Findings Of Fact Application No. 7500050 requested water from one (1) withdrawal point. Said withdrawal is for public supply. This application is for an existing use. The center of withdrawals will be located at Latitude 28 degrees 07' 49" North, Longitude 82 degrees 26' 22" West in Hillsborough County, Florida. Total continuous acreage is 59.4 acres. The use is for not more than 29,000,000 gallons of water per year and not more than 91,650 gallons of water during any single day to be drawn from the Floridian Aquifer. Notice was published in a newspaper of general circulation, to-wit: The Tampa Tribune in the issues of May 28 and June 4, 1975, pursuant to Section 373.146, Florida Statutes. Notices of said public hearing were duly sent by certified mail as required by law. The application and map of the premises, the legal description, the receipt of certified nail, the copy of the Notice and the affidavit of publication were received without objection and marked Exhibit 1. Copy of the franchise application to the Health Department regarding the laboratory analysis on the public water supply was introduced into evidence and received without objection and marked Exhibit 2. The parties agreed to file a joint stipulation as follows: The agreement that a flow meter be installed. That monthly readings be submitted to the District staff at the Headquarters office. That applicant supply evidence that the individual lots will be restricted from having private wells. A copy of the joint stipulation was received by the Division of Administrative Hearings on July 14, 1975. Said stipulation encompassed the following: That applicant, Groveland Developments, Inc. install a flow meter of the propeller type on the well; take monthly readings, and send them into the District monthly. Said stipulation did not encompass the third (3rd) condition agreed to at the hearing, to-wit: That evidence would be supplied that individual lots to be developed in conjunction with this application be restricted from having private wells thereon. Witnesses were duly sworn and agreement was reached on each point enumerated as required by Rule 16J-2.11, Rules of the Southwest Florida Water Management District and Chapter 373, Florida Statutes.
Recommendation Grant Application No. 7500050 for a consumptive-us permit for the quantities of water applied for conditioned upon the items enumerated in the joint stipulation and further conditioned upon the submission by the applicant evidence showing that the individual lots will be restricted from having private wells thereon. August 22, 1975 DELPHENE C. STRICKLAND Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: T. Ahern, Esquire Staff Attorney southwest Florida Water Management District Post Office Box 457 Brooksville, Florida 33512 Mr. George Szell, Hydrologist Permit Section Southwest Florida Water Management District Post Office Box 457 Brooksville, Florida 33512 Groveland Developments, Inc. Post Office Box 578 Lutz, Florida 33549 Mr. Frank Ripa Housel & Martinez, Inc. Consulting Engineers and Land Surveyors Post Office Box 9215 Tampa, Florida 33674 Attachment to the Recommended Order STATE OF FLORIDA
The Issue Whether FDOT has provided reasonable assurances that the activities it proposes to conduct pursuant to proposed District SWM Permit Application No. 940606-10, WRM Permit Application No. 940606-2-D and modification to ROW Permit No. 2584 will comply with the relevant permit criteria set forth in Chapters 373 and 403, F.S., and applicable rules and criteria promulgated thereunder.
Findings Of Fact THE PARTIES Petitioner, 1000 Friends of Florida (1000 Friends), is a not-for-profit, tax exempt membership corporation, organized and existing under the laws of the State of Florida. The principal office of 1000 Friends is 926 East Park Avenue, Tallahassee, Florida 32314 and it also maintains an office at 3305 College Avenue, Ft. Lauderdale, Florida 33314. Petitioner, Florida Bay Initiative, Inc. (FBII), is an entity incorporated under the laws of Florida with its principal office located at 250 Australian Avenue South, Suite 500, West Palm Beach, Florida 33401. Petitioner, the Florida Keys Fishing Guides Association, is an association of sport fishing guides who live in the Florida Keys and is headquartered at 138 Royal Lane, Islamorada, Florida 33036. Petitioner, Michael Collins, is a private individual. His address is 138 Royal Lane, Islamorada, Florida 33036. Petitioner, Charles W. Causey, is a private individual. His address is Post Office Box 448, Islamorada, Florida 33036. Petitioner, the Florida Keys Concerned Citizens Coalition (FKCC), is a not-for-profit Florida corporation whose address is West Shore Drive, Big Pine Key, Florida 33043. Petitioner, AG Intus, Inc., filed a Notice of Voluntary Dismissal on August 9, 1996. DOAH Case 95-5524, the proceeding filed by Intus, was previously consolidated with the other cases to this proceeding. On August 12, 1996, the Intus case was severed from this proceeding and the Intus hearing cancelled. Respondent, the South Florida Water Management District (the District or SFWMD), is a public corporation in the State of Florida existing by virtue of Chapter 25270, Laws of Florida, 1949, and operating pursuant to Chapter 373, F.S., and Title 40E, F.A.C., as a multi-purpose water management district, with its principle office in West Palm Beach, Florida. Respondent, the Florida Department of Transportation (FDOT), is an agency of the State of Florida. Its District Six address is 1000 N.W. 111th Avenue, Miami, Florida 33172. Intervenor, Monroe County, is a political subdivision of the State of Florida. For the purposes of this proceeding the address for Monroe County is c/o Apgar and Pelham, 909 East Park Avenue, Tallahassee, Florida 32301. The District, FDOT and Monroe County did not object to the standing of the Petitioners at the formal hearing and represented that they will not object to the standing in the event of an appeal. Based on the representations of the Respondents, the Petitioners were not required to put on a case as to their standing. THE THREE PERMIT APPLICATIONS FDOT has applied to the District for a Wetland Resource Management (WRM) permit, a Surface Water Management (SWM) permit, and a Right of Way (ROW) occupancy permit. On June 6, 1994, the Applicant submitted applications for surface water management and wetland resource management permits for the purpose of widening and modifying this 20.4 mile stretch of U.S. 1. The surface water management permit application is identified as Application No. 940606-10. The wetland resource management permit application is identified as Application No. 940606-2-D. On October 24, 1995, the District issued Staff Reports on Permit Application No. 960606-10 and Permit Application No. 94060-2-D. These Staff Reports recommended issuance of the permits subject to general and special conditions as specified therein. An addendum to the staff report was issued November 3, 1995. On September 27, 1994, the Applicant submitted a request to modify its existing ROW Occupancy Permit to enable it to replace the bridge where U.S. 1 crosses the C-111 Canal. The land encompassed by the ROW occupancy permit challenged in this proceeding is located in Section 16 and 17, Township 59 South, Range 39 East, Dade County, Florida. A draft right-of-way occupancy permit with standard limiting and special conditions was produced as part of a package that went to the Governing Board and others. The proposed authorization for use of the ROW is for the following: REMOVAL OF EXISTING U.S. HIGHWAY 1 BRIDGE AND REPLACEMENT WITH A NEW FIXED BRIDGE. PROJECT INCLUDES CONSTRUCTION OF A NEW SERVICE/ACCESS ROAD, 2 DETENTION PONDS, 2 CATCH BASINS, 2-15" R.C.P. OUTFALLS, BOAT RAMP WITH LOADING DOCK, PARKING AREA, PEDESTRIAN GATE AT S-197, FENCING AND WILDLIFE CROSSING ALL WITHIN THE NORTH AND SOUTH RIGHT OF WAY OF C-111 (STATION 938+00 - 955+00). The draft right-of-way occupancy permit modification, identified as “SFWMD PERMIT NO. MOD 2548," should correctly be identified at “SFWMD PERMIT NO. MOD 2584.” The numbers “8” and “4” were inadvertently transposed. STIPULATIONS AS TO APPLICABLE LAW The parties have accurately set forth the applicable permitting criteria and the appropriate Basis of Review in their prehearing stipulation. CRITERIA FOR ROW PERMIT Rule 40E-6.301, Florida Administrative Code, provides, in pertinent part, as follows: In determining whether an occupancy permit should be issued, the District shall consider whether the proposed activity: interferes with the present or future construction, alteration, operation or maintenance of the works of the District; is consistent with the policy and objectives of Chapter 373 F.S., the legislative declaration of policy contained in Section 373.016, F.S. and the state water policy, Chapter 17-40, F.A.C.; has an actual or potential negative impact upon environmentally sensitive areas, which include: wetlands; endangered or threatened species habitat; aquatic preserves; outstanding Florida waters; federal, state and privately owned parks and wildlife management areas; designated areas of critical state concern; lands purchased by federal, state and local governments for the purpose of environmental protection, water resource protection and esthetics; and lands which contain native terrestrial plant species in significant amounts. Environmentally sensitive areas include areas on and off- site that are affected by activities which occur on, or are initiated from, the District’s works; degrades water quality within the receiving water body or fails to meet the provisions of Ch. 373, F.S., the state water policy, and Ch. 40E, F.A.C.; involves a discharge of wastewater from a new wastewater source or an increased discharge from an existing wastewater source; will discharge debris or aquatic weeds into District lands or works or cause erosion or shoaling within the works of the District; is supported by financial assurances, which will ensure that the proposed activity will be conducted in accordance with Chapter 373, F.S., and Chapter 40E-6, F.A.C.; presents an increased liability risk to the District; meets the general and specific criteria in the Basis of Review which is incorporated by reference in Rule 40E- 6.091, F.A.C.; interferes with actual or potential public use of the District’s works or public, recreational or other facilities not within the District’s works; is consistent with local zoning and other private land uses in the area; interferes with the quality or quantity of a public or private water supply; meets applicable criteria in Chapters 40E-61 and 40E-62, F.A.C.; ROW occupancy permits typically have standard limiting conditions which are incorporated as part of the permit. The permit may also have special limiting conditions. CRITERIA FOR PERMITTING THE SWM SYSTEM Rule 40E-4.301(1), Florida Administrative Code, contains the following criteria that, at the times pertinent to this proceeding, were used by SFWMD in determining whether to permit a surface water management system: In order to obtain or modify a permit under this chapter, an applicant must give reasonable assurances that the surface water system: provides adequate flood protection and drainage, without causing over- drainage, will not cause adverse water quality and quantity impacts on receiving waters and adjacent lands regulated pursuant to Chapter 373, F.S., will not cause discharges which result in any violations, in surface waters of the state, of the standards and criteria of chapter 17-302, F.A.C., will not cause adverse on-site or off-site impacts on surface and groundwater levels and flows, including impacts to sources of water supply and wetland hydrology, will not cause adverse environmental impacts, can be effectively operated and maintained, will not adversely affect public health and safety, is consistent with the State Water Policy, chapter 17-40, F.A.C., for a DRI with a signed Preliminary Development Agreement with the Florida Department of Community Affairs, pursuant to section 380.06(8), F.S., provides a surface water management system for that portion of the site approval for development which is able to operate separately from the surface water management system for the balance of the project site and still meet applicable District criteria. meets any applicable basin criteria in chapter 40E-41, F.A.C., will not otherwise be harmful to the water resources of the District, will not interfere with the legal rights of others as defined in subsection 17-40.401(8), F.A.C., is not against public policy, will meet general and specific criteria in the document described in subsection 40E-4.091(1)(a), F.A.C., (0) will meet criteria for isolated wetlands, which are found in Appendix 7 of the document described in rule 40E- 4.091(1)(a), F.A.C., (p) will meet the criteria for above ground impoundments, which are found in Appendix 6 of the document described in rule 40E-4.091(1)(a), F.A.C. The SFWMD has adopted certain procedures and criteria contained in a document, referred to as “Basis of Review for Surface Water Management Permit Applications Within The South Florida Water Management District” (BOR). Subsection 40E-4.091(1)(a), F.A.C. incorporates this document by reference into Chapter 40E-4, F.A.C. The BOR is a document that is “described in subsection 40E-4.091(1)(a), F.A.C.,” within the meaning of Rule 40E-4.301(1), F.A.C. The BOR establishes a rebuttable presumption that water quality criteria are met through specified volumetric retention and detention requirements. These performance based criteria are designed to be flexible. CRITERIA FOR THE WRM PERMIT In 1992 DEP entered into an Operating Agreement with the District, which delegated to the District responsibility for issuing wetland resource management (WRM) permits, which are required for dredge and fill activities in wetlands. Both DEP and the District implement the same wetland resource permit and MSSW permit rules. The District agrees with DEP's interpretation and application of the WRM permitting rules and non-rule policy, and applies the same when issuing such permits. Section 403.918, Florida Statutes (1991), provides the pertinent criteria that must be applied by the District in determining whether to grant or deny the WRM permit. That criteria requires the applicant to provide reasonable assurance that water quality standards will not be violated. In addition, for projects in OFW, the applicant must provide reasonable assurance that the project is clearly in the public interest. THE PUBLIC INTEREST TEST The District is required to balance the following criteria, found at Section 403.918(2)(a), Florida Statutes (1991), in determining whether a project is clearly within the public interest: Whether the project will adversely affect the public health, safety, or welfare or the property of others; Whether the project will adversely affect the conservation of fish and wildlife, including endangered species, or their habitats; Whether the project will adversely affect navigation or the flow of water or cause harmful erosion or shoaling; Whether the project will adversely affect the fishing or recreational values or marine productivity in the vicinity of the project; Whether the project will be of a temporary or permanent nature; Whether the project will adversely affect or will enhance significant historical and archaeological resources under the provisions of s.267.061; and The current condition and relative value of functions being performed by areas affected by the proposed activity. MITIGATION If the applicant is unable to otherwise meet the public interest test, the District shall, pursuant to Section 403.918(2)(b), Florida Statutes, “consider measures proposed by or acceptable to the applicant to mitigate adverse effects which may be caused by the project . . .” The District thereafter re-evaluates the project to determine whether the project, as mitigated, meets the public interest test. The criteria for mitigation is found in Chapters 373 and 403, Florida Statutes, Title 40 E (including the Basis of Review) and Rule 62-312, Florida Administrative Code. Rule 62-312.330, Florida Administrative Code, states the general criteria for evaluating mitigation proposals as follows: The goal of the mitigation proposal shall be to offset the expected adverse impact of the project that have resulted in the project being deemed unpermittable such that the resulting project with mitigation is not contrary to the public interest or, in the case of Outstanding Florida Waters, is clearly in the public interest. Each project must be separately evaluated to determine whether the proposed mitigation is sufficient. Rule 62-312.340, Florida Administrative Code, provides guidelines that are to be used in evaluating proposed mitigation projects. GENERAL DESCRIPTION OF THE PROJECT AREA FDOT proposes to widen a 20.4 mile portion of U.S. 1 in southern Dade County and northern Monroe County. Approximately seven miles of the project area is in Monroe County and approximately thirteen miles is in Dade County. The northern terminus of the project is the intersection of U.S. 1 and Card Sound Road, which is located in Dade County south of Florida City. The southern terminus of the project is the intersection of U.S. 1 and Abaco Road on Key Largo in Monroe County. The corridor of the proposed project passes through Sections 6, 7, 16, 18, 21, 27, 28, Township 59 South, Range 39 East; Sections 24, 25, 36, Township 58 South, Range 38 East; Sections 16, 19, 30, 31, Township 58 South, Range 39 East, Sections 16, 30, 31, Township 60 South, Range 40 East; Sections 25, 26, Township 60 South, Ranges 39 East, Dade and Monroe Counties, Florida. U.S. 1 is the main highway between northern Monroe County and southern Dade County. The only other road between Monroe County and Dade County is Card Sound Road. The Florida Keys is designated as an Area of Critical State Concern, pursuant to Section 380.0552, Florida Statutes. The Dade County portion of the road, north of the C- 111 canal, lies within typical Everglades habitat, which is classified as environmentally protected lands of Dade County. Most of the project corridor in Dade County is part of or adjacent to the Everglades National Park. Valuable wetlands exist throughout the project corridor. The following bodies of water will receive discharges if the surface water management system is permitted: C-111 Canal, Jewfish Creek, Lake Surprise, Blackwater Sound, Barnes Sound, Little Blackwater Sound, Long Sound, Manatee Bay, Sarge Lake, andManatee Creek. The receiving bodies of water are Outstanding Florida Waters (OFWs) or are connected to OFWs. THE EXISTING ROADWAY As it presently exists in the project area, U.S. 1 is a two lane undivided highway with two passing zones that are each one mile in length. Each travel lane on the existing facility is twelve feet wide. The existing shoulder on either side of the road consists of four feet of pavement and six feet of grassed area. FDOT Exhibit 7 accurately depicts the existing roadway typical section. Exotic vegetation, generally limited to the areas immediately adjacent to the highway, exist throughout the project corridor. These exotic species are present because FDOT has failed to properly maintain its right of way. A clear zone is an unobstructed area that includes the shoulder of the roadway and typically extends beyond the shoulder. The purpose of the clear zone is to provide a driver who has lost control of his or her vehicle a sufficient clear recovery area to regain control of the vehicle so that it can be maneuvered back onto the road. The clear zone for the existing road is inadequate to provide a safe recovery area. There is at present a two lane bridge over Manatee Creek, a two-lane bridge crossing the C-111 Canal, a bascule bridge, which is a drawbridge, over Jewfish Creek, and a two lane causeway through Lake Surprise. The two existing passing zones are located in Dade County. The first is south of U.S. 1’s intersection with the C-111 canal between mile markers 113-115. The second passing lane is approximately four miles south of the northern terminus of the project between mile markers 120-122. Each existing passing zone is undivided and consists of two northbound lanes and two southbound lanes, with each travel lane being twelve feet in width. The shoulders in the passing zones are the same as for the typical section. A surface water management (SWM) system is defined by Rule 40E-4.021(5), Florida Administrative Code , as being "the collection of devices, improvements or natural systems whereby surface waters are controlled, impounded, or obstructed.". There is no surface water management system presently associated with the road. The roadbed is elevated approximately five feet above mean sea level according to the National Geodetic Vertical Datum and was constructed on the old railroad bed of the Florida East Coast Railroad. No hydrologic culverts have been placed within the roadbed. Consequently, surface water flow between the eastern and western sides of the road north of the C-111 Canal has been cut off. C-109 AND C-111 CANALS In the 1960's, the C-109 and C-111 canals were constructed as part of an overall water management system in the area. As a result of the roadbed and the canals, water has been impounded on the western side of U.S. 1 at a level higher than on the eastern side. Due to cutoff of waterflow by the roadbed embankment, historic freshwater flow between the eastern and western sides of the project area has been restricted, which has resulted in an adverse impact on the Everglades ecosystem north of the C-111 Canal. The restricted water flow has resulted in less fresh water being available for shorter periods of time. Consequently, aquatic life has had reduced opportunities to develop. The restricted flow also has impeded the ability of aquatic life to reach freshwater areas during times of drought. On the east side of the road marine conditions have displaced what naturally should be freshwater conditions. PROJECT HISTORY While FDOT has been aware of traffic safety and hurricane evacuations concerns on the roadway for a long time, the current project originated in 1986 when Monroe County identified this project as a need in its 1986 Comprehensive Plan. Pursuant to agency practice, the proposed project was incorporated into FDOT's five year work program and a study was performed pursuant to FDOT’s Project Development and Environment (PD&E) Manual. FDOT's PD&E manual describes the process by which FDOT determines whether to construct or improve a road. The PD&E process includes an Environmental Impact Statement (EIS) to analyze existing conditions, assess the need for improvement, and develop alternatives. A Draft EIS is performed and circulated for comment to governmental agencies and the public. Based upon comments and further review a Final EIS is prepared. Metric Engineering ("Metric") began the PD&E study of the project in 1988 pursuant to a contract with FDOT. Metric identified seven factors which it concluded supported the need for the project. First, the improved corridor would improve the linkage between the four lane road at the northern terminus and the four lane road at the southern terminus. Second, the project would improve navigation by replacing the existing bascule bridge at Jewfish Creek. Third, the project would improve the level of service for the road. Fourth, the project would improve the safety of the road. Fifth, the project would improve the clearance time for hurricane evacuation. Sixth, the project was consistent with the long range transportation plans adopted by Monroe County. Seventh, the project would accommodate increased traffic, which can be expected with or without the project. Based on the needs evaluation, Metric performed a corridor analysis to determine the best way to get from Florida City to Key Largo, including improving only Card Sound Road, improving only U.S. 1, or improving a combination of the two. Metric concluded that the best resolution was to improve the project corridor. Metric also analyzed various alternatives in an effort to reduce the size of the typical section of the roadway in the U.S. 1 corridor and thereby minimize environmental impacts of the project. Because of concerns from Everglades National Park that no aspects of the project construction occur within its boundaries, FDOT agreed to conduct all construction east of FDOT's existing right of way line. The conclusions of the Metric studies were memorialized in a Final EIS and Final Engineering Report published in 1992. Conclusions regarding alternatives and project needs were then incorporated into the permit application and have continued to be updated. The 1992 version of the project was for a four lane roadway with four lane bridges throughout the project corridor. Subsequent to its June 6, 1994, permit applications to the District for a four lane roadway, FDOT went through an extensive process of providing the District with additional information in an effort to provide the District with the necessary reasonable assurance that the proposed project would comply with the permit criteria. The final series of modifications contained the three lane alternative, which will be described in detail below and is now the subject of this proceeding. The three lane proposal is a compromise that FDOT agreed to in an effort to minimize the direct, secondary, and cumulative impacts of the project. Monroe County passed Resolution No. 315-1995 on September 7, 1995, asking FDOT to build a three-lane road on a four-lane embankment. This resolution provided, in part, that “. . . Monroe County finds that the '3-lane alternative' as described in the Statement of Agency Commitments is the most viable proposal of those considered, because it balances the needs for a widened highway with safeguards designed to address secondary impacts.” The secondary impacts referred to in the resolution included concerns that two southbound lanes would result in more growth. The rationale behind the resolution was that more growth would result from two southbound lanes than from one southbound lane with the proposed passing zones. In response to the request of Monroe County and in response to a similar request made by the District, FDOT notified the District by letter dated September 5, 1996 of FDOT's decision to redesign the project to change the roadway from four to three lanes. FDOT HAS MINIMIZED THE IMPACTS OF THE PROJECT During the PD&E process prior to permit application FDOT studied project needs and alternative alignments, and conducted corridor analyses. FDOT originally considered a proposal that included approximately 250 acres of wetlands impacts. At the District's suggestion, FDOT revised its proposal prior to the permit application to reduce the wetland impacts and project footprint. The application submitted contained approximately 165 acres of impact. FDOT changed the typical section of the proposed roadway again after substantial interagency coordination in an effort to reduce wetlands impacts even further. FDOT agreed to reduce the footprint by changing the design of the median from 22 feet and a Jersey barrier (which is a minimum barrier) to 20 feet with a tri-beam rail barrier. The more substantial barrier was added because the median was narrowed. Additionally, instead of ten-foot paved shoulders on each side of the median, FDOT would use two-foot paved shoulders with sixteen feet of grass in the middle. These minimization efforts resulted in a wetland impacts decrease from 164 acres to 149.07 acres, the current impact of the project. Avoidance, or choosing alternate routes to avoid impacts to wetlands, was not a possible option because only wetlands and open waters exist between the northern and southern terminus of the project. FDOT explored all reasonable alternatives to the proposed project, including a two lane alternative proposed by a consultant for FBII. As discussed below, FDOT did not adopt the two-lane alternative, because the alternative did not address all of FDOT's identified needs for the project. FBII prepared a report with a two-lane alternative to the proposed project. FBII's original proposal included one 12-foot northbound lane with a 10-foot paved shoulder covered with thermoplastic rumble strips to deter vehicular use of the shoulder. In the southbound direction, FBII proposed a 12-foot travel lane with a 4-foot paved shoulder, essentially the same as currently exists. That proposal was analyzed by Metric Engineering on behalf of FDOT. FDOT rejected the FBII alternative for several reasons. First, though the 10-foot northbound shoulder theoretically may be used by cars during hurricane evacuation, removal of the rumble strips would be impractical due to lack of time to do so under threat of a hurricane, and due to the costs involved. It would be unrealistic to require people to otherwise drive over the rumble strips, without removal, because they are designed to prevent such access. Using the 10-foot shoulder during an evacuation would result in there being no shoulder area to remove accident vehicles from the roadway which would otherwise threaten to restrict the flow of traffic or cease it altogether. The reduced width of the shoulder lane below the standard 12-foot lane would also decrease the flow of evacuees. FBII's proposal for a two-lane fixed-height bridge at Jewfish Creek would not completely eliminate rear-end collisions at the bridge. The two-lane alternative proposed by FBII is not a signed and sealed cross section. The proposal by FBII does not include the area necessary for a SWM system or for clear zones. FBII did not do an analysis to determine whether its proposal complies with pertinent FDOT roadway and traffic design standards or with pertinent highway safety and improvement standards. The FBII proposal does not account for removal of the Lake Surprise causeway or construction related impacts from barge traffic. FBII did not do a wetlands survey to determine the impact of its two-lane proposal. At the Final Hearing, Petitioners presented for the first time a new proposal to use "flexible diverters" to pave a third northbound lane and to block that lane from travel traffic with poles. However, no research was conducted into the feasibility of such a proposal, nor was it adequately thought out. Such a use of "flexible diverters" is unprecedented in FDOT's history, is impractical to implement, and would violate FDOT's design standards contained in its Manual on Uniform Traffic Control Devices. Petitioners also presented for the first time at the Final Hearing a proposal to add an 8 to 10 foot paved northbound shoulder which could be converted to a travel lane with traffic control cones in the event of an evacuation. This plan is also not feasible, because the resulting lanes would not be wide enough to safely accommodate evacuating traffic, and because the contradiction between existing road striping and the placement of cones would likely cause accidents, which would halt evacuation. The proposals submitted by FBII do not sufficiently improve hurricane evacuation or traffic safety and, consequently, are not acceptable alternatives to the project. FDOT can do nothing else to minimize the impacts of the project and still address the needs for the project. Minimization of wetlands impacts was accomplished to the greatest extent possible. FDOT has proposed mitigation to offset the impacts that could not be avoided. THE PROPOSED PROJECT - IN GENERAL STIPULATION AS TO DESIGN AND CONSTRUCTION Petitioners stipulated that the design and construction specifications of the roadway proposed to be permitted in this case comply with all applicable design and construction standards for structural integrity, and adequately describe the three-lane divided roadway proposed to be constructed on a four-lane roadbed/embankment. PROPOSED LANES, SHOULDERS, AND MEDIAN FDOT proposes to widen the roadway in the project area to a three lane divided roadway with two northbound lanes and one southbound lane, plus three passing zones. The proposed project will be constructed on a four lane roadbed embankment. FDOT does not presently have plans to add the fourth lane to this roadway. FDOT Exhibit 8 contains an accurate description of the proposed typical section of the roadway. The typical section will consist of two twelve-foot northbound lanes with a six-foot paved shoulder and a four foot stabilized area adjacent to the paved shoulder; a twenty-foot median consisting of a two-foot paved shoulder, sixteen feet of grass and a tri-beam guardrail in the middle as a separator; and one twelve-foot southbound lane with an eight-foot paved shoulder. The proposed typical section also includes a storm water management system that will be described in more detail below. The proposed typical section includes a clear zone thirty feet in width, which is adequate. THE THREE PASSING ZONES The existing passing zone located in Dade County between mile markers 113 and 115 is one mile in length. FDOT proposes to alter this passing zone to 1.44 miles in length. The existing passing zone located in Dade County between mile markers 120 and 122 is also one mile in length. FDOT proposes to alter this passing zone to 2 miles in length. In addition, FDOT proposes to construct a 1.5 mile long passing zone between mile markers 110 and 112 in Monroe County. If permitted, the proposed project will include 2 passing zones in Dade County and 1 passing zone in Monroe County, for a total of 3 passing zones. The total length of the passing zones will equal 4.94 miles. ELEVATION There are no plans to change the elevation of the existing roadway. HYDROLOGIC CULVERTS The project contemplates the construction of 25 hydrologic culverts north of the C-111 Canal. These culverts will remain capped until further hydrological studies are completed and input from all concerned regulatory agencies can be obtained. It has not yet been determined how these culverts will be utilized to maximize the improvement to the ecosystem north of the C-111 Canal. WILDLIFE CROSSINGS INCLUDING THE C-111 BRIDGE The project contemplates the construction of three wildlife crossings north of the C-111 Canal in Dade County with fencing designed to funnel wildlife through the crossing. These crossing, sometimes referred to in the record as “panther crossings” are located between mile markers 118-119, 122-123, and 126-127 and will be constructed as overland bridges. In addition, the replacement bridge over the C-111 Canal (located between mile markers 116-117 in Dade County) is intended to serve as a wildlife crossing and will also employ fencing to funnel wildlife through the crossing. All four of these structures will be constructed as four-lane bridges, but will be striped for three lanes with rumble strips on the southbound fourth lane to discourage vehicular traffic in that lane. There will be an eight foot outside shoulder. FDOT proposes to construct 18 culverts south of the C-111 Canal for crossings by crocodiles, alligators, manatees, and other wildlife. These crossings will consist of 15 box culverts and 3 bridges. MANATEE CREEK BRIDGE The proposed bridge at Manatee Creek would be constructed as a four lane bridge, but would be striped for three lanes with rumble strips on the southbound fourth lane to discourage vehicular travel in that lane. There would be an eight foot outside shoulder. BRIDGING JEWFISH CREEK AND LAKE SURPRISE Jewfish Creek, which is part of the Intracoastal Waterway, and Lake Surprise would be bridged by a continuous structure. The Jewfish Creek bascule bridge would be replaced by a high-level four-lane fixed bridge. The Lake Surprise causeway would be replaced by a low-level four-lane bridge. The total distance for this bridging is approximately 2.35 miles. AREA OF PROJECT THAT WILL BE OPERATED WITH FOUR-LANES The three passing lanes (4.94 miles) and the bridge over Jewfish Creek and Lake Surprise (2.35 miles) would be operated with four lanes. Those areas total 7.29 miles of the 20.4 mile project corridor. Approximately 43 percent of the proposed roadway would have four lanes of pavement. Excluding the areas where the fourth lane will be blocked from travel with rumble strips, only 35 percent of the completed project will contain four travel lanes. This area consists of the three passing zones and the bridges over Jewfish Creek and Lake Surprise. THE PROPOSED SWM SYSTEM The proposed project would provide for a SWM system consisting of inlets, culverts, swales, berms and dry/wet retention areas. For the typical roadway section, runoff from the paved roadway surfaces will be directed to roadside swales designed to provide retention for 50 percent of 2.5 inches times the impervious area. The SWM system for the bridges will collect runoff in inlets and culverts and direct it to either swales or dry or wet retention ponds. The berms of the SWM system provide additional protection by restricting spills of pollutants, such as petroleum from overturned tankers or other vehicle accidents, from running into the surrounding waters. The berms and swales of the SWM are designed to catch pollutants and prevent their discharge into the surrounding waters. FDOT Exhibit 18 consists of four separate drainage reports submitted to the District in 1995 in connection with the project, one report for each section of the project. The reports accurately document the drainage calculations, the drainage design, the rationale behind the drainage design, and compliance of the design with the laws and regulations of the permitting agencies for the original four-lane proposal. On or about September 5, 1995, FDOT submitted revised drainage calculations to the District, determining the amount of stormwater treatment for the three-lane project. The revised calculations established that at least 95% percent of all stormwater runoff from the project would be captured in the proposed SWM system. Because the swale design was based on the originally proposed four-lane road, retention will be in excess of the required volume for most sections of the roadway. The required retention volume for this project is approximately 166 percent of what is required by the BOR. The surface and subsurface geology of the roadway consists of Miami oolite limestone overlain with Perrine maral. Underlying this is Thompson formation, anastasia and Key Largo limestone. Based on these constituencies, the swales proposed by the SWM system would be effective in rapidly removing heavy metals and phosphorous. The revised calculations established that approximately five percent of the project area will not have a SWM system. These areas will not have a SWM system because properly-sized retention systems in those areas can not be constructed without causing a disproportionate, adverse impact to surrounding wetlands. FDOT has provided reasonable assurances that the proposed SWM system’s total water quality treatment exceeds the District's permitting requirements and provides sufficient treatment to exceed the BOR requirements. The water discharged from the proposed system would be of higher quality than that currently discharged, which is not treated. FDOT has provided reasonable assurances that the proposed SWM system complies with the permitting criteria found in Rule 40E.301(1)(a)-(p), Florida Administrative Code. The following findings are made as to that criteria. Rule 40E-4.301(1)(a), F.A.C. The parties stipulated that Rule 40E-4.301(1)(a), F.A.C., pertaining to flood protection and the adequacy of drainage, is not at issue in this proceeding. Rule 40E-4.301(1)(b), F.A.C. The quality of water being discharged from the SWM system will be of substantially higher quality than the existing discharges. Consequently, it is concluded that the system will not cause adverse water quality impacts within the meaning of Rule 40E-4.301(1)(b), F.A.C. In addition, the evidence established that there will likely be less water discharged from the roadway if the project is constructed because of the amounts of water that will likely be retained in the swales that are a part of the SWM systems. Rule 40E-4.301(1)(c), F.A.C. Because the receiving bodies of water are designated Outstanding Florida Waters, the District is required to apply the DEP's most stringent water quality requirements -- the antidegredation requirements for discharge to OFWs, to this project. Those standards will be discussed in more detail below. The evidence established that the proposed project will not violate those requirements. Rule 40E-4.301(1)(d), F.A.C. Impacts to sources of water are not at issue. The District reviewed the potential effect of the SWM system upon on-site and off-site impacts to surface or groundwater levels and flows. The evidence supports the District's conclusion that no adverse impacts will be caused. Petitioners failed to present any evidence on groundwater levels and flows. Consequently, it is found that the criteria found at Rule 40E-4.301(1)(d), F.A.C., has been satisfied. The 25 hydrologic culverts north of C-111 have the potential to re-establish historic surface water flow in the area. They were sized, based on rainstorm events, to help equalize water levels from one side of the road to the other. The culverts are capable of transferring water from west to east to assist in the historic restoration of flows. In order to assure the proper usage of the culverts, they will remain gated until the District develops a management plan in conjunction with other agencies. The District will determine the maintenance entity. The FKAA water main runs beneath this section of the road. As a result, there is no other more hydrologically efficient alternative for the placement of the culverts. The culverts would also provide a means for overwash from storm events, over the U.S. 1 roadbed, to flow back to its point of origin, stabilizing the roadbed and allowing release of the accumulated salt water. Rule 40E-4.301(1)(e), F.A.C. In addition to providing for a net improvement in water quality, the project will offset any adverse impacts through mitigation and other environmental enhancements for which no mitigation credits are being assigned, as described below. Rule 40E-4.301(1)(f), F.A.C. FDOT has a history of adequate maintenance of SWM systems, and has provided reasonable assurance that it has the staff and budget to comply with District operation and maintenance requirements. FDOT will also be able to comply with the District's requirements to control exotic plants and other foliage along project corridor. Rule 40E-4.301(1)(g), F.A.C. The SWM system will not adversely affect public health and safety. The dispute as to the public interest test focused more on the WRM permitting requirements. Findings as to the public interest test are discussed in more detail below. Rule 40E-4.301(1)(h), F.A.C. The evidence established that the SFM system is consistent with State Water Policy. Rule 40E-4.301(1)(i), F.A.C. This project does not pertain to a DRI and, consequently, this criteria is not applicable. Rule 40E-4.301(1)(j), F.A.C. There are no basin criteria applicable to this project. Rule 40E-4.301(1)(k), F.A.C. The evidence established that the SWM system will not be harmful to the water resources of the District. While there will be adverse environmental impacts caused by the project, those adverse impacts have, as will be discussed in more detail below, adequately offset by mitigation. Rule 40E-4.301(1)(l), F.A.C. This issue was not at issue in this proceeding. Rule 40E-4.301(1)(m), F.A.C. As will be discussed in greater detail in a subsequent section of this Recommended Order, the project is not against public policy. For the reasons set forth in that subsequent section, it is found that the project is clearly in the public interest. Rule 40E-4.301(1)(n), F.A.C. Rule 40E-4.091(1)(a), F.A.C., constitutes the BOR. As discussed in detail above, the SWM system complies with the BOR. Rule 40E-4.301(1)(o), F.A.C. There are no isolated wetlands pertaining to this project. Rule 40E-4.301(1)(p), F.A.C. There are no above ground impoundments, as described in Appendix 6 of the BOR, pertaining to this project. WATER QUALITY - DISCHARGES INTO OFW Because the project will involve discharges into Outstanding Florida Waters, it was necessary for FDOT to establish that the discharges from the SFW system will not degrade those OFWs. The evidence established that FDOT's proposed project complies with and exceeds applicable water quality standards and permitting criteria. There will be no significant degradation of ambient water quality as a result of the project. It is expected that there will be a net improvement in ambient water quality resulting from the proposed project, as opposed to the continued degradation if nothing is done to treat stormwater runoff. In FDOT Exhibit 46, FDOT provided baseline water quality data in the form of STORET data for waters adjacent to the project area. STORET is a centralized repository and database for water quality data throughout Florida. It is Florida's principal source of water quality data. STORET contains the best scientific database on water quality in Florida. The STORET data set forth in FDOT Exhibit 46 provided sufficient evidence on ambient water quality for the waters adjacent to the proposed project. In addition to providing the water quality data in FDOT Exhibit 46, FDOT is required by Special Permit Condition 37 to submit appropriate water quality data in the surrounding waters prior to any construction activities. SFWMD Exhibits 5 and 6 contain amendments to Proposed Agency Action made after the beginning of the formal hearing. These amendments include a requirement that an appropriate water quality monitoring plan be submitted within 30 days of the permit issuance. FDOT has provided reasonable assurances that water quality standards will be met and that there will be appropriate water quality monitoring during construction. DIRECT IMPACTS OF THE PROJECT The proposed roadway design will result in the following direct impacts to wetlands adjacent to the roadway corridor: 1) the dredging of 11,028 cubic yards of material from 2.1 acres, 2) the placement of 1,689,553 cubic yards over 147.0 acres of wetlands, and 3) 6.9 acres of (potential) permanent impact due to shading and 4.1 acres (potential) of temporary impacts from the Jewfish Creek Bridge construction activities to seagrass habitat. In order to determine the project's direct impacts, the area surrounding the project was surveyed to determine the number of affected acres. This was done by using a computer aided design ("CAD") system, and by categorizing the various forms of wetlands and associated flora and fauna into the following communities: mangrove, emergent freshwater, open water, and tidal, consisting of seagrass and non-vegetated bottoms. Using these categories and the CAD system, every square foot of direct impacts were accounted for. The adverse direct wetland and surface water impacts of this project are as follows: 1) 27.83 acres Non- Vegetated Tidal Bottom; 2) 11.27 acres Seagrasses; 3) 46.85 acres Mangroves; 4) 42.35 acres Sawgrass/Cattail/Spikerush; 5) 14.31 acres Shrub Wetlands; and 6) 6.46 acres Open Fresh Water; totaling 149.07 acres. Though some wetlands to be impacted may be of lesser quality, FDOT stipulated that all wetlands to be directly impacted by the project should be considered to be high quality wetlands for the purpose of mitigating the impacts. The impacted wetlands are part of larger wetland systems. Petitioners assert that the District should have required studies as to impacts as to the larger wetland systems. The evidence established that the District appropriately considered the type and location of the wetlands involved so that additional study suggested by Petitioners was unnecessary. Petitioners also assert that impacts to isolated wetlands should have been studied. The evidence established that there will be no such impacts. SECONDARY AND CUMULATIVE IMPACTS RECOGNIZED BY SFWMD In addition to the direct impacts of the project, the District is required to analyze secondary and cumulative impacts. A project's secondary impacts are those that, though outside of the project footprint, are very closely linked and causally related to the project. This is a "but for" test. Secondary impacts are those impacts which, if not for the proposed project, would not occur. Both positive and negative secondary impacts are considered. When there are both positive and negative secondary impacts caused by a project, the permitting agency must consider the severity of the impacts and balance these together with the other factors in the public interest test to determine whether or not the project is clearly in the public interest. WRM statutes, and DEP rules and policies pertaining to those statutes do not regulate growth or traffic increases, per se. Only if such increases are very closely linked and causally related to the project will they be considered. The District identified several secondary impacts that would be temporary in nature since they would occur while the project is being constructed. One is the use of a barge facility, primarily at Jewfish Creek, where the anchoring of the barge may result in temporary impacts to seagrass during construction. This impact is addressed by a component of the seagrass mitigation at Boca Chica, discussed below. Another impact is turbidity associated with the dredge and fill and the barge activities. That issue is appropriately addressed by permit conditions, through the use of turbidity control screens and other techniques. The District also identified secondary impacts directly associated with the project footprint that would be permanent in nature. The removal of the exotic vegetation potentially opens up the areas adjacent to the road north of the C-111 canal to off-road vehicles or four-wheel driving and the potential impacts caused by those vehicles. That impact is appropriately addressed by fencing north of the C-111 canal. When a road is widened, animals have a greater distance to travel back and forth from one side of the road to the other. A wider road exposes such animals to greater risk of being hit by a motor vehicle while crossing the road. That impact is addressed in this project by the fencing, the wildlife crossings, and the wildlife box culverts. The crossings are designed for large mammals and some species, such as the Indigo snake, will likely not use these crossings. The wildlife crossings will not entirely mimic the crossing patterns of all wildlife that need to cross U.S. 1 and will result in some wildlife habitat fragmentation. The fencing that will be erected to funnel wildlife through the crossings will fragment the habitat of some species by altering wildlife crossing patterns and blocking access of some species to certain areas of habitat. The greater weight of the evidence established that any habitat fragmentation should, when compared to existing conditions, be minimal. The District appropriately evaluated the advantages and disadvantages of using wildlife crossing and hydrological culverts and appropriately concluded that there would be a net benefit to wildlife as a result of their construction. The District properly concluded that the culverts, bridges and fencing located south of the C-111 canal, construction of wildlife crossings and fencing north of the C- 111 canal, construction of the hydrologic culverts, and removal of the Lake Surprise Causeway are positive secondary benefits of the project. These benefits should be considered when applying the public interest test. THE FKAA PIPELINE RELOCATION The project requires the relocation of two segments of the existing pipe owned by the Florida Keys Aqueduct Authority (FKAA) around Jewfish Creek Bridge. The segments total approximately 1.5 miles. The District inspected the area where the pipeline will be relocated to assist in determining its impact. The pipeline relocation is a temporary disturbance during construction. It is a small linear facility, which will not generate pollution in and of itself. The pipeline relocation is not expected to result in a violation of State water quality standards. The FKAA is responsible for obtaining the necessary permits for the relocation. Direct impacts to wetlands will occur in a 4 to 5 foot wide strip along the length of the relocated aqueduct. The FKAA has submitted a permit application to the DEP for a permit to relocate the aqueduct. DEP believes that adequate mitigation can be achieved to make the project permittable. Once the FKAA submits an adequate mitigation plan, then relocation of the aqueduct will not be an adverse secondary impact caused by the U.S. 1 project. The permit for the subject project should contain a condition that the FKAA obtain a permit for the relocation of these two segments of its pipeline. THE C-111 BOAT RAMP There is an existing boat ramp designed for small boats to access District canals that is located on the north side of the C-111 canal. As a result of the proposed project, it will be relocated to the southern side of the project. This relocation is a relatively minor project requiring a cut in the canal bank and a fourteen-foot wide slab for the boat ramp. When the District considered the potential impacts associated with this relocation in conjunction with the impact of the proposed project, it was determined to be a relatively insignificant impact in terms of the project as a whole. Relocation of the boat ramp is not expected to result in a violation of state water quality standards. All direct, cumulative, and secondary impacts, whether positive or negative, should be considered in balancing the public interest test. ARE THERE ADDITIONAL SECONDARY AND CUMULATIVE IMPACTS Petitioners assert that there are additional cumulative and secondary impacts that the District failed to consider. Petitioners argue that the project cannot meet permitting criteria if those additional impacts are considered. The additional impacts pertain to additional development throughout Monroe County because of the “rate of growth ordinance” (ROGO), additional development along the project corridor, impacts to the coral reefs of the Keys, impacts to Key Deer, generalized impacts, and impacts from increased number of “day trippers." For the reasons discussed below, it is found that the District has considered all appropriate direct, secondary, and cumulative impacts of the project. The additional impacts that Petitioners assert should have been considered are not causally connected or directly linked to the project. THE RATE OF GROWTH ORDINANCE Monroe County adopted its Year 2010 Comprehensive Plan (the "Plan") to meet the requirements of Chapter 163, F.S. The Plan, adopted May 15, 1993, is unusual in that the County limits future growth based on a carrying capacity analysis of its hurricane evacuation clearance time. No other jurisdiction in Florida, and few others in the United States, have used a carrying capacity planning approach. To implement the carrying capacity limitation, Monroe County determined the total number of dwelling units that could be permitted while maintaining an acceptable hurricane evacuation clearance time of 24 hours. This number of dwelling units, less an allowance for vested development and development in municipalities, was the basis for a ROGO that was adopted by the County in 1992. The ROGO allocates the available units at a uniform annual rate of growth (currently, 255 units per year). The ROGO regulates all proposed new residential buildings, including hotels, motels, and other transient tourist accommodations as well as permanent residences. The number of building permits that Monroe County can issue is, at present, directly related to how rapidly the County can be evacuated in the event of a hurricane. The lower the clearance time, the greater the number of permits that can be issued. The Comprehensive Plan requires that the County be able to evacuate within a 24-hour period. As of March 7, 1995, the hurricane evacuation time for Monroe County was determined to be 21.25 hours.1 The project is expected to reduce by six or seven hours the modeled hurricane evacuation capacity for Monroe County, regardless of whether it consists of three or four lanes. This is because both the three lane and four lane plans provide for two northbound lanes. Because of the rate of growth provisions in county law, this reduction of clearance times results directly in an increase in the number of building permits that the county can issue annually. Under ROGO, Monroe County can, with this project, issue 255 permits each year through the year 2026. Without this project, Monroe County can issue 255 permits each year only through the year 2001. Alternatively, without this project, the county can issue 88 permits each year through the year 2010 if it chooses to issue permits over a longer period of time. Following extensive litigation before the Division of Administrative Hearings in an unrelated proceeding2, the Administration Commission entered a final order on December 12, 1995, that approved approximately 97 percent of the Plan. In addition, the Administration Commission has published a proposed rule to bring the remainder of the Plan into compliance and assure its financial feasibility. The central feature of the proposed rule is a five- year work program, with annual reviews by the Administration Commission. It is likely that the proposed rule will eventually result in the complete revision of the ROGO. The proposed rule provides that Monroe County's annual rate of growth be revised within five years, no later than December 31, 2001, "to establish a rate of growth and a set of development standards that ensure that any and all new development does not exceed the capacity of the county's environment and marine systems." A carrying capacity study will comprehensively assess water quality, habitat protection, and public facility issues to determine the capacity of the Keys to sustain further development. The proposed project is but one of many factors that will be considered in future rate of growth regulations. If the expected revisions occur, it would be speculative to predict what development would be allowed. While the studies are underway the rate of growth will remain at 255 units per year. The rate of growth will be reviewed annually, and may be reduced a minimum of 20% if the goals of the studies are not being met. The DCA has determined that Monroe County’s Comprehensive Plan and its land development regulations are sufficient to prevent or mitigate any potential adverse secondary impacts of the project caused by development. The DCA has consistently supported the proposed project, even in its earlier four-lane configuration, because it was consistent with Monroe County's 1986 Comprehensive Plan, and because the project would improve hurricane evacuation clearance times and improve water quality in the vicinity of the roadway. The 1986 plan supported widening of the roadway to four lanes based on projected travel demand. The DCA prefers the current, three-lane proposal to the earlier four-lane. On September 7, 1995, the Monroe County Commission adopted Resolution 315-1995 in support of the proposed project because "it balances the needs for a widened highway with safeguards designed to address secondary impacts." Lorenzo Aghemo, an expert in comprehensive planning, served as Monroe County Planning Director during the development of the Plan and ROGO. In Mr. Aghemo's opinion, the widening of the roadway to either three or four lanes would generate minimal growth pressure in Monroe County, particularly because the Plan limits the rate of growth. Because the Keys are designated by Section 380.0552, F.S., as an area of critical state concern, the DCA is charged with oversight of Monroe County's Comprehensive Plan, its LDRs, and all development that takes place in Monroe County. Additionally, the Administration Commission may amend Monroe County's plan or regulations by rule (See Section 380.0552(9), F.S.). There is virtually no action that Monroe County can take related to the use of land without review and approval of a state agency. The Administration Commission’s proposed rule demonstrates its intent to revise comprehensively Monroe County's ROGO within five years to ensure that future development does not exceed the capacity of the Keys' environmental resources. It also demonstrates the Administration Commission's intention to closely monitor growth and development in the Keys during the five-year study period. Some of the studies required by the proposed rule are already underway: 1) the DCA has entered into a contract with the ACOE to complete the environmental carrying capacity study; 2) the HRS study of advanced on-site waste water treatment systems is underway; 3) Monroe County is developing the required Marathon central sewer facilities plan; and 4) Monroe County and HRS have begun the cesspit identification and elimination process. Caution should be exercised in relying on this or on any other proposed rule. Likewise, caution should be exercised in relying on changes to ROGO that may or may not occur. It is likely that the present status of the law will be changed in the near future so that future development will be based on environmental carrying capacity as opposed to hurricane evacuation clearance times. However, for the purposes of this proceeding the District should accept the fact that the issuance of future building permits is closely linked and causally related to the project. Consequently, it is found that under the present status of the law, the issuance of additional building permits in Monroe County is closely linked or causally related to the project. MONROE COUNTY LDRS AND DCA OVERSIGHT Although Petitioners established that there is a causal relation between the project and the existing status of the law governing the number of building permits that can issued in the future, the evidence was insufficient to establish at a level above speculation that adverse environmental impacts will result because of the issuance of those building permits. The Monroe County Comprehensive Plan contains land development regulations that govern all development in Monroe County. These regulations are among the most stringent in the State and are designed to avoid or minimize adverse environmental impacts caused by development. All development orders in Monroe County are closely scrutinized by the Department of Community Affairs to ensure compliance with applicable permitting criteria. Those regulations and the DCA’s close scrutiny are intervening factors that break any causal relation between the project and the speculative adverse environmental impacts that the Petitioners assert will be caused by future issuance of building permits by Monroe County. Petitioners failed to establish that the impacts of future development are very closely linked or causally related to the project. Consequently, it is found that such impacts are not secondary or cumulative impacts of the project. DEVELOPMENT ALONG THE PROJECT CORRIDOR A major portion of the area next to the road has little or no development potential because it is either water, land in public ownership, or land slated for public ownership. The areas east of the road are mostly in private ownership, but are primarily submerged lands and mangrove areas. The Crocodile Lakes National Wildlife Refuge is federally owned and is managed by the U.S. Fish and Wildlife Service (USFWS). The Southern Glades lands, located immediately west of the project and Everglades National Park (ENP) in Dade County, have been acquired by the District and are managed by the Florida Game and Freshwater fish Commission (FGFWFC). The Model Lands Basin in Dade County is in private ownership but proposed for public acquisition in the future. The land adjoining the roadway in Dade County is designated as open area or environmentally sensitive. Almost half of the land along Monroe County's portion of the roadway is in public ownership. At least 90% of the land in private ownership is mangroves or wetlands that cannot be developed. The small area of uplands is currently being used by a resort marina which will not be allowed to develop further under the new comprehensive plan. There is very little potential for future development in the project area. The comprehensive plan designation for areas in Dade County are open space, and the ones in Monroe County have the conservation designation. The District's regulatory programs consider areas adjacent to the project as sensitive wetland habitats. Based on the District's regulatory authority and comprehensive plan designation for those lands, which would have to be obtained prior to obtaining a permit for development, it is very unlikely that those lands could be developed. Florida Rock and Sand Co. (FRS) has a permit to mine approximately 1,100 acres of wetlands. As part of its mitigation program, FRS will donate this land to the District once its mining and mitigation projects are complete. The FRS mitigation lands are preserved as a permit condition and will ultimately be transferred to the District. This land will not be developed. In addition, the District established that the U.S. 1 project and the FRS project do not constitute a cumulative impact that the District failed to consider. The evidence established that development along the project corridor will not be a secondary or cumulative impact of the project. IMPACTS ON CORAL REEF SYSTEM The evidence was insufficient to establish a close link or causal connection between the project and the coral reef system. As reflected elsewhere, it is found that there will be no degradation of ambient water quality as a result of the project. Therefore, there is no need to resolve the conflicting testimony as to the present status of the coral reef system. IMPACT ON KEY DEER There are no key deer in the project area. The nearest key deer habitat, Big Pine Key, is approximately 70 miles from the southern terminus of the project. The evidence is insufficient to establish that there is a very closely linked and causally related connection between the project and key deer mortality on Big Pine Key. GENERALIZED IMPACTS The Petitioners presented certain opinion testimony that the Keys cannot be developed in an environmentally sensitive manner because of potential adverse impacts of new development in Monroe County, or new boats operating in the waters of the Florida Keys. The credibility of that testimony need not be evaluated because the evidence was not sufficient to tie those generalized concerns into the specific regulatory criteria of the permitting agency. There was insufficient evidence to establish that those alleged impacts would be very closely linked or causally related to the proposed project. DAY TRIPPERS Induced demand is new travel that occurs solely because additional capacity is added to a highway. Petitioners' transportation experts, Michael Replogle and Robert Morris, testified that FDOT's traffic studies, and FDOT's projected rate of traffic growth of approximately 3 percent annually, are incorrect because the studies do not predict the amount of "induced demand" that would result from the proposed project. Petitioners assert that induced demand would generate an unknown number of people who drive to the Keys for the day from south Dade County, referred to as “day trippers,” will have an impact on the Keys that has not been evaluated. The assertion that this potential impact has not been analyzed is rejected as being contrary to the greater weight of the evidence. Induced demand is accounted for in Monroe County's Long Range Transportation Plan, which was never evaluated by Mr. Replogle or Mr. Morris. The Long Range Transportation Plan was prepared by an experienced traffic engineering consulting firm, Barton-Aschman, using an FDOT- approved traffic demand model, the FSUTMS model, that includes all traffic generators and attractors, and all travel on U.S. 1 on weekdays and weekends. The FSUTMS model does not restrict demand based on the existing road capacity. The model uses an "unrestrained assignment" that incorporates the total predicted trip generation on recreational facilities, hotels, and all other attractors. The Long Range Traffic Plan was used to develop the Monroe County Comprehensive Plan, which takes into consideration the projected increases in traffic and makes appropriate provisions for those increases. FDOT has provided reasonable assurances that it has properly projected the amount of traffic for the project corridor after the project is completed and that the projected increases have been appropriately addressed by Monroe County's Comprehensive Plan. MITIGATION - IN GENERAL For the reasons discussed above, it is found that there are no secondary or cumulative impacts that the District failed to consider. Petitioners also contend that the mitigation proposal is insufficient to offset the direct and secondary impacts recognized by the District. This is a large dredge and fill project that will permanently fill 149 acres of wetlands. The wetlands that will be adversely impacted by the project include OFWs that provide a great variety of functions and serve as habitat for fish and wildlife, including threatened and endangered species. The wetlands are unique and of high quality. Mitigation for direct, secondary and cumulative impacts was considered as part of the permit evaluation. In- kind mitigation is considered to be most effective, but out- of-kind mitigation may be offered by the applicant where it is impractical to conduct in-kind mitigation due to historic changes in the project area or sensitivity of the habitat type for which mitigation is offered. Such mitigation is also appropriate to address regional alteration of an ecosystem, such as the Everglades ecosystem alteration caused by the original roadway embankment. FDOT developed a conceptual mitigation plan that took into account project impacts on the freshwater, marine and estuarine components of the ecosystems involved, as well as the impacts on threatened and endangered species of wildlife which may be affected by the project. FDOT coordinated the plan's development with the National Parks Service, U.S. Fish and Wildlife Service, the Army Corps of Engineers, the National Marine Fisheries Service, the U.S. Environmental Protection Agency, the Dade County Department of Environmental Resources Management, the Florida Game and Fresh Water Fish Commission, and the Florida Department of Environmental Protection. The conceptual mitigation plan evolved as a result of project modifications and agency comments into what is now proposed as mitigation for the project. The current proposal is summarized in FDOT Exhibit 26, consisting of Attachment H to FDOT's SWM and WRM permit applications. The timing of their construction falls into two general categories: mitigation previously permitted and concurrent mitigation. UPFRONT MITIGATION Typically, mitigation is done concurrently with project construction rather than prior to permit issuance. Mitigation is often done afterwards because of construction timing constraints. Here, FDOT applied for and, in May 1994 received, permits to conduct mitigation prior to applying for the permits at issue, with the understanding that performance of these activities does not require the District to issue permits for the proposed projects. A total of 385.22 acres of mitigation has already been completed. The applicant received 203.02 mitigation credits from the District on May 12, 1994, for several mitigation projects that the applicant proposes to apply to the proposed U.S. 1 widening project provided it is approved. Table 2 of Attachment H to FDOT Exhibit 26 sets forth the four mitigation projects that constitutes the up- front portion of the mitigation for the project. This table sets forth the acres mitigated, the conversion factor for the mitigation, and the resulting mitigation credit awarded. The four mitigation activities already authorized are: enhancement of the wetland habitat in the Harrison Tract located adjacent to Barnes Sound within the Crocodile Lakes National Wildlife Refuge on the north end of Key Largo (70.37 acres credit for 252.6 acres of restoration); removal of the spoil mounds on the eastern bank of the C-111 canal east of U.S. 1 located on the District’s ROW (10.65 acres credit); the back filling of the C-109 canal levee located on the District ROW within the Southern Glades Save Our River project (112.7 acres credit); and the removal of the roadside spoil mounds on the west side of U.S. 1 located between C-111 and the Dade Work Camp Road within the District’s Southern Glades Save Our Rivers Project (9.30 acres credit). The mitigation projects pertaining to the roadside spoil removal along U.S. 1, the backfill of the C-109 Canal, and the removal of spoil along the C-111 Canal are similar projects because they each involve existing deep ditches cut through wetlands. When these deep ditches were cut, the spoil material from the ditch was deposited alongside the ditch. This resulted in areas that were previously Everglades wetlands becoming spoil, supporting the growth of exotic species and, for the most part, not exhibiting wetland functions. FDOT is proceeding with the backfilling the C-109 canal located between mile markers 122.5 and 117, and removal of the corresponding spoil mounds created during construction of the C-109 canal. In connection with this mitigation, marsh areas, tree islands and deep water aquatic refugia have been restored. In this area, there has been considerable attraction of wildlife subsequent to restoration, including otters, alligators, and turtles, which could not previously use the habitat because the canal was too deep. Upon completion waterflow between the east and the west will be restored, and the area will be restored to a wetland habitat from its current uplands habitat type. Backfilling of the C-109 canal is part of an interagency effort with the ACOE to restore as closely as possible to natural conditions the flow of water in the C-111 watershed area. C-111 mitigation includes removal of roadside spoil along the C-111 canal to restore the natural condition of the area. The mitigation was devised in coordination with the National Maine Fisheries Service (NMFS), which required mitigation for non-vegetated habitat types. Restoration also includes preserving some spoil areas as islands to maintain habitat for endangered species of plants. When the C-111 spoil mounds are scraped down, the fill will not fill the whole ditch. The ditch will, therefore, be a bit more valuable but will not be completely restored to its former elevation. FDOT will also remove roadside spoil along the west side of U.S. 1, upon which exotic species of plants had grown, and returning the area to its original grade. The Harrison Tract is a known habitat and nesting area for American crocodiles. Its wetlands functions were altered or eliminated by prior development of the land by its original owners. Restoration includes regrading the area to restore its original wetlands functions, including habitat for young and adult crocodiles. FDOT's mitigation of the Harrison Tract also includes restoration of tidal flushing to increase contributions of nutrients and food sources to the surrounding tidal bay system. Crocodiles have been observed using the restored areas. FDOT has installed additional nesting berm habitat, basking habitat and shallow lagoon habitat to promote juvenile crocodile development. The District established that the credit awarded for this mitigation and the conversion ratios utilized for determining this credit were consistent with agency practice and its pertinent rules. FDOT was given a 1:1 credit ratio for areas involving full restoration of wetlands. In other portions of the Harrison Tract mitigation involving restoration of flushing to existing wetlands, FDOT was given not full credit, but credit based on the severity of limitation of the existing wetland functions. Based on this evaluation, mitigation credits were given in a range of a 3:1 ratio for restoration of severely disrupted or non-existent wetlands to a 20:1 ration for restoration of higher quality but not fully functional wetlands. FDOT is being awarded 70 mitigation credits for the 252 acres in the Harrison Tract that are being restored or enhanced. CONCURRENT MITIGATION Based on the mitigation ratios developed by the District, additional mitigation credits were required. Consequently, the project contemplates mitigation that will be undertaken concurrently with the construction of the project in addition to the upfront mitigation. FDOT proposes to earn these additional credits by projects involving creation and/or restoration of emergent vegetation, mangrove and seagrass habitats. FDOT’s proposal to mitigate mangrove impacts with "out of kind" mitigation of emergent vegetation habitats was viewed by the District as being necessary and appropriate because there were no sufficiently large areas of mangrove habitat suitable for restoration. Table 7 of Attachment H to FDOT Exhibit 26 sets forth the four mitigation projects that constitutes the concurrent portion of the mitigation for the project. This table sets forth the acres mitigated, the conversion factor for the mitigation, and the resulting mitigation credit awarded. In addition, the table references certain credit for the placement of the hydrological culverts. As will be discussed later, that credit was withdrawn at the formal hearing. The four mitigation activities that will constitute the concurrent portion of the mitigation plan are: the removal of the Lake Surprise causeway (2.90 acres credit); the scrape down of the Jewfish Bridge approaches (0.67 acres credit); the restoration of the FGFWFC road (10.34 acres credit); and the Boca Chica project (27.17 acres credit) The Lake Surprise Causeway removal mitigation involves 5.26 acres of on-site seagrass restoration and 0.54 acres of unvegetated bottom mitigation through the excavation of 52,220 cubic yards of material. Lake Surprise historically was a shallow tidal lake supporting seagrasses before a causeway was built across the lake over the seagrasses. FDOT proposes to remove the causeway and restore the previous elevation, after which it is anticipated that seagrasses that grow on the east side of the causeway will fully recruit naturally to the excavated area. Removing the Lake Surprise Causeway will establish 5.26 acres of seagrass, for which FDOT received 2.63 acres of on-site mitigation credit based on a 2:1 ratio. Through natural recruitment after removal of the causeway, there is a high likelihood that the entire 5.26 acres will recolonize with seagrass. FDOT minimized the seagrass impacts to the greatest extent possible. The mitigation credit pertaining to Lake Surprise does not include credit for the removal of the causeway itself. This awarded credit is for the restoration of seagrass areas. The mitigation pertaining to the Jewfish Creek Bridge approaches proposes the scrape down of 1.33 acres of existing fill to allow the area to become recolonized with mangroves. Boca Chica is located in southern Monroe County over one hundred miles from the southern terminus of the project. This site was chosen by FDOT as a site for seagrass mitigation project after FDOT reviewed several other potential sites. Two other sites were rejected. The area around the C- 111 canal was rejected because the land proposed for use was in private ownership. Several defunct marinas in Port Bougainville were rejected due to poor conditions not conducive to seagrass growth. Boca Chica was finally chosen as the site because it was a large enough area with light and hydrological flow conditions conducive to seagrass growth. The evidence establishes that the Boca Chica site is the most viable for seagrass mitigation. The seagrasses to be impacted at Lake Surprise are healthy and productive turtle grass, manatee grass and cuban shoalgrass. Turtle grass is considered an extremely valuable “climax community” of seagrasses which hold sediments in place, cleanse water quality, and forms the base of the food chain. It is valuable to sea turtles, manatees and recreationally important fish and shellfish. The cuban shoalgrass that will colonize at Boca Chica is a pioneer colonizer species that grows in disturbed areas. It is not as valuable to the marine system as turtle grass. The Boca Chica seagrass mitigation permit condition proposed to offset impacts to 11.27 acres of seagrass. This will involve the removal of 306 cubic yards of sediment and hydraulically dredging approximately 1,175 cubic yards of spoil material. The proposed permit conditions state that FDOT shall provide future maintenance of the culvert areas to maintain adequate flushing. FDOT will plant 25.92 acres of seagrasses to mitigate for the remaining 8.64 acres of impacts, for a mitigation ratio of 3:1. In addition, 8.46 acres of seagrass will be planted to mitigate for the barren bottom area that will be affected, and 1.62 additional acres will be planted to compensate for any unexpected impacts to Boca Chica based on the necessary improvements. Overall, there will be of 36 acres of seagrass mitigation by FDOT, for which FDOT is receiving 27.17 acres credit. FDOT will also increase the water flow between the east and west lagoons of Boca Chica, and maintain the culverts connecting the two sides, in order to further promote growth of seagrass therein. FDOT is responsible for 80% survival of each acre of seagrass mitigation, as well as monitoring once a year for five years. Based on historical data obtained from Boca Chica during past mitigation efforts, there is a high likelihood that the entire 36 acres of mitigation will survive, and that the remaining 74 acres of the Boca Chica lagoons will experience natural recruitment of seagrass as a result of FDOT's efforts. The FGFWFC access area was built by excavating a ditch, and putting fill on the wetlands and creating a dirt road bed. After the C-109 canal is backfilled, the access road will no longer be needed. The mitigation project will excavate the existing road bed, back fill it into the ditch, thereby recreating the wetlands that were there previously. FDOT will receive 10.34 mitigation credits based on a 1:1 ratio of acres restored. EVALUATION OF MITIGATION There is no mitigation in this permit for any wetland impact beyond the direct loss of the specific 149 acres that will be dredged or filled. Mitigation was provided only for the direct, footprint impacts of the project. None of the up front mitigation involves the creation of wetlands, which entails converting areas that were not previously wetlands or open water and turning them into wetlands. It will likely take between 20 and 50 years for the mitigation areas to achieve full functional value required by the South Florida Water Management District mitigation permit. In the interim, there will be a net loss of wetland functional value. With time, the proposed mitigation has a high likelihood of success. Based on FDOT's past successes in mitigation of construction-related impacts, FDOT is able to comply with permit conditions relating to best management practices associated with the construction of bridges and pilings and turbidity screens around road construction, as well as restoration of seagrasses and mangroves. Petitioners assert that the District erred in determining the credit to be given for the up-front portion of the mitigation. While it is true that the SFWMD Rules do not mention "up-front" mitigation, the District has the authority to consider all aspects of a mitigation project in weighing its relative value. Consulting engineering inspectors have been retained by FDOT to insure that all permitting requirements are met during mitigation and construction, and that the technical special provisions for protection of threatened and endangered species are complied with by FDOT. The proposed permits contain appropriate conditions that require FDOT to monitor and maintain the mitigation areas. FDOT will be responsible in perpetuity for maintaining the tidal flushing connection at the Boca Chica mitigation site. Special permit condition 6 to the SWM and WRM staff reports require wetland and upland monitoring. If wetland and upland monitoring or other information demonstrate that additional adverse impacts have occurred due to this project, FDOT would be required to offset the loss of any additional wetland impacts. MITIGATION IS APPROPRIATE The evidence established that the mitigation projects were fairly and appropriately reviewed by SFWMD and that the mitigation credits were fairly and appropriately awarded. The evidence also established that there is appropriate mitigation for the direct, secondary, and cumulative impacts of this project. ACTIVITIES NOT RECEIVING MITIGATION CREDIT Mitigation credits for the 25 hydrologic culverts north of C-111 were originally included in the permit staff reports. Those mitigation credits were removed in an addendum to the staff reports, introduced as District's Exhibits 5 and 6. These credits were not necessary to offset project impacts. After the staff report was issued, they became a point of contention by the Petitioners because they will not be utilized until a management plan is developed. Since they were not necessary to meet mitigation requirements, the credits were removed from this project. These credits were never included in the mitigation ratios for these permit applications. The addendum removed the 9.6 credits initially contemplated for the culverts. No credit has been awarded for the relocation of threatened and endangered species of plants, such as Joewood and Bay Cedar by FDOT from the C-111, C-109 and roadside spoil mitigation areas. These species have been relocated to tree islands constructed by FDOT on the mitigation sites, or to other areas that would not be impacted by the project. FDOT also was not given mitigation credits for: (1) the wildlife crossings and the fencing that will funnel wildlife through these crossings; (2) installation of pipe culverts north of the C-111 canal and bridges and box culverts south of C-111; and which, in addition to providing a corridor for aquatic species, will increase the tidal flushing of the area; (3) the removal of the Lake Surprise Causeway, which will restore historical hydrological flow between the eastern and western sides of Lake Surprise; (4) FDOT's commitment to improve and maintain the flushing of the west lagoon culverts in Boca Chica (mitigation is in the east lagoon); and (5) FDOT's contribution of $300,000 to assist Monroe County in performing a carrying capacity study for the County. Additionally, FDOT will preserve the Jewfish Creek Bridge abutment, which will be preserved for local historical purposes. FDOT will prepare the Jewfish Creek Bridge pilings for an artificial reef at Long Key during construction. THE PUBLIC INTEREST TEST It is appropriate for the SWFMD to consider, in balancing the public interest test, to consider traffic safety and hurricane evacuation.3 Because of FDOT's expertise in those areas, it is appropriate for the permitting agency to give great weight to highway safety concerns, including hurricane evacuation, presented by FDOT. The application of the public interest test does not involve consideration of non-environmental factors other than those expressly set forth in the statutes such as navigation or preservation of historical or archaeological resources. Specifically, aesthetics, quality of life, the potential for a project to cause increased crime, and school overcrowding are not properly considered within any of the seven factors contained in Section 403.918(2)(a), Florida Statutes (1991). The District concluded that the project is clearly in the public interest based upon consideration and balancing of the following factors: hurricane evacuation improvements, public safety improvements, a SWM system where no SWM system currently exists; wildlife crossings and fencing north of the C-111 canal where no such crossings or fencing currently exist; wildlife box culverts to accommodate crocodiles, alligators, manatees and marine life where no such culverts currently exist; and hydrologic culverts, which have the potential to assist in the restoration of hydrologic flows, and the mitigation projects, both upfront and concurrent. SECTION 403.918(2)(a), FLORIDA STATUTES Section 403.918(2)(a), Florida Statutes, requires the permitting agency to determine “[w]hether the project will adversely affect the public health, safety, or welfare or the property of others." The property of others is not at issue. As discussed below, the evidence clearly established that the project will greatly enhance the safety of the road during normal operations and facilitate evacuation in the event of a hurricane. There will be clear benefits to the public safety as a result of this project. As part of the PD&E process, FDOT, through Metric, prepared "A Safety Evaluation" of the existing roadway. The safety analysis was based on FDOT accident statistics for the years 1983-1988, as well as engineering review of the conditions causing the accidents. Specifically, FDOT based their safety analysis on the following: 1) calculation of the abnormally high accident rate on the roadway based on the rate quality control formula set forth in the FDOT Highway Safety Improvement Guidelines, and approved by the Federal Highway Administration; 2) copies of the actual crash reports filed with the Florida Division of Highway Safety and Motor Vehicles, which provided detail greater than that generally available through FDOT's own accident data reports, and which formed the basis of the collision diagram in the Safety Evaluation (FDOT Exhibits 36; and 3) and its August 1996 update thereto (FDOT Exhibit 41), on-site evaluation and review of the roadway to determine geometrics of the roadway, locations of driveway accesses and side roadways and the degrees at which roadways intersected. Metric prepared an update of the Safety Evaluation for the years 1989-1994, to determine the continuing validity of the Safety Evaluation, as well as to review alternative proposals to the original proposed roadway configuration. In preparing the update, the recent accident data (FDOT Exhibit 37) and the underlying research in the Safety Evaluation were used by Metric Engineering in reaching its conclusions. The Safety Evaluation performed by Metric in 1989 established high accident rates on the roadway based on a detailed segmental analysis of the roadway. In August of 1996, the Safety Evaluation was updated by Metric, which update confirmed the findings of the Safety Evaluation, and further stated that accident frequency on the Monroe County portion of the roadway exceeded the state average accident rate and the abnormally high accident rate for the years 1990 through 1994 (notwithstanding the rear-end accidents occurring at Jewfish Creek). Fatal accidents on the Dade County portion exceed the state average on the same stretch by 37 percent for the same years. The most severe accidents occur on the Dade County portion. The Monroe County portion of the roadway exceeds the statewide average in the abnormally high accident rate four out of the last five years that FDOT studied. The Dade County portion does not exceed the accident frequency or the number of accidents, but the fatality rate in Dade County is much higher than the state average. Presently an abnormally high accident rate exists in three locations along the project corridor, two of which are in the vicinity of the Jewfish Creek bridge. The third location is north of the bridge on Cross Key. Replacing the Jewfish Creek Bridge with the fixed-height bridge proposed by FDOT will substantially increase the safety on the project corridor. The District considered this to be an important positive element in the public interest balancing test. The existing 2:1 slopes of the roadway make it difficult for drivers to recover from running off the roadway, resulting in a greater frequency of this type of accident. Moreover, the existing clear zone is not large enough to overcome the 2:1 slope to allow safe recovery of errant vehicles. As a result, catastrophic crashes occur rather than safe recoveries. Also, as with hurricane evacuation discussed in the following section, actual accidents on the roadway prevent traffic from accessing or leaving the Keys, and also prevent emergency vehicles from rapidly accessing the Keys and a crash site. This occurs because there is little or no shoulder or clear zone along the sides of the road to allow emergency vehicles to efficiently access an accident site, and in the event of a severe, head-on type collision, the roadway is blocked off. U.S. 1 through the project corridor is regarded as so unsafe for travel that Monroe County law enforcement officials call it "death alley." There are many head-on collisions due to the two-lane, no-median alignment. Law enforcement is difficult and dangerous along the roadway, because it has very few areas wide enough to allow law enforcement officials to detain driving violators. It is also very dangerous, for the same reasons, for a driver to pull off the roadway with a broken-down vehicle. High rates of speed and impaired drivers contribute to the accident rates along the project corridor. The efforts of law enforcement to control speeders and drunk drivers is impeded since it is practically impossible for enforcement officers to turn their vehicles around to pursue violators without running a high risk of causing an accident on their own. The project would significantly improve safety on the roadway by reversing the problems identified in the this section, as well as the previous sections of this Recommended Order. The project would virtually eliminate head-on collisions which largely contribute to serious injuries and fatalities along the roadway. The project would also help eliminate problems with emergency vehicle access to accident sites and restoration of service in the event of accidents, and would increase the roadway's level of service as discussed below. Improved level of service was an additional need considered by FDOT during the PD&E process. While the District did not consider the traffic level of service by itself to be weighted as part of the positive public interest criteria in this project, the impacts of resulting congestion are relevant to the public interest consideration of traffic safety as discussed in the foregoing sections. Lower quality level of service, as presently exists on the roadway through level of service F, adversely affects the safety of the roadway. When traffic levels rise, driver frustration increases leading to drivers passing in no-passing zones and potentially resulting in head-on collisions and high-severity accidents. Additionally, due to the narrow shoulders of the existing roadway, accident vehicles pose a threat to and impede normal traffic flow on the roadway. The Highway Capacity Manual set the standards for traffic engineering and is used in all fifty states. The manual classifies the existing roadway as a two-lane arterial rural road. Applying the standards for measuring level of service for two-lane rural roads set forth in the Highway Capacity Manual, FDOT determined that the existing level of service on the roadway is E, which is a very poor level of service that does not meet the established standard of level of service C required by the Highway Capacity Manual. Monroe County uses a speed based method of calculating level of service. Using that method, the level of service for U.S. 1 is at an acceptable level. The parties disagree as to which method of calculating the level of service is appropriate. That conflict is resolved by finding that the method used by FDOT is the appropriate method because of its wide acceptance and long-term use. Traffic volume in the area of the southern terminus of the project is growing at a rate average annual rate of 3.07 percent. In the present condition of the roadway, level of service will degrade to F, or forced-flow conditions, by the year 2006. Even with the improvements proposed by FDOT, the level of service in the northbound direction would improve to level of service B, but the level of service in the southbound direction would remain at level of service D or E due to the single southbound land configuration. Hurricanes pose a serious threat to the safety and welfare of residents and visitors of the Keys. Monroe County is the most vulnerable hurricane-prone area in the United States because it is surrounded by tropical waters, land elevation is low throughout the islands, and the evacuation routes are limited to U.S. 1, an extended route that starts in Key West and runs to the mainland, and Card Sound Road. The greatest potential for loss of life during a hurricane in the Keys is from storm surge. Storm surge is a dome of water near the center of a hurricane which is created by the winds on the water's surface. In a category 3, 4 or 5 storm, the entire land mass in the path of the storm will be inundated. Because of the wind and storm surge associated with hurricanes, the best response to a hurricane warning in the Keys is to evacuate people to the mainland away from the water and the storm surge threat. Accordingly, Monroe County orders a mandatory evacuation in a category 3, 4, or 5 hurricane, and no shelters are opened. There is little or no disagreement as to the vulnerability of the Keys to hurricanes or as to the danger posed by a hurricane. There is disagreement as to whether the proposed project is needed for improved hurricane evacuation. The conflicting evidence in this regard is resolved by the following findings, which are based on the more credible, substantial evidence. The existing road does not have sufficient hurricane evacuation capacity to meet the present and projected future needs of Monroe County residents and visitors. In current hurricane evacuations, the two northbound lanes on U.S. 1 between mile marker 90 and 106 are split at Key Largo. Sixty percent of the traffic is directed up the northbound lane of U.S. 1; forty percent of the traffic is diverted onto the northbound lane of Card Sound Road. One southbound lane of U.S. 1 and Card Sound Road must remain open for emergency vehicles to reach an accident or a disabled vehicle, or to bring emergency supplies into the Keys. Improving the roadway is critical to the success of Monroe County's hurricane evacuation plan. FDOT relied on hurricane evacuation and needs modeling performed by Monroe County and the ACOE to confirm the need for improvements. All of the models used indicated that the project corridor is the controlling roadway segment for improving hurricane evacuation of the Keys. Additionally, FDOT relied on the Lewis Report of January 15, 1993, a study commissioned by the Governor of Florida. Recommendation No. 17 of the Lewis report recommends that FDOT expedite the design and construction of the project, which is viewed as being critical for increasing the rate of emergency evacuation. Dr. Robert Sheets, former director of the National Hurricane Center, testified that the failure to make improvements to the roadway would be "unconscionable." Dr. Sheets and Billy Wagner, the Director of Emergency Management for Monroe County, presented very compelling and very persuasive testimony that this project is essential for hurricane evacuation purposes. The proposed project is the minimum transportation improvement that will achieve a significant improvement in evacuation safety and clearance time. With the present two- lane configuration and narrow shoulders, evacuating traffic would be halted completely by a vehicle breakdown or an accident blocking one lane. Replacement of the Jewfish Creek Bridge will also facilitate the hurricane evacuation need for the project. In addition to improving the rate of evacuation, the project will make an evacuation safer. Emergency personnel cannot reach accidents on the roadway during an evacuation because, in certain segments, no roadbed exists adjacent to the northbound lane. A second northbound lane and wider road shoulders would enable disabled vehicles to be serviced and removed from the highway. The proposed changes to the road would improve emergency vehicles' access to an accident scene. The elevation of the roadway at Lake Surprise is so low that it can be flooded easily by a storm. The proposed project would replace the existing muck bed of the roadway with more stable material. The existing roadway is subject to settling and washout during storm events, which reduce the safety of the roadway itself and reduce the evacuation capacity of the roadway. If washout occurs, moving equipment to the islands for recovery efforts following a hurricane will be difficult or impossible. The proposed project will prevent erosion and reduce the effects of storm surge and wave action on the road during a hurricane. When the project has been completed, three lanes of evacuating traffic, two lanes from U. S. 1 and a third from Card Sound Road, will converge at Florida City. Representatives of FDOT, the Monroe County Sheriff's Department, the Florida Department of Law Enforcement and Monroe County Emergency Management have planned to manage the northbound traffic when it reaches Florida City during an evacuation. Several feasible alternatives exist, but additional planning is needed to prevent a monumental bottleneck at the northern terminus of the project. While it is clear that this project will not resolve all problems that exist as to hurricane evacuation, it is also clear that this project is essential to improve hurricane evacuation. SECTION 403.918(2)(a)2, FLORIDA STATUTES Section 403.918(2)(a)2, Florida Statutes, requires the permitting agency to consider “[w]hether the project will adversely affect the conservation of fish and wildlife, including endangered species, or their habitats.” The District considered the effect of the direct loss of dredging and filling 149.07 acres of wetland. As set forth in previous sections, it is found that this loss will be offset by the mitigation. For use during construction of the project, FDOT will adhere to technical special provisions and special permit conditions 9 through 13 to protect manatees, crocodiles, alligators, indigo snakes, marine turtles, and valuable trees, palms and other wildlife, to minimize or preclude any impacts to those species. Additionally, any osprey nests around the Jewfish Creek Bridge area at the time of construction will be relocated by FDOT if necessary. As part of the development of the FEIS, as required by the Federal Highway Administration under the National Environmental Protection Act, FDOT obtained official letters of concurrence from the USFWS and NMFS that the project would cause no adverse impacts to endangered species under section 7 of the Endangered Species Act. That process also established the project's consistency with Florida Coastal Zone Management Program, as determined by the State Clearinghouse within the Office of the Governor, in coordination with DEP, the Department of National Resources and FGFWFC. The project also contains provisions to impact positively or enhance the conservation of fish and wildlife, including threatened or endangered species and their habitat, as described below. These were positive factors that further helped neutralize and offset the 149.07 acres of direct impacts. In addition, FDOT is required to evaluate the effectiveness of the fencing along the entire project corridor, discussed below, and report to the District on that effectiveness. If the District determines that the fencing could be more effective, it may require FDOT to implement those suggestions. South of the C-111 canal, construction of box culverts and bridges addresses impacts to the American crocodile, a listed endangered species. Problems were identified with placement of existing culverts, which did not provide enough clear space and which caused the crocodile to cross over the roadway rather than through the culvert. To address this problem, 15 larger box culverts and three bridges will be placed within the roadway. These provide the necessary clear space to allow the crocodile to safely pass under rather than over the road. The location of the box culverts was chosen by reviewing crocodile mortalities associated with road crossings. Placement of these box culverts and bridges will also improve the hydrological flow of water within the project area, provide a crossing area for manatees, and allow greater dispersal of the crocodile population throughout Florida Bay. Species expected to use these box culverts include aquatic and aquatic water dependent species in the area. They were primarily targeted for crocodiles, alligators, and manatees, but certain fishes, turtles, frogs and other species in the wetlands along the project corridor will utilize the culverts. The box culverts will have 100 feet of wingback fencing extending north and south of each culvert. The intent of the wingback fencing is to funnel wildlife into the box culverts. Intermittent or wingback fencing is appropriate south of the C-111 canal for two primary reasons. First, the animals which will be guided into the box culverts are aquatic dependent. The area south of the C-111 canal is primarily water, washed mangrove areas and tidal creeks. Crocodiles tend to move in tidal creeks. Second, it was not possible to ensure continuous fencing along all portions of the project south of the C-111 canal because there are existing businesses. It could not be assured that these businesses would keep a gate closed. The project originally proposed continuous fencing alongside the road where it abuts ENP. Continuous fencing was initially proposed because the initial application included a solid concrete barrier down the median of the road. If a crocodile did enter the road from the side with discontinuous fencing, after crossing one lane the crocodile would hit the barrier, but then easily find its way back to the area it came from. However, the project was later modified to include a tri-beam barrier because it lessens the footprint of the project and thereby lessens the wetland impact. Since the current application does not include a continuous barrier down the middle of the road, if a crocodile enters the road it would cross the tri-beam barrier, go across another lane of roadway before hitting a continuous fence. The animal would then run up and down that fence with nowhere to go except back across the road again. This would increase their exposure to a road kill. With the installation of bridges and culverts along the southern portions of the project corridor, there is no need for continuous fencing because aquatic wildlife, such as the American crocodile, will tend to follow the flow of water through the culverts rather than climb over the roadway. The FGFWFC and ENP oppose continuous fencing and prefer intermittent fencing south of C-111 canal since the project now includes a tri-beam barrier. Positive benefits also include construction of panther crossings at four locations north of the C-111 canal to account for impacts to the Florida panther, a listed endangered species, in the vicinity of the project, along with continuous fencing on both sides of the road north of the C- 111 canal. The crossings will be placed at locations that show historical use by wildlife, including areas at the Dade County Correctional Institute access roadway, the water control structure on the C-109 canal, and the berm of the C- 111 canal. The wildlife crossings are indicated by blue dots on FDOT's Exhibit 1. FDOT underwent years of extensive coordination with the environmental regulatory and resource agencies to design a project that would accommodate their ecosystem management plans. The location of the wildlife crossings was based upon radio telemetry data, collected from radio-collared panthers, and their typical corridor movement. The location was further chosen based on input from the USFWS and the FGFWFC. The continuous fencing north of the C-111 canal will prevent wildlife from crossing the road, and instead force them to use the wildlife crossings. The crossings were designed for panther use, the panthers being the shyest animal in the area. If panthers can be accommodated, then other threatened and endangered species and other wildlife are expected to use them. DOT studies of the effectiveness of wildlife crossings, with fencing, including crossings installed on Alligator Alley, establish that wildlife will use the crossings, both singly and in groups, and that the crossings substantially reduce, if not eliminate, automobile- related mortality of wildlife. Documented wildlife include panthers, wild turkeys, wading birds, alligators, deer, bobcats, black bears and raccoons. SECTION 403.918(2)(a)3, FLORIDA STATUES Section 403.918(2)(a)3, Florida Statutes, requires the permitting agency to consider “[w]hether the project will adversely affect navigation or the flow of water or cause harmful erosion or shoaling.” The replacement of the bascule bridge at Jewfish Creek with a 65-foot high fixed-height bridge will be a benefit to navigation. Because Jewfish Creek is part of the intracoastal waterway, the existing bridge has to be frequently raised or lowered to accommodate marine traffic. Because of the age of the existing structure, frequent breakdowns have been experienced. Marine traffic is stopped or delayed if the bridge cannot be raised or if there is a delay in raising the bridge. Vehicular traffic is stopped while the bridge is raised. Regarding the flow of water, the project incorporates wildlife box culverts and bridges, which will improve tidal flushing and the flow of water south of the C- 111 canal. The District considered this to be a positive consideration under the public interest test. The 25 hydrologic culverts north of the C-111 canal were also a positive factor in the test because the culverts provide future water management capability. Erosion and shoaling are neutral factors in the public interest test because the permit conditions contain a plan to control erosion and shoaling during construction and to provide for road stabilization after construction. In addition, there is a positive factor regarding shoaling in that the roadway area now has a lot of storm action, causing problems with erosion on the side of the road. The project provides for road stabilization, which is a neutral to positive factor in the public interest test. SECTION 403.918(2)(a)4, FLORIDA STATUTES Section 403.918(2)(a)4, Florida Statutes, requires the permitting agency to consider “[w]hether the project will adversely affect the fishing or recreational values or marine productivity of the project.” A positive factor pertaining to marine productivity is the box culverts and bridges south of C-111, which will allow marine species to travel beneath the road to access the water on both sides of the road. Removal of the causeway along Lake Surprise opens that water body back up to one contiguous system, which is also a positive factor. The seagrass mitigation addressed in previous sections will also improve marine productivity and provide habitat for fish. SECTION 403.918(2)(a)5, FLORIDA STATUTES Section 403.918(2)(a)5, Florida Statutes, requires the permitting agency to consider “[w]hether the project will be of a temporary or permanent nature.” The project is permanent, though some construction impacts are temporary in nature. Once temporary impacts have ended and the project is complete, the project will be a positive benefit, because of the construction of the SWM system, culverts, animal underpasses and other benefits as set forth above. SECTION 403.918(2)(a)6, FLORIDA STATUTES Section 403.918(2)(a)6, Florida Statutes, requires the permitting agency to consider “[w]hether the project will adversely affect or will enhance significant historical and archaeological resources under the provisions of s. 267.061.” This factor is not at issue. SECTION 403.918(2)(a)7, FLORIDA STATUTES Section 403.918(2)(a)7, Florida Statutes, requires the permitting agency to consider “[t]he current condition and relative value of functions being performed by areas affected by the proposed activity.” A percentage of wetlands immediately adjacent to the road are impacted by exotic vegetation. Areas further out are part of a significant wetland ecosystem and are considered high quality. This project contains an exotic control program within FDOT's right of way, which is a positive consideration in the public interest test. Wetlands are currently receiving untreated storm water, which runs off the road immediately into the adjacent wetlands and water bodies without treatment. The project will include a SWM system where none currently exists as is detailed in the previous sections. This is a positive factor in the public interest test. The direct impacts of the project on 149 acres of wetlands alongside the roadway is not as large or significant as the impact caused by placement of the original embankment and resulting cut off of the eastern and western portions of the Everglades north of the C-111 canal. Overall, the concurrent and upfront mitigation efforts of FDOT are of regional significance and benefit to Everglades ecosystem by helping to repair the damage caused by the original embankment. THE PROJECT IS CLEARLY IN THE PUBLIC INTEREST The District appropriately weighed all considerations in determining that the project is clearly in the public interest. The greater weight of the competent, credible evidence established that the project is clearly in the public interest. RIGHT OF WAY PERMIT APPLICATION The land encompassed by the ROW permit has been properly adopted as a "work" of the District, requiring District authorization via a ROW Permit Modification to FDOT. The District's real property interest in the C-111 ROW applicable to the ROW permit modification consists of both fee simple and easement interests. The evidence is clear that DOT's application for the permit modification was thoroughly reviewed by the District, consistent with the District's established ROW permit review process. The District presented uncontroverted evidence and expert testimony to establish by a preponderance of the evidence that issuance of the permit modification to FDOT is consistent with all applicable District statutes, rules and other criteria, including the District's conditions for issuance of ROW Permits set forth in Rule 40E-6.301, F.A.C. FBII offered no evidence or testimony to the contrary. FUTURE MODIFICATIONS Modifying the project at a later date to pave a second southbound lane would require a District ERP permit. The addition of impervious surface triggers the District's SWM jurisdiction in this regard. However, FDOT established that that it had no current plans for further widening. The permit conditions require secondary and cumulative impacts associated with the increased capacity be addressed in accordance with the rules and criteria in effect at the time of any application for future widening. In addition, the permits require that FDOT must comply with any more stringent water quality criteria in effect at the time of any future widening. MODIFICATIONS AT THE FINAL HEARING At the Final Hearing, the District issued an Addendum to Staff Report for each of the SWM and WRM permits. The amendments made non-substantive changes to the District's staff reports regarding fencing along the roadway, performance of a study of fencing on the roadway by FDOT, water quality sampling along the roadway, assignment of mitigation credits, and other technical changes in wording for purposes of clarification. The changes set forth in the District's Exhibits 5 and 6 do not create impacts to the environment beyond those addressed elsewhere herein.
Recommendation Based on the foregoing findings of fact and conclusions of law it is RECOMMENDED that the Governing Board of the South Florida Water Management District enter a Final Order that issues the three permits challenged in this proceeding (SWM Permit No. 940606-10, WRM Permit No. 9460606-2-D, and ROW Permit No. 2584) subject to the conditions contained in the staff reports on the SWM permit application and the WRM permit application and subject to the additional permit conditions reflected by District Exhibits 5 and 6 and by the Findings of Fact pertaining to the permit for the relocation of the FKAA pipe. DONE AND ENTERED this 11th day of April, 1997, in Tallahassee, Leon County, Florida. ___________________________________ CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative this 11th day of April, 1997.
Findings Of Fact Application No. 76-00450 is for a consumptive use permit from 10 wells located in Hillsborough County, to be used for public water supply for the City of Temple Terrace. The permit seeks to withdraw 2.028 million gallons a day average annual withdrawal and 4.564 million gallons per day maximum daily withdrawal. The sought for withdrawal may affect other wells by drawdown of an average of 1" in a surrounding well. Such a drawdown will not seriously and adversely affect the surrounding wells. The Southwest Florida Water Management District's staff recommends issuance of the permit with the following conditions: That the applicant shall install totalizing flowmeters of a type acceptable to the district on all withdrawal points covered by the permit. That the applicant shall record the pumpage on a weekly basis and shall submit a record of that pumpage to the district quarterly beginning January 15, 1977. All individual connections supplied by withdrawals permitted will be metered. Records of meter readings will be made available to the district upon request. That the permit shall expire on December 31, 1980.
The Issue The ultimate legal and factual issue in this matter is whether Engle Homes, Inc., and Lake Bernadette, Inc. (Permittees), have provided the Southwest Florida Water Management District (District) with reasonable assurances that the activities they propose to conduct pursuant to Management and Storage of Surface Water (MSSW) General Construction Permit No. 49005837.017 (the Permit) meet the conditions for issuance of permits established in Rules 40D-4.301, 40D-4.302, and 40D- 40.302, Florida Administrative Code. In particular, the issues of fact to be litigated are whether the Project will cause adverse water quality impacts to receiving waters and adjacent lands; whether the Project will cause adverse flooding of on-site or off-site property; whether the Project will cause impacts to existing surface water storage and conveyance capabilities; and whether the Project will adversely affect the property of others.
Findings Of Fact The Parties Engle Homes, Inc., and Lake Bernadette, Inc., are corporations licensed to operate in the State of Florida. The District is the administrative agency charged with the responsibility to conserve, protect, manage, and control water resources within its boundaries pursuant to Chapter 373, Florida Statutes, and the rules promulgated thereunder as Chapter 40D, Florida Administrative Code. Driscoll resides at 35716 Welby Court, Zephyrhills, Florida 33541, Lot 14, within the Timber Creek 2 Subdivision (Subdivision). Driscoll requested this hearing to show the District that there is a drainage problem on Lots 13 and 14, and the adjacent Geiger property to the south, which should be fixed at this time and as part of the Project. Driscoll wants "Engle Homes to propose a new solution to fix the entire Welby Court Geiger property problem," i.e., from Lots 4 through 14, and not a piecemeal solution as proposed in the Permit modification. The Subdivision Engle Homes, Inc., and Lake Bernadette, Inc., developed the Timber Creek 2 Subdivision. Lots 15 through 25 run east to west and are north of Welby Court. Lots 15 and 16 are located north of the cul-de-sac, on the eastern portion of Welby Court. Lots 3 through 14 run west to east, south of Welby Court. Lots 13 and 14 are south of the cul-de-sac on the eastern portion of Welby Court and are across the street and the cul-de-sac from Lots 16 and 15, respectively. Residences exist on Lots 5, and 7 through 14. Driscoll owns Lot 14, a corner lot, which is the southeastern most lot of the Subdivision. Don Geiger (Geiger) owns the land (approximately five acres) south of the property lines of Subdivision Lots 5 through Geiger's northern driveway, essentially a dirt road, runs parallel to Lots 5 through 14. Subsequent to the original construction activity involving the Subdivision, the developer realized that there was an "existing depression" (referenced on Engle Exhibit number 1), south of Lots 7 and 8, and on Geiger's property. Geiger complained to the District about standing water in this area. This depression area is approximately 90 feet long and 30 feet wide which needed to be "drained off" according to Geiger. The depressed area on Geiger's property was most likely caused when Lots 7 through 14 were graded and sodded, which raised the "lots up a few inches" above Geiger's driveway/property. Water is trapped during a storm event between the back yards and the depressed area. As a result, the southern end of the back yards, particularly Lots 7 and 8, and the driveway remain constantly wet. The Project On January 16, 2001, Engle Homes, Inc., and Lake Bernadette, Inc., filed MSSW Permit Application No. 49005837.017 with the District, to address the problems with the rear lot grading and the adjacent property. The actual Project area for the permit modification1 includes the southern portions of Lots 4 through 9 and south of the property lot line including Geiger's property. See Finding of Fact 5. The modified permit does not address the drainage area including the back yards of Lot 13 and Driscoll's Lot 14, and the other portion of Geiger's property/driveway to the south. On April 5, 2001, the District issued MSSW Permit No. 49005837.017 to Engle Homes, Inc., and Lake Bernadette, Inc., under the provisions of Chapter 373, Florida Statutes, and Chapter 40D-40, Florida Administrative Code, for the modification of a surface water management system to serve the Project area. The proposed Project will involve the construction of a concrete inlet box with a safety grate, storm sewers, and grass swales. Specifically, the project is intended to solve the drainage problems associated with the "existing depression" south of the boundary line for Lots 7 and 8 on Geiger's property (although Lots 4 through 9 ("area 1") are included within the Project area), and the back yards of Lots 7 and 8. A catch basin is proposed to be located south and on the lot line between Lots 8 and 9, which is expected to drain off the water in the depression area to the modified surface water management system. The inlet box will be placed in the corner between Lots 8 and 9. The collected water in the inlet box will be routed underground through a series of 18-inch storm sewer pipe straight north through a drainage easement between Lots 8 and 9 to Welby Court. The underground pipe ties into an existing pipe in front of Lot 9 on the street, then runs east along the Welby Court right-of-way and then north between Lots 19 and 20, and eventually north into a large permitted retention pond, located to the north of the Subdivision which will handle the stormwater. Driscoll's Alleged Drainage Problem There is another distinct drainage area, i.e., "area 2," which includes Geiger's property and the southern portions of Lots 13 and 14, where water drains from south to north into a roadside ditch to Geiger Cemetery Road ("area 3"), which runs south to north and east of Lots 14 and 15. During a September 2001 tropical storm, there was standing water on Geiger's driveway, directly south of Lots 13 and 14, which was present for more than 3 days. This was referred to by Mr. Barrett as a "small drainage problem that could easily be corrected." On the other hand, Geiger says that there is standing water on his driveway, south of Lots 13 and 14, "all the time." This caused Geiger to move his driveway "50 or 60 feet" south. According to Geiger, the berm, which runs across Lots 10 through 14, should be lowered and the backyards reconfigured. But this would be quite disturbing to the neighbors. Therefore, Geiger recommends the placement of drains south of Lots 13 and 14, which would direct the water out to the ditch at Geiger Cemetery Road and away from Driscoll's Lot 14. The modified Permit is not intended to solve this problem, although Driscoll wants this problem fixed. It is not necessary to resolve Driscoll's issue regarding whether there is a drainage problem in and around Driscoll's lot. The two drainage areas 1 and 2 discussed herein are not connected, although they are close in proximity. The solution to the first problem has no impact on the second, and there is no cited statutory or rule requirement that both issues must be addressed in this Permit application. This is Driscoll's quandary. Compliance with Rules 40D-4.301 and 40D-4.302, Florida Administrative Code The Project will not impact wetlands or surface waters. The Project will not adversely impact the value of functions provided to fish and wildlife, and listed species, including aquatic and wetland-dependent species, by wetlands or other surface waters and other water-related resources. The Project will not adversely impact the quality of receiving waters such that the water quality standards will be violated. The Project will not cause adverse secondary impacts to the water resources. The Project will not adversely impact the maintenance of surface or groundwater levels or surface water flows established pursuant to Section 373.042, Florida Statutes. The Project will not cause adverse impacts to a work of the District. The Project is capable, based on generally accepted engineering and scientific principles, of being effectively performed and of functioning as proposed. The Project will be conducted by an entity with financial, legal, and administrative capability of ensuring that the activity will be undertaken in accordance with the terms and conditions of the permit, if issued. The Project will comply with any applicable special basin or geographic area criteria established pursuant to Chapter 40D, Florida Administrative Code, by the District. The Project will not adversely affect the public health, safety, or welfare. The Project will not adversely impact the conservation of fish and wildlife, including endangered or threatened species, or their habitats. The Project will not adversely affect navigation. The Project will not cause harmful erosion or shoaling. The Project will not adversely affect fishing or recreational values or marine productivity in the vicinity of the Project. The Project will not adversely affect significant historical and archeological resources. The Project will not cause unacceptable cumulative impacts upon wetlands and other surface waters. The Project area is less than 100 acres. The Project does not require dredging or filling of wetlands, or construction of boat slips. The Project is not contrary to the public interest. The Project will not cause adverse water quantity impacts to receiving waters and adjacent lands, and will not adversely affect or impact the property of others, including Driscoll's property, Lot 14. "Area 1," between Lots 4 and 9, is a separate drainage area, and the water from this area does not drain to Lot 14. Driscoll's property is not within the Project area, and the Project was not intended to resolve his alleged drainage problem. The Project will not cause adverse flooding to on-site or off-site property. The Project will not cause adverse impacts to existing surface water storage and conveyance capabilities. Rather, the project is expected to improve the conveyance of water and drainage for "area 1" and the Project area.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Southwest Florida Water Management District enter a final order issuing Management and Storage of Surface Water General Construction Permit No. 49005837.017. DONE AND ENTERED this 24th day of October, 2001, in Tallahassee, Leon County, Florida. CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of October, 2001.
The Issue Whether the Southwest Florida Water Management District proved that Alan R. Behrens signed a pleading, motion, or other paper in this proceeding for an “improper purpose,” and, if so, whether sanctions should be imposed pursuant to Section 120.569(2)(e), Florida Statutes?
Findings Of Fact The Parties Alan R. Behrens has resided and owned property at 4740 Southwest Armadillo Trail, Arcadia, DeSoto County, Florida, since 1985. There is a two-inch free-flowing artesian well used for domestic purposes on this property. Mr. Behrens’ well is approximately 150 feet deep and draws water from the Intermediate aquifer. The well currently has no pumping mechanism, and Mr. Behrens relies on an unaided artesian flow to produce water, which at times is inadequate. In prior administrative cases and the case involving Has-Ben Groves, Mr. Behrens is concerned that the withdrawal of water in the amounts requested by others from areas near his property will impair his ability to draw adequate amounts of water from his well. Mr. Behrens stated that his purpose in challenging the Has-Ben Groves WUP “is to receive assurances that any proposed use is not going to adversely impact [his] well. That’s [his] general biggest, main goal.” He feels that he did not receive assurances from the District; therefore, his only option was to request a hearing. The Southwest Florida Water Management District is the administrative agency charged with the responsibility to conserve, protect, manage, and control water resources within its boundaries pursuant to Chapter 373, Florida Statutes, and the rules promulgated thereunder as Chapter 40D, Florida Administrative Code. The District has the statutory duty to review and approve or deny applications requesting consumptive water use permits. The Has-Ben Groves WUP Application On January 27, 2003, the District issued a notice of final agency action for approval of Water Use General Permit No. 20012410.000 issued to Has-Ben Groves. The WUP authorized annual average groundwater withdrawals of 31,100 gallons per day (gpd) to be used for irrigation of Has-Ben Groves’ 40-acre citrus grove. (Peak monthly withdrawals of 254,300 gpd and withdrawals for crop protection at 1,015,200 gpd were authorized.) Tomlinson previously owned the Has-Ben Groves’ 40 acres. The District previously permitted the well on the Has-Ben Groves 40 acres when Tomlinson owned the property. The Tomlinson well was previously permitted for 77,000 gpd on an annual basis, but the permit expired. Thus, Has-Ben Groves applied for a new WUP. The Has-Ben Groves permitted well site is located in Hardee County and is approximately 16 miles from Mr. Behrens’ artesian well in DeSoto County, and is expected to draw approximately 94 percent of its water from the Upper Floridan aquifer. Did Mr. Behrens sign a pleading, motion,or other paper for an improper purpose? On January 20, 2003, Mr. Behrens, by letter, asked the District to be advised of any agency action regarding five WUP applications, including the Has-Ben Groves application. In this letter, Mr. Behrens also requested, what he characterized as “public information,” “what the predicted drawdown to the intermediate and Floridan aquifers are.” He inquired further: “Please make sure the hydrologist includes this information. I have previously asked for this basic information; please do not force me to take legal action against SWFMD per the Sunshine law & other public information laws.” (Emphasis in original.) Mr. Behrens was copied with the District’s “Final Agency Action Transmittal Letter” sent to Has-Ben Groves on January 27, 2003. According to Mr. Behrens, “legal action” meant the filing of a petition requesting an administrative hearing. He felt that it was his only option to receive information and assurances. In particular, Mr. Behrens wanted the District to create and provide him with drawdown contours and modeling even if the District believed it was unnecessary. See Endnote 1. By letter dated January 29, 2003, the District, by Pamela A. Gifford, CLA, Office of General Counsel, responded to Mr. Behrens’ request for ‘predicted drawdown’ information and stated in part: “First, please be advised, the District does not prepare ‘predicted drawdown’ for all water use permits. Second, to ask for ‘predicted drawdown’ for permits, you are making a pubic records request. The District does not accept anticipatory public record requests. In other words, when the District receives a public records request, it will search for existing records responsive to the request as of the date of the public records request. . . . Third, the District will not create a record to respond to a public records request. If a ‘predicted drawdown’ exists, it will be provided to you, if it does not, it will not be created to answer your request.”1 By letter dated January 31, 2003, Mr. Behrens responded to the District’s January 29, 2003, letter referred to above and expressed his understanding that he could “expect the results of drawdown modeling to be included in Notices of Agency Action that [he] receive from the District.” Mr. Behrens requested the name of the District office and the hydrologist who reviewed the Has-Ben Groves WUP application; the location of the file; a statement that it was “apparently a new withdrawal”; a request to identify the amount of water coming from the Intermediate and Floridan aquifers; a query as to why the withdrawal would “be cased to only a depth of 120 feet; won’t this mean that much of the water will be drawn from the intermediate?” Mr. Behrens also requested “a copy of the drawdown modeling results (map).” Mr. Behrens advised that it was “very important that new groundwater withdrawals do not lower [his] well level further, because [he is] relying completely on artesian free-flowing pressure; every inch of level reduction creates further hardship for [him].” (During his deposition, Mr. Behrens felt that the District could produce the information on a “voluntary” basis in order to give him “assurances up front.”) By letter dated February 10, 2003, the District, by Ms. Gifford, responded to Mr. Behrens’ January 31, 2003, letter and advised him “that drawdown modeling will not be included in Notices of Agency Action that you receive from the District. The only way that you will receive the drawdown modeling is if the District has records related to the modeling at the time you make a specific public records request for same. For example, if you make a public records request today for drawdown modeling, the District will only provide records to you that are in our files as of today. You would have to make a subsequent public records request to get any records that were received or created by the District after today’s date.” (Emphasis in original.) Ms. Gifford also advised Mr. Behrens that he was being provided with “copies of documents that are responsive to [his] public records request dated January 31, 2003.” Mr. Behrens was provided with a copy of the Has-Ben Groves General Water Use Permit Application which indicated, in part, that the application was “new” as opposed to a “renewal” or “modification”; the location of the well site; that Has-Ben Groves intended to irrigate 40 acres for citrus; and that the construction date of the well was in “1960.” The word “existing” is written on the line describing, in part, the casing diameter, depth, and pump capacity. See Finding of Fact The name “Phillippi” is handwritten on page one of the application. (Michael Phillippi is a professional geologist and employed with the District for over nine years. He had a pre- application telephone conversation with the applicant for the Has-Ben Groves WUP.) A “Water Use Permit Evaluation Worksheet” was also enclosed which included, among other information, the names “Lucille” and “Deborah” and the initials of two persons. The record does not indicate that Mr. Behrens followed up with the District regarding the Has-Ben Groves application after receiving the District’s February 10, 2003, letter and enclosures. On February 19, 2003, Mr. Behrens filed a Petition for Formal Hearing challenging the District’s preliminary decision to approve the WUP. The District determined that the Petition was timely filed, but not in substantial compliance with the requirements of Section 120.569(2)(c), Florida Statutes, and Florida Administrative Code Rule 28-106.201(2), governing the initiation of administrative proceedings. The District issued an Order of Dismissal Without Prejudice on February 27, 2003. On March 12, 2003, Mr. Behrens filed an Amended Petition for Formal Hearing. Mr. Behrens alleged that the withdrawal to be authorized by the WUP “would use huge quantities of water from the intermediate aquifer, even though water from the Floridan aquifer is completely suitable for citrus irrigation”; is “very close” to Mr. Behrens’ “property and well”; and the “cone of depression in the Intermediate aquifer that would be caused by the new use will cause a reduction in Petitioner’s water level and pressure and impair the ability of his well to produce water.” (Mr. Behrens also alleged that “[t]he proposed well would be eight inches in diameter, 920 feet deep, and cased to only 120 feet.” See Finding of Fact 15.) Mr. Behrens also alleged that the District refused to provide certain information, such as predicted drawdown to area wells. He also raised numerous disputed issues of material fact. On May 23, 2003, the District deposed Mr. Behrens. During his deposition, Mr. Behrens was asked to identify all facts and documents or sources of information he relied on in making the allegations in the Amended Petition. Mr. Behrens testified that the challenged water use withdrawal “seems like a very excessive amount”; “is [c]lose enough to have an impact on [his] well”; “is going to have a drawdown, is going to have an impact on the aquifer” and he has “a well on the aquifer”; that “these wells are going to have a drawdown and they’re going to draw down [his] well”; and that his position, that the Has-Ben Groves well will have a drawdown impact on his well, is based upon “[s]cience and facts and common sense” and “the evidence is self-evident.” Mr. Behrens has “done no studies.” Rather, he relies on information, such as the documents he introduced into evidence and his knowledge about the area and the District, to support the allegations in the Petition and Amended Petition. See, e.g., Findings of Fact 22-23. He does not have enough money to hire experts. He relies on the District’s hydrologists for the information he requests and for assurances. Yet, Mr. Behrens did not contact any District hydrologist to discuss his concerns before he filed the Petition and Amended Petition. See also Findings of Fact 26-28. On June 17, 2003, Mr. Behrens responded to the District’s Interrogatories, which requested Mr. Behrens to identify all facts he relied upon in making his assertions, including all documents prepared or reviewed in connection with such assertions. Mr. Behrens stated that no specific documents were prepared or reviewed in connection with his assertions made in paragraph 6 of the Amended Petition, and that the assertions in paragraph 6 were “pure truth – there’s no need to go searching to prove the obvious!” (Paragraph 6 of the Amended Petition alleged: “The proposed new groundwater withdrawal would use huge quantities of water from the Intermediate aquifer, even though water from the Floridan aquifer is completely suitable for citrus irrigation.”) During the final hearing, Mr. Behrens claimed that prior to filing his Petition, he relied on his experience and the information he maintains regarding the District’s identification of water use problems, and the District’s March 2000 Horse Creek Draft Resource Evaluation Report, the “Water Resources in Jeopardy” report published during the early 1990’s, and the 1992 Recommended Order in Alan R. Behrens, et al. v. Consolidated Minerals, Inc. and Southwest Florida Water Management District, et al., Case Nos. 92-0953-92-0957, 1993 WL 944120 (DOAH April 20, 1993; SWFWMD Nov. 30, 1994), in which Hearing Officer Daniel M. Kilbride found that Mr. Behrens was substantially affected by the District’s then proposed renewal and modification of an existing WUP held by Consolidated Minerals. 1993 WL 944120, at *4. (In interrogatory responses, Mr. Behrens also identified a 1986 potentiometric surface map of the Intermediate aquifer, among other maps he might identify.) These documents do not provide information relevant to whether the challenged Has-Ben Groves water withdrawal meets the conditions for issuance of a WUP or would lead a reasonable person to allege that the challenged Has-Ben Groves water use and well would have an adverse impact on Mr. Behrens’ use of his well. Before filing his initial Petition and during the interval before he filed his Amended Petition, Mr. Behrens did not contact or speak to District staff who reviewed the Has-Ben Groves WUP application or District staff in the Bartow Service Office (the District service office responsible for permitting matters in Hardee County) to obtain information concerning the Has-Ben Groves permit application or to discuss his concerns regarding whether the proposed water use to be authorized by the WUP would adversely affect his well. But see Finding of Fact 13, which indicates that on January 31, 2003, Mr. Behrens posed several questions to the District, prior to filing his Petition, which apparently were left unanswered. It appears Mr. Behrens did not pursue this inquiry until he served the District with Interrogatories on May 29, 2003. Mr. Behrens did not review the District’s “work file” after filing his Petition. In his Proposed Final Order (PFO), Mr. Behrens provided a detailed chronology and analysis of the factors he considered that caused him to file prior challenges to District action and his challenge to the District’s intent to approve the Has-Ben Groves WUP. He has mistrusted the District over time and has had little faith that the District understands his “unique circumstance” and will protect his well from adverse impacts resulting from the issuance of WUPs. See, e.g., (T. 95- 96, 98, 100.) He notes in his PFO that it was not until the Has-Ben Groves case that he “started to have trust in the District staff’s reliance on regional well monitoring data (as its sole source of cumulative impact analysis).” According to Mr. Behrens, the District provided him with information during discovery from which he derived reasonable assurances. He also felt that based on his experience, he “did not contact the permit reviewers in this matter because, from experience, he knew he could not trust them to provide the necessary assurances with a few comments over the telephone.” Yet, because of his financial inability to hire experts, Mr. Behrens relies on the expertise of the District’s hydrologists for assurance that his well will not be adversely impacted. See, e.g., (T. 112) (District Exhibit 13, pp. 41-42, 55, 58-61.) Stated otherwise, Mr. Behrens wanted the District staff to provide him with proof of reasonable assurance and he filed the Petition and Amended Petition because he felt he did not receive appropriate proof. If this final hearing went forward, his intent was to ask questions of the District’s hydrologists regarding many of the documents in his possession and to ask “District staff, under oath, about specific matters related to the protection of his well and the intermediate aquifer, in general,” presumably as he had done in the Basso and Boran cases, for example. See, e.g. (District Exhibit 13, p. 59-60.) Then, the ALJ, after hearing all of evidence, would decide whether reasonable assurance was provided. Prior to and after Mr. Behrens filed his Amended Petition, the District maintained Regional Observation and Monitoring Program (ROMP) wells that provide cumulative monitoring information concerning the Intermediate and Floridan aquifer water levels throughout the District. ROMP well data are available to the public upon request. (In response to a question posed by Mr. Behrens during the final hearing, Mr. Balser stated that ROMP well data do not give absolute assurance or reflect “[e]xactly what is happening in the geology under [Mr. Behrens] property.” Mr. Balser stated that he “would have to do testing of [his] property. But this is the best guess we can make looking at it from a regional view.”) It is more than a fair inference that Mr. Behrens was familiar with ROMP well data and their application in specific cases as a result of his participation in prior administrative cases. See pp. 4-5, supra. He did not request ROMP well data available from the District prior to filing his Petition and Amended Petition, although he asked for the quantity of groundwater which was expected to be withdrawn from the Intermediate and Floridan aquifers. See Conclusions of Law 48- 50. District WUP information and other records are available for public inspection, including the use and permitting history of the water withdrawal challenged by Mr. Behrens in this proceeding. If Mr. Behrens had inquired of the District prior to filing his Petition and Amended Petition, Mr. Behrens could have learned that the well on the Has-Ben Groves property had been in existence as early as the 1960’s for citrus irrigation, was first permitted around 1974, had previously been authorized by the District for withdrawals of as much as 77,000 gpd, was expected to draw approximately 94 percent of its water from the Upper Floridan aquifer, and there was no reasonable basis to conclude that withdrawals of 31,100 gpd from the Has-Ben Groves well would cause any adverse impact to his well, which draws water from the Intermediate aquifer. Stated otherwise, at the time he filed his Petition and Amended Petition, Mr. Behrens had no reasonable factual basis to allege that withdrawals of 31,100 gpd from the Has-Ben Groves’ well, located approximately 16 miles from his well, would have an adverse impact on his use of water from his well. (An applicant for a WUP is required to provide, in part, reasonable assurance that the water use “[w]ill not adversely impact an existing legal withdrawal.” Fla. Admin. Code R. 40D- 2.301(1)(i).) On June 30, 2003, Mr. Behrens filed a “Notice of Voluntary Dismissal” and responded, in part, to the District’s Motion for Summary Recommended Order, but not the District’s request for attorney’s fees and costs. Mr. Behrens stated that he withdrew his Amended Petition because he obtained information that he did not have when he filed his Amended Petition and that addressed his concerns about impacts to his well. He claimed, in part, that being informed of the District’s plan to set minimum levels for the Intermediate aquifer had allayed his fears that he would be without an artesian free-flowing water supply. However, the challenged WUP did not address or involve the setting of minimum flow levels. Based on the foregoing, Mr. Behrens did not make a reasonable inquiry regarding the facts and applicable law. Using an objective standard, an ordinary person standing in Mr. Behrens’ shoes would not have prosecuted this claim if a reasonable inquiry had been conducted. Stated otherwise, Mr. Behrens did not have a “reasonably clear legal justification” to proceed based on his limited inquiry. Mr. Behrens signed the Petition and Amended Petition for an “improper purpose.” The District’s Request for Sanctions The District proved that its lawyers expended approximately 98.8 hours in responding to the challenge brought by Mr. Behrens and that the District incurred $426.25 in costs. An hourly rate of $125.00 per hour is a reasonable rate. The hours expended by District lawyers were reasonable. The costs incurred were reasonable. The District requests that sanctions be imposed in the amount of $12,350.00 for attorney's fees and $426.25 in costs. For the reasons more fully stated in the Conclusions of Law, based on the totality of the facts presented, the imposition of a sanction against Mr. Behrens in the amount of $500.00 (for costs and a small portion of fees) is appropriate.
The Issue Whether Petitioner Ross has standing to challenge the issuance of the WUP? Whether the District should approve the Application and enter a final order that issues the WUP?
Findings Of Fact The Parties Petitioner Ross Petitioner Ross is a resident of Pinellas County, (referred to by him at hearing as "the most urbanized county in the State of Florida"). Besides residing there, Petitioner Ross operates a farm on his property in the County. The City's experts reasonably projected and mapped a 0.5 foot drawdown contour surrounding the well field that is the subject of this proceeding. The contour defines "the cone of depression" associated with the well field. See Tr. 136. Mr. Ross' property is outside the cone of depression, to its south and west. The overall groundwater gradient in the area of the well field is from the east to the west. The water pumped from the well field does not pull water from the west because the pumping withdrawal will not reduce the potentiometric surface gradient enough to reverse the current gradient. Mr. Ross' property and the well on his property are "way outside," tr. 138, the well field and the 0.5 drawdown contour surrounding the well field. Based on the amount of drawdown reasonably projected by the well field, the effect on Mr. Ross' property could not be measured because it would be so slight. If the water in his well were to rise after the WUP is implemented, it would be impossible to tell whether the water rose "because the pump's turned off or because it rained the day before." Tr. 163. The District The District is the administrative agency charged with the responsibility to conserve, protect, manage, and control the water resources within its geographic boundaries. The District administers and enforces chapter 373, and the rules promulgated pursuant thereto. Among those rules are those that relate to the consumptive use of water found in chapter 40D-2. The City The City of Tarpon Springs is the applicant for the WUP that is the subject of this proceeding. The City's application seeks to modify an existing permit. The Existing Permit The City has an existing Water Use Permit (the "Existing Permit") from the District. Originally granted in 1976, it allows for withdrawal of fresh groundwater for public supply. The Existing Permit was last renewed in October of 2005 for a ten-year period. It expires in October of 2015. Under the Existing Permit, the withdrawal capacity is 1.38 million gallons per day annual average and allows for seven production wells. The Application and its Modification The City submitted the Application in July, 2008. The Application at that time was for 25 wells in a brackish water well field for a proposed brackish groundwater reverse osmosis plant that the City plans to build. The City's intent originally was to apply for a permit separate from the Existing Permit.1/ In September of 2009, however, the City requested that the Application be considered a modification of the Existing Permit. In honoring the request, the District changed the number assigned to the Application to "20000742.010."2/ The Application was also modified with regard to the number of production wells in the brackish well field. The number was reduced from 25 to 22, "due to land acquisition efforts indicating that the maximum number of wells . . . required for the project would be 22." Tr. 54. The Application contains an introduction that summarized the City's water supply system and its water supply plans, a completed Individual Water Use Permit Application form, a completed Public Supply Supplemental form, and an Impact Analysis Report (the "Report"). The Report states that the ground-water flow model "MODFLOW"3/ was used to perform the impact analysis. Assessment of average annual and peak month withdrawal impacts in the Upper Floridan and surficial aquifers used the SWFWMD District Wide Regulation Model Version 2 ("DWRM2"). One of the enhancements the DWRM2 offers over earlier model versions is "integrated focused telescopic mesh refinement (FTMR) which allows the model grid user to refine the model grid spacing to focus on specific areas within the District."4/ The Report included the FTMR model grid, total drawdown scenarios in the Upper Floridan Aquifer and the surficial aquifer, and a peak month drawdown scenario. The Application also included a summary of the regional hydro-geology, a summary of the City's wastewater system, a description of the City's potable water supply, an historical operating protocol and a proposed well field management plan for the City's new brackish water well field, a service area and well field location aerial, a table showing the general hydrostratigraphy in northern Pinellas County, a summary of seasonal fluctuations which addressed the conditions for issuance of a permit as set forth in rule 40D-2.381, a summary of the City's reclaimed water system, well location maps, wetland maps, Water Use Permit maps and schedules, the City's well field protection ordinance, maps pertaining to the proposed service areas, a water conservation letter, and water conservation information. The 22 new production wells in the brackish water well field will provide enough water once treated at the proposed reverse osmosis membrane treatment plant to enable the City to supply the anticipated potable water demand for all of the City's customers through the year 2015. Installation of the additional production wells will increase the annual average quantity of groundwater pumpage to 4,200,000 gallons per day ("gpd") and the peak month quantity to 6,300,000 gpd. Review of the Application by the District led to four requests by the District for additional information. The City responded to each. The responses included a well construction and aquifer testing program report, a Water Quality/Water Level Well Impact Mitigation Plan, a Water Quality Action Plan, a revised Water Quality/Water Level Well Impact Mitigation Plan, a revised Water Quality Action Plan and a second revision of the Water Quality Action Plan, a second Water Quality/Water Level Well Impact Mitigation Plan, a proposed Environmental Monitoring Plan, a third revised Water Quality Action Plan, a third revised Water Quality/Water Level Well Impact Mitigation plan, and the final Environmental Monitoring Plan. Draft Water Use Permit On October 8, 2010, the District gave notice of its intent to issue a permit that would modify the City's Existing Permit for public supply use. Attached to the notice is a Draft WUP. The modification includes the development of a brackish water well field with 22 additional production wells to allow the City to self-supply the anticipated potable water demand in 2015 for a customer base of approximately 34,259 persons. The annual average quantity authorized by the WUP is 4,200,000 gpd and the permitted peak month quantity increases to 6,300,000 gpd.5/ Special conditions of the Draft WUP require the City to maintain meters on existing and proposed withdrawal points; record and report monthly meter readings; confirm meter accuracy every five years; monitor and report the water quality and aquifer water levels; maintain an adjusted per capita rate of 150 gpd or less; conduct and report water audits; submit annual reports of residential water use, reclaimed water supplied, per capita water use rates, and well field operations; investigate withdrawal-related well complaints; conduct a well field inventory prior to the activation of the proposed production wells; comply with the environmental monitoring plan; set water quality concentration limits prior to the activation of the proposed production wells; and submit an Annual Water Quality Report and an annual Well Field Report. Criteria in Rule for Issuance of WUPs The District utilizes rule 40D-2.381 (the "Rule") in its review of water use permit applications. The Rule opens with the following: In order to obtain a Water Use Permit, an Applicant must demonstrate that the water use is reasonable and beneficial, is consistent with the public interest, and will not interfere with any existing legal use of water . . . Rule 40D-2.381(1), Tab 1 of the Binder Containing the Matters Officially Recognized, pp. 7-8. The Rule requires that the applicant make the required demonstrations through the provision of "reasonable assurances, on both an individual and a cumulative basis that the water use," id., will meet 14 conditions listed in subsections (a) through (n).6/ Condition (a) Condition (a) requires that the City demonstrate that the water use is necessary to fulfill a certain reasonable demand. To meet this condition, the City provided a population estimate through the end of the permit term and also provided a per capita rate that the City had used in the last five years. Calculations set forth in a table prepared at the request of the City show the population projections and projected water demands over a period from 2008 through 2030. These calculations provide reasonable assurances that the proposed water use meets Condition (a). Condition (b) Condition (b) requires that the City must demonstrate that the water use will not cause quantity or quality changes that adversely affect the water resources, including both surface water and groundwater. The City provided a groundwater model showing the anticipated groundwater drawdowns within the Upper Floridan and surficial aquifers. The City also completed a study on the wells within the sections of the actual proposed well field. Based upon the modeling, the drawdowns are not large enough to cause any impacts to quantity or quality of the water in the area. The City has a Water Quality/Water Level Well Impact Mitigation Plan, should there be any complaints of impact, to correct any problems after implementation of the WUP. The well field is designed with 22 supply wells. All 22 wells need not be operated at the same time to meet the water demand. Wells beyond those needed by demand have been designed into the well field so that there can be rotational capacity. Pumping at lower rates from among the 22 wells on a rotational basis is a management tool for protecting the resource and minimizing the effects of the withdrawals. The City's monitoring program provides for the collection of water levels from a large number of wells either on a monthly or quarterly basis to assess water level fluctuations in the Upper Floridan and surficial aquifers. The City also has numerous wells that will sample for chloride sulfates, total dissolved solids (TDS) and other water quality constituents on a monthly and quarterly basis to ensure that the conditions of issuance continue to be met. The City will submit groundwater pumping data on a monthly basis from all the production wells so that the District can determine that the City is indeed adhering to the quantities reflected in the WUP. Groundwater in the Upper Floridan Aquifer flows in a westward direction towards the Gulf of Mexico. The location of the proposed wells is in an urban land use area near the Gulf Coast. The wells will capture brackish groundwater that would otherwise flow westward into the Gulf. Brackish groundwater from the City's service area is the lowest quality water available for public supply in the area. The City plans to construct a reverse osmosis facility to utilize available brackish groundwater. The brackish groundwater pumped from the well field is an alternative supply source. Isolated from the regional system, it will be used for public supply in the service area. The high number of low-capacity wells will provide rotational ability for the City to manage the quantity and quality of the water resource in the area of the well field. Maximum drawdown within the well field area due to the average annual withdrawal is approximately 3 feet, with an additional 1.5 feet during peak month withdrawal. This amount of drawdown is not likely to impact other wells in the area. Condition (c) Condition (c) requires the City to demonstrate that water use will comply with the provisions of 4.2 of the WUP Basis of Review, incorporated by reference in rule 40D-2.091, regarding adverse impacts to wetlands, lakes, streams, estuaries, fish and wildlife or other natural resources. The Anclote River and associated wetlands are tidally influenced and will not be adversely impacted by the proposed withdrawal. Other wetlands in the well field area examined by a District biologist identified several isolated wetlands of concern. Isolated wetlands are generally more sensitive to withdrawal of groundwater than wetlands connected to larger basins. Initially, the City's proposed drawdowns were deemed to be unacceptable to the District because of the impact to the isolated wetlands of concern. As a first step, the City reduced the quantities of water to be withdrawn. Subsequently, an extensive Wetland Monitoring Plan was developed that included a mitigation plan if adverse impacts did occur to wetlands. Storm-water runoff will be the primary factor controlling the functions of the wetland areas. Mitigation measures, should any adverse impact become too great, include reduction of well field pumping, augmentation with well water, potable water and other feasible sources, and the purchase of mitigation credits. Condition (d) Condition (d) requires the City to demonstrate that the water use will not interfere with a reservation of water as set forth in rule 40D-2.302. The groundwater modeling that the City provided the District indicates that there are no adverse impacts to the minimum flows and levels ("MFLs") in the Anclote River or the water level at the Tarpon Road Deep Well. There are, therefore, no impacts to reservations of water. Condition (e) Condition (e) requires the City to demonstrate that the water use will comply with the provisions of 4.3 of the WUP Basis of Review,7/ regarding MFLs. The closest MFL site is the Upper Floridan Aquifer monitoring well called Tarpon Road Deep, located approximately 2.4 miles southeast of the well field. The impact analysis model results show that at the annual average withdrawal rate of 4.20 million gallons per day ("mgd") approximately 0.1 feet of drawdown at this MFL site is currently projected to occur, assuming static pumping conditions in all other regional groundwater withdrawals. This amount of drawdown will not cause the water level at the Tarpon Road Deep Well to fall below its minimum level. The District is in the process of setting an MFL for the Anclote River. Based on the operation of the new well field and the City's continued operation of their freshwater discharge to the Anclote River from their reclaimed water facility, there will be no impact to the Anclote River. Condition (f) Condition (f) requires the City to demonstrate that the water use will utilize the lowest water quality the City has the ability to use, provided that its use does not interfere with the recovery of a water body to its established MFL and it is not a source that is either currently or projected to be adversely impacted. The City is using brackish water, the lowest water quality available to be used for public supply. The City will be treating it at a reverse osmosis water treatment plant. Water of this quality is not available for others to use without special treatment. Based upon the modeling provided by the City, there are no anticipated impacts to MFLs or any other water body resources. Condition (g) Condition (g) requires the City to demonstrate that the water use will comply with section 4.5 of the WUP Basis of Review,8/ regarding saline intrusion. Groundwater in the Upper Floridan Aquifer in the area of the well field is brackish. The well field's design allowing well rotation minimizes changes in water quality during operation. The amount of drawdown and the fact that water levels will remain above sea level suggests that saline water intrusion will not occur. The reported potentiometric surface in the area of the well is approximately five feet NGVD while the land surface is roughly five feet higher at approximately ten feet NGVD. The City's monitoring and mitigation programs will address adverse impacts from saline intrusion should they occur. Condition (h) Condition (h) requires the City to demonstrate that the water use will not cause the pollution of the aquifer. Soil and groundwater contamination is documented at the Stauffer Management Company site located approximately 3,000 feet west of the well field. The drawdown from the well field is calculated to be about one foot at the Stauffer site. That level of drawdown will not induce migration of contaminants because the upward head differential from the Upper Floridan Aquifer to the surficial aquifer will be altered and the Stauffer site is down gradient of the well field. Testimony from Mr. Wiley established that the aquifers should not be contaminated by the City's withdrawals despite the presence of the Stauffer site: [T]here is a known source of contamination approximately 3,000 feet from the new well field to the west, Stauffer Chemical Company. With the small amount of drawdown that's caused in the Upper Floridan aquifer and the surficial aquifer, there's no potential for the withdrawals to cause pollution of the aquifer. Tr. 254-55. Mr. Wiley's opinion was reached primarily based on the use of the groundwater flow model to determine the drawdown at the Stauffer site and through review of groundwater levels in the Floridan and the surficial aquifers. The United States Environmental Protection Agency (the "EPA") is in charge of managing the contamination at the Stauffer site. A remediation plan has been developed based, in part, on EPA records. The remediation plan includes the construction of a barrier wall in the subsurface around the contaminated area to prevent contaminated groundwater from migrating. The City's groundwater monitoring wells will detect movement of contaminants toward the well field. The monitoring of the wells and the mitigation plan will assist in preventing pollution of the aquifers. Condition (i) Condition (i) requires the City to demonstrate that the water use will not adversely affect offsite land uses existing at the time of the application. Primary existing land uses within the City's service area are residential, commercial, and light industrial. The proposed withdrawal will not adversely impact these land uses as shown in Figure 10 of the City Exhibit 1. Five sink holes are known to exist in the general area around the well field. The closest is approximately 1,000 feet from a proposed well location. Maximum drawdown at the distance is approximately 2 feet. This amount of drawdown does not significantly increase the potential for sinkhole activity. Condition (j) Condition (j) requires that the City demonstrate the water use will not adversely impact an existing legal withdrawal. The Pasco County Utilities' wells located to the north of the well field are listed on the WUP as plugged. Wells owned by Crest Ridge Utility Corp. are located within 0.5 to 0.8 miles of the well field. Drawdown at these wells, due to the average annual withdrawal, is approximately one foot, with an additional 0.4 feet during peak month withdrawal. This amount of drawdown will not create a water level impact at these wells. Maximum drawdown at domestic wells in the area due to the average annual withdrawal is approximately three feet, with an additional 1.5 feet during peak month withdrawal. This amount of drawdown is not likely to impact other wells in the area. The City's mitigation plan addresses any adverse impact that might occur from the City's withdrawal. Condition (k) Condition (k) requires the City to demonstrate that the water use will incorporate water conservation measures. The existing per capita use rate for the City's service area is 110 gpd. Its position well below the district goal of 150 gpd per person demonstrates that the City's water conservation measures are effective. The City uses an inclined block rate structure which encourages water conservation. It also encourages water conservation through a reclaimed water system that encourages conservation of public water supply. It currently uses a little over one million gallons per day of reclaimed water. The City also conserves water through a leak protection program, a water loss audit program, adherence to the District's watering restrictions and provision of a low-flow toilet rebate program through the County, a landscape code, and the provision of educational materials to users. Condition (l) Condition (l) requires the City to demonstrate that the water use will incorporate the use of alternative water supplies to the greatest extent possible. The City has an extensive reclaimed water program. It provides reclaimed water for its golf course, for residential irrigation, for public parks and recreation, and for public schools. The City expanded its reclaimed water storage system recently by doubling the amount of reclaimed water that it is able to store for redistribution. Condition (m) Condition (m) requires the City to demonstrate that the water use will not cause water to go to waste. The City performs an unaccounted-for water audit of its system as required by a special condition of its existing WUP. The unaccounted-for water use is approximately 4 percent, well below the District guidelines. Furthermore, the City's per capita use rate of 110 gpd is well within the District's goal of 150 gpd per person. The City also has an extensive reclaimed water system which offsets potable water supply and prohibits wasted drinking water as an irrigation source. Condition (n) Condition (n) requires that the City demonstrate that the water use will not otherwise be harmful to the water resources within the District. Facts found above support a conclusion that the City has provided reasonable assurances that it meets this condition. In addition, the water that is pumped locally by the City will offset the need for ground water that would have otherwise been obtained from elsewhere in the region. Notices The District published its Notice of Proposed Agency Action in the Tampa Tribune on October 22, 2010. The District published its Notice of Proposed Agency Action in the St. Petersburg Times on October 24, 2010.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Southwest Florida Water Management District enter a Final Order determining that Petitioner Ross lacks standing and that his Petition, therefore, be dismissed. Should it be determined in a Final Order that Petitioner Ross has standing, it is recommended that the Southwest Florida Water Management District enter a Final Order that issues Water Use Permit No. 20000742.010 to the City of Tarpon Springs. DONE AND ENTERED this 14th day of April, 2011, in Tallahassee, Leon County, Florida. S DAVID M. MALONEY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 14th day of April, 2011.