Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. HARRY L. WILSON, 84-002424 (1984)
Division of Administrative Hearings, Florida Number: 84-002424 Latest Update: Mar. 21, 1985

Findings Of Fact Harry L. Wilson is the holder of a registered roofing contractor's license from the Florida Construction Industry Licensing Board. The license, Number RC 0041328, was first issued in March of 1982. The license was issued in the name of Harry L. Wilson Roofing, 1943 Hardy Street, Jacksonville, Florida, with the Respondent as qualifier. The Respondent has been the qualifier of Harry L. Wilson Roofing at all times relevant to this proceeding. On December 6, 1984, the Respondent and Robbie L. Hicks, entered into a written contract (Petitioner'S Exhibit 2). Pursuant to this written contract (hereinafter referred to as the "Contract"), the Respondent agreed to perform the repair work specified in the Contract in a "professional manner" and Ms. Hicks agreed to pay the Respondent $2,395.00. The property to be repaired is rental property owned by Ms. Hicks. The property is located at 1508 Eaverson Street, Jacksonville, Florida. The Respondent commenced work sometime during the early part of 1983. Shortly after commencing work, however, the Respondent and Ms. Hicks began having disagreements as to the work to be performed and the quality of the Respondent's work. These disagreements continued after the Respondent completed the work in November of 1983. Ms. Hicks testified that the work that the Respondent completed was done in an unprofessional manner and that the Respondent had not completed all of the work that he had agreed to perform. In particular, Ms. Hicks testified that the Respondent had failed to paint the interior of the house beige as required by the Contract, had failed to remove saw dust and other debris from the house following completion of the work, had failed to finish cabinets installed in the house, had failed to repair screens and generally had not performed in the manner he had agreed to perform. Ms. Hicks paid the Respondent all but $410.00 of the contract price. The Respondent testified that all off the work called for pursuant to the Contract had been performed. According to the Respondent, he had performed some work not required by the Contract and had not performed other work requested by Ms. Hicks because the work was beyond the scope of the Contract. The Respondent also stated that the work which Ms. Hicks expected would have cost considerably more than the price agreed upon in the Contract. The Respondent did not perform all of the work specified in the Contract in a "professional manner" as required by the Contract. Based upon the testimony of Mr. Claude Bagwell, Deputy Chief, Building and Zoning, Inspection Division of the City of Jacksonville, it is clear that no permit was issued by the City of Jacksonville to perform the work required by the Contract. The only permits issued with regard to Ms. Hicks' rental property was a permit issued in 1961 and the original building permit issued in 1949. Additionally, due to the fact that no Florida registered roofing contractor's license in the name of "Harry L. Wilson Roofing" had been filed with the City of Jacksonville, no permit could be issued to Harry L. Wilson Roofing with regard to the Contract. The Respondent admitted that he had not obtained a permit to perform the work required by the Contract. The Respondent indicated that he had not obtained a permit because he was not aware that one was required in order to perform the work. He did indicate that he had obtained permits to perform other jobs. The Respondent could not, however, have obtained permits for other jobs because no license issued in the name of Harry L. Wilson Roofing had been filed with the City of Jacksonville. The Respondent did take the examination required in order to obtain a registered roofing contractor's license. The Petitioner suggested in its Proposed Findings that the "permit requirement was explained" when the Respondent took the exam. No evidence to support such a finding was presented at the hearing. The Respondent in entering into the Contract clearly used the name "Wilson Recycling". Nowhere on the Contract is the name "Harry L. Wilson Roofing" used. The Respondent ultimately admitted that no Florida license authorizing the use of the name "Wilson Recycling" had been obtained by him. The Respondent, however, when initially asked whether a Florida license in the name of "Wilson Recycling" had been obtained indicated that such a license had been issued. On further examination, however, the Respondent testified that an occupational license in the name of "Wilson Recycling' had been obtained by him and not a Florida license. The work to be performed pursuant to the Contract was beyond the scope off the Respondent's license. As pointed out by Mr. Bagwell the work to be performed pursuant to the Contract would require licensure as a registered residential contractor or more.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That count I of the Administrative Complaint filed against the Respondent be dismissed. It is further RECOMMENDED: That Respondent be found guilty of violating Section 489.129 (1)(g), Florida Statutes (1983), by contracting in a name other than the name as set forth on the Respondent's license. It is further RECOMMENDED: That Respondent be found guilty of violating Section 489.129(1)(j), Florida Statutes (1983), by failing in a material respect to comply with the provisions of Section 489.119(2) and(3), Florida Statutes (1983), in that the Respondent failed to qualify the business name "Wilson Recycling" with the Construction Industry Licensing Board. It is further RECOMMENDED: That Respondent be found guilty of violating Section 489.129(1)(j), Florida Statutes (1983), when he failed in a material respect to comply with the provisions of Section 489.117(2), Florida Statutes (1983), by contracting to perform and actually performing work beyond the scope of his Florida contracting license. It is further RECOMMENDED: That Petitioner suspend Respondent's roofing contractor's license for a period of three (3) months. DONE and ENTERED this17th day of December, 1984, in Tallahassee, Florida. LARRY J. SARTIN Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 17th day of December, 1984. COPIES FURNISHED: H. Reynolds Sampson, Esquire Staff Attorney Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Harry L. Wilson 1943 Hardee Street Jacksonville, Florida 32209 Mr. Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (4) 120.57489.117489.119489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs DANIEL FRANK MOLINARI, 94-005259 (1994)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida Sep. 22, 1994 Number: 94-005259 Latest Update: Mar. 20, 1997

