Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
R. A. M. PLANT GROWERS, INC. vs DEPARTMENT OF TRANSPORTATION, 92-000169BID (1992)
Division of Administrative Hearings, Florida Filed:Miami, Florida Jan. 13, 1992 Number: 92-000169BID Latest Update: Apr. 16, 1992

Findings Of Fact Nine bids were received for Contract E4571, Project/Job No. 99004-3516 ("E4571"). Petitioner's bid was timely received. Respondent opened bids on December 13, 1991. Respondent posted its intent to award E4571 to J & D Tropical Landscape Design on December 20, 1991. Section 1.2 of the Bid Specifications for E4571, as modified by the Special Provisions, states: A contractor's bid shall be in the form of a unit price for each unit expected to be accomplished. The Special Provisions to E4571 require each bidder to submit a single unit price for each pay item called for in the Bid Price Proposal. Item 4 in the Special "Provisions provides: It shall be the responsibility of the Contractor to submit to the Department A SINGLE unit price for each pay item called for in the Bid Price Proposal. The Contractor shall be responsible for his/her method of averaging. Failure to comply shall result in the Contractor's Bid Proposal being declared "Irregular" and such Bid Proposals will be rejected. (emphasis added) Petitioner's Bid Proposal was properly declared irregular and rejected by Respondent. Petitioner failed to comply with the requirements of Item 4 in the Special Provisions by failing to submit a single unit price for each pay item, by failing to correctly average a unit price, and by failing to state the unit price in words. The Unit Price Sheet on page 23 of the Bid Proposals contains the following table listing item numbers A582- 2 through A584-4. Petitioner listed item number A583 as follows: ITEM PLAN ITEM DESCRIPTION AND UNIT PRICE $ AMOUNTS NUMBER QUANTITIES UNIT PRICE (IN FIGURES) (Exten- (IN WORDS) sion Price) 3/ A583 4 200.000 TREES (8' TO 20, 85 20400 PLANT ' HEIGHT OR CLEAR TRUNK) @ DOLLARS CENTS The actual extension price 4/ for 200 trees at $85 per unit is $17,000 rather than the $20,400 stated by Petitioner in the table on page 23. The "Contract Total" stated by Petitioner in the bottom right corner of the table is $37,013.20. The "Contract Total" that should have been stated if Petitioner intended the extension price of item number A583-4 to be $17,000 would have been $33,613. The "Contract Total" listed by a bidder on the Unit Price Sheet is the unverified contract price. The actual contract price is determined by Respondent pursuant to the formula given in Section 1.3 of the Bid Specifications. Section 1.3 of the Bid Specifications foil E4571 states: The contract price is defined as the sum of the unit bid price times the planned work for each item as shown on the Unit Price Sheet. Petitioner would have been the lowest successful bidder irrespective of whether Respondent had replaced the extension price for item number A583-4 and the "Contract Total" stated by Petitioner with the actual extension price for item number A583-4 and the actual "Contract Total" . However, Respondent is precluded from doing so by Section 3-1 of the Standard Specifications For Road ,and Bridge Construction ("Standard Specifications"), published by the Florida Department of Transportation (1991) and by the Special Provisions for E4571. Respondent follows "Section 3-1 of the Standard Specifications for the purpose of evaluating bid proposals. Section 3-1 is used, in part, to determine the extension price for item numbers listed on the Unit Price Sheet. Section 3- 1 provides in relevant part: In the event of any discrepancy in the three entries for the price of any item, the unit price as shown in words shall govern unless the extension and the unit price shown in figures are in agreement with each other, In which case they shall govern over the unit price shown in words. Petitioner did not show the unit price in words for any item number on the Unit Price Sheet, including item number A583-4. There is a discrepancy in the three entries for item number A583-4 on the Unit Price Sheet. Petitioner failed to show the unit price for item number A583-4 in words, and the unit price and extension price are not in agreement. Under such circumstances, Respondent interprets Section 3-1 of the Standard Specifications as requiring that Petitioner's bid be declared irregular and rejected. Respondent's interpretation of Section 3-1 of the Standard Specifications is reasonable and is consistent with the mandate in Item 4 of the Special Provisions for E4571. See Finding 4, supra. Furthermore, in practice, the correct unit price of a pay item is necessary to process payment under the contract and the contractor must submit invoices based upon the pay items and unit prices listed in its bid. The bid specifications for E4571 provide that a bidder is responsible for his or her own averaging of a stated unit price, and that if a bidder fails to provide a single unit price for each pay item on the Unit Price Sheet the bid shall be declared "Irregular" and will be rejected. The requirement to provide a single unit price for each pay item was emphasized by Respondent at the mandatory pre-bid meeting. Petitioner's representative attended the mandatory pre-bid meeting. No challenges were made to the bid specifications by any bidder.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent enter a Final Order dismissing the protest filed by Petitioner. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 20th day of February, 1992. DANIEL MANRY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (964) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of February, 1992.

Florida Laws (2) 120.57337.11
# 1
CARMON S. BOONE vs. DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 88-004900BID (1988)
Division of Administrative Hearings, Florida Number: 88-004900BID Latest Update: Jan. 05, 1989

Findings Of Fact Prior to June, 1988, HRS determined that it needed 32,000 square feet of office space to house some of its indigent social services for southern Escambia County. Since the desired office space is greater than 2,000 square feet HRS was required to competitively bid lease number 590:1984. Towards that end, Respondent prepared an Invitation to Bid and a bid submittal package. The package contained various bid specifications, bid evaluation criteria and the numerical weight assigned to each of those criteria. Specific areas of importance to Respondent in the selection of its office space were: client safety one building to house all its units employee morale moving costs traffic flow within the building public access Many of the above areas were important to HRS since the agency would render indigent services to approximately 17,000 people a month, many of whom are handicapped or lack good mobility due to age or infirmity. Employee morale was important because of high employee burn out due to rendering aid to so many people who have so little and supplying a pleasant environment conducive to the work of the employees. Moving costs were important should HRS be required to find other space to operate in while necessary remodeling took place in the selected building, or be required to incur the expense of moving to a new building. 1/ All of the above areas were covered by one of Respondent's weighted bid evaluation criteria. The District Administrator of HRS, Chelene Schembera, is ultimately responsible for bidding, selection and leasing of all HRS facilities within District I, including Escambia County, Florida. In order to accomplish this task, Ms. Schembera appointed a bid evaluation committee to review and grade the responsive bids under the criteria established in the bid package, and to recommend to her the committee's choice of the lowest and best bid. Ms. Schembera's purpose in establishing the bid evaluation committee was to secure a cross section of input from people who had a variety of backgrounds and knowledge that would be material in evaluating the office space under the uses for which it was intended and the relative public worth of the work space. Ms. Schembera appointed individual who were familiar with the type of work to be done in the proposed space, as well as a persons familiar with the bid process. Ms. Schembera assigned to serve on the committee Charles Bates, Deputy District Administrator; Jim Peters, to provide a fiscal and overall administrative perspective as well as bid expertise; two citizens from the District Advisory Council to assure objectivity and to look at the properties from the perspective of a private citizen; Mamun Rashied, a program manager; Darlene McFarland, a program manager; Cherie Neal, a unit supervisor and program worker; and Stacey Cassidy, a clerical employee. Ms. Schembera did not personally know Cherie Neal or Stacey Cassidy. These staff members were designated by the supervisors upon Ms. Schembera's direction that she wanted persons who were both intelligent and respected by their peers. One private citizen member of the committee did not participate. The committee as constituted showed a great deal of thought on Ms. Schembera's part to ensure the objectivity of the bid process she was engaging in and to ensure the maximum amount of input from persons who had experience relevant to the overall review of the proposed real estate and to the decision they were being asked to make. The selection of the bid evaluation committee members was neither an arbitrary nor capricious act on Ms. Schembera's part. In fact, the evidence demonstrated the merit in constituting the committee as she did for the input she sought. The bid evaluation committee members, minus Mr. Bates, were briefed on their duties by Joe Pastucha, Facilities Services Manager. Mr. Pastucha is part of the staff responsible for the bid process at HRS. He provided these committee members with the weighted bid evaluation criteria found at page 15 in the bid package. He also gave the committee members a copy of Chapter 5 of the HRS manual containing guidelines for the bid process. His verbal instructions on specific procedures to follow in the evaluation process were limited since he did not wish to improperly influence the committee members. On July 20, 1988, HRS received three bids responding to its invitation to bid on Lease Number 590:1984. Bid A was submitted by Phillips and Company, the apparent second lowest bidder and Intervenor in this case. Its property consisted of one multi-story building located at 1740 North Palafox Street, Pensacola, Florida. Bid B was not responsive and therefore was not considered by HRS and is not a part of this litigation. Bid C was submitted by Petitioner Carmon S. Boone, and was the apparent low bid. Mr. Boone's property consisted of two buildings located at 401 and 411 North Baylen Street, Pensacola, Florida. The Boone property is the present location of Respondent's offices. Both Bid A and Bid C were within the mandatory geographical area designated in the bid package. Once the bids were received the bid evaluation committee began its work. The committee members, minus Mr. Bates, visited the Phillips property. However, the members did not visit the Boone property. There was no need. Four of the members currently worked at the Boone property and the other members had previously visited the Boone property on various other occasions. Mr. Bates was likewise already familiar with both properties. All members were sufficiently familiar with the cogent aspects of each property to allow them to make a rational decision. The bid evaluation committee, minus Mr. Bates, met as a group to evaluate each property in accordance with the weighted bid evaluation criteria. Each individual scored their sheets separately and the general consensus was supportive of recommending the Phillips property. Five committee members scored Mr. Phillips' property higher than the Boone property. The one exception was Mr. Peters who felt that HRS could not support a bid awarded for other than monetary reasons, i.e., he felt the lowest bid had to be accepted. Mr. Bates later reviewed all the bid synopsis sheets of the committee members and discussed the bid award with Mr. Peters and Mr. Pastucha. Mr. Bates felt that the Phillips property was the lowest and best bid. At about the same time, the staff responsible for providing technical assistance to the committee and the District Administrator were made aware that the general consensus of the committee was leaning towards the second lowest bidder, Phillips and Company, as the lowest and best bid. The staff members, one of whom was a bid committee member, disagreed with the award of the bid to Phillips and Company because the Boone property was the lower bid. The staff members sought to head off the committee's intended recommendation. The staff personnel held a meeting with some of the committee members in order to get them to join in a recommendation to Ms. Schembera of the Boone property. Mr. Boone was invited and attended the meeting. He was allowed to improperly bolster his bid by agreeing to convert the two buildings to one and other lesser additions. /2 The potential decision was discussed, but no committee member changed his or her mind. However, through a total lack of communication, a run away staff somehow rationalized themselves into a position of being authorized to submit a letter for Ms. Schembera's signature which awarded the Boone property the lease. Ms. Schembera became aware of her staff's attempt to subvert the bid process she had established. She refused to sign the letter submitted by the staff. She removed the staff member of the committee as a voting member. The staff member had supported the Boone property. She also removed a committee member who supported the Phillips property as a voting member. Ms. Schembera feared that her staff had improperly influenced this member to such an extent that his objectivity had been affected. Both members could still participate in committee discussions. Ms. Schembera thereby reasonably ensured the ongoing objectivity of the bid evaluation committee. The committee was reconvened, minus one member. It recommended the Phillips and Company property. Every reason given by the individual committee members for distinguishing and preferring one bid over another were rational and reasonable considerations and were covered by the bid evaluation criteria. Each individual member gave a rational and reasonable basis for the scoring he or she used on the bid synopsis score sheets. The scoring was done by each member after discussion of the two buildings and without influence from the other committee members. In essence, the committee felt that the Phillips property was the better property for the money. The Phillips property allowed working units to be located in one area with each such unit having its own access. It provided flat safe parking areas and sidewalks, bigger and more elevators, wide halls and windows which presented a bright, happy and pleasant working environment. The Boone property was in two buildings which could not accommodate co-located working units with their own access no matter how much remodeling took place. Parking and sidewalks are on a hill which is slippery when wet. It had one small elevator and narrow halls which did not adequately accommodate more than one wheel chair, and one ground floor where no windows could ever be remodeled into the building leaving a dark, dingy and unpleasant environment. Importantly, every committee member except for the staff member came to the conclusion that the Phillips and Company property was the lowest and best bid. There is no statutory or rule requirement that one scoring method be preferred over another. The only requirement is that the method be rational and reasonable especially where highly subjective, but legitimate criteria are involved in the selection of a particular piece of property. On these facts, the individual scoring methods used by the individual committee members were not arbitrary and capricious, but were very rational and reasonably related to the relative importance the committee members gave the above factors. After reviewing and considering information from the bid evaluation committee, the information on the bid synopsis sheet, and the oral recommendations of Mr. Bates, Mr. Peters and Mr. Pastucha, Ms. Schembera concluded that the Phillips property was vastly better, even considering costs. She found it to be materially superior in terms of construction, organization, client accessibility, handicap accessibility, repairability (in terms of walls), and maneuverability for clients and staff. She felt the Phillips' building's qualities would offer more "humanity" to the process of serving the Department's clients. Additional facts she considered when making her decision included the morale of the staff and their productivity; the ability of staff and clients to conduct their business in a reasonably pleasant, comfortable, safe, and easy to understand and comprehend environment; and the desire to provide a minimally adequate work space. In addition to other monetary costs, she considered energy costs and life cycle costs as reflected on the bid synopsis sheet. The bid synopsis sheet defined minimal energy and life cycle costs to be anything less than 55 BTU's per square feet per year. In this case, the Boone property reflected 39.5 BTU's per square feet and the Phillips property reflected 53.5 BTU's per square feet. Both properties were under the 55 BTU cutoff established by HRS. Translated into monetary figures (life cycle costs) the Boone property reflected a cost of $26,735.00 and the Phillips property reflected a cost of $41,160.00. It was the difference between the energy figures which caught Ms. Schembera's eye. In her layman's opinion, it was incomprehensible that the two buildings would have such a wide divergence of energy costs. /3 She learned from her staff that the information used to compute these costs was supplied by the bidders who had vested interests in the outcome. Ms. Schembera concluded the cost difference was minimal and not of overriding concern in relation to the physical characteristics of the two buildings and how they compared to each other. She quite correctly felt the two buildings were not comparable. In essence, the two buildings' differences in design location and construction rendered neither building comparable to the other building as a like facility under Section 255.254, Florida Statutes. 4/ Based on that information she gave the energy figures relatively little weight. More importantly, however, before the final bid award was made by HRS, the Division of General Services within HRS in its failsafe role in reviewing bids considered the life cycle cost figures of the two bids. The minimal language of Section 255.254, Florida Statutes, has been interpreted by HRS to mean that anything under 55 BTU's is minimal and except in one instance not applicable here, numerical differences under 55 BTU's are immaterial. The Division, without getting into the issue of the likeness of the facilities, concluded that both bids met the Department's interpretation of the "minimal" language of Section 255.254, Florida Statutes, and the relative numerical difference in the energy costs was immaterial. Ms. Schembera is entitled to rely on other more expert HRS Division staff to ensure a proper analysis of highly technical bid specifications such as the energy cost analysis required under Section 255.254, Florida Statutes. It does not matter that the review took place after Ms. Schembera had made her preliminary decision. What is important is that the review be made either personal or vicariously through staff before the final award is made. A proper review of energy costs was, therefore, made by Respondent before the final award was made. Likewise, Ms. Schembera's ultimate decision that the buildings were not comparable like facilities was a proper review of energy costs even though that conclusion was arrived at through a layman's unsophisticated, but more accurate intuition and common sense. To that extent, the energy cost data had no impact on the ultimate choice made by the District Administrator and were properly considered by the District Administrator. 5/ A letter for Ms. Schembera's signature adopting the committee's recommendation was drafted by Mr. Pastucha. The letter was signed and sent to the Department's Division of General Services for review. The District was requested to provide additional justification for its choice by the Department's Division of General Services. Mr. Rashied was directed to draft the response. He simply reorganized the original memorandum into a format more compatible with the Division's direction, clarified a few points and without significantly changing the content, submitted the response as directed. The Division acquiesced in Ms. Schembera's decision.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Department of Health and Rehabilitative Services enter a final order dismissing Case NO. 88-4900BID, and awarding lease number 590:1984 to Phillips and Company as the lowest and best bidder. DONE and ORDERED this 5th day of January, 1989, in Tallahassee, Florida. DIANE CLEAVINGER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of January, 1988.

Florida Laws (5) 120.53120.57255.25255.254255.255
# 2
PROCACCI FINANCIAL GROUP, LTD., AND PROCACCI COMMERCIAL REALTY, INC. vs DEPARTMENT OF LABOR AND EMPLOYMENT SECURITY, 92-002650BID (1992)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Apr. 28, 1992 Number: 92-002650BID Latest Update: Oct. 27, 1992

The Issue Whether Respondent's rejection of all bids for Lease No. 540:0920 was improper.

Findings Of Fact The Respondent published an invitation to bid seeking to lease approximately 9,907 net square feet of office space in Broward County (the Lease). There was no evidence of any irregularities in the preparation or the issuance of the invitation. The Petitioner, whose responsive bid was rejected by Respondent, timely and properly brought its protest and has standing to protest the Respondent's rejection of all bids for the Lease. Lynn Mobley was the statewide lease manager of the Respondent and had the responsibility to generally oversee the preparation of the bid package and the bid opening procedures. Barbara Lollie was a staff member under the supervision of Ms. Mobley and was in charge of the preparation of the request for bid proposals. Ms. Mobley's supervisor was a Ms. Barron. Five bids in response to the invitation to bid were duly received by Respondent. An evaluation committee chaired by Don Walker, Respondent's area administrator, was appointed to inspect the proposed properties and to evaluate the bids. The evaluation committee ranked the bids in the following order of preference: 1/ 1. In-Rel ($499,141.80) 2. Taft ($519,090.30) 3. Donlon ($541,119.90) 4. Procacci ($618,373.30) 5. Stirlingwood ($761,906.30) Thereafter the responses to the invitation were forwarded to Ms. Mobley's office for evaluation. Ms. Mobley's staff determined that the top two bids, those of In-Rel and Taft, were non-responsive. 2/ Ms. Mobley, who did not actively participate in the evaluation of the proposals, then advised Mr. Walker of that determination and advised him of two alternatives: to award the bid to the lowest responsive bidder or to reject all bids and re-advertise. The evaluation committee chaired by Mr. Walker had wanted to lease the property to either In-Rel or Taft. Mr. Walker told Ms. Mobley that he wanted to reject all bids and to re-advertise. Pursuant to the request for bids promulgated by the Respondent and Rule 13M-1.015, Florida Administrative Code, the Respondent reserved the right to reject any and all bid proposals for the Lease. The request for proposal of bids specifically stated: The Department reserves the right to reject any and all bid proposals for reasons which shall include but not be limited to the agency's budgetary constraints; waive any minor informality or technicality in bids, to accept that bid deemed to be the lowest and in the best interest of the State, and if necessary, to reinstate procedures for soliciting competitive proposals. Following the telephone conversation between Mr. Walker and Ms. Mobley, Ms. Mobley sent a letter dated March 23, 1992, to all bidders which notified each bidder that all bids had been rejected. That letter did not state the reasons for the rejection of all bids. Mr. Walker sent a memo on March 20, 1992, to Ms. Lollie recommending the rejection of all bids. Although this memo predated the rejection letter and was subsequently made available to Ms. Mobley, the memo was received by Ms. Mobley's office after the rejection letter had been sent. The memo gave no explication of Mr. Walker's reasons for wanting to reject all bids. The Department of General Services (DGS) published lease rate guidelines for Broward County to inform the Respondent of maximum acceptable lease rates. The purpose of these DGS guidelines was to advise the Respondent that proposed lease rates above the guidelines would be summarily rejected. At the time of obtaining bid proposals, the DGS lease rate guidelines were the only established guidelines which could be consulted by the Respondent. At no time did the Respondent calculate a pre-bid estimate of what the Respondent felt was an acceptable range of lease rates in order to be used in determining whether lease rates were too high. The Petitioner's bid, along with the other responsive bidders, were within the DGS lease rate guidelines. Mr. Walker made the request for re-bid after he learned that the bids of Taft and In-Rel were non-responsive. Mr. Walker's decision to recommend the rejection of all bids was based only on the information that the two top choices of the evaluation committee had been found to be non-responsive and on his desire to reopen the bid process in the hope of attracting more bidders. 3/ Mr. Walker wanted to modify the specifications of the invitation to bid in two regards. First, he wanted to amend the specifications to permit the leased premises to be in more than one building. Second, he wanted the geographical boundaries in which the leased premises could be located to be expanded to hopefully attract additional bidders. Mr. Walker believed that a re-bid would provide a wider range of buildings at comparable prices from which to choose and would give him an opportunity to make changes to the bid specifications. His decision to recommend the rejection of all bids was not based on a lease bid analysis or on lease rate guidelines. The recommendation was not dictated by budgetary considerations, but by his desire to shop the bid. It was Mr. Walker's understanding that at the end of his telephone conversation with Ms. Mobley that the decision to reject all bids had been made and that all bids would be rejected. Ms. Mobley made the decision to reject all bids pursuant to the recommendation of Mr. Walker after obtaining input from Ms. Lollie and Ms. Barron. Although Ms. Mobley had Ms. Lollie's analysis of the five bids, that analysis made no comparison of the rates contained in the bids with existing lease rates or the DGS guidelines. Ms. Mobley did not consult the DGS lease rate guidelines, although she was generally familiar with those guidelines, and she was unaware of any budgetary constraints that would dictate the rejection of all bids. When Ms. Mobley decided to reject all bids, she did not compare the bid proposals to the existing lease rates paid by the Respondent for leased office space in Broward County. The decision to reject all bids was not made on the advice of an attorney. Although Ms. Mobley testified that all bids on the Lease were rejected solely for price considerations, the evidence presented established that the decision to reject all bids was not based on price, price guidelines, or the Respondent's budgeting constraints. The greater weight of the evidence establishes that Ms. Mobley rejected all bids because that was the action recommended by Mr. Walker. Respondent's invitation to bid did not contain any lease rate guidelines that would notify prospective bidders of a lease rate ceiling. There was no significant difference in the lease rates between the Taft and In-Rel bids that were favored but non-responsive and the third lowest bidder, the Donlon bid, which was responsive but rejected. Mr. Walker conceded that the Donlon bid was not rejected because of price considerations. Mr. Walker was of the opinion that the Donlon bid was at an acceptable price. He did not testify that the Petitioner's bid was at an unacceptable price and he did not testify as to what, other than the DGS guidelines, would be the maximum acceptable price. The DGS Lease Guidelines applicable to the bid for the Lease were as follows: A full service Lease (including electricity) -- $17.84 a square foot. 4/ Lease without electricity -- $15.18 a square foot. The present rate for the existing lease which was to be replaced by the Lease was $16.60 a square foot; this rate did not include electricity. If electricity was factored in at $2.50 a square foot, which was a factor regularly used by DGS, the present lease rate would be approximately $18.00 a square foot. The three responsive bids to the invitation were lower than the present lease after factoring in electricity. Ms. Goodman was of the opinion that Respondent's budget with respect to the Lease would be based on lease rates already in existence and consequently, that the responsive bids received and rejected were within the budget guidelines. Respondent offered no evidence to controvert that opinion. There was no evidence that the decision to reject all bids was based on economic considerations. All lease rates submitted by the rejected bidders were under the ceiling set by the DGS lease guidelines of $17.84. The Respondent acted arbitrarily when it rejected all bids.

