Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ROBERT MENSCHING, 88-003308 (1988)
Division of Administrative Hearings, Florida Number: 88-003308 Latest Update: Feb. 06, 1989

Findings Of Fact At all times material to these proceedings, the Respondent, ROBERT MENSCHING, was a certified residential building contractor in Florida, and held license number CR C020166. Mr. Mensching was the owner and qualifying agent for Robert Mensching Homes. On or about July 10, 1986, a written proposal was submitted by the Respondent to Mr. and Mrs. Mangiardi for the construction of a single family dwelling in Cape Coral, Florida. The construction price was $60,000.00, with an additional $500.00 for the purchase of the house plans. Mr. and Mrs. Mangiardi paid for the plans on the date of the proposal. Revisions to the proposal were submitted to the Mangiardis in September, 1986. The purchase price and the payment schedule remained the same. The proposal was accepted by the Mangiardis, and the down payment of $5,000.00 required by the contract to start construction, was given to the Respondent. Construction commenced in November 1986. By March 26, 1987, the Respondent had been paid $53,750.00 of the total construction contract price. This included the fourth draw on a five draw payment schedule. Only $6,250.00 remained to be paid by the purchasers for the last phase of construction. In April 1987, the Respondent informed Mr. Mangiardi that he would not complete the final phase of construction. The Respondent informed Mr. Mangiardi that he would pay him $5,000.00. An accounting was not given to the purchasers of the monies disbursed by the Respondent pursuant to the construction schedule. After the Respondent left the project, the Mangiardis were given notice of an outstanding lien in the amount of $963.80, which was owed to Kirkland Electric, Inc. Another Notice to Owner was filed by Wallcrafters, another subcontractor, for $5,272.50. The work completed by both subcontractors was performed during the Respondent's term as the prime contractor on the project. These two subcontractors were never paid by the Respondent out of the draws received by him for that purpose. The Respondent did not pay the $5,000.00 he told Mr. Mangiardi he would pay in April of 1987. The evidence is unclear as to whether this amount of money was a payment of liquidated damages for the breach, the balance of funds entrusted to the contractor which had not been disbursed in the preceding construction phases, or the amount of unpaid liens known to the contractor at the time of breach. The Respondent filed for bankruptcy after a judgment was entered against him in a civil action by the Mangiardis for breach of contract. A Notice of Aggravation was not submitted during the formal hearing regarding the actual damage to the licensee's customers as a circumstance to be considered in aggravation of the penalty to be assessed. A copy of the Florida Construction Industry Licensing Board's previous letter of reprimand was not presented at hearing so that the hearing officer and the Board could use the prior violation for aggravation purposes.

Florida Laws (4) 120.5717.001489.105489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs RONNIE BOLES, 93-001497 (1993)
Division of Administrative Hearings, Florida Filed:Alachua, Florida Mar. 15, 1993 Number: 93-001497 Latest Update: Aug. 08, 1994

The Issue Whether disciplinary action should be taken against Respondent's license to practice contracting number RC 0054458, based on the violations of Section 489.129(1)(j), (k), (h), (p) and (m), F.S., alleged in the five count Administrative Complaint.

Findings Of Fact Since July 1968 and at all times material, Respondent Ronnie Boles, was licensed as a registered roofing contractor in the State of Florida, having been issued license number RC 0054458, and was registered to do business as "Ronnie Boles Roofing Company." On January 8, 1990 Ronnie Boles, doing business as Ronnie Boles Roofing and Construction, contracted with William C. Martin to construct two pole barns at 10550 N.W. 36th Lane, Gainesville, Alachua County, Florida. The contract price was $21,000.00. There is no evidence that "Ronnie Boles Roofing and Construction" was authorized through a valid contractor to construct pole barns. Respondent's roofing contractor license also did not permit the construction of pole barns. On January 12, 1990, Ms. Jean H. Martin, wife of William C. Martin, issued a personal check to the Respondent for $10,000 as partial payment on the January 8, 1990 contract. The Respondent delivered some materials to the site for use in the construction of the aforementioned pole barns, but never began construction. Mr. Martin attempted to have the Respondent construct the pole barns for over three months without success. The value of the materials provided by the Respondent was approximately $2,000.00, Mr. Martin attempted to have the Respondent refund the $8,000.00 balance of the money Ms. Martin previously paid Respondent on the uncompleted contract. Eventually, Mr. Martin retained attorney Ron Holmes who filed a civil suit against the Respondent based on the aforementioned contract. A judgment for Mr. Martin was obtained in the amount of $9,374.36 on October 1, 1991. Mr. Holmes has attempted to collect the judgment for Mr. Martin on several occasions without success. The Respondent has been actively uncooperative. As of the date of the formal administrative hearing, Respondent had paid no portion of the aforementioned judgment. Mr. Martin filed a complaint against the Respondent with the Department of Business and Professional Regulation. Tom Bishop, Department of Business and Professional Regulation Investigator, investigated the case and mailed the Respondent a notification letter on April 20, 1992. In addition, Mr. Bishop left two messages on the Respondent's answering machine. The Respondent did not respond to the notification letter or the phone messages left by Mr. Bishop. The Department of Business and Professional Regulation has accumulated $22.40 in initial investigative costs, $267.50 in investigative costs, and $605.90 in legal costs associated with prosecution of this cause as of the date of Petitioner's Proposed Recommended Order, totalling $895.80.

Recommendation Upon the foregoing findings of fact and conclusions of law, it is recommended that the Construction Industry Licensing Board enter a final order which provides as follows: Finds Respondent guilty of all violations as set out above. Requires Respondent to pay a collective fine of $5,000.00; Requires Respondent to pay restitution to Mr. Martin of $9,374.36; Requires Respondent to pay costs of investigation and legal fees in the amount of $895.80; and Suspends Respondent's license for three years, thereafter renewal of his license to be subject to proof of Respondent's compliance with requirements (2) - (4) inclusive. RECOMMENDED this 1st day of February, 1994, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The De Soto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 1st day of February, 1994. APPENDIX TO RECOMMENDED ORDER, CASE NO. 93-1497 The following constitute specific rulings, pursuant to S120.59(2), F.S., upon the parties' respective proposed findings of fact (PFOF). Petitioner's PFOF: 1 Rejected as unnecessary. 2-9 Accepted as modified to remove rhetoric and cumulative material. Respondent's PFOF: None Filed. COPIES FURNISHED: G. W. Harrell, Esquire Department of Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Ron Boles Route 2 Box 417 Alachua, Florida 32615 Richard Hickok, Executive Director Construction Industry Licensing 7960 Arlington Expressway Jacksonville, Florida 32211-7467 Jack McRay, Esquire Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (4) 120.57489.105489.117489.129 Florida Administrative Code (1) 61G4-17.001
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. FRED S. PETERSON, 89-000752 (1989)
Division of Administrative Hearings, Florida Number: 89-000752 Latest Update: Jun. 11, 1990

The Issue Whether Respondent aided and abetted an unlicensed contractor to engage in contracting by pulling permits for the unlicensed contractor; whether Respondent failed to qualify a firm for whom he was acting as licensed contractor; whether Respondent acted in the capacity of a contractor other than in his own name; and, whether Respondent violated local building codes as alleged in Second Amended Administrative Complaint filed 6-30-89, and Administrative Complaint filed 7-26-89.

Findings Of Fact At all times relevant hereto, Fred S. Petersen was licensed as a general contractor by the Florida Construction Industry Licensing Board (FCILB) and issued License Nos. CG C023928 and CB CA23929 (Exhibit 1). Neither American Weatherall Industries Inc. (AWI), Mel C. Wyatt, nor Steven C. Wyatt were licensed as contractors by the FCILB (Exhibit 2). Prior to mid-August 1987, Kirk Evenstad was the qualifying general contractor for AWI. By letter dated August 20, 1987, AWI proclaimed Kirk Evenstad to be no longer working for AWI because of mismanagement (Exhibit 3). Mel Wyatt, President of AWI, testified that Everstad had stolen between $30,000 and $50,000 of materials from AWI, leaving AWI in a precarious financial situation. In order to continue in business to work out of the financial hole created by Everstad, AWI, through one of its employees, Danny O'Brien, introduced Mel Wyatt to Respondent. Respondent had known O'Brien for some 20 years and, for the proposed reason of helping O'Brien, Respondent agreed to act as qualifying contractor for AWI. To carry out this project, Respondent entered into a contract (Exhibit 4) or Employment Agreement dated July 31, 1987, in which Respondent agreed to supervise construction of projects contracted for by AWI, but the latter was to provide all material and handle all financial aspects of the contracts. Respondent received $1000 for signing this agreement and was to receive a percentage of the gross proceeds of future contracts entered into by AWI. Respondent authorized O'Brien to pull permits for AWI pursuant to Respondent's contractor's license. Although Respondent testified he gave O'Brien authorization for each specific permit pulled and did not believe he signed Exhibit 11, dated August 11, 1987, a copy of General Authorization for O'Brien to pull permits for AWI under Respondent's license, it is found as a fact that Respondent signed the original of Exhibit 11 which is a copy. Within a short period of time after executing Exhibit 4, Respondent became aware of the financial difficulties facing AWI and ceased his efforts to qualify AWI. In the latter part of 1987 (believed to be November-December), AWI reached the point that it could no longer remain solvent and filed for bankruptcy leaving several contracts unfinished for which AWI had received partial payment. Of the four contracts entered into between AWI and homeowners for additions to their houses (Exhibits 7-9 and 14), all were entered into under a printed document showing Everstad's license number; however, the building permits for Exhibits 7-9 were pulled under Respondent's license. By agreement dated August 10, 1987 (Exhibit 7), Alfred and Marjory Hauk contracted with AWI to convert a garage at their home into an office. Hauk made payments of $1000 and $2300 to AWI, the permit for the work was pulled by O'Brien under Respondent's license, but no work was ever done under this contract. AMI subsequently went out of business, and Hauk received no refund of the monies he had paid to AMI. Hauk never met Respondent. On June 12, 1987, John Davis contracted with AWI to convert an existing garage to bedroom and bath and add a garage to his home. The initial permit for this work was pulled by Kenn Covicc as contractor on June 21, 1987, and a subsequent permit was pulled by O'Brien using Respondent's license. Although Davis paid over $6000 to AWI for this work, the work stopped after the footing for the garage addition was poured. On June 2, 1987, Albert Charette entered into a contract with AWI to add a room to his house. Charette paid some $9300 of the $34,400 contract amount during the progress of the work. Differences arose between Charette and AWI involving whether the construction was being done in accordance with the plans and specifications. In September, 1987, Respondent met with Charette and submitted a proposal (Exhibit 15) to Charette to complete the project in accordance with the plans and specifications. About one week after Exhibit 15 was signed, all work stopped on the project, and Respondent never received compensation or commenced work on this contract, which he had entered into in his own name and not as a representative of AWI.

Recommendation It is recommended that Fred S. Petersen be found guilty of violating Sections 489.129(1)(e), (f) and (g), Florida Statutes, and assessed a monetary fine of $3000. ENTERED this 11th day of June, 1990, in Tallahassee, Florida. K. N. AYERS Hearing Officer Division of Administrative Hearings The Desoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of June, 1990. APPENDIX Proposed findings submitted by Petitioner are accepted, except: Finding #7, penultimate sentence which is rejected as uncorroborated hearsay. Finding #11, that portion stating the purpose of Petersen's visit to Charette was to change the licensure on the permit to Petersen is rejected. See HO #13. Proposed findings submitted by Respondent are accepted, except: Finding #4, Accepted, except with regard to Respondent's notification of termination of his association with AWI. No documentation of this act was submitted and, even though Respondent may have ultimately revoked O'Brien's authority to pull permits, this was done well after the permits were pulled. COPIES FURNISHED: Robert B. Jurand, Esquire G. W. Harrell, Esquire Department of Professional Regulation Northwood Centre 1940 North Monroe Street Suite 60 Tallahassee, FL 32399-0792 Brian A. Burden, Esquire Post Office Box 2893 Tampa, FL 33601 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Kenneth E. Easley General Counsel Department of Professional Regulation Northwood Centre 1940 North Monroe Street Suite 60 Tallahassee, FL 32399-0792

Florida Laws (1) 489.129
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs WILLIAM LEETE STONE, IV, 98-001922 (1998)
Division of Administrative Hearings, Florida Filed:Naples, Florida Apr. 22, 1998 Number: 98-001922 Latest Update: Nov. 23, 1998

The Issue The issue in this case is whether Respondent violated Section 489.129(1), Florida Statutes (1997) (hereinafter, "Florida Statutes"), by committing mismanagement or misconduct in the practice of contracting, causing financial harm to a customer, abandoning a construction project, and failing to satisfy a judgment against him.

Findings Of Fact Petitioner is the state agency responsible for regulating the practice of contracting. Respondent is licensed as a contractor pursuant to license number CB C019811. At all relevant times, Respondent was the qualifying agent for Gulf and Bay Sunrooms, Inc. ("Gulf"). As the qualifying agent, Respondent was responsible for all of Gulf's contracting activities in accordance with Section 489.1195, Florida Statutes. On August 23, 1995, Respondent and Gulf entered into a contract with Mr. H. Edward Dowling ("Dowling") to install a Four Seasons System 330 Sunroom in Dowling's residence at 3016 West 38th Street, Orlando, Florida. The contract price was $31,340. Dowling paid the first draw of $9,402 to Respondent and Gulf by check number 45016644. On October 27, 1995, Gulf deposited the check to its account. Respondent and Gulf never commenced work on the sunroom. Respondent and Gulf did not return the first draw to Dowling. Respondent and Gulf abandoned the project without just cause and without notice to Dowling. On June 19, 1997, the County Court of the Ninth Judicial Circuit entered a Default Final Judgment in Case No. CO97-3800. The default judgment was entered in the amount of $9,402 plus costs of $145. Neither Respondent nor Gulf have satisfied the judgment. Respondent has a discipline history in two other cases. In Petitioner's Case No. 96-7123, Respondent failed to pay a supplier for windows. In DOAH Case No. 96-5914, Respondent contracted to build a sunroom in a residence, accepted payment of $1,540.44 toward the contract price of $4,668.00, never commenced construction, and abandoned the project. In the first case, Respondent was found guilty of failing to satisfy a civil judgment, was fined, and was ordered to pay restitution. In the second case, Respondent was found guilty of abandonment, incompetency or misconduct, was fined, and was ordered to pay restitution, and his license was suspended until Respondent complied with the penalty imposed.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Board enter a Final Order finding Respondent guilty of violating Section 489.129(1), Florida Statutes, imposing administrative fines in the aggregate amount of $15,000.00, and revoking Respondent's license. DONE AND ENTERED this 10th day of August, 1998, in Tallahassee, Leon County, Florida. DANIEL MANRY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 10th day of August, 1998. COPIES FURNISHED: Rodney Hurst, Executive Director Department of Business and Professional Regulation Construction Industry Licensing Board 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Lynda L. Goodgame, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Paul F. Kirsch, Senior Attorney Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street, Suite 60 Tallahassee, Florida 32399-0792 William Leete Stone, IV, pro se 3386 Poinsettia Avenue Naples, Florida 34104

Florida Laws (2) 489.1195489.129 Florida Administrative Code (1) 61G4-17.001
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. MARTIN GOLD, 88-003310 (1988)
Division of Administrative Hearings, Florida Number: 88-003310 Latest Update: May 30, 1989

Findings Of Fact Based upon the record evidence, the Hearing Officer makes the following findings of fact: Martin Gold is now, and has been since July, 1986, licensed by Petitioner as a Registered Specialty Contractor authorized to do painting and waterproofing work in Dade County. He holds license number RX 0051718, which expires June 30, 1989. Since receiving his license he has been disciplined twice by the Florida Construction Industry Licensing Board. Gold is the President of Team Leisure Corp., a construction company, and is also its "qualifying agent." On August 14, 1986, Team Leisure Corp. entered into a written contract with Terry Dudley and his wife, Patricia, in which it agreed, for $12,000, to build a two-room, 27-foot by 13- foot addition to the Dudley home located at 15510 Leisure Drive in Dade County and to install new windows in the existing structure. According to the terms of the agreement, Team Leisure was to do "no painting." In his capacity as President of Team Leisure Corp., Gold hired William Sernaker to directly oversee the completion of the construction work specified in the Dudley contract. At the time, Sernaker was licensed as a general contractor in Dade County. As part of his arrangement with Gold, Sernaker assumed responsibility for ensuring that all work permits and inspections necessary to complete the Dudley project were obtained. On September 4, 1986, Sernaker obtained a building permit for the Dudley project. Thereafter, work on the project commenced. The foundation for the addition was laid and, on September 10, 1989, it passed the inspection of James Tucker, a Dade County building inspector. Fifteen days later, Tucker conducted a tie beam inspection. This phase of the project also received his formal approval. Sernaker obtained a roofing permit on October 14, 1986. The exterior of the roof was inspected by Russell Bergsma, another Dade County building inspector, on October 21, 1986. It too passed inspection. An electrical permit was obtained for the Dudley project on November 17, 1986, by Robins Electric, a subcontractor. When the electrical work was initially inspected by Grant Morse, another Dade County building inspector, it was rejected because there were a "few outlets missing." The record is unclear as to the results of any subsequent electrical inspections. Morse also conducted an inspection of the framing work done on the Dudley project. He did so on or around November 21, 1986. In his view, the framing was "not to code." Accordingly, he left a "tag" at the job site on which he gave the following written explanation for his rejection of the framing work: All window bucks must be tight with caulking, no gaps. When the stucco meets the window frame, it should be set back at approximately a 45-degree angle at a width of one quarter to provide a groove to be filled with caulking. Continuous back bed of caulking must be maintained. A follow-up inspection of the framing work was performed by Bergsma on December 1, 1986. In Bergsma's opinion, while some corrections had been made, deficiencies remained. He therefore issued another rejection. A third framing inspection was conducted on December 3, 1986. Tucker was the inspector who performed this inspection. He approved the work that had been done. Prior to this inspection, Gold had paid another contractor $600 to "redo" the framing. This additional expense was not passed on to the Dudleys. Morse attempted to conduct a final building inspection on December 22, 1989. He was unable to do so, however, because "[n]o one was home." From the outset, Gold kept abreast of the progress that was being made on the Dudley project by communicating with Sernaker. He also visited the job site on at least a weekly basis. Gold also heard from the Dudleys concerning the status of the project. The Dudleys closely monitored the work of Sernaker and his crew. If the work was not done to their satisfaction, they expressed their disapproval to Sernaker and, if he did not rectify the matter, they complained to Gold over the telephone. The following were among the complaints made by the Dudleys: the foundation was not level; the roof did not contain any fiberglass material; the window frames did not fit properly; the wood used for the open beam ceilings had cracks in it and was unsightly; the walls in the den were not level and had cracks in them; the linoleum on the Dudleys' screened-in porch was ripped by workers putting up a wall; the outside stucco was cracking and peeling; and trash was left on the property. An effort was made to address the Dudleys' concerns. For instance, in response to the Dudleys' complaints, a "thin cap" was placed over the foundation to make it level. The roof was redone with fiberglass material. The Dudleys were reimbursed for the linoleum they needed to replace on their porch. A contractor was hired to correct the framing problem. Nonetheless, the Dudleys became increasingly dissatisfied with Team Leisure Corp.. Sometime shortly before January 6, 1987, they became so dissatisfied that they ordered Sernaker and his crew off their property and refused to make any additional payments. Following this incident, Gold met with the Dudleys and attempted to mollify them. This was his first face-to-face meeting with them. He offered to send another contractor to the Dudleys' home to perform the work the Dudleys believed needed to be done to satisfactorily complete the project. The Dudleys accepted this offer. On January 6, 1987, Gold sent the Dudleys a letter which read as follows: As per our mutual agreement, these are the items you requested be taken care of. Once taken care of, you agree to sign completion certificate so we can be funded. COMPLETED (please check upon satisfaction) 1.) Touch up outside windows. 2.) Windows to be locked in. 3.) Walls in den to be taken down and leveled out. 4.) Frame around closet door. 5.) Fix two windows; replace concrete in doors and windows. 6.) Clean up. 7.) Replace vinyl, in rear den. 8.) $100.00 dollars to Mrs. Dudley, for clean-up. 9.) 10 year guarantee- roof and release of lien [sic]. 10.) Concrete over build. 11.) Crack under window sill. 12.) Nail in door frame. 13.) Gaps in drywall bedroom. 14.) Stucco cracking outside. 15.) Electrical inspection. (not to be Mike Charles.) Accepted and Approved: x x After receiving this letter, Mr. Dudley checked all but items 2, 5, 6, 8, and 9 on the letter's "completion certificate." Neither he nor his wife, however, signed this "completion certificate." Although the cracks in the outside stucco had been repaired at the time Dudley checked item 14, the stucco subsequently started cracking again. A final building inspection of the Dudley project was conducted by Tucker on January 13, 1989. The project was "turned down" by Inspector Tucker because it was unpainted. Under their contractual agreement, the Dudleys, not Team Leisure Corp., were responsible for the painting of the project. The painting was not done because the Dudleys noticed cracks reappearing in the outside stucco. On or around March 4, 1987, Mr. Dudley telephoned Inspector Bergsma and asked him to conduct an informal field inspection of the project. Bergsma complied with Dudley's request. When he arrived at the Dudley home, Dudley showed him a "gap on the rear of the house ... where the two roofs are at different levels and come together." Bergsma told Dudley that "[i]t didn't belong there" and that it would have to be eliminated if the structure was to pass a final building inspection. As of the date of the hearing, the structure had not passed such an inspection. Team Leisure Corp. received $10,200 for the work done in connection with the Dudley project. The remaining $1,800 of the $12,000 that the Dudleys were to pay pursuant to the contract was held in escrow by a bank. Ultimately, this $1,800, along with approximately an additional $500 from Team Leisure Corp., was given to the Dudleys as part of a settlement between them and Team Leisure Corp.. The money was to be used by the Dudleys to pay another contractor to complete the project to their satisfaction.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a final order (1) finding Respondent guilty of contracting outside the scope of his license in violation of Section 489.129(1) (j) , Florida Statutes; (2) imposing a $750 administrative fine upon Respondent for said violation, and (3) dismissing the remaining charges against Respondent set forth in the instant administrative complaint. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 30th day of May, 1989. STUART M. LERNER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of May, 1989. COPIES FURNISHED: Elizabeth Alsobrook, Esquire Northwood Centre 1940 North Monroe Street Suite 60 Tallahassee, Florida 323399-0792 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Carlos Garcia, Esquire 8603 Dixie Highway Suite 400 Miami, Florida 33143 =================================================================

Florida Laws (8) 120.5717.001489.105489.115489.117489.119489.12990.202
# 8
PINELLAS COUNTY CONSTRUCTION LICENSING BOARD vs BRADLEY T. BARBOUR, 95-001486 (1995)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Mar. 23, 1995 Number: 95-001486 Latest Update: Aug. 04, 1995

The Issue The issue in this case is whether the Pinellas County Construction Licensing Board should discipline the Respondent for alleged failure or refusal to satisfy a civil judgment in a reasonable period of time.

Findings Of Fact The Respondent, Bradley T. Barbour, has not disputed that he is a certified tile and marble specialty contractor, holding Pinellas County Construction Licensing Board license number C-5778. The Respondent entered into a contract with Cameron Vale to tile the floor of his house. The tile job was unsatisfactory to Vale, who sued in the County Court, Pinellas County, Small Claims Division, Case No. 93-5287 SC-NCD. On February 14, 1994, Vale and the Respondent entered into a Pretrial Conference Agreement. Under the Agreement, the Respondent agreed, among other things, to pay Vale $2,500, payable $200 a month beginning February 18, 1994, until paid in full. Based on the Agreement, Vale and the Respondent filed a Stipulation to Stay Entry of Judgment on February 14, 1995, and two days later the court entered an Order staying entry of final judgment. Contrary to the terms of the Agreement and Stipulation, the Respondent only made one payment of $100. On June 7, 1994, the court entered a Judgment against the Respondent in the amount of $2,400, together with 12 percent interest on the Judgment. The Respondent has made no payments to Vale on the Judgment and has not satisfied the Judgment either in full or in part. The Board has published "Guidelines for Disciplinary Action" which provide for a $300 fine as the "typical" penalty for the first "minor" infraction and a $750 fine as the "typical" penalty for the first "major" infraction. The Guidelines give no guidance in distinguishing between "minor" and "major" infractions. The Guidelines also list aggravating and mitigating circumstances which focus on the harm done by the offense, the licensee's efforts to rectify the situation, and whether there is a history of similar offenses by the licensee. They also authorize suspension or revocation and fines "not to exceed $1,000 per count."

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Pinellas County Construction Licensing Board enter a final order: (1) finding the Respondent guilty of violating Section 24(2)(c) of Chapter 75-489, Laws of Florida (1975), as amended; (2) fining him $750; (3) revoking his license; and (4) conditioning relicensure upon both full restitution to Cameron Vale under the terms of the outstanding Judgment and full payment of the fine imposed in this case. RECOMMENDED this 23rd day of June, 1995, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of June, 1995. COPIES FURNISHED: William J. Owens Executive Director Pinellas County Construction Licensing Board Suite 102 11701 Belcher Road Largo, Florida 34643-5116 Bradley T. Barbour B & B Tile 2035 Philippe Parkway Safety Harbor, Florida 34695

Florida Laws (5) 120.52120.54120.56455.227489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer