CONSTRUCTION INDUSTRY LICENSING BOARD vs. GEORGE SOLER, 84-002529 (1984)
Division of Administrative Hearings, Florida Number: 84-002529 Latest Update: Feb. 06, 1986

Findings Of Fact At all times material to this proceeding Respondent was a registered building contractor in the State of Florida having been issued license number RB 0009164. At no time material to this proceeding was Domingo Alonzo (a/k/a Domingo Alonzo) registered, certified or otherwise licensed by the Florida Construction Industry Licensing Board. Respondent and Alonzo signed and submitted a proposal to Myron M. Gold and Roberta Fox for remodeling and additions to their residence located at 1550 Zuleta Avenue, Coral Gables, Florida in accordance with plans prepared by Frese - Camner Associates on file with the City of Coral Gables, Florida, File No. 2897 for a contract price of $65,940.00 with draw schedules attached. On December 6, 1982, Myron M. Gold and Roberta Fox (Homeowners) accepted the Proposal (Contract). On December 6, 1982, the Homeowners paid Respondent and Alonzo jointly $3,297.00 in accordance with the contract whereby they were to receive 5 percent of the contract amount as a down payment upon signing. The draw schedule provided for a 10 percent retainage from each draw which was to be paid to Respondent and Alonzo upon completion and the issuance of a certificate of occupancy. On December 21, 1982 the Homeowners paid Respondent and Alonzo jointly $2,025.00 which represented a draw on Schedule I - Item 3 for $1,350.00, Schedule II - Item 2 for $360.00 and Item 5 for $315.00. On December 17, 1982 the Homeowners and Respondent filed the affidavit required by ordinance with the City of Coral Gables for the purpose of having a building permit issued covering the work under the contract. 9. On January 19, 1983 Respondent using his building contractors license applied for building permit to cover the work anticipated under the contract and on the same day was issued building permit, No. 28214. Under the contract the Homeowners were to pay for the building permit and the bond required by the city. On January 26, 1983 the Homeowners paid Respondent and Alonzo jointly $3,000.00 which along with a payment on January 27, 1983 of $500.00 and January 31, 1983 of $544.60 represented a draw on Schedule I - Item 2 for $405.00, Item 5 for $1,260.00, Item 6 for $1,547.10 and Item 13 for $832.50. All payments from December 6, 1982 through January 31, 1983 under the contract by the Homeowners totaled $9,366.50 and were paid jointly to Respondent and Alonzo. On February 4, 1983 Respondent and Alonzo entered into an agreement, prepared by Myron Gold in the law office of Gold and Fox, whereby the Homeowners were to pay the balance of the funds remaining under the contract to Alonzo individually. After this date all payments were made to Alonzo. It was the Homeowners understanding after the February 3, 1983 agreement that Respondent would still be responsible for the supervision of the construction although they never saw Respondent again until October 1983. Edward Borysiewicz testified that he dealt with Respondent during March 1983 when he made the floor slab inspection on March 3, 1983 and the columns inspection on March 14, 1983. The record is clear that shortly after the agreement on February 3, 1983 Respondent no longer came to the construction site and supervised the work of Alonzo. On February 8, 1983 the Homeowners paid Alonzo $3,060.00 which represented a draw on Schedule I - Item 1 for $810.00, Item 5 for $1,417.50 and Item 13 for $832.50. On February 28, 1983 the Homeowners paid Alonzo $3,155.40 which represented a draw on Schedule I - Item 4 for $1,705.50 and $729.90 for extras apparently not covered by the contract but whether the balance of check No. 1161 (Pet. Ex. 13) of $720.00 was for payment under the contract or for extras is not shown in Petitioner's Exhibit No. 15. On March 18, 1983 the Homeowners paid Alonzo $1,000 which represented a draw on Schedule I - Item 9 for $819.00. Again whether the balance of check No. 1206 (Petitioner's Exhibit No. 13) of $181.00 is for payment under the contract or for extras is not shown in Petitioner's Exhibit No. 15. On March 21, 1983, the Homeowners paid Alonzo $6,400.00 which represented a draw on Schedule I - Items 10, 11, 12, 14 and 15. On March 21, 1983 the Homeowners paid Alonzo $2,166.90 but Petitioner's Exhibit No. 15 does not list check No. 1210 as being a payment under the contract or for extras. On March 31, 1983 the Homeowners paid Alonzo $4,230.00 which represents a draw under Schedule I - Item 7 for $2,520.00 and a payment for extras not covered under the contract in the amount of $1,710.00. On April 21, 1983 the Homeowners paid Alonzo $5,207.40 which represented a draw Schedule I - Items 1, 5, 6, 9 and 14. On June 24, 1983 the Homeowners paid Alonzo $5,788.00 which represented a draw on Schedule I - Item 12 for $667.00, Item 14 for $3,024.00 and payment for extras not under contract for $2,097.00. After March 14, 1983 Respondent was not seen on the job site and there was no longer any apparent supervision of Alonzo by Respondent. After Respondent left the job site there was no licensed building contractor involved in the construction. After Respondent left the construction site the Homeowners soon realized that Alonzo did not know how to proceed with the work and experienced problems with the pace and manner in which the work was being accomplished. On July, 1983, Alonzo stopped working altogether. Although the Homeowners were aware of the problems that Alonzo was having with the construction and that Respondent was not on the job, the record does not reflect that they ever attempted to contact Respondent after the meeting on February 3, 1983. On August 1, 1983 the Homeowners notified Respondent and Alonzo that the contract had been terminated. The Homeowners paid Respondent and Alonzo $42,174.20 total under the contract (pages 1-5, Petitioner's Exhibit No. 15) and paid Alonzo $10,766.37 for extras (Pages 6- 10, Petitioner's Exhibit No. 15). On August 31, 1983 the Homeowners paid Edward Bryant, plastering contractor the sum of $3,100.00 for plastering performed by Edward Bryant. This was for work under the contract that had not been completed or work necessary to correct problems that were already completed. Roberta Fox testified that there were no extras on plaster, however, page 7, line 11 and page 9, line 21 of Petitioner's Exhibit 15 indicates that there was extra plastering. On August 29, 1983 and September 29, 1983 the Homeowners paid Southwest Plumbing Services, Inc. the total amount of $4,875.00 for work contemplated under the contract that had not been completed or needed correction. Homeowners had paid Alonzo $3,591.00 for plumbing under the contract. Both Alonzo and Southwest Plumbing, Inc. were paid for extra plumbing not covered by the contract in the amount of $567.00 and $391.50, respectively by the Homeowners. From September 13, 1983 through June 13, 1984 the Homeowners paid Charles Brueg, Jim Brueg, Charles Buffington and Dan, Inc. the total amount of $4,192.91 for electrical work contemplated under the contract that was not completed or required correction after Alonzo left the construction site. Page 6 lines 6 and 11 of Petitioner's Exhibit No. 15 indicate that there were extras not covered by the contract. The total amount for electricity contemplated by the contract was $3,649.00. Alonzo was paid $2,627.10 under the contract and $1,710.00 for extras. The Homeowners were required to obtain the services of an air conditioning contractor to complete the work contemplated under the contract after Alonzo left the job site and as a result were required to pay Cameron, Inc., the air conditioning contract the amount of $5,181.60 between August 16, 1983 and January 24, 1984. The total amount contemplated under the contract was $3,600.00 of which $1,134.00 had been paid to Alonzo. Debris was dumped in the swimming pool requiring the Homeowners to pay $7,000 to refurbish the swimming pool. This amount included the repair contemplated under the contract and the extra work caused by Alonzo. The contract contemplated $2,300.00 for repairs of which none had been paid to Respondent or Alonzo. The Homeowners paid $1,150.00 to a painting contractor to finish the painting contemplated under the contract. Alonzo had been paid $1,125.00 for painting. (Petitioner's Exhibit No. 15) The contract provided $2,500.00 for all painting required under the contract. Respondent failed to notify the building department that he was no longer responsible for the construction. After the Homeowners terminated the contract due to Respondent's and Alonzo's nonperformance, the Homeowners had to expend a substantial amount of extra money to complete the construction. The evidence is insufficient to determine an exact or approximate amount. Roberta Fox's testimony was conflicting with regard to her understanding as to whether or not the Respondent would continue to supervise the construction after the meeting in the Homeowners' law office on February 3, 1983 when Respondent and Alonzo entered into this agreement. Myron Gold testified that it was his understanding that Respondent would continue to supervise Alonzo after the agreement. However, the Homeowners action in this regard subsequent to February 3, 1983, in making no effort to bring the matter to a "head" and requiring Respondent to supervise the work or terminate the contract and in continuing to deal with Alonzo although Homeowners were aware shortly after February 3, 1983 that Alonzo could not perform without Respondent's supervision and that they knew Respondent was not on the job, tends to show that they were aware or should have been aware that Respondent was no longer involved in the day to day supervision of the construction. Alonzo installed a fireplace pursuant to the contract that the building department determined to be a fire hazard and recommended against its use. The Homeowners applied for and were granted a "owner/builder" permit on September 1, 1983 and requested cancellation of the building permit issued to Respondent which was cancelled on September 6, 1983. They have not received a certificate of occupancy because the building department has not performed the following inspection: electrical final; plumbing final; air conditioning final; roofing final and public works final. The building department would have issued a "stop-work order" had it been aware that Respondent was not supervising the construction and would have required the Homeowners to obtain another licensed building contractor or proceed as a owner/builder. The plans prepared by Frese-Camner Associates that were made a part of the contract by reference were not introduced into evidence with the contract and thus the record is insufficient to determine what was required to meet the specifications of the plans and thereby determine if the specifications had been met. There was a permit issued for the septic tank and drain field which work was started in December, 1982. The construction of the house itself was started in January 1983. The first inspection (foundation) on the house was made by the building department of January 21, 1983.

Recommendation Based on the findings of fact and conclusions of law recited herein, it is Recommended that the Board enter a final order finding Respondent guilty of violating Section 489.129(1)(h)(k)(m), Florida Statutes (1981) and for such violations it is Recommended that the Board assess the Respondent with an administrative fine of $500.00 and suspend the Respondent's contracting license for a period of three (3) years, provided, however, that if Respondent submits to the Board competent and substantial evidence of restitution to Myron Gold and Roberta Fox within one (1) year from the date of the final order herein, then the suspension shall be stayed and Respondent placed on probation for the balance of the suspension. Respectfully submitted and entered this 6th day of February, 1986, in Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 6th day of February, 1986. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 84-2529 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the parties to this case. RULINGS ON PROPOSED FINDINGS OF FACT SUBMITTED BY THE PETITIONER: Adopted in Finding of Fact 1. Adopted in Finding of Fact 2. Adopted in Finding of Fact 3 but clarified. Adopted in Findings of Fact 4 and 5. Adopted in Finding of Fact 4. Adopted in Finding of Fact 6. Adopted in Finding of Fact 5. Adopted in Finding of Fact 9. Adopted in Finding of Fact 9. Adopted in Finding of Fact 9. Adopted in Finding of Fact 9. Adopted in Finding of Fact 10. Adopted in Finding of Fact 11. Adopted in Finding of Fact 12 except clarified as to the last date on construction site. Adopted in Finding of Fact 13. Adopted in Finding of Fact 14 but clarified. Adopted in Finding of Fact 15 but clarified. Adopted in Finding of Fact 16. Adopted in Finding of Fact 17 but clarified. Adopted in Finding of Fact 15 but clarified. Adopted in Finding of Fact 19. Adopted in Finding of Fact 20 but clarified. Adopted in Finding of Fact 21. Adopted in Finding of Fact 11. Adopted in Finding of Fact 21. Adopted in Finding of Fact 22. Adopted in Findings of Fact 22 and 23. Adopted in Finding of Fact24 but clarified to show correct amount paid under contract as indicated by Petitioner's Exhibit 15. Adopted in Finding of Fact 25 but clarified to show that extra plastering not under contract was required. Adopted in Finding of Fact 26. Adopted in Finding of Fact 26. Adopted in Finding of Fact 26. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 27. Adopted in Finding of Fact 28. Adopted in Finding of Fact 28. Adopted in Finding of Fact 28. Adopted in Finding of Fact 28. Adopted in Finding of Fact 29 but clarified. Adopted in Finding of Fact 30 but clarified. Rejected as immaterial. Rejected as not supported by competent substantial evidence. Rejected as not supported by substantial competent evidence. Adopted in Finding of Fact 31. Rejected as immaterial. Adopted in Finding of Fact 32 but clarified to show that the record does not support a figure that approximate $32,000.00. Rejected as not supported by substantial competent evidence even though the Homeowners' testimony supported this fact because the Homeowners' actions with regard to Respondent after February 3, 1983, was to the contrary. Adopted in Finding of Fact 33. Adopted in Finding of Fact 34. Adopted in Finding of Fact 34. Adopted in Finding of Fact 34. Adopted in Finding of Fact 35. Adopted in Finding of Fact 36. Adopted in Finding of Fact 36. RULINGS ON PROPOSED FINDINGS OF FACT SUBMITTED BY RESPONDENT: No Findings of Fact was submitted by the Respondent. COPIES FURNISHED: James Linnan, Executive Director Department of Professional Regulation Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Salvatore A. Carpino, General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 W. Douglas Beason Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. George J. Soler, Pro Se 3315 S.W. 96th Avenue Miami, Florida 33165

Florida Laws (6) 120.57155.40489.105489.113489.127489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs. PRESTON MADDOX, 87-000213 (1987)
Division of Administrative Hearings, Florida Number: 87-000213 Latest Update: Jun. 19, 1987

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: At all times material to this proceeding, Respondent was licensed as a registered general contractor by the State of Florida, Construction Industry Licensing Board, having been issued license number RG 0014645. Respondent's address is 2533 Green Road, Tallahassee, Florida 32308. On or about October 30, 1985, Willie McFarland (McFarland) contracted with Virgil Fleming (Fleming) to perform certain improvements to Fleming's home located at 9008 Broken Lance, Tallahassee, Florida. The contract price was $24,600.00. There was no contract between Fleming and Respondent. Fleming paid McFarland $16,500.00 of the contract price. Most of this money was paid in advance of work being performed. MoFarland was not, at any time material to this proceeding, a licensed contractor in the State of Florida and both Fleming and Respondent knew that he was not a licensed contractor. McFarland was not authorized to pull a permit to complete the work and Fleming, upon finding this out, started to pull the permit as a homeowner but changed his mind. Respondent agreed to pull, and did pull, the permit for this job, after checking on McFarland and with the understanding that he would have to be involved with McFarland on the job. Without the permit, McFarland could not have continued with the job. Fleming did not pay any money to Respondent for pulling the permit or for anything else and there was no evidence that McFarland paid any money to Respondent for pulling the permit or anything else. McFarland partially completed the work contracted for with Fleming. The Respondent went to the job site on several occasions but was unable to make contact with McFarland. Respondent did make contact with McFarland on one (1) occasion after he had pulled the permit and obtained some promises from McFarland concerning the job but McFarland did not "live up" to those promises. There was credible testimony from Respondent that McFarland was not an employee of Respondent's business but that one of the conditions for pulling the permit required McFarland to be an employee of Respondent only on this job. Respondent had no knowledge of the financial arrangements between McFarland and Fleming until after the permit was pulled and McFarland had "skipped." The parties have been unable to locate McFarland.

Florida Laws (2) 120.57489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DAVID H. HAMILTON, 79-000018 (1979)
Division of Administrative Hearings, Florida Number: 79-000018 Latest Update: Apr. 28, 1980

Findings Of Fact At all times pertinent to these proceedings, Hamilton held registered residential contractors license number RR0015037. Hamilton agreed to construct a house in Clearmont, Florida, with a completion date no later than May 1, 1977, for Robert J. and Margaret M. Phlepsen. The construction price was $75,000.00. After construction of the house it was discovered that there existed two violations of the Southern Building Code. First, the "step-down" from the kitchen to the garage was an eleven inch riser contrary to the code requirement that the height of a riser shall not exceed seven and three quarters inches. The second violation occurred through the use of 2 X 8 joists where the code would require 2 X 10 joists. The extra high riser between the kitchen and the garage was apparently caused by an oversight. Hamilton merely failed to install an intermediate step at that location. The second violation occurred because the owner and Hamilton agreed to use the smaller joists in order to save money on the contract price. In neither case is there sufficient evidence to establish that Hamilton's violations were willful or deliberate as alleged in the Administrative Complaint. On June 6, 1978, the Lake County Board of Examiners suspended Hamilton's Lake County Certificate of Competency because of violations of building code requirements in the construction of Phlepsen's house.

# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. GEORGE E. FELD, 86-004429 (1986)
Division of Administrative Hearings, Florida Number: 86-004429 Latest Update: Apr. 09, 1987

Findings Of Fact At all times relevant hereto, respondent, George E. Feld, held certified general contractor license number CG C021801 issued by petitioner, Department of Professional Regulation, Florida Construction Industry Licensing Board. Feld has been a licensed contractor in Florida since June 1982. He has qualified George E. Feld and Associates, Inc. under his license and operates the business at 2131 Northeast 205th Street, North Miami Beach, Florida. After submitting the low bid, on or about March 1, 1985 George Feld and Associates, Inc. entered into a contract with the City of Tamarac to construct a 5,500 square foot recreation building for the City. The negotiated contract price was $195,950. The contract called for commencement of the project within ten days after the contract was signed and completion by July 27, 1985. Sometime prior to March 20, 1985, Feld met one David P. McCall and Marvin Weiss at a motel in North Miami. McCall was interested in doing work on the Tamarac project. He gave Feld a business card with the name "Arrow Head Development Corporation, Inc." printed on it, and which stated the firm was "state certified" and "licensed" as a general contractor. Feld also noted that Weiss held a general contractor's license, and he assumed that McCall and Weiss were working together. Relying on McCall's card, and later representations by McCall, but without checking with petitioner's office to verify if McCall or Arrow Head were licensed or qualified, Feld agreed to subcontract out the shell and sewer work on the Tamarac project to Arrow Head. To this end, Feld and Arrow Head entered into two contracts on March 20, 1985, for Arrow Head to perform the shell and sewer work. On June 21, 1985 McCall submitted a written "proposal" to Feld for the shell work on the job. The proposal had the following words and numbers typed on its face: "State License Number: #CGC 05961." It was not disclosed whose license number this was. Although McCall denied typing this document (because he does not personally know how to type), he did not deny that it was placed on the document at his direction or with his knowledge. It was not until sometime later that Feld learned that Arrow Head was not qualified by any licensee. Because of his mistaken belief that Arrow Head was qualified, Feld had never qualified that firm. Even so, there was no evidence that Feld intended to allow an unqualified firm to perform the work. Work proceeded on a timely basis as required by the contract. Feld visited the job site daily, and supervised all activities, including those performed by McCall. He routinely inspected the work, verified that it was being done according to specifications, and made corrections where needed. The job specifications called for trusses that were over forty feet in length. Because of this, and pursuant to the South Florida Building Code (Code), it was necessary for the City to hire an engineer to oversee their installation. The City hired one George Fink as engineer to supervise this phase of the project. However, Fink's responsibility was limited to just that, and once the installation was completed, Feld resumed responsibility for the remainder of the job. Trusses are a manufactured roof member and may vary in length, height and pitch. In this case, they were designed in the form of a cathedral roof, and were in excess of forty-seven feet in length. Further, because of the building's design, there were a number of trusses to be installed. The installation of the trusses was begun around 9:00 a.m. on Friday, June 27, 1985 and finished by 2:00 p.m. that same day. As required by the Code, Fink was present and supervised the installation of the trusses on the top of the shell. He confirmed at hearing that they were properly installed. The problem herein arose early that day when Fink had noticed that the building plans did not provide for lateral bracing of the trusses. However, according to Fink, this was not unusual since plans do not normally provide for lateral bracing. Even so, Fink told an unnamed person who "appeared to be the fellow running the erection crew" that lateral bracing should be added to the center and two side core members and that the four trusses on each end needed additional bracing. Fink also suggested to this unnamed individual that sheathing be added "as soon as possible" to the top and outside of the trusses to give added stability and protect them from wind damage and the like. In this regard, at hearing Fink conceded that it was "reasonable" for a contractor to erect trusses one day, and to place sheathing on them the following work day. Fink thought sheathing to be particularly necessary on this job since the trusses were high pitched," "long in length," and there were "no gables or anything in between to ... add any other support." By the end of the work day, the crew had placed the proper bracing on the trusses. However, no sheathing was applied. According to Fink, who was accepted as an expert in this proceeding, a prudent and competent contractor would be aware of the need for sheathing and added bracing because of the potential hazard of high winds caused by late afternoon thunderstorms in South Florida. By failing to place sheathing on the roof, Fink opined that Feld was grossly negligent and incompetent in the practice of construction on the Tamarac project. Sometime on late Sunday night or early Monday morning, most of the trusses on the roof collapsed. Some fell on an electrical wire running to the building. However, no injuries occurred. Only five trusses on the north side of the building remained in place. The City of Tamarac then filed a complaint with petitioner against Feld. The cause of the collapse was not disclosed, and even Fink was unable to state that the lack of sheathing was the cause of the accident. There was no evidence that strong winds or thunderstorms occurred on the night the trusses fell, or that bad weather was predicted when the work day ended on Friday afternoon. Feld acknowledged that no sheathing was placed on the trusses. He attributed this to the fact that the construction crew stopped work at 3:30 on Friday afternoon, and did not return to the job site until the following Monday morning. He intended to install the sheathing the following Monday but by then it was too late. This was in accord with the standard enunciated by Fink that it was not unreasonable for a contractor to erect trusses one day, and to place sheathing on them the following work day. Feld also stated that he was well aware of the need for bracing and sheathing on trusses by virtue of his long experience in the construction business. Feld hinted, but did not prove, that McCall may have been responsible for the accident because of bad blood between the two. In any event, he doubted that wind would have caused the trusses in question to fall. Finally, Feld pointed out that, even though city inspectors were present, no one had come to him on Friday afternoon and said the trusses might collapse over the weekend without sheathing. Feld is a graduate of the University of Buenos Aires with a degree in architecture, and has been engaged in the construction/architecture business for twenty-two years. He presently is an instructor of construction at Miami-Dade Community College. There is no evidence he has ever been the subject of a disciplinary action by the Board on any other occasion.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the administrative complaint against George E. Feld be DISMISSED, with prejudice. DONE AND ORDERED this 9th day of April, 1987, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of April, 1987.

Florida Laws (2) 120.57489.129
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOHN W. FARRALL, 89-003291 (1989)
Division of Administrative Hearings, Florida Number: 89-003291 Latest Update: Feb. 15, 1990

Findings Of Fact At all times material to these proceedings, Respondent Farrall was licensed as a certified general contractor in Florida, and held license number CG C040234. In addition, the Respondent was licensed as a certified roofing contractor and held license number CC C024398. Mr. Farrall was the qualifying agent for Sunmaster Roofing Company. On May 25, 1987, Sunmaster Roofing Company entered into a contract with Clarence A. Miller and Emily Miller to reroof their residence in Naples, Florida. After the project was completed, Mr. and Mr. Miller filed a complaint with the Collier County Contractors' Licensing Board on December 7, 1987. Essentially, the complaint alleged as follows: 1) that the contractor abandoned the job without adequately completing construction; 2) that the roof materials were incorrectly installed; 3) that the contractor failed to obtain a building permit; and 4) that the contractor failed to adequately perform the contract due to his failure to correct faulty workmanship on the job. On December 11, 1987, copies of the complaint and a notice of hearing was sent to Respondent Farrall by certified mail to two different addresses. The items were promptly received at both locations. On January 15, 1988, the Respondent acknowledged that he was personally aware of the hearing scheduled for January 20, 1988. The Respondent requested a continuance until after January 29, 1988, because he had to attend to urgent family matters which required his presence in Canada. A continuance was not granted, and the hearing proceeded as scheduled. The Respondent was aware that the hearing was not continued prior to his departure for Canada. On January 20, 1988, a hearing was held, and the local board received evidence regarding the Miller complaint. As a result of the hearing, the local board found that the Respondent violated specific county ordinances in the following manner: by abandoning the job without legal excuse; disregarding or violating the building code by failing to obtain a building permit; and by failing to make good, faulty workmanship obviously performed in evasion of performance of the contract. The Respondent was disciplined by the Collier County Contractors' Licensing Board on January 20, 1988. His permit privileges were suspended in Collier County until the contractor makes restitution and appears before the Board for reinstatement. The Respondent was given fifteen days to appeal the decision. The Respondent personally received a copy of the disposition of the hearing by certified mail on January 28, 1988. An appeal was not taken of the decision.

Recommendation Based upon the foregoing, it is recommended that the charges set forth in the Administrative Complaint against the Respondent, John W. Farrall, in Case No. 89-3291 be DISMISSED. RECOMMENDED this 15th day of February, 1990, in Tallahassee, Leon County, Florida. VERONICA E. DONNELLY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 15th day of February, 1990. APPENDIX TO RECOMMENDED ORDER, CASE NO. 89-3291 The proposed findings of fact set forth in Petitioner's proposed recommended order are addressed as follows: 1. Accepted. See HO #1. 2. Accepted. See HO #2. 3. Accepted. See HO #1 and #2 4. Accepted. See HO #8 and #9. 5. Accepted. See HO #8. Rejected. Irrelevant to the charges filed. Rejected. Irrelevant to the charges filed. The proposed findings of fact filed by the Respondent are addressed as follows: Accept the first two sentences. See HO #1. The rest of paragraph 1 is rejected as improper argument which is not based upon material evidence presented at hearing. Accepted. See HO #2. Rejected. The issue in this proceeding involves the discipline by the local government board and not the underlying facts upon which the board based its findings. Immaterial. 4. Rejected. Immaterial. See above. Rejected. Rejected. Rejected. Irrelevant. Irrelevant. Irrelevant. Rejected. Rejected. Irrelevant. Irrelevant. Rejected. Rejected. Rejected. Irrelevant. Irrelevant. Contrary to fact. See HO #6. Rejected. Rejected. Contrary to Irrelevant. fact. See HO #9. COPIES FURNISHED: Jack M. Larkin, Esquire 806 Jackson Street Tampa, Florida 33602 John W. Farrall 316-2 Tudor Drive Cape Coral, Florida 33904 Fred Seely, Executive Director Construction Industry Licensing Board 111 East Coastline Drive, Room 504 Jacksonville, Florida 32202 Kenneth E. Easley, Esquire General Counsel Department of Professional Regulation 1940 North Monroe, Suite 60 Tallahassee, Florida 32399-0792

Florida Laws (2) 120.57489.129
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. THURSTON L. BATES, 79-002175 (1979)
Division of Administrative Hearings, Florida Number: 79-002175 Latest Update: Mar. 26, 1981

Findings Of Fact At all times relevant to this proceeding, the Respondent was licensed as a contractor by the Florida Construction Industry Licensing Board. His license for the 1979-1981 license period had not been renewed at the time that the hearing was conducted, and he was therefore delinquent. [This finding is determined from Petitioner's Exhibit 1.] During June, 1977, the Respondent entered Into a contract with Emily D. Wohanka and Ruby Sue Dennard. Ms. Wohanka and Ms. Dennard, who are sisters, agreed to purchase a lot in Satellite Beach, Florida, and the Respondent agreed to construct a single-family dwelling on the lot. The parties agreed to an addendum to the contract during July or August, 1977. The addendum included some specifics with respect to construction and provided: Home will be complete and ready for occupancy within a reasonable period of time--normally three to five months. [This finding is determined from Petitioner's Exhibits 8 and 9, and the testimony of Wohanka and Jordan.) The lot which Ms. Wohanka and Ms. Dennard purchased was not cleared until December, 1977. No progress on construction was made during January or February, 1980. The Respondent obtained a building permit from the City of Satellite Beach, Florida, on February 20, 1978. Construction work commenced in either March or April, 1978. By June, 1978, Ms. Wohanka became concerned that work was commencing too slowly. She told the Respondent that she needed to move in by the end of July. Respondent told her that it was probable that construction would not be completed until mid-August. By September, the project was still not completed. Ms. Wohanka tried to reach Respondent by telephone, but he would not return her calls. She tried to locate him at home, but no one would answer the door. She complained to the building official in the City of Satellite Beach, but the building official had similar problems reaching the Respondent. Ms. Wohanka also complained to N. M. Jordan, the real estate agent who had negotiated the contract. Ms. Jordan was able to locate the Respondent, and the Respondent told Ms. Jordan that he could not complete the project because he was losing money. In late September or early October, Ms. Wohanka and her sister located the Respondent at his home. The Respondent was just walking out of the front door when they arrived. The Respondent told them that he could not discuss the matter, that he had turned it over to Ms. Jordan, and that he was not a part of it anymore. [This finding is determined from Petitioner's Exhibits 2 and 3; and from the testimony of Wobanka, Hijort, and Jordan.] When Ms. Wohanka contacted the Respondent in late September or early October, no work had been done on the project for at least a month, and the house was not completed. Light fixtures, appliances, and air conditioning had not been installed. Cabinets and other fixtures were stored in a bathroom. Inside doors had not been installed. Flooring was not completed. No sidewalks or concrete driveway had been constructed. There had been no landscaping or sodding, and the sprinkler system had not been installed. The plumbing was not operational. Ms. Wohanka contracted with a new builder to complete the project. She was able to move into the residence on December 28, 1978, but work was not finally completed until late January, 1979. Additional expenses beyond those agreed to by the Respondent were incurred by Ms. Wohanka. The Respondent had drawn on a construction loan; but, there is no evidence in the record that the Respondent used these funds for any purposes other than the construction of the dwelling. [This finding is determined from the testimony of Wohanka.] During July, 1977, the Respondent entered into a contract with James and Eleanor A. Lawrence. The Lawrences agreed to purchase a lot in Satellite Beach, Florida, and the Respondent agreed to construct a duplex dwelling on the lot. The Respondent obtained a building permit from the City of Satellite Beach on February 22, 1978. Unknown problems developed, and the project was not being completed. The Satellite Beach building official had difficulty locating the Respondent, but he was ultimately assured by the Respondent that the project would be completed. The Respondent told the realtor who negotiated the contract, Ms. Jordan, that he could not complete the 3 reject because he was losing money. The Lawrences did not testify at the hearing, and specifics regarding their relationship with the Respondent are not known. It is not known whether the Respondent abandoned the project uncompleted without notifying the Lawrences, or whether some agreement was made between them regarding completion of the project. There is no evidenced that the Respondent diverted any funds from the project. [This finding is determined from the testimony of Hjort and Jordan.] No building codes from the City of Satellite Beach were received into evidence. There is no evidence in the record from which it could be concluded that the Respondent violated any provisions of the building codes in either the Wohanka or Lawrence transactions.

Florida Laws (2) 120.57489.129
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. RICHARD A. VALDES, 79-000956 (1979)
Division of Administrative Hearings, Florida Number: 79-000956 Latest Update: May 19, 1980

The Issue Whether Respondent, a certified general contractor, is guilty of pulling permits for construction projects not supervised by Respondent, and, if so, the appropriate disciplinary action which should be taken by the Board.

Findings Of Fact At all times material hereto, Respondent was the holder of Certified General Contractor's License No. CG C005204 issued by the Board. Although this license was active at the time the Administrative Complaint was filed, Respondent has placed it on an inactive status until June 30, 1981. (Stipulation, Testimony of Respondent) As to Amiguet Construction Project During 1976, Jose Amiguet entered into a contract with San Pedro Construction Inc. for the construction of an addition to his existing residence located at 1409 Granada Boulevard, Coral Gables, Florida. (Stipulation, Petitioner's Exhibit 1) Since San Pedro Construction Inc. was not properly licensed as a building contractor, it was not qualified to apply for and obtain a Coral Gables building permit to undertake this residential addition. Therefore, on January 12, 1977, pursuant to an agreement with Jose San Pedro, representative of San Pedro Construction Inc., the Respondent applied and obtained the required Coral Gables building permit under his on name. (Stipulation, Testimony of Respondent, Charles Kozak, Petitioner's Exhibit 1) The Respondent did not participate in, manage, or supervise, in any manner, the construction of the Amiguet residential addition by San Pedro Construction Inc. Jose Amiguet neither knew the Respondent, nor had any dealings with him during the construction work. (Stipulation, Testimony of Respondent) Final inspection of the Amiguet construction project has not been conducted by the Coral Gables building inspection department since the required documentation concerning sidewalk improvements and subcontractors used has not yet been submitted. The actual construction work has, however, been completed, to the satisfaction of Jose Amiguet. (Testimony of Charles Kozak, Respondent) Respondent made an effort to assist Jose Amiguet in obtaining the final inspection and clearance by the city building inspection department. However, since Respondent did not supervise the subcontractors' work, he cannot truthfully complete the required documents. He has, therefore, offered to (1) pay for the additional costs associated with obtaining the necessary final inspection, and (2) transfer to Jose Amiguet the right to receive, after final inspection, the refund of the contractor's performance bond in the amount of approximately $400-$500. (Testimony of Respondent) As to the Shaw Construction Project During July, 1977, and on February 8, 1978, James L. Shaw entered into separate contracts with San Pedro Construction Inc. for the construction of residential improvements at 836 Obispo Avenue, Coral Gables, Florida. The final contract was in the amount of $16,700.00. (Stipulation, Testimony of Respondent, James L. Shaw, Petitioner's Exhibit 4) Since San Pedro Construction Inc. was an unlicensed contractor, Respondent, on November 15, 1977, pursuant to an agreement with that company, applied for and obtained the required Coral Gables building permit. (Stipulation, Testimony of Respondent, James L. Shaw, Petitioner's Exhibit 4) The Respondent did not participate in, manage, or supervise in any manner the construction of the Shaw residential improvements by San Pedro Construction Inc. James Shaw neither knew Respondent, nor had any dealings with him during the construction work. (Stipulation, Testimony of Respondent) On or about April, 1978, the lending institution for the Shaw project, and James Shaw stopped making construction payments to San Pedro Construction Inc., due to its failure to proceed on and abandonment of the project. (Testimony of James Shaw, Charles Kozak) On June 20, 1978, James Shaw obtained an "owner-builder" permit from the City of Coral Gables and incurred the following costs in order to complete the construction project as originally planned: $12,000 for labor and materials, and $625.00 for architectural services. Inasmuch as approximately, $10,128.00 had earlier been paid to San Pedro Construction Inc. for the construction project, the total cost of the project to James Shaw was approximately $22,753.00-$6,053.00 in excess of the original contract price. (Testimony of James Shaw and Respondent) San Pedro Construction Inc. is no longer in business, and the whereabouts of its owner, Jose San Pedro, is unknown. (Testimony of Respondent) As with the Amiguet construction project, final inspection of the Shaw project cannot be conducted until missing documentation relative to sidewalk improvements and subcontractors involved is supplied. In an effort to assist James Shaw, the Respondent has offered to transfer to Shaw the right to receive, after final inspection, the refund of the contractor's performance bond in the amount of approximately $400-$500. (Testimony of Charles Kozak and Respondent) At all times material hereto, the Respondent was aware that it was unlawful, under both state law and the Code of Metropolitan Dade County, to aide an unlicensed contractor in evading the contractor licensing law, and to use one's license to pull permits for projects not supervised by the licensee. (Stipulation, Testimony of Respondent, Petitioner's Exhibit 1) The Metro Dade Construction Trades Board heard the complaint against the Respondent and found prima facie evidence and probable cause to refer the matter to the Florida Construction Industry Licensing Board (Stipulation) Notwithstanding the evidence presented, the Administrative Complaint and the Board's counsel at hearing limited the amount sought for restitution purposes to $5,300.00, provided both the performance bonds are refunded to the benefit of Jose Amiguet and James Shaw. (Administrative Complaint, statement of Board's Counsel) Respondent regrets having taken the actions complained of in the Board's Administrative Complaint, and now more fully understands the resulting burdens which have been placed on Jose Amiguet and James Shaw. (Testimony of Respondent)

Recommendation Guilty, as charged. Respondent's certified general contractor's license should be suspended until such time as full restitution is made to the persons damaged by his actions.

Florida Laws (2) 120.57489.129
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. STEVEN E. SHIELDS, 82-001342 (1982)
Division of Administrative Hearings, Florida Number: 82-001342 Latest Update: Dec. 02, 1983

Findings Of Fact The Respondent is licensed as a general contractor in the State of Florida and registered with the Florida Construction Industry Licensing Board. That agency is the agency charged with regulating the practice of contracting in the State of Florida and with monitoring the compliance of licensees with the various provisions of Chapter 489, Florida Statutes, and pertinent rules relating to licensure standards and practice standards of contractors. On April 23, 1980, one Terry Burch and Jim Goodman were operating a construction business under the fictitious name of "T. J. Associates." Neither Terry Burch or Jim Goodman, nor the entity known as T. J. Associates, was qualified or licensed with the Florida Construction Industry Licensing Board at that time, nor at times subsequent thereto which are pertinent to this proceeding. On April 23, 1980, T. J. Associates entered into a written contract with homeowners Florence Martin and her husband to remodel their home at 120 Broadview Avenue, Winter Park, Florida. The original contract was for $26,615.00 with various addenda to that contract, such that the total net contract price, with modifications, ultimately reached $40,597.00. Both the contract and the modification agreements were signed by the Martins and Terry Burch of T. J. Associates. The Respondent, Steven Shields, was not a party to any of these agreements. Mr. Burch and Mr. Goodman of T. J. Associates, obtained the Martin contract entirely through their own efforts and after obtaining the signed contract, approached the Respondent, Steven Shields, to ask him to draft blueprints for the job, also proposing that the three of them enter into some sort of partnership or other business arrangement. During the meeting at which this business was discussed, it was revealed to the Respondent that T. J. Associates was unlicensed with the Florida Construction Industry Licensing Board and the three men agreed that they would obtain proper application documents from the Board's office in Orlando for filing so as to properly qualify the company. In the meantime, the Respondent agreed to obtain from the City of Winter Park Building Department, the necessary building permits and did so. The Respondent was ultimately paid $600.00 by T. J. Associates for labor he performed on the subject project and for obtaining a building permit in his own name. The Respondent ultimately decided not to enter into a business relationship with T. J. Associates, Burch and Goodman. He did, however, work on the "Martin project" as a sort of job supervisor or foreman, performing some labor on the job and going to the job site on possibly two or three occasions during the course of the construction effort of T. J. Associates. The Respondent initially intended to use his contractor's license to properly qualify T. J. Associates with the Board and obtain the papers to do so, but after he did not enter the formal business relationship with T. J. Associates, neglected to do so, nor did T. J. Associates make any further effort to qualify itself as a contracting entity with the Florida Construction Industry Licensing Board. The Respondent did obtain the building permit for T. J. Associates for the Martin job on May 13, 1980, and obtained it under his individual name and contractor license number. T. J. Associates worked on the Martin job from May 6, 1980, to July 16, 1980. On July 16, 1980, after a dispute regarding the quality of the paint work and other matters, T. J. Associates and the Respondent stopped all work. At the time of the stoppage, the work was 90 percent complete. At the time the work was stopped, no more money was due to T. J. Associates for work already performed. The Martins, at that point, had paid T. J. Associates $35,900.00. The Martins had however, upon advice of their attorney, withheld sufficient funds at the point of cessation of work by T. J. Associates, to enable them to pay for the completion of the job by other labor and materialmen. Three subcontractors had been hired or contracted with by T. J. Associates for work which was performed by them on the Martin job. Those three subcontractors, Mr. Anthony Costa, Mr. Clyde Ray and Mr. Michael Ellis, had performed work for which they were owed, respectively, $531.00, $550.00 and $130.00. None of those three subcontractors have, as yet, been paid for these amounts. They repeatedly attempted to obtain payment from T. J. Associates, but were given no satisfaction in that regard. The Respondent never entered into any agreement or hiring arrangement with the three subcontractors involved, nor did the Respondent ever have possession or control of any funds paid from the Martins to T. J. Associates from which the subcontractors should have been paid. The Respondent only received the above- mentioned $600.00 from T. J. Associates for his services.

Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the evidence in the record, the candor and demeanor of the witnesses and the pleadings and arguments of the parties, it is, therefore RECOMMENDED that the Respondent be found guilty of a violation of Section 489.129(1)(e) and (k), in that he aided and abetted an uncertified, unregistered person to evade the act and violated Subsection (k) by abandoning the project without just cause. The remaining charges in the Administrative Complaint should, however, be dismissed. In view of the violations proven, an administrative fine of $500.00 and a three (3) month suspension of his license, followed by a one (1) year period of probation is warranted. DONE and ENTERED this 22nd day of August, 1983, in Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of August, 1983. COPIES FURNISHED: Douglas A. Shropshire, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Charles E. Hoequist, Esquire 301 North Ferncreek Orlando, Florida 32803 James Linnan, Executive Director Florida Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32202 Fred M. Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (5) 120.57489.105489.113489.119489.129
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs. STEPHEN J. BOROVINA, 77-001442 (1977)
Division of Administrative Hearings, Florida Number: 77-001442 Latest Update: Feb. 21, 1978

The Issue The Florida Construction Industry Licensing Board, Petitioner, seeks to revoke the registered contractor's license of Stephen J. Borovina, Respondent, based on allegations, which will be set forth in detail hereafter, that he engaged in conduct violative of Chapter 468, Florida Statutes. The issue presented is whether or not the Respondent aided or abetted and/or knowingly combined or conspired with Mr. Howard North, an uncertified or unregistered contractor, to evade the provisions of Chapter 468.112(2)(b), and (c), Florida Statutes, by allowing North to use his certificate of registration without having any active participation in the operations, management, or control of North's operations. Based on the testimony adduced during the hearing and the exhibits received into evidence, I make the following:

Findings Of Fact The Respondent is a certified general contractor who holds license no. CGC007016, which is current and active. On or about July 25, 1976, Mr. and Mrs. Julius Csobor entered into a contract with Mr. and Mrs. Howard North for the construction of a home in Martin County, Florida, for a total price of $35,990. Neither Mr. or Mrs. North are certified or registered contractors in the State of Florida. (Petitioner's Composite Exhibit #2). Respondent applied for and was issued a permit by the Martin County Building Department to construct a residence for the Csobors at the same address stipulated in the contract between the Csobors and the Norths, i.e., Northwest 16th Street, Palm Lake Park, Florida. (Petitioner's Composite Exhibit #1). Howard North, a licensed masonry contractor for approximately nine (9) years was contacted by the Csobors through a sales representative from a local real estate firm. It appears from the evidence that North had previously constructed a "spec" house which the local realtor had sold and thus put the Csobors in contact with Mr. North when they were shown the "spec" house built by North. Evidence reveals that North contacted Borovina who agreed to pull the permit "if he could get some work from the job and could supervise the project". Having reached an agreement on this point, North purchased the lot to build the home for the Csobors and he orally contracted with the Respondent to, among other things, pull the permit, supervise construction, layout the home and do trim and carpentry work. North paid Respondent approximately $200 to layout the home for the Csobors. By the time that North had poured the slab and erected the subfloor, the Csobors became dissatisfied with his (North's) work and demanded that he leave the project. According to North, Respondent checked the progress of construction periodically. Prior to this hearing, the Csobors had never dealt with Respondent in any manner whatsoever. According to Csobor, North held himself out as a reputable building contractor. A contractor is defined in relevant part as any person who, for compensation, undertakes to, or submits a bid to, or does himself or by others, construct, repair, etc. . . . real estate for others. . . Chapter 468.102(1), Florida Statutes. Applying this definition to the facts herein, it appears that the Respondent, at least in a literal sense, satisfied the requirements and obligations of a contractor, as defined in Chapter 468.102, Florida Statutes. Thus, he contracted with North to oversee and/or supervise the project for the Csobors which he fulfilled, according to the testimony of North. Said testimony was not refuted and thus I find that no effort was made by Respondent to evade any provision of Chapter 468, Florida Statutes. Accordingly, I shall recommend that the complaint filed herein be dismissed in its entirety.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is hereby recommended that the complaint filed herein be dismissed in its entirety. RECOMMENDED this 4th day of November, 1977, in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings 530 Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Barry S. Sinoff, Esquire 1010 Blackstone Building Jacksonville, Florida 32202 Stephen J. Borovina 2347 Southeast Monroe Street Stuart, Florida 33494 J. Hoskinson, Jr. Chief Investigator Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. DIVISION OF ADMINISTRATIVE HEARINGS, DOCKET NO. 77-1442 STEPHEN J. BOROVINA, CG C007016, 2347 S. E. Monroe Street, Stuart, Florida 33494, Respondent. / This cause came before the FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD at its regular meeting on February 10, 1978. Respondent was sent the Hearing Officer's findings and recommendations and was given at least 10 days to submit written exceptions to the recommended order. Respondent was notified of the meeting so that respondent or counsel might appear before the Board. Respondent did not appear The FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD on February 10, 1978, after reviewing a complete transcript of the Administrative Hearing, by motion duly made and seconded voted to revoke the certified general contractor's license of STEPHEN J. BOROVINA. It is therefore, ORDERED that the certification of respondent STEPHEN J. BOROVINA, Number CG C007016, be and is hereby revoked. Respondent is hereby notified that he has 30 days after the date of this final order to appeal pursuant to Chapter 120, Florida Statutes, and the Florida Appellate Rules. DATED this 13th day of February, 1978. FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD BY: JOHN HENRY JONES, President ================================================================= SECOND AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD STEPHEN J. BOROVINA, CG C007016, Respondent/Appellant, vs. DIVISION OF ADMINISTRATIVE HEARINGS, DOCKET NO. 77-1442 FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner/Appellee. / This cause came before the Florida Construction Industry Licensing Board at its regular meeting on August 3, 1979. The respondent was sent the Hearing Officer's findings and recommendations and was given at least 10 days to submit written exceptions to the recommended order. Respondent was notified of the meeting so that respondent or counsel might appear before the Board. Respondent did appear. The Florida Construction Industry Licensing Board, on August 3, 1979, after reviewing a complete transcript of the Administrative Hearing, by motion duly made and seconded, voted to revoke the certified general contractor's license of Stephen J. Borovina, No. CG C007016. On February 13, 1978, the certification of respondent, Stephen J. Borovina, No. CG C007016, was revoked by order of the Florida Construction Industry Licensing Board. On April 25, 1979, the District Court of Appeal of the State of Florida, Fourth District, in Case Number: 78-527, reversed the final order of the Florida Construction Industry Licensing Board. That Court remanded the above captioned case to the Board to further consider the matter and enter such order as it may be advised in conformity with Section 120.57(1)(b)(9), Florida Statutes (1977). In accordance with the decision of the Florida District Court of Appeal, Fourth District, the Board has reconsidered the above captioned matter and finds as follows: The Board rejects the recommended order as the agency's final order. The Board adopts the first paragraph of the hearing officer's finding of fact. The Board, however, rejects the findings of fact found in the second paragraph of the hearing officer's findings. The second paragraph states as follows: A contractor is defined in relevent(sic) part as any person who, for compensation, undertakes to, or submits a bid to, or does himself or by others, construct, repair, etc. real estate for others...Chapter 468.102(1), Florida Statutes. Applying this definition to the facts herein, it appears that the Respondent, at least in a literal sense, satisfied the requirements and obligations of a contractor, as defined in Chapter 468.102, Florida Statutes. Thus, he contracted with North to oversee and/or supervise the project for the Csobors which he fulfilled, according to the testimony of North. Said testimony was not refuted and thus I find that no effort was made by Respondent to evade any provision of Chapter 468, Florida Statutes. Accordingly, I shall recommend that the complaint filed herein be dismissed in its entirety. The findings of fact found in the above-quoted paragraph were not based upon competent substantial evidence. The competent substantial evidence supports a finding that the respondent, Stephen J. Borovina, did not supervise the project and that Borovina evaded the provisions of Chapter 468, Florida Statutes. The following evidence supports the Board's position: There was no written agreement entered into between Howard North and the respondent which indicated that the respondent was to supervise the construction of the Csobors' house (T- 14); It was conceded at the hearing that the only subcontractors or draftmen who worked on the Csobors' house were contracted solely by Howard North and they had no contract whatsoever with the respondent (T-19, 25); The respondent never advised or informed Mr. and Mrs. Csobor that he was the contractor on the job. (T-51); At all times during the act of construction of the house, Mr. and Mrs. Csobor were under the impression that Howard North was the contractor (T-44-51). It is, therefore, ORDERED: That the certification of respondent, Stephen J. Borovina, Number CG 0007016, be and is hereby revoked. Respondent is hereby notified that he has thirty (30) days after the date of the Final Order to appeal pursuant to Chapter 120, Florida Statutes, and the Florida Appellate Rules. Dated this 3rd day of August, 1979. FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD BY: JOHN HENRY JONES, President

Florida Laws (1) 120.57
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs MARVIN M. KAY, 89-003902 (1989)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Jul. 21, 1989 Number: 89-003902 Latest Update: Mar. 12, 1993

The Issue DOAH Case No. 89-3902, the Barona and Carrow Complaints Whether Respondent violated Florida Statutes Section 489.129(1)(d), by willfully or deliberately disregarding and violating the applicable building codes or laws of the state or of any municipalities or counties thereof. Whether Respondent violated Florida Statutes Section 489.129(1)(m), by being guilty of fraud or deceit or of gross negligence, incompetency, or misconduct in the practice of contracting. DOAH Case No. 90-1900, the Grantz, Victor, Beckett, Maffetonne, and Wolfe Complaints Whether Respondent violated Sections 489.129(1)(m), (j), and 489.105(4), and 489.119, Florida Statutes, by being guilty of gross negligence, incompetence, and/or misconduct. Whether Respondent violated Sections 489.129(1)(h), (m), (j), and 489.119, and 489.105(4), Florida Statutes, by being guilty of financial mismanagement or misconduct. Whether Respondent violated Section 489.129(1)(d), Florida Statutes, by wilful or deliberate violation or disregard of applicable local building codes and laws. Whether Respondent violated Sections 489.129(1)(m), (j), 489.119, and 489.105(4), Florida Statutes, by failing to properly supervise contracting activities he was responsible for as qualifying agent, which supervisory deficiency also reflected gross negligence, incompetence, or misconduct Whether Respondent violated Section 489.129(1)(k), Florida Statutes, by abandoning a construction project in which the contractor is engaged or under contract as a contractor. Whether Respondent violated Sections 489.129(1)(m), and (j), Florida Statutes, by giving a guarantee on a job to a consumer and thereafter failing to reasonably honor said guarantee in violation of Florida Statutes. DOAH Case No. 90-1901, the Klokow Complaint Whether Respondent violated Section 489.129(1)(d), Florida Statutes, by wilfully or deliberately disregarding and violating the applicable building codes or laws of the state or any municipalities or counties thereof. Whether Respondent violated Section 489.129(1)(k), Florida Statutes, by abandoning a construction project in which the contractor is engaged or under contract as a contractor. Whether Respondent violated Section 489.129(1)(m), Florida Statutes, by being guilty of fraud or of gross negligence, incompetency, or misconduct in the practice of contracting. DOAH Case No. 90-1902, the Meister Complaint Whether the Respondent violated Section 489.129(1)(n), Florida Statutes, by failure to obtain a permit. DOAH Case No. 91-7493, the Antonelli Complaint Whether Respondent violated Section 489.129(1)(h), Florida Statutes, by committing mismanagement or misconduct in the practice of contracting that causes financial harm to a customer. Whether Respondent violated Section 489.129(1)(k), Florida Statutes, by abandoning a construction project in which the contractor is engaged or under contract as a contractor. Whether Respondent violated Section 489.129(1)(m), Florida Statutes, by being guilty of fraud or deceit or of gross negligence, incompetency, or misconduct in the practice of contracting. DOAH Case No. 91-7951, the Insurance, Palomba, Romanello and Marin Complaints The Insurance Complaint Whether Respondent violated Section 489.129(1)(c), Florida Statutes, by violating Section 455.227(1)(a), Florida Statutes, by making misleading, deceptive, untrue, or fraudulent representations in the practice of his profession. Whether Respondent violated Section 489.129(1)(d), Florida Statutes, by wilfully or deliberately disregarding and violating the applicable building codes or laws of the state or any municipalities or counties thereof. Whether Respondent violated Section 489.129(1)(c), Florida Statutes, by violating Section 455.227(1)(b), Florida Statutes, by intentionally violating a Board rule. Whether Respondent violated Section 489.129(1)(m), Florida Statutes, by being found guilty of fraud or deceit or of gross negligence, incompetency, or misconduct in the practice of contracting. The Palomba Complaint Whether Respondent violated Section 489.129(1)(h), Florida Statutes, by committing mismanagement or misconduct in the practice of contracting that causes financial harm to a customer. Whether Respondent violated Section 489.129(1)(m), Florida Statutes, by being found guilty of fraud or deceit or of gross negligence, incompetency, or misconduct in the practice of contracting. The Romanello Complaint Whether Respondent violated Section 489.129(1)(h), Florida Statutes, by committing mismanagement or misconduct in the practice of contracting that causes financial harm to a customer. Whether Respondent violated Section 489.129(1)(k), Florida Statutes, by abandoning a construction project in which the contractor is engaged or under contract as a contractor. Whether Respondent violated Section 489.129(1)(m), Florida Statutes, by being found guilty of fraud or deceit or of gross negligence, incompetency, or misconduct in the practice of contracting. The Marin Complaint Whether Respondent violated Section 489.129(1)(h), Florida Statutes, by committing mismanagement or misconduct in the practice of contracting that causes financial harm to a customer. Whether Respondent violated Section 489.129(1)(k), Florida Statutes, by abandoning a construction project in which the contractor is engaged or under contract as a contractor. Whether Respondent violated Section 489.129(1)(m), Florida Statutes, by being found guilty of fraud or deceit or of gross negligence, incompetency, or misconduct in the practice of contracting. DOAH Case No. 92-0370, the Pappadoulis Complaint Whether Respondent violated Section 489.129(1)(h), Florida Statutes, by committing financial misconduct. Whether Respondent violated Section 489.129(1)(m), Florida Statutes, by committing gross negligence, incompetence and misconduct in the practice of contracting.

