Findings Of Fact On November 30, 1982 the Chancellor of the State University System approved Amendment 567, as revised, to the Capital Outlay Implementation Plan. This Amendment budgeted $6,350,000 for the construction and equipment of a teaching gymnasium at Florida International University on the Tamiami Campus. Included within that figure were $350,000 of planning expenses appropriated by the 1981 Florida Legislature and $6,000,000 appropriated by the Legislature in 1982 for the expenses of construction, art work and contingencies. In the early part of 1983 the State University System advertised for bids from contractors to construct the gymnasium. The bids were open on May 17, 1983 at 2:00 PM. on the Florida International University Tamiami Campus. Petitioner's base bid of $5,998,000 was the lowest of the 17 received, nevertheless it was $350,000 above the estimate in Amendment 567. The next lowest bid was for $6,045,000. The bid specifications required that six alternatives in addition to the base cost be bid on, but through an oversight Sanmar's bids on these alternatives did not conform to the bid specifications. Sanmar's alternative bids failed to indicate that the amount reflected was in addition to the base cost bid. However, because the issues in this case concern the base bid amount, Sanmar's error with respect to the alternatives is not material. At the May 17, 1983 bid opening Respondent's agent, the architectural firm of Greenleaf-Telesca, announced that it would recommend to the Board of Regents that all bids be rejected as being in excess of the funds available through legislative appropriations. Respondent intends to make design changes in the project to make it less expensive and to then rebid it. On May 18, 1983 Sanmar timely filed a protest to the rejection of its bid. Subsequent to May 17, 1983 and Respondent's decision to reject all bids, the Florida Legislature through Section 2(2)(y), Chapter 83-333, Laws of Florida (1983), appropriated an additional $500,000 for the construction of the gymnasium. This appropriation became effective on July 1, 1983. After its receipt of Sanmar's bid protest Respondent provided in a letter dated June 3, 1983 the figures on which the Respondent based its decision to reject all bids including Sanmar's. These figures follow: Architects fee including additional services $ 379,240.00 **Architects construction observation (included in architects estimate as part of the fee and contingencies) $ 90,000.00 Sanmar Base Bid $5,998,000.00 Equipment $ 200,000.00 Contingency (3 percent of construction cost) $ 179,940.00 Based on Sanmar's bid $6,847,420.00 Artwork $ 28,240.00 $6,875,420.00 **Estimated based on 18-month construction time. Petitioner has taken issue with the 3 percent contingency amount included in the above figures, however, the evidence shows that 3 percent is a reasonable amount based upon the State University System's experience with previous construction and is a fair estimate to insure that projects once begun can be adequately funded by the amount appropriated for their construction.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Board of Regents enter a Final Order rejecting all bids for the construction of a teaching gymnasium at the Tamiami Campus of the Florida International University. DONE and RECOMMENDED this 15th day of December, 1983, in Tallahassee, Florida. MICHAEL PEARCE DODSON Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of December, 1983.
The Issue The issue for determination is whether the Intervenor was properly qualified to complete the construction project contemplated by Invitation to Bid No. DCF-03211120 (ITB)
Findings Of Fact The Department issued the ITB for a construction project, involving the re-roofing of Buildings 1 and 2 at 12195 Quail Roost Drive, Miami, Florida. The ITB was published in the Florida Administrative Weekly on December 24, 2008. The ITB outlined the terms and conditions for responsive bids. The ITB indicated, among other things, that all sealed bids were required to be submitted at 401 NW 2nd Avenue, S-714, Miami, Florida 33128, by January 15, 2009, at 2:00 p.m. Leo Development submitted its sealed bid at the location and by the date and time, in accordance with the ITB. FBM submitted its sealed bid by the date and time, but at a different location—the offices of Russell Partnership— contrary to the ITB. All other bidders submitted their sealed bids at the location and by the date and time, in accordance with the ITB. The Department’s architect of record on the project, Russell Partnership, and one of its principals, Terry Holt, performed the examination and bid tabulation. Mr. Holt, a registered architect for approximately 36 years, was very familiar with the procurement process and had extensive experience in determining whether a bidder was licensed by DBPR in order to complete the work contemplated for a project. The sealed bids submitted at 401 NW 2nd Avenue, S-714, Miami, Florida 33128, on or before January 15, 2009, at 2:00 p.m. were as follows: All Time Roofing, with a bid of $73,400.00; Taylor Roofing, with a bid of $59,708.00; Leo Development, with a bid of $54,109.00; John W. Hunter Enterprises, with a bid of $75,000.00; and Trintec Construction, with a bid of $75,500.00. 9. FBM’s bid was $71,600.00. Mr. Holt determined that Leo Development was the lowest bidder. FBM’s bid was not considered as being non-responsive. Additionally, Mr. Holt reviewed Leo Development’s website to ascertain as to whether any factors existed to disqualify Leo Development. The website failed to reveal any basis for Mr. Holt to disqualify Leo Development. Having discovered no basis to disqualify Leo Development as the lowest bidder, Mr. Holt submitted the list of bidders, with their bids, to Bill Bridges, the Department’s senior architect and a registered architect for approximately 25 years. Mr. Bridges was the person responsible for oversight of the ITB process. As Leo Development was the lowest bidder, Mr. Bridges reviewed the website of the Florida Department of State, Division of Corporations (Division of Corporations) in order to ensure that Leo Development was registered with the Division of Corporations. His review revealed that Leo Development was a fictitious name properly registered to Leo Premier Homes, LLC. Further, Mr. Bridges performed a license background check on Leo Development in order to ensure that Leo Development was licensed by DBPR. Mr. Bridges reviewed DBPR’s website, which revealed that Frank Anthony Leo was the owner of Leo Development and that the following licenses were issued by DBPR: Qualified Business Organization License #QB50182 to Leo Premier Homes, LLC, Leo Development; Certified Building Contractor License #CBC1254723 to Frank Anthony Leo, Leo Development; and Certified Roofing Contractor License #CCC1328402 to Frank Anthony Leo, Leo Development. Mr. Bridges confirmed and was satisfied that Leo Development was properly licensed to complete the work contemplated by the ITB. Mr. Bridges recommended that Leo Development be awarded the ITB as the lowest responsive bidder. FBM filed a written protest (Initial Protest) of “its exclusion from the bid tabulation.” The Department issued a Final Order Rejecting Bid Protest (Final Order) on February 19, 2009. The Final Order provided in pertinent part: FBM was determined non-responsive because the bid was not presented at the time and place specified in the ITB. . . FBM’s formal written protest alleges that FBM, on the date of the bid submission/bid opening, was misdirected as to the location of the bid opening. . . . FBM’s protest must be rejected because it does not state a claim that could entitle it to relief. . . In the context of a bid protest proceeding . . . the protest must adequately allege that the protestor could obtain the contract award or otherwise benefit should the protest be successful. . . Assuming all of FBM’s factual allegations are true and that those facts entitle FBM to have its bid considered, FBM would still be entitled to no relief. Had FBM’s bid been accepted, FBM would have been the third lowest of six bidders. FBM’s formal protest does not allege that the lowest and second lowest bids were deficient in any manner. FBM was not injured in fact, because it still would not have received the contract award. Accordingly, FBM’s formal written protest is REJECTED. No appeal was taken by FBM of the Department’s Final Order rejecting FBM’s Initial Protest. Among other findings, the Department’s Final Order on FBM’s Initial Protest found that, taking FBM’s allegations as true, FBM would have been the third lowest bidder. FBM would not have been the second lowest bidder. The parties agree that the holder of a certified building contractor’s license and a certified roofing contractor license would be permitted to complete the work contemplated by the ITB. Subsequent to the opening of the sealed bids, Leo Premier Homes, LLC, registered the fictitious name of Leo Roofing & Construction with the Division of Corporations. After the registration with the Division of Corporations and after the Department’s Final Order, licenses were issued by DBPR. As to the licenses issued, the record of the instant case provides2: Qualified Business Organization License #QB50182 to Leo Premier Homes, LLC, Leo Roofing & Construction; Certified Building Contractor License #CBC1254723 to Frank Anthony Leo, Leo Roofing & Construction; and Certified Roofing Contractor License #CCC1328402 to Frank Anthony Leo, Leo Roofing & Construction. The licenses reflect the same license numbers, as before, and only the fictitious name is different on each license to indicate Leo Roofing & Construction.3 The contract for the ITB was entered into between the Department and Leo Development. In these proceedings, the Department incurred costs in the amount of $1,311.05.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Children and Family Services enter a final order dismissing FBM General Contracting Corporation’s Protest and awarding costs in the amount of $1,311.05 to the Department of Children and Family Services. DONE AND ENTERED this 21st day of August 2009, in Tallahassee, Leon County, Florida. ERROL H. POWELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 21st day of August, 2009.
Findings Of Fact At some time prior to August 2, 1984, DOT issued bid blanks for a mini- contract for State Project No: 76020-3515, for work consisting of cleaning and guniting a concrete box culvert located on State Road 19, in Putnam County, Florida, approximately one mile south of the Cross Florida Barge Canal. The bid package, signed by C. A. Benedict, District Engineer, for the DOT, specifically reserved the right to reject any and all bids. The bid package broke the work down into three item numbers. The first was mobilization and called for one pricing unit. The second item called for maintenance of traffic at the work site and called for one pricing unit as well. The third area called for restoration of spalled areas (gunite) and called for approximately 437 cubic feet to be priced. In this regard, the plans furnished with the bid package and the bid package itself, in at least three separate locations, called for the bid as to the last item to be priced and paid for on a unit price basis. Petitioner submitted the lowest bid of seven bidders. It was determined to be faulty, however, in that though it properly priced the first two items, it failed to submit a unit price for the third item per unit, submitting instead a total price for the third item based on the entire cubic footage. Petitioner's bid indicated 437 cubic feet priced at a total of $17,832.00. Simple arithmetic permits a division which results in a unit price for each of the 437 cubic feet of $40,805. This last unit price, however, is not reflected on the bid submitted by Petitioner. Petitioner's bid is the only bid of the seven submitted which did not contain a unit price for each of the units in the third item. EDS has been in business since 1980. It performed one previous contract for DOT and is familiar with DOT's rules regarding bidding. It had ample opportunity to examine the plans and the bid blank before submitting its bid and admits that the unit price, though required, was omitted. Petitioner contends, however, that the omission is not a material variance and can be waived by Respondent. Respondent contends, on the other hand, that the failure to list the unit price in the third item is material. This determination is based on the fact that since the bid package calls for payment on a unit basis, the odd one- half cent per unit does not permit even money payment and requires rounding off. Even with this being true, the maximum difference would be one- half cent to be rounded off either upwards or downwards. At some point after opening, at least one of the unsuccessful bidders found out that Petitioner's bid failed to technically conform to the terms of the bid blank and at this point the second lowest bidder, Vann's Sandblasting, whose bid was $4,000.00 higher than that of Petitioner, and who had done several contracts for Respondent in the past, indicated that if petitioner's bid were not rejected, he would file a protest. The one-half cent variance, itself, is not material. Considering all factors, however, the failure to state the unit price may, under certain circumstances, be.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is, therefore: RECOMMENDED THAT Petitioner, EXPLOSIVE AND DIVING SERVICES, INC., be awarded the contract for State project No 76020-3515. RECOMMENDED this 27th day of February, 1985, at Tallahassee, Florida. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904)488-9675 FILED with the Clerk of the Division of Administrative Hearings this 27th day of February, 1985. COPIES FURNISHED: Gail S. Wood, President Explosive and Diving Services, Inc. Post Office Box 200 Clarksville, Florida 32430 Larry D. Scott, Esquire Department of Transportation Haydon Burns Building, MS-58 Tallahassee, Florida 32301 Paul Pappas, Secretary Department of Transportation Haydon Burns Building, MS-58 Tallahassee, Florida 32301
The Issue Whether the certified general contractor's licenses and the registered roofing contractor's licenses held by Petitioner Robert J. Nali should be revoked.
Findings Of Fact The certified General Contractor's License number CG-C007395 and CG- CB07395, and the Registered Roofing Contractor's License number RC0028067, issued to Robert J. Nali are active and current. Respondent entered into a contract with Mr. Charles Rapp on June 1, 1977, to have a house constructed for the contract price of $29,500. The home was financed through the First Federal Savings and Loan Association of Leesburg for the sum of $27,730. Disbursed directly to Respondent Nali in five different draws was $16,638. These disbursements left a total of $11,092 in the bank account for completion of the home. Two bills remain unpaid, one for $500 and one for $560.92. Cost of the home was approximately $2,035.87 above the contract price. Two liens were filed against Mr. Rapp's property which were satisfied out of construction funds from the bank, one by Adobe Building Center, Inc., in the amount of $1,315 and one by Branch Garage Door Sales in the amount of $171.38. Respondent Nali admitted that the Kennedy Company supplied air conditioning duct work for the home, and that Yale Ogron Builders provided labor as a subcontractor; that he was paid for the supplies provided by the Kennedy Company on the second drawing, and for the labor provided by Yale Ogron Builders on the fourth draw. Respondent Nali admitted he did not pay these concerns although he did receive the funds for the material and labor supplied. Mr. Rapp fired Mr. Nali and completed the home himself. There was no date of completion in the contract, but Respondent did not actively pursue the completion. Respondent Nali entered into a contract with Mr. Charles Fosmoen in June of 1977, for the purpose of constructing a home. The contract price was $28,150. The home was financed through the First Federal Savings and Loan Association of Leesburg for the sum of $26,471. Disbursed to Nali under the contract was $19,845.75. The disbursement left a total of $6,625.25 to complete the house. Expended to complete construction of the home in accordance with the contract was $9,351.08, an excess of $2,725.83 of the contract price. A claim of lien was filed against the Fosmoen home by Lake Pre-Hung Door Manufacturing Company, Inc. Mr. Nali was fired from the job and, although no time was designated in the contract for completion, Respondent Nali did not actively pursue the construction of the home. A contract was entered into with Mrs. Ellen Haffey on November 16, 1977, to construct the shell of a home for the contract price of $17,600. Mrs. Haffey paid the sum of $10,000 directly to Respondent and expended a sum of $6,625.93 to complete the house as contracted. She has bills remaining unpaid in the amount of $3,620.50. Spent by Mrs. Haffey above the contract price was $2,648.43. Mrs. Haffey, a contractor, dismissed Mr. Nali, and the house is not yet completed. A claim of lien was filed against Mrs. Haffey's property on behalf of Leesburg Building Materials, Inc., in the amount of $4,384.47. The lien was for materials which had been delivered to the project site and should have been paid for out of the sum previously paid to Respondent. Mrs. Haffey paid $4,000 for the third draw instead of $6,000, as called for by the contract, a fact that prevented Respondent from timely payment of bills. A lien was filed on Mrs. Haffey's property by Keeman Brick of Central Florida, Inc., in the amount of $1,238.03. Respondent admitted he was charged with a criminal violation of misapplication of funds but pled nole contendere, and adjudication was withheld. A document entitled "Stipulation on Motion for Clarification and Modification" was received into evidence. The document constitutes an admission of Respondent that restitution was due from him to the complainants, Mr. and Mrs. Charles Rapp, Mrs. and Mrs. Charles Fosmoen, and Mrs. Ellen Haffey. Petitioner contends that Respondent diverted funds he had received to pay two subcontractors for the Rapp home; that although he may Waive underbid the Rapp and Fosmoen he later also underbid the Haffey contract, which caused these consumers inconvenience and loss and violated a contractor's position of trust. Respondent contends that he could have finished each of the houses within the contract terms, since time was not of the essence. He contended that increased building material costs contributed to the delay of the housing construction, and that he could have finished the houses were he not fired from each of the construction projects. Respondent denied that he had diverted any funds from construction projects. The Hearing Officer further finds: Both Mr. and Mrs. Rapp and Mr. and Mrs. Fosmoen gave Respondent Nali notice that they were dissatisfied because Mr. Nali was not actively finishing the construction of their respective homes. Both gave him notice and an opportunity to recommence active construction, which he did not resume; The dates of completion of homes were not specified in the contracts, but oral promises were given that the homes would be completed within a reasonable time. The delay caused each complainant much inconvenience; Liens were filed against these homes for nonpayment of bills. Respondent did not pay the liens; Each of the three homes cost more than the contracted price before said homes were completed by the parties contracting with Mr. Nali. Mr. Nali received money from Mr. Rapp for work and supplies provided by the Kennedy Company and Yale Ogron Builders, yet Respondent did not pay for these materials or work; and The complainants were justified in dismissing Respondent.
Recommendation Suspend the license of Respondent Robert J. Nali for a period of six months. DONE and ORDERED this 13th day of April, 1979, in Tallahassee, Leon County, Florida. COPIES FURNISHED: Michael Egan, Esquire 217 South Adams Street Post Office Box 1386 Tallahassee, Florida 32302 Joan L. Wollin, Esquire Post Office Box 236 Leesburg, Florida 32748 DELPHENE C. STRICKLAND Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32301 (904) 488-9675 ================================================================= AGENCY FINAL ORDER ================================================================= FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. DIVISION OF ADMINISTRATIVE HEARINGS, DOCKET NO. 78-2103 ROBERT J. NALI, Respondent. /
Findings Of Fact As project architect under contract to HRS, Greenleaf/Telesca Planners, Engineers, Architects, Inc. (Greenleaf) prepared a project manual (manual). The manual invited contractors to bid on a contract for construction of the forensic services building at the South Florida State Hospital in Pembroke Pines, Florida, project No. HRS-0278. The manual contained specifications for a base contract covering construction of the building itself, and for four alternate additive bids, covering various equipment and furnishings. The first alternate called for installation of mess hall tables and seats. For the first alternate, the manual specified tables and seats manufactured by Folger Adam Company, their model number 522, or "upon prior approval" the equivalent. From the floor plan it is clear that 24 tables and corresponding seats would be required. The language of the manual describing alternate No. 1 presents no particular ambiguity or difficulty. The Folger Adam Company is well known in the construction business. Harold Wayne Blackwell, petitioner's president, used the manual in preparing Blackwell's bid for the contract. Blackwell bid on the base contract and on each of the four alternates. There are seven or eight contract hardware suppliers in Dade and Broward Counties, all of whom have access to Folger Adam Company products. Folger Adam Company does not have exclusive distributors. To determine the price of the tables, Mr. Blackwell telephoned several contract hardware suppliers, including Christensen Hardware Services, Inc. (Christensen). Christensen quoted Blackwell a price of ten thousand eight hundred dollars ($10,800.00) for twenty-four sets of Folger Adam model number 522 tables and seats. Blackwell submitted a bid of eleven thousand dollars ($11,000.00) on alternate No. 1. Forsythe bid on the base bid but did not bid on alternate No. 1, because Forsythe failed to obtain a quote on the tables and seats, before preparing its bid. Richard B. Solomon, Greenleaf's project manager for the forensic services building, opened the bids on March 20, 1979. As tabulated by Greenleaf, the bids were: Base Bid Alt. No. 1 Alt. No. 2 Alt. No. 3 Alt. No. 4 M.D. Forsythe Construction Co. $375,000 $ --- $50,842 $27,220 $33,020 Porfiri Construction Co. 406,200 7,000 45,534 25,315 44,130 Wayne Blackwell and Co., Inc. 397,735 11,000 47,000 25,000 35,000 Ed Ricke & Sons, Inc. 405,000 14,900 52,000 28,300 47,650 McKee Construction Co. 407,000 --- 45,000 28,000 --- L.G.H. Construction Corp. 524,176 18,014 43,464 24,712 35,048 Creswell Construction Co. 394,000 41,000 43,000 23,000 33,000 Petitioner's exhibit No. 2. On the base bid, Forsythe was lowest, Creswell Construction Company next lowest, and Blackwell third lowest. Among contractors who bid on the base bid and all alternates, Blackwell's combined bids were lowest for the base bid plus alternate No. 1, the base bid plus alternates Nos. 1 and 2, the base bid plus alternates Nos. 1, 2 and 3, and the base bid plus alternates Nos. 1, 2, 3 and 4. Mr. Solomon was aware of two telephone calls received by Greenleaf during the time for preparation of the bids, inquiring about the price of the tables and seats. In examining the bids, he noticed that two contractors had not bid on alternate No. 1, and that the base bids as well as the bids on alternates Nos. 2, 3 and 4 were "pretty tight" as compared to the range of bids on alternate No. 1. From looking at the bids on alternate No. 1, it was hard for Mr. Solomon to tell what a reasonable price for the tables and seats was. Mr. Solomon recommended to HRS that the bids on alternate No. 1 be thrown out. Charles Robert Yates, an architect employed by HRS, concurred in Mr. Solomon's recommendation. He was under the impression that funding for the project would not be available unless the contract was let before April 1, 1979. Mr. Yates could not recall such diversity among bids in his thirty-year career, yet he had no difficulty learning what the tables and chairs cost when he called architectural firms to find out. After the bids were opened, Blackwell promptly protested Forsythe's bid. Under the heading of alternates, the manual states: If the Base Bid is within the amount of funds available to finance the construction contract and the Owner wishes to accept alternate additive bids, then contract award will be made to that responsible Bidder submitting the low combined bid, consisting of the Base Bid plus alternate additive bids (applied in the numerical order in which they are listed in the Bid Form). Petitioner's exhibit No. 1, Paragraph B-9, Alternates. HRS wrote Blackwell on April 3, 1979, denying Blackwell's protest and stating, as reasons: M.D. Forsythe Construction Co., Inc. did not ignore Alternate No. 1, but completed that section of their bid by stating "No bids received on this item." Proposals for Alternate No. 1 ran the gamut for "No Bid" to prices extending from $7,000 to $41,000. The Department holds, as concurred in by the attached letter from our consultants, that there was confusion in the marketplace regarding the intent of Alternate No. 1, as attested to by the disparity among the proposals, and therefore we choose not to consider Alternate No. 1. Provisions for this deletion include Sections B-17, B-22 and B-24 of the Contract Documents. Petitioner's exhibit No. 3. HRS then awarded the base contract and additive alternates Nos. 2 and 3 to Forsythe, and gave orders to proceed with construction on May 7, 1979. After construction began, Mr. Solomon wrote Forsythe to inquire what Forsythe would charge to install the tables and seats called for by additive alternate No. 1. Forsythe eventually agreed to do it for eleven thousand dollars ($11,000.00), after first quoting a higher price. On August 1, 1979, Greenleaf prepared a change order at HRS' behest, directing Forsythe to install the tables and seats originally called for by additive alternate No. 1, at a price of eleven thousand dollars ($11,000.00). Other provisions of the manual relied on by the parties include the following: B-17 PREPARATION AND SUBMISSION OF BIDS Each Bidder shall copy the Proposal Form on his own letterhead, indicate his bid prices thereon in proper spaces, for the entire work and for alternates on which he bids. Any erasure or other correction in the proposal may be explained or noted over the signature of the Bidder. Proposals containing any conditions, omissions, unexplained erasures, alternations, items not called for or irregularities of any kind may be rejected by the Owner. . . DISQUALIFICATION OF BIDS Any or all proposals will be rejected if there is reason to believe that collusion exists among the Bidders and no participants in such collusion will be considered in future proposals for the same work. Proposals in which the prices obviously are unbalanced will be rejected. Falsification of any entry made on the Contractor's bid proposal will be deemed a material irregularity and will be grounds, at the Owner's option, for rejection. REJECTION OF BIDS The Owner reserves the right to reject any and all bids when such rejection is in the interest of the State of Florida, and to reject the proposal of a Bidder who is not in position to perform the contract. AWARD OF CONTRACT The contract will be awarded as soon as possible to the lowest qualified Bidder provided his bid is reasonable and it is in the best interest of the Owner to accept it. The Owner reserves the right to waive any informality in bids received when such waiver is in the interest of the Owner. The lowest bidder will be determined by adding to the Base Bid such alternates, in numerical order, as available capital funds will allow. The Agreement will only be entered into with responsible contractors, found to be satisfactory by the Owner, qualified by experience, and in a financial position to do the work specified. Each Bidder shall, if so requested by the Owner, present additional evidence of his experience, qualifications, and ability to carry out the terms of the contract, including a financial statement. Petitioner's exhibit No. 1. At no time did Forsythe attempt to influence the award of the contract improperly. At the time of the final hearing, the project was approximately 95 percent complete.
Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That, in the future, HRS adhere to the letter of language like that contained in paragraph B-9 of the manual whenever such language is used in an invitation for bids. DONE and ENTERED this 6th day of March, 1980, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: Louis L. LaFontisee, Jr., Esquire 200 South East First Street, Suite 802 Miami, Florida 33131 Leonard Helfand, Esquire 401 North West 2nd Avenue Room 1040 Miami, Florida 33128 Richard Morgentaler, Esquire 1600 North East Miami Gardens Drive North Miami Beach, Florida 33179 =================================================================
The Issue Whether Respondent acted contrary to the agency's governing statutes, rules or policies, or the bid specifications in its proposed decision to award Contract No. T1285 to Intervenor Kamminga & Roodvoets, Inc. ("K & R").
Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of the proceeding, the following findings of fact are made: On May 14, 2008, the Department released its bid solicitation for Contract T1285. The proposed contract was for the construction of a one-way pair through Lake Alfred, including new construction, reconstruction, milling and resurfacing, widening, drainage improvements, lighting, signalization, signing and pavement marking and landscaping on State Road 600 (U.S. 17/92). Polk County, the location of the project, lies in the Department's District 1. Qualified contractors, including Mid-State and K & R, received an electronic disk containing the solicitation, bid blank, plans and specifications for Contract T1285. The letting date for this project was June 18, 2008. Bids were to be submitted on or before that date via Bid Express, the electronic bidding system used by the Department. No party submitted a protest of the terms, conditions, and specifications contained in the solicitation pursuant to Subsection 120.57(3)(b), Florida Statutes. The work to be performed on Contract T1285 included the installation of limerock road base to be paid for in accordance with line item 0175, Optional Base Group 09 ("Base Group 09"). The bid documents included a set of "Supplemental Specifications." Section 6 of the Supplemental Specification was titled "Control of Materials." Subsection 6-3.3, titled "Construction Aggregates," provided as follows: "Aggregates used on Department projects must be in accordance with Florida Administrative Code Rule 14-103."2 Under the heading "Developmental Specifications" is a February 15, 2008, revision to the Construction Aggregates subsection that provides: Subarticle 6-3.3 (Page 54) is expanded by the following: 6-3.3.1 Department Directed Source for Aggregates: For this Contract, obtain aggregates for use in limerock base from the following vendor: Vulcan Construction Materials LP. Upon award of the Contract, provide the vendor and the Department a schedule of project aggregate needs. Once a schedule has been provided to both the Department and vendor, the Engineer will issue written authorization, with a copy to the vendor, for the purchase of aggregates from the vendor. This authorization is required before aggregates will be released by the vendor. Pick up the required aggregate such that the project schedule will be maintained. Payment to the vendor by the Contractor will be due upon receipt of the materials pursuant to the Department's Vendor Contract No. BDH50. This rate is the unit price agreed upon by the Department and the vendor and will be made available to bid proposal holders at the time of bid at http://www.dot.state.fl.us/construction/aggregate /aggregate.htm. The Department will make payment to the Contractor for the aggregates on progress estimates as a part of the bid unit price for the appropriate pay items. The rate is subject to change and adjustments for such changes will be made to the bid unit price of the appropriate pay items. Disputes with the vendor concerning aggregate supply will not be cause for Contract time adjustments, time suspensions or monetary adjustments to the Contract amount. The Contractor will be solely responsible for providing the necessary advance notice to the vendor and other coordination to obtain timely aggregate supply for the project. The import of Developmental Specification 6-3.3.1 was that all bidders would be required to obtain the limerock needed for Base Group 09 from a single vendor, Vulcan Construction Materials LP ("Vulcan"). The winning bidder would agree to pay Vulcan in accordance with a separate contract negotiated between Vulcan and the Department. The hyperlink provided in Developmental Specification 6-3.3.13 led to a document called "Aggregate Guidance" produced by the Department's State Construction Office. The front page of the Aggregate Guidance document contained "Bidder Information" consisting of a spreadsheet setting forth the Vulcan price per ton for limerock base and limestone coarse aggregate, with the price varying depending on the date and port of delivery. Between January and June 2008, the Vulcan price per ton for limerock base from both the Port of Tampa and Port Canaveral was $16.93. The Aggregate Guidance page contained additional hyperlinks with the following titles: "Aggregate Vendor Contract Usage," "Aggregate Vendor Contract," "Aggregate Vendor Projects List," "Aggregate Vendor Authorization Letter," "Aggregate Vendor Contract Frequently Asked Questions," and "Aggregate Price Adjustment Sheet." Alvin Mulford is the vice-president of Mid-State who, along with his estimator, put together his company's bid for Contract T1285. Mr. Mulford testified that his company has been bidding on Department work, and that he has never before seen a provision similar to Developmental Specification 6-3.3.1. Mr. Mulford directed his estimator to obtain clarification from the Department, to be sure that the bidders were required to purchase the limerock base from Vulcan. One reason for Mr. Mulford's concern was the "exorbitant" rate charged by Vulcan in comparison to other vendors. The restriction to a single supplier was so abnormal, and that supplier's rate was so out of line with the market, that Mr. Mulford decided to seek guidance from the Department through the question and response internet bulletin board provided by the Department for its projects. The question posed by Mid-State was as follows: Does the contractor have to use Vulcan materials for the limerock base at a rate of $16.93 per ton as stated in the Developmental Specifications 6-3.3.1? If so from which location is the material to be picked up? Is it also true that payment to the vendor (Vulcan Materials) will be due immediately upon receipt of the materials? I wanted to clarify this issue as it is unusual for the contractor to be limited to the use of only one vendor. The Department's response was as follows: The unit rate for the Material can be found at the following website: http://www.dot.state.fl.us/construction/ Aggregate/Aggregate.htm Pickup locations for the Material can be found at the following website: http://www.dot.state.fl.us/construction/ Aggregate/Aggregate.htm Payment should be issued by the Contractor to the Vendor (Vulcan Construction Materials LP) upon receipt of the materials as defined in Developmental Specification 6-3.3.1. Because the Department's response did no more than redirect him to the Department's website, Mr. Mulford decided to look at the website in more detail. He investigated the hyperlinks, including the Vulcan contract with the Department. When he clicked on the hyperlink titled "Aggregate Vendor Contract Usage," he found a document that provided as follows, in relevant part: Aggregate Vendor Contract Usage by Districts With the execution of the contract with Vulcan Construction Materials LP, contract number BDH50, Vulcan has committed to provide aggregate in the types and quantities defined in the contract (attached). The process for this contract in Districts 1, 5, and 7, is as follows: Include in the projects identified in the attached spreadsheet the appropriate special provision beginning with the July 2007 lettings. The District Specifications Engineer and District Construction Office will need to coordinate this effort. There are two special provisions for the purpose of notifying construction contract bidders of the Department's intention toward the aggregate. The first special provision is the mandatory version that will direct the bidder to obtain aggregates for the specified work from Vulcan. The second special provision provides the bidder an option to obtain its aggregates from Vulcan. * * * After these projects have been awarded, the contractor is required to notify FDOT and Vulcan a schedule of its aggregate needs for the project. After receiving this schedule, FDOT's Resident Engineer will issue written authorization to the contractor, with copy to Vulcan. This authorization is required before Vulcan will release aggregate to the contractor. Payment to Vulcan will be from the contractor. FDOT will pay cost of aggregate on progress estimates as part of the contractor's bid price for the work. The contractor is required to include in its bid price for the work the cost of the aggregate at the Vulcan rate. The Vulcan rate will be posted on the FDOT State Construction Website showing the rate. When adjustments are made to the Vulcan rate, FDOT will make adjustments in the construction contract unit price. . . . (Emphasis added.) Mr. Mulford testified that he understood the underscored language in the hyperlinked document to be a directive to the bidders and therefore a mandatory requirement of the bid specifications. He did not ask the Department for further clarification because he believed the requirement was clearly stated in the hyperlinked document. David Sadler, the director of the Department's office of construction, testified that the hyperlinked document was developed by his office to offer guidance to the districts as to the concept behind and use of the aggregate vendor contract. The document was not a part of the bid solicitation document. Mid-State's bid price was $7,429,398.44. Mid-State's price for Base Group 09 was $619,645.80, or $19.30 per square yard. This price reflected the Vulcan rate for limerock base of $16.92 plus tax and Mid-State's costs for the work associated with Base Group 09. 19. K & R's bid price was $7,370,505.24, or $58,893.20 lower than the bid price of Mid-State. K & R's price for Base Group 09 was $256,848.00, based on a stated unit price of $8.00 per square yard for limerock base. K & R's price for Base Group 09 was $362,797.80 lower than that of Mid-State, accounting for more than the differential between the overall bids of Mid-State and K & R. Marcus Tidey, Jr., K & R's vice president in charge of its Florida division, testified that K & R was well aware that the Vulcan price for limerock base was $16.93, and that K & R understands its obligation to pay that price to Vulcan should K & R be awarded Contract T1285. Mr. Tidey testified that at the time of bid submission, he cut K & R's bid price to $8.00 per square yard as a competitive strategy to win the contract. Mr. Tidey made a conscious decision that K & R would absorb the difference between $8.00 bid price and the Vulcan price of $16.93. Mr. Tidey testified that K & R needed to win this job in order not to have its crews and equipment sit idle during the economic downturn, and therefore decided to take all of its markup, roughly $250,000, out of the bid. He could have made the $250,000 cut on any item or items in the bid, but decided on Base Group 09 because the limerock base was a big item and therefore easy to cut by a large amount. Mr. Tidey also testified that the contract provides a $400,000 incentive payment for early completion of the job, meaning that K & R will be able to work "faster and smarter" and make up for the price reduction at the end of the job. Mr. Tidey testified that he obtained the Vulcan prices from the Department's website as instructed by Developmental Specification 6-3.3.1. He did not click on the hyperlinks, which appeared to reference the contract between the Department and Vulcan and therefore was of no concern to him. The Department and K & R dispute Mid-State's assertion that the underscored language of the hyperlink set forth in Finding of Fact 15 was a requirement of the bid specifications, based on Mr. Sadler's direct testimony and the underlying illogic and unfairness of requiring bidders to seek out hidden specifications. The Department and K & R concede that if the bid specifications did in fact require the bidders to include in Base Group 09 the full costs associated with obtaining the limerock base from Vulcan, then K & R's bid is nonresponsive. Developmental Specification 6-3.3.1 directed bidders to the Department's webpage for the purpose of obtaining the current Vulcan rate quote. It did not instruct the bidders to investigate the hyperlinks or to assume that the information contained therein was mandatory. Absent an instruction to bidders to review the information contained in the hyperlinks, the Department could not make such information mandatory without placing less curious bidders at a competitive disadvantage. The Department had no intent to play hide-and-seek with the bid specifications in the manner suggested by Mid-State. In addition, K & R points to three line items of the bid specifications in which the Department eliminates competition, instructing the bidders not to bid and inserting a fixed unit price and bid amount for all bidders as to those items. K & R reasonably asserts that the Department was fully capable of treating Base Group 09 in the same fashion, had it intended to require the bidders to pass through to the Department all the costs associated with obtaining the limerock base from Vulcan. However, the Department supplied the bid quantity (31,106 square yards) and left it to the bidders to determine the price per unit they would bid. K & R's bid was responsive. Nothing in the bid specifications prevented K & R from absorbing part of the cost of the Vulcan limerock base and passing the savings on to the Department, or required bidders to pass on to the Department the full costs of complying with the bid specifications regarding Base Group 09. The sole remaining issue is whether K & R's bid, though facially responsive, was materially unbalanced. The Department routinely conducts reviews of bid line items that appear "unbalanced," i.e., for which there appear to be significant differences between the price bid and the Department's cost estimate, in order to determine whether the price difference is due to a quantity error by the bidder. The Department's review confirms that the bid quantity specified on the bid blank is accurate. If a quantity error is found, the bids are recalculated using the bidders' unit prices and the correct quantities to determine whether the bid rankings would change. A bid for which there is a discrepancy between the bid and the Department's estimate is termed "mathematically unbalanced." A mathematically unbalanced bid that affects the ranking of the low bid is "materially unbalanced." A mathematically unbalanced bid is acceptable, but a materially unbalanced bid affords the bidder an unfair competitive advantage and must be rejected. The Department followed its usual procedure in analyzing the K & R bid to determine whether it was unbalanced. Philip Gregory Davis, the Department's state estimates engineer, testified that there were some unbalanced items in the K & R bid, but no quantity errors that would have changed the ranking of the bids. Richard Ryals, the project designer who conducted the unbalanced bid review, testified that the quantities were correct for Base Group 09. As noted above, K & R's low bid for Base Group 09 was an intentional strategy, not the result of a quantity error. K & R's current bonded capacity qualification with the Department is $258 million in contracts at any one time. K & R posted a bid bond, and has more than enough capacity to comfortably perform this contract. There is no economic danger to the Department in accepting K & R's low bid.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is RECOMMENDED that the Department of Transportation enter a final order dismissing Mid-State's formal written protest and awarding Contract T1265 to K & R. DONE AND ENTERED this 9th day of January, 2009, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th day of January, 2009.
The Issue The issues presented here concern the propriety of the Respondent's action in its decision to reject all bids submitted for Project 72906-9109, Duval County, thereby excluding the bid of the Petitioner which was the apparent low bid in this process.
Findings Of Fact Alfair Development Company, Inc. (Alfair), is a company owned by Maggie Alford. This company is certified as a "Disadvantaged Business Enterprise" under the terms of Chapter 337, Florida Statutes. This recognition is for benefit of contractual work done for the State of Florida, Department of Transportation. Alfair, together with two other companies who are "Disadvantaged Business Enterprises," responded to a bid opportunity from the Department of Transportation identified as Project No. 72906-9109, Duval County. The other two bidders were ILA Construction Company, Inc., of Daytona Beach, Florida, and Highway Valets, Inc., of Norwalk, Ohio. This project was for the construction of concrete sidewalks and curb cut ramps, installation and repair. The contract was for competition solely among contractors who had been certified as "Disadvantaged Business Enterprises" by the Office of Minority Programs within the Department of Transportation. As such, it is referred to as a "set-aside" job. In a "set-aside" project, bids are accepted from these "Disadvantaged Business Enterprises" in furtherance of the requirements of Section 339.0805, Florida Statutes, which mandates that not less than 10% of the amounts expended from the State Transportation Trust Fund shall be expended with small business concerns owned and controlled by socially and economically disadvantaged individuals. When the bids were opened related to Project No. 72906-9109, Duval County, Alfair was the apparent winner having offered the lowest bid among the three competitors. However, there was a problem with the bid submission by Alfair and the others, in that Alfair's bid was 70% above the pre-bid estimate of the Department of Transportation concerning the expected price that the agency would have to pay for this project. The other two bidders were even higher, but within the range of the 70% above the pre-bid estimate. The pre-bid estimate had been derived by resort to a manual at the Department of Transportation referred to as the Contract Maintenance Administration and Inspection Manual. Within that manual the pre-bid estimate is found, as it was here, by examining historical workload and/or work needs survey information and development of that information and retention of that information through a computation book. That book includes appropriate forms, square yards, per linear feet, etc., for each item of activity to be paid for in the contract. The form to be used in this process shows the project number, the county, the section number of the roadway to be worked, the method of calculating estimated quantities and specific project location, if known. In this arrangement prior contracts of a similar sort to that contemplated in this instance are reviewed in trying to anticipate the contract costs on this occasion. That approach was followed in making the pre-bid estimate in this project. When the comparison was made of those figures it was a comparison to the immediately preceding years' contract for similar work against the work called for in the subject project at hand. In addition, the Department of Transportation contacted concrete companies to make sure that the concrete cost had remained the same. It also verified that minimum wage requirements had not changed from the prior year to the year in question. At hearing, the only rebuttal which the Petitioner offered to this approach of pre-bid estimate was the attempt to present certain documents which were denied admission as evidence in that the representative of the Petitioner, James D. Alford, III, husband to Maggie Alford, was not shown to be sufficiently apprised of contracting matters to explain those exhibits and show how they would tend to rebut the method of pre-bid estimate by the Department of Transportation. The exhibits standing alone did not lend themselves to the interpretation that they were competent rebuttal. When the degree of difference between the pre-bid estimate and the quotes by the bidders was examined by employees within the Department of Transportation, the belief was expressed that the bids were so out of keeping with the pre-bid estimate as to put to question the advisability of contracting with the apparent low bidder, Alfair. The Department felt that it needed to make certain that its pre-bid estimate was not flawed in some fashion and a determination was made to undergo reevaluation of the initial perception held about the bids offered before making a decision. Nonetheless, the impression was created in the mind of Barry D. Bunn, District Contract Administrator for District II, Department of Transportation, that he was expected in his employment to notice that the bids had been rejected. As a consequence on October 25, 1988, the bidders were advised that all bids were rejected for the project. On that same date, an advertisement was placed in the local newspaper that the project was being resolicited for bid purposes and through the advertisement the "set-aside" was deleted. This meant that for purposes of the re-advertisement of October 25, 1988, a general class of bidders could respond, to include "Disadvantaged Business Enterprises." Having been made mindful of this error, Bunn contacted the newspaper where the advertisement had been placed and told them to take that advertisement out of circulation. This occurred on October 26,1988. On that same date further correspondence was directed to the bidders, to include Alfair, in which it was stated that the bids had not been rejected, identifying that the bids were undergoing a reevaluation process. That reevaluation process did not change the initial impression by the Department of Transportation concerning the quotations received as being too far in excess of the Department's pre-bid estimate. Consequently, on November 1, 1988, a further notice of bid rejection was dispatched. That notice did not describe the reason for the rejection, but upon inquiry Mr. Alford was informed that the basis of the rejection was that the bid quotations were too costly when compared to the pre-bid estimate. Under inquiry the Department of Transportation did not identify the details of that explanation in the sense of saying what items they resorted to for drawing that conclusion and the Alfair company did not seek to gain a further explanation of their reasoning through prehearing discovery. The Department of Transportation had refused to give any further information to the Petitioner about this in the course of the telephone conversation between Mr. Alford and an employee in the Lake City, Florida Office of the Department of Transportation based upon the Department's belief that Section 337.168, Florida Statutes exempts it from having to state the pre-bid cost estimate until a contract has been entered into concerning the project. Nonetheless, it was revealed in the course of the hearing what the difference between the bid quotation of Alfair and the pre-bid estimate had been, as well as identifying the methods for deriving that difference. When Alfair received the notice of rejection of its bid it filed a timely notice of protest followed by a timely petition in protest. In addition, the Petitioner posted the appropriate amount of bond under Section 337.11(3)(b), Florida Statutes, to allow it to pursue this case. The pleadings by the Petitioner are not particularly informative but the sum and substance off the allegations as demonstrated in those pleadings and as set forth by remarks of the representative at hearing, identify the belief held by the Petitioner that the Department of Transportation in rejecting the Alfair bid has been unjust, illegal, dishonest and arbitrary. Moreover, Alfair through its representative found fault with the refusal to reveal to him over the phone the methods of arriving at the pre-bid estimate and the general belief that the Department allows the participation in the bidding process and in the award of contract related to "Disadvantaged Business Enterprises" of persons who are not registered or licensed as contractors through the offices of the Department of professional Regulation within the State of Florida. None of these claims were shown to be meritorious through the proofs submitted at hearing. The Department of Transportation seeks the award of costs under the provisions of Section 337.11(3)(b), Florida statutes. The evidence in this hearing reveals that the salaries of the two witnesses who testified for the Department of Transportation, namely Russell O. Davis and Barry D. Bunn, were $125.80 and $130.00, respectively, per day. These employees were involved in the hearing process for one day. In addition to salary costs the State had to pay these employees $62.50 each for per diem allowance in that the witnesses were from out of town. The cost of attendance at hearing by the court reporter is $67.50.
Recommendation In consideration of the facts found and the conclusions of law reached, it is RECOMMENDED that Final Order be entered which rejects all bids and allows the re-advertisement of Project No. 72906-9109, Duval County. DONE and ENTERED this 28th day of March, 1989, in Tallahassee, Leon County, Florida. CHARLES C. ADAMS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of March, 1989. APPENDIX Petitioner has submitted a Memorandum in which an indication is given concerning the Project 72906-9109, Duval County, as to the scope of that project-and an explanation in the mind of the representative of Petitioner as to the reason for "set-aside" projects. An accusation is made that the Department of Transportation has tried to avoid bringing black businesses into the mainstream of Florida economy. This is not borne out by the proof. An accusation is made which was not proven at hearing and is not relevant to the resolution of this dispute concerning the contributions to the Florida tax base made by the black community and businesses. This contention together with the allegation that the Department of Transportation is using tactics to deny a small percent.age of tax dollars to recirculate into the black community for economic development and by such arrangement promotes institutional slavery was not proven. Reference to rejection of all bids on October 18, 1988 is at odds with the facts of this case. Further, there is no indication in the facts of this case that for the first time in history a black-owned company was going to cross economic a threshold within the district in terms of gaining business and that the agency rejected the bids to avoid this. Further reference to the procedural history of this case and the fact that corrections had to be made to the process of notification of rejection of all bids is not sufficient reason to overturn the decision to reject all bids. Reference within the Memorandum/Argument to the need to post a bond as being done because it would cause an economic hardship on a black-owned company is rejected as a grounds of argument in that the requirement of bond is a matter of law imposed upon all companies black or otherwise. The fact that office holders within the State Legislature were called upon by the Petitioner to ascertain the status of this project and that the Department of Transportation went through the process of correcting "the initial rejection of bids in favor of a reevaluation phase, has been explained in the fact finding elated to the sequence of events and the procedures involved in rejecting all bids. Reference to the failure to describe the reasons for rejection beyond the fact that the bids were too high has been described in the- fact finding. No evidence was shown that the refusal to indicate the reason in detail or to refer to the source of the data was in the interest of somehow favoring white prime contractors over black contractors. There is some other indication within this Memorandum concerning the meeting of goals for "Disadvantaged Business Enterprises" and the concern that the Department of Transportation is using minority individuals instead of minority businesses to meet those goals. There was no indication that the Department of Transportation acted inappropriately in its attempts to gain a contract in this case, or that it generally has participated in a process which the Petitioner refers to dualism in preferring minority persons who are not licensed by the Department of Professional Regulation to engage in the construction business over those who are. Moreover, Section 489.103(1), Florida Statutes, states that the license provisions of Florida law, do not pertain to contractors who are working on bridges, roads, streets and highways and services incidental to that work. Comments about training and apprenticeship found within the Memorandum were not proven in the course of the hearing and are not sufficiently relevant to the inquiry at hand; that they need be considered in resolving this dispute. The suggestion that the Department of Transportation intends to put the contract back out for award in some arrangement other than a "set-aside" is correct in the sense of the intentions expressed in the ad of October 25, 1988; however, that advertisement was not carried forward and the oral indication was made by an official of the Department of Transportation at hearing, that the contract would remain "set- aside" if the Department were allowed to readvertise at some point beyond the outcome of this hearing. Finally, the suggestion that if the second bidder in this case had been a non-black company or individual, the Department would have awarded the project to that entity was not borne out in the proof. Respondent's facts are subordinate to the facts found. COPIES FURNISHED: James D. Alford, III 1348 Davis Street Jacksonville, Florida 32209 Marilyn McFadden, Esquire Department of Transportation 605 Suwannee Street, M.S.-58 Tallahassee, Florida 32399-0458 Kaye N. Henderson, Secretary Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0450 Thomas H. Bateman, III General Counsel Department of Transportation 562 Suwannee Street Tallahassee, Florida 32399-0450
The Issue The issue to be determined is whether Respondent's proposed award for ITB 09-22 for Building 14B renovation is contrary to law, against the University's governing statutes, rules or policies or the specifications of the invitation to bid.
Findings Of Fact The University of North Florida published its Notice of Bid/Request for Proposal in reference to ITB #09-22 entitled "GC's for Building 14B Renovation" on December 19, 2008, with a submission deadline of January 27, 2009. The opening date was eventually extended to January 30, 2009. There were four addendums to the ITB #09-22 Project. The Notice of Bid/Request for Proposal document contained the following provisions: This project consists of the following scope of work: The work includes all labor, supervision, equipment, and materials required to execute the Contract Documents in two phases for the tenant build-out of the existing UNF Building 14-B (approximate square footage 9742). The work includes, but is not limited to, demolition of all interior walls, finishes, mechanical, electrical, plumbing and communication components as well as a new exterior curtain wall system. Exterior construction will include new glazing in aluminum curtain wall. Interior construction will include new gypsum wallboard partitions with metal stud walls, millwork, suspended acoustical and gypsum wallboard ceilings, wood and metal doors in hollow metal frames, coiling overhead grilles, toilet partitions and vanities. Interior finishes include carpeting, resilient tile, ceramic tile, painting, and window treatments. Mechanical work includes installation of new Owner provided HVAC units with ductwork and all necessary connections to the UNF Central Plant chilled water system. Plumbing includes new piping and fixtures for the tenant build-out and renovation of the group male and female restrooms. Electrical work includes new wiring, devices and lighting for the new tenant build-out. Successful bidders must have demonstrable previous experience with the described systems and technical requirements. All bidders must be qualified at the time of the bid opening in accordance with the Bidders Qualification within the ITB 09-22 Bid documents. . . Article I, Section 2 includes a heading in bold stating "Qualification Criteria." This section states: Participants must qualify to bid on this project. UNF will utilize the following criteria to qualify the general contractors within this ITB. The information must be completed on the UNF Qualifications Form provided (page 10-11): Bonding: Demonstrates a bonding capacity of at least $2 million dollars and has an A.M. Best Rating of "A-V" or better. Licenses: Company is licensed to do business in the state of Florida and approved by the US Department of Treasury listing as an acceptable surety. Project references: Company has successfully completed at least 3 commercial construction projects of more than $1 million dollars each in the past three (3) years. List 3 such projects to include project name, client name, completion date, location, project value, role in project. Reference: Project name, owner, owner's representative name/phone number, completion date and construction cost. Years of experience: Company has a minimum five (5) years of GC experience under the current company name. The directions for the General Contractor's Qualification Summary, under Related Experience, reiterated that the bidder was to list "No more than 4 projects of comparable type, size and complexity. (1) Project must be for a college/university)." Addendum I for the Project, issued January 9, 2009, clarified that the requirement for having completed successfully a project of similar size and scope at a Florida University in the last three years is a qualification factor for this project. Addendum II, issued January 12, 2009, removed the requirement for bidders to have completed one project for a college or university. The other two addenda did not address contractor qualifications. Petitioner, Core Construction Company (Core Construction or Petitioner) bid in response to the ITB. Approximately 19 other bidders also responded. Core Construction was the apparent low bidder on the project, with a bid of $1,073,000. There was some concern expressed by the architect reviewing the bids because the bids were all within ten percent of each other for the top bidders, with the bidders 2-10 being within six percent of each other. In an e-mail to Dianna White, the Senior Buyer for UNF purchasing, Mr. Norman stated: Overall there was a 20% range in bid prices which I attribute to a significant difference in the size, quality and abilities of the contractors that bid this project. The apparently low bidder was $60,516 below the second low bidder and $83,000 below the third low bidder. This is a significant concern since there is only $46,484 between the second and fifth low bidders. I suggest the apparent low bidder be contacted and asked if they feel comfortable with their bid, because it appears to me they are missing something significant in their pricing. Purchasing should also carefully review their current financials and current bonding capacity if this is allowed. Project reference checks, price verification against the architect's construction estimate and bonding checks were performed with respect to the four lowest bidding companies: Core Construction, Pooley Contracting, Rivers & Rivers and Warden Construction. Pooley Contracting, the second-lowest bidder, was disqualified as non-responsive because its bid package did not include a bonding letter. Core provided the names of three completed projects that were valued at over one million dollars. Dianna White called each of the references provided, not only for Core but for three of the four lowest bidders. The same questions were asked of each reference for each company: 1) Was the project on time and within budget; 2) Did the project run smoothly; 3) Were project issues handled; and 4) Would you use the contractor again. Calls related to Pooley Contracting were not completed because it was disqualified as non-responsive. While the references for Rivers & Rivers and Warden were consistently good, two of the three references received for Core were not. Ms. White described them as the most "strongly negative" references she had ever received. In particular, the references indicated difficulty in completing jobs within budget and on time, which the Respondent viewed as the basis for determining whether a contractor had successfully completed a project. Two of the references indicated that they would not use the contractor again, or as one put it, "not if there was any way around it." Based on the recommendations received, the Purchasing Office for the University recommended that Core Construction be disqualified for failing to demonstrate successful completion of three projects over one million dollars that were similar in scope. Because Pooley Construction was also disqualified, the Purchasing Department recommended that the Project be awarded to the third-lowest bidder, Rivers & Rivers. The recommendation to award the project to Rivers & Rivers was accepted by the Vice President of Administration and Finance, and on February 18, 2009, a Notice of Award issued identifying Rivers & Rivers as the company receiving the award. On February 19, 2009, Core Construction notified Respondent that it intended to protest the award of the Project to Rivers & Rivers. On February 24, 2009, Core Construction provided a $10,000.00 surety bond and a written protest of the award. The basis of the protest was two-fold. First, Core Construction contended that Rivers & Rivers did not meet the qualification criteria set out in the ITB, because it was did not have a minimum of five years of general contractor experience under the current company name. Second, Core felt that the poor references received should not be a basis for disqualification. Upon receiving the bid protest, Respondent contacted Rivers & Rivers to verify its licensure status. Upon inquiry, it was determined that while the principals of the company had over 30 years of experience, the Rivers & Rivers entity had not been licensed under that name for the requisite five years. While no action has been taken while this bid protest is pending, Respondent indicated its intention to withdraw the award from Rivers & Rivers and award the contract instead to the next lowest bidder. The procedures used by the University in determining the appropriate award were not contrary to law, against the University's governing statutes, rules or policies or the specifications of the invitation to bid. It was consistent with University policy to check references for projects of similar scope and size. Therefore, it was appropriate to ask for and check references for projects of over one million dollars. There is no indication that any bidder questioned what the University would consider as successful completion of a project. The time for questioning this issue would have been when the specifications were issued, consistent with Article I, Section 7 of the ITB. Having a project come in on time and within budget is a reasonable measure of successful completion. It is not the same as "substantial completion," which generally refers to a point of time in the construction process, not the final completion of the project.
Recommendation Upon consideration of the facts found and conclusions of law reached, it is RECOMMENDED: That the President of the University of North Florida, pursuant to his authority under Board of Governor's Regulation 18.002, enter a final order dismissing Petitioner's written protest. DONE AND ENTERED this 30th day of April, 2009, in Tallahassee, Leon County, Florida. S LISA SHEARER NELSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 30th day of April, 2009. COPIES FURNISHED: Jay H. Chung Core Construction Company, Inc. 4940 Emerson Street, Suite 205 Jacksonville, Florida 32207 Paul Christopher Wrenn, Esquire University of North Florida J.J. Daniel Hall, Suite 2100 1 University of North Florida Drive Jacksonville, Florida 32224 John A. Delaney, President University of North Florida J.J. Daniel Hall, Suite 2800 1 University of North Florida Drive Jacksonville, Florida 32224
The Issue Whether Respondent's Notice Of Intent To Award RFP-DOT-91/92-1005 to OHM Remediation Services Corporation is fraudulent, arbitrary, illegal, or dishonest.
Findings Of Fact By RFP-DOT-91/92-1005, the Florida Department of Transportation (DOT), Respondent, sought bid responses to provide equipment and services on an as needed basis to assess and/or clean up contaminants in rights-of-way to be acquired for road construction projects. Principal contaminants envisioned were those resulting from abandoned and leaking petroleum tanks or other business whose waste disposal threatened ground water in the area with contamination. The Requests For Proposals (RFP) provided for technical proposals and price proposals to be submitted for evaluation. The technical evaluation is the process of reviewing the proposer's Executive Summary Management Plan and Technical Plans for understanding the project. The price evaluation is the process of examining a prospective price without evaluation of the separate cost elements and proposed profit of the potential provider (Exhibit 3). The only issue here is the price proposal. In evaluating the Price Proposals, the RFP (Exhibit 3, Section 1.16.2) provided: The Department will determine a "typical project" prior to receipt of proposals. The District Procurement Office will compute costs for the "typical project" based on fees submitted by each proposer. All responsive bid proposals will be scored in relation to the lowest computed cost for the "typical project" using the following formula: (Lowest "Typical Project" cost - by subject "Typical Project" cost) x 40 = Awarded points for price proposal. The "typical project" was prepared by Raymond Nottingham, District I Contamination Coordinator, prior to the proposals being received and opened. Although the exact content of the typical project was not included in the RFP, bidders were informed of the typical type of project they could expect to encounter under the contract during the prebid meeting and in the RFP. The price evaluation was done by matching up the prices offered by the bidders in their price proposals to the items and tasks listed in the DOT's typical project to come up with the bidders typical project cost. This is the first RFP for remediation services offered by DOT District I. In preparing this RFP, the administrative section of the statewide RFP earlier consummated by the department was utilized; however, for more specific pricing bids the price part of the RFP was largely adopted from a similar RFP prepared by DOT District VI in Miami, Florida. As a result of mixing the two RFPs, a slight possibility existed that some proposers would follow the more general descriptions allowed in the earlier statewide RFP rather than the more specific provisions of the District VI RFP. However, a careful reading of the instant RFP would have eliminated any such confusion. Section 1.17.3 of the RFP provided in pertinent part: The Price Proposal information is to be submitted in a separate sealed package marked "Price Proposal Number RFP-DOT- 91/92-1005.(sic) The Price Proposal information shall be submitted on the forms provided in the Request for Proposal or on Proposers' own forms provided the Department format is followed. The Department reserves the right to reject any proposal that is not submitted in this format. The format included in the RFP was broken down into the following classifications: Labor Classification, Heavy Equipment, Mobile Equipment, Water Equipment, Personal Protective Clothing and Equipment, Drilling, Field Analytical Equipment, Treatment Equipment, and Other. The format further indicated one fee for each item listed under the classification at an hourly rate and overtime hourly rate. The proposal submitted by Petitioner included prices for equipment offered under the following classifications: Trucks and Trailers, Personal Protective Equipment, On-Site Recovery and Treatment, Sampling and Testing Equipment, Construction and Excavation Equipment, Miscellaneous Equipment, Rental Equipment, and Expendables. The proposal submitted by Petitioner contained no price for an air stripper or crane. It lists three prices for three sizes of carbon cells, three prices for three sizes of submersible pumps, three prices for three sizes of pools, two prices for drums, three prices for pool liners, separate prices for hood and suit of protective clothing, and three prices for boots. Petitioner was the only proposer of the 17 submitting proposals that failed to submit a price for an air stripper and crane. Several proposers omitted prices for items on which the other proposers submitted a price. In attempting to keep all bidders in the process by not declaring their bid nonresponsive while being fair to all other proposers, the Department adopted different procedures for different items. Generally, when a proposers omitted a price for a particular piece of equipment, the Department inserted the highest price received from other proposers for that piece of equipment in the proposal in calculating the total bid. On other occasions where the proposer submitted more than one price and did not select the price himself, the Department averaged the prices submitted and used that figure to calculate the price for that item. Where there was obviously a lot of confusion and a wide disparity in the proposals as in establishing well point systems and quality control blanks, the Department omitted those items in calculating the prices. In totaling the bids received, only the daily rate offered was used because the RFP specified only a daily rate, and all proposers did not submit weekly and monthly rates. Part of the confusion stemmed from other parts of the RFP which did indicate that weekly and monthly rates were desired. However, since the other section did not require the submission of weekly and hourly rates, the Department in evaluating the bids did not use those rates in determining the bid price. Petitioner contends that the air stripper and crane to be used on a project can vary widely, and it is not practicable to submit a proposal for a fixed price for such an item. However, it is significant that Petitioner was the only proposer that failed to submit a price for these items. Intervenor utilized the bid forms provided with the RFP and, although Intervenor in its supplementary material listed varying prices for different sizes of the same item or different materials, it entered one price, usually the lowest, on the bid form for calculating its bid. Petitioner contends that had Respondent brought forth the lowest price for items Petitioner submitted several prices on, and disallowed the prices on air strippers and cranes, then Petitioner's bid would have been lower than the Intervenor's bid. However, in the final ranking of proposers, Petitioner stood fifth. No evidence was presented that had Petitioner's contentions been granted and applied to all proposers that Petitioner's proposal would have been lower than the other bidders whose proposals were initially deemed superior to Petitioner's proposal. By failing to follow the format contained in the RFP Petitioner's proposal was not responsive.
Recommendation It is recommended that a Final Order be entered dismissing Westinghouse Remediation Services, Inc. protest to the award of RFP-DOT-91/92-1005 and OHM Remediation Services Corporation. DONE and ORDERED this 12th day of May, 1992, in Tallahassee, Florida. K. N. AYERS Hearing Officer Division of Administrative Hearings The Desoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of May, 1992. APPENDIX Proposed findings submitted by Respondent and Intervenor are accepted. Those not included in Hearing Officer's findings were deemed to be unnecessary to the conclusions reached. Proposed findings submitted by Petitioner are accepted except as noted below. Those not noted below or included in Hearing Officer's findings were deemed to be unnecessary to the conclusions reached. 8. Rejected that Petitioner's price proposal followed FDOT format. 22. Rejected. 28. Rejected. Additional reasons for rejection was the wide fluctuation in prices indicating the bidders did not understand the scope of the item. 37. Rejected. Although an inappropriate substitution was selected, the price for the item was below the maximum price offered for a crane. Accordingly, Petitioner benefited from the decision to substitute an item rather than use the highest price offered. 39. While it is true that OHM and Petitioner were the only bidder submitting weekly and monthly rates the reason for FDOT using only daily rates. See HO #13. 43. Rejected. 45. Rejected. See HO #13. 47. Rejected. Table 1. Rejected. This evidence was not submitted at the hearing. COPIES FURNISHED: Neal Smith, District Manager Westinghouse Remediation Services, Inc. 675 Park North Boulevard Building F, Suite 100 Clarkston, GA 30021 Susan P. Stephens, Esquire Department of Transportation 605 Suwannee Street Tallahassee, FL 32399-0450 Vasilis C. Katsafanas, Esquire Post Office Box 1873 Orlando, FL 32802 Ben G. Watts Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, FL 32399-0458 Thornton J. Williams General Counsel Department of Transportation Haydon Burns Building 562 Suwannee Street Tallahassee, FL 32399-0458
The Issue At issue in this proceeding is whether the decision of respondent, Department of Transportation (Department), to award the subject bid to intervenor, The Walsh Group, Ltd., Inc. and Subsidiaries d/b/a Archer-Western Contractors, Ltd. (Archer-Western), comported with the essential requirements of law.
Findings Of Fact The bid process In June 1995, the Department of Transportation (Department) issued an invitation to bid (ITB), State Project Number 93280-3504, Contract Number E- 4866, for the repair and rehabilitation of the Royal Park Bridge, a two span, four leaf bascule bridge, which spans the Intercoastal Waterway and connects the town of Palm Beach to West Palm Beach, Palm Beach County, Florida. Prospective bidders were contacted through a bid solicitation notice, which was sent to prequalified contractors, and interested firms ordered bid packages, which included plans and specifications. The subject project was experimental, and was an effort to identify the most cost-effective means of repainting bridges that contained, inter alia, lead-based paint, a hazardous material, while minimizing exposure of workers and the public as well as the environment (the Intercoastal Waterway), to the hazardous materials. The technical specifications or capabilities of the equipment to be used to abrade and prepare the bridge surfaces for repainting, keeping in mind the objective of the project, were developed by the Department's consultant, Kenneth C. Clear, and are noted in section 560, subsection 1.01.1, of the specifications, discussed infra. At the time, Mr. Clear was aware of one system, the "Cavi-Tech" or "Cavi-Blast" method, a proprietary system devised by Cavi-Tech, Inc., that could comply with the technical specifications, but did not know of any other company that had a similar process. Consequently, in drafting the technical requirements at issue in this bid challenge, discussed more fully infra, he identified the "Cavi-Blast" system of Cavi-Tech, Inc., as capable of satisfying the technical requirements, and further provided, at the bidder's election, for the use of alternative equipment if it could be shown to meet the surface preparations standards described in the ITB. Pertinent to this case, Section 560 of the specifications, entitled Repainting Exposed Steel, at page 560-1 of the ITB, specified the following technical requirements for surface preparation equipment: Surface Preparation Equipment Surfaces shall be abraded and prepared for recoating using an energy enhanced water jet generated by equipment capable of sustained operation at pressures in excess of 17,000 psi. Nozzles shall operate using resonation and cavitation technology. Production rates shall be at least 600 square feet per machine and production shift in the case of full coating removal (CB-4 per section 1.2), and 1,500 square feet per machine and production shift for sweep- off blasts which remove all oil, grease, dirt, loose paint, loose rust, rust scale and loose mill scale, and profile the remaining paint (CB-1 per section 1.2). The equipment shall include closed-loop water handling and filtration systems capable of repeated reuse of blast water and on-site treatment of the water upon completion such that it is rendered non-hazardous. Abrasives, steel shot and/or chemical strippers shall NOT be used. The surface preparation equipment shall be capable of achieving the surface preparation standards described in section 1.2, and document ation of its successful use on at lest 10 similar bridge or industrial structures totaling at least 250,000 square feet shall be submitted with the bid. Additionally, detailed project documentation and air monitoring historical data from at least 5 projects in which paint containing a lead primer was completely removed without the use of negative pressure enclosures, shall be submitted with the bid. These data shall show conclusively that, on each of the projects, the lead exposure to individuals WITHOUT breathing apparatus located 5-feet and further from the water jet nozzle was less than the OSHA action level (i.e. the air qualified as non-hazardous, breathable air in accordance with Code of Federal Regulations 29 CFR 1926.62 "Lead") when the equipment was operated at full capacity for at least 8-hours. The Cavi-Tech, Inc., Inc. (2108 Moon Station Drive, Kennesaw, Georgia 30144; phone Number 404-424-4015; fax Number : 404-424-4009) "Cavi-Blast" system meets the above requirements. The ITB package did not require, apart from any implications that may be drawn from the foregoing provisions, that the bidder specify the type of surface preparation equipment it proposed to use, and no form was included with the bid package on which such election could be denoted. The bid package did include, however, a standard proposal to be executed by the bidder, which bound the bidder "to perform all necessary work, as provided for in the contract, and if awarded the Contractor [Bidder] to execute the contract within 20 calendar days after the date on which the notice of award has been given." The ITB further required a proposal guarantee, payable to the Department, of not less than five percent of the total actual bid, "which guarantee is to be forfeited as liquidated damages if . . . the Proposal is accepted [and] the Bidder . . . fail[s] to execute the attached Contract under the conditions of this proposal. " On August 17, 1995, after the pre-bid conference, the Department issued Addendum Number 1 to the ITB, which included the following clarification as to the painting specifications for the project: Surface preparation equipment requirements are specified in Section 1.01 of the painting specifications. Cavi-Tech, Inc. is indicated as a company having equipment and experience meeting the requirements of this specification section. Other companies meeting the requirements of Section 1.01 can bid on this project. In response to the ITB, the Department received five bids for the project. The lowest bid was submitted by Archer-Western, $2,868,816.35, and the second lowest bid was submitted by Coastal, $2,930,461.68. The three other firms that bid on the project were PCL Civil Contracts, Inc. (PLC), with a bid of $2,943,370.20, Gilbert Southern Corp. (Gilbert), with a bid of $2,967,928.10, and M & J Construction Co. of Pinellas County (M & J), with a bid of $3,274,867.17. The bid price proposal submitted by each bidder contained various items which were tallied to derive the total amount bid. Item Number A560 1 was for painting structural steel, and Archer-Western listed a price of $425,300, Coastal a price of $500,000, PCL a price of $350,000, Gilbert a price of $450,000, and M & J a price of $575,348.45. Pertinent to this case, while Archer-Western did secure a quotation from Cavi-Tech, Inc., for Cavi-Blast and coating services, as well as historical data regarding its use, it did not include such documentation with its bid. Consequently, the bid submitted by Archer-Western, as well as the bid of PCL, contained no information in response to subsection 1.01.3, regarding surface preparation equipment. Contrasted with those bids, Coastal, in what it perceived as the appropriate response to subsection 1.01.3, included information from Cavi-Tech, Inc., on the Cavi-Blast system. Gilbert and M & J likewise included documentation on the Cavi-Blast system. The Department, following its evaluation, deemed the five bids responsive, and on October 4, 1995, posted notice of its intent to award the contract to Archer-Western. Coastal timely protested the proposed award (DOAH Case No. 95-5702BID). On October 9, 1995, the Department notified all bidders that it was rescinding its notice of intended award and proposed to reject all bids. Coastal timely protested such decision (DOAH Case No. 95-5703BID).3 Finally, on October 24, 1995, the Department, following reconsideration of its position, resolved to rescind its rejection of all bids and, consistent with its initial decision, award the contract to Archer-Western. Coastal timely protested such award (DOAH Case No. 95-5701BID). The bid protest Here, Coastal contends that Archer-Western's proposal (bid) was not responsive to the ITB because it did not include documentation in response to subsection 1.01.3 of the ITB. By such failure, Coastal suggests Archer-Western failed to commit to using the Cavi-Blast system or identify an alternative system it would use and, therefore, its bid was at material variance from the ITB. That variance, Coastal avers, accorded Archer-Western the opportunity to reevaluate its bid, after bid opening, and then decide whether to adhere to is bid or refuse to abide its bid without penalty due to its non-responsiveness. Contrasted with Coastal's perception of subsection 1.01.3, the Department views that subsection, when read in pari materia with subsections 1.01.1 through 1.01.4, as only requiring documentations when the bidder proposes to use surface preparation equipment other than the Cavi-Blast system. Indeed, the Department observes, it would be superfluous to include documentation demonstrating that the Cavi-Blast system was capable of achieving the surface preparation standards when subsection 1.01.4 specifically states that the Cavi- Blast system meets requirements. Accordingly, where, as here, the bidder does not provide any documentation in response to subsection 1.01.3, the Department contends it may be fairly implied, based on the bidder's agreement in the proposal "to perform all necessary work, as provided for in the contract," that it has proposed to use, and is bound to use, the Cavi-Blast system. Consequently, the Archer-Western bid was, in the Department's opinion, responsive to the ITB. Reading the provisions of subsections 1.01.1 through 1.01.4 in para materia, it must be concluded that the Department's conclusion in this case is supported by logic, and that its decision to award the contract to Archer- Western did not depart from the essential requirements of law.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered dismissing Coastal's protests and, more particularly, its protest of the award of the subject bid to Archer- Western. DONE AND ENTERED this 26th day of February 1996 in Tallahassee, Leon County, Florida. WILLIAM J. KENDRICK, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of February 1996.