SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT vs EDWARD TANNER, 96-004161 (1996)
Division of Administrative Hearings, Florida Filed:Bartow, Florida Sep. 03, 1996 Number: 96-004161 Latest Update: Mar. 10, 1997

The Issue The issue for consideration in this case is whether the Department should impose administrative penalties in the form of fines, costs and points assessment because of the matters alleged in the Administrative Complaint and Order entered herein.

Findings Of Fact At All times pertinent to the issued herein, the Petitioner, SWFWMD, was the governmental agency responsible for the licensing of well contractors and the permitting of well drilling and abandonment within its jurisdictional area. Respondent, Edward Tanner, was a licensed water well contractor, holding license Number 2276 issued on July 21, 1982. On January 16, 1996, SWFWMD issued Well Construction permit 575267.01 to Respondent for the abandonment of a four-inch diameter water well on property owned by Mr. McCrimmon located at Five Tera Lane in Winter Haven. The well, a domestic water well, had failed and Respondent applied for a permit to construct a new well at the site and abandon the failed well. Stipulation Number Four of the permit issued to the Respondent provided that the well must be examined for debris or obstructions from the land surface to the original depth of construction, and further required that any debris or obstruction discovered be removed from the well prior to the commencement of abandonment. In addition, the stipulation called for the well to be plugged from bottom to top by an approved method of grouting. According to the permit, if any other method of abandonment was to be used, it must be approved in advance by specifically denoted District personnel. Though Respondent did not utilize the approved method of abandonment in this project, he did not apply for a variance from the District. Had he done so, he would have been required to show some emergency or hardship which would have prevented him from properly filling the abandoned well with cement from top to bottom and justified an alternative method of abandonment. In this case, Respondent plugged the well in issue, which was 210 feet in depth, from the land surface down to fifty five feet, utilizing six bags of portland cement. Deviation from the 210 foot plug required a variance to be granted by the District. Respondent did not seek this variance. Well abandonment is a regulated practice because, inter alia, improper abandonment may result in contamination of the aquifer. The well in question here is located in an area susceptible to contamination by ethylene dibromide, (EDB), recognized as a human carcinogen, which is known to be present in the area. In addition to failing to properly abandon the well, Respondent also failed to file a well completion report within thirty days of completion of his abandonment effort. The required report was submitted on June 10, 1996, nearly four months after it was due. Respondent relates that in January 1996, after he had worked on a well “commonly known” to be the subject of litigation, he was asked to try to fix the well in issue. When he saw the problem, he contends he repeatedly advised the authorities that the well was leaking sand and could not be cleaned out to the bottom as the District required. Therefore, to preserve the integrity of the well, he plugged it at a point below the break in the well lining. At that time, he told Mr. McCrimmon what the situation was and advised him the well needed to be abandoned, but he, Tanner, did not do that type of work. Respondent contends, supported by his son, that on January 16, 1996, while he was at Mr. McCrimmon’s property, he was told by Mr. Wheelus and Mr. Lee, both District officials, that Mr. Calandra, also a District official had said he, Tanner, had to pull a well abandonment permit or Calandra would not sign off on the new well. At that point, Respondent claims, he went to the District’s Bartow office to argue with Mr. Calandra, and asked Mr. Calandra to show him the law which supported Calandra’s position. Calandra persisted in his position and even, according to Respondent, bet with another District employees that Respondent had to do what he was told. This other employee does not recall any such bet. Therefore, under protest and only so he could get paid for the work he had done on the new well, Respondent agreed to pull the abandonment permit. At that time, he claims, he asked the District personnel in charge how many bags of concrete would be required to abandon the well and was told, “six”. When the time came to do the actual work, Respondent called for the required observer to be present from the District office, but because no one was available at the time, he was granted permission to do it without observation. He did the job as he felt it had to be done, and thirty days to the day after that, was served with the notice of violation. Respondent contends either that the witnesses for the District are lying in their denials of the coercive statements he alleges, or the situation is a conspiracy to deprive him of his civil rights. He does not believe a well contractor should be required to stay current regarding all the District rules regarding well construction and abandonment because the rules change so often. Respondent admits, however, that the rules in existence at the time in question required the filling of a well all the way down and that he did not do that nor did he seek a variance., He knew he was required to comply with the conditions of a permit. He also admits that a completion report was due within thirty days of work completion. In that regard, however, he contends that when the issue went into litigation, he felt the district would advise him of what he had to do. In this he was mistaken, but he was not misled into believing so by anything done or said by District personnel. Taken together, the evidence does not demonstrate that anyone from the District staff coerced Respondent into abandoning the well. He was issued a permit to drill the new well for Mr. McCrimmon with no conditions thereon. By the same token, the abandonment permit he obtained did require the complete clearing and total plugging of the abandoned well, and this was not done. The costs incurred by the District in the investigation and enforcement of this alleged violation totaled in excess of $500.00.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Southwest Florida Water Management District enter a final order finding Respondent, Edward Tanner, guilty of improperly abandoning the well in issue and failing to file the required report in a timely manner, and assessing enforcement costs in the amount of $500.00 in addition to an administrative fine of $250.00. DONE and ENTERED this 29th day of January, 1997, in Tallahassee, Florida. ARNOLD H. POLLOCK Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6947 Filed with the Clerk of the Division of Administrative Hearings this 29th day of January, 1997. COPIES FURNISHED: Margaret M. Lytle, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899 Edward Tanner 1137 Saint Anne Shrine Road Lake Wales, Florida 33853 Peter G. Hubbell Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899

Florida Laws (1) 120.57 Florida Administrative Code (2) 40D-3.30140D-3.531
# 1
WEST COAST REGIONAL WATER SUPPLY AUTHORITY vs. SOUTHWEST FLORIDA REGIONAL PLANNING COUNCIL, 80-001004RP (1980)
Division of Administrative Hearings, Florida Number: 80-001004RP Latest Update: Aug. 08, 1980

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: The petitioner West Coast Regional Water Supply Authority (WCRWSA) was formed in 1974 by inter-local agreement under Chapter 373, Florida Statutes, as a supply entity to provide and develop sources of water for its members and other governmental entities. The members of WCRWSA include the two cities of St. Petersburg and Tampa and the three counties of Pinellas (intervenor herein), Hillsborough and Pasco. The petitioner and the intervenor own and operate permitted well fields which are regulated by the respondent Southwest Florida Water Management District (SWFWMD) and are therefore subject to the rules and regulations of SWFWMD. All parties have stipulated, and the evidence so demonstrates, that the WCRWSA and Pinellas County are substantially affected by the challenged proposed rule and therefore have standing to challenge its validity. The proposed rule being challenged in this proceeding was considered by the Governing Board of SWFWMD as a result of a prior rule being declared invalid in another proceeding. The prior rule, codified as Rule 16J-2.11(3), Florida Administrative Code, provided as follows: 16J-2.11 Conditions for a Consumptive Use Permit Issuance of a permit will be denied if the amount of water consumptively used will exceed the water crop of lands owned, leased or otherwise controlled by the applicant. (Except where determined otherwise, the water crop [precipitation less evapotranspiration] throughout the District will be assumed to be three hundred sixty-five thousand (365,000) gallons per year per acre.) By Final Order dated April 9, 1980, 1/ that rule was declared to be an invalid exercise of delegated legislative authority on the grounds that it exceeded SWFWMD's statutory authority under Chapter 373, Florida Statutes, it impermissibly conflicted with provisions of Chapter 373, Florida Statutes, it created property rights to water by virtue of land ownership contrary to Chapter 373 and the decision in the case of Village of Tequesta v. Jupiter Inlet Corp., 371 So.2d and 663 (Fla. 1979); and it was a hydrologically unsound method of determining the issuance or denial of consumptive use permits and was accordingly arbitrary and capricious in nature. The two subsections of proposed Rule 40D-2.301 being challenged in this proceeding read as follows: "40D-2.301. Conditions for Issuance of Permits. Among other factors to be considered by the Board in determining whether a particular use is consistent with the public interest will be: the maximum amount to be withdrawn of a single day; the average amount to be withdrawn during a single week, during a typical growing (or irrigation) season, during an extreme cold season, during a year of extreme drought an during the term of the proposed permit; the amount to be withdrawn in relationship to amounts being withdrawn from adjacent or nearby properties; the proximity of withdrawal points to location of points of withdrawal by others; the total amounts presently permitted from the entire basin, or other hydrologic unit; and the change in storage that such withdrawal and use will cause. If the proposed consumptive use will average less than 1,000 gallons per acre per day, in the absence of evidence to the contrary, the Board will presume that the quantity of water proposed for consumptive use is consistent with the public interest and the applicant will not be required to submit further evidence on this point. If the proposed consumptive use is to average 1,000 gallons or more per acre per day, the applicant must establish that the proposed use of water in such quantity is consistent with the public interest. (NOTE: Present subsections 6 through 11 will be renumbered consecutively following the above new subsections.) The factors listed in subsection (6) of the proposed rule are not all- inclusive. Each of the factors listed are resource related or hydrological considerations. The effect of each of the factors listed is appropriate for consideration by the Governing Board of SEFWMD when making a determination as to whether a consumptive use permit should be granted. With the exception of that portion of subsection (6) relating to a weekly average amount to be withdrawn, the factors listed in subsection (6) are covered by existing specific rules of SWFWMD. The word "acre" in the phrase "1,000 gallons per acre per day" is intended to mean land owned, leased or otherwise controlled by the applicant. The figure of 1,000 gallons per acre per day represents the average quantity of water which is available within the respondent's District for man's use and to maintain natural systems. The figure is a district wide estimation. It cannot be arbitrarily applied to any specific site within the District due to the fact that different parcels of land do not possess identical geologic or hydrologic characteristics. The amount of water which is available from a specific parcel of land is dependent upon geographical and hydrological factors which vary considerably from site to site. These factors include, among other things, the amount of rainfall the land receives, the water table, the existence of confining layers, soil and vegetation types, and transmissivity, storage and leakage coefficients. Withdrawals of water in small amounts per acre per day are generally less likely to have adverse hydrologic effects on the water resources within the District than are withdrawals in greater amounts. In most areas of the District, 1,000 gallons per acre per day can be withdrawn without jeopardizing or adversely affecting the resource or the availability of water for others. This would not necessarily be true of coastal areas where salt water intrusion is a possibility or in areas where wells presently exist which withdraw large quantities of water on a daily basis. Eighty-nine percent (89%) of the more than 6,000 consumptive use permits which have been issued by the SWFWMD are for amounts less than 1,000 gallons per acre per day.

Florida Laws (6) 120.52120.54373.019373.113373.171373.223 Florida Administrative Code (1) 40D-2.301
# 2
ANGELO`S AGGREGATE MATERIALS, LTD. vs SUWANNEE RIVER WATER MANAGEMENT DISTRICT, 01-004383RX (2001)
Division of Administrative Hearings, Florida Filed:Live Oak, Florida Nov. 09, 2001 Number: 01-004383RX Latest Update: Oct. 22, 2002

The Issue Whether Rules 40B-1.702(4); 40B-4.1020(12) and (30); 40B-4.1030; 40B-4.1040(1)(b) and (c); 40B-4.2030(4); 40B-4.3000(1)(a); 40B-4.3010; 40B-4.3020; 40B-4.3030; 40B- 4.3040; and 40B-400.103(1)(h), Florida Administrative Code, of the Suwannee River Water Management District, are an invalid exercise of delegated legislative authority for reasons described in the Second Amended Petition to Determine Validity of Rules.

Findings Of Fact Stipulated Facts Angelo's is a Florida Limited Partnership, whose address is 26400 Sherwood, Warren, Michigan 48091. The District is an agency of the State of Florida established under Chapter 373, Florida Statutes, with its address at 9225 County Road 49, Live Oak, Florida 32060. Angelo's owns property in Hamilton County approximately four miles to the east of Interstate 75 and to the north of U.S. Highway 41, immediately to the east of the Alapaha River. Angelo's conducts commercial sand mining operations on a portion of its property pursuant to various agency authorizations, including an Environmental Resource Permit (ERP) issued by the Florida Department of Environmental Protection (Department), Permit No. 158176-001, and a Special Permit issued by Hamilton County, SP 98-3. The ERP was issued by the Department pursuant to its authority under Chapter 373, Part IV, Florida Statutes. Angelo's mining operations constitute a "mining project" as that term is used in Section II.A.1.e of an Operating Agreement Concerning Regulation under Part IV, Chapter 373, Florida Statutes, and Aquaculture General Permits under Section 403.814, Florida Statutes, between the District and the Department (Operating Agreement). The Operating Agreement has been adopted as a District rule pursuant to Rule 40B-400.091, Florida Administrative Code. Angelo's has filed with the Department an application to modify its ERP to expand its sand mining operations into an area of its property immediately to the west of its current operations (the "proposed expanded area"). Angelo's application is being processed by the Department at this time. Angelo's ERP modification application is being processed by the Department under the Operating Agreement. The District has asserted permitting jurisdiction over the proposed expanded area because the proposed sand mining activities would occur in what the District asserts to be the floodway of the Alapaha. The District asserts that an ERP would be required from the District so that the District can address the work of the district (WOD) impacts. Petitioner has not filed a permit application with the District regarding the project. It is Petitioner's position that to do so would be futile. The Challenged Rules The rules or portions thereof which are challenged in this proceeding are as follows: Rule 40B-1.702(4), Florida Administrative Code, reads as follows: (4) A works of the district permit under Chapter 40B-4, F.A.C., must be obtained prior to initiating any project as outlined in (3) above within a regulatory floodway as defined by the District. Rule 40B-4.1020(12) and (30), Florida Administrative Code, read as follows: (12) "Floodway" or 'regulatory floodway" means the channel of a river, stream, or other watercourse and adjacent land areas that must be reserved in order to discharge the 100-year flood without cumulatively increasing the 100-year flood elevation more than a designated height. Unless otherwise noted, all regulatory floodways in the Suwannee River Water Management District provide for no more then one-foot rise in surface water. * * * (30) "Work of the district" means those projects and works including, but not limited to, structures, impoundments, wells, streams, and other watercourses, together with the appurtenant facilities and accompanying lands, which have been officially adopted by the governing board as works of the district. Works of the district officially adopted by the board are adopted by rule in Rule 40B-4.3000 of this chapter. Rule 40B-4.1030, Florida Administrative Code, reads as follows: The implementation dates of this chapter are as follows: January 1, 1986 for Rule 40B- 4.1040(1)(a) which requires persons to obtain surfacewater management permits. April 1, 1986 for Rule 40B- 4.1040(1)(b) and Rule 40B-4.3040 which require persons to obtain works of the district development permit if the proposed development is in one of the following areas adopted as a work of the district. The Alapaha River and its floodway in Hamilton County, Florida; The Aucilla River and its floodway in Jefferson, Madison, or Taylor counties, Florida; The Suwannee River or its floodway in Columbia, Hamilton, Lafayette, Madison, or Suwannee counties, Florida; or The Withlacoochee River and its floodway in Hamilton or Madison counties, Florida. (c) July 1, 1986 for Rule 40B-4.1040(1)(b) or 40B-4.3040 which require persons to obtain work of the district development permit if the proposed development is in one of the following areas adopted as a work of the district. The Santa Fe River and its floodway in Alachua, Bradford, Columbia, Gilchrist, Suwannee, or Union counties, Florida; or The Suwannee River and its floodway in Dixie, Gilchrist, or Levy counties, Florida. Rule 40B-4.1040(1)(b) and (c), Florida Administrative Code, reads as follows: (1) Permits are required as follows: * * * Works of the district development permit prior to connecting with, placing structures or works in or across, discharging to, or other development within a work of the district. When the need to obtain a works of the district development permit is in conjunction with the requirements for obtaining a surfacewater management permit, application shall be made and shall be considered by the district as part of the request for a surfacewater management permit application. Otherwise, a separate works of the district development permit must be obtained. Rule 40B-4.2030(4), Florida Administrative Code, reads as follows: (4) The new surfacewater management systems or individual works shall not facilitate development in a work of the district if such developments will have the potential of reducing floodway conveyance. (emphasis supplied) Rule 40B-4.3000(1)(a), Florida Administrative Code, reads as follows: The governing board is authorized to adopt and prescribe the manner in which persons may connect with or make use of works of the district pursuant to Section 373.085, Florida Statutes. Further, Section 373.019(15) provides that works of the district may include streams and accompanying lands as adopted by the governing board. In order to implement the non-structural flood control policy of the district, the governing board finds it is necessary to prevent any obstruction of the free flow of water of rivers and streams within the district. Therefore, the governing board does hereby adopt the following rivers and their accompanying floodways as works of the district: The Alapaha River and its floodway in Hamilton County, Florida; . . . . Rule 40B-4.3010, Florida Administrative Code, reads as follows: A general works of the district development permit may be granted pursuant to the procedures in Rule 40B-1.703 to any person for the development described below: Construction of a structure for single-family residential or agricultural use including the leveling of land for the foundation and associated private water supply, wastewater disposal, and driveway access which is in compliance with all applicable ordinances or rules of local government, state, and federal agencies, and which meets the requirements of this chapter. A general permit issued pursuant to this rule shall be subject to the conditions in Rule 40B-4.3030. Rule 40B-4.3020, Florida Administrative Code, reads as follows: Content of Works of the District Development Permit Applications. Applications for a general work of the district development permit shall be filed with the district and shall contain the following: Form 40B-4-5, "Application for General Work of the District Development Permit," Suwannee River Water Management District, 4-1-86, hereby incorporated by reference and which contains the following: The applicant's name and complete address including zip code; The owner's name and complete address if applicant is other than the owner; If applicable, the name, complete address, phone number, and contact person of the applicant or owner; Copies of all permits received from local units of government, state, or federal agencies, specifically a copy of the building or development permit issued by the appropriate unit of local government, including any variances issued thereto, and a copy of the onsite sewage disposal system permit issued by the Florida Department of Health and Rehabilitative Services under Chapter 10D- 6, Florida Administrative Code; A site plan to scale showing all improvements, work, or works with any conditions or limitations placed thereon; and Any supporting calculations, designs, surveys, or applicable documents, which in the applicant's opinion, may support the application. Applications for individual or conceptual approval works of the district development permits shall be filed with the district and shall contain the following: Form 40B-4-4, "Application for Surfacewater Management System Construction, Alteration, Operation, Maintenance, and/or Works of the District Development", Suwannee River Water Management District, 10-1-85, hereby adopted by reference and which contains the following: The applicant's name and complete address including zip code; The owner's name and complete address if applicant is other than the owner; If applicable, the name, complete address, phone number, and contact person of the owner. General project information including: The applicant's project name or identification number; The project location relative to county, section, township, and range, or a metes and bounds description; The total project area in acres; The total land area owned or controlled by the applicant or owner which is contiguous with the project area; A description of the scope of the proposed project including the land uses to be served; A description of the proposed surfacewater management system or work; A description of the water body or area which will receive any proposed discharges from the system; and Anticipated beginning and ending date of construction or alteration. Copies of all permits received from, or applications made to, local units of government, state, or federal agencies. A site plan to scale showing all improvements, work, or works with any conditions or limitations placed thereon. Any supporting calculations, designs, surveys, or applicable legal documents, which in the applicant's opinion, support the application. Copies of engineer or surveyor certifications required by this chapter. Rule 40B-4.3030, Florida Administrative Code, reads as follows: Conditions for Issuance of Works of the District Development Permits. The district will not approve the issuance of separate permits for development in a work of the district for any proposed project that requires a district surfacewater management permit pursuant to Part II of this chapter. For such projects, development in a work of the district may be authorized as part of any surfacewater management permit issued. The district will not approve the issuance of a works of the district development permit for any work, structures, road, or other facilities which have the potential of individually or cumulatively reducing floodway conveyance or increasing water-surface elevations above the 100-year flood elevation, or increasing soil erosion. The district will presume such a facility will not reduce conveyance or increase water-surface elevations above the 100-year flood elevation or increase soil erosion if: Roads with public access are constructed and laid out in conformance with the minimum standards of local government. Where roads are not required to be paved, the applicant must provide design specifications for erosion and sediment control. Where roads are required to be paved, swales will generally be considered adequate for erosion and sediment control; Buildings in the floodway are elevated on piles without the use of fill such that the lowest structural member of the first floor of the building is at an elevation at least one foot above the 100-year flood elevation; The area below the first floor of elevated buildings is left clear and unobstructed except for the piles or stairways; A permanent elevation monument is established on the property to be developed by a surveyor. The monument shall be adequate to establish land surface and minimum buildup elevations to the nearest 1/100 of a foot; No permanent fill or other obstructions are placed above the natural grade of the ground except for minor obstructions which are less than or equal to 100 square feet of the cross-sectional area of the floodway on any building or other similar structure provided that all such obstruction developed on any single parcel of land after the implementation date of this chapter is considered cumulatively; No activities are proposed which would result in the filling or conversion of wetlands. For any structure placed within a floodway which, because of its proposed design and method of construction, may, in the opinion of the district, result in obstruction of flows or increase in the water surface elevation of the 100-year flood, the district may require as a condition for issuance of a work of the district development permit that an engineer certify that such a structure will not obstruct flows or increase 100-year flood elevations. The following conditions shall apply to all works of the district development permits issued for development on lands subdivided after January 1, 1985: Clearing of land shall be limited [except as provided in (b) and (c) below] to that necessary to remove diseased vegetation, construct structures, associated water supply, wastewater disposal, and private driveway access facilities, and no construction, additions or reconstruction shall occur in the front 75 feet of an area immediately adjacent to a water. Clearing of vegetation within the front 75 feet immediately adjacent to a water shall be limited to that necessary to gain access or remove diseased vegetation. Harvest or regeneration of timber or agricultural crops shall not be limited provided the erosion of disturbed soils can be controlled through the use of appropriate best management practices, the seasonal scheduling of such activities will avoid work during times of high-flood hazard, and the 75 feet immediately adjacent to and including the normally recognized bank of a water is left in its natural state as a buffer strip. As to those lands subdivided prior to January 1, 1985, the governing board shall, in cases of extreme hardship, issue works of the district development permits with exceptions to the conditions listed in Rule 40B-4.3030(4)(a) through (c). The 75-foot setback in paragraphs (a) through (d) above shall be considered a minimum depth for an undisturbed buffer. The limitations on disturbance and clearing within the buffer as set out in paragraphs through (d) above shall apply, and any runoff through the buffer shall be maintained as unchannelized sheet flow. The actual depth of the setback and buffer for any land use other than single-family residential development, agriculture, or forestry shall be calculated in accordance with the methodology in: "Urban Hydrology for Small Watersheds", U.S. Department of Agriculture, Soil Conservation Service, Engineering Division, Technical Release 55, June 1986; and, "Buffer Zone Study for Suwannee River Water Management District", Dames and Moore, September 8, 1988, such that the post-development composite curve number for any one-acre area within the encroachment line does not exceed; a value of 46 for areas within the encroachment line with predominantly Class A soils; a value of 65 for areas within the encroachment line with predominantly Class B soils; a value of 77 for areas within the encroachment line with predominantly Class C soils; or a value of 82 for areas within the encroachment line with predominantly Class D soils. (emphasis supplied) Rule 40B-4.3040, Florida Administrative Code, reads as follows: Unlawful Use of Works of the District. It shall be unlawful to connect with, place a structure in or across, or otherwise cause development to occur in a work of the district without a works of the district development permit. The district may use any remedy available to it under Chapter 120 or 373, Florida Statutes, and Chapter 40B-1, Florida Administrative Code, to cause an unpermitted development to be removed or permitted. It shall be unlawful for any permitted use to violate the provisions of Chapter 373, Florida Statutes, or this chapter, or the limiting conditions of a works of the district development permit. The district may use any remedy available to it under Chapter 120 or 373, Florida Statutes, and Chapter 40B-1, Florida Administrative Code, to cause the unpermitted use to be removed or brought into compliance with Chapter 373, Florida Statutes, and this chapter. Damage to works of the district resulting from violations specified in Rule 40B-4.3040(1) and (2) above shall be repaired by the violator to the satisfaction of the district. In lieu of making repairs, the violator may deposit with the district a sufficient sum to insure such repair. Rule 40B-400.103(1)(h), Florida Administrative Code, reads as follows: (1) In order to obtain a standard general, individual, or conceptual approval permit under this chapter or chapter 40B-4, F.A.C., an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal or abandonment of a surface water management system: * * * (h) Will not cause adverse impacts to a work of the District established pursuant to s. 373.086. . . . Facts Based Upon the Evidence of Record History of the rules Mr. David Fisk is Assistant Director of the District. At the time of the hearing, he had been employed there for 26 and one-half years. He played a significant role in the rule adoption process of the rules that are the subject of this dispute. As part of that process, the District entered into a consulting contract with an engineering, planning, and consulting firm and consulted with the U.S. Corps of Engineers and the Federal Emergency Management Agency (FEMA), to conduct what are described as the FEMA flood studies. Additionally, the district commissioned an aerial photography consultant who provided a series of rectified ortho photographs of the entire floodplain of the rivers within the District, and a surveying subcontractor who provided vertical control and survey cross sections and hydrographic surveys of the rivers. The District also worked in conjunction with the United States Geological Survey to accumulate all of the hydrologic record available on flooding. The information was given to the U.S. Army Corps of Engineers who, operating under FEMA guidelines for conducting flood insurance rate studies, performed the analytical and computer modeling work to identify the flood plains and floodway boundaries. The District used the amassed knowledge of maps, cross sections and surveys that were developed as part of the FEMA flood studies as technical evidence or support for the adoption of the works of the district rules. Following a series of public workshops and public hearings in 1985, the rules were adopted and became effective in 1986. None of the rules were challenged in their proposed state. The District adopted the floodways of the Suwannee, Santa Fe, Alapaha, Aucilla, and Withlacoochee Rivers as works of the district. According to Mr. Fisk, the District adopted the rules pursuant to Section 373.086, Florida Statutes, which provided authority to the District to adopt district works and Section 373.085, Florida Statutes, which provided authority to regulate activities within those works. The Floodway Line Petitioner hired Mr. John Barnard, a professional civil engineer, with extensive environmental permitting experience, to look at the floodway and floodplain issues associated with Petitioner's site and project. Mr. Barnard conducted an engineering study entitled, "Floodplain Evaluation." It was Mr. Barnard's opinion that FEMA's determination of the floodway line was less than precise. Mr. Barnard used FEMA's data regarding the base flood elevation but manually changed the encroachment factor resulting in his placement of the floodway line in a different location than determined by FEMA. Mr. Barnard acknowledged that different engineers using different encroachment factors would reach different conclusions.1/ Respondent's expert in hydrology and hydraulic engineering, Brett Cunningham, noted that the definition of floodway in Rule 40B-4.1020(12), Florida Administrative Code, is essentially the same definition that used is in the FEMA regulations and which also is commonly used across the country in environmental rules and regulations. Mr. Barnard also acknowledged that the District's definition of "floodway", as found in Rule 40B-4.1020(12), Florida Administrative Code, is fairly commonly used by environmental regulatory agencies. Moreover, it was Mr. Cunningham's opinion that the Alapaha River is a stream or watercourse within the meaning of the rule and its floodway an accompanying land. In Mr. Cunningham's opinion, the FEMA flood insurance studies are widely used across the country for a variety of reasons and are typically relied upon by hydrologists and engineers to locate floodways. The definition of "works of the district" in Rule 40B-1020(30), Florida Administrative Code, is taken directly from the language found in Section 373.019(23), Florida Statutes. The statutory definition includes express references to streams and other watercourses, together with the appurtenant facilities and accompanying lands. Petitioner alleges that the phrase "will not cause adverse impact to a work of the SRWMD" as found in Rule 40B- 400.103(1)(h) is not clear because it does not identify what specific adverse impacts are being reviewed. While Petitioner's expert, Mr. Price, was not clear as to what the phrase means, Respondent's expert, Mr. Cunningham, understood the meaning of the phrase and noted that "adverse impact" is a phrase which is very commonplace in the rules and regulations of environmental agencies and is attributed a commonsense definition. The expert engineers differed in their opinions as to the meaning of the term "potential for reducing floodway conveyance" as used in Rule 40B-4.2030(4), Florida Administrative Code. According to Petitioner's expert engineer, Mr. Barnard, "potential for reducing floodway conveyance" is not a specific term that is open to interpretation as an engineer, and that he cannot quantify what constitutes "potential." Respondent's expert, Mr. Cunningham, understood the meaning of the phrase to be any increase in floodway conveyance. It was his opinion that there was nothing about that phrase to cause confusion. Rule 40B-4.3030, Florida Administrative Code, addresses conditions for issuance of works of the district development permits. Petitioner's expert Mr. Price testified that there is no quantification to what constitutes an "increase in soil erosion" as referenced in subsection (2) and linked the reference of soil erosion to a 100-year flood event referenced in the same subsection. Mr. Cunningham was of the opinion that there is no need to quantify an increase in soil erosion in the rule. He noted that soil erosion is used in a common sense manner and that attempting to put a numerical limit on it is not practical and "it's not something that's done anywhere throughout the country. It's just not something that lends itself to easy quantification like flood stages do". Mr. Cunningham's opinion that the words and phrases which Petitioner asserts are vague are words of common usage and understanding to persons in the field is the more persuasive testimony. This opinion is also consistent with statutory construction used by courts which will be addressed in the conclusions of law.

Florida Laws (15) 120.52120.536120.54120.56120.57120.595120.68373.019373.044373.085373.086373.113373.171403.814704.01
# 3
SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT vs DEBORAH SUGGS, 03-001128 (2003)
Division of Administrative Hearings, Florida Filed:Bushnell, Florida Mar. 28, 2003 Number: 03-001128 Latest Update: Dec. 24, 2024
# 4
SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT vs AMBER SUGGS, 03-000788 (2003)
Division of Administrative Hearings, Florida Filed:Bushnell, Florida Mar. 05, 2003 Number: 03-000788 Latest Update: Dec. 24, 2024
# 5
CITY OF BRADENTON vs SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT, 92-007161 (1992)
Division of Administrative Hearings, Florida Filed:Bradenton, Florida Dec. 04, 1992 Number: 92-007161 Latest Update: Jul. 05, 1994

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant findings of fact are made:

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that the District enter a Final Order denying the City's petition for a variance from the established lawn and landscape irrigation restrictions imposed under the District's Governing Board Order 92-12, as amended. RECOMMENDED this 31st day of May, 1994, at Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of May, 1994. APPENDIX TO RECOMMENDED ORDER, CASE NO. 92-7161 The following constitutes my specific rulings, pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the parties in this case. Petitioner, City of Bradenton 1. The following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 1(7); 2(10); 3(12); 4(11); 6(13); 8-9(3); 12(15a); 16(3); 17(37); 19(38); 23-24(39); 48(40); 49(44); 50,51(42), 53-65(42), 67-70(42); 71(41); 72(42); 76(15a); 77-78(15b); 81- 82(15c); 84(15a); 101(17); 107-119(20-21); 120-126(22-27); 127-131(28); 132- 139(29); 140(25-28); 141(20-24); 142(23-24); 143(47); and 145-146(41). 2. Proposed findings of fact 5, 10, 11, 13-15, 18, 20-22, 25-32, 35-47, 52, 66, 73-75, 79, 80, 83, 85, 87-95, 97, 99, and 102-106 are either immaterial, irrelevant, subordinate or unnecessary. Proposed finding of fact 7 is covered in the Preliminary Statement. Proposed findings of fact 33, 34, 86, 96, 98, and 100 are not supported by competent substantial evidence in the record. Respondent, Southwest Florida Water Management District The following proposed finding(s) of fact are adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding(s) of Fact which so adopts the proposed finding of fact: 1(7); 2(9); 3(7,8); 4(10,12); 5(4); 6(15); 7-8(6); 9(18); 10(17); 11-12(19); 13(20); 14(21); 16(22,23); 17(23,24); 18(25); 19(26); 20(27); 21-22(28); 24(47); 25(46); 26(29); 27(29); 28(30,35); 29-31(31); 32(45); 33(32); 34(33); 35(34); 36(36); 37(37,39); 38(40); 39(41); 40(43); 41(42); 42(43); and 43(44). Proposed findings of fact 15, 23 and 44 are not supported by competent substantial evidence in the record. COPIES FURNISHED: Barbara B. Levin, Esquire Davis, Persson, Smith & Darnell 2033 Main Street, Suite 406 Sarasota, Florida 34237 William Lisch, Esquire 519 13th Street West Bradenton, Florida 34205 James A. Robinson, Esquire Mark F. Lapp, Esquire Southwest Florid Water Management District 2379 Broad Street Brooksville, Florida 34609-6899 Peter G. Hubbell Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899

Florida Laws (7) 120.57120.68373.044373.113373.114373.246373.617 Florida Administrative Code (2) 40D-21.60140D-21.641
# 6
MAC A. GRECO, JR.; JOSEPHINE GRECO; ET AL. vs. WEST COAST REGIONAL WATER SUPPLY AUTHORITY AND SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT, 89-003187 (1989)
Division of Administrative Hearings, Florida Number: 89-003187 Latest Update: Apr. 19, 1990

The Issue The issue at this stage of the proceeding is whether jurisdiction should be relinquished to the Southwest Florida Water Management District based upon the withdrawal of Petitions filed herein on behalf of the Petitioners, and the filing of a stipulation and settlement agreement executed on behalf of the Petitioners and Respondents.

Findings Of Fact By Notices of Referral dated June 7, 1989, and filed June 1 6, 1989, the Southwest Florida Water Management District (District) transmitted to the Division of Administrative Hearings (DOAH) certain Petitions filed on behalf of Petitioners which opposed the issuance of a consumptive use permit numbered 208426 by the District to the West Coast Regional Water Supply Authority (Authority). These Petitions were assigned Case Numbers 89-3187 through 89-3189 by DOAH, and were consolidated for all further proceedings. On August 18, 1989, Chilpub, Inc. (Chilpub), filed a Petition to Intervene, which was granted by Order entered on September 6, 1989. On October 20, 1989, Wiregrass Ranch, Inc. (Wiregrass), filed a Petition to Intervene, which was granted by Order entered on October 31, 1989. The Petitions filed on behalf of Chilpub and Wiregrass were filed at DOAH, and specifically sought leave to intervene in Cases Numbered 89-3187 through 89-3189 in order to oppose the issuance of permit number 208426 to the Authority. Following the granting of these Petitions, Chilpub and Wiregrass have participated in this proceeding as Intervenors On or about November 8, 1989, the Authority provided Wiregrass with a copy of the Notice of Proposed Agency Action which is the subject of this proceeding, pursuant to Rule 40D-2.101, Florida Administrative Code. However, subsequent to receiving this Notice of Proposed Agency Action, Wiregrass failed to file with the District any Petition in its own right seeking to initiate a proceeding under Section 120.57(1), Florida Statutes, to challenge the issuance of permit number 208426 to the Authority. Notices of Withdrawal of Petitions for Formal Hearing were filed on behalf of the Petitioners in Cases Numbered 89-3187 through 89-3189 on April 4, 1990, and on that same date, the Petitioners and Respondents filed their Joint Motion to Relinquish Jurisdiction. A copy of the Stipulation and Settlement Agreement executed by the Petitioners and Respondents was filed on April 9, 1990.

Recommendation Based upon the foregoing, it is recommended that the District enter a Final Order dismissing the Petitions filed herein, and issuing permit number 208426 to the Authority. DONE AND ENTERED this 19 day of April, 1990 in Tallahassee, Florida. DONALD D. CONN Hearing Officer Division of Administrative Hearings The DeSoto Building 120 Apalachee Parkway Tallahassee, Florida 32399-1550 Filed with the Clerk of the Division of Administrative Hearings this 19 day of April, 1990. COPIES FURNISHED: David L. Smith, Esquire Jeffrey A. Aman, Esquire 712 South Oregon Avenue Tampa, FL 33606 Edward P. de la Parte, Jr., Esquire Barbara B. Levin, Esquire 705 East Kennedy Blvd. Tampa, FL 33602 Bram Canter, Esquire 306 North Monroe Street Tallahassee, FL 32302 Enola T. Brown, Esquire P. O. Box 3350 Tampa, FL 33601-3350 James S. Moody, Jr., Esquire P. O. Box TT Plant City, FL 33564-9040 Peter G. Hubbell Executive Director SWFWMD 2379 Broad Street Brooksville, FL 34609-6899

Florida Laws (1) 120.57 Florida Administrative Code (1) 40D-2.101
# 7
LORENZO LAKES vs. SOUTHWEST FLORIDA REGIONAL PLANNING COUNCIL, 75-000306 (1975)
Division of Administrative Hearings, Florida Number: 75-000306 Latest Update: Jan. 24, 1977

The Issue Whether a consumptive-use permit for quantities of water as applied for should be granted.

Findings Of Fact Applicant applied for a permit for a public supply of water from two (2) wells to accommodate 3,100 family units in Hillsborough County, Florida. Each well to be 500 feet deep and designated as "new use", i.e., a use not existing prior to January 1, 1975. Well "No. 1" would draw 72,000 gallons per day and well "No. 2", 682,000 gallons per day. The center of withdrawal is located at latitude 28 degrees 6' 18" North, longitude 82 degrees 29' 48" West in Hillsborough County, Florida. The applicant lists 802.2 acres as being owned, leased or otherwise controlled by it. Notice was published in a newspaper of general circulation, to-wit: The Tampa Tribune on April 28 and May 5, 1975, pursuant to Section 373.146, Florida Statutes. Notices of said public hearing were sent by certified mail to Lorenzo Lakes, A Joint Venture, Route 2, Box 737A, Lutz, Florida, and Hillsborough Dairy, Route 1, Box 115, Tampa, Florida A letter was received although it was not designated a letter of objection. The author of said letter is present at this hearing. His name is Mr. John Logan, Water Resources Director, Hillsborough County, Florida. The letter suggests that action on the subject application would be inappropriate at this time inasmuch as a part of the development is to be deeded to Hillsborough County for public roadways. A specific area does not appear to be established but it may exceed 50 acres. Additional acreage may be needed for flood easements for the extension of channel "F", a proposed part of the upper Tampa Bay Watershed Project. No formal letters of objection were received. The following exhibits were introduced without objection: Application for permit Proof of publication Letter from Mr. John Logan The witnesses were duly sworn and agreement by the parties reached on each point to be considered under Chapter 373, Florida Statutes, and the Rules and Regulations promulgated pursuant thereto, particularly Rule 16J-2.11, with the exception that certain conditions were recommended by Mr. George Szell, Hydrologist for the Permittee, and said conditions were agreed to by the Permittee. Mrs. Sally Casper appeared as a member of the public questioning the need for new housing and objecting in essence to Rule 16J-2.11(2)(e) which restricts consideration of lake stages or vegetation to those not controlled by the applicant. Upon the request of the Hearing Officer the parties agreed to enter into a joint order of stipulation and submit said order to the Hearing Officer. Said stipulation was received by the Hearing Officer on July 7, 1975, and is attached hereto and made a part hereof and marked "Supplement to Record".

Florida Laws (1) 373.146
# 9
AMERICAN ORANGE CORPORATION vs. SOUTHWEST FLORIDA REGIONAL PLANNING COUNCIL, 75-001578 (1975)
Division of Administrative Hearings, Florida Number: 75-001578 Latest Update: Oct. 29, 1990

The Issue Whether a consumptive use permit for the quantities of water as applied for should be granted.

Findings Of Fact Application No. 7500112 requested water from three (3) wells for the purpose of industrial use. This application is for a new use. The center of withdrawals will be located at Latitude 27 degrees 38' 58" North, Longitude 81 degrees 48' 21" West, in Hardee County, Florida. The application is for the use of not more than 470 million gallons of water per year and not more than 2,592,000 gallons of water during any single day to be withdrawn from the Florida Aquifer. Application received as Exhibit 1. Notice was published in a newspaper of general circulation, to-wit: The Herald Advocate, published weekly in Wauchula, Florida, on August 7 and 14, 1975, pursuant to Section 373.146, Florida Statutes. Notices of said public hearing were duly sent by certified mail as required by law. The affidavit of publication was received without objection and entered into evidence as Exhibit 2. Letters of objection were received from the following: Mr. Joseph F. Smith, Route 1, Box 238, Wauchula, Florida 33273. Mr. Smith states that in his opinion such withdrawal of water will severely damage his property. He is developing a mobile home park on eight (8) acres and is fearful that the amount of water requested in this application will diminish his supply of water for his project. A letter from Mr. and Mrs. A. H. Van Dyck, written on August 16, 1975, Route 2, Box 657, Wauchula, Florida 33873. They are fearful that the large amount of water American Orange Corporation proposes to pump each day will affect their shallow well which provides water for their home. They would like to see some type of agreement whereby American Orange Corporation would be willing to pay for replacement of the well if the corporation should cause their well to go dry. Mr. Stanley H. Beck, Counselor at Law, wrote a letter in behalf of his client, Harold Beck, requesting information as to the applicable statutes and regulations which affect the matter of the consumptive use permit. A telegram was sent by Harold Beck of Suite 1021, Rivergate Plaza, Miami 33131, stating that he objected to the application of American Orange Corporation's withdrawal of water or the reason that it would reduce the property value. The witness for the permittee is Barbara Boatwright, hydrologist, who was duly sworn and agreement was reached on each point enumerated as required by Rule 16J-2.11, Rules of the Southwest Florida Water Management District and Chapter 373, Florida Statutes. The staff hydrologist recommended that the permit be granted with two (2) conditions. One was that each of the wells be metered and two, that the District receive monthly reports from each meter. The applicant has consented.

Florida Laws (1) 373.146