Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. DAVID H. TINIUS, 82-003268 (1982)
Division of Administrative Hearings, Florida Number: 82-003268 Latest Update: Dec. 02, 1983

The Issue The issue presented for decision herein is whether or not the Respondent, David H. Tinius, unlawfully abandoned a construction project; diverted funds received for completion of a construction project and thereby failed to fulfill his contractual obligations.

Findings Of Fact Based on my observation of the witnesses and their demeanor while testifying, the documentary evidence received and the entire record compiled herein, the following relevant facts are found. By its administrative complaint filed herein signed October 6, 1982, the Petitioner, Construction Industry Licensing Board, seeks to suspend, revoke or take other disciplinary action against the Respondent's registered building contractor's license. During times material herein, Respondent was a registered building contractor and has been issued license No. RB0024083. On approximately April 20, 1978, Respondent entered into a contract with Jess Marks to build a residence in Tamarac, Florida, for the sum of $46,551. Respondent commenced construction of the Mark's residence but left the site when it was approximately forty percent complete. At that time, Respondent had received approximately $44,000 of the contract sum. Jess Marks completed the construction of his residence by hiring another contractor to complete the project and expended approximately $50,000 over and above the contract price as agreed upon by the Respondent to complete his residence. Respondent never returned any of the monies received from the Marks for completion of the residence. On approximately April 24, 1978, Respondent entered into a contract with Abe Abrahams to construct a residence in Tamarac, Florida, for the sum of $30,473. Respondent left the Abrahams' project after he had received $6,000 and had completed approximately ten percent of the work on the Abrahams' residence. Respondent did not return to the site nor did he return any of the monies received from the Abrahams for the construction of their residence (See Petitioner's Composite Exhibit No. 5). The Abrahams had to pay for supplies and material bought for the project by the Respondent and which reportedly had been paid, according to Respondent. THE RESPONDENT'S POSITION As noted hereinabove, the Respondent did not appear to contest or otherwise refute the allegations contained in the administrative complaint filed herein. However, Respondent, through counsel, filed an answer which admitted the complaint allegations filed herein.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, hereby RECOMMENDED that the Respondent's registered building contractor's license No. RB0024083 be REVOKED. DONE and RECOMMENDED this 29th day of August, 1983 in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 29th day of August, 1983 COPIES FURNISHED: Michael J. Cohen, Esquire 2715 East Oakland Park Boulevard Suite 101 Fort Lauderdale, Florida 33306 David H. Tinius 4420 Northwest 36th Court Lauderdale Lakes, Florida 33309 David H. Tinius Post Office Box 6338 Charlotte Amalil St. Thomas, U.S.V.I. 00801 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Fred M. Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (2) 120.57489.129
# 1
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs LEROY JONES, JR., 05-001496PL (2005)
Division of Administrative Hearings, Florida Filed:Miami, Florida Apr. 22, 2005 Number: 05-001496PL Latest Update: Dec. 13, 2005

The Issue Whether Respondent, a licensed general contractor, committed the violations alleged in the three-count Administrative Complaint filed by Petitioner and the penalties, if any, that should be imposed.

Findings Of Fact Respondent is the agency of the State of Florida with the responsibility to regulate building contracting. At all times relevant to this proceeding, Respondent has been licensed as a certified general contractor, having been issued license number CG C058340 in 1996. At all times relevant to this proceeding, Ms. McKinney owned and resided in a house (the House) in Opa Locka, Florida. Ms. McKinney’s mother, Mattie P. Mathis, also lived in the House. In 2001, Ms. McKinney solicited bids for an addition she wanted to put on the House. Ms. McKinney and her mother, Ms. Mathis, planned to pay for the addition with life insurance proceeds on the life of Ms. Mathis’s deceased daughter (Ms. McKinney’s sister). On the recommendation of a colleague at her work, Ms. McKinney asked Willie Muse, Jr., to bid on the work. Based on the bids she received, Ms. McKinney hired Mr. Muse to construct the addition to the House. Ms. McKinney told Mr. Muse that she wanted all work to comply with all applicable permitting requirements and laws. Mr. Muse represented to Ms. McKinney that he would get the necessary building permits and that the work would comply with all applicable laws. On July 18, 2001, Ms. McKinney and Ms. Mathis entered into a written contract with Mr. Muse whereby Mr. Muse agreed to construct the addition for the sum of $45,000.00. Mr. Muse has never been licensed as a general contractor in Florida. Ms. McKinney thought Mr. Muse was a licensed contractor and would not have entered into a contract with him if she had known that he was not licensed. Pursuant to the contract, Ms. McKinney and Ms. Mathis paid Mr. Muse the following amounts on the following dates: $6,000.00 on July 20, 2001; $7,500.00 on October 10, 2001; and $13,500.00 on November 2, 2001; for a total of $27,000.00. On or about August 21, 2001, Mr. Muse brought to Ms. McKinney a building permit application form for her to sign. The application form had been filled out before Mr. Muse presented it to Ms. McKinney. Respondent was not present when Mr. Muse presented the form to Ms. McKinney. Respondent’s name, signature, and contractor’s license number appeared on the application form when Mr. Muse presented the form to Ms. McKinney. Ms. McKinney signed the form on August 21, 2001. Ms. McKinney saw Respondent’s name for the first time when she read the building permit application form. Prior to that time, Ms. McKinney and Ms. Mathis had never known or heard of Respondent. At all times relevant to this proceeding, Respondent knew that Mr. Muse was not a licensed contractor. Mr. Muse submitted the building permit application form to the Miami-Dade County Building Department (Building Department), which issued a building permit for the work on the House on October 5, 2001. Mr. Muse commenced working on the House in October 2001, but he never finished. After he received the payment in November 2001, Mr. Muse stopped working on the House for an extended period of time. During that time, Ms. McKinney attempted on several occasions to persuade Mr. Muse to resume work on the House. Prior to stopping work on the House, Mr. Muse removed a portion of the roof of the existing structure, which exposed the interior of the House to the elements. That exposure resulted in extensive damages to the House, including the collapse of the kitchen ceiling from water intrusion. By letter dated April 15, 2002, the Building Department advised Ms. McKinney that her building permit would expire in approximately 30 days. That letter prompted Ms. McKinney to contact the Building Department, where she was told that Respondent was her contractor, not Mr. Muse. Ms. McKinney secured information (from the face of the building permit) that enabled her to contact Respondent’s mother.3 That contact resulted in two meetings between Ms. McKinney and Respondent towards the end of April 2002. During the first meeting, Ms. McKinney related to Respondent the history of the project, including the amounts that had been paid to Mr. Muse. She also showed him the work that had been done and the damages that had occurred. During the second meeting, Mr. Muse was in attendance. Ms. McKinney, Ms. Mathis, and Respondent reached a verbal understanding that was not reduced to writing. They agreed that Respondent would finish the work on the House for the unpaid balance of the contract price $45,000.00 less $27,000.00 paid to Mr. Muse, which equals $18,000.00.4 The parties agreed that Respondent would pay for labor and that Ms. McKinney and Ms. Mathis would pay material suppliers directly and receive credit toward the contract price for such payments. The parties contemplated that Mr. Muse would perform most of the labor because of the monies he had already received. On the basis of the verbal contract, Respondent resumed the work on the House. On June 12, 2002, Respondent presented a draw request for $3,500.00 for electrical, plumbing, and roofing work that had been performed. Ms. Mathis wrote Respondent a check in the amount of $3,500.00 for that work. Ms. McKinney was opposed to paying Respondent the sum of $3,500.00 because she believed he had not completed the work for which he was billing. Ms. Mathis paid that sum despite Ms. McKinney’s opposition. At some undetermined time following June 12, 2002, Ms. McKinney told Respondent that she did not want Mr. Muse working on the House. Respondent then asked to be paid in advance for work to be done on the House because he would have to pay his laborers. Ms. McKinney and Ms. Mathis would not agree to payment in advance. In July 2002, the project was not complete and Respondent’s progress on the work on the House became unsatisfactory to Ms. McKinney. On October 14, 2002, Ms. McKinney filed a complaint against Respondent with Petitioner, claiming, among other things, that Respondent had abandoned the project. Her complaint alleged that work ended on the project in July 2002. At some undetermined time between June and October 2002, Ms. McKinney filed a criminal complaint against Mr. Muse, which resulted in criminal misdemeanor charges being filed against him in Miami-Dade County Court. After she filed the criminal complaint against Mr. Muse, Ms. McKinney told Respondent that she wanted to wait to proceed with the project until she knew what was going to happen with her criminal complaint. In the criminal proceeding, the Court ordered Mr. Muse on April 11, 2003, to pay restitution to Ms. McKinney in the amount of $16,008.04, payable in monthly installments of $300.00. On March 2, 2004, the Court reduced the amount of restitution to $4,000.00, payable in monthly installments of $50.00 beginning April 1, 2004. As of the date of the final hearing in this proceeding, Mr. Muse had paid Ms. McKinney restitution in the total amount of $750.00. As part of the criminal proceeding, Respondent was asked to give his opinion as to the value of the work completed by Mr. Muse and his estimated cost of completing the work. Respondent valued the work completed by Mr. Muse at $14,073.75 (labor and materials). Respondent estimated that it would cost $22,200.00 to complete the project. Both estimates were dated March 23, 2003. On October 1, 2003, Theodore R. Gay, Assistant General Counsel for Petitioner wrote Ms. McKinney the following letter pertaining to the complaint she had filed in October 2002: The Legal Department has evaluated your complaint against the above named contractor [Respondent]. After reviewing the evidence gathered during the investigation of the referenced matter, we have determined that in accordance with the rules and policies of the Construction Industry Licensing Board, this case is appropriately closed with the issuance of a Letter of Caution to the contractor. Because this case has been dismissed without a finding of probable cause, the file will remain confidential and exempt from the public records. On January 6, 2004, Ms. McKinney wrote Mr. Gay a letter that provided, in part, as follows: This letter is a request to re-open the case [against Respondent] because as prior conversation (sic) when I spoke to you in late August 2003 or early September 2003, I informed you that Mr. Jones told me that he would help me as much as possible to complete the construction on my property. Since your letter that stated you didn’t find any error on Mr. Jones’ behalf, I have not heard or seen him since October 2003, nor has any work been performed on my property. . . . Respondent came back to the House after October 2003 and talked to Ms. McKinney about the work. Ms. McKinney told him that she would pay up to a total of $45,000.00 for the work, but that she would not pay above that figure. Because of the estimate Respondent provided in the criminal proceeding dated March 23, 2003, Ms. McKinney believed that Respondent wanted $22,0000.00 to complete the work. However, Respondent never told her that he would not complete the work for a sum equal to $45,000.00 less the sums that had already been paid. Ms. McKinney would not pay Respondent for work until after the work was completed. After Mr. Gay’s letter dismissing the complaint that Ms. McKinney had filed, Respondent did no further work on the House, but he did have further conversations about the project. Ms. McKinney and Respondent could not agree on payment terms for Respondent to complete the project. Ms. McKinney testified that she did not fire Respondent. However, it is clear that she would not let Mr. Muse do further work on her house and she would not pay Respondent until after the work had been done. Ms. McKinney changed the terms of her verbal contract with Respondent by prohibiting Mr. Muse from working on the project. In November 2003, Ms. McKinney and Ms. Mathis had an argument over the money that had been spent on the house. Ms. McKinney talked to Respondent about his helping her obtain a mortgage on the house to pay for the balance of the work on the House. Ms. McKinney told Respondent that she did not want Respondent to ask her mother for any more money. Ms. McKinney told Respondent that she would use him as the contractor to complete the work if she obtained the financing. Ms. McKinney was unable to get the financing due to the condition of the House. The permits obtained by Respondent are still valid. Ms. McKinney has hired various workers on her own in an effort to complete the work on the House. As of the final hearing, the work on the House had not been completed. As of May 19, 2005, Petitioner’s costs of investigation and prosecution of this case, excluding costs associated with attorney time, totaled $920.29.

Recommendation Based on the foregoing findings of fact and conclusions of Law, it is RECOMMENDED that Petitioner enter a Final Order that adopts the Findings of Facts and Conclusions of Law set forth in this Recommended Order. It is further recommended that the Final Order: Find Respondent guilty of the violation alleged in Count I of the Administrative Complaint and impose against him an administrative fine in the amount of $2,500.00; Find Respondent guilty of the violation alleged in Count II of the Administrative Complaint, but impose no additional administrative fine for that violation; Find Respondent not guilty of the violation alleged in Count III of the Administrative Complaint; Order that Respondent be jointly and severally liable to Ms. McKinney and Ms. Mathis with Mr. Muse for restitution in the amount of $4,000.00, minus $750.00 paid by Mr. Muse; and Order Respondent to pay costs of investigation and prosecution of this matter in the amount of $920.29. DONE AND ENTERED this 10th day of August, 2005, in Tallahassee, Leon County, Florida. S CLAUDE B. ARRINGTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 10th day of August, 2005.

Florida Laws (9) 120.569120.5717.00117.002455.227489.1195489.125489.127489.129
# 2
CONSTRUCTION INDUSTRY LICENSING BOARD vs. KONRAD V. ISING, 83-002892 (1983)
Division of Administrative Hearings, Florida Number: 83-002892 Latest Update: Mar. 19, 1984

The Issue The issue for determination at the final hearing was whether the contracting license of the Respondent Konrad v. Ising should be suspended, revoked, or otherwise disciplined by the Petitioner Department of Professional Regulation, for alleged violations of Chapter 489, Florida Statutes. At the final hearing Petitioner's Exhibits 1 and 2(a)-(g) were offered and admitted into evidence. The Respondent testified on his own behalf.

Findings Of Fact The Respondent Konrad V. Ising is licensed to practice contracting in Florida, and is a licensed certified general contractor holding license number CG C009669, a license current and active from 1982 through the present. The Respondent qualified Master Craft Constructors using license number CG C009669. During 1982, the Respondent entered into an association with Carlton Mosher whereby the Respondent would use his contractor's license to obtain building permits for construction projects which Mosher had contracted. The Respondent hoped his association with Mosher would lead to a partnership and assist him in obtaining practical experience in the construction field. During his association with the Respondent, Mosher was not a licensed contractor. In December 1982, Mosher, doing business as Re-Builders, contracted with Russell Hirstins to construct a room addition on his home at 4034 27th Avenue, St. Petersburg, Florida. On December 3, 1982, an application for a building permit for the job was submitted to the City of St. Petersburg and permit number 88638 was issued. The permit was obtained using the Respondent's license number and Respondent is listed as the job contractor. However, the Respondent performed no work on the Hirstins job, maintained no control over Mosher's work, failed to adequately supervise the project, and failed to qualify Re-Builders with the Construction Industry Licensing Board. Since becoming licensed in 1975, the Respondent has not been involved in any other disciplinary proceedings. At the final hearing, the Respondent candidly acknowledged that his association with Mosher was a regrettable mistake. The project was completed by Mosher to the apparent satisfaction to the Hirstins.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED: That a Final Order be entered by the Construction Industry Licensing Board finding the Respondent Konrad V. Ising guilty of violating Section 489.129(1)(g) and (j), Florida Statutes, and imposing a $250 administrative fine. DONE AND ORDERED this 30th day of January 1984, in Tallahassee. SHARYN L. SMITH Hearing Officer Division of Administrative Hearings 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 30th day of January 1984. COPIES FURNISHED: Charles F. Tunnicliff, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301 Konrad V. Ising Post Office Box 1023 Maitland, Florida 323751 James Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32202 Frederick Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32302

Florida Laws (3) 120.57489.119489.129
# 3
CONSTRUCTION INDUSTRY LICENSING BOARD vs. ROBERT MACCELLI, 81-002988 (1981)
Division of Administrative Hearings, Florida Number: 81-002988 Latest Update: Dec. 04, 1990

Findings Of Fact The Respondent, Robert Maccelli, is a certified general contractor in inactive status for the period 1981 through 1983, holding License #CG C011040. He was in inactive status as of June 1, 1981. (See Petitioner's Exhibit 1.) Respondent was employed as a building inspector for Broward County, Florida. He was required to be a certified contractor to fill this position. (See Petitioner's Exhibit 3.) On June 1, 1982, Respondent pleaded guilty to a charge of violating Section 838.015, Florida Statutes, by taking a bribe in relation to the performance of his duties as a building inspector for Broward County. (See Petitioner's Exhibit 2.)

Recommendation Having found the Respondent, Robert Maccelli, in violation of Section 489.129(1)(b), Florida Statutes, the Hearing Officer recommends that the Construction Industry Licensing Board revoke the certificate of Respondent as a general contractor. DONE and ORDERED this 13th day of July, 1982, in Tallahassee, Leon County, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of July, 1982. COPIES FURNISHED: Michael J. Cohen, Esquire 2715 East Oakland Park Boulevard Suite 101 Fort Lauderdale, Florida 33306 Mr. Robert Maccelli Post Office Box 8243 Fort Lauderdale, Florida 33310 J. K. Linnan, Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Florida 32201 Samuel Shorstein, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301

Florida Laws (3) 120.57489.129838.015
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs THOMAS J. FREESE, 90-001682 (1990)
Division of Administrative Hearings, Florida Filed:Fort Pierce, Florida Mar. 16, 1990 Number: 90-001682 Latest Update: Jul. 27, 1990

The Issue The issue for determination at the formal hearing was whether Respondent allowed an uncertified and unregistered person to engage in prohibited contracting in violation of Subsections 489.129(1)(e), (f), and (m), Florida Statutes. 1/

Findings Of Fact Petitioner is the state agency charged, in conjunction with the Construction Industry Licensing Board, with the responsibility for prosecuting the Administrative Complaint in this proceeding pursuant to chapters 455 and 489, and the rules promulgated thereunder. In September, 1980, license number CG C015802 was issued to Respondent, Thomas J. Freese, as the qualifying agent for Tracy Industries, 728 St. Lucie Crest, Stuart, Florida 33494 ("Tracy"). Respondent was the licensed qualifying agent for Tracy Industries at all times material to this proceeding. At no time material to this proceeding was Robert Sherno licensed by Petitioner as a contractor. On or about May 30, 1988, Mr. Sherno contracted with William F. Meinking to construct a home for Mr. Meinking. The contract price was not to exceed $64,000.00. A building permit was issued for the construction of Mr. Meinking's home on June 8, 1988. The permit was obtained by Mr. Sherno as agent for Respondent. A notice of commencement was filed by Mr. Meinking on June 20, 1988, listing Respondent as the contractor, and listing Mr. Sherno as the person designated by the owner for service of notice and other documents. Respondent authorized Mr. Sherno to obtain the building permit by letter to the local building department dated June 21, 1988 ("authorization letter"). The authorization letter was requested by Robert Nelson who was Tracy's president. Mr. Nelson was personally acquainted with Mr. Sherno and dealt directly but separately with Mr. Sherno and Respondent. Mr. Sherno paid $200.00 to Mr. Nelson at the time of the authorization letter. Mr. Nelson told Respondent that the permit was for the construction of Mr. Meinking's home. Respondent initially questioned the need for a contractor to pull the permit when the owner could build his own house under an owner's permit. Respondent was told that Mr. Meinking and Mr. Sherno were going to develop a number of homes in the area Not only would the number of homes not qualify for an owner's permit, but it was anticipated by Mr. Nelson that the development plan proposed by Mr. Sherno and Mr. Meinking had excellent profit potential for all concerned. Based on that information from Mr. Nelson, Respondent signed the authorization letter. Respondent knew Mr. Sherno and knew that Mr. Sherno was not a licensed contractor. Neither Respondent nor any qualified person supervised the construction of Mr. Meinking's home. One person employed by Tracy in an administrative or clerical capacity visited the construction site occasionally. Respondent inquired of Mr. Nelson from time to time at the offices of Tracy as to the status of construction. Respondent drove by the construction site from time to time, but did not personally supervise construction in any capacity. Respondent did not inspect the progress of construction, provide insurance, discuss the progress of construction with Mr. Meinking, Mr. Sherno, or anyone at Tracy. Respondent assumed that construction was proceeding according to schedule and in a satisfactory manner as long as there were no complaints. Mr. Meinking paid Mr. Sherno the entire $64,000.00 pursuant to the terms of the contract. During the latter stages of construction in the first or second week of November, Mr. Meinking began receiving calls from subcontractors stating that they had not been paid. Mr. Meinking terminated his contractual relationship with Mr. Sherno on or about November 17, 1988. Mr. Meinking paid approximately $16,500.00 to eight subcontractors and an additional $10,000.00 to $12,000.00 to finish construction of his home.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Respondent be found guilty of violating Subsections 489.129(1)(e), (f), and (m), Florida Statutes. It is further recommended that Respondent be fined $2,000.00 which represents the aggregate amount of the minimum fine for each violation. DONE AND ORDERED in Tallahassee, Leon County, Florida, this 27th day of August, 1990. DANIEL MANRY Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of August, 1990.

Florida Laws (2) 120.57489.129
# 6
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs GAETAN MALSCHALCK, 08-002398PL (2008)
Division of Administrative Hearings, Florida Filed:West Palm Beach, Florida May 19, 2008 Number: 08-002398PL Latest Update: Nov. 12, 2019

The Issue Whether Respondent committed the violations alleged in the Administrative Complaint and, if so, what disciplinary action should be taken.

Findings Of Fact Based on the evidence adduced at hearing, and the record as a whole, the following findings of fact are made: Respondent is now, and has been at all times material to the instant case, a Florida-licensed roofing contractor and general contractor. He received his roofing contractor's license on August 10, 2004, and his general contractor's license on October 13, 2005. At all times material to the instant case, GGC has held a certificate of authority authorizing it to engage in contracting in Florida through a qualifying agent. At all times material to the instant case, Respondent has been the primary qualifying agent for GGC. On January 5, 2007, GGC, through Respondent, entered into a written contract with Assad and Millicent Thompson, agreeing, for $37,135.00, to construct a rear porch lanai addition to the Thompsons' single family home in Royal Palm Beach, Florida (Project). The Thompsons paid GGC (by check) $11,140.50 at the time they entered into the contract. They made three subsequent payments to GGC (by check) totaling $21,232.50. The last of these payments was made on or about April 17, 2007. On January 9, 2007, GGC, through Respondent, applied for a permit from the Palm Beach County Planning, Zoning, and Building Department to perform the work it had agreed to do on the Thompsons' home. The permit was subsequently issued. In or around March of 2007, GGC began work on the Project. Dissatisfied with the progress GGC was making on the Project, the Thompsons, on June 5, 2007, sent the following letter to Respondent: With reference to the delay in completing the above construction, we are writing to request your immediate attention. We would like to know specifically: The reason for the delay[.] Your intention in writing as to your estimated time of completion of [the] specified project. Please note we have not physically seen you since April 19, 2007. We understand that inspection of the roof on May 10th resulted in certain violations and as per your conversation with Assad [Mr. Thompson] (when he called you on May 20th), you had problems contacting the Engineer. Please note that his name, telephone and fax are clearly indicated on the plan[s]. Per telephone conversation with him, he has not heard from you recently. You have indicated impatience and anxiety on our part, quite frankly the patience of JOB would have run out long ago. The pile of rubbish is a breeding room for all kinds of creatures and has been a disgusting sight not only for us, but for our neighbors. The open roof has created a vulnerable situation for us and can only deteriorate as we are now in hurricane season. We urge you to contact us urgently with your plan of action. Not having received a written response from Respondent, the Thompsons, on June 25, 2007, sent a follow-up letter to Respondent, which read as follows We note that you have ignored our previous letter of June 5th and you have also failed to honor your telephone promises of June 8th and June 19th to proceed with stucco/electric/rubbish removal etc. In fact absolutely nothing has been done on this job since May 18th. This is totally unacceptable. We have arrangements in place for use of the patio July 14th, cancellation of which will result in serious inconvenience for us. Please be advised that if no progress is made by June 30, 2007, we will be forced to seek all measures at our disposal to have the patio satisfactorily completed. We once again request your urgent co-operation in this matter. The next day, June 26, 2007, the Thompsons received a letter from Respondent (sent by facsimile transmission) acknowledging his receipt of the Thompsons' June 25, 2007, letter. In his letter, Respondent explained that he was "in a bad situation financially" due to circumstances "out of [his] control" related to another project, and he asked the Thompsons to "help [him] resolve[] this matter" by paying the "stucco man" $1,000.00 for materials and an additional $1,000.00 "when [the stucco work] was completed," as well as paying $400.00 for a dumpster to be brought to the Project site (which payments would go towards the monies the Thompsons had to pay for the Project under their contract with GGC). The Thompsons wrote back to Respondent that same day (June 26, 2007), advising him that they would pay for the materials for the stucco work "upon presentation of the invoice, then pay $1,000 for the job on completion as [Respondent had] requested," and that they also would "pay the dumpster charges on completion of the clean-up." Ernest Joseph was the "stucco man" that GGC sent to the Thompsons' home to work on the Project. He last worked on the Project in mid-July 2007. The Thompsons paid Mr. Joseph (by check) a total of $2,000.00 for labor and materials. They also paid Onyx Waste Services (by check) $416.91 to have a dumpster brought to the Project site. Neither GGC, nor anyone acting on its behalf, did any work on the Project after Mr. Joseph left the site in mid-July 2007. The Project was incomplete when the work ceased.2 GGC provided the Thompsons no explanation for the stoppage. In fact, the Thompsons did not hear from GGC at all. The Thompsons were anxious for the Project to be completed, and they did nothing to prevent GGC from accomplishing this objective. After more than 90 consecutive days had passed without any work having been done on the Project, the Thompsons hired another contractor to finish the Project. The Project was ultimately completed. The Thompsons paid $17,540.00 for the additional work that was necessary to complete the Project. The total amount that the Thompsons paid for the Project was $52,329.91 ($32,373 to GGC; $2,000 to Mr. Joseph; $416.91 to Onyx Waste Services; and $17,540.00 to finish the work GGC had failed to do). This was $15,194.91 more than the contract price. Petitioner has incurred a total of $182.90 in investigative and prosecutorial costs in connection with the instant case (excluding costs associated with any attorney's time).

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is hereby RECOMMENDED that the Board issue a Final Order: (1) finding Respondent guilty of violating Section 489.129(1)(j) and (m), as alleged in Counts II and IV, respectively, of the Administrative Complaint; (2) suspending his license for a period of two years; (3) fining him $7,500.00; (4) requiring him to pay restitution in the amount of $15,194.91 to the Thompsons; (4) ordering him to reimburse the Department $182.90 for investigative and prosecutorial costs; and (5) dismissing Counts I and III of the Administrative Complaint. DONE AND ENTERED this 27th day of August, 2008, in Tallahassee, Leon County, Florida. S STUART M. LERNER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 27th day of August, 2008.

Florida Laws (11) 1.01120.569120.57120.60120.68455.2273489.105489.115489.119489.1195489.129 Florida Administrative Code (2) 61G4-17.00161G4-17.002
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. CHARLES A. WUNDER, 82-000721 (1982)
Division of Administrative Hearings, Florida Number: 82-000721 Latest Update: Jun. 07, 1983

Findings Of Fact Respondent is a certified general contractor holding license number CG C005645. His last known address was Raemel Construction & Engineering, Inc., 950 County Club Boulevard, Cape Coral, Florida 33904 (Prehearing Stipulation). I. Although respondent has engaged in contracting under the name of Raemel Construction & Engineering, Inc., since May 27, 1980, he did not qualify this company with the Construction Industry Licensing Board until December 4, 1980. (Prehearing Stipulation; Testimony of respondent.) This was not, however, an intentional violation of the Construction Industry Licensing Law. It wasn't until December, 1980--after consulting with his new attorney--that respondent discovered that his former attorney had not filed the necessary papers to qualify his newly renamed company with the Construction Industry Licensing Board. Upon discovering this omission, he promptly qualified the company with the Board. (Testimony of respondent.) II. In May, 1980, respondent entered an agreement with Bozidar and Rene Devic to build a commercial building to be known as Atrium Plaza on Lots 1-8, Block 359, Cape Coral, Florida. The construction price was $145,000. (R-1.) Thereafter, respondent, together with his on-site building superintendent, carried out the duties of a general contractor. He supervised the construction of the building, helped obtain the construction loan, received the construction loan proceeds, and, in turn, paid the subcontractors. He, together with Mr. Devic, selected the masonry, plumbing, roofing and electrical subcontractors. He pulled the building permit, checked with his on-site building superintendent daily, and inspected the project at least twice a week. He arranged for all building inspections. Indeed, there is no evidence that the respondent acted other than as a competent and responsible general contractor. (Testimony of respondent, Wunder, Cosser.) Herbert J. Werner, Director of the Building and Zoning Department of the City of Cape Coral, submitted a sworn statement on respondent's behalf, a statement which is singular in its praise of respondent's performance as a contractor: It has been my extreme pleasure to have known and dealt with Charles A. Wunder, Sr., during most of the above mentioned [6] years. He has always conducted himself in a most professional manner and I cannot recall a single complaint against him in all that time. Were I to have my choice of people to conduct business with, out of the 2200 contractors within our city, my first choice would be Mr. Charles A. Wunder, Sr. (R-4.)

Recommendation Based on the foregoing, it is RECOMMENDED: That respondent receive a reprimand for violating Sections 489.129(1)(j) and 489.119(2), Florida Statutes (1981). DONE and RECOMMENDED this 21st day of March, 1983, in Tallahassee, Leon County, Florida. R. L. CALEEN, JR. Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of March, 1983.

Florida Laws (3) 120.57489.119489.129
# 8
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION, CONSTRUCTION INDUSTRY LICENSING BOARD vs ANTONIO L. REQUEJO, 15-007339PL (2015)
Division of Administrative Hearings, Florida Filed:Lighthouse Point, Florida Dec. 28, 2015 Number: 15-007339PL Latest Update: Dec. 01, 2016

The Issue Whether Respondent performed an act which assisted an entity in engaging in the prohibited uncertified and unregistered practice of contracting or whether he abandoned a construction project in which he was engaged or under contract as a contractor, in violation of section 489.129(1), Florida Statutes, as set forth in the Administrative Complaint, and, if so, what is the appropriate sanction.

Findings Of Fact The Board is the state agency charged with regulating the practice of construction contracting pursuant to section 20.165 and chapters 455 and 489, Florida Statutes. At all times material to this proceeding, Mr. Requejo was licensed as a certified general contractor in the state of Florida, having been issued license number CGC 1504266. Mr. Requejo’s address of record is 15941 Southwest 53rd Court, Southwest Ranches, Florida 33331. At all times material to this proceeding, Mr. Requejo was the primary qualifying agent of Recol, Inc. Mr. Andre Chestnut was formerly a registered contractor in the state of Florida. He testified credibly that he used to have nine licenses. At all times relevant to this case, he held no state licensure as a contractor. Consistent with Department records, he testified that his license had been revoked sometime around August 2003. USA Screens was incorporated in December 2011 to perform “any and all lawful business,” with Mr. Chestnut as the incorporator, registered agent, and president. Records of the Department contain no evidence that USA Screens, Inc., has ever been qualified by a licensed contractor or had an active license as a construction business. Ms. Carmen Goehrig owned real property at 6300 Pinehurst Circle East in Tamarac, Florida. She wished to install a screen enclosure on the property. On January 21, 2012, she entered into a construction contract with USA Screens, Inc., signed by Mr. Chestnut. This constituted the practice of contracting by Mr. Chestnut and USA Screens, Inc. Mr. Chestnut testified that he had been working in conjunction with Mr. Requejo on various projects for the past nine years. He credibly testified that he received the template for the contract he entered into with Ms. Goehrig from Mr. Requejo. That contract template contains the full name and address for both Recol, Inc., and USA Screens, Inc., at the top of the contract in large type, but shows only one contractor’s license number, that of Mr. Requejo, under the address for Recol, Inc. No contractor’s license number is shown under the USA Screens, Inc., address. Having worked with Mr. Chestnut for nine years, and having prepared the template contract that they used for common projects, Mr. Requejo had reasonable grounds to know that USA Screens, Inc., was uncertified and unregistered, as suggested by the contract itself. The contract mentioned that it was contingent upon both homeowner association and government approvals, and included a handwritten provision that there would be “no material purchases until association approval.” Ms. Goehrig signed two checks to USA Screens, Inc.: the first in the amount of $500.00 for the application; the other in the amount of $3,000.00 for materials. Both checks were cashed on January 24, 2012. On February 14, 2012, Mr. Requejo, d/b/a Recol, Inc., timely filed building permit application 12-636 for construction of the screen enclosure at 6300 Pinehurst Circle East with the city of Tamarac, using his general contractor’s license number. Recol, Inc., is listed as the general contractor in the city’s records. In filing for a permit from the city of Tamarac for the construction, Mr. Requejo assisted USA Screens, Inc., and Mr. Chestnut in engaging in the prohibited uncertified and unregistered practice of contracting. Mr. Claudio Grande is the chief building official for the city of Tamarac. He oversees permitting and is the custodian of records. He testified that permit 12-636 was denied due to zoning restrictions and structural issues. Mr. Chestnut testified that he made numerous calls trying to get the permit approved. He testified that the problem was that the screen enclosure encroached on a utility easement. As Mr. Goehrig testified: They applied for the permit. He showed us the drawings, Andre, and to my knowledge, submitted the permit application. And then we noticed that the second check was cashed, so we started calling him about that. And all he would say is, “Don’t worry, don’t worry, don’t worry.” And then the permit was denied and then we went back and tried to do something to get it approved and it was denied. And then zoning finally denied it again. So three times, we tried to fix it to make it work. And we finally, you know, the zoning department finally came down and said, “No, end of story, no good.” So we went to him and said, “Okay, we can’t get the permit, please just give us our money back and we’ll go on our way.” And of course, his answer was, “No, you’re not getting any money back, I spent your money, goodbye.” After the permit was finally denied and Mr. Chestnut refused to return their money, the Goehrigs contacted Mr. Requejo to get their money back, again to no avail. It was not shown that the project was terminated without just cause or that it was terminated without proper notification to Ms. Goehrig. It is clear from the filed complaint, as well as the testimony that Ms. Goehrig was aware that the project could not be permitted, and sought a return of the money that had been paid. “The permit was denied and [Chestnut] refuses to refund our deposit.” The Department failed to prove that Mr. Requejo abandoned a construction project in which he was engaged or under contract as a contractor. Prior Discipline On February 13, 2013, a Final Order Adopting Settlement and Vacating Prior Orders was filed by the Board. The Order incorporated a settlement agreement imposing discipline for allegations in several earlier Administrative Complaints. The October 2012 settlement agreement required the payment of fines, investigatory costs, and restitution to six individuals, as well as continuing education and a six-year period of probation. The Order constitutes prior discipline within the meaning of the disciplinary guidelines.

Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Construction Industry Licensing Board enter a final order finding Mr. Antonio L. Requejo in violation of section 489.129(1)(d), Florida Statutes; suspending his contractor’s license for a period of six months, followed by a period of probation deemed advisable by the Board; imposing a fine of $7,000.00; and directing that he make restitution in the amount of $3,500.00 to Carmen Goehrig. DONE AND ENTERED this 17th day of March, 2016, in Tallahassee, Leon County, Florida. S F. SCOTT BOYD Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 17th day of March, 2016. COPIES FURNISHED: Sorin Ardelean, Esquire Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202 (eServed) Antonio L. Requejo 11826 B. Miramar Parkway Miramar, Florida 33025 Daniel Biggins, Executive Director Construction Industry Licensing Board Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399 (eServed) William N. Spicola, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399 (eServed)

Florida Laws (6) 120.569120.5717.00117.002489.1195489.129
# 9
CONSTRUCTION INDUSTRY LICENSING BOARD vs. RICHARD L. JOHNANTONIO, 87-003884 (1987)
Division of Administrative Hearings, Florida Number: 87-003884 Latest Update: Mar. 11, 1988

Findings Of Fact Respondent is, and has been at all times material hereto, a registered roofing contractor in the State of Florida, having been issued license number RC 0039352. Respondent is the qualifying agent for Ken and Rick's Roofing, Inc. of Mami, Florida. On May 16, 1986, Ken and Rick's Roofing, Inc. contracted to repair roof leaks for a Victor Krauthaner of 18441 Northeast 21st Place, North Miami Beach, Florida. The contract, signed by Respondent and Mr. Krauthaner, contained a six (6) month warranty on repairs. The contract price was $215.00. Mr. Krauthaner paid the full amount by a check which was cashed by Respondent. On May 17, 1986, David J. Godfried, an employee of Ken and Rick's Roofing, Inc. was dispatched by Respondent to repair Mr. Krauthaner's roof. Godfried removed tiles from the affected portion of the roof and installed new tar paper. The old tiles could not be re-used and Godfried did not have appropriate tiles in stock, so he left the tar paper exposed and promised Krauthaner that he would return with new tiles within a week. No one from Ken & Rick's Roofing, Inc. returned after May 17, 1986 to replace the tile and Krauthaner began experiencing new leaks. Mr. Krauthaner made repeated attempts by telephone and letter to encourage Ken & Rick's Roofing, Inc. to complete the repairs. Representatives of the company repeatedly assured Krauthaner that someone would respond to repair the leaks, but no one ever did. Mr. Krauthaner repaired the leak himself in June of 1987. Chapter 10 of the Code of Metropolitan Dade County requires that roofing contractors working within the county be either certified by the State of Florida or possess a certificate of competency in roofing issued by the county. Respondent's registered roofing license was suspended by The Construction Industry Licensing Board in March 1985 for failure to pay a fine assessed as the result of a previous disciplinary action. The suspension was in effect at the time Respondent contracted to repair the Krauthaner residence. Respondent does not possess a certificate of competency from Dade County, nor did he possess one at the time the contract was executed. Respondent has been disciplined on three prior occasions by The Construction Industry Licensing Board on January 23, 1984 (DPR Case Number 33028); May 21, 1984 (DPR Case Number 42963); and, June 6, 1985 (DPR Case Number 49942). The complaint in Case Number 42963 alleged that Respondent had exceeded the scope of his license by contracting in Dade County without first meeting local competency requirements.

Florida Laws (7) 120.57489.105489.115489.119489.121489.127489.129
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer