Elawyers Elawyers
Ohio| Change

Eckington & Soldiers' Home Railway Company of the District of Columbia, Plff. In Err. v. Florence McDevitt, 9 (1903)

Court: Supreme Court of the United States Number: 9 Visitors: 12
Filed: Jan. 21, 1903
Latest Update: Feb. 21, 2020
Summary: 191 U.S. 103 24 S. Ct. 36 48 L. Ed. 112 ECKINGTON & SOLDIERS' HOME RAILWAY COMPANY of the District of Columbia, Plff. in Err. , v. FLORENCE McDEVITT. No. 9. Argued January 21, 1903. Ordered submitted to full bench February 2, 1903. Submitted to full bench March 9, 1903. Decided November 16, 1903. This was an action brought in the supreme court of the District of Columbia, August 8, 1894, to recover damages for alleged breach of contract. Plaintiff, on April 4, 1889, being the owner of a tract of
More

191 U.S. 103

24 S. Ct. 36

48 L. Ed. 112

ECKINGTON & SOLDIERS' HOME RAILWAY COMPANY of the District of Columbia, Plff. in Err.,
v.
FLORENCE McDEVITT.

No. 9.

Argued January 21, 1903.

Ordered submitted to full bench February 2, 1903.

Submitted to full bench March 9, 1903.

Decided November 16, 1903.

This was an action brought in the supreme court of the District of Columbia, August 8, 1894, to recover damages for alleged breach of contract. Plaintiff, on April 4, 1889, being the owner of a tract of land in the District of Columbia, containing about 22 acres (with her husband, since deceased), entered into an agreement with the Eckington & Soldiers' Home Railway Company, which recited: 'Whereas the said parties of the first part, being desirous of securing an extension of the Eckington & Soldiers' Home Railway from the corner of Third and T streets northeast extended, to the east line of Lincoln avenue in the District of Columbia, through and along the following streets, to wit: West on T street to Second street east extended, thence north on the line of said Second street extended to V street extended cast in a right line, and thence west on the line of said V street so extended to the east line of Lincoln avenue; and whereas the said party of the second part has agreed to extend said railway to said Lincoln avenue by the route aforesaid, upon certain conditions hereinafter mentioned;' therefore the McDevitts agreed in consideration of the premises 'and of the covenants hereafter mentioned, to be kept and performed' by the railway company, to sell, grant, and convey to it, its successors and assigns, 'a right of way, 60 feet in width, for the use of the said party of the second part, its successors and assigns forever, through and along the following land belonging to the said Florence McDevitt,' described as 'beginning at the southeast corner of the lands of said Florence McDevitt, adjoining the property of George Truesdell known as Eckington, and in the line of Second street east extended northwardly in a right line, and extending thence with uniform width 30 feet on each side of the center of said Second street extended, to a line 15 feet south of the north line of said V street extended, and thence westerly with the same width on each side of the center of said V street extended, to the east line of Lincoln avenue;' also to pay to the railway company $500 five years from the date of the agreement, with interest, to be evidenced by a promissory note. But that the grant was subject to certain 'conditions' to wit, that work on the extension should be commenced on or before May 1, 1889, and completed on or before October 1, 1889; that the grades should be as described: that the material removed in grading should be delivered on the lands of the McDevitts as directed by them; that the excavation should not exceed 20 feet in width at bottom and 60 feet at top; and that 'after said extension is completed and open for traffic, a car shall be run thereon to Lincoln avenue at least once in thirty minutes between 7.30 A. M. and 6 P. M., and at least once an hour to 9 P. M., and one car at 11 P. M.' The extension was completed in the manner and within the time prescribed, and opened to traffic, and the $500 note was given. On December 27, 1889, a deed was executed and delivered to the company by Mr. and Mrs. McDevitt, in form an indenture, but signed and sealed by the McDevitts alone. This conveyed the right of way to the company, 'its successors and assigns forever,' with covenants of warranty and further assurance, and it also recited a covenant on the company's part that the cars should be run as described in the contract.

The extension was operated from 1889 to May or June, 1893, when the night cars were taken off. Thereupon, and on June 26, 1893, Mrs. McDevitt filed her bill for specific performance, to which the company set up in its answer, among other things, that the extension had always been a source of great loss, especially in operating at night, and that 'the present management of the road, having been advised that their right to operate said extension over the line of proposed streets without authority from Congress was very doubtful, deemed it wise to suspend such operation until the question could be definitely settled.'

July 9, 1894, the bill was dismissed but 'without prejudice to the right of complainant to resort to such remedy at law as she may be advised.' About that time and prior to July 25, 1894, the railway company ceased to operate the extension altogether, and it was testified that the attorney of the company, on its behalf, 'refused to do anything in the way of carrying out the contract.' On the last named day Mrs. McDevitt notified the company in writing, to forthwith remove its tracks from the premises, and that she should bring an action for breach of contract. The tracks were accordingly removed. In the meantime the $500 note had matured and was not paid.

The evidence tended to show that Mrs. McDevitt had caused a map of a proposed subdivision of the land to be made, but that this had not been recorded, and that nothing had been done in the way of preparing the tract for subdivision and sale by grading; that no streets had been opened through it except as effected by the action of the railroad company; that the excavations for the railway tracks were what would be Second and V streets, to which extent plaintiff would be relieved from grading. Evidence was introduced of sales by Mrs. McDevitt of four parcels of the land prior to the removal of the tracks, and tending to show the value of the land with and without the railroad in operation through it. Also that the business depression of 1893 caused declines in value, and rendered real estate in the vicinity of this property unsaleable until after 1894.

Among other instructions the court gave the following:

'The jury are instructed that the measure of damages in this case is the excess (if the jury find from the evidence that there was such excess) in the market value of the land at the time that the defendant ceased entirely to run its cars upon that part of its line which extended to and through the plaintiff's land, with the cars running in accordance with the terms of the contract of the parties in evidence, and the expectation of their continuing to so run in the future, over the market value of the same land at the same time without any cars running on said part of said line, and without any expectation that they would ever run thereon.'

To the giving of which defendant objected and duly preserved an exception.

The jury found a verdict in favor of plaintiff for $15,000, and, motions in arrest and for a new trial having been made and overruled, judgment was entered thereon, which was affirmed by the court of appeals of the District (18 Ohio App. D. C. 497), and this writ of error thereupon sued out.

The railway company was a corporation created by an act of Congress approved June 19, 1888 (25 Stat. at L. 190, chap. 419), 'with authority to construct and lay down a single or double-track railway, with the necessary switches, turnouts, and other mechanical devices and sewer connections necessary to operate the same by horse, cable, or electric power, in the District of Columbia, through and along the following avenues, streets, and highways' (describing them), and also a branch as described. The railway was to be laid in the center of the avenues and streets as near as might be, and, in the event of a change of grade of any of the streets, avenues, or roads occupied, it was made the duty of the company, at its own expense, to change its railroad so as to conform to such new grade. The company was to run cars as often as the public convenience might require, in accordance with a time-table or schedule which was to be approved by the commissioners of the District; and was to construct such ticket offices, passenger rooms, etc., at such points on its line as the Commissioners might approve. The government and direction of the affairs of the company were vested in a board of nine directors, who were to choose officers as designated. Congress reserved the right to alter, amend, or repeal the act at any time.

By an act approved April 30, 1890 (26 Stat. at L. 77, chap. 172), amending the charter, the company was authorized to extend its tracks through and along certain streets named, which provided 'and also beginning at the present terminus of its cemetery branch on the east side of Lincoln avenue, and thence northerly along Lincoln avenue to a point opposite the entrance to Glenwood cemetery.'

By an act approved July 5, 1892 (27 Stat. at L. 65, chap. 143), the charter was further amended by authorizing the extension of tracks, and providing 'that the tracks of this company on Lincoln avenue shall be taken up within thirty days from the passage of this act, and the roadway shall be restored to public uses in such manner as the commissioners of the District of Columbia shall direct.'

Messrs. John Ridont and Walter L. McDermott for plaintiff in error.

[Argument of Counsel from pages 107-109 intentionally omitted]

Messrs. A. S. Worthington, John C. Heald, and Charles L. Frailey for defendant in error.

Statement by Mr. Ch. Justice Fuller:

[Argument of Counsel from pages 109-111 intentionally omitted]

Mr. Chief Justice Fuller delivered the opinion of the court:

1

Assuming that the railway company might have lawfully bound itself to construct and operate this piece of road, the question is presented to what compensation in damages plaintiff below would be entitled if the company found that the traffic did not justify its further maintenance, and ceased to run its cars, or if the public interests required such changes of the lines of the road as rendered the abandonment necessary.

2

Plaintiff had been reinstated in the possession of her land, freed from the encumbrance of the right of way, and had been discharged from the liability to pay the $500. And as the record stands, it is doubtful if any direct specific damage can properly be held to have been made out. At all events, and conceding that she was entitled to substantial damages for any injurious change of condition, any liability incurred, and any gains prevented, to secure which action had been taken, in reliance on the contract, the instruction as to the measure of damages embraced none of these matters, and was confined to profits only.

3

The transaction was not a sale of the land where the difference between the price agreed and the market value would represent the measure of loss or gain. Restitution having been made of what plaintiff had parted with, how far could she demand to be compensated for prevented gains or anticipated profits?

4

The contract did not purport to bind the company to operate its cars over the extension for any designated period, but, considering its terms in relation to the right of way, the trial court held that it was bound in perpetuity, and thereupon that if it ceased to do this in whole or in part at any time, she could order the tracks off her premises, and recover the difference between the value of her land with the cars running and with the expectation that they would continue always to run, and the value without the operation of the cars and with no expectation that they would run in the future.

5

The instruction was addressed to differences in market value as affected by the running of the cars, with the element added of expectation of continuance or cessation for all time. As thus put the supposed difference in market value amounted to anticipated profits, and these were not recoverable if dependent on uncertain and changing contingencies, and not in contemplation of both parties as a probable consequence of breach. Howard v. Stillwell & B. Mfg. Co. 139 U.S. 199, 35 L. ed. 147, 11 Sup. Ct. Rep. 500; Globe Ref. Co. v. Landa Cotton Oil Co. 190 U.S. 540, 47 L. ed. 1171, 23 Sup. Ct. Rep. 754. Whether prevented gains or prospective profits are or are not too uncertain and contingent to be regarded as probable and contemplated consequences is always a question of difficulty, and as in such cases juries are permitted to exercise a wide discretion in the allowance of damages, great care is required in advising them as to the elements proper to be considered in making up their verdicts.

6

In a case like this, gain prevented is a more accurate term that loss of profits. And it is said in Sedgwick on Damages, 8th ed. vol. 1, p. 250, § 173: 'Where an injured party claims compensation for gain prevented, the amount of loss is always to some extent conjectural; for there is no way of proving that what might have been, would have been. Thus, when the claim is made for compensation for a deprivation of property, it may be that if the property had remained in the owner's control it would have brought no gain.'

7

Here the evidence tended to show that a financial depression prevailed at the time of the breach, and that all real estate in the particular locality was unsaleable. Gains, then, were practically impossible; while, on the other hand, there was evidence that some years after the breach the depression passed away and real estate rose in value.

8

The books contain many illustrations of the uncertainties which will or may defeat recovery of anticipated profits.

9

In Rockford, R. I. & St. L. R. Co. v. Beckemeier, 72 Ill. 267, it was held, in a suit against a railroad company for the failure to erect a depot building upon plaintiff's farm, as agreed, that any supposed damage to the farm on that account, growing out of anticipated increased value, was too remote.

10

In Evans v. Cincinnati, S. & M. R. Co. 78 Ala. 341, a railroad company agreed to locate houses for its hands near plaintiff's land, and it was held that possible loss of profits at his store and mill was too speculative.

11

So, in Missouri, K. & T. R. Co. v. Ft. Scott, 15 Kan. 435, where a railroad company failed to perform its agreement to make the city of Fort Scott the terminus of one division of its line, and erect machine shops there, it was held that an inquiry into the value of real estate and amount of business, in order to show what profits would have been made, was improper; but the city might recover for the value of the buildings to it as taxable property.

12

Scholten v. St. Louis & S. F. R. Co. (Mo.) 73 S.W. 915, is so far in point that it may well be cited, though not decided by a court of last resort. There the St. Louis court of appeals held that where a railroad's agreement to build and maintain a switch for a private property owner did not affect the performance of the railroad's duties to the public, the railroad was not entitled to allege in an action for illegally destroying the switch, that the contract was void as against public policy; and that as the plaintiff had graded the right of way and furnished the ties, and the agreement did not specify any length of time for the maintenance of the switch, plaintiff was entitled, on the destruction of the switch, to recover the value of the ties, and the cost of grading.

13

Treating the contract as a simple contract, and the refusal to run the cars as a breach which Mrs. McDevitt could accept as finally determining it, we think she could not recover for deprivation of the speculative gains of a remote future. What might have been made by selling the land at a value enhanced by the operation of the tracks in perpetuity was purely problematical and not naturally in contemplation. And the more so in view of the fact that railroad companies, while private corporations, are quasi-public agencies, engaged in the performance of public duties, and that contracts which prevent them from the discharge of those duties cannot be sustained. It did not follow that the company, because it possessed the power to construct and operate this extension, could contract to operate it forever in so absolute a sense that damages could be awarded for the breach of such a contract, predicated on the expectation of its perpetual operation. Texas & P. R. Co. v. Marshall, 136 U.S. 393, 34 L. ed. 385, 10 Sup. Ct. Rep. 846. Again, in this aspect, the instruction treated the agreement as equivalent to a covenant running with the land, and we are inclined to think that the bearing Mrs. McDevitt's demand that the tracks be removed, and the accepted and complete surrender of the right of way by their removal accordingly, might have had, under all the circumstances, on the question of prospective damages, should not have been excluded from the jury.

14

We are of opinion that the instruction as given was erroneous, and as it was definite and peremptory in its terms, and as it cannot be said that the jury was not influenced, and perhaps controlled, by it, we hold the error fatal to the judgment. As there must be a new trial we refrain from discussing the suggestions in respect of the acceptance of the deed by the company, a subject much considered in Willard v. Wood, 135 U.S. 309, 34 L. ed. 210, 10 Sup. Ct. Rep. 831, 164 U.S. 502, 41 L. ed. 531, 17 Sup. Ct. Rep. 176, and the discharge of the alleged covenant, made below, but not pressed in argument here.

15

Reversed and remanded, with directions to reverse the judgment of the Supreme Court of the District, and order a new trial.

16

Mr. Justice White and Mr. Justice McKenna dissented.

Source:  CourtListener

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer