Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. HARRY TINKLER, 81-003043 (1981)
Division of Administrative Hearings, Florida Number: 81-003043 Latest Update: Sep. 07, 1982

Findings Of Fact At all pertinent times, respondent Henry J. Tinkler was licensed by petitioner as a swimming pool contractor, holding license No. 0024949, under the name of "Henry J. Tinkler." At one time, Fred C. Charlton worked as a "salesman" of swimming pool construction contracts for a Ft. Lauderdale construction company. When the Ft. Lauderdale company failed, several contracts to build swimming pools remained unexecuted. So that his "sales" would not have been in valid, Mr. Charlton organized Aquapool in late 1978 or early 1979 to step in to the shoes of the Ft. Lauderdale contractor. He has been president of the corporation since its inception. He knew that he could not pull building permits himself; and Mr. Charlton did not involve himself in the actual construction of the pools. Respondent became vice-president of Aquapool and held this office until September of 1979. Respondent has built several pools pursuant to oral agreements with Charlton (acting for Aquapool), to build all pools Aquapool "sold" in Pinellas County. In these transactions, Charlton made a profit and Tinkler made a profit. Respondent never applied for any building permit under Aquapool's name. He always used his own name or the name "Hank's Custom Pools." Respondent never made application to qualify Aquapool as a registered pool contractor in Florida. Neither did respondent make application to qualify "Hank's Custom Pools" as a registered pool contractor. Not uncommonly, contractors do business under fictitious trade names like "Hank's Custom Pools." Eventually one Clay Andrews of Jacksonville made application to quality Aquapool as a swimming pool contractor in Florida until November 17, 1979. Harry George Pugh and Grace L. Pugh signed, on May 19, 1979, a contract with Aquapool for construction of a swimming pool at their Indian Rocks Beach home. Petitioner's Exhibit No. 2. On the building permit application form, Petitioner's Exhibit No. 3, the contractor is listed as "Hank's Custom Pools." The application is dated June 19, 1979. Mr. Pugh never met Mr. Tinkler. Guy Jean and Jane A. Narejo also contracted with Aquapool to build a swimming pool at their home in Largo, Florida. Petitioner's Exhibit No. 4. Mr. Pugh never met Mr. Tinkler. On June 14, 1979, "H. Tinkler" applied for a permit to build the pool. The permit issued the following day. Petitioner's Exhibit No. 5. Willard L. Marks and Helen J. Marks signed, on May 1, 1979, a contract with Aquapool for construction of a swimming pool at their home in Clearwater, Florida. Petitioner's Exhibit No. 6. Mr. Marks never met Mr. Tinkler. H. J. Tinkler applied for a permit to build the pool on June 7, 1979. Petitioner's Exhibit No. 7. Swimming pool contractors ordinarily subcontract electrical work. Sometimes as many as four or five subcontractors participate in the building of a swimming pool. Petitioner's proposed recommended order has been considered and proposed findings of fact have been adopted except where they have been deemed irrelevant or unsupported by the evidence.

Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That petitioner suspend respondent's registration as a swimming pool contractor for sixty (60) days. DONE and ENTERED this 27th day of April, 1982, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 Telephone: (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of April, 1982. COPIES FURNISHED: Michael Egan, Esquire 217 South Adams Street Tallahassee, Florida 32301 Gerald Nelson, Esquire 4950 West Kennedy Tampa, Florida 33609 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32302 Samuel R. Shorstein, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 ================================================================= AGENCY FINAL ORDER ================================================================= STATE OF FLORIDA DEPARTMENT OF PROFESSIONAL REGULATION CONSTRUCTION INDUSTRY LICENSING BOARD DEPARTMENT OF PROFESSIONAL REGULATION/CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. CASE NO. 81-3043 HENRY J. TINKLER, RP 0024949 d/b/a Individual 5243 27th Avenue St. Petersburg, Florida 33710 Respondent. /

Florida Laws (4) 120.57489.119489.127489.129
# 1
CONSTRUCTION INDUSTRY LICENSING BOARD vs MERWIN C. CARTER, 91-005266 (1991)
Division of Administrative Hearings, Florida Filed:Orlando, Florida Aug. 21, 1991 Number: 91-005266 Latest Update: Apr. 16, 1992

Findings Of Fact Respondent is a certified pool contractor, holding license number CP CO27486. Respondent obtained his certificate in October, 1983. His only prior discipline consists of a letter of guidance in late 1989 or early 1990. At all material times, Respondent was qualifying agent for Gold Medallion Pcol, Inc. On March 27, 1986, Respondent and Mr. and Mrs. Don Burson entered into a contract for the construction cf a swimming pool at the Bursons' residence. The Bursons had purchased the residence while it was still under construction in May or June, 1985. The lot was low and had required fill. Clearly visible behind the lot is a large marshy wetland. The contract called for the Bursons to pay $16,315 for the construction of a 20' by 40' concrete lap pool with depths of 3' at either end and 6' in the center. Paragraph 4 of the contract provides: The Owner is responsible for increased costs incurred by the Contractor due to underground conditions which may be encountered during construction, such as but not limited to, muck, inadequate soil-bearing capacity, and excessive ground water. The Contractor, upon encountering such conditions, shall notify the Owner of their existence and give him an approximate cost estimate to rectify the problem. The Owner shall have five (5) days from the receipt of the approximate cost estimate to instruct the Contractor not to proceed with the pool. . . . If the Contractor determines that additional testing is required prior to furnishing approximate costs estimates to determine the exact nature or extent of the underground condition encountered, the Owner shall be responsible for the cost of all testing and/or engineering required by the Contractor. Paragraph 8.D states that the Owner warrants that there [is] no . . . mock . . . in that portion of the owner's property which the contractor will construct the pool [and] decking . . .. The owner is responsible for the removal, repair or replacement of any underground conditions . . . encountered during construction unless he elects to terminate the contract and pay damages to the contractor as set forth in the clause on underground conditions. Paragraph 11.A provides: Contractor warrants to the original owner for the lifetime of the original purchaser, the swimming pool structure, the shell, will not leak due to cracking. . . . This Limited Structural Warranty does not cover damage to the pool shell caused by fluctuations of the water table, construction in the vicinity of the pool site, or natural phenomenon. . . . The contractor's responsibility under this Limited Structural Warranty shall be to repair the shell so that it holds water without cost to the original owner. . . . The method of repair shall be at the discretion of the contractor. THE CONTRACTOR MAKES NO OTHER EXPRESS OR IMPLIED WARRANTIES INCLUDING THE WARRANTY OF MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE IN REGARDS TO THE POOL STRUCTURE, THE SHELL. Paragraph 11.B.2, which further describes the limited warranty, states: It is anticipated the concrete deck and deck coatings may crack due to settling of deck or weather. Cracks one-quarter inch or less with no substantial deviation in elevation are not covered. . . . The plot plan, which is part of the contract, shows the pool located on the east side of the house. The pool is oriented in a north-south direction. The southern end of the pool runs toward the back of the lot, which is on a steep slope. The southern end of the pool adjoins the widest section of decking, which Respondent constructed at the time of the construction of the pool. The plot plan also shows that excavated dirt was to be placed just south of the decking on the south end of the pool. Shortly after pulling a building permit from the Seminole County Building Department on March 27, 1986, Respondent began construction of the pool. The actual construction was performed by Mid-Florida Pool Company, which is a major pool construction company in Central Florida. Construction was completed on April 23, 1986, and the Bursons paid the amount required under the contract. Prior to commencement of construction of the pool, this area of the Bursons' lot had been filled with about 2 1/2 to 3 feet of dirt. In order to construct the pool, Respondent or his subcontractors added another 2 1/2 to 3 feet of fill, at least to the southern end of site of the pool and decking. It is at this point that the land begins to slope most steeply toward the marsh in the back. Neither Respondent nor any of his subcontractors conducted any soil tests prior to commencing construction or compressed or compacted the soil beneath the pool prior to installing the shell. This omission constitutes a departure from sound contracting practices under the facts cf this case. Respondent constructed several pilasters under the southern end of the deck, but these structural supports were designed to support the deck, not the pool. In general, the depth of the excavation had to exceed the depth of the pool by one foot in order to accommodate the shell. Thus, the extreme southern end of the shell required a hole only about four feet deep. An excavation of this depth did not exceed the combined depth of the old and new fill. There is no indication that Respondent or his subcontractors encountered muck during the excavation or construction of the pool. Likewise, there is no indication that Respondent or any of subcontractors was aware that mucky, unstable soils underlaid the location of the pool, especially the southern end. The pool was completed to the initial satisfaction of the Bursons. However, within 90 days of completion, the southern half of the shell developed five or six major cracks as a result of the settlement of the southern end of the pool. This portion of the pool settled because the underlying muck had been compressed by the weight of the shell and water. Gradually, the water loss from the settlement cracks, which were mostly below the waterline, became significant. At Respondent's suggestion, the Bursons agreed to wait through the winter before commencing repairs in order to allow the cracking to stabilize. In the spring of 1987, the Bursons drained the pool at Respondent's direction. Respondent then scored the cracks with a screwdriver and applied a filling compound in order to seal any leaks. As directed by Respondent, the Bursons then refilled the pool, but before more than two feet of water had been added, the filling compound fell out of the cracks. When the Bursons informed Respondent of the failure of the repair, he responded that he had performed under the contract and had no further obligation. The Bursons exercised their right to arbitrate, as provided in the contract. The arbitrators conducted a limited investigation. Expressly noting that they were not soil engineers and thus could not determine why the soil under the pool failed to support the shell, the arbitrators determined that the contractor was not responsible for any damage to the pool, "which was built to industry standards." The Bursons next contacted various pool contractors about repair options. Most of the contractors suggested a V-cut about 2 1/2 inches deep followed by the injection of hydraulic cement. When the Bursbns informed Respondent that this type of repair appeared necessary, he refused to undertake such work. By this time, one of the contractors documented that five of the cracks, which ranged from 1/16" to 1/4" wide, were pulling water out of the pool at a rate of 1-3" daily. This contractor charged the Bursons $125 for his services. After contacting the Seminole County Building Department, the Bursons learned that the pool had never passed a final inspection. When they had an inspector visit the site on September 13, 1991, he failed the job due to, among ether things, "massive deck cracks." At the insistence of Seminole County officials, the Bursons obtained expert opinions as to the cause of the cracks in preparation for the local hearing on the Bursons' charges against Respondent. In July, 1990, the American Testing Laboratories, Inc. conducted tests and opined that the south end of the pool had settled due to muck at a level of five feet below the bottom of the shell. Additional testing found muck at depths of 3-7 feet at two points just east of the south end of the pool. These tests cost the Bursons $498. When the Seminole County officials insisted upon further testing, the Bursons hired Jammal & Associates, Inc., which performed soil borings on August 23, 1990. The boring sites were just east of a point about midway along the southern half of the pool and a point just south of the southern end of the pool. The latter boring site revealed muck after penetrating about six feet of fill. At the request of Respondent, a Jammal employee returned to the site on November 13, 1990, to determine the potential cause of the cracking of the pool shell and deck. Jammal concluded that the cracking is the result of consolidation of the highly compressible peat layer found in the [southern] boring. Based upon the [cracking] observed, we suspect the southern 1/3 or so of the pool and deck area are underlain by the buried peat layer. The remainder of the pool and deck are most likely underlain by sandy soils. Because of the nature of the buried organic soils, the pool and deck will probably continue to settle at a diminishing rate for several years. Addition of new loads such as placement of additional fill around the pool and deck area, or a significant drop in the groundwater table could cause additional and accelerated settlement of the pool and deck. Jammal offered three repair options. The first was to patch the cracks. Jammal assumed that, although continued cracking could be expected, it would occur at a lesser rate because most of the settlement of the buried muck had already taken place. The second option was to remove the pool and then remove the underlying muck. The third option was to install inside the shell a fiberglass liner. The last option had been first suggested by Respondent. If not rigidly attached to the shell, the liner probably would not reflect further cracking of the shell. The Bursons paid Jammal the sum of $300 for its services. Ultimately, the Bursons decided to install a fiberglass liner and entered into a contract on November 19, 1990, with Fibre Tech for the work. The total cost of the project was $5415. This cost excludes the cost of replacing a pool vacuum for which Respondent does not appear responsible. The liner was later installed, and the Bursons paid the contract price. In the meantime, at a meeting on October 16, 1990, the Seminole County Swimming Pool Contractor's Board revoked Respondent's County certificate of competency until he repaired the pool or made restitution to the owners. This action was based upon a violation of Seminole County Code Section 40.151 and 40.34(2) and (9). Section 40.151 provides that "[a]11 completed pools shall be absolutely watertight." Section 40.34(a) allows the Board to revoke a certificate of competency if the contractor: (2) Continue[s] performance of building work in a negligent, incompetent or unworkmanlike manner. (9) Violate[s] any provision of this Chapter. The determination of the Seminole County Swimming Pool Board became final when Respondent failed to take a timely appeal of the order.

Recommendation Based on the foregoing, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a final order imposing an administrative fine of $2500 and suspending Respondent's license until he makes restitution to the Bursons in the amount of $6338. ENTERED this 29th day of October, 1991, in Tallahassee, Florida. ROBERT E. MEALE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of October, 1991. COPIES FURNISHED: Jack McCray, General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Daniel O'Brien Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Craig M. Dickinson, Senior Attorney Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Merwin C. Carter, pro se 611 Ensenada Avenue Orlando, FL 32825

Florida Laws (5) 120.5717.00140.34474.214489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs ROCCO R. SODOMIRE, 99-001683 (1999)
Division of Administrative Hearings, Florida Filed:Fort Myers, Florida Apr. 12, 1999 Number: 99-001683 Latest Update: Jul. 15, 2004

The Issue Whether Rocco R. Sodomire (Respondent) violated Section 489.129(1)(c) and (r) and Section 455.227(l)(o), Florida Statutes, and if so, what disciplinary action should be taken against his license to practice contracting.

Findings Of Fact Respondent is, and has been at all times material hereto, a Certified Residential Contractor in the State of Florida, having been issued license number CR CO57213. At all times material hereto, Respondent was not licensed to do any swimming pool/spa contracting in the State of Florida. On or about November 1996, Respondent submitted a proposal to Vincent Neglio for the construction of a 28' x 14' in-ground swimming pool, a deck, and a screen enclosure at a cost of $15,000.00. Shortly thereafter, pursuant to the proposal, Respondent began construction of a swimming pool and deck at Mr. Neglio's residence. Prior to completion of the pool project, Mr. Neglio paid Respondent a total of $14,200.00. Although Respondent received $14,200.00 from Vincent Neglio, he never completed the pool project. Respondent presented the proposal for the pool project to Mr. Neglio; accepted money from Mr. Neglio as payment for work on the project; distributed funds to other contractors who worked on the pool project; and performed work on the pool project at Mr. Neglio's home. On August 4, 1997, the County Court of the Twentieth Judicial Circuit in and for Lee County, Florida, Small Claims Division (Case Nos. 97-2569SP-RRS and 97-2570-SP-RRS), entered a Record of Agreement between Respondent and Mr. Neglio whereby Respondent was to pay Mr. Neglio a total of $2,600.00 to settle the dispute involving the aforementioned pool project. On January 13, 1998, the County Court of the Twentieth Judicial Circuit in and for Lee County, Florida, Small Claims Division, in the above-referenced cases entered a Final Judgment by Default against Respondent in favor of Vincent Neglio in the amount of $2,600.00, the payment amount required in the Agreement, as a result of Respondent's failing to pay monies based on the Agreement referenced in paragraph 6. To date, Respondent has failed to make any payments to Vincent Neglio based on the Small Claims Court Record of Agreement, referenced in paragraph 6 or the Final Judgment by Default referenced in paragraph 7.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a final order that: (1) finds Respondent committed the offenses alleged in Counts I and II of the Administrative Complaint and imposes a $500.00 fine for these violations; (2) requires Respondent to pay restitution to Vincent Neglio in the amount of $2,600.00; and (3) requires Respondent to pay to Petitioner $858.97, the costs incurred by Petitioner in the investigation and prosecution of this proceeding. DONE AND ENTERED this 23rd day of November, 1999, in Tallahassee, Leon County, Florida. CAROLYN S. HOLIFIELD Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 23rd day of November, 1999. COPIES FURNISHED: Paul F. Kirsch, Esquire Leonardo N. Ortiz, Qualified Representative Department of Business and Professional Regulation 1940 North Monroe Street, Suite 60 Tallahassee, Florida 32399-0792 Rocco R. Sodomire 3520 Southeast 2nd Avenue Cape Coral, Florida 33904 Rodney Hurst, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Barbara D. Auger, General Counsel Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-0792

Florida Laws (5) 120.57455.227489.105489.1195489.129 Florida Administrative Code (1) 61G4-12.018
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ROBERT C. CHANNELL, D/B/A CHANNELL POOLS, 77-000056 (1977)
Division of Administrative Hearings, Florida Number: 77-000056 Latest Update: Dec. 04, 1990

Findings Of Fact Robert C. Channell is a registered pool contractor holding License No. RP0024653 issued by the Florida Construction Industry Licensing Board. A copy of the Circuit Court of the Thirteenth Judicial Circuit finding that Robert C. Channell had violated Section 501.204, Florida Statutes, and the rules and regulations adopted pursuant to Chapter 501, Florida Statutes, was introduced to prove that he had violated Section 468.112(2)(a), Florida Statutes. An order of contempt was also introduced to show that Robert C. Channell had violated the Court's original injunctive order. Robert Berndt contracted with Robert C. Channell for the construction of a pool at his residence. Subsequently, employees of Robert C. Channell cleared trees from the back of Berndt's residence and construction of a pool was begun by excavation of a hole in Berndt's backyard. Eli Jackson indicated that he had contracted with Robert C. Channell to build a pool at Tyrone Mobile Home Park which Jackson owned. Robert Channell did not apply nor obtain a building permit for the construction of pools at the residence of Robert Berndt or at the Tyrone Mobile Home Park. Robert Thomas indicated that he had inspected the pool constructed at Tyrone Mobile Home Park and determined that no permit had been obtained for construction of said pool, and further that the pool was constructed to residential standards. From the location of the pool it was clearly for the use of residents of Tyrone Mobile Home Park. There were eighty (80) or more families residing in Tyrone Mobile Home Park. On September 30, 1976, Robert C. Channell's license as a pool contractor in Hillsborough County had expired and was not renewed by the county. Subsequently, Channell contracted to build a pool for Randall Harris, who obtained the permit to construct a pool as owner of the property. Although Harris did some work on the pool, Channell was paid $7,200 to remove trees, work on the pool and construct a fence. Electrical work was done by an electrical contractor. Berndt complained that Channell was slow in starting his pool and did not receive many extras for which he had contracted with Channell. The delay in construction was the apparent result of Channell's attempts to finish projects underway in compliance with the requests of Mr. Shaw, the Building and Zone Director of Hillsborough County. Eli Jackson, the owner of Tyrone Mobile Home Park, and Randall Harris were both pleased with the pools Channell constructed for then.

Recommendation Based upon the foregoing findings of fact and conclusions of law, the Hearing Officer recommends that the Florida Construction Industry Licensing Board revoke the license of Robert C. Channell until he has reestablished himself as a licensed pool contractor in Hillsborough County, Florida. DONE and ORDERED this 5th day of July, 1977, in Tallahassee, Florida. STEPHEN F. DEAN Hearing Officer Division of Administrative Bearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 COPIES FURNISHED: David Linn, Esquire Post Office Box L386 Tallahassee, Florida 32302 Mr. Robert C. Channell 309 Jennal Place Tampa, Florida 33612 Mr. J. K. Linnan Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211

Florida Laws (1) 501.204
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. MILLARD P. HILL, JR., 76-001011 (1976)
Division of Administrative Hearings, Florida Number: 76-001011 Latest Update: Dec. 04, 1990

