The Issue The central issue in this case is whether the Department of Environmental Regulation (Department) should grant a dredge and fill permit which has been requested by the Respondent, William R. Cullen (Applicant). That proposed permit has been opposed by the Petitioners (who will be referred to collectively as Petitioners for convenience sake).
Findings Of Fact Based upon the testimony of the witnesses and the documentary evidence received, the following findings of fact are made: The Department is the state agency authorized to issue permits pursuant to Chapter 403, Florida Statutes. The Respondent, William R. Cullen, filed an application for a dredge and fill permit to construct a slip marina on June 4, 1985. The original request was subsequently amended to seek approval for a forty-two slip commercial marina. The project site for the Applicant's marina is located at Key Largo, Monroe County, Florida. The site is within Buttonwood Sound, Florida Bay. The property is owned by Mr. Cullen and his family. All of the proposed improvements will be constructed on submerged lands or uplands owned or controlled by the Cullen family. The project site is located within a commercial area of Key Largo and contains frontage on both the water, Buttonwood Sound, and the highway, U.S. Highway 1. The project site has a basin which was created by the excavation of materials used for road construction from the shoreline and the installation of an L-shaped rock jetty which runs roughly perpendicular and then parallel to the shoreline. This jetty was installed during the late 1960s. The water depths within the basin range from 3 feet to approximately 14 feet. The water within the basin is subject to the same tidal considerations as the waters within Buttonwood Sound. There is no interruption of the flow of water in and out of the basin from those waters of the Sound. The water within this basin is within an Outstanding Florida Water as defined in Rule 17-3.041, Florida Administrative Code. The Applicant's plan calls for the excavation of appproximately 30,170 square feet of upland area and the dredging of the existing basin for approximately 18,460 dredged square feet. During the construction phases, the Applicant proposes to install turbidity curtains to limit the adverse effects expected during that time. The improvements are intended to be a permanent alteration to the basin design and will permanently modify the marine life habitat within that basin. The Applicant proposes to remove portions of the existing jetty to allow additional water to flow through the basin unimpeded by the jetty walls. The removal of the jetty walls will expedite the dilution and flushing of potential pollutants from the basin on a tidal frequency. That flushing is purported to assure that the water quality within the basin will not be diminished. However, such pollutants will be flushed into Buttonwood Sound. Stormwater accumulating on the upland project is to flow toward a lower upland area and should not to be dumped into the basin. The proposed marina is to have fueling facilities and the Applicant has agreed to design that system to limit inadvertent spillage. Further, as a condition of the permit, the Applicant has agreed to abide by the Department of Natural Resources' spill contingency plan requirements. The proposed marina is designed to provide portable sewage pumpout facilities for each slip. A permanent pumpout facilities will also be available. The Applicant seeks to attract boats in the range of 30 to 50 feet in length at this facility. While there are a number of other marinas in other areas of Key Largo which might accomodate that size boat, the marinas in the immediate vicinity of this project site are designed for smaller craft. The area within the basin consists of unvegetated bottom, submerged rip-rap, sea grasses, and hardbottom/algae communities--the predominant classifications being the latter two. The deeper hardbottom areas are to be filled and portions of the sea grasses will be dredged in order to configure the proposed docks. Additionally, other sea grass areas will be shaded, and thereby disturbed, by the construction of the docks. There are no historical or archaeological features relevant to the proposed site. The area has not been designated as a critical manatee area, however, manatees do frequent the project vicinity and have been observed feeding immediately adjacent to the basin. The permit proposed for this project requires a water quality monitoring plan. In addition to sampling for coliform, diesel by-products, oils, greases, detergents, oxygen, copper, lead and zinc, the plan requires sampling for aluminum, cadmium, and chromium. The monitoring stations are to be located both within the basin (2 stations) and outside the basin (2 stations). Liveaboards or others continuously docked at the marina will create additional shading which will disrupt and adversely affect the sea grass system. In order to provide access to the marina, the Applicant intends to dredge a channel in an area containing sea grass which is undisputedly within the Outstanding Florida Waters. The Department deemed the subject application was complete on February 23, 1988. The Department did not apply the Keys Rule found in Rule 17-312.400, Florida Administrative Code, to this project. The Department also did not apply the Mitigation Rule found in Rule 17-312.300, Florida Administrative Code, to this project. Michael Dentzau has personally reviewed and processed 250-300 dredge and fill permits during his tenure with the Department. Of those projects he has reviewed, he has not recommended that dense sea grass beds of the type located within this project site be dredged in order to construct a commercial marina. Phillip Edwards was responsible for executing the Intent to Issue in this case. In determining that this project had provided reasonable assurances that water quality standards will not be violated, Mr. Edwards weighed the public interests criteria set forth in Section 403.918, Florida Statutes. Because he received letters purportedly from elected officials, Mr. Edwards presumed that the project was in the public interest. That assumption of fact has not been established by this record. According to Mr. Edwards, the adverse effects expected by this project could be adequately addressed by the permit conditions when weighed against the public interest in favor of the project. Since Mr. Edwards' assumptions as to the public interest in this project have not been established, his conclusion regarding the weight that interest should receive can be given little consideration. The project as proposed by the Applicant will not adversely affect navigation or cause harmful erosion or shoaling. The project as proposed by the Applicant will adversely affect fishing or marine productivity within the basin since it will permanently alter the basin biologically by destroying sea grass. The increased boat traffic within the Sound will also detract from the present recreational uses enjoyed by area residents. According to Mr. Edwards, it is very unusual for the Department to issue a permit when sea grasses will be adversely affected. In the 17 years in which he has reviewed permits, only two occasions merited approval when the destruction of sea grasses to the extent in this case would result. Neither of those cases were factually similar to the case at issue. In those cases, however, elected officials advised Mr. Edwards, as he presumed they had here, that there was a public need for the permit. Increased boat traffic will result in increased manatee mortality due to collisions. In order to assure water quality will not be degraded within a marina, the project should have a short flushing time comparable to healthy natural embayments. In this case, the flushing proposed by the Applicant is dependent, in part, on winds which may be inconsistent or relatively minimal during the summer months.
Recommendation Based on the foregoing, it is RECOMMENDED: That the Department of Environmental Regulation enter a final order denying the permit requested by the Applicant. DONE and ENTERED this 22nd day of August, 1990, in Tallahassee, Leon County, Florida. JOYOUS D. PARRISH Hearing Officer Division of Administrative Hearings 1230 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of August, 1990. APPENDIX TO CASE NOS. 89-3779 et seq. RULINGS ON THE PROPOSED FINDINGS OF FACT SUBMITTED BY PETITIONERS: The first three sentences of paragraph 1 are accepted; the remainder is rejected as argument or irrelevant. Paragraph 2 is accepted. Paragraph 3 is accepted. With regard to paragraph 4, it is accepted that the Department deemed the application complete on February 23, 1988; otherwise, the paragraph is rejected as argument. With regard to paragraph 5, it is accepted that the habitat within the basin is the same as the habitat throughout Florida Bay and that the basin is not "enclosed" hydrologically; otherwise, the paragraph is rejected as argument or comment. Paragraphs 6, 7, 8, 9, 10, 11, and 12 are rejected as argument, conclusions of law, or comment. The paragraphs do not recite facts pertinent to this case. Paragraphs 13, 14, and the first two sentences of paragraph 15 are accepted. The remainder of paragraph IS is rejected as argument. The first two sentences of paragraph 16 are accepted. The remainder of the paragraph is rejected as comment or argument. Paragraph 17 is accepted. Paragraph 18 is rejected as argument. To the extent that paragraph 19 accurately describes Van de Kreeke's assessment of the report it is accepted; otherwise rejected as irrelevant, comment, argument, recitation of testimony or unsupported by the record. The report upon which comment is directed was not offered in this cause to prove its truth/accuracy. Paragraphs 20 through 22 are rejected as comment, argument, recitation of testimony or unsupported by the record-- see comment to paragraph 19 above. Paragraphs 23 through 26 are accepted. Paragraphs 27 and 28 are rejected as argument, comment, or contrary to the weight of the evidence. Paragraphs 29 and 30 are accepted. Paragraph 31 is rejected as argument or contrary to the weight of the evidence. Paragraphs 32 and 33 are accepted. Paragraph 34 is rejected as hearsay, irrelevant, or argument. Paragraph 35 is rejected as comment or argument. Paragraph 36 is accepted. Paragraphs 37 through 40 are rejected as argument or contrary to the weight of the evidence. Paragraphs 41 through 43 are accepted. Paragraph 44 is rejected as contrary to the record. Paragraph 45 is rejected as argument. Paragraph 46 is rejected as argument or contrary to the weight of the evidence. Paragraph 47 is accepted but is comment. Paragraphs 48 and 49 are accepted. Paragraph 50 is rejected as repetitive. Paragraph 51 is rejected as argument or conclusions of law. The first three sentences of paragraph 52 are accepted. The remainder of the paragraph is rejected as argument. The first sentence and that portion of the second sentence of paragraph 53 that ends with the word "authenticity" is accepted. The remainder of the paragraph is rejected as argument or conclusions of law. Paragraphs 54 and 55 are accepted. Paragraph 56 is rejected as irrelevant or hearsay. Paragraph 57 is rejected as hearsay. Paragraph 58 is rejected as argument, comment, or irrelevant. Paragraphs 59 through 66 are accepted. Paragraph 67 is rejected as contrary to the weight of the evidence. Paragraph 68 is rejected as contrary to the weight of the evidence. Paragraphs 69 and 70 are accepted. Paragraph 71 is rejected as repetitive. Paragraph 72 is rejected as argument. The first sentence of paragraph 73 is accepted; the remainder is rejected as contrary to the weight of the evidence. Paragraph 74 is accepted. Paragraphs 75 through 77 are rejected as contrary to the weight of the evidence. Paragraphs 78 and 79 are accepted. Paragraph 80 is rejected as repetitive. With the inclusion of the words "and hardbottom and algae" paragraph 81 is accepted. Paragraph 82 is accepted. Paragraph 83 is accepted. Paragraph 84 is rejected as contrary to the weight of the evidence. 5l. Paragraphs 85 through 89 are accepted. With the substitution of the word "not" for the word "ever" in the last sentence of paragraph 90, it is accepted. Paragraphs 91 through 94 are accepted. Paragraph 95 is rejected as not supported by the record or contrary to the weight of the evidence. Paragraphs 96 through 100 are accepted. Paragraph 101 is rejected as repetitive. Paragraphs 102 through 106 are rejected as argument, comment, or irrelevant. RULINGS ON THE PROPOSED FINDINGS OF FACT SUBMITTED BY THE DEPARTMENT: Paragraph 1 is accepted. Paragraph 2 is rejected as contrary to the weight of the credible evidence. The waters within the basin are of the same origin as they were prior to the creation of the jetty; no artificial body of water was created. With regard to paragraph 3 it is accepted that the jetty was constructed in the late 1960s. Paragraph 4 is accepted. With regard to paragraph 5 it is accepted that that is the applicants proposal no conclusion as to the likelihood of that is reached. Paragraph 5 is accepted. Paragraph 6 is accepted. Inevitably, however, spills will occur and must be considered as an adverse affect of the project. Paragraph 7 is accepted. Paragraph 8 is rejected as unsupported by competent evidence or contrary to the weight of the evidence presented. Paragraph 9 is rejected as contrary to the weight of the evidence. Paragraph 10 is accepted. Paragraph 11 is accepted but is inadequate to offset the adverse affects to manatees. Paragraph 12 is accepted but is inadequate to limit the adverse affects to sea grass. Paragraph 13 is rejected as contrary to the weight of the evidence. Paragraph 14 is rejected as contrary to the weight of the evidence. Paragraph 15 is accepted. Paragraph 16 is accepted. Paragraphs 17 and 18 are accepted. RULINGS ON THE PROPOSED FINDINGS OF FACT SUBMITTED BY THE APPLICANT: Paragraphs 1 through the first sentence of paragraph 6 are accepted. The second sentence of paragraph 6 is rejected as contrary to the weight of the evidence. Paragraphs 7 through Il are accepted. Paragraph 12 is rejected as irrelevant. Paragraphs 13 through the first sentence of paragraph 17 are accepted. The remainder of paragraph 17 is rejected as contrary to the weight of the evidence. Paragraph 18 is accepted. Paragraph 19 is rejected as unsupported by the record or contrary to the weight of the evidence. Paragraph 20 is accepted. Paragraphs 21 through 26 are rejected as contrary to the weight of the evidence. Paragraph 27 is rejected as contrary to the weight of the evidence or unsupported by competent evidence. The first sentence of paragraph 28 is accepted, the remainder rejected as speculative, comment, or unsupported by the record. The first sentence of paragraph 29 is accepted, the remainder rejected as contrary to the weight of the evidence. Paragraph 30 is accepted. Paragraph 31 is rejected as contrary to the weight of the evidence. Paragraph 32 is rejected as contrary to the weight of the evidence. Paragraph 33 is accepted but is irrelevant. Paragraph 34 is rejected as contrary to the weight of the evidence. Paragraph 35 is accepted; however, sea grasses not disturbed by dredging will still suffer adverse affects from shading and silting. Paragraph 36 is accepted but see comment to paragraph 35 above. Paragraph 37 is accepted. Paragraph 38 is accepted. Paragraph 39 is accepted but is irrelevant. Paragraph 40 is accepted. Paragraph 41 is accepted. Paragraph 42 is accepted. Paragraph 43 is rejected as irrelevant. Paragraph 44 is rejected as contrary to the weight of the evidence. Paragraph 45 is accepted but it should be noted that is not the extent of the proposal. Paragraph 46 is rejected as contrary to the weight of the evidence. Paragraph 47 is accepted. Paragraph 48 is rejected as contrary to the weight of the evidence. Paragraph 49 is rejected as contrary to the weight of the evidence. COPIES FURNISHED: Pamela Presnell Garvin Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Charles Lee Florida Audubon Society 1101 Audubon Way Maitland, Florida 32751 Robert Routa P.O. Box 6506 Tallahassee, Florida 32314-6506 Linda McMullen McFARLAIN, STERNSTEIN, WILEY & CASSEDY, P.A. 600 First Florida Bank Building Tallahassee, Florida 32301 Dale H. Twachtmann, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Daniel H. Thompson General Counsel Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 =================================================================
The Issue The issue to be decided in these cases is whether Petitioner, A. Wayne Lujan (Petitioner), was entitled to issuance of five environmental resource permits (ERPs) that Respondent, Department of Environmental Protection (DEP), intended to deny as stated in notices of denial dated October 25, 2019.
Findings Of Fact The following Findings of Fact are based on the stipulations of the parties and the evidence adduced at the final hearing. Parties and Background Petitioner Lujan is the president and a director of Kay Haven Associated Enterprises, Inc. (Key Haven), that owns the five parcels, which are the subject matter of this hearing. Although Key Haven owns numerous lots, it chose to submit ERP applications for the Subject Lots within the Key Haven Tenth Addition plat dated September 1966 (Plat). See Joint Exhibit 84. Joint Exhibit 84 The Subject Lots are located in an unincorporated part of the County on the northwestern edge of a body of land lying north of State Road A1A, identified on the Plat as Raccoon Key. The Subject Lots are approximately half a mile east of the city limits of Key West, Florida. The Subject Lots are all characterized by a small upland portion adjacent to Floral Avenue. The majority of the Subject Lots transition into a mangrove fringe of varying depth and submerged lands containing marine seagrasses and sponges. See Joint Exhibits 81 and 82. Joint Exhibit 81 Joint Exhibit 82 DEP is the administrative agency of the state having the power and duty to protect Florida's air and water resources, and to administer and enforce the provisions of part II of chapter 380, part IV of chapter 373, and chapter 403, Florida Statutes. DEP also administers the provisions of Florida Administrative Code chapters 62-312 and 62-330 regarding activities in wetlands and other surface waters of the state. DEO is the state land planning agency and reviews certain permit applications for consistency with its statutory responsibilities under the Florida Coastal Management Program (FCMP), which includes part II of chapter 163, and part I of chapter 380, Florida Statutes. Relevant to this proceeding, DEO exercises authority over the ACSC program. See § 380.05, Fla. Stat. On July 26, 2018, Petitioner filed five applications for ERPs with DEP. Although certain details within each application differed, the applications all sought to authorize construction of a seawall in the waters of the Gulf of Mexico and in unnamed wetlands within the landward extent of the Gulf of Mexico, a Class III OFW, to remove the entirety of the existing mangrove fringe, and to place fill within wetlands and other surface waters for the construction of single-family residences (Project). The minor differences in each application relate to the length of the seawall and the amount of fill necessary for each lot. Although some testimony was provided concerning the differences, no party argued that the differences were material to the determinations necessary in this proceeding. Accordingly, the factual and legal analysis for the Subject Lots and ERP applications were addressed without distinction herein. DEP forwarded a copy of the applications to DEO for its recommendation. On August 24, 2018, DEO issued objections to approval of the permits citing inconsistency with the Florida Keys ACSC Principles for Guiding Development (PGDs) in section 380.0552(7). DEO also objected based on inconsistencies between the Project and the Monroe County Comprehensive Plan (Comp Plan) and Land Development Code (LDC), which implement the PGDs. DEP's first RAI dated August 24, 2018, included DEO's objections. The first RAI notified Petitioner that DEP had concerns with the Project that included: (1) installation of the vertical seawall; (2) placement of fill within an OFW; (3) direct impacts to marine seagrass bed community without adequate mitigation; and (4) failure to provide stormwater management plans since the Project was a common plan of development. The first RAI contained 19 specific requests for additional information. On October 23, 2018, Petitioner responded to DEP's first RAI by submitting slightly revised plans. The revised Project proposed less of a vertical seawall footprint by adding rip-rap to the side seawalls as a means of containing fill. Petitioner's responses to the 19 specific requests for information can generally be categorized as follows: (1) elimination of some vertical seawalls, but not the ones on the waterward edge of the Subject Lots; (2) no change in the placement of fill; (3) Petitioner would attempt to find appropriate compensatory mitigation for the seagrass impacts; and (4) Petitioner did not consider the Project to be a common plan of development. Regarding DEO's objections, Petitioner stated that "[w]e acknowledge that the project has been forwarded to FWC [Florida Fish and Wildlife Conservation Commission] and DEO and that additional comments and information may be requested by those agencies in order to fully evaluate the application." Petitioner did not substantively address DEO's objections. DEP issued a second RAI on November 21, 2018. DEO again objected in a letter dated November 26, 2018. DEP's second RAI raised the same concerns as the first RAI and acknowledged that four of the 19 specific items were adequately addressed. On January 11, 2019, Petitioner responded to DEP's second RAI by again submitting slightly revised site plans. However, the Project remained generally unchanged, with a proposed vertical seawall on the waterward edge of the lots, rip-rap along the sides, removal of the entire mangrove fringe, and fill of the entire lots eliminating the existing marine seagrasses. DEP issued a third RAI to Petitioner on February 8, 2019. DEO reiterated its objections by letter dated February 8, 2019. The third RAI raised the same concerns as the first and second RAIs, although DEP acknowledged that six of the 19 specific items were adequately addressed. By letter dated April 8, 2019, Petitioner responded to DEP's third RAI. The response again proposed slightly altered site plans from the January 2019 submissions. Petitioner essentially stated that mitigation opportunities were scarce, but had contacted the County and was looking into derelict vessel removal. However, the proposed Project remained generally unchanged, with a proposed vertical seawall on the waterward edge of the lots, rip-rap along the sides, removal of the entire mangrove fringe, and fill of the entire lots eliminating the existing marine seagrasses. As it relates to DEO's objections, Petitioner responded that "[a]fter review of the comments outlined in the [DEO] revised letter, it seems that the DEO objections are related to compliance with the provision[s] of the [Monroe] County [Comp Plan]. We will deal with those issues at the time of local permitting." Petitioner again failed to substantively address DEO's objections. DEP issued its final RAI on May 8, 2019. DEO again objected by letter dated May 6, 2019. This final RAI raised the same concerns as the first, second, and third RAIs. DEP stated that seven of the 19 specific items were not addressed by Petitioner, and that failure to provide a complete response to the prior RAI may result in denial of the ERP applications. On August 29, 2019, Petitioner responded to DEP's final RAI by once again submitting slightly revised plans, and additional information concerning mitigation proposals. However, the Project did not change and Petitioner again failed to substantively address DEO's objections. DEO’s objection letter identified that the ERP applications were inconsistent with the Florida Keys ACSC PGDs, seven Comp Plan policies, and six regulatory provisions of the County's LDC. DEP denied the ERP applications on October 25, 2019. The grounds for denial reiterated the issues not addressed by Petitioner's RAI responses. Specifically: (1) the failure of the Project to provide reasonable assurances concerning direct, secondary, and cumulative impacts to the marine seagrass bed community; (2) continued reliance upon construction of a vertical seawall; (3) failure to provide stormwater management information necessary given the determination that the Project constituted a common plan of development; (4) inconsistency with the FCMP as identified by DEO in its objection letters; and (5) failure to provide reasonable assurances that the Project was clearly in the public interest. Direct Impacts The Project proposed to entirely fill the Subject Lots, contain the fill with vertical seawalls and rip-rap, and construct pile-supported single-family residences. The Project would remove the entire mangrove fringe that aerials and site inspections show is a healthy mix of red, black, and white mangroves along with some green buttonwood. The shallow, open surface waters are dominated by marine seagrasses that vary in density. Petitioner did not make any design modifications to the Project that sought to reduce or eliminate direct impacts to the mangrove fringe and marine seagrasses. Petitioner's resource inventory was done using GIS aerial photography so that the aerial benthic resource surveys submitted to DEP were not ground- truthed. DEP staff conducted physical site inspections and ground-truthing inspections that included swimming in the open surface waters. DEP staff found significant marine seagrasses and sponges that were not mentioned in Petitioner's resource surveys. Depending on the lot, the Project would fill approximately 6,000 square feet of wetlands and other surface waters, i.e., 900 to 2,500 square feet of mangrove habitat and 4,000 to 4,800 square feet of marine seagrass bed habitat. The seawalls depicted in the final version of Petitioner's site plans were "vertical seawalls" because the rip-rap would not face the seawalls to the mean high water line (MHWL). The rip-rap would be placed on submerged resources inside the property lines of the Subject Lots. Also, Petitioner's final plans did not include the mooring of vessels. Vertical seawalls are prohibited in the OFW of the County. Petitioner did not affirmatively demonstrate that fill or shoreline stabilization could be accomplished by using native vegetation instead of vertical seawalls. Secondary Impacts DEP's expert witness, Ms. Mills, testified that Petitioner's ERP applications did not identify any potential secondary impacts. Ms. Mills testified that the expected secondary impacts from the Project included stormwater runoff, shading, and erosion or shoaling. Although the Project plans showed that stormwater would be collected and directed to Floral Avenue, DEP's investigation established that there is no stormwater management system on the side of Floral Avenue abutting the Subject Lots. Thus, the collected and directed stormwater would end up flowing back into the mangrove fringe and surface waters at the lot locations that were not proposed for development, e.g., Lots 36 and 38. The proposed single-family homes are piling-supported structures. Ms. Mills testified that the piling-supported structure would cause shading of the immediate adjacent resources on either side. She identified potential shading impacts to the resources of the undeveloped Lots 36 and 38. In addition, Ms. Mills identified potential erosion or shoaling impacts to the undeveloped Lots 36, 38, and unnamed lots to the left of Lot 40 since they would be surrounded by developed fill on either side. Although Mr. Swakon testified that tidal velocity is low in this area, other aspects, such as effects from wind-driven circulation, were not adequately addressed. Mitigation Petitioner was required to propose mitigation to offset remaining direct and secondary impacts after going through a reduction and elimination exercise. However, Petitioner did not propose any revisions to the Project to reduce or eliminate the direct and secondary impacts identified above. Ms. Mills explained that appropriate mitigation usually provides benefits to the same type of ecological community as the one being impacted. Petitioner's ultimate mitigation proposal was to purchase saltwater credit at a mitigation bank, the Florida Power and Light Everglades Mitigation Bank (FPL EMB). The FPL EMB is located on the mainland of Florida approximately a hundred miles away from the Subject Lots. Ms. Mills testified that saltwater credit would be appropriate to offset and replace the same ecological function of mangroves, but not to offset the submerged benthic communities that would be impacted by the Project. Mr. Swakon testified that calculation of the amount of mitigation credits included a multiplier to address secondary and cumulative impacts, the out-of-kind mitigation, and the dissimilarities in the communities. However, Ms. Mills persuasively testified that the proposed multiplier was not sufficient to justify the three aspects of impact that needed to be offset. Whether to justify dissimilarities between the ecological communities, secondary and cumulative impacts, or the distance of the mitigation site from the Project, the multiplier was not sufficient. Cumulative Impacts The Project is not within a recognized cumulative impact basin of the South Florida Water Management District (SFWMD) for mitigation of impacts purposes. Accordingly, Ms. Mills testified that the plain language of a cumulative impacts analysis is considered. Contiguous lots to the Subject Lots owned by Petitioner could be developed through similar requests in the future. Also, each ERP application's cumulative impact analysis would consider the other four ERP applications as in-house examples of potential future projects. Common Plan of Development Petitioner contested DEP's conclusion that the Project was a common plan of development subject to section 2.0 of the Applicant's Handbook Volume 1 and associated stormwater management requirements. The Project would facilitate the advancement of land uses such as multiple residences, a residential subdivision, or phased site development. The Project comprised a total land area divided into multiple lots or parcels that are under common ownership or control. In total, Petitioner owns 648 lots under common ownership within the Key Haven Tenth and Eleventh Addition. The Subject Lots are all part of a residential subdivision. Thus, the preponderance of the evidence demonstrated that the Project was a common plan of development. For this common plan of development, Petitioner's proposed stormwater management consisted of a cap on the proposed seawalls directing stormwater to swales on each lot. The swales would then direct stormwater to Floral Avenue with no additional treatment or management. During site inspections, DEP staff did not find any evidence of stormwater management along Floral Avenue. Seawalls and Rip-rap The seawalls depicted in the final version of Petitioner's ERP applications would be vertical seawalls because the rip-rap facing the seawall did not come above the MHWL. In addition, the final plans did not include the mooring of vessels. As found above, the Project would place fill, seawalls, and rip-rap on marine seagrasses and sponges. Petitioner failed to affirmatively demonstrate that native vegetation was not sufficient to prevent erosion. The evidence established that Petitioner did not apply for any waiver or variance of applicable ERP rule criteria. FCMP Consistency The evidence demonstrated that Petitioner refused to address DEO's objections based on a mistaken view of the criteria governing ERP applications in the County and the Florida Keys ACSC. Relevant to this proceeding, DEO exercises authority over the ACSC program. See § 380.05, Fla. Stat.; see also § 380.23(6), Fla. Stat. (Each agency charged with implementing statutes and rules that are part of the FCMP, shall be afforded an opportunity to provide DEP with its comments and determination regarding consistency of the activity with those statutes and rules.). Section 380.05(16) prohibits persons from undertaking any development within the Florida Keys ACSC, except in accordance with the PGDs. Thus DEO, as the administrator of the ACSC program, reviewed the ERP applications for consistency with applicable regulatory requirements. DEO issued objections to approval of the permits citing inconsistency with the Florida Keys ACSC PGDs; and inconsistencies between the Project and the County's Comp Plan and LDC which implement the PGDs. DEO identified that the Project would be inconsistent with four PGDs. DEO's expert witness, Ms. Powell, testified that the Project was inconsistent with the PGD, which provides for strengthening local government capabilities for managing land use and development so that the local government is able to achieve these objectives without continuing the ACSC designation. See § 380.0552(7)(a), Fla. Stat. Ms. Powell persuasively testified that the ERP applications were inconsistent with this PGD because the Project would impair the local government's ability to have the ACSC designation removed. Allowing development inconsistent with its regulations would hurt the local government's ability to pursue de-designation. No evidence was presented by Petitioner that the Project would be consistent with this PGD. The second PGD cited by DEO provides for protecting shoreline and marine resources, including mangroves, coral reef formations, seagrass beds, wetlands, fish and wildlife, and their habitat. See § 380.0552(7)(b), Fla. Stat. It was undisputed that the Project would result in total removal of the mangrove and buttonwood fringe on each lot and 100% destruction of existing submerged marine resources. No evidence was presented by Petitioner that the Project would be consistent with this PGD. The third PGD cited by DEO provides for limiting the adverse impacts of development on the quality of water throughout the Florida Keys. See § 380.0552(7)(e), Fla. Stat. Ms. Powell testified that degradation to nearshore water quality from prior dredge and fill activity was one of the reasons for the designation of the Florida Keys as an ACSC. Additionally, as further discussed below, the Project would be inconsistent with the County's Comp Plan policies and LDC regulations that further the goal of protecting the quality of water throughout the Florida Keys ACSC. No evidence was presented by Petitioner that the Project would be consistent with this PGD. The fourth PGD cited by DEO provides for protecting the public health, safety, and welfare of the citizens of the Florida Keys, and maintaining the Florida Keys as a unique Florida resource. See § 380.0552(7)(n), Fla. Stat. As further discussed below, the Project would be inconsistent with the County's Comp Plan and LDC regulations that prohibit the use of structural fill within velocity zones. No evidence was presented by Petitioner that the Project would be consistent with this PGD. Ms. Powell testified that DEO considered the remaining statutory PGDs, and determined they were not particularly applicable to these ERP applications. In accordance with its duties, DEO had also reviewed and approved the County's Comp Plan and LDC as consistent with the statutory PGDs. DEO identified that the Project would be inconsistent with seven Comp Plan policies. They are Policies 102.1.1, 101.5.25, 203.1.1, 204.2.2, 204.2.3, 204.2.4, and 212.5.3. Policy 102.1.1 provides: The County shall protect submerged lands and wetlands. The open space requirement shall be one hundred (100) percent of the following types of wetlands: submerged lands mangroves salt ponds fresh water wetlands fresh water ponds undisturbed salt marsh and buttonwood wetlands Allocated density (dwelling units per acre) shall be assigned to freshwater wetlands and undisturbed salt marsh and buttonwood wetlands only for use as transferable development rights (TDRs) away from these habitats. Submerged lands, salt ponds, freshwater ponds, and mangroves shall not be assigned any density or intensity. Policy 101.5.25 provides that "[t]he allocated densities for submerged lands, salt ponds, freshwater ponds, and mangroves shall be 0 and the maximum net density bonuses shall not be available." Policy 203.1.1 provides that "[t]he open space requirement for mangrove wetlands shall be one hundred (100) percent. No fill or structures shall be permitted in mangrove wetlands except for elevated, pile-supported walkways, docks, piers and utility pilings." Policy 204.2.2 provides: To protect submerged lands and wetlands, the open space requirement shall be 100 percent of the following types of wetlands: submerged lands; mangroves; salt ponds; freshwater wetlands; freshwater ponds; and undisturbed salt marsh and buttonwood wetlands. Allocated density (dwelling units per acre) shall be assigned to freshwater wetlands and undisturbed salt marsh and buttonwood wetland only for use as transferable development rights away from these habitats. Submerged lands, salt ponds, freshwater ponds and mangroves shall not be assigned any density or intensity. Within one (1) year after the adoption of the 2030 Comprehensive Plan, the County shall revise the LDC to include a prohibition of development in salt ponds. Policy 204.2.3 provides: No structures shall be permitted in submerged lands, mangroves, salt ponds, or wetlands, except for elevated, pile-supported walkways, docks, piers, and utility pilings. No fill shall be permitted in submerged lands, mangroves, salt ponds, or wetlands except: as specifically allowed by Objective 212.5 and subsequent Policies; to fill a manmade excavated water body, such as a canal, boat ramp, or swimming pool if the Director of Environmental Resources determines that such filling will not have a significant adverse impact on marine or wetland communities; or as needed for shoreline stabilization or beach renourishment projects with a valid public purpose that furthers the goals of the Monroe County Comprehensive Plan, as determined by the County. Policy 204.2.4 provides: No fill or structures shall be permitted in mangroves or wetlands except as allowed by Policy 204.2.3 (as amended) and for bridges extending over mangroves or wetlands that are required to provide automobile or pedestrian access to dwelling units located on upland areas within the same property for which there is no alternative means of access. Such bridges shall be elevated on pilings such that the natural movement of water, including volume, rate, and direction of flow shall not be disrupted or altered. Upland areas shall include disturbed wetlands that have been lawfully converted into uplands through filling. Policy 212.5.3 provides: Bulkheads, seawalls or other hardened vertical shoreline structures shall be permitted on residential canals and altered shorelines only in the following situations: to replace an existing deteriorated bulkhead or seawall; or to stabilize a severely eroding shoreline area. DEO's expert witness, Ms. Powell, persuasively testified that the Project was inconsistent with all seven policies, because it did not protect the submerged lands and wetlands, did not provide for 100% open space within the submerged lands and wetlands, and provided for the construction of a seawall not excepted from the general prohibition. Petitioner did not present any evidence that the Project was consistent with the cited policies. Instead, Petitioner's witness, Mr. Nelson, testified that he felt certain County regulations would militate in favor of allowing the development. The main factor cited by Mr. Nelson was that the Subject Lots were designated as Tier III parcels under the County's LDC. However, designation of a parcel as Tier III did not conflict with the policies cited by DEO. The more credible and persuasive evidence concerning the Project's compliance with the Comp Plan policies was provided by Ms. Powell, who concluded that the Project was not consistent with those policies. DEO identified that the Project would be inconsistent with six sections of the County's LDC regulations. Those are sections 118-4, 118-10(e), 118-12(k)(2), 122-4(b)(5), 130-157, and 130-162. The LDC regulations are more specific methods for implementing the Comp Plan policies outlined above. Section 118-4 provides: No development activities, except as provided for in this chapter, are permitted in submerged lands, mangroves, salt ponds, freshwater wetlands, freshwater ponds, or in undisturbed salt marsh and buttonwood wetlands; the open space requirement is 100 percent. Allocated density (dwelling units per acre) shall be assigned to freshwater wetlands and undisturbed salt marsh and buttonwood wetlands only for use as transferable development rights away from these habitats. Submerged lands, salt ponds, freshwater ponds and mangroves shall not be assigned any density or intensity. Section 118-10(e), in relevant part, provides: Mangroves, wetlands, and submerged lands. All structures developed, used or occupied on land classified as mangroves, wetlands or submerged lands (all types and all levels of quality) shall be designed, located and constructed such that: Generally. Only docks and docking facilities, boat ramps, walkways, water access walkways, water observation platforms, boat shelters, nonenclosed gazebos, riprap, seawalls, bulkheads, and utility pilings shall be permitted on or over mangroves, wetlands, and submerged lands, subject to the specific restrictions of this subsection. Trimming and/or removal of mangroves shall meet Florida Department of Environmental Protection requirements. * * * (4) Placement of fill. No fill shall be permitted in any mangroves, wetlands, or submerged lands except: As specifically allowed by this Section or by Section 118- 12(k) (Bulkheads, Seawalls, Riprap) and 118-12(l) (Boat Ramps); To fill a manmade, excavated water body such as a canal, boat ramp, boat slip, boat basin or swimming pool if the County Biologist determines that such filling will not have a significant adverse impact on marine or wetland communities; As needed for shoreline stabilization or beach renourishment projects with a valid public purpose that furthers the goals of the Monroe County Comprehensive Plan, as determined by the County Biologist; For bridges extending over salt marsh and/or buttonwood association wetlands that are required to provide automobile or pedestrian access to lawfully established dwelling units located on upland areas within the same property for which there is no alternate means of access. Such bridges shall be elevated on pilings so that the natural movement of water, including volume, rate and direction of flow shall not be disrupted or altered; or As approved for Disturbed Salt Marsh and Buttonwood Association Wetlands with appropriate mitigation as defined by the wetland regulations of subsection (e)(6) of this Section. Section 118-12(k)(2) provides: (2) Vertical type seawalls or bulkheads shall be permitted only to stabilize severely eroding shorelines and only on manmade canals, channels, or basins. Such seawalls or bulkheads shall be permitted only if native vegetation and/or riprap and filter cloth is not a feasible means to control erosion. No new seawalls, bulkheads, or other hardened vertical structures shall be permitted on open water. Section 122-4(b)(5), in relevant part, provides: Coastal high-hazard areas (V zones). Within the areas of special flood hazard are areas designated as coastal high- hazard areas, which have special flood hazards associated with wave wash. The following provisions shall apply in these areas: * * * e. There shall be no fill used as structural support. Section 130-157, Maximum Permanent Residential Density and Minimum Required Open Space, provides at note (a): (a) The allocated densities for submerged lands, salt ponds, freshwater ponds, and mangroves shall be 0 and the maximum net density bonuses shall not be available. Section 130-162, Maximum Densities for Hotel/Motel, Campground, Recreational Vehicle, Seasonal and Institutional Residential Uses, and Minimum Open Space, proves at note (a): (a) The allocated densities for submerged lands, salt ponds, freshwater ponds, and mangroves shall be 0 and the maximum net density bonuses shall not be available. Ms. Powell persuasively testified that the Project was not consistent with the County's LDC regulations in sections 118-4, 118-10(e), 118-12(k)(2), 122- 4(b)(5), 130-157, and 130-162. The Project was inconsistent with the cited LDC regulations because it sought to construct seawall in submerged land, fill portions of the lots subject to a 100% open space requirement, remove the entirety of the existing mangrove fringe, impair 100% of the marine seagrass resources within the Subject Lots, and utilize structural fill within a Federal Emergency Management Agency (FEMA) designated Velocity Zone. The preponderance of the evidence demonstrated that the Project did not meet the criteria of part IV of chapter 62-312 and section 380.0552. The testimony also demonstrated that Petitioner did not apply for a variance or waiver of the County's LDC regulations. Conditions for Issuance Petitioner generally argued that the five applications provided reasonable assurance for issuance of individual ERPs. However, the persuasive and credible evidence established that the Project did not satisfy a majority of the conditions for issuance under rule 62-330.301. Petitioner failed to provide adequate information regarding stormwater management, the impacts of runoff to Floral Avenue, and runoff flowing back into the Gulf of Mexico OFW. This failure resulted in a lack of reasonable assurance that the Project would not cause adverse flooding to on-site or off-site property; would not cause adverse water quantity impacts to receiving waters and adjacent lands; and would not adversely affect the quality of receiving waters. The preponderance of the evidence demonstrated that the Project would adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters. Those functions would be 100% impacted and the impacts would not be adequately offset by appropriate mitigation. As found above, the Project would cause adverse secondary impacts to the water resources, adverse impacts to surface water conveyance, and the adverse impacts would not be adequately offset by appropriate mitigation. Additional Conditions for Issuance Petitioner generally contended that the five applications provided reasonable assurance that the Project was clearly in the public interest under rule 62-330.302. However, the persuasive and credible evidence established that the Project did not satisfy a majority of the applicable additional conditions for issuance. The Project would adversely affect the public health, safety, or welfare or the property of others because Petitioner failed to provide adequate information regarding stormwater management. DEP's site inspection found no stormwater management or treatment system on the side of Floral Avenue adjacent to the Subject Lots. Thus, the collected and directed stormwater would end up flowing back into the mangrove fringe and the OFW. The preponderance of the evidence demonstrated that the Project would adversely affect the conservation of fish and wildlife, or their habitat, as a result of the 100% impact to benthic communities, which would not be adequately offset by appropriate mitigation. The preponderance of the evidence demonstrated that the Project would adversely affect marine productivity, the current condition, and the relative value of functions being performed by the impacted areas. Also, the Project would be permanent in nature. The preponderance of the evidence demonstrated that Petitioner failed to provide reasonable assurance that there would not be harmful erosion or shoaling. The Project would not adversely affect or enhance any significant historical and archaeological resources. The Project would not be within a recognized cumulative impact basin of the SFWMD for mitigation of impacts purposes. Contiguous lots to the Subject Lots owned by Petitioner could be developed through similar requests in the future. Each ERP application's cumulative impact analysis would consider the other four ERP applications as in-house examples of potential future projects. Thus, Petitioner did not provide reasonable assurance that each ERP application would not cause unacceptable cumulative impacts upon wetlands and other surface waters.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, RECOMMENDED that DEP enter a final order denying Petitioner's five ERP applications. DONE AND ENTERED this 14th day of April, 2021, in Tallahassee, Leon County, Florida. S FRANCINE M. FFOLKES Administrative Law Judge 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 14th day of April, 2021. COPIES FURNISHED: Kathryn E.D. Lewis, Esquire Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 Jay Patrick Reynolds, Esquire Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 William Moore, Esquire Moore Bowman & Reese, P.A. Suite 100 551 North Cattlemen Road Sarasota, Florida 34232 Justin G. Wolfe, General Counsel Department of Environmental Protection Legal Department, Suite 1051-J Mail Station 35 Douglas Building 3900 Commonwealth Boulevard Tallahassee, Florida 32399 Jon F. Morris, Esquire Brandon W. White, Esquire Department of Economic Opportunity 107 East Madison Street, Mail Station 110 Tallahassee, Florida 32399 Lea Crandall, Agency Clerk Department of Environmental Protection Douglas Building, Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 Noah Valenstein, Secretary Department of Environmental Protection Douglas Building 3900 Commonwealth Boulevard Tallahassee, Florida 32399 Valerie A. Wright, Esquire Department of Economic Opportunity 107 East Madison Street Tallahassee, Florida 32399
Findings Of Fact The Department of Environmental Protection (Department) is the administrative agency of the State of Florida which has the authority to administer and enforce the provisions of Chapter 403, Florida Statutes and the rules promulgated thereunder, Title 17, Florida Administrative Code, as well as other laws and rules related to protection of the environment. The Department is the successor agency to the former Department of Environmental Regulation and Department of Natural Resources. Respondent, Bob Chipman, owns and operates Fish Haven Lodge, One Fish Haven Road, Auburndale, Polk County, Florida. This subject property is located on the west shore of Lake Juliana in the Green Swamp Basin. Fish Haven Lodge is a small mobile home park and fishing camp, with approximately fifty mobile homes and seven cottages. There is a fishing pier built in the 1960's and a boat ramp; neither structure is at issue in this action. The lodge and camp were opened in 1963, some twenty years after Mr. Chipman's grandfather bought the property. Originally, the property sloped gently down to the shore of the lake. Mr. Chipman calls the lakefront a "parking lot for boats", as his patrons and tenants pull their boats up on the shore and "park" them. In the early days, poles were installed up on the shore for securing the boats. Over the years, the lake has eroded the shoreline. As people rented the mobile home lots and were given access to the lake, they would ask permission of Mr. Chipman to build little walkways to get in and out of their boats. These proliferated, and now there are at least twelve such structures. The property began experiencing severe erosion. Whenever it stormed, ruts were washed out, cutting into the grassy areas. Attempts to fill the ruts with dirt and sod provided only a temporary solution. Eventually, instead of a gradual slope, there was an abrupt drop into the lake waters. Mr. Chipman perceived this erosion as a hazard to his remaining property and to the people who used the lakefront. He also found it difficult to mow and maintain the neat, well-kept appearance of the property. In June 1992, Mr. Chipman, without benefit of permit of any sort, commenced building small sea walls, or what he calls "retention walls" on both sides of the fishing pier and along the contour of the shore. The walls are constructed of 2 x 10 wooden boards nailed on posts. The only way to hammer the boards on the landward side of the posts was to dig, then build, then backfill the area behind the walls. The fill came from both landward and waterward of the walls. Later, more fill was placed along the walls, but this was gravel fill. As the walls were built, the existing walkways, or small "docks" were removed and were replaced in a neater, more uniform fashion. The poles were repositioned and planks were replaced. There are approximately twelve of these repositioned walkways, or docks. Photographs taken by Mr. Chipman during the construction show the lakewaters approaching the planks of the wall, and in one view (Petitioner's exhibit #4) the water is lapping up to the planks. The walkways or docks are well into the water. Mr. Chipman concedes that the water has risen up the bottom 2 x 10 board, and that the walls were installed during a period of high water. Notwithstanding this evidence, Mr. Chipman contends that he built his walls along the edge, but not within, the jurisdiction of the "waters of the state". He contends that he was not trying to recapture property he lost to erosion, but rather, he was trying to save what he had left. He admits that the walkways or docks are in the water, but he suggests that they are "grandfathered", as they existed for several years, and some as long as twenty to thirty years. A basic principle of water boundary is that it is an ambulatory line; it moves with erosion or accretion. Erosion is a natural phenomenon. The Department established its jurisdictional water boundary in this case by several means. Ted Murray, an environmental specialist with the Department who was qualified at hearing without objection as an expert in jurisdictional determination, inspected the subject property and found submerged species of vegetation along the seawalls. These species included arrowhead and wild tarrow, common names for species which require the presence of water to grow. In an area where the seawalls were not built, wild tarrow was found four or five feet behind the line where the seawalls had been built, indicating that the water fluctuated naturally where unimpeded by the walls to an area landward of the walls. Two hydrological indicators of the landward extent of waters of the state were noted by Mr. Murray. One was the debris line or "rackline" created by the deposit of debris by fluctuating waterlevels. The other hydrological indicator was the escarpment found north of the boat dock. This escarpment is a miniature cliff, or drop-off caused by the high water line. This is a common situation found at lakeshores. In this case, Department staff located a post that already existed at the escarpment. At the request of the Department, the Southwest Florida Water Management District conducted a land survey, shooting elevations at various locations on the property. The existing post was a reference point agreed by the parties the day the survey was conducted; Mr. Chapman claimed that he had constructed his seawalls landward of that post. The elevation at the post and at the base of the escarpment was measured at 132.6 feet above sea level. At a lake like Lake Juliana, the water level will tend to be the same elevation all around the lake. Any structure or fill placed above 132.6 feet elevation would be in uplands; any structure or fill placed below that elevation would be within the landward extent of Lake Juliana, and therefore within the permitting jurisdiction of the Department. Survey elevations of the seawalls, taken at several points, indicate that the seawalls and fill were placed one to two feet below the jurisdictional line. The fact that the Southwest Water Management District had previously established feet as the minimum flood level for Lake Juliana adds credence to the line established as described above. There have been several enforcement actions on Lake Juliana, including three or four recent violations involving seawalls and associated backfill in jurisdictional waters. Mr. Chipman's is not an isolated case. As he recounts, folks saw him building this wall and told him they would like the same thing. The cumulative effect of such structures on the Lake Juliana environment is substantial. Seawalls preclude vegetative shorelines that would otherwise serve as nutrient assimilation and habitat for a variety of organisms that inhabit the lake. Even though Mr. Chipman's walls are only a foot or so into the wetlands, the surface area affected by the approximate 126 feet length of the walls is close to 500 square feet, including the fill area behind the walls. Loss of vegetation will lead to loss of fishes that depend on the vegetation for feeding, hiding and nesting. Although the docks or walkways can provide nesting or hiding places, their effect is still a net loss, since, as constructed, they deprive the vegetation of needed sunlight. As constructed, the seawalls would not have been permitted by the Department because the same purpose could have been served by building the walls in the uplands just a few feet away. The Department staff have discussed alternatives with Mr. Chipman. The best natural defense against erosion is a gentle slope that is vegetated with native plant species. That solution may not be practical where there is an embankment and where there is constant usage by boats and people. The most practical solution based on evidence in this proceeding is for Mr. Chipman to move the walls back into the uplands and restore the shoreline. There is no controversy that all of the construction by Mr. Chipman was done without permits. His business has been operating since 1963, and he felt that the effort to impede erosion of his "boat parking lot" was of no concern to the state. He has been candid and cooperative with the Department staff, and there is no basis to find that his excuse for not seeking permits is in any way bad faith.
Recommendation Based on the foregoing, it is, hereby, RECOMMENDED: That the Department enter its Final Order finding that Respondent, Bob Chipman, committed the violations alleged and requiring the removal and restoration described in the notice of violation and orders for corrective actions which initiated this proceeding. DONE AND RECOMMENDED this 29th day of November, 1994, in Tallahassee, Leon County, Florida. MARY CLARK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of November, 1994. COPIES FURNISHED: Virginia B. Wetherell, Secretary Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Kenneth Plante, Esquire General Counsel Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-2400 David Thulman, Esquire Heidi E. Davis, Esquire Asst. General Counsel DEP-Twin Towers Ofc. Bldg. 2600 Blair Stone Road Tallahassee, FL 32399-2400 Bob Chipman Fish Haven Lodge One Fish Haven Road Auburndale, FL 33823
The Issue The issue is whether an Environmental Resource Permit (ERP) and a Letter of Consent to Use Sovereignty Submerged Lands (Letter of Consent) should be issued to Respondent, Palm Beach County (County), authorizing it to fill 7.97 acres of submerged lands for a restoration project in Lake Worth Lagoon.
Findings Of Fact Based upon all of the evidence, the following findings are determined: The Parties Trump is the owner association for a two-towered residential and commercial condominium building located at 525 South Flagler Drive in downtown West Palm Beach, upland and west of the project site in the Lagoon. Each tower rises thirty floors and together they have of two hundred twenty units. The first five floors are common areas including a lobby on the first floor, while a pool and patio are located on the fifth floor of the north tower. The property is separated from the Lagoon by Flagler Drive, a four-lane divided road with landscaping and sidewalks which runs adjacent to, and on the western side of, the Lagoon. There is no dispute that Trump has standing to initiate this action. Flagler owns, manages, and leases two multi-story office buildings located at 501 Flagler Drive on the upland real property directly west of the project location. Like the Trump property, the Flagler property is separated from the Lagoon by Flagler Drive. There is no dispute that Flagler has standing to participate in this matter. The County is a political subdivision of the State and is the applicant in this proceeding. The Department is the state agency with the authority under Part IV, Chapter 373, Florida Statutes,2 to issue to the County an ERP for the project, as well as authority as staff to the Board of Trustees of the Internal Improvement Trust Fund (Board of Trustees) to authorize activities on sovereign submerged lands pursuant to Chapter 253, Florida Statutes, and Chapter 18-21. Background On October 29, 2007, the County submitted to the Department its Joint Application for an ERP and Letter of Consent to use sovereignty submerged lands in the Lagoon owned by the Board of Trustees. The application was assigned File No. 50- 0283929-00. After an extensive review process, including three requests for additional information, on August 12, 2008, the Department issued its Notice of Intent authorizing the County to fill 7.97 acres of submerged lands in the Lagoon with approximately 172,931 cubic yards of sand and rock material to create the following: (a) approximately 1.75 acres of red mangrove habitat including 1.52 acres of mangrove islands and 0.23 acres of red mangrove planters; (b) approximately 0.22 acres of cordgrass habitat; (c) approximately 0.90 acres of oyster habitat; (d) approximately 3.44 acres of submerged aquatic vegetation habitat; and (e) a 10-foot by 556-foot (5,560 square feet) public boardwalk with two 3-foot by 16-foot (48 square feet) educational kiosk areas and a 16-foot by 16-foot (256 square feet) observation deck for a total square footage of approximately 5,912 square feet. The Notice of Intent also included a number of general and specific conditions particular to this project. Trump (by timely Petition) and Flagler (by intervention) then challenged the Notice of Intent. They contend generally that the project unreasonably infringes upon or restricts their riparian rights and fails to meet the permitting and consent to use criteria set forth in Chapters 18-21 and 40E-4, as well as Chapter 373, Florida Statutes, and Section 253.141, Florida Statutes. Conflicting evidence on these issues was presented at the hearing. The conflicts have been resolved in favor of the County and the Department, who presented the more persuasive evidence. The Project The project area is a cove in the Lagoon, a Class III water body which extends within the County from North Palm Beach to Manalapan. The western side of the water body in the project area is lined with a vertical concrete seawall approximately 6.64 feet above the mean low water line. The waters immediately adjacent to the Trump and Flagler upland property are generally two to five feet deep along the seawall. To the east lies the island of Palm Beach, to the south is the Royal Park Bridge, which connects West Palm Beach and the Town of Palm Beach, while to the north is the Flagler Memorial drawbridge. The Lagoon is approximately 2,000 feet from shore to shore. The Intracoastal Waterway (ICW) runs roughly through the middle of the Lagoon in a north-south direction. Currently, there is an artificial dredge hole in the project area around four hundred feet from the western seawall. The dredge hole, which descends to approximately twenty feet at its deepest location, is filled with muck, which can be re- suspended by wave energy into the water, blocking the sunlight necessary for the support of biotic life. The muck covers the natural hard bottom, consumes oxygen, and presents an unsuitable environment for benthic organisms. The dredge hole is too deep to support seagrasses. The project calls for filling the dredge hole to intertidal elevations, i.e., between the high and low tide elevations, for mangroves and elevations suitable for seagrass. In all, approximately 173,000 cubic yards of fill will be placed in and around the hole to build up three separate islands within the project footprint, on which the County will plant 10,000 red mangroves, which naturally grow between fifteen and twenty-five feet in height. (The County estimates that eighty to ninety percent of the mangroves will survive and grow to a height of at least fifteen feet.) The top of the islands, not including mangroves, will be just below the mean high water mark. The County also proposes locating planters along the seawall and oyster reefs along the southern end of the project. The planters are designed to extend out approximately twenty feet from the seawall and will be placed on sovereign submerged lands. The last five feet will consist of limestone rock. Mangrove, spartina, and seagrass habitats will provide a biodiverse source of food and habitat for other species, and occurs naturally within the Lagoon but has been lost over time. Oyster habitat is proposed for additional bio-diversity and to provide a natural water filtration function. From the County's perspective, the restoration project would be incomplete without all the habitats proposed. The planters will be at an intertidal elevation, planted with red mangroves and spartina, and faced with rock to reduce wave energy in the area. The oyster reefs are rock structures designed to rise one foot above mean high water line for visibility to boaters. The project also includes a boardwalk and attached educational kiosks on the south side of the project to bring the public in contact with the habitats. The County will maintain the boardwalk, empty the trash daily, and open/close the gates at sunrise/sunset. The County proposes a minimum ten-foot buffer between seagrass beds and the fill area. The project is part of the County's Lagoon Management Plan, which outlines the County's restoration goals within the Lagoon. The County has performed numerous other restoration projects within the Lagoon to re-introduce mangrove and seagrass habitat, such as Snook Island, which consisted of filling a 100- acre dredge hole, installing mangrove islands, seagrass flats, and oyster reefs. The Snook Island project restored mangrove habitat and recruited fish and bird species, including endangered and threatened species. Snook Island has remained stable, with no sediment deposition or erosion. The County intends to fill the dredge hole with native lagoon bottom sediment. A clam-shell machine will deposit the sediment below the water line to reduce turbidity. Sediment will be placed around the edges of the dredge hole, reducing the velocity of the fill as it settles to the bottom and encapsulates the muck, as required by Draft Permit Special Condition No. 19. The County will use turbidity curtains, monitor conditions hourly, and stop work if turbidity levels rise beyond acceptable standards. These precautions are included in Draft Permit Conditions 12, 13, and 14. The County will use construction barges with a four- foot draft to avoid propeller dredge or rutting and will place buoys along the project boundary to guide the construction barges, precautions integrated into the Draft Permit conditions. The County's vendor contracts require maintenance of construction equipment to prevent leakage. A similar condition is found in the Draft Permit. Both the intertidal and seagrass flats elevations at the top of the islands will be built at a 4:1 slope; elevations subject to wind and wave energy will be reinforced with a rock revetment constructed of filter cloth and rock boulders. Seagrass elevations will have no reinforcing rock because they are deep enough to avoid significant currents. Proposed drawings were signed and sealed by a professional engineer. The ERP Criteria To secure regulatory approval for an ERP, an applicant must satisfy the conditions in current Rules 40E-4.301 and 40E- 4.302. The first rule focuses primarily on water quantity, environmental impacts, and water quality. The latter rule requires that a public interest balancing test be made, and that cumulative impacts, if any, be considered. Also, the BOR, which implements the rule criteria, must be taken into account. a. Rule 40E-4.301 21. Paragraphs (1)(a), (1)(b), (1)(c), (1)(g), (1)(h), and (1)(k) and subsections (2) and (3) of the rule do not apply. Although Trump and Flagler have focused primarily on paragraphs (1)(d), (f), and (i) in their joint Proposed Recommended Order, all remaining criteria will be addressed. Paragraph (1)(d) requires that an applicant give reasonable assurance that the proposed activity "will not adversely affect the value of the functions provided to fish and wildlife and listed species by wetlands and other surface waters." Based on the project design, the filling of the dredge hole and capping of muck, the restoration of seagrass habitat, and the creation of mangrove habitat, the project will have no adverse impacts but rather will be beneficial to the value of functions for fish and wildlife. Paragraph (1)(e) requires that an applicant give reasonable assurance that the proposed activity will not adversely affect the quality of receiving waters. The County will be required to manage turbidity that may be generated from the project. In part, the turbidity will be contained by the proposed construction method for filling the dredge hole. As noted earlier, the native sand will be deposited using a clamshell-type arm to dump the sand under the water around the periphery of the edge of the downward slope of the dredge hole. This will continue around the periphery of the hole, building up a lip and letting it slide down towards the bottom of the hole, squeezing the muck into the center of the hole and beginning to encapsulate it. Once there are several feet of native sand over the muck to encapsulate it, the County will resume the filling at the target rate. Subsection 4.2.4.1 of the BOR requires that the County address stabilizing newly created slopes of surfaces. To satisfy this requirement, the County will place the fill at a 4:1 slope. The outer edge of the mangrove islands slope back to a 4:1 slope and use rock rip-rap to stabilize that slope. Also, filter cloth, bedding stones, and boulders will be used. Because water currents slow near the bottom, the 4:1 slope for the seagrass elevations on the bottom will not de-stabilize. There will be turbidity curtains around the project area. Those are floating tops and weighted bottoms that reach to the bottom and are intended to contain any turbidity that may be generated by the project. Specific Conditions 12, 13, and 14 require extensive monitoring of turbidity. The County proposes to use a barge with a draft no greater than four feet. This aspect of the project will require a pre-construction meeting and extensive monitoring throughout the project. As a part of the application review, the County performed a hydrographic analysis which was coordinated with and reviewed by the Department staff. There are no expected debris or siltation concerns as a result of the project. The more persuasive evidence supports a finding that over the long term, the project is expected to have a beneficial effect on water quality. By filling the dredge hole and providing habitat for seagrass, mangroves, and oysters, the project will provide net improvement to water quality. The requirements of the rule have been met. Paragraph (1)(f) requires that the applicant provide reasonable assurance that the activities will not "cause secondary impacts to the water resources." More detailed criteria for consideration are found in BOR Subsection 4.2.7. The County has provided reasonable assurance that through best management practices, it will control turbidity. Also, Specific Conditions in the proposed permit require that water quality monitoring be conducted throughout the process. There will be no impacts to upland habitat for aquatic or wetland dependent species. This is because a vertical seawall is located upland of the project site, and no surrounding uplands are available for nesting or denning by aquatic or wetland dependent listed species. A secondary impact evaluation also includes an evaluation of any related activities that might impact historical and archaeological resources. There are, however, no historical or archaeological resources in the area. If resources are uncovered during the project, Draft Permit conditions require notification to the Department of State. Finally, there are no anticipated future activities or future phases on the project to be considered. Rule 40E-4.301(1)(i) requires that the applicant provide reasonable assurance that the project "will be capable, based on generally accepted engineering and scientific principles, of being performed and of functioning as proposed." Trump and Flagler contend that the project cannot be constructed and successfully operated as proposed. Trump's expert witness, Joseph Pike, testified that there were ambiguities and conflicts within the plan drawings that would require changes upon build-out; either fill will be placed outside of the fill area, or the mangrove islands will be smaller than depicted. Mr. Pike also voiced concerns that a 4:1 slope would not be stable and might cause fill to migrate to existing seagrass beds. He further stated that the Snook Island project included 18:1 slopes, and he thought providing rock revetment only at the intertidal zone was insufficient. Mr. Pike acknowledged that he had used 4:1 slopes in lake projects; however, in a tidal project involving fill placement, he opined that a 4:1 slope was likely to "relax." He did not do calculations about what slope might hold and admitted that prior experience using similar slopes with the same type of fill might change his opinion. Finally, Mr. Pike noted that a portion of the dredge hole would not be filled and concluded that the project would not fully cap the muck. Trump's biologist, James Goldasitch, speculated that the water flow changes would cause sediment deposition on existing seagrass beds, possibly causing the seagrasses to die. He admitted, however, that the County's plans called for the creation of 3.44 acres of seagrass and did not know the amount of habitat created compared to the amount of habitat he anticipated being affected. The Department's engineer, Jack Wu, approved the hydrologic aspects of the County's plan, but Mr. Goldasitch speculated that Mr. Wu was more focused on shoreline stability than on depositional forces. Mr. Goldasitch never actually spoke to Mr. Wu regarding his analysis, and Mr. Wu's memorandum refers not only to engineering and construction aspects of the proposal but also to the criteria in Rules 40E-4.301 and 40E-4.302. Mr. Goldasitch believed the County's boardwalk will impact the seagrass beds by blocking sunlight, but acknowledged that the Draft Permit required the boardwalk to be elevated and portions to be grated. Both the Florida Fish and Wildlife Conservation Commission and the Department's expert witness concluded that the permit conditions for constructing the boardwalk, which are common, eliminated impacts to seagrass. Mr. Goldasitch further opined that the 4:1 slope might slump, but then deferred to the opinion of a registered engineer on this type of engineering matter. The County presented its professional engineer, Clint Thomas, who worked on the project design. Mr. Thomas explained that permit drawings are not intended to be construction-level in detail, but are merely intended to provide sufficient detail for the regulator to understand the project within the 8 and 1/2 by 11-inch paper format required by the Department. The County will ultimately prepare permit-level, construction-level, and as-built drawings. Permit conditions also require a pre-construction meeting. No fill will be placed outside the area designated for fill, and the 4:1 slope will start at the outer boundary of the designated fill area until it reaches the specified elevation. Mr. Thomas acknowledged that the plan view drawings depict a mangrove island too close to the western project boundary, but stated that the mangrove island would simply be placed farther to the east during the construction-level plan process. Islands will become smaller islands, but will not be relocated, and in no event will the fill area expand; the fill boundary is a very strict limit. There is no evidence that the County has ever violated a fill boundary established in a permit. The 4:1 slope was based on the type of fill proposed for the project and to maximize project features. Mr. Thomas has successfully used 4:1 slopes with non-compacted fill in the Lagoon, both at Snook Island in its as-built state and at other projects. The islands at Snook Island are similar to those proposed. Other areas in the Lagoon have held slopes steeper than 4:1 with the same type of fill. Therefore, Mr. Thomas opined the 4:1 slope would hold. In rendering this opinion, he explained that the currents in the project vicinity are only around 1.2 knots. Because currents slow near the bottom, the 4:1 slope for the seagrass elevations on the bottom will not de- stabilize. Mr. Thomas addressed the contention that a change in water flow velocity would cause sediment to deposit on existing seagrass. The oyster reefs are rubble structures that allow the water to flow through. If any sediment flows through, it will deposit on the north side of the oyster bar, rather than on the seagrass beds. Given these considerations, the evidence supports a finding that the project will function as proposed. Finally, paragraph (1)(j) requires that the County provide reasonable assurance that it has the financial, legal, and administrative capability to ensure that the activity will be undertaken in accordance with the terms and conditions of the permit. The evidence supports a finding that the County has complied with this requirement. In summary, the evidence supports a finding that the County has given reasonable assurance that the project satisfies the criteria in Rule 40E-4.301. b. Rule 40E-4.302 In addition to the conditions of Rule 40E-4.301, the County must provide reasonable assurance that the construction of the proposed project will not be contrary to the public interest. See Fla. Admin. Code R. 40E-4.302(1)(a)1.-7. Rule 40E-4.302(1)(a)1. requires that the Department consider whether the activity will adversely affect the public health, safety, or welfare or the property of others. Trump first contends that the project will increase the mosquito population. The evidence shows, however, that the mangroves will be placed below the mean high water mark and therefore no increase in mosquitoes should occur. Also, the design of the project, coupled with the local mosquito control program, should ensure that there will be no increase in mosquito population or a risk to the public health. Trump also raised the issue of an increase in trash along the boardwalk area or in the newly-created mangrove islands. The County presented evidence that there will be appropriate trash receptacles in the area as well as regular garbage collection. In terms of safety, navigation markers are included as a part of the project for safe boating by the public. The County consulted with the United States Coast Guard regarding navigation issues. Further, the project will not cause flooding on the property of others or cause an environmental impact on other property. Although a number of Trump residents expressed sincere and well-intended concerns about the project impacting the value of their condominiums (mainly due to a loss of view), BOR Subsection 4.2.3.1(d) provides that the "[Department] will not consider impacts to property values or taxes." Rule 40E-4.302(1)(a)2. requires that the Department consider whether the activity will adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats. Subparagraph 4. of the same rule requires that the Department consider whether the activity will adversely affect the fishing or recreational value or marine productivity in the vicinity of the activity. The proposed activity is a restoration project for the creation of seagrass and mangrove habitats. As such, it is beneficial to the conservation of fish and wildlife and is expected to increase the biotic life in the project area. Besides providing additional habitat for fish and wildlife, the project will add to the marine productivity in the area. In terms of recreational opportunities, the project is expected to be a destination for boating, kayaking, fishing, and birdwatching. The Florida Fish and Wildlife Conservation Commission has also recommended issuance of the permit with the standard manatee condition for in-water work. This recommendation has been incorporated as Specific Conditions 23 through 25 Rule 40E-4.301(1)(a)3. requires that the Department consider whether the activity will adversely affect navigation and the flow of water, or cause harmful erosion or shoaling. The nearest navigation channel is the ICW. The project is located outside of that area. Subsection 4.2.3.3 of the BOR provides additional guidance on the evaluation of impacts of this nature. Paragraph (a) of that subsection provides that, in evaluating a proposed activity, the Department "will consider the current navigational uses of the surface waters and will not speculate on uses which may occur in the future." Trump residents indicated that in the project area persons are now picked up off the seawall and then travel to the ICW. Access to the seawall is possible from the east and south, although existing shoals currently limit the approach from the south. Large boats do not use the area because of shoals. In general, "[t]here's not a whole lot of boating activity in the project area." The parties agree that if the project is constructed as designed, boats will not be able to travel directly out from the seawall in front on Trump or Flagler to the ICW, as they now do. However, navigation in the area will still be available, although not as convenient as before. As to water flow, shoaling, and erosion, the more persuasive evidence supports a finding that the 4:1 slope will be stable and will not cause fill to migrate outside of the boundaries of the project into existing seagrass beds. The tidal flow will continue through the area after construction without sediment deposition into existing seagrass beds or destabilizing the 4:1 slope. There will be no shoaling or erosion. Finally, the project will be permanent and there are no significant historical and archaeological resources in the area. See Fla. Admin. Code R. 40E-4.302(1)(a)5. and 6. In summary, the evidence supports a finding that the County's proposal is neutral as to whether the activity will adversely affect the public health, safety, welfare, or the property of others; that the County's proposal is neutral with respect to navigation, erosion and shoaling, and water flow, as well as to historical and archaeological concerns; and that the County's proposal is positive with respect to the conservation of fish and wildlife, recreational values and marine productivity, permanency, and current values and functions. When these factors are weighed and balanced, the project is not contrary to the public interest and qualifies for an ERP. D. Proprietary Authorization Chapter 18-21 applies to requests for authorization to use sovereign submerged lands. The management policies, standards, and criteria used to determine whether to approve or deny a request are found in Rule 18-21.004. In making its review, the Department reviews the rule in its entirety; it also looks at the forms of authorization (e.g., letters of consent, leases, deeds, or easement) to determine the most appropriate form of authorization for an activity. Trump and Flagler have raised contentions regarding the proprietary authorization, including whether the application should have been treated as one of heightened public concern, whether the proper form of authorization has been used, and whether their riparian rights are unreasonably infringed upon by the project. Heightened Public Concern Rule 18-21.0051 provides for the delegation of review and decision-making authority to the Department for the use of sovereign submerged lands, with the following exception found in subsection (4) of the rule: (4) The delegations set forth in subsection (2) are not applicable to a specific application for a request to use sovereign submerged lands under Chapter 253 or 258, F.S., where one or more members of the Board, the Department, or the appropriate water management district determines that such application is reasonably expected to result in a heightened public concern, because of its potential effect on the environment, natural resources, or controversial nature or location. On March 13, 2008, the Department's West Palm Beach District Office sent a "heightened public concern [HPC]) memo" to the Department's review panel in Tallahassee,3 seeking guidance as to whether the project required review by the Board of Trustees under the above-cited rule. The Department emailed the County on March 14, 2008, stating that the project would be elevated to the Board of Trustees for review to approve the entire Lagoon Management Plan. The County asked for reconsideration, concerned over timing restraints on grant opportunities. This concern is based on the fact that the County will receive grant monies to assist in the construction of the project and must have regulatory approval by a date certain in order to secure those funds. A second HPC memorandum was sent to the review panel on April 22, 2008. Part of the interim decision to elevate the application to the Board of Trustees concerned the boardwalk connection to the City of West Palm Beach's existing seawall. The City of West Palm Beach is the upland owner of the seawall, sidewalk, and Flagler Drive. On June 9, 2008, the Mayor of West Palm Beach sent a letter to the Department stating that the City "fully supports" the proposed activity, and that the County and the City collaborated on the design of the project, held joint public meetings, and produced a project video. See Department Exhibit Trump and Flagler argue that under the City Charter, the Mayor cannot unilaterally bind the local government to allow structures to be built on City property. Assuming this is true, one of the remaining conditions for the County to initiate the project is to obtain a "letter of concurrence" from the City of West Palm Beach authorizing the County to connect the boardwalk to the seawall. Therefore, the review panel ultimately concluded that the application could be reviewed at the staff level and did not require Board of Trustees review. The evidence at hearing did not establish that the application was one of heightened public concern, given the limited size of the project, its location, and the net benefit to both environmental and natural resources. Compare Brown, et al. v. South Fla. Water Mgmt. Dist., et al., DOAH Case No. 04-0476, 2004 Fla. ENV LEXIS 112 (DOAH Aug. 2, 2004, SFWMD Sept. 8, 2004). Therefore, review by the Board of Trustees was not required. Form of Authorization Trump and Flagler contend that an easement is required by the County, rather than a consent of use. The standard for obtaining an easement is more stringent than a consent of use, and an easement offers a greater interest in sovereign lands. Rule 18-21.005(1) provides the general policy direction for determining the appropriate form of authorization and reads in relevant part as follows: It is the intent of the Board that the form of authorization shall grant the least amount of interest in the sovereignty submerged lands necessary for the activity. For activities not specifically listed, the Board will consider the extent of interest needed and the nature of the proposed activity to determine which form of authorization is appropriate. This rule requires that the Department should apply the lowest and least restrictive form of authorization. Trump and Flagler argue that the County's project constitutes a spoil disposal site under Rule 18-21.005(1)(f)8., a public water management project other than public channels under Rule 18-21.005(1)(f)10., or a management activity which includes "permanent preemption by structures or exclusion of the general public," as described in Rule 18-21.005(1)(f)11. Each of these activities requires an easement rather than a letter of consent in order to use sovereign submerged lands. The evidence shows that the County's project is not a spoil disposal site. Also, it is not primarily a public water management project as there is no evidence that the project relates in any way to flood control, water storage or supply, or conservation of water. Likewise, there is no evidence indicating that the activities will prevent access by the public by exclusion. Even though many of the features (structures) of the project will be permanent, the project is intended to generally increase public access to water resources, as well as the islands, boardwalk, and kiosks. Besides raising the issue of heightened public concern, the second HPC Memorandum dated April 22, 2008, sought guidance as to whether the project required a consent of use or an easement. The review panel concluded that the project qualified for a consent of use, rather than an easement under Rule 18- 21.005(1)(f), because the County's project most closely fits the definition in Rule 18-21.005(1)(c)15. That rule provides that if the proposed activity involves "[h]abitat restoration, enhancement, or permitted mitigation activities without permanent preemption by structures or exclusion of the general public," an applicant may use sovereign submerged lands with a consent of use. Because the County's project increases public access not only to water resources in the Lagoon but also to the permanent structures being built, it more closely falls within the type of activity described in Rule 18-21.005(1)(c)15. Notably, all of the County's restoration projects in the Lagoon have been previously authorized through a consent of use. Finally, the review panel concluded that the project did not fall under Rule 18-21.005(1)(f)16., which requires an easement for environmental management activities that include "permanent preemption by structures or exclusion of the general public" because of the rule's focus on the exclusion of the general public. Riparian Rights The parties have stipulated, for the purpose of this proceeding, that Trump and Flagler have riparian rights, including view, ingress/egress, fishing, boating, swimming, and the qualified right to apply for a dock, that should be considered. Trump and Flagler contend that their right to wharf out (build a dock) from the seawall, ingress/egress from navigable water, and view will be unreasonably infringed upon if the application is approved. See Fla. Admin. Code R. 18- 21.004(3)(a)("[n]one of the provisions of this rule shall be implemented in a manner that would unreasonably infringe upon the traditional, common law riparian rights, as defined in Section 253.141, F.S., of upland property owners adjacent to sovereignty submerged lands"). For the reasons given below, the greater weight of evidence establishes that none of these riparian rights will be unreasonably infringed upon. Currently, while access is possible from the east and the southern approaches, existing shoals limit the southern approach. The boardwalk will further limit boat traffic on the south end, and boats would not be able to cross over the islands. Boat traffic will still be able to access the cove from the north end, and the restoration project will create a boating destination. Trump witness Pike opined that the County's project would negatively affect navigation between the upland parcels and the ICW because the project would eliminate the eastern and southern approaches and leave only the northern approach, which could not be used by both parcels fully. The County's expert, Dr. Nicholas De Gennarro, testified that, during his site visits, he observed boat traffic waiting for the drawbridges using the east side of the ICW away from the project site. Dr. De Gennarro noted that several existing structures are closer to the ICW than the proposed County project, which lies 220 feet away from the ICW. Thus, Dr. De Gennarro concluded that the project would not impact navigation in the ICW. With respect to ingress/egress, Dr. De Gennarro acknowledged that access to the Trump and Flagler properties would not be available from the southern and eastern approaches, but concluded that the restriction represented nothing more than an inconvenience. He noted that the southern approach was already a less preferable approach due to existing shoals. At present, there is very little boating in the area outside of special events. While the project would limit the use of boats directly over the one and one-half acres of mangrove islands, the project will provide a boating destination. Further, both the City docks to the north of the site and the temporary docks in front of Flagler's property –- both used for special events –- will still be available under the County's proposal. There is no swimming and very little fishing in the area because of the degraded conditions caused by the dredge hole. Accordingly, while the project will fill a small portion of water currently available, but not used, for swimming, it will greatly enhance swimming by providing a destination for swimmers. The mangroves planned for the intertidal islands are likely to reach a height of fifteen feet and will be interspersed with spartina. The seawall is located six feet above the water line, making a person's view at eye level already several feet above the water. Trump and Flagler's buildings are built at even higher elevations. Therefore, the mangroves will not substantially obscure the view from either property, even at street level where the view is already partially obscured by existing landscaping. The Lagoon is approximately 2,000 feet across. From north to south around one hundred acres of water can now be viewed from the vicinity. Since the intertidal islands only comprise one and one-half acres, the overall impact to the view of the water body is very small. The mangroves in the planters extending out from the seawall will be trimmed to one foot above the seawall; the County requested the condition and committed at hearing to trimming the mangroves if the City of West Palm Beach does not. County photographs show Trump and Flagler's present view of the water body and demonstrate the comparatively small percentage of the view affected by the one and one-half acres of mangrove islands. See County Exhibits 133a-e and 134a-d. The photographs also demonstrated that sizeable palm trees are already part of the existing view. Additionally, the County photographs depicted the small impact that trimmed mangrove planters would have on the view. The area obstructed by the mangrove islands and seagrass is negligible compared to the expanse of the existing view. Trump and Flagler offered no evidence to contradict the County's analysis regarding the scope of the impact on the view. Trump residents Dale McNulty, Dean Goodman, and Charles Lemoine testified that they personally would not want to view mangrove islands regardless of tree size or the size of the islands. Understandably, after years of unfettered view and an open expanse of water, they are opposed to any type of project in this area of the Lagoon. However, Mr. Goodman acknowledged that he would still be able to see the Town of Palm Beach from his unit. The evidence supports a finding that while the project will undoubtedly alter the view of the water from both Trump and Flagler's property, the impact on view is not so significant as to constitute an unreasonable infringement of their riparian rights. Mr. Lemoine stated that he had a forty-foot trawler that he would like to dock in front of his property. He currently docks the boat at a marina twenty miles north of the Trump property. He prefers to bring his boat in stern first and enter slips oriented north to south. He indicated that he can drive his boat in five feet of water, but prefers six feet; however, he also testified that he has brought his boat directly up to the bulkhead in front of Trump, which is approximately a two- or three-foot depth. The witness has seen sailboats and other boats moored near the bulkhead over extended timeframes. Mr. Lemoine speculated that Trump might seek a dock, either alone or in conjunction with Flagler, but admitted that Trump has never applied for a dock permit. He stated that Trump has had discussions about the possibility of a dock over the last fifteen years and speculated that a dock plan might include anything from the purchase/lease of the City docks to a lease of Trump's riparian interests to a third party. By contrast, Trump resident and former Board member Dean Goodman indicated "the idea was to provide an amenity [for] a number of people that are in the building that are boaters." Mr. Goodman stated that he hoped to be able to have a boat in front of the building someday, but did not own a boat in Florida. Association president Dale McNulty explained that, while informal discussions have occurred regarding the possibility of a dock, no official action had been taken. Mr. McNulty characterized the dock plans as being "sort of in the land of wishful thinking." Mr. Pike, while acknowledging that both parcels would still be able to design a dock for their property, opined that the County's project unreasonably limited the size and configuration of the docks possible. Mr. Pike initially admitted that a safe navigation depth for a forty-foot boat, or even a sailboat, was four feet below mean low water (MLW), but stated that he would prefer to design a dock with an additional two-to- three feet of water below the four-foot draft to avoid propeller damage. However, Mr. Pike conceded that he has designed docks for boats in four feet below MLW and ultimately based his own calculations on an assumption of a four-foot draft and one-foot cushion, or five feet below MLW. Mr. Pike also opined that a north-south alignment for boat slips was a preferred slip orientation. Given the bathymetry in the area and the documented seagrasses, Mr. Pike estimated that twenty slips could be designed for the Flagler property, rather than the thirty-four slips provided for by the County Manatee Protection Plan. He thought that a design might accommodate thirty to thirty-two slips for Trump, rather than the forty-slips provided for by the County Manatee Protection Plan. Based on the limitation on number of slips and configurations, the witness opined that the County's project would unreasonably interfere with Trump and Flagler's ability to design a dock. He admitted, though, that the numbers derived from the County Manatee Protection Plan represent a maximum number, rather than a specified or guaranteed number. He further admitted that other agency limitations may further restrict Trump and Flagler's right to dockage. Without a permit application or plan from Trump or Flagler, County witness Robbins concluded that the most reasonable assumption was an owner-oriented facility designed for the building owners/tenants. The County introduced a graphic illustrating areas available for dock construction, with sufficient depth for 35- to 40-foot boats (-6 feet NGVD) and with no seagrasses present. Rule 18-21.004(4)(b)2. limits ownership-oriented facilities generally to forty square feet for each foot of riparian shoreline, giving Trump the ability to apply for a dock that preempted a maximum of 16,000 square feet, and Flagler a maximum of 14,000 square feet. Under the County Manatee Protection Plan, Trump would be limited to forty slips; Flagler would have the potential for thirty-four slips. Mr. Robbins testified that, in his experience, a minus five MLW is a common depth for docks, but that elevations as shallow as a minus four MLW could be used depending on the type of boats and the dock configuration. Mr. Robbins explained that, even with the County's project in place and factoring in the other limitations, Trump would still have 61,842 square feet of potential space within which to design a dock. Flagler would still have 41,481 square feet of potential space, even considering the need to retain a path for ingress and egress from the Trump parcel. A more detailed analysis of the seagrasses might make more square footage available for dock construction. Dr. De Gennarro also evaluated whether a dock could be designed to serve Trump and Flagler's parcels. The vessel owner statistics for the County indicate that at least ninety-five percent of the boats registered in the County are thirty-nine feet or less; consequently, Dr. De Gennarro focused on boats forty feet or less. Dr. De Gennarro considered the water depths and the existence of subaquatic vegetations and concluded that the graphic presented by Mr. Robbins was conservative, but still provided adequate space for both Trump and Flagler to construct appropriate dockage, allowing thirty-eight boats for Trump and thirty-two for Flagler of varying size. However, Dr. De Gennarro concluded that a dock design of forty slips for each would also be possible, depending on the size of the boats. Dr. De Gennarro proposed that a single, double-loaded parallel dock design would be a good layout for a potential docking facility in front of both Trump and Flagler's property that would be protected by the County's proposed islands, provide sufficient water depths, and provide an attractive facility. He specified, however, that the single, double-loaded parallel dock design was simply one of "many" that might work in the given space. Dr. De Gennarro explained that the existing dredge hole would not be a preferable location for either a mooring field or a dock because the deep muck-bottom would drive up the costs for either type of facility. Accordingly, Dr. De Gennarro concluded that the County's project would not foreclose or even substantially restrict the ability to locate a dock in front of Trump and Flagler’s property. The more persuasive evidence supports a finding that neither the right of ingress/egress nor the right to boat in the vicinity is unreasonably infringed upon by the County's project. Trump and Flagler will continue to have reasonable access to navigation. The northerly approach preserved by the County's project will allow for boat traffic to safely navigate in the area. While the southerly and easterly approaches are eliminated by the County's plan, the evidence indicates that the two approaches were less preferable than the northerly approach because of the presence of shoals. Based on the above considerations, the County's project will not unreasonably infringe upon Trump or Flagler's qualified right to a dock. The fact that the project might preclude the design and permitting of a dock that would host very large vessels does not mean that Trump and Flagler's rights regarding docking have been unreasonably infringed. The evidence shows that substantial docking facilities of multiple configurations are still possible even if the County's project is approved. In summary, the County's application for proprietary authorization should be approved. Other Contentions All other contentions raised by Trump and Flagler have been considered and are found to be without merit.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department enter a final order approving the County's application for a consolidated ERP and consent to use sovereignty submerged lands. DONE AND ENTERED this 24th day of September, 2009, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of September, 2009.
Findings Of Fact The Parties. The Petitioner, Clifford O. Hunter, is the owner of real property located at Dekle Beach, Taylor County, Florida. Mr. Hunter's property is located at lot 53, Front Street, Dekle Beach, within section 22, township 7 south, range 7 east, Taylor County. Respondent, the Florida Department of Environmental Protection (hereinafter referred to as the "Department"), is an agency of the State of Florida with responsibility for, among other things, dredge and fill permits involving Florida waters. Mr. Hunter lived in a home on his Dekle Beach property until a storm in March of 1993 destroyed the home. Mr. Hunter's Application for Permit. On or about June 2, 1993, Mr. Hunter applied for a wetland resource permit to rebuild his home, construct a bulkhead and fill 1750 square feet of salt marsh. The permit was designated No. 62-232123-2 by the Department. Mr. Hunter also sought approval for the construction of a dock. The dock, however, is exempt from the permitting requirements of Rule 17- 312.050(1)(d), Florida Administrative Code. On July 21, 1993, the Department issued a Notice of Permit Denial. The Notice of Permit Denial was received by Mr. Hunter. On August 13, 1993, Mr. Hunter filed a Request for Formal Administrative Hearing with the Department contesting the denial of his permit application. The Department's Jurisdiction Over the Proposed Project. The proposed project involves dredging and filling in the waters of the State of Florida. A wetland resource permit is, therefore, required. Wetland jurisdiction of the State of Florida extends to the eastern edge of an existing concrete slab on Mr. Hunter's property from a canal adjacent to Mr. Hunter's northern boundary. The canal connects with the waters of the Gulf of Mexico. The Gulf of Mexico surrounding Dekle Beach, except for an area extending 500 feet outward from the town limits of Dekle Beach, is within the Big Bend Seagrasses Aquatic Preserve. The preserve is an Outstanding Florida Water (hereinafter referred to as an "OFW"). The evidence presented by the Department to support findings of fact 9, 10 and 11 was uncontroverted by Mr. Hunter. Impact on Water Quality Standards. The weight of the evidence failed to prove that the Mr. Hunter has provided reasonable assurances that the proposed project will not lower the existing ambient water quality of waters of the State of Florida. The evidence presented by the Department concerning adverse impacts of the proposed project on water quality standards was uncontroverted by Mr. Hunter. Approval of Mr. Hunter's proposed project would allow the placing of fill in an intertidal area and the elimination of the portion of the intertidal area filled. Intertidal areas help maintain water quality by acting as a filter for water bodies. Mr. Hunter has obtained a variance from the Department of Health and Rehabilitative Services which will allow him to place a septic tank on his property if the permit is granted. The septic tank will leach pollutants. Those pollutants will include nutrients, viruses and bacteria. Because the soil around the septic tank is very saturated, filtering of the pollutants will be low. Pollutants will, therefore, leach into the waters of the State of Florida and adversely impact water quality standards of the canal adjacent to Mr. Hunter's property. Under such circumstances, Mr. Hunter has failed to demonstrate that the project will not lower existing ambient water quality of waters of the State of Florida. Public Interest Test. Mr. Hunter failed to present evidence to support a conclusion that the proposed project will not be adverse to the public interest. Rather, the unrebutted evidence presented by the Department supports a finding that Mr. Hunter's proposed project will not be in the public interest, especially when the cumulative impacts of the proposed project, discussed, infra, are considered. Possible adverse impacts to the public interest include the following: The septic tank which Mr. Hunter will place in the 1750 square feet of filled area will allow fecal coliform, viruses and pathogens to leach into the waters of the canal adjacent to Mr. Hunter's property. Anyone who enters the canal could be infected from bacteria and viruses leaching from the septic tank. The conservation of fish and wildlife would also be adversely affected by the adverse impact on water quality and by the elimination of intertidal area. Recreational value of the canal would be reduced because of the adverse impact on water quality. The proposed project is for a permanent structure. Cumulative Impact. There are a number of applications for permits similar to the application filed by Mr. Hunter which have been filed by property owners of Dekle Beach whose homes were also destroyed by the March 1993 storm. If Mr. Hunter's permit application is granted, the Department will have to also grant most, if not all, of the other similar permit applications. Approximately 20 to 30 other applications involve similar requests which will allow the placement of fill and the installation of septic tanks. The resulting fill and use of septic tanks will have a significant cumulative adverse impact on the waters of the State of Florida. The cumulative impact from leaching effluent from the septic tanks on the waters of the State could be substantial. In addition to the impact on the canal adjacent to Mr. Hunter's property, there will a cumulative negative impact on the ambient water quality of approximately 20 septic tanks on the canals and on the OFW. Errors in the Department's Notice of Permit Denial. The Notice of Permit Denial issued by the Department contained the following errors: An incorrect description of Mr. Hunter's lot number and section number; An incorrect statement that the amount of Mr. Hunter's proposed fill would eliminate 3,200 square feet of marsh; An incorrect statement that Mr. Hunter proposed to fill his lot for a distance of 64 feet waterward. The errors contained in the Notice of Permit Denial did not form any basis for the Department's denial of Mr. Hunter's application. The errors were typographical/word-processing errors. Several notices were being prepared at the same time as the Notice of Permit Denial pertaining to Mr. Hunter. The incorrect information contained in Mr. Hunter's Notice of Permit Denial was information which applied to the other notices. Other than the errors set out in finding of fact 23, the Notice of Permit Denial was accurate. Among other things, it was properly addressed to Mr. Hunter, it contained the project number assigned by the Department to Mr. Hunter's proposed project and it accurately reflected the Department's decision to deny Mr. Hunter's permit application. Mr. Hunter responded to the Notice of Permit Denial by requesting a formal administrative hearing to contest the Department's denial of his application. On December 20, 1993, Mr. Hunter received a letter from the Department which corrected the errors contained in the Notice of Permit Denial. The corrections were also contained in a Notice of Correction filed in this case by the Department on December 20, 1993. The Notice of Permit Denial was received by Mr. Hunter within 90 days after his application was filed. The corrections to the Notice of Permit Denial was received by Mr. Hunter more than 90 days after his application was filed.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a Final Order dismissing the petition in this case and denying the issuance of permit number 62-232123-2 to Clifford O. Hunter. DONE AND ENTERED this 26th day of April, 1994, in Tallahassee, Florida. LARRY J. SARTIN Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of April, 1994. APPENDIX The parties have submitted proposed findings of fact. It has been noted below which proposed findings of fact have been generally accepted and the paragraph number(s) in the Recommended Order where they have been accepted, if any. Those proposed findings of fact which have been rejected and the reason for their rejection have also been noted. Mr. Hunter's Proposed Findings of Fact Accepted in 1 and 3. Accepted in 2. Accepted in 4. Although Ernest Frey, Director of District Management, Northeast District Office of the Department, did ask Mr. Hunter whether he wanted to sell his property to the State, the evidence failed to prove why Mr. Frey asked this question, that Mr. Frey asked the question in his official capacity with the Department, or that Mr. Frey made the inquiry at the direction or on behalf of the Department or the State. More importantly, the evidence failed to prove that the Department denied the permit sought by Mr. Hunter because of any interest the State may have in purchasing Mr. Hunter's property. See 4. 6-8 No relevant. Not supported by the weight of the evidence. Accepted in 6, 23, 28 and 30. Not a proposed finding of fact. See 8. The "aerial photo, Petitioner's exhibit 6, does not show "No vegetation behind the slab, nearly to the Mean High Water Line . . . ." Respondent's exhibit 3 does, however, show vegetation as testified to by Department witnesses. 13-14 Not supported by the weight of the evidence. Not a proposed finding of fact. Generally correct. Mr. Hunter was not properly put on notice of "alternatives" by the Notice of Permit Denial, as corrected, issued by the Department. Summation: Mr. Hunter's Summation was considered argument and was considered in this case. The Department's Proposed Findings of Fact Accepted in 1 and 3. Accepted in 2. Accepted in 1 and 4-5. Accepted 6-7. Accepted in 8. 6-9 Hereby accepted. Accepted in 12. Accepted in 13. Accepted in 14. Accepted in 15. Accepted in 19. Accepted in 20. Accepted in 15. 17-18 Accepted in 15 and hereby accepted. Accepted in 15 and 20-21. Accepted in 10. Accepted in 22. Hereby accepted. Accepted in 22. Accepted in 12. Accepted in 15-16. Accepted in 17 and 21. 27-28 Accepted in 17. Accepted in 18. Accepted in 13. Accepted in 16. 32-33 The Notice of Permit Denial, as corrected, did not put Mr. Hunter on notice that the alternatives raised by the Department at the final hearing would be an issue in this case. Those alternatives should not, therefore, form any basis for the Department's final decision. Accepted in 24-25. Accepted in 23. Accepted in 25. Accepted in 24 and hereby accepted. Accepted in 26. COPIES FURNISHED: Clifford O. Hunter 1410 Ruby Street Live Oak, Florida 32060 Beth Gammie Assistant General Counsel Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-9730 Virginia B. Wetherell, Secretary Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Kenneth Plante, Esquire General Counsel Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400
The Issue The issue to be determined in this case is whether proposed Florida Administrative Code Rule 40E-10.041(3)(d) of the South Florida Water Management District (“the District”) is an invalid exercise of delegated legislative authority.
Findings Of Fact The Conservancy is a non-profit Florida corporation with its offices in Naples, Florida. It has 6,200 members residing in Southwest Florida. The mission of the Conservancy is to protect the environment and natural resources of Southwest Florida. The Caloosahatchee River is an important focus of the Conservancy’s organizational activities and objectives. A substantial number of the members of the Conservancy use the Caloosahatchee River for drinking water, boating, fishing, wildlife observation, and scientific research. The proposed rules create a prospective reservation of water in the not-yet-operational Caloosahatchee River (C-43) West Basin Reservoir “for fish and wildlife.” The Conservancy’s interests would be substantially affected by the proposed reservation. The District is a regional water management agency created, granted powers, and assigned duties under chapter 373, Florida Statutes (2013). It is headquartered in West Palm Beach, Florida. Proposed rule 40E-10.041(3) states: (3) Caloosahatchee River (C-43) West Basin Storage Reservoir: All surface water contained within and released, via operation, from the Caloosahatchee River (C-43) West Basin Storage Reservoir is reserved from allocation. The water reserved under this paragraph will be available for fish and wildlife upon a formal determination of the Governing Board, pursuant to state and federal law, that the Caloosahatchee River (C-43) West Basin Storage Reservoir is operational. The reservation contained within this subsection and the criteria contained in section 3.11.4 of the Applicant’s Handbook for Water Use Permit Applications within the South Florida Water Management District, incorporated by reference in Rule 40E-2.091, F.A.C., shall be revised in light of changed conditions or new information prior to the approval described in paragraph (3)(b) above. Pursuant to subsection 373.223(4), F.S., presently existing legal uses for the duration of a permit existing on [RULE ADOPTION DATE] are not contrary to the public interest. The Conservancy challenges only paragraph (3)(d), contending that it modifies or contravenes the implementing statute, section 373.223(4).
Findings Of Fact Petitioner River Trails is the developer of a condominium community in Palm Beach County known as River Walk. River Walk is contiguous to and immediately adjacent to 2600 feet of South Florida Water Management District (hereinafter "SFWMD") property bordering Canal C-18 in Palm Beach County. The right- of-way adjacent to C-18 as well as the bottom of C-18 is owned by SFWMD. C-18 is not in an area designated as Outstanding Florida Waters. As required by Section 403.813(2), Florida Statutes, River Trails sought and obtained on January 12, 1984, a permit from the SFWMD to construct a dock and boat ramp in Canal C-18. The permit conveyed no property rights to River Trails. On October 12, 1984, River Trails asked DER to confirm that River Trails' proposed boat ramp qualified for an exemption pursuant to Section 403.813(2)(c), Florida Statutes. By letter dated December 20, 1984, DER informed River Trails that the proposed boat ramp did qualify for the exemption and, therefore did not require any permit from DER. On October 18, 1984, River Trails asked DER to confirm that River Trails' proposed dock of 1,000 square feet or less qualified for an exemption from DER's permitting authority pursuant to Section 403.813(2)(b), Florida Statutes. However, on November 30, 1984, DER informed River Trails that its proposed dock did not qualify for the exemption because there was already an existing dock on SFWMD property on Canal C-18. As authority for its position, DER cited the following sentence in DER Rule 17-4.04(9)(c), Florida Administrative Code: "A private dock is a single pier at a parcel of property." On the 2600 feet of SFWMD-owned right-of-way contiguous to River Trails, there are presently no docks. On SFWMD-owned right-of-way east of River Trails, between River Trails and the southwest fork of the Loxahatchee River, there are two docks approximately 300 feet apart located in front of single-family residences. DER contends all contiguous property owned by an individual, group or entity, including a water management district, constitutes a "parcel of property" and accordingly does not recognize River Trails' claim to an exemption because of the existence of these docks. Prior to River Trails' request that DER confirm River Trails' right to an exemption, DER had not interpreted water management district-owned right-of-ways to be a "parcel of property" within the meaning of Rule 17- 4.04(9)(c). In the past, the SFWMD has permitted numerous docks of less than 1,000 square feet on SFWMD-owned right- of-ways. Copies of these permits were routinely forwarded to DER. While these docks were and are on right-of-ways which DER now defines as a "parcel" within the meaning of Rule 17-4.04(9)(c), DER has not required permits for these docks. The DER employees who interpret the rule in question as part of their duties and whose depositions were introduced at hearing do not agree on the configuration which constitutes a single pier, on the degree of ownership or control required over a parcel of property by an applicant for an exemption, or on the definition of a parcel of property. DER has failed to adequately explain its deviation from past agency practice in interpreting SFWMD right-of- way as a parcel of property. But for DER's new interpretation of the term "parcel of property" found in Rule 17-4.04(9)(c), Florida Administrative Code, River Trails' proposed dock meets the statutory and rule requirements for an exemption from obtaining a permit from DER.
The Issue The issue is whether Vista of Fort Walton Beach, LLC (Vista), should be issued Surface Water Management Permit No. 04-2012-0013G authorizing the construction of an earthen embankment dam and impoundment to impound stormwater runoff from a proposed commercial development in the City of DeFuniak Springs (City), Walton County, Florida.
Findings Of Fact The District has regulatory jurisdiction over the construction of certain types of impoundments within its boundaries. If an impoundment is at least ten feet high but less than 25 feet in height and has an impounding capacity of at least 50 acre-feet, a general permit is required. See Fla. Admin. Code R. 40A-4.041(1). Vista, a limited liability corporation, owns an odd- shaped parcel in the City on which it intends to build a small commercial development consisting of a 17,000-square foot building, a parking lot, and related amenities. The vacant parcel abuts the north side of U.S. Highway 90 just east of 18th Street and is approximately 1.66 acres in size. The property is partially wooded and has a small wetland area on its northeastern corner. In conjunction with the proposed commercial development, Vista intends to construct an impoundment to control stormwater runoff from the project. Because the impoundment will be ten feet high and have an impounding capacity of at least 50 acre-feet, Vista is required to obtain a general permit. See Fla. Admin. Code R. 40A-4.041(1). Vista filed a permit application with the District on June 8, 2012. On August 8, 2012, the District gave notice that it intended to issue a surface water management permit to Vista. The permit allows the construction of a stormwater retention basin. A mitigation plan for impacts to 0.23 acres of wetlands was also approved but is not at issue in this proceeding. As described in the District staff report, the project will encompass one earthen embankment dam and impoundment to impound the storm runoff. It will operate as a dry stormwater retention basin designed to impound water only during rainfall events. The facility will utilize a pipe and riser spillway system, and the basin outfall will be protected by a rip-rap lined plunge pool. Due to space restrictions, an engineered retaining wall will be incorporated into the embankment's north side slope. The stormwater will discharge through controlled overflow structures into a nearby wetland area that lies northeast of Vista's property and will then be integrated into an existing channel that eventually forms the headwaters of Sandy Creek to the north. Petitioner has resided on her property since around 1932. Her odd-shaped parcel, described as being between five and seven acres in size, lies immediately to the north of Vista's property. A small wetland is located on the southeastern corner of her property. The two parcels share a common boundary line, appearing to be no more than a hundred feet or so. Because the boundary line is lower than the highest part of each owner's property, a "trench" has formed along the line. Wabash Avenue, a platted but un-built roadway that begins on U.S. Highway 90, runs to the northwest through the wetland area and along the eastern boundaries of both properties. As alleged in the Second Amended Petition, Petitioner is concerned that the project will cause flooding on her property. In a broader sense, she appears to be opposed to any commercial development on Vista's property. The back side of the Vista parcel slopes downhill to a recessed area that is adjacent to both properties. Although some fill has already been placed on the property in preparation for the development, the applicant intends to add "a lot" more fill to the entire parcel to create a gradual slope down to the edge of Wabash Avenue. A basin or pond around 0.20 acres in size will be formed within the fill area and a retaining wall consisting of multiple segments will be constructed around the basin. The wall will be separated from Petitioner's property by a 20-foot buffer, while at its closest point the basin will be "35 feet or so" from her property line. The plans submitted by the applicant demonstrate that the system will be built in accordance with all District standards and should operate in a safe manner. Before construction can begin, the District must approve the retaining wall design specifications. During rain events, the first inch of water will be retained on site for treatment. Additional water will be stored in the basin and then slowly allowed to discharge from the basin into the wetlands. The point of discharge from the basin is at a location a minimum of 20 feet south and east of Petitioner's property line. To ensure that the retention system will not discharge runoff at a higher rate than was discharged before development, Vista performed hydrologic calculations demonstrating pre- and post-development runoff. According to accepted models developed by the United States Department of Agriculture and its predecessor, the Soil Conservation Service, the current peak runoff from the Vista property is 2.46 cubic feet per second (CFS) during a two-year, 24-hour storm event. After development, the volume of water will be reduced to 0.74 CFS. During a 25-year, 24-hour storm event, the volume of runoff post-development is anticipated to drop from 12.59 CFS to 6.51 CFS. Finally, during a 100-year, 24-hour storm event, post- development runoff will be slightly reduced from 19.64 CFS to 18.99 CFS. Therefore, as sited, sized, and designed, the project will reduce runoff during all anticipated storm events. The foregoing calculations were not credibly contradicted and satisfy the requirement that an applicant give reasonable assurance that the project will not cause an increased flow such that it will endanger downstream property in times of flood with respect to state or frequency. See Fla. Admin. Code R. 40A-4.301(2)(f). They also confirm that water in the impoundment will not be raised to a level that could be harmful to the property of others. See Fla. Admin. Code R. 40A- 4.301(2)(c). Thus, the potential for flooding on Petitioner's property will be reduced if the project is constructed as permitted. The Department of Transportation (DOT) is currently repairing the drainage system on U.S. Highway 90 in front of the Vista property. Stormwater from that project drains into the wetlands through an easement deeded to the City at the rear of the Vista property. Petitioner pointed out that after the DOT project began, and fill was added to the Vista property, she has experienced an increase in water on her property. Whether the DOT project is responsible in any way for this hydrologic change is not known. However, accepted testimony by two professional engineers supports a finding that Vista is not responsible for any hydrologic changes on Petitioner's property. Vista was not required to take into account any runoff from the DOT project in making its hydrologic calculations because the amount of runoff from its own property will actually be reduced by the retention system. At hearing, Petitioner contended that a fence she built on the common boundary line with Vista sometime after 1990 was illegally removed by Vista in order to construct the basin. According to Mr. George, who first surveyed the property line in 1990 and then surveyed it a second time a few years ago, the fence was built a few feet beyond Petitioner's property line and lies within the buffer zone between the basin and her property. Petitioner argues that even if this is true, the doctrine of adverse possession applies and she is now the owner of the property on which the fence was built. This type of dispute, however, can only be resolved in circuit court, and not in an administrative forum. See § 26.012(2)(g), Fla. Stat. The District has examined the property records and is satisfied that Vista has ownership of the property on which the impoundment will be built. Notably, the basin will not be located within the 20-foot buffer where the fence once stood and which is dedicated to the City as an easement. Finally, through cross-examination at hearing, Petitioner suggested that any project designed by humans carries with it the remote possibility that it will fail and create a catastrophic situation on her property. In the unlikely event that the design and operation of the retention basin threaten the safety of adjoining property owners, section 373.429 and rule 40A-1.205 enable the District to revoke, suspend, or modify a permit to protect the safety of others.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Northwest Florida Water Management District enter a final order approving the issuance of Surface Water Management System Permit No. 04-2012-0013G to Vista. DONE AND ENTERED this 11th day of March, 2013, in Tallahassee, Leon County, Florida. S D. R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 11th day of March, 2013. COPIES FURNISHED: Jonathon Steverson, Executive Director Northwest Florida Water Management District 152 Water Management Drive Havana, Florida 32333-4712 Helen J. Crenshaw 61 North 18th Street DeFuniak Springs, Florida 32433-9547 Kevin X. Crowley, Esquire Pennington, Moore, Wilkinson, Bell & Dunbar, P.A. Post Office Box 10095 Tallahassee, Florida 32302-2095 James Busby Vista of Fort Walton Beach, LLC Post Office Box 760 Fort Walton Beach, Florida 32549-0760
The Issue The issues in this case are whether Respondents, David H. Fort and Claudia A. Fort, violated certain statutes and rules of Petitioners, Department of Environmental Protection ("Department") and Board of Trustees of the Internal Improvement Trust Fund ("Trustees"), related to the construction of a dock and boathouse and the use of sovereignty submerged lands, as alleged in the Amended Notice of Violation and Orders for Corrective Action ("Amended NOV") and, if so, whether the administrative fines, investigative costs, and corrective actions sought by Petitioners should be imposed against Respondents.
Findings Of Fact The Department is the state agency charged with the power and duty to administer and enforce the provisions of Chapter 403, Florida Statutes, and the rules promulgated in Florida Administrative Code Title 62. The Trustees are responsible for state-owned sovereignty submerged lands and ensuring that such lands are managed for the benefit of the citizens of Florida pursuant to Chapter 253, Florida Statutes, and the rules promulgated in Florida Administrative Code Title 18. The Department performs all staff duties and functions for the Trustees related to the administration of state lands. See § 253.002, Fla. Stat. David and Claudia Fort own property located at 7875 A1A South, St. Augustine, St. Johns County, Florida. The property is located adjacent to the Matanzas River, a part of the Intracoastal Waterway. The Trustees own the lands lying below the mean high water line of the Matanzas River. The Permit and Lease Harbor Engineering (“Harbor”), a marine engineering firm, acted as Respondents' agent in preparing plans and applying for the permit and lease to construct a dock and boathouse at the property. Harbor prepared and submitted to the Department five sketches or drawings showing various layouts, cross sections, and elevations of the proposed dock and boathouse. These drawings were made a part of the permit and became conditions of the permit. The permit drawings show one large covered slip, two smaller covered slips for mooring of jet skis, and a two-level boathouse. Although some of the elevations do not show walls, it is apparent that this was for the purpose of showing interior areas, such as the slips. Although difficult to see, one drawing indicates a doorway on the lower level. The elevations show window openings or "cutouts" in the walls of the boathouse, but do not indicate framed window panes. The drawings do not create a necessary conclusion that the cutouts are intended to be finished with framed window panes. On January 13, 2004, the Department issued Environmental Resource Permit and Sovereign Submerged Lands Authorization No. 55-216127-002-ES ("permit"), which authorized Respondents to construct a dock and boathouse in the Mantanzas River adjacent to Respondents' property. General Condition (a) of the permit states: All activities shall be implemented as set forth in the plans, specifications and performance criteria as approved by this permit. Any deviation from the permitted activity and the conditions for undertaking that activity shall constitute a violation of the permit. On February 24, 2004, the Trustees issued Sovereignty Submerged Lands Lease No. 550034552 ("lease") to Respondents, authorizing the use of sovereignty submerged lands for a 3-slip docking facility and boathouse "as shown and conditioned" in the Department permit, which was incorporated into and made a part of the lease.2/ Paragraph 1 of the lease states that the dock and boathouse are "exclusively to be used for mooring of recreational vessels in conjunction with an upland single-family residence." Paragraph 7 of the lease states in pertinent part: This lease is given to the Lessee to use or occupy the leased premises only for those activities specified herein and as conditioned by the Department of Environmental Protection, Environmental Resource Permit. The Lessee shall not change or add to the approved use of the leased premises as defined herein . . ., shall not change activities in any manner that may have an environmental impact that was not considered in the original authorization . . . without first obtaining . . . the Lessor's written authorization in the form of a modified lease. Paragraph 26 of the lease states that the lessee shall ensure that no "structures whose use is not water-dependant shall be erected or conducted over sovereignty submerged lands without prior written consent from the Lessor." The term "water dependent activity" is defined in Florida Administrative Code Rule 18-21.003(71): "Water dependent activity" means an activity which can only be conducted on, in, over, or adjacent to water area because the activity requires direct access to the water body or sovereign submerged lands for transportation, recreation, energy production or transmission, or source of water, and where the use of the water or sovereign submerged lands is an integral part of the activity. The lease was issued for a term of five years. It expired on January 12, 2009. Enforcement History Respondents began construction of the dock and boathouse in February 2004. A Department employee, Michael Savage, inspected the dock and boathouse on June 8, 2004, while construction was in progress. Savage said he was responding to an anonymous complaint about Respondents' dock and boathouse, but Savage did not explain the nature of the complaint. Savage had the permit drawings with him during the inspection. The dock pilings were in place as well as the "shell" of the boathouse. The structure had some cutouts for windows, but no windows with panes were installed. Savage measured the structure. Savage did not see anything during his June 8, 2004, inspection that caused him to believe the structure was not being constructed in compliance with the permit, except that a copy of the permit had not been posted at the site as required by the permit. Savage said he called Respondents, left a voice message, and talked to the builder. The Department's on-line enforcement record for the June 8, 2004, inspection indicates that a call was made and a message was left: "Need to have permit posted/erosion control in place." Savage and another Department employee inspected the dock and boathouse again on July 9, 2004. Savage had the permit drawings with him during this second inspection. Three outside walls were in place and the second level of the boathouse was under construction. No window framing or glass had been installed. An overhang, extending over the northwest corner of the structure, was in place. Savage had some concern about whether the locations of the window cutouts were in compliance with the permit. In all other respects, he thought that the construction was in compliance. The structure shown in the photographs taken on July 9, 2004, looks like a small house. It does not look like a structure intended only to provide shelter to a boat slip. The Department did not communicate with Respondents about the July 9, 2004, inspection. The Department's on-line enforcement record for the July 9, 2004, inspection includes the entry "In compliance." General Condition (j) of the permit requires that within 30 days after completion of construction of the permitted system, the permittee must submit a written statement of completion using an As Built Certification Form ("as-built"). On the as-built, the permittee is required to note and explain any “substantial deviations." Instead of submitting a single as-built following the completion of the dock and boathouse, Respondents submitted three as-builts. David Fort said his purpose was to keep the Department informed about the progress of the project. On September 8, 2004, the Department received the first of Respondent's as-builts. On the as-built form, David Fort indicated that the work was substantially completed. Although Fort did not intend to mislead the Department, the construction was not substantially completed at that time. A substantial amount of work remained to be done. Savage and another Department employee inspected the dock and boathouse on September 14, 2004. Savage had the permit drawings with him for this inspection. The boathouse was not changed much from its appearance in July 2004. It had no windows or doors. Savage believed that the project was in compliance with the permit and later made a note to that effect on a sheet containing three photographs that were taken during the inspection. The Department's on-line enforcement record for the September 14, 2004, inspection indicates that Savage met with the builder and includes the entries "In Compliance" and "Built as Permitted." Matthew Kershner, Compliance Enforcement Manager for the Department, accompanied Savage on one of the inspections of the dock and boathouse. Kershner placed a telephone call to David Fort and said his purpose in calling was to respond to a complaint from a neighbor "about a large dock being constructed." Kershner told Fort that Fort could not "climatize" the boathouse. Kershner did not explain at the final hearing what he meant by the term "climatize," nor did he give any other details about his conversation with Fort. It is reasonable to infer from the evidence, however, that Kershner meant that Fort was not permitted to provide artificial heating and air- conditioning in the boathouse. Fort called Kershner later and asked if he could install fans and Kershner told Fort that fans would be acceptable. It is reasonable to infer from the photographic evidence, alone, that Kershner knew in September 2004 that the apparent plan of construction was to at least partially enclose the boathouse. However, Kershner told Fort that turning the dock into a residence or "enclosing it" was not permitted. The only reasonable meaning to ascribe to a statement that a structure cannot be enclosed is that there must be some permanent, unobstructed way to pass in and out of the structure. A room surrounded by walls, with a door, is an enclosed structure. In November 2004, the first windows were installed in the boathouse. The windows were specially made to withstand severe weather. Respondents paid $120,000.00 for the windows. On January 7, 2005, the Department received the second as-built from Respondents. Hand-written on the form is “windows installed 1-6-05.” Another Department employee, Tracy Schilling, inspected the dock and boathouse in January 2005. Schilling said the inspection was in response to a complaint from a neighbor that the dock was "extremely large" and that it was blocking the neighbor's view. Schilling reviewed the permit drawings before her inspection. The construction was still incomplete. There was framing work underway on the first floor interior of the boathouse. Schilling said it was apparent from the framing that the boathouse would have "separate rooms." Schilling believed that the dock and boathouse were in compliance with the permit. On April 13, 2005, the Department received the third as-built from Respondents. On June 28, 2005, Schilling and another Department employee inspected the dock and boathouse again. Photographs taken during the inspection show windows were installed. Framing was completed in the upstairs portion of the structure, creating two rooms, and interior walls on the first floor were finished. The rooms were at least partially furnished with chairs, tables, and a lamp. During the June 2005 inspection, Schilling observed a fiberglass shower stall, still in its box, on the dock. Schilling believed that the installation of a shower stall would violate the prohibitions in the permit and lease against structures that were not water-dependent. The Department's notes for the June 2005 inspection indicate “Minor Out-of- compliance.” Schilling said she did not consider the windows to be out of compliance because window openings were shown on the permit drawings. On the first sheet of photographs taken during the June 2005 inspection (Respondents' Exhibit 3B), someone has written, "This is sliding over into non-water dependent category - Let's talk." However, the record does not include any explanation of this handwritten comment. Schilling sent a letter to Respondents on August 29, 2005, informing Respondents that an “item” was found to be non- compliant with Condition 26 of Respondents’ permit that prohibits structures whose use is not water-dependent and that such structures must be removed within 30 days. The letter did not identify the structure that was not water-dependent. On September 7, 2005, David Fort called Schilling about the August 28 letter. Schilling told Fort that the “item” referred to in the letter was the shower stall. She told Fort that plumbing and running water were not allowed. Fort told Schilling that he was not going to install the shower. In February or March, 2006, Schilling called David Fort to request permission for Schilling and some Department employees from the Division of State Lands in Tallahassee to inspect the dock and boathouse. Schilling said State Lands employees occasionally make site visits to inspect unusual docks and marinas "that may have issues." She suggested the inspection of Respondents' boathouse because it was the "Taj Mahal of docks." The inspection was conducted by Schilling and three other Department employees. Schilling had a copy of the lease with her. The exterior construction of the boathouse was complete and the interior work was substantially complete. Schilling believed the structure was built in compliance with the permit. Respondents did not submit an as-built to reflect the final construction of the dock and boathouse. The Department's enforcement action arose as a result of Savage's September 3, 2009, inspection of the dock and boathouse. It was during this inspection when Savage first became aware of the enclosed rooms of the boathouse. He observed a children's playroom with carpeting, lighting, an air conditioning unit, cable for television, and shelves. These structures and uses are not water-dependent. Savage observed another room in the boathouse that contained an air conditioner or dehumidifier, refrigerator, kitchen-style cabinetry, glass-paned windows, kitchen-style sink connected to a water supply, television, and a microwave oven. These structures and uses are not water-dependent. Savage observed another room with a water heater and a shower stall. The room also was being used to store cleaning materials and personal property. These structures and uses are not water-dependent. Savaged observed electrical wiring throughout the boathouse. The Department allows electrical wiring only for water-dependent uses, such as an electric boatlift or for emergency lighting. On the dock adjacent to the large mooring slip, Savage observed a sink connected to a water supply, a glass-paned window, and a door that enclosed a lower level room. Savage did not think the sink was "representative of a fish cleaning station." His objection to the sink was that it had more than one basin and did not have a sign identifying it as a fish cleaning station. Also on the dock in the area of the slips, Savage observed music speakers installed on the wall, doors enclosing rooms, and a closet which was being used to store fishing reels and gear. There is a pump stored next to the boat lift in the boat storage area that pumps water out of the Matanzas River into a tank for keeping live bait. Respondents admitted that they had installed structures at the dock and boathouse that were not authorized by the permit. These unauthorized structures are a stairway and ramp to the beach, a floating platform on pilings with a metal gangway, and an "overhang" (that portion of the upper level deck on the north side of the boathouse that extends 1.5 feet beyond the outer wall of the lower level). The Department incurred $1,874.00 in investigative costs for investigation and enforcement activities associated with Respondents' dock and boathouse. Respondents did not dispute these costs. They are reasonable costs. Detrimental Reliance Respondents claim that they relied on the Department's representations following the Department's inspections of the construction and would not have installed the doors, windows, or other features in the structure if the Department had told Respondents that these structures were not authorized by the permit. The permit drawings indicate a boathouse with areas that would be semi-enclosed. However, the permit and lease limit this boathouse to a structure for the mooring and protection for boats. The boathouse is not supposed to serve as a residence or a clubhouse. It was unreasonable for Respondents to believe that the permit authorized enclosed rooms and amenities typical of an upland residence with many features that are not water-dependent. Respondents presented no evidence to show that similar boathouses have been authorized by Department permit. David Fort's actions showed that he had a complete disregard for the warnings and instructions that he received from the Department. He was told that he could not "climatize" the boathouse. He was told that he could not enclose the boathouse. He was told that he could not install the shower stall. He was told that he could not install plumbing or running water. He was told that he could not use the dock and boathouse for activities that were not water-dependent. Yet he did all of these things anyway. He built certain structures, such as the floating dock and gangway, which he knew were not authorized by the permit. It is in this context of Fort's apparent intent to do whatever he wanted with the boathouse, no matter what the Department said, that Fort's claims of detrimental reliance must be considered. The more persuasive evidence does not show that Respondents relied to their detriment on any representation by a Department employee, except for the installation of fans. David Fort asked a direct question about whether he could install fans, before the fans were installed, and was told by the Department that he could install fans. All of the other structures that are the subject of this case were installed without a prior discussion with the Department or are contrary to instructions given by the Department. Respondents point out several times that certain structures were in place before a Department inspection, facts which Respondents believe support their arguments about the structures being in compliance with the permit, because the Department saw the structures but did not object to them. Although these facts are relevant to the determination of whether the structures were, in fact and in law, in compliance with the permit, they undermine Respondents' claim of reliance. Respondents' claim of reliance is not based on any affirmative acts of the Department, but on the Department's silence. The Department's silence caused Respondents to believe that the Department would not take enforcement action, but the evidence does not show that Respondents relied on the Department's silence to construct or install any of the disputed structures.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioners issue Final Orders that impose the administrative fines and order the corrective actions set forth in the Amended Notice of Violation and Orders for Corrective Action, dated June 1, 2010, with the modifications stated above. DONE AND ENTERED this 29th day of September, 2010, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 29th day of September, 2010.