CONSTRUCTION INDUSTRY LICENSING BOARD vs. CHARLES A. WUNDER, 82-000721 (1982)
Division of Administrative Hearings, Florida Number: 82-000721 Latest Update: Jun. 07, 1983

Findings Of Fact Respondent is a certified general contractor holding license number CG C005645. His last known address was Raemel Construction & Engineering, Inc., 950 County Club Boulevard, Cape Coral, Florida 33904 (Prehearing Stipulation). I. Although respondent has engaged in contracting under the name of Raemel Construction & Engineering, Inc., since May 27, 1980, he did not qualify this company with the Construction Industry Licensing Board until December 4, 1980. (Prehearing Stipulation; Testimony of respondent.) This was not, however, an intentional violation of the Construction Industry Licensing Law. It wasn't until December, 1980--after consulting with his new attorney--that respondent discovered that his former attorney had not filed the necessary papers to qualify his newly renamed company with the Construction Industry Licensing Board. Upon discovering this omission, he promptly qualified the company with the Board. (Testimony of respondent.) II. In May, 1980, respondent entered an agreement with Bozidar and Rene Devic to build a commercial building to be known as Atrium Plaza on Lots 1-8, Block 359, Cape Coral, Florida. The construction price was $145,000. (R-1.) Thereafter, respondent, together with his on-site building superintendent, carried out the duties of a general contractor. He supervised the construction of the building, helped obtain the construction loan, received the construction loan proceeds, and, in turn, paid the subcontractors. He, together with Mr. Devic, selected the masonry, plumbing, roofing and electrical subcontractors. He pulled the building permit, checked with his on-site building superintendent daily, and inspected the project at least twice a week. He arranged for all building inspections. Indeed, there is no evidence that the respondent acted other than as a competent and responsible general contractor. (Testimony of respondent, Wunder, Cosser.) Herbert J. Werner, Director of the Building and Zoning Department of the City of Cape Coral, submitted a sworn statement on respondent's behalf, a statement which is singular in its praise of respondent's performance as a contractor: It has been my extreme pleasure to have known and dealt with Charles A. Wunder, Sr., during most of the above mentioned [6] years. He has always conducted himself in a most professional manner and I cannot recall a single complaint against him in all that time. Were I to have my choice of people to conduct business with, out of the 2200 contractors within our city, my first choice would be Mr. Charles A. Wunder, Sr. (R-4.)

Recommendation Based on the foregoing, it is RECOMMENDED: That respondent receive a reprimand for violating Sections 489.129(1)(j) and 489.119(2), Florida Statutes (1981). DONE and RECOMMENDED this 21st day of March, 1983, in Tallahassee, Leon County, Florida. R. L. CALEEN, JR. Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of March, 1983.

Florida Laws (3) 120.57489.119489.129
# 2
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs ANTONIO L. REQUEJO, 15-007339PL (2015)
Division of Administrative Hearings, Florida Filed:Lighthouse Point, Florida Dec. 28, 2015 Number: 15-007339PL Latest Update: Dec. 01, 2016

The Issue Whether Respondent performed an act which assisted an entity in engaging in the prohibited uncertified and unregistered practice of contracting or whether he abandoned a construction project in which he was engaged or under contract as a contractor, in violation of section 489.129(1), Florida Statutes, as set forth in the Administrative Complaint, and, if so, what is the appropriate sanction.

Findings Of Fact The Board is the state agency charged with regulating the practice of construction contracting pursuant to section 20.165 and chapters 455 and 489, Florida Statutes. At all times material to this proceeding, Mr. Requejo was licensed as a certified general contractor in the state of Florida, having been issued license number CGC 1504266. Mr. Requejo’s address of record is 15941 Southwest 53rd Court, Southwest Ranches, Florida 33331. At all times material to this proceeding, Mr. Requejo was the primary qualifying agent of Recol, Inc. Mr. Andre Chestnut was formerly a registered contractor in the state of Florida. He testified credibly that he used to have nine licenses. At all times relevant to this case, he held no state licensure as a contractor. Consistent with Department records, he testified that his license had been revoked sometime around August 2003. USA Screens was incorporated in December 2011 to perform “any and all lawful business,” with Mr. Chestnut as the incorporator, registered agent, and president. Records of the Department contain no evidence that USA Screens, Inc., has ever been qualified by a licensed contractor or had an active license as a construction business. Ms. Carmen Goehrig owned real property at 6300 Pinehurst Circle East in Tamarac, Florida. She wished to install a screen enclosure on the property. On January 21, 2012, she entered into a construction contract with USA Screens, Inc., signed by Mr. Chestnut. This constituted the practice of contracting by Mr. Chestnut and USA Screens, Inc. Mr. Chestnut testified that he had been working in conjunction with Mr. Requejo on various projects for the past nine years. He credibly testified that he received the template for the contract he entered into with Ms. Goehrig from Mr. Requejo. That contract template contains the full name and address for both Recol, Inc., and USA Screens, Inc., at the top of the contract in large type, but shows only one contractor’s license number, that of Mr. Requejo, under the address for Recol, Inc. No contractor’s license number is shown under the USA Screens, Inc., address. Having worked with Mr. Chestnut for nine years, and having prepared the template contract that they used for common projects, Mr. Requejo had reasonable grounds to know that USA Screens, Inc., was uncertified and unregistered, as suggested by the contract itself. The contract mentioned that it was contingent upon both homeowner association and government approvals, and included a handwritten provision that there would be “no material purchases until association approval.” Ms. Goehrig signed two checks to USA Screens, Inc.: the first in the amount of $500.00 for the application; the other in the amount of $3,000.00 for materials. Both checks were cashed on January 24, 2012. On February 14, 2012, Mr. Requejo, d/b/a Recol, Inc., timely filed building permit application 12-636 for construction of the screen enclosure at 6300 Pinehurst Circle East with the city of Tamarac, using his general contractor’s license number. Recol, Inc., is listed as the general contractor in the city’s records. In filing for a permit from the city of Tamarac for the construction, Mr. Requejo assisted USA Screens, Inc., and Mr. Chestnut in engaging in the prohibited uncertified and unregistered practice of contracting. Mr. Claudio Grande is the chief building official for the city of Tamarac. He oversees permitting and is the custodian of records. He testified that permit 12-636 was denied due to zoning restrictions and structural issues. Mr. Chestnut testified that he made numerous calls trying to get the permit approved. He testified that the problem was that the screen enclosure encroached on a utility easement. As Mr. Goehrig testified: They applied for the permit. He showed us the drawings, Andre, and to my knowledge, submitted the permit application. And then we noticed that the second check was cashed, so we started calling him about that. And all he would say is, “Don’t worry, don’t worry, don’t worry.” And then the permit was denied and then we went back and tried to do something to get it approved and it was denied. And then zoning finally denied it again. So three times, we tried to fix it to make it work. And we finally, you know, the zoning department finally came down and said, “No, end of story, no good.” So we went to him and said, “Okay, we can’t get the permit, please just give us our money back and we’ll go on our way.” And of course, his answer was, “No, you’re not getting any money back, I spent your money, goodbye.” After the permit was finally denied and Mr. Chestnut refused to return their money, the Goehrigs contacted Mr. Requejo to get their money back, again to no avail. It was not shown that the project was terminated without just cause or that it was terminated without proper notification to Ms. Goehrig. It is clear from the filed complaint, as well as the testimony that Ms. Goehrig was aware that the project could not be permitted, and sought a return of the money that had been paid. “The permit was denied and [Chestnut] refuses to refund our deposit.” The Department failed to prove that Mr. Requejo abandoned a construction project in which he was engaged or under contract as a contractor. Prior Discipline On February 13, 2013, a Final Order Adopting Settlement and Vacating Prior Orders was filed by the Board. The Order incorporated a settlement agreement imposing discipline for allegations in several earlier Administrative Complaints. The October 2012 settlement agreement required the payment of fines, investigatory costs, and restitution to six individuals, as well as continuing education and a six-year period of probation. The Order constitutes prior discipline within the meaning of the disciplinary guidelines.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Construction Industry Licensing Board enter a final order finding Mr. Antonio L. Requejo in violation of section 489.129(1)(d), Florida Statutes; suspending his contractor’s license for a period of six months, followed by a period of probation deemed advisable by the Board; imposing a fine of $7,000.00; and directing that he make restitution in the amount of $3,500.00 to Carmen Goehrig. DONE AND ENTERED this 17th day of March, 2016, in Tallahassee, Leon County, Florida. S F. SCOTT BOYD Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 17th day of March, 2016. COPIES FURNISHED: Sorin Ardelean, Esquire Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202 (eServed) Antonio L. Requejo 11826 B. Miramar Parkway Miramar, Florida 33025 Daniel Biggins, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399 (eServed) William N. Spicola, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399 (eServed)

Florida Laws (6) 120.569120.5717.00117.002489.1195489.129
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. KENNETH H. CAIATA, 84-003443 (1984)
Division of Administrative Hearings, Florida Number: 84-003443 Latest Update: Dec. 04, 1990

The Issue Did respondent fail to properly supervise, direct and manage the contracting activities of the business of which he is the qualifier, and if so, what disciplinary action should be taken against respondent's contracting license?

Findings Of Fact At all times material to this proceeding the respondent was a certified building contractor licensed by the State of Florida and the qualifying agent for Custom Concrete of Naples, Inc. (Custom Concrete). Rodney Velez was the president of Custom Concrete and licensed only in concrete--concrete forming, placing and finishing. Susan Velez, Rodney Velez's wife, was an officer of Custom Concrete. On April 23, 1983, Custom Concrete, by and through Rodney Velez, entered into a contract with Mark and Penny Paterson to construct a home for $38,550.00. Mrs. Paterson had previously met Rodney Velez in the course of her work, and Velez had told her that he was a builder. Mrs. Paterson had suggested that Velez look at a floor plan that she and her husband had, and after certain negotiations, including a change of floor plan, the contract was entered into. During the course of the negotiations Mrs. Paterson never talked to the respondent and was unaware that the respondent was involved or would be involved in the construction of the home. Mrs. Paterson believed that Rodney Velez was the "builder"; however, the construction of the Paterson home was beyond the scope of Velez's concrete license. The respondent signed the application to secure the building permit for the Paterson residence, although he did not personally appear to procure the building permit. The clerk of the contractor's licensing section of the building code compliance department relied on the signature on the application because it was notarized. The notary was Susan Velez. Respondent did not supervise or direct the construction of the Paterson home. Neal Jackson, president of the company who did the electric work on the home, was unaware that respondent was involved in the project until well after the house was finished. Although it is usual for a supervisor or superintendent to be at the job site some of the time, Jackson never saw the respondent or Velez at the job site. Jeff Allain, the carpenter who did the framing and certain other work, was on the job site five or six days and saw the respondent once during the framing of the structure "just generally looking around." The respondent didn't say anything to Allain. David Isom did drywall work on the house. He had no contact with the respondent and did not see him at the construction site. Mrs. Paterson went by the construction site quite often and realized that the job was not being properly supervised. Velez was rarely there, and Mrs. Paterson never saw the respondent. The workmen on the site would ask the Patersons when Velez would be there because they had questions concerning the work. Neither of the building inspectors saw anyone supervising at the job site, although usually no one is at the job site when an inspection is made. Two days after the Patersons moved into their house, they compiled a "punch list" of the items that needed to be completed or corrected. The list was given to Velez, but the work was not corrected to the Paterson's satisfaction. Although Velez did not give the "punch list" to respondent, Velez discussed the problems with the respondent. Respondent did not take any steps to remedy the problems and said he thought "a lot of it was nonsense." Velez told respondent that he, Velez, would take care of it. Because of the unresolved problems with the house, Mrs. Paterson finally called the licensing board to file a complaint against Rodney Velez. At that time, she was informed that Rodney Velez was not the contractor; the contractor was the respondent. This was the first time that Mrs. Paterson was aware that the respondent was involved with the construction of the house. All of the Patersons dealings had been with Velez, and all checks for construction payments were made out to Velez personally. 2/ Even though the Patersons had not received satisfaction from Custom Concrete for the problems with the house, they signed the closing papers because Velez threatened to evict them. At closing the Patersons received a lien release from Custom Concrete which released all work prior to March 9, 1984. Subsequently, Velez filed a claim of lien against the Paterson property for work completed on February 9, 1984.

Recommendation Based upon the foregoing findings of fact and conclusions of law it is recommended that respondent be found guilty of violating Section 489.129(j), Florida Statutes, that he be fined $1,000.00, and that his license be suspended for 60 days from the date the Construction Industry Licensing Board enters its final order in this case. DONE and ORDERED this 30th day of January, 1985, in Tallahassee, Florida. DIANE A. GRUBBS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of January, 1985.

Florida Laws (4) 120.57489.105489.119489.129