TRAFALGAR DEVELOPERS OF FLORIDA, INC. vs. SOUTHWEST FLORIDA REGIONAL PLANNING COUNCIL, 75-001299 (1975)
Division of Administrative Hearings, Florida Number: 75-001299 Latest Update: Oct. 29, 1990

Findings Of Fact Mr. George Szell was presented by the Southwest Florida Water Management District and sworn as a witness. Mr. Szell was qualified and accepted as an expert hydrogeologist employed by the District. Included within Mr. Szell's responsibilities to the District were evaluation of the subject application. An application for consumptive use permit has been filed in proper from by Trafalgar Developers of Florida, Inc., and it was admitted into evidence as Exhibit 1. The water source are two existing wells located on a 580.1 acre tract of land in Hillsborough County, Florida, legal description of which is included and admitted into evidence as part of Exhibit 1. A maximum daily withdrawal of each of the wells is 591,700 gallons and the average daily withdrawal of each of the two wells is 295,850 gallons. The total average daily withdrawal for both wells combined is 591,700 gallons, or 94.43 percent of the water crop of the applicant as defined in Section 16J-2.11(3), F.A.C. 85 percent of the water used would be used for general residential purposes and 15 percent of the water used would be used for watering the grounds of the development. Letters of objection were received from Joseph and Roseamn Clements, C. C. and Ida M. Weisner, Sr.,. Miguel and Juanita Perez, Howard R. Lewis, Mr. and Mrs. Lonnie F. Lovell, Stephen J. KucIar (sic), and Carmen Vasquez. Reasons for the objections as stated in these letters was the effect the pending application would have upon the wells of the persons objecting. Mr. Szell testified that none of the matter set forth in Subsection 16J-2.11(2), (3) and (4), F.A.C. exists so as to require the denial of the permit. Mr. Earl Bessent testified that 55 acres of holding ponds were to be constructed on the property during the development and that the effect of these holding ponds would be to increase the input of waters from the 580 acres to the surface aquifer.

Recommendation It is recommended that Application No. 7500087, submitted by Trafalgar Developers of Florida, Inc., 111 Fountainbleau Boulevard, Miami, Florida, be granted for a maximum daily withdrawal of 1,183,400 gallons and an average daily withdrawal of 591,700 gallons, subject to the installation of flow meters on each of the wells and monthly readings thereof reported to the District quarterly. Entered this 4th day of August, 1975, in Tallahassee, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: J. T. Ahern, Esquire C. C. and Ida Weismer, Sr. Staff Attorney Route 7, Box 635-J Southwest Florida Water Tampa, Florida 33614 Management District Post Office Box 457 Miguel and Juanita Perez Brooksville, Florida 33501 Route 7, Box 635-K Tampa, Florida 33614 Trafalgar Developers of Florida, Inc. Mr. and Mrs. Lonnie Lovell 111 Fountainbleau Boulevard Route 5, Box 485-A Miami, Florida 33126 Tampa, Florida 33614 Howard R. Lewis Carmen Vasquez Route 5, box 485-AB Route 7, Box 635 Tampa, Florida 33614 Tampa, Florida 33615 Mr. Earl Bessent Bessent, Hammack & Ruckman, Inc. 3708 Swann Avenue Tampa, Florida 33609 Joseph and Roseann Clememts Route 7, Box 634-J Tampa, Florida 33614

# 1
BROOKSVILLE ASSOCIATES vs SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT, 92-007064 (1992)
Division of Administrative Hearings, Florida Filed:Brooksville, Florida Nov. 25, 1992 Number: 92-007064 Latest Update: Aug. 20, 1993

Findings Of Fact The Parties and the Property. The Respondent, HORNE, owns or has options to purchase approximately 24.35 acres of real property at the southwest corner of U.S. Highway 41 and State Road 50 Bypass in Brooksville, Florida. The Petitioner, the ASSOCIATES, owns approximately 67.5 acres of real property to the south and downstream from the HORNE property. The ASSOCIATES' property is presently undeveloped. The HORNE property contains an existing Publix shopping plaza, a mobile home sales office and vacant lands. The Publix plaza was previously permitted by the DISTRICT before it was constructed. The Surface Water Permit Application On August 7, 1992, HORNE submitted its application for surface water permit No. 400317.02. The application sought approval to construct a surface water management system for a proposed new K-Mart store on HORNE's property. On November 3, 1992, the DISTRICT issued notice of final agency action approving issuance of permit No. 400317.02 to HORNE. The day before the original final hearing in this matter scheduled for March 1993, new information from a study called the Peck Sink Watershed Study came to light which rendered the project as then designed unpermittable. This information resulted in the surface water management system being redesigned. On April 1, 1993, the DISTRICT notified all of the parties that the redesigned surface water management met District rule criteria. This resulted in issuance of what became known as the April 1 submittal. On May 12, 1993, in response to concerns raised by the ASSOCIATES at depositions on May 10, 1993, HORNE produced the May 12 submittal and provided it to all parties on that same date. The changes in design reflected on the May 12 submittal related to lowering the pond bottoms one foot below the orifices and changing the contour lines on the outside of Pond 5A. On May 13, 1993, further minor changes were made to the permit materials. Specifically, the changes were: reflecting on the engineering worksheets the lowering of the pond bottoms accomplished on the May 12 submittal, correction of the contour line on the outside of Pond 5A and showing the amount of additional fill into the 100-year floodplain caused by the addition of the contour line to the outside of Pond 5A. In reviewing HORNE's application, the District applied the standards and criteria set forth in Chapter 40D-4, Florida Administrative Code, and the Basis of Review for Surface Water Management Permit Applications. Compliance with DISTRICT Permitting Criteria Water Quantity The main two areas considered by the DISTRICT in assessing water quantity in a closed basin are: attenuating the peak rate of discharge for the 25 runoff for the 100 The peak rate of runoff for this project for the 25 (2) cubic feet per second (cfs) less in the post-developed condition than in the pre-developed condition, as shown on the April 1 submittal. No changes were made between the April 1 and May 12 or 13 submittals relating to the peak rate of discharge. The difference in the volume of runoff between the pre-developed and post-developed condition during the 100-year storm is being retained on site, as shown on the April 1 submittal. Therefore, DISTRICT rule criteria for the peak rate and volume of runoff were met on the April 1 submittal. Lowering the bottoms of the detention ponds on the May 12 and 13 submittals resulted in additional post 100 system, as redesigned to retain this additional 100-year volume, exceeds the DISTRICT's 100 Floodplain Encroachment Under the DISTRICT's floodplain encroachment standards, any fill within the 100 out an equivalent volume of fill elsewhere on the property. HORNE's application satisfies the DISTRICT's floodplain standards. HORNE is filling 1.59 acre feet of the floodplain and creating 1.75 acre feet of compensation. The floodplain compensation will be above the seasonal high water table, as required by Section 3.2.1.4 of the DISTRICT's Basis of Review. The original, existing seasonal high water table will be lowered as a result of the excavation so that the entire floodplain compensation area will be above the seasonal high water table. Water Quality A wet detention system as proposed by HORNE is an acceptable means under the DISTRICT's rules of treating runoff for water quality purposes. The bottoms of the ponds, as shown on the May 12 submittal, are all at least one foot below the orifice elevations, as required by the Basis of Review. Thus, the project met all relevant DISTRICT water quality requirements as of the May 12 submittal. Operation and Maintenance DISTRICT rules require that reasonable assurances be provided that the surface water management system can be effectively operated and maintained. HORNE will be the operation and maintenance entity for this surface water management system. The DISTRICT's main concerns at the time of permit review are that the design of the surface water management system not be an exotic design, that the design insure that littoral zones can be established, that the system orifice can be cleaned, that the overall system will be stable and that there is a viable operation and maintenance entity. HORNE's project can be effectively operated and maintained. Remaining District Rule Criteria As stipulated to by the parties that the project will not cause adverse impacts to wetlands and will not diminish the capability of a lake or other impoundment to fluctuate through the full range established for it in Chapter 40D Additionally, the proof establishes that the project will not cause adverse impacts on surface and groundwater levels and flows will not adversely affect the public health and safety; is consistent with the requirements of other public agencies; will not otherwise be harmful to the water resources within the District; will not interfere with the legal rights of others as defined in Rule 17 Objections Raised by the ASSOCIATES at the Hearing Pond Slopes and Operation and Maintenance Contrary to the assertion that the pond slopes will not be stable and cannot be effectively operated and maintained, the pond side slopes at this project are going to be constructed out of a heavy clay type of soil. Sodded side slopes of 1:1, as proposed for three of the ponds, can be stabilized and effectively operated and maintained. Although there is no DISTRICT requirement that sodded side slopes be mowed, so on these slopes could, if necessary, be cut. In the event the side slopes were to erode, easy repair is possible. All of the ponds except one side of one pond have areas at least 20 feet wide and slopes no steeper than 4:1 where maintenance can be performed. With regard to the pond that does not have this characteristic, equipment can enter and perform necessary maintenance. Water Quality Treatment Concerns that at least a portion of the bottoms of the ponds need to be below the seasonal high water table and that circulation of the ponds needs to be maximized in order to meet water quality treatment criteria are misplaced since there is no requirement that the pond bottoms be below the seasonal high water table in wet detention systems such as the one at issue in this case. Further, the entire bottoms of the ponds are littoral zone and meet DISTRICT rule requirements that 35 per cent of the pond be littoral zone, concentrated at the outfall. Additionally, the ponds at issue maximize circulation through the location of points of inflow and outflow. Floodplain Mitigation Concerns that volume in the floodplain mitigation area is not available because of problems with the seasonal high water table are also misplaced. Specifically, the floodplain area encroachment requiring mitigation relates to Pond 5A. There is more than enough volume within the area which will be excavated to compensate for the area where the fill will be deposited. The seasonal high water table will be at or below the floodplain mitigation area after the required excavation takes place. Although the seasonal high water table will be lowered where the excavation or cut is made and later raised where the fill is placed, no adverse effects on the water table will result from such lowering and raising of the water table. Volume In Pond 5A Allegations that the May 12 and 13 submittals reflect that Pond 5A has less volume available than the modeling calculations contemplate are incorrect. The changes in the contour lines of Pond 5A on the May 12 and 13 submittals from what was shown on the April 1 submittal occurred on the outside of the pond. The volume on the inside of the pond was not reduced actually increased when the pond bottom was lowered for water quality purposes. In determining how much volume a pond is to have when it is constructed, the computer modeling figures take precedence over the scaled plan drawings. In this case, the computer modeling figures never changed after the April 1 submittal. HORNE submitted a computer model that calculated the volume of Pond 5A. The output data clearly reflects that the top of the bank was 82 feet. Publix's Status as an Existing Site Assertions that the Publix site should have been considered in its pre-developed state since there will be approximately one acre foot of volume of runoff, or possibly less, leaving the site without retention are without validity. The Publix plaza was permitted by the DISTRICT in 1985 and constructed in 1986. The amount of peak flow discharge and overall discharge is currently authorized by a valid MSSW permit. When the DISTRICT reviews a permit application, all existing permitted surface water management systems must be accepted in their present state. There is no authority in the DISTRICT's rules to consider an existing permitted site in its pre Even if the Publix site is considered in its pre project has only .02 of an acre foot more volume of runoff in its post-developed condition than in the pre Storage of 100-Year Volume Allegations that the amount of 100-year volume being retained on site in the ponds has been incorrectly calculated by the DISTRICT and HORNE are also invalid. The DISTRICT's rules require that the difference between the pre- and post-development volume for the 100-year storm be retained on site. In the ponds which are the subject of this proceeding, the 100-year volume is retained in the ponds below the orifice. This volume cannot leave the site through the orifice; it can only leave the site by percolation into the ground or evaporation into the air.

Recommendation Based on the foregoing, it is recommended that the Southwest Florida Water Management District enter a final order granting HORNE's Application for Surface Water Management Permit No. 400317.02. RECOMMENDED this 25th day of June, 1993, in Tallahassee, Florida. DON W. DAVIS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 25th day of June, 1993. APPENDIX The following constitutes my rulings, in accordance with Section 120.59, Florida Statutes, on proposed findings of fact submitted by the parties Proposed findings submitted by Petitioners (Petitioner's proposed findings begin at paragraph number 13.) 13.-19. Accepted. 20.-30. Rejected, unnecessary. 31.-44. Rejected, subordinate to hearing officer findings. 45.-47. Accepted. 48.-77. Rejected, subordinate to hearing officer findings. 78.-79. Rejected, recitation of documents. 80.-84. Rejected, weight of the evidence. 85.-88. Rejected, unnecessary. 89.-93. Rejected, weight of the evidence. 94.-95. Rejected, unnecessary. 96. Accepted. 97.-98. Rejected, subordinate, weight of the evidence. 99.-100. Rejected, unnecessary. 101.-126. Rejected, subordinate. 127. Accepted. 128.-129. Rejected, unnecessary. 130.-135. Rejected, argument. 136.-144. Rejected, weight of the evidence. Respondents Joint Proposed Findings. 1.-56. Accepted, though not verbatim. 58.-59. Rejected, unnecessary. COPIES FURNISHED: David Smolker, Esquire Honigman, Miller, Schwartz & Cohn 2700 Landmark Centre 401 East Jackson Street Tampa, Florida 33602 Rodney S. Fields, Jr., Esquire Blain & Cone, P.A. 202 Madison Street Tampa, Florida 33602 Richard Tschantz, Esquire Mark F. Lapp, Esquire Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609 Peter G. Hubbell Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, FL 34609-6899

Florida Laws (1) 120.57 Florida Administrative Code (1) 40D-4.301
# 2
JAMES SARTORI, D/B/A WILLOWBROOK FARMS vs. ST. JOHNS RIVER WATER MANAGEMENT DISTRICT, 81-002393RX (1981)
Division of Administrative Hearings, Florida Number: 81-002393RX Latest Update: Nov. 24, 1981

Findings Of Fact On December 31, 1976, Respondent's territorial jurisdiction was expanded by transfer of substantial areas formerly regulated by other water management districts. The transfer was effected pursuant to legislative revision of Section 373.069, F.S., which delineates the geographic boundaries of Florida's water management districts. The following rule promulgated by Respondent became effective on January 31, 1977, and was amended on February 3, 1981: 40C-4.031 (previously 16I-4.04, Florida Administrative Code). Implementation. These regulations shall become effective February 1, 1981, throughout the District and will be implemented in those areas transferred to the St. Johns River Water Management District from the Central & Southern Florida Flood Control District and the Southwest Florida Water Management District on the same date. Implementation in other areas will be effected pursuant to public hearing at subsequent dates determined by the Board. The regulations implemented by the above rule establish permitting procedures for projects which involve holding, diversion, or discharge of significant quantities of water. However, permits are required only in the transferred territory. Petitioner owns 11,500 acres located within the territory where permits are required. Petitioner seeks to improve his property for agricultural purposes, which involves the holding and diversion of surface waters. He has accepted Respondent's determination that his property is within the permitting area and has filed the requisite application. However, Petitioner contends that he is unable reasonably to confirm Respondent's determination that his property is situated in the regulated territory. Respondent demonstrated that a determination can be made by comparing the statutory descriptions of Respondent's jurisdiction prior to and after the transfer, and has maps available which reflect the permitting area. To accomplish this task independently requires knowledge of legal territorial descriptions (section, township, range) and a laborious comparison of legal descriptions set out in the 1975 and 1977 versions of the Florida Statutes. At the time reorganization of the water management districts became effective (December 31, 1976) , Respondent had limited regulatory capability. Its decision to implement permitting only in the transferred territory was based on this limited capability and the need to preserve continuity 1/ in areas where permits had previously been required. In the years following this decision, Respondent has continued to require permits only in those areas transferred in 1976. The evidence established that the boundary between the regulated and unregulated areas is one of convenience and has no hydrological or other scientific basis. Respondent is considering a revision of its rules to become effective sometime in 1982. This revision may enlarge the permitting territory and modify the criteria for grant or denial of permits. Petitioner asserts that his application is being evaluated by rules not yet adopted and fears that new standards may be applied after hearing on the application, which is now under consideration pursuant to Subsection 120.57(1), F.S., (DOAH Case No. 81-1588). Hearing is scheduled for December, 1981. In support of this contention, Petitioner points to the technical staff report prepared in May, 1981, which recommends denial of the application giving, among others, the following reasons: Volumes 1 and 2 of Phase 1 of the Upper Basin Plan catalogue a history of a diminish- ing water resource in the upper basin. The water resources in the upper basin have been harmed and the proposed project aggravates the existing harm to the resource. Moreover the proposed project is inconsistent with the overall objectives of the district for the upper basin. Resolutions 75-11 and 81-2, the 1977 Management Plan, and Volumes 1 and 2 of Phase I of the Upper Basin Plan indicate that the objectives of the District are to curtail inter-basin diversion and maintain and enhance, if possible, the existing hydro- logic regime in the upper basin. The pro- posed project is not in conformance with either of these statutory requirements. (Emphasis added.) An earlier technical staff report prepared in November, 1980, recommended grant of the application, with some modification. This report did not refer to inter-basin diversion.

Florida Laws (7) 120.52120.54120.56120.57373.069373.113373.413 Florida Administrative Code (2) 40C-4.03140C-4.301
# 3
CITY OF BRADENTON vs SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT, 92-007161 (1992)
Division of Administrative Hearings, Florida Filed:Bradenton, Florida Dec. 04, 1992 Number: 92-007161 Latest Update: Jul. 05, 1994

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant findings of fact are made:

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that the District enter a Final Order denying the City's petition for a variance from the established lawn and landscape irrigation restrictions imposed under the District's Governing Board Order 92-12, as amended. RECOMMENDED this 31st day of May, 1994, at Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of May, 1994. APPENDIX TO RECOMMENDED ORDER, CASE NO. 92-7161 The following constitutes my specific rulings, pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the parties in this case. Petitioner, City of Bradenton 1. The following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 1(7); 2(10); 3(12); 4(11); 6(13); 8-9(3); 12(15a); 16(3); 17(37); 19(38); 23-24(39); 48(40); 49(44); 50,51(42), 53-65(42), 67-70(42); 71(41); 72(42); 76(15a); 77-78(15b); 81- 82(15c); 84(15a); 101(17); 107-119(20-21); 120-126(22-27); 127-131(28); 132- 139(29); 140(25-28); 141(20-24); 142(23-24); 143(47); and 145-146(41). 2. Proposed findings of fact 5, 10, 11, 13-15, 18, 20-22, 25-32, 35-47, 52, 66, 73-75, 79, 80, 83, 85, 87-95, 97, 99, and 102-106 are either immaterial, irrelevant, subordinate or unnecessary. Proposed finding of fact 7 is covered in the Preliminary Statement. Proposed findings of fact 33, 34, 86, 96, 98, and 100 are not supported by competent substantial evidence in the record. Respondent, Southwest Florida Water Management District The following proposed finding(s) of fact are adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding(s) of Fact which so adopts the proposed finding of fact: 1(7); 2(9); 3(7,8); 4(10,12); 5(4); 6(15); 7-8(6); 9(18); 10(17); 11-12(19); 13(20); 14(21); 16(22,23); 17(23,24); 18(25); 19(26); 20(27); 21-22(28); 24(47); 25(46); 26(29); 27(29); 28(30,35); 29-31(31); 32(45); 33(32); 34(33); 35(34); 36(36); 37(37,39); 38(40); 39(41); 40(43); 41(42); 42(43); and 43(44). Proposed findings of fact 15, 23 and 44 are not supported by competent substantial evidence in the record. COPIES FURNISHED: Barbara B. Levin, Esquire Davis, Persson, Smith & Darnell 2033 Main Street, Suite 406 Sarasota, Florida 34237 William Lisch, Esquire 519 13th Street West Bradenton, Florida 34205 James A. Robinson, Esquire Mark F. Lapp, Esquire Southwest Florid Water Management District 2379 Broad Street Brooksville, Florida 34609-6899 Peter G. Hubbell Executive Director Southwest Florida Water Management District 2379 Broad Street Brooksville, Florida 34609-6899

Florida Laws (7) 120.57120.68373.044373.113373.114373.246373.617 Florida Administrative Code (2) 40D-21.60140D-21.641
# 4
ANGELO`S AGGREGATE MATERIALS, LTD. vs SUWANNEE RIVER WATER MANAGEMENT DISTRICT, 01-004383RX (2001)
Division of Administrative Hearings, Florida Filed:Live Oak, Florida Nov. 09, 2001 Number: 01-004383RX Latest Update: Oct. 22, 2002

The Issue Whether Rules 40B-1.702(4); 40B-4.1020(12) and (30); 40B-4.1030; 40B-4.1040(1)(b) and (c); 40B-4.2030(4); 40B-4.3000(1)(a); 40B-4.3010; 40B-4.3020; 40B-4.3030; 40B- 4.3040; and 40B-400.103(1)(h), Florida Administrative Code, of the Suwannee River Water Management District, are an invalid exercise of delegated legislative authority for reasons described in the Second Amended Petition to Determine Validity of Rules.

Findings Of Fact Stipulated Facts Angelo's is a Florida Limited Partnership, whose address is 26400 Sherwood, Warren, Michigan 48091. The District is an agency of the State of Florida established under Chapter 373, Florida Statutes, with its address at 9225 County Road 49, Live Oak, Florida 32060. Angelo's owns property in Hamilton County approximately four miles to the east of Interstate 75 and to the north of U.S. Highway 41, immediately to the east of the Alapaha River. Angelo's conducts commercial sand mining operations on a portion of its property pursuant to various agency authorizations, including an Environmental Resource Permit (ERP) issued by the Florida Department of Environmental Protection (Department), Permit No. 158176-001, and a Special Permit issued by Hamilton County, SP 98-3. The ERP was issued by the Department pursuant to its authority under Chapter 373, Part IV, Florida Statutes. Angelo's mining operations constitute a "mining project" as that term is used in Section II.A.1.e of an Operating Agreement Concerning Regulation under Part IV, Chapter 373, Florida Statutes, and Aquaculture General Permits under Section 403.814, Florida Statutes, between the District and the Department (Operating Agreement). The Operating Agreement has been adopted as a District rule pursuant to Rule 40B-400.091, Florida Administrative Code. Angelo's has filed with the Department an application to modify its ERP to expand its sand mining operations into an area of its property immediately to the west of its current operations (the "proposed expanded area"). Angelo's application is being processed by the Department at this time. Angelo's ERP modification application is being processed by the Department under the Operating Agreement. The District has asserted permitting jurisdiction over the proposed expanded area because the proposed sand mining activities would occur in what the District asserts to be the floodway of the Alapaha. The District asserts that an ERP would be required from the District so that the District can address the work of the district (WOD) impacts. Petitioner has not filed a permit application with the District regarding the project. It is Petitioner's position that to do so would be futile. The Challenged Rules The rules or portions thereof which are challenged in this proceeding are as follows: Rule 40B-1.702(4), Florida Administrative Code, reads as follows: (4) A works of the district permit under Chapter 40B-4, F.A.C., must be obtained prior to initiating any project as outlined in (3) above within a regulatory floodway as defined by the District. Rule 40B-4.1020(12) and (30), Florida Administrative Code, read as follows: (12) "Floodway" or 'regulatory floodway" means the channel of a river, stream, or other watercourse and adjacent land areas that must be reserved in order to discharge the 100-year flood without cumulatively increasing the 100-year flood elevation more than a designated height. Unless otherwise noted, all regulatory floodways in the Suwannee River Water Management District provide for no more then one-foot rise in surface water. * * * (30) "Work of the district" means those projects and works including, but not limited to, structures, impoundments, wells, streams, and other watercourses, together with the appurtenant facilities and accompanying lands, which have been officially adopted by the governing board as works of the district. Works of the district officially adopted by the board are adopted by rule in Rule 40B-4.3000 of this chapter. Rule 40B-4.1030, Florida Administrative Code, reads as follows: The implementation dates of this chapter are as follows: January 1, 1986 for Rule 40B- 4.1040(1)(a) which requires persons to obtain surfacewater management permits. April 1, 1986 for Rule 40B- 4.1040(1)(b) and Rule 40B-4.3040 which require persons to obtain works of the district development permit if the proposed development is in one of the following areas adopted as a work of the district. The Alapaha River and its floodway in Hamilton County, Florida; The Aucilla River and its floodway in Jefferson, Madison, or Taylor counties, Florida; The Suwannee River or its floodway in Columbia, Hamilton, Lafayette, Madison, or Suwannee counties, Florida; or The Withlacoochee River and its floodway in Hamilton or Madison counties, Florida. (c) July 1, 1986 for Rule 40B-4.1040(1)(b) or 40B-4.3040 which require persons to obtain work of the district development permit if the proposed development is in one of the following areas adopted as a work of the district. The Santa Fe River and its floodway in Alachua, Bradford, Columbia, Gilchrist, Suwannee, or Union counties, Florida; or The Suwannee River and its floodway in Dixie, Gilchrist, or Levy counties, Florida. Rule 40B-4.1040(1)(b) and (c), Florida Administrative Code, reads as follows: (1) Permits are required as follows: * * * Works of the district development permit prior to connecting with, placing structures or works in or across, discharging to, or other development within a work of the district. When the need to obtain a works of the district development permit is in conjunction with the requirements for obtaining a surfacewater management permit, application shall be made and shall be considered by the district as part of the request for a surfacewater management permit application. Otherwise, a separate works of the district development permit must be obtained. Rule 40B-4.2030(4), Florida Administrative Code, reads as follows: (4) The new surfacewater management systems or individual works shall not facilitate development in a work of the district if such developments will have the potential of reducing floodway conveyance. (emphasis supplied) Rule 40B-4.3000(1)(a), Florida Administrative Code, reads as follows: The governing board is authorized to adopt and prescribe the manner in which persons may connect with or make use of works of the district pursuant to Section 373.085, Florida Statutes. Further, Section 373.019(15) provides that works of the district may include streams and accompanying lands as adopted by the governing board. In order to implement the non-structural flood control policy of the district, the governing board finds it is necessary to prevent any obstruction of the free flow of water of rivers and streams within the district. Therefore, the governing board does hereby adopt the following rivers and their accompanying floodways as works of the district: The Alapaha River and its floodway in Hamilton County, Florida; . . . . Rule 40B-4.3010, Florida Administrative Code, reads as follows: A general works of the district development permit may be granted pursuant to the procedures in Rule 40B-1.703 to any person for the development described below: Construction of a structure for single-family residential or agricultural use including the leveling of land for the foundation and associated private water supply, wastewater disposal, and driveway access which is in compliance with all applicable ordinances or rules of local government, state, and federal agencies, and which meets the requirements of this chapter. A general permit issued pursuant to this rule shall be subject to the conditions in Rule 40B-4.3030. Rule 40B-4.3020, Florida Administrative Code, reads as follows: Content of Works of the District Development Permit Applications. Applications for a general work of the district development permit shall be filed with the district and shall contain the following: Form 40B-4-5, "Application for General Work of the District Development Permit," Suwannee River Water Management District, 4-1-86, hereby incorporated by reference and which contains the following: The applicant's name and complete address including zip code; The owner's name and complete address if applicant is other than the owner; If applicable, the name, complete address, phone number, and contact person of the applicant or owner; Copies of all permits received from local units of government, state, or federal agencies, specifically a copy of the building or development permit issued by the appropriate unit of local government, including any variances issued thereto, and a copy of the onsite sewage disposal system permit issued by the Florida Department of Health and Rehabilitative Services under Chapter 10D- 6, Florida Administrative Code; A site plan to scale showing all improvements, work, or works with any conditions or limitations placed thereon; and Any supporting calculations, designs, surveys, or applicable documents, which in the applicant's opinion, may support the application. Applications for individual or conceptual approval works of the district development permits shall be filed with the district and shall contain the following: Form 40B-4-4, "Application for Surfacewater Management System Construction, Alteration, Operation, Maintenance, and/or Works of the District Development", Suwannee River Water Management District, 10-1-85, hereby adopted by reference and which contains the following: The applicant's name and complete address including zip code; The owner's name and complete address if applicant is other than the owner; If applicable, the name, complete address, phone number, and contact person of the owner. General project information including: The applicant's project name or identification number; The project location relative to county, section, township, and range, or a metes and bounds description; The total project area in acres; The total land area owned or controlled by the applicant or owner which is contiguous with the project area; A description of the scope of the proposed project including the land uses to be served; A description of the proposed surfacewater management system or work; A description of the water body or area which will receive any proposed discharges from the system; and Anticipated beginning and ending date of construction or alteration. Copies of all permits received from, or applications made to, local units of government, state, or federal agencies. A site plan to scale showing all improvements, work, or works with any conditions or limitations placed thereon. Any supporting calculations, designs, surveys, or applicable legal documents, which in the applicant's opinion, support the application. Copies of engineer or surveyor certifications required by this chapter. Rule 40B-4.3030, Florida Administrative Code, reads as follows: Conditions for Issuance of Works of the District Development Permits. The district will not approve the issuance of separate permits for development in a work of the district for any proposed project that requires a district surfacewater management permit pursuant to Part II of this chapter. For such projects, development in a work of the district may be authorized as part of any surfacewater management permit issued. The district will not approve the issuance of a works of the district development permit for any work, structures, road, or other facilities which have the potential of individually or cumulatively reducing floodway conveyance or increasing water-surface elevations above the 100-year flood elevation, or increasing soil erosion. The district will presume such a facility will not reduce conveyance or increase water-surface elevations above the 100-year flood elevation or increase soil erosion if: Roads with public access are constructed and laid out in conformance with the minimum standards of local government. Where roads are not required to be paved, the applicant must provide design specifications for erosion and sediment control. Where roads are required to be paved, swales will generally be considered adequate for erosion and sediment control; Buildings in the floodway are elevated on piles without the use of fill such that the lowest structural member of the first floor of the building is at an elevation at least one foot above the 100-year flood elevation; The area below the first floor of elevated buildings is left clear and unobstructed except for the piles or stairways; A permanent elevation monument is established on the property to be developed by a surveyor. The monument shall be adequate to establish land surface and minimum buildup elevations to the nearest 1/100 of a foot; No permanent fill or other obstructions are placed above the natural grade of the ground except for minor obstructions which are less than or equal to 100 square feet of the cross-sectional area of the floodway on any building or other similar structure provided that all such obstruction developed on any single parcel of land after the implementation date of this chapter is considered cumulatively; No activities are proposed which would result in the filling or conversion of wetlands. For any structure placed within a floodway which, because of its proposed design and method of construction, may, in the opinion of the district, result in obstruction of flows or increase in the water surface elevation of the 100-year flood, the district may require as a condition for issuance of a work of the district development permit that an engineer certify that such a structure will not obstruct flows or increase 100-year flood elevations. The following conditions shall apply to all works of the district development permits issued for development on lands subdivided after January 1, 1985: Clearing of land shall be limited [except as provided in (b) and (c) below] to that necessary to remove diseased vegetation, construct structures, associated water supply, wastewater disposal, and private driveway access facilities, and no construction, additions or reconstruction shall occur in the front 75 feet of an area immediately adjacent to a water. Clearing of vegetation within the front 75 feet immediately adjacent to a water shall be limited to that necessary to gain access or remove diseased vegetation. Harvest or regeneration of timber or agricultural crops shall not be limited provided the erosion of disturbed soils can be controlled through the use of appropriate best management practices, the seasonal scheduling of such activities will avoid work during times of high-flood hazard, and the 75 feet immediately adjacent to and including the normally recognized bank of a water is left in its natural state as a buffer strip. As to those lands subdivided prior to January 1, 1985, the governing board shall, in cases of extreme hardship, issue works of the district development permits with exceptions to the conditions listed in Rule 40B-4.3030(4)(a) through (c). The 75-foot setback in paragraphs (a) through (d) above shall be considered a minimum depth for an undisturbed buffer. The limitations on disturbance and clearing within the buffer as set out in paragraphs through (d) above shall apply, and any runoff through the buffer shall be maintained as unchannelized sheet flow. The actual depth of the setback and buffer for any land use other than single-family residential development, agriculture, or forestry shall be calculated in accordance with the methodology in: "Urban Hydrology for Small Watersheds", U.S. Department of Agriculture, Soil Conservation Service, Engineering Division, Technical Release 55, June 1986; and, "Buffer Zone Study for Suwannee River Water Management District", Dames and Moore, September 8, 1988, such that the post-development composite curve number for any one-acre area within the encroachment line does not exceed; a value of 46 for areas within the encroachment line with predominantly Class A soils; a value of 65 for areas within the encroachment line with predominantly Class B soils; a value of 77 for areas within the encroachment line with predominantly Class C soils; or a value of 82 for areas within the encroachment line with predominantly Class D soils. (emphasis supplied) Rule 40B-4.3040, Florida Administrative Code, reads as follows: Unlawful Use of Works of the District. It shall be unlawful to connect with, place a structure in or across, or otherwise cause development to occur in a work of the district without a works of the district development permit. The district may use any remedy available to it under Chapter 120 or 373, Florida Statutes, and Chapter 40B-1, Florida Administrative Code, to cause an unpermitted development to be removed or permitted. It shall be unlawful for any permitted use to violate the provisions of Chapter 373, Florida Statutes, or this chapter, or the limiting conditions of a works of the district development permit. The district may use any remedy available to it under Chapter 120 or 373, Florida Statutes, and Chapter 40B-1, Florida Administrative Code, to cause the unpermitted use to be removed or brought into compliance with Chapter 373, Florida Statutes, and this chapter. Damage to works of the district resulting from violations specified in Rule 40B-4.3040(1) and (2) above shall be repaired by the violator to the satisfaction of the district. In lieu of making repairs, the violator may deposit with the district a sufficient sum to insure such repair. Rule 40B-400.103(1)(h), Florida Administrative Code, reads as follows: (1) In order to obtain a standard general, individual, or conceptual approval permit under this chapter or chapter 40B-4, F.A.C., an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal or abandonment of a surface water management system: * * * (h) Will not cause adverse impacts to a work of the District established pursuant to s. 373.086. . . . Facts Based Upon the Evidence of Record History of the rules Mr. David Fisk is Assistant Director of the District. At the time of the hearing, he had been employed there for 26 and one-half years. He played a significant role in the rule adoption process of the rules that are the subject of this dispute. As part of that process, the District entered into a consulting contract with an engineering, planning, and consulting firm and consulted with the U.S. Corps of Engineers and the Federal Emergency Management Agency (FEMA), to conduct what are described as the FEMA flood studies. Additionally, the district commissioned an aerial photography consultant who provided a series of rectified ortho photographs of the entire floodplain of the rivers within the District, and a surveying subcontractor who provided vertical control and survey cross sections and hydrographic surveys of the rivers. The District also worked in conjunction with the United States Geological Survey to accumulate all of the hydrologic record available on flooding. The information was given to the U.S. Army Corps of Engineers who, operating under FEMA guidelines for conducting flood insurance rate studies, performed the analytical and computer modeling work to identify the flood plains and floodway boundaries. The District used the amassed knowledge of maps, cross sections and surveys that were developed as part of the FEMA flood studies as technical evidence or support for the adoption of the works of the district rules. Following a series of public workshops and public hearings in 1985, the rules were adopted and became effective in 1986. None of the rules were challenged in their proposed state. The District adopted the floodways of the Suwannee, Santa Fe, Alapaha, Aucilla, and Withlacoochee Rivers as works of the district. According to Mr. Fisk, the District adopted the rules pursuant to Section 373.086, Florida Statutes, which provided authority to the District to adopt district works and Section 373.085, Florida Statutes, which provided authority to regulate activities within those works. The Floodway Line Petitioner hired Mr. John Barnard, a professional civil engineer, with extensive environmental permitting experience, to look at the floodway and floodplain issues associated with Petitioner's site and project. Mr. Barnard conducted an engineering study entitled, "Floodplain Evaluation." It was Mr. Barnard's opinion that FEMA's determination of the floodway line was less than precise. Mr. Barnard used FEMA's data regarding the base flood elevation but manually changed the encroachment factor resulting in his placement of the floodway line in a different location than determined by FEMA. Mr. Barnard acknowledged that different engineers using different encroachment factors would reach different conclusions.1/ Respondent's expert in hydrology and hydraulic engineering, Brett Cunningham, noted that the definition of floodway in Rule 40B-4.1020(12), Florida Administrative Code, is essentially the same definition that used is in the FEMA regulations and which also is commonly used across the country in environmental rules and regulations. Mr. Barnard also acknowledged that the District's definition of "floodway", as found in Rule 40B-4.1020(12), Florida Administrative Code, is fairly commonly used by environmental regulatory agencies. Moreover, it was Mr. Cunningham's opinion that the Alapaha River is a stream or watercourse within the meaning of the rule and its floodway an accompanying land. In Mr. Cunningham's opinion, the FEMA flood insurance studies are widely used across the country for a variety of reasons and are typically relied upon by hydrologists and engineers to locate floodways. The definition of "works of the district" in Rule 40B-1020(30), Florida Administrative Code, is taken directly from the language found in Section 373.019(23), Florida Statutes. The statutory definition includes express references to streams and other watercourses, together with the appurtenant facilities and accompanying lands. Petitioner alleges that the phrase "will not cause adverse impact to a work of the SRWMD" as found in Rule 40B- 400.103(1)(h) is not clear because it does not identify what specific adverse impacts are being reviewed. While Petitioner's expert, Mr. Price, was not clear as to what the phrase means, Respondent's expert, Mr. Cunningham, understood the meaning of the phrase and noted that "adverse impact" is a phrase which is very commonplace in the rules and regulations of environmental agencies and is attributed a commonsense definition. The expert engineers differed in their opinions as to the meaning of the term "potential for reducing floodway conveyance" as used in Rule 40B-4.2030(4), Florida Administrative Code. According to Petitioner's expert engineer, Mr. Barnard, "potential for reducing floodway conveyance" is not a specific term that is open to interpretation as an engineer, and that he cannot quantify what constitutes "potential." Respondent's expert, Mr. Cunningham, understood the meaning of the phrase to be any increase in floodway conveyance. It was his opinion that there was nothing about that phrase to cause confusion. Rule 40B-4.3030, Florida Administrative Code, addresses conditions for issuance of works of the district development permits. Petitioner's expert Mr. Price testified that there is no quantification to what constitutes an "increase in soil erosion" as referenced in subsection (2) and linked the reference of soil erosion to a 100-year flood event referenced in the same subsection. Mr. Cunningham was of the opinion that there is no need to quantify an increase in soil erosion in the rule. He noted that soil erosion is used in a common sense manner and that attempting to put a numerical limit on it is not practical and "it's not something that's done anywhere throughout the country. It's just not something that lends itself to easy quantification like flood stages do". Mr. Cunningham's opinion that the words and phrases which Petitioner asserts are vague are words of common usage and understanding to persons in the field is the more persuasive testimony. This opinion is also consistent with statutory construction used by courts which will be addressed in the conclusions of law.

Florida Laws (15) 120.52120.536120.54120.56120.57120.595120.68373.019373.044373.085373.086373.113373.171403.814704.01
# 5
FLORIDA WILDLIFE FEDERATION, JUPITER FARMS ENVIRONMENTAL COUNCIL, INC., D/B/A LOXAHATCHEE RIVER COALITION, AUDUBON SOCIETY OF THE EVERGLADES, MARGE KETTER, PALM BEACH COALITION, STEVEN BELL, ALEXANDRA LARSON, MICHAEL CHRISTIANSON, AND BARRY SILVER vs SOUTH FLORIDA WATER MANAGEMENT DISTRICT, PALM BEACH COUNTY, AND LANTANA FARMS ASSOCIATES, INC., 04-003064 (2004)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Aug. 31, 2004 Number: 04-003064 Latest Update: Dec. 13, 2004

The Issue Petitioners challenge the South Florida Water Management District’s (the District) proposed action to issue Individual Environmental Resource Permit (ERP) 50-06558-P to authorize conceptual approval of a surface water management (SWM) system to serve 1,919 acres of a phased, multiple-use development referred to as the Palm Beach County Biotechnolgy Research Park (BRP) and to authorize construction and operation of Phase 1A of that proposed project. The ultimate issue is whether the Applicants provided reasonable assurances that the proposed activities will not be harmful to the water resources of the District; will not be inconsistent with the overall objectives of the District; and will comply with the water quantity, environmental, and water quality criteria of the District’s ERP regulations, which are set forth in Part IV of Chapter 373, Florida Statutes, Florida Administrative Code Chapter 40E-4, et. seq.; and the Basis of Review for Environmental Resource Permit Applications Within the South Florida Water Management District – September 2003 (BOR).1

Findings Of Fact THE PARTIES The Florida Wildlife Federation, Audubon Society of the Everglades, and Jupiter Farms Environmental Council, Inc. (d/b/a Loxahatchee River Coalition) are not-for-profit corporations in existence prior to 2003 with more than 25 members in Palm Beach County. Palm Beach County Environmental Coalition was formed in 1997 and is a private, county-wide, non-profit citizen’s organization. Ms. Ketter, Mr. Bell, Ms. Larson, and Mr. Christensen are individuals affected by the proposed BRP. The Respondents stipulated that the parties who remained Petitioners after Mr. Silver’s withdrawal as a Petitioner have standing to bring this proceeding. The District, a public corporation existing by virtue of Chapter 25270, Laws of Florida, 1949, operates pursuant to Chapter 373, Florida Statutes, and Title 40E, Florida Administrative Code, as a multipurpose water management district with its principal office in West Palm Beach, Florida. The County is a duly-constituted governmental entity. THE PROJECT SITE AND ADJACENT LANDS The site of the project is generally referred to as the Mecca Farms, which is a contiguous tract of 1,919 acres of land. At present, the Mecca Farms is used for farming and mining operations. There presently exists a permitted, SWM system on the Mecca Farms that was first permitted in 1979, and has been modified from time to time since then. The existing SWM system includes 73 acres of ditches and a 272-acre above-ground impoundment area. The Mecca Farms site is located within the C-18 Basin. There are no jurisdictional wetlands or delineated surface waters on the Mecca Farms. The following, which is taken from the Staff Report (SFWMD Ex. 1), accurately describes the project site and its adjacent lands: The project site consists of 1,919 acres presently supporting an active orange grove with approximately 73 acres of associated drainage and irrigation ditches/canals and a 30-acre active sand mining operation. The ditches/canals are presently maintained at an elevation of approximately 17 feet NGVD.[3] These ditches/canals provide drainage conveyance to a 272-acre above- ground impoundment located in the northeast corner of the site utilizing four (4) 22,000 gpm pumps. The above-ground impoundment discharges to the west leg of the C-18 Canal via gravity discharge. Project site ditches and canals also connect directly to the C-18 Canal through an 18,000 gpm pump. An additional 224-acre agricultural area east of the 1,919 acres of orange groves is connected to and drains into the canal/ditch system on the project site. This adjacent area was leased from the adjacent land owner by the grove owner for use as row crops and was connected to the grove canal/ditch system for better control of drainage and irrigation. The area is no longer used for row crops. There is also a small area on the site that contains caretaker housing and an equipment maintenance building for the orange groves. These facilities were originally permitted in 1979 under Surface Water Management Permit No. 50-00689-S and subsequent modifications. The citrus grove and primary drainage facilities have been in existence since the 1960s. The Hungryland Slough is located north of the project site, separated from the project site by the C-18 Canal. This area is comprised primarily of publicly-owned natural areas, including an area referred to as Unit 11, which is owned in the majority by Palm Beach County. To the west is the J.W. Corbett Wildlife Management Area (CWMA) owned and managed by the Florida Fish and Wildlife Conservation Commission (FFWCC). To the east, a large area of low-intensity agricultural land exists under the ownership of Charles Vavrus and within the City of Palm Beach Gardens. These lands contain extensive wetlands that are adjacent to the Loxahatchee Slough to the east. The Acreage, a low-density residential area, is located directly to the south of the project site. The only access to the site at this time is an unpaved extension of Seminole Pratt-Whitney Road (SPW), connecting the site at its southwestern corner to the Acreage. THE PROPOSED PROJECT The subject application is for conceptual approval of the SWM system for the BRP and for construction and operation of Phase 1A of the project. All of the proposed Phase 1A construction will occur on the Mecca Farms site. The following, taken from the Staff Report, accurately describes the proposed project: The [BRP] is a phased multiple use development planned for approximately 1,919 acres and will consist of land uses related to science and technology, biotechnology, biomedical, and other related research and development industries and manufacturing. Additionally, proposed support and complementary land uses include educational, institutional, residential, commercial, and recreational facilities, along with utilities and a large created natural area. THE PROPOSED SWM SYSTEM The proposed SWM system will consist of several interconnected lakes that will provide wet detention for storm water runoff from the property site and from 39 acres of off- site flows from SPW Road and a proposed Florida Power and Light (FPL) Substation. The lakes will collect, store, and treat the runoff. The storm water will pass through the lakes, through a 247-acre area referred to as the “Natural Area” (which will be created as part of the mitigation plan), and discharged to the C-18 Canal. To provide additional water quality treatment, these lakes will include planted littoral zones and the southern lake will include a filter marsh. The Natural Area will, in subsequent construction phases, be constructed on the western boundary of the Mecca site with discharge to the C-18 canal, which is adjacent to the northern boundary of the Mecca Farms. The southern boundary of the Natural Area will be the north boundary of the lake that is to be constructed on the southern end of the property. This is the area that is available for use as a flow-way (which will be discussed in greater detail in a subsequent section of this Recommended Order). The Natural Area will be a wetland type system that will move water slowly through that system providing additional storage and water quality benefits prior to discharging through a gravity control structure into the C-18 Canal. The C-18 Canal discharges to either the Northwest or Southwest Fork of the Loxahatchee River, depending on how structures are operated downstream. Discharges travel in the C-18 Canal for approximately nine miles before reaching the Loxahatchee River. The existing SWM system for the Mecca Farms currently discharges to the C-18 Canal, as will the proposed SWM system. The proposed project will not discharge to the CWMA or the Hungryland Slough. The Grassy Waters Preserve and the Loxahatchee Slough are several miles from the project site and will not be affected by the project’s proposed activities. The following, which is taken from the Staff Report, accurately describes the proposed SWM system. The proposed conceptual surface water management system which will serve the 1,919-acre site will consist of site grading, storm water inlets and culverts which will direct all runoff to a series of interconnected lakes for water quality treatment and attenuation of the peak runoff rate. Pumps will control the runoff rate from the developed site into the adjacent onsite BRP natural area. The BRP natural area will discharge into the C-18 canal via a gravity control structure. The system has been designed to accommodate 39 acres of off-site flows from SPW [Road] and a proposed Florida Power and Light (FPL) Substation. The existing control elevation of the citrus grove is 17.0’ NGVD. The proposed control elevations are 18.0’ NGVD for the developed area and 19.0’ NGVD for the natural area. The control elevations are being raised to provide a “step down” of water elevations from wetlands to the north, west and east of the site (20.5’ to 21.0’) to lower elevations to the south (17.0’). PHASE 1A CONSTRUCTION The following, which is taken from the Staff Report, accurately describes the proposed Phase 1A construction: The Phase 1A construction activities will allow the applicant to proceed with lake excavation, clearing and site grading of 536 acres in the southern portion of the site. No permanent buildings or parking areas are proposed at this time. Stormwater from Phase 1A and the remainder of the site, to remain in agricultural use, will be treated in the Phase 1A lakes and then pumped into the existing impoundment for additional water quality treatment and attenuation prior to discharging to the west leg of the C-18 Canal via the existing weir structures. The existing 18,000 gpm pump that connects the on-site ditches and canals directly to the C-18 Canal will remain, but will only be used if the impoundment is full. (See Special Condition No. 21). Approval of Phase 1A authorizes the use of the existing, previously permitted surface water management facilities, therefore, the previous permit no. 50-00689-S is superceded by this permit. The 224 acre agricultural area east of the existing grove that is connected to the grove canal/ditch system will be severed as part of Phase 1A. The pipe connecting this area will be removed and portions of the berm around this area will be regraded so the area will sheetflow into the adjacent pasture land’s canal/ditch system as it did previously [sic] to being connected to the grove system. Of the 536 acres involved in the Phase 1A construction, 87 acres will become lake bottom and 449 acres will remain pervious area, subject only to grading. CONCEPTUAL APPROVAL Pertinent to this proceeding, Florida Administrative Code Rule 40E-4.021(5) defines the term “conceptual approval” to mean an ERP issued by the District which approves a conceptual master plan for a surface water management system or a mitigation bank. Florida Administrative Code Rule 40E-4.305, pertains to conceptual approvals and provides, in relevant part, as follows: Conceptual approvals constitute final District action and are binding to the extent that adequate data has been submitted for review by the applicant during the review process. A conceptual approval does not authorize construction, alteration, operation, maintenance, removal, or abandonment of a surface water management system or the establishment and operation of a mitigation bank. * * * For phased projects, the approval process must begin with an application for a conceptual approval which shall be the first permit issued for the project. An application for construction authorization of the first phase(s) may also be included as a part of the initial application. As the permittee desires to construct additional phases, new applications shall be processed as individual or standard general environmental resource permit applications pursuant to the conceptual approval. The conceptual approval, individual and standard general permits shall be modified in accordance with conditions contained in Chapters 40E-4 and 40E-40, F.A.C. Issuance of a conceptual approval permit pursuant to Chapter 40E-4, F.A.C., shall not relieve the applicant of any requirements for obtaining a permit to construct, alter, operate, maintain, remove, or abandon a surface water management system or establish or operate a mitigation bank, nor shall the conceptual approval permit applicant be relieved of the District’s informational requirements or the need to meet the standards of issuance of permits pursuant to Chapters 40E-4 or 40E-40, F.A.C. . . . PERMITTING CRITERIA In order to obtain an ERP, an applicant must satisfy the conditions for issuance set forth in Florida Administrative Code Rules 40E-4.301 and 40E-4.302. The conditions for issuance focus on water quantity criteria, environmental criteria, and water quality criteria. Florida Administrative Code Rule 40E-4.301 contains the following permitting conditions applicable to this proceeding: In order to obtain a standard general, individual, or conceptual approval permit ... an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal, or abandonment of a surface water management system: will not cause adverse water quantity impacts to receiving waters and adjacent lands; will not cause adverse flooding to on-site or off-site property; will not cause adverse impacts to existing surface water storage and conveyance capabilities; will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters; will not adversely affect the quality of receiving waters ...; will not cause adverse secondary impacts to the water resources; will not adversely impact the maintenance of surface or ground water levels or surface water flows ...; will not cause adverse impacts to a work of the District ...; will be capable, based on generally accepted engineering and scientific principles, of being performed and of functioning as proposed; will be conducted by an entity with the sufficient financial, legal and administrative capability to ensure that the activity will be undertaken in accordance with the terms and conditions of the permit, if issued; and will comply with any applicable special basin or geographic area criteria established in Chapter 40E-41 F.A.C. Florida Administrative Code Rule 40E-4.302 provides the following Additional Conditions for Issuance of Permits applicable to this proceeding: In addition to the conditions set forth in section 40E-4.301, F.A.C., in order to obtain a standard general, individual, or conceptual approval permit under this chapter or Chapter 40E-40, F.A.C., an applicant must provide reasonable assurance that the construction, alteration, operation, maintenance, removal, and abandonment of a system: Located in, on, or over wetlands or other surface waters will not be contrary to the public interest, or if such an activity significantly degrades or is within an Outstanding Florida Water, that the activity will be clearly in the public interest, as determined by balancing the following criteria as set forth in subsections 4.2.3 through 4.2.3.7 of the Basis of Review for Environmental Resource Permit Applications Within the South Florida Water Management District: Whether the activity will adversely affect the public health, safety or welfare or the property of others; Whether the activity will adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats; Whether the activity will adversely affect navigation or the flow of water or cause harmful erosion or shoaling; Whether the activity will adversely affect the fishing or recreational values or marine productivity in the vicinity of the activity; Whether the activity will be of a temporary or permanent nature; Whether the activity will adversely affect or will enhance significant historical and archaeological resources under the provisions of Section 267.061, F.S.; and The current condition and relative value of functions being performed by areas affected by the proposed activity. Will not cause unacceptable cumulative impacts upon wetlands and other surface waters as set forth in subsections 4.2.8 through 4.2.8.2 of the Basis of Review. . . . THE BASIS OF REVIEW The District has adopted the BOR and incorporated it by reference by Florida Administrative Code Rule 40E- 4.091(1)(a). The standards and criteria found in the BOR are used to determine whether an applicant has given reasonable assurances that the conditions for issuance of an ERP have been satisfied. Section 1.3 of the BOR provides, in part, as follows: . . . Compliance with the criteria established herein [the BOR] constitutes a presumption that the project proposal is in conformance with the conditions for issuance set forth in Rules 40E-4.301 and 40E-4.302, F.A.C. WATER QUANTITY The term “control elevation” describes the level of freshwater water bodies established by a SWM system. The existing SWM system has a control elevation of 17’ NGVD. The control elevation for the proposed lake system will be raised to 18’ NGVD, and the control elevation for the proposed Natural Area will be raised to 19’ NGVD. Raising the control elevations will permit more treatment of storm water prior to discharge and will permit a more controlled discharge. In addition, raising the control elevation will lessen seepage onto the project site from adjacent wetlands. The Applicants provided reasonable assurances that the proposed project will not cause adverse water quantity impacts to receiving waters and adjacent lands, thereby satisfying the criteria set forth in Florida Administrative Code Rule 40E- 4.301(a). The Applicants provided reasonable assurances that the proposed project will not cause adverse flooding to on-site or off-site property, thereby satisfying the criteria set forth in Florida Administrative Code Rule 40E-4.301(b). The Applicants provided reasonable assurances that the proposed project will not cause adverse impacts to existing surface water storage and conveyance capabilities, thereby satisfying the criteria set forth in Florida Administrative Code Rule 40E-4.301(c). VALUE OF FUNCTIONS OF WETLANDS AND SURFACE WATERS Florida Administrative Code Rule 40E-4.301(d), requires the Applicants to establish that “. . . the construction, alteration, operation, maintenance, removal, or abandonment of a surface water management system . . .” “. . . will not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters.” The District established that the term “value of functions,” as used in the rule, refers to habitat and life support functions. Because there are no wetlands or delineated surface waters on the Mecca Farms site, there are no direct adverse impacts to the functions that wetlands provide to fish and wildlife. The Applicants have provided reasonable assurances to demonstrate that the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters will not be adversely affected. The existing project site does not contain nesting areas for wetland-dependent endangered or threatened wildlife species or species of special concern. The potential for use of the existing project site for nesting by such species is minimal. The existing project site does contain habitat for the American Alligator and foraging habitat for wading birds and birds of prey. The primary foraging habitat on the existing site is around the perimeter of the existing 272-acre impoundment area in the northeast portion of the site. The existing impoundment will be replaced by on-site storm water treatment lakes and the BRP Natural Area that will have shallow banks planted with wetland plant species common to the area. Wildlife is opportunistic; and wading birds commonly feed in areas where there is water, wetland vegetation and wetland plants. The end result will be that the proposed project will have more and better foraging habitat acreage than the existing site. The Natural Area will provide a wetland buffer between the developed area and CWMA that will prevent any adverse impacts both to the wetlands and other surface waters in CWMA and to the value of the functions those wetlands and other surface waters provide to fish, wildlife, and listed species. The Natural Area will provide a wetland buffer between the developed area and Unit 11 that will prevent any adverse impacts both to the wetlands and other surface waters in Unit 11 and to the value of the functions those wetlands and other surface waters provide to fish, wildlife, and listed species. There was no competent evidence that the proposed project would impact the ability of the Florida Fish and Wildlife Conservation Commission to manage the CWMA through control burns or otherwise, thereby adversely affecting the diversity or abundance of fish and wildlife (including endangered species and their habitats). Petitioners attempted to raise the issue of mosquito control in their Petitions and at the Final Hearing. The allegations pertaining to mosquito control were struck by the District and Special Condition Number 26 was added before the Petitions were referred to DOAH. Petitioners made no attempt to amend their Petitions and have not challenged Special Condition 26. The Addendum to Staff Report (SFWMD Ex. 2) contains the following Special Condition Number 26: “Upon submittal of an application for construction of any buildings, the permittee shall submit a mosquito control plan for review and approval by District Staff.” Since there will be no buildings containing people or other facilities which would encourage the use of mosquito spraying, it is appropriate for the mosquito control condition to apply to only future phases of construction. There was no competent evidence of impacts attributable to pesticides associated with the application for the SWM system or for Phase 1A construction and operation that would adversely affect the diversity or abundance of fish and wildlife including endangered species and their habitats. The Applicants have satisfied the criteria set forth in Florida Administrative Code Rule 40E-4.301(d). WATER QUALITY The primary concern during Phase 1A construction will be erosion control. Best Management Practices (“BMPs”) are operational and design elements used to either eliminate or reduce the amount of pollutants at the source so they do not get into a SWM system or move downstream. To contain erosion in Phase 1A, the Applicants will use the following BMPs: Silt screens and turbidity barriers within existing ditches and around the perimeter of property. Planned construction sequencing to reduce movement and stock piling of material; Slope stabilization and seeding or sodding of graded areas; and Containment of construction materials with berms. All erosion and turbidity control measures will remain in place until the completion of the on-site construction and approval by the District’s post-permit compliance staff. The Applicants provided reasonable assurances that the proposed Phase 1A construction activities will not adversely impact the quality of receiving waters and that those activities will not violate State water quality standards. Section 5.2.1, BOR, requires that a SWM system provide wet detention for the first one inch of runoff. The proposed SWM system will provide wet detention for one and one-half inches of runoff. The Applicants provided reasonable assurances to demonstrate that the technical criteria in the BOR will be met. Under Section 1.3 of the BOR, compliance with the criteria in the BOR constitutes a presumption that the Proposed Project is in conformance with the conditions for issuance. This presumption was not rebutted by the Petitioners. The lake system will include planted littoral zones to provide additional uptake of pollutants. A filter marsh is also included in the southern lake. All of the storm water runoff from the lakes will pass through the filter marsh, which will be planted with wetland plants. The filter marsh will provide additional polishing of pollutants, uptake, and filtering through the plants. The discharge will then go into the BRP, which will provide the discharge additional uptake and filtering. BMPs utilized during the Operations and Maintenance phase will include regular maintenance inspections and cleaning of the SWM system, street-sweeping, litter control programs, roadway maintenance inspections and repair schedule, municipal waste collection, pollution prevention education programs, pesticides, herbicides and fertilizer storage, and application training and education. The littoral zones, filter marsh, BRP natural area, and BMPs were not included in the water quality calculations and are over and above rule requirements. The Applicants provided reasonable assurances to demonstrate that the proposed project will not adversely affect the quality of receiving waters. Therefore, Rule 40E- 4.301(1)(e), F.A.C., will be satisfied and water quality standards will not be violated. HAZARDOUS SUBSTANCES Pursuant to Section 5.5.5 of the BOR, commercial or industrial zoned projects shall provide at least one-half inch of dry detention or retention pretreatment as part of the required retention/detention, unless reasonable assurances can be offered that hazardous materials will not enter the project's SWM system. The Addendum to Staff Report reflects the following Special Condition 25 pertaining to hazardous materials: Upon submittal of an application for construction of commercial or industrial uses the permittee shall submit a plan that provides reasonable assurances that hazardous materials will not enter the surface water management system pursuant to the requirements of section 5.2.2(a) of the Basis of Review. Applicable permitting criteria does not require the Applicants to present a hazardous substances plan at this point because no facilities that will contain hazardous materials are part of the Phase 1A construction. SECONDARY IMPACTS Florida Administrative Code Rule 40E-4.301(1)(f) and Section 4.1.1(f) of the BOR, require an applicant to provide reasonable assurances that the proposed activities will not cause adverse secondary impacts to the water resources. A secondary impact is an indirect effect of a project resulting in adverse effects to wetlands or other surface waters. The District considers those adverse effects that would not occur "but for" the activities that are closely linked and causally related to the activity under review. This standard is discussed further in the Conclusions of Law section of this Recommended Order. The County’s Exhibit 3 is a secondary impact analysis identifying the secondary impacts that may potentially result from the proposed project. These impacts are: 1) the widening of SPW Road; 2) the construction of an FPL substation; 3) the extension of PGA Boulevard; and 4) the potential relocation of a runway at North County Airport. The secondary impact analysis performed pursuant to the Uniform Mitigation Assessment Method (UMAM) contained in Florida Administrative Code Chapter 62-345 reflects that up to 153.3 acres of wetlands may be partially or completely impacted by these secondary impacts, resulting in approximately 71.21 units of functional loss. Where future activities are expected to directly impact wetlands, secondary impacts were assessed based on the loss of all current functional value within the direct footprint of that activity. Additionally, an assessment was conducted to determine the degree of partial functional loss where impacts beyond the footprint of these activities are anticipated. SPW Road is an existing dirt road which is in the County's five-year road plan to widen as a four-lane paved road. Because the widening of the existing dirt road to a four-lane paved road is part of the five-year road plan, the impacts of that widening are not attributable to the subject project. However, as part of the proposed project, it is proposed to widen SPW Road to a six-lane paved road. The additional impacts associated with the widening from four to six lanes will be caused by, and are linked to, the proposed project. These impacts amount to approximately 2.2 acres. The FPL substation, which is proposed to service the proposed project, may result in 1.6 acres of potential direct impacts to wetlands. In addition, 1.0 acre of potential indirect secondary impacts may occur to wetlands that are not going to be dredged and filled. Those indirect secondary impacts may have some adverse impact on the functional value to those wetlands for wildlife utilization. The extension of PGA Boulevard to the Mecca Farms site has the potential to result in 45.6 acres of direct impacts to wetlands and 56.6 acres of indirect secondary wetland impacts which will not be dredged or filled, but will be in close proximity to the road. The secondary impact assessment for PGA Boulevard assumed the incorporation of wildlife crossings to minimize habitat fragmentation. If the airport runway needs to be shifted, potential direct wetland impacts to an additional 22.7 acres may occur. Indirect impacts to 23.6 acres of wetlands in close proximity could also occur. Runway relocation may or may not be necessary due to the PGA Boulevard extension; however, the analysis assumed the need for the relocation. Each of the projects listed above as potential secondary impacts will require a separate construction and operation permit from the District. The issuance of this permit does not in any way guarantee the issuance of permits for any of these identified potential secondary impacts. MITIGATION PLAN The Applicants provided a conceptual mitigation plan using UMAM to demonstrate how potential secondary impacts could be offset. Mitigation options have the potential to provide more than twice the functional gain than the functional loss from the identified secondary impacts. The conceptual mitigation options include: 194 acres of the land that had been acquired for future mitigation needs in Unit 11. 227 acres of the BRP natural area. 32.6 acres in the southern lake wetland along with proposed upland habitat. Sufficient mitigation is available in these options to offset the potential secondary impacts. The mitigation for the four potential secondary impacts is not required to be implemented now because the impacts are not occurring now. Section 4.2.7 of the BOR requires that the District consider those future impacts now and that a conceptual mitigation plan be provided to demonstrate and provide reasonable assurances that those impacts, in fact, can be offset in the future. The Governor and Cabinet sitting as the Board of Trustees considered and approved a request for public easement of approximately 30 acres to use a portion of CWMA for SPW Road, an FPL substation, and the land area that may be needed by District in the future for the connection to the flow-way. As consideration in exchange for the public easement over 30 acres, the County will transfer fee simple title of 60 acres to the State. This public easement also provides a benefit for CERP as it includes the small portion that the District is going to need for its future CERP project to connect to the flow-way on the proposed project site. The Applicants provided reasonable assurances that mitigation will offset secondary impacts to wetlands and other surface waters. UNIDENTIFIED SECONDARY IMPACTS Testimony at the final hearing raised a question as to whether there is nesting or roosting by listed wading bird species in adjacent off-site wetlands outside the eastern boundary of the project site. Evidence was inconclusive on nesting or roosting in these areas. Because the status of adjacent listed wading bird nesting or roosting is uncertain, the District suggested in its Proposed Recommended Order that a special condition requiring a wildlife survey prior to construction near the eastern project boundary be added to the permit as follows: Prior to application for construction within 1000 feet of the eastern boundary of the above-ground impoundment, the applicant shall conduct a wildlife survey to identify any nesting or roosting areas in the adjoining off-site wetlands utilized by listed species of wading birds. If such nesting or roosting areas are found the permittee shall, if determined necessary by the District, incorporate additional buffers or other appropriate measures to ensure protection of these wetland functions. The District represented in its Proposed Recommended Order that the County has no objection to adding the foregoing condition. CUMULATIVE IMPACTS Pursuant to Section 373.414(8), Florida Statutes, the District is required to consider cumulative impacts upon wetlands and other surface waters delineated in Section 373.421(1), Florida Statutes, within the same drainage basin. Cumulative impacts are the summation of unmitigated wetland impacts within a drainage basin. The cumulative impact analysis is geographically based upon the drainage basins described in Figure 4.2.8-1 of the BOR. Cumulative impacts are unacceptable when they would result in unacceptable adverse impacts to the functions of wetlands and surface waters within a drainage basin. There are no wetlands or other surface waters delineated pursuant to Section 373.421(1), Florida Statutes, on the Mecca Farms site. Therefore, no cumulative impacts are created by the direct impacts of the project. Cumulative impacts may be created by a project's secondary impacts. If a wetland impact has been appropriately mitigated on-site within the drainage basin, there is no residual impact, and therefore no cumulative impact. The PGA Boulevard extension, a portion of the SPW Road widening, and the airport runway relocation are located within the C-18 Basin. The proposed mitigation options are all located in the C-18 Basin and will offset those impacts. Those potential secondary impacts are considered to meet the cumulative impact requirements of Section 373.414(8), Florida Statutes. The Applicants provided reasonable assurances that the proposed project will not result in cumulative impacts to the C-18 Basin. The FPL substation is located within the L-8 Drainage Basin. The majority of the SPW Road expansion is located within the C-18 Basin, but a portion is located on the basin line between the C-18 Basin and the L-8 Basin. Because the mitigation for the L-8 impacts are proposed in a different basin, the Applicants were required to conduct a cumulative impact analysis for the L-8 Basin impacts. Based on the Florida Land Use Cover Classification System, there are 43,457 acres of freshwater wetlands within the L-8 Basin. Approximately 41,000 acres of the wetlands in L-8 Basin are in public ownership. This total constitutes approximately 95 percent of all the wetlands in the L-8 Basin. Public ownership of these wetlands provide a high level of assurance that these lands will be protected in perpetuity. The Respondents established that proposed mitigation can fully offset the potential impacts from the SPW Road expansion and the FPL substation and the approximately four acres of impacted wetlands in the L-8 Basin. The Applicants provided reasonable assurances that there are no unacceptable adverse cumulative impacts on the L-8 Basin.4 GROUND WATER FLOWS, SURFACE WATER FLOWS, AND MINIMUM FLOWS AND LEVELS Florida Administrative Code Rule 40E-4.301(1)(g) requires an applicant to provide reasonable assurances that the proposed activity will not adversely impact the maintenance of surface or ground water levels or surface water flows established pursuant to Section 373.042, Florida Statutes. The term "maintenance of surface and groundwater levels or surface water flows" in Florida Administrative Code Rule 40E-4.301(1)(g) means that a project will not adversely impact the maintenance of surface water flows that contribute to meeting the minimum flow for the water body. An adverse impact to the maintenance of surface or groundwater levels or surface water flows may occur when a project discharging to a water body with a designated minimum flow level is proposed to be diverted. An analysis was done to compare the peak discharge rate from the existing SWM system on the Mecca Farms site with the projected peak discharge rate from the proposed SWM system. The analysis showed that the peak discharge rate under the proposed system will be less than that of the existing system. That result was expected since the proposed system will have higher control elevations, which, as noted above, will provide better treatment and permit a better control of the discharge into the C-18 Canal. Under the existing SWM system, storm event water in a dry period is frequently stored in the existing impoundment for future irrigation purposes. Under the proposed SWM system such storm event water will be discharged downstream, which will benefit those downstream areas during dry periods. The proposed system will also provide better control over pulse discharges during heavy storm events. The Applicants provided reasonable assurances that the proposed activities will not adversely impact the maintenance of surface or ground levels or surface water flows as required by Florida Administrative Code Rule 40E-4.301(1)(g). THE DISTRICT’S OBJECTIVES Sections 373.414 and 373.416, Florida Statutes, require an applicant to provide reasonable assurances that a regulated activity will not be harmful to the water resources and will not be inconsistent with the overall objectives of the District. Congress initially authorized the Central and Southern Florida (“C&SF”) Project in 1948. Thereafter extensive work was undertaken pertaining to flood control; water supply for municipal, industrial, and agricultural uses; prevention of saltwater intrusion; and protection of fish and wildlife. The work included construction of a primary system of 1000 miles each of levees and canals, 150 water-control structures, and 16 major pump stations. Unintended consequences of the C&SF Project have included the irreversible loss of vast areas of wetlands, including half of the original Everglades; the alteration in the water storage, timing, and flow capacities of natural drainage systems; and the degradation of water quality and habitat due to over-drainage or extreme fluctuations in the timing and delivery of fresh water into the coastal wetlands and estuaries. In 1992, Congress authorized the C&SF Project Comprehensive Review Study, which is generally referred to as the “Restudy.” The objective of the Restudy was to reexamine the C&SF Project to determine the feasibility of modifying the project to restore the South Florida ecosystem and provide for the other water-related needs of the region, such as water supply and flood protection. In April 1999, the U.S. Army Corps of Engineers issued the Central and Southern Florida Project Comprehensive Review Study Final Integrated Feasibility Report and Programmatic Environmental Impact Statement (“Restudy Report”). The Restudy Report recommends a comprehensive plan for the restoration, protection, and preservation of the water resources of Central and South Florida. The resulting plan is known as CERP. The North Palm Beach County Part I project, which includes restoration of the Northwest Fork of the Loxahatchee River (“NWFLR”), is a component of CERP. The successful completion of CERP and the successful restoration of the NWFLR are high-priority objectives of the District. The Loxahatchee River is an important feature of the South Florida ecosystem, nationally and internationally unique, and an important natural and economic resource. Rules pertaining to MFL for the NWFLR and for the recovery of the NWFLR are found at Florida Administrative Code Rule 40E-8.011; 40E-8.221(4); and 40E-8.421. Recovery goals, which are not presently being met, have been established; and strategies to meet those goals have been identified. The Mecca Farms site is located within the boundaries of the CERP North Palm Beach County Part I project and has the potential to affect CERP and the restoration of the NWFLR. Projects that potentially would affect or would be within or adjacent to a CERP project are evaluated on a case-by- case basis to determine whether a proposed project would not be inconsistent with CERP and other District objectives. There was a dispute between Respondents and Petitioners as to whether the proposed project was inconsistent with the District’s objectives, including CERP and its goals pertaining to the restoration of the NWFLR. Petitioners contend that the District has insufficient evidence that the Mecca Farms will not be needed for the construction of a reservoir. That contention is rejected. The greater weight of the credible evidence established that sufficient storage is available at a superior site known as the Palm Beach Aggregates (PBA) site in the L-8 Basin, which is a unique geological site that will provide in-ground storage of water.5 Water from the PBA storage site can be conveyed to the NWFLR to increase dry season flows. Water can be stored at the PBA site in the wet season to prevent potentially damaging high flows. The L-8 Basin, which is adjacent to the C-18 Basin, receives more water during the wet season than it uses. This means that at present a significant amount of water must be discharged to tide (lost) during the wet season to provide for flood protection in this area. As envisioned, the water currently lost to tide could be stored at the PBA site for use during the dry season. By combining the water storage in the L-8 Basin with connective flow-ways to the C-18 Canal, water demands within the C-18 Basin, including the NWFLR, can also be met by the PBA storage site.6 An increase in freshwater flows to the NWFLR will further the District’s restoration goals for the NWFLR. Storage at PBA has regional benefits for other significant natural areas because it will provide additional flows to the Loxahatchee Slough and Grassy Waters Preserve. Those additional flows will further the District’s CERP goals. Since October of 2003, County staff and the District’s ERP staff have coordinated review of the subject project with the District’s CERP Planning and Federal Projects Division and other District staff working on projects in this region. The County asked the District to determine if the Mecca Farms’ site could in some way accommodate CERP objectives, and three alternatives were considered: 1) no action; 2) a reservoir; and 3) a flow-way. As opposed to a reservoir, the more valuable and the more practical, use of the Mecca Farms site would be as part of the system to convey the stored water to the areas that would most benefit from its discharge. The proposed flow-way in the BRP Natural Area would be an integral part of that conveyance system and would provide the District with greater flexibility in managing and directing the discharge of the water stored at the PBA site. Prior to the development of the flow-way concept as part of the proposed development, CERP identified a single route to take water from PBA to the NWFLR. The flow-way will provide an additional route from PBA to the NWFLR. That additional route will provide the District with greater operational flexibility. The flow-way will complement the L-8 Basin flow- way and help reduce peak flows to the NWFLR and the Estuary. The flow-way also provides a potential route allowing excess water to be brought back from the C-18 Basin to the PBA site for storage. There are no other potential routes that allow water to be directed from the C-18 Basin in the wet season to the PBA site. The flow-way provides a feature that was not part of the CERP original plan and is therefore an unanticipated benefit for CERP. The Applicants provided reasonable assurances that the proposed project is not inconsistent with the District’s objectives.7

Recommendation Based on the foregoing findings of fact and conclusions of Law, it is RECOMMENDED that the District issue the subject ERP for the conceptual approval of the SWM system for the BRP and the Phase 1A construction and operation subject to the general and special conditions set forth in the Staff Report and the Amended Staff Report. It is further RECOMMENDED that the District add the following special condition: Prior to application for construction within 1000 feet of the eastern boundary of the above-ground impoundment, the applicants shall conduct a wildlife survey to identify any nesting or roosting areas in the adjoining off-site wetlands utilized by listed species of wading birds. If such nesting or roosting areas are found the permittee shall, if determined necessary by the District, incorporate additional buffers or other appropriate measures to ensure protection of these wetland functions. DONE AND ENTERED this 3rd day of December, 2004, in Tallahassee, Leon County, Florida. S CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 3rd day of December, 2004.

Florida Laws (9) 120.569120.57120.574267.061373.042373.414373.416373.421403.973
# 6
S. A. WILLIAMS CORPORATION vs SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT, 93-007073F (1993)
Division of Administrative Hearings, Florida Filed:Brooksville, Florida Dec. 14, 1993 Number: 93-007073F Latest Update: Jul. 22, 1997

Findings Of Fact S. A. Williams Corporation (Williams) is a Florida corporation which has its principal place of business in Florida, has a net worth of less than two million dollars, has fewer than 25 employees, and was the prevailing party in the initial proceedings. Williams has operated a construction and demolition landfill in Hernando County since prior to the adoption of zoning ordinances by the county, and its use of the land for this purpose was grandfathered. Subsequently, William sought to comply with certain conditions established by the County for expanding the landfill site. These improvements necessitated construction of a basin to retain surface water. On April 6, 1993, William applied for a surface water drainage permit from the Southwest Water Management District. On June 16, 1993, the District gave notice of its intent to issue the surface water drainage permit to Williams. On May 26, 1993, while Williams' application was pending with the Water Management District, the County revoked the zoning of Williams to operate a construction and demolition landfill site. Williams sought and obtained an injunction against the County to prevent it from revoking its zoning, and the County appealed the Circuit Court's order enjoining the revocation of the zoning. The Hernando County Commission was advised by their attorney on May 10, 1993, that the County might desire to challenge the issuance of permits by the Water Management District or the Department of Environmental Regulation to Williams to prevent Williams from proceeding with its operation during the appeal of the injunction. At a meeting on June 24, 1993, before the County challenged issuance of the permit, the Water Management District staff advised the County Attorney and a member of the County Commission, who were attending the presentation in their official capacity, that there would be no adverse drainage impacts to any property owned by the County, its rights-of-way, or any property of any citizen of the county because the drainage would be retained on Williams' property by a close basin system large enough to retain surface water drainage on the property during a 100 year storm. Subsequent to this meeting and prior to filing its petition challenging issuance of the permit, the County did not bring to the attention of the Water Management District any concerns to be resolved between the District, Williams, and the County over adverse drainage impacts to County property or rights-of-way. 7 On June 30, 1993, Hernando County filed a petition in the original proceeding challenging the issuance by Southwest Water Management District to Williams of a surface water drainage permit. That petition alleged two grounds for standing: (1) that the County was substantially affected because of adverse impacts to county property and the rights-of-way to county roads, and (2) that the County had standing to challenge the issuance of the permit under its general police powers. The County Engineer was not asked by the County Attorney to review the drainage impacts of the surface water drainage permit prior to filing the challenge, and did not review the District's file until after his first deposition on October 22, 1993. After reviewing the information, to include a new survey of the berm contours, furnished to the Water Management District by Williams, the County Engineer determined that there were no adverse drainage impacts off site. The County Engineer's opinion that there were no adverse impacts to County property was known by the County Attorney prior to the formal hearing in Case Number 93-4212 on November 16, 1993. At the formal hearing on November 16, 1993, in Case Number 93-4212, Williams moved to dismiss the petition filed by Hernando County for lack of standing on the basis that the County was not substantially effected by the Water Management District's decision to issue a surface water drainage permit to Williams. The County receded from its allegation of damage to County property and rights-of-way at the commencement of the hearing, but asserted standing on the basis of its general police powers. The County specifically denied at the formal hearing acting in a representative capacity in the manner of an association in behalf of the county's citizens. After hearing the argument of counsel and being fully advised in the premises, the undersigned hearing officer recommended that the County's petition be dismissed. At the conclusion of the hearing, Williams moved for the award of attorney's fees and expenses from the County after argument on the motion to dismiss the County's petition. Thereafter, Williams filed a written motion for the award of attorney fees and expenses. The Hearing Officer retained jurisdiction to consider the Motion for Attorney Fees and Expenses when the recommended order was entered. The Water Management District adopted the Recommended Order in its Final Order dated December 20, 1993, and the County appealed the District's Final Order which was affirmed per curiam without opinion in Hernando County v. Southwest Florida Water Management District, 647 So. 2d 124, (Fla. 5th DCA 1994). The instant case was established to consider William's motion which is treated as a collateral fact finding proceeding. The style of the original case was retained to prevent confusion. An evidentiary hearing on the motion for attorney's fees was held on May 10, 1995 which revealed the following facts. During the work-up period prior to notice of intent to issue the permit, the county's engineer and environmental specialist did not raise issues regarding drainage, contours, wetlands, and wildlife. (Tx-220). Although the County Attorney and one of its commissioners had been advised by the District that there would be no impact to County property or rights-of-way, the County Engineer was not asked to investigate whether the drainage from the proposed project would remain on the site as stated in the application and as concluded by the staff of the Water Management District prior to the County challenging the issuance of the permit. (Tx-198,199) The County Engineer looked at the Water Management District's file on the issuance of the permit only after the County had filed its challenge. (Tx-209). The County Engineer had expressed concerns to the District staff about suspected changes in the topography on the site. (Tx-208). When the Water Management District was made aware of the County engineer's concerns, a new survey was conducted which resolved the County engineer's concerns about changes in topography on the site, and revealed that the tops of the berms were as high or higher than represented in the application. The results of this new survey was shared with County Engineer prior to the original hearing. (Tx-208,211-219). The County's environmental specialist did not review the complete file on the Williams' permit application until within two weeks of the original formal hearing, well after the challenge was filed. (Tx-161). The environmental specialist had no basis to question the validity of the number of acres of wetlands stated in the second permit. (Tx-176). The environmental specialist did not have any personal knowledge regarding the flora or fauna on the site because she had never been on the site, and her information was based solely on material provided to her by individuals living in the vicinity of the site. (Tx-176,180-181). She did not have authority to enter on the site because the County had no enforcement authority over endangered species. When the county's concerns about endangered species on the site were voiced, an on site inspection was conducted by the District. The District staff found no endangered species, or evidence of endangered species, or persons who had seen them on the site. The District staff's findings were shared with the County prior to the original hearing. (Tx-220.) Williams incurred attorney fees and expenses responding to the challenge of the County to issuance of the surface water drainage permit. The expenses incurred by Williams were primarily in response to the County's allegations of adverse impacts to County property. However, it is impossible to reasonably separate the expenses incurred by Williams responding to the allegations of off-site impacts from those related to standing based upon general police power. The County's assertion of general regulatory authority was primarily a legal argument which was addressed by the District's staff. Williams sought no fees for the appeal which was litigated principally by the District and County. By agreement of the parties the evidence on the amount of attorney fees and rate were submitted by affidavit without agreement regarding the facts asserted in the affidavits. The rate charged by counsel for Williams of $195/hour was a reasonable rate for the type of service provided in the geographic area in which it was provided considering the skill and experience of counsel. The number of hours billed through preparation of the post hearing briefs in the original formal hearing in this case, 160.25 hours, was not excessive given the number of depositions taken, the motions hearings which were held, and the legal and factual issues raised. The Williams' affidavits of attorney's fees and expenses are as follows: Attorney fees thru original hearing: $31,248.75 Estimate of costs related to preparation and service of Motion for Attorneys Fees and Expenses: $ 1,560.00 Teleconference charges on motion to compel: $ 127.73 Outside copying expense: $ 8.73 Expert Witness fee: $ 1,277.90 Court Reporter fees for depositions & transcripts: $ 1,692.45 Expert fees on Motion for Attorney Fee and expenses: $ 788.00 24. The attorney's fees, expert witness fees, and costs incurred by Williams in the hearing on attorney fees May 10, 1995 of $3,894.81 are reasonable. Williams incurred an expense of $1,019.00 for publication of the transcript in the almost seven hour hearing.

Florida Laws (5) 120.52120.57120.6857.10557.111
# 7
SOUTHWEST FLORIDA WATER MANAGEMENT DISTRICT vs WILLIAM D. GOING, 20-005557 (2020)
Division of Administrative Hearings, Florida Filed:Pinellas Park, Florida Dec. 28, 2020 Number: 20-005557 Latest Update: Jul. 02, 2024

The Issue Did Respondent, William D. Going, willfully and intentionally violate Florida Statutes and Southwest Florida Water Management District (District) rules regulating well construction? If he did, what corrective action is appropriate?

Findings Of Fact William Going is a licensed water well contractor. He has held License Number 1564 since 2007. Mr. Going is a managing member of Going Irrigation, Inc., and conducts business under that name. Mr. Going constructed four sand point irrigation wells at a residential property in St. Petersburg, Florida. He did not have and had not applied for a Well Construction Permit (WCP). 1 All citations to Florida Statutes are to the 2020 codification unless noted otherwise. 2 The findings are based upon the evidence admitted at the hearing and the stipulations of the parties. Mr. Going did not call or otherwise contact the District to request a WCP. The District operates an online permitting system called the Water Management Information System (WMIS). The District will issue a WCP based upon a telephone call, an application on its website, a faxed application, a mailed application, or a hand-delivered application. The District routinely issues permits within two hours of receiving an application, often within ten minutes to half an hour. The District's application system operates from 7:00 a.m. to 10:00 p.m. It is infrequently offline for a few hours. While quick, the process reviews significant information. It verifies that the well location is sufficiently distant from septic systems, verifies construction methods and materials, and verifies, if the well is for drinking water, that the well is not too close to a contamination site. Mr. Going is a registered and experienced user of WMIS. The District learned of the unpermitted wells on April 28, 2020, when it received an anonymous complaint. On May 5, 2020, approximately ten days after he constructed the wells, Mr. Going submitted WCP Application 889173 for construction of the four already completed sand point irrigation wells. He did not disclose that they were already completed. He falsely represented them as proposed. The District approved the application on May 6, 2020, and issued WCP 889173 to Mr. Going. On June 11, 2020, Mr. Going submitted four Well Completion Reports for the wells, falsely representing that each was completed on May 7, 2020. This was more than 30 days after Mr. Going completed the wells. Mr. Going claimed at the hearing that he tried to apply for a WCP for four or five days before constructing the wells but was locked out of the WMIS. Mr. Going said that his son usually obtained permits online for the company. He also claimed that he tried to apply online on April 24 and 25, 2019. His claims are not persuasive. There is no question that Mr. Going knew the requirements for obtaining a permit and reporting completion. In 2009, in Order No. SWF 09- 017, the District imposed a $500.00 fine and assessed five points against his license for an almost identical offense. In that case, Mr. Going also constructed a well without a permit from the District or applying for a permit. In that case, like this one, he sought to excuse failure to apply for a permit by claiming difficulties with the website. In that case he blamed his wife's unfamiliarity with computers, rather than his own, for failure to apply. In that case, like this one, he applied for and obtained a permit after constructing the well. Mr. Going knowingly and willfully constructed four unpermitted wells, filed a WCP application more than thirty days after he completed the wells, and misrepresented the dates of completion in the WCP completion reports that he filed with the District. Mr. Going tries to characterize his after-the-fact misrepresentations as mitigation. But they were not. Mitigation would have been contacting the District to advise it of the wells' unpermitted construction and the asserted justification for it. Furthermore, his misrepresentations deprived the District of the chance to prevent construction of the wells using improper materials or near a septic tank or contaminated location.

Florida Laws (4) 120.569120.57120.574120.68 Florida Administrative Code (4) 40D-3.04140D-3.41162-531.30062-531.450 DOAH Case (1) 20-5557
# 8
NATIONAL AUDUBON SOCIETY, INC.; COLLIER COUNTY AUDUBON SOCIETY, INC.; FLORIDA WILDLIFE FEDERATION; CONSERVANCY OF SOUTHWEST FLORIDA; AND FRANKLIN ADAMS vs I.M. COLLIER J.V. AND SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 06-004157 (2006)
Division of Administrative Hearings, Florida Filed:Naples, Florida Oct. 26, 2006 Number: 06-004157 Latest Update: Sep. 17, 2007

The Issue The issue is whether to approve an application by Respondent, I.M. Collier, J.V. (Collier), to modify its Environmental Resource Permit (ERP) No. 11-02031P (2002 Permit) by changing the surface water management system (SWMS) for a proposed residential and golf course development in Collier County (County), Florida, known as Mirasol.

Findings Of Fact Based on the evidence presented by the parties, the following findings of fact are made: The Parties National Audubon Society, Inc. is a not-for-profit corporation (incorporated outside the State of Florida) while Collier County Audubon Society, Inc., Florida Wildlife Federation, and Conservancy of Southwest Florida are Florida not-for-profit corporations. All are environmental organizations. Franklin Adams is a resident of the County and a member of each of the above organizations. Respondents have not contested Petitioners' standing based upon the stipulated facts set forth in the parties' Pre-Hearing Stipulation. The District is a water management district with the power and duty to exercise regulatory jurisdiction over the administration and enforcement of ERP criteria pursuant to Chapter 373, Florida Statutes, and Florida Administrative Code Title 40E. Collier is the holder of the 2002 Permit authorizing the construction of a SWMS to serve the Mirasol project, a large development located in the County. The parties have stipulated that Collier has the administrative, legal, and financial capabilities to undertake the proposed activity. Fla. Admin. Code R. 40E-4.301(1)(j). The Project Site The Mirasol project consists of approximately 1,713.45 acres located on the north side of Immokalee Road and the Cocohatchee Canal (Canal) in the northern half of the County, approximately three miles east of the intersection with Interstate 75. The property spans three sections of land, the northern third of the property encompassing Section 10, the middle third encompassing Section 15, and the southern third encompassing most of Section 22. The site also includes a peninsula of land extending east of Section 10, encompassing the northernmost quarter of Section 11. The site is bounded on the south by the Canal and Immokalee Road and on the east by an existing residential development known as Heritage Bay, which was previously a rock- mining quarry. To the west of the site, running north to south, are two other proposed residential developments known as Parklands Collier and Terafina/Saturnia Falls and an existing residential and golf course community known as Olde Cypress. There are other existing and proposed residential developments and farm fields to the north of the site. The site is located southwest of the Corkscrew Swamp Sanctuary (Corkscrew Swamp), which is owned by the National Audubon Society, Inc., and appears to stretch from Immokalee (in the northeastern part of the County) south and southwestward through parts of the County. Corkscrew Swamp sits roughly at the center of a 315-mile watershed, much of which is comprised of short hydroperiod wetlands which dry down completely during the late winter and spring and become inundated again in the late summer and fall during the wet season. This water gradually sheet flows down a very slight downhill gradient toward the south and west. A portion of the sheet flow travels southwest in the vicinity of the site. The region has experienced occasional floods, the most severe of which occurred in 1995. At the direction of the District, the cause of the flooding was investigated in the South Lee County Watershed Study (Study), which concluded that the watershed discharges through a variety of outfalls, but that historic connections to downstream conveyances like the Canal were severed by the construction. While downstream conveyances exist, the Study concluded that connections between upstream flows and downstream conveyances should be enhanced or restored. In the late 1990s, the Canal was improved to increase its conveyance capacity. A berm was constructed by the Big Cypress Basin Board (Basin Board), a legislatively-created entity which manages water resources in the County, on the northern bank in the vicinity of, and across from, the Mirasol site. This berm prevented historic wet season sheet flow from reaching the Canal through the project site, except for a few culverts located along that water body. The Basin Board also built a 1,000-foot-long hardened concrete weir on the north side of the Canal a few thousand yards west of the project site. This weir provides the primary outlet for sheet flow in and around the Mirasol site. Currently, upstream drainage flows in a southwesterly direction across Section 10. As the water moves south to the Canal, the flow becomes constricted down to a 580-foot wide gap between the Olde Cypress residential development and commercial developments along Immokalee Road to the east. This constricted area further narrows to a 270-foot wide opening before the sheet flow reaches the 1,000-foot weir and discharges into the Canal. During a 3-day, 25-year storm event, a combined peak flow of 553 cubic feet per second (cfs) of water is discharged into the Canal through the 1,000-foot weir, but the Mirasol property only conveys a small portion of this water (around 20 cfs) through culverts in the Canal berm. Most of the water flows to the west of Mirasol where it passes through the narrow gap and over the 1,000-foot weir. Around 1,431 acres of the 1,714-acre site are jurisdictional wetlands. However, these wetlands are in poor condition due to existing impediments to sheet flow, artificially high water levels during the wet season, and heavy infestation of exotic species, principally melaleuca. Permit History In February 2002, the District issued the 2002 Permit approving the construction of a SWMS to serve two 18-hole golf courses, a single-family residential community, a golf course clubhouse and parking area, golf course maintenance facilities, sales facility, and parking area. The issuance of the 2002 Permit was not challenged. The SWMS included a 36.5-acre flow-way (Flow-Way) that encircled the northern boundary of the development in Section 15 and extended off-site and across adjacent properties to the west. (If constructed, the Flow-Way would be a 200-foot wide, 4-foot deep, 89-acre channel, more than half of which would have been located on the Saturnia Falls/Terafina and Olde Cypress properties.) Besides providing a conveyance function for the Mirasol site, the Flow-Way also enhanced flood protection for other properties by accelerating conveyance of floodwaters to the Canal and reducing peak flood stages by 0.4 feet during a three-day, 25-year storm event. The District included Special Condition 26 in the 2002 Permit, which required construction of the Flow-Way before the remainder of the project could be constructed. The 2002 Permit authorized Collier to directly impact (fill or excavate) 568.66 acres of wetlands within the footprint of the development. Additionally, 39.5 acres of wetlands, which were isolated remnant strips along the golf courses within the development, were considered secondarily impacted and assessed a thirty-three percent reduction in functional value. Mitigation for the project consisted of preservation and enhancement of wetlands and uplands on site. Enhancement of the preserve areas was primarily credited to the eradication of malaleuca and other exotic species and replanting with appropriate native vegetation. Permit conditions required management of the preserve areas to prevent a recurrence of exotic species. The preserve areas included an 846.95-acre external preserve area to the north and northeast of the area to be developed. It was anticipated that this northern preserve area would ultimately be donated to an existing mitigation area known as the Corkscrew Regional Ecosystem Watershed, along with an interest-bearing fund to ensure perpetual management. In December 2005, the United States Army Corps of Engineers (Corps) denied Collier's federal wetlands permit application for the project and the Flow-Way. Because of this denial, in May 2006 Collier submitted an ERP application with the District seeking to modify the 2002 Permit by revising the SWMS and removing the Flow-Way. On October 12, 2006, the District Governing Board approved a modification to the 2002 Permit, which authorized an alternate SWMS to serve the golf course and residential development (2006 Permit). Petitioners' challenge to the proposed modification followed. The 2006 Modification Because of the Corps' denial of its application, Collier was required to remove the Flow-Way and redesign the project's SWMS. The most substantial change in the project was the removal of the Flow-Way and associated control structures and its replacement with a series of interconnected lakes running from north to south through the property allowing for the pass-through of surface waters from the area north of the development site into the Canal. The modification does not alter the boundaries and location of the development. However, the revised SWMS includes: five controlled basins with a total area of 718.43 acres, each of which provides treatment of stormwater prior to discharging into the pass-through system; 45.16 acres of interconnected lakes serving as a pass-through for surface waters from the north; 2.12 acres of perimeter berm backslope/ buffers/spreader swales; and 7.27 acres along the Canal for the existing 100-foot wide canal easement and proposed canal contouring. These changes also required elimination of the 39.5 acres of remnant wetlands inside the development that had previously been assessed as secondarily impacted. Also, there were 0.68 acres of additional impacts resulting from slight changes in the internal site design due to the SWMS. To partially offset these impacts, the internal wetland preserves were enlarged by 13.32 acres. The remaining impacts were mitigated with mitigation credits from the Panther Island Mitigation Bank (PIMB). (The PIMB holds a mitigation bank permit issued by the District for a wetland restoration project in Southwest Florida.) The main preserve was left unchanged, except that 36.5 acres previously dedicated to construction of the Flow-Way will be added to the main preserve and similarly enhanced and preserved. In summary, as modified under the 2006 Permit, the total onsite mitigation consists of the preservation and enhancement of 830.89 acres of wetlands, preservation of 109.58 acres of uplands, and the purchase of a total of 5.68 credits from the PIMB. At hearing, Collier also agreed to purchase from the PIMB an additional 5.68 credits within the Basin for a total of 11.36 credits. The ERP Permitting Criteria To obtain an ERP, an applicant must satisfy the conditions in Florida Administrative Code Rules 40E-4.301 and 40E-4.302. The first rule focuses primarily on water quantity, environmental impacts, and water quality, while the second rule generally requires that a public interest balancing test be made, that cumulative impacts, if any, be considered, and that the District consider past violations, if any, by the applicant of District or Department of Environmental Protection (DEP) rules. (The parties have cited no prior violations by the applicant that should be considered.) Besides these two rules, a number of BOR provisions which implement the rule criteria must also be taken into account. If an applicant proposes to modify an existing ERP, as it does here, Florida Administrative Code Rule 40E-4.331(2)(a) comes into play and requires that the District review the application to modify the ERP "using the same criteria as new applications for those portions of the project proposed for, or affected by, the modification." Under this rule, those portions of the project altered or affected by the modification are reviewed under the current ERP criteria, but otherwise the 2002 Permit is not the subject of review in this case. Therefore, the District's review includes only that portion of the existing permit that is proposed to be modified or affected by the modification. In this case, the 2006 design is very similar to the 2002 design, and the project's footprint, control elevations, roadway network, southern outfall, and main preserve are unchanged. However, as pointed out below, since most of the engineering-related components of the SWMS were affected by the Flow-Way's removal, the District reassessed the hydrologic components of the internal water management system and the pass- through lake system for levels of flood protection and water quality treatment. Because most of the engineering-related components of the SWMS for the project were modified as a result of the removal of the Flow-Way, the District staff reassessed the project's hydrologic calculations associated with levels of flood protection and reassessed the project's water quality treatment volumes applying the currently existing ERP criteria. As to wetland impacts and mitigation, review of the wetland impacts for the 2006 Permit was limited to an analysis of additional wetlands impacts associated with the modification. This was primarily the elimination of the previously permitted, secondarily impacted wetlands. Thus, only the additional wetlands impacts due to the revised SWMS are considered under the currently existing ERP criteria. The 2006 Permit made only slight changes to the project's wetland impacts and mitigation components authorized under the 2002 Permit. The project's footprint was not changed and the main mitigation area (the Northern Preserve) was unaffected by the changes except that 36.50 acres were actually added to that preserve as a result of the removal of the Flow- Way. Collier did not receive any credit in its mitigation analysis for the additional acreage that will become part of the preserve due to the removal of the Flow-Way. Surface Water Management Criteria As noted above, the ERP criteria in Florida Administrative Code Rule 40E-4.301 focus primarily on three areas of concern: water quantity, environmental impacts, and water quality. Related BOR provisions must also be considered. These areas of concern are discussed below. Water Quantity Florida Administrative Code Rule 40E-4.301(1)(a) requires that an applicant provide reasonable assurance that the construction of a SWMS "[w]ill not cause adverse water quantity impacts to receiving waters and adjacent lands." BOR Section 6.2 implements that provision and requires that a project be designed so that it is consistent with the downstream carrying capacity of the receiving waters. In other words, it must not exceed the capacity of downstream receiving waters, which in this case is the Canal. In making this determination, Section 6.3 of the BOR requires that the 25-year, 3-day design storm event be used. Collier complied with this requirement through an extensive hydrologic study conducted by its expert, Richard S. Tomasello, a former District employee. Applying a hydrologic model simulation known as S2DMM, the witness determined the appropriate amount of upstream sheet flow that would need to be routed through the project to avoid adverse water quantity and flooding impacts and calculated the correct dimensions of the intake weir to admit that flow into the project's pass-through system. The S2DMM model is a combination of other accepted models including the Sheet 2d, Massmod, and MBR models, which were developed by Mr. Tomasello, and they have been evaluated and used by the District on numerous occasions. In addition, the S2DMM model has been used for other flood studies in Collier and Lee Counties, and it will be used on a restoration project in Martin County. Based upon Mr. Tomasello's analysis, Collier incorporated a 100-foot-long intake weir with a crest elevation of 14.95 NGVD (National Geodetic Vertical Datum) along the northern boundary of the project to maintain existing upstream water elevations. Collier also complied with BOR Section 6.3, which requires the use of a 25-year, 3-day storm event to be used when computing the discharge rate for the project. The modified intake weir on the northern boundary includes two 3.5-foot wide rectangular notches set at an elevation of 14.00 NGVD, which will provide a "base flow" of up to 20 cfs into the pass-through lakes to mimic the current flow through the property. The determination of this base flow was made through an analysis of the existing culverts at the southern end of the property. While not required by the ERP criteria, Collier also performed a long-term analysis (using a four-year period of record) of the SWMS's effect upon water levels. This analysis demonstrated that the modified system would leave water levels in the wetland areas upstream of the project unchanged during normal rainfall and low-flow periods. This analysis provides additional assurances that the modifications to the SWMS will not affect the Northern Preserve. While Petitioners questioned the accuracy and reliability of the hydrologic study, and its specific application to this project, the criticisms are considered to be vague and unsubstantiated. As noted above, the model has been previously accepted for use in South Florida, and Petitioners' expert conceded he did not have enough information to determine the model's accuracy. The more persuasive evidence established that the hydrologic study submitted by Collier included the relevant available data and was prepared by competent professionals knowledgeable in the field. The claim of Petitioners' experts that they lacked sufficient information to form an opinion on the accuracy of the modeling is not a sufficient basis to overcome the evidence submitted by Collier to meet this criterion. The project's discharge rate in 2006 will not exceed what was permitted in the 2002 Permit. During the 25-year, 3-day storm event, the existing discharge from the project site and the natural area west of the project site into the Canal is 553 cfs. Based on modeling of the modified SWMS, the total discharge from the pass-through system will be 529 cfs, or 24 cfs less than the project's existing pre-development discharge. The discharges resulting from the project as modified in 2006 will not exceed the capacity of the Canal as required by Section 6.3 of the BOR. Accordingly, Collier has provided reasonable assurance that the discharge rate allowed for its project would not be exceeded, as required in Section 6.2 of the BOR. Section 6.8 of the BOR requires that a project allow the passage of drainage from offsite areas to downstream areas, which is necessary to demonstrate that off-site receiving water bodies are not being adversely affected. Collier complied with this provision by conducting the hydrologic analysis using the 25-year, 3-day design storm event, which demonstrated that the discharge rate would be directed to the southern discharge point allowing for the passage of drainage from offsite areas to the downstream areas. The evidence also shows that the current predominant sheetflow from areas outside the project passes through a narrowly constricted area west of the project and discharges into the Canal over an existing concrete weir. See Finding of Fact 9, supra. Only a small portion of the upstream waters currently discharge through the Mirasol site. Petitioners' allegation that the construction of the project will further constrict the sheetflow area is rejected, as the constriction of sheetflow will continue to exist whether the project is built or not. The evidence also shows that the project will not further constrict the flow because it will allow for the pass-through of water from outside the project area. Under the 2002 Permit, the Flow-Way was designed to aid in the diversion of upstream flows around the project. Under the 2006 modifications, the pass-through lake system will convey up to forty percent of the upstream flow through the development which complies with the provisions of Section 6.8 of the BOR. As indicated above, during periods of lower water levels, the notches in the weir along the northern boundary will allow for the flow to pass onto the project site consistent with existing conditions. During major storm events, water will pass over the weir into the pass-through lake system to be conveyed to the Canal. Therefore, Collier has provided reasonable assurance that the criteria in Section 6.8 have been met. Section 6.10 of the BOR requires that the project be designed to conserve water and site environmental values and not lower the water table or groundwater or over-drain wetlands. Section 6.11 of the BOR provides that the control and detention elevations for the project must be established at elevations to accomplish the objectives of Section 6.10. The latter section is adhered to when the control elevations proposed for a project are established consistent with the onsite wetland conditions. In this case, the control elevations for the wetlands and surface water management lakes are essentially the same as the design in the 2002 Permit. Collier has set the control elevations above the average wet season water table (WSWT) for the area, thereby ensuring that the SWMS will not over-drain and will conserve fresh water. Section 6.11 of the BOR addresses Detention and Control Elevations which are intended to assist in complying with the provisions of Section 6.10. The SWMS design control elevation maintains the detention component and the control (wetland protection) elevations in the previously approved SWMS. The control elevations were set by the design engineers in consultation with Collier's wetland ecologist taking into account the ground elevations and biological indicators. The control elevation for the pass-through system and internal drainage basins work in conjunction with the control elevation along the northern boundary of the project and the control elevation for the discharge point along the southern boundary to ensure that the project does not overdrain the wetlands and to preserve the project site's environmental values. By setting the control elevation above the WSWT, the design ensures that the wetlands will not be drawn down below the average WSWT and the SWMS will not over-drain them. Section 6.10 also requires that a project not lower water tables so that the existing rights of others would be adversely affected. Again, based on the control elevations, the water table is not expected to be lowered so there should be no effect on the existing rights of others. Collier must further demonstrate that the site's groundwater recharge characteristics will be preserved through the design of the SWMS. Collier complied with this requirement by setting the control elevations above the average WSWT, allowing standing water in the wetland preserves to recharge the groundwater. The ability of the SWMS to accept flows from the Northern Preserve conserves freshwater by preventing that water from being discharged downstream. The SWMS leaves water elevations in the Northern Preserve unchanged. Consequently, water will remain in the wetlands for the same duration and elevations as in the existing conditions, thereby preserving groundwater recharge characteristics. Section 6.12 of the BOR prohibits lake designs that create an adverse gradient between the control elevations of the lakes and the adjacent wetlands. To satisfy this requirement, Collier set all control elevations at 13.4 - 13.5 NGVD while controlling the internal wetland preserves at a slightly higher elevation. Consequently, there is no adverse gradient and no potential for an adverse effect upon the internal preserves from adjacent lakes. Petitioners argued that the pass-through system would quickly lower water levels in the internal wetland preserves. However, the internal wetlands are still protected from drawdown because there are control structures set at or above the wet season elevation between the pass-through lakes and internal wetlands. They also argued that the internal wetlands would be overdrained during the dry season by the deep lakes. However, no witness presented any real analysis to back up this contention. Indeed, the pass-through lakes are only twelve feet deep, and the wetlands are separated from all the lakes by protective berms to avoid any drawdown. In summary, Collier has provided reasonable assurances that the proposed modification in the 2006 Permit will not cause adverse water quantity impacts to receiving waters or adjacent lands and will not exceed the capacity of the downstream receiving waters (the Canal). Flooding Florida Administrative Code Rule 40E-4.301(1)(b) requires Collier to demonstrate that the project "[w]ill not cause adverse flooding to on-site or off-site property." BOR Section 6.4 sets forth criteria and standards for implementing this requirement and provides that building floors be designed to be protected from a 100-year, 3-day storm event. BOR Section 6.5 provides criteria and standards for flood protection for the project's roads and parking lots. Collier complied with these provisions by providing construction plans demonstrating that the building floors and roads will be built higher than the 100-year, 3-day storm event. BOR Section 6.6 provides that a project may not result in any net encroachment into the 100-year floodplain. Collier was also required to comply with the historic basin provision in Section 6.7 of the BOR, which requires the project to replace or otherwise mitigate the loss of historic basin storage provided by the site. The level of encroachment into the 100-year flood plain and loss of historic basin storage attributed to the project are essentially unchanged from the 2002 design. The only difference between the 2002 Permit and the 2006 Permit is how the conveyance of flood water is provided. In 2002, the Flow-Way served this function, while the pass-through system provides it in the 2006 Permit. Collier's flood simulations demonstrated that the project will not alter flood stages during the 25-year and 100- year design storms, while the testimony of witnesses Tomasello and Waterhouse established that the project will not have adverse flooding impacts on adjacent properties, either alone or in conjunction with neighboring developments. Storage and Conveyance Florida Administrative Code Rule 40E-4.301(1)(c) requires that an applicant demonstrate that the proposed development "[w]ill not cause adverse impacts to existing surface water storage and conveyance capabilities." This criterion is closely related to paragraph (1)(b) of the same rule, which prohibits adverse flooding to onsite or offsite property. Section 6.6 of the BOR implements this provision and specifies the parameters for applying this criterion and prohibits a net encroachment between the WSWT and the 100-year event which will adversely affect the existing rights of others. Collier addressed this criterion through the hydrologic analysis submitted. As previously found, that model is the appropriate model to determine flood stages and to calculate the floodplain. Engineering Design Principles Florida Administrative Code Rule 40E-4.301(1)(i) requires an applicant to provide reasonable assurances that the SWMS "[w]ill be capable, based on generally accepted engineering and scientific principles, of being performed and of functioning as proposed." Section 7.0 of the BOR contains the specific standards and criteria to implement this rule. The evidence demonstrates that the SWMS is based on generally accepted engineering and scientific principles and is capable of performing and functioning as proposed. Section 8.0 of the BOR includes various assumptions and information regarding the design of the SWMS. By incorporating these assumptions into the design, Collier complied with Section 8.0. Water Quality Impacts Florida Administrative Code Rule 40E-4.301(1)(e) requires that the proposed modification "[w]ill not adversely affect the quality of the receiving waters such that the water quality standards set forth in Chapters 62-4, 62-302, 62-520, 62-522 and 62-550, F.A.C., including any antidegradation provisions of paragraphs 62-4.242(1)(a) and (b), subsections 62- 4.242(2) and (3), and Rule 62-302.300, F.A.C., and any special standards for Outstanding Florida Waters and Outstanding National Resource Waters set forth in subsections 62-4.242(2) and (3), F.A.C., will be violated." Stated more plainly, the proposed modifications must not adversely affect the quality of the Canal's waters such that State water quality standards will be violated. Section 5.2 of the BOR describes the District's standard water quality criteria. This provision, which requires a minimum of one-inch detention of stormwater, is referred to as a "presumptive criteria" because it is presumed that if an applicant provides the required one inch of detention, it meets Class III water quality standards, thereby satisfying the rule. As it did under the 2002 Permit, Collier satisfies the presumptive criteria with the 2006 design by providing the one- inch wet detention in its lake system. In fact, the system is designed to provide one and a half inches of treatment in the lake system thereby providing additional treatment. The receiving body of water for the project is the Canal. When the 2002 Permit was issued, the Canal was classified as a Class III water body. It is now classified by DEP as impaired for iron and dissolved oxygen. Because of this new classification, Collier must now comply with Section 4.2.4.5 of the BOR, which reads as follows: If the site of the proposed activity currently does not meet water quality standards, the applicant must demonstrate compliance with the water quality standards by meeting the provisions in 4.2.4.1, 4.2.4.2, and 4.2.4.3, as applicable, and for the parameters which do not meet water quality standards, the applicant must demonstrate that the proposed activity will not contribute to the existing violation. If the proposed activity will contribute to the existing violation, mitigation may be proposed as described in subsection 4.3.1.4. Collier demonstrated that neither short-term (during construction) nor long-term (during operation) water quality impacts will occur. It complied with the short-term requirements by submitting a Construction Pollution Prevention Plan detailing how water quality will be protected during the construction process. As to long-term impacts, the Terrie Bates Water Quality Memorandum (Bates Memo) prepared by District staff on June 11, 2004, provides guidance on the implementation of Section 4.2.4.5 for projects which discharge into an impaired water body. The document sets forth a number of design and operational criteria for the types of additional measures that can be incorporated into a project design to provide the necessary reasonable assurance. The Bates Memo suggests that an additional fifty percent of treatment be incorporated into a SWMS. Collier complied with this suggestion by designing the treatment lakes to provide an additional one-half inch of treatment for the additional fifty percent treatment. In addition to the one and one-half inch treatment, Collier is implementing six of the seven items the Bates Memo lists as potential options to consider. The long-term water quality requirement is addressed by Collier, in part, through an Urban Stormwater Management Plan, which details various source controls or best management practices to be implemented once the project is built and operating. Best management practices assist in ensuring that pollutants will not enter into the lake system. Collier is also implementing a stormwater pollution prevention plan and will utilize the lake system for additional treatment downstream. Collier has further agreed to planting the littoral zones as part of its design of the treatment lakes to provide additional pollutant removal. The design calls for an amount of littoral zones equal to twenty percent of the surface area of the treatment lakes. Collier has agreed to make a Water Quality Monitoring Plan a permit condition, even though such a condition was not included in the staff report. See Collier Exhibit 25. The Bates Memo includes as an option for meeting the long-term requirement a site-specific water quality evaluation of pre vs. post-development pollutant loadings. Collier has presented several such analyses, all of which indicate the post- development pollutant discharges from the site will be less than the pre-development. Mr. Barber prepared a pre vs. post- analysis using a 2003 methodology developed by Dr. Harper. The 2003 version of the Harper methodology is currently accepted by the Corps. (Although Petitioners' witness, a former Corps employee, suggested that the Corps' acceptance of the study was a "political" rather than a scientific decision, there is insufficient evidence to support this contention.) Besides his first analysis, at the direction of the District staff, Mr. Barber prepared a second analysis using the 2003 methodology with certain conservative assumptions that limited the pollutant residents time to fifty days and utilized lower starting concentrations for phosphorous and nitrogen than were recorded in the nearby monitoring stations. Based upon those reports, the District's staff concluded that Collier had provided reasonable assurances that the project met the criteria in BOR Sections 5.2 and 4.2.4.5. At the hearing, Mr. Barber presented a third analysis utilizing an updated methodology developed by Dr. Harper in February 2006. The 2006 methodology was developed after Dr. Harper conducted a study of water management district criteria throughout the state for DEP. All three of the analyses prepared by Mr. Barber concluded that the project would discharge less nitrogen and phosphorous into the receiving body in the post-development condition than is currently being discharged in the pre-development condition. In addition to the three water quality submittals from Mr. Barber, Collier provided an additional water quality analysis specific to the project prepared by Dr. Harper. See Collier Exhibit 26, which is commonly referred to as the Harper Report. The analysis evaluated the project's pre vs. post- development water quality loads and also concluded the project would not contribute to the impairment of the Canal. In preparing his analysis, Dr. Harper relied solely on the lakes for estimating removal of pollutants without accounting for any of the additional treatment expected to occur from the source control best management practices contained in the Urban Stormwater Management Plan, which means his report errs on the conservative side. The Harper Report concluded that iron discharges from the SWMS would be extremely low and substantially less than the Class III standard of 1 mg/L. Petitioners presented no specific evidence to counter these conclusions. Petitioners questioned the Harper Report's use of wetlands as part of the loading calculations and attacked his underlying methodology. However, the evidence is clear that wetlands contribute to the water quality constituents in the pre-development condition. This finding is based on data from monitoring stations located in the middle of Corkscrew Swamp, a statewide study on stormwater treatment and wetlands, and the United States Environmental Protection Agency's (EPA) assignment of nutrient loading rates to wetlands in its regional pollutant loading model. Ignoring the actual water quality in pre-development conditions would not be a true pre vs. post-development analysis. Finally, Petitioners' contention that the Harper methodology should not be considered as admissible evidence because it constitutes "novel" (and therefore unreliable) scientific evidence under the rationale of Frye v. United States, 293 F. 1013 (D.C. Cir. 1923), has been rejected. To begin with, the Frye test has not been accepted in Florida administrative proceedings. Moreover, the methodology is the basis for a new statewide rulemaking effort, has been accepted by the EPA, the Corps, and by the Division of Administrative Hearings in at least two proceedings, and has been subjected to two peer reviews. Petitioners also alleged that Collier failed to show that it complied with Florida Administrative Code Rule 62- 40.432(2)(a)1., a rule administered by DEP which requires that a new SWMS "[a]chieve at least 80 percent reduction of the average annual load of pollutants that would cause or contribute to violations of state water quality standards." However, this is a broad overstatement of DEP's rule. Also, there is no eighty percent removal efficiency requirement adopted or incorporated into any District rule or BOR criteria. See, e.g., Conservancy of Southwest Florida, Inc. v. G.L. Homes of Naples Associates II, LTD et al., DOAH Case No. 06-4922 (DOAH May 15, 2007, SFWMD July 11, 2007). Instead, the District's "presumptive criteria" is that one inch of volumetric treatment required in Section 5.2 of the BOR meets the Class III standards. If, as in this case, additional assurances are required, those assurances are met through implementation of the BOR Section 4.2.4.5. Finally, Florida Administrative Code Rule 62-40.110(2) provides that Rule Chapter 62-40 is "intended to provide water resource implementation goals, objectives, and guidance for the development and review of programs, rules, and plans relating to water resources." Also, Florida Administrative Code Rule 62- 40.110(4) states that "[t]his chapter, in and of itself, shall not constitute standards or criteria for decisions on individual permits. This chapter also does not constitute legislative authority to the Districts for the adoption of rules if such rules are not otherwise authorized by statute." Even if an eighty percent reduction standard applied, Collier has demonstrated that the project very likely will remove eighty percent or more of pollutants when additional low-impact development techniques, pollutant source reduction practices, and additional uncredited wet and dry detention capacity are considered. Based upon the evidence presented, Section 4.2.8 of the BOR regarding cumulative impacts for water quality is not applicable in this case. Collier's submittals provide reasonable assurances that the project will not be contributing to the water quality impairment of the Canal or contribute to any other water quality violation. Indeed, the information submitted indicates there will be an incremental improvement in the post-development condition as compared to existing. Since no contribution or impacts to water quality are expected, a cumulative impact analysis is not necessary to assess the extent of the impacts. The combination of all these water quality measures, when taken together, demonstrates that the 2006 Permit will not adversely affect the quality of receiving waters such that state water quality standards will be violated. Therefore, reasonable assurance has been given that Florida Administrative Code Rule 40E-4.301(1)(e) will be satisfied. Wetland Impacts Florida Administrative Code Rule 40E-4.301(1)(d) requires Collier to provide reasonable assurance that the modification of the SWMS "[w]ill not adversely impact the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters." In determining whether this criterion has been satisfied, it is also necessary to determine whether any 2002 permitted impacts should be subject to a second review in this case. Mitigation is a method by which an applicant can propose to impact certain wetlands on the project site in exchange for providing compensation in the form of preserving, enhancing, restoring, or creating wetlands or uplands to offset those impacts. As noted earlier, there has been no change to the wetland impacts or mitigation proposal as it relates to the Northern Preserve. See Findings of Fact 27 and 28, supra. As a result of the modified SWMS, there has been some additional impact to wetlands within the development area of the project. An additional 40.18 acres will be impacted under the 2006 Permit mostly due to the modified SWMS system. However, 39.5 acres of those wetlands were already considered secondarily impacted under the 2002 Permit. In addition, the preserve areas were expanded by 13.32 acres in the 2006 design. Thus, a portion of the impacts to those wetlands was already factored into the mitigation plan that was developed and approved for the 2002 Permit. As a result, there are 26 acres for which mitigation is necessary under the 2006 Permit. Section 4.3 of the BOR specifies criteria for mitigation proposed as part of an ERP application. Collier has proposed an acceptable mitigation plan for the new wetland impacts that will result from the project due to the proposed modifications incorporated in the 2006 Permit. Except for the mitigation for the additional wetland impacts, the mitigation plan for the 2006 Permit remains essentially unchanged from the 2002 Permit, including the Grading and Planting Plan, Monitoring Plan, and Mitigation, Monitoring, and Maintenance Plan. The onsite mitigation proposal includes preservation and restoration of wetlands through the removal of melaleuca and other exotic plants and replanting in areas of dense exotic species coverage. Significantly, Collier has not proposed any modifications that would change the effectiveness of the Northern Preserve in providing mitigation for the wetland impacts proposed and approved in the 2002 Permit. While Petitioners claim that the wetlands in the Northern Preserve may be subject to some changes in the level and seasonality of inundation as a result of the SWMS modifications, the evidence does not support those assertions. The revised SWMS will continue to allow water to flow through the Northern Preserve in a manner consistent with existing conditions while providing some flood control protection for extreme rainfall events. Petitioners also suggest that additional analysis regarding the timing and levels of inundation in the wetland preserves is necessary to fully determine the impacts of the modified SWMS on the wetlands. However, the more persuasive testimony indicates that the timing and levels within the wetlands will not be affected by the revised SWMS. The control elevations within the development area have not changed from the 2002 Permit, and these protect the onsite wetlands and ensure that those wetlands will function as expected. With respect to the internal wetlands within the development area, the control elevations have not changed from the 2002 Permit and the evidence establishes that the internal wetlands will continue to function and operate as contemplated in the 2002 Permit. There has been some relocation and reconfiguration of the internal wetland preserve areas that will actually enhance the value of the mitigation by connecting those wetland areas to other preserve areas. Petitioners further suggested that the wetland mitigation within the development area would not function as permitted in the 2002 Permit due to the spill over from the lakes to the wetlands. However, when the water reaches those internal wetland preserves, it has been treated to Class III water quality standards. Therefore, the mitigation values of those wetlands preserves will not be changed or affected due to water quality. Petitioners' objections to the wetland impacts and mitigation were primarily directed at the overall impacts rather than to the 2006 modifications. However, their witness was unaware of the values provided by the additional acres that will be impacted through the 2006 Permit. Therefore, a challenge to 2002 permitted wetlands impacts and mitigation is inappropriate in this proceeding. Functions To Fish and Wildlife and Listed Species Section 4.2.2 of the BOR implements Florida Administrative Code Rule 40E-4.301(1)(d) and provides that an applicant must provide reasonable assurances that a project will not cause adverse impact to the abundance and diversity of fish, wildlife, and listed species or their habitat. With respect to the 586.66 acres of wetland impacts permitted in the 2002 Permit, the 2006 Permit does not modify or affect the values that the wetlands provide to either the abundance or diversity of fish and wildlife. Review of the wetlands criteria as to those acres was finally determined in the 2002 Permit and should not be reopened. By relocating thirteen of the previously impacted acres so they are most closely connected to other wetlands, their value to fish and wildlife will increase. As explained by the District's witness Bain, if Collier had moved the preserve area and changed its functional value, the District would have been required to reevaluate the mitigation that had been accepted for the wetland impacts in the 2002 permit. In this case, however, because the Northern Preserve area did not change, the District's review is limited to the newly impacted wetlands internal to the development for which mitigation was not provided in the 2002 Permit. Section 4.2.2.3 of the BOR addresses the functional assessment of the values provided by the project's wetlands. The only wetland values assessed in the 2006 Permit were the additional wetland impacts that were not mitigated in the 2002 Permit. The evidence establishes that the current value of the wetlands is low due to the heavy melaleuca infestation, which is greater than fifty percent coverage in most locations and seventy-five percent or more in much of the area. Melaleuca has the effect of draining short hydroperiod wetlands. While Petitioners may disagree with how the wetlands were previously evaluated, nothing in the 2006 modification allows or requires a reassessment of their value. Section 4.2.2.4 of the BOR requires that a regulated activity not adversely impact the hydroperiod (the depth, duration, or frequency of inundation) of wetlands or other surface waters. Subsection (a) of this standard applies if the project is expected to reduce the hydroperiod in any of the project's wetlands. Conversely, subsection (b) applies if the project is expected to increase the hydroperiod through changing the rate or method of discharge of water to wetlands or other surface waters. Subsection (c) requires monitoring of the wetlands to determine the effects of the hydrological changes. Again, there is no basis for the District to reopen and reevaluate the wetlands for which mitigation has already been permitted. No evidence was presented to indicate that there would be any obstacles or problems to accomplishing the mitigation that was proposed and accepted in 2002. In any event, the engineering and biological testimony demonstrated that no change (neither a reduction nor an increase) in the hydrology on the preserved wetlands or the Northern Preserve will occur from what was permitted in the 2002 Permit. By analyzing the various biological indicators onsite and setting the control elevations within the SWMS and the wetlands (both the Northern Preserve and onsite preserve wetlands) above the WSWT, the project ensures that the appropriate hydrology will be maintained. Though the fish and wildlife are not expected to be adversely affected by the 2006 Permit, Collier will be conducting monitoring of plants and animals on the site as an extra measure of assurance as contemplated under BOR Section 4.2.3.4(c). Focusing on just the changes from 2002 to 2006, Petitioners' two experts conceded that the hydrology in the Northern Preserve and its value to wildlife and listed species (including the wood stork) would be benefited in the 2006 Permit over that contemplated in the 2002 Permit due to the removal of the Flow-Way. Secondary Impacts to Water Resources Florida Administrative Code Rule 40E-4.301(1)(f) requires a demonstration that the proposed activities "[w]ill not cause adverse secondary impacts to the water resources." A similar demonstration is required by Sections 4.1.1(f) and 4.2.7 of the BOR. In this case, the secondary impacts considered by the District were potential impacts due to the relocation and expansion of the buffer preserve areas to the perimeter of the project site. In conducting a secondary impact analysis, BOR Section 4.2.7 requires that the District consider only those future projects or activities which would not occur "but for" the proposed system. Here, the evidence demonstrated that no wetlands or other surface waters will be secondarily impacted by the modifications to the SWMS as part of the 2006 Permit. The undersigned has rejected Petitioners' contention that a proposed extension of County Road 951 through the development site should be considered a secondary impact in evaluating this project. This extension has been proposed for at least fifteen years and its precise configuration is unclear. It is not required to be built as a result of the project and there are no firm plans or contracts in place to construct the road. Although the road is listed on the County's transportation plan, it remains speculative as to if and when it will be built. Additionally, there is no evidence the County has any ownership interest in property for a road in the area identified by Petitioners. Witness Bain testified that the District examined the Collier County Public Records and an easement had not been granted to the County to build the road. i. Elimination and Reduction Florida Administrative Code Rule 40E-4.301((3) provides in part that "the provisions for elimination or reduction of impacts contained in the [BOR] shall determine whether the reasonable assurances required by subsection 40E- 4.301(1) and Rule 40E-4.302, F.A.C., have been provided." Section 4.2.1.1 of the BOR implements that provision and provides that elimination and reduction of impacts is not required when: The ecological value of the function provided by the area of wetland or other surface water to be adversely affected is low based on site specific analysis using the factors in subsection 4.2.2.3 and the proposed mitigation will provide greater long term ecological value than the area of wetland or other surface water to be adversely affected; . . . In accordance with that section, Collier was not required to implement practicable design modifications to reduce or eliminate impacts. The District did a site-specific analysis of the quality of the 39.5 acres of adversely affected wetlands, taking into consideration the condition of the wetlands, hydrologic connection, uniqueness, location, and fish and wildlife utilization. The unrebutted testimony is that the quality of the 39.5 acres of wetlands to be impacted by the 2006 Permit is low and these wetlands were already previously authorized to be secondarily impacted. The low quality wetlands are melaleuca dominated making them not unique. The mitigation will provide greater long-term ecological value than the impacted wetlands. As noted on page 10 of the Staff Report, there will be a larger, contiguous mitigation area to offset direct impacts to previously preserved, but secondarily impacted wetlands and the preservation/enhancement of the external preserve area. The 2006 Permit provides that 5.68 credits are required to be purchased in the PIMB. Collier has advised the District that 27.68 credits are being purchased pursuant to its Corps permit. Thus, Collier will be purchasing more credits than required by the District. Witness Bain took this additional mitigation into account in determining whether the proposed mitigation will provide greater long term ecological value than the area impacted. While the Corps permit is an entirely separate permit action, Collier has agreed to include an additional 5.68 credits within the Basin beyond what is required in the Staff Report as a condition to this 2006 Permit. Therefore, the mitigation is clearly of greater long-term ecological value than the area impacted. Additional Requirements Florida Administrative Code Rule 40E-4.302 imposes additional requirements on an ERP applicant, including a cumulative impact assessment, if appropriate, and satisfaction of a public interest test. Cumulative Impacts Florida Administrative Code Rule 40E-4.302(1)(b) requires that an applicant demonstrate the project "[w]ill not cause unacceptable cumulative impacts upon wetlands and other surface waters as set forth in subsections 4.2.8 through 4.2.8.2 of the [BOR]." Cumulative impacts are the summation of unmitigated wetland impacts within a drainage basin, and a cumulative impact analysis is geographically based upon the drainage basins described in Figure 4.2.8-1 of the BOR. See Florida Wildlife Federation et al. v. South Florida Water Management District et al., 2006 Fla. ENV LEXIS 49 at *49, DOAH Case Nos. 04-3064 and 04-3084 (DOAH Dec. 3, 2006, SFWMD Dec. 8, 2006). Also, Section 373.414(8)(a), Florida Statutes, requires the District to consider the cumulative impacts upon surface water and wetlands within the same drainage basin. Thus, the cumulative impact analysis applies only when mitigation is proposed outside of the drainage basin within which the impacts are to occur. Broward County v. Weiss et al., 2002 Fla. ENV LEXIS 298 at *29, DOAH Case No. 01-3373 (DOAH Aug. 27, 2002, SFWMD Nov. 14, 2002). In this case, all of the proposed mitigation associated with the 2006 Permit modifications is located within the West Collier Basin. The evidence shows that the mitigation will offset the impacts to wetlands proposed in the 2006 Permit. Therefore, since the mitigation will be performed in the same Basin as the impacts and will offset the adverse impacts, the District must "consider the regulated activity to meet the cumulative impact requirements" of Section 373.414(8)(a), Florida Statutes. A new cumulative impacts analysis based on removal of the Flow-Way is not necessary because the modification does not change the cumulative impacts analysis conducted in the 2002 Permit. Since the Flow-Way was not considered a wetland impact or contributing to the mitigation in the 2002 Permit, its removal does not affect the adequacy of the previously conducted cumulative impacts analysis or the mitigation. Accordingly, there is no need for a new cumulative impact analysis with regards to the Northern Preserve. Finally, contrary to Petitioners' assertion, there is no rule or BOR provision which requires Collier to mitigate for the alleged prior impacts of other projects. Public Interest Test In addition to complying with the above criteria, because the project is located in, on, or over wetlands or other surface waters, Collier must also address the criteria contained in the Public Interest Test in Florida Administrative Code Rule 40E-4.302(1) and Section 4.2.3 of the BOR by demonstrating that the project is not contrary to the public interest. See also § 373.414(1)(a), Fla. Stat. Since the project does not discharge into an OFW or significantly degrade an OFW, the higher standard of "clearly in the public interest" does not apply. In determining compliance with the test, Florida Administrative Code Rule 40E-4.302(1)(a) requires that the District do so by "balancing the [seven] criteria [in the rule]." Findings with respect to each of the seven criteria are set out below. (Except for pointing out that the District does not have an adopted rule which provides more specific detail on how to perform the balancing test than is now found in paragraph (1)(a), and a contention that witness Bain's testimony was insufficient to explain how the staff balanced those factors, Petitioners did not present any evidence at hearing or argument in their Proposed Recommended Order in support of their contention that the above rule, BOR section, or the associated statute have been applied by the District in an unconstitutional manner.) Whether the regulated activity will adversely affect the public health, safety, or welfare or the property of others (40E-4.302(1)(a)1.) Collier provided reasonable assurances that the project will not cause any onsite or offsite flooding nor cause any adverse impacts to adjacent lands because the SWMS is designed in accordance with District criteria. Also, the post- development peak rate of discharge does not exceed the allowable discharge rate. Further, the project will not cause any environmental hazards affecting public health, safety, or welfare. The project is considered neutral as to this factor. Whether the regulated activity will adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitats (40E-4.302(1)(a)2.) For the direct wetland impacts under the 2006 Permit, Collier proposes mitigation which has not changed from the 2002 Permit. The mitigation proposed was previously determined to offset potential impacts to fish and wildlife and particularly wood stork habitats. The evidence indicates that the mitigation plan for the Northern Preserve will improve wood stork habitat from its current melaleuca infested condition. For the additional 40.18 acres of wetland impacts authorized in 2006, the mitigation is of greater long-term value. Thus, the project should be considered positive as to this factor. Whether the regulated activity will adversely affect navigation or the flow of water or cause harmful erosion or shoaling (40E-4.302(1)(a)3.) The parties have stipulated that the project will not adversely affect navigation. In addition, no evidence was introduced to suggest that the project's construction would result in harmful erosion or shoaling. Whether the regulated activity will adversely affect the fishing or recreational values or marine productivity in the vicinity of the activity (40E-4.302(1)(a)4.) The project does not provide any fishing, recreational values, or marine productivity. Therefore, the project is neutral as to this factor. Whether the regulated activity will be of a temporary or permanent nature (40E-4.302(1)(a)5.) It is undisputed that the project is permanent in nature. Even though the project is permanent, it is considered neutral as to this factor because mitigation will offset the permanent wetland impacts. Whether the regulated activity will adversely affect or will enhance significant historical and archaeological resources under the provisions of Section 267.061, F.S. (40E- 4.302(1)(a)6.) The parties have stipulated that no significant archeological or historical resources have been identified on this site. Therefore, the project is considered neutral as to this factor. The current condition and relative value of functions being performed by areas affected by the proposed regulated activity (40E-4.302(1)(a)7.) The current condition and relative value of functions being performed by the areas affected by the project is low due to the melaleuca infestation. Project mitigation will restore 940 acres of poor quality wetlands and uplands, greatly enhancing their function and value. Therefore, the project should be considered positive as to this factor because the implementation of the mitigation offsets the wetland impacts and improves the current value. Summary of Public Interest Factors Overall, the project is no worse than neutral measured against any one of the criteria individually. Therefore, the project is not contrary to the public interest.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the South Florida Water Management District enter a final order granting the application of I. M. Collier, J.V. for a modification to Environmental Resource Permit No. 11-02031P. DONE AND ENTERED this 24th day of July, 2007, in Tallahassee, Leon County, Florida. S DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of July, 2007.

Florida Laws (8) 120.569120.57267.061373.413373.414403.4126.107.27
# 9
JOSEPH BELANGER, PATRICIA BELANGER, JEROME STRAUSS, AND SUSAN STRAUSS vs CONQUEST DEVELOPMENTS USA L.C., AND SOUTH FLORIDA WATER MANAGEMENT DISTRICT, 02-000116 (2002)
Division of Administrative Hearings, Florida Filed:Naples, Florida Jan. 09, 2002 Number: 02-000116 Latest Update: Sep. 30, 2002

The Issue The issue is whether an Environmental Resource Permit should be issued to Conquest Developments USA, L.C., authorizing the modification of an existing stormwater management system serving a residential development known as Silver Lakes in Collier County, Florida.

Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: Background In this environmental permitting dispute, Respondent, South Florida Water Management District (District), proposes to issue an Environmental Resource Permit (ERP) to Respondent, Conquest Developments USA, L.C. (Applicant), authorizing the modification of an existing stormwater management system serving a private, gated residential community known as Silver Lakes RV and Golf Club, Inc. (Silver Lakes) in unincorporated Collier County, Florida. As the agency responsible for the administration of the ERP program, the District has the authority to grant or deny the requested permit. Preliminary action approving the application was taken by the District on August 15, 2001. Silver Lakes is a 146-acre residential development located adjacent to, and on the east side of, County Road 951 approximately 1.5 miles south of the intersection of U.S. Highway 41 and County Road 951 in southwestern Collier County, Florida. The project site is a part of the larger development and consists of approximately forty undeveloped acres (40-acre site) just north of, and adjacent to, the residential community. If the application is approved, the Applicant would be allowed to construct an open storage facility on a 7.02-acre tract of land in the western part of the 40-acre site on which trailers, boats, motor homes, tow dollies, and similar items will be stored. It would also allow the Applicant to relocate previously permitted lots along the southeastern boundary of the 40-acre site which border the Silver Lakes development. Petitioners, Jerome and Susan Strauss, own Lots 14, 15, and 16 within Silver Lakes. Petitioners, Joseph H. and Patricia Belanger, own Lot 26 within Silver Lakes, which is adjacent to the proposed storage facility. For obvious reasons, the Belangers do not wish to have a storage facility next to their property. Rather, they and the other Petitioners have suggested that the storage facility be reduced in size and moved to a 3.0-acre site in the northeastern portion of the 40-acre site. The parties have stipulated that Petitioners have standing to bring this action. As reflected in the parties' Prehearing Stipulation, Petitioners contend that the proposed construction of the storage area will cause flooding, adverse secondary impacts, and adverse water quantity impacts; that the proposed activity will result in a violation of state water quality standards; that the proposed system will cause adverse impacts to surface water storage and conveyance capabilities, the value of functions provided to fish and wildlife and listed species by wetlands and other surface waters, and the conservation of fish and wildlife; that the Applicant has failed to minimize or avoid impact to jurisdictional wetlands to the greatest extent practicable; that the proposed site provides a wildlife corridor connected to protected lands directly to the west; that the proposed site is jurisdictional wetlands; that the Applicant has engaged in District activities without a permit; and that the proposed site is subject to a Declaration of Covenants, Conditions, and Restrictions. These objections, where relevant, have been grouped into five categories - wetlands, wildlife, secondary and cumulative impacts, water quality and quantity, and prior enforcement activities - and they are addressed separately below. Wetlands The District has adopted and incorporated by reference in Rule 40E-4.091(1)(a), Florida Administrative Code, a document known as the Basis of Review for Environmental Resource Permit Applications Within the South Florida Water Management District (Basis of Review). The standards and criteria found in the Basis of Review are used to determine whether an applicant has given reasonable assurances that the conditions for issuance of an ERP have been satisfied. Compliance with the criteria in the Basis of Review creates a presumption that the standard and additional conditions for issuance of an ERP in Rules 40E-4.301 and 40E- 4.302, Florida Administrative Code, respectively, have been met. See Section 1.3, Basis of Review. Section 4.2.1 of the Basis of Review generally requires that an applicant provide reasonable assurances that wetland impacts be eliminated or reduced to the greatest extent practicable. This can be done through the implementation of "practicable design modifications" to the project, or where adverse impacts still remain after such modifications, through mitigation. There are 36.82 acres of wetlands throughout the 40- acre site. If the application is approved, there will be adverse impacts to 9.9 acres of wetlands in the western portion of the site (where the storage facility will be located) and to 3.37 acres in the southeastern portion of the site. To avoid and minimize wetland impacts, the Applicant has been required to reduce the number of acres impacted from its original proposal, and to place the storage area on the western part of the 40-acre site near County Road 951. In the original application, the Applicant proposed to place the storage area in the eastern part of the site and to create a larger storage area. Although the western part of the 40-acre site contains higher quality wetlands than the central or eastern parts, the western area is not pristine, and it is substantially impacted by exotic species, such as wax myrtle and Brazilian pepper. In addition, the western area is adjacent to County Road 951, which reduces wetland functions and values, reduces habitat values because of increased light and noise encroachment, and increases risk to wildlife because of passing vehicles. Further, the central and eastern areas are adjacent to other undeveloped lands, and this creates the potential for larger tracts of preserved and enhanced wetlands and maximizes wetland functions and values. Impacts to wetlands will be adequately mitigated by the Applicant preserving and enhancing 26.92 acres within the 40-acre site in a recorded conservation easement; by monitoring and reporting on the on-site mitigation (easement) for a five-year period and by maintaining the property in perpetuity; by purchasing 3.66 mitigation credits of similar wetland habitat from the Panther Island Mitigation Bank; and by adhering to a remediation plan (found in the Special Conditions in the permit) to address any future deficiencies in the mitigation. Given these considerations, it is found that the Applicant has provided reasonable assurances that the wetland impacts from the proposed activities will be eliminated or reduced as required by Section 4.2.1 of the Basis of Review. Impact on Wildlife Section 4.2.2 of the Basis of Review requires an applicant to provide reasonable assurances that the activity will not impact the values of wetlands and other surface water functions so as to cause adverse impacts to the abundance, diversity, or habitat of fish, wildlife, and listed species. The primary agency responsible for the protection of wildlife is the Florida Fish and Wildlife Conservation Commission (Commission), and not the District. Therefore, Section 4.2.2 of the Basis of Review requires that the District provide the Commission with a copy of all ERP applications for its review and comment as to wildlife issues. In this case, the Commission offered no comments or objections regarding wildlife on the property in question. The evidence shows that listed and endangered species such as Florida panthers, wood storks, and Big Cypress fox squirrels have been spotted on infrequent occasions on the 40-acre site by residents of Silver Lake. However, the parties stipulated that there was no evidence of any nesting, denning, or breeding activity on the same site. Based on the evidence of record, including the Applicant's Protected Species Survey, it is fair to infer that there is limited or no use of the property by protected wildlife species. Indeed, Petitioners' own expert found no evidence of endangered or threatened species on the 40-acre site during his two inspections. Two Special Conditions have been incorporated into the permit to protect endangered, threatened, or other listed species. First, in the event that Big Cypress fox squirrels are observed on or near the property, Special Condition 24 requires that the Applicant prepare a habitat management plan, in consultation with the Commission, to address issues related to nesting habitat. Second, if any endangered or threatened species are ever found on the property, Special Condition 25 requires that the Applicant coordinate with the Commission or the U.S. Fish and Wildlife Commission for guidance or recommendations. Given the above, the evidence supports a finding that the Applicant has given reasonable assurances that the requirements of Section 4.2.2 of the Basis of Review have been satisfied. Secondary and Cumulative Impacts Section 4.2.7 of the Basis of Review requires that an applicant provide reasonable assurances that the proposed activity will not cause adverse secondary impacts to the water resources. At the same time, Section 4.2.8 requires that an applicant provide reasonable assurances that a regulated activity will not cause unacceptable cumulative impacts to wetlands and other surface waters within the same drainage basin as the regulated activity for which the permit is being sought. In providing the necessary reasonable assurances regarding cumulative impacts, Section 4.2.8.2 authorizes an applicant to use preservation and mitigation measures to prevent cumulative impacts. The more persuasive evidence shows that the project will not cause secondary impacts to wetlands. This is because a water quality berm system surrounds the wetlands, isolating the wetland system from the surface water management system; a 50-foot preserved area lies between the storage area and the adjacent property boundary to the north; the storage area is being placed in an area already secondarily impacted by County Road 951; and the wetland preservation area will be placed in the conservation easement. Further, the project will not cause secondary impacts to wildlife. This is because structural buffers will prevent future encroachment into the wetlands and distance any wildlife away from the more dense residential functions. These buffers include a 50-foot wide natural preserve on the north side of the storage area (Special Condition 26), an already-erected structural buffer to the south of the storage area (Special Condition 26), and a 17 to 21-foot structural buffer (planted with native vegetation or vegetated buffers) on the eastern side of the 40-acre site where the new lots are proposed. Except for two conclusionary opinion statements by Petitioners' expert, without further facts or explanation, no other evidence on secondary impacts was offered. The project will not cause cumulative impacts to the wetlands. This is because the proposed mitigation for the project adequately offsets the impacts of the 40-acre site, and the impacts from other permitted projects in the basin area have been sufficiently offset. In addition, very little property in the area remains to be developed, and there are no new applications before the District involving the same basin. In the event a new application may be filed, however, the District will require the applicant to offset any impacts associated with its project with buffers and conservation easements, like the Applicant in the instant case. Water Quantity and Quality Section 5.0 et. seq. of the Basis of Review contains water quality criteria that must be satisfied in order for an ERP to be issued, while Section 6.0 et. seq. addresses water quantity criteria for an ERP. Given the limited nature of changes to the existing system and the lack of a hydrologic connection to the wetlands, and for the following additional reasons, the Applicant has given reasonable assurances that the project complies with the water quality and quantity criteria. The project as designed includes a grass swale near the storage area on the western part of the 40-acre site. The rainfall and run-off from the storage area flows into an internal road, through the grass swale, into a storm drain, and then into the pre-existing water management system associated with the original permit for Silver Lake. The project also allows rainfall and run-off from the proposed lots on the southeastern border of the 40-acre site to sheetflow onto an internal road, where waters are collected in existing catch basins and conveyed into the previously permitted water management system associated with the original permit. Since the rainfall and run-off from the storage area and lots drain into the existing lakes (Lakes 1 and 2) that are part of the Silver Lakes water management system, those waters will be treated for water quality through wet detention before their eventual discharge to McIlvane Bay, which lies to the southwest of Silver Lake. The basin discharge rates, minimum floor elevations, road designs, parking lot designs, structure control elevations, and structure sizes are specified in the the District's Staff Report, and were set at or above the calculated design limitations to meet water quality and quantity requirements. Section 5.2.1(a)1. of the Basis of Review specifies that wet detention volume shall be provided for the first inch of runoff from the developed project. The evidence shows that the proposed system captures one inch of run-off over the entire site, which drains into the existing lake system to provide water quality treatment. The system is also designed to meet the relevant discharge rate requirements for a 25-year, 3-day storm event, and the minimum floor elevations were based on a 100-year, 3- day storm event. The wetland preserve area is outside the area served by the surface water management system, is not hydrologically connected to that system, and will not be affected by run-off from the storage area or lots. Just prior to the final hearing, the District added Special Condition 23 to create a 50-foot buffer zone along the southern boundary of the storage area for aesthetic purposes and to reduce secondary impacts. Implementation of that buffer must be in accordance with the staff report, will not change the surface water management system, will have no impact on water quality or flood control, and will be implemented after additional consultation with the District. Past Enforcement Rule 40E-4.302(2), Florida Administrative Code, requires that the District take into consideration past violations of various rules adopted by the District. No enforcement action relating to the property has ever been taken by the District against the Applicant for any violation of ERP requirements. Although Petitioners suggested that unpermitted fill activities have taken place on the southeastern part of the 40-acre site, an inspection by District personnel revealed that unpermitted activities were "not significant." Further, Special Condition 23 requires that the Applicant restore "that portion of the disturbed wetland area located in the southeast corner of the site which is to be included in the wetland preserve area." Therefore, any impacts to the 40-acre site resulting from past unpermitted activities have been considered and remedied.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the South Florida Water Management District enter a final order granting Permit Application No. 010223-5 of Conquest Developments USA, L.C., for an Environmental Resource Permit. DONE AND ENTERED this 24th day of July, 2002, in Tallahassee, Leon County, Florida. ___________________________________ DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of July, 2002. COPIES FURNISHED: Henry Dean, Executive Director South Florida Water Management District Post Office Box 24680 West Palm Beach, Florida 33416-4680 Anthony P. Pires, Jr., Esquire Woodward, Pires & Lombardo, P.A. 3200 Tamiami Trail North, Suite 200 Naples, Florida 34103-4105 Robert E. Murrell, Esquire Samouce, Murrell & Francoeur, P.A. 800 Laurel Oak Drive, Suite 300 Naples, Florida 34108-2713 Keith W. Rizzardi, Esquire South Florida Water Management District Post Office Box 24680 West Palm Beach, Florida 33416-4680 Kenneth B. Cuyler, Esquire Goodlette, Coleman & Johnson, P.A. 4001 Tamiami Trail North, Suite 300 Naples, Florida 34103-3556

Florida Laws (3) 120.569120.577.02