The Issue The issue to be determined in this case is whether Sabal Trail is entitled to the proposed Environmental Resource Permit and Easement to Use Sovereign Submerged Lands to construct a natural gas pipeline.
Findings Of Fact The Parties Petitioner, WWALS, is a Georgia not-for-profit corporation registered with the Florida Department of State as a Foreign Not For Profit Corporation. Its mailing address is in Hahira, Georgia. WWALS’ mission is to advocate for conservation and stewardship of the Withlacoochee, Willacoochee, Alapaha, Little, and Upper Suwannee River watersheds in South Georgia and North Florida. WWALS stated in its petition that it has a total of 85 members, 36 of whom reside in Florida. The total number of WWALS members was not established at the final hearing. If members that joined WWALS after it filed its petition for hearing are included, WWALS has about 40 members living in Hamilton County and Suwannee County. Sabal Trail is a Delaware limited liability company that is registered to do business in the State of Florida. It is the applicant for the authorizations that are challenged by Petitioner. The Department is the state agency charged with administering the Environmental Resource Permitting program under chapter 373, Florida Statutes, and Florida Administrative Code Chapters 62-4 and 62-330. The Department is also the state agency authorized by chapter 253, Florida Statutes, and Florida Administrative Code Chapter 18-21, to review and authorize certain uses of state- owned submerged lands. General Project Description Sabal Trail proposes to construct an interstate natural gas pipeline. The primary purpose of the pipeline is to support electric power generation in Florida. The pipeline would start in the vicinity of a Transcontinental Gas Pipeline Company station in Tallapoosa County in Alabama. The portion of the pipeline in Florida would cross twelve Florida counties, entering the state in Hamilton County and terminating in Osceola County. The pipeline would include 232.75 miles of 36-inch diameter pipe for the Mainline Route, 13.1 miles of 36–inch diameter pipe for the Hunter’s Creek Line, and 21.5 miles of 24- inch pipe for the Citrus County Line. The pipe used would be made of high-strength ductile carbon steel. The project would include construction and operation of three compressor stations and three meter and regulation stations in Florida. There would also be access roads, pig launcher and receiver stations, mainline valves, and pipe storage/work areas. Most of the pipeline would be installed using a conventional “cut and cover” technique, which means a trench is excavated, sections of pipe are placed in the trench and connected, and the trench is backfilled with soil excavated from the trench. However, waterbodies along the route, including the Suwannee River and Santa Fe River, would be crossed using Horizontal Directional Drilling (“HDD”). The HDD method involves boring a pilot hole beneath the waterbody and then enlarging the hole with one or more passes of a reamer until the hole is large enough to pull a prefabricated pipe segment through the hole. The pipeline would be installed more than 40 feet beneath the Suwannee River and Santa Fe River. During HDD operations, drilling fluid or “mud” is used to lubricate the drill head, and remove cuttings from the hole. Drilling mud is a non-toxic, naturally occurring, bentonite clay, which is commonly used for drilling water wells. The pipeline will require a permanent 50-foot right-of- way. Because the construction would require digging trenches through wetlands, drilling under riverbeds, and construction of stormwater management systems for the various stations, an environmental resource permit from the Department must be obtained for the work. Because some construction is over state- owned submerged lands, authorization from the Trustees of the Internal Improvement Trust Fund is also required. Route Selection The pipeline route was selected based on environmental and cultural resource factors and co-location opportunities with existing utility rights-of-way. The proposed route was modified many times to reduce environmental impacts and respond to landowner requests. The pipeline runs parallel to two existing natural gas pipelines that cross the Santa Fe River. The closest major spring to the pipeline route would be Madison Blue Spring, 1.7 miles away. The route is closer to some smaller springs, but it would not cross near spring vents or areas of concentrated spring flow. The pipeline would cross above the Falmouth Cave system. However, the pipeline would be only four-to-six feet beneath the land surface. The cave system is more than 100 feet below ground. Sabal Trail reduced or eliminated impacts to wetlands and waterbodies along the pipeline route, but the project would result in unavoidable temporary and permanent losses of portions of wetlands along the route. The functional loss of wetland functions, as calculated under the Uniform Mitigation Assessment Method (“UMAM”), would be offset by Sabal Trail’s purchase of credits from approved wetland mitigation banks. Petitioner’s Objections The primary concern of WWALS and its members is the possibility of environmental impacts arising from the construction of the pipeline in karst terrain. Karst terrain, which is limestone undergoing dissolution and characterized by the formation in the limestone of holes, cracks, fissures, conduits, and sinkholes, is common in North Florida and throughout the State. Although fragile in particular locations, karst terrain is able to support large linear facilities in North Florida such as Interstate 10, Interstate 75, and railroads, which bear loads of many tons without collapses occurring in the underlying limestone. Sabal Trail conducted geophysical tests, evaluated the potential for sinkhole formation, developed drilling best management practices, and prepared a karst mitigation plan to address potential adverse circumstances that might arise during construction of the pipeline. The pipeline design specifications provide reasonable assurance that the formation of a sinkhole along the path of the pipeline would not cause it to break. It is in the interests of Sabal Trail to build and operate the pipeline so that breaks or disruptions of service do not occur. There are existing natural gas pipelines that were constructed under the Suwannee River and Santa Fe River. A geologist with the Florida Geological Survey testified that he was unaware of any adverse impacts that have been associated with these other pipelines. WWALS presented no evidence of adverse impacts that have been caused by similar pipelines in similar areas. Petitioner’s members are afraid the pipeline will cause adverse impacts because of its construction in karst terrain, but with the exception of four WWALS members whose properties would be crossed by the pipeline, the concerns expressed by members about how they would be affected were vague and speculative. Not all of the potential pipeline impacts described by WWALS members were vague or speculative, but the members’ injuries were vague and speculative. For example, it was not adequately explained how a sinkhole, if one were to occur along the route of the pipeline, would affect them. WWALS expressed concerns about water quality, but the use of drilling mud and grout for the HDD operations is unlikely to affect the residential water wells of any member or non- member. Nor would it affect the water quality of the rivers under which the pipeline is installed, because the amount of drilling mud and grout is so small in relation to groundwater volumes. WWALS expressed general concerns about fish and wildlife impacts, but no member identified any particular wetland impact caused by construction of the pipeline that would directly affect him or her and Petitioner presented no competent evidence to refute the UMAM assessment or the reasonableness of the proposed mitigation. No competent evidence was presented about the possibility that HDD drilling under the rivers could result in adverse impacts to fish and wildlife. Some WWALS members testified they use and enjoy the rivers and surrounding area, but the concerns about adverse impacts to their use and enjoyment were speculative, being based on the proposition that a sinkhole or other disruption of the limestone will be caused by the construction of the pipeline and it will cause a change in the rivers or land to a degree that their use and enjoyment of the rivers or land will be materially diminished. Petitioner did not establish the connection between pipeline impacts and interference with members’ use of area waters. One member testified he has an organic farm and believes it would be adversely affected by air pollution from a proposed compressor station for the pipeline, but there is a separate permit associated with the air quality impacts of the pipeline. Air quality is not a cognizable issue in this proceeding. A few members believe there could be impacts that would adversely affect their business interests, which are not interests that this proceeding was designed to protect. Although a substantial number of WWALS members have substantial interests in the use and enjoyment of the waters and environment of Hamilton County and Suwannee County, a showing of potential injury to those interests was only established in the record for four WWALS members--the four who own land that the pipeline will cross. Four members is not a substantial number when compared to the total number of WWALS members living in Hamilton County and Suwannee County, which is about forty. Public Interest For projects located in, on, or over wetlands or other surface waters, an applicant must provide reasonable assurance that the project will not be contrary to the public interest, or if such activities significantly degrade or are within an Outstanding Florida Water, are clearly in the public interest, as determined by balancing the criteria set forth in rule 62-330.302. Rule 62-330.302(1)(a) lists seven public interest factors to be considered and balanced: 1 Whether the activity will adversely affect the public health, safety, or welfare or the property of others; Whether the activity will adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats; Whether the activity will adversely affect navigation or the flow of water or cause harmful erosion or shoaling; Whether the activity will adversely affect the fishing or recreational values or marine productivity in the vicinity of the activity; Whether the activity will be of a temporary or permanent nature; Whether the activity will adversely affect or will enhance significant historical and archaeological resources under the provisions of s. 267.061; and The current condition and relative value of functions being performed by areas affected by the proposed activity. Petitioner presented no competent evidence to refute the evidence presented by Sabal Trail and the Department that the pipeline project would not result in adverse impacts on public health, safety, or welfare. Beyond general, undisputed evidence about the characteristics of karst geology, no competent evidence was presented by Petitioner to show that a karst-related impact could occur that would affect its members. Petitioner presented no competent evidence to refute the evidence presented by Sabal Trail and the Department that the pipeline would not cause adverse impacts to fish and wildlife. Petitioner presented no competent evidence to refute the evidence presented by Sabal Trail and the Department that the project would not cause adverse impacts to navigation or the flow of water or cause harmful erosion or shoaling. Petitioner presented no competent evidence to refute the evidence presented by Sabal Trail and the Department that the project would not cause adverse impacts to fishing or recreational values or marine productivity. It is undisputed that some of the pipeline impacts and the pipeline, itself, will be of a permanent nature. Petitioner presented no competent evidence to refute the evidence presented by Sabal Trail and the Department that the proposed pipeline would not adversely affect significant historical and archaeological resources. Petitioner presented no competent evidence to refute the evidence presented by Sabal Trail and the Department that the proposed pipeline would not adversely affect the current condition and relative value of environmental functions being performed in the area that would not be fully mitigated. Considering the seven public interest factors listed above, the proposed pipeline is not contrary to the public interest. The Suwannee River and Santa Fe River have been designated as Outstanding Florida Waters. Any activities that would affect them must be shown to be clearly in the public interest. As discussed in the Conclusions of Law, demonstrating that a project is clearly in the public interest requires greater assurance that all permitting requirements will be complied with. Sabal Trail showed clearly that it will comply with all permitting criteria. Rule 62-4.242 prohibits the degradation of water quality in an Outstanding Florida Water. Sabal Trail and the Department showed the construction and operation of the pipeline would not degrade the water quality of the Suwannee River or Santa Fe River. Rule 18-21.004(1)(a) requires that activities on sovereignty submerged lands not be contrary to the public interest. Rule 18-21.003(51) defines public interest in this context as: Demonstrable environmental, social, and economic benefits which would accrue to the public at large as a result of a proposed action, and which would clearly exceed all demonstrable environmental, social, and economic cost of the proposed action. Therefore, to obtain authorization to use sovereignty submerged lands easement, an applicant must create a net public benefit. Sabal Trail and the Department demonstrated the project creates a net public benefit because it would not have adverse environmental impacts that would not be fully mitigated and the project addresses a need determined by the Public Service Commission for additional natural gas transportation capacity into Florida, enhancement of natural gas supply diversity and reliability, and increased competition for natural gas transportation services. WWALS contends the proposed project would conflict with rule 18-21.004(2)(a), which requires that all sovereignty submerged lands be primarily managed to maintain “essentially natural conditions, propagation of fish and wildlife, and traditional recreational uses such as fishing, boating, and swimming.” However, WWALS presented no competent evidence to show that any sovereignty submerged lands would lose their essential natural conditions, that fish and wildlife propagation would be diminished, or that traditional recreational uses would be interfered with. The proposed project complies with the requirement of rule 18-21.004(2).
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection issue a final order that approves issuance of Environmental Resource Permit No. 0328333-001 and grants an easement to use sovereign submerged lands to Sabal Trail Transmission, LLC, for the Sabal Trail Natural Gas Pipeline. DONE AND ENTERED this 11th day of December, 2015, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 11th day of December, 2015. COPIES FURNISHED: Richard S. Brightman, Esquire Timothy M. Riley, Esquire H. French Brown, IV, Esquire Hopping, Green and Sams Post Office Box 6526 Tallahassee, Florida 32314 (eServed) Gus McLachlan Sabal Trail Transmission, LLC Suite 300 400 Colonial Center Parkway Lake Mary, Florida 32746 John S. Quarterman, President WWALS Watershed Coalition, Inc. Post Office Box 88 Hahira, Georgia 31632 (eServed) Jack Chisolm, Esquire Sidney C. Bigham, III, Esquire Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 (eServed) William R. Wohlsifer, Esquire Leighanne C. Boone, Esquire William R. Wohlsifer, P.A. 1100 East Park Avenue, Suite B Tallahassee, Florida 32301 (eServed) Jonathan P. Steverson, Secretary Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 (eServed) Craig Varn, General Counsel Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 (eServed) Lea Crandall, Agency Clerk Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399 (eServed)
Findings Of Fact At all times material to this proceeding, Respondent, James A. Tipton ("Tipton"), has been a registered professional engineer in the State of Florida, having been issued license number PE 0018147, which expires on January 31, 1987. Tipton employed the services of Robert Corno as a field man for taking samples to establish soil profiles, site characteristics and existing water tables for septic tank applications prepared and filed by Tipton. Corno had actual authority from Tipton to conduct tests, site examinations and evaluations and to submit his findings to Tipton. Sometime before April 8, 1985, Tipton was retained to perform professional engineering services in connection with the preparation and filing of an application for a septic tank on lot 168, block 3, Charlotte Ranchettes Subdivision in Charlotte County ("lot 168"), owned by Joseph Duseo. Tipton sent Corno to lot 168 on April 13, 1985, to examine and evaluate the site, take soil samples and make other observations that would have to be reported to Tipton in connection with Tipton's work. Corno completed his work and reported to Tipton. Corno did not bring Tipton the actual soil samples. On April 8, 1985, Duseo's general contractor told Corno about a well on lot 168. When Corno visited the site, he observed the well. The well is an artesian well, about 3 feet high and six inches in diameter. The well is an irrigation-type well and is non-potable. The well was within fifty feet of the drain field of the septic system Tipton proposed for lot 168. The well also is approximately 5 to 10 feet from the north property line. Corno knew at the time of his visit to the site that the well was not plugged. However, Corno understood that Duseo was in the process of arranging with the Southwest Florida Water Management District to have the well plugged. Corno did not tell Tipton about the well before Tipton prepared and filed the application for the proposed septic tank. Therefore, Tipton did not know there was a well on lot 168 when he was preparing the application for the septic tank permit. Tipton did not ask Corno any questions calculated to reveal whether there was a well on lot 168. Corno held the belief that non-potable wells, especially those that were to be plugged, did not have to be shown on septic tank permit applications. There was evidence about a survey of lot 168 certified by a land surveyor employed by a firm of professional engineers which did not show any well on lot 168. However, Tipton did not have access to the survey before he prepared the septic tank permit application on lot 168. (The survey bears two dates, April 17 and April 18, and was not signed until April 25, 1985.) On or about April 15, 1985, Tipton signed and certified the septic tank permit application for lot 168. The application was filed at the Charlotte County Public Health Unit (Health Department) on April 16, 1985. The application indicates "none" in the space provided to indicate the "location of wells within 75 feet of property lines." The well on lot 168 is an important consideration which should have been depicted on the application. Septic tank drain fields could pollute a well. Even if Tipton had known that the well was supposed to be plugged, it was not plugged until July 1985. Failure to show the well was a serious omission. Tipton was negligent for relying on Corno without having an understanding whether Corno would report to him the existence of non-potable wells within 50 feet of the drain field of a septic system or within 75 feet of a property line if the well was likely to be plugged. If he had used due care, Tipton would have either made explicit inquiry of Corno sufficient to reveal the existence of the well or ascertained from Corno in advance that he would report to Tipton the existence of any well within 50 feet of the drain field of a proposed septic system or within 75 feet of property lines. Having failed to exercise due care, Tipton did not realize that Corno would not be reporting to him the existence of a non-potable well which was supposed to be plugged in the future. A few days after he filed the application, Tipton learned about the well on lot 168. But at about the same time, Duseo and his contractor began discussing construction alternatives that would change the septic system and require a new septic tank application. Therefore, Tipton did not immediately amend the April 15 application to show the well. In mid-May, Tipton filed a new application for the different septic system. The new application, not in issue in this case, showed the well. The application also contained a soil profile which probably is not accurate. However, Tipton's soil profile simply reflects the information reported to him by Corno. While Tipton's soil profile does not correspond with soil profiles from other test holes dug in the area of the proposed drain field by the Health Department and an expert witness, the information Corno reported to Tipton was well within the realm of possibilities for soil in the area of lot 168. Corno generally seemed to be a qualified and experienced field man who used proper tools to do his job. There was nothing suspicious about Corno's information, and there was no reason for Tipton to suspect that it was false or fraudulent. While it is the better practice for a professional engineer to require his field man to deliver the actual soil sample to support a soil profile report, this is not required of professional engineers if there is no reason to suspect that a field man's soil profile report is false or fraudulent. On the application, Tipton estimated the high water table on lot 168 at 2.2 feet below existing grade. While other expert witnesses estimated a higher high water table, the evidence did not prove that Tipton was negligent in his estimate. Some of the conflicting estimates were Health Department estimates which, the evidence indicates, tend to be high to be on the safe side. Others were estimates on permit applications which may have been influenced by the Health Department's desires and which may not reflect the engineers' actual estimates. Of all the estimates, only Tipton's was supported by testimony how the estimate was derived. (Tipton used what he called Darcy's Law.) Finally, Petitioner's own expert witness testified that Tipton's high water table estimate could not be called negligent.
Recommendation Based upon the foregoing Findings Of Fact and Conclusions Of Law, it is recommended that the Board of Professional Engineers enter a final order holding Respondent, James A. Tipton, guilty of negligence in the practice of engineering under Count I of the Amended Administrative Complaint (but dismissing Count II of the Amended Administrative Complaint) and imposing an administrative fine in the amount of five hundred dollars ($500.00). RECOMMENDED this 19th day of May, 1986, in Tallahassee, Leon County, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32399 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of May, 1986. COPIES FURNISHED: Ms. Sarah Logan Executive Director Board of Professional Engineers 130 North Monroe Street Tallahassee, FL 32301 Mr. Fred Roche Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, FL 32301 Salvatore A. Carpino, Esq. General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, FL 32301 Wings Slocum Benton, Esq. Department of Professional Regulation 130 North Monroe Street Tallahassee, FL 32301 John Charles Heekin, Esq. C-1 Ocean Plaza 21202 Ocean Blvd. Port Charlotte, FL 33952 APPENDIX The following are specific rulings on all the parties' proposed Findings of Fact as required by Section 120.59(2), Florida Statutes (1985). Rulings on Petitioner's Proposed Findings of Fact Petitioner's Proposed Findings of Fact 1 through 3, 9, 10, 13 through 16, 19, 21 and 22 are accepted as substantially factually accurate and are incorporated in the Findings Of Fact in the same or similar format to the extent necessary. Petitioner's Proposed Finding Of Fact 4 would have been included in paragraph 1 above except that the last sentence is unnecessary. Petitioner's Proposed Finding Of Fact 5 would have been included in paragraph 1 above except that the third sentence is unnecessary. Petitioner's Proposed Findings Of Fact 17, 18 and 27 would have been included in paragraph 1 above except that they are unnecessary. Petitioner's Proposed Finding Of Fact 26 would have been included in paragraph 1 above except that whether Alligator Creek is a "significant" drainage feature would depend on the definition of "significant" which was not established by the evidence. In addition, Petitioner's Proposed Finding Of Fact 26 is unnecessary. Petitioner's Proposed Findings Of Fact 6 through 8 are rejected as conclusions of law and because the last sentence of Proposed Finding Of Fact 6 is cumulative. Petitioner's Proposed Finding Of Fact 11 is rejected because the first sentence is contrary to the greater weight of the evidence and Findings Of Fact and the second sentence is, subordinate to Findings Of Fact. Petitioner's Proposed Findings Of Fact 12, 20, 23 and 24 are rejected as subordinate to Findings Of Fact. Petitioner's Proposed Finding Of Fact 25 is rejected because the first sentence is subordinate to Findings Of Fact and the second sentence is contrary to the greater weight of the evidence. Rulings on Respondent's Proposed Findings of Fact. Respondent's Proposed Findings Of Fact 1 through 3, 5 and 12 are accepted as substantially factually accurate and are incorporated in the Findings Of Fact in the same or similar format to the extent necessary. Respondent's Proposed Finding Of Fact 4 would have been included in paragraph 1 above except that the second sentence is unnecessary. Respondent's Proposed Finding Of Fact 8 would have been included in paragraph 1 above except that it is unnecessary. Respondent's Proposed Finding Of Fact 9 would have been included in paragraph 1 above except that it is in part unnecessary. Respondent's Proposed Finding Of Fact 11 would have been included in paragraph 1 above except that it is contrary to the greater weight of the evidence and Findings Of Fact that there is "no way" for an engineer to avoid relying on a field man's error such as Corno's error in omitting to report the existence of the well. Respondent's Proposed Finding Of Fact 14 would have been included in paragraph 1 above except that it is irrelevant. Respondent's Proposed Finding Of Fact 6 is rejected because it is subordinate to Findings Of Fact and is unnecessary. Respondent's Proposed Finding Of Fact 7 is rejected because it is simply a recitation of conflicting evidence, some of which is accepted but some of which is rejected as contrary to the greater weight of the evidence and Findings Of Fact. Specifically, it was found that Corno did not tell Tipton about the well and that Tipton did not have the survey in his possession at the time the application was filed. Respondent's Proposed Finding Of Fact 10 is rejected as contrary to the greater weight of the evidence and Findings Of Fact. Specifically, the evidence supported a finding of negligence on the part of Tipton for failure to utilize due care and to have due regard for acceptable standards of engineering principles whether or not practicing in Charlotte County. In addition, Mr. Murray's expert testimony must be disregarded because it was given upon a hypothetical assumption that an engineer had possession of a sealed survey showing no improvements on the property as the time of the application, a fact not proved by the evidence. Respondent's Proposed Finding Of Fact 13 is rejected as contrary to the greater weight of the evidence and Findings Of Fact. Specifically, personnel in the Health Department, part of the "general public," were misled. (The general public also reasonably could have been led to a fallacious conclusion, but there was no "misconduct" on Tipton's part. See Conclusions of Law.) ================================================================= AGENCY FINAL ORDER ================================================================= STATE OF FLORIDA DEPARTMENT OF PROFESSIONAL REGULATION BOARD OF PROFESSIONAL ENGINEERS DEPARTMENT OF PROFESSIONAL REGULATION, FLORIDA BOARD OF PROFESSIONAL ENGINEERS Petitioner, vs. DOAH CASE NO. 85-2684 DPR CASE NO.0058289 JAMES A. TIPTON, Respondent. /
Findings Of Fact At all times relevant hereto, ADI and Youngquist Brothers were licensed well drilling contractors and qualified to bid on Bid Request No. 9237 issued by Southwest Florida Water Management District ("SWFWMD" or "District"), Respondent. On July 23, 1992 the District mailed packets for bid requests to ADI, Youngquist Brothers, Inc., and others. On August 12, 1992 a mandatory pre-bid meeting for Bid Request No. 9237 was conducted at the District office. Representatives of ADI and Youngquist attended the pre-bid meeting. Responses to Bid Request No. 9237 were opened by the District on August 26, 1992. ADI's bid was for $159.50 per hour, and Youngquist's bid was for $200.00 per hour. Greg McQuown, District Manager of the Geohydrologic Data Section prepared the technical portions of this bid request and, following the bid opening, visited the facilities of both ADI and Youngquist as provided in Section 2.1.1.19 of the bid specifications to observe the equipment they proposed to use. Request for Bid No. 9237 requested bidders to submit an hourly rate for furnishing an experienced crew, the drilling rig and all equipment, materials, fuel and services necessary for the proper operation and maintenance of the drilling rig to be used in drilling numerous monitoring wells as directed by the District. Although the bid is for one year, it is renewable for two additional years. Drilling contracts on an hourly basis are not frequently used in water well drilling contracts, but for this project, this type contract appeared preferable to the District due to the wide variations in well depths and drilling conditions. Speed of drilling is a very significant element in an hourly rate drilling contract. Section 1.17 of the general conditions of Request for Bid No. 9237 provides in pertinent part: If bids are based on equivalent products, indicate on the bid form the manufacturer name and number. * * * The bidder shall explain in detail the reason(s) hoe (sic) the proposed equivalent will meet the specifications and not be considered an exception thereto. Bids which do not comply with these requirements are subject to rejection. Bids lacking any written indication of intent to quote an alternate brand will be received and considered in complete compliance with the specifications as listed on the bid form. Section 1.11 of the general specifications provides: 1.11 BID DATA. Bidders shall furnish complete and detailed Bid Data as specified on the Request for Bid Form. Bids furnished without data, or incomplete submissions may be rejected at the discretion of the District. Exceptions to the requirements, if any, shall be noted in complete detail. Failure by the bidder to detail each exception to a bid specification or a requirement results in the bidder being required to meet each specification or requirement exactly as stated. Section 2.2.2.3 under Contractor Equipment and Services (exhibit 2) lists the following equipment: API 3 1/2 inch drill pipe, no hard banding, square shoulders acceptable, 1,400 feet. API 4 3/4 inch steel drill collars 10,000 lbs. (approximately 200 feet). API 7 to 7 1/2 inch steel drill collars, 13, 500 lbs. (approximately 100 feet) are acceptable equivalent. Rig equipped with hydraulic torque equipment for drill collars and drill pipe. The drilling contemplated by this Bid Request is reverse air drilling in which an air hose is inserted inside the drill pipe and air from this hose facilitates a removal of the material through which the drill bit penetrates. ADI's Bid Proposal (exhibit 4) under Equipment List provides in pertinent part: Drill stem 4 1/2" flush joint 2 1/8 ID Collars 2 @ 3 1/2" X 20' 1 @ 6" X 20' -2 @ 7 3/4" X 30' * * * Above listed tools available, we will make available any other specified tools. The inside diameter (ID) of API 3 1/2 inch drill pipe is 2 11/16 inches. This size pipe will allow use of a 3/4 inch air hose and still provide adequate area for the drilled material to be excavated from the hole being drilled. Further, this Bid Request proposed the use of 6 inch PVC casing to be provided by the District. Thus, the drill pipe and drilling equipment needed to pass through this size casing. The function of the drill collar is to provide weight on the drill bit to insure a straight hole as well as increase the speed of drilling. All else being equal (especially speed of rotation of drill bit) the greater the weight the faster the drilling. Standard API 3 1/2 inch drill pipe has an outside diameter of 4 3/4 inches and is the largest standard drill pipe that can be used in the 6 inch casing here proposed. Not only does the 4 1/2 inch drill pipe proposed for use by ADI have a smaller ID than API 3 1/2 inch drill pipe specified, but also this is not a constant ID but constricts to this 2 1/8 inch ID where pipe sections are connected. This constriction can increase the turbulence in the pipe and slow the removal of the drilled material. The cross section area of a 2 1/8 inch ID pipe is 5/8 the area of a 2 11/16 inch ID pipe. Accordingly, drilling with the API 3 1/2 inch pipe can be much faster than with a drill pipe with a 2 1/8 inch ID due solely to the greater volume flowing through the 3 1/2 inch pipe. The 4 1/2 inch drill collars listed in ADI's bid proposal weighed in at 1100 pounds in lieu of the 4 3/4 drill collars and 10,000 pounds specified in Request for Bid. ADI contends that by adding the words "above listed tools available, we will make available any other specified tools" they clearly intended to provide all equipment demanded by the District. This is the type language which leads to contract disputes. All of Petitioner's witnesses testified that they intended to commence the work, if awarded the contract, with the equipment listed on their bid proposal. On an hourly drilling contract this equipment is inadequate. All of these witnesses also testified they would use the equipment listed in the Request for Bid specifications if required to do so by the District. Neither Dave Robinson, Petitioner's superintendent who prepared its bid and attended the pre-bid conference, nor Jerry C. Howell, President of Petitioner who modified and approved the bids submitted, had ever used API 3 1/2 inch drill pipe and were not familiar with the dimensions of that item. Yet they did not check to ascertain how the inside diameter of that drill pipe compared with the inside diameter of the 4 1/2 drill stem flush joint they had on hand. Petitioner further contended that the cost of the API 3 1/2 inch drill pipe was insignificant in determining the bid price submitted, and therefore, this discrepancy was immaterial and should not lead to rejection of the bid. Petitioner's bid failed to comply with General Conditions 1.17 in that it failed to explain in detail the reasons the 4 1/2 inch drill stem proposed for use meets the specifications which required a drill pipe with a substantially larger minimum interior cross section area. Petitioner's challenge to Youngquist's bid proposal as being non- responsive for not listing the API 3 1/2 inch pipe is without merit. Youngquist's bid complied with the provision of Section 1.11 of the General Specifications and McQuown's visit to Youngquist's facility confirmed that Youngquist had on hand all of the equipment specified in the Request for Bid Proposal. Petitioner was represented at the compulsory pre-bid conference by David Robinson, ADI's superintendent, who prepared ADI's bid package. Robinson testified that at the pre-bid conference he asked Mr. McQuown what was the inside diameter of the API 3 1/2 inch drill pipe and McQuown responded 1 7/8 inches. Several other witnesses, including McQuown, testified that no questions were asked at the pre-bid conference about the API 3 1/2 inch pipe and all of these witnesses were fully aware that the pipe has an ID greater than 2 1/2 inches. McQuown's testimony that Robinson asked only about the inside diameter of the 4 3/4 inch drill collar shown in the bid specifications and he responded 1 7/8 inches to that question is deemed the more credible evidence. Robinson testified that he thought McQuown has misspoke when he said 1 7/8 inches but did not check available catalogues to determine the actual ID of this pipe to shed some light on the adequacy of the 4 1/2 inch drill pipe proposed in ADI's bid. The more credible testimony is that Robinson was not misinformed about the ID API 3 1/2 inch drill pipe at the pre-bid conference.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the formal bid protest filed by American Drilling, Inc. to challenge the award of Bid Request 9237 be dismissed and that the contract be awarded to Youngquist Brothers, Inc. DONE AND ENTERED this 15th day of February, 1993, in Tallahassee, Leon County, Florida. K. N. AYERS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of February, 1993. APPENDIX TO RECOMMENDED ORDER, CASE NO. 92-6618BID Proposed findings listed by Petitioner are accepted except as noted below. Those neither noted below nor included in the Hearing Officer's findings were deemed unnecessary to the conclusions reached. 16. Rejected. Although there can be a slight variation in the internal diameter of API 3 1/2 inch drill pipe, there is no API 3 1/2 inch drill pipe with an inside diameter less than 2 1/2 inches. 18. Rejected as contrary to the credible evidence. Rejected. ADI fully intended to use the drill pipe and collars listed on its bid unless or until the District mandated a change to the equipment or tools specified. Both of Petitioner's principle witnesses believed the 4 1/2 inch drill stem listed could satisfactorily perform the required drilling. Rejected as contrary to the evidence. Accepted as a fact that after ADI learned it was low bidder inquiries were made to locate a source for the specified drill pipe and collars. At McQuown's visit to ADI, Jerry C. Howell assured him that ADI wanted to fully cooperate with the District in carrying out the contract when issued. Rejected that ADI's response was clear and complete as required by the specifications. Second sentence rejected as irrelevant and immaterial. Rejected as irrelevant. Diversified was not a party to these proceedings. Rejected. Youngquist's bid complied with the bid specifications. By not responding to those items in the bid specification, Youngquist, pursuant to the General Bid Specifications, agreed to provide exactly the equipment specified by the District in the Request for Bid. 32. These omissions have never been deemed by the District to be grounds for rejecting bids. 33 -34. Rejected as immaterial. 36. Although McQuown testified that he did not pay a lot of attention to the general (boiler plate) conditions in the bid proposal, he recognized that the failure of a bidder to list equipment different than that contained in the bid proposal meant that the bidder intended to supply the equipment specified. See 36 above. Rejected as irrelevant. Last sentence rejected as immaterial. First sentence rejected. Rejected. First sentence rejected. 46 - 49. Rejected as immaterial. 51. Rejected insofar as Youngquist's bid is concerned. 53. Last sentence rejected. Rejected as improper and inaccurate interpretation of the contract provisions. Moreover, this is a question of law, not of fact. The bid specifications speak for themselves. Interpretation of these specifications is a legal not a factual matter. Last sentence rejected. Last sentence rejected. Rejected as fact, accepted as a conclusion of law. See 36 above. 63 Generally accepted. However, it is found that all parties recognize that it was not necessary for bidders to have on hand all equipment requested in the bid specification, and that ADI representatives indicated that they would like to start work with the equipment on hand and would do so unless otherwise directed. Proposed joint findings submitted by Respondent and Intervenor are accepted. Those not included in the Hearing Officer's findings were deemed unnecessary to the conclusions reached. COPIES FURNISHED: Douglas Manson, Esquire Mary Catherine Lamoureaux, Esquire Post Office Box 499 Tampa, Florida 33601-0499 Richard Tschantz, Esquire A. Wayne Alfieri, Esquire 2379 Broad Street Brooksville, Florida 34609-6899 Mark R. Komray, Esquire Thomas Smoot, Esquire Suite 600 12800 University Drive Fort Myers, Florida 33906-6259 Peter G. Hubbell, Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899
Findings Of Fact At all times material to this proceeding, Sandra B. Frazier was a licensed real estate broker-salesman in the State of Florida, License No. 0185565, as an associate with Property Associates, Inc., Tallahassee, Florida. On July 1, 1989, Howard M. Burkholz, Leslie Burkholz, and Jacob H. Schiff entered into an Exclusive Right of Sale Agreement with Property Associates, through its agent, Frazier, for the sale of a house located in Forest Green Subdivision, at 2062 Pepperidge Way, Tallahassee, Florida. The Exclusive Right of Sale Agreement states in part: Seller further certifies and represents that the property has no latent defects except the following: septic tank is pumped monthly at Sellers request. [sic] Mr. and Mrs. Burkholz both told Frazier that the septic tank was not a problem, but Frazier had previous knowledge of septic tank problems in the vicinity and of the significance of needing septic tank pumping. Frazier sold the house across from the Burkholz's house. That house, at 2061 Pepperidge Way, was bought by Marcie Doolittle in December of 1988. The listing information and Notice to Prospective Buyers showed that, due to the composition of the soil and heavy rains, it was necessary to have the septic tank pumped. The seller offered an offset to the buyer for the cost of additional drainfield. Only after Doolittle bought the house did Frazier learn of the severity of the problems and the necessity for pump outs every two weeks. In a letter written by Frazier to Doolittle on February 9, 1989, Frazier indicated that "once a septic tank fails it does not correct itself. It then requires regular pumping." Frazier suggested that the only resolution was more drainfield or regular pumping. After Frazier listed the Burkholz house, she mentioned to Mrs. Doolittle that she could not show the Burkholz house during wet weather because the backyard, in which the septic tank and drainfield was located, was too boggy. Further, Frazier discussed with Mrs. Doolittle that the city was going to install sewer in the area because of the septic tank failures. In conformance with the Exclusive Right of Sale agreement with the Burkholzs, Frazier listed the house through the Multiple Listing Service. The data on the house was input on an input sheet. If there are defects, they can be listed on lines RE1-RE4 on the input form. Despite her knowledge about the Burkholz's septic tank and the Doolittle's septic tank, Frazier did not list this as a defect. Mary Wheatley, a sales associate with Bob Wolfe Real Estate, worked with Jesse and Susan Day to locate a house to purchase. She showed the Days the Burkholz house. Her only knowledge of that house came from the MLS listing, the brochure entitled Highlights of this Home prepared by Frazier, and from information verbally given by Frazier. Wheatley had no knowledge of the septic tank problems and Frazier did not tell her anything about the septic tank or the potential hook up to city sewer. After various offers and counteroffers, the Days and the Burkholtzs signed a contract for the sale and purchase of the house on November 24, 1989. The Contract states in paragraph 14: CONDITION OF PROPERTY: BUYER ACKNOWLEDGES THAT HE HAS NOT RELIED UPON ANY REPRESENTA- TIONS MADE BY A REALTOR(S) AS TO THE CONDI- TION OF THE PREMISES. . . .SELLER warrants that the . . . septic tank . . . shall be in working order on the date of closing. SELLER agrees to repair any of the preceding items not in working order. BUYER agrees to inspect the property prior to closing to determine condition of said items; . . . If BUYER fails to make inspections as required, BUYER agrees to accept property in "as is" condition. BUYER and SELLER will diligently learn and disclose to each other prior to closing all facts affecting the value of the property. On December 26, 1989, the night before the closing, the Days, the Burkholzs, Frazier, and Wheatley did the final walk through. While Wheatley and Susan Day were in another room measuring for curtains, Mr. Day flushed a toilet and noted that it went down very slowly. He asked if there were septic tank problems. Mr. Burkholz indicated that there were, but that sewer hookup was coming and the septic tank was pumped out monthly by the city at no cost. Mr. Day asked about the costs and was told that the pumpouts were free and the sewer would cost several hundred dollars. There is a clear conflict in the testimony of the various witnesses about the sewer cost estimate given to Mr. Day, but the exact figure is of no consequence to the ultimate outcome of the case. Therefore the conflict is not resolved. The Days discussed the septic tank and sewer hookup and decided to go through with the closing. After the walk through, they signed an inspection sheet in which they accepted the premises as inspected, without any noted exceptions, and they relieved the sellers and the realtor from further warranty or responsibility for the condition of the property. According to Thomas Bryant, an engineer with the City of Tallahassee, in December, 1989, no one knew whether there would be sewer installed in Forest Green or the potential cost of sewer hookup. No one knew that even on the date of hearing. The city did enter into an agreement to charge $650 for sewer hookup in Forest Green, but there are additional charges and costs to the homeowner which are as yet undetermined. The septic tank problems constitute a latent defect which should have been disclosed to the buyers before a contract was agreed upon. The failure to disclose is not egregious since the regular pumping of the septic tank is done at no cost to the homeowner and results in no liability to the homeowner. The projected sewer hook up was too uncertain to have required such disclosure.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Florida Real Estate Commission enter a Final Order and therein: Find Sandra B. Frazier guilty of one Count of concealment in violation of Section 475.25(1)(b), Florida Statutes. Based on the mitigating factors set forth above and on the relatively minor nature of the offense, impose a fine of $100.00 on Sandra B. Frazier. Issue a written reprimand to Sandra B. Frazier. RECOMMENDED this 27th day of March, 1991, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of March, 1991. APPENDIX TO THE RECOMMENDED ORDER, CASE NO. 90-6189 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the proposed findings of fact submitted in this case. Specific Rulings on Proposed Findings of Fact Submitted by Respondent, Sandra B. Frazier Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1(1). Proposed findings of fact 2-9 are subordinate to the facts actually found in this Recommended Order. COPIES FURNISHED: Janine B. Myrick Senior Attorney Department of Professional Regulation Division of Real Estate 400 West Robinson Street Post Office Box 1900 Orlando, FL 32801-1772 William J. Haley Attorney at Law Post Office Box 1029 Lake City, FL 32056-1029 Jack McRay, General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Darlene F. Keller Division of Real Estate 400 West Robinson Street Post Office Box 1900 Orlando, FL 32801
The Issue The issue is whether Respondent violated Sections 455.227(1)(a) and 471.033(1)(g), Florida Statutes.
Findings Of Fact Mr. Maples is a licensed professional engineer in the State of Florida. He holds license no. PE 10214, and he practices engineering in the Panama City, Florida, area. During all times pertinent Mr. Maples held an active license and practiced pursuant to it. FEMC is charged with providing administrative, investigative, and prosecutorial services to the Board pursuant to Section 471.038, Florida Statutes. The Board exists pursuant to Section 471.007, Florida Statutes, and is authorized to discipline engineers under its authority by Section 455.225, Florida Statutes. Mr. Maples signed and sealed three pages of sprinkler system plans for the Wellness Center at Gulf Coast Community College (Wellness Center), located in Panama City, Florida. These plans were admitted as Petitioner's Exhibit No. 2. No date can be observed on the seal on Petitioner's Exhibit No. 2. It either is illegible or a date was never placed upon it. Hydraulic calculations, which use drawings as a source document, and which appear to coincide with Petitioner's Exhibit No. 2, were dated November 15, 2001. It is deduced, therefore, that Petitioner's Exhibit No. 2 was drawn on or about November 15, 2001. Petitioner filed an Administrative Complaint against Respondent on April 1, 2005. The Administrative Complaint alleged that the plans and calculations for the Wellness Center demonstrated negligence in the practice of engineering. That charge resulted in an final hearing conducted by Administrative Law Judge Stephen Dean on August 11, 2005. That case number was DOAH Case No. 05-2049PL. On October 13, 2005, Judge Dean recommended that the Complaint be dismissed. One of the allegations of negligence in 05-2049PL, related to a charge that inadequate water would be supplied to the hydraulically most demanding (HMD) area in the event of a fire. It was alleged, and proof was elicited, that a single 1 and 1/4-inch pipe traveling from a riser, across the men's shower area to the women's shower area, would be insufficient. This pipe is identified on Petitioner's Exhibit No. 2 as a line between Node 45 and Node 25. This pipe leads to a "T" intersection and further piping carries water, when activated, to the women's shower area. The matter of whether adequate water would be supplied to the HMD devolved into whether the plans called for one 61- foot long, 1 and 1/4-inch diameter pipe, or two 61-foot long, 1 and 1/4-inch diameter pipes. Because there was no pump provided on the drawings, and in fact there was no plan to install a pump, two 61-foot long, 1 and 1/4-inch diameter pipes were necessary to provide sufficient water in case of fire. As was illuminated in Case No. 05-2049PL, calculations were made, based on the drawings, in order to ensure that the HMD area will receive 1500 square feet of coverage per sprinkler head required by the contractor. The coverage required by the contractor exceeds that required by National Fire Protection Association-13 standards. HMD calculations are made at a point most remote from the source of water. The hydraulic calculations are produced through the use of a commercially produced computer program. Calculations from Case No. 05-2049PL became Petitioner's Exhibit No. 3 in this case. At the hearing in Case No. 05-2049PL, the allegation that the fire sprinkler plans signed and sealed by Mr. Maples would not provide adequate water pressure to the HMD area was rejected by Judge Dean. This is because Mr. Maples claimed that the plans, when viewed in light of the calculations, actually depicted two 61-foot long pipes, 1 and 1/4-inch and Judge Dean, while determining that the depiction was inadequate for that purpose, found in essence that adequate water would be provided to the HMD. Mr. Maples works closely with Chris Thomas, a sprinkler contractor whose license does not permit him to design a fire suppression system that consists of more than 49 heads. Their working arrangement is such that it would be expected that Mr. Thomas would understand Mr. Maples' drawings even if they were not as complete as they would be if the drawings were made for a contractor other than Mr. Thomas. In fact, Mr. Thomas participated in the production of the drawings signed and sealed by Mr. Maples. More than one set of drawings were used for the Wellness Center project. The project came under the jurisdiction of the Florida Department of Education. That agency approved the plans and the Florida State Fire Marshal approved the plans, although it is not certain that the plans those agencies approved were Petitioner's Exhibit No. 2. There were errors in the data entry on the hydraulic calculations. The building was completed prior to the time Case No. 05-2049PL was heard on August 11, 2005. Using the plans drawn by Mr. Maples, Mr. Thomas's foremen for the Wellness Center installed a single pipe between Node 45 and Node 25. On a weekend subsequent to the hearing in Case No. 05-2049PL, Mr. Thomas went to the Wellness Center and discovered that only one 61-foot long, 1 and 1/4-inch diameter pipe had been installed in the area represented to be between Node 45 and Node 25. Mr. Thomas immediately installed a second 61-foot long, 1 and 1/4-inch diameter pipe. Mr. Maples never went to the site and, accordingly, was unaware at the time he testified in Case No. 05-2049PL, that only one pipe had been installed. The Administrative Complaint lists five statements made by Mr. Maples in Case No. 05-2049PL that are alleged to express "an opinion publicly on an engineering subject without being informed as to the facts relating thereto." The five statements are further alleged to describe testimony that was, "untruthful, deceptive, or misleading in any professional statement or testimony." As noted above, the statements do not cite with particularity to the Transcript in Case No. 05-2049PL. The five statements read as follows: Respondent testified at the hearing that the line on the plans appearing as a single pipe, in fact, represented two pipes, 61 feet long with 1 1/4 inch diameters, running over the men's showers. Respondent testified at the hearing that the intent to install the sprinkler system with two pipes over the men's showers was obvious to anyone with experience in fire sprinkler systems. Respondent testified that he had signed and sealed revised plans showing a second parallel line over the men's showers. Respondent testified that the second 61 foot long 1 1/4 inch diameter pipe was represented in his calculations by a 3 foot length of pipe. Respondent testified that he used pipe lengths in the supporting calculations that match the pipe lengths shown in the plans. The actual testimony of Mr. Maples that addresses the pipes follows below. The initial questions were posed by Mr. Maples' attorney, Mr. Peters at page 260, line 13, of the Transcript in Case No. 05-2049PL. . Q. Okay. Now, the bulk of this allegation was that the hydraulically demanding design area did not have sufficient water pressure. Let's talk about that. Does the most hydraulically demanding area in this project show that it was receiving sufficient water pressure and distribution? A. Yes, the calculations show that specifically. Q. Do you have any concern that the most hydraulically demanding area is being under served? A. I do not. Q. Do the plans -- while they may not be perfect -- do they reasonably and competently show sufficient water pressure getting to the most hydraulically demanding area? A. Yes. (At this point there was a recess. Subsequently, the interrogation continued.) * * * Q. So do the plans and do the calculations show that there's sufficient water getting to the most challenging -- A. Yes, it does. Q. Okay. And let's take a minute to just make sure we review our nodal system. (At this point the Court interjected and moved the questioning away from the nodal system. The nodal system had been reviewed earlier in the hearing.) * * * Q. How is that? Okay. There is a segment called 20 to 25, which is an inch-and-a-quarter, 61 feet long. A. Correct. Q. And is there a parallel pipe in the same plane that runs along that same segment? A. Yes. Q. How can you tell that from this drawing and this set of calculations? A. I can tell on the calculations, because it tells me from 25 to 30, there's a connection. It tells me that 30 is connected to a three-inch main. Q. All right. Can you show these calculations and -- go over them with us and show us how you see that from these documents? A. Where is my set? Q. Right there. That's yours. THE COURT: Let me ask you this, sir. I see where it says that it's connected to that. But by [sic] my question is, it says that it's only 3-feet long. THE WITNESS: Three feet. Yes, sir. Let me -- can I address that? THE COURT: Surely. THE WITNESS: That is -- I will say an input error on it. But I want to tell you that it doesn't make any difference into the function of the system. BY MR. PETERS: Q. Tell us why not. A. It says 25 to 30 tells me there's a line, a connection to a 3-inch -- to node 30. What that tells me is that 3-inch line is feeding this row of sprinklers right here. Even though it says 3 feet, what it does, it has a short segment of line that just gushes water through there and makes those sprinklers flow a whole lot more than it needed. All right. When you put the right length, you put 61 feet in there, it comes back to just about what this line does, and it cuts the sprinkler flow down in those three areas. But it doesn't effect [sic] the function of the system because it doesn't effect [sic] the head loss in the main system where the pressure goes in the 3-inch line. Q. Head loss. Take a minute to try to explain that. A. The water -- it doesn't effect [sic] the pressure that the sprinklers are getting. What it does, when you put 61 feet in there, those three sprinklers that where it shows a 3-feet [sic] connection, it cuts them down from sprinkling a whole lot more water that's needed back to what's required. But as you go along this -- as you go along this line, go along this line where the 3-inch line is up here, at each place on the 3-inch line, there's a branch that goes towards the sprinklers. And each branch line is calculated separately. And the most demanding branch line is what puts the pressure that's required -- the flow -- required a 3-inch line. So what the 3-foot did, it made these three sprinklers right here flow considerably more, because it was just a little short piece of pipe and didn't have any friction loss going down through there. But it didn't effect [sic] -- it didn't effect [sic] the system head. Because that had less head loss than this one did. So when you put -- BY THE COURT: Q. Head loss is effected [sic] by, what? A. The length of pipe. Flow -- the length of pipe and size of pipe. Q. So will a longer piece of pipe -- assuming all the pipes are the same diameter -- does the pipe -- does the head loss on a short piece, is it greater than a long piece? A. Oh, no. Head loss on short pieces are considerably less than a long piece loss. The further it travels, the more pressure it loses. Q. Okay. And the pressure loss is transmitted, if you will, back to the 3-inch main? It effects [sic] the -- A. It effects [sic] what the flow comes from a 3-inch main. The 3-inch main effects [sic] it, because the three-inch main has the water supply, and has the pressure that's pushing it. Q. So the calculation for this system -- A. Yeah. Q.-- even though there's an error, the error is not a critical error? A. No, sir, it does not effect [sic] the function of the system. Q. It doesn't effect [sic] the function of the system. Thank you. A. What it does, it shows a little more water flow. THE COURT: Okay. DIRECT EXAMINATION (RESUMED) BY MR. PETERS: Q. So do the plans -- does it need a pump to get water to this area? A. No, sir. THE COURT: Now, let me ask you a follow up on that. THE WITNESS: All right. THE COURT: After Mr. Schmidt put his input in, and he was basically engaged to do exactly what he did, and that was, to go through the plans, catch any things that he was concerned about, and turn that back to the general contractor so the general contractor could go back to the people he needed to go back to? THE WITNESS: Yes. THE COURT: The general contractor came back to you, and you did whatever was necessary to generate the second set of plans that you-all put in, which is your Respondent's 1? MR. PETERS: Well, although Respondent's -- can I ask him a couple of questions? THE COURT: Sure. BY MR. PETERS: Q. Respondent's 1, this is the one that shows the second line, the parallel lines, right? A. Yes, if this is the plan we're looking at, it shows the second -- physically shows -- separated it so anybody could see. THE COURT: It also shows the point of service. THE WITNESS: Yes, it also shows a different point of service. It shows --bring it back up to the 5. BY MR. PETERS: Q. But these don't bear your signature. A. This particular set doesn't. We signed some, but I don't know where they are. That came from Gulf Coast College there. Q. All right. All right. In terms of what this case is directly about, then, do the plans provide pipes with adequate diameters for water pressure to provide protection for the area most remote from the main riser? A. Absolutely. Q. Do the plans provide -- do the plans need to show a pump to increase water pressure for the pipe design use? A. No. Q. And did you use pipe lengths in the supporting calculations that match the pipe lengths shown in the plans? A. Yes. (At this point Mr. Peters addresses another matter. Thereafter, Mr. Campbell proceeded with his cross-examination on Page 268, line 25.) * * * BY MR. CAMPBELL Q. Mr. Maples, there was no testimony about phantom pipes in that previous case, was there? A. No. Q. And you would admit that if there was no pipe underneath this Node 25 pipe, that this fork of six sprinkler heads would not adequately be served by 1-and-a-quarter inch diameter pipe; isn't that correct? A. That's correct, with a caveat. The NFPA 13 has a section that says on the density .1 in a 1500 square feet [sic] area, if it is - - if it says ceiling heights less than 20 feet, and this is 10, that you can reduce the area of sprinkling by 40 percent. So that means, if we did that, we would do 900 square feet, and that would be adequate. Now, if you went strictly by NFPA 13 -- Q. But that's not what you drew here. You drew or attempted to draw 1500 square feet. A. That's what we were told to do. But that's not in accordance with NFPA 13. NFPA 13 is less. And we agree NFPA 13 rules. Q. Now, you initially said this was your initial set of plans before you got any input such as being told to do 1500 square feet; is that correct? A. No, no, I was told to do that to start with. Q. All right. Was that part of the specifications on this job? A. I didn't see it. That was --according to the contractor, that was the specifications from Schmidt or whoever they were. Q. All right. Now, looking at the Respondent's 1 you did not sign. A. That one is not signed, but I know there were some that were signed. Q. Doesn't it appear that in these entries for pressures and static pressures, at some point, there was a whiteout and a reentry on the first page of the sheet? A. I can't tell you that. It may have been. Q. All right. Now, in fact, you have got two separate entries of written information where some of those are different. For instance, the required pressure is different -- A. Yes, because it's a different system. This is one that's not in contention right here. This was the gym. It's got the same static pressures and flows, but this is a different set of calculations of the gym. This has not been -- that was for the gymnasium, just to see if there was enough water. They asked us to do that. Q. Now, is the gymnasium a part of the Wellness Center? I thought that was what the Wellness Center was. A. Well, it's part of the Wellness, yes. But it's a separate part. But this has never been in contention. Q. Well, now, on the set of plans, your initial set of plans, there were no such double entries? A. No, they didn't ask for it then. Q. And this separate set of entries here for the gym -- well, this -– yeah -- is still used by the same riser and the same -- A. Yes, sir. Q. -- point of service. A. Yes, sir. Q. So there would be a separate set of calculations somewhere for the gym; is that what you're saying? A. My understanding, they asked Chris to do a set of calculations just so they would have plenty of water at the gym. That's never been in contention. Because one thing, it's located right at the riser. Q. Now, isn't it a fact, if someone never looked at the calculations but only looked at page 2 of Exhibit P-1, that where the node 25 seems to go up to node 45, there is only one line indicating one pipe? A. Depending on who looks at it. Anybody familiar with the calculations and sprinkler systems would know. Q. If they saw no calculations whatsoever, they just looked at this sheet -- A. I would assume so. If it was Joe Blow out there that knew nothing, he would have probably been, you know -- Q. He would think there's one pipe there. A. Who would do that? Q. So the basis of your statement that anyone that knew that there had to be more than one pipe is -- anyone with experience in fire protection systems would know you could not feed -- A. That's correct. Q. -- 6 heads 60 feet down from the 3-inch pipe on a one -- A. An inexperienced person, probably, correct. Q. Well, now, an experienced person would know automatically you couldn't feed it that way, right? You would have to have a second pipe; that's what you're saying? A. Well, you would have to go by the calculations. I didn't say that. Q. But if you didn't go by the calculations, if you didn't know anything about the calculations, would it be obvious to anyone with experience in fire protection sprinkler systems that at the end of 60 feet of a one-and-a-one-quarter-inch pipe you could not support 50 pounds pressure -- support 6 heads on 1 inch pipe? A. I wouldn't say that. Because if I was an experienced person in fire protection and installation, I would look at that, and I would look for something else to see if there was something else. Q. So that sheet of plans by itself is insufficient even with someone with experience in fire protection? A. No, I didn't say that. I said I would be looking for something else. Q. You said you would be looking for something else. A. He would know that there was something supporting it. And especially a licensed contractor that's licensed to design sprinklers, too. He would obviously know. The statement set forth in paragraph 7, of the Administrative Complaint does not appear in the Transcript in Case No. 05-2049PL. Mr. Maples said nothing about showers. He did not say that the single pipe represented two pipes each of which was 61 feet long. What he said was that the calculations told him that there is a parallel pipe in the same plan as the pipe shown on the drawings. He said he could tell that because the calculations showed from Node 25 to 30 a connection to a 3- inch main. Mr. Maples' testimony in this regard was confusing and difficult to follow but not untruthful, deceptive, or misleading. He was not giving fact testimony but was expressing an opinion. The statement set forth in paragraph 8, of the Administrative Complaint does not appear in the Transcript in Case No. 05-2049PL. Mr. Maples never said that the "intent to install the sprinkler system with two pipes over the men's showers was obvious to anyone with experience in fire sprinkler systems." What he said was, that, "Anybody familiar with the calculations and sprinkler systems would know." He further said that if someone familiar with sprinkler systems would know that two pipes were necessary looked at the plans without the calculations that he "assumed" they would know there should be two pipes. With regard to the statement set forth in paragraph 8, when offered to agree with the statement, ". . . an experienced person would know automatically you couldn't feed it that way, right? You would have to have a second pipe; that's what you are saying?" Mr. Maples declined. In response to the question he said, "Well, you would have to go by the calculations. I didn't say that." Mr. Maples' testimony in this regard was not untruthful, deceptive, or misleading. He was not giving fact testimony but was expressing an opinion. The statement alleged as paragraph 9 does not appear in the Transcript. With regard to other plans, he said in response to a question about Respondent's Exhibit No. 1 that, ". . . it shows the second--physically shows--separated so any body could see." He noted that Respondent's Exhibit No. 1 did not bear his signature but said that he had signed some similar plans. There is no proof in the record that his testimony in this regard was untruthful, deceptive, or misleading. The allegation in paragraph 10 of the Administrative Complaint was that Mr. Maples said that the second 61-foot long, 1 and 1/4-inch diameter pipe "was represented in his calculations by a 3 foot length of pipe." Mr. Maples never uttered that statement. In response to a question from Judge Dean, with regard to the 3-foot long pipe, Mr. Maples said, "That is--I will say an input error on it." Mr. Maples' testimony in this regard was confusing and difficult to follow but not untruthful, deceptive, or misleading. The allegation in paragraph 11 of the Administrative Complaint was that Mr. Maples said that, "he used pipe lengths in the supporting calculations that match the pipe lengths shown in the plans." This allegation approximates a verbatim statement made by Mr. Maples. However, he had earlier noted, and thus qualified the statement when he stated that there was input error. Mr. Maples' testimony in this regard was not untruthful, deceptive, or misleading. The allegations contained in the Administrative Complaint at paragraphs 7 and 8, were fairly alleged as the opinions of Mr. Maples. The opinions alleged are in essence that a person with experience in the fire suppression business could determine from the plans and calculations that a second 61-foot long, 1 and 1/4-inch pipe would run parallel to the pipe shown from Node 25 to 45. After an exhaustive study of the plans and calculations in this case, the Administrative Law Judge has not been able to conclude that the testimony as to the second pipe is borne out by Petitioner's Exhibit 2 or the calculations that are Petitioner's Exhibit 3. Moreover, Judge Dean found that the intent to have two pipes, "was not adequately shown in the original drawings." The foremen sent by Mr. Thomas to install the system did not conclude that two parallel pipes were required. They installed only one. An expert called by FEMC, Larry Simmons, an expert in professional engineering, stated unequivocally in this case that using Mr. Maples' drawings and calculations, he could not determine that a second 61-foot long, 1 and 1/4-inch pipe was called for by the plans. Judge Dean was not misled by Mr. Maples' testimony in Case No. 05-2049PL, with regard to the pipe. This was indicated by his acknowledgement in Finding of Fact 8 in his Recommended Order that the intent to have two pipes, "was not adequately shown in the original drawings." Judge Dean was not called as a witness so that he could reveal if he was misled based on the information that became available after the hearing in Case No. 05-2049PL. It was not proven by clear and convincing evidence that Mr. Maples was "untruthful, deceptive, or misleading in any professional statement or testimony." As will be discussed in detail below, Mr. Maples engaged in misconduct in the practice of engineering by expressing an opinion publicly on an engineering subject without being informed as to the facts relating thereto.
Recommendation Based upon the Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Board find that Respondent Lester M. Maples did not violate Section 455.227(1)(a), Florida Statutes, but that he offered an opinion publicly on an engineering subject without being informed as to the facts relating thereto in violation of the prohibitions contained in Section 471.033(1)(g), Florida Statutes. It is further recommended that he be reprimanded, placed on two years' probation, and ordered to pay an administrative fine of $1,000. DONE AND ENTERED this 28th day of April, 2006, in Tallahassee, Leon County, Florida. S HARRY L. HOOPER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 28th day of April, 2006. COPIES FURNISHED: Bruce Campbell, Esquire Florida Engineers Management Corporation 2507 Callaway Road, Suite 200 Tallahassee, Florida 32303-5267 Alvin L. Peters, Esquire Peters & Scoon 25 East 8th Street Panama City, Florida 32401 Paul J. Martin, Executive Director Board of Professional Engineers Department of Business and Professional Regulation 2507 Callaway Road, Suite 200 Tallahassee, Florida 32303-5267 Doug Sunshine, Esquire Vice President for Legal Affairs Florida Engineers Management Corporation 2507 Callaway Road Tallahassee, Florida 32303-5267 Josefina Tamayo, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202
The Issue The issue is whether Palm Beach County's application for a permit to construct a domestic wastewater collection/transmission system in Palm Beach County should be approved.
Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Parties The County is a political subdivision of the State of Florida and is the permittee in this matter. The County Water Utilities Department currently serves approximately 425,000 persons, making it the largest utility provider in Palm Beach County and the third largest in the State of Florida. ITID is an independent water control special district created by special act of the legislature in 1957 and whose boundaries lie within the County. Portions of the transmission line to be constructed by the County will cross easements and roads, and pass under canals, owned by ITID. Petitioners Joseph Acqualotta, Michael D'Ordine, Ann Hawkins, and Lisa Lander all live in areas in close proximity to the proposed transmission line. Lander lives adjacent to the proposed route of the line along 40th Street North, while Acqualotta, D'Ordine, and Hawkins live adjacent to the proposed route along 140th Avenue North. Acqualotta, Hawkins (but not D'Ordine, who resides with Hawkins), and Lander own the property where they reside. Petitioners Troy and Tracey Lee (Case No. 05-2979), Lisa Gabler (Case No. 05- 2980), and Anthony and Veronica Daly (Case No. 05-2982) did not appear at the final hearing. The Department is an agency of the State of Florida authorized to administer the provisions of Part I of Chapter 403, Florida Statutes, and is the state agency charged with the responsibility of issuing domestic wastewater collection/ transmission permits under Section 403.087, Florida Statutes (2004).1 Background On December 15, 2004, the County filed its application with the Department for an individual permit to construct a domestic wastewater collection/transmission system (Transmission Line). The Transmission Line is one element of the County's Northern Region Utilities Improvement Project (Project) and will be approximately 41,050 feet long and comprised of approximately 32,350 linear feet of 20-inch force main and 18,700 linear feet of 30-inch force main (or nearly ten miles in length). A primary purpose of the Project is to provide water and wastewater service to the Village, a 1,900 acre parcel located in the unincorporated part of the County several miles west of the Florida Turnpike, south of State Road 710, and north of the Villages of Wellington and Royal Palm Beach. The Village will be the home of the Scripps Project and Campus. The Transmission Line will run from the southeastern corner of the Village south to Northlake Boulevard, then east to 140th Avenue North, then south along that roadway to 40th Street North, where it turns east until it interconnects with existing facilities. The wastewater will be collected in a regional pump station on the Scripps Project site, where it will be pumped through the Transmission Line to the East Central Plant, which will be the primary treatment facility. The East Central Plant is owned and operated by the City of West Palm Beach (City), but the County owns between forty and forty-five percent of the treatment capacity. Because the wastewater system is interconnected, the wastewater could also be treated at the County's Southern Regional Plant. Ultimately, the flow from the Scripps Project will be one or two million gallons per day. The Transmission Line is the only way that wastewater can be handled at the Scripps Project. A preliminary analysis by the Department and the South Florida Water Management District determined that on-site treatment was not feasible because of the environmentally sensitive nature of the area. The Scripps Project will include residential units, commercial entities, and institutional uses, such as medical clinics. Besides serving these customers, the Transmission Line will also serve other customers in the area. The County has already signed agreements with the Beeline Community Development District (which lies a few miles northwest of the Village) and the Village of Royal Palm Beach (which lies several miles south-southeast of the Village). At the time of the hearing, the County anticipated that it would also sign an agreement with Seacoast Utility Authority (whose service area is located just southeast of the Village) to transport wastewater through the Transmission Line. All of the treatment facilities have sufficient existing capacity to treat the estimated amount of domestic wastewater that will be generated by the Scripps Project and the other users that will discharge to the Line. The County commenced construction of the Transmission Line in May 2005 when the Department issued the Permit. On August 2, 2005, the County published the Department's Notice to issue the Permit, and once the Petitions were filed, the County stopped construction pending the outcome of this hearing. Approximately seventy percent of the Transmission Line is now completed. The Permit does not allow the Transmission Line to be used until it is pressure tested and certified complete. Upon completion, the County must receive an Approval to Place a Domestic Wastewater Collection/Transmission System into Operation from the Department. Such approval is given only after the County has given reasonable assurance that adequate transmission, treatment, and disposal is available in accordance with Department standards. See Fla. Admin. Code R. 62-604.700. On August 15, 2005, Petitions challenging the issuance of the Permit were filed by ITID and the individual Petitioners. ITID contends that the Transmission Line will convey not only domestic wastewater, but also industrial waste; that the County did not comply with all applicable technical standards and criteria required under the Department's rules; that the Project will be located on ITID's right-of-way, on which the County has no right to occupy; that the Project will be located within seventy-five feet from private drinking wells and does not provide an equivalent level of reliability and public health protection; and that the pipe material and pressure design is inappropriate for the Transmission Line's requirements. The individual Petitioners (who filed identical Petitions) are mainly concerned about the location of the Transmission Line in relation to their private drinking wells and property, the possibility of the pipe bursting or leaking once it becomes operational, and the restoration of their property to its original condition after construction is completed. As to the property claims by all Petitioners, the County plans to place the Transmission Line in property that it either owns or has an easement, in property that it is in the process of condemning, or in a public right of way. While the County acknowledges that it has already placed, and intends to place other portions of, the Transmission Line in easements that ITID says it has the exclusive right to use and for which a permit from ITID is required, the County alleges that it also has the right to use those easements without an ITID permit. The dispute between the County and ITID is the subject of a circuit court proceeding in Palm Beach County, and neither the Department nor DOAH has the authority to decide property interests. Petitioners' Objections Domestic wastewater and pretreatment The wastewater that will be generated by the Scripps Project is considered domestic wastewater; it will not include industrial wastewater. Waste that is industrial or non- domestic must be pretreated to protect the wastewater plant, collection system, and the health of system workers and the general public. The Department administers a pretreatment program through which it requires a public wastewater utility to police the entities that discharge to their wastewater plants. A central part of the pretreatment program is the local ordinance that gives legal authority to the utility to permit, inspect, and take enforcement action against industrial users who are part of the pretreatment program. The utility files an annual report with an industrial user survey, and the Department periodically inspects and audits local pretreatment programs to ensure they are being operated as intended. The system is not failsafe but is designed to ensure that potentially harmful wastes are rendered harmless before discharge. For example, the utility has the authority to immediately shut water off if a harmful discharge is occurring. Both the County and the City have pretreatment programs approved by the Department. The City has an ordinance that allows it to enforce the pretreatment standards for all entities that discharge to its wastewater system. The County Water Utilities Department has a written pretreatment manual, and the County has zoning restrictions on the discharge of harmful material to the wastewater system. It has also entered into an interlocal agreement under which it agrees to enforce the City ordinance. The County provides wastewater treatment to industrial, educational, and medical facilities, and it has never experienced a discharge from any of these facilities that has caused adverse health or environmental impacts. The County pretreatment program for the Southern Regional Facility was approved in 1997. The City pretreatment program for the East Central Regional Facility was approved in 1980. The Scripps Project must apply for a permit from the County and provide a baseline monitoring report, data on its flow, and information on the flow frequency and raw materials. Medical waste from the Scripps Project will be pretreated to render it safe before it is discharged into the Transmission Line. Transmission Line Design The Transmission Line was designed in accordance with the technical standards and criteria for wastewater transmission lines in Florida Administrative Code Rule 62- 604.300(5). That rule incorporates by reference a set of standards commonly known as the Ten State Standards, which contain several of the standards used in the design of this project. These standards are recommended, but are not mandatory, and a professional engineer should exercise his or her professional judgment in applying them in any particular case. The Transmission Line also meets the design standards promulgated by the America Water Works Association (AWWA). Specifically, the County used the AWWA C-905 design standard for sizing the polyvinyl chloride, or PVC, pipe used in the project. The County has received written certification from the manufacturer that the PVC pipe meets the standards in AWWA C-905. The Transmission Line is designed with stub-outs, which will allow for future connections without an interruption of service, and inline isolation valves, which allow the line to be shut down for maintenance. The Use of PVC Pipe There is no standard regulating the selection of PVC pipe material in the Department's rules. Instead, the Department relies on the certification of the applicant and the engineer's seal that the force main will be constructed to accepted engineering standards. The only specification applicable to the Transmission Line is the Ten State Standard, adopted and incorporated by reference in Florida Administrative Code Rule 62-604.300(5)(g). That document contains a general requirement that the material selected have a pressure rating sufficient to handle anticipated pressures in wastewater transmission lines. The Transmission Line will be constructed with PVC piping with a thickness of Dimension Ratio (DR) 32.5, which is the ratio of the outside diameter of the pipe to its thickness. Higher ratios mean thinner-walled pipes. This is not the first time the County has used 32.5 PVC piping for one of its projects, and other local governments in the State have used 32.5 or thinner pipe. The County is typically conservative in requiring thicker-walled pipe, because most transmission lines are built by developers, and the County is unable to design the entire line or control or inspect its installation. The specifications for wastewater transmission lines built in the County call for the use of DR 25 pipe. On this project, however, the County determined that thicker- walled pipe would have been an over-design of the system because the County controls the pump stations and oversees the installation; therefore, the Director of the Water Utilities Department has waived that requirement. The County considers the use of DR 32.5 PVC to be conservative. Although this pipe will be thinner than what is typically used in the County, it satisfies the Department's requirements. The Department has permitted many miles of similar PVC force mains in South Florida, and none have failed. PVC has benefits over other transmission line material, such as ductile iron. For example, PVC is more corrosion resistant. Wastewater generates hydrogen sulfide as it decomposes, which can form highly corrosive sulfuric acid. Some of the older transmission lines in the County that were made of ductile iron have corroded. PVC also has a superior ability to absorb surges, such as cyclical surges, than ductile iron. It is easier to install, and its interior flow characteristics are smoother than ductile iron or pre-stressed concrete pipe. Mr. Farabee, a professional engineer who testified on behalf of ITID, recommended a DR 14 pipe, which is thicker- walled than the DR 32.5 pipe used by the County. While he opined that the DR 32.5 pipe was too thin for the project, he could not definitively state that it would not pass the 150 per square inch (psi) pressure test. He also opined that the pipe is undersized because it will be unable to withstand the surge pressures during cleaning. The witness further testified that the pipe would be subject to much higher pressures than 150 psi, and therefore it was impossible to know whether the pipe would fail. In his opinion, this means the Department did not have reasonable assurance for the project. The County consulted with the Unibell PVC Pipe Association (Unibell) in the planning of this project. Unibell is a trade association that provides technical support for PVC pipe manufacturers. Robert Walker, a registered professional engineer and Unibell's executive director who testified on behalf of the County, disagreed with Mr. Farabee's conclusions concerning the adequacy of the PVC pipe in this project. The AWWA C-905 standard uses a safety factor of two, which means the pipes are tested at pressures that are at least twice their stated design strength. Mr. Walker explained the different standards that apply to PVC pipe. DR 32.5 pipe, which is used in this project, has a minimum interior pressure rating of 125 pounds per square psi. Each pipe section is tested before it is shipped at 250 psi, and the minimum burst pressure for the material is in excess of 400 psi. The pipe also meets a 1000- hour test at 270 psi. In light of these standards and testing, the pipe will pass the two-hour 150 psi test required by the Department. Mr. Farabee expressed some concern that the PVC pipe would be more prone to breakage than ductile iron or thicker PVC. However, the PVC pipe standards provide that the pipe can be flattened at sixty percent without splitting, cracking, or breaking. At shallow depths on dirt roads, ovalation, which occurs when PVC is flattened through pressure, will initially occur, but over time the soil around the pipe will become compacted and result in re-rounding of the pipe. The joints are three times stiffer than the body of the pipe, which will protect the joint from excessive ovalation and leaking, and the use of mechanical restrained joints will further strengthen the joints. There has been no joint leakage in Florida due to deflection of the joints. Finally, there have been no failures of PVC pipe caused by three-feet of fill, which is the depth to which the Transmission Line pipe will be buried. To further protect the pipe, the County optimized its pumping system to avoid cyclical surges by using variable frequency drive pumps that gradually increase and decrease speed rather than just turning on or off. In addition, the pump stations are fed by two power lines that come from different directions and emergency generators, which should lessen the chances of harmful surging. Testing the Installation The anticipated pressures in the Transmission Line will likely be about 50 psi. After installation, the Line will be pressure tested at 150 psi for two hours, which is sufficient to provide the Department with reasonable assurance that the Line will hold pressure and will not leak. Also, the County contract inspectors are on the construction site daily. If problems with the installation arise later, the County has committed to promptly fix the problem, even if it means digging up the line. During the hearing, ITID asserted that the Uniform Policies and Procedure Manual standards, which the County has adopted for use by developers when constructing wastewater transmission lines, should be applied to the County as well. This standard, which requires pressure testing to 200 psi for PVC pipes larger than 24 inches, has not been adopted by the Department and is not an applicable Department permitting standard. Even if it did apply, the Transmission Line would meet this criterion because it is designed to withstand 270 psi for at least 1,000 hours. Mr. Farabee believed that the entire Transmission Line would be pressure tested after the construction was complete, which would require digging up sections of the pipe to install bulkheads. However, this assessment of the County's testing program is incorrect. Leisha Pica, Deputy Director of the Water Utilities Department, developed the schedule for the project, helped develop the phasing of the work and budget, and oversaw the technical aspects. She stated that the County has successfully tested approximately fifty percent of the line that was already installed at 150 psi for two hours and not a single section of the line failed the test. Compaction The County has stringent backfilling and compaction requirements, which are sufficient to ensure the pipe will be properly installed and that there will be adequate compaction of the fill material. The County plans and specifications provide that compaction must be to ninety-five percent of the American Association of State Highway and Transportation Officials (AASHTO) standards for non-paved surfaces and one hundred percent of AASHTO standards for paved surfaces. Even ITID's expert agreed that the compaction specifications are sufficient. Mr. Farabee contended, however, that even though the standards are stringent, the County cannot properly test the installation for compliance with the standards. Mr. Farabee believed that testing of the backfill would be done after all of the construction was complete. In that case, he did not see how the testing could be done without digging many holes to check for the density of the backfill. These assumptions, however, are incorrect. The evidence shows that a total of two hundred sixty-four compaction tests have already been done on the portion of the Transmission Line that was completed. No part of the installation failed the tests. The County has an inspector who observes the installation and pressure tests. The compaction was tested at every driveway and major roadway, as well as every five hundred feet along the route. While Lander and D'Ordine pointed out at hearing that no compaction tests have been performed on the dirt roads which run adjacent to their property and on which construction has taken place, the Department requires that, before the work is certified as complete, non-paved roads must be compacted in accordance with AASHTO standards in order to assure that there is adequate compaction of the fill material. The Sufficiency of the Application When an application for an individual transmission/ collection line permit is filed with the Department, the applicant certifies that the design of the pipeline complies with the Department's standards. However, not all of the details of the construction will be included in the permit application. The Department relies on the design engineer to certify that the materials used are appropriate. The application form is also signed and sealed by a professional engineer registered in the State of Florida. All plans submitted by the County, including the original, modifications, and final version, were certified by professional engineers registered in the State of Florida. After receiving the application, the Department requested additional information before issuing the permit, and the County provided all requested information. The original construction plans that were submitted with the application were changed in response to the Department's requests for additional information. The Permit issued by the Department indicates the Transmission Line would be constructed with ductile iron pipe, but this was a typographical error. ITID maintains that all of the technical specifications for the project must be included in the application, and because no separate engineering report was prepared by the County with the application, the County did not meet that standard. While the County did not submit an engineering report, it did submit sufficient data to provide reasonable assurance that the project will comply will all applicable rules of the Department. As a part of its application package, the County submitted construction plans, which contain the specifications required by the Department. Also, the general notes included in the construction drawings specify the use of restrained joints where appropriate, the selection of pipe material, the pressure testing of the Transmission Line, and other engineering requirements. In addition, the plans contain numerous other conditions, which are also specifications sufficient to fulfill the Department's requirements. Finally, further explanation and clarification of the technical aspects of the application was given by the County at the final hearing. At the same time, the Department engineer who oversaw the permitting of this project, testified that a detailed engineering report was not necessary. This engineer has extensive experience in permitting transmission lines for the Department and has worked on over five hundred permits for wastewater transmission and collection systems. The undersigned has accepted his testimony that in a relatively straightforward permit such as this, the application and attachments themselves can function as a sufficient engineering evaluation. This is especially true here since the County is seeking only approval of a pipeline project, which would not authorize the receipt of wastewater flow unless other wastewater facilities are permitted. Impacts on Public and Private Drinking Water Wells As part of the design of the Transmission Line, the County located public and private drinking water wells in the area of the line. County personnel walked the route of the Transmission Line and looked for private wells and researched the site plans for all of the properties along the route. No public wells were found within one-hundred feet of the Transmission Line route, but they did find seventeen private wells that are within seventy-five feet of the line. None of the Petitioners have private wells that are within seventy- five feet of the line. While Petitioners D'Ordine and Hawkins initially contended that the well on Hawkins' property was within seventy-five feet of the Transmission Line, at hearing Mr. D'Ordine admitted that he "misread the plans and referred to the wrong property." In order to protect the private drinking water wells, Florida Administrative Code Rule 62-604.400(1)(b) requires that the County provide an extra level of protection for the wells that are within seventy-five feet of the Transmission Line. The County will provide that extra level of protection by installing restrained joints that will restrain the joints between the pipe sections. The restrained joints are epoxy-coated mechanical devices that reduce the tendency for the pipes to separate under pressure. The County has used these restrained joints on its potable water and wastewater lines in other areas of the County and has never experienced problems with the devices. The restrained joints will provide reliable protection of the private wells within seventy-five feet of the Transmission Line. The Department is unaware of any instances where restrained joints have failed in South Florida. If more wells are discovered that are within seventy-five feet of the Transmission Line, then the County will excavate the Line and install restrained joints. Minimum Separation Distances The County has complied with all applicable pipe separation requirements in the installation of the Transmission Line. More specifically, it is not closer than six feet horizontally from any water main and does not intersect or cross any reclaimed water lines. See Fla. Admin. Code R. 62-555.314(1)(a). It will be at least twelve inches below any water main or culvert that it crosses. See Fla. Admin. Code R. 62-555.314(2)(a). Finally, it will be a minimum of twelve inches below any culverts that it crosses. (However, the Department has no separation requirement for culverts crossed by the Transmission Line.) h. The M-Canal Crossing The Transmission Line must cross the M-canal, which runs in an east-west direction approximately midway between 40th Street North and Northlake Boulevard. The original design called for the Transmission Line to cross above the water, but the City and the Department suggested that it be located below the canal to eliminate the chance that the pipe could leak wastewater into the canal. In response to that suggestion, the County redesigned the crossing so that a 24- inch high density polyethylene pipe in a 48-inch casing will be installed fifteen feet below the design bottom of the canal. The polyethylene is fusion-welded, which eliminates joints, and is isolated with a valve on either side of the canal. Appropriate warning signs will be installed. See Fla. Admin. Code R. 62-604.400(2)(k)2.-5. The depth of the subaqueous line and the use of the slip line, or casing, exceeds the Department's minimum standards. See Fla. Admin. Code R. 62-604.400(2)(k)1. i. Flushing Protocol Section 48.1 of the Ten State Standard recommends that wastewater transmission lines maintain a velocity of two feet per second. When the Transmission Line becomes operational, it will not have sufficient flow to flush (or clean) accumulated solids from the lines at the recommended two feet per second velocities. (Sufficient flow will not occur until other customers connect to the Transmission Line during the first one to three years of operation.) Accumulated solids produce gases and odors that could create a problem at the treatment plant and might leak out of the manhole covers. To address this potential problem, Specific Condition 9 of the Permit requires the County to flush the lines periodically. Pursuant to that Condition, the County plans to flush the Transmission Line with additional water which will raise the velocity to three or four feet per second, so that the accumulated solids will be flushed. The water will be supplied by large portable tanks that will be temporarily set up at several locations along the Line. During the purging of the Line, sewage will collect in the pump stations until the purge is finished. There is sufficient capacity in the pump stations to contain the wastewater. In addition, the County will use a cleansing tool known as a pig, which is like a foam bullet that scrapes the sides of the pipe as it is pushed through the line. This protocol will be sufficient to keep the Line clean. ITID asserts that the County's plan for flushing is inadequate, because it does not provide enough water for long enough to flush both the 20-inch and 30-inch lines. Mr. Farabee calculated that the County would need almost twice the proposed volume, or almost six million gallons, to adequately flush the lines. ITID's analysis of the flushing protocol is flawed, however, because it assumes a constant flow in all segments of the pipe, which is not practical. In order to maintain the flushing velocity of three feet per second, the County will introduce water into the Transmission Line at three separate locations, resulting in a more constant flow velocity throughout the Transmission Line. In this way, it can maintain the proper velocity as the lines transition from a 20-inch to 30-inch to 36-inch pipe. The County has flushed other lines in the past using this protocol and has had no problems. This flushing protocol would only be in effect from one to three years. The County estimates that the necessary volumes to maintain a two-feet-per-second velocity in the 20- inch line would be reached in about one year. The 30-inch line should have sufficient flows sometime in 2008. These estimates are based on the signed agreements the County has with other utilities in the area to take their flows into the Transmission Line. Because of these safeguards, the Transmission Line will not accumulate solids that will cause undesirable impacts while flow is less than two feet per second. Other Requirements The construction and operation of the Transmission Line will not result in the release or disposal of sewage or residuals without providing proper treatment. It will not violate the odor prohibition in Florida Administrative Code Rule 62-600.400(2)(a). It will not result in a cross- connection as defined in Florida Administrative Code Rule 62- 550.200. The construction or operation of the Transmission Line will not result in the introduction of stormwater into the Line, and its operation will not result in the acceptance of non-domestic wastewater that has not been properly pretreated. If constructed and permitted, the Transmission Line will be operated so as to provide uninterrupted service and will be maintained so as to function as intended. The record drawings will be available at the Department's district office and to the County operation and maintenance personnel. Finally, concerns by the individual Petitioners that the County may not restore their property to its original condition after construction is completed are beyond the scope of this proceeding. At the hearing, however, the Deputy Director of the Water Utilities Department represented that the County would cooperate with the individual property owners to assure that these concerns are fully addressed. Reasonable Assurance The County has provided the Department with reasonable assurance, based on plans, test results, installation of equipment, and other information that the construction and installation of the Transmission Line will not discharge, emit, or cause pollution in contravention of the Department's standards.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order denying all Petitions and issuing Permit No. 0048923-017-DWC. DONE AND ENTERED this 18th day of October, 2005, in Tallahassee, Leon County, Florida. S DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 18th day of October, 2005.
Findings Of Fact The Petitioner is a gasoline distributor that provided the gasoline in question to the South Bay Arrow Service Station in South Bay, Florida, which is operated by an independent contractor. On October 10, 1979, a petroleum inspector, Fen Frederick, took a gasoline sample for analysis of unleaded gasoline from the South Bay Arrow Service Station at South Bay, Florida. This sample was tested by the state gasoline laboratory at Port Everglades in Fort Lauderdale, Florida, and on October 11, 1979, the laboratory notified Mr. Frederick that the unleaded gasoline did not meet state standards, in that it contained 2.24 grams of lead per gallon, which is in excess of .05 grams per gallon allowable under the respondent department's rule. On the basis of this information, Mr. Frederick went to the South Bay Arrow Service Station and placed a stop-sale notice on the tank that dispensed the unleaded gasoline. The tank in question at the time had a remaining 2,400 gallons of gasoline. Since the independent owners of South Bay Arrow Service Station could not post a cash bond for the release of the stop-sale, Petitioner, Carl McKinney, agreed to post a bond of $1,000.00 for the release of the stop-sale of the impounded gasoline. The gasoline which Petitioner sold to the service station met state standards at the time of delivery and Petitioner has no direct knowledge of how the gasoline came to be substandard. Petitioner has not challenged the authority of the Department to utilize cash bonds in lieu of confiscation and sale of substandard gas.
Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That the Department deny Petitioner's request for the return of the $1,000.00 bond posted in lieu of confiscation of substandard unleaded gasoline. DONE and ORDERED this 20th day of May, 1980, in Tallahassee, Florida. SHARYN L. SMITH, Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: Robert A. Chastain, Esquire General Counsel Department of Agriculture and Consumer Services Room 513, Mayo Building Tallahassee, Florida 32301 Mr. Carl McKinney C & K Oil Company, Inc. U.S. 27 and Second Street Post Office box 1086 Moore Haven, Florida 33471 Mr. John Whitton Division of Standards Bureau of Petroleum Inspection Department of Agriculture and Consumer Services Mayo Building Tallahassee, Florida 32301