BROWARD COUNTY vs. SOUTH FLORIDA WATER MANAGEMENT DISTRICT AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 80-001048 (1980)
Division of Administrative Hearings, Florida Number: 80-001048 Latest Update: Jan. 20, 1983

Findings Of Fact Existing Conditions Between 1952 and 1957 the United States Army Corps of Engineers (Corps) and the Florida Central and Southern Flood Control District (the forerunner of SFWMD) constructed a chain of levees, L-1, L-2, L-3 and later L-4 in eastern Hendry County, Florida. These levees which begin approximately 10 miles to the southwest of Lake Okeechobee run first east, then south and then east again for a distance of approximately 38 miles. The purpose of these levees is to shield the land5/ to the east of them from the natural sheet flow of water which comes from the west during the area's rainy season. The EAA which is protected from natural flooding consist of rich muck soils which have been successfully exploited for years by sugar cane farming. The present levees were created by excavating a "borrow" canal parallel to the southern and western sides of L-1, 2, 3 and 4. The borrow canal is no larger than was required to provide sufficient material for construction of the levees; nevertheless, the canal has a considerable water carrying capacity in the amount of 1,260 CFS 6/ at peak flow. The canal is a navigable fresh water of the state. It interconnects into other navigable canals which terminate in either Lake Okeechobee or the Miami River. The water carried by the borrow canal flows south and discharges into the Miami canal via either a pumping station designated S-8, or via the borrow canal next to L-28.7/ The water which enters the Miami canal ultimately travels to canal C-60 and then into the section of WCA-3 south of Alligator Alley (State Road 84). Flooding The rain water which once moved from west to east directly across the eastern portion of Hendry County, Florida into the EAA is now interdicted by L- 1, 2 and 3. As a result it ponds in the corner of the intersection of L-1 and L-2 (known in these proceedings as the L-1 angle). The area flooded is grass land used by Hendry County ranchers for the open grazing of beef cattle. Some of the pasture is improved, that is fertilized, but the majority of the area is unimproved range. During flood times the ranchers move their cattle to alternative pastures either to the north or to the west. The deepest flooding, when it occurs, is immediately next to the levees in the L-1 angle. The flooding has been known to reach depths as great as 10 feet and to extend westward for several miles. Because the land to the west of the L-1 angle is higher, the depth of the flooding decreases in a westerly direction. The duration of the ponding immediately in the L-1 angle has been as long as 80 days after a prolonged and heavy rainfall event. This flooding occurs despite the capacity of the borrow canal to remove 0.18 inch of flood water per day from the inundated area. When there is flooding in the L-1 angle there is also high water In the northeast corner of WCA-3A where some of the water from the borrow canal is presently discharged. During a dry season the land immediately adjacent to the present borrow canal suffers overdraining due to seepage of ground water into the canal and its resulting evaporation or conveyance south. Water Conservation Area 3A is part of a series of conservation areas established as their name implies to conserve water. Extending over portions of several South Florida counties including Palm Beach, Broward and Dade, they provide the recharge source for the Biscayne Aquifer and other aquifers which are the water supply for metropolitan South Florida. The water conservation areas are also wildlife refuges and provide natural habitats for numerous South Florida animals such as deer, alligator, and wading birds. Description of Project The Hendry County plan as described by the Corps in General Design Memorandum No. 2, 8/ envisions the construction of a flood control canal, C- 139, with two water flow control structures, S-239 and S-243. To create C-139, the Corps plans to further excavate the existing borrow canal next to L-2, L-3 and L-4 for a total distance of 37 miles. See Illustration I.* This excavation will result in the removal of 5.2 million cubic yards of earth and limestone. Some of the resulting spoil will be used to create a levee along the west side of C-139. Most of the excavation will be done by draglines on the canal banks. Upon its completion C-139 will be an immense water conveyance. At its northern end the canal will be only five feet across the bottom with a depth of 10.6 feet, but by the time the canal reaches WCA-3A it will have enlarged to a bottom width of 80 feet across and a depth of 19.5 feet. Its peak design capacity is 3,000 CFS. That is more than twice the present capacity of the existing borrow canal. Downstream from S-239 C-139 turns south to be designated C-139(S) and to gradually become increasingly shallower. This will cause a discharge pattern designed to create a sheet flow across WCA-3A. Benefits, Future Land Use It appears that when levees L-1, 2 and 3 were constructed the Corps failed to fully consider the adverse effect which would result from the impoundment of water by the new levees. According to the General Design Memorandum, Levees 1, 2, 3 and 4 were constructed in the mid 1950s to prevent flood waters originating on the then sparsely developed lands westward of the levees from contri- buting to flooding on the rich agricultural lands lying to the east of the levees. The original borrow canals were sized based on materials needed for the levee construction. The sparse economic development of the lands to the west precluded increasing the con- veyance capacity of these canals to prevent flooding on those lands. Construction of the levees and the subsequent increased de- velopment over the drainage area have aggra- vated flooding problems on the lands. Water stands on some of the land during practically the entire wet season virtually every year. As the landowners developed the land, they became increasingly vociferous about con- struction of works to alleviate the flooding for which they contend is project-induced. There is merit in their contention in that the adjacent project works adversely affected both depth and duration of flooding in the area west of Levees 1, 2 and 3. (Emphasis added) The facts presented at the instant final hearing are somewhat to the contrary, in that there was no showing of significant subsequent development west of the levees after their construction. For many decades vast family ranches have raised cattle on the mentioned lands as they continue to do today. The primary purpose of the proposed project is to now provide flood control to an approximately 261 square mile drainage basin west of the flood-causing levees.9/ With a design capacity of 3,000 CFS, C-139 can handle twice the water which drains through the present borrow canal. By way of comparison the present canal has a drainage capacity of .18 inches per day from the flooded area during a ten-year flood,10/ while C-139 has the capacity to drain .43 inches per day. This heightened discharge rate will cause land in the L-1 angle to flood less, and once flooded, to be underwater for a shorter period of time. For instance, an area which during a ten-year storm might have been submerged for 40 days prior to the construction of the project Is estimated to have an inundation period of only 10 days upon the project's completion. The significance of the reduced flooding to the landowners in the flooded area is difficult to gauge from the evidence. Because an intensification of land use would result in a lowering in the quality of the water which runs off the land and into C-139 and thence into the environmentally sensitive water conservation area,11/ the landowners supporting the project were understandably reluctant to testify that the project will allow them to use their land for more than continued cattle grazing. The testimony of Mr. Joe Hillard, a partner in Hillard Bros. of Florida, Inc., one of the larger ranches is illustrative: Q If this project, the flood control portion, were built, would your company change any of its land uses on this land that you described? A No, sir, not at all. Not with what I understand is going to be done with the project I wouldn't change anything. In response to the Hearing Officer's later inquiry, Mr. Hillard explained that the project would allow pasture land to be used for twelve months per year as opposed to the current nine months per year during a flood season. He does not anticipate grazing any more head per acre after the project. This evidence contrasted with the assumptions made by the Corps in that part of the General Design Memorandum which discusses the cost-benefit ratio of the project. The Memorandum states at p. 52: As noted previously, the existing activity within the area is predominately agricultural with major emphasis in beef cattle production. Local landowners and managers were asked to indicate the production changes they expected to make with the reduced flood hazards available under with (sic) project condi- tions. These expectations were prepared as a land use map with the basic control matrix. For the most part, these changes in land use represented more intensive types of agricultural cultivation. In some cases, existing beef pastures were expected to be replaced with sugarcane, truck crops, and citrus production. The majority of the changes were an upgrading of existing beef cattle operations. Such upgrading was affected (sic) by planting the more pro- ductive types of pasture such as clover and grass combinations, and the application of additional fertilizers and supplemental water. These expectations were assumed to exist under favorable cultivation conditions. Because of the nature of soil conditions in the project drainage basin, sandy with poor nutrient and water retention ability, it is unlikely that land use in the 261 square mile drainage basin will change significantly. As predicted by Mr. Hillard, it is likely that all the project would do is allow more grazing time on land which is now periodically flooded. Since it is not the function of this proceeding to inquire into whether the purported cost- benefit ratio of the project is accurate, no findings will be made concerning that issue. Project Permitting History The Hendry County portion of the Central and Southern Florida Flood Control project for flood control west of levees 1, 2 and 3 was authorized by the Congress of the United States in the Flood Control Act of October 27, 1965. The Army Corps of Engineers is the actual builder of the project, but SFWMD is the local sponsor and is the Corps' agent in applying for the necessary permits from DER. The Department as the permitting agency is in a curious position here. Its Bureau of Water Resources (BWR) was responsible for the State Public Works Program through which Florida requested Congress to fund the Hendry County Project. Mr. Charles Littlejohn who was head of the Bureau in 1976 had the responsibility of lobbying in Washington for funding of the project. The DER through its Bureau of Permitting is now asked to pass on the validity of a project which the BWR has so vigorously promoted. The Department's uncomfortable posture was recognized by its permitting staff. In a memorandum dated March 9, 1979 to Mr. E.D. "Sonny" Vergara, Mr. Forrest Fields at DER wrote: I told Mr. Brown, as I told you yesterday that I felt rather awkward in reviewing for permitting a project which the agency had endorsed for the public works list." Every year projects being sponsored for federal approval are reviewed by a process In the Division of State Planning called the A-95 Clearinghouse.12/ The Hendry County Project had a checkered history there. Serious objections concerning the environmental impact of the project were raised; nevertheless, DER through the BWR continued to seek and was successful in obtaining federal funding. On November 15, 1978, SFWMD filed an application with DER for the requisite permits to begin construction. During the course of DER's review of the project several issues arose between the parties. Among them were: Whether local approval pursuant to Section 253.124, Florida Statutes would be required? Would an exception from dissolved oxygen (DO) standards be necessary? Whether local water quality standards would apply if they were stricter than state standards? Local Approval As early as February 19, 1979, DER noted that plans submitted by the applicant proposed the placement of fill in waters of the state. In a letter to Mr. Lee M. Brown of SFWMD, Mr. Forrest Fields, the DER permit processor, observed: Second, on page 2/11 of your drawings, you indicated that approximately 5,800 cubic yards of fill material will be placed water- ward of ordinary mean high water. I pre- sume that this fill is associated with structures S-243 and S-239. Pursuant to Section 253.124, Florida Statutes, approval of this filling by resolution of the local government is required. To do this I will, upon receipt of the Department of Environ- mental Regulation field report, summarize and send this to the Hendry County Commission. The Commission will have to consider this report, and, by vote, adopt a resolution approving the project. I will send you a sample resolution. The requirement of local approval was reiterated numerous times. In March, 1979, Mr. Fields sent a staff report of a biological survey of the project to the Hendry County Commission for consideration in their approval of the project. During a meeting on March 21, 1979 in the DER Secretary's office representatives of SFWMD were told that local approval would be required. On April 10, 1979 the County Commissioners of Hendry County gave their approval to the project. In correspondence to Mr. Charles Lee of the Florida Audubon Society, Secretary Jacob D. Varn noted that the permit applications were still incomplete because local approval for filling associated with the two water control structures had not yet been received by DER. During a public meeting held on May 22, 1979, the County Commissioners of Broward County, after three and one-half hours of testimony, voted 6-0 against approving the project as it related to fill in Broward County. Subsequent to that vote the Corps and SFWMD asserted that local approval by Broward County was not required. In response to this assertion Mr. Charles Littlejohn, on behalf of the Secretary, requested a legal opinion from DER's General Counsel. On October 30, 1979, General Counsel's Legal Opinion 79- 72 concluded that the Department could assert Chapter 253 jurisdiction over the project and therefore "local approval" is a statutory requirement for its permitting. On March 17, 1980 Mrs. Evelyn Jackman of Jackman and Sons, Inc., one of the major ranchers in the project drainage basin, wrote to Governor Graham to urge the rapid approval of the project. Her correspondence was forwarded to DER for an appropriate response. Ms. Victoria J. Tschinkel as Assistant Secretary noted in her reply on April 3, 1980 that: Pursuant to Section 253.124(3), Florida Statutes approval must be obtained from the County Commissioners before we can complete the processing of a permitting application for fill in navigable waters. Approval has not been received from Broward County and there Is fill proposed for the Broward County portion of the project. Ms. Tschinkel did, however, assure Mrs. Jackman that: The Department of Environmental Regulation is sympathetic to the problems outlined in your letter, and for that reason the Depart- ment has made this project part of its public works package given each year to Congress. We still support this as a public works pro- ject and for that reason we are attempting to work out the permitting problems as ex- peditiously as possible. Shortly after Ms. Tschinkel's letter was sent there was another meeting in the Secretary's office to discuss the project. Mr. Lotspeich's interoffice memorandum outlines the Department's new position as it related to local approval. In addition, the issue of what constituted fill pursuant to Chapter 253, Florida Statutes, for local approval purposes was discussed. Helen Setchfield also partici- pated in this discussion. After Helen and I looked more closely at the project, it appeared that only a concrete structure (S-239) was to be placed waterward of OHW.13/ We both agreed that in past permitting practices we had not required local approval for the construction of structures waterward of OHW, but only when fill to extend existing lands or create new lands was involved. Since the application drawings did not clearly show the relation of the fill and structure relative to OHW and sheet 2 of 11 clearly indicates that fill will be placed "below MHW" Forrest must have assumed that local approval would be required if the canal was determined to be under Chapter 253, Florida Statutes jurisdic- tion. GCO-79-72 from Randie Denker indicated that the Department can assert Chapter 253, Florida Statutes jurisdiction in the canals and therefore local approval would be required. It would appear that there was really no clear understanding as to what the "fill" consisted of in the case of structure 239. Conversation with Mr. Walker [counsel for SFWMD] and Messrs. Parsons [counsel for Alico and other landowners] and Davis [SFWMD] indicated that there was no intention to place fill in the canal waterward of OHW and that the concrete structure would span the entire canal width. Since the application drawings did not clearly show the relation of the structure and fill re- lative to existing OHW, Mr. Walker said he would provide new drawings which would show this. Helen and I discussed the situation and we scheduled an appointment to talk the problem over the (sic) Terry Cole. It was agreed at the meeting that simultaneous "intent" letters would be sent on May 5, 1980 from permitting and the exception review people. May 16, 1980 DER entered into a Stipulation with SFWMD which states in its entirety: The SOUTH FLORIDA WATER MANAGEMENT DISTRICT and the DEPARTMENT OF ENVIRONMENTAL REGULA- TION for purposes of this proceeding hereby stipulate and agree that: The DEPARTMENT OF ENVIRONMENTAL REGULA- TION has jurisdiction under Chapter 253, Florida Statutes, to require permits autho- rizing construction and other activities described in the application which is the subject of this proceeding. None of the activities or construction, including the construction of the proposed Spillway S-239, as described in the appli- cation which is the subject of this pro- ceeding, constitute construction of islands or an addition to or extension of existing lands and islands so that approval of local governments as described in Section 253.124, Florida Statutes, is not required. This Stipulation is executed by counsel for each party on the date shown. On May 20, 1980 coordinated letters of intent to grant permits for the construction of the project were issued. Pursuant to the Stipulation local approval was no longer being required by DER. Alternative Site Specific Criteria After receipt of SFWMD's permit application for the construction of C- 139 and associated structures, DIR noted that it did not have adequate data on dissolved oxygen. In correspondence dated March 9, 1979, Mr. Forrest Fields said: Fourth, the dissolved oxygen data are not adequate. The available data were col- lected during daylight, only, and these data include occasional concentrations of less than 4.0 mg/l. In an effort to re- solve these deficiencies so that reasonable assurances may be provided, you, Walt Dineen, and I will discuss the South Florida Water Management District data on Thursday, March 15. The results of the March 15, 1979 meeting were memorialized by Mr. Fields in a file memorandum dated March 19, 1979. The memorandum stated in pertinent part that: On March 15, 1979, Mr. Lee Brown, Mr. Walt Dineen, and Mr. Fred Davis, from SFWMD, called to discuss the staff's request for "reasonable assurance" re. the Department's water quality standards. Mr. Davis, the applicant's chief chemist, said that, throughout the Everglades, in both canals and conservation areas, the water quality standards for both conductivity and dis- solved oxygen are frequently violated. He asserted that this is typical of the area. He believes that these data represent natural background. The situation regarding affirmative, reasonable assurance appears to be this: widespread and frequent observations of DO data which are less than the minimum for Class III waters commonly occur within the existing L-1, L-2, L-3 canals. The increase in depth associated with C-139 is predicted to exacerbate existing stress- es on the DO regime.... However, the SFWMD's response does not constitute reasonable assurance re. other Class III standards. The District's DO and conductivity data may conceivably supply assurances that these standards will be violated in C-139. (Whether background DO and conductivity violate the standards may become important.) The District appears to have two alternatives: 1) attack the Class III standard; 2) apply for variances for, at least, DO and conductivity. A follow-up meeting was held on March 21, 1979. Again, in a file memorandum dated March 28, 1979 Mr. Fields wrote: Consideration of reasonable assurance began at the March 15, 1979, conversation among Messrs. Brown, Davis and Fields. According to the SFWMD, widespread and frequent violations of the Class III water quality standard for dissolved oxygen, as contained in Chapter 17-3, F.A.C., occur throughout the Everglades, in the canals, agriculture areas, Lake Okeechobee, and the conservation areas. The existing borrow canals follow this pattern. The SFWMD alleges that this condition is natural back- ground. They agree that it is probable that any existing DO stresses exist in the borrow canal will be exacerbated in the proposed C-139. However, both the former and present editions of Chapter 17-3 F.A.C. allow for exceptions for natural background. The SFWMD will review these rules to determine which regulatory approach will be taken. In addition, the SFWMD will supply to DER data for the "benchmark" station in the L-28 canal and at Everglades National Park to demonstrate lower back- ground concentrations of DO. Furthermore, the SFWMD will apply, per Ch. 403.087, F.S., for a temporary operating permit for the completed structure. Conditions governing private connections and incor- porating BMPs may be included in the TOP. On April 5, 1979, SFWMD submitted in support of its original permit application a document called Evaluation of Natural Background Dissolved Oxygen in Conservation Area 3-A, South Florida. This evaluation received unfavorable reviews at. DER. Landon P. Ross, chief biologist, wrote in an April 9, 1979 memo that: I have reviewed the data provided by SFWMD regarding background DOs in the Everglades area and have the following comments: Indication that DOs are not harmful to local organisms are, in a legal sense, irrelevant to the question. The data provided give evidence of the occurrence of low DOs in the area. Since the measured low DOs seem to be from artificial drainage channels, they can hardly be supposed to be "natural". The measures that SFWMD provided, however, do not seem too different from the values that I would expect to find in a natural swamp habitat. The proposed "standard" cannot be logically derived from the DO measurements provided. This Evaluation was later submitted in support of first Petition for Exception noted infra. In his review of the data Mr. Fred Bartleson at DER wrote:14/ The data submitted by the South Florida Water Management District does not justify the requested exception for dissolved oxy- gen criteria for the Hendry County Project. The petition alleges that D.O. concentra- tions lower than 1.0 mg/l occur in the re- ceiving waters of Conservation Area 3A. However, the data submitted from that area indicate a minimum value of 2.3 mg/l. The value cited in the petition of less than 1.0 mg/l was recorded in the L-3 borrow canal adjacent to the conservation area. This canal drains an agricultural area. Similar data from the L-28 east canal which is less affected by cultural activity depicts minimum D.O. values between 3 - 2 mg/l. The low D.O. values found naturally in fresh- water wetlands during the warmer months ob- viously result in stress to the biota. The introduction of larger quantities of water from the proposed Hendry County Project, which is anticipated to have lower D.O. values as well as nutrients and pesticides from agricultural runoff, could adversely affect the ecosystem. The proposed exception allowing discharge of water with not less than 1.0 mg/l for more than two consecutive hours in any 24-hour period is arbitrary and not supported by data. It may well be that an exception could be granted for some lowering of the D.O. criteria with time constraints. However, more defini- tive and conclusive data are required to in- sure that this action would not cause adverse effects. The burden of supplying this infor- mation should rest with the petitioner. His views were supported by Messrs. Kevin Edwards, Vernon Myers, and G. J. Thabaraj. Mr. Edwards also noted the difference in DO readings between the WCA- 3A and the borrow canals. SFWMD filed a Petition for an Exception on July 23, 1979. The Petition alleged that the receiving waters of the proposed discharge are located in WCA-3A and that due to natural causes that portion of WCA-3A which will receive the discharge does not meet the state standards for DO as set out in Section 17-3.121, Florida Administrative Code. The DO levels of the proposed discharge are alleged to be similar to those levels already present in the water conservation area. In response to the Petition DER requested more information by a letter from Stephen Fox dated August 29, 1979. The letter requested: Data which supports the contention that the condition of the waters is the re- sult of natural causes, that is, there is an absence of man-induced alteration; or Data which supports the contention that the condition of the waters is the re- sult of man-induced causes which cannot be controlled or abated with technology or management practices. Data which supports the contention that the biota have not been adversely af- fected or will not be affected adversely. The data submitted with the application did not address the possibility that the low dis- solved oxygen levels may be caused by the practice of pumping water off the agriculture areas during the summer wet season. Compari- son with similar subtropical, undisturbed aquatic environment should be made. The dis- solved oxygen data should be compared with pumping schedules and with dissolved oxygen values of water pumped. Comprehensive water- shed and land use data is needed for a thorough review. Further, the data submitted did not support the contention in the petition of a corre- lation between C.A. 3A and canals L-3 and L-28. Also, the contention that in C.A. 3A dis- solved oxygen concentrations were below 1.0 mg/l were recorded was unsupported. The data array was not adequate in terms of distri- bution and frequency of sampling, to demon- strate that the dissolved oxygen regime ap- proaches the proposed alternative criteria. On October 2, 1979, E. D. Vergara summarized the status of the SFWMD application for the DER Secretary, Jacob D. Varn. His memorandum with respect to dissolved oxygen states: ... (permits) originally requested under old 17-3 rules, it was found quality assurances could not be made due to a naturally occurring condition of low DO. The Department requested information sup- portive of the low DO background, but due to differences in opinions among the biologists, the district elected to re- quest an exception under the provisions of the new 17-3 rule instead. Additional information has now been requested by the Department to support the request for an exception, and the District is cur- rently putting this together. It is the general feeling that with this additional data, granting the exception should be possible. SFWMD responded to Mr. Fox's letter above by submitting in the Spring of 1980, an Amended Petition for Exception from Criteria. In its Amended Petition the District abandoned the comparison, found in the original petition, of the proposed discharged waters' dissolved oxygen levels to the levels found in the water conservation district. Instead the District concentrated on a comparison of the dissolved oxygen levels in the proposed discharge waters to the levels in the relatively clean canals in the South Florida area, specifically the L-28 canal system. The District proposed that as an alternative to Class III standards the following criterion be established: During any 24-hour cycle the dissolved oxygen concentration within the photic zone shall exceed 1.0 mg/l, except during the extreme low point when values shall not be less than 1.0 mg/l for more than two consecutive hours. (Emphasis added) Accompanying SFWMD's Amended Petition was a report (Supporting Report) dated February, 1980, which provided a voluminous compilation of data to justify the alternative standard proposed.15/ On April 8, 1980, Ms. Helen Setchfield sent a memorandum to DER staff requesting that they review the Amended Petition and report back to her within five days. Also on April 8, 1980, after a meeting attended by both SFWMD representatives and DER representatives, it was decided that DER would issue coordinated letters of intent on May 5, 1980 for both the exception and the dredge and fill applications. In spite of the decision to issue letters of intent, DER permitting staff were not satisfied with the concept that ban-made canals were "natural" background or that the proposed DO standard was reasonable. On April 16, 1980, Rick Lotspeich wrote to Suzanne Walker, Chief of the Bureau of Permitting, that: I have reviewed the referenced "request for exception" and it appears that the petition and supporting report are suf- ficiently complete to allow evaluation of the merits of the request. It would appear that the proposed dis- solved oxygen standard of 2.0 mg/l over 24 hours and 1.0 mg/l "during the extreme low point" for not more than two hours, is excessively low and not warranted by the data presented. A review of the data from figures 4 and 5 generally indicate that the following standard would be appropriate: Dissolved Oxygen: The concentration should not average less than 4.0 mg/l in a 24-hour period and not less than 3.0 mg/l except during the months of June--September, when the concentra- tion shall not average less than 3.0 mg/l in a 24-hour period and never less than 1.0 mg/l. Later, after having received comments from Rick Cantrell and Bob Siciler, Mr. Lotspeich wrote to Ms. Walker the following: My recollection from reading the request for exception was that SFWMD had indeed recognized the fact that the canals and their design had contributed to the de- pressed DO values of the water in them. Pursuant to Subsection 17-3.031(1), Florida Administrative Code, there may be a consideration for "man-induced causes which cannot be controlled or abated I am in full agreement with Cantrell and Siciler's discussion of the adverse impacts that canals in general, and the specific canal involved in this project, have on water quality and biological resources. However, I disagree with the conclusions that they reached. Clearly, there are extenuating circumstances involved in this case which set it apart from other dredge and fill cases. In light of these circum- stances, the fact that the depressed DO levels have resulted from man-induced causes which cannot be controlled, and Cantrell and Siciler's own statement that approval of this project has little probability of worsening the existing water quality of L-2, L-3 and WCA-3, I would recommend that the exception be granted. However, the alternate DO standard which I recommended in my previous memo is still applicable. (Emphases added. The "extenuating circum- stances" were never explained.) Subsequently, on May 20, 1980, the Department issued a coordinated letter of intent to grant an exception but for the standard proposed by Mr. Lotspeich, not that requested by the Water Management District. Dissolved Oxygen and Exception Section 17-3.121(14), Florida Administrative Code requires that discharges into fresh waters of the state must exhibit dissolved oxygen concentrations of 5.04 mg/l or more. Normal daily and seasonal fluctuations above that level must be maintained. Dissolved oxygen in certain concentrations is required for aquatic life. The amount of oxygen contained in water is subject to numerous variables, many of which are interrelated. They include: amount of sunlight entering the water, ability of the water to transmit light, photosynthetic activity of aquatic plants, water temperature, mechanical oxygenation, mixing with other water which may have either a higher or lower dissolved oxygen content, depth of water, rate of oxygen consumption by resident biota, and time of day. It is undisputed that during certain seasons and times of day the water in the existing borrow canal does not meet the state dissolved oxygen standard. Readings as low as 0.9 mg/l have been obtained there. These low readings usually occur in the months of heavy rainfall, primarily July through September. See the data on Figure 4 of SFWMD's Supporting Report. Similar, though not so low measurements have been obtained in neighboring man-made canals such as L-28. L-28 has been used by water quality experts as a "benchmark" for canal water quality since it does not receive large amounts of runoff from agricultural areas where pollutants such as fertilizers are used. There are numerous times during a given year that the dissolved oxygen levels in L-28 are below the 5.0 mg/l state standard. It is also possible to find at least two locations in WCA-3A wetlands where dissolved oxygen readings are below Class III standards. At Gauge 3-2 in the northwest corner of WCA-3A near where the project would discharge, dissolved oxygen levels have varied from 2.3 mg/l to 10.8 mg/l; however, the mean value for the measured levels has been 5.5 mg/l as reported on Table 2 of the Supporting Report.16/ Unfortunately, the data regarding dissolved oxygen concentrations in the proposed discharge area are scant. This paucity was recognized by the Supporting Report which states at page 6: "No systematic study of the dissolved oxygen conditions or requirements for fresh water wetlands in general, or WCA-3A in particular, have yet been conducted." Despite the limited data on WCA-3A, certain comparisons between DO readings in it and in the borrow canal which would discharge into the area can be made. Readings taken at Gauge 3-2 do not sink to levels as low as those found in L-3. Compare Figure 4 of the Report to Table 2. The minimum readings taken in L-3 were during those periods of greatest discharge. If the discharge from the existing borrow canal were presently sent into the area of Gauge 3-2 during months of peak discharge, the waters entering WCA-3A would have a lower dissolved oxygen concentration than would exist naturally in the area. It is not surprising that water in the borrow canal exhibits unusually low dissolved oxygen levels. The levee sides limit reaeration which could occur due to wind movement. The surface-to-volume ratio is also unfavorable. Much oxygenation occurs at the interface between the water and surrounding air, but because the canal is relatively deep compared to its surface area, the proportion of water coming into direct contact with the air is low.17/ The depth of the photic zone, i.e., the section of water penetrated by light, is limited due to the naturally high color of canal water. Construction of C-139 will add somewhat to a lowering of dissolved oxygen levels in the entire canal water column. To increase its conveyance capacity, the existing borrow canal will be deepened significantly, particularly in its southern reaches. This deepening will result in a lowering of the ratio between the area of water surface to the depth of the canal. No mathematical data were presented by which the lowered ratio can be computed; however, an examination of Plates A-24 and A- 25 of the General Design Memorandum indicates that completed C-139 will contain a higher ratio of water below the photic zone than is presently contained in the borrow canal.18/ This is true only during those times when the canal is relatively full of water. As the canal level drops during a drought the photic zone will approach the canal bottom in the shallower sections. Both SFWMD and DER have proposed site specific DO alternative standards. These have been set out in the foregoing discussion of the permitting history. There is a significant difference between the proposals. SFWMD's proposal includes only the waters contained in the photic zone. It fails to recognize that during times of discharge, the waters of C-139 which are deposited in WCA-3A will not be only those of the photic zone, but will come from the entire water column of the canal. While SFWMD's standard might be acceptable for C-139 when it is in a no discharge state, the standard is completely unacceptable when the canal is discharging. Neither the standard proposed by DER nor SFWMD recognizes the difference between the dissolved oxygen regime which can be predicted for C-139 and that presently existing in WCA-3A. The data submitted would justify an exception from the present 5.0 mg/l Class III standard. There are certainly times when both the water existing in relatively unpolluted canals and in the water conservation area contain less than the present minimal content of dissolved oxygen. When C-139 is not discharging an exception, which would have a range now exhibited by the existing borrow canal, would be justified for the new canal. Sufficient data was not presented here to suggest the precise figures for such an exception. The information given for L-3 for instance, is compiled from samples taken only once during a given day. The water depth of the sample is not given. Accurate data would account for the diel variation and the effect of water depth on each sample. Without data which gives a daily average, it is impossible to determine if the water either standing in, or discharging from C- 139 will meet any proposed alternative criterion. For the same reason the data obtained for the present DO concentrations in WCA-3A is incomplete for establishing appropriate levels for discharge waters entering that area. The establishment of site specific alternative criteria must await the submission of more complete dissolved oxygen readings from the applicant. One of the elements in considering whether to grant an exception to established standards is whether the existing biota have adapted to the background DO levels. The proof here shows that the fish and other biota now living in the borrow canal either tolerate or have adapted to the present low DO regime there. It has also been proven that the biota in WCA-3A are tolerant of the naturally occurring low DO levels in that area. It was not shown how they would respond to a massive influx of low DO water when C-139 would be discharging. Hydroperiod in WCA-3A The northwest corner of WCA-3A, where C-139 and C-139(S) will discharge, has a higher ground elevation than that of the southern portion of the water conservation area. The highest elevation in the extreme northwest corner is approximately 17 feet above mean sea level (MSL). It tapers down to approximately ten feet MSL at the southern boundary of WCA-3A. The project is designed to facilitate the sheet flow of discharge water from the northwest area towards the southeast with an ultimate destination being flow into the Miami canal. The construction of the Miami canal, C-123, which runs on a northwest- southeast diagonal across the area, causes overdrainage of the northwest section. The borrow canal along Alligator Alley also contributes to excess runoff. This overdrainage has shortened the hydroperiod in the northwest corner from approximately 9 to 10 months to approximately 5 to 7 months. "Hydroperiod" is the span of time during which land is inundated by ponded water. The shorten hydroperiod has a profoundly destructive impact on the natural environment. The muck soil when not submerged oxidizes at an accelerated rate. At the present time the rate of oxidation in the northwest corner is more rapid than the replacement rate. Since the natural hydroperiod has been altered muck fires have been more severe and frequent. These fires destroy existing tree islands which dot the Prior to 1974 WCA-3A received discharges from the waters of the L-1, 2 and 3 borrow canal. The outlet of the canal at L-4 was determined to be inadequate for flood control purposes in the L-1 angle. To increase the discharge rate of the borrow canal culverts G-88 and G-89 were installed at the L-3/L-4 intersection in October of 1974. G-89 directs part of the flow from the L-3 canal into canal L-28 west, and then into pumping station 5-140 and into C- 60 (parallel to Alligator Alley). G-88 directs another part of the flow from the L-3 canal into the L-4 borrow canal and then into S-8 where it is pumped into the Miami canal. Rather than being allowed to flow in a shallow sheet across the water conservation area, the direct water flow is now sent southeast in canals for ultimate discharge outside the area. This waste would be eliminated by the proposal to have C-139 discharge into WCA-3A via C-139(S). There is no dispute that more water is needed annually in the northwest corner of the water conservation area. What is at issue here is the timing of placing additional water there. Generally when there is flooding in the L-1 angle and C-139 would be discharging at its maximum rate there is already flooding in WCA-3A. Rainstorm events are somewhat regional and cover both areas. The applicant estimates that if the volume of water discharged by C-139 in a two-week period were to be instantaneously spread over the northwest corner of WCA-3A 20/ it would raise the water stage by 0.4 feet. This would occur during a one in ten year storm. At that time the wildlife in the water conservation area would already be stressed by high water levels. A 0.4 foot increase in stage could kill deer and other terrestrial animals and destroy alligator nests, but it also could benefit the more aquatic animals. The result of this increase cannot be accurately predicted on the data supplied by the applicant.21/ While expert witnesses on behalf of the applicant were willing to express an opinion that the influx of drainage water from C-139 would be beneficial, the opinions were simplistically based on the unsupported assumption that because WCA-3A currently suffers from overdrainage, any additional water at any time would be beneficial. It is possible that those opinions were based on studies conducted which prove that a discharge of water such as will come from C-139 may create a beneficial increase in the marsh hydroperiod. Unfortunately, no evidence of the existence of such studies is in this record. The applicant's expert witnesses' opinions are therefore given little weight. In the present situation WCA-3A receives some water from the borrow canal during the dry season when additional water is most beneficial. At the expense of overdraining the land west of the borrow canal, ground water seepage now enters the canal and travels south through L-1, 2 and 3. After the construction of S-239, designed to prevent overdrainage, any possible flow into WCA-3A during dry periods will be cut off. No evidence was presented on what quantity of water WCA-3A will lose during a dry season due to S-239. Also the record does not reflect what effect that reduction will have on biota in the water conservation area. S-239 and Fill When the level of water in the borrow canal drops below the nearby water table, there is groundwater seepage laterally into the canal. If C-139 were to be constructed without any water control devices, it would exacerbate the overdrainage because it will be a far more efficient conveyance than is the borrow canal. S-239 has been designed to prevent this overdrainage. The structure will be located in Broward County. On May 22, 1979 the County declined to give its approval of the use of any fill, as the term is used in Section 253.124, Florida Statutes, for the construction of this project in Broward County. The Department of Environmental Regulation has not maintained a consistent unwritten policy on what is "fill" in navigable waters of the state.22/ Testimony from past and present Department employees indicated that at times a "use" concept was employed to determine what was fill. If additional dry land were created which would be used for commercial purposes, then the newly created land was called fill which required local approval. At other times use was unimportant. The test was whether or not the result of the additional material would be moving the point, at which the high water mark intersected the land, in a waterward direction. It is found that what constituted fill in past permit cases depended upon the personal interpretation of each Department employee. S-239 as proposed is a massive structure which will cost 1.32 million dollars 23/ to build. It will contain 11,000 cubic yards of fill and backfill; 530 cubic yards of 1' by 1' pieces of stone rip-rap; 1,230 cubic yards of concrete and 647,000 pounds of cement. 153,800 pounds of reinforcing steel will be required. The structure will be over 50 feet high and will span C-139 where it is 60 feet wide. Each of the two vertical lift gates which control the water flow will be 27 feet wide. See Illustration II.* In between them will be a concrete pier three feet wide and approximately 38 feet long. The cement bottom of the structure will rise from an elevation of 8.0 feet MSL to a crest of 3.3 feet MSL for a total height of 11.3 feet. In order to allow service vehicles to pass across the canal a bridge 13 feet wide will span from one bank to the other. This bridge will support large trucks. The stone protection provided for in the plans consists of 1 foot square pieces of rip-rap to be placed 40 feet immediately upstream from the control gates and 30 feet immediately downstream of the gates. The purpose of this protection is to prevent erosion of the canal bottom and sides where the water flows by at a relatively high velocity. The majority of rip-rap will be placed below the ordinary high water mark. Local Water Quality Standards The issue of local water quality standards arose late in the permitting process. DER had already issued two letters of intent to SFWMD before the Department gave consideration to standards promulgated by Broward County. It appears from the record that the Broward County standards were formally brought to DER's attention through the County's Petition for Formal Hearing filed on June 3, 1980. On June 26, 1980, DER issued an amended letter of intent which said: This letter is an amendment of the letter of intent to issue signed by the Department on May 20, 1980. In that letter, the Depart- ment stated: "This intent to issue is contin- gent upon the applicant being granted an exception from the criteria for dis- solved oxygen, for Class III waters, pursuant to Section 17-3.031, Florida Administrative Code." The preceding paragraph is hereby amended to include a provision that the applicant must obtain relief from the dissolved oxygen stan- dards that appear in Section 27-5.072(19), Broward County Code, through a variance or other legal mechanism, in addition to the exception from state standards for dissolved oxygen. Section 27-5.072(19), Broward County Code, states that DO is to have a "daily average not less than 5 mg/l; single reading never less than 4 mg/l. The May 20, 1980, letter also contained a paragraph that read: "However, should the Department grant an exception from the dissolved oxygen criteria pursuant to Section 17-3.031, Florida Administrative Code, the Division intends to issue the permit." This paragraph is hereby stricken and the following paragraph substituted: "If the Department grants an exception from the State dissolved oxygen criteria pursuant to Section 17-3.031, Florida Administrative Code, the Division intends to issue a conditional permit which will only become valid upon the granting of relief by Broward County from its existing local standards for dissolved oxygen." The Department is taking this position upon consideration of Section 403.182(6), Florida Statutes, which requires the Department to en- force all stricter or more stringent rules, regulations or orders in the jurisdiction where they apply. It is the Department's position that it is without discretion to grant relief from Broward County's local standard for dis- solved oxygen. By its Petition the County alleged that it has an approved local pollution control program and that the proposed project will violate its local standards for dissolved oxygen and nutrients found in Sections 27-117(b)(9) and 27-117(11) of the Broward County Code.24/ Neither SFWMD nor the Corps has applied to the Broward County Environmental Quality Control Board for either a license under Chapter 27 of the County Code or for a variance from the standards established therein. On April 20, 1972, the Florida Department of Pollution Control (the predecessor of the Department of Environmental Regulation) gave temporary and conditional approval for six months to the Broward County Pollution Control Program. This approval provided that the County has full authority to enforce its own laws, rules and regulations, provided that they must be as strict or stricter than those of the State. The County was also required to modify its rules if the State subsequently adopted the regulations in conflict with those of the County. On November 7, 1972, the Department of Pollution Control gave Broward County full and final approval pursuant to Section 403.182, Florida Statutes. Subsequently, in 1974 and 1976 the State and Broward County entered into new agreements. These agreements were the result of DER's desire to make uniform all its agreements with all qualified local programs. The Broward County pollution control program including the portion administered by the Environmental Quality Control Board, continues to be an approved local program as defined at Section 403.182, Florida Statutes.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Department of Environmental Regulation enter an Order denying South Florida Water Management District's application for a water quality permit and for a dredge and fill permit. DONE and RECOMMENDED this 13th day of October, 1982, in Tallahassee, Florida. MICHAEL PEARCE DODSON Hearing Officer Department of Administration Division of Administrative Hearings Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of October, 1982. * NOTE: Illustration I, noted in paragraph 8 and Illustration II, noted in paragraph 49 are not a part of this ACCESS document. Illustrationn II is available for review in the Division's Clerk's Office.

Florida Laws (6) 120.57120.60253.12403.087403.18290.803
# 1
BERNARD J. PATTERSON AND VIRGINIA T. PATTERSON vs CITY OF DELTONA AND ST. JOHNS RIVER WATER MANAGEMENT DISTRICT, 04-002408 (2004)
Division of Administrative Hearings, Florida Filed:Deltona, Florida Jul. 12, 2004 Number: 04-002408 Latest Update: Jul. 25, 2005

The Issue The issue is whether the applicant for an Environmental Resource Permit ("ERP"), the City of Deltona ("City" or "Applicant"), has provided reasonable assurance that the system proposed complies with the water quantity, environmental, and water quality criteria of the St. Johns River Water Management District's ("District") ERP regulations set forth in Florida Administrative Code Chapter 40C-4, and the Applicant's Handbook: Management and Storage of Surface Waters (2005).

Findings Of Fact The District is a special taxing district created by Chapter 373, Florida Statutes, charged with the duty to prevent harm to the water resources of the District, and to administer and enforce Chapter 373, Florida Statutes, and the rules promulgated thereunder. The City of Deltona is a municipal government established under the provisions of Chapter 165, Florida Statutes. The Lake Theresa Basin is comprised primarily of a system of interconnected lakes extending from Lake Macy in the City of Lake Helen to the Butler Chain of Lakes (Lake Butler and Lake Doyle). The Lake Theresa Basin is land-locked and does not have a natural outfall to Lake Monroe and the St. Johns River. In 2003, after an extended period of above-normal rainfall in the Deltona area, the lakes within the land-locked Lake Theresa Basin staged to extremely high elevations that resulted in standing water in residential yards, and rendered some septic systems inoperable. Lake levels within the Lake Theresa Basin continued to rise and were in danger of rising above the finished floor elevations of some residences within the basin. On March 25, 2003, the District issued an Emergency Order (F.O.R. No. 2003-38) authorizing the construction and short-term operation of the Lake Doyle and Lake Bethel Emergency Overflow Interconnection. Since wetland and surface water impacts would occur, the Emergency Order required the City of Deltona to obtain an ERP for the system. The project area is 4.1 acres, and the system consists of a variable water structure on the west shore of Lake Doyle connected to a series of pipes, swales, water control structures, and wetland systems which outfall to a finger canal of Lake Bethel, with ultimate discharge to Lake Monroe and the St. Johns River. The first segment of the system extends downstream from the weir structure on the west shore of Lake Doyle via a pipe entrenched in the upland berm of the Sheryl Drive right-of-way. The pipe passes under Doyle Road and through xeric pine-oak uplands to the northeast shore of a large (approximately 15 acres) deepwater marsh. Water flows south through the deepwater marsh where it outfalls through four pipes at Ledford Drive. Two of the four pipes are overflow structures, controlled by canal gates. The pipes at Ledford Drive discharge into a ditch and into a large (greater than 20 acres) shallow bay swamp. The south end of the bay swamp is defined (and somewhat impounded) by a 19th Century railroad grade. Water flows through the bay swamp where it outfalls through five pipes at the railroad grade. Three of the five pipes are overflow structures, controlled by channel boards. The pipes at the railroad grade discharge to a 1500-foot long finger canal that was dug some time during the period 1940-1972 from the north central shore of Lake Bethel. The overflow interconnection system has three locations whereby the system can be shut down: 1) Lake Doyle--a control weir, controlled by three sluice gates; 2) Ledford Drive--two thirty-inch reinforced concrete pipes, controlled by canal gates; and 3) railroad grade--three thirty-inch reinforced concrete pipes, controlled by channel boards (collectively referred to as "Overflow Structures"). The Overflow Structures are designed to carry the discharge of water from Lake Doyle to Lake Bethel. With the Overflow Structures closed the system returns to pre-construction characteristics, meaning there will be no increase or decrease in the quantity or quality of water throughout the path of the system as a result of the project. An unequivocal condition of the permit is that the system would operate with all of the Overflow Structures closed. As an added assurance, the City proposes to place a brick and mortar plug in the Lake Doyle weir structure outfall pipe to prevent any discharge from the weir. The City has submitted to the District preliminary plans for a future phase in which the system would be modified for the purpose of alleviating high water levels within the Lake Theresa Basin when the water level in Lake Doyle rises above an elevation of 24.5 feet. The District shall require a separate permit application to be submitted for such future plans. Petitioner, Barbara Ash, has lived on Lake Theresa for 19 years. Ms. Ash lives upstream from the area of the weir that will be plugged in accordance with the ERP. She does not trust either the City of Deltona to comply with or the District to enforce the conditions of the ERP applied for by the City. Petitioner, Barbara Ash, also served as the qualified representative for Petitioners, Francell Frei, Bernard J. and Virginia Patterson, and Ted and Carol Sullivan. Ms. Ash represented that Ms. Frei has lived on Lake Theresa for 12 years, and both the Pattersons and the Sullivans live on Lake Louise, which is within the area of concern in this proceeding. Petitioner, Diana Bauer, has lived on Lake Theresa since February 2004. She fears that the lake will become too dry if the system is allowed to flow. She also believes the wildlife will be adversely affected if the water levels are too low since many species need a swampy or wet environment to thrive. She fears her property value will decrease as a result of the approval of the ERP. She also does not trust either the City to comply with or the District to enforce the conditions of the ERP. Petitioner, Howard Ehmer, lives two to three hundred yards down Lake Theresa from Ms. Bauer. He is concerned about the lake bed being too dry and attracting people on all terrain vehicles who enjoy driving around the lake bottom. He is concerned about his property value decreasing if the lake bed is dry. Further, when the lake level is too low, people cannot enjoy water skiing, boating, and fishing on Lake Theresa. Petitioner, Phillip Lott, a Florida native, has also owned and lived on property abutting Lake Theresa since 1995. Mr. Lott has a Ph.D. in plant ecology, and M.P.A. in coastal zone studies, an M.B.A. in international business, and a B.S. in environmental resource management and planning. Mr. Lott has been well acquainted with the water levels on Lake Theresa for many years. Based upon his personal observations of the lake systems in the Deltona area over the years, Mr. Lott has seen levels fluctuate greatly based upon periods of heavy and light rainfall. Mr. Lott is concerned that the District will permit the City to open the weir to let water flow through the system and cause flooding in some areas and low water levels in other areas. He fears that the District will allow the water to flow and upset the environmental balance, but he admits that this ERP application is for a closed system that will not allow the water to flow as he fears. Mr. Lott similarly does not trust the City to comply with and the District to enforce the conditions of the ERP. Petitioners, James E. and Alicia M. Peake, who were represented by Steven L. Spratt at hearing as their qualified representative, live on Lake Louise, which is interconnected with the Lake Theresa basin. The Peakes are concerned that if the level of Lake Louise drops below 21 feet, nine inches, they will not be able to use the boat launch ramps on the lake. Petitioner, Steven L. Spratt, also lives on Lake Louise, and is concerned about the water levels becoming so low that he cannot use the boat launch on the lake. He has lived on the lake since 2000, and remembers when the water level was extremely low. He fears that approval of the ERP in this case will result in low levels of water once again. Petitioner, Gloria Benoit, has live on Lake Theresa for two years. She also enjoys watching recreational activities on the lake, and feels that approval of the ERP will devalue her lakefront property. Ms. Benoit appeared at the first day of the hearing, but offered no testimony on her behalf. J. Christy Wilson, Esquire, appeared prior to the final hearing as counsel of record for Petitioners, Steven E. Larimer, Kathleen Larimer, and Helen Rose Farrow. Neither Ms. Wilson nor any of the three Petitioners she represented appeared at any time during the hearing, filed any pleadings seeking to excuse themselves from appearing at the final hearing, or offered any evidence, testimony, pre- or post- hearing submittals. Petitioner, Gary Jensen, did not appear at hearing, did not file any pleadings or papers seeking to be excused from appearing at the final hearing, and did not offer any evidence, testimony, pre- or post-hearing submittals. Both the City and the District recognize that areas downstream from the project site, such as Stone Island and Sanford, have experienced flooding in the past in time of high amounts of rainfall. The system proposed by the City for this ERP will operate with the overflow structures closed and a brick and mortar plug in the outfall pipe to prevent water flow from Lake Doyle to Lake Bethel. So long as the overflow structures are closed, the system will mimic pre-construction flow patterns, with no increase in volume flowing downstream. The District has considered the environment in its proposed approval of the ERP. The area abutting the project is little urbanized and provides good aquatic and emergent marsh habitat. With the exception of the western shore area of the deepwater marsh ("west marsh area"), the bay swamp and remaining deepwater marsh area have good ecological value. In the 1940's, the west marsh area was incorporated into the drainage system of a poultry farm that occupied the site. This area apparently suffered increased nutrient influxes and sedimentation that contributed to a proliferation of floating mats of aquatic plants and organic debris. These tussocks reduced the deepwater marsh's open water and diminished the historical marsh habitat. Water under the tussocks is typically anoxic owing to total shading by tussocks and reduced water circulation. Thick, soft, anaerobic muck has accumulated under the matted vegetation. Exotic shrubs (primrose willow Ludwigia peruvania) and other plants (cattails Typha spp.) dominate the tussocks. The construction of the project, from the 2003 Emergency Order, resulted in adverse impacts to 1.3 acres of wetlands having moderately high- to high ecological value and 0.2 acres of other surface waters. The 0.2 acre impact to other surface waters was to the lake bottom and the shoreline of Lake Doyle where the weir structure was installed. The 0.3 acres of wetland impacts occurred at the upper end of the deepwater marsh where the pipe was installed. The largest wetland impact (1.0 acre) was to the bay swamp. The bay swamp is a shallow body dominated by low hummocks and pools connected inefficiently by shallow braided channels and one acre is filled with a 1-2 foot layer of sediment following swamp channelization. Disturbance plants (e.g., primrose willow, Ludwigia peruvania, and elderberry Sambucus Canadensis) now colonize the sediment plume. Pursuant to the District's elimination and reduction criteria, the applicant must implement practicable design modifications, which would reduce or eliminate adverse impacts to wetlands and other surface waters. A proposed modification, which is not technically capable of being done, is not economically viable, or which adversely affects public safety through endangerment of lives or property is not considered "practicable." The City reduced and/or eliminated the impacts to the lake bottom and shoreline of Lake Doyle and deepwater marsh, to the extent practicable. The impacts were the minimum necessary to install the weir structure and pipe for the system; the weir structure and pipe were carefully installed on the edges of the wetland and surface water systems, resulting in a minimum amount of grading and disturbance. To compensate for the loss of 1.3 acres of wetlands and 0.2 acres of other surface waters, the City proposes to preserve a total of 27.5 acres of wetlands, bay swamp, marsh, and contiguous uplands. Included in this 27.5 acres are 6.4 acres of the west marsh, which are to be restored. The parties stipulated that the mitigation plan would adequately compensate for losses of ecological function (e.g. wildlife habitat and biodiversity, etc.) resulting from the project. Water quality is a concern for the District. Lake Monroe is included on the Florida Department of Environmental Protection's verified list of impaired water bodies for nitrogen, phosphorous, and dissolved oxygen. Water quality data for Lake Monroe indicate the lake has experienced high levels of nitrogen and phosphorous and low levels of dissolved oxygen. Prior to construction of the project, there was no natural outfall from the Lake Theresa Basin to Lake Monroe and therefore no contribution from this basin to nitrogen and phosphorous loadings to Lake Monroe. Lake Colby, Three Island Lakes (a/k/a Lake Sixma), and the Savannah are surface waters within the Lake Theresa Basin for which minimum levels have been adopted pursuant to Florida Administrative Code Chapter 40C-8. The system will operate with the overflow structures closed and a brick and mortar plug in the outfall pipe to prevent water flow from Lake Doyle to Lake Bethel, resulting in no outfall from the Theresa Basin to Lake Monroe. Minimum flows established for surface waters within the Lake Theresa Basin will not be adversely impacted. Under the first part of the secondary impact test, the City must provide reasonable assurance that the secondary impacts from construction, alteration, and intended or reasonable expected use of the project will not adversely affect the functions of adjacent wetlands or surface waters. The system is designed as a low intensity project. As proposed, little activity and maintenance are expected in the project site area. The reasonably expected use of the system will not cause adverse impacts to the functions of the wetlands and other surface waters. None of the wetland areas adjacent to uplands are used by listed species for nesting or denning. In its pre-construction state, the project area did not cause or contribute to state water quality violations. Under the second part of the secondary impact test, the City must provide reasonable assurance that the construction, alteration, and intended or reasonably expected uses of the system will not adversely affect the ecological value of the uplands to aquatic or wetland dependent species for enabling existing nesting or denning by these species. There are no listed threatened or endangered species within the project site area. Under the third part of the secondary impact test, and as part of the public interest test, the District must consider any other relevant activities that are closely linked and causally related to any proposed dredging or filling which will cause impacts to significant historical and archaeological resources. When making this determination, the District is required, by rule, to consult with the Division of Historical Resources. The Division of Historical Resources indicated that no historical or archaeological resources are likely present on the site. No impacts to significant historical and archaeological resources are expected. Under the fourth part of the secondary impact test, the City must demonstrate that certain additional activities and future phases of a project will not result in adverse impacts to the functions of wetlands or water quality violations. The City has submitted to the District preliminary plans for a future phase in which the system would be modified for the purpose of alleviating high water levels within the Lake Theresa Basin when the level in Lake Doyle rises above an elevation of 24.5 feet. Based upon the plans and calculations submitted, the proposed future phase, without additional measures, could result in minor increases in the loadings of nitrogen and phosphorous to Lake Monroe. Lake Monroe is included on the Florida Department of Environmental Protection's verified list of impaired water bodies due to water quality data indicating the lake has experienced high levels of nitrogen and phosphorous, and low levels of dissolved oxygen. Under this potential future phase, there would be an outfall from the Lake Theresa Basin to Lake Monroe. To address the impact on water quality of this potential future phase, the City has submitted a loading reduction plan for nitrogen, phosphorous, and dissolved oxygen. The plan includes compensating treatment to fully offset the potential increased nutrient loadings to Lake Monroe. Specifically, the loading reduction plan includes: Construction and operation of compensating treatment systems to fully offset anticipated increased nutrient loadings to Lake Monroe. Weekly water quality monitoring of the discharge from Lake Doyle for total phosphorous and total nitrogen. A requirement that the overflow structure be closed if the total phosphorous level reaches 0.18 mg/l or higher or the total nitrogen level reaches 1.2 mg/l or higher in any given week and will remain closed until levels fall below those limits. The implementation of these water quality mitigation measures will result in a net improvement of the water quality in Lake Monroe for nitrogen, phosphorous, or dissolved oxygen. The future phase was conceptually evaluated by the District for impacts to wetland functions. The future phase as proposed could result in adverse impacts to wetland functions. Operation of the system with the overflow structures open could impact the bay swamp and deepwater marsh. The City has demonstrated that any adverse impacts could be offset through mitigation. Based upon the information provided by the City and general engineering principles, the system is capable of functioning as proposed. The City of Deltona will be responsible for the operation, maintenance, and repair of the surface waster management system. A local government is an acceptable operation and maintenance entity under District rules. The public interest test has seven criteria. The public interest test requires the District to evaluate only those parts of the project actually located in, on, or over surface waters or wetlands, to determine whether a factor is positive, neutral, or negative, and then to balance these factors against each other. The seven factors are as follows: the public health, safety, or welfare of others; conservation of fish and wildlife and their habitats; fishing, recreational value, and marine productivity; temporary or permanent nature; 5) navigation, water flow, erosion, and shoaling; 6) the current condition and relative value of functions; and 7) historical and archaeological resources. There are no identified environmental hazards or improvements to public health and safety. The District does not consider impacts to property values. To offset any adverse impacts to fish and wildlife and their habitats, the City has proposed mitigation. The areas of the project in, on, or over wetlands do not provide recreational opportunities. Construction and operation of the project located in, on, or over wetlands will be permanent in nature. Construction and operation of the project located in, on, or over wetlands will not cause shoaling, and does not provide navigational opportunities. The mitigation will offset the relative value of functions performed by areas affected by the proposed project. No historical or archaeological resources are likely on the site of the project. The mitigation of the project is located within the same drainage basin as the project and offsets the adverse impacts. The project is not expected to cause unacceptable cumulative impacts.

Recommendation Based upon the Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered granting the City of Deltona's application for an environmental resource permit with the conditions set forth in the Technical Staff Report, and dismissing the Petitions for Formal Administrative Hearing filed by Gary Jensen in Case No. 04-2405, and by Steven E. Larimer, Kathleen Larimer, and Helen Rose Farrow in Case No. 04-3048. DONE AND ENTERED this 27th day of May, 2005, in Tallahassee, Leon County, Florida. S ROBERT S. COHEN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of May, 2005. COPIES FURNISHED: George Trovato, Esquire City of Deltona 2345 Providence Boulevard Deltona, Florida 32725 Diana E. Bauer 1324 Tartan Avenue Deltona, Florida 32738 Barbara Ash, Qualified Representative 943 South Dean Circle Deltona, Florida 32738-6801 Phillip Lott 948 North Watt Circle Deltona, Florida Howard Ehmer Nina Ehmer 32738-7919 1081 Anza Court Deltona, Florida 32738 Francell Frei 1080 Peak Circle Deltona, Florida 32738 Bernard T. Patterson Virginia T. Patterson 2518 Sheffield Drive Deltona, Florida 32738 Kealey A. West, Esquire St. Johns River Water Management District 4049 Reid Street Palatka, Florida 32177 J. Christy Wilson, Esquire Wilson, Garber & Small, P.A. 437 North Magnolia Avenue Orlando, Florida 32801 Gloria Benoit 1300 Tartan Avenue Deltona, Florida 32738 Gary Jensen 1298 Tartan Avenue Deltona, Florida 32738 James E. Peake Alicia M. Peake 2442 Weatherford Drive Deltona, Florida 32738 Steven L. Spratt 2492 Weatherford Drive Deltona, Florida 32738 Ted Sullivan 1489 Timbercrest Drive Deltona, Florida 32738 Kirby Green, Executive Director St. Johns River Water Management District 4049 Reid Street Palatka, Florida 32177

Florida Laws (3) 120.569120.57373.086 Florida Administrative Code (6) 40C-4.30140C-4.30240C-4.33140C-4.75162-302.30062-4.242
# 2
JAMES SARTORI, D/B/A WILLOWBROOK FARMS vs. ST. JOHNS RIVER WATER MANAGEMENT DISTRICT, 81-002393RX (1981)
Division of Administrative Hearings, Florida Number: 81-002393RX Latest Update: Nov. 24, 1981

Findings Of Fact On December 31, 1976, Respondent's territorial jurisdiction was expanded by transfer of substantial areas formerly regulated by other water management districts. The transfer was effected pursuant to legislative revision of Section 373.069, F.S., which delineates the geographic boundaries of Florida's water management districts. The following rule promulgated by Respondent became effective on January 31, 1977, and was amended on February 3, 1981: 40C-4.031 (previously 16I-4.04, Florida Administrative Code). Implementation. These regulations shall become effective February 1, 1981, throughout the District and will be implemented in those areas transferred to the St. Johns River Water Management District from the Central & Southern Florida Flood Control District and the Southwest Florida Water Management District on the same date. Implementation in other areas will be effected pursuant to public hearing at subsequent dates determined by the Board. The regulations implemented by the above rule establish permitting procedures for projects which involve holding, diversion, or discharge of significant quantities of water. However, permits are required only in the transferred territory. Petitioner owns 11,500 acres located within the territory where permits are required. Petitioner seeks to improve his property for agricultural purposes, which involves the holding and diversion of surface waters. He has accepted Respondent's determination that his property is within the permitting area and has filed the requisite application. However, Petitioner contends that he is unable reasonably to confirm Respondent's determination that his property is situated in the regulated territory. Respondent demonstrated that a determination can be made by comparing the statutory descriptions of Respondent's jurisdiction prior to and after the transfer, and has maps available which reflect the permitting area. To accomplish this task independently requires knowledge of legal territorial descriptions (section, township, range) and a laborious comparison of legal descriptions set out in the 1975 and 1977 versions of the Florida Statutes. At the time reorganization of the water management districts became effective (December 31, 1976) , Respondent had limited regulatory capability. Its decision to implement permitting only in the transferred territory was based on this limited capability and the need to preserve continuity 1/ in areas where permits had previously been required. In the years following this decision, Respondent has continued to require permits only in those areas transferred in 1976. The evidence established that the boundary between the regulated and unregulated areas is one of convenience and has no hydrological or other scientific basis. Respondent is considering a revision of its rules to become effective sometime in 1982. This revision may enlarge the permitting territory and modify the criteria for grant or denial of permits. Petitioner asserts that his application is being evaluated by rules not yet adopted and fears that new standards may be applied after hearing on the application, which is now under consideration pursuant to Subsection 120.57(1), F.S., (DOAH Case No. 81-1588). Hearing is scheduled for December, 1981. In support of this contention, Petitioner points to the technical staff report prepared in May, 1981, which recommends denial of the application giving, among others, the following reasons: Volumes 1 and 2 of Phase 1 of the Upper Basin Plan catalogue a history of a diminish- ing water resource in the upper basin. The water resources in the upper basin have been harmed and the proposed project aggravates the existing harm to the resource. Moreover the proposed project is inconsistent with the overall objectives of the district for the upper basin. Resolutions 75-11 and 81-2, the 1977 Management Plan, and Volumes 1 and 2 of Phase I of the Upper Basin Plan indicate that the objectives of the District are to curtail inter-basin diversion and maintain and enhance, if possible, the existing hydro- logic regime in the upper basin. The pro- posed project is not in conformance with either of these statutory requirements. (Emphasis added.) An earlier technical staff report prepared in November, 1980, recommended grant of the application, with some modification. This report did not refer to inter-basin diversion.

Florida Laws (7) 120.52120.54120.56120.57373.069373.113373.413 Florida Administrative Code (2) 40C-4.03140C-4.301
# 6
SYSLOGIC TECHNOLOGY SERVICES, INC. vs SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 01-004385BID (2001)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Nov. 09, 2001 Number: 01-004385BID Latest Update: May 24, 2002

The Issue The issues in this bid protest are whether, in making a preliminary decision to award a staff augmentation contract, Respondent acted contrary to a governing statute, rule, policy, or project specification; and, if so, whether such misstep(s) was/were clearly erroneous, arbitrary or capricious, or contrary to competition.

Findings Of Fact The parties' Joint Pre-Hearing Stipulation2 and the evidence presented at final hearing established the facts that follow. The Request for Proposals On July 26, 2001, the District issued Request for Proposals C-11940 (the "RFP"). The purpose of the RFP, as set forth on page one thereof, was to solicit technical and cost proposals from qualified respondents [for a staff augmentation contract.3] The South Florida Water Management District (District) is interested in establishing a single qualified information systems/technology contracting firm to provide the services defined herein on an as-needed basis. Contingent upon the responses received as a result of this Request for Proposals (RFP), the District will determine which respondent meets the required standards and qualifications through an evaluation process. The Vendor meeting the required standards and qualifications will be determined to be “pre-qualified” to provide information systems/technology services to the District. The deadline for submission of proposals in response to the RFP was Monday, August 27, 2001 at 2:30 p.m. Section 1.12 of the RFP, which is relevant to this protest, stated as follows: REJECTION OF RESPONSES The District reserves the right to reject any and all responses when such rejection is in the District's interests. Minor irregularities contained in a response may be waived by the District. A minor irregularity is a variation from the solicitation that does not affect the price of the contract or does not give a respondent an advantage or benefit not enjoyed by other respondents, or does not adversely impact the interests of the District. The District further reserves the right to cancel this solicitation at any time if it is in the best interest of the District to do so. Section 1.13 of the RFP stated, in pertinent part:

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the District enter a Final Order that declares DUA’s proposal to be materially non-responsive and, accordingly, rescinds the proposed award to DUA. In addition, while recognizing that the choice of remedies for invalid procurement actions is within the agency’s discretion, it is nevertheless recommended that, rather than reevaluate or reject all responsive proposals, the District award the contract to the highest-ranked responsive proposer, Syslogic. DONE AND ENTERED this 18th day of January, 2002, in Tallahassee, Leon County, Florida. JOHN G. VAN LANINGHAM Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 18th day of January, 2002.

Florida Laws (5) 120.569120.57287.001287.012287.057
# 7
FLORIDA AUDUBON SOCIETY AND NATIONAL AUDUBON SOCIETY vs. SOUTH FLORIDA WATER MANAGEMENT DISTRICT (MARSH GOLF CLUB), 87-005578 (1987)
Division of Administrative Hearings, Florida Number: 87-005578 Latest Update: Aug. 29, 1988

The Issue As stated by the Hearing Officer the issue in this case is whether the District should issue a surface water management permit to Russell E. and Marilyn F. Scott, and Caloosa Television Corporation for the construction and operation of a surface water management system to serve a television signal tower and control building in Southeast Lee County, Florida. There are no significant water resource impacts related to the management of surface water by the proposed project. The harm at issue in this case is the potential for wood storks and other wading to strike the tower and guy wires which are not structures related to management and storage of waters. The parties disagree as to whether the District has jurisdiction to consider the bird impacts related to collisions with the tower and guy wires, and if so, whether the tower and guy wires will have a significant adverse impact on the water resources of the state through a reduction of wood storks, an endangered species, and other wading birds which through feeding on fish remove biomass from such water, thereby maintaining water quality. In determining jurisdiction in this case, the parties disagree on the meaning of "works" and "surface water management system" as used in Chapter 373, F.S. and Rule 40E-4, F.A.C. The petitioners argue that since one set of guy wires will be placed across one end of the cypress wetland located on the subject property, the entire project including the guy wire and tower is a "works" and part of the surface water management system, which is subject to the permitting jurisdiction of the District. The District and respondent Caloosa Television Corporation contend that the tower and guy wires are not structures related to surface water management and are not "works" nor part of the surface water management system, and therefore, bird mortality, as a result of hitting the tower and guy wires, is not subject to the permitting jurisdiction of the District. FINDINGS ON EXCEPTIONS At the Governing Board meeting of October 6, 1988, the petitioners waived Findings of Fact exceptions 1 and 2 of Petitioners' Exceptions to Finding of Fact, Conclusions of Law, and Recommended Order. Therefore, Findings of Fact exceptions 1 and 2 are rejected. The petitioners' exceptions 1, 2, and 3 to Conclusions of Law of the Recommended Order are rejected as set forth in the District's Response To Exceptions Filed by Petitioners filed on September 27, 1988, and attached hereto as Exhibit B and made part of this Final Order. The Governing Board accepts the exceptions filed by the District and the respondent, Caloosa Television Corporation, as set forth herein under Conclusions of Law.

Findings Of Fact On or about September 14, 1987, Caloosa filed Application Number 09147- B, for a surface water management permit, with the District. This application was for the construction and operation of a surface water management system to serve a 1249 foot high television transmission tower and control building in southeast Lee County, Florida. The proposed location of Caloosa's project is approximately one mile north of the boundary of the Corkscrew Swamp Sanctuary, which is owned and operated by Audubon, and specifically, approximately two and one-half miles north of a wood stork colony located within the Sanctuary. This rookery is the largest rookery of wood stork, a federally endangered wading bird, in the United States. The project site is 60 acres in size, and approximately square in shape. It is improved agricultural land, with a circular cypress wetland of about 5.5 acres located near the center of the site. Extending outward from the cypress wetland are two ditches, one running due east and the other due west. The existing surface water flow varies with the seasons and intensity of storm events. During dry seasons, the rainfall runoff flows into the cypress wetland and percolates into the ground. However, during wet seasons, water builds up in the cypress wetland and flows into the two ditches. In larger storm events, the project site is entirely under water, and sheet flows occur to the southwest. The proposed project should have a negligible impact on the existing surface water system since the total impervious area will only be approximately one acre, or 1.7 percent of the total project area of 60 acres. The project consists of a radio tower and guy wires, a 3150 square foot control building, fill pad and parking area, guy wire anchor slabs, and approximately 1650 feet of lime rock road with an equalizer culvert to maintain existing flow. Three sets of six guy wires will extend from the 1249 foot high tower and connect to the ground at anchor slabs located near the edge of the project site. The entire project is located outside of the limits of the existing wetland, but one set of guy wires does cross the western edge of the cypress wetland. Caloosa proposes to use the tower as a "community tower" which will be capable of supporting more than one transmitting antennae. In addition to Caloosa's antennae, the tower will be able to support up to five commercial radio stations and up to sixty two-way communication antennae. Caloosa has had contacts from several commercial radio stations and governmental agencies which have expressed interest in co-locating their antennae on Caloosa's tower. After review of this application, District staff advised Caloosa, on November 23, 1987, that it was recommending approval of the application since it was felt that any impact from the project on wood storks would not result from the construction and operation of this project. At hearing, the District supported the issuance of this permit, but urged that the tower and guy wires are not a part of the surface water management system over which the District has any permitting jurisdiction. Audubon timely filed its request for a hearing on the District's intent to issue this permit, and at hearing opposed the issuance of this permit to Caloosa, urging that the tower and guy wires were an integral part of the surface water management system, and therefore subject to the District's permitting jurisdiction. The wood stork and other wading birds are an important link in the biological and ecological chain. They are the main mechanism for removing certain species of fish from ponds, lakes and waters of the state. If there is no predation by wading birds, then an increase in the biomass of the water system would be expected, water quality would decrease, and fish kills would result. Ponds that receive biomass reduction by wading birds have a reduction in fish biomass of approximately 75%, with no loss in species, while ponds that do not receive wading bird predation lose almost all individual aquatic animals through reduced water quality resulting from retention of up to 94% of the biomass from dead fish. The reduction in biomass is in direct proportion to the number of birds feeding in a pond, and therefore a 5% reduction in birds will result in a 5% lessening of the biomass reduction. Water quality will be reduced by a lowering of oxygen levels in such waters due to the excessive retention of nutrient laden biomass. During the nesting season, wood storks feed in various ponds and wetland areas that surround the rookery. Their primary feeding areas are within ten miles of the rookery. The proximity of these sites allow the birds to make several flights per day between the colony and the feeding site, and to do so with less energy expended than with feeding sites that are farther away. Caloosa's project site is located between the rookery and a primary feeding area to the north that is within ten miles of the rookery. The proximity of this feeding area allows the birds to fly low, at tree top level, to the site, without the use of thermal updrafts that they use to attain altitudes of up to 5000 feet when traveling greater distances. Thus, if the tower is built, it would be likely that wood storks would fly in the direction of, and at the height of, the tower to reach this primary feeding area. However, it was not established how many such birds actually feed in this nearby area, or how many fish are in these ponds and wetlands. The wood stork colony at Corkscrew Swamp Sanctuary has been experiencing a decline in productivity from approximately 6000 nesting pairs in 1960 and 1966, there has been a steady decline in the number of nesting pairs in the colony, and in 1987, there were no nesting pairs in the colony. During 1988, 750 nesting pairs have been observed. The steady decline in the wood stork colony population is the result of already existing developmental pressures and changes in drainage patterns which have adversely affected the birds' feeding habitats. For nesting to be successful, two adult birds are required per nest during the nesting season, which usually occurs from November to March. This allows one adult bird to be away from the nest obtaining food while the other adult keeps the nest warm and safe from predators. If a nest is left unattended through the loss of one adult bird, it is likely that the entire nest will be lost since the fledglings are very vulnerable throughout the nesting season to predators and changes in temperature. There are usually two or three fledglings per nest. For this reason, the loss of five adult birds per year, for example, results in a total loss to the colony of between ten to fifteen fledglings. This loss compounds each year, as birds lost one year are not available to reproduce in following years. Generally, transmission towers can pose a hazard to birds due to the potential for collisions. Illuminating such towers at night does not decrease this danger since the birds are simply attracted to lights. Strobe lighting has also been tried, but it appears that birds ignore, or are not deterred, by strobes. In this case, Caloosa has agreed to accept conditions placed upon the approval of this project by the Lee County Board of Zoning and Adjustments on March 16, 1987, which include placement of aircraft warning balls on the guy wires and the tower itself, habitat improvement including the creation of a wetland and a wildlife through way, if necessary, and commencement of a monitoring system to identify any problems with wood stork mortality as soon as possible. A very extensive study of bird kills and transmission towers was conducted over a thirty year period involving the WCTV tower in Tallahassee, Florida. The WCTV tower was found to kill 3.9 wading birds per year on average. Based in part upon this data, the U.S. Fish and Wildlife Service concluded that wood stork collisions with the tower will not result in significant mortality, and an "incidental take" of five wood storks per year should result. This is a level of mortality which is noteworthy, since any loss to an endangered species is significant, but is clearly below that which would cause jeopardy to the species. Although Audubon correctly pointed out that the conditions present in the WCTV study do not exactly match those present in this case, such as the fact that there are almost three times as many wading birds in the area of the Caloosa tower as were in the area of the WCTV tower, as well as the differences in the geographical relationship of the tower to nearby wading bird colonies and feeding areas, nevertheless, the WCTV study is relevant and should be considered by the District since it is the most exhaustive study of its kind ever conducted. Caloosa presented evidence of a study it conducted over approximately a one month period in May and June, 1988, of a comparable existing radio tower, the WHEW tower, located near the subject property to the east. Although substantial wood stork and other wading bird activity was observed around the WHEW tower, there were no collisions of wood storks with this 1010 foot high tower. While not a scientific study in the strictest sense, and although it was not conducted for as extensive a period as the WCTV study, nevertheless, the District should consider the WHEW study conducted by Caloosa since it involves a comparable tower in close proximity to the subject property, and the person who conducted the study for Caloosa and who testified at hearing, Robert E. Gatton, appeared particularly credible. The Federal Communications Commission has approved the location of Caloosa's tower. I5. The Florida Game and Fresh Water Fish Commission has recommended that the proposed location for Caloosa's tower be changed to an alternate site which would present a less serious obstacle to the Corkscrew wood stork nesting colony and other wading birds. This recommendation is based on the policy that the mortality of even one wood stork is too much and may present a danger to the population of the wood stork rookery. It was not shown, however, that a basis in fact exists for concluding that the loss of five or fewer wood storks per year would present such a danger. The Commission's recommendation is also based upon a concern that transmission towers will proliferate in the area, and thereby further interfere with the flight paths of wood storks and other wading birds to their feeding locations. However, the fact that Caloosa is seeking to construct a "community tower" to be shared with several governmental agencies, as well as broadcasting stations, will actually serve to decrease this potential proliferation. While there is a potential for wood storks or other wading birds in the area to be killed or injured by striking Caloosa's tower or the guy wires while in flight, the extent of this danger is speculative, but would not appear to exceed five wood storks per year. Under these circumstances, there would not be a significant threat to the population, or continued viability, of the Corkscrew rookery. It has not been shown, by the evidence in this record, that any loss of wood storks and other wading birds caused by this project will result in fish kills through a significant reduction of predation and the resulting failure to remove accumulated biomass in ponds and waters in the area. It was not demonstrated that a fish kill will, or is even likely, to occur. While the loss of five wood storks would result in a certain amount of biomass not being removed from the area's wetlands, nothing in the record suggests that this amount will have an adverse impact on the state's water resources or will otherwise be significant. Therefore, any relationship between the tower proposed by Caloosa and impacts associated with biomass accumulation is purely speculative and de minimis. Fish kills occur naturally as water levels in seasonal marshes and ponds lower in the dry season. The water quality impact of such kills is relatively short-lived, lasting up to two months or until the next wet season begins, at which time water quality parameters return to normal. The evidence produced at hearing does not establish that the project and its surface water management system will have any significant or measurable effect on drainage of surface water runoff from the subject property, or on adjacent properties. The drainage system proposed by Caloosa will utilize the existing ditches and the natural cypress pond on the property. It was established that the post-construction effect of the project on drainage would be insignificant. There are, therefore, no drainage impacts associated with this project.

Recommendation Based upon the foregoing, it is recommended that the District enter a Final Order approving Caloosa's application for surface water management permit number 09147-B, subject to the conditions, agreed to by Caloosa, which were imposed by the Lee County Board of Zoning and Adjustment in its approval of this proposed development. DONE AND ENTERED this 29th day of August, 1988, in Tallahassee, Leon County, Florida. DONALD D. CONN Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of August, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 88-5578 Rulings on Audubon's Proposed Findings of Fact: 1. Adopted in Findings of Fact 1, 3. 2-3. Adopted in Finding of Fact 4, but otherwise Rejected as a conclusion of law rather than a finding of fact. 4-5. Adopted in Finding of Fact 5, but otherwise Rejected as unnecessary, irrelevant and as a summation of testimony. 6. Adopted in Finding of Fact 2. 7-8. Adopted in Finding of Fact 7. 9-10 Adopted in Finding of Fact 8. 11. Adopted in Finding of Fact 11. 12-15. Adopted and Rejected, in part, in Finding of Fact 12. Adopted in Findings of Fact 8, 10, but otherwise Rejected as irrelevant and unnecessary. Adopted in Finding of Fact 9. Adopted in Findings of Fact 10, 12, but otherwise Rejected as cumulative and as argument on the evidence. Rejected in Finding of Fact 13, and otherwise as simply a summation of the testimony and argument on the evidence. 20-21. Adopted in Finding of Fact 6. 22-23. Rejected in Findings of Fact 15-17. 24. Adopted in Finding of Fact 15. Rulings on Caloosa's Proposed Findings of Fact: Adopted in Findings of Fact 1, 2. Adopted in Finding of Fact 4. Adopted in Finding of Fact 13. Adopted in Finding of Fact 1. Adopted In Finding of Fact 5. Adopted in Finding of Fact 19. Adopted in Finding of Fact 5, but otherwise Rejected as a conclusion of law and as simply a summation of testimony. Adopted in Finding of Fact 16. 9-10. Adopted in Finding of Fact 12. Adopted in Findings of Fact 12, 13. Adopted in Finding of Fact 11. Adopted in Findings of Fact 4, 15. Adopted in Finding of Fact 6. 15-16. Adopted in Finding of Fact 17. 17. Adopted in Finding of Fact 18, but otherwise Rejected as irrelevant and as cumulative. Rulings on the District's Proposed Findings of Fact: 1-2. Adopted in Finding-of Fact I. 3. Adopted in Finding of Fact 2. 4-5. Adopted in Finding of Fact 3. Adopted in Finding of Fact 4. Adopted in Finding of Fact 3. Adopted in Finding of Fact 8. Adopted in Findings of Fact 12, 14, 16. Adopted in Finding of Fact 12. 11. Adopted in Finding of Fact 13. 12. Adopted in Finding of Fact 16. 13. Adopted in Finding of Fact 15. 14. Adopted in Finding of Fact 11. 15. Rejected as irrelevant. 16. Adopted in Finding of Fact 11. 17. Adopted in Finding of Fact 6. 18-19. Adopted in Finding of Fact 5. COPIES FURNISHED: Charles Lee Senior Vice President Florida Audubon Society 1101 Audubon Way Maitland, Florida 32751 Russell P. Schropp, Esquire Post Office Box 280 Fort Myers, Florida 33902 James K. Sturgis, Esquire Post Office Box 24680 West Palm Beach, Florida 33416 John R. Wodraska Executive Director South Florida Water Management District Post Office Box 24680 West Palm Beach, Florida 33416 =================================================================

Florida Laws (4) 120.57373.016373.403373.413 Florida Administrative Code (2) 40E-4.02140E-4.301
# 8
WILLIAM B. SWAIM vs FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION, 15-000091RU (2015)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Jan. 08, 2015 Number: 15-000091RU Latest Update: Jan. 27, 2015
Florida Laws (3) 120.52120.54120.68
# 9
CAROL A. RANALLO vs. SOUTHWEST FLORIDA REGIONAL PLANNING COUNCIL, 75-001072 (1975)
Division of Administrative Hearings, Florida Number: 75-001072 Latest Update: Oct. 29, 1990

The Issue Whether a consumptive-use permit for quantities of water as applied for should be granted.

Findings Of Fact Application No. 7500043 requested water from one (1) well. The center of withdrawal will be located at Latitude 27 degrees 40' 38" North, Longitude 82 degrees 29' 31" West in Hillsborough County. Said withdrawal is for disposal off-site. This application is for an existing use. Notice was published in a newspaper of general circulation, to-wit: The Tampa Tribune on May 14 and May 21, 1975 pursuant to Section 373.146, Florida Statutes. Notices of said public hearing were duly sent by certified mail as required by law. The application, map of the premises, legal description, receipts of certified mail, copy of the Notice, and affidavit of publication were received without objection and entered into evidence as Exhibit 1. No letters of objection were received. The witness for Permittee was duly sworn and agreement was reached on each point enumerated as required by Rule 16J-2.11, Rules of the Southwest Florida Water Management District and Chapter 373, Florida Statutes with the exception as enumerated in No. 7. Upon request of the Hearing Officer a Joint Stipulation was filed in which it was agreed that the following conditions to the permit should be attached: "1. That applicant, Carol A. Ranallo, construct two observation wells on the south side of the pit mutually agreeable locations by inserting six (6) inch casings and screens to the depth of at least fifty (50) feet. The casings to be grouted in the bore hole from the bottom of the casing to the top of the ground level. The sites of the observation wells shall be selected by James Hudson of Delta Engineering Company and G. P. Szell within 15 days after issuance of the Consumptive Use Permit. 2. That the applicant or its agents or employees submit monthly readings to the staff of the Southwest Florida Water Management District of the chloride content of the water being withdrawn from the two wells and the level of the water table as read and determined under static conditions."