Findings Of Fact Application 7500165 requested average withdrawal of water of 1,804,750 gallons per day from 4 wells located about a mile east of Highway 41 and a mile north of Apollo Beach. The four wells would be for irrigation of tomato crops on total acreage of 4 acres located in Hillsborough County (Exhibit 1, Testimony of Elsberry and Boatwright). Notice of hearing as to the application was published in a newspaper of general circulation in accordance with statute and rule (Exhibit 3). A letter of objection from Joseph S. Benham, Apollo Beach, Florida, dated November 19, 1975 was submitted to the Water Management District, wherein he expressed concern regarding water shortages and, although he does not seek to totally deny the application, is of the belief that the district must insure sufficient controls and management of irrigation activities so that resources are not wasted, water runoff to drainage ditches is eliminated and renewed justification is given each year for the withdrawal (Exhibit 2). A representative of the District staff established that there would be no violation of statutory or regulatory requirement for issuance of a consumptive water use permit in this case except as to the fact that potentiometric level of the applicant's property would be lowered below sea level as a result of withdrawal. It was agreed at the hearing that a period of thirty days should be granted both parties to formulate a stipulation as to control of runoff. An unsigned stipulation was received from the Water Management District by the hearing officer on March 1, 1976, which provided that the permit would be granted with the following stipulations: Runoff from the property will be limited to 25 percent of the quantity pumped and by December 31, 1980 shall be reduced to 16.5 percent of the quantity pumped. The District may at its own expense install metering devices for the purpose of monitoring runoff. The permittee will be notified in advance of such action. The Permit will expire on December 31, 1980. (Testimony of Boatwright, Exhibit 4).
Recommendation That application 8500165 submitted by Elsberry and Elsberry, Inc. Route 2, Box 70 Ruskin, Florida, for a consumptive water use permit be granted with the conditions as follow: Runoff from the property will be limited to 25 percent of the quantity pumped and by December 31, 1980 shall be reduced to 16.5 percent of the quantity pumped. The District may at its own expenseinstall metering devices for the purpose of monitoring runoff. The permittee will be notified in advance of such action. The Permit will expire on December 31, 1980. That the Board grant an exception to the provision of Rule 16J- 2.11(4)(e), F.A.C., for good cause shown. DONE and ENTERED this 15th day of March, 1976, in Tallahassee, Florida. THOMAS C. OLDHAM Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: Jay T. Ahern, Esquire Southwest Florida Water Management District Post Office Box 457 Brooksville, Florida 33512 Elsberry & Elsberry, Inc. Route 2, Box 70 Ruskin, Florida
Findings Of Fact Petitioner is the receiver for Bayside Club, Islamorada, Inc., a dissolved Florida corporation ("Bayside"). Mr. Joseph Popplewell is a general contractor and former president of Bayside. Respondent is the governmental entity authorized by Chapter 76-441, Section 14(1), Laws of Florida, to adopt impact fees for the water system in the Florida Keys, to equitably adjust the financial burden of a new pipeline, and to expand it or improve appurtenant facilities between existing customers and new water users. In 1986, Bayside sought to construct a 30 unit hotel on approximately one acre of land in Monroe County, Florida. The development project was formally classified as an expansion of an existing eight unit hotel. The existing hotel, however, had little, if any, useful life, and, in substance, the project involved the development of a new 30 unit hotel. Bayside obtained a building permit on June 4, 1985. In the same month, the building permit was challenged by an adjacent land owner. The challenge asserted that the existing hotel constituted a grandfathered nonconforming use and that the building permit improperly treated the development site as if it were located in a zoning district which permitted hotel usage and subsequent expansion. During the last half of 1985, the Monroe County Commission considered the challenge to the building permit and found that the building permit was valid. The adjacent landowner filed suit against Bayside. The circuit court upheld the validity of the building permit. The suit was finally decided on May 29, 1990, when the Third District Court of Appeal reversed the lower court's decision that the building permit was valid. Dowd v. Monroe County, 557 So.2d 63 (Fla. 3d DCA 1990). On May 29, 1990, the circuit court entered its order declaring the building permit invalid. In 1986, Bayside was advised by Respondent that unit water system development fees ("impact fees") were scheduled to increase from $1,500 to $2,000. Bayside chose to avoid paying impact fees at the increased unit rate and to achieve a savings in development costs. On or about April 18, 1986, Bayside executed an Agreement For Water Service. On or about April 29, 1986, Bayside issued a check payable to Respondent in the amount of $36,840, which included impact fees in the aggregate amount of $33,000. As provided in Florida Administrative Code Rule 48-3.002 2., the Agreement For Water Service expressly stated in paragraph 1 that "SAID SYSTEM DEVELOPMENT CHARGE SHALL NOT BE REFUNDABLE." Construction of the proposed hotel stopped sometime in 1986. A receivor was appointed for Bayside by the appropriate circuit court on June 14, 1991. Sometime in early 1992, the receiver for Bayside requested a refund of the impact fees. Respondent denied that request in a letter dated February 27, 1992, but refunded amounts paid by Respondent in excess of the impact fees. Respondent's denial of Petitioner's request for a refund did not constitute an unreasonable classification and did not establish a differential rate that was either unjust or inequitable. Respondent has consistently applied Florida Administrative Code Rule 48-3.002 2. to prohibit the refund of impact fees regardless of the classification or rate charged the person who paid the impact fee. Petitioner had adequate notice in Rule 48-3.002 2. and the Agreement For Water Service that the impact fees were nonrefundable. Respondent reasonably anticipated that the projected costs for expanding the water system would be incurred. The county commission and circuit court both upheld the validity of the building permit. If Bayside reasonably anticipated that projected costs for expanding the water system and appurtenant facilities would not be incurred due to a suit challenging the building permit, Bayside had the option of not paying the impact fees until the final conclusion of litigation. Bayside was on notice that the impact fees were nonrefundable and chose to forego its option not to pay the fees until the conclusion of the suit challenging the building permit. Bayside made a business decision to save money and time by paying the impact fees when it did. Viewed in the light of hindsight, that business decision was imprudent. Bayside did not notify Respondent that the costs of expanding the system were not reasonably anticipated until six years after Bayside chose to pay the impact fees. The nonrefundable impact fees imposed by Respondent in 1986 were just and equitable. Expansion of the water system pipeline and appurtenant facilities was reasonably required as a result of the development proposed by Bayside at the time that the impact fees were imposed. The costs attributable to such expansion were reasonably anticipated by Respondent at the time that the impact fees were imposed. The use of the impact fees was limited to meeting such reasonably anticipated costs of expansion. The impact fees imposed by Respondent in 1986 did not exceed a pro rata share of reasonably anticipated costs. Expansion of Respondent's water system was necessary irrespective of the proposed hotel. The expansion of Respondent's water system and appurtenant facilities was financed through the sale of debentures. The indebtedness incurred is made good through revenues in the form of rates, fees, and other charges. Under such circumstances, rates and fees were set with a view towards raising the money necessary to repay the loan. The impact fees did not cease to be just and equitable merely because they were set high enough to meet the water system's reasonably anticipated capital requirements.
Findings Of Fact Lake Skinner is a 48 acre rain (not spring) lake located in Putnam County, Florida. There is no exotic vegetation in the lake. It has excessive natural vegetation due to natural water level fluctuation in the area and a wide littoral zone. Prior applications by Respondent Homeowners Association for an aquatic plant control permit were denied by DNR since the activities proposed under these prior applications were considered to be excessive or because DNR did not find that the Lake Skinner aquatic vegetation was presenting sufficient problems to justify a permit. Nonetheless, in the summer of 1985, Mrs. Outlaw, a homeowner whose property abuts the lake, used the herbicide 2,4-D on her individual shoreline without first obtaining a permit as required by law. She did so out of ignorance that she must have such a permit, and then ceased herbicide use when the requirement of a permit and the nature of penalties without a permit were made known to her. Her unsupervised use has left a bare patch at her shoreline today, but the herbicide concentration used could not be determined. Also, at some time in the early 1980's, DNR permitted the use of other herbicides by another abutting homeowner, Mrs. Lloyd. The Homeowners Association filed its present application for an aquatic plant control permit with DNR on June 16, 1988. This application requested the control of seven acres of bladderwort and eight acres of milfoil in Lake Skinner through the use of the herbicide, 2,4-D. All members of the Homeowners Association acquiesced in this application, with the exception of the Petitioner. In the course of approving the permit, DNR conducted a survey of Lake Skinner on June 29, 1988, together with the Florida Game and Fresh Water Fish Commission, utilizing visual inspection, identification of plant species, and fathometer tracings. The June 29, 1988 survey revealed there were twenty acres of myriophyllum laxum, or milfoil, and thirteen acres of utricularia, spp., or bladderwort, in Skinner Lake, that most of these submersed aquatic plants were between two and five feet below the water's surface, and that navigational access was inhibited only over two to four percent of the open water. The June 29, 1988 survey also revealed that the abutting landowners were clearing and maintaining access from their respective shorelines to open water, but that without some type of maintenance or control program, this access could be blocked in the future by either submersed or immersed aquatic plants. The growth of the native aquatic vegetation is seasonal, but the vegetation is most dense during the summer months. This phenomenon accounts in part for DNR studies/surveys, introduced by DNR as exhibits but cited by Petitioner, which seem to show a decrease over time in the species sought to be controlled by the present permit application. Competition among, and fluctuation in, these species and other species of aquatic plants surveyed over time also obscures the homeowners' current problem, discussed infra. The native aquatic vegetation in Lake Skinner has interfered with the recreational use of the lake by the members of the Homeowners Association to some degree since 1984. The dense growth of aquatic vegetation in the lake during the summer months interferes with swimming, fishing, and boating activities by the members of the Homeowners Association. Motorboats break off pieces of submersed aquatic vegetation which float to the surface and are blown onto the shoreline. Some of these fragments take root near the shoreline. Those fragments of vegetation which wash off on the shore take time to be removed. Most homeowners who testified personally are regularly removing the debris by hand. Some witnesses spend the better part of one or two days a week (all weekend) removing the material from their respective shorelines; others work at it a little every day. Several members of the Homeowners Association expressed concerns for the safety of people, particularly children, swimming in the lake among the dense aquatic vegetation. In spite of legitimate concerns for future expansion of the problem and some anecdotal stories of past isolated situations, the current status of the lake's vegetation was not proved to be life-threatening but to be more in the nature of a nuisance which deprives the abutting homeowners of full enjoyment of their property and which diminishes the property's resale value. DNR considers abutting owners to be riparian owners. See, Conclusions of Law, infra. On August 4, 1988, DNR issued a permit to the Homeowners Association. The permit authorized the control of four acres of bladderwort through the use of the herbicide 2,4-D, mechanical harvest, or hand removal. It authorized control of four acres of milfoil through the use of 2,4-D, mechanical harvest, or hand removal. It also authorized control of one acre of southern cutgrass through the use of mechanical harvest or hand removal. The decision to issue the permit was based upon a finding, within the agency's expertise, that access for the abutting owners was impeded from the shore to open waters by southern cutgrass mixed with bladderwort and milfoil. Navigation and usage of the lake was found to be inhibited by milfoil and bladderwort which are three feet or less from the surface. The permit was designed to allow the abutting owners two types of access: navigational and riparlan. The permit allows the Homeowners Association to remove one acre of bladderwort and milfoil in open waters where these aquatic plant species are found within three feet of the surface and are inhibiting navigational access. Any open water herbicide treatment plot must be at least 50 yards from shore. The permit also allows riparian access from the shoreline to open waters by controlling/removing southern cutgrass, bladderwort, and milfoil in an area not exceeding 40 percent of the riparian owners' waterfront property from the shore to open water. Any such riparian herbicide treatment plots may not extend mcre than 50 yards from shore. It may be inferred from this requirement that the agency is attempting to avoid any overlapping of herbicide treatment. Although Dr. Christman challenged the permit partly on the basis that its language was unclear, vague, and subject to a variety of interpretations by each homeowner so as to result in an excessive use of 2,4-D not contemplated by the agency's permitting personnel, it is found upon the evidence as a whole that the permit is sufficiently clear as to what activities are and are not permitted, and is, in fact, conservative in nature. The permit is only good for one year, therefore renewals must be subject to agency review. The permit does not allow the eradication or control of all the aquatic vegetation in the lake, and it specifically identifies the species of aquatic plants that can be controlled by the abutting homeowners, as well as the areas in the lake where such control can take place. DNR's Rule 16C-20.0045, F.A.C., requires that all herbicides used for aquatic plant control or maintenance must be used according to the instructions contained on the respective products' labels. Commercially sold 2,4-D is labeled with instructions and directions on the use of the product. Moreover, the testimony of Jeffrey Schardt of DNR's Bureau of Aquatic Plant Management, and of Larry Nall, DNR Research Program Administrator, who qualified as an expert in herbicide usage and registration, is persuasive that when the product 2,4-D is used according to its label's instructions, there will be no direct negative impact on fish, wildlife, or non-target plants. Also, the testimony of Dean Barber, DNR Regional Biologist, to the effect that with a permit, the agency can better "police" the anti-vegetation activities on and around Lake Skinner than DNR was able to do when individual homeowners bought and administered their own herbicides without a permit, is accepted. In summary, Mr. Barber testified that the permit was designed as a justifiable management technique and is restrictive enough to keep the Homeowners Association from proceeding haphazardly. The herbicide 2,4-D is one of the most widely used herbicides in the world. It is used primarily for weed control on food and non-food crops, range and pasture land, and forest management, and for aquatic plant control. 2,4-D has been registered for such uses since 1948. It is presently registered with the United States Environmental Protection Agency (EPA) and the Florida Department of Agriculture and Consumer Services. The EPA has classified 2,4-D in Category "D" (not classifiable as to carcinogenicity) based on the inadequate evidence of cancer in human beings and laboratory animals. Basically, this means that from the federal government's viewpoint, there is insufficient evidence to conclusively prove the suspicions of many, including Petitioner Dr. Christman, that 2,4-D is carcinogenic. Whereas the EPA's conclusions are based upon a consensus of opinion from EPA scientists, national experts on epidemiology, and the Federal Insecticide, Fungicide, and Rodenticide Act Scientific Advisory Panel, Dr. Christman admitted that he had no experience in aquatic toxicology, chemistry or `pharmacology, and that he has conducted no research studies on 2,4-D. Dr. Christman, who was accepted as an expert in terrestrial and fresh water ecology and as a natural historian, expressed the opinion that 2,4-D can be dangerous to human beings, animals, and fish on two levels: their ability to reproduce at all and their ability to produce normal offspring without any mutations in those offspring. However, Dr. Christman did not demonstrate that either of these possible results could be reasonably expected from the application of 2,4-D as limited by the conservative terms of the proposed permit. There is also clear evidence which is contrary to Dr. Christman's assertions that aquatic animal life will be negatively affected. That contrary evidence is compelling in that it arises from considerable direct experience that DNR has had with permitting the use of 2,4-D over a number of years. See Finding of Fact 20, infra. DNR has long permitted the use of 2,4-D for aquatic plant control activities. 2,4-D is the first or second most frequently used aquatic herbicide in Florida. 2,4-D is the primary control method for water hyacinths and has been successful in reducing the number of hyacinths in Florida waters. The pounds of 2,4-D as an active ingredient used to control aquatic plants pursuant to a DNR permit have gone from a high of 159,666 pounds in 1984 to 62,005 pounds in 1987. One possible inference from this decline in poundage used is that the product is effective because repeat usage may be less necessary. Another inference is that its use is not authorized excessively by the agency. 2,4-D will not work on all plants. It is primarily intended for the control of broad-leafed plants. Therefore, it can be targeted for the plants that create a problem. 2,4-D will have a limited effect on grasses at low concentration rates. Its use, according to Mr. Schardt, is mandated to control plants anticipated to create a problem before that problem actually arises, which means that less herbicide can be used, thereby resulting in less cost and better control than might be required later. The Florida Department of Game and Fresh Water Fish is actively controlling native bladderwort and milfoil in Lafayette County with granular 2,4-D this year. In the years that DNR has permitted the use of 2,4-D for aquatic plant control activities in water bodies throughout Florida, there have been no documented fish kills, snail kills, or animal kills where the herbicide has been used. Likewise, there have been no documented reports of people being adversely affected by going into waters treated by 2,4-D
Recommendation From the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Department of Natural Resources enter a Final Order reissuing the August 4, 1988 permit containing all the restrictions and special conditions as it did originally, but modified to reflect a current issuance date, limit the permit's duration to one year from the current issuance date, and clearly specify that renewal is subject to complete review and survey of the lake at the time any renewal is applied for. DONE and ENTERED this 17th day of March, 1989, in Tallahassee, Leon County, Florida. ELLA JANE P. DAVIS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 17th day of March, 1989. APPENDIX TO THE RECOMMENDED ORDER IN CASE NO. 88-4629 The following constitutes specific rulings pursuant to Section 120.59(2), F.S., upon the Proposed Findings Of Fact, (PFOF) of the parties. Petitioner Dr. Christman filed no post-hearing proposals. Respondent Lake Skinner Homeowners Association filed no post-hearing proposals. Respondent Department of Natural Resources PFOF: 1-9 Accepted except where immaterial or unnecessary. 10-21, and 23 Accepted in substance but modified to more closely conform to the credible record fact and expert evidence as a whole. 22 Rejected as subordinate and unnecessary. COPIES FURNISHED: Dr. Steven P. Christman Post Office Box 391 Hawthorne, FL 32640 Mr. Raymond Bragg 1813 Grassington Way Jacksonville, FL 32223 Margaret S. Karniewicz General Counsel Department of Natural Resources 3900 Commonwealth Boulevard Tallahassee, FL 32399-3000 Tom Gardner Executive Director Department of Natural Resources 3900 Commonwealth Boulevard Tallahassee, FL 32399-3000
Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: This controversy began on July 9, 1990, when petitioners, David and Victoria Page, filed an application with the district office of respondent, Department of Environmental Regulation (DER), seeking the issuance of a permit authorizing certain construction activities (including the erection of a seawall) on their residential lot located at 3108 Gulfwinds Circle, Hernando Beach, Florida. The property faces west on the Gulf of Mexico, a water body designated as a Class III water in the State. The application was eventually deemed to be complete on October 24, 1990. After conducting a review of the application and an on-site inspection of the property, on January 18, 1991, DER issued its notice of permit denial. The notice identified the reasons for the denial as being petitioners' failure to give reasonable assurances that water quality standards would not be violated and that the project would be in the public interest. Also, DER cited expected adverse cumulative impacts if the application was granted. The notice provided further that if petitioners agreed to locate their seawall landward of the jurisdictional line, the project would be approved. In July 1991, petitioners amended their application to propose that the seawall be constructed even further seaward of the jurisdictional line. When efforts to resolve the case were unsuccessful, petitioners requested a formal hearing on January 17, 1992, to contest the agency's decision. Petitioners purchased their property in 1989. It lies within Unit 2 of Gulf Coast Retreats, a residential subdivision in Hernando Beach, Florida. The property is identified as lot 20 on Gulfwinds Circle and fronts the Little Pine Island Bay (Bay), which is a part of the Gulf of Mexico. Access to the Gulf is provided by a channel (six feet in depth) in the Bay in front of lot 20 and which eventually runs into the Gulf several miles south of petitioners' lot. It is undisputed that in 1985 Hurricane Elena passed offshore causing erosion to lot 20 and other adjacent lots. Consequently, the upland portion of the lot is now smaller than before the hurricane. However, petitioners purchased their property in that state of condition. Lots 19 and 21 are on the south and north sides of petitioners' property and are owned by the Steins and Budricks, respectively. Both neighbors have constructed vertical concrete seawalls in front of their homes. Budrick was issued a permit to construct a seawall on December 28, 1989, while Stein constructed his without a permit. However, Stein has subsequently filed an after-the-fact permit application and was recently advised by DER that the application was complete. At hearing, a DER representative expressed the view that the Stein application will probably be approved since his wall is landward of the DER jurisdictional line. It is noted that the Stein and Budrick seawalls sit back from the original property lines because of the erosion suffered during the 1985 hurricane and correspond to the jurisdictional line established by DER on their property. Another application for a permit to construct a seawall was filed by the owner of lot 18 in March 1992. Like Stein and Budrick, that owner proposed to construct his wall on the landward side of the jurisdictional line. Petitioners, who live in Kansas, desire to construct a home on their lot. They have proposed to place one hundred cubic yards of fill (limerock) on 1,065 square feet of intertidal wetlands on the western end of their lot and construct a 110-foot vertical seawall up to thirty feet seaward of the jurisdictional line. Thus, there will be dredge and filling activities in the Gulf of Mexico, a class III water of the state, thereby invoking the jurisdiction of DER. By law, DER is required to establish a jurisdictional line to show the landward extent of waters of this state, including the Gulf of Mexico. Such extent is normally defined by species of plants or soils which are characteristic of those areas subject to regular and periodic inundation by the waters of the state. As a general practice, using a prescribed plant or species indicator list, DER makes an on-site inspection of the property to determine what vegetation, if any, is found on the property and is subject to regular and periodic inundation by the waters. In this case, the dominant vegetation found on lot 20 was paspalum distichum, a plant on the species list subject to regular and periodic inundation by the Gulf waters. Accordingly, DER observed where the vegetation ended and used that point for the placement of the jurisdictional line. As a cross check, DER also noted the rack line, which is indicative of the landward extent to which the high tides rise, and found it to correspond to the vegetation line. It should be noted that the jurisdictional line established on petitioners' property corresponds with the line drawn on lots 18, 19 and 21, and if that line is used to construct the seawall on lot 20, the seawalls on all four lots would run in a straight line. Although petitioners objected to the jurisdictional line as established by DER, they offered no credible evidence to show that it was improper or should have been placed at a different location. On January 9 and 15, 1991, Richard W. Pugh, a DER field environmental specialist, conducted an on-site inspection of the property and adjacent waters. He also was responsible for establishing the jurisdictional line. Finding numerous adverse environmental effects that would occur if the permit was granted as proposed, Pugh recommended that the application be denied. This recommendation was accepted by the deputy assistant secretary for DER's Southwest District Office and a notice of permit denial was accordingly issued. The bases for the denial were that (a) reasonable assurances had not been given by petitioners that water quality standards would be satisfied; (b) a cumulative adverse impact on the area would occur if the permit was approved, and (c) petitioners had failed to give reasonable assurances that the project was in the public interest. In order to prove entitlement to a permit, petitioners must give reasonable assurance that water quality standards will not be violated and that the project is in the public interest. In this respect, they offered no evidence to provide these assurances. This in itself supports a finding that no entitlement to a permit has been shown. Even so, the agency elected to present evidence on these issues after petitioners' case-in-chief was concluded. Findings of fact drawn from that evidence are set forth below. On April 6, 1992, a DER marine biologist, Dr. George H. Farrell, visited the site and conducted a biological evaluation of the composition of the benthic community in the intertidal and subtidal wetlands which would be impacted by the project. Based on his tests and observations, Dr. Farrell concluded that the project as proposed would have an adverse impact on marine and wildlife resources in the area. This is because the area has very good water quality, contains a high species diversity, performs an integral part in the food web, and serves a valuable nursery function for estuarine dependent juvenile fish species and a corridor function for migrating estuarine dependent fish species. This testimony was not challenged by petitioners and is hereby accepted. 1/ In granting or denying a water resource permit, DER is also required to consider certain statutory criteria found in Subsection 403.918(2), Florida Statutes, to determine whether a project is in the public interest. Although petitioners did not address these criteria, and thus failed to give any assurances that the project is in the public interest as required by law, testimony adduced by DER established that under petitioners' proposal, there will be a permanent loss of 1,065 square feet of intertidal wetlands due to filling activities. These wetlands are now used by fish and wildlife habitat and will no longer be available for use. In addition, the same area is used as a nursery area by a variety of fish species. As such, the project will adversely affect the conservation of fish and wildlife and their habitats and will adversely affect the fishing values and marine productivity in the vicinity. Second, because petitioners' proposed seawall will jut out from their neighbors' walls by as much as thirty feet, and the corners of the seawall in that configuration will result in erosion or shoaling depending on whether the waters are moving north or south, the project will cause harmful erosion or shoaling. Third, because the wall is being constructed of concrete and steel and is not temporary, the project will be of a permanent nature and thus have a permanent adverse impact. Finally, the ecological functions being performed in the immediate vicinity of the project are extremely important and the elimination of this zone will significantly impair those functions. Collectively, these considerations support a finding that the project is not in the public interest. DER has a policy of not granting a permit if adverse cumulative impacts may be expected as a result of granting that permit. This policy is derived from a statute (s. 403.919, F.S.) requiring such impacts to be considered in the permitting process. In the case at bar, DER reasonably predicts that if it granted petitioners' application and authorized them to construct a seawall which jutted out up to thirty feet beyond their neighbors' walls, it would be obligated to grant similar permits to property owners on adjacent lots. Because petitioners' application will have an adverse impact on the water quality and is contrary to the public interest, the granting of additional permits would exacerbate those impacts. When an applicant proposes to fill (destroy) wetlands, and the applicant is unable to meet the public interest criteria set forth in subsection 403.918(2), DER shall consider measures proposed by or acceptable to the applicant to mitigate the adverse effects caused by the project. In this case, no mitigative measures were proposed by petitioners. At hearing, petitioners' representative asserted that in June 1991, the Cabinet (presumably sitting as the Board of Trustees of the Internal Improvement Trust Fund) implemented a new "policy" which allows property owners to "recover and bulkhead" land previously lost due to avulsion and erosion. He further represented that such requests were to be filed within five years after the event (hurricane). Although petitioners were not the property owners when the event occurred, and more than five years has elapsed, in July 1991 petitioners filed a request with the Department of Natural Resources (DNR) to reclaim and bulkhead their property and that request remained pending as of the date of hearing. A copy of the policy itself (or rule, if any, implementing the policy) was not made a part of this record. Even so, there was no evidence to establish that the granting of that application would require DER to grant a water resource permit, and DER takes the position that the request has no bearing on the issue of whether a water resource permit should be issued to petitioners.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered denying petitioners' application for a water resource permit. DONE and ENTERED this 27th day of April, 1992, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of April, 1992.
Findings Of Fact The Respondent is a multi-county water management district which was created by Chapter 25270, Laws of Florida, 1949, and which operates pursuant to the provisions of Chapter 373, Florida Statutes. The District is the local sponsor for the federally-authorized "Central and Southern Florida Project for Flood Control" and as such, operates and maintains various water control facilities and impoundments in South Florida, as authorized and constructed by the Federal Government. The jurisdiction of the District encompasses 16 counties in southern and central Florida, from Marion County in the north to Monroe County in the south. Water Conservation Area 2A is one of several water conservation areas within Respondent's jurisdiction and is a part of the federally-authorized Central and Southern Florida Project for Flood Control. On April 13, June 2, August 10, September 26, October 19, and October 20, 1978, the Governing Board of the District held public hearings and workshop meetings to receive comments from the District staff and the general public concerning the proposed "draw down" or alteration of water levels in Water Conservation Area 2A. Notice of the September 26, 1978 public hearing was published in the Florida Administrative Weekly, Volume No. 4, No. 36, on September 8, 1978. By the terms of the notice, the purpose of the September 26th public hearing was: To provide interested citizens with an opportunity to express their opinions and hear testimony regarding the District's proposal to lower the water level in Conservation Area 2A, located in western Palm Beach and Broward counties. The purpose of the draw down is to con- solidate the bottom sediments so that a more flexible water schedule can be begun to preserve the natural Everglades ecology . . . . After considering information received from staff and the general public, the Governing Board entered its "Order" No. 78-12 dated October 20, 1978 containing findings of fact and conclusions of law. This "order" provided, in pertinent part: That the staff take appropriate measures to accomplish the following: A draw down from current high water levels will be initiated October 31, 1978, with the goal of reducing water levels in the central portion of the marsh to ground level by December 31 (about 11.2 feet msl). From this point, water levels shall be allowed to continue to recede to a minimum level of 9.5' by the end of May, 1979. Water levels will be allowed to rise to about 12.5' msl by October 31, 1979. That the staff take appropriate measures to regulate water levels in Conservation Area 2A between 12.5' and 9.5' msl as provided in Paragraph 1. until November of 1981. That the regulation of Conservation Area 2A be carried out in a flexible manner to insure maximum environmental benefits and that adjustments in water level fluctuations and stages may be made predicated upon the environmental response of the Conservation Area 2A ecosystem resulting from the previous year's hydroperiod. That the staff pursue such research and data collection as is necessary to fully document the conditions of the marsh throughout the three year duration of the project. No formal hearings pursuant to Section 120.57(1), Florida Statutes, were requested as a result of the aforementioned workshop, public hearings or agency action embodied in the "order" of October 20, 1978. It is undisputed that Respondent did not comply with the requirements of Section 120.54, Florida Statutes, relating to rule making in issuing its Order of October 20, 1978. Petitioner, Joe Burgess, is the owner of Hinckle's Bait and Tackle Shop on State Road 84 in Broward County, approximately 12 miles from Conservation Area 2A. Petitioner Burgess derives approximately 60 to 70 percent of his business from customers who use Conservation Area 2A for hunting, fishing, and other recreational purposes. In addition, Petitioner Burgess personally uses Conservation Area 2A for hunting and fishing. Petitioner, Keith Finlayson, is an environmentalist who uses Conservation Area 2A for recreational purposes, including fishing, bird watching, observing animals in their natural habitats and flora identification. Petitioner Finalyson uses Conservation Area 2A for recreational purposes approximately two to three times per week. Petitioner, Concerned Citizens for the Everglades, Inc., is a not-for- profit Florida corporation, some of whose members presently use Conservation Area 2A for hunting, fishing, and other recreational purposes. Other members of the organization derive their living from businesses supported by revenues obtained from the general public directly attributable to "use" of Conservation Area 2A. One of the effects of the "draw down" will be to make certain portions of Conservation Area 2A inaccessible by boat during some periods of the year, thereby curtailing recreational and other use of the those areas. Water Conservation Area 2A, and other such areas within the jurisdiction of Respondent, is surrounded by levies and various water control structures and is operated independently of other water conservation areas, which are also surrounded by levies and water control structures. All of the water conservation areas within Respondent's jurisdiction are subject to different and independent water regulation schedules. The evidence establishes that it is not feasible to apply the same regulation schedule to all water conservation areas due to differences in topography. In fact, it is anticipated that a different regulation schedule for Water Conservation Area 2A will be developed after the current three-year draw down period is concluded. Although originally scheduled to commence on November 1, 1978, the "draw down" of water levels in Conservation Area 2A was delayed as a result of legal actions taken in state courts. As a result, the District did not actually begin the "draw down" until August, 1980.
The Issue Whether FDOT has provided reasonable assurances that the activities it proposes to conduct pursuant to proposed District SWM Permit Application No. 940606-10, WRM Permit Application No. 940606-2-D and modification to ROW Permit No. 2584 will comply with the relevant permit criteria set forth in Chapters 373 and 403, F.S., and applicable rules and criteria promulgated thereunder.
Findings Of Fact THE PARTIES Petitioner, 1000 Friends of Florida (1000 Friends), is a not-for-profit, tax exempt membership corporation, organized and existing under the laws of the State of Florida. The principal office of 1000 Friends is 926 East Park Avenue, Tallahassee, Florida 32314 and it also maintains an office at 3305 College Avenue, Ft. Lauderdale, Florida 33314. Petitioner, Florida Bay Initiative, Inc. (FBII), is an entity incorporated under the laws of Florida with its principal office located at 250 Australian Avenue South, Suite 500, West Palm Beach, Florida 33401. Petitioner, the Florida Keys Fishing Guides Association, is an association of sport fishing guides who live in the Florida Keys and is headquartered at 138 Royal Lane, Islamorada, Florida 33036. Petitioner, Michael Collins, is a private individual. His address is 138 Royal Lane, Islamorada, Florida 33036. Petitioner, Charles W. Causey, is a private individual. His address is Post Office Box 448, Islamorada, Florida 33036. Petitioner, the Florida Keys Concerned Citizens Coalition (FKCC), is a not-for-profit Florida corporation whose address is West Shore Drive, Big Pine Key, Florida 33043. Petitioner, AG Intus, Inc., filed a Notice of Voluntary Dismissal on August 9, 1996. DOAH Case 95-5524, the proceeding filed by Intus, was previously consolidated with the other cases to this proceeding. On August 12, 1996, the Intus case was severed from this proceeding and the Intus hearing cancelled. Respondent, the South Florida Water Management District (the District or SFWMD), is a public corporation in the State of Florida existing by virtue of Chapter 25270, Laws of Florida, 1949, and operating pursuant to Chapter 373, F.S., and Title 40E, F.A.C., as a multi-purpose water management district, with its principle office in West Palm Beach, Florida. Respondent, the Florida Department of Transportation (FDOT), is an agency of the State of Florida. Its District Six address is 1000 N.W. 111th Avenue, Miami, Florida 33172. Intervenor, Monroe County, is a political subdivision of the State of Florida. For the purposes of this proceeding the address for Monroe County is c/o Apgar and Pelham, 909 East Park Avenue, Tallahassee, Florida 32301. The District, FDOT and Monroe County did not object to the standing of the Petitioners at the formal hearing and represented that they will not object to the standing in the event of an appeal. Based on the representations of the Respondents, the Petitioners were not required to put on a case as to their standing. THE THREE PERMIT APPLICATIONS FDOT has applied to the District for a Wetland Resource Management (WRM) permit, a Surface Water Management (SWM) permit, and a Right of Way (ROW) occupancy permit. On June 6, 1994, the Applicant submitted applications for surface water management and wetland resource management permits for the purpose of widening and modifying this 20.4 mile stretch of U.S. 1. The surface water management permit application is identified as Application No. 940606-10. The wetland resource management permit application is identified as Application No. 940606-2-D. On October 24, 1995, the District issued Staff Reports on Permit Application No. 960606-10 and Permit Application No. 94060-2-D. These Staff Reports recommended issuance of the permits subject to general and special conditions as specified therein. An addendum to the staff report was issued November 3, 1995. On September 27, 1994, the Applicant submitted a request to modify its existing ROW Occupancy Permit to enable it to replace the bridge where U.S. 1 crosses the C-111 Canal. The land encompassed by the ROW occupancy permit challenged in this proceeding is located in Section 16 and 17, Township 59 South, Range 39 East, Dade County, Florida. A draft right-of-way occupancy permit with standard limiting and special conditions was produced as part of a package that went to the Governing Board and others. The proposed authorization for use of the ROW is for the following: REMOVAL OF EXISTING U.S. HIGHWAY 1 BRIDGE AND REPLACEMENT WITH A NEW FIXED BRIDGE. PROJECT INCLUDES CONSTRUCTION OF A NEW SERVICE/ACCESS ROAD, 2 DETENTION PONDS, 2 CATCH BASINS, 2-15" R.C.P. OUTFALLS, BOAT RAMP WITH LOADING DOCK, PARKING AREA, PEDESTRIAN GATE AT S-197, FENCING AND WILDLIFE CROSSING ALL WITHIN THE NORTH AND SOUTH RIGHT OF WAY OF C-111 (STATION 938+00 - 955+00). The draft right-of-way occupancy permit modification, identified as “SFWMD PERMIT NO. MOD 2548," should correctly be identified at “SFWMD PERMIT NO. MOD 2584.” The numbers “8” and “4” were inadvertently transposed. STIPULATIONS AS TO APPLICABLE LAW The parties have accurately set forth the applicable permitting criteria and the appropriate Basis of Review in their prehearing stipulation. CRITERIA FOR ROW PERMIT Rule 40E-6.301, Florida Administrative Code, provides, in pertinent part, as follows: In determining whether an occupancy permit should be issued, the District shall consider whether the proposed activity: interferes with the present or future construction, alteration, operation or maintenance of the works of the District; is consistent with the policy and objectives of Chapter 373 F.S., the legislative declaration of policy contained in Section 373.016, F.S. and the state water policy, Chapter 17-40, F.A.C.; has an actual or potential negative impact upon environmentally sensitive areas, which include: wetlands; endangered or threatened species habitat; aquatic preserves; outstanding Florida waters; federal, state and privately owned parks and wildlife management areas; designated areas of critical state concern; lands purchased by federal, state and local governments for the purpose of environmental protection, water resource protection and esthetics; and lands which contain native terrestrial plant species in significant amounts. Environmentally sensitive areas include areas on and off- site that are affected by activities which occur on, or are initiated from, the District’s works; degrades water quality within the receiving water body or fails to meet the provisions of Ch. 373, F.S., the state water policy, and Ch. 40E, F.A.C.; involves a discharge of wastewater from a new wastewater source or an increased discharge from an existing wastewater source; will discharge debris or aquatic weeds into District lands or works or cause erosion or shoaling within the works of the District; is supported by financial assurances, which will ensure that the proposed activity will be conducted in accordance with Chapter 373, F.S., and Chapter 40E-6, F.A.C.; presents an increased liability risk to the District; meets the general and specific criteria in the Basis of Review which is incorporated by reference in Rule 40E- 6.091, F.A.C.; interferes with actual or potential public use of the District’s works or public, recreational or other facilities not within the District’s works; is consistent with local zoning and other private land uses in the area; interferes with the quality or quantity of a public or private water supply; meets applicable criteria in Chapters 40E-61 and 40E-62, F.A.C.; ROW occupancy permits typically have standard limiting conditions which are incorporated as part of the permit. The permit may also have special limiting conditions. CRITERIA FOR PERMITTING THE SWM SYSTEM Rule 40E-4.301(1), Florida Administrative Code, contains the following criteria that, at the times pertinent to this proceeding, were used by SFWMD in determining whether to permit a surface water management system: In order to obtain or modify a permit under this chapter, an applicant must give reasonable assurances that the surface water system: provides adequate flood protection and drainage, without causing over- drainage, will not cause adverse water quality and quantity impacts on receiving waters and adjacent lands regulated pursuant to Chapter 373, F.S., will not cause discharges which result in any violations, in surface waters of the state, of the standards and criteria of chapter 17-302, F.A.C., will not cause adverse on-site or off-site impacts on surface and groundwater levels and flows, including impacts to sources of water supply and wetland hydrology, will not cause adverse environmental impacts, can be effectively operated and maintained, will not adversely affect public health and safety, is consistent with the State Water Policy, chapter 17-40, F.A.C., for a DRI with a signed Preliminary Development Agreement with the Florida Department of Community Affairs, pursuant to section 380.06(8), F.S., provides a surface water management system for that portion of the site approval for development which is able to operate separately from the surface water management system for the balance of the project site and still meet applicable District criteria. meets any applicable basin criteria in chapter 40E-41, F.A.C., will not otherwise be harmful to the water resources of the District, will not interfere with the legal rights of others as defined in subsection 17-40.401(8), F.A.C., is not against public policy, will meet general and specific criteria in the document described in subsection 40E-4.091(1)(a), F.A.C., (0) will meet criteria for isolated wetlands, which are found in Appendix 7 of the document described in rule 40E- 4.091(1)(a), F.A.C., (p) will meet the criteria for above ground impoundments, which are found in Appendix 6 of the document described in rule 40E-4.091(1)(a), F.A.C. The SFWMD has adopted certain procedures and criteria contained in a document, referred to as “Basis of Review for Surface Water Management Permit Applications Within The South Florida Water Management District” (BOR). Subsection 40E-4.091(1)(a), F.A.C. incorporates this document by reference into Chapter 40E-4, F.A.C. The BOR is a document that is “described in subsection 40E-4.091(1)(a), F.A.C.,” within the meaning of Rule 40E-4.301(1), F.A.C. The BOR establishes a rebuttable presumption that water quality criteria are met through specified volumetric retention and detention requirements. These performance based criteria are designed to be flexible. CRITERIA FOR THE WRM PERMIT In 1992 DEP entered into an Operating Agreement with the District, which delegated to the District responsibility for issuing wetland resource management (WRM) permits, which are required for dredge and fill activities in wetlands. Both DEP and the District implement the same wetland resource permit and MSSW permit rules. The District agrees with DEP's interpretation and application of the WRM permitting rules and non-rule policy, and applies the same when issuing such permits. Section 403.918, Florida Statutes (1991), provides the pertinent criteria that must be applied by the District in determining whether to grant or deny the WRM permit. That criteria requires the applicant to provide reasonable assurance that water quality standards will not be violated. In addition, for projects in OFW, the applicant must provide reasonable assurance that the project is clearly in the public interest. THE PUBLIC INTEREST TEST The District is required to balance the following criteria, found at Section 403.918(2)(a), Florida Statutes (1991), in determining whether a project is clearly within the public interest: Whether the project will adversely affect the public health, safety, or welfare or the property of others; Whether the project will adversely affect the conservation of fish and wildlife, including endangered species, or their habitats; Whether the project will adversely affect navigation or the flow of water or cause harmful erosion or shoaling; Whether the project will adversely affect the fishing or recreational values or marine productivity in the vicinity of the project; Whether the project will be of a temporary or permanent nature; Whether the project will adversely affect or will enhance significant historical and archaeological resources under the provisions of s.267.061; and The current condition and relative value of functions being performed by areas affected by the proposed activity. MITIGATION If the applicant is unable to otherwise meet the public interest test, the District shall, pursuant to Section 403.918(2)(b), Florida Statutes, “consider measures proposed by or acceptable to the applicant to mitigate adverse effects which may be caused by the project . . .” The District thereafter re-evaluates the project to determine whether the project, as mitigated, meets the public interest test. The criteria for mitigation is found in Chapters 373 and 403, Florida Statutes, Title 40 E (including the Basis of Review) and Rule 62-312, Florida Administrative Code. Rule 62-312.330, Florida Administrative Code, states the general criteria for evaluating mitigation proposals as follows: The goal of the mitigation proposal shall be to offset the expected adverse impact of the project that have resulted in the project being deemed unpermittable such that the resulting project with mitigation is not contrary to the public interest or, in the case of Outstanding Florida Waters, is clearly in the public interest. Each project must be separately evaluated to determine whether the proposed mitigation is sufficient. Rule 62-312.340, Florida Administrative Code, provides guidelines that are to be used in evaluating proposed mitigation projects. GENERAL DESCRIPTION OF THE PROJECT AREA FDOT proposes to widen a 20.4 mile portion of U.S. 1 in southern Dade County and northern Monroe County. Approximately seven miles of the project area is in Monroe County and approximately thirteen miles is in Dade County. The northern terminus of the project is the intersection of U.S. 1 and Card Sound Road, which is located in Dade County south of Florida City. The southern terminus of the project is the intersection of U.S. 1 and Abaco Road on Key Largo in Monroe County. The corridor of the proposed project passes through Sections 6, 7, 16, 18, 21, 27, 28, Township 59 South, Range 39 East; Sections 24, 25, 36, Township 58 South, Range 38 East; Sections 16, 19, 30, 31, Township 58 South, Range 39 East, Sections 16, 30, 31, Township 60 South, Range 40 East; Sections 25, 26, Township 60 South, Ranges 39 East, Dade and Monroe Counties, Florida. U.S. 1 is the main highway between northern Monroe County and southern Dade County. The only other road between Monroe County and Dade County is Card Sound Road. The Florida Keys is designated as an Area of Critical State Concern, pursuant to Section 380.0552, Florida Statutes. The Dade County portion of the road, north of the C- 111 canal, lies within typical Everglades habitat, which is classified as environmentally protected lands of Dade County. Most of the project corridor in Dade County is part of or adjacent to the Everglades National Park. Valuable wetlands exist throughout the project corridor. The following bodies of water will receive discharges if the surface water management system is permitted: C-111 Canal, Jewfish Creek, Lake Surprise, Blackwater Sound, Barnes Sound, Little Blackwater Sound, Long Sound, Manatee Bay, Sarge Lake, andManatee Creek. The receiving bodies of water are Outstanding Florida Waters (OFWs) or are connected to OFWs. THE EXISTING ROADWAY As it presently exists in the project area, U.S. 1 is a two lane undivided highway with two passing zones that are each one mile in length. Each travel lane on the existing facility is twelve feet wide. The existing shoulder on either side of the road consists of four feet of pavement and six feet of grassed area. FDOT Exhibit 7 accurately depicts the existing roadway typical section. Exotic vegetation, generally limited to the areas immediately adjacent to the highway, exist throughout the project corridor. These exotic species are present because FDOT has failed to properly maintain its right of way. A clear zone is an unobstructed area that includes the shoulder of the roadway and typically extends beyond the shoulder. The purpose of the clear zone is to provide a driver who has lost control of his or her vehicle a sufficient clear recovery area to regain control of the vehicle so that it can be maneuvered back onto the road. The clear zone for the existing road is inadequate to provide a safe recovery area. There is at present a two lane bridge over Manatee Creek, a two-lane bridge crossing the C-111 Canal, a bascule bridge, which is a drawbridge, over Jewfish Creek, and a two lane causeway through Lake Surprise. The two existing passing zones are located in Dade County. The first is south of U.S. 1’s intersection with the C-111 canal between mile markers 113-115. The second passing lane is approximately four miles south of the northern terminus of the project between mile markers 120-122. Each existing passing zone is undivided and consists of two northbound lanes and two southbound lanes, with each travel lane being twelve feet in width. The shoulders in the passing zones are the same as for the typical section. A surface water management (SWM) system is defined by Rule 40E-4.021(5), Florida Administrative Code , as being "the collection of devices, improvements or natural systems whereby surface waters are controlled, impounded, or obstructed.". There is no surface water management system presently associated with the road. The roadbed is elevated approximately five feet above mean sea level according to the National Geodetic Vertical Datum and was constructed on the old railroad bed of the Florida East Coast Railroad. No hydrologic culverts have been placed within the roadbed. Consequently, surface water flow between the eastern and western sides of the road north of the C-111 Canal has been cut off. C-109 AND C-111 CANALS In the 1960's, the C-109 and C-111 canals were constructed as part of an overall water management system in the area. As a result of the roadbed and the canals, water has been impounded on the western side of U.S. 1 at a level higher than on the eastern side. Due to cutoff of waterflow by the roadbed embankment, historic freshwater flow between the eastern and western sides of the project area has been restricted, which has resulted in an adverse impact on the Everglades ecosystem north of the C-111 Canal. The restricted water flow has resulted in less fresh water being available for shorter periods of time. Consequently, aquatic life has had reduced opportunities to develop. The restricted flow also has impeded the ability of aquatic life to reach freshwater areas during times of drought. On the east side of the road marine conditions have displaced what naturally should be freshwater conditions. PROJECT HISTORY While FDOT has been aware of traffic safety and hurricane evacuations concerns on the roadway for a long time, the current project originated in 1986 when Monroe County identified this project as a need in its 1986 Comprehensive Plan. Pursuant to agency practice, the proposed project was incorporated