The Issue The issue is whether the applicant for an Environmental Resource Permit ("ERP"), the City of Deltona ("City" or "Applicant"), has provided reasonable assurance that the system proposed complies with the water quantity, environmental, and water quality criteria of the St. Johns River Water Management District's ("District") ERP regulations set forth in Florida Administrative Code Chapter 40C-4, and the Applicant's Handbook: Management and Storage of Surface Waters (2005).
Findings Of Fact The District is a special taxing district created by Chapter 373, Florida Statutes, charged with the duty to prevent harm to the water resources of the District, and to administer and enforce Chapter 373, Florida Statutes, and the rules promulgated thereunder. The City of Deltona is a municipal government established under the provisions of Chapter 165, Florida Statutes. The Lake Theresa Basin is comprised primarily of a system of interconnected lakes extending from Lake Macy in the City of Lake Helen to the Butler Chain of Lakes (Lake Butler and Lake Doyle). The Lake Theresa Basin is land-locked and does not have a natural outfall to Lake Monroe and the St. Johns River. In 2003, after an extended period of above-normal rainfall in the Deltona area, the lakes within the land-locked Lake Theresa Basin staged to extremely high elevations that resulted in standing water in residential yards, and rendered some septic systems inoperable. Lake levels within the Lake Theresa Basin continued to rise and were in danger of rising above the finished floor elevations of some residences within the basin. On March 25, 2003, the District issued an Emergency Order (F.O.R. No. 2003-38) authorizing the construction and short-term operation of the Lake Doyle and Lake Bethel Emergency Overflow Interconnection. Since wetland and surface water impacts would occur, the Emergency Order required the City of Deltona to obtain an ERP for the system. The project area is 4.1 acres, and the system consists of a variable water structure on the west shore of Lake Doyle connected to a series of pipes, swales, water control structures, and wetland systems which outfall to a finger canal of Lake Bethel, with ultimate discharge to Lake Monroe and the St. Johns River. The first segment of the system extends downstream from the weir structure on the west shore of Lake Doyle via a pipe entrenched in the upland berm of the Sheryl Drive right-of-way. The pipe passes under Doyle Road and through xeric pine-oak uplands to the northeast shore of a large (approximately 15 acres) deepwater marsh. Water flows south through the deepwater marsh where it outfalls through four pipes at Ledford Drive. Two of the four pipes are overflow structures, controlled by canal gates. The pipes at Ledford Drive discharge into a ditch and into a large (greater than 20 acres) shallow bay swamp. The south end of the bay swamp is defined (and somewhat impounded) by a 19th Century railroad grade. Water flows through the bay swamp where it outfalls through five pipes at the railroad grade. Three of the five pipes are overflow structures, controlled by channel boards. The pipes at the railroad grade discharge to a 1500-foot long finger canal that was dug some time during the period 1940-1972 from the north central shore of Lake Bethel. The overflow interconnection system has three locations whereby the system can be shut down: 1) Lake Doyle--a control weir, controlled by three sluice gates; 2) Ledford Drive--two thirty-inch reinforced concrete pipes, controlled by canal gates; and 3) railroad grade--three thirty-inch reinforced concrete pipes, controlled by channel boards (collectively referred to as "Overflow Structures"). The Overflow Structures are designed to carry the discharge of water from Lake Doyle to Lake Bethel. With the Overflow Structures closed the system returns to pre-construction characteristics, meaning there will be no increase or decrease in the quantity or quality of water throughout the path of the system as a result of the project. An unequivocal condition of the permit is that the system would operate with all of the Overflow Structures closed. As an added assurance, the City proposes to place a brick and mortar plug in the Lake Doyle weir structure outfall pipe to prevent any discharge from the weir. The City has submitted to the District preliminary plans for a future phase in which the system would be modified for the purpose of alleviating high water levels within the Lake Theresa Basin when the water level in Lake Doyle rises above an elevation of 24.5 feet. The District shall require a separate permit application to be submitted for such future plans. Petitioner, Barbara Ash, has lived on Lake Theresa for 19 years. Ms. Ash lives upstream from the area of the weir that will be plugged in accordance with the ERP. She does not trust either the City of Deltona to comply with or the District to enforce the conditions of the ERP applied for by the City. Petitioner, Barbara Ash, also served as the qualified representative for Petitioners, Francell Frei, Bernard J. and Virginia Patterson, and Ted and Carol Sullivan. Ms. Ash represented that Ms. Frei has lived on Lake Theresa for 12 years, and both the Pattersons and the Sullivans live on Lake Louise, which is within the area of concern in this proceeding. Petitioner, Diana Bauer, has lived on Lake Theresa since February 2004. She fears that the lake will become too dry if the system is allowed to flow. She also believes the wildlife will be adversely affected if the water levels are too low since many species need a swampy or wet environment to thrive. She fears her property value will decrease as a result of the approval of the ERP. She also does not trust either the City to comply with or the District to enforce the conditions of the ERP. Petitioner, Howard Ehmer, lives two to three hundred yards down Lake Theresa from Ms. Bauer. He is concerned about the lake bed being too dry and attracting people on all terrain vehicles who enjoy driving around the lake bottom. He is concerned about his property value decreasing if the lake bed is dry. Further, when the lake level is too low, people cannot enjoy water skiing, boating, and fishing on Lake Theresa. Petitioner, Phillip Lott, a Florida native, has also owned and lived on property abutting Lake Theresa since 1995. Mr. Lott has a Ph.D. in plant ecology, and M.P.A. in coastal zone studies, an M.B.A. in international business, and a B.S. in environmental resource management and planning. Mr. Lott has been well acquainted with the water levels on Lake Theresa for many years. Based upon his personal observations of the lake systems in the Deltona area over the years, Mr. Lott has seen levels fluctuate greatly based upon periods of heavy and light rainfall. Mr. Lott is concerned that the District will permit the City to open the weir to let water flow through the system and cause flooding in some areas and low water levels in other areas. He fears that the District will allow the water to flow and upset the environmental balance, but he admits that this ERP application is for a closed system that will not allow the water to flow as he fears. Mr. Lott similarly does not trust the City to comply with and the District to enforce the conditions of the ERP. Petitioners, James E. and Alicia M. Peake, who were represented by Steven L. Spratt at hearing as their qualified representative, live on Lake Louise, which is interconnected with the Lake Theresa basin. The Peakes are concerned that if the level of Lake Louise drops below 21 feet, nine inches, they will not be able to use the boat launch ramps on the lake. Petitioner, Steven L. Spratt, also lives on Lake Louise, and is concerned about the water levels becoming so low that he cannot use the boat launch on the lake. He has lived on the lake since 2000, and remembers when the water level was extremely low. He fears that approval of the ERP in this case will result in low levels of water once again. Petitioner, Gloria Benoit, has live on Lake Theresa for two years. She also enjoys watching recreational activities on the lake, and feels that approval of the ERP will devalue her lakefront property. Ms. Benoit appeared at the first day of the hearing, but offered no testimony on her behalf. J. Christy Wilson, Esquire, appeared prior to the final hearing as counsel of record for Petitioners, Steven E. Larimer, Kathleen Larimer, and Helen Rose Farrow. Neither Ms. Wilson nor any of the three Petitioners she represented appeared at any time during the hearing, filed any pleadings seeking to excuse themselves from appearing at the final hearing, or offered any evidence, testimony, pre- or post- hearing submittals. Petitioner, Gary Jensen, did not appear at hearing, did not file any pleadings or papers seeking to be excused from appearing at the final hearing, and did not offer any evidence, testimony, pre- or post-hearing submittals. Both the City and the District recognize that areas downstream from the project site, such as Stone Island and Sanford, have experienced flooding in the past in time of high amounts of rainfall. The system proposed by the City for this ERP will operate with the overflow structures closed and a brick and mortar plug in the outfall pipe to prevent water flow from Lake Doyle to Lake Bethel. So long as the overflow structures are closed, the system will mimic pre-construction flow patterns, with no increase in volume flowing downstream. The District has considered the environment in its proposed approval of the ERP. The area abutting the project is little urbanized and provides good aquatic and emergent marsh habitat. With the exception of the western shore area of the deepwater marsh ("west marsh area"), the bay swamp and remaining deepwater marsh area have good ecological value. In the 1940's, the west marsh area was incorporated into the drainage system of a poultry farm that occupied the site. This area apparently suffered increased nutrient influxes and sedimentation that contributed to a proliferation of floating mats of aquatic plants and organic debris. These tussocks reduced the deepwater marsh's open water and diminished the historical marsh habitat. Water under the tussocks is typically anoxic owing to total shading by tussocks and reduced water circulation. Thick, soft, anaerobic muck has accumulated under the matted vegetation. Exotic shrubs (primrose willow Ludwigia peruvania) and other plants (cattails Typha spp.) dominate the tussocks. The construction of the project, from the 2003 Emergency Order, resulted in adverse impacts to 1.3 acres of wetlands having moderately high- to high ecological value and 0.2 acres of other surface waters. The 0.2 acre impact to other surface waters was to the lake bottom and the shoreline of Lake Doyle where the weir structure was installed. The 0.3 acres of wetland impacts occurred at the upper end of the deepwater marsh where the pipe was installed. The largest wetland impact (1.0 acre) was to the bay swamp. The bay swamp is a shallow body dominated by low hummocks and pools connected inefficiently by shallow braided channels