The Issue The issue in the case is whether the Respondent violated Subsections 489.129(1)(g)2., 489.129(1)(j), 489.129(1)(i), 489.129(1)(m), and 489.129(1)(o), Florida Statutes (2002), as alleged in the Petitioner's Administrative Complaint, and, if so, what penalty should be imposed.
Findings Of Fact The Petitioner is a state agency charged with the licensing and regulation of building contractors pursuant to Chapter 489, Florida Statutes. The Respondent is a Florida State Certified Building Contractor who holds license number CBC053702. On December 9, 2002, Mack Hayes entered into a contract with "McKay Engineering/Construction" to build an addition to the Hayes residence located at 3011 East Deleuil Avenue in Tampa, Florida. Although the contract refers to McKay Engineering/Construction rather than McKay Engineering Services, Inc., subsequent change orders to the contract show the Respondent's license number in the letterhead. In correspondence to the Petitioner, the Respondent also acknowledged that he was the contractor on the Hayes project. The Hayes contract did not contain a statement explaining the consumers' rights under the Construction Industries Recovery Fund. Counsel for the Petitioner, however, stated that Mr. Hayes remains eligible for assistance from the Fund. The original contract price for the construction was $54,700. Change orders created an adjusted price of $57,450. During the course of the construction, Mr. Hayes made four payments to the Respondent totaling $49,000. Not long after the construction commenced in January 2003, Mr. Hayes and his wife became frustrated with the slow pace of the construction. Mr. Hayes originally understood that the work would take about 90 days. Instead, the construction remained uncompleted after nine months. In July 2003, the pace of work on the Hayes' addition slowed substantially and in October, the Respondent ceased work altogether. The Respondent ceased work on the project despite the fact that he had not been fired or otherwise given a reason to cease work. In order to facilitate progress on the construction, Mr. Hayes paid the air conditioning subcontractor $1,836, the electrical subcontractor $1,000, and the stucco subcontractor $800, even though it was the Respondent's responsibility under the parties' contract to pay the subcontractors. The Respondent's construction of the new roof of the residence was of particular concern to Mr. Hayes. The tie-in of new roof framing with the existing roof was misaligned and otherwise improperly installed which caused the new roof to sag. The records of the City of Tampa indicate that the Respondent did not obtain a permit from the City for the roofing work at the Hayes residence. In an attempt to repair the roof, large holes were cut in the ceiling to gain access for cutting some of the rafters. The holes in the ceiling were not repaired by the Respondent. The plywood and other wood used on the unfinished eaves was left exposed to weather for months, which has resulted in water damage to the wood that will necessitate that it be replaced. Mr. Hayes obtained cost estimates from two other contractors to repair the roof, gables, and eaves installed by the Respondent. One estimate was $17,490 (including materials) and the other estimate was $15,550 (without materials). Numerous aspects of the construction project were never started or were started and then abandoned, including the gables and eaves, the door trim and hardware, internal electrical box, attic access, plumbing, and front trim. Mack Hayes paid $2,500 to Ezekial Bain and $2,500 to Drains, Etc. to finish some of this work after the Respondent abandoned the project. Taking into account the adjusted contract price of the construction, the amount paid to the Respondent by Mr. Hayes, the direct costs paid to subcontractors by Mr. Hayes, and the reasonable estimated costs for repair of the roof, gables, and eaves, the total financial damages that the Respondent caused to Mr. Hayes is $17,676. The Petitioner did not present expert testimony regarding the competency of the Respondent as a building contractor. Without such testimony, the record evidence is not sufficient to clearly and convincingly demonstrate that the problems associated with this particular project were due to incompetence. The problems could have been caused solely by the Respondent's mismanagement and misconduct. The Petitioner incurred investigative costs of $817.66 for the investigation and prosecution of this case.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Construction Industry Licensing Board enter a final order requiring: that the Respondent pay financial restitution to the Hayes of $17,676; that the Respondent obtain seven hours of continuing education in the area of Chapter 489, Part I, Florida Statutes, in addition to the hours required for renewal of the Respondent's certification; that the Respondent's license be suspended for two years; and that the Respondent reimburse the Petitioner for its investigative costs of $817.66. DONE AND ENTERED this 18th day of July, 2005, in Tallahassee, Leon County, Florida. S BRAM D. E. CANTER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 18th day of July, 2005. COPIES FURNISHED: Brian Elzweig, Esquire Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202 Curt L. McKay 9726 Timmons Loop Thonotosassa, Florida 33592 Leon Biegalski, General Counsel Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-2202 Tim Vaccaro, Director Construction Industry Licensing Board Department of Business and Professional Regulation Northwood Centre 1940 North Monroe Street Tallahassee, Florida 32399-0792
Findings Of Fact At all times material, Respondent, Stephen M. Oliver, was both a registered roofing contractor, holding license RC 0042579, and a certified building contractor, holding license CB 025099. Both licenses were issued by the Florida Construction Industry Licensing Board. On or about July 3, 1985, Respondent entered into a contract with Betty Davis to remodel her house in Bradenton. The total contract price was $3,600. Work on the Davis job commenced on Wednesday, July 3, 1985, and proceeded on July 4 and 5 and July 9 through 12, 1985, before Respondent applied for and obtained a Manatee County building permit for the job. This is a violation of local law. Respondent was not attempting to avoid obtaining a permit for the work. He was just busy and did not timely get one. The building permit obtained does not reflect that the permit covered installation of an oven range hood. Although part of the contract, that work was not included on Respondent's application for a building permit. No separate mechanical permit was obtained for this work. Respondent willfully and deliberately installed the oven range hood on the Davis job without obtaining the required Manatee County mechanical permit. At all times material, the Board of County Commissioners of Manatee County had adopted the Standard Building Code and Standard Mechanical Code, with accumulated supplements, to govern construction in Manatee County. Under the applicable code provisions, installation of an oven range hood is mechanical work for which a mechanical license and mechanical permit are required. Respondent is not licensed or qualified by the State or by Manatee County to do mechanical work. Respondent willfully and deliberately did the mechanical work on the Davis job, i.e., installation of the oven range hood, without being licensed or qualified to do it and without a mechanical permit. Respondent's work on the Davis job was incompetent and grossly negligent in that some electrical wires were covered over by vinyl siding that Respondent installed without first being covered with protective coating to prevent safety hazards, in violation of the applicable building code. Otherwise, Respondent's workmanship was not the best, but it was not incompetent or grossly negligent. On or about March 22, 1985, Respondent entered into a settlement stipulation in which Respondent admitted to charges of not getting the required building permit for an August 25, 1983, contract until eleven months after work began. Respondent was fined $500 for that offense. Shortly before the final hearing in this case, Respondent entered into a settlement stipulation in which he admitted to charges of: (1) performing a February 18, 1985, contract without obtaining the required permit and inspections; (2) performing a March 6, 1985, contract by October 1, 1985, without having all necessary inspections done; (3) performing a January 22, 1985, contract without having all necessary building inspections performed, without correcting all violations cited during inspections, and falsely swearing by affidavit that the masonry contractor had been paid; and (4) not having the necessary final inspection done after performance of a March 16, 1985, contract. For these offenses, Respondent was fined an additional $1000 and placed on probation through February, 1988.
Recommendation Based on the foregoing Findings Of Fact and Conclusions Of Law, it is recommended that the Construction Industry Licensing Board enter a final order fining Respondent, Stephen M. Oliver, $1500.00. RECOMMENDED this 26th day of March, 1987 in Tallahassee, Florida. J. LAWRENCE JOHNSTON Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 26th day of March, 1987. APPENDIX TO RECOMMENDED ORDER, CASE NO. 86-5035 Respondent filed no proposed findings of fact. Petitioner's proposed findings of fact are accepted and incorporated to the extent necessary. This ruling complies with Section 120.59(2), Florida Statutes (1985). COPIES FURNISHED: G. Vincent Soto, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Fl 32399-0750 Stephen M. Oliver 2423 Manatee Avenue West Bradenton, Fl 33505 Fred Seely Executive Director Construction Industry Licensing Board Post Office Box 2 Jacksonville, Fl 32201 Van Poole Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Fl 32399-0750 Joseph A. Sole, Esquire General Counsel Department of Professional Regulation 130 North Monroe Street Tallahassee, Fl 32399-0750
Findings Of Fact Findings of Fact 1-13 are made based upon the Stipulation of the parties filed on July 10, 1987. Respondent is, and was at all times material to the pending amended administrative complaint, a certified building contractor having been issued license number CB CAO9793 by the Florida Construction Industry Licensing Board. At all times material the pending amended administrative complaint Respondent's certified building contractor license (CB CAO9793) qualified "George E. Longino and Associates, Inc." with the Florida Construction Industry Licensing Board. Respondent is, and was at all times material to the pending amended administrative complaint, a certified air conditioning contractor having been issued license number CA CO24348 by the Florida Construction Industry Licensing Board. At all times material to the pending amended administrative complaint, Respondent's certified air conditioning contractor license (CA CO24348) qualified "George E. Longino and Associates, Inc." with the Florida Construction Industry Licensing Board. Respondent is, and was at all times material to the pending administrative complaint, a registered mechanical contractor having been issued license number PM 0031246 by the Florida Construction Industry Licensing Board. At all times material to the pending administrative complaint, Respondent's mechanical contractor license qualified "J. C. and Sons, Inc." with the Florida Construction Industry Licensing Board. At no time material to the pending amended administrative complaint was Respondent the qualifying agent for "First City Contractors, Inc." as defined by Sections 489.105(4) and 489.119, Florida Statutes. At no time material to the pending amended administrative complaint was Charles L. Crowe registered, certified or otherwise licensed by the Florida Construction Industry Licensing Board. At no time material to the pending amended administrative complaint was "First City Contractor's, Inc." registered, certified or otherwise licensed by the Florida Construction Industry Licensing Board. On or about January 23, 1986, Charles L. Crowe d/b/a First City Contractors, Inc., contracted with Steve Bell to construct a room addition at 3110 Carrevero Drive West, Jacksonville, Florida. The contract price was approximately $25,000. On or about March 10, 1986, the City of Jacksonville, Building and Zoning Inspection Division, issued building permit number 6196 to George E. Longino and Associates, Inc. The above referenced building permit was for the construction of a room addition at the residence of Steve Bell, 3110 Carrevero Drive West, Jacksonville, Florida. The following Findings of Fact are based upon the evidence introduced at formal hearing. In December, 1985, or January, 1986, Charles L. Crowe, sole owner of First City Contractors, Inc., approached Longino and asked him to become a partner in the business and to pull permits and be the qualifying agent for First City Contractors, Inc. Longino advised Crowe that he would not be interested in doing that until he had resolved certain pending problems with his licenses. Specifically, the Construction Industry Licensing Board had filed a disciplinary action against Respondent's licenses and that case had been heard and a Recommended Order entered on October 30, 1985. The Recommended Order was scheduled to be considered by the Construction Industry Licensing Board on January 9, 1986. Longino did agree to pull permits for any job on which he would be paid to supervise the construction. Longino did pull the permit and supervise the construction of a garage addition in Arlington, Jacksonville, Florida, for First City Contractors in January or February, 1986. On January 23, 1986, Charles L. Crowe, doing business as First City Contractors, Inc., entered into a contract with Steve Bell to construct a room addition to a residence located at 3110 Carrevero Drive, Jacksonville, Florida. The contract price was $25,000. Based upon the contract, Crowe asked Longino to use his license number to sign a permit application for the Bell job. Longino used a building permit application form which he had in his truck and filled in the pertinent information on the building permit application. Specifically, Longino filled in the name of the licensed contractor as "First City Contractors, Inc." and signed his name as the licensee with license number CB CA09793. Longino signed the building permit application on or about the last week of January, 1986. Financing was not secured for the Bell job until March, 1986. On March 10, 1986, Crowe used the permit application which had been previously signed by Longino and sent an employee of First City Contractors, Inc., Robert Cumpston, to secure a building permit from the City of Jacksonville for the Bell job. Specifically, permit number 6196 was issued based upon the permit application which had been previously signed by Longino. On February 19, 1986, the Construction Industry Licensing Board entered a Final Order suspending Longino's licenses. Longino received notice of the suspension on February 24, 1986, by certified mail. Longino advised Crowe that his licenses had been suspended within a few days following receipt of the Final Order. Despite the knowledge that Longino's licenses had been suspended, Crowe used the presigned building permit application to secure a building permit for the Bell job on March 10, 1986. Building permit number 6196 was issued to Longino's license number doing business as George E. Longino and Associates, Inc. The name of the business was changed from that which was stated on the building permit application because Longino was not a qualifying agent for First City Contractors, Inc. He was only a qualifying agent for George E. Longino and Associates, Inc. A permit could not be issued to First City Contractors, Inc. using Longino's license number. The Bell job was completed using permit number 6196. Longino did supervise that construction and was present at the site on a daily basis. Permit number 6196 was posted at the site. Despite Longino's statements that he did not know that the permit was issued to his license number, it is found that Longino knew or should have known that permit number 6196 was issued to his license number, doing business as George E. Longino and Associates, Inc. Longino did nothing to remedy the problem even though his licenses had been suspended.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Professional Regulation, Construction Industry Licensing Board, enter a Final Order suspending the licenses of George E. Longino for a period of one (1) year in addition to the previous suspension. DONE and ENTERED this 11th day of August, 1987, in Leon County, Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 11th day of August, 1987. COPIES FURNISHED: Van Poole, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 Fred Seely Executive Director Construction Industry Licensing Board Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 W. Douglas Beason, Esquire Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32399-0750 William Bruce Muench, Esquire 438 East Monroe Street Jacksonville, Florida 32201 =================================================================
The Issue Whether the Respondent committed the violations alleged in the Administrative Complaint, and, if so, the penalty that should be imposed.
Findings Of Fact Based on the oral and documentary evidence presented at the final hearing and on the entire record of this proceeding, the following findings of fact are made: The Department of Business and Professional Regulation is the state agency responsible for investigating and prosecuting complaints involving violations of the requirements of Chapter 489, Part I, Florida Statutes. Sections 489.131(7)(e) and 455.225, Florida Statutes. Pursuant to Section 489.129(1), the Construction Industry Licensing Board ("Board") is the entity responsible for imposing discipline for any of the violations set out in that section. At all times material to this case, Mr. Vega was a certified general contractor operating under a license issued by the Construction Industry Licensing Board, numbered CG C046448. Mr. Vega has been a licensed general contractor in Florida since 1989, and since 1994, he has been the licensed qualifying agent for Group Construction South Florida, Inc. The residence of David M. Hudson, located at 19801 Southwest 84th Avenue, Miami, Dade County, Florida, was severely damaged in August, 1992, by Hurricane Andrew. In a letter dated October 13, 1992, Mr. Hudson, who holds a doctorate in biology and is the laboratory manager for the University of Miami Chemistry Department, proposed to Mr. Vega that he prepare plans for reconstructing the Hudson residence. On December 23, 1992, Mr. Hudson and Mr. Vega executed a contract for construction work to be performed on the Hudson residence. The parties contemplated that Mr. Vega would complete the work in accordance with the drawings and original blueprints prepared by Jose A. Sanchez, a structural engineer, at Mr. Vega's direction and based on preliminary plans approved by Mr. Hudson. Specifically, Mr. Hudson understood that the major elements of construction included in the December 23 contract were elevation of the house from one story to two stories, construction of a new living area on the second floor, and construction of a basement on the first floor to serve as a "bare bones storage area." The contract price specified in the December 23 contract was $146,338.33, with ten percent due upon acceptance of the proposal, ten percent due at completion of each of eight items of construction specified in the contract, and ten percent due upon completion of the project. The eight items of construction specified in the contract were "demolition work, rising work, tie beams, roof, doors & windows, plaster & tile, pool & fence, finish work and paint." On February 1, 1993, Metropolitan Dade County Building and Zoning Information Department issued Permit Number 93119957 to Mr. Vega for the Hudson project. The building permit was based on the original plans for the project submitted by Mr. Vega on January 19, 1993, together with some items that were added to the plans at the county's request. Mr. Vega began work on the project on February 1, 1993, the day the permit was issued. Mr. Vega hired Ruben Armas to act as foreman for the project, and his duties included hiring and supervising day laborers and procuring materials needed for construction. At the time, Mr. Armas was not licensed, registered, or certified by either Dade County or the State of Florida. Mr. Vega had an arrangement with Mr. Armas whereby he paid Mr. Armas periodic advances on a lump sum payment that Mr. Armas was to receive when the Hudson project was complete. Mr. Vega did not deduct FICA or withholding tax from the payments made to Mr. Armas under this arrangement. Mr. Vega dealt directly with Mr. and/or Mrs. Hudson regarding the project, although they would occasionally leave messages for him with Mr. Armas. Mr. Vega directly supervised Mr. Armas and gave him instructions on the work that was to be performed and the way it was to be done. Mr. Vega was routinely at the job site at least two or three times a day to inspect the work that had been done. Mr. Vega was present at the site during the entire time that cement was poured for footings or other structural elements. Mr. Vega arranged for various subcontractors to work on the project, including electricians, plumbers, air conditioning workers, roofers, carpenters, and drywall hangers. On April 14, 1993, a Department investigator conducted an inspection of the Hudson project during a "hurricane task force sweep." When she and the other members of the task force arrived on the job site, she observed Mr. Armas and two other men "inside working," but she did not observe them working or see the type of work they were doing. Mr. Armas walked out to meet the inspector and gave her a card that contained his name and phone numbers and the words "General construction & roof repair." Mr. Armas told the Department investigator that, when she arrived, he was "working on the footing for the elevation of the house." On April 21, 1993, Mr. Vega signed a Cease and Desist Agreement in which he acknowledged that the Department was investigating allegations that he had "engaged in the practice of aiding and abetting unlicensed contractor Ruben Armas." By signing the agreement, Mr. Vega agreed to cease "engaging in this activity," but he did not admit that the Department's allegations were true. The Department investigator was at the Hudson job site on April 14, 1993, for thirty minutes to an hour, during which time Mr. Vega did not appear at the site. This was the only time she was at the job site while work was being done. As the work progressed on the project, everything appeared to be going well, and Mr. Vega felt that he enjoyed a very good working relationship with Mr. and Mrs. Hudson. Mr. Hudson paid Mr. Vega a total of $116,400.00, or eighty percent, of the original contract price of $146,338.33, in ten percent increments as provided in the contract. By check dated December 23, 1992, Mr. Hudson paid the down payment of $14,633.38. By check dated February 5, 1993, Mr. Hudson paid $14,600.00 upon completion of the demolition work. By check dated March 5, 1993, Mr. Hudson paid $14,633.00 upon completion of raising the structure to two stories. By check dated March 24, 1993, Mr. Hudson paid $14,633.00 upon completion of the tie beams. By check dated April 19, 1997, Mr. Hudson paid $14,633.00 upon completion of the roof. By check dated May 13, 1993, Mr. Hudson paid $14,633.00 which should have been paid upon completion of the doors and windows but which he paid even though the installation of the doors and windows was not complete. By check dated June 23,1993, Mr. Hudson paid $12,000.00 of the $14,633.00 draw because, in his opinion, the project was not being completed on schedule. Finally, by check dated July 2, 1993, Mr. Hudson paid $17,000.00 to bring the payments up to the amount consistent with the contract schedule for completion of the pool and fence. In a letter to Mr. Vega dated June 7, 1993, Mr. Hudson stated that he wanted to make "a major change" in the plans. Specifically, Mr. Hudson wanted to eliminate the swimming pool, which he estimated would save $20,000.00 of the $146,633.00 contract price, and use the money saved "to completely finish the downstairs to be a nice guest area," to "install the better quality carpet we want, complete wooden fence, air conditioning in 1st floor, plumbing ~ electric in 1st floor, [and] indoor wooden shutters for all windows." Mr. Hudson went on to state that he wanted certain enumerated appliances, which would cost $4,108.00, and new furniture, which he estimated would cost $6,000.00, for a total of $10,108.00. According to Mr. Hudson's proposal, Mr. Vega should be able to "finish off the 1st floor the way we want it, install the nice carpet and tile, and do all the other jobs previously listed (fence, plumbing, etc., for 1st floor) for about $10,000.00." The basement area which Mr. Hudson wanted to finish as a "nice" living area consisted of approximately 2,000 square feet and had originally been designed as a storage area, with concrete floor and walls. Mr. Vega and Mr. Hudson discussed the proposal and the costs of the changes, but they did not reach an agreement on the cost of the additional work. 3/ Mr. Hudson asked Mr. Vega to leave the job site and cease work on the project on or about July 3, 1993, and Mr. Vega did not perform any work on the Hudson residence after this time. Mr. Hudson terminated Mr. Vega from the project solely because of the dispute with Mr. Vega over the cost of the changes he had requested in his June 7 letter. Mr. Hudson did not complain to Mr. Vega about the quality of the work that had been completed, and, although he thought that the project was getting behind schedule, Mr. Hudson issued a check dated July 2, 1993, which brought the total payments to eighty percent of the original contract price. When Mr. Vega stopped work on the project, the structure contained deviations from the original plans. 4/ Some of the deviations were items shown in the original blueprints which had not been incorporated into the structure; some were items that were not shown in the original blueprints but were incorporated into the structure at the request of, or with the approval of, Mr. and/or Mrs. Hudson; some were deviations in the size of openings to accommodate doors and in the location and size of windows; most were minor deviations in the placement of electrical switches and receptacles or other similar deviations. The construction was, however, generally consistent with the original plans. 5/ There were three items that were significant deviations from the original plans. The most serious deviation concerned the changes made in the dimensions of the structural slab that formed the floor of the second floor balcony off the family room, kitchen, and dining room and the roof of the first floor terrace. The original plans included a second floor balcony with a width of six feet. The Hudsons asked Mr. Vega to increase the width of the balcony, and Mr. Vega called Mr. Sanchez, the structural engineer who had prepared the original plans, and asked if the width of the slab could be increased. Mr. Sanchez approved an extension from the original six feet to eight feet, eight inches, and he advised Mr. Vega of the additional reinforcement that would be needed to accommodate the increased width. On the basis of Mr. Sanchez's approval, Mr. Vega incorporated the additional reinforcement specified by Mr. Sanchez and poured the slab to the requested width of eight feet, eight inches. Even though Mr. Vega consulted a structural engineer, he did not submit revised blueprints to the building department and obtain approval for the structural change before doing the alteration. He was aware that the building code required approval before such a change could be incorporated into a structure and that his actions violated the code. 6/ The second significant deviation from the original plans was Mr. Vega's failure to construct the fireplace shown in the original plans. According to the plans, a fireplace was to be constructed in the living room, on the second floor. Although the roof was completed and the drywall installed, no accommodation had been made for the fireplace in either the wall or the roof. Mr. Vega intended to construct the fireplace and would have done so had he not been told to cease work on the project. The third significant deviation from the original plans concerns the windows installed in the structure. No window permits or product approvals were contained in the permit file for the Hudson project. In addition, some of the windows were not the size specified in the original plans, some were too deep, and some were placed lower than the thirty inch sill height specified in the original plans. Many of the items identified as "deviations" were actually items not shown on the original plans but incorporated into the structure at the request of, or with the approval of, Mr. and/or Mrs. Hudson. Neither the requests for the additional items nor the costs of the items were reduced to writing by Mr. Hudson or Mr. Vega. At the time Mr. Hudson directed him to cease work on the project, Mr. Vega had contracts with subcontractors to provide the labor and materials specified in the original contract. He was prepared to complete the project in accordance with the original plans and for the original contract amount, with adjustments for the extras that had already been incorporated into the project at the request of, or with the approval of, Mr. and/or Mrs. Hudson. He was also prepared to correct all deficiencies and code violations in the structure. After he was terminated from the project, Mr. Vega continued to negotiate with Mr. Hudson's attorney to arrive at an agreement for completion of the project that would be satisfactory to Mr. Hudson. In a proposal submitted to Mr. Hudson's attorney in the fall of 1993, Mr. Vega offered to complete the project in seven weeks in accordance with the original plans, as modified to incorporate the changes and upgrades Mr. Hudson had requested in the June 7 letter and the changes and upgrades that had already been incorporated into the project at the request of, or with the approval of, Mr. and/or Mrs. Hudson. The total price for completion proposed by Mr. Vega was $56,750.00, which included the cost of the upgrades and extras and the $29,572.00 balance owing under the original contract. Mr. Hudson did not accept this proposal. Instead, he eventually hired a contractor named Robert Krieff, who did some work on the project. In February, 1994, Mr. Hudson took over the building permit himself and hired various subcontractors to work on the project. According to Mr. Hudson, in addition to the $116,400.00 he paid Mr. Vega, he has paid approximately $50,000.00 for work done after he terminated Mr. Vega, and he anticipates spending another $35,000.00 before a Certificate of Occupancy is issued. Mr. Hudson paid off a lien on his property for work done pursuant to his contract with Mr. Vega. A Claim of Lien in the amount of $4,712.00 was filed by Luis A. Roman on October 5, 1993, for drywall hung and finished at the Hudson residence under an arrangement with Mr. Vega. Summary of the evidence. The evidence presented by the Department is sufficient to establish that Mr. Vega willfully violated the building code with respect to the alteration of the width of the second floor balcony. Mr. Vega admitted that he knew he was violating the building code when he extended the width of the second floor balcony beyond the width specified in the original blueprints before submitting revised engineering plans to the county and receiving approval to make the alteration. This violation is one of procedure only, however, and there was no competent evidence presented to establish that Mr. Vega failed to include adequate reinforcement to compensate for the additional width prior to pouring the slab or that there were structural problems with the slab. 7/ The evidence presented by the Department is sufficient to establish that Mr. Vega violated the building code because the work completed by Mr. Vega on the Hudson project contained deviations from the original approved plans. 8/ On the other hand, the evidence presented by the Department is sufficient to establish that this violation is a minor one. The Department's experts testified that the construction done on the Hudson residence by Mr. Vega was generally consistent with the approved plans and that it was commonplace for contractors in Dade County to deviate from the approved plans and later submit revised plans for approval. The evidence presented by the Department is sufficient to establish that Mr. Vega did not file product approvals or obtain window permits prior to windows being installed in the Hudson project. The evidence presented by the Department is not sufficient, however, to establish that these omissions on Mr. Vega's part constituted a violation of section 204.2 of the South Florida Building Code, as alleged in the Administrative Complaint. Although there was some testimony that the building code requires that product approvals be filed and window permits obtained before windows are installed, the applicable code and section were not identified by the Department's witnesses or otherwise made a part of the record. Thus, there is no evidence of the precise obligations imposed on Mr. Vega by the code that was applicable at the time of the Hudson project. As a result, it is not possible to determine whether Mr. Vega fulfilled his obligations under the code. The evidence presented by the Department is not sufficient to establish that Mr. Vega assisted Mr. Armas in engaging in the unregistered or uncertified practice of contracting. There is no evidence in the record that Mr. Armas performed any work on the Hudson project that could be performed only by a licensed contractor. 9/ Notwithstanding the opinions stated by the Department's experts, the evidence presented by the Department is not sufficient to establish that Mr. Vega is guilty of incompetence or misconduct in the practice of contracting as a result of the work done on the Hudson project. The evidence presented by the Department is sufficient to establish that Mr. Hudson suffered financial loss in the amount of $4,712.00, which is the amount Mr. Hudson paid to clear the lien placed on his property by Luis A. Roman. Although this loss is attributable to Mr. Vega's failure to pay Mr. Roman for hanging and finishing drywall in the Hudson residence, the evidence presented by the Department is not sufficient to establish that Mr. Hudson suffered financial loss as a result of the violation with which Mr. Vega was charged and of which he was proven guilty.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Construction Industry Licensing Board issue a Final Order dismissing Counts I and III of its Administrative Complaint, finding that Gonzalo Vega is guilty of violating section 489.129(1)(d), Florida Statutes (1993), and imposing an administrative fine in the amount of $1,000.00. DONE AND ENTERED this 3rd day of July, 1997, in Tallahassee, Leon County, Florida. PATRICIA HART MALONO Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 3rd day of July, 1997.
The Issue The issue presented for decision herein is whether or not Respondent's certified general contractor's license should be revoked, suspended, or otherwise disciplined based on conduct set forth in two Administrative Complaints filed herein dated March 14 and July 19, 1984.
Findings Of Fact Based upon my observation of the witnesses and their demeanor while testifying, documentary evidence received and the entire record compiled herein, I hereby make the following relevant factual findings. At all times material hereto, Respondent was a certified general contractor in Florida and has been issued license number CGC 015834. 3/ (Petitioner's Exhibit 1) Petitioner is an agency of the State of Florida responsible for enforcing the provisions of Chapter 489, Florida Statutes, relating to the imposition of licensure standards and standards for the practice of contracting. During times material hereto, Respondent was a full-time employee of the Metropolitan Dade County Aviation Authority. At no time during his employment with the authority did Respondent advise the Dade County Aviation Authority that he was performing work outside the scope of his employment while on County time. When confronted with the results of an investigation undertaken by the Dade County Attorney's Office in June of 1983 with regard to his (Respondent's) possible violation of the Code of Metropolitan Dade County, Respondent resigned from his position with the County. (Tr. pages 101-102) DOAH CASE NO. 84-1298 During late February, 1983, Albert Kairy contracted with an unlicensed contractor for the closure of a carport at his residence located in North Miami, Florida. After observing Respondent's classified advertisement in a local flier, Kairy contacted Respondent with regard to preparing necessary blueprints for the enclosure. Kairy contracted with Respondent to prepare both the blueprints and to supervise the activities of the unlicensed contractor. The contract amount was $400. On February 25, 1983, Kairy received an owner/builder permit for the carport enclosure from the City of North Miami. (Tr. pages 7-10, 93) Subsequently, problems began to develop with work performed by the unlicensed contractor and Respondent persuaded Kairy to dismiss that individual and to retain him as the contractor. On March 7, 1983, Respondent entered into a contract with Kairy to construct a room addition to the residence. (Petitioner's Exhibit 2) The project was to be completed pursuant to plans and specifications approved by the City of North Miami. The contract called for a bedroom addition; an additional bathroom and a utility room. The contract included extending the carport wall approximately 101 feet. The contract price was $14,500 which included an advance of $2,500. On March 12, 1983, Respondent entered into a second construction contract with Kairy. (Petitioner's Exhibit 3, Tr. 19) The contract price was $15,000. Except for the increase in the contract price, Kairy was led to believe that the terms and conditions of the second contract were substantially similar to the contract previously executed by the parties on March 7, 1983. However, Respondent reduced the extension of the carport wall to 10 feet and Respondent did not inform Kairy of this reduction. (Tr. page 48) The contract called for draw payments as follows: $4,000 as a downpayment/advance; $3,000 upon completion of slab and block walls; $1,500 upon completion of piping and tie-columns; $2,500 upon completion of partition and drywall; $3,000 upon completion of the roof, and $1,000 upon completion of the job. (Petitioner's Exhibit 3) Respondent subsequently applied for a permit from the City of North Miami. The City of North Miami denied Respondent's application because Respondent failed to comply with the Dade County licensing requirements. (Tr. pages 21-22) Although Respondent acted in the capacity of a general contractor, he (Respondent) requested that Kairy obtain a owner/builder permit. Upon applying for the owner/builder permit, the City cancelled the original permit for the carport enclosure. (Tr. page 94) Kairy obtained the owner/builder permit pursuant to Respondent's assurances the permit would be properly transferred to Respondent's contracting license. The City provided Kairy with a "hold harmless letter" for Respondent to execute. (Petitioner's Exhibit 4) Upon presentation of that letter by Kairy to Respondent, Respondent refused to execute the "hold harmless letter." (Tr. pages 22-24) Subsequently, Kairy and Respondent executed an addendum to the construction contract. The addendum involved changing the enclosures roof structure from shingle to barrel tile. This change involved a price difference of $1,950 and increased the total contract price to $16,950. (Petitioner's Exhibit 5, Tr. pages 31-32) The addendum was executed after completion of the tie-beam and tie- column portion of the construction project. Pursuant to the terms and conditions of the March 12, 1983 construction contract, Kairy provided Respondent with the following amounts: $4,000 as an advance/downpayment on March 21, 1983; ($2,500 under the March 7 contract plus an additional $1,500); $3,000 upon completion of the slab and block work; $400 for preparation of the original set of plans; $500 toward tinted windows; $1,500 upon completion of the tie-beam and tie- column; $1,500 as an advance on the barrel tile roof; and $1,500 as an advance upon the completion of the roofs. (Petitioner's Exhibit 6) Kairy paid Respondent a total of $12,400 on the total contract price of $16,950 or approximately 73 percent of the contract price. Kairy timely remitted to Respondent installment payments for the slab and block work, tie- beam and tie-columns and advanced Respondent $3,000 towards completion of the roof. During April, 1983, Respondent commenced construction for enclosing the roof structure. Respondent ceased all construction activity upon being informed (by Kairy) that he would no longer pay Respondent in cash. (Tr. page 44) Respondent refused to accept payment in any form other than cash and offered no explanation, reason or excuse to Kairy for the cessation of work on this project. Kairy offered several reasons for his refusal to pay contract installments in cash. First, Respondent refused to execute the hold harmless letter provided by the City of North Miami and Respondent failed to properly supervise the construction activities by, among other things, disappearing from the project for a period of approximately three weeks. Finally, Respondent requested additional advances on the contract while the project was not progressing as scheduled. (Tr. pages 28, 44-46) Respondent did not return to the construction site after Kairy refused cash payments. On July 20, 1983, Respondent's roofing subcontractor filed a claim of lien against Kairy's property in the amount of $1,210. (Petitioner's Exhibit 8) Respondent has failed to satisfy the claim of lien and Kairy is in the process of satisfying that claim. (.Tr. page 54) Respondent also failed to pay an electrical subcontractor for services provided in the amount of $965. (Petitioner's Exhibit 7) Again, Kairy is currently in the process of satisfying that debt and Respondent refuses to honor that obligation. (Tr. 57) Kairy reimbursed the plumbing subcontractor in the amount of $675 after Respondent's personal check was returned due to insufficient funds. (Tr. page 62 and Petitioner's Exhibit 9) On April 1, 1983, the City of North Miami Building Department inspected the foundation and slab. On April 18, 1983, the Building Department inspected the tie-beam and columns. On May 6, 1983, the City of North Miami Building Department performed a tin-cap inspection on the enclosure roof. The City of North Miami Building Department estimated the actual construction completed when Respondent left the project and determined that it was approximately 70 percent complete. Completed construction included the slab, foundation, walls and tie-beam. Little interior construction work had been performed and drywall and partition walls were only partially complete. Kairy has either expended or will be required to expend the following sums in connection with the contract with Respondent: $12,400 - the amount paid directly to Respondent; $1,210 - the amount of the roofer's lien; $965 representing the amount owed to the electrician; and $675 representing the amount Kairy paid the plumbing subcontractor for a total of $15,250. 4/ Although Respondent completed approximately 70 percent of the actual construction, Kairy will correspondingly be required to expend approximately 90 percent of the contract price over and above monies paid to Respondent to complete this project. DOAH CASE NO. 84-3202 On May 12, 1983, the City of Miramar issued William Borden an owner/builder permit for the construction of a four-bedroom, three-bath home to be located in Miramar, Florida. (Petitioner's Exhibit 8) Between May and October, 1983, the Bordens performed the site preparation necessary for pouring the building's foundation and slab. After observing Respondent's classified advertisement in a local flier, the Bordens contacted Respondent with regard to the construction of their home. (Tr. page 16) On November 11, 1983, Respondent contracted with the Bordens to provide certain contracting services relative to the construction of their home. The Bordens contracted Respondent to pour the foundation and slab, perform the block work, frame and pour the tie-beam and tie-columns. (Petitioner's Exhibit 3, Tr. pages 18-20) The Bordens were to complete all of remaining construction of their home) The contract price was approximately $16,810. On October 17, 1983, the City of Miramar issued William Borden an owner/builder permit. (Petitioner's Exhibit 7) William Borden was to install the rough plumbing prior to Respondent pouring the foundation and slab. (Tr. 33) Due to certain time constraints, Respondent offered to install the rough plumbing. On October 25, 1983, Respondent received $475 from the Bordens toward installation of the rough plumbing. Respondent failed to subcontract the installation of the rough plumbing and failed to obtain the necessary building permit. On November 8, 1983, the Bordens provided Respondent an additional $470 representing final payment for installation of the rough plumbing. (Petitioner's Exhibit 4) On November 1, 1983, Mr. Bill Lafferty, chief building and mechanical inspector for the City of Miramar, performed an inspection of the rough plumbing work performed for the Bordens by Respondent. Lafferty determined that Respondent had failed to install the rough plumbing in accordance with provisions of the South Florida Building Code as adopted by the Broward County Code. As a consequence, Lafferty required Respondent to remove and reinstall the rough plumbing in accordance with applicable building code provisions. On November 7, 1983, Lafferty reinspected and approved the rough plumbing as reinstalled by Respondent. (Tr. pages 51-55) Respondent reinstalled rough plumbing at the Borden residence during the first week of November, 1983. Respondent did not obtain a building permit prior to reinstalling the rough plumbing. On November 16, 1983, the City of Miramar levied against Respondent a fee totalling $163.45. Part of that levy included $63.45 for renewal of the building permit and reinspection fee, and the remaining $100 represented a fine against Respondent for failing to properly obtain a building permit. (Tr. pages 58, 64 and Petitioner's Exhibit 7) On November 10, 1983, Salvatore Jenco, structural building inspector for the City of Miramar Building Department, inspected and approved the footing slab for the Borden residence. Subsequently, Respondent poured the concrete slab and foundation. Respondent did not obtain the requisite building permit prior to proceeding with construction. Respondent could not properly proceed with construction pursuant to William Borden's owner/builder permit. On November 11, 1983, inspector Jenco reinspected the concrete slab and foundation as poured by Respondent. As a result of that inspection, Jenco ordered all construction activities to be stopped at the Borden project. Specifically, Respondent materially deviated from the architect's plans and specifications by failing to pour a monolithic (continuous) slab and foundation for the Borden residence. As result of that deviation, the structural integrity of the building was compromised. (Tr. pages 71-73) Construction activity at the Borden residence was halted approximately three weeks while the Borden's architect developed a new set of blueprints. After the City approved the revised blueprints, Respondent began laying blocks and framing the tie-beam. Subsequently, Respondent requested Sunshine Concrete Company to commence pouring the tie-beam. The concrete company requested payment in cash due to the fact that Respondent had previously tendered a check to Sunshine Concrete Company which was returned due to insufficient funds. When informed of the concrete company's demands, the Respondent ordered the company to cease pouring the tie-beam. Upon being informed the tie-beam required a continuous pour, Respondent left the construction site and the Bordens were required to directly reimburse the concrete company. Respondent abandoned the project and has not returned to the construction site. Respondent owes the Bordens approximately $4,696 in reimbursed expenses. (Tr. pages 40-42) Respondent's Defense In DOAH Case No. 84-1298, Respondent did not offer any testimony to refute or otherwise rebut the allegations set forth in the Administrative Complaint. Respondent refused to be placed under oath when he made statements as to his position in Case No. 84-3202.
Recommendation Based upon the foregoing findings of fact and conclusions of law, it is RECOMMENDED that Respondent's certified general contractor's license be suspended for a period of two (2) years. Additionally, Respondent shall pay to the Construction Industry Licensing Board an administrative fine in the amount of $2,500. However, if Respondent provides the Construction Industry Licensing Board with sufficient evidence indicating settlement and satisfaction of the existing disputes between Mr. Albert Kairy and Mr. and Mrs. William Borden, the suspension shall be reduced to one (1) year after which time it is recommended that his license be reinstated. RECOMMENDED this 8th day of May, 1985, in Tallahassee, Florida. JAMES E. BRADWELL Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32399-1550 (904) 488-9675 FILED with the Clerk of the Division of Administrative Hearings this 9th day of May, 1985.