CONSTRUCTION INDUSTRY LICENSING BOARD vs. CARROLL L. MOZINGO, 77-001095 (1977)
Division of Administrative Hearings, Florida Number: 77-001095 Latest Update: Jan. 20, 1978

The Issue The Florida Construction Industry Licensing Board (Petitioner herein) seeks to revoke Carroll L. Mozingo's (Respondent herein) license to practice as a registered general contractor based on allegations which will be set forth hereinafter in detail that he diverted funds in violation of Chapter 468.112(2)(e), Florida Statutes. Based upon my observation of the witnesses and their demeanor while testifying and the entire record compiled herein, I make the following:

Findings Of Fact The Respondent is a registered general contractor, who holds current license no. RG0015876. On September 7, 1976, Respondent entered into a contract with Robert Johnson and his wife Sandra Johnson for a room addition and patio to their house located at 197 North Roscoe Blvd., Ponte Vedra Beach, Florida. The full amount of the contract plus agreed upon extras amounted to $9,640.00. (Petitioner's Composite Exhibit Number 2) Respondent applied for and obtained a building permit for the construction of the Johnson's addition on or about September 27, 1976, and construction commenced shortly thereafter. (Petitioner's Exhibit Number 1) Donald Jermaine, a St. Johns County field inspector, testified that he conducted inspections on the subject job and noted numerous violations of the St. Johns County Building Code. He coordinated the inspections for this project up until the time it was abandoned by Respondent during mid February, 1977. At the time of abandonment, the owner, Robert Johnson, had paid a total amount of $11,021.96 to Respondent and/or various suppliers. To complete the job as contracted by the parties (Johnson and Mozingo) Messr. Johnson had to pay Proctors Construction Company $2,800.00, an electrical contractor $369.00 and a plumbing contractor $520.00 for a total expenditure over and above the above referenced contract amount of $3,689.00. He testified that no additional work was done to his home. The Respondent testified that he expended $7,458.00 for materials on the Johnson project and was unable to complete it because his mortgage payments were delinquent and he was not receiving any additional monies from Messr. Johnson to fulfill his obligations. He testified that he was unable to work at night and therefore had to seek other employment with another contractor. The above explanation by the Respondent which led to his abandonment of the subject project does not excuse him from his contractual obligations to either fulfill the contract as agreed upon or to seek a renegotiation based on additional costs and/or unexpected circumstances. This was not done nor was any other explanation given as to where the additional monies in excess of $4,000.00 was spent. I therefore conclude that he engaged in a diversion of funds as alleged in the administrative complaint filed by the Petitioner on May 27, 1977. I shall so recommend.

Recommendation Based on the foregoing findings of fact and conclusions of law, I hereby recommend that the Respondent's general contractor's license be suspended for a period of two years. RECOMMENDED this 2nd day of December, 1977, in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings 530 Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry Sinoff, Esquire 1010 Blackstone Building Jacksonville, Florida 32202 C. H. Hoskinson, Chief Investigator Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211 Carroll L. Mozingo 1909 Ed Johnson Drive Jacksonville, Florida 32218 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. DIVISION OF ADMINISTRATIVE HEARINGS, DOCKET NO. 77-1095 CARROLL L. MOZINGO dba CARROLL CONSTRUCTION COMPANY, RG 0015876, 1909 Ed Johnson Drive, Jacksonville, Florida 32218, Respondent. /

Florida Laws (1) 120.57
# 2
BUILDING CODE ADMINISTRATORS AND INSPECTORS BOARD vs LEE MARTIN, 97-004733 (1997)
Division of Administrative Hearings, Florida Filed:Miami, Florida Oct. 14, 1997 Number: 97-004733 Latest Update: Jul. 15, 2004

The Issue The issue presented is whether Respondent is guilty of the allegations contained in the Administrative Complaint filed against him, and, if so, what disciplinary action should be taken against him, if any.

