WALTERS, J.
In this construction defect case, we interpret the meaning of the contractual term "date of substantial completion" and the statutory term "substantial completion" to decide whether defendants were entitled to summary judgment on the basis that plaintiff's tort claims were barred either by the statute of limitations or by the statute of ultimate repose. We conclude that defendants were not entitled to summary judgment, affirm the decision of the Court of Appeals, reverse the decision of the trial court, and remand to the trial court for further proceedings.
We take the following uncontested facts from the record on summary judgment. Plaintiff Sunset Presbyterian Church contracted with defendant Brockamp & Jaeger to act as its general contractor and build a new church facility. Plaintiff and defendant executed a standard form contract provided by the American Institute of Architects (AIA). Defendant then subcontracted with Anderson Roofing Company (defendant subcontractor) and other subcontractors to perform various specialized construction tasks.
Construction began in 1998. On February 14, 1999, plaintiff held its first services in the church, and on March 14, 1999, held a dedication ceremony. In May 1999, defendant general contractor issued plaintiff a warranty that extended for one year from February 7, 1999, a date that defendant identified as the "substantial completion date." The county issued a certificate of final occupancy on May 28, 1999, but additional work continued during the summer of 1999, and it was not until
In early 2009, plaintiff allegedly discovered extensive water damage in the church, and on March 16, 2009, it filed an action asserting tort claims against defendants. Defendant general contractor filed an affirmative defense alleging that, by the terms of the parties' contract, plaintiff's claims accrued on the "date of substantial completion" and were time-barred. Defendant subcontractor, which was not a party to that contract, filed an affirmative defense alleging that plaintiff's claims were barred by the statute of repose provided in ORS 12.135.
The trial court granted defendants' motions and dismissed the case. The Court of Appeals reversed. Sunset Presbyterian Church v. Brockamp & Jaeger, 254 Or.App. 24, 295 P.3d 62 (2012). Defendants then petitioned for review. This court granted defendants' petitions and, for purpose of oral argument, consolidated this case with a companion case, PIH Beaverton, LLC v. Super One, Inc., 254 Or.App. 486, 294 P.3d 536 (2013). We begin with the issue presented by defendant general contractor and consider whether it was entitled to judgment as a matter of law.
Generally, for purposes of the statute of limitations, tort claims accrue when the plaintiff knows or should know that an injury has occurred. See Rice v. Rabb, 354 Or. 721, 725, 320 P.3d 554 (2014) (holding that discovery rule applies to tort actions referenced in ORS 12.080 and ORS 12.110). Defendant contends that, in this case, the parties altered, by contract, the date on which plaintiff's claims accrued. For purposes of this opinion only, we will assume that the contractual provision on which defendant relies — Paragraph 13.7.1.1 — could have that effect and turn to an analysis of that provision.
Paragraph 13.7.1.1 provides that claims arising from "acts or failures to act occurring prior to the relevant date of Substantial Completion" of the construction "accrue[]" and "any applicable statute of limitations shall commence to run * * * not later than such date of Substantial Completion."
Paragraph 9.8.2 includes steps that the contractor, architect, and owner of the property must take before the architect issues a Certificate of Substantial Completion. First, "[w]hen the Contractor considers that the Work * * * is substantially complete, the Contractor shall prepare and submit to the Architect a comprehensive list of items to be completed or corrected." Then, the architect must perform an "inspection" and thereby determine that the "Work or designated portion thereof is substantially complete." At that point, the architect
Defendant did not include an architect's Certificate of Substantial Completion in the documents that it submitted in support of its motion for summary judgment, nor does it argue that the evidence that it did submit established that such a certificate ever had been issued.
Thus, the parties' arguments focus on different contractual provisions. Defendant argues that plaintiff's claims accrued when construction was "Substantially Complete," as that term is defined in Paragraph 9.8.1 — "the stage in the progress of the Work when the Work * * * is sufficiently complete * * * so the Owner can occupy or utilize the Work for its intended use." Plaintiff contends that, under Paragraph 13.7.1.1, its claims accrued on the date of Substantial Completion and that the "date of substantial completion" is as defined in Paragraph 8.1.3 — when an architect determines that the construction is "substantially complete" and issues a certificate to that effect.
Paragraph 9.8.1 defines "Substantial Completion" as a "stage" in the progress of the work, and Paragraph 8.1.3 defines the "date" of Substantial Completion. The contract does not further define the words "stage" or "date," but the difference in the terms is obvious from their dictionary definitions. The dictionary defines "stage" as "a period or step in a process, activity, or development." Webster's Third New Int'l Dictionary 2219 (unabridged ed 2002). The dictionary defines "date" as "the point of time at
Accordingly, under the terms of the parties' contract, if a contractor were to consider construction fit for occupancy or use on, for example, March 1, any date after March 1 would be a date within the "stage" of Substantial Completion. By the terms of the parties' contract, however, claims do not accrue during the "stage" of Substantial Completion but only on a specific "date of Substantial Completion." Paragraph 13.7.1.1 (emphasis added). Paragraph 8.1.3 defines the "date of Substantial Completion" as one date — the "date certified by the Architect in accordance with Paragraph 9.8." Therefore, in our example, the "date of Substantial Completion" could only be the specific date after March 1 designated by the architect in the Certificate of Substantial Completion.
We therefore agree with plaintiff that evidence that plaintiff occupied and used the property for its intended purpose beginning sometime in February 1999, and at the latest by March 14, 1999, does not establish the date on which plaintiff's claims accrued under Paragraph 13.7.1.1. Under that provision, plaintiff's claims accrued only on the date that the architect issued a Certificate of Substantial Completion.
Defendant's complaints about that result are misdirected. Defendant submits that architects are hired by owners and that there may be many reasons why architects may not issue Certificates of Substantial Completion or may do so inaccurately.
Our decision does not mean, of course, that the construction in this case was never substantially complete — indeed, defendant's work may well have been fully complete at some point in 1999, when final payment was authorized. But without evidence that an architect issued a Certificate of Substantial Completion, defendant cannot rely on Paragraph 13.7.1.1 as establishing the date that plaintiff's claims accrued. Our decision also does not mean that plaintiff had unlimited time within which to bring its action against defendant. Plaintiff was required to bring its action within the statute of limitations or, at the very latest, within the period of ultimate repose provided by ORS 12.135.
We now turn to defendant subcontractor's argument that plaintiff's claims are barred by the statute of ultimate repose provided in ORS 12.135. We address a similar argument in PIH Beaverton v. Super One, Inc., 355 Or. 267, 323 P.3d 961 (2014), also decided today. In that case, we conclude that, in the absence of a written acceptance, the limitations period of ORS 12.135 begins to run on the date on which the contractee accepts the construction as fully complete, as opposed to accepting the construction as "sufficiently complete for its intended use or occupancy." Id. at 284, 323 P.3d 961.
In this case, defendant subcontractor contends that the 10-year limitations period of ORS 12.135 began to run on or before March 14, 1999, when the church held its dedication service. The date of that service is relevant evidence that defendant accepted the construction as fully complete on that date, but that is not the only evidence in the record. Plaintiff offered evidence that construction continued after March 14, that neither the architect nor the owner considered the construction to be complete on that date, and that the county did not issue a certificate of final occupancy until May 28, 1999. Because evidence of the date on which construction was fully complete is contested, the trial court erred in granting summary judgment to defendant subcontractor.
In summary, the trial court erred in granting both defendants' motions for summary judgment.
The decision of the Court of Appeals is affirmed. The judgment of the circuit court is reversed, and the case is remanded to the circuit court for further proceedings.