The Issue Whether Respondent violated section 489.13(1), Florida Statutes (2016)1/, by offering, contracting, or performing regulated construction services, for compensation, as charged in the Administrative Complaint; and, if so, what penalty should be imposed.
Findings Of Fact Petitioner is the state agency charged with the licensing and regulation of the construction industry, pursuant to section 20.165 and chapters 455 and 489, Florida Statutes. On September 29, 2016, by letter, the Broward County Environment Protection and Growth Management Department forwarded a complaint to DBPR indicating the subject matter "appears to fall within your area of jurisdiction." The complaint alleged that Ryan D. Kirkland, d/b/a The Shining Light Construction, Inc., represented himself as a licensed contractor, provided a quote, and cashed the check from the victim, Rayon Richards ("Richards"). DBPR assigned Sonya Roa-Zaiter ("Roa-Zaiter"), investigator, to investigate the complaint. During the investigation, Roa-Zaiter interviewed individuals and reviewed several documents to determine Respondent's licensure status and relationship with Richards. Roa-Zaiter discovered that on July 20, 2016, Respondent presented Richards with a written proposal ("proposal") to perform construction work at Richard's rental property, located at 3234 Northwest 31st Terrace, Oakland Park, Florida 33309. In the proposal, Respondent offered to perform regulated services for compensation in the amount of $1,500.00. Specifically, Respondent offered to replace a kitchen faucet, remove a dishwasher, install a new water line and replace exhaust fans. Respondent's proposal listed the company as "State License Insured," but contained the license number CGC 1518408, which is a certified general contractor license number that belongs to Bernard Forges. Bernard Forges did not give Respondent permission to use his license number. Respondent is not licensed and has never been certified or registered as a construction contractor in the State of Florida. Additionally, at all times material to the allegations in this matter, The Shining Light Construction, Inc., has not been an entity properly qualified or licensed in the practice of construction in the State of Florida. Roa-Zaiter also discovered during the investigation that on or about July 22, 2016, Respondent accepted $750.00 as partial payment to perform the services listed in the proposal and cashed the check for the services without performing any of the work. After DBPR completed the investigation, it was determined that Respondent offered to perform a regulated service for compensation without a license contrary to Florida law. On November 1, 2016, DBPR issued Respondent a Notice to Cease and Desist, which notified Respondent that he "may be practicing as a CONTRACTOR (in any trade) without the professional license or certification required by Florida law." On April 25, 2017, DBPR issued an Administrative Complaint charging Respondent with violation of section 489.13(1) for offering to perform regulated construction contracting services for compensation without holding an active and valid certification or registration. Respondent contested the Administrative Complaint and requested a hearing. Roa-Zaiter spent 18 hours and four minutes investigating Respondent's case. DBPR incurred $624.78 for the investigation relating to Respondent's actions in this case, excluding costs relating to any attorney's time.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation enter a final order: finding Respondent, Ryan D. Kirkland, a/k/a Ryan Dee Lon Kirkland, guilty of violating section 489.13(1), Florida Statutes; imposing an administrative fine of $3,000.00; and assessing costs in the amount of $624.78. DONE AND ENTERED this 19th day of January, 2018, in Tallahassee, Leon County, Florida. S JUNE C. MCKINNEY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 19th day of January, 2018.
The Issue The issue for consideration in this hearing is whether Respondent's license as a certified building contractor should be disciplined because of the matters set out in the Administrative Complaint.
Findings Of Fact At all times pertinent to the allegations herein, Petitioner was the state agency responsible for the regulation of the construction industry in Florida. Respondent, David P. Miller, was licensed as a certified building contractor under license number CB C039127 and was doing business as Great Southern Construction and Development, Inc. On March 14, 1988, Robert Crowley, a semi-retired real estate broker and promoter, and Treasurer of Enterprise Industrial Park, Inc., (EIP), entered into contracts with the Respondent to construct three buildings, A, B, and H, for it within the park boundaries. Building A was to house offices and retail space; building B was to house warehouse and offices; and building C was to house garage space. The construction was to be financed by an infusion of shareholders' money and by a construction loan from the Southland bank in the amount of $375,000.00. The loan was ultimately increased to $614,000.00 so that EIP could begin development of phase II of the park. The contracts provided for Respondent to be paid $110,000.00 for Building A, $67,000.00 for Building B, and $52,807.00 for Building H. The loan was obtained in phases. The developers had outlined the project to bank officials who approved it, initially, for development of the park and construction of four buildings. Phase one was to include the roadway and one building. When that was completed, the other buildings were to be erected. Site preparation was accomplished by John T. Day. Most of the site preparation was completed before Respondent started construction. Thereafter, as work progressed, Respondent periodically certified to the bank what work had been done and that suppliers had been paid. Upon receipt of that certification, the bank would issue a check for the appropriate amount to EIP which would, thereafter, issue its own check to Respondent. There was an exception, however, in the case of payments to Ludwig Steel. Whereas that supplier would bill Respondent for small items delivered, it demanded payment by cashiers' check upon delivery for major structural steel fabrications. These checks, for steel for Buildings A and B, were for $18,511.84 and $17,716.84, were issued by Southland Bank, at the request of EIP. During the course of his performance of the contracts for the construction of Buildings A, B, & H, Respondent executed several of the above mentioned certification forms. For Building H: These included: a. August 30, 1988 $ 9,505.00 b. October 4, 1988 9,505.00 c. October 17, 1988 9,505.00 d. December 28, 1988 11,881.50 e. January 31, 1989 9,437.50 TOTAL $49,834.00 Prior to these certificates, the bank also released $90,000 in advances for start up costs and the loan in March, April and May, 1988. In addition to the certificates listed above, Respondent also signed certificates for Building A totalling $91,446.00 as follows: a. August 30, 1988 $ 19,800.00 b. October 4, 1988 19,800.00 c. October 17, 1988 19,800.00 d. December 28, 1988 24,750.00 e. January 31, 1989 7,296.00 TOTAL $ 91,446.00 Respondent also signed additional certificates for Buildings B as follows: a. December 28, 1988 $ 46,642.00 b. January 31, 1989 28,031.00 c. March 1, 1989 28,031.00 TOTAL $102,704.00 These certificates were also signed by the architect, Mr. Wilcockson. In fact, they were not correct in that not all the work had been done and not all suppliers had been paid. Respondent admits to falsely signing the certificates but claims he was urged to do so by representatives of EIP who indicated to him it was just a routine procedure. Consequently, even knowing the certificates were not accurate, he signed them because he wanted to get paid. It is found, however, that Respondent has been a licensed contractor for a number of years and knew the implications of his actions. His attempts at justification for his actions are neither credible nor impressive. Construction progressed satisfactorily and without major problems up to the time for the last draw. At that point, the bank declined to issue a check to EIP for the construction of Building C, also to be erected on the site, when it became aware that numerous liens had been filed by subcontractors and materialmen indicating Respondent's failure to make satisfactory payment for buildings A, B, and H. These liens included claims by: American Roll-Up Door Co. $ 3,630.00 B & B Painting Contractors 3,020.00 Blackton, Inc., 5,820.73 Brownie Septic Tank Contractors #1 1,025.00 Brownie Septic Tank Contractors #2 1,025.00 Brownie Septic Tank Contractors #3 1,635.00 Don Alan Dinora 930.00 Energy Savings Systems, Inc. 10,750.00 Florida Mining & Materials 2,388.31 Mid Florida Air Conditioning, Inc. 3,982.00 Neeley-Built Structures, Inc., 4,995.78 Residential Building Supply 7,857.11 Total $47,058.93 Mr. Crowley claims the above liens were satisfied by EIP, and it is so found. He claims EIP also paid some subcontractors who did not file liens because of a desire to help small contractors who otherwise would not have been paid. No figures were available to support that latter claim, however, and it is not considered to be probative of any issue. It is found, however, that Respondent paid Neeley-Built the amount of $4,995.78 and the claim of lien form included within Petitioner's exhibit of filed liens refers to property other than that in issue here. In addition, the $10,750.00 lien of Energy Savings Systems is not totally attributable to services or materials for the instant project. It is estimated that 60 percent of that amount relates to work done outside the three contracts in issue here. Further, only $1,700.00 of the lien of Residential Building Supply relates to material provided for the work done by Respondent under these contracts. The balance relates to work done outside the original contract limits. Over the course of the contracts, EIP paid Respondent, in addition to a deposit of $25,786,99 for Bldgs. A & H, the sums below, for a total of $259,006.72 for Bldgs. A, B, & H: a. Aug. 31, 1988 $19,800.00 for Bldg. A b. Aug. 31, 1988 9,505.00 for Bldg. H c. Oct. 05, 1988 10,793.16 for Bldg. H & A d. Oct. 17, 1988 29,305.99 for Bldg. A & H e. Dec. 14, 1988 19,000.00 f. Dec. 29, 1988 49,417.06 g. Feb. 06, 1989 7,296.00 for Bldg. A h. Feb. 06, 1989 28,310.00 for Bldg. B i. Feb. 06, 1989 9,473.50 for Bldg. H j. Feb. 10, 1989 2,350.00 for misc. k. Feb. 15, 1989 20,000.00 l. Mar. 03, 1989 28,031.00 for Bldg. B In addition to those payments, EIP also paid $16,000.00 to Benson Drywall on December 12, 1988 at the request of Respondent. The total paid by EIP, either to or on behalf of the Respondent, was: $ 25,786.00 deposit 233,280.72 to Great Southern 16,000.00 Benson Drywall 36,228.68 Ludwig Steel $311,295.40 TOTAL Mr. Crowley was not the main source of corporate funds. The President of the company is a Mr. Nelson who was the "money man." Contractor selection was by agreement between Nelson and Crowley, but Crowley was the supervisor of the contracts and did most of the negotiating with Respondent. The work stipulated in the contracts between EIP and Respondent was not the only work called for in their relationship. The contracts provided for the basic construction but Mr. Crowley requested Respondent to perform additional work in or around buildings A, B, and H, which included: Tenant improvements in buildings A and B valued at $23,000 excluding labor; Additional site work including electrical, telephone, grading and filling, berm modification, concrete sidewalks and parking buffers, and repair of damaged concrete (all but the repair of concrete was the result of the failure of the original site preparation contractor to properly complete his work); Negotiations and discussions with Volusia County regarding the sewer/septic system necessary for the project. In addition to the $23,000.00 for tenant improvements mentioned in the paragraph next above, Respondent also paid out of pocket to the following contractors and suppliers for work outside the scope of the original contracts: a. Ludwig Metal Buildings $ 3,000.00 b. Concrete 3,840.00 c. John Bates & family 6,497.73 d. Four Seasons 1,190.00 e. Will Cox 975.00 f. Riley 3,100.00 All Star Electric 4,705.32 Jerry's Concrete Service 1,350.00 TOTAL $24,658.05 Though the contracts referenced in this proceeding pertain to construction of Buildings A, B, & H, Respondent was also retained to erect a metal building to be designated C. Respondent received a total of $253,000.00 from EIP to construct those buildings for which he had the initial contracts and also to put up the metal building, C. The cost to complete Building C was $45,500.00 but EIP had remaining only slightly over $6,000.00 to pay for that work. Respondent did substantial work for EIP which was over and above the services called for under the contracts for Buildings A, B, & H as amended by the change orders for which he was not paid because Mr. Crowley advised him no additional monies were available. For example, he and his brother, Thomas, did additional site work valued by him at $24,260.00; and additional labor and services on the septic and sewer system problems valued by him at $5,600.00 and for tenant improvement, valued by him at $5,000.00. Here, however, it must be noted that the figures cited are not documented by any supporting material and contain significant amounts for his labor which he priced at $90.00 per hour. Mr. Miller, during his relationship with EIP, purchased a 10 percent interest in the firm. He originally filed his own lien on the property for $80,364.00 based on the contracts he had in hand and the site work which he valued at $18,000.00. He claims he subsequently withdrew his lien without being paid so that the limited funds available could be used to pay the subcontractors. No corroborating evidence on this point was introduced, however. Mr. Miller's contracting license was, subsequent to the incidents herein, placed in inactive status and currently remains so. He is not now engaged in contracting and claims he does not intend to do so in the future. His motivation in contesting the allegations against him is, he claims, solely to clear his good name and reputation.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED THAT the Respondent, David P. Miller, d/b/a Great Southern Construction and Development, Inc. pay an administrative fine of $3,750.00 and be reprimanded. RECOMMENDED this 9th day of November, 1993, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of November, 1993. APPENDIX TO RECOMMENDED ORDER, CASE NO. 92-7413 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties to this case. FOR THE PETITIONER: 1. & 2. Accepted and incorporated herein. Accepted and incorporated herein. Accepted. & 6. Accepted and incorporated herein. 7. - 14. Accepted and incorporated herein. 15. - 17. Accepted and incorporated herein. Accepted and incorporated herein. Accepted. & 21. Accepted and incorporated herein. 22. - 24. Accepted and incorporated herein. 25. & 26. Accepted. FOR THE RESPONDENT: Accepted and incorporated herein. & 3. Accepted and incorporated herein. Rejected as the total amount paid by EIP for the buildings constructed by Respondent. The figure is somewhat higher due to deposit and amounts paid to suppliers by EIP. Accepted and incorporated herein. * At this point, Respondent's proposed Findings of Fact become misnumbered. There are two numbers 5. The subsequent numbers are as reflected in Respondent's submittal. 5. - 9. Accepted and incorporated herein. 10. - 12. Accepted and incorporated herein. 13. - 15. Accepted and incorporated herein. 16. Accepted. 17 & 18. Accepted. Alleged but not proven. Accepted. Rejected as contra to the weight of the evidence. Accepted and incorporated herein. COPIES FURNISHED: Tracy Sumner, Esquire William S. Cummins, Esquire Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792 Kurt R. Borglum, Esquire 366 East Graves Avenue, Suite B Orange City, Florida 32763 Jack McRay General Counsel Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792 Daniel O'Brien Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202
Findings Of Fact At all times relevant hereto Jonas C. Merricks, Respondent, was licensed by the Construction Industry Licensing Board, Petitioner, as a residential building contractor. In May 1981 Respondent was approached by John Oden regarding a building permit to add a room to the residence of Ms. Betty J. Wilson. Respondent testified he went to see Ms. Wilson to discuss the permit before pulling the permit; however, Ms. Wilson testified she did not see Respondent until after the word started. Regardless of the correct version Respondent pulled the permit for the construction knowing that he was not going to do the work. On May 23, 1981 Ms. Wilson entered into a contract with John Oden to construct an additional room on her residence. This contract was modified on May 26, 1981 to enlarge the room two feet and it is this contract (Exhibit 3), upon which the work was done. The contract made no mention of Respondent or of J & J Building Company which is owned by Respondent. Under the terms of the contract Ms. Wilson was to pay Oden one-third when walls were up, one-third when the roof was on and the final one-third when the job was completed. During the course of the construction Respondent appeared on the site a few times and straightened out existing problems. Ms. Wilson made all of her payments to Oden in accordance with the contract. However, she made the final payment before the work was completed. Her attempts to get Oden to satisfactorily complete the job were unsuccessful and Ms. Wilson complained to the Bureau of Consumer Affairs who referred her complaint to the Construction Industry Licensing Board which investigated and filed the complaint here under consideration. No evidence was submitted that Respondent pulled permits for work done by J & J Building Company. Evidence was presented that J & J Building Company is not licensed by petitioner. Respondent testified that he pulled the permit as a favor to Ms. Wilson and not for Oden, and that he did not know Oden had contracted with Ms. Wilson to do this job. However, Respondent did know that Oden was going to build the addition for Ms. Wilson; and, in his affidavit, Exhibit 5, Respondent acknowledged he had "helped out" Oden several times, that he was paid by Oden for work Respondent did on the premises, that payment for this work was made out to J & J Building Company, and that he supervised the work when he was on the premises.
The Issue Whether Respondent committed the violations alleged in the administrative complaint; and, if so, what penalty should be imposed.
Findings Of Fact At all times material to the allegations of this complaint, the Respondent, Joseph Marcelin, was a certified residential contractor, license number CR C028352. Respondent’s place of business and residence are in Dade County, Florida. The Petitioner is the state agency charged with the responsibility of regulating and disciplining licensed contractors. On May 14, 1988, the Construction Industry Licensing Board entered a final order approving a settlement stipulation regarding Case no. 74860 against this Respondent. This final order directed Respondent to adhere to and abide by all of the terms and conditions of the stipulation. The stipulation required the Respondent to not violate the provisions in Chapters 455 and 489, Florida Statutes, in the future; required Respondent to honor a settlement in a civil matter; required Respondent to pay a fine in the amount of $500.00; suspended Respondent’s license for thirty days; and required Respondent to affirmatively demonstrate compliance with the stipulation in order to have his license reinstated. A second final order entered by the Board on May 14, 1988, approved a settlement stipulation regarding Case no. 77499. This final order also directed Respondent to comply with the stipulation applicable to that case. In Case no. 77499, the stipulation required Respondent to abide by a civil settlement; imposed a fine in the amount of $500.00; suspended Respondent’s license for thirty days; and placed the burden on Respondent to demonstrate he had met the terms of the stipulation. As to both cases referenced above, Respondent admitted the allegations of the administrative complaints which, in pertinent part, claimed Respondent had assisted an unlicensed person or entity to perform contracting services thereby aiding and abetting an unlicensed person to evade the provisions of Chapter 489, Florida Statutes. On April 2, 1993, Respondent executed a certification change of status form which was submitted to the Department. Such form was completed for the purpose of qualifying as an individual for licensure and sought to reinstate a delinquent license or change from inactive to active. In the course of completing the change of status form Respondent was required to answer a series of questions by checking either the “yes” or “no” column. In response to the question as to whether Respondent had “been charged with or convicted of acting as a contractor without a license, or if licensed as a contractor in this state or any other state, had a disciplinary action (including probation, fine or reprimand) against such license by a state, county or municipality?,” he answered “no.” Such answer was false. Further such answer was made under with the following affirmation: I affirm that these statements are true and correct and I recognize that providing false information may result in a FINE, SUSPENSION, OR REVOCATION of my contractor’s license. [Emphasis in original.] Thereafter, the Department notified the Respondent that his license would not be issued as he had failed to demonstrate satisfaction of a civil judgment and had not submitted an explanation of the disciplinary action from 1988. Respondent eventually resolved issues of licensure with the Department and, on September 15, 1993, was authorized to practice contracting. Prior to his license being reinstated, Respondent performed the following: on April 7, 1993, Respondent obtained a building permit for construction work at the home of Eduardo Bovea. This permit, no. 93181501, indicated Respondent as the contractor of record for the project. On the permit application Respondent represented himself as the licensed building contractor for the Bovea project to the Metropolitan Dade County building and zoning department. Respondent did not have a contract with Bovea for the construction work to be performed on the Bovea home. In fact, the contract was between Bovea and Lou Greene Construction. The Boveas paid monies to Rodney Salnave, who claimed to be a representative for Lou Greene Construction. Rodney Salnave was not Respondent’s employee, and was not licensed as a contractor. The Respondent did not talk to the Boveas regarding the contract, the scope of the work to be done, or the contract price for the work. All discussions regarding the work at their home (and payments for same) were between Rodney Salnave and the Boveas. The permit for the Bovea project represented the amount of the work to be $2,000.00. In fact, the contract price for the work was $4,500.00. Respondent misrepresented the value of the work for the Bovea project. As of September 26, 1993, Respondent admitted he was involved with seventeen contracting jobs. Just eleven days after having his license reinstated, and while being employed in a full-time (8:00 a.m. to 5:00 p.m.) job with Dade County, Respondent had contracting responsibility for seventeen jobs. In reality, Respondent had made a deal with an unlicensed person, Denis Joseph, to pull permits for him. The jobs were for persons who, in some instances, Respondent had never met. For example, Mr. Joseph pulled a permit for work to be performed on a home owned by Ed Davis. The contract for the work was between Mr. Davis and a Mr. Sutton, an unlicensed contractor, but with the approval of Respondent, Mr. Joseph obtained a permit for the Davis job. A second job was for Bertha Joseph. In this instance, Mr. Joseph completed the permit application which Respondent signed thereby allowing Mr. Joseph to obtain the permit for the project. By signing the permit, Respondent represented himself to be the contractor for the job. In truth, the homeowner had contracted with Denis Joseph for the work to be done, but the project was completed by Emanuel Gideon, an unlicensed contractor. Respondent admitted receiving payments from Denis Joseph. Respondent admitted he was not actively involved with the Bertha Joseph project. In September, 1993, Eric Wardle, an investigator with the Dade County building and zoning department, interviewed Respondent regarding claims that he was obtaining permits for unlicensed contractors. According to Mr. Wardle, Respondent admitted he pulled permits for unlicensed contractors after Hurricane Andrew because they were trying to make a living. At hearing Respondent disputed the accuracy of Mr. Wardle’s investigation but admitted he would have told him “anything just for him to get away from me.” Respondent’s explanation at hearing was not persuasive.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Business and Professional Regulation, Construction Industry Licensing Board, enter a final order revoking Respondent’s contractor license and imposing an administrative fine in the amount of $8,500.00. DONE AND ENTERED this 16th day of May, 1997, in Tallahassee, Florida. J. D. PARRISH Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 COPIES FURNISHED: Bruce M. Pasternack, Esquire Raymond L. Robinson, P.A. 1501 Venera Avenue, Suite 300 Coral Gables, Florida 33146 Joseph Marcelin 16561 Southwest 144th Court Miami, Florida 33177 Filed with the Clerk of the Division of Administrative Hearings this 16th day of May, 1997. Rodney Hurst, Executive Director Department of Business and Professional Regulation/CILB 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Lynda L. Goodgame, General Counsel Department of Business and Professional Regulation 1940 North Monroe Street, Northwood Centre Tallahassee, Florida 32399-0792