and one acre is filled with a 1-2 foot layer of sediment following swamp channelization. Disturbance plants (e.g., primrose willow, Ludwigia peruvania, and elderberry Sambucus Canadensis) now colonize the sediment plume. Pursuant to the District's elimination and reduction criteria, the applicant must implement practicable design modifications, which would reduce or eliminate adverse impacts to wetlands and other surface waters. A proposed modification, which is not technically capable of being done, is not economically viable, or which adversely affects public safety through endangerment of lives or property is not considered "practicable." The City reduced and/or eliminated the impacts to the lake bottom and shoreline of Lake Doyle and deepwater marsh, to the extent practicable. The impacts were the minimum necessary to install the weir structure and pipe for the system; the weir structure and pipe were carefully installed on the edges of the wetland and surface water systems, resulting in a minimum amount of grading and disturbance. To compensate for the loss of 1.3 acres of wetlands and 0.2 acres of other surface waters, the City proposes to preserve a total of 27.5 acres of wetlands, bay swamp, marsh, and contiguous uplands. Included in this 27.5 acres are 6.4 acres of the west marsh, which are to be restored. The parties stipulated that the mitigation plan would adequately compensate for losses of ecological function (e.g. wildlife habitat and biodiversity, etc.) resulting from the project. Water quality is a concern for the District. Lake Monroe is included on the Florida Department of Environmental Protection's verified list of impaired water bodies for nitrogen, phosphorous, and dissolved oxygen. Water quality data for Lake Monroe indicate the lake has experienced high levels of nitrogen and phosphorous and low levels of dissolved oxygen. Prior to construction of the project, there was no natural outfall from the Lake Theresa Basin to Lake Monroe and therefore no contribution from this basin to nitrogen and phosphorous loadings to Lake Monroe. Lake Colby, Three Island Lakes (a/k/a Lake Sixma), and the Savannah are surface waters within the Lake Theresa Basin for which minimum levels have been adopted pursuant to Florida Administrative Code Chapter 40C-8. The system will operate with the overflow structures closed and a brick and mortar plug in the outfall pipe to prevent water flow from Lake Doyle to Lake Bethel, resulting in no outfall from the Theresa Basin to Lake Monroe. Minimum flows established for surface waters within the Lake Theresa Basin will not be adversely impacted. Under the first part of the secondary impact test, the City must provide reasonable assurance that the secondary impacts from construction, alteration, and intended or reasonable expected use of the project will not adversely affect the functions of adjacent wetlands or surface waters. The system is designed as a low intensity project. As proposed, little activity and maintenance are expected in the project site area. The reasonably expected use of the system will not cause adverse impacts to the functions of the wetlands and other surface waters. None of the wetland areas adjacent to uplands are used by listed species for nesting or denning. In its pre-construction state, the project area did not cause or contribute to state water quality violations. Under the second part of the secondary impact test, the City must provide reasonable assurance that the construction, alteration, and intended or reasonably expected uses of the system will not adversely affect the ecological value of the uplands to aquatic or wetland dependent species for enabling existing nesting or denning by these species. There are no listed threatened or endangered species within the project site area. Under the third part of the secondary impact test, and as part of the public interest test, the District must consider any other relevant activities that are closely linked and causally related to any proposed dredging or filling which will cause impacts to significant historical and archaeological resources. When making this determination, the District is required, by rule, to consult with the Division of Historical Resources. The Division of Historical Resources indicated that no historical or archaeological resources are likely present on the site. No impacts to significant historical and archaeological resources are expected. Under the fourth part of the secondary impact test, the City must demonstrate that certain additional activities and future phases of a project will not result in adverse impacts to the functions of wetlands or water quality violations. The City has submitted to the District preliminary plans for a future phase in which the system would be modified for the purpose of alleviating high water levels within the Lake Theresa Basin when the level in Lake Doyle rises above an elevation of 24.5 feet. Based upon the plans and calculations submitted, the proposed future phase, without additional measures, could result in minor increases in the loadings of nitrogen and phosphorous to Lake Monroe. Lake Monroe is included on the Florida Department of Environmental Protection's verified list of impaired water bodies due to water quality data indicating the lake has experienced high levels of nitrogen and phosphorous, and low levels of dissolved oxygen. Under this potential future phase, there would be an outfall from the Lake Theresa Basin to Lake Monroe. To address the impact on water quality of this potential future phase, the City has submitted a loading reduction plan for nitrogen, phosphorous, and dissolved oxygen. The plan includes compensating treatment to fully offset the potential increased nutrient loadings to Lake Monroe. Specifically, the loading reduction plan includes: Construction and operation of compensating treatment systems to fully offset anticipated increased nutrient loadings to Lake Monroe. Weekly water quality monitoring of the discharge from Lake Doyle for total phosphorous and total nitrogen. A requirement that the overflow structure be closed if the total phosphorous level reaches 0.18 mg/l or higher or the total nitrogen level reaches 1.2 mg/l or higher in any given week and will remain closed until levels fall below those limits. The implementation of these water quality mitigation measures will result in a net improvement of the water quality in Lake Monroe for nitrogen, phosphorous, or dissolved oxygen. The future phase was conceptually evaluated by the District for impacts to wetland functions. The future phase as proposed could result in adverse impacts to wetland functions. Operation of the system with the overflow structures open could impact the bay swamp and deepwater marsh. The City has demonstrated that any adverse impacts could be offset through mitigation. Based upon the information provided by the City and general engineering principles, the system is capable of functioning as proposed. The City of Deltona will be responsible for the operation, maintenance, and repair of the surface waster management system. A local government is an acceptable operation and maintenance entity under District rules. The public interest test has seven criteria. The public interest test requires the District to evaluate only those parts of the project actually located in, on, or over surface waters or wetlands, to determine whether a factor is positive, neutral, or negative, and then to balance these factors against each other. The seven factors are as follows: the public health, safety, or welfare of others; conservation of fish and wildlife and their habitats; fishing, recreational value, and marine productivity; temporary or permanent nature; 5) navigation, water flow, erosion, and shoaling; 6) the current condition and relative value of functions; and 7) historical and archaeological resources. There are no identified environmental hazards or improvements to public health and safety. The District does not consider impacts to property values. To offset any adverse impacts to fish and wildlife and their habitats, the City has proposed mitigation. The areas of the project in, on, or over wetlands do not provide recreational opportunities. Construction and operation of the project located in, on, or over wetlands will be permanent in nature. Construction and operation of the project located in, on, or over wetlands will not cause shoaling, and does not provide navigational opportunities. The mitigation will offset the relative value of functions performed by areas affected by the proposed project. No historical or archaeological resources are likely on the site of the project. The mitigation of the project is located within the same drainage basin as the project and offsets the adverse impacts. The project is not expected to cause unacceptable cumulative impacts.
Recommendation Based upon the Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered granting the City of Deltona's application for an environmental resource permit with the conditions set forth in the Technical Staff Report, and dismissing the Petitions for Formal Administrative Hearing filed by Gary Jensen in Case No. 04-2405, and by Steven E. Larimer, Kathleen Larimer, and Helen Rose Farrow in Case No. 04-3048. DONE AND ENTERED this 27th day of May, 2005, in Tallahassee, Leon County, Florida. S ROBERT S. COHEN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of May, 2005. COPIES FURNISHED: George Trovato, Esquire City of Deltona 2345 Providence Boulevard Deltona, Florida 32725 Diana E. Bauer 1324 Tartan Avenue Deltona, Florida 32738 Barbara Ash, Qualified Representative 943 South Dean Circle Deltona, Florida 32738-6801 Phillip Lott 948 North Watt Circle Deltona, Florida Howard Ehmer Nina Ehmer 32738-7919 1081 Anza Court Deltona, Florida 32738 Francell Frei 1080 Peak Circle Deltona, Florida 32738 Bernard T. Patterson Virginia T. Patterson 2518 Sheffield Drive Deltona, Florida 32738 Kealey A. West, Esquire St. Johns River Water Management District 4049 Reid Street Palatka, Florida 32177 J. Christy Wilson, Esquire Wilson, Garber & Small, P.A. 437 North Magnolia Avenue Orlando, Florida 32801 Gloria Benoit 1300 Tartan Avenue Deltona, Florida 32738 Gary Jensen 1298 Tartan Avenue Deltona, Florida 32738 James E. Peake Alicia M. Peake 2442 Weatherford Drive Deltona, Florida 32738 Steven L. Spratt 2492 Weatherford Drive Deltona, Florida 32738 Ted Sullivan 1489 Timbercrest Drive Deltona, Florida 32738 Kirby Green, Executive Director St. Johns River Water Management District 4049 Reid Street Palatka, Florida 32177
The Issue The issue in this case is whether Seacoast Utility Authority's challenge to the South Florida Water Management District's proposed issuance of a water use permit to PGA National Golf Club and Sports Center, Ltd. in a critical water supply area should be upheld. As discussed below, the parties have stipulated that, in deciding to issue the permit, the South Florida Water Management District has not evaluated or considered whether the use of reclaimed water was either economically, environmentally or technically infeasible.
Findings Of Fact Based upon the evidence adduced at the hearing and the entire record in this proceeding, the following findings of fact are made: Seacoast is a publicly owned water and sewer utility which operates a wastewater treatment facility in Palm Beach County, Florida. Seacoast's service area is bounded on the south by Riviera Beach and on the north by the Town of Jupiter. Seacoast operates four treatment plants: two water plants and two wastewater plants. Seacoast's regional wastewater facility currently generates approximately six (6) million gallons per day ("MGD") of reclaimed water and is permitted by the Florida Department of Environmental Protection ("DEP") as an eight (8) MGD wastewater treatment plant. As discussed in more detail in the Conclusions of Law below, the Florida Legislature and DEP have sought to encourage the reuse of reclaimed water. This policy is one of the many sometimes competing goals that are supposed to be taken into account in the water use permitting process. Until a few years ago, the treated effluent from one of Seacoast's wastewater plants was directly discharged to nearby surfacewater. During the last four years, Seacoast installed a pumping station and five miles worth of transmission lines to deliver all of its treated effluent to its regional wastewater facility. Seacoast claims that these efforts were prompted by its interpretation of changing regulations and a perceived regulatory preference for reuse of water.1 Although Seacoast claims that there has been a change in regulatory emphasis in favor of reuse of reclaimed water, Seacoast is not under a mandate from any court or agency to sell or utilize any specific amount of reclaimed water. It does appear that a deep injection well used by Seacoast for disposal of wastewater is not or was not operating as designed. Seacoast was apparently obligated to construct reclaimed water facilities at its wastewater treatment plant as part of its permit from DEP for the injection well. There was no requirement that the reclaimed water be sold or otherwise utilized. The intended primary disposal for Seacoast's reclaimed water is reuse.2 Seacoast's wastewater treatment plant provides irrigation quality reclaimed water. Seacoast tries to sell the reclaimed water for irrigation use in an effort to recoup the costs incurred in constructing the facilities necessary to reclaim the water. Backup disposal is achieved through injection down a 3300 feet deep injection well into the boulder zone. Once the reclaimed water is injected down the well, it is unavailable for reuse. The evidence suggests that there are other possible utilizations available for Seacoast's reclaimed water including sale to another utility and/or backup recharge to preserve wetlands during periods of high pumpage. For example, Seacoast is apparently in the process of applying for the necessary permits to utilize a portion of its reclaimed water to prevent harm to wetlands adjacent to its Hood Road Well Field by constructing an hydraulic barrier. At all times pertinent to this proceeding, only approximately 1.2 MGD of the reclaimed water generated by Seacoast was being reused. The remaining approximately 5 MGD was disposed of through the injection well. PGA owns and operates three (3) golf courses in Palm Beach County within Seacoast's service area. PGA's golf courses are located within an area that has been designated by the District as a Critical Water Supply Problem Area. Critical Water Supply Problems Areas are geographical regions where the available water supply due to the potential for saltwater intrusion, wetland impacts, or impacts to existing legal uses, is predicted not to meet water demands that are projected during the next 20 years. See, Chapter 40E-23, Florida Administrative Code. The use of reclaimed water is not mandated in such areas. However, the District's Rules seek to insure the optimal utilization of alternative sources of water in such areas to minimize the potential harm to water resources. It is not clear from the evidence presented in this case when PGA first obtained the Permit from the District for golf course irrigation. The Permit allows PGA to use the groundwater table as the source of water for its irrigation. Before its expiration, PGA timely sought renewal of the Permit. On April 12, 1994, the District staff recommended renewal of PGA's Permit. The staff recommendation would allow PGA to continue using the groundwater table as the source of its water. The recommendation did not contain a requirement for PGA to use any reclaimed water as part of its golf course irrigation system. Seacoast became aware of PGA's application to renew its Permit through a routine review of all water use permit applications made to the District by "potential reclaimed water users in [its] service area." Seacoast filed a Petition for Formal Administrative Hearing challenging the District staff's recommendation to renew PGA's Permit. In its Petition, Seacoast alleged that its substantial interests would be affected by the renewal of the Permit because Seacoast's ability to achieve the State of Florida's goals of conservation and environmental protection depends upon PGA, and other similar country clubs, being required to consume reclaimed water. Seacoast contends that the staff recommendation immediately eliminates a major potential consumer of Seacoast's reclaimed water which purportedly impairs Seacoast's ability to meet state objectives for reuse of reclaimed water and results in the undesirable continued disposal of reclaimed water via deep well injection. In connection with its challenge to the proposed renewal of PGA's Permit, Seacoast has stipulated that PGA's proposed withdrawals from the groundwater table would not cause harm to the water resources of the District. Seacoast also admits that it has never evaluated whether it would be environmentally injured by PGA's withdrawals from the groundwater table and/or whether the proposed use by PGA is wasteful. The District does not currently have any goals for the utilization of reclaimed water on a regional basis. Instead, the District oversight of the utilization of reclaimed water is done on a permit by permit basis. As a general policy, the District will not accept a water use permit application in an area of critical water shortage unless a reuse feasibility determination is included. The District's rules do not currently contain any guidelines as to how the determination of feasibility is to be made, nor are there any criteria for reviewing an applicant's determination of feasibility. As discussed below, the District does not even consider the applicant's reuse feasibility determination unless the proposed withdrawal is projected to result in harm to the resources of the District. Even when harm to a resource is projected, the District accepts an applicant's feasibility determination regarding the use of reclaimed water without question or analysis. For the other consumptive use criteria set forth in Rule 40E-2.301, the District independently evaluates the applicant's conclusions to confirm that they are reasonable. In other words, the District treats reclaimed water as an alternative source of water in the event that an applicant's proposed water use is projected to cause harm to the water resources of the District. If no harm is expected to occur to water resources as a result of a proposed use, the District does not review the applicant's determination of whether or not to use reclaimed water. If harm is projected, the applicant is required to look at alternatives like water conservation or utilization of water sources other than those proposed (such as reclaimed water). The applicant is free to select any alternative that mitigates the harm. Thus, even in a Critical Water Supply Area, an applicant can mitigate concerns about harm to the resource without utilizing reclaimed water. In sum, under the District's current procedures, the use of reclaimed water is never required. It is simply one alternative an applicant can utilize to offset or mitigate projected harm to water resources (such as saltwater intrusion, contamination, wetland drawdowns or existing legal use impacts) from a proposed withdrawal. Even when the District staff concludes that an applicant's proposed use will result in harm to water resources, the staff does not critically review the applicant's determination of whether the use of reclaimed water is economically, environmentally, or technically infeasible. With respect to PGA's Permit, the District staff concluded that no harm to the resource was predicted as a result of PGA's proposed use. Thus, PGA's determination not to use reclaimed water was not evaluated or even considered. The District explains that its implementation of the permitting program is based upon its interpretation that its primary responsibility is to prevent harm to water resources. The District points out that there are a number of factors to be considered in utilizing reclaimed water. These factors include, but are not limited to, the cost of the reclaimed water, the cost of retrofitting an irrigation system, the long-term availability of the reclaimed supply and the availability of a back-up supply.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the South Florida Water Management District enter a Final Order dismissing the Petition filed by Seacoast challenging the renewal of Permit Number 50-00617-W to PGA for golf course irrigation. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 6th day of February 1995. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 6th day of February 1995.
The Issue The issue to be determined is whether Respondent Land Trust #97-12 (“Land Trust”) is entitled to an Environmental Resource Permit (“ERP”) for its proposed project on Perico Island in Bradenton, Florida.
Findings Of Fact The Parties Petitioner Joseph McClash is a resident of Bradenton, Florida, who uses the waters in the vicinity of the project for fishing, crabbing, boating, and wildlife observation. Petitioner Manasota-88, Inc., is an active Florida nonprofit corporation for more than 20 years. Manasota-88 has approximately 530 members, most of whom (approximately 300) reside in Manatee County. The mission and goal of Manasota-88 includes the protection of the natural resources of Manatee County, including Anna Maria Sound and Perico Island. Petitioner FISH is an active Florida nonprofit corporation in existence since 1991. FISH owns real property in unincorporated Cortez in Manatee County and maintains a Manatee County mailing address. FISH has more than 190 members and more than 150 of them own property or reside in Manatee County. The mission and goal of FISH includes protection of the natural resources of Manatee County, including Anna Maria Sound and Perico Island. Intervenor Suncoast Waterkeeper, Inc., is an active Florida nonprofit corporation in existence since 2012. The mission of Suncoast Waterkeeper is “to protect and restore the Suncoast’s waterways through enforcement, fieldwork, advocacy, and environmental education for the benefit of the communities that rely upon coastal resources.” Suncoast Waterkeeper provided the names and addresses of 25 members residing in Manatee County. A substantial number of the members of Suncoast Waterkeeper use the area and waters near the proposed activity for nature-based activities, including nature observation, fishing, kayaking, wading, and boating along the natural shorelines of Anna Maria Sound and Perico Island. Intervenor Sierra Club, Inc., is a national organization that is a California corporation registered as a foreign nonprofit corporation in Florida. Sierra Club has been permitted to conduct business in Florida since 1982. The mission of Sierra Club includes protection of the natural resources of Manatee County, which include Anna Maria Sound and Perico Island. Sierra Club provided the names and addresses of 26 members who live in Manatee County. A substantial number of the members of Sierra Club use the area and waters near the proposed project for nature-based activities, including observing native flora and fauna, fishing, kayaking, wading, and boating along the natural shorelines of Anna Maria Sound and Perico Island. Respondent Land Trust is the applicant for the challenged ERP and owns the property on which the proposed project would be constructed. Respondent District is an independent special district of the State of Florida created, granted powers, and assigned duties under chapter 373, Florida Statutes, including the regulation of activities in surface waters. The proposed project is within the boundaries of the District. The Project Site The project site is 3.46 acres of a 40.36-acre parcel owned by Land Trust. The parcel includes uplands, wetlands, and submerged lands, on or seaward of Perico Island, next to Anna Maria Sound, which is part of Lower Tampa Bay. Anna Maria Sound is an Outstanding Florida Water. The project site is adjacent to a large multi-family residential development called Harbour Isles, which is currently under construction. Access to the Land Trust property is gained through this development. The Land Trust parcel contains approximately seven acres of high quality mangroves along the shoreline of Anna Maria Sound. They are mostly black and red mangroves, with some white mangroves. The mangroves on the project site amount to a total of 1.9 acres. Mangroves have high biological productivity and are important to estuarine food webs. Mangroves provide nesting, roosting, foraging, and nursery functions for many species of wildlife. Mangroves also provide a buffer from storm surge and help to stabilize shorelines. Wildlife species found on the project site include ibises, pelicans, egrets, spoonbills, mangrove cuckoos, bay scallops, fiddler crabs, mangrove tree crabs, horseshoe crabs, marsh rabbits, raccoons, mangrove bees, and a variety of fish. No endangered species have been observed on the project site, but mangroves are used by a number of listed species. The Proposed Project The proposed project is to construct a retaining wall, place fill behind the wall to create buildable lots for four single-family homes, construct an access driveway, and install a stormwater management facility. The stormwater management facility is a “Stormtech” system, which is an underground system usually used in situations where there is insufficient area to accommodate a stormwater pond. Riprap would be placed on the waterward side of the retaining wall. The retaining wall would be more than 35 feet landward of the mean high water line in most areas. Petitioners contend the proposed retaining wall is a vertical seawall, which is not allowed in an estuary pursuant to section 373.414(5). “Vertical seawall” is defined in section 2.0(a)(111), Volume I, of the Environmental Resource Permit Applicant’s Handbook (“Applicants Handbook”) as a seawall which is steeper than 75 degrees to the horizontal. It further states, “A seawall with sloping riprap covering the waterward face to the mean high water line shall not be considered a vertical seawall.” The retaining wall is vertical, but it would have riprap covering its waterward face and installed at a slope of 70 degrees. The retaining wall is not a vertical seawall under the District’s definition. Stormwater Management Stormwater in excess of the Stormtech system’s design capacity would discharge into Anna Maria Sound. Because Anna Maria Sound is an Outstanding Florida Water, District design criteria require that an additional 50 percent of treatment volume be provided. The Stormtech system meets the District’s design criteria for managing water quality and water quantity. Projects which meet the District’s design criteria are presumed to provide reasonable assurance of compliance with state water quality standards. Petitioners’ evidence was not sufficient to rebut this presumption. Petitioners contend the District waiver of water quality certification for the proposed project means that Land Trust was not required to meet water quality standards. However, that was a misunderstanding of the certification process. All state water quality criteria are applicable. Petitioners contend water quality monitoring should be imposed for this project. However, section 4.7 of the Applicant’s Handbook, Volume II, provides that if the applicant meets the District’s design criteria, water quality monitoring is not required. Petitioners failed to prove the proposed stormwater management system cannot be constructed, operated, or maintained in compliance with applicable criteria. Wetland Impacts In order to create buildable lots, 1.05 acres of the 1.9 acres of mangroves on the project site would be removed and replaced with fill. A swath of mangroves approximately 40 feet wide would remain waterward of the retaining wall. The proposed direct and secondary impacts to the functions provided by wetlands were evaluated using the Uniform Mitigation Assessment Method (“UMAM”) as required by Florida Administrative Code Chapter 62-345. UMAM is used to quantify the loss of functions performed by wetlands considering: current condition, hydrologic connection, uniqueness, location, fish and wildlife utilization, time lag, and mitigation risk. The District determined the filling of 1.05 acres of wetlands would result in a functional loss of 0.81 units and the secondary impacts resulting from installation of the retaining wall would result in a loss of 0.09 units for a total functional loss of 0.9 units. Petitioners contend the functional loss would be greater. Petitioners contend the wetland delineation performed by Land Trust and confirmed by the District did not extend as far landward as the hydric soils and, therefore, the total acreage of affected wetlands would be greater. However, Petitioners did not produce a wetland delineation for the project site, and their evidence was not sufficient to rebut Land Trust's prima facie evidence on this issue. Petitioners’ experts believe the secondary impacts caused by the proposed project would be greater than calculated, including fragmentation of the shoreline mangrove system, damage to the roots of mangroves near the retaining wall, and scouring effects caused by wave action associated with the retaining wall. Respondents assert that the analysis by Petitioners’ expert Jacqueline Cook relied on federal methodology and that “the science used in her analysis is not contained in the state or district rule criteria.” Reliance on science is always appropriate. However, Ms. Cook’s use of a federal impact assessment methodology creates doubt about whether her scoring is consistent with UMAM. Despite the unreliability of Ms. Cook’s UMAM score, it is found that Respondents’ UMAM score under-calculated secondary impacts due to scour and other effects of changed water movement that would be caused by the retaining wall. It was not explained how the loss of storm buffering and erosion prevention functions of wetlands are accounted for in the UMAM score. Elimination or Reduction of Impacts Section 10.2.1 of the Applicant’s Handbook, Volume I, states that in reviewing a project the District is to consider practicable design modifications to eliminate or reduce impacts to wetland functions. Section 10.2.1.1 explains: The term “modification” shall not be construed as including the alternative of not implementing the activity in some form, nor shall it be construed as requiring a project that is significantly different in type or function. A proposed modification that is not technically capable of being completed, is not economically viable, or that adversely affects public safety through the endangerment of lives or property is not considered “practicable.” A proposed modification need not remove all economic value of the property in order to be considered not “practicable.” Conversely, a modification need not provide the highest and best use of the property to be “practicable.” In determining whether a proposed modification is practicable, consideration shall also be given to cost of the modification compared to the environmental benefit it achieves. Land Trust originally proposed constructing a surface water retention pond. The Stormtech stormwater management system would cause less wetland impact than a retention pond. Land Trust contends the use of a retaining wall reduces wetland impacts because, otherwise, more mangroves would have to be removed to account for the slope of the waterward side of the fill area. However, this proposition assumes the appropriateness of the size of the fill area. Land Trust also contends wetland impacts are reduced by using the adjacent development to access the proposed project site, rather than creating a new road. However, the evidence did not establish that Land Trust had a practicable and preferred alternative for access. Unlike the Stormtech system, the retaining wall and access driveway were not shown to be project modifications. The proposed project would cause fewer impacts to wetlands if the fill area was reduced in size, which was not shown to be impracticable. Reducing the size of the fill area would not cause the project to be significantly different in type or function. Land Trust did not demonstrate that it implemented reasonable design modifications to eliminate or reduce impacts to wetland functions. Mitigation Land Trust proposes to purchase credits from the Tampa Bay Mitigation Bank, which is 17 miles north of the proposed project site. The Tampa Bay Mitigation Bank is in the Tampa Bay Drainage Basin. The project site is in the South Coastal Drainage Basin. Pursuant to section 10.2.8 of the Applicant’s Handbook, Volume I, if an applicant mitigates adverse impacts within the same drainage basin, the agency will consider the regulated activity to have no unacceptable cumulative impacts upon wetlands and other surface waters. However, if the applicant proposes to mitigate impacts in another drainage basin, factors such as “connectivity of waters, hydrology, habitat range of affected species, and water quality” will be considered to determine whether the impacts are fully offset. The parties disputed whether there was connectivity between the waters near the project site and the waters at the