Findings Of Fact At all times material hereto, Respondent has been certified by Petitioner as a building code administrator in the State of Florida. On April 5, 1993, Respondent began his employment with Metropolitan Dade County, Florida, as the permit control division chief in the County's Department of Building & Zoning, now known as the Department of Planning, Development and Regulation. Carlos Bonzon was the head of the County's Department of Building & Zoning and also served as the County's Building Official. The Port of Miami is another department within Metropolitan Dade County. At all times material hereto, Carmen Lunetta was the head of that department. The County desired to expand Terminals 8 and 9 at the Port of Miami to accommodate a Carnival Cruise Lines mega-cruise ship, anticipated to arrive in March 1996. The County was concerned that if it could not offer the taller terminal required for such a large ship, the ship would utilize Port Everglades instead of the Port of Miami. For purposes of construction, Terminals 8 and 9 were "threshold" buildings. A threshold building is one which is of such magnitude or complexity that the construction requires continuous inspections. Those continuous inspections are performed by the on-site "threshold inspector," the engineer of record, who keeps a log of the on-going inspections. The expertise required of a threshold inspector is beyond that of most County field inspectors. When a threshold inspector is involved, the County's inspectors check to make sure the log is being kept up-to-date and on-site. On January 27, 1995, a pre-submittal meeting was attended by representatives of Dade County, of the architect, and of the engineer. Respondent was one of the attendees. The meeting was chaired by Jose Cueto, the "special assistant" to Bonzon. Saul Suarez, the project architect, explained the project, and Cueto advised the attendees that the construction needed to begin even without the County's approval of building plans and the issuance of a permit and that County inspectors would perform "courtesy inspections" to make sure the work was being performed according to the architectural plans. Further, the inspectors were not to stop the construction work although there were no approved plans and no permit. While the South Florida Building Code does not provide for courtesy inspections, it was understood that the courtesy inspections referred to by Cueto were the same as "field visits." In a field visit a County inspector will travel to the job site, observe the construction, and meet with the contractor, engineer, or architect to discuss any concerns they may have. A field visit is not an official inspection required by the South Florida Building Code. Construction work began on Phase I, the foundation for Terminals 8 and 9. By letter dated February 10, 1995, Port Director Lunetta wrote to Building & Zoning Department Director Bonzon, confirming Lunetta's understanding that Bonzon's Department had issued a "conditional permit" for the project, allowing the construction to proceed during the review of construction documents "for the work being performed at this time." By letter dated June 29, 1995, Port Director Lunetta again wrote to Director Bonzon, confirming Lunetta's understanding that Bonzon's Department had issued a "conditional permit" for Phase II of the project, allowing construction to proceed during the review of construction documents "for the work being performed at this time." There is no such permit as a conditional permit under the South Florida Building Code. In July 1995 Cueto conducted a meeting regarding Phase II, the superstructure, which was attended by Respondent and other Building & Zoning Department representatives, the architect, and Port of Miami representatives. Cueto acquainted the attendees with Phase II of the construction and advised that the work would exceed the drawings and approved plans. Cueto outlined the procedures which were set up by Director Bonzon and specified that, in addition to the threshold engineer's inspection, County inspections were to be performed only by the Chief Inspector in each of the trades since the chief inspectors would have the most experience. Cueto also advised that he personally would be in charge of coordinating inspections and plans review as a result of the procedures established by Director Bonzon for the project. As the head of the Department of Building & Zoning and as the County's Building Official, Bonzon had the authority to re-assign duties for the Department's employees. Although Cueto was not certified to review plans and had had no authority over the County's plans review and inspection processes, Respondent and the others attending the January 1995 meeting and the July 1995 meeting understood that Bonzon had delegated to Cueto the responsibilities for ordering inspections and overseeing the processing of the building plans for the project. On July 7, 1995, a building permit was issued for the project. The permit was restricted to "foundation only." Throughout 1995 County inspectors visited the job site. They viewed the construction and verified that the threshold inspection log was on-site and up-to-date. The inspections were not recorded as official inspections because the County's computer would not accept inspection entries before a permit had been issued. The inspectors kept notes regarding their courtesy inspections or field visits. All mandatory inspections under the South Florida Building Code were conducted, both before and after the issuance in July 1995 of the building permit with the restriction limiting construction to foundation only. At the end of 1995 the County re-organized some of its departments, including the Building & Zoning Department. Director Bonzon and his special assistant Jose Cueto were transferred to the transportation department, and Bonzon was no longer the County's Building Official. On January 10, 1996, Respondent was certified by the Secretary of the Dade County Board of Rules and Appeals, subject to approval by the Certification Subcommittee at the January 30, 1996, meeting, to become the County's Building Official. As of that date, Respondent considered himself to have assumed the duties of that office. He did not also become the head of the Department; he remained in his position as Permit Control Division Chief. In either the first or second week of January, Respondent went to the offices of Bonzon and Cueto, who were in the process of moving to their new offices, to say good-by. In Cueto's office, Respondent saw a set of building plans lying on Cueto's window ledge. He asked if those were the plans for Terminals 8 and 9, and Cueto answered in the affirmative. Respondent took the plans and personally delivered them to the Chief Construction Plans Examiner, Frank Quintana. He directed Quintana to do whatever was necessary to expedite the County's review of those plans. Quintana divided the required two sets of plans so two reviewers could be processing them at the same time and personally took them from reviewer to reviewer in order to expedite them as quickly as possible. The expedited review process Respondent directed to occur resulted in the foundation- only restriction being removed from the permit on February 6, 1996. On that date, the construction at Terminals 8 and 9 was 85 to 95 percent complete. Prior to the removal of the foundation-only restriction from the permit on February 6, subcontracting permits for mechanical, electrical, and plumbing work had not been, and could not have been, issued. Respondent immediately reported his discovery of the plans in Cueto's office and his decision to expedite their review to his superiors, Guillermo Olmedillo and Ray Villar. Respondent did not order the construction stopped. He knew that the threshold inspector had been performing on-going inspections, the architect had been regularly on-site, and that County inspectors had been visiting the job site on a regular basis. He also knew that all mandatory inspections had been conducted on schedule. He had no reason to believe that any of the construction was unsafe or that there was any danger to the public as a result of the construction having proceeded without proper permitting. He believed that the work itself was in compliance with the South Florida Building Code. On January 18, 1996, the project architect forwarded to Respondent a request that certain mandatory inspections be made. On January 20, Respondent ordered those inspections to be made. Those were the only inspections which Respondent ordered to be performed. In early March shop drawings were reviewed for a pre- fabricated stairwell. Although the stairs were safe for use by the construction workers, the County reviewer questioned the adequacy of the stairs for use by the public using the terminals. Based upon his concerns, repairs were made to the stairs to strengthen them, and they were subsequently approved as complying with all requirements to insure the public's safety. On March 8, 1996, a temporary certificate of occupancy was issued for Terminals 8 and 9. There was never any danger to the public as a result of the construction of Terminals 8 and 9.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that a final order be entered finding Respondent not guilty and dismissing the Administrative Complaint filed against him in this cause. DONE AND ENTERED this 18th day of December, 1998, in Tallahassee, Leon County, Florida. LINDA M. RIGOT Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 18th day of December, 1998. COPIES FURNISHED: Diane Snell Perera, Esquire Seymour Stern, Esquire Department of Business and Professional Regulation 401 Northwest Second Avenue, Suite N607 Miami, Florida 33128 Gary B. Goldman, Esquire Law Offices of Gary B. Goldman 20700 West Dixie Highway, Suite 100 North Miami Beach, Florida 33180 Lynda L. Goodgame, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Ila Jones, Executive Director Building Code Administrators and Inspectors Board Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (3) 120.569120.57468.621
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs EDUARDO KIRKSEY, 90-007869 (1990)
Division of Administrative Hearings, Florida Filed:Miami, Florida Dec. 14, 1990 Number: 90-007869 Latest Update: Jun. 05, 1992

