The Issue The issue for consideration in this case is whether the Department of Transportation's (hereinafter "Department") declaration that the bid of Ranger Construction, Inc. (hereinafter ("Ranger") was materially irregular and therefore unresponsive to an invitation to bid on contracts in highway construction projects 93110-3539, 3543, 3525, on State Road 80, (Avenue E), in West Palm Beach, Florida.
Findings Of Fact On December 4, 1991, both Petitioner, Ranger, and Intervenor, Community, submitted bids for job numbers 93110-3539, 93110-3542, and 93110-3525, for a construction project on State Road 80, (Avenue E), in Palm Beach County. Petitioner's bid was in the total amount of $2,554,390.37, and Intervenor's was in the total amount of $2,557,071.42. On the basis of those figures, Petitioner was the apparent low bidder. Bid specifications incorporated in all this agency's bids indicate that a bid may be rejected for irregularities. The term, "material" is not used in that specification. When bids are opened, agency procurement officials look at each bid to insure that any award is based on balanced bids containing all appropriate signatures and other requirements, and in the event of an irregularity, a decision is made on the question of whether any irregularity is material in that specific contract. This decision, made by the Awards Committee, is whether the irregularity is material enough to declare the questioned bid unresponsive and award the contract to the next lower bidder. When bids are first opened at the Department auditorium, they are checked to see if the bid bond or a cash or cash equivalent alternative is present. Then the figures are read off and recorded. The bids are then taken back to the contracts office and safeguarded until the minority business enterprise office looks at them. When this is done, the bids are then passed out to the checkers for examination. This more detailed review of the bids submitted revealed that Ranger's bid bond form, though attested to by the corporate secretary, and executed by George H. Friedlander, Agent for the bonding company, United States Fidelity and Guaranty Company, did not bear the signature of either Ranger's president or vice president. This is considered by Department representatives as being a requirement of a responsive bid. Community's bid bond was properly signed and attested to, and bore the signature of the agent for Reliant Insurance Company, the surety. Community failed to put the company name on the certificate of non- collusion, but in light of the fact that the certificate was signed by the president and was attached to other Community documents, it was identifiable as a part of that bid. In addition, further review of Ranger's bid revealed that on item 630-1- 12 of the computerized price breakdown, certain conduit was listed with a unit price of $621.00 per linear foot. The computer disc furnished to the bidders by the Department, which was used to compute the pricing breakout, reflected 38 linear feet of this conduit would be required. The price of $621.00 per foot on the bid form was in error, however. It should have been $6.21 per linear foot. The error occurred when Ranger's representative punched in the typographically incorrect figure, a clearly clerical error, at the time the bid forms were being completed. This was done, according to Mr. Slade, Ranger's vice president and the person responsible for the bid preparation, in the press of last minute preparation in a motel room in Tallahassee, under less than optimum circumstances. Notwithstanding the fact that this was a clerical error which was not caught by any Ranger official on review of its bid prior to submittal, Department officials considered the use of that large figure made Ranger's bid "unbalanced." This defect, plus the failure of the bid bond to be signed by Ranger's president or vice-president, were both considered to be material deviations by the members of the Department's technical review committee which, based on those deviations, recommended to the Department's Contract Award Committee that Ranger's bid be declared unresponsive. This was notwithstanding the fact that even with the incorrect pricing for the amount of the conduit stated on the Department's discs, Ranger's bid was still low. It must be noted, however, that the 38 linear foot quantity of conduit listed in the Department's discs was an incorrect amount. The project plans, furnished to all bidders prior to the bid process, reflected, in the breakdown of specifications, that the correct amount was 97 linear feet of conduit required. When Ranger's incorrect price of $621.00 per foot was applied to the actual footage required, the result was a bid figure for Ranger which was substantially higher than that submitted by Community and, therefore, caused a reversal in the order of the bidders. The Department applies a deviation standard of 7% to flag bids for more careful scrutiny. Here, the $621.00 item price was clearly in excess of that standard. As will be seen below, Ranger was not the only party to make a mistake in this procurement. The Department's discs erroneously reflected the quantity of conduit required at 38 feet when the actual amount called for was 97 feet. There is a difference, however, between the Department changing its specifications, as would be the case here, and the bidder correcting a unit price after opening. The Department can but the bidder can't. The bid documents, furnished to each prospective bidder, reserve the Department's right to make changes. Though the evidence indicates that it was not unknown in the past for Department officials to call a bidder for clarification of an unclear point in its bid, prior to bid award in this case, even though the pricing of the conduit was, at a figure almost 100 times the average/estimate of $7.30 per foot, no call was made to Ranger by any Department official to insure that the stated figure was the intended figure for inclusion. Mr. Griner, upon inquiry by the Hearing Officer, indicated that though while not usual, such an intentional inflation was not unknown to happen in bidding on Department contracts. No specific cases were cited, however. The evidence also indicates that this particular item was not the only item the Department considered to be unbalanced. There were three others in Ranger's bid, but this one was the only one which was felt to be inappropriate. By the same token, Community's bid also contained several items considered to be unbalanced, but they were not considered to be in the disqualifying category that the conduit price in Ranger's bid was in. Unbalanced bids are considered bad by the Department because, if successful, they allow the contractor to recoup or receive a larger portion of the contract price at the beginning of the contract term thereby making it less disadvantageous for him to walk away from the contract and making agency control over the contractor more difficult. Here, Mr. Slade unequivocally denies it was Ranger's intention to unbalance its contract for any purpose and claims it was no more than a clerical error in inserting the decimal point in the unit price when entered into the computer which resulted in the error. He claims that if he had been contacted by the Department when the obvious error was discovered, as he asserts, has been done in the past, he would have corrected it. It is clear that while query calls may have been made by the Department to bidders in the past, they were of a nature which did not affect the price of the contract. Ranger never received any notice from the Department about any problem with its bid. The first information Mr. Slade had of any problem with Ranger's bid came when his estimator made a routine call to the Department and was told of the problem with the unbalance. Thereafter Mr. Slade spoke with Mr. Newell to determine what route the subsequent proceedings would take. The Department contends, through the testimony of Mr. Newell and Mr. Griner, that it is Department policy to consider the failure to have a required signature on a relevant document to be grounds for declaring a bid non- responsive. Their testimony further reflects, however, that while the recommendations of the Technical Review Committee, (TRC), and the Contract Award Committee, (CAC), are uniformly to that effect, the Department Secretary has, on occasion, rejected such a recommendation and awarded a contract to a bidder whose bid did not contain a "required" signature. Consequently, it cannot be said to be Department policy to reject all bids containing an unsigned document since the Secretary, who as the agency head, sets agency policy, has acted inconsistent with such a "policy." Further, Mr. Morefield indicated that the Awards Committee could waive a failure of signature if it felt to do so was appropriate. To the best of his knowledge, however, that has not been done on this type of contract documents.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that the Department of Transportation enter a Final Order in this case dismissing the protest of Ranger Construction Industries, Inc., in regard to project Nos. 93110- 3539, 3543, and 3525 in West Palm Beach, Florida. RECOMMENDED in Tallahassee, Florida this 20th day of April, 1992. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of April, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 92-1538 BID The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties to this case. FOR THE PETITIONER: I 1. - 5. Accepted and incorporated herein. II 1. - 6. Accepted and incorporated herein. & 8. Accepted and incorporated herein. Rejected as contra to the evidence. Accepted and incorporated herein. & 12. Accepted. 13. & 14. Accepted and incorporated herein. - 23. Accepted and incorporated herein. Accepted. - 31. Accepted. 32. - 41. Accepted and incorporated herein. 42. - 44. Accepted and incorporated herein. 45. - 48. Accepted and incorporated herein. 49. & 50. Accepted. - 53. Accepted. Accepted and incorporated herein. Accepted. Accepted and incorporated herein. Accepted. Rejected as not supported by the evidence. - 61. Accepted. & 63. Accepted. Accepted. & 66. Accepted. 67. & 68. Accepted. 69. Accepted to the extend that the correction is of mathematical calculations of the bid price - not corrections of pricing elements. 70. Accepted. 71. & 72. Accepted. 73. Accepted as a probability 74. Accepted. 75. & 76. Accepted. 77. Accepted. 78. Accepted. 79. Accepted and incorporated herein. 80. Accepted as to the Bond defect; rejected as to the pricing error. FOR THE RESPONDENT AND INTERVENOR: 1. & 2. Accepted and incorporated herein. - 6. Accepted and incorporated herein. Accepted. Accepted. Accepted and incorporated herein. 10. & 11. Accepted. 12. - 14. Accepted. 15. Accepted and incorporated herein. 16. - 19. Accepted and incorporated herein. 20. - 22. Accepted. 23. - 26. Accepted and incorporated herein. 27. - 30. Accepted. 31. - 33. Accepted and incorporated herein. 34. & 35. Accepted and incorporated herein. Not a Finding of Fact but a summary of testimony. & 38. Accepted. Irrelevant and not related to basis for denial. - 42. Accepted and incorporated herein. & 44. Accepted and incorporated herein. First and Second sentences accepted. Balance accepted and incorporated herein. & 47. Accepted and incorporated herein. 48. Accepted and incorporated herein. COPIES FURNISHED: Susan P. Stephens, Esquire Department of Transportation 605 Suwannee Street, MS 58 Tallahassee, Florida 32399-0450 Douglas S. Roberts, Esquire 123 S. Calhoun Street Tallahassee, Florida 32314 Mary M. Piccard, Esquire 1004 DeSoto Park Drive Tallahassee, Florida 32302-0589 Ben G. Watts Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0450 Thornton J. Williams General Counsel Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0450
Findings Of Fact Petitioner is a corporation organized under the laws of Florida with its principal place of business in Tampa, Florida. It was formed in October, 1973 and is in the business of building bridges throughout west/central Florida. It is an independent construction company which specializes solely in bridge and fender construction. Its business relies solely on contracts from public authorities, especially the Respondent herein. On March 19, 1984, in the United States District Court, Northern District of Florida, Petitioner and its president, Gerald H. Stanley were convicted of violating Title 15, United States Code, Section 1 of the Sherman Antitrust Act, for participating in a conspiracy to rig bids by DOT on June 27, 1979. Petitioner was fined $50,000.00 and Mr. Stanley was fined $20,000.00, ordered to perform 200 hours of community service and placed on three years unsupervised probation. Petitioner did not renew its Certificate of Qualification to bid on Florida bridge projects when it expired on or about April 30, 1984. However, on June 12, 1984, both Petitioner and Mr. Stanley filed a Petition for a determination that they are eligible to apply for and hold a Certificate of Qualification under the provision of Section 337.165(2)(d), Florida Statutes, alleging such reapplication to be in the public interest. Marine Structures, Inc. adopted a formal, written antitrust compliance policy in July, 1984, and the record fails to show any instance of bid rigging or antitrust involvement since the one incident in June, 1979. Because of the limited number of companies involved in the road and bridge construction business, the existing companies, who were formerly involved in bidding misconduct, must, of necessity, deal with each other, but there is no indication or reason to assume that such necessary dealings will result in future misconduct. In addition to the written antitrust compliance policy referenced above, Marine has also taken remedial action to assure that all of its employees conduct their business activities in strict compliance with the law and the rules and regulations of both the state and federal governments. Due to Marine's inability to bid on DOT contracts, it has suffered and continues to suffer extreme financial hardship. In its past dealings with DOT, it has performed quality work and has cooperated fully with the Department. DOT indicates it has not been made aware of any particular circumstances involving Marine's or Mr. Stanley's participation in the instant bid rigging incident which would make that incident any more detrimental to DOT than any of the bid rigging conspiracies by the 26 other companies which have been reinstated by the Department. These 26 companies which have been reinstated, submitted themselves to DOT's independent investigations and agreed to comply with the safeguards required in their individual cases to help to assure that contract crimes would not occur on Department projects. Mr. Stanley, on behalf of Marine Structures, Inc., has offered the same assurances. In a letter dated May 1, 1985, to the Secretary, Department of Transportation, the Honorable Jim Smith, Attorney General of the State of Florida, indicated that though Respondent has, in a confidential sworn statement to attorneys for the State, denied any involvement in bid rigging activities other than in connection with that of which he was convicted in federal court, the State investigation, in the opinion of the Attorney General, raises substantial doubt as to the truth of Mr. Stanley's denials of misconduct. The Attorney General indicates that in an effort to resolve this apparent inconsistency, Mr. Stanley was asked, through his counsel, to take a polygraph examination which he refused. Mr. Stanley denies having refused to take the polygraph at any time. Further, the Attorney General relates that Marine Structures, Inc. has not offered to pay any amount of damages to the State, yet Mr. Stanley contends that he has never, to this day, been asked to make any reimbursement or restitution to the State. Mr. Stanley, on behalf of the Petitioner, does not deny that he committed error and that this error constituted an offense against the state and federal governments. He tells a story, however, regarding it which puts it in a somewhat less serious light than is described by the State. According to Mr. Stanley, he gave a bid figure to two other contractors, who he had previously asked to subcontract in his bid, over which they should bid in order to assure Petitioner of having the lowest bid of the three on this particular contract. Both other contractors, Mr. Carroll and Mr. Conner, submitted bids which were higher than that of Petitioner as did a four potential contractor, Square G, and notwithstanding this, Petitioner's bid was lower than the State estimate. In light of this factor he contends that his misconduct, while technically a violation for which he was tried and convicted, did not cost the State one extra cent. He regrets having done it and would not do it again. Both Carroll and Conner, the two other contractors involved with Petitioner in this incident, pleaded guilty and were convicted, but both have been reinstated as eligible bidders on State work. As to the letter of the Attorney General, Mr. Stanley contends that the comment regarding his veracity relates to a situation involving his testimony before the Attorney General's staff about the Citrus County project. Though he had been advised he would be asked about that specific project, in reality, the questions he was asked related to a different project in Alachua County on which he had bid but which involved no bid rigging on his part. Mr. Stanley contends he told his interrogators what he knew but they were not satisfied as to his knowledge regarding another bidder by the name of Hewitt. His denials of any knowledge of Hewitt's bid were not believed and Mr. Stanley feels he was somewhat threatened by members of the Attorney General's staff who reportedly indicated they would keep him off the bidder's list for some time and would "break" him. He contends that he has cooperated fully with state and federal prosecutors not only because of his desire to be reinstated, but also because the terms of his federal probation require him to cooperate fully. He has, in fact, met with state and federal attorneys on two occasions without being subpoenaed, has made his records available to investigative authorities, and has made copies of any documents desired by the investigators. Other than the one incident involved herein, Mr. Stanley contends that neither he nor his company have ever been involved in any other bid rigging situation. He has given statements to both the Florida Attorney General's office and the Antitrust Division on many occasions other than those referenced in the paragraph above. He has given testimony to a U.S. grand jury and the documents and files which he released to the investigative agencies were released prior to his being granted any immunity from State prosecution by the Attorney General. In short he has cooperated fully with state and federal authorities without holding back any information and will continue to do so even if he is reinstated. He feels, therefore, that it is unnecessary for his reinstatement to be withheld as a threat over his head to coerce testimony from him regarding Mr. Hewitt. Admittedly, neither his personal fine nor that assessed against the company have been paid. He has not, however, been dunned for payment and this is just as well because having been barred from bidding on State business, he is finding it difficult to meet his monthly bills much less pay $70,000.00 in fines. As to the purpose behind the State's manner of handling those companies identified as being involved in bid rigging, the Attorney General very clearly established the action philosophy in a statement made to Florida Trend Magazine on May 29, 1984. In the press release in question he stated: "If we forced these companies into bankruptcy we would not be cleaning up the industry, we'd be abolishing it, putting thousands of employees on the streets and destroying competition in a multi-million dollar industry in which the State is a major purchaser . . . . By obtaining the cooperation of settling defendants we greatly facilitated botch the investigation and the willingness of subsequent defendant to . . . (settle)." Respondent has not shown by any evidence that Petitioner was any worse in its misconduct than any other bidder which has already been reinstated, nor has it exhibited any justification for treating Petitioner more harshly than others.
Findings Of Fact As project architect under contract to HRS, Greenleaf/Telesca Planners, Engineers, Architects, Inc. (Greenleaf) prepared a project manual (manual). The manual invited contractors to bid on a contract for construction of the forensic services building at the South Florida State Hospital in Pembroke Pines, Florida, project No. HRS-0278. The manual contained specifications for a base contract covering construction of the building itself, and for four alternate additive bids, covering various equipment and furnishings. The first alternate called for installation of mess hall tables and seats. For the first alternate, the manual specified tables and seats manufactured by Folger Adam Company, their model number 522, or "upon prior approval" the equivalent. From the floor plan it is clear that 24 tables and corresponding seats would be required. The language of the manual describing alternate No. 1 presents no particular ambiguity or difficulty. The Folger Adam Company is well known in the construction business. Harold Wayne Blackwell, petitioner's president, used the manual in preparing Blackwell's bid for the contract. Blackwell bid on the base contract and on each of the four alternates. There are seven or eight contract hardware suppliers in Dade and Broward Counties, all of whom have access to Folger Adam Company products. Folger Adam Company does not have exclusive distributors. To determine the price of the tables, Mr. Blackwell telephoned several contract hardware suppliers, including Christensen Hardware Services, Inc. (Christensen). Christensen quoted Blackwell a price of ten thousand eight hundred dollars ($10,800.00) for twenty-four sets of Folger Adam model number 522 tables and seats. Blackwell submitted a bid of eleven thousand dollars ($11,000.00) on alternate No. 1. Forsythe bid on the base bid but did not bid on alternate No. 1, because Forsythe failed to obtain a quote on the tables and seats, before preparing its bid. Richard B. Solomon, Greenleaf's project manager for the forensic services building, opened the bids on March 20, 1979. As tabulated by Greenleaf, the bids were: Base Bid Alt. No. 1 Alt. No. 2 Alt. No. 3 Alt. No. 4 M.D. Forsythe Construction Co. $375,000 $ --- $50,842 $27,220 $33,020 Porfiri Construction Co. 406,200 7,000 45,534 25,315 44,130 Wayne Blackwell and Co., Inc. 397,735 11,000 47,000 25,000 35,000 Ed Ricke & Sons, Inc. 405,000 14,900 52,000 28,300 47,650 McKee Construction Co. 407,000 --- 45,000 28,000 --- L.G.H. Construction Corp. 524,176 18,014 43,464 24,712 35,048 Creswell Construction Co. 394,000 41,000 43,000 23,000 33,000 Petitioner's exhibit No. 2. On the base bid, Forsythe was lowest, Creswell Construction Company next lowest, and Blackwell third lowest. Among contractors who bid on the base bid and all alternates, Blackwell's combined bids were lowest for the base bid plus alternate No. 1, the base bid plus alternates Nos. 1 and 2, the base bid plus alternates Nos. 1, 2 and 3, and the base bid plus alternates Nos. 1, 2, 3 and 4. Mr. Solomon was aware of two telephone calls received by Greenleaf during the time for preparation of the bids, inquiring about the price of the tables and seats. In examining the bids, he noticed that two contractors had not bid on alternate No. 1, and that the base bids as well as the bids on alternates Nos. 2, 3 and 4 were "pretty tight" as compared to the range of bids on alternate No. 1. From looking at the bids on alternate No. 1, it was hard for Mr. Solomon to tell what a reasonable price for the tables and seats was. Mr. Solomon recommended to HRS that the bids on alternate No. 1 be thrown out. Charles Robert Yates, an architect employed by HRS, concurred in Mr. Solomon's recommendation. He was under the impression that funding for the project would not be available unless the contract was let before April 1, 1979. Mr. Yates could not recall such diversity among bids in his thirty-year career, yet he had no difficulty learning what the tables and chairs cost when he called architectural firms to find out. After the bids were opened, Blackwell promptly protested Forsythe's bid. Under the heading of alternates, the manual states: If the Base Bid is within the amount of funds available to finance the construction contract and the Owner wishes to accept alternate additive bids, then contract award will be made to that responsible Bidder submitting the low combined bid, consisting of the Base Bid plus alternate additive bids (applied in the numerical order in which they are listed in the Bid Form). Petitioner's exhibit No. 1, Paragraph B-9, Alternates. HRS wrote Blackwell on April 3, 1979, denying Blackwell's protest and stating, as reasons: M.D. Forsythe Construction Co., Inc. did not ignore Alternate No. 1, but completed that section of their bid by stating "No bids received on this item." Proposals for Alternate No. 1 ran the gamut for "No Bid" to prices extending from $7,000 to $41,000. The Department holds, as concurred in by the attached letter from our consultants, that there was confusion in the marketplace regarding the intent of Alternate No. 1, as attested to by the disparity among the proposals, and therefore we choose not to consider Alternate No. 1. Provisions for this deletion include Sections B-17, B-22 and B-24 of the Contract Documents. Petitioner's exhibit No. 3. HRS then awarded the base contract and additive alternates Nos. 2 and 3 to Forsythe, and gave orders to proceed with construction on May 7, 1979. After construction began, Mr. Solomon wrote Forsythe to inquire what Forsythe would charge to install the tables and seats called for by additive alternate No. 1. Forsythe eventually agreed to do it for eleven thousand dollars ($11,000.00), after first quoting a higher price. On August 1, 1979, Greenleaf prepared a change order at HRS' behest, directing Forsythe to install the tables and seats originally called for by additive alternate No. 1, at a price of eleven thousand dollars ($11,000.00). Other provisions of the manual relied on by the parties include the following: B-17 PREPARATION AND SUBMISSION OF BIDS Each Bidder shall copy the Proposal Form on his own letterhead, indicate his bid prices thereon in proper spaces, for the entire work and for alternates on which he bids. Any erasure or other correction in the proposal may be explained or noted over the signature of the Bidder. Proposals containing any conditions, omissions, unexplained erasures, alternations, items not called for or irregularities of any kind may be rejected by the Owner. . . DISQUALIFICATION OF BIDS Any or all proposals will be rejected if there is reason to believe that collusion exists among the Bidders and no participants in such collusion will be considered in future proposals for the same work. Proposals in which the prices obviously are unbalanced will be rejected. Falsification of any entry made on the Contractor's bid proposal will be deemed a material irregularity and will be grounds, at the Owner's option, for rejection. REJECTION OF BIDS The Owner reserves the right to reject any and all bids when such rejection is in the interest of the State of Florida, and to reject the proposal of a Bidder who is not in position to perform the contract. AWARD OF CONTRACT The contract will be awarded as soon as possible to the lowest qualified Bidder provided his bid is reasonable and it is in the best interest of the Owner to accept it. The Owner reserves the right to waive any informality in bids received when such waiver is in the interest of the Owner. The lowest bidder will be determined by adding to the Base Bid such alternates, in numerical order, as available capital funds will allow. The Agreement will only be entered into with responsible contractors, found to be satisfactory by the Owner, qualified by experience, and in a financial position to do the work specified. Each Bidder shall, if so requested by the Owner, present additional evidence of his experience, qualifications, and ability to carry out the terms of the contract, including a financial statement. Petitioner's exhibit No. 1. At no time did Forsythe attempt to influence the award of the contract improperly. At the time of the final hearing, the project was approximately 95 percent complete.
Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That, in the future, HRS adhere to the letter of language like that contained in paragraph B-9 of the manual whenever such language is used in an invitation for bids. DONE and ENTERED this 6th day of March, 1980, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: Louis L. LaFontisee, Jr., Esquire 200 South East First Street, Suite 802 Miami, Florida 33131 Leonard Helfand, Esquire 401 North West 2nd Avenue Room 1040 Miami, Florida 33128 Richard Morgentaler, Esquire 1600 North East Miami Gardens Drive North Miami Beach, Florida 33179 =================================================================
The Issue The issues in this case are whether the Department of Transportation ("Department") erred by considering Willeby Construction, Inc. ("Willeby") a qualified bidder; whether the requirement to submit a bid bond or certified funds check or draft (hereafter "security on the bid") with the bid was a material requirement; whether the Department erred in treating Willeby’s failure to include security on the bid with its bid proposal as a minor, and, thereby, an irregularity which could be waived; and whether said decision of the Department was contrary to the terms of the bid, contrary to law, or arbitrary and capricious.
Findings Of Fact On November 14, 2000, the Department issued a bid solicitation notice for Financial Project No. 40509417201/Contract No. E3A78, a contract for routine mowing of grassed and vegetated roadside areas and litter removal from within the Department’s highway right-of-way in Gadsden and Leon Counties. The invitation to bid stated: In a letter dated November 17, 2000 from Richard Norris of the Department District Contracts Office to all prospective bidders, the Department reiterated the bid bond requirement stating "[i]f your bid is over $150,000, a Bid Bond of 5 percent of the bid amount is required and must be attached to your bid proposal. Failure to submit this with your bid will result in your bid being rejected." (Emphasis is in original.) The invitation to bid further stated: BID OR PROPOSAL BOND (If bid is over $150,000): Must be completely executed if bid is over $150,000. This 5 percent bid bond is required and must be included in your bid package. If bid is less than $150,000 no bid bond shall be necessary, however, the successful bidder shall be required to obtain a performance bond upon execution of the contract. The purpose of the requirement for security on the bid is to compensate the Department for damages in the event the low bidder fails to enter into the contract. The Department received bid proposals from six firms in response to its bid solicitation by the due date of December 7, 2000. The lowest bidder for Contract No. E3A78 was Willeby. Willeby submitted a business check drawn on Willeby’s business account no. 02-140168-01 with Farmers & Merchants Bank. This was an unsecured, personal check. At the time the bids were opened, Willeby’s Account No. 02-140168-01 contained insufficient funds to cover the check Willeby submitted as its bid bond in the amount of $11,996.52 for Contract No. E3A78. Willeby failed to submit the required security on the bid in the form of a cashier’s check, bank money order, bank draft of any national or state bank, or surety bond, payable to the State of Florida, Department of Transportation as required by the solicitation. The Petitioner, Phoenix, was the second lowest bidder. Phoenix submitted a bid bond equal to 5 percent of its total bid with its bid package. Phoenix fully complied with all the requirements of the invitation to bid. Bids for Contract No. E3A78 were opened on Thursday December 7, 2000. At that time, the Department's personnel discovered that Willeby had failed to submit security on bid as required by the terms of the bid solicitation. On December 15, 2000, eight days after the Department discovered that Willeby’s bid submittal was deficient, Starsky Harrell, the contract specialist with the District III office of the Department, telephoned W.J. Willeby, the president of Willeby Construction. Harrell informed Mr. Willeby that Willeby’s bid was non-conforming, and gave Willeby the opportunity to cure its non-responsive bid by submitting a check for certified funds or a bid bond as required by the bid solicitation. Willeby, at this point, had the opportunity to cure the defect or refuse to cure the defect, thereby, negating his bid. This gave Willeby an advantage not enjoyed by the other bidders. Willeby chose to cure its non-responsive bid, and submitted a certified check as its security on the bid. Willeby, thereafter, entered into the contract with the Department on Monday, December 18, 2000, eleven days after the bids were opened. The Department posted its intent to award Contract No. E3A78 on December 21, 2000, indicating its intent to award the contract to Willeby Construction. Phoenix timely filed this formal protest in opposition to the award of Contract No. E3A78 as contrary to Section 120.57(3)(f), Florida Statutes (2000). Regarding the requirements for security on the bid required in the solicitation for the bid and accompanying materials, Richard Norris, the contracts administrator, made the decision to emphasize the language by having it in bold-face type and underlined. His purpose for underlining and placing in bold-face type this language was to "put some accent on it, to make it stand out." A basic tenet of competitive procurement is to protect the integrity of the bidding process and ensure open and fair competition. A responsive bid is one which meets all the requirements of the proposal documents. Mr. Willeby has entered bids on Department contracts seventeen times in the past. Willeby is an experienced participant in the bid process. A bidder who has the option of taking a contract or not taking a contract after the bidder knows what the other bids are on a project has a competitive advantage over other bidders. If the bidder has bid too close to the profit margin, the bidder can refuse to cure the bid defect and avoid performance on the unprofitable contract. It is not only less expensive for a person to submit a personal check for security on a bid, but a stop payment order can be issued on a personal check. The bid bond posted by the Petitioner cost $800.00. This amount is not refundable. However, the proposal provides alternatives to a bid bond to establish security on the bid; therefore, paying the cost of the bond is not a competitive disadvantage. It is noted that a personal check is not among the alternatives, and the bid proposal's provisions for bid security specifically provide that checks or drafts for less than 5 percent of the bid amount will invalidate the bid. The only checks or drafts permitted under the terms of the bid proposal are those checks secured by the banking institution's funds and not subject to stop payment orders of the person in whose behalf the check is issued. It is consistent with the stated terms of invalidation, that, in addition to an insufficient amount, that an instrument not meeting the stated terms of the provision would also invalidate the bid. If being a dollar short on the secured amount is disqualifying, being short the entire amount in secured funds would be similarly disqualifying. Evidence was received regarding whether Willeby was a qualified bidder. This information related to the nature and amount of the equipment which Willeby had, and its financial ability to obtain additional equipment. Although Willeby did not have some of the equipment necessary to handle this job and its other contract obligations, he had ordered this equipment and his bank indicated that it would loan him the money. It was not developed whether the bank's willingness was dependent upon the pendency of the challenged contract award, and it is concluded that Willeby is a qualified bidder.
Recommendation Based upon the findings of fact and conclusions of law, it is RECOMMENDED: That the bid of Willeby Construction on Contract No. E3A78 be rejected, and the contract be awarded to the Petitioner. DONE AND ENTERED this 25th day of April, 2001, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 25th day of April, 2001. COPIES FURNISHED: Julius F. Parker, III, Esquire Pennington, Moore, Wilkinson, Bell & Dunbar, P.A. 215 South Monroe Street, Suite 200 Tallahassee, Florida 32301 Brian A. Crumbaker, Esquire Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0450 James C. Myers, Clerk Department of Transportation Haydon Burns Building, Mail Station 58 605 Suwannee Street Tallahassee, Florida 32399-0450 Pamela Leslie, General Counsel Department of Transportation Haydon Burns Building, Mail Station 58 605 Suwannee Street Tallahassee, Florida 32399-0450
Findings Of Fact Based upon the documentary evidence received and the entire record compiled herein, I hereby note the following findings of fact: Notice and Invitation to Bid on State Project Number 72001-3448 (the project) was extended to various contractors by the Respondent, Department of Transportation, on August 1, 1985. Sealed bids on the project were opened August 28, 1985. The scope of the project involved cleaning and painting the structural steel of the Buckman Bridge over the St. Johns River in Jacksonville, Florida. (State Bridge Numbers 720249 and 720343). The bids were opened and Petitioner was the apparent low bidder on the project with a bid amount of $193,000. The Department of Transportation, on October 2, 1985, rejected all bids "due to error in quantities in plans." According to the contract plans and specifications utilized by the Department of Transportation for the project, the beams, girders, bracing and trusses were composed of 2,540 tons of structural steel. The plans were in error and the tonnage of structural steel was less than 2,540 tons. Petitioner, upon visiting the job site as required, immediately recognized that there was less steel in the bridge than shown in the plans. In submitting and formulating his bid, the Petitioner considered the amount of work and materials which would actually be required to complete the project. 6 Prior to the bids being posted on the project, the Department of Transportation discovered that the amount of structural steel noted in the plans was grossly overestimated. On October 2, 1985, the Department of Transportation notified bidders in writing that all bids submitted on the project were rejected and that the plans would be revised and the project relet.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is, RECOMMENDED that the petition of Industrial Enterprise Sandblast and Painting, Inc., protesting the rejection of all bids on State Project No. 72001- 3448, be dismissed. DONE AND ORDERED this 11th day of December 1985 in Tallahassee, Florida. W. MATTHEW STEVENSON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of December 1985. APPENDIX Respondent's Findings of Fact FINDING RULING Accepted; see Recommended Order paragraph 1. Accepted; see Recommended Order paragraph 2. Accepted, but not included because subordinate. Accepted; see Recommended Order paragraph 4. Accepted; see Recommended Order paragraphs 3 and 6. Accepted; see Recommended Order paragraphs 3 and 6. Accepted; see Recommended Order paragraph 6. COPIES FURNISHED: HONORABLE THOMAS E. DRAWDY, SECRETARY DEPARTMENT OF TRANSPORTATION HAYDON BURNS BUILDING TALLAHASSEE, FLORIDA 32301 A. J. SPALLA, ESQUIRE GENERAL COUNSEL DEPARTMENT OF TRANSPORTATION 562 HAYDON BURNS BUILDING TALLAHASSEE, FLORIDA 32301 LARRY D. SCOTT, ESQUIRE DEPARTMENT OF TRANSPORTATION HAYDON BURNS BUILDING, M.S. 58 TALLAHASSEE, FLORIDA 32301-8064 INDUSTRIAL ENTERPRISE SANDBLAST & PAINTING, INC. P. O. BOX 1547 1502 FOX RUN DRIVE TARPON SPRINGS, FLORIDA 32486-1547
Findings Of Fact On or about October 28, 1987, the Department of Health and Rehabilitative Services (HRS) mailed its Invitation To Bid (ITB) No. 88-32BC to prospective bidders. According to the Special Bid Conditions of ITB No. 88- 32BC, the stated purpose of the ITB was "to obtain competitive bid prices from Vendors/Contractors for the purchase and installation of Open Office Partitions/Furnishings and related accessories for use by the department's ABUSE REGISTRY, located in the East Wing, 2729 Fort Knox Blvd., Tallahassee, Florida 32308." Included among the responses to the ITB were bids by International Interiors, Inc., (International), by Perdue Office Interiors, Inc., (Perdue), by Executive Office Supply, Inc. (Executive), and by Haworth. The construction of the future HRS office space in the East Wing of 2729 Fort Knox Blvd. was coordinated between the owner and HRS to accommodate the needs of the HRS Abuse Registry. The space will be used by qualified HRS personnel and support staff to receive and maintain telephone reports of child abuse and related complaints. HRS consulted with the owner's architect to determine the ultimate floor plan of the HRS space in the building and then consulted an interior design expert to determine how HRS could best utilize the space for the purposes of the Abuse Registry through these efforts, HRS designed an office interior consisting of a system of partitions and furniture. The interior design was reduced to a blue print or design drawing specifying gross dimensions as well as the particular dimensions of offices, partition panels, hallways, work space (desk tops), related components of the system and the particular location of building support columns and electrical power poles. The ITB included a design drawing and provided in pertinent part in its Special Bid Conditions: DESIGN: This project has a limited amount of space with fixed walls and fixed dimensions as given on the architectural drawing. Each vendor must guarantee his system will fit into the space without any violation of Florida Building Codes. Design Drawings and a Component Listing have been included in each bid package so that each vendor will have the equal opportunity to evaluate the project as a whole as well as by its parts. All dimensions are listed as nominal dimensions since various manufacturers' component varys [sic] somewhat in exact dimensional sizes. Surface materials and colors will be selected from the successful vendor's line after the award of the bid has been made. SITE EXAMINATION: The area to be used by the Abuse Registry is located on the main floor, east wing, 2729 Fort Knox Blvd., in Tallahassee, Florida 32308. The site has existing walls, columns, door entrances, etc., which will have to be taken into consideration when integrating your open office system into the design scheme. It is the responsibility of the vendor to inspect the premises and familiarize himself with all of these on-site conditions. A floor plan has been provided for reference only, and any specific analysis or dimensioning should be made on site by the vendor. Contact Mr. DeVoe Moore to schedule a tour of the work site. (904) 656-6211. Failure to consider on-site conditions may result in disqualification of the bid. The Technical Specifications provide in pertinent part: All dimensions in this component listing has [sic] been provided for the purpose of fulfilling the overall dimension requirements as shown in the furniture plan. Variations from these will occur between different manufacturer's products. In providing dimensions other than those listed, it is critical to maintain a minimum hall clearance of 4'0" or code requirement and to work within the given permanent walls. (Emphasis added.) International's bid was the lowest at $211,523.96. But HRS disqualified it as nonconforming because cursory review, as well as International's own design drawing furnished with its bid, showed that International's proposal would intrude three feet into a four foot hallway around the perimeter of the office space which is required, and is required to be four feet wide, by the applicable building codes and the State Fire Marshal. HRS' disqualification of the International bid on that ground was erroneous under the facts presented at final hearing. The intrusion of the International proposal into the required hallway was due to International's error in configuring the partition panels for purposes of the design drawing. No other bidder even included a design drawing, which was not required by the ITB. The apparent intrusion of the International proposal into the hallway is easily corrected by swapping 66" partition panels that had been placed along the length of the office space for purposes of preparing International's design drawing with 48" partition panels that had been placed perpendicular to the 66" panels. With this new configuration, the International bid fits into the gross dimensions of the HRS office space without any loss of work space or cabinet space as a result of the reconfiguration. 3/ However, International's Shaw/Walker product has partition panels that are 3" thick. (The ITB calls for partition panels that are at least 2" thick. See Finding Of Fact 15, below.) At least in part for that reason, International cannot fit as much Shaw/Walker furniture into the HRS office space as specified in the HRS design drawing. To fit the Shaw/Walker product into the space, International substituted 42" corner desk tops for the 48" corner desk tops specified in the Technical Specifications of the ITB in 36 of the 60 office cubicles in the design drawing. This results in a loss of 6" of desk top on either side of those corner desk tops, a total of 6 square feet of desk top in each affected cubicle, and reduces the size of those 36 office cubicles from 64 to less than 58 square feet. Neither Executive nor Perdue had to vary from the Technical Specifications, and they will be able to duplicate the HRS design drawing without losing desk top surface area or office cubicle square footage. If it knew it could have put together an acceptable bid offering less work space, Perdue could have done so at a lower cost and therefore at a lower bid price. Under the ITB, the dimensions of the individual components were nominal, but the assembly of components to reproduce the overall dimensions of the furniture plan on the HRS design drawing was a mandatory bid specification. Although it was the lowest in price, International's bid must be disqualified as unresponsive. As between Perdue and Executive, Executive made the lower bid by only approximately $235, $228,000 to $228,235.36. However, Executive's bid departs from the Technical Specifications in several significant respects. The Special Bid Conditions of the ITB provides in pertinent part: SYSTEM QUALITY - BRAND NAMES: It is the intent of the solicitation that the successful bidder provide modular furnishing comparable-in quality to: Haworth Steelcase Shaw/Walker HRS approved equivalent The department considers that the above furnishings establish standards for comparison and identify levels of quality for design of materials, methods of fabrication and assembly. The department retains the right to determine the acceptability of systems not mentioned above. Bidders proposing systems and components as alternates to those identified above must submit a request for pre-qualification to include complete descriptive literature and a list of current installations. (Emphasis added.) Executive pre-qualified the Westinghouse Furniture Systems' Wes Group product which it bid. The Westinghouse furniture generally is comparable in overall quality to the three specified products -- Haworth, Steelcase and Shaw/Walker. However, the Haworth, Steelcase and Shaw/Walker products were specified not only because of their overall quality but also because HRS, through its consultant, understood that they would meet the requirements of the Technical Specifications of the ITB. The ITB does not state or suggest that its Technical Specifications are waived by pre-qualification of an "equivalent" product. HRS had several major concerns, in addition to the furniture design or floor plan, in putting this project out for bid. Due to the number of people who would be doing primarily telephone work in an open office environment, one primary concern was for high quality acoustical panels. Under "Power And Communication Panels," the Technical Specifications of the ITB state in pertinent part: Acoustical fabric panels shall maintain a Noise Reduction Coefficient (NRC) rating of .90 or greater and an STC rating of at least 29. The higher the acoustical rating of a partition panel, the higher its cost. Therefore, if a bidder could reduce the acoustical rating, it could afford to make a more price competitive bid. For that reason, Perdue telephoned HRS' consultant before submitting its bid to ask if the acoustical rating was "critical" and was told that it was. Perdue bid Steelcase product, including partition panels that conform to the requirements of the Technical Specifications instead of its lower cost, lower rated panels. Executive bid partition panels with an NRC rating of only .80 and an STC rating of only 27. Another major concern of HRS was for quality, durable construction so that HRS could expect to get years of satisfactory use of the furniture system it was purchasing. For this reason, the "Power And Communication Panels" section of the Technical Specification also provides in part: "All panels shall have a minimum 2" all-steel frame." Steelcase partition panels meet the specification; Westinghouse panel frames are only 1 1/2" thick. HRS also wanted to be sure that the office furniture system it was purchasing would be able to accommodate the need for its Abuse Registry personnel to work with a variety of electrically-operated equipment, including computer equipment. Under "Electrical Panels," the Technical Specifications of the ITB provide in pertinent part: "Panels shall have the capability of distributing four 20 amp circuits, one isolated; UL listed." The Westinghouse panels Executive bid have the capability of distributing only three 20 amp circuits (without additional electrical components.) Meanwhile, Perdue's bid meets this specification, too. When Perdue telephoned to inquire about the acoustical specification, it also asked if this electrical specification was critical, and the HRS consultant confirmed that it was. Therefore, Perdue bid higher priced panels that meet the specifications instead of lower priced panels comparable to the Westinghouse panels Executive bid. Both Perdue's and Executive's bid had some other minor non- conformities. Perdue's Steelcase overhead cabinets operate by a nylon glide with metal scissor hinge instead of by a ball bearing hinge, as specified, and its panel tackboards are 15 1/2" x 30" instead of 24" x 30", as specified. But Executive's Westinghouse partition panels have adjustable glides on the post by which the panels are connected instead of two adjustable glides on each panel, as specified (assuming panel-to-panel connections). Because it does not meet critical aspects of the Technical Specifications of the ITB, the Executive bid must be disqualified as unresponsive. The Haworth bid also was responsive but was for approximately $270,000, far above the others. Perdue's bid, as the lowest responsive bid, should be awarded the contract.
Recommendation Based on the foregoing Findings Of Fact and Conclusions Of Law, it is recommended that the Department of Health and Rehabilitative Services enter a final order (1) granting the bid protests of both International and Perdue insofar as they protest the award of HRS Bid 88-32BC to Executive on the ground that the Executive bid is unresponsive, (2) denying the International protest insofar as it seeks the award of HRS Bid 88-32BC on the ground that it too is unresponsive, and (3) granting the bid protest of Perdue also insofar as it seeks the award of HRS Bid 88-32BC because Perdue is the lowest responsive bidder. RECOMMENDED this 27th day of January, 1988, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of January, 1988.
The Issue The issue in this case is whether the bid specifications, together with other applicable authority, require that a bid, in order to be responsive, contain any written list of subcontractors.
Findings Of Fact On September 26, 1989, Respondent issued a document entitled, Specifications for Replacement of Air Conditioning, West Orange High School, Winter Garden, Florida, Engineers Project No. 89-016. As amended by three addenda, the above-described specifications shall be referred to as the "ITB." Respondent duly advertised for bids ore September 26, October 3, and October 10, 1989. The advertisement did not state that Respondent reserved the right to waive minor irregularities. In response to the ITB, Florida Mechanical, Inc. ("FMI") and B & I Contractors, Inc. ("B & I") timely submitted bids. For the base work and alternate 1, which Respondent ultimately decided to select, FMI bid $1,439,000, B & I bid $1,438,000, and a third bidder, S. I. Goldman, Company bid $1,621,000. These bids are recorded on a Bid Tabulation Sheet prepared by the engineer retained by Respondent for the project. The Bid Tabulation Sheet contains eight columns. Four columns record bid amounts for the base work and various alternates. The remaining columns are entitled, "Bidder," "Bid Bond," "Addenda," and "Subs." Each of the three bidders were named in one of the rows beneath the "Bidder," column. Each bidder had one "X" in its "Bid Bond" column and three "X"s in its "Addenda" column. However, only FMI and S. I. Goldman Company had "X"'s in their "Subs" columns. By resolution adopted on November 29, 1989, Respondent directed that all bids were rejected and that the Superintendent would correct any ambiguities and uncertainties in the ITB and solicit new bids. The resolution noted that Respondents staff had recommended that, if any bid were accepted, it should be that of B & I. However, [FMI] submitted with its bid a list of Major Sub-contractors of the form displayed in the [ITB], and B & I did not submit wish its aid a list of Major Sub-contractors[.] The resolution concluded that Respondent based on advice of staff and counsel, found that the [ITB is) ambiguous and/or uncertain as to whether or not a bidder must submit along with his bid a list of Major Sub-contractors, (b) that because of such ambiguity and/or uncertainty, it would be unfair and/or improper for [Respondent] to accept either of the bids received by it, and (c) that as a result thereof [Respondent] should reject all bids received by it for ,the Project and should solicit new bids for the Project as soon as is reasonably feasible after correction by [Respondents] staff of any ambiguity and uncertainty as aforesaid in the [ITB]. FMI and B & I each timely filed a notice of intent to protest and formal written protest of Respondent's decision to reject each company's respective bid. S. I. Goldman did not protest the decision and is not a party to the subject case. At a meeting on December 12, 1989, Respondent elected to refer the bid protests to the Division of Administrative Hearings for a formal hearing., At the beginning of the hearing, the parties filed a written stipulation, which stated that the only issue for determination was which Petitioner should be awarded the contract and not whether Respondent should seek further bids or award the contract to another bidder. The stipulation also stated that the Petitioners and Respondent agreed to abide by the recommendation of the hearing officer. At the hearing, the parties further stipulated that the sole issue for determination is whether the ITB, together with other applicable authority, required that the responsive bid contain any written list of subcontractors. In addition, the parties stipulated that both Petitioners had standing and the protests were timely and sufficient. The ITB requires that each bidder familiarize itself with all federal, state, and "Local Laws, ordinances, rules, and regulations that in any manner affect the work." Under the section entitled, "Preparation and Submission of Bids," the ITB states: "Each bidder shall use the Bid Form that is inserted herein, and may copy or reproduce the form on this own letterhead." Among other requirements, the ITB requires two bonds. The first is a "bid guarantee" of at, least five percent of the amount of the bid. The form of this guarantee may be cash or a Bid Bond." The other bond described in the ITB a 100% public construction bond. The surety on this bond must have been admitted to do business in Florida, must have been in business and have a record of successful continuous operation for at least five years, and must have at least a Bests Financial Rating of "Class VI" and a Bests Policyholder Ration of "A." The Bid Form contained in the ITB is two pages. Among other things, the Bid Form requires that the bidder receiving written notice of acceptance of its bid must provide the prescribed payment and performance bond and execute the contract within ten days after notification. The next document in the ITB is a single page entitled, "Form of Bid Bond." The provisions on this page identify the A.I.A. document to use and state that the Bid Bond "shall be submitted with the Bid Proposal Form." The next document in the ITB is a single page entitled, "List of Major Subcontractors." The List of Major Subcontractors states: Bidders shall list all major subcontractors that will be used if a contract is awarded. Additionally, bidders shall identify in the appropriate box whether or not that trade specialty is minority owned. Another paragraph defines minority ownership. The remainder of the form consists of ten rows for the "bidder" and nine major subcontractors, such as concrete, electrical, HVAC, and controls, and blanks where the bidder can indicate which of these entities are minority owned. The next document in the ITB is the Owner-Contractor Agreement, which is followed by tie Form of Construction Bond, General Conditions, and Supplementary General Conditions. Section 7.11 of the Supplementary General Conditions establishes certain requirements to be performed after the submission of bids. This section provides: Pre-Award Submittals: Before the Contract is awarded the apparent low bidder shall provide the following information to the owner. A copy of the Contractors current State of Florida General Contractor's or Mechanical Contractors License. Pre-Construction Meeting. After the Notice to Proceed and within eight (8) business days of the Owner [sic], the Contractor shall meet with the Owner, Engineer and Subcontractors that the Owner may designate... The Contractor shall provide the following to the Owner. * * * 2. A written list of all Subcontractors, material men and suppliers with such information as requested by the Owner or Engineer. * * * The remaining documents in the ITB are the technical specifications for the job. The three addenda supply additional technical information not relevant to this case. Respondent has promulgated rules with respect to the bidding process ("Rules"). The ITB does not refer to the Rules, which define and use many terms that are found in the ITB. For instance, Rule 1.1.25 defines the phrases, "Performance and Payment Bond," which is the same phrase used in the Bid Form in the ITB. The Rules define several other capitalized terms that are also used in the ITB, such as Bid Bond, Bid Guarantee, Bidder, and Contractor. Rule 4.1 similarly states that the bidder is familiar with federal, state, and "Local Laws, Ordinances, Rules and Regulations that in any manner affect the Work." Rule 6.1 describes the process by which a bidder is to prepare and submit bids and the Bid Guarantee in language similar to that contained in the ITB. Rule 6.2 discusses the listing of subcontractors. Rules 6.2.1 and 6.2.2 state: General Contractor shall include as an integral part of his bid a List of Subcontractors he proposes to use. The Bidder shall enclose this list in a 4" x 9" envelope, sealed and marked "List of Subcontractors" and identified ... The Bidder shall enclose said envelope with his bid proposal in the mailing envelope. The List of Subcontractors enclosed with tee Proposal of each Bidder will be examined by the ... Engineer before the Proposal is opened and read. In the event that the form is not properly executed and signed, the Proposal of that Bidder will be returned to him unopened... Rule 6.3 requires a Statement of Surety as another "integral part" of each bid. Rule 6.3.3 states: The Statement of Surety will be opened examined by the ... Engineer prior to the opening of the Proposal.... Although similar to Rule 6.2, Rule 6.3 lacks the warming that if the Statement of Surety is not "properly executed and signed, the Proposal of that Bidder will be returned to him unopened." Rule 19.1 sets forth the requirements, for the surety. These requirements are different than those set forth in the ITB. Rules 19.1.1 and 19.1.2 require, as does the ITB, that the surety be admitted to do business in the State of Florida and shall have been in business and have a record of successful continuous operations for at least five years. However, Rule 19.1.1 requires that the surety be represented by a reputable and responsible surety bond agency licensed to do, business in the State of Florida and have a local representative in the Orlando area. Rule 19.1.3 requires minimum Bests ratings of "A" in "management," and, as to "strength and surplus," "AAA+" in financial rating and $12,500,000 minimum surplus. Rule 19.1.3.3 also requires that the surety be listed on the U.S. Treasury Departments Circular 570. The bids of FMI and S. I. Goldman Company contained a completed List of Major Subcontractors. The bid of B & I did not. No bidder included a Statement of Surety with its bid.
Recommendation Based on the foregoing, it is hereby RECOMMENDED that the School Board of Orange County enter a Final Order awarding the subject contract to Florida Mechanical, Inc. ENTERED this 15th day of February, 1990, in Tallahassee, Florida. ROBERT E. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of February, 1990. APPENDIX Treatment Accorded Proposed Findings of FMI All of FMI's proposed findings have been adopted or adopted in substance. Treatment Accorded Proposed Findings of B & I 1-4: adopted or adopted in substance. 5: adopted, except that the staff recommended that, if the bid was to be awarded, that it be awarded to B & I. 6: adopted in substance. 7: rejected as conclusion of law and, to the extent fact, subordinate. 8-12: rejected as subordinate. 13-16: adopted or adopted in substance. 17: rejected as subordinate. 18: rejected as unsupported by the greater height of the evidence. 19-21: rejected as subordinate. 22: rejected as beyond the scope of the issues and irrelevant in view of the stipulation. In the stipulation, the parties agreed that the issue to be addressed would not be whether the intended agency action of Respondent was lawful (i.e., not arbitrary, fraudulent, dishonest, or otherwise improper), but rather whether the ITB, together with other applicable authority, required that the responsive bid contain any written list of subcontractors. COPIES FURNISHED: James L. Schott, Superintendent The School Board of Orange County, Florida P.O. Box 271 Orlando, FL 32802 Charles Robinson Fawsett, P. A. Shutts & Bowen 20 North Orange Avenue Suite 1000 Orlando, FL 32801 James F. Butler, III Smith, Currie & Hancock 2600 Peachtree Center Harris Tower 233 Peachtree Street, N.E. Atlanta, GA 30043-6601 William M. Rowland, Jr., Esq. Rowland, Thomas & Jacobs, P.A. 1786 North Mills Avenue P.O. Box 305 Orlando, FL 32803
Findings Of Fact In August 1985, the Department issued a Request for Proposal (RFP), State Project Number RFP-DOT-85-06, for a demonstration bonding assistance program. The program was authorized in 1985 by Congress, using Federal Highway Administration funds, to assist economically and socially disadvantaged business enterprises (DBEs) to meet the bonding requirements mandated on public works projects, and thereby increase their participation in the bid process. Consistent with existent agency policy, and Section 287.057(16), Florida Statutes, the RFP provided: A selection committee of at least three members will be established to review and evaluate each proposer's response to this Request for Pro- posal and subsequently decide the preference order of the proposers. In response to the RFP, the Department received six proposals. The evidence established that it is Department policy to submit the proposals to a "technical review committee," comprised of three members for evaluation of the technical responsiveness of the proposals, and to an employee of the Department's Bureau of Contractual Services to evaluate the cost responsiveness of the proposals. In this case, the proposals were submitted to a "technical review committee" consisting of two members and to an employee of the Department's Bureau of Contractual Services. The "technical review committee" separately evaluated and scored the technical responsiveness of each proposal, and reported their scores to an Operations and Management Consultant, with the Department's Bureau of Minority Programs. 1/ The Consultant did not evaluate the proposals. He merely averaged the scores of the two members of the "technical review committee," added the cost responsiveness of the proposals received from the Department's Bureau of Contractual Services, and prepared a summary evaluation package for the "Selection Committee." The evaluation package ranked the proposals by score. The "Selection Committee" consisted of the Department's Secretary (Thomas E. Drawdy), Deputy Assistant Secretary (Mel Hilliard), and Director of the Division of Administration (Bruce Gordon). Mr. Gordon, based on the scores set forth in the evaluation package, recommended, and the Committee concurred, that Boone's proposal be accepted. Mr. Gordon did not review any of the proposals submitted in response to the RFP. Kenneth L. Sweet, one of the evaluators on the "technical review committee," is an engineer for the Department's Bureau of Construction. While steeped with a broad range of technical and engineering experience, Mr. Sweet lacked knowledge of the requisites to successfully secure a bonding commitment.
The Issue At issue in this proceeding is whether the Department of Environmental Protection's decision to reject all bids submitted for the project entitled BDRS 52-01/02 was illegal, arbitrary, dishonest, or fraudulent.
Findings Of Fact Parties Petitioner, All America Homes of Gainesville, Inc. (All America), is a corporation doing business in the State of Florida. All America submitted a timely written bid in response to the Department's ITB and filed timely protests to the Department's actions. The Respondent, the Department of Environmental Protection, is an agency of the State of Florida which manages and operates state parks under its jurisdiction, and solicits construction projects in state parks, pursuant to Chapter 258, Part I, Florida Statutes, through its Division of Recreation and Parks, Bureau of Design and Recreation Services. The ITB In November, 2001, the Department issued an ITB on a construction project entitled Hillsborough River State Park Concession Building, project number BDRS 52-01/02. The ITB included the Bid Specifications for the project. Bids were required to be submitted no later than 3:30 p.m. on Tuesday, December 18, 2001, at the Bureau's Tallahassee, Florida, office. The written Specifications define several terms, including, but not limited, to the following: ADDENDUM: A written explanation, interpretation, change, correction, addition, deletion, or modification, affecting the contract documents, including drawings and specifications issued by the OWNER [Department] and distributed to the prospective Bidders prior to the bid opening. ALTERNATE BID: Separate optional bid item for more or less project requirement used for tailoring project to available funding. Also may consist of alternate construction techniques. BASE BID: Formal bid exclusive of any alternate bids. BID FORM: The official form on which the OWNER requires formal bids to be prepared and submitted. ORAL STATEMENTS: Verbal instruction. NOTE: No oral statement of any person, whomever shall in any manner or degree modify or otherwise affect the provisions of the contract documents.[1] SEALED BID: The formal written offer of the Bidder for the proposed work when submitted on the prescribed bid form, properly signed and guaranteed. The Bid Specifications also contained the following relevant sections: Alternatives If the OWNER wishes to learn the relative or additional construction cost of an alternative method of construction, an alternative use of type of material or an increase or decrease in scope of the project, these items will be defined as alternates and will be specifically indicated and referenced to the drawings and specifications. Alternates will be listed in the bid form in such a manner that the Bidder shall be able to clearly indicate what sums he will add to (or deduct from) his Base Bid. The OWNER will judge for himself that such alternates are of comparable character and quality to the specified items. The Order of the alternate may be selected by the Department in any sequence so long as such acceptance out of order does not alter the designation of the low bidder. ADDENDA If the Consultant[2] finds it would be expedient to supplement, modify or interpret any portion of the bidding documents during the bidding period, such procedure will be accomplished by the issuance of written Addenda to the bidding documents which will be delivered or mailed by the OWNER'S Contracts section to all bidders who have requested bidding documents. Interpretation No interpretation of the meaning of the drawings, specifications or other bidding documents and no correction of any apparent ambiguity, inconsistency or error therein will be made to any Bidder orally. Every request for such interpretation or correction should be in writing, addressed to the Consultant. All such interpretations and supplemental instructions will be in the form of written Addenda to the bidding documents. Only the interpretation or correction so given by the Consultant in writing and approved by the OWNER shall be binding, and prospective Bidders are advised that no other source is authorized to give information concerning, or to explain or interpret, the bidding documents. B-16 Bid Modification Bid modification will be accepted from Bidders, if addressed as indicated in Advertisement for Bids and if received prior to the opening of bids. No bid modification will be accepted after the close of bidding has been announced. Modifications will only be accepted if addressed in written or printed form submitted with the bid in sealed envelopes. Telegrams, facsimiles, separate sealed envelopes, written on printed modifications on the outside of the sealed envelopes will not be accepted. All bid modifications must be signed by an authorized representative of the Bidder. Modification will be read by the OWNER at the opening of formal bids. B-21 Rejection of Bids The OWNER reserves the right to reject any and all bids when such rejection is in the interest of the State of Florida, and to reject the bid of a bidder who the OWNER determines is not in a position to perform the work. B-23 Award of Bid . . .The qualified Bidder submitting the lowest bid will be that Bidder who has submitted the lowest base bid plus any selected alternates. . . . The OWNER reserves the right to waive any minor irregularities in bids received when such waiver is in the interest of the OWNER. The Award of Bid will be issued by the OWNER only with responsible Bidders, found to meet all requirements for Award of Bid, qualified by experience and in a financial position to do the work specified. Each bidder shall, if so requested by the OWNER, present additional evidence of his experience, qualifications and ability to carry out the terms of the Agreement. (Emphasis in original, except for Section B-10.) The Bid Form is included with the Specifications and provides in part: Base Bid: Furnish labor, equipment, Lump Sum $ supervision and material to construct a new concession building of 2940 square feet located at the Hillsborough River State Park along with the alteration of the existing concession building according to plans and specifications. Alternate #1: Furnish labor, equipment, Add Amt.$__ supervision and material to renovate the existing concession building according to plans and specifications. There is a separate section for "Allowances," i.e., Section 01210, for the Hillsborough State Park. This section provides in part: SECTION 01210 – ALLOWANCES * * * 1.2 SUMMARY This Section includes administrative and procedural requirements governing allowances. Certain materials and equipment are specified in the Contract Documents and are defined by this [sic] specifications as material and labor to be provided against a pre-determined allowance. Allowances have been established in lieu of additional requirements and to defer selection of actual materials and equipment to a later date when additional information is available for evaluation. If necessary, additional requirements will be issued by Change Order. * * * 3.3 SCHEDULE OF ALLOWANCES A. Allowance #1: Include in the base bid an allowance for the purchase and installation of. . . kitchen equipment. . . . The total dollar amount of the allowance to be included shall be $12,000.00. There is also a separate section for "Alternates," i.e., section 01230, for Hillsborough River State Park, which provides in part: SECTION 01230 – ALTERNATES * * * 1.3 DEFINITIONS Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the Bidding Requirements that may be added to or deducted from the Base Bid amount if OWNER decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate alternate into the Work. No other adjustments are made to the Contract Sum. . . . . 3.1 SCHEDULE OF ALTERNATES A. Alternate No. 1: Renovate the existing concession building in its entirety as shown in the drawings and specified herein. (emphasis added.) At this stage of the bidding documents, the contractor/bidder is requested to provide a Base Bid/Lump Sum on the Bid Form to "[f]urnish labor, equipment,. . .to construct a new concession building," and to provide an additional and separate amount for Alternate No. 1 to "[f]urnish labor, equipment, . . . to renovate the existing concession building." On December 13, 2001, the Bureau issued "Addendum No. One (1)" (written by the architect) to the ITB on the "Hillsborough River State Park – Concession Building." The Addendum contained the following relevant sections: Specification Section 01210: Allowances Add the following new paragraph 3.3.B: ”Allowance #2: Include in the base bid an allowance for the renovations of the existing concession building; renovations shall be defined by the Owner. The total dollar amount of the allowance to be included shall be $25,000." Specification Section 01230: Alternates Modify paragraph 3.1.A. as follows: "Alternate No. 1: Renovate the existing concession building as defined by the Owner, and as provided for under Section 01210, Allowances." (emphasis added.) Each contractor was required to sign the Addendum and attach it to the bid. By definition, and pertinent here, an addendum is an additional written instruction to a contractor during the bidding process. Based on the weight of the evidence, the purpose of this Addendum was to require the contractor to include a $25,000.00 Allowance (for Allowance # 2) in the Base Bid, for the work which might be performed if the Department requested the work to be performed for Alternate No. 1, i.e., for the renovation of the existing concession building.3 (The Department's architect decided it would cost approximately $25,000.00 to renovate the existing concession building, hence Allowance # 2.) In other words, the Addendum does not have a specific dollar amount to be included for Alternate No. 1. Rather, the $25,000.00 is an Allowance for the work described as Alternate No. 1, but the amount is to be included in the Base Bid and not as a separate line item, dollar amount. But, importantly, the Addendum did not delete the potential work to be performed as described in Alternate No. 1, although Mr. Bowman and others believed that the Addendum deleted Alternate No. 1. It deleted the necessity to place a specific dollar amount on the Bid Form for Alternate No. 1. (Mr. Bowman is a registered Professional Engineer and a licensed contractor. He has worked for the Department for 15 years and has served as Bureau Chief for two years. He supervises the contract section and the design section, which was responsible for preparing the technical plans and specifications and bidding out the job.) Mr. Bowman offered the following explanation why he believed the Addendum was confusing: Okay. I think the confusion that was created, you know, I think the addendum in itself, you know, said add $25,000 to the base bid, but then on the bid form, it still had the space down there for alternate number one, which alternate number one, which alternate number one had become $25,000 that was to be allowed for the concession building, and I think that's where the confusion came in because I think they were still confused, that they weren't really sure that they should not put that 25 down there but they knew they had been told in the addendum to do it and I think that's the reason for the notes and we got to the correspondence on the bid form, was they wanted to make sure that that's what we were wanting to do. And I think that's where the confusion came in. Like I said, it's always, if you could go back and do it again, it would be much wiser just to issue a whole new bid form and then we wouldn't be here today. But, we didn't do that. Okay. So, that's why we are here. The language in this Addendum, when read with the original Bid Specifications, apparently caused confusion with some of the bidders on the project. Several bidders called Marvin Allen (an architect and project manager for the Department's Bureau of Design and Recreation Services) prior to the submission of the bids, to clarify how the $25,000.00 Allowance should be shown on the Bid Form. (Mr. Allen did not author any of the specifications, including the Addendum.) He was listed as a contact person. He did not contact any bidders. But, Mr. Allen recalled telling each bidder who asked that the Allowance of $25,000.00 should be included in the Base Bid. But, he does not recall the names or numbers of the bidders who called, "possibly" three, four or five. Mr. Allen believed the Addendum was clear. According to Mr. Allen, the bidders who called him found the Addendum confusing. The oral responses to the bidders can be construed as interpretations of the Addendum. However, pursuant to Section B- 10 of the Specifications, any such interpretations were required to "be in the form of written Addenda to the bidding documents." Also, any such questions should have been in writing. If Section B-10 were complied with, all bidders would have been potentially on the same footing, or, at the very least, would have had access to a written clarifying document. Opening of the Bids On December 18, 2001, the bids were opened by Mike Renard, Contracts Manager with the Bureau of Design and Recreation Services, and Susan Maynard, Administrative Assistant. Mr. Dwight Fitzpatrick, a representative of All America, also attended the bid opening. The Bid Form submitted by Nelco showed a Base Bid of $355,478.00 (Lump Sum $355,478.00), and also showed an amount of $25,000.00 on the Alternate # 1 line (Add Amt. $25,000.00). See Finding of Fact 6. (It was clear to Mr. Renard that the $25,000.00 should have been included on Nelco's Base Bid. But Mr. Renard believed that Nelco submitted a responsive bid because the Department only accepted the Base Bid. Mr. Bowman agreed.) Nelco was the only one of five bidders to have a dollar amount in the Alternate #1 line under "Add Amt. $ ." All America submitted the second lowest Base Bid of $362,000.00. There was also a hand-written note on the All- America Bid Form that stated: "Addenda # 1 instruction to place $25,000 allowance in both Base Bid and as alternate # 1." Another hand written note was located below the "Add Amt. $-0-" line: "amount added in Base Bid with $25,000 allowance per Marvin Allen." The Department considered All America's bid responsive. It is a fair inference that three out of five of the other Bid Forms contained language indicating that the bidders were relying on Addendum No. One by placing the $25,000.00 Allowance in the Base Bid.4 It is uncertain whether they did so in light of the instructions of Mr. Allen concerning how to complete the Bids Forms. However, given the nature of the calls to Mr. Allen, there is a reasonable inference that there was some confusion among some of the bidders. The Department determined that Nelco submitted the lowest Base Bid, but the Department's staff had a question as to whether Nelco had included the $25,000.00 in its Base Bid. After conferring with his superiors, Mr. Renard was instructed to call Nelco to make certain that its Base Bid included the Allowance amount ($25,000.00). Mr. Renard spoke with Steve Cleveland, Nelco's Project Manager, "to verify the fact that [Nelco] had the allowance in their base bid." Mr. Cleveland orally confirmed that Nelco's Base Bid included the $25,000.00 Allowance. Mr. Renard asked Mr. Cleveland to send him a letter verifying this statement. Mr. Renard viewed this inquiry as a request for clarification or verification, not an opportunity for Nelco to modify its bid. Mr. Bowman agreed. (Mr. Renard did not believe Addendum No. 1 was confusing.) In a letter dated December 20, 2001, Mr. Cleveland confirmed that Nelco’s Base Bid of $355,478.00 included the Allowance amount and that Nelco could still perform the contract if the $25,000 Allowance was removed from its Base Bid pursuant to the ITB, i.e., that Nelco would perform the contract for $355,478.00 less $25,000.00, or $330,478.00, if the Department did not accept Alternate # 1 and the Allowance. (An alternate does not have to be accepted by the Department.) According to Mr. Renard, Mr. Cleveland never mentioned modifying, changing, or altering Nelco's bid. The Department only accepted the Base Bid for each bid. Mr. Renard did not consider it unusual to call a bidder or contractor to verify information to determine whether they can or cannot perform the work at the stipulated price. He considered it common to make this inquiry. Also, it was common in Mr. Bowman's experience to call a bidder to get clarification. Mr. Renard was not aware of any statute or rule which authorizes the Department to request clarification from a bidder after the bids are opened. Mr. Renard was more familiar with the bid forms than Mr. Allen. After receiving Mr. Cleveland's letter, the Department determined that Nelco submitted the lowest Base Bid and that the $25,000.00 amount that Nelco wrote on the Bid Form Alternate # 1 line, was a minor irregularity in the bid which the Department, as the Owner, could waive pursuant to the ITB. On December 20, 2001, the Department posted the Tabulation of Bids showing the anticipated award of the contract to Nelco. At the hearing, an unsigned letter on Department letterhead was introduced, which was addressed to Nelco and stated that Nelco submitted the apparent low bid. However, Mr. Renard testified that these letters are prepared routinely, but not mailed out without his signature. Mr. Renard did not recall signing the letter or ever sending out such a letter to Nelco. On December 21, 2001, the Department received a Notice of Intent to Protest letter from Allen E. Stine, the President of All America. In his letter, Mr. Stine stated that Nelco’s bid should have been rejected for failure to follow the specified format as per Addendum No. 1, or adjusted to have the $25,000.00 amount added to their Base Bid. Bid Protests All America filed a written formal bid protest on January 4, 2001. On January 9, 2001, Cindy Otero of All America, notified Mr. Renard by letter, and stated that Mr. Stine was available for a hearing regarding the bid protest. On January 28, 2002, Mr. Renard returned All America's check for the bond, stating that it was unnecessary. Mr. Stine recounted a number of unanswered telephone calls after the first protest was filed. During one conversation, Mr. Renard recalled Mr. Stine saying to him, "You can't do this, you can't do this." After receiving the first formal protest, the Department staff consulted with legal staff and reviewed the documents and bid procedures. Based on the number of questions received concerning the Addendum and the hand-written notes on several of the bid forms, Mr. Bowman, Bureau Chief, determined that the bid documents were confusing and ambiguous. (Mr. Bowman stated that this was their first bid protest in his 15 years with the Department.) Therefore, Mr. Bowman decided that it would in the best interest of the State of Florida to reject all of the bids pursuant to the Bid Specifications. Mr. Bowman felt that the ITB should be re-written in order to make it clearer and allowing all of the bidders to re-bid the project without any confusion or ambiguity. Mr. Stine stated that his "senior estimator" told him that the bid language "could be confusing." He and his "senior estimator" had a discussion about whether the Allowance should have been placed in the Base Bid or not. At the time of submission of All America's bid, Mr. Stine was clear that the Allowance should be placed in the Base Bid, especially after calling Mr. Allen. But, his senior estimator was not so clear. In order to appease him, Mr. Stine placed the hand-written note on All America’s proposal. Mr. Stine essentially, "cleaned" up his proposal. At the hearing, Mr. Bowman testified Rule 60D-5.0071, Florida Administrative Code, see Conclusion of Law 59, does not list "confusing or ambiguous bid specifications" as one of the circumstances allowing for the rejection of all bids. However, Mr. Bowman later stated during the hearing that he believed the circumstances listed in Rule 60D-5.0071 were not the only circumstances authorizing the Department to reject all bids. Mr. Bowman testified that he believed that general confusion among the bidders caused by the ambiguous ITB constituted sufficient grounds for rejecting all bids. Mr. Bowman was advised by legal counsel that rejecting all of the bids would probably result in another bid protest by Nelco, All America, or both. Thus, the Department decided to delay addressing All American’s first protest until after posting the rejection of all bids and receiving the subsequent protests, so that all of the protests could be resolved at once in an efficient and economical manner. Notwithstanding the Department's justifications for rejecting all bids and not proceeding on All America's initial protest, the record is unclear why the Department waited several months to reject all bids. On May 13, 2002, the Department posted the rejection of all bids. On May 16, 2002, the Department received a formal written protest of the rejection of all bids filed by All America. On May 17, 2002, Jerome I. Johnson, attorney for the Department, contacted Mr. Robert A. Lash, All America's counsel at the time, concerning the resolution of All America’s formal protest. (Before the final hearing, Mr. Lash, with All America's consent, withdrew as counsel for All America.) The parties agreed to suspend formal bid protest procedures until a meeting could be held between the parties in an attempt to resolve the protests. Mr. Johnson sent a letter dated May 21, 2002, to Mr. Lash confirming this conversation. On June 26, 2002, a meeting was held among the Department staff, legal staff, and Mr. Lash and Mr. Stine, representing All America. The parties were unable to resolve the protests. At the conclusion of the meeting, the parties agreed that formal protest procedures would not be implemented until Mr. Stine could confer further with his counsel. In a letter dated July 5, 2002, Mr. Lash stated that his client wished to proceed with formal protest procedures and requested an administrative hearing on the protests. Are the Specifications and Bid Documents Ambiguous and Was There Confusion? The parties stipulated that "[t]he Addendum language was confusing," notwithstanding the testimony of several witnesses that they were not confused. The Department's determination that the bid Specifications, including the Addendum, and the Bid Form, which remained unchanged after the Addendum was issued, were confusing and ambiguous, is supported by the weight of the evidence. This is particularly true regarding the Bid Form. The Addendum required the bidder to include an Allowance of $25,000.00 in the Base Bid for work described as Alternate # 1. But the Bid Form was unchanged to reflect the Addendum changes. The Bid Form retained a line for the bidder to submit an additional amount for Alternate # 1. Further, it appears that several bidders were confused, including, Mr. Stine, who spoke with Mr. Allen and requested and received clarification. Further, it is unclear whether all of the bidders, including Nelco, were aware of the oral interpretations or clarifications of the Addendum rendered to some of the bidders. Rejection of All Bids Based upon the foregoing, given the standard of review in this proceeding discussed in the Conclusions of Law, the weight of the evidence indicates that the Department's action, in rejecting all bids, was not illegal, arbitrary, dishonest, or fraudulent. The Department's staff was well-intended and made some mistakes along the way, e.g., by not changing the Bid Form, which they readily admit. But there was a rationale for rejecting all bids under the circumstances.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department issue a final order dismissing All America’s Petition to Prevent Rejection of Bids and Award Contract to Petitioner and denying All America's request for attorney’s fees and costs. DONE AND ENTERED this 24th day of September 2002, in Tallahassee, Leon County, Florida. CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of September 2002.
The Issue The issue in this cause is whether costs and attorney's fees are due Petitioner, hereinafter PROCTOR, from Respondent, hereinafter HRS, pursuant to Section 57.111, Florida Statutes, as a result of Division of Administrative Hearings Case Number 91-5963-BID, and, if so, the amount of costs and fees.
Findings Of Fact The petition for fees and costs herein is brought exclusively under Section 57.111, Florida Statutes, and relates back to a bid protest wherein PROCTOR and TCC #3 LTD., INC., hereafter TCC, were the only bidders on HRS lease 590.236. PROCTOR was the protestant/Petitioner and TCC was the apparent successful bidder/Intervenor in Derick Proctor v. Department of Health and Rehabilitative Services, DOAH Case No. 91-5963BID. HRS' Invitation to Bid (ITB) for lease 590:236 required bidders to submit evidence of control of the property being offered, including the parking areas. Evidence of control could take the form of a deed for the property, an option to purchase the property, or a lease or option to lease showing a right to sublease. TCC did not submit a document labelled "deed," "option to purchase," "lease," or "option to lease" with its bid. TCC submitted as its evidence of control a contract for sale and purchase of the property with Hernando Plaza, Ltd., executed by Edward M. Strawgate and Harold Brown representing themselves to be general partners of the limited partnership. At all times material, the actual record title of the property submitted by TCC for the bid was in the Victor and Lillian Brown Foundation. At the times of the bid opening, evaluation, and August 27, 1991 notice of intended award, HRS had no reliable information as to what entity actually owned the property offered by TCC, and TCC had not disclosed to HRS that its contract to purchase the property was with an entity other than the record owner. Up to then, at least, Hernando Plaza, Ltd. had represented itself to TCC as being the owner of the property. The ITB did not require an abstract of title to be submitted with the bid. HRS normally does not require an abstract from successful bidders, although the ITB contained provisions for future disclosures from successful bidders. Absent some reason to "go behind" facial evidence of control, HRS' ITB attempted at the time to protect HRS by requiring successful bidders to post an irrevocable letter of credit to be forfeited in the event a successful bidder could not perform and for future disclosures concerning the chain of title. (See the recommended order in the underlying case). HRS accepted the contract to purchase the property from Hernando Plaza, Ltd. as TCC's required evidence of control, believing it to constitute an option to purchase. (See Findings of Fact 15-17 infra, this final order). On August 27, 1991, PROCTOR received from HRS a notice of intent to award the bid to TCC. This notice constituted the "window" for protests, if any, to be filed. PROCTOR then timely filed a notice of intent to protest and a formal written protest of the award to TCC. The filing of this protest resulted in an automatic suspension of the bid solicitation and contract award process and referral of the matter to the Division of Administrative Hearings, pursuant to Section 120.53(5)(c), Florida Statutes. This protest formed the basis of the underlying bid case, DOAH Case No. 91-5963BID. No later than the time of the Prehearing Order of September 23, 1991 in Case No. 91-5963BID, the law firm of Gibbs and Rudzik had made known to the hearing officer and counsel for both PROCTOR and HRS its retention as counsel for TCC. TCC moved for leave to intervene in a motion filed September 30, 1991, which was granted in an order of October 4, 1991. In a letter of October 10, 1991, counsel for PROCTOR made counsel for HRS aware of a question of whether TCC could obtain good title to the property. Counsel for PROCTOR proposed in a letter of October 14, 1991 to counsel for HRS that HRS reject both PROCTOR's and TCC's bids and rebid the lease, but this letter was primarily devoted to determining if HRS wished to interpose a new defense that PROCTOR's bid was unresponsive. In the instant fees and costs case, PROCTOR relies on its October 14, 1991 letter as the point from which HRS should have acted to avoid incurring attorney's fees and costs. After the receipt of the two letters, HRS did not reject both bids and rebid the contract but proceeded to formal hearing on October 30, 1991. PROCTOR and HRS share the mutual impression that had HRS accepted PROCTOR's proposal to reject both bids, HRS would have to have allowed TCC an opportunity to protest that decision. At the final hearing in Case No. 91-5963BID, evidence was offered that Hernando Plaza, Ltd. had a conditional option to purchase the property from the record title owner, the Brown Foundation. However, it was not established at the hearing that the conditions of the option had been fulfilled or that TCC or Hernando Plaza, Ltd. could otherwise gain good title to the property through a valid option. It was concluded as a matter of law in Case No. 91-5963BID, that on its face, the ITB stated that control could be evidenced merely by attachment of an "option to purchase," that the ITB stated no further requirements concerning the internal provisions of the option to purchase, and that TCC's conditional contract for purchase constituted a conditional option to purchase. The conditions of the option to purchase and the chain of title, among myriad other matters were subjects of proof at the formal hearing. The conditions of the option to purchase and various complicated real property concepts arising from recorded and unrecorded parts of the chain of title constituted the thrust of the recommended order's assessment that TCC's "control" was speculative only. It is here noted that the totality of the "chain" of title might have been unavailable even by "abstract" due to the lack of recordation of some documents. The lengthy formal hearing adduced evidence concerning the factual issue of whether or not the conditional option to purchase was between TCC and an entity which had such a sufficiently unequivocal interest in the proposed property that it could convey title to TCC in time for TCC to fulfill its obligations under its proposed lease to HRS. There is no evidence that HRS knew of these problems on August 27, 1991, when it gave notice of its intent to award the bid to TCC. Hernando Plaza, Ltd. was the entity with which TCC had contracted. At formal hearing, TCC relied on the legal concept that all interests in the property had merged in the non-title holder, Hernando Plaza, Ltd. This concept, together with recorded and unrecorded elements in the chain of title which were presented at formal hearing, were determined in the recommended order to be too "speculative" on the issue of TCC's control. However, it was also found, upon evidence submitted at formal hearing, that TCC's bid contained no other material deviations from the requirements of the ITB, that the signator of TCC's bid had sufficient status to submit the bid for the TCC corporation, and that TCC's signator could not submit the bid as an agent of the owners of the real property. TCC and its bid signator had never purported to have submitted the bid on behalf of the owners of the real property. (See the recommended order of the underlying bid case.) These issues were raised by PROCTOR and they addressed more than just the facial compliance of TCC's original bid documents which was all HRS had to consider when it made its initial decision in favor of TCC and against PROCTOR. However, the recommended order found HRS to have materially deviated in a number of ways from the bid process in its initial evaluation of PROCTOR's bid, not the least of which was determining that PROCTOR had complied with the ITB requirements for demonstrating control. All such evaluation flaws had been committed by HRS in favor of PROCTOR. Both TCC's and PROCTOR's bids were ultimately found to be unresponsive in the recommended order entered on December 20, 1991. The recommended order also found both had standing to be involved in the bid protest and formal hearing. The recommended order recommended rejecting both bids and readvertising the ITB. The Final Order of HRS entered on January 20, 1992 dismissed PROCTOR's protest on the basis that he lacked standing to protest, as his bid was unresponsive, and awarded the bid to TCC. HRS did not give PROCTOR notice that his bid was not responsive until it issued its Final Order. The Final Order of HRS was appealed to the First District Court of Appeals by PROCTOR. The First District Court of Appeals entered an order on June 22, 1992 finding PROCTOR had standing and remanding the case back to HRS for the purpose of a decision of the issue of whether TCC's bid was also unresponsive. On July 27, 1992, HRS entered its Amended Final Order determining both bids to be unresponsive and that the lease should be relet for bids. The First District Court of Appeals affirmed the Amended Final Order of HRS in a per curiam opinion without discussion on October 13, 1992. HRS did not reject both bids and rebid the contract until after this per curiam opinion. No motion for rehearing was filed with respect to either of the First District Court of Appeals' orders entered June 22 or October 13, 1992, nor was any notice to invoke the discretionary jurisdiction of the Supreme Court filed. PROCTOR did file a motion for rehearing solely on the court's denial of PROCTOR's motion for appellate fees. Mandate was issued by the Clerk of the First District Court of Appeals on December 3, 1992. HRS entered an Order Directing Release of Bid Protest Cost Bond on December 18, 1992, in which HRS stated: Petitioner, Derick Proctor, has prevailed in the above styled bid protest. Petitioner's domicile and principal place of business is Vero Beach, Florida. Petitioner has one employee. Petitioner is a sole proprietorship. Petitioner's net worth does not exceed $2,000,000.00. HRS was not a nominal party in the underlying bid case. HRS did not initially challenge PROCTOR's "small business party" status in this instant fees and costs proceeding. Therefore, that allegation of the fees and costs petition is not at issue. Also, Petitioner's "small business party" status is now stipulated to exist. The parties have stipulated that the maximum statutory fee is $15,000.00 and that $15,000.00 is a reasonable fee if an award of attorney's fees is due. HRS has not protested or objected to the amount of costs claimed, $411.25, if costs are due.