into FDOT's five year work program and a study was performed pursuant to FDOT’s Project Development and Environment (PD&E) Manual. FDOT's PD&E manual describes the process by which FDOT determines whether to construct or improve a road. The PD&E process includes an Environmental Impact Statement (EIS) to analyze existing conditions, assess the need for improvement, and develop alternatives. A Draft EIS is performed and circulated for comment to governmental agencies and the public. Based upon comments and further review a Final EIS is prepared. Metric Engineering ("Metric") began the PD&E study of the project in 1988 pursuant to a contract with FDOT. Metric identified seven factors which it concluded supported the need for the project. First, the improved corridor would improve the linkage between the four lane road at the northern terminus and the four lane road at the southern terminus. Second, the project would improve navigation by replacing the existing bascule bridge at Jewfish Creek. Third, the project would improve the level of service for the road. Fourth, the project would improve the safety of the road. Fifth, the project would improve the clearance time for hurricane evacuation. Sixth, the project was consistent with the long range transportation plans adopted by Monroe County. Seventh, the project would accommodate increased traffic, which can be expected with or without the project. Based on the needs evaluation, Metric performed a corridor analysis to determine the best way to get from Florida City to Key Largo, including improving only Card Sound Road, improving only U.S. 1, or improving a combination of the two. Metric concluded that the best resolution was to improve the project corridor. Metric also analyzed various alternatives in an effort to reduce the size of the typical section of the roadway in the U.S. 1 corridor and thereby minimize environmental impacts of the project. Because of concerns from Everglades National Park that no aspects of the project construction occur within its boundaries, FDOT agreed to conduct all construction east of FDOT's existing right of way line. The conclusions of the Metric studies were memorialized in a Final EIS and Final Engineering Report published in 1992. Conclusions regarding alternatives and project needs were then incorporated into the permit application and have continued to be updated. The 1992 version of the project was for a four lane roadway with four lane bridges throughout the project corridor. Subsequent to its June 6, 1994, permit applications to the District for a four lane roadway, FDOT went through an extensive process of providing the District with additional information in an effort to provide the District with the necessary reasonable assurance that the proposed project would comply with the permit criteria. The final series of modifications contained the three lane alternative, which will be described in detail below and is now the subject of this proceeding. The three lane proposal is a compromise that FDOT agreed to in an effort to minimize the direct, secondary, and cumulative impacts of the project. Monroe County passed Resolution No. 315-1995 on September 7, 1995, asking FDOT to build a three-lane road on a four-lane embankment. This resolution provided, in part, that “. . . Monroe County finds that the '3-lane alternative' as described in the Statement of Agency Commitments is the most viable proposal of those considered, because it balances the needs for a widened highway with safeguards designed to address secondary impacts.” The secondary impacts referred to in the resolution included concerns that two southbound lanes would result in more growth. The rationale behind the resolution was that more growth would result from two southbound lanes than from one southbound lane with the proposed passing zones. In response to the request of Monroe County and in response to a similar request made by the District, FDOT notified the District by letter dated September 5, 1996 of FDOT's decision to redesign the project to change the roadway from four to three lanes. FDOT HAS MINIMIZED THE IMPACTS OF THE PROJECT During the PD&E process prior to permit application FDOT studied project needs and alternative alignments, and conducted corridor analyses. FDOT originally considered a proposal that included approximately 250 acres of wetlands impacts. At the District's suggestion, FDOT revised its proposal prior to the permit application to reduce the wetland impacts and project footprint. The application submitted contained approximately 165 acres of impact. FDOT changed the typical section of the proposed roadway again after substantial interagency coordination in an effort to reduce wetlands impacts even further. FDOT agreed to reduce the footprint by changing the design of the median from 22 feet and a Jersey barrier (which is a minimum barrier) to 20 feet with a tri-beam rail barrier. The more substantial barrier was added because the median was narrowed. Additionally, instead of ten-foot paved shoulders on each side of the median, FDOT would use two-foot paved shoulders with sixteen feet of grass in the middle. These minimization efforts resulted in a wetland impacts decrease from 164 acres to 149.07 acres, the current impact of the project. Avoidance, or choosing alternate routes to avoid impacts to wetlands, was not a possible option because only wetlands and open waters exist between the northern and southern terminus of the project. FDOT explored all reasonable alternatives to the proposed project, including a two lane alternative proposed by a consultant for FBII. As discussed below, FDOT did not adopt the two-lane alternative, because the alternative did not address all of FDOT's identified needs for the project. FBII prepared a report with a two-lane alternative to the proposed project. FBII's original proposal included one 12-foot northbound lane with a 10-foot paved shoulder covered with thermoplastic rumble strips to deter vehicular use of the shoulder. In the southbound direction, FBII proposed a 12-foot travel lane with a 4-foot paved shoulder, essentially the same as currently exists. That proposal was analyzed by Metric Engineering on behalf of FDOT. FDOT rejected the FBII alternative for several reasons. First, though the 10-foot northbound shoulder theoretically may be used by cars during hurricane evacuation, removal of the rumble strips would be impractical due to lack of time to do so under threat of a hurricane, and due to the costs involved. It would be unrealistic to require people to otherwise drive over the rumble strips, without removal, because they are designed to prevent such access. Using the 10-foot shoulder during an evacuation would result in there being no shoulder area to remove accident vehicles from the roadway which would otherwise threaten to restrict the flow of traffic or cease it altogether. The reduced width of the shoulder lane below the standard 12-foot lane would also decrease the flow of evacuees. FBII's proposal for a two-lane fixed-height bridge at Jewfish Creek would not completely eliminate rear-end collisions at the bridge. The two-lane alternative proposed by FBII is not a signed and sealed cross section. The proposal by FBII does not include the area necessary for a SWM system or for clear zones. FBII did not do an analysis to determine whether its proposal complies with pertinent FDOT roadway and traffic design standards or with pertinent highway safety and improvement standards. The FBII proposal does not account for removal of the Lake Surprise causeway or construction related impacts from barge traffic. FBII did not do a wetlands survey to determine the impact of its two-lane proposal. At the Final Hearing, Petitioners presented for the first time a new proposal to use "flexible diverters" to pave a third northbound lane and to block that lane from travel traffic with poles. However, no research was conducted into the feasibility of such a proposal, nor was it adequately thought out. Such a use of "flexible diverters" is unprecedented in FDOT's history, is impractical to implement, and would violate FDOT's design standards contained in its Manual on Uniform Traffic Control Devices. Petitioners also presented for the first time at the Final Hearing a proposal to add an 8 to 10 foot paved northbound shoulder which could be converted to a travel lane with traffic control cones in the event of an evacuation. This plan is also not feasible, because the resulting lanes would not be wide enough to safely accommodate evacuating traffic, and because the contradiction between existing road striping and the placement of cones would likely cause accidents, which would halt evacuation. The proposals submitted by FBII do not sufficiently improve hurricane evacuation or traffic safety and, consequently, are not acceptable alternatives to the project. FDOT can do nothing else to minimize the impacts of the project and still address the needs for the project. Minimization of wetlands impacts was accomplished to the greatest extent possible. FDOT has proposed mitigation to offset the impacts that could not be avoided. THE PROPOSED PROJECT - IN GENERAL STIPULATION AS TO DESIGN AND CONSTRUCTION Petitioners stipulated that the design and construction specifications of the roadway proposed to be permitted in this case comply with all applicable design and construction standards for structural integrity, and adequately describe the three-lane divided roadway proposed to be constructed on a four-lane roadbed/embankment. PROPOSED LANES, SHOULDERS, AND MEDIAN FDOT proposes to widen the roadway in the project area to a three lane divided roadway with two northbound lanes and one southbound lane, plus three passing zones. The proposed project will be constructed on a four lane roadbed embankment. FDOT does not presently have plans to add the fourth lane to this roadway. FDOT Exhibit 8 contains an accurate description of the proposed typical section of the roadway. The typical section will consist of two twelve-foot northbound lanes with a six-foot paved shoulder and a four foot stabilized area adjacent to the paved shoulder; a twenty-foot median consisting of a two-foot paved shoulder, sixteen feet of grass and a tri-beam guardrail in the middle as a separator; and one twelve-foot southbound lane with an eight-foot paved shoulder. The proposed typical section also includes a storm water management system that will be described in more detail below. The proposed typical section includes a clear zone thirty feet in width, which is adequate. THE THREE PASSING ZONES The existing passing zone located in Dade County between mile markers 113 and 115 is one mile in length. FDOT proposes to alter this passing zone to 1.44 miles in length. The existing passing zone located in Dade County between mile markers 120 and 122 is also one mile in length. FDOT proposes to alter this passing zone to 2 miles in length. In addition, FDOT proposes to construct a 1.5 mile long passing zone between mile markers 110 and 112 in Monroe County. If permitted, the proposed project will include 2 passing zones in Dade County and 1 passing zone in Monroe County, for a total of 3 passing zones. The total length of the passing zones will equal 4.94 miles. ELEVATION There are no plans to change the elevation of the existing roadway. HYDROLOGIC CULVERTS The project contemplates the construction of 25 hydrologic culverts north of the C-111 Canal. These culverts will remain capped until further hydrological studies are completed and input from all concerned regulatory agencies can be obtained. It has not yet been determined how these culverts will be utilized to maximize the improvement to the ecosystem north of the C-111 Canal. WILDLIFE CROSSINGS INCLUDING THE C-111 BRIDGE The project contemplates the construction of three wildlife crossings north of the C-111 Canal in Dade County with fencing designed to funnel wildlife through the crossing. These crossing, sometimes referred to in the record as “panther crossings” are located between mile markers 118-119, 122-123, and 126-127 and will be constructed as overland bridges. In addition, the replacement bridge over the C-111 Canal (located between mile markers 116-117 in Dade County) is intended to serve as a wildlife crossing and will also employ fencing to funnel wildlife through the crossing. All four of these structures will be constructed as four-lane bridges, but will be striped for three lanes with rumble strips on the southbound fourth lane to discourage vehicular traffic in that lane. There will be an eight foot outside shoulder. FDOT proposes to construct 18 culverts south of the C-111 Canal for crossings by crocodiles, alligators, manatees, and other wildlife. These crossings will consist of 15 box culverts and 3 bridges. MANATEE CREEK BRIDGE The proposed bridge at Manatee Creek would be constructed as a four lane bridge, but would be striped for three lanes with rumble strips on the southbound fourth lane to discourage vehicular travel in that lane. There would be an eight foot outside shoulder. BRIDGING JEWFISH CREEK AND LAKE SURPRISE Jewfish Creek, which is part of the Intracoastal Waterway, and Lake Surprise would be bridged by a continuous structure. The Jewfish Creek bascule bridge would be replaced by a high-level four-lane fixed bridge. The Lake Surprise causeway would be replaced by a low-level four-lane bridge. The total distance for this bridging is approximately 2.35 miles. AREA OF PROJECT THAT WILL BE OPERATED WITH FOUR-LANES The three passing lanes (4.94 miles) and the bridge over Jewfish Creek and Lake Surprise (2.35 miles) would be operated with four lanes. Those areas total 7.29 miles of the 20.4 mile project corridor. Approximately 43 percent of the proposed roadway would have four lanes of pavement. Excluding the areas where the fourth lane will be blocked from travel with rumble strips, only 35 percent of the completed project will contain four travel lanes. This area consists of the three passing zones and the bridges over Jewfish Creek and Lake Surprise. THE PROPOSED SWM SYSTEM The proposed project would provide for a SWM system consisting of inlets, culverts, swales, berms and dry/wet retention areas. For the typical roadway section, runoff from the paved roadway surfaces will be directed to roadside swales designed to provide retention for 50 percent of 2.5 inches times the impervious area. The SWM system for the bridges will collect runoff in inlets and culverts and direct it to either swales or dry or wet retention ponds. The berms of the SWM system provide additional protection by restricting spills of pollutants, such as petroleum from overturned tankers or other vehicle accidents, from running into the surrounding waters. The berms and swales of the SWM are designed to catch pollutants and prevent their discharge into the surrounding waters. FDOT Exhibit 18 consists of four separate drainage reports submitted to the District in 1995 in connection with the project, one report for each section of the project. The reports accurately document the drainage calculations, the drainage design, the rationale behind the drainage design, and compliance of the design with the laws and regulations of the permitting agencies for the original four-lane proposal. On or about September 5, 1995, FDOT submitted revised drainage calculations to the District, determining the amount of stormwater treatment for the three-lane project. The revised calculations established that at least 95% percent of all stormwater runoff from the project would be captured in the proposed SWM system. Because the swale design was based on the originally proposed four-lane road, retention will be in excess of the required volume for most sections of the roadway. The required retention volume for this project is approximately 166 percent of what is required by the BOR. The surface and subsurface geology of the roadway consists of Miami oolite limestone overlain with Perrine maral. Underlying this is Thompson formation, anastasia and Key Largo limestone. Based on these constituencies, the swales proposed by the SWM system would be effective in rapidly removing heavy metals and phosphorous. The revised calculations established that approximately five percent of the project area will not have a SWM system. These areas will not have a SWM system because properly-sized retention systems in those areas can not be constructed without causing a disproportionate, adverse impact to surrounding wetlands. FDOT has provided reasonable assurances that the proposed SWM system’s total water quality treatment exceeds the District's permitting requirements and provides sufficient treatment to exceed the BOR requirements. The water discharged from the proposed system would be of higher quality than that currently discharged, which is not treated. FDOT has provided reasonable assurances that the proposed SWM system complies with the permitting criteria found in Rule 40E.301(1)(a)-(p), Florida Administrative Code. The following findings are made as to that criteria. Rule 40E-4.301(1)(a), F.A.C. The parties stipulated that Rule 40E-4.301(1)(a), F.A.C., pertaining to flood protection and the adequacy of drainage, is not at issue in this proceeding. Rule 40E-4.301(1)(b), F.A.C. The quality of water being discharged from the SWM system will be of substantially higher quality than the existing discharges. Consequently, it is concluded that the system will not cause adverse water quality impacts within the meaning of Rule 40E-4.301(1)(b), F.A.C. In addition, the evidence established that there will likely be less water discharged from the roadway if the project is constructed because of the amounts of water that will likely be retained in the swales that are a part of the SWM systems. Rule 40E-4.301(1)(c), F.A.C. Because the receiving bodies of water are designated Outstanding Florida Waters, the District is required to apply the DEP's most stringent water quality requirements -- the antidegredation requirements for discharge to OFWs, to this project. Those standards will be discussed in more detail below. The evidence established that the proposed project will not violate those requirements. Rule 40E-4.301(1)(d), F.A.C. Impacts to sources of water are not at issue. The District reviewed the potential effect of the SWM system upon on-site and off-site impacts to surface or groundwater levels and flows. The evidence supports the District's conclusion that no adverse impacts will be caused. Petitioners failed to present any evidence on groundwater levels and flows. Consequently, it is found that the criteria found at Rule 40E-4.301(1)(d), F.A.C., has been satisfied. The 25 hydrologic culverts north of C-111 have the potential to re-establish historic surface water flow in the area. They were sized, based on rainstorm events, to help equalize water levels from one side of the road to the other. The culverts are capable of transferring water from west to east to assist in the historic restoration of flows. In order to assure the proper usage of the culverts, they will remain gated until the District develops a management plan in conjunction with other agencies. The District will determine the maintenance entity. The FKAA water main runs beneath this section of the road. As a result, there is no other more hydrologically efficient alternative for the placement of the culverts. The culverts would also provide a means for overwash from storm events, over the U.S. 1 roadbed, to flow back to its point of origin, stabilizing the roadbed and allowing release of the accumulated salt water. Rule 40E-4.301(1)(e), F.A.C. In addition to providing for a net improvement in water quality, the project will offset any adverse impacts through mitigation and other environmental enhancements for which no mitigation credits are being assigned, as described below. Rule 40E-4.301(1)(f), F.A.C. FDOT has a history of adequate maintenance of SWM systems, and has provided reasonable assurance that it has the staff and budget to comply with District operation and maintenance requirements. FDOT will also be able to comply with the District's requirements to control exotic plants and other foliage along project corridor. Rule 40E-4.301(1)(g), F.A.C. The SWM system will not adversely affect public health and safety. The dispute as to the public interest test focused more on the WRM permitting requirements. Findings as to the public interest test are discussed in more detail below. Rule 40E-4.301(1)(h), F.A.C. The evidence established that the SFM system is consistent with State Water Policy. Rule 40E-4.301(1)(i), F.A.C. This project does not pertain to a DRI and, consequently, this criteria is not applicable. Rule 40E-4.301(1)(j), F.A.C. There are no basin criteria applicable to this project. Rule 40E-4.301(1)(k), F.A.C. The evidence established that the SWM system will not be harmful to the water resources of the District. While there will be adverse environmental impacts caused by the project, those adverse impacts have, as will be discussed in more detail below, adequately offset by mitigation. Rule 40E-4.301(1)(l), F.A.C. This issue was not at issue in this proceeding. Rule 40E-4.301(1)(m), F.A.C. As will be discussed in greater detail in a subsequent section of this Recommended Order, the project is not against public policy. For the reasons set forth in that subsequent section, it is found that the project is clearly in the public interest. Rule 40E-4.301(1)(n), F.A.C. Rule 40E-4.091(1)(a), F.A.C., constitutes the BOR. As discussed in detail above, the SWM system complies with the BOR. Rule 40E-4.301(1)(o), F.A.C. There are no isolated wetlands pertaining to this project. Rule 40E-4.301(1)(p), F.A.C. There are no above ground impoundments, as described in Appendix 6 of the BOR, pertaining to this project. WATER QUALITY - DISCHARGES INTO OFW Because the project will involve discharges into Outstanding Florida Waters, it was necessary for FDOT to establish that the discharges from the SFW system will not degrade those OFWs. The evidence established that FDOT's proposed project complies with and exceeds applicable water quality standards and permitting criteria. There will be no significant degradation of ambient water quality as a result of the project. It is expected that there will be a net improvement in ambient water quality resulting from the proposed project, as opposed to the continued degradation if nothing is done to treat stormwater runoff. In FDOT Exhibit 46, FDOT provided baseline water quality data in the form of STORET data for waters adjacent to the project area. STORET is a centralized repository and database for water quality data throughout Florida. It is Florida's principal source of water quality data. STORET contains the best scientific database on water quality in Florida. The STORET data set forth in FDOT Exhibit 46 provided sufficient evidence on ambient water quality for the waters adjacent to the proposed project. In addition to providing the water quality data in FDOT Exhibit 46, FDOT is required by Special Permit Condition 37 to submit appropriate water quality data in the surrounding waters prior to any construction activities. SFWMD Exhibits 5 and 6 contain amendments to Proposed Agency Action made after the beginning of the formal hearing. These amendments include a requirement that an appropriate water quality monitoring plan be submitted within 30 days of the permit issuance. FDOT has provided reasonable assurances that water quality standards will be met and that there will be appropriate water quality monitoring during construction. DIRECT IMPACTS OF THE PROJECT The proposed roadway design will result in the following direct impacts to wetlands adjacent to the roadway corridor: 1) the dredging of 11,028 cubic yards of material from 2.1 acres, 2) the placement of 1,689,553 cubic yards over 147.0 acres of wetlands, and 3) 6.9 acres of (potential) permanent impact due to shading and 4.1 acres (potential) of temporary impacts from the Jewfish Creek Bridge construction activities to seagrass habitat. In order to determine the project's direct impacts, the area surrounding the project was surveyed to determine the number of affected acres. This was done by using a computer aided design ("CAD") system, and by categorizing the various forms of wetlands and associated flora and fauna into the following communities: mangrove, emergent freshwater, open water, and tidal, consisting of seagrass and non-vegetated bottoms. Using these categories and the CAD system, every square foot of direct impacts were accounted for. The adverse direct wetland and surface water impacts of this project are as follows: 1) 27.83 acres Non- Vegetated Tidal Bottom; 2) 11.27 acres Seagrasses; 3) 46.85 acres Mangroves; 4) 42.35 acres Sawgrass/Cattail/Spikerush; 5) 14.31 acres Shrub Wetlands; and 6) 6.46 acres Open Fresh Water; totaling 149.07 acres. Though some wetlands to be impacted may be of lesser quality, FDOT stipulated that all wetlands to be directly impacted by the project should be considered to be high quality wetlands for the purpose of mitigating the impacts. The impacted wetlands are part of larger wetland systems. Petitioners assert that the District should have required studies as to impacts as to the larger wetland systems. The evidence established that the District appropriately considered the type and location of the wetlands involved so that additional study suggested by Petitioners was unnecessary. Petitioners also assert that impacts to isolated wetlands should have been studied. The evidence established that there will be no such impacts. SECONDARY AND CUMULATIVE IMPACTS RECOGNIZED BY SFWMD In addition to the direct impacts of the project, the District is required to analyze secondary and cumulative impacts. A project's secondary impacts are those that, though outside of the project footprint, are very closely linked and causally related to the project. This is a "but for" test. Secondary impacts are those impacts which, if not for the proposed project, would not occur. Both positive and negative secondary impacts are considered. When there are both positive and negative secondary impacts caused by a project, the permitting agency must consider the severity of the impacts and balance these together with the other factors in the public interest test to determine whether or not the project is clearly in the public interest. WRM statutes, and DEP rules and policies pertaining to those statutes do not regulate growth or traffic increases, per se. Only if such increases are very closely linked and causally related to the project will they be considered. The District identified several secondary impacts that would be temporary in nature since they would occur while the project is being constructed. One is the use of a barge facility, primarily at Jewfish Creek, where the anchoring of the barge may result in temporary impacts to seagrass during construction. This impact is addressed by a component of the seagrass mitigation at Boca Chica, discussed below. Another impact is turbidity associated with the dredge and fill and the barge activities. That issue is appropriately addressed by permit conditions, through the use of turbidity control screens and other techniques. The District also identified secondary impacts directly associated with the project footprint that would be permanent in nature. The removal of the exotic vegetation potentially opens up the areas adjacent to the road north of the C-111 canal to off-road vehicles or four-wheel driving and the potential impacts caused by those vehicles. That impact is appropriately addressed by fencing north of the C-111 canal. When a road is widened, animals have a greater distance to travel back and forth from one side of the road to the other. A wider road exposes such animals to greater risk of being hit by a motor vehicle while crossing the road. That impact is addressed in this project by the fencing, the wildlife crossings, and the wildlife box culverts. The crossings are designed for large mammals and some species, such as the Indigo snake, will likely not use these crossings. The wildlife crossings will not entirely mimic the crossing patterns of all wildlife that need to cross U.S. 1 and will result in some wildlife habitat fragmentation. The fencing that will be erected to funnel wildlife through the crossings will fragment the habitat of some species by altering wildlife crossing patterns and blocking access of some species to certain areas of habitat. The greater weight of the evidence established that any habitat fragmentation should, when compared to existing conditions, be minimal. The District appropriately evaluated the advantages and disadvantages of using wildlife crossing and hydrological culverts and appropriately concluded that there would be a net benefit to wildlife as a result of their construction. The District properly concluded that the culverts, bridges and fencing located south of the C-111 canal, construction of wildlife crossings and fencing north of the C- 111 canal, construction of the hydrologic culverts, and removal of the Lake Surprise Causeway are positive secondary benefits of the project. These benefits should be considered when applying the public interest test. THE FKAA PIPELINE RELOCATION The project requires the relocation of two segments of the existing pipe owned by the Florida Keys Aqueduct Authority (FKAA) around Jewfish Creek Bridge. The segments total approximately 1.5 miles. The District inspected the area where the pipeline will be relocated to assist in determining its impact. The pipeline relocation is a temporary disturbance during construction. It is a small linear facility, which will not generate pollution in and of itself. The pipeline relocation is not expected to result in a violation of State water quality standards. The FKAA is responsible for obtaining the necessary permits for the relocation. Direct impacts to wetlands will occur in a 4 to 5 foot wide strip along the length of the relocated aqueduct. The FKAA has submitted a permit application to the DEP for a permit to relocate the aqueduct. DEP believes that adequate mitigation can be achieved to make the project permittable. Once the FKAA submits an adequate mitigation plan, then relocation of the aqueduct will not be an adverse secondary impact caused by the U.S. 1 project. The permit for the subject project should contain a condition that the FKAA obtain a permit for the relocation of these two segments of its pipeline. THE C-111 BOAT RAMP There is an existing boat ramp designed for small boats to access District canals that is located on the north side of the C-111 canal. As a result of the proposed project, it will be relocated to the southern side of the project. This relocation is a relatively minor project requiring a cut in the canal bank and a fourteen-foot wide slab for the boat ramp. When the District considered the potential impacts associated with this relocation in conjunction with the impact of the proposed project, it was determined to be a relatively insignificant impact in terms of the project as a whole. Relocation of the boat ramp is not expected to result in a violation of state water quality standards. All direct, cumulative, and secondary impacts, whether positive or negative, should be considered in balancing the public interest test. ARE THERE ADDITIONAL SECONDARY AND CUMULATIVE IMPACTS Petitioners assert that there are additional cumulative and secondary impacts that the District failed to consider. Petitioners argue that the project cannot meet permitting criteria if those additional impacts are considered. The additional impacts pertain to additional development throughout Monroe County because of the “rate of growth ordinance” (ROGO), additional development along the project corridor, impacts to the coral reefs of the Keys, impacts to Key Deer, generalized impacts, and impacts from increased number of “day trippers." For the reasons discussed below, it is found that the District has considered all appropriate direct, secondary, and cumulative impacts of the project. The additional impacts that Petitioners assert should have been considered are not causally connected or directly linked to the project. THE RATE OF GROWTH ORDINANCE Monroe County adopted its Year 2010 Comprehensive Plan (the "Plan") to meet the requirements of Chapter 163, F.S. The Plan, adopted May 15, 1993, is unusual in that the County limits future growth based on a carrying capacity analysis of its hurricane evacuation clearance time. No other jurisdiction in Florida, and few others in the United States, have used a carrying capacity planning approach. To implement the carrying capacity limitation, Monroe County determined the total number of dwelling units that could be permitted while maintaining an acceptable hurricane evacuation clearance time of 24 hours. This number of dwelling units, less an allowance for vested development and development in municipalities, was the basis for a ROGO that was adopted by the County in 1992. The ROGO allocates the available units at a uniform annual rate of growth (currently, 255 units per year). The ROGO regulates all proposed new residential buildings, including hotels, motels, and other transient tourist accommodations as well as permanent residences. The number of building permits that Monroe County can issue is, at present, directly related to how rapidly the County can be evacuated in the event of a hurricane. The lower the clearance time, the greater the number of permits that can be issued. The Comprehensive Plan requires that the County be able to evacuate within a 24-hour period. As of March 7, 1995, the hurricane evacuation time for Monroe County was determined to be 21.25 hours.1 The project is expected to reduce by six or seven hours the modeled hurricane evacuation capacity for Monroe County, regardless of whether it consists of three or four lanes. This is because both the three lane and four lane plans provide for two northbound lanes. Because of the rate of growth provisions in county law, this reduction of clearance times results directly in an increase in the number of building permits that the county can issue annually. Under ROGO, Monroe County can, with this project, issue 255 permits each year through the year 2026. Without this project, Monroe County can issue 255 permits each year only through the year 2001. Alternatively, without this project, the county can issue 88 permits each year through the year 2010 if it chooses to issue permits over a longer period of time. Following extensive litigation before the Division of Administrative Hearings in an unrelated proceeding2, the Administration Commission entered a final order on December 12, 1995, that approved approximately 97 percent of the Plan. In addition, the Administration Commission has published a proposed rule to bring the remainder of the Plan into compliance and assure its financial feasibility. The central feature of the proposed rule is a five- year work program, with annual reviews by the Administration Commission. It is likely that the proposed rule will eventually result in the complete revision of the ROGO. The proposed rule provides that Monroe County's annual rate of growth be revised within five years, no later than December 31, 2001, "to establish a rate of growth and a set of development standards that ensure that any and all new development does not exceed the capacity of the county's environment and marine systems." A carrying capacity study will comprehensively assess water quality, habitat protection, and public facility issues to determine the capacity of the Keys to sustain further development. The proposed project is but one of many factors that will be considered in future rate of growth regulations. If the expected revisions occur, it would be speculative to predict what development would be allowed. While the studies are underway the rate of growth will remain at 255 units per year. The rate of growth will be reviewed annually, and may be reduced a minimum of 20% if the goals of the studies are not being met. The DCA has determined that Monroe County’s Comprehensive Plan and its land development regulations are sufficient to prevent or mitigate any potential adverse secondary impacts of the project caused by development. The DCA has consistently supported the proposed project, even in its earlier four-lane configuration, because it was consistent with Monroe County's 1986 Comprehensive Plan, and because the project would improve hurricane evacuation clearance times and improve water quality in the vicinity of the roadway. The 1986 plan supported widening of the roadway to four lanes based on projected travel demand. The DCA prefers the current, three-lane proposal to the earlier four-lane. On September 7, 1995, the Monroe County Commission adopted Resolution 315-1995 in support of the proposed project because "it balances the needs for a widened highway with safeguards designed to address secondary impacts." Lorenzo Aghemo, an expert in comprehensive planning, served as Monroe County Planning Director during the development of the Plan and ROGO. In Mr. Aghemo's opinion, the widening of the roadway to either three or four lanes would generate minimal growth pressure in Monroe County, particularly because the Plan limits the rate of growth. Because the Keys are designated by Section 380.0552, F.S., as an area of critical state concern, the DCA is charged with oversight of Monroe County's Comprehensive Plan, its LDRs, and all development that takes place in Monroe County. Additionally, the Administration Commission may amend Monroe County's plan or regulations by rule (See Section 380.0552(9), F.S.). There is virtually no action that Monroe County can take related to the use of land without review and approval of a state agency. The Administration Commission’s proposed rule demonstrates its intent to revise comprehensively Monroe County's ROGO within five years to ensure that future development does not exceed the capacity of the Keys' environmental resources. It also demonstrates the Administration Commission's intention to closely monitor growth and development in the Keys during the five-year study period. Some of the studies required by the proposed rule are already underway: 1) the DCA has entered into a contract with the ACOE to complete the environmental carrying capacity study; 2) the HRS study of advanced on-site waste water treatment systems is underway; 3) Monroe County is developing the required Marathon central sewer facilities plan; and 4) Monroe County and HRS have begun the cesspit identification and elimination process. Caution should be exercised in relying on this or on any other proposed rule. Likewise, caution should be exercised in relying on changes to ROGO that may or may not occur. It is likely that the present status of the law will be changed in the near future so that future development will be based on environmental carrying capacity as opposed to hurricane evacuation clearance times. However, for the purposes of this proceeding the District should accept the fact that the issuance of future building permits is closely linked and causally related to the project. Consequently, it is found that under the present status of the law, the issuance of additional building permits in Monroe County is closely linked or causally related to the project. MONROE COUNTY LDRS AND DCA OVERSIGHT Although Petitioners established that there is a causal relation between the project and the existing status of the law governing the number of building permits that can issued in the future, the evidence was insufficient to establish at a level above speculation that adverse environmental impacts will result because of the issuance of those building permits. The Monroe County Comprehensive Plan contains land development regulations that govern all development in Monroe County. These regulations are among the most stringent in the State and are designed to avoid or minimize adverse environmental impacts caused by development. All development orders in Monroe County are closely scrutinized by the Department of Community Affairs to ensure compliance with applicable permitting criteria. Those regulations and the DCA’s close scrutiny are intervening factors that break any causal relation between the project and the speculative adverse environmental impacts that the Petitioners assert will be caused by future issuance of building permits by Monroe County. Petitioners failed to establish that the impacts of future development are very closely linked or causally related to the project. Consequently, it is found that such impacts are not secondary or cumulative impacts of the project. DEVELOPMENT ALONG THE PROJECT CORRIDOR A major portion of the area next to the road has little or no development potential because it is either water, land in public ownership, or land slated for public ownership. The areas east of the road are mostly in private ownership, but are primarily submerged lands and mangrove areas. The Crocodile Lakes National Wildlife Refuge is federally owned and is managed by the U.S. Fish and Wildlife Service (USFWS). The Southern Glades lands, located immediately west of the project and Everglades National Park (ENP) in Dade County, have been acquired by the District and are managed by the Florida Game and Freshwater fish Commission (FGFWFC). The Model Lands Basin in Dade County is in private ownership but proposed for public acquisition in the future. The land adjoining the roadway in Dade County is designated as open area or environmentally sensitive. Almost half of the land along Monroe County's portion of the roadway is in public ownership. At least 90% of the land in private ownership is mangroves or wetlands that cannot be developed. The small area of uplands is currently being used by a resort marina which will not be allowed to develop further under the new comprehensive plan. There is very little potential for future development in the project area. The comprehensive plan designation for areas in Dade County are open space, and the ones in Monroe County have the conservation designation. The District's regulatory programs consider areas adjacent to the project as sensitive wetland habitats. Based on the District's regulatory authority and comprehensive plan designation for those lands, which would have to be obtained prior to obtaining a permit for development, it is very unlikely that those lands could be developed. Florida Rock and Sand Co. (FRS) has a permit to mine approximately 1,100 acres of wetlands. As part of its mitigation program, FRS will donate this land to the District once its mining and mitigation projects are complete. The FRS mitigation lands are preserved as a permit condition and will ultimately be transferred to the District. This land will not be developed. In addition, the District established that the U.S. 1 project and the FRS project do not constitute a cumulative impact that the District failed to consider. The evidence established that development along the project corridor will not be a secondary or cumulative impact of the project. IMPACTS ON CORAL REEF SYSTEM The evidence was insufficient to establish a close link or causal connection between the project and the coral reef system. As reflected elsewhere, it is found that there will be no degradation of ambient water quality as a result of the project. Therefore, there is no need to resolve the conflicting testimony as to the present status of the coral reef system. IMPACT ON KEY DEER There are no key deer in the project area. The nearest key deer habitat, Big Pine Key, is approximately 70 miles from the southern terminus of the project. The evidence is insufficient to establish that there is a very closely linked and causally related connection between the project and key deer mortality on Big Pine Key. GENERALIZED IMPACTS The Petitioners presented certain opinion testimony that the Keys cannot be developed in an environmentally sensitive manner because of potential adverse impacts of new development in Monroe County, or new boats operating in the waters of the Florida Keys. The credibility of that testimony need not be evaluated because the evidence was not sufficient to tie those generalized concerns into the specific regulatory criteria of the permitting agency. There was insufficient evidence to establish that those alleged impacts would be very closely linked or causally related to the proposed project. DAY TRIPPERS Induced demand is new travel that occurs solely because additional capacity is added to a highway. Petitioners' transportation experts, Michael Replogle and Robert Morris, testified that FDOT's traffic studies, and FDOT's projected rate of traffic growth of approximately 3 percent annually, are incorrect because the studies do not predict the amount of "induced demand" that would result from the proposed project. Petitioners assert that induced demand would generate an unknown number of people who drive to the Keys for the day from south Dade County, referred to as “day trippers,” will have an impact on the Keys that has not been evaluated. The assertion that this potential impact has not been analyzed is rejected as being contrary to the greater weight of the evidence. Induced demand is accounted for in Monroe County's Long Range Transportation Plan, which was never evaluated by Mr. Replogle or Mr. Morris. The Long Range Transportation Plan was prepared by an experienced traffic engineering consulting firm, Barton-Aschman, using an FDOT- approved traffic demand model, the FSUTMS model, that includes all traffic generators and attractors, and all travel on U.S. 1 on weekdays and weekends. The FSUTMS model does not restrict demand based on the existing road capacity. The model uses an "unrestrained assignment" that incorporates the total predicted trip generation on recreational facilities, hotels, and all other attractors. The Long Range Traffic Plan was used to develop the Monroe County Comprehensive Plan, which takes into consideration the projected increases in traffic and makes appropriate provisions for those increases. FDOT has provided reasonable assurances that it has properly projected the amount of traffic for the project corridor after the project is completed and that the projected increases have been appropriately addressed by Monroe County's Comprehensive Plan. MITIGATION - IN GENERAL For the reasons discussed above, it is found that there are no secondary or cumulative impacts that the District failed to consider. Petitioners also contend that the mitigation proposal is insufficient to offset the direct and secondary impacts recognized by the District. This is a large dredge and fill project that will permanently fill 149 acres of wetlands. The wetlands that will be adversely impacted by the project include OFWs that provide a great variety of functions and serve as habitat for fish and wildlife, including threatened and endangered species. The wetlands are unique and of high quality. Mitigation for direct, secondary and cumulative impacts was considered as part of the permit evaluation. In- kind mitigation is considered to be most effective, but out- of-kind mitigation may be offered by the applicant where it is impractical to conduct in-kind mitigation due to historic changes in the project area or sensitivity of the habitat type for which mitigation is offered. Such mitigation is also appropriate to address regional alteration of an ecosystem, such as the Everglades ecosystem alteration caused by the original roadway embankment. FDOT developed a conceptual mitigation plan that took into account project impacts on the freshwater, marine and estuarine components of the ecosystems involved, as well as the impacts on threatened and endangered species of wildlife which may be affected by the project. FDOT coordinated the plan's development with the National Parks Service, U.S. Fish and Wildlife Service, the Army Corps of Engineers, the National Marine Fisheries Service, the U.S. Environmental Protection Agency, the Dade County Department of Environmental Resources Management, the Florida Game and Fresh Water Fish Commission, and the Florida Department of Environmental Protection. The conceptual mitigation plan evolved as a result of project modifications and agency comments into what is now proposed as mitigation for the project. The current proposal is summarized in FDOT Exhibit 26, consisting of Attachment H to FDOT's SWM and WRM permit applications. The timing of their construction falls into two general categories: mitigation previously permitted and concurrent mitigation. UPFRONT MITIGATION Typically, mitigation is done concurrently with project construction rather than prior to permit issuance. Mitigation is often done afterwards because of construction timing constraints. Here, FDOT applied for and, in May 1994 received, permits to conduct mitigation prior to applying for the permits at issue, with the understanding that performance of these activities does not require the District to issue permits for the proposed projects. A total of 385.22 acres of mitigation has already been completed. The applicant received 203.02 mitigation credits from the District on May 12, 1994, for several mitigation projects that the applicant proposes to apply to the proposed U.S. 1 widening project provided it is approved. Table 2 of Attachment H to FDOT Exhibit 26 sets forth the four mitigation projects that constitutes the up- front portion of the mitigation for the project. This table sets forth the acres mitigated, the conversion factor for the mitigation, and the resulting mitigation credit awarded. The four mitigation activities already authorized are: enhancement of the wetland habitat in the Harrison Tract located adjacent to Barnes Sound within the Crocodile Lakes National Wildlife Refuge on the north end of Key Largo (70.37 acres credit for 252.6 acres of restoration); removal of the spoil mounds on the eastern bank of the C-111 canal east of U.S. 1 located on the District’s ROW (10.65 acres credit); the back filling of the C-109 canal levee located on the District ROW within the Southern Glades Save Our River project (112.7 acres credit); and the removal of the roadside spoil mounds on the west side of U.S. 1 located between C-111 and the Dade Work Camp Road within the District’s Southern Glades Save Our Rivers Project (9.30 acres credit). The mitigation projects pertaining to the roadside spoil removal along U.S. 1, the backfill of the C-109 Canal, and the removal of spoil along the C-111 Canal are similar projects because they each involve existing deep ditches cut through wetlands. When these deep ditches were cut, the spoil material from the ditch was deposited alongside the ditch. This resulted in areas that were previously Everglades wetlands becoming spoil, supporting the growth of exotic species and, for the most part, not exhibiting wetland functions. FDOT is proceeding with the backfilling the C-109 canal located between mile markers 122.5 and 117, and removal of the corresponding spoil mounds created during construction of the C-109 canal. In connection with this mitigation, marsh areas, tree islands and deep water aquatic refugia have been restored. In this area, there has been considerable attraction of wildlife subsequent to restoration, including otters, alligators, and turtles, which could not previously use the habitat because the canal was too deep. Upon completion waterflow between the east and the west will be restored, and the area will be restored to a wetland habitat from its current uplands habitat type. Backfilling of the C-109 canal is part of an interagency effort with the ACOE to restore as closely as possible to natural conditions the flow of water in the C-111 watershed area. C-111 mitigation includes removal of roadside spoil along the C-111 canal to restore the natural condition of the area. The mitigation was devised in coordination with the National Maine Fisheries Service (NMFS), which required mitigation for non-vegetated habitat types. Restoration also includes preserving some spoil areas as islands to maintain habitat for endangered species of plants. When the C-111 spoil mounds are scraped down, the fill will not fill the whole ditch. The ditch will, therefore, be a bit more valuable but will not be completely restored to its former elevation. FDOT will also remove roadside spoil along the west side of U.S. 1, upon which exotic species of plants had grown, and returning the area to its original grade. The Harrison Tract is a known habitat and nesting area for American crocodiles. Its wetlands functions were altered or eliminated by prior development of the land by its original owners. Restoration includes regrading the area to restore its original wetlands functions, including habitat for young and adult crocodiles. FDOT's mitigation of the Harrison Tract also includes restoration of tidal flushing to increase contributions of nutrients and food sources to the surrounding tidal bay system. Crocodiles have been observed using the restored areas. FDOT has installed additional nesting berm habitat, basking habitat and shallow lagoon habitat to promote juvenile crocodile development. The District established that the credit awarded for this mitigation and the conversion ratios utilized for determining this credit were consistent with agency practice and its pertinent rules. FDOT was given a 1:1 credit ratio for areas involving full restoration of wetlands. In other portions of the Harrison Tract mitigation involving restoration of flushing to existing wetlands, FDOT was given not full credit, but credit based on the severity of limitation of the existing wetland functions. Based on this evaluation, mitigation credits were given in a range of a 3:1 ratio for restoration of severely disrupted or non-existent wetlands to a 20:1 ration for restoration of higher quality but not fully functional wetlands. FDOT is being awarded 70 mitigation credits for the 252 acres in the Harrison Tract that are being restored or enhanced. CONCURRENT MITIGATION Based on the mitigation ratios developed by the District, additional mitigation credits were required. Consequently, the project contemplates mitigation that will be undertaken concurrently with the construction of the project in addition to the upfront mitigation. FDOT proposes to earn these additional credits by projects involving creation and/or restoration of emergent vegetation, mangrove and seagrass habitats. FDOT’s proposal to mitigate mangrove impacts with "out of kind" mitigation of emergent vegetation habitats was viewed by the District as being necessary and appropriate because there were no sufficiently large areas of mangrove habitat suitable for restoration. Table 7 of Attachment H to FDOT Exhibit 26 sets forth the four mitigation projects that constitutes the concurrent portion of the mitigation for the project. This table sets forth the acres mitigated, the conversion factor for the mitigation, and the resulting mitigation credit awarded. In addition, the table references certain credit for the placement of the hydrological culverts. As will be discussed later, that credit was withdrawn at the formal hearing. The four mitigation activities that will constitute the concurrent portion of the mitigation plan are: the removal of the Lake Surprise causeway (2.90 acres credit); the scrape down of the Jewfish Bridge approaches (0.67 acres credit); the restoration of the FGFWFC road (10.34 acres credit); and the Boca Chica project (27.17 acres credit) The Lake Surprise Causeway removal mitigation involves 5.26 acres of on-site seagrass restoration and 0.54 acres of unvegetated bottom mitigation through the excavation of 52,220 cubic yards of material. Lake Surprise historically was a shallow tidal lake supporting seagrasses before a causeway was built across the lake over the seagrasses. FDOT proposes to remove the causeway and restore the previous elevation, after which it is anticipated that seagrasses that grow on the east side of the causeway will fully recruit naturally to the excavated area. Removing the Lake Surprise Causeway will establish 5.26 acres of seagrass, for which FDOT received 2.63 acres of on-site mitigation credit based on a 2:1 ratio. Through natural recruitment after removal of the causeway, there is a high likelihood that the entire 5.26 acres will recolonize with seagrass. FDOT minimized the seagrass impacts to the greatest extent possible. The mitigation credit pertaining to Lake Surprise does not include credit for the removal of the causeway itself. This awarded credit is for the restoration of seagrass areas. The mitigation pertaining to the Jewfish Creek Bridge approaches proposes the scrape down of 1.33 acres of existing fill to allow the area to become recolonized with mangroves. Boca Chica is located in southern Monroe County over one hundred miles from the southern terminus of the project. This site was chosen by FDOT as a site for seagrass mitigation project after FDOT reviewed several other potential sites. Two other sites were rejected. The area around the C- 111 canal was rejected because the land proposed for use was in private ownership. Several defunct marinas in Port Bougainville were rejected due to poor conditions not conducive to seagrass growth. Boca Chica was finally chosen as the site because it was a large enough area with light and hydrological flow conditions conducive to seagrass growth. The evidence establishes that the Boca Chica site is the most viable for seagrass mitigation. The seagrasses to be impacted at Lake Surprise are healthy and productive turtle grass, manatee grass and cuban shoalgrass. Turtle grass is considered an extremely valuable “climax community” of seagrasses which hold sediments in place, cleanse water quality, and forms the base of the food chain. It is valuable to sea turtles, manatees and recreationally important fish and shellfish. The cuban shoalgrass that will colonize at Boca Chica is a pioneer colonizer species that grows in disturbed areas. It is not as valuable to the marine system as turtle grass. The Boca Chica seagrass mitigation permit condition proposed to offset impacts to 11.27 acres of seagrass. This will involve the removal of 306 cubic yards of sediment and hydraulically dredging approximately 1,175 cubic yards of spoil material. The proposed permit conditions state that FDOT shall provide future maintenance of the culvert areas to maintain adequate flushing. FDOT will plant 25.92 acres of seagrasses to mitigate for the remaining 8.64 acres of impacts, for a mitigation ratio of 3:1. In addition, 8.46 acres of seagrass will be planted to mitigate for the barren bottom area that will be affected, and 1.62 additional acres will be planted to compensate for any unexpected impacts to Boca Chica based on the necessary improvements. Overall, there will be of 36 acres of seagrass mitigation by FDOT, for which FDOT is receiving 27.17 acres credit. FDOT will also increase the water flow between the east and west lagoons of Boca Chica, and maintain the culverts connecting the two sides, in order to further promote growth of seagrass therein. FDOT is responsible for 80% survival of each acre of seagrass mitigation, as well as monitoring once a year for five years. Based on historical data obtained from Boca Chica during past mitigation efforts, there is a high likelihood that the entire 36 acres of mitigation will survive, and that the remaining 74 acres of the Boca Chica lagoons will experience natural recruitment of seagrass as a result of FDOT's efforts. The FGFWFC access area was built by excavating a ditch, and putting fill on the wetlands and creating a dirt road bed. After the C-109 canal is backfilled, the access road will no longer be needed. The mitigation project will excavate the existing road bed, back fill it into the ditch, thereby recreating the wetlands that were there previously. FDOT will receive 10.34 mitigation credits based on a 1:1 ratio of acres restored. EVALUATION OF MITIGATION There is no mitigation in this permit for any wetland impact beyond the direct loss of the specific 149 acres that will be dredged or filled. Mitigation was provided only for the direct, footprint impacts of the project. None of the up front mitigation involves the creation of wetlands, which entails converting areas that were not previously wetlands or open water and turning them into wetlands. It will likely take between 20 and 50 years for the mitigation areas to achieve full functional value required by the South Florida Water Management District mitigation permit. In the interim, there will be a net loss of wetland functional value. With time, the proposed mitigation has a high likelihood of success. Based on FDOT's past successes in mitigation of construction-related impacts, FDOT is able to comply with permit conditions relating to best management practices associated with the construction of bridges and pilings and turbidity screens around road construction, as well as restoration of seagrasses and mangroves. Petitioners assert that the District erred in determining the credit to be given for the up-front portion of the mitigation. While it is true that the SFWMD Rules do not mention "up-front" mitigation, the District has the authority to consider all aspects of a mitigation project in weighing its relative value. Consulting engineering inspectors have been retained by FDOT to insure that all permitting requirements are met during mitigation and construction, and that the technical special provisions for protection of threatened and endangered species are complied with by FDOT. The proposed permits contain appropriate conditions that require FDOT to monitor and maintain the mitigation areas. FDOT will be responsible in perpetuity for maintaining the tidal flushing connection at the Boca Chica mitigation site. Special permit condition 6 to the SWM and WRM staff reports require wetland and upland monitoring. If wetland and upland monitoring or other information demonstrate that additional adverse impacts have occurred due to this project, FDOT would be required to offset the loss of any additional wetland impacts. MITIGATION IS APPROPRIATE The evidence established that the mitigation projects were fairly and appropriately reviewed by SFWMD and that the mitigation credits were fairly and appropriately awarded. The evidence also established that there is appropriate mitigation for the direct, secondary, and cumulative impacts of this project. ACTIVITIES NOT RECEIVING MITIGATION CREDIT Mitigation credits for the 25 hydrologic culverts north of C-111 were originally included in the permit staff reports. Those mitigation credits were removed in an addendum to the staff reports, introduced as District's Exhibits 5 and 6. These credits were not necessary to offset project impacts. After the staff report was issued, they became a point of contention by the Petitioners because they will not be utilized until a management plan is developed. Since they were not necessary to meet mitigation requirements, the credits were removed from this project. These credits were never included in the mitigation ratios for these permit applications. The addendum removed the 9.6 credits initially contemplated for the culverts. No credit has been awarded for the relocation of threatened and endangered species of plants, such as Joewood and Bay Cedar by FDOT from the C-111, C-109 and roadside spoil mitigation areas. These species have been relocated to tree islands constructed by FDOT on the mitigation sites, or to other areas that would not be impacted by the project. FDOT also was not given mitigation credits for: (1) the wildlife crossings and the fencing that will funnel wildlife through these crossings; (2) installation of pipe culverts north of the C-111 canal and bridges and box culverts south of C-111; and which, in addition to providing a corridor for aquatic species, will increase the tidal flushing of the area; (3) the removal of the Lake Surprise Causeway, which will restore historical hydrological flow between the eastern and western sides of Lake Surprise; (4) FDOT's commitment to improve and maintain the flushing of the west lagoon culverts in Boca Chica (mitigation is in the east lagoon); and (5) FDOT's contribution of $300,000 to assist Monroe County in performing a carrying capacity study for the County. Additionally, FDOT will preserve the Jewfish Creek Bridge abutment, which will be preserved for local historical purposes. FDOT will prepare the Jewfish Creek Bridge pilings for an artificial reef at Long Key during construction. THE PUBLIC INTEREST TEST It is appropriate for the SWFMD to consider, in balancing the public interest test, to consider traffic safety and hurricane evacuation.3 Because of FDOT's expertise in those areas, it is appropriate for the permitting agency to give great weight to highway safety concerns, including hurricane evacuation, presented by FDOT. The application of the public interest test does not involve consideration of non-environmental factors other than those expressly set forth in the statutes such as navigation or preservation of historical or archaeological resources. Specifically, aesthetics, quality of life, the potential for a project to cause increased crime, and school overcrowding are not properly considered within any of the seven factors contained in Section 403.918(2)(a), Florida Statutes (1991). The District concluded that the project is clearly in the public interest based upon consideration and balancing of the following factors: hurricane evacuation improvements, public safety improvements, a SWM system where no SWM system currently exists; wildlife crossings and fencing north of the C-111 canal where no such crossings or fencing currently exist; wildlife box culverts to accommodate crocodiles, alligators, manatees and marine life where no such culverts currently exist; and hydrologic culverts, which have the potential to assist in the restoration of hydrologic flows, and the mitigation projects, both upfront and concurrent. SECTION 403.918(2)(a), FLORIDA STATUTES Section 403.918(2)(a), Florida Statutes, requires the permitting agency to determine “[w]hether the project will adversely affect the public health, safety, or welfare or the property of others." The property of others is not at issue. As discussed below, the evidence clearly established that the project will greatly enhance the safety of the road during normal operations and facilitate evacuation in the event of a hurricane. There will be clear benefits to the public safety as a result of this project. As part of the PD&E process, FDOT, through Metric, prepared "A Safety Evaluation" of the existing roadway. The safety analysis was based on FDOT accident statistics for the years 1983-1988, as well as engineering review of the conditions causing the accidents. Specifically, FDOT based their safety analysis on the following: 1) calculation of the abnormally high accident rate on the roadway based on the rate quality control formula set forth in the FDOT Highway Safety Improvement Guidelines, and approved by the Federal Highway Administration; 2) copies of the actual crash reports filed with the Florida Division of Highway Safety and Motor Vehicles, which provided detail greater than that generally available through FDOT's own accident data reports, and which formed the basis of the collision diagram in the Safety Evaluation (FDOT Exhibits 36; and 3) and its August 1996 update thereto (FDOT Exhibit 41), on-site evaluation and review of the roadway to determine geometrics of the roadway, locations of driveway accesses and side roadways and the degrees at which roadways intersected. Metric prepared an update of the Safety Evaluation for the years 1989-1994, to determine the continuing validity of the Safety Evaluation, as well as to review alternative proposals to the original proposed roadway configuration. In preparing the update, the recent accident data (FDOT Exhibit 37) and the underlying research in the Safety Evaluation were used by Metric Engineering in reaching its conclusions. The Safety Evaluation performed by Metric in 1989 established high accident rates on the roadway based on a detailed segmental analysis of the roadway. In August of 1996, the Safety Evaluation was updated by Metric, which update confirmed the findings of the Safety Evaluation, and further stated that accident frequency on the Monroe County portion of the roadway exceeded the state average accident rate and the abnormally high accident rate for the years 1990 through 1994 (notwithstanding the rear-end accidents occurring at Jewfish Creek). Fatal accidents on the Dade County portion exceed the state average on the same stretch by 37 percent for the same years. The most severe accidents occur on the Dade County portion. The Monroe County portion of the roadway exceeds the statewide average in the abnormally high accident rate four out of the last five years that FDOT studied. The Dade County portion does not exceed the accident frequency or the number of accidents, but the fatality rate in Dade County is much higher than the state average. Presently an abnormally high accident rate exists in three locations along the project corridor, two of which are in the vicinity of the Jewfish Creek bridge. The third location is north of the bridge on Cross Key. Replacing the Jewfish Creek Bridge with the fixed-height bridge proposed by FDOT will substantially increase the safety on the project corridor. The District considered this to be an important positive element in the public interest balancing test. The existing 2:1 slopes of the roadway make it difficult for drivers to recover from running off the roadway, resulting in a greater frequency of this type of accident. Moreover, the existing clear zone is not large enough to overcome the 2:1 slope to allow safe recovery of errant vehicles. As a result, catastrophic crashes occur rather than safe recoveries. Also, as with hurricane evacuation discussed in the following section, actual accidents on the roadway prevent traffic from accessing or leaving the Keys, and also prevent emergency vehicles from rapidly accessing the Keys and a crash site. This occurs because there is little or no shoulder or clear zone along the sides of the road to allow emergency vehicles to efficiently access an accident site, and in the event of a severe, head-on type collision, the roadway is blocked off. U.S. 1 through the project corridor is regarded as so unsafe for travel that Monroe County law enforcement officials call it "death alley." There are many head-on collisions due to the two-lane, no-median alignment. Law enforcement is difficult and dangerous along the roadway, because it has very few areas wide enough to allow law enforcement officials to detain driving violators. It is also very dangerous, for the same reasons, for a driver to pull off the roadway with a broken-down vehicle. High rates of speed and impaired drivers contribute to the accident rates along the project corridor. The efforts of law enforcement to control speeders and drunk drivers is impeded since it is practically impossible for enforcement officers to turn their vehicles around to pursue violators without running a high risk of causing an accident on their own. The project would significantly improve safety on the roadway by reversing the problems identified in the this section, as well as the previous sections of this Recommended Order. The project would virtually eliminate head-on collisions which largely contribute to serious injuries and fatalities along the roadway. The project would also help eliminate problems with emergency vehicle access to accident sites and restoration of service in the event of accidents, and would increase the roadway's level of service as discussed below. Improved level of service was an additional need considered by FDOT during the PD&E process. While the District did not consider the traffic level of service by itself to be weighted as part of the positive public interest criteria in this project, the impacts of resulting congestion are relevant to the public interest consideration of traffic safety as discussed in the foregoing sections. Lower quality level of service, as presently exists on the roadway through level of service F, adversely affects the safety of the roadway. When traffic levels rise, driver frustration increases leading to drivers passing in no-passing zones and potentially resulting in head-on collisions and high-severity accidents. Additionally, due to the narrow shoulders of the existing roadway, accident vehicles pose a threat to and impede normal traffic flow on the roadway. The Highway Capacity Manual set the standards for traffic engineering and is used in all fifty states. The manual classifies the existing roadway as a two-lane arterial rural road. Applying the standards for measuring level of service for two-lane rural roads set forth in the Highway Capacity Manual, FDOT determined that the existing level of service on the roadway is E, which is a very poor level of service that does not meet the established standard of level of service C required by the Highway Capacity Manual. Monroe County uses a speed based method of calculating level of service. Using that method, the level of service for U.S. 1 is at an acceptable level. The parties disagree as to which method of calculating the level of service is appropriate. That conflict is resolved by finding that the method used by FDOT is the appropriate method because of its wide acceptance and long-term use. Traffic volume in the area of the southern terminus of the project is growing at a rate average annual rate of 3.07 percent. In the present condition of the roadway, level of service will degrade to F, or forced-flow conditions, by the year 2006. Even with the improvements proposed by FDOT, the level of service in the northbound direction would improve to level of service B, but the level of service in the southbound direction would remain at level of service D or E due to the single southbound land configuration. Hurricanes pose a serious threat to the safety and welfare of residents and visitors of the Keys. Monroe County is the most vulnerable hurricane-prone area in the United States because it is surrounded by tropical waters, land elevation is low throughout the islands, and the evacuation routes are limited to U.S. 1, an extended route that starts in Key West and runs to the mainland, and Card Sound Road. The greatest potential for loss of life during a hurricane in the Keys is from storm surge. Storm surge is a dome of water near the center of a hurricane which is created by the winds on the water's surface. In a category 3, 4 or 5 storm, the entire land mass in the path of the storm will be inundated. Because of the wind and storm surge associated with hurricanes, the best response to a hurricane warning in the Keys is to evacuate people to the mainland away from the water and the storm surge threat. Accordingly, Monroe County orders a mandatory evacuation in a category 3, 4, or 5 hurricane, and no shelters are opened. There is little or no disagreement as to the vulnerability of the Keys to hurricanes or as to the danger posed by a hurricane. There is disagreement as to whether the proposed project is needed for improved hurricane evacuation. The conflicting evidence in this regard is resolved by the following findings, which are based on the more credible, substantial evidence. The existing road does not have sufficient hurricane evacuation capacity to meet the present and projected future needs of Monroe County residents and visitors. In current hurricane evacuations, the two northbound lanes on U.S. 1 between mile marker 90 and 106 are split at Key Largo. Sixty percent of the traffic is directed up the northbound lane of U.S. 1; forty percent of the traffic is diverted onto the northbound lane of Card Sound Road. One southbound lane of U.S. 1 and Card Sound Road must remain open for emergency vehicles to reach an accident or a disabled vehicle, or to bring emergency supplies into the Keys. Improving the roadway is critical to the success of Monroe County's hurricane evacuation plan. FDOT relied on hurricane evacuation and needs modeling performed by Monroe County and the ACOE to confirm the need for improvements. All of the models used indicated that the project corridor is the controlling roadway segment for improving hurricane evacuation of the Keys. Additionally, FDOT relied on the Lewis Report of January 15, 1993, a study commissioned by the Governor of Florida. Recommendation No. 17 of the Lewis report recommends that FDOT expedite the design and construction of the project, which is viewed as being critical for increasing the rate of emergency evacuation. Dr. Robert Sheets, former director of the National Hurricane Center, testified that the failure to make improvements to the roadway would be "unconscionable." Dr. Sheets and Billy Wagner, the Director of Emergency Management for Monroe County, presented very compelling and very persuasive testimony that this project is essential for hurricane evacuation purposes. The proposed project is the minimum transportation improvement that will achieve a significant improvement in evacuation safety and clearance time. With the present two- lane configuration and narrow shoulders, evacuating traffic would be halted completely by a vehicle breakdown or an accident blocking one lane. Replacement of the Jewfish Creek Bridge will also facilitate the hurricane evacuation need for the project. In addition to improving the rate of evacuation, the project will make an evacuation safer. Emergency personnel cannot reach accidents on the roadway during an evacuation because, in certain segments, no roadbed exists adjacent to the northbound lane. A second northbound lane and wider road shoulders would enable disabled vehicles to be serviced and removed from the highway. The proposed changes to the road would improve emergency vehicles' access to an accident scene. The elevation of the roadway at Lake Surprise is so low that it can be flooded easily by a storm. The proposed project would replace the existing muck bed of the roadway with more stable material. The existing roadway is subject to settling and washout during storm events, which reduce the safety of the roadway itself and reduce the evacuation capacity of the roadway. If washout occurs, moving equipment to the islands for recovery efforts following a hurricane will be difficult or impossible. The proposed project will prevent erosion and reduce the effects of storm surge and wave action on the road during a hurricane. When the project has been completed, three lanes of evacuating traffic, two lanes from U. S. 1 and a third from Card Sound Road, will converge at Florida City. Representatives of FDOT, the Monroe County Sheriff's Department, the Florida Department of Law Enforcement and Monroe County Emergency Management have planned to manage the northbound traffic when it reaches Florida City during an evacuation. Several feasible alternatives exist, but additional planning is needed to prevent a monumental bottleneck at the northern terminus of the project. While it is clear that this project will not resolve all problems that exist as to hurricane evacuation, it is also clear that this project is essential to improve hurricane evacuation. SECTION 403.918(2)(a)2, FLORIDA STATUTES Section 403.918(2)(a)2, Florida Statutes, requires the permitting agency to consider “[w]hether the project will adversely affect the conservation of fish and wildlife, including endangered species, or their habitats.” The District considered the effect of the direct loss of dredging and filling 149.07 acres of wetland. As set forth in previous sections, it is found that this loss will be offset by the mitigation. For use during construction of the project, FDOT will adhere to technical special provisions and special permit conditions 9 through 13 to protect manatees, crocodiles, alligators, indigo snakes, marine turtles, and valuable trees, palms and other wildlife, to minimize or preclude any impacts to those species. Additionally, any osprey nests around the Jewfish Creek Bridge area at the time of construction will be relocated by FDOT if necessary. As part of the development of the FEIS, as required by the Federal Highway Administration under the National Environmental Protection Act, FDOT obtained official letters of concurrence from the USFWS and NMFS that the project would cause no adverse impacts to endangered species under section 7 of the Endangered Species Act. That process also established the project's consistency with Florida Coastal Zone Management Program, as determined by the State Clearinghouse within the Office of the Governor, in coordination with DEP, the Department of National Resources and FGFWFC. The project also contains provisions to impact positively or enhance the conservation of fish and wildlife, including threatened or endangered species and their habitat, as described below. These were positive factors that further helped neutralize and offset the 149.07 acres of direct impacts. In addition, FDOT is required to evaluate the effectiveness of the fencing along the entire project corridor, discussed below, and report to the District on that effectiveness. If the District determines that the fencing could be more effective, it may require FDOT to implement those suggestions. South of the C-111 canal, construction of box culverts and bridges addresses impacts to the American crocodile, a listed endangered species. Problems were identified with placement of existing culverts, which did not provide enough clear space and which caused the crocodile to cross over the roadway rather than through the culvert. To address this problem, 15 larger box culverts and three bridges will be placed within the roadway. These provide the necessary clear space to allow the crocodile to safely pass under rather than over the road. The location of the box culverts was chosen by reviewing crocodile mortalities associated with road crossings. Placement of these box culverts and bridges will also improve the hydrological flow of water within the project area, provide a crossing area for manatees, and allow greater dispersal of the crocodile population throughout Florida Bay. Species expected to use these box culverts include aquatic and aquatic water dependent species in the area. They were primarily targeted for crocodiles, alligators, and manatees, but certain fishes, turtles, frogs and other species in the wetlands along the project corridor will utilize the culverts. The box culverts will have 100 feet of wingback fencing extending north and south of each culvert. The intent of the wingback fencing is to funnel wildlife into the box culverts. Intermittent or wingback fencing is appropriate south of the C-111 canal for two primary reasons. First, the animals which will be guided into the box culverts are aquatic dependent. The area south of the C-111 canal is primarily water, washed mangrove areas and tidal creeks. Crocodiles tend to move in tidal creeks. Second, it was not possible to ensure continuous fencing along all portions of the project south of the C-111 canal because there are existing businesses. It could not be assured that these businesses would keep a gate closed. The project originally proposed continuous fencing alongside the road where it abuts ENP. Continuous fencing was initially proposed because the initial application included a solid concrete barrier down the median of the road. If a crocodile did enter the road from the side with discontinuous fencing, after crossing one lane the crocodile would hit the barrier, but then easily find its way back to the area it came from. However, the project was later modified to include a tri-beam barrier because it lessens the footprint of the project and thereby lessens the wetland impact. Since the current application does not include a continuous barrier down the middle of the road, if a crocodile enters the road it would cross the tri-beam barrier, go across another lane of roadway before hitting a continuous fence. The animal would then run up and down that fence with nowhere to go except back across the road again. This would increase their exposure to a road kill. With the installation of bridges and culverts along the southern portions of the project corridor, there is no need for continuous fencing because aquatic wildlife, such as the American crocodile, will tend to follow the flow of water through the culverts rather than climb over the roadway. The FGFWFC and ENP oppose continuous fencing and prefer intermittent fencing south of C-111 canal since the project now includes a tri-beam barrier. Positive benefits also include construction of panther crossings at four locations north of the C-111 canal to account for impacts to the Florida panther, a listed endangered species, in the vicinity of the project, along with continuous fencing on both sides of the road north of the C- 111 canal. The crossings will be placed at locations that show historical use by wildlife, including areas at the Dade County Correctional Institute access roadway, the water control structure on the C-109 canal, and the berm of the C- 111 canal. The wildlife crossings are indicated by blue dots on FDOT's Exhibit 1. FDOT underwent years of extensive coordination with the environmental regulatory and resource agencies to design a project that would accommodate their ecosystem management plans. The location of the wildlife crossings was based upon radio telemetry data, collected from radio-collared panthers, and their typical corridor movement. The location was further chosen based on input from the USFWS and the FGFWFC. The continuous fencing north of the C-111 canal will prevent wildlife from crossing the road, and instead force them to use the wildlife crossings. The crossings were designed for panther use, the panthers being the shyest animal in the area. If panthers can be accommodated, then other threatened and endangered species and other wildlife are expected to use them. DOT studies of the effectiveness of wildlife crossings, with fencing, including crossings installed on Alligator Alley, establish that wildlife will use the crossings, both singly and in groups, and that the crossings substantially reduce, if not eliminate, automobile- related mortality of wildlife. Documented wildlife include panthers, wild turkeys, wading birds, alligators, deer, bobcats, black bears and raccoons. SECTION 403.918(2)(a)3, FLORIDA STATUES Section 403.918(2)(a)3, Florida Statutes, requires the permitting agency to consider “[w]hether the project will adversely affect navigation or the flow of water or cause harmful erosion or shoaling.” The replacement of the bascule bridge at Jewfish Creek with a 65-foot high fixed-height bridge will be a benefit to navigation. Because Jewfish Creek is part of the intracoastal waterway, the existing bridge has to be frequently raised or lowered to accommodate marine traffic. Because of the age of the existing structure, frequent breakdowns have been experienced. Marine traffic is stopped or delayed if the bridge cannot be raised or if there is a delay in raising the bridge. Vehicular traffic is stopped while the bridge is raised. Regarding the flow of water, the project incorporates wildlife box culverts and bridges, which will improve tidal flushing and the flow of water south of the C- 111 canal. The District considered this to be a positive consideration under the public interest test. The 25 hydrologic culverts north of the C-111 canal were also a positive factor in the test because the culverts provide future water management capability. Erosion and shoaling are neutral factors in the public interest test because the permit conditions contain a plan to control erosion and shoaling during construction and to provide for road stabilization after construction. In addition, there is a positive factor regarding shoaling in that the roadway area now has a lot of storm action, causing problems with erosion on the side of the road. The project provides for road stabilization, which is a neutral to positive factor in the public interest test. SECTION 403.918(2)(a)4, FLORIDA STATUTES Section 403.918(2)(a)4, Florida Statutes, requires the permitting agency to consider “[w]hether the project will adversely affect the fishing or recreational values or marine productivity of the project.” A positive factor pertaining to marine productivity is the box culverts and bridges south of C-111, which will allow marine species to travel beneath the road to access the water on both sides of the road. Removal of the causeway along Lake Surprise opens that water body back up to one contiguous system, which is also a positive factor. The seagrass mitigation addressed in previous sections will also improve marine productivity and provide habitat for fish. SECTION 403.918(2)(a)5, FLORIDA STATUTES Section 403.918(2)(a)5, Florida Statutes, requires the permitting agency to consider “[w]hether the project will be of a temporary or permanent nature.” The project is permanent, though some construction impacts are temporary in nature. Once temporary impacts have ended and the project is complete, the project will be a positive benefit, because of the construction of the SWM system, culverts, animal underpasses and other benefits as set forth above. SECTION 403.918(2)(a)6, FLORIDA STATUTES Section 403.918(2)(a)6, Florida Statutes, requires the permitting agency to consider “[w]hether the project will adversely affect or will enhance significant historical and archaeological resources under the provisions of s. 267.061.” This factor is not at issue. SECTION 403.918(2)(a)7, FLORIDA STATUTES Section 403.918(2)(a)7, Florida Statutes, requires the permitting agency to consider “[t]he current condition and relative value of functions being performed by areas affected by the proposed activity.” A percentage of wetlands immediately adjacent to the road are impacted by exotic vegetation. Areas further out are part of a significant wetland ecosystem and are considered high quality. This project contains an exotic control program within FDOT's right of way, which is a positive consideration in the public interest test. Wetlands are currently receiving untreated storm water, which runs off the road immediately into the adjacent wetlands and water bodies without treatment. The project will include a SWM system where none currently exists as is detailed in the previous sections. This is a positive factor in the public interest test. The direct impacts of the project on 149 acres of wetlands alongside the roadway is not as large or significant as the impact caused by placement of the original embankment and resulting cut off of the eastern and western portions of the Everglades north of the C-111 canal. Overall, the concurrent and upfront mitigation efforts of FDOT are of regional significance and benefit to Everglades ecosystem by helping to repair the damage caused by the original embankment. THE PROJECT IS CLEARLY IN THE PUBLIC INTEREST The District appropriately weighed all considerations in determining that the project is clearly in the public interest. The greater weight of the competent, credible evidence established that the project is clearly in the public interest. RIGHT OF WAY PERMIT APPLICATION The land encompassed by the ROW permit has been properly adopted as a "work" of the District, requiring District authorization via a ROW Permit Modification to FDOT. The District's real property interest in the C-111 ROW applicable to the ROW permit modification consists of both fee simple and easement interests. The evidence is clear that DOT's application for the permit modification was thoroughly reviewed by the District, consistent with the District's established ROW permit review process. The District presented uncontroverted evidence and expert testimony to establish by a preponderance of the evidence that issuance of the permit modification to FDOT is consistent with all applicable District statutes, rules and other criteria, including the District's conditions for issuance of ROW Permits set forth in Rule 40E-6.301, F.A.C. FBII offered no evidence or testimony to the contrary. FUTURE MODIFICATIONS Modifying the project at a later date to pave a second southbound lane would require a District ERP permit. The addition of impervious surface triggers the District's SWM jurisdiction in this regard. However, FDOT established that that it had no current plans for further widening. The permit conditions require secondary and cumulative impacts associated with the increased capacity be addressed in accordance with the rules and criteria in effect at the time of any application for future widening. In addition, the permits require that FDOT must comply with any more stringent water quality criteria in effect at the time of any future widening. MODIFICATIONS AT THE FINAL HEARING At the Final Hearing, the District issued an Addendum to Staff Report for each of the SWM and WRM permits. The amendments made non-substantive changes to the District's staff reports regarding fencing along the roadway, performance of a study of fencing on the roadway by FDOT, water quality sampling along the roadway, assignment of mitigation credits, and other technical changes in wording for purposes of clarification. The changes set forth in the District's Exhibits 5 and 6 do not create impacts to the environment beyond those addressed elsewhere herein.
Recommendation Based on the foregoing findings of fact and conclusions of law it is RECOMMENDED that the Governing Board of the South Florida Water Management District enter a Final Order that issues the three permits challenged in this proceeding (SWM Permit No. 940606-10, WRM Permit No. 9460606-2-D, and ROW Permit No. 2584) subject to the conditions contained in the staff reports on the SWM permit application and the WRM permit application and subject to the additional permit conditions reflected by District Exhibits 5 and 6 and by the Findings of Fact pertaining to the permit for the relocation of the FKAA pipe. DONE AND ENTERED this 11th day of April, 1997, in Tallahassee, Leon County, Florida. ___________________________________ CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative this 11th day of April, 1997.
Findings Of Fact Upon a consideration of the oral and documentary evidence adduced at the hearing in this cause, the following pertinent facts are found: 1/ By application number 25793, the applicant seeks a permit to construct and operate a proposed surface water management system to serve a 2,541 acre project within the St. Johns River Basin in Indian River County. The proposed system will consist of a perimeter dike, a central canal with interior laterals and four discharge pumps. The applicant will be discharging into the St. Johns Marsh and seeks a discharge capacity of 139,000 GPM. Three of the discharge pumps are to be located at the southeast corner of the property and a two-way 25,000 GPM pump is to be located at the intersection of the central canal and the western boundary of the property. By application number 25794, the applicant seeks a permit for the use of surface and artesian water for the irrigation of the same 2,541 acres of pasture and truck crops. The applicant requests to withdraw surface water from the St. Johns Marsh by means of a two-way 25,000 GPM pump located at the intersection of the central canal and the western property boundary and to withdraw water from the Floridan aquifer by means of eight eight-inch artesian wells. The amount requested is 5,294 acre-feet per year with a maximum monthly pumpage of 1.47 billion gallons. A staff report of the Central and Southern Florida Flood Control District (FCD) concluded that the major problem with the permit applications is the impact on water quality of the receiving bodies of water and that nutrients and other pollutants will be introduced into runoff waters discharged into the St. Johns Marsh, which is the source of the public water supply for South Brevard County. The staff therefore recommended that the applicant institute a water quality and quantity monitoring program to monitor discharges to the Marsh. The staff further recommended that the applicant not be allowed to discharge from the western property boundary nor irrigate from the ditch on the western property boundary. It was recommended that the two-way 25,000 GPM pump be installed adjacent to the other pumps located at the southeast corner of the property. More specifically, the staff found that if a permit were to be issued pursuant to application number 25793, it should be subject to the conditions that: the allowable discharge capacity to be 104,000 GPM, with discharges to be east to the St. Johns Marsh by means of one 44,000 GPM pump, one 35,000 GPM pump and one 25,000 PM two-way pump to be located at the southeast corner of the property; the applicant notify the FCD prior to any excavation of materials from land lying east of the east property boundary and, if such excavation is done, a discontinuous borrow ditch be created by either leaving 25 foot portions of undisturbed marsh or by placing 25 foot earthen plugs at approximately 500 foot intervals (this was later modified at the hearing to 1,000 foot intervals); and the applicant submit monthly reports of total daily discharges and water quality, the samples to be taken at the southeast corner of the property. With regard to application number 25794, the staff recommended that if such permit were to be issued, it be subject to the following conditions: for the use of surface water, an annual allocation of 2329.3 acre- feet per year and for the use of artesian water, an annual allocation of 2518.5 acre-feet per year, with a maximum monthly pumpage from all sources of 355.3 million gallons; no withdrawal of surface water from the St. Johns Marsh when the water level in Blue Cypress Lake drops to 22.0' msl.; surface water to be withdrawn by means of a 25,000 GPM two-way pump located at the property's southeast corner; artesian waters to be withdrawn by eight eight-inch wells with effective and operative controls placed thereon and analyses of water samples from the water discharge of each the submission of monthly reports of total monthly pumpages and total monthly flows; and permit for the withdrawal of surface and artesian water to expire on January 15, 1979. At the hearing, the applicant agreed to the recommended conditions placed upon the permits by the staff report with the exception of: the amount of the allowable discharge (staff recommending 104,000 GPM as opposed to a desired 139,000 GPM); the location of the 25,000 GPM two-way pump (staff recommending southeast corner as opposed to a proposed site on the western boundary of the property); the expiration date of January 15, 1979. The Environmental Protection Bureau of the Florida Game and Fresh Water Commission requested the FCD to delay issuance of permits for all projects in the Upper St. Johns River basin until a comprehensive water management plan for the area is formulated. Read into the record was a resolution adopted by the Commission on May 16, 1975, recommending that "the further destruction of the marsh be curtailed and a plan be formulated for the return of the diverted waters as a management tool for restoration of fish and wildlife resources." On behalf of the Florida Audubon Society, Mr. Charles Lee contended that, because of this resolution and request of the Game and Fresh Water Fish Commission and that agency's constitutional status, the FCD is precluded from issuing the subject permits. Intervenors and members of the general public who were opposed to the issuance of the instant permits expressed the following concerns: the low water quality and quantity of the St. Johns River and its marshes; the decline in hunting and fishing because of agricultural activities in the St. Johns River valley; the loss of marsh land due to agricultural activity; the lack of a basic water management program for the area; the lack of remedial measures should degradation of the water occur; and the lack of an expiration date for the surface water management system permit.
Recommendation Based upon the findings of fact and conclusions of law recited above, it is the recommendation of the hearing officer that application numbers 25793 and 25794 be granted, subject to those special conditions set forth in the Staff Report as modified by the following: In paragraph number 3 on page 14 of the Staff Report, substitute the words "1,000 foot intervals" for "500 foot intervals;" Add as paragraphs 6 on page 15, paragraph 6 on page 16 and paragraph 7 on page 18 the following: "Should the data in the monthly reports submitted by the applicant indicate the occurrence of a degradation of the waters utilized, the applicant will be required to remedy the situation causing the de- gradation." Add as paragraph 7 on page 15 the following: "7. This permit shall expire on January 15, 1979." Respectfully submitted and entered this 25th of March, 1976, in Tallahassee, Florida. DIANE D. TREMOR Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304
The Issue The issues in this case are whether International Paper Company (IP) is entitled to National Pollutant Discharge Elimination System (NPDES) Permit No. FL0002526 issued by Department of Environmental Protection (Department) and whether the Department should approve Consent Order No. 08-0358, for the operation of IP’s paper mill in Cantonment, Escambia County, Florida.
Findings Of Fact The Department is the state agency authorized under Chapter 403, Florida Statutes (2008), to regulate discharges of industrial wastewater to waters of the state. Under a delegation from the United States Environmental Protection Agency, the Department administers the NPDES permitting program in Florida. IP owns and operates the integrated bleached kraft paper mill in Cantonment. FOPB is a non-profit Alabama corporation established in 1988 whose members are interested in protecting the water quality and natural resources of Perdido Bay. FOPB has approximately 450 members. About 90 percent of the members own property adjacent to Perdido Bay. James Lane is the president of FOPB. Jacqueline Lane and James Lane live on property adjacent to Perdido Bay. The mill's wastewater effluent is discharged into Elevenmile Creek, which is a tributary of Perdido Bay. Perdido Bay is approximately 28 square miles in area. U.S. Highway 90 crosses the Bay, going east and west, and forms the boundary between what is often referred to as the "Upper Bay" and "Lower Bay." The Bay is relatively shallow, especially in the Upper Bay, ranging in depth between five and ten feet. At the north end of Perdido Bay is a large tract of land owned by IP, known as the Rainwater Tract. The northern part of the tract is primarily fresh water wetlands. The southern part is a tidally-affected marsh. The natural features and hydrology of the fresh water wetlands have been substantially altered by agriculture, silviculture, clearing, ditching, and draining. Tee Lake and Wicker Lake are small lakes (approximately 50 acres in total surface area) within the tidal marsh of the Rainwater Tract. Depending on the tides, the lakes can be as shallow as one foot, or several feet deep. A channel through the marsh allows boaters to gain access to the lakes from Perdido Bay. Florida Pulp and Paper Company first began operating the Cantonment paper mill in 1941. St. Regis Paper Company acquired the mill in 1946. In 1984, Champion International Corporation (Champion) acquired the mill. Champion changed the product mix in 1986 from unbleached packaging paper to bleached products such as printing and writing grades of paper. The mill is integrated, meaning that it brings in logs and wood chips, makes pulp, and produces paper. The wood is chemically treated in cookers called digesters to separate the cellulose from the lignin in the wood because only the cellulose is used to make paper. Then the "brown stock" from the digesters goes through the oxygen delignification process, is mixed with water, and is pumped to paper machines that make the paper products. In 1989, the Department and Champion signed a Consent Order to address water quality violations in Elevenmile Creek. Pursuant to the Consent Order, Champion commissioned a comprehensive study of the Perdido Bay system that was undertaken by a team of scientists led by Dr. Robert Livingston, an aquatic ecologist and professor at Florida State University. The initial three-year study by Dr. Livingston's team of scientists was followed by a series of related scientific studies (“the Livingston studies"). Champion was granted variances from the water quality standards in Elevenmile Creek for iron, specific conductance, zinc, biological integrity, un-ionized ammonia, and dissolved oxygen (DO). In 2001, IP and Champion merged and Champion’s industrial wastewater permit and related authorizations were transferred to IP. In 2002, IP submitted a permit application to upgrade its wastewater treatment plant (WWTP) and relocate its discharge. The WWTP upgrades consist of converting to a modified activated sludge treatment process, increasing aeration, constructing storm surge ponds, and adding a process for pH adjustment. The new WWTP would have an average daily effluent discharge of 23.8 million gallons per day (mgd). IP proposes to convey the treated effluent by pipeline 10.7 miles to the Rainwater Tract, where the effluent would be distributed over the wetlands as it flows to lower Elevenmile Creek and upper Perdido Bay. IP's primary objective in upgrading the WWTP was to reduce the nitrogen and phosphorus in the mill's effluent discharge. The upgrades are designed to reduce un-ionized ammonia, total soluble nitrogen, and phosphorus. They are also expected to achieve a reduction of biological oxygen demand (BOD) and TSS. IP plans to obtain up to 5 mgd of treated municipal wastewater from a new treatment facility planned by the Emerald Coast Utility Authority (ECUA), which would be used in the paper production process and would reduce the need for groundwater withdrawals by IP for this purpose. The treated wastewater would enter the WWTP, along with other process wastewater and become part of the effluent conveyed through the pipeline to the wetland tract. The effluent limits required by the proposed permit include technology-based effluent limits (TBELs) that apply to the entire pulp and paper industry. TBELs are predominantly production-based, limiting the amount of pollutants that may be discharged for each ton of product that is produced. The proposed permit also imposes water quality-based effluent limits (WQBELs) that are specific to the Cantonment mill and the waters affected by its effluent discharge. The WQBELs for the mill are necessary for certain constituents of the mill's effluent because the TBELs, alone, would not be sufficient to prevent water quality criteria in the receiving waters from being violated. The Livingston studies represent perhaps the most complete scientific evaluation ever made of a coastal ecosystem. Dr. Livingston developed an extensive biological and chemical history of Perdido Bay and then evaluated the nutrient loadings from Elevenmile Creek over a 12-year period to correlate mill loadings with the biological health of the Bay. The Livingston studies confirmed that when nutrient loadings from the mill were high, they caused toxic algae blooms and reduced biological productivity in Perdido Bay. Some of the adverse effects attributable to the mill effluent were most acute in the area of the Bay near the Lanes' home on the northeastern shore of the Bay because the flow from the Perdido River tends to push the flow from Elevenmile Creek toward the northeastern shore. Because Dr. Livingston determined that the nutrient loadings from the mill that occurred in 1988 and 1989 did not adversely impact the food web of Perdido Bay, he recommended effluent limits for ammonia nitrogen, orthophosphate, and total phosphorous that were correlated with mill loadings of these nutrients in those years. The Department used Dr. Livingston’s data, and did its own analyses, to establish WQBELs for orthophosphate for drought conditions and for nitrate-nitrite. WQBELs were ultimately developed for total ammonia, orthophosphate, nitrate-nitrite, total phosphorus, BOD, color, and soluble inorganic nitrogen. The WQBELs in the proposed permit were developed to assure compliance with water quality standards under conditions of pollutant loadings at the daily limit (based on a monthly average) during low flow in the receiving waters. Petitioners did not dispute that the proposed WWTP is capable of achieving the TBELs and WQBELs. Their main complaint is that the WQBELs are not adequate to protect the receiving waters. A wetland pilot project was constructed in 1990 at the Cantonment mill into which effluent from the mill has been discharged. The flora and fauna of the pilot wetland project have been monitored to evaluate how they are affected by IP’s effluent. An effluent distribution system is proposed for the wetland tract to spread the effluent out over the full width of the wetlands. This would be accomplished by a system of berms running perpendicular to the flow of water through the wetlands, and gates and other structures in and along the berms to gather and redistribute the flow as it moves in a southerly direction toward Perdido Bay. The design incorporates four existing tram roads that were constructed on the wetland tract to serve the past and present silvicultural activities there. The tram roads, with modifications, would serve as the berms in the wetland distribution system. As the effluent is discharged from the pipeline, it would be re-aerated and distributed across Berm 1 through a series of adjustable, gated openings. Mixing with naturally occurring waters, the effluent would move by gravity to the next lower berm. The water will re-collect behind each of the vegetated berms and be distributed again through each berm. The distance between the berms varies from a quarter to a half mile. Approximately 70 percent of the effluent discharged into the wetland would flow a distance of approximately 2.3 miles to Perdido Bay. The remaining 30 percent of the effluent would flow a somewhat shorter distance to lower Elevenmile Creek. A computer simulation performed by Dr. Wade Nutter indicated that the effluent would move through the wetland tract at a velocity of approximately a quarter-of-a-foot per second and the depth of flow across the wetland tract will be 0.6 inches. It would take four or five days for the effluent to reach lower Elevenmile Creek and Perdido Bay. As the treated effluent flows through the wetland tract, there will be some removal of nutrients by plants and soil. Nitrogen and phosphorous are expected to be reduced approximately ten percent. BOD in the effluent is expected to be reduced approximately 90 percent. Construction activities associated with the effluent pipeline, berm, and control structures in the wetland tract, as originally proposed, were permitted by the Department through issuance of a Wetland Resource Permit to IP. The United States Army Corps of Engineers has also permitted this work. Petitioners did not challenge those permits. A wetland monitoring program is required by the proposed permit. The stated purpose of the monitoring program is to assure that there are no significant adverse impacts to the wetland tract, including Tee and Wicker Lakes. After the discharge to the wetland tract commences, the proposed permit requires IP to submit wetland monitoring reports annually to the Department. A monitoring program was also developed by Dr. Livingston and other IP consultants to monitor the impacts of the proposed discharge on Elevenmile Creek and Perdido Bay. It was made a part of the proposed permit. The proposed Consent Order establishes a schedule for the construction activities associated with the proposed WWTP upgrades and the effluent pipeline and for incremental relocation of the mill's discharge from Elevenmile Creek to the wetland tract. IP is given two years to complete construction activities and begin operation of the new facilities. At the end of the construction phase, least 25 percent of the effluent is to be diverted to the wetland tract. The volume of effluent diverted to the wetlands is to be increased another 25 percent every three months thereafter. Three years after issuance of the permit, 100 percent of the effluent would be discharged into the wetland tract and there would no longer be a discharge into Elevenmile Creek. The proposed Consent Order establishes interim effluent limits that would apply immediately upon the effective date of the Consent Order and continue during the two-year construction phase when the mill would continue to discharge into Elevenmile Creek. Other interim effluent limits would apply during the 12- month period following construction when the upgraded WWTP would be operating and the effluent would be incrementally diverted from Elevenmile Creek to the wetland tract. A third set of interim effluent limits would apply when 100 percent of the effluent is discharged into the wetland tract. IP is required by the Consent Order to submit quarterly reports of its progress toward compliance with the required corrective actions and deadlines. Project Changes After the issuance of the Final Order in 05-1609, IP modified its manufacturing process to eliminate the production of white paper. IP now produces brown paper for packaging material and “fluff” pulp used in such products as filters and diapers. IP’s new manufacturing processes uses substantially smaller amounts of bleach and other chemicals that must be treated and discharged. IP reduced its discharge of BOD components, salts that increase the specific conductance of the effluent, adsorbable organic halides, and ammonia. IP also reduced the odor associated with its discharge. In the findings that follow, the portion of the Rainwater Tract into which IP proposes to discharge and distribute its effluent will be referred to as the “effluent distribution system,” which is the term used by Dr. Nutter in his 2008 “White Paper” (IP Exhibit 23). The effluent distribution system includes the berms and other water control structures as well as all of the natural areas over which IP’s effluent will flow to Perdido Bay. Most of the existing ditches, sloughs, and depressions in the effluent distribution system are ephemeral, holding water only after heavy rainfall or during the wet season. Even the more frequently wetted features, other than Tee and Wicker Lakes, intermittently dry out. There is currently little connectivity among the small water bodies that would allow fish and other organisms to move across the site. Fish and other organisms within these water bodies are exposed to wide fluctuations in specific conductivity, pH, and DO. When the water bodies dry out, the minnows and other small fish die. New populations of fish enter these water bodies from Elevenmile Creek during high water conditions, or on the feet of water birds. IP's consultants conducted an extensive investigation and evaluation of animal and plant communities in the Rainwater Tract in coordination with scientists from the Department and the Florida Fish and Wildlife Conservation Commission. Among the habitats that were identified and mapped were some wet prairies, which are designated “S-2," or imperiled, in the Florida Natural Area Inventory. In these wet prairies are rare and endangered pitcher plants. IP modified the design of the proposed effluent distribution system to shorten the upper berms and remove 72.3 acres of S-2 habitat. The total area of the system was reduced from 1,484 acres to 1,381 acres. The proposed land management activities within the effluent distribution system are intended to achieve restoration of historic ecosystems, including the establishment and maintenance of tree species appropriate to the various water depths in the system, and the removal of exotic and invasive plant species. A functional assessment of the existing and projected habitats in the effluent distribution system was performed. The Department concluded that IP’s project would result in a six percent increase in overall wetland functional value within the system. That estimate accounts for the loss of some S-2 habitat, but does not include the benefits associated with IP’s conservation of S-2 habitat and other land forms outside of the effluent distribution system. IP proposes to place in protected conservation status 147 acres of wet prairie, 115 acres of seepage slope, and 72 acres of sand hill lands outside the effluent distribution system. The total area outside of the wetland distribution system that the Consent Order requires IP to perpetually protect and manage as conservation area is 1,188 acres. The Consent Order was modified to incorporate many of the wetland monitoring provisions that had previously been a part of the former experimental use of wetlands authorization. IP proposes to achieve compliance with all proposed water quality standards and permit limits by the end of the schedule established in the Consent Order, including the water quality standards for specific conductance, pH, turbidity, and DO, which IP had previously sought exceptions for pursuant to Florida Administrative Code Rule 62-660.300(1). Limitation of Factual Issues As explained in the Conclusions of Law, the doctrine of collateral estoppel bars the parties in these consolidated cases from re-litigating factual issues that were previously litigated by them in DOAH Case No. 05-1609. The Department’s Final Order of August 8, 2007, determined that IP had provided reasonable assurance that the NPDES permit, Consent Order, exception for the experimental use of wetlands, and variance were in compliance with all applicable statutes and rules, except for the following area: the evidence presented by IP was insufficient to demonstrate that IP’s wastewater effluent would not cause significant adverse impact to the biological community of the wetland tract, including Tee and Wicker Lakes. Following a number of motions and extensive argument on the subject of what factual issues raised by Petitioners are proper for litigation in this new proceeding, an Order was issued on June 2, 2009, that limited the case to two general factual issues: Whether the revised Consent Order and proposed permit are valid with respect to the effects of the proposed discharge on the wetland system, including Tee and Wicker Lakes, and with respect to any modifications to the effluent distribution and treatment functions of the wetland system following the Final Order issued in DOAH Case No. 05- 1609; and Whether the December 2007 report of the Livingston team demonstrates that the WQBELS are inadequate to prevent water quality violations in Perdido Bay. Petitioners’ Disputes Petitioners’ proposed recommended orders include arguments that are barred by collateral estoppel. For example, Jacqueline Lane restates her opinions about physical and chemical processes that would occur if IP’s effluent is discharged into the wetlands, despite the fact that some of these opinions were rejected in DOAH Case No. 05-1609. Dr. Lane believes that IP’s effluent would cause adverse impacts from high water temperatures resulting from color in IP’s effluent. There is already color in the waters of the effluent distribution system under background conditions. The increased amount of shading from the trees that IP is planting in the effluent distribution system would tend to lower water temperatures. Peak summer water temperatures would probably be lowered by the effluent. Petitioners evidence was insufficient to show that the organisms that comprise the biological community of the effluent distribution system cannot tolerate the expected range of temperatures. Dr. Lane also contends that the BOD in IP's effluent would deplete DO in the wetlands and Tee and Wicker Lakes. Her contention, however, is not based on new data about the effluent or changes in the design of the effluent distribution system. There is a natural, wide fluctuation in DO in the wetlands of the effluent distribution system because DO is affected by numerous factors, including temperature, salinity, atmospheric pressure, turbulence, and surface water aeration. There are seasonal changes in DO levels, with higher levels in colder temperatures. There is also a daily cycle of DO, with higher levels occurring during the day and lower levels at night. It is typical for DO levels in wetlands to fall below the Class III water quality standard for DO, which is five milligrams per liter (mg/l). An anaerobic zone in the water column is beneficial for wetland functions. DO levels in the water bodies of the effluent distribution system currently range from a high of 11 to 12 mg/l to a low approaching zero. The principal factor that determines DO concentrations within a wetland is sediment oxygen demand (SOD). SOD refers to the depletion of oxygen from biological responses (respiration) as well as oxidation-reduction reactions within the sediment. The naturally occurring BOD in a wetland is large because of the amount of organic material. The BOD associated with IP’s effluent would be a tiny fraction of the naturally occurring BOD in the effluent distribution system and would be masked by the effect of the SOD. It was estimated that the BOD associated with IP's effluent would represent only about .00000000001 percent of the background BOD, and would have an immeasurable effect. Dr. Pruitt’s testimony about oxygen dynamics in a wetland showed that IP’s effluent should not cause a measurable decrease in DO levels within the effluent distribution system, including Tee and Wicker Lakes. FOPB and James Lane assert that only 200 acres of the effluent distribution system would be inundated by IP’s effluent, so that the alleged assimilation or buffering of the chemical constituents of the effluent would not occur. That assertion misconstrues the record evidence. About 200 acres of the effluent distribution system would be permanently inundated behind the four berms. However, IP proposes to use the entire 1,381-acre system for effluent distribution. The modifications to the berms and the 72-acre reduction in the size of the effluent distribution system would not have a material effect on the assimilative capacity of system. The residence time and travel time of the effluent in the system, for example, would not be materially affected. Variability in topography within the effluent distribution system and in rainfall would affect water depths in the system. The variability in topography, including the creation of some deeper pools, would contribute to plant and animal diversity and overall biological productivity within the system. The pH of the effluent is not expected to change the pH in the effluent distribution system because of natural buffering in the soils. The specific conductance (saltiness) of IP’s effluent is not high enough to adversely affect the biological community in the fresh water wetlands of the effluent distribution system. IP is already close to maintaining compliance with the water quality standard for specific conductance and would be in full compliance by the end of the compliance schedule established in the proposed Consent Order. After the 2007 conversion to brown paper manufacturing, IP’s effluent has shown no toxicity. The effluent has passed the chronic toxicity test, which analyzes the potential for toxicity from the whole effluent, including any toxicity arising from additive or synergistic effects, on sensitive test organisms. Dr. Lane points out that the limits for BOD and TSS in the proposed NPDES permit exceed the limits established by Department rule for discharges of municipal wastewater into wetlands. However, paper mill BOD is more recalcitrant in the environment than municipal wastewater BOD and less “bio- available” in the processes that can lower DO. In addition, the regulatory limits for municipal wastewater are technology-based, representing “secondary treatment.” The secondary treatment technology is not applicable to IP’s wastewater. Sampling in the pilot wetland at the paper mill revealed a diversity of macroinvertebrates, including predator species, and other aquatic organisms. Macroinvertebrates are a good measure of the health of a water body because of their fundamental role in the food web and because they are generally sensitive to pollutants. Petitioners contend that the pilot wetland at the paper mill is not a good model for the effect of the IP’s effluent in the wetland distribution system, primarily because of the small amount of effluent that has been applied to the pilot wetland. Although the utility of the pilot wetland data is diminished in this respect, it is not eliminated. The health of the biological community in the pilot wetland contributes to IP’s demonstration of reasonable assurance that the biological community in the effluent distribution system would not be adversely affected. The effluent would not have a significant effect on the salinity of Tee and Wicker Lakes. Under current conditions, the lakes have a salinity of less than one part per thousand 25 percent of the time, less than 10 parts per thousand 53 percent of the time, and greater than 10 parts per thousand 22 percent of the time. In comparison, marine waters have a salinity of 2.7 parts per thousand. IP’s effluent would not affect the lower end of the salinity range for Tee and Wicker Lakes, and would cause only a minor decrease in the higher range. That minor decrease should not adversely affect the biota in Tee and Wicker Lakes or interfere with their nursery functions. The proposed hydrologic loading rate of the effluent amounts to an average of six-tenths of an inch over the area of effluent distribution system. The addition of IP’s effluent to the wetlands of the effluent distribution system and the creation of permanent pools would allow for permanent fish populations and would increase the opportunity for fish and other organisms to move across the effluent distribution system. Biological diversity and productivity is likely to be increased in the effluent distribution system. By improving fish habitat, the site would attract wading birds and other predatory birds. Although the site would not be open to public use (with the exception of Tee and Wicker Lakes), recreational opportunities could be provided by special permission for guided tours, educational programs, and university research. Even if public access were confined to Tee and Wicker Lakes, that would not be a reduction in public use as compared to the existing situation. IP’s discharge, including its discharges subject to the interim limits established in the Consent Order, would not interfere with the designated uses of the Class III receiving waters, which are the propagation and maintenance of a healthy, well-balanced population of fish and wildlife. The wetlands of the effluent distribution system are the “receiving waters” for IP’s discharge. The proposed project would not be unreasonably destructive to the receiving waters, which would involve a substantial alteration in community structure and function, including the loss of sensitive taxa and their replacement with pollution-tolerant taxa. The proposed WQBELs would maintain the productivity in Tee and Wicker Lakes. There would be no loss of the habitat values or nursery functions of the lakes which are important to recreational and commercial fish species. IP has no reasonable, alternative means of disposing of its wastewater other than by discharging it into waters of the state. IP has demonstrated a need to meet interim limits for a period of time necessary to complete the construction of its alternative waste disposal system. The interim limits and schedule for coming into full compliance with all water quality standards, established in the proposed Consent Order, are reasonable. The proposed project is important and beneficial to the public health, safety, and welfare because (1) economic benefits would accrue to the local and regional economy from the operation of IP’s paper mill, (2) Elevenmile Creek would be set on a course of recovery, (3) the wetlands of the effluent distribution system would become a site of greater biological diversity and productivity, (4) the environmental health of Perdido Bay would be improved, (5) the Department’s decades-long enforcement action against IP would be concluded, (6) substantial areas of important habitat would be set aside for permanent protection, and (7) the effluent distribution system would yield important information on a multitude of scientific topics that were debated by these parties. The proposed project would not adversely affect the conservation of fish or wildlife or their habitats. The proposed project would not adversely affect fishing or water-based recreational values or marine productivity in the vicinity of the proposed discharge. There is no Surface Water Improvement and Management Plan applicable to IP’s proposed discharge. The preponderance of the record evidence establishes reasonable assurance that IP’s proposed project would comply with all applicable laws and that the Consent Order establishes reasonable terms and conditions to resolve the Department’s enforcement action against IP for past violations.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is: RECOMMENDED that the Department enter a final order granting NPDES Permit No. FL0002526 and approving Consent Order No. 08-0358. DONE AND ENTERED this 27th day of January, 2010, in Tallahassee, Leon County, Florida. BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of January, 2010.
The Issue The issue is whether the 100 foot separation of respondents/applicants sewage treatment plant from the surface water management system is adequate.
Findings Of Fact Based upon all of the evidence, the following supplemental findings of fact are determined: Background Respondents/applicant, John D. Remington and Bolton S. Drackett (applicants), are the owners of record of approximately two thirds, or around 2,700 acres, of Keewaydin Island (Key Island), which lies just south of the mainland portion of the City of Naples, Florida. In conjunction with a planned luxury development of forty-two homes on Key Island, applicants have filed an application with respondent, South Florida Water Management District (District), seeking the issuance of a permit authorizing the construction and operation of a surface water management system (system) through which stormwater runoff from the project will be directed and controlled. Petitioner, Florida Audubon Society (FAS), has initiated this proceeding to contest the issuance of a permit. In an earlier and separate proceeding (DOAH Case No. 90-2415), applicants applied for a permit from the Department of Environmental Regulation (DER) to construct a wastewater treatment plant (plant) to serve the planned development. The permit was issued on January 2, 1990, and because all appeals by FAS in Case No. 90-2415 have been concluded, that proceeding is now final. Although the wastewater treatment plant has not yet been constructed, the parties agree that it will be situated more than one hundred feet from the surface water management system. This distance (100 feet) is the minimum amount of space allowed by District rule between the plant and system. Even so, the purpose of the remand proceeding is to determine whether that amount of separation is adequate. Thus, the factual issue here is whether the treated wastewater from the plant and filter fields will enter the surface water management system and cause a violation of applicable water quality standards and other relevant District criteria. In support of their respective positions on this issue, the parties have presented the testimony of a number of experts. In resolving the conflict in their testimony, the undersigned has accepted the more credible and persuasive testimony which is embodied in the findings below. A Brief Description of the Development and System The proposed development and surface water management system were described in detail in the prior recommended order entered in this case. For purposes of this Supplemental Recommended Order, it need only be noted that Key Island now has a lodge, guest quarters and recreation facilities, all presently served by septic tanks. Access to the island is provided by motor launch from an existing shore station. Subaqueous utility crossings from the mainland provide electric power and potable water to the island. The planned development includes the construction of forty-two large luxury homes and an expansion of the lodge facilities to accommodate the needs of the new residents. The homes will be built in phases with approximately ten to be built in the first year. The entire project may take as long as seven or eight years to complete. The proposed surface water management system was designed to handle a seventy-five residential unit development. However, by virtue of a reduction in size imposed by the City of Naples, the project has been reduced to forty-two homes. Even so, the capacity of the system has not been downsized. Therefore, the system as designed will more than accommodate all proposed development on the island. The development area has been divided into seven surface water management basins based upon seven existing natural water sheds on the upland portion of the project. Each basin will have a system of inlets, culverts and swales which will direct runoff to control structures. The dry swales are approximately one foot deep and five to ten feet wide and run parallel on both sides of the cart paths that link the various portions of the project. The cart paths, which will be at an elevation of 5.5 feet above mean sea level (NGVD), will have culverts running underneath to aid in maintaining the natural flow of water and limit impounding of water. The swale bottoms are designed to be one foot below the cart path elevation, or at 4.5 feet NGVD, and will be dry, except during significant rain events, because they are designed so that the bottom of the swale is at least one foot above the average wet season water table. Both the cart paths and swale system utilize a design system that is common to residential developments. Once the water reaches a specified height, it goes over the control structure and is discharged downstream into spreader swales from which the water is dispersed into either interior, low wetland areas or into two artificial lakes (7.3 and 1.0 acres in size) created for wet detention. Basins one, two, three, four and seven are designed to treat water quality by the dry detention method, that is, by the unlined swales that parallel cart paths, while water quality is accomplished in basins five and six by best management practices and wet retention, that is, the two artificial lakes. The Wastewater Treatment Plant The DER permit was issued on January 2, 1990, and carries an expiration date of January 2, 1995. It authorizes applicants to: construct a 0.035 MGD extended aeration process wastewater treatment plant with reclaimed water to dual absorption fields located at the project site as depicted on Wilson, Miller, Barton, Soll & Peek, Inc. design drawings, project number 6270, sheets 1 thru 5 of 5, dated March 20, 1989, revised October 16, 1989 and received October 19, 1989. The design drawings were submitted in support of construction application, engineering report, hydrologeolic characteristics and hydraulic modeling for effluent disposal report and related documents, dated March 20, 1989. The hydraulic capacity of the plant is limited to 0.030 MGD based on the reclaimed water disposal system. The collection system shall not exceed the 0.030 MGD hydraulic capacity as well. The wastewater treatment plant is designed to meet all DER water quality, health and safety standards. For example, the plant must achieve 90% removal of biological oxygen demand (BOD) and 90% removal of total suspended solids from the raw wastewater, or effluent levels below 20 parts per million for BOD and 10 parts per million suspended solids, whichever is more stringent. The plant must also have twenty-four hour detention in the aeration chamber and four hours detention in the clarifer. Further, a chlorine chamber contact time of fifteen minutes is required. In addition, DER has issued the permit with certain specific conditions. Among others, these include standards as to effluent chlorine residuals, the requirement that a professional engineer inspect the construction, operation requirements, sampling schedules, defined perameter levels, and the establishment of a hydraulic plant load (permitted maximum daily flow) at 30,000 gallons per day. By issuing the permit, DER has concluded that up to 30,000 gallons per day of sewage effluent can be treated and disposed of by the plant filter fields without violation of applicable DER water quality, health and safety standards. The wastewater treatment plant will be located on a centralized utility site within basin seven of the system. There are also gravity sand filters and a drainfield effluent disposal system located in basin six, which is the northeastern corner of the project. The plant will provide a high degree of treatment and disinfection for the effluent before it is discharged to the filter field. The filtered (treated) effluent will flow by gravity main to the filter fields located in an adjacent basin. Two filter fields will be used in disposing of the treated wastewater effluent. Constructed as sand mounds at a grade level of two or three feet above the existing island elevation, each filter will have dimensions of twenty feet wide and four hundred feet long. The filter fields will be constructed as a bed of gravel wrapped in filter cloth and placed within a mound of soil. A perforated four-inch pipe will be installed within the gravel bed at 5.5 feet NGVD to distribute the effluent through the filter beds. The effluent will then percolate downward and laterally away from the bed and into the groundwater table. At that point, the effluent will become indistinguishable from the groundwater Because the total daily flow will be pumped alternately into one part of the two sections of the drainfield, this allows one filter field to "rest" for a seven-day period during the use of the other filter field, thereby avoiding saturation. Therefore, the average theoretical maximum input into a filter field over a one year period at the plant's maximum capacity is 15,000 gallons per day. The plant was designed and permitted for maximum daily flows at all times of the year. However, the actual operating conditions will reflect significantly less flows due to the seasonality of the population and occupancy levels. More specifically, the plant was designed and permitted for seventy- five dwelling units and ancillary uses with an estimated maximum design flow of 28,450 gallons per day. The approved planned development will contain only forty-two dwelling units and ancillary uses with a maximum design flow of 21,200 gallons per day. Therefore, the permitted plant will treat the wastewater to a higher level due to the reserve capacity, and the plant will rarely be used at over fifty percent of its available capacity. Revised projected wastewater flows will range from daily loads of 2,325 gallons per day during the months of August and September to a high of 15,137 gallons per day during the month of February. This projected usage is consistent with historical occupancy and usage trends in the Naples area which show that occupancy of homes is at its peak during the dry season (the cooler winter months) and substantially lower during the wet season (the hot summer months). Applicants' projected wastewater flows are found to be reasonable and are hereby accepted. In making this finding, the undersigned has rejected the contention by FAS that the daily wastewater flows will be higher than that projected by the applicants and the plant will operate at maximum capacity for sustained periods of time. The system plans reflect that there will be swales within basin six located between one hundred ten and one hundred twenty feet to the west of the filter fields. These swales run parallel along a cart path and flow to the north discharging into an artificial lake at the north end of the project. The swales in this basin have a bottom elevation of 4.5 feet NGVD and decrease to an elevation of 3.5 feet NGVD at the point of discharge into the artificial lake. Adequacy of Separation Between Plant and System Rule 40E-4.091, Florida Administrative Code, adopts and incorporates by reference a document known as the "Basis for Review for Surface Water Management Permit Applications within the South Florida Water Management District - September 1989" (Basis for Review). Section 3.2.2.8 of the Basis for Review reads as follows: Sewage treatment percolation ponds. Above ground pond dikes shall not be within 200 feet of water bodies or 100 feet of dry detention/ detention areas. Additional calculations by the applicant may be necessary in unusual cases requiring deviations from these dimensions. The purpose of the above section is to provide adequate separation between above-ground percolation ponds and surface water management systems in case the percolation pond dike fails. For example, above grade percolation ponds contain large volumes of sewage treatment plant effluent. If a pond dike should fail, a large portion of effluent would be quickly released into the adjacent ground. The minimum 100-foot separation is designed to provide adequate distance for percolation into the ground prior to infiltrating the surface water management system. However, filter fields contain lesser volumes of effluent than do percolation ponds, and should a filter field fail, the effluent will trickle out the side of the field with a much lower rate of effluent release than from a failed pond dike. In accordance with the District rule, applicants have proposed to locate the surface water management system more than one hundred feet from the wastewater treatment plant and filtration beds. Even though the rule standards have been met, the purpose of this remand proceeding is to determine whether that amount of separation is adequate to prevent adverse impacts to the water quantity and water quality functions of the system from the operation and location of the filter fields. The Computer Models As a part of their application filed with DER in 1989, applicants' witness Missimer prepared and submitted a report known as "Hydrogeologic Characteristics and Hydraulic Modeling for Effluent Disposal at Keewaydin Club". The report was based on a computer model known as "Modflow" and was designed to show the increase in elevation of the water table for a loading rate of 30,000 gallons per day alternating between the two filtration beds. The purpose of the modeling analysis filed with DER was to investigate whether the plant would continue to discharge effluent to the drainfields under the most extreme conditions. The model demonstrated that the effluent discharge would not be impaired even under conditions that are beyond any reasonable or probable operating conditions. After reviewing the model, DER accepted those results and issued a permit. Utilizing in large part the underlying assumptions and parameters of the Missimer model, and without performing any independent field evaluation on the site, FAS witness Chin ran the model to investigate the impact of the operation of the plant on the system. Because the model used by Dr. Chin was not constructed for the design of a surface water management system, but rather was constructed for the purpose of designing an adsorption field, without modification it provided a more than worst case scenario of impacts associated with the operation of a plant. In this case, Dr. Chin utilized the ultra- conservative assumptions used in designing the adsorption field and made no revisions to the model. Thus, it is found that the model as used by Dr. Chin, and any conclusions drawn from the model alone, are not a sufficient or reasonable basis for evaluating the impact of the plant on the system. The model used by Dr. Chin is not representative of the natural occurring conditions on the island or the reasonably expected plant flow rates. Moreover, in developing the worst case scenario, as opposed to reasonable expectations, both the Chin and Missimer models incorporated the simultaneous occurrence of certain conservative assumptions including an impermeable flow boundary, a year round wet season water table elevation, a conservative rate of transmissivity, and a constant rate of evapotranspiration. The use of these assumptions caused the model output to grossly overstate the effects of the plant on the system in the following manner. First, by assuming a flow barrier on the island, the model had the effect of overestimating the height of the groundwater mound from operation of the plant than would occur if no boundary were used. Second, the assumption of a year-round wet season groundwater level is unrealistic since groundwater levels fluctuate seasonally, receding to near zero NGVD on the island during the dry season. Thus, the model overestimated the height of the groundwater level. Further, by using only the upper ten feet of the water table aquifer in calculating the rate of transmissivity, the model incorporated a much lower rate than would be attained had the entire thickness (74 feet) of the aquifer been used. This also resulted in an over-estimation in the height of the mound from the operation of the plant. Finally, by assuming a constant rate of evapotranspiration, the model "grossly exaggerated" the impact to the groundwater level from operation of the plant. In reality, as the water table increases, the loss of water from evapotranspiration increases significantly and constitutes a major output of a water budget. Besides the foregoing assumptions, the Chin model also assumed a continuous loading rate of 30,000 gallons per day for a period of up to one year. While the District should properly consider the permitted flow rate of the plant in evaluating a worst case of potential impact, there was no evidence substantiating any likelihood of the plant actually producing 30,000 gallons per day for 365 consecutive days in conjunction with all other conservative assumptions discussed above. The more reasonable and accepted method of analyzing the impact of plant flows is to examine the peak month's average day flow over a six-month period. As noted earlier, for the proposed forty-two units, the peak day flow is estimated to be approximately 21,200 gallons per day. Therefore, it is highly probable that actual flow rates will be much lower than the maximum plant capacity of 30,000 gallons per day. By failing to use the more reasonable and realistic reduced flow rates, the Chin model overestimated the elevation of the groundwater level from the operation of the plant. In contrast, the Missimer analysis demonstrates that it is extremely unlikely that the plant output will ever elevate groundwater to the extent that it would reach the system swales by either surface water or groundwater flow. The foregoing modeling assessments, including the criticisms of the Chin model, were concurred in by the District expert. Water Quantity Impacts There is no credible evidence to support a finding that the operation of the plant will adversely impact the ability of the system to provide adequate flood protection and drainage. Indeed, the more credible evidence shows that an alteration of existing drainage patterns will not occur by virtue of the operation of the plant, and the post-development discharge rates will not exceed the pre-development discharge rates. Therefore, the undersigned's previous finding that applicants have provided reasonable assurance that the the system provides adequate protection and drainage is not altered after considering the operation and location of the plant. There is insufficient credible evidence to support a finding that the plant's operation will adversely impact the system functions in such a way as to cause adverse water quantity impacts on receiving waters and adjacent lands. Indeed, the post-development discharge rate approximates the pre-development discharge rate on receiving waters, the ultimate receiving water body (the Gulf of Mexico) has an infinite capacity to receive water, and there are no adjacent lands subject to flooding from discharge of the system regardless of whether there is any impact of the plant on the system. There is no credible evidence to support a finding that the plant will cause the system to have an adverse impact on surface and groundwater levels and flows. Rather, the more persuasive evidence shows that the plant's operation will not result in groundwater elevation in the area of the system that would cause the impoundment of water or prevent the percolation of water into the soil. In addition, the overflow levels for control structures will operate as designed to insure against over-drainage or flooding. Finally, the operation of the filter fields will not cause adverse impacts on surface and groundwater levels and flows. Water Quality Impacts The operation of the plant will not impair the water quality functions of the system. This is because the swales will continue to detain the first flush of run-off allowing the majority of the suspended solids and other pollutants to settle out regardless of the operation of the plant. Further, in the unlikely event the treated wastewater effluent reached the system, it would be indistinguishable from the stormwater or rainfall due to the high level of treatment from the plant, the filter fields and dilution from groundwater and rainfall. The operation of the plant will not cause adverse water quality impacts on the receiving waters. In making this finding, the undersigned notes initially that the plant is permitted by DER, and therefore it is assumed to comply with all DER water quality standards. Second, there is no evidence that the system will impact the operation of the plant. In the event the groundwater mixed with treated effluent resurfaces, there would be no adverse impact to the surface water quality. This is because the treated effluent from the plant exceeds state water quality standards. Once the treated effluent becomes a part of the groundwater, it is unlikely that it will resurface again in the areas of the swales, which are more than one hundred ten feet away. Indeed, in order for the groundwater with effluent to travel that distance, it would have been in the groundwater system for at least one hundred days. This period of time is more than sufficient for the denitrification and adsorption processes to remove all nutrients. Even if the worst case scenario became a reality and the groundwater reached the swale bottoms, it would only result in a wetting of the ground and would not be of sufficient quantity to create a flow of water in the swale to travel off-site impacting a receiving water. In any event, at that point, any groundwater resurfacing that distance away would no longer be effluent. Finally, during abnormal conditions, such as a hurricane or large storm event, the groundwater may rise to the surface and mix with the surface water and enter the system. However, any effluent already significantly diluted under normal circumstances would be indistinguishable from the stormwater or rainfall. Adverse Environmental Impacts There is no credible evidence that the operation of the plant filter fields will adversely impact the system in such a manner as to cause an adverse environmental impact. In so finding, the undersigned rejects the contention that the system will act as a conduit for treated effluent to travel off-site to the ponds, marsh, mangrove areas or receiving waters. The evidence shows that the design of the filter fields and high permeability of the island soils will prevent the surface flow of effluent to the system swales. The elevation of the swales above the groundwater table level will prevent the introduction of effluent into the swale system. In the unlikely event the groundwater reaches the bottom elevation of the swale, there would be no significant environmental impact because the quality of effluent would be indistinguishable from the groundwater due to the high level of treatment and dilution, and such water would still be further treated by the system before discharge to receiving bodies. The location of the plant and system will not have an adverse impact on the gopher tortoise population on the island. Rather, the system should enhance the gopher tortoise population by providing mananged land with vegetation suitable for gopher consumption. Further, the general development on the island will reduce the number of raccoons which prey on gopher eggs and young gophers. Miscellaneous During the remand hearing, FAS presented evidence concerning the impact of tides and mean sea level rise and saline lakes on the island. This evidence was essentially the same as that presented in the prior hearing and was rejected in favor of the more credible evidence presented by the applicants on this issue. Nothing was presented during the remand hearing which would alter these prior findings. During the hearing, and in response to a question by District counsel, witness Missimer agreed it would not be unreasonable to install a few monitoring wells to insure that the system is operating properly. Because this requirement is not unreasonable, will serve a valuable purpose, and has been utilized by the District as a special condition on numerous prior occasions, it should be incorporated into the permit conditions. Even though the evidence clearly shows that seasonal tidal fluctuations would not have an adverse impact on the functioning of the system, if such a tidal incursion were to occur, the placement of a check valve device on the water control structures would prevent sea water from flowing back into the system. Such a device would be a minor addition to the system, would not otherwise affect its design, and if deemed necessary by the District, should be incorporated into the permit conditions. Prior to hearing, the District retained the services of an outside consultant to assist it in preparation for trial. The consultant did not testify at final hearing and prepared no reports. He did make several computer runs, none of which are a part of this record. Among other things, District witness Rogers relied upon the computer runs in formulating his opinion on the issue presented on remand.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that a final order be entered granting the requested permit in accordance with the agency's proposed agency action dated March 28, 1990. DONE and ENTERED this 22 day of March, 1991, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22 day of March, 1991.