat safe parking areas and sidewalks, bigger and more elevators, wide halls and windows which presented a bright, happy and pleasant working environment. The Boone property was in two buildings which could not accommodate co-located working units with their own access no matter how much remodeling took place. Parking and sidewalks are on a hill which is slippery when wet. It had one small elevator and narrow halls which did not adequately accommodate more than one wheel chair, and one ground floor where no windows could ever be remodeled into the building leaving a dark, dingy and unpleasant environment. Importantly, every committee member except for the staff member came to the conclusion that the Phillips and Company property was the lowest and best bid. There is no statutory or rule requirement that one scoring method be preferred over another. The only requirement is that the method be rational and reasonable especially where highly subjective, but legitimate criteria are involved in the selection of a particular piece of property. On these facts, the individual scoring methods used by the individual committee members were not arbitrary and capricious, but were very rational and reasonably related to the relative importance the committee members gave the above factors. After reviewing and considering information from the bid evaluation committee, the information on the bid synopsis sheet, and the oral recommendations of Mr. Bates, Mr. Peters and Mr. Pastucha, Ms. Schembera concluded that the Phillips property was vastly better, even considering costs. She found it to be materially superior in terms of construction, organization, client accessibility, handicap accessibility, repairability (in terms of walls), and maneuverability for clients and staff. She felt the Phillips' building's qualities would offer more "humanity" to the process of serving the Department's clients. Additional facts she considered when making her decision included the morale of the staff and their productivity; the ability of staff and clients to conduct their business in a reasonably pleasant, comfortable, safe, and easy to understand and comprehend environment; and the desire to provide a minimally adequate work space. In addition to other monetary costs, she considered energy costs and life cycle costs as reflected on the bid synopsis sheet. The bid synopsis sheet defined minimal energy and life cycle costs to be anything less than 55 BTU's per square feet per year. In this case, the Boone property reflected 39.5 BTU's per square feet and the Phillips property reflected 53.5 BTU's per square feet. Both properties were under the 55 BTU cutoff established by HRS. Translated into monetary figures (life cycle costs) the Boone property reflected a cost of $26,735.00 and the Phillips property reflected a cost of $41,160.00. It was the difference between the energy figures which caught Ms. Schembera's eye. In her layman's opinion, it was incomprehensible that the two buildings would have such a wide divergence of energy costs. /3 She learned from her staff that the information used to compute these costs was supplied by the bidders who had vested interests in the outcome. Ms. Schembera concluded the cost difference was minimal and not of overriding concern in relation to the physical characteristics of the two buildings and how they compared to each other. She quite correctly felt the two buildings were not comparable. In essence, the two buildings' differences in design location and construction rendered neither building comparable to the other building as a like facility under Section 255.254, Florida Statutes. 4/ Based on that information she gave the energy figures relatively little weight. More importantly, however, before the final bid award was made by HRS, the Division of General Services within HRS in its failsafe role in reviewing bids considered the life cycle cost figures of the two bids. The minimal language of Section 255.254, Florida Statutes, has been interpreted by HRS to mean that anything under 55 BTU's is minimal and except in one instance not applicable here, numerical differences under 55 BTU's are immaterial. The Division, without getting into the issue of the likeness of the facilities, concluded that both bids met the Department's interpretation of the "minimal" language of Section 255.254, Florida Statutes, and the relative numerical difference in the energy costs was immaterial. Ms. Schembera is entitled to rely on other more expert HRS Division staff to ensure a proper analysis of highly technical bid specifications such as the energy cost analysis required under Section 255.254, Florida Statutes. It does not matter that the review took place after Ms. Schembera had made her preliminary decision. What is important is that the review be made either personal or vicariously through staff before the final award is made. A proper review of energy costs was, therefore, made by Respondent before the final award was made. Likewise, Ms. Schembera's ultimate decision that the buildings were not comparable like facilities was a proper review of energy costs even though that conclusion was arrived at through a layman's unsophisticated, but more accurate intuition and common sense. To that extent, the energy cost data had no impact on the ultimate choice made by the District Administrator and were properly considered by the District Administrator. 5/ A letter for Ms. Schembera's signature adopting the committee's recommendation was drafted by Mr. Pastucha. The letter was signed and sent to the Department's Division of General Services for review. The District was requested to provide additional justification for its choice by the Department's Division of General Services. Mr. Rashied was directed to draft the response. He simply reorganized the original memorandum into a format more compatible with the Division's direction, clarified a few points and without significantly changing the content, submitted the response as directed. The Division acquiesced in Ms. Schembera's decision.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Department of Health and Rehabilitative Services enter a final order dismissing Case NO. 88-4900BID, and awarding lease number 590:1984 to Phillips and Company as the lowest and best bidder. DONE and ORDERED this 5th day of January, 1989, in Tallahassee, Florida. DIANE CLEAVINGER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of January, 1988.
Findings Of Fact Respondent, St. Johns Water Management District, is a special taxing district authorized by law to perform various water resource duties and is empowered to hire and terminate employees. As an employer, the District has developed an employment policy which states in pertinent part: VII. ACTS OF MISCONDUCT AND WORK STANDARDS VIOLATIONS FOR DISTRICT EMPLOYEES The following acts of misconduct and violation of work standards will subject an employee of the District to disciplinary action: 15. Insubordination - An employee may not willfully or deliberately refuse to comply with a direct order or any established work assignment of an immediate supervisor or higher level supervisor unless such order or assignment would result in an immediate danger to the health and safety of the employee or others. STANDARDS OF DISCIPLINARY ACTION The following standards are established to insure the District is consistent in taking disciplinary actions against employees involved in similar situations. The recommended disciplinary action is normally the penalty which should be imposed. However, circumstances may make a greater or lesser action more appropriate than the one suggested. Realizing that some of the offenses and deficiencies listed will be more serious and more frequent in certain cases, the District shall utilize good judgement in light of all available facts in each case. Secondary and subsequent offenses have a cumulative effect and justify greater penalties. An offense need not be similar in nature to an earlier offense in order to have such cumulative effect. The disciplinary action should be based on an overall evaluation of conditions and severity of the violations. The standard of discipline for the first occasion of insubordination is a written reprimand, suspension up to three days or dismissal. The standard for the second event of insubordination is dismissal. Teresa Brun was employed by the District from July of 1988 to February 25, 1992. From April 1989 to February 25, 1992, Ms. Brun held the position of contract administrator in the water resources section of the District. As a contract administrator, she, along with four other contract administrators, oversaw various purchasing contracts for the District which the District was in the process of letting out for bid. Ms. Brun had also been assigned to work on drafting a new contracts policy manual and drafting standard forms for the new manual. Performance of clerical duties associated with the various purchasing contracts assigned her were not part of Petitioners established work assignment. Ms. Brun's supervisor was Mr. Jadwin, the contract supervisor. The water resources contract section had a secretary who, during the time period relevant to this proceeding, was Betty Anderson. Ms. Anderson had limited experience in the water resources section since she had been employed in the section since October or November 1990. Ms. Anderson's function was to perform clerical duties for the section's supervisor and contract administrators, including Ms. Brun. In essence, Ms. Anderson was supposed to work with the contracts administrators and perform the secretarial functions of the office as instructed by the contracts administrators. Her duties included, among other things, working with the bid files, maintaining a list of bidder's addresses (bidders' list), and typing and preparing bid tabulation sheets. Ms. Brun as well as other contract administrators did take materials to Ms. Anderson and instruct her how to prepare various materials and bid documents required by the contracts office. Ms. Anderson was a slow learner and was difficult to get along with. However, Ms. Brun felt that since Ms. Anderson had been employed for approximately three months, it was time for Ms. Anderson to learn to utilize the bid files and computer files containing bidder's addresses in order to gather the information she needed to prepare bid documents and materials without being spoon fed the information. In short, Ms. Brun legitimately expected Ms. Anderson to perform as past section secretaries had performed. On Friday, January 25, 1991, Ms. Anderson received a note from Ms. Brun asking Ms. Anderson to prepare a standard "Notice of Intent" to issue a contract on a particular bid which was to go before the Board for adoption. A "Notice of Intent" includes a cover letter, bid tabulation sheet and a Notice of Rights. The complete package is then mailed to the bidders who expressed an interest in the bid. Ms. Brun prepared the cover letter and standard Notice of Rights and requested Ms. Anderson to mail the Notice of Intent to all the bidders. Ms. Brun informed Ms. Anderson that the bid tabulation sheet was in the bid file. Ms. Anderson wrote a note back to Ms. Brun requesting that she furnish the "pertinent information" needed to complete the assignment. Ms. Anderson's request for information appears to refer to the bid tabulation sheet and the addresses of interested bidders to whom the Notice of Intent should be sent. 1/ The note from Ms. Anderson was deposited in Ms. Brun's in-basket. On Monday, January 28, Ms. Brun saw Ms. Anderson's note and responded with a note telling Ms. Anderson that the information she sought was in the bid file and she should get it herself. Following the note exchange, Ms. Brun and Ms. Anderson talked over the problem of preparing the Notice of Intent and bid addresses in a meeting initiated by Ms. Anderson about problems with the addresses for this bid. Ms. Brun told Ms. Anderson to go into her contract files and secure the information. Ms. Anderson refused to go into the bid files to find the bid tabulation sheet and refused to print out an address list from her computer file. Ms. Anderson's reply was that if she had to get the information, it would not get done and that she would wait and talk to Mr. Jadwin. Ms. Anderson left the file on Ms. Brun's desk and would not, as instructed by Ms. Brun, take it with her. Ms. Anderson made her refusal in front of another contracts manager, Cindy Gilmore. Ms. Anderson's refusal to comply with the requests of Ms. Brun were only explained as "territorial concerns." However, Ms. Anderson did eventually learn that part of her job was to get information out of the bid files and to utilize the address information she maintained in her directory. Following this impasse, Ms. Anderson went to Mr. Jadwin, who was the mutual supervisor of both Ms. Brun and Ms. Anderson. Mr. Jadwin agreed with Ms. Anderson's position and, told Ms. Anderson that he would talk to Ms. Brun. However, Ms. Anderson asked if she could work it out herself because she wished to develop effective working relationships with the contract administrators. Mr. Jadwin agreed and Ms. Anderson returned to Ms. Brun and asked to speak about the needed materials. Ms. Anderson informed Ms. Brun that Mr. Jadwin thought it was fair that Ms. Brun get the bid tabulation sheet out of the file and give it to Ms. Anderson. Ms. Brun still angry over Ms. Anderson's refusal to perform her secretarial duties refused to discuss the matter further and told Ms. Anderson to "just write in a memo what you will do and what you will not do." Mr. Jadwin later asked Ms. Anderson how her meeting with Ms. Brun had gone. She replied things had not gone well and she was writing the memo requested by Ms. Brun. Mr. Jadwin told her not to write the memo and that he would "take care of it." Ms. Anderson then got the bid file for the first time, went through it, and could not find the bid tabulation sheet. The yellow cards with the bidder's addresses as well as green cards from bidders who had submitted bids were in the file. Ms. Anderson then took the file to Mr. Jadwin and he searched for the bid tabulation sheet and could not find it. The bid tabulation sheet had been removed from the bid file and had been placed in a standard information-packet to the Board. This packet was known as Board back-up. Ms. Brun was unaware that the bid tabulation sheet had been removed from the bid file. On the other hand, the information to recreate the bid tabulation sheet was in the file. Additionally, the bid tabulation sheet was readily findable by any thinking secretary or individual who had become familiar with office procedures. On January 31, 1991, Mr. Jadwin approached Ms. Brun. 2/ This was the first time in these events that an immediate supervisor had addressed Ms. Brun on the bid tabulation sheet and address list. The meeting took place in Ms. Brun's office which was next to Ms. Anderson's desk. Ms. Anderson was seated at her desk and could hear the conversation. All the witnesses agree that Mr. Jadwin asked Ms. Brun if Ms. Anderson had typed a certain bid tabulation sheet. Ms. Brun replied affirmatively. Mr. Jadwin then informed Ms. Brun for the first time that neither he or Ms. Anderson could locate the bid tabulation sheet in the file. Mr. Jadwin asked Ms. Brun to help Ms. Anderson out and give Ms. Anderson the information to type another bid sheet. Ms. Brun said she would. Mr. Jadwin then began to broach the subject of the addresses. He said, 'About the address,' "We've had some problems with the address on that." Ms. Brun replied that she was "not the only person who makes problems with the bids." Mr. Jadwin started to say something else and Ms. Brun cut him short and said, "Why don't you just address everything that you need to me in a memo." Mr. Jadwin again began to say something else but Ms. Brun stated "Bob, I'm not going to argue with you," got up, put the bid file in the file cabinet and walked out of her office. Clearly, Ms. Brun terminated Mr. Jadwin''s conversation with her. Whether the termination was abrupt and cut short what Mr. Jadwin wanted to say, depends on the particular witnesses point of view. However, Mr. Jadwin did not object to the conversation's termination and did not ask or order Ms. Brun to stay. No instructions were given to Ms. Brun in regards to the addresses because she exited her office. However, Ms. Brun's behavior while rude and perhaps contemptuous toward Mr. Jadwin was not insubordinate conduct on her part. That afternoon Ms. Brun learned for the first time that some bid packages had been returned because the party to whom they had been addressed was not located at the address to which the packages had been mailed. Ms. Brun took the returned packages to Mr. Jadwin. Later that same afternoon, Ms. Brun furnished the bid tabulation sheet to Ms. Anderson. Ms. Anderson retyped the bid tabulation sheet which had caused so much trouble. After typing the bid tabulation sheet, Ms. Anderson came into Ms. Brun's office and asked where the bidder's list was. Ms. Brun told Ms. Anderson the list was in the file. Ms. Anderson replied that the list "just won't get done," and threw the bid file on Ms. Bruns desk. Ms. Brun put the file back in Ms. Anderson's work tray. Ms. Anderson said the file would "just stay there." The following day, Ms. Brun sent out a partial Notice of Intent. On Friday, February 1, approximately 2 days after Mr. Jadwin's conversation with Ms. Brun, Mr. Jadwin wrote Ms. Brun a note. The note states: To: Teresa From: Bob Subject: Notice of intended award Walkways - Clay Island Date: 2-91 I have asked you to supply Betty with the list of addresses to which to send the above Notice. Betty has had to re-type the Bid summary sheet that was lost from your file. 3/ If you choose to continue to refuse this request please explain your reasons immediately to Mr. Payton. As of Monday, 2/4/91, your refusal has held this 'Notice' up for one week. Please do not delay in getting this done. Bob The note was placed in Ms. Brun's in-basket on February 1. However, she did not receive Mr. Jadwin's note until Monday morning, February 4. Ms. Brun stated she did not give Ms. Anderson the list of addresses upon receiving the note because the note was in error about being instructed to furnish the addresses to Ms. Anderson and because her interpretation of the note was not as a directive to produce the addresses but as an option of going to Mr. Payton because she would in essence be doing Ms. Anderson's job for her. Ms. Brun decided to go to Mr. Payton. Given the inaccuracies in the note and its tenor, Ms. Brun's interpretation was reasonable under the circumstances of this case. Ms. Brun printed out a copy of Ms. Anderson's directory which included the file for the bidder's list and immediately went to Mr. Payton. There is conflict in the testimony over what occurred at this meeting. Ms. Brun's version is that Mr. Payton sided with her and told her to go back to Ms. Anderson and tell her that the file was in the computer and explain the file to her. Mr. Payton denies this version, saying that he had discussed the matter during the previous week with Mr. Jadwin after the walkout and that he (Mr. Payton) then told Ms. Brun to provide the address list to her supervisor without getting upset and to go and ask Ms. Anderson what information she needed and provide that information. Except as set forth Ms. Brun's hearing testimony that Mr. Payton sided with her against her immediate supervisor is deemed not credible. Ms. Brun returned from Mr. Payton's office and told Ms. Anderson that Mr. Payton had directed her (Ms. Brun) to tell Ms. Anderson what she was to do with the file for the addresses and that the address file was in the computer. Mr. Jadwin overheard the conversation with Ms. Anderson and intervened because it was not consistent with what had been previously told to him by Mr. Payton. Mr. Jadwin then directed Ms. Anderson to complete the matter as best she could and have Ms. Brun verify the addresses. The address list was finally produced and Ms. Brun did satisfactorily verify the addresses. During the time Ms. Brun worked for the District, she was evaluated on an annual basis and never received any evaluation below the "above satisfactory" category. Her only prior disciplinary history was a reprimand for insubordination which she received in December, 1990. A reprimand is the least severe form of discipline at St. Johns River Water Management District.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That a final order be entered by the Governing Board reinstating the Petitioner's employment with the District. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 2nd day of September, 1992. DIANE CLEAVINGER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2 day of September, 1992.
The Issue The issue is whether Respondent lawfully awarded the main-line food contract to Mutual Distributors, Inc., and, if not, whether Respondent is required by law to award the contract to Petitioner.
Findings Of Fact Background This case arises out of Respondent's award of contracts for main-line food and snack foods and beverages. Through these contracts, Respondent obtains the delivery of 334 different items--297 items of main-line food and 37 items of snack foods and beverages--to over 160 sites for preparation and service to Respondent's students, teachers, and noninstructional staff. During the school year, Respondent serves over 150,000 meals daily, and the Director of Respondent's Food Service Operations manages an annual budget of $55 million. The two relevant bidders in this case are Petitioner and Mutual Distributors, Inc. (Mutual). These are the only bidders that submitted nondisqualified bids for the main-line food contract. Petitioner and Mutual also submitted bids for the snack foods and beverages contract. A third bidder, Magic Vending, also submitted a bid for the snack foods and beverages contract. Mutual has held Respondent's main-line food contract in the past. However, for at least the past seven years, Petitioner has held the main-line food and snack foods and beverages contracts. Petitioner was the only bidder for the main-line food contract for the 1996-97 school year, and, pursuant to a provision of that contract, Respondent renewed this contract for the 1997-98 school year. Petitioner presently supplies school food for the school districts in Dade, Palm Beach, Collier, Lee, Indian River, Martin, St. Lucie, Hardee, Hendry, DeSoto, and Glades counties. The size of the Hillsborough school district limits the number of vendors capable of handling the main-line food contract, although nothing in the record suggests that either Petitioner or Mutual lacks the resources to provide the specified food in a timely fashion. Invitation to Bid By Invitation to Bid dated April 30, 1998, concerning Bid Number 3743-HM (ITB), Respondent solicited bids for two product groups: main-line food, which consists of frozen entrees, frozen foods, canned goods, and staples, and snack foods and beverages. The cover sheets to the ITB advise all interested parties that Respondent would accept sealed bids until 3:00 P.M. on May 26, 1998. The cover sheets state that, on or about June 16, 1998, Respondent would award the contract, which would be in effect August 6, 1998, to August 5, 1999. The cover sheets state that Respondent would make its decision "in the best interest of the District " The cover sheets require that all bids incorporate the following language: POSTING OF RECOMMENDATIONS/TABULATIONS Recommendations and Tabulations will be posted at the Hillsborough County School District, Purchasing Department, 901 East Kennedy Boulevard, 3rd Floor, Tampa, Florida 33602 at 10:30 A.M. on 06/11/98 for seventy-two (72) hours. Actions against the specifications or recommendations for award shall follow F.S. 120.53. Procedures are available and on file in the Purchasing Office at the address listed above. The cover sheets identify the schedule of bidding events. The month of April would be for testing new products and evaluating the nutritional information of approved brands. April 30 would be the date of mailing draft copies of the ITB to all interested persons. May 8 would be the date of the pre-bid conference, at which interested persons could bring product information forms for possible approval of other products than those tentatively specified in the ITB. The cover sheets reserved a couple of days immediately after the pre-bid conference for testing any additional new products. The schedule listed May 13 as the date on which Respondent would mail the final copy of the ITB to interested persons. The schedule states that Respondent would review bids and conduct a "pre-award audit," if necessary, from May 26 through June 3. Part I of the ITB contains "general terms and conditions." Part I states: When an item appearing in this bid document is listed by a registered trade name and the wording "no substitute, bid only or only" is indicated, only that trade-named item will be considered. The District reserves the right to reject products that are listed as approved and wa[i]ve formalities. Should a vendor wish to have products evaluated for future bid consideration, please contact, in writing, the buyer listed on the 2nd page of this bid. If the wording "no substitute, bid only or only" does not appear with the trade name, bidders may submit prices on their trade-named item, providing they attach a descriptive label of their product to this proposal. Sample merchandise bid hereunder as "offered equal" may be required to be submitted to purchase in advance of bid award. Substitutions of other brands for items bid, awarded and ordered is prohibited except as may be approved by the supervisor of purchasing. Part I of the ITB includes a number of "stipulations" that are deemed a part of all bids. The stipulations provide: Tabulations of this bid will be based only on items that meet or exceed the specifications given in Part III. All other lesser items will not be considered. Failure to submit, at time of bid opening, complete information as stated in Part III can and may be used as justification for rejection of a bid item. The bidders will not be allowed to offer more than one product/price/service on each item even though the vendor feels that they have two or more types or styles that will meet specifications. If said bidder should submit more than one product/price on any item, all prices for that item will be rejected. . . . The District reserves the right to reject any and all bids or parts thereof, and to request a re-submission. The District further reserves the right to accept a bid other than the lowest bid, which in all other respects complies with the invitation to bid and the bid document, provided that, in the sole judgement and discretion of the District, the item offered at the higher bid price has additional value or function, including, but not limited to: life cycle costing, product performance, quality of workmanship, or suitability for a particular purpose. . . . All bids shall be evaluated on all factors involved, including the foregoing, price, quality, delivery schedules and the like. Purchase orders or contracts shall be awarded to the responsible offeror whose proposal is determined to be advantageous to the District, taking into consideration the factors set forth above and all other factors set forth in the request for bid as "lowest or lowest and best bid." The information called for on the item must be on the line with the item. When omitting a quotation on an item, please insert the words: no quotation, no bid or n/b. to eliminate any confusion about the item(s) being bid. . . . Any requirement by the bidder that certain quantities, weights, or other criteria must be met, in order to qualify for bid prices, will result in disqualification of the bid. Likewise, expiration dates or other constraints, which are in conflict with bid requirements, will result in disqualification. Bids may not be changed after the bid closing time. The exception would be if there was a misinterpretation of the unit for which the bid was requested. In which case, no dollar amount change would be allowed, and only a clarification as to the unit your bid represents will be considered. This must be done in writing 24 hours after notification to the bidder from the supervisor of purchasing. The submittal of a bid proposal shall constitute an irrevocable offer to contract with the District in accordance with the terms of said bid. The offer may not be withdrawn until or unless rejected or not accepted by the District. . . . 13. The District shall be the sole judge as to the acceptability of any and all bids and the terms and conditions thereof, without qualifications o[r] explanation to bidders. 27. This bid and the purchase orders issued hereunder constitute the entire agreement between the School District and the vendor awarded the bid. No modification of this bid shall be binding on the District or the bidders. 30. Variance in condition--Any and all special conditions and specifications attached hereto which vary from general conditions shall have precedence. Part II of the ITB contains "special terms and conditions." Section A of Part II explains that the purpose of the ITB is to establish a "'cost plus fixed fee per carton' annual contract for the delivery of main-line food and snack and beverages . . .." Section A projects that the annual value of Group A and Group B will be $8.5 million. Section A explains that the "product cost" is the vendor's actual cost, including delivery to its warehouse. The "fixed fee" is the difference between the vendor's cost and its selling price to Respondent. Section A notes that, while Respondent’s cost price may vary during the term of the contract, the fixed fee shall remain unchanged. However, Section K fixes the cost prices until December 31, 1998. As used in this order, "total cost" refers either to the total costs per item (i.e., the unit costs times the projected number of units to be purchased) or the total costs of all items, and the "bottom-line cost" is the total of the total costs of all items plus the fixed fee. The fixed fee includes the bidder's profit and is calculated by multiplying the fixed fee per carton, as stated in the bid, times the number of cartons actually delivered. Section B states: Bids will be awarded on the total bottom line cost and fixed fee for each group. To be considered for an award, the vendor must bid on each item within each group. Failure to bid on each item within each group will disqualify the vendor for the bid award. A distributor may choose to bid on both groups, or on only one group. In the event of default or non- availability of product, the School District reserves the right to utilize the next rated low bidder and their stated bid prices as needed. Sections C and D explain that the term of the contract is one year, ending August 5, 1999, but the parties may extend the term, in one-year increments, through August 5, 2001. Section G provides that potential bidders "may attend a pre-bid conference," but attendance is not mandatory. Section G identifies the time, date, and place of the pre-bid conference. Section G adds: If you wish to submit additional brands within a current product description for approval, you must bring from the appropriate broker/rep, a District product information form with all requested attachments to the conference. Do not bring samples. We will evaluate the product information forms and determine if testing an additional brand is necessary at this time. Submitting a product information form does not guarantee that the product will be tested. Samples must be made immediately for any product information forms submitted. Section H states: To be considered for an award, the vendor must bid on each item within each group. Failure to bid on each item within each group will disqualify the vendor for that group bid award. Section I provides: After the opening of the bids, school officials will review the line-by-line prices. Accuracy of additions and extensions, brands, and compliance with all instructions will be reviewed in order to ascertain that the offer is made in accordance with the terms of the request for bid proposal. School officials who find any error(s) in calculations will adjust the bottom line figure accordingly. However, if errors are found which either disqualify the bidder, or will raise the bottom line offer to the point where the vendor may no longer be the apparent low bidder, school officials will review the line-item prices of the next lowest bidder. This procedure will continue until a suitable offer is selected. During the review of the low bid, school officials may audit invoices or quotations on selected items for the accuracy of cost prices quoted. The extent of this audit will be at the discretion of school officials. In reviewing bids, school officials reserve the right to waive technicalities when it is in the best interest of the school system. Section O states that vendors must deliver "the brand that is quoted on the bid sheet." If vendors are "temporarily out-of-stock of a particular item, they must deliver an equal or superior product at an equal or lower price with prior approval of the District Food Service Department." Section O warns that "[e]xcessive occurrences of out-of-stock items is cause for contract cancellation." Part III of the ITB contains "instructions for completing bid sheets," followed by 65 pages of bid specifications for main-line food and nine pages of bid specifications for snack foods and beverages. Each page of specifications contains several rows, with each row devoted to a separate item, and seven columns, with the columns labeled as item number, product descriptions, approved brands, bid unit, unit cost, estimated annual usage, and total cost. Part III provides detailed instructions for describing the items bid and listing the costs for each item. Detailed specifications describe each of the items to be bid. Under "product descriptions," the two paragraphs of Section B address the issue of domestic versus imported products. The first paragraph describes products that the winning bidder may purchase, but the second paragraph limits items than can be bid. The two paragraphs state: Except for items normally not produced in the United States commercially, the contractor should make every effort to purchase domestic products. Products may be allowed from outside the United States provided specifications are met and there is a significant price differential between imported products and those produced within the States. Written documentation of these price differentials must be provided in writing to the School District by the distributor prior to the approval of such purchases. Please note: for purposes of awarding the bid, all distributors shall bid domestic products (pineapple exempt). Under "product descriptions," Section C provides: The contractor must bid on the approved brands (Column 3), packer label or house label for all items. If Column 3 is blank, the School Board will accept the brand quoted provided it meets the product description. For example, if bidding on a distributor's choice of pasta, the contractor would enter the following: Brand: Prince Product Code: 5115 If bidding on a distributor group label for green beans, the distributor must stipulate the code designation which may be a color or label, that denotes a product as being a particular grade. For example, Brand: North American/Larson Product Code: Blue If bidding a packer label the bidder must stipulate the name of the packer and the grade label designation, for example: Brand: Larsen Product Code: Lake Region For all packer label products Hillsborough County School Food Service Form "Private Label Chart for Fruits and Vegetables" (see Attachment D) must be completed and returned with the bid. Under "product descriptions," Section D states: "Bidder shall enter the grade of the brand offered only for those line items where grade is specified. " Under "approved brands," Part III provides: The bidder must bid on the approved brand and product code that is listed. If the column states "house brand," the School Board will accept the brand quoted provided it meets the product description. Some of the code numbers listed may be obsolete or incorrect, in which case the contractor may enter the correct code and submit written documentation provided by the manufacturer, verifying the correct code number. If any inconsistency exists between the approved brands and/or code numbers and the product description, the approved brand/code number will prevail. The decision as to whether a product does or does not meet the description provided in column 2 is at the discretion of the School District. A bidder may be requested to furnish acceptable confirmation from a packer that a product meets the requirements set forth in Column 2. Whenever approved brands are listed with house brands, the distributor's choice brand should be of equal or better quality than the approved brands listed. Buying group brands and codes are acceptable on frozen and canned fruits, vegetables, and juices, however, on further processed and manufactured foods the contractor shall quote a packer's brand. For example, a contractor may quote "Ore-Ida #1234, packed under the 'Code Red Label.'" Pre-Bid Conference Hank Morbach, Principal Buyer of Respondent's Purchasing Department, conducted the pre-bid conference on May 8. Also representing Respondent at the conference were Mr. Morbach's immediate supervisor, William Borrer, who is the Supervisor of Purchasing; Sherry Ebner, who is a Supervisor of Food Service Operations and a registered dietitian; and Mary Kate Harrison, who is Director of Food Service Operations, a registered dietitian, and Ms. Ebner's immediate supervisor. Minutes of the pre-bid conference reveal that Mr. Morbach and Ms. Ebner told the persons in attendance that they did not have to bid both groups, but must bid all items within the group for which they were submitting a bid. In response to a question from Mutual's representative, Mr. Morbach said that the bottom-line cost, not the fixed fee, would be the "deciding factor." In response to a question from Petitioner's representative, Mr. Morbach stated that, where code numbers were omitted for any item, specifications would prevail. The minutes disclose a discussion regarding imported versus domestic products. Although Respondent's representatives were initially ambivalent, Mr. Morbach "clarified by stating all products must be domestic." Likely, everyone understood that pineapples could still be imported. Following the pre-bid conference, Respondent issued a revised ITB on May 13. Presumably, the ITB identified as Joint Exhibit 1 is the revised ITB, so all references in this order to the ITB are to the ITB as it was finally revised. Adverse Publicity Toward the end of the pre-bid conference, a representative of the Weekly Planet appeared. The Weekly Planet is a free weekly Tampa newspaper, and the representative was a reporter, who, since October 1997, had written several articles asserting, at least by implication, that Respondent's food program suffered from excessive costs, favoritism, and possibly even wrongdoing. Part of the adverse publicity concerned Ms. Harrison's husband, who represented several manufacturers from which Petitioner had purchased food for resale to Respondent while Petitioner had the main-line food contract. The Weekly Planet published an article asserting that the husband of Ms. Harrison had lost a civil action brought by his employer for diverted commissions. By the time of the subject procurement, an internal audit had disclosed no conflict of interest on the part of Ms. Harrison, but had suggested that Respondent add personnel in Food Service Operations to monitor vendor compliance and seek more competition in awarding the food contracts. To Ms. Harrison's credit, since her employment with Respondent in 1990, she has converted a food service program that was losing $2.5 million annually into a profitable operation. The record suggests, though, Respondent's staff was extremely sensitive during this bidding process to the adverse publicity surrounding Respondent's business relationship with Petitioner. The Bids Four bidders timely submitted sealed bids for the main-line food contract. However, Respondent promptly disqualified two of the bidders because they did not submit complete bids. One disqualified bidder submitted a bid that was incomplete, unsigned, and omitted five items in the main- line food group. The other disqualified bidder submitted an incomplete bid with only six items in the main-line food group. After submitting their bids, Petitioner and Mutual each sent Respondent letters stating that each bidder did not want the snacks and beverages contract unless it also received the main-line food contract. Respondent did not object to these late-attached conditions to the two bids and did not consider either bidder for only the snack foods and beverages contract. As provided in the ITB, Respondent's staff contacted bidders, after bid opening, to confirm that certain bid items complied with the specifications. By letter dated June 3, Respondent asked Mutual for documentation that 41 listed items met the specifications, that the Fineline/Paris brand that Mutual had bid is Grade A quality, and for a complete private label chart for all canned and frozen fruits and vegetables. The letter requests a response by June 5. By letter dated June 10, Respondent asked Petitioner for documentation that thirty-seven listed items met the specifications and for a complete private label chart for all canned and frozen fruits and vegetables. The letter requests a response by June 12. Respondent wrote each bidder follow-up letters. In a letter dated June 12, Respondent asked Petitioner to document that five items met the specifications, and, in a letter dated June 15, Respondent asked Mutual to document that the same five items met the specifications. The deadlines in both letters were June 16. Mutual and Petitioner responded to these requests for additional information. By letter dated June 5, Mutual disclosed that Items 202 (broccoli), 300 (apple slices), and 366 (raisins) were imported. After receipt of the responses from the bidders, Respondent's employees further reviewed the bids. Early in this review, Respondent's employees realized that neither bid had complied entirely with the specifications. Among the deficiencies of Mutual's bid was the failure to quote a cost for Item 114, which is chicken wings. Mutual's bid identifies only a product, but no cost. Mutual's bid includes a cost for each of the other 296 items and a total cost, presumably for all 297 items. The ITB projects annual purchases for each of the 297 items. The ITB projects the purchase of 283,044 chicken wings. Petitioner bid 12.5 cents per chicken wing for a total cost of $35,309.50. Mr. Morbach justifiably tried to deduce Mutual's quote for chicken wings from the information contained in its bid. He logically assumed that the cost for Item 114 would be the difference between the total cost shown on Mutual's bid, which is shown on the bid, and the total cost for the other 296 items, which must be calculated separately. The details of Mr. Morbach's calculations did not emerge at the hearing, but it is possible to perform these calculations. Mutual's bid shows a total cost for all 297 items of $8,131,470.29. The total costs of each of the quoted 296 items comes to $6,785,080.14. The difference is $1,346,390.15. This figure clearly does not represent Mutual's bid for chicken wings, which would be thirty-eight times greater than Petitioner's bid and would representative the extraordinary cost of $4.75 per chicken wing. The calculations in the preceding paragraph are taken from Mutual's bid, including all changes shown on the bid, as it was submitted, that were made by Mutual. Mutual's representative initialed these changes. The calculations exclude all adjustments made by Respondent's staff because these calculations, which were made after bid opening, logically have no relevance in determining what, if anything, Mutual quoted for chicken wings. These adjustments can play no role in trying to determine, on the face of Mutual's bid, what it intended to bid for chicken wings. In addition to omitting the cost of one item, Mutual failed to bid numerous other items according to the specifications. Petitioner also failed to bid certain items according to the specifications, although Petitioner's bidding errors are fewer in number and less serious than Mutual's bidding errors. Incorporating the information charted by Food Service Operations staff, the following 25 paragraphs identify the errors in both bids. Item 121 is frozen Grade A turkey roasts with a 60/40 ratio of light to dark meat. Mutual's bid does not reveal the extent of white meat or whether the turkey roast is Grade A meat. Petitioner's bid does not reveal whether its turkey roast is Grade A meat. Item 128 is frozen corn dogs. Mutual bid an unapproved code number for an approved brand. Petitioner's bid complied with the specifications. This is a relatively large component of the overall bid, representing over $160,000 in each of the bids. Item 146 is natural swiss cheese. Mutual bid processed cheese. Petitioner's bid complied with the specifications. Item 202 is Grade A cut broccoli in bulk. Mutual bid an imported product. Petitioner's bid complied with the specifications. Item 220 is shoestring French-fried potatoes. Mutual bid a shorter French-fried potato than specified. Petitioner's bid complied with the specifications. Item 223 is shredded triangle potatoes. Mutual and Petitioner bid the same products, but Mutual's bid did not contain required information regarding grade, oil, and region grown. This is a relatively large component of the overall bid, representing over $140,000 in each of the bids. Item 232 is soft eight-inch tortillas weighing 1.39 ounces per serving. Mutual and Petitioner bid the same product, which weighs only 1.29 ounces per serving. Item 300 is canned sliced apples. Mutual bid an imported product. Petitioner's bid complied with the specifications. Item 328 is light, 26-percent concentration tomato paste. Mutual bid a product that does not meet the minimum- concentration specification. Petitioner's bid complied with the specifications. Item 335 is boneless chicken meat that is predominantly white meat. Mutual and Petitioner bid the same brand, but different product code numbers. Mutual's bid is not predominantly white meat. Petitioner's bid complied with the specifications. Item 366 is seedless raisins. Mutual bid an imported product. Petitioner's bid complied with the specifications. Item 399 is 100 percent semolina, spiral macaroni. Mutual's bid complied with the specifications. Petitioner bid a twisted egg noodle, instead of eggless spiral pasta. Item 431 is sugar sprinkles from one of five approved brands. Mutual bid an unapproved brand. Petitioner's bid complied with the specifications. Item 448 is instant yeast. Mutual's bid includes information on a product that it did not bid. Petitioner's bid complied with the specifications. Item 474 is Grade A Fancy apple jelly with no less than 65 percent soluble solids, and Item 475 is Grade A Fancy grape jelly with no less than 65 percent soluble solids. Neither bid provides sufficient information to determine if it met the specifications on either of these items. Item 480 is Dijon mustard. Mutual bid Dijon-style mustard. Petitioner's bid complied with the specifications. Item 484 is whole pitted medium, ripe olives. Mutual bid an imported product. Petitioner's complied with the specifications. Item 492 is whole, kosher pickles of approximately 95 in number per five gallon pail. Mutual and Petitioner bid larger pickles than specified. Item 505 is 50-grain white vinegar. Neither Mutual nor Petitioner provided the information necessary to determine if its bid complied with the specifications. Items 301, 308, 309, 323, and 331 are, respectively, unsweetened canned applesauce, crushed canned pineapple, sliced canned pineapple, canned pumpkin, and whole canned tomatoes. For each of these items, Mutual's bid did not provide the label to prove quality. Petitioner's bid complied with the specifications. Item 325 is Grade A canned sweet potatoes. Mutual and Petitioner both bid Grade B. Item 212 is yellow frozen squash. Mutual bid an imported product. Petitioner's bid complied with the specifications. Respondent's staff also noted on the chart that the yellow frozen squash was the second item manufactured by Fineline that was imported (the other was Item 202), and staff noted that it was "unable to determine if other frozen vegetables bid by this manufacturer are domestic as grading certificates were not provided." Mutual bid Fineline products for Items 201 (lima beans), 205 (corn), 208 (okra), 209 (peas), 211 (spinach), 214 (Italian-style vegetable blend), and 215 (Oriental-style vegetable blend). Cumulatively, the Fineline frozen vegetables represent a moderately large part of the overall cost, in excess of $53,000 of Mutual's bid. Coupled with the fact that two Fineline products were imported, Mutual's failure to demonstrate affirmatively that these produce are domestic constitutes additional failures to comply with the specifications and supports the inference that the products are imported. In an earlier version of their chart showing bidding errors, Respondent's staff identified problems with Items 217-19, 221-22, and 224. These are potatoes that the ITB specifies must be from the Pacific Northwest and processed in 100 percent canola oil. Respondent's staff determined that it was impossible to identify the source of these potatoes. However, Petitioner was able to document that some, but not all, of the potatoes that it bid for these six items were from the Pacific Northwest. In addition to failing to bid a cost for Item 114 and misbidding the numerous items charted by Respondent's staff, Mutual's bid failed to comply with the specifications for four other items. Item 229 is a frozen Gyro Wrap. Mutual bid a pita- fold bread product, even though a more expensive Gyro Wrap is available from the same manufacturer. Petitioner's bid complied with the specifications Item 378 is pure almond extract flavoring. Mutual bid an imitation flavoring. Petitioner's bid complied with the specifications. Item 402 is thin spaghetti of .062-.066 thickness in diameter. Mutual bid a thin-spaghetti product of 1.6 thickness in diameter. Petitioner's bid complied with the specifications. Item 456 is pancake syrup. Mutual bid an invalid code number. Petitioner's bid complied with the specifications. The parties devoted some attention during the hearing to Item 483, which is green olives. Mutual and Petitioner bid imported green olives, but domestic green olives are not available, at least in institutional quantities, so compliance with the specification of domestic green olives was impossible. Bid Evaluation and Award When Ms. Ebner informed Mr. Morbach of the errors that she had found in both bids, he suggested that they should eliminate the same item from both bidder's bids, if one bidder improperly bid the item. For example, if Mutual misbid fruit cocktail and Petitioner properly bid fruit cocktail, Respondent would delete the cost of fruit cocktail from both bids. The purpose of this adjustment, which reportedly is not atypical in school food procurements, is to avoid the unfair result of lowering the noncompliant bidder's bid, by reducing it for the cost of the misbid fruit cocktail, and leaving the compliant bidder's bid higher by the amount of the properly bid fruit cocktail. Ms. Ebner and Ms. Harrison agreed with this suggestion, and Respondent tabulated the bid costs accordingly. Mr. Morbach also suggested that they consider the bid of one of the disqualified bidders. Ms. Ebner disagreed with this suggestion. She rightly believed that they should not reconsider a bid that did not contain all of the specified items, and Mr. Morbach did not press the matter further. Although Ms. Ebner spoke daily with Ms. Harrison and Mr. Morbach, there were three larger meetings in late June and early July concerning the bids. The first meeting was during the week of June 22, the second meeting was early in the week of June 29, and the third meeting was on the Friday of that week, July 3. The only participants at the first of the three meetings were Ms. Ebner, Ms. Harrison, Mr. Morbach, and Mr. Borrer. For the second meeting, these four persons were joined by Dr. Michael Bookman, the Assistant Superintendent for Business and Research, which includes overall responsibility for the Purchasing Department; Michelle Crouse, of the Auditing Department; and Lee Chistiansen, another of Respondent's staff. The persons present at the third and final meeting were the same as at the second meeting, except that Respondent's counsel, Mr. Few, replaced Ms. Crouse. At the first meeting, Ms. Ebner expressed her belief that Petitioner's bid was better than Mutual's bid because Petitioner's bid complied with more of the specifications. She also expressed concern about the ability of Magic Vending to service the snack foods and beverages. Ms. Ebner's preference for Petitioner's bid was partly the result of her misplaced emphasis on awarding both contracts to the same bidder. It is likely that, at the first meeting, Mr. Morbach or Mr. Borrer informed Ms. Ebner that nothing in the ITB required that Respondent award both contracts to the same bidder. At the first meeting, everyone confirmed their agreement to adopt Mr. Morbach's suggestion to discard the cost of any misbid item in both bids, even if only one bidder misbid the item. Everyone agreed that this approach would facilitate a better comparison of bottom-line prices. Respondent's decision to eliminate the cost of any misbid item from both bids, even if one bid correctly bid the item, encourages bidding abuses. A bidder knowing that a competitor can quote lower prices for a wide range, for instance, of chicken items can neutralize this advantage by misbidding each of the chicken items, forcing Respondent to award the bid without regard to the lesser costs quoted by the competitor for the chicken items. The potential destructive impact on competitive bidding is incalculable where, as here, this kind of bid-tabulation method is unaccompanied by a provision in the ITB rejecting a bid in its entirety if it misbids more than a specified number or value of items. The ITB does not authorize Respondent's method of tabulating misbid items. As already noted, Stipulation 2 allows Respondent to tabulate bids based only on items that meet the specifications, but nothing in Stipulation 2 or anywhere else in the ITB authorizes the deletion of quotes for items bid in compliance with the specifications. Part I of the ITB allows Respondent to reject approved products, but this provision is part of a discussion of items approved for bidding and does not authorized the rejection of a cost quoted for an approved product. Nor do Mr. Morbach and Ms. Ebner rely on Stipulation 2 to justify tabulating bid costs by eliminating the costs of any misbid items, even if only one bidder misbid the item. Mr. Morbach and Ms. Ebner believe that the 1998 ITB permitted this approach, but the 1996 invitation to bid for school food did not. However, both invitations to bid contain Stipulation 2. Respondent has not cited the difference between the 1996 and 1998 invitations to bid to justify the tabulation method adopted by Respondent in this procurement. Respondent's staff have relied on ITB provisions allowing Respondent to waive formalities or reject all bids for support of their tabulation method. However, even if these provisions were not in the 1996 invitation to bid, they do not authorize Respondent's tabulation method. Mr. Borrer may have implicitly acknowledged the inadequacy of the claimed authority in the ITB for Respondent's tabulation method when he sensibly deleted the following language from a draft memorandum dated June 25 and bearing his name, but drafted for his revision by another employee: Products that were inconclusive or failed to meet specification were eliminated from all bids for the purpose of data analysis. Purchasing is given this authority to eliminate products by bid specifications, statutory guidelines and Board policy. Item 4, Page 3 of the bid specifications states, "The District reserves the right to reject any and all bids or parts thereof, and request re-submission. The District further reserves the right to accept a bid other than the lowest bid. . ." In addition, Item I, Page 11 of the bid specifications states, "In reviewing bids, school officials reserve the right to waive technicalities when it is in the best interest of the school system." Also Board Policy H-5.6 states, ". . ., in accepting bids the School Board shall accept the lowest and best bid". (Legal Reference Florida Statutes 230.23, 237.02) The most succinct description of Respondent's tabulation method lacks much of a justification for its use. This description occurs in a typewritten question and answer that appears at the end of Petitioner Exhibit 36, but probably does not belong with that exhibit, which is a fax from Mr. Borrer to Respondent's counsel, Mr. Few. The question is, "Why did you choose to award the contract rather than re-bid after you determined that each vendor had made errors?" The answer states: Bids may not be rejected arbitrarily, but may be rejected and re-bid when it is in the best interest of the public (School District) to do so. . . . To re-bid without changing the bid would be unfair because the vendors had exposed their competitive price structure in public. Through the efforts of our skilled Food Service staff "errors" were discovered in products bid by Mutual and [Petitioner]. Since all vendors bid products that did not meet specifications, we determined that it would be proper to build a mathematical model in which we removed all identified items that did not meet specifications from both vendors. Our analysis based the award criteria on the same set of specifications and conditions for each vendor. Achieving comparability of food products was a complex time- consuming task. The award was recommended to go to the low vendor who would agree and be held to meeting our bid specifications at the price bid. Probably not more than one or two days after the date of the first meeting, Ms. Ebner prepared a draft memorandum, dated June 25, to Mr. Borrer, through Ms. Harrison. The draft memorandum states that Mutual bid 14 items not meeting specifications, and Petitioner bid three such items. The draft memorandum states that Mutual bid 11 items for which compliance was inconclusive, and Petitioner bid five such items. The draft memorandum also states that Mutual bid five imported items, despite the "discussion at the pre-bid conference that only domestic products were allowed." In the draft memorandum, Ms. Ebner recalculated the bottom-line costs of the bids of Petitioner and Mutual after discarding all costs for items that either bidder had misbid. She determined that Petitioner had the lowest snack foods and beverages bid. She also determined that Petitioner had the lower total bid for the main-line food and snack foods and beverages contracts. Still preferring an award of both contracts to a single bidder, Ms. Ebner concluded in the draft memorandum that Respondent should award both contracts to Petitioner, and Ms. Harrison concurred with Ms. Ebner's recommendation. At the same time, Mr. Morbach and Mr. Borrer were headed in the opposite direction from Ms. Ebner and Ms. Harrison. At the direction of Mr. Borrer, Mr. Morbach elicited a letter dated June 24 from Magic Vending to Mr. Morbach, in which Magic Vending stated: "As a follow up to our conversation and subsequent to our bid submission, we are prepared to offer you a reduction in our overall bid of $15,000." The letter concludes: "The purpose of this reduction is to make the overall award process run more smoothly and to remove any potential complications." Although Petitioner had already written Respondent expressing no interest in only the snack foods and beverages contract, Respondent obtained this cost concession, which made Magic Vending's bid lower than Petitioner's bid, in case Petitioner changed its mind. By letter dated June 26 from Magic Vending to Mr. Morbach, Magic Vending assured that it would "abide by all the rules and specifications in addition to giving a $15,000.00 discount . . .." The letter concludes with a well- earned expression of gratitude by Magic Vending for Mr. Morbach's "consideration in this matter." As for the main-line food contract, Mr. Borrer obtained from Mutual a one-line letter dated June 26 from Mutual stating: "This letter is to assure you that all products quoted by [Mutual] on bid #3743-HM will meet the specifications as required." At the second meeting between the staff of Food Service Operations and the Purchasing Department, which evidently took place after the Purchasing Department had received the correspondence from Mutual and Magic Vending, Food Service Operations staff continued to recommend that the contracts be awarded to Petitioner. Everyone discussed the errors in Mutual's bid and the fact that the Magic Vending bid was $5000 more than Petitioner's bid for the snack foods and beverages contract. It is unclear if Ms. Ebner or Ms. Harrison yet knew of the price concession of Magic Vending, but everyone discussed that it would be controversial to award the contracts to a bidder that was not the lowest bidder. Apparently in anticipation of the award ultimately made, Petitioner served Respondent, on July 1, with a Notice of Intent to Protest the award of both contracts. By letter dated the same date, Respondent informed Petitioner that it would not stop the procurement process due to the "critical importance of this bid and the serious danger to the health of our children." In fact, Mutual and Magic Vending have been supplying main-line food and snack foods and beverages, respectively, since early August 1998. At the third meeting between the staff of Food Service Operations and the Purchasing Department, everyone agreed to recommend that the School Board award the contracts to Mutual and Magic Vending. The discussion at this last major staff meeting largely involved the matters that they had previously discussed. Unfortunately, no one ever discussed at these or other meetings involving Ms. Ebner how many errors a bid could contain before it should be disqualified. Likewise, no one ever discussed with her the distinction between awarding a contract on the basis of the lowest bid and on the basis of the lowest and best bid. However, Ms. Harrison discussed with Ms. Ebner the safety issues presented by imported, rather than domestic, foods. On the day prior to the July 7 School Board meeting now designated for the School Board to vote on the awards, Ms. Harrison advised Mutual by letter that Respondent's staff would recommend Mutual, "provided that any and all products found not to meet specifications will be replaced with products meeting specifications at the original bid cost." Petitioner Exhibit 13, which is a copy of this letter, lacks the attachment listing the noncompliant items. At the bottom of the July 6 letter is a signature space for Mutual's representative, indicating assent to the following sentence: "Indicate, by signing below, that you are in agreement to provide all products meeting specifications, including USDA Grade A products, at the original bid price." Petitioner Exhibit 13 contains the signature of Mutual's representative. On July 7, the School Board met and gave Petitioner's counsel and corporate representative brief opportunities to explain why Respondent should not award the main-line food contract to Mutual. However, the Board did not give Petitioner's representatives sufficient time to convey much meaningful or detailed information. Mr. Few, Dr. Bookman, and Ms. Harrison supplied the Board with more information, but unfortunately never disclosed that Mutual's bid contained more errors than did Petitioner's bid and that Mutual's bid contained more errors involving more substantive matters than did Petitioner's bid, as discussed below. Contradicting the advice given by Mr. Morbach at the pre-bid conference and ignoring the contrary provision in the ITB and ignoring the distinction in the ITB between items that the winning bidder may purchase additional items that may be bid, Mr. Few advised the Board that the ITB expressed only a preference toward domestic products and cited the unique example of olives as support for this interpretation. Dr. Bookman advised the Board that Mutual had assured them that all items bid were Grade A. He was evidently unaware that, as explained below, Mutual had still not obtained Grade A turkey roast, even though Grade A turkey roast is available. As late as the final hearing, Ms. Ebner admitted that Mutual had still not corrected one or two noncompliant items, although it is unclear if one of them is the turkey roast. Notwithstanding staff's assurances, several Board members expressed misgivings at having to absorb a lot of detailed information in a short period of time. Ms. Harrison informed the Board that they did not have time to defer action, implicitly and correctly informing them that they did not have time to rebid the main-line food contract. One Board member replied that she wanted all of the food to be USDA approved and that parents had enough to be concerned about without being concerned about what Respondent was feeding their children. A motion to award the contracts to Mutual and Magic Vending failed by a 3-4 vote. A second motion to delay awarding these contracts passed 5-2, so that, individually, Board members could talk to staff to learn more about the bids and Petitioner's claim of bidding improprieties. The record does not reveal what staff told individual Board members. After a recess during which Board members, individually, met with staff, one of the Board members who had previously voted not to award the contracts moved to award the contracts to Mutual and Magic Vending, saying that Mutual had agreed to replace noncomplying products with products meeting the specifications. Relying on Mutual's promise to deliver conforming food items, as opposed to the noncomplying items that it had bid, this Board member reasoned that it was one thing to make a mistake with a bid, but another thing to make a mistake with the schoolchildren. The School Board unanimously approved the motion, and the meeting ended. By letter dated July 9 from Mutual to Mr. Borrer, Mutual addressed each of the 25 items charted by Respondent's staff, acknowledging that Mutual's bid had not complied with the specifications for nearly every charted item, but promising that Mutual would supply a product meeting the specifications for all of these items. However, concerning the moderately large component of the bid represented by Item 121 (turkey roasts, which represented over $62,000 in Mutual's bid), the letter states only: "Currently trying to locate an item to meet specifications." Bid Protest On July 10, Petitioner served Respondent with a Protest. The Protest asserts that Mutual's bid did not contain prices on all items, did not propose all domestic products, contained unapproved brands, bid unapproved product codes, and bid products different from those specified in the ITB. The Protest asserts that Respondent allowed Mutual to provide a letter after the deadline for receiving bids assuring that it would provide all Grade A product, as specified in the ITB. The Protest did not mention the snack foods and beverages contract awarded to Magic Vending. The Protest does not allege that Petitioner's bid is responsive. Respondent has not filed any responsive pleading raising the question of the responsiveness of Petitioner's bid. Respondent's Bid Policies Following receipt of Petitioner's Notice of Intent to Protest, Mr. Borrer sent a letter dated July 1 to Petitioner that contained Respondent's rules governing bids. This document, which is part of Petitioner Exhibit 37, is the source of Respondent's bidding rules set forth in the following two paragraphs. Respondent's rules provide for the protest of specifications as follows: Specifications—Any bidder that feels that their firm is adversely affected by an specification contained in a Sealed Bid or Request for Proposal issued by the Purchasing Department may file a written notice of protest with the Supervisor of Purchasing within seventy-two (72) hours after the receipt of the bid documents. . . . A formal written protest shall be filed by the bidder within ten (10) days of the written notice of protest. . . . These rules also provide for the awarding of costs, but not attorneys' fees, as follows: If, after the completion of the Administrative Hearing process and any appellate court proceedings[,] the School District prevails, then the School District shall recover all costs and charges which shall be included in the Final Order or Judgement, including charges made by the Division of Administrative Hearings, but excluding attorney's fees. . . . If the protestor prevails then the protestor shall recover from the School District, all costs and charges which shall be included in the Final Order or Judgement, excluding attorney's fees. Another source of Respondent's rules in the record is Chapter 7 of a compilation of Board policy that was applicable to the present procurement. This document requires that Respondent award bids "on the basis of the lowest and best bid which meets specifications with consideration being given to the specific quality of the product, conformity to the specifications, suitability to school needs, delivery terms and service and past performance of the vendor." Lastly, Mr. Borrer, by memorandum to the file dated July 9, noted that the two disqualified vendors were disqualified under Board Policy H-5.10, which states: "Bids received which do not meet specifications shall not be considered valid and shall not be tabulated." Ultimate Findings of Fact Bid Tabulation Method Is Clearly Erroneous, Contrary to Competition, and Arbitrary It is irrelevant whether the standard of proof governing a protest of specifications is a preponderance of the evidence or the more deferential standard, clearly erroneous, contrary to competition, arbitrary, or capricious. Petitioner has proved that Respondent's tabulation method is clearly erroneous, contrary to competition, and arbitrary. As already noted, Respondent's tabulation method potentially penalizes compliant bidders by eliminating their compliant items from the tabulation when a noncompliant bidder misbids the same item. The anti-competitive, arbitrary effect of this tabulation method may be ameliorated somewhat by the fact that the ITB is for a cost-plus contract. However, the ITB fails to impose any minimum requirement or threshold for compliant items, in terms of number or dollar volume--e.g., if a bid contains noncompliant items totaling more than one percent of the total cost bid, then the entire bid is rejected. This means that Respondent's tabulation method can destroy the competitiveness of the procurement by allowing a bidder purposefully or unintentionally to misbid a large number of items, resulting in the effective elimination of these items from the tabulation of bids submitted by bidders with superior access to these items. Under these circumstances, Respondent's selection of this tabulation method was clearly erroneous, contrary to competition, and arbitrary. Mutual's Bid Is Nonresponsive The standard of proof governing Respondent's determination that Mutual's bid was responsive is clearly erroneous, contrary to competition, arbitrary, or capricious. As already noted, it is impossible to deduce Mutual's quote for Item 114 from the face of Mutual's bid. A failure to quote a cost for an item is little different from a failure to bid the item. In the case of a complete omission, Respondent knows nothing of the item bid; in the case of the omission of only a quote, Respondent knows what item the bidder has bid, but not the cost of the item. The omission of the cost of a single item adequately described in the bid may be a minor irregularity, if the cost can be deduced by subtracting from the total cost of all items the total cost of all but the omitted item. Here, though, the difference between these amounts is clearly wrong, so that, if Respondent overlooks the omission, it leaves open the possibility of a later dispute over the cost of Item 114. Under the present circumstances, including the disqualification of two other bidders for omitting items, Respondent's failure to disqualify Mutual's bid was clearly erroneous, contrary to competition, and arbitrary. Mutual's Bid Contains Material Variances The standard of proof governing Respondent's determination that Mutual's bid did not contain material variances from the ITB is clearly erroneous, contrary to competition, arbitrary, or capricious. Food Service Operations staff identified numerous deficiencies in Mutual's bid. For Mutual's bid, Ms. Ebner's June 25 memorandum counts 14 items not meeting specifications and 11 items for which compliance is inconclusive due to Mutual's failure to submit the required documentation. Treating the misbidding of green olives and the potatoes specified in Items 217-19, 221-22, and 224 as minor irregularities due to the impossibility of compliance with the specifications concerning the origin of these items, Mutual's bid still reveals consequential deviations from the specifications. Using only the chart prepared by Food Service Operations staff and disregarding the green olives and six potato items, Mutual's consequential deviations from the specifications include five imported foods, two meat products that fail to contain the required ratio of light to dark meat (one of the meat products and another product also failing to demonstrate the proper Grade), a lower Grade of canned sweet potatoes, shorter French Fries, excessively diluted tomato concentrate and inadequate documentation of the dilution of two jelly products, processed instead of natural cheese, and a missing ingredient from Dijon mustard. Of all the witnesses, Ms. Ebner was most capable, by training, experience, and job assignment, of understanding the significance of the deviations in Mutual's bid. For instance, addressing the seemingly inconsequential matter of excessively diluted jelly, Ms. Ebner noted that Respondent had had problems with runny jelly not remaining on peanut-butter- and-jelly sandwiches. The nutritional consequences of this seemingly harmless deviation are students discarding peanut- butter-and-jelly sandwiches that have lost their jelly. In each of these consequential deviations from the specifications, Mutual bid a cheaper product than specified, which conferred upon it an unearned competitive advantage, and a product of lower quality than specified, which jeopardized the primary purpose of the specifications to ensure that Respondent obtained food of high nutrition, safety, and taste for students and staff. Any implicit or explicit determination by Respondent dismissing the charted findings of deviations by Food Service Operations staff or treating them as minor irregularities rather than material variances would be clearly erroneous, contrary to competition, and arbitrary. Besides the findings contained in the chart prepared by Food Service Operations staff, Mutual misbid several other items. The consequential deviations from the specifications included seven imported items, a cheaper pita- fold than the specified Gyro wrap, and a cheaper imitation almond flavoring for pure almond flavoring. Any express or implied finding by Respondent discrediting these deviations would be clearly erroneous, contrary to competition, and arbitrary. Although an express or implied determination by Respondent that these deviations, standing alone, are minor irregularities would not be clearly erroneous, contrary to competition, arbitrary, or capricious, such a finding concerning these deviations, together with the previously discussed deviations charted by Food Service Operations staff, would be clearly erroneous, contrary to competition, and arbitrary. The standard of proof governing the determination that Mutual submitted written assurances, after bid opening, that it would supply product in compliance with the specifications, is the preponderance of the evidence. However, the standard of proof governing findings of the significance of the submittal of these assurances is clearly erroneous, contrary to competition, arbitrary, or capricious. Any implied or express determination by Respondent that Mutual's written assurances were not an attempt to change its bid after bid opening would be clearly erroneous, contrary to competition, and arbitrary. As already noted, Petitioner has already proved, by this deferential standard, that Mutual's bid contained material variances from the specifications. The purpose of Mutual's written assurances was to eliminate these material variances, which, in fact, were still not entirely eliminated by the time of the final hearing. Petitioner's Bid Contains Material Variances Consistent with its determination that Mutual's bid is responsive and suffers no material variances, Respondent claims in its proposed recommended order that Petitioner's bid is responsive and contains no material variances. Respondent awarded the main-line food contract to Mutual because it submitted the lower bid. However, Petitioner demands the award of the main- line food contract, so it is necessary to consider whether its bid, which is clearly responsive, contains any material variances. Because of the resolution of this issue, it is unnecessary to consider whether Petitioner's bid contains any minor irregularities, for which Respondent's implied or express refusal to waive would be clearly erroneous, contrary to competition, arbitrary, or capricious. Using the chart prepared by Food Service Operations staff and disregarding the green olives and six potato items, Petitioner misbid only seven items. In fact, the record reveals no other misbid items by Petitioner. Several of Petitioner's misbid items are relatively inconsequential. These are a tortilla slightly lighter than specified, larger pickles than specified, and omitted documentation showing the grain of vinegar. Mutual misbid these items also. However, three of Petitioner's misbid items are consequential. Although Petitioner's bid reflects the specified ratio of light and dark meat, unlike Mutual's bid, Petitioner's bid of turkey roast fails, as does Mutual's bid, to provide sufficient documentation to show that it is Grade A. Like Mutual's bid, Petitioner's bid is for Grade B canned sweet potato and fails to provide documentation that the two jelly products are not excessively diluted. The only consequential deviation in Petitioner's bid not found in Mutual's bid is Petitioner's failure to bid an eggless pasta. However, the standard of reference for determining whether Petitioner's bid contains material variances is not Mutual's bid, but the ITB. Although considerably more compliant than Mutual's bid, Petitioner's bid, when measured against the ITB and the importance of obtaining nutritious, safe, and tasty food for Respondent's schoolchildren, also falls impermissibly short of the mark. Petitioner's consequential deviations from the specifications also mean cheaper items than specified, through which Petitioner would have obtained an unearned competitive advantage, and products of lower quality than specified, which would have jeopardized the primary purpose of the ITB to ensure that Respondent obtained high-quality food. Impossible specifications, like domestic green olives or six potato items from the Northwest, or the failure to comply in some minor respect, such as sugar sprinkles from an unapproved manufacturer or excessively large pickles, may constitute minor irregularities. But the failure to ensure that each of the 297 items bid complies substantially in quality is not. Thus, an implied or expressed determination by Respondent that Petitioner's bid contains no material variances would be clearly erroneous, contrary to competition, and arbitrary. Petitioner has failed to prove that Respondent is liable for attorneys' fees. There is no direct proof of any factual basis to award fees. Perhaps Petitioner infers an improper purpose from the fact that, despite the benefit of highly deferential standards of proof, Respondent has not prevailed. Obviously, Respondent's failure to prevail is due to several express or implied determinations that were clearly erroneous, contrary to competition, arbitrary, or capricious. If this fact alone warranted a fee award, all agencies would be liable for fees in every bid case that they lost. The absence of such a statutory provision reveals the Legislative intent not to make agencies strictly liable for attorneys' fees in bid cases. The better approach is to permit an inference of improper purpose, but only if the agency were aware or reasonably should have been aware that its handling of the award was not merely clearly erroneous, contrary to competition, arbitrary, or capricious, but was so egregiously so as to support an inference of improper purpose. Such is not the case here. There is no evidence of Petitioner's costs, and Petitioner did not request the administrative law judge to reserve jurisdiction or leave the record open for a later determination of costs.
Recommendation It is RECOMMENDED that the School Board of Hillsborough County enter a final order setting aside the award of the main-line food contract to Mutual Distributors, Inc., and rebidding the contract. DONE AND ENTERED this 17th day of November, 1998, in Tallahassee, Leon County, Florida. ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 17th day of November, 1998. COPIES FURNISHED: Dr. Earl Lennard Superintendent School Board of Hillsborough County Post Office Box 3408 Tampa, Florida 33601-3408 Robert W. Rasch 129 Live Oak Lane Altamonte Springs, Florida 32714 W. Crosby Few Few & Ayala, P.A. 109 North Brush Street, Suite 202 Tampa, Florida 33602
The Issue The issue in this proceeding is whether the award of a bid for the sale of scrap metal to Cumbaa Enterprises, Inc. was arbitrary, capricious, clearly erroneous, or contrary to competition or the bid specifications.
Findings Of Fact On January 19, 2011, the Department issued Invitation to Bid (ITB) #10-Apalachee-8252. The ITB was a revenue- generating contract for the sale of scrap metal at Apalachee Correctional Institution in Sneads, Florida. Since the contract would generate revenue to the State, the Department’s purpose was to award the contract to the highest responsive bid and developed bid specifications and criteria to accomplish that goal. The specifications for the ITB stated in relevant part: Material Deviations: The Department has established certain requirements with respect to bids to be submitted by bidders. The use of shall, must or will (except to indicate simple futurity) in this ITB indicates a requirement or condition which may not be waived by the Department except where the deviation therefrom is not material.[emphasis added]. A deviation is material if, in the Department’s sole discretion, the deficient response is not in substantial accord with this ITB’s requirements, provides an advantage to one bidder over other bidders, has a potentially significant effect on the quantity or quality of items bid, or on the cost to the Department. Material deviations cannot be waived and shall be the basis for rejection of a bid. Minor Irregularity: A variation from the ITB terms and conditions which does not affect the price of the bid or give the bidder an advantage or benefit not enjoyed by other bidders or does not adversely impact the interests of the Department. 1.10 Responsive Bid: A bid submitted by a responsive and responsible vendor that conforms in all material respects to the solicitation. * * * 4.3.1 Submission of Bids Each bid shall be prepared simply and economically, providing a straightforward, concise delineation of the bidder’s capabilities to satisfy the requirements of this ITB, fancy bindings, colored displays, and promotional material are not desired. Emphasis in each bid must be on completeness and clarity of content. In order to expedite the review of bids, it is essential that bidders follow the format and instructions contained in the Bid Submission Requirements (Section 5), with particular emphasis on the Mandatory Responsiveness Requirements. Rejection of Bids The Department shall reject any and all bids containing material deviations. The following definitions are to be utilized in making these determinations. Material Deviations The Department has established certain requirements with respect to bids to be submitted by bidders. The use of shall, must or will (except to indicate simple futurity) in this ITB indicates a requirement or condition which may not be waived by the Department except where the deviation therefrom is not material. A deviation is material if, in the Department’s sole discretion, the deficient response is not in substantial accord with the ITB’s requirements, provides an advantage to one bidder over other bidders, has a potentially significant effect on the quantity or quality of items bid, or on the cost to the Department. Material deviations cannot be waived and shall be the basis for rejection of a bid. Minor Irregularities A variation from the ITB terms and conditions which does not affect the price of the bid or give the bidder an advantage or benefit not enjoyed by other bidders or does not adversely impact the interests of the Department. As indicated, Section 5 of the specifications outlined the contents of the bid. Section 5 stated in relevant part: SECTION 5 - CONTENTS OF BID This section contains instructions that describe the required format for the submitted bid. Bids shall be submitted in a sealed envelope, clearly marked “Bid - ITB#- Apalachee-8252”. . . . . [T]he following paragraphs contain instructions that describe the required format for bid responses. Responsiveness Requirements The following terms, conditions, or requirements must be met by the bidder to be considered responsive to this ITB. Failure to meet these responsiveness requirements may cause rejection of a bid. [emphasis added]. Bidder shall complete, sign and return the ITB Bidder Acknowledgement Form (page 1 & 2). The bidder must return either the original or a copy of both pages with an original signature on page one (1). The bidder shall complete, sign, date, and return (all) pricing pages, entitled Cost Information Sheet, which consists of page 28. By submitting a bid or bids under this ITB, each bidder warrants its agreement to the prices submitted. The Department objects to and shall not consider any additional terms or conditions submitted by a bidder, including any appearing in documents attached as part of a bidder’s response. In submitting its bid, a bidder agrees that any additional terms or conditions, whether submitted intentionally or inadvertently, shall have no force or effect. Any qualifications, counter-offers, deviations, or challenges may render the bid un-responsive . . . . * * * 5.3 Certificate of Insurance Bidders shall return a fully executed Certificate of Insurance . . . . In this case, Section 5.1 contains two bid specifications essential to a bid's responsiveness. Those two requirements were submission of a signed and completed, original or copy, of the bidder acknowledgement form and submission of a completed Cost Information Sheet. The Cost Information Sheet is not at issue here. The bidder acknowledgement form is a double-sided Department of Management Services form containing general boilerplate contractual language. The back of the form is a continuation of standard contractual terms from the front. Oddly, signatures acknowledging these terms and the terms of the ITB are on the front page (page 1) of the form. By signing the front page of the bidder acknowledgement form the bidder agrees to abide by all conditions of the bid. The remainder of Section 5 of the ITB contains bid specifications that are not considered essential to determine the initial responsiveness of the bid at the bid opening, but are to be returned at some later point in time after the bid's are opened. However, the language of Section 5 effecting that intent is unclear. In particular, the bid specification contained in Section 5.3 requires the bidder to "return" an "executed" Certificate of Insurance. The Certificate of Insurance provides the Department with proof of a variety of required insurance coverage of the vendor. However, later in the ITB Section 7.14 clarifies that the Certificate of Insurance need only be supplied with the later-signed contract documents. Section 7.14 states, in relevant part: 7.14 Contractor's Insurance The contractor shall not commence any work in connection with this ITB . . . until he has obtained all of the . . . types of insurance and such insurance has been approved by the Department. The Department shall be furnished proof of coverage of insurance by Certificates of Insurance . . . accompanying the contract documents and shall name the Department as an additional named insured [emphasis added]. Indeed, the evidence demonstrated that the Department has long interpreted these provisions to require a winning bidder to provide Certificates of Insurance at the time a contract is entered into and not as part of the essential requirements of the bid due at bid opening. While the Department could (and probably should) clarify this provision, its interpretation of its bid specifications is not unreasonable under these facts. In this case, five bids were timely submitted in response to the ITB, including those of K & M and Cumbaa. On March 8, 2011, the Department opened bids for the ITB. Cumbaa submitted the highest bid for the contract, at $22,197.48. K & M submitted the next highest bid at $20,001.00. At the bid opening, Cumbaa's bid included a Cost Information Sheet, a copy of the signed front page of the bidder acknowledgement form, and the Contact for Contract Administration form known as Attachment 1. However, the bid did not contain the second side of the bidder acknowledgement form or a Certificate of Insurance form at the time the bid was opened. K & M's bid contained the same documents as Cumbaa's bid, as well as the second side of the bidder acknowledgement form and a number of certificates of insurance for K & M. The evidence showed that Cumbaa did not include the Certificate of Insurance form in its sealed bid upon the advice of the Department that the form was not required at bid opening. However, Cumbaa had insurance coverage in place at the time of the bid opening and faxed its certificates of insurance to the Department on March 10, 2011. Given these facts and the Department's reasonable interpretation of its ITB, the omission of Cumbaa's certificate of insurance was neither required at the time of the bid opening, nor material to the award of the bid. The omission of the second page of the bidder's acknowledgement form was not noticed by anyone reviewing the bids until its omission was pointed out by K and M in this bid protest. Cumbaa faxed a copy of the back side of the document to the Department on April 11, 2011. Clearly, this lack of notice demonstrates the immateriality of the back side of the bidder's acknowledgement form. Additionally, since the signatures of both bidders were on the front page of the form submitted by them and those signatures bound the bidders to the terms of the ITB, there was no evidence that demonstrated why submission of a copy of the back side of the form was material to the award of this bid. Ultimately, the Department reviewed the bids for responsiveness and determined that Cumbaa was the highest responsive bid. On March 11, 2011, the Department posted its intent to award the bid to Cumbaa Enterprises, Inc. As indicated, there was no evidence that the omission of these two documents from the Cumbaa bid were material deviations from the bid specifications since neither omission impacted the ultimate contract requirements and did not materially impact the integrity of the bid process. Indeed, the insurance certification was not required for responsiveness under Section 5.1 of the bid under a long-standing and reasonable interpretation of that requirement by the Department. For these reasons, this bid protest should be dismissed.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent, Department of Corrections, enter a final order dismissing the Protest of K & M Pine Straw. DONE AND ENTERED this 1st day of July, 2011, in Tallahassee, Leon County, Florida. S DIANE CLEAVINGER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 1st day of July, 2011. COPIES FURNISHED: Kurt Eldridge K and M Pine Straw 20583 John G Bryant Road Blountstown, Florida 32424 Edith McKay, Esquire Department of Corrections 2601 Blair Stone Road Tallahassee, Florida 32399-2500 Edwin G. Buss, Secretary Department of Corrections 2601 Blair Stone Road Tallahassee, Florida 32399-2500 Jennifer Parker, General Counsel Department of Corrections 2601 Blair Stone Road Tallahassee, Florida 32399-2500
The Issue Whether the Barton-Malow Southern, Inc., deviated from the bid requirements, and if so, whether such deviation consists of a minor deviation which may be waived by the respondent, or whether Ron A. Royal, Inc., should be awarded the elementary school "C" project as the lowest responsive bidder.
Findings Of Fact On April 20, April 27, and May 4, 1986, the Board advertised its Notice of Call for Sealed Bids, soliciting bids for the construction of Elementary School "C". The notice advised that the contract to be awarded would require approval of subcontractors by the Board and stated that the Board "reserves the right to reject any and all bids received and to waive any and all informalities in regard thereto." A pre-bid conference was held on May 15, 1986, at which time the potential bidders were advised that page 14 of the bid documents entitled "List of Subcontractors" would be deleted and addendum #1 would include a more specific list of subcontractors to be completed by the bidder. The original list of subcontractors stated: The undersigned, hereinafter called "Bidder", list below the names of all the subcontractors who will perform under the Bidder. Any work item (Trade) not included will be assumed by the owner as being performed by the Bidder's own forces." A space was provided for the bidder to state the work item and the name of the subcontractor who would perform the work. Addendum #1 instructed the bidders to delete the original page C.14 and insert the enclosed sheet C.14 (addendum #1) "List of Subcontractors" for submission with the sealed bids. The substituted list of subcontractors provided as follows: The undersigned, hereinafter called "Bidder", lists below the names of the subcontractors who will perform under the Bidder. In the event the general contractor will perform one of the phases listed with his own personnel, he shall state by "general contractor". The form listed 20 specific areas of work, such as site work, iron and steel work, roof decks, and electrical, and provided a space for the bidder to fill in the firm name and address of the subcontractor for each specific area. Bids were submitted to the Board by nine (9) general contractors. The lowest bid by $310,000, was submitted by Barton-Malow; the second lowest bid was submitted by Royal. On the list of contractors submitted with Barton Malow's bid, Barton- Malow listed "G.C". (General Contractor) for the work areas described as site work, concrete work, masonry work iron and steel work, and lathing and plastering. Barton-Malow listed a subcontractor and "G.C." for phases described as hard tile and electrical. For the work areas described as "roof decks" and "roofing and sheet metal" three (3) subcontractors were listed for each of the areas. The list submitted by Royal with its bid provided that the concrete work would be performed by the general contractor and listed a single subcontractor for each of the other 19 areas of work specified. Barton-Malow was the only bidder who listed multiple subcontractors for a specified work area. In the blanks provided for the subcontractors' addresses, Royal listed the city where each subcontractor was located; Barton-Malow did not provide any addresses bout stated at the top of the column "will be advised upon request." None of the bidders provided street addresses for the subcontractors, however, only one bidder other than Barton Malow failed to provide the city in which the subcontractor was located. Immediately after the bids were opened and read, 1/ the meeting was adjourned and Mr. Derryberry, Mr. Collins, and two other people reviewed the bids. Mr. Derryberry concluded that the Barton-Malow bid was not in compliance with the bid requirements due to the manner in which Barton-Malow had filled out the subcontractor list. Mr. Derryberry therefore recommended to the Board that the Barton-Malow bid be rejected because of the perceived irregularities and the bid of Royal be accepted. The recommendation of the architect was adopted as the recommendation of the school administration and presented to the Board at a public meeting on June 3, 1986. The Board received the report of the architect and the administration, heard from the attorneys and representatives of Barton- Malow and Royal, and then voted to waive any irregularities and accept the Barton-Malow bid. The original page C.14 was approved by the Board in about 1980 and used since that time. However, there had been some difficulty with that form on two different jobs within the last six months, and therefore it was decided to clarify the purpose of the form by specifically listing all the major subcontracting areas. The intent was to require all bidders to list the primary subcontractor in each of the major work areas, and thus prevent bid shopping after the bids were opened. The architect, Mr. Derryberry, prepared and included the amended form C.14 as part of Addendum #1 to the bid documents. Although the Board never formally approved the amended form, Mr. Derryberry had the authority to clarify any of the bid documents by addendum. Page C.14 (Addendum #1) lists 20 major subcontracting areas; however, in almost all of the areas it would be possible for more than one subcontractor to perform the designated work, and in several areas it would be unlikely that one subcontractor would perform all the required work. For example, site work includes paving, earth moving, culvert work, fencing, and irrigation, and one subcontractor would not normally do the work in all those areas. The amended page C.14 does not state that only one subcontractor should be listed for each specified work area. The bidders were not advised at the pre-bid conferences or subsequent thereto, that only one subcontractor should be listed in each category. The only information the bidders received regarding the list of subcontractors was the information contained on the revised page C.14. In other words, the bidders were simply directed to list "the names of the subcontractors who will perform under the Bidder", and to list general contractor when "the general contractor will perform one of the phases listed with his own personnel." In the subcontractor list submitted with their bid, Barton-Malow listed "Batten Electric Co./G.C." for the subcontract "Electrical", and listed "Bauer & Assoc./G.C." for the "Hard Tile" subcontract. The listing of a subcontractor and the general contractor in these areas is not a deviation from the bid requirements. There is no indication on the list submitted by Barton- Malow that the listing of a subcontractor and the general contractor in the hard tile and electrical categories meant anything other than both the subcontractor and the general contractor would perform the work required in those areas, and there was no evidence presented at the hearing that would require a different conclusion. 2/ Categories 5 and 6 on the subcontractor list are "roof decks" and "roofing and sheet metal." Although listed as two separate categories, the same subcontractor would have to perform both due to the bid requirements. Further only one subcontractor can perform the roofing work; it is not an area that is divisible into subcategories that can be performed by different subcontractors. For categories 5 and 6, Barton-Malow listed "H. H. Robertson/Architectural Exteriors/Commercial Roof Decks." As admitted by Barton-Malow, that all three subcontractors "will perform" the subcontract is an impossibility. 3/ From the list submitted by Barton-Malow it cannot be determined who will perform and be responsible for the roofing work. When asked at the hearing who was going to perform the roofing work for Barton Malow, the vice-president of operations for Barton-Malow responded, "One of those three would have done it." He indicated that a submission would have been made to the Board designating the subcontractor. By listing three subcontractors for the two roofing categories, Barton-Malow deviated from the bid requirements. The subcontractor list contained one basic requirement, that the subcontractors listed "will perform." By listing three subcontractors for the roofing, when only one subcontractor could performs Barton-Malow would be able to bid shop for subcontractors after the bid submission. This would give Barton Malow a definite advantage over the other bidders who complied with the bid requirements and listed only the one contractor who would perform the work. The other bidders would be bound to use the subcontractor listed and therefore, would be unable to negotiate for a better price after obtaining the contract. However, by listing multiple subcontractors, Barton-Malow would be able to negotiate for a better price because it had not committed itself to any one subcontractor. In five categories, site work, concrete work, masonry work, iron and steel work, and lathing and plastering, Barton Malow listed general contractor. About an hour after bid opening, Mr. Derryberry called Mr. Polso, the Vice- President of Operations for Barton-Malow, to inquire about the bid because it was so much lower than the other bids. Mr. Polso assured Mr. Derryberry that there had been no mistake in the amount bid. Mr. Derryberry then asked about the listing of general contractor for the iron and steel work because he had never known of a general contractor doing that type of work. Mr. Polso stated that he had not had time to determine the low bidder in that category and was still getting prices. He also said that Barton-Malow would not be doing the lathing and plastering. However, when Mr. Derryberry advised that he was recommending that the bid be disqualified due to the incompleteness of the subcontractors form and asked whether Barton-Malow wished to withdraw its bid, Mr. Polso stated that Barton-Malow had no intention of withdrawing its bid. Subsequently, Mr. Polso met with Mr. Derryberry and Mr. Collins at the school offices and advised them that Barton-Malow had every intention of performing the work where general contractor had been listed. Barton-Malow is a wholly owned subsidiary of Barton Malow Company and has the resources of Barton-Malow Company available when necessary. In 1985, Barton-Malow did between 60 and 70 million dollars of construction work; Barton- Malow Company had a dollar volume of 600 million dollars. Barton-Malow has the capacity to perform work in the areas where it listed general contractor. Barton-Malow prepares its bid by estimating the value of the total project and the value of the majority of the specific trades involved. If Barton-Malow does not receive a bid from a subcontractor that it feels is competitive in a particular trade area, it performs that work itself. The C.14 (Addendum #1) form permitted a bidder to list "general contractor" in any or all subcontract areas in which it would perform the work with its own personnel. Once the bids are opened, the bidder cannot unilaterally substitute a subcontractor for the general contractor. The general contractor would be required to do the work unless it received authorization to substitute a subcontractor based upon a showing of good cause. The evidence does not support a finding that Barton-Malow was incapable of performing the work in the areas in which it listed "general contractor." Therefore Barton- Malow did not deviate from the bid requirements by listing "general contractor" in five of the twenty specified areas. Although Baron-Malow deviated from the bid requirements by failing to list any addresses on its subcontractor list, this was a minor irregularity which did not give Barton-Malow any competitive advantage over the other bidders. In Division C, Article 5, Section 5.3.1., the bid documents provide: It is the intent of the owner to award a Contract to the lowest responsible Bidder provided the Bid has been submitted in accordance with the requirements of the Bidding Documents....The Owner shall have the right to waive any informality or irregularity in any Bid or Bids received and accept the Bid or Bids which in his judgment, is in his own best interests.
The Issue Whether the Department of Management Services acted arbitrarily, fraudulently, illegally or dishonestly in rejecting the bid proposed by Petitioner Stimsonite Corporation; and Whether the Department of Management Services' proposed award of a contract to Minnesota Mining and Manufacturing, Inc. was arbitrary, illegal, fraudulent or dishonest.
Findings Of Fact On or about October 30, 1995, DMS mailed to interested vendors ITB No. 20-550-590-A for Sign Material, Reflective Sheeting & Related Materials. Stimsonite and 3M were among the vendors who received copies of the ITB. After receiving the ITB, no interested vendor, including Stimsonite and 3M, requested that DMS clarify any of the ITB's general or special terms and conditions. Similarly, no one timely filed any protest to challenge any ITB terms or conditions. On or about December 28, 1995, DMS opened the bids submitted in response to the ITB. Thereafter, DMS evaluated the bids and determined which were responsive to the ITB requirements. Stimsonite and 3M were the only vendors to submit bid prices for ITB Item Nos. 13, 15, and 22, which pertain to reflective sheeting. DMS's bid tabulations reflect that 3M and Stimsonite offered the following bid prices, per square foot, for reflective sheeting under ITB Item Nos. 13, 15, and 22: Item No. 13 15 22 Stimsonite $3.5489 $3.2199 $3.2199 3M $3.588 $3.25 $3.25 On or about January 23, 1996, DMS posted the bid tabulations. DMS's bid tabulations specify an NAS (not as specified) code indicating reasons why it rejected certain bids. Stimsonite's bids on ITB Item Nos. 13, 15, and 22 were rejected as non-responsive with an indication of NAS Code 1. NAS Code 1 provides: "Vendor did not submit diskette as required by the bid." Stimsonite admittedly did not include a computer diskette with its 1995 bid. Because of the absence of the diskette, the Stimsonite bid had neither a price list nor a material list. No responding vendor, except 3M, included a computer diskette in response to the 1995 ITB. l3. DMS consistently rejected all bids submitted in response to its 1995 ITB which failed to include the required computer diskette(s). In evaluating the 1995 bids, DMS reviewed the material list information that 3M submitted with its bid in hard copy and on computer diskette. DMS posted its intent to award the bid to the only fully responsive bidder, 3M. Shortly after DMS posted the 1995 bid tabulations with its intent to award to 3M as the only responsive bidder, Stimsonite urged DMS to accept a materials list that Stimsonite had prepared on computer diskette. DMS refused to accept this diskette, which Stimsonite was offering nearly a month after the 1995 bid opening date. DMS rejected Stimsonite's late offering of the diskette because it was offered after bid opening, because it was offered after evaluation of bids, and because DMS's intent to award already had been posted. However, the greater weight of the evidence is that Stimsonite's after-offered diskette would not have met the 1995 ITB specifications even if it had been submitted simultaneously with Stimsonite's bid response. The after-offered diskette failed to offer the required size widths of reflective sheeting or the accessory items used with the sheeting such as process colors, inks, clears, and thinners. Stimsonite timely challenged the rejection of its 1995 bid as non- responsive and timely challenged DMS's intent to award the contract to 3M. Stimsonite contended, with regard to its failure to timely submit a conforming diskette, that the clear language of the 1995 ITB did not require the submission of a diskette for the items Stimsonite had chosen to bid on, and that submission of such a diskette could legitimately be made only by the successful bidder after bid opening. The 1995 ITB, which is at issue in this proceeding, contains the following Special Conditions directly related to a material list on Page 4: FORMAT FOR SUBMISSION OF BID On all bids which require any of the following documents: Manufacturer's or Dealer's Published Price Lists, Authorized Dealer's List Authorized Service Center Locations. Bidder shall provide these documents, with his bid, in a letter quality text response and with computer diskette media. The format for the computer diskette media shall be: WordPerfect 5.1 file format using an IBM Compatible Personal Computer, On 8-1/2" x 11" paper with portrait orientation, Margins: Left: minimum .3 inch; Right: minimum .8 inch, Top & Bottom: minimum .5 inch, Font: Courier 10 cpi, 3.5 or 5.25 inch diskette media, No landscape, No Tables or Columns, No Line Draw, No pictures, No strike- throughs and No Graphics allowed. These documents shall be submitted in hard copy as well as on 3.5 or 5.25 inch diskette media. [Failure to comply with this requirement will result in disqualification of your bid.] [Emphasis supplied] MATERIAL LIST A material list shall be provided on diskette formatted as specified in the Special Cond- ition "FORMAT FOR SUBMISSION OF BID" along with a print out of same for each item bid. The information must include product number for color, and size specified sheeting under the DMS thirteen (13) digit commodity number. If prices are included on the materials list they must be contract prices. [This list may be included on the same diskette as "Format for Submission of Bid" listed above.] (Emphasis supplied) Some other provisions of the 1995 ITB which affect the issues in this case are as follows: General Condition 4(b) on page 1 of the ITB specifies: ELIGIBLE USERS: Under Florida Law use of State contracts shall be available to political sub- divisions (county, local county board of public instruction, municipal or other local public agency or authority) and State Univer- sities, which may desire to purchase under the terms and conditions of the contract. General Condition 5 provides: ADDITIONAL TERMS AND CONDITIONS: No addition- al terms and conditions included with the bid response shall be evaluated or considered and any and all such additional terms and condi- tions shall have no force and effect and are inapplicable to this bid. If submitted either purposely through intent or design or inadver- tently appearing separately in transmittal letters, specifications, literature, price lists or warranties, it is understood and agreed the general and special conditions in this bid solicitation are the only conditions applicable to this bid and the bidder's autho- rized signature affixed to the bidder acknow- ledgment form attests to this. General Condition 7 states: INTERPRETATIONS/DISPUTES: Any questions con- cerning conditions and specifications shall be directed in writing to this office for receipt no later than (10) days prior to the bid opening. Inquiries must reference the date of the bid opening and the bid number. No interpretation shall be considered binding unless provided in writing by the State of Florida in response to requests in full comp- liance with this provision. . . General Condition 15 states: LEGAL REQUIREMENTS: Applicable provisions of all Federal, State, county and local laws, and of all ordinances, rules and regulations shall govern development, submittal and evalua- tion of all bids received in response hereto and shall govern any and all claims and dis- putes which may arise between person(s) hereto and the State of Florida, by and through its officers, employees and authorized represent- atives, or any other person natural or other- wise; and lack of knowledge thereof shall not constitute a legal defense against the effect thereof. General Condition 26 provides that: [THE SUCCESSFUL BIDDER(S) MUST PROVIDE: a copy of any product literature and price list, in excellent quality black image on white paper.] [Emphasis supplied] On the bottom of page 2, after the list of General Conditions, there is a note which states: [ANY AND ALL CONDITIONS AND SPECIFICATIONS ATTACHED HERETO WHICH VARY FROM THESE GENERAL CONDITIONS SHALL HAVE PRECEDENCE.] THIS SHEET AND THE ACCOMPANYING BID CONSTITUTE AN OFFER FROM THE BIDDER. IF ANY OR ALL PARTS OF THE BID ARE ACCEPTED BY THE STATE OF FLORIDA DEPARTMENT OF MANAGEMENT SERVICES, AN AUTHORIZED REPRESENTATIVE OF THE DIVISION OF PURCHASING OF THE DEPARTMENT OF MANAGEMENT SERVICES, SHALL AFFIX HIS SIGNATURE HERETO, AND THIS SHALL THEN CONSTITUTE THE WRITTEN AGREEMENT BETWEEN PARTIES. THE CONDITIONS OF THIS FORM BECOME A PART OF THE WRITTEN AGREEMENT BETWEEN THE PARTIES. [Emphasis supplied] Page 2A of the ITB contains a Vendor Bid Preparation Checklist. No. 16 thereof reminds all bidders to review the FORMAT FOR SUBMISSION OF BID for compliance with bid requirements. After the list of General Conditions, the Special Conditions begin on page 3 of the ITB. Among the Special Conditions of note in addition to the FORMAT FOR SUBMISSION OF BID and MATERIAL LIST, stated above, are: PURPOSE: ...to establish a 12 month contract by all State of Florida agencies and other eligible users ... TECHNICAL DOCUMENTATION: ... When technical documentation is required by this ITB, its pur- pose is to demonstrate compliance of the pro- duct bid with applicable technical require- ments of the ITB and to allow a technical evaluation of the product. [Failure to provide the required technical documentation with the bid submittal shall make the bidder nonre- sponsive], unless the Division of Purchasing, in its sole discretion and in the best inte- rest of the State, determines the accept- ability of the products offered through technical documentation available within the Division [as of the date and time of bid opening]. ... [Emphasis supplied] ACCESSORIES: [Inks, colors, clears, and thinners, required for use with non-perfor- ated commodities shall be included in the price per square foot bid price.] [Emphasis supplied] BALANCE OF LINE: [The bidder shall bid a balance of line which will include options and accessories at a fixed discount. Only vendors awarded specified sheeting items will be eligible for a balance of line award. Items in the balance of line which are dupli- cative of those specified will be deleted. The balance of line price list must be in effect on the date and time of the bid opening]. [Emphasis supplied] The Specification Summary and Bid Price Sheets for bidding items 13, 15, and 22 of the ITB are found on pages 25, 26, and 27 of the ITB and were as follows: SPECIFICATION SUMMARY AND PRICE SHEET COMMODITY NUMBER AND DESCRIPTION NET DELIVERED PRICE 550-590-350-0100 Sheeting, not perforated, reflective, Type IIIA, or Type IIIC sizes 1" through 48" by 50 yds, with a precoated pressure sensitive adhesive backing (Class I). Primer Not Required. Sheeting (Both Types) shall be available in no less than the following colors: blue, brown, green, yellow, and silver-white. Sheeting Manufacturer: Product No./Series: FDOT Qualified Products List Approval No. $ PER SQ. FT. (13 [Inks, colors, clears and thinners for use with non-preforated commodities shall be in- cluded in the per square foot price bid]. [Emphasis supplied] VENDOR: SPECIFICATIONS SUMMARY AND PRICE SHEET COMMOD- ITY NUMBER AND DESCRIPTION NET DELIVERED PRICE 550-590-350-0120 Sheeting, not perforated, reflective, Type IIIA, or Type IIIC sizes 1" through 48" by 50 yds, with a precoated pressure sensitive adhesive backing (Class I). Primer Not Required. Sheeting (Both Types) shall be available in no less than the following color: orange Sheeting Manufacturer: Product No./Series: FDOT Qualified Products List Approval No. $ PER SQ. FT. (15 [Inks, colors, clears and thinners for use with non-preforated commodities shall be included in the per square foot price bid.] [Emphasis supplied] VENDOR: SPECIFICATION SUMMARY AND PRICE SHEET COMMODITY NUMBER AND DESCRIPTION NET DELIVERED PRICE 550-590-760-2600 Reflective sheeting, construction barricade sheeting, Type IIA, or IIIA, or IIIB, or IIIC pressure sensitive adhesive backing (Class I). 4" or 6" orange and white or orange and silver strips running diagonally across the sheeting at a 45 degree angle, size 12", 24" and 36" by 50 yds. Sheeting Manufacturer: Product No./Series: FDOT Qualified Products List Approval No. $ PER SQ. FT. (22 [Inks, colors, clears and thinners for use with non-preforated commodities shall be in- cluded in the per square foot price bid.] [Emphasis supplied] VENDOR: After the item-by-item specifications, the ITB provides a page (page 39) of specification summary and price sheet for bidding the "balance of line discount offered for directly related sign material, not specified on the Bid Price Sheet." That format requires that the bidder state a fixed percentage discount from the price list for balance of line items. "Balance of Line" as used by DMS in the ITB refers to any and all accessories that might be used with the individual Items that are bid. Stimsonite's bid supervisor claimed that Stimsonite's failure to submit a diskette containing a material list was a reasonable, and indeed a clear and unambiguous, reading of the 1995 ITB. He had read the ITB to provide that the three categories of list (a manufacturer's or dealer's published price list, authorized dealer list, or authorized service center location list) which were named under the Special Condition, FORMAT FOR SUBMISSION OF BID, on page 4 were required to be submitted on a diskette with the bid, but he also considered that the diskette was not required for the three items that Stimsonite bid upon (Items 13, 15, and 22 on pages 25, 26, and 27 at Finding of Fact 20 supra) because none of the categories of list under FORMAT were required specifically within those Item No. specifications on the subsequent specification pages. Apparently due to the admonition at the bottom of ITB page 2 of the General Conditions [see Finding of Fact 19(f)], he assumed that the Item No. instructions on the specifications and price summary sheets on pages 25, 26, and 27 took precedence over, i.e. supplanted, the Special Condition MATERIAL LIST paragraph requiring a material list for every item in both hard copy and on diskette which also included the requirement of including product numbers for color, size, and DMS commodity numbers. Stimsonite's bid supervisor also asserted that because the Special Condition MATERIAL LIST paragraph and the Item No. specifications of pages 25, 26, and 27 did not specifically reiterate that the material list diskette must be submitted with the bid, the material list diskette legitimately could be submitted after the bid award, as was attempted by Stimsonite. He ostensibly interpreted General Condition 26, applicable to successful bidders, to mean that only successful bidders must provide a price list and a material list. Accordingly, Stimsonite further argued in the alternative that even if the ITB could be construed to require submission of a material list on diskette, Stimsonite's failure to submit the diskette to DMS with the rest of its bid response was only a minor irregularity unworthy of being ruled unresponsive because DMS had no substantive need for the information on the material list diskette until it decided which bidder was going to be the successful bidder. The bid supervisor's perception that the information on the diskette was not needed for bid evaluation purposes was another reason he ostensibly did not timely submit a diskette. Stimsonite has not asserted that late submission was a waiveable irregularity. 1/ In fact and to the contrary, the diskette is used by DMS to evaluate bids for responsiveness. This evaluation technique was introduced in 1994. It allows the reviewer, in this case, Ms. Boynton, to use the material list on the diskette to determine if each bidder has actually bid everything DMS asked for in the item by item specifications. Without a diskette, the reviewer cannot confirm that a bid matches the ITB. DMS uses the bidder's material list on diskette to confirm that the bidder currently manufactures the full range of sheeting widths and sizes (1 inch through 48 inches by 50 yards), as the ITB requires, which is a nonstandard range in the reflective sheeting industry. Additionally, DMS uses the material list diskette to confirm that the bidder proposes to make the full range of required sheeting widths and sizes available to state and local government purchasers. (See General Condition (4)(b) ELIGIBLE USERS and Special Condition PURPOSE in the ITB) DMS also uses the material list diskette to ensure that the bidder will make the required range of inks, clears, colors, and thinners available at the bid price. After the bid has been awarded, Ms. Boynton also uses the diskette for dissemination to contract users for ordering purposes on the electronic contract system. The diskette system saves DMS the time and cost of wordprocessing data from hard copy and avoids transcription erors. This was one of the purposes behind DMS' decision to start requiring a diskette in 1994. It comports with General Condition 4(b) ELIGIBLE USERS and Special Conditions PURPOSE. The Stimsonite bid supervisor did not have a manufacturer's price list and was not offering any accessories other than those inks, etc. covered under the Special Condition ACCESSORIES paragraph and those stated on pages 25, 26, and 27. Therefore, he did not read the Special Condition BALANCE OF LINE paragraph saying duplicates listed on page 39 for balance of line would be disregarded by DMS as an indicator that DMS expected any balance of line bids to include more than just the inks, etc. listed under ACCESSORIES and on pages 25, 26, and 27. Because he could not conceive of any balance of line more extensive than the inks, etc. which seemed to him to be excluded by the language on the specifications summary and price sheets for each Item No. (ITB pages 25, 26, and 27) and the balance of line summary and price sheet (page 39), and because Stimsonite was offering these inks, etc. within the price per square foot of sheeting at no extra charge on pages 25, 26, and 27, Stimsonite's bid supervisor felt that the diskette was not needed to evaluate these prices. Therefore, when he showed a balance of line on the balance of line summary sheet (ITB page 39) he showed no discount and he submitted no material list or price list on diskette. The ITB required a discount if a balance of line was offered under Special Condition BALANCE OF LINE. According to DMS employees, a price list was only necessary if a balance of line was bid. If a balance of line was bid, then a price list was necessary. The result of Stimsonite's interpretation of the 1995 ITB was that Stimsonite submitted a bid without a diskette which therefore contained neither a price list nor a material list. The hard copy offered a balance of line with no discount from a price list. Responsiveness in bidding Item Nos 13, 15, and 22 in 1995 did not require that vendors submit an authorized dealer's list or service center location list. The ITB used the language "shall submit" with regard to bidding a balance of line, but according to Ms. Boynton, the evaluator, and Mr. Barker, Chief of DMS's Bureau of Procurement, submission of a balance of line was not mandatory. Ms. Boynton speculated that if DMS did not get a balance of line bid from a responding bidder, DMS "might possibly find it was a minor irregularity." Clearly, the ITB provided that if there were any duplications on the balance of line offering, the agency could unilaterally delete them. However, if a vendor did bid a balance of line, DMS would need a price list, since with a balance of line and no price list, there was no way to evaluate the bid because DMS then could not calculate what the percentage reduction would be based upon. Therefore, under this situation in 1995, Stimsonite's balance of line bid with no price list on diskette was rejected as nonresponsive. 2/ The greater weight of the credible evidence, particularly but not exclusively that of Ms. Boynton, Mr. Barker, and Mr. Johnson, is that allowing any bidder to turn in the diskette after bid opening and award would give that bidder the advantage of changing the balance of line prices. If permitted to submit the material list after award, the bidder could elect to offer only one size which would impose an additional cost on the contract users to provide labor and expertise to cut to size, thus lowering the bidder's cost. Under a scenario which required only successful bidders to submit a diskette, DMS would not have the opportunity to reject the bid if the information on the diskette was nonconforming to the bid specifications. The bidder who delayed or never submitted a diskette also could exclude cities and counties from the cost-saving electronic contract system and could take telephone orders from the Department of Transportation, one of the agencies eligible to tie-in to DMS's electronic contract. Requiring a diskette only after award might permit the successful bidder to limit the sizes and colors offered. By not submitting a diskette at all, even late, a bidder could even disqualify its bid and back out of the contract if that bidder unilaterally decided its bid was too low or if the price of raw materials increased. Experience with successful bidders who ultimately failed to submit a material list at all was another reason for DMS's decision to start requiring a diskette in 1994. Any of the foregoing situations creates an advantage to the bidder who files a diskette late or the bidder who never files a diskette. Any of the foregoing situations increases costs to the state agency and contract users. Factually, this is a material irregularity. Stimsonite alleged that 3M was unresponsive because its bid transmittal letter contained a paragraph on terms and conditions of sale and warranties. However, it appears that the warranty language in 3M's transmittal letter actually enhances its bid. Also, it is standard practice for DMS to ignore these letters pursuant to ITB General Condition 5, which states that transmittal letter variances are of no force and effect. Factually, since 3M's letter cannot be relied upon by 3M either to enhance or diminish its bid, and since all such letters are disregarded in the bid evaluation/tabulation, the transmittal letter is a minor, nondisqualifying irregularity as to the 3M bid. Stimsonite asserted that the 3M diskette was not responsive to the ITB specifications. There is no dispute that the diskette 3M submitted was in the wrong font. However, since font size can be customized by a "click" on a computer mouse, and since Ms. Boynton was able to use 3M's diskette for the purposes intended by the ITB specifications, the irregular font size of 3M's diskette is found factually to constitute an immaterial flaw not worthy of declaring 3M's bid nonresponsive. Finally, Stimsonite contended that because the 3M bid failed to answer an ITB question that requested information about why a vendor's price list was item by item higher or lower than previous years, the entire 3M bid was unresponsive. This contention was not acknowledged as viable by the agency witnesses. DMS, like 3M, viewed this question as only information gathering for some cost trend analysis by the agency apart from bid evaluation. The information requested could not alter the bid price offered by 3M and is not necessary to DMS's evaluation of its bid or comparison of its bid with other bids. It is a flaw systematically ignored by the agency in bid evaluation. There was no evidence that any bid has ever been rejected for such a flaw. The absence of such information does not affect the cost to the agency nor does its absence provide an advantage to 3M. Factually, it is a minor irregularity.
Recommendation Upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Department of Management Services enter a final order ratifying its award of ITB 20-550-590-A Item Nos. 13, 15, and 22 to Minnesota Mining and Manufacturing, Inc. and dismissing the bid protest Petition of Stimsonite. RECOMMENDED this 14th day of June, 1996, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of June, 1996.