DEPARTMENT OF ENVIRONMENTAL REGULATION vs. B. D. TAYLOR AND LANE MOBILE ESTATES, 83-001208 (1983)
Division of Administrative Hearings, Florida Number: 83-001208 Latest Update: Oct. 21, 1983

Findings Of Fact B. D. Taylor, Respondent, is the owner of a wastewater treatment facility near Panama City, Florida, which serves a community of some 125-150 mobile homes at Lane Mobile Home Estates. The facility has a 24,000 gallons per day capacity to provide secondary treatment of wastewater with percolating ponds. It was first permitted in 1971 upon construction and has been in continuous operation since that time. In 1980 Respondent employed the services of a consultant to apply for a renewal of its temporary Permit to operate a wastewater treatment facility. This application stated the temporary operating permit (TOP) was needed to give Respondent time to connect to the regional wastewater treatment facility. The schedule contained in the following paragraph was submitted by Respondent at the time needed to accomplish this objective, Following inspection of the facility, a TOP was issued December 5, 1980 (Exhibit 1), and expired January 1, 1983. TOPs are issued to facilities which do not comply with the requirements for Wastewater treatment. Exhibit 1 contained a schedule of compliance to which Respondent was directed to strictly comply to stop the discharge of pollutants from the property on which the facility is located. These conditions are: Date when preliminary engineering to tie into regional will be complete and notification to DER. July 1, 1981; Date when engineering to tie into regional system will be complete and notification to DER - June 1, 1982; Date construction application will be submitted to phase out present facility - March 1, 1982; Date construction will commence - June 1, 1982; Date construction is to be complete and so certified - October 1, 1982; and Date that wastewater effluent disposal system will be certified "in compliance" to permit - January 1, 1903. None of these conditions or schedules has been met by Respondent. The regional wastewater treatment facility was completed in 1982 and Respondent could have connected to this system in the summer of 1982. This wastewater treatment facility is a potential source of pollution. The holding ponds are bordered by a ditch which is connected to Game Farm Greek, which is classified as Class III waters. The size of Game Farm Creek is such that any discharge of pollution to this body of water would reduce its classification below Class III. On several occasions in the past there have been breaks in the berm surrounding the holding ponds which allow the wastewater in the holding ponds to flow into the ditch and into Game Farm Creek. Even without a break in the berm, wastewater from these holding ponds will enter Game Farm Creek either by percolation or overflow of the holding ponds caused by the inability of the soil to absorb the effluent. On January 28, 1983, this facility was inspected and the results of the inspection were discussed with the operators of the facility. The plant was again inspected on February 8 and February 18, 1983. These inspections disclosed solids were not settling out of the wastewater in the settling tanks; inadequate chlorination of the wastewater was being obtained in the chlorination tanks; samples taken from various points in the system, the ditch along side the holding tanks and in Game Farm Creek, disclosed excess fecal coliform counts; and that very poor treatment was being afforded the wastewater received at the plant as evidence by high levels of total Kejhdal nitrogen and ammonia, high levels of phosphates, high biochemical oxygen demand, and low levels of nitrates and nitrites. In July, 1983, in response to a complaint about odors emanating from the plant, the facility was again inspected. This inspector found the aeration tanks anaerobic, effluent had a strong septic odor, the clarifier was cloudy, the chlorine feeder was empty, no chlorine residual in contact tank, final effluent was cloudy, both ponds were covered with duckweed and small pond was discharging in the roadside ditch (Exhibit 14) Expenses to Petitioner resulting from the inspections intended to bring Respondent in compliance with the requirements for wastewater treatment facilities are $280.32 (Exhibit 9)

Florida Laws (2) 403.087403.088
# 1
L. C. PREVATT, D/B/A RIVERVIEW SPEED WASH, INC. vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 82-000356 (1982)
Division of Administrative Hearings, Florida Number: 82-000356 Latest Update: Oct. 07, 1982

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: Petitioner L. C. Prevatt is the owner and operator of the Riverview Speed Wash, Inc., a coin operated laundry which has been in existence for over ten years. The facility has twelve top load washers, four double load washers, one triple load washer and seven gas dryers. It is open from 7:00 a.m. to 9:00 p.m., seven days a week. The facility is located in a shopping center in space which petitioner rents on a month-by-month basis. The facility utilizes a 0.0075 mgd waste treatment plant with effluent disposal to a county-owned drainage ditch which is connected and discharges to the Alafia River approximately 0.6 miles south of the facility. On or about May 29, 1981, petitioner submitted an application for a temporary operation permit for his Riverview laundry facility. Temporary operation permits are issued by the DER when a facility is not currently meeting State water quality standards and the applicant needs or desires a period of time to bring the facility up to the applicable standards. Here, the petitioner stated on his application that no upgrade of the waste treatment facility was planned. The application further stated that the facility would be connected to an area wide regional waste treatment system when that system became available. After numerous requests for further information from the applicant and various inspections of the facility, the DER issued its notice of intent to deny petitioner's application for a temporary operation permit. Reasons for the intended denial included failure to provide requested background water quality information, failure to provide a proposed water quality standards compliance schedule, failure to provide reasonable assurance that a municipal sewer would be available as an alternative means of disposal and improper and deficient operation and maintenance of the facility. Numerous inspections of the petitioner's facility by personnel from the DER and the Hillsborough County Environmental Protection Commission revealed that the facility was not functional in terms of operating correctly and that the design of the plant was inadequate to meet State water quality standards. Specifically, these inspections revealed that the chlorination equipment was not operational, that the trickling filter was not operational, that the removal rates for BOD and suspended solids were consistently and significantly less than the State standard of 90 percent, that the discharge and effluent were of a milky color and would not meet the State standards for turbidity and color, that the water quality of the drainage ditch was extremely low and that the water quality results were actually worse after going through the existing system. It was determined that the discharge was degrading the quality of the receiving waters and that, even if the petitioner's operational and maintenance problems were solved, the design of the facility is not adequate to assure future compliance with State standards. Petitioner admits that his facility does not currently meet State water quality standards. In mitigation, it is contended that many other laundries in the area also do not meet State standards, that it is not economically feasible to redesign the facility to attain compliance, that he has no land available upon which to discharge effluent and that he would be willing to install a sand filter and did have the permission of the manager (not the owner) of the property to discharge effluent into the parking lot drain ponds. No written evidence of this agreement was adduced and there was no demonstration that such runoff ponds would be able to hold and/or treat effluent from the petitioner's facility. There was also no evidence offered to demonstrate that a municipal or regional sewer system would be available in the near future to serve the laundry facility.

Recommendation Based upon the findings of fact and conclusions of law recited above, it is RECOMMENDED that petitioner's application for a temporary operation permit for Riverview Speed Wash, Inc. be DENIED. Respectfully submitted and entered this 7th day of September, 1982, in Tallahassee, Florida. DIANE D. TREMOR, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 7th day of September, 1982. COPIES FURNISHED: L. C. Prevatt Post Office Box 998 Gibsonton, Florida 33534 William W. Deane, Esquire Assistant General Counsel Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301 Victoria Tschinkel, Secretary Department of Environmental Regulation Twin Towers Office Building 2600 Blair Stone Road Tallahassee, Florida 32301

Florida Laws (1) 403.088
# 2
LOXAHATCHEE RIVER ENVIRONMENTAL CONTROL DISTRICT vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 78-001676 (1978)
Division of Administrative Hearings, Florida Number: 78-001676 Latest Update: Jun. 01, 1979

Findings Of Fact The Petitioner is a special tax district created by special act of the Florida Legislature. Chapter 71-822, Laws of Florida. The district covers approximately seventy-two square miles in northern Palm Beach County and southern Martin County, Florida. Petitioner's purpose is to provide water, sewer, drainage and solid waste services within the district. In conformity with its powers, the Petitioner operates an advanced waste water treatment plant on property which it owns in northern Palm Beach County. Petitioner has secured appropriate permits from DER in order to construct and operate the treatment plant. The treatment plant is among the most advanced in southeastern Florida. It has a four million gallon daily capacity, which could be increased to an eight million gallon capacity. In treating waste water the plant utilizes filtration, disinfection, retention in a holding pond, and discharge into a remote off-site area. The present discharge system is to pump effluent from the retaining pond through a canal or drainage system to a recharge or discharge lake which is located approximately three miles north and west of the treatment plant. This is known as the western discharge system, and was installed at a cost of approximately one million dollars. Due to the large amounts of pumping activity, it is an expensive system to utilize. Through its instant application, the Petitioner is seeking a permit allowing it to discharge effluent on-site. Effluent would flow into percolation ponds that have already been constructed. Effluent would settle in the ponds, and eventually would percolate through the soil. This system would he less expensive to operate than the western discharge system. Petitioner is interested in experimenting with the amount of waste water treatment that can be obtained through action of vegetation in the percolation ponds upon the effluent. Such a natural system, if it operated effectively, could save the Petitioner additional money in treating waste water by reducing the need for chemical treatment. Petitioner's waste water treatment presently results in a discharge of effluent which within some parameters meets even drinking water standards. The Petitioner's system very effectively treats bio-chemical oxygen demand ("bod"), suspended solids, nitrogen, and phosphorus in the effluent. Reports have been submitted by the Petitioner to DER which indicate that the system does not meet DER's standards for advanced waste water treatment. Samples upon which these reports were based were taken at a point in the system before the effluent was subjected to the action of the retention pond and the subsequent bumping into the western discharge system. Samples taken beyond the retention pond indicate that DER's standards are met for "bed", suspended solids, total nitrogen, and total phosphorus. The Intervenor owns property adjacent to the Petitioner's waste water treatment plant. The Intervenor operates a well field and drinking water treatment plant on the property, and provides drinking water to residents of the Town of Jupiter and surrounding communities from the well field. The Intervenor acquired its treatment plant, and surrounding well fields from a private utility company. The Petitioner was aware of the well field when it purchased the property upon which it presently operates its waste water treatment plant. While the Petitioner's plant adequately treats waste water in terms of "bod", suspended solids, total nitrogen, and total phosphorus it does not treat the waste water for heavy metals, pesticides, or viruses. These are common elements found in waste water effluent in the south Florida area. The Petitioner's proposal is to discharge its effluent into on-site ponds. The effluent would then percolate into the ground. The retention ponds are located at a distance from 1200 to 1600 feet from the nearest of the Intervenor's wells. Water which percolates from these ponds would flow directly toward the wells, and would eventually find its way into the wells. The flow from the retention ponds to the wells would be increased due to the draw-down effect that the wells have on the surrounding water table. As water is drawn from the wells, the adjoining water table becomes depressed in the area of the wells, and water from the surrounding area flows more rapidly into the area of the wells. Heavy metals will not be filtered out as a result of retention or percolation. Heavy metals in the effluent would eventually find their way into the Intervenor's well fields. Estimates as to the amount of time that it would take for water from the percolation ponds to reach the wells varied from four months to six years. The longer estimate appears the more reasonable; however, the evidence is conclusive that eventually waters from the percolation ponds would reach the wells, and that heavy metals in the water would not be filtered out. The Petitioner proposes to obviate any problems with heavy metals reaching the well fields by operating testing wells between the percolation ponds and the well fields. If any heavy metals were detected in the ground water, Petitioner would again use the western discharge system rather than the percolation ponds. While this would prevent increased contamination of the wells, contamination that had already reached the test wells would reach the Intervenor's wells. It was suggested that the percolation ponds could be drawn down in order to reverse the flow of ground water back into the percolation ponds, thence to be pumped through the western discharge system. In order to accomplish this, however, the percolation ponds would have to be more than forty feet deep, which they are not. The effect of heavy metals intruding into the Intervenor's water supply could be to increase the cost of treatment, or to render the wells unfit for use. Uncontaminated drinking water supplies are rare in the northern Palm Beach County area, and the expense of finding a new water supply is difficult to calculate.

Florida Laws (2) 120.57120.60
# 3
ROBERT E. MCCUNE AND HERNANDO SSK, LLC vs OUT OF BOUNDS INC., AND DEPARTMENT OF ENVIRONMENTAL PROTECTION, 10-002987 (2010)
Division of Administrative Hearings, Florida Filed:Temple Terrace, Florida Jun. 01, 2010 Number: 10-002987 Latest Update: Mar. 06, 2012

The Issue The issue in this case is whether the Department of Environmental Protection (DEP) should issue a permit to Out of Bounds, Inc. (Out of Bounds, or applicant), to construct, operate, and close a construction and demolition debris disposal facility (C&D facility) in Hernando County.

Findings Of Fact On September 8, 2008, Out of Bounds applied to DEP for a permit to construct, operate, and close an unlined C&D facility on 26 acres located at 29251 Wildlife Lane, Brooksville, Hernando County, Florida, to be known as the Croom C&D Debris Landfill and Recycling Facility. There were four requests by DEP for additional information, which was provided, and the application was complete on September 3, 2009. In 1994, a previous owner of the property was issued a permit to construct, operate, and close an unlined C&D facility on the property. That owner did not proceed with construction, and the permit expired in 1999. The Out of Bounds application was for a new permit, not for the renewal of an existing permit. Robert McCune owns property adjacent to the proposed C&D facility. He and his wife reside on the property, keep horses in stables on the property, and use the property for horseback riding business, which includes hosting public horseback riding events. Hernando SSK was formed by David Belcher and one or more others to continue the business being operated by Paige Cool when she died during this proceeding. The business is conducted on ten acres of property Cool owned approximately one mile west of the proposed C&D facility. Belcher is one of two co-personal representatives of Cool’s estate. Belcher and his wife hold a mortgage on the property. When the estate is finalized, the Belchers plan to assign their mortgage to Hernando SSK. It is not clear who will own the property after the estate is finalized, or how Hernando SSK will be authorized to continue the business on the property. Western pleasure and trail-riding horses are boarded on the Cool property, which is known as At Home Acres. The business also has access to 20 adjoining acres to the east, which are used for grazing. Access to the horseback riding trails in the Withlacoochee State Forest is conveniently located just across Wildlife Lane from the property, to the north. A manager resides in a double-wide trailer on the property, and another trailer and a barn to the east of it are leased out. There is a potable water well on the property, which is the source of drinking water for the manager and lessees. Well Setback In the application process, Out of Bounds disclosed two potable water wells within 500 feet of the proposed landfill disposal area. The application provided that those wells would be converted to non-potable use. Out of Bounds did not disclose the existence of a third potable water well, on property owned by Daniel Knox, which is within 500 feet of the proposed landfill disposal area. When the Knox well was brought to the attention of DEP, Out of Bounds admitted that the well was permitted for potable use but took the position that it was not for potable use because it was not in use, was not connected to a source of electricity, and appeared to be abandoned. Daniel Knox and his brother, Robert Knox, had the Knox well dug and permitted in 1979 in anticipation of using it as the source of potable water for a residence to be built on the property for their parents and sister. The Knoxes have not yet built a residence on the property, but it still is their intention to do so and to use the well as the source of potable water. Since its construction, the well had been maintained and operated periodically using a gasoline-powered generator so that it will be ready for use when needed. During the application process, Out of Bounds also did not disclose the existence of a fourth potable water well within 500 feet of the proposed landfill disposal area on property once owned by Larry Fannin and now owned by his daughter and son-in- law, Robert McCune. The McCune well was permitted and installed in mid-2005 while the sale of the land from Fannin to the McCunes was pending. The intended purpose of the well was to provide potable water for the use of the McCunes when they started to reside on the property. Despite this intent, and unbeknownst to the McCunes, Fannin had the well permitted as an irrigation well. In mid-2008, the McCunes began to reside on their property. At first, they resided in a mobile home. They ran pipes from the well to the mobile home to provide drinking water. Eventually, later in 2008, they began construction of a residence on the property and ran pipes from the well to the house to provide drinking water to the house. The well was being used for drinking water before the Out of Bounds application was complete. (They also use water from the well from time to time for irrigation purposes--i.e., when they host horseback-riding events on weekends, they truck water from the well to their horseback-riding arena to apply to the ground to control dust.) Groundwater flows from the disposal area of the proposed landfill to the west and southwest. The Knox and McCune wells are down-gradient of the groundwater flow from the proposed disposal area. Out of Bounds represented at the hearing that it would accept a permit condition that no C&D debris, but only clean debris, would be disposed within 500 feet of the Knox and McCune wells. See Fla. Admin. Code R. 62-701.200(15)-(16) and (24). However, there was no evidence of new designs, plans, or operations that would be used to meet such a permit condition. Liner and Leachate Collection Existing unlined C&D facilities in the Southwest District report various parameters that exceed groundwater quality standards and criteria. These include arsenic, benzene, iron, aluminum, nitrate, ammonia, vinyl chloride, methylene chloride, 3- and 4-methyl phenols, sulfate, and total dissolved solids (TDS). Arsenic and benzene are primary (health-based) groundwater quality standards. The others are secondary standards that relate to taste, odor, and aesthetics. The likely source of the reported arsenic violations in the Southwest District is wood treated with chromate copper arsenate (CCA). See Fla. Admin. Code R. 62-701.200(11). Out of Bounds proposes to not accept CCA-treated wood and to use a trained “spotter” to exclude CCA-treated wood from the landfill. This is an appropriate measure to prevent arsenic violations, and is now required for C&D facilities. See Fla. Admin. Code R. 62-701.730(7)(d), (8), and (20). It was not clear from the evidence whether the C&D facilities in the Southwest District with arsenic violations accepted CCA-treated wood. Even if they did, the operational plan proposed by Out of Bounds to exclude CCA-treated wood and to use a trained spotter is not a guarantee that no CCA-treated wood will enter the landfill. A C&D facility would not be expected to dispose of material that would result in benzene contamination. The reported benzene violations suggest that unauthorized material contaminated with benzene nonetheless makes its way into C&D facilities in the Southwest District. The evidence was not clear whether a trained spotter was used at those facilities. Whether or not a spotter was used at those facilities, having a trained spotter would not guarantee that no benzene-contaminated material will enter the landfill proposed by Out of Bounds. Out of Bounds suggested that ammonia violations result from C&D facilities accepting yard trash. However, there was no evidence of a connection between acceptance of yard trash and ammonia violations. The operational plan proposed by Out of Bounds to “cover as you go” is the accepted best practice to control hydrogen sulfide odor, which comes from wet drywall. Out of Bounds suggested that its cover plan would prevent any sulfate violations, but there was no evidence to prove it. There was no evidence as to whether the C&D facility proposed by Out of Bounds would be substantially different from the other existing C&D facilities in DEP’s Southwest District. Absent such evidence, Out of Bounds did not provide reasonable assurances that its proposed facility would not cause groundwater quality violations. The site for the C&D facility proposed by Out of Bounds is internally drained. There are no surface waters onsite or within a mile of the site. There was no evidence of a surficial aquifer above the Floridan aquifer. Rainfall entering the Out of Bounds property migrates downward into the Floridan aquifer. Once in the aquifer, there is a horizontal component of groundwater water flow in a generally southwest direction, towards the Knox and McCune wells. Contaminated leachate from the proposed C&D facility would migrate with the groundwater. Out of Bounds suggests that a thick clay layer under the site of its proposed facility would prevent the downward migration of groundwater into the Floridan aquifer. There are several reasons why the clay layer does not provide the reasonable assurance of a liner that contamination from the proposed landfill would not reach the Floridan aquifer. Clay is much more permeable than a geomembrane meeting DEP’s specifications for use as a liner. The clay on the proposed site is on the order of at least a thousand times more permeable. (Out of Bounds appeared to confuse the permeability of such a geomembrane with the allowable permeability of the geosynthetic clay layer or compacted clay layer underlying the geomembrane. Cf. Fla. Admin. Code R. 62-701.730(4)(f).) In the application process, Out of Bounds relied on the clay layer for purposes of sinkhole prevention and mitigation, not for reasonable assurance that no liner was needed. The limestone formation underlying the site is highly variable, with numerous pinnacles; for that reason, the thickness of the clay layer also is highly variable, making it difficult to excavate the proposed landfill with complete assurance that the clay layer would not be penetrated. To provide reasonable assurance for purposes of sinkhole prevention and mitigation, Out of Bounds proposed to leave or create a clay layer at least six feet thick underlying the bottom of the proposed landfill. Because the site is in an area of high recharge to the Floridan aquifer and drains entirely internally, the clay layer alone does not provide reasonable assurance that there will be no downward migration of contaminated groundwater to the Floridan aquifer. Reasonable assurance requires a liner and leachate collection system.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that DEP deny the application for a C&D facility made by Out of Bounds. DONE AND ENTERED this 8th day of December, 2011, in Tallahassee, Leon County, Florida. S J. LAWRENCE JOHNSTON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 8th day of December, 2011. COPIES FURNISHED: Ronda L. Moore, Esquire Department of Environmental Protection 3900 Commonwealth Boulevard, Mail Stop 35 Tallahassee, Florida 32399-3000 John R. Thomas, Esquire Law Office of John R. Thomas, P.A. 233 Third Street North, Suite 101 St. Petersburg, Florida 33701-3818 Timothy W. Weber, Esquire Battaglia, Ross, Dicus & Wein, P.A. Post Office Box 41100 St. Petersburg, Florida 33743-1100 Herschel T. Vinyard, Jr., Secretary Department of Environmental Protection 3900 Commonwealth Boulevard, Mail Stop 35 Tallahassee, Florida 32399-3000 Thomas Beason, General Counsel Department of Environmental Protection 3900 Commonwealth Boulevard, Mail Stop 35 Tallahassee, Florida 32399-3000 Lea Crandall, Agency Clerk Department of Environmental Protection 3900 Commonwealth Boulevard, Mail Stop 35 Tallahassee, Florida 32399-3000

Florida Laws (3) 120.52403.412403.707
# 4
HY KOM DEVELOPMENT COMPANY vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 89-002957 (1989)
Division of Administrative Hearings, Florida Number: 89-002957 Latest Update: Oct. 12, 1992

Findings Of Fact On or about December 28, 1987 Hy Kom filed with the Department an application for a permit to construct a .0126 MGD Advanced Waste Water Treatment Plant on Emerson Point, Snead Island in Manatee County. The proposed waste water treatment plant would discharge effluent into the waters of Terra Ceia Bay in Manatee County. The proposed waste water treatment plant would discharge effluent into the waters of Tampa Bay in Manatee County. The proposed waste water treatment plant would discharge effluent into the waters of Manatee River in Manatee County. The waters of Terra Ceia Bay have been designated Outstanding Florida Waters (OFW) by the Department. On or about April 27, 1989 the Department issued a Notice of Permit Denial concerning Hy Kom's permit application. The parties stipulate the Intervenor, Manasota-88, has standing to intervene as a party Respondent and to object to the issuance of the permit. Petitioner's evidence can best be summarized by what was not submitted. First, the expert witness called to identify the application had not prepared any part of the application or verified any of the studies presented therein. Similarly Petitioner's expert on the proposed treatment plant did not testify that Petitioner was committed to using this plant, or that the construction of the plant and the operation of the plant would comply with statutory and rule requirements. The only witness called by Petitioner to testify to the effect the discharge from the proposed advanced waste water treatment plant would have on the receiving waters was also Respondent's expert; and this witness testified that the effluent discharge from this proposed plant would have an adverse effect on the receiving waters, would seriously degrade the receiving waters as a nursery habitat for both crustacea and fishes endemic to the area, and that no reasonable assurances that this would not happen were ever presented by the Petitioner. This witness further testified that no discharge into these receiving waters would be acceptable not only because of the nitrogen level (which was the most significant reason for denying the permit) but also because even a discharge of absolutely pure water would upset the salinity of the receiving waters at the critical time the receiving waters act as a marine nursery.

Recommendation It is RECOMMENDED that a Final Order be entered denying the application of Hy Kom Development Company, for a permit to construct and operate an advanced waste water treatment facility at Emerson Point, Snead Island, Manatee County, Florida. DONE and ORDERED this _15th_ day of September, 1992 in Tallahassee, Leon County, Florida. COPIES FURNISHED: JAMES W. STARNS ESQ 501 GOODLETTE RD SUITE D-100-24 NAPLES FL 33940 W DOUGLAS BEASON ESQ ASST GENERAL COUNSEL K. N. AYERS Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this _15th_ day of September, 1992. DEPT OF ENVIRONMENTAL REGULATION 2600 BLAIRSTONE RD TALLAHASSEE FL 32399 2400 THOMAS W REESE ESQ 123 EIGHTH ST N ST PETERSBURG FL 33701 DANIEL H THOMPSON ESQ GENERAL COUNSEL DEPT OF ENVIRONMENTAL REGULATION 2600 BLAIRSTONE RD TALLAHASSEE FL 32399 2400 CAROL BROWNER SECRETARY DEPT OF ENVIRONMENTAL REGULATION 2600 BLAIRSTONE RD TALLAHASSEE FL 32399 2400

Florida Laws (1) 403.086
# 5
DEPARTMENT OF ENVIRONMENTAL REGULATION vs. ARNOLD H. PARKER, 79-001985 (1979)
Division of Administrative Hearings, Florida Number: 79-001985 Latest Update: Jan. 24, 1980

The Issue The matter to be resolved by this Recommended Order concerns the Petitioner's Notice of Violation and Order of Corrective Action filed against the Respondent on the subject of alleged violations by the Respondent of the "Florida Safe Drinking Water Act", Sections 403.850 through 403.864, Florida Statutes. Within this complaint document there are six counts constituted of the following allegations: Count I. The Respondent does not continually apply effective disinfection measures to the water distributed to the service connections of the Respondent's water system. Respondent's water system has chlorination equipment installed but a chlorine residual is not continually maintained. This condition has existed since at least February, 1979. These facts show a violation of Rule 17- 22.106(3)(c), Florida Administrative Code. Count II. The Department has not received reports from the Respondent which contain information about the operation and maintenance of the water system. This condition has existed since at least April, 1978. These facts show a violation of Rule 17-22.111(2), Florida Administrative Code. Count III. The Respondent's water system has a daily flow of more than 2,500 gallons per day but less than 0.1 million gallons per day. The operation, maintenance and supervision, if any, of the water system is not performed by a person who has passed an examination that entitled such person to be a certified operator. This condition has existed since at least April, 1978. These facts show a violation of Rule 17-22.107(3)(b), Florida Administrative Code. Count IV. The slab surrounding the well casing has been broken exposing the system to possible contamination. This condition has existed since at least February, 1979. These facts show a violation of Rule 17-22.106(2)(c)2.e., Florida Administrative Code. Count V. The Respondent`s water system has no flow meter for accurately measuring the volume of water distributed by the public water system. This condition has existed since at least February, 1979. These facts show a violation of Rule 17-22.106(3)(g), Florida Administrative Code. Count VI. The Petitioner has incurred costs and expenses in the amount of $57.22 in the course of investigating the case and is entitled to be reimbursed pursuant to Subsection 403.860(3), Florida Statutes.

Findings Of Fact This case is presented for consideration based upon the Notice of Violation and Order of Correction filed by the Secretary of the State of Florida, Department of Environmental Regulation, on August 24, 1979. The action is taken against Arnold H. Parker, an individual who resides in Escambia County, Florida. On September 17, 1979, the Respondent, Parker, by and through his counsel answered the allegations of the Petitioner and requested a Subsection 120.57(1), Florida Statutes, hearing. The request for hearing was granted and on December 6, 1979, in Florida, a formal hearing was held to consider the Petitioner's complaint. (The essential elements of that complaint are reflected in the synopsis reported in the Issue statement of this Recommended Order.) The facts reveal that Daniel C. Walker, an employee of Petitioner, went to Perdido Key, Escambia County, Florida, in February, 1979, for the purpose of inspecting a water system owned and operated by the Respondent and to ascertain the number of service connections associated with the system. When Walker arrived at the location of the Respondent's well, he observed that the above-ground equipment utilized in pumping the water out of the ground was housed in a building. This building had a hole in the roof and the concrete slab surrounding the well casing was broken at the surface allowing for possible contamination by influent. At the time of the inspection a device for introducing chlorine into the extracted water was noted but that device was not connected and no chlorine residual was found in the water system. The water system was not being operated by a certified operator within the meaning of Rule 17-22.107(3)(b), Florida Administrative Code. In addition, the Respondent had not submitted operational reports to the Petitioner since April, 1978. The reports referred to are those reports required by Rule 17- 22.111(2), Florida Administrative Code. While Walker was at the general location of the well in onestion, he observed forty individual lots on which various types of trailers, campers and mobile homes could be found. Walker did not determine if persons were living in these shelters and he does not recall seeing persons in the area of the lots. The witness, Walker, did not observe any restaurant or public food establishment in the area of the well house and lots. On September 25, 1979, Robert Court, another employee of the Petitioner, went to the site of the well house and lots. At that time he counted thirty-two trailers, campers and mobile homes and each of those shelters had a service connection from the well of the Respondent located somewhere on the lot where the shelter was found. The service connection was in the form of a spigot. Court observed several people in the north-east section of the general area which is constituted of the well location and lots. Court returned to the location on November 30, 1979, and in a random survey saw approximately thirty-two trailers, campers and mobile hones. Subsequent to the visits of the employees, the Notice of Violation and Order of Correction was prepared by the enforcement section of the Petitioner and the cost of that preparation was $57.22. The Respondent, Arnold H. Parker, testified in the course of the hearing and his testimony established that there are nine persons who live in the area of the well on a year-round basis and these persons are served by the well during that period of time. Of the nine persons one family, the family of the Respondent, lives in a mobile home and the family is constituted of three persons, the Respondent, his wife and son. In a second mobile home the Respondent's daughter and her husband are found to reside. The final group of persons constituted of the nine full-time residents are the Respondent's daughter, her husband and two children in a third mobile home. Each lot on which the three mobile homes are found is served by a service connection. The remaining lots at the location in question were subdivided approximately two years prior to the hearing date and sold separately with the exception of the three lots where the nine permanent residents reside and two lots where other children of the Respondent resided prior to the February, 1979, inspection by the Petitioner's employee. Respondant sold twenty-four mobile home lots and twelve camper sites to persons other than family members and each of the mobile home lots and camper sites has a service connection to the well. Those persons who use the water system other than the nine permanent residents, use the system from mid-March through mid-September in the calendar year. During that time of usage, there are two families at two separate lots who come down during the week and use the water supply. The number of members in those families was not indicated in the course of the hearing. The balance of the persons using the water supply, excluding the above-mentioned two families and the nine permanent residents, use the shelters for vacation purposes and on the weekend. Some of this latter group would be vacationing in their summer home for a period as long as two weeks. The highest number of persons using the water from the well during the vacation period would be approximately forty persons during holiday weekends in the vacation cycle. From the testimony of the Respondent there would never be more than ten days during the vacation period in which twenty-five or more persons would be utilizing the water supply from the well. The water is brought into the trailers, campers and mobile hones by hoses attached to the spigot service connections and the hoses are removed when the individual owners are not in attendance. The lot owners who are served by the water system of the Respondent pay a fee of $18.00 a year, which the Respondent uses to repair the well pump, for pipe and for the cost of electricity to run the well. The well generating device is a two-horsepower electric pump and the well source is tapped by a two-inch service pipe. A one-half-inch line runs from the main to the service connectors (spigot). After the inspection of February, 1979, the Respondent repaired the broken slab around the well casing and these repairs were made in March or April, 1979. The repairs were depicted in the Respondent's Exhibits 1 and 2 admitted into evidence which are photographs of the well casing after the repair.

Recommendation It is recommended that the action taken by the Petitioner against Respondent pursuant to the Notice of Violation and the Order for Corrective Action be dismissed, to include the Petitioner's claim for costs and expenses. DONE AND ENTERED this 7th day of January, 1980, in Tallahassee, Florida. CHARLES C. ADAMS, Hearing Officer Division of Administrative Hearings Room 101, Collins Building Tallahassee, Florida 32301 (904) 488-9675 COPIES FURNISHED: William Hyde, Esquire Department of Environmental Regulation 2600 Blair Stone Read Tallahassee, Florida 32301 Barne J. Morain, Esquire 113 North Palafox Street Pensacola, Florida 32501

Florida Laws (5) 120.57403.850403.852403.860403.864
# 6
PHILLIP G. PANOS vs DEPARTMENT OF ENVIRONMENTAL REGULATION, 90-000479 (1990)
Division of Administrative Hearings, Florida Filed:Tallahassee, Florida Jan. 25, 1990 Number: 90-000479 Latest Update: Dec. 11, 1990

Findings Of Fact The Petitioner, Phillip G. Panos, recently moved from Michigan to Florida and is now a Florida resident. On December 9, 1989, prior to moving to Florida, he applied to the Respondent, Department of Environmental Regulation for certification as a Class C domestic waste water treatment plant operator. The Respondent is an agency of the State of Florida charged, among other duties, with regulating the certification, the practice standards and the educational standards of Class C domestic waste water treatment plant operators. The Respondent agency reviewed the Petitioner's application and denied it for failure to demonstrate the requisite three years of experience required by the rule cited below. From April, 1974 to June, 1990 the Petitioner was employed at the Chapaton Pumping Station in St. Clair Shores, Macomb, Michigan. The Chapaton Pumping Station duties involved the Petitioner monitoring the distribution of sewage flows, collecting sludge samples, chlorinating the effluent and pumping it into Lake St. Clair. When the Petitioner left the Chapaton Pumping Station, in June of 1990, he held the position of Senior Station Operator II. The Chapaton Pumping Station receives a combination of storm water flow and sanitary sewage flows. It is a pumping and storm water retention facility for combined sewage. The facility provides primary treatment and disinfection for this combined sewage effluent. The effluent is chlorinated and then pumped to nearby Lake St. Clair while the solids that have settled out of the effluent are retained, collected and sent to the Detroit waste water treatment facility for advanced waste treatment. Chapaton is classified by the state of Michigan's Department of Natural Resources as an "industrial/commercial facility". The industrial classification was originated by the U.S. Environmental Protection Agency (EPA) and has been adopted as a designation or classification by both Michigan and Florida. The Petitioner holds an industrial/commercial waste water treatment certification from the state of Michigan in the category of "plain clarification and disinfection." The Petitioner's experience in Michigan is in the area of industrial waste water treatment and does not constitute actual experience in on-site operational control of a domestic waste water treatment plant (that is a sewage treatment plant). The Petitioner's experience in Michigan does not qualify as industrial waste water treatment plant experience, that could be used to meet the actual experience requirement, because the Chapaton plant performs only primary treatment and disinfection. Secondary or advanced waste treatment is performed at the Detroit waste water treatment plant, with which the Petitioner has no experience. In a typical domestic waste water treatment plant in Florida, "primary treatment" involves primary clarification or settling. Primary clarification occurs in a circular or rectangular tank where soluble solids settle out to the bottom of the tank and floating solids are removed by a skimming device. The soluble solids are called sludge. Primary clarification can remove 40% of BOD and suspended solids. It is not a form of advanced treatment or even secondary treatment. At the Chapaton plant, during primary treatment, a minimum of 70% BOD and suspended solids are removed. The sludge is not treated at the Chapaton plant but is pumped to the Detroit waste water treatment plant. Thus Chapaton could not be classified as a domestic waste water treatment plant by Florida standards, since it only provides primary clarification and no secondary or advanced waste water treatment. Secondary treatment consists of two types. Activated sludge or trickling filter treatment. Both types deal with oxygen being introduced to the sludge to achieve stabilization and more settling out of the sludge elements. Since June 18, 1990 the Petitioner has been employed as a waste water treatment plant operator I in a training program at the George L. Lohmeyer Waste water Treatment Plant in Ft. Lauderdale, Florida. In that training program the Petitioner is being trained in all phases of operation of the Lohmeyer plant. It is a 34-million-gallon-per-day (MGD) activated sludge treatment plant. In his duties, the Petitioner monitors the plant treatment processes, takes samples and submits them to the city's laboratory. The Petitioner is capable of testing the samples himself for dissolved oxygen, chlorine and ph. Reports are signed by the regional chief or the regional facilities manager. The Petitioner's present position qualifies as actual, appropriate experience in the operational control of a waste water treatment plant. The Petitioner has accumulated approximately 3-1/2 months of the 12 months of actual experience required for certification as a Class C waste water treatment plant operator, through the exercise of his duties at the Lohmeyer plant. The Petitioner must accumulate 12 months or 2,080 hours of actual experience before he can qualify for the Class C certification. The Petitioner is a high school graduate and has successfully completed Volumes I and II of the California State University correspondence course in waste water treatment, which is included on the Respondent agency's list of approved courses. Petitioner's 3-1/2 months of actual appropriate experience in Ft. Lauderdale, plus his educational background, including the courses taken in California, yield a total of 36 months or 3 years of constructive experience. Petitioner does not yet have the 12 months of actual experience required by the rules but rather, is approximately 8-1/2 months short of the actual experience requirement. Thus, the Petitioner fails to meet the experience requirement necessary for certification as a Class C domestic waste water treatment plant operator at this time, although in approximately 8-1/2 months, he should be able to meet that requirement.

Recommendation Having considered the foregoing findings of fact, conclusions of law, the evidence of record and the candor and demeanor of the witnesses, it is therefore RECOMMENDED: That a Final Order be entered by the Department of Environmental Regulation denying Petitioner's application for certification as a Class C domestic waste water treatment plant operator without prejudice to reapplication at such time as his one year of actual experience at such a treatment facility is completed. DONE and ENTERED this 11 of December, 1990, in Tallahassee, Florida. P. MICHAEL RUFF Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11 day of December, 1990. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 90-479 (The Petitioner filed no proposed findings of fact.) RESPONDENT'S PROPOSED FINDINGS OF FACT 1. - 21. are accepted. COPIES FURNISHED TO: Dale H. Twachtmann, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, Esq. General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Phillip G. Panos 2315 N.W. 115 Drive Coral Springs, FL 33065 Francine M. Ffolkes, Esq. Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400

Florida Laws (1) 120.57
# 7
CHARLES P. PAGE vs SARASOTA COMPANY UTILITIES AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 92-002002 (1992)
Division of Administrative Hearings, Florida Filed:Sarasota, Florida Mar. 27, 1992 Number: 92-002002 Latest Update: Jan. 15, 1993

The Issue Whether Respondent Sarasota County Public Utilities Department (Sarasota County) has provided reasonable assurances pursuant to Rule 17- 555.530(1)(a), Florida Administrative Code, that its proposed water treatment plant will comply with each applicable water quality standard contained in Part III, Chapter 17-550, Florida Administrative Code. Whether Respondent Sarasota County has provided reasonable assurance pursuant to Rule 17-555.530(1)(b), Florida Administrative Code, that its proposed water treatment plant meets adequate engineering design complying with the applicable engineering principles established in Rules 17-555.310 through 17-555.160, Florida Administrative Code.

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant findings of fact are made: STIPULATED FACTS Sarasota County Utilities Department is a department established by Sarasota County, a political subdivision of the State of Florida and operates a public utility department which is charged with meeting, among other things, potable water needs of the residents of Sarasota County. At all times pertinent to the issues herein, HRS was responsible for receiving applications and issuing permits for the construction of water treatment plants and the accompanying well field. Petitioner, Charles P. Page, is a resident of Sarasota County and resides at 259 Glen Oak Road, Venice, Florida. Sarasota County filed an Application for a Water Treatment Plant Construction Permit with HRS seeking to construct a well water collection system and a 12 mgd - electrodialysis treatment plant having an auxiliary power system to provide power for the well field and water treatment plant. Sarasota County has previously obtained a water use permit from the Southwest Florida Water Management District (SWFWMD) #208836.00, restricting Sarasota County to feed water for the water treatment plant to 7,303,000.00 gallons average daily withdrawal and 9,625,000.00 gallons peak monthly withdrawal. Sarasota County has received permits for the eleven (11) production wells from HRS. It was the duty of HRS to review the plans and specifications and all supporting documentation to assure that they address and meet every requirement listed in Rule 17-555, Florida Administrative Code, for the issuance of a construction permit.

Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is, accordingly, RECOMMENDED: That a final order be entered issuing permit No. PATS No. 204307 & WC No. 1591-91-036 to Respondent Sarasota County, as set forth in the Notice of Intent To Issue dated February 20, 1992, provided that the grant of the subject permit shall include the general and specific conditions in the Intent To Issue with the further recommendation that the third required specific condition found on page 1 of the Specific Conditions be modified as follows: Construction of the electrodialysis reversal water treatment plant covered by this permit shall not begin prior to the issuance of a permit as required by State of Florida Department of Environmental Regulation for the EDR concentrate discharge facility. DONE and ENTERED this 21st day of October, 1992, at Tallahassee, Florida. WILLIAM R. CAVE Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 21st day of October, 1992. APPENDIX TO RECOMMENDED ORDER IN CASE NO. 92-2002 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statute, on all of the Proposed Findings of Fact submitted by the parties in this case. Rulings on Proposed Findings of Fact Submitted by the Petitioner 1. The following proposed findings of fact are adopted in substance as modified in the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 1(1); 22(47); 23(48); 24(19-20) 29(49); 38(5); 39(19); 42-43(19,20); and 51(49). 2. Proposed finding(s) of fact 2,3,5,6,7,11,14,15,16,18, 19,20,21,25,26,30,31,35,40,45,46,47,49,and 50 are neither material nor relevant to this proceeding or the conclusion reached in the Recommended Order. Proposed finding(s) of fact 4,8,9,10,12,13,17,27,28,and 41 are rejected as not being supported by competent substantial evidence in the record. Proposed finding(s) of fact 32,33,34,36,37, and 48 are unnecessary. Proposed finding of fact 44 is rejected as not being the "opinion" of the Hearing Officer. The transcript will show that the Hearing Officer was only restating the testimony of Judith Richtar. But see Finding of Fact 49. Rulings on Proposed Findings of Fact Submitted by the Respondent Sarasota County The following proposed findings of fact are adopted in substance as modified if the Recommended Order. The number in parenthesis is the Finding(s) of Fact which so adopts the proposed finding(s) of fact: 1 - 20(1) - 20, respectively); 21(27); 22 - 26(22 - 26, respectively); 27(28); 28(29); 29(31); and 30 - 44(32 - 46, respectively). For proposed findings of fact 45 through 65 see Findings of Fact 51 and 52. Proposed findings of fact 66 through 68 are unnecessary. Rulings on Proposed Findings of Fact Submitted by the Respondent Department of Environmental Regulation The Respondent Department of Environmental Regulation adopted Sarasota County's proposed findings of fact 1 through 44, 63 and 64, and 66 with modification. Therefore, the rulings on the Department's proposed findings of fact would be the same as the previous rulings on Sarasota County's proposed findings of fact adopted by the Department. COPIES FURNISHED: Bruce Wheeler Pitzer, Esquire 546 47th Street Sarasota, FL 34234 William A. Dooley, Esquire Nelson, Hesse, Cyril, et al. 2070 Ringling Blvd. Sarasota, FL 33237 Joseph W. Landers, Esquire Landers & Parsons 310 W. College Avenue, 3rd Floor Tallahassee, FL 32301 W. Douglas Beason, Esquire Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Carol Browner, Secretary Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400 Daniel H. Thompson, General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, FL 32399-2400

Florida Laws (3) 120.57403.861403.862
# 8
MILES REALTY, MARY REILEY, THEODORE CAREY, ET AL. vs. GAR-CON DEVELOPMENT, INC., AND DEPARTMENT OF ENVIRONMENTAL REGULATION, 83-000694 (1983)
Division of Administrative Hearings, Florida Number: 83-000694 Latest Update: Dec. 05, 1983

The Issue Whether Gar-Con's revised application for a permit to construct a sewage plant, and soakage trenches to dispose of the effluent, should be granted?

Findings Of Fact Eight to ten miles south of Melbourne Beach and 8.3 miles north of Sebastian Inlet, Gar-Con plans to develop a parcel of land stretching west from the Atlantic Ocean, across Highway A1A, to the Indian River. Gar-Con expects to build a motel and residential complex complete with tennis courts, parking garage, water treatment plant and the sewage treatment facility for which a construction permit is sought in these proceedings. The sewage treatment plant would be built on a site 480 feet west of Highway A1A and 90 feet south of Gar-Con's northern property line, at an elevation of 11 or 12 feet above mean sea level. Ocean Way Water and Sewer Association, Inc. is to be organized as a nonprofit corporation to own and operate the wastewater treatment facility. The Public Service Commission, through the director of its water and sewer treatment, has taken the position that the proposed "sewer system will fall within the exemption described in Section 367.022(7), Florida Statutes." DER's Composite Exhibit A. PACKAGE PLANT PROPOSED The facility Gar-Con proposes is designed to treat 100,000 gallons of sewage daily, which is the estimated "total flow" (T. 75) the sanitary engineer who designed the system anticipates from the development. Sewage generated by the development would flow to the plant, through a bar rack designed to remove rags and other large objects, and into aeration tanks where, over a 24 hour period, interaction with air and a biological mass would supply oxygen and cause the formation of biological floccules. The flocculant sewage would then move to a clarifier hopper. During its five hour stay there, solids which were not earlier segregated as the sewage moved over a weir into the clarifier, would be precipitated and removed. The clear, residual liquid would be pumped through one of two sand filters (each of which would also have granular activated carbon and be capable of filtering 100,000 gallons daily) into one of two chlorine contact chambers where a gas chlorinator would introduce chlorine for an hour. Under ordinary circumstances, the chlorinated effluent would then be pumped into one of two soakage trenches. The soakage trenches, each designed for use every other week, are to be gravel-filled ditches covered over first with felt paper, then with compacted fill. The gravel would lie at least one foot beneath the surface of the ground in a space ten feet wide and three feet deep stretching the 940 foot length of each soakage trench. Punctured like sieves, two six-inch PVC pipes would run through the gravel, sweating effluent from their pores. There is also a plan to dig a percolation pond or grassed swale five feet deep, 120 feet long and 80 feet wide near the wastewater treatment plant, which could serve as a receptacle for effluent, in case of "a 1:10 year storm or when the filters are down and/or if soakage trenches would need repair." Gar- Con's Exhibit 2-A. It would hold about 100,000 gallons. The solids caught by the weir, those extracted in the clarifying process, and those recovered from backwashing the filters would serve as catalyst for the aeration process as needed. Excess sludge, about 3,000 pounds monthly, would undergo "aerobic digestion," before being removed to Brevard County's Central Disposal Facility on Adamson Road, for disposal there. Gar- Con's Exhibit No. 7. Primary and secondary drinking water standards would be met by the effluent as it left the plant (although the engineer who designed the system would not drink the effluent himself), except that, from time to time, nitrate concentrations might reach 12 milligrams per liter, and except in the "event that a homeowner might put some type of [inorganic toxic or carcinogenic] material into the sewer system." (T. 86) The biological oxygen demand (BOD) would be ten milligrams per liter; suspended solids would probably amount to about five milligrams per liter; pH would probably be slightly under seven; nitrates would average approximately eight milligrams per liter but would "peak out at certain times during the year, for maybe extended periods up to two months, at twelve milligrams per liter," (T. 80); and there would be a chlorine residual after 60 minutes of two milligrams per liter. AMBIENT WATERS There would be no direct discharge to the Atlantic Ocean, Indian River or any other body of surface water, nor would any indirect effect on surface waters be measurable. No body of surface water lies within 500 feet of the site proposed for the plant and soakage trenches. Potable groundwater underlies the site; the groundwater table slopes toward the Atlantic Ocean, 9.5 to 12.5 feet below ground. "[D]uring the traditional rainy season," Gar-Con's Exhibit 2B, Attachment, p.3, the groundwater may rise to within seven feet of the surface. The PVC pipes in the soakage trenches are to be placed two and a half feet deep. As effluent percolated through the sandy soil, there would be "mounding" of the groundwater underneath the soakage trenches, and dispersal in all directions. Surface flow is to be diverted from the soakace trenches so that only rainwater falling directly on them would percolate down through the gravel beds. Taking soil characteristics into account, and assuming a "water table depth" of 20 feet, an engineer retained by Gar-Con predicted that "the maximum expected groundwater rises beneath the east and west trenches are 2.4 and 2.1 feet, respectively under a loading of 100,000 gpd for a period of 7 days." Gar-Con's Exhibit No. 3. The water table depth, "the height, the top of the groundwater from the first restrictive layer," (T. 172), is probably more like 40 feet than 20, which accounts in part for the "conservatism" of the mounding predictions. Under very severe weather conditions (a 100 year storm), groundwater would rise as high as the bottom of the trenches making them unavailable to receive effluent, but the effluent would not be forced above ground. In a 100 year flood, water would be expected to rise to seven feet above mean sea level. Under such conditions, people could be expected to evacuate the area. In a 25 year storm, the system could be expected to continue to function. Groundwater to the north and east of the proposed site was sampled, and the samples were analyzed. The water to the north had 380 milligrams of chlorides per liter and the water to the east had 450 milligrams of chlorides per liter. As it left the proposed treatment plant, the effluent would contain approximately 150 milligrams of chlorides per liter. SOUND AND LIGHT Lights like those used as street lights are to be installed at four places in the wastewater treatment plant. A timer, which can be overridden, would turn the lights on at dusk and off at eleven o'clock at night. The lights would illuminate the plant adequately. Pumps would move sewage to and through the proposed plant. Most of the pump motors would be submerged and unable to be heard. Two electric blowers, a flow meter and a totalizer would also have electrical motors. The blowers and the blower motors are to be equipped with insulated fiberglass covers and the blowers would also have intake and double outlet silencers. Four feet from the plant the noise of the motors would be comparable to that of a home air conditioning unit. At the nearest residence the noise level would scarcely exceed background noise. At hearing, Gar-Con revised its application and agreed to install an emergency generator which would also be encased in insulated housing and is to be equipped with a muffler. AEROSOL AND ODOR Unless the proposed plant loses electric power for 24 hours or longer, no offensive odors would emanate from it. The bar rack and weirs would be regularly hosed down. Against the possibility of a power failure, Gar-Con agreed at hearing to install permanently an emergency generator with sufficient capacity to keep both the wastewater treatment plant and the water treatment plant it plans to build operable. No aerosol drift is foreseen. The surface of the liquid In the aeration tanks would be 1.4 feet below the top of the rim. Walkways four feet wide along the inside perimeters of the aeration holding tanks would prevent dispersal of most of aerosol. A decorative hedge around the treatment plant, which would eventually be 15 feet high, is a final fail-safe. WELLS To the north are two shallow wells within 500 feet of the site proposed for the wastewater treatment plant. Both wells belong to Kel Fox, who wrote Gar-Con that he had no objection to their proposed wastewater treatment facility in light of Gar-Con's agreement to furnish drinking water to existing facilities on his property and reimburse him expenses incurred in disconnecting the two shallow wells. Gar-Con's Exhibit 2E. There is a deep well within 500 feet to the south. DER and Gar-Con have entered into the following stipulation, dated September 2, 1983: Existing Wells. Prior to the operation of its waste water treatment plant, Gar-Con will offer to supply drinking water at a reasonable cost to owners of property on which are located operational or approved shallow drinking water wells that are within 500 feet of Gar-Con's land application site. Gar-Con will make this offer to all such owners known to it prior to the operation of its plant. Gar-Con will further offer to provide reasonable compensation to such owners to disconnect their shallow wells. Gar-Con will endeavor to arrange for provision of drinking water to these owners and the disconnection of those wells prior to the operation of its plant. Future Wells. Should nearby individual (non-corporate) property owners propose to construct shallow drinking wells located within 500 feet of Gar-Con's land application site after Gar-Con begins operation of its waste water treatment plant, Gar-Con also will offer to supply them with drinking water at a reasonable cost and to provide reasonable compensation to them to disconnect those wells. However, Gar-Con shall have no obligation to make any such offer to owners of future wells if sampling of monitoring wells located at or near its external property line indicates that the groundwater meets the primary drinking water standards and, after July 1, 1985, the secondary drinking water standards listed in Florida Administrative Code Rule 17-22.104. Gar-Con agrees to record a master notice of restriction barring future owners of lots within the Ocean Way development, which are owned by Car-Con at the time of permit issuance, from installing shallow drinking water wells on such property or otherwise using the shallow aquifer beneath their property as a source for irrigation or for potable water, so long as use of the proposed sewage disposal system continues, and the Department has not found that this restriction is unnecessary. This restriction, which shall be a covenant running with the land, further shall require future owners to purchase water from Gar-Con or any successor owner of the development's water system if Gar-Con or the successor provides water service. These restrictions also shall be contained in all other appropriate documents of title. In addition, Gar-Con plans to create a non-profit water and sewer association to own and control the development's water and sewer system. Gar-Con will include in the Articles of Incorporation of this association a requirement that all property owners served by the system must be members of the Association. Gar-Con is entitled to a zone of discharge extending to its current property line with the exception that the zone of discharge shall not include the area contained within a 100' radius of Gar-Cons's proposed water supply wells. DER Staff concurs that the above conditions, in conjunction with the sewage treatment and disposal system and the groundwater monitoring program proposed by the applicant, to meet the requirements of Chapter 17-4, F.A.C. will provide reasonable assurance that existing and future off-site and on-site property owners will be protected from any adverse effects that might result from the operation of the proposed sewage treatment disposal system. Petitioner's Exhibit No. 10. There are to be a half dozen monitoring wells to allow sampling of the groundwater at strategic points in the shallow aquifer. NATURAL RESOURCES Turtles nest in the general vicinity but off the site of the proposed project. Construction and operation of the proposed waste water treatment facility would have no impact on the turtles apart from making it possible for more people to live closer to where they nest.

Florida Laws (1) 367.022
# 9
GENERAL DEVELOPMENT CORPORATION vs. DEPARTMENT OF ENVIRONMENTAL REGULATION, 81-000239 (1981)
Division of Administrative Hearings, Florida Number: 81-000239 Latest Update: Dec. 01, 1981

Findings Of Fact Upon consideration of the oral and documentary evidence adduced at the hearing, the following relevant facts are found: Several years prior to1978, petitioner General Development Corporation (GDC) applied to the DER for a dredge and fill permit to remove a plug of land between the Ocean Breeze Waterway and the North Fork of the St. Lucie River. During the course of negotiations for this permit, it was discovered that the North Port St. Lucie Sewage Treatment Plant, owned and operated by General Development Utilities, Inc., a wholly-owned subsidiary of the petitioner, was operating without a permit from the DER and discharging effluent into a ditch which flowed into the Ocean Breeze Waterway. In March of 1978, a temporary operating permit was issued for the sewage treatment plant. In July of 1978, petitioner received from the DER Permit No. 253.123- 1031 to dredge an area approximately 800 feet in length, 90 feet in width and 6 feet in depth in order to connect the Ocean Breeze/Sagamore Waterways to the dead end oxbow of the North Fork of the St. Lucie River. The permit application was given special consideration pursuant to Rule 17-4.28(7), Florida Administrative Code. The purpose for obtaining the permit was to create direct navigable access to the North Fork of the St. Lucie River from thee Ocean Breeze Waterway. The Ocean Breeze Waterway was and is currently connected to the North Fork of the St. Lucie River by a narrow, shallow, meandering creek and lake system. However, there is not a large enough opening to allow the type of navigable access desired by the petitioner for the benefit of 118 lots plotted along the Ocean Breeze and Sagamore Waterways. Among the seven particular or special conditions attached to the dredge and fill permit issued to petitioner was that the earthen plug not be removed until such time as a permanent operational permit was issued for the sewage treatment plant owned and operated by General Development Utilities, Inc. More specifically, petitioner agreed to the following special conditions to the issuance of the dredge and fill permit: "(7) The applicant is aware that the GDC Utilities' sewage plant is providing an unknown quantity of discharge into Ocean Breeze Waterway and that this discharge may be a source of pollution to the receiving body of water unless affirmative steps are taken by the Utilities. The sewage treatment plant is currently operating under a Temporary Operating Permit (TP56-4601). In no case shall the plug at Cove Waterway be removed before an Operation Permit for the STP has been issued by the Department of Environmental Regulation." At time of issuance of the dredge and fill permit, DER personnel considered the quoted special condition number 7 to an integral part of the permit in terms of water quality assurances. General Development Utilities, Inc. has not been able to obtain a permanent operational permit from the DER for its sewage treatment plant which discharges into a ditch that flows into the Ocean Breeze Waterway. Therefore, particular condition number 7 has not been satisfied and petitioner has been unable to proceed with the dredging or removing of the plug under the permit. As a result of the delays in removal of the plug, petitioner has had to repurchase some 41 of the 118 plotted lots. The sewage treatment plant was and is still operating under a temporary permit. General Development Utilities, Inc. has requested a permanent operational permit for the sewage treatment plant and DER has issued a letter of intent to deny such a permit. As a result, General Development Utilities has petitioned DER for site specific alternative criteria pursuant to Rule 17-3.031, Florida Administrative Code. This matter is the subject of a separate proceeding currently being held in abeyance pending a determination of alternative criteria. General Development Utilities, Inc. v. Department of Environmental Regulation, DOAH Case No. 81-177. In September of 1980, petitioner sent a letter to DER requesting that special condition number seven be removed from its dredge and fill Permit No. 253.123-1031. It was intended that this request be considered as a minor modification to the dredge and fill permit. In response, DER's Chief of the Bureau of Permitting, Suzanne P. Walker, informed petitioner by letter dated October 15, 1980, that it was the staff's initial reaction, after a review of the original dredge and fill permit file, that the requirement that the sewage treatment plant obtain a permanent operational permit prior to dredging remain as a condition of the dredge and fill permit. Petitioner was informed that if it wished to pursue the matter further, the project must be reevaluated as a major modification to the dredge and fill permit. A major modification to a permit requires a new permit application and fee and is treated and processed as an initial application for a permit, with the applicant being required to provide reasonable assurances that the water quality standards will not be violated. Upon request for a minor modification, DER simply reviews the file and determines whether the request is obviously environmentally insignificant. After receipt of the letter from Mrs. Walker, petitioner supplied DER with additional water quality data. Based upon this additional data, discussions with DER staff who had been involved with the initial dredge and fill permit and the sewage treatment plant permit, and two days of sampling data collected by DER, DER determined that particular condition number seven was an integral part of the affirmative reasonable water quality assurance provided and should remain a condition of the permit. This determination was communicated to petitioner by letter dated January 7, 1981. The sewage treatment plant discharges treated effluent into a drainage ditch known as C-108. Effluent from the plant first goes into holding or retention ponds. Under its current flow, it takes about forty days for the effluent to be discharged from the plant to C-108 and the Ocean Breeze Waterway. C-108 flows into the Ocean Breeze Waterway, an artificial waterway which is presently connected to the North Fork of the St. Lucie River by a narrow, shallow meandering creek and lake system. The sewage treatment plant currently operates at 300,000 gallons per day but has an authorized capacity to operate at two million gallons per day. It currently contributes approximately two percent of the total daily flow to C-108. The Ocean Breeze Waterway and C-108, independent of the sewage treatment plant, drain approximately 4,000 square acres and produce about 35 percent of the water that will flow into the North Fork. The North Fork is tidal, with four one foot tides per day. The tidal action comprises almost 63 percent of the moving water. At a two million gallons per day discharge, the wastewater plant would be contributing about 12 percent of the water that would be going into the North Fork from the Ocean Breeze Waterway system. In comparison with two adjacent drainage systems, the Ocean Breeze system contributes only about three percent of the fresh water which flows into the North Fork. The dissolved oxygen levels of C-108 are chacteristically below the state standard of five milligrams per liter, primarily due to the seepage of ground water into the canal. Due to man-made alterations and to natural phenomena, the North Fork's dissolved oxygen levels also characteristically fall below state standards. The dissolved oxygen level of the Ocean Breeze Waterway is characteristically above state standards. Higher levels of dissolved oxygen coming from the sewage treatment plant improves the dissolved oxygen levels of the existing system. High levels of nitrogen, phosphate and chlorophyll have been found near the point of discharge. The quality of water in the North Fork is better than in the Ocean Breeze Waterway. It was the opinion of petitioner's experts that no change in dissolved oxygen levels would occur in the Ocean Breeze Waterway or the North Fork if the plug of land between these water bodies were removed. Petitioner's witnesses also opined that the Ocean Breeze/C-108 system was not a source of nutrient enrichment to the North Fork, and that the present creek system provided no water quality benefits in the form of nutrient uptake for the North Fork. It was estimated that, if the plug of land were removed pursuant to the permit, a pollutant placed at the upper end of the Ocean Breeze Waterway would be diluted by 98 percent in 26 hours in lieu of the present 39 hours due to increased flushing. These opinions were based upon analyses by petitioner's witnesses of various samplings and data regarding dissolved oxygen, nutrients and phytoplankton. The respondent's witnesses felt that the poor water quality in the Ocean Breeze Waterway was attributable in large part to the sewage treatment plant discharge and, if the plug of land were removed, the water quality problems would be moved to the North Fork and the St. Lucie River. It was felt that the present creek and lake system -- the narrow circuitous connection presently existing between the canal and the river -- reduces the nutrients which otherwise would flow into the river. These conclusions were based upon DER's own survey, a review of the dredge and fill permit file and a review of the additional data supplied by the petitioner General Development Corporation. No data regarding the water quality of the effluent from the sewage treatment plant was submitted by the petitioner at the time of DER's review of the original application for the dredge and fill permit.

Recommendation Based upon the findings of fact and conclusions of law recited herein, it is RECOMMENDED that the request of General Development Corporation to modify Permit Number 253.123-1031 by removing particular condition number seven be DENIED. Respectfully submitted and entered this 14th day of October, 1981, in Tallahassee, Florida. DIANE D. TREMOR, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 14th day of October, 1981. COPIES FURNISHED: Valerie Fravel Corporate Counsel General Development Corp. 1111 South Bayshore Drive Miami Florida 33131 Alfred J. Malefatto Assistant General Counsel Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301 Honorable Victoria Tschinkel Secretary, Department of Environmental Regulation 2600 Blair Stone Road Tallahassee, Florida 32301

# 10