Findings Of Fact Eduardo Kirksey is licensed as a certified residential contractor, holding license CR C012717. He qualified a corporation known as Modern Construction Company, Inc. (Modern) to engage in contracting.Modern entered into a contract on about July 28, 1986 with Ira Goldstein of 4440 Southwest 32nd Drive, Hollywood, Florida for construction of two-story room addition which would include a family room, bedroom and bath. Modern was to provide the plan by which the addition would be built. A rough sketch of the addition is included on the contract. More specific plans, which are similar to architectural drawings, were thereafter prepared for submission with the building application, which Modern filed with the Broward County Building and Zoning Enforcement Division. The contract was later amended to add a balcony around the second floor of the addition. The plans which are in evidence as Department Exhibit 4 are the second set of plans. According to these plans, the second floor bedroom had a 6" x 6" sliding glass door. The door opened on to a balcony which was created by cantilevered joists consisting of 2" x 10" pieces of lumber bolted to 2" x 12" rafters between the first and second floor. These 2" x 10" members extended out four feet from the building. According to the plans, 2" x 6" decking was to be placed across these joists, and an appropriate railing would then be placed around the balcony. Mr. Kirksey submitted the amended application for the permit and the plan to the Broward County Plan Review Board for approval, and it was approved. After construction began, Mr. Goldstein determined that he did not wish the floor of the balcony to be pressure treated wooden decking. Instead, he wanted a tile floor on the deck. Mr. Kirksey had already filed two sets of plans with Broward County on the project, the first for the addition without the balcony, and the second for the addition with the balcony. He did not want to file a third building permit application which would also require the submission of new drawings. Mr. Kirksey did agree to change the construction to accommodate Mr. Goldstein's desire to tile the balcony but declined to do the tile work himself as part of his contract with Mr. Goldstein. Mr. Goldstein was to arrange for the tiling of the deck. The original design for the decking would have spaced the 2" x 6" lumber which made up the decking with small spaces between each piece of lumber to allow water to fall through during rain. In order to lay tile down, it was necessary to place plywood across the joists, rather than 2" x 6" pressure treated lumber. Before the plywood could be laid, however, Mr. Kirksey had to remove the 2" x 10" cantilevered joists from between the first and second floor, because the original design called for those joists to be level. They were reinstalled at about a 1/2 inch slant so that the water would then drain from the balcony after it had been tiled. In addition, Mr. Kirksey then had to place soffit under the balcony, and put facia around the bottom of the deck. Neither the soffit nor the facia were required in the plans. Although it was more expensive for Mr. Kirksey to add these items, Mr. Goldstein was not charged any additional money for this work. The plywood that was put down over the 2" x 10" rafters instead of the pressure treated 2" x 6" lumber was 3/4 inch exterior grade plywood. Pressure treated plywood was not used because the plywood was to be covered with tile, and if properly tiled, pressure treated plywood is unnecessary. Moreover, even if tile is put over pressure treated plywood, if tile is not laid properly, the pressure treated plywood will rot as well as exterior plywood will rot. It would not have been possible to place tile over the 2" x 6" pressure treated lumber which the amended plan filed with the Broward Building and Zoning Enforcement Division had called for. The 2" x 6" members would shrink and move, causing the tile to crack. Some type of plywood had to be used instead of decking to permit Mr. Goldstein to tile the deck. The 3/4 inch plywood which Mr. Kirksey used met or exceeded the standards established by the South Florida Building Code. No sealant, or paint, was applied to the plywood, nor was the deck covered with visquine. Preparation of the plywood before the tile was placed over it would be the job of the person doing the tile work. An inspector from the Broward County Building and Zoning Enforcement Division visited the site on a number of occasions. During the course of those inspections some of the work was originally rejected by the inspector. For example, the balcony railing pickets had a spacing greater than 5 inches and the top of the rail was only 36 inches high, not 42 inches high. As a result of this rejection, the picket spacing and railing were changed. Ultimately, the inspector gave final approval after having seen the plywood deck, even though no new plans had been submitted to change the deck to have a plywood floor for tile rather than the originally permitted 2" X 6" pressure treated lumber deck. When the job was completed by Modern it was in the condition a project would normally have been left where the contractor was not responsible for laying the tile over the balcony floor. Because the floor was to be tiled, there was no reason for Mr. Kirksey to have painted the balcony floor. In addition, the contract did not require that any painting be done. Mr. Goldstein did the tile work on the deck himself although he had no prior experience in laying tile. Mr. Goldstein spoke with one of Modern's workmen about how to lay tile. This was an informal conversation, and Mr. Kirksey, the contractor, never advised Mr. Goldstein on how to lay tile. I do not accept the testimony of Mr. Goldstein that the employee of Modern who explained to him how to lay tile was the job foreman. Nothing in the contract with Modern required Modern to lay tile, or to advise Mr. Goldstein how to lay tile, so whether the person who discussed laying tile with Mr. Goldstein was a foreman is not significant. Sometime after all the work had been completed by both Modern and Mr. Goldstein, Mr. Goldstein's daughter Evette stepped out onto the balcony, and her foot and leg went through the balcony. This occurred because the plywood had not been sealed or protected before the tile was laid by Mr. Goldstein. As a consequence, the plywood had rotted under the tile. The rot also extended to the supporting joists. Broward County has adopted and incorporated into the Broward County Charter, Chapter 71-575, Laws of Florida, a Special Act of the Legislature. Both adopt for Broward County the "South Florida Building Code, Dade County 1970 edition, as amended." The Department included with its proposed recommended order portions of the South Florida Building Code, 1986 Broward County edition, for the purpose of demonstrating that the conduct of Mr. Kirksey violated Section 301(a) and 302.1(e) of that 1986 code. As a matter of evidence, the 1986 Broward County edition of the Southern Florida Building Code does not appear to apply. The Department's exhibit 7, which is "a copy of the Broward ordinance which adopts the South Florida Building Code" (Tr. 6) shows that it is the South Florida Building Code, Dade County 1970 edition which applies in Broward County. No portion of that document has been offered in the record of this case. As a consequence, there is no record evidence that Mr. Kirksey has violated a portion of an applicable code. It is true that Mr. Joseph Montagnino testified that Section 301(a) of the South Florida Building Code would not permit a change in a plan once it had been approved (Tr. 22, 104). In a case such as this, however, it is necessary for the Department to produce the text of the applicable building code, which has been adopted either by State statute or local ordinance. It cannot prove a violation through the testimony of a witness who merely characterizes his recollection of the text of an authoritative code. Moreover, other witnesses who are experts in construction trades in Broward County testified that it is common for inspectors to approve changes such as that made by Mr. Kirksey here, at the request of Mr. Goldstein, to substitute plywood flooring for pressure treated decking, without the need for amended plans or permits. (Tr. 75-77, 88- 89). Without evidence of the text of the applicable code, it is not possible to determine whether these experts, or Mr. Montagnino are correct. Since Mr. Goldstein, the homeowner, intended to do the tile work, it would not have been Mr. Kirksey's responsibility to pull additional permits for the tile work. At most, Mr. Kirksey's duty might have been to have obtained approval of amended plans, showing the slight pitch of the joists supporting the balcony floor, and the substitution of plywood and tile for 2" X 6" pressure treated lumber as the flooring for the balcony. Mr. Kirksey is in no way responsible for the inadequate preparation of the plywood surface for the application of the tile. Mr. Kirksey is in no way responsible for informal advice given by an employee of Modern, whose identity cannot be determined from the evidence in this case, to Mr. Goldstein about the proper way to prepare the plywood deck for tiling. Tiling was not part of the construction contract which Mr. Goldstein entered into with Mr. Kirksey's company. Mr. Kirksey is therefore not liable for inadequate supervision of employees on the job. Mr. Kirksey's employees performed the work required under the agreement which Modern had with Mr. Goldstein, as the parties amended it after the construction began.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that a Final Order be entered by the Board finding Eduardo Kirksey not guilty of the violations set out in Counts I, II or III of the Administrative Complaint. RECOMMENDED this 24th day of December, 1991, at Tallahassee, Florida. WILLIAM R. DORSEY, JR. Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of December, 1991.

Florida Laws (3) 120.57489.105489.129
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DAVID L. NORRIS, 88-000275 (1988)
Division of Administrative Hearings, Florida Number: 88-000275 Latest Update: Sep. 30, 1988

Findings Of Fact The foregoing findings of fact 1, 2, and 3 are incorporated herein by reference as if fully set forth anew. On January 8, 1987, the Respondent was found guilty of violating Sections 489.129(2), 489.129(3), and 489.129(1)(g) Florida Statutes, by the Construction Industry Licensing Board in DPR Case No. 60987, DOAH Case No. 88- 0002. The Respondent was not present at that Board meeting. He asserted this was due to lack of timely notice of the Board's meeting. Respondent was fined $1,000 by the Final Order of the aforementioned Board filed/served on February 20, 1987. The Respondent has failed to pay the fine. Respondent has not appealed the final order or fine. Respondent expressed himself at formal hearing as intending never to pay the lawfully imposed fine.

Conclusions The foregoing Conclusion of Law 14 is adopted and incorporated herein as if fully set forth anew. Respondent is charged with gross negligence, incompetence or misconduct in the practice of contracting pursuant to Section 489.129(1)(m), Florida Statutes, for failure to pay his $1,000 fine pursuant to the Board's February 20, 1987 final order. However, Petitioner has cited no statutory or rule authority which labels a licensee's refusal to pay a fine or obey a final order of the Construction Industry Licensing Board as gross negligence, incompetence, or misconduct in the practice of contracting. (Emphasis supplied, see definition of "contracting" at Section 489.105, Florida Statutes). Without such authority, the factual allegations of the administrative complaint, although proved, support no conclusion that a statute or rule has been violated. Petitioner's recourse lies not in this forum but in enforcement, execution, and collection actions in Circuit court.

Recommendation Upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that: The Construction Industry Licensing Board enter its final order dismissing the charge of a violation of Section 489.129(1)(m). DONE and RECOMMENDED this 30th day of September, 1988, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of September, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NOS. 88-0275, 88-0732 The following constitute rulings pursuant to Section 120.59(2), Florida Statutes, upon the parties' respective Proposed Findings of Fact (PFOF). DOAH CASE NO. 88-0275 Petitioner's PFOF have been accepted with certain modifications for greater clarity and to conform to the record as a whole. Respondent's Closing Statement is accepted in part in FOF 9. The remainder is rejected as mere argument or as based upon hearsay not properly in the record. DOAH CASE NO. 88-0732 Petitioner's PFOF have been accepted with certain modifications for greater clarity and to conform to the record as a whole. Respondent's Closing Statement is mere legal argument addressing the underlying facts of the previous final order finding Respondent guilty of certain violations and assessing a $1,000 fine. Absent a timely appeal, these matters are immaterial and rejected. These proposals are also rejected as mere argument. COPIES FURNISHED: Fred Seely, Executive Director Construction industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 G. W. Harrell, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 David L. Norris 3144 Northwest 39th Court Lauderdale Lakes, Florida 33309 Bruce D. Lamb, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (4) 120.57489.105489.119489.129
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. LEONARDO SANCHEZ, 88-003445 (1988)
Division of Administrative Hearings, Florida Number: 88-003445 Latest Update: Dec. 29, 1988

The Issue At the commencement of formal hearing, Petitioner voluntarily dismissed Paragraphs 5 and 7 of the pending Administrative Complaint, and the formal hearing proceeded upon Paragraphs 1-4 and 6 of the Administrative Complaint. The Department of Professional Regulation prosecuted Respondent for one count of the following enumerated alleged violations: Sections 489.129(1)(d), willful or deliberate disregard of building codes; (j), failure in any respect to comply with the Act; (m), fraud, deceit, or gross negligence; and 489.105(4), Florida Statutes, all of which arise out of a single incident.

Findings Of Fact At all times material to the Administrative Complaint, Respondent, Leonardo Sanchez, was licensed by the State of Florida as a certified general contractor holding license numbers CG C004810 and CG CA04810. Robert G. Wolf, Investigator Specialist II with Petitioner, investigated a complaint made by Mirta Garcia against a contractor named Leonardo Sanchez. Ms. Garcia told him she had entered into a contract with a Mr. Sanchez; that she had paid Sanchez a sum of money for an addition to her house; that Sanchez never supplied her a written contract; and that Sanchez pulled a permit for the work and never completed it. Ms. Garcia did not appear and testify at formal hearing and her representations to Mr. Wolf are mere hearsay. They do, however, supplement or explain other competent proof. Mr. Wolf spoke with a Mr. Sanchez who, in Mr. Wolf's words "acknowledged the contractual relationship with the Garcias." (TR-15) Mr. Wolf visited Ms. Garcia's home and determined that a job of construction had been begun there but that interior work had yet to be completed. John Delaney is Assistant Chief Code Enforcement Officer for the Board of Rules and Appeals for the Building and Zoning Department, Dade County. He also visited the Garcia home and on August 18, 1987 it was approximately 80 per cent complete, in his opinion. He presented as a certified business record, a building permit application for an owner "Mirta Garcia" by "Caribean Window" [sic] applied for in the name of Leonardo Sanchez, dated "accepted 12/9/85," and carrying the contractor number CGC004810 and the social security number 109-42- 4859 (P-2). The contractor number and social security number on the application match Respondent's contractor's license and social security number. "Caribbean Window" is one of the entities for which Respondent is the registered qualifying agent. Dade County Ordinance 57-22 establishes that the South Florida Building Code was in effect in Dade County at all times material to this Administrative Complaint. Section 305.2(a) of the South Florida Building Code establishes a mandatory duty for the permit holder to obtain a reinforcing inspection. Mr. Delaney also presented a certified computer printout of a Building Inspection log or record (P-3) showing that no one, including Respondent, had obtained the required reinforcing inspection related to the Garcia job as of the date of the computer inquiry. The computer printout reflects the dates of other inspections and the date and number of the application to which it pertains; it does not clarify when Mr. Delaney made his computer inquiry but a reasonable inference is that it was made the date of his visit to the Garcia home, August 18, 1987. No reason was presented to excuse Respondent as permit holder from obtaining the appropriate inspection.

Recommendation Upon the foregoing findings of fact and conclusions of law, it is recommended that the Construction Industry Licensing Board enter a Final Order finding Respondent guilty of violating Section 489.129(1)(d), assessing an administrative fine therefor of $250.00, and dismissing the remaining charges. DONE and RECOMMENDED this 29th day of December, 1988, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of December, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 88-3445 The following constitute specific rulings upon the parties' respective proposed findings of fact (PFOF) pursuant to Section 120.59(2), Florida Statutes. Petitioner's PFOF 1-7 are accepted as modified to reflect the evidence of record. Respondent's PFOF Respondent submitted no proposals. COPIES FURNISHED: Fred Seely, Executive Director Construction Industry Licensing Board Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 G. W. Harrell, Esquire, and Donald Osterhouse, Qualified Representative Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Leonardo Sanchez 12700 Southwest 37 Street Miami, Florida 33175 Bruce D. Lamb, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750

Florida Laws (3) 120.57489.105489.129
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOSE R. GARCIA, D/B/A GABROS CONSTRUCTION, 76-000410 (1976)
Division of Administrative Hearings, Florida Number: 76-000410 Latest Update: Jun. 03, 1977

The Issue Whether Jose Ramone Garcia obtained a building permit for the purpose of aiding an uncertified or unregistered person to evade the provisions of Part 2, Chapter 468, Florida Statutes.

Findings Of Fact Jose Ramone Garcia holds a license as a general contractor issued by the Florida Construction Industry Licensing Board and is licensed as doing business as Gabros Construction. Jose Ramone Garcia, on or about April 26, 1974, obtained a building permit No. 74-1006 issued by Collier County Building Department to build a home at 378 Seabee Avenue, Vanderbilt Beach, Florida. The home at 378 Seabee Avenue, Vanderbilt Beach, Florida, was built by Roger Dulaney, an unlicensed person, who had contracted verbally to build said home with Mr. William E. Young, the owner of the real property. Jose Ramone Garcia obtained the building permit No. 74-1006 with money given to him by Roger Dulaney, but Jose Ramone Garcia did not receive any compensation for his assistance to Roger Dulaney. Jose Ramone Garcia did not contract with William E. Young to build the home at 378 Seabee Avenue, Vanderbilt Beach, Florida. Jose Ramone Garcia did not contract with any of the subcontractors or materialmen for services or goods used in the construction of the home at 378 Seabee Avenue, Vanderbilt Beach, Florida. Jose Ramone Garcia was frequently at the construction site at 378 Seabee Avenue and did oversee the construction which Dulaney directed. Garcia did insure that all construction work done was in accordance with the specifications and plans and the building code of Collier County. All work on the home at 378 Seabee Avenue was inspected and approved by the building authorities of Collier County. With several minor adjustments, the construction was acceptable to the owners. The major problem involved with the house constructed at 378 Seabee Avenue involved the contract price of the home arrived at between Dulaney and Young. Garcia did not negotiate the contract of the construction of the house at 378 Seabee Avenue and had no knowledge of the contract price. The dispute between Dulaney and Young resulted in court action between these parties which resulted in a judgment by the court in the favor of Dulaney. Jose Ramone Garcia has been unable to obtain a building permit as a contractor in Collier County since the filing of the Administrative Complaint in January, 1976. Garcia currently resides in Collier County.

Recommendation Because the licensing privilege of Garcia has already been effectively suspended for 14 months, which is a substantial period of suspension, the Hearing Officer does not feel that a further suspension would be of any benefit. The Hearing Officer would recommend that a civil penalty of $500 be assessed against Garcia based upon the foregoing findings of fact and conclusions of law. DONE and ORDERED this 29th day of March, 1977, in Tallahassee, Florida. STEPHEN F. DEAN Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry S. Sinoff, Esquire Jacobs, Sinoff, Edwards, Alford & Burgess Post Office Drawer I Fernandina Beach, Florida 32034 Jose Ramone Garcia 9341 S. W. 38th Street Miami, Florida J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211

# 8
STEVEN L. JOHNS vs DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD, 99-004164F (1999)
Division of Administrative Hearings, Florida Filed:Miami, Florida Oct. 01, 1999 Number: 99-004164F Latest Update: Jan. 08, 2001

The Issue Whether pursuant to Sections 57.111 or 120.595(1), Florida Statutes, Petitioner Rafael R. Palacios (Palacios) should be awarded reasonable costs and attorney's fees incurred in defense of an administrative proceeding against him that was initiated by the Respondent, Department of Business and Professional Regulation (Department). Whether pursuant to Section 120.595(1), Florida Statutes, Petitioner Steven L. Johns (Johns) should be awarded reasonable costs and attorney's fees incurred in defense of an administrative proceeding against him that was initiated by Respondent.

Findings Of Fact Petitioner, Steven L. Johns, is a Florida Certified General Contractor and the principal qualifier for C. G. Chase Construction Company (Chase Construction). In 1994, Chase Construction entered into a construction contract with Carnival Cruise Lines for an expansion project at the Port of Miami. Chase Construction subcontracted the mechanical work to R. Palacios & Company. Petitioner, Rafael R. Palacios, is the president, primary qualifier, and 100 percent stockholder of R. Palacios & Company. Palacios' principal place of business is located in Miami, Florida. In July and December 1998, Palacios employed less than 25 employees and had a net worth of less than $2,000,000. The contract for the Port of Miami project consisted of two phases. Phase I was to construct an arrival lobby and an enclosed walkway to a terminal. Phase II included the addition of boarding halls, the renovation of an existing elevated area, and the addition of baggage areas. A foundation permit had been pulled for Phase I. The foundation work was quickly completed, and Chase Construction representatives advised both the Port of Miami and Carnival Cruise Lines that they could go no further without a permit. Work stopped for a short period of time. In June 1995, a Representative from the Port of Miami called Chase Construction and told them to go to the Dade County Building and Zoning Department (Building Department) the next day to meet with Port of Miami officials, the architect, and building and zoning officials. Johns sent Dave Whelpley, who was a project manager and officer of Chase Construction. Palacios did not attend the meeting. Dr. Carlos Bonzon (Bonzon) was the director and building official of Dade County's Building Department during the majority of the construction activities at the Port of Miami by Chase Construction. As the building official, Dr. Bonzon gave verbal authorization for the work on the project to proceed above the foundation without a written permit. Inspections were to be done by the chief inspectors for Dade County. After the meeting with the Building Department officials in June 1995, Johns understood that authorization had been given by the building official to proceed with construction without a written permit. Work did proceed and inspections were made on the work completed. The Dade County Building Code Compliance Office (BBCO) had the responsibility to oversee Dade County's Building Department. In early 1996, an officer of the BBCO accompanied a building inspector during an inspection of the Port of Miami project. It came to the attention of the BBCO officer that no written permit had been issued for the project. The BBCO officer notified the chief of code compliance for Dade County. A written permit was issued for Phase II of the Port of Miami Project on February 6, 1996, at which time approximately 80 percent of the work had been completed. On the same date, Chase Construction issued a memorandum to its subcontractors to secure the necessary permits. Shortly after the permits were issued, an article appeared in the Miami Herald concerning the project and the lack of written permits. Respondent, Department of Business and Professional Regulation (Department) became aware of the situation as a result of the newspaper article and began an investigation. Diane Perera (Perera), an attorney employed by the Department since 1993 to prosecute construction-related professional license law violations, played a major role in determining and carrying out the Department's subsequent actions regarding the Port of Miami project and persons licensed by the Department who had been involved in the project. The Department opened investigations against eight Department licensees. Those licensees included two building officials, Bonzon, and Lee Martin; four contractors, Johns, Palacios, Douglas L. Orr, and D. Jack Maxwell; one engineer, Ramon Donnell; and one architect, Willy A. Bermello. By Administrative Complaint prepared by Perera and filed on September 9, 1997, before the Building Code Administrators and Inspectors Board (BCAIB), the Department charged Bonzon with various violations of Part XIII of Chapter 486, Florida Statutes, for having allowed above-grade construction on the project to proceed in the absence of approved plans and building permits. In conjunction with the Bonzon case, Charles Danger (Danger), a licensed professional engineer and Director of BBCO testified in a deposition that above-grade construction of the project had proceeded without a building permit and without approved plans in violation of Chapter 3, Section 301 of the South Florida Building Code. He also testified that Bonzon had exceeded his authority under the South Florida Building Code by authorizing the above-grade construction and that the contractors who performed the work did so in violation of the South Florida Building Code. The Department's charges against Bonzon were resolved through a settlement agreement, whereby Bonzon agreed to relinquish his building code administrator's license. A final order of the BCAIB accepting the settlement agreement was filed on July 2, 1998. In the settlement agreement, Bonzon specifically agreed that his interpretation of the South Florida Building Code provisions, including portions of Section 301, was erroneous. On June 24, 1998, the Department presented the Department's Case Number 97-17322 involving Johns to the Division I Probable Cause Panel (PCP) of the Construction Industry Licensing Board (CILB). The panel members on this date were Gene Simmons and Wayne Beigle. Stuart Wilson-Patton and Leland McCharen, assistant attorneys general, were present to provide legal advise to the PCP. The prosecuting attorney presenting the case to the panel was Perera. The Department was requesting a finding of probable cause against Johns for a violation of Section 489.129(1)(d), Florida Statutes, for knowingly violating the applicable building code by performing above-grade construction work on the Port of Miami project in the absence of approved plans and specifications. Prior to the meeting of the Division I PCP of the CILB, Perera had furnished the two panel members documentary evidence pertaining to the case, copies of which were received in evidence at the final hearing as Respondent's Exhibits 5 and 13, with the exception of a letter dated July 31, 1998, from Petitioners' attorney, Renee Alsobrook. Respondent's Exhibit 5 consisted of materials taken from the Bonzon and Lee Martin cases, including the transcript of the December 22, 1997, deposition of Charles Danger, who was the building officer for the BBCO from 1991 to 1998. Respondent's Exhibit 13 was the investigative file for the Johns' case. The Division I PCP discussed Johns' case and voted to request additional information regarding whether any fast track ordinance existed in Dade County, and if so, how it might have applied to the Port of Miami project. On June 24, 1998, the Division II PCP of the CILB met and discussed the Palacios case, which was designated as the Department's Case No. 97-17313. The members of the panel were James Barge and Richard Cowart. Mr. Wilson-Patton and Mr. McCharen were present to provide legal advise to the PCP. The prosecuting attorney presenting the case to the PCP was Perera. The Department was requesting a finding of probable cause against Palacios for violating Section 489.129(1)(d), Florida Statutes, by knowingly violating the applicable building code by performing above-grade construction work on the Port of Miami project in the absence of approved plans and a building permit. Prior to the Division II PCP meeting, the panel members were provided with materials which were received in evidence at the final hearing as Respondent's Exhibits 5 and 14, with the exception of letters dated July 31 and August 26, 1998, from Renee Alsobrook. Respondent's Exhibit 14 is the Department's investigative file on the Palacios case. Following a discussion of the Palacios case, one of the panel members made a motion not to find probable cause. The motion died for lack of a second, and the panel took no further action on the case that day. Pursuant to Section 455.225(4), Florida Statutes, the case was treated as one in which the PCP failed to make a determination regarding the existence of probable cause and was presented to Hank Osborne, Deputy Secretary of the Department, to make a determination whether probable cause existed. On July 2, 1998, Deputy Secretary Osborne found probable cause, and the Department filed an Administrative Complaint against Palacios, charging a violation of Section 489.129(1)(d), Florida Statutes. The Department never served Palacios with the Administrative Complaint filed on July 2, 1998. The Department did not notify Palacios that the Administrative Complaint had been filed and did not prosecute the Administrative Complaint. At the time the Administrative Complaint was filed, the Department believed that the Legislature was in the process of enacting legislation to repeal Section 489.129(1)(d), Florida Statutes. Chapter 98-419, Laws of Florida, which became law on June 17, 1998, repealed Section 489.129(1)(d), Florida Statutes, effective October 1, 1998. Because of the repeal and the lack of a savings clause for pending cases, the Department determined that as of October 1, 1998, the Department did not have authority to take disciplinary action based on a violation of Section 489.129(1)(d), Florida Statutes. On December 18, 1998, the Department presented the Department's Case Nos. 97-17133 and 97-1732 to the PCPs for a second time with a recommendation to find probable cause that Johns and Palacios had violated Section 489.129(1)(p), Florida Statutes, for proceeding on any job without obtaining applicable local building permits and inspections. Mr. McCharen was present to provide legal advice to the PCPs. Ms. Perera was also present during the meetings of the PCPs. Documentary materials presented to the PCP considering Palacios' case included the materials on the Bonzon and Martin cases which had been previously presented to the PCP panel in June 1998 and the investigative files on Palacios. The investigative file included letters with attachments from Palacios' attorney Rene Alsobrook concerning the materials contained in the Bonzon and Martin cases as they related to Palacios and the investigative file on Palacios. Additionally, the investigative file contained a report from Frank Abbott, a general contractor who had been asked by the Department to review the file on Palacios. Mr. Abbott concluded that Palacios had violated several provisions of Chapters 489 and 455, Florida Statutes, including Section 489.129(p), Florida Statutes. The PCPs found probable cause in the Johns and Palacios cases. On December 23, 1998, the Department filed administrative complaints against Palacios and Johns alleging violations of Section 489.129(1)(p), Florida Statutes. The cases were forwarded to the Division of Administrative Hearings for assignment to an administrative law judge. Palacios and Johns claimed that they were relying on the authorization from Bonzon when they proceeded on the above-grade construction work. No formal administrative hearing was held on the administrative complaints filed on December 23, 1998. On December 18, 1998, a Recommended Order was issued in the related case against Lee Martin, Department Case No. 97-11278, finding that Mr. Martin, the building official who replaced Bonzon and assumed responsibility for the Port of Miami project, had the discretion to allow the remaining construction to proceed while taking action to expedite the plans processsing. A Final Order was entered by the Department dismissing all charges against Mr. Martin. On February 26, 1999, Petitioners Palacios' and Johns' Motions to Dismiss and Respondent's responses were filed. The Motions to Dismiss did not request attorney's fees or costs and did not reference Section 120.595(1), Florida Statutes. The motions did contain the following language: The DBPR has acted in an improper and malicious manner by precluding the Respondent from asserting his response to the second draft Administrative Complaint and requesting the Panel to find probable cause for reasons other than whether there was probable cause to believe the Respondent violated specific disciplinary violations. On March 19, 1999, the cases were consolidated and noticed for hearing on May 12-13, 1999. Section 489.129, Florida Statutes, was amended during the 1999 legislative session to provide: A contractor does not commit a violation of this subsection when the contractor relies on a building code interpretation rendered by a building official or person authorized by s. 553.80 to enforce the building code, absent a finding of fraud or deceit in the practice of contracting, or gross negligence, repeated negligence, or negligence resulting in a significant danger to life or property on the part of the building official, in a proceeding under chapter 120. . . . On April 15, 1999, the Department filed a Motion for Leave to Revisit Probable Cause Panel and to Hold in Abeyance. On April 20, 1999, Petitioners filed a response, stating they did not object to the granting of the motion to hold in abeyance. The final hearing was cancelled, and the cases were placed in abeyance. On May 24, 1999, the Department submitted a Status Report, stating that the cases would be placed on the next regularly scheduled PCP meeting scheduled for June 16, 1999. By order dated May 25, 1999, the cases were continued in abeyance. On July 1, 1999, Palacios and Johns filed a Status Report, indicating that the cases would be presented to the PCPs sometime in July and requesting the cases be continued in abeyance for an additional 30 days in order for the parties to resolve the issues. On July 30, 1999, Palacios and Johns filed a Status Report, stating that the cases were orally dismissed on July 28, 1999, and that a hearing involving issues of disputed facts was no longer required. Based on Johns' and Palacios' status report, the files of the Division of Administrative Hearings were closed by order dated August 3, 1999. No motion for attorney's fees and costs was filed during the pendency of the cases at the Division of Administrative Hearings. On August 3, 1999, orders were entered by Cathleen E. O'Dowd, Lead Attorney, dismissing the cases against Palacios and Johns.

Florida Laws (9) 120.569120.57120.595120.68455.225489.129553.8057.10557.111
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. PHILLIP H. BARE, D/B/A AMERICAN GENERAL CORPORATION, 78-000593 (1978)
Division of Administrative Hearings, Florida Number: 78-000593 Latest Update: Jun. 29, 1979

The Issue Whether Respondent's registration as a general contractor should be suspended or revoked, or the respondent otherwise disciplined, for alleged violations of Sections 468.112 (2)(a), (2)(g), and (2)(h), Florida Statutes, as set forth in the Administrative Complaint.

Findings Of Fact Petitioner Phillip H. Bare, Ocala, Florida, is registered with Respondent as a general contractor under the provisions of Chapter 468, Florida Statutes, and was so registered throughout the year of 1977. He operates under the name of American General Corporation of Florida, but that firm has not been qualified to engage in the contracting business in Florida, pursuant to Section 468.107, Florida Statutes. (Petitioner's Exhibits 1, 2, Stipulation, Testimony of Cherry) On August 15, 1977, Respondent, as president of American General Corporation of Florida, entered into a Home Improvement Installment Contract and Note with Joe Wheeler and wife, who reside at Route 2, Box 63, Live Oak, Florida. The contract provided that for a price of $4,250 Respondent would make the following property improvements on the Wheeler residence: Build 12 X 20 Room Addition and finish with paneling, ceiling tile, & all trim. Build 6 X 14 porch with top. Replace all Rotten sills. Replace all Rotten siding. Paint house with latex paint. Repair floor joist. The Wheelers made a down payment of $350 leaving an unpaid balance of $3,900. The promissory note provided for a total financed cost of $6,629.28 payable in monthly payments over a period of seven years. On August 29, 1977, the parties entered into another such contract for additional work to the residence for the price of $1,600 as follows: Install ceiling tile in (2) bed rooms and bathroom complete with trim. Install paneling in (2) bed rooms complete. Install paneling and tile board in bath. Remove old shingles and install new 235lb asphalt shingles. Install 54" kitchen sink complete and hook to water. The Wheelers paid $100 as a down payment on the work and financed the remainder with a total deferred price of $2,100 payable in 48 consecutive monthly installments. (Petitioner's Exhibits 5, 6, Testimony of E. Wheeler, J. Wheeler) Respondent subcontracted the work on the Wheeler residence to one John Compton. Respondent did not secure a Suwannee County Building Permit for the work, nor was he licensed in that county to act in the capacity of a contractor. (Testimony of Respondent, Wilson) On September 12, 1977, Mr. Wheeler signed a Customer's Completion Certificate" wherein he acknowledged that the contract work had been satisfactorily completed. Although Respondent testified that he explained the contents of the document to Wheeler at the time it was executed, Wheeler denied the same and testified that he had not read its contents prior to signing it. (Testimony of Respondent, J. Wheeler, Respondent's Exhibit 1) Prior to completion of the work, the Wheelers noted that certain deficiencies in the work existed, including a floor that "shaked" in the new addition, looseness of wall paneling, failure to replace rotten siding and lower sills, and failure to install ceiling tile in one bedroom. They spoke to workmen on the job who said that they would return and finish the work. However, nothing further was done in spite of the fact that Respondent told Mrs. Wheeler in a telephone conversation that he would be back to complete the job. As a result, Mrs. Wheeler made a complaint to Derl W. Wilson, the building official for Suwannee County. (Testimony of E. Wheeler, J. Wheeler, Wilson) Pursuant to Mrs. Wheeler's complaint, Wilson inspected the premises at some time during the month of September, 1977, and observed that the accomplished work was of a substandard nature involving various violations of the Southern Standard Building Code which had been adopted by Suwannee County in 1975. These violations, which Respondent acknowledged at the hearing to have been committed, included the following: concrete foundation blocks improperly aligned and unsupported by required concrete pad; improper spacing of floor joists at 24 inch rather required 16 inch intervals; use of one-ply instead of two-ply flooring material; failure to extend vent stack for plumbing system in kitchen to a height of 6 inches above the roof line; failure to provide a shutoff valve for cold water line under kitchen sink; failure to cover and protect splices in wiring of ceiling light fixture; failure to install ridge board for support of roof rafters; improperly installing two inch by four inch wood braces in attic; failure to connect sewer line to septic tank. Additionally, Wilson observed various instances of poor workmanship in installation of an electric wall receptacle and connection of the roof of the new addition to the existing building. Further, he noted that due to the improper spacing of floor joists, the substandard plywood flooring was not firm and constituted a safety hazard. (Testimony of Wilson, Petitioner's Composite Exhibit 3) After his inspection, Wilson wrote a letter to Respondent, dated October 18, 1977, pointing out the deficiencies in construction and advising that a complaint would be filed against him unless a building permit was obtained within ten days and the necessary corrections of deficiencies were made. Although Wilson testified that he did not hear from Respondent as a result of the letter, Respondent made several telephone calls to Wilson's office and was informed that he was on vacation. (Testimony of Wilson, Respondent, Respondent's Exhibit 7) On June 14, 1978, Respondent entered a plea of guilty in the County Court of Suwannee County, Florida to a charge of improper construction arising out of the Wheeler contract, and the Court withheld adjudication of guilt in the matter. (Petitioner's Exhibit 9) Respondent was previously convicted in the County Court of Putnam County, Florida, on August 13, 1974 of engaging in the business or acting in capacity of a contractor without being duly registered in the county pursuant to Section 468.105(2), Florida Statutes. On June 16, 1975, Respondent pleaded nolo contendere in the County Court of Alachua County, Florida to a charge arising out of his activities as a home improvement contractor. The Court withheld adjudication of guilt and placed the Respondent on probation for a period of six months and required that he "make necessary repairs to home of victim to satisfaction of Consumer Protection Section of State Attorney's Office, Eighth Judicial Circuit." (Petitioner's Exhibits 7-9) Petitioner has been a building contractor for twelve years. He testified that his subcontractor for the Wheeler job had been competent in the past and he relied on this fact in not closely inspecting the work under the Wheeler contracts. For this reason, he was unaware that the building code violations had occurred until after he had sold the Wheeler contracts and mortgages to a third party who was contacted by the Wheelers regarding the deficiencies. Respondent denied that he abandoned the work because he thought it had been completed until subsequent notification of the Wheeler complaint. He has since made attempts through Counsel to resolve the complaint by having the work performed by a contractor licensed in Suwannee County or by means of a monetary settlement. He further testified that he had inquired of Petitioner's office as to the necessity for obtaining a Suwannee County license prior to commencing the Wheeler contracts and was informed that his registration was valid for work in that county. He acknowledged that he made a "mistake" in not obtaining a building permit and in failing to supervise his subcontractor properly, but stated that the licensing rules in the various counties were "confusing." As to his prior difficulties in Putnam and Alachua Counties, Respondent testified that the Alachua matter involved a complaint raised four or five years after construction regarding quality of workmanship and that he had taken care of the matter. As to the Putnam County case, he testified that he was unaware that a building permit was necessary at the time he did the work for which he was subsequently prosecuted. It is found that Respondent's exculpatory testimony regarding his failure to obtain a building permit or county licensing, and lack of knowledge of code violations with respect to the work performed at the Wheeler residence is not credible. (Testimony of Respondent, Respondent's Exhibits 2-6)

Recommendation That Respondent's registration as a general contractor be suspended for a period of one year and that an administrative penalty in the amount of $500 be imposed, for violation of Section 468.112(2)(a), Florida Statutes. DONE and ENTERED this 23rd day of March, 1979, in Tallahassee, Florida. THOMAS C. OLDHAM Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of March, 1979. COPIES FURNISHED: Barry Sinoff, Esquire 2400 Independent Square Jacksonville, Florida 32202 C. Valentine Bates, Esquire 726 NW 8th Avenue - Suite B Gainesville, Florida J. K. Linnan, Executive Director Florida Construction Industry Licensing Board Post Office Box 8621