CONSTRUCTION INDUSTRY LICENSING BOARD vs JUAN RODRIGUEZ, 98-004260 (1998)
Division of Administrative Hearings, Florida Filed:Miami, Florida Sep. 28, 1998 Number: 98-004260 Latest Update: Sep. 14, 1999

The Issue At issue in this proceeding is whether Respondent committed the offenses set forth in the Administrative Complaint and, if so, what penalty should be imposed.

Findings Of Fact Preliminary matters At all times material hereto, Respondent, Juan Rodriguez, was licensed by Petitioner, Department of Business and Professional Regulation, Construction Industry Licensing Board (Department), as a certified general contractor, having been issued license number CG C005171. Respondent was licensed as an individual and not as the qualifying agent of any corporation or other business organization. At all times material hereto, Henry Pena was the sole officer and director of U.S.A. Henry Roofing Corp., a Florida corporation. Neither Henry Pena nor U.S.A. Henry Roofing Corp. (hereinafter jointly referred to as "Pena"), were registered, certified, or otherwise qualified under the provisions of Chapter 489, Florida Statutes, to engage in contracting in the State of Florida. Respondent was clearly aware of Pena's lack of licensure.1 The Zapata job Pertinent to this case, Oscar and Consuelo Zapata owned a one-story commercial building located at 59 Beacom Boulevard, Miami, Florida. On August 1, 1996,2 Mr. Pena, on behalf of U.S.A. Henry Roofing Corp., and Mr. Zapata entered into an agreement whereby U.S.A. Henry Roofing Corp. would replace the roof on the building in exchange for an agreed price of $18,200. A first payment of $8,000 was to be paid after the first inspection, and the balance of $10,200 was to be paid following the final inspection. Later in the month of August, Mr. Pena presented a building and zoning permit application, as well as a request for permit, to Mr. Zapata (as owner of the property) for signature. (Petitioner's Exhibit 8.) Following Mr. Zapata's signing, Mr. Pena delivered the forms to Respondent who signed as the contractor. Thereafter, on or about September 3, 1996, Respondent submitted the forms to the City of Miami to obtain a building permit for the re-roofing job. Respondent was not then, nor was he ever, under contract to make improvements to the Zapata property, and his sole involvement was to obtain a permit so Pena could proceed with the job. The permit was issued on or about September 5, 1996.3 On September 17, 1996, Pena began work on the roof, and ceased work the same day when the roof collapsed.4 With the discovery that Pena was not licensed or insured, Mr. Zapata ultimately contracted with another company (that was licensed) to re-roof the building for $16,000. That contract was duly fulfilled, and the re-roofing of the Zapata building was accomplished (notwithstanding the roof collapse) without financial loss to the Zapatas.5 Respondent's lapse of insurance coverage Respondent's liability and property damage insurance policy was terminated June 25, 1996, and was not reinstated until September 19, 1996. Respondent does not dispute the lapse in insurance coverage. (Petitioner's Exhibits 6 and 10, and Transcript, at pages 76-77, and 80-81.) The costs of investigation and prosecution At hearing, the Department offered proof, without objection, that its costs of investigation and prosecution, excluding costs associated with any attorney's time, totalled $306.09, as of January 27, 1999. (Petitioner's Exhibit 7.) Previous disciplinary action On January 18, 1996, the Department entered a final order which found the Respondent guilty of the violations set forth in a two-count Administrative Complaint issued March 25, 1993. (Petitioner's Exhibit 1.) In that complaint, the Department charged (in Count I) that Respondent violated the provisions of Subsection 489.129(1)(e), Florida Statutes, "by performing any act which assists a person or entity in engaging in the prohibited uncertified and unregistered practice of contracting, if the cerfificateholder or registrant knows or has reasonable grounds to know that the person or entity was uncertified and unregistered," and (in Count II) that Respondent violated the provisions of Subsection 489.129(1)(m), Florida Statutes, "by being found guilty of fraud, deceit, or of gross negligence, incompetency, or misconduct in the practice of contracting." Such charges were premised on a renovation contract Respondent held wherein he "subcontracted Nelson Echeverria [who was not a state licensed electrical contractor] to perform electrical work at customer's home for approximately $4,500.00." The final order found Respondent guilty of the charges, and imposed an administrative fine of $1,500 and costs of $1,433.03, to be paid within 30 days. On March 8, 1996, Respondent's license was suspended for failure to satisfy the penalty imposed by the final order; however, the penalty was then apparently satisfied and on June 19, 1996, the suspension was lifted and Respondent's license was reinstated.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered finding Respondent guilty of the violations alleged in Counts I through III of the Administrative Complaint and imposing, as a penalty for such violations, an administrative fine in the sum of $5,000; assessing costs of investigation and prosecution in the sum of $306.09; and, suspending Respondent's licensure for a period of one year, followed by a two-year term of probation subject to such reasonable terms and conditions as the Construction Industry Licensing Board may impose. DONE AND ENTERED this 12th day of May, 1999, in Tallahassee, Leon County, Florida. WILLIAM J. KENDRICK Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 12th day of May, 1999.

Florida Laws (9) 120.569120.57120.6017.002489.105489.113489.1195489.127489.129 Florida Administrative Code (4) 61G4-15.00361G4-17.00161G4-17.00261G4-17.009
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs ARTHUR SIGNORE, 97-001435 (1997)
Division of Administrative Hearings, Florida Filed:Miami, Florida Mar. 21, 1997 Number: 97-001435 Latest Update: May 06, 1998

The Issue The issue for determination is whether Arthur Signore committed the offenses set forth in the administrative complaints and, if so, what action should be taken.

Findings Of Fact At all times material hereto, Arthur Signore (Respondent) was licensed by the Department of Business and Professional Regulation, Construction Industry Licensing Board (Petitioner) as a certified general contractor. He received his license in 1969, qualifying Deluccia Construction. Respondent was issued license number CG CA01004. Subsequently, in 1976, Respondent qualified Construction By Scott (CBS). He was issued license number CG CB01004. At all times material hereto, Respondent has been the qualifier of CBS, and the sole owner and president of CBS. At all times material hereto, Respondent's belief was that Petitioner permitted a general contractor to use his/her license to obtain building permits for construction projects for which the general contractor had no contracts through the business that he/she qualified. Respondent practiced his belief frequently by applying for and obtaining building permits for construction projects for which companies or individuals other than CBS had contracts. Collins Job (Case No. 97-1436) Sometime after Hurricane Andrew in 1992, Respondent made an oral agreement with Harold Bader to go into partnership with Bader and form a construction company, with Respondent qualifying the company. Respondent provided his name, his company's name (CBS), and his license number to Bader in order for the qualifying documents to be completed and submitted to the Petitioner. However, the company was not formed and the qualifying documents were never submitted. At no time material hereto was Bader licensed by the Petitioner to engage in the practice of contracting. Respondent knew or should have known that Bader was not licensed by the Petitioner. In March 1994, Thomas Sherry of American Building Industries, Inc. (ABI), began negotiating with Maria and Wayne Collins, husband and wife, for the remodeling of their home, located at 7417 SW 140th Court, Miami, Florida. On March 24, 1994, the Collins entered into a contract with ABI for the remodeling of their home at a cost of $12,500. Bader was the owner of ABI. Sherry was a salesperson for Bader. Sherry provided the Collins with a business card which showed, among other things, ABI's name, address and telephone number, and license number. The license number on the business card was Respondent's license number. All business cards were provided to Sherry by Bader. At no time material hereto, did Sherry talk with or meet Respondent. The records of the Metropolitan Dade County, Building and Zoning Department reflect, among other things, Respondent's name, his company's name (CBS) and license number on the building permit application for the construction to the Collins' home. However, the address listed for Respondent and his company was the address for ABI. Further, the said records reflect, among other things, that aforementioned information provided, as to Respondent, was used to obtain the building permit. Respondent did not complete the permit application for the building permit to remodel the Collins' home. The Collins paid $6,875 to ABI. Any and all checks were made payable to ABI. No money for the construction on the Collins' home was paid to or received by Respondent. In May 1994, problems developed on the job site between the Collins and ABI. The work performed by ABI failed numerous inspections. Mr. Collins wanted to talk with Respondent who was listed as the contractor on the permit and requested Bader to contact Respondent. Bader refused, indicating to Mr. Collins that all communication should be with him (Bader). Finally, in August 1994 the Collins fired ABI after more problems had developed. At that time ABI had completed some of the work. On August 29, 1994, Mr. Collins met with Respondent at Respondent's place of business. Prior to the meeting, Mr. Collins had called Respondent numerous times regarding his problems with ABI and Bader and requesting assistance from Respondent. Each time Respondent denied having any knowledge of the work being performed. When Mr. Collins met with Respondent, Mr. Collins discussed the problems that he had experienced with ABI and Bader. Respondent continued to deny knowing anything about the construction project but agreed to send his employees to examine the job and determine what could be done, if anything. The following day two of Respondent's workers came to the Collins' home and examined the work completed and the work remaining. Subsequently, Respondent contacted Mr. Collins. Respondent indicated to Mr. Collins that he could complete the job for $5,000. Mr. Collins refused to pay the additional monies since it would extend the remodeling cost beyond the contracted cost and since he was now directly paying the subcontractors. At no time did Respondent or his business (CBS) have a contract with the Collins. Until being contacted by the Collins, Respondent had no knowledge that Bader used his name, business name and license number to contract with the Collins and to obtain the building permit for the remodeling of their home. However, prior to being contacted by the Collins, Respondent had been contacted by other persons who had contracts with ABI, who had been informed by Bader that Respondent was the contractor for their jobs, who had problems with ABI, and who wanted assistance from Respondent. Furthermore, the building permits for the construction jobs of those persons reflected Respondent and Respondent's company as the contractor. At no time material hereto was Bader or ABI licensed by the Petitioner to engage in the practice of contracting. Respondent knew or should have known that neither Bader nor ABI was licensed by the Petitioner to engage in the practice of contracting. Respondent was placed on notice of their unlicensed activity after the contacts by the homeowners prior to the contact by the Collins. Even with the knowledge of the homeowners' complaints prior to the Collins' complaints, at no time did Respondent notify Bader to stop using his (Respondent's) name, company's name and license number. Further, at no time did Respondent notify the Metropolitan Dade County, Building and Zoning Department of Bader's misuse of his (Respondent's) name, company's name, and license number or to no longer issue permits to ABI under his (Respondent's) name, company and license. Walsh Job (Case No. 97-1435) In the Fall of 1995, Patrick and Susan Walsh entered into an oral agreement with John Petracelli for an addition to and the remodeling of their home, located at 761 Glen Ridge Road, Key Biscayne, Florida. On October 16, 1995, the Walshes entered into a verbal agreement with Petracelli for an engineer to produce a set of plans at a cost of $2,250 for the construction to their home. The Walshes paid Petracelli the $2,250 on October 16, 1995. On December 7, 1995, the Walshes entered into a written agreement with Petracelli for the construction work on their home at a cost of $84,000. Pursuant to this written agreement, the Walshes paid Petracelli $16,800 on December 7, 1995. Petracelli contacted Respondent and requested Respondent to be the contractor for the construction work on the Walshes' home. Respondent and Petracelli had met one another previously when Petracelli was a salesperson for Bader. Petracelli informed Respondent that he (Petracelli) had already told the Walshes that Respondent was the contractor. To the contrary, Petracelli had not informed the Walshes that Respondent was involved in the construction to their home. Respondent agreed to be the contractor but informed Petracelli that, until a set of plans was approved by the Village of Key Biscayne Building Division (Building Division), he could not provide Petracelli with a cost figure for the construction work. Petracelli informed Respondent that the plans were being prepared, but did not inform Respondent that the Walshes had paid for the preparation of the plans. Respondent agreed further to submit the completed plans to the Building Division for a "dry run" only. After the dry run, Respondent would provide a cost figure for the construction work. A dry run is a process in which a contractor, who has a complicated job which requires an engineer, submits a set of plans, together with an application for a building permit, to the Building Division for approval. The plans may be subject to several modifications requested by the Building Division before they are approved. As a result, the contractor does not know the estimated cost of a job until the plans have gone through the requested modifications, if any, and approved by the Building Division. After the plans are approved by the Building Division, the contractor is notified to come to the Building Division and sign for and obtain the building permit. Pursuant to the agreement between Respondent and Petracelli, on or about December 11, 1995, Respondent completed an application for a building permit for the addition to and the remodeling of the Walshes' home and gave it to Petracelli. The application reflected, among other things, CBS (Respondent's company) as the contractor, and Respondent as the qualifier. Respondent provided the application to Petracelli for the dry run process only. Further, Respondent reiterated to Petracelli that, once the plans were approved by the Building Division, he (Respondent) would meet with the Walshes and agree on a cost for the construction work on their home and that, after agreeing on the cost he (Respondent) would sign for and obtain the building permit for the construction to begin. Respondent was not aware that Petracelli and the Walshes had a signed agreement for the construction work. Petracelli submitted the plans, along with the permit application, to the Building Division for approval. The plans were modified several times to meet the approval of the Building Division, but were never approved. The Building Division considered the plans submitted to be substandard. Since no plans were approved, no building permit was issued. On or about January 3, 1996, the Walshes met at the Building Division with some of the Building Division's officials, Petracelli, and the engineer who prepared the plans. As a result of the meeting, among other things, the Walshes were able to review the permit application and discovered that Respondent, not Petracelli, was licensed and the contractor for the construction work; concluded that the engineer's work was considered so substandard by the Building Division that any modification produced by the engineer would not be approved by the Building Division; and determined that they no longer wanted Petracelli to perform the construction work on their home. Within 24 hours of the meeting, the Walshes telephoned Petracelli and terminated his services. Also, the Walshes requested the return of all of the monies paid to Petracelli by them; however, Petracelli did not return any of their money. At no time material hereto was Petracelli licensed by the Petitioner to engage in the practice of contracting. Respondent knew or should have known that Petracelli was not licensed by the Petitioner. At no time material hereto did Respondent or his company (CBS) have a contract with the Walshes. At no time material hereto did Respondent have any communication or contact with the Walshes. Biscayne Kennel Club Job (Case No. 97-2998) The Biscayne Kennel Club (BKC), located at 320 NW 115th Street, Miami Shores, Florida, was a track for greyhound racing. On October 30, 1995, the last race was run at BKC. In February 1996, the BKC sold its Pari-Mutuel license. On or about December 11, 1996, the BKC, by and through its representative, Carl Spitzer, entered into a written contract with Cuyahoga Wrecking Corporation (CWC), by and through its representative, Thomas Schwab, for, among other things, the removal of asbestos and the demolition and removal of BKC's grandstand structure and viewing area. The contract was prepared by Schwab, who had 25 years of experience in the demolition business, with 20 years of that experience in the State of Florida. All contract negotiations were between Schwab and Spitzer. At no time was the President and CEO of BKC, Kay Spitzer, involved in the contract negotiations. As to cost, the contract provided at Article 4 that the cost was $37,500 and that the $37,500 was "dedicated to the removal of the described ACM." Further, Article 4 provided that the "balance of the work to be paid for by the sale of the ferrous and non-ferrous metals by the contractor." In addition, the contract provided in Article 7 that, among other things, all permits were included in the contract price and that BKC and the "contractor" would share "equally all the proceeds of the non-ferrous metals minus whatever costs are incurred bringing it to market." The contract did not restrict or prohibit CWC from engaging the services of any individual or subcontractor to perform the work required in the contract. The grandstand structure and viewing area were one structure. Attached to the roof of the structure was a small building which was used by BKC personnel for viewing the races. The roof was the highest part of the structure, except for the small building. The distance from ground level to the top of the roof was 69 feet and 10 inches; and the top of the small building was approximately 15 feet higher than the top of the roof. CWC contracted with Sal's Abatement to perform the asbestos removal. Schwab was licensed by Dade County, Florida, as a specialty contractor. He was notified that the work for the BKC job was outside the scope of his license and that a contractor, licensed by the Petitioner, was required for the BKC job. Schwab contacted Respondent to be the general contractor. Schwab had worked with Respondent before on other, but smaller, jobs. Respondent agreed to be the general contractor in return for a percentage of the contract. Per the agreement, Respondent would obtain the necessary permits, provide the equipment necessary for the demolition, and supervise the workers on the job. On March 6, 1997, Respondent completed an application for a building permit with Miami Shores Village, Florida, for the demolition of the BKC grandstand. The application reflected Respondent's company (CBS) as the contracting company and Respondent as the qualifier. Carl Spitzer signed the permit application on behalf of BKC. On March 17, 1997, a building permit (permit number 41084) was issued by the Village of Miami Shores for the demolition of BKC's grandstand. On April 29, 1997, the cost of the permit, $566.50, was paid. At no time material hereto was Schwab or CWC licensed by Petitioner to engage in the practice of contracting. Respondent knew or should have known that neither Schwab nor CWC were licensed by Petitioner. At no time did a contract exist between Respondent or his company with BKC for the demolition job. Respondent supervised CWC's preparation of the grandstand for demolition. In preparing the grandstand for demolition, Respondent and Schwab met at the site at least 3 times to discuss the demolition and its progress. On May 16, 1997, the grandstand was scheduled to be demolished. On the morning of May 16th, as Schwab was leaving BKC, Respondent arrived. Shortly thereafter, the grandstand accidentally collapsed--the beams supporting the roof of the grandstand failed, and the roof collapsed. Two of CWC's workers were killed and three were seriously injured. After the collapse, BKC contracted with another company, Omega Contracting, to complete the demolition job. The Petitioner submitted documents reflecting that its costs of investigation and prosecution of the complaints against Respondent, excluding costs associated with attorney's time, to be $1,017.25. On May 22, 1997, pursuant to an Emergency Suspension Order, on May 22, 1997, the Petitioner suspended Respondent's license. Respondent has no prior disciplinary action taken against him by the Petitioner.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Construction Industry Licensing Board enter a final order: Dismissing all counts in Case Nos. 97-1435 and 97-1436. Finding that Arthur Signore violated Subsections 489.129(1)(c), (e), and (j), 489.1265(3), and 455.227(1)(a), Florida Statutes (1995). Revoking Arthur Signore's certified general contractor's license. Requiring Arthur Signore to pay all reasonable costs of investigation and prosecution associated with the Department of Business and Professional Regulation's investigation and prosecution of the charges set forth in the Administrative Complaint of Case No. 97-2998.3 DONE AND ENTERED this 13th day of January, 1998, in Tallahassee, Leon County, Florida. ERROL H. POWELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 13th day of January, 1998.

Florida Laws (6) 120.569120.57455.227489.105489.1195489.129 Florida Administrative Code (3) 61G4-12.01861G4-17.00161G4-17.002
# 2
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs LUCIUS P. CLARK, 98-004859 (1998)
Division of Administrative Hearings, Florida Filed:Miami, Florida Oct. 29, 1998 Number: 98-004859 Latest Update: Aug. 01, 2001

The Issue The issue for determination is whether Respondent committed the offenses set forth in the Administrative Complaints and, if so, what penalty should be imposed.

Findings Of Fact It is undisputed that at all times material hereto, Respondent was licensed by the State of Florida as a Certified General Contractor, having been issued license number CG C58099. Respondent passed the licensing examination in August 1995. Case No. 99-0261 Respondent is not a licensed roofing contractor. Respondent's Certified General Contractor's license did not and does not permit him to obtain roofing permits to perform any type of work on roofs. Respondent's Certified General Contractor's license number was not low enough for him to be grandfathered in by the State to allow him to lawfully perform roofing work with his Certified General Contractor's license. On or about February 23, 1998, Delfina Valdes contracted with Johnny Hatcher, d/b/a Hatcher's Roofing, to repair the roof on her residence located at 18101 Northwest 32 Avenue, Miami, Florida. They contracted for Hatcher to remove Valdes' old roof and install a new roof at a cost of $4,000. Valdes paid Hatcher $2,000 as a down payment toward the cost of the roof's repair. At no time material hereto was Hatcher a licensed roofing contractor. Furthermore, at no time material hereto was Hatcher's Roofing qualified by the State of Florida to perform contracting. Hatcher removed the roof from Valdes' residence. After removing the roof, he did not perform any more work. Respondent met with Valdes and represented to her that Hatcher was working for him. Respondent further represented that he would obtain the permit for the roofing work. Respondent paid Cayetano Alfonso to obtain a roofing permit for the work on Valdes' roof. On or about March 26, 1998, Alfonso made application to Metropolitan Dade County, Department of Planning, Development and Regulation for the roofing permit, which was subsequently issued. Alfonso was a Certified General Contractor who was licensed to perform roofing work. Alfonso's Certified General Contractor's license number was low enough for him to be grandfathered in by the State to allow him to lawfully perform roofing work with his Certified General Contractor's license. Alfonso was not the qualifier for Hatcher's Roofing nor was he Respondent's qualifier. Alfonso did not enter into the contract with Valdes for repairing her roof. Alfonso was not a party to the contract for repairing Valdes' roof. An inference is drawn and a finding of fact is made that Hatcher was not acting on behalf of Alfonso when he entered into the contract with Valdes. An inference is drawn and a finding of fact is made that Respondent was not acting on behalf of Alfonso when he represented to Valdes that he would obtain the permit for the roofing work. When Respondent discovered that Hatcher had received a $2,000 deposit from Valdes, he requested Alfonso to cancel the permit. On or about April 20, 1998, Alfonso cancelled the roofing permit. On or about June 5, 1998, Valdes cancelled the contract between her and Hatcher Roofing. Valdes received a refund of the $2,000 from Hatcher, through a third party, that she had paid him. Case No. 98-4859 On or about April 9, 1995, Respondent entered into a contract with Susan Casper to construct an addition to her residence located at 17350 Northeast 12th Court, North Miami Beach, Florida, at a cost of $38,135. Casper paid Respondent $36,285.00 toward the cost of the addition. Respondent was not licensed at the time that he entered into the contract. On or about March 20, 1996, Respondent obtained a permit from the Metropolitan Dade County, Department of Planning, Development and Regulation for the work on the addition. Several delays were encountered during the performance of the work. Some of the delays resulted from changes by Casper, which changes required approval by Metropolitan Dade County, Department of Planning, Development and Regulation; however, most of the delays were Respondent's own doing. In October 1996, Casper paid $2,588 to Best Truss Company for a claim of lien filed on her residence, associated with the work being performed on her residence. Respondent worked sporadically on Casper's addition through April 1997. He would inform her at times that he was returning but failed to return. At one point, Casper's children constructed a sign in their own handwriting, instructing Respondent to keep out and indicating that there was no trespassing by him. The sign was posted on the door of Casper's residence. Casper informed Respondent that her children constructed the sign. It was obvious that the keep out, no trespassing sign was constructed by children. Respondent's assertion that he was kept away from Casper's residence by the children's sign is not credible. Even after the children's sign was posted on the front door of Casper's residence, Respondent agreed with Casper to resume work, and he did so. However, his work was sporadic. In or around June 1997, Casper sought assistance from the Metropolitan Dade County, Department of Planning, Development and Regulation to get Respondent to complete the work. In July 1997, Respondent obtained a window permit for the work on Casper's residence. After July 1997, Respondent ceased working on Casper's residence. He did not provide Casper with any notice that he was ceasing work. Respondent had no valid reason for ceasing the work. In September 1997, Casper transferred the permit for the work on her residence from Respondent's name to her name. Respondent failed to perform all the work under the contract. Some of the work performed by Respondent or caused to be performed by Respondent contained code violations and needed correcting. Certain work performed by Respondent or caused to be performed by Respondent needed correcting. Wood doors, glass block, electrical work, and a sprinkler were in need of correction. Casper bore the expense of the corrections. The corrective work was completed at a cost of $1,675.00. The value of the work performed by Respondent on Casper's residence was $18,272, minus the cost of the corrective work of $1,675, which equals a total value of the work at $16,597. This cost value includes overhead and profit. Even though the value of the work by Respondent was $16,597, Casper paid Respondent $36,285, a difference of $19,688. Casper hired a new contractor on or about September 17, 1997, to complete the construction on her residence at a cost of $16,350. As to Case No. 98-4859, as of January 26, 1999, Petitioner incurred a cost of $1,108.76 for the investigation and prosecution of Respondent. Petitioner previously disciplined Respondent for violating Chapter 489, Florida Statutes (1995), including violating Subsection 489.127(1)(k), Florida Statutes (1995), abandonment of a construction project.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation, Construction Industry Licensing Board enter a final order and therein: As to Case No. 99-0261, finding that Respondent violated Subsection 489.129(1)(e), Florida Statutes (1997). As to Case No. 98-4859, finding that Respondent violated Subsection 489.129(1)(k), Florida Statutes (1997), in Count I; and dismissing Count II. Revoking Respondent's license. Ordering Respondent to pay restitution to Susan Casper in the amount of $19,688.00. DONE AND ENTERED this 31st day of October, 2000, in Tallahassee, Leon County, Florida. ERROL H. POWELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 31st day of October, 2000. COPIES FURNISHED: Diane Snell Perera, Esquire Department of Business and Professional Regulation 401 Northwest 2nd Avenue, Suite N607 Miami, Florida 33128 Richard F. Hayes, Esquire 10300 Sunset Drive, No. 499 Miami, Florida 33173 Rodney L. Hurst, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Barbara D. Auger, General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (7) 120.569120.5717.002489.119489.1195489.127489.129 Florida Administrative Code (3) 61G4-17.00161G4-17.00261G4-17.003
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. RICHARD L. JOHNANTONIO, 87-003884 (1987)
Division of Administrative Hearings, Florida Number: 87-003884 Latest Update: Mar. 11, 1988

Findings Of Fact Respondent is, and has been at all times material hereto, a registered roofing contractor in the State of Florida, having been issued license number RC 0039352. Respondent is the qualifying agent for Ken and Rick's Roofing, Inc. of Mami, Florida. On May 16, 1986, Ken and Rick's Roofing, Inc. contracted to repair roof leaks for a Victor Krauthaner of 18441 Northeast 21st Place, North Miami Beach, Florida. The contract, signed by Respondent and Mr. Krauthaner, contained a six (6) month warranty on repairs. The contract price was $215.00. Mr. Krauthaner paid the full amount by a check which was cashed by Respondent. On May 17, 1986, David J. Godfried, an employee of Ken and Rick's Roofing, Inc. was dispatched by Respondent to repair Mr. Krauthaner's roof. Godfried removed tiles from the affected portion of the roof and installed new tar paper. The old tiles could not be re-used and Godfried did not have appropriate tiles in stock, so he left the tar paper exposed and promised Krauthaner that he would return with new tiles within a week. No one from Ken & Rick's Roofing, Inc. returned after May 17, 1986 to replace the tile and Krauthaner began experiencing new leaks. Mr. Krauthaner made repeated attempts by telephone and letter to encourage Ken & Rick's Roofing, Inc. to complete the repairs. Representatives of the company repeatedly assured Krauthaner that someone would respond to repair the leaks, but no one ever did. Mr. Krauthaner repaired the leak himself in June of 1987. Chapter 10 of the Code of Metropolitan Dade County requires that roofing contractors working within the county be either certified by the State of Florida or possess a certificate of competency in roofing issued by the county. Respondent's registered roofing license was suspended by The Construction Industry Licensing Board in March 1985 for failure to pay a fine assessed as the result of a previous disciplinary action. The suspension was in effect at the time Respondent contracted to repair the Krauthaner residence. Respondent does not possess a certificate of competency from Dade County, nor did he possess one at the time the contract was executed. Respondent has been disciplined on three prior occasions by The Construction Industry Licensing Board on January 23, 1984 (DPR Case Number 33028); May 21, 1984 (DPR Case Number 42963); and, June 6, 1985 (DPR Case Number 49942). The complaint in Case Number 42963 alleged that Respondent had exceeded the scope of his license by contracting in Dade County without first meeting local competency requirements.

Florida Laws (7) 120.57489.105489.115489.119489.121489.127489.129
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs RONNIE L. BARFIELD, 90-002523 (1990)
Division of Administrative Hearings, Florida Filed:Panama City, Florida Apr. 27, 1990 Number: 90-002523 Latest Update: Feb. 01, 1991

The Issue Whether petitioner should take disciplinary action against respondent for the reasons alleged in the amended administrative complaint?

Findings Of Fact At all pertinent times, respondent Ronnie L. Barfield was registered as a roofing contractor and held a state contractor's license, No. RC 0039607. At some point, records reflected the license was inactive, but this was in error. In 1987, Jack Williams lived in the house at 3101 Kings Drive in Panama City, Florida. At all pertinent times the house belonged to Evelyn Rhoads, whose daughter Anna was once married to Mr. Williams. "[B]ack in 1987," (T.10) Mr. Williams contracted with respondent Barfield, on behalf of Ms. Rhoads, to re-roof the house. Doing business as Gulf Coast Roofing Co., Mr. Barfield estimated the work would cost $5,000, before seeing the house, but ultimately presented a bill for (and was paid) $13,922.56. Petitioner's Exhibit No. 2. Respondent removed the existing shingles, replaced rotted portions of the decking near the chimney, installed four new skylights, installed a new drip edge or eave drip and put on new felt and fiberglass shingles. Any flashing there may have been around the chimney did not survive removal of the existing shingles. The eave drip, a strip of aluminum, "puckered" over the carport because the trusses were not uniform. At Mr. Williams' request, Mr. Barfield drove three nails through the eave drip into the fascia to flatten the metal out. Exposed to the elements, the heads of these galvanized nails rusted. On August 10, 1987, after Jack had moved out, Anna moved back in. She noticed "a lot of ridges, indentations and waves in the roof." T.16. (But this may have been nothing new. When a concrete slab foundation varies in height, so that the trusses are at different heights, it makes the roof uneven.) Waviness arising even after respondent's work would more likely have been because of poor attic ventilation than any dereliction by respondent. Anna Bartness, as she has been known since July of 1988, also noticed that the shingles capping the peak or ridge of the roof were loose and uneven. When inspected in January, ridge cap shingles were found attached with only a single nail, instead of two -- one on either side -- which is the industry standard. Eventually "the ridge cap came off it was in the yard." T.16. One of the skylights leaked, when it rained. Ms. Bartness sought Mr. Williams' assistance in locating respondent to tell him of the problems. Mr. Williams remembered getting "the telephone number where [respondent] could be reached." T.14. Whether Mr. Williams himself actually telephoned is not clear, but Ms. Bartness tried repeatedly to reach Mr. Barfield by telephone. Although she never succeeded, she left messages on a telephone answering machine and also left word with a secretary in Mr. Barfield's lawyer's office. A certified letter she mailed respondent was returned unclaimed. These efforts to reach Mr. Barfield may have coincided with time he spent in south Florida. Respondent had agreed "LABOR CARRIES A 5 YEAR WARRANTY." Petitioner's Exhibit No. 2. He did not learn of complaints about the work at 3101 Kings Drive until after Ms. Rhoads complained to the Department of Professional Regulation and the present proceedings began. But he had not offered to reimburse Ms. Rhoads or otherwise honor the warranty in any way, as of the time of the hearing. Giving up on Mr. Barfield, Ms. Bartness got estimates from two other roofers, David C. Stallnecker and Mayo= Rudd. Among other things, flanges around plumbing vents that had sustained damage from external sources required replacement, flashing needed to be installed around the chimney, wood there had again rotted, and ridge cap shingles needed removal and proper installation. Mr. Rudd charged her $710 for repairs he told her consisted of putting flashing around the chimney because there was none, reapplying tar or "bull," replacing a defective vent that was leaking into a skylight and, which she could see herself, replacing shingles on the roof ridge. Petitioner's Exhibit No. 5. On or about January 15, 1988, before these repairs, Mr. Stallnecker, like Mr. Rudd, found "no flashing on the chimney." Petitioner's Exhibit No. 5; T. 44. When water began coming down the chimney in 1990, Ms. Bartness contracted with James Rutledge, doing business as Rutledge Roofing, to do additional work. He removed shingles around the chimney, replaced bad wood, installed a "membrane with plastic [r]oof cement for flashing against chimney," Petitioner's Exhibit No. 7, and replaced felt and shingles. Unless an owner instructs him not to, a reasonably prudent roofer would install flashing around a chimney that did not already have it before laying shingles there. T. 45. Testifying at hearing, Mr. Barfield never claimed that he installed flashing around the chimney. Nor did he ever say he saw flashing around the chimney. He said flashing was built in behind the brick. You couldn't see it . . . until you pulled the brick out. T. 70. On balance, however, his testimony suggested that he assumed there was flashing around the chimney, without ever seeing it. [T]he brick masons put the flashing on unless you go where they're building these 235 houses around here they would have nailed it on the side. You hardly wouldn't do that on a $200,000 house sitting on the water, I wouldn't think. I would think it would be built in. T. 71. However reasonable this assumption, and the unstated assumption that his crew had not (inadvertently) removed the flashing in taking off the existing roof, the evidence as a whole showed there was no flashing around the chimney by the time respondent's crew put down the new shingles.

Recommendation It is, accordingly, RECOMMENDED: That the Construction Industry Licensing Board fine respondent five hundred dollars ($500). DONE and ENTERED this 1st day of January, 1991, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 1st day of January, 1991. Copies furnished to: Daniel O'Brien, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Jack McRay, General Counsel Department of Professional Regulation 1940 N. Monroe Street Tallahassee, FL 32399-0792 G. W. Harrell, Esquire Department of Professional Regulation 1940 N. Monroe Street, Suite 60 Tallahassee, FL 32399-0792 Rowlett W. Bryant, Esquire 833 Harrison Avenue Panama City, FL 32402

Florida Laws (1) 489.129
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. HARRY BRADSHAW, 89-003290 (1989)
Division of Administrative Hearings, Florida Number: 89-003290 Latest Update: Oct. 31, 1989

The Issue Whether Respondent committed the offenses set forth in the administrative complaint and, if so, the penalty which should be imposed.

Findings Of Fact At all times material to this case, the Respondent, Harry Bradshaw, was licensed as a registered roofing contractor in the State of Florida, holding license number RC 0033812. On August 26, 1986, Respondent's license as a registered roofing contractor was suspended by Petitioner. Respondent's license remained suspended at all times material to this case. On December 16, 1987, Respondent contracted with the Moose Lodge located in Hialeah, Florida, to reroof the Moose Lodge building. The proposal submitted by Respondent contained representations that Respondent was licensed as a registered roofing contractor and that he was insured. Respondent knew that his license as a registered roofing contractor was under suspension. Respondent had no insurance. The contract between Respondent and the Moose Lodge provided that Respondent would perform the work and supply the materials for the sum of $6,200.00. The sum of $3,200.00 was paid to Respondent in advance of his beginning the job. Respondent used the sums advanced to purchase materials and supplies. The remaining $3,000.00 was to have been paid upon Respondent's completion of the job. During the negotiations that resulted in the contract between Respondent and the Moose Lodge, Respondent represented that the job should be completed in time for the functions scheduled for New Year's Eve. While Respondent had purchased the materials needed for the job and had done a substantial amount of work on a portion of the roof, he was unable to complete the work by the New Year. Respondent was ordered to stop work on the job on January 26, 1988. Respondent did not abandon the job. Although he was slow in performing the work, a part of Respondent's delay in performance was caused by rain. There was no evidence as to what would have been a reasonable period of time for Respondent to have completed the job. On January 26, 1988, the administrator for the Moose Lodge complained to the Building Inspection Department for the City of Hialeah, Florida, because the administrator was not pleased with the progress that Respondent was making toward completion of the job. The administrator was told by a representative of the Building Inspection Department on January 26, 1988, that Respondent had no license and that the required permit had not been pulled. The administrator was told to prohibit Respondent from working on the roof. Immediately thereafter, the administrator instructed Respondent to do no further work on the roof. The members of the Noose Lodge completed the job started by Respondent for less than $3,000.00, the balance of the amount that would have been owed Respondent if he had finished the job. Respondent knew that a permit was required for this work. Respondent also knew that only a licensed roofing contractor could pull the required permit. Respondent proceeded with the job when he was unable to persuade a licensed roofing contractor to pull the permit for him. Petitioner filed an administrative complaint against Respondent alleging that at the time he contracted with the Moose Lodge, Respondent's license was suspended, thus violating the provisions of Section 489.129(1)(j), Florida Statutes, and the provisions of Section 489.127(1)(e), Florida Statutes. The administrative complaint also alleged that Respondent failed to perform in a reasonably timely manner and/or abandoned the job in violation of Section 489.129(1)(m), Florida Statutes, and Section 489.129(1)(k), Florida Statutes. Respondent denied the allegations of the administrative complaint and timely requested a formal hearing. This proceeding followed. Respondent was previously disciplined by the Construction Industry Licensing Board, and his license remained under suspension at the time of the final hearing.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered finding Respondent guilty of having violated Section 489.127(1)(e), Florida Statutes, and Section 489.129(1)(j), Florida Statutes. It is further recommended that the final order revoke Harry Bradshaw's license in the State of Florida as a registered roofing contractor. DONE and ENTERED this 31st day of October, 1989, in Tallahassee, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of October, 1989. COPIES FURNISHED: Harry Bradshaw 5590 East Seventh Avenue Hialeah, Florida 33013 David M. Gaspari, Esquire Adams, Coogler, Watson & Merkel, P.A Suite 1600 NCNB Tower 1555 Palm Beach Lakes Boulevard West Palm Beach, Florida 33402-2069 Kenneth E. Easley, General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seely, Executive Director Department of Professional Regulation Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201

Florida Laws (3) 120.57489.127489.129
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs BRENT SOMERS GRAHAM, 98-001447 (1998)
Division of Administrative Hearings, Florida Filed:Shalimar, Florida Mar. 20, 1998 Number: 98-001447 Latest Update: Jul. 06, 1999

The Issue The issue is whether Respondent's license as a certified residential contractor should be disciplined for the reasons given in the Administrative Complaint.

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: When the events herein occurred, Respondent, Brent Somers Graham, was licensed as a certified residential contractor having been issued license no. CR C056809 by Petitioner, Department of Business and Professional Regulation, Construction Industry Licensing Board (Board). Respondent was the licensed qualifying agent for G C Construction, Inc., whose business address is not of record. At the present time, Respondent's license is in a delinquent status. In late 1995, a major hurricane struck the Panhandle section of Florida and damaged the home of Katherine M. Cook, who lived at 741 Miracle Strip, Mary Esther, in Okaloosa County, Florida. Among other things, the hurricane lifted an 78-foot porch off of her home, and a tree fell through its roof. On January 18, 1996, Cook accepted a proposal by Respondent to repair the damage to her home for $9,000.00. A description of the work to be performed by Repondent is found on Petitioner's Exhibit 2, and it includes replacing a 78-foot by 12-foot screen porch and its roof, and other related work. Cook paid Respondent $2,700.00 as a down payment on the job on January 19, 1996. On February 8, 1996, Respondent made application for a building permit with the City of Mary Esther (City). After receiving a permit, he then commenced to work on the repairs, mostly by himself but occasionally with the assistance of a few other helpers. When the job was supposedly completed in March 1996, Cook paid Respondent another $6,200.00, or a total of $8,900.00, pursuant to the parties' agreement. Within a short time, Cook noticed that the porch roof was sagging and falling in. Efforts to reach Respondent were futile since he had disconnected his telephone and apparently left the area. She then asked that an inspector for the City, Neil Sasnett, to make an inspection of her home. Sasnett quickly discovered that Respondent had never called for an inspection by the City, although the City Code required that he do so and Cook had paid for one. This omission constituted a violation of the local building code. It can be inferred from the evidence that, given the poor workmanship on the project, as described below, the violation was intentional, especially since a licensed contractor would be expected to be aware of this requirement. Sasnett found numerous deficiencies in the work just completed by Respondent, including rafters that were notched to less than 4 inches about 3 feet inside the load bearing wall, a header on the outside bearing wall that was jointed in between the upright posts, and roofing metal panels improperly sealed. These deficiencies resulted in an unsafe roof in an uplift condition and one that would be dangerous to walk on. Because Cook lived on the Gulf of Mexico, and her home was subject to windy conditions, these deficiencies were especially egregious. All of the foregoing deficiencies constituted violations of the local building code. Cook was forced to hire a second contractor to repair the porch since Respondent had left the area. For this additional work, Cook paid an additional $15,975.00, including $3,000.00 to tear out the faulty work previously performed by Respondent. At hearing, the second contractor described Respondent's work as "very poor" and "substandard." Given this consideration, and the deficiencies described by the City's inspector, it is found that the faulty work constituted incompetency in the practice of contracting on the part of Respondent. Throughout this process, Respondent refused to contact Cook or return to her home to make the needed repairs. After the complaint was issued by the Board, however, he telephoned Cook. Although he then offered to repair the porch, which had been repaired by another contractor some 18 months earlier, his main concern was that his license might be in jeopardy because of her complaint. There is no record of Respondent having been previously disciplined by the Board. Therefore, it is fair to infer that these offenses were the first committed by Respondent.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Construction Industry Licensing Board enter a Final Order finding that Respondent is guilty of the violations described in Counts I through IV of the Administrative Complaint. For those violations, it is recommended that Respondent's license be revoked, and that he be required to pay Katherine M. Cook $11,900.00 as restitution for her costs incurred in her dealings with Respondent. DONE AND ENTERED this 9th day of February, 1999, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th day of February, 1999. COPIES FURNISHED: John O. Williams, Esquire Maureen L. Holz, Esquire 355 North Monroe Street Tallahassee, Florida 32301 Brent Somers Graham 6156 White Oak Drive Flowery Brand, Georgia 30542 Rodney Hurst, Executive Director Construction Industry Licensing Board 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Lynda L. Goodgame, General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (3) 120.569455.227489.129 Florida Administrative Code (1) 61G4-17.001
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JAMES S. STROZ, 85-001135 (1985)
Division of Administrative Hearings, Florida Number: 85-001135 Latest Update: Jul. 02, 1985

Findings Of Fact At all times relevant hereto, respondent, James S. Stroz, held registered roofing contractor license number RC 0034849 issued by petitioner, Department of Professional Regulation, Florida Construction Industry Licensing Board. He was first licensed in November, 1979, and at that time qualified under the name of Stroz Roofing. A change in status application was later filed to qualify Stroz Roofing, Inc., 13696 Exotica Lane, West Palm Beach, Florida. Although licensed as a roofing contractor, respondent's firm only performs work on wood shakes or shingles. He does not do hot roofs or flat roofs, which is another speciality in the roofing business. While working for a roofing firm in1979, Stroz became acquainted with Lacy Davis, an unlicensed individual who specialized in flat roof work. When Stroz started his own roofing company in 1983, he began contracting out the flat roof work to other licensed roofing contractors. Lacy Davis learned of this and approached Stroz offering his services on the flat roof work. Stroz knew Davis was unlicensed and would not initially hire him, but Davis gave him a business card of Henry Haywood, a licensed roofing contractor in Palm Beach County and explained he and Haywood were partners and that the work and permitting would be done under Haywood's license. In actuality, Haywood had not authorized Davis to use his business cards, or topull permits under his name. Indeed, Haywood had no knowledge of Davis' activities. Without verifying the truth of Davis' representations, and accepting them instead at face value, Stroz agreed to hire Davis to perform his flat roof work. Between January 20, 1983 and September 30, 1984, Stroz performed some twenty-one jobs using Davis for the flat roof work. At all times, Stroz was under the impression that the work was being done under Haywood's license and that his activities were lawful. Stroz made all checks for the work payable to Lacy Davis or Lacy Davis Roofing. He did this because Davis told him he frequently had difficulty reaching Haywood to cash the checks, and because the business bank account was in Davis' own name. A few of the checks carried a notation at the bottom that payment was for work by Haywood Roofing, but most made no reference to Haywood. Stroz pulled all permits on their jobs reflecting that Haywood Roofing was the licensed contractor. Of the twenty invoices given by Davis to Stroz for the twenty-one jobs, only four were on invoices printed with Haywood's name. The remainder had various other names including "Lacy Davis Roofing," "Lacy Davis" and "Lacy Davis and Benny Guy Roofing Contractors." None of these were licensed as roofing contractors by petitioner. In June, 1984, a member of Davis' crew was injured and it was discovered Davis had no insurance. Stroz's insurance paid the claim, but an investigation ultimately determined that Davis was unlicensed and had no authority to act on Haywood's behalf. This led to the issuance of the administrative complaint herein. Respondent has fully cooperated with petitioner, and in fact voluntarily disclosed one job with Davis that petitioner's investigation had failed to uncover. He admits he was negligent in not checking out the representations of Davis, but he never intended to violate the law. No consumer was harmed in any way by Davis' work, and there are no complaints concerning the quality of the jobs in question.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent be found guilty as charged in the administrative complaint, and that he be fined $500 to be paid within thirty days from date of the final order rendered in this proceeding. DONE and ORDERED this 2nd day of July, 1985, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, FL 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of July, 1985.

Florida Laws (3) 120.57489.113489.129