RICHARD P. LEVY, D/B/A T-SHIRT FACTORY vs CITY OF CLEARWATER AND ANTONIOS MARKOPOULOS, 91-005218 (1991)
Division of Administrative Hearings, Florida Filed:Clearwater, Florida Aug. 19, 1991 Number: 91-005218 Latest Update: May 04, 1992

The Issue The issue in this case is whether the evidence sustains the decision of the City of Clearwater Development Code Adjustment Board (the Board) to deny the application of the Appellant, Richard P. Levy, d/b/a T-Shirt Factory, for a four parking space variance at his property located at 1498 Gulf to Bay Boulevard, at the junction of Gulf to Bay Boulevard, Highland Avenue and Court Street, Clearwater, Florida. (The variance is required as a result of his desire to convert 877.5 square feet of storage space in his building on the property to retail use.)

Findings Of Fact Appellant, Richard P. Levy, d/b/a T-Shirt Factory, owns part of lots 5 and 8, and all of lots 6 and 7, Block G, Boulevard Heights, at 1498 Gulf to Bay Boulevard, at the junction of Gulf to Bay Boulevard, Highland Avenue and Court Street, 0.24 acres, more or less, Clearwater, Florida. The T-Shirt Factory utilizes back-out parking into Gulf to Bay Boulevard and Highland Avenue. This type of parking for retail use is a traffic hazard and does not conform to the requirements of the City of Clearwater Land Development Code (the Code), but the property enjoys the benefit a having its retail use "grandfathered" under the Code because the prior owner also used the property and parking for retail sales at the time the Code was adopted. Gulf to Bay Boulevard is a busy and fairly high speed traffic artery. Highland Avenue also is a busy street. They meet at an acute angle with the Appellant's property inside the angle. Gulf to Bay Boulevard and Court Street, also a busy and fairly high speed traffic artery, meet at an acute angle just across the street from the Appellant's property, further complicating the traffic pattern in the vicinity of the Appellant's property. The Appellant filed its application for a four parking space variance to allow him to convert 877.5 square feet of storage space in his building on the property to retail use. The Appellant can make reasonable use of his property without the additional retail space. The Appellant's primary purposes in increasing retail space are to directly increase revenue and profit and to make the retail displays in his store more attractive and more spacious, in large part to prevent shoplifting and thereby indirectly increase revenues and profit. As now planned, unless advertised, the existance of additional retail space in the store would not be readily apparent to passers by not already familiar with the store. Nonetheless, the Appellant did not prove that the additional retail use will not lead eventually to additional use of the existing back-out parking on Gulf to Bay Boulevard and Highland Avenue. Even if the retail space were expanded as planned, and not advertised, the expansion eventually could lead to an increase in retail business, one of the Appellant's primary long term purposes.

# 1
MELLITA A. LANE vs DEPARTMENT OF ENVIRONMENTAL PROTECTION AND INTERNATIONAL PAPER COMPANY, 05-001609 (2005)
Division of Administrative Hearings, Florida Filed:Pensacola, Florida May 04, 2005 Number: 05-001609 Latest Update: Aug. 09, 2007

The Issue The issues in this case are whether IP is entitled to issuance of National Pollutant Discharge Elimination System (NPDES) Permit Number FL0002526-001/001-IW1S ("the proposed permit"), Consent Order No. 04-1202, Authorization for Experimental Use of Wetlands Order No. 04-1442, and Waiver Order No. 04-0730 (collectively, "the Department authorizations"), which would authorize IP to discharge treated industrial wastewater from its paper mill in Cantonment, Escambia County, Florida, into wetlands which flow to Elevenmile Creek and Perdido Bay.

Findings Of Fact Introduction A. The Parties The Department is the state agency authorized under Chapter 403, Florida Statutes (2006),2 to regulate discharges of industrial wastewater to waters of the state. Under a delegation from the United States Environmental Protection Agency (EPA), the Department administers the NPDES permitting program in Florida. IP owns and operates the integrated bleached kraft paper mill in Cantonment, Escambia County, Florida. FOPB is a non-profit Alabama corporation3 established in 1988 whose members are interested in protecting the water quality and natural resources of Perdido Bay. FOPB has approximately 450 members. About 90 percent of the members own property adjacent to Perdido Bay. James Lane is the President of FOPB. Mellita A. Lane, Zachary P. Lane, Peter A. Lane, and Sarah M. Lane are the adult children of Dr. Jacqueline Lane and James Lane. Dr. Lane and James Lane live on property adjacent to Perdido Bay with their son Peter. The Adjacent Waters The mill's wastewater effluent is discharged into Elevenmile Creek, which is a tributary of Perdido Bay. The creek flows southwest into the northeastern portion of Perdido Bay. Elevenmile Creek is a freshwater stream for most of its length but is sometimes tidally affected one to two miles from its mouth. Elevenmile Creek is designated as a Class III water. Perdido Bay is approximately 28 square miles in area and is bordered by Escambia County on the east and Baldwin County, Alabama on the west. The dividing line between the states runs north and south in the approximate middle of Perdido Bay. U.S. Highway 90 crosses the Bay, going east and west, and forms the boundary between what is often referred to as the "Upper Bay" and "Lower Bay." The Bay is relatively shallow, especially in the Upper Bay, ranging in depth between five and ten feet. Perdido Bay is designated as a Class III water. Sometime around 1900, a manmade navigation channel was cut through the narrow strip of land separating Perdido Bay from the Gulf of Mexico. The channel, called Perdido Pass, allowed the salt waters of the Gulf to move with the tides up into Perdido Bay. Depending on tides and freshwater inflows, the tidal waters can move into the most northern portions of Perdido Bay and even further, into its tributaries and wetlands. The Perdido River flows into the northwest portion of Perdido Bay. It is primarily a freshwater river but it is sometimes tidally influenced at and near its mouth. The Perdido River was designated an Outstanding Florida Water (OFW) in 1979. At the north end of Perdido Bay, between Elevenmile Creek and the Perdido River, is a large tract of land owned by IP called the Rainwater Tract. The northern part of the tract is primarily freshwater wetlands. The southern part is a tidal marsh. Tee and Wicker Lakes are small (approximately 50 acres in total surface area) tidal ponds within the tidal marsh. Depending on the tides, the lakes can be as shallow as one foot, or several feet deep. A channel through the marsh allows boaters to gain access to Tee and Wicker Lakes from Perdido Bay. The Mill 1. Production Florida Pulp and Paper Company first began operating the Cantonment paper mill in 1941. St. Regis Paper Company (St. Regis) acquired the mill in 1946. In 1984, Champion International Corporation (Champion) acquired the mill. Champion changed the product mix in 1986 from unbleached packaging paper to bleached products such as printing and writing grades of paper. In 2001, Champion merged with IP, and IP took over operation of the mill. The primary product of the mill continues to be printing and writing paper. The mill is integrated, meaning that it brings in logs and wood chips, makes pulp, and produces paper. The wood is chemically treated in cookers called digesters to separate the cellulose from the lignin in the wood because only the cellulose is used to make paper. Then the "brown stock" from the digesters goes through the oxygen delignification process, is mixed with water, and is pumped to paper machines that make the paper products. There are two paper machines located at the mill. The larger paper machine, designated P5, produces approximately 1,000 tons per day of writing and printing paper. The smaller machine, P4, produces approximately 400 to 500 tons per day of "fluff pulp." 2. The Existing Wastewater Treatment Plant The existing wastewater treatment plant (WWTP) at the mill is described in the revised NPDES permit as a "multi-pond primary and secondary treatment system, consisting of a primary treatment system (primary settling basin, polymer addition, two solids/sludge dewatering basins, and a floating dredge), and secondary treatment system (four ponds in series; two aerated stabilization basins with approximately 2,200 horsepower (HP) of aeration capacity, a nutrient feed system, two non-aerated polishing ponds and a final riffle section to re-aerate the effluent)." The WWTP is a system for reducing the biological oxygen demand (BOD) of the mill's wastewater by bacteria. IP’s wastewater is nutrient deficient when it enters the WWTP. Nutrients in the form of phosphorus and nitrogen must be added for the growth of bacteria. The WWTP begins with a primary settling basin in which suspended solids settle to the bottom. The solids form a sludge that is pumped by hydraulic dredge into two dewatering basins. The dewatering basins are used alternately so that, as one pond is filled, water is removed from the other pond. After being dewatered, the sludge is removed and allowed to dry. Then, it is transported to a landfill located about five miles west of the mill on land owned by IP. The water removed from the dewatering basins moves into to the first aeration basin. The aeration basin has floating aerator devices that add oxygen to facilitate biological conversion of the wastewater. The wastewater then flows sequentially through three more basins where there is further oxygenation and settling of the biological solids. The discharge from the fourth settling basin flows through a riffle section where the effluent is aerated using a series of waterfalls. This is the last element of the treatment process from which the mill's effluent enters waters of the state. Chemicals are added during the treatment process to control phosphorus and color. Chemicals are also added to suppress foam. Sanitary wastewater from the mill, after pretreatment in an activated sludge treatment system, is "sewered" to the mill's WWTP and further treated in the same manner as the industrial wastewater. A separate detention pond collects and treats stormwater from onsite and offsite areas and discharges at the same point as the wastewater effluent from the WWTP. Stormwater that falls on the industrial area of the mill is processed through the WWTP. The discharge point from the WWTP, and the point at which the effluent is monitored for compliance with state effluent limitations, is designated D-001, but is also called the Parshall Flume. The effluent is discharged from the Parshall Flume through a pipe to an area of natural wetlands. After passing through the wetlands, the combined flow runs through a pipe that enters Elevenmile Creek from below the surface. This area is called the "boil" because the water can be observed to boil to the surface of Elevenmile Creek. From the boil, the mill effluent flows approximately 14 miles down (apparently misnamed) Elevenmile Creek to upper Perdido Bay. Regulatory History of the Mill Before 1995, the mill had to have both state and federal permits. The former Florida Department of Environmental Regulation (DER) issued St. Regis an industrial wastewater operating permit in 1982 pursuant to Chapter 403, Florida Statutes. The EPA issued St. Regis an NPDES permit in 1983 pursuant to the Clean Water Act. When it acquired the facility in 1984, Champion continued to operate the mill under these two permits. In 1986, Champion obtained a construction permit from DER to install the oxygen delignification technology and other improvements to its WWTP in conjunction with the conversion of the production process from an unbleached to a modified bleached kraft production process. In 1987, Champion applied to DER for an operating permit for its modified WWTP and also petitioned for a variance from the Class III water quality standards in Elevenmile Creek for iron, specific conductance, zinc, and transparency. DER's subsequent proposal to issue the operating permit and variance was formally challenged.4 In 1988, while the challenges to the DER permit and variance were still pending, Champion dropped its application for a regular operating permit and requested a temporary operating permit (TOP), instead. In December 1989, DER and Champion entered into Consent Order No. 87-1398 ("the 1989 Consent Order"). The 1989 Consent Order included an allegation by DER that the mill's wastewater discharge was causing violation of state water quality standards in Elevenmile Creek for dissolved oxygen (DO), un-ionized ammonia, and biological integrity. The 1989 Consent Order authorized the continued operation of the mill, but established a process for addressing the water quality problems in Elevenmile Creek and Perdido Bay and bringing the mill into compliance in the future. Champion was required to install equipment to increase the DO in its effluent within a year. Champion was also required to submit a plan of study and, 30 months after DER's approval of the plan of study, to submit a study report on the impacts of the mill's effluent on DO in Elevenmile Creek and Perdido Bay and recommended measures for reducing or eliminating adverse impacts. The study report was also supposed to address the other water quality violations caused by Champion. A comprehensive study of the Perdido Bay system was undertaken by a team of 24 scientists lead by Dr. Robert Livingston, an aquatic ecologist and professor at Florida State University. The initial three-year study by Dr. Livingston's team of scientists was followed by a series of related scientific studies, which will be referred to collectively in this Recommended Order as "the Livingston studies." The 1989 Consent Order had no expiration date, but it was tied to the TOP, which had an expiration date of December 1, 1994. Champion was to be in compliance with all applicable water quality standards by that date. The TOP established the following specific effluent discharge limitations for the mill: Monthly Average Maximum Biological Oxygen Demand (BOD) (Mar-Oct) 4,500 lbs/day 6,885 lbs/day (Nov-Feb) 5,100 lbs/day 6,885 lbs/day Total Suspended Solids (TSS) (Mar-Oct) 8,000 lbs/day 27,000 lbs/day (Nov-Feb) 11,600 lbs/day 27,000 lbs/day Iron 3.5 mg/l Specific Conductance 2,500 micromhos/cm Zinc .075 mg/l The limits stated above for iron, specific conductance, and zinc were derived from the variance granted to Champion. Champion was also granted variances from the water quality standards for biological integrity, un-ionized ammonia, and DO. The 1989 Consent Order, TOP, and variance were the subject of the Recommended Order and Final Order issued in Perdido Bay Environmental Association, Inc. v. Champion International Corporation, 89 ER FALR 153 (DER Nov. 14, 1989). Champion's deviation from the standards for iron, zinc, and specific conductance pursuant to the variance was determined to present no significant risk of adverse effect on the water quality and biota of Elevenmile Creek and Perdido Bay. The mill effluent's effect on transparency (reduced by color in the mill effluent) was considered a potentially significant problem. However, because it was found that there was no practicable means known or available to reduce the color, and there was insufficient information at that time to determine how Champion's discharge of color was affecting the biota, Champion was allowed to continue its discharge of color into Elevenmile Creek pending the results of the Livingston studies. In the administrative hearing, the petitioners argued that it was unreasonable to put off compliance for five years, but the hearing officer determined that five years was reasonable under the circumstances. One finding in the Recommended Order and a reason for recommending approval of the TOP and Consent Order was: After the studies referred to in the consent order, the Department will not allow Champion additional time to study problems further. Significant improvements will be required within the five year period and at the end of that period, the plant will be in compliance with all water quality standards or will be denied an operating permit, with related enforcement action. The requirement of the 1989 Consent Order that Champion be in compliance with all applicable standards by December 1994, was qualified with the words "unless otherwise agreed." In considering this wording, the hearing officer opined that any change in the compliance deadline "would require a new notice of proposed agency action and point of entry for parties who might wish to contest any modification in the operational requirements, or changes in terms of compliance with water quality standards." The mill was not in compliance with all water quality standards in December 1994. No enforcement action was taken by the Department and no modification of the 1989 Consent Order or TOP was formally proposed that would have provided a point of entry to any members of the public who might have objected. Instead, the Department agreed through correspondence with Champion to allow Champion to pursue additional water quality studies and to investigate alternatives to its discharge to Elevenmile Creek. In 1994 and 1995, Champion applied to renew its state and federal wastewater permits, which were about to expire. The Department and EPA notified Champion that its existing permits were administratively extended during the review of the new permit applications. Today, the Cantonment mill is still operating under the 1989 TOP which, due to the administrative extension, did not terminate in December 1994, as stated on its face. In November 1995, following EPA's delegation of NPDES permitting authority to the Department, the Department issued an order combining the state and federal operating permits into a single permit identified as Wastewater Permit Number FL0002526-002-IWF/MT. In summary, the permit requirements currently applicable to the operation of the Cantonment paper mill are contained in the following documents: January 3, 1983, EPA NPDES Permit December 13, 1989, DER Temporary Operating Permit (TOP) December 13, 1989, DER Consent Order December 12, 1989, DER Variance November 15, 1995, DEP Order (combining the NPDES permit and the State-issued wastewater permit) April 22, 1996, DEP Letter (clarifying November 15, 1995, Order regarding 1983 NPDES Permit) During the period from 1992 to 2001, more water quality studies were conducted and Champion investigated alternatives to discharging into upper Elevenmile Creek, including land application of the effluent and relocation of the discharge to lower Elevenmile Creek or the Escambia River. In 2001, IP and Champion merged and IP applied to the Department to have the mill permit and related authorizations transferred to IP. Dr. Lane formally challenged the proposed transfer, but she was determined to lack standing. One conclusion of law in the Recommended Order issued in the 2001 administrative case was that the mill was in compliance with the consent order, TOP, and variance. That conclusion was not based on a finding that Champion was in compliance with all applicable water quality standards, but that the deadline for compliance (December 1, 1994) had been extended indefinitely by the pending permit renewal application. In 2001, Dr. Lane twice petitioned the Department for a declaratory statement regarding the Department's interpretation of certain provisions of the 1989 Consent Order. The first petition was denied by the Department because Dr. Lane failed to adequately state her interests and because she was a party in a pending case in which the Consent Order was at issue. Dr. Lane second petition was denied for similar reasons. Over 14 years after the deadline established in the 1989 TOP for the mill to be in compliance with all applicable standards in Elevenmile Creek, IP is still not meeting all applicable standards. However, the combination of (1) Consent Order terms that contemplated unspecified future permit requirements based on yet-to-be-conducted studies, (2) the wording in the TOP that tied the deadline for compliance to the expiration of the TOP, and (3) the administrative extension of the TOP, kept the issue of Champion's and IP's compliance in a regulatory limbo. It increased the Department's discretion to determine whether IP was in compliance with the laws enacted to protect the State's natural resources, and reduced the opportunity of interested persons to formally disagree with that determination. The Proposed Authorizations A. In General In September 2002, while Champion's 1994 permit renewal application was still pending at DEP, IP submitted a revised permit renewal application to upgrade the WWTP and relocate its discharge. The WWTP upgrades consist of converting to a modified activated sludge treatment process, increasing aeration, constructing storm surge ponds, and adding a process for pH adjustment. The new WWTP would have an average daily effluent discharge of 23.8 million gallons per day (mgd). IP proposes to convey the treated effluent by pipeline 10.7 miles to a 1,464-acre wetland tract owned by IP5, where the effluent would be distributed over the wetlands as it flows to lower Elevenmile Creek and upper Perdido Bay. IP revised its permit application again in October 2005, to obtain authorization to reconfigure the mill to produce unbleached brown paper for various grades of boxes. If the mill is reconfigured, only softwood (pine) would be used in the new process. On April 12, 2005, the Department issued a Notice of Intent to Issue the proposed NPDES permit, together with Consent Order No. 04-1202, Authorization for Experimental Use of Wetlands Order No. 04-4442, and Waiver Order No. 04-0730. An exemption from water quality criteria in conjunction with the experimental use of wetlands for wastewater treatment is provided for in Florida Administrative Code Rule 62-660.300(1). The proposed exemption order would exempt IP from Class III water quality criteria for pH, DO, transparency, turbidity, and specific conductance. The proposed waiver order is associated with the experimental use of wetlands exemption and relieves IP of the necessity to comply with two exemption criteria related to restricting public access to the area covered by the exemption. The Department and IP contend that restricting public access to Tee and Wicker Lakes is unnecessary. The proposed Consent Order is an enforcement document that is necessary if the mill is to be allowed to operate despite the fact that its wastewater discharge is causing violations of water quality standards. A principal purpose of the proposed Consent Order is to impose a time schedule for the completion of corrective actions and compliance with all state standards. The proposed Consent Order would supersede the 1989 Consent Order. The Proposed NPDES Permit 1. WWTP Upgrades IP's primary objective in upgrading the WWTP was to reduce the nitrogen and phosphorus in the mill's effluent discharge. The upgrades are designed to reduce un-ionized ammonia, total soluble nitrogen, and phosphorus. They are also expected to achieve a modest reduction of BOD and TSS. Upgraded pond 1 is expected to convert soluble BOD to suspended solids and to accomplish other biological conversions seven or eight times faster than the current pond 1. The modification of pond 3 to an activated sludge system is expected to more rapidly remove and recycle the solids back into pond 1. Pond 3 will have a much larger bacterial population to treat the effluent. There would also be additional pH control at the end of pond 3. IP would continue to use its Rock Crossing Landfill for disposal of wastewater sludge removed from the WWTP. Authorization for the landfill is part of the proposed NPDES permit. Groundwater monitoring beneath the landfill is required. The WWTP upgrades would include increased storm surge capacity by converting two existing aeration and settling basins (ponds 2 and 4) to storm surge basins. The surge basins would allow the mill to manage upsets and to withstand a 25-year, 24-hour storm event of 11 inches of rain. Rainfall that falls into the production areas would flow to the WWTP, and be impounded in ponds 2 and 4. After the storm event this impounded water would flow back through the WWTP where it would be treated before flowing through the compliance point and into the pipeline to the wetland tract. The Department required IP to monitor for over 129 pollutants in its stormwater runoff from the mill’s manufacturing facility, roads, parking lots, and offsite nonpoint sources. No pollutants were found in the stormwater at levels of concern. The average volume of mill discharge would be mgd. IP plans to obtain up to 5 mgd of treated municipal wastewater from a new treatment facility planned by the Emerald Coast Utility Authority (ECUA), which would be used in the paper production process and would reduce the need for groundwater withdrawals by IP for this purpose. The treated wastewater would enter the WWTP along with other process wastewater, be treated in the same manner in the WWTP, and become part of the effluent conveyed through the pipeline to the wetland tract. 2. Effluent Limitations The effluent limitations required by the proposed permit include technology-based effluent limits (TBELs) that apply to the entire pulp and paper industry. TBELs are predominantly production-based and are designed to limit the amount of pollutants that may be discharged per ton of product produced. The Cantonment mill has not had a problem in meeting TBELs. The TBELs that IP must meet are in the "Cluster Rule" promulgated by the EPA and adopted by the Department. The mill already meets the TBELS applicable to its current bleaching operation. In fact, EPA determined that the mill was performing in the top 5 percent of similar mills in the nation. The mill would have to meet the TBELs for a brown kraft operation if that conversion is made by IP. The proposed permit also imposes water quality- based effluent limits (WQBELs) that are specific to the Cantonment mill and the waters affected by its effluent discharge. The WQBELs for the mill are necessary for certain constituents of the mill's effluent because the TBELs, alone, would not be sufficient to prevent water quality criteria in the receiving waters from being violated. For example, the TBEL for BOD for similar pulp and paper mills is 15,943 pounds per day (ppd) on a monthly average, but the WQBEL for BOD for the Cantonment mill would be 4,500 ppd in summer and 5,100 ppd in winter. Dr. Livingston developed an extensive biological and chemical history of Perdido Bay and then evaluated the nutrient loadings from Elevenmile Creek over a 12-year period to correlate mill loadings with the biological health of the Bay. Because Dr. Livingston determined that the nutrient loadings from the mill that occurred in 1988 and 1989 did not adversely impact the food web of Perdido Bay, he recommended effluent limits for ammonia nitrogen, orthophosphate, and total phosphorous that were correlated with mill loadings of these nutrients in those years. The Department used Dr. Livingston’s data, and did its own analyses, to establish WQBELs for orthophosphate for drought conditions and for nitrate-nitrite. WQBELs were ultimately developed for total ammonia, orthophosphate, nitrate-nitrite, total phosphorus, BOD, color, and soluble inorganic nitrogen. The WQBELs in the proposed permit were developed to assure compliance with water quality standards under conditions of pollutant loadings at the daily limit (based on a monthly average) during low flow in the receiving waters. The proposed permit also establishes daily maximum limits (the most that can be discharged on any single day). For BOD, the daily maximum limit is 9,000 ppd. William Evans, the Department employee with primary responsibility for the technical review of the proposed Department authorizations, said that setting the daily maximum limit at twice the monthly average was a standard practice of the Department. The maximum daily limits are not derived from the Livingston studies. Dr. Glen Daigger, a civil and environmental engineer, designed a model for the WWTP and determined the modifications necessary to enable the WWTP's discharge to meet all TBELs and WQBELs. Petitioners did not dispute that the proposed WWTP is capable of achieving the TBELs and WQBELs. Their main complaint is that the WQBELs are not adequate to protect the receiving waters. 3. Discharge to the Wetland Tract IP proposes to relocate its discharge to the wetland tract as a means to end decades of failure by the mill to meet water quality standards in Elevenmile Creek. Discharging to the wetland tract, which flows to the marine waters of lower Elevenmile Creek and Perdido Bay, avoids many of the problems associated with trying to meet the more stringent water quality standards applicable in a freshwater stream. An effluent distribution system is proposed for the wetland tract to spread the effluent out over the full width of the wetlands so that their full assimilative capacity is utilized. This would be accomplished by a system of berms running perpendicular to the flow of water through the wetlands, and gates and other structures in and along the berms to gather and redistribute the flow as it moves in a southerly direction toward Perdido Bay and lower Elevenmile Creek. The design incorporates four existing tram roads that were constructed on the wetland tract to serve the past and present silviculture activities there. The tram roads, with modifications, would serve as the berms in the wetland distribution system. As the effluent is discharged from the pipeline, a point designated D-003, it would be re-aerated6 and distributed across Berm 1 through a series of adjustable, gated openings. Mixing with naturally occurring waters, the effluent would move by gravity to the next lower berm. The water will re-collect behind each of the vegetated berms and be distributed again through each berm. The distance between the berms varies from a quarter to a half mile. Approximately 70 percent of the effluent discharged at D-003 would flow by gravity a distance of approximately 2.3 miles to Perdido Bay. The remaining 30 percent of the effluent would flow a shorter distance to lower Elevenmile Creek. A computer simulation performed by Dr. Wade Nutter, an expert in hydrology, soils, and forested wetlands, indicated that the effluent discharged at D-003 will move through the wetland tract at a velocity of approximately a quarter-of-a-foot per second and the depth of flow across the wetland tract will be about one-half inch. It would take four or five days for the effluent to reach lower Elevenmile Creek and Perdido Bay. As the treated effluent flows through the wetland tract, there will be some removal of nutrients by plants and soil. Nitrogen and phosphorous are expected to be reduced approximately ten percent. BOD in the effluent is expected to be reduced approximately 90 percent. Construction activities associated with the effluent pipeline and berm modifications in the wetland tract were permitted by the Department in 2003 through issuance of a Wetland Resource Permit to IP. The United States Army Corps of Engineers has also permitted this work. No person filed a petition to challenge those permits. A wetland monitoring program is required by the proposed permit. The stated purpose of the monitoring program is to assure that there are no significant adverse impacts to the wetland tract, including Tee and Wicker Lakes, and is referred to as the No Significant Adverse Impact (NSAI) analysis. A year of "baseline data" on the wetlands and Tee and Wicker Lakes was collected and submitted to the Department for use in developing the NSAI analysis, but was not made a part of the record in this case. After the discharge to the wetland tract commences, the proposed permit requires IP to submit wetland monitoring reports annually to the Department. A monitoring program was also developed by Dr. Livingston and other IP consultants to monitor the impacts of the proposed discharge on Elevenmile Creek and Perdido Bay. It was made a part of the proposed permit. The Exemption for Experimental Use of Wetlands Florida Administrative Code Rule 62-660.300(1) provides an exemption from water quality criteria for the experimental use of wetlands. The proposed Authorization for Experimental Use of Wetlands Order would exempt IP from Class III water quality criteria for pH, DO, transparency, turbidity, and specific conductance. The proposed exemption order sets forth "interim limits" for pH, DO, color, turbidity, and specific conductance. The proposed exemption order also states that IP may petition for alternative water quality criteria pursuant to Florida Administrative Code Rule 62- 66D.300(1)(b)(c) and (d). The exemption is for 5 years beginning with the commencement of discharge into the wetland tract at D-003. The exemption it can be renewed by IP by application to the Department. The Waiver To qualify for the experimental use of wetlands exemption, Florida Administrative Code Rules 62- 660.300(1)(a)3 and 4 require, respectively, that the public be restricted from the exempted wetland area and that the waters not be used for recreation. IP proposes to prevent public access to the area of the wetland tract where the effluent distribution system is located. This is the freshwater area of the wetland tract and includes the four berms. However, IP does not want, nor believe it is necessary, to prevent public access and recreation on Tee and Wicker Lakes within the tidal marsh below berm 4. These lakes are accessible by boat from Perdido Bay and are used now by the public for boating and fishing. The Proposed Consent Order The proposed Consent Order establishes a schedule for the construction activities associated with the proposed WWTP upgrades and the effluent pipeline and for incremental relocation of the mill's discharge form Elevenmile Creek to the wetland tract. IP is given 24 months to complete construction activities and begin operation of the new facilities. At least 25 percent of the mill's effluent must be diverted to the wetland tract. At least 25 percent of the effluent is to be diverted to the wetland tract when the new facilities begin operations. The volume of effluent diverted to the wetlands is to increase another 25 percent every three months thereafter so that three years after issuance of the permit 100 percent of the effluent is being discharged into the wetland tract and there is no longer a discharge at D-001 into Elevenmile Creek.7 The proposed Consent Order establishes interim effluent limitations that would apply immediately upon the effective date of the Consent Order and continue during the 24-month construction period when the mill will continue to discharge into Elevenmile Creek. Other interim effluent limits would apply during the 12-month period following construction when the upgraded WWTP would be operating and the effluent would be incrementally diverted from Elevenmile Creek to the wetland tract. A third set of interim effluent limits would apply at D-003 when 100 percent of the discharge is into the wetland tract. They include the interim limits for specific conductance, pH, DO, color, and turbidity established through the experimental use of wetland exemption. The proposed Consent Order requires IP to submit a report within six months with the results of the 2004 transparency study. The Department must be satisfied that the study shows the transparency standard will not be violated before the wetlands can be used for the discharge. This report has already been submitted to the Department, but the Department has not yet completed its review of the report. Nevertheless, it was admitted into the record as IP Exhibit 79. The proposed Consent Order provides that, in the event IP's does not receive treated sanitary wastewater from the planned ECUA facility, IP will notify the Department and submit an alternate compliance plan to the Department for the Department's approval. The submittal and approval of an alternate compliance plan would extend the time for compliance with water quality standards by another six months. The Department amended the proposed Consent Order at the conclusion of the hearing to provide for notice to the public and an opportunity for persons to object to the Department's action on any alternate compliance plan. The Consent Order requires a "Plan of Action" to determine "whether there remains a critical period for ortho-phosphate loading to lower Elevenmile Creek and Perdido Bay." The proposed Consent Order requires IP to submit within 97 months (which would allow for five years of discharge to the wetland tract) a final report on whether there has been significant adverse impacts in the wetlands and Tee and Wicker Lakes resulting from the discharge of effluent pursuant to the interim limits for pH, DO, specific conductance, turbidity, and color. If the NSAI analysis shows no significant adverse impact has occurred, the proposed Consent Order contemplates that IP or the Department would establish alternative water quality criteria that would apply permanently in the wetland tract. IP is required by the Consent Order to submit quarterly progress reports of its progress toward compliance with the required corrective actions and deadlines. The Consent Order imposes a "stipulated penalty" of $500 per day for noncompliance with its terms. It also contains a statement that a violation of its terms may subject IP to civil penalties up to $10,000 per day. The Principal Factual Disputes A. The Evidence in General Much of the water quality and biological data presented by Petitioners were limited in terms of the numbers of samples taken, the extent of the area sampled, and the time period covered by the sampling. Much of the expert testimony presented by Petitioners was based on limited data, few field investigations, and the review of some, but not all relevant permit documents.8 On the other hand, the Livingston studies represent perhaps the most complete scientific evaluation ever made of a coastal ecosystem. Even Dr. Lane called the Livingston studies "huge" and "amazing." Therefore, with regard to the factual issues raised by Petitioners that involved scientific subjects investigated in the Livingston studies, Petitioners' data and the expert opinions based on those data were generally of much less weight than the data and conclusions of the Livingston studies. However, the Livingston studies did not address all of the factual issues in dispute. Some of the evidence presented by Petitioners regarding historical water quality conditions in Perdido Bay and Elevenmile Creek was lay testimony. The lay testimony was competent and sufficient to prove the existence of environmental conditions that are detectable to the human senses, such as an offensive smell, a dark color, or a sticky texture. Historical Changes in Perdido Bay Petitioners claim that, before the Cantonment mill began operations in the 1940s, Perdido Bay was a rich and diverse ecosystem and a beautiful place for swimming, fishing, boating, and other recreational activities. Petitioners blame the mill effluent for all the adverse changes they say have occurred in Perdido Bay. Petitioners claim that the water in Perdido Bay was much clearer before the mill was built. James Lane, who has lived on the Bay for 65 years, said he began to notice in the late 1940s that the water was becoming dark and filled with wood fibers. Mr. Lane recalls that there used to be an abundance of fish in the Perdido Bay, including croakers, pinfish, flounder, redfish, minnows, and catfish. Now Mr. Lane sees few of these fish in the Bay and he believes the remaining fish are unfit to eat because they look diseased to him. Mr. Lane said there were extensive areas of sea grasses in the Bay which supported large numbers of shrimp, crabs, and mussels, but these grasses are now gone. The Lane family used to enjoy swimming in Perdido Bay but stopped swimming years ago because the water felt sticky and often had a brown foam or scum on the surface. Mr. Lane and others members of FOPB claim to have gotten infections from swimming in the Bay. Mr. Lane and other witnesses described the odor of Elevenmile Creek near the mill as unpleasant and, at times, offensive. They consider the Creek to be too polluted for swimming. Donald Ray, who has been a Department biologist for 30 years, said he has received many complaints from citizens about the conditions in Perdido Bay. He said the foam that occurs in Perdido Bay is not natural foam, but one that persists and leaves a stain on boats. On the other hand, it is Dr. Livingston's opinion that the ecological problems of Perdido Bay are due primarily to the opening of Perdido Pass around 1900. The opening of the pass allowed Gulf waters to enter Perdido Bay and caused salinity stratification in the Bay, with marine waters on the bottom and fresh water from the Perdido River, Elevenmile Creek, and other tributaries on the top. The stratification occurs regularly in the lower Bay, but only during low flow conditions in most of the upper Bay, Perdido River, and Elevenmile Creek. It restricts DO exchange between the upper and lower water layers and results in low DO levels in the lower layer. Low DO, or "hypoxia," is the primary cause of reduced biological diversity and productivity in Perdido Bay. Dr. Livingston's initial study of the Perdido Bay system (1988-91) included an investigation of historical conditions, using documents and maps, anecdotal statements of area residents, as well as historic water quality and sediment data. Dr. Livingston found general agreement from most sources that: [P]rior to the 1940s, the various rivers and the bay in the Perdido Basin were quite different from what they are today. Eyewitness accounts from 1924 indicate a bay that was clear and "bluish" in color; the bottom could be seen at depths of five feet. According to resident' accounts, seagrasses grew from Garth Point to Witchwood; the grassbeds provided cover for many shrimp that were taken at the time. Flounder were taken with gigs and crabs were taken with hand nets. According to these accounts, the water from the various rivers and creeks in the area was relatively clear, and white sand/gravel bottoms were dominant forms of habitat in the freshwater and estuarine systems. The water was tea- colored but clear. Redfish, trout, blue crabs, shrimp, and mullet were abundant. * * * [T]hrough the early 1900s, the Elevenmile Creek was said to be crystal clear with soft white sand and good fishing. * * * According to various reports, in the early 1950s, the waters of Elevenmile Creek turned black, with concentrations of foam observed floating on the surface. By 1986, more than 28 million gallons of largely untreated effluent was flowing into the Elevenmile Creek- Perdido Bay system each day. Experiments by the Florida Game and Fresh Water Fish Commission had shown that the creek waters were lethal. The Florida Board of Health reported that Elevenmile Creek was "grossly polluted" and that Perdido Bay had been "greatly degraded within the 1.5 mile radius of where Elevenmile Creek dumped into the bay." Nevertheless, Dr. Livingston discounted much of this historical record, especially with regard to the belief that the mill's effluent had adversely affected Perdido Bay, because it was not based on what he considers reliable scientific data. He found "little evidence in the long- term sediment record of a direct response to historical activities of the pulp and paper mill, suggesting that the flushing capacity of Perdido Bay quickly diluted effluents that enter Perdido Bay from Elevenmile Creek." The evidence is persuasive that the salinity stratification in Perdido Bay is a major cause of low DO in the Bay.9 However, the stratification does not explain all of the observed changes in water quality, biological productivity, and recreational values. The stratification does not account for the markedly better conditions in the Bay that existed before the Cantonment paper mill began operations. The Livingston studies confirmed that when nutrient loadings from the mill were high, they caused toxic algae blooms and reduced biological productivity in Perdido Bay. As recently as 2005, there were major toxic blooms of heterosigma in Tee and Wicker Lakes caused by increased nutrient loading from the mill. Other competent evidence showed that the mill's effluent has created nuisance conditions in the past, such as foam and scum, which adversely affected the recreational values of these public waters. Some of the adverse effects attributable to the mill effluent were most acute in the area of the Bay near the Lanes' home on the northeastern shore of the Bay, because the flow from the Perdido River tends to push the flow from Elevenmile Creek toward the northeastern shore. Petitioners were justified in feeling frustrated in having their concerns about the adverse impacts of the mill's effluent discounted for many years, and in having to wait so long for an effective regulatory response. However, with regard to many of their factual disputes, Petitioners' evidence lacked sufficient detail regarding the dates of observations, the locations of observations, and in other respects, to distinguish the relative contribution of the mill effluent from other factors that contributed to the adverse impacts in the Bay, such as salinity stratification, natural nutrient loading from the Perdido River and other tributaries, and anthropogenic sources of pollution other than the paper mill.10 Petitioners generally referred to the mill effluent and its impacts to Perdido Bay as if they have been relatively constant for 65 years. The Livingston studies, however, showed clearly that the mill effluent and its impacts, as well as important factors affecting the impacts, such as drought, have frequently changed. Focusing on the fact that the average daily BOD loading allowed under the proposed permit would be same as under the 1989 TOP (4,500 ppd), Petitioners remarked several times at the final hearing that the proposed permit for the mill was no different than the existing permit. According to Petitioners, if the mill is allowed to operate under the proposed permit, one can predict that the future adverse impacts to Perdido Bay will be the same as the past adverse impacts. However, the 1989 TOP and the proposed permit are very different. Therefore, it cannot be assumed that the impacts would be the same. Petitioners' evidence was generally insufficient to correlate past adverse impacts to Perdido Bay with the likely impacts that would occur under the proposed permit. In contrast, that was the focus of the Livingston studies. Development of the WQBELs Whether Perdido Bay is an Alluvial System and Whether Elevenmile Creek is a Blackwater Stream Alluvial systems are generally characterized by relatively high nutrient inputs from tributaries and associated wetlands that provide for high biological productivity in the receiving bay or estuary. Petitioners disagree with Dr. Livingston's characterization of the Perdido Bay system as an alluvial system. Petitioners presented the testimony of Donald Ray, a Department biologist, who said that the Perdido River is not an alluvial river and the natural nutrient loadings to Perdido Bay are less than would occur in an alluvial system. Although it is curious that two experienced biologists cannot agree on whether Perdido Bay is part of an alluvial system, the dispute is immaterial because it was not shown by Petitioners that any of the four proposed Department authorizations is dependent on the applicability of the term "alluvial." The WQBELs developed by Dr. Livingston, for example, were not dependent on a determination that Perdido Bay meets some definition of an alluvial system, but were based on what the data indicated about actual nutrient loadings into Perdido Bay and the Bay's ecological responses to the loadings. If the dispute is not immaterial, then Dr. Livingston's opinion that Perdido Bay is part of an alluvial system is more persuasive, because he has greater experience and knowledge of the coastal bay systems on the Florida Panhandle than does Mr. Ray. Petitioners also take exception to Dr. Livingston's characterization of Elevenmile Creek as a blackwater creek. Petitioners claim Elevenmile Creek is naturally clear to "slightly tannic" stream. This dispute, however, is also immaterial because the proposed permit calls for the termination of the mill's discharge to Elevenmile Creek, including its contribution of color to the Creek. Petitioners assert that Dr. Livingston's characterizations of Perdido Bay as an alluvial system and Elevenmile Creek as a blackwater creek show he is biased and that his "overall analysis" lacks credibility. Dr. Livingston's opinions on these points do not show bias nor compromise the credibility of his overall analysis of the Perdido Bay system, which is actually the product of many scientists and based on 18 years of data.11 2. Selection of 1988 and 1989 Mill Loadings as a Benchmark for the WQBELs Generally, the Department establishes effluents limits for nutrients based on Chlorophyl A analysis. However, the Livingston studies showed that Chlorophyl A was not significantly associated with plankton blooms in Perdido Bay. Therefore, the Department accepted Dr. Livingston's recommendation to base the WQBELs for nutrients on the nutrient loading from the mill in 1988 and 1989, which the Livingston studies showed were good years for Perdido Bay with respect to its biological health. Phytoplankton are a fundamental component of the food web in Perdido Bay. The number of phytoplankton species is a sensitive indicator of the overall ecological health of the Bay. The Livingston studies showed that the loadings of ammonia and orthophosphate from the mill had a direct effect on the number of phytoplankton species. In the years when the mill discharged high loadings of ammonia and orthophosphate, there were toxic algae blooms and reduced numbers of phytoplankton species. In 1988 and 1989, when the loadings of ammonia and orthophosphate were lower, there were no toxic algae blooms, and there were relatively high numbers of phytoplankton species. Petitioners dispute that 1988 and 1989 are appropriate benchmarks years for developing the WQBELs because Petitioners claim there were high nutrient loadings and algae blooms in those years. Mr. Ray testified that the Department received citizen complaints about algae blooms in those years. Dr. Livingston's analysis was more persuasive, however, because it distinguished types of algae blooms according to their harmful effect on the food web and was based on considerably more water quality and biological data. Petitioners also presented water quality data collected from 1971 to 1994 by the Bream Fishermen Association at one sampling station in the northeastern part of Perdido Bay, which indicate that in 1988 and 1989, the concentrations of nutrients were sometimes high. The proposed nutrient WQBELs were derived from data about the actual response of the Perdido Bay ecosystem over time to various inputs. The sampling data from the Bream Fishermen Association were not correlated to ecosystem response and, therefore, are insufficient to refute Dr. Livingston's evidence that 1988 and 1989 were years of relatively high diversity and productivity in Perdido Bay. Furthermore, nutrients loadings would be reduced under the proposed permit. 3. DO and Sediment Oxygen Demand The parties agreed that sediment oxygen demand (SOD) is a major reason for the low DO in Perdido Bay in areas where there is salinity stratification. SOD is caused by the bacterial degradation of particulate organic matter that settles to the bottom. SOD decreases DO in the lower water layer, but also can cause a reduction of DO in the surface layer. Low DO has substantially reduced the biological productivity of Perdido Bay. Thomas Gallagher, an environmental engineer and water quality modeling expert, showed that even without the mill discharge, DO in the bottom waters of Perdido Bay would fall below the applicable Class III water quality standard of 5 mg/l. Low DO conditions are now a "natural" characteristic of the Bay, usually occurring during summer and early fall when freshwater flows are low and temperatures are high. At these times, surface water DO levels are usually above the state standard, but DO in the bottom waters usually range between 1.0 and 2.0 mg/l. Petitioners claim that the dominant source of the sediment in Perdido Bay is the carbon and nutrient loading in the mill's effluent that flows into the Bay from Elevenmile Creek. Mr. Ray, who sampled sediments in Perdido Bay over several years for the Department, believes that the mill effluent is the main source of the sediment and, consequently, the sediment oxygen demand. Dr. Livingston did extensive sediment analyses in Perdido Bay. He compared the data with sediment data from other bays on the Florida Panhandle. It is Dr. Livingston's opinion that the mill effluent contributes little to the sediments or SOD in Perdidio Bay. His initial three-year study concluded: [T]he hypoxic conditions of Elevenmile Creek are due, in part, to mill discharges. However, low dissolved oxygen conditions at depth in Perdido Bay are not due to the release of mill effluents from Elevenmile Creek, and can actually be attributed to a long history of human activities that include alteration of the hydrological interactions at the gulfward end of the estuary. The entry of saline water from the Gulf and the resulting stratification have been coupled with various forms of human development that release carbon, nitrogen, and phosphorus compounds into the estuary. The landward movement of high-salinity water from the Gulf of Mexico, laden with various types of oxygen-consuming compounds from various sources, together with oxygen demand from sediments to the lower water column that is isolated from reaeration due to salinity stratification, are thus responsible for a large portion of the observed hypoxic conditions at depth in Perdido Bay. [The paper mill] is responsible for a relatively small amount of these oxygen-consuming effects. In East Bay, which is a part of Escambia Bay and a relatively pristine system, there was SOD that caused DO to fall below standards in the lower water layer. Dr. Livingston also found severe oxygen deprivation at times in the lower waters of the Styx River and Perdido River, which do not receive mill effluent. Dr. Livingston believes the low DO that occasionally occurs in these rivers is due to agricultural runoff, urban discharges, and natural organic loading from adjacent wetlands. There was extensive evidence, some of which was presented by Petitioners, showing that the mill loadings of carbon and nutrients are less than the loadings from the Perdido River. Mr. Gallagher concluded that the sediment in the Bay is mostly "terrestrial carbon," and not from the mill's effluent. His water quality modeling work determined that the mill's effluent reduced bottom layer DO by about 0.1 mg/l. Dr. Lane believes that the organic solids in the mill's effluent are accumulating in Perdido Bay sediments, but Mr. Gallagher pointed out that degrading solids cannot accumulate because they are degrading. In addition, Mr. Gallagher said that logic dictates that solids that have not settled out after spending several days in the settling basins of IP's WWTP are not going to readily settle in the more turbulent environment of Perdido Bay. Some of the solids are oxidizing or being transported into the Gulf. Mr. Gallagher determined that in summer and late fall, 60 percent of the water in the bottom layer in the upper Bay is from the Gulf and almost all the rest is from the Perdido River. He believes only 0.1 to 2.0 percent of the water in the bottom layer is mill effluent. Dr. Livingston responded to the BOD and carbon issues that "these Petitioners raised over the years" by investigating them as part of the Livingston studies. He found no relationship between loading and DO. Dr. Livingston concluded that the mill was not having much effect on SOD. Dr. Livingston and Mr. Gallagher referred to a carbon isotope study of the sediment in Perdido Bay by Coffin and Cifuentes. The isotope study was a part of the initial three-year Livingston study entitled "Ecological Study of the Perdido Bay Drainage System." The study identified a unique carbon isotope in the mill's effluent and looked for traces of the isotope in the sediments of Perdido Bay. Very little of the carbon isotope was found in the sediments, suggesting that the mill's effluent was not contributing much to the sediments. The carbon isotope study was not offered into evidence. Petitioners assert that the isotope study is hearsay and cannot be used to support a finding of fact.12 However, Dr. Livingston's opinion about the sources of the sediment was not based solely on the isotope study. The isotope study was consistent with his other studies and with Mr. Gallagher's water quality modeling analysis. Therefore, the conclusions of the isotope study serve to support and explain Dr. Livingston's expert opinion that the mill effluent is not the primary source of the sediment and low DO in Perdido Bay. Dr. Livingston summarized his opinion regarding DO and SOD as follows: "all of these lines of evidence, from all the bays that I have worked in and from them scientific literature and from our own studies, every line of evidence simply eliminated the pulp mill as the primary source of the low dissolved oxygen in the bay." 4. Long-term BOD BOD is a measurement of the oxygen demand exerted by the oxidation of carbon, nitrogen, and the respiration of algae. A five-day BOD analysis is the standard test used in the regulatory process. The use of the standard five-day BOD measurement is not restricted to organic material that is expected to completely degrade in five days. Five days is simply the time period selected to standardize the measurement. For example, the five-day BOD analysis is used in the regulation of domestic wastewater even though most of the organic material in domestic wastewater takes about 60 days to degrade and would exert an oxygen demand throughout the 60 days. It was undisputed that paper mill effluent will continue to consume DO after five days. One estimate given was that it would take 100 days to completely degrade. Some of the naturally occurring organic material flowing into Perdido Bay from the Perdido River and Gulf of Mexico would also include material with long-term BOD. Petitioners claim that long-term BOD analysis is essential to determine the true impacts of the mill's effluent on Perdido Bay, but they failed to show that the Livingston studies did not consider long-term BOD.13 The evidence shows that Dr. Livingston's studies accounted for DO demand in all its forms and for any duration. Dr. Livingston's studies focused on the response of Perdido Bay's food web to nutrients and various other inputs as they changed over time. If long-term BOD was having an adverse effect on the food web, the Livingston studies were designed to detect that effect. Dr. Livingston's opinion is that long-term BOD is not a significant problem for Perdido Bay because the Bay is part of a dynamic system and the sediments are regularly flushed out or otherwise recycled in a matter of a few months, not years.14 5. Carbon Dr. Lane, who is a marine biologist, believes a major reason for low DO in Perdido Bay is "organic carbonaceous BOD." However, Dr. Lane presented no evidence other than statements of the theoretical process by which carbon from the mill would cause low DO in the Bay. She presented no scientific data from Perdido Bay to prove her theory.14 Dr. Livingston said that 16 years of studies in the Bay have found DO and carbon to be "totally uncorrelated." Other Water Quality Issues 1. Toxicity Petitioners allege that the mill effluent has had occasional problems passing toxicity tests. Un-ionized ammonia is the likely cause, and the reduction of un-ionized ammonia in the proposed permit and the distribution of the effluent over the wetland tract should prevent toxicity problems from recurring. Dr. Livingston examined tissue samples from various fish and invertebrates and found low levels of bioconcentrating chlorine compounds in Perdido Bay that he believes were "probably associated with discharges from the Pensacola mill." Although they are toxic substances, Dr. Livingston found no diseased organisms and no evidence of food web magnification of these potentially bioaccumulable compounds. Mr. Ray testified that Perdido Bay was the worst of all the bays he has studied in terms of high sediment metals. Most of his sediment sampling was done in 1977 through 1983, years before the Livingston studies got started. His knowledge about subsequent years was based on only two samples, one in 1988 and another in 2005.16 Dr. Lane did an analysis of 12 sediment samples in Perdido Bay, Perdido River, and Elevenmile Creek in 1999 and concluded that "Eleven Mile Creek appears to be the source of all elevated levels [of metals] except silver." The Livingston studies included toxics analysis of Perdido Bay sediments, including metals, dioxin, and other chlorinated organic compounds. Dr. Livingston testified that metal concentrations in the sediments of Elevenmile Creek did not differ from the metal concentrations in the Perdido River and other streams in the area. The concentrations were not significantly different from concentrations in other bays he has studied that do not have a paper mill discharge. 2. Mutagenic Compounds Petitioners claim that there are chemicals in paper mill effluent that are mutagenic and are causing changes in the sex of fish. They introduced an exhibit from the Department's exhibit list (DEP Exhibit 38) that discussed investigations of effluent from the Cantonment mill and other Florida paper mills which found abnormally high testosterone levels and related mutations in female Gambusia fish. The most recent such study16 implicates androgens produced by the microbial degradation of natural chemicals in the trees pulped at the mills, especially softwood trees (pines), as the cause. Petitioners believe IP's proposal to begin using 100 percent pine at the Cantonment mill could cause mutations in fish and other animals exposed to the mill's effluent. Although IP and the Department are aware of the sex change studies, there was no evidence presented that the subject was investigated or addressed by them in the permitting process. DEP Exhibit 38 is hearsay and no non-hearsay evidence was presented on the issue of mutagenic compounds in the mill's effluent. Therefore, no finding of fact in this Recommended Order can be based on the data and analysis in DEP Exhibit 38.18 Furthermore, Petitioners did not raise the issue of mutagenic compounds in the mill's effluent discharge in their petitions for hearing or in the pre-hearing stipulation.19 Antidegradation Policy Petitioners claimed the proposed permit violated the antidegradation policy for surface waters established in Florida Administrative Code Rule 62-302.300(1). An element of that policy is to require, for any discharge that degrades water quality, a demonstration that the degradation is necessary or desirable under circumstances which are clearly in the public interest. Florida Administrative Code Rule 62-4.242(1)(a) contains a list of factors to be considered and balanced in applying the antidegradation policy. These include consideration of whether the proposed project would be beneficial to public health, safety, or welfare and whether the discharge would adversely affect the, conservation of fish and wildlife, and recreational values. The greater weight of the evidence supports the position of IP and the Department that the proposed discharge to the wetland tract would be an improvement over the existing circumstances. However, as discussed below, there was an insufficient demonstration that the discharge would not cause significant adverse impact to the biological community within the wetland tract, and there was an insufficient demonstration that the Perdido River OFW would not be significantly degraded. Without sufficient demonstrations on these points, it is impossible to find that the degradation has been minimized. Petitioners did not prove that the proposed project was not in the public interest, but the burden was on IP to show the opposite. Because IP did not make a sufficient demonstration regarding potential adverse impacts on the biological community within the wetland tract and on the Perdido River OFW, IP failed to prove compliance with Florida's antidegradation policy. Perdido River OFW Florida Administrative Code Rule 62-302.300(2) contains the standards applicable to OFWs and prohibits a discharge that significantly degrades an OFW unless the proposed discharge is clearly in the public interest or the existing ambient water quality of the OFW would not be lowered.20 Petitioners contend that the water quality of the Perdido River would be significantly degraded by the mill's effluent under the authorizations. Mr. Gallagher's modeling analysis predicted improved water quality in the Perdido River for DO and several other criteria over the conditions that existed in 1979, the year the river was designated as an OFW. However, the modeling also predicted that the discharge would reduce the DO in the river (as it existed in 1979) by .01 mg/l under unusual conditions of effluent loading at the daily limit (based on a monthly average) during a drought. Mr. Gallagher's modeling indicated that a very small (less than 0.1 mg/l) reduction in DO in the surface water of the lower Perdido River would occur as a result of the proposed project. He considered that to be an "insignificant" effect and it was within the model's range of error. However, IP made the wrong comparisons in its modeling analysis to determine compliance with the OFW rule, Florida Administrative Code Rule 62-4.242(2). Mr. Gallagher used the model to compare the DO levels in the Perdido River that would result from the mill's discharge of BOD at the proposed permit limit of 4,500 ppd with the predicted DO levels that would have existed in 1979 if St. Regis was discharging 5,100 ppd of BOD. IP should have compared the DO levels resulting from the proposed permit with the actual DO levels in 1979, or at least the DO levels that the model would have simulated using actual BOD loadings by St. Regis in 1979. The DO levels that would have existed in 1979 if St. Regis had discharged 5,100 ppd of BOD are irrelevant. No DO data from 1979 were presented at the hearing and no explanation was given for why DO data for 1979 were not used in the analysis. No evidence was presented that St. Regis discharged 5,100 ppd of BOD as a monthly average in 1979.21 It might have discharged substantially less.22 Petitioners did not prove that the proposed permit would significantly degrade the Perdido River, but the burden was on IP to show the opposite. Because the wrong anti-degradation comparison was made, IP failed to provide reasonable assurance that the Perdido River would not be significantly degraded by the proposed discharge. The Experimental Use of Wetlands Exemption Petitioners claim that IP did not demonstrate compliance with all the criteria for the experimental use of wetlands exemption. There are seven criteria set forth in Florida Administrative Code Rule 62-660.300(1)(a) that must be met to qualify for the exemption. IP is seeking a waiver from two of the criteria and those will be discussed later in this Recommended Order. Impact on the Biological Community a. In General Florida Administrative Code Rule 62- 660.300(1)(a)1 requires a demonstration that "the wetlands ecosystem may reasonably be expected to assimilate the waste discharge without significant adverse impact on the biological community within the receiving waters." Dr. Nutter used a "STELLA" wetland model to predict the effects of discharging mill effluent to the wetland tract. The STELLA model was programmed to evaluate the "water budget" for the wetland tract, as well as simulate the fate of nitrogen, phosphorus, and total dissolved solids (TDS). Petitioners contend that the STELLA model is too limited to adequately assess potential adverse impacts on the biological community, but the model was not the sole basis upon which Dr. Nutter formed his opinions. He also relied on relevant scientific literature, his general knowledge of wetland processes, and on his 40 years of experience in land treatment of wastewater. The STELLA model predicted that there would be about a 10 percent reduction in nitrogen and phosphorus. Dr. Nutter testified that that figure was a conservative prediction and the scientific literature suggests there could be a greater reduction. Wetlands are effective in processing TSS and BOD. Dr. Nutter ran the model with the proposed permit limits and the model predicted 90 to 95 percent BOD removal before the effluent reached berm 4. Dr. Nutter expected pH levels to be in the range of background levels in the wetlands, which vary between 6.5 and 8.0.23 Dr. Nutter predicts that in high flow conditions, there will be more DO in the water flowing from the wetlands into Tee and Wicker Lakes. During low flow conditions, he predicts no change in the DO level. Background DO levels in the wetland tract now range between and 5.0 mg/l. Mr. Gallagher's water quality modeling for Perdido Bay assumed that the water flowing from the wetland tract would have a DO level of 2.0 mg/l, which Dr. Nutter believes this is a conservative estimate, meaning it could be higher. Specific Conductance A fundamental premise of the relocated discharge is that it solves the mill's decades-long failure to meet the stricter water quality standards applicable in the fresh waters of Elevenmile Creek because the new receiving waters would be marine waters. However, the majority (about 70 percent) of the wetland tract is a freshwater wetland. The tidal influence does not reach above berm 4 in the wetland tract. Before the mill's effluent reaches marine waters, it would be distributed over the entire freshwater portion of the wetland tract. Dr. Livingston explained that, but for the mill's discharge, minnows and other small "primary" freshwater fish species would be found in Elevenmile Creek. The primary fish cannot tolerate the mill's discharge because the high levels of sodium chloride and sulfide (specific conductance) cause osmoregulatory problems, disrupting their blood metabolism and ion regulation. High conductivity also eliminates sensitive microinvertebrates. Because Tee and Wicker Lakes are in the tidally influenced, southern portion of the wetland tract, the fish and other organisms in the lakes are polyhaline, which means they are adapted to rapid changes in salinity, temperature and other habitat features. That is not true of the organisms in the freshwater area of the wetland tract. A constructed wetlands pilot project was built in 1990 at the Cantonment mill. The initial operational phase of the pilot project was July 1991 through June 1993. A second phase was conducted for just three months, from September 1997 through December 1997. The pilot project generated some information about "benthic macroinvertebrate diversity," which was "low to moderate." In addition, there were "observations" made of "three amphibian species, three reptile species, approximately 31 bird species, three fish species that were introduced, and two mammal species." The information generated by the pilot project is ambiguous with respect to the effect of the effluent on fish and other organisms attributable to the specific conductance of the effluent, indicating both successes and failures in terms of survival rates. Moreover, the data presented from the pilot wetland project lacks sufficient detail, both with respect to the specific conductivity of the effluent applied to the wetlands and with respect to the response of salt-intolerant organisms to the specific conductivity of the effluent, to correlate the findings of the pilot project with the proposed discharge to the wetland tract. Freshwater wetlands do not have naturally high levels of specific conductance. The specific conductance in the wetland tract is 100 micromhos/cm or less.24 The proposed interim limit for specific conductance for the discharge into the wetland tract is "2,500 micromhos/cm or 50% above background, whichever is greater." Using total dissolved solids (TDS) as a surrogate for analyzing the effects on specific conductance, Dr. Nutter predicted that average TDS effluent concentrations would only be reduced by 1.0 percent.25 His prediction is consistent with the literature on the use of wetlands for wastewater treatment, which indicates wetlands are not effective in reducing TDS and specific conductance. The wetland tract would not assimilate TDS in mill's effluent. The potential exists, therefore, for the discharge to cause specific conductance in the freshwater area of the wetland tract to reach levels that are too high for fish and other organisms which can only live, thrive, and reproduce in waters of lower specific conductance. It was the opinion of Barry Sulkin, an environmental scientist, that the "freshwater community" would be adversely impacted by the salts in the effluent. Although the freshwater area of the wetland tract is not dominated by open water ponds, creeks, and streams,26 the evidence shows that it contains sloughs, creeks, and other surface water flow. No evidence was presented about the biological community associated with the sloughs, creeks, and other waters in the wetland tract, other than general statements about the existing plants and the trees that are being planted. Petitioners did not prove that granting the exemption would cause significant adverse impact to the biological community in the freshwater area of the wetland tract, but it was IP's burden to affirmatively demonstrate the opposite. Because IP did not adequately address the impact of increased specific conductance levels on fish and other organisms in the freshwater area of the wetland tract, IP did not provide reasonable assurance that the proposed discharge would be assimilated so as not to cause significant adverse impact on the biological community within the wetland tract. Tee and Wicker Lakes When the Department issued the proposed exemption order, it did not have sufficient data and analyses regarding Tee and Wicker Lakes to determine with reasonable confidence that these waterbodies would not be adversely impacted by the proposed discharge. A transparency study of the lakes, which IP introduced as an exhibit at the final hearing, had not previously been reviewed by Department staff. Dr. Livingston is still developing data and analyses for the lakes to use in the NSAI analysis. The proposed NSAI monitoring plan states that one of its objectives is to determine the "ecological state" of the tidal ponds, including whether the ponds "could comprise an important nursery area for estuarine populations." In addition, the monitoring is to determine "the normal distributions of salinity, temperature, color, and dissolved oxygen" in the tidal ponds. These are data that must be known before a determination is possible that the discharge would not have a significant adverse impact on the biological community associated with the lakes. Petitioners did not prove that granting the exemption would cause significant adverse impact to the biological community of Tee and Wicker Lakes, but it was IP's burden to affirmatively demonstrate the opposite. Because insufficient data exists regarding baseline conditions in Tee and Wicker Lakes, IP did not provide reasonable assurance that the proposed discharge would not cause significant adverse impact on the biological community within the wetland tract. 2. Public Interest and Public Health Florida Administrative Code Rule 62- 660.300(1)(a)2. requires the applicant to demonstrate that "granting the exemption is in the public interest and will not adversely affect public health or the cost of public health or other related programs." Public Interest Petitioners made much of a statement by Mr. Evans that the public interest consideration in this permit review was “IP’s interest”. Petitioners claimed that this statement was an admission by the Department that it gave no consideration to the public interest. However, in context, Mr. Evan's statement was not such an admission. Moreover, Florida Administrative Code Rule 62-302.300(6) expressly provides that the public interest is not confined to activities conducted solely for public benefits, but can also include private activities conducted for private purposes. The proposed exemption order does not directly address the public interest criterion, but it notes that "existing impacted wetlands will be restored." In IP's application for the exemption, it states that the exemption would "contribute to our knowledge of wetlands in general and to the refinement of performance guidelines for the application of pulp mill wastewater to wetlands." Petitioners dispute that the wetland tract is being restored. The evidence shows that some restoration would be accomplished. The natural features and hydrology of the tract have been substantially altered by agriculture, silviculture, clearing for pasture, ditching, and draining. The volume of flow in the discharge would offset the artificial drainage that occurred. A mixture of hardwood tree species would be planted, which would restore more of the diversity found in a natural forested wetland. However, an aspect of the project that could substantially detract from the goal of restoration is the transformation of the freshwater wetlands to an unnatural salty condition. Dr. Nutter said that the salt content of the mill's effluent was equivalent to Gatorade, but for many freshwater organisms, that is too salty. Another public benefit of the exemption that was discussed at the final hearing is that it would allow IP to relocate its discharge from Elevenmile Creek and thus end its adverse impacts to the Creek. That public benefit is not given much weight because IP has not shown that its adverse impacts to Elevenmile Creek cannot be eliminated or substantially reduced by decreasing its production of paper products. The evidence shows only that IP has attempted to solve its pollution problems through environmental engineering.27 A sufficient public interest showing for the purpose of obtaining the experimental use of wetlands exemption should not be a rigorous challenge if all the other exemption criteria are met, because that means the proposed wetland discharge was shown to have no harmful consequences. The public interest showing in this proceeding was insufficient, however, because the other exemption criteria were not met and there is a reasonable potential for harmful consequences. Public Health Petitioners raised the issue of the presence of Klebsiella bacteria, which can be a public health problem when they occur at high levels. The more detection of Klebsiella, however, does not constitute a public health concern. Petitioners did not show that Klebsiella bacteria exist in the mill's effluent at levels that exceed applicable water quality standards. Petitioners also did not present competent evidence about the likely fate of Klebsiella bacteria in the proposed effluent distribution system. Dr. Lane's statement that Klebsiella bacteria might be a problem is not sufficient to rebut IP's prima facie showing that the proposed permit will not cause or contribute to a violation of water quality standards applicable to pathogenic bacteria. Petitioners also point to past incidents of high total coliform concentrations in Elevenmile Creek in support of their contention that the proposed exemption poses a risk to public health. However, these past incidents in Elevenmile Creek are not sufficient to prove that fecal coliform in the effluent discharged to the wetland tract will endanger the public health. IP proposes to restrict access to the wetland distribution system. Furthermore, the fate of bacteria in the wetlands is much different than in the Creek. The more persuasive evidence is that the wetland tract would destroy the bacteria by solar radiation and other mechanisms so that bacteria concentrations in waters accessible by the public would not be at levels which pose a threat to public health. Protection of Potable Water Supplies and Human Health Florida Administrative Code Rule 62- 660.300(1)(a)5. requires the applicant for the exemption to demonstrate that "the presently specified criteria are unnecessary" to protect potable water supplies and human health, which presupposes that the applicant has applied for an exemption from water quality criteria applicable to human health. IP has not requested such an exemption and, therefore, this particular criterion appears to be inapplicable. Even if it were applicable, the evidence does not show that the effluent would cause a problem for potable water supplies or human health. 4. Contiguous Waters Florida Administrative Code Rule 62- 660.300(1)(a)6. requires a showing that "the exemption will not interfere with the designated uses of contiguous waters." Contiguous waters, for the purpose of this criterion, would be Elevenmile Creek, Perdido Bay, and the Perdido River. Petitioners argue that Tee and Wicker Lakes should be considered contiguous waters for the purpose of this criterion of the exemption rule. However, Tee and Wicker Lakes are within the exempted wetland tract so they are not contiguous waters. Petitioners contend that IP failed to account for the buildup of detritus in the wetlands and its eventual export to Perdido Bay. Their contention is based primarily on the opinion of Dr. Kevin White, a civil engineer, that treatment wetlands must be scraped or burned to remove plant buildup. However, Dr. Nutter explained that periodic removal of plant material is needed for the relatively small "constructed wetland" treatment systems that Dr. White is familiar with, but should not be needed in the 1,464-acre wetland tract. Nevertheless, because IP did not provide reasonable assurances that the proposed permit and related authorizations would not significantly degrade the Perdido River OFW, IP failed to meet this particular exemption criterion regarding interference with contiguous waters. 5. Scientifically Valid Experimental Controls Florida Administrative Code Rule 62- 660.300(1)(a)6. requires a showing that "scientifically valid environmental controls are provided . . . to monitor the long-term effects and recycling efficiency." Petitioners' argument about this particular criterion was largely misplaced. The term "environmental controls" modifies the term "monitor" and connotes only that the experiment would be monitored in a manner that will generate reliable information about long-term effects and performance. For monitoring purposes, IP's proposed NSAI protocol is an innovative and comprehensive plan that complies with this exemption criterion. Petitioners' objections to the lack of sufficient information about Tee and Wicker Lakes is more appropriately an attack on the sufficiency of IP's showing that its discharge would not cause a significant adverse impact on the biological community within the wetland tract. That issue was discussed above. 6. Duration of the Exemption Petitioners argue that the exemption can not exceed five years in duration, but the time schedules established by the proposed Consent Order and proposed permit would allow the exemption to be in effect for nine years. The Department's exemption order states that the five years does not begin to run until IP begins to discharge effluent at D-003 into the wetland tract. The possibility that IP might seek to renew the exemption after five years does not make the exemption something other than a five-year exemption. The Department's action on the request to renew the exemption would be subject to public review and challenge by persons whose substantial interests are affected. The Waiver The proposed waiver order would excuse IP from compliance with the criteria in Florida Administrative Code Rule 62-660.300(1)(a)3. and 4., which require that public access and recreation be restricted in the area covered by the exemption for experimental use of wetlands. Without the waiver, the public would have to be excluded from Tee and Wicker Lakes. Section 120.542, Florida Statutes, requires a showing by the person seeking the waiver that the purpose of the underlying statute will be achieved by other means and the application of a rule would create a substantial hardship or would violate principles of fairness. Petitioners contend that IP failed to demonstrate substantial hardship. However, Petitioners do not want public access to Tee and Wicker Lakes restricted. The sole reason for their objection to the proposed waiver is apparently to thwart the issuance of the exemption. Section 120.542, Florida Statutes, defines "substantial hardship" as a demonstrated economic, technological, legal, or other type of hardship to the person requesting the waiver. In the proposed waiver order, the Department identifies IP's hardship as the possibility that denial of the waiver could result in denial of IP's NPDES permit and closure of the mill. The proposed waiver order then describes the number of jobs and other economic benefits of the mill that would be lost if the mill were closed. As discussed in the Conclusions of Law below, the Department's interpretation of Section 120.542, Florida Statutes, to accept a demonstration of hardship that is associated with denial of the waiver is mistaken. The statute requires that the hardship arise from the application of the rule. In this case, IP must demonstrate that it would suffer substantial hardship if it were required to restrict public access and recreation on Tee and Wicker Lakes. Petitioners claimed that IP has no authority to restrict the public from gaining access to Tee and Wicker Lakes because those are public waterbodies which the public has a right to enter and use. A substantial legal hardship for IP in complying with the exemption rule, therefore, is that compliance is impossible. The Consent Order 1. Compliance Schedule Subsections 403.088(2)(d) and (e), Florida Statutes, provide that no permit shall be issued unless a reasonable schedule for constructing, installing, or placing into operation of an approved pollution abatement facility or alternative waste disposal system is in place. Petitioners claim the time schedules for compliance are not reasonable. Petitioners presented no competent evidence, however, that the WWTP upgrades, pipeline construction, and other activities required by the proposed permit can be accomplished in a shorter period of time. One recurring theme in the Petitioners' case was that the adverse impacts associated with the continued discharge to Elevenmile Creek should not be allowed to continue, even for an interim period associated with construction of the WWTP upgrades and effluent pipeline. However, Petitioners also advocated the relocation of the discharge to the Escambia River, or to a "constructed wetlands." Both of these alternatives would have required a transition period during which the discharge to Elevenmile Creek would likely have continued. Furthermore, the Consent Order imposes interim limits on the discharge to Elevenmile Creek that would apply immediately upon issuance of the proposed permit. Although altered by the mill's effluent discharge, Elevenmile Creek is now a relatively stable biological system. The proposed permit would effectuate some improvement in the creek and Perdido Bay even during the construction phase. 2. Contingency Plan The proposed Consent Order includes a contingency plan in the event that the NSAI monitoring analysis shows adverse impacts to the biological community within the wetland tract. The plan provides for alternative responses including relocating all or part of the wetland discharge to Elevenmile Creek. Petitioners object to the plan, primarily because they contend it is vague. The provisions in the contingency plan for relocating all or part of the discharge from the wetland tract to Elevenmile Creek, appear to reflect a presumption that the negatives associated with continued discharge to the wetlands would outweigh the negatives associated with returning the discharge to Elevenmile Creek. However, it is not difficult to imagine scenarios where the harm to the biological community of the wetland tract is small in relationship to the harm to the biological community that might have reestablished itself in Elevenmile Creek. Because the selection of an alternative under the contingency plan requires the consideration of data and analyses associated with future events, it is impossible to know at this time whether future action taken by the Department and IP pursuant to the contingency plan would be reasonable. If the contingency plan is intended by the Department and IP to authorize future action when circumstances described in the plan are present, then the plan is too vague. On the other hand, there is adequate detail in the plan if the purpose of the plan is merely to establish a framework for future decision-making that would be subject to permit modification, public review and challenge. Clarification is needed. 2. Penalties Petitioners complained that the stipulated of $500 per day for violations of the proposed Consent Order is too small to provide a deterrent to a company of the size of IP. Petitioners are correct, but did not present evidence to show what size penalty would be appropriate.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Florida Department of Environmental Protection enter a final order: Denying proposed revised NPDES Permit Number FL0002526- 001/001-IW1S; Disapproving revised Consent Order Number 04-1202; Denying IP's petition for authorization for the experimental use of wetlands; and Denying IP's petition for waiver. DONE AND ENTERED this 11th day of May, 2007, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 11th day of May, 2007.

Florida Laws (5) 120.542120.569120.57403.088403.0885
# 2
KATHRYN HAUGHNEY vs DEPARTMENT OF ENVIRONMENTAL REGULATION, 90-007215 (1990)
Division of Administrative Hearings, Florida Filed:Ormond Beach, Florida Nov. 14, 1990 Number: 90-007215 Latest Update: Apr. 25, 1991

The Issue Whether or not Petitioner is entitled to a dredge and fill permit to construct a dock and seawall by provision of reasonable assurances that the project is in the public interest.

Findings Of Fact On May 8, 1989, the Petitioner, Kathryn Haughney, applied to DER for a permit to construct a dock and seawall on the shore of the Halifax River in Volusia County. The portion of the Haughney property where the dock and seawall would be constructed is separated from the Haughney home by John Anderson Drive, which parallels the river's edge and is separated from the river by a ribbon of undeveloped property at that location and to the south. A house is located at water's edge on the lot to the north of the proposed construction site. The Haughney home itself is set well back from John Anderson drive on the side of the street away from the river. The Halifax River is classified as a Class III water body under DER rules. The particular part of the Halifax River where the Haughney property is located and where the dock and seawall are proposed is also within the Tomoka Marsh Aquatic Preserve, which is an Outstanding Florida Water under DER rules. The dock as proposed by Petitioner will be 320 square feet. DER denied the permit application on July 19, 1990, but in so doing did not deny the application on the basis of the proposed dock, which, because of its dimensions, is exempt from DER permitting requirements. The seawall as proposed is to be 137 feet long. Petitioner applied to extend it 16 feet out into waters of the state at the northern end, gradually increasing to 34 feet into waters of the state at the south end. Additionally, 5 feet of riprap would also extend out into waters of the state along the seawall's entire length. The waters of the state that would be filled by the proposed seawall contain lush wetland vegetation that provides habitat for a number of macroinvertebrate species which are part of the food chain feeding fish and wading birds such as egrets and herons. Fiddler crabs and colonies of mussels have been observed on the site. The area to be filled provides a valuable habitat for fish and wildlife. There was no mitigation offered by Petitioner to make up for the loss of habitat to be occasioned by the proposed construction. Although Petitioner asserted DER had named no "endangered species" and that the Environmental Protection Administration had not designated this area as "endangered," those federal concerns were not at issue. If such federally designated species or location designation existed in the locale, it might militate against granting this application for permit, but in the negative, it is irrelevant. A vertical seawall exists immediately north of Petitioner's shoreline. The shoreline to the south remains undeveloped. (See Finding of Fact 2). Construction of seawalls, especially those that extend out from the existing shoreline, typically causes erosion on adjacent shorelines, and additional seawalls exaggerate wave energy and can have a cumulative erosive effect. The foregoing fact is found in reliance upon the testimony of Don Medellin, an Environmental Specialist II for DER, and Barbara Bess, an Environmental Manager for DER, both accepted as experts in environmental aspects of dredge and fill permits. The assertion that actual erosion on the property to the south has already occurred was contained in a letter from Petitioner's southern neighbor (DER Exhibit 6). Petitioner's representatives objected to consideration of this exhibit as "hearsay." They are correct and current erosion to the south is not found as a fact. Nonetheless, actual erosion in a pocket on the north end of Petitioner's shoreline has been shown by the direct testimony of Emmett and Martha Haughney, who assert that their property is eroding due to the existing seawall and that Petitioner wants a permit for a seawall to alleviate this erosion. Their evidence is confirmed by the personal observations and testimony of Mr. Medellin and Ms. Bess. Further, upon their testimony, it is accepted that this minimal pocket of erosion is most likely due to the existing seawall to the north and that if the Petitioner builds a seawall to the specifications now set out in the permit application, there is potential for similar and perhaps cumulative erosion to the shoreline to the south of Petitioner's lot. Neither the city nor county involved has land use restrictions which would prohibit Petitioner's proposed seawall except that Volusia County advocates riprap requirements if this permit application were granted. In its Notice of Permit Denial, DER advised Petitioner as follows: The Department has determined that the follow- ing changes to the project may make the project permittable: The vertical seawall should be eliminated and replaced with coquina rock riprap revet- ment. The riprap should be located further landward and conform to the slope of the existing embankment. Backfilling on the north property line is acceptable provided the fill area does not extend more than 10 feet westward in the most eroded area. Accordingly, the riprap could extend to the adjacent seawall and gradually extend in a more landward direc- tion to prevent excessive elimination of the littoral zone vegetation. Whatever alternative the applicant elects to choose, the removal or elimination of littoral zone vegetation must be offset in the form of mitigation if the impacts can not be reduced any further. Finally, the agent should eliminate the use of generic drawings which must be continually revised. All drawings should reflect the existing and proposed conditions and the impacts associated with the project. Petitioner's contractor, Andy Harris, testified to other alternatives that could be used by Petitioner in constructing her seawall, but the evidence of Mr. Medellin and Ms. Bess is persuasive that the alternative measures proposed by Mr. Harris would not provide the reasonable assurances the law requires DER to obtain from Petitioner.

Recommendation Upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Regulation enter a Final Order affirming its July 19, 1990 Notice of Permit Denial. RECOMMENDED this 25th day of April, 1991, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 25th day of April, 1991. APPENDIX TO RECOMMENDED ORDER, CASE NO. 90-7215 The following constitute specific rulings pursuant to Section 120.59(2) F.S. upon the parties' respective proposed findings of fact (PFOF): Petitioner's letter to Hearing Officer (filed March 22, 1991) The first paragraph complains that a VCR was unavailable in the hearing room so that Petitioner's videotape could not be shown. Petitioner should have made arrangements for showing the tape and did not. Likewise, Petitioner never offered the tape in evidence (for viewing by the Hearing Officer afterwards in preparation of this Recommended Order). Therefore, it very properly was not considered. The next 3 paragraphs refer to the Casden letter (DER Exhibit 6), which is covered in FOF 8-9. The remaining paragraphs are rhetoric and legal argument upon which no ruling need to made under Section 120.59(2) F.S.; however, they are alluded to in the Conclusions of Law. Petitioner's letter to DER Counsel (filed March 25, 1991 by DER, suggesting it was Petitioner's proposed findings of fact) 1-3 For the reasons set out above, the Petitioner's videotape was not considered. The subject of erosion to the degree proved at the hearing is covered in the Recommended Order. 4-5, PS 1-3 Mere rhetoric and legal argument upon which no ruling need be made under Section 120.59(2) F.S.; covered in the Conclusions of Law to the degree appropriate. Respondent's PFOF: 1-11 Accepted as modified to reflect the greater weight of the credible and probative record evidence as a whole. That which is rejected is rejected as not proven or not persuasive. Unnecessary or irrelevant material has likewise been excluded. COPIES FURNISHED: Douglas MacLaughlin Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Kathryn Haughney 2301 John Anderson Drive Ormond Beach, FL 32074 Emmett and Martha Haughney 2301 John Anderson Drive Ormond Beach, FL 32074 Carol Browner, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400

Florida Laws (2) 120.57403.813
# 4
THE CEPCOT CORPORATION AND CLEARWATER TRAIN STATION, INC. vs CITY OF CLEARWATER PLANNING DEPARTMENT, 03-002585 (2003)
Division of Administrative Hearings, Florida Filed:Clearwater, Florida Jul. 16, 2003 Number: 03-002585 Latest Update: Feb. 16, 2005

The Issue The issue on appeal is whether, pursuant to Clearwater Code of Ordinances Section 4-505, to sustain or reverse, with or without conditions, the decision of the Community Development Board on June 20, 2003, denying Cepcot Corporation's application to build a convenience store with two islands for pumping gas.

Findings Of Fact Petitioner The Cepcot Corporation (Cepcot) owns real property located at 657 Court Street in the downtown zoning district of the City of Clearwater (Property). On December 17, 2002, Cepcot filed a Flexible Development Application for a comprehensive infill redevelopment project (Application) on the Property. At the time of the proposal, the Property, which comprises 0.95 acres, was developed with a restaurant in a building that was the former Clearwater train station, a thrift store, and a park. The Application proposes the demolition of these improvements and their replacement with a 3200 square-foot convenience store and two gas pump islands. The Property fronts Chestnut Street to the south, East Avenue to the east, and Court Street to the north. The surrounding area is developed with office uses to the west and south, a privately owned utility plant to the north, and warehouse uses to the east. Upon the completion of the Memorial Causeway bridge, which is presently under construction, traffic to the beach will use Court Street and traffic from the beach will use Chestnut Street. In response to questions and suggestions from Respondent's staff, Cepcot revised the proposed site plan several times. The Application is presently complete. Respondent's Planning Department prepared a Staff Report, which finds that the proposed project does not meet certain requirements and recommends denial of the Application on several grounds. On June 17, 2003, Respondent's Community Development Board (CDB) considered the Application. CDB denied the Application and issued a development order explaining the reasons for denial as follows: The proposal is inconsistent with the adopted Community Development Code, the Comprehensive Plan, 1995 Clearwater Downtown Redevelopment Plan, and the Downtown Design Guidelines. The proposed automobile service station is not a permitted use within the downtown district. Approval of the proposed use may encourage other like uses and may be detrimental to downtown redevelopment. The proposal does not comply with the Flexible Development criteria as a comprehensive infill redevelopment project per Section 2-803. The proposal is not in compliance with the other standards in the Code including the general applicability criteria for Section 3-913. Most of the reasons cited for denial involve Respondent's Community Development Code (CDC), which is the land development regulations. The Property is in the Downtown District. CDC Section 2-901 states: "The intent and purpose of the Downtown District is to establish a mixed use downtown where citizens can work, live, and shop in a place which is the economic, governmental, entertainment and cultural focal point of a liveable city." CDC Section 2-902 sets forth the permitted uses within the Downtown District, and CDC Chart 2-100 lists permitted uses by zoning district. The proposed uses are not among the permitted uses for the Downtown District (or the Tourist District, to which portions of the record refer). CDC Section 2-903.C sets forth the following ten criteria to be applied in determining if the proposed use qualifies as a Comprehensive Infill Redevelopment Project (CIRP) that may qualify an otherwise non-permitted use: The development or redevelopment of the parcel proposed for development is otherwise impractical without deviations from the use, intensity and development standards; The development of the parcel proposed for development as a Comprehensive Infill Redevelopment Project will not reduce the fair market value of abutting properties; The uses within the comprehensive infill redevelopment project are otherwise permitted in the City of Clearwater; The uses or mix of uses within the comprehensive infill redevelopment project are compatible with adjacent land uses; Suitable sites for development or redevelopment of the uses or mix of uses within the comprehensive infill redevelopment project are not otherwise available in the City of Clearwater; The development of the parcel proposed for development as an comprehensive infill redevelopment project will upgrade the immediate vicinity of the parcel proposed for development; The design of the proposed comprehensive infill redevelopment project creates a form and function which enhances the community character of the immediate vicinity of the parcel proposed for development and the City of Clearwater as a whole; Flexibility in regard to lot width, required setbacks, height and off-street parking are justified by the benefits to community character and the immediate vicinity of the parcel proposed for development and the City of Clearwater as a whole; Adequate off-street parking in the immediate vicinity according to the shared parking formula in Division 14 of Article 3 will be available to avoid on-street parking in the immediate vicinity of the parcel proposed for development; The design of all buildings complies with the Downtown District design guidelines in Division 5 of Article 3. CDC Section 3-913.A sets forth the General Applicability criteria. CDC Section 3-913.A.1 states: "The proposed development of the land will be in harmony with the scale, bulk, coverage, density, and character of adjacent properties in which it is located." CDC Section 3-913.A.5 states: The proposed development is consistent with the community character of the immediate vicinity of the parcel proposed for development."

Florida Laws (1) 120.569
# 5
CLEARWATER BAY MARINE WAYS vs CITY OF CLEARWATER AND ANTONIOS MARKOPOULOS, 93-007070 (1993)
Division of Administrative Hearings, Florida Filed:Clearwater, Florida Dec. 13, 1993 Number: 93-007070 Latest Update: Mar. 28, 1994

The Issue The issue in this case is whether the evidence sustains the decision of the City of Clearwater Development Code Adjustment Board (the Board) to deny the application of the Appellant, Clearwater Bay Marine Ways, Inc., for a 62-space parking requirement variance (200 spaces instead of the 262 required under the Code) for its property located at 900 North Osceola Avenue, Clearwater, Florida. (The variance is required as a result of the Appellant's desire to use a part of the property as a cruise ship docking facility.)

Findings Of Fact On or about October 25, 1993, the Appellant, Clearwater Bay Marine Ways, Inc., applied to the City of Clearwater Development Code Adjustment Board (the Board) for an 81-space parking requirement variance (128 spaces instead of the 209 required under the Code) for its property located at 900 North Osceola Avenue, Clearwater, Florida. After filing the application, the site plan was modified, and the variance application was modified to request a 62-space variance (200 spaces instead of the 262 required under the Code). The variance is required as a result of the Appellant's plan to have Adventure Seaways Corporation use a part of the property for use as a docking facility for its 600-passenger cruise ship, the Majestic Empress. The City of Clearwater Development Code (the Code) has no parking space requirements specifically designed for cruise ship operations. To establish the parking space requirements, it was decided to utilize Section 42.34(6)(d)2.c. of the Code, which addresses certain "retail sales and service uses," and states: Theaters, indoor and outdoor recreation centers, swimming pools, skating rinks and other public or private recreation and amusement facilities: One parking space per three customers or patrons computed on the basis of maximum servicing capacity at any one time, as determined by the requirements of the city, plus one additional space for every two persons employed on the premises at peak period of use. Specific provisions over and above the standard may be required for uses such as movie theaters involving successive changes of patrons with a corresponding overlap in parking required. Under that provision, it was calculated that 200 spaces would be needed for peak capacity for the 600-passenger cruise ship. An additional 62 parking spaces are needed for other uses proposed in the site plan (including boat slips, a dive charter operation, a sail charter operation, a 2,800 square foot parts and service business and three work bays), for a total of 262 parking spaces for the overall site plan. The evidence was that no adjustments to the calculation under the "one space per three customers or patrons" formula were "determined by the requirements of the city," and that no additional spaces were required for "persons employed on the premises." (There was some evidence that the Adventure Seaways employees will park off-site.) Nor was there any evidence that there were any "[s]pecific provisions over and above the standard required for . . . successive changes of patrons with a corresponding overlap in parking required." The Adventure Seaways Corporation plans two excursions of the Majestic Empress a day, one during the day and one in the evening. It is expected that the ship would sail at full capacity only approximately one day a week, on Saturday. At peak capacity, it is expected that 30 percent of the passengers will arrive at the docking facility by tour bus. During the day cruise, the buses would leave the facility and return at the end of the cruise to drop off passengers for the evening cruise and pick up off-loading day cruise passengers. They would not remain at the facility during the times other cruise ship passengers would have their cars parked at the facility. Using only the "one space per three customers or patrons" formula under Section 42.34(6)(d)2.c. of the Code, the 70 percent of the total complement of passengers, who are expected to arrive by personal vehicle on peak days, would require only 140 parking spaces (420 passengers divided by three per parking space), well below the 200 spaces allocated to the cruise ship operation under Clearwater Bay Marine Ways site plan. Since Adventure Seaways has not been able to use the Majestic Empress at the Clearwater Bay Marine Ways facility without the parking space variance, it has transferred a smaller cruise ship, the Crown Empress, from its docking facility at Johns Pass on Treasure Island in the interim. The Crown Empress's capacity is only 400 passengers, and no parking space variance is required to use it at the Clearwater Bay Marine Ways facility. Meanwhile, Adventure Seaways has received temporary permission to utilize the Majestic Empress at the Johns Pass facility on the condition that it make greater than normal use of tour buses to transport passengers to and from the Johns Pass docking facility. Adventure Seaways purchased the Majestic Empress after being encouraged by City officials about the prospects of being able to utilize the Clearwater Bay Marine Ways facility. After purchasing the vessel, it had the vessel reconfigured to reduce its draft to accommodate the shallow waters it would have to navigate getting to and from the facility. Adventure Seaways also closed in the top deck of the vessel to meet Code requirements for noise control. Neither the special shallow draft configuration nor the noise control measures are required for utilization of the Johns Pass facility. Part of the encouragement by City officials about the prospects of Adventure Seaways being able to utilize the Clearwater Bay Marine Ways facility included assurances that the City would help Adventure Seaways gain access to additional parking, or develop or acquire additional parking, in the vicinity, if needed. Another option would be to utilize off-site parking and transport passengers to and from the Clearwater Bay Marine Ways facility by bus.

# 6
STANISLAW BUDZINSKI AND KAZIMIERA BUDZINSKI vs CITY OF CLEARWATER AND ANTONIOS MARKOPOULOS, 97-001109 (1997)
Division of Administrative Hearings, Florida Filed:Clearwater, Florida Mar. 10, 1997 Number: 97-001109 Latest Update: Jun. 09, 1997

Findings Of Fact Lior Hason is the owner of Britt's Cafe, a restaurant which occupies property owned by the Petitioner's Stanislaw and Kasimiera Budzinski. On or about December 19, 1995, Harry S. Cline, an attorney for Mr. Hason and the Budzinskis, filed an application for a variance from the City of Clearwater's Development Code, for the purpose of eliminating three required parking spaces from the front of the subject property for the construction of an outdoor cafe at 201 South Gulfview Boulevard. The Code requires one parking space per 200 square feet of gross floor area, and a variance was required to remove three existing parking spaces from the unit's parking space inventory. The matter was brought before the City's Development Code Adjustment Board at its January 11, 1996 meeting. Mr. Cline appeared at the meeting on behalf of the applicant and presented the project. No one else was present to speak in support of or in opposition to the request. However, four letters in opposition from neighboring business owners were submitted. Notwithstanding these objections, the Board determined that the applicant had substantially met all standards for approval listed in the City's Land Development Code; and upon vote of the Board, the application was approved, subject to certain conditions, by a three to two majority. Mr. Hason entered into discussions with City officials to determine what was necessary. Official City reaction was initially favorable. Mr. Hason was advised of the requirements for the project and had plans drawn which called for a deck with a 35 to 36 inch railing with landscaping around it, and with posts and lights. When the plans were submitted to the City officials, the only change suggested was to raise the railing height to 45 inches, which was done, after which the City approved the plans and the permit was granted. The deck was then constructed exactly according to the approved plans. At some time during 1996, Mr. Hason discussed with some City employees putting an awning over the deck. During these discussions, the City employees sent Mr. Hason a copy of Section 41.221(1)(c), Clearwater City Code, which provides for awnings to be removable. Mr. Hason considered the sending of this Code provision to be tantamount to a favorable reply to his inquiry, and, based on that, he finalized his plans for the installation of a removable awning. The proposed awning is designed in such a fashion as to be extendible and retractable on a frame, capable of easily being pulled up against the front of the building like a drapery. With a minimum of further effort, consisting of the removal a several bolts, the entire awning construction can be removed from the frame. Mr. Hason submitted his application for the variance to install the awning on February 2, 1997. In the interim, the City employees with whom Mr. Hason discussed the project changed their position from favoring the project to opposing it. He was ultimately advised in December 1996 or January 1997 that the awning could not be permitted because an awning could not be approved over a deck for which a permit should not have been issued and for which the issuance was a mistake. Though the Board had not yet voted on the application, no information was given to Mr. Hason as to what he could do to make the project approvable. His application, on February 2, 1997, was submitted because, Hason claims, he had been told, by someone not further identified, that applying for a variance for the awning would make everything right. The Variance Staff Report submitted to the Board by the appropriate City employees acknowledged that the frame over which Mr. Hason proposed to put the awning does not meet code because it was constructed within a required setback area from South Gulfview Boulevard, but since the frame was built pursuant to a City-issued permit, consistent with City policy, the City accepted its existence. In its final recommendation to the Board, the staff concluded that notwithstanding the encroachment into the setback area, the project "appears to comply with all standards for approval, provided attention is given to the external appearance of the cafe:" The staff then went on to recommend approval of the project subject to certain conditions, all of which, Mr. Hason accepts and agrees to. Nonetheless, the Board denied the permit by a vote of four to one. Mr. Hason contends that the Board vote was an attempt by the Board to get back at him because of what it perceived as his failure to comply with the conditions placed upon the issuance of the first permit and his alleged misrepresentation of the scope of his project at the time. Mr. Hason, however, categorically denies he has done anything contrary to the dictates of the City. He went back to City officials many times during the construction of the deck to make sure the project was built as required. The majority of the Board members believe, however, that the deck as constructed, goes far beyond the limited structure approved by the granting of the parking space variance in January 1996. This animosity toward the project can be seen from a review of the audio record of the February 13, 1997, Board meeting where, during a colloquy between a Board member and Mr. Hason, it appeared the member was somewhat put out by the entire situation. His analysis indicates a less than complete recollection of the matter, however. Whereas one of the conditions to the issuance of the initial permit was that the area of the outdoor cafe should not be greater than 25 percent of the indoor area of the restaurant, this member pointed out that the 69 outdoor seats were far in excess of 25 percent of the 115 or so indoor seats. This constituted a confusion of seating as opposed to area. No evidence was presented concerning whether Mr. Hason had violated the area constraint. In the main, however, while it appeared that a majority of the Board members were unhappy about the way the project developed, and expressed the opinion that the project did not conform to what they had intended to approve, there was no indication any member s vote was motivated by anything other than a sincere belief in the correctness of his position. There was no indication of any inappropriate or vindictive action by anyone on the Board or its staff. Stephen Sarnoff, a central permitting specialist with the City reviewed the plans for the initial construction and for the current application. As he recalls, the plans for the initial deck construction did not show any support beams, fans, overhead structure or latticework fencing, and the deck, as built, does not conform to the plans as submitted. City Code requirements call for a railing of from 30 to 42 inches high. The current railing of 45 inches does not conform to that standard, and Mr. Sarnoff is not aware of any request from the City that the railing be raised to that height, as Mr. Hason claims. By the same token, while there is no requirement in the ordinance that a deck be of a certain height, anything higher than 12 inches is considered a structure and a waiver is required. This deck was approved for 12 inches. A certificate of occupancy is usually issued for a deck, but in the instant case, such a certificate has not been issued because the deck, as built, is not in compliance with the 1996 approval. If it is brought into compliance, it will be approved. Sarnoff is aware of and familiar with other outdoor restaurant decks built at various locations in the Clearwater area, as indicated by Mr. Hason. Some are not within the CR-28 zone and do not come under the same standards as are applicable here. Others, which must conform to the instant requirements appear to have movable awnings which are acceptable. Still others are in a different zoning district with different set-back requirements, and some were initially denied, but were subsequently approved when they were brought into compliance with the requirements. John Richter, a senior planner for the City, was the individual who prepared the staff report on the instant project and initially recommended approval, contingent upon changes to the external appearance of the facility. He made suggestions and has discussed the project with Hason on his several visits to the property. He did discuss an awning with Hason at some point, but their discussions did not deal with its mobility. All in all, Mr. Richter concluded that the project appears to meet the standard for approval, provided attention is given to the external appearance of the cafe. David S. Shuford, the City's central permitting director and development code administrator indicated that the variance required for the awning, which was an integral part of the structure already built, was not automatically granted with the granting of the permit for the deck structure. Section 42.221, Clearwater City Code, was adopted to promote a more festival atmosphere in some of the outdoor tourist areas. The intent of subsection (l)(c) of that provision was to require the use of moveable items and to design structures that would meet wind requirements and not interfere with pedestrian traffic. The term "moveable" means what it says, and in Shuford's opinion, from the plans he saw, the proposed awning would not be easily moveable on a daily basis. The Clearwater City Code establishes the area in question as one where, once guidelines are developed, they will be adopted and be complied with. Mr. Shuford opines that the current deck, in the rafter area, goes beyond what was proposed at the time the project was submitted for the parking variance and was approved. This is what appears to be the source of the difficulty the Board members have with it. However, if designed to comply with the guidelines, this awning could be approved. He would agree with the conditions outlined in the staff recommendation so far as they relate to painting and architectural matters.

Florida Laws (2) 120.57120.69
# 7
CLIFFORD O. HUNTER vs DEPARTMENT OF ENVIRONMENTAL PROTECTION, 93-005924 (1993)
Division of Administrative Hearings, Florida Filed:Live Oak, Florida Oct. 14, 1993 Number: 93-005924 Latest Update: Jun. 08, 1994

Findings Of Fact The Parties. The Petitioner, Clifford O. Hunter, is the owner of real property located at Dekle Beach, Taylor County, Florida. Mr. Hunter's property is located at lot 53, Front Street, Dekle Beach, within section 22, township 7 south, range 7 east, Taylor County. Respondent, the Florida Department of Environmental Protection (hereinafter referred to as the "Department"), is an agency of the State of Florida with responsibility for, among other things, dredge and fill permits involving Florida waters. Mr. Hunter lived in a home on his Dekle Beach property until a storm in March of 1993 destroyed the home. Mr. Hunter's Application for Permit. On or about June 2, 1993, Mr. Hunter applied for a wetland resource permit to rebuild his home, construct a bulkhead and fill 1750 square feet of salt marsh. The permit was designated No. 62-232123-2 by the Department. Mr. Hunter also sought approval for the construction of a dock. The dock, however, is exempt from the permitting requirements of Rule 17- 312.050(1)(d), Florida Administrative Code. On July 21, 1993, the Department issued a Notice of Permit Denial. The Notice of Permit Denial was received by Mr. Hunter. On August 13, 1993, Mr. Hunter filed a Request for Formal Administrative Hearing with the Department contesting the denial of his permit application. The Department's Jurisdiction Over the Proposed Project. The proposed project involves dredging and filling in the waters of the State of Florida. A wetland resource permit is, therefore, required. Wetland jurisdiction of the State of Florida extends to the eastern edge of an existing concrete slab on Mr. Hunter's property from a canal adjacent to Mr. Hunter's northern boundary. The canal connects with the waters of the Gulf of Mexico. The Gulf of Mexico surrounding Dekle Beach, except for an area extending 500 feet outward from the town limits of Dekle Beach, is within the Big Bend Seagrasses Aquatic Preserve. The preserve is an Outstanding Florida Water (hereinafter referred to as an "OFW"). The evidence presented by the Department to support findings of fact 9, 10 and 11 was uncontroverted by Mr. Hunter. Impact on Water Quality Standards. The weight of the evidence failed to prove that the Mr. Hunter has provided reasonable assurances that the proposed project will not lower the existing ambient water quality of waters of the State of Florida. The evidence presented by the Department concerning adverse impacts of the proposed project on water quality standards was uncontroverted by Mr. Hunter. Approval of Mr. Hunter's proposed project would allow the placing of fill in an intertidal area and the elimination of the portion of the intertidal area filled. Intertidal areas help maintain water quality by acting as a filter for water bodies. Mr. Hunter has obtained a variance from the Department of Health and Rehabilitative Services which will allow him to place a septic tank on his property if the permit is granted. The septic tank will leach pollutants. Those pollutants will include nutrients, viruses and bacteria. Because the soil around the septic tank is very saturated, filtering of the pollutants will be low. Pollutants will, therefore, leach into the waters of the State of Florida and adversely impact water quality standards of the canal adjacent to Mr. Hunter's property. Under such circumstances, Mr. Hunter has failed to demonstrate that the project will not lower existing ambient water quality of waters of the State of Florida. Public Interest Test. Mr. Hunter failed to present evidence to support a conclusion that the proposed project will not be adverse to the public interest. Rather, the unrebutted evidence presented by the Department supports a finding that Mr. Hunter's proposed project will not be in the public interest, especially when the cumulative impacts of the proposed project, discussed, infra, are considered. Possible adverse impacts to the public interest include the following: The septic tank which Mr. Hunter will place in the 1750 square feet of filled area will allow fecal coliform, viruses and pathogens to leach into the waters of the canal adjacent to Mr. Hunter's property. Anyone who enters the canal could be infected from bacteria and viruses leaching from the septic tank. The conservation of fish and wildlife would also be adversely affected by the adverse impact on water quality and by the elimination of intertidal area. Recreational value of the canal would be reduced because of the adverse impact on water quality. The proposed project is for a permanent structure. Cumulative Impact. There are a number of applications for permits similar to the application filed by Mr. Hunter which have been filed by property owners of Dekle Beach whose homes were also destroyed by the March 1993 storm. If Mr. Hunter's permit application is granted, the Department will have to also grant most, if not all, of the other similar permit applications. Approximately 20 to 30 other applications involve similar requests which will allow the placement of fill and the installation of septic tanks. The resulting fill and use of septic tanks will have a significant cumulative adverse impact on the waters of the State of Florida. The cumulative impact from leaching effluent from the septic tanks on the waters of the State could be substantial. In addition to the impact on the canal adjacent to Mr. Hunter's property, there will a cumulative negative impact on the ambient water quality of approximately 20 septic tanks on the canals and on the OFW. Errors in the Department's Notice of Permit Denial. The Notice of Permit Denial issued by the Department contained the following errors: An incorrect description of Mr. Hunter's lot number and section number; An incorrect statement that the amount of Mr. Hunter's proposed fill would eliminate 3,200 square feet of marsh; An incorrect statement that Mr. Hunter proposed to fill his lot for a distance of 64 feet waterward. The errors contained in the Notice of Permit Denial did not form any basis for the Department's denial of Mr. Hunter's application. The errors were typographical/word-processing errors. Several notices were being prepared at the same time as the Notice of Permit Denial pertaining to Mr. Hunter. The incorrect information contained in Mr. Hunter's Notice of Permit Denial was information which applied to the other notices. Other than the errors set out in finding of fact 23, the Notice of Permit Denial was accurate. Among other things, it was properly addressed to Mr. Hunter, it contained the project number assigned by the Department to Mr. Hunter's proposed project and it accurately reflected the Department's decision to deny Mr. Hunter's permit application. Mr. Hunter responded to the Notice of Permit Denial by requesting a formal administrative hearing to contest the Department's denial of his application. On December 20, 1993, Mr. Hunter received a letter from the Department which corrected the errors contained in the Notice of Permit Denial. The corrections were also contained in a Notice of Correction filed in this case by the Department on December 20, 1993. The Notice of Permit Denial was received by Mr. Hunter within 90 days after his application was filed. The corrections to the Notice of Permit Denial was received by Mr. Hunter more than 90 days after his application was filed.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a Final Order dismissing the petition in this case and denying the issuance of permit number 62-232123-2 to Clifford O. Hunter. DONE AND ENTERED this 26th day of April, 1994, in Tallahassee, Florida. LARRY J. SARTIN Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of April, 1994. APPENDIX The parties have submitted proposed findings of fact. It has been noted below which proposed findings of fact have been generally accepted and the paragraph number(s) in the Recommended Order where they have been accepted, if any. Those proposed findings of fact which have been rejected and the reason for their rejection have also been noted. Mr. Hunter's Proposed Findings of Fact Accepted in 1 and 3. Accepted in 2. Accepted in 4. Although Ernest Frey, Director of District Management, Northeast District Office of the Department, did ask Mr. Hunter whether he wanted to sell his property to the State, the evidence failed to prove why Mr. Frey asked this question, that Mr. Frey asked the question in his official capacity with the Department, or that Mr. Frey made the inquiry at the direction or on behalf of the Department or the State. More importantly, the evidence failed to prove that the Department denied the permit sought by Mr. Hunter because of any interest the State may have in purchasing Mr. Hunter's property. See 4. 6-8 No relevant. Not supported by the weight of the evidence. Accepted in 6, 23, 28 and 30. Not a proposed finding of fact. See 8. The "aerial photo, Petitioner's exhibit 6, does not show "No vegetation behind the slab, nearly to the Mean High Water Line . . . ." Respondent's exhibit 3 does, however, show vegetation as testified to by Department witnesses. 13-14 Not supported by the weight of the evidence. Not a proposed finding of fact. Generally correct. Mr. Hunter was not properly put on notice of "alternatives" by the Notice of Permit Denial, as corrected, issued by the Department. Summation: Mr. Hunter's Summation was considered argument and was considered in this case. The Department's Proposed Findings of Fact Accepted in 1 and 3. Accepted in 2. Accepted in 1 and 4-5. Accepted 6-7. Accepted in 8. 6-9 Hereby accepted. Accepted in 12. Accepted in 13. Accepted in 14. Accepted in 15. Accepted in 19. Accepted in 20. Accepted in 15. 17-18 Accepted in 15 and hereby accepted. Accepted in 15 and 20-21. Accepted in 10. Accepted in 22. Hereby accepted. Accepted in 22. Accepted in 12. Accepted in 15-16. Accepted in 17 and 21. 27-28 Accepted in 17. Accepted in 18. Accepted in 13. Accepted in 16. 32-33 The Notice of Permit Denial, as corrected, did not put Mr. Hunter on notice that the alternatives raised by the Department at the final hearing would be an issue in this case. Those alternatives should not, therefore, form any basis for the Department's final decision. Accepted in 24-25. Accepted in 23. Accepted in 25. Accepted in 24 and hereby accepted. Accepted in 26. COPIES FURNISHED: Clifford O. Hunter 1410 Ruby Street Live Oak, Florida 32060 Beth Gammie Assistant General Counsel Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32399-9730 Virginia B. Wetherell, Secretary Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Kenneth Plante, Esquire General Counsel Department of Environmental Protection Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400

Florida Laws (3) 120.57267.061373.414
# 8
FRED THOMAS vs. CITY OF CLEARWATER AND ANTONIOS MARKOPOULOS, 88-001191 (1988)
Division of Administrative Hearings, Florida Number: 88-001191 Latest Update: Jun. 06, 1988

Findings Of Fact Fred Thomas owns a home and lot on the beach in Clearwater at 730 Eldorado Avenue, Mandalay Subdivision, Block 2, Lot 8, now zoned RS-8 (single family residential). The Thomas house was built 30 years ago when front yard setbacks for the area were only 10 feet and there were no open space requirements. Now the front setback in the area is 25 feet, and Section 135.029(8) of the Clearwater Land Development Code now requires lots in RS-8 zones to have a minimum open space of 35 percent of the lot and 40 percent of the front yard. There are many properties in the area of the Thomas house that maintain pre- existing non- conformities to the current setback and open space requirements. The Thomas property, in addition to the pre-existing setback non-conformity, had only 26 percent open space overall and no open space at all (all concrete) in the front yard. In 1987, Thomas undertook renovations to his house. During construction, Thomas' concrete front yard deteriorated from additional cracking, and he decided to replace the concrete with brick pavers. He removed the concrete but then was required to get a building permit for this work. The building permit was not granted because the placement of brick pavers in the front yard violated the open space requirements. Thomas applied for a variance to replace the concrete with brick pavers and later modified the application to be allowed to have 29 percent lot coverage and 12 percent front yard coverage with open space. The modified application was denied by the DCAB after hearing on February 11, 1988, and Thomas took this appeal. Thomas also filed another variance application to be allowed to have 30 percent lot coverage and 16.8 percent front yard coverage with open space. This application was heard on March 10, 1988, and this time the DCAB granted the application. The only open space required under the granted variance not required under the denied variance application is a 10' by 10' square on the far left side of the front yard (facing the house). Thomas claims that this open space requirement prevents him from using a narrow concrete alley to the left of the house (and perhaps the concrete apron in the back of the house) for guest parking, leaving him with a two-car garage and the brick paved area directly in front of the garage that could accommodate two cars but would block the garage. Lack of guest parking would create a hardship of sorts on Thomas. There is no on-street parking in the area, and the Clearwater Police vigorously patrol and ticket violators in the area. The brick paved spaces in front of the garage could be inconvenient to the owners of the vehicles parked in the garage (probably the Thomases) and conceivably could block the cars in the garage temporarily under some circumstances. However, Thomas is incorrect in his presumption that guest parking in the alley and back of the house would be blocked by the 100 square feet of open space required under the granted variance but not under the denied variance application.

# 9
PENINSULAR FISHERIES, INC., AND DALIA DIAZ vs. JOHN H. LAND BUILDERS, INC., AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 81-000298 (1981)
Division of Administrative Hearings, Florida Number: 81-000298 Latest Update: Jun. 12, 1981

Findings Of Fact By application filed on September 9, 1980, Respondent/Applicant, John H. Land Builders, Inc., sought a permit from Respondent, Department of Environmental Regulation (DER), to conduct dredge and fill activities in an approximate one acre area located in the southeast corner of a proposed housing development in Section 10, Township 29 South, Range 19 East, in Hillsborough County, Florida. A copy of this permit application may be found as DER Composite Exhibit B. Specifically, Land sought to excavate 4,100 cubic yards of material (muck) and to backfill the area with 14,400 cubic yards of granular material from adjacent uplands to allow for development of a street and building lots in an unnamed wetland. A permit from DER is required because the project involves a wetland that is contiguous with a ditch that connects to the Palm River, all of which constitute waters of the State that are subject to dredge and fill permitting requirements. The plans have been reviewed by other state and local authorities in the Hillsborough County area, and no adverse comments have been received. After the installation is completed, the elevation of the land will be raised, and will permit five homesites to be built on the land as well as the construction of an access road to the property from an adjacent street. The installation in question is but a small part of a larger proposed housing development known as Timberlake Subdivision that will ultimately involve more than 300 homesites. However, no further dredge and fill activities under DER jurisdiction will be undertaken. The proposal of Respondent/Applicant was received by the Department and certain timely additional requests were made from the Department to the Applicant to provide information necessary to evaluate the request for permit. Applicant subsequently furnished the required information, and it may be found in DER Exhibit C. The Department performed a field inspection and review of the dredge and fill site, including the surrounding areas, to assess the impact of water quality caused by proposed dredging and filling activities in wetlands areas. It concluded that the Applicant had affirmatively provided reasonable assurance to the Department that the short-term and long-term effects of the activity would not result in violations of the water quality criteria, standards, requirements and provisions of Chapter 17-3, Florida Administrative Code. A copy of the permit application appraisal may be found in DER Exhibit A. On January 21, 1981, DER issued its Intent to Issue a dredge and fill/water quality certification with certain conditions therein, including the requirement that future development be dependent upon separate stormwater review by the Department (DER Exhibit D). On October 20, 1980, Applicant filed a Notice of Stormwater Discharge with the Department's Southwest District Office in Tampa (DER Composite Exhibits B & F). Thereafter, the Department conducted a field inspection and review of the proposed housing development and surrounding areas to determine whether the proposed stormwater discharge would have a significant impact on water quality. Based upon the results of that inspection, which concluded that the proposed discharge would not have a significant impact on the waters of this State, the Department issued Applicant a stormwater exemption on November 7, 1980. The project site is located in an unnamed wetlands area. It is weedy and has a dense cover of primrose willow (Ludwigia peruviana), willow (Salix caroliniana), cattail (Typha sp.), red maple (Ace rubrum) and is overgrown with grapes vines (Vitus rotendifolia). It lies just to the north of a series of fish farms owned by Petitioner, Penisular Fisheries, Inc. Other commercial industries and single family dwellings are found south of the proposed activities. To the west and northwest lie marshlands, two old borrow pits, and Interstate Highway 4. Water runoff from the dredge and fill area will flow to the storm drainage system in the proposed street, and from there to a designated retention pond. Because there will be minor contaminants in the runoff, the water will be retained for treatment for a period of five days, which exceeds the 100 hour retention period required by DER. After treatment, the runoff will flow into a well-defined county drainage ditch west of 58th Street, travel down the ditch which lies adjacent to the fish ponds, and then meander into the existing marshland. Water runoff from the remainder of the project (excluding the dredge and fill area) will drain into the two existing borrow pit lakes which lie close to Interstate Highway 4. The designated retention pond will be located west of the project and has a controlled spill-off elevation. It will provide sufficient treatment to and cleaning of the water to insure that no violation of water quality standards will occur. A stormwater system to be constructed by Applicant will actually reduce the volume of water runoff now occurring. Reasonable assurances have been given that the short-term and long-term effects of the proposed activity will not result in violations of the water quality criteria, standards, requirements and provisions of the Florida Administrative Code. Based upon Use location of the point of discharge of Land's proposed stormwater discharge, the volume and frequency of discharge for which the proposed facilities are designed, and the anticipated constituents of discharge, the proposal will not have a significant impact on the water quality of the waters of this State. Accordingly, the exemption from stormwater licensing requirements was properly issued by the Department. Water quality violations which were alleged to have existed in a ditch on property adjoining the properties of Land and Petitioners were the subject of a notice of violation issued to the owners of that property. However, no notice of violation was ever issued to Land. Further, the ditch is not a part of the installation proposed by Applicant for issuance of the dredge and fill permit. Petitioners' concern is that Applicant has not given reasonable assurance that water quality standards would not be violated by the stormwater discharge and that downstream waters might be contaminated by urban runoff from the project. In reaching that conclusion, Petitioners' expert relied on a review of certain materials submitted to him by Petitioner's counsel. He did not visit the project site, nor had he reviewed drainage plans or construction drawings for drainage improvements contemplated by the notice of stormwater discharge filed by Land.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent Department of Environmental Regulation grant the requested dredge and fill permit/water quality certification to Respondent/Applicant John H. Land Builders, Inc. It is further RECOMMENDED that the Respondent Department of Environmental Regulation enter a final order confirming the stormwater exemption issued by the Department to Respondent/Applicant on November 7, 1980. DONE and ENTERED this 27th day of April, 1981, in Tallahassee, Florida. DONALD R. ALEXANDER Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of April, 1981.

Florida Laws (1) 120.57