Findings Of Fact At all times material hereto, Daniel Frank Molinari (Respondent) was a certified plumbing contractor, being licensed by the Florida Construction Industry Licensing Board (CILB) and having been issued license numbers CF C021437 and CF C041671. On or about March 20, 1990, the State Attorney of Dade County, Florida charged Respondent by Information with an attempted offense against intellectual property in violation of Sections 815.04(3) and 777.04, Florida Statutes, a misdemeanor: "[Respondent] on the 19th day of February 1990 . . . willfully, knowingly, without authorization, attempt to disclose or take data, programs, or supporting documentation, to wit: The CONTENTS of a CONTRACTOR'S LICENSING EXAMINATION, which is confidential as provided by law, residing or existing internal or external to a computer, computer system, or computer network. . ." On or about July 30, 1990, Respondent pled nolo contendere to the misdemeanor charge. Based upon Respondent's plea of nolo contendere, the Dade County Judge entered a judgement finding Respondent guilty as charged, withholding adjudication and imposing costs in the amount of $300.00. In the Dade County judicial circuit, a judge usually makes a finding of guilt when a defendant pleads nolo contendere even if adjudication is withheld. Typically, items in a CILB examination are reused on subsequent exams. However, each examination must contain a certain percentage of new items. Because of Respondent's attempted act, the CILB considered the items on the contractors examination in 1990 to be compromised and, therefore, unusable for subsequent examinations. The 1990 CILB examination consisted of two hundred and twenty-one (221) items. Consequently, 221 new items had to be developed at a cost of approximately $100.00 per item. On or about June 10, 1993, Respondent submitted to the CILB a Certification Change of Status Application (Application) to activate his inactive certified plumbing contractor license (license number CF C041671). Question 7(H) of the Application inquired whether Respondent had ever "Been found guilty of any crime other than a traffic violation". He responded "no" to the question. The Application required an affirmation, and Respondent so affirmed, that "these statements are true and correct and I recognize that providing false information may result in a fine, suspension, or revocation of my contractor's license." Respondent's request for activation could have been denied if he had responded "yes" to question 7(H) of the Application.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Construction Industry Licensing Board enter a final order: Dismissing Count II of the administrative complaint in DOAH Case No. 94-5259; Dismissing all counts of the administrative complaint in DOAH Case No. 95-0199; Revoking Respondent's licenses; Imposing costs for the investigation and prosecution to be determined by the construction Industry Licensing Board. DONE AND ENTERED this 29th day of August, 1995, in Tallahassee, Leon County, Florida. ERROL H. POWELL Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of August, 1995.

Florida Laws (4) 120.57489.129777.04815.04
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DANIEL A. ARGUELLES, 85-001293 (1985)
Division of Administrative Hearings, Florida Number: 85-001293 Latest Update: Oct. 01, 1985

Findings Of Fact At all times relevant hereto, Respondent, Daniel A. Arguelles, held certified general contractor license number CG C004252 issued by Petitioner, Department of Professional Regulation, Florida Construction Industry Licensing Board. When the events herein occurred, he was qualified as an individual. He presently resides at 9455 Southwest 78th Street, Miami, Florida. Respondent's brother is J. Alejandro Arguelles. Alejandro holds an inactive contractor's license which has been delinquent since July, 1979. In June, 1984, Alejandro was contacted by an individual named Louis Taylor. Taylor told Alejandro that David Reynolds, who resided at 753 Northwest 116th Street, Miami, Florida, wished to add a room to his house. After meeting with Reynolds, Alejandro had plans for the addition prepared, provided an estimate for the job, and gave Reynolds a business card reflecting that he was a licensed general contractor. Reynolds and Alejandro then jointly executed a contract on July 26, 1985, wherein it was provided that A. Arguelles & Associates would construct the room addition for $19,000. The letterhead on which the contract was executed indicated that Alejandro was a general contractor. However, the entity "A. Arguelles & Associates" has never been qualified by any licensee to do construction work in the state. During all negotiations with Reynolds, Alejandro never mentioned that Daniel would be the contractor on the project although Alejandro did advise him that a general contractor would be required. All checks were made out to Alejandro, and Alejandro ordered all supplies and materials used on the project. In addition, Alejandro was at the job site on a regular basis. Prior to signing the contract on July 26, Daniel was approached by Alejandro and asked if he would be willing to act as contractor on the project. Daniel agreed, and thereafter pulled a job permit and used his license number on all pertinent documentation. Other than visiting the job site on a "couple" of occasions, he had no other contact with the project. He never met or had any contact with Reynolds. The actual amount of work done on the project by Alejandro and Daniel amounted to only $5,000.00 and consisted of constructing the foundation up to the tie beam. There is no evidence that this phase of the work was performed in a negligent or incompetent manner.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent be found guilty as set forth in the Conclusions of Law portion of this order, and that he be fined $500.00. DONE and ORDERED this 1st day of October, 1985, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, FL 32301 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 1st day of October, 1985. COPIES FURNISHED: Salvatore A. Carpino, Esquire 130 N. Monroe St. Tallahassee, FL 32301 Fred Roche, Secretary Dept. of Professional Regulation 130 N. Monroe St. Tallahassee, FL 32301 Nancy M. Snurkowski, Esquire 130 N. Monroe St. Tallahassee, FL 32301 J. K. Linnan, Executive Director Florida Construction Industry Licensing Board P. O. Box 2 Jacksonville, FL 32201 Mr. Daniel A. Arguelles 9455 S.W. 78th Street Miami, FL 33173

Florida Laws (3) 120.57489.105489.129
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. VICTOR S. DAVIS, 85-001963 (1985)
Division of Administrative Hearings, Florida Number: 85-001963 Latest Update: Dec. 03, 1985

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following facts were found: At all times material to these proceedings, the Respondent, Victor S. Davis, held a registered general contractor's license, numbered RG 0013635 issued by the State of Florida, Department of Professional Regulation, Construction Industry Licensing Board in April, 1973. At all times material to these proceedings, Respondent's general contractor's license, number RG 0013635, was in a delinquent status and had been in a delinquent status since July 1, 1977. Respondent failed to renew his license after June 30, 1975 but in May, 1976 made application to reinstate license number RG 0013635 which was approved and reinstated on an active status by Petitioner in May, 1976 and issued to Respondent, Victor S. Davis, qualifying Conch Construction Corp., of Key West, Florida. There was no evidence that the reinstated license was issued for Monroe County, Florida or that Respondent ever held a certificate of competency for Monroe County, Florida. At all times material to these proceedings, Respondent was an officer (Secretary) of Classic Marketing and Development, Inc. (Classic). On July 28, 1983, the Respondent, as Secretary of Classic, entered into a contract with William Dees to construct a shell home on the Dees' property located at Lot 14, Block 7, Breezeswept Estates, Ramrod Key, Florida for a contract price of $27,000.00. On September 13, 1983, William Dees applied for and obtained building permit No. 10902-A as owner/builder for the construction of the Dees's home. Construction of the Dees home began on or about September 13, 1983. Gregory H. O'Berry, President of Classic had knowledge of, and approved of, Respondent entering into contracts for construction of homes in Monroe County, Florida, including the contract with Dees. O'Berry was aware that Respondent did not hold a certificate of competency in Monroe County, Florida and that Respondent's registered general contractor's license did not cover contracting in Monroe County, Florida. O'Berry understood that Phillip A. Braeunig, a properly licensed general contractor in Monroe County, Florida, was acting as the general contractor for Classic- in the construction of homes by Classic, including the construction of the Dees home. Braeunig did not act as general contractor on the construction of the Dees' home. Respondent supervised the contraction of the Dees' home, until Respondent abandoned the construction of the Dees' home, and in performing these supervisory duties fulfilled the responsibilities of a general contractor. No other officer or authorized agent of Classic had any responsibility for the supervision of, or acted in any manner as a general contractor, in the construction of the Dees' home. Braeunig prepared and submitted to Respondent an application to qualify Classic with Petitioner using Braeunig's license but this application was never filed with Petitioner during- anytime material to these proceedings. Classic was never qualified by anyone, including Respondent or Braeunig, at any time material to these proceedings. Braeunig~acted as general contractor for Classic on the Conti home, which was in the beginning stages of Classic and prior to the Dees' job. Braeunig was brought into Classic for the purpose of acting as general contractor because of the Respondent's invalid license.

Recommendation Based upon the findings of fact and conclusions of law recited herein, it is RECOMMENDED that the Board enter a final order Dismissing Count I of the Amended Administrative Complaint filed against the Respondent. It is further RECOMMENDED that the Board enter a final order finding Respondent guilty of the violation charged in Count II of the Amended Administrative Complaint and for such violation it is RECOMMENDED that the Board suspend the Respondent's registered general contractor's license for a period of two (2) years and assess the Respondent with an administrative fine of $500.00, stay the suspension and place Respondent on probation for a period of two (2) years, provided the Respondent pays the $500.00 fine within ninety (90) days. Respondent's failure to pay the $500.00 fine within the time specified will result in his registered general contractor's license being suspended for a period of two (2) years with the requirement that when the fine is paid and the suspension lifted, the Respondent must appear before the Board for reinstatement of his license. Respectfully submitted and entered this 3rd of December, 1985, in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, FL 32301 (904) 488-9675 FILED with the Clerk of the Division of Administrative Hearings this 3rd day of December, 1985. APPENDIX Department of Professional Regulation, Construction Industry Licensing Board v. Victor S. Davis, Division of Administrative Hearings Case No. 85-1963 Ruling on Petitioner's Proposed Findings of Fact: Adopted in Finding of Fact No. 1 except for the statement that "Respondent's license was issued for Okaloosa County only" which is rejected as not being based upon competent substantial evidence. Hearsay alone is not sufficient to support a finding of fact. Adopted in Finding of Fact No. 1 except for statement that "said license has been delinquent since July, 1981" which is rejected as being contrary to the evidence in Petitioner's Exhibit No. 1 which shows delinquent status as of July 1, 1977. Adopted in Finding of Fact No. 3. Rejected as a conclusion of law rather than a proposed finding of fact. Considered as background information and not as a finding of faet. Adopted in Finding of Fact No. 4. Adopted in Finding of Fact No. 5. Adopted in Finding of Fact Nos. 4 and 5. Adopted in Finding of Fact Nos. 5 and 7. Adopted in Finding of Fact No. 5. Adopted in Finding of Fact No. 6. Adopted in Finding of Fact No. 6. Adopted in Finding of Fact No. 9. Adopted in Finding of Fact No. 9. Adopted in Finding of Fact No. 9. Adopted in Finding of Fact No. 9. Adopted in Finding of feet No. 10 Adopted in Finding of Fact No. 10 Rejected as a conclusion of law rather than a proposed finding of fact. Respondent did not submit Proposed Findings of Fact. COPIES FURNISHED: James Linnan, Executive Director Department of Professional Regulation Construction Industry Licensing Board P. O. Box 2 Jacksonville, FL 32202 Nancy M. Snurkowski, Esq. Department of Professional Regulation 130 North Monroe Street Tallahassee, FL 32301 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, FL 32301 Victor S. Davis 2169 North Hercules Avenue Clearwater, FL 33575 and 6290 Sandcrest Circle Orlando, FL 32819

Florida Laws (8) 120.57489.115489.117489.119489.127489.129775.082775.084
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. GEORGE E. FELD, 86-004429 (1986)
Division of Administrative Hearings, Florida Number: 86-004429 Latest Update: Apr. 09, 1987

Findings Of Fact At all times relevant hereto, respondent, George E. Feld, held certified general contractor license number CG C021801 issued by petitioner, Department of Professional Regulation, Florida Construction Industry Licensing Board. Feld has been a licensed contractor in Florida since June 1982. He has qualified George E. Feld and Associates, Inc. under his license and operates the business at 2131 Northeast 205th Street, North Miami Beach, Florida. After submitting the low bid, on or about March 1, 1985 George Feld and Associates, Inc. entered into a contract with the City of Tamarac to construct a 5,500 square foot recreation building for the City. The negotiated contract price was $195,950. The contract called for commencement of the project within ten days after the contract was signed and completion by July 27, 1985. Sometime prior to March 20, 1985, Feld met one David P. McCall and Marvin Weiss at a motel in North Miami. McCall was interested in doing work on the Tamarac project. He gave Feld a business card with the name "Arrow Head Development Corporation, Inc." printed on it, and which stated the firm was "state certified" and "licensed" as a general contractor. Feld also noted that Weiss held a general contractor's license, and he assumed that McCall and Weiss were working together. Relying on McCall's card, and later representations by McCall, but without checking with petitioner's office to verify if McCall or Arrow Head were licensed or qualified, Feld agreed to subcontract out the shell and sewer work on the Tamarac project to Arrow Head. To this end, Feld and Arrow Head entered into two contracts on March 20, 1985, for Arrow Head to perform the shell and sewer work. On June 21, 1985 McCall submitted a written "proposal" to Feld for the shell work on the job. The proposal had the following words and numbers typed on its face: "State License Number: #CGC 05961." It was not disclosed whose license number this was. Although McCall denied typing this document (because he does not personally know how to type), he did not deny that it was placed on the document at his direction or with his knowledge. It was not until sometime later that Feld learned that Arrow Head was not qualified by any licensee. Because of his mistaken belief that Arrow Head was qualified, Feld had never qualified that firm. Even so, there was no evidence that Feld intended to allow an unqualified firm to perform the work. Work proceeded on a timely basis as required by the contract. Feld visited the job site daily, and supervised all activities, including those performed by McCall. He routinely inspected the work, verified that it was being done according to specifications, and made corrections where needed. The job specifications called for trusses that were over forty feet in length. Because of this, and pursuant to the South Florida Building Code (Code), it was necessary for the City to hire an engineer to oversee their installation. The City hired one George Fink as engineer to supervise this phase of the project. However, Fink's responsibility was limited to just that, and once the installation was completed, Feld resumed responsibility for the remainder of the job. Trusses are a manufactured roof member and may vary in length, height and pitch. In this case, they were designed in the form of a cathedral roof, and were in excess of forty-seven feet in length. Further, because of the building's design, there were a number of trusses to be installed. The installation of the trusses was begun around 9:00 a.m. on Friday, June 27, 1985 and finished by 2:00 p.m. that same day. As required by the Code, Fink was present and supervised the installation of the trusses on the top of the shell. He confirmed at hearing that they were properly installed. The problem herein arose early that day when Fink had noticed that the building plans did not provide for lateral bracing of the trusses. However, according to Fink, this was not unusual since plans do not normally provide for lateral bracing. Even so, Fink told an unnamed person who "appeared to be the fellow running the erection crew" that lateral bracing should be added to the center and two side core members and that the four trusses on each end needed additional bracing. Fink also suggested to this unnamed individual that sheathing be added "as soon as possible" to the top and outside of the trusses to give added stability and protect them from wind damage and the like. In this regard, at hearing Fink conceded that it was "reasonable" for a contractor to erect trusses one day, and to place sheathing on them the following work day. Fink thought sheathing to be particularly necessary on this job since the trusses were high pitched," "long in length," and there were "no gables or anything in between to ... add any other support." By the end of the work day, the crew had placed the proper bracing on the trusses. However, no sheathing was applied. According to Fink, who was accepted as an expert in this proceeding, a prudent and competent contractor would be aware of the need for sheathing and added bracing because of the potential hazard of high winds caused by late afternoon thunderstorms in South Florida. By failing to place sheathing on the roof, Fink opined that Feld was grossly negligent and incompetent in the practice of construction on the Tamarac project. Sometime on late Sunday night or early Monday morning, most of the trusses on the roof collapsed. Some fell on an electrical wire running to the building. However, no injuries occurred. Only five trusses on the north side of the building remained in place. The City of Tamarac then filed a complaint with petitioner against Feld. The cause of the collapse was not disclosed, and even Fink was unable to state that the lack of sheathing was the cause of the accident. There was no evidence that strong winds or thunderstorms occurred on the night the trusses fell, or that bad weather was predicted when the work day ended on Friday afternoon. Feld acknowledged that no sheathing was placed on the trusses. He attributed this to the fact that the construction crew stopped work at 3:30 on Friday afternoon, and did not return to the job site until the following Monday morning. He intended to install the sheathing the following Monday but by then it was too late. This was in accord with the standard enunciated by Fink that it was not unreasonable for a contractor to erect trusses one day, and to place sheathing on them the following work day. Feld also stated that he was well aware of the need for bracing and sheathing on trusses by virtue of his long experience in the construction business. Feld hinted, but did not prove, that McCall may have been responsible for the accident because of bad blood between the two. In any event, he doubted that wind would have caused the trusses in question to fall. Finally, Feld pointed out that, even though city inspectors were present, no one had come to him on Friday afternoon and said the trusses might collapse over the weekend without sheathing. Feld is a graduate of the University of Buenos Aires with a degree in architecture, and has been engaged in the construction/architecture business for twenty-two years. He presently is an instructor of construction at Miami-Dade Community College. There is no evidence he has ever been the subject of a disciplinary action by the Board on any other occasion.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the administrative complaint against George E. Feld be DISMISSED, with prejudice. DONE AND ORDERED this 9th day of April, 1987, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of April, 1987.

Florida Laws (2) 120.57489.129
# 5
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs GEOFFREY C. GILL, 07-005536PL (2007)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Dec. 07, 2007 Number: 07-005536PL Latest Update: Nov. 12, 2019

The Issue Whether disciplinary action should be taken against Respondent's contracting license based on the violations as charged in the Administrative Complaint in this proceeding.

Findings Of Fact Based on the evidence and testimony of the witnesses presented and the entire record in this proceeding, the following Findings of Fact are made: Respondent is a certified contractor, having been issued License No. CGC 1506923 by the Florida Construction Industry Licensing Board. Respondent's licensure as a certified general contractor is "Current, Active." Respondent is the primary qualifying agent for his company, Transflorida Corporation, which has a Certificate of Authority as a Contractor Qualified Business, License No. QB 29658; that licensure is "Current." On or about July 3, 2006, Peter Cali entered into a written contractual agreement with Respondent, d/b/a Transflorida Corporation, for the construction of an addition to his residence at 2103 Lake Pickett Road, Orlando Florida. The original contract price between Respondent and Mr. Cali was $60,000.00. On July 3, 2006, Mr. Cali paid a total of $30,000.00 to Respondent. Respondent delivered some bricks to the Cali residence and had the septic tank pumped out. With the exception of the foregoing, Respondent failed to accomplish any meaningful work on the project. Respondent abandoned the project. Mr. Cali telephoned Respondent repeatedly requesting that Respondent perform the construction as agreed. Mr. Cali did nothing to inhibit Respondent's performance of the construction contract. Although requested, Respondent did not refund any money to Mr. Cali. Mr. Cali did not benefit as a result of the delivery of the bricks or the pumping of the septic tank. Mr. Cali's "out of pocket" damages are $30,000.00. Petitioner's total investigative cost for the case is $701.63. Respondent has been the subject of seven final orders revoking his professional license and fining him a total $230,000.00.2/

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered as follows: Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(g)2., Florida Statutes, as alleged in Count II of the Administrative Complaint, and imposing as a penalty an administrative fine in the amount of $5,000.00; Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(j), Florida Statutes, as alleged in Count III of the Administrative Complaint, and imposing as a penalty an administrative fine in the amount of $5,000.00; Finding Respondent guilty of having committed one violation of Subsection 489.129(1)(m), Florida Statutes, as alleged in Count IV of the Administrative Complaint, and imposing as a penalty an administrative fine in the amount of $5,000.00; Requiring Respondent to pay financial restitution in the amount of $30,000.00 to Peter Cali; Assessing cumulative cost of investigation and prosecution in the total amount of $701.63, which excludes costs associated with any attorney's fees; and Permanently revoking Respondent's license as a result of the numerous violations and the financial harm sustained by Peter Cali. DONE AND ENTERED this 10th day of June, 2008, in Tallahassee, Leon County, Florida. S JEFF B. CLARK Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 10th day of June, 2008.

Florida Laws (6) 120.57120.68455.227455.2273489.126489.129 Florida Administrative Code (2) 61G4-17.00161G4-17.002
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JACK A. MARTIN, 83-002941 (1983)
Division of Administrative Hearings, Florida Number: 83-002941 Latest Update: Jun. 26, 1984

Findings Of Fact The Respondent is a certified general contractor holding license number CG C016888. The Petitioner is an agency of the State of Florida charged with enforcing the provisions of Chapter 489, Florida Statutes, regulating the licensure and practice status and standards of building contractors in the State of Florida and enforcing the disciplinary provisions of that chapter. On December 14, 1981, Respondent contracted with Mr. and Mrs. Frank J. Sullivan to build the Sullivans a home in Sarasota County, Florida. Those parties entered into a contract whereby the Respondent was to be paid the actual cost of construction including all labor and materials plus a commission in the amount of 8 percent of the actual cost of construction, provided however, that the total contract price would not exceed $49,000, including actual costs and commission. In January, 1982, Respondent commenced work constructing the home. The Respondent worked on the home for several months and then abruptly ceased and abandoned construction without explanation on May 14, 1982. At this time the house was approximately 70 percent complete. At the time the Respondent ceased work on the project he had already been paid $47,362.29 or approximately 97 percent of the total contract price agreed to by the parties. The Sullivans thereafter had to pay $10,633.53 to subcontractors and materialmen who had been hired by the Respondent to supply labor and/or materials to the house, at the Respondent's direction, prior to his ceasing construction and leaving the job. Additionally, the Nokomis Septic Tank Company, Inc., the subcontractor who installed the septic tank, was owed $1,180.07 by the Respondent for the installation of the septic tank, which amount was to have been paid out of the total $49,000 contract price. The Respondent failed to pay Nokomis Septic Tank Company, which then filed a mechanic's lien on the property. In order to remove this cloud on their title to the property and avoid foreclosure of the lien, the Sullivans were forced to pay the $1,180.07 amount of the lien. In addition to more than $10,000 paid to subcontractors who had already performed labor or supplied materials to the job before the Respondent left it, the Sullivans had to obtain a loan from their bank in order to finish the project. The contracted for items which the Respondent had left undone (approximately 30 percent of the construction) required them to expend $18,662.04 to complete the dwelling in a manner consistent with the contractual specifications. The items which remained to be constructed or installed are listed on Petitioner's Exhibit 7 in evidence. The remaining amount of contract price which the Respondent was due upon completion of the job would have been $1,737.71. With this in mind, as well as the fact that the Sullivans had to pay in excess of $10,000 to defray already outstanding bills to subcontractors for labor and materials already furnished and then had to obtain a loan in order to pay $18,662.04 in order to complete the house, and it being established without contradiction that the Respondent was unable to make his payroll at the point of leaving the job, the Respondent obviously used substantial amounts of the funds he received from the Sullivans for purposes other than furthering the construction project for which he contracted with the Sullivans. Concerning Count II, on December 22, 1981, Frederick Berbert doing business as Venice Enclosures of Venice, Florida, contracted with Mr. Emory K. Allstaedt of Grove City, Florida, Charlotte County, to build an addition to Mr. Allstaedt's mobile home. The contract specified a price of $4,952 for which Berbert was required to construct a 12-foot by 20-foot enclosure or porch. Mr. Allstaedt never did and never intended to contract with the Respondent, Mr. Martin, rather, his contract was only with Frederick Berbert. Mr. Berbert was a registered aluminum specialty contractor in Sarasota County. He was not registered or licensed to practice contracting in Charlotte County where Mr. Allstaedt lived and where the porch was to be constructed. On December 28, 1981, the Respondent obtained building permit number 72030 from the Charlotte County Building and Zoning Department to construct a "Florida room" for Mr. Allstaedt's mobile home, the same room to be constructed by Mr. Berbert. Under Charlotte County Ordinances in evidence as Petitioner's Exhibits 13 and 13A, only a properly licensed "A", "B" or "C" contractor or a registered aluminum contractor can perform this type of job. The Respondent was appropriately licensed for this type of work in Charlotte County, but Mr. Berbert was not and thus could not obtain the permit in his own right. The Respondent's only connection with this job was obtaining the permit in his own name as contractor of record and in performing some minor work in replacing some damaged sheets of paneling shortly after the construction of the room addition and after the performance of the contract by Berbert. Though the Respondent listed himself as contractor in order to be able to obtain a building permit for the job, he never qualified as the contractor of record nor "qualified" Mr. Berbert's firm with the Construction Industry Licensing Board. Both Mr. Berbert and the Respondent were aware that Mr. Berbert could not legally perform contracting in Charlotte County at the time the Respondent obtained the building permit on Berbert's behalf.

Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the evidence of record and the candor and demeanor of the witnesses, it is, therefore RECOMMENDED: That the contractor's license of Jack A. Martin be suspended for a period of ten (10) years, provided however, that if he makes full restitution to the Sullivans of all monies they expended for labor, materials and permits to enable them to complete the work he had contracted to perform, within one year from a final order herein, that that suspension be reduced to three (3) years after which his license should be reinstated. DONE and ENTERED this 27th day of April, 1984, in Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of April, 1984. COPIES FURNISHED: Charles P. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Jack A. Martin 305 Park Lane Drive Venice, Florida James Linnan, Executive Director Florida Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Fred M. Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (5) 120.57180.07489.127489.129658.28
# 8
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs DONALD CLARK, 02-000978 (2002)
Division of Administrative Hearings, Florida Filed:Clearwater, Florida Mar. 01, 2002 Number: 02-000978 Latest Update: Dec. 01, 2003

The Issue The issue in this case is whether Respondent committed the acts alleged in the Administrative Complaint and if so, what penalty is appropriate.

Findings Of Fact Based upon the testimony of the witnesses and the evidence presented and the entire record in this proceeding, the following material and relevant facts are found. At no time material hereto was Respondent, Donald Clark, licensed by the State of Florida Construction Industry Licensing Board to engage in construction contracting. At no time material hereto was Cancun Development Company ever qualified or certified by any State of Florida agency as a certified contractor. With knowledge of that he was not licensed by the State of Florida to solicit, engage in, nor contract for construction work, Respondent entered into an oral agreement with homeowner Ms. Eichar to build a second-story addition to her home, located in Indian Rocks Beach, Florida, for a contract price of $30,000.00. Respondent, who was paid by Ms. Eichar a total of $25,000.00, subcontracted with Mr. Erwin, a licensed electrical contractor, to do the electrical work at the Eichar's residence for $2,364.00. Respondent, after notice, failed to attend the formal final hearing regarding this matter. The investigative and prosecution costs to the Department of Business and Professional Regulation, excluding cost associated with attorney time, were $550.00.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is recommended that a final order be entered by the Department as follows: Finding Respondent, Donald Clark, guilty of having violated Subsection 489.127(1)(f), Florida Statutes, as alleged in the Administrative Complaint herein filed and imposing as a penalty an administrative fine in the amount of $5,000.00. Assess costs of investigation and prosecution, excluding costs associated with an attorney's time, in the amount of $550.70. DONE AND ENTERED this 23rd day of July, 2002, in Tallahassee, Leon County, Florida. FRED L. BUCKINE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 23rd day of July, 2002. COPIES FURNISHED: Donald Clark 813 East Bloomingdale Avenue Suite 252 Brandon, Florida 32720 Brian A. Higgins, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-2202 Hardy L. Roberts, III, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202

Florida Laws (3) 120.57455.228489.127
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs AL CLYDE HUFELD, 94-006781 (1994)
Division of Administrative Hearings, Florida Filed:Miami, Florida Dec. 05, 1994 Number: 94-006781 Latest Update: May 29, 1996

The Issue This is a license discipline proceeding in which the Petitioner seeks to take disciplinary action against the Respondent on the basis of alleged violations of Chapter 489, Florida Statutes, (1992 Supp.). Specifically, the Respondent has been charged in a four-count Administrative Complaint with violations of paragraphs (k), (m), (n) and (p) of Section 489.129(1), Florida Statutes (1992 Supp.).

Findings Of Fact Respondent is, and has been at all times material hereto, a licensed Certified General Contractor, having been issued license number CG C007303, by the State of Florida. At all times material hereto, the Respondent was licensed to contract as an individual. On September 18, 1992, the Respondent, doing business as an individual, contracted with Charles and Elba Williams (hereinafter referred to as "Customers") to reroof their dwelling and shed at 15205 SW 78 Place, Miami, Florida, for the price of Fifteen Thousand, One Hundred Seventeen dollars ($15,117.00). On October 1, 1992, the aforementioned contract was amended to provide for the payment of half of the second draw before the second stage of the project was completed, and to provide for the payment of an additional Three Hundred and Fifty One dollars ($351.00) in materials. On November 5, 1992, the aforementioned contract was amended to provide the Customers with a credit on the contract of One Thousand, Six Hundred Thirty Six dollars and Sixty Four cents ($1,636.64) for their purchase of roof shingles. The revised contract price was Sixteen Thousand and Fifty Eight dollars ($16,058.00). The Customers paid the Respondent Twelve Thousand, Two Hundred Seventy Seven dollars and Ninety cents ($12,277.90) toward the contract. After receiving a credit on the balance due on the contract, the Customers owed Two Thousand, One Hundred Forty Two dollars and Thirty Two cents ($2,142.32) to the Respondent. On September 23, 1992, the Respondent obtained roofing permit number 92-110050 for the Customers' project from the Dade County Building and Zoning Department. The Respondent worked on the Customers' roof from September 23, 1992, through November 15, 1992, when the installation of the shingles was completed. On November 19, 1992, the Respondent failed a final inspection performed on the Customers' roof by the Dade County Building and Zoning Department because the Respondent failed to supply Dade County with product approval information and manufacturer installation specifications for the ridge vent he had installed. On November 24, 1992, the Respondent again failed a final inspection performed on the Customers' roof by the Dade County Building and Zoning Department for the same reason as on November 19, 1992. The Respondent never obtained a passing final inspection on the Customers' roof from the Dade County Building and Zoning Department. On November 24, 1992, the Customers sent the Respondent a Certified letter, Return Receipt requested, informing the Respondent that the roof could not pass final inspection until Dade County was provided with the product approval information and manufacturer installation specifications for the ridge vent he had installed. On December 4, 1992, the Respondent was issued a Notice of Violation from the Dade County Building and Zoning Department for failure to provide product approval information and manufacturer installation specifications for the ridge vent that had been installed on the Customers' roof. On December 4, 1992, the Respondent was issued a Notice of Violation from the Dade County Building and Zoning Department for failure to remove construction debris from the Customers' property. The Respondent did not comply with either Dade County Notice of Violation and did not supply the Dade County Building and Zoning Department with the product approval information and manufacturer installation specifications for the ridge vent that had been installed on the Customers' roof. The Customers were left with a roof that did not comply with Dade County Code. On March 26, 1993, the Customers paid a Forty Five dollar ($45.00) renewal fee to the Dade County Building and Zoning Department and had the roofing permit renewed and reissued in their own names. On March 4, 1993, the Customers paid another contractor, Mark Mitchell, Two Hundred dollars ($200.00) to remove the ridge vent and close the hole in the roof left by the removal of the ridge vent. On March 27, 1993, after the ridge vent had been removed, the Customers paid a Special Investigator, Ken Nash, Fifty dollars ($50.00) to perform a final inspection of the roof. On March 31, 1993, Ken Nash performed a final inspection of the roof and the roof passed inspection. The Customers paid Steve Wooten Thirty dollars ($30.00) to remove construction debris left on their property by the Respondent and to bring their property in compliance with the Notice of Violation issued on December 4, 1992.

Recommendation On the basis of all of the foregoing, it is RECOMMENDED that the Construction Industry Licensing Board issue a Final Order in this case to the following effect: Dismissing the charges alleged in Counts I, II, and IV of the Administrative Complaint; Concluding that the Respondent is guilty of the violation charged in Count III of the Administrative Complaint; and Imposing a penalty consisting of a fine in the amount of Two Hundred Fifty dollars ($250.00) for the violation charged in Count III of the Administrative Complaint. DONE AND ENTERED this 3rd day of May, 1995 in Tallahassee, Leon County, Florida. MICHAEL M. PARRISH Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of May, 1995. COPIES FURNISHED: Diane Snell Perera, Esquire Department of Business and Professional Regulation 7300 North Kendall Drive, Suite 780 Miami, Florida 33156 Mr. Al C. Hufeld Post Office Box 681064 Orlando, Florida 32868-1064 Richard Hickok, Executive Director Construction Industry Licensing Board 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Lynda Goodgame, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (2) 120.57489.129 Florida Administrative Code (2) 61G4-17.00161G4-17.002
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer