Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ROBERT J. NALI, 78-002103 (1978)
Division of Administrative Hearings, Florida Number: 78-002103 Latest Update: Jul. 12, 1979

The Issue Whether the certified general contractor's licenses and the registered roofing contractor's licenses held by Petitioner Robert J. Nali should be revoked.

Findings Of Fact The certified General Contractor's License number CG-C007395 and CG- CB07395, and the Registered Roofing Contractor's License number RC0028067, issued to Robert J. Nali are active and current. Respondent entered into a contract with Mr. Charles Rapp on June 1, 1977, to have a house constructed for the contract price of $29,500. The home was financed through the First Federal Savings and Loan Association of Leesburg for the sum of $27,730. Disbursed directly to Respondent Nali in five different draws was $16,638. These disbursements left a total of $11,092 in the bank account for completion of the home. Two bills remain unpaid, one for $500 and one for $560.92. Cost of the home was approximately $2,035.87 above the contract price. Two liens were filed against Mr. Rapp's property which were satisfied out of construction funds from the bank, one by Adobe Building Center, Inc., in the amount of $1,315 and one by Branch Garage Door Sales in the amount of $171.38. Respondent Nali admitted that the Kennedy Company supplied air conditioning duct work for the home, and that Yale Ogron Builders provided labor as a subcontractor; that he was paid for the supplies provided by the Kennedy Company on the second drawing, and for the labor provided by Yale Ogron Builders on the fourth draw. Respondent Nali admitted he did not pay these concerns although he did receive the funds for the material and labor supplied. Mr. Rapp fired Mr. Nali and completed the home himself. There was no date of completion in the contract, but Respondent did not actively pursue the completion. Respondent Nali entered into a contract with Mr. Charles Fosmoen in June of 1977, for the purpose of constructing a home. The contract price was $28,150. The home was financed through the First Federal Savings and Loan Association of Leesburg for the sum of $26,471. Disbursed to Nali under the contract was $19,845.75. The disbursement left a total of $6,625.25 to complete the house. Expended to complete construction of the home in accordance with the contract was $9,351.08, an excess of $2,725.83 of the contract price. A claim of lien was filed against the Fosmoen home by Lake Pre-Hung Door Manufacturing Company, Inc. Mr. Nali was fired from the job and, although no time was designated in the contract for completion, Respondent Nali did not actively pursue the construction of the home. A contract was entered into with Mrs. Ellen Haffey on November 16, 1977, to construct the shell of a home for the contract price of $17,600. Mrs. Haffey paid the sum of $10,000 directly to Respondent and expended a sum of $6,625.93 to complete the house as contracted. She has bills remaining unpaid in the amount of $3,620.50. Spent by Mrs. Haffey above the contract price was $2,648.43. Mrs. Haffey, a contractor, dismissed Mr. Nali, and the house is not yet completed. A claim of lien was filed against Mrs. Haffey's property on behalf of Leesburg Building Materials, Inc., in the amount of $4,384.47. The lien was for materials which had been delivered to the project site and should have been paid for out of the sum previously paid to Respondent. Mrs. Haffey paid $4,000 for the third draw instead of $6,000, as called for by the contract, a fact that prevented Respondent from timely payment of bills. A lien was filed on Mrs. Haffey's property by Keeman Brick of Central Florida, Inc., in the amount of $1,238.03. Respondent admitted he was charged with a criminal violation of misapplication of funds but pled nole contendere, and adjudication was withheld. A document entitled "Stipulation on Motion for Clarification and Modification" was received into evidence. The document constitutes an admission of Respondent that restitution was due from him to the complainants, Mr. and Mrs. Charles Rapp, Mrs. and Mrs. Charles Fosmoen, and Mrs. Ellen Haffey. Petitioner contends that Respondent diverted funds he had received to pay two subcontractors for the Rapp home; that although he may Waive underbid the Rapp and Fosmoen he later also underbid the Haffey contract, which caused these consumers inconvenience and loss and violated a contractor's position of trust. Respondent contends that he could have finished each of the houses within the contract terms, since time was not of the essence. He contended that increased building material costs contributed to the delay of the housing construction, and that he could have finished the houses were he not fired from each of the construction projects. Respondent denied that he had diverted any funds from construction projects. The Hearing Officer further finds: Both Mr. and Mrs. Rapp and Mr. and Mrs. Fosmoen gave Respondent Nali notice that they were dissatisfied because Mr. Nali was not actively finishing the construction of their respective homes. Both gave him notice and an opportunity to recommence active construction, which he did not resume; The dates of completion of homes were not specified in the contracts, but oral promises were given that the homes would be completed within a reasonable time. The delay caused each complainant much inconvenience; Liens were filed against these homes for nonpayment of bills. Respondent did not pay the liens; Each of the three homes cost more than the contracted price before said homes were completed by the parties contracting with Mr. Nali. Mr. Nali received money from Mr. Rapp for work and supplies provided by the Kennedy Company and Yale Ogron Builders, yet Respondent did not pay for these materials or work; and The complainants were justified in dismissing Respondent.

Recommendation Suspend the license of Respondent Robert J. Nali for a period of six months. DONE and ORDERED this 13th day of April, 1979, in Tallahassee, Leon County, Florida. COPIES FURNISHED: Michael Egan, Esquire 217 South Adams Street Post Office Box 1386 Tallahassee, Florida 32302 Joan L. Wollin, Esquire Post Office Box 236 Leesburg, Florida 32748 DELPHENE C. STRICKLAND Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32301 (904) 488-9675 ================================================================= AGENCY FINAL ORDER ================================================================= FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. DIVISION OF ADMINISTRATIVE HEARINGS, DOCKET NO. 78-2103 ROBERT J. NALI, Respondent. /

Florida Laws (2) 238.03648.43
# 2
MICHAEL J. KRUGER vs. STRUCTURAL STUD PRODUCTS, 77-000289 (1977)
Division of Administrative Hearings, Florida Number: 77-000289 Latest Update: Jul. 13, 1977

Findings Of Fact Michael J. Kruger was employed from September 30, 1976 until January 21, 1977 by Structural Stud Products at an hourly wage rate of $6.15 per hour. According to his testimony he was engaged primarily in welding on this job. He was involved in installing steel wall stud units made from 12 to 16 gauge steel in the Fine Arts Building of Hillsborough Community College. Although his primary function was as a welder, he did assist in loading and moving these wall units from the point where they were unloaded on the job site to where they were put in place. Structural Stud Products is a company primarily engaged in the fabrication of steel wall units. They had entered a contract with the general contractor to provide such units for installation in the Fine Arts Building. Shortly after interior construction began, the dry wall subcontractor who was installing these units abandoned this project. Structural Stud Products took over this contract and not only supplied the materials but installed these units. Michael Kruger was hired by the job supervisor and plant manager to assist in the installation of these units. He was hired as and was paid wages as a laborer. According to the Schedule of Prevailing Wage Rates applicable to the construction of the Fine Arts Building at Hillsborough Community College, welders were to receive the prescribed rate for the craft performing the operation to which the welding was incidental. See Schedule of Prevailing Wage Rates. No evidence was received that the installation of steel wall units requires any specific expertise peculiar to any building trade. Testimony was received that such units are installed by carpenters, dry wall installers, and laborers.

Recommendation Based on the foregoing findings of fact and conclusions of law, the Hearing Officer recommends that the complaint be dismissed. DONE and ORDERED this 2nd day of June, 1977, in Tallahassee, Florida. STEPHEN F. DEAN Hearing Officer Division of Administrative Hearings Room 530 Carlton Building Tallahassee, Florida 32304 COPIES FURNISHED: Harrison Thompson, Esquire Post Office Box 3324 Tampa, Florida 33601 Mr. Michael J. Kruger 160 East Floribraska Avenue Tampa, Florida 33603 Mr. Luther J. Moore Department of Commerce Division of Labor 1321 Executive Center Drive East Tallahassee, Florida 32301

# 3
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs ARMANDO VICTOR CALLEJA, 08-001432PL (2008)
Division of Administrative Hearings, Florida Filed:Viera, Florida Mar. 21, 2008 Number: 08-001432PL Latest Update: Nov. 12, 2019

The Issue The issues in this case are whether Respondent violated Subsections 489.129(1)(g)1., 489.129(1)(g)2., 489.129(1)(j), 489.129(1)(m), and 489.129(1)(o), Florida Statutes (2005),1 and, if so, what discipline should be imposed.

Findings Of Fact At all times material to this proceeding, Mr. Calleja had a valid and active license as a commercial certified pool/spa contractor. His license number is CP 1456568. At all times material to this proceeding, Mr. Calleja was the owner of or did business as Nautica Pools & Spa (Nautica). The Board is charged with regulating the practice of contracting in the State of Florida pursuant to Chapters 455 and 489, Florida Statutes. On April 2, 2005, Mr. Calleja, as the representative for Nautica, entered into a contract with Jack Coleman to renovate Mr. Coleman’s existing pool. From April 2005 to July 27, 2005, Nautica installed rebar in the pool and set a new skimmer. Nautica subcontracted with Prestige Gunite of Melbourne, Inc. (Prestige), to put the gunite in the pool. Gunite is concrete that is sprayed out of a hose to form the walls of the pool. Personnel from Prestige arrived on the project site on the afternoon of July 27, 2005, to apply the gunite, but did not do so because the application would have taken longer to do than one afternoon. The following day, July 28, 2005, Mr. Calleja and a crew from Prestige returned to the project. A representative from Prestige told Mr. Calleja that the steel rebar had not been laid properly. Mr. Calleja told Prestige to apply the gunite and do what was necessary to cover the steel. Mr. Calleja left the project site, and Prestige began applying the gunite. During the application of the gunite, it became evident that the first spraying of gunite was not going to cover the steel. Attempts were made to reach Mr. Calleja, but Mr. Calleja was not available to solve the problem. Prestige began applying additional coats of gunite in an attempt to cover the steel. After the gunite was applied, two problems were identified. The first problem was in the fountain area. The gunite had not been applied properly, and there were hollow areas. The second problem was in the wet deck area. The steel rebar was too close to the surface of the floor, and the steel was visible. In order to remedy the problems, the concrete in the areas would have to be jack hammered to remove the concrete, and new gunite would have to be applied. By letter dated August 28, 2005, Nautica requested Mr. Coleman to pay Prestige $954.57. Nautica advised Mr. Coleman that when that amount had been paid, Nautica would pay the balance owed to Prestige and forward a release to Mr. Coleman. Mr. Calleja claimed that Mr. Coleman owed the $954.57 because Mr. Coleman had damaged Mr. Calleja’s saw. In the letter, Nautica acknowledged that there was additional work which had not been completed. The letter was signed by Mr. Calleja’s wife. Mr. Calleja had verbally told Mr. Coleman that he wanted Mr. Coleman to pay him $2,000.00, and he would take care of paying Prestige. The general specifications in the contract required that the contractor was responsible for “[s]tandard structural engineering plans and permits required by code.” Prior to commencing work on the pool renovation, Mr. Calleja did not secure the required building permits for the project. Mr. Coleman called Clifford Stokes, who is the building official with the town of Indialantic, and asked whether a permit had been issued. Mr. Stokes went to the project site. At that time, the gunite had been shot, and there was exposed steel rebar. Since no permit had been pulled, no inspection had been done after the steel was put in place. On September 15, 2005, Mr. Calleja applied for a building permit. Because the steel had been placed, and the gunite shot, it was impossible to do a visual inspection to determine whether the steel had been placed properly. In order to get a permit after the construction had been commenced, certain affidavits had to be submitted to the building official of Indiatlantic. Mr. Calleja had to submit an affidavit stating that the steel had been placed properly. An affidavit stating that the work had been performed properly had to be submitted from an engineer, who had made a site visit to the project and had determined that the work performed had been according to code. Additionally, Mr. Coleman was required to submit an affidavit that stated that he understood that no inspection had been done of the work by the building official. Mr. Calleja also had to pay a fine to Indiatlantic for commencing work without a building permit. On October 19, 2005, Mr. Calleja and Robert Lee from Lee Engineering came to the project site for the purpose of preparing the affidavits necessary to secure a building permit. Mr. Calleja did not return to the project site after October 19, 2005. Mr. Coleman sent a letter to Mr. Calleja dated October 13, 2005, noting that no work had been done on the project since July 28, 2005, and requesting that Mr. Calleja remedy a number of deficiencies with the work performed on the project and complete the job in accordance with the contract. The letter was returned to Mr. Coleman by the postal service because the time for forwarding mail from the address listed in the letter had expired. When Mr. Calleja came to the project site on October 19, 2005, Mr. Coleman requested a current address from Mr. Calleja, but Mr. Calleja refused to give him one. Mr. Coleman wrote another letter to Mr. Calleja dated October 25, 2005, again stating that no work had been done since July 28, 2005, and requesting that Mr. Calleja correct the deficiencies in the work and complete the contract. Mr. Coleman filed an action in small claims court attempting to recover the money for the lien filed by Prestige. However, Nautica had filed for bankruptcy, and Mr. Coleman did not proceed with the small claim action. A building permit for the project was issued in January 2006. The issuance of the building permit did not relieve Mr. Calleja from the responsibility of assuring that the work in the shallow end of the pool area where the rebar was sticking up was redone properly. After the building permit was issued, neither Mr. Calleja nor Mr. Coleman called for inspections by the Indiatlantic building official. The permit expired in June 2006. After the issuance of the building permit, Nautica performed no further work on the project. The total contract price was $9,340.00. Mr. Coleman and Mr. Calleja entered into an addendum to the contract on July 27, 2005, which increased the contract price to $13,000.00. The contract called for a down payment of $934.00, which was ten percent of the contract amount. After completion of excavation and the form and steel work, a payment of $3,736.00 was due, representing 40 percent of the total work. After completion of the pool shell, a payment of $2,802.00 was due, representing 30 percent of the total work. Prior to plastering, which represented 20 percent of the total work, a payment of $1,868.00 was to be paid. The contract addendum of $3,660.00 called for 50 percent of the addendum amount to be paid at the completion of the pool shell, and the remaining 50 percent of the addendum amount was to be paid at the completion of the pool. By check dated April 22, 2005, signed by Mr. Coleman’s wife, Mr. Coleman paid Mr. Calleja $1,000.00 as down payment on the project. In June 2005, Mr. Coleman gave Mr. Calleja a check for $573.42 for a pool and spa light. Mr. Coleman was to receive a credit of $380.00 toward the contract for the light. Additionally, Mr. Coleman overpaid Mr. Calleja by $166.90. By check dated July 27, 2005, and signed by Mr. Coleman’s wife, Mr. Coleman paid Mr. Calleja $7,396.00. This payment was to include half of the addendum amount, but Mrs. Coleman inadvertently included the full amount of the addendum. By check dated August 1, 2005, and signed by Mrs. Coleman, Mr. Coleman paid Mr. Calleja $739.10. Thus, by August 1, 2005, Mr. Coleman had paid Mr. Calleja, $9,682.00 on the contract. In December 2005, Mr. Coleman asked a representative of Paradise Pools, Patrick McDonough, to come to the project site and give an estimate to complete the pool. The estimate of $7,800.00 from Paradise Pools was for a cosmetic plaster of the existing pool, and the work was not warranted against leakage. Mr. McDonough would not warrant the work, because he saw a lot of potential liability problems with the work performed by Mr. Calleja. Mr. McDonough did not recommend that a cosmetic plaster be performed because of the potential problems. On October 26, 2005, Prestige filed a Claim of Lien against the property of Mr. Coleman for $4,227.40 plus interest, costs, and attorney’s fees. The lien was for the work which Prestige had performed on the project on July 28, 2005, and for which Mr. Calleja had failed to pay. Mr. Coleman called Mr. Calleja and told him that a lien had been filed. Mr. Calleja assured him that he would pay the lien, but he failed to do so. Mr. Coleman satisfied the lien by check dated April 11, 2006, for the amount of $5,139.58. David Bogenrief, P.E., viewed the project in June 2008 and provided Mr. Coleman with a quote to develop structural plans to repair Mr. Coleman’s pool. There was no testimony on the amount of the quote, and the Department did not request that the written proposal be admitted in evidence. Mr. Bogenrief did not know what it would cost to repair the pool. The Department has incurred $470.49 for costs in the prosecution of this case.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered finding that Mr. Calleja did not violate Subsection 489.119(2), Florida Statutes, and that Mr. Calleja violated Subsections 489.129(1)(g)1., 489.129(1)(g)2., 489.129(1)(j), 489.129(1)(m), and 489.129(1)(o), Florida Statutes; for the violation of Subsection 489.129(1)(g)1., Florida Statutes, imposing a fine of $2,000.00, suspending Mr. Calleja's license for six months, and requiring Mr. Calleja to pay Mr. Coleman $5,139.58 as restitution for the payment of the lien filed by Prestige; for the violation of Subsection 489.129(1)(g)2., Florida Statutes, imposing a fine of $2,000.00, suspending Mr. Calleja's license for six months, and requiring Mr. Calleja to pay Mr. Coleman $9,682.00, which represents the amount that Mr. Coleman paid to Mr. Calleja; for the violation of Subsection 489.129(1)(j), Florida Statutes, imposing a $1,000.00 fine and four years of probation; for the violation of Subsection 489.129(1)(m), Florida Statutes, imposing a $1,000.00 fine and four years of probation, which shall run concurrently with the other probation imposed; and, for the violation of Subsection 489.129(1)(o), Florida Statutes, imposing a $1,000.00 fine and two years of probation to run concurrently with the other probation imposed; and requiring payment of $470.49 as costs for the prosecution of this case. DONE AND ENTERED this 29th day of August, 2008, in Tallahassee, Leon County, Florida. S SUSAN B. HARRELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 29th day of August, 2008.

Florida Laws (6) 120.569120.57120.68489.119489.1195489.129 Florida Administrative Code (1) 61G4-17.001
# 4
KERMIT R. KRUGER vs. STRUCTURAL STUD PRODUCTS, 77-000290 (1977)
Division of Administrative Hearings, Florida Number: 77-000290 Latest Update: Jul. 13, 1977

Findings Of Fact Kermit R. Kruger was employed on or about October 5, 1976 by Structural Stud Products at an hourly wage rage of $6.15 per hour. According to his testimony he was engaged primarily in welding on this job. He was involved in installing steel wall stud units made from 12 to 16 gauge steel in the Fine Arts Building of Hillsborough Community College. Although his primary function was as a welder, he did assist in loading and moving these wall units from the point where they were unloaded on the job site to where they were put in place. Structural Stud Products is a company primarily engaged in the fabrication of steel wall units. They had entered a contract with the general contractor to provide such units for installation in the Fine Arts Building. Shortly after interior construction began, the dry wall subcontractor who was installing these units abandoned this project. Structural Stud Products took over this contract and not only supplied the materials but installed these units. Kermit Kruger was hired by the job supervisor and plant manager to assist in the installation of these units. He was hired as and was paid wages as a laborer. According to the Schedule of Prevailing Wage Rates applicable to the construction of the Fine Arts Building at Hillsborough Community College, welders were to receive the prescribed rate for the craft performing the operation to which the welding was incidental. See Schedule of Prevailing Wage Rates. No evidence was received that the installation of steel wall units requires any specific expertise peculiar to any building trade. Testimony was received that such units are installed by carpenters, dry wall installers, and laborers.

Recommendation Based on the foregoing findings of fact and conclusions of law, the Hearing Officer recommends that the complaint be dismissed. DONE and ORDERED this 2nd day of June, 1977, in Tallahassee, Florida. STEPHEN F. DEAN Hearing Officer Division of Administrative Hearings Room 530, Carlton Building 2009 Apalachee Parkway Tallahassee, Florida 32304 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of June, 1977. COPIES FURNISHED: Harrison C. Thompson, Esquire Post Office Box 3324 Tampa, Florida 33601 Mr. Kermit R. Kruger 160 East Floribraska Avenue Tampa, Florida 33603 Mr. Luther J. Moore Department of Commerce Division of Labor 1321 Executive Center Drive East Tallahassee, Florida 32301

# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. RICHARD J. HUNT, D/B/A R. J. HUNT CONSTRUCTION, 76-000576 (1976)
Division of Administrative Hearings, Florida Number: 76-000576 Latest Update: Sep. 08, 1977

Findings Of Fact On September 29, 1975 Respondent, R. J. Hunt Construction Company, through its President and qualifying general contractor, Richard J. Hunt, entered into a contract with Richard McCarty to construct two Second Story Additions to Palm Ocean Villas, Pompano Beach, Florida for a price of $53,700. The contract provided that the contractor would complete the building within 8 weeks of the issuance of a building permit and, if not completed, a 5 percent penalty would be deducted until December 10, 1975 and thereafter, if not complete, an additional 5 percent of the contract price would be deducted each week until complete. Building permits were issued on October 3 and 6, 1975 and work proceeded satisfactorily until the end of the 8 weeks contract period on December 1, 1975 when the project was 90 percent to 95 percent complete. At this time the contractor stopped work on the project and transferred his employees to another job. One of the contract provisions not completed was the application of waterproofing on a deck. Despite Hunt's assurances that he would get a subcontractor to complete this waterproofing, it still had not been completed by Christmas and McCarty employed a contractor to apply the waterproofing material in early January for which he paid $1,000 allowed by the contract. Subsequent thereto McCarty received notice of liens filed against his property from 4 subcontractors. These were American Metal Products Company, J. P. Electric Company, Ole Eds Construction, and Margate Plumbing. In order to get a certificate of occupancy it was necessary for McCarty to pay some of these subcontractors. American Metal Products installed an aluminum railing around the balcony for which they filed a notice of lien for $1,200 and subsequently filed a petition in bankruptcy. The present status of this lien was not ascertained. J. P. Electric Company had split their draw into three parts and they were paid by Hunt $700 for the initial work. When they refused to allow final inspection Hunt asked McCarty to pay them and take it off his last draw. McCarty paid $2,000 to J. P. Electric, leaving a balance owed of $781.92. Hunt also asked McCarty to pay Margate Plumbing and take this payment off the draw. Margate had been paid $1,000 upon completion of the rough work. In order to get occupancy McCarty paid Margate $1,800 which satisfied the lien of Margate. Ole Ed installed the septic tank and drain field for which they have filed a lien for $2,500 which is unpaid to date. Numerous miscellaneous items included in the contract for which McCarty advanced funds to keep work progressing amounted to $671.54. Hunt also requested McCarty to order the appliances which were included in the contract price since he (McCarty) could get them at contractor's price. For these appliances (stoves, air conditioners and refrigerators) McCarty expended $2,373.28. Total expenditures made by McCarty are as follows: McCarty paid to Hunt in draws $48,400.00 McCarty paid to J. P. Electric 2,000.00 McCarty paid to Margate Plumbing 1,800.00 McCarty paid for waterproofing deck 1,000.00 Misc. items paid for by McCarty 671.54 Appliances for which McCarty paid 2,373.28 Total paid by McCarty under contract $56,244.82 Balance owed to subcontractors. American Metals Corporation $ 1,200.00 J. P. Electric 781.92 Ole Ed's Construction 2,500.00 Total cost of project $61,736.74 At the time licensee stopped work on the project the railing around the balcony had not been installed, top decking had not been approved by building inspectors and waterproofing of deck had not been done. Extra costs not included in the contract price which were agreed to by McCarty included $300 to $500 extra for larger electric wire and $400 to $500 for larger septic tank than contract called for. These costs totaled approximately $800 which would bring the total contract price to $54,500. The working foreman on the job for the first three or four weeks of the contract, who testified on behalf of Respondent, was unfamiliar with all terms of the contract or with the finances of Hunt. When the existing roof was removed for the second floor addition to be added, conduits had to be replaced and some 2 x 12 joists had to be replaced. This work unexpectedly increased the cost of the contract to the contractor. The septic tank could not be placed where originally intended, and as a result, about 100 fee of sidewalk had to be torn up and replaced. Further, a larger septic tank than originally planned had to be installed. This latter increase was agreed to and paid for by McCarty. One character witness testified that Richard J. Hunt enjoys a good reputation in the construction industry.

# 6
TLC STONEWORKS, LLC vs DEPARTMENT OF FINANCIAL SERVICES, DIVISION OF WORKERS' COMPENSATION, 08-003545 (2008)
Division of Administrative Hearings, Florida Filed:Sarasota, Florida Jul. 21, 2008 Number: 08-003545 Latest Update: Jan. 15, 2009

The Issue The issue is whether Petitioner is liable for a penalty for failure to maintain workers’ compensation insurance in violation of relevant provisions in Chapter 440, Florida Statutes (2007).1

Findings Of Fact Respondent is the state agency responsible for enforcing the statutory requirement that employers secure the payment of workers’ compensation for the benefit of their employees. § 440.107. Petitioner is a limited liability company domiciled in Florida and engaged in the sale of stone countertops. The disputed issues of fact arise from a single, integrated transaction involving “one and the same business” within the meaning of Subsection 440.10(1)(b). The “business” includes a contractor, a wholesaler, and two subcontractors, one of which is Petitioner. The integrated transaction is between the business and a homeowner. The contractor is identified in the record as Manasota Land Development (Manasota). The homeowner owns a residence on Agate Road in Port Charlotte, Florida (the homeowner). The contractor referred the homeowner to Petitioner for the purpose of selecting granite countertops. Petitioner’s representative visited the residence, took measurements, and received the order for granite from the homeowner. Petitioner placed the order with the wholesaler, the name of which is not material to this proceeding. The wholesaler delivered granite to a fabricator and installer designated by Petitioner and identified in the record as Granite Exclusive (the installer). The installer fabricated the countertops and installed them at the residence. Petitioner visited the residence to ensure customer satisfaction, and Petitioner paid the wholesaler and installer from funds provided by Manasota. Petitioner did not collect payment from the homeowner. Rather, Petitioner agreed with Manasota to a total price of $7,141.00. Petitioner billed Manasota for $3,570.00, an amount equal to approximately one-half of the total agreed price, on May 21, 2008, inferentially when the homeowner placed the order with Petitioner. Manasota paid Petitioner the 50 percent deposit. Petitioner billed Manasota for the balance due, in the amount of $3,571.00, on July 22, 2008, when the work was completed to the satisfaction of the homeowner, and Manasota paid the balance due. Petitioner was a sales agent, order processor, and a collection and payment processor for Manasota. Petitioner paid the wholesaler and installer from funds provided by Manasota. The fact-finder draws a reasonable inference from the evidence that Manasota collected a sum from the homeowner that was equal to or greater than the price Manasota paid to Petitioner. Petitioner and the installer are subcontractors of Manasota. Petitioner had no supervisory control over the installer. Respondent’s claim that a written or oral contract existed between Petitioner and the wholesaler and installer is not supported by clear and convincing evidence. It is undisputed that neither the installer nor Petitioner have workers’ compensation insurance, and the two subcontractors are, by operation of Subsection 440.10(1)(b), the employees of Manasota in “one and the same business.” Manasota is responsible for providing workers’ compensation coverage by operation of the statute. Petitioner mistakenly believed, in goof faith, that it was exempt from the requirements of Chapter 440. A company officer of Petitioner obtained an exemption certificate and, reasonably, concluded that the exemption was for Petitioner and both of Petitioner’s officers or employees. Such an exemption was the officer’s stated purpose when she entered the local state office responsible for issuing exemption certificates. The state employee represented that the exemption certificate actually issued achieved the officer’s stated purpose. The express terms of the exemption certificate provide that the exemption is for the person “and” company named in the certificate. However, Subsection 440.05 makes clear that an exemption covers only the company officer named in the certificate and that each of the two officers must be named in the certificate or that each officer must obtain a separate certificate. Petitioner did not engage in the business of fabricating or installing the stone countertop. Petitioner made a sale of the granite countertop and placed an order with a wholesaler. The wholesaler shipped the countertop to a the installer designated by Petitioner based on proximity to the project site. The fabricator installed the countertop. Petitioner did not supervise the fabrication or installation of the countertop. The fact-finder has considered and weighed conflicts in the evidence pertaining to the issue of whether Petitioner engaged in the business of fabricating and installing the stone countertop and has resolved any evidential conflicts in favor of Petitioner. The testimony of Petitioner’s witness, describing the nature and scope of Petitioner’s business, is consistent with Article 5 in Petitioner’s Articles of Incorporation which states: The general purpose for which the Company is organized is to engage in the business of natural stone countertop sales. . . . On June 3, 2008, Respondent’s investigator, conducted a compliance check at 8206 Agate, South Gulf Cove, Florida, to verify compliance with the workers’ compensation statutes. At the worksite, Respondent’s investigator observed three men installing a stone countertop for the installer. Installation of stone countertops is part of the construction industry and is assigned Class Code 5348 in the Scopes Manual, published by the National Council on Compensation Insurance and adopted in Florida Administrative Code Rule 69L-6.021. The investigator interviewed the three men and requested proof of compliance with the workers’ compensation law. One of the three men, neither furnished proof of an election to be exempt from workers’ compensation nor showed that he had secured workers’ compensation coverage. Utilizing the Department of Financial Services’ Coverage and Compliance Automated System (CCAS), the investigator was unable to determine that the employee of the installer was exempt from the requirements of the workers’ compensation law or that Petitioner had secured the payment of workers’ compensation. On June 4, 2008, the investigator issued a Stop-Work Order and Order of Penalty Assessment against Petitioner for failure to meet the requirements of Chapter 440. Respondent ordered Petitioner to cease all business operations and assessed a $1,000.00 penalty against Petitioner pursuant to Subsection 440.107(7)(d). On June 4, 2008, the investigator issued a Division of Workers’ Compensation Request for Production of Business Records for Penalty Assessment Calculation. Petitioner complied with the Request and provided the required records. Based on Petitioner’s business records, the investigator issued an Amended Order of Penalty Assessment on June 11, 2008, in the amount of $1,218.52. Mr. Thomas Harvey, a company officer of Petitioner, did not posses an election to be exempt from workers’ compensation. Ms. Leslie Lockett, the other company officer had applied for and obtained an exemption from workers’ compensation coverage. Ms. Lockett’s exemption from workers’ compensation lists the scope of business or trade as countertops, pursuant to instructions from the agency employee who issued the certificate. Ms. Lockett’s exemption from workers’ compensation is a construction industry exemption. Ms. Lockett applied for a Notice of Election to be Exempt as a member of a limited liability company in the construction industry pursuant to the instructions previously described. In the transaction at issue in this proceeding, Petitioner collected payment for materials and installation of a stone countertop from Manasota. Petitioner did not collect payment from the homeowner and had no control or authority over either the wholesaler or the installer.

Recommendation Based on the Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent issue a final order dismissing the Stop-Work Order and Amended Order of Penalty Assessment against Petitioner and Mr. Harvey. DONE AND ENTERED this 24th day of October, 2008, in Tallahassee, Leon County, Florida. S DANIEL MANRY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of October, 2008.

Florida Laws (3) 440.05440.10440.107 Florida Administrative Code (1) 69L-6.021
# 7
GATEWAY ESTATES PARK CONDOMINIUM ASSOCIATION vs SDI QUARRY, A/K/A ATLANTIC CIVIL, INC., 16-001025CM (2016)
Division of Administrative Hearings, Florida Filed:Midway, Florida Feb. 22, 2016 Number: 16-001025CM Latest Update: Nov. 06, 2018

The Issue Whether the use of explosives at Respondent's quarry has caused damage to the shore of Petitioner's lake; and, if so, whether (and what amount of) compensatory damages should be paid by Respondent to Petitioner.

Findings Of Fact Petitioner Gateway Estates Park Condominium Association (the "Association") is a condominium association organized under chapter 718, Florida Statutes. The Association oversees the Gateway Estates Park mobile home community ("Gateway Estates"), a condominium, which consists of 220 mobile homes and two vacant lots. Although the lots and mobile homes are owned by the individual owners, the Association holds title to a number of common elements, including two lakes——the South Lake (which is the subject of these proceedings) and the North Lake. Respondent SDI Quarry, a/k/a Atlantic Civil, Inc. ("SDI Quarry"), a mining company, uses explosives to extract construction materials such as limestone from quarries that are located in southwest Miami-Dade County. SDI Quarry has three mines that are near the South Lake; the closest of these is located approximately 7,000 feet from Gateway Estates. In 2005, SDI Quarry began blasting in the vicinity of Gateway Estates, and such activity has continued from that time until the present (i.e., as of the final hearing in this case). SDI Quarry operates the only mines at which blasting is conducted within close proximity to the subject community. The evidence does not establish the number of blasts conducted near Gateway Estates during the roughly dozen years leading up to this litigation. Between July 1, 2015, and October 17, 2016, however, SDI Quarry performed 25 blasts, and neither party suggested that this frequency of activity was unusually high or low relative to SDI Quarry's past performance. The undersigned draws the reasonable inference that the number of historical blasts affecting Gateway Estates is in the range of 200 to 250. The state regulates the use of explosives in conjunction with the extraction of materials such as sand and limestone. A mine operator must obtain a permit before commencing blasting activities. Among other things, a permit holder must comply with the statewide ground vibration limits established by the State Fire Marshal. These limits are set forth in Florida Administrative Code Rule 69A-2.024(4), which states that "[g]round vibration shall not exceed the limits of particle velocity and frequencies established by the U.S. Bureau of Mines Report of Investigations, No. 8507 Ground Vibration, Frequency Limits." The pertinent U.S. Bureau of Mines Report is incorporated by reference in the rule. SDI Quarry has complied with its obligations under rule 69A-2.024 to engage the services of an independent seismologist to measure and record, for every blast, the peak particle velocity ("PPV")——a value that reflects the maximum speed at which a particle vibrates due to a passing wave of seismic energy——at the location of the building nearest to the blast site that is not owned by the permit holder, and to report this information in writing to the State Fire Marshal. The PPV limit in the state of Florida is 0.5 inches per second. This particular standard derives from research conducted by the U.S. Bureau of Mines to determine the ground vibration threshold for damage to structures such as buildings and homes. The state has not adopted a PPV limit dedicated to the protection of shorelines around lakes and ponds. Neither party identified any such standard having the force of law in any jurisdiction in the United States. There is no evidence that any of SDI Quarry's blasts reached or exceeded the 0.5 inch-per-second PPV limit. Moreover, at the location of Gateway Estates, most blasts caused a PPV of approximately 0.1 inches per second or less, and none led to a PPV in excess of 0.2 inches per second. In short, based on the current record, the undersigned determines that SDI Quarry was, at all relevant times, operating in compliance with the state laws regulating mining operations involving explosives. Because, however, as will be discussed below, blasting is an ultrahazardous activity, SDI Quarry is absolutely liable, as a matter of law, for damages caused by its use of explosives, regardless of fault. Therefore, SDI Quarry's regulatory compliance, per se, is irrelevant; that said, the PPV measurements obtained in the course of such compliance have probative value to the extent they bear on the issue of causation. The South Lake is a man-made body. It was excavated sometime before 1975, which was the year the Association was organized. From the waterline, the lake's shore slopes upward and levels off to a flat bank circling the water; beyond the bank are the backyards of the homes on the lake. Until 2011, when the slope began to lose stability and fail, the horizontal area of the South Lake's bank was approximately four to five feet wide, making it possible for residents to walk around the entire perimeter of the lake and engage in activities such as fishing. In 2011, about five or six years after SDI Quarry began blasting near Gateway Estates, the shore of the South Lake began to destabilize, and the saturated soil at the edges of the lake, consisting of silt or marl, began to slough and slump into the water. This opened up fissures in the slope, which undermined the upward bank. In time, holes appeared in the bank, and pieces of the once level surface fell off, resulting in the narrowing of the horizontal area, from roughly five feet or so, to about a foot and a half. Residents have observed the ground falling into the water in close temporal proximity to the blasting. One testified credibly that "after the blasting on January 20th, [2016,] the ground [in one section of the lake] actually separated and dropped into the water." Tr. 32. Because of the deterioration of the lakeshore, residents can no longer walk around the bank, or stand upon it and fish as in the past; the shore is too steep, and there are holes in the ground that render such activities unsafe. The stability of the slope has continued to worsen, and, as of the final hearing, the deterioration of the lakeshore, like the blasting, was ongoing. The Association has suffered property damage in the form of the deterioration of the shore and bank around the South Lake. There is, further, no dispute that from 2005 through the time of the final hearing, SDI Quarry has used explosives in connection with mining activities in the vicinity of Gateway Estates. The only genuine dispute of material fact relating to SDI Quarry's liability to the Association is whether the use of explosives caused the Association's loss——whether, in other words, the existing property damage at the South Lake would not have occurred but for SDI Quarry's blasting. The issue of causation in this case is a close one, and there is competent, substantial evidence on both sides. The Association offered the opinion testimony of James R. McNew, who is a construction consultant. Although Mr. McNew is not licensed as a professional engineer, he holds a bachelor's degree in mechanical engineering, awarded in 1972, and during the course of a 50-plus-year career has been involved as a consultant or project manager on a number of marine projects, including the construction of 27 bridges in South Florida, all of which had earthwork abutments and adjoining bodies of water. Some of the projects Mr. McNew supervised involved drilling and blasting operations. As a result, Mr. McNew has acquired specialized knowledge relating to the use of explosives in or around saturated and submerged soils from long practical experience, which in addition to his formal education and training qualified him to testify as an expert on causation in this case.2/ Mr. McNew's opinion is that vibrations from SDI Quarry's blasting acted upon the soft layer of silt atop the shore and bank of the South Lake, causing the liquefaction of this saturated soil, which extends down from the surface, to distances of up to eight feet. This led, in Mr. McNew's opinion, to the compaction of the loose, wet soil around the edges of the lake, opening up cracks and holes and weakening the slope, which began to erode and fail. Mr. McNew stated that there are no specific legal standards in Florida or elsewhere serving to establish PPV thresholds above which lakeshore slope instability would be expected under the stress of blast-related vibrations.3/ He opined that existing limits based on structure responses to ground vibrations are inapplicable, because buildings are designed and constructed to resist the stresses of seismic energy, in contrast to saturated silt on the shore of a lake. He explained that, consequently, lower levels of energy would suffice to cause damage to the bank of the South Lake, than would be expected to damage, e.g., a house at the same location. SDI Quarry's principal expert witness on causation was Steven E. Black, a Florida-licensed professional engineer who specializes in geotechnical engineering and has been practicing in the field since 1970.4/ In addition to these credentials, Mr. Black holds a bachelor's degree in civil engineering. At hearing, Mr. Black explained that there is a layer of calcareous silt that underlies the mobile home park and is exposed at the lakeshore. Mr. Black testified that this silt layer has been eroded over time by the action of wind, waves, and rainwater percolating down and through the ground, pulling the silt from the bank and resulting in the deterioration of the property. According to Mr. Black, the blasting carried out by SDI Quarry is not close enough to Gateway Estates to impart sufficient energy to affect the soil around the South Lake.5/ In his opinion, SDI Quarry's blasting activities did not cause, as he described it, "the sloughing of the edges of the lake." Yet, interestingly, Mr. Black agreed with Mr. McNew that heavy truck traffic could definitely affect the silt layer of the lakeshore over a continuous period of time. Tr. 145. (Mr. McNew expressed the opinion that ground vibrations from heavy equipment could cause damage to a lakeshore "if you [had] a haul road going around the lake." Tr. 77. He offered this comment while making the point that other sources of seismic energy besides blasting, e.g., heavy construction traffic, could be ruled out as causes of the damage to the South Lake because none have been known to occur.) The undersigned finds this concession of Mr. Black's to be significant because, while there is no evidence in the record establishing the typical levels of ground-borne vibration from heavy trucks or construction equipment traveling over a roadway, common knowledge and ordinary experience are sufficient to permit the fact-finder to infer that such levels would be lower by orders of magnitude, at the source, than those caused by the use of explosives to mine limestone. We know this because in ordinary experience, while we might feel some vibrations under foot when a large truck drives by, especially if the road surface is uneven, we can easily see——because the road remains intact—— that the truck has not suddenly released tremendous gas pressure inside the ground, producing enough energy to break rock, as occurs when explosives are placed in holes and detonated in a limestone quarry. As it happens, there are homes and other structures standing between the South Lake and the nearest streets, so any ground-borne seismic energy from passing trucks necessarily would be attenuated before reaching the lakeshore, just as the seismic energy from SDI Quarry's blasting is attenuated as it travels the one and one-third miles from the mine to the lake. As found above, by the time the energy wave from a blast reaches the South Lake, the PPV is typically 0.1 inches per second or less (although occasionally the level is higher), but obviously the PPV at the source of any given blast is far greater than that. Energy from a passing truck would not need to travel as far, to be sure, but it would be much weaker at the source than a construction mining blast. The undersigned does not have enough evidence before him to make a finding as to what levels of PPV would be expected at the South Lake as heavy trucks drove past the property, but he can reasonably infer that the seismic energy from nearby vehicular traffic would not likely exceed that of SDI Quarry's blasting, and indeed would likely be much lower. It is true, to be fair, that Mr. Black's opinion——that transportation sources of ground-borne vibration, if present, could affect the lakeshore——was qualified by conditions of frequency ("a lot of heavy truck traffic") and duration ("over a continuous period of time"). His opinion about the blasting, however, was that the energy imparted therefrom was insufficient to damage the lake, period———not that the blasting was too infrequent to cause the property damage, or that it had not been conducted for a sufficient period of continuous years to cause such damage. By conceding that the energy imparted from heavy trucks "could definitely affect" the stability of the silt layer, Mr. Black undercut the strongest part of his opinion on causation, namely its certainty that an absolute level of seismic energy, greater than that seen at the lake, is necessary to cause saturated silt to move. On balance, the undersigned finds Mr. McNew's opinion on causation to be more persuasive than the competing view. In addition, the undersigned finds that the circumstantial evidence is consistent with, and supports, Mr. McNew's opinion; indeed, such evidence might have been sufficient, without more, to establish a causal connection between the blasting and the property damage. Consider that the South Lake had existed for at least 35 years without experiencing the deterioration of the shore and bank that became noticeable within just five or six years after the start of the blasting, and which has worsened over time as the blasting has continued. Add to that the persuasive evidence that visible damage occurs in the wake of individual blasts. Taken together, these facts on the ground have probative value independent of expert opinion. That said, the undersigned credits Mr. Black's testimony to the extent it supports a finding that erosion from wind, wave, and rainwater is a natural cause of some deterioration at the shore of the South Lake. It is further found, however, that this natural erosion is not the sole and independent cause of the Association's property damage. Rather, it is determined that the seismic energy from SDI Quarry's blasting is acting in combination with this natural erosion, and that the blasting, as a concurring cause, is contributing substantially to producing the sloughing of the lakeshore, fissures and holes in the slope, and consequent loss of level area from the bank that have occurred, and continue to occur, at the South Lake. In sum, the Association has proved by a preponderance of the evidence that SDI Quarry's blasting is a legal cause of the property damage for which compensation is being sought. As for the measure of damages, the Association presented evidence of a proposal from Upper Keys Consulting LLC ("Upper Keys"), which is dated July 18, 2015, for restoring the shore of the South Lake and installing preventative devices to protect the shoreline against erosion from future blasting. This proposal included several options, ranging in price from $840,000.00 to $1.45 million. The Association seeks to recover $840,000.00 from SDI Quarry to cover the cost of repairing and protecting its property. SDI Quarry did not present persuasive evidence either challenging the efficacy, or questioning the expense, of the Upper Keys proposal. The undersigned finds, therefore, that an amount of $840,000.00 is supported by the preponderance of the evidence presented. SDI Quarry contends, as an affirmative defense, that the Association failed to file its petition for relief within 180 days after the occurrence of the alleged damage, as required by section 552.40(1). The petition was filed on February 22, 2016, and SDI Quarry maintains that the damage to the South Lake had already occurred more than 200 days earlier, by July 18, 2015——i.e., the date of the Upper Keys proposal. SDI argues that, as a result, the Association's claim is time barred. The undersigned rejects this argument because, as a matter of fact, the property damage at issue is present and continuing; the harm to the lakeshore is cumulative, indivisible, and inseparable. The deterioration of the South Lake worsens with each blast, and the blasting was still going on during the 180 days preceding the initiation of this action. The damage, consequently, did not simply occur once in the past. This action is not time barred. Despite finding that SDI Quarry is liable to the Association for the property damage caused by its blasting, the undersigned determines that SDI Quarry's defenses were supported by evidence of material facts; were grounded in existing law; and were not advanced primarily to harass or cause unnecessary delay, for frivolous purposes, or to needlessly increase the cost incurred by the Association. As stated above, the question of causation is close in this case, and there is conflicting evidence on this crucial issue. That the undersigned resolved the evidential conflicts in the Association's favor neither means, nor is meant to imply, that SDI Quarry's position lacked substantial merit.

Florida Laws (11) 120.569120.57120.68552.32552.36552.40552.42552.4490.70290.70690.953
# 8
CECILIA C. MEDINA vs VECELLIO AND GROGAN, INC., A SUBSIDIARY AND WHOLLY OWNED COMPANY OF VECELLIO GROUP, INC., DOING BUSINESS AS WHITE ROCK QUARRIES, 15-005548CM (2015)
Division of Administrative Hearings, Florida Filed:Lauderdale Lakes, Florida Oct. 02, 2015 Number: 15-005548CM Latest Update: Aug. 07, 2017

The Issue The issues presented are whether damages resulted to Petitioner's home as a result of Respondent's use of explosives in connection with construction materials mining activities, and, if so, what is the appropriate remedy.

Findings Of Fact By Notice of Hearing entered March 10, 2016, this cause was scheduled for final hearing on May 18, 2016. An Amended Notice of Hearing dated April 20, 2016, re- noticed the hearing for May 18, 2016, changing the location to Lauderdale Lakes, Florida. On May 12, 2016, a second Amended Notice of Hearing also scheduled the hearing to start on May 18, 2016. On May 17, 2016, Petitioner filed a Notice of Filing Her Power of Attorney. At 9:30 a.m., on May 18, 2016, the date and time scheduled for the final hearing in this cause, Respondent's attorney and its witnesses, the court reporter and the undersigned were present. Petitioner did not appear. Petitioner's husband appeared at hearing indicating that he was there to represent Petitioner by Power of Attorney. In administrative proceedings, pro se parties may either be represented by an attorney or a qualified representative. On May 2, 2016, Petitioner's request that her husband represent her as a qualified representative was denied by Order Denying Motion/Request for Leave to be Represented by a Qualified Representative in this Case ("Order"). The Order held Petitioner's husband does not have the "knowledge and experience identified in Florida Administrative Code Rule 28-106.106 to serve as a qualified representative." Petitioner's Renewed Motion/Request for Leave to be Represented by Qualified Representative in this Case was also denied by Order on Petitioner's Renewed Motion, dated May 16, 2016. While addressing preliminary matters prior to starting the hearing, the undersigned held that the Power of Attorney could not substitute for rule 28-106.106. Therefore, Petitioner's husband was prohibited from representing Petitioner at the hearing due to Petitioner's husband not meeting the qualified representative standards. After waiting for Petitioner to appear, the undersigned convened the hearing. At 10:13 a.m., Petitioner still had not appeared. The final hearing was adjourned.

Florida Laws (3) 120.569120.68552.40
# 9
DIVISION OF REAL ESTATE vs. JAMES J. BARUCH, 81-002398 (1981)
Division of Administrative Hearings, Florida Number: 81-002398 Latest Update: Nov. 01, 1982

Findings Of Fact Pursuant to the Prehearing Stipulation, the following facts are established: This case is based on allegations by John Carosso that James J. Baruch, a licensed real estate broker, wrongfully allowed the dispersal of a deposit Mr. Carosso had made to Centennial Development Corporation on a villa to be constructed. James J. Baruch was associated with Wyn Pope Associates, Inc., as a realtor and salesman over a period of several years and on several projects which Mr. Pope developed. On the Gasa Tiempo project, the developer was Centennial Development Corporation and sales were handled by Wyn Pope Associates, Inc. This corporate realtor was formed using James J. Baruch's realtor's license. During their association, Wyn Pope and James Baruch had always agreed that no deposits would be accepted which could not be used for construction after the mortgage commitment. In the past Mr. Baruch had rejected contracts which did not allow such use of the deposit. The Casa Tiempo contracts all contained such a provision and deposit monies were invariably used for construction with the knowledge of the purchasers. Only the contract with John Carosso was changed to provide for an escrow and to prohibit use of the deposit for construction. Mr. Baruch did not prepare or negotiate this contract and his only connection with the Carosso sale was to witness Mr. Carosso's signature. The contract was negotiated and altered by Wyn Pope without Mr. Baruch's knowledge or consent. Neither Mr. Baruch nor Wyn Pope Associates was a party to the contract and the contract said that the deposit would be held in escrow, but did not specify an escrow agent. As a party to the contract, Centennial acknowledged receipt of the deposit and thereby agreed to hold it in escrow. Since Mr. Baruch was not an officer or in any way a part of Centennial Development Corporation, he had no authority to approve or modify the contracts and no reason to believe that he needed to review each contract himself. Mr. Baruch was therefore not authorized to control the deposit which according to the terms of the contract was made to Centennial Development Corporation. Although the contract was signed July 6, 1979, no deposit was received until July 17, 1979. The changes regarding escrow, although typed in, were each initialed, indicating that the contract was changed after execution and witnessing. Given the ten-day delay and initialing, it is likely that the changes regarding the deposit were made in the contract after Mr. Baruch had witnessed Mr. Carosso's signature and as a condition of the deposit being actually paid. In that case, Mr. Baruch would have no way of knowing that the standard contract had been modified unless he checked each contract submitted by other salesmen. Contrary to paragraph 9 of Petitioner's Complaint, Mr. Baruch never had actual knowledge of the terms of the Carosso contract until the project was taken over by Casa Tiempo Builders, Inc., in May, 1980. Mr. Baruch received no commission on the Carosso sale and never received any part of the deposit. Mr. Baruch completely severed his connection with Wyn Pope Associates, Inc., and Casa Tiempo in March, 1980, and did not profit in any way from the additional deposits demanded and received by Joseph Falso in May, 1980. On or about August 7, 1980, John Carosso entered into an agreement for the completion of his villa in which he released Centennial Development from all claims connected with his deposit. John Carosso was injured by the use of his deposit only in that he lost the option of withdrawing his deposit and rescinding the contract. He could not have finished his home at the original contract price even if the deposit remained in escrow. All the homes in the project had appreciated greatly in value between the contract of July 6, 1979 and the May, 1980 meeting, thus it was to each owner's advantage to pay the 7,500 and complete construction. Because of this appreciation, Mr. Carosso could have paid the $7,500 and immediately sold the house in May, 1980 for enough to return his entire initial deposit plus a profit. One Mr. Hmeilewski, a contract vendee, did so with the help of the new management of Centennial. Selling his contract would thus have enabled Mr. Carosso to be in a better position than rescission and return of the deposit. He preferred to have the house at the increased price. Respondent's position is that he was not responsible for the deposit and should not be sanctioned for the events stipulated to, especially since no actual damage was incurred by Mr. Carosso and all claims against the Developer and escrow holder Centennial Development Corporation were released by Mr. Carosso.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Administrative Complaint filed against James J. Baruch be dismissed. DONE and ORDERED this 24th day of August, 1982, in Tallahassee, Florida. SHARYN L. SMITH, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of August, 1982. COPIES FURNISHED: Frederick H. Wilsen, Esquire Department of Professional Regulation State Office Building 400 West Robinson Street Orlando, Florida 32801 James H. Gillis, Esquire Staff Attorney Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Nicholas Rockwell, Esquire McCUNE HIAASEN CRUM FERRIS & GARDNER, P.A. 25 South Andrews Avenue Post Office Box 14636 Fort Lauderdale, Florida 33302 Samuel R. Shorstein, Secretary Department of Professional Regulation Old Courthouse Square Bldg. 130 North Monroe Street Tallahassee, Florida 32301 Carlos B. Stafford Executive Director Florida Real Estate Commission Post Office Box 1900 Orlando, Florida 32802

Florida Laws (3) 120.57475.25784.05
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer