The Issue The issue presented is whether the Department should award the contract for State Project numbered DOH 95209100 to Petitioner.
Findings Of Fact State Project numbered DOH 95209100 commenced with an invitation to bid on a construction project which involved the restoration and adaptive use of the Gato Cigar Factory in Key West, Florida. The construction would rehabilitate that existing historic structure and construct internal office and clinic spaces for both Monroe County and the Department of Health. Since both agencies would use the building, the project was divided between them. Monroe County and the Department issued separate invitations to bid for their portions of the structure, and each will enter into its own contract with the winning bidder or bidders. It was not required that a bidder submit a bid for both the Monroe County and the Department portions of the work. Any bidder could bid on one or the other or both. Although the invitations to bid and the contracts to result therefrom were not interrelated, some of the construction work was interrelated as some of the systems being installed under one contract would directly affect the other contract. For example, both the air conditioning system and the roofing system, although being performed under one entity's contract, would be applicable to both projects. The Department's invitation to bid required bidders to submit a base price, plus specific prices on particular items. Alternate numbered 1 added to the base price the cost of a second air conditioning chiller. The base price plus alternate numbered 1, taken together, included all work to be performed under the Department's scope of work. Alternates numbered 2 through 5 were deductions from the work included in the base price. Alternates numbered 2 through 5 were included in the Department's invitation to bid to cover the possibility that all bids might come in over budget. In that event the Department could select Alternates numbered 2 through 5, sequentially, until sufficient items had been deducted from the Department's scope of work to result in bids under the amount budgeted by the Department for the project. Section 01030 of the bid specifications is entitled "Alternates." Section 1.2E of Part 1 provides, in part, as follows: Include as part of each Alternate, miscellaneous devices, accessory objects and similar items incidental to or required for a complete installation whether or not mentioned as part of the Alternate. Each Alternate Bid must interface with the work being constructed under a separate contract with Monroe County. Each Alternate Bid item is also applicable to the Monroe County work. An alternate which is deducted from one project will be added to the other. If bidding both projects, the Deductive Alternate price for one project must match the Add Alternate price for the other project. The prospective bidders were also given this information in the pre-bid meetings. The Department received a number of bids for less than the amount budgeted for its portion of the work. Accordingly, the Department was able to select Alternate numbered l, which taken together with the base bid, covered the entire scope of work allocated to the Department. The lowest bids through Petitioner's bid were as follows: Bidder Total Bid D. L. Porter Construction, Inc. $1,418,744. McTeague Construction Co., Inc. $1,454,500. Lodge Construction, Inc. $1,501,500. Rovel Construction, Inc. $1,559,000. Neither McTeague Construction Co., Inc., nor Lodge Construction, Inc., participated in this proceeding to challenge the Department's intended bid award. For the lowest bidder, Intervenor Porter, discrepancies occurred in its first, third, and fifth alternative prices of $3,500, $375, and $l,497, respectively. For the second lowest bidder, McTeague, a discrepancy of $9,000 occurred in its first alternate price. For the third lowest bidder, Lodge, a discrepancy of $3,165 occurred in its fifth alternate price. For the fourth lowest bidder, Petitioner Rovel, there were no discrepancies in any of its alternate prices. Porter's bid on Alternate numbered 1 for the Department was $38,500. Porter's bid on Alternate numbered 1 for Monroe County was $35,000. Porter's estimating staff overlooked the instruction that the two numbers should match. The reason for the difference between the two Alternate numbered 1 amounts is that the bidders were instructed to prepare the two bids as two separate contracts. Alternate numbered 1 required moving one of two chillers from the Monroe County project to the Department's project. Porter could not assume that it could use the crane from the contractor on Monroe County's portion of the project to install this chiller in the Department's portion of the project. Therefore, the cost of a crane had to be added to the Department's project, but the cost of the crane could not be deducted on the Monroe County bid. Porter was the fourth highest bidder on the Monroe County project. Monroe County has not yet awarded its contract. If the Monroe County project is awarded based upon the bids submitted, Porter will not be awarded the Monroe County project. The Department's bid tabulation and notice of intended award were prepared without any reference to the bid opening for the Monroe County project and before the contents of the Monroe County bids were known by the Department. The deviation in price between Porter's Alternate numbered 1 bids did not give Porter an advantage over the other bidders, several of whom made the same error. It was a minor deviation, not a material one. The price submitted on the Department's bid reflected the actual cost of performing that portion of the work. Petitioner's bid listed Florida Keys Electric, Inc., as its electrical subcontractor, its fire alarm subcontractor, and its lightening protection subcontractor. That company is not certified by the State of Florida, but it is registered. The bid specifications provide in section B-14, in part, as follows: Any bidder who lists a subcontractor not certified and/or registered by the State to perform the work of his trade if, such certification or registration is required for the trade by Florida Laws, will be rejected as non-responsive. No change shall be made in the list of subcontractors, before or after the award of a contract, unless agreed to in writing by the Owner. Section 16010, Part 1, section 1.9, subsection A., of the technical specifications which form a part of the bid specifications involves supervision of the construction and provides, in part, that "At least one member of the Electrical Contracting Firm shall hold a State Master Certificate of Competency." Florida Keys Electric, Inc., would use Delor J. Ellis as its qualifying agent. Although Ellis is certified by the State, at the time of the bid submittal and through the date of the final hearing in this cause, Ellis' license was in an inactive status, and no application to activate his license was pending with the State of Florida. Fire alarm work and lightening protection work require a specialty license in the State of Florida. Florida Keys Electric, Inc., is not licensed to perform either type of work. When Florida Keys Electric, Inc., contracts to perform such work, it does so through its own subcontractor. Although the requirement for certification and/or registration contained in the bid specifications is not consistent with the requirement for State certification contained in the technical specifications portion of the bid specifications, Petitioner did not comply with either provision. Accordingly, Petitioner's bid is not responsive to the bid specifications. Porter, which submitted the lowest bid, is responsive to the bid specifications and is, therefore, the lowest responsive bidder.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered finding Petitioner's bid to be non-responsive, dismissing Petitioner's bid protest, and awarding to D. L. Porter Construction, Inc., the contract for the restoration of the Gato Cigar Factory. DONE AND ENTERED this 27th day of April, 1999, in Tallahassee, Leon County, Florida. LINDA M. RIGOT Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of April, 1999. COPIES FURNISHED: Angela T. Hall, Agency Clerk Department of Health 2020 Capital Circle, Southeast BIN A02 Tallahassee, Florida 32399-1703 Pete Peterson, General Counsel Department of Health 2020 Capital Circle, Southeast BIN A02 Tallahassee, Florida 32399-1703 Robert A. Hingston, Esquire Welbaum, Guernsey, Hingston, Greenleaf & Gregory, L.L.P. 901 Ponce de Leon Boulevard, Penthouse Suite Coral Gables, Florida 33134 Michael E. Cover, Esquire Morton R. Laitner, Esquire Department of Health Miami-Dade County Health Department 1350 Northwest 14th Street Miami, Florida 33125 William G. Christopher, Esquire Brown Clark, A Professional Association 1819 Main Street, Suite 1100 Sarasota, Florida 34236
Findings Of Fact Introduction In February, 1988 respondent, Department of Revenue (DOR), issued a Request for Proposal and Bid Proposal Submittal Form (RFP) inviting qualified and interested vendors to submit proposals for providing approximately 19,300 square fee of office space in the central area of Broward County for DOR's district office. The contract was identified as Lease Bid No. 730-0083. The space was to be made available on July 1, 1988 or 30 days after the bid was awarded, whichever was later. According to the RFP, the term of the lease was five years with an option to renew for a second five year period. Sealed bids were to be filed in Tallahassee no later than 2:00 p.m. on May 2, 1988. The RFP scheduled a "preproposal conference" on April 4, 1988 at DOR's district office. It stated further, that any questions concerning the specifications should be directed to Thomas D. Cooper, DOR's assistant director of administration. Under DOR's bidding process, a four person evaluation committee made up of DOR district employees was assigned the responsibility of reviewing all bids and inspecting the proposed office sites. Using twelve prescribed evaluation criteria, one of which was the rental rate, the committee assigned numerical scores to the top seven bids. Its report was then forwarded to Tallahassee as a nonbinding recommendation. There, the assistant director of administration was charged with the responsibility of reviewing the committee's recommendations and to make a further recommendation to the executive director. As always, the final decision rested with DOR's then acting executive director, Sam D. Alexander. It was DOR's intention to ultimately award the contract to the vendor submitting the lowest and best proposal. Fifteen proposals were timely filed by various vendors, including petitioners, Intercontinental Properties, Inc. (Intercontinental) and Nu-West Florida, Inc. (Nu-West) , and intervenor, 241 East 76th Street Company d/b/a Fountains of Plantation (Plantation). After reviewing the proposals and office sites, the DOR evaluation committee assigned the following numerical scores to the top three bidders: Intercontinental-87 percent; Nu-West - 87 percent, and Plantation - 85 percent. However, it recommended that the bid not be awarded to Intercontinental because of its unfavorable site location and because no local government permits had been obtained to construct a drive-through facility. The committee characterized Nu-West's proposal as a "class operation" and noted that 1the committee is unanimous in it's (sic) recommendation that Nu-West Florida Inc.'s bid offers more for the Department when all factors are considered." Finally, the committee criticized Plantation's site location and anticipated delays in remodeling its building. This evaluation was forwarded to DOR's acting executive director on May 17, 1988. On Wednesday, June 1, 1988 DOR's assistant purchasing director, Barbie Foster, gave telephonic notice to all bidders that the contract would be awarded to Intercontinental and that other bidders had 72 hours in which to file a protest. At 11:30 a.m. that same day, DOR posted a "bid tabulation sheet" reflecting the unit cost (per square foot) of office space submitted by twelve vendors and recommending that the contract be awarded to Intercontinental. The tabulation sheet indicated also that unless the parties "file(d) a protest within the time prescribed in section 120.53(5), Florida Statutes," they waived their right to a hearing under chapter 120. Nu-West filed its protest on June 3, 1988. By June 6, two other protests had been filed, including that of Plantation. On June 9, 1988 DOR issued its first written advice on the subject to the parties. The advice, which was in the form of a letter from Foster to the president of Intercontinental, read as follows: This letter is to notify you that as of 11:30 A.M., June 6, 1988, the Department has received three (3) letters of Intent to protest the recommended contract submitted for office space in Ft. Lauderdale, Bid No.: 87/88-238. Enclosed please find copies of the (3) letters submitted. As you are aware, the awarding process on this lease is now at a stand still until the protests are resolved. The Department's legal counsel will be in touch with you in the very near future. Should you wish to contact Mr. Bill Townsend, Director of Technical Assistance, please feel free to do so, he can be reached at (904) 488-0712. A settlement conference was held in Fort Lauderdale on June 17 in an effort to informally resolve the matter. At that time, or shortly thereafter, DOR learned that the proposals of Intercontinental and Nu-West allegedly did not conform to specifications. On June 22, 1988 DOR issued its second notice of intent to award the contract and advised all vendors that the contract was being awarded to Plantation, the third ranked vendor, and that the proposals of Intercontinental and Nu-West were rejected as being nonresponsive. Such notice was in the form of a letter to each bidder advising the name of the successful bidder, giving a short summation of the reason why a particular vendor had been rejected and offering a clear point of entry to a formal hearing. In the case of Intercontinental, DOR advised that Intercontinental's bid was "non- responsive" since it failed "to comply with paragraph D4A, p. 14," it was "not the owner of record of the subject project," and it had not furnished its "authority to offer the facility." As to Nu-West, DOR found its bid "nonresponsive in the requirement of two drive-in stations as set forth in paragraph B14D, p. 14 of the Request for Proposal" because Nu-West had "indicated (it) would provide only one window and a drop box." These letters prompted the filing of formal protests by petitioners. Bid Requirements Pertinent to this controversy are two items in the RFP which formed the basis for DOR's rejection of petitioners' bids. First, Item B14 sets forth various miscellaneous requirements imposed on the bidder. Paragraph D. of that item provided as follows: The Department requires a drive-through teller facility similar to banking and savings and loan institutions. This may be located within the office or may be connected to the office by a pneumatic tube system (minimum of two stations required) (Emphasis added) This item was required because of a recently instituted DOR policy that all district offices have drive-in facilities for taxpayers. As old office buildings are vacated and new ones occupied, DOR requires that the new landlord provide teller facilities. At present, only three district offices in the state (Miami, Tampa and Tallahassee) have teller facilities but DOR plans eventually to install such facilities at all district offices. In this case, DOR envisioned a facility that would be similar to a small banking facility with two work stations that could handle two taxpayers simultaneously. It was necessary that teller facilities be provided since taxpayers often submit money and documentation and pose questions that must be answered by the tellers. As an alternative to two teller stations, DOR considered accepting one teller station and a drop box connected by a pneumatic tube to the main building. However, the use of a drop box without a pneumatic tube was unacceptable since DOR would "lose control" over deposits and lack the necessary security for handling taxpayer money. This item was considered to be material by the agency. Secondly, Item D.4.A. provided that: 4.A. Each proposal shall be signed by the owner(s) , corporate officers, or legal representative(s). The corporate, trade, or partnership title must be either stamped or typewritten beside the actual signature(s). If the Bid Submittal is signed by an Agent, written evidence from the owner of record of his/her authority must accompany the proposal. If the Bid Submittal is offered by anyone other than the owner or owner's agent, proof of the bidder's authority to offer the facility; i.e., copy of bidder's Option to Purchase, must accompany the proposal. This option must be valid through the validity date established for bids. If a corporation foreign to the State of Florida is the owner of record, written evidence of authority to conduct business in Florida must accompany the Bid Submittal. (Emphasis added) The purpose of this item was to give DOR proof that the bidder was authorized to act for the property owner, or, if the bidder was not an agent, to give DOR written assurance that the bidder had an option to purchase, leasehold interest or some other form of interest in the subject property. This was because DOR could not be expected to sign a lease if it was unsure whether it would have the legal right to occupy the property. DOR considered this item to be a material item within the specifications. The first page of the RFP contained the following admonition to bidders: It is the bidder's responsibility to be familiar with all aspects of the bid package outlined below and attached hereto. Finally, page 14 of the RFP contained the following certification to be executed by the bidder when the bid was filed: I hereby certify as owner, officer, or authorized agent, that I have read the request for proposal package and all its attachments and acknowledge my understanding of and agreement to abide by all requirements and conditions contained therein. Intercontinental's Bid Intercontinental was not the owner of the property that was offered to DOR in Intercontinental's bid submission. This was confirmed at hearing by Intercontinental's leasing agent, Nestor Mendoza. According to Mendoza, the property was owned by a partnership using the name "441 South Partnership" but was leased to Intercontinental prior to the bid being submitted. Intercontinental filed its bid in Tallahassee on May 2, 1988. The certification on page 14 of Intercontinental's submission was signed in the following manner: Intercontinental Properties, Inc. Bidder's Name (typewritten) 59-1508950 Bidder's F.E.I.D. or S.S. Number (Illegible) Authorized Signature (manual)(Seal) Caroline Weiss Authorized Signature (typewritten) President Title (typewritten) Notwithstanding the requirement in item D.4.A., there was no documentation attached to Intercontinental's proposal reflecting that Intercontinental had authorization from the true owner to submit a bid or that it had a legal interest in the property. Therefore, DOR assumed that Intercontinental was the legal owner of the property. According to Mendoza, he carried documentation to Tallahassee on May 2 confirming Intercontinental's interest in the property but did not attach it to the proposal because he was under the impression that such documentation was necessary only if Intercontinental was "acting as an agent." Even though this "impression" was contrary to the requirements of the specifications, Mendoza maintained that he understood all RFP requirements. Mendoza was elated after receiving a telephone call on June 1, 1988 from Foster, who advised that Intercontinental had received the award. He was told also that, unless protests were filed within 72 hours, the firm would win the contract. In giving its preliminary intent to award the bid to Intercontinental, DOR overrode its committee's contrary recommendation. After a closer examination of Intercontinental's submission was made, DOR learned that, while Caroline Weiss, Intercontinental's president, had executed the bid submission, Intercontinental was not the legal owner of the property that was described in the proposal. DOR noted also that there was no documentation attached to the proposal, as required by item D.4.A. At a settlement conference held on June 17, 1988 Intercontinental maintained it had a leasehold interest in the property but declined, for whatever reason, to give DOR representatives any proof of this assertion. Because of this, DOR concluded properly that Intercontinental's bid was nonresponsive. During final hearing, Mendoza pointed out that, prior to the bid being submitted, DOR representatives had never questioned him concerning who was the true owner of the property and that he never made representations that Intercontinental owned the property. Intercontinental twice attempted to offer into evidence at hearing what purported to be a copy of a lease agreement in which Intercontinental had leased the property in question from another party. However, the document was never properly authenticated. Even if it had been authenticated, it was too late for Intercontinental to modify its bid submission since the documentation was required with Intercontinental's original submission filed on May 2, 1988. Nu-West's Bid Nu-West first learned of DOR's interest in new office space in February, 1988. After obtaining an RFP, Philip Saia, Nu-West's director of marketing and leasing, telephoned DOR's assistant director of administration to get clarification on several items in the specifications. Saia was told by Cooper to attend a prebid conference on April 4, 1988 in Fort Lauderdale. Also, he was told to telephone John Driggers, the author of the RFP and a district employee. Saia telephoned Driggers and was advised that all questions would be answered at the conference on April 4. Early on the morning of April 4, Saia met with Driggers and Bernard Fox, DOR district administrator, to discuss the item relating to the drive-through tellers and to show them Nu-West's facility. Saia's concern was that, due to space limitations and the cost of a pneumatic tube system, Nu-West would be priced "out of the ballpark" and would be unable to submit a bid. The three discussed other alternatives but reached no agreement. Driggers denied telling Saia that his proposal would comply with specifications but conceded he "probably led them to believe" that Saia's proposal would be "acceptable." Fox's principal concern was whether sufficient security could be provided for an unattached drop box. He voiced this concern to Saia. At the prebid conference later that day, another vendor queried the two DOR representatives (Driggers and Fox) about the drive-through teller requirement. Saia asked no questions. However, Saia contended that, in response to the other vendor's question, DOR representatives were "vague" and left the matter "very open." The actual dialogue between the vendor and Driggers is reflected in the transcript of the meeting received in evidence as DOR exhibit 1. According to the transcript the following exchange on the subject took place: (by unidentified vendor) On the drive through facility you asked about the pneumatic . . . you have a requirement for pneumatic tubes. (by John Driggers) Okay. On the drive through facility what we are trying to reflect there is we would prefer a facility for security purposes that would be contiguous with the office so that it would not be located away from the office. We would entertain a remote type facility that was connected with the office by pneumatic tubes or something that would be feasible. We don't necessarily kick out the possibility that we might use a facility that would not be contiguous to the office itself. However, we would look at that very carefully to make sure that it did meet requirements and that we could feel that it would be a secure place to use for the employees and for the . . . We do accept cash in these offices. What I'm trying to do is to give you some options there because there is no telling what kind of facility that you could come up with that would be acceptable. (Emphasis added) Driggers also advised vendors that if they had any further questions, they should be addressed to Fox. Saia concluded that, given the space limitations in Nu-West's building and the need for a local government site approval plan, the most cost-effective way to meet the requirement was to have one drive-through teller "adjacent to the building" and a drop-box in a separate location not contiguous to or connected with the main building. The use of a drop box was based on Saia's impression that DOR wanted the capability of receiving customer deposits after regular business hours and that a "facility" was not necessarily a teller window. He reasoned that this was comparable to the type of facilities used by banks and would be "a good solution to the problem." To reinforce his idea, Saia met with Fox a second time on April 19, 1988 and showed Fox his proposed plans. According to Saia, Fox told him the plans were "very acceptable." However, Fox's recollection of the conversation was different, and he remembered making no such commitment that the plans were acceptable. Instead, Fox told Saia that a drop-box with one window was better than only one window but that his overall concern was with security. In any event, Saia relied on this meeting to formalize the drop box plan in his bid submission. He went so far as to submit the plans to the City of Lauderdale Lakes for site review approval. Nu-West's submission was timely received by DOR. On page 8 of 14 of the RFP, Nu-West responded to the drive-through teller requirement with the following statement: Drive through teller window and one outside drop box will be provided in the manner shown on the enclosed site plan, subject to final approval by the City of Lauderdale Lakes, which has been applied for. (Preliminary approval has been obtained). The attached site plan is depicted on Joint Exhibit 3A and reflects a single drive-through teller facility. The drop box did not have a pneumatic tube system connecting the box to the main facility. This constituted a material deviation from the specifications. It is noted that of the fifteen vendors filing proposals, only Nu-West failed to provide for two drive-through tellers. A week or so after Nu-West's bid was submitted, the DOR evaluation committee visited Nu-West's office site. The team stayed on the premises for two hours. Saia recalled that even though the team discussed the proposed single drive-in teller facility idea and was shown its proposed location, he heard no objections. In its written evaluation report of Nu- West's bid dated May 17, the committee made no mention of any deficiency in the drive-through teller proposal and described Nu- West's proposed site as "a class operation." Nu-West was also given a grade of 87 and unanimously recommended for award of the contract. On June 2 Saia was advised by telephone that Intercontinental had been awarded the bid. Thereafter, Nu-West timely filed its protest. At the settlement conference held on June 17, Saia was not told his bid had been rejected because it was nonresponsive. He did not learn this until he received a telephone call a few days later from DOR's acting executive director. This was followed by DOR's letter of June 22 advising that Plantation had been awarded the bid and that Nu-West's bid had been rejected on the ground the proposal did not provide for two drive-through tellers. When this final decision was made by DOR, neither Cooper or Alexander were aware of any representations that might have been made to Saia by Fox or Driggers. Nu-West is willing to modify its proposal to provide a second drive- through teller. According to Saia, it can be accomplished with a $72,000 allowance Nu-West set aside to cover any deficiencies incurred during renovation. However, these modifications should have been filed with the original bid package in order to conform to specifications. Plantation's Bid Plantation was ranked number three numerically by the evaluation committee but, after the disqualification of Intercontinental and Nu-West, it had the highest numerical score and was considered the lowest and most responsive bid. Although Nu-West's proposed location in Plantation was questioned by another vendor as being in an inaccessible area of the county, DOR representatives concluded the office site was satisfactory. All material specifications were met by this bidder. 2/ Using a present value of lease payments, Plantation's bid was $1.23 per square feet cheaper than Nu-West's bid proposal but was slightly higher than Intercontinental's proposal.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a Final Order be entered awarding Lease Bid No. 730-0083 to 241 East 76th Street Company d/b/a Fountains of Plantation. DONE AND ORDERED this 5th day of October, 1988, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings 5th day of October, 1988.
The Issue The ultimate issue for determination at formal hearing was whether the intended decision by the Palm Beach County School Board to reject all bids on the Gladeview Elementary School project, Project No. 125191702/205840, departs from the essential requirements of law.
Findings Of Fact Palm Beach County School Board (Respondent) issued a request for proposals (RFP), soliciting sealed bids for the reroofing, renovating and replacing the HVAC of Gladeview Elementary School, Project No. 125191702/205840 (Gladeview Elementary Project). The RFP and bid documents for the Gladeview Elementary Project were contained in the "Project Manual." The addendum to the RFP required all bids to be submitted by April 20, 1993 at 2:00 p.m., at which time all bids were to be publicly opened. Pertinent to the case at hand, the RFP further required a bid bond or cashier's check for not less than five percent (5 percent) of the bid and notified bidders that Respondent had the right to reject all bids and waive any informalities. Section 00100 of the "Instruction to Bidders" in the Project Manual is material to the case at hand and provides in pertinent part: BIDDING PROCEDURES: * * * Preparation and Submission of Bid Proposal Form: [P]roposals containing any conditions, omissions, unexplained erasures, alternates, items not called for or irregularities of any kind may be rejected by the Owner. . . (e) Proposal Submittal shall contain the following documents: Section 000443 - Public Entity Crimes Statement Section 00310 - Proposal Form Section 00410 - Bid Bond or otherwise acceptable Bid Guarantee (see Paragraph 3.08). Manufacturer's Letter of Intent to Warranty (See Section 7610) and will be enclosed in a sealed envelope. . . * * * 3.08 Bid Guarantee: Bids shall be accompanied by a bid guarantee of not less than five percent (5 percent) of the amount of the Base Bid, which shall be a Cashier's Check or a Bid Bond (Bid Bond, see Section 00410) made payable to the Owner. * * * 3.10 Subcontractors: At the time of the Bid Opening each Bidder submitting a Bid shall submit a written list of the major Subcontractors; namely, structural steel, membrane roofing, preformed metal roofing & siding, plumbing, HVAC, electrical and general contractor, on Form 00420 (List of Major Subcontractors). The list shall be placed in a "sealed envelope". . . Within five (5) Owner Business days after the Bid Opening, the apparent low Bidder(s) shall submit Form 00430) (List of Subcontractors), completed in full to the Owner ... Failure to submit these lists within the time period specified herein shall result in a non- responsive Bid. * * * REJECTION OF BIDS: 6.01 The Bidder acknowledges the right of the Owner to reject any or all Bids and to waive any informality or irregularity in any Bid received. In addition, the Bidder recognizes the right of the Owner to reject a Bid if the Bidder failed to furnish any required Bid security, or to submit the data required by the Bidding Documents, or if the Bid is any way incomplete or irregular; to reject the Bid of a Bidder who is not in a position to perform the Contract; and to re-advertise for other or further Bid Proposals. SUBMISSION OF POST-BID INFORMATION: * * * 7.02 The selected Bidder shall within eight (8) Owner business days after notification of Board Award submit the following: . . . 6. Photocopies of prime Contractor's certification and/or registration and either state registrations or Palm Beach County Certificate of Competency of all Subcontractors. . . * * * AWARD OF CONTRACT: The Contract, if awarded by the Owner, will be awarded to the lowest bona fide responsible Bidder; provided the Bid is reasonable and it is in the interest of the Owner to accept the Bid. The method of determining the lowest bona fide Bid from Bidders shall be the Base Bid price plus or minus Alternate Prices listed on the Bid Proposal Form which are accepted by the Owner. Alternates will be considered for acceptance by the Owner as set forth in the Alternate section of the Specifications, Division One-General Requirements, Section 01030-Alternates. The bid opening was conducted on April 20, 1993, at which time the bids were tabulated and the Bid Tabulation Form (BTF) was posted. Respondent received bids from Bonner Roofing whose base bid was $869,000, S&S Roofing, Inc. (Petitioner S&S Roofing) whose bid was $693,000, Therma Seal Roofs, Inc. (Petitioner Therma Seal) whose bid was $691,500, Titan Roofing, Inc. (Petitioner Titan Roofing) whose base bid was $689,500, and Trans Coastal Roofing, Inc. (Petitioner Trans Coastal) whose base bid was $884,248. The BTF showed that the rank of the bids, beginning with the apparent lowest bidder to the apparent highest, were (1) Petitioner Titan Roofing, (2) Petitioner Therma Seal, (3) Petitioner S&S Roofing, and (4) Petitioner Trans Coastal. The BTF showed further that Bonner Roofing failed to submit with its bid the Manufacturers Letter of Intent which was a required document. Bonner Roofing's bid was rejected. Within minutes after the bid opening, Respondent's staff discovered that Petitioner Titan Roofing had failed to list its major subcontractors on Form 00420, List of Major Subcontractors, even though it had submitted the form. Respondent's staff contacted Petitioner Titan Roofing by telephone and requested the list. Petitioner Titan Roofing's failure to submit a completed Form 00420 was inadvertent and not intentional. At the time of the bid opening, Respondent's staff had not considered Petitioner Titan Roofing's failure to submit a completed Form 00420 to be a major irregularity, but a minor one. Consequently, Respondent's staff considered the failure to be a waivable irregularity. Unable to discern if it had the original figures submitted by its major subcontractors, Petitioner Titan Roofing telephoned them to verify the figures it had. Within two hours, Petitioner Titan Roofing had faxed to Respondent's staff a completed Form 00420. Respondent's recommendation or intended action was to award the bid to Petitioner Titan Roofing as the apparent lowest bidder. Petitioner Therma Seal, the apparent second lowest bidder, filed a timely protest of Respondent's intended action. Respondent held an informal hearing on the protest, and the recommendation was to reject all bids. In prior bids, a bidder's failure to submit Form 00420 at bid opening has been considered a major irregularity by Respondent. The purpose of Form 00420 is to prevent or guard against bid shopping. Respondent's action has been to routinely reject bids with such a deficiency. Petitioner Therma Seal failed to submit with its bid the required bid bond of 5 percent of its base bid. Failure to submit a required bid bond is considered by Respondent to be a major irregularity. Furthermore, Petitioner Therma Seal was not a licensed general contractor. It listed itself as the general contractor on Form 00420. All bids failed to comply with the roofing warranties and specifications, which Respondent considers to be a major irregularity. Respondent's budget, based upon its architect's construction estimate, for the Gladeview Elementary Project was $652,130. All bids were over budget. Prior to the formal hearing, Respondent Trans Coastal notified the parties that it was not proceeding with its protest.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Palm Beach County School Board enter its final order rejecting all bids on the Gladview Elementary School project, Project No. 125191702/205840, and re-advertise. DONE AND ENTERED this 7th day of September 1993 in Tallahassee, Leon County, Florida. ERROLL H. POWELL Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 7th day of September, 1993.
The Issue Whether Petitioner/Intervenor Hedin's challenge to Respondent's preliminary determination to award Lease No. 590:2241 to 1436 Building, Inc. should be sustained? Whether Petitioner/Intervenor Schlitt's challenge to said preliminary determination should be sustained?
Findings Of Fact Based upon the record evidence, the following Findings of Fact are made: 1 In March, 1991, after requesting and receiving approval from the Department of General Services, the Respondent issued an Invitation to Bid for Lease No. 590:2241 (hereinafter referred to as the "ITB"). The cover page of the ITB contained the Bid Advertisement, which read as follows: The State of Florida, Department of Health and Rehabilitative services is seeking approximately 17,064 net rentable square feet of office space to lease in Indian River County within the following boundaries: North, to Lindsey Road, South to Olso Road, East to A1A and West to Kings Highway. Space must be in an existing building. Occupancy no later than October 1, 1991, or within 120 days after notification of bid award, whichever occurs last. Desire a five (5) year lease with five (5) one year renewal options. Sealed bids will be received until 3:30 p.m.,, April 24, 199[1] at Riviera Beach, FL. Information and specifications will be provided to all interested parties at a mandatory pre-proposal conference to be held at Department of Health and Rehabilitative Services, 1050 15th Street West, Riviera Beach, FL. 33404, April 5, 1991 at 1:00 p.m. The Department of HRS reserves the right to reject any and all bids received and if necessary to reinstate procedures for soliciting competitive bids. The office space sought by Respondent was to house a client service center that is currently operating out of a 12,000 square foot facility owned by Petitioner/Intervenor Hedin. Respondent needs approximately 5,000 more square feet of office space for this center. Page B-1 of the ITB contained the definitions of various terms used in the ITB. Among the terms defined was "lowest and best bid." "Lowest and best bid" was defined as follows: That bid selected by the District Administrator, designee, or Deputy Secretary upon the recommendation of the bid evaluation committee following an objective and detailed process to evaluate and compare bids. "Lowest" refers to the total evaluation score. Weights for evaluation criteria are prescribed on pages B-7 through 9. Actually, this information was found on pages B-5 though 7 of the ITB, which read in pertinent part as follows: EVALUATION OF BIDS Bids received are first evaluated to determine technical responsiveness, such as use of Bid Submittal Form, inclusion of required information, data, attachments, and signatures. Non- responsive bids will be withdrawn from further consideration. Non-responsive bidders will be informed promptly by certified mail. Responsive bids are presented to a bid evaluation committee for comparison and formulation of a recommendation for award. This is accomplished by a visit to each proposed property and application of the evaluation criteria. The committee's recommendation will be presented to the Department official having award authority for final evaluation and determination of a successful bidder. EVALUATION CRITERIA AWARD FACTORS The successful bidder will be that determined to be the lowest and best. All bids will be evaluated based upon the award factors enumerated below: Associated Fiscal Costs Rental Rental rates for basic term of lease. Evaluated using present value methodology by application of she present value discount rate of 8.74%. 2/ (Weighting: 35 minimum) Rental rates for optional renewal terms of lease. Rates proposed are within projected budgeting restraints of the Department. (Weighting: 5 minimum) Total for rental shall be not less than 40. Moving Costs: a) Cost of relocating communications network computer drop lines as determined by a site survey conducted at each proposed facility by the Department's management information office, or: (Weighting: 5 maximum) b) Cost of relocation of major statewide operational data system as determined by a site survey conducted at each proposed facility by qualified data center management. (Weighting: 6 maximum) Telephone costs as determined by a site survey conducted at each proposed facility by an engineer from the applicable deregulated vendor. (Weighting: 5 maximum) Relocation of furniture and equipment not addressed above. (Weighting: 5 maximum) LOCATION The effect of environmental factors, including the physical characteristics of the building and the area surrounding it, on the efficient and economical conduct of Departmental operations planned for the requested space. Proximity of facility to a preferred area, such as a courthouse or main traffic arteries. (Will not be applicable if there are no preferred areas within the bid boundaries). (Weighting: 5 maximum) Frequency and availability of satisfactory public transportation near the offered space. (Weighting: 5 maximum) Proximity of offered space to the clients to be served by the Department at this facility. (Weighting: 5 maximum) Aesthetics of the building, property the building site [is] on, and of the surrounding neighborhood. (Weighting: 1 maximum) Security issues posed by building and surrounding neighborhood. (Weighting: 1 maximum) PROPERTY Susceptibility of the property's design to efficient layout and good utilization, such as ability of physical structure to house large units together and in close proximity to interdependent units. (Weighting: 15 maximum) Suitability of the building, parking area and property as a whole for future expansion. (Weighting: 5 maximum) Provision of the aggregate square footage in a single building. Proposals will be considered (but fewer points given) which offer the aggregate square footage in not more than two buildings provided the buildings are immediately adjacent to or within 100 yards of each other. If in separate buildings, the structures are connected by enclosed climate controlled walkways. (Weighting: 2 maximum) Prospective bidders were instructed on page B-3 of the ITB that they had to submit their bids on the 22-page Bid Submittal Form, which comprised Section C of the ITB. The Bid Submittal Form (BSF) provided detailed information regarding the needs of the Department and the terms, conditions and requirements that prospective bidders were expected to meet. Among the requirements addressed was that the proposed space be an "existing building," meaning that it was "dry, fully enclosed, and capable of being physically measured." The BSF further indicated that a multistory building would be acceptable, provided that it met certain specified requirements. In addition, pages C-3 through 4 of the BSF informed prospective bidders that, as part of their bid submittal, they would have to provide, among other things, the following: * * * b. A scaled (1/16" or 1/8" or 1/4" 1'0") floor plan showing present configurations with measurements. The final floor plan will be described in the specifications. * * * A scaled site layout showing present location of building(s), location, configuration and number of parking spaces assigned to the Department, access and egress routes and proposed changes. This is to be drawn to scale. Final site layout will be a joint effort between Department and Lessor so as to best meet the needs of the Department. The subject of floor plans was also discussed on page C-11 of the ITB, which provided in pertinent part as follows: Final floor plans will be a joint effort of Departmental staff and the successful bidder. The successful bidder is to provide architectural services by a licensed architect to prepare renovation plans. The final floor plan is subject to Departmental determination and State Fire Marshal review and approval. 3/ Prospective bidders were issued the following advisement and warning on page B-8 of the ITB regarding their protest rights: Any person may dispute any part of the competitive bid process through the filing of a protest. To be considered, a protest must be filed in accordance with Section 120.53(5), Florida Statutes, and Chapter 10-13.11 Florida Administrative Code. Failure to file a protest within the prescribed time limits shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. Prospective bidders, who did not want to file a protest, but merely desired clarification regarding a matter relating to the bidding process, were directed, on page B-3 of the ITB, to follow the following procedure: Any questions concerning an interpretation of meaning, ambiguity, or inconsistency on this project are to be received in writing by the project contact person listed on page A-1 [Steven Young) at least 5 working days prior to bid opening so that a written response may be provided to all bidders. 4/ The mandatory pre-proposal conference on the ITB was held as scheduled on April 5, 1991. Petitioner/Intervenor Schlitt, Petitioner/Intervenor Hedin, and Intervenor 1436 Building, Inc. (hereinafter referred to as "`1436") appeared in person or through a representative at the conference. One other prospective bidder, Alan Taylor, was also in attendance. Among the topics discussed at the pre-proposal conference was the present value index discount rate that would be applied in evaluating proposals. The prospective bidders were advised that the rate which appeared on page C-21 of the ITB-- 7.73%--, not the 8.74% rate appearing on page B-5, would be used. Prospective bidders were also told at the pre- proposal conference that the maximum number of total points available for moving costs was not 15 or 16 as a reading of the ITB might suggest, but 21: 5 for item 1)a) (computer drop lines);6 for item 1)b) (statewide operational data system equipment); 5 for item 2 (telephones); and 5 for item 3 (furniture and other equipment). Under the ITB, as originally issued and clarified at the pre-proposal conference (hereinafter referred to as the "Original ITB"), Respondent was to pay its own moving costs, as it had consistently done in the past, without any contribution on the part of the successful bidder and it would award points to each bidder for moving costs based upon what it would cost Respondent, according to its estimates, to relocate computer drop lines, statewide operational data system equipment, telephones, and furniture and other equipment to the facility proposed by that bidder. The less the expense to the Department to relocate these items, the more points a bidder would receive. Accordingly, to the extent that he intended to offer space already occupied by Respondent, Petitioner/Intervenor Hedin had an advantage over the other prospective bidders under the Original ITB. Some time after the pre-proposal conference, David Feldman, 1436's representative, complained to Respondent about this advantage enjoyed by Hedin in the category of moving costs and inquired if anything could be done about it. Steven Gertel, the Respondent's Assistant Staff Director for Facilities Services, Kevin McAloon, the General Services Manager for Respondent's District IX, Louis Consagra, the then Office Operations Manager for General Services for District IX, and Steven Young, the Facilities Services Manager for District IX and the contact person referenced in the ITB, discussed the matter during a telephone conference call held on April 11, 1991. During their discussion, it was decided that it would be in the best interest of the Department, which was operating under severe fiscal constraints, to change the ITB to allow prospective bidders to essentially buy points by agreeing to pay all or a portion of Respondent's estimated moving costs. Such a change, it was thought, would enhance the competitiveness of the bidding process. Before making the change, however, Respondent attempted to quickly estimate what its costs would be if it had to relocate computer drop lines, statewide operational data system equipment, telephones, and furniture and other equipment to another facility in Indian River County within the geographical boundaries prescribed in the ITB. Respondent estimated that it would cost between $25,000 and $30,000 to relocate computer drop lines and statewide operational data system equipment, $35,000 to $45,000 to relocate telephones and $8,000 to $10,000 to relocate furniture and other equipment. In arriving at these estimates, Respondent relied upon agency personnel who, because of their experience, expertise and/or access to contracts with vendors and other pertinent documents, appeared to be reliable sources of information. On April 12, 1991, the day after the telephone conference call and twelve days before the scheduled bid opening, Facilities Services Manager Young, on behalf of the Department, sent by United States Certified Mail, return receipt requested, to all four prospective bidders who attended the mandatory pre- proposal conference on April 5, 1991, the following memorandum: Page C-22 of the Bid Submittal Form has been changed and is enclosed for use in the Invitation to Bid. Please call me if you have any questions on this change/addition or any information that is needed to complete your Bid Submittal on or before 3:30 p.m., April 24, 1991. The "changed" page C-22 of the ITB, which accompanied the foregoing memorandum, provided as follows with respect to moving costs: The bidder will respond to the items as stated in the Bid submittal,, Page B-6, b. Moving Costs: 1) a) b), 2), 3). Department Bidder Estimate Response 1) a) b) $25,000 to $30,000 2) $35,000 to $45,000 3) $8,000 to $10,000 Young also telephoned each of the four prospective bidders and explained to them how moving costs would be evaluated in light of this revision to the ITB. He told them that if they indicated under "Bidder Response" on page C-22 that they would be willing to pay up to $30,000 for item 1, $45,000 for item 2 and $10,000 for item 3, and in Hedin's case, provided he submitted a bid that included the 12,000 square feet of space presently occupied by Respondent, 28% of these amounts, they would capture the maximum number of points available for each of these items, and that if they indicated a willingness to contribute less than these amounts, they would be awarded points in proportion to amount of their proposed contribution. 5/ Respondent's decision to allow Hedin to earn the same amount of points as the other prospective bidders for moving costs by pledging to contribute only 28% of what his competitors had to pledge was based upon square footage considerations. If a bidder other than Hedin was awarded the lease, Respondent would have to move into more than 17,000 square feet of space. If, on the other hand, Hedin submitted a bid that included the 12,000 square feet of space presently occupied by Respondent and he was the successful bidder, Respondents would be occupying only 5,000 or so square feet of space it had not previously occupied, or approximately 28% of the square footage that it would have to move into if the lease had been awarded to another bidder. The ITB, as so revised and clarified by Respondent (hereinafter referred to as the "Revised ITB"), contemplated that the successful bidder would be obligated to pay only Respondent's actual moving costs up to the amounts pledged on page C-22 of the bidder's completed BSF. Moving costs in excess of the amounts pledged by the successful bidder would be borne by Respondent. Respondent wanted to avoid a situation where, because of Respondent's estimating errors, a successful bidder: was forced to bear a cost in connection with its bid that it did not anticipate at the time it had submitted the bid. Respondent, however, was quite confident that the estimates it had made and incorporated in the Revised ITB would not prove to be too low. 6/ All four of the prospective bidders who participated in the mandatory pre-proposal conference submitted timely bids. Each of bids was deemed to be responsive. Facility Services Manager Young then performed the calculations necessary to determine the number of points that each bidder should be awarded for associated fiscal costs, including rental costs and moving costs. This was purely an objective and non-judgmental exercise. Young performed these calculations in accordance with the methodology that had been described to all of the bidders prior to the submission of their bids. Schlitt had the lowest rental rates for the basic term of the lease, as well as for the five option years. Accordingly, he was awarded the maximum 35 points for the former and the maximum 5 points for the latter, for a total of 40 points. The scores received by the other bidders for rental costs were as follows: 1436- basic term: 34.125, and option years: 4.340; Hedin- basic term: 28.865, and option years: 3.710; and Taylor- basic term: 31.938, and option years: 4.575. Schlitt and 1436 indicated on page C-22 of their completed BSFs that they were each willing to pay up to $30,000 for the relocation of computer drop lines and statewide operational data system equipment, up to $45,000 for the relocation of telephones and up to $10,000 for the relocation of furniture and other equipment. Accordingly, they were both awarded the maximum 21 points for moving costs. Hedin indicated on page C-22 of his completed BSF that he was willing to pay up to 28% of these amounts ($8,400.00 for the relocation of computer drop lines and statewide operational data system equipment, $12,600 for the relocation of telephones and $2,800 for the relocation of furniture and other equipment). Accordingly, he too was awarded the maximum 21 points for moving costs. Taylor, who indicated on page C-22 of his completed BSF a willingness to contribute only a small fraction of the Respondent's estimated moving costs, received a total of 1.667 points for moving costs. After computing these scores 7/ Young prepared a written synopsis of all four bids that had been submitted. He gave copies of his synopsis to the four members of the bid evaluation committee, along with score sheets for them to use in their evaluation of these bids. Typed in on each score sheet were the scores the bidders had received for rental costs and moving costs. These scores were accurately reported on the score sheets except for the score that Hedin had been awarded for rental costs associated with the basic term of the lease. The score sheets erroneously indicated that Hedin had been awarded 32.375 points, rather than 28.665 points, for this item. The four members of the bid evaluation committee were: General Services Manager McAloon; Frank Mueller, District IX's chief financial officer; and Kathy Pelaez and Alfred Swanson, two HRS administrators who supervise staff headquartered in Respondent's Indian River County client service center. 8/ Young, because he was the Facilities Services Manager, was prohibited by agency practice 9/ from serving on the bid evaluation committee. The bid evaluations committee visited each of the bidder's proposed facilities before determining the amount of points to award them for the non- economic categories, i.e., location and property, set forth in the Revised ITB. The committee members visited Schlitt's, 1436's and Taylor's proposed facilities on the same day. They subsequently paid a visit to Hedin's proposed property, which consisted of the building presently occupied by Respondent, plus an addition of approximately 5,000 square feet connected to the existing building by a walkway. The delay in visiting Hedin's proposed facility was the result of a determination, later overturned, that the entire facility was not dry and measurable as required by the Revised ITB. Following their visits to Schlitt's, 1436's and Taylor's proposed facilities, the members of the bid evaluation committee met as a group and discussed each of these proposed facilities. They had a similar meeting and discussion about Hedin's proposed facility after their visit to that proposed facility. Applying the criteria set forth in the Revised ITB, the committee members agreed that the following point awards should be made for the categories of location and property: location/proximity to preferred area (evaluation criterion 2.a., 5 point maximum)- Schlitt: 3, 1436: 2, Hedin: 5, and Taylor: 1; location/public transportation (evaluation criterion 2.b., 5 point maximum)- all four bidders: 0; location/proximity to clients (evaluation criterion 2.c., 5 point maximum)- Schlitt: 3, 1436: 2, Hedin: 5, and Taylor: 1; location/aesthetics (evaluation criterion 2.d., 1 point maximum): Schlitt, 1436, and Hedin: 1, and Taylor: 0; location/security (evaluation criterion 2.e., 1 point maximum)- all bidders: 1; property/design (evaluation criterion 3.a., 15 point maximum)- Schlitt: 9, 1436: 15, Hedin: 14, and Taylor 10; property/future expansion (evaluation criterion 3.b., 5 point maximum): Schlitt: 4, 1436: 5, Hedin 3.5, and Taylor 3, and property/square footage in single building (evaluation criterion 3.c., 2 point maximum)- Schlitt, 1436, and Taylor: 2, and Hedin: 1. Each of the members of the evaluation committee then recorded these scores on their individual score sheets. Although they agreed to each award the same number of points, evaluation committee members were free to do otherwise. They were not subjects to any threats or coercion. The members of the evaluation committee made a good faith effort to fairly base their point awards on the evaluation criteria for the categories of location and property prescribed in the Revised ITB. For instance, they awarded Schlitt only nine out of a possible 15 points for property/design because of their reasonable concerns that the space he offered, which was located in a multistory building which would have other tenants in addition to the Department, would not be able to house large units together and in close proximity to interdependent units. The committee members did not have similar concerns about the space offered by 1436. Accordingly, they awarded 1436 the maximum 15 points for this category. The points awarded by the evaluation committee for location and property were added to the points the bidders had previously received for rental and moving costs to obtain a total point award for each bidder. The; results were as follows: 1436- 87.465 total points; Schlitt- 84 total points; Hedin- 83.875 total points; and Taylor- 56.18 total points. 1436's bid was therefore the "lowest and best bid," as defined on page B-1 of he Revised ITB. Consistent with the Revised ITB's pronouncement that "[t]he successful bid will be that determined to be the lowest and best," the evaluation committee recommended to the District IX Administrator that 1436 be awarded Lease No. 590:2241. General Services Manager McAloon, in his capacity as chairman of the evaluation committee, provided the District IX Administrator with a written justification for the committee's recommendation. 10/ The committee's recommendation, as well as its written justification, were adopted by the District IX Administrator, who, by letter dated October 3, 1991, to 1436, gave notice of the Department's intention to award 1436 Lease No. 590:2241. Copies of this letter were sent to all bidders. The Department's preliminary decision to award the lease to 1436 was the product of, not any fraudulent, arbitrary, capricious or unlawful conduct on the Department's part, but rather the honest exercise of the agency's discretion. After receiving their copies of the District IX Administrator's October 3, 1991, letter to 1436, Schlitt and Hedin filed protests and initiated the instant proceedings.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Department of Health and Rehabilitative Services enter a final order awarding Lease No. 590:2241 to 1436 over the protests of Schlitt and Hedin. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 24th day of February, 1992. STUART M. LERNER Heading Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of February, 1992.
The Issue At issue in this proceeding is whether the Department of Environmental Protection's decision to reject all bids submitted for the project entitled BDRS 52-01/02 was illegal, arbitrary, dishonest, or fraudulent.
Findings Of Fact Parties Petitioner, All America Homes of Gainesville, Inc. (All America), is a corporation doing business in the State of Florida. All America submitted a timely written bid in response to the Department's ITB and filed timely protests to the Department's actions. The Respondent, the Department of Environmental Protection, is an agency of the State of Florida which manages and operates state parks under its jurisdiction, and solicits construction projects in state parks, pursuant to Chapter 258, Part I, Florida Statutes, through its Division of Recreation and Parks, Bureau of Design and Recreation Services. The ITB In November, 2001, the Department issued an ITB on a construction project entitled Hillsborough River State Park Concession Building, project number BDRS 52-01/02. The ITB included the Bid Specifications for the project. Bids were required to be submitted no later than 3:30 p.m. on Tuesday, December 18, 2001, at the Bureau's Tallahassee, Florida, office. The written Specifications define several terms, including, but not limited, to the following: ADDENDUM: A written explanation, interpretation, change, correction, addition, deletion, or modification, affecting the contract documents, including drawings and specifications issued by the OWNER [Department] and distributed to the prospective Bidders prior to the bid opening. ALTERNATE BID: Separate optional bid item for more or less project requirement used for tailoring project to available funding. Also may consist of alternate construction techniques. BASE BID: Formal bid exclusive of any alternate bids. BID FORM: The official form on which the OWNER requires formal bids to be prepared and submitted. ORAL STATEMENTS: Verbal instruction. NOTE: No oral statement of any person, whomever shall in any manner or degree modify or otherwise affect the provisions of the contract documents.[1] SEALED BID: The formal written offer of the Bidder for the proposed work when submitted on the prescribed bid form, properly signed and guaranteed. The Bid Specifications also contained the following relevant sections: Alternatives If the OWNER wishes to learn the relative or additional construction cost of an alternative method of construction, an alternative use of type of material or an increase or decrease in scope of the project, these items will be defined as alternates and will be specifically indicated and referenced to the drawings and specifications. Alternates will be listed in the bid form in such a manner that the Bidder shall be able to clearly indicate what sums he will add to (or deduct from) his Base Bid. The OWNER will judge for himself that such alternates are of comparable character and quality to the specified items. The Order of the alternate may be selected by the Department in any sequence so long as such acceptance out of order does not alter the designation of the low bidder. ADDENDA If the Consultant[2] finds it would be expedient to supplement, modify or interpret any portion of the bidding documents during the bidding period, such procedure will be accomplished by the issuance of written Addenda to the bidding documents which will be delivered or mailed by the OWNER'S Contracts section to all bidders who have requested bidding documents. Interpretation No interpretation of the meaning of the drawings, specifications or other bidding documents and no correction of any apparent ambiguity, inconsistency or error therein will be made to any Bidder orally. Every request for such interpretation or correction should be in writing, addressed to the Consultant. All such interpretations and supplemental instructions will be in the form of written Addenda to the bidding documents. Only the interpretation or correction so given by the Consultant in writing and approved by the OWNER shall be binding, and prospective Bidders are advised that no other source is authorized to give information concerning, or to explain or interpret, the bidding documents. B-16 Bid Modification Bid modification will be accepted from Bidders, if addressed as indicated in Advertisement for Bids and if received prior to the opening of bids. No bid modification will be accepted after the close of bidding has been announced. Modifications will only be accepted if addressed in written or printed form submitted with the bid in sealed envelopes. Telegrams, facsimiles, separate sealed envelopes, written on printed modifications on the outside of the sealed envelopes will not be accepted. All bid modifications must be signed by an authorized representative of the Bidder. Modification will be read by the OWNER at the opening of formal bids. B-21 Rejection of Bids The OWNER reserves the right to reject any and all bids when such rejection is in the interest of the State of Florida, and to reject the bid of a bidder who the OWNER determines is not in a position to perform the work. B-23 Award of Bid . . .The qualified Bidder submitting the lowest bid will be that Bidder who has submitted the lowest base bid plus any selected alternates. . . . The OWNER reserves the right to waive any minor irregularities in bids received when such waiver is in the interest of the OWNER. The Award of Bid will be issued by the OWNER only with responsible Bidders, found to meet all requirements for Award of Bid, qualified by experience and in a financial position to do the work specified. Each bidder shall, if so requested by the OWNER, present additional evidence of his experience, qualifications and ability to carry out the terms of the Agreement. (Emphasis in original, except for Section B-10.) The Bid Form is included with the Specifications and provides in part: Base Bid: Furnish labor, equipment, Lump Sum $ supervision and material to construct a new concession building of 2940 square feet located at the Hillsborough River State Park along with the alteration of the existing concession building according to plans and specifications. Alternate #1: Furnish labor, equipment, Add Amt.$__ supervision and material to renovate the existing concession building according to plans and specifications. There is a separate section for "Allowances," i.e., Section 01210, for the Hillsborough State Park. This section provides in part: SECTION 01210 – ALLOWANCES * * * 1.2 SUMMARY This Section includes administrative and procedural requirements governing allowances. Certain materials and equipment are specified in the Contract Documents and are defined by this [sic] specifications as material and labor to be provided against a pre-determined allowance. Allowances have been established in lieu of additional requirements and to defer selection of actual materials and equipment to a later date when additional information is available for evaluation. If necessary, additional requirements will be issued by Change Order. * * * 3.3 SCHEDULE OF ALLOWANCES A. Allowance #1: Include in the base bid an allowance for the purchase and installation of. . . kitchen equipment. . . . The total dollar amount of the allowance to be included shall be $12,000.00. There is also a separate section for "Alternates," i.e., section 01230, for Hillsborough River State Park, which provides in part: SECTION 01230 – ALTERNATES * * * 1.3 DEFINITIONS Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the Bidding Requirements that may be added to or deducted from the Base Bid amount if OWNER decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate alternate into the Work. No other adjustments are made to the Contract Sum. . . . . 3.1 SCHEDULE OF ALTERNATES A. Alternate No. 1: Renovate the existing concession building in its entirety as shown in the drawings and specified herein. (emphasis added.) At this stage of the bidding documents, the contractor/bidder is requested to provide a Base Bid/Lump Sum on the Bid Form to "[f]urnish labor, equipment,. . .to construct a new concession building," and to provide an additional and separate amount for Alternate No. 1 to "[f]urnish labor, equipment, . . . to renovate the existing concession building." On December 13, 2001, the Bureau issued "Addendum No. One (1)" (written by the architect) to the ITB on the "Hillsborough River State Park – Concession Building." The Addendum contained the following relevant sections: Specification Section 01210: Allowances Add the following new paragraph 3.3.B: ”Allowance #2: Include in the base bid an allowance for the renovations of the existing concession building; renovations shall be defined by the Owner. The total dollar amount of the allowance to be included shall be $25,000." Specification Section 01230: Alternates Modify paragraph 3.1.A. as follows: "Alternate No. 1: Renovate the existing concession building as defined by the Owner, and as provided for under Section 01210, Allowances." (emphasis added.) Each contractor was required to sign the Addendum and attach it to the bid. By definition, and pertinent here, an addendum is an additional written instruction to a contractor during the bidding process. Based on the weight of the evidence, the purpose of this Addendum was to require the contractor to include a $25,000.00 Allowance (for Allowance # 2) in the Base Bid, for the work which might be performed if the Department requested the work to be performed for Alternate No. 1, i.e., for the renovation of the existing concession building.3 (The Department's architect decided it would cost approximately $25,000.00 to renovate the existing concession building, hence Allowance # 2.) In other words, the Addendum does not have a specific dollar amount to be included for Alternate No. 1. Rather, the $25,000.00 is an Allowance for the work described as Alternate No. 1, but the amount is to be included in the Base Bid and not as a separate line item, dollar amount. But, importantly, the Addendum did not delete the potential work to be performed as described in Alternate No. 1, although Mr. Bowman and others believed that the Addendum deleted Alternate No. 1. It deleted the necessity to place a specific dollar amount on the Bid Form for Alternate No. 1. (Mr. Bowman is a registered Professional Engineer and a licensed contractor. He has worked for the Department for 15 years and has served as Bureau Chief for two years. He supervises the contract section and the design section, which was responsible for preparing the technical plans and specifications and bidding out the job.) Mr. Bowman offered the following explanation why he believed the Addendum was confusing: Okay. I think the confusion that was created, you know, I think the addendum in itself, you know, said add $25,000 to the base bid, but then on the bid form, it still had the space down there for alternate number one, which alternate number one, which alternate number one had become $25,000 that was to be allowed for the concession building, and I think that's where the confusion came in because I think they were still confused, that they weren't really sure that they should not put that 25 down there but they knew they had been told in the addendum to do it and I think that's the reason for the notes and we got to the correspondence on the bid form, was they wanted to make sure that that's what we were wanting to do. And I think that's where the confusion came in. Like I said, it's always, if you could go back and do it again, it would be much wiser just to issue a whole new bid form and then we wouldn't be here today. But, we didn't do that. Okay. So, that's why we are here. The language in this Addendum, when read with the original Bid Specifications, apparently caused confusion with some of the bidders on the project. Several bidders called Marvin Allen (an architect and project manager for the Department's Bureau of Design and Recreation Services) prior to the submission of the bids, to clarify how the $25,000.00 Allowance should be shown on the Bid Form. (Mr. Allen did not author any of the specifications, including the Addendum.) He was listed as a contact person. He did not contact any bidders. But, Mr. Allen recalled telling each bidder who asked that the Allowance of $25,000.00 should be included in the Base Bid. But, he does not recall the names or numbers of the bidders who called, "possibly" three, four or five. Mr. Allen believed the Addendum was clear. According to Mr. Allen, the bidders who called him found the Addendum confusing. The oral responses to the bidders can be construed as interpretations of the Addendum. However, pursuant to Section B- 10 of the Specifications, any such interpretations were required to "be in the form of written Addenda to the bidding documents." Also, any such questions should have been in writing. If Section B-10 were complied with, all bidders would have been potentially on the same footing, or, at the very least, would have had access to a written clarifying document. Opening of the Bids On December 18, 2001, the bids were opened by Mike Renard, Contracts Manager with the Bureau of Design and Recreation Services, and Susan Maynard, Administrative Assistant. Mr. Dwight Fitzpatrick, a representative of All America, also attended the bid opening. The Bid Form submitted by Nelco showed a Base Bid of $355,478.00 (Lump Sum $355,478.00), and also showed an amount of $25,000.00 on the Alternate # 1 line (Add Amt. $25,000.00). See Finding of Fact 6. (It was clear to Mr. Renard that the $25,000.00 should have been included on Nelco's Base Bid. But Mr. Renard believed that Nelco submitted a responsive bid because the Department only accepted the Base Bid. Mr. Bowman agreed.) Nelco was the only one of five bidders to have a dollar amount in the Alternate #1 line under "Add Amt. $ ." All America submitted the second lowest Base Bid of $362,000.00. There was also a hand-written note on the All- America Bid Form that stated: "Addenda # 1 instruction to place $25,000 allowance in both Base Bid and as alternate # 1." Another hand written note was located below the "Add Amt. $-0-" line: "amount added in Base Bid with $25,000 allowance per Marvin Allen." The Department considered All America's bid responsive. It is a fair inference that three out of five of the other Bid Forms contained language indicating that the bidders were relying on Addendum No. One by placing the $25,000.00 Allowance in the Base Bid.4 It is uncertain whether they did so in light of the instructions of Mr. Allen concerning how to complete the Bids Forms. However, given the nature of the calls to Mr. Allen, there is a reasonable inference that there was some confusion among some of the bidders. The Department determined that Nelco submitted the lowest Base Bid, but the Department's staff had a question as to whether Nelco had included the $25,000.00 in its Base Bid. After conferring with his superiors, Mr. Renard was instructed to call Nelco to make certain that its Base Bid included the Allowance amount ($25,000.00). Mr. Renard spoke with Steve Cleveland, Nelco's Project Manager, "to verify the fact that [Nelco] had the allowance in their base bid." Mr. Cleveland orally confirmed that Nelco's Base Bid included the $25,000.00 Allowance. Mr. Renard asked Mr. Cleveland to send him a letter verifying this statement. Mr. Renard viewed this inquiry as a request for clarification or verification, not an opportunity for Nelco to modify its bid. Mr. Bowman agreed. (Mr. Renard did not believe Addendum No. 1 was confusing.) In a letter dated December 20, 2001, Mr. Cleveland confirmed that Nelco’s Base Bid of $355,478.00 included the Allowance amount and that Nelco could still perform the contract if the $25,000 Allowance was removed from its Base Bid pursuant to the ITB, i.e., that Nelco would perform the contract for $355,478.00 less $25,000.00, or $330,478.00, if the Department did not accept Alternate # 1 and the Allowance. (An alternate does not have to be accepted by the Department.) According to Mr. Renard, Mr. Cleveland never mentioned modifying, changing, or altering Nelco's bid. The Department only accepted the Base Bid for each bid. Mr. Renard did not consider it unusual to call a bidder or contractor to verify information to determine whether they can or cannot perform the work at the stipulated price. He considered it common to make this inquiry. Also, it was common in Mr. Bowman's experience to call a bidder to get clarification. Mr. Renard was not aware of any statute or rule which authorizes the Department to request clarification from a bidder after the bids are opened. Mr. Renard was more familiar with the bid forms than Mr. Allen. After receiving Mr. Cleveland's letter, the Department determined that Nelco submitted the lowest Base Bid and that the $25,000.00 amount that Nelco wrote on the Bid Form Alternate # 1 line, was a minor irregularity in the bid which the Department, as the Owner, could waive pursuant to the ITB. On December 20, 2001, the Department posted the Tabulation of Bids showing the anticipated award of the contract to Nelco. At the hearing, an unsigned letter on Department letterhead was introduced, which was addressed to Nelco and stated that Nelco submitted the apparent low bid. However, Mr. Renard testified that these letters are prepared routinely, but not mailed out without his signature. Mr. Renard did not recall signing the letter or ever sending out such a letter to Nelco. On December 21, 2001, the Department received a Notice of Intent to Protest letter from Allen E. Stine, the President of All America. In his letter, Mr. Stine stated that Nelco’s bid should have been rejected for failure to follow the specified format as per Addendum No. 1, or adjusted to have the $25,000.00 amount added to their Base Bid. Bid Protests All America filed a written formal bid protest on January 4, 2001. On January 9, 2001, Cindy Otero of All America, notified Mr. Renard by letter, and stated that Mr. Stine was available for a hearing regarding the bid protest. On January 28, 2002, Mr. Renard returned All America's check for the bond, stating that it was unnecessary. Mr. Stine recounted a number of unanswered telephone calls after the first protest was filed. During one conversation, Mr. Renard recalled Mr. Stine saying to him, "You can't do this, you can't do this." After receiving the first formal protest, the Department staff consulted with legal staff and reviewed the documents and bid procedures. Based on the number of questions received concerning the Addendum and the hand-written notes on several of the bid forms, Mr. Bowman, Bureau Chief, determined that the bid documents were confusing and ambiguous. (Mr. Bowman stated that this was their first bid protest in his 15 years with the Department.) Therefore, Mr. Bowman decided that it would in the best interest of the State of Florida to reject all of the bids pursuant to the Bid Specifications. Mr. Bowman felt that the ITB should be re-written in order to make it clearer and allowing all of the bidders to re-bid the project without any confusion or ambiguity. Mr. Stine stated that his "senior estimator" told him that the bid language "could be confusing." He and his "senior estimator" had a discussion about whether the Allowance should have been placed in the Base Bid or not. At the time of submission of All America's bid, Mr. Stine was clear that the Allowance should be placed in the Base Bid, especially after calling Mr. Allen. But, his senior estimator was not so clear. In order to appease him, Mr. Stine placed the hand-written note on All America’s proposal. Mr. Stine essentially, "cleaned" up his proposal. At the hearing, Mr. Bowman testified Rule 60D-5.0071, Florida Administrative Code, see Conclusion of Law 59, does not list "confusing or ambiguous bid specifications" as one of the circumstances allowing for the rejection of all bids. However, Mr. Bowman later stated during the hearing that he believed the circumstances listed in Rule 60D-5.0071 were not the only circumstances authorizing the Department to reject all bids. Mr. Bowman testified that he believed that general confusion among the bidders caused by the ambiguous ITB constituted sufficient grounds for rejecting all bids. Mr. Bowman was advised by legal counsel that rejecting all of the bids would probably result in another bid protest by Nelco, All America, or both. Thus, the Department decided to delay addressing All American’s first protest until after posting the rejection of all bids and receiving the subsequent protests, so that all of the protests could be resolved at once in an efficient and economical manner. Notwithstanding the Department's justifications for rejecting all bids and not proceeding on All America's initial protest, the record is unclear why the Department waited several months to reject all bids. On May 13, 2002, the Department posted the rejection of all bids. On May 16, 2002, the Department received a formal written protest of the rejection of all bids filed by All America. On May 17, 2002, Jerome I. Johnson, attorney for the Department, contacted Mr. Robert A. Lash, All America's counsel at the time, concerning the resolution of All America’s formal protest. (Before the final hearing, Mr. Lash, with All America's consent, withdrew as counsel for All America.) The parties agreed to suspend formal bid protest procedures until a meeting could be held between the parties in an attempt to resolve the protests. Mr. Johnson sent a letter dated May 21, 2002, to Mr. Lash confirming this conversation. On June 26, 2002, a meeting was held among the Department staff, legal staff, and Mr. Lash and Mr. Stine, representing All America. The parties were unable to resolve the protests. At the conclusion of the meeting, the parties agreed that formal protest procedures would not be implemented until Mr. Stine could confer further with his counsel. In a letter dated July 5, 2002, Mr. Lash stated that his client wished to proceed with formal protest procedures and requested an administrative hearing on the protests. Are the Specifications and Bid Documents Ambiguous and Was There Confusion? The parties stipulated that "[t]he Addendum language was confusing," notwithstanding the testimony of several witnesses that they were not confused. The Department's determination that the bid Specifications, including the Addendum, and the Bid Form, which remained unchanged after the Addendum was issued, were confusing and ambiguous, is supported by the weight of the evidence. This is particularly true regarding the Bid Form. The Addendum required the bidder to include an Allowance of $25,000.00 in the Base Bid for work described as Alternate # 1. But the Bid Form was unchanged to reflect the Addendum changes. The Bid Form retained a line for the bidder to submit an additional amount for Alternate # 1. Further, it appears that several bidders were confused, including, Mr. Stine, who spoke with Mr. Allen and requested and received clarification. Further, it is unclear whether all of the bidders, including Nelco, were aware of the oral interpretations or clarifications of the Addendum rendered to some of the bidders. Rejection of All Bids Based upon the foregoing, given the standard of review in this proceeding discussed in the Conclusions of Law, the weight of the evidence indicates that the Department's action, in rejecting all bids, was not illegal, arbitrary, dishonest, or fraudulent. The Department's staff was well-intended and made some mistakes along the way, e.g., by not changing the Bid Form, which they readily admit. But there was a rationale for rejecting all bids under the circumstances.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department issue a final order dismissing All America’s Petition to Prevent Rejection of Bids and Award Contract to Petitioner and denying All America's request for attorney’s fees and costs. DONE AND ENTERED this 24th day of September 2002, in Tallahassee, Leon County, Florida. CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of September 2002.
Findings Of Fact During the month of March 1996, the Pinellas County School Board, pursuant to an advertised invitation for bids, (IFB), solicited bids for the construction of a new facility for John H. Sexton Elementary School (Sexton school). Each party submitting a bid was required to do so on a bid proposal form which was contained in the bid documents prepared by the project architect, Mr. Hoffman, and furnished to each prospective bidder who requested the bid package. One section of the bid proposal form related to "dewatering" potentially required at the construction site, and consistent with that potential two sentences were contained on the bid proposal form relating to dewatering of footings and of utilities, both of which provided for election by checking of an affirmative or a negative, and both of which had been pre-checked in the affirmative by the Board. It was the position of the Board that the pre- checked sentences as to dewatering on the bid proposal form constituted an acknowledgment by each bidder that that bidder's submittal included dewatering in the base bid. In addition to the check, the dewatering section also included blanks for the insertion by the bidder of figures representing lineal feet of header pipe and unit price per foot which figure would constitute a credit given by the bidder to the Board against the total bid price if dewatering were found not to be necessary, both as to footings and to utilities. Even further, the form also contained blanks to be filled in by the bidder for unit prices to be charged the Board in the event additional dewatering was required by virtue of the Board's later inclusion in the project of additional footings or utilities. Prior to the time for bid submittal, the Board conducted a meeting of all prospective bidders at which the project was explained and bidders given an opportunity to ask questions raised by the bid package. Johnson did not ask any questions regarding dewatering or that portion of the package relating thereto. Numerous bids were submitted in response to the proposal, including those from Johnson and Ellis. By stipulation at the hearing, the parties agreed that in all ways other than in that section of the bid proposal form for this project relating to dewatering, Johnson was and is a responsive and responsible bidder, as is Ellis. The bid proposals were opened by the Board at 2:00 PM on April 11, 1996 and the base bid prices on each proposal were read aloud to all in attendance by a Board representative. The project architect was present at the opening and tabulated and reviewed the bid proposals as opened. Johnson submitted the lowest base bid with a price of $7,965,000. The next lowest bid was that of Ellis, whose base bid price was $7,945,200. At the time of opening, no Board representative indicated anything was wrong with Johnson's bid Mr. Hoffman, the project architect, immediately noticed that Johnson had altered the Board's pre-checked bid proposal form by striking out the pre- checked "is" space regarding inclusion of dewatering in the base price of the two dewaterings, and making an X in each of the "is not" spaces. Mr. Hoffman considered that alteration by Johnson as a material alteration of the Board's solicitation which rendered Johnson's bid non-responsive. It must be noted that each change bears the initials, R. Y. Reza Yazdani is Johnson's president who initialed the changes and signed the bid proposal form for the company. In addition, Johnson also inserted a "0" in those spaces which dealt with amount of credit and cost of additional dewatering in the event additional work is required by the Board. In that regard, Hoffman opined that had Johnson not changed the check marks, but inserted the "0" figures as it did, the bid would have been responsive and Johnson would still have been lowest responsive bidder. The reason for this is that the bid form specifically notes that "the unit costs described in A & B above shall in no manner influence the School Board's selection of a firm to whom to award the Contract." The Board now recognizes that there is no part "B", as referenced in the proposal form. Since the "0's" would not influence the selection, use of an unmodified Board form, along with the lowest submitted base price would, in Hoffman's opinion, probably have meant that Johnson would have been awarded the contract. Johnson's representative, Mr. Mohme, who drafted the company proposal, specifically indicated he did not believe dewatering was a potential in this project. He recognized that such dewatering as was necessary was required by other provisions in the project specifications and he could not figure any way to recognize this and yet accurately reflect his belief that dewatering would not be necessary, other than to strike the pre-checked block and insert the check in the alternative block. He felt that by doing so, he was more accurately reflecting Johnson's bid. This reasoning is rather obscure. By letter dated April 12, 1996, written to the Board after the bids were opened, Mr. Mohme reiterated Johnson's position that dewatering is not necessary on this project, but further stated that if dewatering were to be necessary, Johnson would do so solely at its own risk and without any risk of additional cost to the Board. Bids may be clarified by a bidder, but such clarification must take place before the bids are opened. Bids may not be modified after bid opening. Before that letter was written, however, when the bids were opened and Mr. Hoffman observed what he considered was Johnson's alteration of the bid form, Hoffman consulted with a representative of the Board's purchasing department, Ms. Maas, who also reviewed Johnson's bid. Ms. Mass was of the opinion that Johnson may have attempted to qualify its bid, and she and Mr. Hoffman thereafter met with Mr. Rivas, the Board's director of facilities design and construction, to explain the problem. Mr. Rivas took the problem to two other Board personnel to see if there were some way Johnson's bid could be deemed responsive so that the Board could benefit by Johnson's low bid price. Within the context of those aforementioned discussions, Hoffman took the position that the alteration might leave the Board open to a possible change order and additional liability if dewatering were to be required and the Board had accepted Johnson's bid indicating that process was not included in the base price. Mr. Rivas, after consulting with the Board's attorney, also concluded that Johnson's alteration expressly excluded dewatering as an included factor and its exclusion constituted a serious and material deviation from the Board's solicitation. It was deemed material in that the deviation apparently gave Johnson a competitive advantage over other bidders who did not amend the form. This appears to be a valid conclusion and is adopted herein. The decision to recommend rejection of Johnson's bid and acceptance of Ellis's as the lowest responsive bid was ultimately reached by the Board's administrative staff. The Ellis bid was responsive to the solicitation whereas the determination was made that Johnson's was not responsive because of the alteration. It was not the actual act of alteration that caused that determination but rather the potential effect of the alteration. This was consistent with long standing Board policy not to accept a bid which does not conform to a bid solicitation and not to accept bids from bidders who alter the Board's bid proposal form or otherwise attempt to qualify their bids. It is the opinion of the Board personnel that such consistency in bidding procedure has resulted over time in more qualified bidders submitting bids for Board work which, in turn, has resulted in more competitive prices for the work let for bid. This is a reasonable policy. Mr. Gottschalk, Johnson's expert architect, who has designed schools for the Board, offered an alternative disposition to this dilemma. While admitting that Johnson's shifting of the risk of loss as a result of possible dewatering was a material matter, he suggested the Board could have disregarded the dewatering clause on every submittal and thereafter awarded the contract to Johnson, the lowest bidder, whose bid was responsive to the solicitation except for the dewatering provision. Recognizing this solution would have placed each bidder on an equal footing and allowed award to the lowest bidder at a substantial savings to the Board, he nonetheless also understood the decision made by Mr. Hoffman and the Board staff here and could not fault it. He agreed that reasonable men could differ on the issue of responsiveness here and how to deal with it. It is so found. After a review of the evidence submitted, including the testimony indicating the remoteness of the likelihood that extensive dewatering would be required, there appears to be no evidence that the Board, or its staff, acted dishonestly, fraudulently, illegally or arbitrarily in rejecting Johnson's bid on this project and recommending award to Ellis.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Pinellas County School Board enter a final order denying and dismissing G. H. Johnson Construction Company's protest and awarding a contract for the construction of Sexton Elementary School to Ellis Construction Company, Inc. DONE and ENTERED this 8th day of May, 1996, in Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of May, 1996. APPENDIX TO RECOMMENDED ORDER, CASE NO. 96-1942BID To comply with the requirements of Section 120.59(2), Florida Statutes (1993), the following rulings are made on the parties' proposed findings of fact: Johnson's Proposed Findings of Fact. 1.-5. Accepted and incorporated herein. Accepted. Accepted but not a proper Finding of Fact. More a restatement of and comment on testimony. Rejected. Accepted but not a proper Findings of Fact. More a restatement of and comment on testimony. &11. Accepted. Accepted and incorporated herein. First sentence accepted as a literal statement of what appears in the specifications. Second and third sentences accepted but not probative of any material issue of fact. Accepted and incorporated herein. First sentence accepted. Balance not Finding of fact but argument. Ellis' Proposed Findings of Fact. 1.&2. Accepted and incorporated herein. 3.-6. Accepted. 7.-10. Accepted and incorporated herein. 11.-15. Accepted and incorporated herein. 16. Accepted but word "certain" is changed to read "likely." 17.-21. Accepted and incorporated herein. 22. Accepted and incorporated herein. 23.&24. Accepted. 25.&26. Accepted and incorporated herein. 27.-29. Accepted. Accepted and incorporated herein. Not relevant to any material issue of fact. COPIES FURNISHED: Jawdet I. Rubaii, Esquire Clearwater Executive Suites, No. 213 1345 South Missouri Avenue Clearwater, Florida 34616 John W. Bowen, Esquire Pinellas County School Board 301 4th Street S.W. Largo, Florida 34649-2942 E. A. Mills, Jr. Esquire Dale W. Vash, Esquire Fowler, White, Gillen, Boggs, Villareal and Banker, P.A. 501 East Kennedy Boulevard Post Office Box 1438 Tampa, Florida 33601 Pinellas County School Board 301 4th Avenue, S.W. Largo, Florida 34649-2942
The Issue The issue in this bid protest is whether Respondent acted arbitrarily when it decided to reject all of the bids it had received in response to a solicitation seeking bids on a contract for roof repairs.
Findings Of Fact On January 10, 2008, the Florida Department of Environmental Protection (the "Department" or "DEP") issued an Invitation to Bid (the "ITB"), the purpose of which was to solicit competitive bids from qualified contractors on a project whose scope of work envisioned repairs to the wind-damaged roofs of several buildings located on the grounds of the Hugh Taylor Birch State Park in Fort Lauderdale, Florida. Some of the buildings to be repaired were single-family residences. Work on these structures accordingly needed to conform to the requirements prescribed in the 2007 Manual of Hurricane Mitigation Retrofits for Existing Site-Built Single Family Residential Structures (the "Manual"), which the Florida Building Commission (the "Commission"), following an explicit legislative directive, see Section 553.844(3), Florida Statutes,1 recently had adopted, by incorporative reference, as a rule. See Fla. Admin. Code R. 9B-3.0475 (2007).2 The Rule had taken effect on November 14, 2007, giving the Manual's contents the same status and force as the Florida Building Code. Id. Just before the Department issued the ITB, the Commission had approved, at a meeting on January 8, 2008, a modified version of the Manual, which it called the 2007 Manual of Hurricane Mitigation Retrofits for Existing Site-Built Single Family Residential Structures, Version 2 (the "Revised Manual"). In consequence of the Commission's approval of the Revised Manual, the Florida Department of Community Affairs ("DCA") caused a Notice of Proposed Rule Development to be published on January 25, 2008, in the Florida Administrative Weekly. This official advertisement announced that the Commission intended to amend Rule 9B-3.0475, so that its incorporative reference would mention the Revision Manual instead of the Manual. See 34 Fla. Admin. W. 461-62 (Jan. 25, 2008).3 DCA caused a Notice of Proposed Rule respecting the intended revision of Rule 9B-3.0475 to be published on February 1, 2008, in the Florida Administrative Weekly. See 34 Fla. Admin. W. 605 (Feb. 1, 2008).4 On February 5, 2008, the Department issued Addendum No. 4 to the ITB (the "Addendum"). The Addendum provided in pertinent part as follows: Bidders shall bid the project as specified despite the recent change in Rule 9B-3.0475 relating to hurricane mitigation retrofits. Any additional water barrier will be accomplished by Change Order after award of the contract. (The foregoing provisions of the Addendum will be referred to hereinafter as the "Directive"). On February 12, 2008, the Department opened the bids it had received in response to the ITB. Ten (out of 12) of the bids submitted were deemed responsive. The bid of Petitioner Spinella Enterprises, Inc. ("Spinella") was one of the acceptable bids. On February 19, 2008, DEP posted notice of its intent to award a contract to the lowest bidder, namely Spinella, which had offered to perform the work for $94,150. The second lowest bidder was The Bookhardt Group ("Bookhardt"). Bookhardt timely protested the intended award, raising several objections, only one of which is relevant here. In its formal written protest, dated March 3, 2008, Bookhardt alleged that "[t]he new State of Florida law F.S. 553.844 was not part of the solicitation." On April 4, 2008, Rule 9B-3.0475, as amended to incorporate by reference the Revised Manual, took effect. See Fla. Admin. Code R. 9B-3.0475 (2008). On May 16, 2008, DEP posted notice of its intent to reject all bids received in response to the ITB. (Bookhardt's protest, which remained pending, had never been referred to DOAH for a formal hearing.) Spinella timely protested the Department's decision to reject all bids. In an email sent to Spinella on July 22, 2008, DEP's counsel explained the rationale behind the decision: The reason the Department rejected all bids follows. When the Department posted the notice of intent to award the contract to Spinella Enterprises, Inc., the second low bidder (Bookhardt Roofing) protested the intent to award. The second low bidder's basis for protesting the intended award was that Addendum 4 directed bidders to ignore certain rules of the Construction Industry Licensing Board [sic], which had become effective after the bid opening, which was not in accordance with the law. As a result, this may have caused confusion and the Department had no assurance that bidders were bidding the project correctly. In addition, the statement in Addendum 4 that the Department would add the required moisture barrier afterward by change order set up a situation where bidders had no idea how much the Department would be willing to pay for the change order. Further, the moisture barrier was not the only thing required by the new rules. Potential bidders may not have bid due to these uncertainties. The Department agreed with Bookhardt's assertions and rejected all bids . . . . Notwithstanding Spinella's protest, the Department issued a second invitation to bid on the project in question. As of the final hearing, the bids received in response to this second solicitation were scheduled to be opened on August 12, 2008. Ultimate Factual Determinations The Department's decision to reject all bids is premised, ultimately, on the notion that the Directive told prospective bidders to ignore an applicable rule in preparing their respective bids.5 If this were true, then the Directive could have been a source of potential confusion, as the Department argues, because a prudent bidder might reasonably hesitate to quote a price based on (possibly) legally deficient specifications. The Directive, however, did not instruct bidders to ignore an applicable, existing rule. Rather, under any reasonable interpretation, it instructed bidders to ignore a proposed rule and follow existing law. Such an instruction was neither confusing nor inappropriate. To be sure, the first sentence of the Directive——at least when read literally——misstated a fact. It did so by expressing an underlying assumption, i.e. that Rule 9B-3.0475 recently had been changed, which was incorrect. In fact, as of February 5, 2008, the Rule was exactly the same as it had always been. (It would remain that way for the next two months, until April 6, 2008).6 DEP's misstatement about the Rule might, conceivably, have confused a potential bidder, at least momentarily. But DEP did not factor the potential for such confusion into its decision to reject all bids, and no evidence of any confusion in this regard was offered at hearing.7 More important is that the unambiguous thrust of the Directive was to tell bidders to rely upon the "not recently changed" Rule 9B-3.0475, which could only have meant Florida Administrative Code Rule 9B-3.0475 (2007) as originally adopted, because that was the one and only version of the Rule which, to that point, had ever existed. Thus, even if the Department were operating under the mistaken belief, when it issued the Addendum, that Rule 9B-3.0475 recently had been amended; and even if, as a result, DEP thought it was telling prospective bidders to ignore an applicable, existing rule, DEP nevertheless made clear its intention that prospective bidders follow the original Rule 9B- 3.0475, which was in fact the operative Rule at the time, whether or not DEP knew it. Indeed, as any reasonable potential bidder knew or should have known at the time of the Addendum, (a) the Commission recently had approved the Revised Manual, but the contents thereof would not have the force and effect of law unless and until the Revised Manual were adopted as a rule, which had not yet happened; (b) the Commission had initiated rulemaking to amend Rule 9B-3.0475 so as to adopt the Revised Manual as a rule, but the process was pending, not complete; (c) Rule 9B-3.0475 had not been amended, ever; and, therefore, (d) the Manual still had the force and effect of law. See endnote 6. The Directive obviously could not alter or affect these objective facts. At bottom, then, a reasonable bidder, reviewing the Directive, would (or should) have concluded either (a) that the "recent change" which DEP had in mind was the Commission's approval of the Revised Manual (or the subsequent announcement of the proposed amendment to Rule 9B-3.0475) or (b) that DEP mistakenly believed the Rule had been changed, even though it had not been. Either way, a reasonable bidder would (or should) have known that the Department wanted bidders to prepare their respective bids based not on the Revised Manual, but the Manual. In other words, regardless of what DEP subjectively thought was the existing law, DEP clearly intended (and unambiguously expressed its intent) that bidders follow what was, in fact, existing law. This could not have confused a reasonable bidder because, absent an instruction to exceed the minimum required legal standards (which the Directive was not), a reasonable bidder would have followed existing law in preparing its bid, just as the Directive required. Once it is determined that the Directive did not, in fact, instruct bidders to ignore an applicable, existing law, but rather told them to rely upon the applicable, existing law (notwithstanding that such law might change in the foreseeable future), the logic underlying the Department's decision to reject all bids unravels. Simply put, there is no genuine basis in logic or fact for concluding that the Addendum caused confusion. The other grounds that DEP has put forward do not hold water either. Contrary to the Department's contention, the possibility that a Change Order would be necessary if an "additional water barrier" were required could not possibly have confused potential bidders or caused them to be uncertain about how much money the Department would be willing to pay for such extra work. This is because Article 27 of the Construction Contract prescribes the procedure for entering into a Change Order, and it specifies the method for determining the price of any extra work. See ITB at 102-05. The fact that the proposed amendment to Rule 9B-3.0475, if it were to be adopted and become applicable to the instant project, might require other additional work, besides a water barrier, likewise could not reasonably have caused potential bidders to refrain from bidding, for the same reason: The Construction Contract contains explicit provisions which deal with the contingency of extra work or changes in the work. Id. In sum, DEP's intended decision to reject all bids cannot be justified by any analysis that a reasonable person would use to reach a decision of similar importance. It is, therefore, arbitrary.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department enter a final order finding that its decision to reject all bids was arbitrary. Because the Department elected not to comply with the statutory directive to abate this procurement pending the outcome of Spinella's protest, with the result that the contract at issue possibly has been awarded already to another bidder; and because the choice of remedies for invalid procurement actions is ultimately within the agency's discretion, the undersigned declines to make a recommendation regarding the means by which DEP should rectify the harm to Spinella, but he urges that other appropriate relief be granted if Spinella cannot be awarded the contact. DONE AND ENTERED this 2nd day of October, 2008, in Tallahassee, Leon County, Florida. JOHN G. VAN LANINGHAM Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 2nd day of October, 2008.
Findings Of Fact Based upon the documentary evidence received and the entire record compiled herein, I hereby note the following findings of fact: Notice and Invitation to Bid on State Project Number 72001-3448 (the project) was extended to various contractors by the Respondent, Department of Transportation, on August 1, 1985. Sealed bids on the project were opened August 28, 1985. The scope of the project involved cleaning and painting the structural steel of the Buckman Bridge over the St. Johns River in Jacksonville, Florida. (State Bridge Numbers 720249 and 720343). The bids were opened and Petitioner was the apparent low bidder on the project with a bid amount of $193,000. The Department of Transportation, on October 2, 1985, rejected all bids "due to error in quantities in plans." According to the contract plans and specifications utilized by the Department of Transportation for the project, the beams, girders, bracing and trusses were composed of 2,540 tons of structural steel. The plans were in error and the tonnage of structural steel was less than 2,540 tons. Petitioner, upon visiting the job site as required, immediately recognized that there was less steel in the bridge than shown in the plans. In submitting and formulating his bid, the Petitioner considered the amount of work and materials which would actually be required to complete the project. 6 Prior to the bids being posted on the project, the Department of Transportation discovered that the amount of structural steel noted in the plans was grossly overestimated. On October 2, 1985, the Department of Transportation notified bidders in writing that all bids submitted on the project were rejected and that the plans would be revised and the project relet.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is, RECOMMENDED that the petition of Industrial Enterprise Sandblast and Painting, Inc., protesting the rejection of all bids on State Project No. 72001- 3448, be dismissed. DONE AND ORDERED this 11th day of December 1985 in Tallahassee, Florida. W. MATTHEW STEVENSON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of December 1985. APPENDIX Respondent's Findings of Fact FINDING RULING Accepted; see Recommended Order paragraph 1. Accepted; see Recommended Order paragraph 2. Accepted, but not included because subordinate. Accepted; see Recommended Order paragraph 4. Accepted; see Recommended Order paragraphs 3 and 6. Accepted; see Recommended Order paragraphs 3 and 6. Accepted; see Recommended Order paragraph 6. COPIES FURNISHED: HONORABLE THOMAS E. DRAWDY, SECRETARY DEPARTMENT OF TRANSPORTATION HAYDON BURNS BUILDING TALLAHASSEE, FLORIDA 32301 A. J. SPALLA, ESQUIRE GENERAL COUNSEL DEPARTMENT OF TRANSPORTATION 562 HAYDON BURNS BUILDING TALLAHASSEE, FLORIDA 32301 LARRY D. SCOTT, ESQUIRE DEPARTMENT OF TRANSPORTATION HAYDON BURNS BUILDING, M.S. 58 TALLAHASSEE, FLORIDA 32301-8064 INDUSTRIAL ENTERPRISE SANDBLAST & PAINTING, INC. P. O. BOX 1547 1502 FOX RUN DRIVE TARPON SPRINGS, FLORIDA 32486-1547
The Issue Whether, in issuing the Revised Recommendation/Tabulation for contracts for Items 1 and 3 for Invitation to Bid No. 15- 048E, Multifunctional Devices, Cost-Per-Copy, Respondent acted contrary to one or more governing statutes, rules, policies, or procurement specifications, or any combination thereof; and if so, for each such instance, whether the misstep was clearly erroneous, arbitrary or capricious, or contrary to competition.
Findings Of Fact On June 3, 2014, SBBC issued ITB No. 15-048E (the ITB) entitled "Multifunctional Devices, Cost-Per-Copy" for the provision and maintenance of copying devices during the contract term. The listed Submittal Requirements were: Manufacturer's Authorization Special Condition 8; Descriptive Literature Special Condition 6; and Material Safety Data Sheets Special Condition 16. A Bidder's Preference Statement was not identified as a Submittal Requirement. Section 4, Paragraph 2, of the ITB was entitled "TERM" and notified bidders that SBBC sought through the award of this bid to "establish a contract for the period beginning from the date of award and continuing through June 30, 2017." The Bid Summary Sheet found at Section 5 of the ITB requested bidders to provide cost-per-copy based on a stated average monthly number of copies, and to extrapolate cost out for 12 months and for 36 months. Page 1 of the ITB contained a certification to be executed by each bidder's authorized representative which stated in pertinent part as follows: Bidder agrees to be bound to any and all specifications, terms and conditions contained in the ITB, and any released Addenda and understand that the following are requirements of this ITB and failure to comply will result in disqualification of bid submitted. All bidders submitted a signed bidder certification. Section 3, Paragraph 1(a), of the General Conditions of the ITB provided as follows: SEALED BID REQUIREMENTS: The "Bidder Acknowledgment Section" must be completed, signed and returned with the bid. The Bid Summary Sheet pages on which the Bidder actually submits a bid, and any pages, upon which information is required to be inserted, must be completed and submitted with the bid. The School Board of Broward County (SBBC) reserves the right to reject any bid that fails to comply with these submittal requirements. BIDDER'S RESPONSIBILITY: It is the responsibility of the Bidder to be certain that all numbered pages of the bid and all attachments thereto are received and all Addendum released are received prior to submitting a bid without regard to how a copy of this ITB was obtained. All bids are subject to the conditions specified herein on the attached bid documents and on any Addenda issued thereto. Section 3, Paragraph 6, of the General Conditions of the ITB provided as follows: AWARDS: In the best interest of SBBC, the Board reserves the right to: 1) withdraw this bid at any time prior to the time and date specified for the bid opening; 2) to reject any or all bids received when there are sound documented business reasons that serve the best interest of SBBC; 3) to accept any item or group of items unless qualified by Bidder; and 4) to acquire additional quantities at prices quoted on this ITB unless additional quantities are not acceptable, in which case, the bid sheets must be noted "BID IS FOR SPECIFIED QUANTITY ONLY." On June 18, 2014, SBBC issued Addendum Number 1 for the ITB which replaced a number of pages within the bidding documents and contained responses to questions posed by prospective bidders. Addendum Number 1 included Question No. 6 in which Xerox inquired whether SBBC "would . . . consider a change to the contract term of the contract to 48 or 60-month term?" SBBC responded through Addendum Number 1 that it had amended the bid "to include additional pricing for 48 or 60-months term[s]," and SBBC continued to request proposals for a 36-month contract term. Addendum Number 1 revised Section 4, Paragraph 2, of the Special Conditions of the ITB to state as follows: TERM: The award of this bid shall establish a contract for the period beginning from the date of award and continuing through an award for a term of 36, 48 or 60 months. Bids will not be considered for a shorter period of time. All prices quoted must be firm throughout the contract period. Items will be ordered on an as needed basis. Addendum Number 1 included an Appendix A–Summary Cost Sheet which required bidders to provide cost-per-copy based on a stated average monthly number of copies, and to extrapolate cost out for 12 months, 36 months, 48 months, and 60 months. On June 20, 2014, SBBC issued Addendum Number 2 for the ITB. The first page of Addendum Number 2 advised prospective bidders, "This Addendum amends the above referenced bid in the following particulars only: 1. DELETE: Appendix A–Cost Summary Sheet INSERT: Revised Appendix A–Cost Summary Sheet." The first page of Addendum Number 2 further cautioned bidders that "[i]t is important to include the REVISED page when submitting your response." Addendum Number 2 went on to provide a Revised- Appendix A-Summary Cost Sheet which stated "A Cost Summary Sheet must be completed for each options [sic] 36 months, 48 months and 60 months" and included a cost summary sheet for each of those three options. The ITB and addenda numbers 1 and 2 were released by SBBC via Onvia DemandStar, with email notices thereof to prospective vendors who subscribed to its bid notification service. Toshiba downloaded the ITB, Addendum Number 1, and at least the first page of Addendum Number 2 from DemandStar prior to the submission of its bid to SBBC. Again, the first page of Addendum Number 2 cautioned bidders that Appendix A–Summary Cost Sheet had been deleted and replaced and that it was "important to include the REVISED page when submitting your response." No bid specifications protest was filed by any person or entity concerning the ITB or addenda numbers 1 or 2. On July 3, 2014, SBBC opened bids timely submitted in response to the ITB by: Toshiba; ImageNet; Innovative; Lexmark International, Inc.; and Ricoh. Konica had also presented a bid to SBBC in the bid opening room prior to the opening of bids but after the announced time for submittal of bids. The Konica bid was delivered to SBBC but was not opened at the time of the bid opening. Toshiba, the incumbent, was the only bidder that violated the pricing requirements of the ITB. The bid submitted by Toshiba utilized the version of Appendix A-Summary Cost Sheet that was released under Addendum Number 1 and only offered cost- per-copy pricing for the 60-month term option. Toshiba's bid did not submit the Revised-Appendix A-Summary Cost Sheet issued under Addendum Number 2, nor did it contain any bids offering cost per copy pricing to SBBC for the 36 or 48-month term options. Although Toshiba's bid was not rejected as non-responsive for failing to bid on the 36 and 48-month term options and for failing to utilize and complete the Revised-Appendix A-Summary Cost Sheet issued under Addendum Number 2, SBBC's staff later concluded in hindsight that it should have been rejected for such non-compliance. Toshiba's bid included a "Pricing" note immediately prior to its Appendix A–Summary Cost Sheet that stated: [Toshiba] is proposing a 60 month CPC as a response to the [ITB]. Based on the fact the [ITB] has no minimum, cancellation for convenience, ability to upgrade and downgrade with no penalty, it is in the best interest of our organization to bid a term of 60 months. This term allows us to provide the most aggressive price to the [SBBC] and maintain the excellent service and support level in place. SBBC's staff recommended that an award be made under the ITB for pricing offered for a 36-month contract term for Items 1, 2, and 3 for a contract period of August 6, 2014, through September 30, 2017. On July 10, 2014, SBBC posted its initial ITB Recommendation/Tabulation which did not consider the Konica bid. The initial posted Recommendation/Tabulation notified bidders of SBBC's intended award of contracts for Items 1 and 2 to ImageNet as the primary awardee and to Innovative as the alternate awardee for a contract period of August 6, 2014, through September 30, 2017, and recommended the award of contracts for Item 3 to Ricoh as primary awardee and to ImageNet as alternate awardee for a contract period of August 6, 2014, through September 30, 2017. Timely bid protests and bid protest bonds were filed by Konica and by Toshiba concerning SBBC's initial Recommendation/Tabulation of July 10, 2014. SBBC's Bid Protest Committee conducted a meeting with the protestors on August 26, 2014, and determined that Konica's bid had been timely submitted and directed SBBC's Procurement and Warehousing Services Department (the Department) to evaluate Konica's bid for responsiveness. It also directed the Department to revise its recommendation on the ITB to reject Toshiba's bid for Item 2 as the device offered by Toshiba for that item did not meet the ITB's specifications which called for a single device capable of performing 95 copies per minute (cpm) and Toshiba instead offered two devices that performed at 85 cpm. After reviewing Konica's bid for responsiveness, SBBC posted a Revised Recommendation/Tabulation for the ITB on August 29, 2014, which (a) recommended award of Item 1 to ImageNet for a term from October 7, 2014, through November 30, 2017, as the primary awardee and to Innovative as the alternate awardee; (b) recommended award of Item 3 to Ricoh for a term from October 7, 2014, through November 30, 2017, as the primary awardee and to ImageNet as the alternate awardee; and (c) recommended the rejection of Toshiba's bid for Item 2 for its failure to meet the specifications for that Item. On September 4, 2014, Toshiba timely filed its notice of intent to protest the August 29, 2014, posted Revised Recommendation/Tabulation. On September 15, 2014, Toshiba timely filed its Amended Formal Petition Protesting Proposed Revised Recommendation/Tabulation. SBBC's Bid Protest Committee conducted a meeting with Toshiba on November 5, 2014, pursuant to section 120.57(3), SBBC Purchasing Policy 3320, and the ITB, and rejected Toshiba's bid protest. On November 10, 2014, Toshiba timely requested that SBBC forward its bid protest to DOAH for a formal hearing. Toshiba has presented a number of arguments in these proceedings seeking to avoid the circumstances Toshiba created for itself when it failed to comply with Addendum Number 2 and violated the ITB's pricing requirements and the ITB's requirement as to the term of the contract to be awarded, when Toshiba only submitted a single bid and restricted the contract term for which it would be considered to 60 months. First, Toshiba attempts to divest SBBC of its express authority to select proposals for any contract duration for which it solicited bids other than for a month term. Second, Toshiba argues that SBBC was somehow obligated to specify within the bid specifications those business considerations that would inform SBBC's selection of the duration of the contract term to be awarded under the ITB. Third, Toshiba argues that ImageNet was non-responsive regarding the ITB's specifications concerning manufacturer's certifications. Toshiba also argues that all bidders, including itself, were non- responsive with regard to the ITB's specifications regarding bidding preference laws. None of the arguments presented by Toshiba in opposition to SBBC's intended award of Items 1 and 3 are persuasive. The Selection of the 36-Month Term SBBC's recommended award for a 36-month contract period from October 7, 2014, through November 30, 2017, is consistent with the terms and conditions of the ITB and its addenda. At the very start of this competitive solicitation, SBBC informed bidders through Section 4, Paragraph 2, of the ITB and the Bid Summary Sheet at Section 5 of the ITB that it was seeking a contract through June 30, 2017-–i.e., a 36-month contract. SBBC also made it clear in its response to Question No. 6 of Addendum Number 1 that "[t]he contract will be for a full 36 months." Although SBBC revised the bid specifications through Addendum Number 1 to allow bidders to submit "additional pricing for 48 and 60 months term[s]," "to allow the School District to consider a 48 and/or 60 months term contract," and revised Section 4, Paragraph 2, of the ITB to provide for "an award for a term of 36, 48 or 60 months," it was clear under the ITB that SBBC contemplated that a 36-month contract could serve its needs. Addendum Number 2 further revised the bid specifications by providing the Revised–Appendix A–Summary Cost Sheet which informed bidders that "a Cost Summary Sheet must be completed for each options [sic] 36 months, 48 months and 60 months." SBBC intended to review the additional pricing offered for 48 and 60- month contract terms to determine whether those particular options were a better business decision for SBBC. Several factors were considered by SBBC in selecting the contract duration for the award under the ITB. The selection of the shorter 36-month contract term was consistent with the expressed terms of the ITB and addenda and the expressed preference of SBBC's governing board to refrain from entering into long-term contracts and enabled SBBC to be flexible in finding solutions to its copying needs and to take advantage of changes that may arise in technology; avoided problems the school district was currently experiencing with a long-term cost-per- copy contract which ranged from equipment performance issues to the long-term placement of technology in schools; and enabled the school district to conduct research to determine whether future implementation of a managed print solution would provide the school district with additional cost savings or financial benefits in contrast to the cost-per-copy services being procured through the ITB. Clearly, this selection was neither arbitrary nor capricious. SBBC's elected governing board has made it known by its actions taken at public meetings that it disfavors long-term contracts for the procurement of goods and services and has gone so far as to reduce the term of contracts from the dais. SBBC's staff determined that the pricing offered to SBBC for a 60-month contract term was not significant enough to recommend a contract longer than the 36-month term SBBC had been requesting since the release of the ITB. Any cost advantages offered by Toshiba's bids for Items 1, 2, and 3 were reduced by $525,000 per year due to the disqualification of its bid for Item 2, which failed to meet the ITB's specifications. Consideration of Managed Print Services Xerox Corporation informed SBBC that a managed print services (MPS) program could save millions of dollars per year and later submitted a no bid response to SBBC regarding the ITB because SBBC was not implementing a MPS program under the ITB. SBBC had also received proposals from vendors in October 2013 concerning a MPS program and concluded that there existed a potential annual savings of millions of dollars if such a program could be implemented. All of which were additional reasonable, rational reasons for SBBC to remain consistent with its decision to award the contracts for a term of 36 months and not something longer. The ITB contains standard terms and conditions which enable SBBC to terminate an awarded contract regardless of reason and with or without cause upon 30 days written notice to the other party. Toshiba wants SBBC to rescue Toshiba from its failure to submit required bids for 36-month and 48-month periods by forcing SBBC to award a contract obligating the agency for a longer duration under the ITB than desired by the agency and then have SBBC terminate the 60-month contract award for convenience after 36 months. SBBC includes termination for convenience provisions within its contracts for goods and services due to section 1011.14, Florida Statutes, which restricts the ability of district school boards to obligate public funds for a period beyond one year. The inclusion of the standard termination for convenience clauses in its ITBs enables SBBC to enter into contracts exceeding one year which affords the school district opportunities to obtain continuity of service and price advantages that would not be available under shorter contracts. While SBBC has the ability under the ITB to terminate contracts for convenience upon 30 days' notice, it rarely does so. SBBC has never exercised its right to terminate its two prior contracts for the services sought under this ITB. Any such termination requires action by SBBC's governing board during a public meeting. SBBC's staff would not engage in the sham of recommending a contract to its governing board for a contract term longer than the period for which it intends to procure services from a vendor. SBBC's procurement staff believes that using the termination for convenience clause in the manner Toshiba recommends can have an adverse effect upon the school district's ability to encourage bidders to participate in its competitive solicitations or to offer it their best pricing. Questions 1 and 59 of Addendum Number 1 of the ITB provide evidence of concern within the bidding marketplace that SBBC might exercise its termination for convenience clauses with regard to the services being procured under the ITB and support the perception of SBBC's that it should avoid a reputation for exercising such termination authority. Toshiba argues that SBBC somehow materially misled bidders through the ITB by stating in response to Question No. 3 concerning MPS of Addendum Number 1 that: The School District is not planning to implement a Managed Print Services at this time. The School District would like to receive Additional information regarding other districts that have implemented a Managed Print Services. There are no evaluation points associated with this ITB. SBBC's responses to Question No. 3 of Addendum Number 1 were accurate and did not mislead bidders. Toshiba is the only bidder to claim to have been misled. Section 6, Paragraph 10, of the ITB requested bidders provide SBBC with information about how the awardee could transition SBBC to a MPS model from the cost-per-copy model being offered under its bid. While SBBC requested such information from vendors within the bidding marketplace, there is no evidence that any bidder's provision or omission of such information within its bid submission was considered in the selection of the recommended awardees. In fact, ImageNet was recommended for award even though it did not provide this ancillary information about transition to a MPS delivery model. Rather, the recommended awardees for a 36-month contract term for Items 1 and 3 were determined solely on the basis of cost submitted for those items by the bidders, all in accordance with the ITB. A MPS program was a possible initiative being considered by SBBC's former Chief Information Officer prior to his departure from SBBC in February 2014, at which time the school district's current cost-per-copy contract was nearing its expiration. Although SBBC still had an interest in the possibility of a MPS program, it was not going in that direction at the time it needed to release a bid for copying services to replace its current expiring contract. Toshiba contends that SBBC was somehow required to disclose to bidders whether the potential future implementation of a MPS program might impact the contract award period that SBBC might choose under the ITB. A myriad of business considerations may inform an agency in selecting the length of its contracts for goods and services, and there is no law or rule that requires an agency to specify those factors within an ITB. Responsiveness of the Bidders Toshiba has attempted to argue that ImageNet, the recommended awardee for Item 1 and the alternate awardee for Item 3, was somehow non-responsive under the ITB and ineligible for award. In support of this argument, Toshiba has referenced Section 4, Paragraph 8, of the Special Conditions of the ITB which state as follows: MANUFACTURER'S CERTIFICATION: Bidder must submit with their ITB a notarized letter from manufacturer certifying that bidder is authorized to sell, service and warrant the multifunctional devices offered within this ITB. Failure of the bidder to provide this letter with their submitted bid or upon request shall result in disqualification of entire bid. If the bidder is the manufacturer, then bidder should state that their company is the manufacturer of the equipment provided in this bid (the letter does not need to be notarized). A bid is only disqualified under Section 4, Paragraph 8, of the ITB if (1) a notarized manufacturer's letter is omitted from the bid; and (2) the bidder fails to comply with a subsequent request from SBBC to provide the letter. No bidder, including Toshiba and ImageNet, included a notarized letter from a manufacturer with its bid. SBBC did not request any of the bidders to submit a notarized manufacturer's letter at any time after the submission of bids. As a result, none of the bids, including that of ImageNet, was non-responsive for a failure to satisfy Paragraph 8 of Section 4 of the ITB. Toshiba has also argued that all bids should be rejected due to Section 3, Paragraph 1(d), of the General Conditions of the ITB which concerns bidders' preference laws and states as follows: d) BIDDING PREFERENCE LAWS: ALL BIDDERS MUST COMPLETE AND SUBMIT THE LEGAL OPINION OF BIDDER'S PREFERENCE FORM IN ORDER TO BE CONSIDERED [sic] FOR AWARD. The State of Florida provides a Bidder's preference for Florida vendors for the purchase of personal property. The local preference is five (5) percent. Bidders outside the State of Florida must have an Attorney, licensed to practice law in the out-of-state jurisdiction, as required by Florida Statute 287.084(2), execute the "Opinion of Out-of-State Bidder's Attorney on Bidding Preferences" form and must submit this form with the submitted bid. Such opinion should permit SBBC's reliance on such attorney's opinion for purposes of complying with Florida Statute 287.084. Florida Bidders must also complete its portion of the form. Failure to submit and execute this form, with the bid, shall result in bid being considered "non-responsive" and bid rejected. No bidder, including Toshiba, included an "Opinion of Out-of-State Bidder's Attorney on Bidding Preferences" form with its bid. Each bidder's omission of that form was for good reason. Section 3, Paragraph 1(d), of the General Conditions of the ITB is a boilerplate provision within SBBC's standard bidding documents that is included pursuant to section 297.084(2), Florida Statutes, for any competitive solicitations in which personal property is to be purchased by SBBC. In instances in which it solicits bids to purchase personal property, SBBC includes a "Bidder's Preference Statement" form and includes that form among the checked "Submittal Requirements" listed in Section 2, Page 1, of the ITB. This ITB did not include a "Bidders Preference Statement" form among the bidding documents or list it as one of the required submittals. The state law and the boilerplate provision at Section 3, Paragraph 1(d), of the General Conditions of the ITB are only applicable to competitive solicitations for the purchase of personal property and do not extend to competitive solicitations for the purchase of services. As Section 4, Paragraph 12, of the Special Conditions of the ITB makes it clear that the multi-functional devices to be provided by the awardee under the ITB will "remain the property of the vendor," the standard bidder's preference provision contained within the ITB is plainly inapplicable to this procurement.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the School Board of Broward County enter a final order that adopts the Findings of Fact and Conclusions of Law contained herein, dismisses the protest filed by Toshiba Business Solutions (USA), Inc., and upholds the awards of contracts under the procurement for a 36-month term from October 7, 2014, through November 30, 2017, to ImageNet Consulting of Miami, Inc., as the primary awardee for Item 1 and to Innovative Software Solution, Inc., as the alternate awardee for Item 1, and to Ricoh USA, Inc., as the primary awardee for Item 3 and to ImageNet Consulting of Miami, Inc., as the alternate awardee for Item 3. DONE AND ENTERED this 15th day of June, 2015, in Tallahassee, Leon County, Florida. S MARY LI CREASY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 15th day of June, 2015. COPIES FURNISHED: Robert Paul Vignola, Esquire Office of the General Counsel Eleventh Floor 600 Southeast Third Avenue Fort Lauderdale, Florida 33301 (eServed) William G. Salim, Jr., Esquire Moskowitz, Mandell, Salim and Simowitz, P.A. 800 Corporate Drive, Suite 500 Fort Lauderdale, Florida 33334 (eServed) Eric J. Rayman, Esquire Genovese, Joblove and Battista, P.A. PNC Center, Suite 1110 200 East Broward Boulevard Fort Lauderdale, Florida 33301 (eServed) Albert E. Dotson, Esquire Wendy Francois, Esquire Bilzin, Sumberg, Baena, Price and Axelrod, LLP 1450 Brickell Avenue, Suite 2300 Miami, Florida 33131 (eServed) Matthew Mears, General Counsel Department of Education Turlington Building, Suite 1244 325 West Gaines Street Tallahassee, Florida 32399-0400 (eServed) Robert W. Runcie, Superintendent Broward County School Board Tenth Floor 600 Southeast Third Avenue Fort Lauderdale, Florida 33301 (eServed) Pam Stewart Commissioner of Education Department of Education Turlington Building, Suite 1514 325 West Gaines Street Tallahassee, Florida 32399-0400 (eServed)
The Issue Whether a bid dispute arising in connection with an emergency bid letting is an appropriate subject for formal administrative proceedings, in the absence of an administrative challenge to the fact of the emergency?
Findings Of Fact The parties stipulated that DOT had "received [Baxter's] notices of protest dated September 23, 1983, October 14, 1983, and December 16, 1983, protesting the Department of Transportation's determination that Baxter's Asphalt was not the lowest responsible bidder on this project and petitioning for formal administrative hearings." Baxter's bid was indeed the apparent low bid on Job No. 53030-3511, but DOT has taken the position that Baxter is not a responsible bidder, and has disregarded Baxter's bid on that account. The DOT has moved beyond proposed action and has actually awarded the contract to Gulf, the second low bidder. The parties stipulated: Pursuant to Section 120.53(5)(c) , Florida Statutes, the Department has decided to proceed with the award and execution of the contract with Gulf Asphalt Corporation in order to avoid what the Department perceived as an immediate and serious danger to the public health, safety, or welfare. DOT executed the contract with Gulf on January 6, 1984. As grounds for executing the contract, notwithstanding the pendency of formal administrative proceedings, the Secretary of the DOT stated: ...The conversion of this two lane roadway to a four lane facility is badly needed to increase the traffic capacity and improve the safety of the highway for the traveling public. This section of roadway has a structural rating of 35 which places it in the "Critical" range . . . [and] has an accident ratio of 1.244 which is almost 25 percent above the average rate. dditional funds were appropriated by the Florida Legislature so that work could proceed without delay. It is also imperative that these projects proceed in an orderly fashion to maximize the effective use of [DOT] construction in spection and supervisory personnel. Letter from Secretary Pappas to Baxter, December 23, 1983. Baxter does not concede that an emergency exists with respect to Job No. 53030- 3511, but did concede that the existence of an emergency was for the agency head to determine, subject only to judicial review. In its petition for formal administrative proceedings, Baxter did not raise the question whether an emergency exists. For purposes of the present administrative proceeding, there is no dispute or issue as to the existence of the emergency.
Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That respondent dismiss petitioner's formal written protest as moot. DONE and ENTERED this 9th day of February, 1984, in Tallahassee, Florida. ROBERT T. BENTON II Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of February, 1984. COPIES FURNISHED: Frank A. Baker, Esquire Roberts and Baker P. O. Box 854 Marianna, Florida 32446 Robert I. Scanlan, Esquire Department of Transportation Haydon Burns Building, MS-58 Tallahassee, Florida 32301 Paul A. Pappas, Secretary Department of Transportation Haydon Burns Building Tallahassee, Florida 32301