Findings Of Fact In June 1984, Clark Vargas applied for a permit with the Department of Environmental Regulation for activities in the waters of the state. The application stated that the proposed activity was to construct a soil road 700 feet long and constructed of 2,000 cubic yards of fill to be deposited landward of the mean high water line. The roadway proposed was to have Geotextile Fabric placed over it, and would have fifteen inch culverts for cross flow. The purpose of the road was to allow 8 property owners to have automobile access to their lots. Attached to the application was a copy of a larger engineering drawing of the project, reduced to letter size paper. The larger drawing C in evidence as Responder's Exhibit 1, and the original application is in evidence as Respondent's Exhibit 2. The drawing depicts the construction that is proposed, and in the notes states that the mean high water line is 1.1 feet above mean sea level. The drawing (Respondent's Exhibit 2) shows a number of elevation readings along the road. The elevation readings on the land upon which approximately one half of the road is to be located, the southerly portion closest to Julington Creek, and adjacent to lots 19 through 26, are all below the elevation of mean high water. The data as to the mean high water elevation for the note on the drawing was obtained by Mr. Vargas from the Corps of Engineers. The elevations on the road were the elevations measured by a survey caused to be conducted by Mr. Vargas starting from a U.S.G.S. benchmark three quarters of a mile away. The survey was conducted by a registered land surveyor. Mr. Vargas stated that the survey was not meant to be a survey to establish mean high water, and that it was intended to determine a price and plan for construction. In Mr. Vargas's professional opinion, the survey was not adequate to establish the mean high water line. Timothy J. Deuerling, an Environmental Supervisor I for the Northeast District, visited the site of the project in the summer of 1984. He saw water throughout the area. He developed the initial opinion that the project was landward of the mean high water line. When he returned to the office, he looked at the small attached drawing and decided that the project appeared to be mostly landward of the mean high water line. The elevations are very unclear on the reduced size version attached to the application. Mr. Deuerling's statement as to the mean high water line is contained in Respondent's Exhibit 4. It is the finding of the Hearing Officer that the drawing was so small and the elevations so unclear that Mr. Deuerling's opinion as to the mean high water line in Exhibit 4 is not reliable, and is rejected. Jeremy G. Tyler, Environmental Supervisor of the Dredge and Fill Section, North East District, said that the conclusions contained in the Intent to Deny and Final Order of Denial, Respondent's Exhibits 7 and 6, that one-third of the fill was to be placed waterward of the mean high water line, was based upon the data provided to DER by Mr. Vargas, Respondent's Exhibit 2. Mr. Tyler said that it is very hard to determine mean high water line by site inspection, and that he credited the survey as better evidence. It is she finding of the Hearing Officer that the location of the mean high water line has not been established by the evidence. This finding is not based upon the testimony of Mr. Vargas, however. Mr. Vargas did not present any evidence that the standard for mean high water, which was obtained from the Corps of Engineers, was inaccurate, and he did not present any evidence that the survey elevations on the drawing were inaccurate. There is good reason to believe that the proposed road in this case may be, at least with respect to the one half from lots 19 through 26, waterward of the mean high water line. The evidence shows there is an elevated ridge along the edge of the canal, that this ridge was caused by deposit of dredged material when the canal was dredged in the 1950's or 1960's, and that the ridge has eroded in places, and the water from the canal and Julington Creek floods much of the area from time to time through low places in the ridge. The engineering drawing, however, runs a series of elevation readings across only two places on the ridge, and in both cases there is at least one reading above mean high water level. Further, the only reading at a spot directly on the open water is at the southerly end of the proposed road, and it also is above mean high water. It is possible, therefore, that although portions of the road are below mean high water elevation, these portions may be completely surrounded by higher ground. It is also possible that the several low spots on the canal ridge bring the mean high water line to the road itself. On this record, it is not possible to conclude where the mean high water line is. The site of the proposed road and surrounding lots are located in a hardwood swamp associated with Julington Creek in Duval County. The land upon which the road would be built is heavily wooded. Julington Creek is Class III waters of the state. The land upon which the road is to be built is the landward extent of the waters of the state. All of the Petitioners stipulated at the hearing that the Department of Environmental Regulation has jurisdiction to require a permit for fill pursuant to Chapter 403, Florida Statutes. The proposed project would result in the placement of silica fill upon a strip of wetlands described above measuring 25' by 702.5', which is 17,562.5 square feet, plus four driveway pads to lots measuring 25' by 30', for an additional 3900 square feet, for a total of 20,562.5 square feet, which is 0.47 of an acre. (An acre is 43,560 square feet.) The sand of the roadway and driveway pads will not pollute the waters of the state. The sand of the road will not increase biological oxygen demand or nutrients. During construction, turbidity could be increased if high waters are experienced and the area is not properly stabilized, but turbidity could be monitored and controlled. The materials of the roadway further will not depress the oxygen levels in Julington Creek. The project originally proposed that seed and fertilizer be used to stabilize the banks of the road, and fertilizer would contribute to nutrients in the waters of the state, but Petitioners at the hearing gave reasonable assurances that seeding could be accomplished without fertilizer by using burlap and seed. The roadway itself will also not generate unlawful bacteria that could make its way to the waters of the state. The road will disturb the biological integrity of the organisms living in the soil beneath the roadway and driveway pads. The proposed project will permanently destroy 0.47 of an acre of the wetlands associated with Julington Creek. These and adjacent wetlands function as a natural kidney, cleansing the water of pollutants, in a continuous cycle. Wetlands contain soil and living organisms that, in balance, filter out pollutants, assimilate nutrients, and provide habitat for organisms. The silica road proposed by Petitioners will not perform these functions. Petitioners presented no evidence to rebut these findings, except to argue that the loss of wetland was insignificant and to argue that wetlands, at times, will also cause pollution. Petitioners gave no other reasonable assurances that the long-term effects of the road would not degrade water quality. The exchange of water, which results in the natural filtration and cleansing described above, occurs from waters coming from the uplands, from the wetlands, and from open waters such as Julington Creek. Julington Creek is tidal, and the testimony indicated that with significant regularity the wetlands associated with this proposed road were inundated with water. In a natural state, wetlands will experience dry conditions. During such periods, which are natural and cyclical, water will drain from the swamp and there can be a natural depression of oxygen levels in the open waters, increasing suspended solids. While these facts are true, Petitioners did not present evidence to show with particularity whether this had occurred or to what extent this had occurred with respect to the wetland area where the road is to be located, and did not show with particularity how removal of these wetlands by constructing this road would prevent natural degradation of the water in the future. Moreover, whether or not the natural filtration system of a wetland becomes less efficient due to natural cycles is not relevant in this case. Petitioners here do not propose to replace nature's cyclical inefficiencies with a better, manmade system, but propose, rather, to remove a significant portion of the only filter now operating, without replacement. The entire Julington Creek drainage basis is 30 or 40 square miles. The relevance of this figure was not established, since from the map which is Respondent's Exhibit 9 it is clear that the drainage basis of Julington Creek, with its associated wetlands, serves to filter pollutants from an equally large, if not larger, upland area. Petitioners argue that removal of 0.47 acre is insignificant if the entire area is 30 to 40 square miles, but from Respondent's Exhibit 9 it is evident that much of that other part of the wetland is not available to function as a filter for the waters currently filtered by the wetlands in the vicinity of the pro- posed roadway. The proposed road is near the conjunction of Julington and Durbin Creeks, and near the place where the open waters enlarge. The wetlands of the proposed road would be expected to serve the filtration function for those open waters and the uplands immediately above the wetlands, and not some other part of the 30 or 40 square miles. The land at the headwaters of Julington Creek is now being developed for multifamily housing and industrial uses, and the whole watershed of the Creek is being developed. The waters of Julington Creek have already been stressed in a general way by this development. Petitioners Vargas, Mrs. M. E McCullough, Dr. Robert L. Barksdale, and Mr. Steve Scecere, all testified at the hearing, and own, respectively, lots 22, 21, 19, and 24. All testified that they intend to build houses on their lots, but have not yet applied for permits. Since 1977, the Department of Environmental Regulation has consistently taken the position that deposit of fill on the wetlands which are the landward extent of Julington Creek will degrade the quality of the waters of the state, and have consistently acted to prohibit such fill. See Respondent's Exhibits 8, 10, and 11. The Department further has consistently told prospective buyers of this position with regard to these wetlands. Of particular relevance to this application, in 1977 the Respondent denied a fill permit to place 2,500 cubic yards of fill on lot 20 as depicted on Respondent's Exhibit 1. This lot is now owned by Debra H. Prevatt, and is contiguous to lot 19 owned by Petitioner, Dr. Robert L. Barksdale. The fill proposed in 1977 would have eliminated 20,000 square feet of wetlands, approximately the same as the proposed project in this case. Petitioner proposes the finding that the Corps of Engineers stands ready to issue their permit pending resolution of their application by the Department of Environmental Regulation. This finding is based solely upon the testimony of Mr. Vargas as to the intentions of unnamed officials in the Corps of Engineers, and as such, is hearsay. Therefore, absent direct evidence on the point, the proposed finding is rejected. Petitioners propose a finding that the permitting process progressed "without negative feedback" until objections were raised by adjacent property owners. This finding was not supported by any evidence other than the opinion of Mr. Vargas, and will be rejected as unsupported and possibly hearsay. It is also rejected as irrelevant since there was no evidence that the Respondent denied the permit for reasons other than those provided by statute and regulation. The Petitioners have paid taxes on their property, are of the opinion that they cannot build on their land if the permit is denied, and would be willing to sell their land to the state for a reasonable amount if the permit is denied. Respondent has not placed a monetary value on the wetlands which Petitioners propose to fill. If Petitioners proposed to build the road on pilings, elevated above the wetlands so that most of the wetlands would continue to function, the application would be approved.
Recommendation It is therefore recommended that the application for a dredge and fill permit to construct the road and driveway pads as proposed by Petitioners be DENIED. DONE and ORDERED this 1st day of March, 1985, in Tallahassee, Florida. WILLIAM C. SHERRILL, JR. Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 1st day of March, 1985. COPIES FURNISHED: Clark Vargas, P.E. President C. Vargas & Associates 8596 Arlington Expressway Jacksonville, Florida 32211 M. E McCullough 9139 Warwickshire Jacksonville, Florida 32217 Steve Scecere 9058 Kentism Court Jacksonville, Florida 32217 Dr. Robert L. Barksdale 2423 Acadie Jacksonville, Florida 32205 Ross Burnaman, Esq. Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Victoria Tschinke, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant findings of fact are made. Chandler sought exemption from permitting requirement from the Department to perform certain dredging in two artificial dead-end canals located in Placida Point Subdivision (formerly Porto-Fino Subdivision), Charlotte County, Florida. The Department has denied the exemption on the basis that "the proposed work indicates that it is not for maintenance purposes, and therefore, it does not fit the maintenance exemption". The dredging proposed by Chandler would remove the existing earthen plugs between Coral Creek (an adjacent creek) and the two canals. Coral Creek is a natural body of water and is waters of the State. The two canals were excavated (constructed) during the latter part of 1969 and early 1970 (before April 1970). Although no original design specifications were offered into evidence, there is sufficient competent evidence to show that at the time the canals were constructed earthen plugs were left between the canals and Coral Creek which restricted the water exchange between the canals and Coral Creek. The exchange of water apparently occurred at mean high water, and navigation, if any, was restricted to small boats. Porto-Fino Realty Co., Inc., (Porto-Fino) developed the Porto-Fino Subdivision in 1971, and in early 1971 applied to the Board of Trustees of the Internal Improvement Trust Fund (Board) for a dredge permit to connect the certain existing canals, which included the canals in question, to Coral Creek. As part of the application review, a site inspection was made, and it was found that the earthen plugs left between Coral Creek and the canals when they were constructed allowed water to ebb and flow during periods of high tide. As a result of this site inspection, it was recommended that before any further consideration be given the permit application, that the applicant be advised that the canals had to be adequately diked. The record is not clear on whether this permit was granted, but apparently it was not because this subject was raised again in 1974 with Lou Fusz Motor Company, the present owner of Porto-Fino Subdivision, by the Board and the Department of Army, Corps of Engineers (Corps). Apparently, it was determined by the Board, and possibly by the Corps, that the plugs had washed out and needed to be repaired. In 1975, at the request of the Board, the earthen plugs were repaired and culverts placed in the plugs to allow flushing of the canals. The earthen plugs are presently in existence in the mouth of the canals, and are colonized by mangroves, Brazilian pepper and Australian pine. The mangroves are mature trees 10-15 feet in height, and approximately 10-15 years old. The plugs do not show any signs of any recent dredging in or around the mouths of the canals. The plugs form a barrier to navigation between the canals and Coral Creek. The canals have not been used for navigational access to Coral Creek since they were repaired in 1975. The canals have not been previously dredged to maintain navigational access for boat traffic to Coral Creek, and are not presently used for navigational access to Coral Creek. There is sufficient competent substantial evidence to establish facts to show that the earthen plugs, as they presently exist, are man-made barriers that separated the two canals from Coral Creek. There is insufficient evidence to show that the repair of the earthen plugs in 1975 by the developer was illegal. The repair of the earthen plugs in 1975 by the developer was necessary because the original plugs had not been properly constructed or had washed out over the period of years. Coral Creek and the canals in question are surface waters of the state as defined in Rule 17-312.030(2), Florida Administrative Code. Canals which are used for navigation have to be periodically dredged to maintain navigational access. There is sufficient competent substantial evidence to establish facts to show that the dredging proposed by Chandler would not be "maintenance dredging" as contemplated by Rule 17-312.050(1)(e), Florida Administrative Code.
Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: Petitioner David M. Antoniak is the owner of property located at 1211 Hardman Drive in Orlando, Florida. The property fronts on a cove of Lake Lancaster and is adjacent to a stormwater drainage pipe operated by Orange County. When petitioner purchased the property in approximately February of 1978, the general waterfront around his property, as described by petitioner and other neighboring landowners, was filled with weeds which were decaying, trash and other debris, bad odors and bugs. Petitioner attempted to clean up the waterfront area, but was unsuccessful. In August of 1978, petitioner undertook the project which is presently in dispute. He removed approximately two truckloads of muck, weeds and debris from the water and the water's edge, placed a cypress log retaining wall between his property and the waters of Lake Lancaster, placed approximately one truckload of beach sand between the wall and the water, deposited an undetermined amount of fill material landward of the wall and put sod on the soil landward of the wall. Petitioner constructed the cypress log retaining wall in order to level out his lot, prevent runoff to the lake and to separate the dirt from the sand. He continues to fertilize his lawn and to spray it for bugs. The only portion of the retaining wall and property waterward of the natural ordinary high water line of Lake Lancaster is an area approximating eight by four feet. In March of 1979, petitioner applied to the DER for after-the-fact approval of construction of the retaining wall waterward of the ordinary high water line of the lake and the filling. After a field evaluation, DER gave notice of its intent to deny a permit. Lake Lancaster is a Class III body of water. The lake receives outfall from approximately twelve stormwater drainage pipes, one of which is located adjacent to petitioner's property. Aquatic plants and weeds are especially beneficial near such outfalls because they serve to assimilate and eliminate nutrients, stabilize sediments, and filter out suspended materials. Such vegetation also provides a habitat for fish. Although the area in dispute is small, removal of the aquatic vegetation significantly degrades the water quality of Lake Lancaster because of the area's location in a cove and the adjacent stormwater drainage pipe. The placement of the cypress log retaining wall will cause hydrological changes in the nature of increased turbidity due to wave action. Vertical walls may also lead to erosion. While the seawall will serve to reduce the initial flush of run off (of grass clippings, for example), fertilizers and bug sprays used on adjacent upland property will still percolate into the soil and eventually run off to the lake. The backfilling in the 8 by 4 foot space waterward of the ordinary high water level reduces the size of the lake and could possibly relate to flooding problems.
Recommendation Based upon the findings of fact and conclusions of law recited herein, it is recommended that the petitioner's application for a permit be DENIED. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 9th day of October, 1980. DIANE D. TREMOR Hearing Officer Division of Administrative Hearings 101 Collins Building Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 9th day of October, 1980. COPIES FURNISHED: William A. Harmening Stanley, Harmening and Lovett Post Office Box 1706 Orlando, Florida 32802 Charles G. Stephens Assistant General Counsel Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 David M. Antoniak 1121 Hardman Drive Orlando, Florida 32806 Jake Varn, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301
The Issue This proceeding concerns a Consent Order entered into by the Department of Environmental regulation (DER), and James and Patricia Gratzer (Gratzers) regarding an allegedly unpermitted fill in Winter Springs, Florida. The ultimate issue for determination is whether DER abused its discretion in resolving the alleged violations by entering into the subject Consent Order.
Findings Of Fact In the fall of 1990, the Gratzers purchased a 4.35 acre lot located at 216 Stoner Road in Winter Springs, Florida. At the time of purchase, the Gratzers planned to divide the lot and build a residence on the two acre parcel. In preparation for construction of their new home, the Gratzers approached the Winter Springs City Council to subdivide the property and to approve of use of the fill road as ingress and egress for both lots. In February of 1991, the Gratzers and their builder obtained the proper building permits from the County and septic tank permits from the Department of Health and Rehabilitative Services. Construction began on the residence on April 9, 1992 when the Gratzers' builder brought in several trucks of dirt to the end of the existing fill road to begin the house pad. At the time the Gratzers began construction on the subject lot, they had no idea or reason to believe that they were about to build in jurisdictional wetlands of the State of Florida. On approximately April 14, 1992, the Gratzers were first made aware that they may have problems with potential wetlands on the property when an officer of the Game and Fresh Water Fish Commission visiting the site instructed the builders to halt construction, pending a review by DER. As a result of the site visit, the Gratzers investigated further with DER employees the potential wetlands on their property. They also sought the advice of an attorney and his environmental consultant regarding possible ways to solve DER's concerns. On approximately April 26, 1991, an employee of DER visited the site and made an initial determination that the property was a jurisdictional wetland subject to permitting by DER. Under present rules the Gratzer property, with exception of the filled access road, would all be in DER jurisdictional wetlands if only the natural vegetation were considered. Upon being informed of DER's initial determination, the Gratzers hired an engineer from Boyer-Singleton & Associates to make an engineering determination as to the extent of jurisdictional wetlands based upon a ten-year backstop. A ten-year backstop is a method provided by statute to determine the ultimate landward extent of DER's vegetational jurisdictional line. It is a hydrological calculation to determine water elevation levels in a certain area, subject to the ten-year recurrent storm event. By rule and statute, DER's jurisdiction over wetlands effectively stops at the upper end or limit of the ten-year flood elevation line. Claude Cassagnol, of Boyer-Singleton and Associates, an expert in hydrology, reviewed available materials, visited the site and made an initial determination of the ten-year backstop on the Gratzers' property, and ultimately mapped out his conclusions on a plat. Mr. Cassagnol's hydrological study, and his review of Federal Emergency Management Agency (FEMA) materials, led him to conclude that the ten-year backstop would leave the Gratzer's house pad out of any DER jurisdictional wetlands. As a result of his study, Cassagnol forwarded several letters to George Baragona of DER requesting that Mr. Baragona, an expert hydrologist, review his determination and ratify his conclusions. The Gratzers, on advice of counsel, allowed their building contractor to complete compaction of the house pad and begin preparations to pour the house floor. The septic tank contractor for the Gratzers completed installation of the tank and drain field prior to July 1st. After the Gratzers had recommenced construction, on approximately July 10, 1992, DER, issued a Notice of Violation (NOV) which ultimately formed the basis for the Consent Order in this case. The Gratzers immediately ceased further construction on the property and sought further negotiations with DER. Shortly after the NOV was issued, George Baragona reviewed the information, studies and plats submitted by Mr. Cassagnol regarding the ten-year backstop. Baragona made a determination of the ten-year backstop at a point more landward than Cassagnol's. It appears from the plat submitted at hearing, that Baragona's ten- year backstop line runs along the base of the fill roadway; his testimony, however, indicated that his backstop line dipped in and out near the roadway, and he simply chose the baseline of the fill road as his "worst case scenario". Baragona, because of the house pad, was required to extrapolate a line through the house pad, resulting in approximately half of the house pad area being in jurisdictional wetlands. The result of further negotiations between the parties was the Consent Order which is the subject matter of this proceeding. As settlement, the Gratzers agreed to Baragona's "worst case scenario" ten-year backstop, placing approximately half of the house pad was in DER jurisdictional wetlands. As part of the settlement, the Gratzers agreed to, and have paid, a fine of $1,400.00 to DER and have granted a conservation easement over a large portion of the remainder of their property, resulting in an 11.6 to 1 ratio of conservation easement to impacted wetlands, slightly above DER's guideline 10 to 1 ratio. In investigating the alleged violations at the subject property, DER reviewed the cumulative impacts of the project and determined that they were not great, in light of the surrounding area and its already high level of development. In making this determination, DER reviewed property lists, maps and other facts to determine the level of current development. In reviewing the alleged violations, DER also considered whether or not this project would have been able to get a permit had the Gratzers sought a permit prior to any construction. It was DER's determination that the project would have been permittable under the criteria in Chapter 403, in conjunction with the mitigation offered at the site. Finally, in its review and study of the alleged violations, DER determined there was no evidence that this project would have any adverse impact on water quality. DER made a determination that this was a "low to medium" violation, and that the impacts were properly addressed through the Consent Order which imposed the $1,400.00 fine and secured the conservation easement. Fill Road Issue A small road or driveway existed on the site at the time the Gratzers purchased the property, extending from Stoner Road from the south, to the center of their property. Although Baragona indicated the DER modelled backstop line did not always extend to the driveway, he said it sometimes appeared to "bump up" to the eastern edge of the driveway. Baragona could not say with absolute certainty where the 10 year backstop would be on the east side of the site if the driveway were not present. The type of wetland vegetation on the Gratzer property would be considered jurisdictional wetland vegetation under rules adopted pursuant to the 1984 Warren F. Henderson Wetlands Act (Section 403.91, et seq.), but would not be considered jurisdictional wetland vegetation under rules applicable prior to October 1, 1984. If the driveway on the Gratzer property was installed prior to October 1, 1984, it is legal, but if it was installed after that date it is illegal because there is no evidence it ever was properly permitted. DER does not allow illegally filled areas to cut off the extent of its wetland jurisdiction. Therefore, if the driveway on the Gratzer property were placed in DER jurisdictional wetlands without a permit, the road itself could not act as a 10 year backstop cutting off DER wetland jurisdiction to the west. There was conflicting evidence as to when the driveway was placed on the property. James Hartman, who sold the property to the Gratzers, testified he built the driveway in 1978 and 1979. William Kuyper, an expert in aerial photography interpretation, testified that based on his review of aerial photos, the road had been placed on site sometime between January 6, 1986, and March, 1989. The weight of the evidence indicates the driveway was probably placed on site before October 1, 1984, and therefore did not require a DER permit. First, the former landowner's testimony that he built the road in 1978 and 1979, must be considered more reliable than an interpretation of aerial photos taken from 12,000 feet in the air, in spite of the expertise of the photographic interpreter. A possible explanation for why the driveway "appeared" in the 1989 aerial photo but not in the 1986 aerial photo is that the road may have been disturbed, or new fill put on the road sometime between 1986 and 1989, causing the road to be more visible in 1989. Even if the 10 year backstop were to be determined without the driveway present, it would not be significantly different. While DER's 10 year backstop line "bumps up" against the road in places, it does not "bump up" in other places along the driveway, but in order to be conservative the line was placed along with driveway in all areas. The modelled location of the line north of the housepad where there is no driveway is consistent with where the line is modelled south of the housepad where the driveway is located. The Society and its Concerns The Society's corporate status was not controverted. CFWS members have been patrolling the Lake Jessup/Gee Creek area and other wetland areas and have found what they believe are violations of the law and rules intended to protect wetland resources. Although neither Michael Mingea nor his expert witness have been on the Gratzer property, they have been in the immediate area and are concerned about the cumulative impact of small dredging projects, like the Gratzers, which projects are routinely reported to DER by the Society. Beginning in May 1991, the Society corresponded regularly with Secretary Browner at DER and Secretary Williams at the Department of Health and Rehabilitative Services (HRS) and their respective staffs, regarding what the Society perceived were violations occurring through lax enforcement. The Society believed, though review of HRS and DER files, that the Gratzers' project included a septic tank placed in jurisdictional wetlands. This was not established; rather, the septic tank was erroneously placed inside a setback line, but outside the jurisdictional line, and a variance was readily obtained from HRS. DER does not have direct jurisdiction over septic tank permits and HRS' authority is derived from the statutes, not from DER. The Society's position regarding the Gratzer project is based in substantial part on its assertion that the fill road was illegally placed and that DER's jurisdiction extended through the entire property. The Society, however, did not rebut the sound evidence by George Baragona of the 10-year backstop. Nor did it present competent evidence of any alleged water quality violations. Only one other actual violation of permit requirements was established, and DER has required the developer to move the project from jurisdictional wetlands.
Recommendation Based on the foregoing, it is hereby, recommended that the Consent Order that is the subject of this proceeding be adopted as Final Agency Action. RECOMMENDED this 24th day of July, 1992, in Tallahassee, Leon County, Florida. MARY CLARK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of July, 1992. APPENDIX TO RECOMMENDED ORDER, CASE NO. 92-0104 The following constitute specific rulings on the findings of fact proposed by Petitioners: 1.-3. Adopted in preliminary statement and paragraph 19. 4. Adopted in substance in paragraph 5. 5.-6. Rejected as unnecessary. 7.-8. Adopted in substance in paragraph 14. 9.-12. Rejected as unnecessary. 13. Adopted in part in paragraph 20, otherwise rejected as unnecessary. 14.-16. Rejected as unnecessary. 17.-18. Rejected as contrary to the evidence. 19. Rejected as contrary to the greater weight of evidence. 20.-22. Rejected as unnecessary. 23.-25. Rejected as contrary to the evidence. 26. Rejected as unnecessary. 27.-30. Rejected as contrary to the evidence. 31.-32. Rejected as summary of testimony or argument, rather than findings of fact. 33.-34. Rejected as contrary to the weight of evidence. 35.-36. Rejected as unnecessary. 37. Rejected as contrary to the evidence. [Section VI, pp 19-22 includes unnumbered paragraphs summarizing testimony, rather than findings of fact]. COPIES FURNISHED: Michael W. Mingea, President Central Florida Wetlands Society P.O. Box 2826 Orlando, FL 32802 Rex D. Ware, Esquire P.O. Box 1794 Tallahassee, FL 32302 Douglas H. MacLaughlin, Esquire DER-Twin Towers Office Bldg. 2600 Blair Stone Road Tallahassee, FL 32399-2400 Carol Browner, Secretary DER-Twin Towers Office Bldg. 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, Esq. DER-Twin Towers Ofc. Bldg. 2600 Blair Stone Road Tallahassee, FL 32399
The Issue As to Case 92-1751DRI whether Building Permit No. 9110002865 issued by Monroe County, Florida, to Ronald and Patricia LaCroix as owners and Pierce Construction and Builders as contractor for the construction of a dock is contrary to the provisions of Chapter 380, Florida Statutes, the Monroe County Comprehensive Plan and the Monroe County Land Development Regulations. As to Case 92-3949DRI whether Building Permit No. 9110003422 issued by Monroe County, Florida, to David Goodridge as owner and Pierce Construction and Builders as contractor for the construction of a dock is contrary to the provisions of Chapter 380, Florida Statutes, the Monroe County Comprehensive Plan and the Monroe County Land Development Regulations. As to Case 92-5582DRI whether Building Permit No. 9210004503 issued by Monroe County, Florida, to Dick and Jean Madson as owners and Mark W. Milnes Construction as contractor for the construction of a dock is contrary to the provisions of Chapter 380, Florida Statutes, the Monroe County Comprehensive Plan and the Monroe County Land Development Regulations.
Findings Of Fact Petitioner is the state land planning agency charged with the responsibility to administer the provisions of Chapter 380, Florida Statutes, and the regulations promulgated thereunder. Petitioner has the authority to appeal to the Florida Land and Water Adjudicatory Commission any development order issued in an area of critical state concern. Each appeal in this consolidated proceeding was timely and each involved a development within the Florida Keys Area of Critical State Concern as designated under Sections 380.05 and 380.0552, Florida Statutes. Monroe County is a political subdivision of the State of Florida and is responsible for issuing development orders for development in unincorporated Monroe County. Monroe County issued the development orders that are the subject of this appeal. Respondents, Ronald and Patricia LaCroix, are the owners of real property known as Lot 43 Saddlebunch RV Park on Saddlebunch Key in unincorporated Monroe County. On December 12, 1991, Monroe County issued building permit 9110002865 to Mr. and Mrs. LaCroix as owners and to Pierce Construction and Builders as general contractors, to build a boat dock on the subject property and extending beyond the mean high water mark into a man-made canal. At the point that the boat dock would terminate, the canal is more than twenty feet wide and is more than four feet deep at mean low tide. The canal extends throughout the Saddlebunch RV Park. Respondent, David Goodridge is the owner of real property known as Lots 38 and 39 Saddlebunch RV Park on Saddlebunch Key in unincorporated Monroe County. On March 20, 1992, Monroe County issued building permit 9110003422 to Mr. Goodridge as owner and to Pierce Construction and Builders as general contractors, to build a seawall and boat dock on the subject property and extending beyond the mean high water mark into a man-made canal. At the point that the boat dock would terminate, the canal is more than twenty feet wide and is more than four feet deep at mean low tide. The canal extends throughout the Saddlebunch RV Park. Respondents, Dick and Jean Madson are the owners of real property known as Lot 38, Section D, Sugarloaf Shores subdivision, Sugarloaf Key in unincorporated Monroe County. On May 13, 1992, Monroe County issued building permit 9210004503 to Mr. and Mrs. Madson as owners and to Mark W. Milnes Construction as general contractors, to build a dock and davits on the subject property and extending beyond the mean high water mark into a man-made canal. At the point that the boat dock would terminate, the canal is more than twenty feet wide and is more than four feet deep at mean low tide. The canal extends throughout Sugarloaf Shores subdivision. Monroe County's comprehensive plan, which has been approved by the Petitioner and by the Administration Commission, is implemented through its adopted land development regulations, codified in Chapter 9.5, Monroe County Code. Section 9.5-345(m)(2), Monroe County Code, referred to as the four foot rule, provides as follows: (2) All structures on any submerged lands and mangroves shall be designed, located and constructed such that: * * * No structure shall be located on submerged land which is vegetated with sea grasses except as is necessary to reach waters at least four (4) feet below mean low level for docking facilities; No docking facility shall be developed at any site unless a minimum channel of twenty (20) feet in width where a mean low water depth of at least minus four (4) feet exists; Section 2.104, Nearshore Waters, Monroe County Comprehensive Plan, Volume II, Future Land Use Element, provides, in pertinent part, as follows: The Florida Keys are dependent on nearshore water quality for their environmental and economic integrity. The heart of the Florida Keys economy, the means by which Monroe County exists as a civil and social institution, is based on its unique oceanic character. If nearshore water quality is not maintained, then quality of life and the economy of Monroe County will be directly and immediately impacted. OBJECTIVES 1. To protect, maintain and, where appropriate, to improve the quality of nearshore waters in Monroe County. * * * POLICIES 1. To prohibit land use that directly or indirectly degrade nearshore water quality. * * * To prohibit the development of water dependent facilities, including marinas, at locations that would involve significant degradation of the biological character of submerged lands. To limit the location of water-dependent facilities at locations that will not have a significant adverse impact on off-shore resources of particular importance. For the purposes of this policy, off-shore resources of particular importance shall mean hard coral bottoms, habitat of state or federal threatened and endangered species, shallow water areas with natural marine communities with depths at mean low tide of less than four (4) feet, and all designated aquatic preserves under Florida Statutes section 258.39 et seq. Section 9.5-4(W-1), Monroe County Code, provides as follows: (W-1) "Water at least four (4) feet below mean sea level at mean low tide" means locations that will not have a significant adverse impact on off- shore resources of particular importance. For the purposes of this definition, "off-shore resources of particular importance" shall mean hard coral bottoms, habitat of state or federal threatened and endangered species, shallow water areas with natural marine communities with depths at mean low tide of less than four (4) feet, and all designated aquatic preserves under Florida Statutes section 258.39 et seq. Benthic communities exist in the waters between the two canals and deep water, such as rock-hard bottom, sea grasses, algae, and hard coral. Turtles, manatees, sharks, stingrays, eagle rays, snapper, pink shrimp, mullet, and other marine animals populate the Sound. Sea grass beds play an important role in water quality maintenance in the Keys through filtration, nutrient uptake, stabilization of the bottom, and as a habitat for commercially important species. Neither the canal system for Saddlebunch RV Park nor the canal system for Sugarloaf Shores subdivision has access to deep water without crossing areas of water in Sugarloaf Sound with depths of less than four feet at mean low water. Many of these shallow areas contain sea grass beds. The operation of motor driven boats may result in damage to sea grass beds and shallow water marine communities through prop dredging if boats were to attempt to cross these shallow areas. Although there is evidence of prop dredging in parts of these shallow waters, it was not shown that the damage was done by boats traveling from these canal systems and deep water. Whether boats that may be docked at these sites if these permits are granted will cause damage at some future time to some portion of the shallow waters of Sugarloaf Sound between the canal systems and deep water is speculation. Since 1986, Monroe County has adopted an interpretation of Section 9.5-345(m)(2), Monroe County Code, and of Section 2.104, Nearshore Waters, Monroe County Comprehensive Plan, Volume II, Future Land Use Element, that would permit the construction of each of the subject projects. That interpretation permits the development of marginal seawalls, vertical bulkheads and docks in subdivisions that were under development in 1986 if the proposed structure would terminate in a channel more than 20 feet wide with water more than four feet deep at mean low tide. The structures that are the subject of this proceeding meet that permitting criteria. Monroe County's interpretation of the so-called "four foot rule" is that the rule was intended to restrict the development of boating access facilities in new, undeveloped subdivisions and to regulate proposed expansion of existing marinas and the development of new marinas. Monroe County's interpretation of its rules is that the type development at issue in this proceeding, constructed on an individual family home-site, would have minimal effect on the nearshore water environment of critical state concern. Monroe County considers the subject applications to meet all of its permitting criteria. Respondents presented evidence that several similar projects were permitted at approximately the same time as the subject permits were issued without Petitioner filing an appeal. This evidence was insufficient to establish that Petitioner should be estopped to appeal the subject permits, that Petitioner engaged in selective enforcement of its regulatory power, or that Petitioner otherwise brought the subject appeals for an inappropriate purpose.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is recommended that the Florida Land and Water Adjudicatory Commission enter a final order which affirms Monroe County's decision to issue building permit number 9110002865, and which dismisses the appeal filed by the Department of Community Affairs that is at issue in Case 92-1751DRI. It is further recommended that the Florida Land and Water Adjudicatory Commission enter a final order which affirms Monroe County's decision to issue building permit number 9110003422, and which dismisses the appeal filed by the Department of Community Affairs that is at issue in Case No. 92-3949DRI. It is further recommended that the Florida Land and Water Adjudicatory Commission enter a final order which affirms Monroe County's decision to issue building permit number 9210004503, and which dismisses the appeal filed by the Department of Community Affairs that is at issue in Case No. 92-5582DRI. DONE AND ORDERED this 26th day of January, 1993, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON, Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of January, 1993. APPENDIX TO RECOMMENDED ORDER TO CASE NO. 92-1751DRI, CASE NO. 92-3949DRI, AND CASE NO. 92-5582DRI The following rulings are made on the proposed findings of fact submitted by Petitioner. The proposed findings of fact in paragraphs 1, 2, 3, 4, 5, 6, 8, 10, 11, and 14 are adopted in material part by the Recommended Order. The proposed findings of fact in paragraph 7 are rejected as being unnecessary to the conclusions reached. The proposed findings of fact in the first two sentences of paragraph 9 are adopted in material part by the Recommended Order. The proposed findings of fact in the last sentence of Paragraph 9 are rejected as being unsupported by the evidence. While the evidence established that damage may result, the evidence did not establish that damage would result. The proposed findings of fact in the first sentence of paragraph 12 are rejected as being unsubstantiated by the evidence since the water in the canals is deeper than four feet. The proposed findings in the second sentence of paragraph 12 are subordinate to the findings made. The proposed findings of fact in the last sentence of Paragraph 12 are rejected as being unsupported by the evidence. While the evidence established that damage may result, the evidence did not establish that damage would result. The proposed findings of fact in paragraph 13 are rejected as being subordinate to the findings made. The proposed findings of fact in the first sentence of paragraph 15 are rejected since the evidence established that Monroe County's interpretation of the four foot rule dates to 1986. The proposed findings of fact in the second sentence of paragraph 15 are rejected as being unnecessary to the conclusions reached. The remaining proposed findings of fact in paragraph 15 are adopted in material part by the Recommended Order. The proposed findings of fact in the first sentence of paragraph 16 are subordinate to the findings made. The proposed findings of fact in the second sentence of paragraph 16 are rejected as being argument. The proposed findings of fact in the final sentence of paragraph 17 (there are two paragraphs 16, the second of which is being referred to as paragraph 17) are adopted in material part by the Recommended Order. The remaining proposed findings of fact in paragraph 17 are rejected as being unnecessary to the conclusions reached. The following rulings are made on the proposed findings of fact submitted by Respondents. The proposed findings of fact in paragraphs 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 16, and 17 are rejected as being the recitation of testimony that is subordinate to the findings made. The proposed findings of fact in paragraph 12 are rejected as being contrary to the record of the proceedings. The proposed findings of fact in paragraph 13 are adopted in material part by the Recommended Order. The proposed findings of fact in paragraph 14 are adopted in part by the Recommended Order are rejected in part as being subordinate to the findings made. The proposed findings of fact in paragraph 15 are rejected as being unnecessary to the conclusions reached. COPIES FURNISHED: Lucky T. Osho, Esquire Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 Randy Ludacer, Esquire Monroe County Attorney 310 Fleming Street Key West, Florida 33040 James T. Hendrick, Esquire Morgan & Hendrick 317 Whitehead Street Key West, Florida 33040 William R. Kynoch, Deputy Director Florida Land and Water Adjudicatory Commission Executive Office of the Governor 311 Carlton Building Tallahassee, Florida 32301 Carolyn Dekle, Director South Florida Regional Planning Council Suite 140 3400 Hollywood Boulevard Hollywood, Florida 33021 Robert Herman Monroe County Growth Management Division Public Service Building, Wing III 5825 Jr. College Road Stock Island Key West, Florida 33040 Charles M. Milligan, Esquire Post Office Box 1367 Key West, Florida 33041 David and Florence Clark 4606 Wayne Road Corona Del Mar, California 92625 Edward Warren Werling Post Office Box 1042 Summerland Key, Florida 33042 Theodore W. Herzog, Esquire 209 Duval Street Key West, Florida 33040 Pierce Construction & Builders Route 4, Box 319 Summerland Key, Florida 33042 Dick and Jean Madson Post Office Box 276 Summerland Key, Florida 33402 Mark W. Milnes Route 5, Box 775-G Big Pine Key, Florida 33043 David M. Maloney, Esquire Office of the Governor The Capitol, Room 209 Tallahassee, Florida 32399-0001
Findings Of Fact On June 26, 1986, the Department of Environmental Regulation (DER) issued a permit, No. 661168901, to Elizabeth R. McSheehy authorizing construction on the shore of Choctawhatchee Bay of a seawall 165 feet long and eight feet high "faced with rip-rap . . . and backfilled with 18 cubic yards of sand fill . . . in accordance with [an] attached map and drawing." Joint Exhibit No. 1. The permit application had proposed that the seawall "TIE INTO MR. HEATH['S] SEAWALL," and the attached drawing indicated a point of beginning along the seawall already protecting the lot to the east, then owned by Mr. Heath, now owned by Prentice M. Thomas. The drawing has no compass rose and does not specify the angle of either leg of the permitted seawall. The construction permit expired December 30, 1987 (well beyond the 120 days within which the application indicated it would be necessary to complete construction, once begun.) At hearing, the parties stipulated that Ms. McSheehy had erected or caused to be erected a seawall at the location permitted on or before December 30, 1987. DER does not dispute that the seawall functioned as such when built. Seawall Fails Ms. McSheehy received a letter from Mr. Thomas dated June 6, 1990 (in an envelope postmarked June 22, 1990) stating, "I recently visited my lot at Four Mile Post and regret to inform you that the seawall you installed on your property has been demolished by the winter and spring storms." Petitioner's Exhibit No. 2. The letter reported that her "lot was eroding at a rapid pace." Id. Afraid that his own lot would be affected, despite its well-maintained seawall and rip-rap he had added, Mr. Thomas "beseech[ed her]. . . to take action to arrest the erosion of [he]r shoreline." Petitioner's Exhibit No. 2. The lot west of Ms. McSheehy's has no seawall. T. 48. Its shoreline had also eroded, judging from photographs in evidence. Soon after receiving the letter, Ms. McSheehy inspected the property for the first time since the summer before. She found the piles on which the seawall had been constructed in 1986 or 1987, now standing as far as 30 feet out in the bay. Only the eastern 20 or 30 feet of the seawall remained intact. Remnants, including individual boards and wall fragments comprised of as many as four boards had washed up on the receded shoreline. When DER's James Eric Buckelew happened on the site on July 26, 1990, he concluded from the erosion that the seawall had ceased to function as such some months before. Bay waters reached 20 or 30 feet further inland, covering about a tenth of an acre landward of what remained of the seawall. Mr. Buckelew took photographs of the site. Petitioner's Exhibit No. 1. Seawall Now in Bay Before the month ended and apparently before anybody from DER communicated with Ms. McSheehy, the seawall was rebuilt in its original location. No additional fill has been placed landward of the seawall, which now has water on both sides. In various trips to the site and otherwise in responding to this turn of events, DER has expended at least $245.37. DER advised Ms. McSheehy that a permit could be issued for construction of another seawall along what seems to be the new mean high water line, but that she had acted illegally in having the seawall restored at a location now some 20 or 30 feet out in the Bay. (T. 115). After first applying for and receiving a permit to remove the existing seawall and construct a new one further landward, she took the position that restoration of the original seawall had been lawful, and these proceedings ensued.
Recommendation It is, accordingly, RECOMMENDED: That DER make final its proposed orders for corrective action, unless within a reasonable time DNR conveys or leases to respondent the property lying between the seawall and the mean high water line. DONE AND ENTERED this 24th day of February, 1993, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 24th day of February, 1993. APPENDIX TO RECOMMENDED ORDER CASE NO. 91-7281 Petitioner's proposed findings of fact numbers 2, 3, 5, 6 and 12 have been adopted, in substance, insofar as material. With regard to petitioner's proposed finding of fact number 1, the permit issued in 1986, but it is not clear that construction was accomplished in 1986. With regard to petitioner's proposed finding of fact number 4, the seawall failed sometime between the summer of 1989 and the spring of 1990. With regard to petitioner's proposed findings of fact numbers 7, 8, 9, 10 and 11, use of the word "unauthorized" renders these proposed conclusions of law. Respondent's "proposal for the ruling of the hearing officer" did not contain separately numbered proposed findings of fact. COPIES FURNISHED TO: Virginia B. Wetherell, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Daniel H. Thompson, General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Richard L. Windsor, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32399-2400 Elizabeth R. McSheehy 516 Mooney Road Fort Walton Beach, Florida 32547
The Issue The issue in this case is whether Respondents Paul Crum, Sr., and Paul Crum, Jr. (the "Crums"), are entitled to the Noticed General Permit issued by the Department of Environmental Protection ("Department") for the construction of a single- family residential dock and associated structures.
Findings Of Fact Background The Crums are the owners of the riparian property located at 15696 Shark Road West, Jacksonville, Florida. The Crum property is adjacent to Pumpkin Hill Creek, which lies within the Nassau River-St. Johns River Marshes Aquatic Preserve. Extending from the Crum property into Pumpkin Hill Creek is an existing wood dock approximately 90 feet long and four feet wide, with a platform near the landward end of the dock. Petitioner Brooks owns the property immediately adjacent to and north of the Crum property. Petitioner Brooks has a dock and boat lift. Petitioner Cole owns the property immediately adjacent to and southeast of the Crum property. The Cole property is located on a salt marsh and has no dock. Petitioner Jones lives approximately 3,200 feet north of the Crum property, on a tributary to Pumpkin Hill Creek. Petitioner Jones has fished Pumpkin Hill Creek and the surrounding waters for over 25 years. Noticed General Permits are a type of environmental resource permit granted by rule for those activities which have been determined to have minimal impacts to water resources. Florida Administrative Code Rule 62-341.427 grants by rule a general permit to construct a single family pier, along with boat lifts and terminal platforms, provided certain specific criteria are met. In August 2005, the Crums applied for a Noticed General Permit to extend their existing dock into deeper water. The Department issued a Notice of Determination of Qualification for Noticed General Permit, but later rescinded the authorization after Petitioner Brooks complained to the Department that the landward end of the existing dock is located only 21 feet from her property boundary and, therefore, did not comply with Florida Administrative Code Rule 18-21.004(3)(d), which requires that a dock be set back a minimum of 25 feet "inside the applicant's riparian rights lines." In November 2005, the Crums re-applied for a Noticed General Permit. Their revised plans called for removal of the existing dock and construction of a new dock extending approximately 255 feet out into Pumpkin Hill Creek. The proposed dock would be located a minimum of 25 feet inside the Crums' riparian rights lines. On December 6, 2005, the Department issued a Notice of Determination of Qualification for a Noticed General Permit for the revised dock, stating that the project satisfied the requirements of Florida Administrative Code Rule 62-341.427, as well as the conditions for authorization to perform activities on state-owned submerged lands set forth in Florida Administrative Code Rule 18-21 and for activities in an aquatic preserve under Florida Administrative Code Rule 18-20. In April 2006, Petitioners filed three petitions for hearing with the Department alleging that the proposed dock significantly impedes navigation by restricting access to a tidal creek and extends more waterward than necessary to access a water depth of (minus) -4 feet at mean low water, which is prohibited for docks in aquatic preserves under Florida Administrative Code Rule 18-20.005(3)(b)3. Petitioners attached to their petitions a copy of a bathymetric survey showing the elevations of the submerged lands in the vicinity of the proposed project. In response to the information contained in the survey, the Crums revised their plans to shorten the dock to its currently proposed length of 186.56 feet. A new Notice of Determination of Qualification for a Notice General Permit was then issued by the Department on October 16, 2006. The final dock project consists of: (a) removal of the existing wood dock; (b) construction of a four-foot wide, 186.56-foot long, single family residential dock consisting of an access pier, a 12-foot by 12-foot terminal platform, and a 14-foot by 20-foot open boat lift with catwalk (the “proposed dock”). The proposed dock will terminate where the water will be four feet deep at mean low water. Navigating in and Near the Tidal Creek To the south of the Crum property is a wide expanse of salt marsh. Within the salt marsh are unnamed tidal creeks. The mouth of one tidal creek that flows to Pumpkin Hill Creek is located approximately 90 feet south of the existing Crum dock. The tidal creek is shallow and is not navigable at or near low tide. Petitioner Jones owns an 18-foot flatboat which he sometimes keeps at his residence and sometimes at Petitioner Brooks' property. The boat draws about one foot of water. Petitioner Jones uses this boat to fish in the tidal creek located near the Crum property about ten times every month. No evidence was presented to show that Petitioner Brooks or Petitioner Cole ever navigate in or otherwise use this tidal creek. There are many other tidal creeks located in the marshes associated with Pumpkin Hill Creek. Petitioner Jones boats and fishes in most of them. Petitioner Jones said that, currently, he must wait two hours past low tide for the water depth to be sufficient for him to get into the tidal creek near the Crum property. His usual course to the creek lies just beyond the end of the existing Crum dock. He claims there is a channel there, but no channel is shown on the survey or in any of the parties' photographs. After the proposed dock is constructed, Petitioner Jones' usual course to the tidal will be obstructed. He contends that the new course he would have to take to the tidal creek will take him across shallower areas of Pumpkin Hill Creek so that he will have to wait two more hours (a total of four hours) after low tide to get into the creek. Therefore, Petitioner Jones' alleged injury is the reduction of the hours available to him to navigate in and out of the tidal creek for fishing. The existing Crum dock terminates on a broad mud flat which is exposed at mean low water. However, the bathymetric survey shows the mud flat is at a lower elevation near the end of the dock so water covers this area before it covers the rest of the mud flat. However, the bathymetric survey also shows the elevation of the bottom rising as one moves south from the existing dock. At the mouth of the tidal creek the elevation is 1.0 feet NGVD (National Geodetic Vertical Datum, an official, surveyed reference point). Because the tidal creek drains into the main body of Pumpkin Hill Creek, a reasonable inference can be made that the bottom elevations in the creek generally become higher (and the water depths decrease) as one moves up the creek toward dry land. Prop scars in the exposed bottom at the end of the existing dock indicate that boats have traveled over this area when the water was so shallow that the engine props were striking the bottom. Prop scarring can cause turbidity and damage to benthic organisms. The bathymetric survey indicates that mean high water in this area of Pumpkin Hill Creek is 3.03 feet NGVD, and the mean low water is -1.78 feet NGVD. The mean tidal fluctuation between mean low water and mean high water is thus 4.81 feet. Randall Armstrong, who was accepted as an expert in navigation and piloting, explained that in this area, where there are two daily tides, the water elevation will generally increase by 1/12 of the mean tidal fluctuation in the first hour after mean low water, another 2/12 of the fluctuation in the second, and 3/12 in the third hour. Applying this general rule to the tidal fluctuation here of 4.81 feet results in an estimated 1.2-foot increase in water elevation two hours after low tide and a 2.4-foot increase three hours after low tide. Based on the mean low water elevation of -1.78 feet NGVD, the water elevation would usually be about -0.6 foot NGVD two hours after low tide and 0.6 foot NGVD three hours after low tide. Therefore, the tidal creek (with a bottom elevation of 1.0 foot NGVD at the mouth) would usually be "dry" two hours after low tide and would usually have less than a foot of water three hours after low tide. That evidence contradicts Petitioner Jones' statement that he now navigates into the tidal creek two hours after low tide. That might occasionally be possible, but the bathymetric survey indicates the creek would usually be too shallow at that time. In fact, the evidence suggests that the tidal creek is only reliably navigable without causing prop scars to the bottom by using boats with very shallow draft and waiting until high tide (or shortly before or after) when the water depth at the mouth of the creek would be about two feet. It was Mr. Armstrong's opinion that the 1.0-foot NGVD elevation at the mouth of the tidal creek determines when and how long the tidal creek is navigable, and those times would not be affected by the proposed dock. He described the new course that a boater would use to navigate into the tidal creek after the proposed dock is built. He used the bathymetric survey to show that when the water is deep enough to navigate into the tidal creek, the water depth is also sufficient to navigate the new course. The proposed dock might, as Petitioner Jones alleges, cause boaters to traverse a longer section of the mudflat then they do currently. However, the more persuasive testimony supports the Crums' position that the navigability of the tidal creek is controlled by its shallowest point at the 1.0-foot NGVD elevation and that the proposed dock will not interfere with navigation of the tidal creek by requiring boaters to traverse shallower areas. Petitioner Jones testified that he regularly navigates his boat close to the existing Crum dock. The evidence does not indicate that the proposed dock would cause an unreasonable risk of collision for boaters using the new course to the tidal creek.
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the Secretary of the Florida Department of Environmental Protection enter a final order that grants Noticed General Permit No. 16-253057-002-EG to the Crums. DONE AND ENTERED this 22nd day of December, 2006, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 22nd day of December, 2006.
Findings Of Fact In 1950, Petitioner acquired lots 8 and 9, block 23, of Lone Palm Beach subdivision, third addition, which lots front on Boca Ciega Bay in Pinellas County, and she has held the property in free simple since. Petitioner's late husband, her predecessor in title, acquired the lots in 1941. They constitute the tip of man-made peninsula jutting bayward from a barrier island bordered on the other side by the Gulf of Mexico. In 1926, the lots did not exist as such, because the peninsula had not yet been built. Petitioner's exhibit No. 10. Since the creation of the lots, their aquatic periphery has varied continually, on account of accretion and reliction. In the first half of the last decade, wooden and metal stakes were sunk along the shoreline, landward of the water's edge. Since then, water has washed away Petitioner's beach, moving the shoreline inland an average distance of approximately thirty feet. Erosion has been more severe along the northern half of Petitioner's beach than along the southern half. Seawalls have been built along adjacent properties on either side of Petitioner's parcel. The evidence did not establish what proportion of this erosion may have been attributable to the effects of Hurricane Agnes or to the location of neighboring seawalls or to any other particular cause. In 1972, the Honorable C. Richard Leavengood, Petitioner's present husband, hired Rupert Osteen, a contractor, to build a seawall. Pinellas County issued a building permit to Mr. Osteen, covering a "Seawall - 356LF - Type D," Petitioner's Exhibit No. 5, on March 14, 1973. (In September of 1951, the Town of Redington Beach had issued a building permit for "Dredging and Filling behind Sea Wall Constructed on [what is now Petitioner's] Rear Property Line.") Construction began, but came to an abrupt halt in July of 1973, when Mr. Osteen was arrested for building a seawall "without having obtained the recommendation of the Chief of Engineers and the Authorization of the Secretary of the Army prior to beginning," a criminal offense of which he was subsequently convicted in the United States District Court for the Middle District of Florida. Respondent's Exhibit No. 4. Before work on the seawall stopped, Petitioner had caused some 4,500 cubic yards of fill dirt to be deposited on the lots. After Mr. Osteen's arrest, Petitioner applied for a fill permit to the Pinellas County Commission, sitting as the Pinellas County Water and Navigation Control Authority. The Authority granted the permit on March 19, 1974, on condition that the seawall be made to tie in with the existing seawall on lot 7, which adjoins Petitioner's property to the west. On or about August 16, 1974, Petitioner applied to the Department of the Army prior to beginning," a criminal offense of which he was subsequently convicted in the United State District Court for the Middle District of Florida. Respondent's Exhibit No. 4. Before work on the seawall stopped, Petitioner had caused some 4,500 cubic yards of fill dirt to be deposited on the lots. After Mr. Osteen's arrest, Petitioner applied for a fill permit to the Pinellas County Commission, sitting as the Pinellas County Water and Navigation Control Authority. The Authority granted the permit on March 19,1974, on condition that the seawall be made to tie in with the existing seawall on lot 7, which adjoins Petitioner's property to the west. On or about August 16, 1974, Petitioner applied to the Department of the Army for a permit, pursuant to Sections 403 and 1344 of Title 33, United States Code. Petitioner applied for the "after the fact" permit at issue in these proceedings on May 10, 1974. At one point in the course of negotiations between Petitioner and Respondent, Mr. Douglas Jones, Chief of Respondent's Bureau of Permitting, indicated that Respondent would permit Petitioner to erect another seawall along the present mean high water line. Eventually, Respondent's staff notified Petitioner that it would recommended denial of an after the fact permit for the existing seawall, and Petitioner filed a request for administrative hearing, which initiated these proceedings. Aerial photographs dating back to 1942 were received in evidence. Respondent's Exhibits Nos. 5 through 11. None of these phontographs show land as far out in the water as the portion of the seawall Mr. Osteen finished. The partially completed seawall is further waterward tan the 1971 interface between land and water. Respondent's Exhibits Nos. 9 and 10. In November of 1973, Alan J. Burdette, Jr., a marine biologist, who is now employed by Respondent, inspected lots 8 and 9 of Lone Palm Beach subdivision and found water in the low area landward of the seawall. More recent photographs indicate that the seawall still stands somewhat offshore. E.g.., Respondent's Exhibit No. 16, taken on September 7, 1977. Mr. Bardette's inspection revealed oyster and fiddler crabs inside the seawall and clams just outside. Mangroves, which were not there at the time construction began, had sprung up. Removal of the seawall would create additional shallow bottom where algae, clams, oysters, mangroves and other marine life could flourish. Mr. R. S. Murali, a hydorgraphic engineer employed by Respondent, visited Petitioner's property the day before the hearing in this matter was held. While he was on the site, the wind blew from the southwest and waves with an average height between eight and nine inches struck Petitioner's unfinished seawall every 1.2 seconds. Mr. Murali discovered evidence of erosion under the seawall, which was caused by wave action. If the seawall were placed more landward, so that waves travelled up a sloping beach before striking it, the erosion problem could be significantly alleviated.
Recommendation Upon consideration of the foregoing, it is RECOMMENDED: That Petitioner's application for an after the fact fill permit authorizing the seawall which has already been constructed around lots 8 and 9, block 23, of Lone Palm Beach Subdivision, third addition, be denied. DONE and ENTERED this 30th day of November, 1977, in Tallahassee, Florida. ROBERT T. BENTON, II Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 904/488-9675 APPENDIX Paragraph one of Petitioner's Proposed Findings of Fact has been adopted, in substance, insofar as relevant:. Paragraph two of Petitioner's Proposed Findings of Fact has been adopted, in substance, insofar as relevant, except for the date of the permit issued by the Pinellas County Water and Navigation Control Authority, which is immaterial. Paragraph three of Petitioner's Proposed Findings of Fact is apparently predicated on Petitioner's Exhibit No. 12, an uncertified copy of page 74 of Pinellas County's Plat Book 20. Although a handwritten notation on the exhibit reads "Plat Recorded June 21, 1937" such extraneous handwriting on an uncertified copy is not "evidence of a type commonly relied upon by reasonably prudent persons in the conduct of their affairs.". Section 120.58(1)(a), Florida Statutes (1975). The question of the Butler Act's applicability is a question of law rather than of fact and it has not been necessary to decide the question. Paragraph four of Petitioner's Proposed Findings of Fact has not been adopted, for the most part, because of lack of support in the evidence. Paragraph five of Petitioner's Proposed Findings of fact emphasizes that the testimony as to flora and fauna related to a time considerably after application for the after the fact permit was made. While this is true, what is at issue is the ecological consequences of leaving the seawall, so that the relevant time period is the time period beginning when the application was made and extending indefinitely into the future. COPIES FURNISHED: Ms. Carol Haughey, Esq. Department of Environmental Regulation 2562 Executive Center Circle, East Montgomery Building Tallahassee, Florida 32301 Mr. Ross H. Stanton, Jr., Esq. 280 Florida Federal Building 26274th Street North St. Petersburg, Florida 33704 Ms. Patricia M. Duryee, Esq. Department of Environmental Regulation 2562 Executive Center Circle, East Montgomery Building Tallahassee, Florida 32301 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION DOROTHY B. LEAVENGOOD, Petitioner, vs. CASE NOS. 77-484 STATE OF FLORIDA, DEPARTMENT OF ENVIRONMENTAL REGULATION, Respondents. /
The Issue The issue is whether Respondent South Florida Water Management District is entitled to an environmental resource permit from Respondent Department of Environmental Protection to construct a weir in Collier County on the Merritt Canal about 3600 feet south of Interstate 75 for the purpose of extending the hydroperiod on the Florida Panther Federal Wildlife Refuge.
Findings Of Fact Proposed Permit On April 17, 1996, Respondent South Florida Water Management District (District) filed with Respondent Department of Environmental Protection (DEP) an application for the construction of a water-control structure in the Merritt Canal. The stated purpose of the structure, which is a weir, is to extend the hydroperiod of the Lucky Lake Strand. The application states that the District is the owner of a drainage easement covering the land proposed as the site of the weir. According to the application, Collier County, in which the Merritt Canal lies, originally held the drainage easement. The District later adopted the Merritt Canal as a "Works of the District," which transferred operational responsibility for the canal from the County to the District. (A sub-unit of the District, the Big Cypress Basin Board has jurisdiction for District projects of the type involved in this case. References to the District shall include the Big Cypress Basin Board.) The application requests a permit to construct an adjustable sheet-pile weir within the 80-foot Merritt Canal right-of-way. The application accurately describes the Merritt Canal as a Class III waterbody that is not an Outstanding Florida Water. By Notice of Intent to Issue Environmental Resource Permit dated January 29, 1997 (NOI), DEP proposed to issue an environmental resource permit (ERP) to the District for the construction of the Lucky Lake Strand Water Control Structure. The structure would be an adjustable weir with operating levels of 7.0 feet National Geodetic Vertical Datum (NGVD) in the wet season and 9.5 feet NGVD in the dry season. As stated in the NOI, the Merritt Canal is 12 miles long and one of four main north-south canals within a larger system of 183 miles of canals--all Class III waters-- constructed in the 1960s by Gulf American Land Corporation to drain wetlands for development of the Southern Golden Gate Estates area. These four north-south canals drain water south through the Faka Union Canal and into Faka Union Bay, which is part of the 10,000 Islands/Cape Romano Aquatic Preserve. The preserve contains Class II Outstanding Florida Waters. The NOI notes that the U.S. Fish and Wildlife Service (FWS) and District entered into an agreement in September 1994 to construct two weirs in the Merritt Canal "to partially restore historic hydroperiods into two major wetland features within the federally owned lands of the USFWS Florida Panther National Wildlife Refuge, Lucky Lake Strand and Stumpy Strand (Class III Outstanding Florida Waters)." As stated in the NOI, these federally owned wetlands constitute over 3000 acres of cypress and mixed swamps, wet prairies, marshes, and ponds. The NOI relates that FWS staff proposed the project to counteract "subtle vegetational changes and accelerated pond draw-downs [that] were taking place in the strands as a result of shortened hydroperiods caused by a three-year drought, I-75 widening activities, and subsequent canal modifications." The NOI correctly states that water in the wet season historically flowed southerly through Stumpy Strand, Lucky Lake Strand, and Picayune Strand, before entering the larger Fakahatchee Strand. Lucky Lake Strand narrows to 1000 feet at its south end, which is at Interstate 75 (I-75). The NOI accurately asserts that the construction of the Merritt Canal and the I-75 borrow canals combined to draw down the upstream wetlands, thus reducing their hydroperiods. The effect of the Merritt Canal is reportedly significant because of its confluence with the southern tip of Lucky Lake Strand. The NOI discloses that the original agreement between the District and FWS called for the construction of two weirs south of I-75, one at the headwaters of the Merritt Canal and another about 1800 feet downstream in the Merritt Canal. However, the proposed permit eliminates one weir, whose function was performed by plugs in the north I-75 borrow canal, and relocates the remaining proposed weir about 3600 feet south of I-75, rather than immediately south of I-75, reportedly because of difficulties in accessing the proposed weir at I-75. The NOI states that the Merritt Canal is within the 80-foot drainage easement originally acquired by Collier County. The uplands adjacent to the weir are reportedly owned by DEP. The NOI describes the proposed weir as a sheet pile weir with adjustable partitions. As proposed, during the wet season, the District would start to open the gates at 7 feet NGVD and start to close them at 6.5 feet NGVD. During the dry season, the District would start to open the gates at 9.8 feet NGVD and start to close them at 9.3 feet NGVD. Also, the proposed permit would anticipate that the District would dredge the canal to a trapezoidal cross-section having a bottom elevation of -1.5 feet NGVD and a width of about 49 feet at the weir and transitioning to 20-foot bottom widths upstream and downstream of the weir. According to the NOI, the purpose of the proposed weir is to reduce over-drainage of the upstream wetlands in Lucky Lake and Stumpy Strands by extending the hydroperiod further into the dry season. No increase in water levels during the wet season is expected. Although the historic extended hydroperiod is not expected to be achieved, the weir structure is expected to improve current conditions to the upstream wetlands. Holding back water in these wetlands [is] also expected to improve water quality downstream by removal of excess nutrient, sediments, and chemicals. Wildlife values are expected to be enhanced in preferred waterfowl and wading bird habitat, including areas for the endangered wood stork and threatened bald eagle. Forage areas are also expected to be improved for white-tailed deer and other wildlife species which are essential prey for the endangered Florida panther. Aquifer recharge is also expected as the ground water reserves will be raised by raising the canal water levels, while maintaining the existing level of flood protection for adjacent private landowners. The NOI states that FWS will monitor post- construction environmental conditions and will recommend to the District adjustments to the weir elevations. The NOI reports that the District will be the "main operator" of the weir to adjust elevations to maintain flood control for adjacent lands. The NOI adds: The project was designed so as not to decrease the peak discharge capacity in the canal or increase flood stages in the Upper Merritt Canal watershed. Hydraulic modeling by the District indicates that there will be no additional surface water flooding to private property as a result of the project, and the current level of service will be maintained. Based on this analysis, the NOI concludes that the District has provided reasonable assurance that the proposed activity will comply with Part IV, Chapter 373, Florida Statutes, and the underlying rules, including Chapter 62-330 and Rules 40E-4.301 and 40E-4.302, Florida Administrative Code. The NOI states that the District has demonstrated that the activity is clearly in the public interest, pursuant to Section 373.414(1)(a), Florida Statutes. The proposed permit conforms to the NOI's description. Specific Condition 13 sets the fixed crest of the proposed weir at 4.5 feet NGVD and the width of the weir at 48 feet. Although the proposed permit is nowhere explicitly conditioned on a successful wetland enhancement project, Specific Condition 12 states that "the" wetland enhancement project shall be considered successful if, after five years, Lucky Lake Strand and Stumpy Strand display wetland- appropriate vegetation and the "viability of adjacent upland sites [is] not negatively impacted by increased ground water or surface water levels resulting from the authorized project." Specific Condition 17 requires the District to document the operation of the gates and notify DEP, within three days, whenever any of the permitted elevations are exceeded. Annually, the District must supply DEP detailed data and analysis of the operational history of the weir, including "reasons for going to nonstandard operation and a narrative description of the effectiveness of initiating the nonstandard operation to include areas not flooded (or flooded, if applicable) and other associated impacts." During the final hearing, the District proposed, and DEP approved, a modification of Specific Condition 18. As modified, Specific Condition 18 requires the District to "monitor the effects of the operation" of the weir, pursuant to the revised monitoring plan incorporated by reference into this condition. The revised monitoring plan, which is dated November 12, 1997, alters the original monitoring plan by adding two sites for the installation of water-table wells. One of the new sites (Site A) is 1200 feet north of the weir, and the other new site (Site B) is 1200 feet north and 2000 feet west of the weir. These are the only water-table monitoring devices. Five other sites are surface-water monitoring sites. Three of the these sites are in the Merritt Canal: one immediately upstream of the weir, one immediately downstream of the weir, and one farther upstream at I-75. The other two surface-water monitoring sites are farther upstream. One is in Lucky Lake about 1.75 miles north of the weir, and the other is about three miles northeast of Lucky Lake. Three other sites are rainfall-monitoring sites. Two rainfall-monitoring sites are north of the weir. The site just north of I-75 is at the Ford Motor Company test track, which is immediately west of Lucky Lake and Stumpy Strands, and the site more directly north of the Merritt Canal is about ten miles north of I-75. Specific Condition 18 states the frequency with which someone (presumably a District employee or contractor) is to collect the data from these 10 monitoring sites, but contains no performance criteria. The monitoring plan thus commits the District to collecting data, but not to analyzing the data, nor, more importantly, taking specified actions when certain performance parameters are exceeded. Neither the revised monitoring plan nor the application in any way commits the District to using the data collected from the revised monitoring plan to develop a set of criteria, based on rainfall amounts, groundwater levels, and surface water levels, to fine-tune the operation of the gates so as not to exacerbate present flooding. Nothing in the revised monitoring plan or the application suggests that the District will use the data collected from the revised monitoring plan to identify more clearly the relationships between storm events and water levels to understand better the relationship between flooding, on the one hand, and the existence of the proposed weir and the operation of its gates. Faka Union Canal Watershed and Southern Golden Gate Estates What is now known as the Faka Union Canal Watershed historically covered about 234 square miles. It ran from an area about four miles north of what is now known as Immokalee Road south in a widening expanse that approached 12 miles at what is now U.S. Route 41. It then ran south until it emptied into the Gulf of Mexico at Faka Union Bay in what is now the Cape Romano Ten Thousand Islands State Aquatic Preserve east of Marco Island. Land alterations due to road and canal construction and urban and agricultural development eventually reduced the Faka Union Canal Watershed to about 189 square miles. Most noticeably, these changes narrowed the drainage area at U. S. Route 41 from almost 12 miles to little more than the width of the Faka Union Canal. The Faka Union Canal Watershed is characterized by low relief and poorly defined drainage patterns. At the north boundary of the watershed, which now ends at Immokalee Road, the elevation reaches 24 feet NGVD. Twenty-eight miles to the south, at the outlet of the basin, the elevation is two feet NGVD. The water flows generally in a southwest direction. Historically, water ran slowly through the watershed in sheetflow several miles wide and a few inches to a few feet deep. Drainage concentrated in slightly lower sloughs and strands, which generally dried out in the dry season. Historically, the watershed featured flat, swampy lands containing cypress trees, islands of pine forests, and wet and dry prairies. Prior to development, much of the watershed remained inundated by several feet of water during the five- month wet season (roughly from mid-May through mid-October). In this undisturbed state, the prominent features of the watershed were the storage of runoff in depressional areas, attenuated peak flows, and a longer hydroperiod into the dry season. In the early 1960s, Gulf American Land Corporation subdivided a 173 square-mile area in Collier County into many thousands of lots as small as 1.25 acres. The development was Golden Gate Estates. The portion of Golden Gate Estates south of I-75 is known as Southern Golden Gate Estates. Golden Gate Estates is west of the Merritt Canal. Gulf American's purpose in dredging the 183-mile canal system was to allow it to market as land, available for continuous occupation, subdivided lots superimposed over an area that was land during the dry months and water during the wet months. To achieve this objective, Gulf American Land Corporation constructed one group of canals that drains to the west and another group of canals drains to the south into the Faka Union Canal. Gulf American dredged the canals draining to the south, which form the Faka Union Canal System, from 1968 through 1971. Four north-south canals spaced two miles apart drain Southern Golden Gate Estates and the portion of the Faka Union Canal Watershed north of I-75. From west to east, the canals are the Miller Canal, Faka Union Canal, Merritt Canal, and Prairie Canal. Only the two westerly canals run north of I-75. The Miller Canal extends almost seven miles north of I-75, and the Faka Union Canal extends about 14 miles north of I-75. The Merritt Canal starts in the immediate vicinity of I-75, and the Prairie Canal starts about two miles south of I-75. The average excavated depth of the four canals is about ten feet from the top of the bank to the bottom of the channel. Given the relatively close proximity of the water table to the surface in this area, excavation to these depths thus established a direct hydraulic connection with the surficial aquifer. The canals are large, ranging from 45 to over 200 feet wide. Although unable to convey without flooding the water from even a ten-year storm event, which is the level of service standard set by Collier County for Southern Golden Gate Estates, the Faka Union Canal system has nonetheless severely impacted the water resources of Collier County. According to the Hydrologic Restoration of Southern Golden Gate Estates, prepared in February 1996 by the Big Cypress Basin Board (Southern Golden Gate Estates Restoration Plan): . . . Construction of the canals has led to both increased volumes and rates of runoff from the watershed which has had lasting effects on the area's water supply, vegetation, wildlife, and coastal estuaries. The canals intercept large volumes of surface and subsurface flow and quickly divert them to the Faka Union Bay and the Ten Thousand Island Estuary of the Gulf of Mexico resulting in less surface water available for storage. Since groundwater recharge is achieved primarily through infiltration from surface detention storage, reduced groundwater recharge threatens both groundwater supply for the region and the natural barrier to salt water intrusion. Continued overdrainage has caused an eventual lowering of the groundwater table. This has caused vegetation to change from wetland dominant to transitional and upland systems with invasive exotic species. The extreme dry conditions caused by overdrainage have resulted in more frequent and more intense wildfires with a greater destructive impact on vegetation. The increased runoff rate has had severe effects on the receiving estuaries. Historically, the estuaries would receive broad, slow moving sheets of water that were capable of carrying essential nutrients but not high sediment loads. This has been replaced with point loads of freshwater at the Faka Union Canal outlet that push salinity levels down and result in freshwater discharge shocks throughout the Ten Thousand Island Estuary. The increased runoff rate drains the area quickly and does not allow the hydroperiods necessary to sustain wetland vegetation. . . . Southern Golden Gate Estates Restoration Plan, pages 8-9. The major roadway affecting the Faka Union Canal Watershed is State Road 84, which was a two-lane road constructed in 1966. In 1990, construction was completed transforming State Road 84 into four-lane I-75. These road projects have hastened drainage of the lands to the north of I-75 and east of the Faka Union Canal. The land north of the Merritt Canal is largely undeveloped. If one were to extend the Merritt Canal due north of I-75, it would run through the middle of Lucky Lake Strand and much of Stumpy Strand, which is immediately to the north of Lucky Lake Strand. Agricultural land owned by Collier Enterprises is just north of the Ford Motor Company test track and immediately west of Lucky Lake Strand. Agricultural land owned by Baron Collier Company is immediately north of Stumpy Strand. This imaginary extension of Merritt Canal would mark the west boundary of the Florida Panther National Wildlife Refuge, which was established in June 1989. The Florida Panther National Wildlife Refuge constitutes 26,000 relatively undisturbed acres immediately north of I-75. Intervenor Clifford Fort owns property south of the refuge on the south side of I-75. The Florida Panther National Wildlife Refuge features mostly wetlands, oak hammocks, pine flatwoods, and prairies. The refuge receives runoff from stormwater and possibly agricultural pumping of the water table from the adjacent farmland. In addition to draining into the headwaters of the Merritt Canal near the southwest corner of the refuge, the refuge also drains into the northerly borrow canal running along the north side of I-75. In the vicinity of the Merritt Canal, the four borrow canals running along the north and south sides of I-75, on both sides of the Merritt Canal, drain in the direction of the Merritt Canal. Listed species using the Florida Panther National Wildlife Refuge include the Florida panther, Florida black bear, wood stork, roseate spoonbill, limpkin, and Eastern Indigo snake. In October 1995, an inordinate amount of rain fell in the area. Attracted by the increased water depths, which more closely approximated historic conditions, 75 wood storks nested in the Lucky Lake Strand; in drier years, wood storks do not nest in the strand. Lucky Lake Strand occupies the southwest corner of the Florida Panther National Wildlife Refuge. Lucky Lake and two other ponds are present in this area. When full, Lucky Lake and one of the ponds are about 50 meters wide, and the third pond is about half of this width. During the dry season, a person can throw a stone across any of the ponds. Historically, Lucky Lake and Stumpy strands passed surface water into the Picayune Strand, which is west of the Merritt Canal and south of I-75, from which the water ran into the Fakahatchee Strand. Lucky Lake Strand presently narrows to about 1000 feet at I-75. The hydrologic connection between the outlet of Lucky Lake Strand and the headwaters of the Merritt Canal has contributed significantly to the overdrainage of these two strands, which occupy a significant area within the federal refuge. The FWS wildlife biologist stationed at the Florida Panther National Wildlife Refuge reported in a habitat assessment report prepared in August 1996 that four ponds in the strand dried out by December so that they could not sustain fish or provide feeding habitat for birds. Permitting Criteria Public Health, Safety, or Welfare or Others' Property One of the main disputes between the parties is the affect of the proposed weir on flooding. This case is largely about flooding or, more generally, the amount of water to be stored for a specified period of time. Petitioners and Intervenors fear that the District's effort will cause flooding to areas south of I-75 and east and west of the Merritt Canal. Occupying property within a vast area whose natural drainage patterns have been greatly disrupted, Petitioners and Intervenors justifiably fear the ravages of flood and fire. Although this area was undoubtedly subject to these hazards prior to man's alteration of the natural landscape, large- scale alterations to natural drainage in Southwest Florida have artificially heightened the risk presented by these natural hazards. Destructive flooding follows the inhabitation of areas historically devoted to the storage of considerable volumes of water; the flooding is exacerbated where, as here, natural drainage features have been replaced by artificial facilities that are inadequate for both the natural flows and the new, artificial flows generated by development. Although inadequate for the natural and artificial flows generated by even design storm events, the artificial drainage facilities nevertheless change historic drainage rates, accelerating the rate and volume of natural drainage and shortening the hydroperiod. In this manner, the artificial drainage facilities contribute to the desiccation of previously saturated soils and foster conditions suitable for dangerous fires. Initially, Petitioners and Intervenors contend that the District seeks approval of the proposed weir as an indirect means of implementing the Southern Golden Gate Estates Rehydration Plan. Little evidence supports this concern. The Southern Golden Gate Estates Rehydration Plan outlines several alternatives for the proposed rehydration of Southern Golden Gate Estates. The preferred alternative does not call for a weir at the proposed location. The purpose of the proposed weir is to rehydrate an area north of the Southern Golden Gate Estates. As discussed below, the role of the proposed weir in rehydrating Southern Golden Gate Estates appears insubstantial to the point of nonexistent. Focusing on the location of the proposed weir over half of a mile downstream from the southernmost part of the area intended to be rehydrated, Petitioners and Intervenors dispute the stated purpose of the project, focusing on the District's earlier relocation of the proposed weir from positions just north and then just south of I-75 to its present position a half-mile farther to the south. The District did nothing to allay this concern of Petitioners and Intervenors when its employees could not provide a reasonably detailed explanation of the process by which someone moved the proposed site to the south. From the District's evidence, one would infer that the decision to relocate the proposed weir to the south spontaneously emerged, without human sponsor, in the course of bureaucratic decisionmaking. The District asserted that the northerly sites were impractical due to access problems. However, the District made little, if any, real effort to see if the Department of Transportation would allow access to these more northerly sites--one of which the District might be able to access without the consent of the Department of Transportation. The record does not reveal why the District relocated the proposed weir to its present location, considerably south of its initial two locations at I-75. Again, though, the evidence does not support the contention of Petitioners and Intervenors that the relocation decision was part of a private plan among District employees to incorporate the proposed weir as part of a more ambitious project to rehydrate Southern Golden Gate Estates. Nor does the evidence establish, as Petitioners and Intervenors contend, that the relocation decision was driven by the concerns of three influential landholders to the north of I-75--Collier Enterprises, Barron Collier Company, and Ford Motor Company. These three landholders approved the proposed weir in its present location over a half-mile to the south of its original locations and may have expressed concern that the original locations at I-75 would unreasonably raise the risk of flooding their land and business and agricultural activities to the north of I-75. If the District's real reason for relocating the proposed weir was due to objections from these landowners to the north of I-75, this reason would not itself help Petitioners and Intervenors. If the District acceded to the demands of these landowners to the north, it does not necessarily follow that the District lacked confidence in its flood calculations. A relocation decision under these circumstances would have as likely reflected political, as scientific, concerns. Additionally, if the District moved the proposed weir at the insistence or suggestion of the landowners to the north, any flooding concerns voiced by these landowners raise different issues from the flooding concerns raised by Petitioners and Intervenors. Owners of land immediately to the north and west of the federal refuge are more directly within the area of the intended effects than are Petitioners and Intervenors. More substantially, Petitioners and Intervenors claim that the proposed activity is so negligently designed or will be so negligently operated as to result in heightened and more frequent flooding of areas to the west and east of the proposed weir. The District's record in operating weirs in Collier County is not flawless. In recent years, the District constructed and maintained a weir with unlawfully high gates and did not correct the noncompliant water-control structure for several months after first learning of the violation. However, this appears to have been an isolated violation. The division of responsibility between the District and Collier County for the maintenance of drainage canals is based on whether the canal is a primary or secondary drainage facility. The District has assumed responsibility for all of the primary drainage facilities in Collier County. Surprisingly, though, the record reveals no master map or index of the primary drainage facilities and at least the larger nonprimary drainage facilities. However, Petitioners and Intervenors failed to show that any confusion concerning maintenance responsibilities that may exist between the District and Collier County would appreciably raise the probabilities that the District would operate the proposed weir in such a way as to exacerbate present flooding concerns. The District and Collier County agree that the District has jurisdiction over the Merritt Canal. Petitioners and Intervenors have also failed to show that any confusion concerning secondary-drainage contributions that may exist between the District and Collier County would have a substantial impact on the successful operation of the proposed weir. The most significant claim raised by Petitioners and Intervenors asserts that the District failed to provide reasonable assurance that the proposed weir would not exacerbate flooding. Although the weir gates would be closed only during the dry season, the proposed activity requires analysis of the risk of heightened water elevations upstream of the proposed weir. In theory, flooding could result from the effects of the weir even when the gates are open, as well as the possibility of an extreme storm event during the dry season. Expert witnesses on both sides clashed over whether the design of the proposed weir was sufficient not to exacerbate existing levels, rates, and frequencies of flooding of adjacent uplands. The crucial feature over which the experts disagreed was the spoil banks running along the canal. When the Merritt Canal was constructed, the spoil was dumped along the banks. In the ensuing years, vegetation colonized and stabilized the spoil banks, which now function as levees. The expert witness called by Petitioners and Intervenors disregarded the spoil banks in his calculations. His lack of confidence in the opposing expert witness's use of top-of-bank elevations was partly justified for the reasons stated below. Although a minor point, part of the argument of Petitioners and Intervenors' expert witness proved too much by asserting that levees cannot maintain water levels higher inside the levee than the existing ground elevation outside the levee. On the other hand, in showing that the proposed weir would not exacerbate flooding, the District's expert witness relied, not entirely justifiably, on the top-of-bank elevations. The District took only spot elevations of the spoil bank and then assumed that these elevations prevailed along the entire 3600 feet of canal upstream of the weir. The District did not inspect the upstream banks for unpermitted culverts, of which at least one was discovered during the lengthy hearing in this case. There is a possibility of material differences in elevations along the spoil banks. These spoil banks were not constructed to a specified elevation; they were an excavation byproduct that was haphazardly deposited beside the excavated canal. Additionally, the record suggests that this general area has been the site of unpermitted works, such as the installation of a culvert and creation of unpermitted canal plugs. In the months over which the hearing took place, Petitioners and Intervenors alertly found a culvert breaching the spoil bank upstream of the proposed weir. At least one of their representatives demonstrated superior familiarity with the spoil bank over the familiarity demonstrated by the District's representatives. It is a fair inference that, if the spoil bank was substantially missing at any point upstream of the proposed weir, Petitioners and Intervenors would have brought such evidence to the hearing. The absence of such evidence, coupled with the reasonable inferences that may be drawn from the concededly more cursory investigation of the site by the District, precludes a finding that the spoil bank is substantially missing at any material point so as to warrant the use of ground elevations, as used by the expert witness called by Petitioners and Intervenors. At best, from the perspective of Petitioners and Intervenors, the record supports the finding that the spoil banks may not be as continuously as high as the District posits, but they are not nearly as low (i.e., nonexistent) at any point as Petitioners and Intervenors contend. The two experts also disagreed over two subordinate inputs used in running the flood calculations. The expert called by Petitioners and Intervenors claimed that initial tailwaters (i.e., water elevations downstream of the weir) in excess of 8.53 feet were appropriate. Although the canal has experienced historically higher tailwaters than 8.53 feet, the expert did not explain adequately why such higher tailwaters should be used in running the model, especially since flood calculations are not used to predict flooding conditions in all storms, such as a 1000-year storm. Absent a showing that tailwater in excess of 8.53 feet would be present at the relevant time preceding or during the design storm event, the expert called by Petitioners and Intervenors failed to show why the District's tailwater input was unreasonable. On the other hand, the District's expert claimed that the model required an adjustment to the friction factor or Manning's N coefficient. This adjustment, which decreased the friction factor by an order of magnitude, approximated a bottom that was many times smoother than the actual bottom of the Merritt Canal. The District's expert did not explain adequately why the lower friction factor should be used in running the model, and he frankly did not demonstrate the same familiarity with this friction factor as did the expert called by Petitioners and Intervenors. The most likely inference is that the District's expert erred in making this adjustment. There was another controversy between the parties regarding a subordinate input for the flooding calculations. Petitioners and Intervenors raised the possibility that agricultural discharges from the Collier properties adjacent to the federal refuge, which the District ignored in its calculations, might further undermine any assurances as to flooding. This could have been useful information if developed in the record, but the record permits no basis to quantify the value of this additional discharge or ascertain its timing relative to wet and dry seasons and storm events, if in fact this agricultural discharge takes place at all. Also, offsetting any such discharge would be two factors: the District ran its calculations assuming a runoff rate 25 percent greater than that appropriately used by the Florida Department of Transportation for modeling the design storm event, and the District ignored the plugs in the I-75 borrow canals, which attenuate the runoff into the Merritt Canal. Although Petitioners and Intervenors incorrectly inputted ground elevation in place of the top-of-bank elevation--when the best elevation is somewhere in between these two values--their expert's calculations are useful for illustrating a scenario that, for this reason, exceeds the worst-case scenario. Again, this is an illustration of a scenario that predicts greater flooding than reasonably should be predicted because, in actuality, the restraining elevation is higher than ground elevation. Using the 8.53-feet initial value for tailwater, Petitioners' Exhibit 27 illustrates the different water elevations resulting from running the model with and without the excessive reduction of the friction factor. Petitioners Exhibit 27 illustrates the effect of the design storm on upstream water elevations with the gates open. Petitioners Exhibit 27 ignores the spoil banks and instead uses prevailing ground elevations. At the site of the proposed weir, the canal bottom is at about -1.5 feet NGVD. The proposed weir would add fixed barriers up to an elevation of 5.0 feet NGVD; the adjustable gates would, when closed, extend the barrier from 5.0 feet NGVD to 9.5 feet NGVD. Approximate existing ground elevation averages about 10 feet NGVD downstream of I-75, with one dip to below 9 feet NGVD about 600 feet downstream of I-75. For about 6000 feet upstream of I-75, where there is no spoil bank whatsoever, the average ground elevation, outside of the slough, is about 13 feet. The slough bottom in this area gently slopes from about 9 feet NGVD to 10 feet NGVD. Ignoring the spoil bank, Petitioners Exhibit 27 predicts flooding in two major areas in the design storm event, even with the gates open. One of these is about 300 feet long, starting about 400 feet downstream of I-75. The other is at least 300 feet long, starting near the northern extreme of the modeled area and running off the modeled area. The District did not survey in detail the spoil bank along the 300 feet downstream of I-75. There is no spoil bank upstream of I-75 because there is no dredged canal. The water elevation about 400 feet downstream of I-75 would be almost one foot greater than the ground elevation. The water elevation about 6000 feet upstream of I-75 will be as much as half of a foot greater than the ground elevation. At the more downstream point, the actual water elevation would exceed the District's projection by nearly three-quarter of one foot. At the more upstream point, the actual water elevation would exceed the District's projection by over 1.5 feet. Although the record could have been better developed on this important point, there is reasonable assurance that the existing spoil-bank elevations are sufficient to contain these flood elevations predicted by the expert called by Petitioners and Intervenors. Petitioners and Intervenors claimed that the District could achieve its stated purpose of extending the hydroperiod in the Florida Panther National Wildlife Refuge without increasing the risk or extent of flooding of adjacent uplands. Petitioners and Intervenors suggested that the District repair an existing plug in the Merritt Canal just south of I-75. (This "plug" is actually the original ground surface, which evidently was undisturbed during the construction of I-75. Given the excavation of canals on both sides of what is now a narrow strip of earth, the land resembles a plug, and this recommended order refers to it as a plug, although this term is descriptive only of the feature's present appearance, not its method of creation.) There are actually six plugs--again, in the broad sense of the word--in the vicinity of the junction of the Merritt Canal and I-75. Two plugs interrupt the flow into the Merritt Canal of the borrow canals to the north of I-75. Two plugs likewise interrupt the flow into the Merritt Canal of the borrow canals to the south of I-75. The last two plugs are in the Merritt Canal, a few feet north and south of I-75. Repairing the plug immediately south of I-75 would raise the water elevation by about 1.3 feet under the I-75 bridge. By about 2000 feet upstream of I-75, there is no significant difference between the water elevation using the model of Petitioners and Intervenors' expert for the proposed weir 3600 feet downstream of I-75 and the water elevation for the proposed plug repair just south of I-75. Repairing the plugs would have reduced the water elevation downstream of I- 75 by less than one half of a foot. Petitioners, Intervenors, and their expert have proposed a promising alternative to the proposed weir. The alternative appears to serve the stated purpose of the proposed activity at least as well as the proposed weir would, if not somewhat better due to its closer proximity to the targeted federal refuge, and the alternative project would cost much less to construct, maintain, and operate. The restorative nature of the work would probably relieve the District of the necessity of obtaining a permit. Perhaps the prospect of such work might motivate other state and federal agencies to grant the District access to the area at I-75 to build the weir at one of its first two locations. However, the issue is whether the District has provided reasonable assurance for the activity that it has proposed. As to flooding, the District has provided reasonable assurance that the proposed activity will not exacerbate flooding during the design storm events or even more severe storm events. Even assuming an absence of reasonable assurance as to flooding, the first criterion requires consideration of whether the proposed activity would adversely affect the public health, safety, and welfare or the property of others. Extending the hydroperiod of the federal refuge protects the property of others by reducing the period of time that the turf is dried out. This provides a wide range of environmental protection, including protection against the risk of fire caused by excessive drainage, for the federal refuge and other property in the area. Retarding the artificially high rate of drainage will improve water quality in at least two respects. The proposed weir will retard and reduce the nutrients conveyed down the canal and into the estuary into which it eventually empties. The proposed weir will also tend to restore somewhat the rate and timing of historic freshwater inputs on which the viability of the estuary and its inhabitants depends. Concerns about public health, safety, and welfare, as well as the property of others, cannot be severed from these broadscale environmental benefits to be derived from the proposed activity. Public health concerns are tied to these considerations. Thus, even if the District had failed to provide reasonable assurance as to flooding alone, the District has provided reasonable assurance that, on balance, the proposed weir will not adversely affect the matters set forth in the first criterion. Conservation of Fish and Wildlife, Including Endangered or Threatened Species, or Their Habitats The proposed weir will serve the conservation of a wide range of flora and fauna, as well as their wetlands habitat, within the targeted federal refuge. These species include listed species. The evidence does not support a finding that extending the hydroperiod of the federal refuge would in any way disturb the Florida panther. Navigation, Flow of Water, or Harmful Erosion or Shoaling The proposed weir will have not adversely affect navigation or the flow of water within the canal, and it will not cause erosion or shoaling. Fishing or Recreational Values or Marine Productivity in the Vicinity of the Activity The proposed weir will not adversely affect fishing or recreational values or marine productivity in the vicinity of the proposed weir. To the contrary, the proposed weir will enhance these values in the immediate vicinity of the proposed weir and downstream at the estuary at the mouth of the Merritt Canal. Temporary or Permanent Nature The proposed weir will be of a permanent nature. Significant Historic and Archaeological Resources The record provides no basis for a finding that the proposed weir jeopardizes significant historic and archaeological resources. Current Condition and Relative Value of Functions of Areas Affected by the Proposed Activity The federal refuge is functioning well environmentally, despite the adverse impact of dramatic disruptions of the natural drainage regime. The value of these functions is high. Likewise, the receiving estuarine waters are functioning well, despite the adverse impact of dramatic disruptions of the natural drainage regime. Extending the hydroperiod of the federal refuge will partially offset these historic disruptions. Thus, the proposed weir will assist in the functioning of natural systems that are now functioning well, but could use some help. Public Interest The proposed weir is not in an Outstanding Florida Water. Thus, the question is whether the proposed activity is not contrary to the public interest. The District has provided reasonable assurances as to the preceding seven criteria sufficient to demonstrate that, on balance, the proposed activity is not contrary to the public interest. Cumulative Impacts There is no evidence that the proposed weir will cause any adverse cumulative impacts upon wetlands or surface waters. Other Criteria The District has proved that the proposed weir would not violate any water quality standards. To the contrary, any effect from the proposed activity would be to improve water quality, especially downstream at the estuary. The restoration of conditions more typical of historic drainage would allow more nutrients to be captured upstream and would tend to restore the historic timing and volume of freshwater inputs into the estuary. For the reasons set forth above, the District has also provided reasonable assurance that the proposed activity meets the 11 criteria contained in Rule 40E-4.301, which largely duplicate the seven criteria discussed above, and the relevant provisions of the Basis of Review. It is true that the monitoring provisions are largely illusory because they provide no quantifiable parameter beyond which the District must take specified action. In other words, at best, the monitoring provisions assure that the District will collect post-operational flooding data, but they do not promise that the District will take any action if certain levels of flooding take place. However, the monitoring provisions are of little importance given the factual findings concerning flooding, as discussed above, and the legal requirements of the Basis of Review, as discussed below.
Recommendation It is RECOMMENDED that the Department of Environmental Protection enter a final order granting the permit for the construction of the proposed weir about 3600 feet south of I-75 in the Merritt Canal. DONE AND ENTERED this 25th day of June, 1998, in Tallahassee, Leon County, Florida. ROBERT E. MEALE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 25th day of June, 1998. COPIES FURNISHED: James W. McDonald, Jr., Esquire McDonald & Associates Community Plaza, Suite 306 15600 Southwest 288th Street Homestead, Florida 33030 A. Glenn Simpson Qualified Representative 5961 22nd Avenue Southwest Naples, Florida 34116 Marcy I. LaHart Associate Attorney South Florida Water Management District 3301 Gun Club Road West Palm Beach, Florida 33416-4680 Francine M. Ffolkes Assistant General Counsel Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 Walter R. Shaw, Sr., pro se 1400 Northwest 62nd Avenue Sunrise, Florida 33313-6138 Cliffort L. Fort 8410 Northwest 16th Street Pembroke Pines, Florida 33024 Kathy Carter, Agency Clerk Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000 F. Perry Odom, General Counsel Department of Environmental Protection Mail Station 35 3900 Commonwealth Boulevard Tallahassee, Florida 32399-3000