The Issue Did respondent fail to properly supervise, direct and manage the contracting activities of the business of which he is the qualifier, and if so, what disciplinary action should be taken against respondent's contracting license?
Findings Of Fact At all times material to this proceeding the respondent was a certified building contractor licensed by the State of Florida and the qualifying agent for Custom Concrete of Naples, Inc. (Custom Concrete). Rodney Velez was the president of Custom Concrete and licensed only in concrete--concrete forming, placing and finishing. Susan Velez, Rodney Velez's wife, was an officer of Custom Concrete. On April 23, 1983, Custom Concrete, by and through Rodney Velez, entered into a contract with Mark and Penny Paterson to construct a home for $38,550.00. Mrs. Paterson had previously met Rodney Velez in the course of her work, and Velez had told her that he was a builder. Mrs. Paterson had suggested that Velez look at a floor plan that she and her husband had, and after certain negotiations, including a change of floor plan, the contract was entered into. During the course of the negotiations Mrs. Paterson never talked to the respondent and was unaware that the respondent was involved or would be involved in the construction of the home. Mrs. Paterson believed that Rodney Velez was the "builder"; however, the construction of the Paterson home was beyond the scope of Velez's concrete license. The respondent signed the application to secure the building permit for the Paterson residence, although he did not personally appear to procure the building permit. The clerk of the contractor's licensing section of the building code compliance department relied on the signature on the application because it was notarized. The notary was Susan Velez. Respondent did not supervise or direct the construction of the Paterson home. Neal Jackson, president of the company who did the electric work on the home, was unaware that respondent was involved in the project until well after the house was finished. Although it is usual for a supervisor or superintendent to be at the job site some of the time, Jackson never saw the respondent or Velez at the job site. Jeff Allain, the carpenter who did the framing and certain other work, was on the job site five or six days and saw the respondent once during the framing of the structure "just generally looking around." The respondent didn't say anything to Allain. David Isom did drywall work on the house. He had no contact with the respondent and did not see him at the construction site. Mrs. Paterson went by the construction site quite often and realized that the job was not being properly supervised. Velez was rarely there, and Mrs. Paterson never saw the respondent. The workmen on the site would ask the Patersons when Velez would be there because they had questions concerning the work. Neither of the building inspectors saw anyone supervising at the job site, although usually no one is at the job site when an inspection is made. Two days after the Patersons moved into their house, they compiled a "punch list" of the items that needed to be completed or corrected. The list was given to Velez, but the work was not corrected to the Paterson's satisfaction. Although Velez did not give the "punch list" to respondent, Velez discussed the problems with the respondent. Respondent did not take any steps to remedy the problems and said he thought "a lot of it was nonsense." Velez told respondent that he, Velez, would take care of it. Because of the unresolved problems with the house, Mrs. Paterson finally called the licensing board to file a complaint against Rodney Velez. At that time, she was informed that Rodney Velez was not the contractor; the contractor was the respondent. This was the first time that Mrs. Paterson was aware that the respondent was involved with the construction of the house. All of the Patersons dealings had been with Velez, and all checks for construction payments were made out to Velez personally. 2/ Even though the Patersons had not received satisfaction from Custom Concrete for the problems with the house, they signed the closing papers because Velez threatened to evict them. At closing the Patersons received a lien release from Custom Concrete which released all work prior to March 9, 1984. Subsequently, Velez filed a claim of lien against the Paterson property for work completed on February 9, 1984.
Recommendation Based upon the foregoing findings of fact and conclusions of law it is recommended that respondent be found guilty of violating Section 489.129(j), Florida Statutes, that he be fined $1,000.00, and that his license be suspended for 60 days from the date the Construction Industry Licensing Board enters its final order in this case. DONE and ORDERED this 30th day of January, 1985, in Tallahassee, Florida. DIANE A. GRUBBS Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of January, 1985.
The Issue The issue presented for decision herein is whether or not the Respondent, David H. Tinius, unlawfully abandoned a construction project; diverted funds received for completion of a construction project and thereby failed to fulfill his contractual obligations.
Findings Of Fact Based on my observation of the witnesses and their demeanor while testifying, the documentary evidence received and the entire record compiled herein, the following relevant facts are found. By its administrative complaint filed herein signed October 6, 1982, the Petitioner, Construction Industry Licensing Board, seeks to suspend, revoke or take other disciplinary action against the Respondent's registered building contractor's license. During times material herein, Respondent was a registered building contractor and has been issued license No. RB0024083. On approximately April 20, 1978, Respondent entered into a contract with Jess Marks to build a residence in Tamarac, Florida, for the sum of $46,551. Respondent commenced construction of the Mark's residence but left the site when it was approximately forty percent complete. At that time, Respondent had received approximately $44,000 of the contract sum. Jess Marks completed the construction of his residence by hiring another contractor to complete the project and expended approximately $50,000 over and above the contract price as agreed upon by the Respondent to complete his residence. Respondent never returned any of the monies received from the Marks for completion of the residence. On approximately April 24, 1978, Respondent entered into a contract with Abe Abrahams to construct a residence in Tamarac, Florida, for the sum of $30,473. Respondent left the Abrahams' project after he had received $6,000 and had completed approximately ten percent of the work on the Abrahams' residence. Respondent did not return to the site nor did he return any of the monies received from the Abrahams for the construction of their residence (See Petitioner's Composite Exhibit No. 5). The Abrahams had to pay for supplies and material bought for the project by the Respondent and which reportedly had been paid, according to Respondent. THE RESPONDENT'S POSITION As noted hereinabove, the Respondent did not appear to contest or otherwise refute the allegations contained in the administrative complaint filed herein. However, Respondent, through counsel, filed an answer which admitted the complaint allegations filed herein.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, hereby RECOMMENDED that the Respondent's registered building contractor's license No. RB0024083 be REVOKED. DONE and RECOMMENDED this 29th day of August, 1983 in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of August, 1983 COPIES FURNISHED: Michael J. Cohen, Esquire 2715 East Oakland Park Boulevard Suite 101 Fort Lauderdale, Florida 33306 David H. Tinius 4420 Northwest 36th Court Lauderdale Lakes, Florida 33309 David H. Tinius Post Office Box 6338 Charlotte Amalil St. Thomas, U.S.V.I. 00801 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Fred M. Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301
The Issue The issues in this case are whether Respondent, Daniel F. Acevedo, committed the offenses alleged in a four-count Administrative Complaint filed with Petitioner, the Department of Business and Professional Regulation, on July 11, 2008, and, if so, what penalty should be imposed.
Findings Of Fact Petitioner, the Department of Business and Professional Regulation (hereinafter referred to as the "Department"), is the agency of the State of Florida charged with the responsibility for, among other things, the licensure of individuals who wish to engage in contracting in the State of Florida; and the investigation and prosecution of complaints against individuals who have been so licensed. See Chs. 455 and 489, Fla. Stat. Respondent, Daniel F. Acevedo, is and has been at all times material hereto a certified general contractor in Florida, having been issued license number CGC 1506071. Mr. Acevedo is also a Certified Roofing Contractor, having been issued license number CCC 1326888. Both licenses were issued by the Construction Industry Licensing Board (hereinafter referred to as the “Board) and are in “current active” status. At all times material, Mr. Acevedo was the primary qualifying agent for All Design Systems, Inc. (hereinafter referred to as “All Design”). All Design is a Florida corporation. Mr. Acevedo is an officer of the corporation. All Design’s certificate of authority, License Number QB 26737, was issued on September 4, 2003. The license expired on August 31, 2007, and was in delinquent status from September 1, 2007, to May 14, 2008. Mr. Acevedo remained the qualifying agent during the delinquent period. All Design employed three to four sales agents who “sold” construction projects to commercial and residential property owners on behalf of All Design. All Design utilized these individuals because it believed they had experience in the construction industry and that they held licenses or certifications which would allow them to perform estimates on construction projects and make appropriate bids. The sales agents were to find customers for All Design and enter into contracts with them on behalf and in the name of All Design. In August of 2005, Mr. Acevedo was approached by Eduardo Rodriguez. Mr. Rodriguez offered to locate potential home remodeling customers for All Design in exchange for a percentage commission. Mr. Acevedo agreed. At no time relevant to this matter was Mr. Rodriguez licensed in Florida to engage in contracting as a state certified or registered contractor. Nor was Mr. Rodriguez’s business entity, Eduardo’s Construction, Inc. (hereinafter referred to as “Eduardo’s Construction”), licensed with a certificate of authority as a contractor qualified business. Mr. Rodriguez was the president and sole officer of Eduardo’s Construction. Eduardo’s Construction was not incorporated in Florida. Some time during 2005, Grace Esposito obtained a business card for Eduardo’s Construction. She obtained the card after discussing with a neighbor construction work that was being performed by Eduardo’s Construction on the neighbor’s residence. The neighbor informed her that Mr. Rodriguez was the contractor performing the work. The business card incorrectly represented that Mr. Rodriguez was licensed and insured. Ms. Esposito called the number listed for Eduardo’s Construction and spoke with a man who identified himself as Eduardo Rodriguez. In August 2005, Mr. Rodriguez met with Ms. Esposito at her condominium residence, located at 20301 West Country Club Drive, Aventura, Florida (hereinafter referred to as the “Subject Property”). Ms. Esposito discussed with Mr. Rodriguez the work which she desired. Based upon representations from Mr. Rodriguez, Ms. Esposito believed that he was licensed to perform the work being discussed. The evidence failed to prove, as suggested by Mr. Acevedo, that Mr. Rodriguez “bid on the Esposito job, [and] orally agreed to essential terms with Esposito on behalf of All Design Systems, Inc., Respondent’s Firm.” Mr. Acevedo’s testimony in this regard was uncorroborated hearsay and was contradicted by the credible testimony of Ms. Esposito. On September 5, 2005, Ms. Esposito entered into a written contract with Mr. Rodriguez, doing business as Eduardo’s Construction, for the remodeling of the Subject Property (hereinafter referred to as the “Contract”). Ms. Esposito agreed in the Contract to pay $24,000.00 for the remodeling. Upon execution of the Contract, Ms. Esposito paid Eduardo’s Construction with three checks totaling $12,000.00 for the remodeling. Mr. Rodriguez informed Mr. Acevedo of the project in September 2005. At that time, without reviewing the Contract, Mr. Acevedo executed a building permit application which Mr. Rodriguez provided him for the project. The permit application had not been signed by Ms. Esposito. In October 2005, Mr. Rodriguez presented the building permit application to Ms. Esposito for her signature. The permit application was then submitted to the building department. The building permit was subsequently approved and issued under Mr. Acevedo’s license and in the name of All Design. Ms. Esposito had been told that part of the work would be completed in October. When this representation proved untrue, she began contacting Mr. Rodriguez. Mr. Rodriguez told her that it was taking time to get the permit due to delays at the building department. Eventually, when she was no longer able to contact Mr. Rodriguez, Ms. Esposito went directly to the building department where she learned that All Design was the contactor of record and not Eduardo’s Construction. On or about October 31, 2005, Ms. Esposito telephoned All Design and spoke with Mr. Acevedo. She informed Mr. Acevedo about the Contract. Mr. Acevedo agreed to meet with her. On November 1, 2005, Mr. Acevedo visited Ms. Esposito at the Subject Property. She showed him the work that had been performed and explained the details of the Contract and what had transpired with Mr. Rodriguez. Mr. Acevedo told Ms. Esposito that his relationship with Mr. Rodriguez was that he merely allowed Mr. Rodriguez to use his license to pull permits in exchange for $150.00. Mr. Acevedo told Ms. Esposito that he would attempt to get Mr. Rodriguez to complete the job. This meeting was memorialized in a letter to Mr. Acevedo written by Ms. Esposito. At some time in November, work recommenced on the project. Within approximately three days, however, work stopped. Ms. Esposito sent four emails to Mr. Acevedo describing the work performed and the cessation of the project. Ms. Esposito made a final request that the project be completed. Mr. Acevedo did not respond to the emails. On or about November 17, 2005, Ms. Esposito sent a letter to Mr. Acevedo outlining the events, requesting termination of the Contract, and the removal of Mr. Acevedo from the building permit. Mr. Acevedo did not respond to this letter. The building permit was cancelled by Mr. Acevedo in December 2005. The total investigation costs incurred by the Department, excluding those costs associated with any attorney’s time, was $381.83. Mr. Acevedo has not previously been disciplined by the Board.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered finding that Daniel F. Acevedo violated the provisions of Section 489.129(1)(d), (i), and (m), Florida Statutes, as alleged in Counts I, II, III, and IV of the Administrative Complaint; imposing fines of $250.00 for Count I, $1,000.00 for Count II, and $2,000.00 for Count III; requiring that Mr. Acevedo pay the costs incurred by the Department in investigating and prosecuting this matter; placing Mr. Acevedo’s licenses on probation for a period of two years, conditioned upon his payment of the fines, payment of the costs incurred by the Department; and any other conditions determined to be necessary by the Board. DONE AND ENTERED this 11th day of March, 2009, in Tallahassee, Leon County, Florida. LARRY J. SARTIN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 11th day of March, 2009. COPIES FURNISHED: Brian P. Coats, Esquire Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street, Suite 42 Tallahassee, Florida 32399-2022 Daniel Acevedo All Designs Systems, Inc. 2813 Executive Drive Weston, Florida 32388 Kenneth Stein, Esquire 8436 West Oakland Park Boulevard Sunrise, Florida 33351 G. W. Harrell, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Ned Luczynski, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792
The Issue The issue for determination at the final hearing was whether the contracting license of the Respondent Konrad v. Ising should be suspended, revoked, or otherwise disciplined by the Petitioner Department of Professional Regulation, for alleged violations of Chapter 489, Florida Statutes. At the final hearing Petitioner's Exhibits 1 and 2(a)-(g) were offered and admitted into evidence. The Respondent testified on his own behalf.
Findings Of Fact The Respondent Konrad V. Ising is licensed to practice contracting in Florida, and is a licensed certified general contractor holding license number CG C009669, a license current and active from 1982 through the present. The Respondent qualified Master Craft Constructors using license number CG C009669. During 1982, the Respondent entered into an association with Carlton Mosher whereby the Respondent would use his contractor's license to obtain building permits for construction projects which Mosher had contracted. The Respondent hoped his association with Mosher would lead to a partnership and assist him in obtaining practical experience in the construction field. During his association with the Respondent, Mosher was not a licensed contractor. In December 1982, Mosher, doing business as Re-Builders, contracted with Russell Hirstins to construct a room addition on his home at 4034 27th Avenue, St. Petersburg, Florida. On December 3, 1982, an application for a building permit for the job was submitted to the City of St. Petersburg and permit number 88638 was issued. The permit was obtained using the Respondent's license number and Respondent is listed as the job contractor. However, the Respondent performed no work on the Hirstins job, maintained no control over Mosher's work, failed to adequately supervise the project, and failed to qualify Re-Builders with the Construction Industry Licensing Board. Since becoming licensed in 1975, the Respondent has not been involved in any other disciplinary proceedings. At the final hearing, the Respondent candidly acknowledged that his association with Mosher was a regrettable mistake. The project was completed by Mosher to the apparent satisfaction to the Hirstins.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED: That a Final Order be entered by the Construction Industry Licensing Board finding the Respondent Konrad V. Ising guilty of violating Section 489.129(1)(g) and (j), Florida Statutes, and imposing a $250 administrative fine. DONE AND ORDERED this 30th day of January 1984, in Tallahassee. SHARYN L. SMITH Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of January 1984. COPIES FURNISHED: Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Konrad V. Ising Post Office Box 1023 Maitland, Florida 323751 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Frederick Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32302
The Issue Whether Respondent, a licensed general contractor, committed the violations alleged in the three-count Administrative Complaint filed by Petitioner and the penalties, if any, that should be imposed.
Findings Of Fact Respondent is the agency of the State of Florida with the responsibility to regulate building contracting. At all times relevant to this proceeding, Respondent has been licensed as a certified general contractor, having been issued license number CG C058340 in 1996. At all times relevant to this proceeding, Ms. McKinney owned and resided in a house (the House) in Opa Locka, Florida. Ms. McKinney’s mother, Mattie P. Mathis, also lived in the House. In 2001, Ms. McKinney solicited bids for an addition she wanted to put on the House. Ms. McKinney and her mother, Ms. Mathis, planned to pay for the addition with life insurance proceeds on the life of Ms. Mathis’s deceased daughter (Ms. McKinney’s sister). On the recommendation of a colleague at her work, Ms. McKinney asked Willie Muse, Jr., to bid on the work. Based on the bids she received, Ms. McKinney hired Mr. Muse to construct the addition to the House. Ms. McKinney told Mr. Muse that she wanted all work to comply with all applicable permitting requirements and laws. Mr. Muse represented to Ms. McKinney that he would get the necessary building permits and that the work would comply with all applicable laws. On July 18, 2001, Ms. McKinney and Ms. Mathis entered into a written contract with Mr. Muse whereby Mr. Muse agreed to construct the addition for the sum of $45,000.00. Mr. Muse has never been licensed as a general contractor in Florida. Ms. McKinney thought Mr. Muse was a licensed contractor and would not have entered into a contract with him if she had known that he was not licensed. Pursuant to the contract, Ms. McKinney and Ms. Mathis paid Mr. Muse the following amounts on the following dates: $6,000.00 on July 20, 2001; $7,500.00 on October 10, 2001; and $13,500.00 on November 2, 2001; for a total of $27,000.00. On or about August 21, 2001, Mr. Muse brought to Ms. McKinney a building permit application form for her to sign. The application form had been filled out before Mr. Muse presented it to Ms. McKinney. Respondent was not present when Mr. Muse presented the form to Ms. McKinney. Respondent’s name, signature, and contractor’s license number appeared on the application form when Mr. Muse presented the form to Ms. McKinney. Ms. McKinney signed the form on August 21, 2001. Ms. McKinney saw Respondent’s name for the first time when she read the building permit application form. Prior to that time, Ms. McKinney and Ms. Mathis had never known or heard of Respondent. At all times relevant to this proceeding, Respondent knew that Mr. Muse was not a licensed contractor. Mr. Muse submitted the building permit application form to the Miami-Dade County Building Department (Building Department), which issued a building permit for the work on the House on October 5, 2001. Mr. Muse commenced working on the House in October 2001, but he never finished. After he received the payment in November 2001, Mr. Muse stopped working on the House for an extended period of time. During that time, Ms. McKinney attempted on several occasions to persuade Mr. Muse to resume work on the House. Prior to stopping work on the House, Mr. Muse removed a portion of the roof of the existing structure, which exposed the interior of the House to the elements. That exposure resulted in extensive damages to the House, including the collapse of the kitchen ceiling from water intrusion. By letter dated April 15, 2002, the Building Department advised Ms. McKinney that her building permit would expire in approximately 30 days. That letter prompted Ms. McKinney to contact the Building Department, where she was told that Respondent was her contractor, not Mr. Muse. Ms. McKinney secured information (from the face of the building permit) that enabled her to contact Respondent’s mother.3 That contact resulted in two meetings between Ms. McKinney and Respondent towards the end of April 2002. During the first meeting, Ms. McKinney related to Respondent the history of the project, including the amounts that had been paid to Mr. Muse. She also showed him the work that had been done and the damages that had occurred. During the second meeting, Mr. Muse was in attendance. Ms. McKinney, Ms. Mathis, and Respondent reached a verbal understanding that was not reduced to writing. They agreed that Respondent would finish the work on the House for the unpaid balance of the contract price $45,000.00 less $27,000.00 paid to Mr. Muse, which equals $18,000.00.4 The parties agreed that Respondent would pay for labor and that Ms. McKinney and Ms. Mathis would pay material suppliers directly and receive credit toward the contract price for such payments. The parties contemplated that Mr. Muse would perform most of the labor because of the monies he had already received. On the basis of the verbal contract, Respondent resumed the work on the House. On June 12, 2002, Respondent presented a draw request for $3,500.00 for electrical, plumbing, and roofing work that had been performed. Ms. Mathis wrote Respondent a check in the amount of $3,500.00 for that work. Ms. McKinney was opposed to paying Respondent the sum of $3,500.00 because she believed he had not completed the work for which he was billing. Ms. Mathis paid that sum despite Ms. McKinney’s opposition. At some undetermined time following June 12, 2002, Ms. McKinney told Respondent that she did not want Mr. Muse working on the House. Respondent then asked to be paid in advance for work to be done on the House because he would have to pay his laborers. Ms. McKinney and Ms. Mathis would not agree to payment in advance. In July 2002, the project was not complete and Respondent’s progress on the work on the House became unsatisfactory to Ms. McKinney. On October 14, 2002, Ms. McKinney filed a complaint against Respondent with Petitioner, claiming, among other things, that Respondent had abandoned the project. Her complaint alleged that work ended on the project in July 2002. At some undetermined time between June and October 2002, Ms. McKinney filed a criminal complaint against Mr. Muse, which resulted in criminal misdemeanor charges being filed against him in Miami-Dade County Court. After she filed the criminal complaint against Mr. Muse, Ms. McKinney told Respondent that she wanted to wait to proceed with the project until she knew what was going to happen with her criminal complaint. In the criminal proceeding, the Court ordered Mr. Muse on April 11, 2003, to pay restitution to Ms. McKinney in the amount of $16,008.04, payable in monthly installments of $300.00. On March 2, 2004, the Court reduced the amount of restitution to $4,000.00, payable in monthly installments of $50.00 beginning April 1, 2004. As of the date of the final hearing in this proceeding, Mr. Muse had paid Ms. McKinney restitution in the total amount of $750.00. As part of the criminal proceeding, Respondent was asked to give his opinion as to the value of the work completed by Mr. Muse and his estimated cost of completing the work. Respondent valued the work completed by Mr. Muse at $14,073.75 (labor and materials). Respondent estimated that it would cost $22,200.00 to complete the project. Both estimates were dated March 23, 2003. On October 1, 2003, Theodore R. Gay, Assistant General Counsel for Petitioner wrote Ms. McKinney the following letter pertaining to the complaint she had filed in October 2002: The Legal Department has evaluated your complaint against the above named contractor [Respondent]. After reviewing the evidence gathered during the investigation of the referenced matter, we have determined that in accordance with the rules and policies of the Construction Industry Licensing Board, this case is appropriately closed with the issuance of a Letter of Caution to the contractor. Because this case has been dismissed without a finding of probable cause, the file will remain confidential and exempt from the public records. On January 6, 2004, Ms. McKinney wrote Mr. Gay a letter that provided, in part, as follows: This letter is a request to re-open the case [against Respondent] because as prior conversation (sic) when I spoke to you in late August 2003 or early September 2003, I informed you that Mr. Jones told me that he would help me as much as possible to complete the construction on my property. Since your letter that stated you didn’t find any error on Mr. Jones’ behalf, I have not heard or seen him since October 2003, nor has any work been performed on my property. . . . Respondent came back to the House after October 2003 and talked to Ms. McKinney about the work. Ms. McKinney told him that she would pay up to a total of $45,000.00 for the work, but that she would not pay above that figure. Because of the estimate Respondent provided in the criminal proceeding dated March 23, 2003, Ms. McKinney believed that Respondent wanted $22,0000.00 to complete the work. However, Respondent never told her that he would not complete the work for a sum equal to $45,000.00 less the sums that had already been paid. Ms. McKinney would not pay Respondent for work until after the work was completed. After Mr. Gay’s letter dismissing the complaint that Ms. McKinney had filed, Respondent did no further work on the House, but he did have further conversations about the project. Ms. McKinney and Respondent could not agree on payment terms for Respondent to complete the project. Ms. McKinney testified that she did not fire Respondent. However, it is clear that she would not let Mr. Muse do further work on her house and she would not pay Respondent until after the work had been done. Ms. McKinney changed the terms of her verbal contract with Respondent by prohibiting Mr. Muse from working on the project. In November 2003, Ms. McKinney and Ms. Mathis had an argument over the money that had been spent on the house. Ms. McKinney talked to Respondent about his helping her obtain a mortgage on the house to pay for the balance of the work on the House. Ms. McKinney told Respondent that she did not want Respondent to ask her mother for any more money. Ms. McKinney told Respondent that she would use him as the contractor to complete the work if she obtained the financing. Ms. McKinney was unable to get the financing due to the condition of the House. The permits obtained by Respondent are still valid. Ms. McKinney has hired various workers on her own in an effort to complete the work on the House. As of the final hearing, the work on the House had not been completed. As of May 19, 2005, Petitioner’s costs of investigation and prosecution of this case, excluding costs associated with attorney time, totaled $920.29.
Recommendation Based on the foregoing findings of fact and conclusions of Law, it is RECOMMENDED that Petitioner enter a Final Order that adopts the Findings of Facts and Conclusions of Law set forth in this Recommended Order. It is further recommended that the Final Order: Find Respondent guilty of the violation alleged in Count I of the Administrative Complaint and impose against him an administrative fine in the amount of $2,500.00; Find Respondent guilty of the violation alleged in Count II of the Administrative Complaint, but impose no additional administrative fine for that violation; Find Respondent not guilty of the violation alleged in Count III of the Administrative Complaint; Order that Respondent be jointly and severally liable to Ms. McKinney and Ms. Mathis with Mr. Muse for restitution in the amount of $4,000.00, minus $750.00 paid by Mr. Muse; and Order Respondent to pay costs of investigation and prosecution of this matter in the amount of $920.29. DONE AND ENTERED this 10th day of August, 2005, in Tallahassee, Leon County, Florida. S CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 10th day of August, 2005.