Findings Of Fact The parties stipulated that Petitioner's Exhibit number 1, which is the Florida Construction Industry Licensing Board official records as they relate to Millard P. Hill, Jr., should be received into evidence. The parties noted further that there is little dispute as to facts, however, the Respondent contends that there is no diversion of funds based on the facts of this case. On June 10, Respondent advised Petitioner that he wished to qualify Master Pools, a corporation which he had applied to Petitioner to qualify as the name under which his pool contracting would be done to reflect the name H. B. Patten, Inc. as the name under which said contracting would be done. Petitioner changed its records to show this change. On July 12, Respondent entered into a contract with Manuel and Anna Bueno for a pool to be built at 6960 Northwest 4th Place, Margate, Florida, for a sum of $5,665. See Petitioner's Exhibit number 2 received into evidence and made a part hereof by reference. Anna Bueno testified that a hole was dug and tar paper and steel bars were erected in the hole and the work was abandoned thereafter. Prior to abandonment, the Bueno's paid approximately $4,100 to Patten Pools. To complete the construction, the Bueno's used Hallmark Pools to finish the pool which required an additional sum of approximately $5,000. As can be seen, this is approximately $3,300 over and above the contract price. The evidence also reveals that Patten Pools, Inc., through Millard P. Hill, applied for and obtained a permit for the construction of the pool for the Bueno's on August 5. See Petitioner's Exhibit number 3, received into evidence and made a part hereof by reference. On April 24, Mr. and Mrs. Edward Eskie entered a contract with Respondent for the erection of a swimming pool on their property located at 1525 Southeast 14th Court, Deerfield Beach, Florida for $6,786.00. See Petitioner's Exhibit number 4 received in evidence and made a part hereof by reference. Mr. Eskie testified that the excavation for the pool began on May 20, and on June 2 gunite services were complete. On July 9, he received a letter from Crockett- Bradley, Inc. a gunite subcontractor, indicating that it was filing a lien for $1,312 against the Eskie's property for services performed. The building permit for the Eskie project was obtained by Respondent on June 10. See Petitioner's Exhibit number 7 incorporated herein by reference. Edward Eskie paid Respondent approximately $4,778 and $1,312 was paid to Crockett-Bradley, Inc. to satisfy the lien which was placed against their property. The Eskie's completed their pool by payment of an amount in excess of $4,000 to another pool contracting firm. Prior to completing the pool and after the Respondent abandoned the project, Edward Eskie made numerous attempts to contract Respondent by phone to no avail. On June 27, Respondent entered a contract with Orlando Gonzalez for a pool to be built at his residence located at 353 Northwest 22nd Street, Boca Raton, Florida for $9,000.00. See Petitioner's Exhibit number 8 which was received and made a part hereof by reference. Orlando Gonzalez paid Respondent $3,600 through his bank toward the contract price. For that payment, Respondent dug a hole and the project was abandoned. After work was abandoned, Gonzalez made repeated attempts to contact Respondent to no avail. To complete the project, he paid another contractor approximately $6,000. On April 18, Respondent entered into a contract with Howard and Sheila Siclari for a pool to be built at their home located at 7812 Northwest 67th Avenue, Tamarac, Florida, for the sum of $4,280. To commence the construction, Respondent obtained a building permit on June 18, 1975. See Petitioner's Exhibits number 9 and number 10 received in evidence and made a part hereof by reference. The Siclari's paid Respondent $3,456.75. Thereafter they completed the work which cost them an additional $2,500 and they did most of the work themselves. James T. Anglen, a pool salesman for Patten Pools testified that he was initially employed by Master Pools until June, 1975. A reference to Petitioner's Exhibit number 1 indicates that Master Pools registered as Brian Sales Corporation as the first entity that Respondent registered with Petitioner on January 1, 1974. He was a superintendent of Patten Pools in June, 1975 when he commenced employment with Patten. He acknowledged that he received money from the Bueno's which was transmitted to Patten Pools. He also acknowledged that the Bueno's were probably hurt most of all the complaining parties in this case. Respondent discovered that its cash flow was short approximately $40,000 to $50,000 and that that amount in checks were floating with insufficient funds to cover them. He commenced efforts to try to straighten out the firms cash flow and that for a while the bank worked along with him. Anglen also acknowledged the abandonment of the Gonzalez project. He further acknowledged that monies received from projects were used to cover deficiencies on other projects to continue Respondent's operations.

# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOHN H. HOLLAND, 79-002059 (1979)
Division of Administrative Hearings, Florida Number: 79-002059 Latest Update: Aug. 28, 1980

Findings Of Fact Respondent is the holder of currently active General Contractor's license No. RG-0023888. On January 18, 1977, Norwood W. Hope (hereinafter "Developer") entered into a contract with Respondent for the construction of a commercial swimming pool. Respondent was to have been paid the amount of $43,346.40 under the contract for construction of the pool. The contract amount was to be paid pursuant to a five-stage draw schedule as follows: 1. Framing and steel draw paid $10,836.60 2. Gunite draw paid 10,836.60 3. Mancite draw 7,224.40 4. Equipment set draw 7,224.40 5. Final approval draw 7,224.40 Respondent made application for an Alachua County building permit for the swimming pool project on February 23, 1977. The permit application was approved on February 25, 1977, and a building permit was issued. Thereafter, the project received Alachua County approval on a temporary power pole inspection on June 1, 1977. An interim inspection of the property was made by Alachua County officials on November 7, 1977, with no deficiencies noted. A final inspection on the electrical work on the project was made, with satisfactory results, on November 8, 1977. The Alachua County Building Code, by incorporation of the 1973 Southern Standard Building Code, 1974 Revision, provides, in part, as follows: 108.2--INSPECTIONS REQUIRED The Building Official shall inspect or cause to be inspected at various intervals all construction or work for which a permit is required, and a final inspection shall be made of every building or structure upon completion, prior to the issuance of the Certificate of Occupancy, as required in Section 109. * * * (c) The Building Official upon notifica- tion from the permit holder or his agent shall make the following inspections of buildings and such other inspections as may be necessary, and shall either approve that portion of the construction as completed or shall notify the permit bolder or his agent wherein the same fails to comply with the law: * * * Final Inspection: To be made after the building is completed and ready for occupancy. (Emphasis added). The contract entered into on January 18, 1977 between the Developer and Respondent called for Respondent to construct the swimming pool according to the plans and specifications admitted into evidence as Petitioner's Exhibit No. 1. Associated construction, including construction of concrete pool decking, a pumphouse and a fence surrounding the swimming pool site were either completed by the Developer or by other sub contractors. By invoice dated October 12, 1977, Respondent requested a final draw on the project in the amount of 87,000, which, if paid, would have left only $224.40 unpaid under the contract. This draw request indicated that a balance due for extra time and materials would be billed ". . . upon acceptance of total pool." (Respondent's Exhibit No. 4). On October 25, 1977, the Developer paid $6,000 of the $7,000 requested to be paid by Respondent's invoice of October 12, 1977. The Developer contested Respondent's expressed intention to bill for additional time and material, asserting that the Developer had not approved any additional sums for extras. In remitting the $6,000 payment to Respondent, the Developer indicated that "[t]his leaves a balance on our account of $1,224.40, which will be paid upon checking out the pool." (Respondent's Exhibit No. 2). (Emphasis added.) An invoice for back charges on the swimming pool project in the amount of $274 was forwarded to the Developer by Respondent by invoice dated November 8, 1977. In addition, on November 8, 1977, Respondent also invoiced the Developer for a final draw on the project in the amount of $1,224.40. At some time after notification from the Developer's representatives that tile targets in the racing lanes of the pool were improperly located, Respondent returned to the job site after November 9, 1977 to relocate the targets. Respondent performed this work as a result of a written request from the Developer dated November 9, 1977. Respondent completed primary construction of the pool prior to submission of the final draw request of October 12, 1977. At that time, back- filling around the exterior of the pool structure preparatory to the pouring of the concrete pool decking had not been completed. Although by October 12, 1977, Respondent had removed much of the excess dirt and debris from around the edges of the pool. There were still areas of exposed piping which would, in due course, be covered with back-fill and tamped by the decking subcontractor. Respondent did not attempt to back-fill or tamp any areas around the pool's piping system. At some time subsequent to October 12, 1977, which date is not clearly reflected in this record, a separate sub- contractor completed back-filling work around the pool, and poured the concrete decking. Neither the Developer nor his subcontractor advised Respondent that the back-filling had been accomplished and that the deck was to be poured. Prior to October 12, 1977, Respondent "pressure tested" the pool's piping system, and determined that the pool would hold water at a level above its scum gutters. The results of this testing indicated that, at least as of October 12, 1977, there was no leakage from the pool. Standard practice in the pool construction industry dictates that a minimum of three pressure tests be made of a pool's piping system during the course of construction. The first of these tests should occur immediately after installation of the pipes, and a second test should be performed immediately before final back-filling to cover the pipe system. A final pressure test should be conducted after tamping of the fill and prior to the pouring of concrete for the pool deck. The obvious purpose of this system of pressure testing is to discover any water leaks before concrete pool decking is poured to avoid having to cut out sections of the concrete in order to locate leaks. Because the Developer and his subcontractor failed to notify Respondent of further work being done on the pool. Respondent was unable to perform a pressure test either after back-filling was completed, after the back- fill had been tamped and before the concrete deck was poured. By letter dated January 17, 1978, Respondent was furnished by the Developer with a "punch list" indicating several areas of deficiency that needed to be corrected in the pool. In that letter the Developer requested that Respondent complete the necessary work within seven days. The Developer forwarded a second letter to Respondent dated February 23, 1978 advising Respondent that the punch list items had not been corrected, and urging Respondent to complete the work described in the punch list as soon as possible. From receipt of the punch list in January of 1978 through the middle of March, 1978 Respondent had workers on the job intermittently making the corrections indicated in the punch list. Respondent satisfactorily corrected fifteen of the eighteen items listed as defective n the punch list. Some of the items were repaired by other subcontractors. Respondent had difficulty obtaining some items of equipment, which he was required to back-order. When the back-ordered equipment was slow in arriving, the Developer opted to obtain these items from a source other than Respondent. Respondent replaced a defective pump associated with the pool construction at some time subsequent to January 18, 1977. The last work performed by Respondent on the pool project occurred some time between March 10 and March 16, 1978. At no time thereafter was Respondent ever advised by the Developer that any work performed under the contract was either unsatisfactory or incomplete. The pool received a final State of Florida, Department of Health and Rehabilitative Services inspection on July 13, 1978, at which time all necessary permits for operation of the pool under applicable regulations were issued. Respondent at no time requested that Alachua County officials come to the job site to conduct the necessary final inspection of the project, nor did he advise the Developer of the necessity to do so. At some time during 1979, subsequent to the completion of the swimming pool project, the Developer discovered that the pool was losing water at a rate of approximately 2,100 gallons per day. During this period, the water level inside the pool would drop to a level equal to the piping running around the exterior of the pool shell and under the pool decking. When the Developer was unable to ascertain the cause of the leak, an outside subcontractor was hired to check the pool. This sub- contractor performed pressure tests on the pool's piping system in an attempt to determine whether the leakage was occurring through the pipes. These tests apparently showed no leakage through the piping system. The Developer then caused the concrete decking around the edge of the pool to be removed in order to more closely inspect the interior piping. At this point it was discovered that there existed flaws and breaks in the neoprene piping surrounding the exterior shell of the pool. After repairs to the damaged piping, the pool decking was repoured and there has been no subsequent leakage problem in the pool. The Developer incurred expenses in the amount of $2,288 in removing the decking around the pool and repairing the neoprene piping. Because of the fact that several subcontractors in addition to Respondent worked in the pool area during construction of the pool project, it is impossible on the basis of this record to determine the cause of the damage to the neoprene piping. Respondent's testimony is uncontroverted that pressure testing performed prior to the conclusion of primary work on the pool in October of 1977 showed no leakage through the pool's piping system. Further, at the conclusion of the primary work in October, 1977, much of the pool's piping system was left exposed and could have been damaged either by the Developer's own workers or by employees of other subcontractors in the course of back- filling and tamping fill material preparatory to pouring concrete decking. The Developer's failure to advise Respondent of the schedule for back-filling, tamping and pouring of concrete deprived Respondent of an opportunity to properly pressure test the piping system at appropriate stages of construction. Respondent has submitted proposed findings of fact for consideration by the Hearing Officer. To the extent that those proposed findings of fact are not incorporated in this Recommended Order, they have been rejected as being either irrelevant to the subject matter of this proceeding or as not having been supported by the evidence.

Florida Laws (1) 120.57
# 6
CONSTRUCTION INDUSTRY LICENSING BOARD vs. TERRY W. MALICKI, 82-002586 (1982)
Division of Administrative Hearings, Florida Number: 82-002586 Latest Update: Oct. 17, 1983

Findings Of Fact At all material times hereto, Respondent was the holder of a registered swimming pool contractors license number RP 0035739. Respondent's license was issued in the name of Malicki Pools, Terry W. Malicki. In January, 1981, Gary Wieland entered into a contract with Patrick Barr d/b/a Pool and Spa World. Barr was to construct a pool for Weiland in Port Charlotte for $7,856.00. Barr had become known to Wieland as a builder of swimming pools through a neighbor. Barr stated to Wieland that he was a pool contractor. Wieland made all payments due under the contract to Barr. Petitioner's evidence established that the Wieland swimming pool required a building permit. On March 3, 1981, Terry Malicki d/b/a Malicki Pools obtained permit number 66970 to construct a pool at Wieland's residence in Port Charlotte. Wieland's testimony established that Malicki constructed the pool at his residence. However, all of his dealings were with Barr. Barr was not licensed as a swimming pool contractor in Charlotte County or in Florida, and was convicted in the Charlotte County court of acting as a contractor without being licensed. Mr. Robert Guariglia entered into a contract with Barr to construct a swimming pool for $9,500.00. The pool was to be constructed at Lot 17, Block 402, Subdivision 23 or 913 Cherry Chase, Port Charlotte, Florida. Petitioner's evidence established that the Guariglia pool required a building permit. On June 10, 1981, Terry Malicki d/b/a Malicki Pools obtained permit number 68962 to construct a pool at Lot 17, Block 402, Subdivision 23 or 913 Cherry Chase, Port Charlotte, Florida. Guariglia paid the first installment of his contract by check to Barr in the amount of $3,325.00. However, because the pool was not level, Guariglia told Barr or Malicki who was supervising the work that he wanted the pool redone or removed. The pool was later removed and Guariglia had to pay $1,400 to have his property restored. As noted above, Barr was not licensed as a swimming pool contractor in Charlotte County or in Florida, and was convicted of acting as a contractor without being licensed. However, the swimming pool constructed at the identified Guariglia residence required a building permit. On September 3, 1981, the Charlotte County Building Board suspended the certificate of competency of the Respondent until such time as he corrected all matters which were then pending before that Board. On November 5, 1981, the Charlotte County Building Board reinstated Malicki's license.

Recommendation In consideration of the foregoing, it is RECOMMENDED: That Petitioner enter a Final Order suspending the swimming pool contractor's license issued to Respondent for one (1) year. DONE and ENTERED this 22nd day of April, 1983, in Tallahassee, Florida. R. T. CARPENTER, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of April, 1983. COPIES FURNISHED: Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Terry W. Malicki c/o Malicki Pools 1788 S.W. Sicily Avenue Port Charlotte, Florida 33952 Stephen Schwartz, Esquire 680 Aaron Street, N.W. Port Charlotte, Florida 33952 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (1) 489.129
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOHN W. THORNETT, 81-002659 (1981)
Division of Administrative Hearings, Florida Number: 81-002659 Latest Update: Nov. 23, 1982

Findings Of Fact On October 10, 1979, the Respondent entered into a written swimming pool contract with Mr. and Mrs. Stellato, wherein the Respondent agreed to construct a swimming pool for them on their property in accordance with the plans and specifications attached to the contract. Among other things this swimming pool contract provided for the payment of a total purchase price of $11,225.00 to be paid in the following manner: ten percent to be paid at the signing of the contract. fifty percent to be paid upon the installation of the tank. thirty-five percent to be paid upon completion of the base decking and screen enclosure. five percent, or the balance of the purchase price, to be paid when the filter system was put in operation. Further, this contract provided that if the purchasers of the swimming pool failed to pay the purchase price in accordance with the prescribed schedule, the contractor reserved the right to suspend all work on the swimming pool, and to suspend all warranty work due after completion of the pool. During the month of February, 1980, the Respondent, acting through his duly authorized representatives, did all acts necessary to cause the filter system of the subject swimming pool to become operable, and requested that the Stellatos pay the five percent balance due under the contract. The Stellatos failed to make this final payment, claiming that there was a problem with the pool decking. In response to this complaint the Respondent personally met with the Stellatos, and agreed to cover the problem area of the decking with Chattahoochee River Rock at no cost to the Stellatos. In exchange for this agreement the Stellatos agreed to pay the balance due under the contract. Thereupon, the Respondent installed Chattahoochee River Rock over a substantial portion of the decking at his own expense. During the installation of this Chattahoochee River Rock, Mrs. Stellato contacted the Respondent by phone and demanded that he also install, at his own expense, Chattahoochee River Rock over an existing concrete patio area that had not been built by the Respondent. The Respondent refused to incur this additional expense, because it was not in accordance with the agreement of the parties. Thereafter, the Stellatos again failed to pay the balance due under the contract. The subject swimming pool was inspected by an inspector for Palm Bay, and the City issued a certificate of occupancy in June of 1980. The pool was ready for a certificate of occupancy in February of 1980 except for the removal of one pile of dirt that still remained on the premises. All other aspects of the pool construction passed inspection in February of 1980 when the pool filter system was activated. Since February Of 1980, the Stellatos have had full use of the subject swimming pool. Except for alleging that some low spots remain in the pool decking, the Petitioner offered no substantial evidence of any other significant problem with the Respondent's construction. Notwithstanding the failure of the Stellatos to pay the balance of the contract price in a timely manner, the Respondent performed warranty work on the subject swimming pool after February of 1980. During the course of this warranty work the Respondent added chlorine chemicals to the pool because the Stellatos had failed to properly maintain it up to June of 1980. Another claim concerning a leaking pipe on the pool sweep did not manifest itself until April of 1981, after the expiration of the one year warranty period afforded by the Respondent to all customers. The Petitioner offered no evidence to show that the leak in this pipe was caused by the Respondent. Notwithstanding the expiration of the warranty period, and the lack of evidence to show that the leak was caused by the Respondent, he did send an employee to the job site and stopped the water leak, at no cost to the Stellatos. On several occasions when the Respondent or his employees attempted to satisfy the complaints of the Stellatos, they had to leave the job site because of the abusive language and conduct directed toward them by the Stellatos. In one instance Mr. Stellato ordered the Respondent's employees from the job site and prevented performance of any work under the contract.

Recommendation Based upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Administrative Complaint, as amended, against John W. Thornett be dismissed. THIS RECOMMENDED ORDER entered this 9 day of June, 1982, in Tallahassee, Florida. WILLIAM B. THOMAS Hearing Officer Division of Administrative Hearings Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 Filed with the Clerk of the Division of Administrative Hearings this 9th day of June, 1982.

Florida Laws (1) 489.129
# 8
CONSTRUCTION INDUSTRY LICENSING BOARD vs DOMINICK SOLITARIO, 90-004600 (1990)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Jul. 27, 1990 Number: 90-004600 Latest Update: Feb. 08, 1991

The Issue The issue in this case is whether the Respondent, Dominick A. Solitario, committed the offenses alleged in the Amended Administrative Complaint and, if so, what disciplinary action should be taken.

Findings Of Fact Based upon the oral and documentary evidence adduced at the final hearing and the entire record in this proceeding, the following findings of fact are made. At all times pertinent to this proceeding, Respondent, Dominick Solitario, was licensed as a certified pool contractor in the state of Florida, having been issued license no. CP CA17558. At all times pertinent to this proceeding, Respondent was the licensed qualifying agent for Jade Pools, Inc. Sometime around February of 1988, Respondent contracted with Michael and Linda Skidd to remarcite the swimming pool at the Skidd's home in Coral Springs, Florida. The contract price for the remarciting of the Skidd's pool was $2000.00. Respondent has been paid in full for this work. There is no evidence that there were any leaks in the Skidd's pool prior to the time the work was undertaken by Respondent. At the time the work was begun, one of the Respondent's employees discovered an expansion plug that had been inserted in the main drain. The employee inquired as to whether the Skidds had experienced any problems with the drain. The Skidds denied having any problems. The evidence presented at the hearing was inconclusive as to whether the main drain was working properly. At the time the Respondent began work under the contract, the Skidds were using a "creepy crawler" to clean the pool. This device required the main drain to be shut off. While Mrs. Skidd testisfied that she thought the main drain was working properly, she admitted that her husband was more familiar with the cleaning and mechanical aspects of the pool. Mr. Skidd did not testify. Respondent contends that Mr. Skidd was present at the time the plug was removed from the main drain and that the condition was brought to his attention. However, it does not appear that either Respondent or Mr. Skidd knew why the drain was plugged or the significance of the situation. Respondent proceeded with his contractual work without conducting any tests to determine whether there was a leak in the main drain. When the work was completed, the workers directed the Skidds not to use their main drain. No explanation was given for this instruction. After the work was completed, the Skidds turned on the main drain and lost approximately four inches of water from the pool in a relatively short time. The Skidds turned off the drain and called Jade Pools. An employee of Jade Pools came out and inspected the premises. He advised the Skidds not to use the main drain, but instead to use their "creepy crawler." The Respondent's employee indicated that there was a leak in the main drain. It is not cler how he reached that conclusion. In order to complete the work on the Skidd contract, Respondent's employees were required to install a pressure release valve near the pool's main drain by drilling through the bottom of the pool. The hole for this valve was drilled several inches away from the main drain and its plumbing. Petitioner suggests that the Respondent's employees may have punctured the main drain or its plumbing when this hole was drilled. However, no persuasive evidence was introducted to prove this allegation. Respondent contends that the pool was improperly constructed and/or that the main drain line had been previously damaged and plugged shut to avoid detection of the leak. In order to perform the contracted work, Respondent's employees unplugged the drain and the alleged preexisting leak became evident. Respondent has inserted a plug into the main drain and claims that the pool is now in the same condition it was when he began his work. Respondent has refused to repair the main drain or perform any additional work unless he is paid for it. At the time that Respondent first proposed to enter into a contract with the Skidds, he was told by the Skidds that there was a suction leak at the pump. In retrospect, Respondent contends that this suction leak confirms the preexisting problem with the main drain. No conclusvie evidence was presented to establish why the pool is leaking. As of the date of the hearing, the Skidds are still unable to use their main drain. The Petitioner did not present persuasive evidence to establish that Respondent was responsible for the leak in the Skidds' pool. While it is possible that the Respondent's employees caused the leak when they drilled the hole for the pressure release valve, an equally likely explanation is that there was an existing problem that had been obscured by the prior plugging of the main drain. On or about June 29, 1987, Respondent contracted with Anthony Gallagher to construct a swimming pool and a deck at Mr. Gallagher's home in Coral Springs, Florida for the contract price of $17,800.00. Respondent has been paid in full for this work less $100 for damage caused during construction. The contract with Mr. Gallagher called for Respondent's company to top the existing patio slab and tie it into a newly added patio deck surrounding the pool. The building permit for this work was pulled by Jade Pools. Although the work on the Gallagher deck and pool was completed sometime in late 1987 or early 1988, the pool and deck have still not passed final inspection by the City. The local building officials have refused to approve the final inspection on the Gallgher's deck because of the excessive slope from the back of the house to the pool. The pitch of the deck constructed by Respondent's company from the back of the Gallagher's house to the pool is very severe, effectively rendering a portion of the deck unusable. A table cannot sit flat on this portion of the deck because of the slope. The Respondent's construction of a deck with such a severe slope that it is incapable of passing final inspection constitutes incompetency in the practice of contracting. In order to provide a usable deck, Respondent should have ripped out the existing deck or placed the pool at a higher elevation. Respondent contends that his contract did not call for him to rip out the existing deck, but only to top it. He claims the existing deck that was topped had a similarly severe pitch. Nonetheless, Respondent is responsible for insuring that his final product is functional and able to pass inspection. Respondent has failed to take any remedial action to obtain a successful final inspection. During construction, the Gallaghers, on several occassions, expressed displeasure with the deck and its excessive slope in some areas. On two occasions, Respondent sent his workmen out to correct certain aspects of the construction that the Gallaghers found unacceptable. Ultimately, the homeowners paid the Respondent in full and instructed Respondent to stay off their property. Although Respondent's presentation was somewhat unclear, he appears to argue that these actions by the Gallaghers relieve him of any liability for his work under this contract. However, the evidence established that the Respondent was never able to obtain a successful final inspection of his work at the Gallagher home. This failure is the direct result of the excessive pitch in the patio he constructed. While the Gallaghers have paid the full amount of the contract and are apparently using the pool and patio, these facts do not relieve Respondent from responsibility for the incompetently constructed deck. The City of Coral Springs requires a deck electrical inspection to insure that all the steel in the deck is on the same electrical field (same electrical bond) as the pool. Jade Pools failed to call for this electrical bond inspection before pouring the Gallagher's deck. Ultimately, the city building officials required the Respondent's company to expose a portion of the steel in the deck to confirm that the pool was properly bonded. This test indicated that the pool was in fact properly bonded. On or about August 10, 1988, Respondent contracted with Kevin Fusco to construct a swimming pool and deck at Mr. Fusco's home in Boca Raton, Florida for a total contract price of $10,030.00. Respondent has been paid in full under this contract. Jade Pools obtained the building permit for the Fusco's pool. Therefore, Respondent's company was responsible for obtaining all of the inspections for the construction, including the final inspection. Prior to the time that work was begun on the Fusco contract, Respondent's employees inspected the property and were advised as to some existing problems with drainage in the backyard of the house. The Fusco's lot was designed to drain from back to front. A berm runs behind the Fusco property and causes water to drain through the backyard. On some occasions prior to construction, this drainage situation resulted in standing water against the back of the house. The installation of the Fusco's pool seriously affected the drainage plan for the property. After the pool was installed, there was often standing water all around the deck following a rain. After construction was started and the deck was formed out, the county refused to give approval for pouring the deck because of anticipated problems with drainage in the backyard. One of Respondent's employees advised the Fuscos that if they removed approximately three feet of soil from around the deck, the county would allow them to proceed with pouring the deck. Based upon this recommendation, the Fuscos entered into a contract with a company recommended by Respondent. That company removed approximately six or eight feet of soil all around the deck and installed a rock bed in the area. The cost of this removal was in addition to the contractual price agreed to between Respondent and the Fuscos and was borne by the Fuscos. As indicated above, the installation of the pool greatly exacerbated the drainage problems that previously existed on the property. Respondent did not warn the homeowners prior to construction to expect this result nor did the Respondent take steps to preclude these additional drainage problems. While Respondent contends that the Fusco's property was inappropriately graded prior to the time the work was initiated, Respondent never brought this fact to the attention of the homeowners until after the pool was installed and the increased drainage problems became evident. After the work was completed, the county inspectors advised the homeowners that the pool did not pass final inspection because of drainage problems caused by the pool and deck. By the time the Fuscos found out the pool had not passed final inspection, Respondent had been paid in full under the contract. The Fuscos contacted Jade Pools, which refused to take any corrective action. The Respondent claimed that drainage problems were not part of his company's responsibility and refused to return to the property to correct the problem even though the pool had not passed final inspection. The Fuscos hired an engineer to design an acceptable solution to the drainage problem and arranged for the completion of the work at their own expense. In accordance with this solution, the homeowners installed a series of french drains around the back yard in order to try to get the water to percolate into the ground. After this additional work was completed, the pool passed final inspection by the county. It was approximately one year after Jade Pools finished its work before the final inspection was passed. The Fuscos continue to experience increased drainage problems on their property as a result of the installation of the pool and deck. These problems include standing water around the deck after a heavy rain and, in some instances, an overflow of water into the pool. While the Respondent was installing the Fusco's pool, Respondent was concurrently installing a pool at the house next door. There has been no drainage problems on the property next door because the elevation on that house is higher. The Fusco's pool was actually installed at a level that was at or below the surrounding ground level. The problems associated with such an installation were never explained to the homeowners prior to the time the work was commenced. Respondent contends that this situation was necessary because of the existing elevations of the house and lot. He says that the pool and deck had to be installed in a manner that provided a four inch step down from the house and also matched the existing slab. The drainage problems could have been minimized by swaling out from the pool area to the side of the house. While Respondent contends that such "landscaping" efforts were not part of his contract, he should have not undertaken the work unless he could adequately deal with the drainage problem and ensure that the final installation would pass inspection. The pool contractor is responsible for insuring that, after the pool is built, proper drainage is obtained around the pool. The efforts undertaken by the Respondent were insufficient to deal with the resulting drainage problems and constitute incompetency in the practice of contracting.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Construction Industry Licensing Board enter a Final Order finding Respondent guilty of violations of Section 489.129(d) and (m), Florida Statutes, in connection with the Fusco and Gallagher contracts, issuing a reprimand and imposing a fine on Respondent in the amount of $2,000.00 for having committed these violations. In addition, Respondent should be placed on probation for two years and required to reimburse the Fusco's for the money they have expended to correct the drainage problems caused by Respondent. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 8th day of February, 1991. J. STEPHEN MENTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 8th day of February, 1991.

Florida Laws (5) 120.57455.225489.105489.119489.129
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. KENNETH R. MARTIN, 87-005044 (1987)
Division of Administrative Hearings, Florida Number: 87-005044 Latest Update: Aug. 02, 1988

The Issue The administrative complaint filed on September 17, 1987 alleges that in a residential pool contracting job Respondent Martin ". . . exhibited financial mismanagement, misconduct, or diversion, in violation of 489.129(1)(h), (m) . . . [and] failed to perform in a reasonably timely manner, and/or abandoned said job, in violation of 489.129(1)(m), (k)." The issue is whether Martin committed those violations, and if so, what disciplinary action is appropriate.

Findings Of Fact At all times relevant, Kenneth Martin was licensed in the State of Florida as a registered commercial pool contractor, holding license number RP 0021608. His license is currently in inactive status. Martin was President of Adair Pools, Inc., the corporation under which he conducted his pool construction business. In early July 1986, Adair Pools contracted to build a residential pool for Paul and Cynthia Pajak at 8304 Helena Drive in Orange County, Florida. The pool was to be kidney-shaped, approximately 14 feet by 30 feet, with a waterfall and a detached spa. The contract amount of $11,571.00 expressly excluded the deck, electrical work and screening, although the written contract included a sheet describing the specifications for the excluded work, recommended contractors, and estimated costs. This sheet and the pool contract itself clearly indicated that these items were not the responsibility of the pool company and were not included in the contract price. Work commenced in July, shortly after the contract was signed. Although the contract did not specify a completion date, Martin concedes that the pool should have taken no more than four to eight weeks to complete. The Pajaks had planned a Labor Day party and were told by Adair's employees there would be no problem getting their pool finished for the party. The pool was not finished by Labor Day. After the pool was dug, shot with concrete and tiled, someone determined that the spa was supposed to have been raised. In attempting to raise the spa and to change the water jets, the workers cracked the shell of the spa and had to replace it. Until the problems with the spa, the Pajaks felt that the construction progress was reasonable and smooth. At this point, sometime around Labor Day, the problems began. Adair delayed in paying Shotcrete Pools, the subcontractor for the concrete shell, because Adair felt it was Shotcrete's fault that the spa was cracked. Shotcrete notified the Pajaks that a lien would be placed on the property if they were not paid. The notice to owner is dated November 3, 1986. Eventually Adair paid Shotcrete and its other subcontractors for the Pajak work and no lien was filed. The evidence does not reflect a clear sequence of events, but between Labor Day and February or March 1987, little progress was made to finish the pool. Martin's supervisor left and Martin's brother took over. The Pajaks kept calling Martin and were always assured that the job would be completed. Martin admits that the company at this time was in serious financial trouble because it was not being paid for a large commercial job that it had undertaken. On December 10, 1986, Mrs. Pajak's brother-in-law, an attorney, sent Martin a demand letter, giving a 10-day deadline for completion of the work. Martin and his brother met with the attorney and assured him the job would be finished. In spite of the problems, the Pajaks continued working with Martin and paid the full contract price, less the $100.00 that was to be paid when the pool was filled. On March 5, 1987, Martin informed the Pajaks that they should have the deck poured so that Adair could finish the pool. The Pajaks were not satisfied that the pool was ready for the deck as there were leaks in the waterfall, debris was all over the yard and the spa tile work looked messy. In Martin's opinion those items were his company's responsibility, but were part of the finishing to be done after the deck was poured and the pool was lined with marblelite. On March 21, 1987, the Pajaks contracted with another pool company for $4450.00 to finish their pool. Martin denies that Adair abandoned the job, but admits that it took an inordinate amount of time. The Pajaks did not allow him to finish the cleanup, the interior coating and the pool start up because they contracted with someone else. Martin did not contest that the waterfall leaked or that extensive cleanup needed to be done, but disputed that this work should be done before the deck was poured. He contended that the leaks in the waterfall would have been fixed when the finish was done. Martin estimates that between 1974 and 1986, his company completed over fourteen hundred residential pools and approximately five hundred large commercial pools. Martin has been active on various local pool construction industry boards and has no record of prior disciplinary action against his license.

Recommendation Based upon the foregoing, it is, hereby, RECOMMENDED: That Kenneth Martin be found guilty of misconduct, in violation of Section 489.129(1)(m), Florida Statutes, not guilty of the other violations with which he is charged, and that he be required to pay an administrative fine of $500.00. DONE and RECOMMENDED this 2nd day of August, 1988, in Tallahassee, Florida. MARY CLARK Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 2nd day of August, 1988. COPIES FURNISHED: David E. Bryant, Esquire 220 East Madison Street, Suite 530 Tampa, Florida 33602 Kenneth R. Martin 3225 North Glenn Drive Orlando, Florida 32806 Fred Seely, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 William O'Neil, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 =================================================================

Florida Laws (3) 120.57455.225489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer