The Issue The Department of Corrections sought bids for construction of a health services building for a correctional facility. A discrepancy existed between the written specifications and the architectural drawings for the project. An addendum was issued to clarify the matter. The low bidder (Intervenor) did not acknowledge receipt of the addendum until several hours after the opening of bids. The Department accepted the Intervenor's bid. The Petitioner timely protested the action. The issue in this case is whether, in accepting the Intervenor's bid, the Department acted contrary to the requirements of law.
Findings Of Fact On July 31, 1990, the Department of Corrections (hereinafter "Department") issued an Invitation To Bid ("ITB") for PR-35-JRA, Project #90015, consisting of the construction of a Health Classification Building at the Columbia County Correctional Institution. In relevant part, the ITB requested price proposals for said construction, provided that the bid would be awarded to the responsive bidder submitting the lowest cost proposal, provided that "in the interest" of the Department, "any informality" in bids could be waived, and provided space on the bid form for acknowledgment of receipt of all addenda to the ITB. Bids were to be filed no later than 2:00 p.m. on September 11, 1990, the time scheduled for bid opening. Documents issued with the ITB included architectural drawings and written specifications for the building. The architectural firm of Jim Roberson and Associates, (hereinafter "JRA") had been employed by the Department to prepare the drawings and specifications. JRA was responsible for preparation and distribution of related addenda. Further, a JRA representative presided over the opening of bids on behalf of the Department. Following release of the ITB and supporting documents, JRA became aware of a conflict between sink faucets required by the drawings and those required by the written specifications. The specifications provided that sink faucets operated by hand levers or foot pedals were to be installed in the facility. The architectural drawings JRA indicated that sink faucets were to operate by means of "electric-eye" activators, rather than by hand levers or foot pedals. On September 10, 1990, JRA issued an addendum (identified as Addendum #2) 1/ to clarify that "electric-eye" type operators were to be included in the bids. The addendum was sent by telephone facsimile machine to all anticipated bidders. In part the addendum provides as follows: "This Addendum forms a part of the Contract Documents and modifies the original Specifications and Drawings, dated 31 July 1990, as noted below. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject the Bidder to Disqualification." On September 11, 1990, the eight bids submitted in response to the ITB were opened by the JRA representative. The Intervenor, Custom Construction (hereinafter "Custom"), submitted the lowest bid at $898,898. The Petitioner, David Nixon (hereinafter "Nixon"), submitted the next lowest bid at $900,000. The bid form provided by the Department as part of the ITB materials to prospective bidders provided space for acknowledgment of addenda to the ITB documents. Upon opening the bid submitted by Custom, the JRA representative officiating at the opening noted that the Custom bid failed to acknowledge Addendum #2 in the appropriate space on the bid form. 2/ Robert L. Harris, president of Custom Construction, attended the bid opening. When the JRA representative noted the lack of acknowledgment of Addendum #2, Mr. Harris stated that he was unaware of the addendum. At hearing, Mr. Harris testified that his secretary told him that Addendum #2 was not received by his office. The JRA representative testified that his review of JRA's FAX transmission records indicated that the FAXed Addendum #2 was received by all bidders. The greater weight of the evidence establishes that Addendum #2 was transmitted to and received by, all bidders. Upon leaving the bid opening, Mr. Harris immediately contacted his plumbing subcontractor, Jerry Stratyon, and discussed the situation. Approximately two hours after the bid opening, and after talking with Mr. Stratton, Mr. Harris notified JRA, in a letter transmitted by FAX machine to JRA, that his bid price did include plumbing fixtures required by Addendum #2. Mr. Harris concluded the letter, "[w]hen can we start work. I know you don't want the alternate." On October 8, 1990, JRA recommended to the Department, that the Custom bid be accepted. The letter of recommendation, in part, provides: The apparent low bidder however, did not verify receipt of Addendum No. 2 on the Bid Proposal. Our office did receive a, facsimile after the bid verifying Addendum NO. 2 receipt from the Contractor's Office." However, the actual letter from Custom to JRA states, not that Addendum #2 was received, but that it was included in the price bid by Custom's plumbing subcontractor. Both Nixon and Custom obtained plumbing bids from the same subcontractor, Jerry Stratton. The cost increase attendant to the requirements of Addendum #2 is approximately $2,400 over the plumbing fixtures indicated in the written project specifications. Mr. Stratton was aware of Addendum #2 and testified that the requirements of Addendum #2 were reflected in his price quotes to both bidders. Mr. Stratton provided the same price bid to Nixon and Custom. Mr. Stratton also provided bids to Nixon and Custom for HVAC work. Mr. Stratton was accepted as Custom's HVAC subcontractor. Nixon's bid indicates that another HVAC subcontractor will perform the cork should Nixon receive the contract. The ITB provided that bid modification or withdrawal was permitted on written or telegraphic request received from a bidder prior to the time fixed for opening. Mr. Harris did not attempt to either withdraw or modify Custom's bid prior to bid opening. No bid modification was permitted subsequent to the bid opening. The Department's policy is to waive minor irregularities when to do so would be in the best interests of the State and would not be unfair to other bidders. The evidence does not establish that Custom Construction's failure to acknowledge the addendum was purposefully designed to permit withdrawal of their bid subsequent to the public bid opening. The omission of acknowledgment of Addendum #2 provided Custom an opportunity to withdraw the bid that was not available to other bidders. Custom could have informed the Department that the bid price did not include the requirements of Addendum #2, and the bid could have been withdrawn. Custom was therefore provided with a substantial advantage or benefit not enjoyed by the other bidders. The other bidders, all of whom acknowledged receipt of Addendum #2, had no opportunity to, and would not have been permitted to, withdraw their aids. The fact that Custom did not withdraw the bid is irrelevant.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Department of Corrections enter a Final Order rejecting the bid submitted by Intervenor as nonresponsive and awarding the contract to the Petitioner. DONE and RECOMMENDED this 15th day of January, 1991, in Tallahassee, Florida. WILLIAM F. QUATTLEBAUM Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of January, 1991.
The Issue Whether Respondent properly rejected Petitioner's bid on the grounds that the bid did not meet a fatal item requirement.
Findings Of Fact On April 24, 1992, Respondent published a Request for Proposals (RFP) for the provision of housekeeping services to South Florida State Hospital. Attached to the RFP as Appendix I was a blank copy of Respondent's "Standard Contract" which is also referred to as its "core model contract". Paragraph 1.a. of Section D of the RFP contains the following instructions to bidders: BIDDER RESPONSE a. State of Florida Request for Proposal Contractual Services Acknowledgment Form, Pur 7033 The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, Appendix II must be signed and returned ... with the proposal or submitted by itself if you choose not to submit a proposal and wish to remain on the department's active vendor list. Paragraph 1.g. of Section D of the RFP, contains the following instructions to bidders: Required Bidders Certification Contract Terms and Conditions The proposal must include a signed statement in response to the RFP indicating acceptance of the terms and conditions of provisions of service as specified in the RFP and contained in the core model contract. Bidders were provided a copy of the RFP rating sheet which contained the following under the heading of Fatal Items: The following criteria must be met in order for the proposal to be considered for evaluation, failure to receive a "Yes" response for any time [item] will result in automatic rejection of the proposal. * * * Does the proposal include a statement agreeing to terms and conditions set forth in the core model contract and the RFP? Petitioner was represented at a "Bidders' Conference" held May 15, 1992, at which the fatal items were discussed. Bidders were advised that it would be necessary for the responses to contain a statement agreeing to the terms and conditions set forth in the core model contract. The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, contains the following certification: I certify that this proposal is made without prior understanding, agreement, or connection with any corporation, firm, or person submitting a proposal for the same contractual services, and is in all respects fair and without collusion or fraud. I agree to abide by all conditions of this proposal and certify that I am authorized to sign this proposal for the proposer and that the proposer is in compliance with all requirements of the Request for Proposal, including but not limited to, certification requirements. In submitting a proposal to an agency for the State of Florida, the proposer offers and agrees that if the proposal is accepted, the proposer will convey, sell, assign or transfer to the State of Florida all rights, title and interest in and to all causes of action it may now or hereafter acquire under the Anti-trust laws of the United States and the State of Florida for price fixing relating to the particular commodities or services purchased or acquired by the State of Florida. At the State's discretion, such assignment shall be made and become effective at the time the purchasing agency tenders final payment to the proposer. The State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, was signed by Richard A. Cosby on behalf of Petitioner and submitted as part of Petitioner's response to the RFP. Upon receipt of all responses, Respondent convened an evaluation committee to evaluate the responses. The evaluation committee determined that the response submitted by Petitioner did not contain the required statement agreeing to the terms and conditions set forth in the core model contract and the RFP. Consequently, the evaluation committee rejected Petitioner's proposal from further consideration. Petitioner does not challenge the specifications of the RFP, but, instead, asserts that Mr. Cosby's execution of the State of Florida Request for Proposal, Contractual Services Acknowledgment Form, PUR 7033, was sufficient to meet the requirement the evaluation committee found lacking. The language of the Contractual Services Acknowledgment Form, PUR 7033, that most closely approximates the certification that the bidder accepts the terms and conditions set forth in the core model contract and of the RFP is as follows: I agree to abide by all conditions of this proposal and certify that I am authorized to sign this proposal for the proposer and that the proposer is in compliance with all requirements of the Request for Proposal, including but not limited to, certification requirements. The proposal submitted by Petitioner did not contain any other statement which could be construed as accepting the terms and conditions set forth in the core model contract and the RFP. The broad language of the Contractual Services Acknowledgment Form, PUR 7033, upon which Petitioner relies does not state that the bidder accepts the terms and conditions set forth in the core model contract and the RFP. The evaluation committee properly determined that Petitioner's response failed to meet this fatal item. In this proceeding, there was evidence that the Respondent routinely inserts in its Request for Proposals the fatal item requirement that the bidders agree in writing to accept the terms and conditions set forth in the core model contract and the RFP, and that Respondent has never waived that fatal item requirement. There was no evidence that Respondent was using this fatal item requirement to discriminate against or in favor of any bidder.
Recommendation Based upon the foregoing findings of fact and conclusion of law, it is hereby RECOMMENDED that the Respondent dismiss Petitioner's bid protest. DONE AND ENTERED this 18th day of August, 1992, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of August, 1992. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 92-4311BID The following rulings are made on the proposed findings of fact submitted on behalf of the Petitioner. 1. The proposed findings of fact submitted by Petitioner are accepted in material part by the Recommended Order. Petitioner's conclusions based on those facts are rejected for the reasons discussed in the Recommended Order. The following rulings are made on the proposed findings of fact submitted on behalf of the Respondent. 1. The proposed findings of fact submitted by Respondent are adopted in material part by the Recommended Order. COPIES FURNISHED: Richard A. Cosby, Vice President National Cleaning of Florida, Inc. 1101 Holland Drive, #32 Boca Raton, Florida 33487 Colleen A. Donahue, Esquire District 10 Legal Office Room 513 201 West Broward Boulevard Fort Lauderdale, Florida 33301-1885 Sam Power, Agency Clerk Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700 John Slye, General Counsel Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700
The Issue Whether the Respondent, School Board of Broward County, Florida (Respondent or Board), may reject all bids as proposed for Bid No. 2002-02-FC, Group A1, or whether such action is illegal, arbitrary, dishonest, or fraudulent.
Findings Of Fact The Respondent is the entity charged with the responsibility of governing the public schools within the Broward County School District. As such, the acquisition of school properties and attendant improvements fall within the Board's legal authority. These cases involve the procurement of relocatable buildings suitable for classroom purposes. Pursuant to its authority, on or about December 27, 2002, the Respondent issued a bid that is the subject matter of the instant challenge. The bid, identified in this record as Bid 2002-02-FC, sought proposals for the procurement of district-wide relocatable buildings. In a prior time these buildings were known as "portable classrooms" or "portables." In the post-Hurricane Andrew world, these structures are now pre-engineered and constructed of concrete or steel (or a hybrid of both) and must be, by design, capable of being relocated to various sites. The Petitioners, Royal and Padula jointly, and the Intervenor, James B. Pirtle Construction Company, Inc. (Pirtle or Intervenor), design, construct, and install such structures. In these cases the bid sought several distinct proposals. First, the project sought vendors who would provide and deliver concrete relocatable buildings (Group A1). Group A2 (not at issue in this proceeding) sought steel relocatable buildings. Group B (also not at issue in the instant case) sought site adaptation prices for landscaping, lighted covered walkways, steps, ramps, and other engineering incidental to the installation of the buildings. The advertisement for the bid carried the same generic information as to all groups. The bid documents also contained many terms that were applicable to all groups. Pertinent to the issues of these cases are the following excerpts from the bid document (Joint Exhibit 2). The order of the excerpts should not suggest any significance. The excerpts are listed in this manner solely for convenience sake: BASIS OF AWARD In order to meet the needs of the school system . . . each Award will be . . . up to three responsive and responsible bidders meeting specifications, terms and conditions. Individual projects will be issued . . . based upon lowest cost among one or more bidders per project as determined by the project manager. Therefore, it is necessary to bid on every item in the group, and all items in the group must meet specifications in order to have the bid considered for award. Unit prices must be stated in the space provided on Document 00410 Bid Form. SBBC [the Respondent] reserves the right to procure goods from the second and third lowest bidders if: a) the lowest bidder cannot comply with delivery requirements or specifications; b) the lowest bidder is not in compliance with delivery requirements or specifications on current or previous orders; c) in cases of emergency; d) work may be issued to multiple contractors if in the opinion of The School Board of Broward County, Florida or its staff the work cannot be completed by a single contractor in the specified time such as a Summer, Winter or Spring Break or if it is in the best interest of SBBC to do so regardless of reason. ARTICLE 4 BIDDING PROCEDURES 4.01 FORM AND STYLE OF BIDS A. Bids shall be submitted on forms identical to Document 00410, Bid Form, and other standard forms included with the Bidding Documents. The following documents are required to be submitted with the Bid: * * * SIGNED SEALED ARCHITECTURAL AND ENGINEERING DESIGN DRAWINGS OF THE STRUCTURES TO BE PROVIDED (FOR RELOCATABLE BUILDINGS BID ONLY) 5.03 REJECTION OF BIDS AND IRREGULAR PROPOSALS * * * The Owner shall have the right to reject any or all Bids, reject a Bid not accompanied by a required bid security, good faith deposit, or by other data required by the Bid Documents, or reject a Bid which is in any way incomplete, irregular or otherwise not Responsive. The Owner may waive any formality in the bid requirements and award or not award the contract in the best interests of The School Board of Broward County, Florida. (Emphasis in original not shown) In addition to the foregoing, the bid documents contained detailed and specific design criteria that set forth information such as the slope of roofs, the roof spans, the mechanical systems, ventilation, plumbing, windows, and stoops. These design criteria covered hundreds of topics and encompassed virtually every facet of the structures. To review each bid proposal as to whether each design specification was met would require countless man-hours. The issue of how to review the bid proposals was not adequately anticipated by the Respondent. From the outset the bid document evolved from unusual circumstances. Whether the bid document was intended to be a request for proposals (RFP) or an invitation to bid (ITB) was a primary confusion among the Board's staff. If the proposals were to be deemed responsive or not and then ranked solely on price (thus making the bid process more like an ITB) how could staff effectively determine the threshold question of responsiveness? If the proposals were to be ranked based upon a point or qualitative approach (more like an RFP) where were the criteria by which to score the proposals? In fact, there were no objective criteria disclosed in the bid document by which a proposal could be evaluated. More curious is that no bidder brought this lack of evaluation criteria to the Board's attention during the mandatory bidder's conference. Moreover, no one challenged the bid specifications. Presumably, the bidders believed it was an "all or nothing" award. That is, if they were the lowest responsive bidder, they would receive the award. The question of who would be responsive and how that decision would be resolved did not come to light until after the bids had been opened. At the mandatory bidders' conference conducted on January 14, 2003, the bidders posed questions in the form of requests for information. In response, the Respondent issued six addenda intended to cover the questions posed. None of the responses addressed how the bid proposals would be evaluated. If anything, Addendum No. 3 added to confusion related to what documents must be submitted with the bid proposal. More specifically, Addendum No. 3 provided, in pertinent part: [Addendum 3, question and response to inquiry] 9. Can schematics be submitted with the bid instead of the signed and sealed architectural and engineering design drawings of the structures that are requested in Document Article 4.01.A.6? Response: Signed and Sealed Architectural/Structural Drawings are required to be submitted with the Bid. The Requirement for Mechanical and Electrical signed and sealed drawing is waived, however all engineering associated with the Relocatable Buildings will require engineer of record signed and sealed drawings and calculations prior to issuance of building permit DRC review. Nevertheless, when the bid proposals were opened on March 4, 2003, the Petitioners and the Intervenor were found to be the three lowest bidders. If responsive, the Intervenor would be considered the lowest bidder with the Petitioners being considered alternate vendors for the procurement. Unsatisfied with the preliminary determination that the Intervenor was the lowest bidder, the Petitioners timely challenged the bid award. The Petitioners maintained that the Intervenor had not timely provided sealed design drawings as required by the bid document. Petitioners argued that the Intervenor had attempted to impermissibly amend their proposal by late-filing a set of structural drawings for the bid. Thus the initial bid protest sought to determine what design drawings were required by the bid and whether the Intervenor had timely supplied such drawings. The Petitioners contended that the Intervenor's submittal should be rejected as non-responsive to the bid. Whether they had complied with the full dictates of the bid requirements was potentially at issue as well. While the initial bid protest was referred to the Division of Administrative Hearings and scheduled for formal hearing, the parties continued to attempt to resolve the issues. It was apparent that the bidders had not submitted identical proposals. How the proposed products had been compared and evaluated was difficult to determine. From the Respondent's committee members came the disclosure that the decision of determining whether the bidders had complied with the bid ultimately came from three fashioned questions. If the structure proposed was pre- engineered, relocatable to various sites, and suitable for educational purposes, the entry was deemed responsive. Based upon this assessment the Petitioners and the Intervenor were deemed responsive and their bids ranked based upon price. This approach did nothing to discern if the designs were comparable in quality, if they met the bid design criteria, or if the drawings were even sufficient to comply with the dictates of the bid. The first posting of the bid award for Group A1 was entered March 18, 2003. On March 21, 2003, the Petitioners timely filed their notices of intent to protest the award of Group A1 to the Intervenor. Thereafter they timely filed the petitions to protest the award and the initial protest was forwarded to the Division of Administrative Hearings. The protests did not encompass Group A2 or Group B. No bidder protested the proposed awards for Group A2 or Group B. In fact, the Respondent went forward on those procurements and awarded contracts for those groups on April 1, 2003. The Respondent did not award the contract award for the Group at issue in this proceeding. It must be noted that the instant procurement is not the Board's first experience with the procurement of concrete relocatable classrooms. In fact, the Board has purchased similar structures through a procurement contract that the Palm Beach County School Board holds with its vendors. One of the Respondent's concerns when the instant bids were reviewed was why the cost per unit for the bids in this case was higher than the Palm Beach County amount. As it turned out, the installation economy of multiple units at one site directly impacts the cost of the relocatable structures. Royal confirmed this information after the bids had been opened. When the Respondent's staff met with its counsel in preparation for the initial bid dispute (before the Board elected to reject all bids) the cost of the bid, the lack of full evaluation of the bidders' proposals, and the issues of the first protest were openly discussed. By that time any irregularities with the bid documents could not be repaired as to the contracts already awarded, but as to the instant matter the Respondent could revisit the circumstances and determine its best course. As a result of that reassessment, the Respondent elected to reject all bids regarding this group and attempt to re-bid the procurement with more certain terms. To that end on May 9, 2003, the Respondent issued a revised bid decision that provided in pertinent part: The Facilities and Construction Management Division intends to recommend that The School Board of Broward County, Florida, at the School Board meeting on June 3, 2003, reject all bids received for Group A1 and authorize revising the bidding documents and re-bidding. The rejection of all bids received for Group A1 is made due to serious flaws and ambiguities contained in Document 00200 4.01.A-6 as modified by Addendum No. 3. The Division intends to revise the bidding documents to delete the requirements that bidders submit plans with the bids; include ranges of unit quantities within the bid form; include one or more additional types of construction of the classroom buildings including a composite concrete/steel structure; and incorporate within the new Invitation to Bid all revised terms and conditions that were released through addenda in this procurement. The Petitioners timely filed protests regarding this new decision by the Board and the instant action ensued. By issuing the revised decision to reject all bids the Respondent intended to resolve all issues and to cure the perceived problem with the lack of consistent evaluation of the bidders' proposals. More specifically, the Respondent would be able to assure that the project design could comport with the specifications sought; specify whether architectural or engineering drawings were required and when (it was hoped that the confusion over "architect" vs. "engineer" could be eliminated); and obtain a substantial discount based upon economies from multi-unit purchases for a single site. None of the objectives sought were pre-textual or contrived. Additionally, by avoiding any process that would require a detailed reviewed of the bidders' proposals, countless man- hours could be saved.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the School Board of Broward County enter a Final Order affirming the decision to reject all bids in this matter. DONE AND ENTERED this 20th day of November 2003 in Tallahassee, Leon County, Florida. S ___________________________________ D. PARRISH Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 20th day of November 2003. COPIES FURNISHED: Dr. Franklin L. Till, Jr. Superintendent Broward County School Board 600 Southeast Third Avenue Fort Lauderdale, Florida 33301-3125 Daniel J. Woodring, General Counsel Department of Education 325 West Gaines Street 1244 Turlington Building Tallahassee, Florida 32399-0400 Usher Larry Brown, Esquire Brown, Salzman, Weiss & Garganese, P.A. 225 East Robinson Street, Suite 660 Orlando, Florida 32801 Steven L. Schwarzberg, Esquire Schwarzberg & Associates Esperante, Suite 210 222 Lakeview Avenue West Palm Beach, Florida 33401 Thomas R. Shahady, Esquire Adorno & Yoss, P.A. 350 East Las Olas Boulevard, Suite 1700 Fort Lauderdale, Florida 33301 Robert Paul Vignola, Esquire Broward County School Board C. Wright Administrative Building 600 Southeast Third Avenue, 11th Floor Fort Lauderdale, Florida 33301
Findings Of Fact Based upon the documentary evidence received and the entire record compiled herein, I hereby note the following findings of fact: Notice and Invitation to Bid on State Project Number 72001-3448 (the project) was extended to various contractors by the Respondent, Department of Transportation, on August 1, 1985. Sealed bids on the project were opened August 28, 1985. The scope of the project involved cleaning and painting the structural steel of the Buckman Bridge over the St. Johns River in Jacksonville, Florida. (State Bridge Numbers 720249 and 720343). The bids were opened and Petitioner was the apparent low bidder on the project with a bid amount of $193,000. The Department of Transportation, on October 2, 1985, rejected all bids "due to error in quantities in plans." According to the contract plans and specifications utilized by the Department of Transportation for the project, the beams, girders, bracing and trusses were composed of 2,540 tons of structural steel. The plans were in error and the tonnage of structural steel was less than 2,540 tons. Petitioner, upon visiting the job site as required, immediately recognized that there was less steel in the bridge than shown in the plans. In submitting and formulating his bid, the Petitioner considered the amount of work and materials which would actually be required to complete the project. 6 Prior to the bids being posted on the project, the Department of Transportation discovered that the amount of structural steel noted in the plans was grossly overestimated. On October 2, 1985, the Department of Transportation notified bidders in writing that all bids submitted on the project were rejected and that the plans would be revised and the project relet.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is, RECOMMENDED that the petition of Industrial Enterprise Sandblast and Painting, Inc., protesting the rejection of all bids on State Project No. 72001- 3448, be dismissed. DONE AND ORDERED this 11th day of December 1985 in Tallahassee, Florida. W. MATTHEW STEVENSON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of December 1985. APPENDIX Respondent's Findings of Fact FINDING RULING Accepted; see Recommended Order paragraph 1. Accepted; see Recommended Order paragraph 2. Accepted, but not included because subordinate. Accepted; see Recommended Order paragraph 4. Accepted; see Recommended Order paragraphs 3 and 6. Accepted; see Recommended Order paragraphs 3 and 6. Accepted; see Recommended Order paragraph 6. COPIES FURNISHED: HONORABLE THOMAS E. DRAWDY, SECRETARY DEPARTMENT OF TRANSPORTATION HAYDON BURNS BUILDING TALLAHASSEE, FLORIDA 32301 A. J. SPALLA, ESQUIRE GENERAL COUNSEL DEPARTMENT OF TRANSPORTATION 562 HAYDON BURNS BUILDING TALLAHASSEE, FLORIDA 32301 LARRY D. SCOTT, ESQUIRE DEPARTMENT OF TRANSPORTATION HAYDON BURNS BUILDING, M.S. 58 TALLAHASSEE, FLORIDA 32301-8064 INDUSTRIAL ENTERPRISE SANDBLAST & PAINTING, INC. P. O. BOX 1547 1502 FOX RUN DRIVE TARPON SPRINGS, FLORIDA 32486-1547
The Issue Whether Respondent acted contrary to the agency's governing statutes, rules or policies, or the bid specifications in its proposed decision to award Contract No. T1285 to Intervenor Kamminga & Roodvoets, Inc. ("K & R").
Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of the proceeding, the following findings of fact are made: On May 14, 2008, the Department released its bid solicitation for Contract T1285. The proposed contract was for the construction of a one-way pair through Lake Alfred, including new construction, reconstruction, milling and resurfacing, widening, drainage improvements, lighting, signalization, signing and pavement marking and landscaping on State Road 600 (U.S. 17/92). Polk County, the location of the project, lies in the Department's District 1. Qualified contractors, including Mid-State and K & R, received an electronic disk containing the solicitation, bid blank, plans and specifications for Contract T1285. The letting date for this project was June 18, 2008. Bids were to be submitted on or before that date via Bid Express, the electronic bidding system used by the Department. No party submitted a protest of the terms, conditions, and specifications contained in the solicitation pursuant to Subsection 120.57(3)(b), Florida Statutes. The work to be performed on Contract T1285 included the installation of limerock road base to be paid for in accordance with line item 0175, Optional Base Group 09 ("Base Group 09"). The bid documents included a set of "Supplemental Specifications." Section 6 of the Supplemental Specification was titled "Control of Materials." Subsection 6-3.3, titled "Construction Aggregates," provided as follows: "Aggregates used on Department projects must be in accordance with Florida Administrative Code Rule 14-103."2 Under the heading "Developmental Specifications" is a February 15, 2008, revision to the Construction Aggregates subsection that provides: Subarticle 6-3.3 (Page 54) is expanded by the following: 6-3.3.1 Department Directed Source for Aggregates: For this Contract, obtain aggregates for use in limerock base from the following vendor: Vulcan Construction Materials LP. Upon award of the Contract, provide the vendor and the Department a schedule of project aggregate needs. Once a schedule has been provided to both the Department and vendor, the Engineer will issue written authorization, with a copy to the vendor, for the purchase of aggregates from the vendor. This authorization is required before aggregates will be released by the vendor. Pick up the required aggregate such that the project schedule will be maintained. Payment to the vendor by the Contractor will be due upon receipt of the materials pursuant to the Department's Vendor Contract No. BDH50. This rate is the unit price agreed upon by the Department and the vendor and will be made available to bid proposal holders at the time of bid at http://www.dot.state.fl.us/construction/aggregate /aggregate.htm. The Department will make payment to the Contractor for the aggregates on progress estimates as a part of the bid unit price for the appropriate pay items. The rate is subject to change and adjustments for such changes will be made to the bid unit price of the appropriate pay items. Disputes with the vendor concerning aggregate supply will not be cause for Contract time adjustments, time suspensions or monetary adjustments to the Contract amount. The Contractor will be solely responsible for providing the necessary advance notice to the vendor and other coordination to obtain timely aggregate supply for the project. The import of Developmental Specification 6-3.3.1 was that all bidders would be required to obtain the limerock needed for Base Group 09 from a single vendor, Vulcan Construction Materials LP ("Vulcan"). The winning bidder would agree to pay Vulcan in accordance with a separate contract negotiated between Vulcan and the Department. The hyperlink provided in Developmental Specification 6-3.3.13 led to a document called "Aggregate Guidance" produced by the Department's State Construction Office. The front page of the Aggregate Guidance document contained "Bidder Information" consisting of a spreadsheet setting forth the Vulcan price per ton for limerock base and limestone coarse aggregate, with the price varying depending on the date and port of delivery. Between January and June 2008, the Vulcan price per ton for limerock base from both the Port of Tampa and Port Canaveral was $16.93. The Aggregate Guidance page contained additional hyperlinks with the following titles: "Aggregate Vendor Contract Usage," "Aggregate Vendor Contract," "Aggregate Vendor Projects List," "Aggregate Vendor Authorization Letter," "Aggregate Vendor Contract Frequently Asked Questions," and "Aggregate Price Adjustment Sheet." Alvin Mulford is the vice-president of Mid-State who, along with his estimator, put together his company's bid for Contract T1285. Mr. Mulford testified that his company has been bidding on Department work, and that he has never before seen a provision similar to Developmental Specification 6-3.3.1. Mr. Mulford directed his estimator to obtain clarification from the Department, to be sure that the bidders were required to purchase the limerock base from Vulcan. One reason for Mr. Mulford's concern was the "exorbitant" rate charged by Vulcan in comparison to other vendors. The restriction to a single supplier was so abnormal, and that supplier's rate was so out of line with the market, that Mr. Mulford decided to seek guidance from the Department through the question and response internet bulletin board provided by the Department for its projects. The question posed by Mid-State was as follows: Does the contractor have to use Vulcan materials for the limerock base at a rate of $16.93 per ton as stated in the Developmental Specifications 6-3.3.1? If so from which location is the material to be picked up? Is it also true that payment to the vendor (Vulcan Materials) will be due immediately upon receipt of the materials? I wanted to clarify this issue as it is unusual for the contractor to be limited to the use of only one vendor. The Department's response was as follows: The unit rate for the Material can be found at the following website: http://www.dot.state.fl.us/construction/ Aggregate/Aggregate.htm Pickup locations for the Material can be found at the following website: http://www.dot.state.fl.us/construction/ Aggregate/Aggregate.htm Payment should be issued by the Contractor to the Vendor (Vulcan Construction Materials LP) upon receipt of the materials as defined in Developmental Specification 6-3.3.1. Because the Department's response did no more than redirect him to the Department's website, Mr. Mulford decided to look at the website in more detail. He investigated the hyperlinks, including the Vulcan contract with the Department. When he clicked on the hyperlink titled "Aggregate Vendor Contract Usage," he found a document that provided as follows, in relevant part: Aggregate Vendor Contract Usage by Districts With the execution of the contract with Vulcan Construction Materials LP, contract number BDH50, Vulcan has committed to provide aggregate in the types and quantities defined in the contract (attached). The process for this contract in Districts 1, 5, and 7, is as follows: Include in the projects identified in the attached spreadsheet the appropriate special provision beginning with the July 2007 lettings. The District Specifications Engineer and District Construction Office will need to coordinate this effort. There are two special provisions for the purpose of notifying construction contract bidders of the Department's intention toward the aggregate. The first special provision is the mandatory version that will direct the bidder to obtain aggregates for the specified work from Vulcan. The second special provision provides the bidder an option to obtain its aggregates from Vulcan. * * * After these projects have been awarded, the contractor is required to notify FDOT and Vulcan a schedule of its aggregate needs for the project. After receiving this schedule, FDOT's Resident Engineer will issue written authorization to the contractor, with copy to Vulcan. This authorization is required before Vulcan will release aggregate to the contractor. Payment to Vulcan will be from the contractor. FDOT will pay cost of aggregate on progress estimates as part of the contractor's bid price for the work. The contractor is required to include in its bid price for the work the cost of the aggregate at the Vulcan rate. The Vulcan rate will be posted on the FDOT State Construction Website showing the rate. When adjustments are made to the Vulcan rate, FDOT will make adjustments in the construction contract unit price. . . . (Emphasis added.) Mr. Mulford testified that he understood the underscored language in the hyperlinked document to be a directive to the bidders and therefore a mandatory requirement of the bid specifications. He did not ask the Department for further clarification because he believed the requirement was clearly stated in the hyperlinked document. David Sadler, the director of the Department's office of construction, testified that the hyperlinked document was developed by his office to offer guidance to the districts as to the concept behind and use of the aggregate vendor contract. The document was not a part of the bid solicitation document. Mid-State's bid price was $7,429,398.44. Mid-State's price for Base Group 09 was $619,645.80, or $19.30 per square yard. This price reflected the Vulcan rate for limerock base of $16.92 plus tax and Mid-State's costs for the work associated with Base Group 09. 19. K & R's bid price was $7,370,505.24, or $58,893.20 lower than the bid price of Mid-State. K & R's price for Base Group 09 was $256,848.00, based on a stated unit price of $8.00 per square yard for limerock base. K & R's price for Base Group 09 was $362,797.80 lower than that of Mid-State, accounting for more than the differential between the overall bids of Mid-State and K & R. Marcus Tidey, Jr., K & R's vice president in charge of its Florida division, testified that K & R was well aware that the Vulcan price for limerock base was $16.93, and that K & R understands its obligation to pay that price to Vulcan should K & R be awarded Contract T1285. Mr. Tidey testified that at the time of bid submission, he cut K & R's bid price to $8.00 per square yard as a competitive strategy to win the contract. Mr. Tidey made a conscious decision that K & R would absorb the difference between $8.00 bid price and the Vulcan price of $16.93. Mr. Tidey testified that K & R needed to win this job in order not to have its crews and equipment sit idle during the economic downturn, and therefore decided to take all of its markup, roughly $250,000, out of the bid. He could have made the $250,000 cut on any item or items in the bid, but decided on Base Group 09 because the limerock base was a big item and therefore easy to cut by a large amount. Mr. Tidey also testified that the contract provides a $400,000 incentive payment for early completion of the job, meaning that K & R will be able to work "faster and smarter" and make up for the price reduction at the end of the job. Mr. Tidey testified that he obtained the Vulcan prices from the Department's website as instructed by Developmental Specification 6-3.3.1. He did not click on the hyperlinks, which appeared to reference the contract between the Department and Vulcan and therefore was of no concern to him. The Department and K & R dispute Mid-State's assertion that the underscored language of the hyperlink set forth in Finding of Fact 15 was a requirement of the bid specifications, based on Mr. Sadler's direct testimony and the underlying illogic and unfairness of requiring bidders to seek out hidden specifications. The Department and K & R concede that if the bid specifications did in fact require the bidders to include in Base Group 09 the full costs associated with obtaining the limerock base from Vulcan, then K & R's bid is nonresponsive. Developmental Specification 6-3.3.1 directed bidders to the Department's webpage for the purpose of obtaining the current Vulcan rate quote. It did not instruct the bidders to investigate the hyperlinks or to assume that the information contained therein was mandatory. Absent an instruction to bidders to review the information contained in the hyperlinks, the Department could not make such information mandatory without placing less curious bidders at a competitive disadvantage. The Department had no intent to play hide-and-seek with the bid specifications in the manner suggested by Mid-State. In addition, K & R points to three line items of the bid specifications in which the Department eliminates competition, instructing the bidders not to bid and inserting a fixed unit price and bid amount for all bidders as to those items. K & R reasonably asserts that the Department was fully capable of treating Base Group 09 in the same fashion, had it intended to require the bidders to pass through to the Department all the costs associated with obtaining the limerock base from Vulcan. However, the Department supplied the bid quantity (31,106 square yards) and left it to the bidders to determine the price per unit they would bid. K & R's bid was responsive. Nothing in the bid specifications prevented K & R from absorbing part of the cost of the Vulcan limerock base and passing the savings on to the Department, or required bidders to pass on to the Department the full costs of complying with the bid specifications regarding Base Group 09. The sole remaining issue is whether K & R's bid, though facially responsive, was materially unbalanced. The Department routinely conducts reviews of bid line items that appear "unbalanced," i.e., for which there appear to be significant differences between the price bid and the Department's cost estimate, in order to determine whether the price difference is due to a quantity error by the bidder. The Department's review confirms that the bid quantity specified on the bid blank is accurate. If a quantity error is found, the bids are recalculated using the bidders' unit prices and the correct quantities to determine whether the bid rankings would change. A bid for which there is a discrepancy between the bid and the Department's estimate is termed "mathematically unbalanced." A mathematically unbalanced bid that affects the ranking of the low bid is "materially unbalanced." A mathematically unbalanced bid is acceptable, but a materially unbalanced bid affords the bidder an unfair competitive advantage and must be rejected. The Department followed its usual procedure in analyzing the K & R bid to determine whether it was unbalanced. Philip Gregory Davis, the Department's state estimates engineer, testified that there were some unbalanced items in the K & R bid, but no quantity errors that would have changed the ranking of the bids. Richard Ryals, the project designer who conducted the unbalanced bid review, testified that the quantities were correct for Base Group 09. As noted above, K & R's low bid for Base Group 09 was an intentional strategy, not the result of a quantity error. K & R's current bonded capacity qualification with the Department is $258 million in contracts at any one time. K & R posted a bid bond, and has more than enough capacity to comfortably perform this contract. There is no economic danger to the Department in accepting K & R's low bid.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that the Department of Transportation enter a final order dismissing Mid-State's formal written protest and awarding Contract T1265 to K & R. DONE AND ENTERED this 9th day of January, 2009, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th day of January, 2009.
The Issue Whether the Petitioner was the lowest responsive bidder in Lease No. 590:1975, and therefore entitled to the contract award.
Findings Of Fact In 1988, the Department made the determination that it would not exercise its option on leased space owned by the Petitioner Dyess, in Clewiston, Florida. Bid documents were prepared by the agency for its current office space needs. Bid proposals were solicited through newspaper advertisements and personal contact with owners, developers, and realtors within the Clewiston area. The Department included Dyess in its solicitations. He was sent an Invitation to Bid for Existing Facilities by the Department. This bid package contained all of the bid documents for the bid referred to as Lease Number 590:1975. The Invitation to Bid was issued by the Department for approximately 7,962 square feet of net rentable office space in Clewiston, Florida. The invitation was prepared using HRS Facilities Form R01-87. The form used by the Department for soliciting and accepting competitive proposals for the leased space was required to comply with all conditions and requirements adopted by the Department of General Services, as set forth in Rule 13M-1.015(3)(e), Florida Administrative Code. The Department of General Services is the agency which administers real property leasing for the State of Florida for leased space of 2,000 square feet or more in privately owned buildings. During the bidders' conference held on April 26, 1988, Mr. Michael J. Sedgwick, the agency's representative, was questioned about the agency's interpretation of the term "dry and capable of being physically measured" which is set forth on page two of the Invitation to Bid and page three of the Bid Submittal Form. Page two of the Invitation to Bid is a glossary which defines various terms used within the bid documents. The term "existing building" is defined as follows: To be considered as existing, the entire space being bid must be dry and capable of being physically measured to determine net rental square footage at the time of the bid submittal. Paragraph 10 on page three of the Bid Submittal Form reiterates the definition of an "existing building" as set forth in the Invitation to Bid. The language in the bid documents which defines the term "existing building" is identical to the language in Form BPN 4136, which has been promulgated as a rule by the Department of General Services as the format for specifications for the solicitation of leased spaces by the State of Florida. In response to the request for an interpretation, Mr. Sedgwick contacted Mr. George Smith, who administers the leasing program for the Department in Tallahassee, and obtained the following definition: "Dry and measurable" consists of four things: a slab, four corners, a roof, and a valid building permit if construction is in progress. The definition given by Mr. Smith was verbally communicated to the prospective bidders who attended the conference. This definition was verbally communicated to the Petitioner by Mr. Sedgwick on April 27, 1988. The Petitioner timely submitted a bid in Lease Number 590:1975 on the Department's Bid submittal Form by May 24, 1988. On page three of this form, each bidder was required to acknowledge the bid requirements contained on that page by placing his initials in the bottom right hand corner. The Petitioner Dyess acknowledged the requirement that the proposed space must be an "existing building" at the time of the bid submittal. On May 24, 1988, the date of the bid opening, Petitioner's building did not meet the requirements of an existing building as defined within the bid documents or the Department's verbal clarification of the definition. The building did not have a roof, a slab, or a valid building permit. After the bids were opened, the District VIII Bid Evaluation Committee visited each of the proposed lease locations. When the Petitioner's proposed location was reviewed by the committee two days after the close of bids, the addition was found to consist of the following: two partially completed block walls which connected the two existing buildings. The existing buildings were still intact, but it was apparent that an expansion was taking place, and that the completed project would be one building. A slab had not yet been poured in the addition, and it was without a roof. The plans submitted to the Department with the Petitioner's bid suggested that this expansion was capable of producing the square footage required by the Department. The City of Clewiston was aware of the Petitioner's expansion project, but he was not required by this authority to have a building permit at the time the project was viewed by the committee and evaluated by the Department. The Petitioner's bid was rejected by the Department because, on the date of the bid submittal, the proposed addition was not an "existing building" as defined by the bid documents and the further verbal interpretation by the agency. The bid submitted by the Intervenor Tibbetts did not contain the complete contract for the purchase of the property. However, the right to purchase was evidenced by a document submitted with the bid. Full Disclosure Statements of Ownership are not required under Rule 13N-1.015, Florida Administrative Code, until after a bid is awarded. The property was not properly zoned at the time of the Intervenor Tibbetts' bid submittal.
The Issue The issues in this protest are whether Respondent's intended action——i.e., deeming Petitioner's application ineligible for funding on the grounds that the amount of capital the applicant's equity proposal states will be invested during construction is insufficient to cover development costs——is contrary to governing statutes, administrative rules, or the specifications of the solicitation; and, if so, whether this erroneous action is contrary to competition, clearly erroneous, or arbitrary or capricious.
Findings Of Fact FHFC is the housing credit agency for the state of Florida whose responsibilities include the awarding of low- income housing tax credits, which developers use to finance the construction of affordable housing. Tax credits are distributed pursuant to a competitive process similar to a public procurement that starts with FHFC's issuance of a request for applications.1/ On January 9, 2019, FHFC issued Request for Applications 2019-105 (the "RFA"). Eighteen applications were submitted in response to the RFA on February 6, 2019. A Review Committee was appointed to evaluate the applications and make recommendations to FHFC's Board of Directors (the "Board"). Pursuant to the ranking and selection process outlined in the RFA, applicants were evaluated on eligibility items and were awarded points for other items. Florida Administrative Code Rule 67-60.006 provides that "[t]he failure of an Applicant to supply required information in connection with any competitive solicitation . . . shall be grounds for a determination of nonresponsiveness with respect to its Application. If a determination of nonresponsiveness is made by [FHFC], the Application shall be considered ineligible." The RFA sets forth a list of mandatory Eligibility and Point Items that must be included in a response. The RFA expressly provides that "[o]nly Applications that meet all of the Eligibility Items will be eligible for funding and considered for funding selection." As an Eligibility Item, each applicant was required to submit, as part of its application, a Development Cost Pro Forma detailing both the anticipated costs of the proposed development, as well as the anticipated funding sources for the proposed development. In order to demonstrate adequate funding, the Total Construction Sources (including equity proceeds/capital contributions and loans) as shown in the pro forma must equal or exceed the Total Development Costs reflected therein. During the scoring process, if a funding source is not considered or is adjusted downward, then Total Development Costs might wind up exceeding Total Construction Sources, in which event the applicant is said to suffer from a construction funding shortfall (deficit). If an applicant has a funding shortfall, it is ineligible for funding. The Development Cost Pro Forma does not allow applicants to include in their Total Construction Sources any equity proceeds to be paid after construction completion. Instead, the applicant must state only the amount of "Equity Proceeds Paid Prior to Completion of Construction." The pro forma defines "Prior to Completion of Construction" as "Prior to Receipt of a Final Certificate of Occupancy." The RFA requires, as well, that an equity proposal letter be included as an attachment to the application. For a housing credit equity proposal to be counted as a source of financing, it must meet the following criteria: Be executed by the equity provider; Include specific reference to the Applicant as the beneficiary of the equity proceeds; State the proposed amount of equity to be paid prior to construction completion; State the anticipated Eligible Housing Credit Request Amount; State the anticipated dollar amount of Housing Credit allocation to be purchased; and State the anticipated total amount of equity to be provided. (Emphasis added). The Review Committee found 14 applications eligible and four applications ineligible, including the Vistas application. Two applications were recommended for funding: Lincoln Village Apartments and Winchester Place. At a meeting on March 22, 2019, the Board approved the Review Committee's eligibility and funding recommendations. In its application, Vistas requested an allocation of $1,325,000 in housing credits. In formulating its intended action on the RFA, FHFC determined that Vistas is not eligible for an award of housing credits for failing to state in its application that an amount of equity sufficient to cover the anticipated development costs would be invested in the project prior to construction completion. Vistas protests this determination of ineligibility. Due to the limited availability of credits and Vistas' position in the ranking, Winchester Place, a putatively successful applicant, would end up being deselected if FHFC's final agency action were to find Vistas eligible. Thus, Winchester Place has intervened in this proceeding to defend the intended agency action. As Attachment 14 to its application, Vistas submitted an equity proposal letter from RBC Capital Markets ("RBC") executed by David J. Urban (the "Equity Proposal"). In relevant part, the Equity Proposal states: Anticipated Total Equity to be provided: $12,586,241* Equity Proceeds Paid Prior to or simultaneous to closing the construction financing: $2,013,799* (min. 15%) Equity Proceeds to be Paid Prior to Construction Completion: $7,048,295 Pay-In Schedule: Funds available for Capital Contributions #1: $2,013,799* be paid prior to or simultaneously with the closing of the construction financing. Funds available for Capital Contribution #2 $1,887,936* prior to construction completion. Funds available for Capital Contribution #3 $3,146,560* concurrent with permanent loan closing. Equity Proceeds Paid at Lease Up $4,405,184* Equity Proceeds Paid at 8609 $1,132,762* *All numbers rounded to nearest dollar. The Pay-In Schedule in the Equity Proposal refers to "permanent loan closing" as the moment when Capital Contribution #3 will be made "available." The Equity Proposal does not, however, define or discuss permanent loan closing, and, to the point, does not specify when it is expected to occur. Of potential relevance in this regard is a letter from JP Morgan Chase Bank, N.A. (the "Chase Letter"), which is included as Attachment 15 to Vistas' application. Unlike the Equity Proposal, the Chase Letter, if not the last word on the subject, at least sheds some light on the timing of the crucial milestone, i.e., "permanent loan closing." Although the Chase Letter is full of escape clauses and does "not represent a commitment" or "an offer to commit," the document nevertheless outlines the terms for the closing of the proposed construction and permanent loans. The proposed terms call for the payment of a $10,000 Conversion Fee at permanent loan closing and impose preconditions for the conversion from the construction loan to the permanent loan, which include a requirement that there have been "90% economic and physical occupancy for 90 days." No evidence was presented as to the meaning of this language, but the term "physical occupancy" is clear and unambiguous——and it plainly happens after receipt of a final certificate of occupancy, which, under the RFA, is the end point of the construction phase. Winchester Place argues that the Pay-In Schedule casts doubt on whether the entire amount stated in the Equity Proposal's line-item entry for "Equity Proceeds to be Paid Prior to Construction Completion" ($7,048,295) will be paid before the final certificate of occupancy is issued. According to Winchester Place, the Pay-In Schedule shows that the third capital contribution will be paid after construction completion because the second capital contribution, which is the earlier of the two, is due to occur "prior to construction completion." Thus, Winchester Place contends that Vistas' construction financing sources should be reduced by $3,146,560, thereby creating a construction financing shortfall and rendering the Vistas application ineligible for funding. Winchester Place's argument supports FHFC's intended action but is opposed by FHFC in this proceeding. This turnabout on the part of FHFC is the result of FHFC's intended acceptance, as eligible, of the application that Fountains at King's Pointe Limited Partnership ("Fountains") submitted in response to Request for Applications 2018-110 ("RFA 2018-110"). That proposed agency action is relevant because Fountains had attached to its application an equity proposal letter from RBC whose terms and conditions——other than the dollar amounts and (obviously) the applicant's name——are identical to those of the Equity Proposal for Vistas. During the evaluation of applications under RFA 2018-110, which took place at around the same time as the review of applications pursuant to the RFA at issue here, FHFC's scorer determined that Capital Contribution #3 should be included in the amount of equity proceeds to be paid to Fountains prior to construction completion, with the result that Fountains' application, showing a construction funding surplus, was deemed eligible for funding. The Vistas and Fountains applications, competing in separate solicitations, were scored by different FHFC staff members. The evaluator who scored the financial section of Vistas' application sought advice concerning her interpretation of the Equity Proposal, discussing the matter with FHFC's Director of Multifamily Programs and legal counsel at a reconciliation meeting that occurred before the Review Committee convened; this evaluator encountered no resistance to her plan of making a downward adjustment to Vistas' equity funding. The evaluator of the Fountains application did not likewise discuss her scoring rationale and thus received no input or guidance from FHFC's management. Ultimately, however, because each scoring determination belongs to the Review Committee member herself or himself, inconsistent or conflicting results are possible, as these cases demonstrate. Once in litigation, FHFC discovered that it had reached opposite scoring conclusions based on the same material facts. In this proceeding and in the 2018-110 Protests, FHFC has stressed its desire to take a consistent approach to the identical Equity Proposals. To that end, FHFC has reversed course here and argued that, contrary to its intended action, the Equity Proposal provided by Vistas fully satisfies the requirements of RFA; there is no funding shortfall; and Vistas' application is eligible and should be selected for funding. Deeming Vistas' application eligible would achieve consistency, of course, by giving favorable treatment to the applications of both Fountains and Vistas, which are similarly situated as to the Equity Proposal. Naturally, Winchester Place urges that consistency be found the other way around, through the rejection of both applications, or, alternatively, that the inconsistency be tolerated as the price of affording the agency wide discretion in making scoring decisions. In support of its decision to change positions on Vistas' Equity Proposal, FHFC relies upon the following premises: (i) the Equity Proposal plainly specifies, in the line-item entry for "Equity Proceeds to be Paid Prior to Construction Completion," the amount to be paid prior to construction completion; (ii) permanent loan closing does not necessarily have to occur after construction completion; and (iii) the information contained in the Pay-In Schedule is not information that is required by the RFA. The disputes arising from the scoring of the Equity Proposal are solvable as matters of law and therefore will be addressed below.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Florida Housing Finance Corporation enter a final order fully implementing its intended action, as no basis for reversal has been established in this proceeding. DONE AND ENTERED this 16th day of July, 2019, in Tallahassee, Leon County, Florida. S JOHN G. VAN LANINGHAM Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 16th day of July, 2019.
The Issue The issue in this cause is whether costs and attorney's fees are due Petitioner, hereinafter PROCTOR, from Respondent, hereinafter HRS, pursuant to Section 57.111, Florida Statutes, as a result of Division of Administrative Hearings Case Number 91-5963-BID, and, if so, the amount of costs and fees.
Findings Of Fact The petition for fees and costs herein is brought exclusively under Section 57.111, Florida Statutes, and relates back to a bid protest wherein PROCTOR and TCC #3 LTD., INC., hereafter TCC, were the only bidders on HRS lease 590.236. PROCTOR was the protestant/Petitioner and TCC was the apparent successful bidder/Intervenor in Derick Proctor v. Department of Health and Rehabilitative Services, DOAH Case No. 91-5963BID. HRS' Invitation to Bid (ITB) for lease 590:236 required bidders to submit evidence of control of the property being offered, including the parking areas. Evidence of control could take the form of a deed for the property, an option to purchase the property, or a lease or option to lease showing a right to sublease. TCC did not submit a document labelled "deed," "option to purchase," "lease," or "option to lease" with its bid. TCC submitted as its evidence of control a contract for sale and purchase of the property with Hernando Plaza, Ltd., executed by Edward M. Strawgate and Harold Brown representing themselves to be general partners of the limited partnership. At all times material, the actual record title of the property submitted by TCC for the bid was in the Victor and Lillian Brown Foundation. At the times of the bid opening, evaluation, and August 27, 1991 notice of intended award, HRS had no reliable information as to what entity actually owned the property offered by TCC, and TCC had not disclosed to HRS that its contract to purchase the property was with an entity other than the record owner. Up to then, at least, Hernando Plaza, Ltd. had represented itself to TCC as being the owner of the property. The ITB did not require an abstract of title to be submitted with the bid. HRS normally does not require an abstract from successful bidders, although the ITB contained provisions for future disclosures from successful bidders. Absent some reason to "go behind" facial evidence of control, HRS' ITB attempted at the time to protect HRS by requiring successful bidders to post an irrevocable letter of credit to be forfeited in the event a successful bidder could not perform and for future disclosures concerning the chain of title. (See the recommended order in the underlying case). HRS accepted the contract to purchase the property from Hernando Plaza, Ltd. as TCC's required evidence of control, believing it to constitute an option to purchase. (See Findings of Fact 15-17 infra, this final order). On August 27, 1991, PROCTOR received from HRS a notice of intent to award the bid to TCC. This notice constituted the "window" for protests, if any, to be filed. PROCTOR then timely filed a notice of intent to protest and a formal written protest of the award to TCC. The filing of this protest resulted in an automatic suspension of the bid solicitation and contract award process and referral of the matter to the Division of Administrative Hearings, pursuant to Section 120.53(5)(c), Florida Statutes. This protest formed the basis of the underlying bid case, DOAH Case No. 91-5963BID. No later than the time of the Prehearing Order of September 23, 1991 in Case No. 91-5963BID, the law firm of Gibbs and Rudzik had made known to the hearing officer and counsel for both PROCTOR and HRS its retention as counsel for TCC. TCC moved for leave to intervene in a motion filed September 30, 1991, which was granted in an order of October 4, 1991. In a letter of October 10, 1991, counsel for PROCTOR made counsel for HRS aware of a question of whether TCC could obtain good title to the property. Counsel for PROCTOR proposed in a letter of October 14, 1991 to counsel for HRS that HRS reject both PROCTOR's and TCC's bids and rebid the lease, but this letter was primarily devoted to determining if HRS wished to interpose a new defense that PROCTOR's bid was unresponsive. In the instant fees and costs case, PROCTOR relies on its October 14, 1991 letter as the point from which HRS should have acted to avoid incurring attorney's fees and costs. After the receipt of the two letters, HRS did not reject both bids and rebid the contract but proceeded to formal hearing on October 30, 1991. PROCTOR and HRS share the mutual impression that had HRS accepted PROCTOR's proposal to reject both bids, HRS would have to have allowed TCC an opportunity to protest that decision. At the final hearing in Case No. 91-5963BID, evidence was offered that Hernando Plaza, Ltd. had a conditional option to purchase the property from the record title owner, the Brown Foundation. However, it was not established at the hearing that the conditions of the option had been fulfilled or that TCC or Hernando Plaza, Ltd. could otherwise gain good title to the property through a valid option. It was concluded as a matter of law in Case No. 91-5963BID, that on its face, the ITB stated that control could be evidenced merely by attachment of an "option to purchase," that the ITB stated no further requirements concerning the internal provisions of the option to purchase, and that TCC's conditional contract for purchase constituted a conditional option to purchase. The conditions of the option to purchase and the chain of title, among myriad other matters were subjects of proof at the formal hearing. The conditions of the option to purchase and various complicated real property concepts arising from recorded and unrecorded parts of the chain of title constituted the thrust of the recommended order's assessment that TCC's "control" was speculative only. It is here noted that the totality of the "chain" of title might have been unavailable even by "abstract" due to the lack of recordation of some documents. The lengthy formal hearing adduced evidence concerning the factual issue of whether or not the conditional option to purchase was between TCC and an entity which had such a sufficiently unequivocal interest in the proposed property that it could convey title to TCC in time for TCC to fulfill its obligations under its proposed lease to HRS. There is no evidence that HRS knew of these problems on August 27, 1991, when it gave notice of its intent to award the bid to TCC. Hernando Plaza, Ltd. was the entity with which TCC had contracted. At formal hearing, TCC relied on the legal concept that all interests in the property had merged in the non-title holder, Hernando Plaza, Ltd. This concept, together with recorded and unrecorded elements in the chain of title which were presented at formal hearing, were determined in the recommended order to be too "speculative" on the issue of TCC's control. However, it was also found, upon evidence submitted at formal hearing, that TCC's bid contained no other material deviations from the requirements of the ITB, that the signator of TCC's bid had sufficient status to submit the bid for the TCC corporation, and that TCC's signator could not submit the bid as an agent of the owners of the real property. TCC and its bid signator had never purported to have submitted the bid on behalf of the owners of the real property. (See the recommended order of the underlying bid case.) These issues were raised by PROCTOR and they addressed more than just the facial compliance of TCC's original bid documents which was all HRS had to consider when it made its initial decision in favor of TCC and against PROCTOR. However, the recommended order found HRS to have materially deviated in a number of ways from the bid process in its initial evaluation of PROCTOR's bid, not the least of which was determining that PROCTOR had complied with the ITB requirements for demonstrating control. All such evaluation flaws had been committed by HRS in favor of PROCTOR. Both TCC's and PROCTOR's bids were ultimately found to be unresponsive in the recommended order entered on December 20, 1991. The recommended order also found both had standing to be involved in the bid protest and formal hearing. The recommended order recommended rejecting both bids and readvertising the ITB. The Final Order of HRS entered on January 20, 1992 dismissed PROCTOR's protest on the basis that he lacked standing to protest, as his bid was unresponsive, and awarded the bid to TCC. HRS did not give PROCTOR notice that his bid was not responsive until it issued its Final Order. The Final Order of HRS was appealed to the First District Court of Appeals by PROCTOR. The First District Court of Appeals entered an order on June 22, 1992 finding PROCTOR had standing and remanding the case back to HRS for the purpose of a decision of the issue of whether TCC's bid was also unresponsive. On July 27, 1992, HRS entered its Amended Final Order determining both bids to be unresponsive and that the lease should be relet for bids. The First District Court of Appeals affirmed the Amended Final Order of HRS in a per curiam opinion without discussion on October 13, 1992. HRS did not reject both bids and rebid the contract until after this per curiam opinion. No motion for rehearing was filed with respect to either of the First District Court of Appeals' orders entered June 22 or October 13, 1992, nor was any notice to invoke the discretionary jurisdiction of the Supreme Court filed. PROCTOR did file a motion for rehearing solely on the court's denial of PROCTOR's motion for appellate fees. Mandate was issued by the Clerk of the First District Court of Appeals on December 3, 1992. HRS entered an Order Directing Release of Bid Protest Cost Bond on December 18, 1992, in which HRS stated: Petitioner, Derick Proctor, has prevailed in the above styled bid protest. Petitioner's domicile and principal place of business is Vero Beach, Florida. Petitioner has one employee. Petitioner is a sole proprietorship. Petitioner's net worth does not exceed $2,000,000.00. HRS was not a nominal party in the underlying bid case. HRS did not initially challenge PROCTOR's "small business party" status in this instant fees and costs proceeding. Therefore, that allegation of the fees and costs petition is not at issue. Also, Petitioner's "small business party" status is now stipulated to exist. The parties have stipulated that the maximum statutory fee is $15,000.00 and that $15,000.00 is a reasonable fee if an award of attorney's fees is due. HRS has not protested or objected to the amount of costs claimed, $411.25, if costs are due.
The Issue Whether Respondent's intended rejection of all bids submitted in response to Respondent's solicitation of bids for two separate painting projects (the painting of the exterior of Greenacres Elementary School and the painting of the exterior of South Olive Elementary School) is "arbitrary," as alleged by Petitioner, and if so, what alternative action should Respondent take with respect to these two projects.
Findings Of Fact Based on the evidence adduced at hearing, and the record as a whole, the following findings of fact are made: Respondent is a district school board responsible for the operation, control and supervision of all public schools (grades K through 12) in Palm Beach County, Florida (including, among others, Greenacres Elementary School, South Olive Elementary School, and Belvedere Elementary School) and for otherwise providing public instruction to school-aged children in the county. In or around August 2009, Respondent, through its Construction Purchasing Department (Purchasing Department), issued a single Invitation to Bid (ITB) soliciting separate bids for three different painting projects: the painting of the exterior of Greenacres Elementary School; the painting of the exterior of South Olive Elementary School; and the painting of the exterior of Belvedere Elementary School. The bid package contained the following: an Invitation to Bid Bidder Acknowledgement form (PBSD 1186, Rev 2/2001); Special Conditions; Specifications; and Addenda, including a Bid Summary Sheet, a Drug-Free Workplace Certification (PBSD 0580, New 3/91), a Statement of No Bid, Inspection forms, and a Beneficial Interest and Disclosure of Ownership Affidavit. The Invitation to Bid Bidder Acknowledgement form contained the following provision entitled, "Awards": AWARDS: In the best interest of the District, the Purchasing Department reserves the right to reject any and all bids and to waive any irregularity or minor technicalities in bids received; to accept any item or group of items unless qualified by bidder; to acquire additional quantities at prices quoted on this invitation unless additional quantities are not acceptable, in which case the bid sheets must be noted "BID IS FOR SPECIFIED QUANTITY ONLY." All awards made as result of this bid shall conform to applicable Florida Statutes. The Invitation to Bid Bidder Acknowledgement form also included "General Conditions, Instructions and Information for Bidders" (General Conditions), among which were the following: SEALED BIDS: One copy of this executed Invitation to Bid page and Bid Summary page(s) must be returned with the bid in order to be considered for award. All bids are subject to all the conditions specified herein; all General Conditions, Special Conditions on the attached bid documents; and any addenda issued thereto. Any failure on the part of the bidder to comply with the specifications, terms and conditions of this Invitation to Bid shall be reason for termination of contract. EXECUTION OF BID: Bid must contain a manual signature of an authorized representative in the space provided above. Failure to properly sign proposal shall invalidate same, and it shall not be considered for award. All bids must be completed in ink or typewritten. Corrections must be initialed by the person signing the bid. Any corrections not initialed will not be tabulated. The original bid conditions and specifications cannot be changed or altered in any way. Altered bids may not be considered. Clarification of bids submitted shall be in letter form, signed by the bidders and attached to the bid. * * * 20. SIGNED BID CONSIDERED AN OFFER: This signed bid shall be considered an offer on the part of the bidder, which offer shall be deemed accepted upon approval by the Board. In case of a default on the part of the bidder after such acceptance, the District may take such action as it deems appropriate including legal action for damages or specific performance. * * * 25. SPECIAL CONDITIONS: Any and all Special Conditions that may vary from these General Conditions shall have precedence. Among the "Special Conditions" were the following: SCOPE: The purpose and intent of this invitation to bid is to secure firm pricing for Exterior Painting of Greenacres, South Olive, and Belvedere Elementary Schools. The rate shall include all materials and labor for preparation, sealing and painting. AWARD: Time of completion is of the essence. Contract will be awarded to the lowest responsive and responsible bidder(s) for each item as listed on the Bid Summary Sheet. The District reserves the right to use the next lowest bidder(s) in the event the original awardee of the bid cannot fulfill their contract. The next lowest bidder's price must remain the same as originally bid and must remain firm for the duration of the contract. The anticipated award will be approved by the superintendent designee. B. MANDATORY SITE INSPECTION: ALL BIDDERS MUST ATTEND PRE-BID WORKSITE WALK-THROUGH. THE WORK DETAILS ARE OUTLINED IN THIS BID AND ANY QUESTIONS WILL BE ANSWERED AT EACH WORKSITE INSPECTION. BIDS WILL NOT BE ACCEPTED FROM ANY BIDDERS THAT HAVE NOT ATTENDED THE SITE INSPECTION FOR THAT PARTICULAR WORKSITE. THIS MANDATORY SITE INSPECTION EXCLUDES ANY AND ALL PAINT MANUFACTURERS AND/OR PAINT DISTRIBUTORS. * * * BIDDERS RESPONSIBILITY: Before submitting their bid, each bidder is required to carefully examine the invitation to bid specifications and to completely familiarize themselves with all of the terms and conditions that are contained within this bid. Ignorance on the part of the bidder will in no way relieve them of any of the obligations and responsibilities that are part of this bid. SEALED BID REQUIREMENTS: The "INVITATION TO BID" bidder's acknowledgment sheet must be completed, signed, and returned. In addition, the Bid Summary Sheet page(s) on which the bidder actually submits a bid, needs to be executed and submitted with this bid. Bids received that fail to comply with these requirements shall not be considered for award.[2] CONTRACT: The submission of your bid constitutes an offer by the bidder. . . . * * * Q. USE OF OTHER CONTRACTS: The District reserves the right . . . to directly negotiate/purchase per School Board policy and/or State Board Rule 6A-1.012(6) in lieu of any offer received or award made as a result of this bid, if it is in its best interest to do so. The District also reserves the right to separately bid any single order or to purchase any item on this bid if it is in its best interest to do so. * * * HH. POSTING OF BID AND SPECIFICATIONS: Invitation to bid with specifications will be posted for review by interested parties in the Construction Purchasing Department on the date of bid electronic mailing and will remain posted for a period of 72 hours. Failure to file a specification protest within the time prescribed in § 120.57(3), Florida Statutes, will constitute a waiver of proceedings under Chapter 120, Florida Statutes, and applicable Board rules, regulations and policies. II. POSTING OF BID RECOMMENDATION/ TABULATIONS: Bid recommendations and tabulations will be posted in the Construction Purchasing Department, within 10 days of the opening date, and will remain posted for a period of 72 hours. If the bid tabulation with recommended awards is not posted by said date and time, [a] "Notice of Delay of Posting" will be posted to inform all proposers of the new posting date and time. Any person adversely affected by the decision or intended decision must file a notice of protest, in writing, within 72 hours after the posting. The formal written protest shall state with particularity the facts and law upon which the protest is based. Failure to file a specification protest within the time prescribed in § 120.57(3), Florida Statutes, will constitute a waiver of proceedings under Chapter 120, Florida Statutes, and applicable Board rules, regulations and policies. OO. BID PROTEST: If a bidder wishes to protest a bid, they must do so in strict accordance with the procedures outlined in F.S. 120.57(3), and Section FF., Lobbying Paragraph 3, of this proposal and School Board Policy 6.14. Any person who files an action protesting bid specifications, a decision or intended decision pertaining to this bid pursuant to F.S. 120.57(3)(b), shall post with the Purchasing Department, at the time of filing the formal written protest, a bond secured by an acceptable surety company in Florida payable to the School District of Palm Beach County in an amount equal to 1 percent (1%) of the total estimated contract value, but not less than $500 nor more than $5,000. Bond shall be conditioned upon the payment of all costs that may adjudged against the protester in the administrative hearing in which the action is brought and in any subsequent appellate court proceeding. In lieu of a bond, a cashier's check, certified bank check, bank certified company check or money order will be acceptable form of security. If, after completion of the administrative hearing process and any appellate court proceedings, the District prevails, it shall recover all costs and charges included in the final order of judgment, including charges by the Division of Administrative Hearings. Upon payment of such costs and charges by the protester, the protest security shall be returned. If the protest prevails, he or she shall recover from the District all costs and charges, which shall be included in the final order of judgment. Failure to file a specification protest within the time prescribed in § 120.57(3), Florida Statutes, will constitute a waiver of proceedings under Chapter 120, Florida Statutes, and applicable Board rules, regulations and policies. * * * PP. INFORMATION: Any questions by the prospective bidders concerning this invitation to bid should be addressed to Helen R. Stokes, Purchasing Agent, Construction Purchasing . . . , who is authorized only to direct the attention of prospective bidders to various portions of the bid so they may read and interpret such for themselves. Neither Mrs. Stokes nor any employee of the District is authorized to interpret any portion of the bid or give information as the requirements of the bid in addition to that contained in the written bid document. Interpretations of the bid or additional information as to its requirements, where necessary, will be communicated to bidders by written addendum. Site visits to the three schools to be painted were made by prospective bidders on August 13, 2009, following which a First and Final Addendum, dated August 25, 2009, was issued by the School Board. This First and Final Addendum included the following Revised Bid Summary Sheet: REVISED BID SUMMARY SHEET THE SCHOOL DISTRICT OF PALM BEACH COUNTY Construction Purchasing Department 3661 Interstate Park Road North Building 200 Riviera Beach, FL 33404 Ph: 561-882-1952 Fax: 561-434-8655 EXTERIOR PAINTING OF GREENACRES, SOUTH OLIVE, AND BELVEDERE ELEMENTARY SCHOOLS SEALED BIDS ARE TO BE SUBMITTED ON AUGUST 27, 2009 NO LATER THAN 2:00 P.M. TO: Helen Stokes, Construction Purchasing Construction Purchasing Department 3661 Interstate Park Road North Building 200 Riviera Beach, FL 33404 Bids will only be accepted from those contractors in attendance at the Mandatory Site Visit and who are registered with the School District of Palm Beach County as a Small Business Enterprise. The rate shall include paint, preparation, sealing and painting per the attached specifications and detailed scope of work. EXTERIOR PAINTING AT GREENACRES, SOUTH OLIVE, AND BELVEDERE ELEMENTARY SCHOOLS ITEM 1: GREENACRES ELEMENTARY SCHOOL TOTAL $ (PRICE IN WORDS) ITEM 2: SOUTH OLIVE ELEMENTARY SCHOOL TOTAL $ (PRICE IN WORDS) ITEM 3: BELVEDERE ELEMENTARY SCHOOL TOTAL $ (PRICE IN WORDS) RE-TEXTURING TEXCOAT $ (Per Sq. Ft.) ADDENDUM ACKNOWLEDGEMENT: I HEREBY ACKNOWLEDGE RECEIPT OF ADDENDUMS CONTRACTOR: Name Date Address Current License # City, State, Email Address Zip Phone Fax There were no instructions on the Revised Bid Summary Sheet itself directing that an authorized representative sign the document, nor was there any signature line for such purpose. Bids were submitted by Austro Construction, Inc. (Austro); Dynamic Painting, Inc. (Dynamic); Fleischer's, Inc. (Fleischer's); JIJ Construction Corporation (JIJ); and Petitioner. Austro bid $83,900.00 on Item 1 (Greenacres Elementary School); $87,500.00 on Item 2 (South Olive Elementary School); and $105,500.00 and $3.50 per square foot for re-texturing on Item 3 (Belvedere Elementary School). Dynamic bid $55,955.00 on Item 1 (Greenacres Elementary School); $74,800.00 on Item 2 (South Olive Elementary School); and $82,900.00 and $3.00 per square foot for re- texturing on Item 3 (Belvedere Elementary School). Fleischer's bid only on Item 3 (Belvedere Elementary School).3 Its bid was $73,000.00 and $1.25 for re-texturing. JIJ bid $80,000.00 on Item 1 (Greenacres Elementary School); $95,000.00 on Item 2 (South Olive Elementary School); and $95,000.00 and $1.15 per square foot for re-texturing on Item 3 (Belvedere Elementary School). Petitioner bid $89,349.00 (or $33,394.00 more than did Dynamic, the lowest bidder) on Item 1 (Greenacres Elementary School); $93,885.00 (or $19,085.00 more than did Dynamic, the lowest bidder) on Item 2 (South Olive Elementary School); and $94,306.00 and $3.95 per square foot for re-texturing on Item 3 (Belvedere Elementary School). Of the five Revised Bid Summary Sheets that were submitted in response to the ITB (one each by Austro, Dynamic, Fleischer's, JIJ, and Petitioner), only two, those submitted by Fleischer's and Petitioner, contained the signature of an authorized representative of the bidder. The other three had no signatures on them. All of the "blanks" on each of the five Revised Bid Summary Sheets submitted, including the three sheets without signatures, were filled in and completed, however.4 Furthermore, each Revised Bid Summary Sheet was accompanied by an appropriately signed Invitation to Bid Bidder Acknowledgement form. Bids were opened on August 27, 2009. As announced on the Bid Tabulation Form that was posted on August 28, 2009, the Purchasing Department recommended that Items 1 and 2 be awarded to Dynamic and Item 3 be awarded to Fleischer's. Petitioner, on or about September 8, 2009, protested the award of Items 1 and 2 to Dynamic on the ground that Dynamic's bids on these items were non-responsive because its Revised Bid Summary Sheet had not been signed by an authorized representative of the company. The award of Item 3 to Fleischer's was not protested by Petitioner or any other bidder. By letter dated September 15, 2009, Sharon Swan, Respondent's Director of Purchasing (and head of the Purchasing Department), advised Petitioner of the following: We have completed the review of your protest of Bid for "Exterior Painting of Greenacres, South Olive, and Belvedere Elementary Schools," specifically your protest of the recommendation for award for Greenacres and South Olive Elementary Schools, Items 1 & 2 of this bid. A revised recommendation will be posted later today reflecting a change in our recommendation for Items 1 & 2. The revised recommendation will be to reject all bids on these two items[5] and re-bid with revised bid documents which will clarify the ambiguity relating to the requirement to execute the Bid Summary Sheet when no signature line was indicated. Therefore, I am returning your bank check and closing the file on this protest. You are invited and welcome to compete on the re-bid of these projects. As promised, a second, revised bid tabulation form was posted that same day (September 15, 2009) containing the following "revised recommendation": Item[s] 1 & 2: Reject bid Item[] 1 (one) and Item 2 (two) due to an ambiguity in the bid language, SPECIAL CONDITIONS, paragraph E, Sealed Bid Requirements. Item 3: Fleischer's, Inc. The belatedly perceived "ambiguity" referred to in the Purchasing Department's revised bid tabulation form concerned the intended meaning of the term "executed" in Special Condition E. of the ITB. It had been the Purchasing Department's intent, in using this term in Special Condition E., to require that the Revised Bid Summary Sheet be signed by an authorized representative of the bidder; however, the Purchasing Department had not included a signature line on the Revised Bid Summary Sheet (such as the one appearing on the Invitation to Bid Bidder Acknowledgement form), nor had it specified anywhere in the ITB that the Revised Bid Summary Sheet had to be "signed" (in contrast to the instructions, given in the first sentence of Special Condition E., regarding the Invitation to Bid Bidder Acknowledgement form). Upon its consideration of Petitioner's protest, the Purchasing Department had come to the realization that it had not clearly communicated to prospective bidders its intent concerning the need for a bidder's "executed" Revised Bid Summary Sheet to bear an authorized representative's signature. Believing that its failure to have done so effected the outcome of the competitive bidding process in the case of both Item 1 and Item 2 (in that, with respect to each of these items, the lowest bidder, as well as all other bidders bidding on these two items with the exception of Petitioner, submitted an unsigned Revised Bid Summary Sheet, making these bidders, in the School Board's view, ineligible for an award), the Purchasing Department decided "to reject all bids [with respect to these two items] and rebid so [the Purchasing Department] could correct this ambiguity" concerning the need for a bidder's "executed" Revised Bid Summary Sheet to be signed.6 It is this intended action which is the subject of Petitioner's instant protest.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Palm Beach County School Board take the action described in numbered paragraph 51 above. DONE AND ENTERED this 27th day of May, 2010, in Tallahassee, Leon County, Florida. S STUART M. LERNER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of May, 2010.
The Issue The primary issue for determination is whether Respondent's decision to rescind a previous notice of award of a bid to Petitioner First Master Lessors, Inc., on the basis that the original bid was nonresponsive, was appropriate. If rescission of that bid award was proper, a secondary issue is whether Respondent was also justified in rejecting the competing bid submitted on behalf of Petitioner DSJ Realty Company Inc.
Findings Of Fact Respondent issued an Invitation To Bid in order to obtain a leasehold of 15,397 square feet of office space to house operations of its child support enforcement office in Lakeland, Florida, for a term of seven years with an option to renew the lease for two additional three year periods. The Invitation To Bid (ITB) states Respondent's reservation of the right to reject, if in the best interest of the State of Florida, any and all bids. Further, the invitation states a number of conditions that submitting bidders must meet in order for their bids to be deemed responsive. Among the stated conditions is the requirement that bids be submitted on the standardized bid submittal form enclosed in the ITB in compliance with conditions specified on that form. Further, bidders are directed to complete the bid submittal form providing acknowledgements requested by the form. Another stated condition of the ITB is the requirement that a bidder be the owner of record of the facility and parking areas offered for lease; or, if a lessee seeking to sublease, submit with the bid proposal documentation of authority to sublease the facility and parking areas. A further ITB condition requires each bid to be signed by the owner, corporate officers or legal representative of the bidding entity. Corporate, trade or partnership titles of the bidding entity are to be stamped or typewritten beside the actual signature. Bid submissions signed by an agent are required to be accompanied by written evidence from the owner of record documenting the agent's authority. All bid submittal signatures are to be notarized. Page 4 of the standardized bid submittal form enclosed in the ITB requires, in paragraph 11, that any bid offering premises for consideration (including parking areas), which are presently occupied or which will covered by other active leases on the anticipated lease effective date, must be accompanied by documentation executed by those tenants indicating their acknowledgement of the bid and their ability to vacate the premises by the proposed lease effective date. Submitting bidders are required to indicate whether this requirement is applicable to their bid. Page 4 of the standard bid submittal form contains a number of other conditions which require agreement by the submitting bidder. Proof of the bidder's agreement to those conditions is to be documented by the bidder's initials on each page of the bid submittal package and the bidder's notarized signature on page 16, the submittal form's concluding page. Among the conditions on Page 4 of the form is the agreement of the successful bidder to provide leased space to Respondent for exclusive use on a 24 hour basis, seven days per week during the term of any lease resulting from the bid. This condition further explicitly states that the space to be leased will be fully occupied during normal working hours of 8 a.m. to 5 p.m. during the week and may be fully or partially occupied at other times as necessary in Respondent's discretion. Respondent's bid request specified that bidders must offer a minimum of 65 parking spaces in conjunction with premises proposed for lease. Of those spaces, two spaces were required to meet requirements of accessibility for handicapped parking. Of the remaining spaces, 52 spaces were required to accommodate full size automobiles. All parking was required to be provided as part of the lease cost to Respondent and under the "control of the bidder, off street, suitably paved and lined." On May 16, 1989, five bids were opened, including those submitted on behalf of Petitioner DSJ Realty Company Inc. (DSJ), and Petitioner First Master Lessors, Inc. (MASTER). Out of the five bids opened, only the bids of MASTER and DSJ were determined to be responsive. After evaluation of the bids by Respondent's personnel, the bid was awarded to MASTER on July 6, 1989. On July 11, 1989, and in response to the award to MASTER, a notice of intent to protest the award was filed by counsel for Dale S. Jones, as trustee; DSJ; and Elizabethan Development, Inc. (ELIZABETHAN). By letter dated July 12, 1989, Alan Taylor filed a protest of the lease award to MASTER. That letter simply stated its efficacy as a protest with the words "[w]e hereby protest the award of lease # 590:2087 to First Master Lessors, Inc." No particular factual or legal basis for the protest was stated. Taylor is associated with ELIZABETHAN and his letter is typed on stationary of that business entity. Taylor, designated the bidder on page one of the DSJ bid submittal, was authorized to act solely on behalf of DSJ in the submission of its bid by its president, Dale S. Jones, Jr. Documentation of that authority is contained in a May 8, 1989 memorandum attached to the bid package. There is no documentation in the bid submittal package of DSJ that Taylor was empowered to act on behalf of ELIZABETHAN, or that ELIZABETHAN was authorized to act on behalf of any entity in regard to the bid submittal. While not set forth in the bid package, testimony at the final hearing establishes that Jones is the sole owner of DSJ. Subsequent to the filing of the DSJ protest, Respondent determined to reject the bids of MASTER and DSJ as nonresponsive. By letter dated August 28, 1989, Respondent informed both counsel for DSJ and MASTER of this decision. As set forth in the August 28, 1989 letter, Respondent's decision to reject the bid of DSJ was based upon the failure of DSJ's bid submittal to reflect that its agent, Alan Taylor, or the proposed lessee designated in that bid submittal, DSJ Realty Company, had control of the property offered for lease to Respondent. The August 28, 1989 letter also stated Respondent's rejection of MASTER's bid due to a lack of control of the property sought to be leased, specifically control over parking spaces to be provided in conjunction with the premises to be leased. MASTER's bid submittal stated that the bid requirements in paragraph 11 of the bid submittal form requiring documentation of acknowledgements by any existing tenants of the premises (including parking areas) offered for lease, and ability of those existing tenants to vacate the premises, was not applicable. In response to the bid requirement for 65 parking spaces, MASTER's bid proposed 17 "exclusive" spaces on site and 48 "nonexclusive" spaces off site. An attachment to the bid response was a copy of a letter dated June 10, 1983, from the First Christian Church to a predecessor of MASTER, First Bank of Lakeland. The church, located across the street from the site proposed to be leased to Respondent by MASTER, granted "permission to the First Bank of Lakeland to use our parking lot for the convenience of their employees." Subsequent to the opening of bids and receipt of DSJ's bid protest, MASTER provided Respondent with another letter from the church reciting permission for MASTER to use 48 spaces within the church parking lot for the parking of Respondent's employees and clients, provided that the church reserved the right to use those spaces at any time upon the giving of one week's written notice to MASTER. The church also reserved the right to cancel the agreement at any time upon the giving of 60 days written notice. The letter was dated May 15, 1989. Also, as established at the final hearing, yet another letter was sent to MASTER's authorized agent from the church. That letter documents the rejection by the church of any "formalization" of a reciprocal parking arrangement with regard to the premises proposed to be leased by MASTER. However, the letter, dated July 20, 1989, restated the church's consent to the use of the parking lot by tenants of the premises proposed for lease by MASTER in accordance with its previous letter of May 15, 1989. Another letter attached to the bid submittal of MASTER, is also dated May 15, 1989. Directed to Respondent's facilities services manager, this letter is signed by an individual named Geneva Pettus as "[a]gent for First Master Lessors, Inc." The letter signed by Pettus references the 1983 letter from the church and states in pertinent part: We further guarantee your parking requirements during the term of the lease and will accommodate such spaces either within our own building or other locations if changes in the above parking facilities should occur. The MASTER bid submittal contains no documentation of authority of Geneva Pettus to act as agent for MASTER. Further, as established by the proof at final hearing, the vast majority of on site spaces controlled by MASTER are leased to present tenants or their employees. Remaining unencumbered parking spaces are inadequate to meet Respondent's bid requirements. The "guarantee" by Pettus, absent her lack of authorization to act for MASTER, is further invalidated by failure of MASTER to provide acknowledgements, as required by paragraph 11 of the bid submittal form, from the existing lessees of those parking spaces controlled by MASTER which would have to be vacated in order to comply with bid requirements. The proof establishes that MASTER did not have control of a portion of the property submitted for lease consideration by Respondent, specifically the proposed parking areas. Such lack of control is nonresponsive to Respondent's bid requirements. Notably, the May 15, 1989 date of Pettus' letter coincides with the May 15, 1989 letter to MASTER from the church. Respondent's facilities service manager, involved in evaluation of the bid submittals, was understandably concerned that this letter's existence was not disclosed to Respondent's personnel prior to August 17, 1989. The position of the church as reflected in the letter caused Respondent's personnel to reevaluate the issue of whether MASTER's bid demonstrated the requisite control over the property submitted for bid consideration and concluded that such control was absent. The DSJ bid submittal contains the notarized signature of Dale S. Jones, Jr., in the space on page 16 reserved for the signature of the bidder. His signature is followed by the title "PARTNER." That term is not further described, nor is a partnership or connection of that partnership with Jones identified in the bid package. At the final hearing, Jones confirmed his signature. However, the proof fails to establish that the required initials on each page of the DSJ bid package are those of Jones. Jones was unacquainted with the bid package submitted on his behalf, having merely looked through the package before affixing his signature. Further, the bid submittal form, on page 16, has a blank space for insertion of the name of the bidder submitting the bid package. The bid package submitted on behalf of DSJ contains no name in this portion of the submittal form. Page 16 of the bid submittal form also requires that the bidder indicate the name of the entity in whose name the subsequent lease is to be written, if that entity is one other than the bidder. The bid, signed by Jones and submitted by Taylor on behalf of DSJ, contains the statement that any future lease resulting from the bid should be titled in the name of "DSJ REALTY COMPANY as managing and Leasing Agent for Crystal Lake 301 and 302 Joint Venture." Also attached to the DSJ bid submittal package is a copy of an instrument entitled "DEED TO TRUSTEE UNDER TRUST AGREEMENT." By terms of that instrument, the fee simple title to the property and appurtenances of the site of the building proposed to be leased by DSJ, was purportedly conveyed to Dale S. Jones, Jr., as "Trustee under Land Trust Agreement dated June 15, 1987". By terms of the deed, Jones is granted specific authority to convey, lease or otherwise exercise those rights to property which are commensurate with ownership. The grantor of the deed, dated July 7, 1987, is Florida Southern College. The bid package of DSJ contains no documentation that either Jones or DSJ is authorized to act as an agent on behalf of "Crystal Lake 301 and 302 Joint Venture." Further, the bid package of DSJ offers no explanation as to the identity of this entity. As established by Jones' testimony at hearing, the entities "Dale S. Jones, Trustee" and DSJ Realty, Inc., are not interrelated businesses. The DSJ bid submittal further contains no documentation of authority for ELIZABETHAN or Taylor to act as an agent on behalf of "Crystal Lake 301 and 302 Joint Venture." It is found that the bid submittal of DSJ is nonresponsive to the requirements of Respondent's ITB. In response to Respondent's letter rejecting the bids of Petitioners, counsel for both parties filed petitions dated September 8, 1989, protesting the decision and requesting administrative proceedings. The petition filed on behalf of DSJ, ELIZABETHAN, and Dale S. Jones, as Trustee, was entitled "PETITION FOR FORMAL HEARING AND FORMAL BID PROTEST" and alleges the submitting bidder to be ELIZABETHAN. The document, in support of the July 12, 1989 protest of the bid award to MASTER, sets forth specific grounds for that protest. Further, it is alleged in the petition that DSJ was appointed to act as the agent of Dale S. Jones, as trustee, in appointing ELIZABETHAN as his agent. It is found that these allegations, with regard to the identity of the submitting bidder, are not supported by any competent substantial proof; that Dale S. Jones, as trustee was not a submitting bidder; and that ELIZABETHAN was not a submitting bidder. Each petition filed in opposition to Respondent's August 28, 1989 rejection letter, was accompanied by a $5,000 cashier's check payable to Respondent. MASTER subsequently substituted this check with a surety bond. DSJ's July 12, 1989 protest of the bid award was not accompanied by any bond.
Recommendation Based on the foregoing, it is hereby RECOMMENDED that a Final Order be entered finding the bids of MASTER and DSJ to be unresponsive; finding the cancellation of the award to MASTER to be justified; dismissing ELIZABETHAN and Dale S. Jones, as trustee, as petitioners in this proceeding; and rejecting all bids. DONE AND ENTERED this 14th day of November, 1989, in Tallahassee, Leon County, Florida. DON W. DAVIS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of November, 1989. APPENDIX The following constitutes my specific rulings, in accordance with Section 120.59, Florida Statutes, on findings of fact submitted by the parties. Petitioner Master's Proposed Findings. Petitioner MASTER's proposed findings consisted of 21 pages encompassing unnumbered paragraphs dealing with an intertwined mixture of legal conclusions, argument and proposed factual findings. Therefore, MASTER's submission cannot be treated by the Hearing Officer in this appendix on an individualized basis for each proposed finding. However, MASTER's submission has been reviewed and addressed, where possible, by the findings of fact set forth in this recommended order. Otherwise, all disputed issues of material fact have been addressed by the evidence adduced at the hearing held in this cause. Petitioner DSJ's Proposed Findings. Addressed in substance, remainder rejected as unnecessary. Rejected, unsupported by the evidence. Addressed in substance. Rejected, unnecessary to result. 7.-1I. Adopted in substance. Rejected, unsupported by the evidence. Addressed in substance. Adopted by reference. Adopted in substance. 16.-21. Not relevant inasmuch as Jones, in an individual capacity or the legal capacity of trustee or partner, was not a bidder. 22.-23. Adopted in substance. Rejected, legal conclusion, relevancy. Addressed in substance. 26 Rejected, not supported by the evidence. Taylor was authorized to act on behalf of DSJ Realty, Inc., by the corporate president. 27.-28. Rejected, not supported by the evidence; no evidence that Jones was a bidder. 29.-32. Rejected as unnecessary in view of result. 33.-42. Adopted in substance. Respondent's Proposed Findings. 1-12. Adopted in substance. COPIES FURNISHED: Jack E. Farley, Esq. Department of Health and Rehabilitative Services 4000 West Buffalo Avenue 5th Floor, Room 500 Tampa, FL 33614 Gregory L. Coler Secretary Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, FL 32399-0700 John Miller, Esq. General Counsel Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, FL 32399-0700 Sam Power Agency Clerk Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, FL 32399-0700 Bruce Marger, Esq. 1700 66th Street, North Suite 501 St. Petersburg, FL 33710 David H. Simmons, Esq. 120 South Orange Avenue P.O. Box 67 Orlando, FL 32602 =================================================================