Tampa Bay Mitigation Bank. The more persuasive evidence shows there is connectivity. There was also a dispute about the habitat range of affected species. The evidence establishes that the species found in the mangroves at the project site are also found at the mitigation bank. However, local fish and wildlife, and local biological productivity would be diminished by the proposed project. This diminution affects Petitioners’ substantial interests. The loss or reduction of storm buffering and erosion prevention functions performed by the mangroves at Perico Island cannot be mitigated for at the Tampa Bay Mitigation Bank. Cumulative impacts are unacceptable when the proposed activity, considered in conjunction with past, present, and future activities would result in a violation of state water quality standards, or significant adverse impacts to functions of wetlands or other surface waters. See § 10.2.8.1, Applicant’s Handbook, Vol. I. Section 10.2.8(b) provides that, in considering the cumulative impacts associated with a project, the District is to consider other activities which reasonably may be expected to be located within wetlands or other surface waters in the same drainage basin, based upon the local government’s comprehensive plan. Land Trust did not make a prima facie showing on this point. Land Trust could propose a similar project on another part of its property on Perico Island. Anyone owning property in the area which is designated for residential use under the City of Bradenton’s comprehensive plan and bounded by wetlands could apply to enlarge the buildable portion of the property by removing the wetlands and filling behind a retaining wall. When considering future wetland impacts in the basin which are likely to result from similar future activities, the cumulative impacts of the proposed project would result in significant adverse impacts to wetland functions in the area. Public Interest For projects located in, on, or over wetlands or other surface waters, an applicant must provide reasonable assurance that the project will not be contrary to the public interest, or if such activities significantly degrade or are within an Outstanding Florida Water, are clearly in the public interest, as determined by balancing the criteria set forth in rule 62- 330.302(1)(a), and as set forth in sections 10.2.3 through of the Applicant’s Handbook. Rule 62-330.302, which is identical to section 373.414, Florida Statutes, lists the following seven public interest balancing factors to be considered: Whether the activities will adversely affect the public health, safety, or welfare or the property of others; Whether the activities will adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats; Whether the activities will adversely affect navigation or the flow of water or cause harmful erosion or shoaling; Whether the activities will adversely affect the fishing or recreational values or marine productivity in the vicinity of the activity; Whether the activities will be of a temporary or permanent nature; Whether the activities will adversely affect or will enhance significant historical and archaeological resources under the provisions of Section 267.061, F.S.; and The current condition and relative value of functions being performed by areas affected by the proposed regulated activity. The Parties stipulated that the proposed project would not have an adverse impact on public health, navigation, historical resources, archeological resources, or social costs. Land Trust proposes to give $5,000 to the City of Palmetto for an informational kiosk at the City of Palmetto’s public boat ramp. A District employee testified that this contribution made the project clearly in the public interest. Reasonable assurances were not provided that the proposed project is clearly in the public interest because of the adverse cumulative effects on the conservation of fish and wildlife, fishing and recreational values, and marine productivity of Anna Maria Sound, an Outstanding Florida Water.
Recommendation Based on the Findings of Fact and Conclusions of Law set forth above, it is RECOMMENDED that the Southwest Florida Water Management District issue a final order that denies the Environmental Resource Permit. DONE AND ENTERED this 25th day of June, 2015, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 25th day of June, 2015. COPIES FURNISHED: Christian Thomas Van Hise, Esquire Abel Band, Chartered Post Office Box 49948 Sarasota, Florida 34230-6948 (eServed) Martha A. Moore, Esquire Southwest Florida Water Management District 7601 Highway 301 North Tampa, Florida 33637 (eServed) Douglas P. Manson, Esquire MansonBolves, P.A. 1101 West Swann Avenue Tampa, Florida 33606 (eServed) Joseph McClash 711 89th Street Northwest Bradenton, Florida 34209 (eServed) Ralf G. Brookes, Esquire Ralf Brookes Attorney 1217 East Cape Coral Parkway, Suite 107 Cape Coral, Florida 33904 (eServed) Justin Bloom, Esquire Post Office Box 1028 Sarasota, Florida 34230 (eServed) Robert Beltram, P.E., Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34604-6899
Findings Of Fact The Dunes Golf and Country Club, Sanibel, is a partnership owned by John K. Kontinos and William R. Frizzell. They operate a nine hole golf course consisting of 65 acres of the eastern portion of Sanibel Island. The golf course is open to the public and, during the winter season, some 150 to 175 persons utilize the facility daily, but in the period May--November, it is utilized by only about 15 or 20 persons per day. The golf course is presently irrigated by water obtained from the lower Hawthorn and Suwannee aquifers through a well that is approximately 737 feet deep. On the days that water is pumped from the well, the pumping duration is from 8 to 12 hours per day, but the monthly hours during which pumping occurs averages approximately 155 hours per month. There is another existing well in another portion of the applicant's property which extends 896 feet into the Suwannee aquifer. The well presently in use (well number 1) has 546 feet of casing and the well that is not in use (well number 2) has 700 feet of casing. (Testimony of Kontinos, Exhibits 2, 4) On December 15, 1977, the Dunes Golf and Country Club submitted an application to the South Florida Water Management District for a consumptive use permit to withdraw 320 acre feet of groundwater per year to irrigate an area of approximately 109 acres. The intent of the application was to obtain a sufficient quantity of water to irrigate the golf course which the applicant intends to enlarge to consist of 18 holes. The additional 9 holes would cover some 44 acres and well number 2 is intended to be activated to provide additional water for this purpose. (Testimony of Kontinos, Keiling, Exhibits 1- 2) The South Florida Water Management District issued the required public notice of the application on March 30, 1978, and objections to the application were received by that agency from the City Council of Sanibel, the Island Water Association, Inc., and George R. Campbell. Public notice of hearing on the application was duly published on March 30, 1978. (Exhibits 5-7) The staff of the South Florida Water Management District reviewed the application and recommended continuation of the applicant's existing use from the lower Hawthorn Formation and use of additional irrigation water from the Suwannee aquifer in the total amount of 320 acre feet annually. It also recommended that the issuance of a permit should be conditioned in various respects to include semiannual submission of water quality data and pumpage records for each well, installation and maintenance of well controls, and repair or replacement of well casings, valves or controls that leak or become inoperative. The staff further recommended that maximum monthly withdrawals from the lower Hawthorn Formation be limited to 7.5 million gallons and 7.6 million gallons from the Suwannee Formation. At the hearing however, the South Florida Water Management District representative changed these recommendations to 8.9 MO and 6.1 MG respectively. Additionally, the initial recommendation of 320 acre feet annual withdrawal was reduced to 200 acre feet. This amount is considerably less that the average of 600 acre feet used on other comparably sized golf courses. Further the staff representative recommended at the hearing that a further condition be attached to the issuance of the permit; i.e., Condition 15, which requires the permittee to submit analyses of total dissolved concentrations in water samples from each well within 30 days of permit issuance and, if such concentration exceeds 4,000 MG/L, logging procedures as to the affected well will be required with necessary safeguards to be employed to eliminate any interaquifer leakage. (Testimony of Gleason, Exhibit 4) The objections of the City of Sanibel and the Island Water Association, Inc. involved concerns that further withdrawals from the lower Hawthorn aquifer will affect the availability of water which is treated by the water association for general island use. In addition, there is concern about possible contamination of the lower Hawthorn aquifer from interaquifer leakage. The Water Association is a member-owned cooperative that is not under the jurisdiction of the municipality. It is concerned about the draw down in the water table which will be occasioned by additional withdrawals by the applicant. It therefore believes that pumping tests should be conducted prior to the issuance of a permit to provide information concerning the capacity and safe yield of the wells. Although an Association expert testified that the proposed Dunes' withdrawal would create a cone of depression that would extend into and influence the existing Water Association wells, the evidence shows such influence to be minimal due to the fact that the Dunes wells are almost three miles away from the nearest Association well. Further, due to the limited time that the Dunes wells are pumped each day, the aquifer recovers to a certain extent during other hours. Although concerns are felt by the Water Association that water quality will be affected because of leakage from the Suwannee aquifer to the lower Hawthorn aquifer due to possible corrosion of steel casings in the Dunes wells, no evidence was presented that such casings are in fact defective and will contribute to degradation of water quality because of additional withdrawals. The additional special condition placed upon the issuance of a permit by the South Florida Water Management District will require correction of any such leakage that is discovered in the future. Previous studies show that the lower Hawthorn aquifer is separated from the Suwannee aquifer by the Tampa Limestone Formation which would slow down any entry of poorer quality water into the Hawthorn aquifer. It is found that the lesser amounts of water recommended by the South Florida Water Management District at the hearing will further reduce the likelihood of water quality degradation or draw down in other Island wells. (Testimony of Butler, Holland, Nuzman, Gleason, Exhibits 6, 8-13) Ecological concerns were expressed at the hearing by a public witness as to the wastefulness of irrigating golf coup Yes and the requirement for fertilizer in sandy soil which causes leaching of nutrients after heavy water use. (Testimony of Webb)
Recommendation That a permit be issued to the applicant authorizing the consumptive use of the quantity of water recommended by the South Florida Water Management District staff, subject to the recommended conditions thereto. THOMAS C. OLDHAM Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: John H. Wheeler Post Office Box V West Palm Beach, Florida 33402 James D. Decker, Esquire Post Office Box 200 Ft. Myers, Florida 33902
The Issue The issues are whether to (a) issue an Environmental Resource Permit (ERP) to the Department of Transportation (DOT) and Martin County (County) authorizing construction and operation of a surface water management system to serve a project known as the Indian Street Bridge; (b) issue DOT a letter of modification of ERP No. 43-00785-S authorizing roadway and drainage modifications to the Kanner Highway/Indian Street intersection; and (c) issue DOT a letter of modification of ERP No. 43-01229-P authorizing roadway and drainage modifications to Indian Street between the intersections of Kanner Highway and Willoughby Boulevard.
Findings Of Fact Based on the evidence presented by the parties, the following findings of fact are made: The Parties Petitioner Citizens for Smart Growth, Inc., is a Florida 501(c)(3) corporation with its principal place of business in Palm City, Florida. It was formed by Odias Smith in August 2001, who serves as its president. The original directors were Kathie Smith, Odias Smith, and Craig Smith, who is the Smiths' son. The composition of the Board has never changed. According to the original Articles of Incorporation, its objectives are "preserving and enhancing the present advantages of living in Martin County (Quality of Life) for the common good, through public education, and the encouragement of reasonable and considered decision making by full disclosure of impacts and alternatives for the most appropriate use of land, water and resources." The exact number of members fluctuates from time to time. There are no dues paid by any member. At his deposition, Mr. Smith stated that no membership list exists; however, Kathie Smith stated that she currently has a list of 125 names, consisting of persons who at one time or another have made a contribution, have attended a meeting, or asked to be "kept informed of what's going on or asked to be on a mailing list or a telephone list, so they could be advised when we have meetings." No meetings have been held since 2006. Therefore, the Petitions filed in these cases have never been discussed at any meetings of the members, although Ms. Smith indicated that telephone discussions periodically occur with various individuals. Kathie Smith believes that roughly 25 percent of the members reside in a mobile home park north of the project site on Kanner Highway on the eastern side of the St. Lucie River, she does not know how many members reside on the western side of the St. Lucie River, and she is unaware of any member who resides on the South Fork of the St. Lucie River immediately adjacent to the project. Although the three Petitions allege that "seventy percent of the members . . . reside and/or recreate on the St. Lucie River," and in greater detail they allege how those members use that water body or depend on it for their livelihood, no evidence was submitted to support these allegations that 70 percent (or any other percentage of members) use or depend on the South Fork of the St. Lucie River for recreational or other activities. Petitioners Odias Smith and Cathie Smith reside in Palm City, an unincorporated community just south of Stuart in Martin County. They have opposed the construction of the new bridge since they moved to Palm City in 2001. It is fair to infer that Mr. Smith formed the corporation primarily for the purpose of opposing the bridge. Their home faces north, overlooking the South Fork of the St. Lucie River, from which it is separated by Saint Lucie Shores Drive and a narrow strip of common-ownership property. A boat dock extends from the common-ownership property into the St. Lucie River, providing 5 slips for use by the Smiths and other co-owners. The home is located three blocks or approximately 1,000 feet from the proposed western landfall of the new bridge. Due to the direction that the house faces (north) and the site of the new bridge, the surface water management system elements associated with the bridge will not be visible from their property. Mr. Smith believes, however, that when looking south through a veranda window on the second floor of his home, he will be able to see at least a part of the new bridge. From the front of their house, they now have an unobstructed view of the existing Palm City Bridge, a large structure that crosses the St. Lucie River approximately six- tenths of a mile north of their home, and which is similar in size to the new bridge now being proposed by the Applicants. The Smiths' home is more than 500 feet from the Project's right- of-way, and they do not know of any impact on its value caused by the Project. While the Smiths currently engage in walking, boating, running, fishing, and watching wildlife in the neighborhood or the South Fork of the St. Lucie River, there was no credible evidence that the Project would prevent them from doing so after the bridge and other improvements are constructed. Also, there was no evidence showing that the ERP Letter Modifications will cause them to suffer any adverse impacts. In fact, as noted below, by DOT undertaking the Project, the neighborhood will be improved through reduced flooding, improved water quality, and new swales and ponds. The County is a political subdivision of the State. It filed one of the applications at issue in this proceeding. DOT is an agency of the State and filed the three applications being contested. The District has the power and duty to exercise regulatory jurisdiction over the administration and enforcement of ERP criteria pursuant to Part IV, Chapter 373, Florida Statutes, and Title 40E of the Florida Administrative Code. The Department of Environment Protection (DEP) has delegated certain authority to the District, including the authority to authorize an applicant to use sovereign submerged lands via a public easement within the District's geographic jurisdiction. The Project Construction of a new bridge over the St. Lucie River has been studied extensively by the Applicants for over twenty years. DOT has awarded the contract and nearly all of the right-of-way has been purchased. The Project will begin as soon as the remaining permits are acquired. The Project is fully funded through the American Recovery and Reinvestment Act of 2009 and County funding. The Project is located in the County and includes 62.06 acres of roadway bridge development and 12.45 acres of sovereign submerged lands. The Project begins on the west side of the St. Lucie River on County Road 714, approximately 1,300 feet west of Mapp Road in Palm City and ends on the east side of the St. Lucie River approximately 1,400 feet east of Kanner Highway (State Road 76) on Indian Street. It includes construction and operation of a surface water management system to serve the road and bridge project. The total length of the Project is approximately 1.96 miles (1.38 miles of roadway and 0.58 miles of bridge) while the total area is approximately 74.51 acres. After treatment, surface water runoff will discharge to the tidal South Fork of the St. Lucie River. The Project encompasses a bridge crossing the South Fork of the St. Lucie River and the Okeechobee Waterway. Both are classified as Class III waters. The bridge transitions from 4 to 6 lanes east of the Okeechobee Waterway and will require a 55-foot vertical clearance and a 200-foot horizontal clearance between the fender systems at the Okeechobee Waterway. The bridge will cross over a portion of Kiplinger Island owned and preserved by the County. A part of the island was donated to the County in 1993-1994 by The Kiplinger Washington Editors, Inc., and the Kiplinger Foundation, Inc. Audubon of Martin County owns another part of the island. The transfer of title to the County does not include any restriction on the use of the island for conservation purposes only. Documentation submitted at hearing refers to a "two hundred foot wide road right-of-way" easement that the bridge will cross and allows the County to designate where on the island parcel such an easement would be. Therefore, spanning the bridge over a portion of the island owned by the County is clearly permissible. The Project also includes the roadway transition and widening/reconstruction of (a) County Road 714 from the beginning of the Project to Mapp Road from 2-lane to a 4-lane divided roadway; (b) Southwest 36th Street from Mapp Road to the beginning of the bridge from a 2-lane rural roadway to a 4-lane divided roadway with wide roadway swales; and (c) Kanner Highway (along Indian Street) from a 4-lane to a 6-lane divided urban roadway. Drainage improvements on both sides of the St. Lucie River are associated with the roadway construction. DOT proposes to provide both on-site and off-site mitigation for wetland and surface waters impacts pursuant to a mitigation plan approved by the District. The ERP Permitting Criteria In order to obtain an ERP, an applicant must satisfy the conditions for issuance set forth in Florida Administrative Code Rules 40E-4.301 and 40E-4.302. Besides these rules, certain related BOR provisions which implement the rules must also be considered. The conditions for issuance primarily focus on water quality, water quantity, and environmental criteria and form the basis of the District's ERP permitting program. The parties have stipulated that the Project either complies with the following rule provisions or they are not applicable: Rules 40E-4.301(1)(a), (b), (g), (g), (h), and (k), and 40E- 4.302(1)(a)3. and 6. All other provisions remain at issue. Where conflicting evidence on these issues was submitted, the undersigned has resolved all evidentiary conflicts in favor of the Applicants and District. Based on the parties' Stipulation, the following provisions in Rule 40E-4.301(1) are in dispute and require an applicant to provide reasonable assurances that the construction, alteration, operation, maintenance, removal, or abandonment of a surface water management system: will not cause adverse impacts to existing surface water storage and conveyance capabilities; will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters; will not adversely affect the quality of receiving waters such that the water quality standards set forth in chapters 62- 4, 62-302, 62-520, 62-522, 62-550, F.A.C., including any anti-degradation provisions of paragraphs 62-4.242(1)(a) and (b), subsections 62-4.242(2) and (3), and rule 62-302.300, F.A.C., and any special standards for Outstanding Florida Waters and Outstanding National Resource Waters set forth in subsections 62-4.242(2) and (3), F.A.C., will be violated; will not cause adverse secondary impacts to the water resources; will be capable, based on generally accepted engineering and scientific principles, of being performed and of functioning as proposed; will be conducted by an entity with sufficient financial, legal and administrative capability to ensure that the activity will be undertaken in accordance with the terms and conditions of the permit, if issued; These disputed criteria are discussed separately below. Surface Water Storage and Conveyance Rule 40E-4.301(1)(c) requires that an applicant provide reasonable assurances that a proposed activity will not cause adverse impacts to existing surface water storage and conveyance capabilities. Through unrefuted evidence, this requirement was shown to be satisfied. The evidence also establishes that the surface water in and around the Project will actually improve if the Project is constructed as permitted. Further, it will create improved and upgraded surface water management and treatment in areas that now lack features such as swales, retention/detention ponds, curbs and gutters, and improve the overall surface water storage and conveyance capabilities of the Project and surrounding areas. In its current pre-development condition, flooding has occurred in certain areas adjacent to and within the Project area due to poor conveyance, low storage volume, and high tailwater conditions that result from high tides. The Project will remedy historic flooding issues in the Old Palm City area which lies adjacent to a portion of the Project alignment. Surface water runoff will be captured, controlled, and treated by a system of swales, weirs, and retention/detention facilities for pretreatment prior to discharging into the South Fork of the St. Lucie River. Reasonable assurances have been given that existing surface water storage and conveyance capabilities will not be adversely affected. Value of Functions to Fish, Wildlife, and Species Rule 40E-4.301(1)(d) requires that an applicant provide reasonable assurances that a proposed activity will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters. BOR Section 4.2.2 further implements this provision. For the following reasons, the rule and BOR have been satisfied. The evidence shows that the existing functions to fish and wildlife were assessed and analyzed by a number of federal and state fish and wildlife agencies. There were extensive review and site inspections by the District, DOT, United States Fish and Wildlife Service, United States Army Corps of Engineers, and National Marine Fisheries Commission to assess the existence of, and potential impact on, fish and wildlife that may result from the Project. These studies revealed that while portions of the South Fork of the St. Lucie River provide potential habitat for aquatic or wetland-dependent or threatened species of special concern, no nesting or roosting areas within the vicinity of the Project were observed. The evidence further supports a finding that "other surface waters" over and under the Project will not receive unacceptable impacts due to their current condition, the detrimental influences of Lake Okeechobee discharges, and tidal impacts. Many of the wetlands to be impacted by the Project were shown to have been impacted by historic activities, and they provide diminished functions to fish and wildlife. The wetland functions were assessed through the Uniform Mitigation Assessment Methodology (UMAM). The UMAM is a standardized procedure for assessing the functions provided by wetlands and other surface waters, the amount that those functions would be reduced by a proposed project, and the amount of mitigation necessary to offset that loss. Detailed UMAM assessments were prepared by the Applicants and the District. They demonstrate that while certain functional units will be lost, they will be fully offset by the proposed mitigation. No credible evidence to the contrary was presented. Water Quality of Receiving Waters Rule 40E-4.301(1)(e) requires an applicant to provide reasonable assurances that a project will not adversely affect the quality of receiving waters such that State water quality standards will be violated. BOR Section 4.2.4 implements this rule and requires that "reasonable assurances regarding water quality must be provided for both the short term and long term, addressing the proposed construction, . . . [and] operation of the system." The receiving water body is the South Fork of the St. Lucie River, which is designated as an impaired water body. The evidence establishes that the Applicants will avoid and minimize potential short-term impacts to water quality by using silt screens and turbidity barriers, and implementing other best management practices to contain turbidity during construction of the Project. They will also use a temporary trestle rather than barges in the shallow portions of the South Fork to avoid stirring up bottom sediments. Finally, a turbidity monitoring plan will be implemented during construction and dewatering activities for all in-water work. All of these construction techniques will minimize potential impacts during construction. The evidence further establishes that water quality standards will not be violated as a result of the Project. In fact, in some cases water quality will be enhanced due to the installation and maintenance of new or upgraded surface water management features in areas where they do not exist or have fallen into disrepair. Over the long term, the Project is expected to have a beneficial effect on water quality. By improving existing surface water management and adding new surface water treatment features, the Project will provide net improvement to water quality. Wetland Delineation and Impacts The Project includes unavoidable impacts to wetlands and other surface waters. A total of 18.53 acres of wetlands and other surface waters within the Project site will be impacted by the Project, including 3.83 acres of wetlands that will be directly impacted and 14.7 acres of wetlands and other surface waters that will be secondarily impacted. The delineated wetlands are depicted in the Staff Report as wetlands 2a, 19a, 19b, 22, 25-29, 30a, 30b, and 30c, with each having a detailed UMAM assessment of its values and condition. (Impacts to wetland 25 are not included in this Project because they were accounted for in a separate permit proceeding.) Using a conservative assessment and set of assumptions, the District determined that, with the exception of wetlands 19a, 19b, 22, and 27, all wetlands would be impacted by the Project. However, the wetlands that would be impacted suffer from varying historical adverse impacts that have compromised the functions and values they provide to fish, wildlife, and species. This is due to their proximity to urban development, vegetative connectivity, size, historic impacts, altered hydroperiod, and invasive plant species. Likewise, even though the wetlands to be impacted on Kiplinger Island provide certain resting and feeding functions for birds, the value of these functions is comparatively lower than other wetlands due to the presence of invasive species and lack of management. The preponderance of the evidence supports a finding that the Applicants provided reasonable assurances that the Project will not cause adverse impacts to fish, wildlife, or listed species. See Fla. Admin. Code R. 40E-4.301(1)(d). Secondary Impacts Rule 40E-4.301(1)(f) and BOR Sections 4.1.1(f) and 4.2.7. require a demonstration that the proposed activities will not cause adverse secondary impacts to the water resources, both from a wetlands and water quality standpoint. Secondary impacts are those that occur outside the footprint of the project, but which are very closely linked and causally related to the activity to be permitted. De minimis or remotely-related secondary impacts, however, are not considered unacceptable. See § 4.2.7.(a). There will be secondary impacts to 6.83 acres of freshwater wetlands and 7.87 acres of mangroves, or a total of 14.7 acres. To address these secondary impacts, the Applicants have established extensive secondary impact zones and buffers along the Project alignment, which were based in part on District experience with other road projects and another nearby proposed bridge project in an area where a State Preserve is located. While Petitioners' expert contended that a 250-foot buffer on both sides of the roadway's 200-foot right-of-way was insufficient to address secondary impacts to birds (who the expert opines may fly into the bridge or moving vehicles), the greater weight of evidence shows that bird mortality can be avoided and mitigated through various measures incorporated into the Project. Further, the bird mortality studies used by the expert involved significantly different projects and designs, and in some cases involved projects outside the United States with different species concerned. Engineering and Scientific Principles Rule 40E-301(1)(i) requires that an applicant give reasonable assurance that a project "be capable, based on generally accepted engineering and scientific principles, of being performed and of functioning as proposed." Unrefuted evidence establishes that the proposed system will function and be maintained as proposed. Financial, Legal and Administrative Capability Rule 40E-4.301(1)(j) requires that an applicant give reasonable assurance that it has the financial, legal, and administrative capability to ensure that the activity will be undertaken in accordance with the terms of the permit. The evidence supports a finding that Applicants have complied with this requirement. Elimination and Reduction of Impacts Before establishing a mitigation plan, Rule 40E- 4.301(3) requires that an applicant implement practicable design modifications to eliminate and reduce wetland and other surface water impacts. In this case, there are unavoidable, temporary wetland impacts associated with the construction of the Project, as well as unavoidable wetland impacts for direct (project footprint), secondary, and cumulative impacts of the Project. The record shows that the Applicants have undertaken extensive efforts to eliminate and reduce wetland and other surface water impacts of the Project. For example, DOT examined and assessed several innovative construction techniques and bridge designs to eliminate and avoid wetland impacts. To eliminate and reduce temporary impacts occurring during construction, DOT has reduced the effect of scour on the pier foundation and reduced the depth of the footing to minimize the amount of excavation on the mangrove island. Also, during construction, the contractor is prohibited from using the 200- foot right-of-way on the mangrove island for staging or stockpiling of construction materials or equipment. The majority of the bridge width has been reduced to eliminate and avoid impacts. Also, the Project's alignment was adjusted to the north to avoid impacts to a tidal creek. Reasonable assurances have been given that all practicable design and project alternatives to the construction and placement of the Project were assessed with no practicable alternatives. Public Interest Test Besides complying with the requirements of Rule 40E- 4.301, an applicant must also address the seven factors in Rule 40E-4.302(1)(a)1.-7., which comprise the so-called "public interest" test. See also § 373.414(1)(a), Fla. Stat. In interpreting the seven factors, the District balances the potential positive and negative effects of a project to determine if it meets the public interest criteria. Because Petitioners agree that factors 3 and 6 of the rule are not at issue, only the remaining five factors will be considered. For the following reasons, the Project is positive when the criteria are weighed and balanced, and therefore the Project is not contrary to the public interest. Public Health, Safety, and Welfare The Applicants have provided reasonable assurance that the Project will not affect public health, safety, and welfare. Specifically, it will benefit the health, safety, and welfare of the citizens by improving traffic conditions and congestion, emergency and hurricane evacuation, and access to medical facilities. In terms of safety, navigation markers are included as part of the Project for safe boating by the public. See Fla. Admin. Code R. 40E-4.302(1)(a)1. Conservation of Fish and Wildlife The activity will not adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats. The mitigation projects will offset any impacts to fish and wildlife, improve the abundance and diversity of fish and wildlife on Kiplinger Island, create mangrove habitat, and add to the marine productivity in the area by enhancing water quality. See Fla. Admin. Code R. 40E-302(1)(a)2. Fishing or Recreational Values The Project has features that allow for pedestrian and bicycle utilization and observation areas which should enhance recreational values. The Old Palm Bridge, approximately one mile north of the Project, has had no adverse impact on the fishing recreation along the South Fork of the St. Lucie River. Navigation will not be affected due to the height and design of the new bridge. Finally, the bridge is expected to be a destination for boating, kayaking, fishing, and bird watching. See Fla. Admin. Code R. 40E-4.302(1)(a)4. Whether the Activity is of a Permanent Nature The parties have stipulated that the Project is permanent in nature. No future activities or future phases of the project are contemplated. Temporary and permanent impacts are all being fully mitigated. See Fla. Admin. Code R. 40E- 4.302(1)(a)5. Values of Functions Being Performed in Affected Areas Due to historic impacts to the areas affected by the Project, the current condition is degraded and the relative value of functions is minimal. Although Kiplinger Island will have temporary impacts, that island is subject to exotic species and has no recreational use or access by boaters or members of the public. The Applicants propose mitigation which will improve and enhance these wetland functions and values in the areas. See Fla. Admin. Code R. 40E-4.302(1)(a)7. Summary The evidence supports a finding that the Project is positive as to whether it will affect the public health, safety, welfare, or property of others; that the Project is neutral with respect to navigation, erosion and shoaling, and water flow, as well as to historical and archaeological concerns; and that the Project is positive as to conservation of fish, wildlife, recreational values, marine productivity, permanency, and current values and functions. When weighed and balanced, the Project is not contrary to the public interest. Cumulative Impacts Rule 40E-4.302(1)(b) requires that an applicant give reasonable assurance that a project will not cause unacceptable cumulative impacts upon wetlands and other surface waters as set forth in BOR Sections 4.28 through 4.2.8.2. Cumulative impacts are the summation of unmitigated wetland impacts within a drainage basin. An analysis is geographically based upon the drainage basins described in BOR Figure 4.4.1. Petitioners' contention that Figure 4.4.1 is inaccurate or not representative of the basin in which the Project is located has been rejected. In this case, the North St. Lucie Basin was used. To assess and quantify any potential unacceptable cumulative impacts in the basin, and supplement the analyses performed by the Applicants, the District prepared a Basin Map that depicted all the existing and permitted wetland impacts as well as those wetlands under some form of public ownership and/or subject to conservation restrictions or easements. The District's analysis found that the wetlands to be mitigated were of poor quality and provided minimal wildlife and water quality functions. Cumulative impacts from the Project to wetlands within the basin resulted in approximately a four percent loss basin-wide. This is an acceptable adverse cumulative impact. Therefore, the Project will not result in unacceptable cumulative impacts. Mitigation Adverse impacts to wetlands caused by a proposed activity must be offset by mitigation measures. See § 4.3. These may include on-site mitigation, off-site mitigation, off- site regional mitigation, or the purchase of mitigation credits from mitigation banks. The proposed mitigation must offset direct, secondary, and cumulative impacts to the values and functions of the wetlands impacted by the proposed activity. The ability to provide on-site mitigation for a DOT linear transportation project such as a bridge is limited and in this case consists of the creation of mangrove and other wetlands between the realigned St. Lucie Shores Boulevard and the west shore of the St. Lucie River, north and south of the proposed bridge crossing. BOR Section 4.3.1.2 specifically recognizes this limitation and allows off-site mitigation for linear projects that cannot effectively implement on-site mitigation requirements due to right-of-way constraints. Off-site mitigation will offset the majority of the wetland impacts. Because no single on-site or off-site location within the basin was available to provide mitigation necessary to offset all of the Project's impacts, DOT proposed off-site mitigation at two established and functioning mitigation areas known as Dupuis State Reserve (Dupuis), which is managed by the County and for which DOT has available mitigation credits, and the County's Estuarine Mitigation Site, a/k/a Florida Oceanographic Society (FOS) located on Hutchinson Island. Dupuis is outside the North St. Lucie Basin and was selected to offset direct and secondary impacts to freshwater wetlands. That site meets the ERP criteria in using it for this project. The FOS is within the North St. Lucie Basin and was selected to offset direct and secondary impacts to estuarine wetlands. Like Dupuis, this site also meets the ERP criteria for the project. The preponderance of the evidence establishes that the on-site and off-site mitigation projects fully offset any and all project impacts, and in most instances before the impacts will actually occur. Sovereign Submerged Lands and Heightened Public Concern Chapter 18-21 applies to requests for authorization to use sovereign submerged lands. The management policies, standards, and criteria used to determine whether to approve or deny a request are found in Rule 18-21.004. For purposes of granting a public easement to the Applicants, the District determined that the Project is not contrary to the public interest and that all requirements of the rule were satisfied. This determination was not disputed. The only issue raised by Petitioners concerning the use of submerged lands is whether the application should have been treated as one of "heightened public concern." See Fla. Admin. Code R. 18-21.0051(5). If a project falls within the purview of that rule, the Board of Trustees of the Internal Improvement Trust Fund (Board), rather than the District, must review and approve the application to use submerged lands. Review by the Board is appropriate whenever a proposed activity is reasonably expected to result in a heightened public concern because of its potential effect on the environment, natural resources, or controversial nature or location. Id. In accordance with established protocol, the ERP application was sent by the District to DEP's review panel in Tallahassee (acting as the Board's staff) to determine whether the Project required review by the Board. The panel concluded that the Project did not rise to the level of heightened public concern. Evidence by Petitioners that "many people" attended meetings and workshops concerning the Project over the last 20 years or so is insufficient to trigger the rule. Significantly, except for general project objections lodged by Petitioners and Audubon of Martin County, which did not include an objection to an easement, no adjacent property owner or other member of the public voiced objections to the construction of a new bridge. Revised Staff Report On October 20, 2010, the District issued a Revised Staff Report that merely corrected administrative errors or information that had been previously submitted to the District. Contrary to Petitioners' assertion, it did not constitute a material change to the earlier agency action either individually or cumulatively. Therefore, it was properly considered in this proceeding. Letter Modifications The Letter Modifications were used as a mechanism to capture minor alterations made to previously issued permits for Kanner Highway and Indian Street. Neither Letter Modification is significant in terms of water quality, water quantity, or environmental impacts. Both were issued in accordance with District rules and should be approved.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the South Florida Water Management District enter a final order granting Application Nos. 091021-8, 100316-7, and 100316-6. DONE AND ENTERED this 28th day of December, 2010, in Tallahassee, Leon County, Florida. S D. R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 28th day of December, 2010. COPIES FURNISHED: Carol Ann Wehle, Executive Director South Florida Water Management District 3301 Gun Club Road West Palm Beach, Florida 33406-3007 Jeffrey W. Appel, Esquire Ray Quinney and Nebeker, P.C. 36 South State Street, Suite 1400 Salt Lake City, Florida 84111-1401 Bruce R. Conroy, Esquire Department of Transportation 605 Suwannee Street Mail Station 58 Tallahassee, Florida 32399-0458 David A. Acton, Esquire Senior Assistant County Attorney Martin County Administrative Center 2401 Southeast Monterey Road Stuart, Florida 34996-3397 John J. Fumero, Esquire Rose, Sundstrom & Bentley, P.A. 950 Peninsula Corporate Circle Suite 2020 Boca Raton, Florida 33487-1389 Keith L. Williams, Esquire South Florida Water Management District 3301 Gun Club Road Mail Stop 1410 West Palm Beach, Florida 33406-3007