The Issue The issue addressed in this proceeding is whether Respondents should be disciplined for violating provisions of Chapters 381, 386 and 489, Florida Statutes, governing septic tank installation and licensure.
Findings Of Fact Respondent, Susan Burkett, is registered with the Department as a septic tank contractor. She is registered to provide such contracting services under the name U.S.A. Septic Tank Company. Respondent, Ron Burkett, is married to Susan Burkett. She employs her husband in her septic tank business. In the past, Ron Burkett, has done business as Working Man Septic Tank. Neither Ron Burkett nor Working Man Septic Tank have ever been registered septic tank contractors. Mr. Burkett was previously disciplined for the unregistered practice of septic tank contracting. However, there was no non-hearsay evidence presented in this case which demonstrated that Mr. Burkett continues to perform unregistered septic tank work. Likewise there was no substantive evidence which demonstrated that Susan Burkett aided her husband in practicing as an unregistered septic tank contractor. Around March 29, 1995, U.S.A. Septic Tank was hired by Architectural Trends, Inc. to install an on-site 1500 gallon septic tank system for $1500.00. Respondent, Ron Burkett, dug the hole for the septic tank. The septic tank was delivered to the site and was actually placed in the ground by another company. The placement of the tank was difficult because of the layout of the structures on the lot and the soft sandy soil of the lot. Neither Respondent was present when the septic tank was placed in the hole. The company who placed the tank in the ground placed the tank backwards. Additionally, at some point in the process from the tanks supplier to its placement in the hole dug by Mr. Burkett the tank was cracked. For reasons not established by the evidence, the contractor contracted with the company who installed the tank to re-install a new tank and complete additional sewage work necessitated by the tanks elevation. The contractor paid $5081.00 for the second company's work. However, the evidence did not show that either Respondent walked off the job. Likewise, the evidence did not show that either Respondent was negligent in the installation of the tank or caused their employer any monetary harm. This lack of evidence was caused by the fact that the Respondents' employer for the job who had personal knowledge of the facts, could not be found and, therefore, did not testify at the hearing. Given the facts of this case, the Administrative Complaint against Respondents should be dismissed.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law it is, accordingly, RECOMMENDED, that the Department dismiss the Administrative Complaint. DONE and ENTERED this 23rd day of October, 1996, in Tallahassee, Leon County, Florida. DIANNE CLEAVINGER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 23rd day of October, 1996. COPIES FURNISHED: Ron Ringo, Esquire Department of Health and Rehabilitative Services 160 Governmental Center Pensacola, FL 32501 Susan Burkett U.S.A. Septic Tank Company Working Man Post Office Box 3648 Pensacola, FL 32516 Gregory D. Venz, Agency Clerk Department of Health and Rehabilitative Services Building 7, Suite 204-X 1317 Winewood Boulevard Tallahassee, FL 32399-0700 Richard Doran, Esquire Department of Health and Rehabilitative Services Building 7, Room 204 1317 Winewood Boulevard Tallahassee, FL 32399-0700
The Issue The issue is whether Respondent should approve Petitioner's application for a septic tank contractor registration, pursuant to Chapter 489, Florida Statutes.
Findings Of Fact Respondent granted Petitioner a septic tank contracting registration on or about January 8, 1990. On August 23, 1993, Respondent's predecessor served Petitioner with an Administrative Complaint. Said complaint alleged that Petitioner was guilty of committing the following violations: (a) violating Rule 10D-6.075(4)(m), Florida Administrative Code, by pumping a septic tank without a valid operating permit, after receiving notice that his company's operating permit had expired; and (b) violating Rule 10D-6.075(4)(n), Florida Administrative Code, by improperly disposing of septage. The complaint proposed a $1000 fine and revocation Petitioner septic tank contractor registration and authorization. The complaint advised Petitioner of his right to request an administrative hearing pursuant to Chapter 120, Florida Statutes. Petitioner did not request a hearing. On November 18, 1993, Respondent's predecessor entered a final order, case number 93-0038S, revoking Petitioner's registration and authorization to provide septic tank contracting services and imposing a fine in the amount of $1,000. Petitioner made the last payment on his administrative fine on February 10, 1995. On February 22, 1996, Petitioner submitted the instant application for septic tank contractor registration. Respondent denied Petitioner's application by letter dated March 13, 1996. The basis of Respondent's denial was Petitioner's failure to meet the minimum registration eligibility requirements as set forth in Chapter 10D-6, Florida Administrative Code. The letter cited Rule 10D-6.072(3)(d), Florida Administrative Code, which prohibits a person from being eligible to take the registration examination if he or she has had a septic tank contractor registration revoked by Respondent within the last five years.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is recommended that Respondent enter a final order denying Petitioner's application for septic tank contractor registration. DONE AND RECOMMENDED this 22nd day of July, 1997, in Tallahassee, Leon County, Florida. SUZANNE F. HOOD Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (904) 488-9675 SUNCOM 278-9675 Fax Filing (904) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 22nd day of July, 1997. COPIES FURNISHED: David A. West, Esquire Department of Health 1000 Northeast 16th Avenue, Box 3 Gainesville, Florida 32601 Wayne Carroll, Esquire 4010 Newberry Road, Suite A Gainesville, Florida 32607 Gregory D. Venz, Agency Clerk Department of Children and Family Services Building 2, Room 204 1317 Winewood Boulevard Tallahassee, Florida 32399-0700 Pete Peterson, Esquire Department of Health Building 6, Room 102-E 1317 Winewood Boulevard Tallahassee, Florida 32399-0700 Dr. James Howell, Secretary Department of Health Building 6, Room 306 1317 Winewood Boulevard Tallahassee, Florida 32399-0700
The Issue The issue in this case is whether Petitioner failed to obtain a permit for abandoning an on-site sewage treatment and disposal system septic tank, and failed to notify Respondent so that Respondent could inspect the system prior to abandonment, in violation of Section 386.0065, Florida Statutes (1997), and, if so, whether Petitioner should pay a $500 fine. (All Chapter and Section references are to Florida Statutes (1997) unless otherwise stated.)
Findings Of Fact Respondent is the state agency responsible for issuing citations under Chapter 386 and is the licensing authority for Petitioner. The Osceola County Health Department (the "Department") is an agency of Respondent. All Pro Services ("All Pro") practices septic tank contracting in Osceola, Orange, and Seminole counties. All Pro is a Florida corporation wholly-owned by Mr. Wayne H. Crotty. Mr. Crotty is licensed in the state as a septic contractor pursuant to Chapter 386. Mr. Crotty has been in the septic tank business for over 25 years. He has extensive experience in septic tank repair and contracting. Mr. Crotty also has had experience in the rule-making process conducted by Respondent pursuant to Florida Administrative Code Chapter 10D-6. He has participated in various committees and held offices in the Florida Septic Tank Association. (Unless otherwise stated, all references to rules are to rules promulgated in the Florida Administrative Code in effect on the date of this Recommended Order.) In the summer of 1996, Petitioner submitted an application to the Department for a repair permit. Petitioner sought to install a standard drainfield utilizing gravity fall from the existing septic tank of a mobile home owner who used the mobile home facility as a day-care center. The existing drainfield was antiquated, clogged, and had ceased disposing effluent properly. Petitioner made arrangements for the day-care center to refrain from using water or sewage for a period of hours so that the drainfield could be repaired. The application came to the attention of Mr. Thomas Franklin Wolf, Director of the Department's Environmental Health Section. Mr. Wolf did not accept the site evaluation in the application. He chose to perform his own evaluation of the repair site. When Mr. Wolf performed a site evaluation, he placed the seasonal high water table two inches higher than the high water table stated by Petitioner in the application for a repair permit. As a result, Mr. Wolf issued the permit at an elevation that would have required either the use of a pump system or elevated plumbing lines in the existing septic tank to meet the higher elevation deemed necessary by Mr. Wolf. The higher elevation established in the permit could be accommodated in either of two ways. The plumbing underneath the mobile home, along with the septic tank, could be raised. Alternatively, a new pump, and other equipment meeting the requirements of Chapter 10D-6, could be installed. The repair permit issued by Mr. Wolf contemplated the use of a new pump chamber complete with alarm. Pumps fail, are problematic, and are expensive. A conventional gravity-fed drainfield line is preferable, whenever feasible, to the use of a pump chamber system and is less expensive. Petitioner determined that the plumbing and septic tank could be elevated to meet the higher elevation requirements thereby avoiding the need for a pump system and its increased cost. This lower-cost alternative satisfied the requirements of Chapter 10D-6 for a septic tank drainfield. Based on past experience, Mr. Crotty believed he could obtain the Department's approval of this alternative to the pump chamber requirements of the permit. The Department had no objection to an alternative that achieved the higher elevation requirement with a gravity-fed system. One risk associated with Petitioner's alternative was that the existing septic tank might not withstand the rigors of being excavated and raised and could break during the repair process. After conferring with the homeowner about the matter, Petitioner proceeded to elevate the existing plumbing lines and septic tank. Petitioner began excavation and removed the lid from the existing septic tank. Petitioner then determined that it would not be feasible to lift the tank up and reinstall it at the higher elevation due to the age and style of the tank. Petitioner determined that the best way to proceed was to abandon the old tank and to install a new tank at the higher elevation. Petitioner replaced the existing septic tank without obtaining a separate abandonment permit. Petitioner did not need a separate abandonment permit. The repair permit was inclusive of the abandonment of the existing tank. In a previous repair effort for another customer, Petitioner broke the existing septic tank while attempting to elevate the tank to a higher location. The prior incident led to a disagreement between Petitioner and the Department over whether a separate abandonment permit was required for replacing a tank in the course of a repair. Petitioner wrote a certified letter to the Department and Department's counsel memorializing an understanding reached during discussions with Department representatives. Any requirement for a separate abandonment permit in the course of a repair was tabled pending further review by the state health office in Tallahassee. The letter further stated Petitioner's understanding that under Chapter 10D-65, the replacement of an existing tank was provided for through a repair permit, and that no separate abandonment permit is necessary for an abandonment which occurs in conjunction with a repair effort. The letter was received by Mr. Wolf on behalf of the Department. In response, the Department specifically informed Petitioner that the replacement of an existing tank is provided for through the repair permit. Mr. Wolf never retracted this position in his dealings with Petitioner. At about the same time, the state health office, through its acting Health Officer for Environmental Health, issued an interoffice memorandum advising every district administrator in the state that a separate abandonment permit is not required when an existing tank is abandoned during repair. The interoffice memorandum stated, in relevant part: This addresses permitting procedures when a septic tank is abandoned in conjunction with a system repair. Since the repair and tank abandonment inspections can be conducted at the same time, a separate permit and fee is not required if a tank is abandoned in conjunction with a repair permit. The repair permit should specify the abandonment requirements from s. 10D-6.053, F.A.C., and the requirements to have the abandonment inspected. If an additional inspection visit is required for either the repair or abandonment, the unit should charge the $25.00 re-inspection fee. Respondent's memorandum served as the Department's official interpretation of its rules relating to abandonment procedures. The memorandum made a separate abandonment permit unnecessary because the repair permit "is inclusive of the abandonment if the abandonment is necessary." The repair permit in this case suffices as an abandonment permit. Petitioner relied upon the representations of Mr. Wolf personally as well as the Department memorandum of February 18, 1996. Based upon Department policy, Petitioner was not required to amend its permit application to seek specific approval for abandonment of the existing tank, because the tank was being abandoned in conjunction with a repair permit. Petitioner pumped out, ruptured, and demolished the old septic tank with the exception of the inlet end wall and the sidewall closest to the tank. Petitioner left intact the latter portions of the old septic tank for inspection purposes and for stabilization. Petitioner placed the lids and the broken pieces of concrete from the tank alongside the new septic tank that was installed. Mr. Crotty requested an inspection by the Department. Inspector Garner arrived on the scene with a standard probe. The probe is a tool useful for inspecting on-site sewage disposal systems. Mr. Crotty informed Mr. Garner that Petitioner had abandoned the old tank and replaced it with a new one. Mr. Crotty took Mr. Garner over to the site and specifically pointed out the remaining sidewall of the old tank and the lids piled up on-site and remaining from the old tank. Mr. Garner inspected the repairs and satisfied himself that Petitioner had installed a new septic tank in the place of the old tank and had done it in a way that would allow gravity feeding to the new drainfield. The repairs dispensed with the need for a pump and were accomplished at a lower cost to the customer. After the inspection on August 13, 1998, and a subsequent review on August 14, Inspector Garner approved the installation by Petitioner. The approval specifically approved the use of a gravity-fed line rather than the use of the pump contemplated in the permit. The approval constituted the "construction final" approval for the septic system that was repaired. Rule 10D-6 does not specify when the inspection for an abandonment of a septic tank in conjunction with a repair is to occur. Nor does it say anything about requesting an inspection before the tank is filled with sand or other suitable material and covered. It was Inspector Garner's practice, and the unwritten policy of the Department, to conduct inspections of damaged septic tanks at the same time the Department inspected repair constructions. The practice of the Department in such an inspection was to inspect the abandoned tank after it had been pumped and the bottom ruptured, but before a new tank was installed. According to Department practice, the inspection of an abandonment in conjunction with a repair must determine that the tank had been pumped and that the bottom of the tank had been opened or ruptured or collapsed to prevent the tank from retaining water. The inspection can only occur after the tank has been pumped out, opened, ruptured or collapsed. Inspector Garner arrived for the inspection after abandonment of the old tank. Mr. Garner does not dispute that Petitioner abandoned the old tank, but maintains that the abandonment was accomplished without proper notification to the Department. Mr. Garner approved the construction, but recorded x- marks on the approval form adjacent to a box for abandonments and next to "tank pumped" and "tank flushed and filled." Mr. Garner also recorded on the form under "explanation of violations" a notation that the old septic tank "was abandoned without any inspection of [sic] verification." The promulgated rules of the Department and Respondent do not require an inspection before an abandoned tank is filled with sand, or other suitable material, and covered. It was the Department's unwritten policy, evidenced by its practice, to insist that inspection of the abandoned septic tank occurred before the tank is actually crushed. The promulgated rules of Seminole and Orange counties do not require inspection prior to abandonment of an existing tank. The unwritten policies of Seminole and Orange counties deviate from those of the Department. The Seminole County Health Department ("Seminole") also received the Department's interpretive memorandum regarding abandonment of septic tanks in conjunction with repairs. Seminole concluded that abandonment inspections should be conducted simultaneously with the final inspection for repairs. At that point, the old septic tank is already ruptured and filled with sand. Seminole adopted the practice of inspecting abandoned septic systems with a probe to verify the pump-out and the rupturing of the old tank. It is the same type probe used by Mr. Garner and the Department. The probe allows a department employee to verify all of the requirements of Rule 10D-6.053 for abandonment. The Orange County Health Department ("Orange County") also received the interpretive memorandum concerning abandonment of septic tanks in the course of repair procedures. By the time the memo was received, however, it was already the practice of Orange County not to require a separate abandonment permit for an abandonment as part of a repair. In Orange County, inspectors permitted abandonment inspections to occur at the point where the tank was already collapsed and covered with sand. The inspection was accomplished with the use of a probe.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is, therefore: RECOMMENDED that Respondent enter a final order finding Petitioner not guilty of the allegations against it and dismissing the citations. DONE AND ENTERED this 24th day of November, 1998, in Tallahassee, Leon County, Florida. DANIEL MANRY Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 24th day of November, 1998. COPIES FURNISHED: Marya Reynolds Latson Marion County Health Department Post Office Box 2408 Ocala, Florida 34478-2408 Stephen D. Milbrath, Esquire Allen, Dyer, Doppelt, Milbrath and Gilchrist, P.A. Post Office Box 3791 Orlando, Florida 32802-3791 Dr. James Howell, Secretary Department of Health 1317 Winewood Boulevard Building 6, Room 306 Tallahassee, Florida 32399-0700 Pete Peterson Department of Health 2020 Capital Circle, Southeast Bin A 02 Tallahassee, Florida 32399-1703
The Issue At issue in DOAH Case No. 04-4333 is whether Respondent committed the two violations of Florida Administrative Code Rule 64E-6.022 alleged in the citation issued on September 29, 2004, and, if so, whether the imposition of a $1,000.00 fine was properly imposed. At issue in DOAH Case No. 05-0695 is whether Respondent committed the three violations alleged in the Amended Administrative Complaint issued on February 21, 2005, and, if so, whether his septic tank contractor registration should be revoked or some lesser penalty imposed.
Findings Of Fact The Department is the state agency charged with enforcing the statutory provisions pertaining to the practice of septic tank contracting in Florida pursuant to Chapter 489, Part III, and Section 381.0065, Florida Statutes (2004). At all times relevant to this proceeding, Respondent Matt Beebe, was a registered septic tank contractor, having been issued registration number SR0971283, and was the qualifying contractor for his business, Southern Sanitation, Inc. ("Southern Sanitation"), having been issued registration number SA0970864. On June 7, 2001, Mr. Beebe was cited for installing a septic system without a permit, in violation of Florida Administrative Code Rule 64E-6.022, and paid a fine of $500.00 without contest. At all times relevant to this proceeding, Mr. Beebe also operated a septage disposal service business under the Southern Sanitation name, having been issued operating permit number 11-QN-0054. Improper Septage Disposal and Sanitary Nuisance On September 29, 2004, Kenneth Rech, the Department's environmental health and engineering director for Collier County, received a telephone complaint that a Southern Sanitation septage hauling truck had been seen emptying its contents onto a vacant lot at 295 Brandy Lane in Naples. Mr. Rech and his assistant, James Miller, drove out to the location to investigate the complaint. When he arrived at the location, Mr. Rech first spoke to the complainant, who lived across the street from the vacant lot. The complainant estimated that the Southern Sanitation truck left the lot about 20 minutes before Mr. Rech arrived. Mr. Rech and Mr. Miller investigated the site. Mr. Rech described the area containing the dumped contents of the truck as a low-lying wetland. The property was about ten acres in size. The owner kept horses on the lot. Mr. Rech testified that there was a strong smell of septage, though the dumped contents were light gray in color. Raw septage is generally black. Based on the smell, Mr. Rech concluded that the dumped contents included septage mixed with some other material. Mr. Rech telephoned Erin Kurbec to meet him at the dump site. Ms. Kurbec is a Department employee responsible for oversight of septage hauling and disposal businesses. Ms. Kurbec in turn phoned Mr. Beebe and asked him to come to the site. Mr. Rech testified that Mr. Beebe was "very agitated" when he arrived at the dump site, calling Ms. Kurbec a "liar," and protesting that the Department did not have the right to ask for his company's hauling logs. Because of Mr. Beebe's aggressive behavior, Mr. Rech phoned to request a Sheriff's deputy to come to the site. Mr. Beebe conceded that he was somewhat agitated because Ms. Kubec asked him to come to the site, but would not tell him why she wanted to see his truck. She would only say that it was a "spot check," which Mr. Beebe did not believe. By the time the Sheriff's deputy arrived, the situation had calmed down. Mr. Beebe told Mr. Rech that he had dumped approximately 3,000 gallons of "drillers' mud" on the site. Drillers' mud, or bentonite clay, is a colloidal clay sold under various trade names that forms a slick slurry, or gel, when water is added. The appearance of the material dumped at the site was consistent with that of drillers' mud. Mr. Beebe testified that the owner of the vacant lot asked him to dump the drillers' mud to fill in a low-lying, hard to reach area of the property. The liquid-like consistency of the drillers' mud made it ideal for filling this difficult portion of the property. Mr. Beebe's testimony as to having permission to dump materials on the property is credited. Mr. Rech took two samples of the dumped material from a pooled area about six inches deep. He used sterile sample equipment and containers. Because Mr. Beebe had alerted him to the possibility that there could be horse manure under the dumped material, Mr. Rech was careful to scoop the contents from the top of the dumped material. Mr. Rech provided one of the samples to Mr. Beebe to allow Mr. Beebe to have a laboratory of his choice analyze the material. Mr. Rech sent the other sample to the Department's Tampa laboratory, which found the sample to contain a fecal coliform count of 4,800 colonies per gram. The laboratory's report was stamped with the disclosure stating, "Sample does not meet the following NELAC requirements: 1) exceeds 6 hr. hold time; 2) this matrix is not certified under NELAC." NELAC is the National Environmental Laboratory Accreditation Conference, a voluntary association of state and federal agencies, the purpose of which is to establish and promote mutually acceptable performance standards for the operation of environmental laboratories. NELAC certifies environmental laboratories such as the Department's Tampa facility, which was not certified for solid matrices such as the sample provided by Mr. Rech. Dr. Philip Amuso is the director of the Department's Tampa laboratory. Dr. Amuso testified as to the testing procedures and the disclosure statement included on the laboratory report. He concluded that neither of the disclosures affected the validity of the fecal coliform count found in the sample. Dr. Amuso testified that the applicable testing standard calls for a sample to be analyzed for fecal coliform within six hours of the sample collection time. The sample in question was not tested within six hours. However, Dr. Amuso testified that the longer a sample is held, the lower the fecal coliform count will be, because the fecal coliform colonies tend to die off over time. Thus, Dr. Amuso testified that the fecal coliform count in the sample was likely understated, due to the failure to analyze the sample within six hours. Dr. Amuso testified that his laboratory chose to classify the sample as solid. The Tampa laboratory was required to note on its report that it is not NELAC-certified for solid matrices. However, Dr. Amuso testified that the classification of the sample had no impact on the analysis performed or the validity of the result. He explained that the laboratory could have classified the sample as a non-potable liquid, a matrix for which the Tampa laboratory is NELAC-certified, and the same analysis would have been performed and would have yielded the same result. Mr. Beebe forwarded his sample of the dumped material to Sanders Laboratories, Inc. ("Sanders"), a private environmental testing service. The Sanders laboratory classified the sample as a non-potable liquid and performed its analysis within six hours of the sample's collection. The Sanders laboratory report dated September 30, 2004, found the fecal coliform count to be 1,600,000 colonies per 100 milliliters. Placed in comparable terms to the Tampa laboratory's report, this sample showed a fecal coliform count of 16,000 colonies per gram, or about three times higher than the Tampa laboratory's sample. Dr. Amuso attributed this higher reading to the fact that Sanders ran its test within six hours of collection. Dr. Amuso testified that the fecal coliform count of 4,800 colonies per gram found in the Tampa laboratory's sample constituted "pretty significant" contamination. Mr. Rech testified that a count of 4,800 colonies per gram is about one-half of the count found in raw, untreated septage from a septic tank, and that such a count is "bad" in terms of public health significance. Mr. Rech testified that the fecal coliform count in the Sanders sample was "in the range" for raw untreated septage. Mr. Rech stated that the laboratory analyses led to the conclusion that there was a substantial amount of untreated septage mixed with the drillers' mud in the dumped materials. He concluded there was more septage than could reasonably be attributed to residue from a previous dump of septage in Mr. Beebe's truck. He added that it would be impossible to clean the tank of a septage disposal truck sufficiently to prevent fecal contamination of a subsequent non-septage load. Mr. Beebe conceded that Mr. Rech told him that he should not use a septage hauling truck for any other kind of load, especially where that load would be dumped on the ground. Before leaving the dump site on September 29, 2004, Mr. Rech and Ms. Kurbec handed Mr. Beebe the citation for failure to properly treat or dispose of septage and the creation or maintenance of a sanitary nuisance. The citation directed Mr. Beebe to pay a fine of $500.00 for each of the two violations. Mr. Rech testified that he and Ms. Kurbec were able to conclude from their on-site observations that Mr. Beebe had improperly disposed of septage and had created a sanitary nuisance. Mr. Rech stated that the subsequent laboratory analysis served to confirm those conclusions. Mr. Rech testified that untreated septage consists of human waste containing high levels of fecal coliform and viruses, bacteria, and parasites that cause a wide range of gastrointestinal and neurological conditions in humans. Mr. Rech stated that untreated septage dumped anywhere other than at a properly regulated disposal site constitutes a public health nuisance. He noted that the materials were dumped by Mr. Beebe within roughly 100 feet of residential drinking water wells. Mr. Beebe admitted that he dumped the contents of his disposal truck on the vacant lot, though he denied that it contained septage. He theorized that the high fecal coliform counts in the laboratory analyses were caused by animal manure beneath the drillers' mud that he dumped on the property. Dr. Amuso conceded that no testing had been performed to establish the ambient level of coliform on the property, and further conceded that the laboratory tests do not distinguish human from animal feces in measuring the coliform count. However, as noted above, Mr. Rech knew that there were animals on the property and carefully took his sample from the top of the dumped material. Mr. Rech testified that the strong smell of septage, and the high coliform count found by the subsequent laboratory analyses left no doubt that untreated human waste had been dumped on the property by Mr. Beebe. The Department established, by clear and convincing evidence, that Mr. Beebe dumped a mixture of drillers' mud and untreated septage on the lot at 295 Brandy Lane in Naples. Holding Tank On or before January 6, 2005, Mr. Beebe placed a 900-gallon domestic wastewater holding tank into a pre-dug hole at the newly built residence of Edward Ehlen at 616 Crescent Street on Marco Island. Mr. Beebe did not dig the hole, nor did he connect the holding tank to Mr. Ehlen's house. Mr. Ehlen testified that he contracted with the City of Marco Island in July 2004 to connect his new residence, an $800,000 house, to the city sewer system. The connection was to be completed no later than November 2004, when Mr. Ehlen and his family expected to take occupancy of the house. The city did not complete the connection and, therefore, allowed Mr. Ehlen to install a holding tank to be used until the sewer connection was completed. After the holding tank was installed, the city inspected the tank and gave Mr. Ehlen a temporary certificate of occupancy. On January 6, 2005, after Mr. Ehlen and his family had moved into their house, the Department discovered that the Ehlen home was using a holding tank to collect its wastewater. On January 7, 2005, the Department issued to Mr. Ehlen an "Official Notice to Correct and Abate a Sanitary Nuisance," finding that Mr. Ehlen was in violation of "Florida Statutes Chapters 381 and 386" because "plumbing discharge from your home is connected to a sewage holding tank which has not been permitted or inspected by this department." The Notice also provided, in relevant part: You are hereby directed to correct this condition by complying with all the conditions listed below. Apply for a "temporary" Holding Tank permit by close of business on Monday, January 10, 2005. [This permit will be valid for a maximum of 120 days, Permit fee is $185.00] Apply for an abandonment permit for the temporary holding tank by close of business Monday, January 10, 2005. [This permit will be valid for a maximum of 120 days. Complete tank removal will be required within 10 days of hook up to public sewer. Permit fee is $40.00] Have a licensed septic contractor excavate the holding tank for inspection of all connections and seals by this department by Wednesday, January 12, 2005. Sign and maintain a pump-out agreement with a licensed septage hauler until the temporary holding tank is properly abandoned and inspected by this department. Provide a copy of this agreement to the department by Wednesday, January 12, 2005. [Minimum required pump-out frequency to be every other day]. Complete hookup to Marco Island Utilities sewer system within 120 days of receipt of this notice. Failure to comply may result in administrative and/or civil enforcement action, including administrative fines of up to $500 per day per violation of law. On January 12, 2005, the Department issued a 120-day temporary permit to Mr. Ehlen for his holding tank. Also on January 12, 2005, Mr. Ehlen signed a contract with Southern Sanitation pursuant to which Mr. Beebe's company agreed to pump out the holding tank three times per week. Mr. Beebe conceded that he did not obtain a permit from the Health Department before he placed the holding tank in the hole on Mr. Ehlen's property. Mr. Beebe relied on Mr. Ehlen's statement that the City of Marco Island had approved the installation of the holding tank. Florida Administrative Code Rule 64E-6.0101(7) provides that a construction permit must be obtained before the placement or installation of any holding tank. The Department established, by clear and convincing evidence, that Mr. Beebe placed a 900-gallon domestic wastewater holding tank into a pre-dug hole at the Ehlen's residence without obtaining a Department permit. Mr. Beebe's good faith belief that Mr. Ehlen had obtained approval for the placement of the tank is noted as a mitigating factor, but cannot operate as a defense for a registered septic tank contractor's admitted failure to confirm the status of any permit with the Department prior to commencing work on the project. Collection and Hauling Log Mr. Beebe's annual operating permit from the Department authorizes him to pump septage from septic tanks and holding tanks and haul it to an approved treatment site for disposal and treatment. Florida Administrative Code Rule 64E-6.010(7)(e) requires a septage hauler to maintain a collection and hauling log "at the treatment site or at the main business location" and to retain that log for a period of five years. The rule lists the following items for inclusion in the log: Date of septage or water collection; Address of collection; Indicate whether the point of collection is a residence or business and if a business, the type of business; Estimated volume, in gallons, of septage or water transported; Receipts for lime or other materials used for treatment; Location of the approved treatment facility; Date and time of discharge to the treatment facility; and Acknowledgement from treatment facility of receipt of septage or waste. On September 29, 2004, the date on which the Department investigated Mr. Beebe's dumping of drillers' mud and sewage on the lot at 295 Brandy Lane in Naples, the Department requested that Mr. Beebe provide his septage collection and hauling log. On September 30, 2004, Mr. Beebe faxed to the Department a single-page, typed document titled, "RE: Southern Sanitation, Inc. Truck Log for Trucks 1 and 2." The document stated that on September 29, 2004, "Truck #1" transported 3,000 gallons of "Well Drillers Mud" from Southern Well Drillers Services drilling site and disposed of it at 295 Brandy Lane. The document stated that "Truck #2" did not haul materials on September 29, 2004. Mr. Rech testified that this document did not satisfy the rule criteria for collection and hauling logs. He noted that this was not a log kept by the drivers of the trucks, but merely a statement from Mr. Beebe attesting to what the trucks had hauled on a single day. Mr. Rech also pointed out that the Department had inspected and authorized Mr. Beebe to haul septage in two trucks identified by their vehicle identification numbers, but that Mr. Beebe's single-page "log" provided no information specifically identifying the trucks in question. On February 3, 2005, the Department sent a letter to Mr. Beebe requesting that he produce, among other documentation, "your original collection and hauling logs for all domestic sewage and food establishment sludge and/or septage you collected and disposed of from January 1, 2004 through February 2, 2005." On February 11, 2005, Mr. Beebe responded to the Department's request, providing copies of "Septic Receiving Logs" maintained by the North County Water Reclamation Facility ("NCWRF"), the Collier County wastewater facility at which Mr. Beebe disposed of his loads. There were log pages for January through June 2004, and October through December 2004. The logs included the dates of disposal, the number of gallons and type of waste in the load (septic or grease), and the signature of the Southern Sanitation driver who dropped off the load. On March 8, 2005, Mr. Beebe submitted to the Department supplemental information covering January 2005. It includes a typed "Pump Job List" for January 2005, prepared on March 3, 2005. The list contains dates, addresses, and approximate gallons collected, including eight entries for pumping out Mr. Ehlen's holding tank. Individual trucks were not identified on this list. The supplemental information also included an NCWRF Septic Receiving Log for January 2005. Mr. Beebe testified that the Department had never asked him for an accounting during the eight years he has operated his business and that the Department did so in this case only after he contested the allegations in the Brandy Lane dumping case. Mr. Beebe appeared to believe that the Department was acting punitively in requesting documents that Mr. Beebe, as the owner of a permitted septage disposal business, was required to keep. Mr. Beebe did not contest the apparent fact that he did not keep collection and hauling logs for his trucks in the normal course of business. Such documentation as he provided was insufficiently detailed to meet the requirements of Florida Administrative Code Rule 64E-6.010(7)(e), and in some instances was cobbled together well after the fact in order to provide the Department with some documentation of Southern Sanitation's activities. Mr. Rech testified that the Department requires accurate logs of collections and disposals to allow it to monitor compliance and investigate complaints. An accurate, detailed, and contemporaneously-created log would have allowed the Department to discover what Mr. Beebe's truck had collected and dumped prior to the Brandy Lane dumping incident and would have allowed the Department to reconcile the amounts of septage collected by Mr. Beebe from January 2004 through February 2005, with the amounts of septage Mr. Beebe properly disposed of during the same period. The Department established, by clear and convincing evidence, that Mr. Beebe did not maintain a septage collection and hauling log as required by Florida Administrative Code Rule 64E-6.010(7)(e). Improper disposal of septage The terms of Mr. Beebe's septage disposal service permit required him to dispose of his collected septage at the NCWRF. Dale Waller, the plant manager of the NCWRF, testified as to the procedures followed by sewage haulers at the facility. Mr. Waller testified that the facility has a computer capable of generating reports as to the quantity of disposals made by haulers, but that the computer system often does not operate correctly. Therefore, the facility's chief means of monitoring disposals is the "Septic Receiving Logs" discussed above. The Septic Receiving Log requires the hauler to record the date of disposal, whether the disposal consisted of septage or grease, the amount of disposed material in gallons, and the driver's signature and printed name. The number of gallons disposed is shown on a calibrated gauge when the waste is pumped out of the truck. Mr. Waller testified that this gauge is accurate within five per cent of the actual amount pumped. The county sends invoices each month to the hauler, based on the number of gallons and the type of waste disposed of at the facility. The Septic Receiving Log is maintained in the foyer of the NCWRF building, with a monthly sheet for each hauling company that uses the facility. No NCWRF employee monitors the haulers as they make their log entries. Mr. Waller testified that it is essentially an honor system for the haulers. Due to computer problems, the NCWRF had no computer records of disposals for the month of January 2005. The Septic Receiving Log for Southern Sanitation for that month showed six entries totaling 11,908 gallons of septage and grease, plus two early January 2005 entries of 3,450 gallons that were placed on the December 2004 log, for a total of 15,358 gallons. Mr. Waller testified that in March 2005, Mr. Beebe submitted a revised Septic Receiving Log for Southern Sanitation for the month of January 2005. Mr. Beebe also provided this revised log to the Department as part of his March 8, 2005, supplemental information for the month of January 2005. This revised log listed three additional disposals of septage in the month of January 2005: 2,550 gallons on January 17; 2,000 gallons on January 24; and 1,700 gallons on January 28. These additional 6,250 gallons brought the reported total disposals of septage and grease for January 2005 to 21,608 gallons. The NCWRF declined to accept the revised Septic Receiving Log as an official record of Southern Sanitation's disposals at the facility for the month of January 2005, because the NCWRF could not verify the additional disposals. Mr. Beebe was billed only for those disposals documented on the original Septic Receiving Log kept at the facility. As part of the March 8, 2005, submission of supplemental information, Mr. Beebe provided to the Department a "pump job list" for January 1 through 28, 2005. This list indicated that Southern Sanitation collected between 21,000 and 22,600 gallons of wastewater during the period specified, a number that roughly corresponds to the total number of gallons reported by Mr. Beebe in his revised Septic Receiving Log for the month of January 2005. At the hearing, the Department contended that because Mr. Beebe reported collecting between 21,000 and 22,600 gallons of waste, but could only verify the proper disposal of 15,358 gallons of waste, Mr. Beebe must have improperly disposed of at least 5,600 gallons and as much as 7,200 gallons of waste. In a similar fashion, the Department examined the amounts that Mr. Beebe reported pumping from Mr. Ehlen's holding tank, compared those amounts to the Ehlen household's water usage for the month of January 2005, and concluded that Mr. Beebe further underreported the amount of waste collected that month and, therefore, must have improperly disposed of even more than 5,600 to 7,200 gallons of waste. Mr. Beebe was forthright regarding the issues in these cases, even when his testimony was against his own interests. In light of his overall credibility, Mr. Beebe's denial that he made any improper disposals of waste is credited. No evidence was presented to show that Mr. Beebe actually made these improper disposals. The Department's contention was a surmise derived from discrepancies in Mr. Beebe's reports of collections and disposals. Based on all the evidence, the undersigned finds that the discrepancies in the reports were more likely due to Mr. Beebe's poor record-keeping and his after-the-fact efforts to create records complying with Florida Administrative Code Rule 64E-6.010(7)(e), rather than any illegal dumping of waste. The Department failed to establish by clear and convincing evidence that Mr. Beebe improperly disposed of septage during the month of January 2005.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that Petitioner, the Department of Health, enter a final order imposing a $1000.00 fine for the violations described above, relating to DOAH Case No. 04-4333, and imposing a fine of $1,500.00 and a 90-day suspension of Respondent's septage disposal operating permit for the violations described above, relating to DOAH Case No. 05-0695. DONE AND ENTERED this 7th day of July, 2005, in Tallahassee, Leon County, Florida. S LAWRENCE P. STEVENSON Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 7th day of July, 2005. COPIES FURNISHED: Michael F. Kayusa, Esquire Post Office Box 6096 Fort Myers, Florida 33911 Susan Mastin Scott, Esquire Department of Health 2295 Victoria Avenue, Room 206 Fort Myers, Florida 33901 R.S. Power, Agency Clerk Department of Health 4052 Bald Cypress Way, Bin A02 Tallahassee, Florida 32399-1701 Timothy M. Cerio, General Counsel Department of Health 4052 Bald Cypress Way, Bin A02 Tallahassee, Florida 32399-1701
Findings Of Fact The Respondent is a certified building contractor, having been issued license number CB C011621 as an individual contractor. The Petitioner is an agency of the State of Florida, having responsibility and authority to license building contractors and to regulate their licensure status and their standards of practice pursuant to Chapter 489, Florida Statutes. Sometime in December, 1979, the Respondent, doing business as Economy Steel Buildings, Inc., entered into a contract with Digital Machine and Tool Company to construct a steel building for that firm. The Respondent subsequently commenced the construction on land owned by Digital Machine and Tool Company and obtained a permit from Seminole County on December 6, 1979, authorizing the installation of a septic tank. On the face of the permit appeared language containing the specification that the "stub-out" or pipe exiting the septic tank be installed 12 inches above the original grade level. The Respondent observed that language on the face of the building permit and knew and understood its import, as his own testimony reveals. The Respondent subsequently subcontracted the installation of the septic tank to a company known as Al's Septic Tanks, which installed the tank and drain field during the early part of February, 1980. On February 10, 1980, an inspector for the Seminole County Health Department, Don Gross, inspected the septic tank installation and informed the subcontractor and the Respondent that it was not in conformance with Section 10D-6.25(2)(e), Florida Administrative Code, in that the subcontractor had not followed the instructions on the face of the building permit (12 inches above grade level), which were designed to satisfy that Administrative Code section. Sometime between February 10, 1980, and the end of April, 1980, the Respondent received a "Notice of Violation" from the Seminole County Health Department regarding the alleged improper installation of the septic tank. The Respondent admitted that sometime soon after installation of the septic tank he became aware that it did not pass the Seminole County Health Department inspection. The Respondent maintained that he made three attempts to contact the Health Department regarding the Notice of Violation during the month of April, 1980, but he introduced no competent, substantial evidence to show what efforts, if any, he made to correct the installation of the septic tank. There were ongoing disputes between Digital Machine and Tool Company, its representative, Galon Lyell, and the Respondent during this period, and on May 21, 1980, the Respondent was told to stay off the premises and perform no further construction on the site. There arose at about this time a civil dispute between the Respondent and Digital Machine and Tool Company which is outside the scope of this proceeding. In any event, the Respondent did not correct the installation of the septic tank and there is no question that the septic tank was not installed with the "stub-out" pipe 12 inches above the original grade level. Digital Machine and Tool Company later obtained a corrected installation of the septic tank so that it would be "stubbed-out 12 inches above original grade" from a different subcontractor, at its own additional expense, in the amount of $855. From the period of December, 1979, through the completion of the building for Digital Machine and Tool Company, the Respondent was performing contracting under the name of Economy Steel Buildings, Inc. The Respondent admitted that he was fully aware, as of November 19, 1979, that he could not properly perform contracting work under the name, Economy Steel Buildings, Inc., without properly qualifying that company. After a Notice of Violation (Respondent's Exhibit 6) was issued by the Construction Industry Licensing Board through Investigator Hunter, the Respondent was aware that contracting under an unqualified company name was improper. After that Notice of Violation, the Respondent made some attempts to separate his personal contracting business from that of his material supply company, Economy Steel Buildings, Inc. The Respondent, however, accepted payment for contracting and materials from his client, Digital Machine and Tool Company, for the subject project in the name of Economy Steel Buildings, Inc. The Respondent also paid Myron Roseland, a subcontractor, from Economy Steel Buildings, Inc.'s account for work attributable to the Digital Machine and Tool project. Finally, Petitioner's Exhibit 5 establishes that the Respondent attempted to discharge personal liability as a contractor, which attached to him through the Digital Machine and Tool Company project and other projects, by declaring bankruptcy pursuant to Chapter 11 of the Federal Bankruptcy Act as Economy Steel Buildings, Inc., since in that petition he listed numerous subcontractors, including Myron Roseland, who performed work on the Digital Machine and Tool Company job, as creditors of that corporation to be discharged. In summary, during the period of December, 1979, through the completion of the building for Digital Machine and Tool Company, the Respondent was performing contracting work as Economy Steel Buildings, Inc. During that time period, Economy Steel Buildings, Inc., was not properly qualified or registered with the Construction Industry Licensing Board by the Respondent, who was the owner and sole stockholder of Economy Steel Buildings, Inc.
Recommendation Having considered the foregoing Findings of Fact and Conclusions of Law, the evidence in the record, the candor and demeanor of the witnesses, and the pleadings and arguments of the parties, it is, therefore, RECOMMENDED: That a Final Order be entered by the Petitioner finding the Respondent guilty of the violations alleged in Counts III and IV of the Amended Administrative Complaint and imposing an administrative fine of $1,000. The administrative fine should be suspended in part, provided the Respondent provides proof within sixty (60) days from the date thereof that he has made restitution to Digital Machine and Tool Company for the $855 it had to expend to obtain correction of the improper septic tank installation, as well as restitution of monies owed to Mr. Myron Roseland attributable to the Digital Machine and Tool Company project, in which event the Respondent's fine should be reduced to $250. DONE AND ENTERED this 10th day of February, 1983, at Tallahassee, Florida. P. MICHAEL RUFF, Hearing Officer Division of Administrative Hearings The Oakland Building 2009 Apalachee Parkway Tallahassee, Florida 32301 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 10th day of February, 1983. COPIES FURNISHED: John O. Williams, Esquire 547 North Monroe Street Suite 204 Tallahassee, Florida 32301 James R. Lavigne, Esquire 1971 Lee Road Winter Park, Florida 32789 James Linnan, Executive Director Construction Industry Licensing Board Department of Professional Regulation Post Office Box 2 Jacksonville, Florida 32202 Fred Roche, Secretary Department of Professional Regulation 130 North Monroe Street Tallahassee, Florida 32301
The Issue Whether Petitioner may be granted a variance from Rule 64E-6.001(4), Florida Administrative Code, pursuant to Section 381.0065(4)(h)1., Florida Statutes.
Findings Of Fact Tony and Alma Moreno are owners of the building and premises located at 8250 Scenic Highway, Pensacola. They own the real property at that location all the way to road frontage right-of-way at Scenic Highway. The building had been in continuous existence in the same location for twenty or more years before Petitioner became connected with it. During that period of time, except for short hiatuses, either the Morenos or their lessees operated it as a licensed bar, most often under the name, "The Lighthouse Tavern." Sewage lines exist in the right-of-way at Scenic Highway, within 400 feet of the premises. The tavern is equipped with a septic tank. There has never been any history of septic problems on the tavern premises. The Lighthouse Tavern has always been a neighborhood bar of limited success. Martin MacAndrews has been putting amusement games in the tavern since 1978. He testified that during those twenty-two years, the average number of patrons has been eight to 14. Jim McDaniel has sold paper products to successive lessees since the 1970's. He has seen an average of 10 patrons during the day and up to 20 patrons at night. Charles Barcia, a more recent patron, has observed a maximum of nine patrons in the tavern. Denise Powell (nee´ Williams) leased the premises from August 7, 1998, until approximately September 28, 1998, during which time she operated the Lighthouse Tavern. She had approximately ten customers per day, used plastic barware, and had no septic problems. During the month or so she operated the tavern, she did not have the septic tank pumped. Ms. Powell's lease with the Morenos was not due to expire until July 31, 1999. However, on or about September 28, 1998, Hurricane Georges damaged the Lighthouse Tavern and wreaked destruction on Pensacola and much of the Florida Panhandle. The area was declared both a state and federal "disaster area." Ms. Powell immediately notified the Morenos, and they cancelled the lease by mutual agreement, because the premises were uninhabitable due to substantial water damage. Ms. Powell testified that but for Hurricane Georges, she would have continuously operated the Lighthouse Tavern under the terms of her lease from the Morenos. As it was, she abandoned the lease and the property. The Morenos made no repairs to the building. No commercial activity, as a tavern or otherwise, occurred on the subject property from September 28, 1998, through May 1, 2000, approximately a year-and-a-half. City water service to the property was terminated from October 12, 1998 until April 7, 2000. On April 5, 2000, Petitioner, a widowed mother, applied to Escambia County for an occupational license to run a tavern at that location. On or about April 7, 2000, Petitioner negotiated a new lease with the Morenos. It involved rate and terms favorable to Petitioner in exchange for her substantial investment (approximately $35,000, as of the date of hearing) in renovating the Lighthouse Tavern. Among other renovations to the property, Petitioner has replaced the tavern's back wall and outside deck, added two pool tables, coolers, two complete bathrooms, a three compartment sink, and a handwash sink. Very few of the fixtures, etc. are removable, let alone subject to resale. A five-year lease, Exhibit P-2, was executed on May 1, 2000. It limits Petitioner's use of the property to use as a tavern, so she cannot get her renovation money back by converting to another business. Paragraph 21 of the lease, purporting to be a lease/purchase option, has not been filled- out, so Petitioner's option to purchase the property is potentially unenforceable. Current Florida Administrative Code rules require septic tanks to have a minimum capacity of 1050 gallons, a filter, and a baffle. A baffle is a device to keep water and waste from going into the drainfields. On May 15, 2000, Ensley Septic Tank Service, operated by Agnes and Joe Nelson, pumped, inspected, and certified the existing septic tank as structurally sound. However, the existing septic tank is twenty years old and provides only 750 gallons. It is not baffled and does not have a filter. Its two drainfields are 75 feet and 69 feet, respectively, from the waterfront, whereas by Escambia County Ordinance, the current setback requirement is 100 feet. On May 25, 2000, the Department denied Petitioner a permit to utilize the existing septic tank, based on the contents of her application, which stated that the tavern occupancy would be 75 seats. Departmental analysis showed that 75 patrons would result in 1,000 gallons per day usage. The existing septic tank does not have that capacity. Before the execution of the lease, Petitioner made no inquiries of Respondent Agency. Likewise, no one told her before the execution of the lease that she would not be able to utilize the existing septic tank or use the premises for a tavern. Rather, Petitioner relied on her own interpretation of an Escambia County Ordinance providing additional time to meet County regulations for reopening a business (or nonconforming use) after closing the business due to Acts of God, and on the fact that Denise Powell's lease, by its terms, did not expire until July 31, 1999. When she was denied a permit to use the existing system, Petitioner applied for a variance for 75 patrons. Petitioner also filed a second application for variance and requested 24 patron occupancy. Petitioner went before the Department's Variance Review Board, which recommended granting the variance with the provisos offered by Petitioner. However, on July 18, 2000, the Department denied the requested variance, stating that the information provided by Petitioner failed to show that no reasonable alternative exists for the treatment of the sewage or that the discharge from the septic tank will not significantly degrade the groundwater or surface waters. The Department offered to permit the tavern to operate either with a connection to the existing sewer system or with a septic tank that meets the current requirements of the Florida Administrative Code. At hearing, Petitioner established that the tavern's water bills from 1996 to 1998 show a use of only 430 to 588 gallons of water per month. This amount reflects the low number of 10-20 patrons per day during that period of time (See Finding of Fact 4), but it also is only approximately three- quarters of the capacity of the existing septic tank. At hearing, Petitioner offered the following cumulative provisos to reduce water flow to the system: limit tavern hours to 11:00 a.m. to 2:00 a.m. (15 hours) daily; use plastic or paper cups; not serve food or mixed drinks; restrict beverages to beer and wine; and limit occupancy to 24 patrons. She offered to pump the existing septic tank more frequently and provide "port-a-potties," as needed. Petitioner anticipates using 24 seats inside, plus picnic tables on the deck. She offered to eliminate the outside seating. The deck constitutes one-quarter of the 900 square feet of the establishment. She will upgrade the septic system as her income from operating the tavern recoups her investment. She will close-up and terminate her lease if she cannot bring the premises "up to Code," that is, to meet the current Florida Administrative Code requirements for septic tanks and/or sewer connections, in one year's time. She has no objection to such provisos being attached to a variance, if one is granted. At hearing, certified septic tank engineers, Agnes Nelson and Joe Nelson, testified that the existing 750-gallon septic tank should handle 24 patrons and the water use would be further limited by using plastic or paper drink containers. In Mr. Nelson's opinion, since he found no salt water from the Bay or water table inversion in the tank when he inspected it, and since the drainfield slopes away from the building, the only way salt water would enter the existing septic tank is if it got above ground. Agnes Nelson conceded that high tide could fill the tank up. If, for any reason, the drainfields were not working, then the current septic tank would not work. However, because the building is between the beach and the drainfields; because, in her opinion, 24 patrons probably could not fit inside the building; and because there was so little solid waste in the tank when it was pumped, Ms. Nelson doubted that the tide and the drainfields would create a problem, even in ordinary rainy weather. Unfortunately, in rendering her opinion, Ms. Nelson did not consider the seating capacity of the tavern's deck or the effect on the surface waters of Escambia Bay of operating the tavern with the existing system. As of the date of hearing, the Morenos were in agreement with all of Petitioner's efforts to obtain a variance. They also will allow her to bring the premises "up to Code," if she can. The Department's current opposition to granting a variance with the provisos offered by Petitioner is based in part on immaterial disputes between the parties over who signed the original application for variance and who filled in the number of seats as 75. The Department also is mistrustful of Petitioner because her second variance application stated the building constituted 1,200 square feet. Because the Department and Petitioner now agree that the premises comprise 900 square feet, the error in the second application is also irrelevant. The Department's current opposition to granting the variance with the foregoing provisos volunteered by Petitioner is at least in part due to the on-site audit, wherein Departmental staff determined that the premises, including the outside deck, actually could accommodate 60-75 living, but not necessarily seated, patrons. The Department sees this as an impediment to occupancy being limited to 24 patrons, in practice. Human nature is such that if a bar has a large, outside deck in a tropical climate, it will probably have more patrons then those sitting in the 24 "seats" provided. While this concern might be speculative in other realms, in dealing with possible contaminants to groundwater or to the surface waters of Escambia Bay, it is a legitimate, if uncodified, concern. Joseph Scott Hale, Environmental Health Supervisor I, made the following suggestions which do not require a variance. Petitioner could connect her premises to the existing sewer at the 75-person occupancy limit; or could install a septic tank or tanks and drainfield(s) in accordance with Departmental rules for a 47-person occupancy limit; or could install a much more modest tank and drainfield system for a 24-person occupancy limit. Petitioner has received written bids to accomplish such alternatives in the following ranges. (1) Installation of the necessary plumbing and pumps to connect to an accessible sewer line is available at a cost of $27,628 to $28,450, although these costs could be inflated to more than $40,000 by adding a grinder station and by charges from CSX railroad for access across its right-of-way to the existing sewer lines; and (2) Installation of one or more septic tanks and drainfield systems in accordance with current rules and in a size for an occupancy capacity of 47 is available for a price ranging from $28,032 to $29,465. Neither of these options is currently feasible for Petitioner, because she has spent her savings on the completed renovations and has only $1,000 +/-, on deposit at this time. She has no current income. Without a contract to purchase the tavern property, she does not believe she can obtain financing. She is not eligible for an upgrade grant from the State because the tavern is commercial property. Petitioner feels that it would be necessary for her to run the tavern at a profit for a year at a minimum capacity of 24 seats in order to be able to pay for either of the foregoing possibilities. She cannot get an alcoholic beverage license without the variance. Petitioner is satisfied that if she cannot make a go of the tavern within one year, she can rescind the lease. The Morenos were silent on this issue. It is not necessary to interpret the lease on this score in order to resolve this case. Respondent construes part of Mr. and Mrs. Nelson's testimony as providing a third, cost-effective, and reasonable alternative for Petitioner in the form of a septic tank and drainfield which could be installed according to current Code with an occupancy capacity of 24 patrons at an approximate cost of $3,600 to $4,000. This oral estimate was testified to by Mrs. Nelson, who, although a certified septic tank inspector, does not actually do installing of septic tanks. She conceded that dollar figure was purely a guess and based on one elevated tank of 1050 gallons with a baffle. Mr. Nelson, who does the actual installing, estimated that more than one tank, a mount system, and a pump or two might be necessary, at additional cost. His thinking is in line with the components of the other written estimates Petitioner has received. Accordingly, it is found that the estimate that Ensley Septic Tank Service can bring the existing system up to Code at a cost of $3,600 to $4,000 to Petitioner is speculative and not a reasonable alternative. As is common, expert opinions were mixed on the danger, if any, to the groundwater and surface waters which would be occasioned by Petitioner operating the tavern under her foregoing proposed provisos without upgrading the current septic system. Petitioner's expert in civil engineering and degradation of groundwater did soil borings on the premises and hit no groundwater at 15 inches, even after two weeks of significant rain. However, his experience with soil analysis from "mottling" was limited, and accordingly, his opinion that water in the ground will never or rarely rise above 15 inches, so as to endanger groundwater or surface waters was not persuasive. Instead, I accept the greater weight of the evidence as a whole in order to make the following findings of fact. The top of the drainfields are located 12 to 22 inches below grade and occupy a one foot area, 24-34 inches below grade. The seasonal high water table is 15 inches below grade. The drainfields operate within the groundwater table. Current rules require drainfields to have a separation from the bottom of the drainfield to the top of the seasonal high water table so as to provide space for aerobic biological action. When a drainfield operates within the water table, no opportunity exists for aerobic biological action. Anaerobic biological action is not effective in killing viruses and other pathogens. Viruses can travel in soil from a drainfield to surface water at a rate of 100 feet in eight hours. Mr. Hale, (see Finding of Fact 30), who was accepted as an expert in groundwater table determination, has an impressive list of credentials, and among other qualifications, is State-certified in OSTDSs. He has personally witnessed water rising to the level of the leechfield in this location. Mr. Hale also took borings, but not in the leechfield. Even though standing water was not found until 32 inches below grade, the soil was saturated at 15 inches, which is the seasonal high water table and mean high water mark of Escambia Bay at Petitioner's waterfront. The usual groundwater high water table in this location is 24 inches below natural grade, and the temporary water table rises and falls, as affected by Escambia Bay tides and by rainfall. Another concern is that the leechfields average only 15 inches below grade, and soil "capillary action" or water "wicking" through the soil can result in contamination of the groundwater if they become saturated. The close proximity of the property to Escambia Bay presents the potential for pollution of surface waters. Mr. Hale reported that the tavern location is not subject to frequent flooding. However, it can, and probably will, flood, as before, during a hurricane. Mr. Hale testified further that but for the length of the cessation of business as a result of the hurricane (more than one year), the tavern could have continued to operate with eight seats and no danger to the groundwater. In his opinion, the existing system, unaltered, can handle waste disposal for only eight patrons. A 47-seat occupancy is the maximum allowable for a 1,000 gallon flow. Even though 24 seats would not be expected to exceed 1,000 gallons a day, 24 seats would not be accommodated by the existing system's 750 gallon tank, drainfields, leechfields, and insufficient set back footage. Mr. Hale reluctantly conceded that 22 seats might be "feasible," with all proposed provisos in place, plus the substitution of low flow toilets, but that solution would not be his best recommendation nor acceptable to the Department. According to Dr. Malcomb Shields, who was accepted as an expert microbiologist in the field of migration of pollutants from drainfields to surface waters, Escambia Bay is already above its threshold in dangerous nutrients. Dr. Shields further opined, with impressive scientific detail, that narrowing the zone in the drainfield, as on the Lighthouse Tavern property, makes the drainfields susceptible to more pathogens. In his opinion, the offered provisos would have absolutely no effect on the existing septic tank and system efficiency except to limit water and waste into the septic tank itself. Dr. Shields conceded that a variance granted upon the terms requested would not, by itself, cause significant degradation of water quality. However, he felt that perpetual use of the variance, even with the foregoing provisos, would, combined with all other factors present, contribute to surface water degradation, which is the test under the rule. Dr. Shields did not feel that a variance absolutely limited to one year's duration would have the same effect.
Recommendation Based upon the findings of fact and conclusions of law, it is RECOMMENDED: That the Department of Health enter a final order which: Permits Petitioner to operate her tavern either with a connection to the existing sewer system or with installation of a septic tank and drainfield system in accordance with the current Florida Administrative Code rules for an occupancy capacity of 24 patrons; and alternatively Grants Petitioner a 12-month variance to utilize the existing tank and drainfield system upon the following terms: Petitioner shall obtain and maintain an annual OSTDS operating permit allowing inspection at will by the Department; Petitioner shall maintain an annual contract with a licensed septic tank contractor to inspect and service the existing OSTDS at least once per month, or more frequently as necessary; Upon notification by the septic tank contractor of any problem with the OSTDS, Petitioner shall provide port-a- potties sufficient for 22 patrons; During the 12 months the variance is in place, Petitioner shall provide a port-a-potty on any occasion of rain over eight hours' duration. Petitioner shall not open for business until low- flow toilets are substituted; Petitioner shall operate the premises as a tavern for no more than 12 months, during which 12 months Petitioner shall take all necessary steps to bring the system up to Code or to connect to the sewer line; During the 12 months the variance is in place, Petitioner shall limit hours of operation to 15 hours daily; eliminate all deck seating; provide no more than 22 seats inside; use only paper or plastic ware; serve no food or mixed drinks; and actively limit occupancy to 22 patrons at any one time; and At the end of the 12 months, the system shall be in compliance or the tavern shall be closed and remain closed until compliance is achieved. DONE AND ENTERED this 12th day of February, 2001, in Tallahassee, Leon County, Florida. ELLA JANE P. DAVIS Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 www.doah.state.fl.us Filed with the Clerk of the Division of Administrative Hearings this 12th day of February, 2001. COPIES FURNISHED: Steven E. Melei, Esquire 3603 Mobile Highway Pensacola, Florida 32505 Rodney Johnson, Esquire Department of Health 1295 West Fairfield Drive Pensacola, Florida 32501 Theodore M. Henderson, Esquire Agency Clerk Department of Health 4052 Bald Cypress Way, Bin A02 Tallahassee, Florida 32399-1701 Dr. Robert G. Brooks, Secretary Department of Health 4052 Bald Cypress Way, Bin A00 Tallahassee, Florida 32399-1701
Findings Of Fact At all times material to this proceeding, Sandra B. Frazier was a licensed real estate broker-salesman in the State of Florida, License No. 0185565, as an associate with Property Associates, Inc., Tallahassee, Florida. On July 1, 1989, Howard M. Burkholz, Leslie Burkholz, and Jacob H. Schiff entered into an Exclusive Right of Sale Agreement with Property Associates, through its agent, Frazier, for the sale of a house located in Forest Green Subdivision, at 2062 Pepperidge Way, Tallahassee, Florida. The Exclusive Right of Sale Agreement states in part: Seller further certifies and represents that the property has no latent defects except the following: septic tank is pumped monthly at Sellers request. [sic] Mr. and Mrs. Burkholz both told Frazier that the septic tank was not a problem, but Frazier had previous knowledge of septic tank problems in the vicinity and of the significance of needing septic tank pumping. Frazier sold the house across from the Burkholz's house. That house, at 2061 Pepperidge Way, was bought by Marcie Doolittle in December of 1988. The listing information and Notice to Prospective Buyers showed that, due to the composition of the soil and heavy rains, it was necessary to have the septic tank pumped. The seller offered an offset to the buyer for the cost of additional drainfield. Only after Doolittle bought the house did Frazier learn of the severity of the problems and the necessity for pump outs every two weeks. In a letter written by Frazier to Doolittle on February 9, 1989, Frazier indicated that "once a septic tank fails it does not correct itself. It then requires regular pumping." Frazier suggested that the only resolution was more drainfield or regular pumping. After Frazier listed the Burkholz house, she mentioned to Mrs. Doolittle that she could not show the Burkholz house during wet weather because the backyard, in which the septic tank and drainfield was located, was too boggy. Further, Frazier discussed with Mrs. Doolittle that the city was going to install sewer in the area because of the septic tank failures. In conformance with the Exclusive Right of Sale agreement with the Burkholzs, Frazier listed the house through the Multiple Listing Service. The data on the house was input on an input sheet. If there are defects, they can be listed on lines RE1-RE4 on the input form. Despite her knowledge about the Burkholz's septic tank and the Doolittle's septic tank, Frazier did not list this as a defect. Mary Wheatley, a sales associate with Bob Wolfe Real Estate, worked with Jesse and Susan Day to locate a house to purchase. She showed the Days the Burkholz house. Her only knowledge of that house came from the MLS listing, the brochure entitled Highlights of this Home prepared by Frazier, and from information verbally given by Frazier. Wheatley had no knowledge of the septic tank problems and Frazier did not tell her anything about the septic tank or the potential hook up to city sewer. After various offers and counteroffers, the Days and the Burkholtzs signed a contract for the sale and purchase of the house on November 24, 1989. The Contract states in paragraph 14: CONDITION OF PROPERTY: BUYER ACKNOWLEDGES THAT HE HAS NOT RELIED UPON ANY REPRESENTA- TIONS MADE BY A REALTOR(S) AS TO THE CONDI- TION OF THE PREMISES. . . .SELLER warrants that the . . . septic tank . . . shall be in working order on the date of closing. SELLER agrees to repair any of the preceding items not in working order. BUYER agrees to inspect the property prior to closing to determine condition of said items; . . . If BUYER fails to make inspections as required, BUYER agrees to accept property in "as is" condition. BUYER and SELLER will diligently learn and disclose to each other prior to closing all facts affecting the value of the property. On December 26, 1989, the night before the closing, the Days, the Burkholzs, Frazier, and Wheatley did the final walk through. While Wheatley and Susan Day were in another room measuring for curtains, Mr. Day flushed a toilet and noted that it went down very slowly. He asked if there were septic tank problems. Mr. Burkholz indicated that there were, but that sewer hookup was coming and the septic tank was pumped out monthly by the city at no cost. Mr. Day asked about the costs and was told that the pumpouts were free and the sewer would cost several hundred dollars. There is a clear conflict in the testimony of the various witnesses about the sewer cost estimate given to Mr. Day, but the exact figure is of no consequence to the ultimate outcome of the case. Therefore the conflict is not resolved. The Days discussed the septic tank and sewer hookup and decided to go through with the closing. After the walk through, they signed an inspection sheet in which they accepted the premises as inspected, without any noted exceptions, and they relieved the sellers and the realtor from further warranty or responsibility for the condition of the property. According to Thomas Bryant, an engineer with the City of Tallahassee, in December, 1989, no one knew whether there would be sewer installed in Forest Green or the potential cost of sewer hookup. No one knew that even on the date of hearing. The city did enter into an agreement to charge $650 for sewer hookup in Forest Green, but there are additional charges and costs to the homeowner which are as yet undetermined. The septic tank problems constitute a latent defect which should have been disclosed to the buyers before a contract was agreed upon. The failure to disclose is not egregious since the regular pumping of the septic tank is done at no cost to the homeowner and results in no liability to the homeowner. The projected sewer hook up was too uncertain to have required such disclosure.
Recommendation Based upon the foregoing Findings of Fact and Conclusions of Law, it is recommended that the Florida Real Estate Commission enter a Final Order and therein: Find Sandra B. Frazier guilty of one Count of concealment in violation of Section 475.25(1)(b), Florida Statutes. Based on the mitigating factors set forth above and on the relatively minor nature of the offense, impose a fine of $100.00 on Sandra B. Frazier. Issue a written reprimand to Sandra B. Frazier. RECOMMENDED this 27th day of March, 1991, in Tallahassee, Florida. DIANE K. KIESLING Hearing Officer Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, FL 32399-1550 (904) 488-9675 Filed with the Clerk of the Division of Administrative Hearings this 27th day of March, 1991. APPENDIX TO THE RECOMMENDED ORDER, CASE NO. 90-6189 The following constitutes my specific rulings pursuant to Section 120.59(2), Florida Statutes, on the proposed findings of fact submitted in this case. Specific Rulings on Proposed Findings of Fact Submitted by Respondent, Sandra B. Frazier Each of the following proposed findings of fact is adopted in substance as modified in the Recommended Order. The number in parentheses is the Finding of Fact which so adopts the proposed finding of fact: 1(1). Proposed findings of fact 2-9 are subordinate to the facts actually found in this Recommended Order. COPIES FURNISHED: Janine B. Myrick Senior Attorney Department of Professional Regulation Division of Real Estate 400 West Robinson Street Post Office Box 1900 Orlando, FL 32801-1772 William J. Haley Attorney at Law Post Office Box 1029 Lake City, FL 32056-1029 Jack McRay, General Counsel Department of Professional Regulation 1940 North Monroe Street Tallahassee, FL 32399-0792 Darlene F. Keller Division of Real Estate 400 West Robinson Street Post Office Box 1900 Orlando, FL 32801
The Issue The issue is whether Respondent should have an administrative fine imposed for allegedly providing septic tank contracting services without a license.
Findings Of Fact Based upon all of the evidence, the following findings of fact are determined: When the events herein occurred, Respondent, Herman Campbell, operated a back-hoe service in Santa Rosa County, Florida. He presently holds no licenses with, or registrations from, Petitioner, Department of Health (Department), to engage in the septic tank contracting business. In April 1997, Wayne Sullivan, who resides in Navarre, Florida, made arrangements with a local contractor, Robert Hoover, to dig up the drainfield and replace the pipe on a septic tank system at his mother-in-law's home at 8207 Laredo Street, Navarre. Hoover purchased the necessary pipe but then backed out of the job at the last minute. Sullivan then called Mary Esther Plumbing, who recommended that Respondent be used. Respondent was a former licensed septic tank contractor who had installed the original septic tank at the residence more than ten years earlier. Sullivan agreed to purchase all materials (pipe and gravel) needed for the job. Although Sullivan claims that Respondent told him he was licensed to do the work, it is found that Respondent indicated to Sullivan that he held no license or registration and could not obtain any permits. Notwithstanding Respondent's lack of licensure, Sullivan nonetheless asked Respondent to perform the work. Respondent undertook the job on or about Thursday, April 24, 1997. Charging a rate of $45.00 per hour to operate his back-hoe, Respondent replaced the pipe in the drainfield. In addition, he dug up a number of stumps in the front yard. The total charge for all work, including the stump removals, was $1,375.00, which was paid by check from the mother-in-law. The amount related to the septic tank work is not known. The following Monday, the Department received an anonymous complaint that an unlicensed person had performed septic tank contracting services for Sullivan's mother-in-law. After an investigation was conducted by a Department environmental specialist, an administrative complaint was issued. Respondent did not register with the Department before performing the work, and he did not obtain the required permit from, and inspection by, the Department. By failing to do so, Respondent acted in contravention of Department rules. Although the complaint alleges that Respondent caused monetary harm to the customer, there is no evidence that Sullivan's mother-in-law suffered any damages by virtue of Respondent's work. Indeed, at hearing, Sullivan indicated that he was pleased with Respondent's workmanship. While the Department suggests that the mother-in-law has been left with an "unauthorized drainfield," there is no evidence that this caused her to incur additional expense. Respondent contended that he was merely "digging a ditch" with his back-hoe and was not providing septic tank contracting services. However, the evidence shows that he dug the ditch, removed the old pipe, placed gravel in the bed, and laid the new pipe into the ditch, all of which relate to septic tank contracting services. While Sullivan may have assisted Respondent in performing these tasks, it does not relieve Respondent of the responsibility of complying with Department rules. Respondent also contended that he was being singled out for enforcement purposes because he is black. There was no evidence, however, to support this contention. In mitigation, Respondent believed he was working with Sullivan, as the owner of the property, in jointly performing the work, and there was no intent on his part to evade the licensing requirements. In addition, there was no danger to the public, and the customer's property was not damaged. Although the Department contends that Respondent has installed many septic tanks and drain fields "without a permit," there is no evidence in the record of specific jobs performed illegally by Respondent. Finally, the $2,000.00 administrative fine suggested by the Department would appear to have an adverse impact on Respondent's livelihood.
Recommendation Based on the foregoing Findings of Fact and Conclusions of Law, it is RECOMMENDED that the Department of Health enter a Final Order finding Respondent guilty of violating Rules 64E-6.022(1)(a) and (b), Florida Administrative Code, and that Respondent be issued a letter of warning as to the first violation and that an administrative fine in the amount of $250.00 be imposed for the second violation. The allegation that Respondent violated a third rule should be dismissed. DONE AND ENTERED this 6th day of January, 1998, in Tallahassee, Leon County, Florida. DONALD R. ALEXANDER Administrative Law Judge Division of Administrative Hearings The DeSoto Building 1230 Apalachee Parkway Tallahassee, Florida 32399-3060 (850) 488-9675 SUNCOM 278-9675 Fax Filing (850) 921-6847 Filed with the Clerk of the Division of Administrative Hearings this 6th day of January, 1998. COPIES FURNISHED: Angela T. Hall, Agency Clerk Department of Health Building 6, Room 102 1317 Winewood Boulevard Tallahassee, Florida 32399-0700 Rodney M. Johnson, Esquire 1295 West Fairfield Drive Pensacola, Florida 32501 Herman Campbell 621 Oak Lane Fort Walton Beach, Florida 32548 Willie Harmon Post Office Box 733 Fort Walton Beach, Florida 32548 Pete Peterson, Esquire Department of Health Building 6, Room 102 1317 Winewood Boulevard Tallahassee, Florida 32399-0700