The Issue The issue in DOAH Case No. 98-3901 is whether Respondent Deep Lagoon Boat Club, Ltd., is entitled to a maintenance dredging exemption from environmental resource permitting. The issue in DOAH Case No. 98-5409 is whether Respondent Deep Lagoon Boat Club, Ltd., is entitled to an environmental resource permit for the construction of a surface water management system.
Findings Of Fact The Parties Respondent Deep Lagoon Boat Club, Ltd. (Applicant), owns and operates Deep Lagoon Marina. In DOAH Case No. 98-3901, Petitioner and Intervenor challenge Applicant's claim of an exemption to maintenance dredge three canals serving the marina. In DOAH Case No. 98-5409, Petitioner challenges Applicant's request for an environmental resource permit to construct and operate a surface water management system on the uplands on which the marina is located. By stipulation, Petitioner has standing. Intervenor is a nonprofit organization of natural persons, hundreds of whom reside in Lee County. The primary purpose of Intervenor is to protect manatees and their habitat. Many of the members of Intervenor use and enjoy the waters of the State of Florida, in and about Deep Lagoon Marina, and would be substantially affected by an adverse impact to these waters or associated natural resources, including manatees and their habitat. Deep Lagoon Marina is within the jurisdiction of the South Florida Water Management District (SFWMD). By agreement with SFWMD, Respondent Department of Environmental Protection (collectively, with the predecessor agency, DEP) is the agency with permitting jurisdiction in DOAH Case No. 98-5409. The Marina Deep Lagoon is a short, largely mangrove-lined waterway that runs north into the Caloosahatchee River. The Caloosahatchee River runs west from Lake Okeechobee past Fort Myers to the Gulf of Mexico. Deep Lagoon Marina is on Deep Lagoon, less than one-half mile from the Caloosahatchee River. Deep Lagoon Marina comprises uplands and three canals adjoining MacGregor Boulevard south of downtown Fort Myers. Deep Lagoon Marina presently consists of 61 wet slips, 200 dry slips, and other marina-related buildings. One of Applicant's predecessors in interest dredged the three canals in the 1950s or 1960s, and a marina has existed at this location since that time. As a result of a purchase in 1997, Applicant owns the uplands and either owns the submerged bottoms of the canals or has a legitimate claim to such ownership. The attorney who examined the title at the time of the 1997 conveyance testified that the canals are entirely landward of the original mean high water line, so that the then-owner excavated the canals out of privately owned upland. Thus, the attorney opined that the canal bottom is privately owned. Some question may exist as to the delineation of the historic mean high water line, especially regarding its location relative to the waterward edge of the red mangrove fringe, which DEP would consider part of the historic natural waterbody. There may be some question specifically concerning title to the bottom of the northernmost canal where it joins Deep Lagoon. However, the proof required of Applicant for present purposes is considerably short of the proof required to prove title, and the attorney's testimony, absent proof to the contrary, is sufficient to demonstrate the requisite ownership interest to seek the exemption and permit that are the subject of these cases. From north to south, Deep Lagoon Marina comprises the north canal, which is about 1200 feet long and bounded on the north by a red mangrove fringe 10-20 feet wide; a peninsula; the central canal, which is also known as the central or main basin and is roughly the same length as the north canal; a shorter peninsula; and the south canal, which is about half the length of the central canal and turns to the southeast at a 45-degree angle from the midway point of the central canal. The three canals are dead-end canals, terminating at their eastern ends a short distance from MacGregor Boulevard. Manatees and Boating The Caloosahatchee River is critical habitat for the endangered West Indian manatee. Up to 500 manatees use the river during the winter. When, during the winter, the water cools, the animals congregate in waters warmed by the thermal discharge from a power plant about 13 miles upstream of Deep Lagoon. When, during the winter, the water warms, the manatees swim downstream, past and into Deep Lagoon searching for food. Manatees frequently visit Deep Lagoon. It is one of the few places between the power plant and the Gulf where manatees can find a quiet place, relatively free of human disturbance, to rest and feed. Within Deep Lagoon, the Iona Drainage District ditch runs parallel to the north canal, separated from the canal by the previously described mangrove fringe. The Iona Drainage District ditch empties into Deep Lagoon just north of the mouth of the north canal. Manatees frequently visit the ditch because it is a seasonal source of freshwater, which the manatees drink. Manatees visit the north canal due to its moderate depths and proximity to the freshwater outfalls of the Iona Drainage District ditch. Manatee mortality from watercraft is extremely high in the immediate vicinity of Deep Lagoon, and the mortality rate has increased in recent years. The rate of manatee deaths from collisions with watercraft has increased with the popularity of motorboating. Boat registrations in Lee County rose from 13,000 in 1974 to 36,000 in 1997. The potential for mitigation offered by the enactment of speed zones has been undermined by the fact that nearly half of the boaters fail to comply with the speed limits. Water Quality The Caloosahatchee River is laden with sediments, partly due to intermittent discharges from Lake Okeechobee. Seagrass in the riverbottom cannot grow in water much deeper than four feet. Some seagrass grows at the mouth of Deep Lagoon, but little seagrass extends into the lagoon itself. The water quality in the canals is very poor for dissolved oxygen and copper. Applicant stipulated that the water quality in Deep Lagoon violates state standards for dissolved oxygen, copper, and coliform bacteria. In 1997, the canals violated water quality standards for dissolved oxygen nearly each time sampled during the wet season and one-third of the times sampled during the dry season. The dissolved oxygen levels violated even the lower standards for Class IV agricultural waters two-thirds of the times sampled during the wet season. In 1997, the canals violated water quality standards for copper in the water column each time sampled during the wet season and two-thirds of the times sampled during the dry season. During three of the dry season samplings, copper levels were 20 to 30 times lawful limits. The three lowest wet season copper levels were double lawful limits. Copper is a heavy metal that is toxic to a wide range of marine organisms. Copper is applied to boat hulls to prevent marine life from attaching to the hulls. In 1997, the canals violated water quality standards for total coliform bacteria (for any single reading) three of the 60 times sampled during the dry season and one of the 56 times sampled during the wet season. The canals violated the more relaxed, 20-percent standard (which is violated only if 20 percent of the readings exceed it) during the wet season, but not during the dry season. In 1997, the canals violated water quality standards for lead in the water column in one sample (by 25 percent) out of 36, but did not violate water quality standards for oil and grease or fecal coliform bacteria. Results of testing for mercury in the water column (as opposed to sediments) are not contained in the record. As compared to 1987, the water quality in the canals has improved in all but one important respect. In 1987, the water column readings for copper were five to six times higher than the highest 1997 reading. In 1987, the total coliform bacteria were too numerous to count because the colonies had grown together in the sample. However, comparing the April 1987 data with the May 1997 data for the same approximate times of day and the same locations, the dissolved oxygen levels in the three canals have declined dramatically in the last 10 years. Ten years ago, in a one-day sampling period, there were no reported violations; ten years later, in a one-day sampling period, there were four violations. Even worse, the amount of dissolved oxygen in the water during daylight hours has been halved in the last 10 years with a smaller decrease during nighttime hours. Original Permit There are three types of permits relevant to these cases. The first is a dredge and fill permit (sometimes referred to in the record as a wetland resource permit or water resource permit)(DAF permit). The second is a surface water management (sometimes referred to in the record as a management and storage of surface water (MSSW) permit or stormwater management permit)(SWM permit). The third is an environmental resource permit (ERP). Several years ago, responding to a mandate from the Legislature, DEP and the water management districts consolidated DAF permits, which historically were issued by DEP, and SWM permits, which historically were issued by the water management districts, into ERPs. At the time of this change, DEP adopted, within the jurisdictional areas of each water management district, certain of the rules of each district. In 1988, DEP issued a DAF permit to Applicant's predecessor in title for additional wet slips (as modified, the Original Permit). Due partly to the likelihood of the replacement of some older, smaller slips with larger slips, there is some uncertainty as to the precise number of wet slips that Applicant would be able to construct under the Original Permit. However, Applicant would be able to construct approximately 89-113 new wet slips, with an additional 14,440 square feet of overwater decking, so as to raise its marina capacity to 150-174 wet slips. Applicant also plans to construct 227 dry slips, so as to raise its marina capacity to 427 dry slips, and add 115,000 square feet of buildings, including a restaurant. In general, the Original Permit authorizes Applicant to renovate and expand an existing marina from 61 wet slips to 174 wet slips by: excavating 0.358 ac of uplands to create a flushing canal, installing 375 linear feet of seawall along the sides of the flushing canal, excavating 2.43 ac of submerged bottom to remove contaminated sediments, backfilling 2.41 acres of the dredged area (the main basin and south canal to -7 ft. MLW and the north canal to -6 ft. MLW) with clean sand, renovating the existing 61 slips, and constructing an additional 14,440 square feet of overwater decking for 113 new slips, providing after-the-fact authorization for construction of 2 finger piers, creating a 400 sq. ft. mangrove fringe, constructing 180 linear feet of seawall in the vicinity of the mangrove fringe, and relocating and upgrading fueling facilities. The record contains various references to "MLW" or "mean low water," "MHW" or "mean high water," and "NGVD" or "National Geodetic Vertical Datum." The drawings attached to the Original Permit state that MHW equals 0.96 feet NGVD and MLW equals about 0.40 feet NGVD. The Original Permit authorizes activities to proceed in three phases: First, the majority of the water quality improvement measures will be implemented as required in Specific Condition 5. Second, the over water docking structures will be constructed and the fueling facilities will be upgraded and relocated as required in Specific Conditions 6 and 7. Third, the new slips will be occupied in accordance with the phasing plan in Specific Condition 9. Specific Condition 5 imposes several requirements designed "to ensure a net improvement in water quality." Among these requirements is that Applicant must obtain the ERP that is the subject of DOAH Case No. 98-5409 (New Permit). Specific Condition 5 states: In order to ensure a net improvement to water quality within the basin, the construction of any new docking structures or installation of any new pilings shall not occur until the below-listed conditions (A-K) have been met. . . . A baseline water quality study . . .. A stormwater treatment system providing treatment meeting the specifications of Florida Administrative Code 40E-4 for all discharges into the basins from the project site shall be constructed. . . . The boat wash area shall be re-designed and constructed as shown on Sheets 23 and 23A. All water in the washdown area shall drain into the catch basin of the wastewater treatment system shown on Sheet 23. The water passing through the wastewater treatment system shall drain to the stormwater management system which was previously approved by the South Florida Water Management District. The filters of the wastewater treatment system shall be maintained in functional condition. Material cleaned from the filter shall be disposed of in receptacles maintained specifically for that purpose and taken to a sanitary landfill. This system shall be maintained in functional condition for the life of the facility. [As cited, this subparagraph contains modifications stated in a letter dated March 26, 1997, from DEP to Applicant's predecessor in interest.] Contaminated sediments shall be dredged from the areas shown on Sheets 5 and 7 of 23. A closed-bucket clam shell dredge shall be used. The north canal shall be dredged to at least -9.9 feet MLW and backfilled with clean sand to -6 feet MLW. The [main] basin shall be dredged to at least -7.3 feet MLW and backfilled with clean sand to -7 feet MLW. The south canal shall be dredged to at least -10.5 feet MLW and backfilled with clean sand to at least -7.0 feet MLW. Backfilling shall be completed within 120 days of completion of dredging. . . . The sediments shall be placed directly in sealed trucks, and removed to a self-contained upland disposal site which does not have a point of discharge to waters of the state. A channel, 260 ft. long, 60 ft. wide, with a bottom elevation of -4.5 ft. MLW shall be excavated between the north canal and the main basin to improve flushing. * * * K. Upon completion [of] conditions A-J above, renovation of the existing 61 wet slips and construction of the 113 additional wet slips may proceed with the understanding that construction of all 113 additional slips is at the risk of the permittee and that if the success criteria in the monitoring and occupancy program are not met, removal of all or part of the additional slips may be required by the Department. Specific Condition 8 addresses the phasing of occupancy of the wet slips. Specific Condition 8 provides: Occupancy of the additional 113 wet slips shall occur in two phases, described below. Permanent occupancy of the slips shall require [DEP] approval, contingent upon the water quality monitoring program demonstrating a statistically significant (Specific Condition 9) net improvement for those parameters which did not meet State Water Quality Standards in the baseline study. The permittee agrees that if [DEP] determines that net improvement has not occurred, or if violations of other standards occur, and if the corrective measures described in Specific Condition 10 are not successful, all of the additional slips occupied at that time shall be removed. . . . Phase I--Upon completion of the baseline water quality study and the work specified in Specific Condition No. 5, the existing 61 slips and an additional 56 slips, totalling 117 slips, may be occupied. . . . If at the end of one year of monitoring, the data generated from the water quality monitoring program shows a statistically significant improvement over baseline conditions, for those parameters in violation of State Water Quality Standards, and no violations of additional parameters, . . . the new 56 slips which were occupied shall be considered permanent. Phase II--Upon written notification from [DEP] that Phase I was successful, the remaining 57 additional slips may be occupied. Water and sediment quality monitoring shall continue for two years after the occupancy of 140 of the 174 slips. If a statistically significant net improvement to water quality over baseline conditions for those parameters in violation of State Water Quality Standards [sic] and no violation of additional parameters is shown by the monitoring data, and confirmed by [DEP] in writing, the additional slips shall be considered permanent. * * * Specific Condition 11 adds: Implementation of the slip phasing plan described in Specific Condition 8 shall be contingent on compliance of boaters with existing speed zones in the Caloosahatchee River and trends in manatee and [sic] mortality. . . . Approval of additional slips will depend upon manatee mortality trends and boater compliance with speed zones in the Caloosahatchee River and additional slips may not be recommended. . . . Based on the results of the evaluations of Phases I and II, [DEP] may require that slips be removed to adequately protect manatees. Specific Condition 12 requires the construction of a 400 square-foot intertidal area for the planting of mangroves to replace the mangroves lost in the construction of the flushing channel. Specific Condition 14 prohibits liveaboards at the marina. Specific Condition 15 adds various manatee-protection provisions. Plan Views C and D, which are part of the Original Permit, depict submerged bottom elevations for the north and central canals, as well as from the south canal at its intersection with the central canal. Dated August 30, 1995, these "existing" bottom elevations across the mouth of the north canal are about -7, -8, and -4 feet (presumably MLW; see second note to Plan View B). The western two-thirds of the north canal passes over bottoms of about -6 feet MLW. Proceeding east, the bottom deepens to -7 to -9 feet MLW before it tapers up to -7, -6, and finally -3 feet MLW at the head; and the eastern third of the north canal passes over bottoms of about -7 feet MLW that tapers up to -6 feet and -3 feet MLW. The submerged bottom at the mouth of the central canal is about -8 to -9 feet MLW. The bottom drops to -6 to -10 feet MLW at the intersection with the south canal. Proceeding east, the bottom deepens slightly as it reaches the head, where it is -8 feet MLW. The submerged bottom of the south canal runs from -9 feet MLW at the intersection with the central canal and runs about 0.5 feet deeper at the head. Petitioner and others challenged the issuance of the Original Permit in 1988. The permit challengers appealed a final order granting the Original Permit and certifying, under the federal Clean Water Act, that state water quality standards were met. DEP premised its certification on the concept that water quality standards encompassed a net improvement in water quality of the poorly flushed canals. In Sheridan v. Deep Lagoon Marina, 576 So. 2d 771, 772 (Fla. 1st DCA 1991), the court, relying on the above-described 1987 water quality data, noted the "very poor water quality" of Deep Lagoon, as reflected in part by the presence of oil and grease 20 times the Class III standard, copper 13 times the standard, lead 20 times the standard, mercury 1000 times the standard, and coliform bacteria "too numerous to count." However, the court affirmed the issuance of the Original Permit under the statutory authorization of a permit where ambient water quality does not meet applicable standards, but the activity will provide a net improvement to the waters. On the certification issue, though, the court reversed and remanded. The court held that the hearing officer erroneously excluded evidence on DEP's certification of the activity as in compliance the federal Clean Water Act. Following remand, DEP issued a final order issuing the Original Permit. On the certification issue, the final order revoked the earlier certification of compliance and, citing 33 United States Code Section 1341 as authority, waived certification as a precondition to federal permitting. Maintenance Dredging: DOAH Case No. 98-3901 Background The contentions of Petitioner and Intervenor as to maintenance dredging are: the proposed dredging exceeded what was necessary to restore the canals to original design specifications or original configurations; the proposed dredging exceeded the maximum depth allowable for maintenance dredging of canals; the work was not conducted in compliance with Section 370.12(2)(d), Florida Statutes; the spoil was not deposited on a self-contained upland site to prevent the escape of the spoil into waters of the state; and the dredge contractor did not use control devices and best management practices for erosion and sediment control to prevent turbidity, dredged material, and toxic or deleterious substances from discharging into adjacent waters during maintenance dredging. On March 3, 1998, Applicant's engineering consultant submitted drawings to DEP with notification that Applicant intended to "maintenance dredge the internal canals of Deep Lagoon Marina," in conformity with Rule 62-312.050(e), Florida Administrative Code. The letter describes the proposed dredging as mechanical "with no discharge back into Waters of the State." The letter assures that Applicant's contractor will use turbidity curtains "around the dredging and spoil unloading operation" and advises that the contractor will unload the spoil "to the north peninsula upland area." The letter states that the dredging "will be to the design depth/existing canal center line depth of -7 NGVD," which was established by the Original Permit, and will be "done in conjunction with the required dredging under [Original Permit] Condition 5(D)." The consultant attached to the March 3 letter several drawings showing the dredging of all three canals. For each canal, the drawings divide the dredging into two areas. For 1.82 acres, the contractor would dredge contaminated materials from the dead-ends of the three canals (for the south canal, a portion running from the head along the northeast half of the canal) and then replace these materials with clean backfill material. This information is for background only, as the Original Permit authorized this contaminant dredging. For 4.84 acres, which run through the remainder of the three canals, the contractor would maintenance dredge in accordance with the cross-sections provided with the letter. The cross-sections for the north canal reveal relatively extensive dredging beyond the vegetation lines on both sides of the canal bottom. The dredging would extend up to, but not beyond, the edges of the prop roots of the mangroves on both sides of the canal bottom. The contours reveal variable, proposed slope profiles for the submerged sides of the canals, but the dredging would substantially steepen the submerged slopes of the north canal. It is difficult to estimate from the cross-sections the average depth and width to be dredged from the north canal, but it appears that the cross-sections proposed the removal of substantial spoil (an average of 4-6 feet) from areas from 20-40 feet from each side of the deepest point in the north canal. The dredging would alter the two most affected cross-sections, which are just inside the mouth of the north canal, by widening the deepest part of the canal bottom by 85 feet--from about 15 feet to about 100 feet. The drawings proposed much smaller alterations to the bottoms of the central and south canals: typically, spoil about 2 feet deep and 20 feet wide. All but one of the cross-sections revealed that spoil would be dredged only from one side of the deepest point. Additionally, the dredging in these canals would not involve any submerged vegetation; all but one of the canal sides was lined by existing seawalls. By letter dated March 13, 1998, DEP stated that it had determined that, pursuant to Rule 40E-4.051(2)(a), Florida Administrative Code, the proposed activity was exempt from the requirement that the Applicant obtain an ERP. The letter warns that, pursuant to Chapter 62-302, Florida Administrative Code, the construction and operation of the project must not cause water quality violations. The letter adds that DEP may revoke its determination of exemption if the "basis for the exemption is determined to be materially incorrect, or if the installation results in water quality violations." The letter provides a point of entry for persons whose substantial interests are affected by DEP's determination. Following receipt of DEP's letter acknowledging the exemption, Applicant's contractor proceeded to maintenance dredge the three canals. The dredging of the north canal took eight weeks. Applicant's contractor also performed the contaminant dredging and clean backfilling authorized by the Original Permit. As indicated in the March 3 letter and permitted in the Original Permit, the contaminant dredging took place at the dead-end heads of the north and central canals and along the northeast half of a slightly longer section of the south canal, starting from its dead-end head. In maintenance dredging the canals, Applicant's contractor did not exceed the specifications regarding depth and width stated in its March 3 letter. To the contrary, the contractor sometimes dredged slightly narrower or slightly shallower profiles than stated in the March 3 letter. For example, the contractor dredged the north canal to -6 feet NGVD (or -5.6 feet MLW), rather than -7 feet NGVD, as shown in the March 3 letter. The Depths, Widths, and Lengths of Dredging The March 3 letter asserts that -7 feet NGVD is the permitted elevation of the canal bottoms, pursuant to the Original Permit. This is incorrect in two respects. First, the assertion in the March 3 letter of a -7 foot permitted bottom elevation is incorrect for all but the relatively small part of each canal that DEP has determined is contaminated. The Original Permit specifies design elevations for canal bottoms only in the contaminated area within each canal. Nothing in the Original Permit permits bottom elevations for any portion of the bottoms of the three canals outside of these three contaminated areas. Second, the assertion in the March 3 letter of a -7 foot permitted bottom elevation is incorrect, even for the contaminated areas. The March 3 letter states -7 feet NGVD, but the Original Permit specifies bottom elevations, for contaminated areas only, of -7 feet MLW in the south and central canals and -6 feet MLW in the north canal. Thus, due to the differences between NGVD and MLW, the March 3 letter proposes dredging that would deepen the south and central canals by about five inches deeper than the depth permitted in the Original Permit and the north canal by one foot five inches deeper than the depth permitted in the Original Permit. Moreover, nothing in the record clearly establishes all aspects of the original design specifications of the three canals, whether permitted or not, or even all aspects of their original dredged configurations, if not permitted. There is no dispute concerning one aspect of the dredged configuration of the three canals: their lengths. Although there may be some dispute as to the original mean high water line near the mouths of the north and central canals, the original length of the canals is evident from the uplands that presently define them. As to the depth of the canals, although direct evidence is slight, Applicant has sufficiently proved indirectly the depths of the mouths of the canals pursuant to original design specifications or, if not designed, original configurations. The proved bottom elevations are -7 feet NGVD for each canal. Applicant proved these depths based on the prevailing elevations in Deep Lagoon in the vicinity of the mouths of the north and central canal and bottom elevations in areas of Deep Lagoon that are not prone to sedimentation. Additional proof of the bottom elevation of -7 feet NGVD at the mouths of the canals is present in the slightly higher permitted bottom elevations at the dead- ends of the north and central canals and landward portion of the south canal. There is some problem, though, with the proof of the depth of the canal bottoms between their mouths and heads (or, for the south canal, its landward portion of known contamination). Although the problem of the depth of the canals between their heads and mouths might be resolved by inferring a constant bottom elevation change from the deeper mouth to the shallower head, an unresolveable issue remains: the width of this maximum depth. As already noted, without deepening the deepest part of either cross-section, the contractor widened the deepest points along two cross-sections by 85 feet each. In terms of navigability and environmental impact, the width of the maximum depth of a canal is as important as its maximum depth. As to the width of the lowest bottom elevations of the canals, Applicant has produced no proof of original design specifications or, if not designed, original configurations. Nor has Applicant produced indirect proof of historic widths. Nothing in the record supports an inference that Applicant's predecessor in interest originally dredged the canal bottoms as wide as Applicant "maintenance" dredged them under the claimed exemption. Nothing in the record supports an inference that Applicant's predecessor geometrically dredged the canals so that their sides were perpendicular to their bottoms. Nothing in the record describes a sedimentation problem that might have narrowed the canals by such an extent that the dredging of the present widths, especially in the north canal, would be restorative. Nothing in the record even suggests that the original motive in dredging was navigability, which might have yielded relatively wide canal bottoms, versus upland fill, which would yield canal bottoms as wide as needed, not for navigability, but for uplands- creation. After consideration of all the evidence, no evidence supports a finding that the proposed dredging profiles, in terms of the widening of the areas of lowest elevation in each canal bottom, bear any resemblance whatsoever to the original canal profiles, as originally (or at any later point) designed or, if not designed, as originally (or at any later point) configured. It is at least as likely as not that this is the first time that these canal bottoms, especially the north canal bottom, have ever been so wide at any bottom elevation approaching -7 feet NGVD. There is simply no notion of restoration or maintenance in the dredging that produced these new bottom profiles for these three canals. Transforming MLW to NGVD, -5 feet MLW is -4.6 feet NGVD. All proposed and actual maintenance dredging in the three canals dredged the canal bottoms to elevations lower than -5 feet MLW (or -4.6 feet NGVD), despite the absence of any previous permit for construction or maintenance of the canal from the Trustees of the Internal Improvement Trust Fund or the United States Army Corps of Engineers. Impact of Dredging on Manatees and Spoil Containment Prior to dredging, Applicant deployed turbidity curtains around the mouths of the two canals that discharge directly into Deep Lagoon. In this case, the turbidity curtains performed two functions. They contained turbidity and resuspended bottom contaminants within the mixing zone behind (or landward of) the curtains, and they excluded manatees from the dangerous area behind the curtains where the dredging was taking place. Petitioner and Intervenor object to the use of the turbidity curtains on two general grounds. First, they claim that the curtains failed to contain turbidity and resuspended contaminants from escaping the mixing zone. Second, they claim that the curtains adversely affected manatees. As executed, the maintenance dredging did not result in the release of turbidity or resuspended contaminants outside of the mixing zone due to the use of turbidity curtains. Applicant's contractor ensured that the curtains extended from the water surface to the canal bottom and sufficiently on the sides to prevent the escape of turbidity or resuspended contaminants. Although the March 3 letter did not indicate where the contractor would deploy the turbidity curtains, the important point, in retrospect, is that the contractor properly deployed the curtains. There is some question whether turbidity or resuspended contaminants flowed across the mangrove fringe and into the Iona Drainage District ditch. Applicant's witness testified that water flows across the fringe only during the highest three or four tides per month. Petitioner and Intervenor's witness testified that water flows across the fringe as often as twice per day. The actual frequency is likely somewhere between these two extremes, but, regardless of the frequency, there is insufficient evidence to find that any turbidity or resuspended contaminants flowed from the north canal into the Iona Drainage District ditch. Nor did the deployment of the turbidity curtains injure, harm, possess, annoy, molest, harass, or disturb any manatees. Applicant and its contractor carefully checked each canal for manatees before raising the turbidity curtains at the mouth of each canal, so as not to trap any manatees in the area behind the curtains. By ensuring that the curtains extended to the canal bottom and extended fully from side to side, they ensured that the curtains excluded manatees during the dredging. There is no evidence that a manatee could have entered the north canal from the Iona Drainage District ditch by crossing the red mangrove fringe; any breaks in the fringe were obstructed by prop roots that prevented even a kayaker from crossing the fringe without portaging. Applicant and its contractor checked for manatees during dredging operations. Petitioner and Intervenor contend that the mere presence of the turbidity curtains in an area frequented by manatees adversely affected the animals. However, this argument elevates a speculative concern with a manatee's response to encountering an obstruction in its normal path over the practical purpose of curtains in physically obstructing the animal so as to prevent it from entering the dangerous area in which the dredge is operating, as well as the unhealthy area of turbidity and resuspended contaminants in the mixing zone. Under the circumstances, the use of the turbidity curtains to obstruct the manatees from visiting the dredging site or mixing zone did not adversely affect the manatees. In general, there is no evidence of any actual injury or harm to any manatees in the course of the dredging or the preparation for the dredging, including the deployment of the turbidity curtains. Petitioner and Intervenor offered evidence that maintenance dredging would result in more and larger boats and deterioration of water quality, which would both injure the manatees. However, as noted in the conclusions of law, the Administrative Law Judge excluded from DOAH Case No. 98-3901 such evidence concerning long-term impacts upon the manatees following the dredging. As for spoil containment, Applicant's contractor segregated the contaminated spoil from noncontaminated spoil by placing the contaminated spoil in a lined pit in the uplands. The contractor also brought onto the uplands clean fill mined from a sand quarry for backfilling into the dredged contaminated areas. There is evidence of the clean fill subsiding from its upland storage site and entering the canal waters in the mixing zone. Partly, this occurred during the loading of the barge, which transported the clean fill to the dead-end heads of the canals where the fill was placed over the newly dredged bottoms. The fill escaped into the water at a location about 100 feet long along the north seawall of the central canal, but the evidence does not establish whether this location was within the contaminated area at the head of the canal or whether the maintenance or contaminant dredging had already taken place. If the fill subsided into the water inside of the contaminated head of the south canal and the subsidence occurred prior to the contaminant dredging, the subsidence was harmless because the contractor would remove the fill during the dredging. If the fill subsided into the water inside the contaminated head of the south canal and the subsidence occurred after the contaminant dredging, the subsidence was harmless because the contractor intended to add the fill at this location. If the fill subsided into the water outside of the contaminated head of the south canal and the subsidence occurred prior to maintenance dredging, the subsidence was harmless because the contractor would remove the fill during the dredging. If the fill subsided into the water outside the contaminated head of the south canal and the subsidence occurred after the maintenance dredging, the subsidence was harmless because it restored the canal bottom to a higher elevation following the dredging to an excessively low elevation. The subsidence of the clean fill into the water along the north side of the central canal is the only material that entered the water from the uplands during the dredging. Specifically, there is no evidence of dredged spoil entering the water from the uplands during or after the dredging. There is also no evidence that the maintenance dredging significantly impacted previously undisturbed natural areas. There is no evidence of such areas within the vicinity of Deep Lagoon Marina. New Permit: DOAH Case No. 98-5409 New Permit Seeking to satisfy certain of the requirements of Original Permit Specific Condition 5, Applicant filed with DEP, on December 10, 1997, an application for an ERP and water quality certification to construct a surface water management system to serve 15.4 acres of its 24-acre marina. Prior to its reformulation as an ERP, the New Permit sought by Applicant would have been a SWM permit. The application notes that the general upland elevation is 5 feet NGVD and that stormwater runoff presently sheetflows directly to adjacent waterways without any treatment. During the application process, Applicant's engineer Christopher Wright, submitted a letter dated February 27, 1998, to Jack Myers, who is a Professional Engineer II for DEP. In response to a request from DEP for a "written procedure . . . to assure the proper functioning of the proposed . . . system," the letter states: Since the system is not designed as a retention system and does not rely upon infiltration to operate properly[,] operation and maintenance is minimal. Items that will need regular maintenance are limited to removal of silt and debris from the bottom of the drainage structures and the bleed down orifice of the control structure. A maintenance and inspection schedule has been included in this re-submittal as part of Exhibit 14. In relevant part, Exhibit 14 consists of a document provided Mr. Wright from the manufacturer of the components of the surface water management system. The document states that the manufacturer "recommends that the landowner use this schedule for periodic system maintenance . . .." The document lists 16 sediment-control items, but it is unclear whether all of them are incorporated into the proposed system. Four items, including sediment basins, require inspections quarterly or after "large storm events" and maintenance consisting of the removal of sediment; the "water quality inlet" requires inspections quarterly and maintenance consisting of "pump[ing] or vacuum[ing]"; the "maximizer settling chamber" requires inspection biannually and maintenance consisting of "vacuum[ing] or inject[ing] water, suspend silt and pump chamber"; and the "chamber" requires inspection annually and the same maintenance as the maximizer settling chamber. The proposed system includes the water quality inlet and one of the two types of chambers. By Notice of Intent to Issue dated November 5, 1998, DEP provided notice of its intent to issue the New Permit and certification of compliance with state water quality standards, pursuant to Section 401 of the Clean Water Act, 33 United States Code Section 1341. On February 6, 1999, DEP revised the notice of intent by withdrawing its certification of state water quality compliance. As it did with the Original Permit, DEP again waived state water quality certification. This waiver is consistent with a letter dated February 2, 1998, in which then-DEP Secretary Virginia Wetherell announced that DEP would waive state water quality certification for all activities in which the agency issues an ERP based on the "net improvement" provisions of Section 373.414(1)(b), Florida Statutes. The notices of intent (collectively, NOI) recite the recent permitting history of the marina. This history includes the Original Permit, a since-expired MSSW permit issued in 1988 by SFWMD, and then-pending requests--apparently all since granted--to revise the Original Permit by replacing the flushing canal with culverts, relocating a travel lift from the main canal to the north canal, and adding liveaboards to the marina. (Although mentioned below, these revisions, in and of themselves, do not determine the outcome of DOAH Case No. 98-5409.) Reviewing the proposed development for the site, the NOI states that the northerly part of the project would contain an indoor dry boat storage barn, a marina service operation consisting of a ship store and miscellaneous buildings, a harbor master building, an upgraded fueling facility, a parts and service center, a restaurant, retail and commercial facilities, and paved parking areas. The southerly part of the project would contain a new indoor dry boat storage barn, a boat dealership building, and paved parking areas in place of the existing buildings. The NOI states that the proposed water quality treatment system would comprise dry detention systems of several underground vaults with an overall capacity based on the total impervious area, including roofs, receiving 2.5 inches of rain times the percentage of imperviousness. Given the relatively high imperviousness of the finished development, this recommended order considers the percentage of imperviousness to be 100, but ignores the extent to which the post-development pervious surfaces would absorb any rainfall. For storms producing up to 2.5 inches of runoff, the proposed surface water management system, of which the underground vaults are a part, would trap the runoff and provide treatment, as sufficiently sized contaminants settled into the bottom of the vaults. Because the vaults have unenclosed bottoms, the proposed system would provide incidental additional treatment by allowing stormwater to percolate through the ground and into the water table. However, the system is essentially a dry detention system, and volumetric calculations of system capacity properly ignored the incidental treatment available through percolation into the water table. The New Permit notes that the wet season water table is 1.2 feet NGVD, and the bottom of the dry detention system is 2.5 feet NGVD. This relatively thin layer of soil probably explains why DEP's volumetric calculations ignored the treatment potential offered by percolation. The relatively high water table raises the possibility, especially if Applicant does not frequently remove the settled contaminants, that the proposed system could cause groundwater contamination after the thin layer of soil is saturated with contaminants. In any event, the system is not designed for the elimination of the settled contaminants through percolation. The treatment system for the boat wash areas would be self-contained, loop-recycle systems that would permit the separation of oil and free-settling solids prior to reuse. However, the NOI warns that, "during heavy storm events"-- probably again referring to more than 2.5 inches of runoff--the loop-recycle systems would release untreated water to one of the underground vaults, which would, in turn, release the untreated water into the canals. Due to the location of the boat wash areas, the receiving waters would probably be the north canal. As reflected in the drawings and the testimony of Mr. Wright, the surface water management system would discharge at three points: two in the north canal and one in the south canal. (Vol. I, p. 206; future references to the Transcript shall cite only the volume and page as, for example, Vol. I, p. 206). 67. The NOI concludes that Applicant has provided affirmative reasonable assurance that the construction and operation of the activity, considering the direct, secondary and cumulative impacts, will comply with the provisions of Part IV of Chapter 373, F.S., and the rules adopted thereunder, including the Conditions for Issuance or Additional Conditions for Issuance of an environmental resource permit, pursuant to Part IV of Chapter 373, F.S., Chapter 62-330, and Sections SFWMD--40E-4.301 and 40E-4.302, F.A.C. The construction and operation of the activity will not result in violations of water quality standards and will not degrade ambient water quality in Outstanding Florida Waters pursuant to Section 62-4.242, F.A.C. The Applicant has also demonstrated that the construction of the activity, including a consideration of the direct, secondary, and cumulative impacts, is clearly in the public interest, pursuant to Section 373.414(1)(a), F.S. However, the design capacity of the proposed surface water management system raises serious questions concerning the water quality of the discharges into the canals. Mr. Wright initially testified that the surface water management system would be over-taxed by "an extreme storm event, probably a 25- year storm event . . .." (Vol. I, pp. 208-09). The record contains no evidence of the frequency of the storm event that produces 2.5 inches of runoff for the relatively impervious post- development uplands; the record contains no evidence even of the frequency of the storm event that produces 2.5 inches of rainfall. According to Mr. Wright, the 25-year storm would typically produce 8-10 inches of rain. (Vol. I, pp. 223 and 233). As already noted, the relatively large area of imperviousness following upland development and the relative imperviousness of the upland soils present at the site suggest that the runoff will be a relatively large percentage of the rainfall produced by any given storm event. It thus appears that the design capacity of the system is for a storm substantially smaller and substantially more frequent than the 25-year storm. Attached to the NOI is a draft of the New Permit, which contains numerous specific conditions and conforms in all respects with the NOI. Omitting any mention of SFWMD's Basis of Review, the New Permit addresses, among other things, the operation, inspection, and maintenance of the components of the proposed system. As set forth in the testimony of Michael Bateman, who is a Professional Engineer III and statewide stormwater coordinator for DEP, the surface water management system's operation depends on periodic pumping of the "thick, fine sediment," which appears to be a "cross between mud and sand" and will be laden with oil, grease, metals, and other contaminants. (Vol. II, p. 66). However, contrary to Mr. Bateman's assurance that the New Permit requires the periodic pumping or removal of contaminants that have precipitated out of the runoff in the dry detention system and dropped to the bottom sediment (Vol. II, p. 20), neither the NOI nor the New Permit requires, in clear and enforceable language, the periodic removal of settled solids from the underground vaults or their manner of disposal. New Permit Specific Condition 8 requires that Applicant maintain the boat wash area in "functioning condition," although specific inspection and maintenance requirements are omitted from the New Permit. New Permit Specific Condition 7 requires that Applicant "inspect and clean" all stormwater inlets "as necessary, at least once a month and after all large storm events," although the New Permit fails to specify that cleaning shall be by either pumping or vacuuming. By contrast to the marginally adequate inspection and maintenance provisions applicable to the boat wash area (inspections are required in Specific Condition 6, cited below) and stormwater inlets, the New Permit completely fails to specify enforceable inspection and maintenance requirements for the underground vaults. New Permit Specific Condition 6 addresses the operation of the vault as follows: Upon completion of the construction of the stormwater collection and underground vault (Infiltrator) systems and on an annual basis thereafter by September 30 of each year, the Permittee shall submit reports to the Department as to the storage/treatment volume adequacy of the permitted system. The reports shall also include, but not be limited to, the condition of stormwater inlets and control structures as to silt and debris removal and the condition of the inlet wire mesh screens to function properly. The boat wash down areas shall be inspected for proper operation, i.e., no signs of wash water overflows from the containment area, condition of the containment area curbing, etc. Such reports shall include proposal of technique and schedule for the maintenance and/or repair of any deficiencies noted and shall be signed and sealed by a Florida registered Professional Engineer. A report of compliance with the aforementioned proposal shall be submitted by the Professional Engineer to the Department upon completion of the proposed work which shall be accomplished within three months of the initial report for each year. New Permit Specific Condition 6 requires annual reports concerning the sufficiency of the capacity of the underground vaults (first sentence), annual reports of the status of silt- and debris-removal from the inlets and control structures and the condition of the inlet wire mesh screens (second sentence), inspection at no stated intervals of the boat wash area (third sentence), and annual reports with suggestions of maintenance schedules and repairs for the items mentioned in the first two sentences (fourth sentence). New Permit Specific Condition 6 promises only the preparation of a maintenance schedule at some point in the future. Failing to supply an enforceable inspection and maintenance program, Specific Condition 6 indicates that Applicant shall consider in the future techniques and scheduling of maintenance, presumably based on the report concerning system capacity. Such a requirement may or may not impose upon Applicant an enforceable obligation to adopt an enforceable inspection and maintenance program in the future, but it does not do so now. There is no reason why the New Permit should not impose upon Applicant an initial, enforceable inspection and maintenance program incorporating, for example, the clear and enforceable requirements that Applicant inspect all of the underground vaults no less frequently that once (or twice, if this is the applicable recommendation of the manufacturer) annually and, at clearly specified intervals, remove the sediments by resuspending the sediments in the water, pumping out the water, and disposing of the effluent and sediments so they do not reenter waters of the state. Although the record does not disclose such requirements, Applicant could possibly find manufacturer's recommendations for the boat wash components and incorporate them into an enforceable inspection and maintenance program more detailed than that contained in Specific Condition 8. However, for the reasons noted below, water quality considerations require a substantial strengthening of such a program beyond what is set forth in this paragraph as otherwise acceptable. At present, the bottom line on inspection and maintenance is simple: the New Permit does not even incorporate by reference the manufacturer's recommended inspection and maintenance schedule, which Mr. Wright provided to Mr. Myers. Nor was this shortcoming of the New Permit in its treatment of inspection and maintenance necessarily missed by Mr. Wright. He testified that he submitted to DEP the manufacturer's maintenance program (Vol. I, p. 205), but when asked, on direct, if the "permit in any way incorporate[s] the commitment in your application to this maintenance?" Mr. Wright candidly replied, "That I don't know." (Vol. I, p. 206). Satisfaction of Basis of Review Section 5 Basis of Review Section 5--specifically Section 5.2.1(a)--imposes the "volumetric" requirement of 2.5 inches times the percentage of imperviousness, as discussed above and in the conclusions of law. Petitioner does not dispute Applicant's compliance with this volumetric requirement, and the record amply demonstrates such compliance. Applicability of Basis of Review Section 4 The main issues in this case are whether the environmental and water quality requirements of Basis of Review Section 4 apply to the direct, secondary, and cumulative impacts of the proposed activity. Because the record lacks any indication of other relevant pending or vested permits, without which, as noted in the conclusions of law, one cannot assess cumulative impacts, the remainder of the findings of fact will not discuss cumulative impacts, although, to some extent, increased boating pressure constitutes a secondary impact and a cumulative impact. Without regard to the differences between direct and secondary impacts, DEP has taken the position in this case that it could lawfully issue the New Permit upon satisfaction of the volumetric requirements of Basis of Review Section 5 and without consideration of the requirements of Basis of Review Section 4. In large part, DEP's witnesses justify this position by reliance on the historic differences between DAF permits and SWM permits and the fact that the New Permit is a former-SWM ERP. As discussed in detail in the conclusions of law, the Basis of Review imposes different requirements upon former-DAF and former-SWM ERPs, although the Basis of Review does not refer to DAF or SWM permits by their former names. The identifying language used in the Basis of Review for former-DAF ERPs is "regulated activity" "located in, on, or over surface waters or wetlands." References to "regulated activity" without the qualifying clause indicate that the following requirement applies to former-DAF ERPs and former-SWM ERPs. Several witnesses for DEP and Applicant testified that Applicant was entitled to the New Permit upon satisfaction of the volumetric requirements of Basis of Review Section 5. For example, Mr. Wright testified that the water quality requirements for the New Permit required only a "cookbook calculation" to determine volume. (Vol. I, p. 204). Agreeing with a question that analysis of the water quality portion of the system requires "simply a straightforward mathematical calculation," Mr. Wright testified that the quality of discharged water, following treatment, will comply with state water quality standards in storms producing no more than 2.5 inches of runoff. (Vol. I, pp. 210-11). When asked to explain his answer, Mr. Wright testified, "It's kind of an implied situation, in that if you follow the guidelines that you are required to follow with respect to the calculations of water quality, that the end product is going to be in compliance with state standards." (Vol. I, p. 211). DEP witnesses agreed with Mr. Wright's analysis. For instance, Mr. Bateman testified, "The stormwater portion of the Basis of Review gets at that question [meeting water quality standards] by stating, 'if you follow the design criteria in the basis, you are presumed to meet water quality standards.'" (Vol. II, p. 40). Mr. John Iglehart, the program administrator for DEP's South District Office in Fort Myers, testified on the same point: "if . . . you meet the criteria, the engineering criteria, than you have met the presumption that you meet the rule." (Vol. III, p. 52). Mr. Myers also agreed, testifying, "with the stormwater management system, it's for the most part, let's say, fairly cut and dried as far as meeting criteria that is established within these rules and Basis of Review." (Vol. III, p. 144). He added: "Since the criteria for reviewing stormwater management systems and the discharge is based upon a presumed compliance with stormwater criteria and with state water quality, it is presumed it [the proposed system] does meet it." (Vol. III, p. 148). Mr. Bateman explained the historic basis for the water quality presumption given surface water management systems that meet the volumetric requirements: the ERP is a combination of the surface water management rules and the environmental . . ., the dredge-and-fill, and they didn't merge, they didn't marry very well in certain areas. In stormwater we look at--it's a technology- based criteria. We say, "If you build it this way, treat 80 percent of the average annual pollutant load, we're going to give you the permit on the presumption that you're doing the best you can. You're going to meet standards. Once you get into the wetlands, we take--we put on whole new sets of glasses. ALJ: Are you saying that the old dredge-and- fill is more performance-based, and the old MSSW is more technology-based, in that if you've put in the required technology, you've done your job? WITNESS: That is--yes. Dredge-and-fill is a more case by case. We look at the water quality. We look at ambient conditions. We look at hydrographics [here, largely tidal flushing]. It's more like a waste load allocation in that we're very specific. In stormwater, we can't afford to be. MS. HOLMES: So what you're saying is you can't point to the specific rule provision or regulation that excludes these criteria from surface water management systems? WITNESS: Well, you have to read [Basis of Review] Section 4 as a whole. 4.1 is specific to wetlands and other surface waters. 4.2 is environmental review. I mean, if you look at the thing in total, and the--and I realize it's confusing. But these rules are exactly the same in all the water management districts. They were developed together as the wetland criteria, the new dredge-and-fill criteria. They're exactly the same. The stormwater rules of all the [water management districts] is all different. That is for another day, making those all consistent. So these environmental wetland- type dredge-and-fill criteria are all the same, and they refer to in-water impact. [All references in the transcript to "end water" should have been "in-water."] ALJ: What do you mean by that term, "in- water impact?" WITNESS: In other words, dredge-and-fill impact. Construct and--I can't-- MS. HOLMES: May I continue, then? ALJ: Let him answer. What were you going to say? WITNESS: I think it takes a little knowledge of how these [rules] developed to know how they're applied, unfortunately. In other water management districts, it's clearer that these are in-water impacts. (Vol. II, pp. 57-59). In testifying to the exclusivity of the volumetric requirements in Basis of Review Section 5, with respect to former-SWM ERPs, these witnesses likewise opined that the secondary-impact analysis required in Basis of Review Section 4 also was inapplicable to the New Permit. For example, after testifying both ways on the necessity of considering secondary impacts in issuing former-SWM ERPs, Mr. Bateman concluded, "I'm not sure that [the requirement of considering secondary impacts] applies in this case. Certainty the rules apply, I mean, the rules apply. But certain rules are not applicable in this particular instance. I mean, I'm trying to think of a secondary impact associated with stormwater system, and it's difficult for me to do so." (Vol. II, p. 45). Mr. Bateman then testified that DEP did not consider such secondary impacts, as additional boat traffic, and probably did not consider cumulative impacts, such as other marinas. (Vol. II, pp. 51-52). In response to a question asking to what extent DEP considered post-development inputs of contaminants, such as heavy metals, when issuing a former-SWM ERP, Mr. Bateman testified: I have to tell you, very little. I mean, we--stormwater is pretty black and white. The link to secondary and cumulative impact is generally associated with in-water impact. And I realize the line is a little grey here. When we build a Wal-Mart, we don't think about how many cars it's going to put on [U.S. Route] 41 and what the impact might be to an adjacent lake. We just don't. It would be a little burdensome. In this case, I mean, it's a little greyer. (Vol. II, p. 47). Mr. Bateman was then asked to compare the relative impacts from a vacant, but developed, upland without a surface water management system with a proposed activity that would add a surface water management system to facilitate an intensification of land uses on the site so as to add new contaminants to the runoff. Mr. Bateman testified that DEP would apply only the volumetric requirement and not address the complex issue of weighing the potential environmental benefit of a new surface water system against the potential environmental detriment of contaminant loading (at least in storm events greater than the design storm event). Mr. Bateman explained: "The way it works, it is not a water quality-based standard. In other words, we don't go in and say it's so many pounds [of contaminants] per acre per year now. We're going to make it this many pounds per acre per year, and look at it in a detailed fashion. We do the [Best Management Practices], retain an inch and you're there." (Vol. II, p. 49). Agreeing with Mr. Bateman that DEP was not required to consider secondary impacts resulting from the regulated activity, Mr. Iglehart testified: "It's our thought that we don't really look at secondary and cumulative impacts for the stormwater permit. . . . If it [the former-SWM ERP application] meets the criteria, it gets the permit. That--in the ERP, the previous dredge-and-fill side looks at the secondary and cumulative. The stormwater just--like Mr. Bateman testified." (Vol. III, p. 52). After some ambivalence, Mr. Myers also testified that DEP was not required to consider secondary impacts for the New Permit: WITNESS: . . . I did not or I do not consider secondary impacts for the stormwater management system. MS. HOLMES: So, what about cumulative impacts? WITNESS: No. MS. HOLMES: So it's your testimony that you did not review secondary and cumulative impacts-- WITNESS: That's correct. MS. HOLMES: --of this system? WITNESS: What I can say is that the existing system out there, from what I can tell, does not have any stormwater treatment. Basically, it's running off into the canals. The proposed project will provide stormwater treatment for, not only the new construction, which is proposed mainly on the northern peninsula, but it is also provided for that area which is now existing, it will provide stormwater treatment for that area also. And I consider that--I don't consider that to be a secondary impact. I see it as an offsetting improvement to potential as far as the water quality. (Vol. III, pp. 144-45). As discussed in detail in the conclusions of law, these witnesses have misread the provisions of the Basis of Review applicable to the New Permit. As noted in the conclusions of law, the requirements in the Basis of Review of analysis of secondary and cumulative impacts upon water quality and manatees are not limited to in-water or former-DAF activities. Satisfaction of Basis of Review Section 4 Direct vs. Secondary Impacts In terms of construction, the direct impacts of the proposed surface water management system are negligible. Nothing in the record suggests that the construction of the proposed system will violate any of the requirements of Basis of Review Section 4. In terms of maintenance, the direct impacts of the proposed surface water management system are negligible, except for the omission from the New Permit of any provision for the safe disposition of the contaminant removed from the underground vaults. However, the maintenance issues are better treated with the operation issues. In terms of operation, the direct impacts of the proposed surface water management system are substantial. As discussed in the conclusions of law, the analysis of the direct impacts of the operation of the proposed system is limited to the current level of uplands and marine activity at the marina. These direct impacts involve two aspects of the operation of the proposed system: the design capacity and the inspection and maintenance (including disposal of sediment) of the system components. As discussed in the conclusions of law, the secondary impacts involve the intended and reasonably expected uses of the proposed system. These impacts consist of the increased uplands and marine uses associated with the addition of 100 new wet slips, 227 new dry slips, and 115,000 square feet of building space with a restaurant. Apart from their contention that Applicant is required only to satisfy the volumetric requirements of Basis of Review Section 5, Applicant and DEP have contended that Petitioner is estopped from raising direct and secondary impacts because DEP considered these impacts when issuing the Original Permit four years ago. Perhaps the most obvious factual problem with this contention is that it ignores that the New Permit authorizes, for the first time, the construction of the 227 new dry slips and 115,000 square feet of buildings. As counsel for DEP pointed out during the hearing, the Original Permit was a DAF permit and did not extend to these upland uses. The contention that DEP considered these developments as secondary impacts because they were shown on drawings attached to the Original Permit gives too much significance to nonjurisdictional background items shown in drawings without corresponding textual analysis. More generally, the efforts of DEP and Applicant to restrict the scope of this case rely on a misreading of Original Permit Specific Condition 5. The purpose of Original Permit Specific Condition 5 is to "ensure a net improvement to water quality." The purpose of each of the requirements under Specific Condition 5 is to achieve an actual, not presumptive, improvement in water quality. Prohibiting the issuing agency from fully analyzing the direct and secondary impacts of the proposed surface water management system reduces the likelihood that the ensuing New Permit will perform its role, as envisioned in the Original Permit, of helping to achieve an actual, net improvement in water quality. The concept of a "net" improvement is exactly what DEP's witnesses disclaim having done in this case--balancing the potential environmental benefits to the water resources from the proposed surface water management system against the potential environmental detriments to the water resources from the development and land uses that are intended or reasonably expected to result from the construction of the proposed system. The failure to analyze the net gain or loss inherent in this important provision of Specific Condition 5.B undermines the likelihood that the effect of Specific Condition 5.B--a net improvement in water quality--will be achieved. It is therefore illogical to rely on Specific Condition 5.B, as DEP does, as authority for an artificially constrained analysis of the eligibility of the proposed system for a former-SWM ERP. The estoppel argument also ignores that Original Permit Specific Condition 5.B anticipated that the issuing agency would be SFWMD. It is unclear how the parties to the Original Permit, including DEP, would bind what appeared at the time to have to be SFWMD in the exercise of its lawful authority in issuing SWMs or former-SWM ERPs. The attempt of Applicant and DEP trying to limit the scope of this case also overlooks numerous changed circumstances since the issuance of the Original Permit. Changed circumstances militating in favor of the comprehensive analysis mandated for former-SWM ERPs include: increased trends in manatee mortality; increased boating pressure; persistent water quality violations in terms of dissolved oxygen, copper, and total coliform bacteria; a dramatic deterioration in dissolved oxygen levels; the initial presentation for environmental permitting of the previously unpermitted 227 additional dry slips and the 115,000 square feet of buildings; the current canal bottom profiles resulting from excessively deep maintenance dredging; the absence of an updated flushing study; and the failure to dredge the flushing canal required by the Original Permit. Disregarding the environmental and water quality requirements of Basis of Review Section 4 in this case would thus repudiate Specific Condition 5.B, especially when, among other things, the water quality of the canals has deteriorated dramatically with respect to dissolved oxygen, the canals continue to suffer from serious copper violations, the canals were recently maintenance dredged to excessive depths, no flushing study has examined these subsequent developments, and the intended uses to be facilitated by the New Permit more than double the capacity of the existing marina. 2. Water Quality The direct impacts of the proposed surface water management system, based on current levels of uplands and marine use at the marina, would adversely affect the quality of the receiving waters, in violation of Basis of Review Section 4.1.1(c). The excessively increased depths of the canals, especially with respect to the substantially widened depths of the north canal, raise the potential of water quality violations, especially given the history of this site. Potential sources of contaminants exist today in the canal bottoms, uplands, and marine activity associated with the marina. The potential for water quality violations, especially with respect to dissolved oxygen, increases in the absence of an updated flushing study. The potential also increases with the introduction of liveaboards and failure to dredge the flushing canal (or its replacement with culverts). In the face of these current threats to water quality, the New Permit fails to require a system with adequate capacity to accommodate fairly frequent storm events and fails to impose clear and enforceable inspection, maintenance, and disposal requirements for the underground vaults. Although better, the inspection and maintenance requirements for the stormwater inlets and boat wash area unnecessarily present enforcement problems. The effect of these failures in design capacity and inspection and maintenance is synergistic. Deficiencies in vault capacity mean that storms will more frequently resuspend the settled contaminants in the vaults and flush them out into the canal waters. Excessively long maintenance intervals and poor maintenance procedures will increase the volume of contaminants available to be flushed out into the canal waters. Improper disposition of removed contaminants endangers other water resources. The introduction of untreated or inadequately treated water into the canals means the introduction of two substances that will contribute to the current water quality violations. Organics, such as from the boat wash operations and other uplands uses, will raise biochemical oxygen demand, which will accelerate the deterioration in dissolved oxygen levels. Copper removed during boat wash operations, leaching from painted hulls, or remaining in the uplands from past marina operations will also enter the canals in this fashion. On these facts, Applicant has failed to provide reasonable assurance that the operation of the proposed surface water management system will not result, in the long-term, in water quality violations. Applicant has failed to demonstrate that the operation of the proposed system, even as limited to existing levels of use of the uplands and marine waters, will not contribute to existing violations of dissolved oxygen and copper levels. Obviously, the situation is exacerbated by consideration of the uses intended and reasonably expected to follow the construction of the proposed system. With the growing popularity of boating in Lee County over the past 20 years, it is reasonably likely that an expanded marina operation, located close to downtown Fort Myers, will successfully market itself. Thus, many more boats will use the marina because it will offer more wet and dry slips and new buildings, including a restaurant, and the pressure on water quality will intensify with the intensification of these uses. The added intensity of upland and marine uses will contribute to the above-described violations of water quality standards for dissolved oxygen and copper, probably will contribute to the above-described violations of water quality standards for total coliform bacteria and lead, and may contribute to the recurrence of water quality violations for other parameters for which the canals were previously in violation. On these facts, Applicant has failed to provide reasonable assurance that the direct and secondary impacts of the proposed system will not adversely affect the water quality of the canals. 3. Manatees and Manatee Habitat By letter dated June 26, 1998, from a DEP Environmental Specialist to a DEP permitting employee, the Environmental Specialist provided an initial opinion concerning the revisions that Applicant sought to the Original Permit so as to allow liveaboards, replace the flushing canal with culverts, and relocate the travel lift to the north canal. The letter accompanies a Manatee Impact Review Report, also dated June 26, 1998. The Manatee Impact Review Report notes the pending application for the New Permit. The report considers at length the extent of manatee use of Deep Lagoon and the nearby portions of the Caloosahatchee River. The Manatee Impact Review Report states: This project [i.e., the relocation of the boat lift to the north canal, addition of liveaboards, and conversion of the flushing canal to flushing culverts] is expected to add a significant number of boats to this system, significantly increase the level of boat traffic, and change boat traffic patterns in the study area. The vessels from this project are expected to produce significant adverse impacts to manatees that use the Deep Lagoon in the immediate vicinity of the project, as well as in the boater's sphere of influence of the project. Secondary adverse impacts include lethal and sublethal watercraft-related injuries, disturbance contributing to stress, and alteration of natural behaviors. The secondary impacts expected with this project are compounded by the cumulative secondary effects from other facilities in this system. Just south of this project site, another marina was recently constructed (Sun City Corporation aka Gulf Harbor Marina aka River's Edge), which has approximately 190 wet slips. Since October 1995, there have been seven watercraft-related deaths within five miles of this project location. The Gulf Harbor Marina was constructed in late 1995, and was almost fully occupied during 1996. Watercraft-related manatee deaths increased significantly during this time, with one in December 1995, two in 1996 and four in 1997. Additional on-water enforcement by the City of Cape Coral was considered part of the offsetting measures to address the expected impacts to manatees from increases in boat density. This offsetting measure, however, appears to be ineffectual at this time. The Manatee Impact Review Report concludes that the north canal and its mouth are "particularly important" for manatee because of the availability of freshwater from the adjoining Iona Drainage District ditch immediately north of the north canal and "historical use indicates that this area appears to be the most frequently used area in the Deep Lagoon system." The report cautions that the relocated travel lift may significantly increase the number of boats in the little-used north canal, whose narrowness, coupled with moored, large boats on the one side, "would produce significant, adverse impacts to the endangered manatee." The Manatee Impact Review Report finds that Applicant failed to provide reasonable assurance regarding the conservation of fish and wildlife, unless several new conditions were added. These conditions include prohibitions against boat launching along the shoreline of the north canal and the addition of manatee-exclusion grating to any culverts that may be approved. As defined in this recommended order, the direct impacts upon manatees from the proposed surface water management system would be moderate. As defined in this recommended order, direct impacts would not involve any increase in boating pressure. The greater impacts would be in the deterioration of two measures of water quality that are crucial to manatees: dissolved oxygen and copper. However, the secondary impacts are dramatic, not de minimis, and arise from the intended and reasonably expected uses to follow from the construction of the proposed surface water management system. The increased boat traffic intended and reasonably expected from more than doubling the marina capacity, through the addition of 100 wet slips and 227 dry slips, and the addition of 115,000 square feet of buildings, including a restaurant, would adversely impact the value of functions provided to manatees by the affected surface waters. Manatee mortality has increased as boat traffic has increased. Substantial numbers of boaters have ignored speed limits. Quality manatee habitat in this critical area along the Caloosahatchee River is not plentiful. On these facts, Applicant has failed to provide reasonable assurance that the secondary impacts of the proposed system will not adversely impact the abundance and diversity of wildlife and listed species, of which manatees are one, and the habitat of wildlife and listed species. 4. Minimization and Mitigation Due to their contention that Basis of Review Section 4 does not apply to this case, DEP and Applicant did not demonstrate compliance with the minimization and mitigation sections of Basis of Review Section 4. However, the record supports the possibility of design alternatives for water quality impacts, if not manatee impacts, that DEP and Applicant must consider before reanalyzing the direct, secondary, and cumulative impacts of the proposed system on the water resources and, if appropriate, potential mitigation options. Mr. Bateman testified that SFWMD is the only district that permits surface water management systems relying on the settling out of sediments in the bottom of a storage-type detention system. (Vol. II, p. 18). He explained that other districts rely on systems that, taking advantage of the three to four feet typically minimally available between ground surface and the top of the water table, retain the runoff and allow it to percolate into the ground. (Vol. II, p. 19). One relatively straightforward design alternative, which would address water quality issues, would be to perform a flushing study; analyze applicable drainage level of service standards imposed by state, regional, and local authorities; and increase the capacity of the surface water management system to accommodate the runoff from storms of sufficient size and frequency that would be accommodated by the proposed system. Another feature of this design alternative would be to impose for each component of the system a detailed, enforceable program of inspection, maintenance, and contaminant-disposal. This program would incorporate the manufacturer's recommendations for the manner and minimum frequency of inspection and maintenance, but would require more frequent removal of contaminated sediments during periods when larger storms are more numerous (e.g., a specified wet season) or more intense (e.g., a specified hurricane season), as well as any periods of the year when the marine and upland uses are greatest (e.g., during the winter season, if this is the period of greatest use). As testified by Mr. Bateman, the proximity of the water table to the surface, as well as South Florida land costs, discourage reliance upon a conventional percolation-treatment system, even though the site's uplands are 5 feet NGVD and the water table is 1.2 feet NGVD. The bottom of the proposed system is 2.5 feet NGVD, which leaves little soil for absorption. If the nature of the contaminants, such as copper, does not preclude reliance upon a percolation-treatment system, DEP and Applicant could explore design alternatives that incorporate more, shallower vaults, which would increase the soil layer between the bottom of the vaults and the top of the water table. If the technology or contaminants preclude reliance upon such an alternative, the parties could consider the relatively costly alternative, described by Mr. Bateman, of pool-like filters with an "actual filtration device." (Vol. II, pp. 19-20). The preceding design alternatives would address water quality concerns, including as they apply to manatees, but would not address the impact of increased boating upon manatees. The record is not well developed in this regard, but DEP and Intervenor have considerable experience in this area, and it is premature to find no suitable means of eliminating or at least adequately reducing the secondary impacts of the proposed system in this crucial regard as well. In any event, Applicant has failed to consider any design alternatives to eliminate or adequately reduce the direct and secondary impacts of the proposed surface water management system. Having failed to consider minimization, DEP and Applicant have failed to identify the residual direct and secondary impacts that might be offset by mitigation. Applicant has thus failed to mitigate the direct and secondary impacts of the proposed surface water management system.
Recommendation It is RECOMMENDED that the Department of Environmental Protection enter a final order revoking its determination of an exemption for maintenance dredging in DOAH Case No. 98-3901 and denying the application for an environmental resource permit in DOAH Case No. 98-5409. DONE AND ENTERED this 24th day of November, 1999, in Tallahassee, Leon County, Florida. ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of November, 1999. COPIES FURNISHED: Kathy Carter, Agency Clerk Office of the General Counsel Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Teri Donaldson, General Counsel Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 T. Elaine Holmes, Attorney 14502 North Dale Mabry, Suite 200 Tampa, Florida 33618 David Gluckman Gluckman and Gluckman 541 Old Magnolia Road Crawfordville, Florida 32327 Matthew D. Uhle Humphrey & Knott, P.A. 1625 Hendry Street Fort Myers, Florida 33901 Francine M. Ffolkes Senior Assistant General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Mail Station 35 Tallahassee, Florida 32399-3000
Findings Of Fact The proposed project is a six-lane, combination low and high level bridge crossing Mill Cove and the St. John's River in Duval County, Florida. The project entails construction of approximately 6,000 feet of low level trestle-type bridge structure and approach spans beginning on the south side of Mill Cove and extending across the Cove to the northern edge of Quarantine Island, an artificial spoil island; 3,000 feet of high level bridge crossing the main channel of the St. John's River; and northern approach spans touching down on Dame Point on the northern shore of the St. John's River. In order to construct the proposed project, JTA is required to obtain a water quality permit and certification from DER. JTA filed its application with DER, accompanied by supporting data, including several studies performed by professional consultants. After review of the application, DHR filed notice of its intent to issue the requested water quality permit and certification, and Petitioners filed a timely request for a hearing pursuant to Section 120.57(1) Florida Statutes, to oppose the issuance of the permit and certification. Petitioners are various groups and individuals concerned about water quality in the St. John's River and the Jacksonville area. Petitioners' standing to seek relief in this proceeding was stipulated by all parties. Construction of the project will result in: filling of approximately .07 acres of wetlands to construct the south abutment on the shore of Mill Cove; dredging of approximately 185,000 cubic yards of material from Mill Cove to create a 4,400 foot long, 190 foot wide barge access channel, with a five foot navigation control depth parallel to the low level portion of the project; temporary filling of approximately .3 acres of wetlands above mean high water on the south shore of Quarantine Island to provide construction access to the island, which area is to be restored upon completion of construction; construction of a diked upland spoil containment site approximately 31 acres in size above mean high water on Quarantine Island to retain all dredge spoil associated with the project; construction of a temporary dock at the northern end of Quarantine Island for access and staging purposes, which is to be removed on project completion; and filling of approximately 16,000 cubic feet of material waterward of mean high water for rip-rap protection around main piers in the St. John's River. Dredged materials will be removed by hydraulic dredges. The St. John's River and its tributaries have been designated Class III waters by DER in the project area. The project involves dredging below mean high water and filling above mean high water, and is a dredge-and-fill project for purposes of Chapters 403 and 253, Florida Statutes, and Chapters 17-3 and 17-4, Florida Administrative Code, and is regulated by DER. The project is an element in a proposed eastern bypass around the City of Jacksonville. It is expected that, as a result of the project, existing area industry will receive more efficient transportation service, commuter trip miles from southeastern Jacksonville to northern Jacksonville will be reduced, transportation routes to education facilities will be improved, and tourist traffic will be routed around downtown Jacksonville, reducing miles traveled to nearby beach resorts and thereby relieving downtown congestion. The benefits to costs ratio of the project appears positive and beneficial to Duval County and Jacksonville, in that for every dollar spent to construct the project, $2.80 could be returned to the community in the form of increased economic activity and more efficient transportation. Testimony clearly established that the state waters in the project area are currently severely degraded and are not likely to meet Class III water quality standards. Violations of Class III standards for dissolved oxygen and some heavy metals, such as mercury, presently exist as background conditions in the St. John's River and Mill Cove. Further, a water quality analysis performed by DER in the project area indicates high background concentrations of heavy metals and PCB's in both the water column and sediments in the project area. When the pro posed project is analyzed within the context of these existing background water quality conditions, it appears highly unlikely that any impact from the project will further degrade existing conditions. The project as currently designed includes plans for total containment of spoil material resulting from dredging activity on the upland portions of Quarantine Island. There will be no direct discharge of dredge $materials from this containment area into the receiving waters of the state. JTA performed a water and sediment analysis of the project area, the purpose of which was to determine the existence and concentrations of specific pollutants that could adversely impact Class III waters if reintroduced into the aquatic system. JTA employed a consultant whose analytical program was designed in consultation with DER and complied with all standard testing procedures required by Rule 17-3.03, Florida Administrative Code. This analysis identified three primary-project activities where control of toxic and deleterious materials was critical: turbidity control; upland spoil containment; and direct discharge of spoil water to state waters. Sediments in the Mill Cove area are extremely fine and may be resuspended in the water column in quantities that could violate state water quality standards if dredging is done improperly. It appears from the evidence that any turbidity problem can be avoided by employing silt curtains and hydraulic dredging during channel excavation. Silt curtains should adequately retain turbidity below levels which would violate state water quality standards, in view of the fact that the JTA study hypothesized a "worst-case" condition for projecting turbidity and pollutant concentration by assuming no upland spoil containment, silt curtains or reasonable mixing zone. Although use of silt curtains and hydraulic dredging cannot absolutely guarantee zero-discharge of suspended sediments from the dredging area, the proposed system of turbidity control is adequate to provide reasonable assurance of non-violation of state water quality standards. Due to the existing toxic background conditions in Mill Cove, DER imposed a permit condition requiring spoil from dredging activities to be completely contained in an upland landfill-type site, with no overflow that could allow effluent to return to waters of the state. The upland dike system proposed in the project application is designed to retain all spoil material and water without direct discharge into state waters. Testimony established that the proposed dike system is designed to hold far more spoil material than the proposed project will generate. Although the dike system is to be constructed from dredged material previously deposited on Quarantine Island, it appears from the testimony that these materials were dredged from the main channel of the St. John's River and are cleaner and sandier in character than sediments in the Mill Cove area. The dike system, in conjunction with natural percolation and evaporation, is adequately designed to retain dredge spoil on the upland portion of Quarantine Island, and can reasonably be expected not to release toxic and deleterious substances into receiving waters of the state. It is also significant that a condition of the requested permit requires project water quality monitoring to afford continuing assurance that the project will not violate standards contained in Chapter 17-3, Florida Administrative Code. These standards and the conditions required to achieve them have been included in DER's letter of intent to issue the permit for this project. It is specifically concluded from the evidence that project dredging will not release toxic and deleterious substances into Class III waters in violation of state water quality standards, and that project dredging in Mill Cove incorporates reasonable safeguards for spoil disposal and turbidity control so as to assure non-violation of state water quality standards. JTA plans to use a direct discharge method to dispose of storm water from the bridge. Storm water will fall through 4-inch screened holes called "scuppers" placed at regular intervals along the bridge surface directly into either Mill Cove or the St. John's River. JTA was required to provide in its application reasonable assurance that storm water runoff from the Project would not exceed applicable state standards for turbidity, BOD, dissolved solids, zinc, polychlorinated biphenols, lead1 iron, oils or grease, mercury, cadmium and coliform. To this end, JTA submitted a study entitled Effect of Rainfall Runoff from Proposed Dame Point Bridge on Water Quality of St. John's River. This study analyzed the chemical composition of storm water runoff from an existing bridge, comparable in both size and design, to the proposed project, which crosses the St. John's River south of the City of Jacksonville. This study adequately established that storm water runoff into the St. John's River across the length of the proposed bridge will not degrade the water quality of the St. John's River below current water quality standards. All but three of the parameters tested in the study were within standards contained in Chapter 17-3, Florida Administrative Code. The remaining three pollutants were either not automobile-related, or would not violate applicable water quality standards after a reasonable opportunity" for mixing with receiving waters. One of these pollutants, mercury, is not automobile-related, and the concentration of mercury discovered in bridge runoff test samples was essentially the same as that measured in rainfall samples. The sampling for mercury was performed using the ultrasensitive "atomic absorption" method, which is capable of measuring tenths of a part per billion of mercury. Another method, the "Dithizone" method, is a technique recognized as effective by DER, and would have, if utilized, yielded a result within the "none detectable" standard contained in Rule 17-3.05(2) , Florida Administrative Code. As to the remaining two pollutants, coliform and lead, testimony established that a dilution rate of 400 to 1, after mixing with receiving waters, would not result in violation of applicable Class III water standards. Testimony also clearly established that water circulation in the project area would result in the requisite dilution ratio of approximately 400 to 1. The storm water runoff study was performed on a bridge similar in all important characteristics to the proposed project, and therefore validates the scientific methodology utilized to determine the expected impact of runoff from the proposed project on water quality in the St. John's River. The applicant has provided in its permit application the best practicable treatment available to protect state waters in the design of both the low and high level portions of the proposed bridge. Extensive research and analysis of design alternatives for both the low and high level portions of the bridge were undertaken by JTA and its consultants prior to selecting the proposed design for the bridge. JTA prepared and submitted to DER, as part of the application process, a document entitled Summary of Construction Techniques in Mill Cove, Dame Point Expressway. This document analyzed and summarized the available construction and design alternatives for the low level trestle portions of the project. The analysis included consideration of overhead construction, construction from a temporary wooden structure parallel to the project, and construction from barges using a shallow channel parallel to the project. The design chosen will cost more than one million dollars less than the next alternative, and will cut construction time by two years over the next alternative design. Given the demonstrated need for the proposed project, the already degraded water quality in the project area, the safeguards for water quality contained-in the project design, and the savings to be realized in both cost and time of construction, the design presently contained in the application is the best practicable. Both Petitioners and JTA have submitted proposed findings of fact. Petitioners' Proposed Findings of Fact numbered 1 through 4 have been substantially adopted herein. JTA's Proposed Findings of Fact numbered 1 through 7 have also been substantially adopted. To the extent that proposed findings of fact submitted by either Petitioners or JTA are not adopted in the Recommended Order, they have been specifically rejected as being either irrelevant to the issues in this cause, or as not having been supported by the evidence.
Findings Of Fact By Joint Application for Works in the Waters of Florida filed June 22, 1994, Petitioner requested a permit to dredge about 500 square feet of uplands for a boatslip and to maintenance dredge 1700-1900 square feet in an adjacent canal, removing 125 cubic yards of material waterward of mean high water. The Application describes the work as including a vertical concrete seawall running 92 feet inside the boatslip, a cat walk from the boatslip to the canal, and a roof over the boatslip. A drawing attached to the Application depicts the proposed boatslip at the east end of the Petitioner's lot and with rounded corners to facilitate flushing. By Notice of Permit Denial executed October 24, 1994, Respondent advised that the permit was denied. The Notice states that water quality in the surrounding canal system is generally poor with low dissolved oxygen (DO) levels. The shoreline vegetation is primarily mangroves, which are tall but not robust. The proposed dredge area consists of a healthy littoral shelf with live oysters and shells. Based on the foregoing site description, the Notice denies the permit because of impacts to the conservation of fish and wildlife and marine productivity and a degradation of the current condition and relative value of the affected area. The Notice relates all of these factors to the loss of the mangroves and dredging of the adjacent canal bottom. The Notice adds that the project would have an adverse cumulative impact on water quality and public resources if similar projects were constructed. In the alternative, the Notice suggests that Petitioner eliminate the dredging into the uplands and canal and instead construct a boat shelter in the canal in an area of existing adequate water depth. By letter dated November 7, 1994, Petitioner challenged the denial. The letter states that Petitioner has maintained an environmentally productive shoreline consisting of mangroves, oysters, and rip rap, rather than concrete seawalls, as are found along the shoreline of most of his neighbors. The letter suggests that, if Petitioner followed Respondent's suggestion and built a slip in the canal, Petitioner would be permitted to do maintenance dredging in the artificial canal. The letter concludes that the maintenance dredging and shading of an over- the-water boathouse would have more impact on the environment than dredging uplands and a small access channel to the slip. Petitioner's residence is located in Aqualane Shores, which is an established residential subdivision located between Naples Bay on the east and the Gulf of Mexico on the west. Petitioner's lot is located about two-thirds of the distance down a long, relatively wide artificial canal known as Jamaica Channel. Jamaica Channel intersects Naples Bay to the east of Petitioner's property. Jamaica Channel is a Class III waterbody. Petitioner owns about 200 feet of shoreline at the corner of Jamaica Channel and a shorter, narrower canal. The entire area is heavily canalized and completely built-out with nearly exclusively single family residences. Most of the shoreline in the area is bulkheaded with concrete seawalls. Jamaica Channel was dredged in the early 1950s. Early riprap revetment crumbled into the water and in some areas became colonized by oysters, which supply food and filter impurities from water. Shoreline owners weary of repairing riprap installed vertical seawalls, thereby destroying the oyster beds and intertidal habitat. But much of the riprap adjacent to unbulkheaded shoreline eventually was stabilized by mangrove roots. The absence of concrete seawalls along Petitioner's shoreline has permitted a significant colony of oysters to populate the 25-foot littoral shelf running along Petitioner's shoreline. The oysters form a hemisphere, thickest at the middle of Petitioner's shoreline and narrowest at the east and west edges, narrowing to a width of as little as 6-10 feet. In recent years, Australian pines were removed from Petitioner's shoreline. As a result, mangrove seedlings have successfully occupied much of the shoreline. The proposed boatslip would be located at the east end of the shoreline where there is a natural gap in the mangroves. As a result, only three mangroves would have to be removed, and a relatively narrow band of oysters would be dredged and, as offered by Petitioner, relocated. The proposed dredging involves uplands and submerged bottom. As to the uplands, Petitioner intends to create a slope in the slip with the rear one to one and one-half feet shallower than the front, although this slope is not reflected on the Application. The purpose of the slope is to facilitate flushing. Petitioner evidently intends to dredge sufficient material to fill the rear of the slip with two feet of water at mean water and the front of the slip with three feet of water at mean water. The dredging in Jamaica Channel would involve an 18-20 foot wide path leading to the slip. Beyond the oysters, the bottom is fine sandy substrate with scattered rock. The relocation of oyster-covered rocks might be successful, if there are sufficient areas suitable for colonization that have not already been colonized. However, the dredged areas would not be recolonized due to their depths. Presently, the Application discloses level dredging down to an elevation of -5 NGVD. Petitioner's intent to slope the boatslip has been discussed above. Although Petitioner did not reveal a similar intent to slope the area dredged in Jamaica Channel, Petitioner's witness, Naples' Natural Resource Manager, testified that he would insist on similar sloping the entire length of the dredged area, so that the deepest area would be most waterward of the boatslip. If the dredged canal bottom were not sloped, Petitioner proposes removing about 4.25 feet of material about ten feet from shore, about 3.4 feet of material about 22 feet from shore, about 1.8 feet of material about 30 feet from shore, and about 0.5 feet of material about 40 feet from shore. Petitioner did reveal that the cross-section indicating a dredged depth of -5 feet applies only to the centerline of the dredge site, which would be tapered off to the east and west. The slope of the taper was not disclosed, but it is evident that the affected areas within 20 feet of the shoreline would be dredged at least two feet deeper and, in most areas, three feet deeper. The deepening of Jamaica Canal in the vicinity of the shoreline would not only eliminate existing oyster habitat, but would also eliminate habitat currently used by small fish. The deepening of Jamaica Channel in the vicinity of the shoreline would also impact water quality in the area. Water quality in Naples Bay and Jamaica Channel is poor and violates water quality standards for DO. Due to poor mixing of freshwater infusions and saltwater, DO levels deteriorate with depth. Where DO levels are probably adequate in the shallows around Petitioner's shoreline, the proposed dredging would likely result in depths at which violations could be expected to occur. Petitioner offers to install an aerator to introduce oxygen into the water. Ignoring the fact that the aerator was to operate only in the boatslip and not in the remainder of the dredged area, Petitioner did not show the effect on DO levels of this proposal. Even if the aerator had been shown to result in a net improvement in area DO levels, Petitioner also failed to show how the operation of the aerator would be guaranteed to extend indefinitely, or at least until the dredged areas were permitted to regain their pre-dredged depths. Petitioner argues that he could construct an over-the- water boathouse and maintenance dredge, and the resulting environmental impact would be greater. Several factors militate against this proposed alternative and thus preclude consideration of this alternative against the proposed project. Most significantly, the oysters have occupied the littoral shelf adjacent to Petitioner's shoreline for a period in excess of 20 years. There is considerable doubt as to whether Petitioner would be permitted to maintenance dredge under these and other circumstances. Respondent argues more persuasively the issue of cumulative impacts. There are about 350 residences in Aqualane Shores, of which only 150 have boatslips similar to that proposed by Petitioner. This raises the prospect of an additional 200 boatslips as a cumulative impact on water and biological resources.
Recommendation It is hereby RECOMMENDED that the Department of Environmental Protection enter a final order denying the application. ENTERED on May 26, 1995, in Tallahassee, Florida. ROBERT E. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings on May 26, 1995. APPENDIX Rulings on Petitioner's Proposed Findings 1-2: adopted or adopted in substance. 3: rejected as irrelevant. 4-5 (first sentence): adopted or adopted in substance. 5 (remainder)-6: rejected as irrelevant. 7: rejected as recitation of evidence. 8: adopted or adopted in substance. 9: rejected as unsupported by the appropriate weight of the evidence. 10: rejected as unsupported by the appropriate weight of the evidence, irrelevant, and not findings of fact. 11-12 (first sentence): adopted or adopted in substance. 12 (remainder): rejected as recitation of evidence and as unsupported by the appropriate weight of the evidence. 13: rejected as unsupported by the appropriate weight of the evidence. Rulings on Respondent's Proposed Findings 1-20: adopted or adopted in substance. 21-25: rejected as unnecessary. 26-29: adopted or adopted in substance. 30: rejected as unnecessary. COPIES FURNISHED: Virginia B. Wetherell, Secretary Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Kenneth Plante, General Counsel Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Miles L. Scofield Qualified Representative Turrell & Associates, Inc. 3584 Exchange Ave., Suite B Naples, FL 33942 Christine C. Stretesky Assistant General Counsel Department of Environmental Protection 2600 Blair Stone Road Tallahassee, FL 32399-2400
Findings Of Fact On July 19, 1991, the Petitioner, Cahill Pines and Palm Property Owners Association, Inc. (Cahill), filed a permit application with the Department of Environmental Resources, predecessor to the Respondent, Department of Environmental Protection (Department), for a permit to remove two earthen plugs in the Cahill canal system, located in Big Pine Key, Monroe County, Florida. The plugs were to be removed to a depth of -5.5 feet N.G.V.D. Kenneth Echternacht, a hydrologist employed by the Department, had performed a hydrographic review of the proposed project and reduced his findings to writing in a memorandum dated June 25, 1993. Mr. Echternacht recommended that the project not be permitted. On August 20, 1993, the Department issued a notice of its intent to deny Cahill's application to remove the plugs. The notice included six proposed changes to the project which would make the project permittable. Cahill requested an administrative hearing on the Department's intent to deny the permit. On March 3 and 4, 1994, an administrative hearing was held on the issue of whether a permit should be issued. The hearing officer entered a recommended order on May 9, 1994, recommending that a final order be entered denying the permit. The Department issued a final order on June 8, 1994, adopting the recommended order of the hearing officer and denying the permit. See Cahill Pines and Palm Property Owners Association v. Department of Environmental Protection, 16 F.A.L.R. 2569 (DER June 8, 1994). In the final order the Department found that the following findings of Mr. Echternacht were "scientifically sound and credible conclusions": The estimated flushing for the presently open portion of the waterway was calculated to be 14.5 days. The flushing for the open section exceeds the 4 day flushing criterion by approx- imately 3.6 times. Clearly, the open portion poses a potential problem to the maintenance of acceptable water quality. For the presently closed sections of the waterway, the calculated flushing time was found to be 38.6 days. Again, this system would pose a significant potential for contamination to adjacent open waters if opened for use. The waters behind the barrier that presently appear to pose no problem would clearly become a repository for contaminants associated with boat usage. Because of the exceptionally long flushing time, contaminants would build up over time. Below standard water quality throughout the waterway would be expected and, associated with this, below standard water would be exported into adjacent clean water on each ebbing tide. The final order also found the following facts: 13. Neither the water in the open canals nor the water in the closed canals is presently of substandard quality. * * * Petitioner's plug removal project will also spur development in the Cahill subdivision and lead to an increase in boat traffic in the Cahill canal system, as well as in the adjacent waters of Pine Channel. Such activity will result in the discharge of additional contaminants in these waterways. As Echternacht stated in his June 25, 1993, memorandum that he sent to O'Connell, '[b]ecause of the [canal system's] exceptionally long flushing time, [these] contaminants would build up over time' and result in a significant degradation of the water quality of not only the Cahill canals, but also of Pine Channel, into which Cahill canals flow. This degradation of water quality will have an adverse effect on marine productivity and the conservation of fish and wildlife that now inhabit these waterways. Consequently, in the long run, the removal of the plugs will negatively impact fishing opportunities in the area. On the other hand, the project will have a beneficial effect on navigation and recreational boating and related activities. It will have no impact on historical and archaeological resources. On April 10, 1995, Cahill submitted a permit application to the Department to remove portions of the two canal plugs. Cahill proposed to leave an island in the center of each plug. The islands would be stabilized with riprap, and mangrove seedlings would be planted in the riprap. By letter dated April 21, 1995, the Department returned the April 10 permit application to Cahill along with the $500.00 processing fee. The Department advised Cahill that the application was not substantially different from the 1991 permit application which was denied by final order. The Department further advised that Cahill could resubmit the application and application fee if it wanted the permit to be processed but the Department would deny the application on the basis of res judicata. On May 17, 1995, Cahill submitted a revised permit application along with the processing fee. A circulation culvert had been added to the project. Ken Echternacht performed a hydrographic review of the proposed project. In a memorandum dated May 25, 1995, Mr. Echternacht recommended that the permit be denied for the following reasons: The proposed 24-inch culvert connection would not be expected to be visible hydraulically. A 24-inch diameter culvert, length 181 ft would be expected to have a friction factor several orders of magnitude greater than the adjacent canals. As such, water would not be expected to pass through the connector unless there were a sizeable head to drive the flow. No studies and/or supporting documentation have been provided to support the design in terms of the documenting the amplitude and repeatability of the flow driving force. Cutting holes through embankments do not necessarily result in flushing relief. As stated in 1, above, any and all proposed design modifications to the proposed waterway must be accompanied by adequate design justifi- cation based on hydrographic modeling supported by site specific data support. The culvert design proposed does not meet the above require- ment. The proposal is nothing new. In the hearing, ideas such as the above were suggested. However, as was stated in the hearing any and all such proposals must be supported by proper engineering study. On July 7, 1995, the Department issued a Notice of Permit Denial, denying the May, 1995 permit application on the basis of res judicata, stating that the May 1995 permit was not substantially different from the 1991 permit application which had been denied and that no studies had been submitted by Cahill that would support that the use of the islands and culvert would increase the flushing rate to the four day flushing criterion established in the hearing on the 1991 permit application. At the final hearing counsel for Cahill stated for the record that the use of the islands and the culvert would not increase the flushing rate to four days.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a Final Order be entered denying Cahill Pines and Palms Property Owners Association, Inc.'s application for a permit to remove two plugs separating the open and closed canal sections of the Cahill canal system, placing an island in the center of each plug, and adding a 24 inch culvert connection. DONE AND ENTERED this 31st day of July, 1996, in Tallahassee, Leon County, Florida. SUSAN B. KIRKLAND Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 31st day of July, 1996. APPENDIX TO RECOMMENDED ORDER, CASE NO. 95-4377 To comply with the requirements of Section 120.59(2), Florida Statutes (1995), the following rulings are made on the parties' proposed findings of fact: Petitioner's Proposed Findings of Fact. Paragraphs 1-7: Accepted in substance but not necessary to be incorporated in the recommended order. Paragraph 8: The evidence presented showed that there is a dispute of whether the waters are now of substandard quality. For the purposes of this hearing, it is not necessary to determine whether the water quality is presently substandard. Based on the assumption that the water quality is not substandard, Petitioner has failed to show that the change in the design of the project is sufficient to warrant the rejection of the applicability of the doctrine of res judicata. Petitioner has failed to show that the addition of islands and a culvert will eliminate the potential for future contamination of the waters. The second sentence is accepted in substance but not necessary to be incorporated in the recommended order. Paragraphs 9-11: Accepted in substance but not necessary to be incorporated in the recommended order. Paragraphs 12-15: Accepted in substance to the extent that for the purposes of this hearing the water quality is assumed not to be substandard. Paragraph 16: Rejected as unnecessary. Paragraphs 17-27: Rejected as subordinate to the finding that for the purposes of this hearing the present water quality is assumed not to be substandard. Paragraphs 28-30: Accepted in substance. Paragraph 31: Accepted in substance to the extent that the changes in the design will not increase the flushing rate to four days. Paragraphs 32-33: Accepted to the extent that they were findings in the final order on the 1991 application. Paragraphs 34-35: Accepted to the extent that the slow flushing rate is one of the criteria to be considered. The increase of development and boat traffic are also contributors to the potential of contamination building up. Petitioner has not demonstrated that the use of islands and a culvert will eliminate the potential for contamination. Respondent's Proposed Findings of Fact. Paragraphs 1-10: Accepted in substance. Paragraphs 11-14: Rejected as unnecessary. Paragraph 15: Accepted in substance. Paragraph 16: Accepted in substance as corrected. Paragraph 17: Accepted. Paragraphs 18-21: Accepted in substance. Paragraph 22: Accepted. Paragraph 23: Rejected as unnecessary. COPIES FURNISHED: David Paul Horan, Esquire Horan, Horan and Esquinaldo 608 Whitehead Street Key West, Florida 33040-6549 Christine C. Stretesky, Esquire John L. Chaves, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Kenneth J. Plante, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Virginia B. Wetherell, Secretary Department of Environmental Protection 3900 Commonwealth Boulevard, Douglas Building Tallahassee, Florida 32399-3000
Findings Of Fact This hearing was occasioned by the Respondent's denial of (an) environmental permit(s) requested by the Petitioner, Baker Cut Point Company, a corporation owned by James C. Dougherty. The Respondent has asserted permit jurisdiction pursuant to Chapters 253 and 403, Florida Statutes, and attending regulatory provisions of Chapter 17, Florida Administrative Code. The Petitioner requested a formal hearing to consider the matters in dispute, and that hearing was conducted on the dates indicated before and in keeping with Subsection 120.57(1), Florida Statutes. The Petitioner owns land in Monroe County, Florida, identified as Buccaneer Point. This parcel of land is a peninsula which extends from the west side of Key Largo, Florida, and has as its essential features two interior lakes and well-defined mangrove stands to include red mangroves (Rhizophora mangle) and black mangroves (Avicennia germinans). This parcel of land is bordered on the north by Buttonwood Sound and on the south by Florida Bay, navigable water bodies. Respondent's Exhibit No. 1, admitted into evidence, depicts the present condition of the parcel of land, with the exception of proposals involved in the permit review process, which are the subject of this Recommended Order and the companion case of James C. Dougherty v. State of Florida, Department of Environmental Regulation, DOAH Case No. 80-1055. At present, the two lakes do not offer normal access to Buttonwood Sound and Florida Bay, nor do they offer an interior water connection between the two lakes. The southernmost lake does have intermittent water exchange with Florida Bay. Those lakes are identified as North Lake and South Lake. The Petitioner had initially applied for permission to place 75,000 cubic yards of clean limerock fill at the project site and indicated that the fill would be placed landward of the mean high water line. That fill would have covered approximately 17.56 acres in the residential subdivision. The application was made on October 27, 1978. See Petitioner's Exhibit No. 20, admitted into evidence. The Respondent issued an Intent to Deny the permit connected with that request, and that Intent to Deny was issued on April 3, 1980, asserting permit jurisdiction by the Respondent under the provisions of Chapters 253 and 403, Florida Statutes. See Petitioner's Exhibit No. 5, admitted into evidence. The Petitioner modified the permit application effective April 24, 1981. Under the terms of the revised permit application, the Petitioner would place limerock fill over 5.7 acres, including mangroves, constituting approximately 30,000 cubic yards of fill. Additionally, the applicant modified the permit request to include filling the exterior rim of the interior lakes to create a littoral zone and the placement of a berm at that exterior. See Petitioner's Exhibit No. 6, admitted into evidence. The project, as contemplated, allows for a preserve area of mangroves along the northern end of the peninsula and also employs a "pad" concept to preserve the mangrove acreage where fill is to be placed. Those "pads" for houses would be bordered by six- inch dikes to divert upland runoff which might find its way into the interior lakes on the property. The fill material to be placed in those areas, other than the lakes, would be placed above or landward of the line of mean high water, as determined by the mean high water line survey found in Petitioner's Exhibit No. 1, admitted into evidence, dating from December, 1975, and whose methodology was approved on January 15, 1980, for purposes of Chapter 177, Florida Statutes, through the offices of the State of Florida, Department of Natural Resources. This factual determination is also borne out by a review of the Petitioner's Exhibit No. 6, in pari materia with Respondent's Exhibit No. 1 and Petitioner's Exhibit No. 1. As the lakes are now constituted, the placement of the limerock fill at the fringe of the lakes would not be waterward of the line of mean high water; however, when the placement of this fill material is considered in view of the permit request made in Division of Administrative Hearings' Case No. 80-1055, which permit request attempts to open up the lakes by direct water connection to the aforementioned navigable water bodies, then the placement of the fill would be below the line of mean high water. See Petitioner's Exhibit No. 6. Therefore, treatment of the placement of fill for purposes of this case will be considered on a basis that the lakes remain landlocked and the matter of the placement of this fill will be a matter assumed in the Division of Administrative Hearings' Case No. 80-1055, dealing with an attempt to open those lakes by direct water connection to navigable waters of the State. Although the mangrove areas to be filled by the project are landward of the mean high water line, those mangroves are inundated by water at times and considered to be "submerged lands" adjacent to the State water bodies, Buttonwood Sound and Florida Bay. If the mangroves are removed, part of the ecosystem's ability to filter sediments and nutrients contained in stormwater runoff of adjacent upland areas and from tidal flows will be destroyed and will affect water quality considerations for adjacent open bay estuarine or marine systems. The extensive root system of the mangroves and associated vegetation assist in stabilization of estuarine shoreline sediments and attenuation of storm generated tides. Even though some of the mangroves in the proposed area for fill are in a stressed condition, i.e., a condition in which their growth is stunted, if left alone, those mangroves would flourish and provide the same water quality functions as healthy mangroves. A biologist presented by the Petitioner identified the number of mangrove species, the number of mangroves, the diameter of those mangroves and the height of canopies of the mangroves in areas of the project site. These items were summarized through the use of the Holdridge Complexity Index, which measures structural complexity of mangroves within the sites. See Petitioner's Exhibit No. 17, admitted into evidence. In particular, four such station pairs were studied and the pairs were constituted of a station within the basin of the mangrove stand and a station at the fringe of the mangroves. There was a site at each proposed waterway and a site at the northeastern and western points of the peninsula, the area of the proposed mangrove preserve. See Petitioner's Exhibit No. 6, admitted into evidence. This study indicated that fringe mangroves are more developed than the ones in the heart of the basins. This study also revealed that the upland fill would remove primarily black mangroves. The removal of the mangroves and placement of fill would be in furtherance of the creation of twelve to fourteen residential lots, the majority of which would be located on Florida Bay. See Petitioner's Exhibit No. 6. In furtherance of the intention to offer these lots for sale, the Petitioner has sold one of the lots on Florida Bay for $95,000 on or about June 2, 1981. If the proposed utilization of the property in question was not allowed, the Petitioner stands to lose money in his investment in the face of preliminary developmental expenses which, at present, exceed monetary returns from the sale of lots. The area in which the upland fill would be placed is porous limerock, which allows water to seep through and be transported underground to adjoining water bodies, both on site and off site, in addition to the runoff from the upland areas. To address these concerns, the Petitioner has planned for the installation of dikes in the various upland areas which are to be built to prohibit drainage into the remaining mangrove areas and ambient waters. The littoral zones around the edge of the inland lakes would promote marine and wetland vegetation which assists in the function of filtration of sediments and nutrients. On the subject of water quality considerations, the use of the clean limerock fill, which is calcium carbonate, would tend to stabilize seawater at its natural PH level, thereby allowing the specific conductance (measurement of salinity) of the lakes and surrounding ambient waters to remain in a natural state in terms of direct effects of the fill material. On the subject of contamination of water by copper, normally, seawater contains 3 micrograms per liter of copper. In a project such as this one, it is not expected that higher amounts of copper would be found, and the limerock contains only trace amounts of copper, if any. Specific testing done at the project site reveals less than 1 microgram per liter of copper in the North Lake and 4 micrograms per liter in the South Lake. Therefore, the activity is not expected to increase the levels of copper to the extent that measurements exceed 500 micrograms per liter in either the lakes or surrounding waters. In dealing with the substance of zinc, seawater contains as much as 30 micrograms per liter of zinc. Sampling by the Petitioner indicated 2 micrograms per liter in the North Lake and 8 micrograms per liter in the South Lake of that substance. The activity and the development is not expected to increase the levels of zinc to the extent that measurements exceed 1,000 micrograms per liter in either the lakes or surrounding waters. In sampling for lead content, the samples revealed less than 50 micrograms per liter of lead and the placement of limerock fill will not cause the amounts of lead in the lakes and surrounding waters to exceed 50 micrograms per liter. Testing for phenolic compounds at the site revealed that these materials were below established standards of the Respondent, and it is not expected that those standards will be exceeded through activities proposed in this permit process. The testing for oils and greases indicated less than 1 milligram per liter of oils and greases, which is below the State's standard of 15 milligrams per liter, and the activities proposed at the project site are not anticipated to exceed 15 milligrams per liter of oils and greases. Normal PH for coastal waters is 6 to 8.5, and the PH levels of the lakes and ambient waters in the area were in the range of 8, except for measurements done in the winter at the North Lake, where they were shown to be 7.5. The placement of limerock fill will not cause an imbalance in the pH readings. The activity as proposed will not add substances which are created by industrial or agricultural means or cause other discharges, colors or odors, or otherwise promote a nuisance condition in the ambient waters or the lakes. Measurement was made to toxic materials in the way of synthetics, organics or heavy metals. Those tests in the lakes and ambient waters showed heavy metals to be at low levels. There were no sources revealed of synthetics or organics. (The calcium carbonate found in the limerock fill would assist in breaking down lawn pesticides into phosphate.) In summary, the filling, as proposed, is not expected to promote the introduction of toxic substances into the lakes or surrounding waters. The placement of the clean limerock fill in the upland area is not expected to cause problems with turbidity in the lakes or ambient waters, which turbidity would exceed 50 Jackson Units above background. The filling will not affect dissolved, oxygen levels of the surrounding waters. Biochemical oxygen demand, the measurement of demand for oxygen of organic and chemical materials in the water, will not be influenced by the placement of the clean limerock fill related to surrounding waters. The limerock fill is not expected to introduce other oxygen demanding materials into the subject waters, such that dissolved oxygen levels would be lowered by BOD loading. There will be no problem with dissolved solids, in this instance, salts, due to the fact that calcium carbonate fill would not affect the dissolved solids in the ambient waters or in the lakes. Coastal water PH normally measures 6 to 8.5 and PH for open waters in the range of 1. Placement of calcium carbonate fill on the uplands would not cause the PH in the Class II waters in Everglades National Park, which is 300 feet east of Baker Cut Point, to vary above or below normal levels for either coastal or open waters. In addition, there would be no discharge of toxic substances from the calcium carbonate fill into the Class II waters herein described. Tests conducted in the vicinity of homesites utilizing septic tanks, and specifically as sampled in waters adjacent to Buccaneer Point and the subject lakes in a development known as Private Park and Buttonwood Sound , indicated less than one fecal coliform bacterium per 100 milliliters. See Petitioner's Exhibit No. 14, admitted into evidence. Anticipated setbacks for additional septic tanks to be associated with the buildup at the project site would be in keeping with the requirements of Monroe County, Florida, and harmful septic tank leachate is not expected to be a problem.
The Issue Respondent Jacksonville Shipyards, Inc. (JSI) filed a permit application with the State of Florida, Department of Environmental Regulation, (DER), for permission to conduct maintenance dredging in a basin associated with its shipyard operation. This permit application was made in accordance with Chapter 403, Florida Statutes, and Chapter 17, Florida Administrative Code. In the face of DER's statement of intent to grant this permit, George H. Hodges, Jr., (Petitioner), has petitioned in protest. Therefore, the issues to be considered in this dispute concern the entitlement of JSI to the grant of an environmental permit for maintenance dredging of its shipyard basin.
Findings Of Fact DER is an agency of the State of Florida charged with the environmental protection of waters within Florida. Its authority includes regulatory powers announced in Chapter 403, Florida Statutes, and Chapter 17, Florida Administrative Code. Certain activities involving state waters require permission from DER before they be lawfully undertaken. Among those activities are dredge projects such as contemplated by JSI in its pending request to be allowed to maintenance dredge as much as 66,000 cubic yards of material per year from its shipyard basin located in Jacksonville, Duval County, Florida. This is an undertaking which is envisioned by Chapter 403, Florida Statutes, related to the permit responsibility of DER. It is specifically addressed by Rule 17-4.28, Florida Administrative Code, in which is found the statement of permit requirements for dredge and fill activities. JSI, the applicant, operates a facility known as Bellinger Shipyard, which is engaged in the repair and maintenance of commercial and naval vessels. This enterprise includes the drydocking of vessels upon which repairs are effected, through the use of several drydock chambers in shipyard basin. In the course of the maintenance, a technique known as "gritblasting" is employed. The purpose of this "gritblasting" is to clean the ships in anticipation of repainting. On occasion the "gritblasting" would remove all coats of paint down to the metal finish of the ship. The paints being removed contain antifouling and anticorrosive materials. Those materials have, among other properties, the ability to repel marine organisms, causing their mortality. The "gritblasting" process utilizes a material known as "black beauty." This is a waste product from firing power plant boilers and it contains iron, silica, aluminum, titanium, magnesium, lime, penta oxide (P2O5), sodium oxide, sulfur trioxide and potassium oxide. The "black beauty" is applied through the use of a pressurized system which forces the material onto the treated surface under pressure of 70 to 85 pounds per square inch. After the preparation is made, vessels under repair are repainted, and similar paint with antifouling and anticorrosive properties is reapplied. During the "gritblasting" process, dust is generated and a portion of that material finds its way into the water within the basin. Other particles being removed drop to the deck surface of the drydock. When paint is reapplied to the surface of a vessel undergoing repair, it is given the opportunity to dry and the vessel is then refloated and removed from the drydock. To do this, the drydock itself is submerged. When the vessel has exited the drydock facility, the drydock resurfaces and is allowed to dry out. The material which has been removed from the surface of the repaired vessel is then shoveled into containers and transported to an offsite sanitary landfill for disposal. This material removed includes the "gritblasting" compound and paint which has been stripped from the surface of the vessel. When the drydock is submerged following vessel servicing, the inference can be drawn that a certain amount of the materials on the drydock deck surface will be introduced into the water within the basic before the drydock is resurfaced. The arrangement for refloating the vessel is the reverse of the technique employed in lifting the vessel out of the water for maintenance. When the vessel is brought in for service, it is guided into a submerged drydock. Water is then pumped out of the hollow drydock walls and deck to raise the vessel out of the water, allowing access to the vessel, which is completely above the water surface, as is the drydock work deck. The basin in which the business activities of JSI take place is located on the western shore of the Intercoastal Waterway. The Waterway and basin are part of an estuarine system, as these water bodies are tidally influenced. The basin and the Intercoastal Waterway constitute Class III waters of Florida. The configuration of the basin is as found in JSI Exhibit 16, an aerial photograph of the site. Moving from east to west within the basin, it is approximately one thousand feet from the Intercoastal Waterway to the back of the basin in its western-most extremity. In the back area of the basin the north- south axis is 250 feet. The interface between the basin and the Intercoastal Waterway on the eastern reach north-south axis is approximately 625 feet. There are no obstructions to the confluence of the Intercoastal Waterway and the eastern side of the repair basin. The southern-most reach of the basin is approximately 350 feet in length running east to west. On the eastern side of the basin there is a pier area which is roughly 360 feet north-south by 60 feet east-west. As described before, the pier is not a solid structure extending to the bottom of the water. Thus, water can be exchanged between the basin and the Intercoastal Waterway beneath the pier. JSI had acquired the Bellinger Shipyard in 1974. At that time environmental permits had been issued allowing for the maintenance dredging of the basin. These permits were valid through 1975. In 1975, JSI obtained a dredge and fill permit from the Florida Board of Trustees of the Internal Improvement Trust Fund, as well as a dredge and fill permit from the United States Corps of Engineers. These permits were for a ten-year period. They allowed maintenance dredging in the amount of 66,000 cubic yards per annum and for the disposal of the dredged material in an EPA-approved offshore site. In 1980 DER confirmed the dredge and fill permit that had been obtained from the Florida Board of Trustees. This permit by DER required JSI to conduct monitoring of turbidity during dredging, but did not require employment of turbidity screens. In 1979 the Army Corps had required JSI to conduct bioassay analysis in furtherance of the federal dredge and fill permit. In the face of the results obtained in that bioassay analysis, the Army Corps continued the dredge and fill permit to JSI dating from August 14, 1980. A subsequent extension of the federal permit was given through August 14, 1986. Contemporaneous with the present permit application before DER, JSI has requested further permission from the Army Corps related to the ability to excavate as much as 66,000 cubic yards of material on an annual basis. JSI has not been cited by any regulatory agency related to water quality violations associated with its dredging activity. The present DER permit application is for renewal of the 1980 Permit No. 16-21380 and is being processed under the DER File No. 161071139. This application for permit renewal was submitted on July 16, 1985. The application requests permission to maintenance dredge for a period of ten years. If granted, it is the intention of the applicant to use a closed clam shell bucket to excavate the material in the basin. This choice is in furtherance of the suggestion of DER and is a departure from the applicant's initial intention to use an open bucket to excavate. JSI also intends to employ turbidity curtains during the dredge activities. The applicant intends to transport the dredged material to the aforementioned EPA disposal site which is at sea. In doing so, a hopper barge is propelled by a towing vessel. Both the barge and towing vessel are inspected and certified by the United States Coast Guard. The crews involved in the transport of the material are qualified and licensed. In the past, transport of the material has been done under fair weather and smooth sea conditions, and it is intended that the transportation be done in that same setting if the permit is granted. The barge would not be loaded fully, thereby minimizing spillage. This was the arrangement in the past. The United States Coast Guard will be apprised of the departure time of the voyage in transport of the material, certain activities within that transport and upon return. The hopper barge has a bottom dump which is closed during transport and is opened at the bottom in disposing the dredge material. After satisfying DER about its proposal, JSI was informed that DER intended to grant the dredge permit requested. When Petitioner, George H. Hodges, Jr., the owner of real property adjacent to the site of the project, learned of the stated intention to grant the maintenance dredging permit, he offered a timely petition in opposition to the proposed agency action. This property of Petitioner is in Jacksonville, Duval County, Florida. It is located north of the JSI property at issue. Petitioner's real property is connected to the Intercoastal Waterway. Petitioner has filed this action in opposition to the grant of the permit upon the expressed belief that the dredging activity will cause pollution at his property. In particular, it is JSI's intention at various times in the calendar year to do maintenance dredging in the entire basin. In addition to using a closed clam shell bucket, a system of turbidity barriers or curtains will be employed in segmented dredge areas. Those several locations within the basin which are cordoned off with the turbidity curtains are as depicted in JSI's Exhibit 9 admitted into evidence. The design maintenance depths for the dredging project are set forth in JSI's Exhibit 4 admitted into evidence. They vary from -17 to -37.5 feet, with the greatest depth being contemplated under drydock number 1 in the northwestern corner of the basin. Near the Intercoastal Waterways the depth sought is -17 feet, transitioning to -21.5 feet moving toward the back of the basin at the western extreme and outside of the area dredged beneath drydock number 1. The depths sought under drydock numbers 2 and 3 are -26.5 feet and -20 feet respectively. These desired elevations correspond to conditions at mean low water. The tidal range in the Intercoastal Waterway adjacent to the basin, which would promote an influence in the basin proper, is in the neighborhood of 4-foot intervals, with two tidal cycles a day. This would mean, as example, that at the high tide range, the shallowest design depths for dredging of -17 feet become -21 feet in the transition from mean low water to mean high water. Those 4-foot variations would pertain to the other design depths contemplated in the dredging as described in the preceding paragraph as well. The turbidity barriers contemplated for use will extend from the surface through the water column to depths near the bottom. See JSI Exhibits 4 and 9. It is desirable, according to Dr. Gregory Powell, witness for JSI, a reliable expert in describing the effectiveness and use of turbidity curtains, to have those curtains extend to an area just above the bottom. Dr. Powell's education includes a Masters Degree in coastal and oceanographic engineering and a Ph.D. Degree in engineering mechanics, with emphasis on coastal and oceanographic engineering. In consideration of his remarks, under the influence of high tide there could be as much as a 4 foot gap between the curtain and the bottom. Powell and other experts who offered testimony agreed that turbidity screens can have effectiveness in areas of low current velocity, assuming the proper installation, maintenance and extension to a location near the bottom of the water body. If mismanaged, turbidity screens are not effective in controlling turbidity. Moreover, they are less effective in areas where significant current velocities are experienced. This would include the circumstance in which a foot and a half or more per second of flow was being experienced, according to Dr. Powell, whose opinion is accepted on this point. He also indicated that the quiescent areas in the basin, toward the back of the basin or western dimension of the basin, would show a flow regime in a rate of one centimeter per second. This expression is credited. Although, as described by Dr. Powell, the currents in the Intercoastal Waterway are moving at a rate approximating nine feet per second on ebb time at the bridge located on the Intercoastal Waterway to the south of the project site, these current velocities are not expected in the area where the dredging is occurring. Dr. Powell is correct in this assessment. As he describes, and in acceptance of that testimony, eddies from the current from the Intercoastal Waterway at peak flood tide could come into the basin and temporarily show velocities of one foot per second; however, these velocities are within the acceptable range of performance of the turbidity barrier. Dr. Powell's conclusion that wind would have no significant effect on the current velocity, given the depth of this basin, is also accepted. The remaining flow regime in the basin is not found to be a detriment to the function of the turbidity barriers. The use of turbidity curtains in this project is not found to be a "placebo" to placate DER as suggested by Erik J. Olson, engineering expert who testified in behalf of the Petitioner The monitoring that is intended in the course of the dredging activities would call for examination of background turbidity levels at three sites in the Intercoastal Waterway prior to commencing of dredging and twice daily at each of these sites during dredging. Should a violation of state water quality standards for turbidity be detected, dredging will cease until the problem with turbidity can be rectified. To provide ongoing assurances of compliance with water quality standards, JSI will analyze the sediment in the basin for the parameters of cadmium, copper, aluminum, lead, mercury, oil and grease every two years. Dr. Powell, expert in engineering and recognized as an expert in the matter of transport of the resuspended sediment associated with the dredging, as well as David Bickner, the project review specialist for DER, believe that the use of the closed clam shell bucket technique and employment of siltation screens or barriers, together with turbidity monitoring, will effectively protect against turbidity violations in the Intercoastal Waterway adjacent to the basin. This opinion is accepted. Bickner brings to his employment a Bachelor of Science degree in biology and a Master of Science degree in ecology. Bickner identified the principal concern of DER related to this project as the possibility of release of resuspended sediments into the Intercoastal Waterway. With the advent of the techniques described in the previous paragraph, only minimal changes in background conditions related to turbidity are expected. Although there would be turbidity violations within the confines of the areas where the dredging occurs, the principal influence of that turbidity will be confined in those regions. This speaks to dredge areas I, 2 and 3. According to Bickner, whose opinion is accepted, the turbidity changes within the dredge areas in relationship to background conditions do not require a mixing zone permit, nor do they constitute a basis for denial of the permit. As alluded to before, and as described by Dr. Powell, the basic nature of the basin in question is one of quiescent conditions with low current velocity. He points out that the layout of the basin is such that it is a sediment trap allowing the deposit of silt, in particular in the deeper sections of the basin near the western side. The greatest influence by resuspension of sediment in the dredging activities can be expected in the back portions of the basin and it is in this area that the silt barrier can be expected to be most efficient, based upon Powell's remarks. Dr. Powell indicated that there is the expectation of increased efficiency in turbidity control when a closed clam shell bucket is used, as opposed to the open style of clam shell bucket. Those efficiencies range from 30 to 70 per cent. There is some risk of increased turbidity near the bottom of the water column in the use of a closed clam shell bucket, and for that reason the applicant should monitor the activities of the operator of the excavation machinery to guard against inordinate disturbance of the area being excavated. On balance, the closed clam shell bucket is a superior technique to the open style of clam shell bucket excavation when those alternatives are compared. As Dr. Powell explained, the segmentation of the dredge area allows the resuspended sediment to be confined in more discrete circumstances and to be controlled. The location of the silt barriers behind the pier structure guard against the effects of eddying. The silt barriers can be properly anchored and will not be unduly influenced by current velocity. Dr. Powell believes that the use of silt barriers, taking into account a low velocity of current in the basin, and the proper deployment of the siltation screen could bring about a reduction of the resuspended solids by 80 to 90 per cent on the outside of the barrier. To calculate the influence or the environmental significance of that remaining 10 to 20 per cent of resuspended solids at the Intercoastal Waterway, Dr. Powell testified that the suspended load behind the silt curtain resulting from the dredging is expected to average from 100 milligrams per liter to a peak amount of 500 milligrams per liter. He believes that, depending on which methods of calculation is used, the dilution factor in the Intercoastal Waterway ranges from 330:1 to 600:1. In using an environmentally conservative assessment, that is 80 per cent effectiveness of the silt curtain with a 330:1 ratio, Powell calculated that the release of resuspended materials into the Intercoastal Waterway would be approximately .3 to 1.5 milligrams per liter. This translates to less than 1 NTU against background conditions. This result would not exceed the 29 NTU limit against background that is described as the standard for turbidity control. Dr. Powell's opinion of turbidity results based upon the dredge activity is accepted. There is exchange of water between the basin and the Intercoastal Waterway and to accommodate this influence, the turbidity curtains would be placed in such a fashion that they would not compete with the ebb and flow of the tide. Dr. Powell's assessment of the circumstance in describing the effectiveness of turbidity barriers takes into account the tidal conditions and the inappropriateness of trying to have the silt curtains prohibit the flow conditions during these tidal changes. In order to promote maximum effectiveness of the turbidity barriers during the entire course of excavation of materials, the length of, the silt screen must be adjusted as desired elevations are approached. Erik J. Olson is an expert in civil engineering with an emphasis on hydraulics and the holder of a Masters Degree in coastal and oceanographic engineering. As alluded to before, he questions the validity of the use of siltation barriers as an effective protection against the implications of turbidity. He properly points out that the curtains will not extend to the region of the interface of the basin and the water column at all times. He describes the exchange of water between the basin and the Intercoastal Waterway, to include the unrestricted sediment transport beneath the turbidity curtain. He believes that wind can cause changes in current velocity as great as .2 foot per second, activities within the basin an additional .3 foot per second, and eddying .3 foot per second. All of these taken together do not exceed the range of effective response of the turbidity barriers. On balance, Olson's criticism of the benefit of turbidity curtains is unconvincing. Arlynn Quinton White, Jr., who holds a Bachelor of Science Degree, a Master of Science Degree in biology and a Ph.D. in matters related to marine biology, offered his testimony in support of Petitioner. He believes that as much as 2 to 3 per cent of the resuspended sediment related to the dredging activities would reach the Intercoastal Waterway under the best of conditions. It is difficult to translate that testimony into a measurement of changes in turbidity levels against ambient conditions in the Intercoastal Waterway. In any event, as already indicated, the changes in turbidity levels are not expected to exceed 29 NTU against background. It is evident that the turbidity curtains are necessary and their proper use must be assured to protect against problems associated with turbidity and the implications of the constituents of the resuspended particulate matter related to possible toxicity. Therefore, the close monitoring suggested in the statement of intent to grant the dredge permit is viable. Another matter associated with the implications of turbidity pertains to the fact that when the dredge material has been resuspended, as much as two days could pass before the basin returns to background conditions, given the high content of silt with its attached metals. This becomes significant given the uncertainty of the location of the dredge equipment during the course of excavation, i.e., inside the barrier or outside the barrier. Final choice about the placement of the dredge equipment will have to be made at the time of the excavation. Should the dredge equipment be inside of the cordoned area while excavation is occurring, it would be necessary to allow turbidity conditions to achieve background levels before opening up the barrier for the exit of the hopper barge which contains the excavated material. Otherwise, the estimates as to the influence of the dredging activities in the Intercoastal Waterway are unduly optimistic. Likewise, if the excavation platform is placed outside of the work site, that is to say, on the outside of the siltation curtain, extreme caution must be used to avoid spillage of the excavated material when being loaded onto the hopper barge. The occasions in which the excavation is being made from this side of the barrier should be minimized. These safeguards are important because any changes in sediment loading within the Intercoastal Waterway promote an influence in the area immediately adjacent to the basin and other sites within the Intercoastal Waterway as well. The subject of the use of a hydraulic dredge as an alternative to excavation by use of a closed clam shell bucket was examined in remarks by the witnesses appearing at hearing. Olson believes that there are hydraulic dredges which can achieve the design depth contemplated by the project and which equipment could fit inside the basin area. This is contrary to the opinion of witnesses for the applicant and DER who do not believe that the hydraulic dredging equipment which would be necessary to achieve the design depths would fit into the basin area. On balance, the record does not establish that such equipment with the appropriate capability and size does exist. More importantly, the proposed method of excavation is environmentally acceptable when examined in the context of the permit sought in this case. Finally, it was not essential for the applicant to make a detailed investigation of availability of hydraulic dredging equipment and it is not determined that failure to make this investigation warrants the denial of the requested permit. Although an hydraulic dredge is more desirable from the standpoint that it causes less turbidity through resuspension of sediments, it is not the only plausible method of excavation in this instance. Raymond D. Schulze testified in behalf of JSI. He holds a Bachelor of Science Degree and a Master of Science Degree in environmental engineering sciences. In particular, he established the fact that the amount of resuspended solids that would be introduced into the Intercoastal Waterway associated with the dredging activity would not result in the smothering of organisms or to clogging of gills of fish. In addition to the possible problems with turbidity, there is the additional issue of violation of water quality standards in the several parameters associated with concentrations of metals in the water column within the basin and in the sediments or related parameters such as dissolved oxygen and biological integrity. Having considered the testimony, the facts do not point to water quality violations for any parameters occurring in the Intercoastal Waterway as a result of the dredging. To arrive at this factual impression, the testimony of Dr. Pollman and Schulze is relied upon. Water quality sampling done by JSI in locations within the basin and in the Intercoastal Waterway, that by Dr. Pollman and Schulze, supports their impression of the acceptability of the dredge activities. This water quality data was admitted as JSI's Exhibit 18. Additionally, the field conditions existing at the time of testing, to include water temperature, weather conditions, tidal cycle, ph and dissolved oxygen were also made known. This water quality data and other information examined by these witnesses points to the fact that no increases in concentrations of metals are occurring within the Intercoastal Waterway as a result of the business activities of the applicant, nor are they to be expected while dredging operations are under way. Dr. Pollman correctly identifies the fact that there will not be significant degradation of water quality, above DER's minimum standards, related to the Intercoastal Waterway based upon the dredging activities within the basin, dealing with the water quality parameters of mercury, zinc, cadmium, chromium, lead, aluminum, iron and copper, substances which are within the basin. Dr. Pollman also examined sediment data collected by DER, and that data tended to confirm his assessment of the influences of the dredging activity related to these parameters. Dr. Pollman does not believe that metal concentrations contained in the sediment of the basin are leaching into the water column in quantities sufficient to cause violation of water quality standards. His opinion is accepted. Pollman had collected water quality samples in the two locations where the greatest siltation rate was expected and as a consequence the greatest concentration of metals would be expected. The water quality samples were taken at several depths to reach an opinion as to the matter of leaching of metals into the water column and the possibility of those metals dissolving in the water column. If leaching had been occurring, a concentration of metals expressed as a gradient would be expected. The greatest concentration in this instance would be near the sediment interface with the water column. No such gradation was detected and the idea of leaching was ruled out. Bickner's testimony established that testing for the exact amount of iron present at the dredge site was not required, given the nature of the iron source being introduced into the water within the basin. Bickner did not find that type of iron to be toxic. As stated before, Pollman agrees that no violation of state water quality standards as a result of the presence of iron associated with the maintenance dredging should be expected. There is some data which shows water quality violation for mercury in the basin and the Intercoastal Waterway. Subsequent water samples collected by Schulze in the westerly portion of the basis did not show detectable levels of mercury. Moreover, data taken by Pollman and Schulze and compared with the DER sediment data shows that the concentration levels of mercury are greater in the Intercoastal Waterway than in the basin, thereby suggesting that there is no concentration gradient for mercury which would lead to the belief that the basin contributes to the amount of mercury found in the Intercoastal Waterway, nor is the mercury believed to be leaching into the water column in the basin. The explanation of the differences in measurements of the amount of mercury in the basin, depending upon the point in time at which analysis was made, may be attributable to a natural phenomenon, given numerous sources of mercury within the environment. Whatever the explanation of these changes, Dr. Pollman does not believe that the release of mercury associated with the resuspended sediments that may find their way into the Intercoastal Waterway would show a violation of the state water quality standard for mercury in that water body and his opinion is credited. Data collected by Pollman and Schulze did not show water quality violations for aluminum and the DER test data described before indicated aluminum levels lower in the basin than in the Intercoastal Waterway. Some data collected by Technical Services, Inc., an environmental consulting firm in Jacksonville, Florida, which was reviewed by Pollman, Schulze, and Bickner showed a substantial violation of the water quality standard related to aluminum in sediment sampling that was done. The origin of that amount of aluminum found on that occasion was not clear. It is possible, as described by Bickner, Pollman and Schulze, that the level detected In the Technical Service report could have occurred based upon natural phenomena such as storm water runoff from uplands. Bickner also questioned the findings of Technical Service and felt like the determination might be influenced by some intervening circumstance which would promote the need for re-analyzing that parameter. Whatever the explanation of the findings in the Technical Service report, it does not point to any water quality violation of the standard related to aluminum based upon the dredging activities, given the limited amount of total suspended solids that would be introduced into the Intercoastal Waterway. Schulze, in his assessment of the implications of metal concentrations in the sediment transported to the Intercoastal Waterway, did not find them to cause concern about toxicity to marine life in the Intercoastal Waterway. This point of view is accepted. In trying to understand the implications of metal concentrations, Schulze believed that the biologically available fractions of those metals in the sediment is not very high, and when the dilution of the sediments which occurs in these circumstances is examined, no toxicity is expected. Moreover, as Dr. Pollman described related to the parameter aluminum, it is not a toxic material at the ph levels found in the basin, and the resuspension during dredging will not cause it to gain toxicity. This opinion of Dr. Pollman is supported by Bickner and Schulze. The opinion of Dr. White that the amount of aluminum, copper and zinc within the sediment found in the basin would eventuate in the violation of water quality standards for those parameters when introduced into the Intercoastal Waterway is rejected. The information available to Pollman, Schulze and Bickner which describes their opinion about water quality standards was sufficient to reach an opinion, the position of Petitioner's witness Sanford Young, holder of a Bachelor of Science Degree in civil engineering and a Master of Science Degree in zoology notwithstanding. As Bickner indicated in his testimony, it is essential that an applicant give reasonable assurances of compliance with all parameters listed in Chapter 17-3, Florida Administrative Code, dealing with water quality. However, this does not mean that testing must be done for each parameter set forth in that chapter. Reasonable assurance has been given that water quality parameters as identified in that chapter will not be violated. Bickner indicates the biological integrity standard is not one of concern in that given the nature of business operations within the basin, there is no expectation of a stable benthic community which might be disturbed by dredging. From the remarks of Schulze, there is no prospect of danger to benthic communities within the Intercoastal Waterway. These impressions by Bickner and Schulze are accepted. Under the facts of the case, the failure of the DER permit appraisers to discover benthic organisms in the sample grabbed at the site is not unexpected. There is also some question about whether that sample is representative of the circumstance at the site, given the limited sampling. On the topic of normalization of the DER data which was described in the course of the hearing and is identified by Dr. Pollman, the value of that information is seen as establishing the relative quantities of certain metals within the basin as compared with other sites throughout the Intercoastal Waterway. Twenty-one different locations were involved in this analysis. Concentration ratios using aluminum to normalize the data are as reflected in JSI's Exhibit 17 admitted into evidence. The significance of this information as it grossly describes whether the basin routinely contributes to increases in the amounts of these metals within the Intercoastal Waterway. Overall, basin activities are not shown to have promoted such an outcome. This normalization comparison does not address the issue of site specific water quality violations; however, no such violations are expected associated with the dredging activities within the basin as it relates to violations in the adjacent Intercoastal Waterway. Schulze had made sampling related to dissolved oxygen within the basin and the Intercoastal Waterway. As Schulze describes, the levels of dissolved oxygen seem to be at their lowest point just prior to the dawn hours. Sampling which he did was done at 5:00 a.m. in order to obtain the lowest dissolved oxygen readings. Three sites were sampled within the basin and an additional site was sampled in the Intercoastal Waterway. Readings were taken at varying depths at each site to gain an impression of the overall water column. The mean reading for the circumstance was in excess of the required range for state water quality, that is 4.0 per million. Having considered the evidence, no problems with dissolved oxygen are expected in that deficit contribution is in the range of .1 milligram per liter, per Pollman. In addition, Dr. Powell, through modeling, examined the implications of long-term dredging activities on the topic of dissolved oxygen. He employed field data gathered by Schulze in this assessment. This modeling established that decreases in dissolved oxygen levels would range from .1 to .15 milligrams per liter. Given the average of 4.5 parts per million oxygen in the basin at present, the incremental decreases in dissolved oxygen levels related to the dredging would not pose a problems with state water quality standards for dissolved oxygen other than short-term effects in the immediate vicinity of the dredge area, which is an acceptable deviation. As the Petitioner urges in its fact proposal, a 1983 report of Technical Services, Inc., JSI Exhibit 4, and a 1985 report of that firm, JSI Exhibit 7, were made available as part of the application. Officials within Technical Services, Inc. did not appear at the hearing and offer testimony related to the specific findings found in those reports. This information was used by the experts who did testify on behalf of the applicant, in particular Dr. Pollman, as data to question, his assumptions made about the implications of the project in terms of water quality concerns. Pollman also utilized DER data taken from a source known as Storette, and this pertains to the 21 sampling stations involved in the preparation of JSI Exhibit 17, the graphing document related to concentrations of various metals. Again, this was in furtherance of the basic underlying opinion which Pollman had about the project. The Storette data as such was not offered into evidence. Witnesses for the Petitioner, namely Olson and White, were aware of the two reports of Technical Services, Inc. and the use of the DER Storette data and offered their criticism of the project taking into account this information. Petitioner points out that there is no indication as to how far below the sediment/water interface the Technical Services, Inc., and DER sediment samples related to reports of the consultant and the Storette information of DER were extracted. Therefore, it only reflected one portion of the sediment at a depth of extraction. A more complete understanding of the sediment characteristics would have been shown through a core sample, especially in the area to be dredged, but that understanding was not essential. The suggestion by the Petitioner that it was inappropriate to normalize data for purposes of describing the relative concentrations of the metals parameters is not accepted. The preparation of JSI's Exhibit 17 does not point to abnormally high amounts of aluminum, such that the use of aluminum as a known commodity in carrying out the normalization would be contraindicated. As identified by the petitioner in its proposal, sediment sizes within the strata found in the basin depicts higher percentage of silt and clay-size sediments in the back end of the basin with lesser amounts of the silt- and clay-size sediments in the southern reach of the basin and at the intersection of the basin with the Intercoastal Waterway. The smaller the particles, such as silt and clay, will remain suspended for a longer period of time and have a tendency to promote bonding with heavy metal. Nonetheless, this information does not change the impression that the turbidity barriers will be effective. The 1983 Technical Services, Inc., information related to the settling of resuspended sediment and similar information imparted in the 1985 report by that organization tend to confirm that approximately two days should be necessary to allow the area of excavation to return to background conditions related to turbidity. This is in corroboration of remarks by Dr. Powell. These time projections are not found to be inadequate when taking into account other factors such as tidal changes, boat traffic, other activities within the basin, wind and weather events. As White described, the antifouling properties of the paint involved in the business activity of the applicant can be expected to adversely impact any larval forms of marine organisms when introduced into the basin. Nonetheless, this toxicity is not expected to pose a danger to marine organisms in the Intercoastal Waterway given the percentage of resuspended sediment that will escape capture by the sediment barriers and the dilution factor before introduction of those resuspended sediments into the Intercoastal Waterway. Petitioner questions the acceptability of evidence of the findings set forth by E G & G Bionomics, a firm which performed an examination to determine existing diversity of benthic macroinvertebrates. Those results are reported in Petitioner's Exhibit 13, a 1980 report. They were not accepted as evidence of the specific findings within that report in that they were not the subject of discussion by persons who authored that report. The use was limited to corroboration of the opinion by Dr. Pollman and Schulze as to water quality considerations and they were not Crucial to their opinions. Moreover, it was not necessary for the applicant to perform a more recent bioassay in order to give reasonable assurance to DER concerning water quality matters or to establish the implications of the influence of contaminants within the sediment found in the basin related to benthic macroinvertebrates. The biological integrity of the basin area was at risk prior to the proposal for maintenance dredging. The relevant inquiry is the influence of the dredging activities on the biological integrity in the Intercoastal Waterway and those activities do not place organisms within the Intercoastal Waterway in peril. Any synergistic aspects of metals which act as toxins, for example, the increase in the aggregate value of the toxicity of zinc and cadmium, compared to their individual implications as toxins, will not present problems with water quality in the Intercoastal Waterway. Petitioner takes issue with the proposed disposition of the dredge material at an ocean site. While an appropriate upland disposal site would be preferred, it is not mandated. The approved EPA disposal site within federal jurisdiction is acceptable. Petitioner in its fact proposals found at paragraphs 36-39 (incorporated by this reference) points out violations of water quality standards for cadmium, mercury, and aluminum, and other possible violations of the standard for mercury. This information does not cause a change of opinion about the acceptability of the project in terms of reasonable assurances. There is no indication that oils and greases will present a problem related to water quality standards. The project is not contrary to public interest in that: (a) the project will not adversely affect the public health, safety, welfare or the property of others; (b) the project will not adversely affect the conservation of fish and wildlife, including endangered or threatened species, or their habitat; (c) the project will not adversely affect navigation or the flow of water or cause harmful erosion of shoaling; (d) the project will not adversely affect the fishing or recreational values or marine productivity in the vicinity of the project; (e) the project will be of a temporary nature; (f) the project will not adversely affect significant historical and archaeological resources under the provisions of s. 267.061; (g) the project is in no other way contrary to the public interest. The purpose of this fact finding does not include the issue of whether there are ongoing violations of state water quality standards associated with the business activity of the applicant, that not being the subject of the hearing. In any event, the testimony of Dr. Pollman established that the operations of JSI are not causing water quality problems associated with the parameters of cadmium, copper, aluminum, mercury, lead, chromium, tin, zinc or iron related to the Intercoastal Waterway. The influences of the business activities associated with those parameters within the basin are not understood when the evidence presented is examined but are not found to be essential to the resolution of this dispute.
Recommendation Having considered the facts, and the conclusions of law, it is, RECOMMENDED: That DER issue a final order which grants the requested maintenance dredging permit in keeping with the safeguards described in the fact finding of this recommended order. DONE AND ORDERED this 16th day of October 1986 at Tallahassee, Florida. CHARLES C. ADAMS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 16th day of October 1986. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 86-0365 Having examined the proposed facts submitted by the parties, those proposals have been found as fact with the exception of the following which are distinguished: Petitioner's facts Paragraph 1: Subordinate to fact finding. Paragraph 2: The first sentence in this paragraph is rejected because the fact is not found within the indicated exhibits, nor can that fact be fairly inferred. Paragraphs 9, 10, 11, 14, and 15: Except for the last sentence in that latter paragraph are subordinate to facts found. Paragraph 15: The last sentence: Contrary to facts found. Paragraph 18: The last sentence: Subordinate to fact finding. Paragraphs 21, 22, 23, 24, 25 and 26: Subordinate to fact finding. Paragraph 27: Contrary to facts found. Paragraphs 28, 29, 30 and 31: Subordinate to fact finding. Paragraph 32: Not necessary to dispute resolution. Paragraphs 33 and 34: Subordinate to fact finding. Paragraph 35: Contrary to facts found. Paragraphs 40, 41 and 42: Subordinate to fact finding. Paragraphs 44, 45: Not necessary to dispute resolution. Paragraph 47: The first two sentences are information that is not sufficiently credible to allow application to the issues of the present case. Paragraphs 48, 49, 50 and 51: Not necessary to dispute resolution. Paragraph 52: Reject as fact. Paragraph 54: Contrary to facts found. Paragraph 55: Not necessary to dispute resolution. JSI and DER facts Paragraph 2: Pertaining to sentence 8 and the last phrase within sentence 11; Not necessary to dispute resolution. Paragraph 3: As to the first sentence, fourth sentence and seventh sentence; Not necessary to fact resolution. Paragraphs 4, 5 and 6 to the colon in paragraph 6: Not necessary to dispute resolution. The remaining portions of paragraph 6 are subordinate to fact finding. Paragraph 10: as to the last two sentences; Not necessary to dispute resolution. Paragraph 13: As to the next to the last sentence; Not necessary to dispute resolution. Paragraph 14: As to the fourth sentence and the last sentence; Not necessary to dispute resolution. Paragraphs 16, 17, 18 and 20: Subordinate to fact finding. Paragraph 21: Sentence 3 is subordinate to fact finding sentence 4 is not necessary to dispute resolution; sentences 5 and 6 are subordinate to fact finding. Paragraph 22: Next to the last sentence; Not necessary to dispute resolution. Paragraphs 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 38 and 41: Subordinate to fact finding, except the comments in the last sentence of paragraph 41 related to the operations of JSI causing or contributing elevated concentrations of parameters within the basin which is not found as fact. Paragraphs 42, 43 and 44: Subordinate to fact finding. COPIES FURNISHED: Kenneth G. Oertel, Esquire Chris Bryant, Esquire OERTEL AND HOFFMAN, P.A. Post Office Box 6507 Tallahassee, Florida 32314-6507 Thomas M. Baumer, Esquire Deborah Barton, Esq. GALLAGHER, BAUMER, MIKALS, BRADFORD, CANNON AND WALTER, P.A. 252-5 Independent Square Jacksonville, Florida 32202 Bradford L. Thomas, Esquire Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Victoria Tschinkel, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301
Findings Of Fact Petitioner owns a parcel of land including 24 lots that front on an L- shaped canal 1,520 feet long that is landlocked at both ends. At the top, the L-shaped canal is 40 feet across. It has almost perpendicular sides and is eight to ten feet deep. Petitioner proposes to dredge with a steel-track dragline in order to connect the landlocked canal to a canal system that is connected to Kings Bay in Citrus County. Culverts would be placed at the north end of the canal, and earth at the other end would be permanently removed, extending the canal. One result of such dredging would be that two additional lots would abut the L-shaped canal. Even before he bought the property, petitioner discussed some of the problems this project might entail with Alan Burdett, a DER employee. In order to minimize turbidity in open waters, petitioner proposes to dredge outward from the L-shaped canal. Only after the sand from the initial dredging had settled would the final increment of earth be excavated and then only on an incoming tide. Part of the fill would be placed on the bottom of the L-shaped canal to decrease its depth to roughly five feet, more nearly approximating the depth of the canal system to which it would be connected. The water in the L-shaped canal has a high biochemical oxygen demand. The surface is covered with mats of water hyacinths. Floating vegetation intercepts sunlight and interferes with photosynthesis in plants underneath, decreasing their oxygen output. Levels of dissolved oxygen in the water fall as a result. At night, moreover, floating plants may use dissolved oxygen from the water. Dissolved oxygen levels vary diurnally and decrease with depth where water strata are undisturbed. In general, dissolved oxygen levels vary inversely with water temperature. On June 11, 1980, a water sample taken from the bottom of the L-shaped canal was found to be devoid of dissolved oxygen, while a sample from the surface contained 0.4 milligrams per liter of dissolved oxygen. One of petitioner's witnesses described the water in the L-shaped canal as very foul. On the morning of August 21, 980, a dissolved oxygen level in the L-shaped canal of two milligrams per liter was measured. DER's Exhibit No. 2. Sampling of water in the L-shaped canal by petitioner's agent on October 4 and 5, 1979, indicated dissolved oxygen levels of 4.1 milligrams per liter at high tide and 0.5 milligrams per liter at low tide. Petitioner's Exhibit No. 5, Table 3. A witness who reported seeing fish in the L-shaped canal testified that introducing water from the L-shaped canal into the existing canal system could cause a localized fish kill. This danger is evidently not very great, but the evidence did establish that the high level of biochemical oxygen demand and low level of dissolved oxygen found in the L-shaped canal are harmful rather than helpful to fish. The canal system which would receive the water now contained in the L- shaped canal, opens into Kings Bay, the spring-fed source of Crystal River, which one of the petitioner's witnesses characterized as a "complex and sensitive estuarine system." Kings Bay, Crystal River, and the canals into which petitioner proposes to open the L-shaped canal constitute Class III waters. Water in this vicinity is high in chlorides but is classified as fresh water. In the canal system to which petitioner proposes to add the L-shaped canal, rafts of water hyacinths are present. Water quality in the canal system is poor, according to petitioner's expert witness. Measured level of dissolved oxygen in this canal system ranged from 9.0 milligrams per liter in early October of 1979, Petitioner's Exhibit No. 5, Table 3, to 1.9 milligrams per liter on June 11, 1980. Petitioner's Exhibit No. 6. It takes some four days to flush the existing canal system. The time necessary for flushing the canal system would increase if it is enlarged as proposed by petitioner, even though flushing action in one part of the present canal system would be facilitated. Crystal River is subject to tidal influence. Notwithstanding the 600 million gallons of water entering Kings Bay daily from springs, the incoming tide causes a current upriver. As a result, as much as five percent of a substance flushed out of a canal system like the one petitioner proposes to enlarge can be reintroduced into the canal system when the tidal flow reverses. The fecal coliform count in a sample of water taken from the L-shaped canal was very low, 10 per 100 milliliters. A water sample taken nearby downstream, in the vicinity of residential development, contained 850 fecal coliform bacteria, per 100 milliliters. There was no evidence, however, that these bacteria were attributable to human excreta rather than to the excreta of some wild animal. According to petitioner, persons who live in the area hope this project will go forward because they believe that the stagnant water in the L- shaped canal is a breeding place for mosquitoes. No witness reported seeing mosquito larvae in the L-shaped canal, however, and a biologist who had observed the canal was questioned on this point. Testimony was uncontradicted that small fish of a kind that feed on mosquito larvae inhabit the L-shaped canal. The evidence did not establish that mosquitoes breed in the L-shaped canal. Manatees winter in Kings Bay and Crystal River. These vegetarian mammals are members of an endangered species. Of 34 animals in Kings Bay "sampled [in the fall of 1979] . . . [26] . . . had prop scars, and 10 . . . had wounds in a stage of healing that suggested they were less than two months old." Petitioner's Exhibit No. 3. Efforts to protect the manatees include strict speed limits and a recently constructed structure around a favorite spot to act as a barrier for motor boats. A purpose of making the canal connections petitioner proposes is to make Kings Bay and Crystal River more accessible to motor boats.
Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That respondent deny petitioner's application for permit. DONE AND ENTERED this 19th day of December, 1980, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 904/488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of December, 1980. COPIES FURNISHED: John Crider, Esquire Route 1, Box 405 Plantation Village Crystal River, Florida 32629 David M. Levin, Esquire Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301
Findings Of Fact Petitioner, Kyle Brothers Land Company, Inc., is a land development and sales firm with principal offices located in Coral Gables, Florida. On November 12, 1980, Petitioner filed an application seeking the issuance of a permit/water quality certification by Respondent, Department of Environmental Regulation, to authorize the excavation of four canals 525' long x 2' wide each with sixteen 10' x 35' boat moorings and to complete excavation on three partially completed canals, all lying in Sections 4 and 5, Township 665, Range 29E, Big Pine Key, Monroe County, Florida. 2/ A copy of the permit application may be found as Petitioner's Exhibit 2. Petitioner's application was received by the Department on November 25, 1980, and reviewed for compliance with applicable state water quality standards, conservation criteria in Chapters 253 and 403, and rules promulgated thereunder. Additional information requested by Respondent was furnished by Petitioner in early 1981. A field appraisal of the project site was submitted by the Department staff on March 16, 1981. On April 8, 1981, the Department issued its intent to Deny the requested permit. A copy of the intent to Deny may be found as Petitioner's Exhibit 6. The Department based its intention to deny the permit on the grounds (a) applicant had not provided reasonable assurance that long-term impacts of the project would not result in violation of State Water Quality Standards for all surface waters and for Class III surface waters, and specifically including the following standards: biochemical oxygen demand, detergents, oils and greases, bacteriological quality, dissolved oxygen and nutrients, (b) applicant had not affirmatively shown the project would not interfere with the conservation of marine resources, and (c) applicant had not provided an affirmative showing of the public interest which would be served by the proposed dredging. Petitioners disputed the allegations set forth in the intent to Deny and requested a formal hearing to contest the denial of its application. That request precipitated the instant hearing. The proposed project is located within Port Pine Heights, a subdivision located on the northern end of Big Pine Key which lies approximately 25 miles east-northeast from the City of Key West. More than seven hundred lots have been sold within the subdivision since 1959 although only forty homes have been built to date. Of that total, approximately fifteen homes are located in the southern half of the subdivision where the proposed project is found. Two main canal systems have been constructed in the subdivision, each having an east-west channel that opens directly to Pine Key Channel to the west, and a number of closed-end finger canals extending to the north and south. The two east-west channels and the finger canals are artificially created bodies of water. The specific project site involves the southern canal system which is approximately six thousand feet long and fifty feet wide. It has fourteen finger canals extending from its northern side, including those to be unplugged and excavated, and twelve to the south. The finger canals are 525 feet long by 25 feet wide. The canals to be dredged lie on the landward end of the east-west channel and were constructed by blasting around 1960. A cease and desist order issued by the United States Army Corps of Engineers in 1973 halted completion of the canals at issue and they have remained either plugged or unexcavated since that time. Petitioner wishes to undertake the proposed work so that it may complete the subdivision begun in 1959. Upon completion, the six canals will have ninety-six waterfront single-family residential homesites of which twenty have already been sold. Because many homesites have more than one lot, a saturation of the area with homes is unlikely. Additionally, the construction of homes within the subdivision has been extremely slow (only forty homes built in twenty years) and no substantial increase in that pace is expected even after the project is completed. Under applicant's proposal the excavated canals will have depths of -4 feet mean low water (MLW) at the dead end increasing to -6 feet MLW at the connection of the existing fifty foot main canal, or an average depth of five feet. The existing canals are all deeper than the proposed canals. The excavation will be done in native oolite limerock and the spoil from the canal system will be used to grade the adjacent upland and form a rip-rap shoreline above the rock level. The entire area will be enclosed by turbidity screens until all work is completed. The substrate at the location is Miami oolite, a type of limestone which is characterized by the presence of fissures and hollows. Even though some groundwater-to-canal water interchange will occur, stormwater runoff has had no deleterious effects on other areas of the canal system since residential development began in the subdivision some years ago. Additionally, oolite rock is typically filled with crevices and dead-ends which hold water or leachate and can aid in minimizing the groundwater-to-canal water interchange. A modified tidal flushing analysis was performed by Dr. John D. Wang, Jr. on behalf of Petitioner in July, 1981. 3/ The analysis investigated the mixing and circulation (flushing) of tidal water in the existing canal system and determined the quantity of water exchange between Pine Channel and the existing canal system. After the project is completed, the overall flushing characteristics and concomitant water quality in the proposed system will be significantly improved. These improved characteristics are primarily due to the new canals having a favorable ratio of MLW volume to tidal prism 4/. As such, there will be higher tidal velocities and more favorable mixing between the canals and the ocean. This is Particularly true for those canals that lie closest to Big Pine Channel. Because the overall flushing time will be reduced on almost all of the system, its ability to purge itself of unwanted constituents will also improve. The Department's concern that boat slips to be cut into the sides of the new canals will cause dead areas of water is not valid. The moorings will not affect flushing because the proposed canals are sufficiently shallow to insure good mixing. Water quality tests within the existing canal system were made by Petitioner in 1980 and 1981 and by Respondent in 1981. The results of applicant's 1981 testing may be found as Petitioner's Exhibit 5, and include samplings of dissolved oxygen, temperature, oils and greases, detergents, total and fecal coliforms, biochemical demand (BOD), and nutrients. Respondent's testing included only dissolved oxygen and has been received as Respondent's Exhibit 5. Water quality sampling reflected only one total coliform and no fecal coliforms in the most developed canal in the southern canal system. Readings in the older area of the subdivision adjacent to a septic tank disclosed an extremely low bacteria count. Given the rate of growth over the past twenty years, and the almost nonexistent presence of bacteria, the proposed canals should not cause a violation of the bacteriological criterion. Measurements of dissolved oxygen (DO) in the existing canal system and offshore ambient waters were taken by both Petitioner and Respondent. Dissolved oxygen is the amount of oxygen in the water, usually measured in a liter of sea water, and is needed for respiration of animals and organisms in the water. Biochemical demand (BOD) was also measured in the existing canal system. This measures the amount of oxygen demanded by organics or organisms in the water to convert oxygen to dioxide and water. High BOD levels indicate high amounts of organic debris in the water. High BOD and a lack of dissolved oxygen would cause an anaerobic environment which would probably produce hydrogen sulfide. State water quality standards require that the concentration of dissolved oxygen "shall never be less than 4 milligrams per liter" in predominately marine waters. Rule 17-3.121(14), Florida Administrative Code. Measurements in the open canal system taken by Petitioner in August, 1980, and by Respondent in September, 1981, reflected readings of less than 4 milligrams per liter during the early morning hours. However, such readings are not unusual in natural settings such as Big Pine Key following a long period without light or photosynthesis. The values did not fall below the minimum standards in the canal system on samples taken after 10:00 a.m. Measurements taken in the ambient waters adjacent to the canal system reflected lower readings than those in the canal system. These values also increased during the later hours of the day. increased flushing in the proposed system and shallower depths will increase oxygen throughout the canals. Therefore, its construction cannot be expected to cause DO levels to drop below the present levels found in the canals and ambient waters. Indeed, the shallower canals will be strong producers of oxygen with a high degree of photosynthetic activity and will contribute oxygen to the rest of the canal system. With the exception of one BOD reading of 1.02, all were less than one unit, and may be characterized as extremely low. These levels will not be increased as a result of the proposed activity to the extent that dissolved oxygen will be depressed below 4 milligrams per liter. Oil and grease concentrations may not exceed 5 milligrams per liter under state standards. Readings taken by Petitioner in the canals and ambient waters were less than 0.01 milligrams at every station. Automobiles and boat traffic are generally the primary source of oils and greases. The Department's concern that subsequent development within the subdivision will substantially increase the input of oils and greases into the waters is speculative at best, particularly in view of the low rate of growth in the subdivision over the past twenty years, the extremely low readings in already developed areas, the fact that present concentrations would have to be multiplied 5,000 times to approach proscribed levels, and the back-sloping of lots by Petitioner to minimize stormwater runoff into the canals. Detergents are barely measureable in the existing canal system and ambient waters. In order to exceed state standards, the present levels would have to be increased at least 500 times. Although the Department expects detergents to be added to the waters through stormwater runoff and septic tank leachate, this assertion is inconsistent with present readings taken at stations near homes with septic tanks. In the context of this proceeding, nutrients may be defined as fertilizers or food for marine plants. An excess of nutrients in sea water can increase the level of biochemical demand which in turn decreases dissolved oxygen thereby causing eutrophication of the canal system. The nutrient levels of the present system are low. This was evidenced by Petitioner's measurements of ammonium, nitrates, inorganic phosphate and silicate. The low readings were present even in the older, more developed areas of the canal system. Respondent fears that development would hasten eutrophication in the canal system because bacteria and nutrients would be introduced through septic tanks and stormwater runoff. However, stormwater and septic tank leachate have had no adverse effects on the main canal system which has been in use since 1967. Indeed, continual monitoring of the system by Petitioner since 1974 reveals that the system is a thriving biological community in which nutrients are being utilized by animals at the rate the system produced them. No violation of applicable state standards is expected after the project is completed. The present canal system has a rich and diverse natural population of flora and fauna. However, all areas are not uniform in their attributes or communities. The water within the system is clear. The biological communities are more extensive and diverse within the existing canal system than offshore. Because the new canals will not exceed six feet in depth, they can be expected to develop quite extensive communities of plant life on their bottoms. Colonization of algae on the sides of the canals should occur within a few weeks after the canals are opened. The optimum level of diversity of plants and animals should be reached within four years. The amount of photosynthetic activity on the walls and bottom of the new system due to its shallow depth will contribute oxygen to the other canals within the system. The new canals will make a significant contribution to the total marine ecosystem. The method of sewage disposal utilized by homes that have been built at the subdivision is septic tanks. Septic tanks would likely be used by any new homes built in the area in the immediate future. Petitioner is willing to construct a central sewage treatment plant whenever development is sufficient to make a plant economically feasible. in Petitioner's judgment, at least thirty homes on or around the new canal system must be built before it is willing to undertake such a project. The use of septic tank by the forty homes now built in the subdivision has not caused violations of any bacteriological quality standards to date. Moreover, testing of those same standards in another canal system on Big Pine Key by Respondent disclosed that septic tank leachate had not contravened those standards. (Respondent's Exhibit 1). The addition of thirty more homes in the subdivision over an extended period of time should not increase the amount of contaminants to a level that violates state water quality standards. Petitioner commenced development of its subdivision at Port Pine Heights in 1959. The southern portion of the subdivision in which the proposed canal system is located was first platted in 1963. Five lots on the unfinished canals have been sold prior to April 3, 1970. Completion of the canals was a condition of the contracts for deed to those lots. Petitioner has unsuccessfully sought to obtain the necessary permits to complete the canal project in issue in 1974 and 1976.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the application of Kyle Brothers Land Company, Inc. for a permit/water quality certification to excavate four dead end canals and to complete excavation of two partially constructed dead end canals on Petitioner's subdivision in Big Pine Key, Monroe County, Florida, be GRANTED. DONE and ENTERED this 20th day of January, 1982, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 20th day of January, 1982.
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: On May 3, 1978, the petitioner filed with the respondent an application for dredge and fill permits and a water quality certificate to allow petitioner to complete its planned residential community on and adjacent to Marco Island, Florida. the petitioner expended in excess of $100,000.00 in preparing the permit application. The proposed project involves some 4,000 acres of development on approximately 17,000 acres of land owned by the petitioner. On November 28, 1979, after seeking and obtaining additional information from the petitioner, the respondent issued its notice of "intent to deny" the permit application. The Department claims jurisdiction over the proposed project pursuant to Chapter 253 and 403, Florida Statutes, and Section 17-4.28 and 17-4.29, Florida Administrative Code. The nine page "intent to deny" specifically cites Rule 1704.28(3), Florida Administrative Code, and concludes that state water quality standards will be violated. Beyond that regulatory citation, the "intent to deny" does not specify by rule number which of the water quality standards the Department feels would be violated by the proposed project. However, the "intent to deny" does conclude that the area proposed for development will include "approximately 1,500 acres of uplands and approximately 2,600 acres of waters of the State, submerged lands of waters of the State, and transition zone of submerged lands of waters of the State. In discussing the overall impact from the project as a whole, the respondent notes that the intertidal shoreline areas are utilized by wading birds and that the mangrove tidelines provide a vital habitat for fish and wildlife. In discussing the specific work areas, the respondent concludes that the destruction of the extensive freshwater marsh system would eliminate a significant habitat intensely utilized by a wide variety of birds. The "intent to deny" further concludes that the development of the proposed work area would be expected to violate state water quality standards for dissolved oxygen. The respondent's "intent to deny" is the subject of a pending administrative proceeding between these same parties in Case Numbers 79-2471 and 80-683. In those proceedings the petitioner is contesting, inter alia, the respondent's application of the rules under challenge in this proceeding. Although petitioner challenges other rules of the Department, the testimony adduced at the hearing concerned only those rules relating to water quality standards; to wit: Rules 17-3.05, 17-3.08(4) and 17-3.09(3). Dissolved oxygen concentrations are an important gauge of the existing quality of water and the ability of a water body to support a well-balanced aquatic animal life. A concentration of at least 5.0 parts per million (or milligrams per liter) is needed to support a well-balanced fish population, and a concentration of 4.0 mg/1 is about the lowest which will support a varied fish population. There are numerous natural factors which affect the concentration of dissolved oxygen in surface water bodies. Such factors include physical transfer between the water and the atmosphere (aeration), the limit of a water body's ability to absorb oxygen (saturation value), the amount of oxygen used to decompose dead material, photosynthesis of aquatic plants and the actual vertical location of the sampling. These factors are influenced by many variables, such as wind, temperature, stratification, salinity, the season of the year, the time of the day, rainfall, water clarity, mixing and flushing. The level of dissolved oxygen can vary significantly in the same body of water during one twenty-four hour period. A balance of dynamic, natural processes causes dissolved oxygen levels to vary extensively in different water bodies and within the same water body during different times of the day and during different seasons of the year. Some of the water bodies in the Marco Island area contain dissolved oxygen values below 4.0 parts per million (or milligrams per liter) during at least a portion of a twenty-four hour period. This is due to natural, as opposed to manmade, causes. A water body containing levels of dissolved oxygen less than 4.0 milligrams per liter does not necessarily indicate a discharge of contaminants into that water body. The parties have stipulated that the Final Order rendered by the Department of Environmental Regulation in the case of Capeletti Brothers, Inc. v. Dept. of Environmental Regulation, Case No. 79-1602R (July 7, 1980), accurately represents the Department's position with respect to its authority to consider wildlife and other biological factors in reviewing permit applications pursuant to Chapter 403, Florida Statutes.