Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
OLD TAMPA BAY ENTERPRISES, INC. vs DEPARTMENT OF TRANSPORTATION, 98-005225BID (1998)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Dec. 01, 1998 Number: 98-005225BID Latest Update: Apr. 13, 2000

The Issue The issue presented for decision in this case is whether Respondent, the Florida Department of Transportation ("FDOT"), acted contrary to the agency’s governing statutes, rules or policies, or the proposal specifications, in rejecting the proposal of Petitioner, Old Tampa Bay Enterprises, Inc. ("Old Tampa Bay"), to RFP-DOT-97/98-1003, Bridge Tending/Maintenance and Repair Services for Five Movable Bridges, Sarasota and Manatee Counties (the "RFP" or "RFP 1003"), and awarding the contract to Intervenor, General Electric Industrial Systems ("GE"). GE also raises the issue whether Old Tampa Bay lacks standing because it submitted a materially false or fraudulent proposal.

Findings Of Fact Based on the oral and documentary evidence adduced at the final hearing, and the entire record in this proceeding, the following findings of fact are made: On or about April 10, 1998, FDOT issued RFP 1003, requesting proposals for a bridge-tending, maintenance and repair service contract for five movable bridges within Manatee and Sarasota Counties. The contract would run for a period of one year, with an option for two annual renewals. FDOT contemporaneously issued RFP 1004, for the performance of identical bridge tending, preventive maintenance and repair services on four other movable bridges in Sarasota County. The RFP required, among other things, that proposers must employ an experienced bridge tender supervisor and an experienced registered electrical engineer. The RFP required that the contractor must be licensed to perform electrical and mechanical work in the State of Florida, and that a copy of the license be submitted as part of the proposal package. RFP 1003, Section 1.7.5. (In this and some other sections of the RFP, FDOT employed the undefined term "Consultant" rather than the term "Contractor" or "Proposer" used through the bulk of the RFPs. Absent a clarifying explanation, it is assumed that all three terms are used interchangeably.) The RFP required the proposers to provide the names of "key personnel," a resume for each of these individuals, and a description of the functions and responsibilities of each key person relative to the task to be performed. The approximate percent of time to be devoted exclusively to this project was also to be provided. FDOT’s prior written approval was required for the removal and substitution of any of the key personnel proposed. "Key personnel" included project engineers, bridge superintendents, mechanics, and electricians. Under the heading "preventive maintenance," the RFP required the proposers to provide "sufficient and competent personnel to perform the inspection, troubleshooting and work for all bid item requirements." The electrician must be "a licensed electrician with experience in industrial maintenance and troubleshooting." RFP 1003, Exhibit A-3, Section 3.0. The RFPs incorporated by reference the "Bridge Operations and Maintenance Manual" (the "Bridge Manual"), an FDOT document establishing procedures for bridge operations and maintenance requirements statewide. The Bridge Manual set forth the following qualifications for electricians: All electricians working on movable bridges or electrical equipment on any bridge must hold at least a journeyman electrician’s license in at least one Florida county and have skills in industrial electrical work. Ability to read and understand blueprints and written instructions. Ability to communicate effectively orally and in writing. Ability to plan, organize and coordinate work assignments. Ability to install, alter, repair and maintain electrical systems, equipment and fixtures. Bridge Manual, pages 2-3. Another section of the Bridge Manual elaborated on the minimum qualifications for electricians as follows: All electricians working on movable bridges or electrical equipment on any bridge must hold at least a journeyman electrician’s license in at least one Florida county and have at least two years experience in industrial electrical work. Vocational/training in industrial electricity can substitute at the rate of 720 classroom hours for each year of the required experience. After employment, they should attend the Bridge Inspection school and Movable Bridge Inspection school. They should also receive continuing training on motor controls, National Electric Code and applicable safety training. They should be able to read blueprints, and written instructions, communicate effectively, be able to plan, organize, and coordinate work assignments, and have the ability to install, alter, repair and maintain electrical systems, equipment and fixtures. Bridge Manual, pages 2-17 through 2-18. The RFP awarded a maximum of 100 points to responsive proposals. A maximum of 60 points could be awarded for the technical proposals, which were scored by a three-member technical committee that included Hendrik Ooms, FDOT’s assistant maintenance engineer for District One. Each member of the committee scored the proposals independently. Their scores were then averaged to arrive at the final technical score. The RFP listed Richard Marino, the head of contracts for District One, as the project manager who should receive all technical questions from prospective proposers. Regardless of the formal designation, Mr. Ooms was in fact the project manager and the person capable of answering technical questions. The technical proposal scoring subsumed a maximum of 35 points for the "management plan," including 20 points for identified "key personnel." A maximum of 35 points could be awarded for the price proposal. The low price proposal received the maximum 35 points, with the remaining proposals scored according to the formula: (Low price/proposer’s price) x Price points = Proposer’s total points. The technical committee was not aware of the contents of the price proposals prior to scoring the technical proposals. Finally, proposers could obtain 5 preference points for Disadvantaged Business Enterprise (DBE) participation of at least 10 percent of the total dollar amount of the contract, or 2 preference points for DBE participation of between 5 and 10% of the total dollar amount. On or about May 11, 1998, three companies submitted proposals for RFP 1003 and 1004: GE; Old Tampa Bay; and C & S Building Maintenance Corporation. GE is the incumbent vendor for these contracts. Until this bid, Old Tampa Bay was a subcontractor to GE on these contracts. On May 22, 1998, FDOT posted the proposal tabulations indicating the intended awardees of the two contracts. Old Tampa Bay was the apparent awardee of the contract for RFP 1003, the contract at issue in this case, with a total score of 79.67 points. GE was the second high scorer, with 79.45 points. GE was the apparent awardee of the contract for RFP 1004. As to RFP 1003, the averaged technical score for Old Tampa Bay was 39.67 points. The averaged technical score for GE was 49 points. All three members of the technical committee awarded GE more points than Old Tampa Bay, though Mr. Ooms saw a greater difference between the two bids than did the other committee members, Richard Marino and Kenneth Clark. Mr. Marino awarded 56 points to GE and 52 points to Old Tampa Bay. Mr. Clark awarded 53 points to GE and 47 points to Old Tampa Bay. Mr. Ooms awarded 38 points to GE and 20 points to Old Tampa Bay. Despite the difference in the technical proposals, Old Tampa Bay was named the intended awardee for RFP 1003 on the strength of 35 points for its significantly lower price proposal ($539,915 per year, versus $621,340 per year for GE) and obtaining the full 5 points for DBE participation. GE was awarded 30.45 price points according to the RFP formula and obtained no DBE points. No formal protest having been received, FDOT moved forward to the next step in the award process. The agency sent substantially identical letters to Old Tampa Bay as the intended awardee of the contract for RFP 1003 and to GE as the intended awardee of the contract for RFP 1004. The letters, dated June 15, 1998, and signed by Felipe Alvarez, FDOT’s purchasing agent, informed the vendors that they had each proposed the same people as "key personnel" who would devote 100 percent of their time to the project. This situation "concerned" FDOT, as these persons obviously could not devote 100 percent of their time to RFP 1003 as employees of Old Tampa Bay and 100 percent of their time to RFP 1004 as employees of GE. The letters requested each of the vendors to clarify the employment of the following persons: Mr. W. Bruce Chapman, whom GE had identified as its bridge superintendent and Old Tampa Bay had identified as its project manager; Mr. Gary Berkley, whom GE had identified as its mechanic and Old Tampa Bay had identified as its primary mechanic; Kelly Green, whom both GE and Old Tampa Bay had identified as primary electrician; and John Vance, whom both GE and Old Tampa Bay had identified as supporting electrician. The letters concluded with the following statement: The Proposal Package stated that if awarded the Agreement, the Consultant is to provide the services of the key personnel proposed. Removal and substitution of any of the key personnel proposed will require the Department’s prior written approval. Please advise the Department if your firm plans to provide the same key personnel or will be providing an equivalent substitution; equivalent meaning as of [sic] the same caliber, experience, and expertise or better than the individual originally proposed. (Emphasis added.) As noted in FDOT’s letter, the Old Tampa Bay proposal listed Kelly Green and John Vance as electricians. Old Tampa Bay’s proposal emphasized that Vance and Green were the current electricians performing electrical maintenance and repairs on the bridges, with nine years combined experience on the District One contract. Old Tampa Bay's proposal emphasized the ease of transition to the new contract that FDOT would enjoy should it select Old Tampa Bay: There will be no transition pain from the existing prime contractor [GE] to [Old Tampa Bay] as ALL personnel currently serving are already on the [Old Tampa Bay] payroll and have been for several years. FDOT will have no new relationships to establish or unknowns with which to be concerned. (Emphasis in original.) Old Tampa Bay’s proposal emphasized in several places that Old Tampa Bay would provide the same electricians who were already working on the bridges. In describing its technical approach to the electrical systems, Old Tampa Bay emphasized that its electricians would require no orientation before commencing work: The electrical system is a critical link in the operation of the bridge. Its maintenance is crucial to reliable operation. [Old Tampa Bay's] comprehensive maintenance program is designed to meet and exceed contract requirements. The [Old Tampa Bay] electrician (Resume attached) is knowledgeable and experienced in the performance of this program. He has performed this service under other FDOT contracts. Old Tampa Bay's proposal emphasized the experience of its electricians with respect to the electro-mechanical control systems, stating that "All [Old Tampa Bay] service personnel including electricians have been trained to work on, maintain, and troubleshoot as required each intricate system." Old Tampa Bay emphasized the experience of Vance and Green, and stated that they had "never failed to correct any problems on this system on any of the bridges in this contract." Old Tampa Bay made similar representations in regard to equipment malfunctions and computerized control systems, emphasizing the quick, successful responses by and experience of its electricians. The evidence indicated that Old Tampa Bay knew, or should have known, at the time it submitted its proposal, that John Vance had no intention of working for Old Tampa Bay on these contracts. Old Tampa Bay included Mr. Vance’s name and license in its proposal without his consent. Mr. Vance never stated orally or in writing that he agreed to be included in Old Tampa Bay's proposal. Old Tampa Bay never asked Mr. Vance’s permission to include his name as a proposed supporting electrician. Old Tampa Bay never asked Mr. Vance’s permission to include a copy of his electrical contractor’s license in Old Tampa Bay's proposal. About two weeks prior to the proposal submission date, Old Tampa Bay's president, Donald Abernathy, asked Mr. Vance for a copy of his license, but did not tell him that Old Tampa Bay intended to include the license in its proposal. Rather, Mr. Abernathy told Mr. Vance that Old Tampa Bay needed the license for purposes related to insurance. Mr. Vance refused to provide Old Tampa Bay with a copy of his license. Old Tampa Bay obtained a copy of Mr. Vance’s license by making a public records request to Manatee County, and submitted that copy with its proposal. Mr. Bruce Chapman has served for nearly four years as a bridge tender supervisor, employed by Old Tampa Bay under a GE contract with the FDOT. At the time of the hearing, Mr. Chapman was still an Old Tampa Bay employee. Mr. Chapman assisted Mr. Abernathy in trying to obtain permission of various people to use their names in Old Tampa Bay's proposal. Mr. Chapman testified that he knew from conversations with Mr. Vance that Mr. Vance did not want to work for Old Tampa Bay on the new contract. Old Tampa Bay also knew at the time of proposal submission that it had obtained no assurances from Kelly Green that he would work for Old Tampa Bay on the contract for RFP 1003. As detailed below, Mr. Green ultimately signed a letter-of-intent to work for GE on the contract for RFP 1004. Mr. Abernathy contended that Old Tampa Bay was entitled to include Vance and Green in its proposal without permission because they were Old Tampa Bay employees. However, Mr. Abernathy also conceded that Vance and Green were at-will employees, and his prior attempt to secure their permission to use their names in the Old Tampa Bay proposal was a tacit admission that Old Tampa Bay had no control over them. Further, in the fall of 1997, Mr. Abernathy attempted to obtain the signatures of Mr. Vance and several other bridge employees to a non-compete agreement for the purpose of binding them to Old Tampa Bay. Mr. Vance refused to sign the agreement. Old Tampa Bay provided payroll services to Vance and Green during their work on the bridges under GE’s existing contract with the FDOT, but Old Tampa Bay never supervised the work of the bridge electricians, never provided Vance or Green with the tools, equipment or supplies they used in their work as bridge electricians, and never had any control over the day-to- day activities of any electricians on any FDOT contract. The electricians worked on a daily basis with GE’s project engineer, Douglas Blake. Mr. Blake had trained Mr. Vance on bridge electrical equipment when the latter commenced work on the bridges. The electricians looked to Mr. Blake for technical and substantive assistance in working on the bridges. Mr. Vance testified that he considered himself an employee of GE. Mr. Green did not testify at the hearing. On June 26, 1998, both Old Tampa Bay and GE submitted responses to the FDOT letter of June 15, 1998. In a letter signed by William Trainor, contract leader, GE set forth its staffing plan for RFP 1004. GE identified the following as "key personnel" proposed for the positions discussed in the FDOT letters: John Vance as bridge superintendent (replacing W. Bruce Chapman); Bruce Morris as mechanic (replacing Gary Berkley); Kelly Green as primary electrician; and John Vance as Supporting electrician. GE attached résumés for each of these personnel. GE indicated that it would utilize PRM, Inc. as a subcontractor to secure the required contract personnel for the contract under RFP 1004, and GE attached letters-of-intent for employment for each of the named key personnel. Each of these letters was signed either by the named employee or by the president of PRM, Inc. FDOT accepted GE’s response in full. The award of the contract for RFP 1004 to GE was not protested. In a letter dated June 26, 1998, signed by Donald R. Abernathy, president, Old Tampa Bay proposed the following key personnel: W. Bruce Chapman as project manager; Gary Berkley as mechanic; Charles Adam Kenney as bridge superintendent (not mentioned in the FDOT letter); and Kelly Green as primary electrician. Old Tampa Bay attached résumés for each of these personnel. The letter made no mention of a supporting electrician. Old Tampa Bay also attached agreements of the employees to serve in their respective positions. However, the signature line on Kelly Green’s statement of acceptance was left blank. Mr. Abernathy testified that he asked Mr. Green to sign the document indicating his acceptance of employment with Old Tampa Bay, but Mr. Green refused. Mr. Abernathy did not reveal this information to FDOT, continuing to maintain that he was within his rights as Mr. Green's employer to include his name in the proposal. FDOT knew from its review of the GE submission that Mr. Green had in fact signed a letter of intent for employment with PRM, Inc. to work on the GE contract. Mr. Alvarez, the FDOT purchasing agent, acted chiefly as a coordinator and as the person ensuring that the procedural requirements of competitive bidding laws were met by FDOT. He admittedly lacked the expertise to make decisions as to the technical aspects of the project. Thus, Mr. Alvarez forwarded the vendors’ responses to Mr. Ooms, the project manager, for his evaluation. Mr. Ooms is a professional engineer, and for the past five years has supervised the operations of all nine bridges covered by RFPs 1003 and 1004. In a memorandum to Mr. Alvarez, dated July 2, 1998, Mr.. Ooms reported his findings and conclusions regarding the vendors’ submissions. As noted above, he found the GE submission acceptable in its identification of PRM, Inc. as a subcontractor and its naming of Vance, Morris, and Green as intended key personnel. Mr. Ooms found acceptable the submission of Old Tampa Bay insofar as it named Chapman, Kenney, and Berkley as key personnel. However, Mr. Ooms noted that the Old Tampa Bay submission provided no documentation of Kelly Green’s commitment to work for Old Tampa Bay. Mr. Ooms also noted that the Old Tampa Bay submission made no mention of John Vance, who had been listed as support electrician in Old Tampa Bay’s original proposal, and listed no substitute who would take over those duties. Mr. Vance had also accepted an offer from PRM, Inc. to work on the GE contract. Thus, Mr. Ooms concluded that the proposed key personnel roster submitted by Old Tampa Bay was not acceptable. By letter to Donald R. Abernathy dated July 8, 1998, Mr. Alvarez conveyed to Old Tampa Bay the "discrepancies" found by FDOT in the Old Tampa Bay submission of June 26, 1998. While stating that FDOT accepted the proposal of Chapman, Kenney, and Berkley for their respective positions, Mr. Alvarez pointed out the problems noted by Mr. Ooms as to Green and Vance. The letter concluded that "the Department still requires that your firm provide, in writing, clarification as to the positions of Primary and Supporting Electricians," and required the response by July 13, 1998. Old Tampa Bay responded by letter to Mr. Alvarez from Mr. Abernathy dated July 10, 1998. The letter provided no explanation as to Mr. Green’s unsigned agreement or Old Tampa Bay's failure to mention Mr. Vance or otherwise address the position of supporting electrician. The letter stated no objection to any of the conclusions contained in FDOT’s letter of July 8, 1998. The letter took no issue with the standard described for "equivalent" electricians. Old Tampa Bay's letter stated that it had selected Mr. Gary McCormick as its primary electrician. The letter noted that Mr. McCormick was finishing a project but would be available for this contract no later than July 27, 1998. The letter stated that while Mr. McCormick was a "skilled and valuable electrical and hydraulic specialist," he had never been required to have an electrician’s license by any prior employer. The letter requested that FDOT waive the license requirement for 90 days, during which time Mr. McCormick would obtain the required license. The letter attached Mr. McCormick’s résumé, which indicated that he had been involved with the Stickney Point bridge from September 1997 until July 1998. The résumé provided no dates for any of his other employment since 1973. The résumé indicated that most of Mr. McCormick’s electrical experience involved repair and installation of elevators. Old Tampa Bay's submission made no attempt to relate Mr. McCormick’s elevator experience to the electrical specifications of the RFP. The letter further stated that Old Tampa Bay was "actively seeking" a supporting electrician, and that Mr. Abernathy would fill the position until the search was completed over the "next few weeks." The letter gave no further indication of the status of Old Tampa Bay's attempt to locate a support electrician. The letter attached the résumé of Mr. Abernathy. Mr. Alvarez forwarded Old Tampa Bay’s July 10, 1998, letter to Mr. Ooms for his review. By memorandum dated July 15, 1998, Mr. Ooms responded to Mr. Alvarez, concluding that the proposed key personnel roster of Mr. McCormick and Mr. Abernathy as primary and supporting electricians was not acceptable. Mr. Ooms’ memorandum first addressed Old Tampa Bay's original statements in its proposal as to Vance and Green, noting that Old Tampa Bay represented both electricians as follows, in his words (punctuation and capitalization not corrected): [Mr. Green] "has worked on FDOT movable bridge contracts for the past 4 years in Sarasota and Manatee counties. His duties range from preventive maintenance to emergency repair" . . . "an intimate knowledge on the operation of bridges so that during malfunction he can use the bypass functions to keep bridge down time and repair time to a minimum." Mr. Green has a Journeyman’s electricians license. * * * [Mr. Vance] has worked on FDOT movable bridge contracts for the past 5 years in Sarasota and Manatee counties. The maintenance he performs covers the entire bridge--the gates, lock motors, drive motors, variable frequency drives, programmable controllers, contactors, limit switches, control panels and resistors." "intimate knowledge on the operation of bridges so that during malfunction he can use the bypass functions to keep bridge down time and repair time to a minimum." Mr. Vance has a [sic] Electrical Contractor’s license. Mr. Ooms contrasted Mr. Green’s qualifications with those of Mr. McCormick, whose résumé showed that he had less than one year’s experience with bridges, did not hold a journeyman electrician’s license, and thus was not "an equivalent substitution for Mr. Kelly Green." Mr. McCormick’s résumé listed his current employer as "Acutec Inc.," his position as "project electrical foreman," and stated that he was "currently finishing Stickney Point drawbridge rehabilitation project. In charge of electrical, PLC, and hydraulic systems installation, trouble-shooting, and start-up. Working closely with Gregg Martin of FDOT, Sarasota." Mr. Ooms testified that Mr. McCormick did not have the qualifications claimed in his résumé. He testified that Mr. McCormick was not in charge of electrical, PLC and hydraulic systems installation on the Stickney Point bridge. He testified that Mr. McCormick was strictly a "wire puller," with "no experience whatsoever to do this type of work." Mr. Ooms took issue with Mr. McCormick’s claim that he was "in charge" of the installation of the PLC, or programmable logic controls. Mr. Ooms testified that Mr. McCormick’s employer, Acutec, was involved with writing the PLC program, setting up the parameters, checking out the hydraulics, and performing the interfacing, but that Mr. McCormick was simply running wires from point-to-point pursuant to instructions from others. Mr. Ooms testified that he knew these facts from watching at first-hand the work being performed on the Stickney Point bridge. Mr. Ooms did not call Acutec to verify the statements in Mr. McCormick’s resume. Mr. Ooms stated that there was no need to call Acutec, as he was out on the bridge and could see for himself what Mr. McCormick was doing. PLCs, or programmable logic controls, are the means by which newer bridges are controlled by computer. The PLC sequences the computer program to constantly monitor the condition and operation of the bridge. The PLC technology is not unique to bridges. It is common in many manufacturing operations, and is in place on two of the five bridges covered by RFP 1003. The remaining three bridges have a manual relay control system. Old Tampa Bay did not dispute that PLC experience is necessary to perform the work as an electrician on this contract. Mr. Ooms noted that Mr. McCormick’s résumé claimed PLC experience, but that when the time came for the contractor to deliver the laptop computer with the PLC programs to run the renovated Stickney Point bridge, Mr. McCormick could not even run the program on the computer. Mr. Ooms testified that if one cannot run the computer program, one cannot do anything on a computer controlled bridge. Mr. Ooms’ testimony as to the qualifications of Mr. McCormick is credited. While Mr. Ooms might have confirmed his conclusions with Mr. McCormick’s employer, he cannot be found to have acted arbitrarily in relying on his own extensive observations of Mr. McCormick’s job performance. Old Tampa Bay offered no evidence to dispute the factual underpinnings of Mr. Ooms’ decision that Mr. McCormick was not an equivalent substitute for Kelly Green. Mr. Ooms’ July 15, 1998, memorandum also rejected Mr. Abernathy as the temporary supporting electrician. As quoted above, the memorandum noted Old Tampa Bay's representation that John Vance, the supporting electrician it originally proposed, has worked on FDOT movable bridge contracts for the past five years in Sarasota and Manatee counties, has intimate knowledge of these bridges, and has an electrical contractor’s license. Mr. Ooms noted that Mr. Abernathy does not have an electrical contractor’s license. Mr. Ooms also took issue with Mr. Abernathy’s résumé statement that he has acted as a bridge inspector for the past eight years for Kisinger Campo and Associates, a company that FDOT hires to perform bridge inspections. Mr. Ooms wrote that in the five years that FDOT has let out the operations and maintenance contracts, he has never "seen or known of Mr. Abernathy visiting a Sarasota or Manatee county bridge or troubleshooting a bridge problem." He testified that Kisinger Campo could not have used Mr. Abernathy as a bridge inspector because he lacked the required engineer’s license or certification as a bridge inspector. Mr. Ooms admitted that Kisinger Campo does not always tell him who is performing the inspections. Mr. Ooms made no inquiries of Kisinger Campo to verify Mr. Abernathy’s résumé. Mr. Abernathy testified that he was in fact an electrical inspector for Kisinger Campo for eight years and that in 1997 he personally performed inspections on every bridge covered by RFP 1003, including the electrical, lighting, and PLC systems. Mr. Abernathy conceded that he does not have an electrical contractor’s license. Mr. Abernathy’s testimony is credited as to his experience as a bridge inspector. In the case of Mr. McCormick, Mr. Ooms reasonably relied on his own extensive observations. As to Mr. Abernathy, Mr. Ooms attempted to rely on what he did not observe. Mr. Ooms chose to assume, without knowledge or verification, that Mr. Abernathy’s résumé was false. This assumption was arbitrary, and cannot be credited. Mr. Ooms’ decision to reject Mr. Abernathy was nonetheless reasonable. Mr. Abernathy did not possess the requisite license, and admitted that his most recent experience in actually performing bridge electrical maintenance and repair was more than twenty years ago. By letter to Mr. Abernathy dated July 17, 1998, Mr. Alvarez conveyed FDOT’s rejection of Old Tampa Bay’s proposal pertaining to the electrician positions. The reason for rejection was stated as follows: As stated within the Request for Proposal Package, if you are proposing to substitute key personnel you must provide an equivalent substitution; equivalent meaning as of [sic] the same caliber, experience, expertise or better than the individual originally proposed. . . . Please understand, the Department is looking forward in [sic] entering into an Agreement with your firm, [sic] however, it cannot accept anything less than what was originally proposed. Mr. Alvarez’ letter enclosed Mr. Ooms’ memorandum of July 15, 1998, and offered Old Tampa Bay another opportunity to submit substitute electricians no later than July 27, 1998. By letter from Mr. Abernathy to Mr. Alvarez, dated July 27, 1998, Old Tampa Bay submitted a new list of proposed substitutes. The text of the letter stated, in full: We have selected Mr. Steven Manning, Master Electrician License Number 3994, Hillsborough County to be our primary electrician. Attached is his resume. We have selected Mr. Adrian Cook as the supporting electrician, Journeyman License Number JE776, Hillsborough County. We have selected Mr. Wayne Cano as an electrician’s helper. Hillsborough County licenses have full reciprocity with Manatee and Sarasota Counties. Résumés of all three proposed employees were attached, along with copies of the relevant licenses and certificates of completion of various professional training courses. Mr. Manning’s résumé contained sketchy descriptions of the kinds of electrical work he had performed, and gave no indication that he had any experience working with computers or PLCs. Mr. Manning’s résumé revealed no experience with moveable bridge maintenance or repair. Mr. Manning had no experience as an electrician on the FDOT bridges. Mr. Manning’s résumé indicated that his experience included industrial electrical experience intermittently during eight years of electrical work. The résumé indicated "industrial and commercial electrical work," "working in fuel terminals, working with motor controls," "remodeling tenant spaces," "working with new commercial," "working with commercial remodeling, and service work," "traveling around Florida and Georgia remodeling Pizza Huts," "residential and commercial sales, estimating jobs, job foreman, billing and scheduling, handling of permits," and "working with industrial and commercial, service work, remodeling and new construction." Old Tampa Bay's submission offered no specific information or explanation of how Mr. Manning’s varied experience related to the specifications for electrical maintenance and repair in the RFP. Old Tampa Bay had obtained Mr. Manning’s name by calling an electrical company, Southern Power and Controls, and asking for recommendations of personnel with qualifications and experience equivalent to Mr. Green’s. Southern Power and Controls is an industrial electrical firm specializing in industrial controls, motor controls, switch gears, limit switches, and PLCs. Old Tampa Bay would have paid a finder's fee to Southern Power & Controls for any employees who went to work for Old Tampa Bay on this contract. Old Tampa Bay provided Southern Power and Controls with the documentation it had submitted to FDOT regarding the qualifications and experience of Vance and Green. Robert Harwell, a registered electrical engineer and principal of Old Tampa Bay, had discussions with Southern Power and Controls as to the qualifications of the candidates it sought. No person from Southern Power and Controls appeared at the hearing to explain the process by which they selected Mr. Manning. No person from Old Tampa Bay ever interviewed Mr. Manning. Mr. Manning did not testify at the hearing. Old Tampa Bay proposed Adrian Cook as a supporting electrician. Mr. Cook’s résumé indicated that he was a licensed journeyman electrician, with four years’ experience as an electrician and two years as an apprentice. Mr. Cook’s résumé indicated two years of unspecified commercial and industrial work, but no moveable bridge experience. Old Tampa Bay obtained Mr. Cook’s name from Southern Power & Controls, asking for personnel with qualifications and experience equivalent to Mr. Green’s. No person from Southern Power & Controls appeared at the hearing to explain the rationale for choosing Mr. Cook. No person from Old Tampa Bay ever interviewed Mr. Cook. Mr. Cook did not testify at the hearing. Old Tampa Bay submitted Mr. Wayne Cano as an "electrician’s helper." Old Tampa Bay did not specify what function Mr. Cano would serve or what actions he would perform as an "electrician’s helper." Neither the RFP nor Old Tampa Bay's proposal contains any mention of an "electrician’s helper." Mr. Cano’s résumé did not indicate an electrician’s license. Old Tampa Bay did not state that it had any intention to require Mr. Cano to obtain an electrician’s license. Mr. Cano’s résumé did not indicate any moveable bridge experience or experience on other FDOT projects. Again, Mr. Alvarez forwarded the Old Tampa Bay letter and attachments to Mr. Ooms for his review. Mr. Ooms provided his response by memorandum dated August 6, 1998. Again, Mr. Ooms outlined the qualifications and experience of the electricians originally proposed, Kelly Green and John Vance, as set forth in Old Tampa Bay's own proposal. Mr. Ooms wrote as follows (punctuation and capitalization not corrected): Mr. Green’s experience were [sic] listed as follows. "has worked on FDOT movable bridge contracts for the past 4 years in Sarasota and Manatee counties. His duties range from preventive maintenance to emergency repair . . . an intimate knowledge on the operation of bridges so that during malfunction he can use the bypass functions to keep bridge down time and repair time to a minimum." Mr. Green has a Journeyman’s electrician license. Mr. Vance’s experience were [sic] listed as follows. "has worked on FDOT movable bridge contracts for the past 5 years in Sarasota and Manatee counties." "The maintenance he performs covers the entire bridge-- the gates, lock motors, drive motors, variable frequency drives, programmable controllers, contactors, limit switches, control panels and resistors." "intimate knowledge on the operation of bridges so that during malfunction he can use the bypass functions to keep bridge down time and repair time to a minimum." Mr. Vance has a [sic] Electrical Contractor’s license. Mr. Green and Mr. Vance each have over four years of "on the Bridge" experience trouble shooting non functioning systems. They have worked on nine different bridges that were 30-40 years old with antique controll [sic] systems and on bridges recently rehabilitated with modern computer controlled systems. They have years of experience in reading and analyzing bridge ladder logic programs and trouble shooting problems and solutions. All these bridges were operational and any loss of service was quickly reported. An outage can easily block traffic for several miles in minutes generating calls from the sherrifs [sic] department. In addition, any breakdown in service has severe political consequences due to the Ringling bridge and Anna Maria Bridge replacement program. A problem on Ringling Bridge can cause a [sic] hour detour and missed flights. On page C-1 of the contract it states "The Contractor’s personnel that will perform the work required by this Section shall be trained and well experienced in start-up and maintenance of equipment . . . and will have headquarters within Sarasota/Manatee County" . . . On page A-3.2 is [sic] states "the Contractor shall initiate corrective action within fifteen (15) minutes following the malfunction." further down on Page C-1 of the contract "the Contractor agrees to provide men and equipment to a bridge sites [sic] within 30 minutes of notification of any emergency equipment failure". Mr. Ooms contrasted the experience and qualifications of the proposed substitutes as follows (punctuation and capitalization not corrected): Mr. Steven Manning experience [sic] in industrial electrical work does not start until 1997. It does not show any bridge related work. His training certificate in Electrical ladder Drawings" is for a one day 7 contact hours session. The "well experienced" requirement is not clearly indicated by his resume. Mr. Adrian Cook also does not show any bridge related work and the "well experienced". Mr. Wayne Cano has 11 years of industrial experience but no bridge experience or electricians license. In conclusion Old Tampa Bay enterprises needs to provide us with equivalent substitutions. Specifically licensed electricians with a minimum of four years experience in diverse bridge electrical configuration; with old relay logic operation, well experienced in PLC controllers from various manufactures [sic]; the ability to read and interpret ladder logic drawing; the ability to program plc’s. The Department’s inclusion of response time in the contract clearly indicates our desire for prompt and efficient emergency repair work. In other words the Department would like the equivalent of Mr. Green and Mr. Vance in the original proposal who’s [sic] experience will "keep bridge down time and repair time to a minimum." By letter to Mr. Abernathy dated August 13, 1998, Mr. Alvarez forwarded FDOT’s rejection of Old Tampa Bay’s proposed substitutes. The letter essentially reiterated the contents of the memorandum quoted above, and informed Old Tampa Bay that it would have one last opportunity to provide FDOT with equivalent or better substitutions for the electrical key personnel. Old Tampa Bay’s response would be due no later than August 24, 1998. Mr. Alvarez testified that as to this and his prior letters to Mr. Abernathy, he essentially acted as a conduit for the actual decision-maker, Mr. Ooms. Mr. Alvarez wrote the letters because he was the designated contact person in the FDOT contracts office, not because of any personal expertise or authority he possessed to deal with the issue of the qualifications of the proposed key personnel. By letter from Mr. Abernathy to Mr. Alvarez, dated August 21, 1998, Old Tampa Bay informed FDOT that "we are unable to locate electricians which meet or exceed the qualifications of those we proposed, i.e., Mr. Green and Mr. Vance. Please proceed as necessary." Old Tampa Bay’s letter did not take issue with any of the conclusions set forth in Mr. Alvarez’ letter of August 13, 1998. On August 24, 1998, FDOT posted a revised proposal tabulation finding Old Tampa Bay nonresponsive and listing GE as the intended awardee of the contract for RFP 1003. At the hearing, Mr. Ooms testified that he did not know Mr. Manning, Mr. Cook, or Mr. Cano, had no personal knowledge of their background or experience, and relied on their résumés in making his decision. Mr. Ooms felt that Mr. Manning, while a master electrician, lacked sufficient experience on PLCs and had no experience working on bridges. Mr. Ooms noted that the only indication of electrical ladder drawing or computer experience on Mr. Manning’s résumé was a seven-hour continuing education course in electrical ladder drawing. Mr. Ooms’ undisputed testimony was that a single seven-hour course was insufficient to provide the expertise needed to perform the duties required of an electrician on these bridges. Mr. Ooms admitted that John Vance and Kelly Green lacked PLC experience when they started working on the bridges, and were trained by FDOT. However, Mr. Ooms rejected Old Tampa Bay’s suggestion that Mr. Manning could be similarly trained on the job. Vance and Green were trained in connection with the installation of PLC equipment on the Cortez Bridge in 1996. Mr. Ooms testified that this training was simply a part of the rehabilitation of the bridge, and that PLC experience was not a prerequisite at the time Vance and Green were hired. Mr. Ooms further distinguished this situation by noting that the issue here is not simply qualifications, but equivalency. Mr. Ooms stated that because Old Tampa Bay’s winning proposal was based on the presence of Vance and Green, any substitutes for Vance and Green must not only meet the RFP specifications but must be equivalent to the experience of Vance and Green, which included PLC experience. Mr. Ooms testified that he rejected Adrian Cook for the same lack of PLC experience. Mr. Cook held the required journeyman electrician’s license, but his résumé gave no indication of PLC or troubleshooting experience. Mr. Ooms testified that he called Mr. Cook’s current employer, who vouched for him as a "good man," but provided no details as to his PLC experience. Mr. Ooms also admitted that he did not ask the employer about Mr. Cook’s PLC experience. As to Mr. Cano, Mr. Ooms testified that he appeared well qualified but lacked the required journeyman electrician’s license, and lacked bridge experience. Mr. Ooms was impressed by Mr. Cano’s PLC and ladder logic experience, and might have approved him but for the lack of the required license. Mr. Ooms acknowledged that Kelly Green did not have his journeyman electrician’s license when he started work on the bridges. Mr. Ooms testified that he was unaware of that fact at the time Mr. Green was hired. Douglas Blake, project engineer for GE, affirmed that in the five years GE has been performing bridge operations and maintenance, FDOT has never asked any electrician to produce a license. Mr. Blake testified that performance of an electrician’s job on these bridges does not require permitting, and that there is no license exposure to an electrician working these jobs. Mr. Blake’s opinion was that the license requirement is merely a contract tool FDOT can use to eliminate substandard bids. No witness for FDOT assented to Mr. Blake’s characterization of the license requirement. FDOT’s consistent position was that a prospective electrician must have at least a journeyman electrician’s license, as set forth in the RFP and the Bridge Manual. Mr. Blake testified that Manning, Cook, and Cano all appeared to be worthy candidates to be bridge electricians, insofar as their electrical technical qualifications appeared to compare favorably to those of Vance and Green. No evidence was presented that Mr. Ooms had any knowledge of Mr. Blake’s opinion at the time he made his decision, or that such knowledge would have altered that decision. Lane Tyus, a GE electrical engineer with experience on these bridges, likewise testified that the résumés of Manning, Cook, and Cano would pass his initial screening and that he would make a final decision in a face-to-face interview. No evidence was presented that Mr. Ooms had any knowledge of Mr. Tyus’ opinion at the time he made his decision, or that such knowledge would have altered that decision. At the hearing, Old Tampa Bay produced a list purporting to show 25 electricians whose hiring for bridge work was approved by FDOT for various districts during the period 1991 through 1998, despite the fact that none of the 25 had prior bridge experience. This list included Mr. Vance and Mr. Green in District One, where Mr. Ooms works. Mr. Ooms disclaimed knowledge as to the approval practices of other districts, which in any event have no relevance to this proceeding. Mr. Ooms again averred that this situation is different than that prevailing when Vance and Green were hired, because the substitutes here proffered by Old Tampa Bay must not only meet the RFP requirements but must be the equivalent of Vance and Green in experience and expertise. Mr. Abernathy testified that he believed the team of Manning, Cook and Cano was the equivalent of Vance and Green. He testified that any modern industrial electrician must have experience with PLCs, and will not necessarily spell-out that experience on his résumé. He testified that it was his "absolute firm belief" that no matter whose names he submitted to FDOT as substitute electricians, they would be rejected. Mr. Ooms testified that he neither favored GE nor disfavored Old Tampa Bay. He admitted having greater familiarity with GE’s personnel because they have been working on the bridges for the last five years. He testified that he considers it his professional obligation to work with whoever holds the contract. Aside from the obvious licensure deficiency for Mr. Cano, these proposed substitutes may well have been equivalent to Vance and Green. However, their equivalence could not be ascertained from Old Tampa Bay's submissions. Their résumés did not clearly establish their qualifications in areas that Old Tampa Bay knew or should have known were critical to FDOT. The agency made its expectations very clear to Old Tampa Bay as to what was expected of equivalent substitutes. Old Tampa Bay did nothing to expand upon the sketchy résumés of these persons, or to explicate the relationship between their experience and the work to be performed on the bridges. Mr. Ooms cannot be faulted for failing to consider information that the proposer did not provide. It is found that Mr. Ooms was not biased in rejecting Manning, Cook, and Cano. Old Tampa Bay argues that the disparity in the scoring of the technical proposals between Mr. Ooms and the other two evaluators demonstrates his bias in favor of GE. However, as noted above, all three evaluators gave GE the highest marks for RFP 1003. In fact, the scores for GE’s proposal given by the other two evaluators were significantly higher than the score Mr. Ooms gave to GE’s proposal. The fact that Mr. Ooms found an 18-point disparity between the proposal of GE and the proposals of the other two bidders does not of itself indicate bias in favor of GE on his part, any more than the fact that his score for GE was 15 to 18 points lower than the GE scores by the other evaluators indicates a bias against GE. FDOT demonstrated no bias against Old Tampa Bay in this process, providing Old Tampa Bay repeated opportunities to provide satisfactory substitutes for Green and Vance. Old Tampa Bay attempted to show disparate treatment by introducing evidence showing that FDOT allowed GE to substitute Kelly Green for an electrician named Charles Cave in 1995, after award of the previous contract, despite the fact that Green at the time had no experience working on the bridges and did not obtain a journeyman electrician’s license until approximately two months after he commenced work. Assuming arguendo that FDOT’s actions in awarding this contract may be attacked by showing different agency behavior in prior contracts, the evidence adduced by Old Tampa Bay is insufficient because it gives no indication of the qualifications of Charles Cave, the electrician replaced by Mr. Green. There is no way to determine whether Mr. Green was or was not an equivalent substitute for Mr. Cave, and thus no way to establish disparate treatment by FDOT from one contract to the next. Old Tampa Bay further asserts that FDOT’s treatment of Mr. Green when he commenced work indicates that FDOT had the discretion to allow Mr. McCormick to obtain his journeyman electrician’s license after commencing work. Assuming arguendo that Old Tampa Bay’s assertion is correct, the facts establish that the lack of a license was a secondary concern in the rejection of Mr. McCormick. Mr. Ooms testified that his rejection of Mr. McCormick was primarily based on lack of bridge and PLC experience, and the overstatement of qualifications on Mr. McCormick’s résumé. Even if Mr. McCormick possessed the required license, Mr. Ooms would have properly rejected him. Old Tampa Bay challenged FDOT’s allowing GE to make changes in its management personnel after being awarded the contract for RFP 1003. The three upper-level managers in question were located in Atlanta, had nothing directly to do with the operation of the bridges, and were not "key personnel" as described in the RFP and Bridge Manual. GE informed FDOT of the change in a courtesy letter, dated October 20, 1998, more than five months after submission of the original proposals. The RFP did not require these remote persons to be identified by name at all, let alone require GE to freeze them in place as a condition of its contract. As noted above, the facts established that Old Tampa Bay included the name of John Vance in its proposal though it knew or should have known that Mr. Vance had no intention of working for Old Tampa Bay on this project. Old Tampa Bay attempted to demonstrate that GE did substantially the same thing when it included the name of Mr. Lane Tyus in its proposal as its registered electrical engineer. Mr. Tyus indeed testified that he did not know that GE had included his name in the proposal at the time it was submitted, and was not made aware of his inclusion until some time after Old Tampa Bay filed its protest. However, Mr. Tyus also testified that he knew his résumé was kept on file by GE precisely for inclusion in proposals. Further, he testified that he has been involved with the contract for these bridges since 1992, that he was not surprised at his inclusion, and that he was prepared to undertake the tasks described in the GE proposal. Thus, there is no comparison between Mr. Tyus’ situation with GE and that of Mr. Vance with Old Tampa Bay. Finally, Old Tampa Bay attempted to demonstrate bias in the fact that FDOT allowed GE to submit John Vance's name as bridge superintendent for RFP 1004, despite his lack of experience in that position. However, Mr. Ooms testified that Mr. Vance was in fact more than qualified for the position, in that the training requirements set forth in the Bridge Manual for electricians such as Mr. Vance include all the requirements for bridge superintendents as well as electrical courses.

Recommendation Upon the foregoing findings of fact and conclusions of law, it is recommended that the Department of Transportation enter a final order dismissing the protest filed by Old Tampa Bay Enterprises, Inc. and awarding the contract for RFP-DOT-97/98- 1003, Bridge Tending/Maintenance and Repair Services for Five Movable Bridges, Sarasota and Manatee Counties, to General Electric Industrial Systems. DONE AND ENTERED this 27th day of May, 1999, in Tallahassee, Leon County, Florida. LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of May, 1999. COPIES FURNISHED: Jonathan Sjostrom, Esquire Steel, Hector & Davis LLP 215 South Monroe Street, Suite 601 Tallahassee, Florida 32301-1804 Brian F. McGrail, Esquire Office oif the General Counsel Department of Transportation 605 Suwannee Street, Mail Station 58 Tallahassee, Florida 32399-0458 Robert A. Rush, Esquire Robert A. Rush, P.A. 726 Northeast First Street Gainesville, Florida 32601 Thomas F. Barry, Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street, Mail Station 58 Tallahassee, Florida 32399-0458 Pamela Leslie, General Counsel Department of Transportation Haydon Burns Building 605 Suwannee Street, Mail Station 58 Tallahassee, Florida 32399-0458

Florida Laws (2) 120.57287.057
# 1
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs ARMANDO VICTOR CALLEJA, 08-001432PL (2008)
Division of Administrative Hearings, Florida Filed:Viera, Florida Mar. 21, 2008 Number: 08-001432PL Latest Update: Nov. 12, 2019

The Issue The issues in this case are whether Respondent violated Subsections 489.129(1)(g)1., 489.129(1)(g)2., 489.129(1)(j), 489.129(1)(m), and 489.129(1)(o), Florida Statutes (2005),1 and, if so, what discipline should be imposed.

Findings Of Fact At all times material to this proceeding, Mr. Calleja had a valid and active license as a commercial certified pool/spa contractor. His license number is CP 1456568. At all times material to this proceeding, Mr. Calleja was the owner of or did business as Nautica Pools & Spa (Nautica). The Board is charged with regulating the practice of contracting in the State of Florida pursuant to Chapters 455 and 489, Florida Statutes. On April 2, 2005, Mr. Calleja, as the representative for Nautica, entered into a contract with Jack Coleman to renovate Mr. Coleman’s existing pool. From April 2005 to July 27, 2005, Nautica installed rebar in the pool and set a new skimmer. Nautica subcontracted with Prestige Gunite of Melbourne, Inc. (Prestige), to put the gunite in the pool. Gunite is concrete that is sprayed out of a hose to form the walls of the pool. Personnel from Prestige arrived on the project site on the afternoon of July 27, 2005, to apply the gunite, but did not do so because the application would have taken longer to do than one afternoon. The following day, July 28, 2005, Mr. Calleja and a crew from Prestige returned to the project. A representative from Prestige told Mr. Calleja that the steel rebar had not been laid properly. Mr. Calleja told Prestige to apply the gunite and do what was necessary to cover the steel. Mr. Calleja left the project site, and Prestige began applying the gunite. During the application of the gunite, it became evident that the first spraying of gunite was not going to cover the steel. Attempts were made to reach Mr. Calleja, but Mr. Calleja was not available to solve the problem. Prestige began applying additional coats of gunite in an attempt to cover the steel. After the gunite was applied, two problems were identified. The first problem was in the fountain area. The gunite had not been applied properly, and there were hollow areas. The second problem was in the wet deck area. The steel rebar was too close to the surface of the floor, and the steel was visible. In order to remedy the problems, the concrete in the areas would have to be jack hammered to remove the concrete, and new gunite would have to be applied. By letter dated August 28, 2005, Nautica requested Mr. Coleman to pay Prestige $954.57. Nautica advised Mr. Coleman that when that amount had been paid, Nautica would pay the balance owed to Prestige and forward a release to Mr. Coleman. Mr. Calleja claimed that Mr. Coleman owed the $954.57 because Mr. Coleman had damaged Mr. Calleja’s saw. In the letter, Nautica acknowledged that there was additional work which had not been completed. The letter was signed by Mr. Calleja’s wife. Mr. Calleja had verbally told Mr. Coleman that he wanted Mr. Coleman to pay him $2,000.00, and he would take care of paying Prestige. The general specifications in the contract required that the contractor was responsible for “[s]tandard structural engineering plans and permits required by code.” Prior to commencing work on the pool renovation, Mr. Calleja did not secure the required building permits for the project. Mr. Coleman called Clifford Stokes, who is the building official with the town of Indialantic, and asked whether a permit had been issued. Mr. Stokes went to the project site. At that time, the gunite had been shot, and there was exposed steel rebar. Since no permit had been pulled, no inspection had been done after the steel was put in place. On September 15, 2005, Mr. Calleja applied for a building permit. Because the steel had been placed, and the gunite shot, it was impossible to do a visual inspection to determine whether the steel had been placed properly. In order to get a permit after the construction had been commenced, certain affidavits had to be submitted to the building official of Indiatlantic. Mr. Calleja had to submit an affidavit stating that the steel had been placed properly. An affidavit stating that the work had been performed properly had to be submitted from an engineer, who had made a site visit to the project and had determined that the work performed had been according to code. Additionally, Mr. Coleman was required to submit an affidavit that stated that he understood that no inspection had been done of the work by the building official. Mr. Calleja also had to pay a fine to Indiatlantic for commencing work without a building permit. On October 19, 2005, Mr. Calleja and Robert Lee from Lee Engineering came to the project site for the purpose of preparing the affidavits necessary to secure a building permit. Mr. Calleja did not return to the project site after October 19, 2005. Mr. Coleman sent a letter to Mr. Calleja dated October 13, 2005, noting that no work had been done on the project since July 28, 2005, and requesting that Mr. Calleja remedy a number of deficiencies with the work performed on the project and complete the job in accordance with the contract. The letter was returned to Mr. Coleman by the postal service because the time for forwarding mail from the address listed in the letter had expired. When Mr. Calleja came to the project site on October 19, 2005, Mr. Coleman requested a current address from Mr. Calleja, but Mr. Calleja refused to give him one. Mr. Coleman wrote another letter to Mr. Calleja dated October 25, 2005, again stating that no work had been done since July 28, 2005, and requesting that Mr. Calleja correct the deficiencies in the work and complete the contract. Mr. Coleman filed an action in small claims court attempting to recover the money for the lien filed by Prestige. However, Nautica had filed for bankruptcy, and Mr. Coleman did not proceed with the small claim action. A building permit for the project was issued in January 2006. The issuance of the building permit did not relieve Mr. Calleja from the responsibility of assuring that the work in the shallow end of the pool area where the rebar was sticking up was redone properly. After the building permit was issued, neither Mr. Calleja nor Mr. Coleman called for inspections by the Indiatlantic building official. The permit expired in June 2006. After the issuance of the building permit, Nautica performed no further work on the project. The total contract price was $9,340.00. Mr. Coleman and Mr. Calleja entered into an addendum to the contract on July 27, 2005, which increased the contract price to $13,000.00. The contract called for a down payment of $934.00, which was ten percent of the contract amount. After completion of excavation and the form and steel work, a payment of $3,736.00 was due, representing 40 percent of the total work. After completion of the pool shell, a payment of $2,802.00 was due, representing 30 percent of the total work. Prior to plastering, which represented 20 percent of the total work, a payment of $1,868.00 was to be paid. The contract addendum of $3,660.00 called for 50 percent of the addendum amount to be paid at the completion of the pool shell, and the remaining 50 percent of the addendum amount was to be paid at the completion of the pool. By check dated April 22, 2005, signed by Mr. Coleman’s wife, Mr. Coleman paid Mr. Calleja $1,000.00 as down payment on the project. In June 2005, Mr. Coleman gave Mr. Calleja a check for $573.42 for a pool and spa light. Mr. Coleman was to receive a credit of $380.00 toward the contract for the light. Additionally, Mr. Coleman overpaid Mr. Calleja by $166.90. By check dated July 27, 2005, and signed by Mr. Coleman’s wife, Mr. Coleman paid Mr. Calleja $7,396.00. This payment was to include half of the addendum amount, but Mrs. Coleman inadvertently included the full amount of the addendum. By check dated August 1, 2005, and signed by Mrs. Coleman, Mr. Coleman paid Mr. Calleja $739.10. Thus, by August 1, 2005, Mr. Coleman had paid Mr. Calleja, $9,682.00 on the contract. In December 2005, Mr. Coleman asked a representative of Paradise Pools, Patrick McDonough, to come to the project site and give an estimate to complete the pool. The estimate of $7,800.00 from Paradise Pools was for a cosmetic plaster of the existing pool, and the work was not warranted against leakage. Mr. McDonough would not warrant the work, because he saw a lot of potential liability problems with the work performed by Mr. Calleja. Mr. McDonough did not recommend that a cosmetic plaster be performed because of the potential problems. On October 26, 2005, Prestige filed a Claim of Lien against the property of Mr. Coleman for $4,227.40 plus interest, costs, and attorney’s fees. The lien was for the work which Prestige had performed on the project on July 28, 2005, and for which Mr. Calleja had failed to pay. Mr. Coleman called Mr. Calleja and told him that a lien had been filed. Mr. Calleja assured him that he would pay the lien, but he failed to do so. Mr. Coleman satisfied the lien by check dated April 11, 2006, for the amount of $5,139.58. David Bogenrief, P.E., viewed the project in June 2008 and provided Mr. Coleman with a quote to develop structural plans to repair Mr. Coleman’s pool. There was no testimony on the amount of the quote, and the Department did not request that the written proposal be admitted in evidence. Mr. Bogenrief did not know what it would cost to repair the pool. The Department has incurred $470.49 for costs in the prosecution of this case.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered finding that Mr. Calleja did not violate Subsection 489.119(2), Florida Statutes, and that Mr. Calleja violated Subsections 489.129(1)(g)1., 489.129(1)(g)2., 489.129(1)(j), 489.129(1)(m), and 489.129(1)(o), Florida Statutes; for the violation of Subsection 489.129(1)(g)1., Florida Statutes, imposing a fine of $2,000.00, suspending Mr. Calleja's license for six months, and requiring Mr. Calleja to pay Mr. Coleman $5,139.58 as restitution for the payment of the lien filed by Prestige; for the violation of Subsection 489.129(1)(g)2., Florida Statutes, imposing a fine of $2,000.00, suspending Mr. Calleja's license for six months, and requiring Mr. Calleja to pay Mr. Coleman $9,682.00, which represents the amount that Mr. Coleman paid to Mr. Calleja; for the violation of Subsection 489.129(1)(j), Florida Statutes, imposing a $1,000.00 fine and four years of probation; for the violation of Subsection 489.129(1)(m), Florida Statutes, imposing a $1,000.00 fine and four years of probation, which shall run concurrently with the other probation imposed; and, for the violation of Subsection 489.129(1)(o), Florida Statutes, imposing a $1,000.00 fine and two years of probation to run concurrently with the other probation imposed; and requiring payment of $470.49 as costs for the prosecution of this case. DONE AND ENTERED this 29th day of August, 2008, in Tallahassee, Leon County, Florida. S SUSAN B. HARRELL Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 29th day of August, 2008.

Florida Laws (6) 120.569120.57120.68489.119489.1195489.129 Florida Administrative Code (1) 61G4-17.001
# 2
SUPERIOR PAVING, INC. vs. DEPARTMENT OF TRANSPORTATION, 86-000314BID (1986)
Division of Administrative Hearings, Florida Number: 86-000314BID Latest Update: Apr. 09, 1986

Findings Of Fact On or about December 16, 1985, Petitioners submitted an application requesting qualifications in five major classes of work and two incidental classes of work. At the hearing, qualification in cement paving was not pursued. The Department denied the applications for qualification to bid on contracts for Minor Bridges, Portland Cement Concrete, Hot Plant-mixed Bituminous Base and Surface courses, and the two incidental classes of fencing and grassing, seeding and sodding. Petitioner here contests the Minor Bridge, Hot Plant-mixed Bituminous Base and Surface courses and the two miscellaneous categories. Superior Paving has been in the road building business for many years and the sole basis for denying qualification for Hot Plant-mixed Bituminous Base and Surface courses is that Superior does not own an asphalt plant. During the years Petitioner has worked in road construction for DOT its work has been satisfactory, contracts have been completed on time, and there has been no default. Petitioner has the financial ability to perform the work for which qualification is requested and has experienced personnel necessary for this work. With respect to construction work on minor bridges, Petitioner's general manager and superintendent both have extensive experience in this work area. During the past two years, Petitioner has done no work on DOT projects as the result of a two year suspension for a contract crime. Prior thereto on DOT construction involving minor bridge work in which Superior was the prime contractor, this work was subcontracted out to a contractor specializing in bridge construction. However, Superior has the resources to obtain all equipment needed for minor bridge work. Also Petitioner has been the successful bidder on jobs involving fencing as well as grassing, seeding and sodding. Petitioner has used this type work to meet its quota for subcontracting at least ten percent of the job to minority and female subcontractors. On one occasion when the sodding subcontractor failed to complete the project, Petitioner used its own personnel and equipment to do so. Petitioner's request for qualification for these incidental classes was denied because its application failed to show that the company accomplished fencing, grassing, seeding and sodding with its own forces and equipment. (Exhibit 14.) Most of the evidence submitted in these proceedings involved the denial of qualification for the type work that has been Petitioner's primary category for many years, viz. asphalt paving. The sole reason for denying Petitioner qualification in this class of work is that Petitioner does not have its own asphalt plant (Exhibit 14.) This requirement imposed by Respondent is a recent one which was placed into effect in 1985 following the amendment to Rule 14- 22.03 F.A.C. That amendment added "and the adequacy of equipment to perform the specific classes of work." At the time this change to the rule was made DOT was applying the policy of requiring a contractor to own an asphalt plant in order to qualify for this work class. When asked why this unwritten policy was not included in the rule when amended in 1985, the witnesses involved in incorporating the change involving equipment into the rule replied he could not answer that. The policy of DOT that in order to qualify for asphalt paving the bidder must own an asphalt plant has general applicability and has been applied during the past year to all contractors bidding on DOT road projects. DOT personnel who testified in these proceedings stated the purpose of adding the phrase regarding having the necessary equipment to the requirement for qualification, was to bring the rule more in line with the statutory provisions. The adverse publicity DOT received in recent years because of contractor delays in completing projects and deficiencies in some of the work performed resulted in the tightening of the requirements for qualification. Two contractors in particular were late in completing contracts on which they were successful bidders and part of the delay was due to their inability to get the necessary road paving material. However, both of these contractors owned asphalt plants. One had delays in getting a permit from the Department of Environmental Regulation to erect a plant near Destin, Florida, and the other had a falling out with his supplier and could not get the required material. In neither of these cases did the ownership of an asphalt plant alleviate the problem. No evidence was presented showing that a delay in the completion of a project was due solely to the failure of the contractor to have his own asphalt plant. Several asphalt producers submitted letters to the effect that they had supplied paving material to Petitioner for many years and would continue to supply him as much as he would buy. One plant owner testified that he had been in the production and laying of asphalt pavement for many years and much preferred to have the role only of supplier. He also testified that most producers felt the same way. There is no policy or rule requiring contractors who bid on jobs requiring the use of road aggregates to have their own rock quarry in order to qualify for this work class. Petitioner has the necessary equipment to transport mix from the plant to the job site and to install the mix at the job site. Hot Plant-mixed Bituminous Base and Surface courses can be successfully trucked approximately 60 miles from the plant. Accordingly, under DOT's policy, a successful bidder will frequently have to erect an asphalt plant near the job site. This will require him to obtain permits and negotiate the environmental problems associated therewith. The effect of not being qualified for Minor Bridge and Hot Plant-mixed Bituminous classes is that Petitioner is not qualified to bid as a prime contractor when one or more of these classes, in the aggregate, comprises fifty percent or more of the work.

Florida Laws (2) 22.03337.14
# 3
ROBERT AND SOLANGEL VERDE vs MONROE COUNTY PLANNING COMMISSION, 19-001605 (2019)
Division of Administrative Hearings, Florida Filed:Marathon, Florida Mar. 25, 2019 Number: 19-001605 Latest Update: Dec. 04, 2019

The Issue The issue is whether Petitioners are entitled to an after-the-fact building permit for work done to their manufactured home on Big Pine Key following Hurricane Irma.

Findings Of Fact On June 24, 2014, Petitioners paid $115,0003 to acquire title to a lot in unincorporated Monroe County bearing the address of 31480 Avenue F, Big Pine Key (Lot). The Lot is in the Avenues neighborhood within the Sands subdivision, which consists of site-built and manufactured homes. The Lot measures 100 feet deep and 40 feet wide. Because the back 20 feet of the Lot is submerged bottom of a canal, the effective area of the lot is 80 feet deep by 40 feet wide. The Lot is at the southern end of Big Pine Key, just north of Route 1. About 400 feet--or six lots--to the east of the Lot is water that connects to the open waters of the Atlantic Ocean about two miles to the south and to the Gulf of Mexico a greater distance to the north. The landward extent of the canal at the back of the Lot extends three or four lots to the west. The Avenues neighborhood features an alternating series of evenly spaced canals and lettered avenues, all running in an east-west direction. The six canals are of roughly equal dimensions. The canal behind the Lot is the second closest to the ocean. The Lot is in Federal Emergency Management Agency (FEMA) flood zone AE, indicative of a relatively high risk of flooding. The base flood elevation of the Lot is nine feet above mean sea level.4 The base flood elevation is the elevation specified for a structure to avoid floodwaters from the base flood event, which is the flooding projected to result in a flooding event with an annual probability of occurrence of 1%.5 The prevailing elevation of the Sands subdivision is only three feet above mean sea level, so that the base flood event would inundate the subdivision by an average of about six feet of water. The AE zone is associated more with rising and wind- driven water. The VE zone, which extends from the water to a point three lots east of the Lot, is associated with the stronger water forces of surging water. These zones reflect the projected relative risks to structures posed by the depth of a flood and the energy of the water column in terms of velocity and, where applicable, wave action. When they acquired the Lot, Petitioners also acquired the title to a 56-foot by 12-foot 1970 Ritz-Craft, Inc., manufactured home located on the Lot (Trailer). Originally purchased for about $2000, the Trailer has been located on the Lot continuously since at least December 28, 1971, when a predecessor-in-interest of Petitioners filed with the Monroe County property appraiser's office a Declaration of Mobile Home as Real Property. When acquired by Petitioners, the Trailer still had many of its original fixtures, including the original Formica counter, bathroom, and trailer tub, and the finished floor was composed of vinyl strips glued together, the walls were covered in wood paneling, and the kitchen cabinets were made of wood. Given practices prevailing in the industry at the time of the manufacture of the Trailer, the subflooring, cabinets, and unfinished counters were likely particleboard, which is highly susceptible to water damage, and the walls were likely plywood, although these components may have been replaced over the years. The front of the Trailer is the 12-foot end facing Avenue F to the north, and the back of the Trailer is the 12-foot end facing the canal to the south. Abutting one side of the Trailer is a freestanding wood deck measuring 16 feet by 8 feet. At all material times, the Trailer's foundation has consisted of stacks of concrete blocks forming piers under the Trailer. These stacks elevate the Trailer so that the finished floors were about three feet above grade. If the elevation of the Lot approximated the average elevation in the Sands subdivision, without regard to wave action and tide, storm surge would need to exceed six feet to submerge the finished floors of the Trailer. In their first three years of ownership, Petitioners performed the usual maintenance on the Trailer, including a paint job, but did not alter the components described above. The only major work took place in May 2017 when Petitioners paid $2210 to Privateer Alliance, a certified general contractor, to disconnect their septic tank and connect to central sewer lines. On September 10, 2017, Hurricane Irma, a category-four storm, made landfall at Cudjoe Key. The storm caused extensive flooding and wind damage in the Florida Keys, but especially in Big Pine Key, which is about ten miles east of Cudjoe Key. The damage along Avenue F indicated that the causative force was moving water more than from rising water, and structures east of the Lot suffered more damage than structures farther from the water.6 In compliance with a mandatory evacuation order, neither Petitioner was in the Trailer when Hurricane Irma struck. The storm inflicted the most damage to the Sands subdivision, among residential areas. On Big Pine Key, floodwaters reached five to eight feet above mean sea level, and floodwaters in the vicinity of the Trailer persisted for about 12 hours, as noted by Respondent.7 Respondent offered into evidence Composite Exhibit L, page 1, which is a map entitled, "Coastal Depth Grid." The map depicts the portion of the Avenues that includes the Lot. The map bears coloring that, according to the legend, is intended to report the flooding depths from Hurricane Irma. Although the variations in color are too slight to differentiate among the varying depths shown in the legend, Respondent construed the Coastal Depth Grid to show nine feet of floodwater over the Lot. Respondent offered no predicate for the Coastal Depth Grid. To the contrary, one of Respondent's witnesses, Mary Wingate, who is a 24-year employee working in Respondent's Floodplain Office of its Building Department, testified to a more reasonable floodwater depth of five to eight feet. A floodwater depth no higher than the low end of Ms. Wingate's estimate is supported by the damage to the interior of the Trailer, as discussed below.8 For these reasons, the Coastal Depth Grid is not credited as a source of a finding of floodwater of nine feet above mean sea level over the Lot. Following a major storm, prior to the order allowing residents to return to their homes, building or safety inspectors visit affected areas and make initial determinations of the safety of individual residences. If a structure is determined to be unsafe, the inspector posts a red card that states, "Destroyed," so as to prevent reoccupation or re-energizing of the residence. Fifty to sixty inspectors for the entire Keys started inspections in the upper keys on September 13 or 14. Reflective of the devastation caused by Hurricane Irma in the Florida Keys, three weeks passed before a building inspector visited the Lot on October 3, 2017. At that time, the building inspector, who is a licensed professional engineer, determined that the Trailer had been destroyed, so the inspector posted a red card on the Trailer. This determination was based on damage to the front of the Trailer, which was visible from the street; the inspector did not examine the interior, the utilities, or the back of the Trailer. From the street, the inspector correctly determined that the walls, windows, and doors had been unaffected, but the siding and trim would require repair. For the roof and roof structure, the inspector checked boxes stating that these elements required repair and replacement; perhaps, the seemingly inconsistent checkmarks were intended to mean that repair would be sufficient for some parts of the roof and some parts of the roof structure, but replacement would be necessary for other parts of these two elements. In fact, neither the roof nor roof structure required replacement, although the roof required the replacement of a damaged roof panel. In a brief narrative, the inspector noted on the inspection form: "Building completely off foundations & separated from entry stairs & deck." Perhaps due to a daunting workload, the inspector failed to notice that the back of the Trailer was still on its concrete block stacks. The front of the Trailer had been driven off its stacks, likely by storm surge, and rested about four feet from its original position, still somewhat above grade because it rested atop debris. On October 14, 2019, a building inspector conducted another inspection of the Trailer and determined that the damage equaled or exceeded 50% of its assessed value, pursuant to the SI/SD ordinance, which is discussed in the Conclusions of Law. Again, this inspection did not include an examination of the interior of the Trailer. The October 14 determination relied on a FEMA-supplied tool, Composite Exhibit L, page 2 (FEMA Tool), for estimating damage based on a "long-duration" saltwater inundation of a manufactured home. Two problems preclude reliance on the FEMA Tool. First, the inspector used the above-described Coastal Depth Grid to determine that the Lot was subjected to a floodwater depth of nine feet--or six feet above the finished floor of the Trailer. Because the actual floodwater depth was substantially less than nine feet, the FEMA Tool produced an excessive estimate of damage. Second, the inspector applied the FEMA Tool to a flooding event that was not shown to be of long duration, as required for use of the tool.9 It is impossible to determine which of the two flaws in the use of the FEMA Tool produced the greater distortion in damage estimates. Even when using a more-reasonable input of three to four feet of flooding above the finished floor--i.e., six to seven feet of floodwaters--the FEMA Tool predicts that the air conditioning unit, subfloor, finished floor, and bottom cabinets would be completely destroyed. The air conditioning unit, which is installed in the wall, was undamaged, as were the bottom cabinets. The flooring components are discussed below, but were not completely destroyed. The FEMA Tool predicts near-total to total destruction of the plumbing, doors, and wall finishes, which, as discussed below, were substantially undamaged. The FEMA Tool predicts damage of 38% to 72% to the electrical system, which was undamaged. In other respects, as well, the FEMA Tool over-estimates the extent of the damage to the Trailer. The failure of the parties to offer into evidence the FEMA tool for short-duration saltwater flooding to a manufactured home precludes a finding as to the extent to which the actual floodwaters were substantially shallower than even Ms. Wingate's estimate or the duration of inundation was very brief. In either case, the repairs undertaken by Petitioners are a good measure of the damage to the Trailer, except for the finished floor. First, Petitioners rented some jacks and, with one or more friends, lifted the front of the Trailer, restacked the concrete blocks, and reset the Trailer atop them. Apparently at the same time, Petitioners also restored the wood deck to its prestorm condition. The retail value of this work was $1000. Second, the storm damaged the weatherhead or cap that shields the electric service line from the elements where the line enters the Trailer. The retail value of the work to replace the weatherhead and perform the electrical safety inspection required before the power company would restore power to the Trailer was $1060. Third, the storm caused minor damage to one or more plumbing lines. The retail value of this repair work was $240. Fourth, various exterior panels required repair or replacement due to damage. The retail value of the repairs was $575, and the retail value of the replacement of 16 outer panels was $1280. Fifth, the storm destroyed the skirting along the bottom of the Trailer. The retail value of this replacement work was $1056. Sixth, the retail value of minor trim repairs necessitated by the storm was $500. The retail value of the above-described work was $5711. During the same time period, Petitioners performed additional work for which they never obtained a permit. The Conclusions of Law explain the relevance of the retail value of this work, which consisted of the installation of five new windows at $1075, the application of window sealant, caulking and hardware totaling $295, and the installation of a new front door for $320. The retail value of this work, which did not address floodwater damage, was $1690. This work plus the previously described work thus totaled $7401. This leaves the finished floor and subflooring and one panel of plywood that had separated from the wall and was flopping. The plywood paneling is de minimis. One panel of wall plywood separated from the wall, although it is unclear how that happened, and the repair would represent an insignificant expense, even if the panel had to be replaced. One of the Petitioners testified that there was water damage on the floor at the front of the Trailer extending across the front room and into the living area, where it discolored the bottom four inches of a sofa cover and left a muddy residue. At the back of the trailer, Petitioner found a water mark about one-half inch high along metal bunkbeds. According to this witness, the walls bore no dirt or mud, and neither they nor the cabinets were damaged by the water, but the vinyl floor tiles separated by no more than 1/8th of an inch due to ungluing from exposure to the water. This testimony is credited. The floodwater that entered the Trailer left a silty deposit on the floor, so it was relatively easy to determine the vertical reach of any floodwater that entered the Trailer, and the limited damage to the roof and sides of the Trailer does not appear to have allowed significant, if any, amounts of rain water into the Trailer. The crucial questions, which are left unanswered in this record, involve the extent of the work necessary to restore the finished floor and subflooring to their prestorm condition and the retail value of the cost of this work. One of Petitioner's witnesses was David Koppel, who is a licensed professional engineer with considerable experience in the assessment of damages, partly from a 22-year career with Respondent. In December 2018, Mr. Koppel inspected the foundation, tie-downs, interior and underneath of the Trailer, both flooring units, and the walls and cabinets and concluded that the structural elements were "sound" and everything was intact as it was built, except for a little "swelling and separation" of the finished floor, which Mr. Koppel testified was so minor that its repair or replacement would be left to the owners' choice. Mr. Koppel opined that all work had been performed in conformance with the 1970 Building Code, which was in effect when the original building permit was issued. Mr. Koppel's testimony is problematic in two regards.10 He mistook the vinyl floor for a wood floor, and he misidentified the referent as the owners' preference instead of the prestorm condition, as explained in the Conclusions of Law. Otherwise, Mr. Koppel's testimony is credited. There is no evidence that Petitioners repaired or replaced any of the items that Mr. Koppel inspected, prior to his inspection, so he would have found any damage, such as rot or mildew, that would have developed in the intervening 15 months between the storm and his inspection. This leaves as the sole open question as to damages the retail value of the cost of the work to repair or replace the damaged portion of the finished floor--an issue that is not addressed in the record. Lastly, it is necessary to determine the prestorm value of the Trailer. The property appraiser assessed the Trailer at $17,769. After a 20% adjustment, as discussed in the Conclusions of Law, Respondent increased the value of the Trailer to $21,323. Petitioners' witness, an experienced real estate appraiser, testified that the Trailer was worth $53,618, using the cost approach to value. Her total estimate of the cost of the structure, if new, was $73,450, which she reduced by $19,832 for depreciation. Petitioners' appraiser never explained why she estimated only $20,000 or 27% for depreciation for a 50-year-old manufactured home. Her appraisal also lacked comparable sales to back up her cost approach to value and never took into account published sources of market values for used manufactured homes. Petitioners' evidence does not persuade that a manufactured home, parked beside the ocean for 50 years, is worth today over $50,000. Thus, Petitioners failed to overcome the adjusted assessed value of $21,323. However, the proved retail value of the work associated with damage and improvements of $7401 is less than 50% of the value of the Trailer of $21,323. Following the storm, Petitioners and contractors performed the above-described work. By May 12, 2018, Respondent initiated an investigation into the substantial unpermitted work that Petitioners had undertaken. On June 8, 2018, Respondent issued a Notice of Violation/Notice of Hearing for July 26, 2018 (NOV). The NOV alleges the unpermitted work and requires corrective action of obtaining an after-the-fact or demolition permit. The hearing before the special magistrate took place on September 27, 2018. At the hearing, as stated in Petitioners Exhibit F, Respondent's counsel advised the special magistrate: This one isn't terribly complicated or terribly difficult in that we just need the after the fact permit so that the inspections can be performed to make sure that the utilities are connected, safely reconnected, reattached. It's currently on the blocks in the proper situation, hopefully it doesn't happen again. The NOV proceeding concluded with the parties' agreement that Petitioners would file an application for an after-the-fact permit, although the discussion indicates that Respondent was focusing exclusively on the necessity of a permit to replace the Trailer on its concrete block stacks and to replace the wood deck to its original position abutting the Trailer. The after- the-fact permitting process then ensued, as described in the Preliminary Statement.

Florida Administrative Code (1) 28-106.201 DOAH Case (1) 19-1605
# 4
BOARD OF DENTISTRY vs. PETER E. KURACHEK, 89-001240 (1989)
Division of Administrative Hearings, Florida Number: 89-001240 Latest Update: Nov. 21, 1989

The Issue The issue for consideration herein is whether Respondent's license as a dentist in Florida should be disciplined because of the misconduct alleged in the Administrative Complaints filed herein.

Findings Of Fact At all times pertinent to the allegations involved in this hearing, relating to both cases, the Respondent, Peter A. Kurachek, was licensed as a dentist in Florida under license number DN 0005429, and the Board of Dentistry was and is the state agency governing the practice of dentistry in Florida. AS TO CASE NUMBER 89-1240 Jill J. Hageman started work at the Respondent's clinics in Port Charlotte and in Venice, Florida in July, 1985 and left his employ in January, 1986. During the period of her employment it was office practice to soak instruments used on patients in a cold soap solution, not a bactericide. Her job included the task of cleaning used instruments and she had been instructed to scrub them and soak them in a soap solution before placing them in a dry heat sterilizer. This unit, not an autoclave or a chemclave, did not have any gauges or lights to indicate appropriate temperature. The instruments were left in the soap solution between 30 minutes and an hour; then rinsed and dried. During the first three months of her employment the heat unit was not there. It was installed only after she had worked there for some time. Her instructions on the use of the soap solution and the procedure to be followed came from the Respondent. Ms. Hageman was concerned with sterilization. She observed that some instruments were rusty and the procedures she was instructed to follow were not consistent with what she had been taught in dental technician's school. Respondent denies this and none of the other doctors who worked for him who testified at the hearing observed any. It is found, therefore, that allegations of rust are not supported. The sterilizer utilized in Respondent's office was not as sophisticated as those seen by Ms. Hageman in other offices or in school. Since it did not have any means to indicate completion of sterilization, it was difficult to tell when the instruments were completely sterilized. This was the only office in which she has ever seen a dry heat sterilizer used. On one occasion, when she was assisting Respondent with a patient, she saw him drop an instrument on the floor, pick it up, and use it in the patient's mouth without sterilizing it. She was upset by this but failed to discuss the situation with Respondent or the patient, or make a notation in the patient's record. This incident allegedly took place shortly after she began work at Respondent's clinic but she, nonetheless, remained there for several months, perhaps mentioning it only to her friend and coworker, Ms. Gillespie. She finally left Respondent's employ of her own volition because she was concerned about the lack of sanitation in the clinic. To the best of her knowledge, she was not about to be fired. Ms. Gillespie worked in Respondent's office in Port Charlotte during 1985 and 1986, primarily as a receptionist, but, when necessary, as a dental assistant. She was licensed as such, holding an expanded certificate. To the best of her recollection, no sterilization was practiced in the facility. Respondent repeatedly used instruments that had been washed with an all purpose soap, and while there was an autoclave on the premises, it was inoperable during the entire period that she worked for him. As she recalls it, instruments were washed in the soap, dried, and placed back into the instrument drawers for subsequent use on patients, and this lack of sterilization concerned her. On one occasion, Respondent needed a post for a device he was inserting into his patient's mouth. When he could not find a dental post, he asked Ms. Gillespie for her hair brush, and when she gave it to him, cut several bristles off and, as she recalls it, without washing or sterilizing them in any way, inserted one into a patient's mouth as a post. The brush had been used and had hair in it. This shocked her but she did not make any official report of it, discussing it only with Ms. Hageman. Though there is some inconsistency between the testimony of Ms. Hageman and that of Ms. Gillespie regarding the type of mechanical device used by Respondent to sterilize his instruments, it is obvious that both are discussing the same piece of equipment and one or the other is in error in her description of it. However, both agree that the equipment on hand did not work in any case, and that Respondent knew it did not work. According to Ms. Gillespie, he advised his employees to falsely state, if asked, that instruments were taken to the other office for sterilization. Respondent denies both Hageman's and Gillespie's allegations. In the area of sanitation, in Dr. Robinson's opinion, the use of soapy water is not appropriate and does not meet minimum standards of sanitary practice. Further, the use of a dropped instrument or the use of a bristle from a hairbrush for a post in a patient's mouth is not an appropriate sanitary procedure. Use of alcohol as a sterilizing agent is inadequate. Respondent's wife claims that on the day the clinic was visited by the investigator, a sterilizer, a cold sterilizer, and a daylight loader were present and operable. The heat sterilizer in question was a small unit different from that in most other offices. It has a temperature gauge and lights to show its operation, but, admittedly is difficult to operate. The cold sterilizer is merely a covered tray utilized to hold instruments while immersed in a sterilizing fluid. At that time in either March or April, 1985, this office in Port Charlotte had been open for about 7 to 8 months. Ms. Hageman had already left Respondent's employment as had Ms. Gillespie. Ms. Kurachek is not a technician but has picked up considerable knowledge of procedures and equipment over the 21 years she has been married to Respondent. Monica Colburn is a certified dental assistant and Respondent's receptionist in the Port Charlotte office. In May, 1986, she worked in the Venice office and has worked for Respondent for over three years. She did not work with either Ms. Hageman or Ms. Gillespie, both of whom preceded her. She has seen Respondent and other dentists drop instruments while working on a patient. It is a common occurrence. When this happens to Respondent, he always leaves the instrument on the floor and asks for a new one. Only when the patient departs is the instrument picked up and it is sterilized before being used again. The chemclave, the autoclave and the cold sterilizer have all been there as long as she has been employed. Both Ms. Hageman and Ms. Gillespie claim that while employed as dental assistants by Respondent, they were instructed to adjust dentures on patients. Ms. Hageman relates that in order to do this, she had been instructed to place an identifying paste inside the pink part of the denture currently in use by the patient to identify raised pressure points and then adjust the denture. She did this, accomplishing the procedure at the Respondent's direction but without his assistance or supervision. She also was given no training in the procedure by the Respondent but had some background in it because the procedure was briefly covered to give students a familiarity with it, not a use capability, during training. In fact, when in either basic technician school or classes for her expanded certificate, she was advised that for her to do this type of work by herself was illegal. She did it, even knowing it was improper, out of fear of Respondent's ill temper and because, as her boss, he had instructed her to do it. Nonetheless, though it bothered her that she was being required to do something illegal, she did not complain to anyone other than Ms. Gillespie even though she was required to perform the procedure for approximately four different patients. Ms. Gillespie, primarily the receptionist in the office, was occasionally called upon by the Respondent to make adjustments to a patient's dentures and when she did this, on at least 12 separate patients, he did not supervise her performance of the procedure nor was he present in the room while it was being done. His sole participation in training her was to show her once or twice how to accomplish the procedure and even after Ms. Gillespie advised Respondent of her concerns regarding this, and that she was not licensed to do this type of work, he nonetheless inferred that if she did not do as he directed, she was likely to lose her job. Since she was a divorcee with two children and needed the employment, she did as she was told. She was also asked to use a cavitron on a patient but refused and even the potential of losing her job would not convince her to do so. The instrument may legally be used only by a licensed dental hygienist or dentist. According to Dr. William F. Robinson, an expert in general dentistry, whose opinion is accepted herein, the task of adjusting dentures is one which cannot be delegated to a dental assistant whether or not the assistant has an expanded certificate because dental adjustment is a delicate procedure which requires special training that assistants do not normally receive. To do so violates community standards as an improper application of the dentist's practice and can result in: destruction of soft tissue and bone, neurological damage, incorrect occlusion resulting in speech and fungus problems, sanitation problems, and an overreactive gag reflex with choking. Ms. Colburn, Respondent's current assistant, has never adjusted an appliance or been asked to do by Respondent. The same can be said for the other assistants. Only a dentist does adjustment though she has taken a paste impression preparatory to an adjustment being made. This has been the policy at Respondent's clinic so long as she has been there. It should be noted, however, that Ms. Colburn has been employed by Respondent only since the initiation of the investigation involved herein and is not aware of any practice previous to that time. At Respondent's request, she contacted prior denture patients to see if any had had their denture adjusted by an assistant. None of the five who responded so indicated. Respondent claims that his clinics now have and had, during the first five months of 1985, an autoclave and a large tub for cold sterilization. To support this claim, Respondent offered three checks and a purchase order which he asserts refer to the autoclave in question. However, the purchase order, upon review, fails to indicate a vendor and is undated, and the checks total an amount larger than that necessary for the purchase of the instrument. Respondent claims that the autoclave he had worked but not properly. It would heat up to the proper temperature for sterilization and would stay at that temperature but had no timer capability and would not complete the cycle to remove and heat and turn itself off. In order to get the instruments out, the operator would have to pull the plug. Ultimately, Dr. Kurachek purchased another heat sterilizer and then a chemical sterilizer, but asserts that at all times he had some kind of sterilization capability in each of the clinic offices. No doubt some type of equipment was present, but it is found that the equipment did not work sufficiently to be reliable for sterilization, and was a problem. Respondent also denies ever having picked up a dropped instrument and using it in a patient's mouth. He claims that when he drops an instrument he leaves it where it is until either the patient leaves or it is convenient for him to retrieve it and sterilize it. He also denies that he used a hairbrush bristle as alleged by Ms. Gillespie. He admits, however, that at times he used hairbrush bristles as posts and still does when a regular post is not available. In the instant case, Respondent claims that the bristle was taken from a brush bought specifically for this purpose and used only after sterilization in a cold sterilization solution. He unequivocally denies using any bristle from Ms. Gillespie's personal hairbrush claiming he has not ever seen that brush until it was shown to him at the hearing. Respondent also claims that instruments were transported from one center to another but only to replace an instrument that was used and was no longer effective, or to fill a need in the center to which taken. Respondent claims that this sterilization process was adequate and meets sterilization standards. The procedure followed consisted of a wash in soapy water and a rinse, followed by cold sterilization, and for those instruments requiring further sterilization, a second rinse was used followed by heat sterilization. Dr. Kurachek did not clarify what was meant by use of the term "cold sterilization". According to Respondent's expert, Dr. Bliss, at one time it was appropriate to use nylon bristles as posts for crowns and a hair brush bristle, if properly sanitized before use, could legitimately be inserted if it was the proper size. Respondent attempted to discredit the testimony of Ms. Gillespie, and to a lesser extent, Ms. Hageman, by implications that they were merely trying to seek revenge by making the allegations here involved because they had been suspected of misconduct with funds while employed. There was no direct evidence to that effect, however, and such inference is rejected. Taken together, the evidence shows, and it is found, that inadequate sterilization equipment was on hand and proper sanitation procedures were generally not followed, but the allegation relating to use of a dropped instrument is rejected. AS TO CASE NO: 89-1241 Ms. Jean D. Spears was treated at the Respondent's clinic during the period 1984 through 1986. During the early part of her treatment, she went there strictly for routine fillings and cleanings. However, as time went on she also needed some crown preparations. At first she saw Dr. Feasley who took the required x-rays and did the fillings required and, did some other things for her. She had no problem with this treatment. However, in 1985 she also needed a bridge installation for which Dr. Feasley did the preparation but, because he left employment with the Respondent before the bridge could be constructed and placed, it was ultimately completed and placed by a Dr. DeVol. The bridge prepared by Dr. Feasley and installed by Dr. DeVol did not fit at first and could not properly be placed. Ultimately the Respondent was called in and recommended something be done which seemed to cure the problem. However, while the Spears were on vacation, the bridge came out and had to be recemented several times. After this, Respondent made a partial bridge for Mrs. Spears for other teeth, but this bridge did not fit either. Because she was dissatisfied with the fit of the original bridge made by Dr. Feasley Ms. Spears went to another dentist, Dr. Currie. She then returned to Respondent who agreed to remake the original Feasley bridge and an appointment was made for her after Respondent did a lot of other work elsewhere in her mouth. However, when the time came for Respondent to correct the original bridge, even though he had promised to do so, Respondent refused to work on it claiming it was not his responsibility since he did not make it. Ms. Spears thereafter complained to state authorities and sometime later, Respondent called and offered to do the necessary repair work. At this time, Ms. Spears refused to allow him to do so because she had made alternative arrangements for correction and she never went back to Respondent's clinic. Instead, she went to see Dr. Feasley, her original dentist, who remade the bridge which now fits properly and which she wears to this day. Ms. Spears considered herself to be a patient of Respondent's clinic regardless of which dentist did the work for her, and though she does not blame Respondent for the poor fit of the original bridge, she considers him ultimately responsible since he is the owner of the clinic. She was upset by Respondent's attitude and even after he originally agreed to fix the bridge he changed his mind and suggested she go back to Dr. Feasley to get the repair work done because it was not his, Respondent's, responsibility. Respondent questions Ms. Spears' recollection of the particulars involved in her complaint against him and though it is obvious that time has dimmed her memory of exact dates and times, it has not adversely affected her recollection of the ultimate facts. At 78 years of age, she appears to have a good command of her faculties and is considered a credible witness. Dr. Feasley worked at Respondent's Venice clinic from 1983 to 1985 as a contract dentist and during that period, treated Ms. Spears for whom he suggested, on April 25, 1984, a root canal. Though he attempted to do the root canal, he was unable to accomplish it. He sealed it up and suggested she have an endodontist pull the tooth in question, number 18. Somewhat later, on August 1, 1984, he took several x-rays and did some fillings, and prepared three teeth for crowns which he set in place. In light of Ms. Spears' age and health, he felt it appropriate to put in crowns even though she had some periodontal disease. In July, 1985, he also did the preparation work for the construction and insertion of a bridge to cover teeth numbers 18 - 21 for Ms. Spears, but because he severed his connection with the clinic before it was finished, he was unable to follow through on it. However, he saw Ms. Spears again at his new office in May, 1986 when she came to him complaining of the bridge on teeth 18 through 21 which had been placed by Respondent's clinic after his departure and with which she had had problems since its insertion. Dr. Feasley took x-rays and found that the bridge in question was defective and based on what she told him, he recommended it be replaced. On July 15, 1986, Dr. Feasley removed the offending bridge, repaired teeth 18 and 22, and put in a new bridge extending between those two teeth. It is noted that an additional tooth was added. When, in 1986, Dr. Feasley examined the bridge constructed at Respondent's clinic, he determined the fit was inappropriate. There was a margin gap on tooth 21 which had been filled with a tooth colored material. This was not as he, Dr. Feasley, had designed the bridge. When Dr. Feasley made the new bridge for teeth 18 through 22, he charged Ms. Spears even though on May 13, 1986, Ms. Spears told him that the Respondent had sent her to him to have him fix the bridge. In the course of their conversation, Ms. Spears advised him that whenever she had gone to the clinic, they would always do most of the work requested but, would never work on the bridge for teeth 18 through 21 which, though made at the clinic, had been prepared and designed by Dr. Feasley. Dr. David R. Smith, an expert in general dentistry called by the Petitioner, reviewed Ms. Spears' records and x-rays and examined her on April 24, 1988. Based on his review, he concluded that for various reasons, Respondent's treatment failed to meet the minimum standards of performance within the community. These reason were: There was no charting of periodontal disease. X-rays clearly showed periodontal disease on tooth 18 resulting in bone loss; that the teeth were tipped; and that teeth numbers 3 and 4 were periodontally involved. The clinical examination showed severe function involvement on tooth 32; tooth 18 had a 5 mm periodontal pocket on two sides and a 4 mm pocket on two others; teeth 6, 8, 22, and 23 showed buckling and bleeding on probing with active periodontal disease; the mobility of the teeth was slight; teeth 4 and 5 had been roughly ground flat on the biting surface; tooth 11 showed decay on the biting edge; and teeth 12 and 13 showed short margins around a bridge. The charts prepared on Ms. Spears show that Dr. Feasley started treatment with preparation for a bridge for teeth 18 through 21. The bridge was placed in the patient's mouth on July 19, 1985 by Dr. DeVol. There were some problems with this bridge and Dr. Curry treated Ms. Spears and did an extraction of an unrelated tooth. Ms. Spears continued to complaint about the 18 to 21 bridge and in December, 1985, a filling material was placed on the edge of the tooth which leads Dr. Cook to believe there was a short margin which required the patch. Work was also done on upper right teeth 3 through 5 and 12 through 14. Some of these are in direct occlusion with teeth 18 through 21. On February 6, 1986, Dr. Kurachek first saw Ms. Spears. He indicated in the record at that time that it was a difficult case, (teeth 3 through 5 had super-erupted and needed adjustment), and he had to grind down some teeth. He also indicated the patient needed a bridge on the upper left from tooth 12 through tooth 14. On February 7, 1986, he delivered a partial bridge and advised Ms. Spears of the need for another different bridge which she refused to have done. At this time, Respondent failed to chart any periodontal disease. On several follow-up visits, Respondent adjusted the partial bridge and on February 20, 1986, he placed some covering material over a gap left by a short margin. On March 13, 1986, he concluded that the teeth 18 through 21 bridge was to be redone at no charge. On April 8, 1986, the bridge still was not corrected and in May, 1986, Respondent entered in the file that he did not want to interfere with Dr. Feasley's work. The records indicate Respondent did the bridgework on teeth 12 through 14 before the patient's periodontal disease was corrected, and in the opinion of Dr. Smith, this is below community standards. In this, Dr. Smith disagrees with Dr. Feasley's position that in light of the patient's age, installation of a bridge prior to correcting periodontal disease is acceptable. Though there is a divergence of opinion on this issue, the better position is that one should treat and cure the periodontal disease before beginning bridge work. In Dr. Smith's opinion, however, the first bridge on teeth 18 through 21, constructed by Drs. Feasley and DeVol, appears inadequate due to the repeated adjustments that were necessary. Given the fact that this bridge was inadequate, it was improper for Respondent to put a bridge on teeth 12 through 14 without regard to the improper condition of the teeth 18 through 21 bridge. It would have been more appropriate for him to fix the 18 - 21 bridge first and then install the 12 - 14 bridge. Dr. Smith is of the opinion that Respondent's installation of the 12 - 14 bridge without first correcting the problem with 18 - 21 does not meet standards because it did not treat the underlying problem and it impacted and abutted a severely impacted tooth, (18). In addition, the placing of the partial denture on the left side, (teeth 28 - 31), was a violation of standards since it was anchored to a faulty tooth, (tooth 18), by a wire that went around the mouth behind the front teeth. Both conclusions are found to be correct. It also appears that Respondent recommended adjustment of the biting surface of teeth 3 through 5 and that teeth 12 through 14 be planed. He recommended extracting teeth 24 and 25 and insertion of a lower bridge. He also indicated the bridge on teeth 18 through 21 should be redone but refused to do it himself, and it was not done at Respondent's clinic. Dr. Paul A. Hounchell, also an expert in general dentistry, also reviewed Ms. Spears' records and her x-rays, and from the records was unable to determine the treatment plan anticipated for this patient. There was no charting of her periodontal problems and a failure to chart pockets is not within standards in this state. Dr. Hounchell agreed with Dr. Smith regarding the impropriety of inserting a new bridge on different teeth in Ms. Spears' mouth without first correcting the improper formulation of the 18 through 21 bridge. He also observed that the margin on tooth 12 was open at least 1 mm and that on tooth 13 by at least 1/2 mm or more and his opinion, this is outside minimum standards. Dr. Rupert Q. Bliss, an expert in general dentistry, has served on the Board of Dental Examiners and has been a consultant for it thereafter. He teaches at the University of Florida Dental School and has, over the years, reviewed thousands of charts and records. He has considerable experience in crown and bridge work and general reconstructive dentistry with the majority of his practice dealing with prosthetic manufacture. His examination of the records kept on Ms. Spears by Dr. Smith, Petitioner's expert, shows they contain little in regard to periodontal pockets. In charting this area, training generally calls for the noting of six items for each tooth. Other than as to teeth 32 and 18, Dr. Smith's records note only four items per tooth. This is not appropriate. However, Dr. Smith's charting is not in issue. Comment is made by Dr. Bliss only for comparison. The clinic notes on Ms. Spears prior to the Respondent's taking over of her treatment in February, 1986, show many problems in her mouth which Respondent recognized and agreed to correct, especially regarding the bridge for teeth 18 through 21. Since Respondent took over treatment of Ms. Spears in mid process, it is not necessarily below standards for him to have failed to rechart prior conditions and to continue with the treatment already begun, especially since she had been seen be another dentist in the same office. Though Dr. Bliss keeps detailed charts on his patients, it is not uncommon to see charts which do not include thorough periodontal pocket charting. While he does not approve of this practice, there is no absolute requirement for it. The Board standards require a complete examination including thorough charting of periodontal pocketing. The chart kept by Respondent appears to be typical. It does not conform to the minimum standards in Florida but is consistent with common practice in the dental community. As to Respondent's grinding down of teeth to make them fit to a bridge, this can legitimately be done, but if it is, it leaves the tooth open to the mouth environment. According to Dr. Bliss, whether to do so is a judgement call, but evaluating Respondent's performance in grinding down teeth 12 through 14 before correcting teeth 18 through 21, in his opinion the process was accomplished in a manner equal to or above minimum standards. If the grinding of teeth 12 through 14 were done to an ideal plane of occlusion, it would reduce pressure on the lower bridge and would improve the periodontal condition of the patient on teeth 18 through 21. Consequently, it would eliminate the potential for traumatic occlusion. Further, the initiation of crown and bridge work before clearing up the periodontal problems was acceptable in this case, Bliss opines, because Respondent was picking the patient up in mid treatment. Had Ms. Spears been a new patient, it would have been more appropriate to clear up the periodontal problems before starting the crown and bridge work. Ms. Kurachek was present in her husband's office when the investigator from the Department came. He was there for approximately 15 minutes during which she heard him indicate it appeared everything was in place and he would so report. There appears to have been a serious misunderstanding on someone's part regarding this, and it is highly unlikely the investigator made such comments.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that Respondent's license to practice dentistry in Florida be suspended for a period of six months and that he be fined $3,000.00, and that when reinstated, he be placed on probation, under such terms and conditions as the Board may prescribe, for a period of three additional years, these actions to run concurrently with the penalty, if any, imposed by the Board in its action, when taken, in its allied case involving the Respondent, heard under DOAH case number 89-5544. RECOMMENDED this 21st day of November, 1989, in Tallahassee, Florida. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of November, 1989. APPENDIX TO RECOMMENDED ORDER, CASE NOS. 89-1240 AND 89-1241 The following constitutes my specific ruling pursuant to Section 120.59(2), Florida Statutes, on all of the proposed Findings of Fact submitted by the parties to this case. By the Petitioner: 1. & 2. Accepted and incorporated herein. 3(a). Accepted and incorporated herein. 3(b). Rejected. 3(c & d). Accepted and incorporated herein. 4. Not a Finding of Fact but a Conclusion of Law. 5.-7. Accepted and incorporated herein. 8. & 9. Accepted and incorporated herein. 10. & 11. Accepted and incorporated herein. 12.-14. Accepted and incorporated herein. 15. & 16. Accepted and incorporated herein. 17. & 18. Accepted and incorporated herein. Accepted and incorporated herein. Not a Finding of Fact but a Conclusion of Law. By the Respondent: 1. & 2. Accepted and incorporated herein. 3. & 4. Accepted and incorporated but not dispositive since there is some issue as to whether either worked properly. 1st sentence accepted. Rejected since sole evidence of this is hearsay testimony. Balance accepted. Not a Finding of Fact but a summation of testimony and a comment thereon. 1st sentence accepted. Balance is not a Finding of Fact but a summation of testimony. A restatement or and comment on testimony, not a Finding of Fact. 1st Sentence accepted. Balance merely a restatement of testimony. Accepted and incorporated herein. 11.-14. Accepted and incorporated herein. 15.-19. Accepted and incorporated herein. 20. & 21. Accepted. 1st sentence rejected as not supported by evidence of record. Balance accepted. Accepted as accurate description of treatment plan and of Respondent's reasons therefore without accepting appropriateness thereof. & 25. Accepted. Accepted. & 28. Accepted and incorporated herein. 29.-32. Accepted. Not a Finding of Fact but a restatement of testimony. Accepted. Accepted but not determinative. Accepted, but it was never done properly. Accepted, but failure to examine eventually is a failure of standard. Rejected as an inaccurate summary of testimony. Dr. Bliss indicated charting is often not done properly and indicated specifically that Respondent's charting was not up to standards. Accepted and incorporated herein. Accepted. Accepted. Accepted. Accepted. COPIES FURNISHED: Bruce D. Lamb, Esquire Department of Professional Regulation 730 South Sterling Street, Suite 201 Tampa, Florida 33609 Salvatore A. Carpino, Esquire One Urban Centre, Suite 750 4830 West Kennedy Boulevard Tampa, Florida 33609 Kenneth E. Easley, Esquire General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792 William Buckhalt Executive Director Board of Dentistry 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (2) 120.57466.028
# 5
KENNETH J. THOMAS, NANCY ALBRIGHT, ET AL. vs. GENERAL DEVELOPMENT CORPORATION AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 80-001698 (1980)
Division of Administrative Hearings, Florida Number: 80-001698 Latest Update: Jan. 29, 1981

Findings Of Fact Petitioners own residential property near South Florida Water Management District (SFWMD) Canal C-24. The canal is owned and maintained by SFWMD, an agency of the State of Florida. The State property includes the banks and bottom of Canal C-24 and a 50-foot-wide strip of land which separates Petitioners' property from the canal. However, some of the Petitioners have obtained permits from SFWMD to maintain boat docks in the canal and to cross the 50 feet of intervening property as necessary. Canal C-24 is closed to navigation immediately west of Petitioners' property by a SFWMD dam used to control the water level. However, the canal is open to navigation east of the dam and connects with the St. Lucie River which flows into the Atlantic Ocean. Respondent GDC plans the residential development of property east of that owned by Petitioners. Construction of the proposed bridge will improve access to the GDC property and other portions of southeast Port St. Lucie which are now blocked on the north and east by water and on the west by the Florida Turnpike. On August 28, 1980, Respondent Department of Environmental Regulation (DER) issued its Notice of Intent to grant a permit for construction of the bridge with 17 feet clearance. The bridge was originally planned to provide 12 feet clearance which was approved by SFWMD and the City of Port St. Lucie. Based on Petitioner's objections and the recommendation of the US Coast Guard, the clearance was increased to 17 feet. However, Petitioners maintained their opposition, giving rise to these proceedings. At 17 feet the bridge would be approximately six feet below the Florida Turnpike bridge which is situated between the GDC residential development and Petitioners' property. Thus, Petitioners are currently limited to a 23-foot navigation clearance by the Florida Turnpike bridge which was present when they purchased their property. None of the Petitioners operates any boat at his Port St. Lucie residence which would be affected by construction of the proposed bridge. Rather, Petitioners' objections are based on the obstruction of larger boats they might acquire and on the belief that resale value of their property would be diminished. They also content that use of the canal as a hurricane refuge for large boats will be restricted. Finally, Petitioners argue that bridge pilings will cause erosion and thus create a surface hazard in addition to the height impediment. The Petitioners indicated no plans to acquire any power boats of such size as to be restricted by a 17-foot clearance, nor did their plans include the purchase or use of any sailboats which would not already be blocked by the 23- foot turnpike bridge. No studies, appraisals or together evidence was introduced to establish that property values would be affected by construction of the proposed bridge. Conflicting evidence was presented on the use of the canal by third parties as a hurricane refuge. However, the expert testimony given by Respondents' witnesses established that use of the canal during storms was unsafe and impractical due to the narrowness of the canal, the absence of trees to reduce the force of the wind or secure the boats, and the possibility of strong currents caused by operation of the flood control dam. Further, this testimony established that safer moorings are available on the adjacent portion of the St. Lucie River, which has the added advantage of being directly accessible to the ocean. Such moorings are preferable because of the greater maneuverability in the river and the presence of mangroves which provide anchorage and wind protection. The alleged erosion problem was not supported by any studies or expert testimony, but was based on Petitioners' observations of some soil erosion around turnpike bridge pilings. GDC's construction proposal has been considered by DER, and its engineering plans will be reviewed by the City of Port St. Lucie before it authorizes construction. This process should insure that any potential erosion problems are minimized. Furthermore, there was no evidence to indicate that soil erosion, even if it did occur at the site of the proposed bridge, would create any hazard to navigation. The City Manager of Port St. Lucie supports construction of the bridge at its present level. His concern, and that of the City Commission, is centered on the need to deliver police, fire and ambulance service to the area south of the proposed bridge. Additionally, opening of the bridge will result in the improved flow of vehicular traffic in the community. A local contractor who owns lots on both sides of the canal opposes any further elevation of the bridge as it would reduce the view from houses he intends to construct in this area. The GDC evidence established that raising the height of the bridge would also enlarge the property on either side of the canal required for bridge purposes. Finally, the cost of construction of further increasing bridge height would be substantial, amounting to approximately $40,000 per foot.

Recommendation From the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED: That the Department of Environmental Regulation grant the permit to General Development Corporation as reflected in the Notice of Intent issued on August 28, 1980. DONE and ENTERED this 8th day of January, 1981, in Tallahassee, Leon County, Florida. R. T. CARPENTER, Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of January, 1981. COPIES FURNISHED: Mr. Kenneth J. Thomas 2649 SW Harem Circle Port St. Lucie, Florida 33452 Ms. Anita R. Cockerham 2549 SW Harem Circle Port St. Lucie, Florida 33452 Mr. Walter J. Konrad Ms. Victoria Konrad 2657 Harem Circle, SW Port St. Lucie, Florida 33452 Mr. Henry Albright Ms. Nancy Albright 2651 Harem Circle, SW Port St. Lucie, Florida 33452 Mr. William Isaacs 2645 SW Harem Circle Port St. Lucie, Florida 33452 Mr. and Mrs. Frederick C. Walrath 2647 SW Harem Circle Port St. Lucie, Florida 33452 Ms. Mary Bruins Kars 2659 Harem Circle Port St. Lucie, Florida 33452 Mr. Norman Zlinkoff 1814 Erwin Road Port St. Lucie, Florida 33452 Mr. Donald M. Homer General Development Corporation 111 South Bayshore Drive Miami, Florida 33131 Randall E. Denker, Esquire Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 Joseph Z. Fleming, Esquire 620 Ingraham Building 25 SE Second Avenue Miami, Florida 33131

Florida Laws (1) 120.57
# 6
DEPARTMENT OF HEALTH, BOARD OF DENTISTRY vs JOSEPH GAETA, D.D.S., 07-001164PL (2007)
Division of Administrative Hearings, Florida Filed:Sarasota, Florida Mar. 13, 2007 Number: 07-001164PL Latest Update: Aug. 28, 2009

The Issue The issues are whether Respondent is guilty of recordkeeping violations of Section 466.028(1)(m), Florida Statutes, and standard-of-care violations of Section 466.028(1)(x), Florida Statutes, in connection with bridgework, implants, and root canals that he performed on a single dental patient.

Findings Of Fact Background At all material times, Respondent has been a licensed dentist, holding license number DN 11262. He is not Board- certified in any areas recognized by the American Dental Association, but he is a fellow, associate fellow, or diplomate with four associations, not recognized by the American Dental Association, devoted to dental implants. Respondent has been licensed to practice dentistry for over 20 years. At all material times, Respondent practiced in Port Charlotte. At one time, his practice grew to six offices employing 13 dentists and 80 employees. During that timeframe, Respondent performed about 100 crowns and bridges per month, endodontics (which includes root canals) on 7-10 teeth per month, and limited periodontics, including 20-30 implants and 2-3 sinus lifts per month. Respondent has been disciplined previously. In Nebraska, where he was licensed to practice dentistry, Respondent's license was suspended in 1989 upon his conviction for a felony for obtaining a controlled substance by fraud in writing one or more prescriptions, ostensibly for his father, so that Respondent could satisfy his chemical dependency. The Board of Dentistry consequently imposed discipline the following year for this offense (or the suspension arising from it), suspended Respondent's Florida license for one year, and required him to attend the PRN program for impaired practitioners. In February 1995, the Board of Dentistry imposed discipline against Respondent for his violation of the applicable standard of care by failing to diagnose periodontitis prior to seating crowns. The Board imposed a $3000 administrative fine and required Respondent to attend the PRN program and complete 35 remedial continuing education hours. Two years later, the Board of Dentistry imposed discipline against Respondent for his failure to pay the fine. The Board imposed a $500 administrative fine and issued a reprimand. In February 2002, the Board of Dentistry imposed discipline against Respondent for his violation of the applicable standard-of-care and recordkeeping requirements by failing to diagnose and treat periodontitis or recording required exams prior to seating a bridge and crowns and failing to document examinations and test results. The Board imposed a $6000 administrative fine and required Respondent to attend 60 hours of continuing education. In December 1993, evidently in connection with the acquisition of an existing practice, Respondent acquired W. C. as a patient. W. C. was a cost-conscious, aging man who wanted to preserve his natural teeth. Respondent treated him for about ten years and often acceded to W. C.'s requests for reduced pricing for specific procedures. The relationship ended only when Respondent insisted that W. C. pay off a balance that he had agreed to pay. Over the course of their professional relationship, which included about 120 visits, Respondent wrote off $10,000 in charges in an effort to help W. C. control costs. Likely due to pricing sensitivity, W. C. was an episodic patient, rather than a regular patient. This means that W. C. visited Respondent only for relief from particular problems, rather than appearing regularly for cleaning, x-rays, and maintenance. Sometimes W. C.'s refusal to visit the dentist except when he had a problem and his desire to control costs conflicted with his dental needs, which at times became fairly extensive. All of the issues in this case involve, directly or indirectly, Respondent's treatment of two bridges: one in the upper right quadrant and one in the lower left quadrant. The issues require findings addressing the endodontic (root canal) and implant issues, but these issues arose in the larger context of the bridgework issues that W. C. presented. When Respondent acquired W. C., he found bridges already in place in these two locations. A bridge is a fixed prosthesis that supports missing teeth between crowns. Abutment teeth are the retainers; missing teeth are the pontics (or false teeth). The bridge permits the patient to replace missing teeth without having to take them out overnight. Bridges are intended to remain in place for at least five years, although some may remain in place for 20 years. Bridges may be placed temporarily or "permanently." Although some dentists use plastic bridges for temporary placements, Respondent did not do so with W. C. References below to temporary bridges mean that Respondent used temporary cement with no intent, for various reasons, of "permanently" seating the bridge at that time. At the start of the operative timeframe, W. C.'s lower left bridge supplied a pontic for missing tooth number 19, tooth number 17 was missing, and tooth number 18 was a blade implant. On the other side of the pontic were teeth numbers 20 and 21. The presence of a blade implant confirms the age of the lower left bridge, as this type of implant was not typically in use after the 1980s. At the start of the operative timeframe, the upper right bridge supplied pontics for missing teeth numbers 3, 4, and 5. Prior to 1996, a predecessor to this bridge used natural teeth numbers 2 and 6 as abutments. However, in early 1996, Respondent extracted tooth number 2, replaced it with an implant, and installed a new bridge that used the implant at the site of tooth number 2 and teeth 6 and 7 as abutments. In May 1997, when W. C. returned with a loose upper right bridge, Respondent's notes state that he advised W. C. that he needed an implant and performed only palliative treatment. In June 1997, Respondent performed a root canal on tooth number 6, installed a temporary bridge, and later installed a new permanent bridge in the upper right quadrant. Petitioner's expert witness, Dr. Harold Haering, testified that, by July 24, 1997, Respondent extended this bridge to abutment tooth number 8. This is borne out by the note for that date, as well as the notes for October 27, 1997, and July 23, 1998. Some more remote history is available for both these bridges. The record contains dental records for W. C. as far back as September 1974, at which time he had periodontal surgery for teeth numbers 3 through 8. In November 1974, W. C. received a bridge for teeth numbers 4 through 7--a precursor of the upper right bridge at issue in this case. Five years later, the dentist treating W. C. recommended that the upper right bridge be remade after periodontal surgery to tooth number 5. He placed a new upper right bridge in August 1979 and performed a root canal on tooth number 4 in May 1980. In April and May 1981, the dentist placed another bridge, although his notes prevent identifying where. In June 1982, after performing the root canal on tooth number 21, as noted above, the dentist removed the lower left bridge due to decay in tooth number 18. The dentist continued to treat the teeth at the lower left bridge through 1982, removing and recementing the bridge as needed. In January 1983, the dentist discovered a cracked root in tooth number 4. He removed the upper right bridge and then extracted tooth number 4. Likely, dental records are missing from the record for the next five years because, in mid-1988, the records restart with the removal of sutures at teeth numbers 2-5. The records note that this bridge still suffers from mobility. A few months later, the dentist had to remove the upper right bridge again and take new impressions. In mid-1989, the lower left bridge failed, as pontics at sites 18 and 19 separated. At this time, the dentist replaced the lower left bridge. Respondent began to see W. C. in December 1993. Still prior to the operative timeframe, on February 15, 1995, after noting that the prognosis for tooth number 2 was guarded to hopeless, Respondent performed a root canal on this tooth. One year later, Respondent sectioned the upper right bridge and, as noted above, placed an implant at site number 2. In September 1996, Respondent prepared a bridge from teeth sites or numbers 2-7, using 2, 6, and 7 as abutments. After a couple of trials, Respondent cemented the permanent upper right bridge on November 5, 1996. The upper right bridge was rechecked for looseness in May and June 1997, at which time Respondent removed the bridge to perform a root canal on tooth number 6 and prepared a temporary upper right bridge. On July 24, 1997, Respondent prepared tooth number 8 for inclusion in the upper right bridge, which had previously stopped at tooth number 7. The temporary upper right bridge broke on August 6, 1997, at tooth number 6. A week later, Respondent tried in the permanent upper right bridge, but found it needed additional porcelain to the pontic area and took new bite impressions. His notes reflect that he would deliver the bridge after August 28, 1997. On September 3, 1997, Respondent had to send the upper right bridge back to the lab for more porcelain to the occlusal surface and recemented the temporary bridge, which had broken and presumably was repaired again. On October 10, 1997, Respondent cemented the permanent upper right bridge and adjusted it two weeks later. On October 27, 1997, Respondent again recemented the upper right bridge, noting that he was going to submit to W. C.'s insurer a request for pre-approval of a sinus lift in the upper right quadrant. This note states that Respondent was not going to permanently cement the upper right bridge (presumably, again) until he received a response from the insurer. On January 6, 1998, W. C.'s temporary upper right bridge was loose, and Respondent recemented it. For the first time in nearly nine years, based on the notes in the record, attention was also focused on the area of the lower left bridge. Respondent noted pockets of 4-5 mm at tooth number 20. Scaling removed a large seed hull from the vicinity of teeth numbers 20 and 21. On June 10, 1998, W. C. visited Respondent with complaints of sensitivity in the area of the lower left bridge. Respondent took periapical and bitewing x-rays of tooth number These x-rays, which are part of the dental records, justify the root canal for tooth number 20 that Respondent proposed, if the tooth were to be saved for use in the bridge, which was W. C.'s desire. Respondent's notes reflect that he scheduled a root canal for tooth number 20 on the next office visit. A root canal may be called for due to irritation or infection in the tooth's pulp. To perform a root canal, a dentist drills a hole through the crown to access the tooth's pulp and nerves, removes the pulp and nerves for disinfection, fills the resulting cavity, and reseals the tooth. The intent is to clean out the area to the far end of the root, which is called the apex. Overinstrumentation of the cavity or overfilling of the cleaned-out cavity may result in fill escaping beyond the tooth's apex. Underinstrumentation of the cavity results in fill failing to reach to the tooth's apex. On July 1, 1998, Respondent performed a root canal on tooth number 20. Respondent cut a hole in the crown that had already been placed on the tooth and proceeded to clean out and disinfect the interior of the tooth. After he was finished, he placed composite fill to reseal the tooth. Respondent completed the root canal in this single visit. His records adequately record the procedure. Although Respondent had taken intraoperative x-rays that revealed the location of the endodontic cleaning instrument--a file--relative to the apex of tooth number 20, the post-operative x-ray revealed that the fill extended beyond the apex of the tooth almost 3 mm. This means that the fill extended beyond the tooth and into the bony area surrounding the tooth. Dr. Haering testified with evident conviction that the standard of care requires fill to the apex, but not beyond. Dr. Haering testified that the standard of care permits the fill to end 0.5 mm short of the apex. He noted that the standard of care is not violated by an apical puff, in which cement may spiral out during application beyond these limits, but added that this case is not an example of an apical puff. Dr. Haering explained that fill past the apex much more often than not will create sensitivity and will require correction. He testified that "every clinical exam" administered to dental students requires zero extrusion of fill past the apex. The dental records do not reveal any post-operative instructions. Dr. Haering stressed the importance of such instructions after this procedure, more than any other in this case, because of the likelihood of pain from the extrusion of the fill past the apex. Dr. Haering did not find fault with Respondent's practice of performing a root canal and "permanently" sealing it in a single visit. One week later, W. C. returned to the office, complaining of pain at the site of tooth number 20. Respondent reopened the root canal and recleaned the area, although nothing suggests that he found it necessary to readdress the extent of the fill. Respondent applied xylocaine in the cavity and temporarily resealed it until W. C. could return on July 15 for further treatment. He also prescribed an antibiotic and a painkiller. During this visit on July 8, Respondent noted that the upper right bridge was loose. On July 15, W. C. returned to the office and presented again with complaints of pain. However, the notes reveal a loosened lower left bridge, so it is unclear whether the recently treated tooth or the lower left bridge was causing the pain. Unable to remove the bridge, Respondent had to cut it out. He then removed the temporary fill for tooth number 20, rechecked the tooth, and completed the endodontic treatment of this tooth by placing permanent fill in the cavity. During the same visit, while the bridge was off, Respondent also retreated a root canal previously done on tooth number 21, which appears not to have been retreated since it was originally done in 1982. Respondent temporarily sealed the cavity in tooth number 21 and permanently resealed it during an office visit two weeks later. Respondent prescribed an antibiotic and Motrin. The Administrative Complaint alleges that Respondent inadequately shaped and improperly filled the cavity left after the root canal of tooth number 21. During the operative timeframe, Respondent did nothing more than clean out the existing cavity left by the previous root canal, and nothing suggests that Respondent extended the cavity in tooth number 21 beyond the tooth's apex or that he overfilled or underfilled this cavity. Dr. Haering testified that a postoperative x-ray of tooth number 21 revealed that the fill in that cavity did not extend to the apex, although he fails to specify by how much the fill was short. He testified that the applicable standard of care requires filling to the apex. However, as noted above, when testifying about the root canal of tooth number 20, Dr. Haering conceded that 0.5 mm short is acceptable, and a dentist would always want to be short rather than long with the fill. From an endodontic perspective, Petitioner has failed to make a standard-of-care case against Respondent for his retreatment of tooth number 21. Nothing suggests that he did any more than re-clean the preexisting cavity left after a root canal performed many years prior to the operative timeframe. Nothing suggests that Respondent underfilled the cavity, such as by leaving a gap, nor does clear and convincing evidence establish that leaving the fill short--by whatever amount it was short in tooth number 21--would violate the applicable standard of care. From an endodontic perspective, the standard-of-care case as to tooth number 20 is closer. Respondent probably overinstrumented the cavity and clearly overfilled the area past the apex. However, post-operatively, Respondent treated the pain at the site during the July 8 visit when he removed the permanent fill, injected a painkiller, and placed temporary fill in the cavity, as well as prescribing an antibiotic and painkiller. Although Respondent still complained of pain at the follow-up visit on July 15, it is at least as likely that the cause was the loosening of the lower left bridge, given the fact that Respondent did not retreat the endodontics and the records reveal no more complaints of pain in this area in the ensuing months. It appears that Respondent successfully treated tooth number 20, whose failure, years later, is more likely due to the failure of the blade implant at site 18 than to this root canal. In light of these developments, as well as Dr. Haering's inconsistency as to whether a short fill necessarily violates the standard of care, the testimony of Respondent's expert witness, Dr. Robert Fish, as to overfills is entitled to greater weight, at least as to whether an overfill or underfill is, in itself, a violation of the applicable standard of care. Dr. Fish properly stressed that teeth numbers 20 and 21 lasted for the duration of treatment and their ultimate failure was due to the loss of support of the aged blade implant at site number 18, not due to endodontic failure. This failure occurred two years and nine months after Respondent's endodontic work in July 1998. Dr. Fish's testimony is more persuasive as to the endodontics, although his testimony that tooth number 20 was not overfilled and that intentional overinstrumentation is sometimes required to ensure the removal of all infected material is not credited. For these reasons set forth above, Petitioner failed to prove that Respondent violated the applicable standard of care in the root canal that he performed on tooth number 20. Additionally, Petitioner has failed to prove a dental records violation with respect to these root canals. As Dr. Fish testified, the pre-operative x-rays themselves justify the course of treatment. Contrary to the allegations, Respondent recorded symptoms of pain with respect to both teeth. Contrary to Petitioner's contention, nothing in the record explains why Respondent would have to perform a periodontal exam before doing a root canal on tooth number 20 or revising a root canal on tooth number 21, especially when neither tooth failed until the old blade implant at site number 18--not, as alleged, placed by Respondent--failed nearly three years later. The preoperative x-rays showed adequate bone and no periodontal pathology to suggest any periodontal issues with these teeth prior to the endodontic work that Respondent did. The mobility that later developed in teeth numbers 20 and 21 was due to the ultimate failure of the blade implant at site number 18, which took place long after the endodontic work of Respondent on teeth numbers 20 and 21. The only remaining issue concerning the Root Canal Counts is tooth number 6. As noted above, the allegations pertain to root canal procedures performed on tooth number 6 from 1998 through 2001 or 2002. Respondent performed no such procedures on tooth number 6 during these timeframes. For these reasons, Petitioner has failed to prove the recordkeeping and standard-of-care Root Canal Counts. On July 23, 1998, W. C. presented for a repair of the porcelain on tooth site number 3 in the temporary upper right bridge. Respondent also scheduled W. C. for preparation of a new bridge to replace the lower left bridge that he had had to cut off. On the next office visit, which was July 29, Respondent took a final impression for a new lower left bridge. During this visit, he recemented the temporary bridge into place and, according to the notes, discussed shade and coping options with W. C. On August 4, Respondent recemented the temporary lower left bridge, but, on August 17, he had to return it to the lab after another try-in. Ten days later, Respondent had to recement the temporary lower left bridge. Three days later, on August 30, W. C. returned with the temporary bridge broken, and Respondent repaired it and recemented it. On September 15, 1998, the coping failed, and Respondent returned the lower left bridge with a new occlusal mounting. On October 9, 1998, Respondent cemented the permanent lower left bridge, which remained in place until its removal on February 19, 2001. Dr. Fish testified persuasively that there were no violations of the standard of care during this period. He testified that the notes were sufficient for what was essentially revisionary treatment of pre-existing dentistry in the form of the placement of both bridges. The sectioning of the lower left bridge at the time of the endodontics was merely reflective of the age of the bridge, according to Dr. Fish, and the sensitivity that required the root canal of 20 and retreatment of a pre-existing root canal in 21. For the upper right quadrant, where Respondent had placed a permanent bridge in October 1997, he had to recement the bridge in January and again in July and then repair it later in July when a pontic broke. But there were no more problems with this bridge in 1998. It is true that in 1997, prior to the operative timeframe, this bridge suffered more failures, but the first two loosenings--in May and June 1997--appear to be related to problems with tooth number 6, prior to its root canal. Later problems with loosening and breakage involved the temporary, except for one recementing of the new permanent on October 27, 1997. Significantly, Respondent attached to the notes for this visit the need to obtain pre-approval from W. C.'s insurer for a sinus lift, which, as described below, is necessary to permit the placement of implants in an area where the bony area was insufficient for implants. For the lower left quadrant, where Respondent had performed the root canal and root canal retreatment described above, there were two or three recementings of the temporary lower left bridge that Respondent placed after he had to remove the pre-existing lower left bridge to deal with teeth numbers 20 and 21. The additional work consisted of taking impressions for a new bridge, trying it on for size, and fixing breaks in the temporary lower left bridge--all ending with the placement of the permanent lower left bridge on October 9, 1998. After delivering the permanent lower left bridge, the next time that W. C. visited Respondent's office was on February 19, 1999, for full-mouth x-rays and, three days later, for a periodontal screening. The x-rays revealed some caries under the upper right bridge. During the cleaning that took place on February 22, W. C. declined Perioguard, a medicated rinse for gum health. This is a relatively inexpensive way to facilitate healthy gums and suggests that W. C. may have been reluctant to assume his share of the responsibility for maintaining good dental health. A note on March 23, 1999, states that W. C.'s physician recommends postponing treatment due to a heart problem. The postponed dental treatment is not specified, but it is the sinus lift, for which Respondent had sought pre- approval from the insurer. The sinus lift would require intravenous sedation, which, due to W. C.'s health problems, required clearance from his physician. Thus, this note implies that Respondent continued to recognize that the status quo was not sustainable for the upper right quadrant and that a more- lasting solution required a bone augmentation in order to permit the placement of implants to better secure a fixture in the upper right area. Almost as important as Respondent's recognition of the need for a sinus lift is the timing of it: it does not accompany any failure of the permanent upper right bridge that Respondent had seated in October 1997. Instead, the note confirms that Respondent was aware that the upper right bridge was precarious and needed to be readdressed. Consistent with Respondent's recognition of the need to proceed with a bone augmentation and implants in the upper right quadrant, on June 9, 1999, W. C. returned to the office because the upper right bridge had fallen out of his mouth while brushing his teeth. The dental note for this visit states that W. C.'s physician advises that the patient cannot undergo intravenous sedation until early September at the earliest. The note concludes with the tentative scheduling of a pre-operative sinus lift followed by an implant. During the operative timeframe, the instability of the upper right bridge was not due, as Petitioner contends, to Respondent's placement of an excessively long and wide post when doing the root canal in tooth number 6 prior to the operative timeframe; the upper right bridge had had problems before that root canal was performed, and the evidence is mixed as to whether this tooth even had an excessively long post--an issue outside of the scope of this case due to the pre-1998 date of service for this procedure. Nor does there seem to have been a problem with the implant at site number 2 that Respondent had placed prior to the operative timeframe. Respondent's expert, Dr. Carl Misch, testified persuasively that the implant served as an acceptable abutment. (Misch deposition, p. 35.) Also, Respondent's placement of an implant at site number 2 is an issue outside the scope of this case due to the pre-1998 date of service for this procedure. During the operative timeframe, the immediate need-- given W. C.'s rejection of removable dentures--was the placement of multiple implants in the upper right area, as Respondent recognized at the time. This is a fact agreed to by Petitioner's expert, Dr. David Clary, (Clary deposition, p. 19.), and Dr. Misch, who succinctly explained: between tooth number two and tooth number six there are no teeth. [B]etween those two teeth, which is basically the last molar on the upper right and the eye tooth on the upper right, this patient is missing three teeth. And as a consequence of that span a good option . . . is to put some implants in that span. However, if you don't have any bone you can't place implants. (Misch deposition, pp. 32-33.) On August 30, 1999, Respondent took another x-ray of W. C.'s mouth. This is the x-ray that Dr. Haering testified was necessary, before undertaking a sinus lift, to determine the thickness of the bone at the intended site of the implant. During this visit, Respondent scheduled W. C. for intravenous sedation and a sinus lift between September 9 and October 19. A sinus lift is a not-uncommon procedure that may be performed by a general dentist to augment bone in preparation for implant surgery. If the patient's sinus drops down too far, it leaves insufficient bony structure to secure the implant, so the dentist moves the membrane of the maxillary sinus and applies a paste derived from freeze-dried bone. The new material is then sutured into place. Eventually, the new material integrates into the adjacent bone, essentially augmenting the available bone to allow, in this case, the successful placement of implants. On October 4, 1999, Respondent removed the upper right bridge and performed a sinus lift in the area of the upper right quadrant. As conceded by Petitioner's expert, Dr. Gerald Laboda, an oral and maxillofacial surgeon, Respondent's notes adequately detail the sinus lift procedure and materials used, although they omit mention of the fact that W. C. bled heavily and had to go to the emergency room for treatment. However, a note one week later states that W. C. was doing well and not in any pain. Obviously, the bleeding that necessitated a visit to the emergency room is a serious matter. Dr. Laboda testified that the medial wall of the sinus is the lateral wall of the nasal cavity, and Respondent "may" have penetrated this wall accidentally during the procedure. Dr. Laboda was ambivalent in opining whether the applicable standard of care requires a general practitioner to conduct a CT scan prior to a sinus lift in order to identify the anatomy of the patient and reduce the chances of an incident during surgery. On direct examination, Dr. Laboda was unable to say unequivocally that the incident would have been avoided with the anatomical information that a CT scan would have yielded. At one point, Dr. Laboda testified that a general dentist must always obtain a CT scan, in addition to x-rays, prior to performing a sinus lift, but then he quickly characterized this statement merely as a recommendation. Some of Dr. Laboda's ambivalence may be explained by the testimony of Dr. Misch on this point. He testified that x-rays alone met the standard of care and a CT scan exceeded the standard of care, (Misch deposition, p. 66.), but he stated that he has used a CT scan prior to sinus lifts since 2005, even though this practice is still not the standard of care. (Misch deposition, p. 289.) Considering the testimony of both dentists, it appears that the standard of care may be evolving toward the requirement of a CT scan prior to a sinus lift, but did not so require when Respondent performed the sinus lift in 1999. Additionally, Petitioner's proof on this issue was not helped by the refusal of Dr. Laboda to accept Respondent as his peer in implants, suggesting that Dr. Laboda may not be an especially good source of generally prevailing peer performance, and the refusal of Dr. Haering, Petitioner's lone witness who was a general dentist, to opine as to the sinus lift. Likewise, the records justify the course of the treatment in terms of the sinus lift. The need for this procedure is reflected in the records, including the x-rays, which revealed that implants could not be placed unless the bone was augmented. The other notes justifying this course of treatment have already been detailed above. On February 7, 2000, after giving the bone augmentation time to stabilize, Respondent placed an implant in site 3 and an implant in site 4, according to Dr. Clary's interpretation of the record, which is credited. There does not appear to be any real issue with the placement of these implants, which, surprisingly, works somewhat to the disadvantage of Respondent as to recordkeeping, for the reasons set forth below. Dr. Misch testified that, judging from the x-rays, the placement of the implants was acceptable. (Misch deposition, p. 294.) Dr. Laboda testified that the placement of the implants did not violate the applicable standard of care, and he could not opine as to why any implants failed (if, in fact, they did), although he attributed his inability partly due to Respondent's records, which he deemed inadequate. Respondent also replaced the temporary upper right bridge at this time, but his main focus was, of course, on the two new implants. An x-ray on February 29 disclosed that "everything [was] healing well." However, on March 23, a note written by someone other than Respondent states that x-rays were taken and tissue was growing around the bridge, but W. C. needed to return to the office to see Respondent "to have removed"-- apparently, referring to the implants, but possibly the bridge. Four days later, the same person wrote that the bridge was removed, revealing 6 mm pockets around the "implant," although the pockets were around both implants. Without further analysis in the records, Respondent removed the implants. Based on the dental records, the removal of the implants seems to have simply happened. The finding of 6 mm pockets, without more, explains nothing. The placement of the implants was, as noted above, unremarkable. Dr. Laboda explained that 6 mm pockets are not necessarily pathological, and the sole reason for removing the implants is mobility, about which Respondent's notes state nothing. Dr. Laboda added that six-week implants are still integrating into the bone, so concern with these pockets should dictate nothing more than a trimming of the gum around the implants, a procedure known as a gingivalplasty. When asked why a dentist would remove implants with 6 mm pockets, Dr. Misch, acknowledging that some dentists would repair them, never addressed why this condition would justify removal; he merely addressed what other dentists would do. (Misch deposition, p. 296.) Dr. Fish's testimony is unpersuasive on this point. He testified that diagnosis was ongoing--evidently confusing findings of pockets with the diagnosis of a problem requiring the removal of the implants and, more importantly, with careful analysis of the course that the patient was taking with the implants. Dr. Fish also tried to justify the scant records concerning the removal of the implants based on the "fact" that the treatment plan was based on the presentation of an episodic problem. This clearly misses the mark: Respondent had been trying to initiate a treatment plan for the upper right bridge for two years and finally, with the clearance obtained from W. C.'s physician, was able to execute the plan. The best that Dr. Fish could offer, after looking at an x-ray, was that one implant "might" start to travel--hardly justification for the removal of the two implants after only six weeks. Dr. Fish's testimony that Respondent was diagnosing W. C. continuously following the implants, implying some insight on Respondent's part as to why he thought that the implants had failed or were failing, contradicts the more persuasive testimony of Dr. Misch, who stated that, typically, a dentist does not know why an implant fails. (Misch deposition, p. 68.) Respondent testified that he removed the implants due to the presence of the 6 mm pockets. He testified that the problem was not so much periodontal as that the surgical site needed more time to heal. (Respondent deposition, pp. 40-41.) This testimony suggests that the implants may have been placed prematurely, or at least that Respondent thought so. Either way, Petitioner has proved a standard-of-care violation as to the removal of the implants. If Dr. Laboda's testimony were credited over Respondent's testimony on the status of the implants at the time of their removal, and it is, Respondent violated the standard of care by removing these implants prematurely and subjecting an elderly patient unnecessarily to the trauma of the removal and, as noted below, replacement of these implants a short time later. If Respondent's testimony were credited on the status of the implants at the time of their removal, and it is not, Respondent violated the standard of care by placing the implants prematurely. In this instance, the records are silent as to the reason for the removal of these two implants because there was no good reason to do so at that time. Thus, Petitioner has proved the standard-of-care Implant Count. Petitioner has also proved the recordkeeping Implant Count in the removal of the implants. As Dr. Laboda testified, when admitting that he could not explain the failure of the implants, the problem lies in the scant information contained in Respondent's records. Records justifying the course of treatment would detail the case sufficiently so it would be clear whether the implants were placed prematurely or, as is found, they were removed prematurely. If the pockets alone warranted the removal of the implants, Respondent needed to document this fact to justify their removal, rather than treatment of the gums, and to guide his or another dentist's attempt to place implants in the upper right quadrant of W. C.'s mouth in the future. If the implants were mobile, Respondent needed to state this fact, again for the same purposes. On May 8, 2000, using local anaesthetic, Respondent added bone to the area where he had performed the sinus lift and had placed and later removed the two implants described above. Checking them for the first month at two-week intervals and then one month later, on July 5, 2000, Respondent noted that the tissue was healing fine. Later in July, as well as in August, September, and October, Respondent had to repair the temporary bridge, as the permanent bridge still awaited the successful seating of two implants at sites 3 and 4. On November 13, 2000, Respondent again placed implants at sites 3 and 4. He noted the procedure as he had the previous procedure. These implants performed fine and integrated into the surrounding bone as intended. After a series of fittings, Respondent delivered the permanent fixtures for the upper right quadrant on May 22, 2001. Acknowledging the stability problems with the upper right bridge in its past configuration--although failing to mention this analysis anywhere in his notes--Respondent chose not to try to use a single bridge. Toward the back, he splinted together implants at sites 2, 3, and 4. Toward the front, he cantilevered a pontic at site 5 off natural teeth 6, 7, and 8. Petitioner's expert, Dr. Clary testified that he was "very fine" with the design for 2, 3, and 4. (Clary deposition, p. 123.) Dr. Clary expressed concerns about the cantilever bridge that extended from abutment teeth numbers 6, 7, and 8 to the pontic at site number 5. (Clary deposition, p. 124.) In particular, Dr. Clary questioned the length of the post in tooth number 6, for which, as noted above, Respondent had performed a root canal prior to the operative timeframe. (Clary deposition, p. 125.) Ultimately, Dr. Clary's concerns about the cantilever bridge are unpersuasive. The contemporary reader of Respondent's notes probably would not have known that Respondent delivered two fixtures on May 22. Prior to May 22, the lone indication of two fixtures is a brief note, dated May 2, that states that Respondent repaired the broken upper right bridge by cementing 6-8 with one bond and 2-4 with a different bond. More significantly is the omission of any findings or analysis supporting the choice to divide the upper right bridge into two fixtures. The notes continue to refer to a single "1-8" structure on May 14 during a try-in, May 16 concerning a production process, and May 22 at the time delivery. After the hint contained in the May 2 note, the next mention of a shorter fixture is a note on June 4 referring to a "6-7" bridge, evidently for delivery by the next visit, at the end of a note describing a porcelain failure of the crown for tooth number 6. Also, on June 26, the notes state that a metal fracture--not the fault of Respondent--occurred on the "bridge" "2-4." Even after these references, a note on August 6 refers to the delivery of "2-8." The notes are consistent with one of two situations, both of which lead to a recordkeeping violation in terms of the bridgework. Perhaps Respondent delivered another iteration of the 2-8 bridge on May 22 and, after encountering one more failure of this design only a few days later, abruptly decided to go with two fixtures. More likely, Respondent actually delivered two fixtures on May 22, and the recordkeeping was slow to reflect this fact. Either way, the records are devoid of analysis supporting the treatment choice of two fixtures. After W. C. switched dentists, he visited Dr. William McKenzie, a periodontist, for a consultation in January 2003 after presenting for x-rays in December 2002. Called by Petitioner as a fact witness, Dr. McKenzie testified that he found that the upper right bridge was "hopeless," (McKenzie deposition, p. 8.), at least partly due to the fracturing of tooth number 6. (In subsequent questioning, Dr. McKenzie clarified that he was referring to the cantilever bridge on teeth numbers 6-8. (McKenzie deposition, p. 13.)) He added that he could recall no other problems in W. C.'s mouth, except for tooth number 16, which lacked bone around it. (McKenzie deposition, pp. 13 and 30.) In particular, Dr. McKenzie saw no problem with the implants. (McKenzie deposition, p. 34.) Dr. McKenzie testified that these problems could have arisen "very, very quickly." (McKenzie deposition, p. 15.) Dr. Misch testified that about ten percent of teeth that undergo root canals suffer problems within eight years (Misch deposition, p. 39), commonly in the form of fractures (Misch deposition, p. 40). When the tooth that has undergone a root canal is used as an abutment for a bridge, the fracture risk may increase four-fold. (Misch deposition, p. 40.) The performance of the upper right bridge and, later, the cantilever bridge, was probably undermined by several factors. First, W. C. would not accept a removable denture, and he may not have been willing to undertake the growing responsibilities that he would have to shoulder to maintain his remaining natural teeth in this area, as the incidence of certain dental problems, like caries, would suggest. Second, teeth numbers 6-8 may have had anomalies of crown height and root length, which combined with the next factor to cause problems. Third, W. C., a tooth grinder, likely placed large loads on the teeth at night, which would be especially problematic during the period, after work on the teeth, that they were to remain unloaded. On this record, though, any problems in the performance of the upper right bridge and, later, the cantilever bridge cannot be attributed to Respondent, so Petitioner has failed to prove the standard-of-care Bridgework Count, at least as to the upper right quadrant. However, Respondent's recordkeeping concerning the upper right bridge failed to justify the course of treatment in one respect: the decision to separate the single fixture into two. When considered from the perspective of Respondent's records, this action has the same deus-ex-machina quality to it as the removal of the implants from sites 3 and 4 in March 2000: without warning, a seemingly outside force implements surprise treatment choices. As was the case with the implant-removal decision, the decision to place an implant splint and a cantilever bridge cannot be inferred or justified from x-rays or other dental records. There are two distinctions between the abrupt decision to place two fixtures and the abrupt decision to remove the implants. First, the treatment regarding the design of the new fixtures for the upper right quadrant does not represent a standard-of-care violation, but actually reinforces the impression that Respondent had a treatment plan in mind--not on paper--from the start of the operative timeframe, if not before. Second, the notes, apart from x-rays, fail adequately to describe the implant splint and cantilever bridge and rely excessively on inference to establish even the existence of these fixtures. The remaining factual issues concern the lower left bridge. As noted above, Respondent delivered the permanent lower left bridge on October 9, 1998. According to the notes, the next time it was addressed was when it was removed on February 19, 2001, which coincides with the end of the most intensive treatment, described above, of the upper right quadrant and precedes the delivery of the two upper right fixtures, also described above, by three months. Although the handwritten dental records do not indicate why Respondent removed the lower left bridge, a note on January 29, 2001, states that W. C. presented with a tooth ache in the lower left quadrant, and an x-ray taken on the same date revealed an infection around the blade implant at site number (Respondent deposition, pp. 56 and 58.) (Respondent's response on page 58 that the blade implant was placed in 1998 was either inaccurate or inaccurately transcribed given the era in which blade implants were used and Respondent's interrupted testimony, on the next page, suggesting that another dentist placed this implant, which, if 1998, would have been when Respondent was treating W. C. and routinely doing implants.) On February 19, Respondent placed a temporary lower left bridge and prepared for the production of a new permanent bridge. He also prepared a post and core for tooth number 20. On March 20, Respondent cleaned up the area around the blade implant at site number 18 and placed some bone material in the area to build it up to better secure the blade implant. After doing this work, on the same day, Respondent cemented the temporary lower left bridge. Respondent recemented the temporary lower left bridge the day after W. C. was hospitalized for "lethargy," according to a note on March 27, 2001. On April 9, the records note that the tissue looked good. On April 23, Respondent again recemented the temporary lower left bridge. Initially misreading his own notes, Respondent testified that he did the final impression for the lower left bridge on April 23 when he actually did the final impression for the upper right bridge/fixtures on that date. (Respondent deposition, pp. 61- 62.) When advised of this error, Respondent testified that he did eventually replace the lower left bridge with a permanent fixture, but it is not reflected in the notes. (Respondent deposition, p. 62.) This is an odd answer because the notes actually document the delivery of the permanent lower left bridge on July 8, 2002. After April 23, the next reference to the lower left quadrant in the notes is June 26, 2001, when Respondent had to recement the temporary lower left bridge. On August 20, 2001, the notes indicate that Respondent "attempted to restore 20, 21 guarded." Evidently, the attempt was short-lived and the deterioration from guarded to hopeless was quick because the same note--confirmed by Respondent as accurate (Respondent deposition, p. 63)--is that he extracted teeth numbers 20 and 21. On August 27, 2001, W. C. returned to the office. Respondent recommended a treatment plan to include the placement of four implants in the lower left quadrant. Due to cost considerations expressed by W. C., Respondent only placed three implants, which took place on October 31, 2001. The October 31 note adequately describes the procedure. The implants integrated into the surrounding bone after a brief infection shortly after their placement. On April 17, 2002, Respondent restored the implants and placed a temporary lower left bridge. On May 8, 2002, Respondent took a final impression for a bridge from site number 18 to site number On July 8, 2002, Respondent delivered the permanent lower left bridge. The professional relationship ended with a note on July 31 that W. C. agreed to pay the balance in three weeks; he later failed to appear for an appointment on January 30, 2003. Of course, by this time, he had presented for x-rays and been seen by Dr. McKenzie on a consultation in connection with dental work that W. C. was undertaking with another general dentist. The recordkeeping fails to justify the course of treatment as to the removal of teeth numbers 20 and 21. Respondent could explain orally that these two teeth became mobile when they lost the support they required from the blade implant at site 18, but nothing in the records mentions this fact, and, from the perspective of the records, these two extractions just seem to happen. However, Petitioner already proved the recordkeeping Bridgework Count in connection with the treatment decision to divide the single upper right bridge into two fixtures, so this additional violations may only have a bearing on the penalty. The lone count not yet proved, but still at issue in connection with the lower left bridge, is the standard-of-care Bridgework Count because Petitioner failed to prove this count in connection with the upper right bridge. Dr. Clary testified that he had no problem with the decision to place implants at site numbers 20 and 21; his lone criticism of this treatment is that it did not take place in 1998. (Clary deposition, p. 99.) Nor did he disagree with the placement of the third implant at site number 18. (Clary deposition, p. 100.) Questioning whether the standard of care permits the connection of implants to natural teeth (Clary deposition, p. 100), Dr. Clary conceded that this is a point of controversy within the dentistry profession (Clary deposition, p. 101), implicitly admitting that the standard of care does not prohibit this practice. Dr. Clary conceded that controversy also existed as to the type of connector--ridged or unridged-- that should be used for these implants and natural tooth. (Clary deposition, p. 102-03.) In sum, Dr. Clary did not try to make much of a case as to the standard of care concerning the lower left bridge, especially if one accepts the fact that patient resistance precluded the use of a removable denture in this area and that extensive work on the lower left bridge probably had to await completion of the extensive work on the upper right bridge, given W. C.'s financial constraints and the practical problem of ensuring that he could chew on at least one side of his mouth for weeks at a time. Likewise, Dr. Laboda did not fault the placement of any implants; his focus was on the sinus lift and recordkeeping. Thus, Petitioner has failed to prove a standard-of-care violation with respect to the bridgework in the lower left quadrant. Based on the foregoing, Petitioner has proved only the following violations. First, Petitioner proved the recordkeeping Bridgework Count (Count I) concerning Respondent's decision to replace the single upper right bridge with two fixtures in May 2001. This was a good treatment choice. However, Respondent not only failed to document the reasons for this choice or findings that would support this choice; he even failed to identify adequately the treatment choice. Second, Petitioner again proved the recordkeeping Bridgework Count (again, Count I) concerning Respondent's decision to extract teeth numbers 20 and 21 in August 2001. Relying on Dr. Clary's testimony, this was probably a good treatment choice, although Dr. Clary's testimony that this action should have been taken in 1998 is not credited, at least as to the implication that it violated the standard of care for Respondent not to have taken this action earlier. Third, Petitioner proved the recordkeeping Implant Count concerning the sudden removal of the recently placed implants at site numbers 3 and 4 in March 2000. Fourth, Petitioner proved the standard-of-care Implant Count concerning the premature removal in March 2000 of the recently placed implants at site numbers 3 and 4, although the consequences of this departure from the applicable standard of care are slight due to Respondent's immediate addition of more bone, using only local anaesthetic, and successful replacement of implants at these two locations. Aggravating factors are the number of times that the Board of Dentistry has disciplined Respondent, including one case involving a recordkeeping violation; and the presence of three separate recordkeeping violations in this case (although two of them are alleged in the same Bridgework count). Mitigating factors are the lack of danger to the lone patient from, and the lack of severity of, the proved violations; the reversibility of the limited damage that resulted from the lone standard-of-care violation (i.e., the premature removal of the two implants followed by the addition of more bone and successful replacement of two new implants); the number of years that Respondent has practiced; and the time that has elapsed-- eight years--since the last violation, during the last seven and one-half years of which Respondent has not been disciplined.

Recommendation Based on the foregoing, it is RECOMMENDED that the Board of Dentistry enter a final order finding Respondent guilty of Counts I, III, and IV of the Administrative Complaint and imposing the following discipline: $20,000 administrative fine; license suspension until the greatest of 30 days, full payment of fine, or posting of security adequate to the Board for the full payment of fine; passage of the Florida Rules and Laws exam within one year of the Final Order; probation for the greater of five years or until Respondent successfully completes the two-year remedial course described above; and audits every two years to ensure that Respondent is current on his continuing education. As noted above, a suitable restriction on practice would be an effective substitute for the minimum 30-day suspension described above, although the restriction on practice would need to extend longer than 30 days. DONE AND ENTERED this 17th day of June, 2009, in Tallahassee, Leon County, Florida. ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 17th day of June, 2009. COPIES FURNISHED: H. Wayne Mitchell, Esquire Assistant General Counsel Department of Health 4052 Bald Cypress Way, Bin C-65 Tallahassee, Florida 32399-3265 Max R. Price, Esquire Law Offices of Max R. Price, P.A. 6701 Sunset Drive, Suite 104 Miami, Florida 33143 Susan Foster, Executive Director Board of Dentistry Department of Health 4052 Bald Cypress Way Tallahassee, Florida 32399-1701 R. S. Power, Agency Clerk Department of Health 4052 Bald Cypress Way, Bin A02 Tallahassee, Florida 32399-1701 Josefina M. Tamayo, General Counsel Department of Health 4052 Bald Cypress Way, Bin A02 Tallahassee, Florida 32399-1701 Dr. Ana M. Viamonte, Secretary State Surgeon General Department of Health 4052 Bald Cypress Way, Bin A00 Tallahassee, Florida 32399-1701

Florida Laws (4) 120.569456.072458.331466.028 Florida Administrative Code (1) 64B5-17.002
# 7
PETER V. EREG, ELIZABETH S. EREG, BARBARA L. LACINA, HERBERT W. WARNER, CHRISTINE D. ABRAM, AND BUNNY L. GARST vs DEPARTMENT OF TRANSPORTATION, 94-004634 (1994)
Division of Administrative Hearings, Florida Filed:Bradenton Beach, Florida Aug. 18, 1994 Number: 94-004634 Latest Update: Oct. 04, 1999

The Issue The issues in this case are whether the Department of Transportation abused its discretion in deciding to replace an existing drawbridge with a fixed-span, high-level bridge and whether the Department of Transportation violated the statutory requirement of public hearings with effective public participation prior to selecting, siting, and designing the fixed-span, high-level bridge. Prior to referring this matter to the Division of Administrative Hearings, the Department of Transportation determined as a matter of law that Petitioners lacked standing to challenge the Florida Transportation Plan. The Department of Transportation therefore declined to refer to the Division Petitioners' challenge to the Florida Transportation Plan. For this reason, the recommended order does not address the issue whether the Florida Transportation Plan appropriately includes the proposed bridge or whether the Department of Transportation correctly determined that Petitioners lacked standing to raise this issue.

Findings Of Fact Parties Intervenor Save Anna Maria Island, Inc. (SAM) is a not- for-profit corporation organized to inform the residents of Anna Maria Island about the proposal of the Department of Transportation (DOT) to replace the Anna Maria Island Bridge with a fixed-span, high-level bridge. The general purpose of SAM is to preserve the environment and character of Anna Maria Island by persuading DOT not to proceed with the proposed project and encouraging local officials to join SAM in opposing the project. Some members of SAM live in Sunbow Bay and West Bay Cove, which are condominiums near the proposed project. Most members of SAM and at least some Petitioners reside on Anna Maria Island. Intervenor Robert E. VanWagoner lives on Anna Maria Island. Petitioners, Intervenor VanWagoner, and members of SAM use the Anna Maria Island Bridge, driving motor vehicles across the bridge on errands to the mainland, fishing from the bridge, and walking, jogging, and bicycling on the bridge. Due to their proximity to the bridge and Sarasota Pass, Petitioners and Intervenors have a heightened interest in the environmental, cultural, and aesthetic ramifications of the replacement of the Anna Maria Island Bridge with a fixed-span, high-level bridge. Petitioners and Intervenors would be uniquely impacted by any abuse by DOT in the exercise of its planning discretion in deciding to build the fixed-span, high-level bridge. Petitioners and Intervenors have participated in the transportation- planning process culminating in DOT's decision to replace the Anna Maria Island Bridge with a fixed-span, high- level bridge. Petitioners and Intervenors would be expected beneficiaries of additional public hearings or enhanced public participation concerning the proposed project. Petitioners and Intervenors would be uniquely impacted by any violation by DOT of statutes requiring public hearings with effective public participation. Anna Maria Island Bridge and Proposed Bridge Manatee Avenue, which is part of State Road 64, connects Bradenton on the east with Anna Maria Island on the west. The road segment between the mainland and the island is a minor urban arterial. The road spans Sarasota Pass, which is also known as Anna Maria Island Sound, by the Anna Maria Island Bridge about 7.2 miles west of U.S. Route 41 (Business) in downtown Bradenton. The Anna Maria Island Bridge is a drawbridge or bascule bridge that was built 37 years ago. The deck of the drawbridge is 25 feet above the water at mean water, and the vertical clearance with a closed bascule is 17.5 feet at mean high water. (All elevations over the water and all water depths are relative to mean water, unless otherwise stated.) The bridge spans are 48 feet long, and the bascule span is 128 feet long. The bridge is scuppered so that untreated stormwater runs off the edge of the bridge into the water below. The Anna Maria Island Bridge is 3123 feet long and 37.4 feet wide. It contains two 12-feet traffic lanes, no shoulders, and two five-foot sidewalks separated from the traffic lanes by nine-inch curbs. The bridge is not lighted except for navigation lighting in its below-deck structure. Manatee Avenue consists of two lanes on both sides of the Anna Maria Island Bridge. A shorter, two-lane bridge lies between the Anna Maria Island Bridge and the mainland. The speed limit along the approaches and on the Anna Maria Island Bridge is 50 miles per hour. The approach roadway consists of two 12-foot traffic lanes with 8-foot gravel shoulders. There are no sidewalks or bicycle paths along the approaches to the bridge. Gulf Drive is the major north-south road on Anna Maria Island, intersecting Manatee Avenue one-half mile west of the Anna Maria Island Bridge. At least partly designated as State Road 789, Gulf Drive is a two-lane arterial under state jurisdiction south of Manatee Avenue and a two-lane collector under city jurisdiction north of Manatee Avenue. There is little if any opportunity to expand the capacity of Gulf Drive or other roads on the largely developed island; though heavily travelled during peak periods, most if not all of these roads are constrained. Average daily traffic across the Anna Maria Island Bridge in 1988 was 14,000-15,000 vehicles. A traffic signal at Gulf Drive is the major cause of traffic congestion on Manatee Avenue at the bridge. On Friday and Saturday nights, traffic at the light often backs up past the bascule. Compared to the Anna Maria Island Bridge, the proposed bridge would be a little longer, at 3372 feet long, and half again as wide, at 54 feet wide. On a 4 percent grade, the deck would be 75 feet high at the center with two 12-foot travel lanes, two 10- foot shoulders, and one six-foot sidewalk separated from the traffic lane by a sturdier divider than those separating the sidewalks from traffic lanes on the Anna Maria Island Bridge. The spans of the proposed bridge would be three times longer than the spans of the Anna Maria Island Bridge. The tripling of widths between supports under the bridge would open up the view under the bridge and facilitate the bypassing of the channel by small boats cutting under the bridge. At mean high tide, the vertical clearance at the edge of the navigation channel would be 65 feet. At 800 feet from either shore, the slightly asymmetrical bridge would be 40 feet high at the west end and 45 feet high on the east end, according to the bridge profile in the Final Bridge Concept Report. The northern edge of the proposed bridge would be 20 feet south of the southern edge of the Anna Maria Island Bridge. Construction of the proposed bridge would take about two years. Demolition of the existing bridge would be by unspecified means, probably explosives, following completion of the construction of the new bridge. The proposed bridge would combine stormwater treatment with scuppers. The stormwater treatment would extend from the ends of the bridge 300 feet toward the center, leaving untreated stormwater along most of the proposed bridge. The untreated area on the proposed bridge would exceed the untreated area on the Anna Maria Island Bridge by over one-half acre. However, the additional amount of stormwater contaminants entering the water would be limited to road surface particles and road cleaners because no additional traffic would use the proposed two-lane bridge. Anna Maria Island and Sarasota Pass Anna Maria Island is a barrier island between Sarasota Pass to the east and the Gulf of Mexico to the west. For the most part, Anna Maria Island is less than one-half mile wide, except for a canalized area at the north end where a minor bridge connects the island to a small key. The Anna Maria Island Bridge connects the island to the mainland indirectly by way of Perico Island, a noncoastal barrier island to the east of Anna Maria Island. Sarasota Pass is about 6000 feet wide at the Anna Maria Island Bridge. However, when the bridge was constructed, the contractor deposited long fingers of fill at the east and west ends of the bridge. The west finger is about 2000 feet long, and the east finger is about 1000 feet long. Thus, as a result of artificial constrictions, Sarasota Pass at the existing bridge is a little over 3000 feet wide. The City of Holmes Beach lies at the west end of the Anna Maria Island Bridge, although its jurisdiction probably does not include the 2000 feet of fill added when the bridge was built. The City of Anna Maria lies to the north of Holmes Beach at the north end of Anna Maria Island. The Anna Maria Island Bridge is about three miles south of the north end of the island. About two miles south of the Anna Maria Island Bridge lies the Cortez Bridge, which is also a drawbridge of the same vintage as the Anna Maria Island Bridge. The Cortez Bridge, which is shorter than the Anna Maria Island Bridge, serves Cortez Road and connects the mainland to the island at the City of Bradenton Beach, which is the third municipality on Anna Maria Island. Bradenton Beach is a little less than two miles from the south end of the island. The remaining major bridge on Anna Maria Island connects Gulf Drive to Longboat Key to the south. A bridge at the south end of Longboat Key runs to Lido Key, which is joined to the mainland at Sarasota by the Ringling Bridge. The Anna Maria Island Bridge is about 9000 feet south of the confluence of Sarasota Pass and Lower Tampa Bay. The estuarine waters of Sarasota Pass connect the expansive Tampa Bay estuary to the north with the Sarasota Bay estuary to the south. Sarasota Pass and Sarasota Bay are Outstanding Florida Waters. The water in the vicinity of the Anna Maria Island Bridge is Class II water. Seagrass is a key component of the Sarasota Pass estuary. Seagrass is vital to water quality and provides essential habitat and food for wildlife, including wading and diving birds, fish, shellfish, and manatee. Seagrass beds provide nursery habitat for juvenile marine life of considerable importance at maturity to recreational or commercial fishermen and are important foraging areas for snook, spotted seatrout, and red drum or redfish. Seagrass aids water quality by filtering suspended material from the water column and stabilizing the bottom. The resulting improvements in water transparency increase the depths to which sunlight can penetrate. Seagrass is dependent on sunlight. Thus, the deeper that sunlight can penetrate due to water transparency, water color, and other water-quality parameters, the deeper the water in which seagrass can grow. Seagrass is not hardy and is especially sensitive to changes in the amount of light that it receives. Submerged in water, seagrass can be killed by reductions in water transparency, such as those typically accompanying nutrient loading, which can lead to phytoplankton in the water blocking light generally and epiphytes on the seagrass leaves directly interfering with the plant's absorption of light. Seagrass can also die off due to the introduction or resuspension of sediments in the water column, which may result from stormwater runoff, agricultural drainage, boat prop dredging, and construction (references to "construction" include demolition). Another source of seagrass mortality is the introduction or elevation of certain toxic substances in the water column or sediments by way of stormwater runoff, agricultural drainage, boat emissions, or construction activities. Toxic substances include heavy metals and petrochemicals, such as those associated with urban stormwater runoff. Discrete patches of seagrass may also be destroyed by the burrowing and feeding of marine life such as rays. Relatively small reductions in sunlight can destroy seagrass over a wide area. If, while all other factors remain constant, reductions in transparency or increases in turbidity reduce by one foot the maximum water depth at which seagrass can grow, the effects may be widespread in estuarine bottoms, which are often gently sloped. Two factors discourage seagrass recolonization following their destruction, even assuming the elimination of the cause of the seagrass mortality in the first place. First, the species of seagrass involved in this case spread very slowly. Second, even a temporary loss of seagrass may change background conditions to discourage recolonization. Once the seagrass in an area is destroyed, bottom sediments may build up, turbidity may increase, and water transparency may decrease. This process may effectively prevent seagrass recolonization at depths at which seagrass previously grew, regardless whether recolonization is through natural means or artificial transplantation. If an area is so well-flushed as to remove sediments, the loss of the stabilizing bottom vegetation may result in erosion, critically deepening the water depth so that seagrass cannot capture enough light to recolonize the area. The Anna Maria Island Bridge is at the north end of a flourishing seagrass meadow featuring Thalassia, Halodule, and Syringodium. Important areas of seagrass exist north of the bridge, but the dense, lush seagrass meadow to the south is more prolific. Near the Anna Maria Island Bridge, seagrass grows in water as deep as six feet. The record lacks evidence of a comprehensive, detailed bathymetry, but several important facts are clear from available evidence of water depths. First, the water in the middle of the pass under the existing or proposed bridge is too deep for seagrass. Seagrass would not grow in the middle of the pass at this location even if there were no bridge. Second, the water is deeper under the existing bridge than it would be under the proposed bridge. The only place where the water under the Anna Maria Island Bridge is not deeper than the water under the proposed bridge is the westernmost 100 feet, where the water depths are about the same. Most importantly, the depths under the Anna Maria Island Bridge are too great for seagrass growth along nearly the entire length of the bridge, even if the bridge were removed. On the other hand, seagrass thrives upon the bottom that would be under at least 1600 feet of the proposed bridge. Suitably shallow depths exist 800 feet along either end of the proposed bridge, and seagrass occupies these areas, which amount to about two acres of seagrass. Despite the known sensitivity of seagrass to changes in lighting, DOT and its consultants never considered how much the proposed bridge would shade these two acres of seagrass. There was no analysis of such factors as the area or duration of the shadow that would be cast at different times of the year by the proposed bridge or the variation in the shadow from the low east and west ends of the proposed bridge to the 40- and 45-foot heights where the seagrass ends. Thus, there is also no evidence of any analysis of the effect of such shading on the seagrass presently growing in the area that would be covered by the proposed bridge. It is more likely than not that the two acres of seagrass presently growing in the area that would be covered by the proposed bridge would be destroyed by the proposed project. If, as is probable, the seagrass did not survive disturbances from construction, including temporary turbidity, recolonization is unlikely due to shading from the new bridge and either long- term turbidity from stirred-up, destabilized sediments or deeper water from erosion. In the unlikely event the seagrass survived the construction, shading from the new bridge would likely kill it anyway and prevent recolonization. But more than two acres of seagrass are imperilled by the proposed project. The record is devoid of any analysis of bottom sediments. For 37 years, the scuppered Anna Maria Island Bridge has dumped untreated stormwater into the water below. The new bridge would add even more untreated stormwater to Sarasota Pass. Stormwater contaminants include a wide variety of potentially toxic materials, such as road materials, tire materials, lubrication, road cleaners, paint, building materials, and virtually anything that might be loaded onto vehicles using the bridge. Common runoff contaminants are heavy metals, hydrocarbons, oil and grease, zinc, and copper. Stormwater pollution of the sediments along the drip line of the Anna Maria Island Bridge is more than a theoretical possibility. Seagrass is generally absent at all depths in the 20 feet immediately south of the existing bridge. (Increased water depths account for seagrass conditions north of the bridge.) The general absence of seagrass in the 20 feet immediately to the south of the bridge is unlikely the result of shading because dense seagrass grows in the 20 feet immediately to the south of the west end of the bridge, and off-bridge shading appears to exist to the north of the bridge, not the south. The general absence of seagrass in the 20 feet immediately south of the bridge is unlikely the result of prop dredging because adjacent seagrass is dense. The general absence of seagrass along the south dripline may be attributable due to the biochemical or mechanical disturbance caused by the stormwater rushing off the bridge. To the extent of mechanical disturbance, the presence of seagrass in the adjacent 20 feet at the west end of the bridge may be due to a lack of proximity to an unblocked scupper drain at that location. To the extent the disturbance may be biochemically caused, this anomaly may reflect variations in flushing. At least 1000 feet of seagrass (500 feet at either end of the new bridge) just south of the proposed bridge would receive untreated stormwater rushing through the scuppers of the proposed bridge. The width of the affected band would presumably be the same 20 feet as the width affected by the existing bridge. It is more likely than not that this half acre of seagrass would not survive the proposed project, especially after consideration of additional seagrass losses from prop dredging caused by small boats bypassing the channel and running between the new bridge's widely spaced supports. Foundations for the proposed bridge would occupy 0.12 acres of seagrass. However, this seagrass would be under the deck of the proposed bridge, so this area has already been taken into account in the shading analysis. In addition to the likely permanent destruction of 2.5 acres of seagrass under, and 20 feet south of, the proposed bridge, it is more likely than not that construction would at least temporarily destroy additional seagrass farther to the south. The proposed project calls for the construction of large work platforms parallel to, and south of, the new bridge and small fingerplatforms running from the work platforms toward the new bridge. The work platforms would be placed in water shallower than six feet and would cover areas vegetated by seagrass. The platforms would be 1100 and 1200 feet long and 40 feet wide and would thus cover a little about two acres of seagrass. The platforms would be low on the water--lower than the existing bridge--and effectively shade the seagrass below them. DOT witnesses promised the use of slatted platforms to minimize shading, but, again, there was no showing that the slats would pass sufficient sunlight at critical water depths for sufficient periods of time. What seagrass survived the construction of the platforms would not survive the shading and turbidity during construction, as this area is well within the mixing zone allowed by the dredge-and-fill permit tentatively approved by the Department of Environmental Protection (DEP; references to DEP include the predecessor agency, the Department of Environmental Regulation (DER), except where references to DER are necessary for clarity). The likely loss of the two acres of seagrass from the work platform would not be permanent absent permanent alteration of the bathymetry, introduction of persistent contaminants, or collection of substantial amounts of sediment during construction in the area under the work platform. Recolonization would probably begin upon completion of the project. The platforms would not remain in place during the entire two-year period of construction. There would be no need for the platforms on the south side of the proposed bridge during the demolition of the existing bridge to the north. It is also possible that the platforms would be removed as construction was finished along the bridge. However, the slow growth of the seagrass suggests that considerable time would be required for the recolonization of the two acres to the present density. There is no reason to calculate lost seagrass from the construction of the fingerplatforms. They will span the area from the south edge of the proposed bridge to the north edge of the work platforms. Thus, they cover the area already affected by the stormwater running off the bridge. The 600- by 20- foot area proposed to be served by the stormwater management system, where adjacent seagrass presumably would not be affected, might be affected by the fingerplatforms, but the small size of the platforms renders the loss unnecessary to consider for purposes of this recommended order. DOT has proposed mitigation to compensate for some seagrass losses. But DOT did not account for the permanent loss of 2.5 acres of seagrass and temporary loss of 2.0 acres of seagrass. The proposed mitigation is ineffective for a number of reasons. The seagrass transplant receiving area proposed for mitigation is too small. It is 0.19 acres as compared to the likely permanent loss of 2.5 acres and temporary loss of 2.0 acres. This is a dramatic departure from the normal seagrass mitigation ratio of 1:1 required by DEP. Although less important due to the gross inadequacy of the size of the transplant receiving site, there is also a major discrepancy between the densely vegetated donor area and the sparse transplantation pattern specified for the receiving area. The primary seagrass mitigation is too speculative. The transplant receiving area is near the natural western shore of the pass. Unlawful boat use of a nearby fishing pier and bioturbation have resulted in barren patches in the transplantation area, but the recolonization process is proceeding naturally. Consistent with the slightly more colored water and somewhat poorer flushing than is found at the bridge, natural recolonization in the transplant receiving area is already establishing as extensive and dense a seagrass bed as boating and bioturbation will permit. The natural recolonization process now taking place in the transplant receiving area will revegetate more quickly and completely the portion of the bottom capable of supporting seagrass than would DOT's mitigation effort. DOT's proposed seagrass transplantation might even disrupt the natural recolonization process. The success of the proposed seagrass transplantation is speculative at best. Seagrass transplantation is complicated and remains experimental. Under the best of circumstances, seagrass transplantation is a complicated process that has not consistently prevented net habitat loss. The DEP witness who reviewed DOT's application is an Environmental Specialist III who has been with DEP nearly nine years and has reviewed over 500 dredge-and-fill permits. Testifying against the permit and particularly the seagrass mitigation plan, he noted that DOT's seagrass mitigation plan promises uncertain benefits. Unsupported by comprehensive bathymetric and water-quality data, the primary seagrass mitigation plan, which is the only one sufficiently detailed to evaluate, more likely than not would fail. The overall seagrass mitigation plan is excessively contingent. The importance of alternative and contingent seagrass mitigation plans is underscored by the likelihood of the failure of the main transplant receiving site and the unlikelihood that seagrass will recolonize under the existing or proposed bridge. But the alternative and contingent mitigation plans are illusory. The alternative and contingent mitigation plans lack success criteria, detailed guidelines for identifying donor and receiving areas, and practicality. The alternative and contingent mitigation plans amount to nothing more than vague and unenforceable undertakings to find seagrass somewhere and transplant it somewhere else. Such a difficult task demands more detail. One of the two crucial functions of seagrass in the immediate area of the Anna Maria Island Bridge is that it is consumed by manatee. Manatee are especially prevalent in an area just north of the bridge. Between 1985 and 1991, there were 432 adult manatee sightings and 44 manatee calf sightings in the vicinity of the Anna Maria Island Bridge. About two-thirds of these 476 sightings were north of the bridge and one-third south of the bridge. Manatee use Sarasota Pass to travel between Tampa Bay and Sarasota Bay. The fill added during the construction of the Anna Maria Island Bridge already constrains the manatee passageway under the Anna Maria Island Bridge by artificially narrowing the pass by about one-third. Construction at either end of the bridge would tend to concentrate the manatee even more toward the center of the bridge where they would more likely encounter boats in the main channel. Estimates in 1987 were that Florida's manatee population is about 1200, with equal numbers on the east and west coasts. Manatee populations are slow-breeding. Gestation runs 13-15 months with one or sometimes two calves born. The breeding cycle is 3-5 years. The natural life expectancy and reproductive life of a female are unknown. The risk of extinction heightens when the low reproductive rate and manatee mortality attributable to collisions with boats and barges are combined with the permanent and temporary loss of seagrass, two-year constriction of the already-reduced passageway at the bridge, and permanent dispersal of small boats through shallow seagrass beds where manatee are likely to feed. The other crucial function of seagrass is in maintaining water quality through the assimilation of nutrients and stabilization of bottom sediments. The water-quality data in this case are limited. DOT never determined the extent to which sediments at the existing bridge may have been contaminated over the years by stormwater-borne heavy metals or oil and grease. DOT never analyzed these sediments by grain size and percentage of fine organic materials. Instead, DOT proceeded with the proposed project in Outstanding Florida Waters without knowledge of these sediments in terms of their chemical composition or susceptibility to resuspension into the water column. IV Planning and Hearing Process DOT's Project Development and Environmental Guidelines Pursuant to its Project Development and Environmental (PD&E) Guidelines, DOT conducts a PD&E study at the start of the planning process for projects of the scope of the proposed bridge. The PD&E manual, which "fully reflects the Department's policy for projected development . . .," assists project managers and district engineers by informing them of various requirements imposed by law on transportation projects and identifying the documentation required in the various stages of the transportation-planning process. Section 2-1 of the PD&E manual describes the Advance Notification process as the means by which DOT advises other federal, state, and local agencies of proposed projects. Chapter 25 of the PD&E manual explains DEP's role in determining whether a proposed project is consistent with the Coastal Zone Management Act. Section 25-2.4 warns that an agency finding of consistency may be changed. Section 3-1 divides proposed projects into three types in terms of environmental impact. Projects with the least impact qualify for a categoric exclusion. Projects with a categoric exclusion include actions that "do not have a significant impact on any natural, cultural, recreational, historic, or other resources [or] do not involve significant air, noise, or water quality impacts[.]" Section 18-2.4 states that a project qualifying for a categoric exclusion "may have an involvement with wetlands so long as this involvement is determined not to be significant." The next class of proposed projects are those subjected to an environmental assessment. For such projects, "the significance of the environmental impact is not clearly established." The environmental assessment is prepared "whenever there is a need to determine the appropriate class of environmental determination required." The last class of proposed projects are those subjected to an environmental impact statement. Such projects "significantly affect the human environment " Projects with a categoric exclusion typically require less public involvement and environmental review than projects requiring an environmental assessment or environmental impact statement. However, Section 8-2.7.2.3 provides: "A public hearing must be held to comply with Chapter 339 F.S. regardless of funding [federal or state] . . . [w]hen a project is controversial in nature." Section 8-2.8 describes public hearings: A public hearing is the official public forum used by the Department through which citizens and government officials express their concerns, opinions, and comments regarding a project. It is by no means the only opportunity whereby citizens have access to the Department about the project, but it is the official point in the project development process where information developed to date [is] shared with the community and the community can go on record officially concerning the project. Much of what is shared with the community has been developed with citizen and local government input during early stages of project development. Section 8-2.8.1 requires a DOT representative to appear at each public hearing to discuss briefly all alternates studied and the advantages of each. The DOT representative must outline the social, economic, and environmental impacts of the project. Revised Section 9-2.1 explains that the Project Concept Report marks the start of the "project development process." This report identifies the activities required to conduct the PD&E study. Section 9.1 describes the engineering reports to be developed during the planning process: The preliminary engineering report is prepared by the District or consultant during the early stages of project development .... After the public hearing has been held and a recommended alternative has been selected the final engineering report is prepared. The final engineering report is submitted after the recommended alternative has been approved by the Federal Highway Administration. . . . Section 9-2.2.1 explains that the Final Engineering Report must follow a sufficient amount of engineering so as to consider types of bridges. Section 10-2.4 identifies the Permit Coordination Package, which DOT sends to all agencies from which it must obtain a permit. The package evaluates the impacts of the project upon permittable areas, addressing such issues as the "elimination of habitat" and "destruction of vegetation." The package also contains a discussion of proposed mitigation. Section 10-2.5 directs DOT to submit permit applications when the "design of the project is 65 to 70 percent complete." Section 13-1 addresses nonfederally funded projects, which the proposed project eventually proved to be. The manual sets forth a number of policies and objectives which DOT "must address to comply with the [Florida Transportation Plan.]" These include provisions to "prohibit the destruction of endangered species and protect their habitats," "promote rehabilitation and reuse of existing facilities, structure and buildings as an alternative to new construction," and "encourage citizen participation at all levels of policy development, planning, and operations." These provisions guide DOT in the preparation of the Florida Transportation Plan and do not apply to individual transportation projects, such as the proposed bridge. Section 13-1 states: "It shall be the policy of the Department to develop environmental studies on all major transportation projects regardless of funding to comply with state and federal laws." Section 13-1 requires DOT to prepare a state environmental impact study on "all major transportation projects" in which state monies are used. Section 13-2.2 defines a "major transportation project" as, among other things, "Replacement of an existing bridge that could have substantial adverse effect on land use, community development patterns, community cohesion or natural ecological systems." If a project is a "major transportation project," DOT must prepare and circulate an Advance Notification Package and conduct a hearing, which must be announced by letters to all owners or property within 300 feet of the centerline of the alternates under consideration. Section 13-2.5 imposes upon DOT the same public hearing procedures as set forth in Chapter 8 of the PD&E manual. Proposed Project 1. 1987-89 In 1987, DOT started a bridge replacement program to identify bridges for possible replacement or widening. According to Robert Crim, DOT's project manager for the proposed bridge, one objective of the bridge program was to eliminate drawbridges. A statewide consultant, Sverdrup Corporation, studied numerous bridges of all types for inclusion in the program and ultimately recommended that DOT widen or replace some, but not all, of them. DOT submitted the Anna Maria Island Bridge to Sverdrup for possible inclusion in the bridge-replacement study program. But before doing so, DOT obtained the approval of the local Metropolitan Planning Organization (MPO) for replacing the bridge. On the recommendation of Sverdrup to include the Anna Maria Island Bridge in the bridge-replacement study program, DOT included the replacement bridge in its five-year work program in 1988 and each subsequent year. DOT conducts annual public hearings on the work program. At the public hearing, DOT's representatives discuss each project, and members of the public may comment on projects. On March 29, 1988, Sverdrup issued a Project Concept Report, which is intended to identify the ideal transportation solution. The Project Concept Report starts the PD&E process, which eventually determines if it is feasible to implement the ideal solution identified in the Project Concept Report. The Project Concept Report proposes the replacement of the Anna Maria Island Bridge with a fixed-span, high-level bridge. The report refers to the proposed project as a "major bridge replacement project." The report anticipates a categoric exclusion for the project despite the classification of Sarasota Pass as Outstanding Florida Waters and the presence of considerable seagrass and manatee around the Anna Maria Island Bridge. In April 1988, DOT circulated an Advance Notification Package to interested agencies informing them that DOT was starting a study of the construction of a two-lane bridge. The Manatee County Board of County Commissioners responded to the April 1988 Advance Notification Package. By letter dated June 14, 1988, to DOT's then-Secretary Kaye Henderson, the County Commissioners expressed "strong support" for the replacement of the Anna Maria Island Bridge with a fixed- span, high-level bridge. The letter cautions that two lanes are inadequate for existing and projected traffic. In a letter to Sverdrup dated October 3, 1988, the Chairman of the Board of County Commissioners emphasized the Board's position: "it is the unanimous feeling here that planning to build anything less than a four-lane replacement would be disastrous, or simply planned obsolescence." In August 1988, DOT hired Figg and Muller Engineers, Inc. (references to Figg and Muller include Figg Engineers, Inc., which prepared certain reports) to perform the PD&E study. The role of Figg and Muller in conducting the PD&E study was to identify the means of accomplishing a predetermined goal--in this study, the best way to replace the Anna Maria Island Bridge. DOT asked Figg and Muller specifically to evaluate a fixed-span, high-level bridge, but, in discharging its duties, Figg and Muller considered all viable alternatives, including the no- build option, and considered all environmental impacts of these alternatives. After DOT issued the Advance Notification Package in April 1988, the MPO asked DOT to evaluate the possibility of expanding the facility to four lanes. Despite a strong preference to limit the new facility to two lanes, DOT evaluated the four-lane option to comply with local transportation plans. DOT thus directed Figg and Muller, which had already begun its work, to consider four-lane alternatives as well. Anticipating its formal retention in August 1988 to conduct the PD&E study, Figg and Muller had earlier retained an environmental subconsultant. On May 31, 1988, Figg and Muller sent a letter with a proposed contract and related materials to Peninsula Design and Engineering, Inc. (references to this company and Mangrove Systems, Inc. shall be to "Peninsula"; the same person, first employed by Peninsula and later Mangrove Systems, performed the environmental work). Figg and Muller described the proposed project as the "replacement of a two-lane bascule bridge . . . with a fixed- span, high-level bridge." Enclosed materials describe the new bridge as 54 feet wide with a 40-foot roadway, five-feet sidewalks on each side, and a 65-foot vertical clearance. The new bridge, which would be next to the existing bridge, is described, as it was then conceived, as a federal-aid project. The attachment warns that aesthetics, grassbeds, and manatees, among other things, would be important considerations during the study and design. The subconsulting contract requires Peninsula to quantify wetland encroachments and endangered species. The contract warns that the environmental sensitivity of the area requires the identification of an "intensive baseline environmental assessment" to identify the best environmental alternatives regarding alignment and construction techniques. The contract warns further that "accurate description of floral and fauna communities in submergent habitats requires a greater level of effort than is typically necessary in [terrestrial] habitat evaluations." Because environmental permits could be "challenging to obtain" without intensive evaluation of submergent communities, the contract requires Peninsula to develop transects of flora communities in the impacted area and identify endangered species and their habitats. The contract requires Peninsula to develop additional biological information necessary for environmental assessment, including sampling the bottom sediments for, among other things, heavy metal concentrations. The contract also requires Peninsula to prepare a Permit Coordination Package to develop proposed mitigation plans and evaluate project impacts, including the elimination of habitat, changes in sedimentation, and destruction of vegetation. Peninsula conducted a macrophyte investigation on September 27, 1988. The Peninsula employee established eight stations--four just offshore from the filled-in bridge approaches and four closer to the channel, north and south of the existing bridge. The Peninsula employee set 100-meter transects with ten data- collection sites along each transect. The transects for the stations near the approaches ran perpendicular to the bridge. The Peninsula employee followed a "similar" approach with the stations near the channel, although ambiguous language in the report leaves it unclear if the transects for the four "offshore" stations ran perpendicular or, as stated at one point, "parallel" to the bridge. In either case, the transects run on September 27, 1988 do not travel under the existing or proposed bridge. The fieldwork thus yielded information about seagrass in the general area of the project, but no data that could be directly used to study and analyze the effects of shading from the existing or proposed bridge. The Peninsula report notes a continuing chronic loss of seagrass south of the existing [bridge] in the vicinity of [two] stations. . . . The causal factors contributing to these losses include continuing historic degradation of water quality in the area and more importantly, the hydraulic conditions created by the configuration and construction of the [bridge] approach fills and the submerged borrow areas. The report also records "unusual foraging signatures" at one station, possibly indicative of manatee foraging. Figg and Muller, Peninsula, and other consultants prepared the Site Characteristics Inventory Report dated November 8, 1988, and updated December 20, 1988. The inventory report summarizes the data "necessary for adequate evaluation of the location, design and impacts of the project." The Site Characteristics Inventory Report describes various features of the Anna Maria Island Bridge. Stating that the bridge's overall vehicular accident rate is low, the inventory report notes the high percentage of rear-end collisions and concludes: "The high percentage of rear end collisions suggests a high amount of vehicle cueing [sic]. This could be attributed to vehicles stopped for a left turn, stopped for the SR 789 signalized intersection or stopped for a bridge opening." Peninsula prepared the Permit Coordination Package by May, 1989. The package misidentifies the waters around the Anna Maria Island Bridge as Class III waters, though it reports more importantly that these waters are Outstanding Florida Waters. However, the Permit Coordination Package grossly understates the area of subtidal and intertidal seagrass within 1000 feet of the Anna Maria Island Bridge. The Permit Coordination Package considers seagrass mitigation only in passing, assuming without any analysis of water depths, water transparency, turbidity, or sediment composition, that seagrass would recolonize under the removed part of the existing bridge. The mitigation discussion is directed mostly to mangroves. The Permit Coordination Package contains an extensive discussion of manatee as an endangered species. Peninsula reported 163 manatee sitings north of the Anna Maria Island Bridge from 1985 through 1988 and 63 sitings south of the bridge during the same time. The Permit Coordination Package contains a reasonably detailed set of suggestions for minimizing construction-related impacts to manatee. Peninsula considered the impact of the proposed bridge on the seagrass beds upon which manatee feed. Peninsula reported that the impact on seagrass of the south alignment would be an order of magnitude greater than the impact on seagrass of the north alignment. The Permit Coordination Package reviews research suggesting that manatee mortality from boat collisions is higher when the mammals are feeding in seagrass beds, are in areas frequented by small recreational boats that operate at relatively high speeds and move in unpredictable ways in shallow water, and are in shallow, restricted navigation channels. The Permit Coordination Package notes that bicycles, joggers, and pedestrians use the Anna Maria Island Bridge, but not extensively. However, the Permit Coordination Package acknowledges that the bridge is "heavily used by fishermen, principally recreational or low volume commercial mullet netters using large castnets." These fishermen use the 400 feet at either end of the bridge and up to 200-300 feet of the margins of the pass. Figg and Muller conducted a study of ship impacts, culminating in the Ship Impact Analysis Data Collection dated November 7, 1988. The document describes the proposed project as the replacement of the Anna Maria Island Bridge with a fixed- span bridge with a 65-foot clearance. The ship-impact study notes that, from January 1985 through September 1988, 650 vessels monthly required bridge openings to navigate the Intracoastal Waterway, which runs under the Anna Maria Island Bridge. Over nearly four years, these vessels comprised 24,889 sailboats (83.5 percent), 4447 powerboats (14.9 percent), 467 tugs/barges (1.67 percent). The tugboats were typically 35 feet by 195 feet. A variety of the sailboats had masts requiring a vertical clearance greater than 65 feet. Sailboats with masts as high as 80 feet-- including a number of boats manufactured in Florida--have passed through the opened drawbridge. The growing importance of a clearance greater than 65 feet is evidenced by the closing of other nearby passes into the Gulf and the increasing use of taller-masted boats. The ship-impact document includes a survey of bridge tenders and commercial boating interests. One tender, who had worked at the Anna Maria Island Bridge for 12 years, reported that he had never seen or known of an marine vessel colliding with the bridge. No one else reported any such collisions. In general, persons surveyed agreed that winds and currents present no navigational difficulties at the fendered channel of the Anna Maria Island Bridge. Figg and Muller prepared the Draft Preliminary Engineering Report dated December 20, 1988, and revised February 13, 1989, "to examine the most feasible and prudent locations and conceptual designs for the construction of the proposed bridge replacement structure . . . at Sarasota Pass ...." The study's objective was to "develop a bridge replacement that will provide an efficient, economical and safe transportation facility with minimal adverse impacts on both the human and natural element." The introduction to the Draft Preliminary Engineering Report notes that DOT has classified the Anna Maria Island Bridge as functionally obsolete. The draft report states that the proposed bridge replacement project is necessary to correct the primary deficiencies of a "lack of emergency shoulders, obsolete design load of H-15 and low overall clearance." The introduction to the draft report states that the current project would be either a two- or four-lane facility. The actual size and need would be consistent with the Manatee County comprehensive plan and MPO transportation plan. The next section of the Draft Preliminary Engineering Report describes existing conditions. This section accurately details most aspects of the existing condition of the Anna Maria Island Bridge. The draft report identifies the bridge's H-15 design load, posted speed limit of 50 miles per hour, and absence of posted weight restrictions. The draft report reveals that the bridge has 36 scheduled daily openings most of the year. Based on a 1988 DOT inspection, the draft report states that the bascule is in "good" condition, meaning that there was "moderate incidence of significant early deterioration." Based on a 1987 DOT inspection, the draft report states that the deck, superstructure, and substructure are in "fair" condition, meaning that there was "early to moderate deterioration that does not reduce element capacity," and the channel protection was in "excellent" condition. The draft report collects detailed accident data for the Anna Maria Island Bridge. The draft report states that the 1988 average daily traffic "on the facility in the vicinity of the Anna Maria Island Bridge" was 14,300 vehicles with an average daily traffic of 17,000 vehicles projected for 2010. Based on accident data for 1984 through 1986, the draft report concedes that the accident rate for the bridge is low. For the two approaches, bascule, and remainder of the existing bridge, there were a total of 62 collisions during the three-year period, with the most prevalent being 27 rear- end collisions. None of these 27 rear-end collisions occurred on the bascule. Most of the rear-end collisions--17--occurred on the two approaches. The remaining ten rear-end collisions occurred on the bridge between the bascule and the approaches. The approaches were also the sites of more total collisions than the bridge itself, including the bascule. For the three-year period, 61 percent of the collisions occurred on the two approaches, 5 percent occurred on the bascule, and 34 percent occurred on the remainder of the bridge. There was only one collision involving a vehicle and a pedestrian during the three years in question. This took place on the eastern approach. There were no collisions involving bicyclists. The draft report states that a high percentage of the rear-end collisions occurred near a boat ramp on the west approach and a marina and convenience store on the east approach. The marina and convenience store are about one-quarter mile east of the Anna Maria Island Bridge. The boat ramp is between the west end of the bridge and the signal at Gulf Drive. The draft report suggests that rear-end collisions on the approaches may involve vehicles slowing for right turns into these destinations. The draft report opines that the "high percentage of rear-end collisions on the bridge (39 percent)" may involve vehicles stopping quickly for a bridge opening. This suggestion ignores the queuing effect from vehicles turning into the boat ramp or convenience store and marina. The draft report tries to limit the effect of these traffic backups to rear-end collisions on the bridge approaches. However, attributing a high percentage of rear-end collisions on the bridge to bridge openings ignores the traffic backups from these off-bridge sources, as well as the traffic light at Gulf Drive. Figg and Muller's analysis of the sources of rear-end collisions lacks support, such as through analysis of accident reports. The analysis even cites the wrong figure. The 39 percent figure applies to total collisions on the bridge compared to total collisions; the percentage of total rear-end collisions occurring on the bridge is 37 percent (10/27). The draft report also falters when describing cultural and environmental features. Noting low pedestrian volumes on the Anna Maria Island Bridge, the draft report contends three times in one paragraph that "pedestrian activity is not a major consideration for this project," "pedestrian activity does not warrant special consideration on the project," and "sidewalks ... are used very little by pedestrians." As for environmental factors, the draft report incorrectly identifies the Class II waters surrounding the Anna Maria Island Bridge as Class III waters, although the draft report correctly notes that these waters are Outstanding Florida Waters. But the omissions in the draft report are more significant. The draft report omits any mention of manatee or the seagrass located under what would be the new bridge. The draft report does not discuss the effects of shading, water transparency, and water depth on seagrass. The section following the description of existing conditions is entitled "Need for Improvement." As the name of the section suggests, this part of the Draft Preliminary Engineering Report contains less data and more analysis of the existing and proposed bridges. The discussion is at times more promotional than it is analytic. This section of the draft report starts by noting that the existing bridge has had no significant upgrades to its two, 12-foot shoulder-less traffic lanes. The draft report finds that the lack of shoulders presents a traffic hazard when traffic is stalled on the bridge. The opening of the drawbridge is another source of danger to motorists due to stopped traffic, according to the draft report. The draft report argues that this hazard is "substantiated" by the previously discussed data on rear-end collisions. The draft report summarizes the above-described accident data "for the existing facility" without disclosing that more than half of the accidents occurred on the bridge approaches and not the bridge itself. The draft report adds that opening the drawbridge would also present a danger during evacuations by preventing people from evacuating the island. However, there is no discussion of Coast Guard policy, which is not to order bridge openings during an evacuation, nor is there any mention of the frequency of evacuations, which take place about once every six years. There is also no discussion of the widely known necessity of early evacuations from the island due to early flooding of island roads and bridge approaches. On incomplete data, the draft report merely contends that "evacuation efforts would be severely hampered" by the need to open the drawbridge. The draft report suggests that bicycle traffic would be better accommodated by a new bridge. The draft report observes that the two existing five-foot sidewalks on the Anna Maria Island Bridge create an unsafe condition by mixing bicycle traffic with pedestrians and fishermen. The draft report neglects to discuss the discouraging effects on bicyclists, pedestrians, and fishermen of using a single six-foot sidewalk running up a 4 percent grade to a final height of 75 feet over the water. The draft report states that the MPO's 2000 Plan identified a need for a four-lane facility over Sarasota Pass. However, the 2010 Plan, which was prepared after the draft report, identifies no such need. The draft report notes that the proposed project is also in compliance with the Manatee County comprehensive plan. Addressing social and economic issues, the draft report accurately describes the area surrounding the proposed project as a "naturally beautiful site" with the proposed project promising to be "highly visible from both land and water." The draft report assures that engineers would design a bridge profile "to ensure a pleasing visual effect." The draft report acknowledges that the proposed project is not directly needed to meet any economic demands. But the "social demands for the project would be based on a more efficient and convenient transportation system linking Anna Maria Island with the mainland." The draft report suggests that the improved link "could foster economic development in the area" and everyone would be served by a more dependable evacuation route. However, there is no evidence that the existing drawbridge has ever impeded vehicular or vessel traffic during an evacuation or that the proposed bridge would result in more traffic on Anna Maria Island by way of Manatee Avenue or other routes. The next section of the Draft Preliminary Engineering Report is the analysis of alternative alignments. This section first considers the no-build alternative. The cited advantages of not building the project are that there would be no disturbance to the environment, even though these impacts, according to the draft report, "are nearly all of short term duration and can be considered as minor over the life of the new structure." On the other hand, the benefits of building the bridge include the elimination of the inconvenience of the drawbridge to motorists and boaters and the cost of operation of the typical bascule bridge. The draft report states that maintenance costs for a typical bascule bridge are about $150,000 annually plus estimated major rehabilitation costs of $500,000 to $750,000 every 15-20 years. Additional reported benefits to replacing the Anna Maria Island Bridge are eliminating the safety hazards posed by the lack of shoulders and raising by 25 percent the design load from H-15 to H-20. The draft report concludes that the benefits of the no-build alternative are outweighed by the "substandard design and safety concerns." The draft report considers a two-lane bridge, a four- lane bridge, and two two-lane bridges. Additionally, the draft report considers alignments north and south of the Anna Maria Island Bridge with three structure levels: high-level fixed, mid-level bascule (i.e., a 45-foot closed vertical clearance drawbridge), and low-level bascule. These options account for 18 alternatives. Figg and Muller studied each of the 18 alternatives for traffic flow, ease of construction, bicycle accessibility, operation, safety, aesthetics, environmental impacts, right-of- way impacts, and project costs. As to the north alignment, the draft report notes several problems, including the need to relocate a power line and water line and modify two navigation channels. The draft report states that the boat ramp just west of the bridge and the marina on the east would be impacted if DOT constructed a single four- lane bridge, which would also impact right-of-way. As to the south alignment, the draft report notes several problems, including the need to relocate a water line. Any structure would also impact right-of-way. As to the low- and mid-level bascules, the draft report contends without significant supporting data that few boats could pass through an unopened mid-level bascule that could not also pass through an unopened low- level bascule. The draft report cannot justify any bascule options due to the "additional expenses of the bascule construction, bascule maintenance and bascule operations." The draft report cautions that the bascule alternatives are not "a practical, improved replacement to the existing bascule bridge." The final section of the Draft Preliminary Engineering Report is entitled "Preliminary Design Analysis." The draft report offers rough summaries of projected construction costs for various alternatives. The projections are of greater value for the comparison of differences in probable costs of various alternatives than they are for identifying the estimated cost of a particular alternative. According to the draft report, a two-lane, fixed- span, high-level bridge on the north alignment would cost $9.9 million, and a two-lane, mid-level bascule on the north alignment would cost $12.5 million. On the south alignment, these bridges would cost $10 and $12.6 million, respectively. Discussing the benefits of replacing the Anna Maria Island Bridge, the draft report states that the "most obvious" benefit would be the elimination of the delays to vehicular and vessel traffic from drawbridge openings. A fixed-span bridge also would offer a dependable evacuation route. The draft report suggests that shallow-draft boaters would find navigation enhanced by the tripling of the widths between the supports under the fixed-span, high-level bridge as compared to the more narrowly spaced supports under the existing bridge. The draft report again asserts that the new structure would also offer improved aesthetics, both in terms of the view of the proposed bridge and the view from the proposed bridge. Page VIII-13 of the draft report is missing from SAM Exhibit No. 32. In the final report, and possibly in the draft report, Figg and Muller admitted on this page that the proposed grade of the new bridge would "limit fishing activities and pedestrian use." A brief discussion of rear-end collisions and economic and community development was probably present on the omitted page, but this section generally summarizes discussions from earlier sections. The draft report also considers wetland impacts of new two-lane bridges on the north and south alignments. Relying on the understatements of Peninsula, the draft report states that the area of subtidal seagrass is only 0.63 acres 500 feet north of the existing bridge and 0 acres 500 feet south of the existing bridge. The draft report concludes that a two-lane bridge 25 feet north or 25 feet south of the Anna Maria Island Bridge would not impact any subtidal seagrass and would impact only 0.06 acres of intertidal seagrass on the north alignment and 1.65 acres of intertidal seagrass on the south alignment. The draft report also considers the impacts of new four-lane bridges on the north and south alignment. All of this analysis understates seagrass loss by considerable amounts. Based on these data and analysis, the Draft Preliminary Engineering Report concludes that [a]lignment se[le]ctions based solely on a vegetative impact evaluation would focus on the northern alternative. However, alignment selection will necessarily need to be tempered with a consideration of endangered species involvement and impacts to navigation, partic- ularly when addressing the northern alignment. Sverdrup reviewed Figg and Muller's Draft Preliminary Engineering Report prior to its revision in February 1989. Addressing the discussion of bascule alternates, one Sverdrup engineer stated in a Review Comment Sheet dated January 6, 1989: Information presented thus far does not support premature rejection of bascule options. Vessel height distribution may require some detective work. Consider visits to local marinas, corre- lation with vessel numbers/names on bridge tender logs, additional data recorded by bridge tenders for a few weeks. . . . Objective is to establish relations between traffic benefit vs. reduced openings for different vessel clearances. Ultimate rejection or viability of bascule alternate must have adequate foundation. . . . Sverdrup's environmental representative, Don Smith, reviewed the work of Peninsula. Despite Peninsula's excessively conservative estimates of seagrass loss, Mr. Smith rejected even these estimates as too pessimistic. By review comment sheet to Figg and Muller dated December 28, 1988, Mr. Smith wrote: "As presently written, this section grossly overestimates the extent of possible wetland impact & must be redone." Adamantly rejecting Mr. Smith's criticism, the Peninsula employee wrote on his copy of the review comment sheet: Table 7 does not grossly over estimate wetland impacts. . . . The acreage figures are not grossly overestimated at all. I resent the grossly! Does Sverdrup have any DATA! that reflects my gross overestimates! NO, SHIT A memorandum dated January 23, 1989, memorializes the conclusions of a meeting involving Sverdrup and Figg and Muller representatives. Figg and Muller argued that its subconsultant did not overestimate wetlands and asked Sverdrup to substantiate Mr. Smith's contrary assertion. Sverdrup appears to have relented, and the two consultants agreed to remove a drawing. On January 11 and 12, 1989, the value engineering (VE) team met to define the goals of the first phase of review. The VE team is a multidisciplinary group of engineers unrelated to the project who determine the suitability of the proposal and the feasibility of any more cost-effective proposals. VE responds to the design alternatives presented in the draft report. The VE team listened to a Figg and Muller representative discuss alignment issues, including the presence of seagrass beds immediately south of the Anna Maria Island Bridge. The VE team understood that concerns about the north alignment included navigation and "occasional manatee sitings," and concerns about the south alignment included greater seagrass impact. The VE team visited the Anna Maria Island Bridge, which they found to be in "good condition." They found "no severe deterioration which would endanger the capacity of the bridge." Preliminary VE considers the maintenance and operation costs of bascule alternates, although the memorandum omits mention of the costs of the no-build alternate. Preliminary VE does not identify the no-build alternative as a viable option requiring further consideration. On February 27, 1989, DOT conducted its first public meeting on the proposed project. DOT conducted a public information workshop at the Manatee County public library in Bradenton. DOT regarded the February 1989 workshop as an opportunity for the public and DOT, as equal partners, to gather and make basic plans about whether to replace the Anna Maria Island Bridge and, if so, with what. In March 1989, the MPO adopted an updated long-range transportation plan, which still showed State Road 64 as a four- lane road, including the segment over Sarasota Pass. A memorandum dated March 31, 1989, from a Sverdrup representative to a Figg and Muller representative transmitted new traffic data with the direction: "This data must be analyzed and documented in a revised Traffic Report in order to reach the conclusions necessary to proceed with the project development." The Sverdrup representative relieved Figg and Muller from the obligation of doing certain traffic calculations for bascule alternatives "since it is evident that the fixed high-level structure will be recommended due to lower overall cost." A review comment sheet dated June 13, 1989, from Mr. Smith to Figg and Muller suggested that they revise the draft report to state that the "no- build alternate is eliminated from further consideration; i.e, definitively close the door." On July 7, 1989, Mr. Crim, two Figg and Muller representatives, and two Sverdrup representatives, including Mr. Smith, discussed the north and south alignments to try to agree on the preferred alternative. Someone mentioned that they needed to take a closer look at the environmental impacts because a DEP representative had implied to Sverdrup that the "documentation must show very good reasons for selecting anything but the most environmentally sound alternative." A Figg and Muller representative added that manatee frequently use an area north of the bridge, but the participants felt this was not a significant issue for alternative selection "since manatees can be found throughout the area, north and south." The agenda for the July 7 meeting contains numerous items. Under seagrass, it identifies a need to confirm the area impacted, adding parenthetically "3.65 acres vegetated and 0.63 acres non-vegetated?" On July 7, 1989, Mr. Crim and a Sverdrup representative met with three representatives of the Federal Highway Administration to obtain their comments on the Draft Preliminary Engineering Report. The Sverdrup representative explained that the existing bridge was functionally obsolete due to the lack of shoulders and substandard design load. She explained that the proposed project would be a new four-lane bridge and did not identify a no-build alternative. She disclosed that seagrass impacts were 3.65 acres for the south alignment and 1.55 acres for the north alignment and said that the Federal Highway Administration would receive an application for a categoric exclusion in mid-September, 1989. On July 20, 1989, two Sverdrup representatives, including Mr. Smith, participated in a teleconference with five DOT representatives, including Mr. Crim. They discussed the north and south alignments to try to agree on a preferred alternative to present at the August 10 public hearing. The participants discussed the navigational problems with the north alignment and seagrass problems with the south alignment. Sverdrup tended to agree with Figg and Muller's recommendation of the south alignment. The participants agreed that it should be possible to negotiate an acceptable mitigation plan with DEP, even though one of the DOT representatives warned that DOT District 1, in which the proposed project is located, "has not had much success with seagrass mitigation in the past and that it can be very expensive and still not work." This DOT representative suggested that they present both alignments at the public hearing and defer the recommendation until after receiving public comments. The participants decided to do this. On August 10, 1989, DOT conducted the first public hearing on the project. The public hearing took place at the Anna Maria Island City Hall. DOT uses public hearings to present to the public a preferred alternate and give the public a chance to present information to show that DOT or its consultants have made any mistakes or omitted any considerations or that circumstances have changed materially. Transcribed by a court reporter, a public hearing is tightly structured. The hearing begins with opening remarks of representatives of DOT and its consultants describing the proposed project. These opening remarks are followed by a break during which members of the public may approach representatives of DOT or the consultants, ask questions, and presumably receive answers. However, these questions and answers are not recorded by the court reporter. Following the break, back on the record, members of the public may make oral comments to the DOT and consultant representatives, who almost invariably decline to respond to general questions or engage in any give-and- take with a speaker. Likewise, the DOT and consultant representatives almost invariably insist that speakers limit their comments to the individual project and not discuss other projects, even if relevant (e.g., the Cortez Bridge and a new bridge farther south). After the hearing is concluded, the public may submit written comments for a short period. After this period ends, DOT and the consultants meet privately, consider the record, make a decision on the project, and announce the decision publicly. About 50 persons attended the August 10 public hearing, which was held at Anna Maria City Hall. DOT, Sverdrup, and Figg and Muller provided comment sheets, displays, and reports for public inspection at the public hearing. Representatives of the consultants and DOT encouraged the audience to examine the materials, ask questions of knowledgeable individuals during the off-the-record break, and then make public comments. According to Mr. Crim, DOT intended the August 1989 public hearing to serve as a combined location and design public hearing. However, DOT had failed to give notice to owners of condominiums within 300 feet of the centerline of the west terminus of the proposed project. DOT instead had notified only the condominium association. In his opening remarks to the persons attending the public hearing, Mr. Crim stated that the Anna Maria Island Bridge was one of about 60 bridges in the statewide program "being studied for future replacement." He explained that DOT was "evaluating viable options for either improving or replacing these bridges, obtaining public input and then completing the environmental documentation and design for any recommended improvements." Mr. Crim told the audience: Our study to replace the Anna Maria Island Bridge is nearing the completion of the project development phase. Tonight's hearing is an important step in that phase where we present preferred project alternates for your input prior to selecting a final alternate and then proceeding with preliminary design. Mr. Smith told the audience that DOT had three options: build a new bridge on the north alignment, build a new bridge on the south alignment, or not build a bridge. He stressed that displays in the hearing room did not represent "final plans" and that "absolutely no decisions have been made to this point." Later during the public-comment portion of the public hearing, Mr. Smith stated that there would be no more public hearings, unless so much time passed without construction that the project had to undergo additional review. A Figg and Muller representative told the audience that the 36 drawbridge openings daily "is a cause of a significant number of rear end collision accidents." She identified as the preferred alternative two fixed- span, high- level, two-lane bridges with a single such bridge initially. The Figg and Muller representative noted the seagrass impacts of both alignments. She stated that manatee are in the area, but that DOT expected no impacts due to the use of protective measures. After an hour and a half, the representatives of DOT and the consultants finished their initial presentations. During the break, members of the audience spoke with the representatives of DOT and the consultants. Public comments were divided as to the proposed fixed-span, high- level bridge. Speakers informed DOT of impending recreational and commercial development on the north side of the bridge, as well as navigational concerns, that would be adversely affected by the north alignment. Explaining DOT's practice of typically presenting a preferred alternate, Mr. Crim testified that DOT "can't go to a public hearing and say we don't know what we're going to do. Anybody got any comments?" Instead, DOT presents its recommendation to sharpen the focus of the public hearing. The February 1989 workshop was to help form the decision; the August 1989 public hearing was to show whether DOT should change a tentative decision. On November 1, 1989, Figg and Muller issued the Final Preliminary Engineering Report. The text of the final report is not materially different from the text of the draft report issued nine months earlier except as noted below. Mr. Crim testified that, at this point, DOT had decided to replace the bridge, but had not decided to build a fixed-span, high-level bridge. The final report recites the same "primary deficiencies" of the Anna Maria Island Bridge cited in the draft report, but adds a new deficiency--delays due to bascule openings. Acknowledging the existence of the marina and convenience store one-quarter mile east of the bridge, the final report suggests that collisions on the bridge approaches could be due to vehicles stopping for left turns, as well as right turns. Discussing traffic projections, the final report mentions that, when the draft report was first drafted in December 1988, traffic projections disclosed a need for a two- lane facility with possible expansion to four lanes at some future point. New traffic information demonstrated that the four-lane facility would be needed prior to 2015. The final report increases, without discussion, the 1988 average daily traffic "on the facility in the vicinity of the Anna Maria Island Bridge" to 15,400, from 14,300 vehicles reported in the draft report for the same period. The final report adds that the two-lane bridge would reach a level of service E in 2006, so "it is recommended that a four lane facility be constructed prior to this date." The final report contains a new section on endangered and threatened species. This section contains data showing that the area around the Anna Maria Island Bridge is frequented by manatee. The final report relays the information from the Permit Coordination Package that, from 1985 through 1988, there were 163 manatee sitings north of the bridge and 63 manatee sitings south of the bridge. Early in the section analyzing alternative alignments, the final report notes, as does the draft report, that the benefits of the no-build alternative are outweighed by the disadvantages of "substandard design and safety concerns." Recognizing that only the no-build alternative would avoid impacts to the wetlands, the Final Preliminary Engineering Report states: "this alternative is not feasible considering the structural deficiency of the bridge, the absence of shoulders (functional obsolescence) and projected traffic increases indicating the need for two additional lanes." The final report concludes: "Therefore, the No-Build Alternative is not a viable alternative and is hereby eliminated from further consideration in this report." The final report revises the comparative cost estimates, reducing the north and south alignment costs for a two-lane bridge by a little over $1 million. The final report continues to understate the area of subtidal seagrass north and south of the bridge. The final report describes the public involvement on the proposed project. Referring to the public workshop that took place on February 27, 1989. the final report states that, of the 36 individuals who supplied written comments on the proposed bridge, 21 favored a two-lane bridge, six favored a four-lane bridge, 30 favored a high-level, fixed-span bridge, 21 favored the south alignment, and two favored the north alignment. Summarizing the results of the public hearing held on August 10, 1989, the final report recounts that, among oral comments, five favored two lanes, three favored four lanes, five favored the south alignment, no one favored the north alignment, and seven favored the no-build alternative. Written comments were two favoring four lanes, one favoring two lanes, four favoring the south alignment, no one favoring the north alignment, and one favoring the no-build alternative. A new section of the final report is entitled, "Preferred Alternative." Recommending that four lanes be built, the final report recommends the south alignment, mostly on the basis of impediments to navigation posed by the north alignment. There is little discussion of seagrass impact. Relying on the needs of boat traffic, although ignoring the needs of high- masted boats, the final report recommends a fixed-span, high- level bridge and proceeds to analyze the projected costs in greater detail than did the draft report. The remaining material differences between the draft and final reports are that the final report drops the repeated references to the unimportance of pedestrian activity on the Anna Maria Island Bridge, the description of the area surrounding the proposed bridge as "a naturally beautiful site," the assurance that the proposed bridge would be "highly visible from both land and water," and the exhortation that DOT consider the "aesthetics or visual impacts of the project." The final report continues to misidentify the waters around the Anna Maria Island Bridge as Class III waters. On November 27, 1989, DOT circulated a revised Advance Notification Package, noting that the new proposal was for two two-lane, high-level bridges to be constructed in two phases. The notice states that the project is a federal-aid project and that DOT and the Federal Highway Administration would determine the degree of environmental documentation necessary. 2. 1990-92 Various state agencies responded in early 1990 to the revised Advance Notification Package. Several agencies expressed reservations about the proposed project, although ultimately all state agencies dropped their objections at this stage. By letter dated January 4, 1990, DER objected to the loss of seagrass from construction and shading. DER also warned that seagrass mitigation had met with little success in this general area. DER suggested that DOT consider rebuilding the bridge at its current location at or near its current width. The letter suggests that DOT take several steps. In particular, the letter states that the proposed project is in Outstanding Florida Waters, and DOT must, among other things, show that "existing ambient water quality will not be lowered." Representatives of DOT, Sverdrup, Figg and Muller, Peninsula, and DER met on March 23, 1990, to discuss DER concerns about impacts to seagrass and the ability to mitigate. The Peninsula employee estimated seagrass losses of 0.1 acre from pier placement, 0.5 acres (worst case) from construction, and an overshadow effect. Due to the greater height of the new bridge, someone at the meeting said that the overshadow effect would be minimized. As to mitigation, someone reported DER's concern that seagrass typically was already growing where conditions were favorable and, where seagrass was absent, conditions were unfavorable. The Peninsula employee suggested that they could fill holes in the area, raising the bottom elevation to a depth at which seagrass could grow. Someone reported DER's insistence to consider mitigation now, to avoid problems in the permitting stage. In response, DOT "proposed to commit to studying the overshadow effects of the new bridge and the rate of re- colonization of seagrasses in the alignment of the old bridge." DOT agreed to develop alternative mitigation prior to construction of the second two-lane bridge, if recolonization failed. DER agreed to this approach. The agreement between DOT and DER was memorialized by letter dated March 30, 1990, from a DOT representative to a DER representative. The letter promises that, after completion of the construction of the first two-lane bridge, DOT would start monitoring recolonization where the Anna Maria Island Bridge had stood and the effect of shading from the new bridge. If at the end of a monitoring period of unspecified duration an unspecified entity determined that recolonization had been unsuccessful, DOT would implement mitigation at an unspecified location. The letter concludes that DOT's commitment to this procedure will "alleviate DER's concerns regarding the impacts to seagrass and allow for a determination of consistency with the Florida Coastal Management Program." By letter from DER to the Office of the Governor dated April 13, 1990, DER stated that DOT had provided reasonable assurance of seagrass mitigation in part by assuring that seagrass would recolonize under the existing bridge once it was removed. DER noted that DOT promised to monitor recolonization and shading following removal of the existing bridge and construction of the first two-lane bridge. DER recommended a bathymetric survey and stated that a permit would contain success criteria for natural recolonization and require alternate mitigation plans. Withdrawing its earlier objection, the DER letter finds that the project is "consistent with our authorities in the Florida Coastal Management Program at this time." The letter concludes with the promise of a more detailed review during permitting. In the meantime, consultants continued to work on the project. Figg and Muller prepared a draft of the Final Engineering Report and submitted it to Sverdrup for review. In a Review Comment Sheet dated February 15, 1990, directed to Figg and Muller, Mr. Smith again protested high estimates of seagrass losses, stating: "Shading is a non-issue which is not even addressed in any agency regulations. Revise the document accordingly." Other work early in 1990 included final VE review of the project. The second VE memorandum was completed March 26, 1990. Memorializing a meeting that took place February 28, 1990, final VE describes the proposed project as a 65-foot clearance bridge 20 feet north of the Anna Maria Island Bridge. The memorandum concludes that VE could offer no significant improvements to the proposed project. The memorandum does not consider the no- build alternative. However, the memorandum recommends that DOT consider relaxing the ship-impact standard at the ends of the bridge based on the shallow depths at the ends of the bridge, the absence of reported marine collisions with the bridge, and the existence of alternative access to Anna Maria Island. While Figg and Muller spent most of 1990 and early 1991 preparing the Final Engineering Report, consultants or subconsultants prepared additional reports, such as the geotechnical report and bridge hydraulic report. In December 1990, DOT made some changes to the new design, widening the shoulders and adding a sidewalk. Figg and Muller issued the Final Engineering Report about a year after the date of January 31, 1990, shown on its title page. The first paragraph of the Final Engineering Report makes the case for the replacement of the existing bridge, but without any mention of structural deficiency. The report states that the Anna Maria Island Bridge is narrow, without shoulders, and functionally obsolete. . . . In addition to safety concerns associated with a lack of shoulders, accident data show a high number of rear end collisions. One factor contributing to these collisions is the delays to the traffic caused by the opening of the bridge's drawspan. These factors, combined with a need for efficient and safe transportation routes to and from the islands, determined the need to replace the existing bridge at this time. The Final Engineering Report states that DOT and its consultants evaluated 18 alternatives, plus the no-build alternative, and describes the Final Preliminary Engineering Report. The Final Engineering Report notes that the Federal Highway Administration issued a categoric exclusion July 23, 1990. The categoric exclusion was based on, among other things, a DOT representation that the project had no "controversy potential," which may have seemed plausible at the time. DOT District 1 Secretary David May contended that such a representation, which preceded his appointment as District Secretary, would be correct if the controversy were based on unfounded information. In any event, the Federal Highway Administration did not withdraw the categoric exclusion in 1995, even after DOT disclosed the controversy surrounding the proposed project. The Final Engineering Report explains that the original traffic data were faulty. Correct data revealed that the "original concept of a two-lane replacement bridge was unworkable." Thus, DOT and the consultants decided to pursue a two-phase project with the first phase being the demolition of the existing bridge and construction of a single two-lane bridge. The Final Engineering Report states that the decision to build ultimately four lanes warranted reissuance of the Advance Notification Package. The Final Engineering Report states that, in a meeting between representatives of DER and DOT, DOT representatives suggested that the advance notification stage was premature for the development of mitigation commitments, but acceded to DER's insistence due to the availability of a "great deal" of information. The two agencies reportedly reached an understanding of what would be required to offset environmental impacts. The Final Engineering Report states: "Based on that agreement, DOT proceeded with completing the environmental study process and the final design at a cost of approximately $1,000,000 of public funds." The Final Engineering Report discloses that the consultants eliminated the existing alignment in the PD&E study and selected the south alignment due to fewer adverse impacts. The report notes direct and indirect impacts to 3.01 acres of vegetated wetlands, including 1.65 acres of seagrass. The report calculates the seagrass impacts as 0.25 acres from pier placement and 1.4 acres from shading. DOT and the consultants selected the south alignment based on "strong public support" and DER's suggestion that impacts could be offset. The Final Engineering Report explains that DOT eliminated the alternate of the existing alignment because of the loss of access to the island from Manatee Avenue during the two- year construction period. The Final Engineering Report does not mention the reasons for the elimination of the no- build alternative. On July 8, 1991, Figg and Muller issued the Final Bridge Concept Report. The concept remained the construction of two, two-lane fixed-span, high-level bridges in two phases and the removal of the Anna Maria Island Bridge. The purpose of the Final Bridge Concept Report is to provide detailed findings of different types of structures and recommend the appropriate alternatives for consideration in the "final phase of the design and plan preparation." The recommendation is based on comparative analyses of cost and design features. The Final Bridge Concept Report refers the reader to the Final Preliminary Engineering Report for information about environmental conditions. In a brief synopsis, the Final Bridge Concept Report continues erroneously to describe the waters around the Anna Maria Island Bridge as Class III waters, but recognizes that they are Outstanding Florida Waters, so "special emphasis must be placed on the water quality." The Final Bridge Concept Report notes that the total area of seagrass "involved" with the proposed bridge is 1.65 acres and that manatee use the area. Describing the two phases of the overall project, the Final Bridge Concept Report states that the first two-lane bridge would be constructed in the same "corridor alignment," just south of the existing bridge. DOT would build the second bridge when traffic warranted, which is projected to be 2006. In mid-1991, DOT entered into a new contract with Figg and Muller to prepare final design and construction plans for the proposed bridge. DOT included funding for construction of the bridge in its work program adopted in July 1991 with work scheduled for fiscal year 1996. In June and July 1992, the Peninsula employee conducted additional fieldwork to determine the extent of seagrass. This time, though, his work focused specifically on the area under the existing and proposed bridge. The resulting Baseline Seagrass Survey, which Peninsula submitted to DEP in November 1992, states that the purpose of the fieldwork was to collect sufficient baseline data so that DOT could determine the success of natural recolonization under the existing bridge and seagrass shading under the new bridge. The 1992 fieldwork is more intensive than the 1988 fieldwork. The Peninsula employee made ten north-south transects across Sarasota Pass. Although still lacking a bathymetric survey of bottom elevations and effective water depths, the employee calculated approximate water depths at each of 20 data- collection points along each transect and determined, for each point, the species, shoot density, and areal density of any seagrass. He also collected water-quality data for temperature, salinity, conductivity, dissolved oxygen, and water clarity (secchi depth) and recorded "incidental faunal observations." According to Mr. Crim, DOT had completed about 90 percent of its final design and construction plans in August 1992. At this time, DOT applied to the Army Corps of Engineers for a dredge-and-fill permit, DER for a dredge- and-fill permit, Coast Guard for a bridge permit, and Southwest Florida Water Management District for a management-and-storage-of-surface- water permit. In November 1992, residents of Anna Maria, Holmes Beach, and Bradenton Beach voted on a referendum concerning the 65-foot clearance, fixed- span bridge proposed to replace the Anna Maria Island Bridge. The vote was 1961 opposed and 515 in favor. On December 11, 1992, the City Council of Bradenton Beach voted for DOT to place the proposed bridge project on hold pending further study. However, by memorandum dated December 1, 1992, to Mr. Crim, District Secretary May stated: You may be aware that there is concern currently being expressed by some local officials about the design of the Anna Maria Bridge replacement project. We will proceed with the fixed-span bridge concept as developed in the PD&E document. Please make every effort to render this project "production ready" as rapidly as possible. 3. 1993 Public opposition to the proposed bridge--in any alignment--continued in 1993. DOT participated in two MPO- sponsored public hearings on January 8, 1993, where numerous bridge opponents expressed disapproval of the proposed project. At the 1:00 pm meeting, a DOT representative disclosed that the bridge construction plans were 95 percent complete and right-of-way acquisition was underway. At the 7:00 pm meeting, the DOT representative responded to a question whether DOT could change its plans. He acknowledged that DOT and the MPO could change their plans, but a discussion of such a change three years earlier would have been better because dropping the project now would mean that "we have thrown away a million dollars of tax money." On January 13, 1993, a special MPO task force met and voted 4-3 to oppose the proposed bridge. There was some support on the task force for a 45- foot-high bascule bridge instead of a fixed-span, high-level bridge. On January 19, 1993, area mayors and city council members met with District Secretary May, who discussed the DOT five-year work program. Addressing the proposed bridge, District Secretary May said: . . . one of the primary components of the program is the Anna Maria Bridge and I know that's a great concern to all of you. It's a concern to the department too. So, rather than get into a big discourse on that, it is a 65', fixed span bridge. It's been designed as such. We're in the middle of purchasing right-of-way for that bridge. . . . In response to a question as to the extent of completion of design work and the ability of the MPO to stop the project, District Secretary May stated that 100 percent of the design was completed and, by law, both the MPO and DOT had to concur to stop the project. In response to criticism about the limited extent of public participation, District Secretary May conceded that DOT had improved public participation compared to seven or eight years ago, when DOT "didn't go to . . . near the level of public involvement that we do now." For the Ringling Bridge, for example, he said that he was "soliciting all sorts of input from all those people," referring to the public. Conceding that the Anna Maria Island Bridge is "not structurally deficient," District Secretary May explained that rehabilitation was not a cost- effective solution. When asked if it was a "done deal that the new bridge is coming in," District Secretary May answered, ". . . Yes, there's a new bridge going to be put there." Responding to a follow-up question, District Secretary May repeated the message: "Without a doubt. As opposed to rehabilitation. The MPO has not come to us with any requests yet so we'll respond once we get a request from them. Yes, ma'am." When asked what DOT would do if the MPO now suggested a 45-foot bascule, District Secretary May said he would "respond at that point in time. But that's a million dollars worth of throw-away design." Asked if public reaction to the proposed bridge would not justify dropping the project, District Secretary May replied: . . . First, if I IMPLIED that we were not doing a good job several years ago [in public participation], that, that is incorrect. We did as good a job as we could do then. We're trying . . . we're exceeding that now. He added that the results of the island-wide referendum were based in part on public misunderstanding of the safety issue and advised that the bridge is of interest to the region, not merely the island. Asked at the end of the meeting if he meant that the proposed bridge was "going to happen," District Secretary May answered, "A bridge is going to happen here." He added, "We need a replacement. We need to replace that bridge. We need to have a bridge replacement," rejecting rehabilitation as not cost effective. Still supported by the Manatee County Commission, the bridge was now opposed by the city councils of Anna Maria and Bradenton Beach. The executive director of the MPO mentioned that the Mayor of Holmes Beach reported that the city approved the 75-foot-high bridge, but this support was short-lived. About 40 residents spoke at an MPO meeting on January 25, 1993; nearly all of them opposed the bridge. A SAM attorney argued that DOT's notice preceding the August 1989 public hearing had been defective. Following discussion, with some support for a 45-foot-high bascule bridge, the MPO voted 10-4 to recommend that DOT proceed with the 75-foot-high bridge. Meanwhile, DEP was again expressing concern about the proposed project. By letter dated January 21, 1993, to James Wilt, the DOT district permit engineer responsible for the bridge project, a DEP administrator in the Tampa office advised that he could not recommend the project for approval. Although the letter was not final agency action, it was sent "to allow applicant time to assess fully the further commitment of financial resources for this project." By letter dated February 3, 1993, Mr. Wilt informed the DEP administrator in Tampa that DEP had long known of seagrass impacts from the proposed bridge in the southern alignment. The February 3 letter complains that DEP neglected to mention the possibility that the bridge project might not be permitted in a September 1992 letter stating that the application was complete or in a December 1992 letter stating that processing of the application had begun. The February 3 letter also complains that a DOT representative called DEP in late December "to inquire about the anticipated date of issuance of the Dredge/Fill permit. [She] was advised that a final field review of the site had to be conducted and the DOT could expect to receive a permit the 2nd or 3rd week in January, 1993." Concluding the February 3 letter, DOT warned DEP: Based upon the early and extensive coordination that has occurred on this project, the absence of any adverse comments during the processing of the application and the fact that DER estimated the issuance of a permit in January of this year, anything other than the issuance of a permit for the southern alignment is unacceptable. On February 10, 1993, DEP issued a Notice of Permit Denial, stating that the proposed bridge would "run directly through the most productive and prolific seagrass nursery areas and impact approximately 2.5 acres of productive shallow bottom." Noting that DEP had expressed concerns about the likely inadequacy of mitigation three years earlier, it had recommended that any new bridge be located at the current location. The Notice of Permit Denial acknowledges that DEP had found the proposed project consistent with the Florida Coastal Management Program, "pending a more detailed review during the permitting stage." However, DOT had failed to substantiate its assurances to offset seagrass impacts, according to the Notice of Permit Denial. The Notice of Permit Denial reports that DEP expressed "significant concerns" about the project in January 1990, including the concern that DEP "'could not expect the applicant to be able to provide reasonable assurances that they could offset the loss of this valuable resource (seagrass beds) through mitigation.'" Thus, DEP recommended that the proposed bridge should be located at the location of the existing bridge. The Notice of Permit Denial denies the application because DOT failed to provide reasonable assurance that the project would be clearly in the public interest and would not significantly degrade Outstanding Florida Waters. DEP found that the project would be adverse to endangered species and threatened habitats, adverse to fishing and marine productivity, and adverse to the current condition and relative value of functions being performed because nutrient assimilation would be reduced by the loss of at least 2.5 acres of seagrass serving as viable nursery area. DEP also concluded that DOT had failed to provide a plan to protect Class II, Outstanding Florida Waters, from significant damage or to provide reasonable assurance that the project would not result in the violation of water-quality standards. The Notice of Permit Denial notes in particular that the project could not lawfully reduce below ambient conditions the following water-quality parameters: biological oxygen demand, dissolved oxygen, iron, mercury, nutrients, phosphorus, turbidity, zinc, and biological integrity. On April 27, 1993, the City Council of Anna Maria voted unanimously to reject the proposed bridge. On May 4, 1993, the City Council of Holmes Beach voted 4-1 to reject the proposed bridge. The mayor vetoed the resolution, and the City Council overrode the veto. On July 4, 1993, the Sarasota Herald-Tribune published the results of a survey asking if readers preferred replacing drawbridges on the Intracoastal Waterway with fixed-span, high- level bridges. The results were 73 percent favored replacement and 26 percent opposed replacement. The newspaper reprinted about 75 responses, ranging in emotion between the following: Yes. Don't let the old-timers sway the decision. Let's go with the modern time. Some of them will be long gone before the bridge is completed. No. Keep the unique and lovely part of our country as it was when you were first attracted to it--or move away. Environmental work on the proposed project stepped up after DEP denied the permit. On July 13, 1993, Peninsula forwarded to DEP the Seagrass Mitigation Plan, which later became part of the permit. At the same time, responding to public concerns about wind safety on high-level bridges, DOT retained Dr. Robert C. Sheets, former director of the National Weather Service, to advise on the effects of high winds at high elevations. Dr. Sheets explained why the higher bridge did not pose a significantly greater risk to bridge users than the lower bridge. According to Dr. Sheets, the vertical exchange of energy characteristic of predominantly convective storms like thunderstorms and hurricanes precludes much difference in wind speeds at the two heights in question. The difference in wind speeds during nonconvective storms like "no- name storms" or "storms of the century" is larger, but still not great. No-name storms lack the vertical exchange of energy of hurricanes and thunderstorms, so wind speeds at 75 feet are greater than at 25 feet. Local emergency management and law enforcement officials would close any bridge when wind speeds at the deck reach 45 miles per hour. A 75-foot-high bridge might encounter such winds in nonconvective storms about 20 minutes earlier than would the 25-foot-high existing bridge. In June 1993, Petitioners filed a petition alleging, among other things, that DOT's notice preceding the August 1989 public hearing was legally insufficient because DOT failed to send it to owners of condominiums within 300 feet of the proposed project. Abating any proceedings on the petition, DOT decided to conduct another public hearing on the project. Agreeing to requests of residents to schedule the public hearing in the fall when seasonal residents could attend, DOT scheduled the public hearing for October 26 and 27, 1993. On October 1, 1993, DOT mailed letters to all required persons, including owners of condominiums within 300 feet of the proposed project, advising them of the times, dates, and locations of the public hearing on October 26 and 27, 1993. DOT also advertised the public hearings. The letter and advertisement state: This hearing is being conducted to solicit input from area residents, local public officials, and other interested persons or organizations relative to the location, design, and social, economic and environmental effects of the proposed improvements. . . . The purpose of the project is to replace the existing bascule bridge with a fixed-span high level bridge. To encourage public participation, DOT conducted one public hearing on the mainland and another public hearing on the island. The two public hearings were really a single, two-day public hearing. About 200 persons attended the October 26 hearing in Bradenton and 550 persons attended the October 27 hearing in Holmes Beach. The hearing format for both nights was identical and tracked DOT's typical practice in conducting public hearings, such as the August 1989 hearing. However, each hearing began, after a brief introduction, with an eight-and-one- half minute videotape instead of a live project description. During a break following the videotape, persons in attendance could talk to representatives of DOT and the consultants and ask them questions off the record. The final part of the hearing was devoted entirely to recorded comments from the audience. At the start of the first night's hearing, the DOT representative identified the fixed-span, high-level bridge as DOT's preferred alternate, stating: The reason for holding the public hearing and the purpose of this public hearing is to allow you to present to us any new, any additional information that has not been considered in the past and was not looked at during the study that was held some several years ago on this bridge. At the start of the second night's hearing, the same DOT representative said: "This public hearing . . . involves the replacement of the Anna Maria Bridge. . . . The proposed improvement involves a replacement of the . . . Anna Maria Bridge with a 65-foot minimum clearance, high level, fixed span bridge." The DOT representative added, referring to the fixed- span, high- level bridge: . . . We refer to this as the DOT preferred alternative. It has been said that you did not have the choices that you hear that others have. The public hearing that was held, several people in this room remember that were there about five years ago, presented many different alternatives at that time. In the normal course of a project development and environmental study allows us to go through many different alternatives, and through the weeding out process we then select a preferred alternative based on all of the elements that we can possibly get into in making this decision. We did that. The preferred alternative was chosen and what we have here tonight, for you tonight is the preferred alternative, two level, high level-- 2-lane, high level, fixed bridge. With that, we will now have the presentation. The professionally produced videotape features background music, narration, computer graphics, and skilled editing and cinematography. The videotape begins by stating that DOT has determined the "aging drawbridge to be functionally obsolete because it fails to meet current design standards and has no emergency shoulders for breakdowns." The narration explains that traffic congestion is compounded by bridge openings for marine traffic. The videotape generates an artificial tone of anxiety by fast editing of closeups of existing road traffic and the drawbridge warning light, then zooming in ominously on the warning light and chipped-away concrete revealing steel-reinforcing bars. The narrator tells the audience that these obsolete conditions led DOT to recommend replacing the bridge. As the videotape explains, "Several alternatives were considered when plans for upgrading the Anna Maria Island Bridge were made." The videotape identifies these alternatives as the no-build option, north alignment, and south alignment. The videotape states that the no-build alternative would require extensive and expensive repairs, including the complete renovation of the drawspan and extensive substructure, but this is not economically viable. A new bridge using the existing alignment would eliminate Manatee Avenue access to Anna Maria Island for two years. The north alignment would impact the nearby boat ramp and require a new navigational channel, which would destroy seagrass. The videotape reports that the preferred alternative is the south alignment, which "affects about one and one-half acres of seagrass" that "will be closely monitored." The videotape assures the viewer that the "Florida Department of Transportation is committed to minimizing impacts to the seagrass in the project area." The narration and block letters on the screen add: "The benefits of the recommended alignment constitute the most favorable balance of environmental concerns, welfare of the community and achieving the objective of providing a modern and effective bridge." The videotape mentions that drawbridges require regular openings to allow vessel passage. A computer-graphic rendering of the bascule opening shows the bridge opening quickly without a gate or warning lights, a bus suddenly stopping less than a bus length from the vertical bridge span, and a convertible car stopping quickly behind the bus with a second car immediately queuing up behind the delayed bus and car passengers. The videotape concedes that a mid-level bascule bridge would "alleviate much of the traffic delay," but warns that it is a "greater financial burden." The videotape states that the initial construction cost of a drawbridge would be $11.4 million, and the annual operation and maintenance costs of a drawbridge average at least $150,000 plus a $500,000 major repair job every 20 years. On the other hand, the videotape states that the cost of a fixed- span, high-level bridge would be $8.4 million, so the preferred alternative would save at least $3 million over the life of the project. The videotape displays a sailboat with a mast under 65 feet cruising under the proposed bridge just as emergency vehicles pass cars pulled over onto the spacious shoulder. To the extent of any implication that emergency vehicles could be delayed by an opened drawbridge, the videotape ignores the radio coordination that exists between such vehicles and the bridge tenders. The videotape next considers emergency evacuations. Noting that wave effects and flooding on approaches would more likely close a bridge than would high winds, the videotape warns of conflicts between marine vessels and vehicles during evacuations. This warning ignores the Coast Guard practice not to order bridge openings so as to interfere with evacuations and the effect of the need of islanders to get off the island early due to the flooding of island roads and bridge approaches, typically well in advance of the worst of the storm. Displaying photographs from the same perspective of the existing bridge and the proposed bridge superimposed by computer, the videotape assures that "the bridge blends gracefully with the surrounding area." One photograph depicting the proposed bridge was on display with a photograph displaying the existing bridge, both as seen from the east, slightly south of Manatee Avenue. The actual photographs were also on display at the public hearings. The obvious purpose of the two photographs was to encourage viewers to compare the two bridges. However, the comparison was distorted so as to underrepresent the size of the proposed bridge. The photograph of the proposed bridge was taken with a wide-angle lens with the sides cropped, which removed the distortion and extra field of vision accompanying a wide-angle photograph. Because the photograph of the existing bridge was taken with a normal lens, the photograph of the proposed bridge underrepresented its height and width by 20 percent relative to the height and width of the existing bridge. The videotape concludes: An aesthetically appealing and environmentally sound structure that safely spans the Intracoastal Waterway is the Department's goal. A bridge that blends with the unique ambience of this island paradise while guaranteeing Manatee County's residents and visitors safe and efficient travel is of paramount importance to us all. Though not unanimous, public comment at the public hearings was vastly against the proposed project. Figg and Muller summarized the comments by stating that 374 persons favored the project and 940 persons opposed the project. The most popular reasons against the new bridge were in descending order: environmental problems, high-level wind problems, accelerated development, bad aesthetics, and failure to solve evacuation problems. Among the oral or written comments were comments from an orthopedic surgeon who has lived in Holmes Beach for 24 years, opposed the proposed bridge, and said that the existing bridge had never been a problem in treating his patients on the mainland. The Manatee Chamber of Commerce supported the proposed bridge. The Mayor of the City of Anna Maria complained that DOT took its direction from the MPO, from which the island municipalities had been denied voting membership until late 1989 when they obtained one voting member. The mayor also complained of a bridge-by-bridge approach to bridge construction, rather than a regional plan addressing the uniqueness of the barrier island. Mr. Crim testified at the January 1996 formal hearing in this case that DOT's position at the October 1993 public hearings, compared to the August 1989 public hearing, was "even more defined." Unless "something significant" came up, DOT was "going to build the bridge that it had already planned." Mr. Crim testified that the only other viable option at the 1993 public hearings was the no-build alternative. After the public hearings on October 26 and 27, 1993, District Secretary May reported to the MPO, during its meeting of November 22, 1993, that comments were about 3-1 opposed to the bridge. The MPO voted 6-8 not to reconsider its support for the 75-foot-high bridge. 4. 1994-Present Following the October 1993 public hearings, Petitioners filed a petition with DOT in January 1994 challenging DOT's decision to replace the Anna Maria Island Bridge with a fixed-span, high-level bridge. The procedural history of this case is set forth in the Preliminary Statement and is incorporated by reference. Between the October 1993 public hearings and the formal hearing in this case in January 1996, the MPO dropped the four-lane bridge from its 2020 needs plan based on updated traffic projections that indicate no need for the additional capacity. The needs plan continues to limit Manatee Avenue to two lanes east of the Anna Maria Island Bridge to 75th Street, which is substantially east of the bridge. At the January 1996 formal hearing, Mr. Crim was unaware that the MPO had dropped from its 2020 needs plan the four-laning of Manatee Avenue over Sarasota Pass. However, DOT policy is that once a project has reached a certain stage of development, which this proposed project has, it can only be stopped if both DOT and the MPO agree. As District Secretary May testified, DOT no longer begins the planning process with the MPOs, as it did here, but instead starts with local communities. But even if the MPO voted to eliminate the proposed project, District Secretary May intends for DOT to proceed with the fixed-span, high-level bridge because, by the January 1996 formal hearing, DOT had spent over $2 million on the proposed project. DOT acceded to an MPO request to stop the Cortez bridge- replacement project, but this action preceded District Secretary May's appointment. After more than two years of discussions with DOT following the Notice of Permit Denial, on May 2, 1995, DEP issued an Intent to Issue a dredge- and-fill permit for the demolition of the Anna Maria Island Bridge and construction of a fixed-span, high-level bridge on the originally proposed south alignment. Intervenors filed petitions with DEP in June and July 1995 challenging DEP's Intent to Issue the dredge-and-fill permit. After the formal hearing in December 1995 and issuance of a recommended order recommending that DEP deny the permit, DEP has not yet issued a final order. Ultimate Findings of Fact DOT's Exercise of Discretion in Deciding to Replace the Anna Maria Island Bridge with a Fixed-Span, High-Level Bridge The proposed project would permanently destroy 2.5 acres of seagrass and temporarily destroy 2.0 acres of seagrass. Proposed mitigation is vague, contingent, and ultimate illusory. Degradation of water quality is likely, and DOT never obtained the baseline water-quality data from which analysis must begin. The proposed project would adversely affect the conservation of fish and wildlife, including endangered species and their habitats; adversely affect navigation on the Intracoastal Waterway for tall-masted boats currently using Sarasota Pass; and adversely affect fishing and recreation values by destroying vast areas of seagrass and removing the existing bridge as a popular area for fishing, bicycling, jogging, and walking. A permanent improvement, the proposed project would be sited in a productive marine environment performing crucial functions of feeding endangered manatee and other wildlife and cleaning Outstanding Florida Waters through nutrient assimilation and stabilization of sediments. The proposed project would poorly serve important cultural and aesthetic concerns expressed by an overwhelming majority of island residents, who would be uniquely affected by the proposed project. A large majority of the people of Anna Maria Island do not want the proposed bridge. The island-wide referendum conducted by the three municipalities in November 1992 reveals that opponents outnumber proponents by nearly a 4:1 margin. Some residents reject the bridge because they believe that it is only the first of two bridges, which would double the lanes onto the island and result in greater traffic on the island. DOT does not presently intend to build a second bridge, nor is the MPO seeking such a bridge at present. Some bridge opponents distrust DOT and the mainland-dominated MPO on this point, but the record does not indicate that such plans are presently under active consideration. Most if not all residents opposing the bridge focus on the height of the proposed bridge from the perspective of wind safety, but these concerns are largely ungrounded. However, the concerns of bridge opponents about the height of the proposed bridge extend beyond wind-safety issues. Some residents oppose the proposed bridge because they believe that it is unsuitable for their small island community. A high-level bridge would not permit fishing from anywhere but the extreme ends. Many area residents--many of whom are older persons--who walk, bicycle, or jog on the existing bridge would find the 4 percent grade and bridge height forbidding. It is difficult to see how a single six-foot sidewalk on the proposed bridge would better accommodate walking, bicycling, jogging, and fishing better than the two five-foot sidewalks on the existing bridge. Objections to the bridge height involve more than reduced access for nonmotorists. Except for one condominium permitted under prior law, nothing manmade on the island stands over 38 feet high. Bridge opponents claim that the size and appearance of the bridge would not blend well with the subdued appearance and casual ambience of their island. Bridge opponents prefer their timeworn drawbridge, which allows motorists, bicyclists, and pedestrians to view the water just a few feet below them as they approach or leave the island. Better scaled to the island community, the drawbridge, occasionally interrupting vehicular traffic, provides a marked boundary between the island and the mainland. Such a boundary is less apparent from a wide expanse of new roadway across a fixed- span, high-level bridge, from which motorists, bicyclists, and pedestrians would have little if any view or feeling of the water separating the island from the mainland. Most if not all bridge opponents resist the bridge as a dramatic alteration of the daily gateway to their community. These residents are trying to preserve the special lifestyle-- the pace and rhythm of their lives--that they sought in moving to the island in the first place. At the same time, the reasons for the proposed bridge are insubstantial. Interestingly, DOT recently completed the rehabilitation of the Cortez Bridge. Abandoning earlier plans to replace the bridge, DOT instead repaired and rehabilitated the drawbridge without widening the bridge or bascule spans. The Anna Maria Island Bridge has not proved unsafe over 37 years. Collisions on the bridge approaches are 50 percent more numerous than on the bridge itself. Superficial analysis of the accident data does not alter the fact that the bridge's accident rate is low. Most of the rear-end collisions on the bridge and bridge approaches are attributable to traffic backups from the Gulf Drive light and turns into the boat ramp on the west and convenience store and marina on the east. The drawbridge has not been a material cause of collisions on the bridge and bridge approaches, and the fixed-span, high-level bridge therefore would probably not reduce the number of collisions in this area. If vehicular safety were a problem on the Anna Maria Island Bridge, the sensible response would be to analyze the data carefully. If, for instance, numerous collisions were at night, DOT should considering adding street lights to the bridge. If, as is likely, most of the rear-end collisions are attributable to traffic backups, then DOT should consider the effects of lowering the speed limit through an increasingly congested area with boat ramps, a marina, and a convenience store. Perhaps such a study would present DOT an opportunity to revisit the wisdom of maintaining a 50-mile-per-hour speed limit on a road segment that, to the west, quickly ends at the Gulf of Mexico on a narrow barrier island with constrained and congested roads and, to the east, passes through increasingly urbanized areas. In promoting the proposed bridge, DOT has oversold the planning and design standards that arguably militate against the Anna Maria Island Bridge. In reality, these standards reveal that the decision to add shoulders is conditioned on consideration of numerous other factors, including the environmental, cultural, and aesthetic factors militating in favor of retaining the Anna Maria Island Bridge. DOT claims that the Anna Maria Island Bridge is functionally obsolete in large part due to the absence of shoulders or breakdown lanes on the bridge. Although the safety of a road segment is enhanced by the presence of breakdown lanes, the added margin of safety is not as great as DOT implies in this case. Countering suggestions of greater safety, the shouldered approaches to the bridge have experienced 50 percent more collisions than the unshouldered bridge. The record contains three sources of design standards for bridges: DOT's Index No. 700 or Design Criteria Related to Highway Safety, dated September 1991 (SAM Exhibit No. 123); Chapters 1 and 2 of Volume I of DOT's Plans Preparation Manual (SAM Exhibit No. 126); and the 1990 standards of the American Association of State Highway and Transportation Officials (AASHTO) (SAM Exhibit No. 105). The Plans Preparation Manual specifies that through lanes should be "as wide as practical, up to 12 feet." Index No. 700 specifies that clear widths for bridges with undivided travel lanes on urban arterials with design speeds of 30-50 miles per hour, such as this road segment, should be the "travel lanes plus approach shoulder widths." The introduction to Chapter 1 of the Plans Preparation Manual states that projects are normally based on established design standards for the various elements of the project, such as width of roadway . . .. Selection of the appropriate standards is influenced by traffic volume and composition, desired levels of service, terrain features, roadside developments, environmental considerations and other individual characteristics. Addressing the aesthetics of road projects, Chapter 1 states that the designer should consider, after functionality, how a highway will be perceived by users, ensuring that "[h]orizontal and vertical alignment should be coordinated so that a driver has an opportunity to gain a sense of the local environment." Notes to Index No. 700 stress the conditionality of the design standards. One note states: "Values shown above shall be used on all new construction and on reconstruction projects to the extent that economic and environmental considerations and [right-of-way] limitations will allow." Another note adds for clear zones: Standard values are to be used for all new construction projects. These values may be reduced only where individually justified to mitigate critical social, economic, and environ- mental impacts or to lessen right-of- way costs. Standard values are also to be used for recon- struction projects; however values down to AASHTO minimum may be used where individually justified due to critical social, economic and environmental impacts and/or excessive right-of-way costs or when existing roadside obstacles are not considered hazardous as evidenced by field review and by accident history or accident potential. AASHTO standards call for a minimum width of the travel lanes plus three feet per side. But AASHTO standards recognize that reasonably adequate bridges . . . that meet tolerable criteria may be retained. Some of the nontechnical factors that should be considered are the esthetic value and the historical signifi- cance attached to famous structures, covered bridges, and stone arches. The bridge approaches have eight-foot gravel shoulders, although no design shoulders. However, the design standards do not require bridge shoulders of eight feet or even three feet without consideration of environmental, aesthetic, social, and economic factors. After consideration of all the factors, the cited design standards do not mandate the widening of the existing bridge to add shoulders. As for the failure of the Anna Maria Island Bridge to meet current load standards for bridges, the AASHTO minimum design standard for new bridges "should be HS-20." The existing bridge is rated HS-15. However, the same conditions attach to the load standard of a bridge as apply to the presence and width of shoulders. HS-15 is a "tolerable" criterion. There is nothing in the record suggesting that the current load limit of the Anna Maria Island Bridge is unsafe. If DOT were concerned about the load capacity of the bridge, it would have imposed weight limits on the bridge. After consideration of all the factors, the design standards no more call for a new bridge to increase the load rating to HS-20 than they call for adding shoulders to the bridge. As for the failure of the Anna Maria Island Bridge to meet current ship-impact standards, the record does not clearly establish that the existing bridge fails to meet these standards. Even if it fails to meet these standards, the VE team itself recommended relaxing the H-20 bridge-impact standard outside of the channel, partly based on the faultless marine safety record of the bridge and the availability of alternative access to Anna Maria Island. Even DOT does not cite a 25 percent improvement in ship- impact resistance as a compelling reason, in isolation, for a new bridge. The Draft Preliminary Engineering Report contends that the Anna Maria Island Bridge should be replaced due to its low overall clearance. But the proposed bridge would effectively close the Intracoastal Waterway at Sarasota Pass to a growing number of sailboats that can presently navigate the pass. And there is no evidence that the 36 daily bridge openings unduly delay vehicular traffic, especially in view of the traffic delays already caused by the traffic light at Gulf Drive. The Final Preliminary Engineering Report adds two more reasons for replacing the Anna Maria Island Bridge. The first is the need to accommodate traffic increases. However, updated analysis has reduced traffic projections, and the proposed bridge is now clearly limited to two lanes in any event. The second reason cited in the Final Preliminary Engineering Report is "structural deficiency." There is absolutely no evidence in the record suggesting that the Anna Maria Island Bridge is structurally deficient. Nine months prior to this statement appearing in the Final Preliminary Engineering Report the VE team inspected the bridge and found it was in "good condition" with "no severe deterioration which would endanger the capacity of the bridge." Coming from engineers, the assertion that the bridge is "structurally deficient," without support or qualification, was irresponsible. The driving force behind DOT's decision to replace the Anna Maria Island Bridge seems to be cost. DOT contends that it is less expensive to replace the Anna Maria Island Bridge now than it is to rehabilitate and repair it for the remainder of its useful life. When built, the Anna Maria Island Bridge had a life expectancy of 50 years. The bridge remains in "good condition," and traffic demands on this segment of Manatee Avenue can be satisfied by two lanes for a period in excess of the remaining useful life of the bridge. DOT projects the cost of the new bridge at $8.4 million. However, DOT has spent $2 million without commencing construction and still has not identified aspects of construction that might be dictated by environmental concerns, such as the construction of work platforms or use of specialized demolition techniques. The $8.4 million figure is probably low. The $8.4 million projection for the proposed bridge is definitely low once environmental costs are considered. Perhaps incapable even of approximation as to lost seagrass beds, degraded water quality, and reduced wildlife, including manatee, environmental costs can be partly quantified in terms of lost recreational opportunities, property values, and business income in the event of degraded waterbodies and increased governmental expenditures to reverse environmental degradation. It is even more likely that DOT's cost figures for retaining the Anna Maria Island Bridge are high. DOT projects "minor" (i.e., without widening) rehabilitation costs for the Anna Maria Island Bridge as $2.0-$3.8 million. They are based on general experience, which has not proved reliable for this bridge. General experience suggests that a bridge of this type and vintage should have needed to be rehabilitated at 20 years; yet, 37 years later, still without such a rehabil- itation, the Anna Maria Island Bridge remains in good condition. The Anna Maria Island Bridge could benefit from a "minor" rehabilitation costing at least $500,000. This probably would be the only substantial rehabilitation required for the remaining useful life of the bridge. DOT typically replaces rather than rehabilitates when rehabilitation will cost at least 60 percent of the cost of replacement. If so, using DOT's numbers, replacement would not be indicated unless rehabilitation were to cost over $5 million. Several provisions in the state comprehensive plan tend to sustain DOT's decision to replace the Anna Maria Island Bridge with a fixed-span, high- level bridge. Three of these provisions are in the transportation section of the state comprehensive plan calling for transportation planning to manage growth, enhance system efficiency, and ensure efficient access to services, jobs, markets, and attractions. A provision in the public facilities section calls for planning and financing new facilities in a timely, orderly, and efficient manner. These provisions favor the new bridge only to the extent of a need for the new structure. Absent a need, some of these provisions, such as favoring timely and efficient planning of new facilities, actually militate against the new bridge because DOT could advance the funding of another, needed project if it did not spend the money on the replacement bridge. Arrayed against these provisions of the state comprehensive plan are numerous other provisions clearly disfavoring the new bridge. Some of these provisions are in the sections on transportation and public facilities. One provision admonishes that, in addition to enhancing system efficiency, it is also important to minimize adverse environmental impacts. Another transportation provision is to promote timely resurfacing and repair of roads and bridges to minimize costly reconstruction and enhance safety. A final applicable transportation provision is to avoid transportation improvements that encourage increased development in coastal high-hazard or productive marine areas. According to the Draft Preliminary Engineering Report, the proposed bridge "could foster economic development in the area," meaning the barrier island. Provisions in the section on public facilities are to protect substantial investments in already-existing public facilities and promote rehabilitation and reuse of existing facilities rather than commence new construction. Numerous provisions of the state comprehensive plan disfavor the new bridge on environmental grounds. Florida must ensure that development in coastal areas does not endanger important natural or marine resources and must protect and restore long-term productivity of marine fisheries habitat and other aquatic resources. Other provisions are to conserve wetlands, fish, and marine life to maintain their environmental, economic, aesthetic, and recreational values; to prohibit the destruction of endangered species and protect their habitats; and to protect and restore the ecological functions of wetlands systems to ensure their long-term environmental, economic, and recreational value. One provision explicitly links Florida's environmental health with its economic health by requiring that Florida maintain the environment as one of its primary economic assets. The proposed bridge project is inconsistent with the state comprehensive plan, taken as a whole. The proposed project disregards the requirements to rehabilitate and reuse existing facilities where possible, to avoid transportation improvements that encourage development in coastal high- hazard areas, and to repair and resurface roads and bridges in time to avoid more costly expenses. The inconsistencies between the proposed project and environmental provisions of the state comprehensive plan are evident. Another group of provisions disfavors on a different basis the decision to replace the Anna Maria Island Bridge with the new bridge. These provisions call for improved intergovernmental coordination, maximized citizen involvement, and encouraged citizen participation at all levels of policy development, planning, and operations. The record does not support a finding that DOT seriously addressed the various elements in the state comprehensive plan that must guide state agencies in their capital expenditures. In so doing, DOT undermined citizen participation in this important planning process. DOT and its consultants collected some environmental data, but too little, too late. Also, DOT never subjected the environmental data to detailed, careful analysis. Motivated by cost considerations, which offer scant support for the proposed bridge project, DOT sought to replace old drawbridges and wanted to replace them as inexpensively as was reasonably possible. In pursuing its drawbridge-replacement policy in this case, DOT did not assess sufficiently the relevant environmental, cultural, and aesthetic factors. This failure undermined citizen participation and the planning process itself. For instance, before collecting the detailed seagrass data in June and July 1992, DOT had already proceeded far into the planning for the present project, rejecting the no-build alternative, selecting the south alignment, and possibly selecting the fixed-span, high-level design. Yet, informed consideration by DOT and the public of all of the alternatives demanded early knowledge of the area and functions of seagrass to be destroyed by the project. The seagrass issue came as no surprise to DOT. Sarasota Pass is Outstanding Florida Waters. A DOT representative had warned other DOT representatives in July 1989 that they had not had much success with seagrass mitigation. Over a year earlier, at the very inception of this long planning process, Figg and Muller amply identified in its subconsulting contract with Peninsula the various environmental problems posed by this project. In early 1990, DER warned DOT about the importance of seagrass and mitigation. Yet, DOT elected to avoid federal environmental review by obtaining in mid-1990 a categoric exclusion on the basis that the proposed supposedly had no significant impact on any natural, cultural, or recreational resources and had no significant impact on water quality. Instead of seriously confronting the seagrass issue, Sverdrup twice tried to influence Figg and Muller and its subconsultant to understate the amount of seagrass that would be destroyed by the proposed project. These efforts are not merely unreasonable in retrospect, but were unreasonable at the time, as evidenced by the angry reaction of the Peninsula employee and the more businesslike resistance of Figg and Muller. The resulting atmosphere was not conducive to a vigorous investigation of environmental conditions and thoughtful analysis of the impact of the proposed alternatives on these conditions. DOT and its consultants never obtained much data that various parties demanded. When entering into the subconsulting contract with Peninsula, Figg and Muller required Peninsula to do an analysis of bottom sediments for heavy metal concentrations, but this was never done. In early 1990, DER warned DOT about the strict water-quality standards applicable to the project. Yet, DOT and its consultants never obtained vital water-quality data. Still in the first half of 1990, DEP recommended that DOT obtain a bathymetric survey, which DEP promised to review in detail at the permitting stage. But DOT and its consultants never obtained this crucial data either. In fact, it was not until two years later--after DOT had rejected the no-build alternative and south alignment, if not also the bascule designs--that Peninsula obtained seagrass data of the level of detail even approaching what DEP had sought. The treatment of manatee in the planning process was also inadequate. Omitted entirely from the Draft Preliminary Engineering Report, manatee were discussed in later documents. But at no time did any consultant address two distinct threats posed to manatee by the proposed project. First, the wider-spanned bridge would, as promised by the Draft Preliminary Engineering Report, enhance navigation for shallow-drafter boats by facilitating their bypassing of the channel and cutting under the bridge. In addition to destroying seagrass by prop dredging, small boats cutting under the bridge would threaten manatee feeding in shallow water in exactly the manner described in the Permit Coordination Package. Second, construction of the new bridge would effectively narrow the pass, which has already been constricted by fill placed when the Anna Maria Island Bridge was built. This would drive manatee into a narrower area within the channel and increase the chances of injury from collisions with boats. 335. More than once in this planning process, DOT and its consultants tried unreasonably to wring support for the proposed project from unfavorable data and analysis. Mr. Smith's attempts to coerce the analysis of seagrass losses is perhaps the most glaring example of this unfortunate treatment of data and analysis. Another Sverdrup representative discouraged independent analysis of new traffic data by Figg and Muller when he sent Figg and Muller a memorandum with the instructions to analyze and document the data "to reach the conclusions necessary to proceed with the project development." A more pervasive example of this practice is in the treatment of the accident data. In the Site Characteristics Report prepared at the end of 1988, the consultants noted the low accident rate of the Anna Maria Island Bridge and suggested reasonably that the high percentage of rear-end collisions might be due to traffic backups, which might be due to backups from the Gulf Drive traffic light, nearby left turns, or drawbridge openings. A month or two later, in the Draft Preliminary Engineering Report, Figg and Muller tried, without detailed analysis of accident reports, to limit the effects of the boat ramp, marina, convenience store, and traffic signal to rear-end collisions on the approaches and attribute rear-end collisions on the bridge to the opening of the drawbridge. A later reference in the draft report to accident data "for the existing facility" is misleading for its failure to differentiate between the bridge and the bridge approaches. By the August 1989 public hearing, the Figg and Muller representative was telling the public that the drawbridge openings were a cause of a "significant number" of rear-end collisions. No evidence supports this conjecture, which does not rise to the level of analysis. DOT and its consultants failed to substantiate other vehicular safety concerns when they failed to account for the coordination that exists between drawbridge openings and emergency vehicles and drawbridge openings and hurricane evacuation. Yet, DOT and its consultants continued to cite these nonissues, like they cited rear-end collisions, prominently in their arguments about functional obsolescence and safety, at least through the rejection of the no- build alternative in the Final Preliminary Engineering Report issued on November 1, 1989. At the formal hearing, DOT tried to bolster its safety arguments with two new arguments that are hopelessly anecdotal. DOT presented evidence that bridge tenders are susceptible to crime: a DOT witness testified that the shelter of a bridge tender in Dade County was pockmarked by numerous bullet holes. Another DOT witness testified that a bridge tender was crushed by the gears of a drawbridge he was trying to fix when the power company suddenly restored power after an outage. Neither narrative establishes widespread problems with drawbridges. There is nothing to suggest that a bridge tender on the Anna Maria Island Bridge must contend with drive-by shootings. If so, motorists and other users of the bridge might be safer if a bridge tender were available to telephone the police. The death of the bridge tender crushed by the drawbridge gears was tragic, but easily avoidable simply by shutting down the power to the bridge before working on it. Likewise, DOT tried at the formal hearing to support the functional- obsolescence argument by contending that the additional lanes would hasten evacuation efforts by the ability to convert to more lanes one-way east. But island evacuation does not require the addition of two shoulders that could be converted into travel lanes during evacuations. Successful evacuations have taken place with the existing bridge, whose two lanes can be used one-way east in emergencies. The two-lane bridge is not a bottleneck considering the two- lane facility to the east and the floodprone bridge approaches and island road system to the west. DOT's premature commitment to project implementation discouraged objective analysis of the data. Nor was DOT receptive to DEP's role in reviewing the proposed project. When DER withdrew its early objections to the Advance Notification Package in April 1990, it promised a more detailed review during permitting. But the Final Engineering Report in early 1991 sounded what proved to be an ominous note when it stated that, based on the agreement with DER, DOT had spent about $1 million of public funds on the completion of the PD&E process and final design of the new bridge. Not applying for permits when the design work was 65- 70 percent complete, as directed by the PD&E, DOT waited instead until August 1992, when the final design and construction plans for the project were 90 percent complete. When DEP expressed concern about the project, DOT, ignoring another opportunity to focus on the substantive environmental and public welfare issues, responded instead with an insubstantial estoppel argument and stern warning that "anything other than the issuance of a permit for the southern alignment is unacceptable." Not every transportation project will serve all provisions of the state comprehensive plan. Some planning processes and decisions may even conflict with more provisions of the state comprehensive plan than they serve, but still not conflict sufficiently with the entire state comprehensive plan, construed as a whole, to constitute an abuse of discretion. But in this case, the proposed project is marginally consistent with a few provisions and markedly inconsistent with numerous, material provisions of the state comprehensive plan. And the inconsistencies appear to be the direct result of the repeated failures of DOT and its consultants to collect necessary data and their repeated efforts to wring support from unsupportive data and analysis. These inconsistencies with the state comprehensive plan amount to an abuse of discretion in deciding to replace the Anna Maria Island Bridge with the fixed- span, high-level bridge. DOT's Compliance with the Statutory Requirement of Public Hearings, Including Effective Public Participation, Prior to Selecting, Locating, and Designing the Fixed-Span, High-Level Bridge The replacement of the Anna Maria Island Bridge with a fixed-span, high-level bridge is a major transportation improvement. The proposed bridge would cost millions of dollars, destroy 2.5 acres of seagrass permanently and 2.0 acres of seagrass temporarily, imperil manatee, and degrade Outstanding Florida Waters. The proposed project has generated considerable public controversy, which triggers the requirement of a public hearing in the PD&E manual. The proposed project is a "major transportation project," under the definition in the PD&E manual requiring an environmental impact study. Sverdrup's Project Concept Report calls the proposed project a "major bridge replacement project." DOT was amenable to public input on all issues at the February 1989 workshop, but there is no indication that DOT provided sufficient notice as to permit the public to participate effectively. DOT was clearly amenable to public input at the August 1989 public hearing as to the location of the proposed bridge. DOT still was in the formulative stage of deciding the alignment of any new bridge. DOT opted for the south alignment only after hearing public comments concerning the impact of the north alignment on navigation, recreation, and business. The notice for the August 1989 public hearing, though insufficient to satisfy the statutory requirement for a design public hearing, was reasonable in that it was sufficient to satisfy the requirement of effective public participation. It is less clear that DOT had not, prior to the August 1989 public hearing, already selected the facility-type--namely, a new bridge over the no- build option. But Petitioners and Intervenors failed to show that DOT had in fact already made this decision before the August 1989 public hearing. DOT announced the rejection of the no-build alternative on November 1, 1989, in the Final Preliminary Engineering Report. Although Mr. Smith's June 13, 1989, memorandum to Figg and Muller recommended the rejection of the no-build alternative, Figg and Muller proved able to resist Sverdrup's suggestions as to seagrass losses, and other evidence does not point clearly to an earlier rejection of the no-build option. But the preponderance of the evidence establishes that, long prior to October 1993, DOT had selected and committed to the design of the new fixed- span, high-level bridge over such alternatives as a low-, mid-, or high-level bascule bridge. DOT representatives and consultants thought that they had already conducted the design public hearing four years earlier. Only in early 1993 did DOT decide to hold another design public hearing after reconsidering the legal sufficiency of the notice before the August 1989 public hearing. So, for at least three and one-half years, DOT and its consultants operated on the assumption that DOT had satisfied the requirement of a design public hearing and could proceed to the next step. It is unreasonable to expect, given DOT's strong commitment to project implementation, that the project did not proceed through design in these three and one-half years. DOT spent $1 million on planning and design for this project through the Final Engineering Report issued on November 1, 1989. If the total cost of the fixed-span, high-level bridge on the south alignment was to be $8.4 million and construction had not yet begun, one would infer that the $1 million covered a lot of the required design. By the formal hearing in January 1996, DOT had spent $2 million on the proposed bridge. Although part of that sum may have gone toward litigation expenses, most of it presumably went toward additional design and construction planning. Additional evidence that DOT selected the design prior to the October 1993 public hearings comes from two sources: the preparation of documentary milestones in the planning process and statements of DOT representatives. According to the PD&E manual, DOT issues the Final Engineering Report after the public hearings and selection of the recommended alternate. The Final Engineering Report, which was issued in late 1990 or early 1991, follows the approval by the Federal Highway Administration of the recommended alternative, according to the PD&E manual. According to the PD&E manual, DOT applies for permits when the project design is 65-70 percent done. In August 1991, DOT applied for permits after retaining Figg and Muller in mid-1991 to prepare final design and construction plans. All this time, the Draft Preliminary Engineering Report had all but eliminated bascule alternatives in February 1989. Public comments of DOT representatives disclose with greater certainty than milestone documentation the design progress on this project. As early as March 31, 1989, Sverdrup advised Figg and Muller not to do traffic calculations for bascule alternatives "since it is evident that the fixed high- level structure will be recommended due to lower overall cost." Later comments consistently portray the bridge design as finished or all but finished by the end of 1992 and start of 1993; there is no doubt that DOT had selected and committed to a design by this time. When DOT submitted the dredge-and-fill application in August 1992, final design and construction planning was 90 percent complete, according to Mr. Crim. On December 1, 1992, District Secretary May, sensing increasing community resistance to the proposed bridge, acknowledged local resistance to the "design" of the replacement bridge and directed Mr. Crim that "we will proceed with the fixed-span bridge concept as developed in the PD&E document. Please make every effort to render this project 'production ready' as rapidly as possible." On January 8, 1993, a DOT representative told MPO representatives that construction plans were 95 percent done and acquisition of right-of-way had begun. Referring to the new bridge, District Secretary May told a meeting of local government officials on January 19, 1993, that "it's been designed" as a fixed-span, high-level bridge. He stated that 100 percent of the design work was done and changing to a 45-foot bascule bridge would mean that DOT had thrown away $1 million on design work. According to Mr. Crim, the options at the October 1993 public hearing were the fixed-span, high-level bridge or the no- build alternative; the bridge design was thus no longer in doubt. DOT's misplaced reliance on the August 1989 public hearing as a design hearing did not preclude the possibility that DOT could have conducted a design public hearing at a later date with effective public participation. The key factual questions would be whether DOT had already decided upon a design and, if so, whether it had restarted the design-selection process so as to approach the curative public hearing with no precommitment toward the fixed- span, high-level design. It is unnecessary to explore in any detail what restarting the design selection process would entail. DOT could have approached the October 1993 public hearing differently than it approached other public hearings. DOT could have engaged the public, on the record, in a give-and-take analysis of the engineering, traffic, environmental, cultural, and other data. DOT could have abandoned its customary approach requiring the public to show an error, an omission, or changed conditions, or else DOT's tentative decision would become final. Instead, DOT approached the October 1993 public hearing, as Mr. Crim admitted, with an "even more defined" position than usual. Unless something "significant" came up at the hearing, the fixed-span, high-level bridge was going in. Presenting a blatantly promotional videotape and a distorted comparative photograph, DOT tried to rescue the $1-2 million it had invested in this project rather than risk a wide-ranging public discussion on the design of the proposed bridge with a meaningful exchange of information and analysis. The resulting burden placed on the public to change DOT's mind was inordinate, precluded effective public participation, and revealed DOT's commitment to the fixed-span, high-level design.

Recommendation It is RECOMMENDED that the Department of Transportation enter a final order cancelling the proposed project to replace the Anna Maria Island Bridge with a fixed-span, high-level bridge. ENTERED on May 6, 1996, in Tallahassee, Florida. ROBERT E. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings on May 6, 1996. APPENDIX Rulings on Proposed Findings of Petitioners and SAM 1-5: adopted or adopted in substance. 6: same rulings as in prior recommended order except to extent of any contrary rulings in this recommended order. 7: adopted or adopted in substance, during the early part of the planning process. 8: adopted or adopted in substance, except as to the date of the public hearing. 9-17: adopted or adopted in substance. 18: rejected as irrelevant. 19-23: adopted or adopted in substance. 24: rejected as irrelevant. 25: adopted or adopted in substance. 26: adopted or adopted in substance, except as to author and recipient of memorandum. 27: rejected as unnecessary. 28: adopted or adopted in substance. 29-35: rejected as unnecessary. 36-37: adopted or adopted in substance. 38-41: rejected as subordinate. 42-43: rejected as irrelevant. 44: rejected as unsupported by the appropriate weight of the evidence. 45-46: rejected as subordinate. 47-54: adopted or adopted in substance. 55: rejected as unsupported by the appropriate weight of the evidence. 56: rejected as recitation of evidence. 57: rejected as subordinate. 58-63: adopted or adopted in substance. 64: rejected as subordinate. 65-66: adopted or adopted in substance. 67-79: rejected as subordinate. 80-83: adopted or adopted in substance. 84: rejected as recitation of evidence. The selection of the type of facility in this case is a bridge--specifically whether to build a new bridge or rehabilitate the old one. 85: adopted or adopted in substance. 86: adopted or adopted in substance, except that DOT did not select the facility-type (a bridge) and the site (the south alignment) until after the August 1989 public hearing. 87: rejected as not finding of fact. 88: adopted or adopted in substance. 89: rejected as unnecessary. It is only necessary to find that DOT selected the fixed-span, high-level design prior to the October 1993 design public hearings. 90-91: rejected as subordinate. 92: adopted or adopted in substance. 93: rejected as subordinate. 94-98: adopted or adopted in substance. 99: adopted or adopted in substance, but the approaches have actual, gravel shoulders of eight feet. 100: rejected as unsupported by the appropriate weight of the evidence. 101-43: adopted or adopted in substance. 144: rejected as subordinate. 145: adopted or adopted in substance. 146-47: rejected as unsupported by the appropriate weight of the evidence. 148-53: adopted or adopted in substance. 154-57: rejected as unsupported by the appropriate weight of the evidence. 158-60: adopted or adopted in substance. Rulings on Proposed Findings of Intervenor VanWagoner Any proposed findings referring to statements of counsel that have been adopted were adopted because of evidence in the record supporting such findings. Counsel's statements are not support for such proposed findings because these statements are not evidence. Any proposed findings referring to views taken by the undersigned that have been adopted were adopted because of evidence in the record supporting such findings, such as road maps. 1-11: adopted or adopted in substance. 12: rejected as subordinate and unnecessary. 13: adopted or adopted in substance, as to removal of four- laning project from MPO needs plan. 14: rejected as speculative. 15: rejected as unsupported by the appropriate weight of the evidence, as to safety being an issue. 16: adopted or adopted in substance. 17: rejected as subordinate, except as to a design change. 18: rejected as unsupported by the appropriate weight of the evidence. 19-20: rejected as subordinate. 21 (first sentence): rejected as unsupported by the appropriate weight of the evidence. 21 (remainder): rejected as recitation of evidence. 22-24: rejected as unnecessary. 25: adopted or adopted in substance. 26-27: rejected as unsupported by the appropriate weight of the evidence. 28-33: rejected as recitation of evidence. 34-37: adopted or adopted in substance. 38: rejected as recitation of evidence. 39: adopted or adopted in substance, except that proposed finding as to disclosure is rejected as unnecessary. 40-43: rejected as subordinate. 44: adopted or adopted in substance. 45-47: rejected as recitation of evidence. 48: adopted or adopted in substance. 49: rejected as unnecessary. 50-51: rejected as subordinate and recitation of evidence. 52-53: adopted or adopted in substance. 54-64: rejected as subordinate. 65-66 (first paragraph): rejected as recitation of evidence. 66 (remainder): adopted or adopted in substance. 67-70: rejected as recitation of evidence. 71: adopted or adopted in substance. 72-73: rejected as subordinate. 74: adopted or adopted in substance. 73 (second 73)-75: rejected as not findings of fact. 76: adopted or adopted in substance. 77 (first clause): rejected as unsupported by the appropriate weight of the evidence. 77 (second clause): adopted or adopted in substance. 78: adopted or adopted in substance. 79-80: rejected as unsupported by the appropriate weight of the evidence. 81-83: rejected as not findings of fact. 84: adopted or adopted in substance. 85: rejected as unsupported by the appropriate weight of the evidence. 86: adopted or adopted in substance. 87: rejected as unsupported by the appropriate weight of the evidence. Rulings on Proposed Findings of DOT 1-2: adopted or adopted in substance except for the date of construction. Most references in the DOT documentation are to 1959, although there are some references to 1957. 3 (first two sentences): adopted or adopted in substance. 3 (last sentence): rejected as subordinate. 4-13: adopted or adopted in substance. 14: adopted as to 4 percent grade, but rejected as irrelevant as to remainder. 15: rejected as subordinate. 16 (first sentence): adopted or adopted in substance. (second sentence): rejected as subordinate. (first sentence): rejected as subordinate. 17 (second sentence): adopted or adopted in substance. 18-21: adopted or adopted in substance. 22-24: rejected as irrelevant and subordinate. 25-26 (first sentence): adopted or adopted in substance. 26 (second sentence): rejected as unsupported by the appropriate weight of the evidence. 27: adopted or adopted in substance. 28: adopted or adopted in substance, except that there are conditions attached to the standard criteria. Also, replacement remains a factual determination requiring consideration of all the circumstances. 29: adopted or adopted in substance. 30: adopted in the sense that the decision to replace the Anna Maria Island Bridge accompanied the PD&E process. 31 (first sentence): adopted or adopted in substance. 31 (second sentence): rejected as unsupported by the appropriate weight of the evidence. 32-34: adopted or adopted in substance. 35: rejected as subordinate, irrelevant, or unsupported by the appropriate weight of the evidence. 36-39: adopted or adopted in substance, except as to no foregone conclusions reached as a result of DOT's studies, which is rejected as unsupported by the appropriate weight of the evidence. 40-53: adopted or adopted in substance. 54: adopted or adopted in substance, except the public lacked effective participation in the February 1989 workshop because of lack of notice and lack of factual background. If the references to "workshop" are to the August 1989 public hearing, this format too leaves something to be desired as to effective public participation given the refusal of DOT and consultant representatives to engage in any give-and-take with member of the public except off the record during the break and the refusal to discuss anything but the project under consideration. 55-60: adopted or adopted in substance. 61: adopted or adopted in substance, except willingness to continue with public involvement is rejected as unsupported by the appropriate weight of the evidence. 62: adopted or adopted in substance. 63 (first two sentences): rejected as unsupported by the appropriate weight of the evidence. 63 (third sentence): adopted or adopted in substance, as the sole reason for the October 1993 public hearings. 64-65 (first sentence): rejected as unsupported by the appropriate weight of the evidence. 65 (remainder)-68: adopted or adopted in substance. 69: rejected as unsupported by the appropriate weight of the evidence; the fixed-span, high-level bridge was the selection, not merely a preferred alternative. 70-71: adopted or adopted in substance. 72 (first sentence): rejected as irrelevant. District Secretary May does not need to attend the public hearings or remain in the hearing room during the public hearings, if he attends. If he is to be involved in the decision, he needs only to familiarize himself with the public comments. 72 (second sentence)-74: rejected as unsupported by the appropriate weight of the evidence. 75: rejected as subordinate and unnecessary. 76: rejected as unsupported by the appropriate weight of the evidence. 77-78: rejected as subordinate. 79: rejected as unsupported by the appropriate weight of the evidence, although cost was a major factor in the design decision, whenever it was actually made. 80: rejected as subordinate. 81-82 (first sentence): adopted or adopted in substance. 82 (second and third sentences): rejected as unsupported by the appropriate weight of the evidence. 82 (fourth sentence): adopted or adopted in substance, although this projection is probably too low. 83-84: rejected as unsupported by the appropriate weight of the evidence. 85-87: adopted or adopted in substance, as recitals of DOT's reasoning-- not as persuasive reasoning under all of the circumstances. 88: adopted or adopted in substance, as recital of Final Preliminary Engineering Report. 89: rejected as unsupported by the appropriate weight of the evidence. 90: rejected as subordinate and irrelevant. 91-92 (except last sentence): adopted or adopted in substance. 92 (last sentence): rejected as unsupported by the appropriate weight of the evidence. 93-94 (first sentence): adopted or adopted in substance. 94 (second sentence): rejected as unsupported by the appropriate weight of the evidence. 95: adopted or adopted in substance. 96: adopted or adopted in substance, as recital of DOT's thinking. 97: adopted or adopted in substance. 98: adopted or adopted in substance, except as to not meeting design standards. 99: adopted or adopted in substance, as recital of DOT's thinking. 100-04: rejected as irrelevant. 105: adopted or adopted in substance, as recital of thinking of these individuals. 106: rejected as repetitious. 107: adopted or adopted in substance. 108 (first sentence): rejected as irrelevant. 108 (second sentence): rejected as unsupported by the appropriate weight of the evidence. 109: rejected as unsupported by the appropriate weight of the evidence and irrelevant. 110: rejected as unsupported by the appropriate weight of the evidence. 111: rejected as unsupported by the appropriate weight of the evidence. 112: rejected as unsupported by the appropriate weight of the evidence and irrelevant. 113 (first sentence): adopted or adopted in substance. 113 (second sentence): rejected as irrelevant and as unsupported by the appropriate weight of the evidence. 114-16: rejected as unsupported by the appropriate weight of the evidence. 117 (except second sentence): rejected as subordinate. (second sentence): adopted or adopted in substance. (first sentence): rejected as subordinate and irrelevant. 118 (second sentence): adopted or adopted in substance. 119: rejected as irrelevant and subordinate. 120: rejected as unsupported by the appropriate weight of the evidence. 121 (first clause): adopted or adopted in substance. 121 (remainder): rejected as irrelevant and subordinate. 122-26: adopted or adopted in substance. 127-28: adopted or adopted in substance. 129-30: rejected as subordinate and unnecessary. 131 (first sentence): adopted or adopted in substance. 131 (remainder)-32: rejected as subordinate and unnecessary. 133 (first sentence): adopted or adopted in substance. 133 (remainder): rejected as subordinate and unnecessary. COPIES FURNISHED: Ben G. Watts, Secretary Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0458 ATTN: Eleanor F. Turner, Mail Station 58 Thornton J. Williams, General Counsel Department of Transportation 562 Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32399-0458 David M. Levin Icard Merrill 2033 Main Street, Suite 600 Sarasota, Florida 34237 Paul Sexton Chief, Administrative Law Department of Transportation Haydon Burns Building, Mail Station 58 605 Suwannee Street Tallahassee, Florida 32399-0458 Francine Ffolkes, Assistant General Counsel Department of Transportation Haydon Burns Building, Mail Station 58 605 Suwannee Street Tallahassee, Florida 32399-0458 Robert E. VanWagoner Post Office Box 4121 Anna Maria, Florida 34216 Christine C. Stretesky, Assistant General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000

Florida Laws (6) 120.57187.101187.201334.044339.155380.27
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. GEORGE MORRISON, 82-001532 (1982)
Division of Administrative Hearings, Florida Number: 82-001532 Latest Update: Jun. 07, 1983

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: At all times pertinent to this proceeding, respondent George W. Morrison was a registered residential contractor holding license number RR 0021945. On April 28, 1979, respondent entered into a contract with T. Joseph Feeney to construct a residence and pool on Sanibel Island "according to plans and specifications approved and signed by both parties" for the sum of $100,200.00. Construction on the residence was begun by respondent in late August, 1979. In January, the Feeneys desired to move into the home because they were having difficulty locating rental property. At that time, construction was not completed and neither a final inspection nor a Certificate of Occupancy had been obtained. Although construction had not yet been completed and respondent advised Mr. Feeney that it would be against the law to move into the house before a Certificate of Occupancy was obtained, Mr. Feeney and his family moved into the house on or about January 12, 1980. During the first week of occupancy, Mr. Feeney noticed that there was a sag in the bearing wall of the kitchen and that the house "swayed considerably." According to Mr. Feeney, after he was advised by Mr. Benson, a structural engineer, to either move out of the house or to "shore the house up, he attempted to contact the respondent. Mr. Feeney could not recall whether this occurred in late January, February or March of 1980. Being unable to contact the respondent, Mr. Feeney found his carpenter, Doug Hale, and explained the problem to him. Hale saw respondent that same day and respondent instructed Hale and his crew to go out to the Feeney residence that afternoon and shore the house up. Mr. Hale did notice a deflection and observed that one span was sagging down a small amount. He observed that the bridging work had been nailed from the top and recalled that the bottom nailing was to be performed after the house had settled. When performing the preventive shoring, Mr. Hale noticed that the bolts had been properly installed with washers. The bolts would have been retightened after the wood had dried and before calling in for a final inspection. Upon learning of the structural deficiencies in the Feeney residence, respondent hired his own structural engineer, Charles Wunder, and took the plans and specifications for the Feeney residence to him. Mr. Wunder found that the original drawings, plans and specifications caused the deflection problem in that the framing members used for the ledger beams were not of sufficient strength to hold up in the area where they were placed. Wonder's remedial plan was to use additional beam supports and steel flitch plates. He so advised the respondent by a letter dated February 12, 1980 and an attached sketch for the remedial work. After receiving Mr. Wunder's plans to remedy the structural defects, respondent ordered the steel plates and had them delivered to the Feeney residence. When respondent went there to perform the work, Mr. Feeney informed him that he wanted the work performed according to Mr. Benson's plans and blueprints. Benson's plans were much more involved and extensive, and respondent did not have the materials available to perform the work. Thereafter, an impasse occurred between Mr. Feeney and the respondent as to the manner in which the structural remedial work should be performed, and respondent was terminated by Mr. Feeney on or about April 13, 1980. Both respondent and his engineer, Mr. Wonder, believed that Mr. Benson's plans were "overdesigned" and massive compared to what needed to be done to make the residence structurally sound. Respondent testified that his engineer's plans for remediation would result in a cost of about $1,000.00. Mr. Feeney testified that he incurred costs of approximately $21,000.00 to have the remediation work performed according to Mr. Benson's plans. There was evidence that at least a portion of this figure was attributable to decorative and swimming pool work, as opposed to structural work. In late February or early March, 1980, after the preventive shoring had been completed by Doug Hale, the Building Official for Sanibel, George E. Blain, inspected the Feeney residence at Mr. Feeney's request. Mr. Blain found that the flooring and joist system had been installed according to the plans and specifications submitted and approved for the building permit. He could not give an opinion as to the cause of the deflection of the beams, but felt that there appeared to be a problem with the construction which could be corrected in the normal construction phase. A violation of the Southern Standard Building Code would occur only if the problem were not corrected at the time of final inspection, and this project had not yet been called up for such final inspection. While Mr. Blain found that some of the bolts were not properly placed or tightened at the time of his inspection, he found nothing to indicate that the required number of nails were not in place. After his inspection, Mrs. Blain wrote a letter to the respondent expressing his opinion that extensive remedial work was necessary to stabilize the floor support system of the Feeney residence. Respondent was instructed to have a registered engineer examine the floor support system and submit a report detailing the requirements necessary for loads stability. This report was to be received by Mr. Blain's office prior to the commencement of any corrective work by the respondent. Mr. Blain never received a response from the respondent to his March 5, 1980 letter. Respondent explained that he did not receive this letter from Mr. Blain until some time near the time that he and Mr. Feeney had reached an impasse situation with regard to the manner in which the remedial work was to be done. He therefore did not respond to Mr. Blain's letter because he did not believe that he would be performing the work.

Recommendation Based upon the findings of fact and conclusions of law recited herein, it is RECOMMENDED that the Administrative Complaint filed against George Morrison on March 8, 1982, be DISMISSED. Respectfully submitted and entered this 10th day of March, 1983, in Tallahassee, Florida. DIANE D. TREMOR, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 10th day of March, 1983. COPIES FURNISHED: John O. Williams, Esquire 547 North Monroe Street (Suite 204) Tallahassee, Florida 32301 Allan T. Griffith, Esquire Griffith & Griffith, P.A. 9150 S. Cleveland Ave. (Suite 1) Ft. Myers, Florida 33907 Mr. Fred Roche Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. James Linnan Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202

Florida Laws (1) 489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer