Elawyers Elawyers
Ohio| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
EXPLOSIVES AND DIVING SERVICES, INC. vs. DEPARTMENT OF TRANSPORTATION, 84-003792 (1984)
Division of Administrative Hearings, Florida Number: 84-003792 Latest Update: Feb. 27, 1985

Findings Of Fact At some time prior to August 2, 1984, DOT issued bid blanks for a mini- contract for State Project No: 76020-3515, for work consisting of cleaning and guniting a concrete box culvert located on State Road 19, in Putnam County, Florida, approximately one mile south of the Cross Florida Barge Canal. The bid package, signed by C. A. Benedict, District Engineer, for the DOT, specifically reserved the right to reject any and all bids. The bid package broke the work down into three item numbers. The first was mobilization and called for one pricing unit. The second item called for maintenance of traffic at the work site and called for one pricing unit as well. The third area called for restoration of spalled areas (gunite) and called for approximately 437 cubic feet to be priced. In this regard, the plans furnished with the bid package and the bid package itself, in at least three separate locations, called for the bid as to the last item to be priced and paid for on a unit price basis. Petitioner submitted the lowest bid of seven bidders. It was determined to be faulty, however, in that though it properly priced the first two items, it failed to submit a unit price for the third item per unit, submitting instead a total price for the third item based on the entire cubic footage. Petitioner's bid indicated 437 cubic feet priced at a total of $17,832.00. Simple arithmetic permits a division which results in a unit price for each of the 437 cubic feet of $40,805. This last unit price, however, is not reflected on the bid submitted by Petitioner. Petitioner's bid is the only bid of the seven submitted which did not contain a unit price for each of the units in the third item. EDS has been in business since 1980. It performed one previous contract for DOT and is familiar with DOT's rules regarding bidding. It had ample opportunity to examine the plans and the bid blank before submitting its bid and admits that the unit price, though required, was omitted. Petitioner contends, however, that the omission is not a material variance and can be waived by Respondent. Respondent contends, on the other hand, that the failure to list the unit price in the third item is material. This determination is based on the fact that since the bid package calls for payment on a unit basis, the odd one- half cent per unit does not permit even money payment and requires rounding off. Even with this being true, the maximum difference would be one- half cent to be rounded off either upwards or downwards. At some point after opening, at least one of the unsuccessful bidders found out that Petitioner's bid failed to technically conform to the terms of the bid blank and at this point the second lowest bidder, Vann's Sandblasting, whose bid was $4,000.00 higher than that of Petitioner, and who had done several contracts for Respondent in the past, indicated that if petitioner's bid were not rejected, he would file a protest. The one-half cent variance, itself, is not material. Considering all factors, however, the failure to state the unit price may, under certain circumstances, be.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is, therefore: RECOMMENDED THAT Petitioner, EXPLOSIVE AND DIVING SERVICES, INC., be awarded the contract for State project No 76020-3515. RECOMMENDED this 27th day of February, 1985, at Tallahassee, Florida. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904)488-9675 FILED with the Clerk of the Division of Administrative Hearings this 27th day of February, 1985. COPIES FURNISHED: Gail S. Wood, President Explosive and Diving Services, Inc. Post Office Box 200 Clarksville, Florida 32430 Larry D. Scott, Esquire Department of Transportation Haydon Burns Building, MS-58 Tallahassee, Florida 32301 Paul Pappas, Secretary Department of Transportation Haydon Burns Building, MS-58 Tallahassee, Florida 32301

Florida Laws (1) 120.57
# 1
POWER SWEEPING SERVICE, INC. vs DEPARTMENT OF TRANSPORTATION, 91-007592BID (1991)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Nov. 26, 1991 Number: 91-007592BID Latest Update: May 01, 1992

Findings Of Fact By Joint Prehearing Stipulation filed at the time of hearing, the parties agree that bids for contract No. E-4450, the contract in issue here, were opened by the Respondent in Fort Lauderdale on October 11, 1991. Bids were received from five bidders including the Petitioner, Power, and the low bidder, Certified. Based on its evaluation of the bids submitted, on October 18, 1991, Respondent posted an intent to award the contract to Power Sweeping Services, Inc., Petitioner herein. However, thereafter, on October 22, 1991, the Department received a formal protest from the low bidder, Certified, challenging the intent to award. After review of the substance of Certified's protest, Respondent notified all bidders that it would be reposting its intent to award on November 5, 1991, and on that date, did repost, indicating an intent to award the contract in question to Certified, the low bidder. Thereafter, on November 14, 1991, Petitioner timely filed its formal protest, having filed its initial intent to protest on November 6, 1991. The bid blank, which was issued to all prospective bidders at the pre- bid conference held in this matter for a contract to involve mechanical sweeping on Interstate Highway 595 from its eastern terminus to Southwest 136th Avenue, including interchange ramps at I-95, I-595, and State Road 84, contained as a part thereof a notice to contractors which, at page 1 of 4, (page 1 of the 36 page bid package), contained a notation that for contracts of $150,000.00 or less, the bidder would be required to submit, as proof of ability to acquire a performance and payments bond: a notarized letter from a bonding company, bank or other financial institution stating they intend to issue a performance and payment bond in the amount of your bid, should your firm be awarded the project; in lieu of a notarized letter the following may be substituted: a bid guarantee of five percent (5%); or a copy of the contractor's certificate of qualification issued by the Department. This note specifically states that "failure to provide the following required evidence of bonding", as indicated above, with the bid proposal would result in rejection of the contractor's bid. Petitioner submitted a notarized "letter of commitment to issue bond" dated October 8, 1991, by Burton Harris, attorney in fact and resident agent for American Bonding Company. Certified submitted with its bid an un-notarized letter from Mark A. Latini, bond manager with Bonina - McCutchen - Bradshaw Insurance to the effect that "Amwest Surety Insurance Company is the surety for the above referenced contractor and stands ready to provide the necessary performance and payment bond for the referenced bid should CPM be low and awarded the referenced contract." Five bidders submitted bids. Certified was the low bidder with a bid price of $61,474.85. Florida Sweeping, Incorporated was second low bidder with a bid of $67,388.16, but that bid was rejected because an addendum was not noted. Petitioner was third lowest bidder with a bid of $72,290.65. Because Certified's bid as initially submitted did not contain the required notarized letter from the bonding company, its bid was initially rejected. Thereafter, however, Certified's president, Mr. Hanousek, who prepared Certified's bid, and who attended the pre-bid meeting, called the Department's District office the day the bids were opened and was informed that his company's bid was low, but was rejected because its bond commitment letter was not notarized. As a result, he submitted a notice of protest and a subsequent protest to the denial of Certified's bid. A hearing on Certified's protest was not held. When Joseph Yesbeck, the District's director of planning and programs, who was at the time serving as acting district secretary in the absence of the appointed secretary, was contacted by Mr. Hanousek. He reviewed the file and met with Ms. Martin, the District's contract administrator for construction and maintenance contracts and the contracting staff to see what was happening. At that point Ms. Martin explained why Certified's bid had been disqualified, and the matter was thereafter discussed with the District and Department attorneys. When the District secretary came back, Mr. Yesbeck briefed him and recommended that based on the information he had received from the District and Department attorneys, the failure to submit the notarized letter should be considered a non-material deviation and the Certified bid be determined the low responsive bidder. The reasons for this were that the absence of the notary did not really give any competitive advantage to Certified and that ordinarily defects of this nature are routinely allowed to be cured. When the District secretary, on the basis of the information provided by Mr. Yesbeck, decided to repost the contract, Mr. Yesbeck prepared a joint letter of reposting which removed Certified's disqualification and left it as the low bidder. None of the other rejected bidders, including Florida Sweeping and bidder Number 5, which was rejected because its bond proposal was not of a proper character, were advised that they could come in and correct the defects with their bond letters. According to Ms. Martin, the notice to contractors requiring a notarized letter from a bonding company as an alternative to the requirement to post a 5% bid guarantee was designed to promote participation in state contracting by small business and minority business enterprise applicants, so that the bidder does not actually have to post the bond in question. The notarization requirement was put in by the Department but neither Ms. Martin nor any other witness testifying on behalf of the Department was able to indicate why the bond certification had to be notarized. Historically, when the Department has gotten a bid without a notarized bond letter it has been rejected, and in Ms. Martin's experience, she has never known of a protest based on such a denial since she began working with contracts in July, 1988. When she reviews the bids, she reviews the bonding letter for its content as well as seeing whether it is notarized. Here, her reason for initially rejecting certified's bid was solely that the bond commitment letter was not notarized. The decision to reject was not hers alone, however, since she also checked with the District General Counsel who initially advised her that Certified's bond commitment letter was no good. Apparently, counsel changed his position upon discussion of the matter with Mr. Yesbeck and the Department's General Counsel since, according to Mr. Yesbeck, both counsel recommended subsequently that the absence of the notarization not be a disqualification. Further, according to Ms. Martin the requirement for the notarization has been utilized by District 4 since 1987 with all bids requiring it notwithstanding Mr. Hanousek's testimony that he has never seen the requirement before in any of the 6 successful contract's he has had with the Department before. In that regard, however, he admits this is the only contract he has had with District 4. Ms. Martin does not know if the notarization requirement is used in other Districts and no evidence as presented by any party to clarify that issue.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law it is, therefore: RECOMMENDED that a Final Order be entered setting aside the determination that Certified Property Maintenance's bid on Contract No. E4450, Job No. 869069108 was the low responsive bid. RECOMMENDED in Tallahassee, Florida this 28th day of January, 1992. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 28th day of January, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 91-7592BID The following constitute my ruling on all Proposed Findings of Fact pursuant to Section 120.59(2), Florida Statutes submitted by the parties hereto. FOR THE PETITIONER: None submitted. FOR THE RESPONDENT: 1. & 2. Accepted and incorporated herein. Accepted and incorporated herein except for the finding that Certified's bid complied in every respect except the notarization. The assurance by the bonding company was not unqualified but conditioned upon Certified being awarded the contract. Accepted and incorporated herein. & 6. Accepted and incorporated herein. Accepted. Accepted and incorporated herein. Accepted and incorporated herein except for last sentence regarding which see 3., supra. Accepted and incorporated herein. FOR THE INTERVENOR: None submitted. COPIES FURNISHED: Bruce M. Cease, Esquire 2720 West Flagler Street Miami, Florida 33135 Susan P. Stephens, Esquire Department of Transportation 605 Suwannee Street, MS 58 Tallahassee, Florida 32399-0458 Ray Hanousek President Certified Property Maintenance 3203 Robbins Road Pompano Beach, Florida 33062 Ben G. Watts Secretary Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0458 Thornton J. Williams General Counsel Department of Transportation 605 Suwannee Street Tallahassee, Florida 32399-0458

Florida Laws (3) 120.53120.57337.11
# 2
ROBERT A. WEINBERG, TRUSTEE FOR ROBERT ALLAN WEINBERG REVOCABLE TRUST vs DEPARTMENT OF INSURANCE, 98-003593BID (1998)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Aug. 10, 1998 Number: 98-003593BID Latest Update: Nov. 24, 1998

The Issue The issue in this proceeding is whether the Respondent, the Department of Insurance, acted illegally, arbitrarily, fraudulently, or dishonestly in rejecting all bids for lease #460:0119 and not awarding subject lease to Petitioner.

Findings Of Fact The Department of Insurance established a requirement to lease 5371 square feet of office space in Daytona Beach, Florida, and a "Request for Space Need" was approved by the Department of Management Services on February 11, 1998. The Department of Insurance subsequently issued a Request for Proposal (RFP) for lease #460:0119 (Respondent's Exhibit 1). A non-mandatory pre-bid conference was held on June 1, 1998, in Daytona Beach and two prospective bidders, Petitioner and Nova Village Market partnership attended. The RFP provided that proposals which did not meet all mandatory requirements of the RFP would be rejected as non- responsive. The RFP provided for evaluation criteria are awards factors. The awards factors totaled 100 points with no minimum point total required. Ten of the points were allotted for moving costs defined as the costs of relocating communications, networks, furniture and other equipment. This factor gave the current landlord an automatic 10-point advantage since there would be no relocation costs. Moving costs provisions tend to discourage the presentation of bids because the bidders have to overcome an automatic 10-point advantage provided the current landlord. The RFP also provided that all proposals could be rejected, however, such "rejection shall not be arbitrary, but be based on strong justification." None of the conditions of the RFP were questioned or challenged by interested parties. Two responses were received by the Department of Insurance in response to the RFP and these were opened in Respondent's Tallahassee office on July 8, 1998, by Mr. Kip Wells of the Department. One was received from the current landlord, Nova Village Partnership, hereafter Nova, and the other from the Petitioner. The Nova proposal was deemed non-responsive. Neither Nova nor Petitioner contested the determination that Nova's proposal was non-responsive. Only one responsive proposal, the Petitioner's proposal, remained. On July 9, 1998, the Department representative, Mr. Kip Wells, called Petitioner to schedule an appointment for 9:00 a.m., on July 10, 1998, to visit and evaluate the proposed facility. No persons from the Department appeared at the scheduled appointment. At 10:45 a.m., on July 10, 1998, Kip Wells called Petitioner to say that since Petitioner's proposal was the only responsive proposal received, and that "all bids" were being rejected. Mr. Wells testified at hearing. His reason for rejecting the remaining bid was: When I saw that it was obvious the current landlord was not going to be very cooperative, I decided that one choice was not enough. If we were going to have to make a move, we needed more than one thing to choose from. So, I immediately - - since I had already set up with local people in Daytona to tell them that I was coming down to evaluate the bids, I sent them an E-mail and told them that I would not be meeting the following day to evaluate the bids. Mr. Wells decided to reissue the RFP without any moving costs criteria, and redistribute those 10 points among the other award factors. Petitioner filed a Notice of Intent to Protest and then a Formal Protest, both in a timely fashion. There is no state policy prohibiting the award of a lease to a sole bidder on a RFP. The "Leasing Policy" of the Department of Insurance states that "The Lease Administrator, with assistance from the Division employees, will establish bid or quote specifications. These specifications will include special needs for the Division(s) as well as the evaluation criteria upon which to evaluate the proposals." Neither the Department's Lease Policy (Petitioner Exhibit 3) nor the State's Real Property Leasing Manual (Petitioner's Exhibit 4) give the Lease Administrator the authority to reject or evaluate bid responses. Neither does he have a vote in the bid evaluation process. His responsibility is to coordinate the process. Randall Baker, Manager of Private Sector Leasing of the Bureau of Property Management of the Department of Management Services (hereinafter DMS), testified. The DMS prepares a manual as a guideline for user agencies to assist in the leasing of property. The DMS manual is not binding on agencies and DMS has no review oversight; however, their comments on agencies' leases are reviewed by the state auditing authorities and failure to follow the guidelines can result in audit criticism. Baker confirmed that the agency's written procedures as outlined in the RFP were consistent with the DMS guidelines. The DMS manual states as follows regarding the receipt of only one responsive proposal: When only one responsive proposal is received it may be considered and accepted providing the following conditions are documented: Adequate competition was solicited. The rate is within established rental rate guidelines. The proposal meets stated requirements. The proposal was processed as though other proposals were received. The Petitioner's bid was responsive to the RFP and the lease rate bid by the Petitioner was less than the average rate for state leases in the Daytona area and less than the amount budgeted by the Department for this lease. The lease rate by the Petitioner was reasonably priced and competitive. Although the agency failed to complete the process as envisioned, see paragraph 20 below, this was in no way the fault of Petitioner. The Department's leasing policy requires that the lowest and best response to an RFP be determined through cost analysis and evaluation by an evaluation committee. Mr. Wells did not forward Petitioner's bid to or discuss with the evaluation committee Petitioner's bid, but unilaterally rejected it. It was clear from Mr. Wells' testimony that this was his individual decision and was based upon his personal belief that it was the best thing to do.1 At hearing, the stated justification for rejecting "all bids" was that it gave the Department the opportunity to delete the requirement of moving costs from the awards factors; however, the evidence does not indicate that the moving cost provision result in non-competitive bids. The sole responsive bidder was within the local lease price range and within budget. Neither the Respondent nor DMS has established a policy prohibiting the acceptance of a sole responsive bid if there is competition solicited. The Department of Insurance has accepted a sole bid on at least one project in the past. There was no evidence that the RFP was not an open and fair competition. The evidence shows that it was properly advertised, that all conditions were known, and that all interested parties had an equal opportunity to participate. In sum, there was adequate competition in submitting the bids. Mr. Baker testified regarding the policy of DMS. The DMS policy is that if there is one responsive bidder, there has been competitive bidding. The RFP provides that the Respondent may reject all bids if it has strong justification. See paragraph 5 above. Mr. Baker also provided examples of "strong justification for rejecting proposals." His examples include facilities which are proposed outside the required geographic area, prices considerably in excess of state guidelines and agency budgets, specification changes due to modification of the agency's program requirements, and "intervening external forces." No evidence establishing a strong justification for rejecting the Petitioner's bid was presented. Without completing the process and evaluating the Petitioner's bid, the agency never considered whether the bid was in the state's best interest. However, this was not the fault of the Respondent, and the agency's failure to follow its procedures should not inure to its benefits. Further, Because there was no minimum score required on the evaluation criteria of the RFP, there is no need to evaluate Petitioner's proposal because it is the only responsive proposal. For all the reasons stated above, the rejection of Petitioner's bid was contrary to the terms of the RFP, contrary to state policy, and arbitrary.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law set forth herein, it is, RECOMMENDED: That a Final Order be entered which finds that: Respondent's actions in rejecting Petitioner's responsive bid were arbitrary; The Respondent did not follow the requirements set forth in the Department of Insurance Leasing Policy, nor the Department of Management Services Real Property Leasing Manual, or the Request for Proposal itself; That no adverse interest to the State or the Department would have occurred had Petitioner's responsive bid been accepted; and therefore, Petitioner's claim shall be upheld as the lowest cost and best proposal for RFP #460:0119, and that the Department of Insurance shall award Petitioner Lease #460:0119. DONE AND ENTERED this 30th day of October, 1998, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 30th day of October, 1998.

Florida Laws (3) 120.57255.249255.25
# 3
GREENHUT CONSTRUCTION COMPANY, INC. vs DEPARTMENT OF GENERAL SERVICES, 92-001297BID (1992)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Feb. 24, 1992 Number: 92-001297BID Latest Update: Jun. 04, 1992

The Issue The issue for consideration herein is whether the Respondent's proposed award on BID No. HSMV - 90022010 to Dunn Construction Company, Inc., should be upheld.

Findings Of Fact At all times pertinent to the issues herein, the Department was the state agency responsible for the solicitation of bids for and award of contracts for the construction of state buildings in Florida. Both Greenhut and Dunn are qualified contractors who are certified to bid on state construction contracts in general and this procurement in particular. In December, 1991, the Department issued an advertisement for bids for the project in issue herein, the construction of the Kirkman Complex Addition Data Center in Tallahassee, Florida. According to the Advertisement for Bids, all bids "must be submitted in full accordance with the requirements of the Drawings, Specifications, Bidding Conditions and Contractual Conditions, which may be examined and obtained ..." from the Department's designated architect/engineer, Clemons, Rutherford and Associates, Inc. in Tallahassee. Section B-21 of the request for proposals (invitation to bid) reads, in pertinent part: The recommendation for contract award will be for the bidder qualified in accordance with Section B-2 and submitting the lowest bid provided his bid is responsible and it is in the best interest of the Owner to accept it. The Owner reserves the right to waive any informality in bids received when such waiver is in the interest of the owner. Bids received on this project were originally scheduled to be opened and read aloud on January 15, 1992 with the tabulation and Bid Award Recommendation to be posted the following days at the location where the bids were opened. The proposal as originally issued called for the submittal of a Base Bid with four Alternates, 1a, 1b, 2, and 3. Alternate 1a was a deduct for merely extending the existing Johnson Controls System to incorporate the new work instead of providing a totally new and independent control system. Alternate 1b called for adding furniture and landscaping for certain of the rooms shown on the drawings; Alternate 2 called for adding a "shelled" fourth floor as described in the proposal; and Alternate 3, as originally issued, called for: Add a complete fourth floor as indicated in drawings including the finished interior partitions with full HVAC, Plumbing and Electrical Service. Include furniture and landscaping for rooms 414 and 419. (Includes items in Alternate No. 2) As a result of questions received from prospective bidders at the pre-bid conference which indicated some confusion as to the meaning and intent of the Department regarding Alternate No. 3, by letter to all prospective bidders, dated January 8, 1992 the Department's architect indicated: Alternate #3 shall be the fourth floor complete, as shown on drawings, which includes items in Alternate #2. Addendum #1 to the request for bids, dated January 10, 1992, clarified Item 1-3.6), PROPOSAL FORM, of the PROJECT MANUAL to ADD to "Alternate #3", "(Include items in Alternate #2)". Item #2-1 of Addendum #2, dated January 16, 1992, deleted the sentence changed by Item #1- 3.6, and revised the sentence to read as follows: This includes any items required in addition to Alternate #2 to complete the remainder of the work for the Fourth Floor. Information contained at the beginning of each Addendum calls the bidders' attention to the change and indicates that failure to incorporate it may result in disqualification. The due date for bids was extended at the instance of the Department. Both Petitioner and Intervenor submitted bids for this project as did several other concerns on January 23, 1992. Greenhut's base bid was $4,139,000 with a deduct of $63,600 for Alternate 1a, and additions for Alternates 1b, 2, and 3 of $69,500, $239,000, and $209,000 respectively. Greenhut's total bid, therefore, through Alternate 3, was $4,592,900. Dunn's base bid was $4,079,000 with a zero deduct for Alternate 1a, and additions for Alternates 1b through 3 of $67,000, and $428,000. Dunn's total bid, therefore, was $4,574,000 for a difference of $18,900. Greenhut's bid was submitted on a form which provided for the base bid, the deduct for 1a, and the additions for 1b. 2 and 3 with the figure for 3 being those costs in addition to those identified in Dunn's bid was submitted on a prior form which provided for a base bid, a 1a deduction if any, (there was none), and additions for 1b, 2, and 3 with the figure for 3 including the figure listed for 2. An initial review of Dunn's bid form, then, showed a base bid of $4,079,000, no 1a deduction, a 1b addition of $67,000, a 2 addition of $311,000, and a 3 addition of $428,000. This letter figure included the $311,000 figure for Alternate 2, which should have been deducted from the bid during tabulation. When the bids were opened on January 23, 1992 by Mr. Everline, each figure on each bid was read off and listed on the bid tabulation form in the appropriate area. No attention was given at that time to the appropriateness or correctness of the figures listed on each bid form, nor was any attention paid to any other technical requirement of the procurement. This was merely a transfer of figures from the bid form to the tabulation form, and when this was done, Mr. Everline announced to all in attendance, including many contractor representatives, that the "apparent low bidder" was Greenhut. In arriving at that conclusion, Mr. Everline added all of Dunn's figures together without deducting the $311,000 listed for Alternate 2, a figure which was included in the $428,000 figure listed for Alternate 3. This resulted in an incorrectly large total bid for Dunn. Sometime later that day, a representative of Dunn contacted Mr. Everline to indicate that Dunn had inadvertently bid on the wrong form which precipitated its misleading presentation. Mr. Everline properly declined to discuss the matter and referred the Dunn representative to the Department's legal counsel. Sometime thereafter, when the bids had been tabulated and reviewed for responsiveness and legal qualification of bidders, Mr. Everline suggested to representatives of DHSMV that in order to forestall a protest, only so much of the project as extended through Alternate 2 be awarded. DHSMV officials, however, had sufficient funds available for the entire project, including some additional funds, if necessary, for cabling, and insisted they wanted the entire project awarded. The Department's legal counsel, upon review of the situation, concluded that the Dunn's actual bid intent was clear to include the amount listed for Alternate 2 within that listed for Alternate 3, and not to consider the two as additives to each other. It further concluded that Dunn's use of the improper form on which to submit its bid was immaterial and afforded it no improper competitive edge over other bidders. Therefore, it was concluded that Dunn was the low responsive bidder and, on February 4, 1992, the Department issued a Notice of Award to Dunn. Thereafter, Greenhut filed its Petition For Hearing taken as a protest to the award. Both the Department and Dunn agreed that Greenhut had standing to protest the award and that the protest was timely filed. It is so found.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that the Department of General Services enter a Final Order in this case dismissing the protest of Greenhut Construction Company, Inc., in regard to the proposed award of contact in bid number HSMV - 90022010 to Dunn Construction Company, Inc. RECOMMENDED in Tallahassee, Florida this 21st day of April, 1992. ARNOLD H. POLLOCK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of April, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 92-1297 BID The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of fact submitted by the parties to this case. FOR THE PETITIONER: 1. - 6. Accepted and incorporated herein. 7. - 9. Accepted. Accepted. & 12. Accepted and incorporated herein. Accepted. Accepted. & 16. Accepted and incorporated herein. Accepted and incorporated herein. & 19. Accepted and incorporated herein. Accepted. & 22. Accepted and incorporated herein. Argument and not Finding of Fact except for 1st sentence which is accepted. & 25. Accepted and incorporated herein. FOR THE RESPONDENT: 1. - 3. Accepted. 4. - 6. Accepted and incorporated herein. 7. & 8. Accepted. 9. - 12. Accepted and incorporated herein. Accepted. Accepted and incorporated herein. Accepted and incorporated herein. & 17. Accepted and incorporated herein. Irrelevant but accepted as true. Accepted. Accepted and incorporated herein. Accepted. Accepted. Irrelevant but accepted as true. Accepted. Accepted and incorporated herein. Irrelevant. Accepted and incorporated herein. Accepted. FOR THE INTERVENOR: Accepted. - 5. Accepted and incorporated herein. Accepted and incorporated herein. & 8. Accepted and incorporated herein. Accepted and incorporated herein. Accepted and incorporated herein. Accepted and incorporated herein. - 15. Accepted. 16. - 19. Accepted. 20. & 21. Accepted. Accepted and incorporated herein. & 24. Accepted. COPIES FURNISHED: Robert A. Emmanuel, Esquire 30 South Spring Street Post Office Drawer 1271 Pensacola, Florida 32596 Sylvan Strickland, Esquire Suite 309, Knight Building 2737 Centerview Drive Tallahassee, Florida 32399-0950 Harry R. Detwiler, Jr., Esquire 315 S. Calhoun Street, Suite 600 Tallahassee, Florida 32301 Ronald W. Thomas Executive Director Department of General Services Suite 307, Knight Building 2737 Centerview Drive Tallahassee, Florida 32399-0950 Susan Kirkland General Counsel Department of General Services Suite 309, knight Building 2737 Centerview Drive Tallahassee, Florida 32399-0950

Florida Laws (1) 120.57
# 4
ALL AMERICAN COMPANIES vs DEPARTMENT OF ENVIRONMENTAL PROTECTION, 02-002776BID (2002)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jul. 12, 2002 Number: 02-002776BID Latest Update: Oct. 25, 2002

The Issue At issue in this proceeding is whether the Department of Environmental Protection's decision to reject all bids submitted for the project entitled BDRS 52-01/02 was illegal, arbitrary, dishonest, or fraudulent.

Findings Of Fact Parties Petitioner, All America Homes of Gainesville, Inc. (All America), is a corporation doing business in the State of Florida. All America submitted a timely written bid in response to the Department's ITB and filed timely protests to the Department's actions. The Respondent, the Department of Environmental Protection, is an agency of the State of Florida which manages and operates state parks under its jurisdiction, and solicits construction projects in state parks, pursuant to Chapter 258, Part I, Florida Statutes, through its Division of Recreation and Parks, Bureau of Design and Recreation Services. The ITB In November, 2001, the Department issued an ITB on a construction project entitled Hillsborough River State Park Concession Building, project number BDRS 52-01/02. The ITB included the Bid Specifications for the project. Bids were required to be submitted no later than 3:30 p.m. on Tuesday, December 18, 2001, at the Bureau's Tallahassee, Florida, office. The written Specifications define several terms, including, but not limited, to the following: ADDENDUM: A written explanation, interpretation, change, correction, addition, deletion, or modification, affecting the contract documents, including drawings and specifications issued by the OWNER [Department] and distributed to the prospective Bidders prior to the bid opening. ALTERNATE BID: Separate optional bid item for more or less project requirement used for tailoring project to available funding. Also may consist of alternate construction techniques. BASE BID: Formal bid exclusive of any alternate bids. BID FORM: The official form on which the OWNER requires formal bids to be prepared and submitted. ORAL STATEMENTS: Verbal instruction. NOTE: No oral statement of any person, whomever shall in any manner or degree modify or otherwise affect the provisions of the contract documents.[1] SEALED BID: The formal written offer of the Bidder for the proposed work when submitted on the prescribed bid form, properly signed and guaranteed. The Bid Specifications also contained the following relevant sections: Alternatives If the OWNER wishes to learn the relative or additional construction cost of an alternative method of construction, an alternative use of type of material or an increase or decrease in scope of the project, these items will be defined as alternates and will be specifically indicated and referenced to the drawings and specifications. Alternates will be listed in the bid form in such a manner that the Bidder shall be able to clearly indicate what sums he will add to (or deduct from) his Base Bid. The OWNER will judge for himself that such alternates are of comparable character and quality to the specified items. The Order of the alternate may be selected by the Department in any sequence so long as such acceptance out of order does not alter the designation of the low bidder. ADDENDA If the Consultant[2] finds it would be expedient to supplement, modify or interpret any portion of the bidding documents during the bidding period, such procedure will be accomplished by the issuance of written Addenda to the bidding documents which will be delivered or mailed by the OWNER'S Contracts section to all bidders who have requested bidding documents. Interpretation No interpretation of the meaning of the drawings, specifications or other bidding documents and no correction of any apparent ambiguity, inconsistency or error therein will be made to any Bidder orally. Every request for such interpretation or correction should be in writing, addressed to the Consultant. All such interpretations and supplemental instructions will be in the form of written Addenda to the bidding documents. Only the interpretation or correction so given by the Consultant in writing and approved by the OWNER shall be binding, and prospective Bidders are advised that no other source is authorized to give information concerning, or to explain or interpret, the bidding documents. B-16 Bid Modification Bid modification will be accepted from Bidders, if addressed as indicated in Advertisement for Bids and if received prior to the opening of bids. No bid modification will be accepted after the close of bidding has been announced. Modifications will only be accepted if addressed in written or printed form submitted with the bid in sealed envelopes. Telegrams, facsimiles, separate sealed envelopes, written on printed modifications on the outside of the sealed envelopes will not be accepted. All bid modifications must be signed by an authorized representative of the Bidder. Modification will be read by the OWNER at the opening of formal bids. B-21 Rejection of Bids The OWNER reserves the right to reject any and all bids when such rejection is in the interest of the State of Florida, and to reject the bid of a bidder who the OWNER determines is not in a position to perform the work. B-23 Award of Bid . . .The qualified Bidder submitting the lowest bid will be that Bidder who has submitted the lowest base bid plus any selected alternates. . . . The OWNER reserves the right to waive any minor irregularities in bids received when such waiver is in the interest of the OWNER. The Award of Bid will be issued by the OWNER only with responsible Bidders, found to meet all requirements for Award of Bid, qualified by experience and in a financial position to do the work specified. Each bidder shall, if so requested by the OWNER, present additional evidence of his experience, qualifications and ability to carry out the terms of the Agreement. (Emphasis in original, except for Section B-10.) The Bid Form is included with the Specifications and provides in part: Base Bid: Furnish labor, equipment, Lump Sum $ supervision and material to construct a new concession building of 2940 square feet located at the Hillsborough River State Park along with the alteration of the existing concession building according to plans and specifications. Alternate #1: Furnish labor, equipment, Add Amt.$__ supervision and material to renovate the existing concession building according to plans and specifications. There is a separate section for "Allowances," i.e., Section 01210, for the Hillsborough State Park. This section provides in part: SECTION 01210 – ALLOWANCES * * * 1.2 SUMMARY This Section includes administrative and procedural requirements governing allowances. Certain materials and equipment are specified in the Contract Documents and are defined by this [sic] specifications as material and labor to be provided against a pre-determined allowance. Allowances have been established in lieu of additional requirements and to defer selection of actual materials and equipment to a later date when additional information is available for evaluation. If necessary, additional requirements will be issued by Change Order. * * * 3.3 SCHEDULE OF ALLOWANCES A. Allowance #1: Include in the base bid an allowance for the purchase and installation of. . . kitchen equipment. . . . The total dollar amount of the allowance to be included shall be $12,000.00. There is also a separate section for "Alternates," i.e., section 01230, for Hillsborough River State Park, which provides in part: SECTION 01230 – ALTERNATES * * * 1.3 DEFINITIONS Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the Bidding Requirements that may be added to or deducted from the Base Bid amount if OWNER decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate alternate into the Work. No other adjustments are made to the Contract Sum. . . . . 3.1 SCHEDULE OF ALTERNATES A. Alternate No. 1: Renovate the existing concession building in its entirety as shown in the drawings and specified herein. (emphasis added.) At this stage of the bidding documents, the contractor/bidder is requested to provide a Base Bid/Lump Sum on the Bid Form to "[f]urnish labor, equipment,. . .to construct a new concession building," and to provide an additional and separate amount for Alternate No. 1 to "[f]urnish labor, equipment, . . . to renovate the existing concession building." On December 13, 2001, the Bureau issued "Addendum No. One (1)" (written by the architect) to the ITB on the "Hillsborough River State Park – Concession Building." The Addendum contained the following relevant sections: Specification Section 01210: Allowances Add the following new paragraph 3.3.B: ”Allowance #2: Include in the base bid an allowance for the renovations of the existing concession building; renovations shall be defined by the Owner. The total dollar amount of the allowance to be included shall be $25,000." Specification Section 01230: Alternates Modify paragraph 3.1.A. as follows: "Alternate No. 1: Renovate the existing concession building as defined by the Owner, and as provided for under Section 01210, Allowances." (emphasis added.) Each contractor was required to sign the Addendum and attach it to the bid. By definition, and pertinent here, an addendum is an additional written instruction to a contractor during the bidding process. Based on the weight of the evidence, the purpose of this Addendum was to require the contractor to include a $25,000.00 Allowance (for Allowance # 2) in the Base Bid, for the work which might be performed if the Department requested the work to be performed for Alternate No. 1, i.e., for the renovation of the existing concession building.3 (The Department's architect decided it would cost approximately $25,000.00 to renovate the existing concession building, hence Allowance # 2.) In other words, the Addendum does not have a specific dollar amount to be included for Alternate No. 1. Rather, the $25,000.00 is an Allowance for the work described as Alternate No. 1, but the amount is to be included in the Base Bid and not as a separate line item, dollar amount. But, importantly, the Addendum did not delete the potential work to be performed as described in Alternate No. 1, although Mr. Bowman and others believed that the Addendum deleted Alternate No. 1. It deleted the necessity to place a specific dollar amount on the Bid Form for Alternate No. 1. (Mr. Bowman is a registered Professional Engineer and a licensed contractor. He has worked for the Department for 15 years and has served as Bureau Chief for two years. He supervises the contract section and the design section, which was responsible for preparing the technical plans and specifications and bidding out the job.) Mr. Bowman offered the following explanation why he believed the Addendum was confusing: Okay. I think the confusion that was created, you know, I think the addendum in itself, you know, said add $25,000 to the base bid, but then on the bid form, it still had the space down there for alternate number one, which alternate number one, which alternate number one had become $25,000 that was to be allowed for the concession building, and I think that's where the confusion came in because I think they were still confused, that they weren't really sure that they should not put that 25 down there but they knew they had been told in the addendum to do it and I think that's the reason for the notes and we got to the correspondence on the bid form, was they wanted to make sure that that's what we were wanting to do. And I think that's where the confusion came in. Like I said, it's always, if you could go back and do it again, it would be much wiser just to issue a whole new bid form and then we wouldn't be here today. But, we didn't do that. Okay. So, that's why we are here. The language in this Addendum, when read with the original Bid Specifications, apparently caused confusion with some of the bidders on the project. Several bidders called Marvin Allen (an architect and project manager for the Department's Bureau of Design and Recreation Services) prior to the submission of the bids, to clarify how the $25,000.00 Allowance should be shown on the Bid Form. (Mr. Allen did not author any of the specifications, including the Addendum.) He was listed as a contact person. He did not contact any bidders. But, Mr. Allen recalled telling each bidder who asked that the Allowance of $25,000.00 should be included in the Base Bid. But, he does not recall the names or numbers of the bidders who called, "possibly" three, four or five. Mr. Allen believed the Addendum was clear. According to Mr. Allen, the bidders who called him found the Addendum confusing. The oral responses to the bidders can be construed as interpretations of the Addendum. However, pursuant to Section B- 10 of the Specifications, any such interpretations were required to "be in the form of written Addenda to the bidding documents." Also, any such questions should have been in writing. If Section B-10 were complied with, all bidders would have been potentially on the same footing, or, at the very least, would have had access to a written clarifying document. Opening of the Bids On December 18, 2001, the bids were opened by Mike Renard, Contracts Manager with the Bureau of Design and Recreation Services, and Susan Maynard, Administrative Assistant. Mr. Dwight Fitzpatrick, a representative of All America, also attended the bid opening. The Bid Form submitted by Nelco showed a Base Bid of $355,478.00 (Lump Sum $355,478.00), and also showed an amount of $25,000.00 on the Alternate # 1 line (Add Amt. $25,000.00). See Finding of Fact 6. (It was clear to Mr. Renard that the $25,000.00 should have been included on Nelco's Base Bid. But Mr. Renard believed that Nelco submitted a responsive bid because the Department only accepted the Base Bid. Mr. Bowman agreed.) Nelco was the only one of five bidders to have a dollar amount in the Alternate #1 line under "Add Amt. $ ." All America submitted the second lowest Base Bid of $362,000.00. There was also a hand-written note on the All- America Bid Form that stated: "Addenda # 1 instruction to place $25,000 allowance in both Base Bid and as alternate # 1." Another hand written note was located below the "Add Amt. $-0-" line: "amount added in Base Bid with $25,000 allowance per Marvin Allen." The Department considered All America's bid responsive. It is a fair inference that three out of five of the other Bid Forms contained language indicating that the bidders were relying on Addendum No. One by placing the $25,000.00 Allowance in the Base Bid.4 It is uncertain whether they did so in light of the instructions of Mr. Allen concerning how to complete the Bids Forms. However, given the nature of the calls to Mr. Allen, there is a reasonable inference that there was some confusion among some of the bidders. The Department determined that Nelco submitted the lowest Base Bid, but the Department's staff had a question as to whether Nelco had included the $25,000.00 in its Base Bid. After conferring with his superiors, Mr. Renard was instructed to call Nelco to make certain that its Base Bid included the Allowance amount ($25,000.00). Mr. Renard spoke with Steve Cleveland, Nelco's Project Manager, "to verify the fact that [Nelco] had the allowance in their base bid." Mr. Cleveland orally confirmed that Nelco's Base Bid included the $25,000.00 Allowance. Mr. Renard asked Mr. Cleveland to send him a letter verifying this statement. Mr. Renard viewed this inquiry as a request for clarification or verification, not an opportunity for Nelco to modify its bid. Mr. Bowman agreed. (Mr. Renard did not believe Addendum No. 1 was confusing.) In a letter dated December 20, 2001, Mr. Cleveland confirmed that Nelco’s Base Bid of $355,478.00 included the Allowance amount and that Nelco could still perform the contract if the $25,000 Allowance was removed from its Base Bid pursuant to the ITB, i.e., that Nelco would perform the contract for $355,478.00 less $25,000.00, or $330,478.00, if the Department did not accept Alternate # 1 and the Allowance. (An alternate does not have to be accepted by the Department.) According to Mr. Renard, Mr. Cleveland never mentioned modifying, changing, or altering Nelco's bid. The Department only accepted the Base Bid for each bid. Mr. Renard did not consider it unusual to call a bidder or contractor to verify information to determine whether they can or cannot perform the work at the stipulated price. He considered it common to make this inquiry. Also, it was common in Mr. Bowman's experience to call a bidder to get clarification. Mr. Renard was not aware of any statute or rule which authorizes the Department to request clarification from a bidder after the bids are opened. Mr. Renard was more familiar with the bid forms than Mr. Allen. After receiving Mr. Cleveland's letter, the Department determined that Nelco submitted the lowest Base Bid and that the $25,000.00 amount that Nelco wrote on the Bid Form Alternate # 1 line, was a minor irregularity in the bid which the Department, as the Owner, could waive pursuant to the ITB. On December 20, 2001, the Department posted the Tabulation of Bids showing the anticipated award of the contract to Nelco. At the hearing, an unsigned letter on Department letterhead was introduced, which was addressed to Nelco and stated that Nelco submitted the apparent low bid. However, Mr. Renard testified that these letters are prepared routinely, but not mailed out without his signature. Mr. Renard did not recall signing the letter or ever sending out such a letter to Nelco. On December 21, 2001, the Department received a Notice of Intent to Protest letter from Allen E. Stine, the President of All America. In his letter, Mr. Stine stated that Nelco’s bid should have been rejected for failure to follow the specified format as per Addendum No. 1, or adjusted to have the $25,000.00 amount added to their Base Bid. Bid Protests All America filed a written formal bid protest on January 4, 2001. On January 9, 2001, Cindy Otero of All America, notified Mr. Renard by letter, and stated that Mr. Stine was available for a hearing regarding the bid protest. On January 28, 2002, Mr. Renard returned All America's check for the bond, stating that it was unnecessary. Mr. Stine recounted a number of unanswered telephone calls after the first protest was filed. During one conversation, Mr. Renard recalled Mr. Stine saying to him, "You can't do this, you can't do this." After receiving the first formal protest, the Department staff consulted with legal staff and reviewed the documents and bid procedures. Based on the number of questions received concerning the Addendum and the hand-written notes on several of the bid forms, Mr. Bowman, Bureau Chief, determined that the bid documents were confusing and ambiguous. (Mr. Bowman stated that this was their first bid protest in his 15 years with the Department.) Therefore, Mr. Bowman decided that it would in the best interest of the State of Florida to reject all of the bids pursuant to the Bid Specifications. Mr. Bowman felt that the ITB should be re-written in order to make it clearer and allowing all of the bidders to re-bid the project without any confusion or ambiguity. Mr. Stine stated that his "senior estimator" told him that the bid language "could be confusing." He and his "senior estimator" had a discussion about whether the Allowance should have been placed in the Base Bid or not. At the time of submission of All America's bid, Mr. Stine was clear that the Allowance should be placed in the Base Bid, especially after calling Mr. Allen. But, his senior estimator was not so clear. In order to appease him, Mr. Stine placed the hand-written note on All America’s proposal. Mr. Stine essentially, "cleaned" up his proposal. At the hearing, Mr. Bowman testified Rule 60D-5.0071, Florida Administrative Code, see Conclusion of Law 59, does not list "confusing or ambiguous bid specifications" as one of the circumstances allowing for the rejection of all bids. However, Mr. Bowman later stated during the hearing that he believed the circumstances listed in Rule 60D-5.0071 were not the only circumstances authorizing the Department to reject all bids. Mr. Bowman testified that he believed that general confusion among the bidders caused by the ambiguous ITB constituted sufficient grounds for rejecting all bids. Mr. Bowman was advised by legal counsel that rejecting all of the bids would probably result in another bid protest by Nelco, All America, or both. Thus, the Department decided to delay addressing All American’s first protest until after posting the rejection of all bids and receiving the subsequent protests, so that all of the protests could be resolved at once in an efficient and economical manner. Notwithstanding the Department's justifications for rejecting all bids and not proceeding on All America's initial protest, the record is unclear why the Department waited several months to reject all bids. On May 13, 2002, the Department posted the rejection of all bids. On May 16, 2002, the Department received a formal written protest of the rejection of all bids filed by All America. On May 17, 2002, Jerome I. Johnson, attorney for the Department, contacted Mr. Robert A. Lash, All America's counsel at the time, concerning the resolution of All America’s formal protest. (Before the final hearing, Mr. Lash, with All America's consent, withdrew as counsel for All America.) The parties agreed to suspend formal bid protest procedures until a meeting could be held between the parties in an attempt to resolve the protests. Mr. Johnson sent a letter dated May 21, 2002, to Mr. Lash confirming this conversation. On June 26, 2002, a meeting was held among the Department staff, legal staff, and Mr. Lash and Mr. Stine, representing All America. The parties were unable to resolve the protests. At the conclusion of the meeting, the parties agreed that formal protest procedures would not be implemented until Mr. Stine could confer further with his counsel. In a letter dated July 5, 2002, Mr. Lash stated that his client wished to proceed with formal protest procedures and requested an administrative hearing on the protests. Are the Specifications and Bid Documents Ambiguous and Was There Confusion? The parties stipulated that "[t]he Addendum language was confusing," notwithstanding the testimony of several witnesses that they were not confused. The Department's determination that the bid Specifications, including the Addendum, and the Bid Form, which remained unchanged after the Addendum was issued, were confusing and ambiguous, is supported by the weight of the evidence. This is particularly true regarding the Bid Form. The Addendum required the bidder to include an Allowance of $25,000.00 in the Base Bid for work described as Alternate # 1. But the Bid Form was unchanged to reflect the Addendum changes. The Bid Form retained a line for the bidder to submit an additional amount for Alternate # 1. Further, it appears that several bidders were confused, including, Mr. Stine, who spoke with Mr. Allen and requested and received clarification. Further, it is unclear whether all of the bidders, including Nelco, were aware of the oral interpretations or clarifications of the Addendum rendered to some of the bidders. Rejection of All Bids Based upon the foregoing, given the standard of review in this proceeding discussed in the Conclusions of Law, the weight of the evidence indicates that the Department's action, in rejecting all bids, was not illegal, arbitrary, dishonest, or fraudulent. The Department's staff was well-intended and made some mistakes along the way, e.g., by not changing the Bid Form, which they readily admit. But there was a rationale for rejecting all bids under the circumstances.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Department issue a final order dismissing All America’s Petition to Prevent Rejection of Bids and Award Contract to Petitioner and denying All America's request for attorney’s fees and costs. DONE AND ENTERED this 24th day of September 2002, in Tallahassee, Leon County, Florida. CHARLES A. STAMPELOS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 24th day of September 2002.

Florida Laws (3) 120.569120.57120.595
# 6
DIVERSIFIED DESIGN ENTERPRISES vs SEMINOLE COUNTY SCHOOL BOARD, 90-002357BID (1990)
Division of Administrative Hearings, Florida Filed:Sanford, Florida Apr. 20, 1990 Number: 90-002357BID Latest Update: May 22, 1990

The Issue The issue in this case is whether Respondent properly rejected the bid of Petitioner.

Findings Of Fact Respondent issued on February 28, 1990, an invitation to bid concerning the installation of bleachers at a high school ("ITB"). The ITB was duly advertised. Among the bidders was Interkal, Inc., which is a manufacturer of bleachers. The Interkal bid, which was timely submitted, was executed by its president. The Interkal bid contained a bid bond naming Interkal as principal and a certification from the secretary of Interkal reflecting a corporate resolution authorizing the execution of all bid documents on behalf of Interkal by its corporate officers. The Interkal bid disclosed two subcontractors. The supplier was shown as Interkal, and the erector was shown as Petitioner. Petitioner is the authorized factory representative for Interkal in Florida. As such, Petitioner solicits business and installs and removes bleachers on behalf of Interkal. As compensation, Petitioner receives commissions for such work from Interkal. However, the shareholder and chief executive officer of Petitioner is not a shareholder or officer of Interkal. In addition, Petitioner is not authorized to execute bid documents on behalf of Interkal. Petitioner is no more than a Subcontrator of Interkal. The bidder in this case was Interkal, not Petitioner, even though Petitioner handled much of the paperwork or its manufacturer. When an unrelated bidder was awarded the contract, Petitioner filed a formal written protest in its name. Interkal has not participated as a party in the subject proceeding.

Recommendation Based on the foregoing, it is hereby RECOMMENDED that Respondent enter a Final Order dismissing the petition of Diversified Design Enterprises. ENTERED this 22nd day of May, 1990, in Tallahassee, Florida. ROBERT D. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of May, 1990. COPIES FURNISHED: Ned N. Julian Stenstrom, McIntosh, et al. P.O. Box 1330 Sanford, FL 32772-1330 William Merkel, President Diversified Design Enterprises 321 N.E. Second Avenue Delray Beach, FL 33444 Robert W. Hughes, Superintendent Seminole County School Board 1211 Mellonville Avenue Sanford, FL 32771

Florida Laws (2) 120.53120.57
# 7
ELIZABETHAN DEVELOPMENT, INC. vs DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 90-004064BID (1990)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Jun. 29, 1990 Number: 90-004064BID Latest Update: Jul. 27, 1990

Findings Of Fact On or about January 26, 1990, the Respondent sought competitive bids for Lease Number 590:2154 for the lease of certain office space in Brandon, Florida. The bid opening occurred on March 1, 1990, and Intervenor was determined to have submitted the lowest responsive bid. In addition to Intervenor's bid, the only other bid received in response to this invitation to bid was from Regina M. Hasey, for whom Petitioner purports to act as agent in this proceeding. A condition set forth in the invitation to bid was that bids would remain valid for a minimum of forty-five days following the bid opening. There is no dispute that Regina M. Hasey withdrew her bid and terminated her offer on April 18, 1990, after the expiration of this forty-five day period. Petitioner's representative admitted that he knew of Hasey's termination of her offer prior to the filing of this protest, and that he had been copied on the letter of April 18, 1990 withdrawing her bid. On or about May 8, 1990, the Department notified Hasey of its intent to award this lease to Intervenor, and on May 10, 1990, the Petitioner filed its notice of protest concerning this award claiming that Intervenor's bid was not responsive to the parking requirements in the invitation to bid. Petitioner is designated in the Hasey bid as agent for Hasey, and it is clear that Petitioner did not submit this bid in its own right, but rather solely as agent for Hasey. Petitioner's protest was filed without any reasonable inquiry by Petitioner into the facts surrounding the Respondent's invitation to bid, Intervenor's bid, and the legal consequences of the withdrawal of Hasey's bid. As a result of Petitioner's protest, the award of Lease Number 590:2154 to Intervenor has been delayed, at this stage of the proceeding, for almost three months, and the Respondent and Intervenor have had to incur legal expenses to oppose Petitioner's protest and proceed with this award. There is no evidence in this record to indicate that Petitioner filed this protest in an attempt to change the agency's mind regarding the award of this lease to Intervenor, and in fact there is no possible basis upon which this award could have been made to Petitioner after Hasey withdrew her bid. As such, Petitioner's protest was entirely frivolous. See Mercedes Lighting and Electrical Supply v. Department of General Services, et al., 12 F.A.L.R. 1912 (Fla. 1st DCA 1990).

Recommendation Based on the foregoing, it is recommended that the Respondent enter a Final Order dismissing Petitioner's protest for lack of standing, and awarding Lease Number 590:2154 to Intervenor. DONE AND ENTERED this 27th day of July, 1990, in Tallahassee, Leon County, Florida. DONALD D. CONN Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of July, 1990. APPENDIX Rulings on Intervenor's Proposed Findings of Fact: Adopted in Findings 1 and 2. Adopted in Finding 3. 3-4. Adopted in Finding 4. Rejected as procedural matters and otherwise as unnecessary. Adopted in Finding 3. Rejected as unnecessary. Adopted in Findings 3 and 4. Adopted in Finding 6. 10-11. A ruling has been reserved on the issue of an award of attorney's fees and costs, and these proposed findings are solely related to that issue which has not been addressed in this Recommended Order. Copies furnished: Jack Farley, Esquire District 6 Legal Office 4000 West Dr. Martin Luther King, Jr., Blvd. 5th Floor, Room 520 Tampa, FL 33614-9990 Alan Taylor P. O. Box 7077 Winter Haven, FL 33883-7077 Mark A. Brown, Esquire Theo J. Karaphillis, Esquire P. O. Box 3239 Tampa, FL 33601 R. S. Power, Agency Clerk 1323 Winewood Blvd. Building One, Room 407 Tallahassee, FL 32399-0700 John Miller, General Counsel 1323 Winewood Blvd. Tallahassee, FL 32399-0700

Florida Laws (2) 120.53120.57
# 8
MARVIN`S GARDEN AND LANDSCAPE SOUTHEAST SERVICE, INC. vs. DEPARTMENT OF TRANSPORTATION, 85-003337BID (1985)
Division of Administrative Hearings, Florida Number: 85-003337BID Latest Update: Dec. 02, 1985

Findings Of Fact Both DOT and Weekley submitted proposed Recommended Orders. Their proposed findings of fact have generally been adopted here but are addressed in detail in Appendix A, attached and incorporated in this Recommended Order. On or before July 31, 1985, DOT received sealed bids from three bidders for State Project Nos. 86070-3492 and 93220-3403, involving landscaping of interchanges in Broward and Palm Beach counties. Marvin's Garden was the apparent low bidder, with a total of $389,112.19 shown on the face sheet of the bid blank form. Weekley was the next lowest bidder with a total of $419,899.56, and P. J. Constructors, Inc., was the highest bidder with a total of $458,805.90. After review of the bid documents for compliance with DOT bid procedures, a discrepancy was found in the Marvin's Garden bid and DOT notified the parties by letter dated August 20, 1985, that Weekley was the apparent low bidder on the project. The discrepancy was found on page 001 of the bid blank form submitted by Marvin's Garden. For item 570-11, "Water for Plant Establishment," under the column, unit price written in words, Marvin's Garden showed "fourteen thousand two hundred eighty two dollars and sixty six cents." The column, unit price in figures, showed "14,282.66," and the final column, headed "amounts" showed "14,282.16." The bid item was supposed to show the unit price for a thousand gallons of water (which price was to be written in both words and figures) and a total, or extension price for 3,743.125 thousand gallons of water. When the unit price on Marvin's Garden's bid was multiplied by 3,743.125 (number of units), the resulting total price for that bid item was $53,461,781.71. This figure was entered on the form in red ink and was initialled by Raymond Patrick Haverty, the DOT reviewer. Marvin's Garden's total bid for the project was then adjusted to $53,836,611.04, a figure far in excess of either Weekley's or P. J. Constructors' bids. Marvin Gross is the individual responsible for preparing and submitting bids for his corporation. He has been doing bid work for DOT for approximately 20 years and is thoroughly familiar with the bid procedures, forms and standard specifications. He attributes the irregularity on his submission to his "tunnel vision." Unit prices are significant because the quantity designated by DOT is merely an approximate, best guess by the Department engineers. For item 570-II, unpredictable weather conditions will ultimately dictate exactly how much water will be necessary to successfully complete the landscape project. That exact quantity times the unit price will be the basis of payment to the contractor. DOT found no violations of bid requirements in the bids of Weekley and P. J. Constructors, Inc., and none have been raised in this proceeding.

Recommendation For the foregoing reasons, a final order should be issued declaring Weekley the lowest responsible bidder on project Nos. 86070-3492 and 93220-3403, and the contract awarded accordingly. DONE and ORDERED this 2nd day of December 1985, in Tallahassee, Florida. Hearings Hearings MARY CLARK, Hearing Officer Division of Administrative The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative this 2nd day of December 1985. APPENDIX In accordance with Section 120.59(2) Florida Statutes, the following are recommended rulings on proposed findings of fact submitted by Respondent and Intervenor in this case. Respondent's Paragraph: Corresponding R. O. Paragraph or basis for rejection: The corporate status and the addresses of the bidders are not material. See Paragraph 1, R.O. See Paragraph 2, R.O. and Conclusion of law 2, R.O. See Paragraph 3, R.O. See Conclusion of law 2, R.O. See Paragraph 3, R.O. See Paragraph 6, R.O. See Paragraph 2, R.O. Intervenor's Paragraph: Corresponding R.O. Paragraph or basis for rejection: See Paragraphs 1 and 2, R.O. Facts which relate to the composition of bid packages are not material. See Paragraph 3, R.O. See Paragraph 3, R.O. See Conclusion of law 2, R.O. See Paragraph 3, R.0. See Conclusion of law 5, R.O., relating to the specifications of the department. The remainder of the paragraph proposed is immaterial. See Paragraph 5, R.O. COPIES FURNISHED: Thomas E. Drawdy, Secretary Department of Transportation Haydon Burns Building Tallahassee, Florida 32301 A. J. Spalla, Esquire General Counsel 562 Haydon Burns Bldg. 605 Suwannee Street Tallahassee, Florida 32301 Mr. Marvin Gross, President Marvin's Garden and Landscape Services, Inc. 37 North McIntosh Sarasota, Florida 33582 Mel L. Wilson, Esquire Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, Florida 32301 Harry R. Detwiler, Jr., Esquire HOLLAND & KNIGHT Post Office Drawer 810 Tallahassee, Florida 32302

Florida Laws (3) 112.19120.53120.57
# 9
BUTLER CONSTRUCTION COMPANY vs DEPARTMENT OF CORRECTIONS, 93-003971BID (1993)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jul. 22, 1993 Number: 93-003971BID Latest Update: Sep. 15, 1993

Findings Of Fact Based upon the evidence adduced at hearing, and the record as a whole, the following Findings of Fact are made: In March of 1993, the Department issued an Advertisement for Bids (hereinafter referred to as the "Advertisement") through which it solicited the submission of bids on a construction project (Department Project No. NV-30A, which is hereinafter referred to as the "Project") involving the expansion of the water treatment facility at the Martin Correctional Institution. The Advertisement, along with the other bid documents issued in conjunction with the Advertisement, including, but not limited to, the Instructions to Bidders (hereinafter referred to as the "Instructions") and the Proposal Form, were compiled in a two-volume Specifications Manual (hereinafter referred to as the "Manual") that was made available for public inspection. Section B of the Manual's first volume contained the Instructions. Section B-2 2.A.(11) thereof provided that "Section 01420 as contained in the Technical Specifications must be submitted and the qualifications listed therein must be satisfactory to the Owner and the Engineer. " "Section 01420 as contained in the Technical Specifications" was a "Bidder's Qualification Form, Reverse Osmosis Treatment System Component" (hereinafter referred to as the "R.O. Form"), on which the bidder was to provide "R.O. [Reverse Osmosis] System Supplier" information. The R.O. Form repeated the directive that the bidder was to "[r]eturn [the] [c]ompleted [R.O.] Form [w]ith [its] proposal." Section B-14 of the Instructions addressed the subject of "preparation and submission of bids" and provided, in pertinent part, as follows: Each Bidder shall copy the proposal form on his own letterhead, indicate his bid prices thereon in proper spaces, for the Base Bid and for alternates on which he bids. . . . Proposals containing . . . . items not called for or irregularities of any kind may be rejected by the Owner. Section B-16 of the Instructions addressed the subject of "disqualification of bidders" and provided, in pertinent part, as follows: More than one bid from an individual, firm, partnership, corporation or association under the same or different names will not be considered. Reasonable grounds for believing that a Bidder is interested in more than one proposal for the same work will cause the rejection of all proposals in which such Bidders are believed to be interested. The subject of "contract award" was addressed in Section B-21 of the Instructions, which provided, in pertinent part, as follows: . . . The recommendation for contract award will be for the bidder qualified in accordance with Section B-2 and submitting the lowest bid provided his bid is responsible and it is in the best interest of the Owner to accept it. The qualified bidder submitting the lowest bid will be that bidder who has submitted the lowest price for the base bid, or the base bid plus additive alternates or less deductive alternates, taken in the numerical order listed in the bid documents in an amount to be determined by the Owner. The Order of the alternates may be accepted by the Owner in any sequence so long as such acceptance does not alter the designation of the low bidder. The Owner reserves the right to waive any informality in bids received when such waiver is in the interest of the Owner. Section C of Volume I of the Manual contained the Proposal Form that all bidders were required to use to indicate their bid prices. The following statement appeared at the bottom of the second page of the Proposal Form: There is enclosed: A certified check, cashier's check, treasurer's check, bank draft or Bid Bond in the amount of not less than five (5) percent of the Base Bid payable to the Department of Corrections, as a guarantee. An executed Trench Excavation Safety Certification, Section F-13. An executed Experience Questionnaire and Contractor's Financial Statement and Public Entity Criminal Conviction Form, Section L. An executed Bidder's Qualifications Form (Reverse Osmosis), Technical Specification Section 01420. While one completed R.O. Form had to accompany each bid, there was no provision in any of the bid documents issued by the Department requiring a bidder to submit only one such completed form and no more. Petitioner, McMahan and R.J. Sullivan Corporation (hereinafter referred to as "Sullivan") were among the contractors that timely submitted bids in response to the Advertisement. McMahan's and Sullivan's bids were each accompanied by more than one completed R.O. Form. Petitioner, on the other hand, provided the Department with only one completed R.O. Form along with its bid. Of the bids submitted, McMahan's was the lowest, Sullivan's was the second lowest and Petitioner's was the third lowest. McMahan's base bid price was $857,000.00. Petitioner's was $905,000.00. McMahan's total price, including the nine additive alternates accepted by the Department, was $948,000.00. Petitioner's was $1,032,600.00, $84,600.00 more than McMahan's. By letter dated July 1, 1993, the Department advised McMahan of its intent "to award the contract [for Department Project No. NV-30A] to [McMahan] as the lowest responsive bidder." On July 9, 1993, Petitioner filed a formal written protest of the preliminary determination to award the contract to McMahan alleging that McMahan was not a responsive bidder inasmuch as McMahan "submitted Reverse Osmosis ("R.O.") Qualifications Forms for more tha[n] one vendor." According to Petitioner, "[t]his [was] not in conformance with the Bid Documents and gave [McMahan] an unfair advantage."

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Department of Corrections enter a final order finding Petitioner's bid protest to be without merit and awarding McMahan, as the lowest responsive and qualified bidder, the contract for Department Project No. NV-30A. DONE AND ENTERED in Tallahassee, Leon County, Florida, this 2nd day of September, 1993. STUART M. LERNER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of September, 1993.

Florida Administrative Code (3) 60D-5.00260D-5.00760D-5.0071
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer