Findings Of Fact At all times pertinent to the allegations contained in Ms. Cheren's April 15, 1988 letter of denial of renewal, Petitioner, Earlen Braddy operated Earlen's ACLF home at 2840 47th Avenue South, St. Petersburg, Florida. Respondent, DHRS, is the state agency responsible for licensing ACLF's in Florida. Ms. Braddy has operated the ACLF in question at the current location for about four years during which time she has had as many as five residents at one time. Currently, and for the past year, she has had only three residents in the facility which she also occupies as her home. One current resident has been with her since she opened. On December 4 and 9, 1986, while Ms. Braddy was operating her ACLF in a licensed status, her facility was inspected by representatives of Respondent's Office of Licensure and Certification on its yearly survey. During the survey, the inspectors found several deficiencies, all of a Class III, (least serious) category, in such areas as Administration; Management and Staffing Standards, (6 deficiencies); Admission Criteria and Resident Standards, (3 deficiencies); Food Service, (12 deficiencies); Physical Plant, (5 deficiencies); Fire Safety, (1 deficiency); and Other Administrative Rule Requirements, (4 deficiencies). Though most deficiencies related to the failure to keep or provide the surveyors with the paperwork required to be kept by statute and the rules of the Department, some of the deficiencies related to resident care. These deficiencies were identified to Ms. Braddy in person by the inspectors at the time of discovery and again at the out-briefing. She was also advised as to how to correct them and where to secure assistance in doing so, if necessary. Nevertheless, and notwithstanding the uncorrected deficiencies identified in the December, 1986 survey and the March, 1987 follow-up, the Petitioner's license was renewed in April, 1987. Follow-up surveys were conducted in March, June, and October, 1987, at the next annual survey in 1988, and at its follow-ups. While some deficiencies originally identified were thereafter corrected, many were not. Another annual survey of the facility was conducted on February 16, 1988, prior to the issuance by the Department of the yearly renewal license. At this survey, again, numerous Class III deficiencies were identified including: Administrative, (5 deficiencies); Admission, (3 deficiencies); Food Service, (9 deficiencies); Physical Plant, (1 deficiency); Fire Safety, (3 deficiencies); and Other Administrative, (3 deficiencies). Many of these were carried over uncorrected from the previous year's survey, (December, 1986) and its follow- ups, and some were new. Some of the former remained uncorrected through the June, 1988 follow-up to the February, 1988 survey. In August, 1988, the Department filed three Administrative Complaints against the Petitioner seeking to impose monetary civil penalties against her. All three resulted in Final Orders being entered. In the last of the three, Petitioner was alleged to have committed five violations of the statutes and Departmental rules, all of which relate to Petitioner's alleged failure to "provide or make available for review documentation" in five certain areas. Petitioner and Respondent agree that these areas are those primarily involved in the uncorrected deficiencies outlined in the survey reports and upon which the Department relies to support denial of Petitioner's renewal. Petitioner readily agrees that the deficiencies cited by the Department both in the survey reports and in the Administrative Complaints existed at the time of identification and, in many cases, for some time thereafter. While Petitioner now claims all deficiencies have been corrected, her accountant, Mr. Schaub, indicates that at least one, that relating to the failure to document and keep on file scheduled leisure time, had not been accomplished previously and was not now being accomplished. As to the others, those requirements which were not being complied with at the time of the surveys are now being met. Some identified deficiencies were not actually defects. The documentation was being kept, but due to Petitioner's inability to keep up with it, was not made available to the surveyors. Mr. Schaub is convinced that Petitioner has a paperwork problem and needs help with it. She spends her time taking care of the residents without much help and does not keep up with the required paperwork. As he describes it, she is being "choked with red tape" due to the paperwork requirements imposed by the Department whose rules do not differentiate much in the requirements for record keeping between large facilities and very small ones as this is. In his opinion, however, and also in the opinion of the surveyors who visited the facility, the residents appeared to be clean, appropriately dressed, well fed, and content. Ms. Braddy contends that at the present, all the actions the rules require are being taken and while in the past she may not have done everything correctly, she has made the effort to comply with the instructions she received from the Department. She has recently hired an individual to help her and stay with the residents while she is gone. Before he came to work, she received some assistance from her children who, without pay, helped her from time to time. She believes her facility is now operating within the Department's requirements and there has been no survey conducted since June, 1988, to indicate whether this true or not.
Recommendation Based on the foregoing Finding of Facts and Conclusions of Law, it is, therefore: RECOMMENDED that Petitioner, Earlen Braddy, be issued a conditional license to operate an Adult Congregate Living Facility for a period of 6 months at which time, if all deficiencies are not corrected, the application for renewal be denied. RECOMMENDED this 12th day of December, 1988, at Tallahassee, Florida. ARNOLD H. POLLOCK, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of December, 1988. APPENDIX TO RECOMMENDED ORDER, CASE NO. 88-3025 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the Proposed Findings of Fact submitted by the parties to this case. BY THE PETITIONER None submitted. BY THE RESPONDENT 1. - 7. Accepted and incorporated herein Accepted and incorporated herein though the problem appears to be more a question of inability rather than unwillingness. Rejected as contra to the state of the evidence. Mr. Schaub indicated she would continue to have paperwork problems but with help could master the problem Not a Finding of Fact but a comment of the state of the evidence. COPIES FURNISHED: Gardner Beckett, Esquire 123 8th Street North St. Petersburg, Florida 33701 Edward Haman, Esquire Office of Licensure and Certification Legal Counsel Department of Health and Rehabilitative Services 7827 North Dale Mabry Highway Tampa, Florida 33614 Gregory L. Coler, Secretary Department of Health and Rehabilitative Services 1323 Winewood Blvd. Tallahassee, Florida 32399-0700 R. S. Power, Agency Clerk Department of Health and Rehabilitative Services 1323 Winewood Blvd. Tallahassee, Florida 32399-0700
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are made: At all times material to this proceeding, Respondent Joseph W. Miklavic was licensed as a certified building contractor in the state of Florida, holding license number CB C006615, qualifying Security Home d/b/a Security Homes of Clearwater (Security). Since March, 1989 the Respondent's license has been on active status qualifying, Individual. At all times material to this proceeding, Respondent was a salaried employee of Security. Ronald MacLaren was president of Security and also sole owner and president of Yankee Construction Inc. d/b/a Olympic Homes of Citrus County (Olympic). In accordance with a management agreement between Security and Olympic, the Respondent was assigned by Ronald MacLaren to oversee the operation of Olympic. Olympic was licensed to engage in construction having been qualified by Wilmon Ray Stevenson through license number RB A035005 which was in effect from June, 1987 until October, 1988 when Stevenson filed a change of status application with the Construction Industry Licensing Board (Board) requesting license number RB A035005 be changed to inactive status qualifying, Individual. While this application was not acted upon until February, 1989, the Board considered license number RB A035005 in effect as qualifying Olympic only until October, 1988. Effective September 26, 1988, the name of Yankee Construction, Inc. was changed to Rivercoast Homes, Inc. (Rivercoast) which apparently ceased doing business under the fictitious name of Olympic Homes of Citrus County. On September 19, 1988 Wilmon Ray Stevenson advised the Citrus County Building Department that he was no longer the "qualifier for Olympic Homes". Around this same time, the Respondent, Ronald MacLaren and the management of Olympic became aware that Stevenson would no longer be the qualifying agent for Olympic. There was no evidence that Rivercoast Homes, Inc. a/k/a Yankee Construction Inc. ever advised the Board of the name change or the termination of Stevenson as its only qualifying agent affiliation in accordance with Section 489.119(2)(3), Florida Statutes. Nor was there any evidence that Rivercoast was ever qualified by another qualifying agent pursuant to Section 489.119, Florida Statutes. In accordance with the agreement between Security and Olympic, referred to in Finding of Fact 4, the Respondent continued to oversee the Rivercoast operations until sometime around December 1988 when all of MacLaren's operations in Florida, including Security, closed down. Under Security's agreement with both Olympic and Rivercoast, Respondent's duties included working with management and subcontractors to develop construction schedules and to advise Ron MacLaren of the financial aspect of the company so that MacLaren could make funds available to pay subcontractors, etc. Respondent did not have any control over the finances of either Olympic or Rivercoast such as receiving, depositing or disbursing funds. Either in late September or early October of 1988, Respondent approached Larry Vitt, Citrus County Building Department, as to whether the Respondent could pull permits under his license for Olympic or Rivercoast. Vitt advised Respondent that unless he qualified the company he could not pull permits for that company under his license. Respondent advised MacLaren that Rivercoast would have to have a qualifying contractor in order to engage in contracting. MacLaren did not get Rivercoast qualified to engage in contracting at anytime. Respondent did not qualify Rivercoast under his contractor's license at anytime. Sometime around the last of September or the first part of October of 1988, Respondent became aware that Rivercoast a/k/a Yankee Construction, Inc. was no longer qualified under Section 489.119, Florida Statutes, and therefore, not authorized under law to engage in contracting. On August 16, 1988 Ernest and Marjorie Ellison met with Ken Smith and Gloria Stevenson of Olympic to discuss Olympic building the Ellisons a home. The Ellisons picked out a floor plan at this time and gave Olympic a $100.00 deposit to hold the price until a contract could be executed. On October 1, 1988 the Ellisons met again with Ken Smith and was introduced to the Respondent who gave them a brief run down on the status of the company and advised them that the company was in "good shape". At this meeting, Ken Smith advised the Ellisons of certain things that were required of them before construction began, including a survey. On October 31, 1988 the Ellisons signed a contract with Rivercoast to construct their home. In his capacity as a representative of Security, under the agreement between Security and Rivercoast, the Respondent signed this contract on the line designated Contractor/Representative. There is insufficient evidence to show that Respondent intended to sign the contract as contractor of record as the term contractor is defined in Section 489.105(3), Florida Statutes (Supp. 1988), and thereby impose upon himself the responsibility for the entire project. The contract price was $44,634.00. On November 1, 1977 the Ellisons delivered to Rivercoast a check for $4,363.40 which along with the $100.00 deposit paid in August represented a total down payment of $4,463.40. Respondent did not personally receive any funds from the Ellisons for Rivercoast or receive any funds for himself from the Ellisons under this contract. No permit was ever pulled or any work performed by Rivercoast under the aforementioned contract. Ernest Ellison met with Respondent on November 21, 1988 and requested that the contract be cancelled. Under the authority granted Respondent through the agreement between Security and Rivercoast, the Respondent and Ernest Ellison signed the contract as being cancelled on November 21, 1988. Although the Ellisons were offered an opportunity by the Respondent to transfer their deposit of $4,463.40 to Security and enter into a contract with Security to build their house, they declined and contracted with another contractor. On the date the contract was cancelled, Respondent advised Ernest Ellison that the down payment of $4,463.40 would be reimbursed. Although Respondent attempted to obtain a refund for the Ellisons from MacLaren and was advised by MacLaren that a refund was forthcoming, no refund of the Ellison's down payment was ever made by Rivercoast, Ronald MacLaren, the Respondent or anyone else. Respondent was aware during the negotiation and at the time the Ellison's contract was executed, that Rivercoast was not authorized by law to engage in contracting. However, there is insufficient evidence to show that Respondent ever advised the Ellisons that he would be the contractor responsible for building their home under the contract with Rivercoast or that he would be the contractor to pull the necessary permits for construction of their home. There is no evidence that Respondent had any financial interest or owned any stock or held any office in Rivercoast a/k/a Yankee Construction, Inc. Around October 1, 1988, after Stevenson had withdrawn as qualifying agent for Olympic, Rivercoast was no longer authorized to engage in the practice of contracting since it had not been qualified by another qualifying agent in accordance with Section 489.119, Florida Statutes.
Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the evidence of record, the demeanor of the witnesses and the disciplinary guidelines set out in Chapter 21E- 17, Florida Administrative Code, it is RECOMMENDED: That the Board enter a final order finding Respondent guilty of violating Section 489.129(1)(e), Florida Statutes, and for such violation it is recommended that the Board assess the Respondent with an administrative fine of $1,000.00. It is further recommended that Counts I, II, IV and V be dismissed DONE and ORDERED this 27th day of November, 1990, in Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of November, 1990. APPENDIX CASE NO. 90-2046 The following constitute my specific rulings pursuant to Section 120.59(2), Florida Statutes, on all of the proposed findings of fact submitted by the parties in this case. Rulings of Proposed Findings of Fact Submitted by the Petitioner Not necessary. Adopted in Finding of Fact 1. Adopted in Finding of Fact 7 but modified. Adopted in Findings of Fact 4, 8, and 10. Adopted in Findings of Fact 9 and 14 but modified. Adopted in Finding of Fact 15. Adopted in Findings of Fact 16 and 17 but modified. Adopted in Findings of Fact 17 and 18. Rulings of Proposed Findings of Fact Submitted by Respondent 1. - 2. Not material or relevant. Adopted in Findings of Fact 1, 7 and 20. Adopted in Finding of Fact 4. Adopted in Findings of Fact 4 and 8. Not material or relevant. Adopted in Finding of Fact 19. - 10. Adopted in Finding of Fact 15. Restatement of testimony not a Finding of Fact but see Finding of Fact 13. Adopted in Finding of Fact 15. Not material or relevant. Adopted in Finding of Fact 15. - 16. Not material or relevant. Restatement of testimony not a Finding of Fact but see Findings of Fact 13, 14 and 15. Adopted in Finding of Fact 19 but modified. Not material or relevant. Adopted in Finding of Fact 4. Restatement of testimony not a Finding of Fact but see Finding of Fact 4. Adopted in Finding of Fact 9. Adopted in Finding of Fact 4 but modified to show license effective until October, 1988 rather than February, 1989. Restatement of testimony not a Finding of Fact but see Findings of Fact 1, 7 and 20. - 26. Not material or relevant. Adopted in Finding of Fact 4 but modified to show from June, 1987 until October, 1988. - 29. Adopted in Findings of Fact 5 and 13. Restatement of testimony not a Finding of Fact but see Finding of Fact 4. - 32. Adopted in Findings of Fact 4, 8 and 9 but modified. Not material or relevant. - 36. Adopted in Findings of Fact 4, 8, and 9 but modified. Adopted in Finding of Fact 10. Not material or relevant. - 40. Adopted in Findings of Fact 8, and 17, respectively. Rejected as there is no substantial competent evidence in the record to show any other contract than the one Respondent signed on October 31, 1988. Not material or relevant. Not supported by substantial competent evidence in the record. Not material or relevant. Adopted in Finding of Fact 18. Restatement of testimony not a Finding of Fact but see Finding of Fact 9. - 50. Not necessary to the conclusion reached since this matter was covered in the Preliminary Statement wherein the motion was denied. COPIES FURNISHED: G. W. Harrell, Senior Attorney Department of Professional Regulation 1940 N. Monroe Street, Suite 60 Tallahassee, FL 32399-0750 Geoffrey Vining, P.A. 2212 South Florida Avenue Suite 300 Lakeland, FL 33803 Daniel O'Brien, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Kenneth D. Easley, General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792
The Issue Whether disciplinary action should be taken against Respondent's license to practice contracting, license number CC C057275, based on the violations of Section 489.129(1), Florida Statutes, as charged in the Administrative Complaint filed against Respondent in this proceeding.
Findings Of Fact At all times material, Respondent was a certified contractor, having been issued license number CC C057275 by the Florida Construction Industry Licensing Board. At all times material, Respondent was registered or certified with the Construction Licensing Industry Board doing business as Comtec Coatings Company (Comtec). At no time material hereto did Respondent apply for or obtain a certificate of authority for Comtec. Respondent has previously been disciplined for violations of Chapter 489, Florida Statutes, in Department of Business and Professional Regulation Case Number 2001-03759, including the failure to honor a warranty. On or about March 29, 1996, Respondent, doing business as Comtec Coatings Company, contracted with Kopp to re-roof her home located at 1010 Terry Drive, Melbourne, Florida, for the contract price of $8,600. Respondent's contract contained a five year warranty. Respondent was paid-in-full on or about April 6, 1996. Shortly after Respondent performed the roofing work, the roof experienced significant problems including excessive leakage and material deterioration. Eventually, the roof lost its ability to repel water and large portions rotted. Immediately, Respondent was advised of the problems yet failed to repair them. Kopp, along with her concerned friends and neighbors, expended hundreds of labor hours and at least $896.61 above the original contract price to mitigate the damage to her roof and home as a result of Respondent's workmanship. An independent roofing contractor estimated that it would cost $3,000 to temporarily repair the leaks and approximately $33,000 to replace it and completely correct the problem. As of the date of the administrative hearing, the roof has not been repaired, remains in poor condition and continues to leak. Kopp is legitimately concerned that her home may be condemned. The total investigative costs of this case to the Department of Business and Professional Regulation, excluding costs associated with counsel's time, are $399.30.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Petitioner enter a Final Order as follows: Finding Respondent guilty of having violated Section 489.129(1)(i), Florida Statutes, for failing to file for a certificate of authority as required by Section 489.119(2), Florida Statutes, as alleged in Count I of the Administrative Complaint, and imposing an administrative fine in the amount of $1,000. Finding Respondent guilty of having violated Section 489.129(1)(m), Florida Statutes, for incompetency and misconduct as alleged in Count II of the Administrative Complaint, and imposing an administrative fine in the amount of $2,000, revoking all licensure under the auspices of the Florida Construction Industry Licensing Board. Finding Respondent guilty of having violated Section 489.129(1)(g)(3), Florida Statutes, for having Kopp pay significantly more than the roofing repair contract price, and imposing an administrative fine in the amount of $5,000, revoking all licensure under the auspices of the Florida Construction Industry Licensing Board, and ordering Respondent to pay financial restitution to consumer Judith Kopp in the amount of $33,896.61 for consumer harm suffered. Assessing costs of investigation and prosecution in the amount of $399.30, which excludes costs associated with any attorney's time. DONE AND ENTERED this 31st day of December, 2002, in Tallahassee, Leon County, Florida. WILLIAM R. PFEIFFER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 31st day of December, 2002. COPIES FURNISHED: Brian A. Higgins, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-2202 Larry S. Olson 3451 Riva Ridge Place Fort Collins, Colorado 80526 Robert Crabill, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Hardy L. Roberts, III, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202
The Issue Whether Respondent aided and abetted an unlicensed contractor to engage in contracting by pulling permits for the unlicensed contractor; whether Respondent failed to qualify a firm for whom he was acting as licensed contractor; whether Respondent acted in the capacity of a contractor other than in his own name; and, whether Respondent violated local building codes as alleged in Second Amended Administrative Complaint filed 6-30-89, and Administrative Complaint filed 7-26-89.
Findings Of Fact At all times relevant hereto, Fred S. Petersen was licensed as a general contractor by the Florida Construction Industry Licensing Board (FCILB) and issued License Nos. CG C023928 and CB CA23929 (Exhibit 1). Neither American Weatherall Industries Inc. (AWI), Mel C. Wyatt, nor Steven C. Wyatt were licensed as contractors by the FCILB (Exhibit 2). Prior to mid-August 1987, Kirk Evenstad was the qualifying general contractor for AWI. By letter dated August 20, 1987, AWI proclaimed Kirk Evenstad to be no longer working for AWI because of mismanagement (Exhibit 3). Mel Wyatt, President of AWI, testified that Everstad had stolen between $30,000 and $50,000 of materials from AWI, leaving AWI in a precarious financial situation. In order to continue in business to work out of the financial hole created by Everstad, AWI, through one of its employees, Danny O'Brien, introduced Mel Wyatt to Respondent. Respondent had known O'Brien for some 20 years and, for the proposed reason of helping O'Brien, Respondent agreed to act as qualifying contractor for AWI. To carry out this project, Respondent entered into a contract (Exhibit 4) or Employment Agreement dated July 31, 1987, in which Respondent agreed to supervise construction of projects contracted for by AWI, but the latter was to provide all material and handle all financial aspects of the contracts. Respondent received $1000 for signing this agreement and was to receive a percentage of the gross proceeds of future contracts entered into by AWI. Respondent authorized O'Brien to pull permits for AWI pursuant to Respondent's contractor's license. Although Respondent testified he gave O'Brien authorization for each specific permit pulled and did not believe he signed Exhibit 11, dated August 11, 1987, a copy of General Authorization for O'Brien to pull permits for AWI under Respondent's license, it is found as a fact that Respondent signed the original of Exhibit 11 which is a copy. Within a short period of time after executing Exhibit 4, Respondent became aware of the financial difficulties facing AWI and ceased his efforts to qualify AWI. In the latter part of 1987 (believed to be November-December), AWI reached the point that it could no longer remain solvent and filed for bankruptcy leaving several contracts unfinished for which AWI had received partial payment. Of the four contracts entered into between AWI and homeowners for additions to their houses (Exhibits 7-9 and 14), all were entered into under a printed document showing Everstad's license number; however, the building permits for Exhibits 7-9 were pulled under Respondent's license. By agreement dated August 10, 1987 (Exhibit 7), Alfred and Marjory Hauk contracted with AWI to convert a garage at their home into an office. Hauk made payments of $1000 and $2300 to AWI, the permit for the work was pulled by O'Brien under Respondent's license, but no work was ever done under this contract. AMI subsequently went out of business, and Hauk received no refund of the monies he had paid to AMI. Hauk never met Respondent. On June 12, 1987, John Davis contracted with AWI to convert an existing garage to bedroom and bath and add a garage to his home. The initial permit for this work was pulled by Kenn Covicc as contractor on June 21, 1987, and a subsequent permit was pulled by O'Brien using Respondent's license. Although Davis paid over $6000 to AWI for this work, the work stopped after the footing for the garage addition was poured. On June 2, 1987, Albert Charette entered into a contract with AWI to add a room to his house. Charette paid some $9300 of the $34,400 contract amount during the progress of the work. Differences arose between Charette and AWI involving whether the construction was being done in accordance with the plans and specifications. In September, 1987, Respondent met with Charette and submitted a proposal (Exhibit 15) to Charette to complete the project in accordance with the plans and specifications. About one week after Exhibit 15 was signed, all work stopped on the project, and Respondent never received compensation or commenced work on this contract, which he had entered into in his own name and not as a representative of AWI.
Recommendation It is recommended that Fred S. Petersen be found guilty of violating Sections 489.129(1)(e), (f) and (g), Florida Statutes, and assessed a monetary fine of $3000. ENTERED this 11th day of June, 1990, in Tallahassee, Florida. K. N. AYERS Hearing Officer Division of Administrative Hearings The Desoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of June, 1990. APPENDIX Proposed findings submitted by Petitioner are accepted, except: Finding #7, penultimate sentence which is rejected as uncorroborated hearsay. Finding #11, that portion stating the purpose of Petersen's visit to Charette was to change the licensure on the permit to Petersen is rejected. See HO #13. Proposed findings submitted by Respondent are accepted, except: Finding #4, Accepted, except with regard to Respondent's notification of termination of his association with AWI. No documentation of this act was submitted and, even though Respondent may have ultimately revoked O'Brien's authority to pull permits, this was done well after the permits were pulled. COPIES FURNISHED: Robert B. Jurand, Esquire G. W. Harrell, Esquire Department of Professional Regulation Northwood Centre 1940 North Monroe Street Suite 60 Tallahassee, FL 32399-0792 Brian A. Burden, Esquire Post Office Box 2893 Tampa, FL 33601 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, FL 32202 Kenneth E. Easley General Counsel Department of Professional Regulation Northwood Centre 1940 North Monroe Street Suite 60 Tallahassee, FL 32399-0792
Findings Of Fact The Respondent, Marlene E. Lutman, is a vice president of American Custom Builders, Inc. and was a vice president in 1977. Respondent holds licenses Number CR C012570 end Number CR CA12570 issued by the Petitioner Board. On September 11, 1978, Respondent submitted a certification change of status application to the Florida Construction Industry Licensing Board. This application, completed by Respondent under oath on September 7, 1978, was filed for the purpose of changing the contractor's licenses held by Respondent to add the name of American Custom Builders, Inc. to said licenses. On July 6, 1979, an Administrative Complaint was filed against Respondent, doing business as American Custom Builders, Inc., seeking to permanently revoke her licenses and her right to practice under said licenses and to impose an administrative fine in the amount of $500.00. Respondent Lutman requested an administrative hearing, which was scheduled for September 6, 1979, continued on Motion of Respondent, and held November 29, 1979. On the application completed by Respondent, Question 12(b) asked: Are there now any unpaid past-due bills or claims for labor, materials, or services, as a result of the construction operations of any person named in (i) below or any organization in which such person was a member of the personnel? Question 12(c) of the application asked: Are there now any liens, suits, or judgments of record or pending as a result of the construction operations of any person named in "(i) below" or any organization in which any such person was a member of the personnel? Respondent, as a vice president of American Custom Builders, Inc., was designated in "(i) below." She answered "no" on the application to both of the above stated questions. Respondent completed the application while she was in Florida. Prior to completing the application, Respondent spoke by telephone with John D. Cannell, an attorney in Ohio, in reference to Questions 12(b) and 12(c), supra. Cannell told Respondent that there were no unpaid bills outstanding. He said that there had been liens filed involving American Custom Builders, Inc., but that these liens had been cancelled. Cannell based his statements to Respondent upon oral assurances from personnel at the bank involved in financing the construction project associated with the liens that all liens had been paid. It was later learned that on September 7, 1978, the date Cannell told Respondent the liens had been cancelled, the liens had not been cancelled and were of record in the Recorder's Office of Geauga County, Ohio. Liens had been filed on January 6, 1978, January 23, 1978, and January 3l, 1978, by various subcontractors involved in the construction of a house owned by Winford and Sally Ferrentina. The liens were based on claims against American Custom Builders, Inc. as general contractor and the Ferrentinas as owners for unpaid labor and materials and were not satisfied of record until September 20, 1978, on which date the January 6, 1978 lien was satisfied, and March 22, 1979, on which date the other two (2) liens were satisfied. The Hearing Officer finds that Respondent Lutman did not intend to make a material false statement but negligently relied on oral representations that there were no past-due bills and no liens of record pending as a result of her construction operations. Both parties submitted proposed findings of fact, memoranda of law and proposed recommended orders, and the Petitioner Board submitted a reply memorandum. These instruments were considered in the writing of this order. To the extent the proposed findings of fact have not been adopted in, or are inconsistent with, factual findings in this order they have been specifically rejected as being irrelevant or not having been supported by the evidence.
Recommendation Based upon the foregoing Findings and Conclusions of Law, the Hearing Officer recommends that the Respondent, Marlene Lutman, be reprimanded. DONE and ORDERED this 1st day of February, 1980, in Tallahassee, Leon County, Florida. COPIES FURNISHED: Jeffery B. Morris, Esquire 2400 Independent Square One Independent Drive Jacksonville, Florida 32202 Jeffrey R. Garvin, Esquire 2532 East First Street Post Office Box 2040 Fort Myers, Florida 33902 DELPHENE C. STRICKLAND Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. DOAH CASE NO. 79-1546 Marlene Lutman, CR C012570, CR CA 12570 Respondent, /
Findings Of Fact Respondent Henry Huggins is presently licensed by the Construction Industry Licensing Board as a certified general contractor under license number CO C003466. He first received his license in November of 1972 and has since been continuously licensed. His license was however suspended for a period of one year beginning on May 16, 1980. That suspension was by an Order of the Florida Construction Industry Licensing Board. In October of 1981 Mr. Huggins renewed his license on inactive status but changed it to active status in December 1981. His license continued to be active and he is the qualifying agent for Florida Petroleum Services, Inc., in Winter Park Florida. In the fall of 1980 Mr. Albert Dupre agreed to do some home renovation work for Dr. Charles Gill at Dr. Gill's residence located at 2193 Turkey Run, Winter Park, Florida. Mr. Dupre completed the work and shortly thereafter in the spring of 1981 he and Dr. Gill entered into another oral contract whereby Mr. Dupre would construct an upstairs addition to Dr. Gill's home. The addition included the installation of a bathroom and another bedroom. In exchange for these services Dr. Gill "traded off" dental work for Mr. Dupre's wife and agreed to pay an additional $12,000 or $13,000. At Mr. Dupre's request the construction permit for the upstairs addition was obtained by the Respondent Henry L. Huggins. At all times material Albert Dupre has held no contracting licenses authorizing him to individually perform the work called for by his agreement with Dr. Gill. During the time in question, that is April 1981, Respondent did not himself have an active contractor's license due to his suspension by the Construction Industry Licensing Board. He was authorized by the qualifying agent for Roberts Insurance Contractors to obtain building permits under the qualifying agent's license in order to undertake building projects for Roberts. Roberts Insurance Contractors was not a party to the agreement between Dr. Gill and Mr. Dupre for the up stairs addition to Dr. Gill's home. On April 7, 1981 Respondent obtained building permit number 7487 from the City of Winter Park, Florida, which authorized the construction of a bedroom and bathroom addition on the property of Dr. Charles Gill in Winter Park, Florida. Respondent obtained that permit on behalf of Mr. Dupre because of their friendship and their previous business associations dating back to the mid- 1970's Respondent did not supervise or otherwise participate in the construction of Dr. Gill's addition until the work was complete and Dr. Gill made a complaint to several regulatory bodies about Mr. Dupre's work. This complaint centered around the earlier air conditioning project; but once notified that there were difficulties concerning the project, Respondent, along with Mr. Dupre, completed all unfinished items and corrected all defects. As a result of Respondent's willingness to remedy those defects Dr. Gill has requested that all charges against Mr. Huggins here be dropped.
Recommendation Based on the foregoing Findings of Fact and Conclusions Law, it is RECOMMENDED: That the Construction Industry Licensing Board enter a Final Order suspending the license of Henry L. Huggins as a certified general contractor for a period of two (2) years from the date of the Board's Final Order. DONE and RECOMMENDED this 17th day of February, 1984, in Tallahassee, Florida. MICHAEL PEARCE DODSON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9673 Filed with the Clerk of the Division of Administrative Hearings this 17th day of February, 1984.
Findings Of Fact Petitioner is the state agency charged with the responsibility to prosecute administrative complaints pursuant to Chapters 489, 455, and 120, Florida Statutes, and the rules promulgated pursuant thereto. At all times material to the Administrative Complaint, Respondent James J. Hastings was licensed as a certified general contractor in the State of Florida, holding license number CG C009847. At all times material hereto, Respondent was a qualifying agent for Hastings Construction Company, Inc. Respondent and Candace Reinertz are married. At all times material to the violations charged, she was operating under her maiden name for all purposes. At all times material hereto, Candace Reinertz was not licensed by the Florida Construction Industry Licensing Board, and the Respondent had knowledge thereof. Over several years, Ms. Reinertz regularly assisted Mr. Hastings in the operation of Hastings Construction Company, Inc., including day to day supervision of pool, small building, and house construction and pulling building permits for that corporation. She had been authorized in writing by Hastings to pull building permits for him on specific projects (not necessarily in a corporate name) at least since April 27, 1987. At all times material hereto, Castles `n' Pools, Inc., 205 Third Avenue, Melbourne Beach, Florida, was a firm that was not qualified with the Construction Industry Licensing Board, and Respondent had knowledge thereof. This corporation was intended to become a venture to be run jointly by husband and wife. Castles `n' Pools, Inc. had been qualified as a corporation with the Florida Secretary of State and had received an occupational license. The corporate officers/directors were Reinertz and Hastings. However, a Florida Construction Industry Licensing Board License was never applied for by Ms. Reinertz in her own name nor was one applied for by Mr. Hastings as a qualifier for Castles `n' Pools, Inc. On June 27, 1987, Castles `n' Pools, Inc., through Candace Reinertz, contracted with Zimmer Dominque for construction of a pool at Mr. Dominque's residence located at 866 Van Circle, N.E., Palm Bay, Florida, for $7,750. The contract promised completion of the pool by September 23, 1987, barring adverse weather and mishaps. It is Ms. Reinertz's testimony that she inadvertently filled in a Castles `n' Pools, Inc. blank contract when she intended to use a Hastings Construction Company blank contract. The blank forms are, indeed, very similar. Mr. Dominque's testimony is that he thought at all times that he was contracting with Castles `n' Pools, Inc., through Ms. Reinertz. Although he admits that at least by September 22, 1988, he considered Respondent in charge of the project and that he thereafter dealt directly with Respondent, Mr. Dominque's payment by checks made out to Castles `n' Pools and/or Candace Reinertz dated June 27, July 7, September 22, and September 24, 1987 (P-10) support a finding that all work to that point was progressing in the name of Castles `n' Pools. Also supportive of such a finding is that on July 6, 1987, Pyramid Equipment Service billed Castles `n' Pools for digging the hole for the pool (R-8) and on August 11, 1987, R & J Crane Service billed Castles `n' Pools for setting the pool in place (R-9). However, the issuance of the building permit to Hastings Construction Company, Inc. and the chronology of how the permit came to be issued (see infra.) suggest that Mr. Hastings did not know about the Castles `n' Pools connection until at least late September. Respondent's and Ms. Reinertz' testimony that Respondent did not find out that the wrong contract had been used until after construction was underway on the Dominque property is unrefuted and the exact date of his discovery was not demonstrated, but he admits he did not attempt to qualify Castles `n' Pools once he found out. On June 29, 1987, the Respondent authorized Candace Reinertz to pull a permit for the construction of a pool at Mr. Dominque's residence. The authorization, (P-12), does not specify either Castles `n' Pools nor Hastings Construction Company, Inc. as the construction corporation applicant. Ms. Reinertz's subsequent permit application was denied on July 2, 1987, by the Palm Bay Building Department, for failure to include a survey certified by a civil engineer or architect. The record does not reflect in what corporate name Ms. Reinertz made this initial application. She may not even have gotten as far as filling out a permit application before she was refused at the permit desk, but the line drawing prepared for that application (R-1) specifies that the line drawing was that of Hastings Construction Company, Inc. Mr. Hastings regularly did line drawings for Hastings Construction Company, Inc. projects on a particular machine in that corporation's offices. The certified survey requirement was a recent innovation of the Palm Bay Building Code. On July 6, 1987, Castles `n' Pools, Inc. delivered the prefabricated fiberglass pool, excavated the site and dropped the pool in the hole. No further efforts of permanent installation occurred at that time, due to failure to obtain a permit. A dispute then ensued between Hastings and Reinertz on one side and Mr. Dominque on the other over who must provide the survey and how. This dispute occasioned some delay in the project, but on July 26, 1987, Ms. Reinertz again applied, with a certified survey, to the Palm Bay Building Department for a permit for the construction of Mr. Dominque's pool, listing the builder as Hastings Construction Company, Inc. (P-5). On July 30, 1987, permit number 8702101 was issued by the Palm Bay Building Department for the construction of Mr. Dominque's pool by Hastings Construction Company, Inc. (P-6). Thereafter, work on the pool progressed sporadically until September 22, 1987, when the pool floated up out of the ground. The pool floated up out of the ground during a rainstorm and after Respondent had left Mr. Dominque with instructions to fill the pool to a certain level with water. There is sufficient evidence to demonstrate that Mr. Dominque failed to follow Respondent's directions with precision. Subsequent to September 22, 1987, the pool was reinserted in the excavation by crane and by October 2, 1987, the deck was installed. Two or three months later a crack appeared in the pool which has since been repaired, however, the drain and light still do not work properly, and Mr. Dominque had to pay an additional $50 for cleanup of the resulting debris. Some of the delay in completion of work on the pool can be attributed to the dispute about the survey, some to injury of a key employee, and some to heavy rains, but the testimony of Mr. Nasrallah, architect and expert contractor, is accepted that 30 to 45 days would be sufficient to install the entire pool except for the pool deck even in rainy weather. Also, Mr. Dominque's and Respondent's testimony is in agreement that Respondent (not Ms. Reinertz) was fired for a period of time and then rehired. The length of time and the dates that Respondent was off the job is unclear, but it was minimally from September 9 to September 22, 1987. Oversight of the work at all times was by the Respondent. Mr. Dominque has paid the total contract price of $7,750 and expressed himself that any amount he questioned has either "evened out" or been paid back by Respondent. Stan Alexander is a certified general contractor and former chairman of the Florida Construction Industry Licensing Board. In his expert opinion as a contractor, construction began when the hole was first dug on July 6, 1987 and the pool was placed in it even temporarily. Also in his expert opinion as a contractor, Mr. Alexander determined that the contractor responsible for the installation of this pool was guilty of gross negligence or incompetence due in part to the insufficiency of dewatering devices (including a hydrostatic device) and placement of the responsibility to fill the pool on the home owner. Mark Nasrallah is a registered Florida architect and a licensed general contractor. Also in his expert opinion as a contractor, construction began on the job when the pool was placed in the excavation. It is also Mr. Nasrallah's expert opinion that the contractor responsible for this job is guilty of gross negligence or incompetence. Although Mr. Alexander was unfamiliar with any local Palm Bay zoning or permitting provision which would allow "site clearing" prior to excavation/construction, and although Mr. Nasrallah considered it "questionable" whether the digging for the pool constituted "construction without a permit," Mr. Nasrallah's assessment that digging the hole and putting the pool in the hole even temporarily was in excess of mere site clearing and was work which clearly began construction is accepted. Section 103 of the Standard Building Code has been adopted by the City of Palm Bay. It provides as follows: A person, firm or corporation shall not erect, construct, enlarge, alter, repair, move, improve, remove, convert, or demolish any building or structure in the applicable jurisdiction, or cause the same to be done, without first obtaining a building permit for such building or structure from the Building Official. Respondent was disciplined by the Construction Industry Licensing Board in October, 1984, for violation of Sections 489.129(1)(c), (g), (j); 489.119(2), (3); and 455.227(1)(a) Florida Statutes.
Recommendation Upon the foregoing findings of fact and conclusions of law, it is recommended that the Construction Industry Licensing Board enter a final order finding Respondent guilty of violations of Sections 489.129 (1)(d) and (m) Florida Statutes, issuing a letter of guidance with regard to the permitting violation, fining the Respondent $750.00 for gross negligence or incompetence, and dismissing the remaining two charges. DONE and RECOMMENDED this 23rd day of November, 1988, at Tallahassee, Florida. ELLA JANE P. DAVIS, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of November, 1988. APPENDIX TO RECOMMENDED ORDER DOAH Case No. 87-5172 The following constitute rulings pursuant to s. 120.59(2), Florida Statutes, upon the parties' respective Proposed Findings of fact (FOF). Petitioner PFOF: Accepted in FOF 1. Accepted in FOF 2. Accepted in FOF 3. Accepted in FOF 5. Accepted in FOF 7. Accepted in FOF 8. 7-8. Accepted and expanded to more accurately reflect the record in FOF 10 9. Accepted in FOF 11. 10-11. Accepted and expanded to more accurately reflect the record in FOF 12. Accepted and expanded to more accurately reflect the record in FOF 13. Accepted in FOF 14. 14-15. Accepted in part and rejected in part in FOF 15-17. The modifications are made to more accurately reflect the record as a whole, the specific expert opinion as given by Messrs. Alexander and Nasrallah (discussed in the Conclusions of Law) and to reflect that some hydrostatic devices were used, some removed, and at least one left in for a period of time. 16. Accepted in FOF 19. COPIES FURNISHED: Fred Seely, Executive Director Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32201 G. W. Harrell, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 James J. Hastings 205 Third Avenue Melbourne Beach, Florida 32951 Lawrence A. Gonzalez, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Bruce D. Lamb, General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 =================================================================
The Issue The issue in this case is whether Respondent violated Section 489.129(1), Florida Statutes (1997) (hereinafter, "Florida Statutes"), by committing mismanagement or misconduct in the practice of contracting, causing financial harm to a customer, abandoning a construction project, and failing to satisfy a judgment against him.
Findings Of Fact Petitioner is the state agency responsible for regulating the practice of contracting. Respondent is licensed as a contractor pursuant to license number CB C019811. At all relevant times, Respondent was the qualifying agent for Gulf and Bay Sunrooms, Inc. ("Gulf"). As the qualifying agent, Respondent was responsible for all of Gulf's contracting activities in accordance with Section 489.1195, Florida Statutes. On August 23, 1995, Respondent and Gulf entered into a contract with Mr. H. Edward Dowling ("Dowling") to install a Four Seasons System 330 Sunroom in Dowling's residence at 3016 West 38th Street, Orlando, Florida. The contract price was $31,340. Dowling paid the first draw of $9,402 to Respondent and Gulf by check number 45016644. On October 27, 1995, Gulf deposited the check to its account. Respondent and Gulf never commenced work on the sunroom. Respondent and Gulf did not return the first draw to Dowling. Respondent and Gulf abandoned the project without just cause and without notice to Dowling. On June 19, 1997, the County Court of the Ninth Judicial Circuit entered a Default Final Judgment in Case No. CO97-3800. The default judgment was entered in the amount of $9,402 plus costs of $145. Neither Respondent nor Gulf have satisfied the judgment. Respondent has a discipline history in two other cases. In Petitioner's Case No. 96-7123, Respondent failed to pay a supplier for windows. In DOAH Case No. 96-5914, Respondent contracted to build a sunroom in a residence, accepted payment of $1,540.44 toward the contract price of $4,668.00, never commenced construction, and abandoned the project. In the first case, Respondent was found guilty of failing to satisfy a civil judgment, was fined, and was ordered to pay restitution. In the second case, Respondent was found guilty of abandonment, incompetency or misconduct, was fined, and was ordered to pay restitution, and his license was suspended until Respondent complied with the penalty imposed.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Board enter a Final Order finding Respondent guilty of violating Section 489.129(1), Florida Statutes, imposing administrative fines in the aggregate amount of $15,000.00, and revoking Respondent's license. DONE AND ENTERED this 10th day of August, 1998, in Tallahassee, Leon County, Florida. DANIEL MANRY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 10th day of August, 1998. COPIES FURNISHED: Rodney Hurst, Executive Director Department of Business and Professional Regulation Construction Industry Licensing Board 7960 Arlington Expressway, Suite 300 Jacksonville, Florida 32211-7467 Lynda L. Goodgame, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792 Paul F. Kirsch, Senior Attorney Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street, Suite 60 Tallahassee, Florida 32399-0792 William Leete Stone, IV, pro se 3386 Poinsettia Avenue Naples, Florida 34104
The Issue Whether Respondent, a certified general contractor, is guilty of pulling permits for construction projects not supervised by Respondent, and, if so, the appropriate disciplinary action which should be taken by the Board.
Findings Of Fact At all times material hereto, Respondent was the holder of Certified General Contractor's License No. CG C005204 issued by the Board. Although this license was active at the time the Administrative Complaint was filed, Respondent has placed it on an inactive status until June 30, 1981. (Stipulation, Testimony of Respondent) As to Amiguet Construction Project During 1976, Jose Amiguet entered into a contract with San Pedro Construction Inc. for the construction of an addition to his existing residence located at 1409 Granada Boulevard, Coral Gables, Florida. (Stipulation, Petitioner's Exhibit 1) Since San Pedro Construction Inc. was not properly licensed as a building contractor, it was not qualified to apply for and obtain a Coral Gables building permit to undertake this residential addition. Therefore, on January 12, 1977, pursuant to an agreement with Jose San Pedro, representative of San Pedro Construction Inc., the Respondent applied and obtained the required Coral Gables building permit under his on name. (Stipulation, Testimony of Respondent, Charles Kozak, Petitioner's Exhibit 1) The Respondent did not participate in, manage, or supervise, in any manner, the construction of the Amiguet residential addition by San Pedro Construction Inc. Jose Amiguet neither knew the Respondent, nor had any dealings with him during the construction work. (Stipulation, Testimony of Respondent) Final inspection of the Amiguet construction project has not been conducted by the Coral Gables building inspection department since the required documentation concerning sidewalk improvements and subcontractors used has not yet been submitted. The actual construction work has, however, been completed, to the satisfaction of Jose Amiguet. (Testimony of Charles Kozak, Respondent) Respondent made an effort to assist Jose Amiguet in obtaining the final inspection and clearance by the city building inspection department. However, since Respondent did not supervise the subcontractors' work, he cannot truthfully complete the required documents. He has, therefore, offered to (1) pay for the additional costs associated with obtaining the necessary final inspection, and (2) transfer to Jose Amiguet the right to receive, after final inspection, the refund of the contractor's performance bond in the amount of approximately $400-$500. (Testimony of Respondent) As to the Shaw Construction Project During July, 1977, and on February 8, 1978, James L. Shaw entered into separate contracts with San Pedro Construction Inc. for the construction of residential improvements at 836 Obispo Avenue, Coral Gables, Florida. The final contract was in the amount of $16,700.00. (Stipulation, Testimony of Respondent, James L. Shaw, Petitioner's Exhibit 4) Since San Pedro Construction Inc. was an unlicensed contractor, Respondent, on November 15, 1977, pursuant to an agreement with that company, applied for and obtained the required Coral Gables building permit. (Stipulation, Testimony of Respondent, James L. Shaw, Petitioner's Exhibit 4) The Respondent did not participate in, manage, or supervise in any manner the construction of the Shaw residential improvements by San Pedro Construction Inc. James Shaw neither knew Respondent, nor had any dealings with him during the construction work. (Stipulation, Testimony of Respondent) On or about April, 1978, the lending institution for the Shaw project, and James Shaw stopped making construction payments to San Pedro Construction Inc., due to its failure to proceed on and abandonment of the project. (Testimony of James Shaw, Charles Kozak) On June 20, 1978, James Shaw obtained an "owner-builder" permit from the City of Coral Gables and incurred the following costs in order to complete the construction project as originally planned: $12,000 for labor and materials, and $625.00 for architectural services. Inasmuch as approximately, $10,128.00 had earlier been paid to San Pedro Construction Inc. for the construction project, the total cost of the project to James Shaw was approximately $22,753.00-$6,053.00 in excess of the original contract price. (Testimony of James Shaw and Respondent) San Pedro Construction Inc. is no longer in business, and the whereabouts of its owner, Jose San Pedro, is unknown. (Testimony of Respondent) As with the Amiguet construction project, final inspection of the Shaw project cannot be conducted until missing documentation relative to sidewalk improvements and subcontractors involved is supplied. In an effort to assist James Shaw, the Respondent has offered to transfer to Shaw the right to receive, after final inspection, the refund of the contractor's performance bond in the amount of approximately $400-$500. (Testimony of Charles Kozak and Respondent) At all times material hereto, the Respondent was aware that it was unlawful, under both state law and the Code of Metropolitan Dade County, to aide an unlicensed contractor in evading the contractor licensing law, and to use one's license to pull permits for projects not supervised by the licensee. (Stipulation, Testimony of Respondent, Petitioner's Exhibit 1) The Metro Dade Construction Trades Board heard the complaint against the Respondent and found prima facie evidence and probable cause to refer the matter to the Florida Construction Industry Licensing Board (Stipulation) Notwithstanding the evidence presented, the Administrative Complaint and the Board's counsel at hearing limited the amount sought for restitution purposes to $5,300.00, provided both the performance bonds are refunded to the benefit of Jose Amiguet and James Shaw. (Administrative Complaint, statement of Board's Counsel) Respondent regrets having taken the actions complained of in the Board's Administrative Complaint, and now more fully understands the resulting burdens which have been placed on Jose Amiguet and James Shaw. (Testimony of Respondent)
Recommendation Guilty, as charged. Respondent's certified general contractor's license should be suspended until such time as full restitution is made to the persons damaged by his actions.
Findings Of Fact The Respondent is a certified general contractor holding license number CG C016888. The Petitioner is an agency of the State of Florida charged with enforcing the provisions of Chapter 489, Florida Statutes, regulating the licensure and practice status and standards of building contractors in the State of Florida and enforcing the disciplinary provisions of that chapter. On December 14, 1981, Respondent contracted with Mr. and Mrs. Frank J. Sullivan to build the Sullivans a home in Sarasota County, Florida. Those parties entered into a contract whereby the Respondent was to be paid the actual cost of construction including all labor and materials plus a commission in the amount of 8 percent of the actual cost of construction, provided however, that the total contract price would not exceed $49,000, including actual costs and commission. In January, 1982, Respondent commenced work constructing the home. The Respondent worked on the home for several months and then abruptly ceased and abandoned construction without explanation on May 14, 1982. At this time the house was approximately 70 percent complete. At the time the Respondent ceased work on the project he had already been paid $47,362.29 or approximately 97 percent of the total contract price agreed to by the parties. The Sullivans thereafter had to pay $10,633.53 to subcontractors and materialmen who had been hired by the Respondent to supply labor and/or materials to the house, at the Respondent's direction, prior to his ceasing construction and leaving the job. Additionally, the Nokomis Septic Tank Company, Inc., the subcontractor who installed the septic tank, was owed $1,180.07 by the Respondent for the installation of the septic tank, which amount was to have been paid out of the total $49,000 contract price. The Respondent failed to pay Nokomis Septic Tank Company, which then filed a mechanic's lien on the property. In order to remove this cloud on their title to the property and avoid foreclosure of the lien, the Sullivans were forced to pay the $1,180.07 amount of the lien. In addition to more than $10,000 paid to subcontractors who had already performed labor or supplied materials to the job before the Respondent left it, the Sullivans had to obtain a loan from their bank in order to finish the project. The contracted for items which the Respondent had left undone (approximately 30 percent of the construction) required them to expend $18,662.04 to complete the dwelling in a manner consistent with the contractual specifications. The items which remained to be constructed or installed are listed on Petitioner's Exhibit 7 in evidence. The remaining amount of contract price which the Respondent was due upon completion of the job would have been $1,737.71. With this in mind, as well as the fact that the Sullivans had to pay in excess of $10,000 to defray already outstanding bills to subcontractors for labor and materials already furnished and then had to obtain a loan in order to pay $18,662.04 in order to complete the house, and it being established without contradiction that the Respondent was unable to make his payroll at the point of leaving the job, the Respondent obviously used substantial amounts of the funds he received from the Sullivans for purposes other than furthering the construction project for which he contracted with the Sullivans. Concerning Count II, on December 22, 1981, Frederick Berbert doing business as Venice Enclosures of Venice, Florida, contracted with Mr. Emory K. Allstaedt of Grove City, Florida, Charlotte County, to build an addition to Mr. Allstaedt's mobile home. The contract specified a price of $4,952 for which Berbert was required to construct a 12-foot by 20-foot enclosure or porch. Mr. Allstaedt never did and never intended to contract with the Respondent, Mr. Martin, rather, his contract was only with Frederick Berbert. Mr. Berbert was a registered aluminum specialty contractor in Sarasota County. He was not registered or licensed to practice contracting in Charlotte County where Mr. Allstaedt lived and where the porch was to be constructed. On December 28, 1981, the Respondent obtained building permit number 72030 from the Charlotte County Building and Zoning Department to construct a "Florida room" for Mr. Allstaedt's mobile home, the same room to be constructed by Mr. Berbert. Under Charlotte County Ordinances in evidence as Petitioner's Exhibits 13 and 13A, only a properly licensed "A", "B" or "C" contractor or a registered aluminum contractor can perform this type of job. The Respondent was appropriately licensed for this type of work in Charlotte County, but Mr. Berbert was not and thus could not obtain the permit in his own right. The Respondent's only connection with this job was obtaining the permit in his own name as contractor of record and in performing some minor work in replacing some damaged sheets of paneling shortly after the construction of the room addition and after the performance of the contract by Berbert. Though the Respondent listed himself as contractor in order to be able to obtain a building permit for the job, he never qualified as the contractor of record nor "qualified" Mr. Berbert's firm with the Construction Industry Licensing Board. Both Mr. Berbert and the Respondent were aware that Mr. Berbert could not legally perform contracting in Charlotte County at the time the Respondent obtained the building permit on Berbert's behalf.
Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the evidence of record and the candor and demeanor of the witnesses, it is, therefore RECOMMENDED: That the contractor's license of Jack A. Martin be suspended for a period of ten (10) years, provided however, that if he makes full restitution to the Sullivans of all monies they expended for labor, materials and permits to enable them to complete the work he had contracted to perform, within one year from a final order herein, that that suspension be reduced to three (3) years after which his license should be reinstated. DONE and ENTERED this 27th day of April, 1984, in Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of April, 1984. COPIES FURNISHED: Charles P. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Mr. Jack A. Martin 305 Park Lane Drive Venice, Florida James Linnan, Executive Director Florida Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Fred M. Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301