Findings Of Fact Pre-Hearing Admissions 3/ Admissions Applicable to All Cases Respondent is currently licensed as a contractor by the Florida Construction Industry Licensing Board. Respondent's current license number from the Florida Construction Industry Licensing Board is CG C040139. Respondent is licensed by the Florida Construction Industry Licensing Board as a certified general contractor. Respondent holds Florida Certified Roofing License No. CC-042792. Respondent is the qualifying agent for Tropical Home Industries, Inc. As qualifying agent for Tropical Home Industries, Inc., Respondent is responsible for all work performed. DOAH Case No. 89-3902 Respondent was licensed as set forth in items 1, 2, 3 and 4 above at the time of the job alleged in the Administrative Complaint. Exhibit "A", attached to the Request for Admissions 4/ is a true and correct copy of the contract between Sarah S. Carrow and the firm Respondent qualified at the time the contract was executed. As a qualifier for Tropical Home Industries, Inc., Respondent was responsible in his capacity as a certified general and roofing contractor for all work performed by Tropical Home Industries, Inc., pursuant to its contract with Sarah S. Carrow. Pursuant to the contract between Sarah S. Carrow and Tropical Home Industries, Inc., all work under said contract was to be completed in three (3) to six (6) weeks. Respondent, acting through Tropical Home Industries, Inc., failed to complete all work under the contract with Sarah S. Carrow within six (6) weeks after work was commenced. Respondent, acting through Tropical Home Industries, Inc., failed to obtain a final inspection of the work under the contract with Sarah S. Carrow prior to the building permit's expiration date. Broward County, Florida, has adopted the South Florida Building Code as its local ordinance governing residential construction. Respondent's failure to obtain a timely final inspection of the work performed pursuant to the contract between Tropical Home Industries, Inc., and Sarah S. Carrow is a violation of Section 305.2 of the South Florida Building Code. Section 1405.1 of the South Florida Building Code requires installation of either a window or vent fan in each bathroom. Section 3407.9(a) of the South Florida Building Code requires that flashing be installed on plumbing vent pipes which are installed through the roof. Any problems or deficiencies in the work performed by Tropical Home Industries, Inc., pursuant to its contract with Sarah S. Carrow were caused by employees and/or subcontractors of Tropical Home Industries, Inc. DOAH Case Nos. 89-3902, 90-1900, 90-1901, and 90-1902 DOAH Case No. 89-3902 The Baronas' house is located at 1251 Westchester Drive East, West Palm Beach, Florida 33417. Respondent contracted with the Baronas as the qualifying agent of Tropical Home Industries, Inc. The Baronas' house is located within Palm Beach County. Palm Beach County is the appropriate Building Department under which all inspections were to have been performed. DOAH Case No. 90-1901 On or about December 5, 1988, Respondent contracted with Mel Klokow, acting for Linda Klokow ("Klokow"), for the renovation of a screen porch with a roof to her home. Respondent contracted with Klokow as a qualifying agent of Tropical Home Industries, Inc. Permit No. 88-8085 was issued by the local building department. The work at the Klokow residence did not pass final inspection. DOAH Case No. 90-1902 In December of 1987, Respondent contracted to close in a screen porch for Janet Meister ("Meister"). Respondent contracted with Meister as the qualifying agent for Tropical Home Industries, Inc. Respondent failed to obtain a permit for the work performed at the Meister's. Respondent's failure to obtain a permit for the Meister job violated local building codes and Section 489.129(1)(n), Florida Statutes. DOAH Case No. 90-1900 The Grantz home is located at 10878 Granite Street, Boca Raton, Florida. The approximate amount of the contract price with the Grantz was $1,890.00. Respondent contracted for the Grantz job as a qualifying agent of Tropical Home Industries, Inc. Respondent began work at the Grantz residence on or about May 10, 1989. The work at the Grantz residence failed final inspection on July 12, 1989. Respondent wilfully violated applicable local building codes and laws on the Grantz project. Respondent wilfully disregarded local building codes and laws in connection with the Grantz project. Respondent deliberately violated applicable local building codes and laws in connection with the Grantz project. Respondent deliberately disregarded applicable local building codes and laws in connection with the Grantz project. On or about April 12, 1989, and April 17, 1989, Respondent contracted with Stephen Victor ("Victor") to install sliding glass doors at his home. The Victor residence is located at 9768 Majorca Place, Boca Raton, Florida. The contract price with Victor was $3,293.00. Respondent contracted with Victor as a qualifying agent of Tropical Home Industries, Inc. Victor paid a total deposit of $670.00 to Respondent. Respondent never began work at the Victor residence. On or about April 17, 1989, Respondent contracted with Vinton Beckett ("Beckett") to install windows at her home. The Beckett residence is located at 2501 N.W. 41st Avenue, Unit 302, Lauderhill, Florida. The contract price with Beckett was $1,684.00. Respondent contracted with Beckett as a qualifying agent of Tropical Home Industries, Inc. On or about October 29, 1988, Respondent contracted with Thomas and Sherry Maffetonne (the "Maffetonnes") to construct a patio enclosure at their home. The Maffetonne's residence is located at 22980 Old Inlet Bridge Drive, Boca Raton, Florida. The contract price for the work to be performed at the Maffetonnes was $4,350.00. Respondent contracted with the Maffetonnes as a qualifying agent for Tropical Home Industries, Inc. A five-year warranty on materials was given by Respondent for the work to be performed at the Maffetonne's. A one-year warranty on labor was given by Respondent for the work performed at the Maffetonne's. On or about June 6, 1989, Respondent contracted with Mr. and Mrs. Morton Wolfe (the "Wolfes") to install windows at their home. The Wolfe's residence is located at 7267 Huntington Lane, #204, Delray Beach, Florida. Respondent contracted with the Wolfes as the qualifying agent of Tropical Home Industries, Inc. Respondent failed to obtain a timely permit or call for required inspections at the Wolfe residence. DOAH Case No. 91-7951 On June 21, 1990, Tropical's general liability insurance coverage (policy number 891006GL327), produced by Steven Adams and Associates, Inc., (hereinafter "Adams and Associates") and afforded by Guardian P & C Insurance Company, expired. On July 17, 1990, Tropical issued a check to Adams and Associates in the amount of $2,475.00 to obtain general liability and workers' compensation insurance. Upon receipt of the check, Adams and Associates issued a Certificate of Insurance to the Davie (Florida) Building Department indicating that Tropical had general liability (policy number GL 235810) and workers' compensation insurance in force through July 17, 1991. After said Certificate of Insurance was issued, Tropical stopped payment on the check issued to Adams and Associates. Tropical failed to issue an additional check or remit payment of any kind, resulting in both the general liability and workers' compensation insurance being canceled, effective July17, 1990. In September of 1990, a Certificate of Insurance was submitted to the Davie Building Department indicating that Tropical had general liability insurance in effect from September21, 1990, until September 21, 1991. Said certificate had been altered in that the issue, effective, and expiration dates had been updated to reflect that the policy coverage was current and in force. The policy listed on the certificate (number 891006GL327, produced by Adams and Associates with coverage being afforded by Guardian P & C Insurance Company) expired on June21,1990, and was never renewed or kept in force after that date. The Davie Building Department had no other certificates or records indicating that Tropical had insurance coverage. Between July 17, 1990, and April 8, 1991, Tropical obtained five (5) building permits from the Davie Building Department. At no time during the aforementioned period did Tropical have general liability insurance, thereby violating Section 302.1(b) of the South Florida Building Code which requires that building permit applicants be qualified in accordance with PartI of Chapter 489, Florida Statutes. Licensees are required to maintain public liability insurance at all times as provided by rules promulgated pursuant to Part I of Chapter 489, Florida Statutes. Construction Industry Licensing Board records indicate that Tropical has general liability insurance coverage through Equity Insurance (hereinafter "Equity") of Hollywood, Florida. Effective June 8, 1988, Tropical's insurance with Equity was canceled. On February 20, 1991, Tropical entered into an agreement with Michael and Margaret Palomba (hereinafter "Palombas") to perform enclosure and remodeling work at the Palombas' residence located at 130 North East 5th Court, Ft. Lauderdale, Florida 33334. The approximate contract price was $11,978.00. On March 13, 1991, Tropical received a $2,994.50 deposit from the Palombas. On March 25, 1991, Tropical obtained a permit for the project from the Broward County Building Department. Subsequent to receiving the permit, Tropical removed an interior closet from the area that was to be remodeled. Subsequent to receiving the permit, Tropical removed interior plaster from the area that was to be remodeled. Subsequent to receiving the permit, Tropical removed exterior doors from the area that was to be remodeled. Tropical then stopped work stating that rotten wood had been discovered, and requested an additional $2,800.00 to continue with and complete the project. Tropical refused to perform any additional work without the Palombas agreeing to the added cost. Tropical failed to continue with the project pursuant to the original agreement. Tropical refused to continue with the project pursuant to the original agreement. Tropical failed to return any monies to the Palombas. In May 1991, the Palombas hired a second contractor, Dan Sturgeon, to complete the project for $13,830.00. On or about July 11, 1990, Tropical entered into an agreement with Don Romanello (hereinafter "Romanello") to construct a screen room on an existing slab at Romanello's residence located in Boca Raton, Florida. The contract price was $9,500.00. Tropical received $4,800.00 in payments from Romanello, but failed to obtain a permit or perform any work pursuant to the agreement. Tropical has failed to return any portion of Romanello's payments. Tropical refused to communicate with Romanello. Based on the preceding, Tropical committed misconduct in the practice of contracting. On or about June 23, 1990, Tropical entered into an agreement with Marcelina Marin (hereinafter "Marin") to construct a screen room at Marin's residence located in Broward County, Florida, for $4,021.00. Tropical received a $2,000.00 deposit from Marin at the time the agreement was entered into. Tropical failed to perform any work under the terms of the agreement. Tropical has failed to return Marin's deposit. Tropical has refused to return Marin's deposit. Based on the preceding, Tropical committed misconduct in the practice of contracting. DOAH Case No. 91-7493 On July 2, 1988, Respondent contracted with Anthony Antonelli ("Antonelli") to construct an aluminum roof over the patio and gutters of his residence at 9303 Laurel Green Drive, Boynton Beach, Florida. The price of the contract was $2,016.00. Antonelli paid a deposit of $500.00 to Tropical Home Industries. Respondent informed Antonelli that he would not be able to perform the work at the contracted price. Respondent never performed any work at the Antonelli's home. Respondent canceled the contract with Antonelli. Respondent failed to return the deposit paid by Antonelli to Tropical Home Industries. Testimony at Final Hearing Facts Applicable to All Cases Respondent is, and has been at all times hereto, a certified general and roofing contractor in the State of Florida, having been issued license number CG C040139 and CC 2042792. For all contracts and jobs referenced in all of the administrative complaints in these consolidated cases, Respondent acted through the contracting business with which he was associated and for which he was responsible in his capacity as a licensed contractor. DOAH Case No. 89-3902, The Barona and Carrow Complaints Respondent contracted with Rhonda Barona to build an addition to her home at 1251 Westchester Dr. East., West Palm Beach, Florida, for approximately $5,124. The work performed at the Barona residence took an unreasonable amount of time to complete. The permit issued to perform the work at the Barona residence was canceled and Respondent failed to obtain a final inspection. Respondent contracted with Sarah Carrow to build an addition at her home located at 1421 N. 70th Avenue, Hollywood, Florida, for approximately $14,460.60. Respondent allowed the permit to expire and failed to obtain required inspections at the Carrow residence. Respondent failed to fully comply with applicable local codes by failing to install a window or vent fan in the bathroom. DOAH Case No. 90-1900, The Grantz, Victor, Beckett, Maffetonne and Wolfe Complaints On or about March 31, 1989, Respondent contracted with John and Lori Grantz to install windows at 10878 Granite Street, Boca Raton, Florida, for the amount of $1,890.00. Work at the Grantz residence began on or about May 10, 1989. At the time work began, no permit had been obtained. A late permit was obtained on June 15, 1989, in violation of local codes. The work performed by Respondent at the Grantz residence failed final inspection on July 12, 1989, because the structure was not constructed as for the intended use. The windows which were installed were designed as a temporary structure, removable in cases of severe weather and not as a permanent enclosure. On or about April 12, 1989, and April 17, 1989, Respondent contracted with Stephen Victor ("Victor") to install sliding glass doors and windows at 9768 Majorca Place, Boca Raton, Florida, for the total amount of $3,293.00. Victor paid Tropical a total deposit of $670.00, but work never began. On or about April 17, 1989, Respondent contracted with Vinton Beckett ("Beckett") to install windows at 2501 N.W. 41st St., Unit 808, Lauderhill, Florida, in the amount of $1,684. A five-year warranty on materials and a one-year warranty on labor were provided to Beckett by Tropical. Respondent failed to obtain a timely permit or call for required inspections in violation of local law. Respondent failed to correct defects and deficiencies in the work performed at the Beckett residence in a reasonable amount of time. On or about October 29, 1988, Respondent contracted with Thomas and Sharee Maffetonne to construct a patio enclosure at 22980 Old Inlet Bridge Drive, Boca Raton, Florida, for the amount of $4,350.00. A five-year warranty on materials and a one-year warranty on labor were given. Respondent failed to correct defects and deficiencies in the work on the Maffetonne residence in a reasonable amount of time. On or about June 6, 1989, Respondent contracted with Morton Wolfe to install windows at 7267 Huntington Lane, #204, Delray Beach, Florida, for the amount of $1,668.13. Respondent failed to obtain a timely permit or call for required inspections at the Wolfe residence in violation of local codes. DOAH Case No. 90-1901 The Klokow Complaint On or about December 5, 1989, Respondent contracted with Mel Klokow, acting for Linda Klokow, for the construction of a screen porch with a roof to her home at 5292 N.E. 10th Terr., Ft. Lauderdale, Florida, for the sum of $4,473.00. Permit number 88-8085 was issued by the local building department. The work performed at the Klokow residence initially failed to pass the final inspection, and the Respondent failed to return to correct the code violations in a reasonable amount of time. DOAH Case Number 90-1902 The Meister Complaint In December of 1987, Respondent contracted to close in a screen porch for Janet Meister. Respondent failed to obtain a permit for the work performed, which is a violation of local building codes. DOAH Case Number 91-7493 The Antonelli Complaint On July 2, 1988, Respondent contracted with Anthony Antonelli ("Antonelli") to construct an aluminum roof over the patio and gutters at his residence at 9303 Laurel Green Drive, Boynton Beach, Florida. The price of the contract for the work to be performed at the Antonelli residence was $2,016.00. Antonelli remitted a deposit of $500 to the Respondent. Respondent informed Antonelli that he would not be able to perform said job for the contracted price and no work ever began. Respondent canceled the contract with Antonelli and failed to return the deposit to Antonelli. DOAH Case Number 91-7951 The Insurance, Palomba, Romanello and Marin Complaints On June 21, 1990, Tropical's general liability insurance coverage, policy number (891006GL327), produced by Stephen Adams & Associates, Inc., ("Adams & Associates") and afforded by Guardian Property & Casualty Company, expired. On July 17, 1990, Tropical issued a check to Adams & Associates in the amount of $2,475.00 to obtain and/or renew general liability and workers' compensation insurance. Upon receipt of the check, Adams & Associates issued a certificate of insurance to the Davie Building Department in Davie, Florida, indicating that Tropical had general liability (policy number 235810) and workers compensation insurance in force through July 17, 1991. After said certificate of insurance was issued, Tropical stopped payment on the check issued to Adams & Associates. Tropical failed to issue an additional check or remit payment of any kind resulting in the general liability and workers compensation insurance being canceled, effective July 17, 1990. In about September 1990, a certificate of insurance was submitted to the Davie Building Department indicating that Tropical had general liability insurance in effect from September 21, 1990, until September 21, 1991. Said certificate had been altered in that the issue, effective and expiration dates had been updated to reflect that the policy coverage was current and in force. The policy listed on the certificate (number 891006GL327), produced by Adams & Associates and afforded by Guardian Property & Casualty Company, expired on June 21, 1990, and was never renewed or kept in force after that date. The Davie Building Department has no other certificates or records indicating that Tropical has insurance coverage. Between July 17, 1990, and April 8, 1991, Tropical obtained five (5) building permits from the Davie Building Department. At no time during the aforementioned period did Tropical have general liability insurance thereby violating Section 302.1(b) of the South Florida Building Code which requires that building permit applicants be qualified in accordance with Part I of Chapter 489, Florida Statutes. Licensees are required to maintain public liability insurance at all times as provided by rules promulgated pursuant to Part I of Chapter 489, Florida Statutes. Construction Industry Licensing Board ("CILB") records indicate that Tropical has general liability insurance coverage through Equity Insurance Company ("Equity") of Hollywood, Florida. Effective June 8, 1988, Tropical's insurance with Equity was canceled. On February 20, 1991, Tropical entered into an agreement with Michael and Margaret Palomba (the "Palombas") to perform enclosure and remodeling work at the Palomba's residence located at 130 N.E. 5th Ct., Ft. Lauderdale, Florida 33334. The approximate contract price was $11,978.00. On March 13, 1991, Tropical received a $2,994.50 deposit from the Palombas. On March 25, 1991, Tropical obtained a permit for the project from the Broward County Building Department. Subsequent to receiving the permit, Tropical removed an interior closet and exterior doors from the area that was to be remodeled. Tropical then stopped work stating that rotten wood had been discovered, and requested an additional $2,800.00 to continue with and complete the project. Tropical refused to perform any additional work without the Palombas agreeing to the added cost. Tropical failed or refused to continue with the project pursuant to the original agreement and failed to return any monies to the Palombas. In May, 1991, the Palombas hired a second contractor, Dan Sturgeon, to complete the project for $13,000.00. 156. Based on the foregoing, Tropical committed misconduct in the practice of contracting. On or about July 11, 1990, Tropical entered into an agreement with Don and Norma Romanello (the "Romanellos") to construct a screened room on an existing slab at the Romanello's residence located in Boca Raton, Florida. The contract price was $9,500. Tropical received a $4,800.00 payment from the Romanellos but failed to perform any work pursuant to the agreement. Tropical has failed or refused to return any portion of the Romanellos payments and has refused to communicate with the Romanellos. Based on the preceding, Tropical committed misconduct in the practice of contracting. On or about June 23, 1990, Tropical entered into an agreement with Marcelina Marin to construct a screened room at Marin's residence located in Broward County, Florida for $4,021.00 Tropical received a $2,000.00 deposit at the time the agreement was entered into. Tropical failed to perform any work under the terms of the agreement, and has failed or refused to return Marin's deposit. Based on the preceding, Tropical committed misconduct in the practice of contracting. DOAH Case Number 92-0370 The Pappadoulis Complaint On or about February 11, 1990, the Respondent contracted with John Pappadoulis ("Pappadoulis") to remodel a Florida room for the agreed upon amount of $11,448.00 at his residence located at 983 Southwest 31st Street, Fort Lauderdale, Florida. Respondent received a deposit of $648.00, but never obtained a permit nor began work. The Respondent failed or refused to return Pappadoulis' deposit. John Pappadoulis has since passed away. Aggravating and Mitigating Circumstances Monetary Damages Several of the customers in these cases suffered monetary damages. The Baronas had to hire an attorney to deal with the Respondent. The Baronas also incurred additional costs in the work they performed to complete the contract. John and Lori Grantz also suffered monetary damages due to their dealings with the Respondent. The work at the Grantz residence was never completed by the Respondent. The Respondent filed a lien on the Grantz property and also filed a lawsuit to receive the full amount of the contract price. The Grantz had to hire an attorney to obtain legal advice and to defend the lawsuit. The Grantz prevailed in that lawsuit and a judgment was entered requiring the Respondent to refund the $500.00 cash deposit. The Grantz also spent at least $150.00 on attorney fees. The deposit money was never returned and none of their costs were ever reimbursed by the Respondent. Steven Victor also sustained monetary damages in his dealings with the Respondent. Victor paid the Respondent $670.00 as a deposit. No work was ever performed. After requesting the return of his deposit money and failing to receive it, Victor filed a civil action against the Respondent. Judgment was entered in favor of Victor, but the judgment was never paid. The Maffetonnes also sustained monetary damages in their dealings with the Respondent. The Respondent agreed to refund a portion of the contract money to the Maffetonnes due to a problem with the carpet he installed incorrectly, but failed to ever refund any money. The Maffetonnes therefore paid for goods which were defective, and never received a compensatory credit. Klokow also sustained monetary damages in his dealings with the Respondent Because of continuing roof problems, Klokow had to hire an independent roofing expert to inspect the roof and prepare a report. Mr. and Mrs. Palomba also sustained monetary damage due to their dealings with the Respondent. When the Respondent abandoned the Palomba job, the Palombas were forced to hire a second contractor at a higher contract price. The Respondent's actions also caused monetary damages to Antonelli, Pappadoulis, Marin, and Romanello. In each case, the homeowner paid a deposit to the Respondent, and the Respondent failed to ever perform work or return any of the deposit money. The Antonellis paid $500.00, Pappadoulis paid $648.00, Marin paid $2,000.00, and Romanello paid $4,800.00. Actual Job-Site Violations of Building Codes or Conditions Exhibiting Gross Negligence, Incompetence, or Misconduct by the Licensee Several of the jobs involved in these cases had actual job site violations of building codes or conditions which exhibited gross negligence, incompetence, or misconduct by the Respondent which had not been resolved as of the date of the formal hearing. At the Barona residence, the framing inspection failed twice before finally being passed a third time; the lath inspection failed three times before finally passing on the fourth time; and the final inspection failed and was never satisfactorily completed by the Respondent. At the Carrow residence, the Respondent failed to install a window or vent fan in the bathroom of the room addition which he installed. In addition to the building code violation, the work performed was incompetent as the structure installed leaked for many months. Further, the original permit expired prior to a final inspection ever being obtained. At the Grantz residence, the Respondent exhibited incompetence and misconduct by installing windows that he knew or should have known were unsuitable for the purposes specified by the customer. Severity of the Offense The large number of violations established in these cases indicates that the Respondent is a serious threat to the public. These violations establish that the Respondent had a pattern of failing to conduct any meaningful supervision of work in progress. And perhaps most serious of all is his frequent act of soliciting deposits for projects he apparently had no intention of even beginning, much less finishing. This latter practice borders on constituting some form of larceny. Danger to the Public The Respondent is a danger to the public in two ways. First, he is a financial threat to the public, most significantly by his practice of taking deposits for jobs he apparently did not intend to perform. Second, he is a threat to public safety, because the work he performs is often done in a haphazard, careless manner. The Number of Repetitions of Offenses As is obvious from the findings of fact and conclusions of law in this Recommended Order, the Respondent is guilty of numerous repeated offenses which occurred over a period of approximately three years. The Respondent's numerous offenses are indicative of an attitude of contempt or disregard for the requirements of the applicable rules and statutes. Number of Complaints Against Respondent The charges in these cases are based on fifteen separate customer complaints to the Department of Professional Regulation regarding the Respondent. Further, the Palm Beach County Construction Industry Licensing Board received four complaints from homeowners regarding the Respondent 5/ and the Broward County Consumer Affairs Department received twenty-nine complaints regarding the Respondent. 6/ Such a large number of complaints indicates that the Respondent's shortcomings were not isolated events, but represent a recurring problem. The Length of Time the Licensee Has Practiced The Respondent was first licensed as a state general contractor in 1987. He obtained his roofing contractor license shortly thereafter. The Respondent's licenses were placed under emergency suspension in August of 1991. Damage to the Customers The damages, monetary and otherwise, suffered by the Respondent's customers has already been addressed. In addition, all of the Respondent's customers mentioned in the findings of fact suffered a great deal of aggravation, stress, and frustration in dealing with the Respondent. Penalty and Deterrent Effect In these cases, the proof submitted demonstrates that no penalties short of revocation of the Respondent's licenses and imposition of the maximum amount of fines will act as a deterrent to the Respondent and others and as appropriate punishment for the many violations established by the record in these cases. Efforts at Rehabilitation There is no persuasive evidence in the record of these cases that the Respondent has become, or is likely to become, rehabilitated. To the contrary, the greater weight of the evidence is to the effect that the Respondent is unwilling or unable to conform his conduct to the requirements of the statutes and rules governing the practice of contracting.

Recommendation Based upon the foregoing findings of fact and conclusions of law, IT IS RECOMMENDED: That the Respondent be found guilty of all of the violations charged in each Administrative Complaint and Amended Administrative Complaint as noted in the conclusions of law, and that the Respondent be disciplined as follows: The Respondent be required to pay an administrative fine in the amount of $5,000.00 for each of the twenty-nine counts of violations charged and proved, for a grand total of $145,000.00 in administrative fines; The Respondent's license numbers CG C040139 and CC C042792 be revoked; and The Respondent be required to pay restitution to the following Complainants in the following amounts: Steven Victor - $670.00; John Grantz - $650.00; Don Romanello - $4,800.00; Marcelina Marin - $2,000.00; Anthony Antonelli - $500.00; John Pappadoulis' next of kin - $648.00. All restitution shall earn 12% interest per annum from the date the Complainants paid their deposit to Respondent. DONE AND ENTERED at Tallahassee, Leon County, Florida, this 21st day of October, 1992. MICHAEL M. PARRISH, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 904/488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of October, 1992.

Florida Laws (6) 120.57455.227489.105489.119489.1195489.129