Elawyers Elawyers
Washington| Change
Find Similar Cases by Filters
You can browse Case Laws by Courts, or by your need.
Find 49 similar cases
CONSTRUCTION INDUSTRY LICENSING BOARD vs. JOHN C. LEDBETTER, 76-000490 (1976)
Division of Administrative Hearings, Florida Number: 76-000490 Latest Update: Jun. 03, 1977

Findings Of Fact On or about March 3, 1976, the Board served its Administrative Complaint upon the Licensee. On May 18, 1976 the Licensee filed its Answer to the Administrative Complaint. The final hearing in this case was scheduled by Notice dated April 13, 1976, and was rescheduled by Notice dated May 27, 1976. John C. Ledbetter holds Certified General Contractor's License No. CG C5281 issued by the Florida Construction Industry Licensing Board. The Licensee Ledbetter has been a certified contractor at all times relevant to this proceeding. The Licensee was the co-developer of a condominium project known as Ocean Palm Villas South or Ocean Palms Riverfront Condominium. Gerald M. Hadley, Sr., a certified contractor was initially listed as the general contractor for the project. Later Neil Wayne Smith was designated the general contractor. Smith was discharged as the general contractor, and by letter dated June 11, 1973 the Licensee notified the North Peninsular Zoning Commission that he would be substituted as the general contractor. Shortly thereafter Gerald M. Hadley was again designated the general contractor, and the change was acknowledged by the forth Peninsular Zoning Commission by letter dated August 28, 1973. Construction on Ocean Palm Villas South did not commence until after August 28, 1973. No construction was undertaken during the time that Ledbetter was designated as the general contractor. The general contractor was responsible for installation of the walls in Ocean Palm Villas South. A subcontractor was utilized to install the dry wall, but the wall construction was supervised by the general contractor. The original plans called for use of 5/8" thick gypsum wallboard. The wall units were to be installed in the manner depicted in Board Exhibit 5. The gypsum was to be nailed on either side of 4" studs, with insulating material laid between the studs. 5/8" gypsum was not available to the general contractor. 1/2" gypsum wallboard was utilized. A new wall assembly was planned. With this assembly gypsum wallboard was nailed to studs, but the wallboard on the other side of the wall was nailed to alternately interspaced studs. Insulating material was woven between the interspaced studs. (See: Board Exhibit 3). The decision to use this assembly was made by Gerald A. Hadley, a labor foreman. Hadley's father was the general contractor, and was consulted in making the decision. A Mr. Rasmussen, the building inspector, was consulted about the wall assembly, and he gave his approval. At the time that construction was under way on the Ocean Palm Villas South project, the 1965 Edition with Revisions of the Southern Standard Building Code was in effect in the North Peninsular Zoning District of Volusia County. The Ocean Palm Villas South project lied within that district. The wall assembly utilized by the general contractor does not precisely follow any of the assemblies set out as appropriate in the code. The wall assembly utilized does, however, meet the one hour fire resistance standard required by the code. There was no evidence presented at the hearing from which it could be concluded that the Licensee Ledbetter had any knowledge of the wall assembly utilized in this project other than what was set out in the original plans. Ledbetter was not the contractor for the project when the assembly was constructed.

# 1
FLORIDA BOARD OF PROFESSIONAL ENGINEERS vs THOMAS PLOTTS, P.E., 12-002526PL (2012)
Division of Administrative Hearings, Florida Filed:Tampa, Florida Jul. 25, 2012 Number: 12-002526PL Latest Update: Dec. 25, 2024
# 2
# 3
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION vs DONALD CLARK, 02-000978 (2002)
Division of Administrative Hearings, Florida Filed:Clearwater, Florida Mar. 01, 2002 Number: 02-000978 Latest Update: Dec. 01, 2003

The Issue The issue in this case is whether Respondent committed the acts alleged in the Administrative Complaint and if so, what penalty is appropriate.

Findings Of Fact Based upon the testimony of the witnesses and the evidence presented and the entire record in this proceeding, the following material and relevant facts are found. At no time material hereto was Respondent, Donald Clark, licensed by the State of Florida Construction Industry Licensing Board to engage in construction contracting. At no time material hereto was Cancun Development Company ever qualified or certified by any State of Florida agency as a certified contractor. With knowledge of that he was not licensed by the State of Florida to solicit, engage in, nor contract for construction work, Respondent entered into an oral agreement with homeowner Ms. Eichar to build a second-story addition to her home, located in Indian Rocks Beach, Florida, for a contract price of $30,000.00. Respondent, who was paid by Ms. Eichar a total of $25,000.00, subcontracted with Mr. Erwin, a licensed electrical contractor, to do the electrical work at the Eichar's residence for $2,364.00. Respondent, after notice, failed to attend the formal final hearing regarding this matter. The investigative and prosecution costs to the Department of Business and Professional Regulation, excluding cost associated with attorney time, were $550.00.

Recommendation Based on the foregoing findings of fact and conclusions of law, it is recommended that a final order be entered by the Department as follows: Finding Respondent, Donald Clark, guilty of having violated Subsection 489.127(1)(f), Florida Statutes, as alleged in the Administrative Complaint herein filed and imposing as a penalty an administrative fine in the amount of $5,000.00. Assess costs of investigation and prosecution, excluding costs associated with an attorney's time, in the amount of $550.70. DONE AND ENTERED this 23rd day of July, 2002, in Tallahassee, Leon County, Florida. FRED L. BUCKINE Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 23rd day of July, 2002. COPIES FURNISHED: Donald Clark 813 East Bloomingdale Avenue Suite 252 Brandon, Florida 32720 Brian A. Higgins, Esquire Department of Business and Professional Regulation 1940 North Monroe Street Tallahassee, Florida 32399-2202 Hardy L. Roberts, III, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202

Florida Laws (3) 120.57455.228489.127
# 4
CONSTRUCTION INDUSTRY LICENSING BOARD vs. RICHARD A. VALDES, 79-000956 (1979)
Division of Administrative Hearings, Florida Number: 79-000956 Latest Update: May 19, 1980

The Issue Whether Respondent, a certified general contractor, is guilty of pulling permits for construction projects not supervised by Respondent, and, if so, the appropriate disciplinary action which should be taken by the Board.

Findings Of Fact At all times material hereto, Respondent was the holder of Certified General Contractor's License No. CG C005204 issued by the Board. Although this license was active at the time the Administrative Complaint was filed, Respondent has placed it on an inactive status until June 30, 1981. (Stipulation, Testimony of Respondent) As to Amiguet Construction Project During 1976, Jose Amiguet entered into a contract with San Pedro Construction Inc. for the construction of an addition to his existing residence located at 1409 Granada Boulevard, Coral Gables, Florida. (Stipulation, Petitioner's Exhibit 1) Since San Pedro Construction Inc. was not properly licensed as a building contractor, it was not qualified to apply for and obtain a Coral Gables building permit to undertake this residential addition. Therefore, on January 12, 1977, pursuant to an agreement with Jose San Pedro, representative of San Pedro Construction Inc., the Respondent applied and obtained the required Coral Gables building permit under his on name. (Stipulation, Testimony of Respondent, Charles Kozak, Petitioner's Exhibit 1) The Respondent did not participate in, manage, or supervise, in any manner, the construction of the Amiguet residential addition by San Pedro Construction Inc. Jose Amiguet neither knew the Respondent, nor had any dealings with him during the construction work. (Stipulation, Testimony of Respondent) Final inspection of the Amiguet construction project has not been conducted by the Coral Gables building inspection department since the required documentation concerning sidewalk improvements and subcontractors used has not yet been submitted. The actual construction work has, however, been completed, to the satisfaction of Jose Amiguet. (Testimony of Charles Kozak, Respondent) Respondent made an effort to assist Jose Amiguet in obtaining the final inspection and clearance by the city building inspection department. However, since Respondent did not supervise the subcontractors' work, he cannot truthfully complete the required documents. He has, therefore, offered to (1) pay for the additional costs associated with obtaining the necessary final inspection, and (2) transfer to Jose Amiguet the right to receive, after final inspection, the refund of the contractor's performance bond in the amount of approximately $400-$500. (Testimony of Respondent) As to the Shaw Construction Project During July, 1977, and on February 8, 1978, James L. Shaw entered into separate contracts with San Pedro Construction Inc. for the construction of residential improvements at 836 Obispo Avenue, Coral Gables, Florida. The final contract was in the amount of $16,700.00. (Stipulation, Testimony of Respondent, James L. Shaw, Petitioner's Exhibit 4) Since San Pedro Construction Inc. was an unlicensed contractor, Respondent, on November 15, 1977, pursuant to an agreement with that company, applied for and obtained the required Coral Gables building permit. (Stipulation, Testimony of Respondent, James L. Shaw, Petitioner's Exhibit 4) The Respondent did not participate in, manage, or supervise in any manner the construction of the Shaw residential improvements by San Pedro Construction Inc. James Shaw neither knew Respondent, nor had any dealings with him during the construction work. (Stipulation, Testimony of Respondent) On or about April, 1978, the lending institution for the Shaw project, and James Shaw stopped making construction payments to San Pedro Construction Inc., due to its failure to proceed on and abandonment of the project. (Testimony of James Shaw, Charles Kozak) On June 20, 1978, James Shaw obtained an "owner-builder" permit from the City of Coral Gables and incurred the following costs in order to complete the construction project as originally planned: $12,000 for labor and materials, and $625.00 for architectural services. Inasmuch as approximately, $10,128.00 had earlier been paid to San Pedro Construction Inc. for the construction project, the total cost of the project to James Shaw was approximately $22,753.00-$6,053.00 in excess of the original contract price. (Testimony of James Shaw and Respondent) San Pedro Construction Inc. is no longer in business, and the whereabouts of its owner, Jose San Pedro, is unknown. (Testimony of Respondent) As with the Amiguet construction project, final inspection of the Shaw project cannot be conducted until missing documentation relative to sidewalk improvements and subcontractors involved is supplied. In an effort to assist James Shaw, the Respondent has offered to transfer to Shaw the right to receive, after final inspection, the refund of the contractor's performance bond in the amount of approximately $400-$500. (Testimony of Charles Kozak and Respondent) At all times material hereto, the Respondent was aware that it was unlawful, under both state law and the Code of Metropolitan Dade County, to aide an unlicensed contractor in evading the contractor licensing law, and to use one's license to pull permits for projects not supervised by the licensee. (Stipulation, Testimony of Respondent, Petitioner's Exhibit 1) The Metro Dade Construction Trades Board heard the complaint against the Respondent and found prima facie evidence and probable cause to refer the matter to the Florida Construction Industry Licensing Board (Stipulation) Notwithstanding the evidence presented, the Administrative Complaint and the Board's counsel at hearing limited the amount sought for restitution purposes to $5,300.00, provided both the performance bonds are refunded to the benefit of Jose Amiguet and James Shaw. (Administrative Complaint, statement of Board's Counsel) Respondent regrets having taken the actions complained of in the Board's Administrative Complaint, and now more fully understands the resulting burdens which have been placed on Jose Amiguet and James Shaw. (Testimony of Respondent)

Recommendation Guilty, as charged. Respondent's certified general contractor's license should be suspended until such time as full restitution is made to the persons damaged by his actions.

Florida Laws (2) 120.57489.129
# 5
CONSTRUCTION INDUSTRY LICENSING BOARD vs. E. J. POLLOCK, 79-000502 (1979)
Division of Administrative Hearings, Florida Number: 79-000502 Latest Update: Feb. 27, 1980

Findings Of Fact This cause comes on for consideration based on the Administrative Complaint of the Petitioner, State of Florida, Department of Professional and Occupational Regulation, Florida Construction Industry Licensing Board, now referred to as State of Florida, Department of Professional Regulation, Florida Construction Industry Licensing Board. The essential allegations of the Administrative Complaint are as found in the issue statement of this Recommended Order and that discussion in the issue statement is incorporated into the Findings of Fact and made a part hereof. The Petitioner, State of Florida, Department of Professional Regulation, Florida Construction Industry Licensing Board, is an agency of the State of Florida, which has the responsibility to regulate those individuals who serve the public in the capacity of contractors in the State of Florida. This regulatory function carries with it the obligation to prosecute those individual licensees whom the regulatory agency believes to have committed offenses as defined by Chapter 468, Florida Statutes. The possible outcome of such a prosecution carries with it the potential revocation or suspension of the license of those persons regulated by the agency. On this occasion, by Administrative Complaint, the Petitioner has charged E. J. Pollock, d/b/a Miami Advertising, Inc., with violations of Chapter 468, Florida Statutes, as set out herein. The Respondent has replied to the Administrative Complaint by reguesting a Subsection 120.57(1), Florida Statutes, hearing, which de novo hearing was held on the date and at the time and place set out above. E. J. Pollock, d/b/a Miami Advertising, Inc., is the holder of a Certified general Contractor's license, No. CG C004577, held with the Petitioner. That license was current and active in October, 1975, and continued as an active license until the year 1977 when the license became inactive and it remains inactive at this time. The facts reveal that the Respondent in 1975 entered into a discussion with Dr. Thor Brickman about assisting Dr. Brickman in obtaining a building permit from the Metropolitan Dade County Building and Zoning Department, Dade County, Florida. This permit was to allow the construction of certain office alterations of Dr. Brickman's office located at 1136 N.W. 119th Street, Dade County, Florida. The plans and specifications for such alterations may be found as Petitioner's Exhibit No. 8 admitted into evidence. After some discussion, the Respondent and Dr. Brickman concluded an arrangement by which the Respondent would act as a contractor on the job, in the sense of having the overall responsibility for its construction. This included the responsibility to pay the workers, sub contractors and material man. The agreement between Pollock and Brickman was one in which Pollock was acting in his individual capacity as opposed to through affiliation with a contracting firm. However, at the time Pollock entered into this agreement with Dr. Brickman, his Certified general Contractor's license had been transferred to an affiliation with Miami Advertising, Inc. The Respondent had made this transfer in anticipation of a job to be performed for Miami Advertising, Inc., and in fact certain preliminary matters had been concluded with Pollock acting as manager for the project for Miami Advertising, Inc. Miami Advertising, Inc., was without knowledge of the contract between Pollock and Dr. Brickman. Notwithstanding the lack of knowledge on the part of Miami Advertising, Inc., and the representations to Brickman that the Respondent was acting in his individual capacity when he contracted to remodel Brickman's office, the Respondent applied for a building permit to be issued by the Dade County Building and Zoning Department and in doing so he indicated that he was securing that permit as a qualifier for Miami Advertising, Inc. This can be seen in the petitioner's Exhibit No. 5 admitted into evidence which is a copy of the building permit application as issued on October 31, 1975. Pollock commenced the work and Dr. Brickman paid Pollock directly for the work that was being done. The parent checks were endorsed and cashed by Pollock. The amount Pollock received totaled $6,797.22. Sometime in December, 1975, the owner, Dr. Brickman, became disenchanted with some of the workers whom Pollock had on the job in the sense that those workers had been drinking while on the job. Brickman advised Pollock of this and indicated to Pollock that he did not want those persons on the job without supervision. Nonetheless, the owner continued to advance money to Pollock to pay for the job as contracted for. In January, 1976, the Respondent left the job and Brickman was of the impression that the roof on the extension was finished and that there was no problem with the roof, but this impression was wrong because in February, 1976, one of the owner's tenants began to complaint about the roof leaking and those complaints continued until the tenant moved out due to water damage. This caused Brickman to lose moneys in rentals. When Brickman spoke with Pollock about the leaking roof, Pollock sent a roofer to the job to see about the problems but Brickman was not satisfied with that roofer and declined to have him make any corrections to the roof job. (Although the Respondent denies the responsibility for the completion of the roofing work on the Brickman project, the testimony clearly reveals that he had accepted that responsibility as a part of the contract.) The roofer spoken of, whose name is Montgomery, came to the job in March, 1976. Subsequent to Montgomery's visit, problems continued to occur with the roof and the condition of the roof in April, 1976, and the interior of the building may be seen in the Composite Exhibit No. 1 by the Petitioner, which is a series of photos depicting the roof and interior. Pollock would not return and complete the job and Dr. Brickman made a complaint to cause administrative charges against the Respondent. This original complaint was dropped and in November, 1977, Pollock called about completing the job which was still unfinished. Brickman agreed to have Pollock cane and complete the job. Pollock did not return to the job as he stated he would do. In December, 1978, a representative of the Metropolitan Dade County Building and Zoning Department went to the project and found that the job was closed and found that no framing inspection had been requested by Pollock and completed as required by Metropolitan Dade County Building and Zoning Department Code. Other matters within the job site were found to be deficient. The original building permit had expired and the required roofing permit had never been granted. The condition of the project as it existed at the time of the inspection may be found in certain photographs taken by the Building Inspector which may be found as a part of the Petitioner's Composite Exhibit No. 2 admitted into evidence. The problem with permits was subsequently rectified; however, based upon the inspector's evaluation, notices of violations were filed in January, 1979, against the Respondent Pollock. The violations spoken to above were for violations of the building and zoning code, particularly Metropolitan Dade County Building and Zoning Department Code No. 305.2, failure to call for inspections between October 31, 1971, and January 4, 1979, and Metropolitan Dade County Building and Zoning Department Code Section No. 304.4(b), failure to construct office alterations according to plans between October 31, 1975, and January 4, 1979. (These provisions are part of the South Florida Building Code which is used by Metropolitan Dade County.) The charges were made through a two-count information in Case 79-53600 in the County Court in and for Dade County, Florida. For the former violation, the Respondent was adjudged guilty and received a fine of $750.00 with $25.00 court costs, and for the latter count Pollock was sentenced, with the sentence being suspended from day to day and term to term. This Statement of Charges and Disposition may be found as petitioner' s Composite Exhibit No 3 admitted into evidence, a copy of the Charges, Judgment, Sentence and Order of the Court. The Respondent, Pollock, was also charged by Metropolitan Dade County with a violation of the Code of Metro Dade, Chapter 10, Section 10-22 (b), abandonment of the construction project without legal authority. (The disposition of that charge is unknown to the Hearing Officer, in that it was not presented as a matter of proof in the course of the hearing and the facts of the existence of such charge came in by a stipulation of fact between the parties to this action.) The Respondent returned to the job in January, 1979, and on the date of the hearing 95 to 99 percent of the job had been completed. Still remaining to be completed were certain roofing work with metal-to-metal soldering and gravel stops to be concluded and at that time the roof was still leaking. In view of the damage to Brickman' s property, a claim was made against the liability insurance required by Subsection 468.106(6), Florida Statutes. This claim was denied by the insurance carrier because their insurance covered Miami Advertising, Inc., only, and that company had no knowledge of the contract or the job. An indication of this denial may be found as Petitioner's Composite Exhibit No. 4 admitted into evidence, which are copies of letters denying coverage. They are addressed to Dr. Brickman and are from Parliament Insurance Company, insurer of Miami Advertising, Inc.

Recommendation It is recommended that the Respondent, E. J. Pollock, who holds his license as qualifier for Miami Advertising, Inc., License No. CG C004577, be suspended for a period of one (1) year. This recommendation is made with the knowledge of the letters offered in mitigation of the penalty. DONE AND ENTERED this 26th day of November, 1979, in Tallahassee, Florida. CHARLES C. ADAMS, Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: Barry Sinoff, Esquire Sinoff, Edwards & Alford 2400 Independent Square One Independent Drive Jacksonville, Florida 32202 H. Adams Weaver, Esquire 310 Okeechobee Boulevard Post Office Box "M" West Palm Beach, Florida 33402 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD

Florida Laws (1) 120.57
# 6
FLORIDA BOARD OF PROFESSIONAL ENGINEERS vs ABBAS BORUJERDI, P.E., 11-002108PL (2011)
Division of Administrative Hearings, Florida Filed:Tamarac, Florida Apr. 27, 2011 Number: 11-002108PL Latest Update: Dec. 25, 2024
# 7
CONSTRUCTION INDUSTRY LICENSING BOARD vs. GARY A. SMITH, 78-001780 (1978)
Division of Administrative Hearings, Florida Number: 78-001780 Latest Update: Feb. 13, 1979

Findings Of Fact Gary Smith d/b/a Sirmons Roofing Company is a roofing contractor registered with the Florida Construction Industry Licensing Board. Smith does not hold any license issued by local construction licensing boards which does not license roofing contractors. Smith admitted that he had commenced construction projects without acquiring the appropriate building permits from the local building officials. Calvin Smith identified a contract, Exhibit 2, which he had entered into with Gary Smith d/b/a Sirmons Roofing regarding the repair of the roof of his house. This contract called for the replacement of bad wood, which was understood by the parties to refer to rotten wood planking and rafters. Calvin Smith stated that after construction commenced and the old roof had been removed, his house had suffered rain damage although Gary Smith had advised him that the roof had been dried in. Gary Smith explained that he had in fact laid the requisite felt paper on the roof but that a severe wind and rain storm and occurred immediately following which had destroyed the felt paper. Smith stated that a crew was on the job during the storm at all times trying to keep the felt nailed down and maintain the water-tight integrity of the roof. There were no delays following the removal of the roof in replacing the felt and diligently proceeding with the re-roofing. Several days after the storm the roof had been finished, the plywood ceiling of the family room of Calvin Smith's house was partially removed to permit the insulation to be replaced. At this time Calvin Smith discovered rotten wood which Smith felt should have been removed and replaced by Gary Smith pursuant to their contract. Gary Smith stated that he had found one rotten rafter, but that he had advised Calvin Smith of the fact that it was there and that Calvin Smith realized that he was not replacing it. Gary Smith stated that he had removed and replaced all the rotten wood in the roof and that the rotten wood discovered by Calvin Smith was on that portion of the family room roof which was under the eaves of the pre-existing roof of the house where it could only be seen upon removal of the family room ceiling. Gary Smith further testified that subsequent to finding the rotten wood, Calvin Smith had not permitted him to correct the job and that he had not personally seen the rotten wood, pictures of which Calvin Smith had identified. Calvin Smith identified photographs of the interior and exterior of the roof as repaired by Gary Smith. These photographs were received as Exhibits 3 and 8. Exhibits 7 and 8 were photographs of the exterior of the roof. Exhibit 8 is a photograph of a shingle which was not properly installed. Gary Smith admitted that the shingle was not properly installed but stated that it would have been corrected prior to finishing the job. Exhibit 7 is a photograph showing a course of shingles which does not have the proper overlap. Gary Smith explained that this short run of shingles was necessary to even up or balance the runs on both sides of a hip in the roof because the distance from the eave to the top or peak of the hip was not the same on both sides. Gary Smith also pointed out that in both photographs the shingles are laid so that the bottom of the upper course of shingles comes to or overlaps the lower course of shingles to the top of the tab, causing good contact between the shingles and the adhesive strips. Contrary to the assertion of Calvin Smith that the shingles had been laid in such a manner that the adhesive strips did not touch. Calvin Smith had identified Exhibit 6 as photograph of roof flashing on the family room roof which he asserted was improperly installed. Gary Smith stated that the flashing in Exhibit 6 was installed in accordance with the manufacturer's recommendation and that the roof on the family room had the requisite number of layers of felt and tar as required by the building code. Gary Smith stated that he could not identify the purported location of the underside of the roof depicted in Exhibit 5 and identified by Calvin Smith as being in the middle of the family room. Gary Smith stated that he could not identify the purported location of the underside of roof depicted in Exhibit 5 and identified by Calvin Smith as being in the middle of the family room. Gary Smith stated that he had shown the rotten beam indicated in Exhibit 4 to Calvin Smith and that Calvin Smith had known that he was not replacing the bean because replacement would have required the removal of the family room ceiling as well as the sheeting on the roof over the beam. Gary Smith stated that the wood shown in Exhibit 3 was not rotten but water stained and that the beam was sufficiently solid to hold the weight of the roofing materials on top of it and to nail the new sheeting into. Tommy Thompson, construction inspection supervisor of the City of Jacksonville, inspected the roof of Calvin Smith's home. Thompson found that the shingles had not been lapped properly, that some shingles had been laid so that the ceiling strips would not adhere properly, that rotten rafters and wood had been left, that the correct number of nails had not been placed in the shingles, that metal flashing around the chimney had not been installed in accordance with the manufacturer's specifications, and that one, twelve inch hold had been left in the roof sheeting. Thompson identified the Building Code of the City of Jacksonville and those portions of the code relating to installation of roofing materials. Thompson stated that the items mentioned in the paragraph above constituted violations of the code. Thompson also pointed out that it was a violation of the code to commence construction or repair of a roof without obtaining the requisite building permit. J. R. Bond, Executive Director of the Construction Trades Qualifying Board of the City of Jacksonville, stated that the board did not certify roofers. The ordinances of the City of Jacksonville empower the Construction Trades Qualifying Board to hear complaints against state registered but unlicensed contractors. However, the board lacks authority to take direct action against persons who are state registered but unlicensed. The board may only request that the city building official not issue the individual any further building permits. The building official must exercise his own independent authority and judgment in determining whether to suspend an individual's right to obtain building permits. The building official suspended Smith's privilege to obtain permits without a hearing.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, the Hearing Officer recommends that Smith's registration as a roofing contractor be suspended for a period of one year. DONE and ORDERED this 3rd day of January, 1979, in Tallahassee, Florida. STEPHEN F. DEAN Hearing Officer Division of Administrative Hearings 530 Carlton Building Tallahassee, Florida 32304 Telephone: 904/488-9675 COPIES FURNISHED: Michael Egan, Esquire 217 South Adams Street Tallahassee, Florida 32304 Gary A. Smith Sirmons Roofing Company 3845 Edidin Drive Jacksonville, Florida 32211 J. K. Linnan, Executive Director Florida Construction Industry Licensing Board Post Office Box 8621 Jacksonville, Florida 32211 ================================================================= AGENCY FINAL ORDER ================================================================= BEFORE THE CONSTRUCTION INDUSTRY LICENSING BOARD FLORIDA CONSTRUCTION INDUSTRY LICENSING BOARD, Petitioner, vs. CASE NO.: 78-1780 GARY A. SMITH d/b/a SIMMONS ROOFING CO., RC 0030047, 3845 Edidin Drive, Jacksonville, Florida 32211, Respondent. /

# 8
FLORIDA BOARD OF PROFESSIONAL ENGINEERS vs ALBERTO CARDONA, P.E., 15-000656PL (2015)
Division of Administrative Hearings, Florida Filed:St. Petersburg, Florida Feb. 09, 2015 Number: 15-000656PL Latest Update: Dec. 25, 2024
# 10

Can't find what you're looking for?

Post a free question on our public forum.
Ask a Question
Search for lawyers by practice areas.
Find a Lawyer