Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. KENNETH R. MARTIN, 87-005044 (1987)
Division of Administrative Hearings, Florida Number: 87-005044 Latest Update: Aug. 02, 1988

The Issue The administrative complaint filed on September 17, 1987 alleges that in a residential pool contracting job Respondent Martin ". . . exhibited financial mismanagement, misconduct, or diversion, in violation of 489.129(1)(h), (m) . . . [and] failed to perform in a reasonably timely manner, and/or abandoned said job, in violation of 489.129(1)(m), (k)." The issue is whether Martin committed those violations, and if so, what disciplinary action is appropriate.

Findings Of Fact At all times relevant, Kenneth Martin was licensed in the State of Florida as a registered commercial pool contractor, holding license number RP 0021608. His license is currently in inactive status. Martin was President of Adair Pools, Inc., the corporation under which he conducted his pool construction business. In early July 1986, Adair Pools contracted to build a residential pool for Paul and Cynthia Pajak at 8304 Helena Drive in Orange County, Florida. The pool was to be kidney-shaped, approximately 14 feet by 30 feet, with a waterfall and a detached spa. The contract amount of $11,571.00 expressly excluded the deck, electrical work and screening, although the written contract included a sheet describing the specifications for the excluded work, recommended contractors, and estimated costs. This sheet and the pool contract itself clearly indicated that these items were not the responsibility of the pool company and were not included in the contract price. Work commenced in July, shortly after the contract was signed. Although the contract did not specify a completion date, Martin concedes that the pool should have taken no more than four to eight weeks to complete. The Pajaks had planned a Labor Day party and were told by Adair's employees there would be no problem getting their pool finished for the party. The pool was not finished by Labor Day. After the pool was dug, shot with concrete and tiled, someone determined that the spa was supposed to have been raised. In attempting to raise the spa and to change the water jets, the workers cracked the shell of the spa and had to replace it. Until the problems with the spa, the Pajaks felt that the construction progress was reasonable and smooth. At this point, sometime around Labor Day, the problems began. Adair delayed in paying Shotcrete Pools, the subcontractor for the concrete shell, because Adair felt it was Shotcrete's fault that the spa was cracked. Shotcrete notified the Pajaks that a lien would be placed on the property if they were not paid. The notice to owner is dated November 3, 1986. Eventually Adair paid Shotcrete and its other subcontractors for the Pajak work and no lien was filed. The evidence does not reflect a clear sequence of events, but between Labor Day and February or March 1987, little progress was made to finish the pool. Martin's supervisor left and Martin's brother took over. The Pajaks kept calling Martin and were always assured that the job would be completed. Martin admits that the company at this time was in serious financial trouble because it was not being paid for a large commercial job that it had undertaken. On December 10, 1986, Mrs. Pajak's brother-in-law, an attorney, sent Martin a demand letter, giving a 10-day deadline for completion of the work. Martin and his brother met with the attorney and assured him the job would be finished. In spite of the problems, the Pajaks continued working with Martin and paid the full contract price, less the $100.00 that was to be paid when the pool was filled. On March 5, 1987, Martin informed the Pajaks that they should have the deck poured so that Adair could finish the pool. The Pajaks were not satisfied that the pool was ready for the deck as there were leaks in the waterfall, debris was all over the yard and the spa tile work looked messy. In Martin's opinion those items were his company's responsibility, but were part of the finishing to be done after the deck was poured and the pool was lined with marblelite. On March 21, 1987, the Pajaks contracted with another pool company for $4450.00 to finish their pool. Martin denies that Adair abandoned the job, but admits that it took an inordinate amount of time. The Pajaks did not allow him to finish the cleanup, the interior coating and the pool start up because they contracted with someone else. Martin did not contest that the waterfall leaked or that extensive cleanup needed to be done, but disputed that this work should be done before the deck was poured. He contended that the leaks in the waterfall would have been fixed when the finish was done. Martin estimates that between 1974 and 1986, his company completed over fourteen hundred residential pools and approximately five hundred large commercial pools. Martin has been active on various local pool construction industry boards and has no record of prior disciplinary action against his license.

Recommendation Based upon the foregoing, it is, hereby, RECOMMENDED: That Kenneth Martin be found guilty of misconduct, in violation of Section 489.129(1)(m), Florida Statutes, not guilty of the other violations with which he is charged, and that he be required to pay an administrative fine of $500.00. DONE and RECOMMENDED this 2nd day of August, 1988, in Tallahassee, Florida. MARY CLARK Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of August, 1988. COPIES FURNISHED: David E. Bryant, Esquire 220 East Madison Street, Suite 530 Tampa, Florida 33602 Kenneth R. Martin 3225 North Glenn Drive Orlando, Florida 32806 Fred Seely, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 William O'Neil, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 =================================================================

Florida Laws (3) 120.57455.225489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. THOMAS CHARLES HITCHENS, 84-003766 (1984)
Division of Administrative Hearings, Florida Number: 84-003766 Latest Update: Jul. 10, 1985

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following facts were found: At all times material to these proceedings Respondent was licensed by the State of Florida as a certified pool contractor, licensed No. CP C025535 and registered pool contractor, License No. RP 0041301. On June 7, 1983, Respondent entered into a Contract (Contract) with Edward and Maureen Kerstein (Kersteins) of 283 Islander Lane, Hudson, Florida, under which a pool was to be constructed on the Kersteins' property for a contract price of $7,777.00. The Contract was later amended by a letter, signed by Respondent and dated July 15, 1983, providing a penalty of $50.00 per day to be deducted from the balance due on the contract price if Respondent failed to complete the pool by July 23, 1983. Respondent obtained building permit No. 34342 on June 15, 1983, in the name of Crystal Clear Pool for the construction of the Kersteins' pool from the Pasco County Building Division. The pool steel inspection was called for and approved on July 8, 1983 and the pool bonding inspection was called for and approved on July 18, 1983. No other inspections were called for by the Respondent and the Respondent did not request an extension of time on the building permit. Therefore, on January 18, 1984, as required by the Standard Building Code of Pasco County, the permit lapsed and was invalid. However for reasons that are not clear in the record Vern Rossky, Building Inspector, Pasco County Building Division, made a final inspection of the Kersteins' pool (Permit No. 34342) on June 28, 1984 and approved the pool. Ordinarily the contractor would call for the final inspection or if the permit had lapsed or was invalid then the Pasco County Building Division would contact the contractor in order to finalize the permit. However, the record is clear that Respondent's intent was to leave the permit open due to the problems with completing the pool and satisfying the Kersteins. Although problems with the pool still existed, the pool was substantially completed in August, 1983 and the Kersteins used the pool in late summer 1983 (August) and the summer of 1984. The pool was operational in August of 1983. The respondent has received $7,055.05 for his work on the construction of the pool under the Contract with the Kersteins. While the Contract did not specify which side yard Respondent was to have access through for construction of the pool, the testimony of both the Respondent and the Kersteins was that it was the west side yard. However, the record reflects that the Kersteins gave either an expressed or implied approval for the use of the east side yard. All of the shrubbery, with the exception of the shrubbery that was part of the Contract, has been properly replaced and the clothesline has been replaced. The evidence was insufficient to show that the cracks which occurred in the house some 3-6 months after the pool construction was caused by the equipment being brought in on the east side of the house. Although Edward Kerstein's testimony was that an expert had not looked at the damage caused by the alleged water seepage around the electrical conduit pipe installed by the Respondent, his testimony that he had identified the Respondent's failure to caulk around the conduit pipe as the reason for the water seepage which resulted in damage to the carpet and speakers went unrebutted and was credible. However, Respondent was not made aware of this problem until the summer of 1984, almost a year later. The record is clear on the following: (a) that the tile placed around the top edge of the pool by Respondent was defective; (b) that there were several acceptable methods of replacing the defective tile; (c) that there were differences of opinion as to which method should be used in this situation; (d) that the reglazing over the existing tile was not an acceptable method; (e) that the pool would have to be drained to replace the defective tile; (f) that the Kersteins did not want to tile over the existing defective tile; (g) that the Respondent and Drew Tile Supply Company (Drew), the supplier of the defective tile, agreed on the method of cutting the tile away from the bull nose cap and replacing just the tile and based on this agreement; Drew delivered a check to Respondent in the sum of $823.75 ($700 for labor and $123.75 for tile) made payable to Crystal Clear Pools and Phil Klein, the subcontractor who had installed the defective tile; (h) that the Respondent, as President of Crystal Clear Pools assigned Crystal Clear Pools' interest in the check to Phil Klein provided the work on the defective tile in the Kersteins' pool commenced no later than February 1, 1984; (i) that Phil Klein endorsed and cashed the check with the knowledge of the assignment; and Phil Klein's testimony that even though the assignment was on the check at the time he endorsed and cashed the check the Respondent told him that the money was a partial payment of another job is just not credible; (j) the more credible evidence is that Respondent assigned the check to Phil Klein for labor and tile to replace the defective tile on the Kersteins' pool and there was no intent by Respondent to divert these funds to another job; (k) that the Kersteins' had not agreed to the method of replacing the defective tile which was part of the agreement between the Respondent and Drew; (1) that Drew had agreed that if the method selected was not satisfactory, then Drew would make it right; (m) that the problem with the drain in the pool, the filtering system, the telescoping rod, the damage to the air conditioning controls on the house, the failure to put tile chips on pool steps and the damage to the underground wire, were legitimate problems and it was Respondent's intent to correct all by the time the pool was drained to replace the defective tile; (n) that the Kersteins understood this when they agreed to allow Respondent to wait until the winter of 1984 to correct these problems because they were already using the pool in the latter part of the summer of 1983 and did not want to drain it at that time; (o) that none of these problems had been corrected due to the failure of both the Respondent and Drew to reach an agreement with the Kersteins on how both the defective tile problem and the other problems were to be resolved and; (p) that there had been continuous negotiations between either the Respondent and the Kersteins or Drew and the Kersteins concerning the settlement of this problem.

Recommendation Based upon the findings of fact and conclusions of law cited herein it is RECOMMENDED that the Board enter a final order finding the respondent not guilty of the violations charged in Count I, Count II, and Count III of the Administrative Complaint and that Counts I, Count II and Count III of the Administrative Complaint be DISMISSED. Respectfully submitted and entered this 10th day of July, 1985 in Tallahassee, Leon County, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 10th day of July, 1985. COPIES FURNISHED: Douglas A. Shropshire, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Gerald A. Figurski Post Office Box 786 New Port Richey, Florida 33552 Mr. James Linnan Executive Director Department of Professional Regulation Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Mr. Fred Roche Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Salvatore A. Carpino General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (3) 120.57455.227489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. WESLEY ASH, 86-002642 (1986)
Division of Administrative Hearings, Florida Number: 86-002642 Latest Update: Dec. 09, 1986

Findings Of Fact Respondent, Wesley Ash, currently holds license number CP C015871 issued by the Construction Industry Licensing Board to authorize Ash to engage in the pool contracting business. Dodd Complaint (Count I). Respondent, Wesley Ash, doing business as Wada Pools, Inc., contracted with Jerry Dodd on or about June 17, 1981, to build a pneumatic concrete pool with skimmer and recirculation system. The contract did not include installation of the concrete deck around the pool. Dodd decided to contract with another independent contractor to install the deck at a lower price than Ash wanted for the job. Ash completed his work by approximately August 1981. He installed the concrete pool shell, finished the inside surface and installed tile along the water line. He then attached the skimmer assembly, plumbing it so that it was level and attaching it to the concrete pool shell by means of the skimmer's PVC plumbing piping. After Ash finished his work, Dodd's other contractor came behind Ash. He used some of the dirt Ash had excavated from the pool site to raise the ground surrounding the pool by approximately six inches above grade. He then poured the concrete deck but failed to encase the skimmer assembly with the deck concrete in the process of pouring the concrete deck. It was not Ash's practice to make any special arrangements to stabilize the skimmer assembly when he installed both pool and concrete deck. He relies on the skimmer assembly plumbing to stabilize the skimmer assembly until the concrete deck is poured. In pouring the concrete deck, Ash encases the skimmer assembly with the deck concrete to stabilize the skimmer assembly and prevent leakage. In the case of the Poland pool (paragraphs 17 and 22, below), Ash used this method to install both the pool and the concrete deck, and Poland has had no complaint of leakage at the skimmer (nor was there any evidence of leakage at the skimmer). In the case of the Priests' pool (paragraphs 11 through 13, below), Ash followed the same procedures as he did with the Dodd pool, and another contractor poured the concrete deck. As with the Poland pool, there have been no complaints (nor was there any evidence) of leakage at the skimmer. Within approximately one and one-half years after installation of the Dodd pool, Dodd began to notice what he thinks is a leak in his pool. The water level in the Dodd pool drops approximately one-quarter inch per day. But the Department's own expert witness conceded that water loss of between one-eight and one-quarter inch can be explained by evaporation. It was not proved that the Dodd pool is leaking at all. If there is a leak causing a small increment of water loss above loss through normal evaporation, the leak would have to be very small and would be very difficult to detect. Ash and others have tried but have been unable to find a leak at the skimmer of Dodd pool. In approximately summer 1985, Dodd himself dug a hole under the concrete deck to expose the bottom of the skimmer assembly. The excavation revealed an unusual amount of moisture that might be the result of a leak at the skimmer. It also revealed that the contractor who poured the Dodd concrete deck did not encase the skimmer assembly as Ash had thought he would. The Department's expert - a professional engineer with a B.S. degree in civil engineering, an M.S. degree in structural engineering and a Ph.D. degree in environmental engineering - gave his opinion that a residential pool skimmer assembly should be either (1) encased with the concrete of the pool shell or (2) encased with deck concrete which is structurally tied to the concrete pool shell. He opined that the latter method would require either a very rough surface on the pool shell concrete or steel extending from the pool shell in order for the structural tie to be accomplished. But he also conceded that it is possible for deck concrete encasing a skimmer assembly to be sufficient to stabilize the skimmer assembly even without taking any extra measures to accomplish a structural tie. There was no evidence that any building code would require a pool contractor to take these measures to accomplish a structural tie between the pool shell and skimmer assembly. Nor was there any evidence that a reasonably prudent pool contractor (as opposed to a professional engineer) would be expected to take these measures. Based on this evidence, together with all the other evidence taken as a whole, the Department did not prove that Ash was either incompetent or grossly negligent in not taking any extra measurers to accomplish a structural tie between the concrete pool shell and the skimmer assembly. Based on the evidence in this case, the contractor Dodd hired to pour the concrete deck was either incompetent or grossly negligent (assuming he was even a licensed pool contractor a fact not shown by the evidence.) He did not encase the skimmer assembly with the deck concrete, allowing it to "float" unprotected in the fill under the concrete deck. Settling of the fill could have caused the deck to settle and crack, moving the skimmer assembly and causing a small leak. Ash may have been able to prevent this by warning the contractor to be sure to encase the skimmer assembly with deck concrete when he poured the concrete deck. But there was no evidence that Ash had a duty to advise the other independent contractor Dodd hired or was responsible for the other contractor's incompetence or gross negligence. Ash's failure to advise the other contractor was not incompetence or gross negligence on Ash's part. Dodd has no other complaints about the pool Ash built for him. Priests' Complaint (Count II). On or about October 11, 1984, Ash contracted with Joseph and Rita Priest to build them a pneumatic concrete pool. The Contract included a warranty that the labor, materials and workmanship would be free of defects for one year and that the shell would be structural sound and capable of holding the water for ten years. Like Dodd, the Priests contracted with another independent contractor to install the concrete deck around the pool. Ash was responsible only for placement of decorative "river rock" on top of the deck. Ash finished his work in February 1985. Like Dodd, the Priests complained of water loss from the pool although the Priests noticed the water loss sooner than Dodd (approximately March, 1985). The water level was dropping approximately one-quarter inch per day more than it was dropping in a bucket used as a control. In response to the complaint, Ash sent his employees to the Priests' pool on several occasions. They found no leak at the skimmer. To determine whether the pool's "caretaker system" 1/ was leaking, Ash's employees plugged all but one pair of the caretaker heads. After waiting a period of days, they would try to see whether the rate of water loss changed. They tested all four pairs of caretaker heads on the bottom of the pool and the pair in the spa attached to the pool. No leaks could be found. They did not replace the last two (in the spa), and Mr. Priest had to replace them. As with the Dodd pool, the Department did not prove that the Priests' pool is leaking at all. The Priests continue to complain of water loss of approximately one-quarter inch per day, within the range of water loss from normal evaporation. As with the Dodd pool, a leak responsible for a small increment of water loss above water loss from normal evaporation would be very small and difficult to find, especially if the leak were in the caretaker heads or pipes under the pool leading to the heads. Now the Priests suspect a water leak at the filter. But the Department's expert witness could not find a leak there large enough to account for much water loss. The minor leak at the filter is a normal maintenance item for a pool as old as the Priests' pool. There was no evidence how long it has existed, and there was no evidence that the Priests ever told Ash there was a leak at the filter. The Priests now also complain that one of the caretaker heads does not re-seat properly. But this has nothing to do with the leakage complaint to which Ash is charged with not reasonably responding. Taken as a whole, the evidence did not prove that Ash committed misconduct or deceit by failing to make reasonable response to warranty service requests within a reasonable time, as charged. Nor does the evidence prove misleading or untrue representations, gross negligence, incompetence or fraud in connection with the Priests' pool, as charged. Poland Complaint (Count III). On or about December 9, 1981, Ash entered into a contract with James Poland to build Poland a pneumatic concrete pool and concrete deck. Poland contracted with another independent contractor to build a screen enclosure around the pool. Before construction began, one of Ash's employees asked Poland to sign an addendum to the contract for an additional $235 to pay for foundation footers required to comply with Lee County building code provisions for the screen enclosures. Before Ash signed the initial Poland contract on December 9, 1981, he was unaware of the Lee County Aluminum Code, adopted March 18, 1981. The code requires eight inch foundation footers for "aluminum additions." Another part of the code addresses "screen enclosures with screen roofs known to the industry as birdcage swimming pool enclosures." The language of the code is not explicit that screen swimming pool enclosures are required to meet the foundation requirements for "aluminum additions," and at first Lee County did not interpret the code that way. With a change of personnel in code enforcement, Lee County began to interpret the code that way, and screen swimming pool enclosures Ash had under construction began to fail building inspection for inadequate foundation footers. Ash inquired why and was told about the aluminum code and how it was being interpreted. Ash argued that the interpretation was erroneous but, failing to dissuade enforcement personnel, began to comply. As part of his compliance efforts, Ash had his employees try to secure the contract addendum from Poland. Poland refused to sign the contract addendum, insisting on an opportunity to verify that the additional foundation footers were indeed new building code requirements. There still is a dispute between the parties whether Poland ever agreed to pay the additional $235 after he verified that the footers were being required. (He never signed the contract addendum.) But, in any event, the evidence did not prove that Ash was incompetent, grossly negligent, deceitful or guilty of fraud or misconduct in connection with the additional $235 charge. 2/ There was some evidence that Ash did not in fact comply with the Lee County Aluminum Code, as he was told it was being interpreted, in his construction of the Poland pool deck. In two places the foundation footers were 6 and 7 inches - deeper than the four-inch normal thickness of a concrete pool deck but short of the eight-inch requirement. But Ash was not charged with failure to comply with the foundation footer requirement. He had no legally sufficient notice that he should be prepared to defend against that charge and was not prepared to defend against that charge. Therefore, no finding is made whether Ash complied with the Lee County Aluminum Code. Ash performed the Poland contract between approximately January 27 and February 26, 1982. In September, 1985, Poland began to notice that some of the tile Ash installed at the waterline around the perimeter of the pool was coming loose. As explained by the Department's expert witness, the concrete deck settled in places, cracking slightly and rotating over the fulcrum created by the wall of the concrete shell of the pool. The rotating action pulled up on the tile attached to the inside of the pool wall in places, loosening the tile. In all, less than 10 percent of the 77 foot perimeter of the Poland pool experienced problems with loose tile. The loose tile easily can be removed and replaced. The minor deck cracking and loose tile problems at the Poland pool are within the normal range for a competently constructed pool under normal conditions of ground settlement. The evidence did not prove that Ash improperly installed the pool deck or that he was incompetent or grossly negligent in the construction of the Poland pool and deck. Besides the loose tile and minor cracks in the concrete deck, the Poland pool had no apparent defects. There also was evidence that the Poland pool was finished with a coating of marcite on the inside surface of the pool shell which was mottled gray in color instead of white. Poland complained persistently about the marcite3 and insisted that Ash make it white. But the discolored marcite was a factory defect of which Ash had been unable to know before he used it. There is no way to make mottled gray marcite white. Ash tried to explain this to Poland but the customer would not be satisfied. Taken as a whole, the marcite evidence did not prove that Ash was incompetent, grossly negligent, deceitful or guilty of fraud or misconduct. Nor does the evidence prove any of those violations for failure to cure the marcite problem under warranty. First, as already stated, there was no cure. Second, Ash and Poland also had a running dispute whether Poland had paid the full contract price, including the additional $235 for foundation footers, so as to entitle him to any warranty repairs. In light of this genuine dispute, failure to do warranty work, if otherwise a reasonable request, still could not be found to be misconduct, fraud or deceit.

Recommendation Based on the foregoing Findings Of Fact and Conclusions Of Law, it is recommended that the Construction Industry Licensing Board enter a final order dismissing the Amended Administrative Complaint that has been filed against Respondent, Wesley Ash, in these cases. DONE AND ORDERED this 9th day of December 1986, in Tallahassee, Leon County, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of December, 1986.

Florida Laws (3) 455.227489.105489.129
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. GEORGE W. BOUKATER, 85-002538 (1985)
Division of Administrative Hearings, Florida Number: 85-002538 Latest Update: Jan. 31, 1986

Findings Of Fact At all times material hereto Respondent, George W. Boukater, was a certified general contractor, license number CG C012598, and a registered pool contractor, license number RP 0032042. Respondent was the qualifier for Swimming Pools by M.J. Donohue, Inc. (Donohue), under license number RP 0032042, from February 1979 until June 30, 1985. On July 29, 1984 Donohue contracted to construct a swimming pool at the residence of Ms. Loretta Hunley in Fort Lauderdale, Florida, for the sum of $6,400.00. Respondent, on behalf of Donohue, applied for and received the building and plumbing permits for the pool. Apart from securing the permits, Respondent had no contact with the job and never inspected its progress. By August 30, 1984, Donohue had substantially completed the pool. All that remained to be done was to marcite the pool, hook up the pool light and plumbing, and install the pumps. However, before these items could be completed it was necessary that the area surrounding the pool be backfilled, the patio poured, and the electric installed. Under the July 29, 1984 contract Ms. Hunley did not contract with Donohue for any patio, electric or fence work. She expressly retained responsibility for that work in an effort to save money on the pool construction. The area surrounding the pool was not backfilled and the patio slab approved by the Broward County Building and Zoning Department (County) until September 14, 1984. As of September 5, 1985, the fence work was still in violation of the County code. The electric work received the County's final approval on January 8, 1986. In October 1984 demands were exchanged between Ms. Hunley and Donohue. Ms. Hunley demanded that the pool be completed. Donohue demanded adequate electrical service so the pool could be pumped and cleaned for marciting, and dates when someone would be available at the premises. In November 1984 Donohue got its pumps in operation, however Ms. Hunley disconnected them in the evenings. Consequently, the pool could not be drained and cleaned to marcite it. In November 1984 Ms. Hunley ejected Donohue from the job site. Subsequently, Ms. Hunley and Donohue formally settled their dispute.

Florida Laws (2) 120.57489.129
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. THEODORE A. DYSART, 82-000720 (1982)
Division of Administrative Hearings, Florida Number: 82-000720 Latest Update: Dec. 04, 1990

Findings Of Fact Respondent is a licensed general contractor and pool contractor. He is employed by Sally Dysart, Inc., and is currently the qualifying contractor for that company. Additionally, Respondent has served as qualifier for ARK Swimming Pool Service, Inc. On June 6, 1981, Sally Dysart, Inc., contracted with Theresa Pica to construct a swimming pool at her North Lauderdale residence. On June 9, 1981, Respondent obtained a permit from the City of North Lauderdale to construct the Pica pool. The permit indicated that ARK Swimming Pool Service, Inc., was the contractor. The contract specified that the pool would measure 16 x 32 x 3 x 6 1/2 feet, with stainless steel walls. The contract allowed "minor variations in dimensions . . ." and provided that, "Dysart is authorized to use its discretion in making changes or additions if the customer is not immediately available." The pool as installed was 8 feet rather than 6 1/2 feet deep, and the walls were of aluminum rather than stainless steel. These changes were not approved by Theresa Pica and she complained to Petitioner regarding these changes and other problems which are not relevant to the charges herein. This was an 18 inch change in pool depth and could not be considered a minor variation in dimensions, nor could the change in materials be considered insignificant. Respondent should have, but did not, obtain the owner's concurrence before substituting the 8 foot aluminum pool for the 6 1/2 foot steel pool, which the contract called for. This installation was also held to be in violation of Broward County Ordinance Section 9-14(b)(9), by the local board having jurisdiction. Respondent was not properly registered as the qualifying agent for Sally Dysart, Inc., at the time of this project. He was registered as the qualifier for Ark beginning in 1977, but his application to qualify Sally Dysart, Inc., was not received by Petitioner until November 1981 and not issued until December 1981. A Julius Kaplan was also a qualifier for Sally Dysart, Inc., but his application was not received by Petitioner until October 1981. Sally Dysart, Inc., was therefore not qualified by a licensed pool contractor at the time this company undertook the Pica project. The permit was improperly drawn on Ark Pool Service, Inc., by Respondent since Ark was not a party to the Pica contract. Respondent demonstrated that the administrator for Sally Dysart, Inc., was attempting to secure a qualifier for this company between April and December 1981. Thus, while some effort had been made to qualify Sally Dysart, Inc., this had not been accomplished at the time the Pica project was undertaken. Sally Dysart, Inc., contracted with James J. Mirrione to install a spa for him at his residence in Boca Raton. The permit was obtained by Respondent on behalf of Sally Dysart, Inc., on April 23, 1981. As noted above, Respondent was not a qualifier for Sally Dysart until December 1981. No final inspection of the Mirrione installation was ever made. Respondent believed that officer personnel at Sally Dysart, Inc., had arranged for such inspection, but it was either not requested or requested but not performed. On June 25, 1981, Warren Schober contracted with Sally Dysart, Inc., to construct a pool at his Miami residence. He negotiated the contract with a Milton Wolf who he understood to be the sales manager for Sally Dysart, Inc. The project was completed, but Schober encountered problems with a defective light and leaks in the pool. The difficulties were eventually corrected and Schober is now satisfied with the installation. In late August 1981, Milton Wolf agreed to sell Dr. Ronald Scott a swimming pool for $5,970. Scott made an initial payment of $3,970 to Milton Wolf by cashier's check dated September 8, 1981. Scott believed he was dealing with Sally Dysart, Inc., since Wolf held himself out as a representative of that company. Although he had some reservations about making the check payable to Milton Wolf personally, he had contacted a Better Business Bureau to determine that Sally Dysart, Inc., was a reputable company. Further, Wolf was available when he telephoned him at the Sally Dysart, Inc., offices. Sally Dysart, Inc., later disclaimed the Wolf agreement but offered to honor it if Scott would turn over the balance due. However, Scott rejected this offer and it was later withdrawn. He did not receive the pool or return of his initial payment. The evidence did not establish whether or not Sally Dysart, Inc., approved the contract for sale of the pool negotiated by Wolf. However, there was no construction contemplated and therefore no active involvement by Respondent in his capacity as construction supervisor. On July 31, 1981, Milton Wolf, on behalf of Sally Dysart, Inc., contracted with Mr. William D. Black for the sale and installation of a swimming pool at the latter's Miami resident. By check dated August 28, 1981, Black made an initial payment of $4,585 to Wolf. Black left the payee portion of the check blank at Wolf's request on the representation that he would use a stamp to supply the Dysart firm name. Wolf later filled in his own name, cashed the check and absconded. Black had no reason to distrust Wolf as he had communicated with Wolf at Sally Dysart, Inc., and had checked on the company through the Better Business Bureau. Wolf held himself out as sales manager and this was not repudiated by Sally Dysart, Inc., until after Wolf absconded. Respondent obtained a permit for the Black project on October 13, 1981, and some of the initial approvals were made. However, by letter dated September 22, 1981, Sally Dysart, Inc. (by its president, Sally Dysart), advised Black that the company would attempt to complete the project only if he would pay the balance of all payments due. This letter also disclaimed responsibility for Wolf's representations. In response, Black demanded that Sally Dysart, Inc., honor the contract and proposed that remaining payments be placed in escrow pending satisfactory completion. This proposal was rejected, and Black did not obtain the pool nor was his $4,585 "deposit" returned. Respondent sought to establish that Milton Wolf was not authorized to act on behalf of Sally Dysart, Inc., but that he was merely present in the Dysart offices as a potential business partner. His contact with customers was purportedly limited to investigation of leads and company business potential. However, the testimony of a former Dysart employee established that Wolf did make sales and brought in cash receipts to the company prior to his defalcation. Therefore, regardless of any private understanding between Sally Dysart, Inc., and Milton Wolf, the latter was holding himself out to the public as a company representative with the knowledge and approval of Sally Dysart, Inc.

Recommendation Based on the foregoing, it is RECOMMENDED that Petitioner enter a Final Order suspending Respondent's contractor licenses for a period of ninety (90) days. DONE AND ENTERED this 16th day of May, 1984, in Tallahassee, Florida. R. T. CARPENTER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 16th day of May 1984.

Florida Laws (2) 489.119489.129
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs MERWIN C. CARTER, 91-005266 (1991)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Aug. 21, 1991 Number: 91-005266 Latest Update: Apr. 16, 1992

Findings Of Fact Respondent is a certified pool contractor, holding license number CP CO27486. Respondent obtained his certificate in October, 1983. His only prior discipline consists of a letter of guidance in late 1989 or early 1990. At all material times, Respondent was qualifying agent for Gold Medallion Pcol, Inc. On March 27, 1986, Respondent and Mr. and Mrs. Don Burson entered into a contract for the construction cf a swimming pool at the Bursons' residence. The Bursons had purchased the residence while it was still under construction in May or June, 1985. The lot was low and had required fill. Clearly visible behind the lot is a large marshy wetland. The contract called for the Bursons to pay $16,315 for the construction of a 20' by 40' concrete lap pool with depths of 3' at either end and 6' in the center. Paragraph 4 of the contract provides: The Owner is responsible for increased costs incurred by the Contractor due to underground conditions which may be encountered during construction, such as but not limited to, muck, inadequate soil-bearing capacity, and excessive ground water. The Contractor, upon encountering such conditions, shall notify the Owner of their existence and give him an approximate cost estimate to rectify the problem. The Owner shall have five (5) days from the receipt of the approximate cost estimate to instruct the Contractor not to proceed with the pool. . . . If the Contractor determines that additional testing is required prior to furnishing approximate costs estimates to determine the exact nature or extent of the underground condition encountered, the Owner shall be responsible for the cost of all testing and/or engineering required by the Contractor. Paragraph 8.D states that the Owner warrants that there [is] no . . . mock . . . in that portion of the owner's property which the contractor will construct the pool [and] decking . . .. The owner is responsible for the removal, repair or replacement of any underground conditions . . . encountered during construction unless he elects to terminate the contract and pay damages to the contractor as set forth in the clause on underground conditions. Paragraph 11.A provides: Contractor warrants to the original owner for the lifetime of the original purchaser, the swimming pool structure, the shell, will not leak due to cracking. . . . This Limited Structural Warranty does not cover damage to the pool shell caused by fluctuations of the water table, construction in the vicinity of the pool site, or natural phenomenon. . . . The contractor's responsibility under this Limited Structural Warranty shall be to repair the shell so that it holds water without cost to the original owner. . . . The method of repair shall be at the discretion of the contractor. THE CONTRACTOR MAKES NO OTHER EXPRESS OR IMPLIED WARRANTIES INCLUDING THE WARRANTY OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE IN REGARDS TO THE POOL STRUCTURE, THE SHELL. Paragraph 11.B.2, which further describes the limited warranty, states: It is anticipated the concrete deck and deck coatings may crack due to settling of deck or weather. Cracks one-quarter inch or less with no substantial deviation in elevation are not covered. . . . The plot plan, which is part of the contract, shows the pool located on the east side of the house. The pool is oriented in a north-south direction. The southern end of the pool runs toward the back of the lot, which is on a steep slope. The southern end of the pool adjoins the widest section of decking, which Respondent constructed at the time of the construction of the pool. The plot plan also shows that excavated dirt was to be placed just south of the decking on the south end of the pool. Shortly after pulling a building permit from the Seminole County Building Department on March 27, 1986, Respondent began construction of the pool. The actual construction was performed by Mid-Florida Pool Company, which is a major pool construction company in Central Florida. Construction was completed on April 23, 1986, and the Bursons paid the amount required under the contract. Prior to commencement of construction of the pool, this area of the Bursons' lot had been filled with about 2 1/2 to 3 feet of dirt. In order to construct the pool, Respondent or his subcontractors added another 2 1/2 to 3 feet of fill, at least to the southern end of site of the pool and decking. It is at this point that the land begins to slope most steeply toward the marsh in the back. Neither Respondent nor any of his subcontractors conducted any soil tests prior to commencing construction or compressed or compacted the soil beneath the pool prior to installing the shell. This omission constitutes a departure from sound contracting practices under the facts cf this case. Respondent constructed several pilasters under the southern end of the deck, but these structural supports were designed to support the deck, not the pool. In general, the depth of the excavation had to exceed the depth of the pool by one foot in order to accommodate the shell. Thus, the extreme southern end of the shell required a hole only about four feet deep. An excavation of this depth did not exceed the combined depth of the old and new fill. There is no indication that Respondent or his subcontractors encountered muck during the excavation or construction of the pool. Likewise, there is no indication that Respondent or any of subcontractors was aware that mucky, unstable soils underlaid the location of the pool, especially the southern end. The pool was completed to the initial satisfaction of the Bursons. However, within 90 days of completion, the southern half of the shell developed five or six major cracks as a result of the settlement of the southern end of the pool. This portion of the pool settled because the underlying muck had been compressed by the weight of the shell and water. Gradually, the water loss from the settlement cracks, which were mostly below the waterline, became significant. At Respondent's suggestion, the Bursons agreed to wait through the winter before commencing repairs in order to allow the cracking to stabilize. In the spring of 1987, the Bursons drained the pool at Respondent's direction. Respondent then scored the cracks with a screwdriver and applied a filling compound in order to seal any leaks. As directed by Respondent, the Bursons then refilled the pool, but before more than two feet of water had been added, the filling compound fell out of the cracks. When the Bursons informed Respondent of the failure of the repair, he responded that he had performed under the contract and had no further obligation. The Bursons exercised their right to arbitrate, as provided in the contract. The arbitrators conducted a limited investigation. Expressly noting that they were not soil engineers and thus could not determine why the soil under the pool failed to support the shell, the arbitrators determined that the contractor was not responsible for any damage to the pool, "which was built to industry standards." The Bursons next contacted various pool contractors about repair options. Most of the contractors suggested a V-cut about 2 1/2 inches deep followed by the injection of hydraulic cement. When the Bursbns informed Respondent that this type of repair appeared necessary, he refused to undertake such work. By this time, one of the contractors documented that five of the cracks, which ranged from 1/16" to 1/4" wide, were pulling water out of the pool at a rate of 1-3" daily. This contractor charged the Bursons $125 for his services. After contacting the Seminole County Building Department, the Bursons learned that the pool had never passed a final inspection. When they had an inspector visit the site on September 13, 1991, he failed the job due to, among ether things, "massive deck cracks." At the insistence of Seminole County officials, the Bursons obtained expert opinions as to the cause of the cracks in preparation for the local hearing on the Bursons' charges against Respondent. In July, 1990, the American Testing Laboratories, Inc. conducted tests and opined that the south end of the pool had settled due to muck at a level of five feet below the bottom of the shell. Additional testing found muck at depths of 3-7 feet at two points just east of the south end of the pool. These tests cost the Bursons $498. When the Seminole County officials insisted upon further testing, the Bursons hired Jammal & Associates, Inc., which performed soil borings on August 23, 1990. The boring sites were just east of a point about midway along the southern half of the pool and a point just south of the southern end of the pool. The latter boring site revealed muck after penetrating about six feet of fill. At the request of Respondent, a Jammal employee returned to the site on November 13, 1990, to determine the potential cause of the cracking of the pool shell and deck. Jammal concluded that the cracking is the result of consolidation of the highly compressible peat layer found in the [southern] boring. Based upon the [cracking] observed, we suspect the southern 1/3 or so of the pool and deck area are underlain by the buried peat layer. The remainder of the pool and deck are most likely underlain by sandy soils. Because of the nature of the buried organic soils, the pool and deck will probably continue to settle at a diminishing rate for several years. Addition of new loads such as placement of additional fill around the pool and deck area, or a significant drop in the groundwater table could cause additional and accelerated settlement of the pool and deck. Jammal offered three repair options. The first was to patch the cracks. Jammal assumed that, although continued cracking could be expected, it would occur at a lesser rate because most of the settlement of the buried muck had already taken place. The second option was to remove the pool and then remove the underlying muck. The third option was to install inside the shell a fiberglass liner. The last option had been first suggested by Respondent. If not rigidly attached to the shell, the liner probably would not reflect further cracking of the shell. The Bursons paid Jammal the sum of $300 for its services. Ultimately, the Bursons decided to install a fiberglass liner and entered into a contract on November 19, 1990, with Fibre Tech for the work. The total cost of the project was $5415. This cost excludes the cost of replacing a pool vacuum for which Respondent does not appear responsible. The liner was later installed, and the Bursons paid the contract price. In the meantime, at a meeting on October 16, 1990, the Seminole County Swimming Pool Contractor's Board revoked Respondent's County certificate of competency until he repaired the pool or made restitution to the owners. This action was based upon a violation of Seminole County Code Section 40.151 and 40.34(2) and (9). Section 40.151 provides that "[a]11 completed pools shall be absolutely watertight." Section 40.34(a) allows the Board to revoke a certificate of competency if the contractor: (2) Continue[s] performance of building work in a negligent, incompetent or unworkmanlike manner. (9) Violate[s] any provision of this Chapter. The determination of the Seminole County Swimming Pool Board became final when Respondent failed to take a timely appeal of the order.

Recommendation Based on the foregoing, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a final order imposing an administrative fine of $2500 and suspending Respondent's license until he makes restitution to the Bursons in the amount of $6338. ENTERED this 29th day of October, 1991, in Tallahassee, Florida. ROBERT E. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of October, 1991. COPIES FURNISHED: Jack McCray, General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Daniel O'Brien Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Craig M. Dickinson, Senior Attorney Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Merwin C. Carter, pro se 611 Ensenada Avenue Orlando, FL 32825

Florida Laws (5) 120.5717.00140.34474.214489.129
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. CRAIG G. ROBERTS, 82-000686 (1982)
Division of Administrative Hearings, Florida Number: 82-000686 Latest Update: Aug. 10, 1983

The Issue The issues to be resolved in this proceeding are whether the Respondent has committed violations of provisions of law relating to the licensing of construction contractors and, if so, what disciplinary action should be taken against him.

Findings Of Fact The Respondent is registered by the Florida Construction Industry Licensing Board as a residential swimming pool contractor. The Respondent holds licenses numbered RP A027187 and RP 0027187 issued by the Board. During 1979 and 1980, the Respondent was registered with the Construction Industry Licensing Board as the licensed qualifier for "Cowboy Pools, Inc." Cowboy Pools, Inc., was owned by Jim Anglin. During December, 1980, the Respondent and Anglin experienced difficulties in their business relationship. The difficulties resulted from Anglin's failure to pay for work performed for Cowboy Pools by subcontractors and by Anglin's issuing checks to the Respondent which were not honored by the bank. In early January, 1981, Respondent became concerned that he was unable to control the flow of money at Cowboy Pools. He advised Anglin that he would no longer serve as the qualifier for Cowboy Pools. On January 8, 1981, the Respondent called the office of the Construction Industry Licensing Board and inquired as to steps that he needed to take to withdraw as the qualifier for Cowboy Pools. On that same date, he wrote a letter to the Board stating: This is to inform you that I am no longer associated with Cowboy Pools and will assume no responsibilities whatsoever for Cowboy Pools. The Respondent wrote that same letter to all persons that he knew had contracts with Cowboy Pools. The letter was received in the Department of Professional Regulation offices on January 12, 1981. At the Department's request, the Respondent forwarded proper forms to withdraw his qualification of Cowboy Pools. In his letter, he stated: I hereby certify that I have not been able to bind the construction moneys for Cowboy Pools and saw no hope that I would be allowed to do so in the future. Therefore 1 have withdrawn my association from Cowboy Pools as I have previously notified you. This letter was received in the offices of the Department of Professional Regulation on January 22, 1981. The Department requested that Respondent send the Board his qualifying licenses, which he did on January 28, 1981. The licenses were received in the Department's offices on February 2, 1981. On approximately January 14, 1981, Anglin asked the Respondent to obtain a permit so that Cowboy Pools could construct another swimming pool. Anglin was apparently unable to obtain permits on his own behalf. The Respondent refused to obtain such a permit and has had no business dealings with Cowboy Pools since January 8, 1981. Anglin continues to owe money to the Respondent. During 1980 and 1981, Mr. and Mrs. Robert Mosca owned a residence in Longwood, Florida. On December 26, 1980, they entered into a contract with Cowboy Pools, Inc., to construct a swimming pool at their residence for a sum of $6,800. The contract was negotiated on behalf of Cowboy Pools by Jim Anglin. Anglin signed the contract for Cowboy Pools. The Moscas paid Anglin a $100 deposit on December 26. By checks dated January 5, 1981, and January 21, 1981, the Moscas paid Cowboy Pools and Anglin an additional $4,736 on the contract. On December 27, 1980, Anglin had the pool area at the Moscas' property staked off. Nothing was done for several weeks, and the Moscas contacted Anglin, who advised them that a permit would be obtained soon. On January 14, 1981, a permit was obtained, and a crew from a company known as "Virgil Brothers" dug the hole for the pool and put in wire. Officials from Seminole County inspected that work on January 20. The following day, a crew from Virgil Brothers gunited the pool. There was a pile of dirt left from the dig. The Moscas asked Anglin about it, and he advised that it would be leveled. Approximately a week later, that was done, but no further work was done on the pool. The Moscas were not aware that there were any difficulties with completion of the pool until January 30, when a man visited their house and asked if they knew where Anglin might be. The man indicated that Anglin had left town. The same day, the Moscas received a notice from Virgil Brothers indicating that they had not been paid by Cowboy Pools. The Moscas went to the Cowboy Pools office that evening. All of the furniture had been removed. They were told by a secretary where Anglin lived. They went to his house and discovered that it was a rental house that had been vacated a couple of days before. Anglin has apparently not been seen in the central Florida area since that time. The Moscas ultimately had their pool completed by another contractor. It cost them $2,600 above the contract price to complete the pool. The building permit for the Moscas' swimming pool was obtained by Kelly Slusher, a registered swimming pool contractor. Slusher did not supervise the work and apparently, in effect, allowed Cowboy Pools to use his contractor's license to obtain the permit. Slusher did not become the qualifier for Cowboy Pools and was apparently not involved in the operation except to obtain the permit to construct the Moscas' swimming pool. Slusher has been the subject of disciplinary action initiated by the Construction Industry Licensing Board. When work on the Moscas' swimming pool was abandoned, the Moscas obtained a copy of the building permit and learned that Slusher had obtained the permit. When they contacted Slusher, he disclaimed any responsibility. The Respondent was not, until sometime in February, 1981, aware that Anglin had contracted with the Moscas to construct a swimming pool. Anglin did not tell him of the contract and was not allowing Respondent access to the company's records and books. The Respondent made a good-faith effort to advise all persons that were doing business with Cowboy Pools that he was no longer associated with the company. He wrote to all of the persons who had contracts with Cowboy Pools on January 8, 1981. He was not aware of the Mosca contract, and so he did not write to them. The Respondent did not obtain the building permit for the Moscas' swimming pool. He was asked by Anglin to obtain a permit, but refused. If Slusher had not agreed improperly to obtain a building permit for the Moscas' swimming pool, Cowboy Pools would not have been able to commence construction on the pool, and the Moscas would not have made payments to Cowboy Pools beyond the $100 deposit. The Moscas did not learn that the Respondent had any connection with Cowboy pools until sometime in February, 1981. The Moscas learned through other persons who had contracted with Cowboy Pools that the Respondent was the qualifying registered swimming pool contractor. The Moscas did contact the Respondent about the abandoned work, but it does not appear that they formally demanded that he complete the work on behalf of Cowboy Pools. No evidence was offered at the hearing from which it could be concluded that the Respondent diverted any funds in connection with the construction of the Moscas swimming pool. Indeed, it appears that he was totally uninvolved with the project.

Florida Laws (2) 120.57489.129
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. EDWARD G. BATTER, D/B/A TROPICANA POOLS, INC., 79-001938 (1979)
Division of Administrative Hearings, Florida Number: 79-001938 Latest Update: Apr. 30, 1980

The Issue The issues posed for decision herein are whether or not the certified pool contractor's license issued to Respondents Licensee, Edward G. Batter, should be revoked or suspended or the Licensee's right to practice thereunder should be withdrawn based on conduct which will be set forth hereinafter in detail as set out in the Administrative Complaint filed herein on August 23, 1979.

Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, the arguments of counsel and the entire record compiled herein, the following relevant facts are found. Edward G. Batter, d/b/a Tropicana Pools, Inc., (Respondent or Licensee) is a certified pool contractor who holds license No. CPC 012906. Respondent was first licensed on July 28, 1978, as qualifier of Tropicana Pools, Inc., which license was temporarily suspended in June, 1979, and remains in an invalid status to this date. By its Administrative Complaint, Petitioner's Executive Director took action to revoke or otherwise suspend the Respondent's rights to practice pursuant to his referenced license. As a licensed pool contractor, Respondent is subject to the Board's rules and regulations. (See Petitioner's Composite Exhibit 1.) A special meeting of the Board of Adjustment, Appeals and Examiners for general building contractors for Hillsborough County was held on Thursday, July 19, 1979, for the purpose of hearing certain allegations concerning the demise of Tropicana pools, Inc. Jerry Taylor, Petitioner's field investigator, presented the Hillsborough County Board with the results of an investigation of Respondent and presented several cases wherein funds were diverted after being collected for a specific contract to other projects or for other purposes and that projects for which funds had been collected had either been left unstarted or abandoned at the time Tropicana Pools, Inc., ceased doing business. At that meeting, the Respondent's construction activities were suspended by the Board until restitution or settlement was made and verified by affected parties. The temporary suspension by Hillsborough County became final during August of 1979. (Petitioner's Exhibits 2 and 3.) Howard Shaw, Director of Building and Zoning for the City of Tampa, appeared and testified to substantiate the disciplinary action taken against the Respondent by Hillsborough County during the summer of 1979. On June 7, 1979, Mr. and Mrs. James R. Stanton entered into a contract with Respondent to have a pool constructed for a price of $8,182.00. Respondent was paid a 10 percent deposit to commence construction of the Stantons' pool. Respondent absconded with the deposit and never notified the Stantons that their pool would not be built nor did Respondent return their deposit. (See Petitioner's Exhibits 4 and 5.) On April 19, 1979, Mr. and Mrs. Theodore Hillary entered into a contract for the construction of a swimming pool for a contract price of $8,130.00. Approximately $5,690.00 or approximately 70 percent of the contract sum was paid on June 18, 1979, and the work ceased on the Hillary project at a completion stage of approximately 40 percent. Respondent abandoned the Hillary project on approximately June 5, 1979. The Hillarys completed their pool at a price of approximately $5,000.00 over and above the contracted price. (Petitioner's Composite Exhibit 6.) On April 30, 1979, Mr. and Mrs. Leon Tope entered into a contract for the construction of a swimming pool at their residence for the contract price of $8,050.00. On June 18, 1979, the Topes had tendered to Respondent approximately 70 percent of the contract cost while the Respondent abandoned the construction of the Topes' pool after approximately 40 percent of the work was complete. Respondent abandoned the project on June 18, 1979, and the Topes completed the construction of their pool at a price of approximately $2,000.00 by engaging the services of other contractors in the area. (See Petitioner's Exhibits 7, 8, 9, 10, and the testimony of Jim Moran.) Jerry Taylor, Petitioner's field investigator, attended the probable cause hearing during August of 1979 in which the Hillsborough County Board of Examiners suspended the pool license of Respondent. Investigator Taylor briefed the Hillsborough County Board respecting the results of the investigation conducted by Petitioner.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Respondent's pool contractor's license No. CPC 012906 be REVOKED. ENTERED this 10th day of March, 1980, in Tallahassee, Florida. JAMES E. BRADWELL, Hearing Officer Division of Administrative Hearings 101 Collins Building Tallahassee, Florida 32301 (904) 488-9675

Florida Laws (1) 120.57
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. TERRY W. MALICKI, 82-002586 (1982)
Division of Administrative Hearings, Florida Number: 82-002586 Latest Update: Oct. 17, 1983

Findings Of Fact At all material times hereto, Respondent was the holder of a registered swimming pool contractors license number RP 0035739. Respondent's license was issued in the name of Malicki Pools, Terry W. Malicki. In January, 1981, Gary Wieland entered into a contract with Patrick Barr d/b/a Pool and Spa World. Barr was to construct a pool for Weiland in Port Charlotte for $7,856.00. Barr had become known to Wieland as a builder of swimming pools through a neighbor. Barr stated to Wieland that he was a pool contractor. Wieland made all payments due under the contract to Barr. Petitioner's evidence established that the Wieland swimming pool required a building permit. On March 3, 1981, Terry Malicki d/b/a Malicki Pools obtained permit number 66970 to construct a pool at Wieland's residence in Port Charlotte. Wieland's testimony established that Malicki constructed the pool at his residence. However, all of his dealings were with Barr. Barr was not licensed as a swimming pool contractor in Charlotte County or in Florida, and was convicted in the Charlotte County court of acting as a contractor without being licensed. Mr. Robert Guariglia entered into a contract with Barr to construct a swimming pool for $9,500.00. The pool was to be constructed at Lot 17, Block 402, Subdivision 23 or 913 Cherry Chase, Port Charlotte, Florida. Petitioner's evidence established that the Guariglia pool required a building permit. On June 10, 1981, Terry Malicki d/b/a Malicki Pools obtained permit number 68962 to construct a pool at Lot 17, Block 402, Subdivision 23 or 913 Cherry Chase, Port Charlotte, Florida. Guariglia paid the first installment of his contract by check to Barr in the amount of $3,325.00. However, because the pool was not level, Guariglia told Barr or Malicki who was supervising the work that he wanted the pool redone or removed. The pool was later removed and Guariglia had to pay $1,400 to have his property restored. As noted above, Barr was not licensed as a swimming pool contractor in Charlotte County or in Florida, and was convicted of acting as a contractor without being licensed. However, the swimming pool constructed at the identified Guariglia residence required a building permit. On September 3, 1981, the Charlotte County Building Board suspended the certificate of competency of the Respondent until such time as he corrected all matters which were then pending before that Board. On November 5, 1981, the Charlotte County Building Board reinstated Malicki's license.

Recommendation In consideration of the foregoing, it is RECOMMENDED: That Petitioner enter a Final Order suspending the swimming pool contractor's license issued to Respondent for one (1) year. DONE and ENTERED this 22nd day of April, 1983, in Tallahassee, Florida. R. T. CARPENTER, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of April, 1983. COPIES FURNISHED: Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Terry W. Malicki c/o Malicki Pools 1788 S.W. Sicily Avenue Port Charlotte, Florida 33952 Stephen Schwartz, Esquire 680 Aaron Street, N.W. Port Charlotte, Florida 33952 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (1) 489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer