Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. MARK V. ANSLEY, 88-005225 (1988)
Division of Administrative Hearings, Florida Number: 88-005225 Latest Update: Apr. 17, 1989

Findings Of Fact Mr. Ansley is the holder of license No. CB C033338 as a building contractor in the State of Florida, having been issued that license in 1985. At all times relevant hereto, Mr. Ansley was so licensed. In 1987, Fred Fox Enterprises, a private consulting firm in economic development and housing rehabilitation, worked with the Town of Baldwin to write a Community Development Block Grant to upgrade housing in targeted areas of the town. The Town of Baldwin received the grant and Fred Fox Enterprises administered the grant. As part of the grant, arrangements were made to build a new home for Michael and Karen Turner. The Turners qualified for a $25,000 grant and the Turners augmented the grant with their own funds in the amount of $2,750. Fred Fox Enterprises solicited contractors to participate in the grant activities. Mr. Ansley was one of the contractors who agreed to participate. The Turners selected a floor plan and Mr. Ansley's bid for the job was acceptable. A contract was signed on June 29, 1987. Ansley was to receive $27,750 in draws from a special escrow account in the name of the homeowner and the contractor. Ansley pulled the permits and began construction pursuant to a Notice to Proceed dated August 31, 1987. Ansley had 75 days to complete construction. Ansley did the foundation and poured the slab. He was paid his first draw of $3,750 for the slab on September 24, 1987. By early October, the exterior walls were constructed up to the lintel, however no trusses and no roof were in place. No further work was done on the house. Ansley's next draw would have been at dry-in, but the construction never reached that stage. Representatives of Fred Fox Enterprises and of the Town of Baldwin tried to contact Ansley about the work stoppage. Letters were sent to Ansley by the Town of Baldwin on September 30, October 15, and October 30, 1987, reminding Ansley that by contract he had 75 days to complete the project, that his time was running out, that liquidated damages of $50 per day were called for under the contract, and that the deadline for completion was November 14, 1987. On November 10, 1987, the Town of Baldwin wrote to Ansley advising that no work had been done since October 26, 1987, in violation of the contract, that the structure was only 20% complete in violation of the contract, that a Claim of Lien had been placed against the property by a materialman, and that any further payments would cease until the lien was satisfied. Ansley never responded to that letter. On November 27, 1987, the Town of Baldwin officially informed Ansley that his contract was terminated. The letter also reminded Ansley that he was still responsible for payment for materials, labor and/or supplies purchased for work on the Turner's house prior to termination of the contract. On December 3, 1987, another Claim of Lien was filed by Southern Atlantic Concrete in the amount of $3,386.59. The previous lien was by Holmes Lumber Company in the amount of $194.63. At various times Ansley contacted representatives of Fred Fox Enterprises and the Town of Baldwin and told them that the liens were in error or that he would take care of them in the future. Ansley acknowledged that he was having financial difficulties. Another contractor was retained to complete the house for approximately $1,000 more than the Ansley/Turner contract price. Also, the Turner's were placed in temporary housing at the cost of the Town of Baldwin and the grant. Ansley never paid the liens. Finally, to protect its reputation, Fred Fox Enterprises paid the liens out of its own funds, not from the grant money. Including interest, Fred Fox Enterprises paid $3,873,15 to cover the liens. Ansley acknowledges that he was in a financial crunch. He intended to finish the house and not to abandon it, but he was financially unable to do so. He says he had $5,500 of his own money tied up in the house, in addition to the liens. He simply did not have the funds to complete the house up to the second draw so he could use the draw funds to pay for the materials and labor.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Professional Regulation, Construction Industry Licensing Board, enter a Final Order and therein: Find Mark V. Ansley guilty of violating Sections 489.105(4) and 489.129(1)(h), (j), (k), and (m), Florida Statutes, as charged in the Administrative Complaint. Order Mark V. Ansley to pay an administrative fine of $5,000. Suspend building contractor's license No. CB-C033338 issued to Mark V. Ansley for a period of one (1) year. DONE and ENTERED this 17th day of April, 1989, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 17th day of April, 1989. COPIES FURNISHED: Mark A. Sieron Attorney at Law 1329-A Kingsley Avenue Orange Park, Florida 32073 Mark V. Ansley 7034 Luke Street Jacksonville, Florida 32210 Harper Fields General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201

Florida Laws (3) 120.57489.105489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DANIEL S. ROTHBERG, 88-003335 (1988)
Division of Administrative Hearings, Florida Number: 88-003335 Latest Update: Dec. 19, 1988

Findings Of Fact At all times material to this proceeding, the Respondent has been licensed as a residential contractor in the State of Florida, holding license number CR C022406, and was the licensed contractor qualifying Rothberg Homes, Inc. On or about May 21, 1986, the Respondent entered into a contract to build Mr. and Mrs. Frank Sargent a new home in Palm Harbor, Florida, for $95,670. The home was to be completed before November 15, 1986, so that the Sargents could qualify for a lower interest rate. The Respondent relied heavily on his construction superintendent, Frank Jackson, to accomplish the work in a timely and workmanlike manner. The Respondent was responsible primarily for selling contracts and for taking care of the company finances. To comply with the technical requirements of the contract, the Respondent had construction begin in July, 1986, with the clearing of the lot. But foundation footers were not dug and poured until about a month later, and construction proceeded at a slow pace (then it went on at all.) The Sargents registered numerous complaints to Jackson about the slow pace and some complaints to the Respondent about Jackson, but nothing was done to speed construction along. In October, 1986, the Sargents, who were on the job site daily, began hearing complaints from suppliers and subcontractors that the Respondent was slow paying them but was told that he eventually was coming through with the payments due. By November, the Respondent was not making payments at all in some cases. Also in October and November, Jackson was in the process of opening his own business (not construction-related) and was devoting less and less time to the Sargent job. November 15, 1986, approached, and it became obvious that the deadline would not be met. The Sargents and the Respondent met and agreed to extend the deadline one month to December 16. On December 11th, the Sargents again reminded the Respondent of the deadline and its importance to them, but the December 16 deadline also came and went with the house only about 70 percent complete. In December, Jackson quit altogether. The Sargents complained to the Respondent, who promised to replace Jackson but never did. Because the Respondent had stopped paying subs and suppliers, they refused to do any more work, and the Sargents wound up having to pay some of them out of their own pockets in order for work to continue. In March 1987, some of the subs and suppliers also filed claims of liens for unpaid work which the Sargents had to clear out of their own pockets in order to close the purchase of the house. Mr. Sargent himself did some of the work, some of which would have been warranty work if the Respondent had paid his bills on time, to save some additional expense caused by the Respondent's failure to keep current on his accounts with the subs and suppliers and to avoid some of the additional hassle of trying to persuade an unpaid sub or supplier to do warranty work. On March 16, 1987, the Sargents met with the Respondent to arrive at an accounting for purposes of the upcoming closing. They agreed that the Sargents should receive the last construction loan draw of about $9,500 to compensate them for payments they made that should have been made by the Respondent and that the Respondent still owed them $6,000, which the parties agreed would be the subject of a promissory note from the Respondent to the Sargents. (This does not even account for the Sargents being shortchanged when a three-foot roof overhang for which they had contracted turned out to be only a two-foot overhang.) The Respondent has paid the promissory note.

Recommendation Based on the foregoing Findings Of Fact and Conclusions Of Law, it is recommended that the Construction Industry Licensing Board enter a final order finding the Respondent, Daniel S. Rothberg, guilty of violating Section 489.129(1)(h) and (m), Florida Statutes (1987), and imposing an administrative fine in the amount of $1,500. RECOMMENDED this 19th day of December, 1988, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of December, 1988. COPIES FURNISHED: Elizabeth R. Alsobrook, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Daniel S. Rothberg 624 Charisma Drive Tarpon Springs, Florida 34689 Daniel S. Rothberg 196 Mayfair Circle Palm Harbor, Florida 34684 Warren A. Wilson, III, Esquire 2101 U.S. Highway 19 North Suite 201 Palm Harbor, Florida 33563 Fred Seely, Executive Director Department of Professional Regulation Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Bruce D. Lamb, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (1) 489.129
# 2
DEPARTMENT OF FINANCIAL SERVICES, DIVISION OF WORKERS' COMPENSATION vs GMD CARPET, INC., 04-002477 (2004)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Jul. 16, 2004 Number: 04-002477 Latest Update: Nov. 24, 2004

The Issue Whether GMD Carpet, Inc., failed to comply with coverage requirements of the workers’ compensation law, Chapter 440, Florida Statutes, and if so, what penalty should be imposed.

Findings Of Fact Petitioner is the state agency responsible for enforcing provisions of Florida law, specifically Chapter 440 of the Florida Statutes, which require that employers secure workers’ compensation coverage for their employees. Respondent, whose principal is Emmanuel Simone, Jr. (Mr. Simone), is in the business of providing carpet installation services. At all times material to this case, Respondent is an employer within the meaning of Section 440.02(16)(a), Florida Statutes. At all times material to this case, Respondent was legally obligated to provide workers' compensation insurance in accordance with the provisions of Chapter 440, Florida Statutes, for Mr. Simone and four other individuals employed by GMD. On or about May 21, 2004, Petitioner became aware that Mr. Simone and another GMD employee were working a carpet installation job in Broward County, Florida. Upon inquiry, Petitioner accurately determined that GMD had not furnished the required coverage, and that there was no valid exemption from the coverage requirement. Accordingly, on May 21, 2004, a Stop Work and Penalty Assessment Order was properly entered. Thereafter, Petitioner reviewed Respondent's payroll records, which revealed that GMD employed three other individuals under circumstances which obliged Respondent to provide workers’ compensation for these employees. Based upon Respondent's payroll records, Petitioner recalculated the penalty assessment to be imposed in accordance with the requirements of Chapter 440, and issued an Amended Order in the amount of $1,916.65 on May 25, 2004. Respondent did not intend to violate the law. Rather, he mistakenly believed that he held a valid exemption; that his wife was not an employee, but rather a helper; and that the three other carpet installers were subcontractors to whom he had no insurance-related obligations. It is undisputed that Petitioner correctly calculated the penalty prescribed by law in the amount of $1,916.65 based upon Respondent's records and applicable law.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Petitioner enter a final order confirming the Stop Work Order and imposing a penalty in the amount of $1,916.65, as set forth in the Amended Order. DONE AND ENTERED this 15th day of October, 2004, in Tallahassee, Leon County, Florida. S FLORENCE SNYDER RIVAS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 15th day of October, 2004. COPIES FURNISHED: Colin M. Roopnarine, Esquire Department of Financial Services Division of Workers’ Compensation 200 East Gaines Street Tallahassee, Florida 32399-4229 Emmanuel Simone, Jr. Debra Simone GMD Carpet, Inc. 717 North 31st Avenue Hollywood, Florida 33021 Honorable Tom Gallagher Chief Financial Officer Department of Financial Services The Capitol, Plaza Level 11 Tallahassee, Florid a 32399-0300 Pete Dunbar, General Counsel Department of Financial Services The Capitol, Plaza Level 11 Tallahassee, Florida 32399-0300

Florida Laws (7) 120.569120.57440.02440.10440.13440.16440.38
# 3
DEPARTMENT OF FINANCIAL SERVICES, DIVISION OF WORKERS' COMPENSATION vs A TO Z ROOFING, INC., 14-002830 (2014)
Division of Administrative Hearings, Florida Filed:Tamarac, Florida Jun. 18, 2014 Number: 14-002830 Latest Update: May 21, 2015

The Issue The issue in this case is whether Respondent violated the provisions of chapter 440, Florida Statutes,1/ by failing to secure the payment of workers’ compensation, as alleged in the Stop-Work Order and Third Amended Order of Penalty Assessment, and if so, what is the appropriate penalty.

Findings Of Fact The Department is the state agency responsible for enforcing the statutory requirement that employers secure workers’ compensation coverage for the benefit of their employees. Respondent is a Florida, for-profit corporation with its principal office located at 3539 Apalachee Parkway, Suite 3-204, Tallahassee, Florida 32311. Respondent was incorporated on October 26, 2012, and has been engaged in the construction industry in Florida as a roofing company since October 31, 2012. From Respondent’s inception, Richard Paul Morejon has been Respondent’s president, secretary, and treasurer, and has received compensation from Respondent’s roofing contract proceeds. In July or August 2013, the Department received a complaint alleging that Respondent was not in compliance with Florida's Workers' Compensation Law. The Department assigned investigation of the complaint to then-Department investigator Carey Horn. Based upon materials apparently gathered and reports purportedly authored by Investigator Horn, the Department issued a stop-work order dated September 23, 2013, to Respondent alleging that Respondent did not secure workers’ compensation coverage for its employees as required. The Department, however, did not call Investigator Horn as a witness, and, despite Mr. Morejon’s attempt to subpoena her to testify in this case, Investigator Horn could not be found. The Department’s delay in referring this case for a final hearing either caused or contributed to Investigator Horn’s unavailability as a witness in this proceeding. The reports and conclusions of Investigator Horn were prepared in anticipation of litigation and are hearsay.2/ Therefore, they have not been used to support factual findings in this Recommended Order unless corroborative of non-hearsay evidence.3/ In addition, on October 20, 2014, the Department filed a document entitled "Joint Prehearing Stipulation" signed by the Department’s counsel and Mr. Morejon purporting to contain a number of stipulated facts and factual admissions by Mr. Morejon on behalf of Respondent. However, at the final hearing, the manner in which the Joint Prehearing Stipulation was procured was brought into question when Mr. Morejon advised that he was told to sign it and that the stipulation would be “ironed out” at the final hearing. The Department’s counsel confirmed that the conversation occurred regarding the correct classification code to be utilized in calculating the penalty against Respondent. Accordingly, it was ruled at the final hearing that the Joint Stipulation would not be used to support a finding regarding the classification. Upon further consideration of Mr. Morejon’s comments and the Department’s counsel’s admission as to the manner in which at least one of the stipulated facts was secured, the undersigned has not utilized and otherwise rejects as untrustworthy the document entitled "Joint Prehearing Stipulation" filed in this case on October 20, 2014, finding that it does not represent any bona fide stipulations or admissions. Nevertheless, in his testimony during his deposition and at the final hearing in this case, Mr. Morejon admitted a number of factual matters demonstrating that Respondent was not in compliance with Florida’s Workers’ Compensation Law on September 23, 2013. The factual findings in this Recommended Order are derived from Mr. Morejon’s testimony, non-hearsay evidence, and corroborative hearsay submitted during the final hearing. On September 23, 2013, Investigator Horn visited a jobsite at a residence located at 5747 Sioux Drive, Tallahassee, Florida (Jobsite), where Respondent, through employees, was performing roofing and related activities. On that date, Mr. Morejon was on the ground supervising two men on the roof engaged in roofing activities and two men on the ground picking up debris, for a total of five men, including Mr. Morejon, at the Jobsite working for Respondent. There was another man sitting in a vehicle at the Jobsite that day who never did any work for Respondent. There is no evidence that Respondent provided workers’ compensation coverage for any of the men working at the Jobsite that day. The two men working on the roof were Guadalupe Perez- Martinez and Hermilo Perez-Martinez. At the time, Guadalupe Perez-Martinez had an exemption from the requirements for workers’ compensation through his company, Lupe Builders, LLC. Although Hermilo Perez-Martinez previously had an exemption from the requirements of workers’ compensation through Perez Builders, LLC, that exemption expired the previous month, on August 3, 2013. There is no evidence that the two men picking up debris, Hermilo Pantaleon Paz and Timotio Aguilar, qualified for an exemption from workers’ compensation coverage that day. Although Mr. Morejon had an exemption from the requirements of Florida's Workers' Compensation Law for a separate and unaffiliated company, Comerxio, Mr. Morejon did not have an exemption from the coverage requirements of Florida's Workers' Compensation Law for Respondent on September 23, 2013, or during the relative time periods of this case. According to Mr. Morejon, other than Guadalupe Perez- Martinez, none of the other workers at the Jobsite that day had ever performed work for Respondent. Mr. Morejon also recalled that another person on the Jobsite that day, David Amaro- Rodriguez, just sat in a car and performed no work. Mr. Morejon’s recollections are unrefuted. The Department’s delay in referring this case undoubtedly affected the ability of either party to call other witnesses, including a number of the workers or the investigator, who were at the Jobsite that day. During the relevant time periods, Respondent did not maintain a bank account to pay its employees and it did not directly pay Mr. Morejon or other employees. Rather, historically, proceeds from roofing contracts performed by Respondent were deposited into a bank account held by another corporation named "A 2 Z Roofing, Inc." After paying various expenses, including permit fees, materials, and other costs associated with the roofing contracts, A 2 Z Roofing, Inc., paid Mr. Morejon, and any others performing work under the contracts, by check. On September 23, 2013, the Department personally served the Respondent with a stop work order (Stop Work Order) and a request for production of business records for penalty assessment calculation (Records Request). The Records Request requested Respondent’s corporate records, licenses, payroll documents, account documents, disbursements, contracts for work, employee leasing information, subcontractors, and workers' compensation coverage or exemptions "for the period from 10/31/2012 through 09/23/2013 [the Non- Compliance Period]." The Records Request further stated, in part: The employer should scan and email the records requested herein to the investigator with the Department of Financial Services, Division of Workers’ Compensation for examination within 5 business days after receipt of this Request for Production of Business Records. If the employer fails to provide the required business records sufficient to enable the Department of Financial Services, Division of Workers’ Compensation to determine the employer’s payroll for the period requested for the calculation of the penalty provided in section 440.107(7)(d), F.S., the imputed weekly payroll for each employee, corporate officer, sole proprietor, or partner shall be the statewide average weekly wage as defined in section 440.12(2), F.S. multiplied by 1.5. The Department shall impute the employer’s payroll at any time after ten, but before the expiration of twenty business days after receipt by the employer of a written request to produce such business records. (FAC 69L-6.028) If the employer is unable to scan and email these documents, please mail or deliver copies to our office located at 200 East Gaines Street Tallahassee, FL, 32399-4228. The next day, September 24, 2013, Mr. Morejon hand delivered Respondent’s business records to the Department in response to the Records Request. The business records delivered by Mr. Morejon included roofing permit applications; roofing permits issued to A to Z Roofing, Inc.; several contracts between homeowners and A to Z Roofing, Inc., identifying Mr. Morejon as project manager; five checks from A 2 Z Roofing, Inc. (not Respondent), payable to the City of Tallahassee; and 24 checks from A 2 Z Roofing, Inc., payable to "Mr. Morejon – Petty Cash." The 24 checks from A 2 Z Roofing, Inc., to Mr. Morejon totaled $55,955.4/ The checks, dated from November 17, 2012, to August 23, 2013, constitute all of the money paid to Mr. Morejon from Respondent’s roofing contract proceeds during the Non- Compliance Period. In addition to the 24 checks payable to Mr. Morejon, it is evident that the Department also received other checks from A 2 Z Roofing, Inc., from the records requests made in this case and in DOAH Case No. 14-2829, made payable to Lupe Builders, LLC, Gene Pfund, and perhaps others, during the Non- Compliance Period. The Department, however, did not utilize those records in its determinations in this case. In fact, the Department’s penalty auditor did not utilize payments made by A 2 Z Roofing, Inc., in calculating the penalty because, in the Department’s penalty auditor’s opinion, Respondent was not compliant because it did not have a bank account. Final Hearing Transcript, pp. 232-233. The determination of payroll, however, is not dependent on whether an employer has a bank account or whether the employer is the entity that pays its employees. Rather, the Department’s own rule defining payroll considers "[p]ayments, including cash payments, made to employees by or on behalf of the employer" in determining payroll. See Fla. Admin. Code Rule 69L-6.035(1)(b)(emphasis added). During the hearing, the Department, through counsel, stated that the payments from A 2 Z Roofing to Lupe Builders, LLC, or Gene Pfund were not considered because those entities had valid exemptions from the requirements of workers’ compensation. In addition, the Department complained that their receipt of bank records from A 2 Z Roofing, Inc., had been delayed and took the position that bank records from A 2 Z Roofing, Inc., would not be utilized in this case. The Department’s own discovery tactics, however, were responsible for delays in responses to its requests for records from A 2 Z Roofing, Inc.5/ Considering the records produced by Respondent introduced into evidence in this case, the testimony of Mr. Morejon regarding the checks payable to him from A 2 Z Roofing, Inc., the Department’s unwillingness to utilize other records from A 2 Z Roofing, Inc., in its possession, and evidence of the total payments to Mr. Morejon during the Non- Compliance Period, it is found that the Department’s decision to impute payroll is unfounded. Imputation of payroll would improperly allow the Department to benefit from its own lack of analysis. The imputed payroll determined by the Department in the amount of $347,334.69 exceeds Respondent’s total revenue for the Non- Compliance Period by more than $100,0006/ and is based, at least in part, upon hearsay evidence prepared by a witness whose unavailability was likely caused by the Department’s undue delay in referring Respondent’s Request for Hearing. Furthermore, the records produced by Respondent and the evidence in this case are sufficient to determine Respondent's payroll for use in the calculation of a penalty pursuant to section 440.107(7)(d)l. The evidence demonstrated that the $55,955 reflected in checks payable to Mr. Morejon from A 2 Z Roofing, Inc., represent all of the payments to Respondent’s employees who were not covered by workers’ compensation while performing services for roofing contracts during the Non-Compliance Period, other than payments reflected in records the Department may have in its possession but did not present at the final hearing. It was also shown, however, that the $55,955 was paid to Mr. Morejon without the maintenance of a cash log or cash journal and without securing the payment of workers' compensation coverage for Mr. Morejon or others receiving cash payments from those funds. And, there is no evidence that any of those employees were exempt from the requirements of workers’ compensation. Respondent was required to secure workers' compensation coverage and failed to secure that coverage under Florida’s Workers’ Compensation Law for its employees who were paid $55,955.00 during the Non-Compliance Period. Therefore, the Department was justified in issuing the Stop Work Order delivered to Mr. Morejon on September 23, 2013. Although the Department failed to show that Respondent’s payroll should be imputed, the evidence adduced at the final hearing demonstrated that a penalty should be imposed against Respondent for failure to pay workers’ compensation for its employees who were paid a total of $55,955 during the Non- Compliance Period. For determining the appropriate penalty, the Department has adopted a penalty calculation worksheet to aid in calculating penalties against employers pursuant to section 440.107, Florida Statutes. See Florida Administrative Code Rule 69L-6.027. The classification codes listed in the National Council on Compensation Insurance ("NCCI") Scopes® Manual have been adopted by the Department through Florida Administrative Code Rules 69L-6.021 and 69L-6.031. Classification codes are four-digit codes assigned to occupations by NCCI to assist in the calculation of workers' compensation insurance premiums. Under the descriptions listed in the NCCI Scopes® Manual, the proper classification code for Respondent’s employees is 5551, which corresponds to "Roofing - All Kinds and Drivers." The Department has adopted the approved manual rates in the Florida Administrative Code, as authorized by section 440.107(7). Rule 69L-6.027 adopts form number DFS-F4-1595, the Penalty Calculation Worksheet, which specifically incorporates approved manual rates. As accurately set forth in the Penalty Calculation Worksheets attached to the Amended Order of Penalty Assessment, the approved manual rates for the following periods of Non- Compliance were: From 10/31/2012 to 12/31/2012 the rate was 17.10; From 01/01/2013 to 06/30/2013 the rate was 18.17; From 07/01/2013 to 09/23/2013 the rate was 18.03. A breakdown of Respondent’s total payroll of $55,955 based upon check dates corresponding to the manual rates in effect during the Non-Compliance Period, is as follows: From 10/31/2012 to 12/31/2012 payroll totaled $6,300; From 01/01/2013 to 06/30/2013 payroll totaled $33,655; From 07/01/2013 to 09/23/2013 payroll totaled $16,000. Calculation of the penalty, using the Penalty Calculation Worksheet and Respondent’s payroll based on records (as opposed to imputed) during the Non-Compliance Period, results in a total penalty of $15,116.12, as follows: Calculation Method (a) Class Code (b) Non-Compliance period (c) Gross Payroll (d) /100 (e) Approved Rates (f) Premium (d)X(e) (g) Penalty (f)X 1.5 Records 5551 10/31/12 12/31/12 6,300 63 17.10 1,077.30 1,616.25 Records 5551 01/01/13 06/30/13 33,655 336.55 18.17 6,115.11 9,172.67 Records 5551 07/01/13 09/23/13 16,000 160 18.03 2,884.80 4,327.20 Totals: $55,955.00 $15,116.12 The clear and convincing evidence in this proceeding demonstrated that Respondent was in violation of Florida’s Workers’ Compensation law because it employed one or more uninsured employees in the construction industry throughout the Non-Compliance Penalty, and that the appropriate penalty, based upon Respondent’s payroll, is in the amount of $15,116.12.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department enter a Final Order consistent with this Recommended Order upholding the Stop Work Order, and reducing the penalty set forth in the Amended Order of Penalty Assessment to $15,116.12 by recalculating the penalty based upon Respondent’s payroll of $55,955.00 during the Non-Compliance Period. DONE AND ENTERED this 5th day of February, 2015, in Tallahassee, Leon County, Florida. S JAMES H. PETERSON, III Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 5th day of February, 2015.

Florida Laws (8) 115.11120.56917.10440.02440.10440.107440.1290.801
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs AGNES SANGSTER, 93-006438 (1993)
Division of Administrative Hearings, Florida Filed:Miami, Florida Nov. 03, 1993 Number: 93-006438 Latest Update: May 29, 1996

The Issue The issue in this case is whether disciplinary action should be taken against Respondent's contractor's license based upon the alleged violations of Sections 489.129(1)(h) and (m), Florida Statutes, set forth in the Administrative Complaint.

Findings Of Fact Based upon the oral and documentary evidence adduced at the hearing and the entire record in this proceeding, the following findings of fact are made. At all times pertinent to this proceeding, Respondent was licensed by the Construction Industry Licensing Board (the "Board") as a certified general contractor having been issued License No. CG C024612. Respondent has been a licensed contractor since 1983. On May 3, 1991, the Board filed a Final Order in Board Case Nos. 89-009986 and 89-013330 imposing a reprimand against Respondent. The Final Order was issued as part of the settlement of an amended administrative complaint filed against Respondent by Petitioner regarding certain unrelated transactions. Respondent was the qualifying agent for Willie William Construction Company, Inc. until October 1985. At that time, as a result of a corporate name change, Respondent became the qualified agent for Ashar Construction Company. On February 21, 1985, the Unsafe Structures Board of the Building and Zoning Department for Dade County advised Ruby Delancy that a hearing would be conducted on March 12, 1985 to determine whether a one story framed residence that Mrs. Delancy owned at 1005 NW 58th Street in Miami (the "House" or the "Property") should be demolished. The Notice indicated that the structure was "open, vacant, vandalized, filled with combustible materials; posing a serious fire hazard. Structure is a danger to human life and public welfare." The Notice estimated the present value of the building at $16,080 and the estimated cost of repairs at $51,120. The County's records indicate that a Notice of Violation regarding the Property had been issued to the owner on October 31, 1984. Facing imminent demolition of the House, Mrs. Delancy began to investigate possible ways to get the House repaired. She filed an application with the City of Miami for a low income, low interest loan that was funded through Federal HUD Community Development Funds. Her efforts to obtain funding to repair the House, delayed the proceedings that had been initiated to demolish the structure. In September of 1985, the City approved Mrs. Delancy for a grant of $10,000 and loan of $20,000 to repair the House. Mrs. Delancy has no other funds to pay for repairs to the Property other than the $30,000 she was obtaining through the City Program. Under the City's program, Mrs. Delancy was responsible for selecting a contractor. Mrs. Delancy contacted Respondent, who inspected the Property and prepared a construction estimate which was submitted to the City. Respondent entered into a contract (the "Contract") dated September 20, 1985 with Mrs. Delancy for home improvement work on the House. The total contract price was $29,870, which was to be paid in two installments: $10,835 on or before December 31, 1985 and a final payment of $19,035 on or before March 3, 1986. The evidence established that Respondent was initially reluctant to enter into the Contract and at least two other contractors refused to undertake the work given the limited funds available. However, Respondent agreed to take the job because of Mrs. Delancy's insistence and because of Respondent's sympathy for Mrs. Delancy's desperate situation in view of the imminent demolition of the House. The evidence also established that Mrs. Delancy requested Respondent to undertake additional work and/or services that were beyond the scope of the Contract. Among the extra items undertaken by Respondent was replacement of the floor in the family room. Additional expenses were also incurred because of unanticipated problems encountered during the renovation. For example one side of the house gave way during the renovation work. Upon investigation, it was discovered that there was no footing. Respondent was required to shore up that side of the House. In addition, the electrician was unable to get a meter because there was an outstanding electric bill for the Property. Respondent paid the old bill in order to get the meter connected. Similarly, she paid the gas company to get the stove hooked up. It does not appear Respondent received any additional compensation for the extra work. Except for $345 that Respondent paid for utilities on behalf of Mrs. Delancy, the evidence at the hearing was insufficient to place a dollar value on these extra services and expenses. The first installment under the Contract of $10,835 was paid to Respondent on or about December 31, 1985. In approximately January of 1986, Mrs. Delancy's son, Gerald Delancy, who had been living out of the state, returned to Miami and became involved in overseeing the construction on behalf of his mother. Gerald Delancy was not pleased with the quality of the construction and a great deal of tension developed between Gerald Delancy and Respondent. The final payment request form was submitted on February 20, 1986. Mrs. Delancy signed a document (the "Certificate of Completeness") indicating that the work was completed and the final payment was made to Respondent by the City on March 3, 1986. Gerald Delancy was present when his mother signed the Certificate of Completeness. She signed this Certificate against the advice of her son. At the time the document was signed, Respondent agreed in principal to complete any remaining work. The City Inspection Form which was posted on the project fails to indicate that a final inspection approval was obtained from the City. In addition, the evidence established that required roof inspections were not obtained prior to the final structural inspection. Gerald Delancy prepared a punch list of items which he felt were incomplete and submitted it to Respondent. It does not appear that this list was prepared until July of 1986. Because of the dispute between Respondent and Gerald Delancy as to what was required under the Contract, a copy of the punch list was also sent to the City. The punch list prepared by Gerald Delancy included a number of items which were beyond the scope of the Contract. For example, with respect to the plumbing, the complaints included the following: the water pressure was to low on the water line, the kitchen sink was too small, and the bathroom vanity was substandard. The Contract did not provide for a bathroom vanity. There were also complaints about ants and roaches and "missing shower rods and towel racks" even though these items were not specifically included within the Contract between Respondent and Mrs. Delancy. The City sent its estimator to the House to review the punch list items. The City's estimator felt that Respondent should provide another coat of paint and should complete some other minor repair work, but the estimator did not concur in many of Gerald Delancy's complaints. The City's rehabilitation estimator met with Respondent and Gerald Delancy at the House on July 15, 1986. At that meeting, Respondent agreed to correct certain matters and asked for one month to complete the work. On August 1, 1986, the work was not completed and Respondent requested an additional 30 days. On August 13, 1986, Respondent stated that she did not have the money to complete the work. According to the City's estimator, the cost to repair the construction deficiencies he noted would be approximately $2,500 to $3,000 as of the date of the hearing. During this period in August, Respondent did send some workers back to the house to complete some additional work. A dispute arose between those workers and Gerald Delancy. The exact nature and reasons for this dispute are not clear. Ultimately, Gerald Delancy refused to allow the workers to perform any work because he did not feel he received adequate answers to his inquiries as to the nature of the work they intended to perform. After the City refused to concur in all of his complaints, Gerald Delancy hired a building inspection company. He paid that company $534 and it rendered a report dated August 4, 1986 which detailed many other deficiencies in the construction. It is not clear whether this report was ever presented to Respondent. On or about November 3, 1986, Mrs. Delancy, at the urging of her son, filed a lawsuit against Respondent. On or about August 8, 1989, Mrs. Delancy obtained a final default judgement against Respondent in the amount of $65,000 plus costs of $102.50. Respondent claims that she was unaware of the lawsuit and the default final judgement until Petitioner's investigator questioned her about it on September 25, 1990. As of the date of the hearing in this case, Respondent has not appealed the judgement nor has she attempted to have it set aside or vacated. In addition to alleged construction defects, the default judgement included claims against Respondent for allegedly mishandling certain household goods and other property owned by Mrs. Delancy. The evidence presented in this case was confusing and inconclusive as to the nature and justification for these claims by the Delancys for property which Respondent was allegedly storing for Mrs. Delancy. Apparently, Respondent agreed to assist Mrs. Delancy by moving some of the furniture out of the house and placing it in storage during construction. The contract did not require Respondent to provide any moving or storage services and there is no evidence that Respondent was paid for this work. Some or all of the property that was moved out of the house was lost, stolen or destroyed. There is a dispute between the parties as to circumstances surrounding the loss of this property. The evidence presented in this case was insufficient to establish what happened to the property, who was responsible for it and/or how much it was worth. It does appear that the default judgement against Respondent includes a very high assessment for the property involved. However, as noted above, that judgement has not been vacated or appealed.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered dismissing Count I of the Administrative Complaint, finding the Respondent guilty of having violated Section 489.129(1)(m), Florida Statutes, as alleged in Count II of the Administrative Complaint, and imposing the following disciplinary action against the Respondent: Imposition of an administrative fine of $1,000. Suspension of the Respondent's license for a period of one year, followed by two years probation under such terms as may be imposed by the Board. DONE and ENTERED this 22nd day of August, 1994, at Tallahassee, Florida. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of August, 1994. APPENDIX TO RECOMMENDED ORDER DOAH CASE NO. 93-6438 Only Petitioner submitted a proposed recommended order. The following rulings are made with respect to the proposed findings of fact submitted by Petitioner. The Petitioner's Proposed Findings of Fact Adopted in substance in Findings of Fact 1. Adopted in substance in Findings of Fact 2. Adopted in substance in Findings of Fact 7 and 8. Adopted in substance in Findings of Fact 4, 11, and 12. Adopted in substance in Findings of Fact 3 through 9. Adopted in substance in Findings of Fact 10. Subordinate to Findings of Fact 14 through 18. Subordinate to Findings of Fact 18. Subordinate to Findings of Fact 16 through 18. Subordinate to Findings of Fact 17. Adopted in substance in Findings of Fact 20. Subordinate to Findings of Fact 20. Adopted in substance in Findings of Fact 20. Adopted in substance in Findings of Fact 20. Rejected as unnecessary. Adopted in substance in Findings of Fact 21 and 22. Subordinate to Findings of Fact 21. Subordinate to Findings of Fact 22. Subordinate to Findings of Fact 21 and 22. Subordinate to Findings of Fact 21 and 22. Adopted in substance in Findings of Fact 1. COPIES FURNISHED: Theodore R. Gay, Esquire Dept. of Bus. and Prof. Reg. 401 NW 2nd Ave., Ste N-607 Miami, FL 33128 Agnes Sangster 9925 NW 25th Ave. Miami, FL 33147 Jack McRay Acting General Counsel Dept. of Bus. and Prof. Reg. 1940 N. Monroe St. Tallahassee, FL 32399-0792 Richard Hickok, Exec. Dir. Construction Industry Licensing 7960 Arlington Expressway, Ste 300 Jacksonville, FL 32211-7467

Florida Laws (4) 120.5717.00117.002489.129
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. MARK O. HOLLAND, 88-002489 (1988)
Division of Administrative Hearings, Florida Number: 88-002489 Latest Update: Nov. 09, 1988

Findings Of Fact Respondent, Mark O. Holland, is a licensed registered building contractor holding license number RB 0039443. Respondent was licensed at all times material to this action. Sometime around June 19, 1986, Respondent entered into a contract with Mrs. Mary Sue Thames. Ms. Thames resided in Tennessee. The contract covered Ms. Thames' partially burned out home located at 528 Dement Circle, Panama City, Florida. Respondent was to rebuild the damaged portions of the home and to build an addition onto the home. The contract improvements were to be completed within sixty days of the contract date. The contract contemplated installment payments by Mrs. Thames, by September 5, 1986, she had paid $15,000.00 of the total contract price of $17,300.00 to Respondent. The remaining $2,300.00 was to be paid upon completion of the job. Mrs. Thames became concerned that the job was not progressing in a reasonably timely manner in September 1986 when she visited the job site from Tennessee. She observed that "nothing was done" even though the sixty day contract period had expired. Suppliers were removing items from the job that Respondent had not paid for under the contract. Mrs. Thames throughout the job had telephoned the Respondent weekly to check on the progress. Respondent would assure Mrs. Thames that he would "get right on it" and finish the job. Due to Respondent's assurances, Mrs. Thames elected to stay with Respondent so that he could complete the contract. Respondent never substantially performed the job although he did perform part of the contract. Between September 1986 and January 1987, Mrs. Thames in an effort to get the job finished, paid for supplies and materials that Respondent was contractually obligated to purchase. She paid for sheet rock, vinyl, carpet and doors. Respondent had told Mrs. Thames that he had no money to finish the job and that if she would purchase those materials he could finish the job. Mrs. Thames knew the contract obligated the Respondent to furnish the materials she purchased but was trying to work with the Respondent. The effort did not pay off. Respondent had in effect abandoned the job. As stated earlier, Respondent did not complete Mrs. Thames' job. In March 1987, Mrs. Thames' family assisted her in obtaining other subcontractors and suppliers to complete the job. She incurred costs of $8,000.00 to these subcontractors and suppliers, an amount less than the amount already paid to Respondent. Mrs. Thames testified that at least two subcontractors have not been paid by the Respondent those being Stephens Heating and Air Conditioning and M.D. Stewart Plumbing Company. Mr. Lester Stephens, owner of Stephens Heating and Air Conditioning subcontracted with the Respondent. Stephens' company roughed in the central ducts system valued at $700.00 on September 1, 1986 and as of September 27, 1988, had not been paid by Respondent. Coastal Insulation of Northwest Florida, Inc. filed a lien against Mrs. Thames' property as a result of Respondent not paying for supplies. The lien was apparently discharged by Respondent. Mr. Richard Dodson confirmed the testimony of Mrs. Thames. Mr. Dodson added that in addition to the $8,000.00 Mrs. Thames paid to complete the job, she also incurred hotel and travel bills. She also lost approximately 1 - 1/2 years worth of rental income on the house because of Respondent's misconduct and abandonment of the job. Respondent was disciplined by the Panama City Beach Board of Examiners on September 10, 1987 for misconduct and violations of the Building Regulations and Ordinances of the City of Panama City Beach during the Thames job. Respondent's competency card was revoked by the Board. Respondent has never refunded any of the contract price to Mrs. Thames.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That an administrative fine in the amount of $1,000.00 be levied against Respondent. DONE and ENTERED this 9th day of November, 1988, in Tallahassee, Florida. DIANE CLEAVINGER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of November, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 88-2489 The facts contained in paragraphs 1, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12 and 13 of Petitioner's Proposed Findings of Fact are adopted in substance, in so far as material. The facts contained in paragraph 2 of Petitioner's Proposed Findings of Fact are subordinate. COPIES FURNISHED: Elizabeth R. Alsobrook, Esquire Tectonics Section Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Mark O. Holland Route A, Box 366 Youngstown, Florida 32466 Fred Seely Executive Director Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32201 Lawrence A. Gonzalez, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Bruce D. Lamb, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (2) 120.57489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer