CLOSE CONSTRUCTION, INC. vs SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 09-004996BID (2009)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Sep. 14, 2009 Number: 09-004996BID Latest Update: Jul. 13, 2011

The Issue The issues to be resolved in this proceeding concern whether the Petitioner, Close Construction, Inc. (Petitioner), (Close) was the lowest responsive and responsible bidder in the Request For Bid (RFB) Number 6000000262, whether the subject contract should be awarded to the Petitioner, and, concomitantly, whether the Respondent agency's decision to award the contract to the Intervener, Worth Contracting, Inc. (Worth) was clearly erroneous, contrary to competition, arbitrary or capricious.

Findings Of Fact The South Florida Water Management District is a public corporation authorized under Chapter 373, Florida Statutes. It issued a request for bids for the refurbishment and automation of certain facilities in Broward County, Florida. Close is a construction company duly authorized to do business in the state of Florida. It was one of the bidders on the procurement represented by the subject request for bids and is the Petitioner in this case. This dispute had its beginnings on June 5, 2009, when the Respondent issued RFB number 6000000262. The RFB solicited construction services for the refurbishment and automation of two facilities in Broward County. The procurement would involve the installation of new direct-drive electric pumps at the Respondent's G-123 Pump Station in Broward County, along with the construction of an equipment shelter and the replacement of a retaining wall with a poured concrete retaining wall, as well as refurbishment of "pump flap gates." The RFB also requested construction services for the replacement of gates at the Respondent's S-34 water-control structure in Broward County. Both facilities would thus be automated so that they can be remotely operated from the Respondent's headquarters in West Palm Beach. After issuance of the RFB, two addenda were supplied to vendors and were posted. The first addendum was posted on or about June 19, 2009, concerning a change in specifications for flap gates and is not the subject of this dispute. Addendum No. Two was electronically posted on or about June 30, 2009. It amended the technical specifications of the RFB by deleting Section 11212 regarding measurement of payment of electric motors/belt-driven axial flow pumps. That addendum also added a new measure and payment to Subpart 1.01 of the technical specifications to provide for an owner-directed allowance of $40,000.00 to provide for the potential need for certain electrical utility work to be done by FPL in order to complete the project. Addendum No. Two added an additional term to the RFB in providing that the $40,000.00 allowance price "Shall be added to the other costs to complete the bid." The second Addendum also stated, "The allowance price shall be used at the discretion of the District and, if not used, will be deducted from the final Contract Price." That addendum also directed bidders to replace the original Bid Form 00320-2, which had been enclosed with the RFB, with a new Bid Form, 00320R1-2. The new Bid Form is identical to the original form except that the schedule of bid prices contained in paragraph four, on page 003201-2, was altered to itemize the $40,000.00 discretionary cost allowance. The original form had contained a single line for the bidder's lump sum bid price, whereas the revised form provided for a lump sum bid amount to be itemized and a base bid amount, which required the bidder to enter on the form the amount of its bid, then add the discretionary cost amount and write the sum of those two numbers on a third line. In paragraph four of the new bid form there is re- printed language concerning the use of the discretionary allowance which appeared on the face of Addendum No. Two. Other than the change to paragraph four and the alteration of the page numbers to include an "R" in the page number, the revised bid form is identical to the original bid form. The other bid documents were not altered in any manner by Addendum No. Two. The deadline for bid submissions was Thursday, July 9, 2009, at 2:30 p.m. The Petitioner timely submitted its bid to the District. In submitting its bid however, the Petitioner used the original bid form which had been enclosed with the RFB. The bid form submitted was an exact copy of the bid form furnished by the District which Close had printed from the electronic copy of the RFB received from the District. The Petitioner did not substitute the revised bid form, attached to Addendum No. Two, for the original form in submitting its bid. The Petitioner's bid was deemed non-responsive by the District and was rejected on the basis that Close had failed to submit the bid on the revised form required by Addendum No. Two. Thereafter, the District, at its August 13, 2009, meeting, approved award of the bid to Worth. The intent to award was posted electronically on or about August 14, 2009. The persuasive evidence establishes that Close received both addenda to the bid documents. It was aware of the Addendum No. Two, and it accounted for all of the changes to the technical specifications made in both addenda in the preparation of its bid. The evidence shows that Close was aware of the $40,000.00, owner-directed cost allowance and that it incorporated it in the formulation of its total bid price. Thus, Close's final bid amount was $3,751,795.00. That number included the $40,000.00 cost allowance at issue, added to the bid documents by Addendum No. Two. The internal bid work sheets, prepared by personnel of Close, identified and itemized the $40,000.00 discretionary cost allowance as a component of the final bid price. The persuasive evidence thus establishes that Close's final bid amount did include the $40,000.00 cost allowance. Moreover, the written notes of witness Christopher Rossi, the estimator for Close, show the $40,000.00 amount as an "FPL Allowance." Both Mr. Rossi and Mr. Boromei, the Vice President for Close, who prepared the bid, explained that the $40,000.00 was understood by Close to be a cost allowance, that it would only be charged to the District to the extent that it was actually used, at the District's discretion. If it were not used, it was to be deducted from the overall contract price. Addendum Two specifically provides that the discretionary cost allowance was to be used only at the discretion of the District and that the unused portion would be deducted from the contract amount. When Close submitted its bid it mistakenly submitted it on the original bid form and failed to exchange the bid forms as directed in Item Two of Addendum No. 2. In paragraph one of both bid forms, however, the bidder is required to specifically fill out, acknowledge and identify all addenda. By doing so the bidder expressly agrees to build the project in conformance with all contract documents, including all addenda, for the price quoted in the bid. Close completed this paragraph, specifically identified both Addendum One and Addendum Two, and specifically agreed to strictly conform, in performance of the work to the plans, specifications and other contract documents, including Addendum Nos. One and Two. Paragraph one was not changed by the addition of Addendum No. Two and it is identical in both the original and the revised forms at issue. Paragraph one of the original and the revised bid forms constitutes an agreement by the bidder to perform and construct a project "in strict conformity with the plans, specifications and other Contract Documents. . . ." The addenda are part of the contract documents and are expressly referenced as such in this agreement. Both bid forms, the original and the revised, include paragraph eight, which clearly states that the bidder will post a bid bond to secure and guaranty that it will enter into a contract with the District, if its bid is selected. Paragraph eight was unchanged by Addendum No. Two and its terms are identical in both Bid forms at issue, including the form that Close signed and submitted as its bid. The persuasive evidence shows that in submitting its bid, whether on either form, Close committed itself to the identical terms as set forth in the identical contract documents agreed to by Worth and the other bidders. The evidence established that Close intended to bind itself to the terms of the RFB, and all terms of Addendum No. Two, including the discretionary cost allowance term. Close considered itself bound to enter into a contract for the price of its bid if selected by the District. It likewise considered that the price of its bid, would only include the cost allowance if the discretionary allowance was implemented by the District. Upon the opening of the bids, the firm of Cone and Graham, Inc., was identified as the lowest bidder. Cone and Graham's bid was in the amount of $2,690,000.00. Close was the second lowest bidder, with a bid of $3,751,795.00. The third lowest bidder was Worth Contracting, Inc., with a bid of $3,898,410.00. Cone and Graham was allowed to provide additional information and to even meet with some District staff following the opening of its bid. The additional information it was allowed to provide concerned technical specifications of the pumps proposed in its bid. Through this verification process conducted with the Agency, Cone and Graham ultimately convinced the District to permit them to withdraw its bid without forfeiting their bid bond. This left the Petitioner, Close, the lowest bidder, at $146,615.00 less than the bid submitted by Worth, the initially-awarded bidder. Close's bid, upon review, was rejected as non- responsive due to its failure to exchange the original Bid form with the revised Bid form, as indicated above, in spite of the fact that Close had also agreed to adhere to the entirety of Addendum No. Two on the face of the Bid form. Thus the recommended award to Worth for the above-referenced additional amount of bid price was adopted by the District, engendering this protest. James Reynolds, the Contracts Specialist for the District, conceded that it was apparent on the face of Close's bid that a mistake had been made in the use of the original form, rather than the revised form. He conceded there was an inconsistency between Close's clear acknowledgement of and agreement to the terms of the contract documents, which expressly included Addendum No. Two and Close's apparent mistaken use of the original Bid form. Under the express terms of Article 19.03 of the RFB, "The Bid shall be construed as though the addendum(a) have been received and acknowledged by the bidder." Mr. Reynolds admitted, however, that he did not apply the terms of Article 19.03 of the RFB in his review of Close's bid and did not construe the bid in the manner provided in the RFB to resolve the apparent inconsistency. He reasoned that Close had used the wrong bid form and looked no further. The District's Procurement Manual provides a procedure whereby a bidder may correct inadvertent mistakes in its bid. Under the terms of Chapter 5-5 of that manual, where the District knows or has reason to conclude, after unsealing of bids, that a mistake may have been made by a bidder, the District "shall request written verification of the bid." In such a circumstance the bidder "shall be permitted the opportunity to furnish information in support of the bid verification as long as it does not affect responsiveness, i.e., the bid substantially conforms to the requirements of the RFB as it relates to pricing, surety, insurance, specifications and any other matter unequivocally stated in the RFB as determinant of responsiveness." See Joint Exhibit 7,6 pages 61 and 62, in evidence. Mr. Reynolds admitted in his testimony that he did not follow the procedure set forth in the manual for verifying a bid because, in his view, that would be allowing an impermissible supplementation of Close's bid. Ms. Lavery, in her testimony, in essence agreed. The Procurement Manual expressly required the District, upon recognizing the mistake and an inconsistency apparent on the face of Close's bid, to verify that bid and to provide Close with the opportunity to furnish information in support of bid verification. Thus, by the express terms of the manual, a bidder must be given an opportunity to clarify mistakes. The Procurement Manual expressly permits a bidder under these circumstances to correct any "inadvertent, non- judgmental mistake" in its bid. Chapter 5 of the Manual provides that "a non-judgmental mistake" is a mistake not attributable to an error in judgment, such as mistakes in personal judgment or wrongful assumptions of contract obligations. Inadvertent technical errors, such as errors of form rather than substance, are considered non-judgmental errors." See Joint Exhibit 7, page 62, in evidence. It is patently apparent that Close's use of the original bid form, inadvertently, while also unequivocally acknowledging and agreeing to the entirety of Addendum No. Two, represented a non-judgmental mistake. Both of the District witnesses, however, testified that the policy regarding mistakes was not followed and Close was not given an opportunity under the District's policy to provide additional information to support verification of the bid. Although Close failed to substitute the revised Bid form for the original Bid form, as called for by Addendum No. Two, its bid was substantively responsive to the technical specifications and requirements of the RFB, and the irregularity is technical in nature. The parties stipulated that the use of the original form, rather than the revised bid form, was the sole basis for Close being determined to be non-responsive by the Agency. In accordance with Florida Administrative Code Rule 40E-7.301, in Chapter 5 of the District's Procurement Manual, the District reserves the right to waive minor irregularities in a bid. A material irregularity is defined by the District's policy as one which is not minor in that it: (a) affects the price, quality, time or manner of performance of the service such that it would deprive the District of an assurance that the contract will be entered into, performed and guaranteed according to the specified requirements; (b) provides an advantage or benefit to a bidder which is not enjoyed by other bidders; or (c) undermines the necessary common standards of competition. See Joint Exhibit 7, page 58, in evidence. The preponderant, persuasive evidence shows that the irregularity in Close's bid did not affect the price of the bid or truly deprive the District of assurance that the contract would be entered into and performed according to all the terms of the RFB, including addenda. The evidence established that Close actually included the $40,000.00 discretionary cost allowance in its final bid price. It merely did not show it as a separate itemization, because it did not use the revised form providing that itemization line. The fact that the discretionary allowance was itemized in the revised bid form, as part of the bid amount, does not equate to an effect on the contract price as a result of Close's using the original Bid form. Close's error, by mistakenly submitting its bid on the original bid form, did not alter the price of its bid. The evidence clearly established that the bid price for Close's bid would be the same regardless of which form it used. Moreover, the preponderant, persuasive evidence establishes that the use of the original Bid form by Close did not deprive the District of assurance that the contract would be performed in accordance with the all bid documents. Close's bid, secured by its bid bond, clearly acknowledged and agreed to the express terms of Addendum No. Two in their entirety, which included the terms under which the discretionary cost allowance could be applied. Close considered itself bound to the terms of the RFB and assured the Agency that it was so bound by the written acknowledgement and agreement it submitted to the Agency as part of its bid, concerning the elements of Addendum No. Two. The evidence demonstrated that Close understood that the $40,000.00 amount was a discretionary cost allowance and that Close would not be entitled to it unless the District decided to use it. Despite the opinion of Agency witnesses to the contrary, the error in Close's bid was a technical one and non- material because it did not confer a competitive advantage upon Close. Close's use of the wrong form did not alter the price of its bid. Its mistake in the use of the original bid form could only change the relative, competitive positions of Close and Worth if the amount of the discretionary cost allowance was greater or equal to the difference between those two bids, i.e., the $146,650.00 amount by which Worth's bid exceeded the bid of Close. 1/ The bid of Worth exceeds Close's bid by an amount far greater than the amount at issue in the discretionary cost allowance identified in Addendum No. Two and expressly itemized in the revised Bid form, i.e. $40,000.00. The District contends that Close gained some competitive economic advantage over other bidders by having the means by which it could optionally withdraw its bid, based upon alleged non-responsiveness, in not substituting the revised Bid form which would contain the itemization of the $40,000.00 cost allowance. It is difficult to see how it could gain a competitive advantage versus other bidders through some perceived ability to deem itself non-responsive, at its option, and withdraw its bid, thus denying itself the contract. The competitive bidding laws are designed to prevent a firm from gaining a competitive advantage in obtaining a contract versus the efforts of other bidders, not in depriving itself of the opportunity to get the work. Moreover, concerning the argument by the District that this may confer the advantage to Close of allowing it to withdraw its bid at its option and still obtain a refund of its bid bond; even if that occurred, it would not confer a competitive advantage vis-à-vis other bidders. It would merely involve a potential pecuniary advantage to Close's interest, versus that of the Agency itself, which obviously is not a bidder. Moreover, it should again be pointed out that Cone and Graham was allowed to provide additional information concerning its bid elements, and even to meet with the District staff, following the opening of the bids. It was then allowed to withdraw its bid without forfeiting its bid bond. If the District had inquired, by way of verification of Close's bid, as to whether the discretionary cost amount was included in it's bid, that inquiry does not equate to allowing Close to unlawfully supplement its bid. Indeed, if in response to such an inquiry, Close announced that the discretionary allowance was not included in its bid, its bid at that point would be materially non-responsive to the specifications. If Close was then allowed to supplement its bid by changing its price to add the allowance, such would indeed be an unfair competitive advantage and a violation of law on the part of Close and the Agency. The evidence does not show that such happened or was proposed by any party. If a verification inquiry had been made and Close announced that, indeed, its bid price did include the subject discretionary cost allowance, without further response to the specifications being added, then no competitive advantage would be afforded Close and no legal violation would occur. In fact, however, as pointed out above, the verification request, pursuant to the District's policy manual, was never made. This was despite the fact that the District's witness, Mr. Reynolds, acknowledged that the use of the original bid form was an apparent mistake on the face of the bid, when considered in conjunction with Close's express agreement to construct the project in strict conformance with all contract documents, and particularly with regard to Addenda Numbers One and Two. The non-judgmental mistake, involving use of the original bid form in lieu of the revised bid form, could have been easily clarified by a verification inquiry. That policy was not followed, based solely on the fact that the wrong bid form was used, even though the preponderant, persuasive evidence shows that in all material and substantive respects the bid was a conforming, responsive bid and included in its price the discretionary cost allowance. The preponderance of the evidence shows that the mistaken use of the original Bid form was a non- material irregularity under the District's policies and the terms of the RFB. The District's actions in failing to uniformly apply its own bid verification policy when, in fact, it had allowed verification to one of the other bidders, and when, according to its own witness, it perceived an apparent mistake, was clearly erroneous. It is true that Close may not supplement its bid by changing material terms, but it is permitted to verify whether, in light of the mistaken use of the original Bid form, its bid price, as submitted, included the $40,000.00 discretionary allowance or not. Providing such "yes or no" type of additional information in order to clarify, and only clarify, information already submitted in the bid, in response to an inquiry by the District does not constitute "supplementation" of the bid for purposes of Section 120.57(3)(f), Florida Statutes (2008). NCS Pearson, Inc. v. Dept of Education, 2005 WL 31776, at page 18 (DOAH, Feb. 8, 2005). Even without verification of the bid, the bid on its face agrees to compliance with all terms and specifications, including Addendum No. Two. It is thus determined that there is no material irregularity. The bid submitted by Close does not afford it any competitive advantage vis-à-vis the other bidders and it is responsive.

Recommendation Having considered the foregoing Findings of Fact, conclusions of law, the evidence of record, the candor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is, therefore, RECOMMENDED that a Final Order be entered by the South Florida Water Management District, awarding the subject contract for RFB 6000000262 to the Petitioner herein, Close Construction, Inc. DONE AND ENTERED this 5th day of January, 2010, in Tallahassee, Leon County, Florida. S P. MICHAEL RUFF Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 5th day of January, 2010.

Florida Laws (3) 1.01120.569120.57 Florida Administrative Code (1) 40E-7.301
# 1
K AND M PINE STRAW vs DEPARTMENT OF CORRECTIONS, 11-001670BID (2011)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Apr. 04, 2011 Number: 11-001670BID Latest Update: Jul. 27, 2011

The Issue The issue in this proceeding is whether the award of a bid for the sale of scrap metal to Cumbaa Enterprises, Inc. was arbitrary, capricious, clearly erroneous, or contrary to competition or the bid specifications.

Findings Of Fact On January 19, 2011, the Department issued Invitation to Bid (ITB) #10-Apalachee-8252. The ITB was a revenue- generating contract for the sale of scrap metal at Apalachee Correctional Institution in Sneads, Florida. Since the contract would generate revenue to the State, the Department’s purpose was to award the contract to the highest responsive bid and developed bid specifications and criteria to accomplish that goal. The specifications for the ITB stated in relevant part: Material Deviations: The Department has established certain requirements with respect to bids to be submitted by bidders. The use of shall, must or will (except to indicate simple futurity) in this ITB indicates a requirement or condition which may not be waived by the Department except where the deviation therefrom is not material.[emphasis added]. A deviation is material if, in the Department’s sole discretion, the deficient response is not in substantial accord with this ITB’s requirements, provides an advantage to one bidder over other bidders, has a potentially significant effect on the quantity or quality of items bid, or on the cost to the Department. Material deviations cannot be waived and shall be the basis for rejection of a bid. Minor Irregularity: A variation from the ITB terms and conditions which does not affect the price of the bid or give the bidder an advantage or benefit not enjoyed by other bidders or does not adversely impact the interests of the Department. 1.10 Responsive Bid: A bid submitted by a responsive and responsible vendor that conforms in all material respects to the solicitation. * * * 4.3.1 Submission of Bids Each bid shall be prepared simply and economically, providing a straightforward, concise delineation of the bidder’s capabilities to satisfy the requirements of this ITB, fancy bindings, colored displays, and promotional material are not desired. Emphasis in each bid must be on completeness and clarity of content. In order to expedite the review of bids, it is essential that bidders follow the format and instructions contained in the Bid Submission Requirements (Section 5), with particular emphasis on the Mandatory Responsiveness Requirements. Rejection of Bids The Department shall reject any and all bids containing material deviations. The following definitions are to be utilized in making these determinations. Material Deviations The Department has established certain requirements with respect to bids to be submitted by bidders. The use of shall, must or will (except to indicate simple futurity) in this ITB indicates a requirement or condition which may not be waived by the Department except where the deviation therefrom is not material. A deviation is material if, in the Department’s sole discretion, the deficient response is not in substantial accord with the ITB’s requirements, provides an advantage to one bidder over other bidders, has a potentially significant effect on the quantity or quality of items bid, or on the cost to the Department. Material deviations cannot be waived and shall be the basis for rejection of a bid. Minor Irregularities A variation from the ITB terms and conditions which does not affect the price of the bid or give the bidder an advantage or benefit not enjoyed by other bidders or does not adversely impact the interests of the Department. As indicated, Section 5 of the specifications outlined the contents of the bid. Section 5 stated in relevant part: SECTION 5 - CONTENTS OF BID This section contains instructions that describe the required format for the submitted bid. Bids shall be submitted in a sealed envelope, clearly marked “Bid - ITB#- Apalachee-8252”. . . . . [T]he following paragraphs contain instructions that describe the required format for bid responses. Responsiveness Requirements The following terms, conditions, or requirements must be met by the bidder to be considered responsive to this ITB. Failure to meet these responsiveness requirements may cause rejection of a bid. [emphasis added]. Bidder shall complete, sign and return the ITB Bidder Acknowledgement Form (page 1 & 2). The bidder must return either the original or a copy of both pages with an original signature on page one (1). The bidder shall complete, sign, date, and return (all) pricing pages, entitled Cost Information Sheet, which consists of page 28. By submitting a bid or bids under this ITB, each bidder warrants its agreement to the prices submitted. The Department objects to and shall not consider any additional terms or conditions submitted by a bidder, including any appearing in documents attached as part of a bidder’s response. In submitting its bid, a bidder agrees that any additional terms or conditions, whether submitted intentionally or inadvertently, shall have no force or effect. Any qualifications, counter-offers, deviations, or challenges may render the bid un-responsive . . . . * * * 5.3 Certificate of Insurance Bidders shall return a fully executed Certificate of Insurance . . . . In this case, Section 5.1 contains two bid specifications essential to a bid's responsiveness. Those two requirements were submission of a signed and completed, original or copy, of the bidder acknowledgement form and submission of a completed Cost Information Sheet. The Cost Information Sheet is not at issue here. The bidder acknowledgement form is a double-sided Department of Management Services form containing general boilerplate contractual language. The back of the form is a continuation of standard contractual terms from the front. Oddly, signatures acknowledging these terms and the terms of the ITB are on the front page (page 1) of the form. By signing the front page of the bidder acknowledgement form the bidder agrees to abide by all conditions of the bid. The remainder of Section 5 of the ITB contains bid specifications that are not considered essential to determine the initial responsiveness of the bid at the bid opening, but are to be returned at some later point in time after the bid's are opened. However, the language of Section 5 effecting that intent is unclear. In particular, the bid specification contained in Section 5.3 requires the bidder to "return" an "executed" Certificate of Insurance. The Certificate of Insurance provides the Department with proof of a variety of required insurance coverage of the vendor. However, later in the ITB Section 7.14 clarifies that the Certificate of Insurance need only be supplied with the later-signed contract documents. Section 7.14 states, in relevant part: 7.14 Contractor's Insurance The contractor shall not commence any work in connection with this ITB . . . until he has obtained all of the . . . types of insurance and such insurance has been approved by the Department. The Department shall be furnished proof of coverage of insurance by Certificates of Insurance . . . accompanying the contract documents and shall name the Department as an additional named insured [emphasis added]. Indeed, the evidence demonstrated that the Department has long interpreted these provisions to require a winning bidder to provide Certificates of Insurance at the time a contract is entered into and not as part of the essential requirements of the bid due at bid opening. While the Department could (and probably should) clarify this provision, its interpretation of its bid specifications is not unreasonable under these facts. In this case, five bids were timely submitted in response to the ITB, including those of K & M and Cumbaa. On March 8, 2011, the Department opened bids for the ITB. Cumbaa submitted the highest bid for the contract, at $22,197.48. K & M submitted the next highest bid at $20,001.00. At the bid opening, Cumbaa's bid included a Cost Information Sheet, a copy of the signed front page of the bidder acknowledgement form, and the Contact for Contract Administration form known as Attachment 1. However, the bid did not contain the second side of the bidder acknowledgement form or a Certificate of Insurance form at the time the bid was opened. K & M's bid contained the same documents as Cumbaa's bid, as well as the second side of the bidder acknowledgement form and a number of certificates of insurance for K & M. The evidence showed that Cumbaa did not include the Certificate of Insurance form in its sealed bid upon the advice of the Department that the form was not required at bid opening. However, Cumbaa had insurance coverage in place at the time of the bid opening and faxed its certificates of insurance to the Department on March 10, 2011. Given these facts and the Department's reasonable interpretation of its ITB, the omission of Cumbaa's certificate of insurance was neither required at the time of the bid opening, nor material to the award of the bid. The omission of the second page of the bidder's acknowledgement form was not noticed by anyone reviewing the bids until its omission was pointed out by K and M in this bid protest. Cumbaa faxed a copy of the back side of the document to the Department on April 11, 2011. Clearly, this lack of notice demonstrates the immateriality of the back side of the bidder's acknowledgement form. Additionally, since the signatures of both bidders were on the front page of the form submitted by them and those signatures bound the bidders to the terms of the ITB, there was no evidence that demonstrated why submission of a copy of the back side of the form was material to the award of this bid. Ultimately, the Department reviewed the bids for responsiveness and determined that Cumbaa was the highest responsive bid. On March 11, 2011, the Department posted its intent to award the bid to Cumbaa Enterprises, Inc. As indicated, there was no evidence that the omission of these two documents from the Cumbaa bid were material deviations from the bid specifications since neither omission impacted the ultimate contract requirements and did not materially impact the integrity of the bid process. Indeed, the insurance certification was not required for responsiveness under Section 5.1 of the bid under a long-standing and reasonable interpretation of that requirement by the Department. For these reasons, this bid protest should be dismissed.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent, Department of Corrections, enter a final order dismissing the Protest of K & M Pine Straw. DONE AND ENTERED this 1st day of July, 2011, in Tallahassee, Leon County, Florida. S DIANE CLEAVINGER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 1st day of July, 2011. COPIES FURNISHED: Kurt Eldridge K and M Pine Straw 20583 John G Bryant Road Blountstown, Florida 32424 Edith McKay, Esquire Department of Corrections 2601 Blair Stone Road Tallahassee, Florida 32399-2500 Edwin G. Buss, Secretary Department of Corrections 2601 Blair Stone Road Tallahassee, Florida 32399-2500 Jennifer Parker, General Counsel Department of Corrections 2601 Blair Stone Road Tallahassee, Florida 32399-2500

Florida Laws (4) 120.569120.57120.687.14
# 2
PANHANDLE GRADING AND PAVING, INC. vs DEPARTMENT OF CORRECTIONS, 93-004210BID (1993)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jul. 29, 1993 Number: 93-004210BID Latest Update: Jul. 14, 1995

The Issue The issue addressed in this proceeding is whether Petitioner or Intervenor submitted the lowest and best bid on Project No. RS-40.

Findings Of Fact On June 4, 1993, Respondent issued an invitation to bid (ITB) for Project No. RS-40 to develop the site for the future construction of a work camp in Holmes County. The work under Project No. RS-40 specifically included site preparation, grading, electrical work, sewage, utilities and fencing. The bids were due to be opened on June 29, 1993. Ten bids were submitted to the Department, including Petitioner, Panhandle Grading and Paving, Inc., and Intervenor's, Hewitt Contracting Co., Inc., bids. Panhandle's bid total was $815,734.00, and was the lowest monetary bid. Hewitt's bid total was $847,554.00, and was the third lowest monetary bid. Baxter Asphalt had the second lowest monetary bid. However, both Baxter and Panhandle's bids were disqualified as nonresponsive because neither company complied with the Department's prequalification requirements. Baxter did not protest the Department's bid award to Hewitt and Baxter is not a party to this action. On the other hand, Hewitt's bid was accepted since Hewitt had complied with the Department's prequalification requirements and was otherwise responsive to the ITB. Therefore, the Department awarded Hewitt the contract for Project No. RS-40 since in its opinion Hewitt was the lowest responsive bid on the project. The ITB clearly notified potential bidders that they must prequalify with the Department. The ITB stated, in pertinent part: All bidders must submit evidence that they are qualified to perform the work in accordance with Section B, paragraph B-2 of the specifications. Evidence of eligibility must be submitted to the owner (defined in article B-1) not later than five (5) calendar days prior to bid date. Additionally, the cover sheet for the bid documents admonished all bidders to submit evidence of their eligibility to bid to Respondent at least five (5) days before the bid letting. The cover sheet stated: All bidders on this project must prequalify according to the provisions of section B, "Instructions to Bidders", article B-2. Evidence of eligibility must be submitted to the owner (defined in article B-1) not later than five (5) calendar days prior to bid date. Section B-1 of the bid documents defines the owner of Project RS-40 as the Department of Corrections. Section B-2 of the bid documents instructed all bidders to prequalify with Respondent to participate in the bid process. Section B-2 states: Prequalification: Each bidder whose field is governed by Chapter 399, 489, and 633 of the Florida Statutes for licensure will be prequalified by the Department to participate in the bid process for a specific field or area of construction based on the bidder's area of license or certification. Bidder qualification requirements and procedures are established by the State of Florida, Department of General Services rule (Chapter 13D-11, Florida Administrative Code) and by the bidding conditions and specifications. Failure of the bidder to strictly meet and follow all such requirements and procedures may result in bid rejection or disqualification for contract award. For the bidder's convenience, the provisions of Rule 13D-11.004 Bidder's Qualifications Requirements and Procedures are set forth below. Requirements: Each potential bidder must present, or have presented within this current biennium (July 1 through June 30) odd number years, evidence that: He is authorized to perform the work required by these documents in accordance with the applicable provisions of Florida Statutes governing contractors, as a general (Insert contractor designation) contractor. If the Bidder is a corporation, he must submit evidence that this corporation is properly registered with the State of Florida, Department of State, Division of Corporations, and holds a current State Corporation Charter Number in accordance with the Florida Statutes. (*This sentence to be deleted by Architect- Engineer if not applicable.) All interested firms who have NOT qualified within the current biennium (July 1 thru June 30) odd number years must submit evidence of their eligibility during the bidding period, not later than five (5) calendar days (received date) prior to the bid date. The Owner may, for good cause, allow a firm to correct any deficiencies in evidence submitted. Notice of qualification will be mailed to each bidder, but a Bidder may not receive the written notification prior to a bid opening. He may learn his status prior to the bid opening time by calling the Owner (Department of Corrections), Bureau of Facilities Services at 904-487-1330). The Bidder shall submit the required evidence of eligibility to the Department of Corrections, Bureau of Facilities Services, 2601 Blairstone Road, Tallahassee, Florida 32399-2500. (emphasis supplied) All information shall indicate the full name, address and telephone number of the individual, partnership, or corporation, and the name of the contact person. Include a self-addressed stamped envelope. The names of all bidders will be checked against the list of contractors who have prequalified in accordance with the requirements of Section B-2. Additionally, a careful reading of Rule 13D-11, Florida Administrative Code, reveals that the information required under the Rule should be submitted to the owner of the project involved in the bid process, i.e. the Department of Corrections in this case. A contractor is the person who is qualified and responsible for an entire project and includes the person who submits a bid for a given project. Section 489.105(3), Florida Statutes. A general contractor is a person who is unlimited as to the type of work they can do, unless a specific type of license is required by Chapter 489, Florida Statutes. Section 489.105(3)(a), Florida Statutes. See also Section 489.113, Florida Statutes. Under Chapter 489, Florida Statutes, a contractor can be a certified general contractor or a registered general contractor. A certified general contractor can contract in any jurisdiction in the state without fulfilling the competency requirements of the local jurisdiction. Section 489.105(8), Florida Statutes. On the other hand, a registered general contractor is required by Section 489.117(2), Florida Statutes, to comply with all local licensing requirements. Registration with the state is specific for a given local jurisdiction and cannot be used in another jurisdiction. Section 489.113(2), Florida Statutes. In fact, Section 489.113(1), Florida Statutes, requires a contractor to be registered for a specific jurisdiction prior to engaging in the business of contracting. Additionally, a contractor must subcontract electrical, mechanical and plumbing work unless the contractor is state certified or holds the specific trade license required by the appropriate local authority if such a local license is required. Section 489.113(3), Florida Statutes. Importantly, Chapter 489, Florida Statutes, permits a person to act as a prime contractor, including submitting a bid on a project, where the bulk of the work under the contract is covered by the contractor's specific license, as long as the parts of the project for which he is not licensed are subcontracted to persons holding an appropriate license. Section 489.113(9), Florida Statutes. Respondent requires prequalification of contractors in advance of its bid lettings to ensure that everyone who bids is legally or financially qualified to do the work required in the bid. The five (5) day deadline prior to the bid letting gives Respondent's staff an opportunity to resolve any irregularities in a bidder's prequalification materials prior to the letting. Indeed, if a contractor is state registered, as opposed to state certified, Respondent's staff, prior to the bid, routinely contacts the local government with jurisdiction over the building site to determine if there are any local licensing requirements and if there are, to determine if the bidder/contractor is locally licensed in that jurisdiction. This process avoids the waste of time involved in reviewing a bid package from a bidder who cannot ultimately perform the work called for in the bid. More importantly, this process prevents a locally unlicensed registered contractor from having the ability to void a contract at its will after the bids are opened since it would be unlawful for the contractor to have either bid on a project located in a jurisdiction where the contractor was not licensed or enter into such a contract. The ability to refuse an award of a bid clearly constitutes an unfair advantage to the locally unlicensed registered contractor and could not be waived as immaterial by an agency. In this case, Hewitt is a certified general contractor and is therefore automatically qualified to work in Holmes County. Panhandle is a registered general contractor and can only bid on Project RS-40 if it has met the requirements for general contracting in Holmes County. The prequalification process requires a bidder who has not prequalified with Respondent during the current biennium to submit to Respondent his current state contractor license certification or registration, as well as his current corporate charter registration (if a corporation). When Respondent opened the bids for the Project, Petitioner had neither prequalified with Respondent nor obtained a license or certification of competency to engage in contracting work in Holmes County. Petitioner thought it was already prequalified under its prequalification with the Department of Management Services. However, prequalification with the Department of Management Services does not meet the requirements of the ITB which requires prequalification with the Department of Corrections. Panhandle did obtain the necessary licensure after submitting its bid and after the bids were opened. However, such belated licensure does not negate the unfair advantage created by Panhandle's failure to prequalify and be properly licensed prior to the bid opening as required by the bid documents.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent issue a Final Order in this case dismissing Petitioner's formal protest and awarding the contract for the Project to Intervenor. DONE AND ENTERED this 4th day of October, 1993, in Tallahassee, Florida. DIANE CLEAVINGER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 4th day of October, 1993.

Florida Laws (6) 120.57489.105489.113489.117489.127489.131
# 3
RON A. ROYAL, INC. vs. SARASOTA COUNTY SCHOOL BOARD, 86-002233BID (1986)
Division of Administrative Hearings, Florida Number: 86-002233BID Latest Update: Aug. 19, 1986

The Issue Whether the Barton-Malow Southern, Inc., deviated from the bid requirements, and if so, whether such deviation consists of a minor deviation which may be waived by the respondent, or whether Ron A. Royal, Inc., should be awarded the elementary school "C" project as the lowest responsive bidder.

Findings Of Fact On April 20, April 27, and May 4, 1986, the Board advertised its Notice of Call for Sealed Bids, soliciting bids for the construction of Elementary School "C". The notice advised that the contract to be awarded would require approval of subcontractors by the Board and stated that the Board "reserves the right to reject any and all bids received and to waive any and all informalities in regard thereto." A pre-bid conference was held on May 15, 1986, at which time the potential bidders were advised that page 14 of the bid documents entitled "List of Subcontractors" would be deleted and addendum #1 would include a more specific list of subcontractors to be completed by the bidder. The original list of subcontractors stated: The undersigned, hereinafter called "Bidder", list below the names of all the subcontractors who will perform under the Bidder. Any work item (Trade) not included will be assumed by the owner as being performed by the Bidder's own forces." A space was provided for the bidder to state the work item and the name of the subcontractor who would perform the work. Addendum #1 instructed the bidders to delete the original page C.14 and insert the enclosed sheet C.14 (addendum #1) "List of Subcontractors" for submission with the sealed bids. The substituted list of subcontractors provided as follows: The undersigned, hereinafter called "Bidder", lists below the names of the subcontractors who will perform under the Bidder. In the event the general contractor will perform one of the phases listed with his own personnel, he shall state by "general contractor". The form listed 20 specific areas of work, such as site work, iron and steel work, roof decks, and electrical, and provided a space for the bidder to fill in the firm name and address of the subcontractor for each specific area. Bids were submitted to the Board by nine (9) general contractors. The lowest bid by $310,000, was submitted by Barton-Malow; the second lowest bid was submitted by Royal. On the list of contractors submitted with Barton Malow's bid, Barton- Malow listed "G.C". (General Contractor) for the work areas described as site work, concrete work, masonry work iron and steel work, and lathing and plastering. Barton-Malow listed a subcontractor and "G.C." for phases described as hard tile and electrical. For the work areas described as "roof decks" and "roofing and sheet metal" three (3) subcontractors were listed for each of the areas. The list submitted by Royal with its bid provided that the concrete work would be performed by the general contractor and listed a single subcontractor for each of the other 19 areas of work specified. Barton-Malow was the only bidder who listed multiple subcontractors for a specified work area. In the blanks provided for the subcontractors' addresses, Royal listed the city where each subcontractor was located; Barton-Malow did not provide any addresses bout stated at the top of the column "will be advised upon request." None of the bidders provided street addresses for the subcontractors, however, only one bidder other than Barton Malow failed to provide the city in which the subcontractor was located. Immediately after the bids were opened and read, 1/ the meeting was adjourned and Mr. Derryberry, Mr. Collins, and two other people reviewed the bids. Mr. Derryberry concluded that the Barton-Malow bid was not in compliance with the bid requirements due to the manner in which Barton-Malow had filled out the subcontractor list. Mr. Derryberry therefore recommended to the Board that the Barton-Malow bid be rejected because of the perceived irregularities and the bid of Royal be accepted. The recommendation of the architect was adopted as the recommendation of the school administration and presented to the Board at a public meeting on June 3, 1986. The Board received the report of the architect and the administration, heard from the attorneys and representatives of Barton- Malow and Royal, and then voted to waive any irregularities and accept the Barton-Malow bid. The original page C.14 was approved by the Board in about 1980 and used since that time. However, there had been some difficulty with that form on two different jobs within the last six months, and therefore it was decided to clarify the purpose of the form by specifically listing all the major subcontracting areas. The intent was to require all bidders to list the primary subcontractor in each of the major work areas, and thus prevent bid shopping after the bids were opened. The architect, Mr. Derryberry, prepared and included the amended form C.14 as part of Addendum #1 to the bid documents. Although the Board never formally approved the amended form, Mr. Derryberry had the authority to clarify any of the bid documents by addendum. Page C.14 (Addendum #1) lists 20 major subcontracting areas; however, in almost all of the areas it would be possible for more than one subcontractor to perform the designated work, and in several areas it would be unlikely that one subcontractor would perform all the required work. For example, site work includes paving, earth moving, culvert work, fencing, and irrigation, and one subcontractor would not normally do the work in all those areas. The amended page C.14 does not state that only one subcontractor should be listed for each specified work area. The bidders were not advised at the pre-bid conferences or subsequent thereto, that only one subcontractor should be listed in each category. The only information the bidders received regarding the list of subcontractors was the information contained on the revised page C.14. In other words, the bidders were simply directed to list "the names of the subcontractors who will perform under the Bidder", and to list general contractor when "the general contractor will perform one of the phases listed with his own personnel." In the subcontractor list submitted with their bid, Barton-Malow listed "Batten Electric Co./G.C." for the subcontract "Electrical", and listed "Bauer & Assoc./G.C." for the "Hard Tile" subcontract. The listing of a subcontractor and the general contractor in these areas is not a deviation from the bid requirements. There is no indication on the list submitted by Barton- Malow that the listing of a subcontractor and the general contractor in the hard tile and electrical categories meant anything other than both the subcontractor and the general contractor would perform the work required in those areas, and there was no evidence presented at the hearing that would require a different conclusion. 2/ Categories 5 and 6 on the subcontractor list are "roof decks" and "roofing and sheet metal." Although listed as two separate categories, the same subcontractor would have to perform both due to the bid requirements. Further only one subcontractor can perform the roofing work; it is not an area that is divisible into subcategories that can be performed by different subcontractors. For categories 5 and 6, Barton-Malow listed "H. H. Robertson/Architectural Exteriors/Commercial Roof Decks." As admitted by Barton-Malow, that all three subcontractors "will perform" the subcontract is an impossibility. 3/ From the list submitted by Barton-Malow it cannot be determined who will perform and be responsible for the roofing work. When asked at the hearing who was going to perform the roofing work for Barton Malow, the vice-president of operations for Barton-Malow responded, "One of those three would have done it." He indicated that a submission would have been made to the Board designating the subcontractor. By listing three subcontractors for the two roofing categories, Barton-Malow deviated from the bid requirements. The subcontractor list contained one basic requirement, that the subcontractors listed "will perform." By listing three subcontractors for the roofing, when only one subcontractor could performs Barton-Malow would be able to bid shop for subcontractors after the bid submission. This would give Barton Malow a definite advantage over the other bidders who complied with the bid requirements and listed only the one contractor who would perform the work. The other bidders would be bound to use the subcontractor listed and therefore, would be unable to negotiate for a better price after obtaining the contract. However, by listing multiple subcontractors, Barton-Malow would be able to negotiate for a better price because it had not committed itself to any one subcontractor. In five categories, site work, concrete work, masonry work, iron and steel work, and lathing and plastering, Barton Malow listed general contractor. About an hour after bid opening, Mr. Derryberry called Mr. Polso, the Vice- President of Operations for Barton-Malow, to inquire about the bid because it was so much lower than the other bids. Mr. Polso assured Mr. Derryberry that there had been no mistake in the amount bid. Mr. Derryberry then asked about the listing of general contractor for the iron and steel work because he had never known of a general contractor doing that type of work. Mr. Polso stated that he had not had time to determine the low bidder in that category and was still getting prices. He also said that Barton-Malow would not be doing the lathing and plastering. However, when Mr. Derryberry advised that he was recommending that the bid be disqualified due to the incompleteness of the subcontractors form and asked whether Barton-Malow wished to withdraw its bid, Mr. Polso stated that Barton-Malow had no intention of withdrawing its bid. Subsequently, Mr. Polso met with Mr. Derryberry and Mr. Collins at the school offices and advised them that Barton-Malow had every intention of performing the work where general contractor had been listed. Barton-Malow is a wholly owned subsidiary of Barton Malow Company and has the resources of Barton-Malow Company available when necessary. In 1985, Barton-Malow did between 60 and 70 million dollars of construction work; Barton- Malow Company had a dollar volume of 600 million dollars. Barton-Malow has the capacity to perform work in the areas where it listed general contractor. Barton-Malow prepares its bid by estimating the value of the total project and the value of the majority of the specific trades involved. If Barton-Malow does not receive a bid from a subcontractor that it feels is competitive in a particular trade area, it performs that work itself. The C.14 (Addendum #1) form permitted a bidder to list "general contractor" in any or all subcontract areas in which it would perform the work with its own personnel. Once the bids are opened, the bidder cannot unilaterally substitute a subcontractor for the general contractor. The general contractor would be required to do the work unless it received authorization to substitute a subcontractor based upon a showing of good cause. The evidence does not support a finding that Barton-Malow was incapable of performing the work in the areas in which it listed "general contractor." Therefore Barton- Malow did not deviate from the bid requirements by listing "general contractor" in five of the twenty specified areas. Although Baron-Malow deviated from the bid requirements by failing to list any addresses on its subcontractor list, this was a minor irregularity which did not give Barton-Malow any competitive advantage over the other bidders. In Division C, Article 5, Section 5.3.1., the bid documents provide: It is the intent of the owner to award a Contract to the lowest responsible Bidder provided the Bid has been submitted in accordance with the requirements of the Bidding Documents....The Owner shall have the right to waive any informality or irregularity in any Bid or Bids received and accept the Bid or Bids which in his judgment, is in his own best interests.

Florida Laws (2) 120.57255.0515
# 4
SOLID WASTE AND RECOVERY SYSTEMS, INC. vs DEPARTMENT OF CORRECTIONS, 89-005854BID (1989)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Oct. 31, 1989 Number: 89-005854BID Latest Update: Feb. 07, 1990

Findings Of Fact The Department of Corrections (Corrections) initially published an Invitation to Bid (ITB) 90-Region-001 for the provision of a recyclable baling machine which had an opening date and time of 1:00 p.m., August 22, 1989. Upon opening and evaluation of the bids filed in response to ITB 90- Region-001, Corrections' purchasing and technical staff determined that the specifications for this initial ITB had been drafted too narrowly for them to validly and reasonably compare the bids submitted. This was Corrections' first attempt to meet certain recycling mandates and the agency personnel were initially unfamiliar with all of the machinery available in the marketplace. Lack of technical literature from some bidders was also a problem. In comparing the five bid responses received, it became apparent to Barbara Stephens, Corrections' Purchasing Director, that the specifications she had initially drafted worked against agency interests in that they were so narrow that different models could not be compared. In Ms. Stephens' words, one could not even compare "apples and apples," let alone "apples and oranges." The line item on Page 6 defied comparison and other line items presented significant comparison problems. After a review by Corrections' General Services Specialist Bob Sandall, it was determined that it was to the agency's advantage, as well as advantageous to the competitive bidding process, to rebid on more general specifications instead of specifications solely geared to one single model of one type of baler already owned by the agency, a McDonald single phase baler. For the foregoing reasons, Corrections elected to reject all bids received in response to ITB 90-Region-001 and rebid the item so as to broaden the eligibility base through new specifications, thereby ensuring that more than a single manufacturer could compete while making line item comparisons by the agency possible. Line item comparisons were considered advantageous to all potential bidders and to the agency and essential to a fair competitive bidding process. Considering purely bottom-line cost, Petitioner Solid Waste was the low bidder on initial ITB No. 90-Region-001 if its mathematical error were ignored and its bid were recorded as $23,960.00 instead of as $35,970.00. There were apparently some other problems with Solid Waste's bid response. These were not clearly addressed by any witness' testimony, but it is apparent that the requested manufacturer's specification sheet was included with Solid Waste's response to ITB 90-Region-001. Corrections did not reach any of the potential bid defects of Solid Waste because the agency elected to discard all the bids almost immediately. Rule 13A-1.002(9) F.A.C. provides that an agency shall reserve the right to reject any and all bids and shall so indicate in its invitation to bid. Corrections followed this requirement in General Condition 10 of ITB No. 90- Region-001, which provides in pertinent part, as follows: As the best interest of the State may require, the right is reserved to reject any and all bids . . Bob Sandall and Barbara Stephens redrafted the bid specifications for the recyclable baling machine more broadly, primarily to encourage greater competition of bidders. Corrections properly published these new specifications in ITB No. 90-Region-001 on or about September 18, 1989. Bids were to be opened on October 3, 1989. On October 3, 1989, the bids submitted in response to ITB No. 90- Region-001 were opened and checked for completeness. Upon opening the bid packet submitted by Petitioner Solid Waste, Corrections personnel discovered that the manufacturer's specification sheet which had been required in both initial ITB No. 90-Region-001 and in rebid ITB No. 90- Region-001R was missing. Based on the missing specification sheet, Petitioner's bid on ITB No. 90-Region- 001R was rejected as unresponsive. General Condition 7 in ITB 90-Region-001R provided in pertinent part: Bidder shall submit with his bid, cuts, sketches, and descriptive literature and/or complete specifications. Reference to literature submitted with a pervious bid will not satisfy this provision. The State of Florida reserves the right to determine acceptance of item(s) as an approved equivalent. Bids which do not comply with these requirements are subiect to reiection. (Emphasis supplied) Special Condition VI of ITB 90-Region-001R, "Submission of Mandatory Forms/Literature," further provided that: 5. Complete Technical Data on items other than as specified shall be provided with bid by the vendor, for evaluation purposes, otherwise bid will not be considered. Nowhere in ITB 90-Region-001R is there any suggestion that responses thereto are supplemental to those filed for ITB 90-Region-001 or that "carryovers" or "reactivations" of earlier ITB 90-Region-001 responses would be considered. Corrections rejected other bidders' responses for other acts of non- responsiveness, and it was not necessary to waive any condition in order to award the bid to any of the bidders who were in full compliance with ITB 90- Region-001R. Petitioner timely filed a formal written protest to Corrections' bid tabulation of ITB 90-Region-001R on October 23, 1989. In this protest, Petitioner also included its only and untimely challenge to the agency's rejection of all bids for ITB 90-Region-001.

Recommendation Upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department of Corrections enter a Final Order dismissing Petitioner's protest and ratifying its rejection of all bids for ITB 90-Region- O01R and its tabulation of bids for ITB 90-Region-001R. DONE AND ENTERED this 7th day of February, 1990, in Tallahassee, Florida. ELLA JANE P. DAVIS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 7th day of February, 1990. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 89-5854BID The following constitute specific rulings pursuant to Section 120.59(2) F.S. upon the parties' respective proposed findings of fact (PFOF): Petitioner's PFOF: 1. is accepted except for the ultimate conclusion of law. See Conclusions of Law. 2-3, 5-7 are rejected as mere legal argument or proposed conclusions of law. See Conclusions of Law. 4 is rejected as characterization of testimony. Respondent' s PFOF: 1-7 are accepted. COPIES FURNISHED: W. K. Lally, P.A. 6160 Arlington Expressway Jacksonville, Florida 32211 Perri M. King Assistant General Counsel Department of Corrections 1311 Winewood Boulevard Tallahassee, Florida 32399-2500 Courtesy copy to: Richard L. Dugger, Secretary Thomas W. Riggs, President Department of Corrections Municipal Sales and Leasing 1311 Winewood Boulevard Inc. Post Office Box 90306 Tallahassee, Florida 32399-2500 Lakeland, Florida, 33804 Louis A. Vargas, General Counsel Department of Corrections 1311 Winewood Boulevard Tallahassee, Florida 32399-2500

Florida Laws (2) 120.53120.57
# 5
CON-AIR INDUSTRIES, INC. vs SEMINOLE COUNTY SCHOOL BOARD, 98-004714BID (1998)
Division of Administrative Hearings, Florida Filed:Sanford, Florida Oct. 27, 1998 Number: 98-004714BID Latest Update: Jan. 20, 1999

The Issue Whether the School Board of Seminole County's, notice of intent to award Bid No. 102589, for air filter maintenance, service, and replacement to Filter Service and Installation Corporation was clearly erroneous, contrary to competition, arbitrary, or capricious.

Findings Of Fact The Seminole County School District is a political subdivision of the State of Florida, created by Article IX, Section 4, Florida Constitution. The powers and duties of the school board are enumerated in Chapter 230, Florida Statutes. The Superintendent of the Seminole County School District is a constitutional officer, whose office is created by Article IX, Section 5, Florida Constitution. The powers and duties of the Superintendent are enumerated in Chapter 230, Florida Statutes. The Seminole County School Board issued a call for bids for air filter maintenance service and replacement under Bid No. 102589 on September 14, 1998. Bids were submitted by Con-Air Industries, Inc., the protester, and Filter Service & Installation Corp., the apparent low bidder. The bids were opened on September 28, 1998, and were evaluated. Each bidder was determined to be a responsible bidder to the CFB. Intervenor submitted the lowest numerical bid. On October 1, 1998, Respondent's staff recommended that the CFB be awarded to Intervenor. The decision to recommend the award of the filter service Bid No. 102589 complies with the bid specifications. The instructions to bidders, as stated on the Proposal Form, direct a bidder to total lines A-C and to enter the total at line D. The instructions state that a bidder is not to include the cost as stated at lines E & F in the total. The proposal form then states that the total cost, as stated at line D shall be used to determine the apparent low bidder. The bid proposal document stated that the total of the prices stated at items A, B, and C would be used to determine the lowest numerical bid. The bid proposal document stated that the Respondent reserves the right to negotiate unit cost proposed for item E. The line D total submitted by the Petitioner is stated at $3.45. The line D total submitted by the apparent low bidder, is stated at $2.60. Intervenor submitted the lowest numerical bid. Intervenor does business under the fictitious name Filter Sales & Service. That fictitious name has been registered with the Secretary of State for the State of Florida. Filter Service & Installation Corp., and Filter Sales & Service are one and the same. The reference by Intervenor at line F to "Per Price Sheet" and the failure of Filter Service & Installation Corp. to attach a price sheet to its proposal form is not a material deviation from the requirements of the bid specifications. The total at line D is the total used to determine the lowest bidder. Filter Service & Installation Corp. is the lowest and best bid from a responsive and responsible bidder. The Petitioner followed the procedure set forth in the bid proposal document in making a determination that the Intervenor was the lowest numerical bidder. Petitioner reserved the right to reject all bids and to waive any informalities. Petitioner failed to prove that the notice of intent to award the bid to Intervenor was clearly erroneous, contrary to competition, arbitrary, or capricious.

Recommendation Upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Respondent award the contract for filter maintenance, service, and replacement under Bid No. 102589 to the Intervenor, Filter Service and Installation Corp., as recommended by its staff. DONE AND ENTERED this 11th day of December, 1998, in Tallahassee, Leon County, Florida. DANIEL M. KILBRIDE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 11th day of December, 1998. COPIES FURNISHED: Robert N. Hering, President Con-Air Industries, Inc. 3055 Pennington Drive Orlando, Florida 32804 Ned N. Julian, Jr., Esquire Seminole County Public Schools Legal Services Department 400 East Lake Mary Boulevard Sanford, Florida 32773-7127 Robert W. Smith, Esquire 430 North Mills Avenue, Suite 1000 Orlando, Florida 32803 Dr. Paul J. Hagerty, Superintendent Seminole County Public Schools 400 East Lake Mary Boulevard Sanford, Florida 32773-7127

Florida Laws (1) 120.57
# 6
SWEEPING CORPORATION OF AMERICA, INC. vs DEPARTMENT OF TRANSPORTATION, 91-008230BID (1991)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Dec. 26, 1991 Number: 91-008230BID Latest Update: May 01, 1992

Findings Of Fact Based upon the oral and documentary evidence adduced at the final hearing and the entire record in this proceeding, the following findings of fact are made. On October 11, 1991, DOT's District Four office let out for bid district contracts E4551 and E4554. Contract E4551 calls for the mechanical sweeping of Interstate 95 in Broward County. Contract E4554 calls for the mechanical sweeping of Interstate 95 in Palm Beach County. At a mandatory pre-bid conference, the bidders for the Contracts were provided with a packet which included a Notice to Contractors and Standard Specifications. The Notice to Contractors is a four page document which is specific to each contract. The Standard Specifications are the same for all district contracts. Both the Notice to Contractors and the Standard Specifications to the bidders required bidders to submit proof of the ability to acquire a performance and payment bond in an amount equal to the contract bid price. Bidders could satisfy this requirement by submitting a bid guarantee of 5% of the bid, submitting a notarized letter of intent from a bonding company or by providing a Certificate of Qualification issued by Respondent. The Notice to Contractors for both Contracts provided as follows: Failure to provide the following with each bid proposal will result in rejection of the contractor's bid.... District contracts of $150,000 or less require the following as proof of ability to acquire a performance and payment bond: A notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a performance and payment bond in the amount of your bid, should your firm be awarded the project; in lieu of a notarized letter the following may be substituted: (1) a bid guarantee of five percent (5%); or (2) a copy of the Contractor's Certificate of Qualification issued by the Department. (No emphasis added) Similarly, the first Standard Specification provides: 1.1 Bidders (contractors) A contractor shall be eligible to bid on this contract if:... (2) Proof of ability to acquire a performance and payment bond in an amount equal to the contract bid price is provided to the District Contract Administrator with the bid proposal. As such proof all bids must be accompanied by a notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a bond in the amount of your bid, should your firm be awarded the project.... The requirement to submit proof of the ability to acquire a performance and payment bond has been imposed on the Districts by DOT Directive 375-00-001-a (hereinafter the "Directive".) This Directive was in place at all times material to this proceeding. Section 3.2.2 of the Directive provides: A contractor shall be eligible to bid if: ...Proof of ability to acquire a performance and payment bond in an amount equal to the contract bid price is provided to the minicontract administrator with the bid proposal. As such proof all bids must be accompanied by a notarized letter from a bonding company, bank or other financial institution stating that they intend to issue a bond in the amount of the bid, should the firm be awarded the project. A bid guaranty as specified above may substitute as proof of ability to obtain a performance and payment bond. This applies to bids amount over or under $150,000. A copy of the Contractor's Certificate of Qualification issued by the Department may be substituted in lieu of a notarized letter for those contracts not requiring a bid bond. The bids for the Contracts were opened on October 11, 1991 in Fort Lauderdale, Florida. Bids were received from four bidders: CPM, SCA, Florida Sweeping, Inc. and P. F. Gomez Construction Co., Inc. In its bid proposals, SCA included executed bid bonds in an amount sufficient to cover the amount of each bid proposal. Each bid bond cost $55.00. CPM did not submit executed bid bonds with its proposals. Instead, CPM submitted letters from Mark A. Latini dated September 25, 1991. Those letters were provided on the stationery of Bonina-McCutchen-Bradshaw, Insurance and indicate that Mr. Latini is the "bond manager." The letters provide as follows: Amwest Surety Insurance Company is the surety for the above-referenced contractor and stands ready to provide the necessary performance and payment bond for the referenced bid should Certified Property Maintenance, Inc., be low and awarded the referenced contract. All bonds are subject to normal underwriting requirements at the time of the bond request.... The letters submitted by CPM with its bid proposals were not notarized and were not binding obligations to issue bonds since they were conditioned upon meeting certain unspecified underwriting requirements at the time of the bond requests. The submitted bids were reviewed by the District Four Contractual Services Office. The bids submitted by CPM were the lowest for each contract. Its bid for Contract No. E4551 was $109,343.97. Its bid for Contract No. E4554 was $30,312.63. SCA's bids for the Contracts were $139,442.14 and $44,100.00, respectively. During the initial review of the bid proposals, the Contractual Services Office rejected CPM's bids for failure to have its bonding company "letters of intent" notarized. In addition, the bid proposals submitted by Florida Sweeping, Inc. were rejected for failure to note a required addendum and the bids submitted by P. F. Gomez Construction Co., Inc. were rejected because the "proposal bond was not of proper character". On October 18, 1991, DOT posted its Notice of Intent to Award the Contracts to SCA, the only bidder for the Contracts whose proposals had not been rejected. CPM timely filed protests of the proposed awards to SCA on October 22, 1991. The protests filed by CPM argued that its bids should not have been invalidated simply because the bonding company's letters did not include notary seals. At this point, the sole basis for the disqualification of CPM's bids was the failure to have the bonding company letters notarized. Respondent contends that, except for the absence of the notary seal, the letters submitted by CPM met the requirements of the Notice to Contractor and the Standard Specifications cited above. However, those letters are equivocal and do not evidence a binding commitment to issue a bond upon award of the contract. The DOT officials admit that they do not know what "normal underwriting requirements" would or could be required by CPM's bonding company. This conditional language makes it uncertain whether CPM could obtain the necessary bond. Therefore, it is concluded that those letters do not meet the requirements of the Notice to Contractors, the Standard Specifications or the Directive. A hearing on CPM's protest was not held. CPM's president, Raymond Hanousek, who prepared CPM's bid and attended the pre-bid meeting, called DOT's District office the day the bids were opened and was informed that his company's bid was low, but was rejected because its bond commitment letter was not notarized. Mr. Hanousek spoke with Joseph Yesbeck, the District's Director of Planning and Programs. After their conversation, Mr. Yesbeck reviewed the file and met with Teresa Martin, the District's contract administrator for construction and maintenance contracts, and other members of the contracting staff. Ms. Martin explained why CPM's bid had been disqualified, and the matter was thereafter discussed with the District and Department attorneys. After reviewing the situation, Mr. Yesbeck determined that the failure to submit notarized letters should be considered a non-material deviation and the bids submitted by CPM should be accepted and considered the low responsive bids. Mr. Yesbeck concluded that the absence of the notary seal did not give any competitive advantage to CPM and that defects of this nature are routinely allowed to be cured. Therefore, he reversed the contract administrator's decision to disqualify CPM on both Contracts. The District secretary concurred in the decision reached by Mr. Yesbeck to repost the award of the Contracts. Mr. Yesbeck prepared a joint letter of reposting which removed CPM's disqualification and declared CPM to be the low bidder for both Contracts. At the time Mr. Yesbeck made his decision, he had not reviewed the Directive from the Assistant Secretary's office stating that there must be a notarized letter showing proof of ability to obtain a performance and payment bond. Mr. Yesbeck did not review the Directive until his deposition was taken one week prior to the hearing in this case. According to Ms. Martin, the option to provide a notarized letter from a bonding company as an alternative to the posting of a 5% bid guarantee or obtaining prequalification was designed to promote participation in state contracting by small business and minority business enterprise applicants. While DOT was apparently trying to make it easier and cheaper for companies to bid by not requiring a bond to be posted, the DOT Directive and the bid documents still clearly required unconditional proof that a bid bond would be issued if the contract was awarded to the bidder. CPM was not prequalified nor did it post a bond. Thus, in order to meet the requirements of the Notice to Contractors and the Standard Specifications, CPM's only option was to submit a notarized letter showing proof of ability to obtain a performance and payment bond. DOT was never provided with any proof that CPM had been prequalified by the bonding company for a bond and/or that a bond would unconditionally be issued if CPM was awarded the Contracts. Because the letters stated they were "subject to normal underwriting requirements at the time of the bond request", there was some possibility CPM would not be able to obtain a bond. Such a condition was not permissible under the bid doucments. The decision to accept CPM's bid was contrary to the DOT Directive, the Notice to Contractors and the bid specifications which require that a bidder demonstrate proof of ability to obtain a performance and payment bond. Consequently, it is concluded that DOT's decision to accept the conditional, unnotarized letters submitted by CPM was arbitrary and capricious. There is some indication that other DOT Districts have, on occasion, waived the notarization requirement for the bond letter. However, it is not clear whether the language in the bid documents was the same or similar in those cases and/or whether the bond letters were conditional. In the past, whenever District Four has gotten a bid without a notarized bond letter, the bid was rejected. Apparently, there has never been a protest based on such a denial in District Four. Under Section 337.18, DOT does not need to require notarized, unconditional bond letters on contracts under $150,000. Indeed, there was a suggestion that some DOT Districts have dropped the requirement for certain contracts under $150,000. However, the bid documents in this case clearly required some proof that the bidder could acquire a performance and payment bond upon award of the Contracts. It was incumbent for all bidders to meet this requirement. It was arbitrary to delete this requirement after the bids were submitted.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner enter a Final Order finding the bids submitted by CPM to be non-responsive and rejecting those bids. Petitioner should enter into negotiations with SCA regarding the award of the contract. In the absence of a favorable negotiation, Petitioner should enter a Final Order rejecting all bids and opening the Contracts up for new bids. DONE and ENTERED this 24th day of March, 1992, at Tallahassee, Florida. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of March, 1992.

Florida Laws (8) 120.53120.57120.68287.012287.057337.11337.18343.97
# 8
DUVAL FORD vs DEPARTMENT OF MANAGEMENT SERVICES, 93-006790BID (1993)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Nov. 23, 1993 Number: 93-006790BID Latest Update: Mar. 31, 1994

Findings Of Fact Pursuant to Section 287.042(2), Florida Statutes, the Department of Management Services (DMS), lets various Invitations to Bid (ITB) for the benefit of state agencies, cities, counties and other local government agencies so that these entities may purchase a variety of goods and services. On August 24, 1993, DMS issued Invitation To Bid #28-070-700-P. The bid was one of 225 Invitations to Bid issued by DMS in 1993. The bid was for the purchase of medium and heavy trucks. The bid which is the subject of this case involves truck #150. The truck #150 bid has thirteen pages with forty- seven options plus base truck bid blanks. General Condition 1 of the Invitation to Bid requires that "all corrections made by bidder to his price must be initialed." Other documents provided by the Department to interested bidders as part of the bid package reiterate the requirement that all price changes must be initialed. These documents include the "Checklist," a document entitled "Common Problems That Result in Bid Being Rejected" and the document entitled "Medium and Heavy Trucks Index." The requirement in General Condition I of the Invitation to Bid, that all price changes must be initialed, contains no printed exceptions with respect to "nonpreselected" options. The purpose of the requirements of General Condition 1 of the Invitation to Bid is to protect both the State of Florida as well as competing vendors. The reason for the requirement that all price changes or alterations be initialed by the vendor is to protect both the State of Florida against a successful bidder later inserting higher option prices and charging the state agencies those prices, and the vendor against the State later inserting lower prices and attempting to hold the vendor to those prices. General Condition 13 of the bid document states: LEGAL REQUIREMENTS: Applicable provisions of Federal, State and Local law and all ordinances, rules, and regulations shall govern development, submittal and evaluation of all bids received in response hereto and shall govern any and all claims and disputes which may arise between persons(s) submitting a bid response hereto and the State of Florida, by and through its officers, employees and authorized representatives, or any other person, natural or otherwise; and lack of knowledge by any bidder shall not constitute a cognizable defense against the legal effect thereof. . . (Emphasis added.) General Condition 13 incorporates Rule 60A-1.001(3), Florida Administrative Code, which permits the State to waive minor irregularities in the conformance of a bid proposal to the formal bid requirements. The lowest bidder is determined by two factors. The first factor is the price for the base truck. The base truck is the minimum truck which can be ordered in this contract with no options. It is basically a chassis with an engine. The second factor involves additions to the truck called preselected options or predetermined options. All of the other options for the particular vehicle are deemed nonpreselected options. Preselected options are generally the most frequently ordered additions to the base truck along with some other less frequently ordered options. The preselected options can vary from bid to bid; however, DMS always determines the preselected options before opening the bids. The price of any option cannot exceed retail price. There is, therefore, a ceiling for the prices of preselected and nonpreselected options. The preselected options are not announced until after the bid is posted to prevent dishonestly low prices on preselected options and to promote competitive prices throughout the contract document. The bidders therefore do not know which options are preselected when they are composing their bids. There is nothing to be gained by a bidder loading a particular option with a high markup, because the bidder cannot guarantee that the option will not be preselected. The bid evaluation price is the base truck price plus the price of the combined chosen preselected options. DMS received numerous bids on the ITB, including a bid from Petitioner and Intervenor. Atlantic Ford bid a combined price of $38,737.00, and was the apparent low bidder; Duval Ford bid a combined price of $39,944.00 and was the apparent second low bidder. Upon receipt of the bids from the bidders, the bids were held in a locked room until the bid opening. After the bid opening, the purchasing specialist assigned to this bid reviewed each bid for conformity to the general non-technical specifications. Only the Bureau of Procurement is responsible for the nontechnical review although other Bureaus or Divisions may review and have input into the review process. However, these other Divisions' input is not binding. In the nontechnical review the purchasing specialist reviewed each bid's signatures, whether or not the bid was signed in ink, and numerous other requirements. The purchasing specialist also reviewed the bids to determine if all base bid blanks and price blanks for preselected options were filled in and that no corrections were made to those prices without a bidder's initials acknowledging the change. The bids which failed to meet the general conditions of the bid for base bid items and preselected options were rejected as nonresponsive bids. After the initial nontechnical review, the bids were sent to the Division of Motor Vehicles and Watercraft for a technical evaluation. However, since each bid document contains bids for several trucks, there may be a mixture of responsive and nonresponsive bids for various trucks in the same document and the Division of Motor Vehicles and Watercraft may receive responsive and nonresponsive bids for technical review. John Bevins of the Division of Motor Vehicles and Watercraft reviewed the technical parts of the bid. This information included manufacturer's codes for options and base truck features as well as the manufacturer's retail price which no bidder can exceed. After John Bevins completed his review, he filled out a bid rejection recommendation form. John Bevins chose to include nontechnical items in his recommendation, although this was beyond the scope of his review. Mr. Bevins indicated on his bid evaluation form that Atlantic Ford failed to initial a typewritten correction on option 8206 of truck 150. Mr. Bevins returned the reviewed bids to the purchasing specialist along with his recommendation that Atlantic Ford's bid was not responsive since it failed to initial the typewritten correction on option 8206. The purchasing specialist discussed the failure of Atlantic Ford to initial the typewritten correction on option 8206 with H. P. Barker, Jr., the Bureau Chief of Procurement. H. P. Barker, Jr. has the final authority within the Bureau of Procurement to decide if a bid is responsive. He is the customary agency decision-maker on these matters. After careful consideration and discussion, H. P. Barker, Jr., determined that the failure of Atlantic Ford to initial the typewritten correction on a credit is a minor irregularity according to the Department's purchasing rules, since option 8206 was a nonpreselected option and did not effect the total bid price for determining the lowest bidder. Barker's decision was based on the State's interest in obtaining trucks at the lowest price, thereby obtaining the most goods per contracting dollar. Duval Ford conceded that the typewritten correction was faint and does not appear on photocopies of the bid. Barker testified that DMS accepts photocopies of bids. If Atlantic Ford had submitted a photocopy of its bid, as it could have legally done, then the typewritten correction would probably not have been noted by the Department or the other bidders. Barker also testified that bids are not rejected if nonpreselected option blanks are not filled in. Dealers can choose not to offer all nonpreselected options. Finally, in this case option 8206 was a credit. Even if a purchaser under the contract orders option 8206, it will pay six dollars ($6.00) less for the overall truck from Atlantic Ford than if the truck was ordered from Duval Ford. Duval Ford offered evidence from 1991, that DMS had rejected a bid of another dealer for failure to initial a price change on a nonpreselected option. However, Nelson Easom, Duval Ford's manager had not been able to discover any similar rejections in the subsequent two years. Barker testified that the policy regarding noninitialed nonpreselected options changed three years ago. DMS then decided to treat them as minor irregularities. The policy change was based on the public policy to award the lowest bid whenever possible and to prevent minor deviations in bids from causing the state to pay higher prices for goods and services. Moreover, the evidence did not show any abuse of the bid process which would occur should price changes not be initialed. The alleged "protection" afforded to bidders by requiring every change to be initialed is at best tenuous since any fraudulent price changes could easily be recognized by the party against whom the change was made. Given these facts, this case over initials appears to be much ado about nothing, and the failure of Atlantic Ford to initial its price change on a nonpreselected option is a minor irregularity and waiveable by DMS. DMS therefore did not act in an arbitrary and capricious manner by waiving the irregularity and awarding the bid to Atlantic Ford.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent issue a Final Order in this case dismissing Petitioner's formal protest and awarding the contract for the Project to Atlantic Ford. DONE AND ENTERED this 15th day of March, 1994, in Tallahassee, Florida. DIANE CLEAVINGER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of March, 1994. APPENDIX TO RECOMMENDED ORDER, CASE NO. 93-6790BID The facts contained in paragraphs 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 16, 17, 18, and 19, of Respondent's Proposed Findings of Fact are adopted in substance insofar as material. Paragraphs 15 of Respondent's Proposed Findings of Fact was legal argument. The facts contained in paragraphs 1, 2, 3, 4, 10, 13, 17, 18, 21 and 24 of the Petitioner's Proposed Findings of Fact are adopted in substance insofar as material. The facts contained in paragraphs 11 of Petitioner's Proposed Findings of Fact were immaterial. The facts contained in paragraphs 5, 6, 7, 8, 9, 12, 14, 15, 16, 19 and 20 of Petitioner's Proposed Findings of Fact are subordinate. 9. The facts contained in paragraphs 22 and 23 of Petitioner's Proposed Findings of Fact were not shown by the evidence. COPIES FURNISHED: Charles Cook Howell, III Howell, O'Neal & Johnson Suite 1100 Jacksonville, Florida 32202 Cindy Horne Office of the General Counsel Department of Management Services Knight Building, Suite 309 2737 Centerview Drive Tallahassee, Florida 32399-0950 Kerri L. Barsh Attorney at Law Greenberg Traurig et al. 1221 Brickell Avenue Miami, FL 33131 Paul A. Rowell, Esquire General Counsel Department of Management Services 312 Knight Building 2737 Centerview Drive Tallahassee, FL 32399-0950 William H. Lindner Secretary Knight Building, Suite 307 Koger Executive Center 2737 Centerview Drive Tallahassee, FL 32399-0950

Florida Laws (3) 120.53120.57287.042 Florida Administrative Code (1) 60A-1.001
# 9
R. A. M. PLANT GROWERS, INC. vs DEPARTMENT OF TRANSPORTATION, 92-000169BID (1992)
Division of Administrative Hearings, Florida Filed:Miami, Florida Jan. 13, 1992 Number: 92-000169BID Latest Update: Apr. 16, 1992

Findings Of Fact Nine bids were received for Contract E4571, Project/Job No. 99004-3516 ("E4571"). Petitioner's bid was timely received. Respondent opened bids on December 13, 1991. Respondent posted its intent to award E4571 to J & D Tropical Landscape Design on December 20, 1991. Section 1.2 of the Bid Specifications for E4571, as modified by the Special Provisions, states: A contractor's bid shall be in the form of a unit price for each unit expected to be accomplished. The Special Provisions to E4571 require each bidder to submit a single unit price for each pay item called for in the Bid Price Proposal. Item 4 in the Special "Provisions provides: It shall be the responsibility of the Contractor to submit to the Department A SINGLE unit price for each pay item called for in the Bid Price Proposal. The Contractor shall be responsible for his/her method of averaging. Failure to comply shall result in the Contractor's Bid Proposal being declared "Irregular" and such Bid Proposals will be rejected. (emphasis added) Petitioner's Bid Proposal was properly declared irregular and rejected by Respondent. Petitioner failed to comply with the requirements of Item 4 in the Special Provisions by failing to submit a single unit price for each pay item, by failing to correctly average a unit price, and by failing to state the unit price in words. The Unit Price Sheet on page 23 of the Bid Proposals contains the following table listing item numbers A582- 2 through A584-4. Petitioner listed item number A583 as follows: ITEM PLAN ITEM DESCRIPTION AND UNIT PRICE $ AMOUNTS NUMBER QUANTITIES UNIT PRICE (IN FIGURES) (Exten- (IN WORDS) sion Price) 3/ A583 4 200.000 TREES (8' TO 20, 85 20400 PLANT ' HEIGHT OR CLEAR TRUNK) @ DOLLARS CENTS The actual extension price 4/ for 200 trees at $85 per unit is $17,000 rather than the $20,400 stated by Petitioner in the table on page 23. The "Contract Total" stated by Petitioner in the bottom right corner of the table is $37,013.20. The "Contract Total" that should have been stated if Petitioner intended the extension price of item number A583-4 to be $17,000 would have been $33,613. The "Contract Total" listed by a bidder on the Unit Price Sheet is the unverified contract price. The actual contract price is determined by Respondent pursuant to the formula given in Section 1.3 of the Bid Specifications. Section 1.3 of the Bid Specifications foil E4571 states: The contract price is defined as the sum of the unit bid price times the planned work for each item as shown on the Unit Price Sheet. Petitioner would have been the lowest successful bidder irrespective of whether Respondent had replaced the extension price for item number A583-4 and the "Contract Total" stated by Petitioner with the actual extension price for item number A583-4 and the actual "Contract Total" . However, Respondent is precluded from doing so by Section 3-1 of the Standard Specifications For Road ,and Bridge Construction ("Standard Specifications"), published by the Florida Department of Transportation (1991) and by the Special Provisions for E4571. Respondent follows "Section 3-1 of the Standard Specifications for the purpose of evaluating bid proposals. Section 3-1 is used, in part, to determine the extension price for item numbers listed on the Unit Price Sheet. Section 3- 1 provides in relevant part: In the event of any discrepancy in the three entries for the price of any item, the unit price as shown in words shall govern unless the extension and the unit price shown in figures are in agreement with each other, In which case they shall govern over the unit price shown in words. Petitioner did not show the unit price in words for any item number on the Unit Price Sheet, including item number A583-4. There is a discrepancy in the three entries for item number A583-4 on the Unit Price Sheet. Petitioner failed to show the unit price for item number A583-4 in words, and the unit price and extension price are not in agreement. Under such circumstances, Respondent interprets Section 3-1 of the Standard Specifications as requiring that Petitioner's bid be declared irregular and rejected. Respondent's interpretation of Section 3-1 of the Standard Specifications is reasonable and is consistent with the mandate in Item 4 of the Special Provisions for E4571. See Finding 4, supra. Furthermore, in practice, the correct unit price of a pay item is necessary to process payment under the contract and the contractor must submit invoices based upon the pay items and unit prices listed in its bid. The bid specifications for E4571 provide that a bidder is responsible for his or her own averaging of a stated unit price, and that if a bidder fails to provide a single unit price for each pay item on the Unit Price Sheet the bid shall be declared "Irregular" and will be rejected. The requirement to provide a single unit price for each pay item was emphasized by Respondent at the mandatory pre-bid meeting. Petitioner's representative attended the mandatory pre-bid meeting. No challenges were made to the bid specifications by any bidder.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent enter a Final Order dismissing the protest filed by Petitioner. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 20th day of February, 1992. DANIEL MANRY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (964) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of February, 1992.

Florida Laws (2) 120.57337.11