Recommendation Based upon the foregoing findings of fact and conclusion of law, it is hereby recommended that the Respondent accept and evaluate the responsive bids submitted for the Lease and determine the proper recipient for an award of the Lease. RECOMMENDED this 29th day of June, 1992, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of June, 1992.

Florida Laws (4) 120.57120.68255.25287.012
# 3
MARVIN`S GARDEN AND LANDSCAPE SOUTHEAST SERVICE, INC. vs. DEPARTMENT OF TRANSPORTATION, 85-003337BID (1985)
Division of Administrative Hearings, Florida Number: 85-003337BID Latest Update: Dec. 02, 1985

Findings Of Fact Both DOT and Weekley submitted proposed Recommended Orders. Their proposed findings of fact have generally been adopted here but are addressed in detail in Appendix A, attached and incorporated in this Recommended Order. On or before July 31, 1985, DOT received sealed bids from three bidders for State Project Nos. 86070-3492 and 93220-3403, involving landscaping of interchanges in Broward and Palm Beach counties. Marvin's Garden was the apparent low bidder, with a total of $389,112.19 shown on the face sheet of the bid blank form. Weekley was the next lowest bidder with a total of $419,899.56, and P. J. Constructors, Inc., was the highest bidder with a total of $458,805.90. After review of the bid documents for compliance with DOT bid procedures, a discrepancy was found in the Marvin's Garden bid and DOT notified the parties by letter dated August 20, 1985, that Weekley was the apparent low bidder on the project. The discrepancy was found on page 001 of the bid blank form submitted by Marvin's Garden. For item 570-11, "Water for Plant Establishment," under the column, unit price written in words, Marvin's Garden showed "fourteen thousand two hundred eighty two dollars and sixty six cents." The column, unit price in figures, showed "14,282.66," and the final column, headed "amounts" showed "14,282.16." The bid item was supposed to show the unit price for a thousand gallons of water (which price was to be written in both words and figures) and a total, or extension price for 3,743.125 thousand gallons of water. When the unit price on Marvin's Garden's bid was multiplied by 3,743.125 (number of units), the resulting total price for that bid item was $53,461,781.71. This figure was entered on the form in red ink and was initialled by Raymond Patrick Haverty, the DOT reviewer. Marvin's Garden's total bid for the project was then adjusted to $53,836,611.04, a figure far in excess of either Weekley's or P. J. Constructors' bids. Marvin Gross is the individual responsible for preparing and submitting bids for his corporation. He has been doing bid work for DOT for approximately 20 years and is thoroughly familiar with the bid procedures, forms and standard specifications. He attributes the irregularity on his submission to his "tunnel vision." Unit prices are significant because the quantity designated by DOT is merely an approximate, best guess by the Department engineers. For item 570-II, unpredictable weather conditions will ultimately dictate exactly how much water will be necessary to successfully complete the landscape project. That exact quantity times the unit price will be the basis of payment to the contractor. DOT found no violations of bid requirements in the bids of Weekley and P. J. Constructors, Inc., and none have been raised in this proceeding.

Recommendation For the foregoing reasons, a final order should be issued declaring Weekley the lowest responsible bidder on project Nos. 86070-3492 and 93220-3403, and the contract awarded accordingly. DONE and ORDERED this 2nd day of December 1985, in Tallahassee, Florida. Hearings Hearings MARY CLARK, Hearing Officer Division of Administrative The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative this 2nd day of December 1985. APPENDIX In accordance with Section 120.59(2) Florida Statutes, the following are recommended rulings on proposed findings of fact submitted by Respondent and Intervenor in this case. Respondent's Paragraph: Corresponding R. O. Paragraph or basis for rejection: The corporate status and the addresses of the bidders are not material. See Paragraph 1, R.O. See Paragraph 2, R.O. and Conclusion of law 2, R.O. See Paragraph 3, R.O. See Conclusion of law 2, R.O. See Paragraph 3, R.O. See Paragraph 6, R.O. See Paragraph 2, R.O. Intervenor's Paragraph: Corresponding R.O. Paragraph or basis for rejection: See Paragraphs 1 and 2, R.O. Facts which relate to the composition of bid packages are not material. See Paragraph 3, R.O. See Paragraph 3, R.O. See Conclusion of law 2, R.O. See Paragraph 3, R.0. See Conclusion of law 5, R.O., relating to the specifications of the department. The remainder of the paragraph proposed is immaterial. See Paragraph 5, R.O. COPIES FURNISHED: Thomas E. Drawdy, Secretary Department of Transportation Haydon Burns Building Tallahassee, Florida 32301 A. J. Spalla, Esquire General Counsel 562 Haydon Burns Bldg. 605 Suwannee Street Tallahassee, Florida 32301 Mr. Marvin Gross, President Marvin's Garden and Landscape Services, Inc. 37 North McIntosh Sarasota, Florida 33582 Mel L. Wilson, Esquire Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32301 Harry R. Detwiler, Jr., Esquire HOLLAND & KNIGHT Post Office Drawer 810 Tallahassee, Florida 32302

Florida Laws (3) 112.19120.53120.57
# 4
PRINCE CONTRACTING, LLC vs DEPARTMENT OF TRANSPORTATION, 16-004982BID (2016)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Aug. 29, 2016 Number: 16-004982BID Latest Update: Jan. 20, 2017

The Issue Whether Respondent acted contrary to the agency's governing statutes, rules, or policies or the bid specifications in its proposed decision to award Contract No. T7380 to Astaldi Construction Corporation ("Astaldi").

Findings Of Fact Based on the oral and documentary evidence presented at the final hearing, and on the entire record of the proceeding, the following Findings of Fact are made: The Department is a state agency authorized by section 337.11 to contract for the construction and maintenance of roads within the State Highway System, the State Park Road System, and roads placed under its supervision by law. The Department is specifically authorized to award contracts under section 337.11(4) to “the lowest responsible bidder.” On April 15, 2016, the Department advertised a bid solicitation for Contract T7380, seeking contractors for the widening of a 3.8 mile portion of U.S. Highway 301 in Hillsborough County from two lanes to six lanes between State Road 674 and County Road 672 and over Big Bull Frog Creek. The advertisement provided a specification package for the project and the “Standard Specifications for Road and Bridge Construction” (“Standard Specifications”) used on Department roadway projects. The work included seven components: bridge structures (Section 0001), roadway (Section 0002), signage (Section 0003), lighting (Section 0004), signalization (Section 0005), utilities (Section 0006), and intelligent transportation systems (Section 0007). The advertisement identified 666 individual items of work to be performed and quantity units for each item. The project was advertised as a low-bid contract with a budget estimate of $51,702,729. The Department’s bid proposal form contains five columns with the following headings: Line Number; Item Number and Item Description; Approximate Quantities and Units; Unit Price; and Bid Amount. The bid proposal form contains line items for the seven components of the project. The utilities component contains 42 line items, each with an Item Number and Item Description. For example, Line Number 1410 corresponds with the following Item Number and Item Description: “1050 11225 Utility Pipe, F&I, PVC, Water/Sewer, 20–40.9 [inches].” Each bidder inserts a Unit Price for the line item in the corresponding “Unit Price” column. The “Bid Amount” column for each line item is an amount generated by multiplying a bidder’s Unit Price by the Quantities (determined by the Department) for each Line Number. The Bid Amount for each Line Number is then added together to generate the “Total Bid Amount” representing the bid for the entire project. Astaldi, Prince, Hubbard, and other potential bidders attended the mandatory pre-bid meeting. Prequalified contractors were given proposal documents that allowed them to enter bids through Bid Express, the electronic bidding system used by the Department. Plan revisions were issued by addenda dated May 10, 2016, and June 7, 2016. A Question and Answer Report was published and updated as inquiries were addressed. Bids were opened on the letting date of June 15, 2016. Bids for Contract T7380 were received from Astaldi, Prince, Hubbard, the DeMoya Group (“DeMoya”), Ajax Paving Industries of Florida, LLC (“Ajax”), and Cone & Graham, Inc. (“Cone & Graham”). The bids were reviewed by the Department’s contracts administration office to ensure they were timely, included a Unit Price for each line item, and contained the completed certifications required by the specifications. Bidders were checked against the Department’s list of prequalified bidders to confirm they possessed a certification of qualification in the particular work classes identified by the bid solicitation. Each bidder’s total current work under contract with the Department was examined to ensure that award of Contract T7380 would not place the bidder over its Department-designated financial capacity limit. Astaldi submitted the lowest bid, a total amount of $48,960,013. Prince submitted the next lowest bid, a total amount of $57,792,043. Hubbard’s total bid was the third lowest at $58,572,352.66. The remaining bidders came in as follows: DeMoya, $63,511,686.16; Ajax, $68,617,978.10; and Cone & Graham, $70,383,697.74. All bidders were prequalified in the appropriate work classes and had sufficient financial capacity, in accordance with section 337.14 and Florida Administrative Code Chapter 14-22. The Department’s construction procurement procedure, from authorization to advertisement through contract execution, is outlined in the Department’s “Road and Bridge Contract Procurement” document (“Contract Procurement Procedure”). The scope statement of the Contract Procurement Procedure provides: “This procedure applies to all Contracts Administration Offices responsible for advertising, letting, awarding, and executing low bid, design-bid-build, construction, and maintenance contracts.” Limited exceptions to the procedure may be made if approved by the assistant secretary for Engineering and Operations. If federal funds are included, the Federal Highway Administration division administrator, or designee, must also approve any exceptions from the procedure. The stated objectives of the Contract Procurement Procedure are: “to standardize and clarify procedures for administering low-bid, design-bid-build, construction, and maintenance contracts” and “to provide program flexibility and more rapid response time in meeting public needs.” The Department’s process for review of bids is set forth in the “Preparation of the Authorization/Official Construction Cost Estimate and Contract Bid Review Package” (“Bid Review Procedure”). The scope statement of the Bid Review Procedure states: This procedure describes the responsibilities and activities of the District and Central Estimates Offices in preparing the authorization and official construction cost estimates and bid review packages from proposal development through the bid review process. Individuals affected by this procedure include Central and District personnel involved with estimates, specifications, design, construction, contracts administration, work program, production management, federal aid, and the District Directors of Transportation Development. The Bid Review Procedure contains a definitions section that defines several terms employed by the Department to determine whether a bid or a unit item within a bid is “unbalanced.” Those terms and their definitions are as follows: Materially Unbalanced: A bid that generates reasonable doubt that award to that bidder would result in the lowest ultimate cost or, a switch in low bidder due to a quantity error. Mathematically Unbalanced: A unit price or lump sum bid that does not reflect a reasonable cost for the respective pay item, as determined by the department’s mathematically unbalanced bid algorithm. Official Estimate: Department’s official construction cost estimate used for evaluating bids received on a proposal. Significantly Unbalanced: A mathematically unbalanced bid that is 75% lower than the statistical average. Statistical Average: For a given pay item, the sum of all bids for that item plus the Department’s Official Estimate which are then divided by the total number of bids plus one. This average does not include statistical outliers as determined by the department’s unit price algorithm. For every road and construction project procurement, the Department prepares an “official estimate,” which is not necessarily the same number as the “budget estimate” found in the public bid solicitation. The Department keeps the official estimate confidential pursuant to section 337.168(1), which provides: A document or electronic file revealing the official cost estimate of the department of a project is confidential and exempt from the provisions of s. 119.07(1) until the contract for the project has been executed or until the project is no longer under active consideration. In accordance with the Bid Review Procedure, the six bids for Contract T7380 were uploaded into a Department computer system along with the Department’s official estimate. A confidential algorithm identified outlier bids that were significantly outside the average (such as penny bids) and removed them to create a “statistical average” for each pay item. Astaldi’s unit pricing was then compared to the statistical average for each item. The computer program then created an “Unbalanced Item Report,” flagging Astaldi’s “mathematically unbalanced” items, i.e., those that were above or below a confidential tolerance value from the statistical average. The unbalanced item report was then reviewed by the district design engineer for possible quantity errors. No quantity errors were found.1/ The Department then used the Unbalanced Item Report and its computer software to cull the work items down to those for which Astaldi’s unit price was 75 percent more than or below the statistical average. The Department sent Astaldi a form titled “Notice to Contractor,” which provided as follows: The Florida Department of Transportation (FDOT) has reviewed your proposal and discovered that there are bid unit prices that are mathematically unbalanced. The purpose of this notice is to inform you of the unbalanced nature of your proposal. You may not modify or amend your proposal. The explanation of the bid unit prices in your proposal set forth below was provided by ASTALDI CONSTRUCTION CORPORATION on ( ) INSERT DATE. FDOT does not guarantee advanced approval of: Alternate Traffic Control Plans (TCP), if permitted by the contract documents; Alternative means and methods of construction; Cost savings initiatives (CSI), if permitted by the contract documents. You must comply with all contractual requirements for submittals of alternative TCP, means and methods of construction, and CSI, and FDOT reserves the right to review such submittals on their merits. As provided in section 5-4 of the Standard Specifications for Road and Bridge Construction you cannot take advantage of any apparent error or omission in the plans or specifications, but will immediately notify the Engineer of such discovery. Please acknowledge receipt of this notice and confirmation of the unit bid price for the item(s) listed below by signing and returning this document. Section 5.4 of the Bid Review Procedure describes the Notice to Contractor and states: “Contracts are not considered for award until this form has been signed and successfully returned to the Department per the instruction on the form.” State estimating engineer Greg Davis testified that the stated procedure was no longer accurate and “need[s] to be corrected” for the following reason: Since the procedure was approved back in 2011, we’ve had some subsequent conversations about whether to just automatically not consider the award for those that are not signed. And since then we have decided to go ahead and just consider the contract, but we are presenting a notice, of course, unsigned and then let the technical review and contract awards committee determine. Astaldi signed and returned the Notice to Contractor and noted below each of the ten listed items: “Astaldi Construction confirms the unit price.” Mr. Davis explained that the purpose of the Notice to Contractor form is to notify the contractor that items have been identified as extremely low and to ask the contractor to confirm its understanding that in accepting the bid, the Department will not necessarily approve design changes, methods of construction, or maintenance of traffic changes. Section 6.6 of the Contract Procurement Procedure sets forth the circumstances under which an apparent low bid must be considered by the Department’s Technical Review Committee (“TRC”) and then by the Contract Awards Committee (“CAC”). Those circumstances include: single bid contracts; re-let contracts; “significantly mathematical unbalanced” bids; bids that are more than 25 percent below the Department’s estimate; 10 percent above the Department’s estimate (or 15 percent above if the estimate is under $500,000); materially unbalanced bids, irregular bids (not prepared in accordance with the Standard Specifications); other bid irregularities2/; or “[a]ny other reason deemed necessary by the chairperson.”3/ Bids that are not required to go before the TRC and CAC are referred to as “automatic qualifiers.” Because it was mathematically unbalanced, the Astaldi bid was submitted to the TRC for review at its June 28, 2016, meeting. The TRC is chaired by the Department’s contracts administration manager, Alan Autry, and is guided by a document entitled “Technical Review Committees” (“TRC Procedure”). The TRC Procedure sets forth the responsibilities of the TRC in reviewing bid analyses and making recommendations to the CAC to award or reject bids. The TRC voted to recommend awarding Contract T7380 to Astaldi. The TRC’s recommendation and supporting paperwork was referred to the CAC for its meeting on June 29, 2016. The duties of the CAC are described in a document entitled “Contracts Award Committees” (“CAC Procedure”). Pursuant to the CAC Procedure, the CAC meets approximately 14 days after a letting to assess the recommendations made by the TRC and determines by majority vote an official decision to award or reject bids. Minutes for the June 29, 2016, CAC meeting reflect 21 items before the committee including: two single bid contracts; four bids that were 10 percent or more above the official estimate; one bid that was 15 percent or more above the official estimate on a project under $500,000; three bids that were more than 25 percent below the official estimate; and 11 bids with significantly unbalanced items, including Contract T7380 with an intended awardee of Astaldi. The CAC voted to award Contract T7380 based on the low bid submitted by Astaldi. A Notice of Intent to award the contract to Astaldi was posted on June 29, 2016. As noted at Finding of Fact 2, supra, Contract T7380 consisted of seven components: structures, roadway, signage, lighting, signalization, utilities, and intelligent transportation system. The Department does not compare bids by component, but looks at the total bid amount to find the lowest bidder. The Department also reviews the bids for discrepancies in individual unit items using the process described above. Astaldi’s bid of $48,960,013 was approximately $8.8 million below Prince’s bid of $57,792,043, $9.6 million less than Hubbard’s bid of $58,572,352, and $2.7 million below the Department’s public proposal budget estimate of $51,702,729. As part of its challenge to the intended award, Prince performed a breakdown of bids by individual components and discovered that nearly all of the differences between its bid and Astaldi’s could be attributed to the utilities component. Astaldi’s bid for the utilities component was $7,811,720, which was roughly $8.5 million below Prince’s utilities bid of $16,305,903 and $5.8 million below Hubbard’s utilities bid of $13,603,846.4/ The utilities component was included pursuant to an agreement between the Department and Hillsborough County, the owner of the water and sewer lines, relating to the improvement of water and sewer lines along the roadway limits of the project. The utility work consists of installing a new water- line and force main sewer. The existing water main and the existing force main conflict with the proposed location of the new storm drainage system. The new water main and force main must be installed, tested, and approved before being put into active service. To prevent water utility outages to customers, the new system must be installed and approved before the existing waterline and existing force main can be cut off and removed. Utility work is therefore the first task to be performed on Contract T7380. Once the utility component is completed, the contractor will furnish and install the stormwater system, the roadway, the bridgework, and all other components. Article 3-1 of the Standard Specifications5/ reserves to the Department the right to delete the utility relocation work from the contract and allow the utility owner to relocate the utilities. Utilities are the only portion of a Department contract subject to deletion because the funding is provided by the utility owner, which usually has allocated a certain dollar figure to contribute towards the contract prior to the bidding. If the bid for utilities comes in over the utility owner’s budget, the owner can opt out of the contract and self-perform. In this case, Hillsborough County had contracted with the Department to contribute $8.9 million for utility relocation work. The Department did not exercise the option to delete the utilities portion of the contract. Jack Calandros, Prince’s chief executive, testified that Prince uses a computer program called HeavyBid, created and supported by a company called HCSS, to build the cost components of its bids. Every witness with industry knowledge agreed that HeavyBid is the standard program for compiling bids in the construction field. Mr. Calandros testified that cost components include material quotes provided by third-party vendors and quotes from potential subcontractors. Labor and equipment costs are ascertained by using historical rates and actual cost estimates that are tracked by the HeavyBid software. Prince maintains its own database of costs derived from 20 years’ experience. Mr. Calandros stated that Prince’s internal labor and equipment rates are checked and adjusted at least once a year to ensure they are current and accurate based on existing equipment and personnel. Prince received three vendor quotes for the materials to perform the utility work on Contract T7380. In compiling its bid, Prince ultimately relied on a final quote from Ferguson Waterworks (“Ferguson”) of $8,849,850. Based on this materials quote and Prince’s overall utilities bid of $16,305,903, Mr. Calandros opined that it would not be possible for Astaldi to perform the utilities component for its bid amount of $7.8 million. Prince’s estimating expert, John Armeni, reviewed Astaldi’s bid file, read the deposition testimony of Astaldi’s chief estimator, Ed Thornton, and spoke to Mr. Thornton by telephone. Mr. Armeni also reviewed Prince’s bid and the bid tabulation of all bidders’ utilities component line items. Based on his review and his extensive experience in the industry, Mr. Armeni concluded that Astaldi’s bid does not include all costs for labor, material, and equipment necessary to construct the utilities portion of this project. Mr. Armeni reviewed the materials quote from Ferguson that Prince used in its bid. He noted that Astaldi’s bid file contained an identical quote from Ferguson of $8.8 million for materials, including some non-utilities materials. Mr. Armeni noted that the Ferguson quote for utilities materials alone was approximately $8 million, an amount exceeding Astaldi’s entire bid for the utilities portion of the project. Mr. Armeni also noted that Astaldi’s overall bid was 18 percent below that of the second lowest bidder, Prince. He testified that 18 percent is an extraordinary spread on a bid where the Department is providing the quantities and all bidders are working off the same drawings and specifications. Mr. Armeni believed that the contracting authority “should start looking at it” when the difference between the lowest and second lowest bidder is more than 10 percent. In his deposition, Mr. Thornton testified he was not aware of how Astaldi arrived at its bid prices for the utility section of the project. Mr. Thornton indicated multiple times that he was not Astaldi’s most knowledgeable person regarding the bid submitted by Astaldi on Contract T7380 project. He testified that Astaldi intended to subcontract the utilities work and acknowledged that the company received a subcontractor quote of $14.9 million after the bids were submitted. Mr. Thornton did not know if Astaldi had solicited the quote. He said it is not unusual for a company to receive subcontractor bids after it has been named the low bidder on a project. Mr. Thornton conceded that Astaldi’s bid did not include all the costs necessary to construct the utilities portion of Contract T7380. At his deposition, he did not have before him the materials needed to determine which items of cost Astaldi had omitted. Mr. Thornton testified that Astaldi was not missing any information it needed at the time of bid submission and understood that its price was to include all labor, materials, and subcontracting costs to perform the contract. After the proposed bid award, Astaldi used HeavyBid to produce a report indicating that the company now estimates its cost of performing the contract at $53,708,129.03, or roughly $4.75 million more than its winning bid. Mr. Thornton testified that Astaldi nonetheless stood ready to execute the contract and perform the work at its bid price. Central to the dispute in this case is Standard Specifications Section 9, “Measurement and Payment,” article 9-2 of which is titled “Scope of Payments.” In particular, subarticle 9-2.1 provides: 9-2.1 Items Included in Payment: Accept the compensation as provided in the Contract as full payment for furnishing all materials and for performing all work contemplated and embraced under the Contract; also for all loss or damage arising out of the nature of the work or from the action of the elements, or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the work until its final acceptance; also for all other costs incurred under the provisions of Division I. For any item of work contained in the proposal, except as might be specifically provided otherwise in the payment clause for the item, include in the Contract unit price (or lump sum price) for the pay item or items the cost of all labor, equipment, materials, tools and incidentals required for the complete item of work, including all requirements of the Section specifying such item of work, except as specially excluded from such payments. Prince contends that the second paragraph of subarticle 9-2.1 renders Astaldi’s bid nonresponsive because Astaldi admittedly failed to include “the cost of all labor, equipment, materials, tools and incidentals” in its bid. Prince points out that the “Technical Special Provisions” governing the utilities portion of the project reinforce the requirement that each bidder include all costs for the work. Technical Special Provisions Section 1-7.1 provides that “[p]ipe installation cost shall include all necessary work, equipment, and labor needed for installing the pipe, such as, coordination with existing utilities and support during construction and support of existing power poles during construction.” Technical Special Provisions Section 1-8.1 goes on to say that “[n]o separate payment will be made for the following items for work under this Technical Special Provision and the cost of such work shall be included in the applicable contract pay items of work,” followed by a comprehensive list of 30 items. Prince concludes that the requirement that each bidder include all costs, including costs of all necessary labor, equipment, and materials, in the Unit Price for each work item is “manifest” in the bid specifications and requires rejection of any bid that does not include all costs. Mr. Armeni opined that if one bidder excludes a portion of its costs, the other bidders are placed at a competitive disadvantage. Alan Autry, the Department’s central contracts administration manager, testified that five other projects were let as part of the bid package that included Contract T7380. He stated that it is typical for the Department to list multiple projects on one day. Mr. Autry’s office usually performs one bid letting per month, with the holiday months of November and December rolled together in a single letting. Mr. Autry stated that his office lets between 200 and 300 projects per year, not counting contracts that are let at the district level. Twenty other contracts were before the CAC at the June 29, 2016, meeting at which the Astaldi award in this case was approved. As noted at Finding of Fact 2, supra, Contract T7380 included 666 line items. Six companies submitted bids, meaning there were a total of 3,996 line items in this single contract. Assuming that the 200 to 300 other projects let by the Department’s Tallahassee office contain similar numbers, there are more than one million line items bid in any given year. If Prince’s reading of the bid specifications is correct, the Department is required to examine each of these line items and somehow make a determination whether the item includes all of the bidder’s costs. This problem of determining bidder cost is complicated by the presence of “companion” or “sister” items in bids, i.e., two items that must be considered in tandem to arrive at something like the actual cost of the work. Prince provided an example of such companion items in its analysis of the bids in this project. Two bid items included in the structures section of the bid proposal form were concrete culverts and reinforcing steel. The contractor may cast the culverts in place at the worksite or purchase them precast. If the concrete culvert is cast in place at the worksite, then reinforcing steel must be used to strengthen the culvert. If the concrete culvert is precast by a materials supplier, then the reinforcing steel has already been incorporated into the culvert at the time of installation. Mr. Calandros explained that when a contractor uses precast culverts, there is no need to list a separate additional cost for reinforcing steel; all costs are captured in the line item for concrete culverts. In this bid, Prince used precast culverts and therefore bid a penny per unit for reinforcing steel.6/ Bidders who cast the culverts in place showed a much higher cost for reinforcing steel but a lower cost for the concrete culverts. When the “companion items” were considered in tandem, the total cost for each vendor was fairly consistent. Prince’s explanation for companion items was coherent but did not explain how the Department is supposed to know which items are companion items as it undertakes the line-by-line cost examination of each bid in accordance with Prince’s reading of the bid specifications. Prince also failed to provide an explanation as to how the Department is to determine a bidder’s costs for any one line item or, for that matter, for its overall bid on a project. Bidders consider their cost information and the processes by which they build bids to be confidential proprietary information. In the instant case, Prince disclosed its own information (aside from materials costs) only under seal during litigation. In its ordinary course of business, the Department does not have access to this information. In fact, as noted at Finding of Fact 23, supra, the Department does not compare bids by component. It looks only at the total bid amount in determining the lowest bidder. Standard Specifications Article 3-8 reserves to the Department the right to perform an audit of the contractor’s records pertaining to the project upon execution of the contract. No authorization is provided to audit records of bidders prior to contracting. Standard Specifications Subarticle 2-5.1 allows bidders to indicate “free” or “$.00” for items that will be supplied at no cost to the Department. Though the Department’s practice, according to Mr. Autry, is to include zero bid items on the Notice to Contractor for confirmation of the price, subarticle 2-5.1 requires no Department investigation as to whether the bidder’s cost for a zero bid is actually zero. Bidders often bid a penny on items, as Prince did on reinforcing steel in this case. Standard Specifications Article 3-5 requires all contracts to be secured by a surety bond such that, in the event of a default by the contractor, the surety company will indemnify the Department on all claims and performance issues. Standard Specifications Section 4 provides that the scope of work is to be determined within the contract, including the furnishing of all labor, materials, equipment, tools, transportation, and supplies required to complete the work. The Department is authorized to make changes to the scope of work and make equitable adjustments of payments. If necessary, the Department may enter into supplemental agreements for additional or unforeseen work. Prince cautions that these change provisions could become relevant because Astaldi’s bid contains no information explaining how Astaldi will cover the $4.75 million difference between its bid price and its actual cost to perform the contract. Prince accurately states that nothing in Astaldi’s bid demonstrates that it has cash reserves to cover the loss and still complete the entire scope of the work.7/ Prince contends that this lack of demonstrable reserves renders Astaldi nonresponsible as to this project. Prince argues that it is error for the Department to rely on Astaldi’s certificate of qualification as proof of the company’s responsibility. The certificate of qualification process considers a contractor’s financial status at the time it submits its financial statements and other information regarding company resources. Prince contends that the Department’s assessment of the contractor’s financial statements and issuance of a certificate of qualification is insufficient to determine the contractor’s responsibility on a given bid. Prince argues that the Department is required by its governing statutes and the Standard Specifications to award a particular contract to the particular bidder that is the lowest, responsive, and responsible bidder, and that “responsible” for a given project is not synonymous with “prequalified.” Prince hypothesizes that under the Department’s practice, a bidder could possess a certificate of qualification issued in January, be indicted in another state for fraud and bribery in February, submit the lowest bid for a Department project in March, and be awarded the contract. By relying solely on the bidder’s certificate of qualification to determine responsibility, the Department could award a contract to a nonresponsible bidder. Section 337.14 provides that any person desiring to bid on any construction contract in excess of $250,000 must first be certified by the Department. Mr. Autry explained that the Department prequalifies contractors to submit bids on certain types of contract, such as major bridges and structures. Contractors applying for certification are required to submit their latest annual financial statements. The Department is charged with reviewing applications to determine “whether the applicant is competent, is responsible, and possesses the necessary financial resources to perform the desired work.” § 337.14(3), Fla. Stat. The Department assigns the contractor work classes and a total capacity after evaluating its experience and financials. The Department’s certificate is good for 18 months, though the contractor’s capacity is reviewed annually. At the time of a particular bid, the Department verifies the contractor’s available capacity, which is simply its total assigned capacity minus current work the contractor is performing for the Department. Mr. Autry testified that the Department does not go back and look at a bidder’s financials to determine whether it can sustain a loss on a given project. The Department does not repeat its capacity analysis during the year, regardless of how many projects the company bids on. The Department’s analysis is limited to whether the company’s current capacity is sufficient for the project on which it is bidding.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that the Department of Transportation enter a final order dismissing Prince Contracting, LLC’s, second amended formal written protest and awarding Contract T7380 to Astaldi Construction Corporation. DONE AND ENTERED this 22nd day of December, 2016, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of December, 2016.

Florida Laws (18) 1.01119.07120.52120.53120.54120.56120.569120.57120.68129.0320.23334.048337.015337.11337.14337.16337.164337.168 Florida Administrative Code (1) 28-106.217
# 5
GREENHUT CONSTRUCTION COMPANY, INC. vs DEPARTMENT OF GENERAL SERVICES, 92-001297BID (1992)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Feb. 24, 1992 Number: 92-001297BID Latest Update: Jun. 04, 1992

The Issue The issue for consideration herein is whether the Respondent's proposed award on BID No. HSMV - 90022010 to Dunn Construction Company, Inc., should be upheld.

Findings Of Fact At all times pertinent to the issues herein, the Department was the state agency responsible for the solicitation of bids for and award of contracts for the construction of state buildings in Florida. Both Greenhut and Dunn are qualified contractors who are certified to bid on state construction contracts in general and this procurement in particular. In December, 1991, the Department issued an advertisement for bids for the project in issue herein, the construction of the Kirkman Complex Addition Data Center in Tallahassee, Florida. According to the Advertisement for Bids, all bids "must be submitted in full accordance with the requirements of the Drawings, Specifications, Bidding Conditions and Contractual Conditions, which may be examined and obtained ..." from the Department's designated architect/engineer, Clemons, Rutherford and Associates, Inc. in Tallahassee. Section B-21 of the request for proposals (invitation to bid) reads, in pertinent part: The recommendation for contract award will be for the bidder qualified in accordance with Section B-2 and submitting the lowest bid provided his bid is responsible and it is in the best interest of the Owner to accept it. The Owner reserves the right to waive any informality in bids received when such waiver is in the interest of the owner. Bids received on this project were originally scheduled to be opened and read aloud on January 15, 1992 with the tabulation and Bid Award Recommendation to be posted the following days at the location where the bids were opened. The proposal as originally issued called for the submittal of a Base Bid with four Alternates, 1a, 1b, 2, and 3. Alternate 1a was a deduct for merely extending the existing Johnson Controls System to incorporate the new work instead of providing a totally new and independent control system. Alternate 1b called for adding furniture and landscaping for certain of the rooms shown on the drawings; Alternate 2 called for adding a "shelled" fourth floor as described in the proposal; and Alternate 3, as originally issued, called for: Add a complete fourth floor as indicated in drawings including the finished interior partitions with full HVAC, Plumbing and Electrical Service. Include furniture and landscaping for rooms 414 and 419. (Includes items in Alternate No. 2) As a result of questions received from prospective bidders at the pre-bid conference which indicated some confusion as to the meaning and intent of the Department regarding Alternate No. 3, by letter to all prospective bidders, dated January 8, 1992 the Department's architect indicated: Alternate #3 shall be the fourth floor complete, as shown on drawings, which includes items in Alternate #2. Addendum #1 to the request for bids, dated January 10, 1992, clarified Item 1-3.6), PROPOSAL FORM, of the PROJECT MANUAL to ADD to "Alternate #3", "(Include items in Alternate #2)". Item #2-1 of Addendum #2, dated January 16, 1992, deleted the sentence changed by Item #1- 3.6, and revised the sentence to read as follows: This includes any items required in addition to Alternate #2 to complete the remainder of the work for the Fourth Floor. Information contained at the beginning of each Addendum calls the bidders' attention to the change and indicates that failure to incorporate it may result in disqualification. The due date for bids was extended at the instance of the Department. Both Petitioner and Intervenor submitted bids for this project as did several other concerns on January 23, 1992. Greenhut's base bid was $4,139,000 with a deduct of $63,600 for Alternate 1a, and additions for Alternates 1b, 2, and 3 of $69,500, $239,000, and $209,000 respectively. Greenhut's total bid, therefore, through Alternate 3, was $4,592,900. Dunn's base bid was $4,079,000 with a zero deduct for Alternate 1a, and additions for Alternates 1b through 3 of $67,000, and $428,000. Dunn's total bid, therefore, was $4,574,000 for a difference of $18,900. Greenhut's bid was submitted on a form which provided for the base bid, the deduct for 1a, and the additions for 1b. 2 and 3 with the figure for 3 being those costs in addition to those identified in Dunn's bid was submitted on a prior form which provided for a base bid, a 1a deduction if any, (there was none), and additions for 1b, 2, and 3 with the figure for 3 including the figure listed for 2. An initial review of Dunn's bid form, then, showed a base bid of $4,079,000, no 1a deduction, a 1b addition of $67,000, a 2 addition of $311,000, and a 3 addition of $428,000. This letter figure included the $311,000 figure for Alternate 2, which should have been deducted from the bid during tabulation. When the bids were opened on January 23, 1992 by Mr. Everline, each figure on each bid was read off and listed on the bid tabulation form in the appropriate area. No attention was given at that time to the appropriateness or correctness of the figures listed on each bid form, nor was any attention paid to any other technical requirement of the procurement. This was merely a transfer of figures from the bid form to the tabulation form, and when this was done, Mr. Everline announced to all in attendance, including many contractor representatives, that the "apparent low bidder" was Greenhut. In arriving at that conclusion, Mr. Everline added all of Dunn's figures together without deducting the $311,000 listed for Alternate 2, a figure which was included in the $428,000 figure listed for Alternate 3. This resulted in an incorrectly large total bid for Dunn. Sometime later that day, a representative of Dunn contacted Mr. Everline to indicate that Dunn had inadvertently bid on the wrong form which precipitated its misleading presentation. Mr. Everline properly declined to discuss the matter and referred the Dunn representative to the Department's legal counsel. Sometime thereafter, when the bids had been tabulated and reviewed for responsiveness and legal qualification of bidders, Mr. Everline suggested to representatives of DHSMV that in order to forestall a protest, only so much of the project as extended through Alternate 2 be awarded. DHSMV officials, however, had sufficient funds available for the entire project, including some additional funds, if necessary, for cabling, and insisted they wanted the entire project awarded. The Department's legal counsel, upon review of the situation, concluded that the Dunn's actual bid intent was clear to include the amount listed for Alternate 2 within that listed for Alternate 3, and not to consider the two as additives to each other. It further concluded that Dunn's use of the improper form on which to submit its bid was immaterial and afforded it no improper competitive edge over other bidders. Therefore, it was concluded that Dunn was the low responsive bidder and, on February 4, 1992, the Department issued a Notice of Award to Dunn. Thereafter, Greenhut filed its Petition For Hearing taken as a protest to the award. Both the Department and Dunn agreed that Greenhut had standing to protest the award and that the protest was timely filed. It is so found.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that the Department of General Services enter a Final Order in this case dismissing the protest of Greenhut Construction Company, Inc., in regard to the proposed award of contact in bid number HSMV - 90022010 to Dunn Construction Company, Inc. RECOMMENDED in Tallahassee, Florida this 21st day of April, 1992. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of April, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 92-1297 BID The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of fact submitted by the parties to this case. FOR THE PETITIONER: 1. - 6. Accepted and incorporated herein. 7. - 9. Accepted. Accepted. & 12. Accepted and incorporated herein. Accepted. Accepted. & 16. Accepted and incorporated herein. Accepted and incorporated herein. & 19. Accepted and incorporated herein. Accepted. & 22. Accepted and incorporated herein. Argument and not Finding of Fact except for 1st sentence which is accepted. & 25. Accepted and incorporated herein. FOR THE RESPONDENT: 1. - 3. Accepted. 4. - 6. Accepted and incorporated herein. 7. & 8. Accepted. 9. - 12. Accepted and incorporated herein. Accepted. Accepted and incorporated herein. Accepted and incorporated herein. & 17. Accepted and incorporated herein. Irrelevant but accepted as true. Accepted. Accepted and incorporated herein. Accepted. Accepted. Irrelevant but accepted as true. Accepted. Accepted and incorporated herein. Irrelevant. Accepted and incorporated herein. Accepted. FOR THE INTERVENOR: Accepted. - 5. Accepted and incorporated herein. Accepted and incorporated herein. & 8. Accepted and incorporated herein. Accepted and incorporated herein. Accepted and incorporated herein. Accepted and incorporated herein. - 15. Accepted. 16. - 19. Accepted. 20. & 21. Accepted. Accepted and incorporated herein. & 24. Accepted. COPIES FURNISHED: Robert A. Emmanuel, Esquire 30 South Spring Street Post Office Drawer 1271 Pensacola, Florida 32596 Sylvan Strickland, Esquire Suite 309, Knight Building 2737 Centerview Drive Tallahassee, Florida 32399-0950 Harry R. Detwiler, Jr., Esquire 315 S. Calhoun Street, Suite 600 Tallahassee, Florida 32301 Ronald W. Thomas Executive Director Department of General Services Suite 307, Knight Building 2737 Centerview Drive Tallahassee, Florida 32399-0950 Susan Kirkland General Counsel Department of General Services Suite 309, knight Building 2737 Centerview Drive Tallahassee, Florida 32399-0950

Florida Laws (1) 120.57
# 6
TOXICOLOGY TESTING SERVICE, INC. vs DEPARTMENT OF CORRECTIONS, 92-001779BID (1992)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Mar. 19, 1992 Number: 92-001779BID Latest Update: Jun. 04, 1992

The Issue At issue in this proceeding is whether the decision of the respondent, Department of Corrections (Department), to award the subject bid to intervenor, Doctors and Physicians Laboratories, Inc. (Doctors), comported with the essential requirements of law.

Findings Of Fact Background On October 16, 1991, the Department of Corrections (Department) issued invitation to bid number 91-CO-5369 (hereinafter "the ITB"), which sought to secure appropriate services to perform drug tests on certain applicants for employment and existing employees of the Department. The deadline for submitting bids was established as 11:00 a.m., November 7, 1991. At the time of the deadline, the Department had received four bids, including those of petitioner, Toxicology Testing Service, Inc., and intervenor, Doctors and Physicians Laboratories, Inc. (Doctors). Petitioner's bid was $372,000, and Doctors' bid was $315,491.60. Based on its evaluation, the Department ranked Doctors first and petitioner second, with composite scores of 91.67 and 90.38, respectively, and proposed to award the contract to Doctors. Petitioner filed a timely formal written protest to contest the Department's decision, and charged that the Department materially departed from the evaluation criteria contained in the ITB. The Invitation to Bid Pertinent to this case, section 4.7 of the ITB established the evaluation criteria to be used in determining the acceptability of the bids as follows: 4.7 Evaluation Criteria Criteria Point Value 1. References 5 2. Firm Profile 5 3. Firms Qualifications 15 Understanding of Scope of Services 25 Bid Price 50 100 And, section 4.7.5 of the ITB established the following methodology to be utilized in awarding points for the bid price criteria: The award for bid price shall be determined as follows: The Bidder who submits the lowest bid price will be awarded 50 points. All others bidders will be awarded points based on the following formula: Bid Price Points = 50 X [1-A/B] where: A = the difference between the percentage of the bid being evaluated and the low bid(s). B = the low bid. The lowest bid price will be computed by multiplying the unit prices for Items 1, 2 and 3 for all three years by the estimated quantity. The estimated quantity is for bidding purposes only and is not a guarantee. The total annual cost for Items 1 and 2 for all three years will be added to determine the Total Cost for all three years. The vendor with the lowest Total Cost will be awarded the 50 points. Negative points will not be awarded. Pursuant to the provisions of section 5.13 of the ITB, the contract was to be awarded to the bidder that received the highest overall point total under the criteria established by section 4.7 of the ITB. The Department's evaluation and the protest Based on its evaluation of the bids, the Department's evaluation committee awarded petitioner 49.34 points for its technical proposal (items 1-4 of the evaluation criteria) and Doctor's 41.67 points for its technical proposal. Bid price points were then established through a preexisting computer program, which derived 41.04 points for petitioner and 50 points for Doctors. When totalled, petitioner received 90.38 points and Doctors received 91.67 points. Accordingly, the Department proposed to award the contract to Doctors. Petitioner filed a timely protest to contest such award. The gravamen of that protest is petitioner's contention that the Department applied a methodology other than that established by the ITB to derive the bid price points and that had it utilized the methodology established by the ITB petitioner would have received the most points and been the prevailing bidder. 1/ Consistent with petitioner's contention, the proof demonstrates that the computer program used to derive the bid price points and the methodology established by the ITB to derive such points differed with regard to the definition of A in the formula, discussed supra. In the computer program, factor A was defined as the difference between the price of the bid being evaluated and the low bid. In the ITB, factor A was defined as the difference between the percentage of the bid being evaluated and the low bid. The Department was not, however, aware of this dichotomy until the subject protest, believing that its ITB conformed with the methodology it had previously programed for its computer, and, at hearing, offered proof, which is credited, that use of the word "percentage" in the definition of A was a typographical error which should have read "price." Notably, the Department heavily weighed price (50%) in its ITB, and it is apparent the Department intended to use a formula that would create a difference in price scoring that was relative to any difference in the bid prices. Use of the formula, as correctly defined in its computer program, would accomplish such goal. Use of the formula, as incorrectly defined by the ITB and interpreted by petitioner in these proceedings, would not accord any meaningful weight to price. 2/ Under such circumstances, it cannot be reasonably concluded that the Department departed from the essential requirements of law when it declined to apply the methodology as interpreted by petitioner to award the contract. Moreover, for the reasons that follow, petitioner has failed to demonstrate that the Department's decision to stand by its award based on the correctly defined methodology departed from the essential requirements of law. Here, the proof demonstrates that petitioner, upon receipt and review of the ITB, was well aware that the formula for awarding points based on price was nonsensical, and most likely, in error. 3/ Notwithstanding, petitioner took no action under the provisions of general condition 6 and special condition 4.4 of the ITB to raise any question or seek any clarification or interpretation of the formula from the Department. 4/ Rather, petitioner submitted its best price offer, more likely than not, without reliance on the erroneous formula set forth in the ITB. 5/ Under such circumstances, it cannot be concluded that the Department's award of the contract, based on an application of the correct definition of factor A, accorded any bidder an unfair advantage or otherwise departed from the essential requirements of law.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be rendered dismissing the subject bid protest. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 20th day of May 1992. WILLIAM J. KENDRICK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of May 1992.

Florida Laws (3) 120.57120.68287.057
# 7
BLISS PARKING, INC. vs BROWARD COUNTY SCHOOL BOARD, 94-002031BID (1994)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Apr. 15, 1994 Number: 94-002031BID Latest Update: Jul. 26, 1994

Findings Of Fact Findings based on stipulation The School Board of Broward County, Florida, ["Board"] issued bid number 94-307D [Lease of School Board Owned Parking Lot - Term Contract] on the 22nd day of November, 1993. Three bidders responded to the invitation to bid. They were: Bliss Parking, Inc., a Florida Corporation ("Bliss"); Fort Lauderdale Transportation, Inc., d/b/a USA Parking Systems ("USA"); and Carl A. Borge. An initial review of the tabulations of the bids indicated that Bliss and USA had submitted the identical percentage of shared revenue to the Board in their respective bids. After the review of the bids, Board staff posted a recommendation to award the bid to USA. [See the "remarks" portion of Exhibit B.] A bid protest was filed by Bliss because of the "remarks" portion of Exhibit B. After a review of Bliss' bid protest, Board staff amended its recommendation to reject all bids because of the issues raised in Bliss' protest. After Board staff notified all bidders of this amended recommendation, USA filed a notice and formal protest. The Board, at its meeting on March 1, 1994, heard the presentation of USA and Board staff. The Board, after deliberating the matter, deferred the item until the meeting of March 15, 1994, wherein seven Board members would be present. At the March 15, 1994, Board meeting, by a vote of 4 to 3, the Board granted USA's protest and awarded the bid to USA whom the Board had determined was the highest bidder meeting bid specifications. All bidders were notified of the Board's action and on the 16th day of March 1994 Bliss timely filed its notice of protest and its formal written protest. Bliss appeared with counsel before the Board on the 5th day of April 1994. After considering arguments of counsel for Bliss and reviewing the material in Agenda Item H-1 and in consideration of its previous actions, it voted to reject Bliss' protest seeking the rejection of all bids received and re-bidding of the item. Bliss subsequently requested a formal hearing under Chapter 120.57, Florida Statutes. Findings based on evidence adduced at hearing The General Conditions portion of the Invitation To Bid includes the following provision: INTERPRETATIONS: Any questions concerning conditions and specifications must be submitted in writing and received by the Department of Purchasing no later than five (5) working days prior to the original bid opening date. If necessary, an Addendum will be issued. A related provision in the Special Conditions portion of the Invitation To Bid reads as follows: 21. INFORMATION: Any questions by prospective bidders concerning this Invitation to Bid should be addressed to Mrs. Sharon Swan, Purchasing Agent, Purchasing Department, (305) 765-6086 who is authorized only to direct the attention of prospective bidders to various portions of the Bid so they may read and interpret such for themselves. Neither Mrs. Swan nor any employee of the SBBC is authorized to interpret any portion of the Bid or give information as to the requirements of the Bid in addition to that contained in the written Bid Document. Questions should be submitted in accordance with General Condition #7. Interpretations of the Bid or additional information as to its requirements, where necessary, shall be communicated to bidders only by written addendum. The Special Conditions portion of the subject Invitation To Bid includes the following provisions: REFERENCES: A minimum of three (3) references must be provided by completing page 14 of the bid. Failure to provide references with the bid or within five (5) days of request by the Purchasing Department will be reason for disqualification of bid submitted. All references will be called. SBBC reserves the right to reject bid based on information provided by references. Page 14 of the Invitation To Bid has three sections, each of which reads as follows: COMPANY NAME: STREET ADDRESS: CITY: STATE: ZIP: TELEPHONE NUMBER: CONTACT PERSON'S NAME: NUMBER OF PARKING SPACES: LENGTH OF CONTRACT: At page 12 of the Invitation To Bid, the following note appears under the Bid Summary Sheet portion of the document: "NOTE: Calculation of high bidder shall be the bidder offering the highest percent of shared revenue meeting all specifications and conditions of this bid." The Special Conditions portion of the Invitation To Bid also contains a procedure for resolving tie bids, which reads as follows, in pertinent part: TIE BID PROCEDURES: When identical prices are received from two or more vendors and all other factors are equal, priority for award shall be given to vendors in the following sequence: A business that certifies that it has implemented a drug free work place program shall be given preference in accordance with the provisions of Chapter 287.087, Florida Statutes; The Broward County Certified Minority/ Women Business Enterprise vendor; The Palm Beach or Dade County Certified Minority/Women Business Enterprise vendor; The Florida Certified Minority/Women Business Enterprise vendor; The Broward County vendor, other than a Minority/Women Business Enterprise vendor: The Palm Beach or Dade County vendor, other than a Minority/Women Business Enterprise vendor; The Florida vendor, other than a Minority/Women Business Enterprise vendor. If application of the above criteria does not indicate a priority for award, the award will be decided by a coin toss. The coin toss shall be held publicly in the Purchasing Department; the tie low bid vendors invited to be present as witnesses. The Petitioner filled out all three sections on page 14 of the Invitation To Bid and submitted that page with its bid. The three references listed by the Petitioner were companies for whom the Petitioner provided parking services or parking facilities, but none of the three references listed by the Petitioner was a land owner from whom the Petitioner leased land for the operation of a parking facility. Mr. Arthur Smith Hanby is the Director of Purchasing for the School Board of Broward County. In that capacity he is in charge of the bidding process for the School Board. Specifically, he was in charge of the bidding process for the subject project. In the course of evaluating the bids on the subject project, the evaluation committee reached the conclusion that there was a problem with the bid submitted by the Petitioner with respect to the references listed in the Petitioner's bid. In the original bid tabulation and recommendation posted on January 4, 1994, the recommendation was that the contract be awarded to the Intervenor, whose bid amount tied with the Petitioner's bid amount. 4/ The reasons for the recommendation were described as follows in the "remarks" portion of the tabulation and recommendation form: REJECT BID FROM BLISS PARKING, INC. REFERENCES WERE GIVEN ON PAGE 14 OF BID. ALL REFERENCES WERE CALLED. BASED UPON INFORMATION PROVIDED BY THESE REFERENCES AND IN ACCORDANCE WITH SPECIAL CONDITION #10, IT IS RECOMMENDED THAT THE BID FROM BLISS PARKING, INC. BE REJECTED. EVALUATION OF THIS BID CEASED AT THIS TIME. THERE MAY BE ADDITIONAL REASONS WHY THIS BID COULD NOT BE ACCEPTED. The sole reason for the rejection of the Petitioner's bid was that the references listed by the Petitioner were not the types of references the evaluation committee wanted to receive. The evaluation committee wanted references from entities who, like the School Board, were land owners who had leased land to a parking lot operator. The evaluation committee was of the opinion that references from other sources would not adequately protect the interests of the School Board. There is nothing in the Invitation To Bid that addresses the issue of who should be listed as references. Specifically, there is nothing in the Invitation To Bid requiring that references be submitted from land owners who had leased land to a parking lot operator. At the time of the issuance of the subject Invitation To Bid, the Petitioner was operating the subject parking lot for the School Board. There were no material differences in the bids submitted by the Petitioner and the Intervenor other than the differences in the types of references they listed. The Petitioner's references who were contacted did not provide any adverse information about the Petitioner. The evaluation committee spoke to two of the references listed by the Petitioner, but did not speak to the third listed reference. The third reference listed by the Petitioner was a court reporting firm located across the street from the location of the subject parking lot. The evaluation committee did not speak to anyone at the court reporting office because the telephone number listed for that reference was not a working number. The evaluation committee made an unsuccessful attempt to locate the telephone number of the court reporting firm in the telephone book.

Recommendation On the basis of all of the foregoing, it is RECOMMENDED that the School Board issue a final order in this case concluding that the Petitioner's bid is responsive to the Invitation To Bid and that the School Board then take one of the courses of action described in paragraph 26, above. DONE AND ENTERED this 23rd day of June 1994 at Tallahassee, Leon County, Florida. MICHAEL M. PARRISH Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of June 1994.

Florida Laws (2) 120.57287.087
# 8
DAVID NIXON, INC. vs DEPARTMENT OF CORRECTIONS, 90-006278BID (1990)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Oct. 05, 1990 Number: 90-006278BID Latest Update: Jan. 15, 1991

The Issue The Department of Corrections sought bids for construction of a health services building for a correctional facility. A discrepancy existed between the written specifications and the architectural drawings for the project. An addendum was issued to clarify the matter. The low bidder (Intervenor) did not acknowledge receipt of the addendum until several hours after the opening of bids. The Department accepted the Intervenor's bid. The Petitioner timely protested the action. The issue in this case is whether, in accepting the Intervenor's bid, the Department acted contrary to the requirements of law.

Findings Of Fact On July 31, 1990, the Department of Corrections (hereinafter "Department") issued an Invitation To Bid ("ITB") for PR-35-JRA, Project #90015, consisting of the construction of a Health Classification Building at the Columbia County Correctional Institution. In relevant part, the ITB requested price proposals for said construction, provided that the bid would be awarded to the responsive bidder submitting the lowest cost proposal, provided that "in the interest" of the Department, "any informality" in bids could be waived, and provided space on the bid form for acknowledgment of receipt of all addenda to the ITB. Bids were to be filed no later than 2:00 p.m. on September 11, 1990, the time scheduled for bid opening. Documents issued with the ITB included architectural drawings and written specifications for the building. The architectural firm of Jim Roberson and Associates, (hereinafter "JRA") had been employed by the Department to prepare the drawings and specifications. JRA was responsible for preparation and distribution of related addenda. Further, a JRA representative presided over the opening of bids on behalf of the Department. Following release of the ITB and supporting documents, JRA became aware of a conflict between sink faucets required by the drawings and those required by the written specifications. The specifications provided that sink faucets operated by hand levers or foot pedals were to be installed in the facility. The architectural drawings JRA indicated that sink faucets were to operate by means of "electric-eye" activators, rather than by hand levers or foot pedals. On September 10, 1990, JRA issued an addendum (identified as Addendum #2) 1/ to clarify that "electric-eye" type operators were to be included in the bids. The addendum was sent by telephone facsimile machine to all anticipated bidders. In part the addendum provides as follows: "This Addendum forms a part of the Contract Documents and modifies the original Specifications and Drawings, dated 31 July 1990, as noted below. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject the Bidder to Disqualification." On September 11, 1990, the eight bids submitted in response to the ITB were opened by the JRA representative. The Intervenor, Custom Construction (hereinafter "Custom"), submitted the lowest bid at $898,898. The Petitioner, David Nixon (hereinafter "Nixon"), submitted the next lowest bid at $900,000. The bid form provided by the Department as part of the ITB materials to prospective bidders provided space for acknowledgment of addenda to the ITB documents. Upon opening the bid submitted by Custom, the JRA representative officiating at the opening noted that the Custom bid failed to acknowledge Addendum #2 in the appropriate space on the bid form. 2/ Robert L. Harris, president of Custom Construction, attended the bid opening. When the JRA representative noted the lack of acknowledgment of Addendum #2, Mr. Harris stated that he was unaware of the addendum. At hearing, Mr. Harris testified that his secretary told him that Addendum #2 was not received by his office. The JRA representative testified that his review of JRA's FAX transmission records indicated that the FAXed Addendum #2 was received by all bidders. The greater weight of the evidence establishes that Addendum #2 was transmitted to and received by, all bidders. Upon leaving the bid opening, Mr. Harris immediately contacted his plumbing subcontractor, Jerry Stratyon, and discussed the situation. Approximately two hours after the bid opening, and after talking with Mr. Stratton, Mr. Harris notified JRA, in a letter transmitted by FAX machine to JRA, that his bid price did include plumbing fixtures required by Addendum #2. Mr. Harris concluded the letter, "[w]hen can we start work. I know you don't want the alternate." On October 8, 1990, JRA recommended to the Department, that the Custom bid be accepted. The letter of recommendation, in part, provides: The apparent low bidder however, did not verify receipt of Addendum No. 2 on the Bid Proposal. Our office did receive a, facsimile after the bid verifying Addendum NO. 2 receipt from the Contractor's Office." However, the actual letter from Custom to JRA states, not that Addendum #2 was received, but that it was included in the price bid by Custom's plumbing subcontractor. Both Nixon and Custom obtained plumbing bids from the same subcontractor, Jerry Stratton. The cost increase attendant to the requirements of Addendum #2 is approximately $2,400 over the plumbing fixtures indicated in the written project specifications. Mr. Stratton was aware of Addendum #2 and testified that the requirements of Addendum #2 were reflected in his price quotes to both bidders. Mr. Stratton provided the same price bid to Nixon and Custom. Mr. Stratton also provided bids to Nixon and Custom for HVAC work. Mr. Stratton was accepted as Custom's HVAC subcontractor. Nixon's bid indicates that another HVAC subcontractor will perform the cork should Nixon receive the contract. The ITB provided that bid modification or withdrawal was permitted on written or telegraphic request received from a bidder prior to the time fixed for opening. Mr. Harris did not attempt to either withdraw or modify Custom's bid prior to bid opening. No bid modification was permitted subsequent to the bid opening. The Department's policy is to waive minor irregularities when to do so would be in the best interests of the State and would not be unfair to other bidders. The evidence does not establish that Custom Construction's failure to acknowledge the addendum was purposefully designed to permit withdrawal of their bid subsequent to the public bid opening. The omission of acknowledgment of Addendum #2 provided Custom an opportunity to withdraw the bid that was not available to other bidders. Custom could have informed the Department that the bid price did not include the requirements of Addendum #2, and the bid could have been withdrawn. Custom was therefore provided with a substantial advantage or benefit not enjoyed by the other bidders. The other bidders, all of whom acknowledged receipt of Addendum #2, had no opportunity to, and would not have been permitted to, withdraw their aids. The fact that Custom did not withdraw the bid is irrelevant.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Department of Corrections enter a Final Order rejecting the bid submitted by Intervenor as nonresponsive and awarding the contract to the Petitioner. DONE and RECOMMENDED this 15th day of January, 1991, in Tallahassee, Florida. WILLIAM F. QUATTLEBAUM Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of January, 1991.

Florida Laws (4) 120.53120.57120.68255.29
# 9
DOUGLAS PRINTING COMPANY, INC. vs. DEPARTMENT OF AGRICULTURE AND CONSUMER SERVICES, DIVISION OF FORESTRY, 83-001984 (1983)
Division of Administrative Hearings, Florida Number: 83-001984 Latest Update: Jul. 03, 1990

Findings Of Fact On May 19, 1983, Respondent mailed official Invitations to Bid (IFB) forms to 18 different firms, including Petitioner, soliciting bids for Class VI printing in accordance with the specifications and conditions attached to the letter, signed by R. E. Read, Jr. This letter contained the comment, "As the best interests of the State may require, the right is reserved to reject any and all bids and to waive any irregularities in bids received." This letter also advised prospective bidders who had questions regarding the IFB to call Larry Amison, the individual who had drafted the accompanying specifications. The notice of IFB, published in the Tallahassee Democrat on Thursday, May 19, 1983, also contained a notice of reservation of the right to reject all bids. Only five IFB forms were returned. Three of the five were returned without bids for various reasons, such as "Not Competitive," "Unable to meet specified delivery date" and "Cannot schedule job of this proportion at this time." This type of explanation, in government procurement circles, need not be taken at face value, but is often used to signal the recipient's thanks for the invitation to bid and a desire to be invited to bid again at some time in the future. The other two forms received were bids: one from Zenith Communications Group, and one from Petitioner. This procurement was somewhat unusual in that the IFB stipulated the amount of money the agency had to spend and requested a hid as to the most product it could get for that money. There were two publications involved: "A" and "B." An alternative was given on delivery date options: one within 30 working days of receipt of approved proofs, and one within 45. Zenith offered to provide 7,180 copies of Book "A" and 7,155 copies of Book "B" (14,335 total books) for a total price of $53,400 1/ within 30 working days. Petitioner offered to provide 9,473 copies of Book "A" and 4,950 copies of Book "B" (15,423 total books) for a total price of $53,344.64 within 45 days. The bids were opened on June 1, 1983, and published from June 1 through June 10, 1983. They were brought to the Director for consideration upon opening. It is his responsibility to evaluate the bids and make a recommendation to the Commissioner of Agriculture on the successful low bidder. Since there was only one bid on each delivery date, the Director felt there were not two comparative bids. As a result, he forwarded the bid package to Ms. Grace Harrison, a purchasing agent with the Department of Agriculture and Consumer Services and an individual very familiar with the procurement of printing services. After a review of the entire bid package, Ms. Harrison's studied opinion was that there were two valid bids and Douglas was the low bidder, and it is so found. Ms. Harrison also felt it was unusual not to receive any more responses than were received on a procurement of this magnitude. This same opinion is held by Mr. Amison, who drafted the specifications. Others have differing opinions, however. Whether it was unusual or not, however, is immaterial. There were two valid bids, and only two are required for an award. However, even in the case of two bids, the agency reserved the right to reject any and all bids. As a result, on or about June 6, 1983, the Director decided, based on his understanding of state policy on the matter and in light of the size of the procurement, to seek more bids through rebidding. In this case, the Director felt more bids were available because of the responses of the nonbidders which referred to the response times being so short. Therefore, he directed a rebid, and this information was communicated to all bidders, including Petitioner. On June 7, 1983, Petitioner wrote to the Director, disagreeing with his decision and notifying him of its protest. On the following day, the Director notified Petitioner the rebidding was being delayed, giving Petitioner 10 days to file a formal notice of protest. This was done in a timely manner. The phrase regarding the agency's right to reject bids is contained in every State IFB. Its purpose is to permit state agencies to reject bids where it becomes apparent there is a valid and legitimate benefit to be gained by the agency in doing so. One such situation is when, in the bona fide opinion of the agency, there are insufficient bids. While there is a difference of opinion as to whether only two bids are unusual in a procurement of this nature, there is no dispute that it would have been beneficial to the agency to have received more than two, since more bids would increase competition. To rebid the contract at this juncture would undoubtedly increase competition to the potential benefit of the Respondent. However, Petitioner claims it would also work to its detriment because other potential bidders would have access to the details of the two present bids and would thereby gain an advantage. This may be the result of rebidding.

Recommendation In light of the foregoing, it is RECOMMENDED: That Petitioner, Douglas Printing Company, Inc., be awarded Contract DOF- ADM-79. RECOMMENDED this 8th day of September, 1983, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of September, 1983.

Florida Laws (1) 120.57
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer