Findings Of Fact On July 19, 1991, the Petitioner, Cahill Pines and Palm Property Owners Association, Inc. (Cahill), filed a permit application with the Department of Environmental Resources, predecessor to the Respondent, Department of Environmental Protection (Department), for a permit to remove two earthen plugs in the Cahill canal system, located in Big Pine Key, Monroe County, Florida. The plugs were to be removed to a depth of -5.5 feet N.G.V.D. Kenneth Echternacht, a hydrologist employed by the Department, had performed a hydrographic review of the proposed project and reduced his findings to writing in a memorandum dated June 25, 1993. Mr. Echternacht recommended that the project not be permitted. On August 20, 1993, the Department issued a notice of its intent to deny Cahill's application to remove the plugs. The notice included six proposed changes to the project which would make the project permittable. Cahill requested an administrative hearing on the Department's intent to deny the permit. On March 3 and 4, 1994, an administrative hearing was held on the issue of whether a permit should be issued. The hearing officer entered a recommended order on May 9, 1994, recommending that a final order be entered denying the permit. The Department issued a final order on June 8, 1994, adopting the recommended order of the hearing officer and denying the permit. See Cahill Pines and Palm Property Owners Association v. Department of Environmental Protection, 16 F.A.L.R. 2569 (DER June 8, 1994). In the final order the Department found that the following findings of Mr. Echternacht were "scientifically sound and credible conclusions": The estimated flushing for the presently open portion of the waterway was calculated to be 14.5 days. The flushing for the open section exceeds the 4 day flushing criterion by approx- imately 3.6 times. Clearly, the open portion poses a potential problem to the maintenance of acceptable water quality. For the presently closed sections of the waterway, the calculated flushing time was found to be 38.6 days. Again, this system would pose a significant potential for contamination to adjacent open waters if opened for use. The waters behind the barrier that presently appear to pose no problem would clearly become a repository for contaminants associated with boat usage. Because of the exceptionally long flushing time, contaminants would build up over time. Below standard water quality throughout the waterway would be expected and, associated with this, below standard water would be exported into adjacent clean water on each ebbing tide. The final order also found the following facts: 13. Neither the water in the open canals nor the water in the closed canals is presently of substandard quality. * * * Petitioner's plug removal project will also spur development in the Cahill subdivision and lead to an increase in boat traffic in the Cahill canal system, as well as in the adjacent waters of Pine Channel. Such activity will result in the discharge of additional contaminants in these waterways. As Echternacht stated in his June 25, 1993, memorandum that he sent to O'Connell, '[b]ecause of the [canal system's] exceptionally long flushing time, [these] contaminants would build up over time' and result in a significant degradation of the water quality of not only the Cahill canals, but also of Pine Channel, into which Cahill canals flow. This degradation of water quality will have an adverse effect on marine productivity and the conservation of fish and wildlife that now inhabit these waterways. Consequently, in the long run, the removal of the plugs will negatively impact fishing opportunities in the area. On the other hand, the project will have a beneficial effect on navigation and recreational boating and related activities. It will have no impact on historical and archaeological resources. On April 10, 1995, Cahill submitted a permit application to the Department to remove portions of the two canal plugs. Cahill proposed to leave an island in the center of each plug. The islands would be stabilized with riprap, and mangrove seedlings would be planted in the riprap. By letter dated April 21, 1995, the Department returned the April 10 permit application to Cahill along with the $500.00 processing fee. The Department advised Cahill that the application was not substantially different from the 1991 permit application which was denied by final order. The Department further advised that Cahill could resubmit the application and application fee if it wanted the permit to be processed but the Department would deny the application on the basis of res judicata. On May 17, 1995, Cahill submitted a revised permit application along with the processing fee. A circulation culvert had been added to the project. Ken Echternacht performed a hydrographic review of the proposed project. In a memorandum dated May 25, 1995, Mr. Echternacht recommended that the permit be denied for the following reasons: The proposed 24-inch culvert connection would not be expected to be visible hydraulically. A 24-inch diameter culvert, length 181 ft would be expected to have a friction factor several orders of magnitude greater than the adjacent canals. As such, water would not be expected to pass through the connector unless there were a sizeable head to drive the flow. No studies and/or supporting documentation have been provided to support the design in terms of the documenting the amplitude and repeatability of the flow driving force. Cutting holes through embankments do not necessarily result in flushing relief. As stated in 1, above, any and all proposed design modifications to the proposed waterway must be accompanied by adequate design justifi- cation based on hydrographic modeling supported by site specific data support. The culvert design proposed does not meet the above require- ment. The proposal is nothing new. In the hearing, ideas such as the above were suggested. However, as was stated in the hearing any and all such proposals must be supported by proper engineering study. On July 7, 1995, the Department issued a Notice of Permit Denial, denying the May, 1995 permit application on the basis of res judicata, stating that the May 1995 permit was not substantially different from the 1991 permit application which had been denied and that no studies had been submitted by Cahill that would support that the use of the islands and culvert would increase the flushing rate to the four day flushing criterion established in the hearing on the 1991 permit application. At the final hearing counsel for Cahill stated for the record that the use of the islands and the culvert would not increase the flushing rate to four days.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered denying Cahill Pines and Palms Property Owners Association, Inc.'s application for a permit to remove two plugs separating the open and closed canal sections of the Cahill canal system, placing an island in the center of each plug, and adding a 24 inch culvert connection. DONE AND ENTERED this 31st day of July, 1996, in Tallahassee, Leon County, Florida. SUSAN B. KIRKLAND Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of July, 1996. APPENDIX TO RECOMMENDED ORDER, CASE NO. 95-4377 To comply with the requirements of Section 120.59(2), Florida Statutes (1995), the following rulings are made on the parties' proposed findings of fact: Petitioner's Proposed Findings of Fact. Paragraphs 1-7: Accepted in substance but not necessary to be incorporated in the recommended order. Paragraph 8: The evidence presented showed that there is a dispute of whether the waters are now of substandard quality. For the purposes of this hearing, it is not necessary to determine whether the water quality is presently substandard. Based on the assumption that the water quality is not substandard, Petitioner has failed to show that the change in the design of the project is sufficient to warrant the rejection of the applicability of the doctrine of res judicata. Petitioner has failed to show that the addition of islands and a culvert will eliminate the potential for future contamination of the waters. The second sentence is accepted in substance but not necessary to be incorporated in the recommended order. Paragraphs 9-11: Accepted in substance but not necessary to be incorporated in the recommended order. Paragraphs 12-15: Accepted in substance to the extent that for the purposes of this hearing the water quality is assumed not to be substandard. Paragraph 16: Rejected as unnecessary. Paragraphs 17-27: Rejected as subordinate to the finding that for the purposes of this hearing the present water quality is assumed not to be substandard. Paragraphs 28-30: Accepted in substance. Paragraph 31: Accepted in substance to the extent that the changes in the design will not increase the flushing rate to four days. Paragraphs 32-33: Accepted to the extent that they were findings in the final order on the 1991 application. Paragraphs 34-35: Accepted to the extent that the slow flushing rate is one of the criteria to be considered. The increase of development and boat traffic are also contributors to the potential of contamination building up. Petitioner has not demonstrated that the use of islands and a culvert will eliminate the potential for contamination. Respondent's Proposed Findings of Fact. Paragraphs 1-10: Accepted in substance. Paragraphs 11-14: Rejected as unnecessary. Paragraph 15: Accepted in substance. Paragraph 16: Accepted in substance as corrected. Paragraph 17: Accepted. Paragraphs 18-21: Accepted in substance. Paragraph 22: Accepted. Paragraph 23: Rejected as unnecessary. COPIES FURNISHED: David Paul Horan, Esquire Horan, Horan and Esquinaldo 608 Whitehead Street Key West, Florida 33040-6549 Christine C. Stretesky, Esquire John L. Chaves, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Kenneth J. Plante, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Virginia B. Wetherell, Secretary Department of Environmental Protection 3900 Commonwealth Boulevard, Douglas Building Tallahassee, Florida 32399-3000
Findings Of Fact Respondent, Arthur B. Lujan (Lujan) and his wife, Betty L. Lujan, are the owners of a 34.09-acre parcel of land which includes Enchanted Island and its surrounding submerged lands. 1/ Enchanted Island is a 3 1/2-acre island located in Florida Bay to the east of Key Haven and north of U.S. Highway 1, Monroe County, Florida. On January 15, 1986, Lujan applied to Monroe County for a land clearing permit and fill permit. The permits, as requested, would have permitted him to clear, after-the-fact, the island of vegetation, fill the island to +4' MHW (mean high water), and restore an access road to the island. Lujan's applications were approved, and the permits issued on February 4, 1986. The Department of Community Affairs (Department), pursuant to Section 380.07, Florida Statutes, filed a timely appeal with the Florida Land and Water Adjudicatory Commission (Adjudicatory Commission). Background In 1970, Lujan and his wife purchased the subject property, which included Enchanted Island and its surrounding submerged lands. At that time, an access road connected the western tip of the island to U.S. Highway 1. 2/ In or about April 1972, Lujan constructed, by the deposit of fill over bay bottom, an access road from U.S. Highway 1 to the eastern tip of Enchanted Island. Since this work was being performed without a federal permit, the Department of the Army, Corps of Engineers (Corps) on April 26, 1972, advised Lujan to cease and desist all unauthorized work in navigable waters of the United States. Lujan complied with the Corps' request, but did not remove the road. In late December 1972, Lujan began fill work on the western access road and on Enchanted Island itself. According to Lujan, his intention was to clearly define the boundary of Enchanted Island, raise its elevation from approximately +3' MSL (mean sea level) to +4' MSL, and restore the western access road, which had been subjected to erosion. Lujan was performing the work on the access road without a federal permit, and on January 4, 1973, the Corps advised Lujan to cease and desist all unauthorized work in navigable waters. 3/ In response to the cease and desist order, Lujan ceased activity on both the access road and Enchanted Island itself. 4/ At that time, the boundary of Enchanted Island had been defined by a perimeter road above MHW and the access road restored, but the elevation of the island had not been raised or its interior altered. Lujan further responded to the Corps' cease and desist order by filing suit in the United States District Court, Southern District of Florida (District Court) to enjoin the Corps from any further interference with the use and enjoyment of Enchanted Island. That suit was dismissed without prejudice when Lujan agreed to submit an after-the-fact permit application to the Corps. That application, filed May 30, 1973, sought leave to restore the western access road, place three culverts through the road, and to remove the unauthorized eastern access road and place its material on the island to bring the final elevation of the island to +4' MLW (mean low water). Subsequently, on June 17, 1974, the Corps denied Lujan's permit. In February, 1975, Lujan again filed suit against the Corps in District Court seeking injunctive and declaratory relief and de novo review of the Corps' permit denial. The United States responded by instituting suit against Lujan for violation of the permit requirements of Section 10 of the Rivers and Harbor Act of 1899, and the Federal Water Pollution Control Act of 1972. In their action, the government sought civil penalties, and an order that the unauthorized work be removed and the area restored to its pre-existing condition. These two actions (Case Nos. 75-150-CIV-EBD and 75-635-CIV-EBD) were ultimately consolidated. On December 5, 1975, the District Court ruled that the Corps' permit denial was neither arbitrary nor capricious. The court further ordered Lujan to remove the western access road and restore the area to the natural depth of the adjacent bottom, and to pay a civil penalty. 5/ Lujan appealed. On appeal, the United States Court of Appeals, Fifth Circuit (Appellate Court) agreed with Lujan's assertion that, inter alia, the Corps had breached an agreement to only consider in their determination substantive objections from the state agencies who had to be notified. The Appellate Court found the state agencies' objections to lack substance, and reversed the decision of the District Court. On remand, the Corps was instructed not to consider any previously filed objections from the state agencies since they were not specific in nature. 6/ Following remand, the Corps notified Lujan that viewed from the context of its 1975 regulations, the interior of Enchanted Island was deemed a wetlands area which could not be filled absent a Corps permit. The District court found, however, that since the Corps acted improvidently in stopping Lujan's activities in January 1973, it would be inequitable for the Corps to retroactively apply its wetlands policy to Lujan's property. Succinctly, the court found in its order of April 26, 1985, that: In 1972, when Lujan initially was ordered to cease work on the road, Corps jurisdiction was not exercised above MHTL. Its 1975 regulations created a "wetlands policy" which asserted jurisdiction over activities above MHTL. Had the Corps not interfered capriciously with Lujan's activities, he would have completed his fill project prior to the change in regulations and the project would have been "grand fathered in" ... Retroactive application of the permitting requirement is not appropriate. Consequently, the court held: The Corps is directed to reopen the permit application only with respect to the western access strip and only so that the administrative process may effec- tuate a reasonable restoration plan. No permitting is required as to Enchanted Island above MHTL, and the Corps is enjoined from exercis- ing jurisdiction over the area (to the extent that Lujan's activities do not affect navigable waters, which would confer jurisdiction upon the Corps). The parties shall meet, formulate an agreed restoration order, and submit it to the court for evaluation within sixty (60) days of this order. (Emphasis added). Lujan and the Corps experienced no difficulty in formulating an agreed restoration plan for the western access road; however, they reached an impass when Lujan insisted that the plan include approval of his desire to fill the interior of Enchanted Island to +4' MHW. While it took no exception to the court's order that it not exercise jurisdiction over the interior of Enchanted Island, the Corps refused to agree that a provision directing the filling of the interior of the island was appropriate. According to the Corps, such matters were not a subject matter of the current litigation and could be an infringement upon county and state permitting requirements. At a hearing held November 15, 1985, at which Mr. Lujan was present, the court concurred with the Corps and directed that any language which referred to raising the existing uplands of Enchanted Island to +4' MHW be deleted. Notwithstanding the court's instruction that the restoration plan contain no reference to filling the uplands of the island, the plans attached to the consent agreement still contained such language, in brackets, when submitted to the court. By order of December 20, 1985, the court ratified the restoration plan, as submitted; however, by order of February 14, 1986, the court corrected its oversight by deleting the bracketed language which dealt with filling the uplands of the island. Current Development Activities On January 6, 1986, Lujan applied with the Florida Department of Transportation (DOT) for a driveway permit which would allow him to connect the western access road through DOT right-of-way to U.S. Highway 1. Receipt of this permit was crucial to Lujan's plans, since at sometime subsequent to January 4, 1973, the portion of the western access road which occupied DOT right-of-way had been removed, creating a water gap in the road. On January 8, 1986, the requested permit was granted, with the following legend stamped conspicuously thereon: VALIDITY OF THIS PERMIT IS CONTINGENT UPON PERMITTEE OBTAINING NECESSARY PERMITS FROM ALL OTHER AGENCIES INVOLVED. On January 14, 1986, Lujan began to prepare the island to receive fill. On that day Lujan filled the "water gap" in the access road and began the process of leveling the high and low portions of the island by bulldozing on the southerly end of the island. It was Lujan's intention to level to the north end of the island and along the access road, and then fill and grade the island. At approximately 5:30 p.m., January 14, 1986, George Garrett, a Monroe County biologist, arrived on the job site with the announced intention of red tagging it since no county permits had been obtained. In response, Lujan exhibited a copy of the District Court's order. Mr. Garrett, at that point, elected not to red tag the job site and requested that Lujan with his supervisor the next day. 7/ Mr. Garrett's request that Lujan meet with his supervisor the next day regarding the project did nothing to deter Lujan's clearing efforts. The proof establishes that when Mr. Garrett left the island on January 14, 1986, there had been some scarification at the southerly end of the island, but the mangrove community which dominated the central portion of the island, discussed infra, had not been disturbed. At 8:30 a.m., January 16, 1986, when the island was again inspected, the island had been cleared of most vegetation and leveled, and the mangroves which had occupied the interior of the island were now resting in several large piles of debris. On January 15, 1986, Lujan met with Bob Herman, Mr. Garrett's supervisor, to discuss the activities which were occurring on the island. As a consequence of that meeting, the job site was red tagged pending Lujan's application for and receipt of Monroe County permits. On January 15, 1986, Lujan filed an application with Monroe County for a fill permit which would permit him to fill the island to +4' MHW and restore the western access road, as well as a land clearing permit which would permit him, after the fact, to clear the island of vegetation. Attached to the applications were copies of the District Court's order of December 20, 1985, and the consent agreement of December 16, 1985. On each application Lujan affixed the following legend: This application is without waiver of applicant's rights in Case Nos. 75-150-CIV-EBD and 75-635-CIV-EBD and position that no permits may be required and that such permits (if any) should be processed using 1972 county laws then in effect. Lujan's applications were not accompanied by a vegetation survey and plot plan as required by Chapters 4 and 18, Monroe County Code, infra. The applications were, however, accompanied by a copy of the December 16, 1985, consent agreement, which contained plans for the restoration of the westerly access road. These plans delineated the areas to be filled, the location of culverts, and the location and elevations of the proposed paved access road. On February 4, 1986, upon instructions from its County Attorney, Monroe County issued a fill permit and land clearing permit to Lujan despite his failure to provide a vegetation survey or disclose his development plans for the island. Each permit contained the following remarks: Said permit issued in accord with the Federal Court Orders entered by Judge Ned Davis on the 26th day of April, 1985, and on the 20th day of December, 1985. Immediately upon receipt of the county permits, Lujan began to fill the interior of the island and restore the westerly access road as rapidly as possible. According to Lujan, he had a contract to obtain fill on advantageous terms if he could promptly remove it from the Key West naval station. By February 14, 1986, auspiciously, Enchanted Island had been cleared of vegetation and its elevation raised to +4' MHW, and the access road restored. On February 20, 1986, the Department of Community affairs (Department) noticed its appeal of the Monroe County permits to the Adjudicatory Commissions. 8/ Enchanted Island At the time Lujan was stopped by the Corps on January 4, 1973, the topography of Enchanted Island had been altered by the establishment of a perimeter road around its boundaries above the MHW mark, and its westerly access road restored. Mangroves fringed the island waterward of the perimeter road, but none existed along the newly restored access road. The interior of the island, located upland of the perimeter road, was not shown to have been significantly altered at that time. On January 14, 1986, when Lujan began to clear and grade the island, its topography had not changed significantly from January 1973; the perimeter of the island was still defined by a roadway above MW and the fringing mangroves waterward of the road still stood. At the center of the island, upland from the perimeter road, a depression existed which covered approximately 15-25 percent of the island's lands and which was characterized by red, black and white mangroves, as well as some buttonwood. This depression was saturated by water at a frequency and duration adequate to support its wetlands species; however, since it was located upland of the MHW mark the Source of its waters was most probably from percolation and rainfall. Located elsewhere on the interior of the island were buttonwood, Bay Cedar and sea oxeye daisy. By January 16, 1986, Lujan had cleared the interior of the island of any significant vegetation, and leveled it. The mangroves, which now fringed portions of the access road, as well as those which fringed the island, were not, however, disturbed. Monroe County Regulations Chapter 4, Article II, of the Monroe County Code (MCC) establishes and regulates development within a shoreline protection zone. Pursuant to Section 4-18, MCC, the zone is established as follows: There is hereby established a shoreline protection zone in all that portion of the county defined in Section 22F-8.02, Florida Administrative Code, and generally known as the Florida Keys. The shoreline protection zone includes submerged lands covered by the waters of the Atlantic Ocean and the Gulf of Mexico (Florida Bay) out to the seaward limit of the State's territorial boundaries, whether in sovereign or private ownership, including those lands contiguous to such waters where fringing mangrove communities occur. In order to maintain the functional integrity of these mangrove communities, the interior boundary of the shoreline protec- tion zone is hereby established at a line extending fifty (50) feet laterally upland from the landward limit of the shoreline mangroves. The shoreline mangroves shall include mangrove communities which contain red (Rhizophora mangle), black (Avicennia nitida) or white (Laguncularia racemosa) mangroves but excluding those mangrove communities which are isolated inland and separated from open water areas by nonmangrove natural vegetative communities. Consequently, all of the western access road and the portion of Enchanted Island lying within 50' upland from the landward limit of the shoreline mangroves are within the shoreline protection zone. The mangroves which occupied the depressed area in the central portion of the island were not, however, within the zone. Pemittable uses within the shoreline protection zone are delineated by sections 4-19 and 4-20, MCC, as follows: Sec. 4-19. Permitted uses in zone. Only the following uses are permitted within the shoreline protection zone established by this article: Access canals or channels; Docks; Elevated boardwalks; Other structures elevated on pilings; Utility lines, crossing or rights-of-way. Sec. 4-20. Uses permitted upon special approval; special exception uses. The following uses are permitted by special approval of the zoning board as provided by the provisions of chapter 19, article IV of this Code of Ordinances. Access driveways and turnarounds for single-family residences. [Additionally] ... the follow- ing standards shall also be met before the zoning board may grant approval for a special exceptions use within the shoreline protection zone: The principal structure shall be located as close as possible to the landward edge of site so as to reduce driveway length. All access driveways and turnarounds shall provide for piped culverts under the access driveway and/or turnaround at appropriate intervals so as to maintain tidal regime. To secure a permit for development within the shoreline protection zone, whether for a permitted use or special exception use, it is incumbent upon the applicant to comply with the provisions of section 4-21, MCC. That section provides: No development permit of any kind shall be issued to any person to undertake any development within the shoreline protection zone without first obtaining a zoning clearance from the zoning official. An application for any development permit within the shoreline protection zone shall be referred to the zoning official. The materials to be referred to the zoning official shall include the following, in duplicate: Proposed site plan A natural vegetation map Other information as may be appropriate to determine the impact of the development on the natural functions of the shoreline protection zone. The placement of landfill within the shoreline protection zone is hereby prohibited and no permit shall be issued authorizing the same, except as provided in section 4-20 of this article. No application for a zoning clearance shall be approved and no permit shall be issued except upon a written finding by the zoning board 9/ that the proposed development will not encroach upon or destroy the value of areas within the shoreline protection zone or otherwise adversely affect those conditions and characteristics which promote shoreline stabilization, storm surge abatement, water quality maintenance, wildlife and marine resource habitats, and marine productivity. Lujan's proof in support of his request for a fill permit within the shoreline protection zone was deficient. He offered no natural vegetation map or proposed site plan, and offered no proof that his proposed activity would not encroach upon or destroy the value of the shoreline protection zone or otherwise adversely affect shoreline stabilization, storm surge abatement, water quality maintenance, wildlife and marine habitats, and marine productivity. Significantly, Lujan also failed to disclose his plans for the development or use of the island. Absent proof that the fill activity is designed to create an access driveway or turnaround for single-family residences, the deposit of fill within the shoreline protection zone is prohibited. 10/ Section 4-21(c), MCC. Under the circumstances, it is concluded that Lujan has failed to demonstrate that he is entitled to a special exception use which would permit the deposit of fill on the westerly access road or upon those lands lying within 50' upland from the landward limit of the shoreline mangroves (the shoreline protection zone). Lujan's failure to disclose the nature of his plans to develop the island also rendered it impossible to evaluate the criteria established by section 4-20(b)(1), MCC. The deposit of fill within those areas of Enchanted Island lying upland of the shoreline protection zone is governed by chapter 19, MCC. Pertinent to this proceeding, section 9-111, MCC, provides: (a) Deposit of Fill. No person shall engage in the deposit of fill within the unincorporated areas of Monroe County, without first having obtained a county permit for such activity. (1) Definitions. Deposit: The act of placing, discharging or spreading any fill material. Fill: Any material used or deposited to change elevation or contour in upland areas, create dry land from wetlands or marsh in an aquatic area, or material discharged into a body of water to change depth or benthic contour. * * * Uplands: Land areas upon which the dominant vegetative communities are other than species which require saturated soil for growth and propagation. Wetlands: Aarshes and shallow areas which may periodically be inundated by tidal waters and which are normally characterized by the prevalence of salt and brackish water vegetation capable of growth and reproduction in saturated soil, including but not limited to the following species: * * * Black mangrove Buttonwood Red mangrove White mangrove * * * * * * * * * * * * Upland permit application. In reviewing all applications for a permit in upland areas, consideration will be given to the nature of indigenous vegetation, and protection of same as defined in chapter 18 of the Monroe County Code, which set standards for the removal of endangered and protected vegetative species, and to drainage patterns and the possible effects the deposit of fill would have upon water and storm runoff. * * * Wetland permit application. In reviewing all applications for a permit in wetland areas, consideration will be given to the natural biological functions, including food chain production, general habitat, nesting, spawning, rearing and resting sites for aquatic or terrestrial species; the physical aspects of natural drainage, salinity and sedimenta- tion patterns, physical protection provided by wetland vegetation from storm and wave action. The proposal will also be reviewed in conjunction with chapter 4 of the Monroe County Code, which provides for the protection of wetland vegetative communities within Monroe County. When reviewing applications for fill permits, whether within or without the shoreline protection zone, the provisions of Chapter 18, MCC, and the Monroe County Comprehensive plan, which deal with land clearing, must also be evaluated. Pertinent to this case, chapter 18 provides: Sec. 18-18. Land clearing permit -- Required ... It shall be unlawful and an offense against the county for any person, either individually or through agents, employees or independent contractors, to clear, by mechanical or any other means, any land located within the unincorporated areas of the county without having first applied for and obtained a land clearing permit from the building department of the county. A land clearing permit shall be required for the removal of all or parts of naturally occurring vegetation in the county. * * * Sec. 18-19. Same -- Application (a) Any person requesting a land clearing permit shall file an application with the county building department on a form provided by such department. Such application shall contain the following information: * * * A map of the natural vegeta- tive communities found on and adjacent to the site, prepared by a qualified biologist, naturalist, landscape archi- tect or other professional with a working knowledge of the native vegetation of the Florida Keys ... With projects that are five (5) acres or more in size, the vegetation map does not have to identify the location of individual trees. For projects of this size, the vegetation map should identify the different vegetative communities, such as tropical hammock, mangrove and buttonwood transitional, and be accompanied by a descriptive narrative that identifies any significant trees or natural features of the side (sic). An overall site plan of the land for which the permit is requested, indicating - the shape and dimensions of said land, the purposes for which clearing is requested, and the steps taken to minimize effects of clearing on surrounding vegetation and water bodies. A site plan analysis prepared by a qualified individual, as described above in (3), shall be included. * * * Sec. 18-21. Same -- Approval. After an application for a land clearing permit has been filed and verified, the building department and the planning and zoning department shall review and consider what effects such removal of vegetation will have upon the natural resources, scenic amenities and water quality on and adjacent to the proposed site. Upon finding that such removal of natural vegetation will not adversely affect the natural resources, scenic amenities and water quality adjacent to the proposed site, the permit shall be approved, approved subject to modification or specified conditions, or denied. In the event a request is denied, the reasons for denial shall be noted on the application form and the applicant shall be so notified. Pertinent to this case, the Monroe County Comprehensive Plan, Coastal Zone Protection and Conservation Element, provides: NATURAL VEGETATION MANAGEMENT POLICIES In recognizing the need to preserve as much natural vegetation as possible, the County will direct its land use and development regulations to minimize destruction of natural vegetation and modification of landscape. Guidelines and performance stan- dards designed to protect natural vegetation from development will be developed and enforced. Clearing of native vegetation for development will be controlled. Land clearing will be restricted to site area being prepared for immediate construction. If the construction cannot begin within reasonable time, the cleared area will be replanted with ground cover. * * * 3. Regulations controlling development in areas characterized primarily by wetland vegetative species such as mangrove and associated vegetation will emphasize preservation of natural vegetation to the maximum degree possible. Local regulations in this regard will be consistent with the appropriate State and Federal regulations. 8. The existing County ordinances designed to protect and conserve natural vegetation will be strictly interpreted, rigidly enforced, and/or amended when necessary. Lujan violated the provisions of sections 9-111 and 18-18, MCC, when he, without benefit of a permit, leveled and cleared Enchanted Island of vegetation. Now, after the fact, he requests the appropriate fill and land clearing permits; however, he offers no vegetation map, no plan to mitigate the removal of endangered and protected species, and no proof as to the drainage patterns on the island and the probable effect the deposit of fill or the removal of vegetation would have upon storm runoff or water quality. While no vegetation map was submitted, the proof at hearing did establish the general nature of the vegetation existent on the island prior to clearing. That proof established that the mangrove community previously located at the center of the island reposed in relative isolation, and that its natural biological functions were nominal. Consequently, the removal of that vegetation was not counterindicated from the biological function perspective; however, the impact of such removal and the filling of that area on storm runoff and water quality was not addressed by Lujan. Further, Lujan offered no plan to mitigate the impact caused by his removal of Bay Cedart, and endangered species. With respect to the access road, Lujan offered no vegetation survey, and the proof was insufficient to assure that only minimal clearing would occur. Additionally, Lujan offered no proof concerning the impact that such removal, if any, and the deposit of fill would have on drainage patterns, storm runoff, or water quality. The premises considered, it is concluded that Lujan has failed to demonstrate his entitlement to a fill permit or land clearing permit for Enchanted Island and the access road. In addition to the reasons set forth in paragraphs 27-28, supra, Lujan has also failed to address the issues of storm runoff and water quality.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Florida Land and Water Adjudicatory Commission enter a Final Order reversing Monroe County's decision to issue the subject permits No. 14723A and 14724A, and deny Lujan's request for a land clearing and fill permit for Enchanted Island and the westerly access road. That such Final Order specify those items set forth in paragraph 10, Conclusions of Law, as the changes necessary that would make Lujan's proposal eligible to receive the requested permits. DONE AND ORDERED this 9th day of April, 1987, in Tallahassee, Florida. WILLIAM J. KENDRICK Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of April, 1987.
Findings Of Fact The dredge/fill project sought to be permitted involves a proposed residential lot located on Lake Padgett in Pasco County. The tract is also adjacent to a canal dug by the Applicant and his father. The Applicant, Michael Millen, acquired this property from his father, Otis Millen, who continues to own other property in this area. Petitioner is an adjoining landowner, and also acquired his property from Otis Millen. DER prematurely issued the proposed permit 1/ on August 9, 1984. If reissued, this permit would allow the Applicant to develop a residential lot by filling a portion of a cypress swamp and creating compensating wetland elsewhere on his property. Additionally, the Applicant agrees to dedicate a three acre "conservation easement" and to install a culvert to improve drainage. The advantages of this project include the creation of a homesite where none is available now, acquisition by the State of three acres of dedicated wetland (conservation easement) and improved drainage through the culvert installation. There would be no net loss in cypress swamp area. The disadvantages include temporary turbidity in surrounding waters and some tree removal in the construction area. The Applicant would replace any trees removed through replanting. The Applicant also seeks permits to build a "summer kitchen" over jurisdictional wetlands and to fill the lakefront area with white sand. These "add-on" permit requests are not properly a part of this proceeding, however, and were not contemplated in the application at issue here. DER's expert witness gave only limited testimony on their feasibility during the rebuttal phase of this hearing. Petitioner has raised numerous objections to all the proposed projects, but principally to the one at issue here. He was not notified of DER's intent to grant the dredge and fill permit, and became aware of the project only after he observed construction activity. It was determined that DER had failed to notify him through an oversight of that agency or the Applicant. Petitioner points out that lot development is not being done in accordance with the (proposed) permit. He noted that trees have been cut down, fill was dumped in the canal and work on canal banks was taking place, all in contravention of permit conditions. Petitioner believes DER has acted improperly in tolerating the Applicant's unpermitted construction activity. To support this charge, he called as a witness a neighbor who had placed white sand on his lakefront property, but was required to remove it by DER enforcement personnel. The Applicant, on the other hand, has placed white sand on his beachfront property without a permit, and DER is assisting him in obtaining an after the-fact permit. Petitioner proved, through a series of aerial photographs, and the testimony of both expert and lay witnesses, that the canal which separates his lot from the Millen properties was constructed between 1976 and 1977. DER had jurisdiction at that time, 2/ but no permit was ever sought or obtained. The canal was dug as a "joint venture" of the Applicant and his father. It connects Lake Padgett with a drainage pond several hundred feet behind the lake. This canal has changed area drainage causing one nearby resident to experience periodic property flooding as a result. Prior to the canal's construction, a small drainage ditch with an earthen or cement dam did exist in the general area. However, the canal construction removed the dam and greatly enlarged the size and capacity of the previous ditch. Expert interpretation of aerial photographs revealed that a substantial number of mature cypress trees were removed in conjunction with the Millens' canal project. Some cypress trees were also cut for the recent (unpermitted) construction of the "summer kitchen" by the Applicant. He also constructed a dock which was later determined to be exempt by DER. Again, the Applicant had not obtained DER approval for the dock and had, in fact, been advised to stop construction until a determination of permitting requirements, if any, was made. Petitioner attempted to show a conflict of interest within DER. However, the fact that one DER field representative knew Otis Millen did not demonstrate such a conflict. Rather, DER's enforcement policies have been lax or inconsistent primarily due to a shortage of field personnel.
Recommendation From the foregoing, it is RECOMMENDED: That the Department of Environmental Regulation reissue Permit No. 510852383 to Michael A. Millen. DONE and ENTERED this 24th day of September, 1985 in Tallahassee, Florida. R. T. CARPENTER, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of September, 1985.
The Issue Whether the Mosquito Ditch Exemption of Section 373.4211(25), Florida Statutes, applies so as to exclude Petitioners' property adjacent to Miguel Bay in Manatee County from the permitting authority of the Department of Environmental Protection? If not, whether Petitioners are entitled to an Environmental Resources Permit from the Department?
Findings Of Fact The Property Not far from the southern terminus of the Sunshine Skyway Bridge spanning the waters where Tampa Bay and the Gulf of Mexico meet is a subdivision known as San Miguel Estates. On the western shore of Terra Ceia Island in Manatee County, it takes its name from an adjacent body of water: Miguel Bay. Miguel Bay is classified by rule of the Department of Environmental Protection as Class II surface waters meaning it has been designated usable for "Shellfish Propagation or Harvesting," Rule 62.302-400(1), Florida Administrative Code. The classification is the highest available to surface waters which are not fresh. As a part of the Terra Ceia Aquatic Preserve, Miguel Bay also enjoys the status of an Outstanding Florida Water, so designated by the Environmental Regulation Commission to confirm its worthiness to receive special protection because of natural attributes. See Rules 62- 302.200(17) and 62-302.700(9)(h)39., Florida Administrative Code. The bay surrounds the subdivision together with two bayous, Custer to the northwest and Tillette to the southeast. The mouth of Tillette Bayou is formed by Boots Point, also a part of Terra Ceia Island and the subdivision jutting into the bay directly north of the point. The bay surrounds or washes onto the shores of a number of keys: Sister, Skeet, Ed's, and Rattlesnake. Through the middle of the subdivision runs a county- maintained road: Miguel Bay Drive. It provides access to a cul- de-sac containing seven lots. Lots 2, 6, 7, and 8 are fully improved with residential structures, boat docks and elevated walkways. Lots 3 and 4 are undeveloped. An application for a permit to construct a house on Lot 3 was denied in the early part of this decade. It is uncertain whether Lot 4 is permitted for a residential structure but an application for a permit to construct a boardwalk on the property is pending. The lot owned by the petitioner and his wife, also undeveloped, is Lot 5. Consisting of approximately 5.5 acres on the south side of Miguel Bay Drive, Lot 5 is within the geographical jurisdiction of the Southwest Florida Water Management District. It contains wetlands contiguous to the bay. The wetlands have suffered various disruptions over the years. In addition, to mosquito ditches dug more than 30 years ago, a dike was built around the same time to prevent the gulf tide from flowing onto the property. Furthermore, part of the property was cleared at one time as part of an agricultural venture. On its northern side, adjacent to Miguel Bay Drive, is the property’s approximate 0.9 acres of uplands. On the opposite side of the lot, where the wetlands meet the bay, the Petitioners plan a boat basin. A section of the proposed boat channel serving the basin, where it connects to the bay, is located within the Outstanding Florida Waters boundary of the bay. The boat basin will be part of a residential project planned by Mr. and Mrs. McGinnis. In addition to an access drive and the boat basin and channel, the Petitioners plan to build a house in the middle of the lot. In the mid-1960’s, Lot 5 was ditched for mosquito control. The mosquito control ditches transect the property along two lines running roughly east-west: one, just to the south of the uplands, not too far from the road; the other, just to the north of the dike and a mean high-water line approximated by Mr. and Mrs. McGinnis’ engineer, John Benson. Valuable Mangroves Mangroves cover the bulk of the property south of the uplands. Most are normal-sized. For example, “[a]ll the mangroves up . . . at the mosquito ditch going toward the . . . street [are] huge, . . . 10, 15, 20 feet.” (Tr. 41.) The mangroves closer to San Miguel Bay, too, are normal-sized. But in a basin in the center of the property there is an acre or so of “stunted mangroves that [are] only . . . three to four feet tall." (Tr. 39.) "And that [is] very unusual . . . there [is] obviously something wrong with them.” (Tr. 40-41.) The problem for the stunted mangroves is stress in their root zone due to "anoxia in the soil, that is, lack of oxygen." (Tr. 318). The anoxia is most likely a function of location: the stunted mangroves are in a basin surrounded by the mosquito ditches. The normal-sized mangroves are not experiencing anoxia because they are better irrigated. Those alongside or in the mosquito ditches are irrigated by the water which collects in the ditches while those in the southernmost part of the property are irrigated by tidal froth from the bay. Although the property has been ditched, diked and bermed (and may have even been tilled at one time for agricultural purposes after it was cleared), the mangroves on the property serve a valuable ecological function, particularly to the bay. The height of the mangroves does not alter their ecological value because the value is largely in their root system. The entire root system of the mangroves covering over four-fifths of the property serves as a filtration base for water running off the uplands. It provides, moreover, critical habitat for commercially important species such as redfish and snook. Building a residence in the middle of this mangrove swamp, even were it to disrupt only the stunted mangroves, would cause adverse ecological impact. The adverse impact would fall heavily on the bay because it needs the natural flushing action allowed by the uninterrupted tangle of mangroves covering more than four acres of the five and one-half acre plot. At the same time, wildlife enjoy orderly habitat in the mangroves on the property. The presence of a residence and the alterations to the property, particularly the loss of well over an acre of a mangrove root-system caused by dredging and filling to support the residence, would render the remaining mangrove wetlands on the property much less supportive of the wildlife inhabiting it now and the wildlife that would otherwise inhabit it in the future. The Parties Petitioners moved to Florida from Illinois in 1991. Mel McGinnis is a double above-the-knee amputee who walks with the aid of prosthetic devices. Pamela McGinnis is a licensed real estate broker. Mr. and Mrs. McGinnis live in Palmetto where Mrs. McGinnis conducts her real estate business. The Department of Environmental Protection is the state administrative agency with permitting authority under Part IV of the Florida Water Resources Act of 1972, Chapter 373, Florida Statutes and Chapters 62-330, 62-341 and 62-343, Florida Administrative Code, as well as Section 404 of the federal Clean Water Act (33 U.S.C. 1344). Pursuant to operating agreements executed between the Department and the Southwest Florida Water Management District (SWFWMD) via the authority of Chapter 62-113, Florida Administrative Code, the Department is responsible in this case for reviewing the permit application of the Petitioners. Manasota-88, Inc., filed a petition to intervene which was granted subject to proof of standing at hearing. No proof of standing was offered, however; Manasota-88's status as an Intervenor has been rescinded and it has been dismissed as a party to the proceeding. See Paragraphs 78 - 81, below in the Conclusions of Law section of this order. Acquisition of the Property In 1993, Mel and Pamela McGinnis purchased Lot 5 in San Miguel Estates. They were attracted to the lot because of the more than 500 feet of waterfront it enjoyed on Miguel Bay. The seller of the property was the federal government. The sale was arranged through the United States Marshall’s office as part of a forfeiture proceeding. The property had been seized by federal authorities because of the illegal involvement in drug activity of its owner at the time of the seizure. Prior to a decision to make the purchase, Mr. and Mrs. McGinnis were concerned about clear title because of the property's shadowy history. They researched the matter at the county offices. Their concerns were allayed when they found no liens and discovered the property was part of a platted subdivision. They inquired whether there would be water or sewer services provided by local government. The county reported plans to put water lines in soon, a promise made good in 1994. In testimony, Mrs. McGinnis summed up the results of the pre- purchase investigation: “We really didn’t perceive [there] to be a problem.” (Tr. 22.) Plans to Develop and an Application for an ERP In 1995, the McGinnises began planning the construction of the residential structure and boat dock on Lot 5. Accompanied by their engineer, John Benson, they met on the site in August of 1995 with Ken Huntington, an environmental manager in the Environmental Resources Permitting Section of the Department. Before the meeting, the McGinnises believed the mosquito ditches to be creeks. After John Benson corrected the misimpression, Mr. Huntington indicated there was a possibility the property might qualify for a mosquito ditch exemption from environmental resource permitting. Mr. Huntington did not make a commitment, however, at this early stage of the case's development that the Department would determine the exemption applied. In fact, the Department insisted that an application for an Environmental Resources Permit be filed before a decision could be made on the exemption. Mr. and Mrs. McGinnis, on October 5, 1995, applied for the Environmental Resource Permit. The application sought authority to dredge and fill in waters of the state for the purpose of constructing a single-family residence, driveway, swimming pool and boat channel and basin. It showed the construction to have impact upon approximately 1.61 acres of wetlands. About 1.39 acres of the affected area would be cleared and filled for the construction of the home, pool, and driveway. The remainder of the area under impact (about .22 acres) would be excavated for the construction of the boat basin and channel. Two months later, in December of 1995, Mr. and Mrs. McGinnis submitted additional application materials. The submission consisted of several parts: a written statement from Larry Rhodes, the Mosquito Control Director for Manatee County from 1961-94; a proposed work order of the mosquito control district from 1966; information from their engineers; and, aerial photographs from 1960 and 1965. These materials were intended to support the assertion that Lot 5 was eligible for a mosquito control exemption from Environmental Resource Permitting. Preliminary DEP Action On April 1, 1996, a Preliminary Evaluation Letter was sent to Petitioners by the Department. The letter stated that based on site inspection, "it appears that the project cannot be recommended for approval." Petitioners' Exhibit 1-h. Cautioning that the preliminary evaluation did not represent final agency action, the letter went on to provide modifications which would reduce or compensate for the project's negative impacts. Among them, was "relocation of the proposed structure to a more landward location." Id. The letter was not preliminary in one way. It explained the Department’s final position that the project site did not qualify for the mosquito ditch exemption: As indicated in previous Department correspondence of January 19, 1996, the Department does not believe that the project meets the . . . exemption. Pursuant to 40D- 4.051(14), Florida Administrative Code, the subject exemption applies only to 'lands that have become surface waters or wetlands solely because of a mosquito control program, and which lands were neither wetlands nor other surface waters before such activities . . .' Historical aerial photographs do not support that the parcel was not previously wetlands. Id., at pg. 2. Ten days later, Mr. and Mrs. McGinnis, through their attorneys, requested a one-week extension to submit revised plans "which attempt[] to reduce the impacts in response to the issues . . . raised [by the April 1 correspondence]." Petitioners' Exhibit 1-i. In a letter dated April 17, 1996, Mr. McGinnis submitted the revised plans in the form of proposals designed by Benson Engineering and CCI Environmental Services. As a prelude to the proposed modifications it had designed, Benson Engineering wrote, We have spent considerable effort to reduce the negative impacts with out (sic) placing the development in the unacceptable upland. The location of the residence has been chosen due to the nature of the stressed mangroves. This area (approximately 1.6 acres) is characterized in a report by H. Clayton Roberson, Environmental Scientist with CCI Environmental Services, Inc. dated 29 January, 1996. The majority of the mangroves to be impacted are less than 3 feet in height, with atypical stunted growth. The current proposal reduces the impacts to only 45% of the stressed area, and only 24% impact to the total site. This 24% development ratio is also being mitigated with enhanced water circulation to the entire site, . . . Petitioners' Exhibit 1-j. In the cover letter submitting the proposed modifications, Mr. McGinnis' frustration at this point with the process was evident. At least two of the items in the letter demonstrate its depth: Property was purchased by us from the government with no disclosure by anyone or any recorded documentation that would have given us even a hint that building our home would become such a nightmare. This property is in a long established recorded subdivision, and all adjacent property owners are either built, under construction or permitted to build. Our property as submitted to you under the revised design is compatible with the surrounding neighborhood. Placement of any dwelling on the road will have a major negative impact on this parcel. I cannot stress enough the negative economic impact that would be incurred by this action. Petitioners' Exhibit 1-j. Denial On May 1, 1996, the Department issued its Notice of Denial. The notice contained five parts: I. Description of the Proposed Activity; II. Authority for Review; III. Reasons for Denial; IV. Proposed Changes; and V. Rights of Affected Parties. Part III of the notice (Reasons for Denial) cited a June 1995 site inspection. It included a description of the site: 5.5 acres, the majority of which, according to a 1952 Soil Conservation Service survey, is Tidal Swamp, and according to a 1983 Soil Survey is classified as Wulfert-Kesson Association soils. The site had been found during the inspection to be dominated by mangroves, red, black and white. Other vegetation associated with wetlands had been observed "within the subject system at the time of inspection" (Petitioners' Exhibit 1-k) as well as Marsh periwinkle, Fiddler crabs, tricolered heron, greenback heron, and snowy egret. The project was found, moreover, to result in 1.61 acres of impact to a mangrove community with wetlands in a Class II waterbody directly contiguous to an aquatic preserve. After detailing the value and significance of mangroves to habitat and water quality functions and the applicant's failure to provide reasonable assurance that the construction and operation of the activity, considering direct, secondary and cumulative impacts, would comply with the provisions of Part IV of Chapter 373 and the rules adopted thereunder, Part III of the notice recited two primary bases for the denial. First, the immediate and long-term impacts of the activity were expected to cause violations of water quality standards. Second, the project was found to be contrary to the public interest for those portions of the activity located in, on or over wetlands or other surface waters. With regard to water quality, the Department found the project did not meet standards applicable to biological integrity, transparency, and turbidity. The project was expected, furthermore, to cause: adverse water quality impacts to receiving waters and adjacent lands; adverse impacts to the value of functions provided fish, wildlife and listed species by wetlands and other surface waters; and adverse secondary impacts to water resources. With regard to the public interest test for those portions of the activity located in, on or over wetlands or other surface waters, the Department expected the project to adversely affect the conservation of fish and wildlife, including endangered or threatened species and their habitats; adversely affect navigation or the flow of water or cause harmful erosion or shoaling; adversely affect the fishing or recreational value or marine productivity in the vicinity of the project, among other adverse impacts; and fail to meet standards imposed by law. Despite the existence in the Department's opinion of numerous substantial bases for denial, the Department offered hope to Petitioners that they might yet be able to build a residential structure on Lot 5. The first of changes to the project listed in the notice that might "enable the Department to grant a permit," Petitioners' Exhibit 1-k, was for Petitioners to "[r]elocate the proposed residence to a landward location-in proximity to the existing road which would result in a significantly minimized wetland impacts." Id. Other modifications included submission of an acceptable mitigation plan and addressing cumulative impacts, perhaps by way of granting a conservation easement. In response, the McGinnises modified their proposal. But the modifications did not include moving the residence into the uplands at the northern end of the property. The Department considered the changes to the proposal but the changes did not, in the Department's view, make the project permittable. (See Tr. 155). Environmental Dispute Resolution On May 15, 1996, a few weeks from the issuance of the Department's Notice of Denial, Mel and Pamela McGinnis filed a Request for Relief under the Florida Land Use and Environmental Resolution Act, Section 70.51, et seq., Florida Statutes. The Department filed a response to the request and parties participated in a hearing and mediation in accordance with the Act. A hearing was held on September 18 and 19, 1996, before Special Master Raymond M. McLarney who referred to the event as the "first Special Master Proceeding in Property Rights with the FDEP and a landowner." Petitioners' No. 4, Special Master Summary Report, Ex. 1a, p. 1. 36. Paragraph 4 of the Report Summary, bearing the heading, "Special Master's Initial Observation," states: Following completion of the hearings . . ., the Special Master concluded and communicated to the parties that the FDEP's Notice of Denial unreasonably and/or unfairly burdens use of the McGinnises['] real property. The Special Master's initial observation and conclusion was provided to the parties to serve as an indication of sufficient hardship to support modification, variances or special exceptions to applicable statutes, rules, regulations or ordinances of FDEP as applicable to the subject property, all as authorized by Section 70.51(25) of the Florida Statutes. The Special Master encouraged the parties to mediate their differences and attempt to seek a mutually- acceptable solution through the process of mediation. The parties agreed. Id., at 4. The Special Master's Report Summary reports that the result of the mediation was that "the McGinnises and FDEP reached a mutually-acceptable solution evidenced by an [attached] agreement . . . incorporated herein. The . . . solution . . . was initialed/signed on each page by authorized representatives of the parties and was accomplished in accordance with Section 70.51(19)(c) of the Act." Id., at 5. The “Initial Observation” section of the Report Summary appears to contain what would have been the Special Master’s Recommendation (that is, the conclusion that the Department’s actions “unfairly burdened the Petitioners’ use of the property”) had the Special Master not thought that the Department and the McGinnises had reached a mediated agreement. Whatever the appropriate characterization of this section of the report, the Department treated it as a recommendation. It did so when it declared the Special Master’s Report Summary null and void several months after receiving it. Null and Void On January 29, 1997, the Department received the Special Master's Report Summary. By order dated March 14, 1997, the Department rejected its "recommendations." Petitioners' Exhibit 4, Order, p. 1. Under an overarching declaration that the report summary was null and void (amounting to a declaration that the entire proceeding was null and void) the order detailed essentially four bases for the rejection: a. the hearing that led to it was not open to the public as required by the Act; the report was not timely submitted; c. the proceeding had not satisfied other requirements of the Act besides public openness and therefore was inadequate; and d. the report incorrectly concluded that the Department and the McGinnises had reached a mutually-acceptable solution. Allegations of the Petition In the body of the petition which initiated this case, Petitioners refer to the Special Master proceeding as one which led to a mediated agreement. They also make reference to the Department’s rejection of the Special Master’s recommendation. See Petition, paragraph 11, p. 3. But although they seek “[s]uch other relief as may be just and appropriate under the circumstances [of the case],” Petition, paragraph 12.c., p. 5, they do not plead in the petition that the rejection was either wrong as matter of law or action for which they specifically seek relief. Instead of challenging the Department’s rejection of a recommendation by the Special Master or the Department’s declaration that his Report Summary was null and void, the petition challenges only two decisions of the department. One is the Notice of Denial determining the Petitioners not entitled to an Environmental Resource Permit. The other is the decision that the project is not exempt from permitting because of effects caused by the mosquito control ditches. The Days of Mosquito Ditching Long before the Legislature enacted the Florida Land Use and Environmental Dispute Resolution Act to address unreasonable burdens placed on land owners by governmental regulation, local governments were confronted by issues less abstruse. The Manatee County Commission, for example, was striving to eradicate mosquito infestation along its coastline. One of the tools the county used in its efforts was ditching. Mosquito ditches were installed in uplands and fresh waters throughout Manatee County but they were excavated mainly in the salt marshes along the county’s coastline because "the biggest [mosquito] problem in Florida is coastal mosquitoes." (Tr. 105). Larry Rhodes, presently a resident of Terra Ceia and a long-time resident of the area, was the Director of Manatee County Mosquito Control at the time the mosquito ditches were dug across the McGinnis property. His tenure as director ended in 1994. It spanned a period of more than 33 years, having begun in 1961. Shortly after the commencement of Mr. Rhodes’ tenure, but prior to some of the canal construction by the developers of nearby Terra Ceia Estates, the McGinnis property was cleared almost entirely. Except for a small wet area of black mangroves, the property had been dominated by wax myrtle, guava and Brazilian Pepper, an invasive exotic in the process of pushing out the other dominant species. The clearing by the developers of Terra Ceia Estates, personally observed by Mr. Rhodes, was done at the time of installation of a system of canals. Around the canals a waterward dike was placed in order to keep the tides from Miguel Bay from inundating the property. The clearing shows up in an aerial photograph taken in 1965. Soon after the aerial was taken and developed, the mosquito ditches were excavated. Approved by the State Board of Health in 1966, the ditches were dug through the McGinnis property during that year or the next, when the mosquito ditch system in the area of San Miguel Estates was completed in 1967. As the result of the ditching, with the exception of the spoil banks where Brazilian Pepper took over, mangroves proliferated over the formerly-cleared land. Red mangroves grew "up [in] all the ditches and then black and white mangroves in other areas." (Tr.122). Maps, Aerial Photographs, and Soil Surveys The status of the property as cleared thirty-odd years ago and the subsequent generation of mangroves produced in the intervening years over most of the property, including alongside and in the mosquito ditches, did not mean necessarily that the cleared area had not been wetlands prior to the clearing activity. The Department, therefore, confronted with the Petitioners’ claim of a mosquito control exemption, set out to investigate. The investigation was necessary because entitlement to the exemption turns on whether the nature of the property as wetlands after the clearing was due solely to the excavation of the ditches. The investigation consisted of reviewing aerial photographs, maps and soil surveys and later required resort to expert opinion from outside the department. After an initial review conducted by Ken Huntington and Rose Poyner, another Department staff member, the Department contacted GIS analyst Robert P. Evans of the Southwest Florida Water Management District. As a GIS analyst, Mr. Evans’ primary functions (conducted for more than 25 years for the district) are GIS mapping and interpretation of aerial photographs. Mr. Evans reviewed a series of aerial photographs beginning with 1940 black and white photographs and ending with infrared photos from 1990. A 1940 Natural Resource Conservation Service (NRCS) photograph showed that the site of the McGinnis' proposed project consisted of mangroves that year. A copy of a 1951 NRCS aerial photo showed mangroves on the site as did a copy of a 1957 aerial photo. After review of the photos, Mr. Evans was of the opinion that the site of the proposed project was wetlands and had been so historically, that is, before the ditches approved and excavated in the mid-sixties. Rick Cantrell, the Administrator of the Wetlands Evaluation and Delineation Section of the Department, the "Administrator [of wetlands delineation] for the whole Department in the whole State of Florida," (Tr. 306), and an expert in aerial photo interpretation for purposes of wetlands delineation, also reviewed aerial photos of the site. Mr. Cantrell reached the opinion that the property had been historical wetlands, just as had Mr. Evans. In the meantime, Mr. Evans was hard at work seeking independent confirmation of his opinion. First, he reviewed United States geological surveys of the site. The 1969 revision of the 1964 edition of the Palmetto USGS Quad map of the area, based on an aerial photograph taken in 1951, shows the McGinnis project site was wetlands prior to the ditching. Not content to rely on the authoritative evidence of aerials and official federal geological survey maps, Mr. Evans sought out another source: soil surveys. These, too, confirmed the historic existence of wetlands on the site. Favored with Mr. Evans’ opinion, the Department contacted Juan Vega, a soil scientist, and asked him to use his expertise in both soil survey review and site testing to assist the inquiry. Mr. Vega agreed to look into the issues. He examined two soil surveys: a survey of Manatee County soils issued in December of 1958 by the United States Department of Agriculture's Soil Conservation Service in cooperation with a Florida Agricultural Experiment Station (Respondent's Exhibit 8) and a subsequent Soil Survey of Manatee County conducted by the federal Soil Conservation Service in cooperation with the University of Florida and other state entities (Petitioner's No. 9). The second survey, "done in '79 or '80," (Tr. 286) was a recorrelation of the first. The first survey shows the site to be tidal swamp as is all of Lot 5 with the exception of the less than one acre of uplands on the property's northern border. Vegetation in tidal swamps is usually mangroves in abundance. As one would expect from their denomination, tidal swamps are influenced by salt water tides, contain tidal soils and are generally wet. The 1979-80 survey indicated that the soil found on the site is Wulfert-Kesson Association. This soil is characterized by an accumulation of organic materials and ore black minerals on the surface, a process known as gleying. Gleying is caused by saltwater inundation and tidal effects and therefore, of course, is indicative of the presence of hydric soils in a wet area. The soil surveys led Mr. Vega to conclude that the site of the project was composed of historic wetlands. Field Testing The Department's interest in having Mr. Vega conduct soil testing on the site of the project was not fruitful. Access to the site was denied. In lieu of on-site testing, therefore, Mr. Vega conducted soil analysis nearby, a few hundred feet to the east of the proposed site. In March of 1996, he dug several holes, one near the road and others adjacent to the mangrove area of Lot 5. The soil near the road was Bradenton, "pretty much natural native soil." (Tr. 289). The soil from the other areas, buried under approximately two feet of fill, was Wulfert and Kesson, both hydric soils. There was also present a layer of muck, that is, decomposed organic material. It indicated that the soil had not been converted from uplands to wetlands but rather that the soil had been wetlands historically. The field testing conducted by Mr. Vega on the adjacent site confirmed his opinion that the site of the proposed McGinnis project was wetlands and had been so historically. Historic Wetlands The evidence on the issue of the property's status is summarized as follows: United States Geographical Survey maps indicate the area of Lot 5 in San Miguel Estates to be historic wetlands; federal soil surveys confirmed by nearby soil testing and conducted with the cooperation of the State of Florida indicate the presence of hydric soils on the lot; and aerial photographs show that mangroves existed on the site both before the clearing in the sixties and after the mosquito ditches were excavated in 1966-67. Although the proposed site contains mangroves stunted and suffering from the stress of anoxia today, and there are mangroves in and alongside the mosquito ditches dug as part of a governmental program in the 1960s which grew after the land had been cleared, Lot 5 in San Miguel Estates, with the exception of the approximate .9 of an acre alongside the road at the north end of the property, is comprised of wetlands that existed prior to the mosquito ditching activity. In short, Lot 5 is comprised of historic wetlands. The Permit Application Sovereign submerged lands would be affected by the project, a project permanent in nature. "[D]irect impact would be the excavation of the access channel from the boat basin to the water. So that last [scoop] of dirt, if you will, or piece of land separating the basin from Miguel Bay, that cut would be into the bottom of Miguel Bay, [an Outstanding Florida Water and part of the Terra Ceia Aquatic Preserve]." (Tr. 156). The proposed project would cause adverse impact to the quality of the receiving waters. The filtration function of the mangrove forest would be diminished and the boat basin would cut into the bottom of the bay within the aquatic preserve. Petitioners offered no evidence that water quality standards listed in Chapter 62-302, Florida Administrative Code, including those for biological integrity, transparency and turbidity would be met, all concerns listed by the Department in its Notice of Denial as a basis for its action on the permit application. Nor did Petitioners demonstrate that the dredging of the boat access channel in Miguel Bay would not violate ambient water quality standards, another basis for the Department's notice of denial. Any mitigation offered by Petitioners for the impacts of fill associated with construction of the access road and fill pad for the house were not adequate. "That fill will eliminate over half an acre . . . of mangroves and wetlands that are crucial to the eco system (sic) in Miguel Bay." (Tr. 157). In addition to the filtration these lost mangroves would have provided, "mangrove wetlands are vital for habitat, for fish and wildlife services." Id. Petitioners have not provided reasonable assurance that the boat basin would not create water quality violations, including dissolved oxygen concentrations falling below standards. Petitioners have not provided reasonable assurance that the proposed activity will not cause adverse secondary impacts that result from construction activities on the site. Secondary impacts include the establishment of nuisance species in disturbed areas. The property contains sufficient uplands upon which to construct the residential structure or at least enough of it to greatly minimize impact to wetlands. Siting a dock on the bay would obviate the need for the boat basin and channel. An associated boardwalk would eliminate the need to dredge wetlands populated by mangroves. Utilizing a dock and a boardwalk would save almost a quarter of an acre of wetlands from dredging. Mr. McGinnis' status as a double above-the-knee amputee may certainly be expected to create special needs, but other than to mention his disability, Petitioners made no showing that such a modification was not practicable in light of his condition. The proposed project would also present cumulative impacts to wetlands and other surface waters. There is significant development already in San Miguel Estates and there are other applications for development pending: for example, a permit application for construction of a boardwalk through wetlands submitted for the adjacent Lot 4. In sum, the project will have adverse water quality impacts, impacts to sovereignty submerged lands, secondary impacts, and cumulative impacts. Ways proposed by the Department of dramatically minimizing, reducing or preventing these impacts have not been accepted by Mr. and Mrs. McGinnis.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED: That the Department of Environmental Regulation enter a final order denying both the mosquito ditch exemption and the Environmental Resource Permit applied for by Petitioners, Mel and Pamela McGinnis, for the project in DEP Permit File No. 412783533. DONE AND ENTERED this 17th day of April, 1998, in Tallahassee, Leon County, Florida. DAVID M. MALONEY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 17th day of April, 1998. COPIES FURNISHED: Frank E. Matthews, Esquire Kimberly A. Grippa, Esquire Hopping, Green, Sams and Smith, P.A. Post Office Box 6526 Tallahassee, Florida 32314-6526 Douglas H. MacLaughlin, Esquire T. Andrew Zodrow, Esquire Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Thomas W. Reese, Esquire 2951 61st Avenue, South St. Petersburg, Florida 33712 Kathy Carter, Agency Clerk Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Perry Odom, General Counsel Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000
The Issue The issue for determination is whether Petitioner's revocation of Respondent's modified permit, authorizing a cross- fence on Petitioner's fee owned right-of-way, should be approved.
Findings Of Fact The South Florida Water Management District (District) is a public corporation in the State of Florida, existing by virtue of Chapter 25270, Laws of Florida (1949), and operating pursuant to Chapter 373, Florida Statutes, and Title 40E, Florida Administrative Code, as a multi-purpose water management district. The District's principal office is West Palm Beach, Florida. In executing its multi-purpose, the District, as local sponsor for the US Army Corps of Engineers' Central and Southern Florida Flood Control Project, acquired canal rights-of-way. The District's rights-of-way were acquired to enable the Corps of Engineers to construct the flood control project and to maintain the system after its construction. The District operates a proprietary-based right-of-way program to manage the various property interests of the canal rights-of-way. The purpose of the District's right-of-way program is, to the extent possible, to allow uses of the rights- of-way that do not conflict with the flood control project. The rights-of way are used by both public and private concerns, including adjacent property owners, governmental entities, and utility companies. Jesus G. Quevedo is a private individual. His address is 2615 North Federal Highway, Lake Worth, Florida. The property at this address was vacant when Mr. Quevedo purchased it, and he has owned the property for approximately ten (10) years. The District has fee simple title to a strip of land on the south side of the District's C-51 Canal, immediately west of the Federal Highway/Olive Avenue bridge (C-51 Right-of-Way). Mr. Quevedo's property is located at the side of and adjacent to the C-51 Right-of-Way. The C-51 Right-of-Way is also located within the boundaries of Spillway Park as established in the agreement between the District and the City of Lake Worth. Generally described, Spillway Park includes the District's fee simple owned right-of-way on the south side of the District's C-51 Canal, beginning at the west side of the Federal Highway/Olive Avenue bridge and continuing to the east side of the Dixie Highway bridge. Mr. Quevedo has no real property interest in the C-51 Right-of-Way. Prior to purchasing his property, Mr. Quevedo was aware that the District owned the C-51 Right-of-Way. Historically, portions of Spillway Park and the C-51 Right-of-Way, in particular, have been a unique and popular location for excellent snook fishing by the public. These areas continue to be considered as such. On February 11, 1993, Mr. Quevedo was issued SFWMD Permit No. 9801 (Permit), a right-of-way occupancy permit, by the District’s Governing Board. The Permit authorized him to make use of the District’s lands and works as follows: 20’ X 50’ BOAT DOCK WITH WALKWAY, BURIED WATER AND ELECTRICAL SERVICE, POP-UP SPRINKLERS, AND SODDING WITHIN THE SOUTH RIGHT OF WAY OF C-51 LOCATED IMMEDIATELY WEST OF THE OLIVE AVENUE/FEDERAL HIGHWAY BRIDGE. During the permit application process, but prior to the issuance of the Permit, Mr. Quevedo had discussed with the District's staff the erection of a cross-fence based on allegations of improper or criminal activities by members of the public. Subsequently, in November 1995, Mr. Quevedo again discussed with the District's staff erection of a cross-fence based on the same allegations but he also included a new allegation of public safety as to the C-51 seawall. Based on the concern for public safety, the District's staff recommended that Mr. Quevedo be granted a modification to the Permit for a cross-fence. On November 14, 1996, the District's Governing Board approved, as part of its consent agenda, and issued SFWMD Permit MOD No. 9801 (MOD Permit)3 authorizing the following: CHAIN LINK CROSS FENCE WITH 16’ VEHICULAR GATE ALONG THE WEST PROPERTY LINE WITHIN THE SOUTH RIGHT OF WAY OF C-51 LOCATED AT 2615 NORTH FEDERAL HIGHWAY. The MOD Permit, as did the Permit, provides in pertinent part on its face the following: The permittee, by acceptance of this permit, hereby agrees that he shall promptly comply with all orders of the District and shall alter, repair or remove his use solely at his expense in a timely fashion. . . . This permit is issued by the District as a license to use or occupy District works or lands. . . By acceptance of this permit, the permittee expressly acknowledges that the permittee bears all risk of loss as a result of revocation of this permit. The MOD Permit, as did the Permit, contained standard limiting conditions, as provided in Rule 40E-6.381, Florida Administrative Code, and special conditions. The limiting conditions provide in pertinent part as follows: Permittee agrees to abide by all of the terms and conditions of this permit, including any representations made on the permit application and related documents. . . . This permit does not create any vested rights, and except for governmental entities and public or private utilities, is revocable at will upon reasonable prior written notice. Permittee bears all risk of loss as to monies expended in furtherance of the permitted use. Upon revocation, the permittee shall promptly modify, relocate or remove the permitted use. In the event of failure to so comply within the specified time, the District may remove the permitted use and permittee shall be responsible for all removal costs. This permit does not convey any property rights nor any rights or privileges other than those specified herein. . . . Having been granted the MOD Permit, Mr. Quevedo erected the cross-fence within and onto the C-51 Right-of-Way. The C-51 Right-of-Way is located adjacent to Mr. Quevedo’s property, as indicated earlier, and continues westerly to the permitted cross-fence. The C-51 Right-of-Way is enclosed by the cross-fence, preventing access by the public, and is located easterly of the cross-fence. As the C-51 Right-of-Way is located within the boundaries of the Spillway Park, the cross- fence is also located within the boundaries of the Spillway Park. During the time that Mr. Quevedo has owned his home, including prior to and after erection of the cross-fence, he, his family members and/or guests have frequently fished from the C-51 seawall and used the C-51 Right-of-Way enclosed by the cross- fence. Prior to and after the erection of the cross-fence, Mr. Quevedo and his family members have selectively controlled access by the public to the C-51 Right-of-Way at the C-51 seawall. Prior to the erection of the cross-fence, Mr. Quevedo chased members of the public off the C-51 Right-of-Way. Mr. Quevedo and members of his family also called law enforcement officers to remove members of the public who were located on the C-51 Right-of-Way, even if the members of the public were fishing from the C-51 seawall. After the erection of the cross-fence, Mr. Quevedo and his family members continued to engage in this conduct of selective access. Subsequent to the erection of the cross-fence, Mr. Quevedo had a member of the public arrested for trespassing. The person allegedly jumped over or went around the cross-fence to fish from the C-51 seawall in the C-51 Right-of-Way. With the existence of the cross-fence, Mr. Quevedo has prevented the general public from using the C-51 Right-of-Way, including the C-51 seawall. As a result, he has acquired the exclusive, private use of the C-51 Right-of-Way at the C-51 seawall, which is publicly owned land, and has, almost doubled the size of his adjacent property without the obligations and expense of acquisition, assuming he could acquire the property through acquisition. The District's policy is that public land should be open to the public. Contrary to this policy, Mr. Quevedo's cross-fence precludes access to the District's right-of-way (C-51 Right-of-Way), including the seawall, for passive recreational use. Similar cross-fencing, although not within the boundaries of Spillway Park, have been erected behind residences on the northeast, northwest, and southeast sides of Federal Highway, along the District’s C-51 Canal bank. The cross-fencing prevents public use of the District’s C-51 Canal bank at these locations. The City of Lake Worth made improvements within the boundaries of Spillway Park; however, it made no improvements, and does not intend to make any improvements in the future, at the C-51 Right-of-Way where Mr. Quevedo’s cross-fence is located or at the other private lots west of Mr. Quevedo's property. All of the improvements made at Mr. Quevedo’s cross-fence at the C-51 Right-of-Way have been made by him even though the C-51 Right-of- Way is located within Spillway Park. The original public safety rationale for authorizing Mr. Quevedo to erect the cross-fence blocking public access was revisited by the District. Additional investigation by safety experts (Risk Management staff) revealed that no unreasonable danger existed by allowing public access to the C-51 seawall at the C-51 Right-of-Way. In the absence of the public safety basis for closure of the C-51 Right-of-Way, such closure was contrary to District policy. As a consequence, the District’s staff recommended to the District’s Governing Board that the MOD Permit, authorizing Mr. Quevedo’s cross-fence, be revoked. After conducting two public meetings and receiving comments from Mr. Quevedo, members of the public, and the District’s staff as to the policy issue of pubic access to the C- 51 Right-of-Way, the District’s Governing Board determined that the C-51 Right-of-Way should be open to the public. Consequently, the Governing Board decided to revoke Mr. Quevedo's MOD Permit. Allegations of criminal activity within the general boundaries of Spillway Park and, specifically, in the C-51 Right- of-Way at the cross-fence area, were made by Mr. Quevedo as a basis to not revoke the MOD Permit and allow the cross-fence to remain. Such allegations have no bearing on the revocation of the MOD Permit.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the South Florida Water Management District enter a final order revoking SFWMD Permit No. MOD 981 issued to Jesus G. Quevedo. DONE AND ENTERED this 8th day of March, 1999, in Tallahassee, Leon County, Florida. ERROL H. POWELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 8th day of March, 1999.
Findings Of Fact Respondent, Woodland, is made up of property owners in Woodland Lakes subdivision, an area abutting on Woodland Bayou, situated off Pensacola Bay in Santa Rosa County, Florida. Petitioner, Margaret B. Miller, owns property directly across the channel which forms the entrance to Woodland Bayou and which is the proposed location for the bulkhead and riprap forming the subject matter of this dispute. Mrs. Miller and her late husband purchased their property, which is not located in Woodland Lakes subdivision, in 1957. Their lot is located on Pensacola Bay and at the time she and her husband purchased the property, they were looking for an area that had the special characteristics of this lot she now owns. It included big trees, a gentle slope to the Bay, and a view out over Pensacola Bay across a sandy peninsula which extended out into the bay a considerable distance and which they owned. At the time they made their purchase, Woodland Bayou opened into Pensacola Bay at the East End but the opening near Mrs. Miller's property was obstructed by a sandy beach. The extent of channel blocking and obstruction caused by this sandy beach was the subject of a lawsuit between the Millers, the Woodland Lake Property Owners Association, and the State of Florida 1n June, 1972. The substance of that suit was concerned with ownership of the land which extended out from the Miller property into Pensacola Bay over which certain of the parties desired to cut a channel from Woodland Bayou into Pensacola Bay. There was substantial conflict in the testimony at the time as to whether there was a natural channel existing across the Miller property prior to 1957-1958 or not, or, in the alternative, whether the Millers filled in an existing channel thereby blocking reasonable entrance to Woodland Bayou. The answer to that question is irrelevant to the issue in this hearing. However, a judgment of the Circuit Court entered on June 13, 1972, awarded to the Millers title to property which extended out across the currently existing channel dredged subsequent to that time by the Respondent, Woodland, to a point into Pensacola Bay. The decision of the court also awarded to the Trustees of the Internal Improvement Fund a section of property directly west of the northern tip of the Miller property consisting of a strip approximately 40 feet wide and a maximum of76 feet long lying approximately perpendicular to the currently-existing channel and through which it was envisioned the channel would be dredged from the entrance of Woodland Bayou out to Pensacola Bay. By so doing, the canal would have made a left turn coming out of the bayou into Pensacola Bay but the Miller's property, which was not then split by the canal, would be left intact. According to Mr. Hunsley, the dredging completed after the entry of the final judgment in the Quiet Title suit was not done consistent with the dictates of that judgment. Instead, the channel was cut straight out from the bayou across the Miller property, and so it remains to this day. He contends, however, that historically, the channel existed in this very spot and that the Millers as well as other property owners in the area at the time, closed the channel off by dredging and filling at their own expense some time in 1957 and 1958. Regardless of the history regarding the genesis of the channel, however, the fact remains that the channel now exists in a straight line from Woodland Bayou to Pensacola Bay across the Miller property and has so since 1972 when it was dredged subsequent to the lawsuit. The channel, being a tidal channel and subject to sand drift caused by wind and wave action, tends to become clogged with sand on a periodic basis. Because of the increased clogging currently experienced, sometime prior to September 9, 1983, the officers of Woodland circulated a petition to secure the permission of all the neighbors in the subdivision to construct a bulkhead on the Woodland side of the channel across from and up channel from the Miller property. This petition, which at the time did not include riprap, was approved by all property owners in the subdivision except for 2 and was then forwarded to the Gulf Breeze City Council to allow the Council to assess costs in the amount of approximately $600.00 per property owner against the property owners in the event DER approved the permit to construct the bulkhead. Mrs. Miller was not solicited to sign the Petition nor will she be assessed any of the costs of construction of the bulkhead if approved since she is not a property owner in the subdivision in question. The petition was circulated, according to Mr. Kettenring, who has lived in the area for several years, because of the increasing sedimentation. To his knowledge, the channel was last dredged in 1982 and 1983. Prior to that time, during the period 1979-1981, he recalls at least three fish kills in the bayou but none since the dredging was accomplished. The residents of Woodland and the surrounding owners are all on septic tanks. There is no city sewage service to this area and every year there is a change in the clarity of the water in Woodland Bayou in the summer. During warmer weather, as the temperature increases, the water becomes cloudy and full of algae. However, after dredging was accomplished and the channel was opened further both in width and in depth, the water quality improved considerably. Mr. Kettenring has seen patterns of sand drifting from the point into the channel. The area has changed considerably in that the point has scalloped out into the channel blocking it. As a result, the bayou, which is at the mainland source of the channel, is currently somewhat brackish. Access of boat owners to the bayou has become impaired. On September 9, 1983, the application submitted by Woodland was received by DER, and a determination was made that the proposed project lay in Class III waters of the State, the standards for which are outlined in Rule 17-3.121, Florida Administrative Code. Shortly thereafter on September 28, 1983, DER notified Woodland that the application was incomplete in that the application fee had not been submitted, aerial photographs of the area were required, and a consent for the use of State-owned land was necessary. In addition, it was determined that Woodland needed to provide detailed plans for compliance with State water quality standards as well as a hydrographic survey. All requirements were subsequently met except for the survey. The application originally called for an additional 300 foot bulkhead to the east of the area in question here and the hydrographic survey referred to that bulkhead. Subsequent to the filing of the application, however, that bulkhead portion of the project was deleted and when that was done, the need for the hydrographic survey was obviated. Since all other shortcomings in the application had been corrected, the project was then reviewed by Mr. Hambrick who recommended the installation of riprap in front of the remaining bulkhead and grass, and on December 20, 1984, DER published an intent to issue for the project. The project in question is a 150 feet long bulkhead fronted with 35 cubic yards of riprap at the toe. The bulkhead will be located at the entrance channel of Woodland bayou across from Petitioner's property. Mr. Hambrick, who initially reviewed the application for DER and who signed off on it in December, 1984, visited the site in question on at least 2 or 3 occasions in relation to the application and because Mrs. York, Miller's neighbor, also had an application for a bulkhead pending. He looked at the property and determined that the amended application did not call for riprap. However, because the new law requires riprap in front of seawalls, he recommended that the riprap be installed here where there is no grass. In other words, according to Mr. Hambrick, riprap will be placed flush against the bulkhead where no sea grasses exist but will curve out in front of the sea grasses where there is grass at the foot of the bulkhead which will proceed behind the grassed area. The purpose of using riprap is to dissipate wave energy. Riprap will diminish the effect of the wave and its adverse effect on Petitioner's property. Mr. Hambrick is of the opinion that installing the bulkhead and riprap would not cause or increase damage to Petitioner's property and based on the criteria he used in analyzing the project, he feels that it is in the public interest. The factors he used in his consideration of this project include: that an erosion problem exists in the area, that bulkheading and riprapping would reduce the need for dredging, that there is a history of fish kills in the area, that maintaining a channel would help flush out the bayou, and homeowners on the bayou would have access to Pensacola Bay and their interests constituted a part of the public interest. Since the revised application was completed in October, 1984, it therefore had to comply with the criteria outlined in the new water quality bill which are two-fold in general application. These are: that the project will have no adverse effects on water quality of Woodland Bayou but would likely improve it through the increased flushing of the bayou as a result of maintaininq the channel, and that a need for dredging would be reduced since the channel will not shoal in as much. According to Mr. Hambrick, at the present time there is a collapsing and sluffing off of soil along the channel, which has increased since his prior visit in November, 1984. In his analysis of the project, he considered the effects that the project would have on the public interest, water quality, wildlife and fish in the area, and the historical and archeological aspects of the area. In his opinion, riprap would provide a habitat for marine wildlife which is a plus factor and would help to maintain a shallow shore environment. It would help to maintain a stand of marsh grass that is presently in the area and which is being covered with sand coming from the eroding point. In his opinion, there would be no adverse effect on the archaeological aspects of the area nor is there any indication of any adverse effect on the public interest, including Mrs. Miller. He also considers there would be no adverse effect on marine productivity which, in his opinion, would very likely improve as a result of the project. In his opinion, overall the project will maintain and even enhance the public interest considerations in the area and there would be no damage to the marine bottom by the installation of the riprap. Since the bulkhead will be fronted by riprap, it is not considered a vertical seawall which would be prohibited by the statute as it is currently constituted. Mr. Hambrick is quite certain in his opinion that since Mrs. Miller's property is already bulkheaded and riprapped, there would be no further erosion of her property. Consequently, there would be no adverse ecological effect notwithstanding the fact that Mrs. Miller contends that keeping the channel open would be a continuing trespass to her property. She also contends that when she put in her bulkhead, now at water's edge, it was designed as a retaining wall and was located in sand some substantial distance from the water. When the channel was cut across her land, the beach from the channel to the "retaining wall" eroded and when it appeared the wall would be undercut as well, she put in the riprap. All of this would be perpetuated by the construction of Woodland's project which would keep the channel open and keep it naturally closing as she believes it would do if left alone. In short, Mr. Hambrick's analysis of the situation including his personal visits to the site lead him to conclude that the project will not: harm water quality in the area, increase the number of boats using the channel, influence the speed of boats that use the channel, or increase erosion of Petitioner's property. This opinion is supported by that of Dr. Echternacht, a hydrographic engineer who is also convinced that construction of the proposed bulkhead and riprap would not cause any erosion to Petitioner's property. In fact, the riprap in front of the bulkhead will act to absorb wave energy and since it cannot be placed in a vertical manner, it reduces that amount of reflected energy. The bulkhead and riprap as proposed here would reduce the amount of soil infusion into the channel and thereby the amount of dredging needed. The technical aspects of the proposal were also considered by Mr. Fancher, the dredge and fill supervisor for DER in the Northwest District. When he reviewed the application, including Mr. Hambrick's proposal for riprap, he concurred with it. In order to appropriately receive a permit, applicants must show that the application conforms to both water quality and public interest standards. After his review of the entire project, Mr. Fancher concluded that this project would not adversely affect water quality standards and would not adversely affect but in fact might promote public interest considerations. When the Florida Legislature passed its new water quality bill in October, 1983, it prohibited the construction of most vertical seawalls. In Mr. Fancher's opinion, what is proposed here is not a vertical seawall and there is no evidence submitted by Petitioner to refute this. In fact, there was no evidence presented by Petitioner, save her own testimony which does not serve to overcome the expert opinions to the contrary, that the proposed project fails to meet the tests set out under the laws of this State.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore RECOMMENDED that the Respondent, Woodland Lake Property Owners, Inc.'s permit to construct a bulkhead be issued as modified. RECOMMENDED this 11th day of October, 1985, in Tallahassee, Florida. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division Administrative Hearings this 11th day of October, 1985. COPIES FURNISHED: Kenneth G. Oertel, Esq. Oertel and Hoffman 2700 Blair Stone Road Suite C Tallahassee, Florida 32301 J. B. Murphy, Esq. 506 S. Palafox Street Pensacola, Florida 32501 Brad Thomas, Esq. Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Victoria Tschinkel Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Rd. Tallahassee, Florida 32301
Findings Of Fact Application for consumptive use permit No. 75-00225 is a request for an existing use to be withdrawn from the Floridan Aquifer from two different wells. These two wells are located in the Hillsborough Basin and in Polk County. The property contiguous to the wells encompasses approximately 80.9 acres. The water is to be used for citrus processing and disposed of off site. The permit seeks, for average daily withdrawal, 2.98 million gallons per day for one well and 1.566 million gallons per day for the other well for a total average daily withdrawal of 3.864 million gallons per day. For maximum daily withdrawal the permit seeks 4.096 million gallons per day for one well and 2.792 million gallons per day for the other well for a total maximum daily withdrawal of 6.888 million gallons per day. The amount of water sought to be consumptively used by this application greatly exceeds the water crop of the subject lands owned by applicant. Mr. John C. Jennings and Mr. William Sunderland, owners of property adjacent to the Kraft property, appeared in their own behalf and stated that they felt that their wells were being hurt because of the large quantities of water pumped by Kraft. They did not attempt to offer expert testimony nor did they claim to be hydrologists. They did note that each had substantial problems with their wells running out of water.
Recommendation It does not appear that the district has had a reasonable opportunity to examine the objections and comments of Messers. Jennings and Sunderland with regard to the effect of the applied for consumptive use on their property. These objections were apparently raised for the first time at the hearing. As noted in paragraph 6, if the wells of Messers. Jennings and Sunderland are substantially affected in an adverse manner by applicant's use of such large quantities of water, such a use would not seem to be a reasonable, beneficial use as is required for permit unless further conditions were placed upon the permit. Therefore, it is recommended that the Southwest Florida Water Management District staff further investigate the effect of the applied for consumptive use on the wells located on the property of John C. Jennings and William Sunderland prior to the Board taking formal action on this application. ENTERED this 26th day of May, 1976, in Tallahassee, Florida. CHRIS H. BENTLEY, Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Jay T. Ahern, Esquire Staff Attorney Southwest Florida Water Management District P. 0. Box 457 Brooksville, Florida 33512 Douglas T. Moring, Esquire Kraftco Corporation Kraftco Court Glenview, Illinois 60025
Findings Of Fact Twelve-acre Lake Tresca lies at an elevation of approximately 8 feet on the northern edge of sand dunes that stretch some 250 yards south to the Gulf of Mexico in Walton County, Florida, just east of Eastern Lake. According to one of petitioners' witnesses, this group of freshwater lakes in a dune system may be unique. Lake Tresca is a source of freshwater for migrating birds, at the gulf's edge. White, great blue, and Louisiana herons feed in the lake's shallows. Purple martins are present in numbers. The eastern lobe of Lake Tresca is in excellent place for birds to feed and nest. The lake has a balanced fish population. Game fish as big as the ten-pound bass spotted by Douglas B. Bailey of the Florida Game and Freshwater Fish Commission have smaller fish on which to feed, including gambusia and other minnows that feed, in turn, on mosquito larvae. Lake Tresca is oligotrophic. There are no aquatic weeds, but there are fragrant water lilies, bladder wort, yellow-eyed grass, and other plant species valuable to wildlife. Most of the lake bottom is bare of vegetation, but the shallow, littoral portions support various plants, including significant colonies of rooted macrophytes, and furnish a suitable habitat for bedding fish. This vegetation removes some nutrients, makes others more usable, filters runoff from the surrounding yards, and stabilizes the shoreline. Bacteria and algae, primary constituents of the lake's "food web," also flourish in Lake Tresca. A shallow area of Lake Tresca stretches across part of Mr. Copelan's half-acre lot onto the Pettengills' lot. The application for permit uses this diagram to represent the configuration: * NOTE: A map of the pond is on the Recommended Order on file with DOAH and is not available in this ACCESS document. Lake Tresca Copelan Property Pettengill Property Petitioners' Exhibit No. 9. (Legend supplied.) The Pettengills have built a house on their lot for occasional, seasonal use and with a view toward his retirement. Their septic tank is about 80 feet from the lake. The house was built to take advantage of the prevailing southwesterlies and has a porch facing Lake Tresca and the causeway. The house has no air conditioning. Except for the causeway, Mr. Copelan's lot is unimproved. There are about 14 other riparian owners many of whom have built houses and put in septic tanks. After discussions between Mr. Copelan and Mr. Pettengill about an easement across the Pettengill property, to provide access overland to the Copelan property, had faltered, Mr. Copelan indicated that he might place fill dirt across the lake so as to block the Pettengills' access to the main body of the lake and to create a roadbed for travel across the lake to and from his lot. As a result, on April 20, 1980, Mr. Pettengill wrote Mr. Copelan a letter in which he stated: Any dredging, filling or other manmade changes may be accomplished only if proper permits are obtained in advance for them. I have taken the liberty of attaching copies of relevant sections of Florida Statutes and the Florida Administrative Code regarding the required procedures for these activities. Petitioners' Exhibit No. 8. Because, as he testified, Mr. Copelan had no faith in Mr. Pettengill's legal expertise, Mr. Copelan asked Marge Crawford, the real estate agent from whom he had purchased the land-locked lot, to inquire as to permits. At Ms. Crawford's instance, she and Curtis Larry Taylor, an environmental specialist employed by DER in Panama City, visited Lake Tresca on June 16, 1980. In a contemporaneous memorandum, Mr. Taylor recorded his impression that a DER permit "under the authority of Chapter 403 F.S. Section 17-4.28(2)(d) [Florida Administrative Code," DER's Exhibit No. 1, would be necessary for construction of the causeway Mr. Copelan had in mind. He furnished Ms. Crawford an application form to forward to Mr. Copelan. On June 19, 1980, Ms. Crawford wrote Mr. Copelan: I met with Mr. Taylor, of the Department of Natural Resources, Dredging and Fill Department and inspected the site at which you would like to put in a drive way. Mr. Taylor said he saw little inpact [sic] on the invironment [sic] and would recom- mend a permit be given. This would take 6 to 8 weeks with out any protests. The DNR will contact property owners around that portion of the lake. If there is a protest there will be a delay'. I think you can expect a protest from at least two owners. Fill out the application as soon as possible and mail it to the location indicated on the form. If I can be of help with he applica- tion let me know. I asked Mr. Taylor what would happen if you just went ahead and fill[ed] in that portion of the lake. He said nothing unless some- one files a complaint and then it could be costly, attorney fees. I also got another price on a road in for the long way, $8/per foot. Joint Exhibit No. 7. Mr. Copelan received and read the letters from Mr. Pettengill and Ms. Crawford, and read highlighted portions of the dredge and fill rules Mr. Pettengill sent him. In early August, without having applied for a permit, Mr. Copelan contracted with James A. Madden for the construction of a causeway across the eastern lobe of Lake Tresca. Work began in early August of 1980 and continued for four working days, a weekend intervening. Mr. Madden and his son used dump trucks and a bulldozer to haul sand from a borrow pit Mr. Madden has leased and to build a causeway 162 feet long with a top surface approximately 12 feet wide. About midway they placed a culvert with a 12-inch diameter to join Lake Tresca to the pool on the Pettengills' property severed by the causeway from the rest of the lake. On either side of the causeway, waiter lily and bladder wort are the predominant plant species. On August 11, 1980, Mr. Pettengill told DER's Mr. Taylor that work on the causeway had begun. The following day Mr. Taylor visited the site, and found yellow sand fill about 18 to 24 inches deep covering an area approximately 15 feet by 45 feet. Joint Exhibit No. 8. He found no telephone number listed for George Copelan but telephoned Marge Crawford on August 12 or 13, 1980, to ask her to tell Mr. Copelan to stop work. Joint Exhibit No. 8. On August 19, 1980, DER's Northwest District Enforcement Officer, George E. Hoffman, Jr., wrote Mr. Copelan advising him "to cease and desist from any further unauthorized filling." Joint Exhibit No. 5. By the time this letter reached Mr. Copelan, the causeway had been completed. On October 6, 1980, Mr. Copelan wrote Mr. Hoffman saying that he owned the land under the road and in general to the effect that he thought he was within his rights. Joint Exhibit No. 4. Mr. Hoffman responded with a letter to Mr. Copelan on December 23, 1980, in which Mr. Hoffman "requested that [Copelan] voluntarily agree to remove the fill and restore the area to its original contour. Joint Exhibit No. 6. This letter stated that, "Otherwise, the Department will have no alternative but to initiate a formal administrative enforcement proceeding . . . seeking the restoration." Joint Exhibit No. 6. On February 27, 1981, DER filed its notice of violation, No. DF-010- 81-NW, finding that the filling accomplished before August 12, 1980, had been accomplished without a permit, and that it "will have a detrimental [e]ffect on the water quality and may be potentially harmful . . . to the aquatic life of the lake" and that it had "created pollution violating Section 403.161(1)(a), Florida Statutes, and the rules of the Department." Joint Exhibit No. 1. Orders for corrective action contained in the same document proposed to require Mr. Copelan to reimburse DER for its expenses "in tracing, controlling and abating the source of pollution," to "cease aid desist from further unauthorized filling," and to remove the fill and restore the area to its original contours (even though by this time the causeway had been completed). Joint Exhibit No. 1. DER inspected on March 2, 1981, and learned that the causeway had been completed. Thereafter, the parties agreed to a consent order dated May 5, 1981, which provided, in part: Within thirty (30) days of the effective date of this Order, the Respon- dent shall submit an after-the-fact permit application for the construction and/or filling project described in this Order [the causeway] In the event the application is determined to be incomplete, the Respondent shall provide the requested additional information within a fifteen (15) day period. * * * In the event the application is denied, the Respondent agrees to remove the fill material and restore the area to its preproject contours within forty-five (45) days of the receipt of final agency action. Respondent does not waive his right to claim that the aforementioned fill project is exempt from the Department's permitting requirements and that this defense may be asserted by the Respondent in any future pleadings of proceedings. The Department, for and in consid- eration of the complete and timely perfor- mance by the Respondent of the obligations contained in this Consent Order, hereby agrees to waive its right to seek the judi- cial imposition of damages or civil penalties or to seek criminal penalties for the alleged violations outlined in this Consent Order. * * * 9. This Consent Order shall be a final agency action of the Department and may be enforced pursuant to Sections 120.69 and 403.121, Florida Statutes. The Respondent hereby waives any right to a hearing or administrative or judicial review of the provisions of this Consent Order provided however that the Respondent does not waive the right to assert defenses available pur- suant to Section 120.69(5), Florida Statutes, should the Department seek judicial enforce- ment of the Consent Order. The Respondent's failure to comply with the terms of this Consent Order shall constitute a violation of Section 403.161, Florida Statutes. Joint Exhibit No. 2. In accordance with the consent order, Mr. Copelan filed an application for an after-the-fact permit, which DER received on June 8, 1981. Petitioners' Exhibit No. 9. At DER's request, on August 17, 1981, James R. Webb, Esquire, counsel for Mr. Copelan, sent DER copies of a survey including a plan view and a cross- sectional view of the causeway, Applicant's Exhibit No. 2; Petitioners' Exhibit No. 10, and, on November 2, 1981, copies of a survey showing the approximate ordinary high water line. Applicant's Exhibit No. 2. Neither the application nor the supplemental information was prepared by a professional engineer. DER determined the application to be complete on November 3, 1981, and, on January 7, 1982, issued its intent to issue a permit to partially after-the-fact construct a road- way approximately 80' long by 20' wide by 3' high, in accordance with the attached drawing labelled "Fill Road" Sheet 1, Revi- sion No. 1 by R.E.P. 13 August, 1981; located in Section 19, Township 3 South, Range 18 West. Joint Exhibit No. 10. According to the case file, DER received the Pettengills' administrative petition for section 120.57 hearing on January 21, 1982; but a permit was nevertheless inadvertently mailed to Mr. Copelan on January 29, 1982. On receipt of the permit, Mr. Copelan caused oyster shells to be placed on the roadbed and sod to be planted along the sides of the causeway. The permit was followed by a letter from DER instructing Mr. Copelan to disregard it. APPLICATION INACCURATE In describing the causeway, the application gives its dimensions as "approximately 10 feet wide by 30 feet in length." Petitioners' Exhibit No. 9. In fact, the top surface of the (causeway is 12 feet wide and the causeway is broader at the base. It is 20 feet across at one point, according to Petitioners' Exhibit No. 10. From a surveyor's drawing subsequently furnished at DER.'s request, Petitioners' Exhibit No. 10, DER inferred that the road was 80 feet long, even though this drawing was not accompanied by an amendment to the written description of the project. In fact, the causeway is 162 feet long, and not 30 or 80 feet long. The application states that the culvert has a diameter of 19 inches. In fact, the culvert had a diameter of 12 inches, so that the application overstates the area of the cross-section by more than 150 percent. Under the "Remarks" section of Mr. Copelan's application appears the following: Applicant was under the belief that no permit was necessary at the time of commencement and completion of the project. Petitioners' Exhibit No. 9. In fact, Mr. Copelan had been informed twice in writing that he needed a permit to place fill in the lake and had even been furnished an application form, but went ahead anyway, without seeking legal advice, or contacting DER. Lake Tresca is not a man-made lake as stated on the application. Construction of a causeway was completed by mid-August and did not occur on September 1 and 2, 1980, as stated in the application. In what was apparently a typographical error, the township is stated as 35, rather than 3 South, on the application originally filed, Petitioners' Exhibit No. 9, but this error is rectified in a later submission. Petitioners' Exhibit No. 10. PRIVATE PROPERTY RIGHTS Since the fill was originally placed, it has spread out along the bottom or "migrated." Along its southern extent, the causeway now overlaps the Pettengills' property. The road has the effect of blocking access to Lake Tresca for the Pettengills. They have, indeed, sold their boat now that they can no longer make their wonted use of it on the lake. DISSOLVED OXYGEN, TRANSPARENCY, HEAVY METALS The water in Lake Tresca Is very clear, except for an iridescent sheen in the vicinity of the causeway, and an organic scum on the water restricted by the causeway. Analysis of water samples taken at four locations in Lake Tresca by Petitioners' own expert revealed no violations of the dissolved oxygen standards. There was speculation but no hard evidence that lead and other heavy metals associated with automobile pollution may have made their way into Lake Tresca as a result of the causeway. OILS AND GREASES Mr. Madden, the contractor, did not add oil or grease to the fill he used to build a causeway through Lake Tresca. He has used fill from the same borrow pit on other projects and has had no complaints that it was oily or greasy. But there was no oil or grease on the lake before Mr. Copelan had the road put in. When the fill was originally placed, in the fall of 1980, there was a distinct petroleum odor, for the first time, particularly in humid weather. Mr. Ryan detected a strong petroleum odor as recently as February of this year, but the odor has abated over time somewhat. Oils and greases have coated the water's surface with an iridescent film, on either side of the southern stretch of the causeway, since it was built. Nowhere else in the lake can oils and greases be detected visually. Three water samples taken near the causeway on February 6, 1982, were analyzed and found to con-tain 3.2, 4.1, and 5.4 milligrams per liter (or parts per million) of oils and greases. A water sample taken elsewhere in the lake on the same day, although at another well-vegetated location, was found to contain less than one part per 100 million (.01 mg. per liter) oils and greases. Mr. Taylor is one of three DER employees who has seen a sheen on the water near the causeway, even after the sod and oyster shells were added. Another DER employee, Lynn Griffin, testifying as an expert in general biology with a special emphasis on oil pollution, concluded that the oil and grease she saw in Lake Tresca came from the causeway, because she discovered no other possible source. Her uncontroverted testimomy specifically rejected the theory that this greasy film could be traced to septic tanks, because the bacteria in septic tanks produce a milky liquid, not an oil sheen. DER's John B. Outland testified unequivocally that the oil and grease on the surface of Lake Tresca either leached out of the fill or came from equipment operated on the fill road. Petitioners' chemist would have had to use another test in addition to the Soxhlet extraction method he did use, in order to establish to a scientific certainty that the oils and greases he identified in samples taken from Lake Tresca were petroleum hydrocarbons. But with convincing testimony that what looked like petroleum also smelt like petroleum, other evidence did establish that the oils and greases were petroleum derivatives. BIOLOGICAL EFFECTS Placement of fill on the lake bottom eliminated benthic organisms that have not reestablished themselves on the submerged causeway surface, nor on dry land above water, subject to the disturbances of automobile traffic. Habitat, shelter, and forage for fishes and invertebrates have been destroyed; bacterial and algal processes have been eliminated. No animals live on top of the submerged fill even though certain larvae may be found less than a meter away, and several animals thrive in the vegetated areas of Lake Tresca. Although the filled area covers no more than 2,000 square feet, the oils and greases spread out over a larger area, with dimensions not established by the evidence. The iridescent oily film decreases the amount of light penetrating to plants underneath and so reduces photosynthesis in benthic plants. In the short term, oils and greases obstruct gas and nutrient exchanges necessary to plant life and may cause acute toxicity or death. In the long term, oils and greases can cause neoplasia and affect the reproductive capacity and so the growth rate of animals. They can be taken into lipid-rich eggs and other tissues, contaminating the food web. The untoward effects of oils and grease are more critical in the part of the lake cut off and restricted by the causeway, because of the lack of adequate circulation. There is at present plant and animal life in this part of the lake, nevertheless, and similar fauna and flora in the shallow area of the lake stretching 300 to 400 feet toward open water on the other side of the causeway. The causeway has eliminated a narrow strip from this biologically productive area, an area that also serves to filter pollutants from upland runoff. The full extent of the deleterious effects of the oils and greases is not yet known. In preparing the foregoing findings of fact, the hearing officer has had the benefit of petitioners' proposed recommended order and the department's proposed findings of fact, proposed conclusions of law, proposed recommended order, and memorandum, all adopted by the applicant. To the extent proposed findings of fact have not been adopted, they have been rejected as unsupported by the evidence or irrelevant to the issues.
Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That DER deny the application for an after-the-fact permit to create a fill road across Lake Tresca, and order respondent George Copelan to restore the area to its preproject contours within forty-five (45) days. DONE AND ENTERED this 3rd day of June, 1982, in Tallahassee, Florida. ROBERT T. BENTON II Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of June, 1982 COPIES FURNISHED: Randall E. Denker, Esquire 103 North Gadsden Street Tallahassee, Florida 32301 Gordon D. Cherr, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 James Webb, Esquire Post Office Box 385 Destin, Florida 32541 Victoria Tschinkel, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 ================================================================= AGENCY FINAL ORDER ================================================================= STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION DWYNAL and IONA PETTENGILL, Petitioners, vs. CASE NO. 82-294 STATE OF FLORIDA, DEPARTMENT OF ENVIRONMENTAL REGULATION, and GEORGE COPLAN, Respondents. /
The Issue Did the Respondent, Charles W. Coxwell, Sr., excavate in statutorily- protected waters of the State of Florida in March of 1992, as alleged in the Department's Notice of Violation (NOV).
Findings Of Fact 1. In back of Respondent's house, on property owned by the Respondent, is a spring system where underground streams of water flow to the surface and out into an area formerly dominated by wetland plant species, to include: Fetterbush (Lyonia Iucida), Sweet Gallberry (Ilex Corjacea), and Sweet Bay Magnolia (Magnolia Virginiana). The stream continues over property owned by other persons, ultimately flowing into Grassy Lake which connects to Choctawhatchee Bay. All of this water is statutorily protected and within the regulatory jurisdiction created and assigned to the Department by the Legislature. In 1990, Respondent applied for a permit from the Department to construct a small impoundment where the springs flow out, on his property (and before the waters flow onto the property of other downstream landowners). The application form for the permit sought by Respondent in 1990 required him to list the adjoining landowner, who was, in fact, a Mr. Finch. Mr. Finch expressed his concern that an improperly built impoundment might be unsafe. The Department made a number of requests to Respondent for specific design specifications and drawings of the impoundment and its outfall structure. Respondent had discussions with Department staff in which he acknowledged that a permit was required; however, he declined to respond satisfactorily to the Department's "incompleteness requests" for additional information. Ultimately, the permit application was denied on May 16, 1991. Respondent did not pursue administrative remedies in the matter of the permit denial. In approximately March of 1992, Respondent caused 0.3 acres of the statutorily-protected waters and wetlands where the springs emerge behind his house to be excavated without the permit required by Florida law. Respondent knew that permits for such excavation were required by Florida law. The NOV assessed $404.51 (four hundred and four dollars and fifty-one cents) in enforcement costs.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, the findings of the Department's Notice of Violation were proven by substantial and competent evidence, and it is RECOMMENDED that the Orders for Corrective Action set out in the Notice of Violation and restated below be made final: Respondent shall immediately cease and desist from either dredging and/or filling within waters of the State as defined in Florida Administrative Code Rules 17-4.022 and 17-312 prior to receiving the necessary permit form the Department or notice that the proposed activity is exempt from the permitting requirements of the Department. Within 30 days of the effective date of the Final order, Respondent shall reimburse the Department for expenses incurred in investigating the violation in the sum of $404.51. Payment shall be made by certified check, cashiers' check or money order submitted to the Department's Northwest District Office, 160 Governmental Center, Pensacola, Florida 32501-5794. See Exhibit 3 Attached. Within 60 days of the effective date of the Final Order, Respondent shall restore the excavated area as identified on the drawings attached hereto as Exhibit 2. The excavated material shall be regraded so as to re-establish pre-existing contours and elevations as indicated by the adjacent undisturbed areas. Respondent shall revegetate the restored site as identified in paragraph d below. Respondent shall stabilize the site as needed to retain sediment on- site during restoration. Respondent shall utilize turbidity control devices throughout the restoration including the use of staked filter cloths in the vegetated wetlands and floating screens where needed in the open waters. Within 15 days of the effective date of the Final Order, Respondent shall submit a planting plan and schedule to the Department for approval prior to revegetating the regraded site as identified in Exhibit 2. No work to revegetate the site shall be undertaken until the plan is approved by the Department. Respondent's plan shall address and institute measures necessary to insure successful revegetation. The restoration area shall be planted with indigenous tree species of no less than 2 feet in height, such as Fetterbush (Lyonia Iucida), Sweet Gallberry (Ilex Corjacea), and Sweet Bay Magnolia (Magnolia Virginiana). The trees shall be planted on ten (10) foot centers. Respondent shall implement the restoration plan within 10 days of Department approval. Upon completion of the restoration work required by paragraph c above, Respondent shall maintain the restored area as follows: the revegetation effort shall be considered successful if, after one year or one growing season - whichever is less, 80% of the revegetation effort yield values of less than 80%, then the unsuccessful areas shall be replanted to meet, at a minimum, the required percentage. DONE AND ENTERED this 29th day of March, 1993, in Tallahassee, Florida. STEPHEN F. DEAN Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of March, 1993. COPIES FURNISHED: Virginia B. Wetherell, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, Esquire Acting General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Richard L. Windsor, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Charles W. Coxwell, Sr. 1133 White Point Road Niceville, FL 32578