WINKO-MATIC SIGNAL COMPANY vs. DEPARTMENT OF TRANSPORTATION, 84-002250 (1984)
Division of Administrative Hearings, Florida Number: 84-002250 Latest Update: Jan. 18, 1985

Findings Of Fact On March 1, 1984, Respondent gave notice to qualified contractors that it would receive sealed bids for State Project No. 72000-3541, referred to as Federal-Aid Project No. M 9041(10). This project involves the installation of a computerized traffic control system for the City of Jacksonville. In response to the opportunity to bid, the Department of Transportation received four bids. Petitioner, Winko-Matic Signal Company, was among the bidders. The other bidders were Georgia Electric Company, Traffic Control Devices, Inc., and Sperry Systems Management. The bids of Traffic Control Devices and Sperry Systems were rejected based upon an error in bid tabulations on the part of Traffic Control, a mistake on the quantities page, with the Sperry rejection being based upon a bid bond problem. Traffic Control had been the apparent low bidder with a bid of $1,964,115. Winko-Matic was the second apparent low bidder with a bid of $2,279,604.70. The Department of Transportation had estimated that the total cost of the Jacksonville project would be $ 2,024,680.61. Having discarded the bid of Traffic Control Devices, the Department of Transportation telegrammed Winko-Matic on April 4, 1984, advising Winko-Matic that it was the apparent low bidder for the Jacksonville project. Subsequently, the awards committee of the Department of Transportation met on April 18, 1984, and determined to reject all bids and re-advertise the job. In the course of this meeting the awards committee was told that there were erratic bids received on contract items, pointing to some perceived confusion among the contractors as to requirements of the contract. Discussion was also held on the possibility of establishing a pre-bid conference if the project was re advertised. The awards committee then voted to reject the bids on the basis that the apparent low bidder, Winko-Matic, had submitted a bid which-was 12.6 percent over the Department's estimate, instead of being within 7 percent of the Department of Transportation's pre-bid estimate, a point above which the Department of Transportation in its non-rule policy would call to question to the acceptability of the apparent low bid. In addition to deciding to reject all bids and re-advertise, it was determined that a pre-bid conference should be scheduled at least 30 days prior to the bid-letting date. Winko-Matic was advised that the Department of Transportation's decision to reject all bids by correspondence of May 4, 1984, in which it was indicated that all bids had been rejected based upon the fact that they were too high. In response to this notice of rejection, Winko-Matic, effective May 17, 1984, filed a written notice of protest. The case was subsequently referred to the Division of Administrative Hearings on June 20, 1984, and a final hearing date was established by Notice of Hearing of July 5, 1984. The hearing date in this cause was September 12, 1984. The Jacksonville project in question requires the utilization of what has been referred to "UTCS Enhanced" software. This software package is unique and has only been used in a limited number of locations within the country. Those locations are Los Angeles, California; San Diego, California; Broward County, Florida; and Birmingham, Alabama. Another unique feature within the project design is the use of an associated coaxial computer sys gem. Given the unique nature of this project and the fact that the Department of Transportation had never advertised for bids related to UTCS software, Department of Transportation obtained assistance from a consulting firm, Harland, Bartholomew & Associates. In fulfilling its function Harland gave estimates to include an estimate related to the projected cost of the software, Item 681-102. The Harland estimate for the overall project was $2,143,130 including a $100,000 estimate for the software system. That estimate relating to the software was subsequently adjusted by the Department of Transportation to depict a cost of $13,780. The Department of Transportation estimate was based upon information within its computer related to a system unlike the enhanced software contemplated by the plans and specifications. In other words, the stored information in the Department of Transportation computer was not the same as contemplated by the plans and specifications in the Jacksonville project. Moreover, the initial estimate of Harland was based upon the idea of an extended software system, as opposed to an enhanced software system. Winko-Matic had bid $389,500 for the software in Item 681-102. That estimate was premised upon figures obtained from JHK and Associates, the group which Winko-Matic intended to use as its subcontractor for the enhanced software portion of the project. JHK developed the software and was responsible for systems integration of the Los Angeles, California, project, one of the locations in which UTCS enhanced software has been utilized. JHK premised its estimate for the software hare upon experience in Los Angeles and an evaluation of the tasks to be performed related to the enhanced software. This included general software development activities, hardware innovation, installation costs during the period of acceptance and testing, and the preparation of data base. The JHK bid price was $339,500. Another $50,000 was added to that price related to what the Petitioner describes as its management costs for that item. By June 20, 1984, when a further meeting was held by the awards committee on the subject of the Jacksonville project, it was concluded that the estimate made by the Department of Transportation of $13,780 was not correct, on the topic of the enhanced software. A more reasonable estimate, according to the information imparted in this session, would be $200,000 for enhanced software as called for in this project, with a $100,000 amount being a reasonable estimate had they chosen to use extended software. Adjusting the initial price related to the UTCS enhanced software to reflect a corrected estimate of the Department of Transportation in its original advertised bid, that estimate becomes $2,210,900.61 and its consultant Harland's estimate becomes $2,243,130. With this adjustment, the differential in the estimate made by the Department of Transportation and the Petitioner approaches 3 percent and not the 12.6 percent originally found. The 3 percent is below the threshold of 7 percent used as the policy for determining whether a bid might be rejected as being far beyond the acceptable limits set forth in the Department of Transportation's estimate. In the aforementioned June 20, 1984, awards committee meeting, the Department of Transportation continued to hold the opinion that all bids in the Jacksonville project should be rejected and the matter re-advertised. Although the problem pertaining to the estimate of the cost of the enhanced software package had been addressed, the committee continued to feel that the prices received in the bid letting were erratic Reference was also made to revisions or modifications to the project plan which would be offered if the matter were re- advertised. It was also pointed out that the Federal Highway Administration would concur in the Department's decision to reject all bids and would accept modifications. The awards committee again voted to reject the bids. The matter was again considered by the awards committee on August 31, 1984. On that occasion, it was pointed out that the revisions contemplated by the Department of Transportation, should the matter be re-advertised, would not affect in a substantial way the cost estimate for the project with the exception of Item 680-101, the system control equipment (CPU), which would promote a lower price for the project. The committee determined in the August, 1984, meeting to reject all bids and re-advertise. While the initial notice of rejection of May 4, 1984, had suggested the basis for rejection as being the fact that Petitioner's bid far exceeded the 7 percent allowance for price above the Department of Transportation's estimate of costs, the meetings of the awards committee and the suggestion of the Respondent in the course of the final hearing in this case indicated that there were other reasons for the decision to reject. Those Were: (a) an apparent lack of clarity among bidders regarding specifications for the Jacksonville job, (b) the desire of the Respondent to revise specifications on the Jacksonville project; and (c) a lack of sufficient competition in the bids. In connection with the first of the additional reasons Respondent suggests that variations within the bid responses related to particular line items within the specifications point out a lack of clarity in the project's specifications or confusion by bidders related to those specifications. Respondent did not bring forth any of the bidders who might speak to the matter of possible confusion or misunderstanding concerning some of the bid items. By contrast, the Petitioner's president; the president of JHK & Associates and James Robinson, Harland's project manager for the Jacksonville job, did not find the specifications in the original documents to be confusing. In addition, the testimony of those individuals established the fact that bid variations related to particular line items are not extraordinary and do not establish any apparent confusion by the bidders as to the requirements of those line items. In effect, what the differentials demonstrate are variations related to the manufacture or in-house capabilities of the bidders and an effort to allocate discretionary costs in various places as to line items. Moreover, they might indicate last- minute adjustments in the bid quote prior to the opening and a possible effort by a contractor to enter into a new job market. Finally, they demonstrate offsetting which is the allocation of item prices by a contractor to maximize profits. To do this, a contractor submits high bids on items representing quantities which the contractor feels will increase after the contract is awarded and submits low bids on items representing quantities which are not likely to change. In summary, while the Department of Transportation in its presentation expressed some concern about the variations in the pricing in the bid quotations offered by the respective bidders in this project, its suspicions on the question of the possible clarity of its specifications were not confirmed and are not convincing. On the topic of revisions which the Department of Transportation would offer if the matter were re-advertised, with one exception those matters appear to be items that could be attended through change orders or supplemental agreements. They are not matters which necessarily must be addressed through a rejection of all bids and a re-advertising of the project. The lone exception to this is the possibility that the Department of Transportation may not be able to protect its proprietary rights in the enhanced software which is being developed for the project, under the terms of the present bid documents. Given that uncertainty, the Respondent would wish to re-advertise the project and make certain that its proprietary interests are protected. Finally, Respondent has alluded to the fact that the Jacksonville project should be re-advertised in view of the lack of competition in the initial letting. Only four bidders expressed an interest in this project at the time of the first letting. Of those, two bidders were found to be responsive. While this is a low number of bidders, there does not appear to be any agency practice on the part of' the Department of Transportation to the effect that this number of bidders would not be accepted. Moreover, no indication has been given that should the matter be re-advertised a greater number of bidders would express an interest than was the case in the first letting. Consequently, this reason for bid rejection is not acceptable. If Respondent did not reject the bids and re-advertise the project, Winko-Matic would be the successful bidder in the Jacksonville project.

Florida Laws (3) 120.53120.57337.11
# 1
PLASCO, INC. vs BROWARD COUNTY SCHOOL BOARD, 01-003203BID (2001)
Division of Administrative Hearings, Florida Filed:Fort Lauderdale, Florida Aug. 14, 2001 Number: 01-003203BID Latest Update: Oct. 18, 2019

The Issue The issue for determination is whether the School Board of Broward County, Florida (“SBBC”) improperly awarded a contract pursuant to Invitation to Bid No. 21-244H for “Photo ID Card and Printing System Supplies” (“ITB”) to Intervenor, Identicard Systems, Inc. (“Identicard"). Petitioner Plasco, Inc. ("Plasco") contends that the recommended award to Identicard is clearly erroneous, contrary to competition, arbitrary, capricious, or contrary to the specifications of the ITB. The resolution of the ultimate issue turns on whether the uninitialed corrected figures contained within Plasco’s bid response for both the unit price and the total cost of Item 1(N) were a material deviation from the bid specifications requiring rejection of the bid.

Findings Of Fact SBBC desired to procure photo identification card and printing systems supplies to prepare identification cards for school district employees, students in selected schools, and outside vendors. SBBC has adopted School Board Policy 3320 which governs its purchasing of goods and services. On or about April 30, 2001, SBBC released the ITB. General Condition 1(c) of the ITB stated in pertinent part: EXECUTION OF BID: . . . If a correction is necessary, draw a single line through the entered figure and enter the corrected figure or use an opaque correction fluid. All corrections must be initialed by the person signing the bid even when using opaque correction fluid. Any illegible entries, pencil bids or corrections not initialed will not be tabulated. . . . General Condition 2 of the ITB stated in pertinent part: PRICES QUOTED: . . . Give both unit price and extended total. Prices must be stated in units to quantity specified in the bidding specification. In case of discrepancy in computing the amount of the bid, the Unit Price quoted will govern. . . . General Condition 7 of the ITB stated in pertinent part: AWARDS: In the best interest of the School Board, the Board reserves the right to withdraw this bid at any time prior to the time and date specified for the bid opening; to reject any and all bids and to waive any irregularity in bids received; to accept any item or group of items unless qualified by bidder. . . . All awards made as a result of this bid shall conform to applicable Florida Statutes. Special Condition 3 of the ITB states as follows: AWARD: Bid shall be awarded by GROUP to the lowest responsive and responsible bidder meeting specifications, terms and conditions. Therefore, it is necessary to bid on every item in the group, in order to have the bid considered for award. Unit prices must be stated in the space provided on the Bid Summary Sheet. SBBC may need to order an individual component within a group. All items within a group must have an individual cost. Failure to state the individual cost for an item within a group will result in disqualification of the group. Bidder should carefully consider each item for conformance to specifications. In the event that one item in the group does not meet the specifications, the entire group will be disqualified. On June 7, 2001, Plasco, Identicard, and seven other companies submitted responses to the ITB. After receiving the bid responses, SBBC’s Purchasing Department examined and computed the figures submitted by each bidder for each item listed in the Bid Summary Sheets. For each item, a quantity figure had been supplied by SBBC in the bid specifications. The bid was structured so that the specified quantity would be multiplied by a unit price furnished by the bidder on its Bid Summary Sheets. The bidder was also required to furnish a total cost for each individual item in its Bid Summary Sheets. The bids submitted by both Identicard and Plasco contained a number of uninitialed corrections. Although such uninitialed corrections violated General Condition 1(c), the SBBC properly deemed such errors to be immaterial in every instance where only one figure per specified Item was tainted by a violation of this General Condition. For example, where a particular component of the bid required the bidder to specify a unit cost and a total cost for the quantity of goods specified in that particular component, the SBBC was willing to perform the mathematical calculation necessary to confirm the correctness of the uninitialed figure. As applied to this particular type of uninitialed correction, SBBC staff would multiply or divide the quantity specified in the ITB by the "untainted" number provided by the bidder to confirm the correctness of the uninitialed corrected figure submitted in violation of General Condition 1(c). The Bid Summary Sheet submitted by Plasco for Item 1(N) contained a different violation of General Condition 1(c), to wit, it contained two uninitialed corrected figures. The corrections were accomplished through the use of correction fluid. Plasco's Bid Summary Sheet with respect to Item 1(N) stated in pertinent part as follows: UNIT TOTAL PRICE COST * * * FARGO ACCESSORIES N. 3 each 81524 Thermal Printhead $389.35 ea $1,168.05 for Cheetah/Cheetah II/ Pro/Pro-L/Presto! Quatro/ Presto! System The Unit Price of $389.35 as well as the Total Cost of $1,168.05 for Item 1(N) set forth in Plasco’s bid was a corrected price and was not initialed by the person signing the bid on behalf of Plasco. Notwithstanding this "double correction," it was possible within the four corners of Plasco's bid to verify the unit price of the Item and thus to confirm, mathematically, a total price. The Item in question, a printhead, was the subject of four additional bid items. In each instance, Plasco bid $389.35 per printhead, a number which matched Plasco's corrected figure in Item 1(N). SBBC was not misled by Plasco's failure to initial either or both corrections in Item 1(N). Correctly using Plasco's uninitialed corrections as set forth in Item 1(N), SBBC accurately performed the calculations necessary to verify Plasco's bid; therefore the Bid Summary prepared by SBBC staff accurately reflected that Plasco was the low bidder at $93,449.68. The responses to the ITB were reviewed by school district staff on or about June 7, 2001. The so-called "double correction" in Item 1(N) was SBBC's sole basis for its decision to reject Plasco's low bid, and to recommend that Identicard's next lowest bid of $100,720.12 be accepted. At no time relevant to this case did SBBC have a written policy which compels that any bid containing two uninitialed corrections be excluded from consideration. The evidence establishes that SBBC was able to and in fact did accurately account for the individual numbers contained in Item 1(N), as well as any and all other numbers affected by the numbers supplied by Plasco in response to Item 1(N). Under the facts of this case, Plasco's error in failing to initial the corrections in Item 1(N) was immaterial. SBBC maintains that it must enforce its unwritten policy of excluding bids containing two uninitialed corrections within a single item in order to protect the integrity of the bid process. There is no evidence that the integrity of the bid process in this case was compromised in any way. No good faith argument was made that there was any type of collusion or improper conduct in connection with this bid. Instead, the evidence establishes that Plasco's bid was responsive and responsible in all material respects, inasmuch as SBBC staff was able to accurately ascertain, to the penny, the amount of Plasco's low bid. Plasco timely filed its Notice of Protest with SBBC on June 18, 2001. Plasco timely filed a Formal Written Protest with SBBC on June 27, 2001. Pursuant to Section 120.57(3)(c), Florida Statutes, and School Board Policy 3320, SBBC provided an opportunity for Plasco to meet with the agency’s Bid Protest Committee in an attempt to resolve the protest by mutual agreement. The Bid Protest Committee conducted a duly-noticed public meeting with Petitioner Plasco on July 9, 2001. Upon consideration, the Bid Protest Committee rejected the protest of Plasco and upheld the recommendation to award the bid to Identicard.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the School Board of Broward County, Florida, enter a Final Order awarding the ITB to Plasco, and, upon submission of documentation contemplated in the parties' stipulation regarding costs, assess costs of this action in Plasco's favor in its Final Order pursuant to School Board Policy 3320, VI (n). DONE AND ENTERED this 9th day of October, 2001, in Tallahassee, Leon County, Florida. ___________________________________ FLORENCE SNYDER RIVAS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 9th day of October, 2001. COPIES FURNISHED: Mitchell W. Berger, Esquire David L. Ferguson, Esquire Berger Singerman 350 East Las Olas Boulevard Suite 1000 Fort Lauderdale, Florida 33301 Robert Paul Vignola, Esquire Steven H. Feldman, Esquire Broward County School Board K.C. Wright Administration Building 600 Southeast Third Avenue, 11th Floor Fort Lauderdale, Florida 33301 Mark A. Emanuele, Esquire Panza, Maurer, Maynard & Neel, P.A. Bank of America Building, Third Floor 3600 North Federal Highway Fort Lauderdale, Florida 33308 Dr. Franklin Till, Jr., Superintendent Broward County School Board K.C. Wright Administration Building 600 Southeast Third Avenue Fort Lauderdale, Florida 33301 James A. Robinson, General Counsel Department of Education The Capitol, Suite 1701 Tallahassee, Florida 32399-0400

Florida Laws (2) 120.57120.68
# 2
SOUTHERN STAR EVENT SERVICES, INC. vs PALM BEACH COUNTY SCHOOL BOARD, 94-002922BID (1994)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida May 26, 1994 Number: 94-002922BID Latest Update: Aug. 16, 1996

The Issue Whether Respondent acted fraudulently, arbitrarily, illegally, or dishonestly in determining that Intervenor's bid was responsive.

Findings Of Fact On March 16, 1994, the Respondent issued an invitation to bid (ITB) for security guard services. The desired services were described in detail by the bid documents. Bids from eleven bidders, including a bid from Petitioner and a bid from Intervenor, were opened on April 13, 1994. After the bids were evaluated, the Respondent determined that Intervenor's and Petitioner's bids were responsive. Intervenor was determined to be the lowest bidder and Petitioner was determined to be the second lowest bidder. Respondent thereafter notified all bidders that it intended to award the bid to Intervenor. Pertinent to this proceeding, the bid document contained the following general condition: AWARDS; In the best interest of the School Board, the Board reserves the right to reject any and all bids and to waive any irregularity in bids received . . . [Emphasis has been added.] Pertinent to this proceeding, the bid document contained the following special conditions: G. OCCUPATIONAL LICENSE: Each bidder, by submitting a bid, certifies that they possess a Class B license issued by the State of Florida as well as town and county occupational license. ALL BIDDERS MUST SUBMIT PROOF OF THE ABOVE REFERENCED LICENSE WITH THEIR BID (PHOTOCOPY) IF IT IS TO BE CONSIDERED FOR AWARD. * * * J. QUALIFICATIONS: The bidder will have maintained continual work experience in security guard services for a period of three years prior to the bid date. Bidder must submit written documentation with bid or within three days upon request, substantiating experience requirement. The bidder will have a place for contact by the owner during normal working days. [Emphasis in the original.] Petitioner timely protested the intended award of the bid to Intervenor on the ground that the Intervenor did not have an occupational license issued by Palm Beach County at the time of its response as required by Special Condition G. Intervenor submitted with its bid a copy of its Class B license issued by the State of Florida, Division of Licensing, and a copy of its occupational licenses issued by Broward County. Because Intervenor did not have any business in Palm Beach County at the time it submitted its bid, it did not have an occupational license issued by Palm Beach County. Respondent determined that Special Condition G. was met when Intervenor submitted a copy of its Class B license. Respondent has the discretion to waive as a minor irregularity the fact that Intervenor did not have a Palm Beach County occupational license at the time it submitted its bid. There was evidence that Respondent waived similar irregularities in the occupational licenses of other bidders, including an irregularity pertaining to the Petitioner. There was no evidence that the Respondent acted fraudulently, arbitrarily, illegally, or dishonestly in determining that Special Condition G. had been met. Intervenor was not afforded an unfair advantage in the bid process by this determination. Petitioner also timely protested the intended award of the bid to Intervenor on the ground that the Intervenor had not been incorporated for three years at the time of the bid and that it did not meet the experience condition contained in Special Condition J. The Intervenor was incorporated August 27, 1992. At the time of the bid, the Intervenor had been a viable business for more than two years but less than three years. Mr. Inyang, the president of the corporation, submitted documentation that established that his qualifications and experience exceeded the requirements of Special Condition J. Respondent acted within its discretion in determining that the experience of the president of the corporation satisfied the requirement that the bidder "... have maintained continual work experience in security guard services for a period of three years prior to the bid date" as required by Special Condition J. There was no evidence that the Respondent acted fraudulently, arbitrarily, illegally, or dishonestly in making this determination as to Intervenor's experience. Intervenor was not afforded an unfair advantage in the bid process by this determination.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Respondent dismiss Petitioner's bid protest. DONE AND ENTERED this 18th day of July, 1994, in Tallahassee, Leon County, Florida. CLAUDE B. ARRINGTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 18th day of July, 1994. COPIES FURNISHED: Donald H. Neff, President Southern Star Event Services, Inc. 316 Flamingo Road West Palm Beach, Florida 33401 Robert A. Rosillo, Esquire Palm Beach County School Board 3318 Forest Hill Boulevard West Palm Beach, Florida 33406-5813 Robert E. Inyang, President Michael Graziano, Investigator Supreme Intelligence Agency, Inc. 4700 North State Road 7, Suite 120 Lauderdale Lakes, Florida 33319 Dr. C. Monica Ulhorn, Superintendent Palm Beach County School Board 3340 Forest Hill Boulevard West Palm Beach, Florida 33406-5869

Florida Laws (3) 120.57287.012287.057
# 3
PICKETT, FANELLI AND O'TOOLE, P. A. vs DEPARTMENT OF REVENUE, 96-001122F (1996)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Mar. 04, 1996 Number: 96-001122F Latest Update: Oct. 28, 1996

Findings Of Fact The Petitioner, PFO, is a professional corporation organized and existing under the laws of the State of Florida. Petitioner's principal office is located in West Palm Beach, Florida. At all times material to the claims of this case, Petitioner had fewer than 25 full-time employees. At all times material to the claims of this case, Petitioner had a net worth of less than $2 million. On May 22, 1995, the Department provided Petitioner with a clear point of entry to a formal administrative hearing pursuant to Section 120.53(5), Florida Statutes. At that time the Department issued an intent to award the Palm Beach County (Intrastate) CSE contract to a third party. This dispute evolved into DOAH case no. 95-3138BID or "the bid case." The Department was not a "nominal party" in the bid case. A recommended order was entered in the bid case on September 5, 1995. Except for a minor point not relevant to the issues of this matter, the Department adopted the findings and conclusions of the recommended order and entered its final order on December 1, 1995. The final order in DOAH case no. 95-3138BID awarded the Palm Beach County (Intrastate) contract for CSE legal services to Petitioner. Such award was based upon the conclusions that the third party's proposal was nonresponsive and that aspects of the evaluation process were arbitrary. No appeal was timely filed against the final order. Petitioner is, therefore, a prevailing small business party within the meaning of Section 57.111, Florida Statutes. The Petitioner timely filed its request for attorneys' fees and costs in the instant case pursuant to Section 57.111, Florida Statutes. The total amount of attorneys' fees and costs incurred by Petitioner in the bid case was $63,495.25. Of that amount, at least $15,000 was reasonable and necessary for Petitioner to incur in the preparations for, and attendance at, the hearing in the bid case. The solicitation package for the bid case contained mandatory requirements with which all applicants were to comply. The final order in the bid case concluded that the successful applicant had failed to satisfy all mandatory requirements. Its bid was, therefore, nonresponsive to the solicitation. Additionally, the final order determined that the instructions regarding how the proposals were to be evaluated were unclear and that points were inappropriately assigned to the successful applicant. The overall conclusion of the final order found that the Department had acted arbitrarily in the intended award to this third party applicant. All of the material deficiencies relied on in the recommended order and the final order to reach the conclusion that the Department had acted arbitrarily were known to the Department at the time of its initial review and evaluation of the proposals. For example, the Department knew that the applicant had not identified two attorneys who would be expected to perform services under the contract, and had not included certificates of good standing from the Florida Bar for them. Additionally, the applicant had not provided references from three persons as specified in the solicitation package. This was evident upon the opening of the proposal. Nevertheless, the Department scored the nonresponsive proposal and awarded it sufficient points to be the apparent winner among the applicants. An award of attorneys fees' and costs under Section 57.111, Florida Statutes, is capped at $15,000. The agency has not disputed the reasonableness nor the amount of fees claimed in connection with the bid case. The agency has not offered evidence to specify each item of cost or fee in dispute. Discovery requested by the Department sought information for the period September 1995 through January 1996 which included runner logs of Petitioner's counsel, itemized bills regarding another party (not a party to the bid case nor this case), and the deposition of Don Pickett. None of the requested discovery addressed the issue of whether the Department's actions in the bid case were substantially justified. None of the requested discovery addressed facts which the Department had placed in issue by its response to the petition. None of the discovery addressed the issue of whether there are special circumstances which would make an award of reasonable fees and costs unjust. Moreover, the parties have stipulated that there are no special circumstances which would make an award of reasonable fees and costs unjust. No new information pertinent to the claim for fees and costs herein which was unknown to the Department as a result of the bid case proceeding was discovered from the deposition of Don Pickett. No new information pertinent to the reasonableness or amount of the fees claimed was discovered from the deposition of Don Pickett or the other discovery requested. The factual circumstances argued in Respondent's Proposed (sic) Recommended Order, ie. that the agency had relied on findings and conclusions from an unrelated DOAH case in connection with the review of the underlying bid case, were not set forth in the response filed by the agency in the instant case and have not been deemed credible in determining the issues of this case. The proposal submitted by the third party in the bid case was nonresponsive. The Department has stipulated that the award of a contract to a nonresponsive bidder is arbitrary.

Florida Laws (3) 120.53120.6857.111
# 4
STATE PAVING CORPORATION vs. DEPARTMENT OF TRANSPORTATION, 87-003848BID (1987)
Division of Administrative Hearings, Florida Number: 87-003848BID Latest Update: Oct. 01, 1987

Findings Of Fact On or about June 3, 1987, DOT advertised that it would receive bids on State Project No. 97870-334, etc. in Dade, Broward and Palm Beach Counties to improve portions of the Florida Turnpike. On June 24, 1987, bids were received by DOT from Gilbert, State Paving and Archer Western Contractors. The apparent low bidder at bid opening on June 24, 1987, was Gilbert and State Paving was apparent second low bidder. DOT was informally advised by John Beck, an attorney representing State Paving, that Gilbert's bid was believed to be unbalanced and the appropriate officials referred the issue to the DOT Bureau of Estimates to look into the low bid to see if it was unbalanced to the detriment of the State. Review of the Gilbert bid began with an internal analysis of the bid prices in comparison to the DOT Estimate of the Work. All bid prices above or below a certain percent of the engineer's estimate of costs were prepared in a computer printout and those items were checked by the consultants on the project. Basically, the major items in the project, which comprises some 400 bid items, were broken down to 10 groupings and the bids for each item in these groups was prepared for the three bidders and tabulated in Exhibit 2. The DOT Technical Committee reviewed the bids and concluded there was no unbalancing in Gilbert's bid which was detrimental to the State. This recommendation was approved by the Awards Committee which had also been furnished the information in Exhibit 2 by the consulting engineer for the project. Based upon this information, the Awards Committee concluded that the awards should go to Gilbert as no unbalancing detrimental to the State was found. Specification made a part of all DOT bid proposals provide that DOT may reject an unbalanced bid. As a matter of policy, DOT only rejects unbalanced bids deemed contrary to the interests of the State. Bids may be unbalanced in numerous ways. One significant method is known as front loading where the bidder submits a high bid for the work to be done at the beginning of the project such as clearing and grubbing and low bids for the work done later in the project. If successful in getting the award, this bidder would have excess profits on the clearing and grubbing which could draw interest while the less profitable later work was being done. Another variant is to study the plans and specifications to see if the quantities listed in the bid proposal are accurately reflected in the plans and specifications. If not, those items for which the bid proposal shows more than the plans and specifications reasonably required can be bid low, and for those items by which the bid proposal shows less than actually will be required can be bid high. Since the contractor is paid by the units used, those excess units at a higher price would result in more profit for the contractor yet allow him to submit an overall lower bid. For example, if the bid proposal contains two similar items for which the request for proposal estimates 100 each will be required, and the bidder concludes that only 50 will be required at Site A and 150 at Site B, he submits a low bid for Site A and a high bid for Site B. If the fair price for these units is $10 each, and the bidder bids $5 per unit for Site A or $500, and $15 for Site B or $1500, the total bid price is $2000, but if the bidder only installs 50 at Site A he would be paid $250 and install $150 at Site B for which he would be paid $2250. His total compensation would be $2500. In competitively bid contracts, such as the instant project, contractors modify their prices by taking a calculated risk that certain items bid on will not need to be accomplished and submit a nominal bid of $1 or 1 cent for such an item. By definition, such a bid is unbalanced, but if the item so bid has to be provided, the contractor has to provide this service at the bid price. The only evidence submitted by Petitioner tending to show Gilbert's bid was unbalanced to the detriment of the State was testimony, objected to and sustained, that the plans and specifications showed more of certain units would be needed than the estimated quantities on the bid proposal, which constituted the basis for the bids submitted. Such evidence constitutes a challenge to the bid specifications and is untimely. Gilbert's witness who prepared the bid submitted by Gilbert adequately explained the basis for bids submitted by Gilbert on the challenged items. The document entitled "This is Not an Addendum," clearly states on its face that "an addendum may follow containing the following information." No bids are solicited thereby and for no item contained thereon is the State obligated to contract. This document was provided all bidders before bids were open and no unfair advantage to anyone or detriment to the State was shown. In a project containing some 400 bid items, many modifications of the contract during construction is required to cover unforeseen circumstances that arise. While it would be better to get competitive bids on every bit of work done on this project, in this imperfect world unforeseen items will appear. The document complained of attempts to alert the bidders to some anticipated work not foreseen when the bid proposal was prepared, but it is not a part of the bid solicitation.

Florida Administrative Code (1) 14-25.024
# 5
FAIRCHILD CORPORATION vs DEPARTMENT OF TRANSPORTATION, 90-003122BID (1990)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida May 23, 1990 Number: 90-003122BID Latest Update: Jul. 30, 1990

Findings Of Fact State Project No. 46090-3511 (the project) is for construction of the West Bay Bridge on State Road 79 in Bay County, Florida. Competitive bids on the project were solicited in February, 1990. The bid letting on the project was held in March, 1990. The Petitioner, Fairchild, the Hardaway Company and ten other contractors bid on the project. The Hardaway Company submitted the lowest bid on the project in the amount of $9,487,258.17. Fairchild submitted the next lowest bid in the amount of $9,835,279.34. Divergent Unit Prices and Imbalances. The part of the Hardaway Company's bid relating to construction of the foundation for the approaches to the bridge (the "structural bid") is obviously below reasonable cost in several respects. The contract specifications require the use of sand fill, shell fill, reinforcement grid (biaxial type 2), and Class III (seal) concrete. The Hardaway Company's unit prices for these items were, respectively, one dollar per cubic yard for the sand fill, fifty cents per cubic yard for the shell fill, twenty-five cents per square yard for the reinforcement grid, and ten cents per cubic yard for the Class III seal concrete. As a result, the Hardaway Company's bid for these items is obviously significantly below reasonable cost and approximately $95,500 below what Fairchild bid for the same portion of the contract. In contrast to the sand fill, shell fill, reinforcement grid and Class III concrete, the Hardaway Company's bid on some of the other parts of the structural bid were relatively high. The reinforcing steel for the substructure (Item 415-1-5) was bid at approximately twice reasonable cost (80 a pound versus, e.g., 42 in Fairchild's bid), resulting in $609,936.80 attributable to that part of the bid versus, e.g., $320,216.82 for Fairchild. The statistical average (the DOT's so-called "average 2") for the other serious bidders under this item also was 42 a pound. The Hardaway Company also bid obviously in excess of reasonable cost for the lump sum item of mobilization for pile installation--$600,000 versus $125,000 in Fairchild's bid and less in the bids of several of the others bidders. (The statistical average for the other serious bidders under this item was $225,000.) But the Hardaway Company bid only $60,000 for the lump sum item for removal of existing structures (versus $160,000 in Fairchild's bid) and only $30,000 for the lump sum item for removal and disposal of fender system (versus $110,000 in Fairchild's bid). The portion of the Hardaway Company's bid attributable to mobilization for the roadway work is significantly less than the Fairchild bid under this item ($200,000 versus $375,000) and partially counterbalances the excess in the part of the Hardaway bid for mobilization for the pile installation. The portion of the Hardaway Company's bid attributable to clearing and grubbing also was high, at $20,000 an acre versus a statistical average of $4,200 an acre for the other serious bidders, resulting in $216,000 for the Hardaway Company bid versus, e.g., $32,400 for the Fairchild bid and the $45,360 statistical average. DOT Review Procedures. Section 2-6 of the DOT's Standard Specifications applicable to the project provides: 2-6 Rejection of Irregular Proposals. A proposal will be subject to being considered irregular and may be rejected if it shows omissions, alterations of form, additions not called for, conditioinal or unauthorized alternate bids, or irregularities of any kind; also if the unit prices are obviously unbalanced, either in excess of or below the reasonable cost analysis values. The DOT is in the process of formulating a policy on the use of the Technical Review Committee in the bidding process. A proposed procedure has been developed, which has not yet been made final and has not yet been signed by the Secretary of the DOT, under which the Technical Review Committee would review the low bid on each contract, among other things not applicable to this case, for "any significant irregularities in unit bid prices" and for "unbalanced bidding." The DOT has not yet defined "any significant irregularities in unit bid prices" or "unbalanced bidding" for purposes of defining the event that triggers review by the Technical Review Committee. The DOT Director of the Office of Construction, Robert Buser, is of the opinion that the unit prices the Hardaway Company bid for the sand fill, the shell fill, the reinforcement grid and the Class III seal concrete are "significant irregularities in unit bid prices." On the other hand, the DOT's Preliminary Estimates Engineer, Robert Griner, who, unlike Buser, is a member of both the Technical Review Committee and its Preliminary Technical Subcommittee, and is of the opinion that the Hardaway bid for the sand fill, the shell fill, the reinforcement grid and the Class III (seal) concrete are "mathematical imbalances," not "significant irregularities in unit bid prices," which he would define as bids that omit a unit price, whose numerical values do not match words used to express the values, or that are not signed. Under Griner's approach, which was followed in this case, the Preliminary Technical Subcommittee looks at "mathematical imbalances" to see if they are "material imbalances." If the Preliminary Technical Subcommittee decides that it is not a "material imbalance," it simply reports this finding at the outset of the meeting of the Technical Review Committee, which accepts the finding and does not itself consider the matter any further. Only if the Preliminary Technical Subcommittee reports a "material imbalance" does the Technical Review Committee further consider the question. Front-end Bidding. Under the DOT contract for the project, like other items in the specifications, mobilization and land clearing and grubbing are paid in installments as the work proceeds. But, unlike the other items, all of the portion of the contract attributable to mobilization and land clearing and grubbing is paid by the time the entire project is half completed. Similarly, a contractor is paid for reinforcement steel (substructure) when it is delivered to the site. As a result, by shifting dollars in a bid to these "front-end," lump sum items, a contractor can manipulate the bid process and contract to reasonably insure himself of early payment of these inflated items regardless what may happen to the project later. In analyzing these front-end, lump sum items, Griner treated them (along with the unreasonably low bids on the sand fill, shell fill, reinforcement grids and C III seal concrete) as "mathematical imbalances." Following the guidance of a Federal Highway Administration (FHWA) memorandum, dated May 16, 1988, on the subject of "Bid Analysis and Unbalanced Bids," Griner analyzed the Hardaway bid to be sure it would not be susceptible to cost overruns (it was not) and to be sure the quantities were correctly estimated (they were). He also analyzed the additional cost to the DOT of paying the Hardaway Company early (by the half way point of the project) for the inflated front-end items to determine whether the "mathematical" imbalance was "material," i.e., whether "the mathematically imbalanced bid will result in the lowest ultimate cost to the Government." Based on a twelve percent interest rate, Griner calculated that the inflated front-end items would cost the DOT approximately an additional $98,000, 1/ still much less than the difference between the low Hardaway bid and any other bid. Based on this calculation, Griner concluded that the "mathematical imbalance" in the Hardaway bid was not a "material imbalance" and did not require the award of the bid to Fairchild or one of the other bidders. Griner overlooked and did not apply another portion of the method of analysis in the FHWA memorandum on "Bid Analysis and Unbalanced Bids" that states: There are numerous reasons why a bidder may want to unbalance his/her bid on a contract. One reason is to get more money at the beginning of the project. The bidder does this by overpricing the work done early in the project. This is called "front loading" the contract. The leading case in the "front loading" area is Matter of: Riverport Industries, 64 Comp. Gen. 441 (1985). Here the Comptroller General held that if the bid is front loaded, regardless if it is the lowest bid, it "should be viewed as materially unbalanced since acceptance of the bid would result in the same evils as an advance payment. An advance payment is prohibited by law." The "front loading" may also be materially unbalanced due to the cost of money that must be paid out early versus over the normal construction fo the project. Under the Hardaway Company bid, the pile mobilization, the land clearing and grubbing, and the reinforcement steel (substructure) parts of the bid are "front-ended." 2/ Under the method of analysis suggested by the FHWA memorandum, the Hardaway Company would be paid approximately $428,000 in "advance payments" under these two items if it is awarded the contract. Approximately $375,000 in pile mobilization, $183,600 in land clearing and grubbing, and $289,700 in the reinforcement steel were shifted to these front- end items from the unbalanced sand fill, shell fill, reinforcement grid, and Class III (seal) concrete items. These dollars The shifted dollars are estimated by taking the difference between the statistical average for these items and the Hardaway bid on them. Since roiughly half of the shifted dollars would be paid earlier than they would be paid if they were bid under the sand fill, shell fill, reinforcement grid and Class III (seal) concrete items, the amount of "advance payment," under the FHWA analysis would be approximately $428,000. Griner did not explain why he only followed part, but not all, of the method of analysis suggested by the FHWA memorandum, other than to say he overlooked it. But he also testified that it is common practice for contractors to submit mathematically unbalanced bids, and the DOT always analyzes them the way he did in this case. Indeed, in the March, 1990, bid letting, Griner found "mathematical imbalances" in 21 of the 29 low bids but no "material imbalances." The Fairchild bid also contains "mathematical imbalances." It also "front-ends" several items. The total dollar value of the "front-ending" in the Fairchild bid (including roadway mobilization) closely approximates that found in the Hardaway bid and, under the FHWA analysis, would result in approximately the same amount of advance payment. Under Section 101-2.2 of the DOT's Standard Specifications for this project, contractors are limited to a maximum of ten percent of the total contract for mobilization. The Hardaway Company's total mobilization bid is within the maximum under the specifications. Notwithstanding the imbalances in the Hardaway bid, and the so-called "advance payments" that would result from the "front-ending" in the Hardaway bid, the Hardaway bid remains the lowest and best bid on the project, and it is the best interest of the DOT and the public to award the contract to the Hardaway Company. Even if the Hardaway Company had bid the sand fill, shell fill, reinforcement grid, and Class III (seal) concrete items exactly as Fairchild did, Hardaway still would be low bidder. "Value Engineering" and Alleged Alternative or Contingent Bidding. Inferences reasonably could be drawn from the evidence that the Hardaway Company may intend to propose to the DOT that the approach to the bridge be re-engineered so as to eliminate the need for the sand fill, the shell fill, the reinforcement grid and the C III (seal) concrete. If the DOT accepts such a proposal, the contract between the DOT and the Hardaway Company would have to be modified. If the re-engineered project were to allow the Hardaway Company to do the job for less than its bid price, half (or, if the proposal is innovative or unique, up to 80%) of the savings would be paid to the Hardaway Company under what the DOT calls "value engineering." Under DOT procedures, "value engineering" proposals are not made or evaluated until after the original contract is signed with the successful bidder. It is not an alternative bid or a contingent bid.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Respondent, the Department of Transportation, enter a final order dismissing the bid protest filed by W. R. Fairchild Construction Company, Ltd., and awarding State Project No. 46090-3511 to the Hardaway Company. RECOMMENDED this 30th day of July, 1990, in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of July, 1990.

Florida Laws (1) 120.57
# 6
TAMCO ELECTRIC, INC. vs PINELLAS COUNTY SCHOOL BOARD, 13-002152BID (2013)
Division of Administrative Hearings, Florida Filed:St. Petersburg, Florida Jun. 13, 2013 Number: 13-002152BID Latest Update: Nov. 13, 2013

The Issue Whether Respondent's action to reject all bids submitted in response to ITB 13-803-205, relating to the removal and replacement of the public address system at Countryside High School, is illegal, arbitrary, dishonest, or fraudulent, as alleged in the Amended Petition.

Findings Of Fact On March 4, 2013, the ITB was issued by Respondent for work related to the removal and replacement of the public address system at Countryside High School in Clearwater, Florida. According to the Special Conditions portions of the ITB, the "scope" of the project is to "[p]rovide labor and materials to remove and replace the auditorium sound system as per plans and specifications by Keane Acoustics, Inc." The ITB was assigned bid number 13-803-205 by Respondent. Bids for the contract were to be submitted to Respondent by 3:00 p.m., April 11, 2013. Bids for the project were timely received from two companies. The first company, Becker Communications, Inc., d/b/a BCI Integrated Solutions (BCI), submitted a bid in the amount of $118,143.27. Petitioner submitted a bid in the amount of $108,000.00. There is a section of the ITB titled "special conditions." The special conditions provide in part that "[t]his is an ALL or NONE bid [and] [t]he entire contract shall be awarded to the lowest responsive and responsible bidder meeting the specifications." On April 22, 2013, Respondent posted a notice advising of its intent to award the contract to BCI. Although Petitioner submitted the lowest bid, Respondent determined that Petitioner's bid was non-responsive because the bid failed to include "proof of 5 years [of] experience with this type of work" as required by the special conditions of the ITB. Petitioner interpreted this provision as requiring five years of experience as a certain type of general contractor, which Petitioner had, whereas Respondent intended for the ITB to convey that five years of experience related to the removal and installation of audio equipment was the desired type of experience. Petitioner's failure to respond to the ITB in the manner contemplated by Respondent was a technical, nonmaterial irregularity.1/ Numbered paragraph six of the General Terms & Conditions of the ITB provides in part that Respondent "expressly reserves the right to reject any bid proposal if it determines that the . . . experience of the bidder, compared to work proposed, justifies such rejection." On April 24, 2013, Petitioner provided to Respondent a notice advising of its intent to protest the award of the contract to BCI. On May 3, 2013, Petitioner filed its formal protest challenging Respondent's intended action of awarding the contract to BCI. Petitioner's formal protest enumerated several grounds. Of particular concern to Respondent were Petitioner's assertions that the ITB was "inconsistent with Florida law since bidders [were] not required to submit a List of Subcontractors by the time of opening bid"2/ and that provisions of the ITB were ambiguous with respect to the type of experience required to qualify for bidding.3/ Prior to receiving Petitioner's protest, Respondent was unaware of the fact that its bid specifications governing the disclosure of subcontractors did not comply with Florida law. Upon consideration of Petitioner's grounds for protest, Respondent determined that the ITB, as alleged by Petitioner, failed to comply with section 255.0515, Florida Statutes (2012),4/ and that there was ambiguity in the language regarding the experience requirements for bidders.5/ Respondent refers to the problems with the ITB as "procedural errors." These procedural errors will be referred to herein as "irregularities" as this term is more in keeping with the nomenclature of this area of jurisprudence. Given the ITB's irregularities, Respondent decided to reject all bids. In explaining Respondent's rationale for rejecting all bids, Michael Hewett, Respondent's Director of Maintenance,6/ testified that "the [irregularities] were such that [they] potentially could give an unfair advantage to one bidder over another." As for the issue related to the requirements of section 255.0515, Mr. Hewett explained that neither of the two bidders submitted a listing of subcontractors. It would have been competitively disadvantageous to BCI if Petitioner were able to successfully argue that BCI should be disqualified for failing to provide a listing of subcontractors when Petitioner also failed to provide such listing. During the same approximate time that the ITB in the present case was issued, Respondent issued an ITB for nearly identical work to be performed at one of its other facilities (Palm Harbor). In all material respects, the Palm Harbor ITB was identical to the one at issue herein. Unlike the present case, BCI was the sole bidder for the Palm Harbor project and this distinguishing fact reasonably explains why Respondent did not reject BCI's bid for the Palm Harbor Project even though the ITB therein was plagued with the same irregularities found in the present case.7/

Recommendation Upon consideration of the above findings of fact and conclusions of law, it is RECOMMENDED: That the Pinellas County School Board enter a final order finding that the rejection of all bids submitted in response to ITB 13-803-205 was not illegal, arbitrary, dishonest, or fraudulent, and dismissing Tamco Electric, Inc.'s instant protest. DONE AND ENTERED this 16th day of October, 2013, in Tallahassee, Leon County, Florida. S LINZIE F. BOGAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 16th day of October, 2013.

Florida Laws (3) 120.569120.57255.0515
# 7
ROBERT COOK, SARA COOK, AND ALAN TAYLOR vs DEPARTMENT OF JUVENILE JUSTICE, 98-001641BID (1998)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Apr. 09, 1998 Number: 98-001641BID Latest Update: Aug. 10, 1998

The Issue Whether the Department of Juvenile Justice's (Respondent) decision to reject all bids is illegal, arbitrary, dishonest or fraudulent and should be rejected.

Findings Of Fact Petitioners Robert and Sara Cook own a building located at 205 Gus Hipp Boulevard, Rockledge, Florida. The address for Petitioners Robert and Sara Cook is 1950 Murrell Road, Rockledge, Florida. Petitioner Alan Taylor is an agent for Petitioners Robert and Sara Cook, and assisted the Cooks in the preparation and submittal of their Response to the Department's Request for Proposals for Lease Number: 800:0176-COCOA. Respondent, Florida Department of Juvenile Justice, is the state agency that issued the Request for Proposals for Lease Number: 800:0176-COCOA. Intervenor, 11 Riverside Corp., is the bidder to whom the Respondent issued an award letter for the Lease prior to the Respondent's decision to reject all bids. On or about January 12, 1998, the Respondent advertised Request for Proposals ("RFP") for Lease No. 800:0176-COCOA. This was the second RFP issued by the Respondent for the Cocoa Lease. The Respondent did not receive any bids in response to the first RFP. Draft versions of both RFPs were prepared by Respondent's staff. There were only very "minor changes" in the contents of the first and second RFPs, such as revisions to the issuing and advertising dates. The Respondent received proposals from three entities: Robert and Sara Cook, 11 Riverside Corp., and James E. and Jacie Stivers. All three proposals were timely submitted. Respondent's General Services Manager, Fran Lyles, reviewed the three proposals and completed a responsiveness checklist for each proposal. When Ms. Lyles provided the three responsiveness checklists to Ms. Sandy Veal, the checklists for the proposals submitted by the Cooks and 11 Riverside Corp. did not contain any notations that said proposals were non- responsive. Ms. Lyles also informed Ms. Veal that the proposals submitted by the Cooks and 11 Riverside Corp. were responsive. On or about February 19, 1998, Sandy Veal traveled to Cocoa to perform site visits for the two responsive properties. On February 23, 1998, the Respondent issued a written letter of intent to award the Cocoa Lease to 11 Riverside Corp. The letter was prepared by Ms. Veal and signed by Ms. Lyles. The Petitioners timely filed a written Notice of Protest with the Respondent on March 2, 1998, in which the Petitioners challenged the Respondent's February 23, 1988, decision to award the Cocoa Lease to 11 Riverside Corp. In subsequent correspondent and telephone calls to the Respondent, Petitioners' agent provided a detailed analysis regarding the basis for the Petitioners' Notice of Protest. The primary basis was that the other two proposals were not responsive, and that, as the remaining responsive bidder, the Respondent should award the Lease to the Petitioners. Prior to the deadline for the filing of the Petitioners' Formal Written Bid Protest of the Respondent's February 23, 1988, decision to award the Cocoa Lease to 11 Riverside Corp., the Respondent informed the Petitioners that the Respondent had decided to reject all three proposals that the Respondent had received for the Cocoa Lease. On March 12, 1998, the Respondent provided written notification to the Petitioners that the Respondent had rejected all proposals and would "re issue [sic] at a later date." This date coincided with the deadline for the Petitioners to file their Formal Petition in support of their Notice of Protest pursuant to Florida law. On March 17, 1998, the Petitioners timely filed a second written Notice of Protest with the Respondent, in which the Petitioners challenged the Respondent's March 12 decision. No entity other than the Petitioners timely filed a Notice of Intent to Protest. The Respondent's contention that General Services Manager, Fran Lyles, did not review the RFP prior to its issuance is not credible. Ms. Lyles' testimony that she informed Ms. Veal that all three proposals were not responsive prior to Ms. Veal's trip to Cocoa for a site visit is also not credible. Ms. Lyles signed the award letter to 11 Riverside Corp., even though she had allegedly informed Ms. Veal that all three proposals were non-responsive. Ms. Lyles' explanation that she was very busy and simply didn't ask how an award could be made to a bidder that she had determined was non-responsive is also not credible. Ms. Lyles altered the responsiveness determination checklists after the Petitioners filed their Notice of Protest of the Respondent's award to 11 Riverside Corp. Words were added and white-out was used to cover up Ms. Lyles' initial responsiveness determination which was made prior to the filing of the Petitioner's first Notice of Intent. It appears that such alterations were made by Ms. Lyles in an attempt to shift the responsibility for errors made in the bidding process. The sole basis for the Respondent's contention that the proposals submitted by the Petitioners is non-responsive is that the site plan allegedly failed to show parking spaces. The evidence established that the site plan adequately showed the parking spaces, and that the proposal submitted by the Petitioners was responsive. The Respondent erroneously determined that the proposal submitted by the Petitioners was non-responsive. The proposal submitted by 11 Riverside Corp. failed to include the public entity crime statement as required by the Respondent's RFP, and also failed to include proof of zoning. The floor plan included in the proposals submitted by 11 Riverside Corp. failed to include the calculations as required by the Respondent's RFP. The proposal submitted by 11 Riverside Corp. also failed to include the documentation necessary to establish bidder control of the property as required by the Respondent's RFP. Any one of the aforementioned flaws in the proposal submitted by 11 Riverside Corp. rendered the proposal non- responsive. The building included in the proposal submitted by James E. and Jacie Stivers failed to provide the square footage calculations and failed to provide a scaled floor plan with square footage calculations, as required by the Respondent's RFP. The proposal submitted by the Stivers consisted of two separate facilities. However, the proposal submitted by the Stivers only included the items required by the Respondent's RFP for one of the two separate facilities. The proposal submitted by the Stivers failed to include a letter of authority from the owners of both facilities as required by the Respondent's RFP. Any one of the aforementioned flaws in the proposal submitted by the Stivers rendered the proposal non-responsive. It is not arbitrary for Respondent to reject all bids if there is only one responsive bidder. The state has discretion to award, or not award, in the event of a single responsive bidder, so long as the basis for the rejection is not improper. Whether such rejection is in the best interests of the state may be based on several criteria to be taken into account by the Respondent. One of the criteria is the absence of competition for state business and the lack of offerings. Rejection of all bids can be premised on an omission from the RFP or change in the Respondent's needs that would affect the ability of the Respondent to perform the duties prescribed by the Respondent. The Respondent provided evidence of the importance of correct specifications in the RFP. The Respondent made a decision before January 1, 1998, to develop new specifications for use in lease RFPs. The new specifications were used in the "Bradenton" RFP (issued after the Cocoa lease). The new specifications in the Bradenton RFP include a three percent cap on increases in the lease rate. This specification was material because it is an important part of the Respondent's budget evaluation. It was the Respondent's intent to use this new specification in the Cocoa RFP. Another specification omitted from the Cocoa RFP, that was in the Bradenton RFP, was the specification requiring proposer to provide copies of licenses of contractors. The Respondent intended to use that specification in the Cocoa RFP. The absence of this specification in the part has caused delays in occupancy of the leased space by the Respondent. Another specification omitted from the Cocoa RFP, that was in the Bradenton RFP, was the specification requiring the proposer to provide a construction schedule. The Respondent intended to use that specification in the Cocoa RFP. The absence of this specification was deemed by the Respondent to impede the Respondent's ability to assess liquidated damages. The Respondent identified a lease in Sarasota that was negatively affected by the absence of this specification. Another specification omitted from the Cocoa RFP, that was in the Bradenton RFP, was the specification requiring proposer to pay all renovation costs and that there be no outstanding liens on the property. The Respondent intended to use that specification in the Cocoa RFP. The absence of this specification has resulted in liens imposed on office space the Respondent was procuring. Another specification omitted from the Cocoa RFP, that was in the Bradenton RFP, was the specification clarifying whether the proposed space had to be in a single building. The absence of this specification was a concern to the Respondent and has created problems for other state agencies. The Department did not reject all proposals with the intent of avoiding a protest. The terms of the RFP do not specify when or how the Respondent is to notify proposers of the basis for the rejection of all bids. The evidence is insufficient to show that the Respondent's rejecting all proposals was illegal, arbitrary, dishonest or fraudulent.

Recommendation Upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that the formal bid protest filed by Petitioners be DISMISSED. DONE AND ENTERED this 24th day of June, 1998, at Tallahassee, Leon County, Florida. DANIEL M. KILBRIDE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 24th day of June, 1998. COPIES FURNISHED: David A. Theriaque, Esquire 909 East Park Avenue Tallahassee, Florida 32301 Scott C. Wright, Esquire Department of Juvenile Justice 2737 Centerview Drive Tallahassee, Florida 32399-3100 Theodore E. Mack, Esquire Powell & Mack 803 North Calhoun Street Tallahassee, Florida 32303 Calvin Ross, Secretary Department of Juvenile Justice 2737 Centerview Drive Tallahassee, Florida 32399-3100 Janet Ferris, General Counsel Department of Juvenile Justice 2737 Centerview Drive Tallahassee, Florida 32399-3100

Florida Laws (1) 120.57
# 8
TAMCO ELECTRIC, INC. vs PINELLAS COUNTY SCHOOL BOARD, 13-002153BID (2013)
Division of Administrative Hearings, Florida Filed:St. Petersburg, Florida Jun. 13, 2013 Number: 13-002153BID Latest Update: Nov. 13, 2013

The Issue Whether Respondent's action to reject all bids submitted in response to ITB 13-803-206, relating to the removal and replacement of the public address system at Pinellas Park High School, is illegal, arbitrary, dishonest, or fraudulent, as alleged in the Amended Petition.

Findings Of Fact On March 4, 2013, ITB was issued by Respondent for work related to the removal and replacement of the public address system at Pinellas Park High School in Largo, Florida. According to the Special Conditions portions of the ITB, the "scope" of the project is to "[p]rovide labor and materials to remove and replace the auditorium sound system as per plans and specifications by Keane Acoustics, Inc." The ITB was assigned bid number 13-803-206 by Respondent. Bids for the contract were to be submitted to Respondent by 3:00 p.m., April 11, 2013. Bids for the project were timely received from two companies. The first company, Becker Communications, Inc., d/b/a BCI Integrated Solutions (BCI), submitted a bid in the amount of $130,756.66. Petitioner submitted a bid in the amount of $116,000.00. There is a section of the ITB titled "special conditions." The special conditions provide in part that "[t]his is an ALL or NONE bid [and] [t]he entire contract shall be awarded to the lowest responsive and responsible bidder meeting the specifications." On April 22, 2013, Respondent posted a notice advising of its intent to award the contract to BCI. Although Petitioner submitted the lowest bid, Respondent determined that Petitioner's bid was non-responsive because the bid failed to include "proof of 5 years [of] experience with this type of work" as required by the special conditions of the ITB. Petitioner interpreted this provision as requiring five years of experience as a certain type of general contractor, which Petitioner had, whereas Respondent intended for the ITB to convey that five years of experience related to the removal and installation of audio equipment was the desired type of experience. Petitioner's failure to respond to the ITB in the manner contemplated by Respondent was a technical, nonmaterial irregularity.1/ Numbered paragraph six of the General Terms & Conditions of the ITB provides in part that Respondent "expressly reserves the right to reject any bid proposal if it determines that the . . . experience of the bidder, compared to work proposed, justifies such rejection." On April 24, 2013, Petitioner provided to Respondent a notice advising of its intent to protest the award of the contract to BCI. On May 3, 2013, Petitioner filed its formal protest challenging Respondent's intended action of awarding the contract to BCI. Petitioner's formal protest enumerated several grounds. Of particular concern to Respondent were Petitioner's assertions that the ITB was "inconsistent with Florida law since bidders [were] not required to submit a List of Subcontractors by the time of opening bid"2/ and that provisions of the ITB were ambiguous with respect to the type of experience required to qualify for bidding.3/ Prior to receiving Petitioner's protest, Respondent was unaware of the fact that its bid specifications governing the disclosure of subcontractors did not comply with Florida law. Upon consideration of Petitioner's grounds for protest, Respondent determined that the ITB, as alleged by Petitioner, failed to comply with section 255.0515, Florida Statutes (2012),4/ and that there was ambiguity in the language regarding the experience requirements for bidders.5/ Respondent refers to the problems with the ITB as "procedural errors." These procedural errors will be referred to herein as "irregularities" as this term is more in keeping with the nomenclature of this area of jurisprudence. Given the ITB's irregularities, Respondent decided to reject all bids. In explaining Respondent's rationale for rejecting all bids, Michael Hewett, Respondent's Director of Maintenance,6/ testified that "the [irregularities] were such that [they] potentially could give an unfair advantage to one bidder over another." As for the issue related to the requirements of section 255.0515, Mr. Hewett explained that neither of the two bidders submitted a listing of subcontractors. It would have been competitively disadvantageous to BCI if Petitioner were able to successfully argue that BCI should be disqualified for failing to provide a listing of subcontractors when Petitioner also failed to provide such listing. During the same approximate time that the ITB in the present case was issued, Respondent issued an ITB for nearly identical work to be performed at one of its other facilities (Palm Harbor). In all material respects, the Palm Harbor ITB was identical to the one at issue herein. Unlike the present case, BCI was the sole bidder for the Palm Harbor project and this distinguishing fact reasonably explains why Respondent did not reject BCI's bid for the Palm Harbor Project even though the ITB therein was plagued with the same irregularities found in the present case.7/

Recommendation Upon consideration of the above findings of fact and conclusions of law, it is RECOMMENDED: That the Pinellas County School Board enter a final order finding that the rejection of all bids submitted in response to ITB 13-803-206 was not illegal, arbitrary, dishonest, or fraudulent, and dismissing Tamco Electric, Inc.'s instant protest. DONE AND ENTERED this 16th day of October, 2013, in Tallahassee, Leon County, Florida. S LINZIE F. BOGAN Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 16th day of October, 2013.

Florida Laws (3) 120.569120.57255.0515
# 9
BURROUGHS CORP. vs. DEPARTMENT OF HEALTH AND REHABILITATIVE SERVICES, 86-004460BID (1986)
Division of Administrative Hearings, Florida Number: 86-004460BID Latest Update: Jun. 25, 1987

The Issue The two major issues in this case are as follows: Was the failure of Datamaxx to submit resumes of training and maintenance personnel as required by Performance Mandatory No. 10 of the Invitation to Bid a material deviation from the Invitation to Bid such as to render Datamaxx a nonresponsive bidder? If Datamaxx was a nonresponsive bidder, must the contract be awarded to Burroughs, or must DHRS, pursuant to Section 13A-1.002(3), Florida Administrative Code, have the contract rebid, or seek single source procurement or negotiation approval from the Division of Purchasing?

Findings Of Fact Based on the admissions of the parties, on the testimony of the witnesses at the hearing, and on the exhibits received in evidence, I make the following findings of fact: For at least the past 10 years, the DHRS Data Communications Network has been maintained by Burroughs on a sole source basis. At the end of the previous Burroughs Terminal Maintenance contract with Burroughs, the Department of General Services (DOS) asked DHRS to bid the contract in lieu of sole source procurement, it being the belief of DOS that there was competition in this area. On or about September 19, 1986, DHRS published an Invitation to Bid which advised prospective bidders that sealed bids would be opened on October 20, 1986, for a contract, known as "Burroughs Terminal Maintenance" [Bid No. 86 ATM] regarding maintenance of the terminals of the DHRS Data Communications Network. The Special Conditions of the Invitation to Bid contained, among others, the following provisions: The State has established certain require- ments with respect to bids to be submitted by bidders. The use of "shall," "must" or "will" (except to indicate simple futurity) in this Invitation to Bid indicates a requirement or condition from which a material deviation may not be waived by the State. A deviation is material if, in the State's sole discretion, the deficient response is not in substantial accord with this Invitation to Bid requirements, provides an advantage to one bidder over other bidders, has a potentially significant effect on the quantity or quality of items bid, or on the cost to the State. Material deviations cannot be waived. (at p. 1) No negotiations, decision, or actions shall be initiated or executed by the bidder as a result of any discussions with any State employee. Only those communications which are in writing from the Department's Purchasing office may be considered as a duly authorized expression on behalf of the State. Also, only communications from bidders which are signed and in writing will be recognized by the State as duly authorized expressions on behalf of the bidder. (at p. 2) All personnel performing maintenance must be trained to service the equipment covered by this contract. Training shall be completed before the individual is assigned to service the equipment covered by this contract. Training shall be provided to whatever level is necessary to ensure the individual has the required qualifications to perform satisfactory maintenance service on Burroughs equipment listed in Attachment A of this Invitation to Bid. Bidder shall submit with their bid a summary of their Burroughs training program and resumes of personnel who will be performing this training and the resumes of personnel who will be per- forming the maintenance. (at p. 8) Bidder shall certify to the State, at the time the bid is submitted, that bidder has existing established service centers staffed with personnel trained to service the equipment covered by this contract . . . In lieu of this requirement, if bidder does not have existing established service centers, liaison office, and trained personnel, and bidder submits a plan for compliance, the required certification must be given the State no later than two (2) weeks prior to the anticipated starting date of the contract as indicated in the paragraph of this document entitled Calendar of Events. Failure to comply with this requirement shall result in rejection of the bid and award of the bid to the next lowest responsive bidder. The Invitation to Bid was drafted by the Department of Health and Rehabilitative Services. The only bidders on the contract (other than no- bids) were Burroughs and Datamaxx. DHRS found Burroughs and Datamaxx both to be responsive bidders and posted their bids making them public in the recognized manner of publicizing the bidder to be awarded a bid. Both bids were found to be responsive by DHRS at the time they were made public. The Datamaxx bid was the lowest bid and the Burroughs bid was the next to lowest bid. DHRS staff recommended the contract be awarded to Datamaxx. The Datamaxx bid was approximately $784,000 less than the Burroughs bid. In its bid Datamaxx indicated that it understood and agreed to all provisions of the Invitation to Bid, specifically including those dealing with Mandatory Requirements, Verbal Instruction Procedure, Rejection of Bids, Bid Evaluation, Performance Mandatories, and Certification. Datamaxx submitted the Certification required under the terms of the Invitation to Bid and did not submit a plan for compliance with its bid. Datamaxx never requested in writing that the requirement for resumes be waived, and DHRS never advised Datamaxx in writing that it did not have to submit the resumes. Datamaxx did not submit with its bid the resumes of training and maintenance personnel required under Performance Mandatory 10 of the Invitation to Bid. Performance Mandatory No. 10 required the submission of resumes with the bid, and did not concern an event that would take place after the bid had been let. DHRS considered the requirement for resumes to be a mandatory requirement. The qualifications of the persons who would be performing the maintenance under the contract would have a potentially significant effect on the quality of the maintenance provided. Nothing could be more material to the contract than the ability of the personnel to perform that contract. The difference in the dollar amount of the bids of Burroughs and Datamaxx influenced the decision of DHRS in finding Datamaxx to be a responsive bidder. This was a major reason Datamaxx was found to be a responsive bidder. In evaluating the Datamaxx bid, DHRS went outside the material provided in the Datamaxx bid. Subsequent to the posting of bids, DHRS met with Datamaxx and advised Datamaxx that its initial submission was deficient for not including resumes with the bid, that DHRS had waived the resumes, but that in order for DHRS to continue its recommendation that the bid be awarded to Datamaxx, DHRS had to have the resumes prior to the awarding of the bid. DHRS considered it an error and a deficiency in the bid that the resumes were not furnished. Datamaxx, on November 6, 1986, advised DHRS in a letter to Charles Ray that it would submit a plan which would address, among other things, service personnel resumes by November 17, 1986. DHRS could not have considered Datamaxx's letter of November 6, 1986, in evaluating whether Datamaxx was a responsive bidder, because that letter was not received until after DHRS had already found Datamaxx to be a responsive bidder and recommended that the contract be awarded to Datamaxx. Had Datamaxx not submitted the resumes prior to November 17, 1986, DHRS staff would have recommended that the award of the contract be withdrawn. The performance the State would receive under the contract would directly depend on the qualifications of the persons performing the service and the maintenance, and the resumes would be the only source of information regarding the qualifications of the personnel.

Recommendation For all of the foregoing reasons, it is recommended that a final order be entered to the following effect: Concluding that the bid submitted by Datamaxx USA Corporation on Bid No. 86 ATM should be rejected on the grounds that it is not responsive, Concluding that the bid submitted by Burroughs Corporation should be rejected on the basis of Rule 13A-1.002(3), Florida Administrative Code, and, Providing for the agency to issue a second invitation to bid/request for proposals or take other action provided by Rule 13A-1.002(3), Florida Administrative Code. DONE AND ENTERED this 25th day of June 1987, at Tallahassee, Florida. MICHAEL M. PARRISH Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 FILED with the Clerk of the Division of Administrative Hearings this 25th day of June 1987. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 86-4460B1D The following are my specific rulings on each of the proposed findings of fact submitted by both parties: Findings proposed by Petitioner Paragraphs 1 through 19 are accepted with a few minor editorial modifications. The first two lines of paragraph 20 are rejected as redundant. The remainder of paragraph 20 is accepted. Findings proposed by Respondent Paragraphs 1 and 2 are accepted in substance. Paragraph 3 is rejected as constituting unnecessary details. Paragraphs 4 through 7 are accepted. Paragraphs 8, 9, and 10 are rejected as irrelevant. Paragraph 11 is rejected in part as irrelevant and in part as contrary to the greater weight of the evidence. Paragraph 12 is accepted. Paragraph 13 is rejected as constituting irrelevant and unnecessary details. COPIES FURNISHED: Robert L. Powell Assistant General Counsel Department of Health and Rehabilitative Services 1323 Winewood Boulevard Building One, Room 407 Tallahassee, Florida 32399-0700 Edgar Lee Elzie, Jr., Esquire MacFarlane, Ferguson, Allison & Kelly 804 First Florida Bank Building Tallahassee, Florida 32301 Gregory L. Coler, Secretary Department of Health and Rehabilitative Services 1323 Winewood Boulevard Tallahassee, Florida 32399-0700

Florida Laws (3) 120.53120.57287.042