Findings Of Fact On July 5, 1978, Gulfside applied to DER for the issuance of a permit to operate a wastewater treatment plant on property owned by it on Perdido Key in Escambia County, Florida. The proposed plant is designed to serve a condominium complex consisting of 64 units, with the expectation that 350 gallons of water per day per unit will be discharged into the system, thus requiring a minimum plant capacity of 22,400 gallons per day. The plant described in the application has a capacity to handle 24,000 gallons per day. The proposed plant will use an extended aeration process whereby effluent is routed from the individual units through a filter within the proposed plant and then discharged into two percolation ponds associated with the facility. The plant is designed to remove 90 percent of B.O.D. and suspended solids. In addition, the plant is designed with duplex blowers and pumps to insure continued operation in the event of failure of one of the units. An emergency generator is included to provide back-up power for the entire plant, including blowers, pumps and chlorinators. Perdido Key, where the proposed plant is to be located, is a barrier island located off the coast of Escambia County, Florida, near the Florida- Alabama border. There is substantial residential development presently on Perdido Key, but no central sewer system exists to service the area. Currently, only septic tanks and package sewer plants are available for waste treatment purposes on the island. Adjacent to Perdido Key is Old River, which has been classified a Class III water. Soils on Perdido Key are primarily sandy, and as a result, have a high percolation rate. The problem of high percolation rate through the soils of Perdido Key was adequately addressed by Gulfside in the design of percolation ponds associated with the proposed plant. The two percolation ponds are designed to be located at a minimum of four feet elevation above maximum high ground water level. In fact, during DER's review of this application, Gulfside agreed to raise the bottom elevation of these percolation ponds in response to a concern regarding their initial location in close proximity to the water table. The problem of the expected fast percolation rate was addressed in designing the size of these percolation ponds, and also taken into consideration in designing the method of distributing effluent across the bottom surface of the ponds. With regard to the latter consideration, initial design of the project contemplated a single point for discharge of effluent into each percolation pond. However, Gulfside has agreed to redesign these percolation ponds in such a fashion to discharge effluent more evenly throughout the bottom area of the ponds too combat the problem of the excess percolation rate. The proposed percolation ponds are designed with surface areas in excess of 15,000 square feet. The ponds were initially designed utilizing a six-to-one slope, which would have given twice the bottom surface area of the three-to-one slope eventually required by DER in the process of reviewing the application. The three-to-one slope shown in the plans and specifications results in a bottom surface area of 2,974 square feet. However, the engineering report submitted with the application indicates that percolation ponds will have a bottom surface area of 4,480 square feet. From the evidence, it would appear appropriate for the ponds to have a minimum bottom surface area of 4,480 square feet. From the evidence, this problem can easily be rectified by raising the bottom elevation of the percolation ponds by approximately one foot. This requirement should be imposed as a condition to the granting of the requested permit. The proposed plant, although designed to remove 90 percent of B.O.D. and suspended solids, is not designed to remove nutrients from the effluent. However, the evidence establishes that these nutrients. Will be removed by a combination of filtration through soil substrata and biological action in the percolation ponds. Gulfside has also agreed to install a spartina marsh waterward of the percolation ponds to act as a final nutrient scrubber. The system design is reasonably calculated to assure removal of harmful quantities of nutrients, and no competent evidence was adduced to indicate that the system design was not sufficient for this purpose. Thus, although the treatment plant is proposed to be located only 50 feet from Old River, there is no indication that it will, in fact, result in any adverse impacts to that water body. In addition, DER has no rules or guidelines regulating distances from which package sewer plants, such as that proposed in this application, should be located from bodies of water such as Old River. It should be noted here that the application which is the subject of this proceeding is solely for the purpose of construction of the proposed facility. DER has imposed a permit condition requiring an initial four months operation for appropriate testing to determine compliance with the rules and regulations promulgated by DER before issuance of an operation permit. If testing demonstrates noncompliance with DER's rules and regulations, the operating permit for the facility can be denied. Testimony adduced at the hearing established that members of Petitioner, Southest Escambia Improvement Association, Inc., own property in the vicinity of the proposed facility, and that they utilize waters surrounding Perdido Key for sailing, swimming, crabbing and other recreational uses. Both Petitioner and Gulfside have submitted Proposed Findings of Fact. Petitioner's Proposed Findings of Fact numbered 1, 2, 3, 4 and 8 have been substantially adopted in this Recommended Order. Gulfside's Proposed Findings of Fact numbered 1 through 5 have also been substantially adopted in this Recommended Order. To the extent that Proposed Findings of Fact submitted by either Petitioner or Gulfside are not adopted in this Recommended Order, they have been specifically rejected as being either irrelevant to the issues under consideration in this cause, or as not having been supported by the evidence.
Findings Of Fact Kyle Brothers Land Company, Inc. filed its application with the Department of Environmental Regulation to excavate four canals and to unplug two canals which they had already dug within its development in Port Pine Heights located on Big Pine Key, Monroe County, Florida. The application of Kyle Brothers Land Company, Inc. was introduced as Composite Exhibit No. 1 and a plat of the proposed development was introduced as Exhibit 9. The proposed activity would be constructed on Class 3 waters as defined in Chapter 17-3, F.A.C. Test data submitted shows that the water quality of the water in the existing canals meets or exceeds the standards established in Section 17-3.09, F.A.C. The proposed canals, as well as the existing canals, are being developed as residential home sites. Two potential threats exist to the maintenance of water quality standards within the canals. The first threat is the short-term effect of increased turbidity of the waters due to the construction of the proposed activity. The second threat is the long-term effect of the increased pollution of the waters resulting from waste disposal through proposed septic tank systems to be used in the residential home sites adjoining the proposed and existing canals. The permit application appraisal, Exhibit 2, indicates that the short- term effects of increased turbidity could be controlled by the use of plugs, screens, and daily testing for turbidity and dissolved oxygen. The evidence further shows a variance in the depth of the existing canals and the two plugged canals. The two plugged canals and several of the existing canals have a depth greater than the central canal. The variance in depth permits the accumulation of debris and silt in the finger canals which under certain conditions could be stirred up and become suspended in the waters of the canals increasing the turbidity of the canals and violating the water quality standards. To prevent this from occurring these canals would have to be filled to bring them to the depth of the central canal. The long-term threat to water quality in the canals is the introduction into the canals of nutrients and chemicals attributable to surface water runoff and the proposed septic tank systems to be utilized on the residential home sites. Control of surface water runoff can be obtained by backs loping the uplands away from the canals. The control of nutrient loading associated with the septic tank systems is more complex. The Declaration of Restrictions for Port Pine Heights, Exhibit 7, recites that sewage disposal shall be by septic tank or central disposal plant. However, the plans submitted by the Applicant do not indicate any provision for establishment of a central disposal plant. Further, under the provisions of the deed restrictions there is no requirement that a resident of Port Pine Heights use a central disposal plant even if such a system were available. The current residents of Port Pine Heights currently use septic tank waste disposal systems; however, the number of current residents is substantially less than the number of residents that Port Pine Heights is designed to accommodate. The disposal of sewage by septic tanks will result in the introduction in the canal waters of partially treated effluent through exchange with subsurface waters in the porous limestone substrata present in the area. To maintain the water quality at the required level, the waste effluent from the residential development must be prevented from entering into the canal. Because of the substantial difference in the level of development existing in Port Pine Heights currently and the potential level of development, the test data and the projections based upon that data do not give reasonable assurances that the increased pollutions attributable to the use of septic tanks would not violate water-quality standards.
Recommendation Until the Applicant makes a reasonable, affirmative showing that the long- term effect of the activity will not violate the water-quality standards, the application should be denied. DONE and ORDERED this 22nd day of October, 1976 in Tallahassee, Florida. STEPHEN F. DEAN, Hearing Officer Division of Administrative Hearings Room 530, Carlton Building Tallahassee, Florida 32304 (904) 488-9675 ================================================================= AGENCY FINAL ORDER ================================================================= STATE OF FLORIDA DEPARTMENT OF ENVIRONMENTAL REGULATION KYLE BROTHERS LAND COMPANY, INC. Petitioner, vs. CASE NO. 76-607 DEPARTMENT OF ENVIRONMENTAL REGULATION, Respondent. /
The Issue The issue in this case is whether Respondent KW Resort Utilities Corp. ("KWRU") is entitled to issuance, by Respondent Department of Environmental Protection ("DEP"), of Domestic Wastewater Facility Permit FLA014951-012-DWIP and UIC Permits 18490-020 and 18490-021 (collectively, the "Permit at Issue"), authorizing the major modification of KWRU's existing permit to operate a domestic wastewater facility located at 6630 Front Street, Stock Island, Florida 33040. The Permit at Issue would authorize the expansion of KWRU's existing domestic wastewater facility and the installation of two additional underground injection wells.
Findings Of Fact The Parties Petitioner Last Stand is a not-for-profit corporation incorporated under Florida law. Last Stand has challenged the Permit at Issue in this proceeding. Petitioner George Halloran is a natural person residing in Key West, Florida, and is a member of Last Stand. Halloran has challenged the Permit at Issue in this proceeding. Respondent KWRU is a Florida corporation. KWRU is the wastewater utility service provider that owns and operates the Existing Wastewater Facility2/ and is responsible for its design, construction, operation, and maintenance. It is the applicant for the Permit at Issue in this proceeding. Respondent DEP is the state agency charged with administering the domestic wastewater program in Florida pursuant to chapter 403, Florida Statutes, implementing, as applicable, rules codified at Florida Administrative Code Chapters 62-4, 62-302, 62-303, 62-520, 62-528, 62-600, and 62-620, and various industry standards and manuals incorporated by reference into DEP rules. DEP's proposed agency action to grant the Permit at Issue is the subject of this proceeding. Background and Overview Domestic Wastewater Regulation in the Florida Keys The State of Florida has recognized the need to protect the Florida Keys' unique, sensitive environmental resources. To that end, portions of the Florida Keys are designated, pursuant to statute and by DEP rule, as an Outstanding Florida Water ("OFW"). § 403.061(27), Fla. Stat.; Fla. Admin. Code R. 62-302.700(9). The Florida Legislature also designated the Florida Keys an Area of Critical State Concern. § 380.0552, Fla. Stat. A stated purpose of this designation is to protect and improve the Florida Keys nearshore water quality through construction and operation of wastewater facilities that meet the requirements of section 403.086(10). Additionally, the Florida Legislature has enacted section 403.086(10), which addresses the discharge of domestic wastewater in the Florida Keys. That statute finds that the discharge of inadequately treated and managed domestic wastewater from small wastewater facilities and septic tanks and other onsite systems in the Florida Keys compromises the coastal environment, including the nearshore and offshore waters, and threatens the quality of life and local economies that depend on these resources. Section 403.086(10) directs that after December 31, 2015, all new or expanded domestic wastewater discharges must comply with the treatment and disposal requirements of the statute and DEP rules. Specifically, domestic wastewater treatment facilities having design capacities greater than or equal to 100,000 gallons per day must provide basic disinfection of the wastewater pursuant to DEP rule and must treat the wastewater to a level of treatment, which, on a permitted annual average basis, produces an effluent that contains no more than the following concentrations of the specified constituents: Biochemical Oxygen Demand ("CBOD5") of 5 milligrams per liter ("mg/L"); Suspended Solids of 5 mg/L; Total Nitrogen, expressed as N of 3 mg/L; and Total Phosphorus, expressed as P of 1 mg/L. Collectively, these effluent standards constitute the "advanced wastewater treatment" ("AWT") standards. Section 403.086(10)(e) also imposes requirements regarding disposal of treated domestic wastewater effluent through underground injection. Section 403.086(10)(e)1. requires Class V injection wells serving domestic wastewater treatment facilities having design capacities of less than one million gallons per day (hereafter "MGD") to be at least 90 feet deep and cased to a minimum depth of 60 feet, or to such greater cased depth and total well depth as may be required by DEP rule. Section 403.086(10)(e)2. requires Class V injection wells serving wastewater treatment facilities with design capacities greater than or equal to 1 MGD, excluding backup wells, to be cased to a minimum depth of 2,000 feet or to such greater depth as may be required by DEP rule. The Existing Wastewater Facility KWRU currently is permitted, pursuant to Permit FLA014591 (the "Existing Permit"), to operate a domestic wastewater facility (the "Existing Wastewater Facility" or "Facility")3/ located at 6630 Front Street, Stock Island, Florida. Stock Island is located immediately east and slightly north of Key West. By way of background, KWRU's domestic wastewater system currently consists of three elements: a collection system, which collects wastewater from serviced properties; a transmission system, which transmits wastewater from the collection system to the treatment plant; and the Existing Wastewater Facility, which treats the wastewater and then sends it either as reclaimed water for reuse as irrigation water at the Key West Golf Club, or for toilet flushing or air conditioning makeup water at other facilities specified in the Existing Permit,4/ or disposes of it as treated effluent through two underground injection wells. No modifications to the collection or transmission systems have been proposed or challenged. Thus, only the proposed modifications to the Existing Wastewater Facility are at issue in this proceeding. The Existing Wastewater Facility serves residential and commercial properties located on Stock Island, Florida, immediately adjacent to Key West in the lower Florida Keys. Specifically, the Facility treats domestic wastewater originating from approximately 1,416 existing residential connections and 216 commercial connections. The commercial connections consist of a convalescent center, a college, restaurants, recreational vehicle parks, an animal clinic, and a hospital. There are no industrial wastewater contributors to the Facility. The Facility includes a Category III, Class C wastewater treatment facility operating under the Existing Permit. It is staffed by a Class C or higher operator for six hours a day, seven days per week, in accordance with the Existing Permit and applicable DEP rules. The Facility has a design capacity and a permitted capacity5/ of .499 MGD annual average daily flow ("AADF") and consists of two treatment trains having capacities of .249 MGD and .250 MGD AADF. These treatment trains are piped together to allow operation of the Facility as a single plant. The Facility was upgraded in the mid-2000s and is capable of treating influent wastewater to AWT. However, as authorized under the Existing Permit, the Facility currently treats domestic wastewater to secondary standards, which do not impose nitrogen or phosphorous limits. Under the Existing Permit and in accordance with section 403.086(10), the Facility is not required to meet AWT standards until January 1, 2016. Vacuum and gravity collection systems collect the domestic wastewater from the properties that KWRU services. Wastewater influent from the collection systems flows through the transmission system to a splitter box at the KWRU property, where it is sent to the Facility for treatment. The Facility contains two treatment trains, each consisting of a bar screen, an equalization tank, an aeration tank, an anoxic zone, a post-aeration basin, a clarifier, a silica sand/river rock filter, and a chlorine contact chamber. The bar screens, which constitute the first step in the treatment trains, remove floatables from the wastewater stream. After passing through the bar screens, the wastewater drops into two equalization tanks. As their name indicates, the equalization tanks smooth out the peaks in wastewater flow to the Existing Wastewater Facility. Specifically, wastewater flows to the Facility in large volumes during two periods each day, morning and evening, corresponding with peak water use by the serviced properties. During these large flow volume periods, the equalization tanks fill up with sewage influent, which is meted out during lower-flow periods for treatment by the Facility. In this manner, the Facility treats roughly the same amount of wastewater per hour, which is key to the steady state operation of, and the reliable treatment of the wastewater by, the Facility. From the equalization tanks, the wastewater is directed to the three-stage bioreactor portion of the treatment process. Microorganisms are utilized at each stage to break down the waste. The first stage of the bioreactor process occurs in the aeration basins. Here, wastewater enters the fine-air zone, where it and the microbes used in this stage of the treatment process come into contact with tiny oxygen bubbles. The microorganisms use the oxygen to oxidize the waste and complete the ammonification of the wastewater. The wastewater then passes through bulkheads to the anoxic zones, where the oxygen level is extremely low. In the anoxic zones, bacteria denitrify, or remove nitrogen from, the wastewater. The wastewater is then sent to the post-aeration basins, where excess carbon is removed through oxidation. Thereafter, the wastewater is sent to the clarifiers, where the microorganisms settle out of the wastewater to form a solid precipitate on the bottom of the tank. The precipitate is plowed into a sump and returned by pump to the bioreactors, where the microorganisms are reused in the activated treatment process. When the microorganisms cease to optimally function in treating the waste, they are culled from the treatment process and sent to a digester, where they oxidize, through the endogenous decay process, to the point that they die and only their endoskeletons remain. Sludge, consisting of the endoskeletons and water, is pumped to a sand filter drying bed. The filtrate water is pumped back through the Wastewater Facility to be reused in the wastewater treatment process, while the dried endoskeletons, which are termed "biosolids," are transported offsite for disposal in a Class I landfill. The treated, clarified wastewater is pumped through sand/rock filters, then to the chlorine contact chambers where it is exposed to a minimum of 15 minutes of chlorine disinfection. As noted above, the Existing Permit authorizes the reuse of reclaimed water for, among other uses, irrigation by land application at the 100.27-acre Key West Golf Club golf course. The golf course irrigation system consists, in part, of two unlined interconnected ponds that do not directly discharge to surface waters6/ and that have a storage capacity exceeding one million gallons. KWRU sends reclaimed water to the golf course through its reclaimed water reuse system only in the quantity required to meet the course's irrigation needs. The Existing Permit imposes a minimum residual chlorine level of 1 mg/L and a maximum of 5 mg/L turbidity for the treated wastewater to be considered reclaimed water that can be reused as irrigation at the golf course or as otherwise authorized in the Existing Permit. If the treated wastewater does not meet these standards, switchover/interlock equipment at the Facility disables the power to the pumps that send the reclaimed water offsite for reuse.7/ At that point, the treated wastewater is considered treated effluent.8/ The effluent fills the effluent wet well and is piped directly to the existing underground injection wells for disposal. Pursuant to the Existing Permit, the effluent is disposed of by gravity flow through two Class V, Group 3, ten- inch underground injection wells bored to a depth of 110 feet and cased to a minimum depth of 60 feet. Collectively, the two injection wells have a maximum permitted capacity of .499 MGD AADF. As authorized by the Existing Permit, the underground injection wells discharge the effluent to Class G-III ground water within the Key Largo Limestone.9/ The underground injection wells are not the primary means of disposal for the treated wastewater, in the sense that they are used to remove effluent from the Facility only if and when reclaimed water is not needed by the golf course or the other receiving facilities, or when the treated wastewater does not meet the required residual chlorine and turbidity limits discussed above. The Existing Permit and the activities authorized thereunder are not at issue in this proceeding. Activities Authorized by the Permit at Issue The Permit at Issue proposes to authorize the construction of a new .350 MGD treatment train, which will increase the design capacity and permitted capacity of the plant from .499 MGD to .849 MGD AADF. The proposed modification of the Existing Wastewater Facility entails the addition of a 90-foot diameter tank containing an influent screen, a 105,554-gallon influent equalization tank, a 163,000-gallon aeration chamber, a 154,725-gallon post-anoxic chamber, a 35,525-gallon re-aeration zone, a 112,062-gallon clarifier, and a 317,950-gallon digester. The sand filters and chlorine contact chambers currently in use will be expanded to accommodate flows from the new treatment train, and the chlorine contact chambers will be changed to liquid bleach feed. The Permit at Issue also proposes to authorize the construction and operation of a new .499 MGD AADF underground injection well system consisting of two new Class V, Group 3 ten- inch wells, drilled to a depth of at least 110 feet and cased to a depth of at least 60 feet, which would discharge effluent to Class G-III ground water within Key Largo Limestone. When placed into service along with the two existing injection wells, the total design capacity and permitted capacity of all four underground injection wells would be .998 MGD AADF.10/ The existing reclaimed water reuse system for the Key West Golf Club or the other receiving facilities currently is authorized for a permitted flow capacity of .499 MGD AADF and a design capacity of 1 MGD AADF. The Permit at Issue would authorize the construction of a new reclaimed water reuse system having a permitted capacity of .849 MGD AADF; however, the design capacity of the system remains 1 MGD AADF, and the amount of reclaimed water sent to the golf course for reuse as irrigation is not being changed by the Permit at Issue from that currently authorized by the Existing Permit. Hereafter, the proposed modifications to the Existing Wastewater Facility that are the subject of the Permit at Issue are referred to as the "Project." The expanded facility resulting from completion of the Project is referred to as the "Expanded Wastewater Facility." The Existing Wastewater Facility treatment trains will be modified to meet the AWT standards as of January 1, 2016. Specifically, an alkalinity control system, a carbon injection system, and an alum injection will be added and certain aspects of the wastewater treatment process will be modified as necessary to meet the AWT standard. The new treatment train proposed as part of the Project will be designed to meet the AWT standards upon operation, which will not occur sooner than 2016. Accordingly, as required by section 403.086(10(d)1., all effluent from the Expanded Wastewater Treatment Facility will meet the AWT standards as of January 1, 2016. As a result of conversion of the wastewater treatment process to AWT, and even assuming all treated effluent is injected down the wells, total nitrogen loading will be decreased from 58 pounds per day to 15.9 pounds per day and total phosphorous loading will be decreased from 14.4 pounds per day to 5.3 pounds per day. This is the case even though the volume of effluent disposed of through the wells may as much as double. Only the activities comprising the Project, which are the proposed to be authorized by the Permit at Issue, are the subject of this proceeding. The Permitting Process The overarching purpose of the wastewater facility permitting process, including permitting of modifications to an existing wastewater facility, is to ensure that the wastewater facility does not discharge wastes to any waters of the state without first being given the degree of treatment necessary to protect the beneficial uses of such waters. This is accomplished by requiring the facility to be designed, constructed, and operated in accordance with applicable DEP rule standards, which incorporate industry standards. Fla. Admin. Code R. 62- 600.100(1). Similarly, the overarching purpose of the Underground Injection Well System permitting process is to protect the quality of underground sources of drinking water and prevent degradation of the quality of other aquifers adjacent to the injection zone that may be used for other purposes. This is accomplished by requiring underground injection wells to be designed, constructed, and operated in accordance with applicable DEP rule requirements and standards. Fla. Admin. Code R. 62- 528.100(1). The Wastewater Facility or Activity Permit Application Form 1, General Information, and Application Form 2A, Permit for Domestic Wastewater Treatment and Reuse or Disposal Facility, which are adopted by rule, are the forms that must be completed and submitted to DEP to receive authorization to modify existing wastewater facilities or construct new wastewater facilities. This form includes a list of requirements, some (but not necessarily all) of which apply to proposed modification of an existing wastewater facility. The form requires that a Florida- licensed P.E. certify that the engineering features of the project have been designed by the engineer in conformance with the sound engineering principles applicable to such projects, and that, in his or her professional judgment, the facility, when properly constructed, operated, and maintained, will comply with all applicable statutes and the rules. The Application to Construct/Operate/Abandon Class I, III, or V Injection Well System, which is adopted by rule, is the application form that must be completed and submitted to DEP to receive authorization to construct and operate a Class V Injection Well System. This application form includes a list of requirements, some (but not necessarily all) of which apply to a specific underground injection well construction project. The form requires that a Florida-licensed P.E. certify that the engineering features of the injection well have been designed and examined by the engineer and found to conform to modern engineering principles applicable to the disposal of pollutants as proposed in the permit application. By signing and sealing the application, the P.E. certifies that, in his or her professional judgment, there is reasonable assurance that the injection well, when properly maintained and operated, will discharge effluent in compliance with all applicable statutes and rules. Once the application forms are submitted, DEP permitting staff reviews the applications and determines whether items on the forms and any materials submitted to support those items are incomplete or need clarification. In that event, staff sends the applicant a Request for Additional Information ("RAI"), requesting the applicant to provide additional information to address incomplete or unclear aspects of the application. Once the applicant has provided information sufficient to enable DEP to review the application for issuance or denial of the permit, DEP determines the applications complete and reviews the project for substantive compliance with all applicable statutory and rule permitting requirements. DEP is authorized to issue the permit, with such conditions as it may direct, if the applicant affirmatively provides reasonable assurance, based on the information provided in the application, that the construction, expansion, modification, operation, or activity of the installation will not discharge, emit, or cause pollution in contravention of DEP standards or rules proposed in the application. Fla. Admin. Code R. 62-4.070(1). If the applicant fails to provide such reasonable assurance, the permit must be denied. Conversely, if the applicant provides such reasonable assurance, the applicant is legally entitled to issuance of the permit. Engineering Design of the Project KWRU retained Weiler Engineering Corporation to design the proposed modifications to the Existing Wastewater Facility and the new underground injection well (again, collectively referred to as the "Project") and to prepare and submit the applications for the Permit at Issue to DEP. Edward Castle and Christopher Johnson prepared the applications for the Permit at Issue. As the applicant, Johnson signed the application documents as required pursuant to the application form. As the engineer of record, Castle signed and sealed the certifications in the application forms, representing that he was the engineer in responsible charge of preparing the Project's engineering documents. Castle's signature and seal on the application forms for the wastewater treatment facility expansion portion of the Project constitute his representation that he designed and examined the engineering features of the wastewater treatment facility expansion; that these features conform to sound engineering principles applicable to the Project; and that, in his professional judgment, the wastewater treatment facility expansion portion of the Project, when properly constructed, operated, and maintained, will comply with all applicable statutes and rules, including the requirement that the effluent meet the AWT standards as of January 1, 2016. Similarly, Castle's signature and seal on the application to construct the new underground injection wells constitute his representation that he designed the engineering features of these injection wells; that the injection wells conform to modern engineering principles applicable to the disposal of pollutants as proposed in the permit application; and that in his professional judgment, there is reasonable assurance that the wells, when properly maintained and operated, will discharge effluent in compliance with all applicable statutes and rules, including the requirement that the effluent discharged through the injection wells meet AWT standards as of January 1, 2016. As previously noted, the design capacity of wastewater treatment portion of the Expanded Wastewater Facility is proposed to be .849 MGD AADF. Castle selected this design capacity based on historic wastewater flows at the Existing Wastewater Facility and foreseeable projected wastewater treatment capacity demand in the future.11/ Specifically, to estimate future capacity demand, Castle considered development agreements, requests for utility service, the existence of scarified property and applicable development density, wetslips, recent property sales, and estimated and proposed in-fill development on Stock Island. He projected residential development wastewater treatment demand based on historic actual flow data from the Monroe County Sanitary Wastewater Master Plan ("Master Plan"), in conformance with the Recommended Standards for Wastewater Facilities, the so- called "Ten States Standards," a wastewater systems design and planning guidance document incorporated by reference in rule 62- 600.300(4). Additionally, Castle applied the estimated sewage flows codified in Florida Department of Health rule 64E-6.008, Table I, System Design Estimated Sewage Flows ("DOH Table I"), to estimate wastewater treatment demand for projected commercial and hotel development uses. Once Castle had projected wastewater capacity demand for residential and hotel/commercial uses at buildout on Stock Island, he factored in an additional 15 percent capacity safety factor to derive the .849 MGD AADF design capacity for the Expanded Wastewater Facility. Castle chose AADF, rather than the maximum monthly average daily flow or three-month average daily flow, as the timeframe for the design capacity based on historical flow amounts to the Existing Wastewater Facility and because of insignificant seasonal variations in historical flows to the Facility.12/ This is because the population on Stock Island contributing flow to the Existing Wastewater Facility is largely comprised of non-seasonal residents and commercial operations.13/ Nonetheless, to ensure the Expanded Wastewater Facility will have adequate capacity to effectively treat wastewater to the required standards during higher flow periods that may result from non- residential seasonal occupancy in the future, Castle assumed year-round, 100 percent occupancy for the projected hotel and commercial development on Stock Island in determining the design capacity for the Expanded Wastewater Facility. Castle estimated a peak hourly flow of 1.273 MGD for the Expanded Wastewater Facility. This figure estimates the maximum flow through the facility on an hourly basis specifically to take into account the diurnal variability of wastewater flow entering the facility. By definition, the peak hourly flow is a maximum hourly flow rather than the sustained flow or volume into or through the facility. The projected maximum hourly flow of 1.273 MGD, which was determined by multiplying the annual average daily flow by a peaking factor of 1.5, is an estimate of the maximum hourly flow wastewater coming into the Expanded Wastewater Facility's equalization tanks. Importantly, it is not the volume of wastewater flow, on an annual average daily basis, that will leave the facility's equalization tanks and flow through the facility's treatment process. Put another way, the 1.273 MGD peak hourly flow is not the Expanded Wastewater Facility's design capacity. As previously noted, the permitted capacity of the wastewater treatment portion of the Expanded Facility also would be .849 MGD AADF. The permitted capacity is the amount, on an annual average daily flow basis, that the wastewater treatment portion of the Expanded Wastewater Facility is authorized to treat and discharge. This metric establishes an absolute limit, on an annual average daily basis, on the quantity of wastewater that can be treated by, and discharged from, the Expanded Wastewater Facility. Also as discussed above, once the two new underground injection wells are installed, the total design capacity of the four wells at the Expanded Wastewater Facility will be .998 MGD AADF. The two new injection wells are being added to ensure adequate disposal capacity for the .849 MGD permitted capacity and, importantly, to accommodate the peak hourly flow. The reclaimed water reuse system currently has an authorized design capacity of 1 MGD AADF, and this is not being changed by the Project, although the permitted capacity is being increased to .849 MGD AADF. As discussed in greater detail below, neither the design capacity nor the permitted capacity of the reuse system is a function of the irrigation application rate per acre of the golf course, and neither represent the amount of irrigation applied to the golf course per day. In determining the design capacity for the Expanded Wastewater Facility, Castle considered wastewater capacity demand for the facility through the year 2020, rather than over a 20- year period. This is because buildout of the properties on Stock Island that will contribute flow to the facility is reasonably projected to occur between 2018 and 2020. After buildout, there will be no additional properties being developed to contribute additional wastewater flows to the Expanded Wastewater Facility. The credible, persuasive evidence establishes that the proposed design capacity of .849 MGD AADF for the Expanded Wastewater Facility is appropriate under rule 62-600.200(19) and other pertinent provisions in chapter 62-600 and conforms to sound engineering principles applicable to the Expanded Wastewater Facility. The credible, persuasive evidence also establishes that the proposed permitted capacity of .849 MGD AADF for the Expanded Wastewater Facility is appropriate under rule 62- 600.200(62) and other pertinent provisions of chapter 62-600 and conforms to sound engineering principles applicable to the Expanded Wastewater Facility. The credible, persuasive evidence further establishes that the Project, when properly constructed, operated, and maintained, will comply with all applicable statutes and rules, including the requirement that the effluent meet the AWT standards as of January 1, 2016. The credible, persuasive evidence also establishes that the underground injection wells, as designed, conform to modern engineering principles applicable to the disposal of pollutants as proposed in the permit application; and that there is reasonable assurance that the wells, when properly constructed, maintained, and operated, will discharge effluent in compliance with all pertinent statutes and rules, including the requirement that the effluent discharged down the injection wells meet AWT standards as of January 1, 2016. DEP Review and Proposed Issuance of the Permit at Issue The wastewater treatment facility and underground injection well applications for the Project were submitted to DEP on April 15, 2014. During DEP's review of the applications for the Project, the question arose whether the 1.273 MGD peak hourly flow stated in the permit application would trigger the so-called "deep well" requirement in section 403.086(10)(e)2. that the underground injection wells be cased to a minimum depth of 2,000 feet. DEP ultimately concluded that the term "design capacity," as used in the statute, referred to an average daily flow rate14/ over a specified period of time——here, a year——for the Expanded Wastewater Facility, rather than the transient peak hourly flow for the facility. Thus, the Expanded Wastewater Facility does not have a design capacity exceeding 1 MGD, so the deep well requirement in section 403.086(10)(e)2. does not apply to the Expanded Wastewater Facility. DEP permit review staff issued one RAI, and KWRU timely provided the requested information. Upon receipt and review of KWRU's response to the RAI, DEP deemed the application for the Permit at Issue complete. DEP staff reviewed the permit applications for compliance with applicable statutory and rule requirements and standards. DEP's review does not entail re-designing or re- engineering the project or questioning the design engineer's reasonable exercise of judgment on design matters, as long as the project is accurately designed based on sound engineering principles and will operate in accordance with the applicable permitting requirements and standards. Thus, as a matter of practice, DEP relies, to a large extent, on the design engineer's certification that the system is accurately designed according to sound engineering principles——as is appropriate and authorized pursuant to the certification provisions on the application forms, rule 62-4.050(3), and chapter 471 and Florida Board of Engineering rules.15/ Gary Maier, P.E., professional engineer supervisor III and supervisor of DEP's domestic wastewater facility permit review staff, also reviewed the applications, the Intent to Issue, and the draft Permit at Issue to ensure that the Project complied with all applicable rules and standards and that KWRU had provided reasonable assurances such that the Project should be approved. Ultimately, DEP determined that KWRU provided reasonable assurances that the relevant permit applications met the applicable statutory and rule requirements and standards. Accordingly, DEP issued a Notice of Intent to issue the Permit at Issue. Establishment of Prima Facie Entitlement to Permit at Issue The relevant portions of the permit file, including the permit applications, supporting information, and Notice of Intent to Issue for the Permit at Issue, were admitted into evidence at the final hearing. With the admission of these documents into evidence, KWRU established its prima facie case demonstrating entitlement to the Permit at Issue. See § 120.569(2)(p), Fla. Stat. Challenge to the Permit at Issue Once KWRU demonstrated prima facie entitlement to the Permit at Issue, the burden shifted to Petitioners to present evidence proving their case in opposition to the Permit at Issue. See id. To prevail in this proceeding, Petitioners bear the ultimate burden of persuasion to prove their case by a preponderance of the competent substantial evidence. Petitioners have raised numerous grounds in the Second Amended Verified Petition for Formal Administrative Hearing16/ that they contend mandate denial of the Permit at Issue. Each of these grounds is addressed below. Alleged Permit Application Deficiencies Petitioners contend that the Permit at Issue should be denied due to alleged deficiencies in the applications submitted for the Project. Capacity Analysis Report Petitioners allege that, under rule 62-600.405, KWRU was required to submit a Capacity Analysis Report ("CAR") as part of its application for the Permit at Issue and that its failure to do so renders the applications incomplete, thus requiring denial of the Permit at Issue. The purpose of a CAR is to analyze capacity at an existing wastewater facility and to apprise DEP when it becomes evident that expansion of the wastewater facility may be needed. Specifically, the CAR is performed and submitted on a periodic basis, or when certain contingencies occur, to apprise DEP of the actual flows through the facility. If the actual flows are approaching the facility's permitted capacity, the CAR serves to notify DEP that expansion of the facility may be warranted. Thus, the CAR helps ensure that the permittee recognizes the need for, and properly plans for, future expansion of the facility. In support of their contention, Petitioners presented the testimony of William Lynch, a Florida-licensed P.E., who has experience in the planning and design of wastewater treatment facilities in Florida, including the Florida Keys. Lynch testified that the most recent three-month average daily flows reported to the DEP by KWRU repeatedly exceeded 50 percent of the permitted capacity of the Existing Wastewater Facility, thereby triggering the requirement in rule 62-600.40517/ that a CAR be submitted. KWRU previously submitted an initial CAR when the Existing Wastewater Facility historically exceeded 50 percent of its permitted capacity. Thereafter, KWRU submitted an updated CAR in April 2012, as part of the renewal application for the Existing Permit that KWRU filed in October 2011. The April 2012 CAR indicated that permitted flows would not be exceeded for ten years. Thus, under rule 62-600.405(5), a subsequent updated CAR would be due at five year intervals or when the applicant applied for an operation permit or renewal of an operation permit, whichever occurred first.18/ The persuasive evidence establishes that during the period between issuance of the Existing Permit in February 2012 and submittal of the applications for the Permit at Issue in 2014, the three-month average daily flows for the Existing Facility had not exceeded 50 percent of the treatment plant's capacity and the five-year interval CAR submittal interval (which would have expired in 2017) had not yet expired, so an updated CAR was neither required nor submitted. When development on Stock Island resumed in the 2012 through 2014 timeframe following an economic recession, it became apparent from actual flow data that the Existing Wastewater Facility would need to be expanded to accommodate the wastewater flow from new development, as well as to accommodate wastewater flow from existing development being required by law to connect to a central wastewater system. Accordingly, in April 2014, KWRU submitted the applications for the Permit at Issue. As part of KWRU's applications, the design and permitted capacity of the Existing Wastewater Facility were analyzed, and future wastewater flows for the facility were projected, taking into account all relevant factors, including projected development over an appropriate planning period, new connections from existing development, and the lack of seasonal variation in historic flows. Based on this information, the proposed design and permitted capacities for the Expanded Wastewater Facility were determined. This information is precisely that which would have been required in an updated CAR. Because all pertinent information necessary to determine the design and permitted capacities for the Expanded Wastewater Facility was submitted as part of the applications for the Permit at Issue, a separate CAR was not required and, indeed, would have been redundant and pointless. It should be noted that the Permit at Issue specifically requires submittal of a CAR upon renewal, which is five years from the date of issuance. Further, the Expanded Wastewater Facility is subject to chapter 62-600, including rule 62-600.405, so KWRU would be required to submit a CAR if circumstances specified in the rule were to occur.19/ Thus, Petitioners failed to demonstrate, by a preponderance of the competent substantial evidence, that a CAR was required to be submitted as part of applications for the Permit at Issue. Accordingly, the absence of a CAR as part of the applications is not a basis for denying the Permit at Issue. Deep Injection Well Requirement Petitioners contend that the design capacity for KWRU's wells exceeds 1 MGD, so KWRU was required under section 403.086(10)(e)2. to apply for approval to install deep injection wells——i.e., wells that are cased to a minimum depth of 2,000 feet. Petitioners further contend that KWRU's failure to include an application for deep injection wells in its applications thus mandates denial of the Permit at Issue. Under section 403.086(10)(e)1., injection wells serving wastewater facilities that have a design capacity of less than 1 MGD are required to be at least 90 feet deep and cased to a minimum depth of 60 feet. Under section 403.086(1)(e)2., injection wells serving wastewater facilities having a design capacity equal to or greater than 1 MGD must be cased to a minimum depth of 2,000 feet or such greater depth as may be required by DEP rule. As previously discussed, rule 62-600.200(19) defines "design capacity" as "the average daily flow projected for the design year which serves as the basis for the sizing and design of the wastewater facilities." The rule states that the design capacity is established by the permit applicant, and that the timeframe associated with the design capacity——such as annual average daily flow, maximum monthly average daily flow, or three- month average daily flow——also is specified by the applicant. Additionally, rule 62-600.400(3)(a), which is part of DEP's Design Requirements rule for domestic wastewater facilities, reiterates that the applicant establishes both the design capacity and the timeframe used to define its selected design capacity, with the caveat that the timeframe selected must reflect seasonal variations in flow, if any. As discussed above, the credible, persuasive evidence establishes that KWRU's selected design capacity and timeframe ——here, .849 MGD AADF——accurately and appropriately addresses the projected wastewater flows that will be treated by the Expanded Wastewater Facility. As Castle credibly testified, historical flows to the Existing Wastewater Facility do not indicate substantial seasonal residential flow, consistent with the workforce population residing year-round on Stock Island. Moreover, to the extent there may be some seasonal flow variation associated with projected hotel and commercial development, Castle took that into account in determining the design capacity for the Expanded Wastewater Facility. For these reasons, Castle's selection of AADF as the design capacity metric is appropriate, conforms to sound engineering principles, and complies with applicable DEP rules. Further, as previously discussed, the 1.273 MGD peak hourly flow is exactly that——the peak or maximum flow expressed on an hourly basis——that can be processed by the Expanded Wastewater Facility. It does not constitute the design capacity of the Expanded Wastewater Facility, which, by definition, is the average flow over a specified period of time. The persuasive evidence in the record shows that the proposed design capacity of the Expanded Wastewater Facility is .849 MGD AADF, and this design capacity is appropriate and based on sound engineering principles. As such, the design capacity of the facility is less than 1 MGD, so the deep well requirement in section 403.086(10)(e)2. does not apply to the Project. Thus, Petitioners failed to demonstrate, by a preponderance of the evidence, that the deep well requirement in section 403.086(10)(e)2. applies to the Project. Accordingly, they did not establish that the Permit at Issue should be denied on the basis that KWRU did not apply for approval of deep injection wells as part of the applications for the Project. Identity of Permittee The Permit at Issue is proposed to be issued to Key West Resort Utilities Corporation, which is not an existing entity registered to do business in Florida or in any other state. Petitioners contend, and KWRU and DEP do not dispute, that a permit issued to an entity that does not legally exist cannot legally authorize any activities. Accordingly, to the extent the Permit at Issue is proposed to be issued to Key West Resort Utilities Corporation, Petitioners contend that this constitutes a basis for denying the Permit at Issue. At the hearing, DEP and KWRU presented credible evidence showing that the correct permittee is KW Resort Utilities Corp., not Key West Resort Utilities Corporation as was stated on the proposed Permit at Issue. Further, the permit applications correctly identify KWRU as the applicant for the Permit at Issue. Thus, identification of Key West Resort Utilities Corporation as the permittee on the proposed Permit at Issue was a typographical error, and the evidence establishes that this error will be corrected when the Permit at Issue is issued. If this typographical error is corrected, then the Permit at Issue should not be denied on this basis. Alleged Project Design and Engineering Deficiencies Petitioners allege that KWRU failed to provide reasonable assurance, based on a preliminary design report, plans, test results, installation of pollution control equipment, or other information, that the construction, modification, or operation of the Expanded Wastewater Facility will not discharge or cause pollution in contravention of chapter 403 and applicable DEP rules. Petitioners further allege that KWRU has undersized the design capacity of the Expanded Wastewater Facility and that the appropriate design capacity is greater than 1 MGD, thus triggering the deep well requirement in section 403.086(10)(e)2. Projected Flows to Expanded Wastewater Facility In support of their position, Petitioners presented the testimony of William Lynch, a Florida-licensed P.E., who testified that the future wastewater flows to the Expanded Wastewater Facility projected by KWRU in its applications are incorrect because they do not accurately address planned development in KWRU's service area, as required by the Ten States Standards. Lynch took the position that pursuant to the Ten States Standards, the appropriate planning horizon for the Project is at least ten years, which would require KWRU to project wastewater flow to the Expanded Wastewater Facility through approximately 2025, rather than through 2020, as projected in the applications for the Project. However, the persuasive evidence shows that KWRU utilized an appropriate planning horizon in projecting future wastewater flows to the Expanded Wastewater Facility. KWRU's facility design engineer, Castle testified, persuasively, that although the graphic submitted in the application shows the projected wastewater flows only through the year 2020, the planning horizon he used actually was infinite. This is because the projected buildout of the service area20/ to maximum wastewater flow is anticipated to occur between 2018 and 2020, and after that point, wastewater flows to the facility would remain constant. Thus, it was pointless to depict projected flows out to the year 2025——particularly since the narrative in the application describing the Project makes clear that buildout of KWRU's service area is anticipated to occur by 2020. Because the wastewater flows projected for the year 2020 accurately represent the maximum flows that the Expanded Wastewater Facility can process, the projected planning horizon to the year 2020 is appropriate for the facility, complies with the Ten States Standards, and complies with DEP rules. Lynch also asserted that the projected wastewater flows to the Expanded Wastewater Facility from development identified in the application do not accurately apply the standards in DOH Table I and that this inaccuracy further contributed to underestimation of the design capacity of the Expanded Wastewater Facility. Lynch arrived at this position by applying Table I to all identified future development——both residential and nonresidential——and considering an additional development (Key West Harbor Yacht Club) not listed in the applications. He projected that the future wastewater flow from these developments would be approximately 146,110 gallons per day——approximately 46,000 gallons per day higher than the 100,000 gallons per day that Lynch claimed KWRU projected for the planned developments on Stock Island. Based on the addition of 46,000 gallons to KWRU's proposed design capacity of .849 MGD, Lynch opined that .895 MGD is the design capacity that should have been proposed for the Expanded Wastewater Facility. However, the credible, persuasive evidence establishes that, in determining the design capacity of .849 MGD for the Expanded Wastewater Facility, Castle accurately projected the wastewater flow quantities from future development on Stock Island. Castle described in detail the process he undertook to determine the projected wastewater flows from the various land uses and locations on Stock Island through projected buildout between 2018 and 2020. Specifically, he identified planned nonresidential development on Stock Island expected to begin producing wastewater flows in 2014 and applied the DOH Table I standards to determine the projected flows for each development. To determine projected wastewater flow from future residential development on Stock Island, Castle identified approximately 40 acres of scarified or under-utilized property in KWRU's service area and applied a density of 12 equivalent dwelling units ("EDU") per acre,21/ with 167 gallons per day of wastewater flow attributable to each EDU, using actual historic wastewater flow data from the Master Plan. Additionally, for each scarified or under-utilized property having water frontage, he projected one boat slip per 35 feet of frontage and applied a 75-gallon-per-day flow for each boat slip using DOH Table I recreational vehicle flows. For years 2016 through 2019, Castle projected incremental increases in wastewater flows per year22/ to account for potential development of other currently occupied properties. The aggregate of all projected flows from the identified developments, the 40 acres and boat slips, and the incremental increases per year through buildout yielded a projected wastewater flow of .74 MGD to the Expanded Wastewater Facility by years 2018 through 2020, which represents buildout flow to the facility. Castle then added a "safety factor" of 15 percent to the projected .74 MGD wastewater flow to accommodate currently unknown future redevelopment of existing occupied properties, to reach the .849 MGD design capacity. The 46,000-gallon discrepancy between Lynch's .895 MGD design capacity calculation and Castle's .849 MGD design capacity calculation is attributable to four basic differences in how they each determined design capacity. First, Lynch used more recent development agreement and development order information that more precisely identified and quantified specific land uses than the information that KWRU had available to it at the time it prepared and submitted its application. However, the evidence did not establish that the flow information on which Lynch relied and that on which Castle relied were so appreciably different as to significantly affect the projected design capacity for the Expanded Wastewater Facility. Second, Lynch applied DOH Table I to project future wastewater flows from all future planned development on Stock Island, both residential and nonresidential, whereas Castle applied DOH Table I only to determine nonresidential development future flows, and used actual historic flow data from the Master Plan to determine residential development future flows. Castle's residential flow calculation using historical actual flow data conforms to the recommendation in section 11.242(a) of the Ten States Standards that actual flow data be used, to the extent possible, to predict future flows; thus, Castle's calculation likely more precisely projects future flow attributable to residential development on Stock Island.23/ Third, Lynch took into account the Key West Harbor Yacht Club flow into the Expanded Wastewater Facility, whereas KWRU did not consider this flow in projecting future flows to the facility. This omission constituted an oversight on KWRU's part, and the flow from this development should have been included in the wastewater flow projection for the facility. However, the persuasive evidence did not show that this omission constituted a significant error in KWRU's .849 MGD AADF design capacity projection.24/ Fourth, Lynch apparently misinterpreted a statement in the application referencing "such redevelopment" as referring to the known planned developments on Stock Island, which were specifically identified by name in the application, and, thus, interpreted the reference to 100,000 gallons as being the flow KWRU projected for those known, named developments. However, the persuasive evidence established that the 100,000 gallons that KWRU assigned to "such redevelopment" in its application referred not to the known, named developments identified in the application, but instead to presently unknown future development on Stock Island, which Castle took into account by including the 15 percent "safety factor" in determining design capacity. Pursuant to the foregoing, it is determined that KWRU demonstrated, by credible, persuasive evidence, that it accurately estimated future wastewater flows from projected development on Stock Island to determine an appropriate design capacity of .849 MGD AADF for the Expanded Wastewater Facility. Design Capacity Timeframe Petitioners allege that the timeframe associated with the design capacity specified by KWRU——the annual average daily flow, or AADF——is not appropriate for the Expanded Wastewater Facility because it fails to reflect seasonal flows to the facility as required by rules 62-600.200(16) and 62-600.400(3)(a). Petitioners assert that the design capacity for the facility should instead be expressed in maximum monthly average daily flow ("MMADF") to account for seasonal flows. In support, Petitioners presented the testimony of Lynch, who opined that the KWRU service area experiences seasonal flows driven by the influx of tourists to Stock Island during tourist season. Lynch based this opinion on the wastewater flow data for the Existing Wastewater Facility for the year 2014, and his calculations showing that the three-month average daily flow ("ADF") for October through December 2014 was 11 percent higher than the AADF and that the MMADF for that period was 16 percent higher than the AADF. Lynch considered this variation substantial enough to indicate seasonality, so that MMADF is the appropriate design capacity timeframe for the Expanded Wastewater Facility. Using MMADF as the design capacity timeframe, Lynch opined that the design capacity of the Expanded Wastewater Facility should be 1.04 MGD MMADF——which would trigger the deep well requirement in section 403.086(10)(e)2. Castle chose AADF as the timeframe for the Expanded Wastewater Facility design capacity because historical flow records over a period of years do not show significant seasonal variations in flow for Stock Island. Castle testified, credibly and persuasively, that while the historical flow data shows a consistent slight increase in flows from August to December, in his view, the variation is not significant enough to constitute a seasonal flow. This is consistent with the evidence establishing that Stock Island is a "bedroom community" having a mostly year- round workforce population. Lynch formulated his opinion regarding appropriate design capacity using 2014 flow data for the entire year, which was not available at the time KWRU filed its permit applications for the Project in April 2014. Although Lynch relied on more recent data, his opinion was based only on one year of data. By contrast, Castle selected AADF as the design capacity metric based on the previous five years of flow data, which showed variations in flow ranging between two percent and 12 percent on a three-month average daily flow basis. Castle credibly testified that these variations were not significant enough to indicate seasonal flows and did not closely correlate with tourist season in the Keys. Additionally, in calculating his flow projections for the Expanded Wastewater Facility, Castle assumed 100 percent year-round occupancy for residential units, so that his projected design capacity of .849 MGD necessarily took into account potential seasonal flows. Thus, to the extent there are seasonal flows, the facility simply will receive flows below the design capacity during off-season. The undersigned finds Castle's use of long-term historical flow data more reliable than Lynch's use of only one year of data in assessing whether there is flow seasonality.25/ DEP's wastewater permitting supervisor, Gary Maier, concurred that the variations in wastewater flow do not reflect a significant seasonal variation that would require the use of a smaller averaging period than AADF. Maier also observed that none of the wastewater facilities in the Florida Keys having a design capacity greater than 100,000 gallons per day has a design capacity based on MMADF. This evidences that Castle's selection of AADF as the timeframe metric conforms to the design capacity standard used for facilities of comparable size in the Florida Keys. Based on the foregoing, it is determined that KWRU's selection of AADF as the design capacity timeframe metric for the Expanded Wastewater Facility is appropriate and complies with DEP rules. Petitioners failed to demonstrate that KWRU's selection of AADF as the design capacity timeframe metric violates any applicable laws or rules. Accordingly, Petitioners did not demonstrate that the Permit at Issue should be denied on this basis. Ability of Expanded Wastewater Facility to Reliably Meet AWT Petitioners further allege that KWRU failed to provide a complete application demonstrating that the treatment processes for the Expanded Wastewater Facility will efficiently and reliably meet effluent limitations for design year flow. As discussed above, the evidence establishes that KWRU provided all of the information required for the applications for the Permit at Issue, so DEP correctly determined that the applications were complete before commencing its substantive review of the applications. Also as discussed above, Lynch opined that the proposed design capacity was undersized for the flows he projected for the Expanded Wastewater Facility. However, the persuasive evidence shows that KWRU's proposed design capacity of .849 MGD AADF is appropriate, conforms to sound engineering principles, and meets applicable statutory and rule requirements. In order to ensure that a wastewater facility functions effectively and reliably, it is important that the facility not be substantially oversized for the amount of wastewater flowing into the facility. In an over-sized facility, inconsistent timing of wastewater flow, lack of appropriate chemical environment for waste breakdown, and inadequate food supply for the microorganisms may lead to ineffective performance of the facility. A consequence of these imbalances is that undesirable microbes may populate the facility, causing incomplete solids settlement, overflow of solids downstream to the filters, and operational problems resulting in failure of the facility to treat wastewater to AWT standards. KWRU provided reasonable assurance, based on the proposed .849 MGD AADF design capacity and the other engineering features of the Project, that the Expanded Wastewater Facility is appropriately sized and will effectively and reliably treat the wastewater to AWT standards. Thus, Petitioners failed to prove that the Permit at Issue should be denied on the basis that it is undersized and will not reliably meet AWT standards. Key West Golf Club Reuse System Issues Petitioners contend that as part of the applications for the Project, KWRU proposes to send 1 MGD of reclaimed water to the golf course. Petitioners claim that, given an irrigated area of 100.27 acres and an average irrigation rate of .73 inches per acre per day, only 300,000 gallons of reclaimed water per day is accounted for by reuse as irrigation. On that basis, Petitioners allege that KWRU has not demonstrated that the 700,000 gallon-per-day balance of reclaimed water sent to the golf course will be reused for a beneficial purpose rather than being disposed. This contention is based on a misunderstanding of the structure and function of the reuse system. The 1 MGD flow stated in the permit application is the design capacity of the reuse system, which is not being changed by the Permit at Issue. Importantly, this figure does not quantify the amount of water that is or actually will be sent to the golf course or applied as irrigation to the golf course irrigated area in a single day. Rather, it represents the flow capacity to which the reuse system is designed.26/ The applications for the Permit at Issue do not propose any changes to the quantity of reclaimed water being reused, which is governed by the irrigated acreage at the golf course and the irrigation rate. These parameters are not being changed. As previously discussed, KWRU sends reclaimed water to the golf course only on an as-needed basis, where it is stored in the ponds until needed for irrigation. If the course does not need reclaimed water sent to the ponds, KWRU does not send the water. Thus, the golf course controls the amount of reclaimed water that is sent to the storage ponds. Although the permitted capacity of the reuse system is being expanded from .499 MGD AADF to .849 MGD AADF, the actual amount of reclaimed water sent to the golf course by KWRU is not anticipated to change because, as discussed above, the amount being reused for irrigation is not being changed. Since the amount of reclaimed water being reused for irrigation is not increasing, the reuse system is not being expanded. Thus, the evidence does not show that 700,000 gallons per day of reclaimed water will be sent to the golf course for disposal, inconsistent with rule 62-610.810(2), rather than being reused for a beneficial purpose.27/ Petitioners also assert that the increased permitted capacity of the reuse system constitutes a "new or expanded reuse or land application project," so that an engineering report and reuse feasibility study were required as part of the applications for the Permit at Issue, pursuant to rule 62-610.310(1). KWRU previously provided these documents when it originally applied for authorization of the reuse system. The credible, persuasive evidence shows that increasing the permitted capacity of the reuse system does not trigger the requirement to submit another engineering report or reuse feasibility study. This is because no changes to the structural components or operation of the reuse system facilities are proposed. As Castle credibly explained, and Maier confirmed, the relevant question in determining whether an engineering report is required is whether the land application rate and/or the irrigated acreage is being changed, which would increase the amount of reclaimed water being reused and, thus, would require expansion of the reuse system. As discussed, neither the irrigated area nor the irrigation application rate is proposed to change under the Project. Thus, neither an engineering report nor a reuse feasibility study are required as part of the applications for the Permit at Issue. Therefore, Petitioners failed to demonstrate that the Permit at Issue should be denied on the basis that KWRU did not submit a reuse feasibility or engineering report as part of its applications for the Permit at Issue. Alleged Surface Water Quality Violations by Injection Wells Petitioners allege that disposing of the effluent from the Expanded Wastewater Facility through the injection wells will cause or contribute to violations of surface water quality standards codified in chapter 62-302. Petitioners further allege that, as a consequence, the discharge will violate antidegradation requirements in rules 62- 4.242, 62-302.300, and 62-302.700(1), and that the wells do not comply with the underground injection control rule requirement in rule 62-528.630(7), specific to Monroe County, that the wells not cause or contribute to surface water quality violations. Regulatory Status of Surface Waters in Stock Island Vicinity A significant portion of the surface waters in the Florida Keys, including those surrounding Stock Island and Key West, are classified as Class III surface waters pursuant to rule 62-302.400. Water quality criteria adopted by rule for Class III surface waters are established to protect fish consumption, recreation, and the propagation of a healthy, well- balanced population of fish and wildlife. As previously noted, certain portions of the Florida Keys, including the surface waters surrounding Stock Island and Key West, are designated an OFW. Fla. Admin. Code R. 62- 302.700(9)(i)13. No degradation of surface water quality, other than that allowed under rules 62-4.242(2) and (3), is permitted in an OFW. See Fla. Admin. Code R. 62-302.700(1). The narrative nutrient criterion codified at rule 62- 302.530(47)(a) states: "[t]he discharge of nutrients shall be limited as needed to prevent violations of other standards contained in this chapter. Man-induced nutrient enrichment (total nitrogen or total phosphorus) shall be considered degradation in relation to the provisions of Rules 62-302.300, 62-302.700, and 62-4.242, F.A.C." The narrative nutrient criterion codified at rule 62-302.530(47)(b) states: "[i]n no case shall nutrient concentrations of a body of water be altered so as to cause an imbalance in natural populations of aquatic flora or fauna." These criteria apply in Class III surface waters, including the surface waters in and around the Florida Keys. See Fla. Admin. Code R. 62-302.531(1). Rule 62-302.531(2) requires DEP to numerically interpret the narrative nutrient criterion for nutrients (nitrogen and phosphorus) and for nutrient response (chlorophyll- a). Where a site-specific numeric interpretation of rule 62- 302.530(47)(b) has been established, that numeric interpretation constitutes the primary standard applicable to that site. Fla. Admin. Code R. 62-302.531(2)(a). A range of natural factors affect nutrient loading for a given waterbody. Therefore, site- specific numeric interpretations of the narrative nutrient criteria generally are deemed more reliable than broadly applicable, non-site specific criteria. Estuary-specific numeric interpretations of the narrative nutrient criterion in rule 62-302.530(47)(b), consisting of nutrient values for nitrogen and phosphorus and a nutrient response value for chlorophyll-a have been adopted for many areas in the state of Florida, including the Florida Keys. These numeric interpretations——commonly referred to as "numeric nutrient criteria," or "NNCs"——are open water, area-wide averages. See Fla. Admin. Code R. 62-302.532(1). For the Florida Keys, seven Florida Keys Marine Nutrient Regions ("FKMNRs") have been identified and geographically delineated on a series of maps adopted by rule. For each of these FKMNRs, NNCs have been adopted for nitrogen, phosphorus, and chlorophyll-a. Fla. Admin. Code R. 62- 302.532(1)(g). The NNCs for the Lower Keys Region and the Back Bay Region are germane to this proceeding. For the Bay Back Region, the NNCs are .009 mg/L for phosphorus, .25 mg/L for nitrogen, and .3 µg/L for chlorophyll-a. For the Lower Keys Region, the NNCs are .008 mg/L for phosphorus, 0.21 mg/L for nitrogen, and 0.3 µg/L for chlorophyll-a. These NNCs are expressed as annual geometric means that are not to be exceeded more than once in a three-year period.28/ The area of water extending from the shoreline out to 500 meters offshore in the Florida Keys is referred to as the "Halo Zone." DEP has adopted by rule a map delineating the Halo Zone. The NNCs applicable to surface waters in each of the FKMNRs currently do not apply to the surface waters in the Halo Zone. Thus, only the narrative nutrient criteria codified at rules 62-302.530(47)(a) and (b) apply to surface waters in the Halo Zone at this time.29/ Additionally, pursuant to chapter 62-303, the Impaired Waters Rule, DEP has identified and delineated spatial assessment areas in waterbodies based on homogeneity for multiple water quality parameters.30/ These assessment areas, called "Waterbody IDs" or "WBIDs," are delineated for purposes of assessing, through water quality sampling, whether the surface waters within the WBID are impaired——that is, whether they fail to meet one or more of the applicable water quality standards due to pollutants.31/ DEP has delineated several WBIDs, identified by number, in the Halo Zone surrounding Key West and Stock Island. The Halo Zone surrounding Stock Island comprises WBID 6014B, and the Halo Zone surrounding Key West consists of WBIDs 6014A and 8073A through 8073H.32/ The Back Bay Region, which is located north of Stock Island and outside of the Halo Zone, is designated as WBID 8074. The Lower Keys Region consists of WBID 8073, which is located northwest of Stock Island and surrounding Key West outside of the Halo Zone, and WBID 8079, which is located south of Stock Island outside of the Halo Zone. Water quality monitoring, consisting of sampling for a range of parameters, is conducted at monitoring stations within each of these WBIDs. At least one monitoring station is located within each WBID. This water quality sampling is conducted according to DEP's applicable standard operating procedures. The monitoring stations have collected nutrient and nutrient response data spanning a period of years. The data collected in 1995 through 2013 are pertinent to this proceeding.33/ The Keys RAP, which was prepared in 2008 and updated in 2011, prescribes specific management activities to be implemented to restore surface water quality in the Florida Keys, including eliminating cesspits and onsite septic tank systems and connecting wastewater generators to centralized wastewater systems that treat the wastewater to AWT standards. As authorized under rule 62-303.600, DEP determined that the Keys RAP provides reasonable assurance that the restoration goals for the surface waters in the Florida Keys will be achieved by ensuring that all management activities specified in the Keys RAP would be implemented for specified waterbodies by 2015. Accordingly, in February 2012, DEP approved and adopted the Keys RAP by Secretarial Order. Current and historic water quality data show that all WBIDs in the Keys, including those in the Lower Keys Region, Back Bay Region, and Halo Zone for the surface waters surrounding Key West and Stock Island, are not impaired for nutrients——that is, that the NNCs and narrative nutrient criteria, as applicable, are being met. Pursuant to sections 403.061 and 403.067, Florida Statutes, and rule 62-303.600, DEP has classified the Florida Keys WBIDs as Category 2 under the waterbody use attainment classification scheme34/ for nutrients and nutrient response. The classification of the Keys WBIDs in this category means that sufficient water quality data are available to determine that at least one designated use is attained. Thus, as authorized by section 403.067 and rule 62-303.600(2), DEP has placed the Keys WBIDs on the "Delist List."35/ This "de-listing" action recognizes that the Florida Keys WBIDs, including those in the Halo Zone, are not impaired for nutrients and chlorophyll-a. Subsurface Geology in Vicinity of Stock Island The parties agree that, as a general proposition, the ground water and surface waters are connected to each other in the Florida Keys. However, no evidence was presented showing a specific location or locations where ground water connects to surface waters. Although it generally is undisputed that, at some point, ground water connects to surface waters, the parties disagree regarding whether, where, and how long it may take for the injected effluent to reach surface waters. Petitioners contend that due to the local geology, the injected effluent from the Existing Wastewater Facility rapidly reaches surface waters in the vicinity of Stock Island and that the increased discharge through the new injection wells will exacerbate and cause or contribute to surface water quality violations in the immediate vicinity of Stock Island and offshore. In support of this position, Petitioners presented the testimony of Scott Zednek, a Florida-licensed P.G. Zednek opined that due to the absence of subsurface sediments that would prevent upward flow to surface waters, the buoyant freshwater effluent injected down the wells will rapidly vertically migrate through the highly transmissive Key Largo Limestone and Miami Limestone to reach surface waters. To develop his opinion, Zednek reviewed a Florida Geological Survey boring log ("FGS Log") approximately one-third mile from the Existing Wastewater Treatment Facility and a Universal Engineering Services geotechnical study boring log ("UES Log") performed on the KWRU site. The FGS Log was prepared specifically to analyze the subsurface geology. The UES Log was performed as part of a geotechnical study to analyze subsurface conditions onsite specifically for the purpose of determining the load-bearing capability of the KWRU site to support a concrete water tank. As such, the FGS Log provides a more precise view of the subsurface geology in the vicinity of the KWRU site.36/ Based on the UES Log, Zednek opined that there are no confining layers underlying the KWRU site. The UES Log for the site shows N-values, generated using an ASTM-designated process for determining the resistivity or strength of the subsurface, of between two and 43 for the first 60 feet of sediment below the surface. According to Zednek, an N-value of less than 50 indicates lack of a confining layer. Further, his review of the UES Log did not show the presence of Q-layers, which may function as semi-confining layers, or aquitards, that would substantially restrict the movement of fluid, including the injected effluent.37/ Based on the UES Log, Zednek opined that the limestone underlying the site is fractured, creating vertical pathways for the injected effluent to migrate upward to the surface. Zednek testified that the Key Largo Limestone, into which the effluent is injected, is very porous and highly transmissive, facilitating rapid migration once the effluent is injected. Based on his review of the FGS Log, Zednek testified that a Q-layer first appears at approximately 62 feet below the ground surface——below the depth of the injection wells' casing—— so it would not act as a confining layer for the injected effluent. Zednek further observed that this Q-layer is only 1.5 centimeters thick. In his experience, this thickness is not sufficient to create a confining or semi-confining layer. Zednek thus opined that the subsurface geology at the KWRU site will enable and facilitate vertical migration of the injected effluent to surface waters. Zednek also noted the proximity of the Safe Harbor channel cut. He opined that the injected effluent likely would horizontally migrate through the highly transmissive Key Largo Limestone,38/ then vertically migrate to surface waters through the "path of least resistance" at the Safe Harbor channel cut. As further support for his opinion, Zednek cited an interim report summarizing results of a subsurface dye tracer study performed for the Florida Keys Aqueduct Authority regional wastewater treatment facility. The study's purpose was to determine whether the subsurface geology at the Cudjoe Key location was sufficiently confining to prevent vertical migration of the injected effluent from shallow injection wells proposed at that facility. According to Zednek, the interim report showed that the subsurface at the injection site was not sufficiently confining to prevent the injected effluent from rapidly vertically migrating to surface waters. Petitioners also presented the testimony of John Paul, Ph.D., in support of their contention that the injected effluent from the Expanded Wastewater Facility would rapidly rise through the subsurface limestone up into surface waters. Dr. Paul testified regarding viral tracer studies he had conducted at Long Key, approximately 65 miles east-northeast of Stock Island, and at the Saddlebunch Keys, located approximately 20 miles east- northeast of Stock Island. In conducting these studies, Paul injected bacteriophage viruses into Class V wells and tracked their movement into surface waters. In the Long Key study, the injected viruses moved through the subsurface limestone to the south-southeast and appeared in surface waters in deep canals on the ocean side of U.S. 1 approximately 53 hours after injection. In the Saddlebunch Keys study, the viruses also appeared in surface waters some distance south-southeast of the location at which they were injected.39/ Paul acknowledged that when the viruses appeared in surface waters, they were detected at a concentration of one trillionth (.0000000000001 or 1 x 10-12) less than the concentration in which they had been injected, indicating significant dilution by ground water and/or surface waters. He also acknowledged that canals dredged to depths shallower than the injected depth may not facilitate rapid migration of the injected effluent to surface waters. In rebuttal, KWRU presented the testimony of Michael Alfieri, a Florida-licensed P.G. who specializes in hydrogeology. Alfieri examined the FGS Log and UES Log, and also reviewed the detailed lithology logs and photographs for the FGS Log. Based on his review of this information, Alfieri opined that the FGS Log indicates the presence of semi-confining layers that function as aquitards in the first 60 feet of subsurface sediment. Alfieri noted that the existence of an aquitard depends on the nature of the geologic materials present at that location, so that N-values do not perfectly correlate with the presence or absence of confining layers. Thus, a carbonate silt or clay having an N-value of only two may better function as an aquitard than a porous, transmissive limestone having an N-value of 50, and silts or clays having a thickness as little as one centimeter may function as an aquitard to significantly impede fluid flow.40/ Based on his review of the FGS Log and the detailed lithology log descriptions and photographs for the FGS Log, Alfieri observed four laminated calcrete zones, six Q-zones, and chalky limestone within the first 60 feet——all of which would function as aquitards to impede the vertical movement of the effluent.41/ Thus, according to Alfieri, the effluent is anticipated to migrate laterally from the injection wells below these confining layers before migrating through a vertical pathway to reach surface waters at an unknown location. To predict the likely migration pathway for the effluent, Alfieri conducted hydrological modeling using a simplistic SEAWAT computer model. He used horizontal and vertical transmissivity values for the subsurface strata derived from geological studies previously conducted in the Florida Keys. Although these studies indicate greater horizontal than vertical transmissivity, Alfieri assumed equal vertical and horizontal transmissivity for modeling purposes——necessarily yielding more conservative results than would be anticipated to occur in real life. Accordingly, the modeling results showed more rapid vertical migration than would be anticipated in real life when the Q-zones and calcrete layers depicted in the FGS Log are considered. Even with these conservative assumptions, the modeling results showed the injected effluent migrating horizontally at least a mile offshore42/ before migrating upward to surface waters. The persuasive evidence shows that the injected effluent will be confined to the subsurface and will travel laterally a substantial distance before rising to surface waters at some unknown location or locations offshore. Thus, the credible, persuasive evidence does not support the conclusion that the effluent will rapidly rise to the surface waters in the nearshore area in the vicinity of the KWRU site.43/ Narrative Nutrient Criteria Petitioners allege that the effluent injected down the wells into the ground water will reach surface waters, causing or contributing to a violation of the narrative nutrient criteria for surface waters codified in rules 62-302.530(47)(a) and (b).44/ In support, Petitioners presented the testimony of James Fourqurean, Ph.D., who has extensive experience in research on Florida Keys aquatic ecosystems in their healthy and imbalanced states. Dr. Fourqurean described these ecosystems in their healthy state and in their nutrient-enriched state. Florida Keys nearshore ecosystems normally are oligotrophic, which means they are nutrient-limited. Thus, they do not normally exhibit high chlorophyll-a levels and microalgae counts. When nutrient levels in the Florida Keys ecosystems increase——whether by increasing the concentration of nutrients in discharges or by increasing the volume of water containing nutrients——primary production, i.e., plant growth, increases. Seagrass communities are phosphorus-limited, so that when these communities are exposed to phosphorus-enriched water, the phosphorus is rapidly absorbed from the water column and is stored in the benthos.45/ This phosphorus capture initially leads to increased seagrass abundance, but as phosphorus enrichment continues, the community species composition rapidly shifts to favoring seaweed and microscopic algae, ultimately damaging or destroying the seagrass community. Coral reef communities similarly are nitrogen-limited. Thus, when coral reef communities are exposed to nitrogen- enriched water, they shift to algae-dominated communities——again, damaging or destroying the coral reef communities. Based on historical aerial photographs of the area surrounding Safe Harbor and his experience studying seagrasses in the Florida Keys, Fourqurean concluded that the natural seagrass populations in the entire Florida Keys National Marine Sanctuary area, which includes the Stock Island area, are experiencing ecological imbalance. On the basis of the water quality sampling he conducted in and around Safe Harbor, Fourqurean opined that the imbalance is the result of man-induced nutrient enrichment. However, he did not engage in field studies in and around Safe Harbor, so could not cite specific examples where seagrasses had been replaced by algal-dominated communities in that area. Fourqurean noted that human waste contains high concentrations of phosphorus and nitrogen. In his view, because the effluent from the Existing Wastewater Facility contains phosphorous, it necessarily constitutes a source of phosphorous in the surface waters in Safe Harbor, even though it is injected into ground water. However, he acknowledged the existence of numerous other sources of nitrogen and phosphorus in the Safe Harbor vicinity, including septic tanks, boat cleaning operations and pump outs, and storm water runoff. He further acknowledged that he did not know where or when effluent from the Existing Wastewater Facility (and, by extension, the Expanded Wastewater Facility) may reach surface waters. Fourqurean acknowledged that the Permit at Issue would authorize the injection of effluent treated to AWT standards into ground water, rather than directly to surface waters, and he further acknowledged that the total phosphorus and nitrogen loading from the Expanded Wastewater Facility would substantially decrease as a result of conversion to AWT, even though the volume of effluent discharged down the wells may as much as double. He remained concerned that the Expanded Wastewater Facility may contribute phosphorus——even in very small quantities——to surface waters, causing imbalance to seagrass communities. He also opined that when saline ground water and the fresher effluent mix, the resulting brackish solution would dissolve the calcium carbonate comprising the subsurface limestone, releasing stored phosphorus that would eventually reach surface waters and negatively affect nearshore seagrass communities, However, he acknowledged that depending on subsurface physical conditions and flow paths of the effluent, phosphorous, nitrogen, or both, may be completely removed prior to the effluent reaching surface waters. He further acknowledged that seagrass community health in the Florida Keys National Marine Sanctuary has improved in the last two years and that water quality also has improved, reversing a ten-year decline. This is consistent with replacement of onsite septic tanks by central wastewater treatment systems in the Florida Keys. On rebuttal, KWRU presented the testimony of William Precht, who has extensive experience with Florida Keys geology and aquatic communities. Precht confirmed the existence of numerous sources of significant nutrient enrichment in the Safe Harbor vicinity other than the Existing Wastewater Facility, and noted that these sources must be taken into account when analyzing nutrient enrichment in Safe Harbor. He testified that raw wastewater is particularly deleterious to benthic communities. Thus, connecting wastewater generators that currently use septic tanks to central wastewater treatment systems can significantly improve water quality. Precht observed that Fourqurean's single-day sampling in the Safe Harbor area provided information regarding variability in nutrient concentrations, but characterized Fourqurean's conclusion that the Existing Wastewater Facility was the source of the nutrients as "unscientific" because it was based on supposition rather than on testing. He opined that the limited data set gathered over a one-day period could not reliably identify the source of nutrient enrichment in Safe Harbor. Precht testified that flushing capability is a key influence on nutrient concentration in surface waters. The further from a natural marine environment that water quality testing is performed, the more likely water quality will be poor due to nutrient enrichment from land-based sources. Given the configuration of Safe Harbor, water quality would be poorest in the interior dead-end canals and would steadily improve as one moved into more open water and flushing increased, with the highest water quality in open waters outside the canal system. Precht opined that the presence of noxious benthic plant life in the Safe Harbor vicinity may be attributable the destruction of seagrass communities in the area by historical dredging, rather than due to nutrient enrichment. Based on the reduction in total nitrogen and total phosphorus loading as a result of implementing AWT, Precht opined that the proposed discharge will not negatively affect the biological communities in the Safe Harbor vicinity. He further opined that due to the rapid uptake of phosphorus in the marine environment and due to denitrification that occurs in ground water and in marine surface waters, there is little chance that any nutrient loading that may result from the injected effluent would cause damage to the coral reef environment. Also on rebuttal, Alfieri persuasively testified that although phosphate release does occur when freshwater is injected into limestone that formed in a saline environment, this process gradually occurs over "geologic time"——that is, over millions of years. Therefore, he did not anticipate a significant release of phosphate from the subsurface limestone as a result of the effluent discharge. Also, limestone rapidly absorbs phosphorous, so phosphorus in the injected effluent would be absorbed quickly by the subsurface limestone.46/ Further, in any event, the effluent will be diluted by at least seven orders of magnitude——that is, one hundred millionth (.00000001)——of the injected concentration by the ground water, and/or by surface waters (assuming the effluent eventually reaches surface waters). As discussed above, the Keys RAP was prepared in 2008 and updated in 2011. The Keys RAP prescribes specific management activities to be implemented to restore surface water quality in the Florida Keys, including eliminating cesspits and onsite septic tank systems and connecting wastewater generators to centralized wastewater systems that treat the wastewater to AWT standards. Pursuant to the Impaired Waters Rule and DEP's adoption of the Keys RAP, activities that are consistent with the Keys RAP are considered to provide reasonable assurance that the narrative nutrient criterion in rule 62-302.530(47)(b) will be met. As discussed above, the Project will expand a centralized wastewater treatment plant that will accept, and treat to AWT standards, wastewater generated by development on Stock Island——including development that currently relies on onsite septic tanks for wastewater disposal. The Project is consistent with the Keys RAP, so there is reasonable assurance that the Project will meet the narrative nutrient criterion in rule 62-302.530(47)(b). The persuasive evidence shows that the Project will not cause or contribute to alterations of nutrient concentrations in water bodies so as to cause an imbalance in natural populations of aquatic flora or fauna. Thus, Petitioners failed to show that the Project will cause or contribute to violation of the narrative nutrient criterion in rule 62-302.530(47)(b). Further, for the reasons discussed below, it also is determined that the Project will not violate the narrative nutrient criterion codified at rule 62-302.530(47)(a). Numeric Nutrient Criteria Petitioners also allege that the effluent will cause or contribute to violation of the estuary-specific numeric interpretations of the narrative nutrient criteria for the Back Bay nutrient region, codified at rule 62-302.532(1)(g)1., and the Lower Keys nutrient region, codified at rule 62-302.532(1)(g)3. In support, Petitioners cite the results of surface water sampling performed by Fourqurean in the Safe Harbor area showing high levels of nitrogen, phosphorus, and chlorophyll-a. Petitioners contend that these high nutrient levels evidence that the existing injection wells already are causing or contributing to surface water quality violations in the waters surrounding Stock Island, and that the increased effluent discharge from the proposed new injection wells will exacerbate this situation, further causing or contributing to violations of surface water quality standards. In preparing his opinion regarding the effect of the proposed injection wells on surface water quality, Fourqurean sampled surface water quality on one day at nine stations located in the vicinity of Stock Island, ranging from shallow waters inside the Safe Harbor basin to deeper waters offshore. Samples were collected at the surface and at a depth of one meter below the surface following the standard operating procedures for water quality sampling established by the Florida Keys Water Quality Protection Program. Fourqurean testified that the samples collected at the stations inside the Safe Harbor basin and near the shore of Stock Island showed very high levels of chlorophyll-a, evidencing that these areas are dominated by microalgae and, thus, are eutrophic. Additionally, the samples collected inside the Safe Harbor basin exhibited very high phosphorus concentrations—— almost three times greater than the estuary-specific numeric nutrient criterion for phosphorus. Phosphorus concentrations correspondingly decreased as samples were collected outside of the basin and offshore. Nitrogen concentrations followed a similar pattern in the sampling that Fourqurean conducted inside and outside of the Safe Harbor basin. According to Fourqurean, the high nutrient concentrations in the samples taken in Safe Harbor, when compared to the lower concentrations in samples taken outside of Safe Harbor, evidence the existence of a large source of phosphorous and nitrogen in Safe Harbor——in his view, the Existing Wastewater Facility. However, Fourqurean acknowledged that there are many potential nutrient enrichment sources on Stock Island, including fishing operations, boat sewage pump-outs, and direct discharges of storm water to surface waters. He further acknowledged that the specific source of phosphorus and nitrogen in the surface waters surrounding Stock Island cannot be identified. He did not opine as to the relative amounts of nutrients in surface waters that he believes are being contributed by the Existing Wastewater Facility or that will be contributed by the Expanded Wastewater Facility, as compared to other nutrient sources in the Safe Harbor area. He also acknowledged that a scientifically-valid water quality study would require more than a single day of sampling.47/ Kenneth Weaver, environmental administrator for DEP's Standards Development Section,48/ credibly and persuasively testified, and the water quality data for nutrients and chlorophyll-a collected in the WBIDs surrounding Key West and Stock Island show, that the surface waters in these WBIDs meet the applicable NNCs.49/ Historical water quality data also show that since 2008, the surface waters in these WBIDs continuously have met the baseline concentrations on which the NNCs were established and adopted. Even with the increased volume of wastewater treated by the Expanded Wastewater Facility, implementation of the AWT standard by the facility's wastewater treatment trains will substantially reduce the amount of total nitrogen and total phosphorus discharged into ground water through the injection wells. Specifically, for total nitrogen, the concentration will be reduced from 13.92 mg/L to 2.25 mg/L, and the total amount of nitrogen loading will be reduced from 58 to 15.9 pounds per day, representing a total net reduction of 72.4 percent in the discharge of total nitrogen. For total phosphorus, the concentration will be reduced from 3.47 mg/L to .75 mg/L, and the total amount of phosphorus loading will be reduced from 14.4 to 5.3 pounds per day, representing a total net reduction of 63.3 percent in the discharge of total phosphorus.50/ Weaver addressed the effects of these projected nutrient discharge concentrations on the surface waters in WBIDs 8074 and 8079, which comprise the portions of the Lower Keys Region and Back Bay Region closest to the KWRU site. He opined that, because these regions are currently meeting the applicable NNCs for nitrogen and phosphorus, and because KWRU's implementation of AWT will result in substantial reduction of total nitrogen and phosphorus loading, the NNCs will continue to be met in these regions——even in a "worst-case" scenario that assumes all of the treated effluent from the Expanded Wastewater Facility is disposed of through the injection wells and reaches the surface. The persuasive evidence shows that the Project will not cause or contribute to violations of the applicable numeric nutrient criteria. Thus, Petitioners failed to show that the Project will cause or contribute to violation of the applicable numeric nutrient criteria in rule 62-302.532(1)(g)1. and 3. Surface Water "Free-From" Standards Petitioners allege that the effluent contains iron and copper above detection limits, as well as personal care products and pharmaceuticals, and that these constituents violate rules 62-302.500(1)(a)5. and 62-302.530(61). Rule 62- 302.500(1)(a)5. requires all surface waters of the state to be free from domestic, industrial, agricultural, or other man- induced non-thermal components of discharges which, alone or in combination with other components of discharges (whether thermal or non-thermal), are present in concentrations which are carcinogenic, mutagenic, or teratogenic to human beings or to significant, locally occurring wildlife or aquatic species, unless specific standards for such components are established by rule. Rule 62-302.530(61) effectively requires surface waters to be free from substances in concentrations which injure, are chronically toxic to, or produce adverse physiological or behavioral response in humans, animals, or plants. These rules collectively comprise the "free-from" standards for surface waters. Petitioners presented no evidence to substantiate the allegation that the effluent from the Expanded Wastewater Facility will contain pharmaceuticals or personal care products. However, even assuming these constituents were present in the effluent, Petitioners did not present evidence showing that they are carcinogenic; mutagenic; or teratogenic to human beings or to significant, locally occurring wildlife or aquatic species; or that they are injurious or chronically toxic to, or produce adverse physiological or behavioral response, in humans, animals, or plants. Petitioners did not present evidence showing that the effluent contains copper and iron in quantities that violate any applicable surface water quality standards, including the surface water "free-from" standards. Paul testified, based on sampling he conducted at domestic wastewater outfalls discharging directly to surface waters, that effluent treated to AWT standards often contains pathogenic bacteria and viruses that constitute threats to human health. On this basis, he opined that even though the effluent from the Expanded Wastewater Facility is treated to AWT, it may contain pathogenic constituents that are harmful to human health. However, as previously discussed, the evidence shows that the effluent discharged through KWRU's injection wells will be substantially diluted by groundwater, and also by surface waters to the extent it reaches surface waters at some unknown location. Accordingly, the results of Paul's pathogen studies cannot be extrapolated to conclude that KWRU's effluent also will contain pathogenic bacteria and viruses in such amounts as to constitute a threat to human health. Petitioners failed to show that the effluent disposed of in the injection wells will cause or contribute to violations of the surface water quality standards in rules 62- 302.500(1)(a)5. and 62-302.530(61). Dilution to Meet Surface Water Quality Standards Petitioners allege that KWRU is relying on dilution of the effluent in order to meet surface water quality standards without having been permitted for a mixing zone, in violation of rule 62-302.500(1)(c).51/ This contention lacks merit. As discussed in detail above, the credible, persuasive evidence establishes that the effluent discharged through the injection wells will not violate water quality standards for and parameters, including for nutrients, and will not cause or contribute to the violation of water quality standards. The credible, persuasive evidence establishes that once injected, the effluent will horizontally migrate a considerable distance before it may migrate vertically to reach surface waters. The parties generally agree that ground water and surface waters are "connected" in the Florida Keys. To that point, although it appears likely that at some point the effluent will reach surface water, the evidence does not establish that is an absolute certainty. Nonetheless, even assuming the effluent would reach surface waters at some unknown location and time, the persuasive evidence shows that it would be so substantially diluted by the ground water that it would neither cause nor contribute to violations of surface water quality standards. Further, the persuasive evidence, consisting of Weaver's "worst case" analysis of nutrient loading from the effluent discharge, which assumed no dilution by ground water, establishes that even if the effluent——which will be treated to AWT standards——were discharged directly into surface waters, it would meet the applicable nutrient criteria. Finally, Petitioners' claim assumes that the effluent will be discharged into surface waters. However, as discussed above and in greater detail below, to the extent the effluent ultimately may be discharged to surface waters, such discharge would be indirect, so would not be subject to statutory and rule provisions requiring establishment of a mixing zone. For these reasons, Petitioners failed to prove that KWRU violated any applicable law or rule by not requesting and obtaining a mixing zone for the discharge of the effluent through the injection wells. Class V Injection Wells in Monroe County Petitioners also allege that issuance of the Permit at Issue violates rule 62-528.630(7), which requires all Class V Group 3 domestic wastewater injection wells in Monroe County to provide reasonable assurance that operation of the well will not cause or contribute to a violation of surface waters standards as defined in chapter 62-302. As discussed above, the credible, persuasive evidence establishes that the operation of the wells as authorized under the Permit at Issue will not cause or contribute to violations of surface water quality standards codified in chapter 62-302. Accordingly, Petitioners failed to prove that the Permit at Issue should be denied on the basis that it violates rule 62-528.630(7). Antidegradation Petitioners contend that the Permit at Issue must be denied because KWRU failed to provide reasonable assurance that the injection of effluent will not violate the antidegradation requirements applicable to surface waters codified at rules 62- 4.242, 62-302.300, 62-302.530(47)(a), and 62-302.700(1). This contention lacks merit. As more fully discussed below, the antidegradation requirements in these rules apply only to a direct discharge to surface waters, which is not present in this case. Here, the evidence clearly establishes that the injection wells do not directly discharge effluent into surface waters. It is undisputed that the effluent will be injected from the wells into Class III ground water, where it will migrate through the subsurface strata. Although it is likely that, due to a "connection" between ground water and surface waters, the effluent ultimately will reach surface waters at some unknown location or locations at some unknown time, this constitutes an indirect discharge, which is specifically excluded from the term "discharge of a pollutant." Fla. Admin. Code R. 62-620.200(13). However, even if the antidegradation rules did apply to the discharge of the effluent through the injection wells, Petitioners failed to prove that the discharge would degrade surface waters. As discussed above, the credible, persuasive evidence establishes that the surface waters in the Florida Keys, including those in and around Stock Island and Key West, currently meet the narrative and/or nutrient criteria, as applicable, and that effluent discharged through the injection wells will be treated to AWT standards, substantially reducing the facility's total nutrient loading below current levels. Thus, the credible, persuasive evidence established that, even in a "worst-case" scenario, which assumes no dilution of the effluent by ground or surface waters, the effluent still would not cause or contribute to a violation of the narrative or numeric nutrient criteria. As discussed above, the credible, persuasive evidence showed that, in fact, the effluent will be very substantially diluted by the ground water into which it is injected, and will be further diluted if and when it ultimately reaches surface waters. For these reasons, Petitioners failed to prove that KWRU did not provide reasonable assurance that the disposal of the effluent through the injection wells would not degrade surface waters, in violation of rules 62-4.242, 62-302.300, 62- 302.530(47)(a), and 62-302.700(1). Alleged Violation of Ground Water Standards Petitioners allege that KWRU did not provide reasonable assurance that the injection wells would not violate applicable ground water standards. Petitioners further allege that there is an underground drinking water source under Stock Island. In that case, more stringent ground water quality and injection well rule standards would apply to operation of the injection wells. Petitioners did not present any credible, persuasive evidence to support these allegations. The persuasive evidence establishes that although there is a fresh water lens under Stock Island, it is not classified as an underground source of drinking water52/ due to its substantial variability in horizontal and vertical extent, which renders the salinity levels highly variable. Thus, the ground water at Stock Island is classified as Class G-III ground water which is non-potable ground water having a total dissolved solids content of 10,000 mg/L or greater, or having a total dissolved solids content of 3,000 to 10,000 mg/L and having been determined to have no reasonable potential as a future source of drinking water or designated by rule as an exempted aquifer. Only the minimum criteria for ground water, known as the "free-from" standards, apply to Class G-III ground water. Fla. Admin. Code R. 62-520.430(1). These criteria require that at all times and in all places, ground water be free from discharge components in concentrations that are carcinogenic, teratogenic, mutagenic, or toxic to humans; acutely toxic within surface waters affected by ground water; pose a serious danger to the public health, safety, or welfare; create or constitute a nuisance; or impair the reasonable and beneficial use of adjacent waters. Fla. Admin. Code R. 62-520.400. There is no evidentiary basis on which to infer that the effluent from Expanded Wastewater Facility that is disposed through the injection wells will violate the free-from standards KWRU's many years of effluent monitoring at the Existing Wastewater Facility show that the effluent does not violate these standards. Further, David Rhodes, a Florida-licensed P.G. employed by DEP, credibly testified that a violation of the free- from standards necessarily would entail the presence of toxic materials in KWRU's effluent and that there would be immediate and dramatic effects on the flora and fauna at the golf course, where reclaimed water is reused for irrigation. Since such effects never have occurred, it is reasonable to infer that the effluent from the Expanded Wastewater Facility will not violate the free-from standards.53/ Additionally, as previously addressed, the credible, persuasive evidence demonstrates that no surface water quality violations will result from installation and operation of the injection wells as part of the Expanded Wastewater Facility. Accordingly, the reasonable and beneficial use of adjacent waters will not be impaired due as a result of the injection wells. Petitioners also claim that due to inadequate treatment by the Expanded Wastewater Facility, the effluent disposed in the injection wells will contain unacceptably high levels of bacteria and viruses. The persuasive evidence establishes that KWRU provides high-level disinfection prior to injecting the effluent or sending the reclaimed water for reuse at the golf course. Historical monitoring data shows that KWRU's effluent complies with applicable microbial standards, and unrebutted evidence consisting of quality-related beach closure data for the Florida Keys, gathered as part of the Department of Health's Healthy Beaches monitoring program, indicates that no beach closings in the Florida Keys ever have been attributed to KWRU's Existing Wastewater Facility. Petitioners did not prove that KWRU failed to provide reasonable assurance that operation of the injection wells authorized as part of the Project will not result in violations of applicable ground water standards. To the contrary, KWRU provided reasonable assurance that the effluent from the Expanded Wastewater Facility disposed in the injection wells authorized as part of the Project will not violate any applicable ground water standards. Alleged Water Quality Violations Due to Reuse System Petitioners allege that KWRU did not provide reasonable assurance that the storage of up to 1 MGD of reclaimed water in the reuse system storage ponds on the Key West Golf Club golf course will not cause or contribute to a violation of surface water quality standards and ground water standards. Specifically, Petitioners posit that, because the ponds are unlined, reclaimed water from the Expanded Wastewater Facility will leach from the ponds into the ground water and reach surface waters, violating surface water quality standards and ground water standards and negatively impacting human health through high levels of microbial pathogens, pharmaceuticals, and personal care products. Petitioners further allege that discharge of reclaimed water from the ponds into the ground water could mobilize constituents of concern from the Key West Landfill and a closed waste-to-energy facility, both of which are near the golf course, ultimately resulting in surface water quality standards and ground water violations. In support of these contentions, Petitioners presented the testimony of Scott Zednek, who testified that the reclaimed water, which is fresher than the surrounding ground water, may leach from the ponds into the ground water, and thereafter potentially may reach surface waters. According to Zednek, this leaching could occur because the ponds are unlined. Additionally, Zednek opined that, because there is a closed landfill near the golf course, the reclaimed water leaching from the reuse system ponds could mobilize and spread contaminants from the landfill. The persuasive evidence demonstrates that storage of the reclaimed water in the reuse system ponds will not result in violations of ground water standards or surface water quality standards. Although the golf course ponds are unlined in the sense that a high-density polyethylene or impermeable clay liner has not been installed on the bottom and sides of the ponds, over the years, marl has formed on the bottom and sides of the ponds, creating an aquitard that substantially confines the reclaimed water to the ponds, rather than allowing it to readily leach into the ground water. Further, the reclaimed water generally is less saline than the ground water underlying the course, so tends to "float" on top of, rather than readily mixing with, the denser, more saline ground water. Additionally, the evidence shows that years of historical ground water monitoring data obtained through monitoring wells on the golf course near the reuse system ponds showed no ground water standards violations as a result of storing reclaimed water from KWRU in the ponds.54/ Because the amount of reclaimed water being sent to the reuse storage ponds is not being changed by the Project, and the nutrient levels in the reclaimed water are being through AWT, there is no factual basis from which to infer that storage of the reclaimed water in the pond will result in violations of ground water standards or surface water quality standards. The persuasive evidence also does not support Zednek's view that reclaimed water leaching into the ground water from the storage ponds will mobilize pollutants under the nearby landfill. As discussed above, the persuasive evidence establishes that, due to the aquitard, there will be very little leaching of reclaimed water into the ground water, and even if such leaching did occur, there would be very little mixing of the reclaimed water with the more saline ground water. As such, there is no demonstrated factual basis on which to infer that reclaimed water will flow under, and mobilize and spread pollutants from, the landfill. Further, the evidence establishes that the predominant ground water flow direction under Stock Island is to the south- southeast. Since the landfill is located north of the reuse system ponds, any reclaimed water that did enter ground water would flow south-southeast, away from the landfill. Zednek also opined that if the storage ponds overflowed, the reclaimed water could run off into surface waters, resulting in surface water quality violations. However, the evidence establishes that KWRU will only send as much reclaimed water to the reuse storage ponds as the Key West Golf Club requests, so any assertion that the ponds will overflow is speculative. Further, even if the ponds were to overflow, Petitioners did not show that the reclaimed water would flow into surface waters, or that it would violate surface water quality standards if it were to flow into surface waters. Petitioners did not prove that KWRU failed to provide reasonable assurance that the storage of reclaimed water in the reuse system storage ponds at the Key West Golf Club will not violate any ground water standards. Stated another way, KWRU provided reasonable assurance that the storage of reclaimed water in the reuse system ponds at the Key West Golf Club golf course will not cause or contribute to violations of ground water standards or surface water quality standards. Applicability of AWT to Existing Wastewater Facility Commencing January 1, 2016, the two new treatment trains authorized by the Permit at Issue must meet the AWT standards. These treatment trains are authorized to treat wastewater to specified secondary standards through December 31, 2015. Petitioners assert that the Permit at Issue must be denied because the two new treatment trains should be required to meet AWT standards immediately upon operation, and that allowing the new treatment trains to meet secondary standards through December 31, 2015, violates section 403.806(10) and rule 62- 620.620(4). Sections 403.086(10)(c) and (d) expressly impose the AWT standards on all new or expanded domestic wastewater discharges after December 31, 2015. Accordingly, the Permit at Issue is completely consistent with the statute. Further, the Permit at Issue does not violate rule 62- 620.602(4). That rule requires a wastewater facility permit applicant to make certain specified demonstrations when a permit is renewed, revised, or reissued having a less stringent effluent limitation than contained in a previous permit. Although the Existing Permit states that the Existing Wastewater Facility has been modified to meet the AWT standards, it further states: "[t]he extended aeration process will be switched to the AWT nutrient removal system prior to January 1, 2016." The clear import of this statement is that the AWT standards are not required to be met until January 1, 2016, consistent with section 403.806(10). Because the Permit at Issue also requires the new treatment trains to meet the AWT standards commencing on January 1, 2016, the Permit at Issue does not impose a less stringent effluent limitation than that imposed by the Existing Permit; accordingly, KWRU is not required to make the so-called "anti-backsliding" demonstrations set forth in rule 62- 620.620(4). Furthermore, it is undisputed that the new treatment trains will not be constructed and operational before January 1, 2016; thus, as a practical matter, the new treatment trains must meet the AWT standards immediately upon going into operation. Thus, Petitioners have not shown that the Permit at Issue should be denied on the basis that it violates section 403.806(10) and rule 62-620.620(4). Petitioners' Standing As noted above, Petitioner Halloran, resides in Key West, Florida. His residence fronts on the water and he owns a boat. Halloran and his family use and enjoy the waters around Key West for swimming, fishing, kayaking, and other in-water recreational uses, eat local-caught seafood, and engage in nature photography. Halloran also owns rental properties that front on the water, and he owns and rents out dock space for houseboat mooring. He is a member of Last Stand. Halloran has challenged the Permit at Issue because he is concerned that the increased discharge of effluent from the Project down the injection wells will degrade the waters around Key West where he and his family engage in in-water recreational uses. He also is concerned that the increased effluent discharge, particularly nutrients, will harm the seagrasses, coral reefs, and the benthic communities in the waters around Key West. Halloran read the initial petition prepared and filed in this proceeding, and he skimmed the Amended Petition specifically to determine the changes from the initial Petition.55/ He acknowledges that he does not completely recall the entire contents of the initial petition or the Amended Petition. Petitioner Last Stand is a not-for-profit corporation incorporated under Florida law. Naja Girard D'Albissin, a member of the Board of Directors of Last Stand, appeared on behalf of Last Stand. D'Albissin testified that Last Stand currently has approximately 105 members. Last Stand's mission is to promote, preserve, and protect the quality of life in Key West and the Florida Keys, with particular emphasis on protecting the natural environment. Last Stand historically has engaged in environmental advocacy directed toward governmental entities and engaged in litigation opposing activities that its members believe would harm the natural environment. In July 2014, Last Stand's Board of Directors voted to challenge the Permit at Issue. Respondent DEP stipulated that 52 members of Last Stand spend time or reside in Monroe County, 50 members enjoy the waters and natural environment of the Florida Keys, and 50 members believe that their use and enjoyment of the natural environment and economic interests in Monroe County will be adversely affected by the Project. Last Stand tendered, for admission into evidence, affidavits of some of its members attesting to the substantial interests they contend will be injured by the Project. However, Last Stand had refused to allow Respondents to engage in discovery regarding these members' alleged substantial interests; accordingly, the undersigned did not allow these members to testify at the final hearing.56/ The affidavits were excluded from admission into evidence as unsupported hearsay. See § 120.57(1)(c), Fla. Stat. Entitlement to Permit at Issue KWRU met its burden under section 120.569(2)(p) to present a prima facie case demonstrating entitlement to the Permit at Issue by entering into evidence the applications and supporting materials for the Permit at Issue for the Project. Additionally, KWRU presented persuasive, competent, and substantial evidence beyond that necessary to meet its burden under section 120.569(2)(p) to demonstrate its entitlement to the Permit at Issue. Petitioners did not meet their burden of persuasion under section 120.569(2)(p) in this proceeding to demonstrate that the Project does not meet all applicable statutory and rule requirements. Furthermore, on rebuttal, KWRU and DEP thoroughly addressed and rebutted the grounds that Petitioners allege justify denial of the Permit at Issue. The persuasive evidence demonstrates that the Project meets all applicable statutory and rule requirements. Accordingly, KWRU is entitled to issuance of the Permit at Issue.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Environmental Protection enter a final order approving the issuance of Domestic Wastewater Facility Permit FLA014951-012-DWIP and UIC Permits 18490-020 and 18490-021. DONE AND ENTERED this 15th day of January, 2016, in Tallahassee, Leon County, Florida. S CATHY M. SELLERS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 15th day of January, 2016.
Findings Of Fact Petitioner Alexis Crlenjak is the owner of an unimproved lot approximately 90 feet by 230 feet in size which abuts Black Creek in Clay County, Florida. (Testimony of Petitioner, Exhibit 2) By application received by the St. Johns River Subdistrict of the Department of Environmental Regulation on September 9, 1980, Petitioner sought a permit to place approximately 1,000 cubic yards of clean fill dirt over an area of 90 by 130 feet to a depth of 3 feet on the southern portion of his lot. The stated purpose for the request was to enable Petitioner to obtain a county permit to install a septic tank and drainfield in the filled portion of the lot. Such a permit previously had been denied by the county for the reason that inadequate drainage for a septic tank existed in the lot's present natural condition. (Testimony of Petitioner, Exhibit 2) Subsequent to receipt of the application, DER's Subdistrict Office solicited comments or objections to the proposed project from adjacent landowners and various governmental agencies. An adjoining landowner, Frederick G. Flagge, filed an opposition to the concept of placement of a septic tank and drainfield next to his land due to the possibility of seepage and contamination. The United States Environmental Protection Agency, Region IV, expressed the view that placement of fill material in flood plain wetlands to raise the elevation for a septic tank placement is not in the public's interest and recommended denial of the application, and suggested that the applicant utilize the upland portion of his property for such purpose. The Southeast Regional Office of the National Marine Fisheries Service, U.S. Department of Commerce, concluded that the work would adversely impact fishery resources by filling productive wetlands and made a similar recommendation to that of the EPA. A representative of the Department of Interior Fish and Wildlife Service inspected the area in November 1980, and found that the proposed project would destroy 0.27 acres of wetlands which provide nesting, feed and shelter habitat for various species of birds, maimals and reptiles. The agency therefore recommended that any fill be limited to upland areas. The Florida Game and Freshwater Fish Commission reviewed the application and recommended denial because the project would adversely affect fish and wildlife resources by eliminating a protective wetland habitat. (Testimony of Tyler, Exhibit 2) Petitioner's lot is bounded on the north by Black Creek, on the east by a dredged canal which terminates at a boat basin immediately south of his property. A filled driveway separates Petitioner' s land from the Flagge property to the west. Although the area surrounding the north bank of Black Creek is still in a natural condition, Petitioner's and Flagge's lots are practically the only ones on the south bank in that area which are undeveloped and still in a relatively natural state. The northern border of Petitioner's property is high and dry due to the berm along Black Creek which has been deposited over the years and has become vegetated. However, the southern half is a hardwood swamp area where blackgum is the dominant species, together with other species such as buttonbush, water ash, dahoon, willow, water locust, red maple and sweetgum. Black Creek is classified as a Class III body of water under Chapter 17-3, Florida Administrative Code. The type of vegetation on the southern portion of Petitioner's lot is associated with periodic inundation during seasonal rainfall, and is thus deemed to constitute the landward extent of waters of the state pursuant to the vegetative indices of Chapter 17-4, Florida Administrative Code. After receiving the application an environmental specialist in Respondent's subdistrict office visited the site and thereafter prepared a Permit Application Appraisal. He identified the various species of plant life located in the area to be filled and determined that it was properly within Respondent's jurisdiction. His appraisal found that the swamp area in question benefits the water quality of Black Creek by filtering sediments and assimilating pollutants generated by upland runoff. He also found that the area is a fish and wildlife habitat, provides flood control, and serves as a primary food source for fish and wildlife. He therefore determined that the proposed project would result in the elimination of those biological resources that aid in maintaining water quality and would further degrade water quality by adding septic tank waste in close proximity to the waterway. He concluded that the project as proposed would induce flooding on the lot to the West by blocking the flow through the swamp which presently is connected by a culvert under the filled driveway to the west. His supervisor subsequently visited the site and agreed with the application appraisal. It was their combined opinion that filling of the land would eventually lead to eutrophication of the adjacent canal and adversely affect the water quality of Black Creek. At the time of their visits, the DER personnel did not observe standing water on Petitioner's property, but did so on the adjacent lot to the west. (Testimony of Rector, Tyler, Exhibit 2) As a result of the adverse application appraisal, Respondent advised Petitioner on December 9, 1980, of its intent to deny the application based on the loss of submerged land, and anticipated water quality degradation by replacing the aquatic ecosystem with a septic tank and drain ield which has a potential for leaking into the adjacent canal. The Notice of Intent to Deny further specified state water quality standards which would be adversely affected, and found that the applicant had not provided the department with affirmative reasonable assurances that the immediate and long-term impacts of the project would not result in a violation of state water quality standards. (Testimony of Tyler, Exhibit 2) At the hearing, Petitioner scaled down his request by stating that he now only wished to fill an area approximately 25 feet by 40 feet in the southwest corner of his lot to serve as the drainfield for a septic tank. However, the DER personnel who had reviewed the project testified that their recommendation of denial would not be changed in spite of the reduced proposed filling activity. They were of the opinion that the same considerations which led to the denial recommendation would still be present, except on a smaller scale. They indicated that Petitioner could still use his land, in spite of the permit denial, for recreational activities, or by erecting a "stilt" house on the lower half of the lot. However, in such an eventuality, the septic tank and drainfield would have to be placed on the upland portion of the lot. As petitioner pointed out, this cannot take place under current health regulations in view of the fact that a well is located on the north side of the adjacent lot, and the spacing distance would be insufficient for state and county permitting purposes. Although Petitioner denied that a culvert existed under the driveway separating the lots, he conceded that he had not visited the property for about a year. (Testimony of Tyler, petitioner, Exhibit 2)
Recommendation That Petitioner's application be DENIED. DONE and ENTERED this 12th day of August, 1981, in Tallahassee, Florida. THOMAS C. OLDHAM Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 12th day of August, 1981. COPIES FURNISHED: Honorable Victoria J. TSchinkel Secretary, Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Silvia Morell Alderman, Esquire Alexis Crlenjak Assistant General Counsel Route 2, Box 618 Department of Environmental Havana, Florida 32333 Regulation 2600 Blair Stone Road Tallahassee, Florida 32301
The Issue The ultimate issue is whether Celebrity Resorts, Inc., (Celebrity) is entitled to a Management and Storage of Surface Waters (MSSW) permit for a surface management system to serve its proposed development in Marion County, Florida.
Findings Of Fact PROPOSED PROJECT Celebrity is seeking a District MSSW permit to construct a surface water management system to serve a proposed recreation vehicle (RV) park. The facility is to be located in northern Marion County on the southern border of Orange Lake, an Outstanding Florida Water. The entire site is within the geographic boundaries of the District. The RV park is to be located on 75 acres of land, and is to contain 372 RV and "park model" sites, four bath houses, a clubhouse, and an expanded boathouse. There is a "break" in the watersheds of the Celebrity property caused by a ridge across the approximate center of the project site. The effect of this "break" is that approximately one-half of the property drains toward the lake while the approximate southerly half of the property drains into an independent depression creating a watershed separate from the lake. Parts of Marion County and Alachua county have been designated as Sensitive Karst Area Basin by the District. The project site is located in the designated area. The existing land use is open pasture. The property was previously used for citrus groves. STANDING Concerned Citizens of Orange Lake Area is an unincorporated group of approximately 76 individuals who want to prevent pollution of Orange Lake. Of the 76 members, three members were present and testified at the hearing. The members attending the hearing were an artist (Riley), a photographer (Suto), and a bass guide (Solomon). Ms. Suto testified that she lives about 1 to 1 1/2 miles from the site. Ms. Riley testified that she lives next door to Ms. Suto and determined that to be over two miles away from the site. Mr. Solomon testified that he lives on the southeast side of Orange Lake approximately 1 to 1 1/2 miles from the project site. No witness testified that any member has a property interest in the subject property. Of the members who testified, none use the subject property. There was no testimony that other members use the property. Twenty-six members wrote letters of concern to the District. Ms. Suto testified to the existence of high levels of lead in her well water. WATER QUANTITY The existing land use, pasture, was used to determine the pre- development peak rate and volume of discharge. The existing surface drainage of the 75-acre project site is divided into two basins. On the north side of the property, the surface water flows toward Orange Lake. This basin is designated on the plans, sheet 3 of 16, by a "2." The south portion of the property is contained within the landlocked drainage basin which is designated on the plans, sheet 3 of 16, by a "1." The post-development flow of surface water will be in the same direction as the pre-development flow. There are no proposed development plans or encroachments into the 100- year floodplain. Therefore, there is no increase in potential for damages to off-site property or persons caused by floodplain development or encroachment, retardance, acceleration, displacement, or diversion of surface waters. There is no reduction in natural storage areas and, in fact, the proposed project increases the natural storage on site. Drainage Basin 2 The District's criterion for systems discharging to basins with an outlet is that the post-development peak rate of discharge for the 25-year, 24- hour storm event shall not exceed the pre-development peak rate of discharge for the 25-year, 24-hour storm event. The District's criteria also require that the post-development volume of discharge not exceed the pre-development volume of discharge. The retention system which ultimately discharges to Orange Lake is designed to retain the entire 25-year, 24-hour storm event through the series of basins on site. The pre-development peak rate of discharge for the drainage basin which flows to the lake is 55 cubic feet per second (cfs) during the 25-year, 24-hour storm event. The post-development peak rate of discharge from drainage basin 2 is 4 cfs. The post-development peak rate of discharge is less than the pre- development peak rate of discharge. Runoff from each RV site will be collected in an individual, ten-inch- deep retention basin. Runoff from the road will be collected in roadside swales. Runoff from the clubhouse, country store, and associated parking lots will be conveyed to drainage retention area (DRA) No. 8. The individual retention basins have the capacity to retain the 25- year, 24-hour storm event without discharging. Any surface water discharges from the individual retention basins in Basins 2A, 2B, and 2C as designated on sheet 3 of 16 will flow to DRA Nos. 4, 5, and 7, respectively. In Basin 2D, runoff from the road and RV park model sites will flow to DRA No. 6. The discharge from DRA No. 6 in the 25-year, 24-hour storm will be zero (0) cfs. In larger storms, any discharge from DRA No. 6 will flow to DRA No. 7. In the event DRA No. 7 overflows, the runoff will flow to DRA No. 5. Basins 2G and 2F are located around two existing sinkholes which currently collect stormwater runoff. In the proposed project, Basins 2G and 2F continue to drain the same area as pre-development. However, additional impervious surfaces will be placed in the drainage area. For this reason, an additional three to five feet of clean fill will be placed in the bottom of each sinkhole for filtration purposes. Basins 2H and 2I are less than one acre and currently drain off site. Berms are proposed around the property line at the basin to keep the stormwater on site. Basins 2H and 2I retain 3/4 inch of runoff over the individual basin. The runoff from Basins 2E1 and 2E flows to DRA No. 8 via a drainage swale. DRA No. 8 will retain 3/4 inch of runoff from the drainage area and is an off-line retention basin. The DRA No. 8 is equipped with a diversion box which allows the 3/4 inch of runoff to enter the DRA and then diverts the runoff from larger storms around the DRA so that the treatment volume of runoff (3/4 inch) continues to be treated in DRA No. 8 and does not mix with and discharge from DRA No. 8 during larger storms. Drainage Basin 1 Drainage Basin 1 as designated on plan sheet 3 of 16 is a landlocked basin which does not discharge to Orange Lake. In Drainage Basin 1, as in Basin 2, the runoff from the RV sites flows to the individual retention basins which retain the 25-year, 96-hour storm event. The runoff from the road flows to swales. Overflow from the basins and swales flow to the DRAs. Drainage Basin 1 does not discharge during the 100- year, 24-hour or the 25-year, 24-hour storm event, pre-development or post- development Drainage Basin 1 is designed to retain the 100-year, 24-hour storm, which is an 11 inch storm event. Drainage Basin 1 is also designed to retain the 25-year, 96-hour storm event. The 25-year, 96-hour storm event is 143% of the 25-year, 24-hour storm event. WATER QUALITY Design Criteria The District's design criteria for water quality are set out in Section 40C-42.025, Florida Administrative Code. The District's retention criteria require that a proposed system have a treatment/pollution abatement volume of 1/2 inch of runoff from the site. For discharges to an OFW, the pollution abatement volume is increased by fifty percent. Therefore, the system must have the volume to retain 3/4 inch of runoff from the site. Each retention basin retains a minimum of 3/4 inch of runoff from the site. The District's criteria regarding quantity of water discharged require a larger volume of runoff to be retained than the District's criteria regarding quality. Therefore, the retention system exceeds the District's criteria regarding quality in order to meet the criteria regarding quantity. The District's retention criteria require that the basin recover the treatment volume within 72 hours. Most of the retention basins retain more than the required treatment volume of 3/4 inch, and most will also recover, or become dry, within 72 hours. The retention basins are capable of being effectively maintained in that the side slopes and bottom of the basins can easily accommodate mowing equipment. For erosion control, staked hay bales and silt screens will be utilized on site during construction to prevent the off-site transport of soil material. Following construction, the retention basins will be vegetated with sod to prevent erosion. The District's criteria require that facilities which receive stormwater runoff from areas with greater than fifty percent of impervious surface shall include a baffle or other device for preventing oil and grease from leaving the system. DRA Nos. 1, 4, 5, and 8 are equipped with an oil and grease removal device called a baffle. The baffle is an acceptable engineering design for the removal of oil and grease from stormwater in a retention basin. The facility operation is uncomplicated. If the individual basins did fill due to a storm event greater than the 25-year, 24-hour or the 25-year, 96- hour in the landlocked basin, they would simply overflow into a DRA. No structures are involved to prevent flooding in large storm events. Water Quality Impacts The individual retention basin at each RV site is considered off-line because it does not discharge in the 25-year, 24-hour storm event. DRA Nos. 1, 2, 3, 4, 5, 6, and 7 are considered off-line because they do not discharge during the design storm. DRA No. 8 is considered off-line because of the diversion box which provides for the retention of the treatment volume and diversion of the larger storms. Off-line retention systems generally show greater pollutant treatment efficiencies than other types of stormwater treatment. The first 1/2 inch of runoff or the "first flush" of rainfall contains ninety percent of the pollutants from the site. SURFACE WATER Utilizing information and methodologies generally accepted by experts in the field of water quality, the District analyzed and projected the average surface water and groundwater quality of the discharge from the surface water management system for the proposed project. No data on runoff concentrations currently exists for RV parks. This analysis was based on a review of existing data on untreated runoff concentrations from three multifamily developments and one highway study. Because data from studies of multifamily residential and highway projects was used, the District's estimates of the untreated runoff concentrations for this project are conservative in that the actual concentrations are probably less than estimated. The District's analysis of the average quality of the discharge from the proposed system was also based on projecting the treatment efficiencies associated with the system. This analysis was done by reviewing data from documented studies previously conducted to ascertain the treatment efficiency of retention methods of stormwater treatment. Generally, retention of the first 1/2 inch of runoff removes eighty percent of the pollutants. On this project, a treatment efficiency of ninety-five percent was assumed based on the fact that the system is off-line treatment and a minimum of 3/4 inch of runoff from the site will be retained in the basins prior to discharge. The expected average untreated runoff concentrations were then educed by the expected treatment efficiencies to project post-treatment water quality of the discharge from the proposed system. These numbers were then compared to Chapter 17-302, Florida Administrative Code, water quality standards for Class III water bodies, and ambient water quality in Orange Lake. Orange Lake is classified as an OFW. Therefore, the proposed project cannot be permitted if it will cause degradation of that water body. The background data or ambient water quality data for phosphorous and nitrogen was taken from the Orange Lake Biological Report by the Florida Game and Freshwater Fish Commission in 1986. The ambient water quality for the other parameters in Table 2 of District Exhibit 2 was computed using eight years of data from a District monitoring station on Orange Lake. The projected average concentration for each constituent in the discharge from the system is less than the ambient water quality of Orange Lake. Therefore, the proposed surface water discharge will not violate state water quality standards in waters of the state. The post-development pollutant loading rates should be equal to or better than the pollutant loading rates from the use of the property as citrus or pastureland because the runoff is being retained on site and treated before being discharged. GROUNDWATER Groundwater discharges were reviewed by assessing the type of soil below the retention basin and the distance to the water table. The soil on the site contains some organic matter which is beneficial for treatment purposes. Based on the borings submitted by Celebrity, the water table, if any, is five feet or more below the bottom of any proposed retention basin. Runoff in the basin will percolate through the soil. Nutrients such as nitrogen and phosphorus will be taken up by the vegetation in the bottom of the basins. Metals will bind to the soil material below the basin. Oils and greases will be broken down through microbial degradation into nontoxic material. Groundwater discharges from the proposed system will not violate any applicable state groundwater quality standards. These standards will be met within the first three feet below the treatment basins. The standards will also be met by the time the groundwater discharge moves to the edge of the zone of discharge which is at the property boundary. The discharge from the proposed Celebrity project will not cause or contribute to a violation of state water quality standards in the receiving waters. SINKHOLES Sinkholes may form on the site. Sinkholes that form will probably be "cover subsidence" sinkholes. Cover subsidence sinkholes are those in which a void below the surface fills with the soil from above, causing a depression in the ground surface. There are four relict sinkholes on site. They are cover subsidence sinkholes. The sinkhole nearest the lake has water in the bottom. Stormwater runoff is directed away from the sinkhole. Any water which enters the sinkhole from the land surface or above will enter from the sky. The District has proposed criteria for stormwater systems in designated Sensitive Karst Area Basins. Those criteria are that 1) the water in the basins shall be no deeper than ten feet deep; 2) there should be at least three feet of unconsolidated material between the bottom of the basin and the top of the water table; and 3) the basins should be fully vegetated. The District currently applies these criteria as policy. In this project, the basins are shallow, ranging from ten inches deep at the RV sites to 2 1/2 feet in the DRAs. The basins have at least three feet of unconsolidated material between the bottom of the basin and the top of the water table. In the soil borings performed by Celebrity, the water table was shown to exist between five and fifty feet below land surface. The proposed project design meets or exceeds the proposed criteria for Sensitive Karst Area Basins. The basins will be fully vegetated or sodded with grass. Lineations or lineaments are solution features which may indicate a fracture of the underlying limestone. There may be a lineament on the site. There are other sinkholes in the area. If a cover subsidence sinkhole develops in an individual retention basin or DRA, stormwater, if any, will seep or percolate through the several feet of soil prior to reaching an aquifer. Most of the pollutants in the retention basin will meet groundwater quality standards prior to percolation and further treatment in the soil. OPERATION AND MAINTENANCE Special conditions Nos. 13, 14, and 15 on the permit will require Celebrity to inspect the system monthly for sinkhole development. If a sinkhole develops, Celebrity must notify the District within 48 hours of its discovery. Celebrity must submit a detailed repair plan within 30 days for written approval by the District. Celebrity proposes to repair any sinkholes that develop by a District- approved method. Celebrity Resorts, Inc., is a legally established corporation registered in Delaware and owns the subject property. Celebrity does not intend to subdivide the property but to sell memberships to use the property on a time-share basis. Celebrity will administratively operate the site by employing a park manager who will remain on the property 24 hours a day. If any problems occur with the basins, either he or his designee will be on site to respond quickly to the situation. The park manager will have a full-time maintenance staff which will operate the park. Celebrity will financially operate and maintain the proposed system using funds currently raised and in the future by membership fees. Celebrity is a publicly held corporation. Funds raised from the sale of stock, approximately $3,500,000, have paid for legal and administrative fees as well as the land purchase. Approximately $400,000 has been reserved to operate the facility. It will cost approximately $15,000 per month to run the park. Memberships will be sold for $300 per year. Part of the membership fees will go toward the general maintenance of the site. Maintenance of the proposed system will include regular mowing and monthly inspection for sinkholes and repair if necessary. WETLANDS IMPACTS OF THE PROJECT The property contains waters of the state wetlands and isolated wetlands. The waters of the state wetlands are those along the shore of Orange Lake. One isolated wetland exists on site in the sinkhole which is closest to the lake. The sinkhole has standing water in which lemna, or duckweed, is growing. Duckweed is a listed plant species in Section 16.1.1(2) of the Handbook. No construction is proposed in either the waters of the state wetlands or the isolated wetland. The District criteria require the review of impacts to off-site aquatic and wetland dependent species relative to the functions currently provided by the wetlands to these types of fish and wildlife. Since there will be no construction in the wetlands, there will be no impacts to the habitat, abundance and diversity, or food sources of off-site aquatic and wetland dependent species from this proposed project. No threatened or endangered aquatic and wetland dependent species were observed on site. The proposed permit application will not adversely affect natural resources, fish, or wildlife in a manner which is inconsistent with the District criteria. The proposed permit application will not adversely affect hydrologically-related environmental functions in a manner which is inconsistent with the District criteria.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the petition filed by Concerned Citizens of Orange Lake Area be dismissed for lack of standing and that Celebrity Resorts, Inc., be issued a MSSW permit for its system as designed and proposed. DONE and ENTERED this 19th day of July, 1991, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 19th day of July, 1991. APPENDIX TO THE RECOMMENDED ORDER The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the proposed findings of fact submitted by the parties in this case. Specific Rulings on Proposed Findings of Fact Submitted by Petitioner, Concerned Citizens of Orange Lake Area 1. Proposed findings of fact 1-6 are subordinate to the facts actually found in this Recommended Order. Specific Rulings on Proposed Findings of Fact Submitted by Respondent, Celebrity Resorts, Inc. 1. Proposed findings of fact 1-38 are subordinate to the facts actually found in this Recommended Order. Specific Rulings on Proposed Findings of Fact Submitted by Respondent, St. Johns River Water Management District 1. Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1&2(1); 3-7(4-7); 8-20(8- 20); 21(2); 22-31(21-30); 32(16); and 33-107(31-105). COPIES FURNISHED: Crawford Solomon Qualified Representative Concerned Citizens of Orange Lake Post Office Box 481 Citra, FL 32681 William L. Townsend, Jr. Attorney at Law Post Office Box 250 Palatka, FL 32178-0250 Nancy B. Barnard Attorney at Law St. Johns River Water Management District Post Office Box 1429 Palatka, FL 32178-1429 Henry Dean, Executive Director St. Johns River Water Management District Post Office Box 1429 Palatka, FL 32178-1429
The Issue Schofield Corporation of Orlando has applied to the Department of Environmental Regulation for a permit to construct and operate a Class III trash/yard trash landfill in Orange County, Florida. The issues are whether the applicant is entitled to the permit and, if so, what conditions should attach. Also at issue is Schofield Corporation's motion for attorney's fees and costs, pursuant to Section 403.412(2)(f), F.S.
Findings Of Fact The applicant, Schofield Corporation of Orlando (Schofield), owns the proposed landfill site and existing permits for the site. The proposed site is located in West Orange County, southwest of the intersection of State Road 545 and Schofield Road on the west half of the northwest quarter of section 32, township 23 south, range 27 east, comprising approximately sixty acres within a larger eighty-acre parcel. In some undetermined distant past the site was cultivated in citrus. It is currently being excavated as a borrow pit. The materials proposed to be placed in the landfill include trash, yard trash, construction and demolition debris and clean debris, as defined in DER Rule 17-701.020, F.A.C. The northern half of the site is flat and will be used first for the composting operation. The southern excavated portion of the site will receive the permitted fill material until it is flattened. Then, the two functions will alternate; the composting will occur on the south, and the north end will be excavated to receive fill. The proposed facility will be operated by Chambers Corporation, a nationally recognized waste management company with approximately 20 years of experience in solid waste management. The landfill site will be completely fenced, with a gate entrance mid-site between the landfill and compost area. The gate will be locked when the facility is not in operation, and will be patrolled by security personnel 24 hours a day. "Spotters", or inspectors will be employed to examine incoming waste loads at the gate, from a high gantry, and at the place where the waste is deposited. The loads will be monitored by a television camera, and all haulers will be under contract. The landfill will not accept loads from trucks coming off the road looking for a place to dump. Receptacles will be maintained on site to receive errant non-permitted waste that is found in a load, and that waste will be properly disposed of elsewhere. Schofield has several permits related to its proposed operation. These include a type III landfill permit from Orange County, a compost facility permit from DER, a general construction and demolition debris landfill permit from DER, a surface water management permit from the South Florida Water Management District, and a permit to excavate or mine from the Florida Department of Natural Resources. Schofield also has a contract to receive yard waste from Orange County. The initial term of contract requires at least ten percent of the yard waste to be composted or recycled, with the percentage amount to be renegotiated in subsequent contract renewals. In the hierarchy of landfills, DER considers Class III the least environmentally sensitive. Problems with unauthorized waste and with water quality occur more frequently with Class I landfills, defined as accommodating more than twenty tons a day of residential garbage. In this case DER has proposed to grant Schofield its Class III permit without the requirement of a bottom liner or a leachate or gas control system because of the nature of the waste that will be accepted and because of the rigorous controls, described above, to avoid receiving unauthorized or hazardous waste. The Petitioners are an individual and a homeowners' association representing a residential area approximately a half mile south of the proposed site. Petitioners contend that the applicant's data is insufficient to provide reasonable assurances that water quality standards will not be violated. Petitioners contend that the landfill, if approved, should be required to have a liner to prevent leachate from polluting the groundwater. They further contend that the groundwater monitoring plan submitted by the applicant is inadequate to detect vertical movement of contaminated leachate into the Floridan aquifer, a major source of water supply in Orange County. Hydrogeology The site of the proposed landfill is within a high recharge area. Water percolates rapidly though the soil, moving downward into the aquifer, and laterally off site. The site is considered Karst terrain, underlined with limerock. There is evidence of relic sinkholes, thousands of years old, but there is a low probability of future open sinkhole development. The geology in the area of the site provides adequate structural support for the proposed facility. An aquifer is generally defined as a unit of material which contains water and can give up a sufficient amount of yield to provide some productive flow for pumpage. Below the site there are two aquifers: the shallow water table, or surficial aquifer, containing clean well-drained fine sands, about 70 feet down; and the Floridan, primarily limestone, encountered at a depth of approximately 115 feet. The two are separated by a confining layer of less permeable sands and clay. Flow in the Floridan at the site is primarily from the west to east. Flow in the surficial is also generally from west to east, but the Petitioners theorize, and have presented competent supporting evidence, that there are fissures in the confining layer, allowing some internal drainage within the site, causing surficial water to flow vertically into the Floridan, rather than laterally off-site in an eastward direction. Based on recent data taken from two piezometers installed near the middle of the site, the applicant's hydrogeologist, James Golden, concedes that "mounding" exists along the eastern boundary of the site, reflecting some flow westerly back into the interior of the site. Petitioners' theory regarding internal draining of the site is based in part on data as to groundwater elevation. Groundwater elevation or high groundwater table is the elevation at which water stands on a continuous surface under the site. Jammal and Associates is a consultant firm which has done field studies of this and neighboring sites in the past, for various purposes. Some open bore readings taken by Jammal and Associates in a 1983 study for the Orange County Rapid Infiltration Basin project indicate groundwater table levels on site up to 126 feet, National Geodetic Vertical Data (NGVD). Open bore readings are less reliable than cased hole readings; due to collapses within the hole, artificially high readings are sometimes obtained. Data from the applicant's consultants reveals groundwater tables at 96-98 NGVD. This data was most recently obtained in December 1991 from sealed and surveyed piezometer casings, but not from the area of the site where Jammal's higher readings were obtained. Although it may be conjectured that Jammal's high readings are anomalous, additional sealed borings need to be obtained before the anomaly is confirmed. Groundwater elevations are significant also to determine the depth to which the landfill may be excavated. Based on its December 1991 readings, obtained after the application for permit was filed, the applicant agreed to raise the proposed bottom of the landfill to approximately five feet above the level of the estimated high (wet weather) groundwater table in the area. Water Quality and Monitoring Specific conditions of the proposed permit include DER's requirements that Class GII water quality standards be met at the boundary of the zone of discharge, in accordance with Rule 17-3, F.A.C. The zone of discharge for this facility is a three-dimensional volume defined in the vertical plane as the top of the ground to the base of the most surficial aquifer, and horizontally 100 feet from the edge of the waste-filled area, or the property boundary, whichever is less. The groundwater monitoring plan proposed by the applicant includes one upstream monitoring well on the west side of the site and five wells along the east side of the site, with an additional well at the south, between the project and the Petitioners' residential area. The wells extend down into the upper zone of the surficial aquifer, but not into the deeper limestone Floridan. The downstream wells should detect any contamination in the surficial aquifer flowing from west to east at the zone of discharge. However, they will not pick up contamination draining internally within the site and into the Floridan. Such contamination is possible, even though leachate from Class III- type wastes is expected to be relatively benign. Volatile organic carbons (VOCs) have not typically been a problem in Class III landfills, unless those landfills were previously operated as Class I sites. Secondary drinking water standards for certain metals have been violated at some Class III sites, but such violations are often related to the problem of sampling newly-installed wells. From DER records, Petitioners presented evidence of consistent drinking water quality standard violations in Class III landfills. That such violations can occur in Class III landfills is clearly established. It is not so clear that such violations will occur in this facility, given the proposed controls on load content. However, even acceptable materials will not avoid the production of leachate or gas. Within demolition waste there are chemically bound components which are inseparable, for example, creosote and other preservatives, glues, paints, resins, varnishes and stains. The lignin, tannins and volatile organic acids which are produced when wood decomposes alter the pH of the groundwater. As the water becomes more acidic, heavy metals that were typically bound up in the waste or in the soil, are released in soluble form and travel with the water. The decomposition process occurring in the construction and demolition waste is enhanced by the addition of yard trash which becomes the food source for the biodegradation. Summary of Findings and Proposed Permit Conditions If, as applicant suggests, all groundwater moves primarily from west to east within the site, given the proposed operational controls and the proposed monitoring plan, reasonable assurances have been provided that water quality standards will not be violated beyond the zone of discharge. That is, any contamination likely to occur will be contained within the surficial aquifer and within the 100 feet or property line horizontal boundary. Transmissivity of the surficial aquifer is low enough to allow mixing of the leachate before it reaches the zone of discharge. The Petitioners, however, have presented credible evidence sufficient to question the groundwater flow premise and sufficient to require additional conditions on the permit. If leachate reaches the Floridan through fissures in the confining layer, it will move rapidly off site. In its proposed recommended order DER has suggested additional permit conditions and in its adoption of the proposed recommended order, the applicant has accepted those additional permit conditions. Those permit conditions recognize the fact that data presently provided by the applicant is insufficient to overcome the evidence by Petitioners as to the hydrogeological characteristics of the site with the possibility of internal drainage and vertical intrusion of contaminated water into the Floridan aquifer. The proposed recommended order provides this finding: ...that the ground water monitoring plan as proposed in this proceeding is adequate, provided that there be added to the permit conditions that the permittee conduct appropriate water table testing with cased piezometers during the next wet season to determine whether ground water flow is internal within the site and therefore not intercepted by the present ground water monitoring wells. The permittee shall consult with DER and get approval for the location and construction of these wells prior to their installation. The results shall be immediately submitted to the DER. The ground water monitoring requirements should be modified if necessary at that time pursuant to Rule 17-28.700(5) to assure proper monitoring at this site. (DER proposed Recommended Order, p. 17) The ground water monitoring plan modification suggested by DER is that deeper monitoring wells, into the Floridan aquifer, be required if the additional testing reveals the likelihood of internal on-site ground water drainage. These conditions are still inadequate since they lack specificity with regard to the extent of testing, the location and construction of the wells, and the amendments to the monitoring program to be required if internal drainage is confirmed. Moreover, the proposed conditions fail to address the possibility that the permit should require a liner for the landfill if the data to be obtained reveals the likelihood that contaminates will penetrate into the groundwater of the Floridan. Monitoring programs, however effective, only predict or detect problems; they do not remediate them. Groundwater contamination by landfills is not quickly and easily reversed. Unlike discharges from other facilities such as spray application or deep well injection, the leachate from a landfill is not "turned off". Without the additional data which all parties agree is needed, it is impossible to determine what additional conditions, if any, should be required or what amendments, if any, need to be made to the applicant's proposed monitoring plan.
Recommendation Based on the foregoing, it is hereby, RECOMMENDED: That the Department of Environmental Regulation issue its Final Order denying the application for Class III land fill permit. DONE AND RECOMMENDED this 17th day of June, 1992, in Tallahassee, Leon County, Florida. MARY CLARK Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904)488-9675 Filed with the Clerk of the Division of Administrative Hearings this 17th day of June, 1992. APPENDIX TO RECOMMENDED ORDER The following constitute specific rulings on the findings of fact proposed by the parties: Petitioner's Proposed Findings of Fact Adopted in paragraph 1. Adopted in substance in paragraph 10. 3.-11. Rejected as unnecessary. 12.-23. Rejected as argument or summary of testimony, rather than findings of fact. 24. Rejected as unnecessary. 25.-30. Rejected as argument or summary of testimony, rather than findings of fact. 31. Rejected as unnecessary. 32.-41. Rejected as argument or summary of testimony, rather than findings of fact. Rejected as unnecessary. Adopted in substance throughout the recommended findings. 44.-50. Adopted in Preliminary Statement and paragraph 4. 51. Rejected as unnecessary. 52.-53. Adopted in paragraph 2. 54.-55. Rejected as statement of testimony rather than finding of fact. Adopted in paragraph 3. Rejected as unnecessary. 58.-97. Rejected as argument or statement of testimony, rather than findings of fact. Subparts a), b), c) and e) are rejected as unsupported by competent evidence. The evidence suggests that violations might occur and that insufficient data has been produced. Subpart d) is adopted, by implication in paragraph 18. 99.-101. Adopted in summary in paragraph 20. Respondent's Proposed Findings of Fact Addressed in Preliminary Statement. Adopted in paragraphs 1, 2 and 5. 3.-4. Adopted in paragraph 4. Adopted in summary in paragraph 11. Adopted in paragraph 13. Rejected as unnecessary or irrelevant, given the stipulation related to Section 403.412, F.S. standing. Rejected as cumulative. Adopted in paragraph 10. Adopted in paragraph 9. Adopted in substance in paragraph 9. 12.-13. Adopted in paragraph 13. Adopted in substance in paragraph 16. Rejected as unsupported by the evidence. If internal drainage is shown to exist, conditions other than additional monitoring wells may be required. Adopted in paragraph 17. 17.-18. Adopted in paragraph 3. 19.-21. Rejected as unnecessary. Adopted in paragraph 4. Adopted in paragraph 12. 24.-26. Adopted in general in paragraph 14. 27. The unlikelihood that unauthorized waste will be dumped is adopted in paragraph 3. Whether there will be a violation of ground water quality standards at the zone of discharge was not established, given the need for additional data on internal draining. COPIES FURNISHED: Thomas B. Drage, Jr., Esquire P.O. Box 87 Orlando, FL 32802 Irby G. Pugh, Esquire 218 Annie Street Orlando, FL 32806 Douglas H. MacLaughlin Asst. General Counsel DER-Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Carol Browner, Secretary DER-Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson General Counsel DER-Twin Towers Office Building 2600 Blair Stone Road Tallahassee, FL 32399-2400
The Issue Whether Gar-Con's revised application for a permit to construct a sewage plant, and soakage trenches to dispose of the effluent, should be granted?
Findings Of Fact Eight to ten miles south of Melbourne Beach and 8.3 miles north of Sebastian Inlet, Gar-Con plans to develop a parcel of land stretching west from the Atlantic Ocean, across Highway A1A, to the Indian River. Gar-Con expects to build a motel and residential complex complete with tennis courts, parking garage, water treatment plant and the sewage treatment facility for which a construction permit is sought in these proceedings. The sewage treatment plant would be built on a site 480 feet west of Highway A1A and 90 feet south of Gar-Con's northern property line, at an elevation of 11 or 12 feet above mean sea level. Ocean Way Water and Sewer Association, Inc. is to be organized as a nonprofit corporation to own and operate the wastewater treatment facility. The Public Service Commission, through the director of its water and sewer treatment, has taken the position that the proposed "sewer system will fall within the exemption described in Section 367.022(7), Florida Statutes." DER's Composite Exhibit A. PACKAGE PLANT PROPOSED The facility Gar-Con proposes is designed to treat 100,000 gallons of sewage daily, which is the estimated "total flow" (T. 75) the sanitary engineer who designed the system anticipates from the development. Sewage generated by the development would flow to the plant, through a bar rack designed to remove rags and other large objects, and into aeration tanks where, over a 24 hour period, interaction with air and a biological mass would supply oxygen and cause the formation of biological floccules. The flocculant sewage would then move to a clarifier hopper. During its five hour stay there, solids which were not earlier segregated as the sewage moved over a weir into the clarifier, would be precipitated and removed. The clear, residual liquid would be pumped through one of two sand filters (each of which would also have granular activated carbon and be capable of filtering 100,000 gallons daily) into one of two chlorine contact chambers where a gas chlorinator would introduce chlorine for an hour. Under ordinary circumstances, the chlorinated effluent would then be pumped into one of two soakage trenches. The soakage trenches, each designed for use every other week, are to be gravel-filled ditches covered over first with felt paper, then with compacted fill. The gravel would lie at least one foot beneath the surface of the ground in a space ten feet wide and three feet deep stretching the 940 foot length of each soakage trench. Punctured like sieves, two six-inch PVC pipes would run through the gravel, sweating effluent from their pores. There is also a plan to dig a percolation pond or grassed swale five feet deep, 120 feet long and 80 feet wide near the wastewater treatment plant, which could serve as a receptacle for effluent, in case of "a 1:10 year storm or when the filters are down and/or if soakage trenches would need repair." Gar- Con's Exhibit 2-A. It would hold about 100,000 gallons. The solids caught by the weir, those extracted in the clarifying process, and those recovered from backwashing the filters would serve as catalyst for the aeration process as needed. Excess sludge, about 3,000 pounds monthly, would undergo "aerobic digestion," before being removed to Brevard County's Central Disposal Facility on Adamson Road, for disposal there. Gar- Con's Exhibit No. 7. Primary and secondary drinking water standards would be met by the effluent as it left the plant (although the engineer who designed the system would not drink the effluent himself), except that, from time to time, nitrate concentrations might reach 12 milligrams per liter, and except in the "event that a homeowner might put some type of [inorganic toxic or carcinogenic] material into the sewer system." (T. 86) The biological oxygen demand (BOD) would be ten milligrams per liter; suspended solids would probably amount to about five milligrams per liter; pH would probably be slightly under seven; nitrates would average approximately eight milligrams per liter but would "peak out at certain times during the year, for maybe extended periods up to two months, at twelve milligrams per liter," (T. 80); and there would be a chlorine residual after 60 minutes of two milligrams per liter. AMBIENT WATERS There would be no direct discharge to the Atlantic Ocean, Indian River or any other body of surface water, nor would any indirect effect on surface waters be measurable. No body of surface water lies within 500 feet of the site proposed for the plant and soakage trenches. Potable groundwater underlies the site; the groundwater table slopes toward the Atlantic Ocean, 9.5 to 12.5 feet below ground. "[D]uring the traditional rainy season," Gar-Con's Exhibit 2B, Attachment, p.3, the groundwater may rise to within seven feet of the surface. The PVC pipes in the soakage trenches are to be placed two and a half feet deep. As effluent percolated through the sandy soil, there would be "mounding" of the groundwater underneath the soakage trenches, and dispersal in all directions. Surface flow is to be diverted from the soakace trenches so that only rainwater falling directly on them would percolate down through the gravel beds. Taking soil characteristics into account, and assuming a "water table depth" of 20 feet, an engineer retained by Gar-Con predicted that "the maximum expected groundwater rises beneath the east and west trenches are 2.4 and 2.1 feet, respectively under a loading of 100,000 gpd for a period of 7 days." Gar-Con's Exhibit No. 3. The water table depth, "the height, the top of the groundwater from the first restrictive layer," (T. 172), is probably more like 40 feet than 20, which accounts in part for the "conservatism" of the mounding predictions. Under very severe weather conditions (a 100 year storm), groundwater would rise as high as the bottom of the trenches making them unavailable to receive effluent, but the effluent would not be forced above ground. In a 100 year flood, water would be expected to rise to seven feet above mean sea level. Under such conditions, people could be expected to evacuate the area. In a 25 year storm, the system could be expected to continue to function. Groundwater to the north and east of the proposed site was sampled, and the samples were analyzed. The water to the north had 380 milligrams of chlorides per liter and the water to the east had 450 milligrams of chlorides per liter. As it left the proposed treatment plant, the effluent would contain approximately 150 milligrams of chlorides per liter. SOUND AND LIGHT Lights like those used as street lights are to be installed at four places in the wastewater treatment plant. A timer, which can be overridden, would turn the lights on at dusk and off at eleven o'clock at night. The lights would illuminate the plant adequately. Pumps would move sewage to and through the proposed plant. Most of the pump motors would be submerged and unable to be heard. Two electric blowers, a flow meter and a totalizer would also have electrical motors. The blowers and the blower motors are to be equipped with insulated fiberglass covers and the blowers would also have intake and double outlet silencers. Four feet from the plant the noise of the motors would be comparable to that of a home air conditioning unit. At the nearest residence the noise level would scarcely exceed background noise. At hearing, Gar-Con revised its application and agreed to install an emergency generator which would also be encased in insulated housing and is to be equipped with a muffler. AEROSOL AND ODOR Unless the proposed plant loses electric power for 24 hours or longer, no offensive odors would emanate from it. The bar rack and weirs would be regularly hosed down. Against the possibility of a power failure, Gar-Con agreed at hearing to install permanently an emergency generator with sufficient capacity to keep both the wastewater treatment plant and the water treatment plant it plans to build operable. No aerosol drift is foreseen. The surface of the liquid In the aeration tanks would be 1.4 feet below the top of the rim. Walkways four feet wide along the inside perimeters of the aeration holding tanks would prevent dispersal of most of aerosol. A decorative hedge around the treatment plant, which would eventually be 15 feet high, is a final fail-safe. WELLS To the north are two shallow wells within 500 feet of the site proposed for the wastewater treatment plant. Both wells belong to Kel Fox, who wrote Gar-Con that he had no objection to their proposed wastewater treatment facility in light of Gar-Con's agreement to furnish drinking water to existing facilities on his property and reimburse him expenses incurred in disconnecting the two shallow wells. Gar-Con's Exhibit 2E. There is a deep well within 500 feet to the south. DER and Gar-Con have entered into the following stipulation, dated September 2, 1983: Existing Wells. Prior to the operation of its waste water treatment plant, Gar-Con will offer to supply drinking water at a reasonable cost to owners of property on which are located operational or approved shallow drinking water wells that are within 500 feet of Gar-Con's land application site. Gar-Con will make this offer to all such owners known to it prior to the operation of its plant. Gar-Con will further offer to provide reasonable compensation to such owners to disconnect their shallow wells. Gar-Con will endeavor to arrange for provision of drinking water to these owners and the disconnection of those wells prior to the operation of its plant. Future Wells. Should nearby individual (non-corporate) property owners propose to construct shallow drinking wells located within 500 feet of Gar-Con's land application site after Gar-Con begins operation of its waste water treatment plant, Gar-Con also will offer to supply them with drinking water at a reasonable cost and to provide reasonable compensation to them to disconnect those wells. However, Gar-Con shall have no obligation to make any such offer to owners of future wells if sampling of monitoring wells located at or near its external property line indicates that the groundwater meets the primary drinking water standards and, after July 1, 1985, the secondary drinking water standards listed in Florida Administrative Code Rule 17-22.104. Gar-Con agrees to record a master notice of restriction barring future owners of lots within the Ocean Way development, which are owned by Car-Con at the time of permit issuance, from installing shallow drinking water wells on such property or otherwise using the shallow aquifer beneath their property as a source for irrigation or for potable water, so long as use of the proposed sewage disposal system continues, and the Department has not found that this restriction is unnecessary. This restriction, which shall be a covenant running with the land, further shall require future owners to purchase water from Gar-Con or any successor owner of the development's water system if Gar-Con or the successor provides water service. These restrictions also shall be contained in all other appropriate documents of title. In addition, Gar-Con plans to create a non-profit water and sewer association to own and control the development's water and sewer system. Gar-Con will include in the Articles of Incorporation of this association a requirement that all property owners served by the system must be members of the Association. Gar-Con is entitled to a zone of discharge extending to its current property line with the exception that the zone of discharge shall not include the area contained within a 100' radius of Gar-Cons's proposed water supply wells. DER Staff concurs that the above conditions, in conjunction with the sewage treatment and disposal system and the groundwater monitoring program proposed by the applicant, to meet the requirements of Chapter 17-4, F.A.C. will provide reasonable assurance that existing and future off-site and on-site property owners will be protected from any adverse effects that might result from the operation of the proposed sewage treatment disposal system. Petitioner's Exhibit No. 10. There are to be a half dozen monitoring wells to allow sampling of the groundwater at strategic points in the shallow aquifer. NATURAL RESOURCES Turtles nest in the general vicinity but off the site of the proposed project. Construction and operation of the proposed waste water treatment facility would have no impact on the turtles apart from making it possible for more people to live closer to where they nest.
Findings Of Fact Upon consideration of the petition for a variance, the recommendation of the Department of Environmental Regulation and the prehearing stipulation of the parties, the following relevant facts are found: Tampa Electric Company is the owner and operator of the Big Bend Generating Station which presently consists of three coal fired steam electric generating units (Units 1, 2 and 3) in Hillsborough County, Florida. The Big Bend Generating Station is located on the eastern shore of Hillsborough Bay, a Class III body of water. Discharges from the Big Bend Station are subject to regulation by the Department of Environmental Regulation. The discharge that is the subject of this proceeding is from the slag pond currently serving Big Bend Units 1, 2 and 3. Tampa Electric Company originally requested variances from the surface water quality standards contained in Rules 17-3.051 (minimum criteria), 17-3.061(2) (general prohibition), 17-3.061(2)(a) (arsenic), 17-3.061(2)(d) (chromium), 17- 3.061(2)(h) (lead), 17-3.121(9) (cadmium), 17-3.121(11) (copper), 17-3.121(16) (iron), 17-3.121(17) (lead), 17-3.121(18) (mercury), 17-3.121 (19) (nickel), and 17-3.121(26) (selenium) of the Florida Administrative Code for the discharge from this existing slag pond. At the hearing, Tampa Electric Company withdrew its request for variances from the provisions of Rules 17-3.051 (minimum criteria), 17-3.061(2) (general prohibition), and 17-3.061(2)(h) and 17- 3.121(17) (lead). Data collected by Tampa Electric Company during the period of 1970 through 1974, 1980 and 1981 demonstrate that the quality of the ambient intake water in Hillsborough Bay contains concentration of arsenic, chromium, cadmium, copper, iron, mercury, nickel, and selenium in amounts which periodically exceed the applicable Florida water quality standards for that water body as contained in Chapter 17-3, Florida Administrative Code. Water quality data for the Big Bend Units 1, 2 and 3 slag pond discharge collected during the 1980-81 study demonstrate that there will be either minimal or no net increase, or a reduction between the ambient intake and discharge for all metals except iron and selenium. Upon mixing with the flow in the discharge canal, water quality impacts due to these parameters are expected to be minimal. The Department of Environmental Regulation has recommended granting a variance for the parameters cadmium, mercury and nickel based upon the following: mercury concentration decrease upon passing through the slag pond; cadmium and nickel concentrations remain the same passing through the slag pond; and, therefore, the slag pond system does not appear to contribute to the existing water quality violations for cadmium, mercury, or nickel. The Department of Environmental Regulation's analysis of the other parameters indicates that the concentrations of arsenic, chromium, iron and selenium increase in passing through the slag pond system. This increase appears to be due to an increase in suspended metals. Additional treatment of the discharge from the slag pond would be necessary to meet water quality criteria in the effluent for the parameters arsenic, chromium, iron and selenium. Compliance would require further removal of these parameters possibly by the use of a reverse osmosis treatment system. The cost of treating the slag pond discharge pond stream to comply with water quality standards by use of reverse osmosis would be approximately $28.2 million. The $28.2 million expenditure is not justified or practicable in this case. The Department of Environmental Regulation agrees that this expenditure is not justified in this case and has recommended a variance for these parameters as well. The damage or harm resulting or which may result to Tampa Electric Company from compliance with the rules from which the variance relief is sought would be the expenditure of $28.2 million for an additional treatment system with no significant resulting benefit to the environment. The failure of the Department of Environmental Regulation to grant the requested variance could result in Tampa Electric Company being unable to operate this facility. The Department of Environmental Regulation recommends a two-year variance from the surface water quality standards contained in Rules 17- 3.061(2)(a) (arsenic), 17-3.061(2)(d) (chromium), 17-3.121(9) (cadmium), 17- 3.121(11) (copper), 17-3.121(16) (iron), 17-3.121(18) (mercury), 17-3.121(19) (nickel), and 17-3.121(26) (selenium) of the Florida Administrative Code for the discharge from the slag pond serving existing Big Bend Station Units 1, 2 and 3. The recommendation is conditioned upon Tampa Electric Company's agreement to monitor the metal content of the slag pond discharge, to evaluate alternative treatment systems and to submit a report describing treatment systems evaluated, including costs and feasibility, within eighteen (18) months of the effective date of the variance relief. Tampa Electric Company has agreed to the recommendation and conditions of the Department of Environmental Regulation. Appropriate public notice of this proceeding has been given. At the conclusion of the hearing, the public was given an opportunity to comment and present evidence on the petition for variance. No public testimony was offered.
Recommendation Based upon the findings of fact and conclusions of law recited herein, it is RECOMMENDED that Tampa Electric Company be granted a two-year variance from the surface water quality standards contained in Rules 17-3.061(2)(a) (arsenic), 17-3.061(2)(d) (chromium), 17-3.121(9) (cadmium), 17-3.121(11) (copper), 17- 3.121(16) (iron), 17-3.121(18) (mercury), 17-3.121(19) (nickel) and 17-3.121(26) (selenium), Florida Administrative Code, for discharges from the slag pond for existing Big Bend Station Units 1, 2 and 3. The granting of this variance should be conditioned upon Tampa Electric Company's agreement to monitor the metal content of the slag pond discharge during the duration of the variance, evaluate alternative suspended metals removal treatment systems, and submit a report to the Department of Environmental Regulation describing the treatment systems evaluated and the costs and feasibility of those systems within eighteen (18) months of the effective date of the variance. Respectfully submitted and entered this 5th day of August, 1981, in Tallahassee, Florida. DIANE D. TREMOR Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 904/488-9675 Filed with the Clerk of the Division of Administrative Hearings this 5th day of August, 1981. COPIES FURNISHED: Lawrence N. Curtin, Esquire Holland and Knight Post Office Drawer BW Lakeland, Florida 33802 Louis F. Hubener, Esquire Assistant General Counsel Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 Hamilton S. Oven, Jr. Administrator, Power Plant Siting Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 Honorable Victoria Tschinkel Secretary, Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301
The Issue Whether Petitioner should be granted a certificate authorizing it to continue operating a water and sewer utility in Flagler County; and Whether Petitioner's application to increase its water and sewer rates to its customers should be granted.
Findings Of Fact The Utility The Utility, a subsidiary of ITT Community Development Corporation, owns and operates a central water and sewer system serving Palm Coast Community--a planned development of approximately 40 square miles located in Flagler County. Although the development has less than 3,000 occupied homesites, more than 40,000 homesites are planned. (Testimony of Potter; P-2, R-4.) The Water System The water system includes wells, a treatment plant, storage facilities, and distribution mains. There are 13 water supply wells with a flow capability of 3.40 MGD (million gallons per day); present peak flow is 2.00 MGD. The raw water is piped to a central water treatment plant which utilizes a lime- softening process. Present plant peak flows equal the maximum rated capacity: 2.00 MGD. There are two ground storage reservoirs (with a total capacity of 1,300,000 gallons) and two elevated storage tanks (with a total capacity of 850,000 gallons). The water distribution system consists of an extensive network of mains, valves, fire hydrants, and meters used to convey potable water from the treatment plant to customers throughout Palm Coast Community. Although during the test year ending June 28, 1980, the Utility supplied water to an average of 2,191 residential and 80 general service customers, water distribution mains have been constructed to 22,988 building sites. The total water system, as of June 28, 1980, has been constructed at a cost of $17,486,433. (Testimony of Potter; P-2, R-4.) The Sewer System The sewer system includes a collection system, 57 lift stations, a wastewater treatment plant, and effluent disposal facilities. The wastewater plant utilizes an extended aeration process and has a rated hydraulic capacity of 600,000 gallons per day. Effluent is disposed of by spray irrigation on a 65-acre disposal field. Although during the test year, the Utility supplied sewer service to an average of 1,502 residential and 39 general service customers, sewage collection mains have been constructed to 22,988 building sites. As of June 28, 1980, the sewer system has been constructed at a cost of $24,850,962. (Testimony of Potter; P-2, R-4). The Rate Increase Application By its application, the Utility seeks authorization to increase water operating revenues by $170,460 and sewer operating revenues by $106,924. If granted, annual gross water revenues would increase (by approximately 40 percent) to $422,211 and gross sewer revenues would increase (by approximately 40 percent) to $267,194. (Testimony of Deterding; 5-3 P-4, R-2.) As grounds, the Utility contends that during the test year ending June 28, 1980, it suffered an operating loss of $225,430 in its water operations, and a loss of $109,909 in its sewer operations; that it is entitled to a 13.08 percent rate of return on its rate base. (Application for Rate Increase, dated November 3, 1980). II. The Elements of Rate Making In issuing a certificate and setting rates, the Commission must determine: the rate base 2/ ; (2) the cost of providing the utility service, including debt interest, working capital, maintenance, depreciation, tax, and operating expenses; (3) a fair return on the rate base; and (4) the quality of service provided. At hearing, the Utility presented evidence on each of these rate-making elements. For the most part, the Commission did not oppose the Utility's evidence; those matters which were disputed are separately addressed below. Rate Base Rate base represents the Utility's property which provides the services for which rates are charged. There are three issues involving the establishment of rate base: (1) average or year-end rate base. (2) inclusion of cost of a 750,000 gallon water storage tank; and (3) deferral of depreciation on non-used- and-useful plant. Average or Year-End Rate Base At hearing, the Utility asserted that it had experienced extraordinary growth, justifying the utilization of year-end rate base. The Commission disputed this claim of extraordinary growth, and urged the use of a 13-month average. On June 22, 1981, the Utility filed a post-hearing "Notice of Change in the Position of the Applicant," by which it receded from its previous position and agreed that, for purposes of this proceeding, an average rate base should be used. The issue is, therefore, moot and utilization of a 13-month average rate base is accepted. However, the Utility continues to assert that a year-end rate base should be established for "purposes of certification." 3/ Such assertion is rejected as inconsistent with its June 22, 1981, acceptance of average rate base: the acceptance applied to this "proceeding," 4/ and was not limited to rate-making purposes. Moreover, the Utility has not shown why a second rate base, based on year-end figures, should be established. Year-end rate base constitutes a deviation from the standard and preferable method of using a 13-month average; it may only be used under circumstances of unusual or extraordinary growth-- circumstances which the Utility no longer claims exist. (Testimony of Deterding; R-2) Deferral of Depreciation and Amortization The Utility requests authority to defer depreciating non-used-and-useful plant and amortizing contributions-in-aid-of-construction ("CIAC") until such time as the plant or contributions become used and useful. The effect would be to preserve the original cost of the property so it may eventually be recovered from future customers benefitting from its use; because original cost would not have been reduced, rate base would be higher for those future customers. The Commission opposes the requested deferral. Both parties cite language in a previous Commission order (Order No. 7455, Docket No. 760034, In Re: Petition of North Orlando Water and Sewer Corporation) as evidence of existing Commission non-rule policy on deferral of depreciation expense on non-used-and-useful property. The Commission language in that order lends support to the opposing arguments of each party. Even if the policy was stated unequivocally it could not--without record support--establish Commission policy for purposes of this rate proceeding. The Utility's request is rejected because record evidence in this proceeding. The Utility executed a Revenue Agreement with ITT Community Development Corporation on June 27, 1980. Under that agreement, Community Development Corporation, the developer of Palm Coast Community, agreed to pay the Utility--through 1990--an amount sufficient to allow recovery of costs, including depreciation, attributable to utility property installed for unimproved lots. Such utility property is the same non-used-and-useful property for which the utility now seeks to defer depreciation and amortization. Since this revenue agreement allows the Utility to recover from the developer depreciation expenses attributable to non-used-and-useful property, deferral of depreciation--to allow recovery from future customers--is unnecessary. (Testimony of Gregg, Deterding; R2) 5/ Inclusion of Cost of Water Storage Tank The Utility proposes to include in rate base the use-and-useful portion of a 0.75 million gallon elevated storage tank. It was not completed and placed in service until after the test year. Neither was its construction explicitly ordered by government order. However, from an engineering standpoint, it was needed during this test period to maintain minimum water pressure during peak- flow periods and provide adequate flows for fire protection purposes. It now functions as an integral component of the Utility's water system. At hearing, the Commission's accountant testified that 100 percent of the cost of the water storage tank should be removed from the plant-in-service component of rate base because it was not in service during the test year. The parties agreed to his submittal of a post-hearing accounting exhibit showing adjustments resulting from his testimony. However, in his late-filed exhibit (R-2), the accountant took a position which contradicted his testimony at hearing: In this case we feel that consideration of this after test year plant must be given. The utility's used and useful portion of the other storage facilities will increase substantially. In addition this item appears to be an integral component of the plant which was operating during the test year and at present. (R-2.) (Emphasis supplied.) He included proposed schedules which: (1) include the tank as if placed in service during the last month of the test year; (2) include the total cost of the tank including interest capitalized net of the non-used-and-useful portion in calculating average rate base; and (3) show the effect of these adjustments in construction work in progress (CWIP) so that they can be easily identified and not confused with plant that was, in fact, in service by the end of the test year. Notwithstanding this significant change in its accountant's testimony, the Commission continues to advocate 6/ the accountant's earlier position at hearing--one which he has now abandoned. Thus, the Commission argues that: [T]he only correct position in calculating an average rate base is to exclude the after test year plant addition and adjust the used and useful percentage. . .as he [its accountant] originally proposed at the hearing. (Commission's Recommended Order, p. 5) This contention his rejected as inconsistent with the Commission's own accounting and engineering evidence. 7/ It also overlooks the undisputed fact that the storage tank is now operating as an essential component of the water system, and that it will continue to be used during the period in which the new rates will be in effect. The Commission's alternative treatment--as proposed by its accountant's post-hearing exhibit (R-2), is accepted as persuasive. The cost of the storage tank is thus included as CWIP, and is calculated as if placed in service during the last month of the test year; the total cost of the tank, including interest capitalized net of the non-used-and-useful portion, is utilized (Testimony of Gregg, Deterding, Chastain; R-1.) The sewer system rate base proposed by the Utility is not disputed by the Commission and is accepted. The resulting average rate bases for the water and sewer systems are $2,736,279 and $1,044,165, respectively. They are depicted below. WATER RATE BASE (Test Year Ended 6-28-80) Utility Plant in Service $12,397,249 Plant Held for Future Use (8,848,497) Construction Work in Progress 39,097 Accumulated Depreciation (216,405) Contribution-in-Aid-of-Construction (Net of Amortization) (687,787) Working Capital Allowance 35,837 Materials and Supplies 7,785 Income Tax Lag -0- RATE BASE $ 2,736,279 SEWER RATE BASE (Test Year Ended 6-28-80) Utility Plant in Service $18,461,055 Plant Held for Future Use (15,787,481) Construction Work in Progress -0- Accumulated Depreciation (109,729) Contributions-in-Aid-of-Construction (Net of Amortization) (1,551,865) Working Capital Allowance 27,186 Materials and Supplies 4,999 Income Tax tag -0- RATE BASE $ 1,044,145 (Late-filed Exhibit, R-2.) B. Operating Income The parties agree that, during the test year, the Utility had a $130,243 operating loss from its water operations, and a sewer operations. The operating statements are $95,281 operating loss from it depicted below: WATER OPERATING STATEMENT (Test Year Ended 6-28-80) Operating Revenues (Present Rates) $251,751 Operating Revenue Deductions Operation 286,694 Depreciation 75,314 Amortization 954 Taxes Other Than Income 19,032 Income Taxes -0- TOTAL OPERATING EXPENSES $381,994 s Operating Income (Loss) $(130,243) SEWER OPERATING STATEMENT (Test Year Ended 6-28-80) Operating Revenues (Present Rates) $160,270 Operating Revenue Deductions Operation 217,487 Depreciation 21,872 Amortization 767 Taxes Other Than Income 15,425 Income Taxes -0- TOTAL OPERATING EXPENSES $255,551 Operating Income (Loss) $(95,281) Since during the test year, the Utility operated its water and sewer systems at a loss; it received a negative rate of return on its rate base. (Testimony of Gregg, Deterding; Late-Filed Exhibit R-2, P-3, P-4.) Cost of Capital and Fair Rate of Return The only issue between the parties concerning cost of capital to the Utility is whether deferred taxes should be included in its capital structure. At the end of the test year, the Utility's books showed no deferred taxes; however, during the later half of 1980, it changed its accounting treatment for deferred taxes. Applying its new method, deferred taxes at the end of the test year would be $3,137,000--assuming deferred depreciation on non-used-and-useful property is disallowed. The Utility failed to establish the impropriety of applying an accounting method which it will continue to follow in the foreseeable future; it is therefore concluded that the deferred taxes should be calculated as $3,137,000, at zero cost. 8/ The resulting overall cost of capital is 12.29 percent. A reasonable rate of return falls within a range of 11.87 percent to 12.72 percent. It is depicted below: COST OF CAPITAL Weighted Component Common Stock Equity Amount $22,224,497 Weight 42.23 Cost 15.0 percent Cost 6.33 Long Term Debt 27,163,003 51.62 11.5 5.94 Customer Deposits 99,653 .19 8.0 .02 Deferred Taxes 3,137,000 5.96 -0- -0- $52,624,153 100.00 12.29 (Testimony of Kelly, Potter; R-5.) proposed Revenue The Utility seeks increased water revenues of $170,460 and increased sewer revenues of $106,924. Although the parties agree on a base facility rate design, 9/ the Commission disputes proposed charges for fire hydrants and irrigation meters. 10/ Fire Hydrant Charges The Utility presently collects, under contract, a fire hydrant charge of $70 per year per hydrant from two fire districts which serve the area. This method is favored by customers and the fire districts; because the fire districts raise their funds through tax assessments, the customers payments are tax deductable. The Commission argues that the $70 charges do not cover all of the Utility's fire protection costs and that such costs should be recovered through regular service rates. While the $70 charge was shown to be insufficient to cover fire service costs, no reason was provided why the additional funds could not be recovered by increasing charges to the fire districts. This method of paying for fire protection costs is advantageous to the customers. It is likely that the fire service districts would cooperate with the Utility in negotiating fire service charges which are adequate to cover the costs of the service provided. Consequently, it is concluded that the present method of collecting fire service charges should be retained, although the charges should be increased sufficiently to cover the attendant costs to the Utility. (Testimony of Fabelo, Public Witnesses.) Irrigation Meter Charges The Utility proposes a $2.00 base facility charge for irrigation meters, with a $4.50 charge for regular service. The Commission prefers an irrigation meter base facility charge equal to one-half of the base charge of a corresponding regular service meter, assuming both meters are on the same tap to the water main. Since the demand for water that both meters can cumulatively place on the water system is 1.5 times that placed by a regular service meter, the Commission's position is persuasive. 11/ The parties also disputed the base facility customer accounting charges for irrigation meters--the Utility contending that the additional meters impose little additional costs and the Commission asserting that customer accounting charges should be given full weight. The Utility's position is accepted as persuasive. The two meters are usually close together and easily read. Both services are included on one account and one monthly bill covers both. Thus, while the irrigation meter imposes a slight additional accounting cost, it is minimal when compared to the cost imposed by a separate regular service meter. (Testimony of Gregg, Fabelo.) Rate of Return Allowed by Proposed Revenue Adding the requested water revenue increase of $165,633 to the adjusted test-year water operating revenues of $251,751 results in total recommended operating revenues of $417,384. Subtracting test-year operating expenses of $381,994 leaves a net operating income of $35,390--a 1.29 percent return on a water rate base of $2,736,279. Adding the requested sewer revenue increase of $111,751 to the adjusted test-year sewer operating revenues of $160,270 results in total recommended operating revenues of $272,021. Subtracting test-year operating expenses of $255,551 leaves a net operating income of $16,470--a 1.58 percent return on a sewer rate base of $1,044,165. (Testimony of Deterding; R-2) Quality of Service The quality of the water furnished the Utility's customers depends on their location. Customers residing in the area most heavily populated--north of Highway 100--receive satisfactory water service. Their water is treated by the Utility's central lime-softening plant. In contrast, the customers residing in the Seminole Woods area have not received water of comparable quality. Seminole Woods lies in the south extremity of the service area; it consists of approximately eight single-family residences and one duplex. Due to the remote location and slow rate of growth of Seminole Woods, the Utility has not found it practical to interconnect with the central lime-softening plant or build a separate lime-softening plant to serve the area. Instead, the Utility pumps raw water from a nearby well to a temporary facility where it is chlorinated and then conveyed to the residences where it is treated by separate zeolite or "Culligan" water-softening devices. These devices are furnished customers by the Utility without additional charge. The residents of Seminole Woods have frequently received water with excessive chlorine or hydrogen sulfide. The Utility's efforts to monitor the chlorine levels and regularly flush the system have not solved the problems. Seminole Woods customers have repeatedly complained about the quality of their water--its excessive chlorine taste, offensive odor (similar to the smell of rotten eggs), and high sodium content. The water quality is so poor that at least three of the residents have found it undrinkable; they buy bottled water at an additional cost of approximately $20 per month. The Utility's current solution to the problem is to extend mains from the northern area to Seminole Woods. The lines are now under construction and completion is expected "within a year or so." (Tr. 253.) With the exception of the Seminole Woods area, the quality of sewer and water service provided by the Utility is acceptable and has rarely been the subject of complaints. Occasional problems of power outages have been corrected. Neither the water nor the sewer system has been or is now under any governmental citation for non-sewage or water treatment standards. Upon completion of the connecting water mains, it is likely that the residents of Seminole Woods will receive water equal in quality to that enjoyed by other residents of Palm Coast Community. (Testimony of Thomas, Sannartano, Creolino, Potter, Likins.) III. Certificate of Public Convenience and Necessity The Utility has filed with the Commission a map of its existing utility systems, a description of the area served, and all information requested by the Commission concerning its rates and charges. Neither the Commission nor the public objected to the granting of a certificate authorizing it to continue providing water and sewer services in the affected area. (Testimony of Chastain, Members of the Public; Prehearing Statement.)
Recommendation Based on the foregoing findings of fact and conclusions of law, it is RECOMMENDED: That the Utility be granted a certificate to continue operating its water and sewer systems in the areas described, and That it be authorized to file tariffs, consistent with the provisions of this Recommended Order, designed to generate annual gross water revenues of $417,384 and annual gross sewer revenues of $272,021. DONE AND RECOMMENDED this 13th day of August, 1981, in Tallahassee, Florida. R. L. CALEEN, JR. Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 13th day of August, 1981.