Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
BAXTER`S ASPHALT AND CONCRETE, INC. vs. DEPARTMENT OF TRANSPORTATION, 84-003151 (1984)
Division of Administrative Hearings, Florida Number: 84-003151 Latest Update: Mar. 02, 1987

The Issue The issues to be considered in the course of this Recommended Order concern the question of whether Baxter's Asphalt & Concrete, Inc. or White Construction Company, Inc. should be accepted as a successful bidder on State Project No. 53050-3514, Jackson County, Florida, as advertised by the State of Florida, Department of Transportation.

Findings Of Fact The State of Florida, Department of Transportation, (DOT), advertised for bids on State Project No. 53050-3514, Jackson County, Florida. This was a project in which DOT had determined that 10 percent of the funding within the State Department of Transportation Trust Fund, as allotted for the project, would be devoted to economically disadvantaged individuals, also referred to as Disadvantaged Business Enterprises (DBE). This decision was in keeping with Section 339.081, Florida Statutes. Consequently, interested bidders were called upon to submit bids reflecting a DBE participation of a minimum of 10 percent of the bid submitted. Baxter's Asphalt & Concrete, Inc. (Baxter) and White Construction Company, Inc. (White) responded to the bid opportunity. The bids were opened on July 25, 1984, and Baxter's bid was the apparent low bid. The bid amount was $882,641.25. White was the second low bidder offering a bid of $928,353. Both bids were within the DOT estimate of construction costs. When the bids were reviewed, Baxter's bid was rejected by DOT based upon the belief that the bid failed to meet the DBE 10 percent requirement or to offer explanation of good faith attempts by Baxter to comply with the DBE contract requirement amount. See Section 14-78.03(2)(b)4., Florida Administrative Code. No other claim of error was made by DOT on the subject of the acceptability of the Baxter bid. The White bid is conforming. In preparing the bid, bidders are required to use DBE Utilization Form No. 1 to reflect the amount of DBE participation as a percentage of the overall bid estimate. In submitting its form as part of its bid blank, Baxter indicated that the total project cost was $884,000, and indicated that Ozark Striping, a DBE subcontractor, would be given $20,000 of that work or 3 percent, and that Glenn Powell, DBE subcontractor, would be afforded 7 percent of the total contract in the amount of $55,000. The total percentage according to Baxter is 10 percent, thus meeting the required DBE participation. This form is found as part of the joint Exhibit No. 1 offered by the parties. In fact, the Ozark Striping participation was 2.26 percent, and the Glenn Powell participation was 6.22 percent, for a total of 8.48 percent of the estimate reflected in the Form No. 1. Contrasted against the actual estimate of $882,641.25, these projections constitute 8.49 percent of that estimate. Thus, they are less than the 10 percent required. Given the fact that this DBE projection is less than the 10 percent, and in the absence of any attempt to offer a good faith explanation why Baxter failed to comply with the requirement, the bid was rejected for this irregularity. The Contract Awards Committee of DOT, when confronted with the irregularity of the Baxter bid, then determined to recommend the rejection of all bids. This was in keeping with the fact that the difference between the unsuccessful apparent low bid, with irregularities, and the second low bid exceeded 1 percent of the contract amount. At the time of this decision to reject all bids, DOT felt that the difference would justify re-advertising the bids. That policy position had been abandoned at the point of final hearing in this cause, wherein DOT expressed the opinion that it would be better served to accept the bid of White, and not re-advertise, again for cost reasons. In the face of the initial action to reject all bids and in accordance with Section 120.53, Florida Statutes, Baxter and White appealed that decision and by that appeal requested recognition as a successful bidder. This led to the present Section 120.57(1), Florida Statutes hearing. Baxter has never attempted to offer a good faith explanation of its non-compliance. It chooses to proceed on the theory that the mistake in computation can be rectified by allowing Baxter to submit a supplemental Form No. 1, bringing its total above the DBE requirement. In its contention, Baxter indicates that Glenn Powell could have provided $126,000 of the DBE goal, which is in excess of the 10 percent requirement. Baxter also alludes to the fact that it had contacted other DBE enterprises, such as Oglesby and Hogg, Michael Grassing, and J.E. Hill. All told, Baxter indicates that if given the opportunity, it would allow $146,000 of DBE participation to include $126,000 by Glenn Powell, and $20,000 by Ozark. This comment is suspect, given the lack of compliance in the initial bid response, and the realization that within that bid response on the item related to Glenn Powell, the original amount of work attributed to Glenn Powell was $100,000, and was struck through in favor of the $55,000, leaving a fair inference that Baxter was attempting to meet the DBE goal with a projection as close to the 10 percent as could be achieved. They fell short because in adding the $20,000 for Ozark, and the $55,000 for Glenn Powell, the addition in the Form No. 1 showed $85,000, which is more than 10 percent of the $884,000 shown on the form, when in fact the two amounts were $75,000, and less than the 10 percent required. Baxter characterizes its mistake in computation as a technical error, which can be remedied without harm to the bid process. The Baxter position must be examined in the context of action by DOT relating to compliance with DBE requirements. Prior to June 1984, a time before the subject July 25, 1984 bid opening, bidders had been allowed to amend the Form No. 1 to show compliance with the DBE requirements or demonstrate good faith efforts of compliance. That amendment as to compliance through listing of the DBE subcontractors or submission of good faith effort documentation had to be offered within 10 days per former Section 14-78.03, Florida Administrative Code. Beginning with the June 1984 bid-lettings, all documentation had to be submitted with the bid, reflecting compliance or describing good faith efforts at compliance per Section 14-78.03(2)(b), Florida Administrative Code, effective May 1984. This change was brought about to prevent the apparent low bidder, as indicated at the point of bid-letting, from shopping the quotations by the DBE's found in its original quote against other quotes from DBE's not listed in the bid documents initially submitted, and by amendment to the DBE statement prejudicing the former DBE group. The change was also made to avoid the possibility that the apparent low bidder could evade his bid by rendering it non-conforming, in the sense of refusing to submit the required documentation of compliance with DBE requirements or to the offer of a good faith explanation of non-compliance after the bid-letting. The change of May 1984, removed the possibility of bid shopping and bid avoidance. Both versions of Section 14-78.03, Florida Administrative Code, pre and post May 1984, indicate that failure to satisfy the DBE requirements or offer a showing of a good faith attempt at compliance, would result in the contractor's bid being deemed non-responsive, and cause its rejection. Baxter has been able to comply with the DBE goals of DOT in its bidding prior to the present controversy.

Florida Laws (5) 120.53120.57337.11339.081641.25
# 1
KELLOGG AND KIMSEY, INC. vs LEE COUNTY SCHOOL BOARD, 91-007597BID (1991)
Division of Administrative Hearings, Florida Filed:Fort Myers, Florida Nov. 26, 1991 Number: 91-007597BID Latest Update: Mar. 02, 1992

Findings Of Fact Upon consideration of the oral and documentary evidence addressed at the hearing, the following relevant findings of fact are made: The request for sealed bids for the construction of the Project was advertised on October 9, 16 and 23, 1991. There were six addenda to the original bid documents which added, deleted or modified provisions of the original bidding requirements, contract requirements, administrative requirements and technical specifications. The original bid documents plus the six addenda will be referred to herein as the "bid documents". The bid documents required that all bids be in full accord with the contract documents. Sealed bids for the Project were opened on October 30, 1991. Wright submitted the lowest lump sum bid for the Project, with Sovran submitting the second lowest lump sum bid and Kellogg submitting the third lowest lump sum bid. At the time of the bid opening, the bid documents listed only four casework manufacturers that were approved to furnish casework for the Project. Empire Custom Cabinets, Inc. (Empire) was not listed as one of the four approved casework manufacturers in the bid documents. The bid documents did not require the bidder to list the casework manufacturer it intended to obtain the casework from, but only that the bidder name the casework subcontractor. The only work item in the bid documents which requires identifying the name of the manufacturer on the subcontractor's list is the metal roof system. Because Empire's bid on the casework was extremely low compared to other bids received by Wright on the casework, Wright called Empire prior to submitting its bid to confirm that Empire's bid was submitted per plans and specifications. Although Wright did not specifically inquire of Empire at this time as to which manufacturer Empire was obtaining the casework from for the Project, Empire did advise Wright that Empire's bid on the casework was according to plans and specifications. Additionally, Empire did not divulge or advise Wright at this time that the bid was based on Empire manufacturing the casework for the Project. Based on this representation from Empire, Wright listed Empire as its casework subcontractor, and calculated its lump sum bid for the Project using Empire's bid. Although Wright listed Empire as its casework subcontractor in its bid, this did not create an irregularity in Wright's bid since Wright's bid was per plans and specification without exception or exclusion. This would require Wright to furnish casework for the Project manufactured by one of the four approved casework manufacturers listed in the bid documents regardless of which subcontractor Wright listed as the subcontractor for casework. By letter dated November 1, 1991, the Board's architect for the Project requested Wright to have Empire submit written certification by one of the four approved casework manufacturers that its casework was being furnished to Empire for the project. By letter dated November 4, 1991, Empire advised Wright that Empire's bid on the casework for the Project was based on casework to be manufactured by Empire. On the same day, Wright furnished the architect for the Project a copy of Empire's letter of November 4, 1991. In response to a request by the Board, Wright, by letter dated November 7, 1991, advised the Board that Wright would furnish casework manufactured by one of the four approved manufacturers listed in the bid documents for the Project. By letter dated December 3, 1991, Empire advised Wright that Empire would need to withdraw its bid if Empire was required to use casework manufactured by one of the four approved casework manufacturers listed in the bid documents. On that same day, Wright furnished the Board a copy of Empire's letter and requested that the Board allow Wright to remove and replace Empire with Steven Ward and Associates, Inc. (Ward), as the casework subcontractor since Ward would be able to furnish and install casework manufactured by LSI Corporation of America, Inc., one of the four approved casework manufacturers. No Action has been taken on that request. The bid documents provide for a subcontractor to be removed and replaced from the list of subcontractors after the bid is opened if there is a showing of good cause and written approval by the Board and the Project architect is obtained. Although Empire's bid on the casework for the Project submitted to Wright was based on Empire manufacturing the casework, there is competent substantial evidence in the record to establish facts to show that at the time Wright submitted its bid on the Project it had reasonable grounds to believe that Empire's bid on the casework was based on Empire furnishing and installing casework manufactured by one of the four approved casework manufacturers. After determining that Empire could not perform under its bid, Wright obtained a bid from Ward for furnishing and installing the casework for the Project which was less than Ward's original bid submitted to Wright before the bid opening. However, this bid was substantially more than Empire's bid, and if Wright is allowed to substitute Ward for Empire, Wright will have to absorb the additional costs since the bids were lump sum bids. Wright is neither attempting to furnish casework from a manufacturer that is not approved, nor is Wright requesting an increase in the lump sum bid price. The advertisement for Sealed Bids for the Project required that all bidders be prequalified by the Board prior to the bid date. Sovran and one other bidder were not prequalified by the Board prior to the bid date in accordance with Advertisement for Sealed Bids for the Project. Sovran received the bid documents for the Project approximately one month before the bid date but did not file a Notice of Protest of the prequalification requirement contained in the Advertisement for Sealed Bids for the Project. Sovran holds a certificate as a general contractor licensed in the State of Florida in accordance with Chapter 489, Florida Statutes. As a certified general contractor Sovran, pursuant to Section 489.125, Florida Statutes, was authorized to bid on the Project notwithstanding the Board's prequalification requirement. This was explained by the Board's representative at the bid opening. The bid documents required that a subcontractor list be submitted by all bidders, and when submitted with the bid becomes an integral part of the bid. The purpose of the subcontractor list was to prevent bid shopping, and to allow the Board an opportunity to review the subcontractors to determine if any subcontractor on the list had performed unsatisfactorily on previous Board projects. Neither the statutes relating to competitive bidding nor the bid documents prohibit the listing of the general contractor together with a subcontractor on a subcontractor list. The subcontractor list submitted by Sovran indicated "Sovran Constr/Naples" as the name of the subcontractor for the masonry work and "Sovran/Naples" as the name of the subcontractor for the poured-in-place concrete work. "Naples" is Naples Concrete and Masonry Work, Inc. The bid received by Sovran from Naples was for both labor and materials for the poured-in-place concrete and masonry work. Sovran neither requested nor did Naples furnish Sovran a bid to provide labor only for the poured-in-place concrete and masonry work. There was no agreement between Sovran and Naples whereby Sovran would supply the materials and Naples would furnish the labor for the poured-in-place concrete and masonry work. Sovran did request and receive bids from other companies for furnishing materials only for the poured-in-place concrete and masonry work. Sovran listed itself, the general contractor, along with Naples on the subcontractor list for the purpose of supplying the materials for the poured-in- place concrete and masonry work. Sovran's main reason for supplying the materials was that Naples was not bondable. Without a payment bond from Naples, Sovran would be without protection and could be forced into paying double for the materials in the event Naples failed to pay the material suppliers. Although the Superintendent of the Lee County Schools has recommended to the Board that the Board accept Wright's bid for the Project, the Board has not voted on that recommendation. The fact that Wright used Empire's bid to calculate its lump sum bid in no way excuses Wright for the requirement set out in the bid documents that casework used for the Project (when the time comes) be manufactured by one of the four approved casework manufacturers. Wright gains no economic advantage in this regard since the lump sum bid price remains the same. The advertisement for Sealed Bids on the Project provides that the Board reserves the right to waive any and all irregularities of any bid received.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, accordingly RECOMMENDED: That the Board enter a Final Order dismissing the instant bid protest and awarding to Wright the contract for the construction of Elementary School "C", Job No. 91063. DONE and ORDERED this 13th day of February, 1992, in Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13 day of February, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NUMBER 91-7597B1D The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the parties in this case. Rulings on Proposed Findings of Fact Submitted by the Petitioner Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 1 - 3(1,2 and 3 , respectively); 4 - 5(6); 6(4); 7 - 9(5); 12(10); 13(11); 15 - 16(12); 17(13); 18 - 19(16); 20(29); 21(18); 23(19); 24 - 25(20); 26(22); 27(23); 28(22); 29 - 30(29); 32 - 33(25); and 34(26). Proposed finding of fact 10 is rejected as not being supported by competent substantial evidence in the record in that Wright's bid was as per plans and specifications without exceptions or exclusions which included the use of casework manufactured by one of the approved casework manufacturers. Proposed finding of fact 11 is rejected as not being supported by competent, substantial evidence in the record in that the Board knew of Empire's bid being based on nonconforming materials prior to issuing its Notice of Intent. However, the only information the Board had in reference to Wright's bid before issuing its Notice of Intent was that Wright had bid as per plans and specifications and would be installing casework manufactured by one of the approved manufacturers. The only question was whether Empire could furnish casework manufactured by one of the approved manufacturers. Proposed finding of fact 14 is neither material nor relevant. How the Board's architect interpreted Wright's bid is neither material nor relevant to this proceeding. Proposed finding of fact 22 is unnecessary to the conclusion reached in the Recommended Order. Proposed finding of fact 31 is more in the way of an argument than a finding of fact. Proposed findings of fact 35 and 36 are covered in the Preliminary Statement. The timeliness of Kellogg's protest is not an issue and therefore, a finding that it was timely is unnecessary. Rulings on Proposed Findings of Fact Submitted by the Respondent While not specifically adopting proposed finding of fact 1, where material or relevant or necessary to this proceeding, and supported by competent, substantial evidence in the record the stipulated facts have been adopted. Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 2(4,5); 3(9); 4 - 5(7); 7 - 8(8); 10(16); 11(14); 12(31); 13(21); and 15(23). Proposed finding of fact 6 is more in the way of an argument than a finding of fact. Proposed finding of fact 9 and 14 are neither material nor relevant. Rulings on Proposed Findings of Fact Submitted by the Intervenor See ruling on Respondent's proposed finding of fact Each of the following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 2 - 3(21); 4(24); 5 - 6(21); 13(23); 14(24,28); 15(22); 16 - 17(23,24); and 18(28). Proposed findings of fact 7 through 12 are neither material nor relevant to this proceeding. COPIES FURNISHED: David E. Gurley, Esquire Norton, Gurley & Darnell, P.A. 1819 Main Street, Suite 610 Sarasota, FL 34236 Marianne Kantor, Esquire The School Board of Lee County 2055 Central Avenue Fort Myers, FL 33901 James M. Talley, Esquire Fisher, Rushmer, Werrenrath, Keiner, Wack & Dickson, P.A. Post Office Box 712 Orlando, FL 32802 Karl Engel Superintendent Lee County School Board 2055 Central Avenue Ft. Myers, FL 33901 Honorable Betty Castor Commissioner of Education The Capitol Tallahassee, FL 32399-0400

Florida Laws (3) 120.53120.57489.125
# 2
BAXTER`S ASPHALT AND CONCRETE, INC. vs. DEPARTMENT OF TRANSPORTATION, 83-003397 (1983)
Division of Administrative Hearings, Florida Number: 83-003397 Latest Update: May 21, 1990

The Issue Whether a bid dispute arising in connection with an emergency bid letting is an appropriate subject for formal administrative proceedings, in the absence of an administrative challenge to the fact of the emergency?

Findings Of Fact The parties stipulated that DOT had "received [Baxter's] notices of protest dated September 23, 1983, October 14, 1983, and December 16, 1983, protesting the Department of Transportation's determination that Baxter's Asphalt was not the lowest responsible bidder on this project and petitioning for formal administrative hearings." Baxter's bid was indeed the apparent low bid on Job No. 53030-3511, but DOT has taken the position that Baxter is not a responsible bidder, and has disregarded Baxter's bid on that account. The DOT has moved beyond proposed action and has actually awarded the contract to Gulf, the second low bidder. The parties stipulated: Pursuant to Section 120.53(5)(c) , Florida Statutes, the Department has decided to proceed with the award and execution of the contract with Gulf Asphalt Corporation in order to avoid what the Department perceived as an immediate and serious danger to the public health, safety, or welfare. DOT executed the contract with Gulf on January 6, 1984. As grounds for executing the contract, notwithstanding the pendency of formal administrative proceedings, the Secretary of the DOT stated: ...The conversion of this two lane roadway to a four lane facility is badly needed to increase the traffic capacity and improve the safety of the highway for the traveling public. This section of roadway has a structural rating of 35 which places it in the "Critical" range . . . [and] has an accident ratio of 1.244 which is almost 25 percent above the average rate. dditional funds were appropriated by the Florida Legislature so that work could proceed without delay. It is also imperative that these projects proceed in an orderly fashion to maximize the effective use of [DOT] construction in spection and supervisory personnel. Letter from Secretary Pappas to Baxter, December 23, 1983. Baxter does not concede that an emergency exists with respect to Job No. 53030- 3511, but did concede that the existence of an emergency was for the agency head to determine, subject only to judicial review. In its petition for formal administrative proceedings, Baxter did not raise the question whether an emergency exists. For purposes of the present administrative proceeding, there is no dispute or issue as to the existence of the emergency.

Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That respondent dismiss petitioner's formal written protest as moot. DONE and ENTERED this 9th day of February, 1984, in Tallahassee, Florida. ROBERT T. BENTON II Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of February, 1984. COPIES FURNISHED: Frank A. Baker, Esquire Roberts and Baker P. O. Box 854 Marianna, Florida 32446 Robert I. Scanlan, Esquire Department of Transportation Haydon Burns Building, MS-58 Tallahassee, Florida 32301 Paul A. Pappas, Secretary Department of Transportation Haydon Burns Building Tallahassee, Florida 32301

Florida Laws (2) 120.53120.57
# 3
DIVERSIFIED DESIGN ENTERPRISES vs SEMINOLE COUNTY SCHOOL BOARD, 90-002357BID (1990)
Division of Administrative Hearings, Florida Filed:Sanford, Florida Apr. 20, 1990 Number: 90-002357BID Latest Update: May 22, 1990

The Issue The issue in this case is whether Respondent properly rejected the bid of Petitioner.

Findings Of Fact Respondent issued on February 28, 1990, an invitation to bid concerning the installation of bleachers at a high school ("ITB"). The ITB was duly advertised. Among the bidders was Interkal, Inc., which is a manufacturer of bleachers. The Interkal bid, which was timely submitted, was executed by its president. The Interkal bid contained a bid bond naming Interkal as principal and a certification from the secretary of Interkal reflecting a corporate resolution authorizing the execution of all bid documents on behalf of Interkal by its corporate officers. The Interkal bid disclosed two subcontractors. The supplier was shown as Interkal, and the erector was shown as Petitioner. Petitioner is the authorized factory representative for Interkal in Florida. As such, Petitioner solicits business and installs and removes bleachers on behalf of Interkal. As compensation, Petitioner receives commissions for such work from Interkal. However, the shareholder and chief executive officer of Petitioner is not a shareholder or officer of Interkal. In addition, Petitioner is not authorized to execute bid documents on behalf of Interkal. Petitioner is no more than a Subcontrator of Interkal. The bidder in this case was Interkal, not Petitioner, even though Petitioner handled much of the paperwork or its manufacturer. When an unrelated bidder was awarded the contract, Petitioner filed a formal written protest in its name. Interkal has not participated as a party in the subject proceeding.

Recommendation Based on the foregoing, it is hereby RECOMMENDED that Respondent enter a Final Order dismissing the petition of Diversified Design Enterprises. ENTERED this 22nd day of May, 1990, in Tallahassee, Florida. ROBERT D. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of May, 1990. COPIES FURNISHED: Ned N. Julian Stenstrom, McIntosh, et al. P.O. Box 1330 Sanford, FL 32772-1330 William Merkel, President Diversified Design Enterprises 321 N.E. Second Avenue Delray Beach, FL 33444 Robert W. Hughes, Superintendent Seminole County School Board 1211 Mellonville Avenue Sanford, FL 32771

Florida Laws (2) 120.53120.57
# 5
ROBERT COOK, SARA COOK, AND ALAN TAYLOR vs DEPARTMENT OF JUVENILE JUSTICE, 98-001641BID (1998)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Apr. 09, 1998 Number: 98-001641BID Latest Update: Aug. 10, 1998

The Issue Whether the Department of Juvenile Justice's (Respondent) decision to reject all bids is illegal, arbitrary, dishonest or fraudulent and should be rejected.

Findings Of Fact Petitioners Robert and Sara Cook own a building located at 205 Gus Hipp Boulevard, Rockledge, Florida. The address for Petitioners Robert and Sara Cook is 1950 Murrell Road, Rockledge, Florida. Petitioner Alan Taylor is an agent for Petitioners Robert and Sara Cook, and assisted the Cooks in the preparation and submittal of their Response to the Department's Request for Proposals for Lease Number: 800:0176-COCOA. Respondent, Florida Department of Juvenile Justice, is the state agency that issued the Request for Proposals for Lease Number: 800:0176-COCOA. Intervenor, 11 Riverside Corp., is the bidder to whom the Respondent issued an award letter for the Lease prior to the Respondent's decision to reject all bids. On or about January 12, 1998, the Respondent advertised Request for Proposals ("RFP") for Lease No. 800:0176-COCOA. This was the second RFP issued by the Respondent for the Cocoa Lease. The Respondent did not receive any bids in response to the first RFP. Draft versions of both RFPs were prepared by Respondent's staff. There were only very "minor changes" in the contents of the first and second RFPs, such as revisions to the issuing and advertising dates. The Respondent received proposals from three entities: Robert and Sara Cook, 11 Riverside Corp., and James E. and Jacie Stivers. All three proposals were timely submitted. Respondent's General Services Manager, Fran Lyles, reviewed the three proposals and completed a responsiveness checklist for each proposal. When Ms. Lyles provided the three responsiveness checklists to Ms. Sandy Veal, the checklists for the proposals submitted by the Cooks and 11 Riverside Corp. did not contain any notations that said proposals were non- responsive. Ms. Lyles also informed Ms. Veal that the proposals submitted by the Cooks and 11 Riverside Corp. were responsive. On or about February 19, 1998, Sandy Veal traveled to Cocoa to perform site visits for the two responsive properties. On February 23, 1998, the Respondent issued a written letter of intent to award the Cocoa Lease to 11 Riverside Corp. The letter was prepared by Ms. Veal and signed by Ms. Lyles. The Petitioners timely filed a written Notice of Protest with the Respondent on March 2, 1998, in which the Petitioners challenged the Respondent's February 23, 1988, decision to award the Cocoa Lease to 11 Riverside Corp. In subsequent correspondent and telephone calls to the Respondent, Petitioners' agent provided a detailed analysis regarding the basis for the Petitioners' Notice of Protest. The primary basis was that the other two proposals were not responsive, and that, as the remaining responsive bidder, the Respondent should award the Lease to the Petitioners. Prior to the deadline for the filing of the Petitioners' Formal Written Bid Protest of the Respondent's February 23, 1988, decision to award the Cocoa Lease to 11 Riverside Corp., the Respondent informed the Petitioners that the Respondent had decided to reject all three proposals that the Respondent had received for the Cocoa Lease. On March 12, 1998, the Respondent provided written notification to the Petitioners that the Respondent had rejected all proposals and would "re issue [sic] at a later date." This date coincided with the deadline for the Petitioners to file their Formal Petition in support of their Notice of Protest pursuant to Florida law. On March 17, 1998, the Petitioners timely filed a second written Notice of Protest with the Respondent, in which the Petitioners challenged the Respondent's March 12 decision. No entity other than the Petitioners timely filed a Notice of Intent to Protest. The Respondent's contention that General Services Manager, Fran Lyles, did not review the RFP prior to its issuance is not credible. Ms. Lyles' testimony that she informed Ms. Veal that all three proposals were not responsive prior to Ms. Veal's trip to Cocoa for a site visit is also not credible. Ms. Lyles signed the award letter to 11 Riverside Corp., even though she had allegedly informed Ms. Veal that all three proposals were non-responsive. Ms. Lyles' explanation that she was very busy and simply didn't ask how an award could be made to a bidder that she had determined was non-responsive is also not credible. Ms. Lyles altered the responsiveness determination checklists after the Petitioners filed their Notice of Protest of the Respondent's award to 11 Riverside Corp. Words were added and white-out was used to cover up Ms. Lyles' initial responsiveness determination which was made prior to the filing of the Petitioner's first Notice of Intent. It appears that such alterations were made by Ms. Lyles in an attempt to shift the responsibility for errors made in the bidding process. The sole basis for the Respondent's contention that the proposals submitted by the Petitioners is non-responsive is that the site plan allegedly failed to show parking spaces. The evidence established that the site plan adequately showed the parking spaces, and that the proposal submitted by the Petitioners was responsive. The Respondent erroneously determined that the proposal submitted by the Petitioners was non-responsive. The proposal submitted by 11 Riverside Corp. failed to include the public entity crime statement as required by the Respondent's RFP, and also failed to include proof of zoning. The floor plan included in the proposals submitted by 11 Riverside Corp. failed to include the calculations as required by the Respondent's RFP. The proposal submitted by 11 Riverside Corp. also failed to include the documentation necessary to establish bidder control of the property as required by the Respondent's RFP. Any one of the aforementioned flaws in the proposal submitted by 11 Riverside Corp. rendered the proposal non- responsive. The building included in the proposal submitted by James E. and Jacie Stivers failed to provide the square footage calculations and failed to provide a scaled floor plan with square footage calculations, as required by the Respondent's RFP. The proposal submitted by the Stivers consisted of two separate facilities. However, the proposal submitted by the Stivers only included the items required by the Respondent's RFP for one of the two separate facilities. The proposal submitted by the Stivers failed to include a letter of authority from the owners of both facilities as required by the Respondent's RFP. Any one of the aforementioned flaws in the proposal submitted by the Stivers rendered the proposal non-responsive. It is not arbitrary for Respondent to reject all bids if there is only one responsive bidder. The state has discretion to award, or not award, in the event of a single responsive bidder, so long as the basis for the rejection is not improper. Whether such rejection is in the best interests of the state may be based on several criteria to be taken into account by the Respondent. One of the criteria is the absence of competition for state business and the lack of offerings. Rejection of all bids can be premised on an omission from the RFP or change in the Respondent's needs that would affect the ability of the Respondent to perform the duties prescribed by the Respondent. The Respondent provided evidence of the importance of correct specifications in the RFP. The Respondent made a decision before January 1, 1998, to develop new specifications for use in lease RFPs. The new specifications were used in the "Bradenton" RFP (issued after the Cocoa lease). The new specifications in the Bradenton RFP include a three percent cap on increases in the lease rate. This specification was material because it is an important part of the Respondent's budget evaluation. It was the Respondent's intent to use this new specification in the Cocoa RFP. Another specification omitted from the Cocoa RFP, that was in the Bradenton RFP, was the specification requiring proposer to provide copies of licenses of contractors. The Respondent intended to use that specification in the Cocoa RFP. The absence of this specification in the part has caused delays in occupancy of the leased space by the Respondent. Another specification omitted from the Cocoa RFP, that was in the Bradenton RFP, was the specification requiring the proposer to provide a construction schedule. The Respondent intended to use that specification in the Cocoa RFP. The absence of this specification was deemed by the Respondent to impede the Respondent's ability to assess liquidated damages. The Respondent identified a lease in Sarasota that was negatively affected by the absence of this specification. Another specification omitted from the Cocoa RFP, that was in the Bradenton RFP, was the specification requiring proposer to pay all renovation costs and that there be no outstanding liens on the property. The Respondent intended to use that specification in the Cocoa RFP. The absence of this specification has resulted in liens imposed on office space the Respondent was procuring. Another specification omitted from the Cocoa RFP, that was in the Bradenton RFP, was the specification clarifying whether the proposed space had to be in a single building. The absence of this specification was a concern to the Respondent and has created problems for other state agencies. The Department did not reject all proposals with the intent of avoiding a protest. The terms of the RFP do not specify when or how the Respondent is to notify proposers of the basis for the rejection of all bids. The evidence is insufficient to show that the Respondent's rejecting all proposals was illegal, arbitrary, dishonest or fraudulent.

Recommendation Upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the formal bid protest filed by Petitioners be DISMISSED. DONE AND ENTERED this 24th day of June, 1998, at Tallahassee, Leon County, Florida. DANIEL M. KILBRIDE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 24th day of June, 1998. COPIES FURNISHED: David A. Theriaque, Esquire 909 East Park Avenue Tallahassee, Florida 32301 Scott C. Wright, Esquire Department of Juvenile Justice 2737 Centerview Drive Tallahassee, Florida 32399-3100 Theodore E. Mack, Esquire Powell & Mack 803 North Calhoun Street Tallahassee, Florida 32303 Calvin Ross, Secretary Department of Juvenile Justice 2737 Centerview Drive Tallahassee, Florida 32399-3100 Janet Ferris, General Counsel Department of Juvenile Justice 2737 Centerview Drive Tallahassee, Florida 32399-3100

Florida Laws (1) 120.57
# 6
MIDDLESEX CORPORATION AND AFFILIATES, INC. vs DEPARTMENT OF TRANSPORTATION, 92-004858BID (1992)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Aug. 10, 1992 Number: 92-004858BID Latest Update: Jan. 12, 1993

The Issue The issue in this proceeding is whether Petitioner, The Middlesex Corporation and Affiliates (Middlesex) or Intevenor, J. B. Coxwell Contracting, Inc. (J. B. Coxwell), submitted the lowest and best responsive bid for State Project No. 55040-3521 let by the Florida Department of Transportation (FDOT).

Findings Of Fact The Florida Department of Transportation issued an invitation to bid (ITB) for a contract to construct road improvements on State Road 363 in Tallahassee, Leon County, Florida; Project No. 55040-3521. The ITB incorporated the plans and specifications for the proposed highway improvements. The specifications stated in pertinent part: Article 1-3. . . . for the purpose of award, after the proposals are opened and read, the correct summation of the products of the approximate quantities shown in the proposal, by the unit prices, will be considered the bid. . . . . Until the actual award of the contract, however, the right will be reserved to reject any or all proposals and to waive technical errors as may be deemed in the best interest of the State. . . . .(emphasis supplied) Article 2-6. A proposal will be subject to being considered irregular and may be rejected if it shows omissions, alterations of form, additions not called for, conditional or unauthorized alternate bids, or irregularities of any kind; also if the unit prices are obviously unbalanced, either in excess of or below the reasonable costs analysis values. In addition to the specifications, a part of the plans for the project required the successful bidder to perform substantial excavation work on the project site. The excavation work would more likely than not yield enough fill material to complete any fill or embankments required in the project. Therefore, the plans contemplated that the soils obtained from the excavation work would be used for the construction of an estimated 44,000 cubic yards of embankment in the project. In order to achieve this goal, page seven of the plans entitled "The Summary of Quantities" indicated that embankment was to be a "no-pay item". However, the bid proposal, the form which constitutes the actual bid of the contractor, contained a line item for a price quotation for embankment/fill, Item No. 120-6. By including such a line item in the bid proposal, bidders were required to submit some figure for this item or risk their bid being declared irregular under the specifications for this project. There was no timely objection filed by any bidder indicating that the bidder would be prejudiced by treatment of the embankment/fill item as a no-pay or as a pay item. Likewise, there was no timely challenge to the apparently conflicting plans and pay item sheet or that the conflicting plans and pay item sheet created a stiutaion which prohibited a bidder from submitting a responsive bid. Seven bids for the contract were submitted and opened on May 27, 1992. The three apparent lowest bids at the opening were: Anderson-Columbia at $4,251,147.89; J. B. Coxwell at $4,964,327.81; and Middlesex at $4,977,371.48. After the bids were opened, each bid was reviewed by FDOT's Technical Review Committee (TRC) to determine whether the bid was mathematically and materially unbalanced, contained all appropriate signatures, contained all appropriate documents and otherwise met the technical requirements of the ITB. In essence, the TRC reviews each bid to determine whether it is responsive to the bid proposal and, if not responsive whether the bid's lack of responsiveness is immaterial and waivable by FDOT. After its review of all the bids, the TRC then makes a recommendation to FDOT's Contract Awards Committee on whether a bid should be rejected for material nonresponsiveness to the ITB. In this case, the TRC recommended to the Contract Awards Committee that Anderson-Columbia's bid be rejected as nonresponsive to the ITB. On June 16, 1992, FDOT's Contract Awards Committee adopted the recommendation of the Technical Review Committee and declared Anderson-Columbia's bid nonresponsive. The awards committee also voted to award the bid to J. B. Coxwell as the second responsive low bidder and on July 6, 1992, FDOT posted a notice of intent to award the contract to J. B. Coxwell. In making the award, FDOT looked at the impact of the conflict between the plans and the bid proposal sheet. FDOT's practice is to add all the unit prices listed on the bid proposal sheet to determine the total amount of the bid. FDOT has never deleted an item from the unit price list to determine the amount of a bid. Following these policies and Consistent with Article 3-1 of the specifications, FDOT determined that a bidder's price quote for the enbankment/fill item would be included as a pay item in the total bid despite the plan's indication that embankment/fill would be a no-pay item and despite the fact that the embankment item probably will not be paid as long as the fill required is less than the excavation. However, at the time of bidding, no bidder could be certain that FDOT would choose to pay or not pay item 120-6. In this case, a review of the bids demonstrates that bidders were not uniform in their application of the conflict between the plans and bid proposal sheet in developing their specific bids. Some bidder's, like J. B. Coxwell, bid very low prices for the embankment/fill in their bid. Some bidder's, like Middlesex, bid prices for the embankment/fill item closer to the average unit price for embankment/fill. In any event, no bidder received any advantage over another bidder due to the conflicting designation of the embankment/fill item and no bidder was favored or discriminated against because of the conflict. In short, all bidders received the same plans and bid proposal, reacted to them in the normal course of their businesses and prepared their bids according to those dictates. The evidence did not demonstrate that the conflict between the plans and bid proposal sheet or FDOT's handling of the conflict was so unfair or confusing that the conflict completely impeded or subverted the purpose or fairness of the competitive bidding process. J. B. Coxwell. Finally, as indicated, the TRC reviews bids to determine whether they are materially unbalanced. In general, unbalanced bids are discouraged by the Department because an unbalanced bid has the potential to allow the contractor to recoup or receive a larger portion of the contract price at the beginning of the contract term thereby making it less disadvantageous for the contractor to walk away from the contract and making agency control over the contractor more difficult. However, not all unbalanced bids will be rejected by FDOT because mathematically unbalanced bids often will have no material impact on the order of the bidders or the interests of the state in the timely and orderly performance of a given road project. Additionally, because of the nature of a given project, there may be a very good reason for a contractor to submit a mathematicallly unbalanced bid. In fact, approximately 80% of all the bids submitted to FDOT contain some form of mathematical unbalancing. Given these facts, FDOT will only reject an unbalanced bid if the unbalancing is material to the project and its award. In evaluating unbalanced bids, FDOT follows the guidance in a May, 1988, memorandum from the Federal Highway Administration (FHWA), which addresses bid analysis and unbalanced bids. The memorandum provides that where unit prices for items bid are either unusually high or low in relation to the engineer's estimate of the price (or mathematically unbalanced), the accuracy of the estimated quantities of the items are to be checked. If the quantities are reasonably accurate, the bid is to be further evaluated to determine whether the mathematical imbalance is "materially unbalanced" such that there is "reasonable doubt that award to the bidder submitting the mathematically unbalanced bid will result in the lowest ultimate cost to the Government." The analysis of a mathematically unbalanced bid to determine if it is materially unbalanced considers the effect of the unbalanced bid on the total contract amount; the increase, if any, in the contract cost when quantities are corrected; whether the low bidder will remain as the low bidder; and whether the unbalanced bid would have a potential detrimental effect upon the competitive process or cause contract administration problems later. In this case, FDOT compared the unit prices (line item prices) by each bidder on the bid proposal sheet to the average unit price for that item. The average unit price is based upon an average of the bidders' unit prices bid for a given pay item and the Department's estimated unit price for that item. If an individual bidder's unit price is significantly greater or less than the average price, FDOT's computer flags the item as mathematically unbalanced. Such a bid then receives further evaluation by FDOT to ensure the accuracy of the original estimates of the quantities of those items for which an unbalanced unit price has been submitted. FDOT also reviews the project plans for accuracy. The more in-depth review is performed to determine if there is a potential for a cost overrun or if there is an error in FDOT's estimated quantities which would result in an increased cost to the State for the project. In this case, J. B. Coxwell and Middlesex submitted bid proposals for each of the individual line item prices contained on FDOT's form. J. B. Coxwell's unit price for the embankment/fill item was $.10 per cubic yard of fill. FDOT's average price for the embankment/fill item was $3.20. The Middlesex quotation for embankment/fill was $2.25 per cubic yard of fill. FDOT's computer analysis of J. B. Coxwell's bid flagged the embankment/fill item as mathematically unbalanced. The quote by Middlesex for the embankment/fill item was not unbalanced and therefore was not flagged for furhter review by FDOT. However, the Middlesex bid was flagged as unbalanced for other line item quotations contained in its bid proposal. FDOT then made a more in-depth review of the bid of J. B. Coxwell and determined that although the bid was mathematically unbalanced, it was not materially unbalanced and did not result in a change in the bidding order. This determination was primarily based on the fact that the excavation portion of the project would yield enough fill to perform the embankment portion of the contract. Thus, a lower than average price in that item was not detrimental to the state, but, in fact, was in its best interest since a quote closer to FDOT's average would cause the state to be double billed for the fill FDOT's site would supply. There is no question that this was a reasonable analysis of the project in this case. Similarly, FDOT, utilizing the same analysis for unbalanced bids, also determined that the mathematically unbalanced unit prices submitted in the Middlesex bid were not materially unbalanced. Given the fact that Middlesex also had a mathematically unbalanced bid, which received the same analysis, Petitioner's argument that Coxwell's mathematically unbalanced bid should be rejected for such imbalance is rejected. Therefore, Middlesex has failed to demonstrate that it submitted the best responsive bid for State Project No. 55040-3521 and its protest should be dismissed.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered awarding the bid to J. B. Coxwell and dismissing Petitioner's protest. DONE AND ENTERED this 8th day of December, 1992, in Tallahassee, Leon County, Florida. DIANNE CLEAVINGER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings thes 8th day of December, 1992

Florida Laws (3) 120.53120.57337.11
# 7
M K MECHANICAL, INC. vs PALM BEACH COMMUNITY COLLEGE, 93-000933BID (1993)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Feb. 22, 1993 Number: 93-000933BID Latest Update: Aug. 19, 1993

Findings Of Fact Facts based on stipulation These proceedings concern Petitioner's Bid Protest in connection with that certain project known as Chiller Installation, Glades Campus, Project NO. 9237, PBCC No. 6812. Petitioner has taken all steps necessary to perfect its bid protest in a timely manner and has standing to bring this bid protest. Petitioner and Respondent met and were unsuccessful in an attempt to resolve the bid protest as required by Section 120.53(5), Florida Statutes. M. K. Mechanical, Inc., a Florida corporation, is a State of Florida Certified Mechanical Contractor and as such was a "Qualified Bidder." The original specifications for the subject project contained few electrical specifications and were silent as to how an electrical contractor was to be licensed. The bid was due on Tuesday, January 12, 1993, at 2:00 p.m. On Friday, January 8, 1993, at 3:42 p.m., via facsimile transmission, M. K. Mechanical, Inc., received supplementary electrical specifications, thirty (30) pages in length. Contained in these supplementary specifications, for the first time, was a requirement that the electrical subcontractor had to be "locally" licensed. M. K. Mechanical, Inc.'s, primary place of business is in Edgewater, Volusia County, Florida. M. K. Mechanical, Inc.'s, submitted bid was proper in all respects other than an electrical subcontractor's name was not given, instead "to be determined" was inserted. M. K. Mechanical, Inc., submitted the lowest bid. Electrical subcontractor is a "major" subcontractor on this project. The sole basis for the decision by Respondent that Petitioner's bid was "non-responsive" was the failure to list an electrical subcontractor. Additional facts regarding bid specifications The bid specifications include the requirement that bidders list all "major subcontractors" and that the category of "major subcontractors" includes electrical subcontractors. Section 5.2.1 of the Contract Documents within the Bid Specifications provides as follows: Unless otherwise required by the Contract Documents or the Bidding Documents the Contractor at the bid opening shall furnish to the Owner and Architect Form 00420, a written list of the major Subcontractors; Site Utilities, Structural Concrete, Masonry, Structural Steel & Steel Joists, Plumbing, HVAC, Electrical and Roofing, who he proposes to use on this work.

Recommendation On the basis of all the foregoing, it is RECOMMENDED that Palm Beach Community College enter a Final Order in this case denying the protest of the Petitioner, M. K. Mechanical, Inc., and awarding the contract in Project No. 9237, PBCC No. 6812 to the Intervenor, Hill York Corporation. DONE AND ENTERED this 15th day of July, 1993, in Tallahassee, Leon County, Florida. MICHAEL M. PARRISH Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of July, 1993. COPIES FURNISHED: Sid C. Peterson, Jr., Esquire DeLoach & Peterson, P.A. Post Office Box 428 New Smyrna Beach, Florida 33170 James M. Adams, Esquire Gibson & Adams, P.A. Post Office Box 1629 West Palm Beach, Florida 33402 Herbert L. Dell, President Hill York Corporation Post Office Box 350155 Fort Lauderdale, Florida 33335 The District Board of Trustees Palm Beach Community College 4200 Congress Avenue Administration Building Lake Worth, Florida 33461 Attention: Mr. Dick Jones

Florida Laws (2) 120.53255.0515
# 8
CON-AIR INDUSTRIES, INC. vs SEMINOLE COUNTY SCHOOL BOARD, 98-004714BID (1998)
Division of Administrative Hearings, Florida Filed:Sanford, Florida Oct. 27, 1998 Number: 98-004714BID Latest Update: Jan. 20, 1999

The Issue Whether the School Board of Seminole County's, notice of intent to award Bid No. 102589, for air filter maintenance, service, and replacement to Filter Service and Installation Corporation was clearly erroneous, contrary to competition, arbitrary, or capricious.

Findings Of Fact The Seminole County School District is a political subdivision of the State of Florida, created by Article IX, Section 4, Florida Constitution. The powers and duties of the school board are enumerated in Chapter 230, Florida Statutes. The Superintendent of the Seminole County School District is a constitutional officer, whose office is created by Article IX, Section 5, Florida Constitution. The powers and duties of the Superintendent are enumerated in Chapter 230, Florida Statutes. The Seminole County School Board issued a call for bids for air filter maintenance service and replacement under Bid No. 102589 on September 14, 1998. Bids were submitted by Con-Air Industries, Inc., the protester, and Filter Service & Installation Corp., the apparent low bidder. The bids were opened on September 28, 1998, and were evaluated. Each bidder was determined to be a responsible bidder to the CFB. Intervenor submitted the lowest numerical bid. On October 1, 1998, Respondent's staff recommended that the CFB be awarded to Intervenor. The decision to recommend the award of the filter service Bid No. 102589 complies with the bid specifications. The instructions to bidders, as stated on the Proposal Form, direct a bidder to total lines A-C and to enter the total at line D. The instructions state that a bidder is not to include the cost as stated at lines E & F in the total. The proposal form then states that the total cost, as stated at line D shall be used to determine the apparent low bidder. The bid proposal document stated that the total of the prices stated at items A, B, and C would be used to determine the lowest numerical bid. The bid proposal document stated that the Respondent reserves the right to negotiate unit cost proposed for item E. The line D total submitted by the Petitioner is stated at $3.45. The line D total submitted by the apparent low bidder, is stated at $2.60. Intervenor submitted the lowest numerical bid. Intervenor does business under the fictitious name Filter Sales & Service. That fictitious name has been registered with the Secretary of State for the State of Florida. Filter Service & Installation Corp., and Filter Sales & Service are one and the same. The reference by Intervenor at line F to "Per Price Sheet" and the failure of Filter Service & Installation Corp. to attach a price sheet to its proposal form is not a material deviation from the requirements of the bid specifications. The total at line D is the total used to determine the lowest bidder. Filter Service & Installation Corp. is the lowest and best bid from a responsive and responsible bidder. The Petitioner followed the procedure set forth in the bid proposal document in making a determination that the Intervenor was the lowest numerical bidder. Petitioner reserved the right to reject all bids and to waive any informalities. Petitioner failed to prove that the notice of intent to award the bid to Intervenor was clearly erroneous, contrary to competition, arbitrary, or capricious.

Recommendation Upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Respondent award the contract for filter maintenance, service, and replacement under Bid No. 102589 to the Intervenor, Filter Service and Installation Corp., as recommended by its staff. DONE AND ENTERED this 11th day of December, 1998, in Tallahassee, Leon County, Florida. DANIEL M. KILBRIDE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 11th day of December, 1998. COPIES FURNISHED: Robert N. Hering, President Con-Air Industries, Inc. 3055 Pennington Drive Orlando, Florida 32804 Ned N. Julian, Jr., Esquire Seminole County Public Schools Legal Services Department 400 East Lake Mary Boulevard Sanford, Florida 32773-7127 Robert W. Smith, Esquire 430 North Mills Avenue, Suite 1000 Orlando, Florida 32803 Dr. Paul J. Hagerty, Superintendent Seminole County Public Schools 400 East Lake Mary Boulevard Sanford, Florida 32773-7127

Florida Laws (1) 120.57
# 9
SHAFER AND MILLER, INC. vs. DEPARTMENT OF GENERAL SERVICES, 76-001375 (1976)
Division of Administrative Hearings, Florida Number: 76-001375 Latest Update: Oct. 05, 1977

The Issue Whether Petitioner should be granted an equitable adjustment to increase the contract price in the amount of $337,714 for a mistake in bid on project No. BR-7702/8701, Library/Auditorium, Florida International University.

Findings Of Fact In April 1974, Respondent advertised for bids for the construction of a library-auditorium building at Florida International University, Miami, Florida, State Project No. B.R. 7702/8701. Respondent's representative for this project was the architectural firm of Ferendino/Grafton/Spillis/Candela, Coral Gables, Florida. The advertisement for bids specified that sealed bids would be received until 2:00 p.m. on May 16, 1974, at which time they would be publicly opened and read aloud. In fact, the advertised time period was extended until the same hour on May 23, 1974. The advertisement provided that bids must be submitted on the proposal form furnished by the architect/engineer and be accompanied by a bid bond or an equivalent cash amount in a sum not less than five per cent of the amount of the base bid as a guarantee that the bidder would enter into an agreement with the owner if this bid was accepted. It further provided that the bid would remain in force for thirty (30) days after the time of opening. The advertisement also contained the following statement: "The Department of General Services reserves the right to reject any and all bids and to waive informalities in any bid whenever such rejection or waiver is in the interest of the State of Florida." (Exhibit 1a, testimony of Williams) In preparing its bid on the project, Petitioner utilized two company forms. One included columns for the various portions of the work with blocks opposite each portion for the insertion of the names of subcontractors and the amounts of their bids. The other form was a recapitulation of the low subcontractors' bid by the various segments of the contract, and the form also included spaces and amounts for the work to be accomplished by the contractor itself. The normal procedure followed by Petitioner in this and prior projects was to enter subcontractors' bids on the subcontractor's bid tabulation form when received over the telephone and, when all such bids had been received shortly before the deadline for submission of bids by the prime contractors on the project, to enter each low subcontractor bid on the recapitulation form. This would then be totaled to arrive at Petitioner's bid to be submitted to Respondent. (Testimony of Kearns). The subcontractor tabulation form for the instant project listed an item for "PRECAST STRUCTURAL." Opposite this entry in blocks on the form had been printed the names of subcontractors from whom Petitioner expected to receive bids, including Pre-Stressed Systems, Inc. (P.S.I.), Meekins, Stresscon, and Houdaille. However, since there were two different pre-case structural items called for under the specification, i.e., joists under section 3-B and pre-case panels under section 3-C, the words and figures "3B Joists" and "3C panels" were penciled in above and below the printed words "PRE-CAST STRUCTURAL" to show the need for entering bid figures for both items. However, there was no separation of these items in the various blocks for subcontractor's bids. (Exhibits 1b, 1c, Testimony of Kearns) Usually bids of major subcontractors were not received until the morning of the final day for submission of the total bids, and many were not received until immediately prior to the time the bid must be tallied and submitted. On the morning of May 23, 1974, the day for bid opening, Petitioner's employee, Edward A. Kearns, Jr., an estimator, was responsible for preparing Petitioner's bid. The only bid Petitioner had received for precast joists was that submitted by P.S.I. in the base amount of $460,000. This sum was entered on the bid tabulation from in pencil under the printed name P.S.I. Bids for the pre-cast panels were received from two of the subcontractors whose names were printed on the form an the amounts were entered in pencil as follows: "Meekins - 399,800, Stresscon - 400,00." No bid was entered for Houdaille. About 11:00 a.m., a telephonic bid on the panels was received from Cast-Crete Corporation of Kissimmee. This bid was considerably lower than that of Meekins and, because Petitioner had not heard of or dealt with Cast-Crete in the past, it asked all three bidders on the panels to verify the requirements and prices. While awaiting the return of this information, the Cast-Crete bid was not entered on the bid tabulation form. Thereafter, Cast-Crete informed Petitioner that it was raising its bid somewhat and this information was placed on a separate subcontractor bid form for cast-Crete, but not entered on the tabulation form containing all bids. The final Cast-Crete bid was in the amount of $337,714. By this time, Petitioner's office was quite hectic in that other bids were coming in at a fast pace and the phone was ringing continuously. Many bidders sought clarification on items or had to give their bids to Kearns which was time-consuming. As the time for submission by Petitioner to Respondent drew near, Kearns took the low subcontractor bids from the bid tabulation form and transferred them for each category of work to the recapitulation form. On this form, there was a single line for "Precast structural" and, on that line, Kearns entered the bid that had been received from P.S.I. for precast joists, but forgot to include any bid for the precast panes. Since no breakdown for joists and panels was shown on the recapitulation form, he assumed that bids for all portions of the work hand been included. All items on the recapitulation form were added and Petitioner arrived at a total base bid of $3,999,259, which did not include the bid for precast panels in the amount of $337,714. (Testimony of Shafer, Sr., Kearns, Exhibits 1b, 1c, 1f) Petitioner's employee, Ron Shafer, Jr., previously had been sent to the place of bid opening at Florida International University with the formal bid letter with the amounts left blank. Shortly before 2:00 p.m., Petitioner provided him by telephone with the amounts to place on the be bid form and submit to the Respondent's representative. He submitted the formal bid just prior to the deadline. The bids were thereafter opened and, although Ron Shafer, Jr., noted that Petitioner's bid was some $400,000 lower than the next lowest bidder, he was unaware of the circumstances of the mistake and returned to the office. The representative of Respondent had opened the bids and an officer of the architectural firm, Freeman J. Williams, was also present. Nothing was said at the time concerning the large disparity between Petitioner's bid and the other bids, and Williams saw no need to ask Petitioner to verify its bid at that time. (Testimony of Shafer, Jr., Williams, Exhibits 1d, 1v) Meanwhile, after Kearns had tallied the final bid figures and they had been called in to the employee at Florida International University, Petitioner's personnel sat around the office and discussed the job for several minutes. They then started to gather up all the sub-bids to put in a folder when they discovered a "subcontractor's bid form" for Cast-Crete Corporation and realized that it had not been included on the tabulation sheet or on the final recap sheet. Immediate attempts were made to telephone the architect about the mistake. When Williams was reached at his office some thirty minutes after he had left Florida International University, Petitioner requested that its bid be withdrawn after explaining the circumstances. Williams suggested that Petitioner immediately send a telegram to Respondent explaining this situation. Petitioner did so in the following language: "In reviewing our bid, we discovered we had omitted the cost of precast panels manufacturers bid from our tabulation sheet, in the amount of $282,714. We, therefor, regretfully must with- draw our bid on the FIU library and auditorium building. We could, however, accept award of contract if this amount could be added to either of our base bids. Please advise. SHAFER AND MILLER, INC. R C Shafer" In the telegram, an additional mistake was made by using the figure of $282,714 which did not include the erection of the panels in the amount of $55,000 that had been the subject of a separate bid by Cast-Crete. After receipt of the telegram, Respondent's representatives requested that Petitioner come to Tallahassee with their pertinent documents relating to the bid to discuss the matter. They did so and thereafter heard nothing further until June 5, 1974, at which time a letter was received from the Department of General Services, dated May 31, 1974, advising that, subject to final approval by the Governor and the Cabinet, it was propose to recommend acceptance of Petitioner's low bid and award the contract to it in the amount of $4,122,000 for Base Bid 1 and Priority 1 Alternate A, Priority 2, Alternate C, and Priority 3, Alternate D. The meeting of the Cabinet at which the award was to be recommended was stated in the letter to be held on June 4, 1975. Since Petitioner did not receive the letter until June 5, it had no opportunity to be present at the time matter was considered. By separate letter of May 31, 1974, the Department of General Services enclosed four copies of a standard form of agreement and performance and payment bond to be executed and returned. (Testimony of Williams, Shafer, Sr., Kearns, Exhibits 1e, 1g, 1h) Petitioner contacted legal counsel, James E. Glass, on June 5. He checked into the matter and found that the contract had already been awarded on June 4 by the Cabinet. He then telephoned Arnold Greenfield, General Counsel for the Department of General Services, and asked if the state could rebid the job at which time Petitioner would submit its original intended bid. Greenfield stated that the project was critical from a budget standpoint and that the state would not rebid it, and insisted that the Petitioner proceed or else forfeit its bid bond and be subject to suit for any excess costs of performance. Glass reminded Greenfield that Petitioner proceed or else forfeit its bid bond and be subject to suit for any excess costs of performance. Glass reminded Greenfield that Petitioner could seek injunctive relief in the matter, and the latter then stated that if Petitioner would proceed with the contract, Respondent would acknowledge its right to claim a modification of the contract. This conversation was confirmed in a letter from Greenfield to Glass, dated June 7, 1974, wherein it was stated "We further understand that your client may wish to seek a modification of such contract, after execution." Glass, in a return letter dated June 12, returned the executed contracts and bonds, stating that Petitioner was doing so in order to act "equitably and in good faith", and was fully reserving its rights to contest the erroneous bid by judicial action for equitable relief. Thereafter, Petitioner received notice to proceed with the work and in due course satisfactorily completed the contract within the required period. This was evidenced by a certificate of acceptance of the building by the using agency, which was approved by Respondent on December 4, 1975. (Testimony of Glass, Exhibit 1e, 1g, 1h, 1i, 1j, 11, 1m, 1s) In December, 1974, Petitioner had submitted its claim for an equitable adjustment in the amount of $337,714 which was the amount of the omitted Cast- Crete bid. During the ensuing year Petitioner submitted audits of its expenses on the job to Respondent and in January, 1976, further audit information was provided at the request of Respondent. On May 6, 1976, Respondent informed Petitioner that it would not approve any increase in the contract amount. Thereafter, on June 11, Petitioner filed its petition herein seeking an equitable adjustment in the amount of $337,714. The petition was referred to the Division of Administrative Hearings by the Respondent on August 2, 1976, and the undersigned Hearing Officer was assigned to conduct the hearing therein. (Exhibit 1r, 2, 4, 5, 6) By a Motion to Abate, dated August 23, 1976, Respondent requested that the matter be held in abeyance pending the submission of the petition to the project architect and his rendering of a determination indicating whether the relief should be granted or denied, as a "condition precedent to the contractor obtaining consideration of said petition in any proceeding authorized by Chapter 120, Florida Statutes." Respondent stated in its motion that the contract clearly provided that nay and all claims or disputes should be first submitted to the architect for determination, and that thereafter, either party could obtain administrative review of the determination by filing a written appeal to the Department of General Services within thirty days. The motion further stated that since this prerequisite had not been accomplished, there was no basis for an administrative appeal at that time. On the same date, Respondent advised the architect of the situation and requested expeditious consideration of the matter. On August 27, the architect issued its determination stating "From our personal knowledge of the events during the bid opening process, and the subsequent events that led to the awarding of the bid, we concur in the contractor's request." In November 1976, Respondent's general counsel advised the Hearing Officer that settlement efforts were in progress but requested that the matter be scheduled for hearing nevertheless. Notice of hearing was issued on December 15, 1976, and the case was heard on January 27, 1977. (Exhibits 1t, 1u, Pleadings) Petitioner's intended total bid, including alternates, amounted to $4,459,714. A change order of $194 was issued during the course of the work, amounting to a total of $4,459,908. Petitioner's direct costs on the project were $4,094,890. Overhead was computed at 2.85 per cent of direct costs in the amount of $116,705, for a total cost of $4,211,595. Overhead was computed based on the ratio of total general and administrative expense to total direct costs incurred on all of Petitioner's jobs in process for the year ending May 31, 1975. However, the audit reports included payment in the amount of $335,634 to Cast-Crete Corporation. The actual amount paid to that firm was $325,234 - difference of $10,400, making Petitioner's actual costs $4,201,195. During the course of the contract, Respondent paid Petitioner $4,122,194, resulting in a net loss to Petitioner of $79,001. An anticipated profit for performance of the contract was computed on the basis of the average profit on other jobs of 4.4 per cent, amounting to the sum of $180,377. The latter two sums total $259,378, and it is found that figure is the reasonable amount of Petitioner's claim. (Exhibits 2-5)

Recommendation That Petitioner's claim for equitable adjustment under Project No. BR- 7702/8701 be granted and that a change order be issued increasing the contract price by $259,378.00. DONE and ENTERED this 21st day of March, 1977, in Tallahassee, Florida. THOMAS C. OLDHAM Hearing Officer Division of Administrative Hearings Room 530 Carlton Building Tallahassee, Florida 32304 (904) 388-9675 COPIES FURNISHED: Donna H. Stinson and Daniel S. Dearing, Esquires Post Office Box 1118 Tallahassee, Florida 32302 James E. Glass, Esquire 2600 First Federal Building 1 Southeast 3rd Avenue Miami, Florida 33131 John A. Barley, Esquire General Counsel Department of General Services Room 110 Larson Building Tallahassee, Florida 32301

Florida Laws (1) 120.57
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer